﻿
Volume 2 1975 Annual Report 
.,':\ ,:~r aw) c:< -x. 
w " 
.< P. Nh " 
S A'L\ ' \,\f I \ 
'I - ' "IS. -_( 
" " \ __ ' 
Ar ,

\* NA p IK 
-A\ . -\ >\ , c -A 
\-'A\ 
\ 
' 
. S 
e. - " S > 
1 - . 
II 
f 
A / 
A " 
! a' \:

CONTENTS 
\'ii Page 
NEW ENGLAND DIVISION ..................................................................................... 1-1 
NORTH ATLANTIC DIVISION: 
New Y ork, N. Y., District .......................................... .............................................................................................. .. 2-1 
Philadelphia, Pa., District .......................................... .............................................................................................. . 3-1 
Baltimo re, M d., District .............................................. .............................................................................................. . 4-1 
No rfolk, V a., District .........................................................................5.-.1.................................................................................... 
SOUTH ATLANTIC DIVISION: 
W ilm ington, N. C. District .......................................... .............................................................................................. . 6-1 
Charleston, S. C., District ............ ...................................................... .................7..-1..... ................................................... 
Savannah, Ga., District .......................................................................8.-.1.................................................................................. 
Jacksonville, Fla., District .....................................................................9.-.1............................................................................... 
M obile, Ala., District ........................................................................1.0.-.1.................................................................................... 
LOWER MISSISSIPPI VALLEY DIVISION: 
New Orleans, La., District .....................................................................1.1-.1................................................................................ 
V icksburg, M iss., District ................................................... 12-1 
M emp his, Tenn., District ......................................................................1.3-.1.............................................................................. 
St. Louis, M o., District ................................................. 14-1 
SOUTHWESTERN DIVISION: 
G alveston, Tex., District ......................................................................1.5.-1.................................................................................. 
Fort W orth, Tex., District .................................................. 16-1 
Albuquerque, N. M ex., District .................................................................1.7.-.1........................................................................... 
Little Rock, A rk., District .....................................................................1.8-.1............................................................................... 
Tulsa, Okla., District .........................................................................1.9-.1..................................................................................... 
MISSOURI RIVER DIVISION: 
K ansas City, M o., District ....................................................................2.0.-1................................................................................ 
Om aha, Ne br., District .......................................................................2.1.-.1................................................................................... 
OHIO RIVER DIVISION: 
Ohio River .................................................................................2.2.-1............................................................................................... 
N ashville, Tenn., District .....................................................................2.3.-1................................................................................ 
Louisville, K y., District ............................................ .............................................................................................. . 24-1 
Huntington, W. Va., District ................................................................................................... ............ .... 25-1 
Pittsburgh, Pa., District ......................................................................2.6.-1.................................................................................. 
NORTH CENTRAL DIVISION: 
St. Paul, M inn., District ................................................................. .............2..7..-1...... ............................................................ 
Rock Island, hi., District .......................................... .............................................................................................. . 28-1 
Mississippi River between Missouri River and Minneapolis, Minn ........................... ............. 29-1 
Chicago, Ill., District .........................................................................3.0-.1..................................................................................... 
Detroit, M ich., District ......................................... ................................................................................................ .. 31-1 
Buffalo, N. Y., District ............................................ ........................................................................................... .......3.2-.1... 
SOUTH PACIFIC DIVISION: 
Los An geles, Calif., D istrict ...................................................................3.3.-.1.............................................................................. 
San Francisco, Calif., District ................................................... ........................................................................... 34-1 
Sacram ento, Calif., District .............................. .................................................................................................. ...3.5.-1... 
PA CIFIC OCEAN D IV ISIO N ....................................................................3.6.-1................................................................................ 
NORTH PACIFIC DIVISION: 
Portland, Oreg., District ......................................................................3.7.-1.................................................................................. 
Seattle, W ash., District ......................................... .............. ........................................................... .... . ... 38-1 
Walla Walla, Wash., District ...................................................................39.-.1....................................................................... 
Alaska District ......................................................................40.-.1........................................................................... 
Board of Engineers for Rivers and H arbors ..................................................4.1-.1................................................................... 
M ississippi River Com mi ssion ............................................................4.2-.1................................................................................ 
Coastal Engineering Research Center 4-.......................................California Debris Commission ............................................................4.4-.1................................................................................ 
Waterways Experiment Station ...........................................................45.-.1.............................................................................. 
Permanent International Association of Navigation Congress .....................................4.6.-1.................................................... 
Investigations and Supervision of Projects Under Federal Water Power Act ...........................4.7.-1.................................... 
M iscellaneous Civil W orks ..............................................................4.8.-1.................................................................................... 
Index ..............................................................................I.-.1............................................................................................................... 
iii

DIVISIONS AND DISTRICTS FOR CIVIL WORKS ACTIVITIES 
DIVISION BOUNDARIES 
--- DISTRICT BOUNDARIES 
DIVISION HEADQUARTERS 
" DIVISION HEADQUARTERS 
A DIVISION AND DISTRICT 
HEADQUARTERS 
STATUTEM ILES 
100 0 100 200 Mies

NEW ENGLAND DIVISION* 
The New England Division, an operating division 
with both district and division functions, 
comprises all of New England except western 
Vermont and small portions of Massachusetts 
and Connecticut along their western boundaries, 
and includes small portions of southeastern New 
York, all embraced in the drainage basins tributary 
to Long Island Sound and the Atlantic 
Ocean east of the New York-Connecticut State 
line. It also includes Fishers Island, N.Y. 
IMPROVEMENTS 
Navigation 
1. Andrews River, Mass........ 
2. Aquatic Plant Control ........ 
3. Boston Harbor, Mass. -........ 
4. Branford Harbo, Conn...... 
5. Bridgeport Harbor, Conn ...... 
6. Bucks Harbor, Machiasport, Me. 
7. Cape Cod Canal, Mass........ 
8. Clinton Harbor, Conn. ........ 
9. Connecticut River Below 
Hartford, Conn............ . 
10. Cuttyhunk Harbor, Mass ...... 
11. Edgartown Harbor, Mass...... 
12. Fall River Harbor, Mass...... 
13. Frenchboro Harbor, Me...... 
14. Green'Harbor, Mass.......... 
15. Guilford Harbor, Conn....... 
16. Hampton. Harbor, N.H. ....... 
17. Housatonic River, Conn.- ...... 
18. Hyannis Harbor, Mass. ........ 
19. Isle of Shoals Harbor, Me. 
and N.H. .,. . . . . . ... . . . 
20. Kennebec River, Me.......... 
21. Kennebunk River, Me....... . 
22. Lagoon Pond, Tisbury, 
Martha's Vineyard, Mass..... . 
23. Little Harbor, N.H. .......... 
24. New Haven Harbor, Conn .... .. 
25. Newburyport Harbor, Mass. ... 
26. Pawtuxet Cove, R.L.......... 
27. Plymouth Harbor, Mass...... 
28. Providence River and 
Harbor, R.I. ................ 
29. Rockland Harbor, Me. ...... . 
30. Scarboro River, Me.......... 
31. Warwick Cove, R.I............ 
32. Wells Harbor, Me............ 
Page 
1-2 
1-2 
1-3 
1-3 
1-4 
1-4 
1-4 
1-6 
1-6 
1-6 
1-7 
1-7 
1-8 
1-9 
1-9 
1-9 
1-10 
1-10 
1-11 
1-11 
1-12 
1-12 
1-12 
1-13 
1-13 
1-14 
1-14 
1-15 
1-15 
1-16 
1-16 
1-17 
Navigation (cont.) 
33. Weymouth-Fore and Town 
Rivers, Boston Harbor, Mass . .. 
34. Winter Harbor, Me............ 
35. York Harbor, Me............. 
36. Reconnaissance and condition 
surveys ................... 
37. Other authorized navigation 
projects ...................... 
38. Navigation activities pursuant to 
Section 107, Public Law 86-645 
(Preauthorization) ........... 
39. Authorized bridge alteration ... 
Beach Erosion Control 
40. Oak Bluffs Town Beach, Martha's 
Vineyard, Mass.............. 
41. Plum Island, Mass. ............ 
42. Revere Beach, Mass........... 
43. Inspection of completed beach 
erosion control projects ....... 
44. Other authorized beach erosion 
control projects .............. 
45. Beach erosion control activities 
pursuant to Section 103, Public 
Law 87-874 (Preauthorization) 
Flood Control 
46. Blackstone River Basin, 
Mass. and R.I. .............. 
46A. West Hill Dam, Mass. ...... :. . 
46B. Worcester Diversion, Mass. .... 
47. Charles River Dam, Mass. ..... 
48. Charles River (Natural Valley 
Storage Areas), Mass. ......... 
49. Connecticut River Basin, Vt., 
NH., Mass. and Conn... .. . 
*All cost and financial statements and authorizing legislation for projects are listed at the end of this chapter. All 
other tables are referenced in text and also appear at the end of this chapter. 
1-1 
Page 
1-17 
1-18 
1-18 
1-19 
1-19 
1-19 
1-19 
1-19 
1-19 
1-20 
1-20 
1-20 
1-20 
1-20 
1-21 
1-21 
1-21 
1-22 
1-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (cont.) 
49A. Ball Mountain Lake, Vt...... 
49B. Barre Falls Dam, Mass. ....... 
49C. Birch Hill Dam, Mass. ........ 
49D. Charlestown, N.H ............ 
49E. Chicopee Falls, Mass......... . 
49F. Colebrook River Lake, Conn. . . 
49G. Conant Rrook Dam, Mass. ..... 
49H. Knightville Dam, Mass. ....... 
491. Littleville Lake, Mass........ 
49J. North Hartland Lake, Vt. ..... 
49K. North Springfield Lake, Vt .... 
49L. Otter Brook Lake, N.H......... 
49M. Park River, Hartford, Conn. ... 
49N. Sucker Brook Dam, Conn. ..... 
490. Surry Mountain Lake, N.H. .... 
49P. Townshend Lake, Vt. ........ 
49Q. Tully Lake, Mass............ 
49R. Union Village Dam, Vt....... . 
50. Fox Point Barrier, Narragansett 
Bay, R.I ................ .. 
51. Hayward Creek, Quincy- 
Braintree, Mass............... 
52. Housatonic River Basin, Conn. 
52A. Ansonia-Derby, Conn.......... 
52B. Black Rock Lake, Conn........ 
52C. Danbury, Conn. ............. 
52D. Derby, Conn.. ............... 
52E. Hancock Brook Lake, Conn .. . 
52F. Hop Brook Lake, Conn. ...... 
52G. Lee, Mass. ................. 
52H. Northfield Brook Lake, Conn. . . 
521. Thomaston Dam, Conn ....... 
53. Merrimack River Basin, N.H. 
and Mass . .................. 
53A. Blackwater Dam, N.H. ........ 
53B. Edward MacDowell Lake, N.H.. 
Page 
1-23 
1-24 
1-24 
1-24 
1-25 
1-25 
1-26 
1-26 
1-26 
1-27 
1-27 
1-28 
1-28 
1-29 
1-29 
1-29 
1-30 
1-30 
1-30 
1-31 
1-31 
1-31 
1-32 
1-32 
1-33 
1-33 
1-33 
1-34 
1-34 
1-34 
1-35 
1-35 
1-35 
Flood Control (cont.) 
53C. Franklin Falls Dam, N.H ...... 
53D. Hopkinton-Everett Lakes, N.H.. 
53E. Nookagee Lake, Mass....... .. 
53F. Saxonville, Mass. ........ . . 
54. New Bedford, Fairhaven and 
Acushnet, Mass.............. 
55. New London, Conn........... 
56. Saint John River Basin, Me ... . 
56A. Dickey-Lincoln School 
Lakes, Me. ................. 
56B. Fort Kent, Me.............. 
57. Smelt Brook, Weymouth- 
Braintree, Mass............... 
58. Stamford, Conn.............. 
59. Thames River Basin, Conn., R.I. 
and Mass................. 
59A. Buffumville Lake, Mass...... 
59B. East Brimfield Lake, Mass. .... 
59C. Hodges Village Dam, Mass. .... 
59D. Mansfield Hollow Lake, Conn. 
59E. West Thompson Lake, Conn. ... 
59F. Westville Lake, Mass. ......... 
60. Inspection of completed flood 
control projects ............. 
61. Flood control reservoir 
operations ................. 
62. Hurricane barrier operations ... 
63. Other authorized flood control 
projects ................... 
64. Flood control work under special 
authorization ............... 
65. 
66. 
General Investigations 
Surveys ................... 
Collection and Study of Basic 
Data ..................... 
Navigation 
1. ANDREWS RIVER, MASS. 
Location. On Nantucket Sound within town 
of Harwich, Mass., about 84 miles southeast of 
Boston, Mass. (See Coast and Geodetic Survey 
Chart 257.) 
Existing project. Channel 6 feet deep, 75 feet 
wide, extending about 2,900 feet from deep 
water in Nantucket Sound to a public marina, 
two jetties on east and west sides of harbor 
entrance, and a 3-acre maneuvering and anchorage 
basin. Mean tidal range is 3.7 feet, and 
maximum range, due to combined effect of 
wind and other causes, is 6.5 feet. (See. Table 
1-B at end of chapter for Acts authorizing 
existing project. 
Local cooperation. Fully complied with. 
Terminal facilities. None. 
Operations and results during fiscal year. 
Maintenance: Final payment in the amount of 
$3,890 was made for the maintenance dredging 
contract completed in fiscal year 1974. Final 
contract costs for removal of approximately 
22,000 cubic yards of material were $63,018. 
Condition at end of fiscal year. East jetty 
completed in June 1967. Dredging was completed 
in April 1968. Construction of west jetty 
completed in May 1973. 
2. AQUATIC PLANT CONTROL. 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
New England Division. 
Existing project. Provides for control and 
progressive eradication of water-hyacinth, 
1-2 
Page 
1-36 
1-36 
1-37 
1-37 
1-38 
1-38 
1-39 
1-39 
1-40 
1-40 
1-41 
1-41 
1-41 
1-42 
1-42 
1-42 
1-43 
1-43 
1-43 
1-44 
1-44 
1-44 
1-44 
1-45 
1-45

NEW ENGLAND DIVISION 
alligator-weed, Eurasian water milfoil, and other 
obnoxious aquatic plant growths, from the 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and 
wildlife conservation, public health, and related 
purposes, including continued research for development 
of the most effective and economic 
control measures, to be administered by the 
Chief of Engineers, under the direction of the 
Secretary of the Army in cooperation with other 
Federal and State agencies. 
Local cooperation. Local interests must agree 
to hold the United States free from damages 
that may occur from control operations performed 
in connection with this program, and 
participate to the extent of 30 percent of the 
cost of such operations. 
Operations and results during fiscal year. 
Engineering studies for the control of aquatic 
plants in the Lower Mystic Lakes were concluded 
for FY 1975. It was found that the lake 
is culturally eutrophicated, and that any further 
work on this lake was beyond Corps' authority. 
Work on the Upper Mystic Lake is scheduled to 
start in fiscal year 1976. As requests were 
received, assistance was given to State and local 
officials, and to individuals and associations 
under the Aquatic Plant Control Program. 
Condition at end of fiscal year. The Aquatic 
Plant Control Program is presently limited to the 
Upper Mystic Lake with particular attention to 
water quality for recreation activities. 
3. BOSTON HARBOR, MASS. 
Location. Harbor includes all expanse of tidewater 
lying within a line from Point Allerton to 
Point Shirley and extending from that line 
westward to mainland. This comprises an area of 
about 47 square miles, exclusive of the islands. 
(See Coast and Geodetic Survey Charts 246 and 
248.) 
Previous projects. For details see Annual 
Reports for 1915, 1917, 1938. 
Existing project. The existing project for 
Boston Harbor, adopted in 1825 and supplemented 
by enactments through 1958, provides 
for the improvement of the harbor proper and 
its approaches, Fort Point Channel, Reserved 
Channel, Chelsea River and Weir River. For a 
more detailed description see page 3 of Annual 
Report for 1974. (See Table 1-B at end of 
chapter for Acts authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 183 wharves and 
piers in harbor, not including Mystic, Weymouth 
Fore, and Town Rivers, which are reported 
elsewhere. In addition, there are four ferry slips 
and two car floats. Of the terminals, 28 are 
publicly owned, 13 are open to public use, 77 
have mechanical-handling facilities, and 57 have 
railroad connections. Facilities are considered 
adequate for existing commerce. For a full 
description of channel facilities in Chelsea River 
refer to House Document 350, 87th Congress, 
2d session (See Port Series No.. 3, Port of 
Boston, Mass., dated 1956). 
Operations and results during fiscal year. 
Maintenance: Hired labor costs incurred in 
closing out contracts completed in fiscal year 
1974 for removal of rock pinnacle and removal 
of sunken barge. Project condition surveys were 
conducted at a cost of $40,811. 
Condition at end of fiscal year. The existing 
project was completed in May 1966 with the 
construction of Chelsea River 35-foot channel 
and maneuvering basin. That portion of Fort 
Point Channel from northeasterly side of Summer 
Street highway bridge to the easterly side of 
Dorchester Highway Bridge has been abandoned 
pursuant to P.L. 91-624 dated 31 December 
1970. Remaining area of the authorized channel 
from the entrance to the northeasterly side of 
the Summer Street Bridge has not been abandoned. 
(See Table 1-C at end of chapter for total 
Federal cost of existing project to June 1973.) 
4. BRANFORD HARBOR, CONN. 
Location. On north shore of Long Island 
Sound, 5 miles east of New Haven Harbor. (See 
Coast and Geodetic Survey Chart 217.) 
Existing project. A channel 8.5 feet deep and 
100 feet wide from outer harbor to upper wharf 
in Branford Harbor, about 2.3 miles. Mean tidal 
range is 5.9 feet, and maximum range, due to 
combined effect of wind and other causes, is 10 
feet or more. Federal cost of new work for 
completed project was $9,537. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, comprising two 
wharves near head of the harbor and one at 
mouth of river, are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Hired labor costs incurred in 
preparation of contract drawings and specifications 
and an Environmental Impact Statement 
for maintenance dredging of the recreational 
boat channel. The proposed operations consist 
of maintenance dredging of 2.3 miles of channel 
in Branford Harbor and the utilization of the 
dredged material to develop a marsh. Project 
1-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
condition surveys were conducted at a cost of 
$7,544. 
Condition at end of fiscal year. The existing 
project was completed in 1907. 
5. BRIDGEPORT HARBOR, CONN. 
Location. On north shore of Long Island 
Sound, about 51 miles east of New York City. 
(See Coast and Geodetic Survey Chart 220.) 
Previous projects. For details see page 1756 of 
Annual Report for 1915 and page 133 of 
Annual Report for 1938. 
Existing project. The existing project, adopted 
in 1836 and supplemented by enactments 
through 1958, provides for the improvement of 
the harbor proper and its approaches, Black 
Rock Harbor, Johnsons River, Pequonnock 
River Channel, Yellow Mill Pond Channel, and 
Burr and Cedar Creek anchorage. Removal of 
rock in Yellow Mill Pond portion is considered 
inactive. Construction of Black Rock Harbor 
breakwater and the Burr and Cedar Creek 
anchorage are also considered inactive. For a 
more detailed description see page 4 of Annual 
Report for 1968. (See Table 1-B at end of 
chapter for Acts authorizing existing project.) 
Local cooperation. Fully complied with for 
completed portion of project, for Black Rock 
Harbor breakwaters and Burr and Cedar Creek 
anchorage there is no reasonable prospect that 
required cooperation will be forthcoming from 
local interests. For further details, see Annual 
Report for 1968. 
Terminal facilities. There are 35 waterfront 
facilities serving port of Bridgeport, all of which 
are used or in usable condition. Three wharves 
are owned by city of Bridgeport and three 
others may be used by public upon agreement 
with the owners or operators. (See Port and 
Terminal Facilities of Southern New England, 
No. 4, revised in 1952.) Facilities are adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Hired labor costs incurred for 
preparation of plans and specifications for 
maintenance dredging of 18 foot channel in 
Johnson's River and environmental sampling and 
testing of the main 35 foot channel. A project 
condition survey of Pequonnock River was 
conducted at a cost of $10,600. 
Condition at end of fiscal year. Existing 
project is complete except for inactive portion. 
6. BUCKS HARBOR, ME. 
Location. On the west side of Machias Bay, 
about eight miles south of Machias, Me. and 90 
miles east of Bangor, Me. (See Coast and 
Geodetic Survey Chart 304.) 
Existing project. Eleven acres of anchorage, 
eight feet deep, extending from the southerly 
side of Bucks Neck about 1,450 feet along the 
westerly side of the harbor, southeasterly 
toward Bucks Head. Cost for new work was 
$278,000. (See Table 1-B at end of chapter for 
Act authorizing existing project.) 
Local cooperation. Local interests are required 
to provide, maintain and operate without cost to 
the United States, a public landing with adequate 
parking area and supply facilities open to 
all on equal terms; provide and maintain access 
channels to and berthing areas at all wharves 
adjacent to the proposed anchorage, with depths 
commensurate with those in the anchorage; hold 
and save the United States free from all damages 
which may result from the construction and 
subsequent maintenance of the project; provide 
without cost to the United States all lands, 
easements and rights-of-way required for construction 
and subsequent maintenance of the 
project; regulate the use, growth and free development 
of the harbor facilities with the understanding 
that they will be open to all on equal 
terms; establish regulations prohibiting discharge 
of untreated sewage, garbage and other pollutants 
in the waters of the harbor by users 
thereof, which regulations shall be in accordance 
with applicable laws or regulations of Federal, 
State and local authorities responsible for pollution 
prevention and control. 
Terminal facilities. Consist of five timber 
wharves, one of which is a town wharf. Three 
wharves are located in the inner harbor and are 
accessible only during high tide. Two are in the 
outer harbor and have depths of four to six feet. 
Operations and results during fiscal year. New 
work: Contract for improvement dredging to 
provide eleven acres of anchorage awarded on 23 
April 1974 was completed in July 1974. A total 
of 65,000 cubic yards of material was removed 
at a cost of $210,950. 
Condition at end of fiscal year. Project is 
complete. 
7. CAPE COD CANAL, MASS. 
Location. This waterway is a sea level canal; 
extending from head of Buzzards Bay, Mass., to 
a point on Cape Cod Bay about 15 miles 
southeast of Plymouth Harbor, Mass. In general 
direction canal trends from Buzzards Bay easterly 
to Cape Cod Bay. (See Coast and Geodetic 
Charts 251 and 1208.) 
Existing project. Purchase of Cape Cod Canal, 
(March 31, 1928), including a 600-foot stone 
jetty and a 3,000-foot stone breakwater at east 
1-4

NEW ENGLAND DIVISION 
end of canal at a cost to United States of 
$11,500,000: for an open canal 32 feet deep at 
mean low water, with widths of 540 feet in land 
cut, 500 feet in a straight channel in Buzzards 
Bay to Wings Neck, and 700 feet beyond Wings 
Neck, mooring basins consisting of a basin on 
south side of Hog Island channel 4,000 feet 
long, with widths varying from 0 to 400 feet, 32 
feet deep at mean low water, and a basin at 
Sandwich 3,260 feet long, with widths varying 
from 0 to 385 feet, and 25 feet deep at mean 
low water; construction of two fixed highway 
bridges with horizontal clearance of 500 feet, 
and a vertical clearance of 135 feet at mean high 
water; construction of a vertical lift railroad 
bridge with a 500-foot span and 135-foot 
clearance above mean high water when span is 
raised; an improved lighting system; other accessory 
and minor features which may be deemed 
necessary and to be in accordance with plans 
approved by Chief of Engineers, which include a 
dike extending southwesterly 10,700 feet from 
Stony Point, a dike between Hog and Mashnee 
Islands, a dike between Hog Island and Rocky 
Point, a small East Boat Basin, 13 feet deep at 
mean low water on south bank of canal, an 
extension to the East Boat Basin covering an 
area of about 4.3 acres, to 8 feet deep, and a 
small West Boat Basin 18 feet deep at mean low 
water on north bank of canal; a harbor of refuge 
for small vessels by dredging a channel 150 feet 
wide and 15 feet deep at mean low water into 
Onset Bay and to town wharf in village of Onset; 
for enlargement of 15-foot turning basin at town 
wharf and for an anchorage basin of about 16 
acres, 8 feet deep below mean low water, 
located contiguous to 15-foot channel and 
turning basin. 
Land cut is 7.7 miles long, and with approach 
channels, total length of canal is 17.5 miles. 
Mean range of tide in Cape Cod Bay at Cape Cod 
Canal entrance is 9.4 feet and in Buzzards Bay 4 
feet at Cape Cod Canal entrance. Mean range of 
spring tides is about 13 feet in Cape Cod Bay, 
and 6.5 feet in Buzzards Bay. (See Table 1-B at 
end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Fully complied with. Local 
interests must also bear 50 percent of future 
recreational development in accordance with 
1965 Federal Water Project Recreation Act. 
Terminal facilities. There are four terminals on 
the canal. Three are privately owned, one used 
for receipt and freezing of fish and two for 
receipt and storage of oil. Fourth terminal is 
State pier, owned by Commonwealth of Massachusetts, 
and on north bank of canal at Bourne 
Neck. Terminals are adequate for purposes for 
which they are used. 
Operations and results during fiscal year. New 
work: Plans and specifications completed for 
construction of comfort stations and sanitary 
dumping station at Bourne Scenic Park. 
Maintenance: Dredging of shoals in project 
channels and basins was accomplished during 
June 1975 by Government owned hopper 
dredge. Approximately 125,620 cubic yards of 
ordinary material was removed at a cost of 
$200,000. Contract for dredging West Boat 
Basin was accomplished in June 1975. Approximately 
4,900 cubic yards of ordinary material 
was removed at a cost of $22,250. Contracts 
completed included installation of electronic 
traffic control equipment, painting the Buzzards 
Bay vertical lift bridge, boundary survey of 
project lands, paving and drainage adjacent to 
boat shop, rehabilitation of South Jetty at 
Sandwich, furnishing riprap for repair of slopes 
and dike, replacement parts for electronic traffic 
control system, repair and replacement to 
dolphins and marine structures, removal of 
sunken vessel at East Boat Basin, inspection and 
report of hangar cables for highway bridges. 
Contract still in progress is the rehabilitation of 
the Sagamore Bridge. Contracts were awarded 
but no work performed for construction of 
recreation facilities south side of Canal at gravel 
pit area, furnishing steel hangar cables for 
highway bridges, furnishing riprap for repair of 
slopes and dikes and furnishing three dimensional 
model of Canal. Condition surveys were 
performed by hired labor at a cost of $53,933 to 
determine channel depths, conditions of dikes 
and bank stabilization. Hired labor costs 
incurred for normal operation and maintenance 
activities were $1,024,699. 
Condition at end of fiscal year. Navigational 
improvements were completed in April 1963, 
with completion of East Boat Basin extension. 
Initial recreational development consisting of 
public use facilities at various locations was 
completed in February 1965. Improvements to 
public use facilities at the East Boat Basin were 
completed in May 1974. Proposed additional 
recreational facilities remain to be constructed. 
Canal is crossed by two high-level highway 
bridges and a vertical-lift railroad bridge. 
Major rehabilitation of Bourne Highway 
Bridge was completed in December 1965. Minor 
rehabilitation of stone breakwater was completed 
in October 1963. 
Canal in landcut from easterly entrance to 
station 430 has a minimum bottom width of 
480 feet, except opposite State pier where width 
is 450 feet. From station 430 to Wings Neck 
(Hog Island Channel) width is 500 feet and 
beyond Wings Neck (Cleveland Ledge Channel), 
700 feet. 
1-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
8. CLINTON HARBOR, CONN. 
Location. On north shore of Long Island 
Sound, about 10 miles west of mouth of 
Connecticut River and about 20 miles east of 
New Haven Harbor, Conn. (See Coast and 
Geodetic Survey Charts 216 and 1212.) 
Previous project. For details see page 640, 
Annual Report for 1894 and page 112, Annual 
Report for 1943. 
Existing project. A channel 8 feet deep at 
mean low water and 100 feet wide from Long 
Island Sound to upper end of wharves at 
Clinton, an anchorage area of same depth. 
opposite and above wharves, 50 feet wide south 
of channel and extending 600 feet above end of 
channel, with widths of 150 to 250 feet, and for 
maintenance of a stone dike closing a breach in 
the sandy peninsula which separates the river 
from outer harbor. Mean and spring tidal ranges 
are 4.7 and 5.5 feet, respectively. (See Table 1-B 
at end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are several small 
private wharves, some of which are open to 
public use. These facilities are adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Funding adjustment in the 
amount of $4,468 was made to dredging contract 
completed in August 1972. Hired labor 
costs were incurred in connection with closing 
out the contract. Project condition surveys were 
conducted at a cost of $9,031. 
Condition at end of fiscal year. Existing 
project was completed in 1950. 
9. CONNECTICUT RIVER BELOW 
HARTFORD, CONN. 
Location. Has its source in Connecticut Lake 
in northern New Hampshire, flows southerly 
380 miles and empties into Long Island Sound 
at Saybrook, Conn., 14 miles west of New 
London. Hartford, now head of commercial 
navigation, is 52 statute miles, by channel, from 
mouth. (See Coast and Geodetic Survey Charts 
215, 266, 267.) 
Previous project. For details see Annual 
Reports for 1915 and 1938. 
Eightmile River, Conn., elimination as separate 
project: Provides for a channel 8 feet deep and 
75 feet wide from deep water in Connecticut 
River to Hamburg and for turning basin of same 
depth, 150 feet wide, approximately 300 feet 
long at Hamburg. Project was adopted by River 
and Harbor Act of 1910. Costs and expenditures 
were $9,000 all for new work. In accordance 
with River and Harbor Act of 1950, project for 
Connecticut River below Hartford was modified 
to include project for Eightmile River. Aforementioned 
act also provided for an anchorage 
basin 6 feet deep and about 6.5 acres in area in 
upper cove at Hamburg. 
Existing project. A channel 15 feet deep and 
150 feet wide for a distance of 52 miles 
upstream to Hartford; two riprap jetties at the 
mouth of the river; and dikes, training walls, 
revetments and other regulatory works along the 
river between Hartford and Gildersleeve Island. 
The project provides for small-boat improvements 
at Wethersfield Cove; Eightmile River and 
Hamburg Cove; Essex; and North Cove, Old 
Saybrook. Dredging 6-foot channel, turning 
basin, and anchorage area at Hamburg is considered 
inactive. For a more detailed description 
of project see page 7 of Annual Report for 
1974. (See Table 1-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. On both Connecticut and 
Eightmile Rivers there are two or three wharves 
at each of river towns, one or more in each town 
being open to public use. At Hartford and 
Middletown there is about one-half of wharf 
frontage along west bank of river. Facilities 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Hired labor costs were incurred 
for preparation of plans and specifications for 
maintenance dredging of nine bar channels in 
the river and of the North Cove entrance 
channel and anchorage and for environmental 
sampling of North Cove and Brockway Bar. A 
contract was awarded on 3 January 1975 in the 
amount of $127,020 for maintenance dredging 
of the 10 and 15 foot channels at Essex Shoal 
with disposal on Nott Island, in conjunction 
with the Waterways Experiment Station's 
Dredged Material Research Program. Dredging 
commenced on 5 March 1975 and was suspended 
on 29 March due to state of Connecticut 
restrictions. During this period, approximately 
15,000 c.y. of material was removed at a cost of 
approximately $52,000. 
Condition at end of fiscal year. Except for 
inactive portion, existing project was completed 
in September 1965 with the construction of 
channel and anchorage in North Cove, Old 
Saybrook, Conn. For further details, see Annual 
Report for 1974. 
10. CUTTYHUNK HARBOR, MASS. 
Location. At eastern end of Cuttyhunk Island, 
at western entrance to Buzzards Bay, about 14 
1-6

NEW ENGLAND DIVISION 
miles south of New Bedford Harbor, Mass. (See 
Coast and Geodetic Survey Chart 297). 
Existing project. A channel generally 75 feet 
wide and 10 feet deep from outer harbor to 
westerly terminal in Cuttyhunk Pond, about 
3,500 feet; an anchorage in inner harbor 10 feet 
deep, 900 feet long, and 800 feet wide; and 
maintenance of existing jetties and stone dikes. 
Mean and spring tidal ranges are 3.4 and 4.2 
feet, respectively. (See Table 1-B at end of 
chapter for Acts authorizing existing project.) 
Local cooperation. Fully complied with. Spoildisposal 
areas for maintenance will be furnished 
when required. 
Terminal facilities. Two town wharves of 
timber and pile construction, having total 
berthing space of 400 feet, are open to public 
use. No mechanical-handling facilities are available. 
Facilities are adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging of the 10-foot entrance 
channel by the Government sidecaster dredge 
Fry commenced 24 May 1975 and was completed 
11 June 1975. Approximately 5,720 
cubic yards of material was removed at a cost of 
$38,800. 
Condition at end of fiscal year. Existing 
project was completed in 1939. 
11. EDGARTOWN HARBOR, MASS. 
Location. On the east side of Martha's Vineyard, 
the largest of a group of islands off the 
southern coast of Cape Cod, Massachusetts, 
about 27 miles southeast of New Bedford, 
Massachusetts. (See Coast and Geodetic Survey 
Chart No. 346.) 
Existing project. Authorized in 1937 and 
completed in 1939, provided for a channel 17 
feet deep, generally 150 feet wide from the 
Outer Harbor to deep water in the Inner Harbor, 
suitably widened at the bend inside the Inner 
Harbor, and removal to a depth of 12 feet of the 
entire Middle Ground shoal inside and east of 
the entrance to the Inner Harbor. Modification 
authorized in 1970 provides for construction of 
an artificial sand dune along Katama Beach from 
high ground on Martha's Vineyard toward 
Chappaquiddick Island and a 10 acre anchorage, 
6 feet deep in Edgartown Harbor. Total 
estimated Federal cost for new work is 
$2,460,000 (July 1974) exclusive of $15,614 
for new work completed. (See Table 1-B at end 
of chapter for Acts authorizing existing 
projects. ) 
Local cooperation. Fully complied with for 
completed work. Terms of local cooperation 
pertaining to remaining work authorized in 1970 
are: provide a cash contribution of 5.4 percent 
toward the project cost, an amount currently 
estimated at $140,000; maintain and operate a 
public landing with berthing depths alongside 
commensurate to the anchorage depth; hold and 
save the United States free from all damages 
which may result from the construction and 
subsequent maintenance of the project; provide 
without cost to the United States all lands, 
easements, and rights-of-way required for construction 
and subsequent maintenance of the 
project; regulate the use, growth, and free 
development of the harbor facilities with the 
understanding that they will be open to all on 
equal terms; and establish regulations prohibiting 
discharge of pollutants into the water of 
the harbor by users thereof, which regulations 
shall be in accordance with applicable law or 
regulations of Federal, State, and local authorities 
responsible for pollution prevention and 
control. Formal assurances will be requested 
during final design. 
Terminal facilities. There are two public 
wharves in the town, and in addition a commercial 
wharf and a yacht club wharf where 
recreational boats receive services and supplies. 
These wharves are ample for the needs of the 
existing and prospective fleets. Private wharves 
serving individual property owners number 
between 30 and 35. All of the wharves are of 
wood pile and timber construction and are in 
excellent condition. 
Operation and results during fiscal year. New 
work: Advance engineering and design was 
initiated. 
Condition at end of fiscal year. Construction 
has not been started on the artificial sand dune 
and 10 acre anchorage portion authorized in 
1970. The remaining portion of the existing 
project was completed in 1939. 
12. FALL RIVER HARBOR, MASS. 
Location. At mouth of Taunton River, on east 
side and at head of Mount Hope Bay, which 
empties into ocean through Narragansett Bay 
and Sakonnet River; it is about 18 miles 
northerly from Newport Harbor. (See Coast and 
Geodetic Survey Chart No. 353.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938. 
Existing project. The authorized project provides 
for a channel 40 feet deep, 400 feet wide 
from deep water in Mount Hope Bay easterly 
into Tiverton lower pool, thence northerly and 
southerly along Tiverton waterfront to Gulf Oil 
Co. wharf and Bay Oil Co. wharf respectively; 
and for a channel 40 feet deep, 400 feet wide 
1-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
from deep water in Mount Hope Bay to Globe 
wharf thence to wharves above bridge with 
increased width at bends; turning basin 40 feet 
deep, about 1,100 feet wide and 850 feet long 
above bridge between Shell and Montaup 
wharves; removal to 30 feet of lower end of Hog 
Island Shoal; maintenance of 25-foot anchorage, 
west of harbor channel; channel 30 feet deep 
and generally 300 feet wide extending about one 
mile below Slades Ferry Bridge, east of harbor 
channel and alteration of Brightman Street 
Bridge to provide for a clear channel width of 
300 feet through the drawspan. 
Mean tidal range is 4 feet, Bristol Point, and 
4.4 feet, Fall River, and maximum range, due to 
combined effect of wind and other causes, is 8 
feet or more. Total estimated Federal cost (July 
1974) for new work is $27,300,000 exclusive of 
$4,438,204 for new work completed before 
1959 and amounts expended on previous 
projects. Portion of project for removal of rock 
at Hog Island shoal is considered inactive and 
excluded from cost of new work. Cost of this 
portion estimated to be $185,000 (1954). (See 
Table 1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Fully complied with for 
completed work. Terms of local cooperation 
pertinent to remaining work authorized by River 
and Harbor Act of 1968 are: provide all lands, 
easements, rights-of-way required for construction 
and maintenance, and for aids to navigation 
upon request; hold United States free from 
damages due to construction and maintenance; 
provide and maintain adequate depths in 
approach channels and berthing areas commensurate 
with project depths; make necessary 
alterations to underwater utilities; remove existing 
Slades Ferry Bridge and alter or reconstruct 
the Brightman Street Bridge, assuming a share of 
the costs in accordance with principles of the 
Truman-Hobbs Act, all at an estimated cost to 
local interests of $3,000,000. The Commissioner, 
Massachusetts Department of Public 
Works signed an agreement with the Division 
Engineer on December 16, 1966 that establishes 
the cost apportionment for bridge alterations, 
utilizing the principle of Truman-Hobbs Act. 
However, plans for replacement of the Brightman 
Street Bridge are uncertain at this time and 
dredging of the Mount Hope Bay channel is 
contingent upon resolution of that problem. 
Terminal facilities. In upper harbor there are 
several deep-draft terminals, two of which are in 
Somerset and four in Fall River; four more 
deep-draft terminals are located along the 
Tiverton waterfront in Rhode Island. These are 
modemrn terminals used in connection with 
electrical generating stations; receipt, distribution 
and storage of oil and petroleum products; 
and a State Pier for handling general cargo, 
and a permanent berth for the battleship 
Massachusetts. 
There are ten other wharves with berthing 
depth of less than 25 feet used for mooring 
recreational and training craft, receipt and 
storage of petroleum products, boat servicing 
and repairs. For details see H. Doc 175, 90th 
Cong., 1st sess. 
Operations and results during fiscal year. New 
work: Preparation of plans and specifications for 
deepening of the Tiverton Channel portion of 
the project to 40 feet was delayed pending 
selection of a disposal area. Environmental 
studies to determine adequacy of a recommended 
disposal area and to serve as basis for a 
revised environmental impact statement were 
undertaken. Maintenance: Contract awarded 25 
June 1973 for the removal of unclassified 
material was completed in November 1974. A 
total of 18,000 c.y. of material was removed at a 
contract cost of $259,550. Final payment 
pending resolution of remaining liquidated 
damages. 
Condition at end of fiscal year. Planning 
continued for deepening Mount Hope Bay and 
Tiverton channels from 35 to 40 feet. All work 
for projects authorized prior to 1968 was 
completed in March 1959. The Commonwealth 
of Massachusetts' plans for the Brightman Street 
Bridge replacement are uncertain and dredging 
of the Mt. Hope Bay channel may be delayed 
several years. 
13. FRENCHBORO HARBOR, ME. 
Location. Frenchboro Harbor is in Hancock 
County on the northwest side of Long Island, 
the most southerly island of a large group of 
islands in Jericho Bay off the Maine coast and 
about 100 miles northeast of Portland, Maine. 
(See Coast and Geodetic Survey Charts Nos. 308 
and 1202.) 
Existing project. Authorized in 1970 to 
provide a 5 acre anchorage 10 feet deep in the 
outer harbor and an entrance channel 75 feet 
wide, 6 feet deep leading into a 1.5 acre 
anchorage basin, 6 feet deep, within the inner 
harbor. 
The current total Federal project cost (July 
1974) is estimated at $850,000. (See Table 1-B 
at end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Local interests are required 
to provide all lands, easements and rights-of-way 
required for construction and subsequent 
maintenance of the project and for aids to 
navigation; hold and save the United States free 
1-8

NEW ENGLAND DIVISION 
from damages due to construction and subsequent 
maintenance of the project; provide, 
maintain and operate a public landing with 
berthing depths alongside commensurate to the 
anchorage depth and an access road to the 
landing, including parking facilities, open to all 
on equal terms; provide and maintain depths in 
berthing areas and local access channels serving 
other wharves adjacent to the anchorage commensurate 
with the depths provided in the 
related project areas; remove a sufficient portion 
of a privately-owned pier extending into the 
proposed 6-foot anchorage; regulate the use, 
growth and development of the harbor facilities, 
with the understanding that they will,.be open to 
all on equal terms; and establish regulations 
prohibiting discharge of untreated Sewage, 
garbage and other pollutants in the waters of the 
harbor. Estimated initial cost to local interests is 
$20,000 for public access channels and berthing 
areas. Formal assurances were signed by local 
interests in December 1974. 
Terminal facilities. There are 18 wharves in the 
inner harbor and 3 in the outer harbor. All of 
these with the sole exception of the ferry wharf 
are owned by the local fishermen. The berthing 
areas of all wharves in the inner harbor are 
exposed at mean low water. 
Operations and results during fiscal year. New 
work: A contract for improvement dredging was 
awarded in April 1975 in the amount of 
$289,000. Contractor earnings for fiscal year 
1975 were $8,670. Contract is 2 percent 
complete. 
Condition at end of fiscal year. Project is 
under construction. 
14. GREEN HARBOR, MASS. 
Location. On west side of Massachusetts Bay, 
within the town of Marshfield, about 30 miles 
southeast of Boston and 9 miles north of 
Plymouth Harbor. (See Coast and Geodetic 
Survey Chart 245.) 
Existing project. Provides for channel 6 feet 
deep (8 feet at entrance), 100 feet wide extending 
about 4,000 feet from deep water to 
head of navigation, with small turning basin at 
upstream limit; 5-acre anchorage near Town 
pier, 6 feet deep; sealing, rebuilding in part, and 
a 200-foot extension of existing west jetty at 
elevation +12, with dike to beach berm at 
elevation +14 feet, and raising east jetty to 
elevation +14. (See Table 1-B at end of chapter 
for Act authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. Major terminal facility is 
Town pier in village of Brant Rock. Facility is a 
bulkheaded, earth-filled landing and parking area 
about 290 feet wide, extending 210 feet into 
harbor. A marine service is south of Town pier; 
and a facility for recreational craft has been 
developed on south side of harbor near head of 
navigation. 
Operations and results during fiscal year. 
Maintenance: A contract for repairs to the west 
stone jetty was awarded 22 November 1974 in 
the amount of $39,970. Work commenced in 
February 1975 and was completed in March 
1975. Final cost of the contract was $39,885. 
Hired labor costs were incurred for engineering 
and supervision in connection with the repairs. 
Costs in the amount of $2,500 were incurred for 
environmental sampling and testing of the 
channel and anchorage. 
Condition at end of fiscal year. Construction 
of existing project commenced in July 1968 and 
was comffpleted in October 1969. 
15. GUILFORD HARBOR, CONN. 
Location. On north shore of Long Island 
Sound about 13 miles east of New Haven 
Harbor, Conn. (See Coast and Geodetic Survey 
Charts 217 and 1212.) 
Existing project. An entrance channel 6 feet 
deep, 100 feet wide through the harbor from 
Long Island Sound to an anchorage basin in East 
River, length 0.8 mile; a channel 6 feet deep, 60 
feet wide up Sluice Creek 880 feet to Whitfield 
Street; an anchorage basin 6 feet deep, 200 feet 
wide in East River, length 1,500 feet. Mean and 
spring tidal ranges are 5.4 and 6.4 feet, respectively. 
(See Table 1-B at end of chapter for Act 
authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. State wharf about 370 feet 
long provides adequate facilities for existing 
commerce. Town wharf on north bank of East 
River at foot of Whitfield Street is no longer 
useable. 
Operations and results during fiscal year. 
Maintenance: Hired labor costs were incurred in 
connection with closing out the maintenance 
dredging contract completed in March 1974. A 
total of 69,000 c.y. of material was removed at a 
contract cost of $233,350. 
Condition at end of fiscal year. Existing 
project was completed in April 1957, with 
exception of a boulder, which was removed 
from project area in 1958. 
16. HAMPTON HARBOR, N.H. 
Location. On New Hampshire seacoast 13 
miles south of Portsmouth Harbor, 5 miles north 
of mouth of Merrimack River at Newburyport, 
Mass. (See Coast and Geodetic Survey Chart 
1206.) 
1-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. Extending north jetty 1,000 
feet, raising outer 300 feet of south jetty and 
constructing a 180-foot spur to high ground, and 
dredging to provide a channel 8 feet deep and 
150 feet wide across entrance bar. Mean tidal 
range is 8.3 feet and spring range is 9.5 feet. (See 
Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are six piers in 
Hampton Harbor. State of New Hampshire 
maintains two pile and timber piers, one in 
Hampton about 1,500 feet north of entrance 
and one in Seabrook one-half mile south of 
entrance. Hampton pier has a 6-foot walkway to 
a float that has depths of 4 to 6 feet. Seabrook 
pier has no float and a water depth of about 3 
feet at outer end. Both landings are open to 
public. Facilities are adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: From 9 April to 5 May 1975 
Government owned sidecasting dredge removed 
21,070 c.y. of material from the 8 ft. channel at 
a cost of $61,280. 
Condition at end of fiscal year. Existing 
project was completed in November 1965. 
17. HOUSATONIC RIVER, CONN. 
Location. Rises in northwestern Massachusetts, 
flows southerly 130 miles through 
Massachusetts and Connecticut, and empties 
into Long Island at Stratford, 5 miles east of 
Bridgeport Harbor. (See Coast and Geodetic 
Survey Chart 219.) 
Existing project. A channel 18 feet deep and 
200 feet wide for a distance of 5 miles to lower 
end of Culvers Bar, then 7 feet deep for 8 miles 
to Derby and Shelton; a 5,820-foot riprap 
breakwater at the mouth; a 1,500-foot training 
dike 2 miles upstream at Stratford; and a 
163-foot riprap jetty 13 miles upstream at East 
Derby. The enlargement of the breakwater and 
extension of the Stratford dike are inactive 
portions of the existing project. For more 
detailed description see page 11 of Annual 
Report for 1974. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 6 wharves for 
commercial use at Stratford, 1 at Devon, and 8 
at Shelton and Derby. The facilities are considered 
adequate for the existing commerce. 
Operations and results during fiscal year. 
Maintenance: A contract was awarded on 4 
February 1975 in the amount of $695,824 for 
maintenance dredging of the 18-foot channel. 
Work commenced in February 1975 and was 
still in progress at the end of the fiscal year. Due 
to an overrun in quantities approximately 
168,000 c.y. of material was removed at a cost 
of approximately $930,000. 
Condition at end of fiscal year. The existing 
project was fully completed in September 1957. 
18. HYANNIS HARBOR, MASS. 
Location. On south shore of Cape Cod about 
16 miles west of Chatham, Mass., and 20 miles 
northeast of Vineyard Haven, Mass. (See Coast 
and Geodetic Survey Chart 1209.) 
Existing project. A stone breakwater 1,170 
feet long, lying about 0.7 mile off shore, 
dredging to 15.5 feet deep in protected area 
behind breakwater; a channel 12 feet deep with 
widths of 150 and 100 feet in outer and inner 
harbors, respectively, an anchorage area 12 feet 
deep and about 5 acres in area adjacent to inner 
harbor channel north of Harbor Bluff; and a 
riprap jetty 1,000 feet long extending south 
from Dunbar Point. Mean spring tidal ranges in 
outer harbor are 3.1 and 3.7 feet, respectively. 
Federal cost of new work for completed project 
was $484,499. Breakwater was completed in 
1882. A survey revealed that top of the structure 
was 3 to 5 feet below authorized project 
elevation in some places and severely deteriorated. 
Minor rehabilitation was required to 
restore the breakwater to designed purpose of 
providing a harbor of refuge. Federal cost of 
completed rehabilitation of breakwater was 
$129,757. (See Table 1-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Fully complied with. Total 
actual costs for all requirements of local cooperation 
under terms of the project authorization 
amount to $103,001, cash contribution. In 
addition, Commonwealth of Massachusetts and 
local interests expended nearly $235,000 in 
extending breakwater to shore, and dredging 
channels in outer and inner harbors; and 
$52,000 expended by local interests for construction 
of a riprap jetty, 1,000 feet long, 
extending south from Dunbar Point. 
Terminal facilities. There are two town 
wharves in the inner harbor. One has a bulkhead 
frontage of about 800 feet. Other private 
landings are available. Facilities are adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging of the 12 foot entrance 
channel by the Government sidecaster dredge 
Fry commenced on 16 March 1975 and was 
completed on 8 April 1975. Approximately 
8,680 cubic yards of material was removed at a 
1-10

NEW ENGLAND DIVISION 
cost of $61,275. Project condition surveys were 
conducted at a cost of $8,957. 
Condition at end of fiscal year. Existing 
project was completed in November 1959. 
Breakwater was completed in 1882 and dredging 
behind breakwater in 1906. Rehabilitation was 
necessary to restore breakwater to its designed 
purpose of providing a harbor of refuge. Restoration 
was completed in November 1961. 
Construction of 12-foot channel and anchorage 
was initiated in May and completed in November 
1959. Commonwealth of Massachusetts 
constructed the jetty extending south from 
Dunbar Point in 1962. 
19. ISLE OF SHOALS HARBOR, ME. 
AND N.H. 
Location. A group of islands in the open sea 
about 6 miles northeast of Portsmouth Harbor, 
N.H. Three of them, Smuttynose, Cedar and 
Star Islands, are so situated that, with the shoals 
connecting them, they afford a small harbor of 
fair depth, open only to the west and northwest 
known as Gosport Harbor. (See Coast and 
Geodetic Survey Chart 330.) 
Previous projects. For details, see Annual 
Report for 1915. 
Existing project. Three rough-stone breakwaters: 
One from Smuttynose Island westwardly 
240 feet to Malaga Island on north side of 
harbor; one extending southeastwardly 700 feet 
from Smuttynose Island to Cedar Island; and a 
third extending southwestwardly 530 feet from 
Cedar Island to Star Island, affording protection 
from the southeast and south. Mean range of 
tide is 8.7 feet and the extreme 9.9 feet. (See 
Table 1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. None required. 
Terminal facilities. There is one wharf near the 
hotel on Star Island which is used to accommodate 
a passenger steamer plying between 
Portsmouth, N.H., and the Island during 3 
months of the summer. 
Operations and results during fiscal year. 
Maintenance: A contract for repairs to the 
breakwater between Cedar and Star Islands 
awarded in April 1974 was completed in 
October 1974. Approximately 8,100 tons of 
stone was placed at a cost of approximately 
$450,784. Outstanding claim by Contractor for 
underrun in quantities remains to be negotiated. 
Condition at end of fiscal year. Existing 
project was completed in 1913. Breakwater 
from Star Island to Cedar Island is in need of 
repairs; breakwaters from Cedar Island to 
Smuttynose Island to Malaga Island are in good 
condition. 
20. KENNEBEC RIVER, ME. 
Location. Drains a large number of lakes and 
minor streams, and flows from Moosehead Lake 
about 150 miles southerly and discharges into 
Atlantic Ocean about 25 miles east of Portland. 
(See Coast and Geodetic Survey Charts 288, 289 
and 314.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938. 
Existing project. A channel 27 feet deep and 
not less than 500 feet wide, extending from 
mouth to bridge at Bath; thence to Gardiner a 
channel not less than 150 feet wide, 17 feet 
deep at Beef Rock Shoal, at foot of Swan Island, 
18 feet deep through rock at Lovejoy Narrows, 
near head of Swan Island, decreasing to 16 feet 
deep at Gardiner; channel west of Swan Island 
100 feet wide, 12 feet deep, except at upper 
shoal, where depth was to be 15 feet; and 
channel 125 feet wide and 11 feet deep from 
Gardiner upstream to Augusta at head of navigation. 
Section of river included in project is about 
44 miles long. Work includes dredging, rock 
excavation, and two riprap training walls. Mean 
tidal range is 8.4 feet at mouth of river, 6.4 feet 
at Bath, 5.3 feet at Richmond, 5 feet at 
Gardiner, and 4.1 feet at Augusta. Spring tides 
are about 1 foot greater at mouth and about 0.5 
foot greater at Augusta. Portion of project for 
dredging 27-foot channel from Bath Iron Works 
Corp. to 0.6 of a mile above bridge at Bath is 
considered inactive and excluded from foregoing 
costs. Estimated cost (1954) of this portion is 
$129,500. (See Table 1-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. None required. 
Terminal facilities. Wharves suitable for 
landing or loading are at Bath, Woolwich, 
Richmond, Randolph, Gardiner, Hallowell, and 
Augusta. Of the 24 wharves at Bath, 5 are 
publicly owned and 19 privately owned, about 
one-third are in poor repair and little used. Rail 
connections are available at 19 wharves at Bath. 
Depths alongside range from 12 to 25 feet. At 
other points named above there are 16 wharves 
in usable condition. All but one are equipped 
with mechanism for handling passengers and 
freight. Those open to the public on equal terms 
are two at Hallowell and one each at Randolph 
and Augusta. None are publicly owned. Facilities 
are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging of the 27 foot channel at 
Doubling Point by Government owned hopper 
dredge was completed between 12 June and 30 
June 1975. Approximately 102,930 cubic yards 
of material was removed at a cost of $242,203. 
1-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Hired labor costs were incurred for the preparation 
of an environmental assessment. 
Condition at end of fiscal year. Existing 
project is complete except for inactive portion. 
21. KENNEBUNK RIVER, ME. 
Location. Source of Kennebunk River is in 
central part of York County in southwestern 
Maine. Stream flows about 15 miles southeasterly 
and discharges into Atlantic Ocean 
about 30 miles southwest of Portland, Maine. 
(See Coast and Geodetic Survey Chart 1205.) 
Existing project. A stone breakwater on easterly 
side of mouth of river about 550 feet long, 
a pier or jetty on westerly side of mouth about 
290 feet long, a wharf about 700 feet upstream 
from shore end of breakwater (transferred to 
Treasury in 1936), a jetty on east bank a short 
distance farther upstream, a channel 8 feet deep 
and 100 feet wide extending 1,700 feet from 
deep water to town landing, thence 6 feet deep 
over a width of 100 feet for 2,300 feet and a 
width of 75 feet for remaining 2,000 feet to 
project limit; an anchorage, 4 acres in area, on 
west side of channel and an anchorage, 2 acres in 
area, on east side, each 6 feet deep; and 
extension of west jetty by about 300 feet, 
supplemented by construction of a sand fence. 
Mean tidal range is 9 feet; extreme 13.5 feet. 
(See Table 1-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 22 landings, 16 
of which are private, 1 public, 2 yacht clubs, 1 
hotel, and 2 boatyards. Marine railway facilities 
include two of 15-ton capacity, and one of 
10-ton capacity. There are 4 berths and 10 
moorings. Open storage, boat building, repairs, 
and supplies are available for pleasure and 
commercial craft. Public landing, or granite 
block construction, has unloading facilities 
which include two tackle and falls on arms; and 
is used by fishing craft to transfer catches for 
transportation. Facilities are adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: A contract was awarded on 29 
May 1975 in the amount of $110,900 for 
maintenance dredging of the 6-foot and 8-foot 
channels. No dredging was performed during the 
year. 
Condition at end of fiscal year. Project was 
completed in December 1968, with the completion 
of rock removal at entrance to west 
channel. Extension of west jetty was completed 
in April 1965; and improvement dredging in the 
6- and 8-foot channels, 6-foot anchorages, and 
construction of a sand fence were completed in 
November 1965. 
22. LAGOON POND, MARTHA'S 
VINEYARD, MASS. 
Location. In Town of Tisbury on north shore 
of Martha's Vineyard, an island 3 miles off the 
southern coast of Cape Cod, Massachusetts. (See 
Coast and Geodetic Survey Chart 264). 
Existing project. Entrance channel 8 feet deep, 
100 feet wide from deep water in Vineyard 
Haven Harbor leading into the natural deep 
water anchorage in Lagoon Pond and seaward 
extension of existing jetty at entrance for a 
distance of 200 feet. Mean range of tide is 1.7 
feet and spring range is 2.0 feet. (See Table 1-B 
at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Local interests are required 
to make a cash contribution of 50 percent of 
project construction cost; provide and maintain 
public landing, access roads, parking areas and 
other public use facilities open to all on equal 
terms; hold United States free from damages; 
provide without cost lands, easements and 
rights-of-way; regulate use, growth and development 
of harbor, open to all on equal terms; 
establish regulations prohibiting discharge of 
untreated sewage, garbage, and other pollutants 
in the waters of Lagoon Pond. The provision of 
a public landing remains an unfulfilled item of 
local cooperation. 
Terminal facilities. Except for two boatyards 
located at its north end, Lagoon Pond has no 
terminal facilities. Most of the terminals servicing 
the Tisbury-Oak Bluffs area are located at 
southeast end of Vineyard Haven Harbor. 
Operations and results during fiscal year. New 
work: Funding adjustment was made to reflect 
final project costs. 
Condition at end of fiscal year. Project is 
complete. Improvement dredging was completed 
in September 1973; extension of jetty was 
completed in November 1973. 
23. LITTLE HARBOR, N.H. 
Location. Little Harbor is located on the west 
side of Portsmouth Harbor between New Castle 
Island and the New Hampshire mainland. 
Existing project. A channel 3,000 feet long, 
100 feet wide, and 12 feet deep; an anchorage 
basin 12 feet deep and 40 acres in area and two 
breakwaters at the harbor entrance. The north 
breakwater which is 550 feet long extends 
southeasterly from Jaffrey Point on New Castle 
Island. The south breakwater is 900 feet long 
1-12

NEW ENGLAND DIVISION 
and extends northeasterly from Frost Point in 
Rye, New Hampshire. Mean tidal range is 8.7 
feet. H. Doc. 467, 69th Cong., 1st session, 
recommended eliminating maintenance dredging. 
(See Table 1-B at end of chapter for 
Act authorizing existing project.) 
Local cooperation. None required. 
Terminal facilities. No terminal facilities present. 
Tentative State plans include a small boat 
landing and shore facilities. 
Operations and results during fiscal year. New 
work: A contract was awarded on 30 June 1975 
in the amount of $159,510 for repairs to the 
north and south breakwaters. Hired labor costs 
amounted to $2,500 for preparation of plans 
and specifications. Project condition surveys 
were conducted at a cost of $20,413. 
Condition at end of fiscal year. Existing 
project was completed in 1903. 
24. NEW HAVEN HARBOR, CONN. 
Location. On north shore of Long Island 
Sound, about 67 miles to east of New York 
City. (See Coast and Geodetic Survey Chart 
218.) 
Previous projects. For details, see Annual 
Reports for 1915 and 1938. 
Existing project. A main channel 35 feet deep, 
400 to 800 feet wide, from Long Island Sound 
to Tomlinson Bridge; two anchorage basins 
below Tomlinson Bridge of 16- and 15-foot 
depths; a pile-and-riprap dike about 4,200 feet 
long, to contract tidal flow at Fort Hale bar; a 
channel 12 feet deep and 100 to 150 feet wide, 
from southwest corner of 16-foot anchorage 
basin via City Point and West Haven wharf front 
to Kimberly Avenue Bridge; thence 12 feet deep 
and prevailing width of 75 feet up West River to 
about 600 feet upstream of Kimberly Avenue 
Bridge, and an anchorage basin 6 feet deep in 
West River opposite Mars wharf; a channel 100 
feet wide and 12 feet deep from 15-foot 
anchorage basin toward Brewery Street, about 
300 feet; a channel in Quinnipiac River 22 feet 
deep and 250 to 400 feet wide to a point about 
1,000 feet above Ferry Street, thence 16 feet 
deep and 200 feet wide to Grand Avenue, with 
turning basin 22 feet deep, 200 to 800 feet 
wide, and 700 feet long at mouth of Mill River; 
a channel up Mill River 12 feet deep, 200 feet 
wide to junction of two branches above Chapel 
Street, thence to Grand Avenue, 100 feet wide 
in East Branch and generally 125 feet wide in 
West Branch; and removal of certain obstructive 
rocks in Morris Cove. Mean range of tide is 6.2 
feet at entrance to harbor, and 6.3 feet at Long 
Wharf Light. The 22-foot channel and turning 
basin portion is to be restudied. Estimated cost 
(1960) of this portion is $980,000. (See Table 
1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. Port of New Haven is 
served by 53 waterfront facilities; 48 are within 
city limits of New Haven, and 5 in West Haven. 
Improved waterways within port area along 
which facilities are located include West River, 
Main Harbor, West and East Branches of Mill 
River, and Quinnipiac River channels. Facilities 
are all privately owned and operated with 
exception of city wharf. Depths alongside piers 
and wharves range from 35 to zero feet at mean 
low water. Nearly half of the facilities have rail 
connections either on or at rear which connect 
with Penn Central Railroad and most are accessible 
by paved streets. Nineteen wharves have 
mechanical-handling facilities, six wharves are 
open to public use upon agreement with the 
owners. Facilities are adequate for existing 
commerce. (For further details see Port and 
Terminal Facilities of Southern New England 
No. 4 revised in 1952.) 
Operations and results during fiscal year. 
Maintenance: Final cost adjustments were made 
to contract for maintenance dredging of 35-foot 
main ship channel completed in March 1974. A 
total of 945,000 c.y. of material was removed at 
a final contract cost of $1,653,750. A contract 
was awarded on 27 January 1975 in the amount 
of $74,301 for removal of shoals in the 35 foot 
main ship channel. Work commenced 7 March 
1975 and was completed 23 April 1975. The 
contract awarded to Yale University in November 
1973 to study the environmental effects of 
disposal of dredged material in Long Island 
Sound was completed in February 1975. Costs 
were $20,852. 
Condition at end of fiscal year. Existing 
project is complete. 
25. NEWBURYPORT HARBOR, MASS. 
Location. On south bank of Merrimack River, 
about 2.5 miles above mouth, and about 48 
miles by water north of Boston. (See Coast and 
Geodetic Survey Chart 331.) 
Existing project. Two jetties, one projecting 
4,118 feet from the north shore, the other 
projecting 2,445 feet from the south shore, 
converging until 1,000 feet apart, then extending 
seaward 1,000 feet parallel to axis of 
channel; partially closing Plum Island Basin by a 
timber dike; channel 12 feet deep and 400 feet 
wide through bar, thence 9 feet deep and 200 
feet wide to and including a widened turning 
basin in front of wharves. Mean range of tide is 
7.9 feet at the bar and 7.8 feet at Newburyport. 
1-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Portion of project for continuous channel from 
sea to wharves at Newburyport, 15 feet deep 
and 200 feet wide to and including a widened 
turning basin in front of wharves is considered 
inactive. Estimate this portion (June 1955) was 
$106,000. (See Table 1-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. Sixteen wharves extending 
along a frontage of about 3,500 feet of south 
bank of Merrimack River below highway bridge 
and one small pier on north side of river. 
Terminal facilities are adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Hired labor costs were incurred 
for hydrographic and topographic surveys of the 
harbor entrance and adjacent areas in conjunction 
with the Newburyport Harbor Hydraulic 
Model Study. Costs in the amount of $107,572 
were incurred for the model study itself, which 
is being conducted by the Waterways Experiment 
Station. 
Condition at end of fiscal year. Existing 
project was completed in August 1958, with the 
improvement of 12-foot channel and outer 
harbor. North jetty was completed in 1914; 
south jetty was completed, except for a length 
of about 30 feet at its outer end, in 1905. 
Required rehabilitation of these jetties completed 
in September 1970. Plum Island basin 
was partially closed in 1883 by construction of a 
timber dike. North Rock was removed in 1901. 
26. PAWTUXET COVE, R.I. 
Location. A small indentation on west shore 
of Providence River, a tributary of Narragansett 
Bay at mouth of Pawtuxet River, a small stream 
in central Rhode Island. (See Coast and Geodetic 
Survey Charts 113 and 278.) 
Existing project. A channel 100 feet wide and 
6 feet deep from deep water to head of cove, 
with a turning basin near upper end; and an 
anchorage of about 14 acres, 6 feet deep, south 
of entrance channel, with a sheltering dike, 
2,200 feet long, constructed to 12 feet above 
mean low water, on east side of anchorage. Mean 
tidal range is 4.5 feet; extreme 7.5 feet. (See 
Table 1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. All assurances of local 
cooperation have not been fulfilled. The provision 
of public landings by the city of Warwick 
remains as an unfulfilled item of local cooperation. 
Terminal facilities. There are several wharves, 
two boat yards and one marina in the cove. 
Local interests will provide and maintain necessary 
mooring facilities and utilities including two 
public landings with suitable supply facilities, 
open to all on equal terms; regulate use of 
harbor with facilities also open to all on equal 
terms. For further details see page 14 of Annual 
Report for 1974. 
Operations and results during fiscal year. 
Contributed Funds, new work: Refund of contributed 
funds in the amount of $3,483 was 
made to the State of Rhode Island and the city 
of Warwick. 
Condition at end of fiscal year. Existing 
project was completed in April 1966. 
27. PLYMOUTH HARBOR, MASS. 
Location. Harbor is 45 miles by water south of 
Boston. Its outer anchorage, the "Cow Yard," is 
common to Plymouth, Duxbury, and Kingston. 
(See Coast Geodetic Survey Chart 245.) 
Previous projects. For details, see Annual 
Reports for 1815 and 1938. 
Existing project. Provides for: protecting by 
riprap sections of Long Beach damaged by storm 
of November 1898, and restoring Eel River to its 
former course; dredging a channel 18 feet deep 
at mean low water and 200 feet wide, increased 
at entrance and on curves, from the bay to town 
wharves, formerly in areas south of State pier, a 
distance of about 2.5 miles, with a suitable 
turning basin at inner end; dredging a channel 
150 feet wide, 15 feet deep at mean low water, 
extending northwesterly about 0.3 mile from a 
point off site of northerly Craigs wharf (now 
State pier) with a turning basin 300 feet square, 
and of same depth, at its northwesterly end; 
maintenance of area dredged to 18 feet deep 
below mean low water by the Commonwealth of 
Massachusetts, connecting 15-foot channel with 
18-foot channel in vicinity of State pier; a 
rubblestone breakwater extending 1,400 feet 
easterly from a point north of Town wharf, and 
thence southeasterly for 2,100 feet; an anchorage 
8 feet deep and 60 acres in area inside 
breakwater; and elimination of authorized 
18-foot anchorage from existing project; recreational 
development, to provide for sport fishing 
from breakwater, consisting of stone causeway 
about 360 feet long from westerly end of 
breakwater to land, guard rail along top of 
breakwater and causeway, footbridge spanning a 
navigation opening through breakwater, and 
public access, parking and sanitary facilities for 
sport fishermen use. Mean range of tide is 9.6 
feet; extreme range is 13.7 feet. (See Table 1-B 
at end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Fully complied with. 
1-14

NEW ENGLAND DIVISION 
Terminal facilities. There are three wharves of 
pile and timber construction; one is owned by 
the State, one by the town, and the third by 
Plymouth Yacht Club. State and town wharves 
are open to public use. In addition, there are six 
boatyards with marine railway facilities along 
waterfront, equipped for boat building and 
repairs. Local interests will maintain existing 
public landings open to all on equal terms, and 
provide all necessary mooring facilities in 
anchorage. 
Operations and results during fiscal year. 
Maintenance: Hired labor costs were incurred 
for acquisition of a permanent easement for 
construction and maintenance of the adjustable 
groin on Long Beach Dike. Hired labor costs 
were also incurred in connection with closing 
out the contract for repairs to the adjustable 
groin which was completed in June 1973. 
Project condition survey was conducted at a cost 
of $573. 
Condition at end of fiscal year. Project is 
complete. Construction of anchorage 8 feet deep 
and 60 acres in area inside breakwater was 
completed in 1967. Construction of the rubblestone 
breakwater was completed in 1971. 
Rehabilitation of Long Beach Dike was completed 
in 1971. 
28. PROVIDENCE RIVER AND 
HARBOR, R.I. 
Location. Formed at city of Providence by 
junction of Seekonk River and two small 
streams which rise in northern Rhode Island. It 
is tidal and flows southerly in a deep channel 
between broad flats about 8 miles, emptying 
into Narragansett Bay. (See Coast and Geodetic 
Survey Chart 278.) 
Previous projects. For details see Annual 
Report for 1915, 1936, and 1938. 
Existing project. Channel 40 feet deep, generally 
600 feet wide from deep water in Narragansett 
Bay just south of Prudence Island Light to 
turn below Field Point at Providence, thence up 
to 1,700 feet wide to existing project limit at 
Fox Point, with easing of bends to minimum 
radius of 5,000 feet, excluding marginal strip 75 
feet wide channelward of established harbor 
lines; channel 30 feet deep and 150 feet wide, 
extending northeastward from upper end of 
existing project to vicinity of India Point at 
mouth of Seekonk River. Mean tidal range is 
about 4.6 feet and maximum range, due to 
combined effect of wind and other causes is 8 
feet or more. Latest approved estimate of 
project cost (July 1974) to deepen channel to 
40 feet is $18,850,000. India Pt. Channel 
portion of project is inactive and excluded from 
foregoing estimate. Estimated Federal cost of 
this portion is $300,000 (1968). (See Table 1-B 
at end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Assurances have been 
received. 
Terminal facilities. There are 27 water terminal 
facilities serving port of Providence. 
Three-fourths of all facilities have railway connections. 
Four facilities are owned by city of 
Providence and two by State of Rhode Island. 
Facilities are adequate for existing commerce. 
(For details see Port and Terminal Facilities of 
Southern New England No. 4, revised in 1952.) 
Operations and results during fiscal year. New 
work: A $1,582,000 contract for removal of an 
estimated 100,000 c.y. of rock and unclassified 
material in sections of the 40-foot channel was 
awarded 29 June 1973. However, initiation of 
contract work had been delayed by court order 
pending selection and approval of an acceptable 
disposal area. U.S. Court injunction issued 14 
March 1974 was lifted on 5 March 1975. 
Agreement was reached with the contractor and 
the contract amount was increased to 
$2,200,000. Contract work has not been initiated. 
Hired labor costs were incurred in connection 
with environmental studies of potential 
disposal areas. 
Condition at end of fiscal year. Existing 
project is 85 percent complete. Channel 35 feet 
deep, 600 feet wide was completed in 1949, and 
has now been authorized for deepening to 40 
feet. To complete the project there remains 
construction of 40 and 30-foot channels. Dredging 
contract for removal of ordinary materials in 
the 40-foot channel was completed in June 1971. 
Contract for removal of rock and unclassified 
material in the 40-foot channel has been 
awarded and work is expected to be initiated in 
fiscal year 1976. The 30-foot channel has been 
classified inactive. Head of commercial navigation 
is at Fox Point. 
29. ROCKLAND HARBOR, ME. 
Location. This harbor is on the westerly side 
of Penobscot Bay, near its mouth, and about 80 
miles northeast of Portland by water. (See U.S. 
Coast and Geodetic Survey Chart No. 320). 
Previous project. Adopted by the River and 
Harbor Acts of June 3, 1896. For further details 
of previous project see page 27 of Annual 
Report for 1906. 
Existing project. Provides for construction and 
maintenance of a breakwater 4,346 feet long 
extending southerly from Jameson Point, which 
was completed under the previous project,

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
dredging a short approach channel, and 3 branch 
channels, each with a turning basin, extending 
from deep water along about 1.5 miles of the 
central and northern waterfront. Portions of-the 
outer limits of the branch channels were not 
dredged to full depths as ledge was encountered 
and are considered to be inactive, and are 
excluded from the foregoing cost of new work. 
The estimate for this portion was last revised in 
1960 and was estimated at $310,000. For 
further description, see Annual Report for 1974. 
(See Table 1-B at end of chapter for Acts 
authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. About 15,000 feet of the 
total water frontage of the harbor has been 
developed, and over 20 wharves are in active use 
at the present time. Wharf construction varies 
from timber cribs filled with stones or earth, to 
granite faced fills with wooden-pile additions. 
Seven of the wharves have depths ranging from 
10 to 15 feet; 8 have depths ranging from 5 to 9 
feet; 4 have depths ranging from 1 to 4 feet; 
and the remainder are dry at low water. The 
Rockland Port District has constructed a 
public pier and terminal at the entrance to 
Lermond Cove. Shipping using this terminal 
includes ferry boats and supply ships servicing 
the Penobscot Bay islands. City of Rockland has 
provided a public landing with floats attached, 
having depths at mean low water of about 6 feet 
alongside. Facilities are considered adequate for 
existing commerce. (For a further description of 
terminal facilities, see S. Doc. 82, 84th Cong., 
1st sess. ) 
Operations and results during fiscal year. 
Maintenance: Hired labor costs were incurred 
for environmental sampling and monitoring of 
the ocean disposal site following maintenance 
dredging completed in January 1974. 
Condition at end of fiscal year. The existing 
project, except for the inactive portion, was 
completed in July 1959. The breakwater was 
completed in 1904. 
30. SCARBORO RIVER, ME. 
Location. A small and generally shallow 
stream about 2.5 miles long which rises in town 
of Scarboro, Maine, and empties into north end 
of Saco Bay, immediately west of Prouts Neck. 
It is 17 miles by water southeast of Portland, 
Maine. (See Coast and Geodetic Sirvey Charts 
231 and 1205.) 
Existing project. A channel across the bar 200 
feet wide and 8 feet deep at mean low water and 
a channel 2,400 feet long, 100 feet wide, and 6 
feet deep at mean low water, leading to an 
anchorage of the same depth 1,350 feet long and 
300 feet wide, and a jetty 800 feet long at tip of 
Pine Point. Mean range of tide is 8.8 feet and 
spring range is 10.1 feet. (See Table 1-B at end 
of chapter for Act authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one wharf of pile 
and timber construction on Scarboro River, 
extending northerly from Pine Point almost to 
southerly limit of anchorage. Facility is owned 
by town of Scarboro and considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Repairs by contract were made to 
Pine Point Jetty at a cost of $1,990. Dredging of 
the 8 foot channel by the Government sidecaster 
Fry was performed from 6 May to 23 May 1975. 
Approximately 9,090 c.y. of material was 
removed at a cost of approximately $45,000. 
Condition at end of fiscal year. Existing 
project was completed in May 1962. Dredging 
entrance channel and inner harbor basin was 
completed in October 1956. Channel across bar 
later shoaled and shifted until controlling depth 
in best channel was plus 0.1 foot. Because of 
excessive shoaling rate, project design was modified 
under authority delegated to Chief of 
Engineers to include construction of a jetty at 
harbor entrance. Construction of jetty was 
commenced July 1961 and completed May 
1962. 
31. WARWICK COVE, R.I. 
Location. Ten miles south of Providence, R.I., 
in city of Warwick. (See Coast and Geodetic 
Survey Chart 278.) 
Existing project. Entrance channel 6 feet deep, 
150 feet wide, into and through lower portion 
of cove, then 100 feet wide, 6 feet deep, to head 
of cove and four anchorage areas, 6 feet deep 
totalling 13 acres; 2 acres in vicinity of Oakland 
Beach Park, 5 acres on each side of the channel 
in lower part of cove and 1 acre at head of cove. 
(See Table 1-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation. Total costs for all requirements 
of local cooperation under terms of the 
project authorization amount to $133,985; and, 
in addition, local interests expended $10,000 for 
sand placement, Oakland Beach. Work was 
accomplished by hydraulic dredging in conjunction 
with project construction. Construction of 
public landings and other facilities, required of 
locaI interests, have not been started. 
Terminal facilities. There are 10 commercial 
marinas in Warwick Cove that have berthing 
facilities for 700 boats; the majority are on west 
side of cove. Most of the docks are constructed 
1-16

NEW ENGLAND DIVISION 
of wood floats and wood pilings. Services 
provided include dry and wet storage, fuel, 
water, power hoists and truck access. 
Operations and results during fiscal year. 
Contributed funds, new work: Refund of Contributed 
Funds in the amount of $26,765 was 
made to the State of Rhode Island and the city 
of Warwick. 
Condition at end of fiscal year. Existing 
project completed in August 1966. Construction 
of public landings and other facilities, required 
by local interests, remain to be completed. 
32. WELLS HARBOR, ME. 
Location. In town of Wells at mouth of 
Webhannet River about 20 miles northeast of 
Portsmouth Harbor and about 34 miles southwest 
of Portland Harbor. (See Coast and Geodetic 
Survey Chart 1205.) 
Existing project. Repairs to an old Government 
pier about 750 feet long, made of cribwork 
ballasted with stone extending seaward 
from Drakes Island; an anchorage basin 7.4 acres 
in area and 6 feet deep; a channel 100 to 150 
feet wide, extending from deep water in the 
Atlantic Ocean to inner end of basin, with 
seaward section 8 feet deep, and harbor section 
6 feet deep; and two converging stone jetties, 
one extending 940 feet easterly from Wells 
Beach and the other 840 feet southerly from 
Drakes Island, separated so as to provide a clear 
opening 400 feet wide, and for revetment of 
seaward face of tip of Wells Beach. Mean range 
of tide is 8.7 feet and spring range is 9.9 feet. 
Extension of the Wells Beach jetty to a total 
length of 2,240 feet and extension of Drakes 
Island jetty to a total length of 3,065 feet, and 
dredging a 300- by 450-foot settling basin south 
of the anchorage, was authorized by the Chief of 
Engineers on September 20, 1965. (See Table 
1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one wharf of pile 
and timber construction on the north side of the 
anchorage. Facility is owned and operated by 
the town of Wells and is considered adequate. 
Operations and results during fiscal year. 
Maintenance: An indepth study of the harbor 
was initiated to determine the cause of the rapid 
shoaling problems that have beset this project 
since its initial construction. The final study 
report will also include recommended modifications 
to the project to correct the shoaling and 
rough sea conditions at the entrance. The study 
will require at least 18 months to complete and 
will involve a review of local geology, project 
history and field measurements of physical 
events such as currents, waves, wind and sand 
transport. The study is scheduled to be complete 
by December 1976. Costs in the amount of 
$31,328 was incurred during the fiscal year. 
Project condition surveys were conducted at a 
cost of approximately $16,850. 
Condition at end of fiscal year. Project completed 
in April 1967. 
33. WEYMOUTH-FORE AND TOWN 
RIVERS, BOSTON HARBOR, MASS. 
Location. Weymouth-Fore River rises in Braintree, 
Mass., and flows northward 7.5 miles to 
empty into Hingham Bay on south side of 
Boston Harbor. It is tidal for about 6 miles of its 
length. Town River is a small tidal stream about 
2 miles long, lying entirely within the city limits 
of Quincy, Mass. It is a tributary of Weymouth- 
Fore River into which it empties about 2 miles 
above the mouth. (See Coast and Geodetic 
Survey Chart 246.) 
Previous projects. For details see Annual 
Reports for: 1907, 1915, 1932, and 1938. 
Existing project. (For details of completed 
work under separable projects for Weymouth- 
Fore and Town Rivers see Annual Report for 
1961, pages 24 and 26.) Provides for: combining 
Weymouth-Foe and Town Rivers, Mass., into a 
single project and modifies for construction of 
channel 35 feet deep, 37 feet in rock, and 500 
feet wide from deep water in Nantasket Roads, 
and along the southerly half of the Boston 
Harbor "Narrows" channel, through Nantasket 
Gut, then 35 feet deep and 400 feet wide to 
mouth of Weymouth-Fore River, then 35 feet 
deep, generally within limits of existing project 
to Weymouth-Fore River Bridge, then 35 feet 
deep and generally 400 feet wide to upper limit 
of existing project; channel 35 feet deep and 
300 feet wide, increased from 400 to 550 feet at 
bends, from mouth of Town River to existing 
turning basin in Town River; turning and 
maneuvering basin 35 feet deep at confluence of 
the two rivers in King Cove; enlarging and 
deepening to 35 feet the existing turning basin 
in Town River; 6 acres of 8-foot anchorage to 
compensate for that part of an existing local 
small-boat anchorage that would be usurped by 
widening 35-foot commercial channel; and 
dimensions of 15-foot channel, 100 feet wide, 
continuing from end of channel to point just 
below Quincy Electric Light & Power Co. 
substation, completed before 1965, remain 
unchanged. Latest approved Federal cost 
estimate for new work is $22,700,000 (July 
1974) exclusive of $6,031,853 for new work 
completed before 1962 and amounts expended 
on previous projects. Estimated cost to local 
interests for alterations to sewer lines or other 
1-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
obstructing features is $500,000. (See Table 1-B 
at end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Fully complied with for 
completed work. Assurances for 1965 modification 
have been received. 
Terminal facilities. There are nine wharves in 
Weymouth-Fore River, all grouped near the head 
of the Federal improvement. Construction consists 
mainly of pile and timber piers extending 
from timber or concrete bulkheads. There are 
6,092 feet of berthing space available. Six of the 
wharves have railroad connections and mechanical-
handling facilities. Three of the wharves are 
used in connection with a large shipyard, 2 with 
oil terminals, 1 with an electric generating plant, 
1 with a large soap manufacturing plant, and 2 
with yacht clubs. On the south bank of Town 
River are 8 wharves, 3 of which are used for 
boat building and repair work, 3 used for receipt 
of petroleum products, 1 for receiving and 
storing lumber, and 1 for receiving scrap 
materials. On the north bank of the river is a 
yacht building and repair yard. There are no 
publicly owned wharves. Facilities are considered 
adequate for the present needs of commerce. 
(For further description of terminal 
facilities, see Port Series No. 3, Port of Boston, 
revised 1956.) 
Operations and results during fiscal year. New 
work: A contract was awarded in August 1974 
for removal of unclassified material at Town 
River in the amount of $2,016,000. Contractor 
earnings for fiscal year 1975 were $1,774,000. 
Contract is 90 percent complete. A similar 
contract was awarded in March 1975 for removal 
of unclassified material at Fore River in 
the amount of $2,288,000. Contractor earnings 
for fiscal year 1975 were $594,000. Contract is 
26 percent complete. 
Condition at end of fiscal year. All work 
adopted before 1965 is complete. Contract for 
removal of ordinary material was completed in 
November 1973. Remaining work to complete 
1965 modification consists of removal of isolated 
areas of unclassified material in both rivers. 
34. WINTER HARBOR, ME. 
Location. Winter harbor is situated on the east 
side of Frenchman Bay, 6 miles east of Bar 
Harbor, Maine, on the west side of Schoodic 
Peninsula. (See Coast and Geodetic Survey 
Charts 204 and 306.) 
Existing project. The recommended plan of 
improvement would provide a 6.5 acre anchorage 
including a 75 foot wide fairway all at a 
depth of 8 feet below mean low water extending 
from the entrance to Inner Winter Harbor to a 
point near the head of the harbor. The mean 
range of tide is 10.1 feet. The cost of construction 
for the project is estimated to be 
$219,000. (See Table 1-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Local interests must maintain 
and operate the existing public landing with 
adequate parking open to all on equal terms; 
provide and maintain access channels to, and 
berthing areas at, all wharves with depths commensurate 
with those in the anchorage; hold and 
save the United States free from damages due to 
the construction and maintenance of the Federal 
anchorage; provide all lands, easements, and 
rights-of-way required for construction and 
maintenance of the improvement; regulate the 
use and growth of the harbor with the understanding 
that they will be open to all on equal 
terms; and establish regulations prohibiting 
discharge of untreated sewage, garbage and other 
pollutants in the waters of the harbor by users 
thereof. 
Terminal facilities. There is a public pier with 
floats, a yacht club landing, five small marine 
railways, and a few private piers in Winter 
Harbor. The town pier and floats are located on 
the west side of Guptill Point inside the entrance 
to Inner Winter Harbor, with depths of 4 to 8 
feet alongside at mean low water. A commercial 
wharf with three marine railways is located near 
the head of Inner Winter Harbor. 
Operations and results during fiscal year. The 
detailed project report was approved on 16 
January 1975. Plans and specifications have 
been completed and a contract in the amount of 
$99,020 was awarded on 30 June 1975 for the 
improvement dredging. 
Condition at end of fiscal year. Construction 
has not yet started. 
35. YORK HARBOR, ME. 
Location. York Harbor is at the mouth of 
York River, a small stream emptying into the 
Atlantic Ocean, about 12 miles northeast of 
Portsmouth, N.H., and 41 miles southwest of 
Portland, Maine. (See U.S. Coast and Geodetic 
Survey Charts Nos. 228 and 1205.) 
Previous projects. Adopted by the act of 
August 5, 1886. For further details see page 40 
of Annual Report for 1907. 
Existing project. The existing Federal project 
provides for widening by 170 feet the channel 
off Bragdons Island to a depth of 10 feet at 
mean low water, and for removing to the same 
depth the point of a projecting shoal just above 
the island; an 8-foot deep anchorage basin, north 
of Bragdons Island, with an average width of 
320 feet and average length of 700 feet, approxi- 
1-18

NEW ENGLAND DIVISION 
mately 5.2 acres in area; and an 8-foot deep 
anchorage basin, south of Bragdons Island, with 
an average width of 450 feet and average length 
of 550 feet, approximately 5.6 acres in area. The 
mean range of tide is 8.7 feet. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are eight wharves in 
York Harbor. Six are situated on the east side of 
the harbor. One, the combined hotel, yacht 
club, and Vinal's boat wharf is located on the 
northwest side of Stage Neck. Berth depth at 
this wharf is 13 feet. Five wharves and floats are 
located on the northeast side of the harbor. All 
have depths of 13 feet in their berths, and are 
open to the public without charge. Gasoline, 
water and supplies are available. There are two 
wharves on the west side of the harbor, the York 
Marine Service on Harris Island and the town 
wharf on Bragdon Island. 
Operations and results during fiscal year. 
Maintenance: Costs were incurred for hired 
labor activities in connection with preparation 
of plans and specifications for the proposed 
maintenance dredging. A contract was awarded 
on 10 June 1975 in the amount of $188,700 for 
maintenance dredging of the two eight-foot 
anchorages. 
Condition at end of fiscal year. The existing 
project was completed in 1961. 
36. RECONNAISSANCE AND CONDITION 
SURVEYS 
(See Table 1-D at end of chapter.) 
37. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
(See Table 1-E at end of chapter.) 
38. NAVIGATION ACTIVITIES PURSUANT 
TO SECTION 107, PUBLIC LAW 
86-645 (PREAUTHORIZATION) 
(See Table 1-F at end of chapter.) 
Alteration of Bridges 
39. AUTHORIZED BRIDGE ALTERATION 
Location. Chelsea Street Highway Bridge, 
Mass. Construction was completed in October 
1961 with a Federal cost of $138,518. In 
addition, non-Federal contributed funds 
amounted to $8,602. For details, see page 63 of 
Annual Report for 1962. 
Beach Erosion Control 
40. OAK BLUFFS TOWN BEACH, 
MARTHA'S VINEYARD, MASS. 
Location. In town of Oak Bluffs on east shore 
of island of Martha's Vineyard, Massachusetts. 
Existing project. Federal participation to 
extent of 57.5 percent of first cost of construction 
for widening 1,200 feet of beach by 
direct placement of sand fill to a width ranging 
from 200 to 150 feet to mean high water along 
its southerly 750 feet decreasing gradually 
northward along remaining 450 feet, and construction 
of a 530-foot long impermeable terminal 
groin at southern extremity of beach. 
Mean range of tide is 1.7 feet and spring range is 
2.0 feet. (See Table 1-B at end of chapter for 
Act authorizing existing project.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: Administrative costs incurred in closing 
out project. 
Condition at end of fiscal year. Project is 
complete. Construction of stone groin and 
raising and widening of beach was initiated in 
May 1973 and completed in October 1973. 
41. PLUM ISLAND, MASS. 
Location. Plum Island comprises the ocean 
shoreline of northern Massachusetts, extending 
from four miles south of the Massachusetts - 
New Hampshire state line southward about eight 
miles. (See Coast and Geodetic Survey Chart 
Nos. 213 and 1206.) 
Existing project. Provides for dune restoration 
and embankment reinforcing along 800 feet of 
backshore fronted by a protective beach formed 
by direct placement of suitable sandfill furnishing 
a level beach berm of 75.0 feet in width 
at an elevation of 15.0 feet above mean low 
water. The construction forms a protective 
width of about 210 feet in front of the existing 
backshore. Mean tide range is 8.3 feet and spring 
range is 9.5 feet. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Local interests are required 
to contribute in cash 50 percent of project 
construction cost, estimated to be $100,000; 
assure continued public ownership and use of 
shore and its administration for public use 
during economic life of project; assure performance 
of maintenance and repair of project 
during economic life; with Federal assistance in 
the amount of 50 percent of periodic beach 
nourishment; water pollution that would 
endanger health of bathers will not be permitted; 
provide necessary parking and sanitary 
1-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
facilities, open to all on equal terms; hold and 
save United States free from damages; and bear 
all project costs in excess of Federal cost 
limitation of $1,000,000. Formal assurances 
have been received from the Commonwealth of 
Massachusetts. Local cash contributions in the 
amount of $100,000 have been received. 
Final contract quantities and associated costs 
have now been determined. Based on the prescribed 
50 percent cost sharing, the Commonwealth's 
share is $104,875. Accordingly, a 
non-Federal funding deficiency of $4,875 exists. 
These funds have been requested. 
Operations and results during fiscal year. New 
work: Final project cost, including both contract 
and Government costs, determined to be 
$209,750. Request made of Commonwealth of 
Mass. for deficiency in local funding. 
Condition at end of fiscal year. Existing 
project is complete. Construction to provide for 
dune restoration and embankment reinforcing 
was initiated in February 1973 and completed in 
April 1973. 
42. REVERE BEACH, MASS. 
Location. In the City of Revere, Suffolk 
County, Massachusetts, approximately 7 miles 
north of the main entrance channel to Boston 
Harbor and 6 miles northeast of the City of 
Boston. (See U.S. Coast and Geodetic Survey 
Chart No. 1207, and U.S. Geological Survey 
Maps, Boston Bay quadrangle.) 
Existing project. In lieu of the project authorized 
by Rivers and Harbor Act of 1954 (See 
Annual Report for 1957) provides for raising 
and widening about 13,000 feet of beach by 
placement of suitable sandfill to a general 
backshore elevation of 18 feet above mean low 
water, thus furnishing a protective and recreational 
beach of about 185 feet in width behind 
the mean high water line. The latest approved 
cost estimate (1974) is $4,800,000 of which 
$2,400,000 is non-Federal. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Formal assurances have not 
been requested. Local interests are required to: 
contribute in cash 50 percent of the cost of 
construction of the project, presently estimated 
at $2,400,000; contribute in cash 50 percent of 
the periodic nourishment cost for an initial 
period of ten years, now estimated at $37,500 
annually, such contribution to be prior to each 
nourishment operation; assure the continued 
performance of the periodic nourishment and 
repair of the project after the first ten years and 
during the economic life as may be required to 
serve the intended purpose; assure that water 
pollution that would endanger the health of 
bathers would not be permitted; hold the United 
States free from damages due to construction of 
the project; provide all necessary lands, easements 
and rights-of-way for the initial construction 
and subsequent nourishment of the project; 
assure continued public ownership of the shore 
and its administration for public use during the 
economic life of the project. 
Operations and results during fiscal year. New 
work: Preconstruction planning, by hired labor, 
was suspended on 14 April 1975. 
Condition at end of fiscal year. Revere Beach 
was reclassified as inactive on 14 April 1975 
when local interests indicated inability to provide 
the required items of local cooperation at 
that time. 
43. INSPECTION OF COMPLETED BEACH 
EROSION CONTROL PROJECTS. 
Fiscal year costs for inspection of beach 
erosion control projects were $46,487. Inspections 
were made at the following beaches in July 
and August 1974: Connecticut - Burial Hill, 
Calf Pasture, Compo, Cove Island, Cummings 
Park, Guilford Point, Gulf, Hammonassett, 
Jennings, Lighthouse Point, Middle, Prospect, 
Sasco Hill, Seaside Park, Sherwood Island Park, 
Short, Silver to Cedar, Southport, Woodmont 
Shore; Massachusetts - North Scituate, 
Plymouth Town, Quincy Shore, Revere, 
Wessagussett and Winthrop; New Hampshire - 
Hampton and Wallis Sands State Beach; Rhode 
Island - Misquamicut, Sand Hill Cove and Cliff 
Walk. 
44. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS. 
(See Table 1-G at end of chapter.) 
45. BEACH EROSION CONTROL ACTIVITIES 
PURSUANT TO SECTION 103, 
PUBLIC LAW 87-874 
(PREAUTHORIZATION) 
(See Table 1-H at end of chapter.) 
Flood Control 
46. BLACKSTONE RIVER BASIN, 
MASS. AND R.I. 
Works covered by this plan consist of a dam 
and reservoir on West River and local protection 
works at three cities on Blackstone River. Flood 
Control Act of 1944 authorized plan for a 
reservoir on West River and local protection 
works at Worcester, Mass., and Woonsocket and 
1-20

NEW ENGLAND DIVISION 
Pawtucket, R.I., substantially in accordance 
with House Document 624, 78th Congress, 2d 
session. Flood Control Act of 1960 authorized a 
local flood protection project at Lower Woonsocket, 
R.I., substantially in accordance with 
Senate Document 87, 85th Congress, 2d session. 
(See Table 1-I end of chapter on reservoir and 
local protection projects, Blackstone River 
Basin, for projects comprising authorized plan.) 
46A. WEST HILL DAM, MASS. 
Location. Dam is on West River, Mass., 3 miles 
above its confluence with Blackstone River and 
2.5 miles northeast of Uxbridge, Mass. (See 
Geological Survey maps - Blackstone, Mass. and 
R.I., Milford, Mass., and Grafton, Mass.) 
Existing project. A rolled-earthfill dam 2,400 
feet long with a maximum height of 51 feet 
above streambed. An ogee spillway and channel 
constructed through a rock knoll on west 
abutment. Outlet consists of three gatecontrolled 
conduits through spillway section. 
Reservoir has a flood control storage capacity of 
12,400 acre-feet, equivalent to 8.3 inches of 
runoff from its drainage area of 28 square miles. 
Conservation storage of 3,000 acre-feet, equivalent 
to 2 inches of runoff, is authorized. Dam is 
constructed to allow for future raising to provide 
conservation storage. Cost of new work for 
completed project is $1,367,000 for construction 
and $940,000 for lands and damages 
including highway and utility relocations, a total 
of $2,307,000. (See Table 1-B at end of chapter 
for Act authorizing existing project. ) 
Local cooperation. Section 3, Flood Control 
Act of 1944, applies. 
Operations and results during fiscal year. 
Maintenance: Operations consisted of ordinary 
operation and maintenance. 
Condition at end of fiscal year. Project is 
complete. Work on contract for dam and 
appurtenant structures was initiated in June 
1959 and completed in June 1961. 
46B. WORCESTER DIVERSION, MASS. 
Location. The project extends from Leesville 
Pond, 1 mile southwest of Worcester, to a point 
on the Blackstone River, 1 mile southeast of the 
city, in the towns of Auburn and Millbury, 
Worcester County, Mass. (See U.S. Geological 
Survey map for Worcester South, Mass.) 
Existing project. The project consists of a 
control dam across Leesville Pond and an uncontrolled 
intake structure containing a diversion 
weir and transition. From the intake structure a 
4,205 foot diversion tunnel of circular concrete, 
16 feet in diameter runs southeasterly through 
Pakachoag Hill. The tunnel connects with an 
11,300-foot open channel excavated in earth 
and rock which follows the general alinement of 
Hull Brook to the Blackstone River. Included in 
the project are construction of a railroad bridge, 
three highway bridges across the Worcester 
Diversion Channel, caring for a petroleum pipeline, 
a gas transmission pipeline, and an 8-inch 
water main which cross the channel alinement. 
The latest approved cost estimate for new work 
is $4,923,500 for construction including 
$142,000 for corrective work along Hull Brook, 
and $1,179,000 for bridge alterations, lands, and 
rights-of-way, a total of $6,102,500. (See Table 
1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Local cooperation requirements 
have been fully complied with. All relocations 
for which local interests are responsible 
were completed in 1958. Total estimated costs 
for all requirements of local cooperation amount 
to $1,021,000. 
Operations and results during fiscal year. New 
work: Contract awarded 21 August 1974 for 
Worcester Diversion Channel modifications to 
Hull Brook and tributaries. All work was completed 
in May 1975. Total earnings were 
$82,968. 
Condition at end of fiscal year. Construction 
of project was initiated in July 1957 and 
completed in January 1960. 
47. CHARLES RIVER DAM, MASS. 
Location. On the Charles River in the city of 
Boston, Suffolk County, Massachusetts, about 
2,250 feet downstream of the existing Charles 
River Dam. (See Geological Survey map for 
Boston South, Mass.) 
Existing project. A multiple-purpose earth and 
concrete dam with river pumping facilities, three 
navigation locks and an overhead highway 
viaduct. Dam about 750 feet long with maximum 
height of 36 feet. Pumping facilities 
comprised of six 1,400 cfs capacity pumps. One 
commercial lock 40 feet by 300 feet and 17 feet 
deep. Two recreational locks 25 feet by 200 feet 
and 8 feet deep. Overhead highway viaduct 
about 700 feet long and a roadway width of 52 
feet consists of 11 spans of reinforced concrete 
slab and steel stringer deck. 
The project provides flood protection to the 
intensively developed urban and industrial area 
of Boston and its suburbs. The locks afford 
increased locking capacity and reduced locking 
time. The highway viaduct allows for future 
provision of a needed highway crossing of the 
Charles River in the Warren Avenue area of 
Boston and Charlestown. Latest approved cost 
1-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
estimate (July 1974) for new work is 
$9,900,000 for lands including relocations and 
$46,000,000 for construction, a total of 
$55,900,000. Total includes local costs of 
$500,000 for lands, $9,400,000 for relocations 
and a cash contribution of $6,900,000 a total of 
$16,800,000. (See Table 1-B at end of chapter 
for Act authorizing existing project.) 
Local cooperation. Local interests will be 
required to: provide all lands, easements, and 
rights-of-way necessary for construction of the 
project, presently estimated at $500,000; 
accomplish all modifications to existing sewerage 
and drainage facilities which may be required 
to prevent their continued emptying into 
the pool above the new dam and provide all 
relocations of buildings and utilities, highways, 
sewers and related special facilities that will be 
required by reason of construction of the 
project, presently estimated at $9,400,000; hold 
and save the United States free from damages 
due to construction works; prevent encroachment 
on the Basin, including its extension, 
which would decrease its flood storage effectiveness; 
continue to operate and maintain existing 
public use, access, and landing facilities for 
recreational boats; provide public access to the 
new area of the basin between the new and 
existing dams; regulate the use, growth and 
development of navigation and navigation facilities 
in the basin; establish regulations prohibiting 
discharge of pollutants into the waters of the 
basin by users thereof, which regulations shall be 
in accordance with applicable laws and regulations 
of Federal, State and local authorities 
responsible for pollution prevention and control; 
preserve present openings - locks and sluices - 
through the existing Charles River Dam in order 
to assure the continued flow of water and 
passage of boats through the dam; bear 50 
percent of the cost of structural features allocated 
to navigation and 100 percent of the cost 
of structural features allocated to highway transportation, 
a sum presently estimated at 
$6,900,000; operate and maintain all features of 
the project after its completion; furnish to the 
United States, without cost, all available 
engineering data pertinent to the project, 
including plans prepared for the Metropolitan 
District Commission for construction of a dam 
at Warren Avenue. 
Operations and results during fiscal year. New 
work: Contract for fabrication and delivery of 
pumps was substantially completed. Remaining 
contract work consists of installation and testing 
of the pumps which is expected to be completed 
December 1976. Contractor earnings this fiscal 
year were $692,702. A multi-component contract 
for construction of the Charles River Dam 
was awarded on 22 February 1974 for 
$34,957,250. Contract is 34 percent complete. 
Contractor earnings this fiscal year were 
$9,900,768. 
Condition at end of fiscal year. Project is 
under construction. 
48. CHARLES RIVER (NATURAL 
VALLEY STORAGE AREAS), MASS. 
Location. The Charles River extends inland 
from Boston Harbor southwesterly toward the 
Massachusetts-Rhode Island border and is some 
80 miles long with a watershed covering 307 
square miles. 
Existing project. The project provides for 
Federal acquisition and perpetual protection of 
17 crucial natural valley storage areas totalling 
an estimated 8,422 acres in what is known as the 
Middle and Upper watershed of the Charles 
River. The acquisition in fee or by easement of 
the major natural valley storage areas within the 
Charles River watershed is intended as a 
multiple-purpose project for flood control, 
recreation, and fish and wildlife management. 
Not only do the upstream wetlands suffer the 
effects of high flow periods, they also mitigate 
the consequences of low flow and extended 
drought. By releasing their stored waters gradually 
in the summer months, stream flows are 
naturally sustained through periods of low precipitation. 
Much of the wetlands protected will 
be managed as a wildlife refuge with limited 
public access. The benefits projected for the 
Middle and Upper Charles River area relate to 
minimizing future flood losses and protecting 
the ecologic integrity of a fragile environment. 
The latest approved cost estimate (July 1974) 
for new work is $9,680,000. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Local interests are required 
to prevent modification or alteration of existing 
roadways, utilities, bridges, culverts, and any 
other improvements that might affect the drainage 
characteristics of the natural storage areas; 
adopt and enforce regulations to restrict development 
of flood plain lands; and operate and 
maintain the existing dams along the Charles 
River. 
Operations and results during fiscal year. New 
work: Advance engineering and design was 
initiated. Contract for photogrammetric survey 
was awarded 28 March 1975 in the amount of 
$80,194. Contractor earnings for FY 1975 were 
$37,000. 
Condition at end of fiscal year. Construction 
has not been started. Advance engineering and 
design is continuing and is 22% complete. 
1-22

NEW ENGLAND DIVISION 
49. CONNECTICUT RIVER BASIN, 
VT., N.H., MASS., AND CONN. 
Location. Works covered by this project are a 
series of dams and reservoirs on tributaries of 
Connecticut River in Vermont, New Hampshire 
and Massachusetts, within a radius of 230 miles 
from Hartford, Conn., and local protection 
works at several cities in the basin. 
Existing project. Flood Control Act of 1936, 
as amended by act of May 25, 1937, authorized 
construction of 10 reservoirs on tributaries of 
Connecticut River in accordance with plans in 
House Document 412, 74th Congress, 2d session, 
as the same may be revised upon further 
investigation of 1936 flood. Flood Control Act 
of 1938 approved a general comprehensive plan 
for control of floods and other purposes in 
Connecticut River Valley, as set forth in House 
Document 455, 75th Congress 2d session, and 
authorized $11,524,000 for construction of 
local flood-protection projects in the plan. Act 
of October 15, 1940, modified act of June 28, 
1938, to provide additional protection at East 
Hartford, Conn., as set forth in House Document 
653, 76th Congress, 3d session. Act of 
August 18, 1941, modified comprehensive plan 
approved in 1938 to include improvements 
recommended in House Document 653, 76th 
Congress, 3d session, and House Document 724, 
76th Congress, 3d session, with such further 
modifications as may be found justifiable in 
discretion of Secretary of the Army and Chief of 
Engineers. Latter act also authorized to be 
appropriated additional $6 million for local 
protection works and $10 million for reservoirs, 
Act of October 26, 1942, further modified plan 
by including construction of Gully Brook conduit 
at Hartford, Conn. Flood Control Act of 
1944, authorized expenditure of $30 million in 
addition to previous authorization for comprehensive 
plan approved in 1938 and modified 
plan by directing specific consideration of an 
alternative plan of Vermont State Water Conservation 
Board instead of Williamsville Reservoir 
in West River Basin, Vt.; directing consultation 
with affected States during course of investigations 
and transmission of proposal and plans to 
each affected State for written views and 
recommendations for reservoir projects heretofore 
authorized for construction at Cambridgeport, 
Ludlow, South Tunbridge, and Gaysville, 
and resubmission of projects or modifications 
thereof to Congress; and rescinded authorization 
for construction at Sugar Hill site. Flood 
Control Act of 1950 modified project for flood 
control at Hartford, Conn., authorized by Flood 
Control Act of 1938, as amended, to include 
Folly Brook dike and conduit. Flood Control 
Act of 1954 modified plan for flood control in 
Connecticut River Basin to provide for construction 
of a reservoir on Otter Brook at South 
Keene, N.H., in lieu of any reservoir or reservoirs 
heretofore authorized. This act further modified 
plan for West River Basin of Connecticut River 
in Vermont to consist of three reservoirs at Ball 
Mountain, The Islands, and Townshend sites, in 
lieu of plan of eight reservoirs authorized in 
Flood Control Act of 1944. Flood Control Act 
of 1958 modified plan for flood control in 
Connecticut River Basin to include construction 
of Littleville Reservoir on Middle Branch of 
Westfield River, Mass., and Mad River Reservoir 
on Mad River, above Winsted, Conn. Flood 
Control Act of 1960 included authorization in 
Connecticut River Basin of plan for flood 
protection on Chicopee River, Mass., substantially 
in accordance with House Document 434, 
86th Congress; plan for flood protection on 
Westfield River, Mass. substantially in accordance 
with Senate Document 109, 86th Congress; 
plan for flood control and related purposes 
on Farmington River, Conn., substantially 
in accordance with House Document 443, 86th 
Congress. Flood Control Act of 1968 included 
authorization in Connecticut River Basin of plan 
for construction of Beaver Brook Reservoir, on 
Beaver Brook in Keene, N.H., substantially in 
accordance with Senate Document 60, 90th 
Congress; and plan for flood protection on Park 
River, Conn., substantially in accordance with 
Senate Document 43, 90th Congress. Flood 
Control Act of 1970 deauthorized the construction 
of a reservoir at Claremont, N.H. Local 
protection projects at Gardner, Mass. and 
Hartford, Vt. authorized in accordance with 
Section 205 of 1948 Flood Control Act. (See 
Table 1-J at end of chapter for reservoirs and 
local protection works proposed for construction 
in modified comprehensive plan.) 
49A. BALL MOUNTAIN LAKE, VT. 
Location. Dam is on West River, 29 miles 
above its junction with Connecticut River at 
Brattleboro, Vt. It is 2 miles north of village of 
Jamaica, Vt. (See Geological Survey map for 
Londonderry, Vt.) 
Existing project. A rock and earthfill dam, 915 
feet long at its crest, 265 feet above riverbed. A 
chute spillway with a concrete weir 235 feet 
long was constructed in right abutment. A 
reinforced concrete-lined tunnel under dam was 
constructed as an outlet works and is controlled 
by hydraulically operated gates from a tower at 
intake end. Reservoir is operated for flood 
control purposes and has a storage capacity of 
54,600 acre-feet, equivalent to 6 inches of 
runoff from its drainage area of 172 square 
miles. Estimated cost for new work is 
1-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
$10,535,200 for construction and $350,000 for 
lands and damages, a total of $10,885,200. 
Total includes an estimated $350,000 for additional 
recreational facilities to be constructed. 
Project is a unit of comprehensive plan for 
flood control and other purposes in Connecticut 
River Basin. (See Table 1-B at end of chapter for 
Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. New 
work: Contract for construction of comfort 
station was awarded 30 June 1975, in the 
amount of $58,700. Maintenance: Ordinary 
operation and maintenance activities. 
Condition at end of fiscal year. Project is 
complete except for construction of additional 
recreation facilities. Construction of dam and 
appurtenamt works was initiated in May 1957 
and completed in November 1961. 
49B. BARRE FALLS DAM, MASS. 
Location. Dam is on Ware River in town of 
Barre, Mass., 31.9 miles above confluence of 
Ware and Swift Rivers. It is 13 miles, northwest 
of Worcester, Mass. (See Geological Survey 
maps - Barre, Mass., and Wachusett Mountain, 
Mass.) 
Existing project. Dam, of earth and rockfill 
construction, is 885 feet long with a maximum 
height of 62 feet above streambed. Spillway is 
concrete chute-type with a crest length of 60 
feet in right abutment of dam. Outlet works, 
including a reinforced concrete conduit and gate 
structure, are founded on bedrock under left 
abutment. Included in project are three dikes 
with a total length of 3,215 feet and a maximum 
height of 48 feet in saddles in rim of reservoir. 
Flood control storage capacity of reservoir is 
24,000 acre-feet, equivalent to 8.2 inches of 
runoff from drainage area of 55 square miles. 
Reservoir is operated as a unit of a coordinated 
system of reservoirs for control of floods in 
Connecticut River Basin. Completed cost of new 
work is $1,928,800 for construction and 
$39,000 for lands and damages including highway 
relocation, a total of $1,967,800. (See 
Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in May 1956 and completed 
in May 1958. 
49C. BIRCH HILL DAM, MASS. 
Location. Dam is on Millers River, 27.3 miles 
above its junction with Connecticut River. It is 
1.3 miles east of South Royalston, Mass., and 
7.5 miles northwest of city of Gardner, Mass. 
(See Geological Survey maps for Royalston and 
Winchendon, Mass.-N.H. and Templeton, Mass.) 
Existing project. Dam is rolled-earth type with 
a dumped rock shell. It has a top length of 1,400 
feet, a top width of 25 feet, and is 56 feet above 
riverbed. Spillway consists of three concrete 
weirs in two natural saddles and an abandoned 
railroad cut northwest of dam. Main weirs have a 
crest length of 720 and 350 feet, respectively, 
and the weir in the railroad cut has a crest length 
of 23 feet. Outlet works are on rock at right end 
of dam and consist of an intake channel 1,500 
feet long, a gate structure with a gatehouse 
directly above, and an outlet channel 1,150 feet 
long. Outlet works are controlled by four 6- by 
12-foot roller gates mechanically operated from 
gatehouse above. Reservoir is operated for flood 
control purposes and has a storage capacity of 
49,900 acre-feet, equivalent to 5.3 inches of 
runoff from its drainage area of 175 square 
miles. Estimated cost of new work for project is 
$2,347,000 for construction and $3,075,000 for 
lands and damages, a total of $5,422,000. Total 
includes $315,000 as local share of additional 
recreation facilities to be constructed. Project is 
a unit of comprehensive plan for flood control 
and other purposes in Connecticut River Basin. 
(See Table 1-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. Local interests must also 
bear 50 percent of future recreational development 
in accordance with 1965 Federal Water 
Project Recreation Act. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activity. 
Condition at end of fiscal year. Project is 
complete except for construction of additional 
recreational facilities. Construction of dam and 
appurtenant works was initiated in June 1940 
and completed in February 1942. 
49D. CHARLESTOWN, N.H. 
Location. The town of Charlestown is located 
on the left bank of the Connecticut River about 
25 miles northwest of Keene, New Hampshire, 
and about 7 miles north of Bellows Falls, 
Vermont. 
1-24

NEW ENGLAND DIVISION 
Existing project. The project consists of placement 
of stone slope protection along an approximate 
1,350 foot reach of the Connecticut River 
in Charlestown, N.H. to prevent future river 
bank erosion at the Charlestown Sewage Treatment 
Plant. The proposed works consist of a 36" 
layer of rock fill placed on dumped gravel fill. 
No clearing or earth excavation is required. The 
existing 12" pipe outlet to the treatment plant 
will be extended through the fill section. 
Estimated cost of new work is $114,000. (See 
Table 1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Local interests will provide 
without cost to the United States all lands, 
easements, rights of way, utilities relocation and 
alterations necessary for project construction; 
hold and save the United States free from 
damages due to the construction works; maintain 
and operate all the works after completion 
in accordance with regulations prescribed by the 
Secretary of the Army, currently estimated at 
$200 per year; prevent future encroachment 
which might interfere with proper functioning 
of the project; and contribute to the United 
States all necessary funds over and above the 
federal cost limitation of $250,000, should this 
become necessary. 
Operations and results during fiscal year. New 
work: Contract for Construction of Emergency 
Bank Protection was awarded 21 August 1974 
and completed 3 December 1974. Total earnings 
for fiscal year 1975 were $91,538. 
Condition at end of fiscal year. Existing 
project is complete. 
49E. CHICOPEE FALLS, MASS. 
Location. Chicopee Falls local protection 
project is on left (east) bank of Chicopee River 
in city of Chicopee, Mass. (See Geological 
Survey map for Springfield, North, Mass.) 
Existing project. About 1,400 feet of concrete 
floodwalls and 3,620 feet of earth dikes along 
left bank of Chicopee River extending between 
Chicopee Dam and high ground at lower end of 
property owned by the U.S. Rubber Co. Right 
bank excavated along downstream half of 
project to provide additional waterway area 
needed because of encroachment on channel 
resulting from construction of dike on left bank. 
Surface drainage from large high area above 
plants is intercepted into river by two gravity 
outfall systems. Two pumping stations dispose 
of surface runoff, industrial process water, 
sewage and seepage collected in low area during 
flood stage. Latest approved estimated cost for 
new work is $2,600,000 for construction and 
$70,000 for lands, damages, and relocation, a 
total of $2,670,000 for new work. Total 
includes $475,000 estimated local costs. (See 
Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Local interests must 
assume at least 20 percent of cost (except costs 
of planning, design, and acquisition of water 
rights) of completed project, payable either as 
construction proceeds or pursuant to a contract 
providing for repayment with interest within 50 
years. Actual cost, or fair market value of lands, 
easements, rights-of-way, and work performed 
or services rendered prior to completion of 
construction of project, which are furnished by 
a non-Federal entity, shall be included in share 
of cost to be borne by non-Federal entity. Local 
interests must furnish lands and rights-of-way 
for construction; provide sewer and utility alterations 
for construction and operation, including 
construction of a water intake and extension of 
a low dam for furnishing water to U.S. Rubber 
Co. as a replacement for existing facilities; 
maintain and operate works after completion; 
and permit no encroachment on improved channels 
or on ponding areas or, if ponding areas or 
capacities are impaired, provide substitute 
storage capacity. Total estimated costs for all 
requirements of local cooperation are $475,000 
including $20,000 for lands, $35,000 for relocations, 
and $420,000 cash contribution. Assurances 
accepted and all requirements are being 
fulfilled. 
Operations and results during fiscal year. New 
work: Costs incurred for audit of local costs to 
determine final cost sharing. 
Condition at end of fiscal year. Construction 
of project was initiated in October 1963 and 
completed in July 1965. Remaining work consists 
of completing audit of local costs to 
determine final cost sharing. 
49F. COLEBROOK RIVER LAKE, CONN. 
Location. Damsite is in town of Colebrook, 
Litchfield County, Conn., on West Branch 
Farmington River about 3.9 miles upstream 
from its confluence with Still River at Riverton, 
Conn., and about 1.5 miles upstream from 
Goodwin (Hogback) Dam. (See Geological Survey 
map for Winsted, Conn.) 
Existing project. Construction of a combined 
earth and rockfilled dam 1,300 feet long with a 
maximum height of 223 feet above streambed. 
An earth dike 1,240 feet long and 54 feet high 
prevents reservoir overflow into Sandy Brook. 
Spillway is chute type with a crest length of 205 
feet. Outlet consists of a rock tunnel 10 feet in 
diameter. Control tower contains three, 4 by 8 
feet hydraulic gates to regulate reservoir dis- 
1-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
charge. Capacity of reservoir includes 11,000 
acre-feet of existing water supply in Goodwin 
Dam Reservoir pool, 30,700 acre-feet of new 
water-supply storage, 50,800 acre-feet for flood 
control storage, 5,000 acre-feet for fish and 
wildlife purposes and 1,000 acre-feet dead storage, 
a total of 98,500 acre-feet equivalent to 
15.5 inches of runoff from its drainage area of 
118 square miles. Latest approved estimated 
cost for new work is $8,342,000 for construction 
and $5,922,000 for lands, damages, and 
relocations, a total of $14,264,000 for new 
work. (See Table 1-B at end of chapter for Act 
authorizing existing project.) 
Local cooperation. Water supply contract was 
signed by Hartford Connecticut Metropolitan 
Water District. Repayment will be made in 
accordance with provisions of 1958 Water 
Supply Act. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activity. Contract awarded in April 1974 
for repair of control tower concrete was completed 
December 1974. Contractor earnings for 
fiscal year were $34,450. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in May 1965 and completed 
in June 1969. Construction of recreation facilities 
was initiated in August 1969 and completed 
in June 1970. 
49G. CONANT BROOK DAM, MASS. 
Location. Site is in south central part of 
Massachusetts in town of Monson. Damsite, 
across Conant Brook, is about 2 miles southwest 
of community of Monson. (See Geological Survey 
map for Monson, Mass.) 
Existing project. Dam is of combined rolledearthfill 
and rockfill construction, about 1,050 
feet long, with a maximum height of 85 feet 
above streambed. A concrete ogee spillway, 100 
feet long, and a spillway channel on right bank 
carries reservoir overflow around dam. Flood 
control capacity of reservoir is 3,740 acre-feet, 
equivalent to 9 inches of runoff from drainage 
area of 7.8 square miles. Total cost of new work 
for completed project was $1,936,000 for construction 
and $1,015,000 for lands, damages, 
and relocation of roads and utilities, a total of 
$2,951,000. (See Table 1-B at end of chapter for 
Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activity. 
Condition at end of fiscal year. Construction 
of dam, highway relocations, and appurtenances 
was initiated in June 1964 and completed in 
December 1966. 
49H. KNIGHTVILLE DAM, MASS. 
Location. Dam is on Westfield River, 27.5 
miles above its junction with Connecticut River. 
It is 4 miles north of town of Huntington, Mass., 
and about 12 miles west of city of Northampton, 
Mass. (See Geological Survey map for 
Westhampton, Mass.) 
Existing project. Dam is hydraulic earthfill 
type with a dumped rock shell and a downstream 
rock toe. It has a top length of 1,200 
feet, a top width of 30 feet, and 160 feet above 
riverbed. Spillway is a curved concrete weir 410 
feet long, on rock in a saddle at right end of 
dam. Outlet works are in right abutment and 
consist of an intake channel 280 feet long and a 
16-foot-diameter tunnel through rock. Tunnel is 
605 feet long and controlled by three 6- by 
12-foot broome gates mechanically operated 
through a control tower from a gatehouse above. 
Provision has been made for future installation 
of a penstock for development of power at the 
site in accordance with a request by Federal 
Power Commission. Reservoir is now operated 
for flood control purposes and has a storage 
capacity of 49,000 acre-feet, equivalent to 5.6 
inches of runoff from its drainage area of 164 
square miles. Latest approved cost estimate for 
new work is $2,879,200 for construction and 
$821,200 for lands and damages, a total of 
$3,700,400. Total includes $185,000 as local 
share of additional recreation facilities to be 
constructed. Project is a unit of comprehensive 
plan for flood control and other purposes in 
Connecticut River Basin. (See Table 1-B at end 
of chapter for Acts authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete except for construction of additional 
recreational facilities. Construction of dam and 
appurtenant works was initiated in August 1939 
and completed December 1941. 
49I. LITTLEVILLE LAKE, MASS. 
Location. Dam is on Middle Branch of Westfield 
River 1 mile above its confluence with 
main stem of Westfield River and 25.2 miles 
above confluence of Westfield River with 
Connecticut River, in town of Chester. (See 
Geological Survey map, Chester, Mass.) 
1-26

NEW ENGLAND DIVISION 
Existing project. A rolled-earth and rockfill 
dam, 1,360 feet long with a maximum height of 
164 feet above streambed. Concrete chute spillway 
is on east bank of river. Reservoir has a 
total storage capacity of 32,400 acre-feet, of 
which 23,000 acre-feet is for flood control, 
equivalent to 8.2 inches of runoff from controlled 
net drainage area of 52.3 square miles. 
Remaining 9,400 acre-feet of storage, equivalent 
to 3.4 inches of runoff, is for future water 
supply. Littleville Reservoir will be operated in 
conjunction with Knightville Reservoir when 
flows on Westfield River are expected to exceed 
channel capacity. It would also be operated in 
conjunction with other existing or proposed 
reservoirs to reduce floodflows on lower 
Connecticut River. Littleville project was 
authorized as a single-purpose flood control 
project. Under provision of title III of 
PL 85-500 (Water Supply Act of 1958) city of 
Springfield, Mass., furnished assurances for participating 
in cost of project including provisions 
for future water supply. Total cost of new work 
was $5,863,400 for construction and 
$1,150,000 for lands and damages, including 
relocation of a highway, utilities, cemeteries, 
and structures, a total of $7,013,400. (See Table 
1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938, and Title III, Water 
Supply Act of 1958 applies and fully complied 
with. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activity. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenances 
was initiated under a multicomponent 
contract in June 1962 and completed in 
September 1965. 
49J. NORTH HARTLAND LAKE, VT. 
Location. Dam is on Ottauquechee River, 1.5 
miles above its junction with Connecticut River 
and 1 mile northwest of North Hartland, Vt. 
Reservoir extends upstream 5.5 miles. (See 
Geological Survey map for Hanover, N.H.-Vt.) 
Existing project. A rolled-earthfill dam, 1,520 
feet long, 185 feet above streambed, providing a 
total storage capacity of 71,400 acre-feet. A 
side-channel spillway with a concrete weir 450 
feet long provided on left bank. Outlet consists 
of a 14-foot diameter tunnel cut through rock 
and located in left bank, a concrete intake and 
gate-operating tower, and hydraulically operated 
control gates. An outlet channel returns discharge 
to main stream below dam. An earth dike 
2,100 feet long with a maximum height of 52 
feet is across a saddle south of main dam. 
Drainage area controlled is 220 square miles or 
practically all of drainage area of Ottauquechee 
River. Reservoir is operated as a unit of a 
coordinated system of reservoirs for flood control 
in Connecticut River Basin. Latest cost 
estimate for new work is $6,331,000 for construction 
and $963,000 for lands and damages 
(including highway and utility relocations), a 
total of $7,294,000 for new work. Total 
includes an estimated $62,000 for additional 
recreation facilities to be constructed. (See 
Table 1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. New 
work: Surface treatment of pavement was completed 
by contract in September. Total contract 
costs amounted to $3,640. Maintenance: 
Ordinary operation and maintenance activities. 
Condition at end of fiscal year. Project is 
complete except for construction of additional 
recreation facilities. Construction of dam was 
initiated in June 1958 and completed in June 
1961. 
49K. NORTH SPRINGFIELD LAKE, VT. 
Location. Dam is in town of Springfield, Vt., 
on Black River, 8.7 miles above its junction with 
Connecticut River, and 3 miles northwest of 
Springfield, Vt. (See Geological Survey maps - 
Ludlow, Vt. and Claremont, N.H.) 
Existing project. A rolled-earthfill dam 2,940 
feet long with a maximum height of 120 feet 
above riverbed. Side channel spillway in left 
abutment of dam has a crest length of 384 feet. 
A discharge channel, about 425 feet long, 
connects side channel section to a short basin 
which has a length of 200 feet. Outlet works 
consist of an approach channel, 735 feet long, a 
12.75-foot horseshoe-shaped concrete conduit, 
604 feet long, and discharges into spillway basin. 
Three hydraulically operated 5- by 12-foot slide 
gates in intake structure are provided to control 
releases. Reservoir has a flood control storage 
capacity of about 50,600 acre-feet. Drainage 
area controlled is 158 square miles, or 77 
percent of total drainage area of Black River. 
Reservoir is operated as a unit of a coordinated 
system of reservoirs for flood control in 
Connecticut River Basin. Cost for new work is 
$4,782,000 for construction and $2,050,000 for 
lands and damages, including highway, cemetery, 
and utility relocations, a total of 
$6,832,000 for new work. (See Table 1-B at end 
of chapter for Acts authorizing existing project.) 
1-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operation and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam was initiated in 
May 1958 and completed in November 1960. 
49L. OTTER BROOK LAKE, N.H. 
Location. Dam is on Otter Brook, 2.4 miles 
upstream from its junction with The Branch, 
which flows 2.5 miles to Ashuelot River at 
Keene. (See Geological Survey maps - Keene, 
N.H.-Vt., and Monadnock, N.H.) 
Existing project. Dam is rolled-earthfill type 
with rockfill slope protection. It has a top length 
of 1,288 feet, a top width of 25 feet, accommodating 
a paved access road, and a maximum 
height of 133 feet above streambed. Outlet 
works, on right bank, are founded on bedrock 
and consist of a 6-foot diameter horseshoeshaped 
conduit 540 feet long controlled by 
three hydraulically operated slide gates. Spillway 
is in a natural saddle in right abutment, separated 
from dam by a rock knob. Weir is a low 
concrete ogee section founded on bedrock and 
145 feet long at spillway crest elevation 781. 
Reservoir operated for flood control purposes, 
has a storage capacity of 17,600 acre-feet, and 
permanent storage capacity of 700 acre-feet 
totaling 18,300 acre-feet, equivalent to 7.3 
inches of runoff from its drainage area of 47 
square miles. Project is operated as a unit of a 
coordinated system of reservoirs for flood control 
in Connecticut River Basin. Total cost for 
new work was $2,682,600 for construction and 
$1,378,400 for lands and damages, including 
highway relocation, a total of $4,061,000 for 
new work. (See Table 1-B at end of chapter for 
Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in September 1956 and 
completed in August 1958. 
49M. PARK RIVER, HARTFORD, CONN. 
Location. On the Park River in the City of 
Hartford, Hartford County, Connecticut. (See 
Geological Survey map of Hartford North, 
Connecticut.) 
Existing project. Authorized as a modification 
to completed Hartford, Conn. local protection 
project. (For Details on completed project see 
Annual Report for 1960.) Two sections of 
reinforced concrete conduit totaling 2,569 feet 
with width of 34 feet and height of 26.5 feet on 
the Park River; one section of reinforced concrete 
conduit 103 feet long, 36 feet wide and 
27.5 feet high on the South Branch; three 
sections of reinforced concrete conduit 1,467 
feet long, 22 feet wide and 25 feet high on the 
North Branch; a reinforced concrete junction 
structure to combine the flows from the North 
and South Branches and distribute them to the 
Park River and auxiliary conduits and thence to 
the Connecticut River; circular auxiliary conduit 
approximately 9,200 feet long to be constructed 
as a deep tunnel in rock with an inside diameter 
of 22 feet and lined with 2-foot thick concrete 
walls, an inlet structure and an outlet structure; 
a concrete headwall at the entrance to the North 
Branch conduit extension; and two pumping 
stations on the banks of the Park River. The 
latest approved cost estimate (November 1974) 
for new work is $1,400,000 for lands including 
relocations and $69,700,000 for construction, a 
total of $71,100,000. Total includes local costs 
of $1,000,000 for lands and $400,000 for 
relocations a total of $1,400,000. (See Table 1-B 
at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Provide all lands, easements 
and rights-of-way for construction and 
operation of project; hold and save the United 
States free from damages due to construction 
works; maintain and operate all works after 
completion; upon completion of conduit construction 
replace pavements, sidewalks, drainage 
and other appurtenances, including those at 
Broad Street, Flower Street and Laurel Street 
and bear cost of removal, replacement and 
modification to sewers, drains, utilities or highways 
beyond the area required for excavation 
and construction of the project; prevent changes 
in headpool ponding areas which would decrease 
the effectiveness of the improvements and if 
ponding areas and capacities are impaired, 
promptly substitute equivalent storage capacity; 
and undertake all practical measures to prevent 
pollution from entering the Park River conduit 
system. 
Operations and results during fiscal year. New 
work: Advanced engineering and design was 
continued. 
Condition at end of fiscal year. Construction 
has not been started. Preconstruction planning is 
approximately 82 percent complete. 
1-28

NEW ENGLAND DIVISION 
49N. SUCKER BROOK DAM, CONN. 
Location. Damsite is about 2 miles southwest 
of Winsted, Conn., on Sucker Brook, in town of 
Winchester, Conn., about 400 feet upstream 
from the brook's entrance into Highland Lake. 
Sucker Brook is a subtributary of Farmington 
River in Connecticut River Basin. (See Geological 
Survey map for Winsted, Conn.) 
Existing project. Dam is a rolled-earthfill 
structure with a length of 1,160 feet and a 
maximum height of 68 feet above streambed. A 
concrete uncontrolled chute spillway, 60 feet 
long, and a spillway channel were constructed at 
northeast end of dam for carrying reservoir 
overflow around the dam into Highland Lake. 
Capacity of reservoir, for flood control storage, 
is 1,480 acre-feet, equivalent to 8 inches of 
runoff from the intercepted drainage area of 3.4 
square miles. Latest approved cost estimate for 
new work is $2,550,000 for construction and 
$180,000 for relocations and lands and damages, 
a total of $2,730,000. Total includes local costs 
of $505,000 for lands, relocations and modifications 
to Highland Lake Dam. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Fully complied with. For 
further details of local requirements, see Annual 
Report for 1974. 
Operations and results during fiscal year. New 
work: Contract was awarded in August 1974 for 
fish passage facilities in the amount of 
$49,567. All work substantially complete in 
December 1974 except for topsoiling and seeding 
which was completed in May 1975. 
Condition at end of fiscal year. Construction 
of the dam and appurtenant work was initiated 
in September 1966 and completed in June 1971. 
Construction of fish weirs in the outlet channel 
is complete. Final cost-sharing with State 
remains to be determined by audit. 
490. SURRY MOUNTAIN LAKE, N.H. 
Location. Dam is on Ashuelot River, 34.6 
miles above its junction with Connecticut River 
and 5 miles north of Keene, N.H. (See Geological 
Survey maps for Keene and Bellows Falls, 
N.H.-Vt.) 
Existing project. Dam is rolled-earth type with 
a dumped rock shell and a downstream rock toe. 
It has a top length of 1,670 feet, a top width of 
30 feet, and 86 feet above riverbed. Spillway is 
at right end of dam and of open side-channel 
type with a low concrete weir 338 feet long. 
Spillway discharge channel is in rock cut and 
2,000 feet long. Outlet works, in right abutment, 
consist of a 748-foot-long intake channel 
and a 10-foot-diameter, horseshoe-shaped tunnel 
through rock. The tunnel is 383 feet long and 
discharges into spillway channel. Outlet works 
are controlled by two 4-foot 6-inch by 10-foot 
broome gates mechanically operated through a 
shaft from a gatehouse above. Reservoir is 
operated for flood control purposes and has a 
storage capacity of 32,500 acre-feet, equivalent 
to 6.1 inches of runoff from its drainage area of 
100 square miles. Estimated cost of new work 
for project is $2,305,000 for construction and 
$385,000 for lands and damages, a total of 
$2,690,000. Project is a unit of comprehensive 
plan for flood control and other purposes in 
Connecticut River Basin. (See Table 1-B at end 
of chapter for Acts authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in August 1939 and completed 
in June 1942. Initial phase of additional 
recreational facilities completed in September 
1969. 
49P. TOWNSHEND LAKE, VT. 
Location. Dam is on West River, 19.1 miles 
above its junction with Connecticut River at 
Brattleboro, Vt., and about 2 miles west of, 
Townshend, Vt. Reservoir extends upstream 
about 4 miles. (See Geological Survey 
maps - Saxtons River, Vt., and Londonderry, 
Vt.) 
Existing project. A rolled-earthfill dam, 1,700 
feet long at its crest, 133 feet above streambed, 
and providing a total storage capacity of 33,600 
acre-feet for flood control purposes. A sidechannel 
spillway with a concrete weir 438.9 feet 
long, having a discharge capacity of 201,000 
cubic feet per second, in left abutment. A 
reinforced concrete conduit under dam and on 
rock comprises outlet works and is controlled by 
mechanically operated gates from a gate tower 
at intake end. Drainage area controlled is 278 
square miles gross and 106 square miles net. 
Reservoir is operated as a unit of a coordinated 
system for flood control in Connecticut River 
Basin. Estimated cost of new work is 
$5,530,000 for construction and $1,870,000 for 
lands and damages including highway relocations 
and utilities, a total of $7,400,000. (See Table 
1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
1-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. Contract for repairs to discharge 
channel awarded October 1974 in the amount of 
$19,215. Final payment was made in June 1975 
for $20,319. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in November 1958 and 
completed in June 1961. Initial phase of additional 
recreational facilities completed in 
October 1969. Secondary phase completed in 
September 1971. 
49Q. TULLY LAKE, MASS. 
Location. Dam is on East Branch of Tully 
River, 3.9 miles above its junction with Millers 
River. It is 1 mile north of Fryville, Mass., and 
3.5 miles north of Athol, Mass. (See Geological 
Survey map for Royalston, Mass.-N.H.) 
Existing project. Dam is rolled-earth type with 
a dumped rock shell. It has a top length of 1,570 
feet, a top width of 30 feet, and 62 feet above 
riverbed. Spillway is on rock in a saddle about 
800 feet from left end of dam and is a low, 
concrete weir, 255 feet long. Spillway approach 
channel is 600 feet long and discharge channel is 
chute type 1,775 feet long. Outlet works, in left 
abutment, consist of a 6-foot-diameter tunnel 
through rock. Tunnel is 274 feet long and 
controlled by two 3-foot 6-inch by 6-foot slide 
gates mechanically operated through a shaft 
from a gatehouse above. Outlet works intake 
and outlet channels are 500 and 580 feet long, 
respectively. Project was constructed with provision 
for future raising for inclusion of power at 
site. Reservoir is operated for flood control 
purposes and has a storage capacity of 22,000 
acre-feet which is equivalent to 8.3 inches of 
runoff from its drainage area of 50 square miles. 
Estimated cost of new work is $1,383,600 for 
construction and $368,000 for lands and damages, 
a total of $1,751,600. Total includes 
$100,000 as local share of additional recreation 
facilities to be constructed. Project is a unit of 
comprehensive plan for flood control and other 
purposes in Connecticut River Basin. (See Table 
1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. Local interests must also 
bear 50 percent of future recreation development 
in accordance with 1965 Federal Water 
Project Recreation Act. 
Operations and results during fiscal year. New 
work: Planning and design of recreational facilities 
consisting of rest rooms, parking area, access 
road, utilities and cuamping area was initiated. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete except for construction of recreation 
facilities. Construction of dam and appurtenant 
works was initiated in March 1947 and completed 
in September 1949. 
49R. UNION VILLAGE DAM, VT. 
Location. Dam is on Ompompanoosuc River, 
4 miles above its junction with Connecticut 
River. It is one-fourth mile north of Union 
Village, Vt., and 11 miles north of White River 
Junction, Vt. (See Geological Survey maps for 
Strafford, Vt., and Mount Cube, N.H.-Vt.) 
Existing project. Dam is rolled-earth type with 
a dumped rock shell. It has a top length of 1,100 
feet, a top width of 30 feet, and a maximum 
height of 170 feet. Spillway is about 350 feet 
from right end of dam and is chute type with a 
low, curved 400-foot long concrete weir. 
Approach channel and discharge chute are 1,000 
and 1,130 feet long, respectively. Outlet works 
are in left abutment and consist of a 1,236-footlong 
13-foot-diameter tunnel through rock. Outlet 
works are controlled by two 7-foot 6-inch by 
12-foot broome gates mechanically operated 
through a shaft from a gatehouse above. Reservoir 
is operated for flood control purposes and 
has a storage capacity of 38,000 acre-feet, which 
is equivalent to 5.7 inches of runoff from its 
drainage area of 126 square miles. Cost of 
completed project was $3,102,400 for construction 
and $908,300 for lands and damages, a 
total of $4,010,700. Project is a unit of comprehensive 
plan for flood control and other 
purposes in Connecticut River Basin. (See Table 
1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam was initiated in 
March 1947 and completed in June 1950. 
50. FOX POINT BARRIER, 
NARRAGANSETT BAY, R.I. 
Location. On Providence River at Fox Point, 
in city of Providence, R.I. (See Geological 
Survey map for Providence, R.I.) 
Existing project. A concrete hurricane barrier 
across Providence River and earth-dike land 
sections to high ground at east and west ends. 
1-30

NEW ENGLAND DIVISION 
Barrier is 700 feet long and dikes total 2,200 
feet. Concrete river section includes a pumping 
station, a river sluice gate and barrier structure, 
and tie walls to dikes. For further details see 
page 32 of 1974 Annual Report. Latest 
approved cost estimate for new work is 
$14,711,000 for construction and $1,134,000 
for lands and rights-of-way, a total of 
$15,845,000. Total cost includes local costs for 
all lands and a $3,679,500 cash contribution for 
construction. (See Table 1-B at end of chapter 
for Act authorizing existing project.) 
Local cooperation. Local interests must hold 
the United States free from damages, maintain 
and operate improvement after completion, and 
contribute in cash 30 percent of total cost, 
including lands, easements, and relocations. 
Total estimated costs for all requirements of 
local cooperation are $4,753,400. 
Operations and results during fiscal year. New 
work: Administrative costs were incurred in 
closing out the contract to correct deficiencies 
at Fox Point Hurricane Barrier. 
Condition at end of fiscal year. Project is 
complete. Barrier contract was initiated in July 
1961 and completed in January 1966. 
51. HAYWARD CREEK, QUINCYBRAINTREE, 
MASS. 
Location. The Hayward Creek watershed 
covers about 600 acres in the City of Quincy 
and the Town of Braintree and is located on 
Massachusetts Bay about eight miles south of 
Boston, Mass. 
Existing project. The local protection project 
will consist of a 2,800 foot reinforced concrete 
pipe conduit system to convey flows along 
Lower Hayward Creek to Fore River; 150 feet 
of concrete flood wall and 100 feet of earth dike 
near the southeast portion of Hayward Pond; an 
earth dam upstream of the upper end of 
Hayward Pond; channel diversion of Echo 
Creek; a 4-foot increase in the height of Hayward 
Pond Dam; improvement of the Hayward 
Creek channel from the Hayward Pond outlet to 
West Howard Street near the Quincy-Braintree 
town, line; and preservation of a natural greenbelt 
area of about 33 acres at Hayward Pond and 
the wetlands upstream for flood control storage 
and potential public use. Latest approved cost 
estimate for new work is $400,000 for lands 
including relocations and $1,500,000 for construction, 
a total of $1,900,000. (See Table 1-B 
at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Local interests are required 
to provide without cost to United States all 
lands, easements, rights-of-way and utility relocation 
necessary for project, presently estimated 
at $400,000; maintain and operate all 
works after project completion; and prevent 
further encroachment in the natural flood plain 
of the stream. Section 205 of Public Law 87-874 
applies. By letter dated 8 April 1974, the 
Commissioner of the Massachusetts Department 
of Public Works endorsed the project and 
provided preliminary assurances of local 
cooperation. 
Operation and results during fiscal year. New 
work: Preparation of plans and specifications 
were initiated in January 1975. 
Condition at end of fiscal year. Construction 
has not yet started. 
52. HOUSATONIC RIVER BASIN, CONN. 
Authorized improvements in Housatonic River 
Basin are comprised of seven flood control 
reservoirs on tributaries of the Naugatuck River, 
principal tributary of Housatonic River, and 
three local protection projects, two of which are 
along Naugatuck River and one on Still River. 
Naugatuck and Housatonic Rivers converge 12 
miles above mouth of Housatonic River. (See 
Table 1-B at end of chapter for Acts authorizing 
existing project; also Table 1-K on dams and 
reservoirs and local protection project for 
Housatonic River Basin.) 
52A. ANSONIA-DERBY, CONN. 
Location. On Naugatuck River in cities of 
Ansonia and Derby, Conn., about 2 miles 
upstream from confluence of Naugatuck and 
Housatonic Rivers. (See Geological Survey map 
for Ansonia, Conn.) 
Existing project. Construction of about 7,600 
feet of dikes, 7,500 feet of floodwalls, and 
5,700 feet of channel improvement along the 
Naugatuck River. Four pumping stations with 
total capacity of 183,900 gallons per minute 
would be constructed to discharge interior drainage. 
Other appurtenant structures would consist 
of 4 railroad and 5 street swing gates. Protection 
would also be provided along Beaver Brook 
tributary consisting of 1,800 feet of dikes, 1,900 
feet of channel improvement, and 1,030 feet of 
8- by 14.5-foot reinforced concrete conduit. For 
further details, see page 32 of 1974 Annual 
Report. Latest approved cost estimate is 
$17,850,000 for construction and $1,050,000 
for lands, damages, and relocations, a total of 
$18,900,000 for new work. This total includes 
local costs of $1,050,000 for lands and reloactions. 
(See Table 1-B at end of chapter for Act 
authorizing existing project.) 
1-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Fully complied with. Local 
interests must provide lands and rights-of-way 
for construction, including relocations; hold the 
United States free from damages; maintain and 
operate all works; prevent encroachment on 
improved channels and ponding areas and provide 
effective storage or pumping capacity if 
impaired. Estimated costs to local interests are 
$650,000 for lands and $400,000 for 
relocations. 
Operation and results during fiscal year. New 
work: Miscellaneous land acquisition and 
project closeout administration continued. 
Condition at end of fiscal year. Project is 
complete. Construction of project was initiated 
in September 1968 and completed in January 
1973. 
52B. BLACK ROCK LAKE, CONN. 
Location. Damsite is on Branch Brook about 2 
miles upstream from its confluence with 
Naugatuck River in towns of Thomaston and 
Watertown, Conn. (See Geological Survey map 
for Thomaston, Conn.) 
Existing project. Construction of a rolledearthfill 
dam 933 feet long and a maximum 
height of 154 feet above streambed. An uncontrolled 
chute spillway 140 feet long is in right 
abutment. A 4- by 5-foot reinforced concrete 
conduit constructed in rock along right bank 
provides control by means of two 3- by 4-foot 
hydraulically operated gates. Reservoir is about 
1.8 miles long and provides storage capacity of 
8,700 acre-feet, including 270 acre-feet for 
recreation pool, equivalent to 8 inches of runoff 
from its tributary drainage area of 20.4 square 
miles. Construction of project required relocating 
1.9 miles of State road and relocation of a 
36-inch local water supply line and appurtenant 
structures. Cost of completed project is 
$5,223,700 for construction and $2,958,600 for 
lands and damages, including roads and utilities 
relocation, a total of $8,182,300. (See Table 1-B 
at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. However local interests 
must establish encroachment lines downstream 
of dam to permit efficient reservoir operation. 
State legislation requires establishment of such 
lines. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
activities. 
Condition at end of fiscal year. Project 
complete. Road relocation completed 
November 1967. Contract for construction 
is 
in 
of 
dam and appurtenances was awarded in July 
1967 and completed in July 1971. 
52C. DANBURY, CONN. 
Location. On Still River in city of Danbury, 
Conn., about 45 miles southwest of Hartford. 
(See Geological Survey map for Danbury, 
Conn.) 
Existing project. Construction of 3,625 feet of 
rectangular reinforced concrete conduit and 
2,695 of riprapped trapezoidal channel; replacement 
of four railroad bridges and two highway 
bridges and removal of a private road bridge. 
Approved cost estimate (July 1974) for new 
work is $2,120,000 for lands including relocations 
and $14,100,000 for construction, a total 
of $16,220,000. Total includes local costs of 
$780,000 for lands and $1,340,000 for relocations, 
a total of $2,120,000. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Local interests must provide 
all lands, easements, and rights-of-way for 
construction, including lands for spoil disposal, 
storm water pondage and collector ditches together 
with necessary changes to sewage systems, 
highway bridges and roads, railroad track 
except railroad bridges and approaches, and 
other utilities; hold the United States free from 
damages; maintain and operate all works after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; prevent 
encroachment on improved channels and 
on ponding areas and if capacity of latter is 
impaired, provide equally effective storage, 
pumping capacity or both. Estimated cost to 
local interests is $2,120,000. Formal assurances 
were signed by the Mayor of Danbury on 24 
March 1972. The City Solicitor of Danbury 
approved of the agreement on 12 June 1972 in 
accordance with Section 221 of P.L. 91-611. 
Assurances were received from the State of 
Connecticut through its Department of Environmental 
Protection on 16 November 1972. 
Operations and results during fiscal year. New 
work: Construction of the Danbury local protection 
project by multicomponent contract was 
initiated in July 1974. Contract is 31 percent 
complete and contract earnings have totaled 
$3,801,000. Work by contract for railroad relocation 
was initiated in March 1975. Contractor 
earnings were $25,500 with work 7 percent 
complete. A contract in the amount of 
$615,875 for railroad bridge and channel 
improvement was awarded in November 1974. 
Contract is 37 percent complete and contract 
earnings have totaled $196,000. 
Condition at end of fiscal year. Project is 
under construction. 
1-32

NEW ENGLAND DIVISION 
52D. DERBY, CONN. 
Location. At confluence of Naugatuck and 
Housatonic Rivers in city of Derby, Conn., 
about 35 miles southwest of Hartford and 12 
miles north of Long Island Sound. (See Geological 
Survey map for Ansonia, Conn.) 
Existing project. Construction of system of 
earthfilled levees and concrete floodwalls extending 
about 2,050 feet along the bank of 
Housatonic River and about 3,200 feet along 
Naugatuck River. System would also include 
flood gates at railroad crossings and a pumping 
station near the confluence of the two rivers to 
handle interior drainage. Dike along Naugatuck 
River ties into lower end of the completed 
Ansonia-Derby project. Approved cost estimate 
(1974) for new work is $590,000 for lands 
including relocations and $7,600,000 for construction, 
a total of $8,190,000. Total includes 
local costs of $535,000 for lands and $55,000 
for relocations. (See Table 1-B at end of chapter 
for Act authorizing existing project.) 
Local cooperation. Local interests must provide 
all lands, easements, and rights-of-way for 
construction including land for spoil disposal, 
storm water pondage and collector ditches 
together with necessary changes to sewage systems, 
highway bridges and roads, railroad track 
except railroad bridges and approaches, and 
other utilities; hold the United States free from 
damages; maintain and operate all works after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; prevent 
encroachment on improved channels and 
on ponding areas and if capacity of latter is 
impaired, provide eqtually effective storage, 
pumping capacity, or both, without cost to the 
United States; and, prevent encroachment within 
20 feet of the top of the west bank of 
Naugatuck River at proposed channel widening 
upstream from highway bridge at Derby. Estimated 
cost to local interests is $590,000. 
Formal assurances were accepted 24 September 
1968 from the City of Derby and the State 
of Connecticut. Local interests have accomplished 
real estate acquisition necessary for 
construction. 
Operations and results during fiscal year. New 
work: Administrative costs incurred in project 
finalization. 
Condition at end of fiscal year. Project is 
complete. Railroad relocation was initiated in 
September 1970 and completed in August 1973. 
Contract for construction of local protection 
project was awarded in May 1970 and completed 
in June 1973. 
52E. HANCOCK BROOK LAKE, CONN. 
Location. Dam is on Hancock Brook in town 
of Plymouth, Conn., about 3.4 miles above its 
confluence with Naugatuck River. (See Geological 
Survey map for Waterbury, Conn.) 
Existing project. A rolled-earthfill dam 630 
feet long and a maximum height of 57 feet 
above streambed. A chute spillway with a 
concrete ogee weir, 100 feet long, in right 
abutment. Outlet works consist of an ungated, 
3- by 4-foot 6-inch reinforced concrete conduit 
founded on rock on right bank of stream. 
Reservoir, which is entirely within town of 
Plymouth, Conn., will extend up Hancock 
Brook about 1.5 miles and about 1.3 miles up 
Todd Hollow Brook, principal tributary of 
Hancock Brook. It will provide a flood control 
storage capacity of 4,030 acre-feet equivalent to 
6.33 inches of runoff from tributary drainage 
area of 12 square miles. Cost for new work for 
completed project was $1,595,000 for construction 
and $2,585,000 for lands and damages 
including relocation of roads and railroads, a 
total of $4,180,000. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. However, local interests are 
specifically required to establish encroachment 
lines downstream of dam to permit efficient 
reservoir operation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
structures was initiated in July 1963 and completed 
in August 1966. 
52F. HOP BROOK LAKE, CONN. 
Location. Damsite is on Hop Brook in city of 
Waterbury and towns of Middlebury and 
Naugatuck, Conn., about 1.4 miles upstream of 
confluence of Naugatuck River and Hop Brook. 
(See Geological Survey map for Waterbury, 
Conn.) 
Existing project. Construction of a rolledearthfill 
dam about 520 feet long with a 
maximum height of 97 feet above streambed. A 
dike about 404 feet long with a maximum 
height of 33 feet closes a saddle in left abutment. 
A chute spillway with a broad-crested 
weir 200 feet long is founded on rock 1,200 feet 
northeast of left abutment of dam. A 3- by 
5-foot reinforced concrete conduit constructed 
along left bank of brook controls flows by 
means of two 3- by 4-foot hydraulically operated 
gates. Reservoir, about 1.5 miles long, is in 
1-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
towns of Middlebury and Naugatuck and city of 
Waterbury, Conn., and provide storage capacity 
of 6,970 acre-feet, which includes 120 acre-foot 
recreation pool, equivalent to 8 inches of runoff 
from tributary drainage area of 16.4 square 
miles. Construction of project required relocation 
of 1.8 miles of State Route 63. Latest 
approved cost estimate for new work is 
$2,558,000 for construction and $3,450,000 for 
lands, rights-of-way, and relocation of roads, a 
total of $6,008,000. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. However local interests 
must establish encroachment lines downstream 
of dam to permit efficient reservoir operation. 
State legislation requires establishment of such 
lines. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
structures was initiated in December 1965 and 
completed in December 1968. Construction of a 
public use facility was completed in November 
1973. 
52G. LEE, MASS. 
Location. On the Housatonic River in the 
town of Lee in western Massachusetts about 10 
miles south of Pittsfield, Massachusetts and 
about 8 miles east of the New York state line. 
Existing project. An emergency bank protection 
project consisting of placement of a twofoot 
thick layer of stone slope protection along 
a 360-foot reach of the Housatonic River bank 
in Lee. The project will prevent further river 
bank erosion and protect a sewer main and 
inverted siphon structure which lead to the Lee 
sewage treatment plant. Latest cost estimate for 
new work is $42,400. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: Construction was accomplished by contract 
awarded 31 October 1974 in the amount 
of $21,200 and completed in February 1975. 
Condition at end of fiscal year. Project is 
complete. 
52H. NORTHFIELD BROOK LAKE, CONN. 
Location. Dam is on Northfield Brook about 
1.3 miles upstream from its confluence with 
Naugatuck River, in town of Thomaston, Conn. 
(See Geological Survey map for Thomaston, 
Conn.) 
Existing project. A rolled-earthfill dam, 810 
feet long and a maximum height of 118 feet 
above streambed. A chute spillway, with an ogee 
weir, 72 feet long, on rock in left abutment of 
dam. Outlet works consist of an ungated 36-inch 
reinforced concrete conduit founded on rock on 
right bank of stream. Reservoir is about 1.2 
miles long, within towns of Thomaston and 
Litchfield, Conn., and will have a flood control 
storage capacity of 2,432 acre-feet, equivalent to 
8 inches of runoff from 5.7 square mile drainage 
area. Cost for new work was $1,856,000 for 
construction and $975,000 for lands and 
damages, including roads and utility relocations, 
a total of $2,831,000. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. However, local interests 
must establish encroachment lines downstream 
of dam to permit efficient reservoir operation. 
Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
activities. Contract awarded 7 October 
1974 for rehabilitation of comfort station. 
Contract work was completed in May 1975 at a 
cost of $48,349. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenances 
was initiated in May 1963 and completed 
in October 1965. Construction of recreation 
facilities was initiated in November 1966 and 
completed in August 1967. 
521. THOMASTON DAM, CONN. 
Location. On Naugatuck River about 30.4 
miles above its junction with Housatonic River 
and about 1.6 miles north of Thomaston, Conn. 
Reservoir extends upstream about 6.4 miles. 
(See Geological Survey map for Thomaston, 
Conn.) 
Existing project. A rolled-earthfill and rock 
dam 2,000 feet long rising 142 feet above 
streambed and providing a storage capacity of 
42,000 acre-feet. Spillway consists of an open 
side channel constructed in rock and a low 
concrete weir. Outlet consists of a concrete 
conduit. Control is accomplished by gates 
mechanically operated through a shaft from a 
house above. Drainage area controlled is 97 
square miles. Reservoir is operated for flood 
protection of Waterbury and other communities 
downstream on Naugatuck River. Cost for new 
work was $6,382,000 for construction and 
$7,900,000 for lands and damages, including 
highway, railroad, and utility relocations, a total 
of $14,282,000. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
1-34

NEW ENGLAND DIVISION 
Local cooperation. Section 3, Flood Control 
Act of 1944 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was started in May 1958 and completed 
in November 1960. 
53. MERRIMACK RIVER BASIN, N.H. 
AND MASS. 
Works covered by comprehensive plan are on 
Merrimack River and its tributaries in New 
Hampshire and Massachusetts. Flood Control 
Act of 1936 authorized construction of a system 
of flood control reservoirs in Merrimack River 
Basin for reduction of flood heights in Merrimack 
Valley. Flood Control Act of 1938 
approved general comprehensive plan for flood 
control and other purposes as approved by Chief 
of Engineers pursuant to preliminary examinations 
and surveys authorized by act of June 22, 
1936, and modified project to provide in addition 
to construction of a system of flood control 
reservoirs, related flood control works which 
may be found justified by the Chief of 
Engineers. All operations pertaining to flood 
control in Merrimack River Basin are now 
carried on under and reported under projects for 
individual units of comprehensive plan referred 
to above. No further expenditures are contemplated 
under general project for flood control in 
Merrimack River Basin. For final cost and 
financial summary, see Annual Report for 1946. 
A comprehensive plan for development of 
water resources of the North Nashua River 
Basin, a principal tributary of the Merrimack 
River, was authorized by 1966 Flood Control 
Act substantially in accordance with Senate 
Document 113, 89th Congress. Plan provides for 
construction of coordinated system of four 
reservoirs and three local protection projects for 
flood protection, water supply, recreation and 
allied purposes. 
The 1966 Flood Control Act also authorized 
construction of Saxonville local protection 
project substantially in accordance with Senate 
Document 61, 89th Congress. (See Table 1-L at 
end of chapter for reservoirs and related flood 
control works included for construction under 
comprehensive plan.) 
53A. BLACKWATER DAM, N.H. 
Location. Dam is on Blackwater River, N.H., 
8.2 miles above confluence with Contoocook 
River and 118.8 miles above mouth of Merrimack 
River. It is in town of Webster, just 
above village of Swetts Mills, 12.5 miles by 
highway northwest of Concord, N.H. (See 
Geological Survey maps for Penacook and 
Mount Kearsarge, N.H.) 
Existing project. Dam is rolled-earth type with 
a dumped rock blanket on upstream face and a 
downstream rock toe. It has a top length, 
including spillway, of 1,150 feet, a top width of 
39 feet and a maximum height, above riverbed, 
of 75 feet. There are also two earth dikes on 
west side of reservoir with respective lengths of 
420 and 1,230 feet and a respective maximum 
height of 18 and 30 feet. Spillway is concrete, 
gravity type 240 feet long and has a 160-footlong 
approach channel and a 400-foot-long 
discharge channel. Outlet works are in spillway 
and consist of three conduits, each controlled by 
a 3-foot 6-inch by 5-foot 3-inch slide gate 
hydraulically operated from a gallery within 
spillway. Dam and appurtenant work contain a 
16-foot diameter penstock intake and were 
constructed to provide for future raising and 
inclusion of power at site. Reservoir is operated 
for flood control purposes and has a storage 
capacity of 46,000 acre-feet which is equivalent 
to 6.7 inches of runoff from its drainage area of 
128 square miles. Estimated cost of project is 
$837,000 for construction and $553,000 for 
lands and damages, a total of $1,390,000. Total 
includes an estimated $70,000 for construction 
of public use facilities. Project is a unit of 
comprehensive plan for flood control and other 
purposes in Merrimack River Basin. (See Table 
1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete except for construction of public use 
facilities. Construction of dam and appurtenant 
works was initiated in May 1940 and completed 
in November 1941. 
53B. EDWARD MACDOWELL LAKE, N.H. 
Location. Dam is on Nubanusit Brook, a 
tributary of Contoocook River, one-half mile 
upstream from village of West Peterborough, 
N.H., and 14 miles east of Keene, N.H. (See 
Geological Survey maps for Peterboro and 
Monadnock, N.H.) 
Existing project. Dam is rolled-earth type with 
a dumped rock blanket on upstream face and a 
downstream rock toe. It has a top length of 
1,030 feet, a top width of 25 feet, and a 
maximum height of 67 feet. Outlet works in 
1-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
west abutment of dam consist of an intake 
structure, a 7-foot square conduit which is 275 
feet long and controlled by 3- by 7-foot slide 
gates mechanically operated through a control 
tower from a gatehouse above, and a stilling 
basin emptying into pool of Verney Mills Dam. 
Spillway is a low, concrete weir, 100 feet long, 
with a 1,900-foot long approach channel, a 
3,080-foot long discharge channel, and a 
2,540-foot long protective dike to guide spillway 
discharge. Spillway is in a natural saddle on 
north side of reservoir about 3 miles from 
damsite and discharges into Ferguson Brook. 
Reservoir is operated for flood control purposes 
and has a storage capacity of 12,800 acre-feet, 
equivalent to 5.5 inches of runoff from its 
drainage area of 44 square miles. Completed cost 
of project is $1,708,300 for construction and 
$306,000 for lands and damages, a total of 
$2,014,300. Project is a unit of comprehensive 
plan for flood control and other purposes in 
Merrimack River Basin. Name "Edward 
MacDowell Dam" was adopted by section 206, 
Flood Control Act of 1950. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operations and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in March 1948 and completed 
in March 1950. 
53C. FRANKLIN FALLS DAM, N.H. 
Location. Dam is on Pemigewasset River, 
N.H., main tributary of Merrimack River, and 
about 2.5 miles upstream of Franklin, N.H. (See 
Geological Survey maps for Penacook and 
Holderness, N.H.) 
Existing project. Dam is rolled-earth type with 
a dumped rock shell. It has a top length of 1,740 
feet, a top width of 25 feet, and 140 feet above 
riverbed. Spillway is on rock in right abutment 
and is a low, concrete weir with a crest length of 
546 feet. Spillway approach and discharge channels 
are in earth and rock cut and are 1,785 and 
900 feet long, respectively. Outlet works are on 
right bank of river and consist of an intake 
channel 840 feet long, and two 22-foot 
horseshoe-shaped conduits each 542 feet long 
and each controlled by four broome gates 
operated through a control tower from a gatehouse 
above. Outlet works also have a stilling 
basin and an outlet channel with a length of 
2,350 feet. Reservoir is operated for flood 
control purposes and has a storage capacity of 
154,000 acre-feet, equivalent to 2.9 inches of 
runoff from its drainage area of 1,000 square 
miles. Cost of project is $6,190,000 for construction 
and $1,760,000 for lands and damages, 
a total of $7,950,000. Project is a unit of 
comprehensive plan for flood control and other 
purposes in Merrimack River Basin. (See Table 
1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in November 1939 and 
completed in October 1943. 
53D. HOPKINTON-EVERETT LAKES, N.H. 
Location. Hopkinton Dam is on Contoocook 
River, N.H., 17.3 miles above its junction with 
Merrimack River and about one-half mile upstream 
from village of West Hopkinton. Everett 
Dam is on Piscataquog River, N.H., 16 miles 
above its junction with Merrimack River and 
about 1.3 miles southeast of village of East 
Weare. Two interconnecting canals were 
provided to enable the two reservoir areas to 
function as one. (See Geological Survey maps 
for Hillsboro, N.H., and Concord, N.H.) 
Existing project. Included in overall project 
are 2 dams and spillways, .4 dikes and 2 
interconnecting canals. The 790-foot long 
Hopkinton Dam on Contoocook River is rolledearth 
construction with a maximum height of 76 
feet. Outlet works are provided in dam. A 
spillway is in a saddle 1.8 miles east of West 
Hopkinton. Two dikes with a total length of 
9,600 feet and a maximum height of 77 feet are 
included in this portion of project to close 
reservoir saddles. Everett Dam on Piscataquog 
River is 2,000 feet long of rolled-earth construction 
with a maximum height of 115 feet and a 
concrete spillway adjacent to dam. Outlet works 
are included in construction. Dikes for closing 
reservoir saddles, totaling 6,400 feet long and 
with a maximum height of 50 feet, are a part of 
this project. Reservoir formed by dams has a 
capacity of 70,800 acre-feet in Contoocook 
River Basin and 86,500 acre-feet in Piscataquog 
River Basin, a total of 157,300 acre-feet equivalent 
to 6 inches of runoff from a gross drainage 
area of 490 square miles. Two interconnecting 
canals, totaling 17,000 feet long and varying in 
bottom widths from 120 to 160 feet, have been 
constructed and are of sufficient capacity to 
1-36

NEW ENGLAND DIVISION 
cause storage areas to function as a single unit of 
a coordinated system of reservoirs for control of 
floods in Merrimack River Basin. Cost estimate 
for new work is $12,971,000 for construction 
and $8,737,000 for lands and damages, 
including relocation of roads, railroads, cemeteries, 
and utilities, a total of $21,708,000. Total 
includes an estimated $184,000 as local share of 
recreation facilities to be constructed. (See 
Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. Local interests must also 
bear 50 percent of future recreational development 
in accordance with 1965 Federal Water 
Project Recreation Act. 
Operations and results during fiscal year. New 
work: Contract for construction of comfort 
station was awarded in November 1974. Current 
contract price is $62,851. Contractor earnings to 
date are $59,174. Contract is 92 percent complete. 
Maintenance: Ordinary operation and 
maintenance activities. 
Condition at end of fiscal year. Project is 
complete except for construction of additional 
recreation facilities, for which planning is underway. 
Construction of two dams and appurtenant 
works was initiated- in November 1959 and 
completed in December 1962. 
53E. NOOKAGEE LAKE, MASS. 
Location. On Phillips Brook in Westminster, 
Worcester County, the north-central section of 
Massachusetts about 45 miles west of Boston. 
(See Geological Survey map for Fitchburg, 
Mass.) 
Existing project. Earth-filled dam about 2,150 
feet long with maximum height of 106 feet. A 
concrete side channel spillway with ogee weir 
205 feet long will be located in left abutment. A 
concrete drop inlet structure with a 48-inch 
concrete pipe will serve as uncontrolled outlet to 
maintain the water supply pool. An intake tower 
with two 2-foot gated outlets will regulate water 
supply out-flow. A single 4-foot by 7-foot 
emergency gate will be located in the intake 
structure immediately upstream of the service 
gates. Dam and appurtenances will impound a 
multi-purpose reservoir with total storage 
capacity of 8,400 acre-feet equivalent to 14.6 
inches of runoff from its drainage area of 11 
square miles. Of total storage, 3,900 acre-feet 
would be allocated for flood control, 800 
acre-feet for seasonal joint-use for flood control 
and water quality purposes, 700 acre-feet for a 
minimum conservation pool, and 3,000 acre-feet 
for water quality storage. The 140 acre permanent 
pool will offer opportunity for public 
outdoor recreation and will include day-use 
park-type recreation containing facilities for 
swimming, picnicking and fishing. The reservoir 
would be operated as an integral part of the 
comprehensive water resources development 
plan for the North Nashua River, a tributary of 
the Merrimack River. Latest approved cost 
estimate (July 1974) for new work is 
$3,410,000 for lands including relocations and 
$8,890,000 for construction, a total of 
$12,300,000. Project has been reformulated to 
exclude the authorized water supply storage and 
recreation purposes and to add water quality as 
a project purpose. The project is being reviewed 
as part of the development of an environmental 
quality (EQ) plan for the North Nashua River 
Basin. (See Table 1-B at end of chapter for Act 
authorizing existing project.) 
Local cooperation. Based on the reformulated 
project local interests are required to protect 
channels downstream of the reservoirs from 
encroachments which would adversely affect 
operation of the system; hold and save the 
United States free from all damages due to water 
rights claims resulting from construction and 
operation of the reservoirs; and exercise to the 
full extent of their legal capability, control 
against removal of water in the basin which will 
affect the reservoir's water quality storage and 
the development of dependable stream regulations; 
and exercise, to the full extent of their 
legal capability, control against removal of 
streamflow made available by reservoir storage 
for water quality. Formal assurances will be 
requested during final design. 
Operations and results during fiscal year. New 
work: Continued preparation of project reformulation 
report, including coordination with 
local interests and EPA, and review of project in 
light of development of an environmental 
quality plan for the North Nashua River Basin. 
Condition at end of fiscal year. Advance 
engineering and design is 65 percent complete; 
will resume upon approval of the project reformulation 
report by OMB and Congress, as 
needed or upon project status determination as 
defined in Basin EQ plan now being formulated. 
53F. SAXONVILLE, MASS. 
Location. On the Sudbury River in the village 
of Saxonville in the northeasterly part of the 
Town of Framingham, Middlesex County about 
20 miles west of Boston, Massachusetts. (See 
Geological Survey map for Framingham, Mass.) 
Existing project. About 2,900 feet of earth 
dikes, 750 feet of concrete floodwalls, vehicular 
flood gate, railroad stoplog structure, pumping 
station and appurtenant structures all located 
1-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
along the left bank of the river. In addition 
about 1,200 feet of existing channel will be 
straightened with 60-foot bottom width. Latest 
approved cost estimate (July 1974) for new 
work is $480,000 for lands including relocations 
and $3,770,000 for construction, a total of 
$4,250,000. Total includes local costs of 
$460,000 for lands and $20,000 for relocations, 
a total of $480,000. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Local interests must 
provide all lands, easements and rights-of-way 
for construction; hold and save United States 
free from damages due to construction works; 
maintain and operate all works after completion; 
provide all alterations and replacements of 
existing utilities including bridges, highways, 
sewers and railroad modifications and relocations 
except for railroad bridges and bridge 
approaches; prevent encroachment on both 
improved and unimproved channel through 
Saxonville; and prohibit encroachment on 
ponding areas and, if capacity of these areas is 
impaired, provide suitable ponding capacity or 
equivalent pumping capacity. Estimated cost to 
local interests is $480,000. All required assurances, 
consistent with the requirements of 
Section 221 of the 1970 Flood Control Act, 
have been received and approved by the Secretary 
of the Army. 
Operations and results during fiscal year. New 
work: Advanced engineering and design was 
completed. 
Condition at end of fiscal year. Construction 
has not been started. Contract plans and specifications 
were completed in April 1975. Initiation 
of construction dependent upon future 
appropriations. 
54. NEW BEDFORD, FAIRHAVEN, AND 
ACUSHNET, MASS. 
Location. Main harbor barrier is across New 
Bedford and Fairhaven Harbor in vicinity of 
Palmer Island. Supplemental dikes and walls are 
provided in Clark Cove area of New Bedford and 
Fairhaven. (See Geological Survey maps for New 
Bedford North, New Bedford South, Marion, 
and Sconticut Neck, Mass., and Coast and 
Geodetic Survey Charts 249, 252, and 1210.) 
Existing project. A 4,500-foot earthfill dike, 
with rock faces and toes and a top width of 20 
feet. A gated opening, 150 feet wide, is included 
in section of barrier between Palmer Island and 
Fairhaven mainland to accommodate navigation. 
Closure of navigation opening in barrier accomplished 
by sector gates with concrete abutments 
and sill founded on rock. Each gate has a radius 
of 90 feet, a central angle of 60 degrees, and a 
total height of 59 feet. Gates are opened and 
closed by means of a rack and pinion drive. 
Controls are arranged so that gates can be 
operated singly or simultaneously from either of 
two control houses, one on each abutment. Two 
gated conduits are constructed in section of 
barrier between New Bedford and Palmer Island, 
each consisting of two separate conduits side by 
side, each 6 feet wide by 9 feet high. These 
conduits will permit emergency emptying of 
pool above barrier. A dike extension of earthfill 
with rock facing runs south for 3,600 feet from 
western end of harbor barrier. Closure to high 
ground is effected by 1,000 feet of dike of 
earthfill with rock facing running westward. 
Protection in Clark Cove area consists of 5,800 
feet of earthfill, rock-faced dike, running 2,700 
feet across head of Clark Cove, then south along 
east shore of cove for about 2,400 feet. At west 
end, closure to high ground is accomplished by a 
dike constructed of earthfill with rock facing, 
600 feet long and at east end by a similar dike 
100 feet long. The 3,100-foot long Fairhaven 
dike is constructed of earthfill with rock facing. 
Cost of completed project is $17,997,900 for 
construction, and $616,500 for lands, right-ofway 
and relocations, a total of $18,614,400. 
This total includes local costs of $590,560 for 
lands and relocations and a $6,513,763 cash 
contribution. (See Table 1-B at end of chapter 
for Act authorizing existing project.) 
Local cooperation. Local interests must contribute 
30 percent of first cost, including lands 
and rights-of-way; contribute capitalized value 
of annual maintenance and operation 
($1,520,000) for main harbor barrier; hold the 
United States free from damages; and maintain 
and operate improvement except main harbor 
barrier after completion. Total costs for all 
requirements of local cooperation are 
$7,104,323. Local requirements fully complied 
with. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. A contract was awarded in May 
1975 for relocation of stop gates in the amount 
of $24,400. There were no earnings this fiscal 
year. 
Condition at end of fiscal year. Project is 
complete. Construction of barrier and appurtenances 
was initiated in October 1962, and 
completed in January 1966. Construction of the 
pumping station was initiated in October 1962 
and completed in June 1964. 
55. NEW LONDON, CONN. 
Location. In the city of New London, Conn., 
about 45 miles southeast of Hartford, Conn., 
1-38

NEW ENGLAND DIVISION 
and 50 miles southwest of Providence, R.I. (See 
Geological Survey map for New London, Conn.) 
Existing project. The hurricane protection 
project is currently in the process of reformulation. 
The original project involved separate 
barriers at Shaw Cove and Bentley's Creek with 
gated navigation openings, street gate, pumping 
station and railroad gates. The New London City 
Council by letter dated 23 February 1972 
requested modification of the project involving 
deletion of Bentley's Creek barrier and relocation 
of the Shaw Cove dike. In addition, the city 
requested that the degree of flood protection be 
reduced to a 100-year storm frequency. The 
plan endorsed by the city consists of approximately 
3,000 feet of rock-faced eathfill dike 
and 390 feet of I-walls around the north and 
west shore of Shaw Cove. Top of the barrier will 
be 14.5 feet mean sea level along the northerly 
portion of the project and 12 feet mean sea level 
along the westerly portion. Appurtenant structures 
will include a street gate, pressure conduit 
and a pumping station to discharge interior 
drainage. Latest estimate (May 1975) for the 
revised project is $7,090,000 for construction 
and $910,000 for lands and damages including 
relocations, a total of $8,000,000 for new work. 
Total includes local costs of $820,000 for lands 
and a $1,580,000 cash contribution. (See Table 
1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Local interests must: (a) 
Provide lands and rights-of-way for construction; 
(b) make alterations and relocations (c) bear 30 
percent of construction cost with credit allowed 
for (a) and (b); (d) hold the United States free 
from damages; and (e) maintain and operate all 
works. Estimated costs to local interests are 
$820,000 for lands and relocations and a cash 
contribution of $1,580,000, a total of 
$2,400,000. Assurances will be requested during 
final design. 
Operations and results during fiscal year. New 
work: Project reformulation continued. Work to 
revise the general design memorandum, prepare 
a post-authorization change report and a supplement 
to the Environmental Impact Statement 
is in progress. 
Condition at end of fiscal year. Advance 
engineering and design was approximately 80 
percent complete in early 1972 when further 
design was suspended due to local request for 
project alteration. The change in the scope of 
the authorized project and the degree of protection 
proposed necessitates a post-authorization 
change report and revised general design 
memorandum and environmental impact 
statement. 
56. SAINT JOHN RIVER BASIN, ME. 
Comprehensive plan for water resources development 
within the basin is comprised of the 
multiple-purpose Dickey and Lincoln School 
Reservoirs on the upper Saint John River. 
Projects were authorized by Flood Control Act 
of 1965 substantially in accordance with plans 
included in report of Department of Interior and 
Corps of Engineers dated August 1964 which is 
supplement to July 1963 report of International 
Passamaquoddy Tidal Power Project and Upper 
Saint John River Hydroelectric Power Development. 
Local protection project at Fort Kent 
authorized by Chief of Engineers on 25 September 
1975 in accordance with Section 205 of 
1948 Flood Control Act. (See Table 1-P at end 
of chapter for other authorized multiple-purpose 
projects including power.) 
56A. DICKEY-LINCOLN SCHOOL LAKES 
Location. On Upper Saint John River near 
town of Dickey, Maine, about 340 miles north 
of Boston, Mass. (See Geological Survey map for 
Allagash, Maine.) 
Existing project. Plan consists of Dickey and 
Lincoln School Reservoirs functioning as a single 
coordinated unit. Dickey Dam, on Saint John 
River immediately above its confluence with the 
Allagash River, would be rolled-earthfill structure 
about 10,600 feet long with maximum 
height of 335 feet. Three earthfilled perimeter 
dikes acting in conjunction with the dam would 
impound a reservoir with total capacity of 
7,707,000 acre-feet of which 2,900,000 acrefeet 
would be actively utilized for power and 
flood control purposes. Reservoir area at maximum 
operating level is 86,000 acres and its 
upper reaches extend into the Canadian Province 
of Quebec. Power facilities would be provided in 
main dam consisting of 8 units at 95,000 
kilowatts each for total of 760,000 kilowatts. 
Two low level outlet tunnels each 26 feet in 
diameter would be provided in the dam for 
stream diversion during construction. An ungated 
concrete side channel spillway with 919 
foot crest length would be in the right abutment 
to discharge floodflows. Drainage area controlled 
is 2,725 square miles. 
Lincoln School Dam, 11 miles downstream 
from Dickey Dam, would be a rolled-earthfill 
structure about 1,600 feet long with maximum 
height of 85 feet. Dam would be operated to 
impound and regulate discharges from Dickey 
Dam to maximize benefits at downstream 
hydroplants. Power facilities would include a 
powerhouse on the right abutment containing 
two units at 35,000 kilowatts each for total of 
70,000 kilowatts. Spillway structure would be 
1-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
between the powerhouse and dam and consist of 
a concrete chute spillway 160 feet long topped 
by four 40- by 50-foot taintor gates. Intermediate 
piers along the weir will support a bridge 
deck for a two lane roadway over the dam. In 
addition to drainage area controlled by Dickey 
Dam, the Lincoln School Dam would control an 
additional 1,361 square miles. Installed capacity 
totals 830,000 kilowatts for the Dickey-Lincoln 
School development. Plan was authorized by the 
1965 Flood Control Act. Approved estimate 
(January 1975) for new work is $31,250,000 for 
land including relocations and $396,750,000 for 
construction, a total of $428,000,000. (See 
Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Local interests are required 
to pay or repay one-half separable first costs 
allocated to recreation and fish and wildlife; and 
administer and operate and maintain, including 
replacement, recreation and fish and wildlife 
lands and facilities all in accordance with the 
Federal Water Project Recreation Act. Responsibility 
for repayment of costs allocated to power 
rests with the Department of Interior, pursuant 
to Federal laws. 
Operations and results during fiscal year. New 
work: Advance engineering and design activity 
was resumed. Seven preconstruction planning 
contracts totaling $154,736 were awarded in 
fiscal year 1975. Completed by contract was an 
update of the 1967 general design memorandum 
project estimate. Contracts still in progress 
included preparation of a scope of work for the 
environmental impact statement and a topographical 
survey of the Dickey Dam site. Work 
orders totaling $416,520 were issued for geological 
maps, aerial surveys, seismological studies 
and model studies for water quality, marketing 
irrigation and transmission. 
Condition at end of fiscal year. Construction 
has not been started. Advance engineering and 
design has been resumed following termination 
of prior activity in 1967. 
56B. FORT KENT, ME. 
Location. Fort Kent, located about 435 miles 
northeast of Boston, is a border town between 
the United States and Canada, situated at the 
confluence of the Saint John River and the Fish 
River. 
Existing project. The proposed local flood 
protection project provides for the construction 
of 3,245 feet of earth dike along the Saint John 
River, extending from high ground, about 950 
feet upstream of the International Bridge, to an 
existing embankment near the Fort Kent Blockhouse; 
a pumping station and appurtenances to 
handle interior drainage from 620 acres of 
developed land behind the protection works; 
650 feet of pressure conduit; and 550 feet of 
raised roadway, extending along the Fish River 
from Main Street to near the Blockhouse. The 
latest approved cost estimate (November 1974) 
for new work is $1,355,000 for construction 
and $200,000 for lands and relocations, a total 
of $1,555,000. (See Table 1-B at end of chapter 
for Act authorizing existing project). 
Local cooperation. Local interests will be 
required to provide without cost to the United 
States all lands, easements, rights of way, utility 
relocations and alterations necessary for project 
construction, currently estimated at $200,000; 
hold and save the United States free from 
damages due to the construction works; maintain 
and operate the project after completion; 
and prevent future encroachment which might 
interfere with proper functioning of the project 
for flood control. Assurances of local cooperation 
are being sought. 
Operations and results during fiscal year. New 
work: Detailed project report was completed in 
November 1974. Preparation of plans and specifications 
are under way. 
Condition at end of fiscal year. Construction 
has not yet started. 
57. SMELT BROOK, WEYMOUTHBRAINTREE, 
MASS. 
Location. Project site located in the towns of 
Weymouth and Braintree, in eastern Massachusetts, 
approximately 14 miles south of Boston. 
(See Geological Survey map for Weymouth, 
Mass.) 
Existing project. Construction of a small flood 
control dam in the upper watershed of Smelt 
Brook, minor channel improvement, and the 
construction of an 1,100-foot reinforced 
concrete conduit under Weymouth Landing. 
Latest approved estimate is $1,750,000 for 
construction and $300,000 for lands, right-ofway 
and relocations, a total of $2,050,000. (See 
Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Local interests are required 
to provide without cost to United States all 
lands, easements, rights-of-way and utility relocation 
necessary for project, currently estimated 
at $300,000; maintain and operate all works 
after project completion; and prevent further 
encroachment in the natural flood plain. Section 
205 as amended by the Water Resources 
Development Act of 1974 applies. 
Operations and results during fiscal year. New 
work: Construction was initated by contract in 
1-40

NEW ENGLAND DIVISION 
July 1974 and is now 95 percent complete. 
Contractor earnings were $1,275,129. 
Condition at end of fiscal year. Construction is 
underway. 
58. STAMFORD, CONN. 
Location. In Fairfield County on north shore 
of Long Island Sound, about 30 miles east of 
New York City and 20 miles southwest of 
Bridgeport, Conn. (See Geological Survey map 
for Stamford, Conn.) 
Existing project. This hurricane protection 
project consists principally of three structures: 
East Branch barrier consists of 2,850 feet of 
earthfilled dike, with rock faces and toes. A 
45,000 gallons per minute pumping station is in 
navigation gate structure to prevent excessive 
ponding during flood stages. West Branch protection 
on east bank of West Branch consists of 
1,340 feet of concrete wall, 160 feet of sheet 
pile bulkhead wall, and 2,950 feet of earthfilled 
dike. Appurtenant structures include a 229,500 
gallons per minute pumping station to handle 
storm runoff and discharge of cooling water 
during periods of gate closure. Westcott Cove 
protection consists of 4,400 feet of earthfilled 
dike and two pumping stations with total 
capacity of 85,500 gallons per minute. Latest 
approved estimate for new work is $9,820,000 
for construction, and $1,880,000 for lands and 
damages and relocations, a total of $11,700,000. 
Total includes local costs of $1,183,000 for 
lands and damages and a cash contribution of 
$3,207,000. For further details, see page 41 of 
1974 Annual Report. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Local interests will provide 
lands, easements, and rights-of-way; make modifications 
to existing storm drainage system 
which may be required to obtain full benefits of* 
protection plan, all necessary modifications to 
existing sanitary sewer facilities required to 
prevent entry of tidal-waters, and all changes, 
alterations and additions to or relocations of any 
buildings and utilities made necessary by construction 
of project; bear 30 percent of total 
first cost, estimated at $3,510,000 and consisting 
of cost of items listed above plus a cash 
contribution estimated at $2,327,000; contribute 
in cash, in lieu of cost of annual 
maintenance and operation of tidal portion of 
East Branch barrier which is to be operated and 
maintained by the United States, an amount 
presently estimated at $800,000; maintain and 
operate all works after completion with exception 
of tidal portion of East Branch barrier and 
aids to navigation; and hold the United States 
free from damages. Assurances received and cash 
contributions have been deposited. 
Operations and results during fiscal year. New 
work: Administrative and technical in-house 
review continued on substantial claims submitted 
by Contractor. Maintenance: Ordinary 
operation and maintenance activities. 
Condition at end of fiscal year. Project is 
complete. Construction of project initiated in 
May 1965 and was completed in January 1969. 
Final audit will determine cost sharing. 
59. THAMES RIVER BASIN, CONN., 
R.I., AND MASS. 
Works covered by this plan are a series of dams 
and reservoirs on tributaries of Thames River in 
Massachusetts and Connecticut, within a radius 
of 45 miles from Norwich, Conn., and a channel 
enlargement on Shetucket River where it 
discharges into Thames River at Norwich. Flood 
Control Act of August 18, 1941, approved plan 
for a system of reservoirs and channel improvements 
in Thames River Basin in accordance with 
House Document 885, 76th Congress, 3d session, 
and authorized $6 million for initiation 
and partial accomplishment of project. Flood 
Control Act of December 22, 1944, authorized 
completion of approved plan. Flood Control Act 
of July 14, 1960, authorized project for West 
Thompson Reservoir, substantially as recommended 
in Senate Document 41, 86th Congress, 
2d session. (See Table 1-M at end of chapter on 
reservoirs and local protection districts, Thames 
River Basin, for projects comprising approved 
plan.) 
59A. BUFFUMVILLE LAKE, MASS. 
Location. Dam is on Little River, 1.3 miles 
above its junction with French River and 8 miles 
northeast of Southbridge, Mass. Reservoir extends 
upstream about 1.7 miles northerly and 
1.9 miles southerly. (See Geological Survey 
maps - Webster, Mass. and Conn., and Leicester, 
Mass.) 
Existing project. Dam is rolled-earth type with 
rockfill slope protection. It has a top length of 
3,255 feet, a top width of 20 feet and a 
maximum height of 66 feet above streambed. A 
combined spillway and outlet founded on firm 
bedrock is in the right, or south abutment. 
Spillway is concrete overflow type, having a crest 
length of 220 feet and a peak discharge capacity 
of 29,800 cubic feet per second. Outlet consists 
of three 3-by 4.5-foot conduits provided with 
sluice gates. Gates are electrically operated from 
control house on right abutment. An earth dike 
610 feet long is at south end of reservoir, 2.75 
miles from spillway. Reservoir capacity totals 
12,700 acre-feet (11,300 acre-feet for flood 
control purposes and 1,400 acre-feet permanent 
1-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
storage), equivalent to 9 inches of runoff from 
its drainage area of 26.5 square miles. Latest 
cost estimate for new work is $2,414,000 for 
construction and $841,000 for lands and 
damages including highway relocations, a total 
of $3,255,000. Total includes an estimated 
$127,500 as local share of additional recreation 
facilities to be constructed. Project is a unit of 
comprehensive plan for flood control and other 
purposes in Thames River Basin. (See Table 1-B 
at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete except for construction of recreational 
facilities. Construction of dam and appurtenant 
works was initiated in September 1956 and 
completed in June 1958. 
59B. EAST BRIMFIELD LAKE, MASS. 
Location. Dam is on Quinebaug River, 64.5 
miles above its confluence with Shetucket River 
and 1 mile southwest of village of Fiskdale, 
Mass. (See Geological Survey maps - Whales, 
Mass., and Conn., Southbridge, Mass. and Conn., 
East Brookfield, Mass., and Warren, Mass.) 
Existing project. A rolled-earthfill dam 520 
feet long, 55 feet above streambed. Dam provides 
a flood control storage capacity of 28,800 
acre-feet and an operational storage capacity of 
1,200 acre-feet, a total of 30,000 acre-feet, 
equivalent to 8.3 inches of runoff from its 
controlled drainage area of 67.5 square miles. 
Chute-type spillway with a crest length of 75 
feet is in the right, or south abutment. Outlet 
works consist of intake, with stoplog facilities, 
gate structure with two 6-foot 3-inch by 11-foot 
gates and controls; a 10-foot 6-inch horseshoeshaped 
conduit, about 230 feet long; a stilling 
basin and service bridge. Reservoir is operated as 
a unit of a coordinated system of reservoirs for 
control of floods in Thames River Basin. Latest 
cost estimate for new work is $1,338,000 for 
construction and $5,720,000 for lands and 
damages including highway relocations, a total 
of $7,058,000. (See Table 1-B at end of chapter 
for Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in May 1958 and completed 
in June 1960. 
59C. HODGES VILLAGE DAM, MASS. 
Location. Dam is on French River, 15 miles 
above its confluence with Quinebaug River, at 
Hodges Village in town of Oxford, Mass., about 
5 miles north of Webster, Mass. (See Geological 
Survey maps for Webster, Mass., and Conn., 
Leicester, Mass., Worcester South, Mass., and 
Oxford, Mass.) 
Existing project. A rolled-earthfill dam 2,140 
feet long, 55 feet above streambed, with a 
concrete overflow section. Dam provides a flood 
control storage capacity of 12,800 acre-feet. 
Drainage area controlled is 31 square miles. 
Reservoir, at spillway crest elevation 501, extends 
about 3 miles upstream and lies entirely in 
town of Oxford, Mass. Included in project are 
four earth dikes necessary for closing saddles in 
reservoir perimeter. The four dikes have a total 
length of 2,600 feet and maximum height of 35 
feet. Reservoir is operated as a unit of a 
coordinated system of reservoirs for flood control 
in Thames River Basin. Latest cost estimate 
for new work is $2,171,000 for construction 
and $3,144,000 for lands and damages including 
highway, railroad, and utility relocation, a total 
of $5,315,000. Total includes an estimated 
$447,000 as local share of additional recreation 
facilities to be constructed. (See Table 1-B at 
end of chapter for Act authorizing existing 
project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. Local interests must also 
bear 50 percent of future recreational development 
in accordance with 1965 Federal Water 
Project Recreation Act. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete, except for construction of additional 
recreation facilities. Construction of dam and 
appurtenant works, initiated in March 1958, was 
completed in December 1959. 
59D. MANSFIELD HOLLOW LAKE, CONN. 
Location. Dam is at Mansfield Hollow, Conn., 
on Natchaug River, 5.3 miles above its confluence 
with Willimantic River. It is 4 miles 
northeast of city of Willimantic, Conn. (See 
Geological Survey maps for Spring Hill and 
Willimantic, Conn.) 
Existing project. Dam is rolled-earth type with 
a dumped rock blanket on upstream face. It has 
a top length, including spillway, of 12,422 feet, 
1-42

NEW ENGLAND DIVISION 
a top width of 15 feet, and a maximum height 
of 70 feet. There are also five earth dikes north 
of dam and one earth dike south of dam having 
a respective length of 190, 830, 464, 257, 766, 
and 104 feet and a respective maximum height 
of 12, 55, 15, 11, 8, and 12 feet. Spillway is in 
river channel and is concrete, gravity type with a 
crest length of 690 feet. Outlet works are in 
spillway and consist of five conduits, each 
controlled by a 5-foot 6-inch by 7-foot slide gate 
hydraulically operated from a gallery within 
spillway. Reservoir is operated for flood control 
purposes and has a storage capacity of 52,000 
acre-feet which is equivalent to 6.1 inches of 
runoff from its drainage area of 159 square 
miles. Cost of completed project was 
$4,108,000 for construction and $2,340,000 for 
lands and damages, a total of $6,448,000. 
Project is a unit of comprehensive plan for flood 
control and other purposes in Thames River 
Basin. (See Table 1-B at end of chapter for Act 
authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam, initiated in 
1949, was completed in May 1952. 
59E. WEST THOMPSON LAKE, CONN. 
Location. Dam is on Quinebaug River in town 
of Thompson, Conn. Site is in village of West 
Thompson, 2 miles upstream from city of 
Putnam, Conn. (See Geological Survey map, 
Putnam, Conn.) 
Existing project. Dam is a rolled-earthfill 
structure 2,550 feet long with maximum height 
of 70 feet above streambed. A side channel 
spillway with a 320-foot L-shaped concrete weir 
is in right abutment. A 600-foot long dike with a 
maximum height of 19 feet is northeast of dam. 
Reservoir overflows will discharge through a side 
channel spillway in the west (right) abutment. 
Dam impounds a reservoir 6.3 miles long with a 
surface area of 1,250 acres. Reservoir provides a 
flood control storage capacity of 25,600 acrefeet, 
equivalent to 6.5 inches of runoff from its 
net drainage area of 74 square miles, below 
Westville and East Brimfield Reservoirs. In addition, 
a 200 acre permanent pool with storage 
capacity of 1,200 acre-feet is provided for 
recreational activity. Latest approved cost 
estimate for new work is $4,888,000 for construction 
and $1,965,000 for lands, damages and 
road relocations, a total of $6,853,000. Total 
includes an estimated $167,000 for additional 
recreation facilities to be constructed. (See 
Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. New 
work: A contract for construction of recreation 
facilities to provide a comfort station, water 
supply and sewage disposal systems was awarded 
in May 1975 in the amount of $99,955. Contractor 
earnings this fiscal year were $7,000. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete except for construction of additional 
recreational facilities. Construction of dam, road 
relocations, and appurtenances was initiated in 
August 1963 and completed in October 1965. 
59F. WESTVILLE LAKE, MASS. 
Location. Dam is on Quinebaug River, 56.7 
miles above its confluence with Shetucket River, 
in towns of Sturbridge and Southbridge, Mass., 
and 1.3 miles west of center of Southbridge. 
(See Geological Survey maps - Southbridge, 
Mass. and R.I., and East Brookfield, Mass.) 
Existing project. A rolled-earthfill dam across 
main river channel, with a maximum height of 
78 feet above streambed. Concrete spillway 
section is on north abutment. Reservoir has a 
flood control storage capacity of 11,000 acrefeet, 
equivalent to 6.5 inches of runoff from 
controlled net drainage area of 32 square miles. 
Reservoir is operated as a unit of coordinated 
system of reservoirs for flood control in Thames 
River Basin. Estimated cost of new work is 
$2,285,000 for construction, and $3,400,000 
for lands and damages (including relocation of 
highways, utilities, cemeteries, and structures), a 
total of $5,685,000. (See Table 1-B at end of 
chapter for Act authorizing existing project.) 
Local cooperation. Section 2, Flood Control 
Act of 1938 applies. 
Operations and results during fiscal year. 
Maintenance: Ordinary operation and maintenance 
activities. 
Condition at end of fiscal year. Project is 
complete. Construction of dam and appurtenant 
works was initiated in April 1960 and completed 
in August 1962. 
60. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
In accordance with provisions of Flood Control 
Act of 1936, as amniended, local flood 
protection works constructed with Federal 
1-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
funds are transferred to local interests to operate 
and maintain. To insure compliance with regulations 
prescribed for their operation and maintenance 
regular inspections of the following 
projects were made during the fiscal year: 
Connecticut: October 1974 and April 1975 - 
Winsted, Torrington, Ansonia, Derby, Stamford, 
Norwalk, Waterbury, Hall Meadow, 
East Branch, Pawcatuck. October 1974 and May 
1975 - East Hartford, Hartford, Mad River, 
Sucker Brook. Maine: October 1974 and April 
1975 - Cherryfield. Massachusetts: September 
1974 and April 1975 - Haverhill, Lowell. October 
1974 and April 1975 - Worcester, Ware, 
Three Rivers, Chicopee, Chicopee Falls, Springfield, 
West Springfield, Gardner, West Warren, 
Canton, Blackstone, Scituate, Fitchburg. October 
1974 and May 1975 - New Bedford, 
Northampton, Holyoke. New Hampshire: 
September 1974 and April 1975 - Nashua, 
Farmington, Lincoln. October 1974 and April 
1975 - Wilton, Keene. Rhode Island: October 
1974 and April 1975 - Woonsocket. September 
1974 and May 1975--Providence. Vermont: 
October 1974 and April 1975 - Weston. 
61. FLOOD CONTROL RESERVOIR 
OPERATIONS 
A coordinated system of reservoirs, many of 
which are multi-purpose in nature and all containing 
significant amounts of storage for flood 
control purposes, has been established in five 
major flood producing basins in New England. 
During periods of flood flows, regulation of 
reservoirs is fully coordinated within each basin 
dependent upon its location in the watershed, its 
available storage capacity and origin of flood. In 
addition to flood control releases, water supply 
and flow augmentation releases were made from 
selected reservoirs. 
During fiscal year 1975 moderate rains during 
the autumn and spring months resulted in three 
minor flood events in September 1974, March 
1975, and April 1975. However, no benefits 
were claimed from the operation of our reservoirs 
or local protection projects. 
Blackstone River Basin. There was no significant 
regulation of West Hill reservoir during 
FY 75. 
Connecticut River Basin. During March and 
April 1975 a number of reservoirs in the basin 
were utilized for storing flood waters. Most of 
the projects stored less than 10 percent with 
Knightville and Littleville storing 20 percent in 
March, and Surry Mountain and Colebrook 
storing 10 and 20 percent, respectively in April. 
In addition, releases for white water canoeing 
occurred at Ball Mountain during October 1974 
and May 1975, and at Knightville during March 
and April 1975. Water supply and fish releases 
were discharged from Colebrook River Lake. 
Housatonic River Basin. Thomaston, Hall 
Meadow, East Branch, Northfield, Black Rock, 
Hancock Brook and Hop Brook utilized storage 
on three occasions in FY 75: September 1974 
with storages up to six percent, March 1975 
with five to 12 percent and April 1975 with five 
to seven percent. 
Merrimack River Basin. Franklin Falls, 
MacDowell, Hopkinton, Everett and Blackwater 
were regulated to store water in April 1975 with 
storages varying between four and six percent. 
Thames River Basin. There was no significant 
regulation of the Thames River Basin Projects 
during FY 1975. West Thompson Lake level was 
raised several feet for the AKC retriever trials in 
September 1974. 
62. HURRICANE BARRIER OPERATIONS 
Four hurricane barriers, located along the 
southern coast of New England, protect coastal 
communities from tidal flooding associated with 
hurricanes or severe coastal storms. The Corps 
operates the navigational elements of the 
Stamford, Connecticut and New Bedford- 
Fairhaven, Massachusetts barriers. The Fox 
Point, Rhode Island and Pawcatuck, Connecticut 
barriers are operated by the local communities. 
A brief resume of operations follows: 
Stamford Barrier. The barrier gate was closed 
on 12 occasions, all due to coastal storms. The 
maximum ocean tide rose to 7.8 feet msl. 
New Bedford-Fairhaven Barrier. The barrier 
gates were closed on five occasions, all due to 
coastal storms. The maximum ocean tide rose to 
5.7 feet msl. 
Fox Point and Pawcatuck Barriers. Neither of 
these barriers were operated during the fiscal 
year. 
63. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 1-N at end of chapter.) 
64. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 
205, Public Law 858, 80th Congress, as 
amended (preauthorization). 
(See table 1-O at end of chapter.) 
Emergency Bank Protection activities pursuant 
to Section 14 of the 1946 Flood Control Act. 
1-44

NEW ENGLAND DIVISION 
Androscoggin River, Canton, Me. Costs for 
fiscal year were $1,215. 
Androscoggin River, Gorham, N.H. Costs for 
fiscal year were $1,727. 
Connecticut River, Charlestown, N.H. Costs 
for fiscal year were $102,499. (See Section 49D 
of Text.) 
Connecticut River, West Stewartstown, N.H. 
Costs for fiscal year were $7,600. 
Green River, Alford, Mass. Costs for fiscal year 
were $5,330. 
Housatonic River, Lee, Mass. Costs for fiscal 
year were $31,776. (See Section 52G of Text.) 
Emergency flood control activities - repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal costs for fiscal year were $157,323 for 
advance preparation of flood control and coastal 
emergencies, $5,431 for emergency operations 
and $17,457 for initiation of rehabilitation work 
on the Nashua River, at Nashua, N.H. 
General Investigations 
65. SURVEYS 
Fiscal year costs for surveys from regular 
funds were $1,832,014 of which $172,429 was 
for navigation surveys; $802,991 for flood control 
surveys; $90,180 for beach erosion surveys; 
$77,777 for coordination surveys; $2,781 for 
special studies; $365,588 for comprehensive 
basin surveys; and $97,400 for restudy of 
deferred projects; $25,318 for review of completed 
projects; $21,480 for deauthorized review 
program and $176,070 inventory of dams. 
66. COLLECTION AND STUDY OF 
BASIC DATA 
The Division Engineer is the U.S. member on 
Saint Croix River Board of Control. Annual 
inspections are made of conditions on these two 
rivers and a continuing program of compilation 
of basic hydrologic information is carried out. 
Division Engineer's representatives during past 
year kept closely in touch with developments in 
the two basins and cooperated with their 
Canadian counterparts assisting in development 
of basins' resources. Total costs for fiscal year 
were $9;623. Total costs to June 30, 1975 were 
$79,983. 
Flood plain studies comprise compilation and 
dissemination, upon responsible local request, of 
information on floods and potential flood 
damages, including identification of areas subject 
to inundation by floods of various magnitudes 
and frequencies, and general criteria for 
guidance in use of flood plain areas; and 
engineering advice to local interests for their use 
in planning to ameliorate flood hazard. Total 
costs for fiscal year were $367,900. Total costs 
to June 30, 1975 were $2,329,628. (See Table 
1-Q at end of chapter for completed flood plain 
studies.) 
1-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Andrews River, 
Mass. 
(Regular Funds) 
(Contributed 
Funds) 
2. Aquatic Plant 
Control 
3. Boston Harbor, 
Mass. 
4. Branford Harbor, 
Conn. 
5. Bridgeport Harbor, 
Conn. 
6. Bucks Harbor, 
Machiasport, Me. 
7. Cape Cod Canal, 
Mass. 
8. Clinton Harbor, 
Conn. 
9. Connecticut 
River below 
Hartford, Conn. 
10. Cuttyhunk Harbor, 
Mass. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
52,500 
7,117 
13,908 
12,228 
2,774 
46,433 
42,948 
-862 
5,638 
123,300 
58,259 
2,481,546 
2,362,679 
89,800 
24,680 
369,000 
22,980 
3,618 
8,799 
8,799 
5,500 
50,512 
112,500 
25,600 
21,500 
48,657 
15,000 
7,140 
123,127 
57,867 
12,949 
12,949 
34,100 
34,100 
20,000 
-3,000 
139,980 
2,179,569 
2,107,792 
24,798 
89,918 
76,421 
284,509 
2,344 
2,344 
-4,859 
-4,488 
9,879 
72,005 
3,913 
30,000 
22,154 
52,590 
121,141 
58,738 
58,553 
39,459 
39,459 
250,000 
148,226 
2,000 
62,257 
2,326,434 
2,475,397 
-60 
185,998 
319,426 
210 
210 
-20,312 
6,142 
30,000 
23,466 
43,390 
43,524 
80,544 
79,340 
18,878 
18,878 
101,056 
341,464 
48,980 
2,496,506 
2,945,674 
14,901 
14,961 
215,367 
137,335 
31,500 
30,248 
219,042 
219,042 
116,322 
116,322 
187,500 
187,500 
135,000 
112,728 
25,313,0831 
25,313,0831 
6,096,9202 
6,096,8602 
9,537 
9,537 
655,390 
654,001 
4,491,119 s 0 
4,491,119 s 
1,541,448s 3 
1,541,448 s 3 
298,138 
277,420 
32,568,0464 ,s 
32,275,1294,6 
40,932,765 
40,661,319 
390,677 
390,677 
1,295,000 
1,295,000 
72,405 
72,405 
386,271 
386,271 
1,541,1851 o,11 
1,541,18510o, 1 
6,023,00112 
5,911,84012 
60,000 
60,000 
.27,16720 
27,167 20 
776,1299 
774,877' 
1-46

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
11. Edgartown 
Harbor, Mass. 
12. Fall River 
Harbor, Mass. 
13. Frenchboro 
Harbor, Me. 
14. Green Harbor, 
Mass. 
(Regular Funds) 
(Contributed 
Funds) 
15. Guilford Harbor, 
Conn. 
16. Hampton Harbor, 
N.H. 
17. Housatonic River, 
Conn. 
18. Hyannis Harbor, 
Mass. 
19. Isle of Shoals 
Harbor, Me. and 
N.H. 
20. Kennebec River, 
Me. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
600,000 
103,587 
26 
5,062 
6,162 
14,446 
14,446 
28,331 
32,206 
48,900 
45,135 
12,245 
12,245 
25,865 
26,165 
6,500 
6,500 
1,010,000 
40,148 
335,040 
59,540 
60,000 
-1,500 
152,907 
41,271 
241,610 
17,350 
8,376 
8,376 
-- 520,000 
92,392 
38,100 
293,611 
25,000 
33,462 
52,000 
127,305 
63,000 
268,767 
172,712 147,500 
62,512 254,035 
32,065 7,000 
35,830 6,334 
- 7,109 
- 7,109 
- - 
200 408,877 
200 94,459 
-. - 
-,- -, 
1-47 
35,000 
13,372 
-597,500 
106,278 
30,700 
32,737 
200,000 
26,569 
827 
22,203 
58,534 
- 
-16,891 
1,602 
56,800 
60,112 
1,128,942 
1,008,094 
61,230 
61,230 
181,000 
475,501 
259,000 
258,111 
50,61421 
28,9861 
18,614 
18,614 
5,510,90814 
5,318,79314 
1,307,1331 s 
1,289,1811 s 
285,000 
60,031 
261,500 
254,582 
405,228 
405,228 
164,000 
158,269 
137,222 7 
137,222 
435,829 
435,829 
200,0008 
200,00018 
642,251 
641,398 
859,69119 
859,691'9 
1,690,079 
1,568,565 
484,4993 
484,499 
196,92071 
196,92071 
80,691 52 
80,691 2 
668,517 
648,600 
1,599,94032 
1,599,940 2 
1,102,644 
1,101,755

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
21. Kennebunk River, 
Me. 
22. Lagoon Pond, 
Martha's Vineyard, 
Mass. 
(Regular Funds) 
(Contributed 
Funds) 
23. Little Harbor, N.H. 
24. New Haven Harbor, 
Conn. 
25. Newburyport 
Harbor, Mass. 
26. Pawtuxet Cove, 
R.I. 
(Regular Funds) 
(Contributed 
Funds) 
27. Plymouth Harbor, 
Mass. 
(Regular Funds) 
(Contributed 
Funds) 
28. Providence River 
and Harbor, R.I. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
11,399 
11,399 
2,392 
98,000 
1,291,800 
104,366 
-3,560 
19,208 
-23,478 
9,085 
9,085 
20,000 
121,969 
23,475 
60,184 
38,984 
1,817,300 
99,307 
200 
200 
1,163 
407,713 
225,553 
42,461 
15,330 
10,084 
10,074 
-1,161 
13,061 
13,061 
-20,000 
874 
50,638 
3,000 
5,100 
71,571 
80,224 
533,273 
1,866,085 
541,000 
421,969 
5,951 
5,961 
212 
60,912 
60,882 
698,000 
35,714 
147,000 
36,938 
-766 
766 
50,413 
22,975 
119,519 
144,106 
252,000 
315,461 
-3,483
98 
13,402 
- 
13,432 
138,000 
74,011 
350,33430 
350,3343 o 
521,299 
408,237 
107,300 
99,098 
98,000 
80,990 
133,227 
133,227 
56,072 
28,634 
4,205,24622 
4,205,24622 
5,990,7512 3 
5,978,51823 
565,225 
565,225 
2,055,524 
1,972,823 
1,415,524 
1,415,524 
295,356 
295,356 
31,308 
31,308 
295,356 
295,356 
2,127,21826 
2,126,989 6 
800,04827 
800,04827 
894,475 
894,475 
573,000 
541,611 
400 
400 
25,506,9452 8 
23,113,17928 
3,664,30529 
3,664,30529 
1-48

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
29. Rockland Harbor, 
Me. 
30. Scarboro River, 
Me. 
31. Warwick Cove, R.I. 
(Regular Funds) 
(Contributed 
Funds) 
32. Wells Harbor, Me. 
33. Weymouth-Fore 
and Town Rivers, 
Boston Harbor, 
Mass. 
34. Winter Harbor, Me. 
35. York Harbor, Me. 
40. Oak Bluffs Town 
Beach, Martha's 
Vineyard, Mass. 
"(Contributed 
Funds) 
41. Plum Island, Mass. 
(Regular Funds) 
(Contributed 
Funds) 
42. Revere Beach, 
Mass. 
46A. West Hill Dam, 
Mass. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
19,000 335,764 
13,528 50,955 
11,189 
11,189 
363,195 
26,270 
3,306 
3,306 
6,237 
6,237 
4,565,200 
4,747,499 
264,602 
506,602 
7,516 
17,397 
-1,087 
9,385 
5,900,000 
4,991,803 
100,000 
6,683 
- 8,076 
- 8,076 
- 20,000 
718 45,196 
36,000 - 
- 30,600 
- 114,000 
- 113,146 
- 100,000 
- 99,151 
- 30,000 
64,900 
63,328 
56,100 
58,969 
68,750 
325,633 
181,200 
515,248 
17,065 
17,065 
45,000 
43,733 
3,200,000 
1,414,243 
1,816 
13,875 
10,875 
18,600 
203,181 
166,458 
203 
50,000 
9,777 
78,300 
70,775 
-20,000 
13,398 
107,060 
98,972 
567 
567 
-26,765 
64,851 
48,178 
1,696,000 
2,693,496 
249,000 
16,736 
237,000 
54,903 
34 
1,154 
1,525 
-35 
303 
-68,000 
2,223 
89,300 
94,348 
1,948,46231 
1,948,46231 
417,166 
417,166 
392,63533 
392,63533 
1,167,028 
1,156,063 
155,430 
155,430 
20,938 
20,938 
107,220 
107,220 
360,97334 
360,97334 
1,210,650 
1,192,710 
26,218,95335,36 
24,514,7013 s5,36 
1,050,7143 
1,050,714" 
286,516 
54,251 
239,65413,4 7 
239,6541 3,4 7 
288,032 
102,935 
273,334 
273,334 
206,000 
198,583 
113,965 
113,652 
100,000 
99,151 
85,800 3 8 
85,800 
2,306,9023 9 
2,306,9023 9 
571,784 
568,784 
1-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975' 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
46B. Worcester 
Diversion, Mass. 
47. Charles River Dam, 
Mass. 
(Regular Funds) 
(Contributed 
Funds) 
(Other Contributed 
Funds) 
48. Charles River, 
(Natural Valley 
Storage Areas), 
Mass. 
49A. Ball Mountain 
Lake, Vt. 
49B. Barre Falls Dam, 
Mass. 
49C. Birch Hill Dam, 
Mass. 
49D. Charlestown, N.H. 
49E. Chicopee Falls, 
Mass. 
(Regular Funds) 
(Contributed 
Funds) 
49F. Colebrook River 
Lake, Conn. 
49G. Conant Brook 
Dam, Mass. 
49H. Knightville Dam, 
Mass. 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
650,000 
315,614 
106,950 
83,547 
129,820 
125,657 
49,600 
32,068 
84,540 
93,578 
50,000 
6,493 
7,412 
5,540 
-5,419 
6,500 
14,114 
41,668 
44,615 
850 
850 
33,336 
32,510 
65,000 
6,676 
3,000,000 
1,580,204 
2,800,000 
25,050 
166,996 
129,576 
135,900 
117,600 
100,000 
28,481 
117,400 
97,671 
103 
557 
6,500 
12,290 
60,653 
58,755 
40,800 
41,434 
-! 
-1 
-3,000 
13,282 
5,400,000 
4,810,650 
964,288 
1,407,000 
83,130 
135,349 
190,830 
99,165 
126,681 
4,500 
152,715 
105,924 
124,932 
35,000 
3,150 
190 
100,000 
95,473 
85,800 
60,009 
46,809 
47,000 
80,000 
115,529 
5,750,000 
8,141,558 
800,000 
2,537,512 
195,527 
115,000 
90,886 
102,412 
20,604 
148,400 
152,578 
155,200 
150,906 
1,000 
-18 
127,500 
129,289 
39,000 
102,499 
648 
2,500 
7,419 
102,500 
128,695 
41,500 
41,449 
104,946 96,300 105,320 130,200 
92,192 102,184 111,507 129,104 
5,081,50040 
5,074,98740 
15,370,000 
15,209,725 
3,600,000 
3,526,850 
1,407,000 
278,657 
115,000 
90,886 
10,637,650 69 
10,555,84270 
1,301,239 
1,294,829 
1,967,819 
1,967,819 
1,043,727 
1,036,453 
4,792,3384 1 
4,789,84942 
1,200,627 
1,196,882 
124,000 
112,245 
2,183,912 
2,183,087 
436,2004 3 
411,29244 
14,264,000 
14,263,495 
399,144 
395,466 
2,950,530 
2,950,530 
267,580 
267,529 
3 ,220,4454 5 
3,220,44545 
1,323,604 
1,319,624 
1-50

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
491. Littleville Lake, 
Mass. 
49J. North Hartland 
Lake, Vt. 
49K. North Springfield 
Lake, Vt. 
49L. Otter Brook Lake, 
N.H. 
49M. Park River, 
Hartford, Conn. 
49N. Sucker Brook 
Dam, Conn. 
(Regular Funds) 
(Contributed 
Funds) 
490. Surry Mountain 
Lake, N.H. 
49P. Townshend Lake, 
Vt. 
49Q. Tully Lake, Mass. 
49R. Union Village 
Dam, Vt. 
50. Fox Point Barrier, 
Narragansett Bay, 
R.I. 
(Regular Funds) 
SContributed 
unds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
95,124 
94,274 
70,000 
9,559 
80,986 
80,732 
-110,000 
5,514 
136,484 
125,437 
88,930 
82,486 
198,600 
84,875 
7,262 
15,000 
3,402 
93,300 
84,689 
3,396 
92,298 
88,812 
117,185 
121,782 
92,925 
78,376 
101,400 
101,802 
3,500 
95,350 
152,600 
154,360 
114,225 
122,637 
94,400 
88,047 
548,000 
216,731 
5,000 
1,508 
9,590 
96,300 
94,001 
65,000 
9,687 
146,700 
125,504 
101,300 
103,829 
97,500 
98,931 
98,453 
95,077 
8,700 
6,531 
104,829 
106,083 
111,732 
114,264 
69,375 
78,855 
184,000 
569,667 
8,000 
11,899 
38,800 
4,000 
2,300 
71,160 
112,266 
120,614 
55,765 
125,051 
143,061 
95,666 
100,973 
115,787 
123,182 
22,000 
13,662 
102,500 
110,130 
-1,464 
4,496 
120,700 
127,979 
197,400 
194,389 
94,400 
97,317 
708,000 
860,198 
16,000 
18,181 
35,800 
-3 
2,219 
131,700 
132,078 
168 
1,395 
153,600 
146,840 
100,000 
14,105 
105,000 
85,028 
128,600 
130,413 
7,715 
7,013,412 
7,013,412 
675,091 
673,726 
7,230,0254 6 
7,230,0254 6 
968,915 
965,163 
6,831,52625 s 
6,831,52625 
1,381,597 
1,377,948 
4,061,0484 8 
4,061,048 
869,514 
868,714 
1,738,600 
1,731,471 
2,226,292 
2,225,000 
58,800 
58,800 
2,689,61349 
2,689,6134 9 
1,203,145 
1,200,427 
7,398,413 s 1 
7,398,413 s 
1,539,171 
1,525,739 
1,651,613' 
1,565,7188 
1,050,186 
1,029,971 
4,010,698 
4,010,698 
1,118,956 
1,108,627 
11,113,180 
11,112,557 
3,679,50024 
3,679,50024 
1-51

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
51. Hayward Creek, 
Mass. 
52A. Ansonia-Derby, 
Conn. 
(Other Contributed 
Funds) 
52B. Black Rock Lake, 
Conn. 
52C. Danbury, Conn. 
(Regular Funds) 
(Other Contributed 
Funds) 
52D. Derby, Conn. 
(Other Contributed 
Funds) 
52E. Hancock Brook 
Lake, Conn. 
52F. Hop Brook Lake, 
Conn. 
52G. Lee, Mass. 
52H. Northfield Brook 
Lake, Conn. 
521. Thomaston Dam, 
Conn. 
53A. Blackwater Dam, 
N.H. 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
4,667,300 
4,014,349 
28,000 
17,771 
38,224 
93,600 
91,728 
49,600 
8,833 
3,379,200 
3,175,651 
-17,978
13 
49,718 
47,709 
8,000 
21,617 
84,400 
74,843 
50,000 
50,074 
500 
411 
141,173 
121,111 
61,698 
57,910 
--95,000 
585,819 
7,679 
-26,700 
67,660 
77,200 
74,655 
193,400 
225,894 
1,293,000 
1,513,035 
3,046 
47,900 
49,681 
379,500 
202,339 
86,300 
92,104 
68,000 
60,895 
200 
197 
348,900 
132,546 
69,100 
72,100 
-2 
-- 2
15 
- 158,000 
- 86,226 
5,000 
3,697 9,275 
1,694 6,500 
2,634 40,409 
-1,000 - 
94,623 
98,828 
818,000 
394,296 
222,000 
17,550 
-141,000 
-49,473 
1,977 
53,482 
53,525 
45,600 
273,940 
99,325 
97,945 
10,000 
3,715 
54,245 
61,019 
1,300 
1,392 
135,823 
372,326 
71,653 
72,149 
97,400 
95,154 
3,675,000 
3,808,739 
700,000 
795,449 
-225,000 
19,295 
--6,500 
1,180 
53,500 
52,685 
2,285 
152,100 
155,696 
32,352 
31,776 
120,200 
117,428 
153,400 
150,314 
87,400 
87,692 
1-52 
158,000 
86,226 
17,817,300 
17,769,923 
728,53954 
726,045 
8,182,300 
8,182,300 
427,809 
425,013 
5,002,000 
4,680,964 
922,000 
812,999 
7,583,200 
7,572,264 
346,653 
287,927 
4,179,911 
4,179,911 
278,549 
277,549 
6,008,024 
6,008,024 
564,335 
561,722 
42,352 
35,491 
2,830,512 
2,830,512 
388,111 
383,582 
14,282,112 
14,282,112 
1,200,567 
1,196,729 
1,319,746 s 
1,319,746 s 
742,585 
742,585

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
53B. Edward MacDowell 
Lake, N.H. 
53C. Franklin Falls 
Dam, N.H. 
53D. Hopkinton-Everett 
Lakes, N.H. 
53E. Nookagee Lake, 
Mass. 
53F. Saxonville, Mass. 
54. New Bedford, Mass. 
(Regular Funds) 
(Contributed 
Funds) 
55. New London, 
Conn. 
(Regular Funds) 
(Contributed 
Funds) 
56A. Dickey Lincoln 
School Lakes, Me. 
56B. Fort Kent, Me. 
57. Smelt Brook, 
Weymouth- 
Braintree, Mass. 
58. Stamford Conn. 
(Regular Funds) 
(Contributed 
Funds) 
59A. Buffumville Lake, 
Mass. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
85,168 
72,361 
122,760 
103,068 
-30,000 
3,600 
189,282 
175,182 
191,700 
200,834 
99,300 
34,570 
-412 
6,942 
100,700 
105,145 
-96,237 
2,057 
197,900 
22,967 
16,346 
2,730 
93,600 
82,971 
77,690 
70,690 
152,350 
105,982 
108,600 
116,324 
5,637 
9,850 
203,100 
208,422 
95,000 
71,431 
111,000 
93,372 
72,500 
77,612 
-317,000 
5,726 
-550,000 
90,000 
35,190 
1,000 
1,339 
10,000 
11,731 
256,700 
123,757 
70,294 
82,904 
117,694 
175,299 
128,398 
129,004 
109,000 
35,7 64 
191,701 
195,414 
-170,000 
15,137 
68,000 
85,760 
144,000 
134,256 
33,057 
2]1 
2C 
2f 
1] 
- 949,000 
- 534,199 
2,020 91,800 
38,002 66,977 
1,556,000 8,200 
74,679 1,324,847 
18,700 75,000 
19,454 35,491 
106,700 86,000 
249,987 83,279 
62,636 
62,827 
- 2,014,2535 6 
- 2,014,253 6 
32,800 1,193,792 
34,875 1,189,326 
- 7,950,487 s 7 
- 7,950,487 7 
30,000 1,673,937 
34,817 1,667,218 
16,556 21,454,00558 
33,094 21,442,747s9 
11,000 1,638,940 
07,814 1,630,689 
- 563,700 
6,484 546,497 
88,000 505,300 
86,138 499,840 
- 11,510,088 
- 11,510,088 
11,500 1,012,855 
96,163 986,988 
- 6,513,76360 
- 6,513,76360 
30,000 1,010,900 
89,963 981,165 
61 
61 
3,103,300 
2,688,499 
183,820 
140,169 
1,681,700 
1,516,639 
7,332,700 
7,281,796 
828,672 
825,666 
3,367,97062 
3,316,60462 
2,998,60363 
2,998,6036 
779,122 
775,309 
117,500 
113,911 
1-53

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
59B. East Brimfield New Work 
Lake, Mass. Approp. 54,800 - 9,500 - 7,057,4436 4 
Cost 26,655 56,682 27,857 1,080 7,056,5316s 
Maint. 
Approp. 167,133 87,738 89,939 95,600 815,783 
Cost 156,016 98,613 88,092 95,259 813,353 
59C. Hodges Village New Work 
Dam, Mass. Approp. - - - - 4,420,91566 
Cost - - - - 4,420,9156 
Maint. 
Approp. 74,693 76,300 73,652 92,700 745,588 
Cost 72,013 78,651 74,115 88,901 741,565 
59D. Mansfield Hollow New Work 
Lake, Conn. Approp. - - - - 6,447,16416 
Cost - - - - 6,447,164 
Maint. 
Approp. 74,500 76,200 93,621 122,176 968,843 
Cost 72,355 77,264 88,095 120,586 960,646 
59E. West Thompson New Work 
Lake, Conn. Approp. 20,000 27,800 4,000 176,900 6,862,70072 
Cost 33,378 35,419 4,043 78,227 6,764,027" 
Maint. 
Approp. 81,500 64,400 81,222 102,600 547,798 
Cost 76,347 68,467 83,603 99,996 544,798 
59F. Westville Lake, New Work 
Mass. Approp. 64,700 3,000 - -33 5,684,6836 7 
Cost 8,104 46,479 12,686 365 5,684,6506 8 
Maint. 
Approp. 73,590 78,044 84,655 111,800 718,196 
Cost 70,910 78,704 83,850 108,184 711,755 
1. Includes $1,465,123 for previous projects. 
Includes $935,303 emergency relief funds and 
$1,030,806 public works funds. 
2. Includes $17,879 for previous projects. Excludes 
$17,767 contributed funds. 
3. Excludes $103,001 expended from contributed 
funds.
4. Includes $6,138,157 from public works funds 
and $4,849,740 from emergency relief funds. Excludes 
$115,432 contributed funds. 
5. Includes $682,846 Code 711 funds. 
6. Includes $389,929 Code 711 funds. 
7. Includes $103,695 Code 711 funds. 
8. Includes $17,800 Code 711 funds. 
9. Excludes $50,000 Contributed funds expended. 
10. Includes $287,374 for previous projects. Excludes 
$130,410 contributed funds. 
11. Includes $9,000 for subproject "Eightmile River, 
Conn." 
12. Includes $366,348 for previous projects. 
13. Excludes $32,161 expended from contributed 
funds. 
14. Includes $330,204 for previous project. 
15. Includes $81,410 for previous project. 
16. Includes $68,717 Code 711 funds. 
17. Excludes $25,500 contributed funds. 
18. Excludes $193,761 contributed funds. 
19. Excludes $222,010 expended from contributed 
funds. 
20. Excludes $11,643 expended from contributed 
funds. 
21. Includes $15,614 for new work for previous 
project and excludes $10,000 expended from contributed 
funds for new work. 
22. Includes $331,626 for previous projects. Includes 
$290,877 National Industrial Recovery Funds and 
$59,207 public works funds. 
23. Includes $32,570 for previous projects. 
24. Cash for construction only. Excludes $245,000 
expended for land condemnation. 
25. Includes $59,536 Code 711 funds. 
26. Includes $188,647 for previous projects. 
27. Includes $2,013 for previous projects. 
28. Includes $3,761,412 for previous projects. 
29. Includes $650,136 for previous projects. 
30. Excludes $88,917 expended from contributed 
funds. 
31. Excludes about $255,000 expended by local 
interests in terminal and transfer facilities. Authorized 
work remaining on project is comprised of an incomplete 
and an inactive portion. 
32. Includes $509,411 for previous project. 
33. Excludes $10,000 contributed funds. 
34. Excludes $212,000 expended from contributed 
funds. 
35. Includes for previous projects $735,900 (Weymouth-
Fore River) and $25,000 (Town River). 
36. Excludes contributed funds expended $100,000 
(Weymouth-Fore River) and $340,237 (Town River). 
37. Includes for previous projects $5,250 (Weymouth-
Fore River) and $12,577 (Town River). 
38. Includes $73,800 for previous project. Excludes 
$142,965 contributed funds. 
39. Includes $18,310 Code 711 funds. 
40. Excludes $79,300 contributed funds. 
41. Includes $627,128 Code 711 funds. 
42. Includes $624,639 Code 711 funds. 
43. Cash for construction only. 
1-54

NEW ENGLAND DIVISION 
COST AND FINANCIAL STATEMENT 
44. Excludes $12,000 expended for land condemnations. 
In addition, $25,184 expended from Contributed 
Funds, Other, for relocations. 
45. Includes $4,109 Code 711 funds. 
46. Includes $147,236 Code 711 funds. 
47. Includes $44,000 for previous projects. 
48. Includes $65,288 Code 711 funds. 
49. Includes $326,080 Code 711 funds. 
50. Includes $378,450 for previous projects and 
excludes $147,887 expended from contributed funds. 
51. Includes $245,168 Code 711 funds. 
52. Includes $41,453 for previous project. 
53. Includes $11,949 for maintenance of previous 
projects. 
54. Includes $497,039 from Ansonia, $231,500 
from Derby. 
55. Includes $2,881 Code 711 funds. 
56. Includes $6,432 Code 711 funds. 
57. Includes $4,671 Code 711 funds. 
58. Includes $181,293 Code 711 funds. 
TABLE 1-B AUTHORIZII 
59. Includes $170,035 Code 711 funds. 
60. Cash for construction only. Excludes $164,020 
expended to date for land condemnations. 
61. Excludes $22,517 expended to date for land 
condemnations. 
62. Cash for construction only. Excludes $199,410 
expended to date for land condemnations. 
63. Includes $71,943 Code 711 funds. 
64. Includes $208,100 Code 711 funds. 
65. Includes $207,188 Code 711 funds. 
66. Includes $6,255 Code 711 funds. 
67. Includes $67,667 Code 711 funds. 
68. Includes $67,634 Code 711 funds. 
69. Includes $102,412 Code 711 funds. 
70. Includes $20,604 Code 711 funds. 
71. Excludes $129,757 expended for rehabilitation; 
breakwater repaired in 1961. 
72. Includes $176,900 Code 711 funds. 
73. Includes $78,227 Code 711 funds. 
LG LEGISLATION 
Acts Work Authorized Documents 
July 14, 1960 as amended 
in 1965 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1825 
June 14, 1880 
Aug. 5, 1886 
Sept. 19, 1890 
July 25, 1892 
July 13, 1892 
June 3, 1896 
Mar. 3, 1899 
ANDREWS RIVER, MASS. (See Section 1 of Text). 
Channel 6 feet deep, 75 feet wide from deep water in 
Nantucket Sound to public marina; 2 jetties; 3-acre 
maneuvering and anchorage basin. 
AQUATIC PLANT CONTROL (See Section 2 of Text). 
Control and progressive eradication of obnoxious Aquatic 
Plant growths from the navigable waters and streams in 
the U.S. 
Research and planning costs to be borne by U.S. 
Provided for continued research 
BOSTON HARBOR, MASS. (See Section 3 of Text). 
Preservation of islands by seawalls. 
Weir River (Nantasket Beach Channel) 9.5 ft. deep, 
100 ft. wide to Steamboat wharf at Nantasket. 
Fort Point Channel. 13 
Weir River (Nantasket Beach Channel) 9.5 ft. deep, 
150 ft. wide to Steamboat wharf at Nantasket. 
Weir River (Nantasket Beach Channel) from mouth of 
Weir River to Steamboat wharf at Nantasket Beach 
12 ft. deep, 150 ft. wide. 
Channel 15 feet deep from Long Island to Nixes Mate 
Shoal (Nixes Mate or Nubble Channel). 
Channel 27 feet deep from Nantasket Roads to President 
Roads. 
Dredge Chelsea River channel to 18 feet. 
For 30-foot channel from sea to President Roads through 
Broad Sound by less direct route than 35- and 40-foot 
channels. 
Section 107 PL 86-645, 
Authorized by Chief of Engineers 
May 2, 1966. 
H. Doc. 37, 85th Cong., 1st sess. 
Public Law 87-874, 87th Cong. 
H. Doc. 251, 89th Cong. 
Annual Report, 1881, p. 518. 
H. Ex. Doc. 206, 48th Cong., 2d 
sess., Annual Report, 1885, 
p. 543. 
Annual Report, 1890, p. 503. 
Annual Report, 1893, p. 769. 
Annual Report, 1887, p. 517. 
Annual Report, 1893, p. 766. 
H. Ex. Doc. 162, 53d Cong., 
3d sess., Annual Report 1895, 
p. 648. 
H. Doc. 133, 55th Cong., 2d 
sess., Annual Report, 1898, 
p. 886. 
1-55 
TABLE 1-A (Continued)

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 13, 1902 
July 25, 1912 
Aug. 8, 1917 
Aug. 30, 19352 
Do. 
Aug. 26, 1937 
Oct. 17, 1940 
Sept. 7, 1940 
Mar. 2, 19453 
July 24, 1946 
July 3, 1958 
Oct. 23, 1962 
June 13, 1902 
Mar. 2, 1907 
July 4, 1836 
Mar. 3, 1899 
Mar. 2, 1907 
Mar. 2, 1919 
July 3, 193011 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 3, 195812 
For 35-foot channel from sea to Boston Naval Shipyard, 
Chelsea and Charles River Bridges. 
Elimination from project of removal of Finns Ledge at 
outer entrance. 
Dredge Chelsea River channel 25 feet. 
Depth of 40 feet (45 feet in rock) in Broad Sound 
Channel. 
Present project dimensions of channel from President 
Roads to Commonwealth pier No. 1, East Boston and 
anchorage area north side of President Roads. 
Present project dimensions of that part of approach 
channel to U.S. Navy drydock No. 3, at South Boston 
between Main Ship Channel and U.S. harbor line. 
Chelsea River channel 30 feet deep. 
Reserved channel 30 feet deep. 
Abandons seaplane channel authorized in 1940 River 
and Harbor Act (H. Doc. 262, 76th Cong., 1st sess.). 
Extension of 40-foot channel. 
Extension of President Roads anchorage. 
Reserved channel 35 feet deep, 430 feet wide, extending 
1 mile from 40-foot main channel to L St. 
Chelsea River Channel and Maneuvering Basin 35 feet 
deep. 
BRANFORD HARBOR, CONN. (See Section 4 of Text). 
Channel between upper and lower wharves in the river. 
Channel at the mouth of the harbor. 
BRIDGEPORT HARBOR, CONN. (See Section 5 of 
Text). 
Fayerweather Island seawall. 
Shore protection of Fayerweather Island. 
West breakwater and present project dimensions of 
east breakwater. 
Present project depths of 18- and 12-fort anchorage 
basins. 
25-foot entrance channel, 25-foot anchorage and an 
18-foot channel through Johnsons River present 
project dimensions of channels through Poquonock 
River, Yellow Mill Pond, Black Rock Harbor and 
Cedar Creek. 
25-foot channel through main harbor, and present 
project location and extent of 18- and 12-foot 
anchorage basins. 
30-foot channel; elimination of 12-foot anchorage. 
30-foot turning basin and 15- and 9-foot channels in 
Johnsons River. 
Present depth and extent of main channel, and turning 
basin south and southeast of Cilco Terminal; Black 
Rock Harbor breakwater; Burr and Cedar Creek 
anchorage. Upper Johnsons River anchorage; lower 
Johnsons River anchorage. 
H. Doc. 119, 56th Cong., 2d 
sess., Annual Report, 1901, 
p. 1096. 
Authorized by Chief of Engineers 
Mar. 11, 1913. 
H. Doc. 272, 62d Cong., 2d sess. 
H. Dop. 931, 63d Cong., 2d 
sess. 
H. Dop. 244, 72d Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 29, 74th Cong., 1st sess.l 
Rivers and Harbors Committee 
Doc. 24, 75th Cong., 1st sess. 1 
H. Dop. 225, 76th Cong., 1st 
sess. 
Public Law 420, 78th Cong. 
H. Dop. 733, 79th Cong., 2d 
sess. 
H. Doc. 244, 80th Cong., 1st 
sess. 
H. Doc. 349, 84th Cong. 1 
H. Doc. 350, 87th Cong., 2d 
sess. 
H. Doc. 100, 56th Cong., 2d 
sess., and Annual Report for 
1901, p. 1188. 
Specified in Act. 
Annual Report, 1899, p. 1173. 
H. Does. 275 and 521, 59th 
Cong., 2d sess. 
H. Doc. 898, 63d Cong., 2d sess. 
H. Doc. 281, 71st Cong., 2d sess. 
H. Doc. 232, 75th Cong., 1st 
sess. 
H. Doc. 819, 76th Cong., 3d 
sess. 
H. Doe. 680, 79th Cong., 2d 
sess. 
H. Doc. 136, 85th Cong. 
1-56'

TABLE 1-B (Continued) 
NEW ENGLAND DIVISION 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 14, 1960 as amended 
in 1970 
Jan. 21, 1927 (Sec. 2) 
Included in Public Works 
Administration program, 
Sept. 6, 1933. 
June 26, 1934 (Permanent 
Appropriations Repeal 
Act). 
Included in Public Works 
Administration program, 
Apr. 29, 1935. 
Included in Emergency 
Relief Program, May 28, 
1935. 
Aug. 30, 1935 
Mar. 2, 1945 
July 3, 1958 
Aug. 2, 1882 
Mar. 2, 1945 
June 10, 1872 
Mar. 3, 1881 
June 25, 1910 
Feb. 27, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
May 24, 1937 
Mar. 2, 1945 
May 17, 1950 s 
July 14, 1960 (Sec. 107) 
Aug. 26, 1937 
BUCKS HARBOR, MACHIASPORT, ME. (See 
Section 6 of Text). 
Anchorage area of 11 acres, 8 feet deep in outer harbor. 
CAPE COD CANAL, MASS. (See Section 7 of Text). 
Purchase canal from Boston, Cape Cod & New York 
Canal Co., in accordance with contract dated July 29, 
1921, executed by that company. 
Construct 3 bridges and widen canal to 250 feet. 
Operation and care of works of improvement provided 
for the funds frofn War Department appropriations for 
rivers and harbors. 
Construct a mooring basin. 
Dredging and bank protection. 
Existing project for main canal adopted. 
15-foot channel and turning basin in Onset Bay. 
Extend East Boat Basin for an area of about 4.3 acres to 
a depth of 8 feet. 
CLINTON HARBOR, CONN. (See Section 8 of Text). 
Maintenance of a stone dike closing a breach in sandy 
peninsula which separates river from outer harbor. 
8-foot channel and anchorage. 
CONNECTICUT RIVER BELOW HARTFORD, CONN. 
(See Section 9 of Text). 
Jetties at the mouth. 
The Hartford dike. 
Channel and turning basin in Eight-mile River. 
Present project dimensions of channel over Saybrook bar. 
Dikes, training walls, and revetments. 
Present project dimensions of channel and additional 
dikes, training walls, revetments, and accessory works. 
Park River declared nonnavigable. 
Channel and anchorages, North Cove, Old Saybrook. 
Channel, anchorage, and turning basin, Eight-mile River. 
Channel and anchorage in Essex Cove. 
Channel and anchorage in Wethersfield Cove. 
CUTTYHUNK HARBOR, MASS. (See Section 10 of 
Text). 
Channel 10 feet deep, 75 feet wide. 
Anchorage 10 feet deep, 900 feet long, 800 feet wide. 
Maintenance of existing jetties and stone dikes. 
P.L. 86-645, Section 107, 
Authorized by Chief of Engineers 
Nov. 2, 1972. 
H. Doc. 139, 67th Cong., 2d 
sess. 
H. Doc. 795, 71st Cong., 3d 
sess. 
Do. 
Do. 
Do. 
Rivers and Harbors Committee 
Doc. 15, 74th Cong., 1st sess. 
H. Doc. 431, 77th Cong., 1st 
sess. 
H. Doc. 168, 85th Cong. 
S. Ex. Doc. 84, 47th Cong., 
1st sess. 
H. Doc. 240, 76th Cong., 1st 
sess. 
Present project dimensions 
approved by Chief of Engineers, 
Dec. 22, 1887. 
Present project dimensions 
authorized by Chief of Engi 
neers in 1889. 
H. Doc. 327, 60th Cong., 1st 
sess. 
H. Doc. 1294, 61st Cong., 3d 
sess. 
H. Doe. 132, 65th Cong., 1st 
sess. 
H. Doe. 49, 73d Cong., 1st 
sess. 
Ltr. Sec. War, Apr. 21, 1937. 
H. Doe. 368, 76th Cong., 1st 
sess. 
H. Doc. 666, 80th Cong., 2d 
sess. 
Chief of Engineers Oct. 18, 1961. 
Chief of Engineers Nov. 15,1960. 
H. Doc. 81, 75th Cong., 1st sess. 
1-57

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
July 3, 19306 
July 24, 1946 
Sept. 3, 1954 
Aug. 13, 1968 
Oct. 27, 1965 
July 14, 1960 as amended 
in 1965 
Mar. 2, 1945 
July 14, 1960 as amended 
in 1965 
Mar. 3, 1871 
Aug. 11, 1888 
July 3, 1930 
Mar. 2, 1827 
July 11, 1871 
Aug. 5, 1886 
Mar. 2, 1945 
June 25, 1910 
EDGARTOWN HARBOR, MASS. (See Section 11 of 
Text). 
Artificial sand dune barrier along Katama Beach and a 
10 acre anchorage, 6 ft. deep. 
FALL RIVER HARBOR, MASS. (See Section 12 of 
Text). 
30-foot channel including Hog Island Shoals, and maintenance 
of 25-foot anchorage. 
35-foot channel and turning basin. 
Deepening mid bay channel to 35 feet for a width of 
400 feet between deep water in Mount Hope Bay and 
Globe Wharf. 
Deepening Mount Hope Bay and Tiverton Channels to 
40 feet. 
FRENCHBORO HARBOR, ME. (See Section 13 of Text). 
5-acre anchorage, 10 feet deep in outer harbor; entrance 
channel 75 feet wide, 6 feet deep; 1.5-acre anchorage 
basin, 6 feet deep in inner harbor. 
GREEN HARBOR, MASS. (See Section 14 of Text). 
Channel 6 feet deep, 100 feet wide from deep water to 
head of navigation; anchorage near town pier; sealing, 
rebuilding in part and extension of existing west jetty. 
GUILFORD HARBOR, CONN. (See Section 15 of Text). 
Entrance channel 100 feet wide, 6 feet deep; a channel 
60 feet wide, 6 feet deep; an anchorage basin 6 feet 
deep, 200 feet wide. 
HAMPTON HARBOR, N.H. (See Section 16 of Text). 
Extending north jetty 1,000 feet, raising outer 300 feet 
south jetty and constructing 180-foot spur to high 
ground, channel 8 feet deep, 150 feet wide across 
entrance bar. 
HOUSATONIC RIVER, CONN. (See Section 17 of Text). 
A jetty at Sow and Pigs Rocks and the present project 
width of the channel across the outer bar. 
Breakwater at the mouth and the present project 
dimensions of the river channel above the lower end 
of Culvers Bar. (Enlargement of outer arm of breakwater 
and extension of Stratford dike not required.) 
The Stratford dike. 
Present project dimensions of channel up to Culvers 
Bar. 
HYANNIS HARBOR, MASS. (See Section 18 of Text). 
Breakwater. 
Present dimensions of breakwater. 
Dredging behind breakwater. 
Channel, anchorage and jetty. 
ISLE OF SHOALS HARBOR, ME. and N.H. (See 
Section 19 of Text). 
Three rough-stone breakwaters. 
S. Doc. 108, 91st Cong., 2d 
sess., in accordance with Section 
201 of 1965 Flood Control 
Act. 
H. Doc. 158, 71st Cong., 2d sess. 
H. Doc. 628, 79th Cong., 2d sess. 
H. Doc. 405, 83d Cong. 
H. DoS. 175, 90th Cong., 1st 
sess. 
S. Doc. 32, 91st Cong., 1st sess., 
in accordance with Section 201 
of 1965 Flood Control Act. 
Section 107, PL 86-645 
Authorized by Chief of Engineers 
Dec. 15, 1965. 
H. Doc. 149, 77th Cong., 1st 
sess. 
Section 107, PL 86-645, Chief 
of Engineers Feb. 18, 1964. 
H. Doc. 95, 41st Cong., 3d sess. 
and Annual Report 1871, 
p. 781. 
S. Doc. 103, 50th Cong., 1st 
seas. and Annual Report 1888, 
p. 554. 
Authorized by Dept. project 
submitted by the district 
engineer July 15, 1892. 
H. Doc. 449, 70th Cong., 2nd 
sess. (Contains latest published 
map.) 
S. Doc. 32, 18th Cong., 2d sess. 
H. Doc. 63, 41st Cong., 2d sess. 
H. Ex. Doc. 96, 48th Cong., 2d 
sess. 
H. Doe. 98, 77th Cong., 1st 
sess. 
H. Doc. 1122, 60th Cong., 2d 
sess. 
1-58

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 13, 1902 
Mar. 2, 1907 
Mar. 4, 1913 
Oct. 17, 1940 
Mar. 2, 1829 
Aug. 14, 1876 
Sept. 19, 1890 
Oct. 23, 1962 
July 14, 1960 as amended 
in 1965 
Aug. 5, 1886 
Aug. 2, 1882 
Mar. 3, 1899 
June 25, 1910 
July 25, 1912 
Do. 
July 3, 1930 
Aug. 30, 19357 
Mar. 2, 1945 
July 24, 1946 
Aug. 16, 1949 
Aug. 9, 1955 
June 14, 1880 
June 25, 1910 
Mar. 2, 19459 
KENNEBEC RIVER, ME. (See Section 20 of Text). 
Channel between Augusta and Gardiner, Maine. 
Channel below Gardiner, Maine. 
Channel west of Swan Island. 
27-foot channel from mouth of Bath. 
KENNEBUNK RIVER, ME. (See Section 21 of Text). 
Repair of pier on east side of channel entrance. 
Deepening at Wading Place and Mitchells Point. 
Jetty at Wading Place. 
8-foot channel. 
6-foot channel. 
6-foot anchorage, west side of channel. 
6-foot anchorage, east side of channel. 
Extension of west jetty, and construction of sand fence. 
LAGOON POND, MARTHA'S VINEYARD, MASS. 
(See Section 22 of Text). 
Entrance channel 8 feet deep, 100 feet wide. 
LITTLE HARBOR, N.H. (See Section 23 of Text). 
Provides for a channel 3,000 feet long, 100 feet wide 
12 feet deep, anchorage basin of like depth 40 acres 
in area, and for the construction of two breakwaters 
at the harbor entrance. 1 0 
NEW HAVEN HARBOR, CONN. (See Section 24 of 
Text). 
Sandy Point dike. 
The 16-foot anchorage basin. 
Brewery Street channel, removal of rocks in Morris 
Cove and present project dimensions of 15-foot basin. 
Present project dimensions of channels in Mill River. 
Present project dimensions of West Rivert channel and 
anchorage. 
18- and 16-foot channels in Quinnipiac River. 
25-foot channel. 
30-foot channel and anchorage and present location of 
16-foot anchorage. 
35-foot main channel, elimination of 30-foot anchorage, 
present location and extent of 16-foot anchorage and 
22-foot channel and turning basin in Quinnipiac River. 
Brewery Street channel declared nonnavigable. 
Abandonment of upper end of West River. 
NEWBURYPORT HARBOR, MASS. (See Section 25 of 
Text). 
Construction of rubblestone jetties. 
Dredging the bar at entrance to harbor. 
Dredging channel from sea to wharves and a widened 
turning basin. 
H. Do4. 262, 56th Cong., 1st 
sess. 
H. Doe. 321, 59th Cong., 2d 
sess. 
H. Do. 746, 62d Cong., 2d 
sess. 
S. Dos. 55, 77th Cong., 1st 
sess. 
Annual Report, 1875, p. 115. 
H. Ex. Doc. 136, 51st Cong., 1st 
sess. and Annual Report 1890, 
p. 471. 
H. Doc. 459, 87th Cong., 2d 
sess. 4 
PL 86-645 Section 107, 
Authorized by Chief of Engineers 
Dec. 24, 1968. 
H. Doc. 91, 48th Cong., 2d sess. 
Plans approved by a Board of 
Engineers, Oct. 2, 1882. 
H. Doc. 82, 55th Cong., 1st sess. 
H. Doc. 1159, 60th Cong., 2d 
sess. 
H. Doc. 26, 62d Cong., 1st sess. 
H. Doc. 535, 62d Cong., 2d sess. 
H. Doc. 686, 69th Cong., 2d sess. 
H. Doc. 479, 72d Cong., 2d sess. 
H. Doc. 307, 76th Cong., 1st 
sess. 
H. Doc. 517, 79th Cong., 2d 
sess. 4 
Annual Report 1910, p. 59. 
H. Doc. 703, 76th Cong., 3d 
sess. 
1-59

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Mar. 3, 1899 
Mar. 4, 1913 
Sept. 22, 1922 
Oct. 23, 1962 
July 9, 1965 
Aug. 26, 1937 
Oct. 18, 1965 
June 14, 1880 
June 29, 1956 
May 17, 1950 
July 14, 1960 as amended 
in 1965 
June 10, 1872 
July 14, 1960 as amended 
in 1965 
1965 River & Harbor Act. 
July 14, 1960 as amended 
in 1965 
Mar. 3, 1905 
July 14, 1960 
Oct. 23, 1962 
PAWTUXET COVE, R.I. (See Section 26 of Text). 
Channel 100 feet wide, 6 feet deep from deep water to 
head of cove, with turning basin; 14-acre anchorage 
6 feet deep with sheltering dike, 2,200 feet long. 
PLYMOUTH HARBOR, MASS. (See Section 27 of Text). 
Beach protection. 
Dredging 18-foot channel. 
Dredging 15-foot extension, including turning basin. 
Rubblestone breakwater. Anchorages are 8 feet deep 
inside breakwater. Elimination of authorized 18-foot 
anchorage from existing project. 
Recreational development. 
PROVIDENCE RIVER AND HARBOR, R.I. (See 
Section 28 of Text). 
35-foot channel. 
Deepen 35-foot channel to 40 feet. 
ROCKLAND HARBOR, ME. (See Section 29 of Text). 
Breakwater. 
Approach channel 18 feet deep and branch channels. 
SCARBORO RIVER, ME. (See Section 30 of Text). 
Channel across bar 200 feet wide, 8 feet deep; channel 
2,400 feet long, 6 feet deep, leading to an anchorage; 
and jetty 800 feet long. 
WARWICK COVE, R.I. (See Section 31 of Text). 
Entrance channel 6 feet deep, 150 feet wide into and 
through lower portion of cove, then 100 feet wide, 
6 feet deep, to head of cove; and four anchorage areas, 
6 feet deep. 
WELLS HARBOR, ME. (See Section 32 of Text). 
Repairs of Old Government pier about 750 feet long; 
anchorage basin; channel 100 to 150 feet wide. 
Two stone jetties. 
WEYMOUTH-FORE AND TOWN RIVERS, BOSTON 
HARBOR, MASS. (See Section 33 of Text). 
Combining Weymouth-Fore & Town Rivers into single 
project and modifies construction of 35-foot deep 
channel and anchorage. 
WINTER HARBOR, ME. (See Section 34 of Text). 
Anchorage area of 6.5 acres, 8-feet deep and a 75-foot 
wide fairway. 
YORK HARBOR, ME. (See Section 35 of Text). 
Channel off Bragdons Island 170 feet wide, 10 feet deep. 
Removing to the same depth projecting shoal just above 
the island. 
Anchorages 8 feet deep north and south of Bragdons 
Island. 
OAK BLUFFS TOWN BEACH, MASS. (See Section 40 
of Text). 
Widening 1,200 feet of beach and construction of 530- 
foot long groin at southern extremity. 
H. Doc. 236, 87th Cong., 1st 
sess. 
Annual Report for 1899, p. 1089. 
H. Doc. 1194, 62d Cong., 3d 
sess. 
H. Doc. 996, 3d sess. 
H. Doc. 124, 87th Cong., 2d sess. 
Annual Report 1915, 1936, 
1938 H. Doc. 173, 75th Cong., 
1st sess. 
S. Doc. 93, 88th Cong., 2d sess. 
S. Doc. 82, 84th Cong., 1st sess. 
Chief of Engineers, Mar. 8, 1960, 
H. Doc. 69, 81st Cong., 1st 
sess.4 
Section 107 of 1960 River and 
Harbor Act, Authorized by 
Chief of Engineers 21 May 
1965. 
H. Doc. 202, 86th Cong., 2d 
sess., Chief of Engineers, 
Sept. 20, 1965.4 
Annual Report for 1907, 1915, 
1932, 1938, 1961, p. 24 & 26 
H. Doc. 247, 88th Cong., 2d 
sess. 
PL 86-645, Section 107, 
Authorized by Chief of Engineers 
16 Jan. 1975. 
H. Doc. 301, 58th Cong., 2d sess. 
H. Ex. Doc. 243, 48th Cong., 
2d sess. 
H. Doc. 395, 86th Cong., 2d 
sess.4 
Section 103 of 1962 River and 
Harbor Act, Authorized by 
Chief of Engineers Apr. 7, 1967. 
1-60

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Sept. 3, 1954 
Oct. 27, 1965 
Dec. 22, 1944 
Dec. 22, 1944 
Aug. 13, 1968 
Mar. 7, 1974 
Dec. 22, 1944 
Sept. 3, 1954 
Aug. 18, 1941 
June 22, 1936 
June 28, 1938 
July 24, 1946 as amended 
July 14, 1960 
July 14, 1960 
July 14, 1960 
June 22, 1936 
June 28, 1938 
PLUM ISLAND, MASS. (See Section 41 of Text). 
Beach and dune restoration. 
REVERE BEACH, MASS. (See Section 42 of Text). 
Placement of sandfill for protection and improvement. 
Raising and widening of about 13,000 feet of beach by 
placement of sandfill. 
WEST HILL DAM, MASS. (See Section 46A of Text). 
Construction of flood control dam on West River, Mass. 
WORCESTER DIVERSION (See Section 46B of Text). 
Construction of diversion tunnel and channel. 
CHARLES RIVER DAM, MASS. (See Section 47 of 
Text). 
Flood control dam and navigation locks on Charles River. 
CHARLES RIVER (NATURAL VALLEY STORAGE 
AREAS), MASS. (See Section 48 of Text). 
Federal acquisition and perpetual protection of 17 
crucial natural valley storage areas totalling 8,422 acres 
in what is known as the Middle and Upper watershed 
of the Charles River. 
BALL MOUNTAIN LAKE, VT. (See Section 49A of 
Text). 
Construction of dam on West River, Vt. 29 miles above 
junction with Connecticut River. 
System of 3 reservoirs on West River, including Ball 
Mountain. 
BARRE FALLS DAM, MASS. (See Section 49B of Text). 
Construction of flood control dam on Ware River in 
Barre, Mass. 
BIRCH HILL DAM, MASS. (See Section 49C of Text). 
General comprehensive plan for flood protection in Conn. 
River Valley. 
Construction of flood control dam on Millers River. 
CHARLESTOWN, N.H. (See Section 49D of Text). 
Emergency Bank Protection to prevent river bank 
erosion. 
CHICOPEE FALLS, MASS. (See Section 49E of Text). 
Flood protection along Chicopee River. 
COLEBROOK RIVER LAKE, CONN. (See Section 49F 
of Text). 
Construction of multi-purpose dam on West Branch 
Farmington River. 
CONANT BROOK DAM, MASS. (See Section 49G of 
Text). 
Construction of flood control dam on Conant Brook. 
KNIGHTVILLE DAM, MASS. (See Section 49H of 
Text). 
Comprehensive plan for Conn. River Valley. 
Construction of flood control dam on Westfield River. 
Section 103 of 1962 River and 
Harbor Act, Authorized by 
Chief of Engineers 1 Feb. 1973. 
H. Doc. 146, 82d Cong., 1st sess. 
H. Doc. 211,91st Cong., 2d sess., 
in accordance with Section 201 
of 1965 Flood Control Act. 
H. Doc. 624, 78th Cong., 2d sess. 
PL 534, 78th Cong. 
H. Doc. 370, 90th Cong., 2d sess. 
Chief of Engineers report dated 
Dec. 6, 1972. 
H. Doc. 724, 76th Cong., 3d 
sess. 
H. Doc. 412, 74th Cong., 2d 
sess. 
H. Doc. 455, 75th Cong., 2d sess. 
PL 79-256, Sec. 14, Authorized 
by Chief of Engineers Dec. 1, 
1971. 
H. Doc. 434, 86th Cong., 2d sess. 
H. Doc. 443, 86th Cong., 2d 
sess. 
H. Doc. 434, 86th Cong., 2d sess. 
H. Doc. 412, 74th Cong., 2d sess. 
H. Doc. 455, 75th Cong., 2d sess. 
1-61

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
June 28, 1938 
Aug. 18, 1941 
June 28, 1938 
Aug. 18, 1941 
Sept. 3, 1954 
Aug. 13, 1968 
July 14, 1960 
June 22, 1936 
June 28, 1938 
Dec. 22, 1944 
Sept. 3, 1954 
June 22, 1936 
June 28, 1938 
June 22, 1936 
June 28, 1938 
July 3, 1958 
June 30, 1948 
Oct. 23, 1962 
July 14, 1960 
LITTLEVILLE LAKE MASS. (See Section 49I of Text). 
Construction of multi-purpose dam on Westfield River. 
NORTH HARTLAND LAKE, VT. (See Section 49J of 
Text). 
Construction of dam on Ottauquechee River. 
Modification of 1938 Act. 
NORTH SPRINGFIELD LAKE, VT. (See Section 49K 
of Text). 
Construction of dam on Black River. 
Modification of 1938 Act. 
OTTER BROOK LAKE, N.H. (See Section 49L of Text). 
Construction of flood control dam on Otter Brook. 
PARK RIVER, HARTFORD, CONN. (See Section 49M 
of Text). 
Flood protection on Park River in Hartford, Conn. 
SUCKER BROOK DAM, CONN. (See Section 49N of 
Text). 
Construction of flood control dam on Sucker Brook. 
SURRY MOUNTAIN LAKE, N.H. (See Section 490 of 
Text). 
Comprehensive plan for Conn. River Valley. 
Construction of flood control dam on Ashuelot River, 
(modification of 1936 Act). 
TOWNSHEND LAKE, VT. (See Section 49P of Text). 
Construction of dam on West River 19 miles above 
junction with Connecticut River. 
System of 3 reservoirs on West River, including 
Townshend. 
TULLY LAKE, MASS. (See Section 49Q of Text). 
Comprehensive plan for Conn. River flood control. 
Construction of flood control dam on East Branch of 
Tully River (modification of 1936 Act). 
UNION VILLAGE DAM, VT. (See Section 49R of 
Text). 
Construction of flood control dam on Ompompanoosuc 
River (part of Conn. River Valley plan). 
Modification of 1936 Act. 
FOX POINT BARRIER, R.I. (See Section 50 of Text). 
Construction of concrete hurricane barrier across 
Providence River at Fox Point in City of Providence. 
HAYWARD CREEK, MASS. (See Section 51 of Text). 
Local flood protection along Hayward Creek in the city 
of Quincy and the town of Braintree. 
ANSONIA-DERBY, CONN. (See Section 52A of Text). 
Flood protection (dikes, floodwalls, channel improvement) 
along Naugatuck River in cities of Ansonia and 
Derby. 
BLACK ROCK LAKE, CONN. (See Section 52B of 
Text). 
Construction of flood control dam on Branch Brook. 
S. Doc. 17, 85th Cong., 1st sess. 
H. Doc. 455, 75th Cong., 2d sess. 
H. Doc. 724, 76th Cong., 3d sess. 
H. Doc. 455, 75th Cong., 2d sess. 
H. Doc. 724, 76th Cong., 3d sess. 
S. Doc. 43,90th Cong., 1st sess. 
H. Doc. 443, 86th Cong., 2d sess. 
H. Doc. 412, 74th Cong., 2d sess. 
H. Doc. 455, 75th Cong., 2d sess. 
H. Doc. 412, 74th Cong., 2d sess. 
H. Doc. 455, 75th Cong., 2d sess. 
H. Doc. 412, 74th Cong., 2d sess. 
H. Doc. 455, 75th Cong., 2d sess. 
H. Doc. 230, 85th Cong., 1st sess. 
PL 80-858, Sec. 205, as 
amended, Authorized by Chief 
of Engineers, Mar. 28, 1975. 
H. Doc. 437, 86th Cong., 2d sess. 
H. Doc. 372, 86th Cong., 2d seas. 
1-62

TABLE 1-B (Continued) 
Acts 
Oct. 27, 1965 
Oct. 27, 1965 
July 14, 1960 
July 14, 1960 
July 24, 1946 as amended 
July 14, 1960 
Dec. 22, 1944 
June 22, 1936 
June 28, 1938 
June 22, 1936 
June 28, 1938 
June 22, 1936 
June 28, 1938 
June 28, 1938 
Nov. 7, 1966 
Nov. 7, 1966 
July 3, 1958 
NEW ENGLAND DIVISION 
AUTHORIZING LEGISLATION 
Work Authorized 
DANBURY, CONN. (See Section 52C of Text). 
Flood protection (channel improvement) along Still 
River in city of Danbury. 
DERBY, CONN. (See Section 52D of Text). 
Flood protection (levees and floodwalls) along Naugatuck 
and Housatonic Rivers at their confluence in city 
of Derby. 
HANCOCK BROOK LAKE, CONN. (See Section 52E 
of Text). 
Construction of flood control dam on Hancock Brook 
in town of Plymouth. 
HOP BROOK LAKE, CONN. (See Section 52F of Text). 
Construction of flood control dam on Hop Brook in 
city of Waterbury, towns of Middlebury and Naugatuck. 
LEE, MASS. (See Section 52G of Text). 
Construction of stream bank protection project along the 
Housatonic River in Lee. 
NORTHFIELD BROOK LAKE, CONN. (See Section 
52H of Text). 
Construction of flood control dam on Northfield Brook 
in town of Thomaston. 
THOMASTON DAM, CONN. (See Section 521 of Text). 
Construction of flood control dam on Naugatuck River 
in town of Thomaston. 
BLACKWATER DAM, N.H. (See Section 53A of Text). 
System of flood control dams in Merrimack River Basin, 
including dam on Blackwater River. 
Modification of 1936 Act. 
EDWARD MACDOWELL LAKE, N.H. (See Section 
53B of Text). 
System of flood control dams in Merrimack River 
Basin, including dam on Nubanusit Brook in West 
Peterborough. 
Modification of 1936 Act. 
FRANKLIN FALLS DAM, N.H. (See Section 53C of 
Text). 
System of flood control dams in Merrimack River 
Basin, including dam on Pemigewasset River in 
Franklin, N.H. 
Modification of 1936 Act. 
HOPKINTON-EVERETT LAKES, N.H. (See Section 
53D of Text). 
Modification of 1936 Act (Merrimack River Basin) to 
include flood control dams on the Contoocook and 
Piscataquog Rivers. 
NOOKAGEE LAKE, MASS. (See Section 53E of 
Text). 
Multi-purpose dam on Phillips Brook in Westminster. 
SAXONVILLE, MASS. (See Section 53F of Text). 
Flood control, local protection project on Sudbury 
River in Saxonville, Mass. 
NEW BEDFORD, FAIRHAVEN AND ACUSHNET, 
MASS. (See Section 54 of Text). 
Hurricane barriers in New Bedford Harbor. 
1-63 
Documents 
H. Doc. 324, 88th Cong., 2d sess. 
H. Doc. 324, 88th Cong., 2d sess. 
H. Doc. 372, 86th Cong., 2d sess. 
H. Doc. 372, 86th Cong., 2d sess. 
PL 79-256, Sec. 14, Authorized 
by Chief of Engineers 7 May 
1974. 
H. Doc. 37 2, 86th Cong., 2d sess. 
H. Doc. 338, 77th Cong., 1st sess. 
H. Doc. 689, 75th Cong., 3d sess. 
H. Doc. 689, 75th Cong., 3d sess. 
H. Doc. 689, 75th Cong., 3d sess. 
H. Doc. 689, 75th Cong., 3d sess. 
S. Doc. 113, 89th Cong., 2d sess. 
S. Doc. 61, 89th Cong., 2d sess. 
S. Doc. 59, 85th Cong., 1st sess.

TABLE 1-B (Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Oct. 27, 1965 
June 30, 1948 
June 30, 1948 
July 14, 1960 
Aug. 18, 1941 
Aug. 18, 1941 
Aug. 18, 1941 
Aug. 18, 1941 
July 14, 1960 
Aug. 18, 1941 
NEW LONDON, CONN. (See Section 55 of Text). 
Hurricane barriers protecting city of New London from 
tidal damage. 
DICKEY-LINCOLN SCHOOL LAKES, ME. (See 
Section 56A of Text). 
Construction of multi-purpose project on the upper 
St. John River to provide for power, flood control and 
recreation. 
FORT KENT, ME. (See Section 56B of Text). 
Local Flood Protection on the St. John River, town of 
Fort Kent. 
SMELT BROOK, WEYMOUTH-BRAINTREE, MASS. 
(See Section 57 of Text). 
Local flood protection along Smelt Brook in the towns 
of Weymouth and Braintree. 
STAMFORD, CONN. (See Section 58 of Text). 
Hurricane barriers protecting areas of Stamford from 
tidal damage. 
BUFFUMVILLE LAKE, MASS. (See Section 59A of 
Text). 
Flood control dam on Little River as part of flood control 
system in Thames River Basin. 
EAST BRIMFIELD LAKE, MASS. (See Section 59B 
of Text). 
Flood control dam on Quinebaug River as part of flood 
control system in Thames River Basin. 
HODGES VILLAGE DAM, MASS. (See Section 59C 
of Text). 
Flood control dam on French River in Oxford as part 
of flood control system in Thames River Basin. 
MANSFIELD HOLLOW LAKE, MASS. (See Section 
59D of Text). 
Flood control dam on Natchaug River in Mansfield 
Hollow as part of flood control system in Thames 
River Basin. 
WEST THOMPSON LAKE, CONN. (See Section 59E 
of Text). 
Flood control dam on Quinebaug River in Thompson. 
WESTVILLE LAKE, MASS. (See Section 59F of Text). 
Flood control dam on Quinebaug River in towns of 
Sturbridge and Southbridge as part of flood control 
system in Thames River Basin. 
H. Doc. 478, 87th Cong., 2d sess. 
H. Doc. 236, 89th Cong., 1st sess. 
PL 80-858, Sec. 205, as 
amended, Authorized by Chief 
of Engineers, Sept. 25, 1975. 
PL 80-858, Sec. 205, as 
amended, Authorized by Chief 
of Engineers, July 10, 1973. 
H. Doc. 210, 86th Cong., 1st sess. 
H. Doc. 885, 76th Cong., 3d sess. 
H. Doc. 885, 76th Cong., 3d sess. 
H. Doc. 885, 76th Cong., 3d sess. 
H. Doc. 885, 76th Cong., 3d sess. 
S. Doc. 41, 86th Cong., 1st sess. 
H. Doc. 885, 76th Cong., 3d sess. 
1. Contains latest published maps. See also Annual 8. Quinnipiac River 22-foot channel and turning 
Report, 1911, p. 1178 (seawalls and Nixes Mate Chan- basin deferred for restudy. 
nel) and Annual Report, 1903, p. 770 (Fort Point 9. 15- and 12-foot channel and basin inactive. 
Channel). 10. H. Doc. 467, 69th Cong., 1st sess., recommended 
2. Authorized in part by Public Works Administra- eliminating maintenance dredging. 
tion, Sept. 6, 1933. 11. Removal of rock in Yellow Mill Pond inactive - 
3. A portion deferred for restudy, not presently required. 
4. Contains latest maps. 12. Black Rock Harbor breakwater; Burr and Cedar 
5. Inactive. Creek anchorage inactive. 
6. Rock removal at Hog Island Shoal inactive. 13. A portion has been abandoned pursuant to PL 91- 
7. Also Public Works Administration, Sept. 6, 1933. 624, Dec. 31, 1970. 
1-64

NEW ENGLAND DIVISION 
TABLE 1-C BOSTON HARBOR, MASS. 
Total Federal Cost for Existing Project to 30 June 1975 
(See Section 3 of Text) 
Funds New Work Maintenance Total 
Regular $21,881,851 $6,078,981 $27,960,832 
Public Works 1,030,806 - 1,030,806 
Emergency Relief 935,303 - 935,303 
$23,847,960 $6,078,9811 $29,926,941 
SExcludes $17,767 contributed funds. 
TABLE 1-D RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 36 of Text) 
Date Survey Date Survey 
Project Conducted Project Conducted 
Connecticut 
Branford Harbor 
Bridgeport Harbor 
Clinton Harbor 
Connecticut River below 
Hartford 
Duck Island Anchorage 
Housatonic River 
Mianus River 
Mystic River 
New Haven Harbor 
Norwalk Harbor 
Patchogue River 
Southport Harbor 
Stamford Harbor 
Stony Creek 
Thames River 
Westport Harbor 
Maine 
Bass Harbor Bar 
Bass Harbor 
Beals Harbor 
Belfast Harbor 
Boothbay Harbor 
Bucksport Harbor 
Bunker Harbor 
Camden Harbor 
Cape Porpoise Harbor 
Corea Harbor 
Georges River 
Josias River 
Narraguagus River 
Owls Head Harbor 
Penobscot River 
Pepperell Cove 
Portland Harbor 
Royal River 
Saco River 
Searsport Harbor 
Stockton Harbor 
Wells Harbor 
Wood Island Harbor 
May 197 5 
Mar 197 5 
Jan 1975 
Sep 1974 
Jul 1974 
Sep 1974 
Jun 1975 
Jan 1975 
Mar 1975 
Mar 1975 
Mar 1975 
Jan 1975 
May 1975 
Feb 1975 
Apr 1975 
Mar 1975 
Aug 1974 
Aug 1974 
Jul 1974 
Jul 1974 
Apr 1975 
Sep 1974 
Oct 1974 
Dec 1974 
Nov 1974 
Jul 1974 
Nov 1974 
May 1975 
Jul 1974 
Feb 1975 
Apr 1975 
Aug 1974 
Nov 1974 
May 1975 
Feb 1975 
Oct 1974 
Nov 1974 
Sep 1974 
Dec 1974 
Massachusetts 
Annisquam River, Gloucester 
Beverly Harbor 
Boston Harbor 
Cohasset Harbor 
Duxbury Harbor 
Essex River, Gloucester 
Falmouth Harbor 
Gloucester 
Hingham Harbor 
Hyannis Harbor 
Little Harbor 
Lynn 
Nantucket Harbor 
Neponset R., Dorchester Bay 
New Bedford Harbor 
Plymouth Harbor 
Wellfleet Harbor 
Woods Hole 
New Hampshire 
Little Harbor 
Portsmouth Harbor 
Rye Harbor 
Rhode Island 
Apponaug Cove 
Block Island, Harbor of 
Refuge 
Block Island, Great Salt 
Pond 
Point Judith Harbor 
Seekonk River 
Warwick Cove 
Watch Hill Cove (Pawcatuck) 
Wickford Harbor 
New York 
Hay West Harbor 
1-65 
Jun 197 5 
Aug 1974 
May 1975 
Nov 1974 
Dec 1974 
Feb 197 5 
Nov 1974 
Jul 1974 
Aug 1974 
Apr 1975 
Apr 1975 
Sep 1974 
Jul 1974 
Jul 1974 
Dec 1974 
Jul 1974 
Feb 1975 
Nov 197 4 
Mar 1975 
Oct 1974 
Oct 1974 
Jul 1974 
Jan 197 5 
Feb 197 5 
Oct 1974 
Dec 1974 
Nov 1974 
Oct 1974 
Sep 1974 
Aug 1974

TABLE 1-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 37 of Text) 
For last Cost to June 30, 1975 
Name of Project full report Contributed 
see Annual Operation and Funds Expended 
Report for Construction Maintenance (Construction) 
Apponaug Cove, R.I.' 
Bagaduce River, Me. 3 ,4,s 
Bar Harbor, Me.s 
Bass Harbor, Me. 
Bass Harbor Bar, Me.' 
Beals Harbor, Me.' 
Belfast Harbor, Me.' 
Bellamy River, N.H. 1 ' , 3 ,4 
Beverly Harbor, Mass.' 
Boothbay Harbor, Me. 1 ,4 
Bristol Harbor, R.I. 
Bucksport Harbor, Me.' 
Bullocks Point Cove R.I.' 
Bunker Harbor, Me.i,6 
Buttermilk Bay Channel, Mass.' 
Camden Harbor, Me.' 
Canapitsit Channel, Mass.',4 
Cape Porpoise Harbor, Me.' 
Carvers Hbr., Vinalhaven, Me.' 
Cathance River, Me.' 1 ,3 , 4 
Chatham (Stage) Harbor, Mass. 
Coasters Island Harbor, R.I.' ,4 
Cobscook Bay, Me. 1,3,4 
Cocheco River, N.H. 1 ,3 ,4 
Cohasset Harbor, Mass. 1, 6 
Connecticut River (above 
Hartford), Conn. 8 
Corea Harbor, Me.' 
Cotuit Harbor, Mass. 8 
Criehaven Harbor, Me.1 
Cross Rip Shoals, Nantucket 
Sound, Mass.' 
Damariscotta River, Me.1,4 
Deer Island Thoroughfare, Me.' ,4 
Dorchester Bay and Neponset 
River, Mass.' 1 
Duck Island Harbor, Conn. 1 
Duxbury Harbor, Mass. 
East Boothbay Harbor, Me. 1 
Eastport Harbor, Me. I 
Essex River, Mass.' 
Exeter River, N.H. 1 ,4 
Falmouth Harbor, Mass.' 
Fivemile River Harbor, Conn.5 
Georges River, Me. ,1 s5 
Gloucester Harbor and 
Annisquam River, Mass. 
Great Salt Pond, Block Island, R.I. 5 
Greenwich Bay, R.I.' 
Greenwich Harbor, Conn. 1 
Harbor of Refuge, Block Island, 
R.I.s 
Harbor of Refuge, Point Judith, 
R.I. 
Harraseeket River, Me. 1 ,4 
Hay (West Harbor), Fisher's 
Island, N.Y.' 
Hendrick's Harbor, Me. 1' 
Hingham Harbor, Mass.' 
Ipswich River, Mass. 
Isle au Haut Thoroughfare, Me.' 
Josias River, Me.1 
Kingston Harbor (North Plymouth), 
Mass. 1 
Lamprey River, N.H. 1 ,4 
Little Harbor, Woods Hole, Mass.' ,4 
Lubec Channel, Me. 1 
Lynn Harbor, Mass. 1 9 
Machias River, Me.1 
Malden River, Mass. 1,2 o 
1964 
1912 
1932 
1965 
1920 
1959 
1971 
1897 
1951 
1953 
1969 
1907 
1974 
1969 
1960 
1960 
1899 
1954 
1964 
1884 
1974 
1911 
1866 
1913 
1974 
1932 
1954 
1962 
1939 
1954 
1906 
1916 
1968 
1953 
1969 
1953 
1974 
1948 
1913 
1965 
1969 
1935 
1973 
1973 
1893 
1969 
1974 
1972 
1896 
1931 
1957 
1954 
1969 
1959 
1971 
1895 
1913 
1906 
1956 
1956 
1972 
1922 
$. 156,8742 
28,000 
406,591 
188,859 
4,076 
184,880 
61,561 
34,643 
246,048 
18,000 
0 
18,421 
170,902 
95,372 
31,676 
102,400 
9,113 
175,037 
190,438 
21,000 
266,705 
5,500 
4,173 
119,089 
279,072 
116,324 
31,707 
8,541 
40,776 
24,200 
5,000 
40,000 
94,584 
482,166 
421,29712 
6,500 
638,675 
21,759 
27,454 
123,763 
35,490 
25,788 
1,296,934 
189,037 
2,000 
198,758 
576,856 
2,500,430' 3 
30,963 
8,401 
28,204 
28,316 
5,618 
137,653 
115,565 
8,940 
19,980 
18,000 
380,322 
755,576 
32,000 
104,853 
$ 13,625 
39 
2,187 
13,187 
8,828 
23,305 
197,983 
13,483 
15,685 
0
8,981 
29,109 
27,081 
50,525 
125,936 
6,434 
37,528 
9,021 
0 
972,447 
13,161 
0 
24,694 
70,952 
14,374 
63,888 
0
8,125 
54,328 
905 
0 
267,334 
368,165 
200,892 
17,238 
42,341 
68,778'14 
3,032 
47,030 
141,263 
47,979 
1,073,026 
283,313 
6,527 
174,667 
1,135,550 
1,342,930 
5,309 
1,908 
6,325 
66,320 
2,166 
966 
64,273 
10,221 
5,224 
13,583 
108,134 
166,864 
45,097 
$
100,000 
123,757 
20,000 
43,500 
100,835 
141,530 
35,000 
25,000 
100,000 
17,587 
26,813 
62,000 
1-66

NEW ENGLAND DIVISION 
TABLE 1-E (Cont.) OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 37 of Text) 
For last Cost to June 30, 1975 
Name of Project full report Contributed 
see Annual Operation and Funds Expended 
Report for Construction Maintenance (Construction) 
Manchester Harbor, Mass. 8 
Marblehead Harbor, Mass. 8 
Matinicus Harbor, Me. 1 
Mattapoisett Harbor, Mass.4 ,8 
Medomak River, Me. 1 
Menemsha Creek, Martha's Vineyard, 
Mass.' 
Merrimack River, Mass. 1 
Mianus River, Conn. 1 
Milford Harbor, Conn.s 
Moosabec Bar, Me.' 
Mystic River, Conn.s 
Mystic River, Mass. 1 
Nantucket (Harbor of Refuge), Mass.s 
Narragaugus River, Me. 1 
New Bedford and Fairhaven Harbor, 
Mass.s 
New Harbor, Me. 1 
New Haven Breakwater, Conn.1 
New London Harbor, Conn.1 
Newport Harbor, R.I.' 
Niantic Bay and Harbor, Conn.1 
Northeast Harbor, Me.l 
Norwalk Harbor, Conn. 1 
Owls Head Harbor, Me.2 s 5 
Patchogue River, Conn.1 
Pawcatuck River, R.I. and Conn.s 
Penobscot River, Me. 1 
Pepperell Cove, Me.s 
Pig Island Gut, Me. 1 ,6 
Pleasant Bay, Mass. 
Pleasant River, Me. 1 ,4 
Pollock Rip Shoals, Nantucket Sound, 
Mass. 1 
Portland Harbor, Me. 1 
Portsmouth Harbor and Piscataqua 
River, Me. and N.H.1 
Potowomut River, R.I.1,4 
Provincetown Harbor, Mass.s 
Red Brook Harbor, Bourne, Mass.8 
Richmond Harbor, Me. 1 ,4 
Richmond's Island Harbor, Me. 1 ,4 
Rockport Harbor, Mass. 1 
Rockport Harbor, Me. 1 ,3 
Royal River, Me.1 
Rye Harbor, N.H.' 
Saco River, Me. 
St. Croix River, Me.1 
Sakonnet River, R.I.1 ,1 
Sakonnet Harbor, R.I.' 
Salem Harbor, Mass.s 
Sandy Bay (Harbor of Refuge), 
Cape Ann, Mass.s,1s8 
Sasanoa River, Me. 1 ,3,4 
Scituate Harbor, Mass. 1 
SearSport Harbor, Me. 1 
Seekonk River, R.I.' 
South Bristol Harbor, Me. 1 
Southport Harbor, Conn. 1 
Southwest Harbor, Me.1 
Stamford Harbor, Conn.s 
Stockton Harbor, Me.1 ,3,4 
Stonington Harbor, Conn.s 
Stonington Harbor, Me. 8 
Stony Creek, Branford, Conn. 1 
Sullivan Falls Harbor, Me. 1 
Taunton River, Mass.s 
Tenants Harbor, Me.' 
Thames River, Conn.s 
Union River, Me.3,'1 s 5 
1949 
1968 
1962 
1950 
1953 
1974 
1940 
1964 
1974 
1930 
1957 
1967 
1965 
1969 
1953 
1966 
1950 
1954 
1953 
1972 
1954 
1973 
1968 
1973 
1963 
1969 
1969 
1966 
1971 
1892 
1956 
1972 
1972 
1882 
1974 
1972 
1883 
1882 
1974 
1915 
1971 
1965 
1972 
1950 
1909 
1974 
1969 
1922 
1915 
1971 
1966 
1954 
1971 
1962 
1962 
1972 
1915 
1959 
1961 
1972 
1914 
1948 
1920 
1967 
1912 
$ 23,986 
43,711 
14,00021 
17,000 
56,926 
369,891 
132,435 
90,506 
114,000 
197,582 
3,222,777 
502,6612 3 
821,144 
1,857,618 
118,62024 
1,242,246 
608,774 
733,524 
66,464 
138,942 
531,129 
124,158 
150,000 
318,787 
501,020 
171,351 
191,753 
0
3,500 
1,083,504 
9,588,710 
5,384,043 
5,000 
3,548,954 
38,764 
20,000 
119,844 
22,000 
32,000 
336,704 16 
130,34217 
663,739 
179,550 
38,427 
588,478 
1,693,202 
1,925,553 
35,000 
379,8512 
572,5682 6 
672,214 
89,593 
96,9277 
180,042 
892,824 
33,000 
377,328 
2,543 
112,487 
19,871 
442,895 
18,750 
1,471,919 
146,855 
584 
8,989 
92,359 
475,292 
158,224 
80,950 
294,535 
16,780 
104,932 
719,036 
403,902 
17,060 
680,938 
21,705 
40,273 
246,974 
75,780 
3,299 
1,116,837 
6,945 
164,228 
390,152 
565,989 
18,946 
9,700 
0 
217 
846,590 
1,738,538 
379,533 
50 
261,910 
1,808 
70,843 
96,475 
12,145 
896,616 
14,004 
1,559 
100,041 
266,995 
15,926 
124 
67,599 
12,912 
793,234 
4,438 
202,880 
9,109 
508,713 
17,112 
100,269 
5,765 
32,917 
12,678 
1,327,687 
17,344 
12,500 
46,500 
11,380 
14,000 
20,385 
7,015 
67,500 
34,500 
4,383 
100,000 
20,000 
99,707 
760,000 
49,562 
61,338 
78,474 
19,892 
21,928 
69,976 
67,792 
2,663 
18,525 
7,501 
169,636 
92,000 
1-67

TABLE 1-E (Cont.) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 37 of Text) 
For last Cost to June 30, 1975 
Name of Project full report Contributed 
see Annual Operation and Funds Expended 
Report for Construction Maintenance (Construction) 
Vineyard Haven, Mass. 1 1943 $ 27,186 $ 8,699 $ 
Wareham Harbor, Mass.s 1896 95,997 258 
Warren River, R.I.1 1890 5,000 - 
Wellfleet Harbor, Mass.1 1972 157,634 215,170 32,000 
Westcott Cove, Conn.1 1972 55,960 49,593 21,000 
Westport Harbor and Saugatuck 
River, Conn.s 1972 19,308 169,253 
Westport River, Mass.4 ,9 1942 - - 
Weymouth Back River, Mass. 1 1944 48,740 3,860 20,000 
Wickford Harbor, R.I.1,2 2 1973 233,410 63,314 49,094 
Wilson Point Harbor, Conn. 1 ,4 1895 54,177 - 
Winnipesaukee Lake, N.H. 1 1952 7,500 29,870 
Winthrop Harbor, Mass. 1 1895 8,992 6,752 
Wood Island Harbor, Me. and Pool 
at Biddeford1 1957 135,612 12,451 12,000 
Woods Hole Channel, Mass. 1 1940 230,000 23,069 
1. Completed. 16. Excludes $18,000 contributed funds "other" 
2. Excludes costs of $137,583 for local cooperation expended. 
requirements, which includes $104,583 cash contribution. 17. Excludes $81,548 contributed funds "other" 
3. Abandonment recommended in H. Doc. 467, expended. 
69th Congress, 1st session. 18. Abandonment recommended in H. Doc. 411, 
4. No commerce reported. 64th Congress, 1st session, and in River and Harbor 
5. Completed except for inactive portion. Committee Doc. 3, 65th Congress, 1st session. 
6. Authorized by the Chief of Engineers (Public Law 19. Improvement to be restudied. 
86-645, Sec. 107). 20. Under State maintenance. 
7. Includes $37,714 emergency relief funds. Excludes 21. Excludes $114,327 expended for rehabilitation; 
$18,525 contributed funds, of which $1,785 was for breakwater repaired in 1962. 
work outside approved project. 22. Portion of project authorized by Chief of Engi- 
8. Inactive. neers (Public Law 86-645, Sec. 107). 
9. Awaiting local cooperation. Improvement to be 23. Excludes $211,649 expended for rehabilitation; 
restudied. jetty repaired in 1963. 
10. Commerce included under Tiverton Harbor, R.I. 24. All assurances of local cooperation have not been 
11. Authorized work remaining on project is com- fulfilled. Public landing at Back Cove has not been conprised 
of an incomplete and an inactive portion. structed. Portion of project authorized by Chief of 
12. Excludes local cooperation requirements of Engineers (Public Law 86-645, Sec. 107). 
$100,000, consisting of $35,000 cash contribution, 25. Recommendation for abandonment of existing 
$13,000 for public wharf, and $52,000 for additional project made in H. Doc. 467, 69th Congress, 1st session. 
construction costs. Portion of project authorized by the Chief of Engineers 
13. Excludes $1,926,000 Federal funds for (Public Law 86-645, Sec. 107) is complete. 
rehabilitation. 26. Costs to local interests for berth improvements 
14. Excludes $5,000 contributed funds expended. are estimated to be $60,000. 
15. Improvement adequate for commerce. 
TABLE 1-F NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 (PREAUTHORIZATION) 
(See Section 38 of Text) 
Study Identification Fiosal Year 
Brushneck Cove, Warwick, R.I. $10,302 
Lake Tashmoo, Tisbury, Mass. 4,360 
Newport Harbor, R.I. 6,615 
Sesuit Harbor, Dennis, Mass. 27,812 
Westport River, Mass. 12,537 
1-68

NEW ENGLAND DIVISION 
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
(See Section 44 of Text) 
For Last 
Project Full Report Cost to Amount 
See Annual June 30, 1975 Expended by 
Report For Construction Local Interests 
Brant Rock Beach, Marshfield, Mass. 
Burial Hill Beach, Westport, Conn.1 
Calf Pasture Beach Park, Norwalk, Conn.' 
Clark Point, New Bedford, Mass. 
Cliff Walk, Newport, R.I.8 
Compo Beach, Westport, Conn.1 
Cove Island, Stamford, Conn.1 
Cummings Park, Stamford, Conn.1 
Greenwich Point Park, Conn. 4 
Guilford Point Beach (Jacobs Beach), Guilford, Conn.' 
Gulf Beach, Milford, Conn.1 
Hammonasset Beach, Madison, Conn.' 
Hampton Beach, Hampton, N.H.1 
Jennings Beach, Fairfield, Conn.' 
Lighthouse Point Park (Area 9), Conn.1 
Lynn-Nahant Beach, Mass. 
Matunuck Beach, South Kingston, R.I. 2 
Middle Beach, Conn.1 
Misquamicut Beach, Westerly, R.I.3 
Nantasket Beach, Mass. 4 
Napatree Beach, R.I.4 
North Hampton Beach, North Hampton, N.H. 4 
North Scituate Beach, Scituate, Mass. 1 
Prospect Beach, West Haven, Conn.1 
Provincetown Beach, Provincetown, Mass. 4 
Quincy Shore Beach, Quincy, Mass.' 
Sand Hill Cove Beach, R.I.' 
Sasco Hill Beach, Fairfield, Conn.' 
Seaside Park, Conn.' 
Sherwood Island State Park, Conn.' 
Short Beach, Conn. 1 
Silver Beach to Cedar Beach, Conn. 
Southport Beach, Conn.1 
Thumpertown Beach, Eastham, Mass. 
Town Beach, Plymouth, Mass. 
Town Neck Beach, Sandwich, Mass. 
Wallis Sands State Beach, Rye, N.H.' 
Wessagusset Beach, Weymouth, Mass. 1 
Winthrop Beach, Mass. 
Woodmont Shore, Milford, Conn.' 
1961 
1958 
1964 
1963 
1973 
1962 
1961 
1963 
1959 
1961 
1958 
1956 
1966 
1956 
1961 
1961 
1958 
1963 
1971 
1963 
1969 
1958 
1961 
1962 
1959 
1961 
1958 
1959 
1964 
1960 
1961 
1964 
1961 
1966 
1971 
1960 
1961 
5,810 
56,386 
290,491 
84,544 
47,131 
26,886 
15,620 
21,303 
163,183 
260,868 
14,401 
3,930 
8,810 
14,512 
106,552 
104,573 
621,440 
40,143 
23,759 
150,000 
186,8305 
62,560 
17,631 
5,490 
65,131 
180,944 
176,5676 
53,838 
1. Completed. 
2. Project is to be included in Point Judith water 
resources development plan authorized by 1962 River 
and Harbor Act. 
3. Additional Federal participation will be required 
based on Public Law 87-874. 
4. Project inactive. 
5. Project completed at no cost to Federal Government 
by using fill from Federal navigation improvement 
at Housatonic River. 
6. Project is 79% complete. In addition to uncompleted 
work, there are three additional groins, construction 
of which is deferred until it is determined that they 
are necessary. 
7. Excludes $118,215 expended for work beyond 
scope of project. 
8. Completed except for inactive portion. 
1-69 
TABLE 1-G 
- 
11,612 
120,179 
955,237 
169,089 
94,262 
53,771 
31,241 
42,606 
326,366 
385,641 
28,802 
7,859 
17,620 
29,024 
106,552 
240,819 
1,242,880 
82,000 
47,518 
329,921 
372,802 
270,695 
35,263 
10,981 
435,942 
200,208 
353,134 
111,679'

TABLE 1-H 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
BEACH EROSION ACTIVITIES PURSUANT TO SECTION 103, 
PUBLIC LAW 87-874 (PREAUTHORIZATION) 
(See Section 45 of Text) 
Study Identification Fiscal Year Cost 
Lynn-Nahant Beach, Mass. $2,800 
TABLE 1-I BLACKSTONE RIVER BASIN, MASS. AND R.I. 
(See Section 46 of Text) 
RESERVOIR 
Miles 
Above Estimated Federal Cost 
Mouth of 
Black- Reservoir Lands 
stone Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
West Hill2 Worcester, Mass. 25.8 51 Earthfill 12,400 $1,367,000 $940,000 $2,307,000 
1. Includes highway, railroad, and utility relocations. 
2. See individual report for details. 
LOCAL PROTECTION PROJECTS 
Miles 
Above Estimated Costs 
Mouth of 
Black- Lands 
stone and 
Location River Type of Structure Construction Damages' Total 
Worcester, Mass.4 48 Diversion tunnel and channel $4,923,500 $1,179,0002 $6,102,500 
Woonsocket, R.I. 15 Channel improvement 3,740,100 .1,069,0003 4,809,100 
Lower Woonsocket, R.I.4 13 Floodwall, conduits and 8,150,000 1,000,000 9,150,000 
channel improvement 
Pawtucket, R.I.s 2 Floodwall 202,000 - 202,000 
1. Includes relocations. 
2. $158,000 Federal; $1,021,000 non-Federal. 
3. $300,000 Federal; $769,000 non-Federal. 
4. See individual report for details. 
5. Inactive, cost revised in 1954. 
1-70

NEW ENGLAND DIVISION 
CONNECTICUT RIVER BASIN, VT., N.H., MASS. AND CONN. 
(See Section 49 of Text) 
DAMS AND RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of Reservoir Lands 
Connecticut Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
Vermont: 
Victory 1 0 St. Johnsbury 
South Tunbridge3 Barre 
Union Village 2 White River 
Junction 
Gaysville o Rutland 
North Hartland 2 White River 
Junction 
Ludlow 3 Rutland 
North Springfield 2 Springfield 
Brockway3 Bellows Falls 
The Island Brattleboro 
Cambridgeport 3 Bellows Falls 
Ball Mountain2 Brattleboro 
Townshend 2 Brattleboro 
New Hampshire: 
Sugar Hill4 
West Canaan 3 
Claremont 9 
Surry Mountain 2 
Otter Brook 2 
Beaver Brook 
Honey Hill4 
Massachusetts: 
Birch Hill2 
Tully 2 
Barre Falls2 
Knightville2 
Littleville 2 
West Brookfield 7 
Conant Brook2 
Connecticut: 
Colebrook River 2 
Mad River 
Sucker Brook2 
Woodsville 
Lebanon 
Claremont 
Keene 
Keene 
Keene 
Keene 
Gardner 
Athol 
Worcester 
Northampton 
Northampton 
Worcester 
Springfield 
Winsted 
Winsted 
Winsted 
306.0 90 
234.5 105 
228.4 170 
246.8 192 
211.7 185 
211.8 118 
191.3 120 
182.0 122 
189.6 100 
180.3 101 
178.2 265 
168.3 133 
280.9 
233.8 
202.4 
174.4 
171.2 
170.7 
168.9 
153.3 
148.7 
130.2 
102.8 
102.0 
100.5 
122.0 
116.0 
120.0 
118.5 
163 
80 
138 
86 
133 
60 
65 
56 
62 
62 
160 
150 
30 
85 
Earthfill 106,000 $ 4,087,000 $ 1,413,000 $ 5,500,000 
Earthfill 32,600 3,138,000 2,302,000 5,440,000 
Earthfill 38,000 3,102,400 908,300 4,010,700 
Earthfill 82,500 
Earthfill 71,400 
Earthfill 23,900 
Earthfill 50,600 
Earthfill 37,700 
Earthfill 19,400 
Earthfill 21,600 
Rockfill- 54,600 
earth 
Earthfill 33,200 
Earthfill 91,600 
Earthfill 51,000 
Earthfill 78,400 
Earthfill 32,500 
Earthfill 18,300 
Earthfill 5,750 
Earthfill 26,200 
Earthfill 49,900 
Earthfill 22,000 
Rockfill- 24,000 
earth 
Earthfill 49,000 
Earthfill 32,400 
Earthfill 33,000 
Rockfill- 3,740 
earth 
223 Rockfill- 98,500 
earth 
178 Earthfill 9,700 
68 Earthfill 1,480 
13,700,000 15,000,000 
6,331,000 963,000 
2,532,000 3,158,000 
4,782,000 2,050,000 
4,801,000 5,899,000 
3,670,000 1,110,000 
4,078,000 1,092,000 
10,535,200 350,000 
5,530,000 1,870,000 
3,500,000 3,385,000 
3,471,000 5,589,000 
11,020,000 3,800,000 
2,305,000 385,000 
2,682,600 1,378,400 
3,005,000 1,395,000 
2,662,000 1,398,000 
2,347,000 3,075,000 
1,383,600 368,000 
1,928,800 39,000 
2,879,200 821,200 
5,863,400 1,150,000 
3,422,000 5,568,000 
1,936,000 1,015,000 
28,700,000 
7,294,000 
5,690,000 
6,832,000 
10,700,000 
4,780,000 
5,170,000 
10,885,200 
7,400,000 
6,885,000 
9,060,000 
14,820,000 
2,690,000 
4,061,000 
4,400,0008 
4,060,000 
5,422,000 
1,751,600 
1,967,800 
3,700,400 
7,013,400 
8,990,000 
2,951,000 
8,342,000 5,922,000 14,264,000 
3,380,000 2,210,000 s 5,590,000 
2,550,000 180,0006 2,730,000 
1. Includes highway, railroad and utility relocation. 
2. For details, see individual report. 
3. Inactive; cost last revised in 1954. 
4. Alternative site to be selected. Cost has not been 
revised on current price basis. 
5. Non-Federal $670,000; Federal $1,540,000. 
6. Non-Federal cost. 
7. Deauthorized by House Document 434, 88th 
Congress, 2d Session. 
8. Includes $750,000 non-Federal cash contribution 
and $1,900,000 non-Federal reimbursement cost; 
inactive. 
9. Deauthorized by Rivers and Harbors Act of 1970. 
10. Inactive cost has not been revised on current price 
basis. 
1-71 
TABLE 1-J

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 1-J (Continued) LOCAL PROTECTION PROJECTS 
Miles Above Estimated Cost 
Mouth of 
Connecticut Lands and 
Location River Type of Structure Construction Damages1 Total 
Hartford, Vt. 216 Channel improvement $ 332,000 $ - $ 332,000 
Charlestown, N.H.2 181 Riverbank protection 114,000 - 114,000 
Weston, Vt. 195 Channel improvement 13,000 2,000 15,000 
Keene, N.H. 167 Channel improvement 44,000 - 44,000 
Gardner, Mass. 163 Dam and levee 493,900 35,000 528,900 
Northampton, Mass. 94 Wall and levee 960,000 150,000 1,110,000 
Holyoke, Mass. 85 Wall and levee 3,418,000 150,000 3,568,000 
Springdale, Mass. 84 Wall and levee 700,000 57,000 757,000 
West Warren, Mass. 111 Wall and levee 390,000 64,000 454,000 
Ware, Mass. 110 Channel improvement 400,000 85,000 485,000 
Three Rivers, Mass. 98 Wall and levee 1,580,000 700,000 2,280,000 
Chicopee, Mass. 80 Wall and levee 1,7 38,000 250,000 1,988,000 
Chicopee Falls, Mass. 2 83 Wall and levee 2,600,000 70,000 2,670,000 
Huntington, Mass. 100 Riverbank protection 4,000 - 4,000 
Riverdale, Mass. 80 Wall and levee 1,138,000 50,000 1,188,000 
Springfield, Mass. 76 Wall and levee 932,000 272,000 1,204,000 
West Springfield, Mass. 76 Wall and levee 1,579,0003 30,000 1,609,000 
Winsted, Conn. 115 Channel improvement 246,000 30,000 276,000 
East Hartford, Conn. 52 Wall and levee 2,135,000 271,000 2,406,000 
Hartford, Conn. 52 Wall and levee 6,930,0004 1,150,000 8,080,000 
Park River, Conn.2 51 Conduit 69,700,000 1,400,000 71,100,000 
1. To be borne by local interests. Also includes local 3. Includes 
interests portion of relocation. funds. 
2. For details see individual report. 4. Includes 
funds. 
$245,000 Public Works Administration 
$835,000 Public Works Administration 
1-72

NEW ENGLAND DIVISION 
TABLE 1-K HOUSATONIC RIVER BASIN, CONN. 
(See Section 52 of Text) 
DAMS AND RESERVOIRS' 
Miles Estimated Federal Cost 
Above 
Mouth of Reservoir Lands 
Naugatuck Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages2 Total 
Hall Meadow 4 Torrington, Conn. 41.0 73 Rock and 8,620 $1,852,400 $1,290,0003 $ 3,142,400 
earthfill 
East Branchs Torrington, Conn. 43.7 92 Earthfill 4,350 1,509,800 1,290,0003 2,799,800 
Thomaston Torrington, Conn 30.5 142 Rock and 42,000 6,382,000 7,900,000 14,282,000 
earthfill 
Northfield Torrington, Conn. 30.6 118 Earthfill 2,432 1,856,000 975,000 2,831,000 
Black Rock Waterbury, Conn. 29.0 154 Earthfill 8,700 5,223,700 2,958,600 8,182,300 
Hancock Br. Waterbury, Conn. 25.0 57 Earthfill 4,030 1,595,000 2,585,000 4,180,000 
Hop Brook Waterbury, Conn. 15.9 97 Earthfill 6,970 2,558,000 3,450,000 6,008,000 
1. For details of projects, see individual reports. 4. For last full report, see Annual Report for 1970. 
2. Includes highway, railroad, and utility relocations. 5. For last full report, see Annual Report for 1973. 
3. Includes cost of lands borne by local interests. 
LOCAL PROTECTION PROJECT' 
Miles Estimated Costs 
Above 
Mouth of Lands 
Housatonic and 
Location River Type of Structure Construction Damages 2 Total 
Ansonia-Derby, Conn. 13.0 Wall, levee, channel improve- $17,850,000 $1,050,000 $18,900,000 
ment and pumping station 
Danbury, Conn. 56.0 Walls, channel improvement 14,100,000 2,120,000 16,220,000 
and bridge replacement 
Derby, Conn. 12.0 Walls, levees and pumping 7,600,000 590,000 8,190,000 
station 
1. For details of projects, see individual reports. 
2. To be borne by local interests. Includes relocations. 
1-73

TABLE 1-L 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
MERRIMACK RIVER BASIN, N.H., AND MASS. 
(See Section 53 of Text) 
RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of Reservoir Lands 
Merrimack Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages1 Total 
Franklin Falls 2 Franklin, N.H. 118.2 140 Earthfill 154,000 $ 6,190,000 $1,760,000 $ 7,950,000 
Blackwater 2 Concord, N.H. 118.8 75 Earthfill 46,000 837,000 553,000 1,390,000 
Hopkinton- 
Everett2, 4 Concord, N.H. 87.3 115 Earthfill 157,300 12,971,000 8,737,000 21,708,000 
Edward 
MacDowell2 Keene, N.H. 161.3 67 Earthfill 12,800 1,708,300 306,000 2,014,300 
Mountain 
Brook 3 Keene, N.H. 167.8 50 Earthfill 5,300 695,000 79,000 774,000 
Monoosnoc 6 Leominster, Mass. 100.6 71 Earthfill 2,000 3,430,000 370,000 3,800,000 s 
Phillips Fitchburg, Mass. 105.4 48 Earthfill 1,600 3,940,000 360,000 4,300,000 
Nookagee 2 Fitchburg, Mass. 107.9 106 Earthfill 8,100 8,890,000 3,410,000 12,300,000 s 
Whitmanville 2 Fitchburg, Mass. 110.6 76 Earthfill 9,350 6,780,000 3,220,000 10,000,000 s 
1. Includes highway, railroad, and utility relocation, height for Hopkinton Dam are 118 miles and 76 feet, 
2. For details, see individual report. respectively. 
3. A dam has been constructed at site by private in- 5. Includes Non-Federal reimbursement. 
terests. Cost has not been revised on current price basis. 6. Project deferred, cost has not been revised on cur- 
4. Substituted for Bennington and Beards Brook. Dis- rent price basis. 
tance and height are for Everett Dam. Distance and 
LOCAL PROTECTION PROJECTS 
Miles Estimated Federal Costs 
Above 
Mouth of Lands 
Merrimack and 
Location River Type of Structure Construction Damages' Total 
Nashua, N.H. 55.0 Wall and levee $ 270,000 $ 3,000 $ 273,000 
North Andover and Lawrence, 
Mass.2 27.3 Wall and levee 1,680,000 43,000 1,723,000 
Lowell, Mass. 39.0 Wall and levee 490,600 90,000 580,600 
Baker Brook, Mass.2 101.2 Channel improvement 2,110,000 280,000 2,390,000 
Monoosnoc Brook, Mass.3 98.4 Channel improvement 310,000 90,000 400,000 
North Nashua River, Mass. 100.5 Channel improvement 1,7 30,000 - 1,7 30,000 
Saxonville, Mass. 4 69.0 Wall, levee, channel 3,770,000 480,000 4,250,000 
1. To be borne by local interests. 
2. Project inactive. Cost has not been revised on current 
price basis. 
3. Project deferred. Cost has not been revised on current 
price basis. 
4. For details, see individual report. 
1-74

NEW ENGLAND DIVISION 
TABLE 1-M THAMES RIVER BASIN, CONN., R.I. AND MASS. 
(See Section 59 of Text) 
RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of Reservoir Lands 
Thames Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
Hodges Village 2 Webster, Mass. 74.5 55 Earthfill 13,000 $2,171,000 $3,144,000 $ 5,315,000 
Buffumville2 Webster, Mass. 74.4 66 Earthfill 12,700 2,414,000 841,000 3,255,000 
East Brimfield2 Southbridge, Mass. 82.8 55 Earthfill 30,000 1,338,000 5,720,000 7,058,000 
Westville 2 Southbridge, Mass. 75.2 80 Earthfill 11,000 2,285,000 3,400,000 5,685,000 
West Thompson 2 Putnam, Conn. 59.3 70 Earthfill 25,600 4,888,000 1,965,000 6,853,000 
South Coventry 3 Willimantic, Conn. 41.6 94 Earthfill 36,900 4,434,000 5,666,000 10,100,000 
Mansfield Hollow2 Willimantic, Conn. 40.0 70 Earthfill 52,000 4,108,000 2,340,000 6,448,000 
Andover 3 Manchester, Conn. 47.0 80 Earthfill 16,800 3,777,000 1,123,000 4,900,000 
1. Includes highway, railroad and utility relocations. 
2. For details, see individual report. 
3. Inactive; cost last revised 1954. 
LOCAL PROTECTION PROJECTS 
Miles Estimated Federal Cost 
Above 
Mouth of Lands 
Thames and 
Location River Type of Structure Construction Damages 1 Total 
Norwich, Conn. 15.0 Channel improvement $1,209,000 $72,000 $1,281,000 
1. Borne by local interests. 
1-75

TABLE 1-N 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Project Full Report 
See Annual Contributed 
Report For Construction Funds 
Andover Lake, Conn.' 
Baker Brook, Mass. 1 
Beards Brook Reservoir, N.H.'1 ,2 
Beaver Brook Lake, N.H.' 
Bennington Reservoir, N.H. 1 ',2 
Brockway Lake, Vt.' 
Cambridgeport Lake, Vt.' 
Canton, Mass.3 ',4 
Cherryfield, Me. 3 ,4 
Chicopee, Mass. 6 
Cocheco River, N.H.3 '4 
East Branch Dam, Conn.3 
East Hartford, Conn.3 
Gardner, Mass. 3 ',4 
Gaysville Lake, Vt.' 
Hall Meadow Brook Dam, Conn.3 
Hartford, Conn.3 
Hartford, Vt.3 ',4 
Holyoke, Mass. 3 
Honey Hill Lake, N.H.' 
Huntington, Mass. 3 ',4," 
Keene, N.H.3 ,4 
Lowell, Mass.3 
Lower Woonsocket, R.I.3 
Ludlow Lake, Vt.' 
Mad River Lake, Conn.3 
Monoosnoc Brook, Mass.' 3 
Monoosnoc Lake, Mass. 1 
Mountain Brook Dam, N.H.' "'1 
Nashua, N.H.3 
North Andover and Lawrence, Mass. 1 
North Nashua River, Mass. 
Northampton, Mass.3 
Norwalk, Conn. 3 ' 4 
Norwalk-Wilton, Conn.' 
Norwich, Conn.3 
Pawcatuck, Conn.3 
Pawtucket, R.I.1 
Phillips Dam, Mass. 
Point Judith, R.I. 1 
Riverdale, Mass.3 
South Coventry Lake, Conn.' 
South Tunbridge Lake, Vt.' 
Springdale, Mass.3 
Springfield, Mass.3 
Stratford, Conn. 
The Island Lake, Vt.' 
Three Rivers, Mass.3 
Torrington, East Branch, Conn. 3 '4 
Torrington, West Branch, Conn. 3 ,4 
Trumbull Lake, Conn.' 
Victory Lake, Vt. 14 
Wareham-Marion, Mass.' 
Ware, Mass. 3,4 
Waterbury-Watertown, Conn.3 '4 
West Canaan Lake, N.H.' 
Westerly, R.I. 
1972 
1949 
1973 
1949 
1946 
1964 
1963 
1954 
1963 
1973 
1951 
1970 
1970 
1970 
1960 
1973 
1953 
1949 
1960 
1955 
1945 
1974 
1973 
1967 
1967 
1949 
1950 
1949 
1967 
1950 
1952 
1973 
1960 
1966 
1949 
1967 
1968 
1952 
1951 
1952 
1950 
1973 
1970 
1963 
1963 
1973 
1967 
1965 
1963 
1963 
1948 
1966 
$ - 
94,000 
78,000 
378,300 
205,000 
180,670 s 
203,000 
1,433,6007 
183,100 
1,959,836 
2,135,000 
493,927 
206,600 
2,572,357 
6,094,1009 
332,236 
3,418,000 
92,000 
3,900 
44,100 
490,600 
6,547,137 
4,773,020 
57,000 
270,000'19 
20,000 
680,0001 7 
52,150 
1,209,000 
644,311 
198,447 
1,138,000 
96,000 
700,000 
577,0001 
934,500 
1,577,18912 
389,200 
228,300 
1,457,845 
168,400 
81,715 
400,000 
263,300 
92,000 
1-76 
$ - 
-
-
- 
92,891 
385 
7,637 
15,000 
2,781,100 
24,447 
1,254,1358 
327 
2,800 
214,106 
25,000 
5,350

NEW ENGLAND DIVISION 
TABLE 1-N OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Project Full Report 
See Annual Contributed 
Report For Construction Funds 
Weston, Vt.3 '4 1957 $ 13,000 $ 1,800 
West Springfield, Mass.3 1954 1,334,00016 
West Warren, Mass. 3 '4 1964 389,200 41,000 
Whitmanville Lake, Mass. 1974 574,481 - 
Williamsville Reservoir, Vt.1 ,1 s 1949 146,500 - 
Winsted, Conn.3 1954 245,500 - 
Woonsocket, R.I. 3 1962 4,040,000 224,500 
1. Inactive. 12. Excludes $565,168 Contributed Funds, Other. 
2. Hopkinton-Everett substituted for Beards Brook 13. To be restudied. 
and Bennington. 14. Deferred. 
3. Completed. 15. The Island, Townshend, and Ball Mountain Lakes 
4. Authorized by Chief of Engineers. were substituted. 
5. Reflects FY 1967 settlement of outstanding claim. 16. Excludes $245,000 Public Works Administration 
6. Completed except for inactive portion. funds. 
7. Includes $295,000 Public Works Administration 17. Excludes $280,000 Public Works Administration 
funds. funds. 
8. Excludes $487,925 Contributed Funds, Other. 18. Excludes $355,000 Public Works Administration 
9. Excludes $835,000 Public Works Administration funds. 
funds. 19. Excludes $17,457 flood control and coastal 
10. Emergency Bank Protection. emergency funds expended in FY 1975. 
11. A dam was constructed at site by private interests. 
TABLE 1-0 FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858 (PREAUTHORIZATION) 
(See Section 64 of Text) 
Study Identification Fiscal Year 
Cost 
Ammonoosuc River, Lisbon, N.H. $ 4,020 
Brockton, Mass. 14,040 
Folly Brook, Wethersfield, Conn. 5,626 
Housatonic River, Shelton, Conn. 4,942 
Israel River, Lancaster, N.H. 7,561 
Ogden Brook, Vernon, Conn. 1,190 
Penobscot River, Old Town, Me. 6,358 
Squamscott River, Exeter, N.H. 1,386 
1-77

TABLE 1-P 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED MULTIPLE-PURPOSE 
PROJECTS INCLUDING POWER 
For Last Cost to June 30, 1975 
Project Full Report 
See Annual Contributed 
Report For Construction Funds 
Dickey-Lincoln School Lakes, Me. 1968 $2,688,4991 
(See Section 56A of Text) 
Passamaquoddy Tidal Power Project, Me.2 1935 6,384,394 
1. Design funds only. 
2. Work discontinued in 1937. Facilities transferred to War Assets Administration. 
TABLE 1-Q FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 66 of Text) 
Location Requesting Date Federal 
Agency Completed Cost 
Contoocook River, Water Resources Board Oct 1974 $30,000 
Henniker and Hillsboro, N.H. State of New Hampshire 
Presumpscot River, Soil & Water Conservation Jan 1975 30,000 
Falmouth to Windham, Me. Commission, State of Maine 
Beaver Brook, Water Resources Commission, Mar 1975 26,000 
Littleton, Mass. Commonwealth of Massachusetts 
TABLE 1-R DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Project Full Report 
See Annual Date Contributed 
Report For Deauthorized Construction Funds 
Claremont Lake, N.H. 1968 Dec 1970 $242,700 - 
Clyde, R.I. 1948 Apr 1951 8,800 - 
Mystic, Conn. 1968 Aug 1972 67,700 - 
Narragansett Pier, R.I. 1966 Nov 1970 115,590 - 
Pontiac Diversion, R.I. 1948 Apr 1951 24,200 - 
Sugar Hill Reservoir, N.H. 1946 Dec 1944 - 
West Brookfield Reservoir, Mass. 1948 Jul 1960 67,000 - 
Westfield, Mass. 1967 Sep 1969 507,200 - 
Westport, Conn. 1965 Feb 1970 29,634 - 
1-78

NEW YORK, N 
This district comprises western Vermont, 
small portions of western Massachusetts, Connecticut, 
and eastern and south-central New 
York, including Long Island, and northeastern 
New Jersey, embraced in the drainage basins 
tributary to Lake Champlain and St. Lawrence 
River system east thereof and to Atlantic Ocean 
from New York-Connecticut State line to but not 
including Manasquan Inlet, N.J. It exercises 
Y., DISTRICT* 
jurisdiction, however, over all matters pertaining 
to improvement of Great Lakes to Hudson 
River waterway. Under the direction of the 
Secretary of the Army, the District Engineer, as 
Supervisor of New York Harbor, also exercises 
jurisdiction under the laws enacted for the 
preservation of the tidal waters of New York 
Harbor, its adjacent or tributary water, and 
waters of Long Island Sound. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control ............... 2-2 
2. Bay Ridge and Red Hook Channels, 
N.Y........................................ 2-2 
3. Browns Creek, N.Y. ............... 2-2 
4. East Chester Creek, N.Y............. 2-3 
5. East River, N.Y ................... 2-3 
6. East Rockaway Inlet, N.Y............ 2-4 
7. Hudson River, N.Y.............. 2-5 
8. Hudson River Channel, N.Y.......... 2-6 
9. Jones Inlet, N.Y. .................. 2-7 
10. Lake Montauk Harbor, N.Y. ........ 2-7 
11. Long Island Intracoastal Waterway, 
N .Y ........... ...................... 2-8 
12. Mattituck Harbor, N.Y............. 2-8 
13. Moriches Inlet, N.Y...............2-9 
14. Narrows of Lake Champlain, N.Y. ... 2-9 
15. Newark Bay, Hackensack and Passaic 
Rivers, N.J ......................... 2-10 
16. New York & New Jersey Channels ... 2-11 
17. New York Harbor-collection and 
removal of drift ..................... 2-12 
18. New York Harbor-entrance 
channels & anchorage areas ......... 2-13 
19. Raritan River, N.J............... 2-14 
20. Shrewsbury River, N.J............. 2-15 
21. Supervision of New York Harbor ..... 2-16 
22. Reconnaissance and condition surveys 2-17 
23. Other authorized navigation projects. 2-17 
24. Navigation work under special 
authorization ...................... 2-17 
Beach Erosion Control 
25. East Rockaway Inlet to Rockaway Inlet 
and Jamaica Bay, N.Y. (Part I)....... 2-17 
Beach Erosion Control (Continued) Page 
26. Fire Island Inlet to Jones Inlet, N.Y... 
27. Other authorized beach erosion 
control projects... ................. 
28. Beach erosion control work under 
special authorization ................ 
2-18 
2-19 
2-19 
Flood Control 
29. East Rockaway Inlet to Rockaway Inlet 
and Jamaica Bay, N.Y. (PartII)...... 2-19 
30. Elizabeth, N.J.................... 2-20 
31. Fire Island Inlet to Montauk Point, N.Y. 2-21 
32. North Ellenville, N.Y. ............. 2-23 
33. Rahway, South Branch, N.J.......... 2-24 
34. Raritan Bay and Sandy Hook Bay, N.J. 2-25 
35. Rosendale, N.Y. ................. .. 2-25 
36. Sandburg Creek, Spring Glen, N.Y.... 2-26 
37. South Ellenville, N.Y. .............. 2-27 
38. South Orange, N.J. ................ 2-27 
39. Staten Island, N.Y. ................ 2-28 
40. Waterbury Dam, Winoosk, 
River Basin, Vt. .................. 2-29 
41. Yonkers, N.Y...................... 2-29 
42. Inspection of completed flood control 
projects............................. 2-30 
43. Other aithorized flood control 
projects............................. 2-30 
44. Flood control work under 
special authorization .............. 2-30 
General Investigations 
45. Surveys............................. 2-31 
46. Collection and study of basic data .... 2-31 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
2-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary 
streams, connecting channels, and other allied 
waters in New York District. 
Existing project. Provides for control and 
progressive eradication of water-hyacinth, 
alligatorweed, Eurasian water milfoil, and 
other obnoxious aquatic plant growths, from the 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the 
United States, in the combined interest of 
navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health, 
and related purposes, including continued 
research for development of the most effective 
and economic control measures. (See Table 2-B 
for Authorizing Legislation.) 
Local cooperation. Local interests must 
provide 30 percent of the cost of the program except 
as modified by 1962 River and Harbor Act 
and agree to hold the United States free from 
damages. State indicated on March 17, 1970 its 
intention to cooperate. 
Operations and results during fiscal year. 
$28,700 and $37,500 contracts for waterchestnut 
control in Hudson and Mohawk were awarded 
in June 1974, and June 1975 respectively. Work 
was completed on $28,700 contract in September 
1974 with final payment of $28,700. 
Condition at end of fiscal year. Reconnaissance 
report covering the aquatic plant 
problems of the North Atlantic Division area 
was completed in August 1967. Planning for the 
waterchestnut control in the Hudson-Mohawk 
basin was completed by the New York District, 
contracts for $22,136, $17,861, $22,000, $27,652 
and $28,700 were accomplished in FY 1971, FY 
1972, FY 1973, FY 1974 and FY 1975 respectively. 
2. BAY RIDGE AND RED HOOK 
CHANNELS, N.Y. 
Location. These channels lie along east shore 
of Upper Bay, New York Harbor, and with 
Buttermilk Channel, form an easterly channel 
along Brooklyn waterfront from the Narrows to 
East River. (See Coast and Geodetic Survey 
Charts 369 and 541.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938; pages 1768 and 195, 
respectively. 
Existing project. A channel 1,200 feet wide 
and 40 feet deep at mean low water from the 
Narrows to Bay Ridge Avenue, Brooklyn, 
thence 1,750 feet wide to junction of Bay Ridge 
and Red Hook Channels, thence 1,200 feet wide 
through Red Hook Channel to junction with 
Buttermilk Channel and a channel of same 
depth extending into Gowanus Bay from junction 
of Bay Ridge Channel with Red Hook 
Channel, narrowing uniformly in width to 
about 500 feet at 28th Street, Brooklyn. Section 
included in project is 4 miles long. Mean tidal 
range, 4.7 feet; mean range of spring tides, 5.6 
feet; irregular fluctuations due to wind and atmosphere 
pressure vary from 3.9 feet below 
mean low water up to 5.2 feet above mean high 
water. New work for completed project cost 
$4,277,197, exclusive of amounts expended on 
previous projects. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, 
revised 1965, Vol. 2, Part 2, pages 153-170. 
Operations and results during fiscal year. 
Hopper Dredge Essayons and attendant plant 
were employed intermittently from August 25, 
1974 to September 12, 1974, in dredging to 
restore partial project depth of 30 feet in entrance 
to Gowanus Creek channel. Removed 
300,000 cubic yards place measurement of 
material at a cost of $389,400. 
Condition at end of fiscal year. Work under existing 
project was commenced March 1901 and 
completed June 1940. 
3. BROWNS CREEK, N.Y. 
Location. A narrow, crooked tidal stream 
emptying into Great South Bay, near Sayville, 
Long Island, N.Y., about 15 miles by water 
northeast of Fire Island Inlet, and about 65 
miles by water east of New York City. (See Coast 
and Geodetic Survey Chart 578.) 
Existing project. A channel 100 feet wide and 
6 feet deep at mean low water from 6-foot contour 
in Great South Bay for 1,850 feet, and 
thence, with same width, 4 feet deep for 1,350 
feet; also for two stone jetties to protect the entrance, 
east jetty to be 448 feet long and west jetty 
700 feet long. Section included in project is 
about 0.6 mile. Mean tidal range, 0.6 foot; mean 
range of spring tides 0.7 foot; irregular fluctuations 
due to wind and atmospheric pressure 
vary from 1.8 feet below mean low water up to 
3.2 feet above mean high water. Cost of new 
work for completed active portion of project is 
$33,976. Dredging of channel to a depth of 4 feet 
for 3,300 feet northward to upper limit of project 
and extension of jetties; east jetty to 1,400 feet 
long and west jetty 1,600 feet long are considered 
inactive and excluded from foregoing 
2-2

NEW YORK, N. Y., DISTRICT 
description and cost estimate. Cost estimate for 
this portion is $447,000 (1954). (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. Fifteen terminals, including 
two ferries, with a total available 
dockage of 7,980 feet, are scattered along shore 
of creek between its mouth and head of improved 
channel. Three are publicly owned; all 
are open to the public. None has rail connections. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. A 
contract for the removal and satisfactory disposal 
of all material except ledge rock lying 
above the planes of 6 feet and 4 feet below mean 
low water was awarded on May 9, 1975 and completed 
June 12, 1975. Removed 26,773 cubic 
yards, place measurement of material at a cost 
of $95,252 for maintenance, including $11,782 
for engineering and design preliminary to 
dredging for maintenance. Reconnaissance surveys 
cost of $8,860. 
Condition at end of fiscal year. Work under entire 
existing project is about 40 percent complete. 
Work under active portion of existing project 
was commenced August 1891 and completed 
July 1927. East jetty was completed to a length 
of 448 feet in 1893. West jetty was completed to a 
length of 492 feet in 1892 and extended in 1927 to 
a total length of 700 feet. Six-foot channel has 
been completed. Four-foot channel has been 
completed for 1,350 feet. Work remaining to complete 
project consists of extending jetties to project 
length and dredging channel of 4-foot depth 
northward, for about 3,300 feet. 
4. EAST CHESTER CREEK, N.Y. 
Location. This creek, also known as Hutchinson 
River, is a small tidal stream emptying into 
East Chester Bay, and indentation in north 
shore of Long Island Sound immediately north 
of Throgs Neck, 12 miles southwest of Connecticut 
State line and 21 miles by water northeast 
of the Battery, New York City. (See Coast and 
Geodetic Survey Chart 223.) 
Previous projects. For details see Annual 
Reports for 1915, 1929, 1938 and 1949, pages 
1761, 167, 163, and 208, respectively. 
Existing project. A channel 10 feet deep at 
mean low water and generally 150 feet wide 
from Long Island Sound through East Chester 
Bay to a point 700 feet below Boston Post Road 
Bridge, and thence 70 feet wide extending to a 
point where the creek divides into a Y, thence 
approximately 1,000 feet into east branch of the 
Y and approximately 500 feet into west branch 
of the Y; a passing basin south of Boston Post 
Road Bridge; widening channel at Boston Post 
Road Bridge; and construction of a check dam at 
head of navigation. Section included in project 
is 5 miles. Mean tidal range, 7.3 feet in the estuary; 
mean range of spring tides, 8.6 feet; 
irregular fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below 
mean low water up to 8.1 feet above mean high 
water. Estimate of cost for new work is $2,550,- 
000 (October 1975) exclusive of amounts expended 
on previous projects and inclusive of an estimated 
$40,000 non-Federal cost for lowering 
utilities, (See Table 2-B for authorizing legislation.) 
Local cooperation. River and Harbor Act of 
May 17, 1950, provides that local interests furnish 
lands, rights-of-way, and suitable areas for 
disposal of dredged material during construction 
and future maintenance, and hold the 
United States free from damages. City of New 
York has complied with requirements. 
Assurances are yet to be received from other 
local interests concerned with improvement. 
Terminal facilities. See Port Series No. 5, 
revised 1965, Vol. 2, Part 2. 
Operations and results during fiscal year. A' 
contract for the removal and satisfactory disposal 
of all material, except ledge work lying 
above the plane of 8 feet below mean low water, 
was awarded on April 1, 1974 and completed on 
July 5, 1974. Removed balance of 7,211 cubic 
yards, place measurement of material at a cost 
of $28,368 for maintenance in Fiscal Year 1975, 
making the total under this contract of 45,211 
cubic yards removed at a cost of $269,500. 
Reconnaissance surveys cost of $769. 
5. EAST RIVER, N.Y. 
Location. A tidal strait about 16 miles long 
and 600 to 4,000 feet wide, connecting Hudson 
River and Upper Bay at the Battery, New York 
City, with Long Island Sound at Throgs Neck, 
New York City, and separating Long Island 
from Manhattan Island and the mainland. (See 
Coast and Geodetic Survey Charts 223,226 and 
745.) 
Previous projects. For details see page 210 of 
Annual Report for 1932. 
Existing project. Channels of following 
dimensions (depths refer to mean low water): 
From deep water in Upper New York Bay to 
Wallabout Channel, 40 feet deep and 1,000 feet 
wide; from Wallabout Channel to Throgs Neck, 
35 feet deep, with widths varying from about 550 
to 1,000 feet, according to locality; east of F.D. 
2-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Roosevelt Island up to English Place (43d Dr.), 
Long Island City, 30 feet deep and varying in 
width from 500 to 900 feet, with widening in approach 
from main channel; between South 
Brother and Berrian Islands, 20 feet deep and 
300 feet wide, with widening in approach from 
main channel; from East River channel to 
Astoria waterfront, a flared 0.31 mile entrance 
channel 1,600 to 400 feet wide, a 0.64 mile 
channel 400 feet wide, and a turning basin 1,000 
feet wide and 1,600 feet long, all 37 feet deep in 
rock and 35 feet in soft material (South Brother 
Island Channel); removal of Coenties Reef to a 
depth of 40 feet, also removal of following rocks 
and reefs lying outside of limiting lines of main 
channel to give access to wharves: Along 
Brooklyn shore, Brooklyn Bridge to Manhattan 
Bridge (Fulton Ferry Reef), to a depth of 25 feet; 
Jay Street Reef, 25 feet; Corlears Reef, 35 feet; 
Shell Reef, 25 feet; Horns Hook, 40 feet; 
Rhinelander Reef, 26 feet; and reef off Oak 
Point, 30 feet; and construction of a dike in Pot 
Cove in Hell Gate. Section included in improvement 
is about 17.8 miles long. Mean range of tide 
varies according to locality from 4 feet at North 
Third Street, Brooklyn, and 4.4 feet at the 
Battery to 4.9 feet at Hallets Point, 6.3 feet at 
Port Morris, and 7.1 feet at eastern entrance at 
Throgs Neck; mean range of spring tides 4.8, 5.3, 
5.9, 7.6, and 8.5 feet, respectively; irregular fluctuations 
due to wind and atmospheric pressure 
vary according to locality from 3.8 feet below 
mean low water at the Battery, 2.4 feet at North 
Third Street, Brooklyn, and 3.8 feet at Throgs 
Neck up to about 5.2 feet above mean high water 
at the Battery and 8.4 feet above mean high 
water at Throgs Neck; extreme fluctuations do 
not seriously affect navigation. Cost estimate 
for new work is $26,430,000 (October 1975). (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. Resolutions of 1970 require 
local interests to furnish lands, easements and 
rights-of-way for construction and 
maintenance; hold the United States free from 
damages; provide and maintain depths in 
berthing areas and local access channels serving 
the terminals commensurate with project 
depth; provide upon transfer to the United 
States, a depth in the existing South Brother 
Island Channel and turning basin of not less 
than 30 feet; and establish regulations 
prohibiting discharge of untreated sewage, garbage, 
and other pollutants in the waters of the 
harbor, which shall be in accordance with 
regulations of Federal, State and local 
authorities responsible for pollution control. By 
January 18, 1972 letter. N.Y. City indicated 
willingness to give assurances of cooperation 
for dredging, but wouldn't commit itself on fixed 
terminal plan until further study. 
Terminal facilities. See Port Series No. 5, 
revised 1965, Vol. 2, Part 2, pages 92-147. 
Operations and results during fiscal year. A 
continuing contract for dredging to deepen the 
Spur Channel to Astoria Waterfront to 35 feet 
was awarded on July 8, 1974. Removed 859,383 
cubic yards place measurement of material and 
6,757 cubic yards of rock at a cost of $2,466,256 
including $32,645 for engineering and design 
preliminary to dredging for Fiscal Year 1975. 
Reconnaissance Surveys cost $1,487. 
Condition at end of fiscal year. Work under existing 
project was commenced June 1916 and is 
about 89 percent complete. Work remaining consists 
of deepening and widening South Brother 
Island Channel and turning basin. Construction 
of dike at Pot Cove in Hell Gate and a part of 
widening near pierhead line in Jay Street Reef 
are considered unnecessary for the needs of 
current navigation. Preconstruction planning 
was begun for the remaining portion of the project. 
6. EAST ROCKAWAY INLET, N.Y. 
Location. On south shore of Long Island 
between main body of island and western end of 
Long Beach. It is 10 miles east of Rockaway Inlet 
and about 27 miles by water south and east 
from the Battery, New York City. (See Coast and 
Geodetic Survey Charts 579 and 1215.) 
Existing project. A channel 12 feet deep at 
mean low water and 250 feet wide from 12-foot 
contour in Atlantic Ocean for about 0.6 mile to 
12-foot contour in Long Beach Channel 
protected by a jetty. Mean tidal range, 4.3 feet; 
mean range of spring tides, 5.2 feet; irregular 
fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below mean low 
water up to 5.6 feet above mean high water. New 
work for completed active portion of project cost 
$603,969, including $100,000 contributed funds. 
West jetty portion of project is considered inactive 
and excluded from foregoing description of 
existing project and cost estimate. Estimated 
cost (1954) of this portion is $806,000. (See Table 
2-B for Authorizing Legislation.) 
Local cooperation. Complied with, except for 
those items required for constructing west jetty 
which is not considered now. 
Terminal facilities. There are 39 terminals in 
Oceanside, Island Park, Long Beach, and East 
Rockaway. Nine of these are oil terminals, one 
of which has a railroad spur. Other terminals 
are repair and mooring docks with a berthage of 
7,655 feet. Of these, 21 have marine railways 
and 1 has mechanical-handling facilities. There 
are public wharves at East Rockaway and 
2-4

NEW YORK, N. Y., DISTRICT 
Woodmere.Waterfront on north side of Long 
Beach has been bulkheaded. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Hopper Dredge Davison and attendant plant 
was employed from 25 November 1974 to 11 
December 1974, in dredging to remove shoals in 
12 foot channel. Removed 34,400 cubic yards of 
material, for $149,005. Sidecaster Dredge. Fry. 
and attendant plant were employed from 
October 8, 1974 to November 25, 1974 in 
dredging to remove shoals in 12 foot channel. 
Removed 50,000 cubic yards of material, for 
$99,732. The above includes engineering 
preliminary to dredging for maintenance of 
$14,256. 
Condition at end of fiscal year. Work under active 
portion of existing project began February 
1933 and is 100 percent complete. East jetty, 
4,250 feet long, was completed in July 1934. Project 
channel was completed in May 1935. East 
jetty was in good condition except for minor 
repairs. Work remaining under existing project 
consists of building a west jetty, if determined 
necessary, to protect channel. 
7. HUDSON RIVER, N.Y. 
Location. Originates in Adirondack Mountains, 
about 250 miles in a direct line and 315 
miles along its course from the Battery, New 
York City, and flows generally southerly into 
New York Bay. Section under improvement extends 
from New York City about 156 miles to 
Waterford. (See Coast and Geodetic Survey 
Charts 282, 283, 284, 747, and 748.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938, pages 1764 and 226, 
respectively. 
Existing project. A channel 600 feet wide from 
New York City to Kingston and thence 400 feet 
wide to Albany, with widening at bends, a turning 
basin 700 feet wide and 1,200 feet long at 
Albany, and 2 anchorages, 1 near Hudson and 1 
near Stuyvesant, each 400 feet wide and an 
average length of 2,400 feet; all with depths of 32 
feet in soft material and 34 feet in rock to 2,200 
feet south of the Mall Bridge; thence 27 feet deep 
and 400 feet wide to 900 feet south of the Mall 
Bridge; thence 14 feet deep at lower low water 
and generally 400 feet wide to Federal lock at 
Troy; and thence of same depth and 200 feet 
wide to southern limit of State barge canal at 
Waterford; and removal of State dam at Troy 
and construction of a lock and dam about 2.50 
miles below Waterford. Channel is to be formed 
by dredging and rock excavation, and maintained 
by dredging and constructing new, and 
raising and repairing old, longitudinal dikes, 
built partly under previous projects and partly 
by the State of New York. Mean range of pool 
elevation above Federal dam at Troy, in seasons 
of moderage rains, is about 2.2 feet, as determined 
in 1934. Mean tidal range is about 4.8 feet 
between May and October and 5.1 feet between 
July and September at Federal dam at Troy and 
about 4.8 feet between May and October and 5.0 
feet between July and September at Albany, extreme 
range due to freshets is 33.1 and 25.9 feet, 
respectively normal pool level above Federal 
dam from Troy to Waterford is 14.33 feet above 
mean sea level. In tidal section of river below 
dam, assumed lowest low water plane from Troy 
to Albany is 3 feet below mean sea level. (See 
Table 2-C for features of lock and dam included 
in existing project.) New work for completed project 
cost $39,050,019 exclusive of amounts expended 
on previous projects. Widening to form 
harbors at Albany and Troy, N.Y., to 12 feet 
deep at a cost of $552,000 (1954) and completion 
of 27-foot channel at Albany at a cost of $458,000 
(1957) are inactive. Construction of dikes at a 
cost of $642,000 (1957) was placed in deferred for 
restudy category. All three features of work are 
excluded from foregoing description of existing 
project and cost estimate. Construction of mooring 
facilities has been authorized. (See Table 2-B 
for Authorizing Legislation.) 
Local cooperation. Complied with except that 
local interests must furnish suitable spoil disposal 
areas for future maintenance as required. 
Terminal facilities. Piers and other terminal 
or transfer facilities served by the improvement 
are: between Waterford and Federal dam at 
Troy there are 14 wharves aggregating about 
5,000 feet in length. State of New York constructed 
a barge-canal terminal at Cohoes. 
There is a dock 325 feet long on west side of river 
just north of Federal dam. At Troy there are nine 
terminals with available dockage of 2,383 feet, 
including the State barge-canal terminal with 
960 feet. In addition, 1.25 miles of concrete 
bulkhead were constructed along waterfront by 
city of Troy. At Watervliet there is a stone 
bulkhead 755 feet long. Between this point and 
Albany there are five timber wharves 
aggregating 2,300 feet in length. At Albany, and 
Rensselaer on east side of river, there are 25 terminals 
aggregating 15,150 feet of available 
berthage, and the State barge-canal terminal 
with 1,586 feet on west side of the river. These 
terminals are adequately served with railroad 
trackage. There are five transit sheds, one 
warehouse, a 13,500,000 bushel grain elevator, 
and a molasses-storage plant, all provided by 
Albany Port District Commission. Between 
Albany and Hudson there are about 100 timber 
wharves aggregating 36,700 feet in length; at 
Hudson there are 12 timber wharves 
aggregating 5,000 feet in length; at Athens there 
2-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
are nine timber wharves aggregating 4,000 feet 
in length. Between Hudson and upper limits of 
New York City entire waterfronts of Poughkeepsie, 
Newburgh, and Yonkers are equipped with 
transfer facilities. At Poughkeepsie there are six 
terminals with available dockage 2,580 feet. At 
Newburgh and New Windsor there are 17 terminals 
with a total dockage fo 8,431 feet, of 
which one with 90 feet of dockage is open to the 
public. At Yonkers there are 20 terminals with 
dockage of 5,764 feet, of which 531 feet are for 
public use. Existing wharves are ample for Hudson 
River traffic. 
Operations and results during fiscal year. By 
use of Government plant and hired labor, 
stumps and snags which formed a potential 
menace to navigation, and other obstructions, 
were removed from the shores and channel of 
the river at a cost of $94,611 for maintenance. 
Government plant and hired labor were 
employed intermittently through the fiscal year 
in performing surveys to restore horizontal and 
vertical controls, at a cost of $58,188 for 
maintenance. 
Government plant and hired labor were 
employed intermittently through the fiscal year 
on repairs to Bath Dike at a cost of $96,721. 
The lock and dam in Hudson River at Troy, 
N.Y. were operated and maintained. Operation 
of lock for 1975 navigation season was suspended 
December 14, 1974 and resumed April 14, 
1975. Cost incurred was $350,842 for 
maintenance. 
A contract for Aerial Photography of the Hudson 
River was awarded on June 28, 1974 and 
completed 5 December 1974. Cost incurred was 
$64,760. 
Engineering and Design for recreational 
facilities was accomplished. Costs incurred during 
fiscal year 1975 were $5,392. 
Under a contract for fabrication and installation 
of 4 gate valves in lock chamber at Troy 
Lock, work began June 21, 1971 and was completed 
on April 13, 1973. Work is 100 percent 
complete. No costs were incurred during Fiscal 
Year 1975. Contractor submitted new claim. 
A contract for repairs to Turning Basin, Port 
of Albany, was awarded on 24 June 1975 and 
continuing. $13,899 was expended for engineering 
and design preliminary to repairs for 
maintenance in Fiscal Year 1975. 
Reconnaissance survey costs $50,413 for 
maintenance . 
Condition at end of fiscal year. Work under existing 
project began in July 1910 and was substantially 
completed in November 1965. New 
lock and dam at Troy, removal of dam at Troy 
and construction of 15,545 linear feet of dikes 
also are complete. In reconstruction of old dikes 
39,676 linear feet were raised to adopted crest 
height. Channel from New York City to Albany 
is complete to a depth of 32 feet except for the 
1,500 linear-foot section at the northern end of 
the 32-foot project which has never been dredged 
to project depth. Additionally, the 1,300 linear 
feet of the 27-foot project remains undredged. 
Channel from Albany to Waterford is complete 
to a depth of 14 feet except for a small part of the 
widening to form a harbor at Troy. Work 
remaining under the project consists of completion 
of the 12-foot harbor at Troy and dredging 
the 27-foot and the remainder of th 32-foot 
channels at Albany which are not deemed 
necessary at this time; and reconstruction of 
dikes. Started coordination with State regarding 
mooring facilities. (See Table 2-D for total 
costs of existing project to June 30, 1975.) 
8. HUDSON RIVER CHANNEL, N.Y. 
Location. Hudson River empties into Upper 
Bay of New York Harbor at the Battery, New 
York City. Section included under this title extends 
from deep water in Upper New York Bay 
about 14.5 miles to just north of Harlem River 
(Spuyten Duyvil Creek). (See Coast and 
Geodetic Survey Charts 745, 746, and 747.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938, pages 1765, and 213 
respectively. 
Existing project. A channel 48 feet deep and 
2,000 feet wide, suitably widened at bends from 
West 59th Street, Manhattan, to West 40th 
Street, thence 45 feet deep of same width to deep 
water in Upper Bay; a channel 40 feet deep for 
full width of river extending from northline of 
59th Street to south side of Little Basin, and 
thence a channel of same depth to deep water in 
Upper New York Bay off Ellis Island, substantially 
as shown on maps in H. Doc. 309, 72d 
Cong., 1st sess., subject to provision that no 
dredging be done under project within 50 feet of 
pierhead lines; a channel 750 feet wide and 30 
feet deep along Weehawken-Edgewater waterfront; 
removal of a shoal on New York side 
between West 59th and West 61st Streets to a 
depth of 40 feet; and removal of an obstruction 
north of mouth of Spuyten Duyvil Creek to 
depth of surrounding river bottom. Channel included 
in project is about 11 miles long. Plane of 
reference is mean low water. Mean tidal range at 
the Battery, 4.4 feet, and at West 129th Street, 
4.1 feet; mean range of spring tides, 5.3 and 4.9 
feet, respectively; irregular fluctuations due to 
wind and atmospheric pressure vary from 3.8 
feet below mean low water at the Battery up to 
2-6

NEW YORK, N. Y., DISTRICT 
6.2 feet above mean high water and at West 
129th Street from 3.6 feet below mean low water 
up to 5.3 feet above mean high water. (See Table 
2-B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, 
revised 1965, Vol. 2 Part 2, pages 1-29 and 41-91. 
Operations and results during fiscal year. 
Hopper Dredge Essayons and attendant plant 
were employed from July 1, 1974 to July 22, 1974 
and March 17,1975 to April 7,1975, in dredging to 
restore channel along Weehawken-Edgewaer 
waterfront to 30-foot depth. Removed 557,904 
cubic yards, place measurement, of material at a 
cost of $892,500 including $33,826 for engineering 
preliminary to dredging for maintenance. 
Condition at end of fiscal year. Work under existing 
project was commenced April 1913 and 
completed September 1952. Widening and 
deepening Weehawken-Edgewater Channel to 
project dimensions was completed in August 
1937. Widening 40-foot channel for full width of 
river from Ellis Island to West 59th Street, 
Manhattan, was completed in March 1939. 
Widening 48-foot project to full project width of 
2,000 feet from West 40th Street to West 59th 
Street was completed in November 1950. 
Deepening 45-foot channel for a width of 2,000 
feet from Upper Bay to West 40th Street was 
completed to project dimensions in September 
1952. 
9. JONES INLET, N.Y. 
Location. A small inlet on south shore of Long 
Island connecting Hempstead Bay with Atlantic 
Ocean, 37 miles by water southeast of the 
Battery, New York City. (See Coast and 
Geodetic Survey Chart 579.) 
Existing project. An entrance jetty and a 
channel 12 feet deep and 250 feet wide, from that 
depth in the ocean through the inlet to Loop 
Causeway Bridge over Long Creek. Section included 
in project is about 2.1 miles long. Mean 
tidal range varies from 4.2 feet at ocean entrance 
to 3.1 feet at Loop Causeway Bridge; 
mean range of spring tides varies from 5 to 3.7 
feet, respectively; irregular fluctuations due to 
wind and atmospheric pressure vary from 3.9 
feet below mean low water up to 8.5 feet above 
mean high water. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Complied with except that 
local interests must furnish suitable spoildisposal 
areas for future maintenance as required, 
and must maintain a channel 12 feet 
deep and generally 200 feet wide from Loop 
Causeway Bridge over Long Creek to head of 
navigation in Freeport Creek at Mill Road. 
Terminal facilities. Within area tributary to 
Jones Inlet there are a number of privately owned 
small wharves and 40 boat repair and storage 
yards. The latter are equipped for repair of 
pleasure craft and fishing vessels. In addition, 
there are nine public wharves open to the public 
free of charge, with a total dockage of 2,180 feet. 
Additional terminals would have to be constructed 
for receipt of commercial freight in any 
sizable quantity. 
Operations and results during fiscal year. 
Hopper Dredge Davison and Attendant plant 
were employed from October 16, 1974 to 
November 25, 1974 in dredging to restore project 
depth of 12 feet in entrance channel (outside 
reach). Removed 80,700 cubic yards, place 
measurement, of material at a cost of $288,657 
including $11,624 for engineering and design 
preliminary to dredging for maintenance. 
Sidecaster Dredge Fry. and attendant plant 
were employed from September 5, 1974 to 
October 7, 1974 and November 25, 1974 to 
December 12, 1974 in dredging to restore project 
depth of 12 feet in entrance channel (outside 
channel). Removed 50,000 cubic yards, place 
measurement, of material at a cost of $111,443 
including $4,437 for engineering preliminary to 
dredging for maintenance. 
Reconnaissance survey costs $358. 
Condition at end of fiscal year. Work under existing 
project was commenced August 1953 and 
completed June 1959. 
10. LAKE MONTAUK HARBOR, N.Y. 
Location. On east end of Long Island, about 3 
miles by land west of Montauk Point and 125 
miles by water east of New York City. It is 
landlocked on the east, south and west sides and 
is connected on the north with Block Island 
Sound by an artificial inlet. (See Coast and 
Geodetic Survey Chart 362.) 
Existing project. A channel 12 feet deep and 
150 feet wide extending from 12-foot contour in 
Block Island Sound to same depth in existing 
yacht basin east of Star Island; a boat basin 10 
feet deep, 400 feet wide, and 900 feet long, 
northwest of Star Island; repair and extension 
shoreward of the east and west jetties; and addition 
of sport fishing facilities on top of both jetties. 
Section included in the project is 0.7 miles 
long. Mean tidal range, 1.9 feet; mean range of 
spring tides, 2.2 feet; irregular fluctuations due 
to wind and atmospheric pressure vary from 2 
feet below mean low water up to 7 feet above 
mean high water. For latest published map see 
project document. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. 
2-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Terminal facilities. There are fourteen 
marinas and mooring facilities for recreational 
boats. In addition, two terminals are used for 
commercial fishing vessels. None of the terminals 
have rail connections or are equipped 
with freight handling devices. Terminals are 
considered adequate for existing commerce. 
Operations and results during fiscal year. A 
contract for the removal and satisfactory disposal 
of all material except ledge rock lying 
above the plane of 12 feet below mean low water 
was awarded on June 27, 1975 and continuing. 
$7,000 was expended for engineering and design 
preliminary to dredging for maintenance. 
Condition at end of fiscal year. Work under existing 
project was commenced August 1942 and 
was completed November 1968. Dredging entrance 
channel and shoreward extension of west 
jetty were performed from August 1942 to 
January 1943, at the request of the Navy Department 
with Navy funds. Extension of east jetty 
and repair of both jetties, provision of sport 
fishing facilities on both jetties and dredging 
the boat basin was completed November 1968. 
11. LONG ISLAND INTRACOASTAL 
WATERWAY, N.Y. 
Location. Extends from East Rockaway Inlet, 
on the south side of Long Island, to Great 
Peconic Bay at eastern end of Long Island. Section 
included under this project extends from 
Great South Bay opposite Patchogue to the 
south end of Shinnecock Canal. (See Coast and 
Geodetic Survey Chart 578.) 
Existing project. A channel 100 feet wide and 
6 feet deep at mean low water from the federally 
improved channel in Great South Bay, opposite 
Patchogue to south end of Shinnecock Canal. 
Section included in project is 34 miles long. 
Mean tidal range varies from 1 foot in 
Shinnecock Bay to 0.7 foot in Patchogue Bay; 
mean range of spring tides varies from 1.2 feet to 
0.8 foot; irregular fluctuations due to wind and 
atmospheric pressure vary from 1.8 feet below 
mean low water to 12 feet above mean high 
water. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with except local 
interests must furnish suitable spoil-disposal 
areas for future maintenance as required. 
Terminal facilities. There are 17 boat repair 
and storage yards within the area immediately 
adjacent to the Federal improvement. There is 
ample room for expansion and development of 
terminals when future commerce warrants. 
Operations and results during fiscal year. Under 
a contract for dredging to restore project 
depth of 6 foot in Bellport, Moriches, Narrows 
and Shinnecock Bays. Contract was awarded 
May 3, 1974 and was completed on 7 August 
1974. Removed balance of 32,711 cubic yards 
place measurement of material at a cost of 
$177,150 for maintenance in Fiscal Year 1975, 
making the total under the contract of 137,745 
cubic yards removed at a cost of $567,900. 
Reconnaissance surveys cost of $2,543. 
Condition at end of fiscal year. Work under existing 
project was commenced October 1939 and 
completed September 1940. 
12. MATTITUCK HARBOR, N.Y. 
Location. A tidal inlet on North shore of Long 
Island, 85 miles east of the Battery, New York 
City, and 24 miles southeast of New Haven Harbor, 
Conn., extending southward about 21/4 mile 
to village of Mattituck. (See Coast and Geodetic 
Survey Chart 363.) 
Existing project. A channel 7 feet deep at 
mean low water from Long Island Sound to a 
460- by 570-foot anchorage area at village of 
Mattituck, protected at the entrance by two 
parallel jetties 400 feet apart, channel widths 
are 100 feet at entrance 80 feet elsewhere. Total 
length is about 2.2 miles. Mean tidal range at 
entrance, 4.9 feet; at Old Mill Bridge, Waterville, 
5.1 feet; mean range of spring tides at entrance, 
5.8 feet; at Old Mill Bridge, 6 feet; irregular fluctuations 
due to wind and atmospheric pressure 
vary from 2.2 feet below mean low water up to 
6.6 feet above mean high water. 
Local cooperation. Complied with except local 
interests must furnish spoil-disposal areas for 
maintenance. 
Terminal facilities. Lower portion of harbor 
contains four commercial and two recreational 
boating terminals. Commercial terminals are 
used for handling petroleum products, sand, 
gravel, building materials, fish and shellfish. 
Recreational terminals have mooring accommodations 
available for 20 boats and facilities 
for the sale of gasoline, oil, bait, miscellaneous 
supplies and for repair services. Upper portion 
of harbor contains facilities for recreational 
craft and are open to the general public. 
Operations and results during fiscal year. A 
contract to repair East Jetty was awarded on 
February 18, 1975 and ensuing work consisted 
of 10,620 tons of stone placed, 1,600 cubic yards 
of earth excavation, installation of weighing 
facilities at a cost of $367,703, including $17,223 
for engineering preliminary to repairs for 
maintenance. 
Reconnaissance survey costs of $1,262. 
Condition at end of fiscal year. Project is complete. 
Original dredging was completed in 1914. 
2-8

NEW YORK, N.Y., DISTRICT 
East jetty was completed in 1906 for a 775-foot 
length. West jetty was completed in 1938. Controlling 
depth (July 1964-Sept. 1965) at mean 
low water was 7 and 100 feet wide from Long 
Island Sound to 650 feet upstream from south 
end of west jetty, thence 7 feet deep for a width 
varying from 80 to 50 feet to upstream limit of 
anchorage at village of Mattituck. Anchorage 
has a controlling depth of 7 feet. 
13. MORICHES INLET, N.Y. 
Location. On the south shore of Long Island, 
about 80 miles by water east of the Battery, New 
York City. It is an opening through the narrow, 
sandy barrier beach on the south shore of Long 
Island which separates the Atlantic Ocean from 
a series of interconnected bays. (See Coast and 
Geodetic Survey Chart 12352.) 
Existing project. Provides for a channel, 10 
feet deep at mean low water and 200 feet wide 
extending from that depth in the Atlantic Ocean 
to Moriches Bay, a distance of 0.8 mile; thence a 
channel 6 feet deep and 100 feet wide to the Long 
Island Intracoastal Waterway, a distance of 1.1 
miles; rehabilitation of the existing jetties and 
revetments; seaward extension of the east jetty 
to the 12-foot contour and seaward extension of 
the west jetty a distance of 400 feet; construction 
of a fixed by-passing facility to transfer sand 
from the east side of the inlet to the west side. 
Mean tidal range in the ocean at the inlet is 3.3 
feet and in the bay at Westhampton Beach is 0.6 
foot. Irregular fluctuations due to wind and 
atmospheric pressure vary from 1.7 feet below 
mean low water up to 15.7 feet above mean low 
water at the bay. 
Estimate of cost for new work is $15,180,000 
(October 1975); including $30,000 from Coast 
Guard and $3,530,000 to be contributed by local 
interests. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. The River and Harbor Act 
of July 14, 1960 provides that local interests 
shall, prior to construction agree to contribute in 
cash 45 percent of the cost of construction by the 
Corps of Engineers and agree to contribute in 
cash 50 percent of the maintenance, operation, 
and replacement, or perform work of equal value 
when and as acceptable to the Chief Engineers; 
and provided further that in connection with the 
improvement of the inlet, local interests, prior to 
construction, agree to (a) make the cash contribution 
either a lump sum prior to commencement 
of the work, or in installments prior to commencement 
of pertinent work items, in 
accordance with work schedules as required by 
the Chief of Engineers, the final apportionment 
of cost to be made after actual costs have been 
determined; (b) furnish, free of cost to the United 
States, all lands, easements, rights-of-way, and 
suitable spoil-disposal areas for the initial work 
and for subsequent maintenance when and as 
required; and (c) hold and save the United States 
free from damages due to the construction and 
maintenance of the project; (d) provide and 
maintain suitable terminal facilities when and 
as required for the accommodation of vessels 
that would navigate the inlets and adjacent 
bays, open to all on equal terms; and (e) maintain 
for the duration of the economic life of the 
project, continued public ownership of the 
publicly owned shores and their administration 
for public use, and continued availability for 
public use of the privately owned shores upon 
which a portion of the Federal share of the cost 
is based. Based on General Design memorandum 
submitted June 1971 the revised percentages 
of first cost are 76.2 percent Federal and 
23.8 percent non-Federal. 
Terminal facilities. No terminals are within 
the area immediately adjacent to the Federal improvement. 
However, numerous public and 
private terminal facilities are available in 
Moriches Bay and in the connecting canals. 
Three yacht clubs, six boatyards, 12 public 
wharves and landings, and numerous private 
landings are located in Moriches Bay. The yacht 
clubs and boatyards have equipment for servicing 
boats. There are four public boat basins 
open to the public. The facilities existing in the 
bay are considered adequate for present and 
probable future needs. There is room for expansion 
should future commerce warrant. 
Operations and results during fiscal year. 
Continued coordination engineering concepts 
and environmental study was initiated. $10,- 
485.11 was expended in FY 1975 for preconstruction 
planning. 
Condition at end of fiscal year. Construction 
has not been initiated. Preconstruction planning 
(advance engineering and design) underway. 
14. NARROWS OF LAKE CHAMPLAIN, 
N.Y. AND VT. 
Location. This waterway, 37 miles long, comprises 
southern end of Lake Champlain and extends 
from Whitehall to Crown Point, N.Y. Project 
extends 13.5 miles from Whitehall, N.Y., at 
southern extremity of lake, northerly to Benson 
Landing, Vt. (See Lake Survey Chart 174.) 
Previous projects. For details, see Annual 
Reports for 1932, and 1963, pages 256 and 177, 
respectively. 
Existing project. A channel extending from 
Whitehall, N.Y., at head of Lake Champlain, to 
Benson Landing, 12 feet deep at low lake level 
and generally 150 feet wide, and installation of 
2-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
fender booms at Putts Rock, Putts Leap, 
Narrows near Dresden, Pulpit Point, and Cedar 
Mountain. Reference plane of low lake level is 93 
feet above mean sea level. Section included in 
project is about 13.5 miles. Usual annual variation 
of lake level is 5.8 feet, and extreme variation 
varies from 0.6 foot below up to 8.8 feet 
above low lake level. 
Widening channel throughout its entire 
length to project width of 200 feet is inactive and 
excluded from foregoing description of existing 
project and cost estimate. Estimated cost of this 
portion, revised in (1954), was $1,573,000. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. In Whitehall Harbor consisting 
of three timber wharves, aggregating 
4,200 feet in length. State of New York constructed 
a barge canal terminal at Whitehall, 
just, south of terminus of canal, which has 
been equipped with a 5-ton hand-operated 
derrick and a storehouse. Facilities are considered 
adequate for present commerce. 
Operations and results during fiscal year. 
Government plant and hired labor were 
employed intermittently during the fiscal year 
in removal of stumps and snags, at a total cost of 
$4,000 for maintenance. 
Government plant and hired labor were 
employed in replacing deteriorated fender 
booms at a total cost of $4,000 for maintenance. 
Reconnaissance surveys cost $7,549. 
Condition at end of fiscal year. Work under 
the existing project was commenced June 1919 
and is about 47 percent complete. A channel 12 
feet deep at low lake level and least width of 150 
feet has been excavated throughout the length 
of the improvement, except at the Elbow (Putts 
Leap and Putts Rock). (Fender booms opposite 
the Delaware and Hudson Railroad trestle have 
been removed as they no longer are considered 
necessary for navigation). The work remaining 
to complete the project consists of widening the 
channel throughout its entire length to the project 
width of 200 feet. 
15. NEWARK BAY, HACKENSACK AND 
PASSAIC RIVERS, N.J. 
Location. Newark Bay is an estuary about 
1.25 miles wide and 6 miles long extending 
southerly from confluence of Hackensack and 
Passaic Rivers to New York and New Jersey 
Channels. Hackensack River rises near 
Haverstraw. Rockland County, N.Y., and flows 
about 45 miles into Newark Bay. Passaic River 
rises in highlands of northeastern New Jersey 
and flows about 80 miles into Newark Bay. (See 
Coast and Geodetic Survey Charts 285 and 287.) 
Previous projects. For details see 1926 Annual 
Report, pages 265 and 266; and Annual Reports 
for 1929, 1938, and 1954, pages 301, 244, and 134, 
respectively. 
Existing project. * (Depths are 37 feet in rock 
and 35 feet in other material unless noted) 
(a) Newark Bay: A main channel 700 feet 
wide to the branch channel to Port Newark, 
length about 3.1 miles, thence 500 feet wide to 
junction of Hackensack and Passaic River 
channels, total length about 4.7 miles; removal 
of east and west cutoffs at junction with Kill 
Van Kull; additional widening at this junction 
in vicinity of Bergen Point by deepening a 
triangular area at the eastern end of the channel 
south of Shooters Island from 30 to 35 feet, this 
area to be transferred from the New York and 
New Jersey Channels project to the Newark Bay 
project; a maneuvering area south of the Central 
R.R. of N.J. bridge 300 feet wide and 2,200 feet 
long with increased depth of 40 feet (rock) and 38 
feet (other material) in the southern half; a large 
maneuvering and turning area just above the 
Central R.R. of N.J. bridge serving also as a 
south branch channel to Elizabeth Marine Terminal; 
bend widening at branch channel to Port 
Newark, and a combined bend cutoff and 
maneuvering area at the branch channel to 
Elizabeth Marine Terminal; a turning basin 
1300 feet long and 900 feet wide at the junction 
with Hackensack and Passaic Rivers. 
(b) Port Newark: A branch channel 800 feet 
wide leading to an inshore channel 400 feet 
wide, total length about 1.6 miles; a pierhead 
channel 200 feet wide, length about 4100 feet. 
(c) Elizabeth Marine Terminal: A branch 
channel 500 feet wide, length about 1.5 miles; a 
pierhead channel 290 feet wide, length about 1.1 
miles; a south channel along the south bulkhead 
290 feet wide, length about 2500 feet. 
(d) Hackensack River: A channel 34 feet deep 
in rock and 32 feet in other material and 400 feet 
wide from upper end of Newark Bay channel to 
Central Railroad of New Jersey Bridge about 1.1 
miles; thence 32 feet deep and 300 feet wide to a 
point about 2,000 feet north of Erie Lackawanna 
(formerly Delaware, Lackawanna & Western 
RR) Bridge, 2.8 miles; with a turning basin 25 
feet deep at upper end of channel; thence 15 feet 
deep, 200 feet wide, for 10.1 miles to Little Ferry; 
thence 15 feet deep, 150 feet wide to the Court 
Street Bridge. Total length about 16.3 miles. 
(e) Passaic River: A channel 30 feet deep and 
300 feet wide, from Newark Bay to a point 3,000 
feet above Lincoln Highway Bridge, 2.6 miles; 
thence 20 feet deep and 300 feet wide to Jackson 
Street Bridge, 2 miles; thence 16 feet deep and 
300 feet wide to Nairn Linoleum Works, 2.4 
miles; thence 16 feet deep and 200 feet wide to 
2-10

NEW YORK, N.Y., DISTRICT 
Montclair & G:eenwood Lake Railroad Bridge, 
about 1.1 miles; thence 10 feet deep and 150 feet 
wide to Eighth Street Bridge at Passaic, 7.3 
miles, a total distance for Passaic River of 15.4 
miles. All depths refer to plane of mean low 
water. Mean tidal range in Newark Bay is 4.9 
feet; in Hackensack River at Court Street 
Bridge, 5.5 feet; in Passaic River at Pennsylvania 
Railroad Freight Bridge, 5.2 feet; and 
in Passaic River at Gregory Avenue Bridge, 5.5 
feet; mean range of spring tides, 5.9, 6.6, 6.3 and 
6.5 feet, and respectively; irregular fluctuations 
due to wind and atmospheric pressure vary from 
4.3 feet below mean low water up to 6.0 feet 
above mean high water. Estimate of cost for new 
work for active portion of existing project consisting 
of channels described above, is $37,580,- 
000 (October 1975), exclusive of amounts expended 
on previous projects; including 
$6,410,000 to be contributed by local interests. 
Dredging Passaic River to 20 feet deep and 300 
feet wide from Jackson Street Bridge about 2.4 
miles to Nairn Linoleum Works, is inactive and 
excluded from foregoing description and cost estimate. 
Estimated cost (1954) of this portion is 
$1,182,000. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. River and Harbor Act of 
1954 provides local interests furnish lands, 
rights-of-way, and suitable spoil-disposal areas 
for initial construction and future maintenance; 
provide depths commensurate with channel 
depth in approaches and berths at terminals of 
companies which would use improvement; and 
hold the United States free from damages. River 
and Harbor Act of 1962 provides that local interests 
must provide lands, easements and 
rights-of-way for maintenance and construction, 
hold the United States free from damages, 
provide and maintain adequate public terminal 
and transfer facilities, and provide and maintain 
depths in berting areas at terminals, accomplish 
without cost to the United States 
removal' or relocation of pipelines, cables and 
other utilities. Assurances were furnished by 
Port of New York Authority and accepted June 
12, 1964. Local cooperation required by previous 
modifications is fully complied with. 
Terminal facilities. See Port Series No. 5, 
revised 1965, Vol. 2, Part, 2 pages 354-399. 
Operations and results during fiscal year. 
Studies completed for modification of project 
consisting of additional widening at junction 
with Kill Van Kull by deepening to 35 feet a 
triangular area at the eastern end of the 30 foot 
channel south of Shooters Island. 
Condition and end of fiscal year. Work under 
the active portion of project began August 1907 
and is about 60 percent complete. Hackensack 
River is navigable 20.5 miles above mouth to 
New Milford. Passaic River is navigable 16 
miles above mouth to Dundee Rapids. Work 
remaining to complete existing project consists 
of the following: (a) Hackensack River- 
Dredging 32-foot channel and deepening 12-foot 
channel to 15 feet; (b) Passaic River-Dredging 
20-foot channel from Jackson Street to Nairn 
Linoleum Works (inactive). Work in Passaic 
River includes removing a small quantity of 
rock on west side of channel above Center Street 
Bridge. Adjacent property owners are opposed 
to this work; (c) Bergen Point-deepening 
triangular area south of Shooters Island to 35 
feet. 
16. NEW YORK AND NEW JERSEY 
CHANNELS 
Location.Extends from deep water northwest 
of Sandy Hook, through Lower New York Bay 
and Raritan Bay, to Perth Amboy, and thence 
through Arthur Kill, lower Newark Bay, and 
Kill Van Kull to deep water in Upper New York 
Bay. This route is approximately along boundary 
line between States of New York and New 
Jersey. (See Coast and Geodetic Survey Charts 
285, 286, and 369.) 
Previous projects.For details see 1963 Annual 
Report, pages 184 and 185. 
Existing project.A channel through Lower 
New York Bay, Raritan Bay, Arthur Kill, lower 
Newark Bay, and Kill Van Kull to Upper New 
York Bay, depths of 37 feet in rock and 35 feet in 
soft material throughout, 600 feet wide across 
Lower New York Bay and Raritan Bay and in 
Arthur Kill to a point 1,000 feet north of Smith 
Creek, widened to 800 feet in vicinities of 
Seguine Point and Wards Point, respectively; 
thence 500 wide to a point 1,000 feet south of 
Piles Creek; thence 500 to 600 feet wide and passing 
north of Shooters Island and protected by a 
dike on its northern side to junction of channel 
into Newark Bay; thence 800 feet wide through 
Kill Van Kull to Constable Hook; thence 1,000 
feet wide from a point opposite the east end of 
Constable Hook to a point near the intersection 
with the channel along New Jersey pierhead 
line; and thence 1,400 feet wide through Kill Van 
Kull to Upper New York Bay; with an anchorage 
38 feet deep to accommodate five vessels south 
of Perth Amboy, all with suitable easing at 
bends and junctions. Section included in project 
is 30.8 miles long. In addition, construction of a 
dike north of Shooters Island and two secondary 
channels 30 feet deep and 400 feet wide, one 
south of Shooters Island and the other in 
Raritan Bay connecting with Raritan River, 
were completed under previous projects and 
2-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
maintained under existing project. A triangular 
area at the eastern end of the 30 foot channel 
south of Shooters Island is to be deepened to 35 
feet in order to provide additional widening in 
the vicinity of Bergen Point and is included in 
the Newark Bay project. All depths refer to 
plane of mean lower water. Mean range of tides 
varies between 4.7 and 5.1 feet; mean range of 
spring tides, 5.7 to 6.3 feet; irregular fluctuations 
due to wind and atmospheric pressure vary from 
3.9 feet below mean low water up to 6.9 feet 
above mean high water. Anchorage at Sandy 
Hook, and cutoff at junction of Main Ship 
Channel are deferred for restudy and excluded 
from foregoing description and cost estimate. 
Estimated cost of this portion (1957) is $2,150,- 
000. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. See page 170, 1962 Annual 
Report for requirements under acts of May 28 
and August 30, 1935. See page 156, 1965 Annual 
Report for requirements under act of May 17, 
1950. See page 168, 1966 Annual Report for requirements 
under act of October 27, 1965. 
Terminalfacilities.See Port Series No. 5, revised 
1965, Vol. 2, Part 2, pages 282-342. 
Operations and results during fiscal year: 
Contract #1 for removal and satisfactory disposal 
of all material except ledge rock lying 
above the plane of 35 feet below mean low water 
in the Channel North of Shooters Island, New 
York and New Jersey Channels was awarded on 
June 18, 1974 and completed December 31, 1974. 
Removed 248,578 cubic yards, place measurement, 
of material at a cost of $454,138, including 
$270 for engineering and design preliminary to 
dredging for maintenance in Fiscal Year 1975, 
making the total expended under this contract 
$458,655. 
Contract #2 for removal and satisfactory disposal 
of all material except ledge rock lying 
above the plane of 35 feet below low water in the 
Channel North of Shooters Island, New York 
and New Jersey Channels, was awarded on 
June 18, 1974 and completed on November 2, 
1974. Removed 345,605 cubic yards, place 
measurement, of material at a cost of $663,697. 
Hopper Dredge Essayons and attendant plant 
were employed intermittently from May 27, 1975 
to June 30, 1975 in dredging to restore project 
depth of 35 feet in Raritan Bay Channel. 
Removed 500,000 cubic yards, place measurement, 
of material at a cost of $725,827 including 
$54,565 for engineering and design preliminary 
to dredging for maintenance. 
Condition at end of fiscal year. Work under active 
portion of existing project began in October 
1933 and was completed in September 1968. 
Work completed consists of providing authorized 
project depth and widths throughout entire 
channel from Lower New York Bay to Upper 
; w York Bay and providing depths of 37 and 
25 feet in Perth Amboy Anchorage. In addition 
to above mentioned work, construction of a dike 
north of Shooters Island, two secondary 
channels 30 feet deep and 400 feet wide, one 
south of Shooters Island, the other in Raritan 
Bay connecting with Raritan River were completed 
under previous projects. Work remaining 
under existing project consists of dredging 
cutoff at junction of Main Ship Channel to 
dimensions authorized by River and Harbor 
Acts of August 30, 1935, and May 17, 1950, and 
dredging anchorage in vicinity of Sandy Hook. 
(See Table 2-D for total costs for existing project 
to June 30, 1975.) 
17. NEW YORK HARBORCOLLECTION 
AND REMOVAL 
OF DRIFT 
Location. Applies to Lower and Upper Bays, 
New York Harbor: East River, Harlem River, 
Hudson River Channel, N.Y., New York and 
New Jersey Channels, Newark Bay, N.J., and 
their tributaries. 
Existing project. Provides for collection, 
removal and disposal of drift, derelict vessels, 
deteriorated shore structures and debris along 
shores of New York Harbor and tributary 
waters, and for the repair of certain other piers, 
wharves and shore structures. Work authorized 
before Act of 1970 was restricted solely to 
removal of drift from waterways and was funded 
as a maintenance activity. Estimate of first 
cost of improvement under Act of 1974 is $31,- 
600,000 (October 1975) including $15,800,000 
cash contribution from local interests, plus 
$19,200,000 to be contributed for repair and 
disposal of deteriorated shore structures in use. 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local cooperation conditions 
of the plans currently under review by 
the Chief of Engineers provide that local interests 
must furnish all lands, easements and 
rights-of-way required for the improvement; 
hold the United States free from damages; enact 
and enforce local legislation to prevent creation 
of sources of drift, contribute in cash one third of 
the first cost of the Federal work, and make 
necessary repairs to deteriorated structures in 
use so as to eliminate them as a source of drift. 
These conditions are subject to approval by 
Secretary of the Army and the President, as 
stipulated ini Section 113 of the authorizing law, 
Public Law 91-611. 
Operations and results during fiscal year. 
New Work: Initiated coordination and Preconstruction 
Planning for the entire project 
area and detailed studies for Liberty State Park 
2-12

NEW YORK, N.Y., DISTRICT 
Area. Maintenance: U.S. Debris Boats Driftmaster, 
Gorham, and Hayward. Tugs Daly, 
Stanwix, and auxiliary plant were assigned the 
work of removing and disposing of drift when 
not employed on other work. Removed and disposed 
of 460,000 cubic feet (3,594 cords) of 
driftwood, ranging in size from small blocks to 
timbers of large dimensions, including piles and 
pieces of wreckage at a cost of $1,152,087. 
Studies and investigations to improve the operation 
of the incinerator at Caven Point, N.J. are 
continuing. An Engineering & Design Contract 
was awarded on June 28, 1973 and continuing. 
Costs of $161,698 in this regard were incurred 
during Fiscal Year 1975 
A contract for bank protection and bulkhead 
was awarded on April 25, 1975 and continuing. 
Costs incurred were $356,606 in Fiscal Year 1975 
including $50,405 for engineering and design 
preliminary to construction of a steel sheet 
bulkhead and fender pile system and dredging 
for vessel access to the facility. 
Condition at end of Fiscal year. Work 
authorized under River and Harbor Acts of 1915, 
1917 and 1930 is continuous maintenance for 
which no percentage of completion exists. 
Engineering and Design is underway for the 
work authorized by the 1974 Water Resources 
Development Act. 
18. NEW YORK HARBORENTRANCE 
CHANNELS AND 
ANCHORAGE AREAS 
Location. In Upper and Lower bays, New 
York Harbor. Harbor is 330 miles southwest by 
water of Boston Harbor, Mass., and 165 miles 
northeast of entrance to Delaware Bay, N.J., 
and Del Upper bay extends about 5.5 miles 
southerly from junction of Hudson and East 
Rivers opposite the Battery, New York City; to 
the Narrows. Lower bay extends about 9 miles 
from the Narrows to the sea. (See Coast and 
Geodetic Survey Chart 369.). 
Existing project. Ambrose Channel 45 feet 
deep and 2,000 feet wide, extending about 10.2 
miles from the sea to deep water in the Lower 
bay; Anchorage Channel, an extension of Ambrose 
Channel, with same depth and width, in 
the Upper bay, opposite anchorage grounds, 
about 5.7 miles long; a southerly entrance 
channel, Sandy Hook Channel (East Section) 35 
feet deep and generally 800 feet wide extending 
3.4 miles from 35-foot ocean contour to Bayside 
Channel along an alinement generally west of 
South Channel; and elimination from authorized 
project of that portion of Bayside-Gedney 
Channel east of junction with new southerly entrance 
channel; for Bayside Channel 35 feet 
deep and 800 feet wide, extending about 3.7 
miles from junction with new southerly entrance 
channel to junction with Main Ship 
Channel; Main Ship Channel 30 feet deep and 
1,000 feet wide, extending about 5.3 miles from 
Bayside Channel to deep water in Lower bay; a 
channel along New Jersey pierhead line connecting 
Kill Van Kull with deep water in Anchorage 
Channel, south of Liberty Island anchorage, 20 
feet deep for 500 feet wide with widening at 
bends to 800 feet and about 3 miles long; an 
anchorage in vicinity of Liberty (Bedloe) Island 
(about 160 acres in extent) 20 feet deep; and for 
removal of Craven Shoal to 30 feet deep; for a 
channel 16 feet deep, 200 feet wide, and about 2.3 
miles long, extending from bell buoy 23 to Hoffman 
and Swinburne Island; for an anchorage 
area in Red Hook Flats to depths of 45, 40, and 35 
feet over an area of 928 acres and an anchorage 
area in Gravesend Bay to 47 feet deep over area 
of 334 acres. Project depths refer to mean low 
water. Mean tidal range is 4.7 feet at Fort 
Hamilton; mean range of spring tides, 5.7 feet; 
irregular fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below 
mean low water up to 6.2 feet above mean high 
water. Cost estimate for new work is $27,840,000 
(October 1975). (See Table 2-B for Authorizing 
Legislation.) 
New Work. Hopper Dredge ESSA YONS and 
attendant plant were employed intermittently 
from April 7, 1975 to May 26, 1975 to dredge 
South of the Fairway to a depth of 40 feet (Area 
C). Removed 676,700 cubic yards, place 
measurement, of material at a cost of $1,016,545, 
including $68,899 for engineering and design 
preliminary to dredging. 
A continuing contract for dredging to deepen 
Area D-4 (Part II) of Red Hook Flats Anchorage 
to 35 feet was awarded on February 22,1974 and 
completed November 1, 1974. Removed 882,555 
cubic yards, place measurement of material 
(balance of contract) at a cost of $1,083,900, including 
$1,847 for engineering and design 
preliminary to dredging for Fiscal Year 1975, 
making the total under this contract of 1,931,555 
cubic yards at a cost of $2,531,327. 
A continuing contract for dredging to deepen 
Area D-5 of Red Hook Flats Anchorage to 35 feet 
was awarded on February 6, 1975. Removed 
1,281,555 cubic yards, place measurement of 
material at a cost of $1,770,074 including 
$104,954 for engineering and design 
preliminary to dredging, for Fiscal Year 1975. 
Maintenance. Hopper Dredge Essayons and 
attendant plants were employed on July 23, 
1974 and completed work on August 24, 1974 to 
restore project dimensions of 45 feet in Ambrose 
Channel. Removed 321,947 cubic yards, place 
2-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
measurement, of material at cost of $687,676 
including $43,284 for engineering and design 
preliminary to dredging for maintenance. 
A contract for the removal and satisfactory 
disposal of all material except ledge rock lying 
above the plane of 35 feet below mean low water 
in specified sections of Sandy Hook Channel, 
New York Harbor, New York was awarded 
March 24, 1975 and continuing. Removed 15,000 
cubic yards, place measurement of material at a 
cost of $439,156, including $99,424 for 
engineering and design preliminary to dredging 
for maintenance. 
A contract for Feasibility Study of developing 
a Dredge Spoil Disposal Area in vicinity of 
Hoffman-Swinburne Islands was awarded May 
4, 1975 and continuing. Costs of $86,056 were 
incurred in this regard in Fiscal Year 1975. 
Reconnaissance surveys cost of $30,232. 
Local cooperation. Fully complied with. 
Terminal facilities. See Port Series No. 5, 
revised 1965, Vol. 2, Part 2, pages 343-353 and 
400-408. 
Operations and results during fiscal year. See 
above. 
Condition at end of fiscal year. Work under 
existing project began in 1885 and is about 54 
percent complete. Main Ship and Bayside- 
Gedney Channels were completed to 30 feet deep 
in February 1891. Deepening of Bayside-Gedney 
Channel to 35 feet for a width of 800 feet was 
completed in June 1939. Ambrose Channel was 
completed to 40 feet deep for a width of 2,000 feet 
in April 1914, and substantially completed to 45 
feet deep for a width of 2,000 feet in 1951. 
Relocation of Anchorage Channel was completed 
to 40 feet deep in October 1932. Center 800 
feet was dredged to 45 feet in June 1947 and 
westerly 600-foot strip in April 1948. Easterly 
600-foot strip was substantially completed in 
June 1953. Channel between Staten Island and 
Hoffman and Swinburne Islands was completed 
in December 1920 up to within 300 feet of 
southerly limits of project. Dredged channel 
meets all needs of navigation and no further 
work of improvement is contemplated for the 
present. Channel along New Jersey pierhead 
line from Kill Van Kull to Anchorage Channel 
was completed in March 1939. Widening at 
bends near southerly and northerly ends 
authorized in 1948 was completed in November 
1960. Red Hook Flats anchorage was completed 
to 40 and 30 feet and Liberty (Bedloe) Island 
anchorage was completed to 20 feet in October 
1944. Sandy Hook Channel (east section) was 
completed to a depth of 35 feet in June 1963. 
Work remaining under existing project consists 
of continuation of deepening and expanding 
Red Hook Flats anchorage and deepening 
Gravesend Bay anchorage. 
19. RARITAN RIVER, N.J. 
Location. Rises in north-central part of New 
Jersey and flows generally southeasterly into 
Raritan Bay, between Perth Amboy and South 
Amboy, about 24 miles by water south of the 
Battery, New York City. (See Coast and 
Geodetic Survey Chart 375.) 
Previous projects. For details see Annual 
Reports for 1915,1918, and 1938, pages 1777, 359 
and 259, respectively. 
Existing project. A channel 25 feet deep and 
300 feet wide extending 5.8 miles from turn in 
New York and New Jersey Channels near Great 
Beds Light to Government wharf on Main 
Channel, widened to 600 feet for 1,000 feet long 
opposite wharf to form a turning basin of same 
depth; thence a channel 15 feet deep and 200 feet 
wide 3 miles to Washington Canal; thence 10 
feet deep in soft material, 11 feet deep in rock, 
and generally 100 feet wide with widening at 
bends 5 miles to Delaware and Raritan Canal 
entrance at New Brunswick, and a South 
Channel 25 feet deep and 300 feet wide 0.8 mile 
from junction with Main Channel at Keasby to 
upper limit of Titanium Pigment Co. property; 
thence 15 feet deep and 150 feet wide 0.4 mile to 
dock of Middlesex County Sewerage Authority; 
thence 10 feet deep and 150 feet wide 2 miles to a 
point 1,300 feet below upper junction with Main 
Channel at Crab Island. Plane of reference is 
mean low water. Mean range of tides is 5.1 feet 
at mouth of river and 5.6 feet at New Brunswick; 
mean range of spring tides, 6.1 and 6.6 feet, 
respectively. Irregular fluctuations due to winds 
and atmospheric pressure vary from 3.6 feet 
below mean low water up to 6.9 feet above mean 
high water. New work for completed portion of 
project, consisting of channels described above 
cost $1,237,000, exclusive of amounts expended 
on previous projects and including $66,000 
contributed by local interests. Dredging South 
Channel to 10 feet deep and 150 feet wide for 
1,300 feet to upper junction with Main Channel 
at Crab Island is inactive and excluded from 
foregoing description and cost estimate. Cost 
estimate for this portion is $86,000 (1954). (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with except local 
interests must furnish spoil-disposal areas for 
maintenance to 25-foot channel from New York 
& Long Branch Railroad bridge to junction of 
Main and South Channels, and in South 
Channel to Titanium Pigment Co. property. 
River and Harbor Act of 1962, provides local 
interests furnish spoil-disposal areas and 
necessary retaining dikes, bulkheads and em- 
2-14

NEW YORK, N.Y., DISTRICT 
bankments therefor, required for maintenance 
of improvement, and hold the United States free 
from damages. 
Terminal facilities. See Port Series No. 5, 
revised 1965, Vol. 2, Part 2, pages 274-279 and 
281. 
Operations and results during fiscal year. A 
contract for dredging to restore project depth of 
25 feet in South Channel was awarded on May 5, 
1975 and continuing. Due to flood conditions of 
river, no material was removed. $37,449 was 
expended for engineering and design 
preliminary to dredging for maintenance. The 
estimated accrual of $120,000 for contract work 
did not materialize due to flood conditions of the 
river. 
A contract for dredging to restore project 
depth of 20 to 25 feet in Main Channel was 
awarded on June 30, 1975 and continuing. 
$47,408 was expended for engineering and 
design preliminary to dredging for 
maintenance. 
Reconnaissance surveys cost $20,495. 
Condition at end of fiscal year. Entire existing 
project is about 96 percent complete. Work under 
active portion of existing project was commenced 
September 1919 and completed July 1941. A 
shoal along northerly channel line in vicinity of 
Victory Bridge was eliminated by relocation of 
channel in February 1959. Main Channel 
dredged 25 feet deep and 300 feet wide from 
junction with New York and New Jersey 
Channels to and including a turning basin of 
same depth opposite Government wharf, thence 
15 feet deep and 200 feet wide to mouth of 
Washington Canal, thence 10 and 11 feet deep 
and 100 feet wide to Delaware and Raritan 
Canal outlet locks at New Brunswick. South 
Channel dredged 25 feet deep and 300 feet wide 
for 3,200 feet, thence 10 feet deep and 150 feet 
wide for 12,400 feet to within 1,300 feet of 
junction with Main Channel at Crab Island. 
Model study of Raritan River was completed in 
March 1952. Work remaining under existing 
project is dredging South Channel to 10 feet 
deep and 150 feet wide for 1,300 feet to upper 
junction with Main Channel at Crab Island. 
20. SHREWSBURY RIVER, N.J. 
Location. Mainly a large tidal basin in 
eastern part of New Jersey, the outlet being at 
the southeast end of Sandy Hook Bay, about 4 
miles south from the point of Sandy Hook. (See 
Coast and Geodetic Survey Chart 824.) 
Previous Projects. For details see Annual 
Reports of 1915, 1918, and 1938, pages 1778, 373, 
and 267, respectively. 
Existing project. A channel 12 feet deep and 
300 feet wide, following the westerly shore, from 
deep water in Sandy Hook Bay 2.2 miles to a 
point 600 feet south of former location of 
railroad bridge at Highlands; then 9 feet deep 
and generally 150 feet wide, suitably widened at 
bends and turns, in south branch of river 6.8 
miles to Branchport Avenue Bridge in city of 
Long Branch; and a channel in north branch 6 
feet deep and 150 feet wide 6.1 miles from the 
junction to Red Bank. Plane of reference is mean 
low water. River and Harbor Act of 1965 
modified existing project to include an inlet 
channel across base of Sandy Hook Peninsula 
between Spermaceti Cove and Island Beach 
connecting the Atlantic Ocean with 
Shrewsbury River. The ocean channel to be 15 
feet deep, 200 feet wide and 830 feet long 
protected by parallel jetties spaced 500 feet 
apart and through the land cut to be protected 
by bulkheads in extension jetties; thence a bay 
channel 9 feet deep, 200 feet wide, and 2,860 feet 
long extending to existing Shrewsbury River 
channel. Plane of reference is mean low water. 
New inlet is to be spanned by a 6-lane fixed 
highway bridge with a vertical clearance of 35 
feet above mean high water and a total length of 
1,560 feet. Mean range of tide at Highlands, 3.8 
feet; at Seabright, 1.7 feet; at Branchport, 1.7 
feet; and at Red Bank, 3 feet. Mean range of 
spring tides is 4.7, 2.1, 2.2, and 3.6 feet, 
respectively. Irregular fluctuations due to wind 
and atmospheric pressure vary from 1.9 feet 
below mean low water up to 6.5 feet above mean 
high water. Estimate of cost for new work is 
$12,946,000 (July 1971) including $6,200,000 to 
be contributed and $36,300 already contributed 
by local interests and exclusive of amounts 
expended on previous projects. This work was 
reclassified to Inactive because of state and 
local opposition. Dredging turning basin and 
anchorage in vicinity of Red Bank, 6 feet deep 
and about 19 acres in area; a channel in Claypit 
Creek, 6 feet deep and 100 feet wide about 1 mile 
from 6-foot curve in north branch to head of the 
creek; a channel in Oceanport Creek, 6 feet deep, 
100 feet wide and 2 miles long from channel in 
south branch to New York and Long Branch 
Railroad Bridge; and a channel in Little Silver 
Creek, 6 feet deep, 100 feet wide, and 1.6 miles 
long from channel in south branch to Seven 
Bridge Road Bridge is also inactive and excluded 
from foregoing description and cost estimate. 
Cost estimate for this portion (1960) is $578,000 
exclusive of $86,000 to be contributed by local 
interests. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. River and Harbor Act of 
1950 provides local interests furnish lands, 
rights-of-way, and spoil-disposal areas for 
2-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
construction and future maintenance; hold the 
United States free from damages; provide and 
maintain a suitable public wharf on each of the 
creeks to be improved, which shall be open to all 
on equal terms; remove Locust Avenue Bridge 
over Claypit Creek; and make cash contributions 
of $25,000, $33,000, and $27,500 
toward cost of improvement of Claypit, Oceanport, 
and Little Silver Creeks, respectively. 
Provided further that construction of any unit of 
proposed improvement may be undertaken 
independently of the other units when the 
required local cooperation has been provided. 
These conditions have not been fulfilled. Requirements 
under prior acts have been fully 
complied with. River and Harbor Act of 1965 
provides that local interests furnish lands, 
rights-of-way outside of the Federally owned 
lands, for construction and future maintenance 
and for aids to navigation upon request of the 
Chief of Engineers, including suitable spoildisposal 
areas, and necessary retaining dikes, 
bulkheads, and embankments therefor or the 
costs of such retaining works; hold the United 
States free from damages; assume all 
obligations of owning, operating and maintaining 
highway bridge, with such obligations 
to be assumed by local interests upon final 
completion of its construction; assign to a 
competent and properly constituted public body 
the power to regulate the use, growth, and free 
development of adequate boating facilities in 
the area to be served by the inlet, with the 
understanding that such facilities will be open 
to all equally; and provide, maintain, and 
operate necessary mooring and terminal 
facilities and utilities including an adequate 
public landing or wharf with provisions for the 
sale of motor fuel, lubricants and potable water, 
available to all equally. Requirements under 
1965 River and Harbor Act have not been 
complied with. 
Terminal facilities. There are 33 terminals 
with a total berthage of 7,986 feet on the 
waterway. Eight terminals with a total 
berthage of 1,000 feet are open to the public. In 
addition, many private pleasure boat landings 
have been constructed by owners of riverfront 
estates. Fifteen boatyards with storage space 
for 670 craft and equipped with 21 marine 
railways are available. None of the terminals 
has direct rail connections. Facilities considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Closeout report, to cancel project, underway. 
Condition at end of fiscal year. Work under 
the active portion of existing project began in 
October 1919 and is about 10 percent complete. 
Work completed consisted of providing 
authorized project dimensions in 12-foot entrance 
channel, 9-foot channel in South Branch, 
and a 6-foot channel in North Branch of the 
river. Work remaining under the existing project 
consists of dredging an inlet channel across the 
base of Sandy Hook protected by jetties and 
bulkheads, a bay channel extending to the 
existing Shrewsbury River Channel and a sixlane 
fixed highway bridge to span the new inlet 
as authorized by the River and Harbor Act of 
1965. Preconstruction planning (advance 
engineering and design) for work under this Act 
is about 50 percent complete. Planning included 
a physical model study, which was completed. 
The remaining work was subsequently 
reclassified to inactive because of state and local 
opposition. Close out report underway. Fomal 
close out of this work remains. Under the River 
and Harbor Act of 1950 work remaining consists 
of dredging turning basin and anchorage in 
vicinity of Red Bank, and channels in Claypit, 
Oceanport, and Little Silver Creeks. 
21. SUPERVISOR OF NEW YORK 
HARBOR 
(Prevention of Obstructive and Injurious 
Deposits) 
The District Engineer, New York District, was 
designated Supervisor of New York Harbor 
under the provisions of the River and Harbor 
Act of June 29, 1888 (33 U.S.C. 441-451), as 
amended July 12, 1952. Under this Act, the 
Supervisor of New York Harbor is charged with 
the mission of preventing the deposit of obstructive 
injurious materials in New York Harbor 
and its adjacent and tributary waters, including 
Long Island Sound. The Supervisor of New York 
Harbor is also responsible for enforcing the 
River and Harbor Act of August 18, 1894 (33 
U.S.C. 452) which makes it unlawful for any 
person or persons to engage in fishing or 
dredging for shellfish in any of the channels 
leading to and from New York Harbor, or to 
interfere in any way with the safe navigation of 
those channels by ocean steamships and ships 
of deep draft. The River and Harbor Act of 
March 3, 1899 (33 U.S.C. 403, 407, 409), commonly 
known as the Refuse Act, applies to all 
navigable waters in the United States. This 
Statute is used for enforcement purposes by the 
New York District Engineer on waterway 
violations not within the scope of the Act of 1888 
or on violations that occur within his area of 
jurisdiction outside of New York Harbor and 
Long Island Sound. The waters under the 
jurisdiction of the Supervisor of New York 
Harbor include New York Harbor and its 
tributaries, Raritan River, Arthur Kill, Newark 
2-16

NEW YORK, N. Y., DISTRICT 
Bay, Hackensack and Passaic Rivers, Kill Van 
Kull, Hudson River and its tributaries to the 
Federal Lock and Dam at Troy, New York, the 
East River and its tributaries, Harlem River and 
Long Island Sound. Enforcement of the Act of 
1888 in Long Island Sound is limited to the 
Sound itself, ending at lines drawn between the 
headlands of the many inlets and harbors along 
its shores. The Supervisor of the Harbor, in his 
capacity as District Engineer, may apprehend 
violators of anti-pollution laws under authority 
of the Act of March 3, 1899 when violations 
occur in the inland tributary waters of Long 
Island Sound. The navigable waters of the 
Hudson River extending north from Troy, New 
York to the New York District boundary line at 
the Canadian border are under the jurisdiction 
of the Disctrict Engineer. The mission includes 
surveillance and inspection by Patrol Boat, to 
the 3-mile limit of tows enroute to dumping 
grounds in the Atlantic Ocean to ensure that 
material is not illegally deposited in the waters 
of New York Harbor; patrol of inland waters i.e. 
Long Island Sound and the Hudson River to 
prevent illegal deposits that would have an 
adverse effect on navigation or anchorage; and 
prevention of interference with safe navigation 
in New York Harbor entrance channels and 
other waters under the jurisdiction of this office. 
Inspections of shorefront facilities and property 
are conducted by Inspectors utilizing government 
vehicles equipped with two-way radios. 
These Inspectors operate out of field offices 
located at Belle Meade and Jersey City, New 
Jersey, Fort Tilden, Fort Totten, Kingston and 
Troy, New York. The Troy Field Office covers 
the area of the upper Hudson River and Lake 
Champlain to the International Boundary at 
the Canadian Border. Inspections of shorefront 
facilities are conducted on an 8-hour a day, five 
days a week schedule. The activities include 
inspection of construction work, fill or excavation 
in waterways, including wetland areas, to 
determine if the individual or company concerned 
has a Department of the Army permit for 
such work, and if so, if the work is being 
performed in accordance with the provisions of 
the permit; investigation of illegal deposits of 
refuse into navigable waters or their tributaries, 
or on the shoreline where the material is subject 
to being washed into the waterways and 
adversely affect navigation; obstruction, by 
vessels, to navigation; inspections of placement 
and operation of fish pounds and fish nets in the 
waters of the bays and estuaries tributary to the 
Atlantic Ocean between Montauk Point, New 
York and Manasquan, New Jersey, the bays 
and estuaries in the State of New York tributary 
to Long Island Sound, and in the Hudson River. 
(See Table 2-E for Statement of Activities.) 
22. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 2-F at end of chapter.) 
23. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 2-G at end of chapter.) 
24. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Fiscal Year cost for preauthorization studies 
were $5,000 to complete Reconnaissance Report 
for Lake Bomoseen Channel, N.Y. and $25,220 
to complete Detailed Project Report for New 
Rochelle and Echo Bay, N.Y. 
Plans and specifications were completed for 
Catskill Creek, N.Y. Contract No. 2. Costs for 
Fiscal Year were $9,871. A contract for the 
removal and satisfactory disposal of all 
material except ledge rock lying above the plane 
of 11 feet below mean low water was awarded on 
June 20, 1975 and is continuing. 
Beach Erosion Control 
25. EAST ROCKAWAY INLET TO 
ROCKAWAY INLET & 
JAMAICA BAY, N.Y. (PT.I) 
Location. Atlantic coast of New York City, 
between East Rockaway and Rockaway Inlets, 
and the lands within and surrounding Jamaica 
Bay. The coastal area (about 10 miles long) is a 
peninsula in Queens County separating the 
ocean and the bay. (See Coast and Geodetic 
Suvey Charts 12327, 12350, and 12326.) 
Existing project. The project provides for 
approximately 8.7 million cubic yards of sand 
fill including the advanced placement of a two 
year supply of beach nourishment, and Federal 
participation in the cost of periodic beach 
nourishment of the shore protection works for 10 
years after completion of the initial beach fill. 
Federal participation (50 percent) includes 
$12,980,000 (October 1975) first cost and $832,- 
000 annually for 10 years for beach nourishment 
a total of $21,300,000. 
Local cooperation. Local interests must 
provide lands and rights-of-way, including 
borrow areas; bear 50.0 percent of total first cost 
presently estimated at $12,980,000 consisting of 
a cash contribution of $12,980,000 the final 
apportionment of cost to be made after actual 
costs and values have been determined and 
2-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
$832,000 annually for periodic nourishment for 
10 years, total non-Federal cost $21,300,000; 
hold the united States free from damages; 
maintain, during economic life of project, 
continued public ownership and use of non- 
Federal publicly owned shores upon which 
Federal participation in beach protection is 
based; maintain and operate all works after 
completion, control water pollution to the extent 
necessary to safeguard the health of bathers; 
local cooperation agreement was executed by 
the state May 17, 1974 and approved for 
Sec/Army 5/31/74. On May 22, 1974 sent to 
state an approved (OCE) Escrow Agreement. 
Operations and results during fiscal year. 
Advance engineering and design completed. 
Contract #1 awarded on 16 August 1974 at 
$10,434,465 for placement of 4.1 million cubic 
yards of fill along 3.0 miles of the project 
shorefront between B 110 and B 46 Streets. 
Actual placement of fill commenced in April 
1975 and was anticipated to be completed in 
October 1975. 
Condition at end of fiscal year. Advance 
engineering and design is completed. Placement 
of fill on Contract #1 was commenced in April 
1975 and ancitipated to be completed in October 
1975. 
26. FIRE ISLAND INLET TO 
JONES INLET, N.Y. 
Location. Atlantic Coast of Long Island, N.Y., 
between Fire Island Inlet and Jones Inlet, about 
15 miles. Fire Island Inlet is on south shore of 
Long Island, about 50 miles by water south and 
east of the Battery, New York City, and connects 
Great South Bay and the Atlantic Ocean. Jones 
Inlet is on south shore of Long Island, about 37 
miles by water south and east of the Battery, 
New York City, and connects Hempstead Bay 
and the Atlantic Ocean. (See Coast and Geodetic 
Survey Chart 12352.) 
Existing project. Provides for Federal participation 
in restoration and protection of shore 
from Fire Island to Jones Inlets by dredging 
inlet shoal in Fire Island Inlet and construction 
of a sand dike to relieve pressure of tidal 
currents against Oak Beach, to provide a 
deposition area for littoral drift, and to obtain 
fill material for a feeder beach and Oak Beach. 
Authorization initially provided for three dredging 
operations over a period of 10 years, but was 
reduced to two, based on subsequently authorized 
project modification for sand bypassing 
facilities and on limited reduction of channel 
maintenance costs of navigation project. 
For first increment, based on cost sharing 
provisions of Public Law 727, 79th Congress, 
pertinent to beach erosion control benefits, 
Federal participation was authorized to extent 
of one-third of costs allocated to beach erosion 
control feature and entire cost allocated to 
navigation feature, a total of 42 percent for first 
increment. Based on provisions of 1962 River 
and Harbor Act enacted after completion of first 
increment, which modified Federal participation 
to extent of one-half of costs allocated to 
beach erosion control feature, and on deletion of 
navigation benefits based on maintenance 
experience, Federal share of second increment 
was evaluated at 67.9 percent. 
Project, as modified, provides for combined 
beach erosion control and navigation improvements 
comprising a 1,000-foot extension of 
existing jetty, a littoral reservoir with a capacity 
of 1,200,000 cubic yards west of jetty, a navigation 
channel 28 feet deep and 500 feet wide 
leading from the littoral reservoir to a deposition 
reservoir inside the inlet with a capacity of 2 
million cubic yards, and other appurtenant 
works including jetty modifications to permit 
fishermen use, and dikes. Estimated Federal 
share of participation is 60.5 percent of the first 
cost of project modification. Periodic transfer of 
littoral drift involving the bypassing of 1,200,- 
000 cubic yards of sand on the average of once 
every 2 years to a feeder beach over the economic 
life of the project, serving both maintenance of 
navigation channel and nourishment of 
beaches westerly of the inlet, is included in 
annual maintenance. Mean range of tide is 4.1 
feet. Total estimated Federal cost of new work is 
$28,786,767 (October 1975), of which $2,646,767 
is for work authorized by 1958 River and Harbor 
Act, and $26,140,000 for modification authorized 
by 1962 River and Harbor Act. Project 
documents contain latest published maps. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. River and Harbor Act of 
1958 provides local interests obtain approval by 
Chief of Engineers, before starting work on any 
feature of project, of detailed plans and 
specifications and arrangements for 
prosecuting work on that feature; provide lands, 
and rights-of-ways; hold the United States free 
from damages; assure that water pollution that 
would endanger health of bathers will not be 
permitted; assure maintenance of recommended 
project during its useful life as may be required 
to insure realization of anticipated benefits; and 
assure continued public ownership of the shore 
and its administration for public use during 
economic life of project. Long Island State Park 
Commission of State of New York, the 
cooperating agency, entered into an agreement 
with United States August 21, 1958, as modified 
November 18, 1959, and February 1, 1962, in 
which the agency adopted plan of improvement 
2-18

NEW YORK, N. Y., DISTRICT 
for beach erosion control authorized by Congress 
and agreed to furnish its share of cost, and 
comply with all other requirements of local 
cooperaton. By letter dated October 7, 1958, 
cooperating agency requested United States to 
undertake and supervise construction of first 
increment of work. First modification to agreement 
enabled construction by Federal Government 
of a sand closure across gorge channel 
which was completed in 1960 at a cost of 
$364,000 from funds furnished by cooperating 
agency (contributed funds-other). Second 
modification enabled delineation of sand 
closure as a part of authorized project in 
accordance with Public Works Appropriation 
Act, 1962, which included $152,880 (42 percent of 
$364,000) specifically for repayment of Federal 
share of cost. Unused contributed funds, surplus 
to needs of first increment, were returned May 
17, 1962. Second dredging operation was financially 
complete April 30, 1966, and unused 
required contributed funds were returned July 7, 
1966. In addition to assurances similar to those 
cited for the work under the 1958 act, local 
interests, for the work under the 1962 act, must 
provide and maintain a parking lot with 
adequate sanitary facilities as may be required 
for recreational fishermen use of the jetty 
extension; and contribute about 39.5 percent of 
total first cost, 32.1 percent of periodic dredging 
cost allocated to beach erosion control for beach 
nourishment, and 9.8 percent of maintenance 
cost. Off-project fishing facilities are a non- 
Federal responsibility. Total estimated cost of 
local cooperation to be provided by local 
interests is $19,332,335 (October 1975) for new 
work, of which $2,272,335 (cash contribution) is 
for work authorized by the 1958 act; and 
$17,060,000 the 1962 act, of which $17,040,000 is 
cash contribution and $20,000 is other non- 
Federal costs for off-project facilities; exclusive 
of shares of annual periodic dredging and 
maintenaice costs. Assurances executed with 
State 4/27/73 approved by Sec of Army 5/24/73. 
Operations and results during fiscal year. 
Contract #2 was awarded on June 12, 1974 for 
$4,892,650. $25,072 was expended for engineering 
and design preliminary dredging. Actual 
work on contract #2 was commenced on July 27, 
1974, and was terminated by the contractor on 
April 18, 1975 after having dredged 931,310 
cubic yards of which 897,554 cubic yards was 
pay-uuantity at a cost of $3,335,000 which was 
the available funds in the fiscal year for the 
contract. An invitation for bids on the third 
contract consisting of dredging about 1,845,000 
cubic yards of material and placing it along the 
11,000-foot long feeder beach was advertised in 
June 1975. 
Condition at end of fiscal year. Under the 1958 
Act, the first dredging operation is complete at a 
cost of $1,124,826 exclusive of $1,553,331 required 
contributed funds. Second dredging 
operation is complete at a cost of $1,521,941, 
exclusive of $719,504 required contributed 
funds. Engineering and design for work under 
the 1962 act was initiated in April 1965. Model 
test by Waterways Experiment Station was 
completed and report submitted November 
1969. Design Memorandum was submitted to 
Chief of Engineers September 1971 and was 
approved February 1971 subject to comments, 
which were submitted April 1971. Advance 
plans and specifications submitted April 1971. 
The Environmental Statement was submitted 
to the Council of Environmental Quality April 
16, 1971. Contract 1 awarded June 8, 1973, and 
physically complete May 22, 1974. Contract 2 
was awarded in June 12,1974. Construction was 
commenced in July 1974 and was terminated in 
April 1975. $21,100 was allotted to Water 
Experiment Station in January 1975 for computer 
aided historical photo-analysis study of 
Fire Island Inlet system. 
27. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 2-H at end of chapter.) 
28. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
Beach Erosion Control activities pursuant to 
Section 103 Public Law 826, 84th Congress as 
amended (preauthorization) 
Fiscal year cost for preauthorization studies 
was $1,807 on Neptune City, N.J. to continue 
Detailed Project Report. 
Flood Control 
29. EAST ROCKAWAY INLET TO 
ROCKAWAY INLET & 
JAMAICA BAY, N.Y. (PT. II) 
Location. Atlantic coast of New York City, 
between East Rockaway and Rockaway Inlets, 
and the lands within and surrounding Jamaica 
Bay. The coastal area (about 10 miles long) is a 
peninsula in Queens County separating the 
ocean and the bay. (See Coast and Geodetic 
Survey Charts 12327, 12350, and 12326.) 
Existing project. The multi-purpose improvement 
provides for a hurricane barrier, 4,530 feet 
long, across entrance to Jamaica Bay with a 
2-19

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
600-foot navigation opening and two 150-foot 
gates which would partially close the opening to 
300 feet; dikes and levees, 1.2 miles long to high 
ground north from the barrier and dikes, levees, 
and floodwalls, 7.7 miles long, south and east 
from the barrier to and along the oceanfront to 
high ground at eastern end of Rockaway 
peninsula; fill placement along the 6-mile 
oceanfront floodwall with a berm 100 to 200 feet 
wide at 10.0 feet above mean sea level; and 
stoplog structures, stairways, ramps, road 
raising, and other appurtenant works, including 
fishing platforms on hurricane barrier. 
Estimated Federal cost is $101,600,000 (October 
1975) for construction (which represents the 
Federal share of total first cost of project 
reduced by amount of local cash contribution 
presently estimated at $7,380,000 for the barrier, 
its gates and fishing platforms, equivalent to 
the present worth of the annual cost of 
maintenance, operation, and major 
replacements by the United States), 
maintenance, operation and major 
replacements of the barrier, its gates and 
fishing platforms would be a Federal responsibility. 
Estimated non-Federal cost is $51,800,- 
000 (representing 34 percent of total first cost of 
project) consisting of $270,000 for lands and 
alterations and relocations of structures, and a 
cash contribution of $51,530,000 including a 
cash contribution of $7,380,000 for the barrier, 
its gates and fishing platforms; exlusive of 
annual maintenance and operation costs for the 
project (except the barrier, its gates and fishing 
platforms). (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must 
provide lands and rights-of-way, including 
borrow areas; alter and relocate buildings, 
streets, storm drains, utilities, and other structures; 
bear 34.0 percent of total first cost 
presently estimated at $51,800,000 consisting of 
$270,000 for items listed above, and a cash 
contribution of $51,530,000 the final apportionment 
of cost to be made after actual costs and 
values have been determined; provide an 
additional cash contribution for the barrier, its 
gates and fishing platforms, equivalent to the 
present worth of the annual cost of 
maintenance, operation, and major 
replacements by the United States, presently 
estimated at $7,380,000 subject to adjustment 
based on detailed design of project features, to 
be paid in a lump sum before starting construction; 
hold the United States free from damages; 
maintain, during economic life of project, 
continued public ownership and use of non- 
Federal publicly owned shores upon which 
Federal participation in beach protection is 
based; maintain and operate all works after 
completion, except the barrier, its gates, and 
fishing platforms, control water pollution to the 
extent necessary to safeguard the health of 
bathers; and at least annually inform interests 
affected that hurricane improvements will not 
provide substantial protection against 
hurricane and storm tide levels higher than 
about 3 feet above the elevation of Hurricane 
Donna of September 12, 1960. State of New York 
Water Resources Commission stated that the 
State would cooperate in meeting requirements 
subject to final development of a soundly 
engineered and economically feasible plan and 
cooperation from local municipalities. 
Operations and results during fiscal year. 
Advance engineering and design continued 
coordination with local interests. Additional 
model studies for the enhancement of water 
quality through modification of the proposed 
hurricane barrier design were continued. 
Condition at end of fiscal year. Advance 
engineering and design was started January 
1967. Initial model testing complete. The present 
modeling program is about 75 percent 
completed. Additional model studies planned 
for the future. Completion of engineering and 
design and of construction remain. 
30. ELIZABETH, N.J. 
Location. In city of Elizabeth, N.J. (Union 
County), extending 4.2 miles upstream from 
mouth of Elizabeth River at Arthur Kill. The 
river continues 7.7 miles northward through 
Union and Essex counties to its headwaters in 
East Orange, N.J. (See Geological Survey 
quadrangles, Roselle, Elizabeth, Caldwell and 
Orange; and Army Map Service quadrangles, 
similarly designated.) 
Existing project. Includes an improved 
channel with levees and/or walls where 
necessary between Bridge Street and Arthur 
Kill (2.1 miles); a concrete flume between 
Trotter's Land and U.S. Highway No. 1 (1.4 
miles); closure to high ground at upstream and 
downstream ends; interior drainage, including 5 
pumping stations and 11 ponding areas; 
reconstruction or replacement of 16 bridges and 
associated street regrading; and utilities 
relocations. Total estimated Federal cost is 
$28,740,000 (October 1975). Total estimated non- 
Federal cost for all requirements of local 
cooperation excluding maintenance is $7,870,- 
000 including $390,000 cash contribution. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. Local interests must 
provide lands and rights-of-way for construction 
and subsequent maintenance, the costs and 
values incurred in the interest of hurricane tidal 
2-20

NEW YORK, N. Y., DISTRICT 
flood protection to be credited to required local 
contribution to the project first costs allocated to 
hurricane tidal flood protection; hold the United 
States free from damages; maintain and operate 
completed works including all dredging required 
in the channel to maintain the design 
depths in the tidal reach; reconstruct all bridges 
and approaches except railroad bridges, and 
relocate existing sewerage and drainage 
facilities, streets, utilities, and other structures, 
such costs and values incurred in interest of 
hurricane tidal flood protection to be credited to 
required local contribution to protect first costs 
allocated to hurricane tidal flood protection; 
bear 30 percent of first costs allocated to 
hurricane tidal flood protection, including the 
two items listed above pertaining to lands, 
reconstruction and alterations, and a cash 
contribution now estimated at $390,000 to be 
paid either in a lump sum before starting 
construction, or in installments before starting 
pertinent work items in accordance with construction 
schedules as required by the Chief of 
Engineers; take necessary action to protect 
channels from future obstruction or encroachment 
including waste disposal that would 
reduce their flood-carrying capacity; take appropriate 
measures to control development in 
partially protected areas and fringe areas not 
included in the project with a view to preventing 
an undue increase in flood damage potential; 
maintain existing natural detention areas 
along the Elizabeth River between Union 
Avenue and Trotters Lane free from encroachment 
so as not to reduce their detention 
capacity; provide any additional gravity outlets 
or pumping station capacities made necessary 
by any modifications or encroachments on the 
ponding areas; bear any increased Federal costs 
for the improvement that may result from any 
future requirements for parkway developments; 
and at least annually, notify interests affected 
that the improvements will not provide complete 
protection from fluvial floods greater than 
that in July 1897. Agency responsible for local 
cooperation is city of Elizabeth (with concurrence 
of Union County and State of New 
Jersey). Signed assurances of local cooperation 
were accepted by the District Engineer on 
January 9, 1970. 
Operation and results during fiscal year. 
Advance planning continued. Penn-Central 
Bridge construction continued. Construction of 
downstream dredging portion of the project was 
initiated. Continued local cooperation. 
Condition at end of fiscal year. Advance. 
planning (begun January 1966), leading to first 
construction (Ursino Basin) and the Penn- 
Central Bridge and downstream dredging 
contracts, has been completed. General design 
memorandum and its supplement submitted. 
Penn-Central Railroad Bridge agreement executed. 
Environmental impact statement submitted 
to the council on environmental quality 
on April 20, 1971. Upstream Ursino Basin 
construction complete. Completion of engineering 
and design and construction remain. 
31. FIRE ISLAND INLET TO MONTAUK 
POINT, N.Y. 
Location. That portion of Atlantic Coast of 
Long Island in Suffolk County extending from 
Fire Island Inlet easterly to Montauk Point, 
N.Y.-about 83 miles long. This frontage, comprises 
about 70 percent of total ocean frontage of 
Long Island. Fire Island Inlet is about 50 miles 
by water east of the Battery, New York City. (See 
Coast and Geodetic Charts 13209, 12354 and 
12353.) 
Existing project. Provides for Federal participation 
in improvement to prevent beach 
erosion and hurricane damages by: widening 
beaches along developed areas between Kismet 
and Mecox Bay t a minimum width of 100 feet 
at elevation 14 feet above mean sea level; raising 
dunes to an elevation of 16 feet above mean sea 
level from Fire Island Inlet to Hither Hills State 
Park, at Montauk and opposite Lake Montauk 
Harbor; planting grass on dunes; constructing 
gated interior drainage structures at Mecox 
Bay, Sagaponack Lake, and Georgica Pond; 
constructing not to exceed 50 groins, if needed; 
and Federal participation in cost of beach 
nourishment for not to exceed 10 years from 
year of completion of a useful nourishment unit. 
Total estimated Federal cost is $95,020,000 
(October 1975) which includes participation in 
periodic beach nourishment for 10 years at 
$66,000 annually. Total estimated non-Federal 
cost for all requirements of local cooperation is 
$47,630,000 inclusive of $35,690,000 cash contribution 
by local interests. Project cost estimate 
reflects revised cost sharing provisions of 1962 
River and Harbor Act. Increased Federal 
participation from about 53 percent due to an 
adjustment of cost sharing in accordance with 
Section 31 of the Water Resources Development 
Act of 1974 to about 70 percent of first cost of 
project construction, excluding annual nourishment 
costs. 
Local cooperation. River and Harbor Act of 
1960 provides that before starting construction, 
local interests give assurances they will (a) 
provide lands, rights-of-way, including borrow 
areas, for construction; (b) make alterations and 
relocations of buildings, streets, storm drains, 
utilities, and other structures made necessary 
by construction; (c) bear 30 percent of total first 
2-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
cost estimated at $40,440,000 to consist of items 
listed in (a) and (b) above and a cash contribution 
estimated at $35,690,000 or, if any section is 
undertaken separately apportionment of first 
cost will be as shown in District Engineer's 
report, with due regard to change in public use 
and ownership and other changes before construction; 
provided that cash contribution be 
paid either in a lump sum before starting entire 
project, or in installments before starting 
pertinent items, in accordance with construction 
schedules as required by Chief of 
Engineers, final apportionment of cost to be 
made after actual costs and values have been 
determined; (d) hold the United States free from 
damages; (e) maintain all works and undertake 
periodic beach nourishment after completion, 
except that for 10 years after completion of a 
useful nourishment unit Federal Government 
would contribute, dependent on conditions of 
public use and ownership and other changes at 
time of construction an amount for entire project 
now estimated at $66,000 annually; (f) maintain 
during economic life of project continued public 
ownership of non-Federal publicly owned 
shores and continued availability for public use 
of privately owned shore equivalent to that upon 
which recommended Federal participation is 
based; (g) adopt appropriate ordinances to 
provide for preservation of dunes and their 
protective vegetation; (h) control water pollution 
to extent necessary to safeguard health of 
bathers; (i) obtain approval of Chief of 
Engineers of detailed plans and specifications 
for work contemplated and arrangements for its 
prosecution before starting any work on beach 
protection phase of project for which Federal 
participation is planned, if undertaken 
separately from recommended combined project; 
and (j) contribute in cash toward cost of 
hurricane protection works constructed under 
this plan, in addition to apportionment required 
in (c) above, an amount equal to increased 
Federal cost resulting from separate construction 
of beach protection work referred to in (i) 
above. Responsible agency is State of New York. 
On July 30, 1963, the State reflecting the desires 
of Suffolk County, requested the inclusion of a 
minimum of 13 groins in initial construction of 
Moriches-Shinnecock reach. Chief of Engineers 
concurred in inclusion of up to 13 groins. 
Assurances were executed by Superintendent of 
Public Works, State of New York, on August 14 
and accepted by the District Engineer August 
20, 1963. On February 5, 1964, the State 
requested consideration of a plan, as proposed 
by Suffolk County, for initial construction of 13 
groins of which 11 would be in the Moriches- 
Shinnecock reach, and 2 in the Southampton- 
Beach Hampton reach in vicinity of Georgica 
Pond; and that sandfill and dune construction 
be withheld for the present except for 1 miles on 
each side of Shinnecock Inlet. On February 27, 
1964, the Chief of Engineers accepted the 
proposals, in part, and supplemental 
assurances were executed by State of New York 
on April 20, 1964, and accepted by District 
Engineer April 27, 1964, as follows: the State of 
New York now elects to proceed with authorized 
combined beach erosion control and hurricane 
protection project for South Shore of Long 
Island; that Superintendent of Public Works 
hereby reaffirms his assurance of August 14, 
1963, relative to complete project; that State of 
New York, as cooperating agency, will now 
agree that artificial fills will be added when and 
to extent found necessary by the Chief of 
Engineers, but not earlier than 3 years after 
completion of groins unless both the State of 
New York and the Chief of Engineers mutually 
agree to an earlier placement; that the 
superintendant agrees for State of New York to 
contribute the full amount of any increase in 
Federal costs resulting from the separate 
construction of the groins and subsequent fill; 
and that the State agree that construction of the 
two groins in the Georgica Pond area will 
depend on a favorable finding, following a study 
by the Chief of Engineers. Study was completed 
July 31, 1964, recommending construction, and 
approved by the Chief of Engineers on 
September 22, 1964. By letter dated November 5, 
1964, the New York State Department of Public 
Works confirmed that title to all properties and 
interests in properties necessary for constructing 
the 11 groins was fully vested in Suffolk 
County. By letter dated December 7, 1964, the 
Department stated that the county had obtained 
easements or fee title for the parcels necessary 
for constructing the two groins. New York State 
Department of Public Works furnished $844,600 
and $830,330 required contributed funds October 
30, 1964, and September 7, 1965, respectively, 
for construction of 11 groins in Moriches- 
Shinnecock reach, and $439,900 on January 22, 
1965, for construction of 2 groins in Georgica 
Pond area of the Southampton-Beach Hampton 
reach. The completed 2 groins and 11 groins 
were accepted by the New York State Department 
of Public Works for maintenance on May 
11, 1966 and April 10, 1967, respectively. 
On March 22, 1965, the State recommended 
that planning priority be in the order: 
Southampton-Beach Hampton (drainage structures 
first); Shinnecock Inlet-Southampton; 
Beach Hampton-Montauk Point; and Fire 
Island Inlet-Moriches Inlet. Planning on the 
drainage structures was initiated but was 
suspended, based on: meeting of October 28, 
1965 with the Georgica Pond Association and 
2-22

NEW YORK, N. Y., DISTRICT 
the Preservation Society of East End wnerein 
concern was indicated regarding the effects of 
the proposed drainage structure on ecology, 
salinity, pond level and aesthetic values; 
meeting with Congressional representatives, 
State legislators, Federal agencies and local 
officials held on May 26, 1966; and resolution of 
the Suffolk County Board of Supervisors 
adopted June 13, 1966 requesting advancement 
of the planning of the Fire Island Inlet-Moriches 
Inlet reach (Fire Island National Seashore). On 
June 16, 1967, the New York State Department 
of Public Works requested that the following 
work be undertaken as immediate priority 
items: in Moriches-Shinnecock Reach, beach 
and dune fill at 11 groin site, construction of four 
groins west of the completed 11 groins, beach 
and dune fill east of the 11 groins; in 
Southampton-Beach Hampton reach (at East 
Hampton), construction of two additional 
groins, and the outlet structure at Georgica 
Pond. On March 18, 1968 the Suffolk County 
Board of Supervisors adopted a resolution 
supporting construction of 4 groins in Reach 2 
(Moriches-Shinnecock) and 2 groins in Reach 4 
(Southampton-Beach Hampton). On April 22, 
1968 the Board adopted a more inclusive 
resolution authorizing participation in beach 
erosion and hurricane protection for the 
Moriches-Shinnecock reach and in the Georgica 
Pond area of the Southampton-Beach Hampton 
reach. On December 24, 1968, the Commissioner 
of the New York State Conservation Department 
executed the second supplement to the 
assurances of local cooperation, which was 
accepted by the District Engineer on January 
24, 1969. This reaffirmed previous assurances 
contained provisions for constructing four 
additional groins in an area extending 6,000 feet 
west from the most westerly groin in the 
existing eleven-groin field in the Moriches Inlet 
to Shinnecock Inlet Reach, and for placing 
beach and dune fill in this area to the full design 
cross section as defined in the authorized project 
report, except for the portion of the dune mean 
sea level elevation 16 feet and 20 feet. Thus this 
stage construction established the top of dune to 
an elevation of 16 feet m.s.l. with a 65 foot width 
at that elevation and the top of berm to 14 feet 
m.s.4. with a 100 foot width at that elevation. 
These assurances also required that the State 
obtain and provide without cost to the United 
States all lands, easements, and rights-of-way, 
to permit entry.for the period of construction, 
and that the necessary rights will be obtained, 
as required, of lands, easements and rights-ofway, 
for maintenance and repair of the groins, 
dunes, and berms, and to insure the integrity of 
the completed structure. (See Table 2-B for 
Authorizing Legislation.) 
Operations and results during fiscal year. 
Continued study of coastal protection needs for 
present and future conditions. At the request of 
the local cooperating agency planning was 
resumed in 1975 for another increment of work 
at Westhampton Beach in the Moriches Inlet to 
Shinnecock Inlet reach, consisting of placement 
of beach and dune fill in the initial 11 groin field 
constructed in 1966 and along the 9,500 feet of 
shore westward of the existing groin field. 
Condition at end of fiscal year. Engineering 
and design began November 1962 and project 
construction commenced in January 1965. Two 
groins in Reach 4: Southampton-Beach Hampton, 
Section 3, were initiated in March, and 
completed in September 1965, at a total cost of 
$720,950 of which $382,109 were incurred 
against required contributed funds. Eleven 
groins in Reach 2: Moriches-Shinnecock, Section 
2, were initiated in January 1965, and 
completed in October 1966 at a total cost of 
$2,854,565 of which $1,370,191 were incurred 
against required contributed funds. Initial 
beach fill placement for 750,000 cubic yards in 
Reach 2, Section 1A was completed on May 23, 
1969. On August 4, 1969 work started on 4 groins 
and sandfill in Reach 2, Section 1A and was 
completed November 14, 1970. 3,083 tons of 
stone and 1,111,000 cubic yards of sand were 
placed. Total cost for all Section lA was 
$3,663,455 including $1,791,428 required contributed 
funds. Planning for another increment 
of work at Westhampton Beach underway. 
Completion of engineering and design, and 
construction of the remainder of the project 
remain. 
32. NORTH ELLENVILLE, N.Y. 
Location. In Ellenville, N.Y., on Beer Kill and 
Fantine Kill, at their confluence with Sandburg 
Creek, which discharges into Rondout Creek at 
Napanoch, N.Y., about 2 miles downstream 
from Ellenville. (See Geological Survey, Ellenville 
quadrangle; and Army Map Service, 
Ellenville quadrangle.) 
Existing project. Improvement includes constructing 
10,821 feet of levees (9,078 feet along 
Beer Kill and 1,743 feet along Fantine Kill) and 
2,761 feet of floodwalls (1,946 feet along Beer 
Kill and 815 feet along Fantine Kill); capping 
440 feet of retaining walls on Beer Kill; removing 
concrete dam, improving 985 feet of channel, 
and constructing a 1,144 foot stream diversion 
on Fantine Kill; providing interior drainage 
including 2,800 feet of diversion ditches, 4 
drainange structures, 2 ponding areas; altering 
or replacing 6 bridges; and relocating 15 
2-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
structures and miscellaneous utilities. Existing 
project known also as "Beer Kill and Fantine 
Kill at Ellenville, N.Y." is one of three physically 
and functionally independent projects included 
in Rondout Creek and Wallkill River, N.Y. 
and N.J., Survey Report. Final project plans 
contain latest map. Estimated Federal cost for 
project is $3,751,300 (October 1975). Estimated 
non-Federal cost including landsand 
relocations is $1,427,367. (See Table 2-B for 
Authorizing Legislation.) 
Local ccoperation. It was necessary, under 
project authorization, for local interests to 
furnish lands and rights-of-way for construction; 
alter highways, highway bridges, utility 
and related facilities; hold the United States free 
from damages; protect channels, ponding areas 
and other flood works from future encroachment 
or obstruction that would reduce their 
flood carrying capacity and control development 
of fringe areas not protected by proposed 
improvement with a view to preventing an 
undue increase in flood damage potential; and 
maintain and operate completed works. State of 
New York is responsible for local cooperation. 
The Commissioner, New York State Conservation 
Department (now Dept. of Environmental 
Conservation), representing New York State, 
executed the assurances of Local Cooperation 
on March 5, 1968, which were accepted by the 
District Engineer for the United States on 
March 25, 1968. A supplemental assurance was 
signed by the State of New York on March 30, 
1970 and accepted by the District Engineer on 
April 10, 1970. 
Operations and results during fiscal year. 
Construction of the project was completed on 7 
October 1974. 
Condition at end of fiscal year. Preconstruction 
planning was started November 1964 and 
completed September 1967. Based on local 
interests requests, design was revised. Design 
Memorandum was approved May 18, 1970. 
Environmental Statement submitted to the 
Council of Environmental Quality February 16, 
1971. Final plans and specifications submitted 
April 21, 1971. Porject construction complete. 
33. RAHWAY, SOUTH BRANCH, N.J. 
Location. In city of Rahway, at the junction of 
South Branch of the Rahway River with the 
Rahway River, in Union County, New Jersey, 
4.6 miles upstream of confluence of the river 
with Arthur Kill which separates New Jersey 
from Staten Island, N.Y. (See Army Map Service 
quadrangles Perth Amboy and Roselle). 
Existing project. Improvement includes 
realingment and reshaping of existing channel 
for 1900 feet extending upstream from 
Hazelwood Avenue (about 300 from stream 
junction); compacted fill on east bank; 1180 feet 
of levee, 60 feet of wall, and compacted fill on the 
west bank; remove Mill Street Bridge; interior 
drainage including pump station and ditches. 
Project was authorized by the Chief of 
Engineers January 6, 1969, pursuant to section 
205, Public Law 858, 80th Congress, as amended, 
subject to the adoption of a Department of 
Housing and Urban Development project (subsequently 
adopted). Estimated Federal cost for 
project is $1,557,000 (October 1975). Estimated 
non-Federal cost, including real estate, is 
$430,600. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. It was necessary, under 
project authorization, for local interests to 
furnish without cost to the United States all 
lands, easements, and rights-of-way for the 
project, including spoil areas within the city 
necessary for construction. Local interets must 
also: hold and save the United States free from 
damages; maintain completed works; provide 
without cost to the United States for the 
relocation of utilities, buildings, raising of roads 
and manholes, construction of appurtenant 
sidewalks and curbs; protect the channel and 
flood control works from encroachment or 
obstruction including waste disposal that would 
reduce their flood carrying capactiy. Also, agree 
to take appropriate measures to control development 
in fringe areas not protected by the 
improvement with a view to preventing an 
undue increase in the flood damage potential; to 
pay all Federal costs in excess of $2,000,000; at 
least annually notify interests affected that the 
improvements will not provide complete protection 
from floods greater than the design condition. 
An agreement of Local Cooperation was 
signed by the Mayor, City of Rahway, New 
Jersey on March 8, 1972, and was signed by the 
New York District Engineer for the United 
Stated on March 16, 1972. A modification No. 1 
to the basic agreement was signed by the City of 
Rahway Mayor on April 9, 1974 and signed by 
the District Engineer on April 19, 1974. On July 
29, 1969, the City of Rahway furnished $27,500 
(contributed "other") for non-Federal design 
costs. Construction of project was authorized on 
basis of the Department of Housing and 
Development's acceptance of a city urban 
renewal project. 
Operation and results during fiscal year. 
Design supplement to detailed project report 
approved on December 3, 1974. Construction of 
project was initiated on June 30, 1975. 
Condition at end of fiscal year. Detailed 
project report for project was completed on 
2-24

NEW YORK, N.Y., DISTRICT 
September 18, 1967 and financed under 
"Rahway, N.J." project. Engineering was 
started January 9, 1969. Philadelphia District 
submitted Federal and non-Federal plans and 
specifications to New York District July 6, 1970. 
Plans and specifications were subsequently 
updated by New York District. Environmental 
Impact Statement submitted to the Council on 
Environmental Quality on November 8, 1972. 
Construction of project was initiated and is 
being continued. 
34. RARITAN BAY AND SANDY 
HOOK BAY, N.J. 
Location. Comprises about 21 miles of coast in 
Middlesex and Monmouth Counties, N.J., and is 
about 30 miles southwest of New York City. It 
extends along Raritan and Sandy Hook Bays 
between entrances to Raritan River on the west 
and Shrewsbury River on the east. Sandy Hook, 
N.J., a low-lying peninsula on the east, 
separates Atlantic Ocean from Sandy Hook 
Bay. (See Coast and Geodetic Survey Charts 70, 
286, 369, 824, 1000, 1108, 1215; and Geological 
Survey quadrangles of South Amboy, Keyport 
and Sandy Hook.) 
Existing project. Federal participation in 
constructing levees, beach fill, interior drainage 
facilities and groins for beach erosion control 
and hurricane protection. For Madison 
Township section, combined shore and 
hurricane protection improvement provides for: 
about 1.7 miles of beach fill at elevations of 5.5, 
10, and 15 feet above mean sea level: about 0.4 
mile of tieback levees at 15 feet above mean sea 
level; and interior drainage facilities. Shore 
protection improvement is provided for 
Matawan Township and Borough of Unionr 
Beach sections, including about 0.9 miles of 
beach fill at elevations of 5.5 and 10 feet above 
mean sea level for Matawan, and about 0.6 mile 
of beach fill at 5.5 feet above mean sea level for 
Union Beach. In the Borough of Keansburgh 
East Keansburg, and West Keansburg, hurrican 
protection is provided, including about 2.7 miles 
of beach fill and 2.3 miles of tieback levees at an 
elevation of 15 feet above mean sea level; 
interior drainage structures; and three groins in 
Keansburg for shore protection. Design studies 
relocated for Keansburgh-East Keansburg 
closure to an alignment west of Thorne Creek 
and provide additional protection in West 
Keansburg. Total estimated Federal cost is 
$8,130,000 (October 1975) which includes $57,- 
000 reimbursement to local interests as federal 
share of costs incurred for beach protection 
accomplished at Keansburg in 1957. Total 
estimated non-Federal cost for all requirements 
of local cooperation is $4,540,00, including 
$3,910,000 cash contribution. Project cost estimate 
reflects the cost sharing provisions of 
1962 River and Harbor Act. These new 
provisions resulted in increase in Federal 
participation from about 64.8 percent to about 
66.4 percent of estimated project cost exclusive 
of reimbursable completed work at Keansburg. 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with for the 
Madison and Keansburg-East-West Keansburg 
sections, except for those provisions affecting 
continuing actions such as operation and 
maintenance. For details see 1970 Annual 
Report. By resolution dated December 2, 1963, 
Matawan Township declined to participate in 
the project at the present time. The State then 
requested construction of Matawan Township 
section be deferred for inclusion in a later 
contract. Assurances for Matawan and Union 
Beach will be obtained if and when construction 
planning starts. 
Operations and results during fiscal year. 
Construction was accomplished for improvement 
work which was added to the previously 
completed original Keansburg Closure Work. 
Preparation of Operations and Maintenance 
Manual for shore and closure work at 
Keansburg initiated and work is 90 percent 
complete. 
Condition at end of fiscal year. Engineering 
and design of existing project commenced 
November 1962 and resulted in the completion 
of design studies, and plans and specifications 
for the Madison section and the Keansburg 
section. Design for the tentatively deferred 
Matawan section is about 90 percent complete. 
Entire project construction about 93 percent 
complete. Madison Township construction was 
completed on October 27, 1966, and accepted by 
the State of New Jersey for operation and 
maintenance on March 20, 1967. Operations 
and maintenance manual for Madison section 
completed and furnished to State of New Jersey. 
Construction of the shore work at Keansburg 
was completed on December 23, 1969 and 
accepted by State on February 5,1970. Construction 
of Keansburg closure work completed on 
January 15, 1974. Additional items of improvement 
work incorporated into Keansburg closure 
work facilities. State accepted Keansburg 
closure work on June 6, 1974. Operation and 
maintenance manual for shore work and closure 
work at Keansburg being prepared and is 90 
percent complete. 
35. ROSENDALE, N.Y. 
Location. In town of Rosendale, N.Y., on 
Rondout Creek just upstream of its confluence 
2-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
with Wallkill River, its largest tributary. Creek 
flows into Hudson River at Kingston, N.Y. (See 
Geological Survey quadrangle, Rosendale; and 
Army Map Service quadrangle, Rosendale). 
Previous project. For details of completed 
clearing and snagging project pursuant to 
section 208, 1954 Flood Control Act, see Annual 
Report for 1957. 
Existing project. Includes channel excavation 
to deepen and widen for 11,300 feet, starting 
1,000 feet upstream of the New York State 
Thruway bridge and ending 450 feet upstream 
of James Street Bridge, with widening and 
deepenng through the gorge at Lefevre Falls for 
about 500 feet; supplemented by about 2,750 feet 
of levees along low banks on both banks, about 
1,470 feet of concrete walls in vicinity of bridges, 
and interior drainage works consisting of 
ditches, gated culverts and outlets, ponding 
areas, and pumping station. Existing project is 
one of three physically and functionally independent 
projects included in Rondout Creek 
and Wallkill River, N.Y. and N.J. Survey 
Report. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Fully complied with except 
for those concerning operation and 
maintenance. For details see 1970 Annual 
Report. Contributions by the Village of Rosendale 
of $26,000 and $3,736 were received on 
March 5 and May 15, 1968 respectively. Contributions 
by the State of New York of $94,000, 
$24,112, $2,000, $29,700 and $2,825 were received 
on February 23, May 10, 1968, October 17, 
1969, January 7, 1970 and October 10, 1970 
respectively. 
Operations and results during fiscal year. 
Non-Federal funds totaling $12,384.50 were 
returned to the State ($9,009.12) and the village 
of Rosendale ($3,375.38). Projecy complete. 
Condition at end of fiscal year. Advance 
engineering and design was started January 
1964 and completed May 18, 1966. Design of 
local cooperation items was completed May 
1968, with revisions in FY 1969 and FY 1970. 
Contruction work by contract was started June 
24, 1968 and was accepted as completed 
January 5, 1971. Operation and Mainteance 
Manual and as-built drawings completed. 
36. SANDBURG CREEK, SPRING 
GLEN, N.Y. 
Location. At Spring Glen, N.Y., about 7 miles 
upstream of the mouth of Sandburg Creek near 
Naponock, N.Y. where it joins with Rondout 
Creek. Sandburg Creek rises in the Town of 
Wawarsing, flows in a southeasterly direction 
for about 12.7 miles to its junction with 
Homowack Kill just below Spring Glen, then 
continues for about 4.8 miles to discharge into 
Rondout Creek. (See U.S. Geological Survey 
quadrangle: Ellenville, N.Y.). 
Existing Project. Improvement includes 
channel excavation and clearing, 2,530 feet of 
levees, 2,325 feet offloodwalls, interior drainage 
facilities and land fill along Sandburg Creek, 
extending for a total distance of about 4,000 feet; 
and about 800 feet of levees and interior 
drainage facilities along Homowack Kill. 
Reconnaissance report was authorized on April 
3, 1962 and completed on February 14, 1963. The 
detailed project report was authorized on 
August 6, 1963, completed on December 21, 1964, 
and revised concerning the reconstruction of 
Old Route 209 bridge, by December 23, 1966. 
Project was authorized for construction by Chief 
of Engineers March 16, 1967. Estimated Federal 
cost of new work is $2,000,000 (October 1975), 
which includes $26,000 for preauthorization 
study reports, exclusive of lands, easements and 
rights-of-way, utility relocations, road raising, 
and reconstruction of bridges, and other pertinent 
work, to be provided by local interests at an 
estimated cost of $57,000. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Local Interets must give 
assurances they will provide all lands, 
easements and rights-of-way, including spoil 
areas necessary for construction; hold the 
United States free from damages; maintain 
completed works; provide for relocation of 
utilities, raising of roads and reconstruction of 
bridges; protect the channel and flood control 
works from future encroachment or obstruction, 
including waste disposal, that would reduce 
their flood carrying capacity. Also agree to take 
appropriate measures to control development in 
fringe areas not protected by the improvement 
with a view to preventing an undue increase in 
the flood damage potential. Provide a pumping 
station or additional gravity outlets, as appropriate, 
to compensate for any loss in ponding 
area effectiveness due to the modification of or 
encroachment upon such area. Agency responsible 
for local cooperation is the State of New 
York. In letter dated November 28, 1966, the 
New York State Department of Public Works 
(now Department of Environmental Conservation) 
stated that the State is prepared to 
participate in the project. Assurances of local 
cooperation were requested from the State 
January 10, and November 7, 1967, March 27, 
October 20, and October 31, 1969. By September 
5, 1969 letter, the State requested that planning 
be continued but construction not be scheduled. 
New York State letter of November 21,1971 said 
2-26

NEW YORK, N.Y., DISTRICT 
definite information regarding providing local 
cooperation could not be furnished. 
Operations and results during fiscal year. 
Local coordination continued. Draft Environmental 
Impact Statement completed. 
Condition at end of fiscal year. Preauthorization 
studies were completed. Detailed Project 
Report was completed on December 21, 1964 and 
approved on September 9, 1965. Design 
engineering was initiated June 1967 and 
resulted in the completion of final plans and 
specifications. Draft Environmental Impact 
Statement completed. Initiation of final Environmental 
Impact Statement awaiting execution 
of agreement of Local Cooperation by New 
York State. Construction of project dependent 
upon fulfillment of local cooperation by State. 
37. SOUTH ELLENVILLE, N.Y. 
Location. In Ellenville, N.Y., on North Gully 
just above its confluence with Sandburg Creek, 
which discharges into Rondout Creek at 
Napanock, N.Y., about 2 miles downstream 
from Ellenville. (See U.S. Geological Survey, 
Ellenville quadrangle; Army Map Service, 
Ellenville quandrangle.) 
Existing project. Includes: a 2,300 foot concrete 
chute, a crib dam to prevent debris from 
entering chute; 380 feet of walls and a stilling 
basin; 823 feet of levees to protect against 
backwater from Sandburg Creek; a ponding 
area, drainage ditches and other interior 
drainage facilities. Physical model study to 
determine design of stilling basin required and 
authorized on August 28, 1970. Existing project, 
also known as "North Gully at Ellenville, N.Y.", 
is one of three physically and functionally 
independent projects included in Rondout Creek 
and Wallkill River, N.Y. and N.J. Survey 
Report. 
Estimated Federal cost for new work is 
$3,770,000 (October 1975), exclusive of lands, 
relocations and other work to be provided by 
local interests at an estimated cost of $360,000. 
(See Table 2B for Authorizing Legislation.) 
Local cooperation. Local interests must, prior 
to construction, give assurances they will 
furnish all lands, easements, and rights-of-way 
necessary for construction of improvements; 
perform all alteration of highways, highway 
bridges, utility and related facilities made 
necessary for construction of project; hold the 
United States free from damages; protect 
channels, ponding areas and other flood works 
from future encroachment or obstruction that 
would reduce their flood carrying capacity and 
control development of fringe areas not 
protected by proposed improvement with a view 
to preventing an undue increase in flood 
damage potential; and maintain and operate 
completed works. Agency responsible for local 
cooperation is State of New York. The Commissioner, 
New York State Department of 
Conservation (now Department of Environmental 
Conservation) executed assurances of local 
cooperation on March 5, 1968 which was 
accepted by the District Engineer for the United 
States on March 25, 1968. To comply with 
Section 221 of the Flood Control Act of 1970 
(PL91-611), the preparation of an agreement of 
Local Cooperation is being initiated to replace 
the signed assurance. Implementation of project 
dependent upon N.Y. State's decision on proposed 
relocation of Route 52 located within project 
area. 
Operations and results during fiscal year. 
Continued coordination with the State of New 
York. 
Condition at end of fiscal year. Preconstruction 
planning was started in January 1967. 
Model study completed in January 1972 and 
final report from Waterways Experiment Station 
received on May 4, 1974. General Design 
Memorandum submitted and returned for 
revisions. Environmental Impact Statement 
submitted to Council on Environmental Quality 
on July 27, 1971. Completion of engineering and 
design and construction remain. 
38. SOUTH ORANGE, N.J. 
Location. Village of South Orange, N.J., 
about 3.5 miles upstream from junction of East 
and West Branches of Rahway River. It is in 
northeastern New Jersey and lies within 
metropolitan area of Greater New York. (See 
N.J. Department of Conservation and 
Economic Development quadrangles and Army 
Map Service quadrangle sheets for South 
Orange, N.J.) 
Existing project. Provides for clearing and 
excavating the East Branch (7,217 feet); constructing 
300 feet of floodwalls, 690 feet of 
levees, 3,324 feet of concrete flume; reconstructing 
five bridges; raising roads; providing 
interior drainage work, and miscellaneous 
utility changes. Estimated Federal cost for new 
work is $4,553,600 (October 1975) exclusive of 
land and other work to be provided by local 
interests at an estimated cost of $2,044,600. (See 
table 2-B for Authorizing Legislation.) 
Local cooperation. It was necessary, under 
project authorization, for local interests to 
provide lands, easements and rights-of-way for 
construction; hold the United States free from 
2-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
damages; maintain and operate completed 
works; make necessary changes to highways, 
highway bridges and approaches, utilities, and 
miscellaneous existing improvements; protect 
channels and other flood control works from 
future encroachment or obstruction that would 
reduce their flood-carrying capacity; and control 
development of the fringe areas not 
protected by the proposed improvement with a 
view to preventing an undue increase in the 
flood damage potential. The Village of South 
Orange, New Jersey is the Local Cooperation 
Agency. Signed assurance of Local Cooperation 
was received from the Village on August 15, 
1969 and accepted by the District Engineer on 
August 25, 1969. First supplemental assurance 
covering items of local work accepted July 6, 
1970. Authority granted to accept contributed 
other funds for Village (December 1969 and 
January 1970) and in June 1971 for Essex 
County, Orange and East Orange. On June 1, 
1970, and November 4, 1970, $40,000 and 
$41,000 respectively were received from the 
Village for non-federal design. During fiscal 
year 1972 the following funds were received. 
$19,000 from the City of Orange, $395,000 from 
the County of Essex, and $57,00 from the City of 
East Orange. During Fiscal Year 1973, $105,000 
was received from County of Essex. 
Operations and results during fiscal year. 
Construction continued. 
Condition at end of fiscal year. Engineering 
and design was started in March 1967 and 
subsequently completed. Submitted General 
Design Memorandum and Post Authorization 
Letter (June 5, 1970). Final plans and 
specifications completed. Environmental Impact 
Statement submitted to Council on Environmental 
Quality on March 31, 1971. Awarded 
construction contract for Federal work and 
options for non-Federal work. Completion of 
construction remains. 
39. STATEN ISLAND, N.Y. 
Location. About 13 miles of coast along 
southern and eastern coast of Staten Island (a 
New York City borough) from Ft. Wadsworth at 
the Narrows to Tottenville at the mouth of 
Arthur Kill along Lower New York and Raritan 
Bays. (See Coast and Geodetic Survey Charts 
and Geological Survey maps for New York and 
vicinity, Staten Island and Sandy Hook Bay 
area.) 
Existing project. Provides shore and 
hurricane protection between Graham and 
Oakwood Beaches and at Tottenville Beach; 
shore protection at Great Kills Park and 
between Arbutus Lake and Sequine Point. 
Improvement includes 2.6 miles of beach fill and 
dunes at Tottenville Beach and between 
Graham and Oakwood Beaches; 2.2 miles of 
beach fill only at Great Kills Park and between 
Arbutus Lake and Sequine Point; 2.9 miles of 
levees at Tottenville Beach, Graham Beach and 
between Oakwood Beach and Great Kills Park; 
two groins at Tottenville Beach and Sequine 
Point; interior drainage facilities including four 
pumping stations between Graham and 
Oakwood Beaches; and relocations. ENGCWEZ 
April 7, 1970 5th Indorsement to NANEN-Br 
September 30, 1969 letter submitting Feasibility 
Study authorized continuing Design Memorandum 
to incorporate extension from Graham 
Beach to Ft. Wadsworth. Total estimated 
Federal Cost is $17,180,000 (October 1975) 
which includes participation in periodic beach 
nourishment for 10 years at $99,000 annually. 
Total estimated non-Federal cost for all requirements 
of local cooperation is $9,810,000 
including $6,480,000 cash contribution, 
$1,860,000 for lands and relocation, $1,470,000 
estimated annual beach nourishment cost for a 
10-year period, and excludes annual nourishment 
costs thereafter and annual maintenance 
and replacement costs. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Local interests must 
provide lands and rights-of-way for construction; 
alter and relocate buildings, streets, storm 
drains, utilities and other structures; bear 34 
percent of total first cost, estimated at $8,340,- 
000 to consist of the two items listed above and a 
cash contriubtion now estimated at $6,480,000 
which excludes $1,470,000 for 10-year nourishment, 
or, if any section is undertaken separately 
the apportionment of first cost will be as shown 
in District Engineer's report, with due regard to 
change in public ownership and other changes 
before construction, provided that cash contribution 
be paid either in a lump sum before 
starting entire project, or in installments before 
starting pertinent items, final apportionment of 
cost to be made after actual costs and values 
have been determined; hold the United States 
free from damages; maintain completed works 
and provide periodic nourishment during 
economic life of the shore protection works 
subject to Federal participation in cost of 
periodic nourishment for an initial period of 10 
years, non-Federal share of such costs for the 10- 
year period is presently estimated at 31 percent 
for Graham Beach to Oakwood Beach reach, 33 
percent for Tottenville Beach reach, 30 percent 
for Great Kills Park reach, and 62 percent for 
Arbutus Lake to Sequine Point reach; maintain 
during economic life of project continued public 
ownership and administration for public use of 
non-Federal publicly owned shores upon which 
2-28

NEW YORK, N.Y., DISTRICT 
recommended Federal participation is based; 
adopt appropriate ordinances to provide for 
preservation of dunes; and control water pollution 
to safeguard the health of bathers. If local 
interests elect to incorporate features in 
highway or other developments in the waterfront 
area which serve the purpose of hurricane 
protection, United States shall participate in 
cost of such features on a basis such that overall 
Federal cost for hurricane protection shall not 
be greater than that which would apply in the 
absence of such features, and such that any 
resultant savings in overall cost of combined 
features shall be shared equitably between the 
United States and local interests on the basis of 
cost allocation and cost apportionment approved 
by the Chief of Engineers, provided that 
such participation in the combined features 
shall be subject to the undertaking of any 
necessary remaining hurricane protection 
works by the United States. New York State 
Department of Public Works in letter dated 
December 1965 stated it was prepared to execute 
assurances when plans are in final form. 
Operation and results during fiscal year. In 
April 1974 local interests furnished their desire 
for the modified plan incorperating a floodwall 
and their intent to support this plan. Preparation 
of Environmental Impact Statement and 
general Design Memorandum is underway and 
is scheduled for completion in 1976. 
Condition at end of fiscal year. Preconstruction 
planning was started in January 1966 and 
is about 99 percent complete. Feasibility Study 
of project extension from Graham Beach to Fort 
Wadsworth was authorized November 16, 1967 
and is complete. Coordination was initiated 
with the National Park Services in connection 
with the Gateway National Recreation Area. In 
April 1974 local interests submitted their formal 
intent to support the modified plan. Preparation 
of Environmental Impact Statement was initiated. 
Completion of the General Design 
Memorandum and EIS for Ft. Wadsworth to 
Great Kills Park is to be scheduled in 1976. 
40. WATERBURY DAM, WINOOSKI 
RIVER BASIN, VT. 
Location. The Winooski River rises in the 
northeastern part of Vermont and flows westerly 
about 90 miles into Lake Champlain, about 4 
miles north of Burlington, Vt. It lies wholly 
within the State and has a drainage area of 
about 1,080 square miles. The Waterbury 
Reservoir with a drainage area of 109 square 
miles is located in the Waterbury River, which 
enters the Winooski River 42 miles above the 
mouth, about 2 miles below Waterbury, Vt. (See 
U.S. Geological Survey map covering Camels 
Hump, Vt., quadrangle.) 
Existing project. For details of dam project see 
Annual Report for Fiscal Year 1972. 
The recreation project was authorized per 
ENGCW-OM January 24, 1968 1st Indorsement 
to NADPL-R November 1,1 967 letter 
subject cost sharing of Recreational Development, 
Waterbury Reservoir, Vermont. Initial 
development would be the vehicular access day 
use area which would include: a family picnic 
area of 120 units, upaved circulation and access 
roads, a parking area for 150 units, a water 
supply and sanitation system, boat launching 
ramps and a bath house. The Estimated Cost for 
the Recreational Facilities is $126,000 of which 
$63,000 are federal funds. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Complied with for original 
project and modification. For details see 1970 
Annual Report. Assurances for the Recreation 
development are being determined during the 
Design Memorandum stage. 
Operation and results during fiscal year. 
Continued coordination and work on master 
plan. 
Condition at end of fiscal year. Construction 
of the existing project was commenced on 
October 19, 1956, was operationally completed 
in September 1958, and was physically completed 
and accepted by local interests on July 14, 
1959. All project new work was completed 
February 27, 1961. Project regulation manual 
completed. Due to lack of funds, the State of 
Vermont withdrew its participation and support 
for the project. 
41. YONKERS, N. Y. 
Location.On Sawmill River in Yonkers, N.Y., 
about 1 mile upstream from junction of Sawmill 
and Hudson Rivers. (See Geological Survey, 
Yonkers quadrangle.) 
Existing project. Project provides for: constructing 
a 24-foot wide concrete flume extending 
3,781 feet along most congested reach of 
the channel; improving channel in other 
reaches (5,689 feet); constructing floodwalls 
(5,370 feet), one closure structure, closure levee, 
various interior drainage facilities; reconstructing 
or raising of nine bridges, and miscellaneous 
utility changes. Estimated Federal 
cost for new work is $9,300,000 (October 1975) 
exclusive of land, relocations and other work to 
be provided by local interests at an estimated 
cost of $2,720,000. (See Table 2-B for Authorizing 
Legislation.) 
2-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Local interests must 
provide lands and rights-of-way for construction, 
including borrow, ponding, and wastedisposal 
areas; hold the United States free from 
damages; maintain and operate completed 
works; provide all alterations, relocations, and 
necessary replacements of existing facilities, 
including bridges, highways, sewers, including 
those storm sewers and drains required to 
convey interior drainage to improved channels 
or ponding areas, utilities, and railroad 
modifications and relocations other than 
bridges and bridge approaches; protect the 
channel and other flood works from future 
encroachment or obstruction, including waste 
disposal, which would reduce or otherwise 
impair their flood-carrying capacity, or provide 
a pumping station or additional gravity outlets, 
as appropriate, to compensate for any loss in 
ponding area effectiveness due to modification 
of or encroachment upon such areas; take 
appropriate measures to control development in 
partially protected areas and fringe areas not 
included in the project with a view toward 
preventing an undue increase in the flood 
damage potential; and at least annually, notify 
those affected that flooding will still be possible 
from large floods. New York State is the Local 
Cooperating Agency. An agreement of Local 
Cooperation was signed by the Commissioner of 
the New York State Department of Environmental 
Conservation on April 9, 1974, and signed by 
the New York District Engineer on April 30, 
1974 for the United States and approved by the 
Secretary of the Army on May 17, 1974. The city 
of Yonkers, through the State, furnished $93,000 
(contributed, "other") for non-Federal design 
costs. 
Operations and results during fiscal year. 
Construction of Initial Increment of project 
(contract #1) involving one-third mile of the 
uppermost reach of the project area is continuing. 
Preconstruction planning, including 
the development of the Phase II General Design 
Memorandum, is continuing, Local Coordination 
continuing. 
Condition at end of fiscal year. Started 
preconstruction planning December 1970. 
Phase I General Design Memorandum completed 
on October 1, 1973 and approved on April 
19,1974. Phase II General Design Memorandum 
is 85 percent complete. Agreement of Local 
Cooperation executed with New York State. 
Final Environmental Impact Statement in 
Federal Register on May 13, 1974. Initial plans 
and specifications for contract No. 1 completed 
and construction contract for this increment 
awarded August 30, 1974. Construction of 
contract #1 is 50 percent complete. Planning and 
construction for remaining increment of project 
(Contract #2) remains. 
42. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspections of completed flood control works 
are performed semi-annually to determine the 
extent of compliance by local interests with the 
requirements of operation and maintenance. 
43. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 2-I at end of chapter.) 
44. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood Control Activities pursuant to Section 
205, Public Law 858, 80th Congress as amended 
(Preauthorization) 
Fiscal year costs for preauthorization studies 
to complete reconnaissance reports were: $5,000 
on East Branch, Rahway River, South Orange, 
N.J. $5,000 on East Branch, Rahway River, 
Millburn, N.J., $5,000 on Fulmer Creek, Village 
of Mohawk, N.Y., $5,000 on Fulton Brook, White 
Plains, N.Y.,$5,000 on Missisquoi River, Vt.,- 
$30.49 on Third River Basin, N.J., $5,000 on 
Wappingers Creek, Manchester, N.Y. Costs to 
continue reconnaissance reports were: $1,067.45 
on Mohawk River, Glenville, N.Y., $5,290.46 on 
Whitesboro, N.Y., $21,159.86 on Pinebrook, 
Manalapan, N.J. Costs to continue Detailed 
Project Reports were:$25,708.14 on Byram 
River, Greenwich, Conn., Portchester N.Y., 
$10,903.22 on Cuckholds Brook, Bridgewater 
N.J., $58,123.86 on Lamoille River, Harwick, 
Vt.,$30,880.50 on Patroon Creek, Albany, N.Y.,- 
$21,362.34 on Ramapo River, Suffern, N.Y., 
$23,628.68 on Rondout Creek, Accord, N.Y., 
$18,762.87 on Saranac River, Plattsburg, N.Y., 
$14,021.77 on Yonkers, Nepera Park, N.Y. 
Work on plans and specifications was completed 
for Esopus Creek, Kingston, N.Y. and 
continued on Chappaqua, (Saw Mill River), N.Y. 
Fiscal year costs were $1,154.46 for Esopus 
Creek and $62,998.78 for Chappaqua. Construction 
was completed on Nine Mile Creek (Holland 
Patent), N.Y. with fiscal years costs of $124,- 
025.81. 
Emergency flood control activities-repair, 
flood fighting and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
2-30

NEW YORK, N.Y., DISTRICT 
Under "Advance Preparation": The following 
work was accomplished: Supplements A, B and 
C were revised and distributed. New York 
District pamphlet "Guidelines for Repair and 
Restoration Activities under PL 93-288" was 
published and distributed. Emergency Operation 
Planner attended many preliminary 
meetings of Metropolitan Regional Council on 
planning of closed circuit TV natural disaster 
seminar and attended TV presentation in 
January 1975. Emergency Operation Planner 
attended Federal Disaster Assistance critique in 
Nov 74; also attended hearing in Wash, D.C. in 
connection with Ft. Edward court case. Four 
New York District technical personnel attended 
Emergency Operation Center Course in Cincinnati 
in Oct 74 and the Emergency Operation 
Planner and 2 engineers attended Federal 
Disaster Assistance briefing in July 74 regarding 
provisions of PL 93-288. Emergency 
Operation Planner also attended Baltimore 
District flood emergency exercises in Sept. 74 
and March 1975. New York District participated 
in Exercise PRIME RATE 74 and held in-house 
refresher course in Radiological recovery 
operations in March 75. Emergency Operation 
Planner attended Defense Civil Preparedness 
Agency seminar in New York City 3-4 April 75; 
also attended seminar on Federal-State natural 
disaster procedures and operations sponsored 
by Defense Civil Preparedness Agency and New 
York University on Apr 29 75 at Yonkers, N.Y. 
Emergency Operation Planner also attended 
N.Y. City Civil Defense seminar at Kiamesha 
Lake, N.Y. on May 28, 75. New York District's 
new Emergency Operations Center was furnished 
and made operational this fiscal year. 
New York District flood emergency exercise was 
held June 26, 75 at Winooski River Basin, 
Waterbury, Vt. 
Under "Emergency Operations": The District 
Emergency Operation Center opoerated during 
storms and other emergencies. During the fiscal 
year 25,000 sandbags were distributed to 
various State and local communities. During 
the winter season personnel were on the alert for 
ice jam conditions in Vermont areas; however, 
critical situations eased. In April 1975, one New 
York District engineer was sent on Temporary 
Duty to Vicksburg, Miss. for one month and two 
New York District engineers on Temporary 
Duty to New Orleans District for two weeks in 
connection with Mississippi River flooding. 
were requested and received for removal of 
additional shoaling and correction action needed 
on ponding problem. 
Disaster Assistance Administration: Work 
accomplished under PL 93-288. 
New York State Major Disaster (Jul 73): 
Status work accomplished in the four counties 
within New York District boundaries (Kingston, 
N.Y. Field Office) as of June 30, 1975: 
No. of initial inspections 
completed: 54 
Est. final total funds 
recommended by 
New York District: $929,000 
Final inspections required: 35 
Final inspections completed: 35 
New Jersey Major Disaster (Aug 73): Status of 
work accomplished in four counties in 
northeastern New Jersey (Plainfield, N.J. 
Office) as of June 30, 1975: 
No. of initial inspections 
completed: 
Est. final total funds 
recommended by 
New York District: 
Final inspections required: 
Final inspections completed: 
52 
$2,336,000 
56 
56 
Central New York (Mohawk Valley) Major 
Disaster (Jul 74): Status of work accomplished 
in four counties in central New York (Utica, N.Y. 
Office) as of June 30, 1975: 
Number of initial 
inspections completed: 44 
Est. final total funds 
recommended by 
New York District: $567,681 
Final inspections required: 44 
Final inspections completed: 40 
45. SURVEYS 
(See Table 2-J at end of chapter.) 
46. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs of $414,928 for flood plain 
management services are set forth in Table 2-L 
at end of chapter. (See also Table 2-K on 
completed flood plain studies.) 
2-31

TABLE 2-A 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
FY 72 FY 73 FY 74 FY 75 
See 
Section 
in Text Projects Funding 
1. Aquatic Plant New Work 
Control Approp. 
Cost 
2. Bay Ridge & Red New Work 
Hook Channels, N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
3. Browns Creek, New Work 
N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
4. East Chester New Work 
Creek, N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. East River, N.Y. New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
6. East Rockaway New Work 
Inlet, N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
7. Hudson River, N.Y. New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
8. Hudson River New Work 
Channel, N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
9. Jones Inlet, N.Y. New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
10. Lake Montauk New Work 
Harbor, N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
11. Long Island New Work 
Intracoastal Approp. 
Waterway, N.Y. Cost 
Maint. 
Approp. 
Cost 
(Required New Work 
Contributed Funds) Contrib. 
Cost 
20,000 
23,773 
50,502 
50,620 
-30,000 
17,783 
4,000 
20,251 
514,985 
513,959 
428 
428 
1,955 
1,955 
59,600 
11,765 
80,633 
89,708 
3,400 
748 
900,517 
640,310 
1,244,403 
1,244,403 
467,814 
449,275 
118,538 
82,223 
182,519 
182,519 
9f 
9, 
50,000 
39,459 
296,186 
296,186 
9,302 
9,302 
282,756 
243,888 
130,000 
113,110 
22,769 
22,769 
171,587 
171,587 
2,590 62 
79,600 871,703 
)7,328 1,137,262 
50,371 368,700 
50,371 368,700 
56,778 377,328 
)9,086 543,558 
-882 3,074 
35,432 3,074 
- 571,456 
- 394,306 
39,000 
31,594 
389,400 
389,400 
105,860 
104,112 
-9,731 
29,137 
2,500,000 
2,148,628 
1,487 
1,487 
248,738 
248,738 
25,000 
920 
793,184 
734,276 
892,500 
892,500 
400,458 
400,458 
111,222 
7,002 
2,543 
179,693 
Total Cost to 
June 30, 1975 
220,0001 
182,1272 
5,523,2973 
5,523,2973 
8,921,712 
8,921,712 
33,9764 
33,9764 
307,327 
305,579 
592,0564, 5 
592,0564,5 
754,2384 
754,2384 
32,750,7457,8 
32,382,4837,8 
1,471,7698 
1,471,7698 
503,9699 
503,9699 
1,978,212 
1,978,212 
44,186,69310,11 
44,162,61310,11 
19,011,13312,1:1 
18,915,73312,13 
6,771,87014 
6,771,87014 
17,086,107 
17,086,107 
1,822,53015 
1,822,53015 
3,678,375 
3,678,375 
791,68016 
791,68016 
641,709 
537,489 
235,964 
235,964 
2,059,872 
2,059,872 
9,182 
9,182 
2-32 
)1,820 
)3,283

NEW YORK, N. Y., DISTRICT 
TABLE 2-A (Continued)COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Projects Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
12. Mattituck Harbor, New Work 
N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
13. Moriches Inlet, New Work 
N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
14. Narrows of Lake New Work 
Champlain, N.Y. Approp. 
Cost 
Maint. 
Approp. 
Cost 
15. Newark Bay, New Work 
Hackensack & Approp. 
Passaic Rivers, Cost 
N.J. 
Maint. 
Approp. 
Cost 
16. New York and New New Work 
Jersey Channels Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
17. New York Harbor- New Work 
Collection and Approp. 
Removal and Drift Cost 
Maint. 
Approp. 
Cost 
Maint. & Oper. 
Approp. 
Cost 
18. New York Harbor- New Work 
Entrance Channels Approp. 
and Anchorage Cost 
Areas Maint. 
Approp. 
Cost 
19. Raitan River, New Work 
N.J. Approp. 
Cost 
Maint. 
Approp. 
Cost 
20. Shrewsbury New Work 
River, N.J. Approp. 
Cost 
Maint. 
Approp. 
Cost 
21. Supervisor of New Maint. 
York Harbor Approp. 
Cost 
9,170 
9,170 
7,368 
- 18,873 396,262 
- 18,873 368,965 
-55,000 55,000 - 
8,364 14,835 10,485 
- - 7,955 
- - 7,955 
10,600 - 8,240 
21,626 - 8,240 
4,070,500 4,855,038 -50,000 
2,898,609 4,658,917 1,253,461 
15,549 
15,549 
5,590 
20,413 
177,92517 
177,92517 
725,084 
697,787 
470,000 
437,898 
9,422 
9,422 
681,81118 
681,81118 
722,27419,20 
722,27419,20 
23,909,51021,22 
23,866,86821,22 
291,386 500,021 1,217,945 -5,424 10,471,6992: 
342,182 35,195 1,670,025 7,496 10,471,69923 
- 22,903 - - 
- 22,862 - - 
1,828,685 1,703,101 990,547 878,262 
1,765,959 1,773,848 26,464 1,843,662 
- - 80,000 330,000 
- - - 130,992 
931,700 1,257,500 1,355,000 1,602,000 
894,816 1,043,741 1,518,753 1,670,390 
4,587,900 4,981,500 4,500,000 3,770,000 
2,467,717 6,369,538 4,468,271 3,870,520 
1,439,447 657,836 1,293,064 2,268,359 
863,923 1,273,913 1,325,811 1,246,459 
211,996 409,084 -13,200 2,155,495 
82,224 268,633 346,304 225,352 
-132,000 -4,000 4,000 - 
1,616 - -501 5,334 
4,165 - - - 
30,411 - - - 
660,900 614,000 - 900,000 
660,542 613,768 - 900,241 
73,052,43524,25,26 
73,052,43524,25,26 
17,680,73927 
17,685,21527 
454,773 
454,773 
410,000 
130,992 
20,565,92228 
20,515,92228 
997,81328 
997,81328 
41,484,19029 
40,800,49629 
15,978,416 
14,953,516 
1,551,47030,31 
1,551,47030,31 
9,590,77032 
7,660,62732 
1,145,45733,34 
1,145,32933,34 
1,522,36535 
1,522,36535 
20,581,047 
20,579,975 
2-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 2-A (Continued) COST AND FINANCIAL STATEMENT 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
12,900 10,000 285,000 4,000,000 
2,600 4,700 252,043 1,828,280 
- - - 4,360,000 
- - - 1,901,346 
-58,200 765,200 - 2,125,000 
6,143 61,664 822,678 2,070,553 
See 
Section 
in Text Projects Funding 
25. East Rockaway Inlet New Work 
to Rockaway Inlet Approp. 
and Jamaica Bay, Cost 
N.Y. (Part I) 
(Required New Work 
Contributed Funds) Contrib. 
Cost 
26. Fire Island Inlet, New Work 
to Jones Inlet, Approp. 
N.Y. Cost 
Maint. 
Approp. 
Cost 
(Required New Work 
Contributed Funds) Contrib. 
Cost 
29. East Rockaway Inlet New Work 
to Rockaway Inlet Approp. 
& Jamaica Bay, N.Y. Cost 
(Part II) 
30. Elizabeth, N.J. New York 
Approp. 
Cost 
(Other Contributed New Work 
Funds) Approp. 
Cost 
31. Fire Island Inlet New Work 
to Montauk Point, Approp. 
N.Y. (Federal Cost 
Funds) Maint. 
Approp. 
Cost 
(Required New Work 
Contributed Funds) Contrib. 
Cost 
32. North Ellenville, New Work 
N.Y. Approp. 
Cost 
(Other Contributed New Work 
Funds) Approp. 
Cost 
33. Rahway South New Work 
Branch, N.J. Approp. 
(Regular Funds) Cost 
Other Contributed New Work 
Funds) Approp. 
Cost 
34. Raritan Bay & New Work 
Sandy Hook Bay, Approp. 
N.J. Cost 
(Regular Funds) Maint. 
Approp. 
Cost 
(Required New Work 
Contributed Funds) Contrib. 
Cost 
35. Rosendale, N.Y. New Work 
(Regular Funds) Approp. 
Cost 
(Other Contributed New Work 
Funds) Contrib. 
Cost 
36. Sandburg Creek, New Work 
Spring Glen, N.Y. Approp. 
Cost 
37. South Ellenville, New Work 
N.Y. Approp. 
Cost 
1,200,000 - 1,420,000 
- 829,826 1,502,440 
127,000 90,000 75,000 
64,066 145,417 167,124 
1,258,400 1,536,000 495,400 2,055,( 
922,169 1,026,639 1,085,113 1,195, 
- 290,000 - 
- 98,533 138,578 43,( 
-- 190,600 -671,700 - 306, 
11,019 45,593 178,870 243, 
-.-.- 
10,476 
49,700 
1,111,839 
12,933 
794,400 
6,101 
2,081,400 
1,965,876 
820,000 
787,447 
4,302 
2,199 
49,700 
27,097 
38,735 -106,672 53, 
2,200,000 51,600 
1,947,170 308,444 16, 
8,585 30,700 
72,683 115,711 9, 
- - -365, 
6,645 27,842 30, 
- _ 
139,000 90,000 48, 
296,146 33,504 134, 
46,400 63,009 
95,790 9,807 53, 
45,000 -7,000 
5,500 32,607 
7,000
7 
4,274 
12, 
1, 
612 
3,785 
5,173 
4,360,000 
2,155,323 
4,360,000 
1,901,346 
6,578,767 
6,151,671 
18,298 
18,298 
2,620,000 
2,332,266 
1,185,700 
1,093,378 
000 7,139,800 
154 5,095,305 
- 290,000 
000 280,111 
690 4,707,158 
424 4,567,990 
- 13,97336 
- 13.97336 
- 4,012,930 
461 3,596,975 
- 3,751,300 
432 3,751,173 
- 226,685 
297 215,532 
000 486,300 
028 126,077 
- 27,500 
- 27,443 
900 7,792,800 
582 7,753,411 
- 262 
- 262 
- 3,291,384 
448 3,267,697 
- 3,685,590 
-- 3,684,966 
- 182,373 
384 182,373 
- 111,000 
947 109,702 
- 299,700 
80 278,585 
2-34 
175,800 
35,679

NEW YORK, N. Y., DISTRICT 
TABLE 2-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Projects Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
38. South Orange N.J. New Work 
(Regular Funds) Approp. 743,900 780,000 2,500,000 800,000 5,058,900 
Cost 67,866 1,553,073 2,098,662 762,401 4,619,963 
(Other Contributed New Work 
Funds) Approp. 1,471,000 319,000 - - 1,780,000 
Cost 40,309 459,515 794,404 355,545 1,629,773 
39. Staten Island, N.Y. New Work 
Approp. - - - 25,000 595,000 
Cost 23 - - 11,129 580,771 
40. Waterbury Dam, New Work 
Winooski River Approp. -- 12,200 - - 39,000 917,269 
Basin, Vt. Cost 3,487 5,198 - 2,421 880,690 
Maint. 
Approp. - - - - 8,200 
Cost - - - - 8,200 
41. Yonkers, N.Y. New Work 
Approp. 69,900 95,000 250,000 815,000 1,264,900 
Cost 70,867 26,496 103,194 750,404 973,692 
(Other Contributed New Work 
Funds) Approp. - - 93,000 - 93,000 
Cost - - - 20,423 20,423 
1. Of which $12,500 is for North Atlantic Division 
accounts. 
2. Of which $12,127 is for North Atlantic Division 
accounts. 
3. Includes $1,246,100 for new work for previous 
projects and $64,560 extended from public works funds. 
4. Excludes $71,423 for rehabilitation. 
5. Costs for previous project only. 
6. Includes $183,507 for new work expended from 
emergency relief funds. Excludes $14,403 for new work 
expended from contributed funds for previous projects. 
7. Includes $6,187,694 for new work for previous projects.
8. Includes $37,664 for maintenance for previous projects.
9. Excludes $100,000 for new work expended from 
contributed funds and includes $82,600 for new work 
expended from public works funds. 
10. Includes $5,112,594 for new work for previous 
project. 
11. Includes $238,350 for new work expended from 
public works funds and $31,461 emergency relief funds. 
Excludes $81,373 expended from contributed funds, other. 
12. Excludes $454,273 expended between August 18 
1915 and June 30, 1935, for operation and care of lock and 
dam at Troy, N.Y., under permanent indefinite appropriation. 
Excludes $23,735 reimbursement for repairs to Troy 
Lock. 
13. Includes $346,797 for maintenance for previous 
project. 
14. Includes $69,629 for new work for previous projects 
and $668 820 expended from public works funds. 
15. Excludes $1,822,530 for new work expended from 
contributed funds. 
16. Excludes $104,805 for new work expended from 
contributed funds. 
17. Excludes $34,580 for new work expended from 
contributed funds. 
18. Includes $115,000 for new work for previous projects. 
19. Includes $19,140 for maintenance for previous 
projects. 
20. Includes $31,166 for U.S. Lake Survey Revisory and 
Inshore Sounding Program. 
21. Includes $1,836,403 for new work for previous 
projects. 
22. Excludes $285,600 for new work expended from 
contributed funds. 
23. Includes $1,490,713 for maintenance for previous 
projects. 
24. Includes $12,809,975 for new work for previous 
projects, and $6,621 for new work for Lemon Creek, Staten 
Island, N.Y. 
25. Excludes $7,712 for new work expended from 
contributed funds. 
26. Includes $807,000 for new work expended from 
public works funds and $2,023,308 for new work expended 
from emergency relief funds. 
27. Includes $1,160,380 for maintenance for previous 
project, and $1,621 for maintenance for Lemon Creek, 
Staten Island, N.Y. 
28. Includes $2,491,206 expended to date for construction 
of a land-based overfire air pit incinerator ($1,493,393 in 
maintenance funds and $997,813 in O&M funds.) 
29. Includes $116,530 applied to removing wrecks 
authorized by acts prior to adoption of existing project. 
30. Includes $673,155 for new work for previous project. 
31. Excludes $292,685 for new work expended from 
Ordinance funds and $66,000 for new work expended from 
contributed funds. 
32. Includes $111,419 for maintenance for previous 
projects. 
33. Includes $220,894 for new work for previous projects.
34. Excludes $36,311 for new work expended from 
contributed funds. 
35. Includes $286,606 for maintenance for previous 
projects. 
36. For pilot program to improve coastal storm warnings. 
2-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 2-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
River and Harbor 
Act of 1958 
Section 104 River 
and Harbor Act of 
1958 
Section 302 River and 
Harbor act of 1965 
Mar. 3, 1899 
Mar. 2, 1907 
July 3, 1930 
Sept. 19, 1890 
May 17, 1950 
Mar. 2, 19152 
July 27, 1916 
Aug. 8, 1917 
Do. 
ACQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and Progressive eradication of obnoxious 
Acquatic Plant growths. 
Provided that all research and Planning cost to 
be borne fully by the United States. 
Modified project to include control of 
waterchestnut. 
BAY RIDGE AND RED HOOK CHANNELS, N.Y. 
(See Section 2 of Text) 
Channel 40 feet deep and 1,200 feet wide. 
Dredging to obtain first a depth of 35 feet, subsequently 
increasing depth of 40 feet for full width. 
Widening of Bay Ridge Channel to 1,780 feet. 
BROWNS CREEK, N.Y. (See Section 3 of Text) 
6 foot channel for 1,850 feet and 4 feet 
for 1,350 feet, and construct 2 jetties. 
EAST CHESTER CREEK, N.Y. (See Section 4 of Text) 
Channel 10 feet deep and 150 to 70 feet wide. 
EAST RIVER, N.Y. (See Section 5 of Text) 
Removal of Coenties Reef to 35 feet, conditioned upon local H. D 
interests increasing depth to 40 feet. ses 
Channel across Diamond Reef 35 feet deep and 1,000 feet Do. 
wide. 
Channel east of Blackwells Island to 20 feet; channel between Do. 
South Brother and Berrian Islands, to 20 feet; channel 
between North and South Brother Islands to 26 feet. 
Channel 40 feet deep through East River and Hell Gate. H. E 
July 18, 1918 Secure a depth of 40 feet in channel through East River and 
Hell Gate as soon as practicable. 
Sept. 22, 1922 Depth limited to 35 feet in through channel between 
Wallabout Channel and Throgs Neck. Channel east of 
Blackwells Island, 30 feet to English P1. and eliminated 
20-foot channel north of English P1. Eliminated 
channel between North and South Brother Islands except as 
authorized prior to existing projeot. Remove certain rocks 
and reefs and construct dike in pot cove, Hell Gate. 
E. Pub. Wks. Comm. Res., Spur channel to Astoria waterfront 37 feet in rock, 35 feet 
Dec. 15, 1970 and S. Pub. Wks. in other material, for a length of 0.95 mile for varying 
Comm. Res. Dec. 17, 19703 widths, and a turning basin. (South Brother Island 
Channel). 
H. Doc 37 85th Cong., 
1st sess. 
H. Doc. 337,54th cong., 2d 
sess. (Annual Report 1899, 
p. 1177). 
Rivers and Harbors Committee 
Doc. 44, 71st Cong., 
2d sess.' 
H. Ex. Doc. 22,51st cong. 
1st sess. 
H. Doc. 749, 80th Cong., 
2d sess. 
)oc. 188, 63d Cong., 1st 
S. 
)oc. 140, 65th Cong., 1st 
s. 
cified in act. 
ers and Harbors Committee 
c. 3, 67th Cong., 2d sess.i 
)oc. 91-60, 91st Cong., 
sess. 
ses 
Spec 
Riv 
Doi 
S.D 
2d 
EAST ROCKAWAY INLET, N.Y. (See Section 6 of Text) 
Channel 12 feet deep and 250 feet wide, and a jetty. H. Doc. 19, 71st Cong., 
1st sess. 
Straightening channel at Johnson Iron Works. Annual Report, 1912, p. 198 
H. Doc. 557, 62d Cong., 2d 
sess. (contains latest 
published maps). 
HUDSON RIVER, N.Y. (See SECTION 7 OF Text) 
Channel 12 feet deep from Hudson to Waterford, remove 
State lock and dam at Troy and construct a new 
lock and dam.4 
Channel 27 feet deep from Hudson to Albany, N.Y. 
Channel 27 feet deep below Hudson. 
H. Doc. 719, 61st Cong., 
2d sess.i 
H. Doc. 350, 68th Cong., 
1st sess.x 
H. Doc. 210, 70th Cong., 
1st sess.i 
2-36 
July 3, 1930 
Mar. 4, 1913 
June 25, 1910 
Mar. 3, 1925 
July 3, 1930

NEW YORK, N. Y., DISTRICT 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Operation and care of lock and dam at Troy were included 
in project July 1, 1935. 
Relocation of 12-foot channel between Troy and Waterford. S. Doc. 155, 72d Cong., 
2d sess.' 
Deepen channel between Albany and Waterford to 14 feet H. Doc. 572, 75th Cong., 
with no change in depths for harbors in front of 3d sess.' 
Albany and Troy. 
Deepen channel between New York City and Albany to 32 
feet and construct a turning basin and 2 anchorages. 
Mooring facilities. 
H. Doc. 228, 83d Cong., 
1st sess.' 
Aug. 30, 19356 
June 20, 1938 
Sept. 3, 1954 
P.L. 89-72 
Mar. 4, 1913 
Mar. 4, 1915 
Aug. 8, 1917 
Mar. 3, 1925 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 19357 
Aug. 30, 19357 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
JONES INLET, N.Y. (See Section 9 of Text) 
Construction of jetty and channel 12 feet deep and 250 feet 
wide. 
HUDSON RIVER CHANNEL, N.Y. (See Section 8 of Text) 
Channel 30 feet deep from Ellis Island to Newark St., 40 feet H. Doc. 719, 62d Cong., 
deep through shoal from Newark St. to Castle Point and 2d sess. 
channel 26 by 550 feet along Weehawken-Edgewater 
waterfront. Remove shoal east side of river between 
West 19th and West 32d Sts.; remove rock near Battery 
to 40 feet; remove obstruction near Spuyten Duyvil 
Creek. 
Additional dredging through shoal from Newark St. to Annual Report 1914, pp 
Castle Point. 234-235 
Remove shoal between West 32d and West 61st Sts. to 40 H. Doc. 1697, 64th Cong 
feet and widen 40-foot channel between the Battery and 2d sess. 
Canal St. to 2,000 feet. 
Channel 30 by 750 feet along Weehawken-Edgewater H. Doc. 313, 68th Cong., 
waterfront. 1st sess. 
Modification of conditions of local cooperation affecting 
channel along Weehawken-Edgewater waterfront. 
Channel 40 feet deep between pierhead lines from 20th St., H. Doc. 450, 70th Cong., 
Manhattan, to a point 1,300 feet below Newark St. 2d sess. 
Hoboken thence 2,800 feet wide to deep water off Illis 
Island. Channel 30 feet deep between 40-foot channel 
and channel along Jersey City waterfront. 
Widen 40-foot channel to full width of river from north H. Doc. 309, 72d Cong., 
line of 59th St. to south side of Little Basin, thence 1st sess. 
a channel of same depth to deep water off Ellis Island. 
Waiver all conditions of local cooperation affecting Rivers and Harbors Con 
channel along Weehawken-Edgewater waterfront. Doc. 49, 72d Cong., 2d 
Channel 45 and 48 feet deep and 2,000 feet wide. Senate committee print, 
Cong., 1st sess.' 
H. Doc. 409. 77th Cong., 
1st sess.' 
LAKE MONTAUK HARBOR, N.Y. (See Section 10 of Text) 
Channel 12 feet deep and 150 feet wide, 10 foot boat basin; H. Doc. 369, 76th Cong. 
repair and extension of two jetties; and addition of 1st Sess.' 
sport fishing facilities on top of jetties. 
LONG ISLAND INTRACOASTAL WATERWAY, N.Y. 
(See Section 11 of Text) 
Channel 6 feet deep and 100 feet wide. 
MATTITUCK HARBOR, N.Y. (See Section 12 of Text) 
Dredging 7 foot channel and 2 riprap jetties. 
250-foot extension of west jetty. 
Dredging anchorage area and deepening channel at 
upper end. 
MORICHES INLET, N.Y. (See Section 13 of Text) 
Channel 10 feet deep and 200 feet wide. 
H. Doc. 181, 75th Cong., 
1st sess. 
Annual Report 1891, p 843. 
H. Doc. 8, 71st Cong., 
1st Sess.' 
Chief of Engineers 
pursuant to Sec. 107, 
Public Law 86-645. 
H. Doc. 126, 86th Cong., 
Ist sess,i 
2-37 
5 
nmittee 
sess. 
75th 
Aug. 26, 1937 
June 3, 1896 
Aug. 30, 1935 
Aug. 11, 1964 
July 14, 1960 
).

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 8, 1917 
Mar. 2, 1907 
Feb. 27, 1911 
July 25, 1912 
Jan. 21, 1927 
July 3, 1930 
Mar. 2, 1945 
Mar. 2, 1945 
Sept. 3, 1954 
Oct. 23, 1962 
Nov. 7, 1966 
Sept. 6, 19339 
Aug. 30, 1935 
May 28, 193510 
May 17, 1950 
Oct. 27, 1965 
Mar. 4, 1915 
Aug. 8, 1917 
July 3, 1930 
Dec. 31, 1970 
Mar. 7, 1974 
NARROWS OF LAKE CHAMPLAIN, N.Y. and 
VERMONT. (See Section 14 of Text) 
Channel 12 feet deep and 150 feet wide. H. Doc. 1387, 62nd Cong., 
3d sess. 
NEWARK BAY, HACKENSACK AND PASSAIC 
RIVERS, N.J. (See Section 15 of Text) 
16-foot channel in Passaic River. H. Doc. 441, 59th Cong., 
2d sess. 
Widening 16-foot channel in Passaic River. H. Doc. 441,59th Cong., 
2d sess. 
20-foot channel in Passaic River.a H. Doc. 707, 62d Cong., 
2d sess. 
10-foot channel in Passaic River. H. Doc. 284, 69th Cong., 
2d sess. 
30-foot channel in Passaic River. H. Doc. 156, 71st Cong., 
2d sess.' 
35 and 37 feet in main channel of Newark Bay and branch S. Doc. 250, 79th Cong., 
channel to and inshore channel at Port Newark Terminal 2d sess. 
and remove portion of rock area at Bergen Point to same 
depths. 
Modification of local cooperation for 10-foot channel in H. Doc. 430, 76th Cong., 
Passaic River. 1st sess. 
34- and 32-foot channel in Hackensack River including H. Doc. 252, 82d Cong., 
approach channel in Newark Bay from branch channel at 1st sess. I 
Port Newark Terminal and a 25-foot turning basin. 
35-foot channels at Port Elizabeth. H. Doc. 289, 88th cong., 
2d sess. 
Widening 35-foot channel in Newark Bay, provision of two H. Doc. 494, 89th Cong., 
maneuvering areas, widening entrance into Port Elizabeth 2d sess.' 
and Port Newark branch channels, deepening and widening 
Newark Bay 32-foot channel, and provision of a turning 
basin at junction of Hackensack and Passaic Rivers; and 
deepening 12-foot channel in Hackensack River to 15 feet. 
Additional widening at junction with Report on file in the 
Kill Van Kull by deepening to 35 feet a office of the Chief of 
triangular area at the eastern end of the Engineers. 
30 foot channel south of Shooters Island. 
NEW YORK AND NEW JERSEY CHANNELS 
(See Section 16 of Text) 
Anchorage off Perth Amboy to 35 feet. Rivers and Harbors Committee 
Doc. 17, 71st Cong., 2d 
sess. 
Channel 35 feet deep from lower bay to upper bay except H. Doc. 133, 74th Cong., 
between vicinity of Smith Creek and vicinity of Piles 1st sess. 
Creek to 30 feet with anchorages 38 feet deep at Sandy 
Hook and Perth Amboy. 
Channel 35 feet deep from vicinity of Smith Creek to vicinity H. Doc. 233, 81st Cong., 
of Piles Creek. 1st sess. 
Widen entrance to Kill Van Kull to 1,400 feet narrowing to H. Doc. 108, 89th Cong., 
a minimum width of 1,000 feet. 1st sess. 
NEW YORK HARBOR, COLLECTION AND REMOVAL 
OF DRIFT (See Section 17 of Text) 
Allotment from appropriations made for New York Harbor and 
its immediate tributaries may be used for collection 
and removal of drift in these waterways. 
Carrying on this work as a separate and distinct project. 
Increases scope of project to include removal and disposal P.L. 91-611,91st Cong., 
of derelict vessels, some deterioriated shore structures, H. R. 19877. 
and debris along shores; and the repair of other shore 
structures; all subject to approval by Secretary of the 
Army and the President. 
Removal and disposal of derelict vessels, some deteriorated P.L. 93-251,93rd Cong., 
shore structures and debris along shores and H.R. 10203 
the repair of other shore structures. 
2-38

NEW YORK, N. Y., DISTRICT 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 5, 1884 
Mar. 3, 1899 
June 25, 1910 
Aug. 8, 1917 
Aug. 8, 1917 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
July 3, 1958 
Oct. 27, 1965 
Mar. 2, 1919 
July 3, 1930 
July 3, 1930 
July 3, 1930 
Aug. 26, 1937 
Oct. 17, 1940 
Oct. 23, 1962 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 30, 1935 
May 17, 1950 
Oct. 27, 1965 
2-39 
NEW YORK HARBOR-ENTRANCE CHANNELS AND 
ANCHORAGE AREAS (See Section 18 of Text) 
Main Ship-Bayside-Gedney to 30 feet for width of 1,000 feet Annual Reports 1887, p. 6 2 
(dimensions fixed by Secretary of War, Dec. 27, 1886, by and 1888, p. 6 3 
authority of act of Aug. 5, 1886). 
Ambrose Channel (East Channel) to 40 feet. H. Doc. 159, 55th Cong., 
3d sess. (Annual Report 
1899, p. 1279). 
Maintenance of entrance channel under 1 head. 
Anchorage Channel, extension of Ambrose Channel into H. Doc. 518, 63d Cong., 
Upper Bay. 2d sess. 
Removal of Craven Shoal. H. Doc. 557, 64th cong., 
1st sess. 
Channel between Staten Island and Hoffman and H. Doc. 625, 64th Cong., 
Swinburne Islands 1st sess. 
Relocation of southerly section of Anchorage Channel. Rivers and Harbors Committee 
Doc. 18, 71st Cong., 
2d sess. 
Dredging south end of Red Hook Flats, Liberty Island H. Doc. 183, 73d Cong., 
Anchorage, and channel along New Jersey pierhead line. 2d sess.1 
Deepend Bayside-Gedney Channel to 35 feet for a width H. Doc. 133, 74th Cong., 
of 800 feet. 1st sess.1 
Deepen Ambrose and Anchorage Channels to 45 feet for Senate committee print, 75th 
a width of 2,000 feet. Cong., 1st sess.' 
Dredging South Channel. Elimination of portion of S. Doc. 45, 84th Cong., 
Bayside-Gedney Channel. 1st sess. 
Deepen and expand Red Hook Flats Anchorage. Deepen S. Doc. 17, 89th Cong., 
Gravesend Bay Anchorage. 1st sess. 
RARITAN RIVER, N.J. (See Section 19 of Text) 
Channel 15 deep and 200 feet wide to Washington H. Doc. 1341, 62d Cong., 
Canal, thence 10 feet deep and 150 feet wide to canal 3d sess. 
locks and 10 feet deep through south channel. 
Channel 25 feet deep and 300 feet wide up to New York and H. Doc. 127, 70th Cong., 
Long Branch R. R. bridge. 1st sess. 
Channel 10 feet deep in earth and 11 feet in rock to New H. Doc. 454, 70th Cong., 
Brunswick. Width reduced to 100 feet. 2d sess.' 
Relocation of lower reach of south channel." Rivers and Harbors Committee 
Doc. 31, 71st Cong., 
2d sess.' 
Channel 25 feet deep and 300 feet wide to junction of main Rivers and Harbors Committee 
and south channels, thence of same depth on south Doc. 74, 74th Cong., 
channel to Titanium Pigment Co. 2d sess.' 
Channel 25 feet deep and 300 feet wide from junction of Report on file in the Office, 
main and south channels to government wharf, including Chief of Engineers (report 
a turning basin, not printed.) 
In south channel, maintenance of 15-foot channel to dock H. Doc. 455, 86th Cong., 
of Middlesex County Sewerage Authority. 2d sess.' 
SHREWSBURY RIVER, N.J. (See Section 20 of Text) 
Channel 6 feet in North Branch. H. Doc. 1296, 62d Cong., 
3d sess. 
Channel 12 feet deep. H. Doc. 157, 71st Cong., 
2d sess. 
Channel 9 feet deep. Rivers and Harbors Committee 
Doc. 31, 74th Cong., 
1st sess. 
Turning basin and anchorage 6 feet deep at Red Bank, and H. Doc. 285, 81st Cong., 
channels 6 feet deep in Claypit, Oceanport, and Little 1st sess. 
Silver Creeks. 
Ocean channel 15 feet deep 200 feet wide protected by H. Doc. 274, 89th cong., 
two parallel jetties and bulkheads; bay channel 9 feet 1st sess.' 
deep, 200 feet wide; 6-lane fixed highway bridge 
spanning new inlet.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
1965 Flood Control Act 
1974 Water Resources 
Development Act 
1958 River and Harbor Act 
1962 River and Harbor Act 
1965 Flood Control Act 
1974 Water Resources 
Development Act 
1965 Flood Control Act 
1960 River and Harbor Act 
1974 Water Resources 
Development Act 
1962 Flood Control Act 
Section 205 P. L. 858 
80th Cong. as amended 
1962 Flood Control Act 
1962 Flood Control Act 
Section 205 P.L. 858, 80th 
Cong. as amended 
1962 Flood Control Act 
1965 Flood Control Act 
EAST ROCKAWAY INLET TO ROCKAWAY INLET AND 
JAMAICA BAY, N.Y. (PART I). (See Section 25 
of Text) 
Hurricane barrier, dikes, levees, floodwalls, fill H. Doc. 215, 89th cong., 
placement, stoplog structures, stairways, ramps, 1st sess.i 
road raising, fishing platforms, annual nourishment. 
Authorized beach erosion control aspect to be constructed 
independent of the hurricane flood protection aspect of 
the project. 
FIRE ISLAND INLET TO JONES INLET, N.Y. 
(See Section 26 of Text) 
Three dredging operations with sand serving as H. Doc. 411, 84th Cong., 
nourishment to the beaches westerly of the inlet. 2d sess. 1 
Extension of existing jetty, a littoral reservoir, a H. Doc. 115, 89th Cong., 
navigation channel and dikes, sand deposit on westerly 1st sess. 
beaches. 
EAST ROCKAWAY INLET TO ROCKAWAY INLET AND 
JAMAICA BAY, N.Y. (PART II) (See Section 29 of Text) 
Hurricane barrier, dikes, levees, floodwalls, fill placement, H. Doc. 215, 89th cong., 
stoplog structures, stairways, ramps, road raising, fishing 1st sess.i 
platforms, annual nourishment. 
Authorized beach erosion control aspect to be constructed 
independent of the Hurricane flood protection 
aspect of the project. 
ELIZABETH, N.J. (See Section 30 of Text) 
Channel improvement, flume, levees, floodwalls, bridges, Doc. 249, 89th cong., 
interior drainage facilities. 1st sess. 
FIRE ISLAND INLET TO MONTAUK POINT, N.Y. 
(See Section 31 of Text) 
Raising dunes, widening beaches, interior drainage H. Doc. 425, 86th Cong., 
structures, groins, beach replenishment, annual 2d sess. 
nourishment. 
Project modified to provide that non-Federal P.L. 93-251, 93rd Cong., 
interest shall contribute 30 percent of the H.R. 10203 
first costs. 
NORTH ELLENVILLE, N.Y. (See Section 32 of Text) 
Levees and floodwalls, removing concrete dam, stream S. Doc. 113, 87th Cong., 
diversion, interior drainage structures. 2d sess.i 
RAHWAY (S. BRANCH), N.J. (See Section 33 of Text) 
Channel improvements, fill placement, bridge replacement 
and interior drainage structures. 
RARITAN BAY AND SANDY HOOK BAY, N.J. 
(See Section 34 of Text) 
Levees and floodwalls, interior drainage structures, groins, 
beachfill. 
ROSENDALE, N.Y. (See Section 35 of Text) 
Levees and floodwalls, interior drainage structures, 
culverts, a pumping station and channel improvements. 
H. Doc. 464, 87th Cobg., 
2d sess.1 
S. Doc. 113, 87th Cong., 
2d sess. 1 
SANDBURG CREEK, SPRING GLEN, N.Y. (See Section 
36 of Text) 
Channel improvements, levees and floodwalls, interior 
drainage structures. 
SOUTH ELLENVILLE, N.Y. (See Section 37 of Text) 
Levees, drainage ditches, walls, a concrete chute 
and a crib dam. 
SOUTH ORANGE, N.J. (See Section 38 of Text) 
Levees and floodwalls, a concrete flume, raising roads, 
drainage facilities, bridge reconstruction. 
S. Doc. 113, 87th Cong., 
2d sess.1 
H. Doc. 67, 89th Cong., 
1st sess.i 
2-40

NEW YORK, N.Y., DISTRICT 
TABLE 2-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
STATEN ISLAND, N.Y. (See Section 39 of Text) 
1965 Flood Control Act Beachfill, groins, drainage facilities, four pumping stations. H. Doc. 181, 89th Cong., 
1st sees.' 
WATERBURY DAM, WINOOSKI RIVER BASIN, Vt. (See 
Section 40 of Text) 
Flood Control Act of Modify existing dam by: increasing height by 3 feet, H. Doc. 629, 78th Cong., 
Dec. 22, 1944 adding an extra gate. 2d sess. 1 
P.L. 89-72 Recreational facilities including parking, mooring areas, 
a public wharf, sanitary facilities. 
YONKERS, N.Y. (See Section 41 of Text) 
1965 Flood Control Act Channel improvement, concrete flume, floodwalls, closure H. Doc. 258, 89th cong., 
structure, various drainage facilities, reconstruct or 1st sess.' 
raise nine bridges. 
1. Contains latest published maps. 7. Also Public Works Administration Sept. 6, 1933, and 
2. Public Resolution 67, 63d Congress 3d session. April 27, 1935. 
3. Authorized under Section 201, Flood Control Act 8. Portion from 3,000 feet above Lincoln Highway 
1965, (Public Law 89-298, 89th Congress, October 27, 1965). Bridge to Jackson Street Bridge complete. From Jackson 
4. Widening to form harbors at Albany and Troy to 12 Street Bridge to Nairn Linoleum Works considered inactive. 
feet deep considered inactive. 9. Public Works Administration. 
5. Permanent Appropriations Repeal Act of June 26, 10. Emergency Relief Act of 1935. 
1934. 11. Upper 1,300 feet of South Channel, 10 feet deep and 
6. Public Works Administration, Sept. 6, 1933. 150 feet wide considered inactive. 
2-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 2-C HUDSON RIVER, N.Y. 
FEATURES OF LOCK AND DAM INCLUDED IN EXISTING PROJECT 
(See Section 7 of Text) 
Location: 
Below Waterford 
Above Battery, New York City 
Locks: 
Clear Width 
Greatest length available for full width 
Lift at lowest stages 
Depth on miter sills; 
Upper (at normal pool level) 
Lower (at lowest low water) 
Character of foundation: Rock 
Kind of dam: Fixed 
Type of construction: Concrete 
Completed: 1917 
Cost: $1,463,014 
2.2 miles 
153.8 miles 
44.44 feet 
492.5 feet 
17.3 feet 
16.3 feet 
13.0 feet 
TABLE 2-D TOTAL COSTS FOR EXISTING PROJECT TO JUNE 30, 1975 
Operation 
See Section Rehabili- Mainte- and 
of Text Project Funds New Work tation nance Cost Total 
7. Hudson River, Regular $38,500,208 - $10,401,742 $8,166,594 $57,068,544 
New York Public Works 238,350 - - - 238,350 
Emergency 
Relief 311,461 - - - 311,461 
Total $39,050,019 - $10,401,742 $8,166,594 $57,681,355 
16. New York and Regular 57,412,152 $454,773 $16,524,835 - $74,391,760 
New Jersey Public Works 807,000 - - - 807,000 
Channels Emergency 
Relief 2,023,308 - - - 2,023,308 
Contributed 7,712 - - - 7,712 
Total $60,250,172 $454,773 $16,524,835 - $77,229,780 
2-42

NEW YORK, N.Y., DISTRICT 
TABLE 2-E SUPERVISOR OF NEW YORK HARBOR 
(SEE SECTION 21 OF TEXT) 
STATEMENT OF ACTIVITIES-FY 1975 
1. Number of Patrols: 
a. Shore 1,679 
b. Vessel 1,109 
c. Air 18 
Total 2,806 
2. Number of Inspections: 
a. Shore Facilities 9,031 
b. Vessels 5,587 
Total 14,618 
3. Number of Investigations: 
a. Illegal Deposit of Refuse 103 
b. Illegal construction 146 
c. Interference (Vessels) With Navigation 26 
Total Number of Cases 275 
Supplemental Investigations 95 
Total Number of Investigations 370 
4. Disposition of Cases: 
a. Unfounded Complaints 58 
b. Unknown Violators 12 
c. Violations Corrected 69 
d. Corrective Action in Progress 82 
e. Referred to U. S. Attorneys 54 
Total Number of Cases 275 
5. Number of Warning Letters Issued 175 
6. Fines Imposed-U.S. District Courts $25,250 
7. Status of Cases Referred to U.S. 
Attorneys for Legal Proceedings: 
a. Number pendingprior to 1 July 1973 309 
b. Number referred during Fiscal Year 1975 +54 
c. Number closed in Fiscal Year 1975 -311 
Total Number Pending 1 July 1975 52 
2-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 2-F RECONNAISSANCE AND CONDITION SURVEYS FY 75 
Name of Project Date Survey Conducted' 
NEW JERSEY 
Cheesequake Creek........ ................. .................... 
Newark Bay, Hackensack and Passaic Rivers .................. 
Raritan River................ ......................... 
Sandy Hook Bay at Leonardo................ .............. 
Sandy Hook Bay ........ ........ ............................... 
Shoal Harbor and Compton Creek... ............ ......... 
W aycake Creek......... ...... .................................. 
NEW YORK 
B ronx R iver.......... .... ...................................... 
Brow ns C reek ......... ...... ................................... 
Coney Island Channel....... ........ ........................... 
East Chester Creek............. ........................ 
East River ............................................ 
Flushing Bay and Creek.. ............. ................... 
Glen Cove Creek ................................... 
Gowanus Creek Channel .............. ................ 
Great South Bay ................................... 
Harlem River .......................................... 
Hempstead Harbor ............. ........................ 
Hudson River....... ..................................... 
Jamaica Bay ........................................... 
Jones Inlet........................................... 
Lake Montauk Harbor............... 
Long Island Intracoastal Waterway............................. 
Mattituck Harbor .................................. 
M ilton H arbor, N.Y ........ ....... .............................. 
Moriches Inlet....... .................................. 
New Rochelle Harbor.............. ................... 
Newtown Creek ........................................ 
New York Harbor......... ............................. 
Sag Harbor.................................... ................. 
Sheepshead B ay ........ .............. ......................... 
NEW YORK & VERMONT 
Narrows of Lake Champlain .................................. 
-
- 
May 1975 
April 1975 
November 1974 
December 1974 
May 1975 
July 1974 
February 1975 
1Items for which no date is furnished reflects costs for gathering data only. 
2-44 
- 
January 1975 
August 1974

NEW YORK, N.Y., DISTRICT 
TABLE 2-G OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to 30 June, 1975 
Full report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Bronx River, N.Y. 1973 1,149,946 1,129,027 
Burlington Harbor, Vt.' 1966 706,4149 283,556 
Buttermilk Channel, N.Y.' 1972 4,590,201 3,082,773 
Channel between North and South Hero 1909 31,000 1,288 
Island, Lake Champlain, Vt.1,2 
Cheesequake Creek, N.J. (Active)1,2,5 1953 40,000 30,675 
Coney Island Inlet, N.Y. 1973 111,371 284,109 
Coney Island Creek, N.Y. (Active)',5 1952 69,489 6,203 
Echo Bay Harbor, N.Y.' 1953 64,584 11,571" 
Elizabeth River, N.J. (Inactive)2 ,3 1953 60,4814 59,5344 
Fire Island Inlet, N.Y. 1973 594,355 2,908,786 
Flushing Bay and Creek, N.Y.' 1974 2,102,9056,7 727,7646 
Glen Cove Creek, N.Y. (Active)" 5 1966 29,76012 1&0,593 
Glen Cove Harbor, N.Y. (Active)1,5 1966 72,000' 2,455 
Gordons Landing, Lake Champlain, Vt.12 1892 34,750 115 
Gowanus Creek Channel, N.Y.' 1972 346,831 255,291 
Great Chazy River, N.Y.1,2 1895 18,000 13,328 
Great Kills Harbor, N.Y.1,2 1962 137,301'4 88,029 
Great Lakes to Hudson River Waterway, N.Y. 1971 33,456,99710 457 
Great South Bay, N.Y.' 1974 266,857 1,290,469 
Greenport Harbor, N.Y.' 1953 74,681 21,720 
Harlem River, N.Y.' 1969 3,616,119 480,777 
Hempstead Harbor, N.Y. 1969 39,468 76,49715' 
Huntington Harbor, N.Y. (Active)', 5 1953 71,53516 60,535 
Irvington Harbor, N.Y. (Inactive)3 1948 - 1,188 
Jamaica Bay, N.Y.' 1964 4,545,753 278,29517 
Keyport Harbor, N.J.' 1968 40,475 215,951 
Larchmont Harbor, N.Y. 1970 76,065 267,768 
Lemon Creek, N.Y. (Inactive)2 ,3 1937 6,62118 1,621 
Little Neck Bay, N.Y.' 1969 1,741,21019 537 
Mamaroneck Harbor, N.Y.' 1967 339,72020 304,93921 
Manhasset Bay, N.Y. (Inactive)3 1948 - 4,636 
Matawan Creek, N.J. (Active)2 ,5 1968 21,000 165,341 
Milton Harbor, N.Y.' 1968 151,3732: 16,482 
New Rochelle Harbor, N.Y.1,2 1971 73,2148 142,411 
Newtown Creek, N.Y. (Active)',5 1974 1,168,354 1,626,35122 
Northport Harbor, N.Y.' 1956 78,64424 1,487 
Orowoc Creek, N.Y. (Inactive)3 1949 - 4,951 
Otter Creek, Vt. (Active)1,2 1967 60,254 19,152 
Peconic River, N.Y.' 1953 25,000 116,509 
Peekskill Harbor, N.Y.' 1951 19,400 66,037 
Plattsburgh Harbor, N.Y.' 1972 198,415 229,111 
Portchester Harbor, N.Y. (Active)",5 1967 433,470 443,79525 
Port Henry Harbor, N.Y.' 1931 69,40626 1,299 
Port Jefferson Harbor, N.Y. 1974 221,00532 20,64632 
Rahway River, N.J. (To Be Restudied)3 1949 37,0004 5734 
Raritan River to Arthur Kill Cutoff Channel, 1972 810,500 2,019,141 
N.J.' 
Rondout Harbor, N.Y.' 1972 142,437 260,441 
Rouses Point, Lake Champlain, N.Y.' 1895 98,468 249 
Sag Harbor, N.Y.' 1964 121,80527 11,710 
St. Albans Harbor, Lake Champlain, Vt.x,2 1917 3,125 385 
Sandy Hook Bay, N.J.' 1957 508,93628 154,565 
Sandy Hook Bay at Leonardo, N.J., 2 1967 56,470 93,964 
Saugerties Harbor, N.Y.1,2 1968 81,905 169,18129 
2-45

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 2-G(Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to 30 June, 1975 
Full report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Shark River, N.J.1,2 1971 150,000 475,496 
Sheepshead Bay, N.Y.1 1948 33,828 5,364 
Shinnecock Inlet, N.Y. 1961 - 22 
Shoal Harbor and Compton Creek, N.J.1 1972 124,572 768,347 
Staten Island Rapid Transit Railway Co. 1973 7,730,476 - 
bridge across Arthur Kill, N.Y. 
Sumpawanus (Babylon Creek) Inlet, N.Y.1,2 1895 7,000 13 
Swanton Harbor, Vt. (Inactive)2 1888 70,500 235 
Tarrytown Harbor, N.Y. 1 1974 69,836 431,199 
Ticonderoga River, N.Y. (Inactive)2 1895 16,500 1,260 
Wallabout Channel, N.Y.1 1953 18,174 36,312 
Wappinger Creek, N.Y.1, 2 1950 13,000 44,691 
Washington Canal and South River, N.J.' 1953 206,1163� 212,82731 
Waycake Creek, N.J.2 ,3 1949 - 2,781 
Westchester Creek, N.Y. (Active)1 , 1974 175,93333 1,637,31134 
Woodbridge Creek, N.J.' 1953 49,823 178,398 
1. Completed. 
2. No commerce reported. 
3. Awaiting local cooperation. 
4. Costs for previous projects only. 
5. A portion of this project is classified "inactive." 
6. Includes $628,502 for new work and $210,365 for 
maintenance for previous projects. 
7. Excludes $419 879 for new work expended from 
contributed funds and $58,425 contributed funds other and 
$8,752 expended by the Worlds Fair Corp. for riprap 
protection of rubble dike. 
8. Includes $43,175 for new work for previous projects. 
9. Includes costs of maintenance prior to July 1, 1886. 
Excludes $1,425,133 for rehabilitation. 
10. Includes $4,813,400 for new work expended from 
emergency relief funds. 
11. Includes $10 for maintenance for previous projects. 
12. Excludes $29,774 for new work expended from 
contributed funds. 
13. Excludes $94,366 for rehabilitation. 
14. Excludes $104,805 for new work expended from 
contributed funds. 
15. Includes $64,034 for maintenance for previous 
projects. 
16. Excludes $19,546 for new work expended from 
contributed funds and $31,454 to be contributed. 
17. Includes $2,961 for maintenance for previous projects.
18. This amount also included in costs for New York 
and New Jersey channels. No work has been done on the 
existing project for Lemon Creek. 
19. Excludes $1,741,210 for new work expended from 
contributed funds. 
20. Excludes $151,044 for new work expended from 
contributed funds. In addition, excludes $43,023 for new 
work and $5,502 for maintenance, expended from contributed 
funds, other. 
21. Includes $13,415 for maintenance for previous 
projects. 
22. Includes $1,490,713 for maintenance for previous 
projects. 
23. Excludes $119,276 for new work expended from 
contributed funds. In addition excludes $72,619 for new 
work expended from contributed funds, other. 
24. Excludes $15,000 for new work expended from 
contributed funds. 
25. Includes $16,369 for maintenance for previous 
projects. 
26. Excludes $10,000 for new work expended from 
contributed funds. 
27. Excludes $66,758 for rehabilitation. 
28. Excludes $53,790 for new work expended from 
contributed funds. 
29. Includes $15,000 for maintenance for previous 
projects. 
30. Excludes $365 for new work expended from contributed 
funds. 
31. Includes $84,934 for maintenance for previous 
projects. 
32. Includes costs for new work $171,427 and 
maintenance $20,646 for previous projects. 
33. Includes $77,182 for new work for previous projects. 
34. Includes $66,000 for maintenance for previous 
projects. 
2-46

NEW YORK, N.Y., DISTRICT 
TABLE 2-H OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Cost to 30 June, 1975 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Atlantic Coast of N.J., Sandy Hook to 1959 
Barnegat Inlets' 
Perth Amboy, N.J. 1966 
TABLE 2-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to 30 June, 1975 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Adams, Hoosic River Basin, Mass.1 1964 6,282,3072 
Bennington, Vt. 1974 670,000 - 
Byram River at Pemberwick, Conn."1, 1959 363,515 - 
East Barre Dam, Winooski River, Vt.' 1963 2,832,084 - 
Herkimer, N.Y. 1973 1,301,2759 - 
Hoosic Falls, Hoosic River Basin, N.Y.1 1956 1,064,626 - 
Lamoille River, Vt.: 
Hardwick Dams,4,5 1939 - - 
Johnson Gorges' 1939 49,8376 
Mississquoi River at Richford, Vt.,' 1965 221,476 - 
North Adams, Hoosic River Basin, Mass. 1968 15,409,3257- 
Proctor, Otter Creek Basin, Vt. 4,5 1937 -- 
Rahway, N.J. 1971 973,1428 - 
Rome, Mohawk River, N.Y.4 1959 - - 
Rutland, Otter Creek, Vt.4 1963 211,015 - 
South Amsterdam, Mohawk River, N.Y.1 1967 1,564,976 - 
Wappinger Creek at Pleasant Valley, N.Y. 1,' 1959 142,075 - 
Waterbury, Winooski, River Basin, Vt. 4 1951 - 
Waterford, Hudson and Mohawk Rivers, N.Y.4 1940 - - 
Winooski River, Vt.' 1940 5,897,427 - 
Wrightsville Dam, Winooski River Basin, Vt. 1970 1,549,929 - 
1. Completed. 
2. Excludes costs of $913,360 under other contributed 
funds. 
3. Authorized by Chief of Engineers phrsuant to sec. 
205, Public Law 858, 80th Cong., as amended. 
4. Inactive. 
5. Not desired by local interests. 
6. Includes $23,507 emergency relief funds. 
7. Excludes costs of $2,718,624 under other contributed 
funds. 
8. Excludes cost of $21,000 under other contributed 
funds. 
.9. Excludes cost of $51,500 under other contributed 
funds. 
2-47

TABLE 2-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
SURVEYS 
(See Section 45 of Text) 
Study Class 
Navigation Studies 
Flood Control Studies 
Beach Erosion Studies 
Special Studies' 
Total Surveys 
$ 84,460 
382,945 
386 
1,705,792 
$2,173,583 
'Includes review of Authorized Projects, Inventory of Dams, Coordination Studies with Other Agencys, International 
Water Studies and $1,568,805 by North Atlantic Division. 
TABLE 2-K FLOOD CONTROL STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 46 of Text) 
Location Requesting Agency Dated Completed Federal cost 
Herkimer-Ilion, N.Y. Division of Water Resources July 2, 1974 $35,017 
(Mohawk R., FulmerCr. State of New York 
Steele Cr.) 
North Haven, Suffolk Division of Water Resources, Dec 27, 1974 13,700 
County, N.Y. State of New York 
Utica-Whitesboro- Division of Water Resources April 1, 1975 63,421 
Oriskany, N.Y. State of New York 
(Mohawk R., Sauquoit 
Cr., Oriskany Cr.) 
Bolton, Winooski R., Vt. Department of Water Resources, April 9, 1975 19,300 
State of Vermont 
Bennington, Walloomsac R., Department of Water Resources April 10, 1975 38,400 
South Stream, Roaring Br., Vt. State of Vermont 
2-48 
Fiscal Year Cost

NEW YORK, N. Y., DISTRICT 
TABLE 2-L COSTS FOR FLOOD PLAIN MANAGEMENT SERVICES 
(See Section 46 of Text) 
Studies and Services Fiscal Year Costs 
Ambrose Broox, Middlesex Piscataway-Edison, N.J. $1,670 
Bennington Vt., Walloomsac River-Roaring Branch 2,894 
Bolton Vt., Winooski River 2,045 
Essex-Williston Vt., Winooski River 1,774 
Guides Pamphlets-Supporting Studies 15,446 
Ilion-Utica, N.Y. Mohawk River 1,319 
Linden-Carteret, N.J., Rahway River 2,320 
Montgomery Township, Orange County, N.Y., Wallkill River 17,035 
North Haven-Suffolk County, N.Y. Great Peconic Bay 2,275 
Oriskany, Rome, N.Y., Mohawk River 9,358 
Poughkeepsie, N.Y., Wappinger Creek 38,474 
Rahway River, N.J., Rahway, Clark, Cranford 9,425 
Rahway River, N.J., Nomahegan Creek, Van Winkle Brook 9,274 
Robinson's Branch, Pumpkin Patch Brook-A-B-C, N.J. 31,611 
South Branch, Rahway River, N.J. 14,388 
Town of Berlin, Vt., Dog River 20,600 
Town of Northfield, Vt., Dog River 14,614 
Town of Colchester-Milton, Vt., Lamoille River 29,400 
Utica-Whitesboro, N.Y., Mohawk River 1,850 
Wallkill-Hamptonburg Township, Orange County, N.Y., Wallkill River 1,100 
Flood Plain Technical Services 62,900 
Flood Plain Management Unit 75,156 
Flood Plain Management Unit-North Atlantic Division Office 50,000 
Total $414,928 
2-49

PHILADELPHIA, PA., DISTRICT* 
This district comprises a portion of southeastern 
New York, eastern Pennsylvania, western 
and southern New Jersey, northern and southeastern 
Delaware, and a small part of northeastern 
Maryland embraced in the drainage 
basins tributary to the Atlantic Ocean from 
Manasquan River, N.J., inclusive, to south 
boundary of Delaware. It also includes Chesapeake 
and Delaware Canal and approach channel 
thereto in Chesapeake Bay and Elk River, Md. 
IMPROVEMENTS 
Navigation Page 
1. Absecon Inlet, N. J.... ........ .3-2 
2. Aquatic Plant Control ............ 3-2 
3. Barnegat Inlet, N. J............. 3-3 
4. Broadkill River, Del............. 3-3 
5. Cohansey River, N. J............ 3-3 
6. Cold Spring Inlet, N. J........... 3-4 
7. Delaware Bay - Chesapeake Bay 
Waterway in Del., Md., and Va. .... 3-4 
8. Delaware River at Camden, N. J ..... 3-4 
9. Delaware River between 
Philadelphia, Pa., and Trenton, N.J... 3-5 
10. Delaware River, Pa., N.J. and Del. 
Philadelphia to the Sea .......... 3-6 
11. Indian River Inlet and Bay, Del. .... 3-7 
12. Inland Waterway, Rehoboth Bay to 
Delaware Bay, Del.............. 3-7 
13. Inland Waterway from Chincoteague 
Bay, Va., to Delaware Bay, Del. .... 3-8 
14. Inland Waterway from Delaware 
River to Chesapeake Bay, Del., and Md. 3-8 
15. Little River, Del. .............. 3-9 
16. Manasquan River, N.J............ 3-10 
17. Murderkill River, Del............ 3-10 
18. Neshaminy State Park Harbor, Pa.... 3-11 
19. New Jersey Inlets and Beaches - 
Corson Inlet and Ludlam Beach .... 3-11 
20. New Jersey Inlets and Beaches - Great 
Egg Harbor Inlet and Peck Beach . . . 3-11 
21. New Jersey Intracoastal Waterway . . 3-12 
22. Schuylkill River, Pa. ............ 3-13 
23. Wilmington Harbor, Del.......... 3-13 
24. Reconnaissance and Condition 
Surveys .................... 3-14 
25. Other Authorized Navigation 
Projects ................... 3-14 
26. Navigation Work Under Special 
Authorization ................ 3-14 
Beach Erosion Control Page 
27. Other Authorized Beach Erosion 
Control Projects .............. 3-14 
28. Beach Erosion Control Work 
Under Special Authorization ...... 3-14 
Flood Control 
29. Beltzville Lake, Pa.............. 3-14 
30. Blue Marsh Lake, Pa............ 3-15 
31. Delaware Coast Protection, Del..... 3-15 
32. Francis E. Walter Dam, Pa ....... 3-15 
33. General Edgar Jadwin Dam and 
Reservoir, Pa.................. 3-16 
34. Prompton Lake, Pa.............. 3-16 
35. Trexler Lake, Pa . ............. 3-17 
36. Inspection of Completed Flood 
Control Projects ................ 3-17 
37. Other Authorized Flood Control 
Projects .................... 3-18 
38. Flood Control Work Under 
Special Authorization .......... 3-18 
Multiple-Purpose Projects Including Power 
39. Tocks Island Lake, Pa., 
N.J., and N.Y................. 3-18 
General Investigations 
40. Surveys .................... 3-18 
41. Collection and Study of Basic Data .. 3-18 
*All costs and financial statement for projects are listed at the end of this chapter. All other tables are referenced in 
text and also appear at the end of this chapter. 
3-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
NAVIGATION 
1. ABSECON INLET, N. J. 
Location. On New Jersey coast about 65 miles 
north of Delaware breakwater, between Brigantine 
Beach on the north and Absecon Beach on 
the south. It forms entrance to harbor at 
Atlantic City, N. J. (See U.S. Coast and 
Geodetic Survey Charts 826 and 1217.) 
Previous project. For details see Annual Report 
for 1936, page 319. 
Existing project. This provides for an inlet entrance 
channel 20 feet deep at mean low water 
and 400 feet wide, for an entrance channel 15 
feet deep and 200 feet wide from the inlet channel 
into Clam Creek, and for a turning basin 15 
feet deep within Clam Creek. The act authorizing 
the inlet entrance channel also provides that 
should the channel at any time have a deleterious 
effect on the Atlantic City Beach, work 
upon the improvements may cease; it being 
understood that the project is adopted on the 
basis that the interests of the beach in front of 
the city are superior to those of the inlet. The 
total length of the section included in the project 
is about 1.5 miles. The extreme tidal range, 
due to ocean storms, is about 11 feet. 
The cost for the completed project was 
$307,712. (See Table 3-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Fully compiled with except 
that local interests are required to furnish 
suitable spoil-disposal areas for maintenance 
when and as required for the dredging of the 
entrance channel into Clam Creek and the turning 
basin within Clam Creek. 
Terminal facilities. See pages 239 and 240 of 
Annual Report for 1962. 
Operations and results during fiscal year. Maintenance, 
hired labor: U.S. Hopper Dredge HYDE 
commenced dredging 27 March 1975 and completed 
the work on 2 May 1975. A total of 71,039 
cubic yards of material was removed at a cost of 
$219,127. Sidecasting Dredge FRY performed 
dredging from 13 August 1974 to 5 September 
1974, removing 13,511 cubic yards of material at 
a cost of $37,063; and from 12 December 1974 to 
5 January 1975, removing 19,527 cubic yards of 
mqterial at a cost of $52,230. Costs of $21,526 
were incurred for surveys and miscellaneous engineering 
and administration. 
Condition at end of fiscal year. Project was 
completed May 1957. Inlet channel was completed 
in 1938. Dredging entrance from inlet 
channel into Clam Creek was completed in 
1957. 
Costs for existing project were $307,712 for 
new work and $4,880,020 for maintenance, a 
total of $5,187,742. 
2. AQUATIC PLANT CONTROL 
Location. Includes those waters within geographic 
limits of Philadelphia District excessively 
infested with sea lettuce, eel grass, Eurasian 
water milfoil, filomentous algae or other obnoxious 
aquatic plant growth. 
Existing Project. A comprehensive program to 
provide for control and progressive eradication 
of sea lettuce, eel grass, Eurasian water milfoil, 
filomentous algae and other obnoxious aquatic 
plant growths from the navigable waters, tributary 
streams, connecting channels and other 
allied waters in the Philadelphia District in the 
combined interest of navigation, flood control, 
drainage, agriculture, fish and wildlife conservation, 
public health and related purposes including 
continued study for the most effective 
and economic control measures in cooperation 
with other Federal and State agencies. Cost to 
the Federal Government is estimated at 
$257,000 (July 1968). Cost to local interest, 
$89,000 (July 1968). Project was authorized by 
River and Harbor Act of 1965. Section 104 of 
Public Law 89-298, 89th Congress, 1st Session. 
Local Cooperation. Local interests shall agree 
to hold and save the United States free from 
claims that may occur from control operations 
and to participate to the extent of 30 percent of 
the cost of such operation. Cost for research and 
planning before construction shall be borne fully 
by the Federal Government. Planning has identified 
the problem areas and District personnel 
have met or corresponded with Federal, State 
and local groups and individuals. The Department 
of Forests and Waters of the Commonwealth 
of Pennsylvania has signified its willingness 
to cooperate. Representatives of New 
Jersey State agencies have informally indicated 
that the required cost sharing could be accomplished 
and have signified they will assist in any 
way possible. They are also cognizant of the 70 
percent-30 percent cost-share provisions. 
Operations and results during fiscal year. Costs 
of $147 were incurred for cooperation with 
other agencies and State officials of New Jersey 
and Pennsylvania. 
Condition at end of fiscal year. General Design 
Memorandum for the Commonwealth of Pennsylvania 
completed December 1969, and memorandum 
for the State of New Jersey submitted 
for approval April 1970. After review, Design 
Memorandum was returned with comments. 
Completion of the memorandum and submission 
for final approval are dependent upon the State 
3-2

PHILADELPHIA, PA., DISTRICT 
of New Jersey. Several meetings have been 
scheduled and each time, the State of New 
Jersey has asked for a postponement. Planning 
with the States of New Jersey and Pennsylvania 
continuing. 
Costs for the existing project total $82,052. 
3. BARNEGAT INLET, N. J. 
Location. On east coast of New Jersey about 
50 miles south of Sandy Hook, between Island 
Beach on the north and Long Beach on the 
south (See U. S. Coast and Geodetic Chart Nos. 
825 and 1216). This inlet is main entrance to 
Barnegat Bay, largest of the bays on New Jersey 
coast which are separated from the ocean by 
narrow barrier beaches. 
Existing project. Provides for a channel 8 feet 
deep through inlet and 10 feet through outer 
bar, channel to be protected by two converging 
stone jetties extending to 12-foot contour in the 
ocean and spaced 1,000 feet apart at outer ends; 
a channel of suitable hydraulic characteristics 
extending in a northwesterly direction from 
gorge in inlet to Oyster Creek Channel just 
northwest of Sunset Shoal, thence via Oyster 
Creek Channel to deep water in the bay; and 
maintenance of a channel 8 feet deep and 200 
feet wide to connect Barnegat City Harbor with 
main inlet channel. Total length of section included 
in project is about 4.5 miles. Plane of 
reference is mean low water. Extreme tidal range 
at inlet is from about 2 feet below mean low 
water to about 3 feet above mean high water. 
Cost for new work for completed project was 
$448,849 exclusive of $300,000 contributed by 
local interests. (See Table 3-B at end of chapter 
for Acts authorizing existing projects.) 
Local Cooperation. Fully complied with. 
Terminal facilities. There are four docks or terminals 
in inner harbor at Barnegat Light which 
furnish adequate facilities for present commerce 
of locality. 
Operations and results during fiscal year. Maintenance, 
contract: Work on contract for second 
increment for alteration of north jetty was 
completed in September 1974 at a total cost of 
$1,464,298. Costs for Environmental Impact 
Statement were $2,410. 
Maintenance, hired labor: Sidecasting Dredge 
FRY performed dredging from 2 July 1974 to 13 
August 1974, removing 11,822 cubic yards of material 
at a cost of $61,280; and from 7 February 
1975 to 16 March 1975, removing 29,150 cubic 
yards of material at a cost of $68,738. Miscellaneous 
engineering and administrative costs were 
$58,627. 
Condition at end of fiscal year. Project was 
completed in 1940. (For details, see page 203, 
Annual Report for 1964.) 
Cost under existing projects, excluding 
$300,000 contributed funds expended for new 
work, were $448,849 for new work and 
$5,943,295 for maintenance, a total of 
$6,392,144. 
4. BROADKILL RIVER, DEL. 
Location. Rises in Sussex County, Del., flows 
northeasterly 13 miles, and empties into Delaware 
Bay about 5 miles above Cape Henlopen. 
(See U. S. Coast and Geodetic Survey Chart 
1218.) 
Existing project. A channel 6 feet deep at 
mean low water with a least width of 40 feet 
from the junction of Broadkill River and Inland 
Waterway between Rehoboth Bay and Delaware 
Bay, upstream to Milton. Total length of the 
project is 10.25 miles. Mean range of tide is 4.1 
feet at the mouth and 3.5 feet at Milton. Cost 
for new work for completed project was 
$68,228. Project was further modified by Public 
Law 78, 83d Congress, 1st Session, which authorized 
abandonment of the part of the Federal 
project which provides for an entrance channel 
from such river to Delaware River. 
Local cooperation. None required. 
Terminal facilities. There is one boat ramp on 
the waterway and it is considered adequate for 
existing commerce in the area. Local interests 
are planning additional facilities. 
Operations and results during fiscal year. Maintenance, 
hired labor: Costs for environmental report 
were $219. 
5. COHANSEY RIVER, N. J. 
Location. Rises in Salem County, N.J., flows 
southerly and southwesterly 27 miles through 
Cumberland County, and empties into Delaware 
Bay about 62 miles below Philadelphia, Pa. (See 
Coast and Geodetic Survey Chart 1218.) 
Previous projects. For details see page 1785, 
Annual Report for 1915, and page 348, Annual 
Report for 1938. 
Existing project. A channel 12 feet deep, 100 
feet wide from that depth in Delaware Bay 
through a neck of land at the mouth and within 
the river to the south side of Glass Street in 
Bridgeton, 19 miles above the mouth; thence a 
channel 8 feet deep, 100 feet wide to Broad 
Street; and thence 75 feet wide to Commerce 
3-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Street Bridge, 19.25 miles above the mouth; and 
a turning basin 12 feet deep and 800 feet long 
formed by widening the channel on the south 
side to a maximum width of 250 feet just below 
Glass Street. Section included in project is about 
19.5 miles long. All depths refer to the plane of 
mean low water. Extreme tidal range is from 
about 2 feet below mean low water to about 3 
feet above mean high water. Completed project 
cost $110,756 for new work, exclusive of 
amounts expended on previous projects. (See 
Table 3-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Compiled with except local 
interests must furnish suitable spoil-disposal 
areas for required maintenance. 
Terminal facilities. Twenty wharves, of which 
16 are at Bridgeton and 4 at Greenwich. Facilities 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance, 
hired labor: Costs were $1,600 for environmental 
impact statement and $374 for miscellaneous 
engineering and administration. 
Condition at end of fiscal year. Existing project 
was completed in 1939. Costs were 
$110,756 for new work and $633,399 for maintenance, 
a total of $744,155. 
6. COLD SPRING INLET, N.J. 
Location. In Cape May County, southern New 
Jersey, about 3 miles east of Cape May City and 
about 16 miles northeast of Delaware breakwater. 
Inlet connects Cape May Harbor and New 
Jersey Intracoastal Waterway with the Atlantic 
Ocean and is about 1 mile long. (See Coast and 
Geodetic Survey Charts 234, 827 and 1219.) 
Existing project. This provides for an entrance 
channel 25 feet deep and 400 feet wide, protected 
by two parallel jetties, and extending 
from the 25-foot depth curve in the Atlantic 
Ocean to a line 500 feet harborward of a line 
joining the inner ends of the jetties; thence 20 
feet deep and 300 feet wide to deep water in 
Cape May Harbor. The total length of the section 
included in the project is about 2.25 miles. 
Extreme tidal range, due to ocean storms, is 
about 11 feet. Cost of new work for completed 
project was $879,275 exclusive of $100,000 
contributed by local interests and $50,000 Navy 
Department funds. (See table at end of chapter 
for Acts authorizing existing project.) 
Local cooperation. Complied with Act of 
1907, except work of deepening and enlarging 
inner harbor, which is 80 percent complete. 
Terminal facilities. See page 238, Annual Report 
for 1962. 
Operations and results during fiscal year. Maintenance, 
hired labor: U.S. hopper dredge Hyde 
dredged during the month of May 1975 and removed 
27,232 cubic yards of material at a cost 
of $89,049. Miscellaneous engineering costs 
were $1,928. 
Condition at end of fiscal year. Project was 
completed in 1942. (For details see page 238, 
Annual Report for 1962.) 
7. DELAWARE BAY - CHESAPEAKE BAY 
WATERWAY IN DEL., MD. AND VA. 
Location. The project is located in Sussex 
County, Delaware; Worcester County, Maryland; 
and Accomack and Northampton Counties in 
Virginia. It starts at Roosevelt Inlet, Delaware, 
and extends in a southerly direction to Cape 
Charles, Virginia. (See H. Doc. 400, 91st Cong., 
2d Sess.). Estimated cost of project (October 
1975), $19,770,000 includes $6,370,000 required 
non-Federal costs. 
Existing project. The plan of improvement is 
to provide a continuous waterway along the 
coasts of Delaware, Maryland and Virginia for a 
length of approximately 145 miles and will consist 
of a channel generally 6 feet deep by 100 
feet wide, except in the existing Assawoman 
Canal which will be 60 feet wide. The Lewes and 
Rehoboth Canal in Delaware, which forms a part 
of the waterway, will remain unchanged. Four 
existing bridges will be replaced to provide adequate 
navigation clearances. 
Local cooperation. The Governors of Delaware 
and Maryland and the Director of the Virginia 
Department of Conservation and Economic Development 
have indicated they favor the proposed 
improvements. Action to obtain the necessary 
assurances will be implemented during the 
preconstruction planning phase. 
Operations and results during fiscal year. New 
work, contract: Engineering and design costs 
were $118,493 for preparation of Environmental 
Impact Statement and Phase I, GDM. 
New work, hired labor: Design and miscellaneous 
engineering costs were $60,460. Total costs 
to date are $287,197. 
Condition at end of fiscal year. Work accomplished 
was advance engineering and design. 
8. DELAWARE RIVER AT CAMDEN, N.J. 
Location. Camden, N.J., on east bank of Delaware 
River, is directly opposite city of Philadelphia, 
Pa. It is about 51 miles above mouth of 
river and about 101 miles above Harbor of Refuge 
at mouth of Delaware Bay. (See U.S. Coast 
and Geodetic Survey Charts Nos. 295 and 280.) 
3-4

PHILADELPHIA, PA., DISTRICT 
Previous projects. Adopted by River and Harbor 
Act of June 25, 1910. No work was done on 
this project. For further details, see page 321, 
Annual Report for 1932. 
Existing project. See page 217, Annual Report 
for 1962. Cost for new work for completed portions 
of project was $464,906 and $15,000, 
Federal and non-Federal funds, respectively. 
Deepening 37-foot portion of project has been 
deferred for restudy. Estimated cost of this portion, 
as revised in July 1960, was $850,000. 
Average annual maintenance cost for past 2 
years was $45,319. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 55 piers, 
wharves, and docks near project area along Delaware 
River waterfront at Camden and Gloucester, 
N.J., including 3 oil terminals on Petty 
Island. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance, 
hired labor: Costs for environmental 
impact statement were $364. 
Conditions at end of fiscal year. Project was 
about 36 percent complete. Work remaining is 
deepening channel from 30 to 37 feet which was 
placed in deferred restudy category. Controlling 
depths at local mean low water were as follows: 
In February 1962, 11.8 feet at northerly end of 
18-foot channel opposite Cooper Point; and 30 
feet in front of marine terminal. Project depths 
are well maintained in 30-foot depth section of 
channel. Cost under existing project, excluding 
$15,000 contributed funds expended for new 
work, were $462,906 for new work; and 
$331,933 for maintenance, a total of $794,839. 
9. DELAWARE RIVER BETWEEN PHILADELPHIA, 
PA., AND TRENTON, N.J. 
Location. Rises in southeastern New York, 
flows generally southerly 367 miles, forming 
boundary line between New York and New 
Jersey on the east and Pennsylvania and Delaware 
on the west, and empties into Delaware 
Bay. (See U.S. Coast and Geodetic Survey 
Charts 1218, 280, 294, 295, and 296.) 
Previous projects. For details see page 1778 of 
Annual Report for 1915, page 311 of Annual 
Report for 1924, page 220 of Annual Report for 
1934, and page 296, Annual Report for 1938. 
Existing project. A channel from Allegheny 
Avenue, Philadelphia, 23.5 miles to upstream 
end of Newbold Island 40 feet deep and 400 
feet wide, with suitable widening of bends, including 
relocation of channel at Delair Railroad 
bridge, and reconstruction of bridge, thence 5.5 
miles to upper end of Trenton Marine Terminal, 
35 feet deep and 300 feet wide, with a turning 
basin 800 feet wide and 1,700 feet long at the 
terminal; and maintenance of a channel 12 feet 
deep and 300 feet wide from upper end of 
34-foot channel to Penn Central Railroad Bridge 
at Trenton, dredged under a previous project. 
Project also provides for an auxiliary channel 20 
feet deep and 200 feet wide east of Burlington 
Island, extending easterly from main channel to 
upper end of U.S. Pipe and Foundry Co.'s property 
at East Burlington, with a turning 
basin 450 feet wide at upper end; for initial excavation, 
only, of a cross channel 8 feet deep 
and 200 feet wide through artificial island opposite 
Delanco, N.J., and for construction such 
bank protection works as may be necessary. Section 
included in project is about 30.5 miles long, 
excluding auxiliary channel east of Burlington 
Island, which is 1.4 miles long, and cross channel 
opposite Delanco. Lower end is about 55 miles 
about river mouth at Liston Point and about 
105 miles above Harbor of Refuge at mouth of 
Delaware Bay. Freshets, which occur usually 
during February and March, attain a height of 9 
to 20 feet above mean low water in vicinity of 
Trenton. Navigation is occasionally suspended 
during a portion of winter months due to ice. 
Total estimated cost for new work is 
$69,663.904 (July 1965), exclusive of amounts 
expended for previous projects; $15,000 contributed 
funds and dredging upper channel, 
Newbold Island to Trenton, estimated cost 
$7,507,900 (July 1962). (See Table 3-B at end 
of chapter for Acts authorizing existing project.) 
Local cooperation. Modification authorized by 
1954 River and Harbor Act provides local interests 
must provide suitable terminal facilities, furnish 
lands and rights-of-way for construction 
and future maintenance, and hold the United 
States free from damages. Local interests complied 
with requirements, except city of Trenton 
has not provided suitable terminal facilities. 
Terminal facilities. There are 21 piers, 
wharves, and docks from Allegheny Avenue, 
Philadelphia, Pa., to Trenton, N.J. Facilities are 
considered adequate for existing commerce. 
(For details see Port Series No. 8 (revised 1966) 
Corps of Engineers.) 
Operations and results during fiscal year. Maintenance, 
contract: Dredging commenced in January 
1975 and was completed in June 1975. A 
total of 680,628 cubic yards of material was removed 
at a cost of $1,300,000. Costs for monitoring 
fish migration were $32,534; aerial photography 
and topographic surveys, $4,690; and 
stream gaging, $11,770. 
3-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Maintenance, hired labor: Cost of real estate 
activities were $1,645; snagging and clearing, 
$26,359; biological study, $12,345; engineering 
surveys, $59,025; environmental impact statement, 
$4,870; miscellaneous engineering and design 
and supervision and inspection, $99,349. 
Condition at end of fiscal year. Existing project 
is 90 percent complete. A 40-foot channel 
under the 1954 modification from Allegheny 
Avenue to upper end of Newbold Island was 
completed April 1964. Work remaining is dredging 
from upper end of Newbold Island to Trenton 
Marine Terminal and widening turning basin 
at terminal which is in deferred category. (See 
Table 3-C at end of chapter for total costs for 
existing project to June 30, 1975.) Total deferred 
charges, undistributed for amortization of 
cost of disposal areas, are $47,323. No charges 
during this fiscal year. 
10. DELAWARE RIVER, PA., N.J. AND 
DEL., PHILADELPHIA TO THE SEA 
Location. See U.S. Coast and Geodetic Survey 
Charts 1218, 394, 295, and 280. 
Previous projects. For details see page 1779 of 
Annual Report for 1915, and page 299, Annual 
Report for 1938. 
Existing project. Provides for a channel from 
deep water in Delaware Bay to a point in the 
bay near Ship John Light, 40 feet deep and 
1,000 feet wide; thence to Philadelphia Naval 
Base, 40 feet deep and 800 feet wide, with 
1,200-foot width at Bulkhead Bar and 1,000- 
foot width at other bends; thence to Allegheny 
Avenue, Philadelphia, Pa., 40 feet deep and 500 
feet wide through Horseshoe Bend and 40 feet 
deep and 400 feet wide through Philadelphia 
Harbor, along west side of channel; and for 
anchorages at Reedy Point, Deepwater Point, 
Marcus Hook, and Mantua Creek, each 40 feet 
deep and 2,300 feet wide with respective lengths 
of 8,000, 5,200, 13,650, and 11,500 feet; anchorage 
'at Gloucester 30 feet deep and about 
3,500 feet long. Project also provides for construction 
of dikes and training works for regulation 
and control of tidal flow; for maintenance 
of an area on north side of channel opposite 
Philadelphia Naval Base between Shipway 3 and 
Schuylkill River to 40 feet deep and a width of 
150 feet on Mifflin Range and of 200 feet on 
West Horseshoe Range; and for maintenance of 
any areas dredged by local interests to 35 feet 
deep between channel and a line 100 feet channelward 
of pierhead line between Point House 
wharf and Philadelphia Naval Base, when in 
opinion of Chief of Engineers such areas are so 
located as to be of benefit to general navigation. 
Section included in project is about 96.5 miles 
long. All depths refer to plane of mean low 
water. Under influence of heavy and longcontinued 
winds extreme tidal range is about 14 
feet. Normal maximum velocity of tidal currents 
in the dredged channel varies between 2 and 3.5 
miles per hour. Storm tides may increase maximum 
to as much as 4.5 miles per hour. Estimated 
cost for new work is $71,630,000 (July 
1972) exclusive of amounts expended on previous 
projects. Channel to 37 feet deep and 500 
feet wide through Horseshoe Bend and 37 feet 
deep and 600 feet wide through Philadelphia 
Harbor along east side of channel and Port Richmond 
anchorage to 37 feet deep, except for that 
portion of channel which forms a part of 40 feet 
deep and 400 feet wide channel portion of project 
is to be restudied and excluded from foregoing 
cost estimate. Estimated cost (July 1960) 
of this portion is $2,951,000. (See Table 3-B at 
end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Requirements under 1938 
River and Harbor Act for maintaining channel 
and anchorage in Philadelphia Harbor annually 
by cities of Philadelphia and Camden were removed 
(see 1962 Annual Report for details). 
Terminal facilities. There are 217 piers, 
wharves, and docks between Allegheny Avenue, 
Philadelphia and the sea, 135 on waterfront of 
Philadelphia, Camden, and Gloucester, and 82 
below Philadelphia. Facilities are considered adequate 
for existing commerce. (For further details 
see Port Series Nos. 7, revised 1967, and 8, 
revised 1966--Corps of Engineers). 
Operations and results during fiscal year. Maintenance, 
contract: Rock removal performed during 
the period November 1974 through June 
1975. Costs incurred were $1,048,000. Other 
costs were $21,120, stream gaging; $72,241, 
aerial photography and topographic surveys; 
$105,684, maintenance of dikes and banks; and 
$16,200 for biological monitoring. 
Maintenance, hired labor: U.S. Hopper Dredge 
COMBER dredged during the period 1 July 1974 
to 4 September 1974 and removed 937,430 cubic 
yards of material at a cost of $1,121,448. Dredging 
by the COMBER was also performed during 
the period 18 December 1974 to 18 May 1975. A 
total of 1,595,604 cubic yards of material was 
removed at a cost of $2,608,099. Cost of preparation 
and maintenance of disposal areas were 
$316,557; real estate activities, $23,088; snagging 
and clearing, $89,337; removal of navigation 
structures $36,649; condition and operation 
studies, $4,288; environmental impact statement, 
$15,876; deep draft dredging study, $37,357; 
construction of banks, $136,654; raising of dikes, 
$103,905; and miscellaneous engineering and supervision 
and inspection, $736,551. 
3-6

PHILADELPHIA, PA., DISTRICT 
Condition at end of fiscal year. Existing project, 
excluding work deferred for restudy, is 
about 66 percent complete. The 40-foot channel 
from naval base to the sea was completed in 
1942. Dredging Naval Base to Allegheny Avenue 
to 40 feet deep was completed in 1962. Work 
remaining is to construct new anchorages at 
Reedy Point and Deepwater Point, enlarge Marcus 
Hook and Mantua Creek anchorages, channel 
dredging from 35 to 37 feet deep over a width 
of 500 feet through Horseshoe Bend and 600 
feet through Philadelphia Harbor, and deepening 
Port Richmond Anchorage to 37 feet all of 
which have been deferred for restudy. (See 
Table 3-C at end of chapter for total costs for 
existing project to June 30, 1975.) Total deferred 
charges, undistributed, for amortization 
of costs of disposal areas were $87,537. 
11. INDIAN RIVER INLET AND BAY, DEL. 
Location. Indian River rises in Sussex County, 
Del., and flows easterly 13 miles into Indian 
River Bay which is a shallow lagoon 6 miles long 
and 2 miles wide on the Delaware Coast about 
midway between Cape Henlopen and the Maryland 
State line. The inlet is an opening through 
the barrier beach separating Indian River Bay 
and the Atlantic Ocean. (See U.S. Coast and 
Geodetic Survey Chart No. 1219.) 
Previous projects. Adopted by River and Harbor 
Act of August 2, 1882. For further details 
see page 744, Annual Report for 1888. 
Existing project. This provides for the fixation 
of the inlet by the construction of two parallel 
jetties of steel-sheet pile and stone design extending 
to approximately the 14-foot depth 
curve in the ocean, and for dredging an entrance 
channel 15 feet deep and 200 feet wide, for a 
distance of 7,000 feet inshore from the jetties; 
thence a channel 9 feet deep, 100 feet wide in 
the bay, and 80 feet wide in the river, to and 
including a turning basin 9 feet deep, 175 feet 
wide, and 300 feet long at Old Landing; thence a 
channel 4 feet deep and 60 feet wide to the 
highway bridge at Millsboro. The project also 
provides that the interior channel dimensions 
may, in the discretion of the Chief of Engineers, 
be modified as found desirable to increase the 
hydraulic efficiency of the channel, without increasing 
the cost. The total length of the section 
included in the project is about 13.75 miles. All 
depths refer to the plane of mean low water. 
The extreme tidal range at the highway bridge is 
about 6 feet. 
The cost for new work for the completed project 
was $511,210, exclusive of $10,000 expended 
on previous projects and exclusive of 
$210,000 contributed funds. (See Table 3-B at 
end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Fully complied with except 
that local interests are required to furnish 
suitable areas for disposal of dredged material 
during maintenance as and when needed, and 
provide terminal facilities. 
Terminal facilities. There is a privately owned 
basin with berthing facilities for small boats 
located about .75 mile west of the highway 
bridge near the inlet and .25 mile north of the 
inlet channel, connected therewith by a channel 
6 feet deep and 40 feet wide; a U.S. Coast Guard 
wharf on the north side of the inlet channel in 
the same locality; and two wharves at Oak 
Orchard in Indian River Bay. The facilities are 
considered adequate for existing commerce. 
Operations and results during the fiscal year. 
Maintenace, hired labor: Costs were $285 for 
environmental impact statement, $147 for engineering 
surveys; and $1,163 for miscellaneous 
engineering and administration. 
Condition at end of fiscal year. Existing project 
was completed in 1951. For details see Annual 
Report for 1963. Costs under existing project, 
excluding $210,000 contributed funds expended 
for new work, were $511,210 for new 
work, $1,332,140 for maintenance and 
$1,323,775 for major rehabilitation, a total of 
$3,167,125. 
12. INLAND WATERWAY, REHOBOTH BAY 
TO DELAWARE BAY, DEL. 
Location. A tidal canal in southeasterly part of 
Sussex County, Del. It extends 12 miles northward 
from Rehoboth Bay through high land 
west of town of Rehoboth to Gordon Lake; 
thence through marshes back of Cape Henlopen 
to Lewes River; thence down Lewes River to its 
junction with Broadkill River near its mouth. An 
entrance to the waterway from Delaware Bay is 
about 4 miles above Cape Henlopen. (See U.S. 
Coast and Geodetic Survey Charts 379, 1218, 
and 1219.) 
Previous projects. A canal along a slightly different 
route formed a part of projected waterway 
from Chincoteague Bay, Va., to Delaware 
Bay, begun in 1886 and abandoned in 1905. 
Existing project. This provides for an entrance 
channel near Lewes 10 feet deep and 200 feet 
wide protected by two parallel jetties 500 feet 
apart; thence a channel 10 feet deep and 100 
feet wide to South Street Bridge at Lewes, with 
a basin of the same depth 1,200 feet long and up 
to 375 feet in width at the latter point: thence a 
3-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
channel 6 feet deep and 50 feet wide (40 feet 
wide through Deep Cut near Rehoboth) to 
Rehoboth Bay; a channel 6 feet deep and 100 
feet wide from the entrance to Broadkill River; 
two parallel rubble jetties 725 feet long at the 
Rehoboth Bay entrance; and the construction of 
one highway bridge and one railroad bridge at 
Rehoboth. The total length of the section included 
in the project is about 12 miles. 
The cost for new work for the completed portion 
of the project was $561,514, exclusive of 
amounts expended on previous projects and 
$60,000 contributed funds. The extension of 
the jetties at the Delaware Bay entrance is considered 
to be inactive and is excluded from the 
foregoing cost. The cost of the portion was last 
revised in 1960 and was estimated to be 
$816,000. (See Table 3-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Complied with except local 
interests must furnish suitable terminal facilities 
and necessary spoil-disposal areas. 
Terminal facilities. See page 228, Annual Report 
for 1962. 
Operation and results during fiscal year. Maintenance, 
contract: Dredging commenced in November 
1974 and was completed in February 
1975. A total of 86,637 cubic yards of material 
was removed at a cost of $140,700. Stream gaging 
costs were $1,480. 
Maintenance, hired labor: Costs for real estate 
activities were $6,373; engineering surveys, 
$37,680; and miscellaneous engineering and administrative 
activities, $15,311. 
Condition at end of fiscal year. Existing project 
is about 70 percent complete. For details on 
completed work see page 241 of Annual Report 
for 1963. Work remaining, extension of existing 
jetties at Delaware Bay entrance, is considered 
inactive. 
13. INLAND WATERWAY FROM CHINCOTEAGUE 
BAY, VA., TO DELAWARE 
BAY, DEL. 
Location. Extends northerly from Chincoteague 
Bay, Va., following waterways parallel 
with Atlantic Ocean through Virginia, Maryland, 
and Delaware, passing through neck of land at 
Ocean View, Del., and land between Rehoboth 
Bay and headwaters of Lewes River, entering 
Delaware Bay at or near town of Lewes, a total 
distance of about 70 miles. (See U.S. Coast and 
Geodetic Survey Charts 1218, 1219, and 1220.) 
Previous projects. For details see page 382, 
Annual Report for 1932. 
Existing project. Provides for maintenance of 
three bridges built by the Government at Ocean 
View, Del., under previous project. Existing 
project was adopted by 1910 River and Harbor 
Act (H. Doc. 538, 59th Cong., 1st sess.). Latest 
published map is in House Document 128, 67th 
Congress, 2d session. 
Local cooperation. Fully complied with. 
Terminal facilities. See page 232, Annual Report 
for 1962. 
Operations and results during fiscal year. Maintenance, 
hired labor: Costs were $2,325 for real 
estate activities. 
Condition at end of fiscal year. For details see 
page 245, Annual Report for 1963. Costs under 
existing project excluding $2,000 contributed 
by State of Delaware, were $49,151 for maintenance. 
14. INLAND WATERWAY FROM DELAWARE 
RIVER TO CHESAPEAKE BAY, 
DEL., AND MD. 
Location. Begins at Reedy Point on Delaware 
River, about 41 miles below Philadelphia, Pa., 
and passes through sea level Chesapeake and Delaware 
Canal, a distance of 14 miles, to Back 
Creek, at Chesapeake City, Md. It then passes 
for 5 miles down Back Creek, thence 9 miles 
down Elk River to Chesapeake Bay and thence 
18 miles down Chesapeake Bay to a point near 
Pooles Island. A branch channel connects Delaware 
River at Delaware City, Del., with main 
channel at a point about 1.5 miles west of 
Reedy Point. (See U.S. Coast and Geodetic Survey 
Charts 294, 1226, 570, and 572.) 
Previous projects. For details see Annual Report 
for 1934, page 242, and Annual Report for 
1938, page 312. 
Existing project. A channel 35 feet deep and 
450 feet wide from Delaware River through Elk 
River and Chesapeake Bay to water of natural 
35-foot depth in Chesapeake Bay including a 
cutoff at Penn Central Railroad crossing, and 
having a minimum radius of curvature of 7,000 
feet at bends; a high level, fixed railroad bridge 
with vertical clearance of 135 feet and horizontal 
clearance of 600 feet at the railroad crossing 
over the cutoff; (economic study of railroad 
crossing requested by Office of Management and 
Budget resulted in construction of a single track 
vertical lift bridge in lieu of a high-level fixed 
railroad bridge), high-level fixed highway bridges 
over canal at Reedy Point, St. Georges, Summit, 
and Chesapeake City; a bascule drawbridge 
across Delaware City Branch Channel; extension 
3-8

PHILADELPHIA, PA., DISTRICT 
of entrance jetties at Reedy Point; and anchorage 
in Elk River, 35 feet deep and 1,200 feet 
wide, with an average length of 3,700 feet; enlargement 
of anchorage and mooring basin in 
Back Creek to afford an area about 400 feet 
wide, 1,000 feet long, and 12 feet deep; dredging 
Delaware City Branch Channel to 8 feet deep 
and 50 feet wide, and deepening existing basin 
to same depth; revetment of banks of canal as 
required between Delaware and Elk Rivers, and 
on banks of Delaware City Branch Channel east 
of Fifth Street Bridge; and construction of bulkheads. 
Total length of section included in project, 
excluding Delaware City Branch Channel, 
which is about 2 miles long, is about 46 miles. 
All depths refer to plane of mean low water in 
Delaware River. Extreme tidal range is from 6.3 
feet above mean high water to 3 feet below 
mean low water. 
Original cost of canal including purchase was 
$10,709,755; estimated cost of new work for 
modifications of 1935 and 1954 is 
$132,674,000 (October 1975). Total estimated 
cost of new work including original purchase is 
$144,783,755. Portion of project comprising 
completion of Delaware City Branch Channel 
from a point 400 feet east of Fifth Street Bridge 
to its junction with canal is to be restudied and 
excluded from foregoing estimate. Estimated 
cost of this portion is $145,000 (July 1954). 
(See Table 3-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. River and Harbor Act of 
1954 provided that local interests furnish lands 
and rights-of-way required for bridges. Assurances 
accepted and approved February 16, 
1955. Requirements for Summit and Reedy 
Point Bridges have been met. 
Terminal facilities. Ample mooring facilities at 
eastern and western ends of canal and bulkheads 
at Delaware City and St. Georges were constructed 
by the United States. A small-boat harbor 
was provided and a wharf constructed at 
Chesapeake City. Facilities are considered adequate 
for existing commerce. 
(See Table D on operations and results during 
fiscal year at end of chapter.) Other costs were: 
$114,390 for design and water transfer study 
contracts. New work, hired labor: Engineering 
and design, supervision and administration costs 
were $279,387. 
Maintenance contract: Dredging commenced 
September 1974 and was completed in October 
1974 at a cost of $978,486. A total of 422,729 
cubic yards of material was removed. Painting 
and alterations to Chesapeake City Bridge incurred 
costs of $663,264; mosquito control, 
$8,307; aerial surveys, $15,382; roadway main 
tenance for bridges, $29,398; dredging study, 
$14,006; and inspection reports, $16,708. 
Maintenance, hired labor: Maintenance and repair 
of banks and disposal areas continued at a 
cost of $254,833; preparation of disposal areas, 
$12,506; repair of riprap, $4,923; real estate 
activities, $11,602; locks, dispatch service and 
traffic control TV, $144,006; service facilities, 
$113,188; environmental impact statement, 
$1,465; mosquito control, $7,734; condition 
and operation studies reports, and pamphlets, 
$10,914; general maintenance and operation of 
the canal, $207,011; maintenance of traffic, 
$30,092; engineering and miscellaneous expenses, 
$486,328. 
Condition at end of fiscal year. Existing project 
is about 89 percent completed. Channel 27 
feet deep and 250 and 400 feet wide, Delaware 
River to Pooles Island, was completed in 1938. 
High level fixed highway bridges were completed 
at St. Georges (4-lane) in 1942; at Chesapeake 
City (2-lane) in 1949; and at Summit (4-lane) in 
1960. Relocation of Penn Central Railroad 
bridge was completed December 21, 1965. 
Channel enlargement to 35 feet deep and 450 
feet wide between St. Georges and Summit 
bridges and Summit Bridge and Goose Island 
was completed on June 20, 1972 and February 
18, 1972, respectively. Removing the old Penn 
Central railroad bridge was completed on January 
21, 1972. Channel work for Part II is about 
87 percent complete. Work remaining consists of 
completing channel enlargement to 35 feet deep 
and 450 feet wide between Reedy Point Bridge 
and St. Georges Bridge; widening and deepening 
the channel between Delaware River and Reedy 
Point Bridge, the completion of recreation facilities, 
and miscellaneous completion items. Deepening 
Delaware City Branch Channel from 6 to 8 
feet from a point 400 feet east of Fifth Street 
Bridge to its junction with the canal has been 
deferred for study. Total cost of existing project 
to June 30, 1975 was $174,144,279 of which 
$120,389,600 was for new work ($4,756,248 
emergency relief funds and $115,633,352 regular 
funds), and $53,754,679 regular funds for 
maintenance. 
15. LITTLE RIVER, DEL 
Location. In Kent County, Delaware, flows 
easterly 7 miles, and empties into Delaware Bay 
about 32 miles above Cape Henlopen. 
Existing project. A channel 5 feet deep at 
3-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
mean low water from the 5-foot contour in Delaware 
Bay to the bridge at Little Creek Landing, 
3 miles above the mouth, 60 feet wide across the 
bar outside the mouth and 40 feet in the river, 
including several cutoffs to eliminate sharp 
bends, which shortened the distance about .5 
mile. Cost for new work for the completed 
project was $12,016. Existing project was adopted 
by 1912 River and Harbor Act (H. Doc. 626, 
62d Cong., 2d Sess.). 
Local cooperation. Fully complied with. 
Terminal facilities. Three pile-and-timber 
wharves or landings on this stream, which are 
considered adequate for the existing commerce. 
Operations and results during fiscal year. Maintenance, 
hired labor: Engineering surveys were 
made at a cost of $279. 
Condition at end of fiscal year. Project was 
completed in 1914. 
16. MANASQUAN RIVER, N. J. 
Location. This small stream flows in eastern 
part of New Jersey, rises near Freehold, flows 
easterly and empties into the Atlantic Ocean, 
about 26 miles south of Sandy Hook. (See U.S. 
Coast and Geodetic Survey Chart No. 795.) 
Previous projects. For details see Annual Report 
for 1909, page 186, and Annual Report for 
1938, page 269. 
Existing project. A channel 14 feet deep and 
250 feet wide, protected by jetties and other 
works, extending from the Atlantic Ocean to inner 
end of north jetty, thence 12 feet deep and 
300 feet wide to within 700 feet of New York 
and Long Branch Railroad bridge, thence of 
same depth and narrowing to 100 feet wide to 
within 300 feet of bridge; for a widening on 
northerly side of channel of 200 feet for 3,150 
feet to a depth of 8 feet; for a 19-acre anchorage 
to 10 feet deep on south side of channel and for 
a 27.5-acre anchorage to 12 feet deep about 0.5 
miles west of route 35 highway bridge. Section 
included in project is about 1.5 miles long. Mean 
tidal range is 3.7 feet at inner end of inlet and 4 
feet at ocean end; mean range of spring tides, 
4.4 and 4.8 feet, respectively; irregular fluctuations 
due to wind and barometric pressure vary 
from 2.7 feet below to 7.5 feet above mean low 
water at inner end of inlet. Project, excluding 
10- and 12-foot anchorages, cost $518,243. Estimated 
cost (1958) for 10- and 12-foot anchorages 
portion of project considered inactive is 
$504,000. (See Table 3-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. River and Harbor Act of 
1945 provides that local interests must furnish 
lands and rights-of-way for construction and future 
maintenance and hold the United States 
free from damages. Assurances to date have been 
complied with. 
Terminal facilities. Five landings with a total 
wharfage of 700 feet used by commercial fisherman, 
and 7 landings and boat basins for pleasure 
craft. Existing facilities are considered adequate 
for present requirements. 
Operations and results during fiscal year. Maintenance, 
contract: Costs for rehabilitation of 
bulkheads were $32,161. 
Maintenance, hired labor: Miscellaneous engineering 
and supervision and inspection costs 
were $460. 
Condition at end of fiscal year. Existing project 
was completed in June 1963. Dredging 19 
acre anchorage south of channel and 27.5 acre 
anchorage west of highway bridge is in the inactive 
category. Costs under existing project, excluding 
$300,000 (new work) contributed funds 
expended, were $518,249 for new work, 
$555,600 for major rehabilitation, and 
$1,833,393 for maintenance, a total of 
$2,907,242. 
17. MURDERKILL RIVER, DEL. 
Location. Rises in Kent County, Del., flows 
northeasterly 19 miles through county, and 
empties into Delaware Bay about 25 miles above 
Cape Henlopen. (See U.S. Coast and Geodetic 
Survey Chart No. 1218.) 
Existing project. Provides for a channel 7 feet 
deep at mean low water, 150 feet wide in Delaware 
Bay to mouth, and thence 80 feet wide to 
Frederica, 7.5 miles above mouth. Total length 
of section included in project is about 8.5 miles. 
Extreme tidal range is from about 1 foot below 
mean low water to about 2 feet above mean high 
water. 
Estimated cost for new work revised in 1954 is 
$38,000. Portion of project comprising widening 
channel to project width throughout its length is 
to be restudied and excluded from foregoing 
cost estimate. Estimated cost of this portion last 
revised in 1954 was $86,000. 
Project was authorized by River and Harbor 
Act of July 13, 1892 (H.Ex. Doc. 21, 52d 
Cong., 1st sess.). (See page 981 Annual Report 
of 1892.) Latest published map is in House 
Document 1058, 62nd Congress, 3d session. 
Local cooperation. None required. 
Terminal facilities. There are a number of light 
timber wharves on both sides of river near 
mouth and two wharves at Frederica, all private- 
3-10

PHILADELPHIA, PA., DISTRICT 
ly owned. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance, 
hired labor: Costs for environmental 
impact statement were $854. 
Condition at end of fiscal year. Existing project 
about 30 percent complete, including revision 
to be restudied. Channel 7 feet deep and 
60 feet wide was completed in 1911. Work remaining 
is widening channel to project width. 
18. NESHAMINY STATE PARK HARBOR, 
PA. 
Location. Marina is along right bank of Delaware 
River in southeastern section of community 
of Croydon, in Bristol Township, Bucks 
County, Pa., about 500 feet generally east of 
confluence of Neshaminy Creek with Delaware 
River and about 17 miles upstream from Benjamin 
Franklin Bridge across Delaware River at 
Philadelphia, Pa.-Camden, N.J. (See U.S. Coast 
and Geodetic Survey Chart 296.) 
Existing project. Dredging an entrance channel 
generally 60 feet wide and 350 feet long from 
the river to the basin; an access channel 100 feet 
wide, 760 feet long from basin entrance to turning 
basin; an anchorage area 100 feet wide and 
760 feet long; a turning basin 200 feet wide and 
240 feet long; a stone jetty 230 feet long; and 
675 feet of stone revetment. Project depth is 8 
feet. The limit of Federal dredging for access 
channel and turning basin shall be 25 feet from 
berthing area facilities. Also, consideration be 
given to possible widening at the bend near entrance 
channel and/or straightening on downstream 
side. Estimated cost for new work is 
$456,161 of which the Federal first cost is 
$128,204 and remaining cost borne by local interests. 
Local cooperation. See detailed project report 
- Small Navigation Project for Neshaminy State 
Park Marina - Assurances were accepted September 
21, 1964. Pennsylvania General State 
Authority contributed $322,760 in August 
1965, and an additional $5,197 in August 1967. 
Operations and results during fiscal year. Maintenance, 
contract: Costs for environmental report 
were $700. Maintenance, hired labor: Miscellaneous 
engineering and design costs were 
$1,628. 
Condition at end of fiscal year. Controlling 
depths (February 1974) were 9.5 feet in the entrance 
channel and 8.9 feet in the Federal portion 
of the main basin. 
19. NEW JERSEY INLETS AND BEACHES - 
CORSON INLET AND LUDLAM BEACH 
Location. The project is located in Cape May 
County, New Jersey. Corson Inlet is about 0.3 
mile wide at its narrowest point, between sand 
spits extending from Peck Beach, and the island 
barrier beach to the southwest, Ludlam Beach. 
The ocean front of Ludlam Beach extends for 
about 7 miles. The northeastern 2 miles is occupied 
by a part of upper township. The remaining 
5-mile length is occupied by Sea Isle City. 
Existing project. The project will provide a 
12-foot by 300-foot inlet channel, with 6-foot 
by 100-foot interior channels, inlet jetties; deposition 
basins; bulkheads and backfill; appurtenant 
works for jetty and bulkhead fishing; beach 
fill; construction of ten additional groins; and 
periodic nourishment. Estimated cost of project 
(October 1975) is $15,400,000 which includes 
$7,697,500 non-Federal cash contribution. 
Local cooperation. The State of New Jersey, 
Department of Environmental Protection is the 
local agency responsible for the project. The Department, 
in letter dated September 19, 1974, 
indicated continued interest in the project. 
Specific assurances of local cooperation are 
being developed during preconstruction planning 
and will be formalized in contract form as part 
of preconstruction planning. 
Operations and results during fiscal year. New 
work, hired labor: Miscellaneous engineering and 
design costs were $40,090. New work, contract: 
Costs were $14,816 for prototype data for 
model studies; $2,044 for aerial surveys; 
$19,988 for geophysical survey and ocean floor 
sampling; and $17,500 for mathematical model 
studies. 
Condition at end of fiscal year. Work accom- 
'plished was advance engineering and design. 
20. NEW JERSEY INLETS AND BEACHES - 
GREAT EGG HARBOR INLET AND 
PECK BEACH 
Location. The project is located in Cape May 
and Atlantic Counties, New Jersey. Great Egg 
Harbor Inlet, an unimproved inlet, is about 1.1 
miles wide at its narrowest point and provides a 
tidal connection between the Atlantic Ocean 
and Great Egg Harbor Bay, the New Jersey Intracoastal 
Waterway, and Great Egg Harbor 
River. Peck Beach is occupied in its entirety by 
the city of Ocean City and extends from Great 
Egg Harbor Inlet southward to Corson Inlet. The 
ocean frontage is about 8.0 miles in length. 
3-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. The project will provide 12 
foot by 300-foot inlet channel, with 6 foot by 
100-foot interior channels, inlet jetties, deposition 
basin; bulkhead and back fill; appurtenant 
works for jetty and bulkhead fishing; beach fill; 
extending nine existing groins and periodic beach 
nourishment. Estimated cost of project (October 
1975) is $17,300,000 which includes $8,611,000 
non-Federal cash contribution. 
Local cooperation. The State of New Jersey, 
Department of Environmental Protection, is the 
local agency responsible for the project. The Department, 
in letter dated September 19, 1974, 
indicated continued interest in the project. 
Specific assurances of local cooperation are 
being developed during preconstruction planning 
and will be formalized in contract form as part 
of preconstruction planning. 
Operations and results during fiscal year. New 
work, contract: Costs were $21,278 for prototype 
data for model studies; $4,004 for aerial 
surveys; $19,988 for geophysical survey and 
ocean floor sampling; and $17,500 for mathematical 
model studies. 
Condition at end of fiscal year. Work accomplished 
was advance engineering and design. 
21. NEW JERSEY INTRACOASTAL WATERWAY 
Location. A sea level inland water route approximately 
parallel with New Jersey coast, extends 
from Atlantic Ocean at Manasquan Inlet, 
about 26 miles south of Sandy Hook, N.J., to 
Delaware Bay about 3 miles above Cape May 
Point. Waterway extends through inlet and up 
Manasquan River about 2 miles; thence by Point 
Pleasant Canal through high ground for 2 miles 
to head of Barnegat Bay. It then passes through 
a series of bays, lagoons, and thoroughfares 
along New Jersey coast to Cape May Harbor; 
thence across Cape May County to Delaware 
Bay through a land cut by way of New England 
Creek basin. (See U.S. Coast and Geodetic Survey 
Charts, 234, 795, 825, 826, 827, 1216, 
1217, 1218, and 1219.) 
Existing project. This provides for a channel 
12 feet deep at mean low water and generally 
100 feet wide, extending from the Atlantic 
Ocean at Manasquan Inlet, N.J., to Delaware 
Bay above Cape May, N.J., by the further improvement 
of Manasquan River and Inlet, N.J., 
and the present New Jersey Intracoastal Waterway, 
and by the construction of a canal of 
similar dimensions from Cape May Harbor to 
Delaware Bay via the New England Creek basin, 
with adequate jetties at the Delaware Bay entrance. 
The total length of the project is about 
117 miles. Normal tide range in sections of the 
waterway remote from inlets is 0.5 foot. 
Estimated cost for new work is $71,549 (July 
1969), exclusive of $1,824,940 Navy Department 
funds and $99,000 contributed by local 
interests. Portion of project extending from 
Manasquan River to Cape May Harbor is to be 
restudied and excluded from new work cost estimate. 
Estimated cost of this portion is 
$6,470,000 (July 1954). Existing project was 
adopted by 1945 River and Harbor Act (H. Doc. 
133, 76th Cong., 1st sess.). Latest published 
map is in project document. River and Harbor 
Act of 1946 (Public Law 525, 79th Cong., 2d 
sess., as extended by Public Law 240, 82nd 
Cong.), authorized use for a period not to exceed 
6 years, of funds from appropriations heretofore 
or hereafter made for maintenance and 
improvement of rivers and harbors, for maintenance 
of canal from Cape May Harbor to Delaware 
Bay constructed as an emergency wartime 
project with Navy Department funds, including 
cost of maintaining temporary railroad and seashore 
highway bridges over canal. 
Local cooperation. The project is subject to 
the conditions that the State of New Jersey cede 
to the United States all right, title, and interest 
that it has acquired to lands, easements, rightsof-
way, and structures other than bridges for the 
Bayhead-Manasquan Canal; that the State of 
New Jersey furnish, free of cost to the United 
States, all lands, easements, rights-of-way, and 
disposal areas required for construction of the 
Cape May Canal and for improvement of the 
proposed waterway and for their subsequent 
maintenance; that local interests provide, maintain, 
and operate suitable bridges over the waterway; 
that the State of New Jersey donate to the 
United States the navigation aids in use on the 
present New Jersey Intracoastal Waterway; and 
that the State of New Jersey hold and save the 
Unites States and its agents free from any claims 
for damages resulting from the work of improvement. 
Compliance with these conditions was 
completed January 15, 1954, except that local 
interests are required to furnish disposal areas 
for the construction and the subsequent maintenance 
of the proposed improvement. 
Terminal facilities. See Annual Report for 
1962. 
Operations and results during fiscal year. Maintenance, 
contract: Dredging commenced during 
July 1974 and was completed in September 
1974. Costs of $167,558 were incurred for the 
removal of 67,292 cubic yards of material. 
Dredging occurred during June 1975 with 
43,805 cubic yards of material being removed at 
3-12

PHILADELPHIA, PA., DISTRICT 
a cost of $49,500. Costs for stream gaging were 
$2,520; bank stabilization surveys, $394; environmental 
impact statement, $222. 
Maintenance, hired labor: Real estate activity 
costs were $8,918; engineering surveys, $62,697; 
and miscellaneous engineering, supervision and 
inspection, $73,694. 
Condition at end of fiscal year. Existing project 
is about 25 percent complete. A canal 12 
feet deep and 100 feet wide from Cape May 
Harbor to Delaware Bay was completed in 1942; 
two parallel stone jetties at Delaware Bay entrance 
and a temporary highway and a railroad 
bridge in 1944, all with Navy Department funds. 
Work remaining, dredging a channel 12 feet deep 
and 100 feet wide from Atlantic Ocean at Manasquan 
Inlet to Cape May Harbor, has been deferred 
for restudy; however, the project between 
Ottens Harbor and Richardson Channel and 
from that point to Cape May are being maintained 
to 10 feet and 12 feet, respectively, since 
they were originally dredged to these depths by 
the State. 
22. SCHUYLKILL RIVER, PA. 
Location. Rises in Schuylkill County, Pa., 
flows generally southeasterly 150 miles, and 
empties into Delaware River at Philadelphia, Pa. 
(See U.S. Coast and Geodetic Survey Charts 295 
and 280.) 
Previous project. For details see page 325, Annual 
Report for 1932. 
Existing project. This provides for a channel 
33 feet deep and 400 feet wide in Delaware 
River to the mouth and within the river to 29th 
Street, .75 mile above the mouth; thence the 
same depth and 300 feet wide to Passyunk 
Avenue Bridge, 3.5 miles above the mouth; 
thence 26 feet deep and 200 feet wide to Gibson 
Point, 4.5 miles above the mouth; and thence 22 
feet deep and 200 feet wide to University 
Avenue Bridge, 6 miles above the mouth, including 
widening at bends. The total length of 
the section included in the project is about 6.5 
miles. All depths refer to the plane of mean low 
water. The extreme tidal range, due to freshets 
and prolonged heavy winds, is about 14 feet. 
The cost for new work for the completed existing 
project was $2,809,007. (See Table 3-B at 
end of chapter for Acts authorizing existing 
project.) 
Local cooperation. The River and Harbor Act 
of July 24, 1946, imposed the condition that 
the city of Philadelphia agree to remove 60,000 
cubic yards, place measurement, of material annually 
from that portion or those portions of 
the project which the District Engineer may designate 
until such time as adequate municipal 
sewage-treatment works are constructed and 
placed in effective operation. Compliance with 
this condition has been met through the completion 
of sewage-treatment works by the city of 
Philadelphia. All other requirements have been 
fully complied with. 
Terminal facilities. There are 38 wharves, 
piers, and docks within limits of improvement. 
Facilities are considered adequate for existing 
commerce. (For further details see Port Series 
No. 7-Revised 1967-Corps of Engineers.) 
Operations and results during fiscal year. Maintenance, 
contract: Dredging commenced during 
July 1974 and was completed in November 
1974. A total of 505,813 cubic yards of material 
was removed at a cost of $743,545. Stream gaging 
costs were $19,040. 
Maintenance, hired labor: Costs for engineering 
surveys were $22,239; environmental 
impact statement, $400; and miscellaneous engineering 
and design and supervision and inspection, 
$38,432. 
Condition at end of fiscal year. Existing project 
was completed in September 1962. For details 
see Annual Report for 1962. Costs under 
existing project were $2,809,007 for new work 
and $17,965,286 for maintenance, a total of 
$20,774,293. 
23. WILMINGTON HARBOR, DEL. 
Location. Formed by Christina River, which 
rises in New Castle County, Del., flows northeasterly 
16 miles, passing through city of Wilmington, 
Del., and empties into Delaware River 
about 29 miles below Philadelphia, Pa. (See U.S. 
Coast and Geodetic Survey Chart 294.) 
Previous projects. For details see page 1785 of 
Annual Report for 1915 and page 308 of Annual 
Report for 1938. 
Existing project. This provides for a channel 
35 feet deep and 400 feet wide from west edge 
of Delaware River ship channel to Lobdell 
Canal, a distance of about 1.2 miles; thence 21 
feet deep and 250 feet wide for a distance of .8 
mile to the mouth of Brandywine River; thence 
the same depth and 200 feet wide for a distance 
of about 2.2 miles to a point approximately 4.2 
miles from the Delaware River ship channel; 
thence decreasing to a depth of 10 feet in a 
distance of 750 feet to Penn Central Railroad 
bridge No. 4; and thence 7 feet deep and 100 
feet wide for a distance of about 5.6 miles to 
Newport, Del., approximately 9.9 miles above 
the Delaware River ship channel, including a 
3-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
turning basin 35 feet deep opposite the Wilmington 
Marine terminal and extending upstream 
from the mouth to Lobdell Canal, 200 
feet wide, 2,900 feet long on the north side of 
the channel and decreasing to a length of 2,000 
feet on the north side of the basin. It also provides 
for the removal of about 1,200 feet of the 
outer end of a stone-filled, pile-and-timber-crib 
jetty constructed 2,150 feet long on the north 
side of the entrance; for a steel sheet-pile jetty 
2,300 feet long, with 120-foot inshore wing, on 
the south side of the entrance, and for a 
V-shaped stone-filled pile-and-timber jetty at the 
mouth of Brandywine River 430 feet long along 
the north side of the Brandywine and 260 feet 
long on the Christina. All depths refer to the 
plane of mean low water. The extreme tidal 
range, due to prolonged heavy winds, is about 
13 feet. (See Table 3-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 18 piers, 
wharves, and docks within improvement. Facilities 
considered adequate for existing commerce. 
(For further details see Port Series No. 8, revised 
1966, - Corps of Engineers). 
Operations and results during fiscal year. Maintenance, 
contract: Dredging commenced during 
November 1974 and was completed in March 
1975. A total of 755,831 cubic yards of material 
was removed at a cost of $498,607. Costs for 
stream gaging were $3,570. 
Maintenance, hired labor: Maintenance of disposal 
area costs were $169,276; engineering surveys, 
$5,685; general maintenance, $2,160; real 
estate activities, $4,661; and miscellaneous engineering 
and inspection work, $58,854. 
Condition at end of fiscal year. Existing project 
was completed in 1962. (For details see page 
222, Annual Report for 1962.) 
Total cost of existing project to 30 June 1975 
is $16,096,827 of which $1,552,604 is for new 
work ($206,177 emergency relief funds and 
$1,346,427 regular funds), and $14,544,223 regular 
funds for maintenance. 
24. RECONNAISSANCE AND CONDITION 
SURVEYS 
(See Table 3-E at end of chapter.) 
25. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
(See Table 3-F at end of chapter.) 
26. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation Activities Pursuant to Section 107, 
Public Law 86-645 (Preauthorization). 
Fiscal year costs were $5,984 for Bristol 
Marina, Pa. 
27. OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
(See Table 3-G at end of chapter.) 
28. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Table 3-H at end of chapter.) 
FLOOD CONTROL 
29. BELTZVILLE LAKE, PA. 
Location. Damsite is on Pohopoco Creek 
about 4.5 miles upstream from its confluence 
with Lehigh River and 4 miles east of Lehighton, 
Pa. (See Geological Survey Quandrangle Map for 
Lehighton, Pa. - 1960.) 
Existing project. A multiple purpose development 
project to provide water supply, flood control, 
and recreation. Plan of improvement provides 
for an earth and rock fill dam 4,500 feet 
long rising 160 feet above creekbed; a spillway 
around north end of dam; and gate-control outlet 
works discharging through a conduit on rock 
along right abutment. The lake, a unit of comprehensive 
plan for flood control and other purposes 
of Delaware River Basin, will have a reservoir 
capacity of 68,200 acre-feet at spillway 
crest level with 1,200 acre-feet of inactive storage, 
40,000 acre-feet for water supply and recreation, 
and 27,000 acre-feet for flood control. 
(For details see H. Doc. 522, 87th Cong., 2d 
Sess.) Design changes, based on planning to July 
1965, indicate an earthfill dam 4,200 feet long 
rising 170 feet above creekbed, a controlled reservoir 
capacity of 68,250 acre-feet at spillway 
crest with 1,390 acre-feet of inactive storage, 
41,220 acre-feet for water supply, water quality 
control and recreation. Estimated cost of project 
(July 1974) is $22,944,200 including 
$6,100,000 required non-Federal reimbursement 
for costs allocated to water supply storage during 
life of project after use of this storage is 
initiated; ultimate Federal cost is $16,100,000. 
Local cooperation. Project was approved subject 
to certain requirements of cooperation by 
local interests as defined in approved House 
Document. Resolution of Delaware River Basin 
3-14

PHILADELPHIA, PA., DISTRICT 
Commission providing assurances of repayment 
of water supply and pollution control costs was 
accepted June 7, 1965. A contract for repayment 
of water supply costs was signed October 
16, 1966. 
Operations and costs during fiscal year. Maintenance, 
contract: Costs were incurred for snow 
survey, $1,000; stream gaging, $9,860; water 
quality management, $1,475; and operation and 
maintenance of reservoir, $6,400. 
Maintenance, hired labor: Operation and maintenance 
of dam and reservoir, $49,990; real 
estate activities, $1,238; water quality data, 
$8,754; stream gaging, $2,126; periodic inspection 
reports, $6,174; and miscellaneous engineering 
and supervision and inspection, $31,192. 
Condition at end of fiscal year. Project is 
about 99 percent complete. Acquisition of the 
necessary land is complete. 
30. BLUE MARSH LAKE, PA. 
Location. Damsite is on Tulpehocken Creek 
about 1.5 miles upstream from its confluence 
with Plum Creek and about 6 miles northwest of 
Reading, Pa. (See Geological Survey Quadrangle 
Sheet, Bernville, Pa.) 
Existing project. A multiple purpose development 
project to provide supplies of water, flood 
control, and recreation. Plan of improvement 
provides for an earth and rock fill dam, 1,775 
feet long and rising 98 feet above creekbed, with 
a spillway about 1,500 feet south of dam, and 
gate-controlled outlet works discharging through 
a conduit on rock along right abutment. The 
lake, a unit of comprehensive plan for flood 
control and other purposes of Delaware River 
Basin, will have a capacity of 50,010 acre-feet at 
spillway crest level, with 3,000 acre-feet of 
inactive storage, 14,620 acre-feet for water 
supply and recreation, and 32,390 acre-feet for 
flood control. (For details see H. Doc. 522 87th 
Cong., 2d sess.) Estimated cost of project 
(October 1975), $59,000,000 includes 
$15,043,000 required non-Federal reimbursement 
for costs allocated to water supply storage 
during life of project after use of this storage is 
initiated. Existing project was authorized by 
1962 Flood Control Act (H. Doc. 522, 87th 
Cong., 2d sess., contains latest published maps). 
Local cooperation. Project was approved, subject 
to certain requirements by local interests, as 
prescribed in House Document cited above. 
Delaware River Basin Commission on December 
29, 1964, adopted a preliminary resolution 
providing for repayment of water supply costs. 
Operations and results during fiscal year. New 
work, contract: Costs were $40,828, master plan 
design memorandum; $11,550, flood protection 
works and highway relocation in vicinity of 
Bernville; $35,288, design memorandum for 
highway relocation; $19,410, stream gaging; 
$23,000, relocation of gages; $20,000 preimpoundment 
surveys; $10,141, borings and core 
drilling; $20,667, relocation of Gruber Wagon 
Works; $79,521, demolition of structures; 
$105,224, real estate activities; $4,056, survey 
and mapping; $2,035,130, construction of dam 
and appurtenant buildings; and $3,392,113 for 
land payments. 
New work, hired labor: Design and miscellaneous 
engineering costs were $1,109,291. 
Condition at end of fiscal year. Continued 
engineering and design and acquisition of land 
and initiated construction. 
31. DELAWARE COAST PROTECTION, 
DEL. 
Location. The project is located in Sussex 
County, Delaware, on the Atlantic Ocean and 
starts immediately south of Delaware Bay extending 
in a southerly direction a distance of 
24.5 miles to Fenwick Island on the Delaware- 
Maryland border. 
Existing project. Provides a plan of improvement 
which consists of the construction of 
dunes and beach fill; the construction of bulkheads 
at Rehoboth and Dewey beaches; periodic 
nourishment of the beaches; placement of sand 
fences; planting dune grass and maintenance and 
replacement of existing structures. (For details, 
see S. Doc. 90, 90th Cong., 2d Sess.) Estimated 
cost of project (October 1975), $22,600,000 
includes $7,600,000 required non-Federal costs. 
Local cooperation. Assurances of local cooperation 
were provided by the State of Delaware, 
July 8, 1969. 
Operations and results during fiscal year. New 
work, contract: Costs were $9,484 for preparation 
of topographic surveys and GDM. New 
work, hired labor: Design and miscellaneous 
engineering costs were $36,945. 
Condition at end of fiscal year. Work accomplished 
was advance engineering and design. 
32. FRANCIS E. WALTER DAM, PA. 
Location. Reservoir is in northeastern Pennsylvania 
on Lehigh River between White Haven and 
Stoddartsville. Dam is about 0.4 mile below 
mouth of Bear Creek, about 60 miles above 
confluence of Lehigh River and Delaware River 
3-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
at Easton, Pa. (See Geological Survey Quadrangle 
Sheet, Stoddartsville, Pa.) 
Existing project. Plan of improvement authorized 
by 1946 Flood Control Act (H. Doc. 587, 
79th Cong., 2d sess.) provided for a single 
purpose flood control reservoir. Modification of 
project, authorized by 1962 Flood Control Act 
(H. Doc. 522, 87th Cong., 2d sess.), provides for 
a multiple-purpose development for water supply 
and recreation in addition to present singlepurpose 
flood control project. Plan of improvement 
requires altering spillway increasing height 
of dam, extending outlet tunnel by addition of a 
concrete conduit, and constructing new dikes 
and raising existing dikes. Modified dam will rise 
263 feet above riverbed and be 3,500 feet long. 
Reservoir modification, a unit of comprehensive 
plan for flood control and other purposes of 
Delaware River Basin, will have a reservoir 
capacity of 180,000 acre-feet spillway crest level 
with 2,000 acre-feet of inactive storage, 70,000 
acre-feet for water supply and recreation and 
108,000 acre-feet for flood control. Estimated 
Federal cost of new work (October 1975) is 
$45,623,600 including $23,455,000 required 
non-Federal reimbursement for costs allocated 
to water supply storage during life of project 
after use of this storage is initiated. 
Local cooperation. None required under 1946 
Flood Control Act. Under 1962 Flood Control 
Act, project was approved subject to certain 
requirements by local interests, as defined in 
House Document 522 cited above. 
Operations and results during fiscal year. 
Maintenance, contract: Costs of $6,050 were 
incurred for stream gaging; $1,000, snow survey; 
$3,604, spillway repair; $13,745, resurfacing 
roads; $2,800, painting service bridge; $132,957, 
removal of dead trees; $1,956, for revision to 
master plan. 
Maintenance, hired labor: Operation and maintenance 
of dam and reservoir, $53,515; real 
estate activities, $963; service facilities, $2,453; 
recreational facilities, $10,000; condition and 
operation studies, $1,438; stream gaging, 
$4,912; and miscellaneous engineering, inspection, 
and administrative costs, $36,385. 
Conditions at end of fiscal year. Project as 
authorized under the 1946 Flood Control Act 
was completed June 1961. Settlement for lands 
was completed October 1962. 
33. GENERAL EDGAR JADWIN DAM AND 
RESERVOIR, PA. 
Location. In Dyberry Creek valley in central 
part of Wayne County, Pa., between borough of 
Honesdale and village of Tanners Falls. Dam is 
about 3 miles above confluence of Dyberry 
Creek and Lackawaxen River in Honesdale and 
29 miles above confluence of Lackawaxen and 
Delaware Rivers. (See Geological Survey Quadrangle 
Sheet, Honesdale, Pa.) 
Existing project. A single-purpose flood control 
reservoir with a capacity of 24,500 acre-feet 
formed by an earth embankment, about 1,225 
feet long at crest and rising 109 feet above 
creekbed. It also has a tunnel with intake 
structure and a chute-type spillway with a 
stilling basin in left abutment. Reservoir controls 
runoff from a drainage area of 65 square miles 
which is 91 percent of watershed of Dyberry 
Creek and 39 percent of Lackawaxen River 
watershed above Honesdale, Pa. Construction of 
project was authorized by 1948 Flood Control 
Act (H. Doc. 113, 80th Cong., 1st sess.). Federal 
cost of new work was $4,064,510. Non-Federal 
funds not required. 
Local cooperation. Assurances of compliance 
with requirements of local cooperation were 
accepted July 30, 1956. For details see page 
251, Annual Report for 1962. 
Operations and results during fiscal year. 
Maintenance, contract: Costs of $1,512 were 
incurred for stream gaging and $198 for subsurface 
explorations. 
Maintenance, hired labor: Operation and maintenance 
of reservoir, $15,271; miscellaneous 
engineering and related work, $4,562. 
Condition at end of fiscal year. Project was 
completed in June 1960. 
34. PROMPTON LAKE, PA. 
Location. In Lackawaxen River Valley in 
central part of Wayne County, Pa., between 
borough of Prompton and village of Aldenville. 
Dam is within corporate limits of Prompton, 4 
miles upstream from Honesdale, Pa., and approximately 
30 miles above confluence of Lackawaxen 
and Delaware Rivers. (See Geological 
Survey Quadrangle Sheet, Honesdale, Pa.) 
Existing project. Plan of improvement authorized 
by 1948 Flood Control Act (H. Doc. 113, 
80th Cong., 1st sess.) provided for a singlepurpose 
flood control reservoir. Modification of 
project authorized by 1962 Flood Control Act 
(H. Doc. 522, 87th Cong., 2d sess.) provides for 
multiple-purpose development for water supply 
and recreation in addition to present singlepurpose 
flood control project. Plan of improvement 
requires construction of a control tower 
with gates and service bridge, placing an imper- 
3-16

PHILADELPHIA, PA., DISTRICT 
vious blanket on valley walls and floor upstream 
from dam, widening spillway, and clearing land 
and relocating roads in reservoir. Dam, completed 
under 1948 Flood Control Act which will 
not be modified, is 1,230 feet long and rises 140 
feet above riverbed. Existing spillway, cut into 
rock of right abutment, will be modified and 
present uncontrolled outlet works discharging 
into a concrete conduit along right bank, will be 
provided with gates and a control tower. Reservoir 
modification, a unit of comprehensive plan 
for flood control and other purposes of Delaware 
River Basin has a capacity of 52,000 
acre-feet; 3,500 acre-feet for inactive storage, 
28,200 acre-feet for water supply and recreation, 
and 20,300 acre-feet for flood control. 
Estimated Federal cost of new work (October 
1975) is $21,925,000 including $15,435,000 
required non-Federal reimbursement for costs 
allocated to water supply storage during life of 
project after use of this storage is initiated. 
Local cooperation. Project modification was 
approved subject to certain requirements by 
local interests, as defined in House Document 
522 cited above. Assurances of compliance 
under Flood Control Act of 1948 have been 
met. Delaware River Basin Commission on 
March 18, 1966, gave their view that the need 
for water supply is not urgent at this time. 
Study is continuing in order to resolve this 
question before completion of preconstruction 
planning. 
Operations and results during fiscal year. 
Maintenance, contract: Costs of $16,800 were 
incurred for repair to access road, and $1,465 
for relocation and installation of fencing. 
Maintenance, hired labor: Operation and maintenance 
of dam and reservoir costs were 
$19,597; real estate activities, $960; stream 
gaging, $2,174; water quality data, $1,238; snow 
survey, $1,000; miscellaneous engineering and 
related work, $15,792. 
Condition at end of fiscal year. Project as 
authorized under the 1948 Flood Control Act 
was completed in November 1960. (For details, 
see page 358, Annual Report for 1963.) Work 
accomplished under the 1962 Flood Control Act 
was advance engineering and design. 
35. TREXLER LAKE, PA. 
Location. Damsite is on Jordan Creek about 
0.5 mile downstream from its confluence with 
Mill Creek and 8 miles northwest of Allentown, 
Pa. (See Geological Survey Quadrangle Sheet, W. 
Allentown, Pa.) 
Existing project. A multiple-purpose development 
project to provide supplies of water, flood 
control, and recreation. Plan of improvement 
provides for a concrete gravity type dam 800 
feet long rising 120 feet above creekbed, a 
spillway in stream channel, and gate-controlled 
outlet works discharging through sluices in 
spillway section. The lake, a unit of the comprehensive 
plan for flood control and other purposes 
of Delaware River Basin, will have a 
capacity of 39,000 acre-feet at spillway crest 
with 800 acre-feet of inactive storage, 24,200 
acre-feet for water supply and recreation, and 
14,000 acre-feet for flood control. (For details 
see H. Doc. 522, 87th Cong., 2d sess.) Estimated 
cost of project (October 1975), $31,600,000 
includes $15,500,000 required non-Federal reimbursement 
for costs allocated to water supply 
storage during life of project after use of this 
storage is initiated. Existing project was authorized 
by 1962 Flood Control Act (H. Doc. 522, 
87th Cong., 2d sess., contains latest published 
map). 
Local cooperation. Project was approved subject 
to certain requirements by local interests, as 
prescribed in House Document cited above. The 
portion of assurances dealing with water supply 
requirements is being studied jointly by Delaware 
River Basin Commission and Lehigh-Northampton 
County Planning Commission. 
Operations and results during fiscal year. New 
work, contract: Costs for preparation of DM for 
highway relocations were $3,623; preimpoundment 
and low flow measurement, $16,000. 
New work, hired labor: Miscellaneous engineering 
and design costs were $16,376. 
Condition at end of fiscal year. Work accomplished 
was advance engineering and design, 
which is 49 percent complete. 
36. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
To ascertain whether local interests were 
maintaining and operating completed projects as 
required, inspections were made as follows: 
Allentown, Pa., 20 December 1974; Bethlehem, 
Pa., 20 December 1974; East Branch, N. Y., 30 
December 1974; Chester, Pa., 26 December 
1976 and 21 April 1975; Mt. Holly, N.J., 12 
December 1974 and 23 April 1975. 
Local interests are satisfactorily maintaining 
and operating projects in accordance with regulation. 
Fiscal year costs were $3,484. Total costs 
were $43,691. 
3-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
37. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
(See Table 3-I at end of chapter.) 
38. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 
205, Public Law 838, 80th Congress, as 
amended (preauthorization). Also feasibility 
study pursuant to Emergency Bank Protection 
Authority provided by Section 14 of the 1946 
Flood Control Act. (See Table 3-J at end of 
chapter.) 
Emergency flood control activities - repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation). 
Federal fiscal year costs were $38,413 for 
advance preparation and $48,044 for flood 
emergency operations; and $3,005 for rehabilitation. 
MULTIPLE-PURPOSE PROJECTS 
INCLUDING POWER 
39. TOCKS ISLAND LAKE, PA., N. J., AND 
N. Y. 
Location. Damsite is on Delaware River about 
5 miles upstream from Delaware Water Gap and 
7 miles northeast of Stroudsburg, Pa. (See 
Geological Survey Quadrangle Sheet, Bushkill, 
Pa. and N.J.). 
Existing project. A multiple-purpose development 
project to provide supplies of water, flood 
control, production of hydroelectric power, and 
recreation. Plan of improvement provides for 
construction of an earth and rock fill dam, 
3,000 feet long, and 160 feet above riverbed; a 
spillway cut in rock of left abutment, and lined 
with concrete and provided with crest gates; a 
gate-co ntrolled outlet works, discharging 
through tunnels in rock along left bank regulating 
releases either through turbines in powerhouse 
at downstream end of conduits or through 
bypass channels in powerhouse structure. The 
lake, a unit of comprehensive plan for flood 
control and other purposes of Delaware River 
Basin, will have a reservoir capacity of 845,400 
acre-feet at top of spillway gates, with 96,300 
acre-feet of inactive storage and 425,600 acrefeet 
for water supply, power and recreation, and 
323,000 acre-feet for flood control. (For details 
see H. Doc. 522, 87th Cong., 2d sess.) Estimated 
cost of project (October 1975) $426,500,000 
including $117,900,000 required non-Federal 
reimbursement for costs allocated to water 
supply storage during life of project after use of 
this storage is initiated and reimbursement of 
$58,700,000 for power revenue; ultimate Federal 
cost is $249,900,000. Existing project was 
authorized by 1962 Flood Control Act (H. Doc. 
522, 87th Cong., 2d sess., contains latest published 
maps). 
Local cooperation. Project was approved, subject 
to certain requirements by local interests, as 
defined in House Document cited above. Delaware 
River Basin Commission on September 13, 
1965, adopted a resolution providing for repayment 
of water supply costs. 
Operations and results during fiscal year. New 
work, contract: Costs incurred were $2,382,619 
for land payments; relocation of cemeteries DM, 
$42, 560; design of U. S. Route 209, segment 4, 
$36,079; relocation of utilities, $47,482; protective 
works DM, Port Jervis, $12,851; design 
of Little Bushkill Bridge, $22,420; stream 
gaging, $11,680; historic study, $8,750; demolition 
of structures, $188,273; telephone services, 
$2,448; and DM, plans and specifications for 
Matamoras, $7,202. 
New work, hired labor: Costs for land acquisition 
were $157,795; operation and maintenance 
charges, $32,635; design and miscellaneous engineering 
costs, $234,679. 
Condition at end of fiscal year. Land acquisition 
is continuing and is approximately 51 
percent complete. Engineering and design work 
is approximately 60 percent complete. A credit 
of $77,384 received from Commonwealth of 
Pennsylvania in connection with Route 209. 
Public Law 93-393, Public Works for Water 
and Power Development and Atomic Energy 
Commission Appropriation Act, 1975, appropriated 
$1,500,000 for the re-evaluation of 
the Tocks Island Lake Project. 
GENERAL INVESTIGATIONS 
40. SURVEYS 
Fiscal year costs were $31,272 for navigation 
studies; $425,842 for flood control studies; and 
$58,490 for special stuides, a total of $515,604. 
41. COLLECTION AND STUDY OF BASIC 
DATA 
Costs and expenditures during fiscal year for 
flood plan information studies were $283,317. 
Studies of the following areas were in progress; 
Allegheny Creek, Pa.; Antietam-Heisters, Pa.; 
Cooper River and North Branch, N.J.; Crum 
Creek, Pa.; Darby Creek, Pa.; Delhi, N.Y.; East 
Branch, Perkiomen Creek, Pa.; Mantua Creek, 
N.J.; Maurice River, N.J.; Musconetcong River, 
N.J.; Pike Creek, Del.; Stony Creek, Pa.; Unami 
Creek, Pa.; Watson Creek, Pa.; and Zacharias 
Creek, Del. 
3-18

PHILADELPHIA, PA., DISTRICT 
TABLE 3-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Absecon Inlet, New Work 
N.J. Approp. 
Cost 
Maint. 
Approp. 
Cost 
138,270 153,676 
203,781 81,014 
- - 534,209' 
- - 534,209' 
14,000 329,500 5,115,9622 
88,065 329,946 5,115,806 
2. Aquatic Plant 
Control 
New Work 
Approp. 
Cost 
15,900 
3,516 
- -10,000 
7,131 5,034 
3. Barnegat Inlet, New Work 
N.J. Approp. 
Cost 
Maint. 
Approp. 
Cost 
4. Broadkill River New Work 
Del. Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. Cohansey River, New Work 
N.J. Approp. 
Cost 
Maint. 
Approp. 
Cost 
142,040 1,536,600 
101,753 1,483,549 
1,745,500 
1,759,304 
- 2,500 
- 2,241 
100 
93 
100 
102 
200 
194 
- 448,8493 
- 448,849 
191,250 5,943,979 
305,353 5,943,295 
- 68,228 
- 68,228 
- 243,641 
219 243,601 
2,000 
1,974 
146,7564 
146,7564 
633,436 
633,399 
6. Cold Spring 
Inlet, N.J. 
409 
- 879,275 s 
- 879,275 
94,000 1,545,627 
90,977 1,542,588 
- 1,134,346 
- 1,134,346 
7. Delaware Bay New Work 
Chesapeake Bay Approp. 
Waterway in Cost 
Delaware, 
Maryland and 
Virginia 
64,500 -30,000 
15,646 18,854 
250,000 125,000 409,500 
73,744 178,953 287,197 
8. Del. River at 
Camden, N.J. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,000 -1,000 
9. Delaware River New Work 
between Phila Approp. - - 
delphia, Pa., and Cost - - 
Trenton, N.J. Maint. 
Approp. 1,412,700 185,145 
Cost 1,77 6,923 111,785 
10. Delaware River New Work 
Pa., N.J. and Approp. - - 
Dela., Philadel- Cost - - 
phia to the Sea Maint. 
Approp. 5,307,900 6,334,169 
Cost 6,072,105 5,960,922 
Rehab. 
Approp. - - 
Cost - - 
2,500 
2,043 
- 462,906 
- 462,906 
- 332,962 
364 332,869 
- - 72,147,8006 
- - 72,147,800 
138,767 1,582,933 14,584,3857 
209,958 1,552,587 14,547,8127 
6,516,000 
6,883,051 
- 57,879,8728 
- 57,879,0288 
6,277,356 164,903,7919 
6,401,517 164,861,588 9 
- 508,324 
- 508,324 
3-19 
147 
82,900 
82,052 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
-361 
-361 
88,300 
87,875

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 3-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
11. Indian River 
Inlet and Bay, 
Del. 
12. Inland Waterway, 
Rehoboth 
Bay to Delaware 
Bay, Del. 
13. Inland Waterway 
from 
Chincoteague 
Bay, Va. to 
Delaware Bay, 
Del. 
14. Inland Waterway 
from Delaware 
River to Chesapeake 
Bay, Del. 
and Md. 
15. Little River, 
Del. 
16. Manasquan 
River, N.J. 
17. Murderkill 
River, Del. 
18. Neshaminy 
State Park 
Harbor, Pa. 
19. New Jersey 
Inlets & Beaches 
-Corson Inlet & 
Ludlam Beach 
20. New Jersey 
Inlets & Beaches 
-Great Egg 
Harbor Inlet & 
Peck Beach 
21. New Jersey 
Intracoastal 
Waterway 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
- 511,21010 
- 511,21010 
-4,000 
1,607 
13,385 
15,004 
2,900 
2,655 
4,291,900 
5,782,085 
3,668,161 
5,774,227 
125,500 
44,295 
11,355 
11,645 
3,024 
3,506 
2,814,000 
4,443,323 
3,159,131 
2,664,514 
- 124,300 
- 17,365 
80,330 
80,121 
74,400 
72,805 
327,000 
410,447 
10,500 
9,859 
4,000 
3,662 
1,834,000 
1,225,542 
1,834,000 
2,302,393 
-5,200 
101,417 
- 141,200 
- 108,576 
53,500 
5,390 
2,800 
51,582 
600 
1,593 
201,000 
201,544 
2,000 
2,325 
2,565,000 
2,780,867 
2,998,000 
3,010,153 
1,332,323 
1,332,134 
1,323,775 
1,323,775 
561,51411 
561,51411 
907,678 
907,581 
168,41212 
168,412 
76,9141 
76,8541 
131,707,5911 4 
131,099,35414 
60,972,5331 s 
60,892,7881 s 
- 12,016 
- 12,016 
- 268,462 
279 268,423 
- 1,112,8492 3 
- 1,112,849 
- 1,944,2352 4 
32,621 1,944,023 
- 37,630 
- 37,630 
- 468,744 
854 468,705 
- 128,203 
- 128,203 
- 50,000 
- 49,578 
- 65,000 
- 12,497 
2,450 
2,328 
54,601 
54,057 
93,000 158,000 
94,438 106,935 
- 125,000 53,000 178,000 
- 20,841 105,715 126,556 
- 71,54916 
- 71,549 
3-20

PHILADELPHIA, PA., DISTRICT 
TABLE 3-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
22. Schuylkill 
River, Pa. 
23. Wilmington 
Harbor, Del. 
29. Beltzville Lake, 
Pa. 
30. Blue Marsh 
Lake, Pa. 
31. Delaware Coast 
Protection, Del. 
32. Francis E. 
Walter Dam, Pa. 
33. General Edgar 
Jadwin Dam and 
Reservoir, Pa. 
34. Prompton Lake, 
Pa. 
35. Trexler Lake, 
Pa. 
39. Tocks Island 
Lake, Pa., N.J. 
and N.Y. 
Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
1,975,100 
2,132,451 
926,600 
652,745 
43,100 
303,299 
941,100 
1,347,899 
157,400 
109,641 
979,400 
1,288,094 
149,000 
57,316 
102,300 
89,052 
23,400 
29,098 
11,000 
36,000 
35,091 
158,900 
100,719 
12,298,700 
11,475,899 
1,751,209 
1,654,209 
285,600 
230,103 
-15,800 
94,940 
28,100 
121,601 
178,200 
217,844 
1,883,500 
1,853,100 
--67,000 
71,040 
40,000 
20,285 
163,099 
140,383 
26,301 
24,764 
2,329 
42,200 
38,475 
229,200 
223,379 
11,818,400 
12,101,500 
1,001,400 
1,297,168 
500,000 
457,336 
383,200 
431,111 
107,000 
109,558 
94,350 
113,742 
4,365,000 
4,476,953 
217,000 
191,020 
19,690 
151,400 
156,515 
23,450 
27,268 
2,618 
36,700 
43,364 
5,000 
65,243 
11,118,000 
11,387,183 
448,500 
365,503 
420,000 
823,656 
794,400 
742,813 
2,567 
119,825 
118,209 
6,885,000 
6,906,219 
25,000 
46,429 
241,275 
271,878 
21,600 
21,543 
41,000 
47,039 
59,200 
59,026 
34,000 
35,999 
3,000,000 
3,110,089 
1. Includes $226,497 for new work for previous 
projects. 
2. Includes $235,786 for maintenance for previous 
projects. 
3. Excludes $300,000 contributed funds. 
4. Includes $36,000 for new work for previous 
projects. 
5. Excludes $50,000 Navy Department and 
$100,000 contributed funds. 
6. Includes $2,489,173 for new work, for previous 
projects, $105,000 for preauthorization studies and minus 
$142,015 adjustment (new work) to Delaware River, 
Philadelphia to Sea project from this project under the 
1954 modification. 
3-21 
10,867,47117 
10,726,876 
1,196,581 
1,196,581 
3,334,00718 
3,334,007 
18,433,133 
18,422,622 
1,954,7259 
1,954,72519 
14,603,46520 
14,544,22420 
22,931,831 
22,931,157 
639,775 
635,525 
16,147,400 
15,998,128 
374,000 
369,449 
11,127,43221 
11,127,40721 
1,546,121 
1,531,989 
4,073,105 
4,073,105 
612,264 
612,051 
4,609,48322 
4,609,46922 
599,216 
597,406 
988,521 
986,591 
59,224,187 
59,030,282

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 3-A (continued) COST AND FINANCIAL STATEMENT 
7. Includes $552,720 for maintenance for previous 16. Excludes $1,824,940 Navy Department funds 
projects. and $99,000 contributed funds expended for new work. 
8. Excludes $12,976,058 for new work for previous 17. Excludes $286,953 Navy Department funds exprojects 
and $142,015 adjustment from Delaware River, pended for maintenance. 
Philadelphia to Trenton, N.J. under 1954 modification. 18. Includes $525,000 for previous projects. 
9. Includes $1,025,409 for maintenance of previous 19. Includes $402,121 for new work for previous 
projects. project. 
10. Excludes $10,000 for previous project and 20. Excludes $60,000 contributed funds expended 
$210,000 contributed funds. for maintenance. 
11. Excludes $60,000 contributed funds. 21. Includes $40,000 appropriated and $39,975 ex- 
12. Entire amount expended on previous project re- pended under Code 710 Recreation Facilities. 
pealed in 1905. 22. Includes $74,000 appropriated and $66,498 ex- 
13. Excludes $2,000 contributed funds and includes pended under Code 710 Recreation Facilities. 
$25,330 for maintenance for previous projects. 23. Includes $39,000 for new work for previous 
14. Includes $10,709,755 for new work for previous projects. Excludes $300,000 contributed funds exprojects. 
pended on new work. 
15. Includes $6,093,748 for maintenance for previ- 24. Includes $2,054 for maintenance for previous 
ous projects. projects. 
TABLE 3-B 
Acts 
Sept. 22, 1922 
July 24, 1946 
Aug. 30, 1935 
Aug. 26, 1937 
July 24, 1946 
Mar. 2, 1907 
Aug. 26, 1937 
Mar. 2, 1907 
Mar. 2, 1945 
July 3, 1930 
Aug. 30, 19352 
Aug. 30, 19352 
Aug. 26, 1937 
July 24, 1946 
AUTHORIZING LEGISLATION 
Work Authorized 
ABSECON INLET, N.J. (See Section 1 of Text) 
An inlet entrance channel 20 feet deep. 
A channel 15 feet deep into Clam Creek and a turning basin. 
BARNEGAT INLET, N.J. (See Section 3 of Text) 
An 8-foot depth through inlet to Oyster Creek Channel across 
inner bar, 10-foot depth through outer bar and for jetties. 
A channel of suitable hydraulic characteristics from gorge to 
Oyster Creek Channel, and thence to deep water in bay. 
Maintenance dredging of channel to connect main inlet channel 
with Barnegat City Harbor. 
COHANSEY RIVER, N.J. (See Section 5 of Text) 
Channel 7 feet deep over entire project. 
Channel 12 feet deep to Glass Street, thence 8 feet to Commerce 
Street, with turning basin. 
COLD SPRING INLET, N.J. (See Section 6 of Text) 
An inlet channel 25 feet deep and jetties. 
A 20-foot channel to deep water in harbor. 
DELAWARE RIVER BETWEEN PHILADELPHIA, PA., AND 
TRENTON, N.J. (See Section 9 of Text). 
A channel 28 feet deep, 300 feet wide between Allegheny Ave., 
Philadelphia, Pa. and Delair Bridge. 
Channel 25 feet deep from Delair Bridge to Trenton, N.J., and 
maintenance of 12-foot channel from upper end of 25-foot 
project to Penn Central R.R. Bridge at Ferry St., Trenton 
Auxiliary channel, 20 feet deep east of Burlington Island. 
A cross channel 8 feet deep, opposite Delanco, N.J. 
Anchorage at mouth of Biles Creek 
Documents 
H. Doc. 375, 67th Cong., 
2d sess. 
H. Doc. 504, 79th Cong., 
2d sess.1 
Rivers and Harbors Committee 
Doc. 19, 73d 
Cong., 2d sess.1 
Rivers and Harbors Committee 
Doc. 85, 74th 
Cong., 2d sess.1 
H. Doc. 358, 79th Cong., 
2d sess.l 
H. Doc. 645, 59th Cong., 
1st sess.l 
Senate Committee print, 
75th Cong., 1st sess. 
H. Doc. 388, 59th Cong., 
2d sess. 
H. Doc. 262, 77th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 3, 71st 
Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 11, 73d 
Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 66, 74th 
Cong., 1st sess.1 
Rivers and Harbors Committee 
Doc. 90, 74th 
Cong., 2d sess. 
H. Doc. 679, 79th Cong., 
2d sess. 
3-22

TABLE 3-B (continued) 
PHILADELPHIA, PA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 3, 1954 
June 25, 1910 
July 3, 1930 
Aug. 30, 19353 
June 20, 19384 
Mar. 2, 19455 
Mar. 2, 19455 
Mar. 2, 19455 
Sept. 3, 1954 
July 3, 1958 
Aug. 26, 1937 
Mar. 2, 1945 
July 25, 1912 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 30, 1935 
Aug. 7, 1939 
A channel 40 feet deep and 400 feet wide between Allegheny 
Ave., Philadelphia, Pa., and upstream end of Newbold Island, 
thence 35 feet deep to Trenton Marine Terminal and turning 
basin to 800 feet wide. Relocate channel at railroad bridge at 
Delair and suitably reconstruct bridge. Construct necessary 
bank protection works; and eliminate authorized anchorage 
near mouth of Biles Creek, Pa. 
DELAWARE RIVER, PA., N.J., AND DEL., PHILADELPHIA 
TO THE SEA (See Section 10 of Text) 
Channel 35 feet deep from Allegheny Ave., Philadelphia, Pa., to 
Delaware Bay. 
Anchorages 35 feet deep at Port Richmond and Mantua Creek, a 
30 foot anchorage at Gloucester, N.J.,.and extend 1,000 foot 
channel in Philadelphia Harbor to Horseshoe Bend. 
An anchorage 35 feet deep at Marcus Hook, Pa. 
A channel 37 feet deep from Philadelphia--Camden Bridge to 
Navy Yard, thence 40 feet deep to deep water in Delaware Bay. 
A 37-foot depth in channel from Allegheny Ave., Philadelphia, 
Pa., to Philadelphia-Camden Bridge and in anchorage at Port 
Richmond. 
A 37-foot depth in an enlargement of anchorages near Mantua 
Creek and Marcus Hook. 
Maintain enlarged channel opposite Philadelphia Navy Yard. 
A channel from Allegheny Ave., to Naval Base 40 feet deep, 
400 feet wide along west side of channel through Philadelphia 
Harbor and 500 feet wide through Horseshoe Bend. 
Anchorages at Reedy Point, Deepwater Point, Marcus Hook, and 
Mantua Creek, 40 feet deep and 2,300 feet wide with mean 
lengths of 8,000, 5,200, 13,650 and 11,500 feet respectively. 
INDIAN RIVER INLET AND BAY, DEL. (See Section 11 of 
Text) 
A 15-foot inlet channel, steel and stone jetties, 6 foot channel 
from end of inlet channel to deep water in the bay and 
authority to modify interior inlet channel. 
A 9 foot channel from inlet to Old Landing, including basin, 
and 4 foot channel to highway bridge at Millsboro. 
INLAND WATERWAY, REHOBOTH BAY TO DELAWARE 
BAY, DEL. (See Section 12 of Text) 
For a 6-foot depth canal to connect Rehoboth Bay and 
Delaware Bay. 
For a 6 foot depth entrance near Lewes, for jetties, for 
widening the canal from Broadkill River to Lewes, and basin. 
For a 10-foot depth from Delaware Bay to Lewes and in basin, 
and for extending jetties.6 
INLAND WATERWAY FROM DELAWARE RIVER TO 
CHESAPEAKE BAY, DEL. AND MD. (See Section 14 
of Text) 
A sea level channel 27 feet deep, 250 feet wide from Delaware 
River to Elk River and 400 feet wide down Elk River and 
Chesapeake Bay to deep water at or near Pooles Island; 
alter existing bridges over canal; enlarge Delaware City 
Branch Channel to 8 feet deep and 50 feet wide, with a basin 
same depth, and revetment of both banks east of Fifth Street; 
enlarge anchorage and mooring basin in Back Creek to 400 
feet wide, 1,000 feet long, and 12 feet deep; extend jetties at 
Reedy Point; and construct bulkheads. 
Construct a 4-lane high-level fixed highway bridge at or near 
St. Georges. 
H. Doc. 358, 83d Cong., 
2d sess. 1 
H. Doc. 733, 61st Cong., 
2d sess. 
H. Doc. 304, 71st Cong., 
2d sess.l 
Rivers and Harbors Committee 
Doc. 5, 73d 
Cong., 1st sess. 
S. Doc. 159, 75th Cong., 
3d sess.1 1 
H. Doc. 580, 76th Cong., 
3d sess. 1 1 
H. Doc. 340, 77th Cong., 
1st sess. 1 
Specified in Act. 
H. Doc. 358, 83d Cong., 
2d sess. 1 
H. Doc. 185, 85th Cong., 
1st sess. 
River and Harbors Committee 
Doc. 41, 75th 
Cong., 1st sess. 
H. Doc. 330, 76th Cong., 
1st sess.1 
H. Doc. 823, 60th Cong., 
1st sess. and Rivers and 
Harbors Committee 
Doc. 51, 61st Cong., 
3rd sess. 
Rivers and Harbors Committee 
Doc. 56, 75th 
Cong., 1st sess.1 
H. Doc. 344, 77th Cong., 
1st sess. 1 
H. Doc. 201, 72d Cong., 
1st sess. and Rivers 
and Harbors 
Committee Docs. 18 and 
24, 73d Cong., 2d sess. 1 
Public Law 310, 76th 
Cong., 1st sess. 
3-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 3-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 3, 1954 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 8, 1917 
July 3, 1930 
July 24, 1946 
June 3, 1896 
July 25, 1912 
Sept. 22, 1922 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 19358 
Oct. 17, 1940 
July 14, 1960 
A channel 35 feet deep and 450 feet wide from Delaware River 
through Elk River and Chesapeake Bay at water of that depth 
in the bay, including a cutoff at Penn Central Railroad 
crossing, with a minimum radius of curvature of 7,000 feet 
at bends; a high level fixed railroad bridge over cutoff; high 
level fixed highway bridge at Reedy Point and Summit; and 
an anchorage in Elk River 35 feet deep and 1,200 feet wide, 
averaging 3,700 feet long. 
MANASQUAN RIVER, N.J. (See Section 16 of Text) 
Channel 8 feet deep and provision of works designed to secure 
channel. 
Widening channel on northerly side. 
Deepening channel to 12 and 14 feet, 10 and 12 foot anchorages. 7 
SCHUYLKILL RIVER, PA. (See Section 22 of Text) 
Depths of 35 feet from mouth to Girard Point, thence 30 feet, 
26 feet, and 22 feet to University Avenue Bridge, Philadelphia. 
A depth of 30 feet instead of 35 feet between the mouth and the 
conditional restoration and maintenance of the channel below 
Passyunk Ave., by the United States. 
A depth of 33 feet from the channel in Delaware River to 
Passyunk Ave., restoration of the project channel dimensions 
between Passyunk Ave. and University Ave., and full 
maintenance of the entire project. 
WILMINGTON HARBOR, DEL. (See Section 23 of Text) 
Depths of 21, 10, and 7 feet and jetties. 
Purchase or construct a dredge and auxiliaries including a 
wharf and depot, and maintenance of project. 
Entrance channel and basin with 25-foot depth and construction 
by local interests of new south jetty. 
A 30 foot depth between Delaware River and Lobdell Canal and 
modification or removal of a portion of north jetty. 
Completion of new south jetty by the United States; subject 
to provision that city of Wilmington reimburse the United 
States for cost, without interest, of any part of structure that 
may subsequently be occupied and utilized for city activities. 
Permit temporary occupancy by city of Wilmington of any part 
of south jetty for city activities under revocable license, 
provided occupied portion of jetty is properly maintained 
without expense to the United States. 
A 35-foot depth between Delaware River ship channel and 
Lobdell Canal including turning basin of same depth, opposite 
Wilmington Marine Terminal, 200 feet wide, 2,900 feet long 
on north side of channel, and 2,000 feet long on north side 
of basin. 
S. Doc. 123, 83d Cong., 
2d sess. 1 
H. Doc. 482, 70th Cong., 
2d sess. 
Senate Committee Doc., 
74th Cong., 1st sess. 
H. Doc. 356, 77th Cong., 
1st sess. 1 
H. Doc. 1270, 64th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 40, 71st 
Cong., 2d sess.1 
H. Doc. 699, 79th Cong., 
2d sess. 1 
H. Doc. 66, 54th Cong., 
1st sess. 
Annual Report, 1896, 
p. 973; 
Annual Report 1897, 
p. 1250.1 
H. Doc. 359, 62d Cong., 
2d sess. 
H. Doc. 114, 67th Cong., 
1st sess. and S. Committee 
Print, 68th 
Cong., 1st sess. 
Rivers and Harbor Committee 
Doc. 20, 71st 
Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 32, 73d 
Cong., 2d sess. 
H. Doc. 658, 76th Cong., 
3d sess. 
S. Doc. 88, 86th Cong., 
2d sess. 
1. Contains latest published maps. 
2. Also Public Works Administration, September 6, 
1933, and Emergency Relief Administration, May 28, 
1935. 
3. Also Public Works Adminstration, September 6, 
1933. 
4. Channel 37 feet deep and 600 feet wide from 
Naval Base to Philadelphia-Camden Bridge, deferred for 
restudy. 
5. Channel 37 feet deep and 600 feet wide from 
Philadelphia-Camden Bridge to Allegheny Avenue, Deferred 
for restudy. 
6. Extension of jetties considered to be inactive. 
7. The 10 and 12 foot anchorages are considered 
inactive. 
8. Also May 28, 1935, under Emergency Relief Administration. 
3-24 
--

PHILADELPHIA, PA., DISTRICT 
TOTAL COSTS FOR EXISTING PROJECTS TO JUNE 30, 1975 
Text Project 
9. Delaware River between 
Philadelphia, 
Pa., and Trenton, 
N.J. 
10. Delaware River, Pa., 
N.J. and Del., 
Philadelphia 
to the Sea 
Funds 
Public Works 
Emergency 
Relief 
Regular 
Totals 
Public Works 
Regular 
Totals 
New Work 
$ 2,189,956 
2,636,456 
64,727,215 
$69,553,627 
813,046 
44,089,923 
$44,902,969 
Maintenance 
$ 13,853,872 
$ 13,853,872 
$163,095,742 
$163,095,742 
Rehabilitation 
$508,324 
$508,324 
Totals 
$ 2,189,956 
2,636,456 
78,581,087 
$83,407,499 
$ 813,046 
207,693,989 
$208,507,035 
TABLE 3-D 
Type of Work 
Channels: 
Excavation of Borrow Area 
and Dredging Secs. 1 & 2 
Other Items: 
Bank Stabilization, 
Phase II 
Bridge over Fossil Area 
Recreation Facilities, 
Summit, North Area 
TABLE 3-E 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
Inland Waterway from Delaware River 
to Chesapeake Bay, Del. and Md. 
(See Section 14 of Text) 
New Work Contracts 
Quantity 
Removed 
Location (Cu. Yds.) Cost 
$1,782,820 
- 517,025 
- 56,495 
- 30,750 
Status 
Complete 
Continued 
Complete 
Continued 
RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 24 of Text) 
Project 
Indian River Inlet and Bay, Del. 
TABLE 3-C 
See 
Section 
in 
Date Survey Conducted 
October 1972 
3-25 
II

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 3-F OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Absecon Creek, N.J.' 1969 11,935 167,426* 
Alloway Creek, N.J.' 1931 21,398 35,786 
Appoquinimink River, Del. 1931 36,973 41,270 
Big Timber Creek, N.J.' 1962 58,6652 53,894* 
Chester River, Pa.3 1931 6,000 1,139 
Cooper River, N.J.' 1962 33,102 379,163* 
Delaware River, N.Y., N.J., and Pa., 
at or near mouth of Neversink River4 1917 
Dennis Creek, N.J.' 1897 4,701 - 
Double Creek, N.J.' 1912 7,800 - s 
Goshen Creek, N.J.' 1905 15,359 870 
Harbor of Refuge, Delaware Bay, Del.' 1964 5,162,230 405,408* 
Ice Harbor at Marcus Hook, Pa.L,6 1928 208,964 14,336 
Ice Harbor at New Castle, Del. 1,6 1898 224,704 - 
Leipsic River, Del.' 1931 36,956 32,345 
Little Egg Harbor, N.J.', 4 - 15,048 
Mantua Creek, N.J. 1966 169,6878 339,099* 
Maurice River, N.J. 1948 - 
Channel 8 feet deep, Delaware Bay to mouth9 
Delaware Bay to Millville - 143,98410 137,050 
Mispillion River, Del.'' 1965 631,339 612,215* 
Oldmans Creek, N.J. 1941 31,188 32,125 
Pepper Creek, Del.' 1965 138,094 1,797* 
Raccoon Creek, N.J.' 1966 83,65512 319,993* 
Rancocas River, N.J. 1942 44,500 13,090 
St. Jones River, Del.. 1961 
Delaware Bay to Lebanon' 3 - 207,102 66,093 
Jetties and new entrance at mouth9 
Salem River, N.J. 1961 - 1,792* 
Delaware River to fixed bridge' 4 
- 107,634' S 287,479 
Penns Neck Bridge to fixed bridge' 6 
Schuylkill River above Fairmount Dam, Pa.' 1955 4,291,810 - s 
Smyrna River, Del. 1949 
Delaware River to Wharf at Smyrna Landing' 7 -198,844 197,327 
Wharf at Smyrna Landing to fixed bridge 9 
Toms River, N.J. 1950 - - 
Channel 5 ft. deep' - 10,050 33,311 
Channel 12 feet deep 9 
Tuckerton Creek, N.J. 1972 60,242 399,930* 
Woodbury Creek, N.J.' 1940 27,093'9 56,474 
Waterway from Indian River Inlet to Rehoboth Bay, Del. 1974 90,9082 0 41,002 
3-26

PHILADELPHIA, PA., DISTRICT 
TABLE 3-F (continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
1. Completed. 
2. Excludes $50,000 contributed funds expended 
for new work. 
3. Includes $6,000 new work and $63 maintenance 
funds expended on previous projects. 
4. Abandonment recommended in House Document 
467, 69th Congress, 1st Session. 
5. Maintenance assumed by local interests. 
6. Harbor not now required by commerce. 
7. Last appropriation for project was in 1852. No 
information is at hand relative to work done. 
8. Includes $3,000 for new work for previous projects.
9. Deferred. 
10. Includes $43,000 new work funds expended on 
previous projects. 
11. Includes $148,798 for new work and $61,172 
for maintenance of previous projects and $253,491 for 
minor rehabilitation for existing project. 
12. Includes $757 new work funds expended on previous 
projects. 
13. Includes $54,590 new work and $28,935 maintenance 
funds expended on previous projects. 
14. Includes $55,809 new work and $48,000 maintenance 
funds expended on previous projects. 
15. Exclusive of $51,825 contributed by local interests. 
16. Deferred. Dredged under previous project to 9 
foot depth. 
17. Includes $55,085 new work and $22,723 maintenance 
funds expended on previous projects. 
18. In addition $20,000 expended for new work 
from contributed funds. 
19. Includes $2,950 new work funds expended on 
previous projects. 
20. Excludes $20,000 contributed funds. 
*Operation and maintenance figure includes cost incurred for preparation of environmental impact statements. 
TABLE 3-G OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance1 
Atlantic City, N.J. 1972 2,083,289 
Barnegat Light, N.J. 1964 70,908 
Cape May City, N.J. 1961 22,9572 
Long Beach Island, N.J. 1964 40,665 
North Wildwood, N.J. 1961 -- 
Ocean City, N.J. 1969 395,831- 
Rehoboth Beach to Indian River Inlet, Del. 1965 326,116 
Stone Harbor, N.J. 1961 -- 
Ventnor, Margate and Longport, N.J. 1961 -- 
1. Operation and maintenance required by law to 3. Excludescostof $1,146,325 to local interests and 
be assumed by local interests. $272,766 Federal participation expended under Public 
2. Excludes $58,585 Accelerated Public Works Works Acceleration Program for extension of five existfunds 
expended for extension to two groins. ing groins completed 11 May 1964. 
TABLE 3-H BEACH EROSION CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 1 
(See Section 28 of Text) 
Project Fiscal Year Costs 
Broadkill Beach, Sussex County, Del. $ 5,380 
Lewes, Del. $76,755 
1. Beach erosion control activities pursuant to Section 103, Public law 87-874 (Preauthorization). 
3-27

TABLE 3-I 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Allentown, Lehigh River, Pa. 1961 1,615,581 - 1 
Aquashicola Reservoir, Pa.2 1963 - - 
Bethlehem, Pa. 1966 4,520,995 - 1 
Maiden Creek Reservoir, Pa.2 1963 - - 
Mt. Holly, N.J. 1946 283,665 - 1 
1. Maintenance assumed by local interests as re- 2. New project. 
quired by authorizing project. 
TABLE 3-J FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION' 
(See Section 38 of Text) 
STUDY FISCAL YEAR COST 
Belvidere, Warren County, N.J. $ 5,946 
Gibbstown, N.J. $53,022 
Liberty, Sullivan County, N.Y. $13,363 
Little Mill Creek, New Castle County, Del. $ 1,965 
Nesquehoning, Carbon County, Pa. $36,040 
Temple, Berks County, Pa. $ 1,669 
Trout Creek, Tredyffrin Township, Pa. $38,212 
Stony Creek, Norristown, Pa. $63,328 
1. Flood control activities pursuant to Section 205, Public Law 838, 80th Congress, as amended (preauthorization). 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 2 
(See Section 38 of Text) 
STUDY FISCAL YEAR COST 
Pocono Creek, Stroud Township, Pa. 
2. Feasibility study pursuant to emergency bank protection, provided by Section 14 of the 1946 Flood Control Act. 
3-28

BALTIMORE, MD., DISTRICT* 
This district comprises the watershed of 
Susquehanna River and its tributaries from 
headwaters in south central New York State 
through central Pennsylvania to its mouth in 
Chesapeake Bay; watershed of the Potomac River 
and its tributaries from headwaters in Maryland, 
eastern West Virginia, and northern Virginia to 
its mouth in Chesapeake Bay; District of 
Columbia; and southwestern portion of 
Delaware. It includes that portion of Chesapeake 
Bay and its tributaries north of Smith Point, Md., 
on western shore of the bay, and includes that 
portion of Maryland between Chesapeake Bay 
and Atlantic Ocean. 
IMPROVEMENTS 
Navigation (Continued) 
1. Baltimore Harbor and Channels, 
M d ......................... ....... 4-2 
2. Baltimore Harbor, Md., Collection 
and Removal of Drift .............. 4-4 
3. Chester River, Md. ................. 4-4 
4. Choptank River, Md................ 4-5 
5. Harbor of Baltimore, Md., Prevention 
of Obstructions and Injurious 
Deposits .......................... 4-5 
6. Knapps Narrows, Md. .............. 4-5 
7. Nanticoke River at Bivalve, Md...... 4-6 
8. Neabsco Creek, Va ................ 4-6 
9. Ocean City Harbor and Inlet and 
Sinepuxent Bay, Md ............... 4-7 
10. Potomac and Anacostia Rivers, 
D.C., C6llection and Removal of 
Drift ............................. 4-7 
11. Potomac River and Tributaries at 
and below Washington, D.C., 
Elimination of Waterchestnut ....... 4-8 
12. Slaughter Creek, Md. .............. 4-8 
13. Tred Avon River, Md .............. 4-8 
14. Twitch Cove and Big Thorofare, 
Md................................ 4-9 
15. Upper Thorofare, Deal Island, Md. .. 4-9 
16. Washington Harbor, D. C. .......... 4-10 
17. Wicomico River, Md .............. 4-10 
18. Reconnaissance and Condition 
Surveys ......................... 4-11 
*All cost and financial statements and authorizing legislation 
for projects are listed at the end of this chapter. Additionally, 
19. Other Authorized Navigation 
Projects .......................... 
20. Navigation work under special 
authorization ..................... 
4-11 
4-11 
Beach Erosion Control 
21. Other Authorized Beach Erosion 
Control Projects .................. 4-11 
22. Beach Erosion Control work under 
special authorization ................ 4-11 
Flood Control 
23.. Anacostia River and Tributaries, 
Flood Protection and Navigation 
Improvements, D.C. and Md. ........ 4-11 
24. Anacostia River and Tributaries, 
Prince Georges County, Md. ........ 4-12 
25. Bloomington Lake, North Branch, 
Potomac River, Md. and Va. ........ 4-12 
26. Cumberland, Md., and Ridgeley, 
W . Va. ............................ 4-13 
27. Fourmile Run, Va.................. 4-13 
28. Lackawanna River Basin, Pa. ....... 4-14 
28A. Aylesworth Creek Lake, Pa. ........ 4-14 
29. Raystown Lake, Raystown Branch, 
Juniata River, Pa.................. 4-14 
30. Southern New York Flood Control 
Projects .......................... 4-15 
30A. Addison, N.Y. .................... 4-15 
30B. Almond Lake, N.Y. ................. 4-15 
30C. Arkport Dam, N.Y................... 4-15 
30D.Avoca, N.Y. ....................... 4-16 
all tables which are referenced in text appear at the end of this 
chapter. 
4-1 
Navigation Page Page

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (Continued) Page 
30E. Binghamton, N.Y. ................ 4-16 
30F. Canisteo, N.Y. .................... 4-16 
30G. Corning, N.Y. ...................... 4-17 
30H.East Sidney Lake, N.Y ............. 4-17 
301. Elmira, N.Y. ....................... 4-18 
30J. Hornell, N.Y ....................... 4-18 
30K. Lisle, N.Y. ....................... 4-18 
30L. Oxford, N.Y. ..................... 4-19 
30M.Whitney Point Lake, N.Y. ............ 4-19 
30N. Whitney Point Village, N.Y. ........ 4-19 
31. Stillwater Lake, Lackawanna River, 
Pa. ................................. 4-20 
32. Susquehanna River Flood Control 
Project, N.Y. and Pa ................ 4-20 
32A. Cowanesque Lake, Pa. .............. 4-20 
32B. Tioga-Hammond Lakes, Pa.......... 4-20 
33. Tyrone, Pa. ...................... 4-21 
34. West Branch of Susquehanna River, 
Pa. ............................... 4-21 
34A. Alvin R. Bush Dam, Pa. .......... 4-21 
34B. Curwensville Lake, Pa ............. 4-22 
34C. Foster Joseph Sayers Dam, Pa....... 4-22 
35. York, Codorus Creek, Pa............ 4-22 
Navigation 
1. BALTIMORE HARBOR AND 
CHANNELS, MD. 
Location. Baltimore Harbor is at head of 
navigable portion of Patapsco River about 12 
miles from Chesapeake Bay. River rises near 
town of Westminister in Carroll County, Md., and 
flows generally southeast for about 65 miles to 
enter Chesapeake Bay. (See Coast and Geodetic 
Survey Chart 549). 
Previous project. For details see page 274 of 
Annual Report for 1963. 
Existing project. 
a. A uniform main channel depth of 50 feet 
between Cape Charles, Va., and Fort McHenry at 
Baltimore, Md., with dimensions as follows: (1) 
Cape Henry Channel: 50 feet deep and 1,000 feet 
wide from the 50-foot depth curve in the Atlantic 
Ocean to that depth in Chesapeake Bay, a 
distance of 2.3 miles; (2) York Spit Channel: 50 
feet deep and 1,000 feet wide connecting the 50- 
foot depth curves in Chesapeake Bay near York 
Spit, a distance of 18.2 miles; (3) Rappahannock 
Shoal Channel: 50 feet deep and 1,000 feet wide 
connecting the 50-foot depth curves in the 
Chesapeake Bay opposite the Rappahannock 
River, a distance of 9.9 miles; and (4) Baltimore 
Harbor Approach Channels: 50 feet deep and 
generally 800 feet wide, widened at the approach 
and bends, from the 50-foot depth curve in 
Flood Control (Continued) Page 
36. Inspection of Completed Flood 
Control Works .................... 4-23 
37. Scheduling Flood Control Reservoir 
Operations ........................ 4-23 
38. Other Authorized Flood Control 
Projects ............................ 4-23 
39. Flood Control Work under Special 
Authorization ..................... 4-23 
Water Supply 
40. Potomac Estuary Pilot Water 
Treatment Plant, D.C., Md., and 
Va. ................................. 4-23 
41. Verona Lake, Va .................. 4-23 
General Investigations 
42. Surveys ............................. 4-24 
43. Collection and Study of Basic Data ... 4-24 
Miscellaneous Activities 
44. Maintenance Operation and capital 
Outlay of the Washington Aqueduct .. 4-24 
Chesapeake Bay opposite the mouth of the 
Magothy River to Fort McHenry on the Patapsco 
River, a distance of 20.5 miles. 
b. Branch channels with dimensions as 
follows: (1) Connecting Channel to Chesapeake 
and Delaware Canal Approach Channel: 35 feet 
deep, 600 feet wide, and 13.0 miles long from the 
Cutoff-Brewerton Angle in the main channel to 
the 35-foot depth curves in the natural channel on 
the east side of Chesapeake Bay which is part of 
the inland waterway from Delaware River to 
Chesapeake Bay. The channel includes the 
Brewerton Extension and Swan Point and 
Tolchester Sections; (2) Curtis Bay: 50 feet deep, 
600 feet wide, and 2.2 miles long from the main 
channel to and including a 950-foot wide turning 
basin at the head of Curtis Bay; (3) Curtis Creek: 
(a) a channel, 35 feet deep and generally 200 feet 
wide, from the 50-foot channel in Curtis Bay to 
750 feet downstream of the Pennington Avenue 
Bridge; (b) a channel, 22 feet deep and generally 
200 feet wide, from the 35-foot channel to and 
along the marginal wharf of the Curtis Bay 
Ordinance Depot; (c) an irregular shaped 3-acre 
basin, with a depth of 18 feet, adjacent to the 
head of the 22-foot channel; (d) a basin, 15 feet 
deep and 450 feet wide, from the end of the 22-foot 
channel to the end of the marginal wharf; and (e) 
a channel, 22 feet deep and 200 feet wide, from 
the 22-foot channel south of the Baltimore and 
Ohio Railroad Bridge to the vicinity of Arundel 
Cove, a distance of 2,800 feet, thence 100 feet wide 
4-2

BALTIMORE, MD., DISTRICT 
in Arundel Cove for a distance of 2,100 feet, with 
an anchorage basin, 700 feet square, adjacent to 
the channel and southwest of the wharf of the 
Coast Guard Depot at Curtis Bay;, (4) Middle 
Branch: (a) Ferry Bar East Section: a channel, 42 
feet deep and 600 feet wide, from the main 
channel at Fort McHenry to Ferry Bar, a 
distance of 1.4 miles; (b) Ferry Bar West Section: 
a channel, 35 feet deep and 400 feet wide, from 
the Ferry Bar East Section to Ferry Bar, a 
distance of 0.8 mile: (c) Spring Garden Section: a 
channel, 27 feet deep and 250 feet wide, from 
Ferry Bar to and including a turning and 
anchorage basin immediately below the Western 
Maryland Railway Bridge, a distance of 1.0 mile; 
and (5) Northwest Branch; Federal maintenance 
of 39-foot or 35-foot deep channels after either 
depth has been provided by local interest: (a) East 
Channel: a channel, 49 feet deep, 600 feet wide, 
and 1.3 miles long with a turning basin at the 
head of the channel from that depth existing at 
the time of construction; and (b) West Channel: a 
channel, 40 feet deep, 600 feet wide, and 1.2 miles 
long with a turning basin at the head of the 
channel from that depth existing at the time of 
construction. 
c. The following anchorages: (1) Quarantine 
Anchorage: 35 feet deep, 3,500 feet long, and 600 
feet wide; (2) Riverview Anchorage No. 2: 30 feet 
deep, 2,400 feet long, and 1,200 feet wide; (3) 
Riverview Anchorage No. 1: 35 feet deep, 4,500 
feet long, and 1,500 feet wide: and (4) Fort 
McHenry Anchorage: 35 feet deep, 3,500 feet 
long, and 400 feet wide. 
The mean range of tide is 2.8 feet at the Cape 
Henry Channel, 2.3 feet at the York Spit Channel, 
1.4 feet at the Rappahannock Shoal Channel, 0.8 
foot at the Craighill Entrance, 0.9 foot in the 
Cutoff Section, 1.1 feet at Fort McHenry, and 1.2 
feet at Pooles Island in the upper Chesapeake 
Bay. Depths refer to mean low water. 
Estimated cost (1975) for a new work, exclusive 
of amounts expended on previous projects, is 
$147,130,000 of which $8,330,000 is for 
completed work through the River and Harbor 
Act of 1945, $24,700,000 for work authorized by 
the River and Harbor Act of 1958, and 
$114,100,000 for work authorized by the River 
and Harbor Act of 1970. 
Widening 35-foot depth from Port Covington 
channel from 150 to 400 feet to Ferry Bar, 
widening 27-foot depth channel from 150 to 250 
feet to Hanover Street Bridge, and providing a 
channel 27 feet deep by 250 feet wide to Western 
Maryland Railway bridge with an anchorage and 
turning basin at upper end is considered inactive 
and excluded from foregoing estimate. 
Estimated cost (1954) of this portion is $1,603,000. 
Local cooperation. Fully complied with for 
improvements authorized under River and 
Harbor Act of 1945 and prior acts. River and 
Harbor Act of 1958 requires local interests 
furnish lands, rights-of-way, and spoil disposal 
area for construction and future maintenance, 
hold the United States free from damages, and 
provide and maintain all necessary alterations in 
sewer, water supply, drainage, and other 
utilities. Local interests gave formal assurance 
that terms will be complied with. River and 
Harbor Act of 1970 requires local interest to: (a) 
provide without cost to the United States all 
lands, easements, and rights-of-way required for 
construction and subsequent maintenance of the 
project and for aids to navigation upon the 
request of the Chief of Engineers, including 
suitable areas determined by the Chief of 
Engineers to be required in the general public 
interest for initial and subsequent disposal of 
dredged material and necessary retaining dikes, 
bulkheads, and embankments therefor, or the 
costs of such retaining works; (b) hold and save 
the United States free from damages that may 
result from the construction and maintenance of 
the project; (c) provide and maintain at local 
expense adequate public terminal and transfer 
facilities open to all on equal terms, and depths in 
berthing areas and local access channels serving 
terminals commensurate with the depth 
provided in the related project area; (d) 
accomplish without cost to the United States such 
utility and other relocations or alterations as 
necessary for project purposes; (e) prohibit 
erection of any structure within 125 feet of the 
project channel or turning basin; and (f) establish 
regulations prohibiting discharge of pollutants 
into the waters of the channels and harbor by 
users thereof, which regulations shall be in 
accordance with applicable laws or regulations of 
Federal, State, and local authorities responsible 
for pollution prevention and control. 
Terminal facilities. The Port of Baltimore has 
45 miles of waterfront of which 25 miles are 
industrially developed. There are 94 covered and 
open overseas piers for the loading and 
discharging of 173 ships, providing 84 general 
cargo, 65 specialized cargo, and 24 public bulk 
cargo berths. The existing ground storage is 
equivalent to 53,700 railroad cars of cargo. There 
are 31 public general merchandise warehouses, 
with 4.9 million square feet of storage space and 
4.7 million cubic feet of cold storage space. Eight 
ship-building, ship repair, and ship dismantling 
yards are available for handling up to 90 vessels. 
The three grain elevators in the port have a 
capacity of about 13 million bushels. Latest 
description of terminal facilities is in "Port Series 
No. 10 (revised 1966)" on Port of Baltimore, Md., 
issued by Board of Engineers for Rivers and 
Harbors. 
4-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. New 
Work, Baltimore District: Miscellaneous 
administrative costs in connection with dredging 
the Connecting Channel to the C&D Canal. 
New Work, Norfolk District: None. 
Maintenance, Baltimore District: Condition 
surveys of Baltimore Harbor cost $43,522. 
Maintenance dredging of the inbound portions of 
the Craighill Cutoff Angle and the Brewerton 
Angle by the U.S. Hopper Dredge ESSAYONS 
began February 18, 1975 and was completed 
March 15, 1975. Material amounting to 858,200 
cubic yards were removed at a cost of $626,732. 
Maintenance, Norfolk District: Condition 
surveys were made at a cost of $8,647.82. 
Supervision and administration costs were 
$1,677.71. 
Condition at end of fiscal year. Project as 
authorized by 1945 River and Harbor Act and 
prior acts was completed in March 1954 except 
for inactive portion. Norfolk District undertook 
jurisdiction of the channel in York Spit Section in 
fiscal year 1942 and the channels in Cape Henry 
and Rappahannock Shoal Sections in fiscal year 
1961. 
Project as authorized by 1958 River and 
Harbor Act is 85 percent complete. Work within 
the Baltimore District is 78 percent complete. 
The work remaining to be done is dredging the 
Connecting Channel to the C&D Canal and 
remaining width of the approaches thereto. Work 
within the Norfolk District on Cape Henry, York 
Spit, and Rappahannock Shoal sections was 
completed in March 1967. 
Work has not started on the project as 
authorized by 1970 River and Harbor Act. 
Total costs for existing project were 
$45,948,574 of which $28,654,257 was for new 
work and $17,294,317 for maintenance. 
2. BALTIMORE HARBOR, MD., COLLECTION 
AND REMOVAL OF 
DRIFT 
Location. Project applies to Baltimore Harbor, 
Md., and its tributaries. 
Existing project. Provides for collection and 
removal of drift from Baltimore Harbor and its 
tributary waters, and authorizes Secretary of the 
Army to allot such amounts as may be necessary 
for work from appropriations for maintenance 
and improvement of existing river and harbor 
works or other available appropriations, and that 
this work shall be carried as a separate and 
distinct project. It is wholly a work of 
maintenance. Purpose of work is to afford relief 
from variable conditions of obstruction. 
Local cooperation. None required. 
Terminal facilities. See report for Baltimore 
Harbor and Channels, Md. 
Operations and results during fiscal year. 
Maintenance operations, by hired labor, 
consisted of collection and disposal of 27,540 
cubic feet of driftwood, ranging from small 
blocks up to timbers of large dimensions. 
Condition at end offiscal year. Existing project 
is one of continuous maintenance. Navigation has 
been made safer by continued patrol of the 
harbor and removal of drift material which 
began in July 1949. 
3. CHESTER RIVER, MD. 
Location. Rises in Kent County, Del., flows 50 
miles generally southwesterly and empties into 
Chesapeake Bay. Kent Island Narrows is a 
passage connecting Chester River and Eastern 
Bay. Wells Cove is an indentation on easterly side 
of Kent Island Narrows about 0.4 mile south of 
highway bridge crossing the Narrows. (See Coast 
and Geodetic Survey Charts 548 and 1226.) 
Previous project. For details see page 262 of 
Annual Report for 1960. 
Existing project. Provides for a channel 6 feet 
deep at mean low water and 60 feet wide from 
Crumpton to Jones Landing, section included in 
project is about 5.5 miles long, lower end of the 
section being about 37 miles above mouth of 
river; for a channel 7 feet deep at mean low water 
and 75 feet wide from Chester River to Eastern 
Bay through Kent Island Narrows; and a channel 
7 feet deep at mean low water and 75 feet wide 
extending from 7-foot deep curve in Kent Island 
Narrows 800 feet into Wells Cove with a basin of 
same depth and 300 feet square at head of 
Channel. Mean range of tide is 2.4 feet. Cost of 
new work for completed project was $32,454, 
exclusive of amounts expended on previous 
projects. Widening 7-foot deep channel from 75 to 
100 feet from Chester River to Eastern Bay 
through Kent Island Narrows is considered 
inactive and excluded from foregoing estimate. 
Local cooperation. Fully complied with except 
local interests are to furnish spoil disposal areas 
for future maintenance of Wells Cove section of 
project. 
Terminal facilities. There are two bulkhead 
wharves on Chester River section. Facilities on 
the Kent Island Narrows section of the existing 
project consist of about 10,000 linear feet of 
timber pile bulkheaded wharf. About 1,350 
linear feet of the wharf is owned and operated by 
the Queen Anne's County: the remainder is 
privately owned. The privately owned bulkheaded 
wharf is operated mostly by the 7 marinas 
4-4

BALTIMORE, MD., DISTRICT 
located on the narrows with the remainder being 
owned and operated by the seafood packing 
houses in the area. In addition to the slips of the 
marinas, there are marine railways, launching 
ramps, and travel-lifts. All of these facilities are 
in good condition and are located adjacent to the 
proposed improvements. In Wells Cove there is a 
small wharf, a small marine railway, and a 
public landing. All facilities are privately owned 
except the public landing on Wells Cove. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Final payment for contract of maintenance 
dredging of project channel completed in April 
1974, was $8,855. 
Condition at end of fiscal year. Active portion of 
existing project was completed in 1950. Total 
costs of existing project were $519,440 of which 
$32,454 was new work and $486,986 for 
maintenance. 
4. CHOPTANK RIVER, MD. 
Location. Rises in Delaware, below Dover, and 
flows in a generally southwesterly direction to 
Cambridge, Md., where it turns northwest and 
empties into Chesapeake Bay south of Tilghman 
Island, Md. Head of navigation is at Greensboro, 
Md., about 60 miles above mouth of river. Total 
length of river is about 70 miles. (See Coast and 
Geodetic Survey Chart 1225.) 
Existing project. Provides for channel 75 feet 
wide and 8 feet deep at mean low water from 
Denton to Greensboro, length of section included 
in project is about 8 miles, lower end of section 
being about 46 miles above mouth of river, and 
for a channel 12 feet deep, 100 feet wide, and two 
miles long in the Choptank River from a point 
opposite Watts Creek to Denton. Mean range of 
tide is about 2.2 feet, and extreme tidal range is 
4.6 feet. 
Local cooperationt. Local interests must 
furnish lands and rights-of-way for new work 
and future maintenance; provide suitable spoil 
disposal areas including retaining dyke, 
bulkheads, and embankments or the costs of such 
retaining works; hold the United States free from 
damages; make alterations, relocations, and 
removals as required of utility facilities; execute 
an assurance of compliance in accordance with 
the Civil Rights Act of 1964; and assume full 
project cost in excess of $500,000. There is no local 
cooperation required for the portion of project 
above Denton. 
Terminal facilities. Facilities on the Choptank 
River consist of three privately-owned piers 
located between the highway and railroad 
bridges at Denton and a timber pile bulkheaded 
wharf just south of the highway bridge. These 
facilities are used by oil companies for the 
transfer of petroleum products. Other facilities 
include a few privately-owned piers, a small 
marina at Denton, and a public landing provided 
by the County of Greensboro. 
Operations and results during fiscal year. New 
work: a field investigation made March 26, 1975 
revealed that the industry upon which the project 
was economically justified at one time, no longer 
exists in the project area. The County indicated 
that they will request that normal maintenance 
dredging (8-foot depth) be performed in lieu of the 
proposed new work dredging (12-foot depth). 
Condition at end of fiscal year. Existing project 
is about 40 percent complete. Work remaining is 
deepening of channel from 8 feet to 12 feet in the 
reach from Watts Creek to Denton, which based 
on a recent analysis, is not economically justified. 
5. HARBOR OF BALTIMORE, MD., 
PREVENTION OF OBSTRUCTIONS 
AND INJURIOUS DEPOSITS. 
Location. Project applies to tidal waters of the 
harbor of Baltimore and its adjacent and 
tributary waters, and all tidal waters of 
Chesapeake Bay and its tributaries within State 
of Maryland. 
Existing project. Continuous patrol and 
inspection of Baltimore Harbor. Chesapeake 
Bay, and its tributaries to prevent and detect 
violations of the River and Harbor Act of June 29, 
1888, Sections 10 and 13 of the River and Harbor 
Act of March 3, 1899, and other related federal 
laws. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance operations, by supervisor of Harbor 
of Baltimore, included: 1,945 inspections; 338 
detailed investigations of violations of federal 
laws, with cease and desist orders issued in 128 
cases; 507 vessels observed; 122 cases sent to U.S. 
Attorney for further action. Fines in the amount 
of $4,650 were imposed. 
Condition at end of fiscal year. Work under 
existing project began in July 1959 and is one of 
continuing operation and maintenance. 
6. KNAPPS NARROWS, MD. 
Location. A small channel separating 
Tilghman Island from mainland of eastern shore 
of Chesapeake Bay about 40 miles south of 
Baltimore, Md. (See Coast and Geodetic Survey 
Chart 1225.) 
4-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. A channel 9 feet deep at mean 
low water, 75 feet wide, widened at the bends 
from deep water in Chesapeake Bay to deep 
water in Harris Creek, Md., with a turning basin 
located west of the drawbridge, 7 feet deep, 320 
feet long and 120 feet wide. Mean range of tide is 
1.4 feet. Cost of new work for completed project 
was $46,121. Existing project channel was 
authorized by the Public Works Administration 
September 16, 1933, and later adopted by 1935 
River and Harbor Act. 
Local cooperation. Complied with except local 
interests must furnish spoil disposal areas as 
needed for future maintenance. 
Terminal facilities. A bulkhead wharf on each 
side of southerly abutment of the bridge across 
the Narrows. There are several small-boat 
landings within the Narrows and 3 marine 
railways for repairing boats of few feet draft. A 
bulkhead landing is available for public use on 3 
sides of turning basin. 
Operations and results during fiscal year. 
Maintenance dredging of the Chesapeake Bay 
portion of project channel, by contract, was 
begun December 1974 and completed April 1975. 
A total of 85,500 cubic yards of material, place 
value, was removed and deposited. Costs were 
$121,968. 
Condition at end of fiscal year. Project was 
completed April 1935. 
7. NANTICOKE RIVER AT BIVALVE, 
MD. 
Location. Bivalve is on east bank of Nanticoke 
River, a tidal arm of Tangier Sound on east side of 
Chesapeake Bay. It is 6 miles above mouth of 
river and about 113 miles by water from 
Baltimore. Jacksons Gut is a slough through a 
marshland about one-quarter mile' north of 
Bivalve. (See U.S. Coast and Geodetic Survey 
Chart 1224.) 
Existing project. Provides for a protected 
anchorage basin in Jacksons Gut 7 feet deep at 
mean low water, 150 feet wide, and 350 feet long 
and an approach channel of like depth, 60 feet 
wide and about 1,400 feet long, extending from 7- 
foot depth in Nanticoke River, protected by twin 
rock jetties about 1,000 feet long extending from 
shore to 4-foot depth in river. Mean range of tide 
in vicinity of Bivalve is about 2.5 feet. 
Federal cost of new work for completed project 
was $240,817. 
Portion of project which provides for extension 
of anchorage basin from 350 to 550 feet long is 
considered inactive and excluded from foregoing 
costs. Cost of this portion last revised in 1958 was 
estimated to be $14,000. 
Local cooperation. Fully complied with except 
that local interests are to furnish spoil disposal 
areas as needed for future maintenance. 
Terminal facilities. There are at present two 
timber-pile wharves in a bulkhead area in 
Nanticoke River at Bivalve. Bulkhead has 
deteriorated extensively due to original use of 
untreated timber piling and sheathing. One, a 
county wharf, is at northeast corner of area and 
the other near southeast corner is at a seafood 
packing house. There are no wharves at Jacksons 
Gut. Sufficient areas are available for 
construction of additional terminals by private 
interests. 
Operations and results during fiscal year. 
Modification of contract to remove dredged 
material from existing dike and construct a new 
dike was accomplished at a cost of $9,800. 
Condition at end offiscal year. Existing project 
is complete. Approach channel and anchorage 
basin were completed in October 1959 and twin 
stone jetties were completed July 1960. Total 
costs were $362,990, of which $240,817 was for 
new work and $122,173 for maintenance. 
8. NEABSCO CREEK, VA. 
Location. A tidal estuary approximately three 
miles long, enters the west side of the Potomac 
River about 83 miles above its mouth and about 
27 miles south of Washington, D.C., (See Coast 
and Geodetic Survey Chart 560). 
Existing project. The project provides for a 
channel, 100 feet wide and 7 feet deep, from that 
depth in the Potomac River to Atkinson's Upper 
Landing and Willis' Wharf. The project was 
authorized by the River and Harbor Act of March 
3, 1881 (H. Ex. Doc. 41, 46th Cong., 3rd sess.) but 
was classified as inactive for many years. On 
September 2, 1966, the Chief of Engineers 
reclassified the following portion from the 
inactive to the active category: a channel, 100 feet 
wide and 6 feet deep, from the Potomac River to 
the Richmond, Fredericksburg, and Potomac 
Railroad Bridge over Neabsco Creek and a 
channel upstream from the railroad bridge 60 
feet wide and 6 feet deep to an anchorage basin of 
the same depth 140 feet wide and 150 feet long. 
The estimated cost of the active portion is 
$664,000, of which $212,000 is Federal cost, 
$212,000 is required local cash contribution, and 
$240,000 is the estimated local cost for lands and 
dikes. The inactive portion of the project is 
estimated to cost $210,000. 
Local cooperation. Project was reclassified to 
active subject to conditions that local interests 
provide lands, easements, and rights-of-way for 
new work and future maintenance, hold the 
United States free from damages, establish 
4-6

BALTIMORE, MD., DISTRICT 
regulations concerning pollution control and 
prevention, provide and maintain depths in 
berthing areas and access channels commensurate 
with depths in Federal project, 
accomplish necessary relocations and alterations, 
establish a public body to regulate the 
harbor facilities, make a cash contribution of 50 
percent of the first cost of providing the channel 
and basin, construct a public landing, and 
execute a compliance assurance with the Civil 
Rights Act of 1964. The assurances of local 
cooperation were accepted by the District 
Engineer on February 20, 1967. 
Terminal facilities. None. 
Operations and results during fiscal year. 
Negotiations with local interests concerning the 
terms of local cooperation continued. 
Condition at end of fiscal year. Preparation of 
plans and specifications are 70 percent complete. 
Work remaining is completion of plans and 
specifications and construction of project. 
9. OCEAN CITY HARBOR AND INLET 
AND SINEPUXENT BAY, MD. 
Location. Ocean City is on a barrier island 
between Sinepuxent Bay and Atlantic Ocean 
about 35 miles south of entrance to Delaware 
Bay. (See Coast and Geodetic Survey Chart 1220.) 
Existing project. An inlet between the Atlantic 
Ocean and Sinepuxent Bay, 10 feet deep and 200 
feet wide, protected on south side by a stone jetty 
2,380 feet long and on north side by a stone jetty 
projecting 1,531 feet into the Atlantic Ocean and 
connected on shore to a timber and stone 
bulkhead 255 feet long, continuing with a riprap 
dike 213 feet long and steel sheet pile bulkhead 
460 feet long, along shore of inlet; a channel 6 feet 
deep and 150 feet wide from inlet to Green Point, 
and thence 100 feet wide into Chincoteague Bay; 
a channel 10 feet deep at mean low water, 100 feet 
wide, and 3,000 feet long from inlet channel into 
marsh area south of railroad on west side of 
Sinepuxent Bay, with two turning basins of 
same depth; and a channel 6 feet deep and 125 
feet wide from inlet channel to a point opposite 
North Eighth Street in Ocean City, thence 75 feet 
wide into Isle of Wight Bay. Mean range of ocean 
tide is 3.4 feet. Federal cost of new work for 
completed project was $360,530, exclusive of 
$500,000 contributed by local interests. 
Modification of project, authorized by 1954 River 
and Harbor Act, which provides for raising north 
jetty to an elevation of 9 feet above mean low 
water, and a channel 300 feet wide and 16 feet 
deep from the ocean through the inlet to Isle of 
Wight Bay channel, thence 200 feet wide and 16 
feet deep to project harbor, and a depth of 14 feet 
in project harbor is considered inactive portion of 
project and excluded from foregoing estimate. 
Estimated cost (1957) of this portion is $704,000. 
Local cooperation. Fully complied with except 
local interests must furnish spoil disposal areas 
for future maintenance as needed. 
Terminal facilities. On bay side of Ocean City: 
two storage basins, for pleasure and small 
commercial craft, and numerous privately 
owned pile-and-timber piers and bulkhead 
wharves. At project harbor: a public landing 
about 1,000 feet long, several privately 
constructed bulkhead wharves open to the public 
for transaction of business with the owners, and a 
boat repair yard with a marine railway capable 
of handling boats up to about 150 tons. Project 
harbor is served by Baltimore, Chesapeake & 
Atlantic Railway, which has a spur line parallel 
to harbor on north side about 200 feet away. All 
piers and wharves are accessible by highway. 
Adequate space is presently available for 
expansion of facilities as required. Terminal 
facilities for channel across Sinepuxent Bay to 
Assateague Island consist of a county owned 
timber bulkhead landing at both South Point and 
Asateague Island termini of channel. Adequate 
space is available for expansion of these facilities. 
Operations and results during fiscal year. 
Maintenance: Maintenance dredging of the Inlet 
Channel, by contract, was accomplished during 
February 1975. A total of 44,500 cubic yards of 
material, place value, was removed and 
deposited at a cost of $78,380. 
Condition at end offiscal year. Existing project 
was completed in 1936. Raising of the north jetty 
from 7 feet to 9 feet in 1956 in accordance with 
plans for new constructions authorized by the 
1954 River and Harbor Act was accomplished 
with maintenance funds. Rehabilitation of north 
and south jetties was completed in August 1965. 
10. POTOMAC AND ANACOSTIA 
RIVERS, D.C. COLLECTION AND 
REMOVAL OF DRIFT 
Location. Project applies to the Potomac and 
Anacostia Rivers, Washington, D.C., and their 
tributaries. 
Existing project. Collection and removal of 
drift from the waters of the Potomac and 
Anacostia Rivers and their tributaries in the 
Washington Area from the head of tidewater to 
Mount Vernon, Va. Total length of project, 
considering both sides of the waterway, is about 
50 miles. 
Local cooperation. None required. 
Terminal facilities. See report for Washington 
Harbor, D.C. 
4-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. 
Maintenance: Operations, by hired labor, 
consisted of collection and disposal of 387,963 
cubic feet of driftwood, ranging from small 
blocks up to timbers of large dimensions. 
Condition at end offiscal year. Existing project 
is one of continuous maintenance. Navigation has 
been made safer by continued patrol and removal 
of drift material which began in July 1966. 
11. POTOMAC RIVER AND TRIBUTARIES 
AT AND BELOW WASHINGTON, 
D.C., ELIMINATION OF 
WATERCHESTNUT 
Location. The waterchestnut, botanically 
known as Trapa natans, is an annual fresh water 
plant infesting navigable portions of the Potomac 
River and its tributaries between Key Bridge in 
District of Columbia and Maryland Point, 48 
miles downstream of Washington, D.C. At the 
height of infestation in 1939, it covered about 
10,000 acres of navigable water between these 
limits. (See Coast and Geodetic Survey Charts 
559 and 560.) 
Existing project. A plan for complete 
eradication of waterchestnut from Potomac 
River and its tributaries at and below 
Washington, D.C. For details see Annual Report 
for 1969. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Removal of waterchestnut growth 
was in progress during the fiscal year in 
following areas: Washington Harbor, Potomac 
River at Alexandria, Va., Potomac River at 
Mount Vernon, Va., Occoquan Creek, Va., and 
Potomac River below Washington, D.C., by 
Government plant and hired labor. 
Condition at end of fiscal year. At the present 
time growth of the plant in the Potomac River 
and tributaries for a distance of 40 miles below 
Washington is being brought under control. 
However, an adequate annual removal operation 
for waterchestnuts is required. Should any 
abatement of the present removal operations be 
effected, the plants would quickly be reestablished 
and thus nullify all previous work and 
expenditures. 
12. SLAUGHTER CREEK, MD. 
Location. This is a waterway about 8 miles long 
and tidal throughout connecting with Little 
Choptank River 5 miles from its mouth. It lies in 
Dorchester County, Md., between Taylors Island 
and the mainland of the eastern shore of 
Chesapeake Bay. (See Coast and Geodetic Survey 
Chart 1225.) 
Existing project. This provides for dredging a 
channel 7 feet deep and 100 feet wide at mean 
low water through the bar at the mouth, a 
distance of about one-third of a mile, the lower 
end of the section extending about 900 feet into 
Little Choptank River. The mean range of tide is 
about 1.5 feet and the extreme tidal range is 2.9 
feet. The cost for new work, made in 1911, is 
$4,140. 
Local cooperation. None required. 
Terminal facilities. There is one solid bulkhead 
wharf about 300 feet long, served by this 
improvement. It is privately owned but open to 
general public use, and is considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance dredging, by contract, of channel 
was completed in April 1974. A total of 37,200 
cubic yards of material, place value, was 
removed and deposited. Costs were $32,803. A 
contract for vegetative stabilization of dredged 
material was completed in December 1975. Costs 
were $26,441. Engineering and design, 
supervision and administration costs were $1,533 
and $568, respectively. 
Condition at end of fiscal year. The existing 
project was completed in 1913. 
13. TRED AVON RIVER, MD. 
Location. This stream, formerly called 
Treadhaven Creek, rises in Talbot County, Md., 
flows southerly and empties into Choptank River 
10 miles above its mouth. It is about 10 miles long 
and is a tidal estuary with very little natural flow. 
Drainage area is 36 square miles. (See Coast and 
Geodetic Survey Chart 78.) 
Previous project. For details see page 397 of 
Annual Report for 1951. 
Existing project. Provides for a channel 12 feet 
deep and 150 feet wide in Tred Avon River from 
that depth in river near Peach Blossom Creek to 
Easton Point, thence a channel of same depth and 
width and about 1,400 feet long in the North 
Fork, thence a channel of same width and 8 feet 
deep and about 700 feet long with a turning basin 
of same depth at upper end. Project also provides 
for a turning basin in South Fork 12 feet deep and 
250 feet wide and 600 feet long on east side of 
main channel at Easton Point. Section included 
in project is about 2 miles long, and its lower end 
is about 7.5 miles above mouth. Mean range of 
tide is about 2 feet. 
Local cooperation. Project was modified 
subject to conditions that local interests provide 
lands, rights-of-way, and disposal areas for 
4-8

BALTIMORE, MD., DISTRICT 
construction and future maintenance, hold the 
United States free from damages, and provide 
and maintain all necessary utilities, including a 
public landing with suitable supply facilities 
open to all on equal terms; establish a competent 
and properly constituted public body to regulate 
use, growth, and free development of harbor 
facilities; provide and maintain depth in 
berthing areas, and local access channels serving 
terminals commensurate with depths provided 
in related project areas. In addition, the act of 
March 2, 1919, required that the town of Easton 
previously establish, adjacent to proposed 
improvement of North Fork, public terminal 
facilities to be permanently open to all vessels on 
equal terms, and connected to the city by proper 
public highways. Assurances of local cooperation 
were accepted on August 30, 1968. 
Terminal facilities. Five large terminals for 
receiving and distributing petroleum products, 
and a marina with stalls and ships, marine 
railway, a launchng ramp, and a 6-ton travel-lift 
at Easton Point. These facilities are in good 
condition. 
Operations and results during fiscal year. New 
work: Contract dredging of the North Fork (Sta 
0+000 to 1+400), South Fork (Sta 0+000 
to 0+600), and the Main Channel (Sta 0+000 to 
6+100) to a depth of 11 feet plus 2 feet overdepth 
was initiated October 11, 1974 and completed 
May 31, 1975 at a cost of $417,344. A total of 
215,000 cubic yards of material was removed. 
Local interests contributed $50,000 for the 
construction dikes under the government 
contract. 
Condition at end of fiscal year. Existing project 
is about 50 percent complete. Work remaining is 
deepening the channel in Tred Avon River (Sta 
6+100 to 12+100) from 8 feet to 12 feet. The 
channel, 8 feet deep, 150 feet wide, and 700 feet 
long in the North Fork is considered inactive. 
14. TWITCH COVE AND BIG THOROFARE, 
MD, 
Location. A tidal waterway about 4 miles long 
traversing Smith Island, Md., southeasterly from 
Chesapeake Bay on the west to Tangier Sound on 
the east. (See Coast and Geodetic Survey Chart 
1224.) 
Existing project. A channel 7 feet deep at mean 
low water and*60 feet wide from Twitch Cove on 
Tangier Sound through Big Thorofare, thence 
through canal at Ewell, Md., thence through 
Levering Creek and Big Thorofare to vicinity of 
Swan Point, thence of same depth and 100 feet 
wide through offshore bar to deep water in 
Chesapeake Bay, with twin stone jetties at 
entrance, north jetty is about 2,080 feet long, and 
south jetty about 1,8000 feet long; and anchorage 
basin 7 feet deep, 100 feet wide, and 700 feet long 
connecting with west side of existing project 
channel at Ewell; extension of existing project 
channel in Levering Creek, 6 feet deep, 60 feet 
wide, and 1,000 feet long; and a channel 4 feet 
deep and 25 feet wide around point between Big 
Thorofare and Tylers River. Mean range of tide is 
1.7 feet, and extreme tidal range is 3 feet. Federal 
cost of new work for completed project was 
$193,175. 
Local cooperation. Fully complied with, except 
that local interests are to furnish spoil disposal 
areas for future maintenance as needed. 
Terminal facilities. Numerous privately 
owned pile-and-timber wharves and bulkheads 
at Ewell which are open to the public for business 
transactions with the owners. A county wharf is 
also at west end of town. Five crab houses are on 
Levering Creek, and one oyster house on project 
waterway west of town of Ewell. 
Operations and results during fiscal year. 
Engineering and design in connection with 
proposed maintenance dredging of the Big 
Thorofare Channel. 
Condition at end of fiscal year. Existing project 
is complete. Work authorized by 1950 River and 
Harbor Act was completed in September 1956 
and work authorized under prior acts was 
completed in November 1940. 
15. UPPER THOROFARE, DEAL 
ISLAND, MD. 
Location. Natural waterway lying between 
Deal Island and mainland of Somerset County, 
Md., on eastern shore of Chesapeake Bay. (See 
Coast and Geodetic Survey Chart 1224.) 
Previous projects. For details see page 277 of 
Annual Report for 1962. 
Existing project. Entrance channel from 
Tangier Sound 9 feet deep and 100 feet wide, 
thence of irregular width to and along south 
shore of Thorofare, protected by two stone 
breakwaters at entrance, north breakwater is 
about 410 feet long and south breakwater about 
310 feet long, with a turning basin at inner end 9 
feet deep on south side of channel to within 50 feet 
of bulkhead along south shore, an anchorage area 
6 feet deep and 150 feet wide extending across 
waterway parallel to highway bridge to within 50 
feet of bulkhead on south shore, and an anchorage 
area 650 feet long, 300 feet wide, and 9 feet deep 
on north side of channel between breakwater and 
6-foot anchorage. Mean range of tide is about 2 
feet. Cost of new work for completed project was 
$62,116. 
Local cooperation. Fully complied with. 
4-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Terminal facilities. A small packing-house 
wharf on shore of Tangier Sound south of project 
channel; two small packing houses along aproach 
channel at which seafood is landed; and a public 
wharf at turning basin with a suitable road 
connecting it with the road system. 
Operations and results during fiscal year. 
Engineering and design in connection with 
proposed maintenance dredging of the project 
channel, turning basin, and anchorage area. 
Condition at end of fiscal year. Existing project 
was completed in 1939. Total costs for existing 
project were $241,963 of which $24,773 (regular 
funds) and $37,343 (public works funds) was for 
new work and $179,847 (regular funds) for 
maintenance. 
16. WASHINGTON HARBOR, D.C. 
Location. Within District of Columbia at 
junction of Anacostia River with Potomac River 
which flows southeasterly 108 miles to 
Chesapeake Bay. It is southerly 202 miles by 
water from Baltimore, Md., and northerly 195 
miles from Norfolk, Va. (See Coast and Geodetic 
Survey Chart 560.) 
Previous projects. For details see page 291 of 
Annual Report for 1963. 
Existing project. A combination and extension 
of latest projects for Potomac River at 
Washington, D.C., and Anacostia River, D.C. 
Project provides for: (a) Virginia Channel, from 
Giesboro Point to Francis Scott Key Bridge, 24 
feet deep and 400 feet wide, with width increased 
as necessary to afford a low-water cross section 
area of 25,000 square feet; (b) Washington 
Channel, from Hains Point to head of Washington 
Channel, 24 feet deep and 400 feet wide; (c) 
Anacostia River from Giesboro Point to 
Anacostia Bridge, 24 feet deep and 400 feet wide, 
with turning basin 800 feet wide and about 2,400 
feet long of same depth opposite Naval Weapons 
Plant; (d) Anacostia River from Anacostia 
Bridge 24 feet deep and 200 feet wide to turning 
basin 400 feet square of same depth at foot of 15th 
Street SE. Channel lengths including turning 
basins are: Virginia Channel, 25,000 feet; 
Washington Channel, 10,000 feet; and Anacostia 
River, 15,000 feet; and (e) operation and 
maintenance of inlet gates and lock and outlet 
gates of Tidal Basin constructed under a previous 
project to flush Washington Channel. Plane of 
reference is low-water datum which is 0.35 foot 
below mean low tide as observed from 1932 to 
1942. Tidal ranges are: Mean, 2.9 feet; irregular, 
4.5 feet; and extreme, 10.7 feet. Estimated 
Federal cost (1955) for new work is $572,000, 
exclusive of amounts expended under previous 
projects. 
Local cooperation. None required. 
Terminal facilities. There are four wharves 
generally of bulkhead type on Virginia Channel 
that are privately owned and not open to the 
public except by special arrangement. On 
Washington Channel there are four piers under 
jurisdiction of District of Columbia, two of which 
are open to the public and one open to the public 
by special arrangement. In Anacostia River 
there are four privately owned piers and eight 
governmental piers and slips. None of the piers 
are open to the public except by special 
arrangement. Terminal facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
of tidal basin gates by hired labor cost 
$7,319. 
Condition at end of fiscal year. Existing project 
is about 30 percent complete. Channels and basins 
in Anacostia River are complete and those at 
forks of channel at Haines Point are partially 
complete. Except for dredging between limits of 
2,000 feet above and 3,000 feet below Memorial 
Bridge, no new work has been done downstream 
of Key Bridge in Virginia channel. 
Work remaining to complete project consists of 
removing rock in Virginia Channel upstream of 
Memorial Bridge and dredging Virginia 
Channel from Giesboro Point upstream to a point 
3,000 feet below Memorial Bridge. Total costs for 
existing project were $2,015,435 of which 
$162,006 was for new work and $1,853,429 was 
for maintenance. This excludes $4,000 for 
emergency dredging under provisions of section 
3, 1945 River and Harbor Act. 
17. WICOMICO RIVER, MD. 
Location. Wicomico River has its source in 
northern part of Wicomico County, Md., and 
flows generally southwardly emptying into 
Monie Bay, a tributary of Tangier Sound on each 
-side of Chesapeake Bay about 85 miles southeast 
of Baltimore. Webster Cove is site of improved 
small-boat harbor on southeast bank of Wicomico 
River about 3 miles above the mouth. (See Coast 
and Geodetic Survey Charts 567 and 1224.) 
Previous projects. For details see page 275 of 
Annual Report for 1962. 
Existing project. Channel 14 feet deep and 150 
feet wide from Chesapeake Bay to Salisbury, 
section included in project is 37 miles long, 
including about 12 miles from mouth of river to 
Chesapeake Bay; 14 feet deep in channels and 
turning basins in north and south prongs with 
channel widths of 100 feet, and a channel 6 feet 
deep and 60 feet wide extending from 6-foot 
4-10

BALTIMORE, MD., DISTRICT 
contour in Wicomico River to and including a 
basin in Webster Cove of same depth, 100 feet and 
400 feet long; and extension of basin 200 feet long 
and 100 feet wide on each side. Plane of reference 
is mean low water. Mean range of tide is about 3 
feet and extreme tidal range is 4.4 feet. Cost of 
new work for completed project was $421,609, 
exclusive of amounts expended on previous 
project. 
Local cooperation. Fully complied with, except 
that local interests are to furnish spoil disposal 
areas for future maintenance as needed and hold 
the United States free from such damages as may 
occur to public or leased oyster beds. 
Terminal facilities. Present waterfront at 
Salisbury consists of pile-and-timber bulkheads 
with earthfills. Some wharves have warehouses 
and factories with mechanical freight-handling 
facilities and rail sidings. With exception of 
wharf on north prong, owned by State Roads 
Commission, and a wharf on south prong, owned 
by the county, all terminals are privately owned. 
A shipyard, with two marine railways with 
capacities of 1,200 and 500 tons, respectively, is 
on right bank of river below prongs. Areas for 
development of new terminals on north and south 
prongs are limited. Areas for considerable 
expansion of terminal facilities are available on 
main river. There is a pile-and-timber wharf 
about 4 miles above mouth of river at Mount 
Vernon. A wharf of similar construction is at 
White Haven. There is a county wharf at head of 
basin in Webster Cove a pile-and-timber pier at 
oyster house on southwest side of basin, a Tshaped 
pile-and-timber pier at cafe on southwest 
side of basin and several small timber piers on 
walkways that local interests constructed around 
the basin. Fueling facilities are available at the 
T-shaped pier. Sufficient areas are available for 
construction of additional facilities when 
required. 
Operations and results during fiscal year. 
Engineering and design in connection with 
proposed maintenance dredging of the Wicomico 
River channel. 
Condition at the end of the fiscal year. Existing 
project was completed in 1942 except for 
enlarging basin in Webster Cove which was 
completed November 1956. Total costs for 
existing project were $1,126,311 of which 
$421,609 (Federal funds) and $14,000 (contributed 
funds) were for new work, and $657,702 
(Federal funds) and $33,000 (contributed funds) 
were for maintenance. 
18. RECONNAISSANCE AND CONDITION 
SURVEYS 
(See Table 4-C at end of chapter.) 
19. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
(See Table 4-D at end of chapter.) 
20. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
Fiscal year costs for preauthorization studies 
were $5,000 for Knapps Narrows, Md., 
$12,506.80 for Madison Bay, Md., and $33,567.37 
for Rock Hall, Md. 
Beach Erosion Control 
21. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 4-E at end of chapter.) 
22. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to 
Section 103, Public Law 87-874 (preauthorization). 
Fiscal year costs were $9,716.72 for Aquai 
Creek, Va., and $3,035.47 for Westmoreland 
State Park, Va.
Flood Control 
23. ANACOSTIA RIVER AND TRIBUTARIES, 
FLOOD PROTECTION 
AND NAVIGATION IMPROVEMENTS, 
D.C. AND MD. 
Location. Project is on Anacostia River at 
confluence of northeast and northwest branches 
at Bladensburg, Md., about 9 miles above mouth 
at Washington, D.C. (See Coast and Geodetic 
Survey Chart 560.) 
Existing project. Channel improvements of 
Anacostia River from foot of 15th Street SE in 
District of Columbia, to junction of Northeast and 
Northwest Branches at Bladensburg, Md.; 
channel improvement in Northeast Branch from 
mouth upstream to near Longfellow Street in 
Riverdale, Md.; channel improvement in 
Northwest Branch from mouth upstream to near 
38th Street in Brentwood, Md.; levees along both 
banks of the streams to protect Bladensburg, 
Edmonston, Riverdale, Cottage City, and Colmar 
Manor, Md.: interior drainage facilities in these 
communities, including four pumping stations 
4-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
and necessary intercepting sewers; and 
alterations and reconstruction of highway and 
railroad bridges. Portion of channel 
improvement of Anacostia River from vicinity of 
15th Street SE in District of Columbia to near 
Defense Highway Bridge on U.S. Route 50, 
provides for navigation channel 8 feet deep and 
80 feet wide with a commercial boat basin, and a 
recreational boat basin having a capacity of 150 
boats, both on east bank of river near 
Bladensburg, Md. Federal cost for new work for 
completed project was $6,042,325. Estimated 
cost to local interests for construction, lands, and 
damages is $6,275,000. 
Local cooperation. Fully complied with. 
Operations and results during fiscal 
year.Maintenance: Final contract payment of 
$95,705.40 was made for maintenance dredging 
completed June 25, 1974. 
Condition at end of fiscal year. Existing project 
was started in November 1954 and completed in 
November 1959. Project was transferred to 
Washington Suburban Sanitary Commission 
November 17, 1959 for operation and 
maintenance. (For further details see Annual 
Report for 1967.) 
24. ANACOSTIA RIVER AND TRIBUTARIES, 
PRINCE GEORGES 
COUNTY, MD. 
Location. The project is located on the 
Northeast and Northwest Branches of the 
Anacostia River and on the Paint Branch and 
Indian Creek tributaries of the Anacostia River 
in Prince Georges County, Md., immediately 
northeast of Washington, D.C. 
Existing project. Provides for channel 
improvement by realigning, widening, and 
deepening the streambed of the Northwest 
Branch upstream and downstream from Queens 
Chapel Road bridge for a total distance of 5,610 
feet: channel improvement by realigning, 
widening and deepening some 7,200 feet of 
channel of Northeast Branch and Paint Branch, 
starting 540 feet upstream from the new Calvert 
Road bridge and extending up Paint Branch to 
Baltimore Avenue bridge: and channel 
realigning, deepening, and widening of Indian 
Creek from its junction with Paint Branch, 7,600 
feet upstream to Greenbelt Road culvert. 
Overbank clearing to provide a 500-foot floodway 
will also be included along the Northeast Branch 
and Paint Branch. Estimated total Federal cost 
(1974) for new work is $1,000,000. Estimated cost 
to local interests is $468,000 for construction. 
Local cooperation. Fully complied with to date. 
Operations and results during fiscal year.New 
work: A contract for removal of concrete 
obstructions was awarded April 21, 1975 to 
complete the project in a manner acceptable by 
local interests. 
Condition at end of fiscal year. Construction 
was initiated in April 1973 and completed in June 
1974 except for the removal of concrete 
obstructions which was completed in June 1975. 
25. BLOOMINGTON LAKE, MD. & W. 
VA. 
Location. Project is located on the North 
Branch Potomac River on the state line between 
Garrett County, Md., and Mineral County, W. Va. 
The damsite is located approximately 7.9 miles 
upstream from the confluence with Savage River 
at Bloomington, Md. It is also about 5 air miles 
southwest of the tritowns of Luke and 
Westernport, Md., and Piedmont, W. Va. (See 
Geological Survey Quandrangle sheets, "Kitzmiller" 
and "Westernport," Md.) 
Existing project. Plan of improvement consists 
of a rolled earth and rock fill dam with an 
impervious core and an 800-foot long dike on the 
left bank. Top of dam would be 296 feet above 
stream bed with a total length of 2,130 feet. When 
filled to spillway crest, reservoir would extend 
about 6.6 miles upstream and inundate 965 acres. 
Flood control storage of 36,200 acre-feet would be 
provided. Storage available for low flow 
augmentation for water supply and water quality 
improvement would be 92,000 acre-feet. 
Reservoir would control a drainage area of 263 
square miles. Recreation facilities will be 
provided for picnicking, camping and boating. 
Estimated cost (1975) of new work is 
$151,200,000 of which $50,200,000 is required 
non-federal reimbursement. 
Local cooperation. Local interests must: (a) 
agree to pay all costs allocated to water supply 
amounting to 33.2 percent of project construction 
cost presently estimated at $50,200,000; in a lump 
sum prior to start of construction or in 
installments before commencement of pertinent 
work items in accordance with construction 
scheduled as required by the Chief of Engineers; 
or as an alternative, contract with United States 
to repay, within 50 years, a portion of costs 
allocated to water supply on basis of initial 
requirements amounting to 5.8 percent of 
construction costs plus interest during 
construction on this amount with interest on 
unpaid balance and payments to begin when 
storage is first available for water supply; and 
repay remaining costs allocated to water supply 
on basis of future requirements, amounting to 
27.4 percent of construction cost, plus interest 
during construction on this amount with interest 
4-12

BALTIMORE, MD., DISTRICT 
on unpaid balance beginning 10 years after 
storage is first available for water supply and 
with final payment to be made 50 years 
thereafter, except that no interest will be 
charged thereon for first 10 years after storage is 
first available for water supply; (b) contract with 
the United States to pay the operation and 
maintenance cost allocated to initial water 
supply, beginning when storage is first available 
for water supply, and furnish assurances 
satisfactory to the Secretary of the Army that 
they will pay the operation and maintenance 
costs allocated to future water supply; (c) agree to 
pay the major replacement costs allocated to 
initial water supply as such costs are incurred, 
and furnish assurances satisfactory to the 
Secretary of the Army that they will pay major 
replacement costs allocated to future water 
supply; (d) control pollution of streams subject to 
low flow augmentation by adequate treatment or 
other methods of controlling wastes at their 
source; and (e) protect downstream channels 
from encroachments which would adversely 
affect operation of project. 
Operations and results during fiscal year. 
Relocation of Western Maryland Railway Unit I 
was completed in August 1974 at a cost of 
$403,647. Unit II relocations were advanced to 98 
percent complete at a cost of $2,824,051. 
Relocation Unit III were advanced to 68 percent 
complete at a cost of $2,226,416. Tracks and 
facilities work continued at a cost of $422,885 and 
is 9 percent complete. The phase I dam and 
appurtenances work was completed in March 
1975 at a cost of $2,510,007. Grouting of the valley 
floor and left abutment was advanced to 46 
percent complete at a cost of $366,978. 
Fabrication of flood control gates began in 
April 1975 and is 5 percent complete. Costs were 
$198,000. Land acquisition continued at a cost of 
$400,449. Ejngineering and design, supervision 
and administration costs were $1,090,310 and 
$529,176, respectively. 
Condition at end of fiscal year. Construction of 
the project began in June 1971. The overall 
project is 32 percent complete. 
26. CUMBERLAND, MD., AND 
RIDGELEY, W. VA. 
Location. On North Branch of Potomac River, 
21 miles upstream from its junction with South 
Branch of Potomac River and 197 miles 
upstream from Washington, D.C. (See Geological 
Survey Quadrangles, Frostburg and Flint Stone, 
Md., W. Va., and Pa.) 
Existing project. Channel improvements of 
North Branch of Potomac River from Western 
Maryland Railway bridge in South Cumberland 
upstream to mouth of Wills Creek, with levees 
and fill along left bank and levees along right 
bank from downstream corporate limits of 
Ridgeley, W. Va., to a point about 150 feet above 
Johnson Street Bridge; channel improvements 
along Wills Creek from its mouth upstream to a 
point in the Narrows about 500 feet upstream 
from highway bridge on U.S. Highway 40; levee 
and floodwall in West Cumberland, Md., on left 
bank of North Branch of Potomac River from 
mouth of Wills Creek upstream to Kelly 
Boulevard; levee and floodwall in Ridgeley, W. 
Va., on right bank of North Branch of Potomac 
River from Carpenter Avenue upstream to 
Patapsco Street near upstream corporate limits 
of Ridgeley, W. Va.; interior drainage facilities in 
Cumberland and West Cumberland, Md., and 
Ridgeley, W. Va.; removal of Chesapeake and 
Ohio Canal dam and construction of a new 
industrial dam on North Branch of Potomac 
River immediately above mouth of Wills Creek; 
and alteration and reconstruction of highway and 
railroad bridges. Federal cost of new work for the 
completed project was $15,633,970, which 
includes $49,998 emergency relief funds and is 
exclusive of $197,513 public works acceleration 
funds. Estimated cost to local interests is 
$2,900,000 of which $1,402,001 is contributed 
funds and $1,497,999 is for lands and damages. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Removal of gravel deposits, grass 
cutting of areas channelward of levees, and 
removal of brush and debris from channel were 
accomplished as required in channel area. 
Condition at end of fiscal year. Existing project 
was started in March 1949 and completed in May 
1959, except for minor items of land acquisition, 
which were completed in June 1963. Project was 
transferred to City of Cumberland, Md., for 
operation and maintenance May 1959. 
27. FOURMILE RUN, VA. 
Location. The project is located in the City of 
Alexandria and in Arlington County, Va., on 
Fourmile Run immediately above its confluence 
with the Potomac River at Washington, D.C. (See 
Geological Survey Quadrangle sheets for 
Alexandria, Va., Annandale, Va., Falls Church, 
Va., and Washington West, D.C., Md., and Va.) 
Existing project. Provides for construction of a 
floodwall protection system, an improved 
channel, and replacement of two highway and 
four railroad bridges. Total estimated cost(1975) 
of new work is $60,870,000 of which $13,409,000 
is non-Federal. 
Local cooperation. Local interests must: 
provide all lands, easements, and rights-of-way 
4-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
necessary for construction and maintenance of 
the project; modify or relocate buildings, 
utilities, roads, and other facilities where 
necessary for the construction of the project; 
reconstruct one existing highway bridge 
including approach ramps; hold and save the 
United States free from damages due to 
construction and maintenance of the project; 
maintain and operate all the works after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; prevent 
any encroachment on the project flood channels 
which would decrease the effectiveness of the 
flood control improvemerits; and provide guidance 
and leadership in preventing unwise future 
development of the flood plain, particularly 
above the proposed improvement, by use of 
appropriate flood plain management techniques 
to reduce flood losses; develop a land 
management planning process acceptable to the 
Secretary of the Army for the entire watershed; 
contribute in cash toward construction of the 
project a sum estimated at $2,439,000; and pay 50 
per cent of the separable costs of the project 
allocated to recreation. 
Agreements for local cooperation complying 
with Section 221 of the 1970 Flood Control Act 
and Subsection 84 (b) of the 1974 Water 
Resources Development Act were accepted for 
the Secretary of the Army on April 23, 1974. 
Agreements for local cooperation concerning 
recreation cost sharing were accepted for the 
Secretary of the Army on May 30, 1974. 
Operations and results during fiscal year. New 
work: Replacement of the George Washington 
Memorial Parkway Bridge was advanced to 39 
percent complete at a cost of $1,915,423. 
Construction of temporary railroad bridges was 
advanced to 34 percent complete at a cost of 
$806,535. Engineering and design and 
supervision and administration costs were 
$522,206 and $23,617, respectively. 
Condition at end of fiscal year. Construction 
was initiated in June 1974. 
28. LACKAWANNA RIVER BASIN, PA. 
Flood Control Act of 1962 authorized 
construction of Aylesworth Creek Lake, Fall 
Brook Lake, and local protection works on 
Lackawanna River at Scranton, Pa.,substantially 
as recommended by Chief of Engineers 
(S. Doc. 141, 87th Cong., 2d sess.). The Basin 
includes an area of 346 square miles in 
northeastern Pennsylvania. (See Tables 4-F and 
4-G at end of chapter.) (See Geological Survey 
maps: "Avoca," "Carbondale," "Clifford," and 
"Scranton," Pa.) 
28A AYLESWORTH CREEK LAKE., 
PA. 
Location. Project is located in Lackawanna 
County on Aylesworth Creek about one mile 
above its confluence with the Lackawanna River, 
just below the community of East Jermyn, Pa. 
Existing project. Provides for an earthfill dam 
with a maximum height of 90 feet above 
streambed and a top length of 1,200 feet. The 
spillway located adjacent to the left abutment is 
an open cut channel 80 feet wide with a concrete 
sill. The outlet works consist of a 3-foot diameter 
uncontrolled conduit. Project will control a 
drainage area of 6.2 square miles and provide 
flood control storage of 1,700 acre-feet, 
equivalent to 5.1 inches of runoff from the 
drainage area. The lake will extend about 4,600 
feet and inundate 87 acres when filled to spillway 
crest. Federal cost of new work was $2,268,200 of 
which $2,153,559 was for construction and 
$114,641 for lands and damages. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
of the project continued. Boundary line 
monumentation of the project by contract began 
in April 1974 and was completed in May 1974. 
Contract payment was made in Fiscal Year 1975. 
Condition at end of fiscal year. Construction of 
the project began in November, 1967 and was 
completed in October, 1970. 
29. RAYSTOWN LAKE, RAYSTOWN 
BRANCH, JUNIATA RIVER, PA. 
Location. Damsite is on Raystown Branch, 
about 5.5 miles upstream from its confluence 
with Juniata River. Project is about 10 miles 
south of Huntingdon, Pa. (See Geological Survey 
Quadrangle sheets, Huntingdon, Mt. Union, 
Broad Top and Everett, Pa.) 
Existing project. Plan consists of a rock and 
earthfill dam rising 225 feet above streambed 
with a gated concrete spillway and auxiliary 
spillway in the right abutment. Reservoir 
capacity would be 762,000 acre-feet, of which 
248,000 acre-feet would be for flood control, 
476,000 acre-feet for recreation and water 
quality control and the balances as sediment 
reserve. At full flood control pool elevation, 
reservoir would inundate 10,800 acres and 
extend 34 miles upstream. Recreation facilities 
will be provided for boating, fishing, camping, 
hunting, and picnicking. Estimated Federal cost 
(1975) for new work, excluding power facilities, 
is $76,600,000 of which $45,435,000 is for 
construction and $31,165,000 is for lands and 
damages including relocations. 
4-14

BALTIMORE, MD., DISTRICT 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Land acquisition continued at a cost of 
$1,027,008. Work performed under contract 
included: Completion of phase V clearing at a cost 
of $14,833. The Seven Points public use and 
access facilities work was advanced to 47 percent 
complete at a cost of $2,306,000. Relocation of LR 
31019 began November 21, 1974 and is 99 percent 
complete. Costs were $260,048. Engineering and 
design costs were $130,823 and supervision and 
administration costs were $281,519. 
Maintenance: Operation and maintenance of 
the project continued. 
Condition at end of fiscal year. Construction of 
the project began in November 1968. The dam 
and appurtenances were operationally complete 
November 1, 1973. The overall project is 85 
percent complete. Work remaining consists of: 
completion of land acquisition, public use 
facilities, reservoir clearing, and raising LR 
31019. 
30. SOUTHERN NEW YORK FLOOD 
CONTROL PROJECTS 
Authorized plan provides for construction of 
reservoirs and related flood control works for 
protection of towns in New York and 
Pennsylvania. The improvements are located in 
the upper watershed of Susquehanna River to 
and including Chemung River. Individual units 
which constitute approved plan of improvement 
are listed in Table 4-H at end of chapter. (Also see 
Table 4-I at end of chapter.) 
30A. ADDISON, N.Y. 
Location. At confluence of Tuscarora Creek 
and Canisteo River in the City of Addison, N.Y. 
(See Geological Survey map for Addison, N.Y.) 
Existing project. Provides for construction of 
about 3,100 feet of earth levee and 700 feet of 
concrete floodwall on right bank of Canisteo 
River, extending from high ground on Steuben 
Street near Baltimore & Ohio Railroad to mouth 
of Tuscarora Creek; removal of existing dam, 
mill, and raceway from channel; construction of 
about 2,200 feet of earth levee on left bank of 
Tuscarora Creek, extending from Tuscarora 
Street to Canisteo River; construction of 4,600 
feet of earth levee on right bank of Tuscarora 
Creek, extending from high ground at southwest 
edge of village to high ground at southeast edge of 
village; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end offiscal year. Existing project 
was completed in 1947. 
30B. ALMOND LAKE, N.Y. 
Location. Dam is located two miles upstream 
from Hornell, N.Y., on Canacadea Creek, a 
tributary of the Canisteo River. (See Geological 
Survey map for Hornell, N.Y.) 
Existing project. The dam is an earthfill 
structure 1,260 feet long rising 90 feet above the 
streambed, with a concrete spillway and a gated 
outlet conduit in the left abutment. The outlet 
works consist of three 5-foot by 10-foot service 
gates and three emergency gates of the same size. 
The reservoir has a storage capacity of 14,640 
acre-feet at spillway crest. The project controls a 
drainage area of 56 square miles, 36 percent of 
the watershed of the Canisteo River upstream 
from Hornell, N.Y. Recreation facilities include a 
boat-launching ramp and dock, bathing beach, 
picnic area, and tent and trailer camping areas. 
Local cooperation. None required. Local 
interests have developed recreational facilities at 
the lake in conjunction with the Federal 
Government. These facilities are operated and 
maintained by the Steuben County Board of 
Supervisors. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
of project continued. 
Condition at end of fiscal year. The dam was 
operationally complete in fiscal year 1949 and 
physically complete in fiscal year 1956. 
Recreational facilities, including a seasonal 
recreation pool of 124 acres, boating, picnicking 
and sanitary facilities, were completed in fiscal 
year 1966. 
30C ARKPORT DAM, N.Y. 
Location. Dam is located five miles upstream 
from Hornell, N.Y., on the Canisteo River, a 
tributary of the Chemung River which flows into 
the Susquehanna River. (See Geological Survey 
map for Arkport, N.Y.) 
Existing project. The dam is an earthfill 
structure, 1,200 feet long, exclusive of spillway, 
rises 113 feet above streambed, with a concrete 
spillway and an ungated outlet in the right 
abutment. The outlet structure consists of an 8- 
foot diameter reinforced concrete lined conduit, 
660 feet long. A cast iron nozzle is placed in the 
lower end of the conduit, reducing the outlet size 
to 4 feet 4 inches. The reservoir has a storage 
4-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
capacity of 7,950 acre-feet at spillway crest. The 
project controls a drainage area of 31 square 
miles; 20 percent of the watershed of the Canisteo 
River upstream from Hornell. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Normal operation and maintenance of project 
continued. 
Condition at end of fiscal year. The dam was 
operationally complete in fiscal year 1940 and 
physically complete in fiscal year 1953. 
30D. AVOCA, N.Y. 
Location. On the Cohocton River at Village of 
Avoca, N.Y., about 30 miles upstream from 
confluence of Cohocton and Chemung Rivers. 
(See Geological Survey map for Avoca, N.Y.) 
Existing project. Provides for improvement 
and realinement of about 8,300 feet of Cohocton 
River channel, extending from above Erie 
Railroad to below junction of Main Street and 
U.S. Highway 15; construction of about 8,500 feet 
of earth levee on left bank of Cohocton River, 
extending from high ground above Alexander 
Avenue to about 1,300 feet below junction of Main 
Street and U.S. Highway 15; and 4,500 feet of 
earth levee on right bank of Salmon Creek, 
extending from high ground above Alexander 
Avenue to Erie Railroad: a new highway bridge 
for U.S. Highway 15 over Cohocton River, raising 
of Erie Railroad bridge 4 feet; and appurtenant 
drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end offiscal year. Existing project 
was completed in 1939. 
30E. BINGHAMTON, N.Y. 
Location. At the confluence of the Chenango 
and Susquehanna Rivers in the City of 
Binghamton, N.Y. (See Geological Survey map 
for Binghamton, N.Y.) 
Existing project. Provides for construction of 
earth levees, concrete floodwalls, and appurtenant 
drainage structures, consisting of about 
850 feet of channel excavation and about 1,375 
feet of earth levee along Phelps Creek, town of 
Pork Dickinson; new concrete wall on right bank 
of Chenango River, extending downstream from 
high ground near city limits to existing floodwall 
below DeForest Street, a distance of about 520 
feet: about 150 feet of concrete wall just below 
Cutler Dam: about 180 feet of concrete wall at 
pumphouse near McDonald Avenue; raising 
existing earth levees on right bank of Chenango 
River, extending from Cutler Dam downstream 
for about 1,220 feet: about 2,915 feet of earth levee 
on left bank of Chenango River north of city 
limits in village of Port Dickinson, extending 
from Church Street to high ground just north of 
city line; about 3,900 feet of earth levee on left 
bank of Chenango River, extending from 
DeForest Street to Cutler Dam: new concrete 
floodwalls and riverbank revetment for about 
5,570 feet extending on left bank of Chenango 
River from Cutler Dam to junction with 
Susquehanna River; about 540 feet of new 
concrete floodwall and raising about 1,085 feet of 
concrete floodwall on right bank of Susquehanna 
River, extending from Delaware, Lackawanna & 
Western Railroad downstream to Tompkins 
Street Bridge; about 1,940 feet of earth levee; 
about 1,940 feet of concrete floodwall; and 
capping about 125 feet of concrete floodwall, on 
right bank of Susquehanna River from 
Stuyvesent Street to mouth of Chenango River; 
about 8,380 feet of earth levee; about 2,180 feet of 
new concrete floodwall and raising about 125 feet 
of existing floodwall on left bank of susquehanna 
River extending from Pierce Creek to high 
ground at State Highway 17; a debris dam and 
flume between Corbett and Hotchkiss Streets 
and a concrete pressure conduit, 1,060 feet long to 
carry flow of Park Creek from Vestal Avenue to 
Susquehanna River; about 665 feet of levee 
extending from Erie Railroad to high ground 
along right bank of Chamberlain Creek near the 
mouth; closure structures at Erie Railroad and at 
Court Street; a weir, a drop structure, and about 
1,800 feet of earth levee, about 2,235 feet of 
channel excavation; about 645 feet of channel 
paving and raising about 470 feet of existing 
concrete floodwall and about 200 feet of new 
concrete floodwall for improvement of Pierce 
Creek from its mouth to about 1,000 feet above 
Conklin Avenue; and appurtenant drainage 
structures. Improvement, supplemented by 
authorized flood control dams above the area, 
will provide protection for City of Binghamton 
against a flood discharge about 20 percent 
greater than maximum flood of record, which 
occurred in July 1935 on Chenango River and in 
March 1936 on Susquehanna River. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end offiscal year. Existing project 
was completed in 1943. 
30F. CANISTEO, N.Y. 
Location. On Purdy and Bennetts Creeks in 
4-16

BALTIMORE, MD., DISTRICT 
town of Canisteo, N.Y., situated along the south 
side of Canisteo River, at the confluence of 
Bennetts Creek and Canisteo River. (See 
Geological Survey map for Canisteo, N.Y.) 
Existing project. Provides for construction of 
about 8,000 feet of earth levees on right bank of 
Canisteo River, extending from high ground 
1,570 feet west of State Highway Route 21 above 
village to a point at intersection of Ordway Lane 
and East Main Street; about 7,400 feet of earth 
levee on left bank of Purdy and Bennetts Creeks, 
extending from Main Street Bridge to high 
ground above Greenwood Street; 1,000 feet of 
earth levee on right bank of Bennetts Creek, 
extending upstream from Main Street Bridge; a 
concrete check dam with wing levees from 
Greenwood Street: a new highway bridge at 
Greenwood Street; alterations to existing timber 
check dams in Bennetts Creek; channel excavation 
in Bennetts and Purdy Creeks; and appurtenant 
drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end of fiscal year. Existing project 
was completed in 1948. 
30G. CORNING, N.Y. 
Location. On Chemung River in City of 
Corning, N.Y., about 44 miles upstream from 
confluence of Chemung River and North Branch 
of Susquehanna River. (See Geological Survey 
map for Corning, N.Y.) 
Existing project. Flood protection for this 
community was originally authorized by Flood 
Control Act of 1936. Plan of improvement 
provides for construction of a pumping station, 
earth levees, and concrete floodwalls, consisting 
of: about 4,3)0 feet of earth levee, enlargement of 
about 8,610 feet of existing earth levee and about 
3,100 feet of concrete floodwall on right bank of 
Chemung River, extending from Erie Railroad 
bridge to high ground at Park Avenue below city; 
about 200 feet of concrete floodwalls; about 2,500 
feet of earth levees and enlargement of about 
11,500 feet of existing earth levee on left bank of 
Chemung and Cohocton Rivers, extending from 
Erie Railroad bridge over Cohocton River mouth 
of Post Creek; about 2,500 feet of earth levee and 
enlargement of about 4,700 feet of existing earth 
levee on right bank of Post Creek from its mouth 
to Watkins Street; realinement of about 3,000 feet 
of channel, about 8,800 feet of earth levee, about 
3,000 of channel excavation, a pressure conduit 
about 400 feet long, a drop structure and a weir 
for improvement of Cutler Creek, extending 
from its mouth to high ground at Deckertown 
Road and Hornby Road; and appurtenant 
drainage structures. Flood protection on Monkey 
Run was authorized by Flood Control Act of 1950. 
Plan of improvement provides for construction of 
2,010 feet of open flume, 2,320 feet of pressure 
conduit storm sewers and appurtenant facilities 
between existing improved channel above Sixth 
Street and Chemung River at a point 
immediately east of Pine Street East. Modified 
improvement will provide protection for City of 
Corning against a flood discharge in Chemung 
River approximately equal to maximum flood of 
record, which occurred in May 1945, and on 
tributary streams against floods of greater 
magnitude than known to date. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end of fiscal year. Project was 
completed in 1942 except for work on Monkey 
Run, which was completed in 1955. 
30H. EAST SIDNEY LAKE, N.Y. 
Location. Dam is located near East Sidney, 
N.Y., on Ouleout Creek, about five miles above 
confluence of the creek with Susquehanna River. 
(See Geological Survey map for Franklin, N.Y.) 
Existing project. The dam is an earthfill and 
concrete structure, 2,010 feet long, including 
spillway, rises 128 feet above streambed and 
consists of a concrete gravity-type section with a 
compacted earth-dike section at the right 
abutment. The outlet works consist of five 
rectangular conduits each 3.5 feet by 5.85 feet 
and 105 feet long. The reservoir has a storage 
capacity of 33,500 acre-feet at spillway crest. The 
project controls a drainage area of 102 square 
miles which is 93 percent of the Ouleout Creek 
drainage area, and 5 percent of the watershed of 
the Susquehanna River upstream from 
Binghamton, N.Y., exclusive of the separately 
controlled Chenango River. Recreation facilities 
include a bathing beach, picnic and camping 
areas, and boat-launching and docking facilities. 
Local cooperation. None required. The Town of 
Sidney, N.Y., cooperated in the development of 
recreation facilities and operates and maintains 
all the facilities with the exception of the 
recreational pool, which is the responsibility of 
the Federal Government. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
of the project continued. 
Condition at end of fiscal year. The dam was 
operationally complete in fiscal year 1949 and 
physically complete in fiscal year 1956. 
4-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
301 ELMIRA, N.Y. 
Location. On Chemung River in City of Elmira, 
N.Y., about 27 miles upstream from confluence of 
Chemung River and North Branch of 
Susquehanna River. (See Geological Survey map 
for Elmira, N.Y.) 
Existing project. Provides for construction of 
about 17,700 feet of earth levees, and about 4,100 
feet of concrete floodwall on right bank of 
Chemung River, extending from South Hoffman 
Street to a point below city near upper end of Big 
Island; about 12,100 feet of earth levee and about 
6,300 feet of concrete wall on left bank of 
Chemung River extending from Durland Avenue 
to Delaware, Lackawanna & Western Railroad at 
mouth of Newton Creek; about 10,000 feet of 
earth levee on right bank of Newton Creek, 
extending from about intersection of Delaware, 
Lackawanna & Western Railroad and east 
Church Street to high ground near intersection of 
Sullivan and Warren Streets; about 4,300 feet of 
earth levee on right bank of Diven Creek; about 
2,000 feet of concrete conduit inclosing Hoffman 
Brook from West Second Street to Chemung 
River clearing islands and riverbanks of trees 
and brush for about 3.5 miles in Chemung River; 
about 14,300 feet of earth levee on left bank of 
Seely Creek, extending from Erie Railroad to 
high ground approximately 1,000 feet northwest 
of intersection of South Broadway and 
Pennsylvania Avenue; a pumping plant for 
disposal of interior drainage; an interceptor 
sewer about 6,000 feet long varying in size from 
48 to 96 inches in diameter; and appurtenant 
structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end of fiscal year. Existing project 
was completed in 1950. 
30J. HORNELL, N.Y. 
Location. On Canisteo River in City of Hornell, 
N.Y., about 42 miles upstream from confluence of 
Canisteo and Tioga Rivers. (See Geological 
Survey map for Canisteo, N.Y.) 
Existing project. Provides for channel 
realinement and construction of earth levees, 
concrete floodwalls, and check dams consisting 
of: realinement of about 4,600 feet of Canisteo 
River channel, and about 5,800 feet of earth levee 
on its right bank, extending from Seneca Street 
upstream to junction of Pittsburgh, Shawmut & 
Northern Railroad and Erie Railroad; construction 
of about 4,500 feet of earth levee, extending 
on both sides of Seneca Street from Canisteo 
River to Wrightman Avenue and junction of 
Cleveland Avenue and Bethesda Drive; 
construction of about 7,200 feet of earth levee, 
about 2,500 feet of concrete floodwall, and raising 
about 1,500 feet of existing concrete floodwall, on 
right bank of Canisteo River, and about 12,000 
feet of channel improvement, extending from 
Seneca Street to Erie Railroad; construction of 
about 2,500 feet of earth levee, about 2,100 feet of 
concrete floodwall on left bank of Canisteo River, 
extending from a point opposite Walnut Street to 
Erie Railroad; a ring-earth levee about 
2,800 feet long around sewage-disposal plant on 
left bank of Canisteo River; about 4,500 feet of 
realinement and improvement of Canisteo River 
channel, with about 4,500 feet of earth levee on its 
right bank, extending from Cedar Street 
downstream to about 1,400 feet above East 
Avenue; about 2,400 feet of channel paving, 1,400 
feet of earth levee, raising about 1,900 feet of 
concrete floodwall, and construction of one check 
dam on Canacadea Creek; about 1,600 feet of 
channel paying and construction of three check 
dams on Chauncey Run with about 300 feet of 
new wall and about 300 feet of capping; a weir, a 
check dam, 3,030 feet of channel paving, 4,800 
feet of floodwalls and levees, and related work on 
existing walls, all on Crosby Creek; removal of 6 
bridges, erection of 4 bridges, miscellaneous 
bridge structures, and 3 drop structures; and 
appurtenant drainage structures and small 
stream control works. Improvement, supplemented 
by Arkport and Almond Reservoirs 
above the area, provides protection for City of 
Hornell against a flood discharge approximately 
double maximum flood of record, which occurred 
in July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end of fiscal year. Existing project 
was completed in 1941. Rehabilitation of check 
dam on Canacadea Creek, by contract, began 
May 18, 1966 and was completed January 12, 
1967. Rehabilitation of deteriorated floodwalls 
along Canacadea and Crosby Creeks, by contract, 
began June 19, 1962 and was completed May 21, 
1963. 
30K. LISLE, N.Y. 
Location. On Tioughnioga River in village of 
Lisle, N.Y., about 12 miles upstream from 
confluence of Tioughnioga and Chenango Rivers. 
(See Geological Survey map for Lisle, N.Y.) 
Existing project. Provides for channel 
realinement and construction of earth levees and 
concrete floodwalls, consisting of: relocation of 
4-18

BALTIMORE, MD., DISTRICT 
about 3,000 feet of Dudley Creek channel, 
extending from 1,200 feet west of intersection of 
Cortland and Main streets to confluence with 
Tioughnioga River, realinement of some 5,700 
feet of Tioughnioga River channel east of village; 
about 4,150 feet of earth levee and 970 feet of 
concrete wall on right bank of Dudley Creek and 
Tioughnioga River, realinement of some 5,700 
feet of Tioughnioga Street to railroad crossing on 
River Street; raising about 1,860 feet of 
Delaware, Lackawanna & Western single track 
railroad over the levee; relocation of about 1,600 
feet of Cortland Street; a new bridge over 
relocated Dudley Creek; and appurtenant 
drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end of fiscal year. Existing project 
was completed in 1948. 
30L. OXFORD, N.Y. 
Location. On Chenango River in the village of 
Oxford, N.Y., about 40 miles upstream from 
confluence of Chenango and Susquehanna 
Rivers. (See Geological Survey map for Oxford, 
N.Y.) 
Existing project. Provides for construction of 
earth levees and clearing of Chenango River 
channel, consisting of about 2,100 feet of earth 
levees on left bank of Chenango River, extending 
from high ground near Cemetery Drive and 
running mostly along railroad to high ground 
near Main Street; removal of dam and island 
below Main Street; raising Delaware, Lackawanna 
& Western Railroad over levee; and 
appurtenant closure and drainage structures. 
Improvement provides protection for village of 
Oxford on left bank against a flood discharge 
substantially larger than maximum flood of 
record, which occurred in July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
Condition at end offiscal year. Existing project 
was completed in 1938. 
30M. WHITNEY POINT LAKE, N.Y. 
Location. Dam is located near Whitney Point, 
N.Y., on the Otselic River about 0.7 of a mile 
upstream from its confluence with Tioughnioga 
River. (See Geological Survey map for Whitney 
Point and Willet, N.Y.) 
Existing project. The dam is an earthfill 
structure, 4,900 feet long, exclusive of spillway, 
rises 95 feet above the streambed, with a concrete 
spillway and a gated outlet in the left abutment. 
The outlet works consist of three 5-foot by 10-foot 
gates and one emergency gate of the same size. 
The reservoir has a storage capacity of 86,440 
acre-feet at spillway crest. The project controls a 
drainage area of 255 square miles, the entire 
watershed of Otselic River, or 16 percent of the 
Chenango River watershed upstream from 
Binghamton, N.Y. Recreation facilities were 
provided for swimming, picnicking, camping, 
and boating. 
Local cooperation. None required. The Broome 
County Board of Supervisors operates and 
maintains all the recreational facilities except 
the boat launching ramp, parking area, and 
access roads which are the responsibility of the 
Federal Government. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
of the project continued. 
Condition at end of fiscal year. The dam was 
operationally complete in fiscal year 1942 and 
physically complete in fiscal year 1953. Access 
road construction to Area No. 3 was performed 
under three contracts. The first contract, 
providing for a turn around and for relocating 
those sections of the road inundated by the 
summer lake, was completed June 16, 1967. The 
second contract provided for improvement of a 
portion of the remaining sections of the access 
road and was completed August 23, 1968. The 
third contract provided for completing the 
remaining section of the access road and parking 
area and was completed October 15, 1970. 
30N. WHITNEY POINT VILLAGE, N.Y. 
Location. On Tioughnioga River at the 
confluence of Tioughnioga and Otselic Rivers, 
tributaries of the Susquehanna River. (See 
Geological Survey map for Whitney Point, N.Y.) 
Existing project. Provides for channel 
realinement and construction of earth levees, 
consisting of realinement of about 1,800 feet of 
Tioughnioga River channel, above confluence 
with Otselic River; about 7,100 feet of earth levee 
along right bank of Tioughnioga River, 
extending from high ground on Main Street 
above village to Collins Street just below village; 
and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Normal operation and maintenance of the project 
continued. 
4-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Condition at end of fiscal year. Existing project 
was completed in 1948. 
31. STILLWATER LAKE 
LACKAWANNA RIVER, PA. 
Location. Dam is on Lackawanna River, 39 
miles from mouth of stream and about 4 miles 
upstream from Forest City, Susquehanna 
County, Pa. (See Geological Survey Quadrangle 
sheet, "Honesdale, Pa.") 
Existing project. Dam is earthfill type, rising 
77 feet above streambed, with a controlled outlet 
conduit and side channel spillway in left 
abutment. Reservoir capacity is 12,000 acre-feet, 
of which 11,600 acre-feet is flood control storage 
and remainder utilized to maintain existing 
water supply reservoir for Forest City, Pa., at 
this site. Reservoir area is 422 acres, and pool 
extends about 2.1 miles upstream. Reservoir 
controls 52 percent of watershed above 
Carbondale, 26 percent above Olyphant, and 17 
percent above Scranton. Federal cost of new 
work, completed in 1965, was $5,725,700 of which 
$4,500,500 was for construction and $1,225,200 
was for lands and damages. 
Local cooperation. None required. Section 2, 
Flood Control Act of June 28, 1938, applies. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
of project continued. 
Condition at end of fiscal year. Construction of 
project was completed in 1964. 
32. SUSQUEHANNA RIVER FLOOD 
CONTROL PROJECTS, N.Y. AND 
PA. 
Plan of improvement authorized by 1958 Flood 
Control Act provides for construction of 
Cowanesque Lake, Pa., Tioga-Hammond Lakes, 
Pa., local protection works at Elkland, Pa., and 
Nichols, N.Y., and channel improvements at 
Cortland, N.Y. This project plan supplemented 
the comprehensive flood control program for 
Southern New York and northern Pennsylvania 
which included Southern New York flood control 
project and Stillwater, Genegantslet, and South 
Plymouth Reservoirs. (See Tables 4-J and 4-K at 
end of chapter.) 
32A. COWANESQUE LAKE, PA. 
Location. Dam will be on Cowanesque River 
about 2.2 miles above its confluence with Tioga 
River at Lawrenceville, Pa. (See Geological 
Survey map for Tioga, Pa.) 
Existing project. Provides for construction of 
an earthfill dam, 3,100 feet long and rising 151 
feet above streambed, with an uncontrolled 
spillway in right abutment and a gated conduit in 
valley floor. Flood control storage would be 
82,000 acre-feet, equivalent to 5.6 inches of runoff 
from drainage area. Estimated Federal cost 
(1975) of new work if $92,600,000, of which 
$57,705,000 is for construction and $34,895,000 
for lands and damages and relocations. 
Operations and results during fiscal year. Land 
acquisition continued at a cost of $1,535,224. 
Highway relocation Unit I was advanced to 99 
percent complete at a cost of $547,625. The 
Highway relocation Unit II contract was 
awarded October 17, 1974 and work is 42 percent 
complete. Costs were $4,843,993. Utility 
relocations continued at a cost of $826,545. 
Engineering and design and supervision and 
administration costs were $1,189,364 and 
$345,153, respectively. 
Condition at end of fiscal year. Construction of 
the project began July 24, 1973. The overall 
project is 15 percent complete. 
32B. TIOGA-HAMMOND LAKES, PA. 
Location. The dams will be located in Tioga 
County, Pa., upstream from the confluence of the 
Tioga River and Crooked Creek. Tioga Dam will 
be located on the Tioga River and Hammond 
Dam on Crooked Creek, approximately opposite 
the Tioga damsite, about 3.3 miles above its 
mouth and less than one mile from the village of 
Brooklyn. (See Geological Survey map for Tioga, 
Pa.) 
Existing project. Tioga Dam will be 2,600 feet 
long, rising 140 feet above streambed, with a 
controlled outlet conduit. Hammond Dam will be 
5,900 feet long, a maximum height of 121.5 feet 
above streambed, with a concrete spillway. Both 
dams will be of earth and rockfill construction. 
The Tioga-Hammond Lakes project will control a 
total drainage area of 402 square miles, with 
Tioga Dam controlling 280 square miles of the 
Tioga River Basin and Hammond Dam 
controlling 122 square miles of the Crooked 
Creek Basin. Recreation facilities will be 
provided for swimming, camping, picnicking, 
boating, and fishing. Estimated Federal cost 
(1975) of new work is $157,700,000, of which 
$107,000,000 is for construction and $50,700,000 
for lands and damages and relocations. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Land acquisition continued at a cost of 
$1,954,989. Work performed under contract 
included: Relocation of Pennsylvania Highway 
287 and Penn Central railroad Unit II172 percent 
complete, $3,447,610; Relocation of Penn Central 
railroad Unit III 90 percent complete, 
4-20

BALTIMORE, MD., DISTRICT 
$1,741,907; US 15 relocation 62 percent 
complete, $4,422,266; excavation and embankment 
construction 36 percent complete, 
$8,273,980; relocation of LR 58044 - Section 5 
began April 25, 1975 and is 12 percent complete, 
$280,631; and construction of structures and 
appurtenant works began April 1 and is 2 
percent complete, $692,941. Relocation of 
utilities continued at a cost of $510,012. 
Engineering and design and supervision and 
administration costs were $1,087,274 and 
$668,928, respectively. 
Condition at end of fiscal year. Construction of 
the project began October 5, 1971. The overall 
project is 34 percent complete. 
33. TYRONE, PA. 
Location. On left bank of Little Juniata River, 
15 miles above its confluence with Frankstown 
Branch, and 116 miles above mouth of Juniata 
River. Bald Eagle Creek, Sink Run, and Schell 
Run, draining 53, 7, and 2 square miles, 
respectively, flow through the city. (See 
Geological Survey Quadrangle sheet, "Tyrone, 
Pa.") 
Existing project. Plan of improvement for 
Little Juniata River will consist of levees and 
walls along left bank, a drop structure, channel 
improvements in river, and protection of bridges. 
Channel improvements on Bald Eagle Creek will 
consist of new levee and wall on right bank, 
concrete overflow dam, concrete flume, and 
stilling basin. Sink Run will be diverted to Schell 
Run watershed about a mile upstream from the 
borough. Improvements for Schell Run will 
consist of a conduit with intake structure and a 
debris basin at the upstream end, and a stilling 
basin at the downstream end. Improvement will 
provide protection for Borough of Tyrone against 
a flood discharge equal to maximum flood of 
record, which occurred in March 1936. 
Estimated Federal and local costs (1975) are 
$31,000,000 and $3,000,000 respectively. 
Local cooperation. Local interests must furnish 
lands, and rights-of-way necessary for construction 
of project, hold the United States free from 
damages due to construction works, and 
maintain and operate all works after completion 
in accordance with regulations prescribed by the 
Secretary of the Army. An agreement of local 
cooperation was signed by the Director of Real 
Estate, Office of the Chief of Engineers, for, and 
in behalf of, the Secretary of the Army on 
February 14, 1972. 
Operations and results during fiscal year. 
Construction of the Schell Run Conduit was 
advanced to 63 percent complete at a cost of 
$1,504,746. Engineering and design and 
supervision and administration costs were 
$216,240 and $91,108, respectively. 
Condition at end of fiscal year. Construction of 
the project began July 20, 1972. The overall 
project is 14 percent complete. 
34. WEST BRANCH OF 
SUSQUEHANNA RIVER, PA. 
A system of three flood control reservoirs in 
headwaters of West Branch Susquehanna River, 
Pa. The reservoirs, to be known as Curwensville, 
Alvin R. Bush, formerly known as Kettle Creek, 
and Foster Joseph Sayers formerly known as 
Blanchard, are on West Branch about 2.5 miles 
upstream from Curwensville, Pa.; on Kettle 
Creek 8.4 miles above the mouth and 16 miles 
upstream from Renovo, Pa.; and on Bald Eagle 
Creek about 1 mile upstream from Blanchard, 
Pa., respectively. (See Table 4-L at end of 
chapter.) 
In accordance with the terms of local 
cooperation, the Commonwealth of Pennsylvania 
furnished assurances that it will coordinate 
operation of George B. Stevenson Reservoir, 
formerly known as First Fork Reservoir, with 
operation of Curwensville, Alvin R. Bush, and 
Foster Joseph Sayers Reservoirs, to secure 
optimum flood control benefits from system 
operation. George B. Stevenson Reservoir on 
First Fork Sinnemahoning Creek in Cameron 
and Potter Counties, Pa., was constructed by 
Commonwealth of Pennsylvania at a first cost of 
$12,240,000 and an estimated $30,000 annually 
for operation and maintenance. 
34A. ALVIN R. BUSH DAM, PA. 
Location. Alvin R. Bush Dam (formerly Kettle 
Creek Dam) is located on Kettle Creek about 8.4 
miles above the mouth and 15 miles upstream 
from Renovo. Pa. (See Geological Survey map for 
Keating, Pa.) 
Existing project. Dam is an earthfill structure, 
about 1,350 feet long, rises 165 feet above the 
streambed, with an uncontrolled spillway located 
in rock adjacent to the right abutment, and a 
horseshoe-shaped outlet tunnel with 3 service 
gates. The reservoir has a storage capacity of 
75,000 acre-feet at spillway crest. The project 
controls a drainage area of 226 square miles or 
about 92 percent of the Kettle Creek watershed. 
Recreation facilities include a tenting and 
camping area, parking area, bathing area, and 
boat ramp. 
Local cooperation. None required. The Commonwealth 
of Pennsylvania operates and 
maintains the recreational facilities. 
4-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. 
Normal operations and results during fiscal year. 
Maintenance: Hired labor work consisted of 
normal operation and maintenance of the project 
at a cost of $94,141.35 and completion of remedial 
work for seepage control at a cost of $83,888.34. 
Condition at end of fiscal year. Construction of 
project began in May 1959 and was completed in 
February 1962. 
34B. CURWENSVILLE LAKE, PA. 
Location. Dam is on West Branch of the 
Susquehanna River approximately 2.5 miles 
upstream from Curwensville, Clearfield 
County, Pa. (See Geological Survey map for 
Curwensville, Pa.) 
Existing project. Dam is an earthfill structure, 
about 2,850 feet long, rises 131 feet above the 
streambed, with an open-cut concrete sill, 1,750 
feet from the left abutment. The outlet works 
located in the left abutment, consist of a 15-foot 
diameter circular outlet conduit with 3 slide 
control gates 5.5 feet wide and 12 feet high. The 
reservoir has a storage capacity of 119,300 acrefeet 
at spillway crest. The project controls a 
drainage area of 365 square miles, or about 98 
percent of the West Branch Susquehanna River 
at Curwensville and about 75 percent at 
Clearfield. Recreation facilities include a 
seasonal recreational pool of 540 acres, access 
roads, parking areas, beach area, camping area, 
boat dock and launching ramp. 
Local cooperation. None required. The 
Commonwealth of Pennsylvania operates and 
maintains the recreational facilities. 
Operations and results during fiscal year. 
Maintenance: Normal operation and maintenance 
of project continued. Outlet channel 
improvements, by contract, were completed in 
July 1974 at a cost of $352,257.26. 
Condition at end of fiscal year. Construction of 
project began May 1962 and was completed 
November 1966. 
34C. FOSTER JOSEPH SAYERS DAM, 
PA. 
Location. Dam is located on Bald Eagle Creek 
in Centre County, Pa., about one mile upstream 
from Blanchard and about 14 miles above the 
confluence of Bald Eagle creek with the West 
Branch Susquehanna River at Lock Haven, Pa. 
(See Geological Survey map for Howard, Pa.) 
Existing project. Dam is an earthfill structure, 
about 6,835 feet long, rises 100 feet above the 
streambed, with an open-cut concrete chute and 
uncontrolled concrete weir 600 feet wide located 
in rock in a saddle adjacent to the left abutment. 
The outlet works, located in the left abutment, 
consist of a 15-foot diameter circular outlet conduit 
with two hydraulically-operated wheel 
gates 7 feet wide and 15 feet high. The reservoir 
has a storage capacity of 99,000 acre-feet at 
spillway crest. The project controls a drainage 
area of 339 square miles or 88 percent of the 
drainage area above Beech Creek and 43 percent 
of the Bald Eagle Creek drainage area. 
Recreation facilities will include a summer 
recreation pool of 1,730 acres and a conservation 
pool of 630 acres for the preservation of fish life. 
Access roads, parking areas, a beach area, boat 
docks and launching ramps and camping areas 
will be provided. 
Local cooperation. None required. The 
Commonwealth of Pennsylvania will operate and 
maintain all recreational facilities when 
completed. 
Operations and results during fiscal year. New 
work: Repair of damaged sections of the sanitary 
piping system, by contract, began June 29, 1974 
and was completed October 8, 1974. 
Maintenance: Normal operation and maintenance 
of the project continued. 
Condition at end of fiscal year. The project is 
complete and has been operational since August 
1969. Construction of the project began in March 
1965 and was completed in September 1972. 
35. YORK, CODORUS CREEK, PA. 
Location. On Codorus Creek 10 miles above its 
confluence with main Susquehanna River. 
Codorus Creek withs its tributary branches is in 
York county in south and central parts of 
Pennsylvania. (See Geological Survey Quadrangle 
sheets, "Pennsylvania - York and 
Hanover.") 
Existing project. Construction of Indian Rock 
Dam, an earth and rockfill dam about 1,000 feet 
long at top, rising 83 feet above streambed, with a 
reservoir providing for controlled storage of 
28,000 acre-feet at elevation of spillway crest. 
Dam is on main branch of Codorus Creek about 3 
miles above York. Outlet works are in right 
abutment and uncontrolled spillway is on right 
bank, discharging upstream from tunnel outlet. 
Reservoir will control entire drainage area of 
main branch of Codorus Creek and 41 percent of 
drainage area above York. Plan also provides for 
improvements to Codorus Creek channel in 
vicinity of and through City of York for about 
22,969 feet extending from 300 feet above 
Richland Avenue to a point downstream from 
Pennsylvania Railroad crossing known as Black 
Bridge. Improvements, which will increase 
channel capacity to 24,000 cubic feet per second, 
4-22

BALTIMORE, MD., DISTRICT 
include widening and deepening channel, 
constructing bank protection, removing York 
Roller Mill Dam, and construction of a low water 
channel about 3,900 feet long in vicinity of York 
Roller Mill Dam. Cost of new work for completed 
project was $5,061,167, of which $4,566,446 
(regular funds) and $11,588 (emergency relief 
funds) was for construction and $483,133 
(regular funds) for lands and damages. 
Local cooperation. Section 2. Flood Control Act 
of June 28, 1938, applies. 
Operations and results during fiscal year. 
Normal operation and maintenance of project 
continued. 
Condition at end of fiscal year. Project was 
operationally complete in November 1947 and 
remaining construction features were completed 
in September 1952 and November 1955. 
36. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Projects in New York, Pennsylvania, 
Maryland, District of Columbia, and Virginia, 
were inspected during fiscal year by hired labor. 
37. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Operations and results during fiscal year. The 
operation of George B. Stevenson Dam, Pa., was 
coordinated with the operation of Alvin R. Bush, 
Curwensville, and Foster Joseph Sayers Dams in 
the West Branch Susquehanna River Basin in 
order to secure optimum flood control benefits 
from the system operation. Costs during the fiscal 
year were $4,005. 
Supplemental instructions for the operation of 
Savage River Dam, Md., were provided, during 
periods of high water, to insure maximum 
protection for downstream localities. Costs 
during the fiscal year were $2,995. 
38. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 4-M at end of chapter.) 
39. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation). 
(See Table 4-N at end of chapter.) 
Flood control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended 
(preauthorization). 
Fiscal year costs were $51,824.71 for Bull Run, 
Loyalsock Township, Pa., $6,000 for Deep Run, 
Elkridge, Md., and $5,000 for Spring Creek, 
Swatara Township, Pa. 
Emergency bank protection (Sec. 14, 1946 
Flood Control Act, Public Law 526, 79th 
Congress). 
Fiscal year costs were $2,000 for Bath, N.Y., 
and $1,900 for Marathon, N.Y. 
Water Supply 
40. POTOMAC ESTUARY PILOT 
WATER TREATMENT PLANT 
Location. The project is located in Washington, 
D.C., in the area of the Blue Plains wastewater 
plant adjoining the Potomac River. 
Existing project. The project consists of a water 
treatment plant with a nominal capacity of one 
million gallons per day that includes advanced 
treatment processes and an evaluation 
laboratory. 
Local cooperation. Approval will be necessary 
from the D.C. government for constructing the 
plant on approximately 1.5 acres of land 
available at the Blue Plains water treatment 
facility in Washington. Studies will be 
accomplished during preconstruction planning 
to determine an appropriate method of financing 
by the District of Columbia and other benefiting 
governmental entities with such funding 
arrangement subject to approval by the 
Secretary of the Army prior to initiation of 
construction. 
Operations and results during fiscal year. 
Preconstruction planning was initiated in 
November 1974. A contract for preparation of the 
general design memorandum and plans and 
specifications was awarded May 9, 1975. 
Condition at end of fiscal year. Preconstruction 
planning initiated. 
41. VERONA LAKE, VIRGINIA 
Location. The project is located in Augusta 
County, Virginia, about nine miles northeast of 
Staunton, Virginia, on the Middle River Branch 
of the South Fork Shenandoah River. 
Existing project. The plan of improvement 
provides for a concrete-gravity dam with gated 
outlet conduits and a gate-controlled spillway as 
integral parts of the concrete-gravity structure. 
The project will provide 104,000 acre-feet of 
storage for water supply and recreation. 
Preliminary proposals for development include 
4-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
two administrative areas, one wayside area, 
three day-use areas, one marina, four camp 
areas, and five additional access areas. 
Estimated cost (1975) of new work is $55,100,000 
of which $32,539,000 is required non-federal 
reimbursement. 
Local cooperation. Prior to construction, 
responsible local interests must agree to repay all 
costs allocated to water supply amounting to 49.7 
percent of the construction cost of the project, 
presently estimated at $27,398,000 and pay 
annually the costs of operation, maintenance, and 
replacements allocated to water supply 
amounting to 31.4 percent of these annual costs, 
presently estimated at $76,000. Local interests 
must also agree to pay, contribute in kind, or 
repay (which may be through user fees) with 
interest, not less than one-half the separable first 
cost of the project allocated to general recreation 
and fish and wildlife enhancement - such costs 
are presently estimated at $5,141,000 for initial 
facilities and $1,915,000 for future development 
- and bear separable costs of operation, 
maintenance, and replacement of recreation and 
fish and wildlife enhancement, presently 
estimated at $89,000 annually. 
Operations and results during fiscal year. 
Preconstruction planning was initiated in 
November 1974. A contract for aerial 
photography and mapping of the project area 
was awarded May 14, 1975. 
Condition at end offiscal year. Preconstruction 
planning initiated. 
General Investigations 
42. SURVEYS 
Costs for the fiscal year were $3,739,031.21 of 
which $41,174.64 was for navigation studies, 
$345,819.02 for flood control studies, $31,621.52 
for beach erosion control studies, $2,288,407.37 
for special studies, $865,385.10 for comprehensive 
basin studies, $10,292.29 for review of 
authorized projects, $12,625.68 for inventory of 
dams, and $143,705.59 for coordination studies 
with other agencies. 
43. COLLECTION AND STUDY OF 
BASIC DATA 
Cost for flood plain information studies during 
the fiscal year was $311,304.93. Gathering 
existing hydrologic and hydraulic data, and 
development of new flood data for presentation in 
a form usable to guide local interests in planning 
decisions on flood plain use, were in progress at 
end of fiscal year. (See Table 4-0 at end of 
chapter.) 
44. MISCELLANEOUS ACTIVITIES 
MAINTENANCE, OPERATIONS, 
AND CAPITAL OUTLAY OF THE 
WASHINGTON AQUEDUCT 
Location. The diversion dam and raw water 
supply intakes at Great Falls, the two collecting 
conduits, part of Dalecarlia receiving reservoir, 
the booster pumping station, and the Little Falls 
raw water pumping station are located in 
Maryland. All other structures of the water 
supply system, including parts of the raw water 
collecting system, two purification plants, 
pumping stations, storage reservoirs, and 
transmission mains are in the District of 
Columbia. Federally owned water mains are 
maintained in Virginia and Maryland. 
Existing Project. Control of the water supply 
system is vested in Chief of Engineers (See acts of 
March 3, 1859, and March 2, 1867, November 22, 
1973 and Sec. 1800 of Revised Statutes). The 
project includes administration, operation, 
maintenance, and protection of water supply 
system, including operation and maintenance of 
collection, purification, pumping, engineering, 
and construction of major water system additions 
and improvements. 
Authority to supply water to adjacent 
Maryland areas and to Arlington County, the 
City of Falls Church, and other jurisdictions in 
Virginia is contained in the following Public 
Laws: Public Law 378, 64th Congress, of March 
3, 1917; Public Law 119, 69th Congress, approved 
April 14, 1926; and Public Law 118, 80th 
Congress, June 26, 1947. 
Local cooperation. Prior to July 1, 1880, 
expenses of Washngton Aqueduct for construction, 
operation, and maintenance were paid 
entirely out of revenues of the United States. 
From July 1, 1880 to June 30, 1882, half of the 
expenses of operation and maintenance were 
paid by the United States and the other half came 
from the general revenues of the District of 
Columbia. From July 1, 1882 to June 30, 1898, 
one-half of construction costs were charged to a 
capital account on the books of the Treasury to be 
repaid by the District of Columbia from water 
rents with 3 percent interest. From July 1, 1898 
to June 30, 1916, expenses of construction, operation, 
and maintenance were paid one-half from 
the United States Treasury. From July 1, 1916 to 
June 30, 1927, 60 percent of the expense of construction 
was paid from the general revenues of 
the District of Columbia and 40 percent was paid 
by the United States. From July 1, 1916 to date, 
all expenses of operation and maintenance have 
been paid from the Water Fund of the District of 
Columbia which was established by Congress to 
receive the water revenues from water consumed 
by the Federal Government, the District of 
Columbia, Arlington County, Va., and Falls 
4-24

BALTIMORE, MD., DISTRICT 
Church, Va., as well as loans from the U.S. 
Treasury for Capital Improvements. From July 
1, 1927 to date, all expenses for construction 
have been paid from loans and revenues 
deposited in the Water Fund. 
Public Law 533, 81st Congress, 2nd session, 
authorized the Secretary of the Treasury to lend 
to the Commissioners of the District of Columbia 
such sums as may hereafter be appropriated 
(with a limit of $23,000,000) to finance expansion 
and improvement of the water system when 
sufficient funds therefore are not available from 
the District of Columbia Water Fund established 
by law (D.C. Code 1940 edition, title 1943, ch. 15). 
The borrowing limit was extended by Public Law 
364, 83rd Congress, 2nd session, to $35,000,000 
and again by Public Law 650, 91st Congress, 2nd 
session to $51,000,000. From April 1953 to June 
30, 1975, $44,290,000 was borrowed from the 
United States Treasury, in installments, to 
finance expansion and improvement of the water 
system as authorized by the above laws. 
Fiscal year 1948 through fiscal year 1954, 
pursuant to Public Law 195, 80th Congress, 1st 
session, $1,000,000 was authorized each year for 
water consumed by the Federal Government. 
Public Law 364, 83rd Congress, 2nd session, 
known as the "District of Columbia Public Works 
Act of 1954," provided for payment by the United 
States for all water and water services furnished 
within the District of Columbia at the rates 
applicable to other consumers in the District of 
Columbia. For water used outside the District, 
the rates applicable are those charged to the 
respective local jurisdictions within which the 
Federal facilities are situated. 
Operations and results during the fiscal year. 
An uninterrupted and adequate supply of purified 
water was furnished to the District of 
Columbia; Arlington County, and Falls Church, 
Virginia; and to Federal establishments in the 
District of Columbia, Arlington County, 
Virginia, and Montgomery and Prince Georges 
counties in Maryland. Total consumption for the 
year was 70,338 million gallons; the maximum 
daily consumption was 257.5 million gallons and 
average daily consumption was 192.7 million 
gallons. Average per capita consumption was 
180.4 gallons per day. The average amount 
furnished Arlington County and Falls Church, 
Virginia, was 40.3 million gallons per day. The 
D.C. Water Fund was reimbursed in the amount 
of $1,915,383 for water furnished to the Virginia 
communities. Maryland communities were 
supplied an average of 23,562 gallons per day 
during fiscal year 1975 by the District of 
Columbia through connections to the Washington 
Surburban Sanitary Commission system. 
On June 23, 1952, fluoridation equipment was 
placed in service. The application of fluoride to 
the water supply has been continuous since that 
date. 
Average turbidity of raw water from the 
Potomac River was 31 Jackson Units and the 
average Most Probable Number of coliform 
bacteria was 27,565. After treatment, the 
average turbidity of the filtered water was 0.15 
and the average Most Probable Number of 
coliform bacteria per 100 milliliters was 0.15. 
The average calcium carbonate alkalinity of the 
filtered water was 67 P.P.M. and the average pH 
value was 7.9. Average hardness was 130 P.P.M. 
Analyses were made for coliform bacteria on 
129,101 tubes of Lactose broth inoculated with 
water taken from 228 sampling points in the 
collection, purification, and distribution systems. 
Approximately 94,820 physical and chemical 
tests were made on 10,922 water samples from 
the supply and distribution system. Fluoride 
content of 3,848 water samples was determined. 
During fiscal year 1975, direct operating costs 
of water treated and delivered to system per 
million gallons was $87.72. Similar costs during 
fiscal year 1974 were $69.79 per million gallons. 
Visitors. During the year, 1,384 persons toured 
the water supply facilities, including 10 from 
foreign countries. 
Control. All funds were expended in 
conformity with legislative provision contained 
in the annual appropriation act which is as 
follows: 
"Nothing herein shall be construed as 
affecting the superintendence and control of 
the Secretary of the Army over the 
Washington Aqueduct, its rights, appurtenances, 
and fixtures connected with the 
same, and over appropriations and 
expenditures therefore as now provided by 
law." 
Condition at end of fiscal year. The intakes, 
conduits, reservoirs, filter plants, pumping 
stations, mechanical equipment, and structures 
were generally in good condition. During 
maximum demand periods, the Little Falls raw 
water pumping station was operated to augment 
the raw water supply provided by the gravityflow 
conduits. 
Construction work authorized with "no year" 
funds not previously reported as completed was 
as follows: 
New shops and storehouses, Dalecarlia, 52%; 
Great Falls intake structure, 100 percent, flood 
and water quality protection, Dalecarlia, 99 percent; 
emergency pumping from Potomac River 
estuary, 11 percent. 
4-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
TABLE 4-A 
See 
Section 
in Text Project Funding FY 72 FY 73 
Total Cost 
to 
FY 74 FY 75 30 June 1975 
1. Baltimore Harbor and New Work 
Channels, Md. Approp. 
Cost 
Maint. 
Approp. 
Cost 
2. Baltimore Harbor, Md. Maint. 
Collection and Approp. 
Removal of Drift Cost 
3. Chester River, New Work 
Md. Approp. 
Cost 
4. Choptank River, Md. 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. Harbor of Baltimore Maint. 
Md. Prevention of Approp. 
Obstructions and Cost 
Injurious Deposits 
6. Knapps Narrows, Md. New Work 
Approp. 
Cost 
7. Nanticoke River at 
Bivalve, Md. 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
8. Neabsco Creek, Va. New Work 
Approp. 
Cost 
9. Ocean City Harbor and New Work 
Inlet and Sinepuxent Approp. 
Bay, Md. Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
10. Potomac and Anacostia Maint. 
Rivers, D.C., Collection Approp. 
and Removal of Drift Cost 
37,700 -25,800 - - 37,418,716' 
10,091 564 440 349 37,418,2601 
884,4082 637,9844 169,2956 785,1007 17,709,2989 
840,7773 644,4335 183,4886 769,9218 17,694,1199 
17,900 78,700 76,070 85,000 1,291,367 
60,981 79,534 82,399 84,982 1,290,085 
- - - - 70,49510 
- - - - 70,49510 
1,400 - 124,022 9,458 486,986 
11,000 - 121,168 12,312 486,986 
- - - - 95,796 
2,406 - - 4,303 95,438 
- - - 1,973 61,353 
- - - 1,973 61,353 
179,400 146,700 208,000 200,000 2,534,053 
153,636 160,722 222,186 199,941 2,533,994 
- - - - 46,121" 
- - - - 46,12111 
1,100 
788 
1.106 
2,233 
2,545 
- 160,600 340,701 
- 160,600 340,701 
- - 240,817 
- - 240,817 
- 93,827 
- 21,405 
- 5,000 
18 - 
4,000 122,173 
76,422 122,173 
- 14.600 
2,755 12,355 
- 350,19312 
- 350,19312 
388,000 138,000 -15,975 99,500 3,295,085 
194,436 435,365 137,478 101,000 3,295,085 
- - - - 264,000 
- - - - 264,000 
197,000 378,600 232,130 338,000 1,919,417 
191,418 386,739 243,290 341,480 1,918,854 
11. Potomac River and 
Tributaries at and 
Below Washington, 
D.C., Elimination of 
Waterchestnut 
12. Slaughter Creek, 
Md. 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
3,900 -1,800 
1,849 1,391 
3,500 
3,636 
5,000 177,394 
5,000 177,394 
- - - 4,140 
- - - 4,140 
- 123,700 -23,000 107,526 
- 40,111 55,009 101,946 
4-26 
1- ~ - - -- - -- I-~ - -~ -- - -- --

BALTIMORE, MD., DISTRICT 
COST AND FINANCIAL STATEMENT 
TABLE 4-A (Continued) 
See 
Section 
in Text Project 
13. Tred Avon River, 
Md. 
14. Twitch Cove and 
Big Thorofare, 
Md. 
15. Upper Thorofare, 
Deal Island, Md. 
16. Washington Harbor, 
D.C. 
17. Wicomico River, Md. 
23. Anacostia River and 
Tributaries, Flood 
Protection and 
Navigation Improvements, 
D. C. and Md. 
24. Anacostia River and 
Tributaries, Prince 
Georges Co., Md. 
(Contributed Funds) 
25. Bloomington Lake, 
North Branch 
Potomac River, 
26. Cumberland, Md. 
and Ridgeley, 
W. Va. 
27. Fourmile Run, Va. 
(Contributed Funds) 
28A. Aylesworth Creek 
Lake, Pa. 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Approp. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Con't 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost 
to 
FY 72 FY 73 FY 74 FY 75 30 June 1975 
- 10,000 495,437 - 528,13018 
5,840 3,781 6,956 458,387 489,88613 
-- - - 13,843 
- - - - 13,843 
- - - - 193,175 
- - - - 193,175 
- - 56,005 12,200 575,377 
54,444 - 56,005 12,200 575,377 
- - - - 62,44614 
- - - - 62,44614 
- - -10,199 179,847 
- - - 10,199 179,847 
- - - - 3,191,00715 
- - - - 3,191,00715 
33,600 10,200 8,178 12,000 3,689,03816 17 
2,731 48,361 11,498 12,000 3,689,03816 17 
- - - - 471,60918 
- - - - 471,60918 
- - -110,084 658,45219 
- - - 109,334 657,70219 
- - - - 6,042,325 
- - - 6,042,325 
4,241 
450,000 
31,647 
10,500 251,979 53,100 790,434 
6,112 160,662 148,805 790,434 
400,000 53,000 - 1,000,00020 
169,019 732,983 16,130 999,93920 
204,305 264,000 - 468,305 
- 317,984 16,370 334,354 
5,316,800 15,000,000 15,463,500 6,250,000 50,314,300 
5,813,553 11,373,728 14,010,852 10,998,007 47,709,445 
- - - - 15,633,97021 22 
- - - - 15,633,97021 22 
13,800 6,300 14,500 17,000 184,511 
13,071 13,080 21,343 17,012 184,511 
413,300 1,818,000 2,540,000 1,950,000 6,731,300 
287,674 794,250 666,830 3,158,031 4,906,786 
- - 6,910 109,750 116,660 
- - 109,750 109,750 
35,000 - - - 2,268,200 
22,691 40,790 2,599 - 2,268,200 
27,400 27,800 30,076 31,800 155,311 
31,537 27,358 21,710 44,362 155,098 
4-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
TABLE 4-A (Continued) 
See Total Cost 
Section to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 1975 
29. Raystown Lake, New Work 
Raystown Branch, 
Juniata River, Pa. 
30A. Addison, N.Y. 
30B. Almond Lake, 
N.Y. 
30C. Arkport, Dam, N.Y. 
30D. Avoca, N.Y. 
30E. Binghamton, N.Y. 
30F. Canisteo, N.Y. 
30G. Corning, N.Y. 
30H. East Sidney Lake, 
N.Y. 
301. Elmira, N.Y. 
30J. Hornell, N.Y. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
13,414,700 14,407,000 5,635,000 
12,555,274 12,582,167 7,369,155 
- - 123,915 
- - 121.142 
1,000 
1,695 
71,600 
76,822 
20,300 
30,211 
7,300 
10,608 
7,000 
6,166 
10,000 
13,678 
7,700 
13,172 
7,500 
69,339 
52,300 
68,356 
3,600 
3,528 
38,800 
38.417 
2,700,000 65,534,700 
4,286,339 65,129,411 
358,000 481,915 
326,664 447,806 
- 827,050 
- 827,050 
1,370 1,916 5,920 32,462 
1,095 2,199 5,920 32,462 
- 150,000 - 5,760,211 
- 150,000 - 5,760,211 
90,300 66,926 103,535 994,417 
98,038 70,470 101,593 991,965 
- - - 1,910,00023 
- - - 1,910,00023 
47,300 24,132 30,455 481,232 
41,866 30,145 30,451 481,228 
- - - 436,37424 
- - - 436,37424 
7,840 8,015 15,535 181,777 
8,044 8,214 15,536 181,777 
- - - 2,952,000"5 
- - - 2,952,00025 
890 5,851 12,070 175,376 
5,103 6,271 11,376 174,681 
- - - 1,183,11126 
- - - 1,183,11126 
9,000 18,144 17,750 284,709 
10,406 18,613 17,750 284,709 
- - - 3,322,00027 
- - - 3,322,00027 
12,790 13,358 15,060 240,491 
12,164 14,104 15,060 240,491 
- - - 6,049,504 
- - - 6,049,504 
86,200 62,861 76,800 1,032,245 
77,804 71,866 75,098 1,029,789 
- - - 6,738,305 
- - - 6,738,305 
18,010 9,977 7,260 81,319 
17,870 10,189 7,260 81,319 
- - - 4,558,69828 
- - - 4,558,69828 
32,900 54,331 68,695 1,002,639 
43.602 54,361 68,766 1,002,639 
4-28

BALTIMORE, MD., DISTRICT 
COST AND FINANCIAL STATEMENT 
TABLE 4-A (Continued) 
Project 
30K. Lisle, N.Y. 
30L. Oxford, N.Y. 
30M. Whitney Point 
Lake, N.Y. 
30N. Whitney Point 
Village, N.Y. 
31. Stillwater Lake, 
Lackawanna 
River, Pa. 
32A. Cowanesque Lake, 
Pa. 
32B. Tioga-Hammond 
Lakes, Pa. 
33. Tyrone, Pa. 
34A. Alvin R. Bush Dam, 
Pa. 
34B. Curwensville Lake, 
Pa. 
34C. Foster Joseph 
Sayers Dam, 
Pa.. 
(Contributed Funds) 
35. York, Codorus Creek, 
Pa. 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost 
to 
FY 72 FY 73 FY 74 FY 75 30June1975 
- - - _ 661,19929 
- - - _ 661,19929 
6,000 5,550 9,603 13,905 247,729 
8,459 8,088 10,102 13,905 247,729 
- - - - 131,00030 
- - - - 131,00030 
5,500 4,700 5,889 4,880 66,061 
6,192 4,362 6,490 4,881 - 66,061 
- - - - 5,421,539 
- - - - 5,421,539 
50,100 89,600 94,179 75,175 1,292,095 
69,473 76,393 110,045 82,843 1,289,414 
- - -- 424,096 
- - - - 424,096 
5,600 2,750 7,416 12,925 117,878 
4,386 6,114 8,179 12,925 117,878 
- - - - 5,725,700 
- - - - 5,725,700 
34,300 56,700 51,900 53,985 575,008 
48,507 58,566 55,453 51,920 572,674 
49,000 1,655,000 1,900,000 8,800,000 14,103,700 
52,262 196,608 2,744,118 9,381,125 13,936,975 
2,742,900 12,000,000 18,230,000 18,450,000 57,692,800 
2,482,140 5,237,631 17,775,978 23,163,195 53,830,684 
461,500 1,445,000 675,000 1,500,000 4,581,016 
73,141 948,633 1,035,418 1,881,632 4,437,840 
- - - - 7,103,001 
- - - - 7,103,001 
74,400 71,400 455,763 113,055 1,200,068 
74,248 57,689 408,407 178,258 1,196,690 
- - - - 20,396,060 
13,439 8,778 2,028 - 20,396,060 
145,000 433,000 532,599 460,180 1,882,289 
147,575 405,695 568,019 456,689 1,877,409 
971,000 307,000 -40,937 - 30,907,063 
861,706 478,209 8,296 59,030 30,851,129 
106,200 172,099 295,159 166,425 892,556 
108,975 160,741 323,588 164,223 889,835 
- - - - 263,90031' 
30,008 - 21,658 10,247 263,90031 
- - - - 5,061,16732 
- - - - 5,061,16732 
101,300 80,400 121,691 101,990 1,584,95333 
80,863 100,808 128,470 105,119 1,580,34933 
4-29 
See 
Section 
in Text 
.. -

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
TABLE 4-A (Continued) 
See Total Cost 
Section to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June1975 
40. Potomac Estuary Pilot New Work 
Water Treatment Plant, Approp. - - - 350,000 350,000 
D.C., Md., & Va. Cost - - - 74,163 74,163 
41. Verona Lake, Va. New Work 
Approp. - - - 250,000 250,000 
Cost - - - 197,295 197,295 
Includes $8,764,003 for previous projects. 
Includes $489,408 for sections of project in Norfolk 
District. 
Includes $477,948 for sections of project in Norfolk 
District. 
Includes $507,184 for sections of project in Norfolk 
District. 
Includes $518,644 for sections of project in Norfolk 
District. 
Includes $117,749 for sections of project in Norfolk 
Distict. 
Includes $15,000 for sections of project in Norfolk 
District. 
Includes $10,326 for sections of project in Norfolk 
District 
Includes $399,802 for previous projects. 
Includes $38,041 for previous projects. 
Includes $46,121 public works funds. 
Includes $283,008 public works funds and $67,185 
emergency relief funds; excludes $500,000 contributed 
funds. 
Includes $6,000 for previous project. 
Includes $37,343 Public Works funds and $330 for 
previous project. 
Includes $3,029,001 for previous projects. 
16. 
17. 
18. 
19. 
20. 
21. 
22. 
23. 
24. 
25. 
26. 
27. 
28. 
29. 
30. 
31. 
32. 
33. 
Includes $1,831,609 for previous projects. 
Excludes $4,000 for emergency dredging under 
provisions of Section 3, 1945 River and Harbor Act. 
Includes $50,000 for previous project and $14,000 contributed 
funds. 
Excludes $33,000 contributed funds. 
Includes $12,000 for Detailed Project Report prior to 
adoption of project. 
Includes $49,998 emergency relief funds. 
Excludes $1,402,001 contributed funds and $197,513 
public works acceleration funds. 
Includes $62,577 emergency relief funds. 
Includes $109,944 emergency relief funds. 
Excludes $163,096 contributed funds. 
Includes $207,520 rehabilitation funds. 
Excludes $34,729 contributed funds. 
Includes $250,899 emergency relief funds. Excludes 
$15,000 contributed funds. 
Includes $71,557 emergency relief funds. 
Includes $73,465 emergency relief funds. 
Local cost in accordance with the Tri-party Agreement 
for construction of Sanitary Systems for Public Use. 
Includes $11,588 relief funds. 
Includes $15,000 for deferred maintenance. 
4-30 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13. 
14. 
15.

BALTIMORE, MD., DISTRICT 
TABLE 4-B AUTHORIZING LEGISLATION 
Work Authorized 
Mar. 3, 1905 
Mar. 3, 1909 
Feb. 27, 1911 
Aug. 8, 1917 
Jan. 21, 1927 
July 3, 1930 
July 3, 1930 
Oct. 17,1940 
Mar. 2, 1945 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
BALTIMORE HARBOR AND CHANNELS, MD. (See 
Section 1 of Text) 
Main Channel 35 feet deep and 600 feet wide throughout. 
Anchorage basin near intersection of Fort McHenry and 
Curtis Bay Channels (within original limit of cost authorized 
by act of March 2, 1907). 
Width increased at entrances and bends (increase to be made 
within limit of original estimate). 
Branch channel 35 feet deep to head of Curtis Bay, and one 
35 feet deep and 400 feet wide from Fort McHenry to Port 
Covington entrance channel, thence 150 feet wide to Ferry 
Bar, and thence 27 feet deep and 150 feet wide to Hanover 
Street Bridge, widen approaches and bends, and enlarge 
anchorage basin near entrance. Inclusion of Patapsco River 
and tributaries into one project for Baltimore Harbor. 2 
Change in location of anchorage near upper end of Fort 
McHenry Channel. 
Increased anchorage facilities. 
For 37-foot depth in that portion of channel to Baltimore 
lying between 37-foot depth curve near Baltimore Light to 
Sparrows Point entrance channel: widen angle between 
Fort McHenry and Ferry Bar Section; and for width of 400 
feet in Curtis Bay section. 
For 22-, 18-, and 15-foot channels in Curtis Creek from 
22-foot depth below Pennington Ave. Bridge to upper end 
of marginal wharf of U.S. Ordnance Depot. 
Uniform main channel 39 feet deep from the ocean through 
York Spit section and Craighill entrance to Fort McHenry, 
additional anchorage area, 2,400 feet long, 1,200 feet wide, 
and 30 feet deep: a connecting channel 400 feet wide and 
27 feet deep from Cutoff Brewerton Angle in main 
channel to Inland Waterway from Delaware River to 
Chesapeake Bay: a channel in Curtis Creek 200 feet wide 
and 35 feet deep from head of existing 35-foot project 
channel in Curtis Bay to a point in the creek about 750 
feet below Pennington Ave. Bridge. 
A channel 22 feet deep and 200 feet wide from 22-foot 
depth curve south of Baltimore & Ohio R.R. bridge about 
2,800 feet to vicinity of Arundel Cove, thence 100 feet 
wide in Arundel Cove for about 2,100 feet: with an 
anchorage basin about 700 feet square adjacent to channel 
southwesterly of Coast Guard wharf. 
Main channel 42 feet deep and 1,000 feet wide in Cape 
Henry section at entrance to Chesapeake Bay and in York 
Spit section: 42 feet deep and 800 feet wide in Rappahannock 
Spit section and in approach channel to Baltimore 
Harbor from Craighill entrance to Fort McHenry, with 
widening at entrance and bends; channels 42 feet deep and 
600 feet wide in Curtis Bay and Ferry Bar sections of 
harbor; a connecting channel 35 feet deep and 600 feet wide 
from main channel to approach channel to Chesapeake and 
Delaware Canal, and for three disjointed sections of channels 
of same depth and width in Chesapeake Bay leading to 
Chesapeake and Delaware Canal: and to provide Federal 
maintenance of a 39-foot depth in Northwest Branch, in 
areas dredged to that depth by local interests. 
Deepening of the Cape Henry Channel to 50 feet at the 
existing width of 1,000 feet, with widening at bends: 
deepening of the York Spit Channel to 50 feet at the 
existing width 6f 1,000 feet, with widening at bends: 
enlargement of the Rappahannock Shoal Channel to a 
depth of 50 feet and a width of 1,000 feet; deepening of 
the main ship channel from Chesapeake Bay to Fort 
McHenry to a depth of 50 feet at the existing width of 800 
feet, with widening at bends and at the Craighill Entrance: 
deepening of the Curtis Bay Channel to a depth of 50 feet 
at the existing width of 600 feet, and deepening of the 
950-foot wide and 980-foot long turning basin at the head 
of the channel to the same depth; deepening of the 
Northwest Branch-East Channel to a depth of 49 feet 
from the depth existing at the time of construction at a 
4-31 
Acts Documents 
H. Doc. 186, 57th Cong., 2d sess. 
H. Doc. 799, 64th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 11, 70th Cong., 1st sess. 
H. Doc. 86, 85th Cong., 1st sess.' 
Adopted as a national defense 
project. (No printed report.) 
H. Doc. 741, 79th Cong., 2d sess. 
In accordance with plans on file 
in the Office, Chief of Engineers. 
H. Doc. 86, 85th Cong., 1st sess. 
Report on file in the Office, 
Chief of Engineers 
--- _- ---- ---- -___ ~ -- - -. YW)I-)M- ---- -- 
____1____~_1___ 

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
width of 600 feet, and deepening of the 950-foot wide and 
950-foot long turning basin at the head of the channel to 
the same depth; and deepening and extension of the 
Northwest Branch-West Channel to a depth of 40 feet 
from the depth existing at the time of construction, at a 
width of 600 feet, and with an irregularly shaped turning 
basin at the head of the channel 40 feet deep and about 
2,000 feet long with a maximum width of 1,150. 
BALTIMORE HARBOR, MD.-COLLECTION AND 
REMOVAL OF DRIFT (See Section 2 of Text) 
Collection and removal of drift from Baltimore Harbor and 
its tributary waters. 
CHESTER RIVER, MD. (See Section 3 of Text) 
A channel 7 feet deep at mean low water and 100 feet wide 
from Chester River to Eastern Bay through Kent Island 
Narrows. 
A channel 6 feet deep at mean low water and 60 feet wide 
from Crumpton to Jones Landing. 
A channel 7 feet deep at mean low water and 75 feet wide 
extending from the 7-foot depth in Kent Island Narrows 
800 feet into Wells Cove with a basin of the same depth 
and 300 feet square at the head of the channel. 
CHOPTANK RIVER, MD. (See Section 4 of Text) 
A channel 75 feet in width and 8 feet deep, at mean low water, 
from Denton Bridge to Greensboro Bridge. 
A channel through Pealiquor Shoal 8 feet deep and 100 feet 
wide. 
A channel 12 feet deep and 100 feet wide in the Choptank River 
from a point opposite Watts Creek to Denton. 
HARBOR OF BALTIMORE, MD. PREVENTION OF 
OBSTRUCTIONS (See Section 5 of Text) 
Continuous patrol and inspection of Baltimore Harbor, 
Chesapeake Bay, and its tributaries to prevent and detect 
violations, and issue permits as required for transporting 
and depositing waste materials in navigable waters. (The 
project is limited to the tidal waters of Chesapeake Bay and 
its tributaries that lie within the State of Maryland.) 
KNAPPS NARROWS, MD. (See Section 6 of Text) 
A channel 9 feet deep at mean low water, 75 feet wide, 
widened at the bends from deep water in Chesapeake Bay to 
deep water in Harris Creek, Md., with a turning basin west 
of the drawbridge, 7 feet deep at mean low water, about 320 
feet long and 120 feet wide. Project channel was authorized 
by the Public Works Administration September 16, 1933 and 
later adopted by 1935 River and Harbor Act. 
NANTICOKE RIVER AT BIVALVE, MD. (See Section 7 
of Text) 
An Anchorage basin in Jackson Gut 7 feet deep, 150 feet 
wide and 350 feet long initially with ultimate length 550 
feet and approach channel of same depth 60 feet wide and 
about 1,400 feet long, protected by twin stone jetties. 
NEABSCO CREEK, VA. (See Section 8 of Text) 
Channel 100 feet wide and 7 feet deep from that depth in the 
Potomac River to Atkinson's Upper Landing and Willis' 
Wharf. 
River and Harbor Act of 1948. 
E. Doc. 25, 42d Cong., 3rd sess. 
H. Ex. Doc. 65, 51st Cong., 1st sess. 
H. Doc. 380, 80th Cong., 1st sess.1 
S. Ex. Doc. 66, 46th Cong., 2d 
sess. 
H Doc. 188, 70th Cong., 1st sess.' 
Detailed Project Report, 
November 1967. 
June 30, 1948 
Mar. 3, 1873 
Sep. 19, 1890 
June 30, 1948 
June 14, 1880 
July 3, 1930 
Jan. 3, 1969 
Sec. 107 
July 14, 1960 
Aug. 28, 1958 
Aug. 30, 1935 
Sep. 3, 1954 
Mar. 3, 1881 
4-32 
River and Harbor Act, June 29, 
1888 as amended by Public Law 
85-802 dated August 28, 1958. 
H. Doc. 308, 72nd Cong., 1st sess. 
H. Doc. 91, 82nd Cong., 1st sess.' 
H. Ex. Doc. 41, 46th Cong., 3d 
sess.

BALTIMORE, MD., DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 19354 
Aug. 30, 19355 
Sep. 3, 1954 
Oct. 27, 1965 
May 17, 1950 
July 25, 1912 
July 25, 1912 
Mar. 2, 1919 
Oct. 27, 1965 
July 25, 1912 
July 3, 1930 
Aug. 30, 1935 
June 20, 1938 
May 17, 1950 
OCEAN CITY HARBOR & INLET & SINEPUXENT 
BAY, MD. (See Section 9 of Text) 
Construction of an inlet between the Atlantic Ocean and 
Sinepuxent Bay, 10 feet deep and 200 feet wide, protected 
by jetties, a channel 8 feet deep and 100 feet wide from 
the inlet to Ocean City, 6 feet deep and 150 feet wide to 
Green Point, and 100 feet wide into Chincoteague Bay. 
Modification providing a 10-by 100-foot channel from the 
inlet to the west side of the bay with 2 turning basins, a 
channel 6 feet deep and 125 feet wide from the inlet 
channel to opposite North 8th Street, Ocean City, and 75 
feet wide into Isle of Wight Bay. 
Modification providing for raising the north jetty to an 
elevation 9 feet above mean low water, and a channel 300 
feet wide and 16 feet deep from the ocean through the 
inlet to the Isle of Wight Bay channel, thence 200 feet to 
the project harbor, and a depth of 14 feet in the project 
harbor. Channel depths refer to project datum.3 
6 
POTOMAC & ANACOSTIA RIVERS, D.C.-COLLECTION 
& REMOVAL OF DRIFT (See Section 10 of Text) 
Collection and removal of drift from waters of the Potomac 
and Anacostia Rivers and their tributaries in the Washington, 
D.C., area from the head of tidewater to Mount 
Vernon, Virginia. 
POTOMAC RIVER & TRIBUTARIES AT AND 
BELOW WASHINGTON, D.C., ELIMINATION OF 
WATERCHESTNUT (See Section 11 of Text) 
Complete eradication of waterchestnut from the Potomac 
River and its tributaries at and below Washington, D.C. 
SLAUGHTER CREEK, MD. (See Section 12 of Text) 
A channel 7 feet deep and 100 feet wide at mean low water 
through the bar at the mouth, a distance of about one-third 
of a mile, the lower end of the section extending about 900 
feet into Little Choptank River. 
TRED AVON RIVER, MD. (See Section 13 of Text) 
Restore the channel formerly dredged from Peach Blossom 
Creek to Easton Point to 8 feet deep at mean low water, 
and 150 feet wide, widening out at the upper end. 
A channel 8 feet deep and 150 feet wide up the North Fork, 
with a turning basin at the upper end. 
A 12-foot channel from a point near Peach Blossom Creek to 
Easton Point, thence 1,400 feet in North Fork and a turning 
basin 12 feet and 250 feet wide and 600 feet long in the 
South Fork. 
TWITCH COVE AND BIG THOROFARE, MD. (See 
Section 14 of Text) 
A channel 4 feet deep and 25 feet wide from Tangier Sound 
into Big Thorofare River, and one of same dimensions 
around point between said river and Tyler River. 
A channel 5 feet deep at mean low water and 25 feet wide 
from Twitch Cove on Tangier Sound through Big Thorofare 
River to a point on Levering Creek about 800 feet 
north of canal at Ewell, Md. 
A channel 7 feet deep and 60 feet wide from Twitch Cove 
through Big Thorofare River to a point on Levering Creek 
about 800 feet north of canal at Ewell, Md. 
Present project dimensions of main channel with twin jetties 
at entrance. 
Anchorage basin 7 feet deep, 100 feet wide, and 700 feet 
long on west side of project channel at Ewell, Md., and an 
extension of existing project channel in Levering Creek, 6 
feet deep, 60 feet wide, and 1,000 feet long. 
4-33 
Rivers and Harbors Committee 
Doc. 38, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 60, 74th Cong., 1st sess. 
H. Doc. 444, 82d Cong., 2d sess. 
H. Doc. 286, 89th Cong., 1st sess. 
H. Doe. 113, 81st Cong., 1st sess.2 
H. Doc. 87, 62nd Cong., 1st sess. 
H. Doc. 399, 62d Cong., 2d sess.' 
H. Doc. 27, 63rd Cong., 1st sess.' 
H. Doc. 225, 89th Cong., 1st sess.' 
H. Doc. 285, 62d Cong., 2d sess. 
H. Doc. 313, 71st Cong., 2d sess. 
Rivers and Harbors Committee 
Doec. 67, 74th Cong., 1st sess. 
Rivers & Harbors Committee 
Doec. 49, 75th Cong., 2d sess.' 
H. Doc. 340, 81st Cong., 1st sess.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 19356 
Aug. 26, 1937 
Aug. 30, 1935 
Sep. 19, 1890 
June 25, 1910 
Mar. 2, 1919 
July 3, 1930 
Aug. 26, 1937 
Sep. 3, 1954 
May 17, 1950 
Mar. 3, 1970 
Sec. 205 
June 30, 1948 
Oct. 23, 1962 
June 22, 1936 
UPPER THOROFARE, DEAL ISLAND, MD. (See Section 
15 of Text) 
A 9-foot channel 75 feet wide protected by breakwater at 
entrance, with turning basin at inner end and anchorage 
area 6-foot deep and 150 feet wide. 
Widen entrance channel to 100 feet, extend 9-foot turning 
basin and 6-foot anchorage, and dredging an additional 
anchorage area on north side of channel. 
WASHINGTON HARBOR, D.C. (See Section 16 of Text) 
Provides for: (a) Virginia Channel, from Giesboro Point to 
Francis Scott Key Bridge, 24 feet deep and 400 feet wide, 
with width increased as necessary to afford a low-water 
cross section area of 25,000 square feet: (b) Washington 
Channel, from Hains Point to head of Washington Channel, 
24 feet deep and 400 feet wide: (c) Anacostia River from 
Giesboro Point to Anacostia Bridge, 24 feet deep and 400 
feet wide, with turning basin 800 feet wide and about 
2,400 feet long of same depth opposite Naval Weapons 
Plant: (d) Anacostia River from Anacostia Bridge 24 feet 
deep and 200 feet wide to turning basin 400 feet square of 
same depth at foot of 15th Street SE. Channel lengths 
including turning basins are: Virginia Channel, 25,000 feet; 
Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and (e) operation and maintenance of inlet 
gates and lock and outlet gates of Tidal Basin constructed 
under a previous project to flush Washington Channel. 
WICOMICO RIVER, MD. (See Section 17 of Text) 
Channel 9 feet deep from Main St. Bridge to about 2 miles 
below. 
Extend 9-foot depth into north prong from Main Street 
Bridge to the Salisbury Dam and turning basin. 
Extend 9-foot depth into south prong to head of navigation at 
Cathell St., including a turning basin and extend project 
down to mouth of river in Monie Bay. 
A 12-foot channel below the Main Street Bridge. 
A 14-foot channel, 150 feet wide; depths of 14 feet in the 
north and south prongs and a basin 6 feet deep at Webster 
Cove and approach channel thereto of the same depth. 
Enlarge existing basin at Webster Cove, by dredging an 
extension 6 feet deep, 100 feet wide, and 200 feet long on 
each side of existing basin to form a T-shaped harbor. 
ANACOSTIA RIVER & TRIBUTARIES, FLOOD PROTECTION 
& NAVIGATION IMPROVEMENTS, D.C. 
& MD. (See Section 23 of Text) 
Channel improvements, levees, pumping stations with connecting 
storm sewers, pressure conduit and relocation and 
reconstruction of 4 highway bridges and 1 railroad bridge. 
ANACOSTIA RIVER AND TRIBUTARIES, PRINCE 
GEORGES COUNTY, MD. (See Section 24 of Text) 
Channel improvements by realigning, widening, and deepening. 
BLOOMINGTON LAKE, NORTH BRANCH 
POTOMAC RIVER, MD. & W. VA. (See Section 
25 of Text) 
Construction of Bloomington Lake project. 
CUMBERLAND, MD. AND RIDGELEY, W. VA. (See 
Section 26 of Text) 
Levees, retaining walls, movable dam, and channel clearing 
for Cumberland. West Cumberland and South Cumberland, 
Md., and Ridgeley, W. Va. 
Rivers and Harbors Committee 
Doc. 37, 72d Cong., 1st sess. 
H. Doc. 76, 75th Cong., 1st sess.1 
Rivers and Harbors Committee 
Doc. 22, 74th Cong., 1st sess.2 
H. Doc. 20, 51st Cong. 1st sess., 
and Annual Report, 1890, p. 947. 
H. Doc. 569, 61st Cong., 2d sess. 
H. Doc. 1509, 63rd Cong., 3rd 
sess. 
Senate Committee Print, 75th 
Cong., 3rd sess.' 
H. Doc. 619, 81st Cong., 2d sess.' 
H. Doc. 202, 81st Cong., 1st sess. 
Detailed Project Report, April 1968. 
H. Doc. 469, 87th Cong., 2d sess. 
H. Doc. 101, 73rd Cong., 1st sess. 
4-34

BALTIMORE, MD., DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 24, 1946 Levees, wall, channel improvement, remove Chesapeake and 
Ohio Canal dam and construct new industrial dam. 
FOURMILE RUN, VA. (See Section 27 of Text) 
June 25, 1970 Construction of a levee and floodwall protection system with 
July 14, 1970 associated interior drainage facilities, an improved channel, 
and replacement of two highway and four railroad bridges. 
March 7, 1974 Modification providing for channel capacity of 27,000 c.f.s.; 
increase channel bottom widths along Fourmile Run; 
deletion of pumping stations,ponding areas, levees, except 
for a short levee on long Branch; and the addition of 
recreation as a project feature. 
LACKAWANNA RIVER BASIN, PA. (See Section 28 of 
Text) 
Oct. 23, 1962 Construction of Aylesworth Creek Lake. Fall Brook Lake, 
and local protection works on Lackawanna River at 
Scranton, Pennsylvania. 
RAYSTOWN LAKE, RAYSTOWN BRANCH, 
JUNIATA RIVER, PA. (See Section 29 of Text) 
Oct. 23, 1962 Construction of dam and appurtenant facilities. 
SOUTHERN NEW YORK FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
June 22, 1936 Construction of detention reservoirs and related flood conmodified 
by trol works for protection of Binghamton, Hornell, Corning 
Acts of June and other towns in New York and Pennsylvania. 
28, 1938; 
Aug. 18, 1941; 
Dec. 22, 1944; 
May 17, 1950; and 
July 3, 1958 
Aug. 18, 1941 
July 3, 1958 
Dec. 22, 1944 
Sep. 3, 1954 
June 22, 1936 
March 7, 1974 
STILLWATER LAKE, LACKAWANNA RIVER, PA. 
(See Section 31 of Text) 
Construction of a flood control reservoir. 
SUSQUEHANNA RIVER FLOOD CONTROL 
PROJECTS, N.Y. and PA. (See Section 32 of Text) 
Construction of Cowanesque and Tioga-Hammond reservoirs, 
local flood protection works at Elkland, Pa., and Nichols, 
N.Y. and channel improvement at Cortland, N.Y. 
TYRONE, PA. (See Section 33 of Text) 
Levees, walls, drop structure, channel improvements, and 
protection of bridges. 
WEST BRANCH OF SUSQUEHANNA RIVER, PA. 
(See Section 34 of Text) 
Construction of three flood control reservoirs. 
YORK, CODORUS CREEK, PA. (See Section 35 of Text) 
Construction of Indian Rock Dam and channel improvements 
on Codorus Creek. 
POTOMAC ESTUARY PILOT WATER TREATMENT 
PLANT, D.C., MD. & VA. (See Section 40 of Text) 
To construct, operate, and evaluate a pilot project on the 
Potomac estuary for the treatment of water at an estimated 
cost of $6,000,000. 
Report on file in Office, Chief 
of Engineers. 
H. Doc. 358, 91st Cong., 2d sess. 
S. Doc. 141, 87th Cong., 2d sess. 
H. Doc. 565, 87th Cong., 2d sess. 
H. Doc. 702, 77th Cong., 2d sess. 
H. Doc. 702, 77th Cong., 2d sess. 
H. Doc. 394, 84th Cong., 2d sess. 
H. Doc. 702, 77th Cong., 2d sess. 
H. Doc. 29, 84th Cong., 1st sess. 
H. Doc. 702, 77th Cong., 2d sess. 
H. Doc. 2, 93rd Cong., 1st sess. 
4-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
VERONA LAKE, VA. (See Section 41 of Text) 
March 7, 1974 Project authorization limited to the design memorandum of H. Doc. 343, 91st Cong., 2nd sess. 
advance engineering and design. 
1. Contains latest published maps. September 16, 1933. The site chosen for the inlet under 
2. Exclusive of portion considered inactive. Inactive portion this authorization was that opened just south of Ocean 
is widening 35-foot depth channel from 150 to 400 feet City by natural forces during a severe storm in August 
from Port Covington to Ferry Bar widening 27-foot depth 1933. This eliminated the necessity for an 8-foot channel 
channel from 150 to 250-feet to Hanover Street Bridge, from the inlet to Ocean City. 
and providing a channel 27 feet deep by 250 feet wide to 5. Included in Emergency Relief program 1935. 
Western Maryland Railway bridge with an anchorage 6. Raising of the north jetty to an elevation of 9 feet above 
and turning basin at the upper end. mean low water was accomplished with maintenance 
3. Entire modification considered to be inactive, funds in 1956. 
4. Included in Public Works Administration program 
TABLE 4-C RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 18 of Text) 
Date Reconnaissance 
Project or Condition Survey 
Conducted Cost 
Cambridge Harbor, Md. July 1974 $2,986 
Fishing Creek, Md. December 1974 $2,428 
Honga River & Tar Bay, Md. June 1975 $1,558 
Little Wicomico River, Va. October 1974 $2,322 
Nanticoke River, Md. March 1975 $2,515 
Nanticoke River (Incl Northwest Fork), Md. June 1975 $7,605 
Potomac River below Washington, D.C. November 1975 $4,561 
Pocomoke River, Md. June 1974 $1,011 
4-36

BALTIMORE, MD., DISTRICT 
TABLE 4-D OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost To June 30, 1975 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Accotink Creek, Va.' 1878 5,000 - 
Anacostia River and Flats2 1953 3,910,582 - 
Annapolis Harbor, Md.3 1946 34,2504 15,623 
Aquia Creek, Va.1 1928 52,4655 11,770 
Back Creek, Md.3 1946 23,061 10,441 
Betterton Harbor, Md.' 1960 3,482 - 
Black Walnut Harbor, Md. 3 1966 32,631 56,142 
Bonum Creek, Va.3 1971 202,0006 19,010 
Branson Cove, Lower Machodoc River, Va.3 1950 15,755 6,454 
Breton Bay, Md.3 1950 47,9247 12,621 
Broad Creek River, Del.3 1964 64,5208 112,0359 
Broad Creek, Md.3 1962 28,227 73,581 
Broadwater Creek, Md.' 1949 - 212 
Cadle Creek, Md.' 1949 - - 
Cambridge Harbor, Md. 1973 195,974 '
0 28,651 
Channel connecting Plain Dealing Creek and Oak Creek, Md.' 1940 112 - 
Claiborne Harbor, Md.3 1933 42,974 48,629 
Coan River, Va.' 1937 - - 
C',sica River, Md.3 1948 39,071" 56,974 
3 .ficld Harbor, Md.3 1972 349,15412 119,01313 
Cuckold Creek, Md.14 1970 5,220 - 
Cunninghill Cove, Md. 5 16 1970 10,700 - 
Cypress Creek, Md.3 1947 3,057 3,787 
Duck Point Cove (Hearns Creek), Md.3 1966 25,289 24,058 
Elk and Little Elk Rivers, Md.3 1932 90,121 7 44,89218 
Fishing Bay, Md. 1974 33,874 148,840 
Fishing Creek, Md.3 1973 111,242 294,025 
Goose Creek, Md.3 24 1973 75,900 - 
Governor's Run, Md.' 1950 - - 
Helens Creek, Md.' 'S 1950 - - 
Herring Bay and Rockhold Creek, Md. 1974 50,591 102,022 
Herring Creek, Md.3 1961 284,80020 4,596 
Honga River and Tar Bay, Md. 1974 66,119 522,271 
Island Creek, Md.3 1948 6,230 4,261 
Island Creeli St. George Island, Md.3 1971 23,836 48,565 
Lake Ogleton, Md.' 1950 - - 
La Trappe River, Md.3 1948 8,064 18,153 
Lower Thorofare, Deal Island, Md.3 1971 44,65821 113,474 
Lowes Wharf, Md.3 1971 21,000 34,123 
Little Creek, Kent Island, Md.3 1958 23,00022 1,108 
Little Wicomico River, Md. 3 1972 81,88523 326,384 
Lower Machodoc Creek, Va.3 1904 9,916 1,634 
Manokin River, Md.3 24 1919 34,78825 32,724 
Middle River and Dark Head Creek, Md.3 1947 38,71526 16,506 
Mill Creek, Md.' 1949 - - 
Monroe Bay and.Creek, Va.2 1972 12,460 73,082 
Muddy Hook and Tyler Coves, Md.3 24 1966 64,001 2,519 
Nan Cove, Md. 3 16 1965 34,86127 - 
Nanticoke River (including Northwest Fork) Del. and Md. 2 1973 143,13421 76,791 
Nanticoke River, Md.3 1971 73,243 52,356 
Neale Sound, Md.3 1973 12,60028 69,668 
Neavitt Harbor, Md. 3 24 1968 36,500 3,215 
Nomini Bay and Creek, Va.3 1946 78,446 31,863 
Northeast River, Md. 1972 28,48929 125,653 
4-37

TABLE 4-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(Continued) Cost To June 30, 1975 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Occoquan Creek, Va.30 1971 66,25331' 171,609 
Parish Creek, Md. 3 1963 19,17033 43,067 
Patuxent River, Md.' 33 1905 14,00034 - 
Pocomoke River, Md. 35 1971 191,72636 490,806 
Potomac River at Alexandria, Va.3 1965 95,214 491,500 
Potomac River at Lower Cedar Point, Md.3 1920 10,234 6,216 
Potomac River at Mount Vernon, Va.3 1950 17,000 53,409 
Potomac River below Washington, D.C.3 1967 153,836 1,651,24737 
Potomac River North Side of Washington Channel, D.C.' 1956 1,744,69238 27,461 
Queenstown Harbor, Md. 3 1958 72,85839 30,790 
Rhodes Point to Tylerton, Md.3 1971 155,366 21,772 
Rock Hall Harbor, Md. 3 1972 201,66040 54,24741 
Shad Landing State Park, Md.3 
15 1966 33,53142 2,228 
St. Catherines Sound, Md.3 1972 29,94743 8,528 
St. Georges Creek, Md. 1971 - 
St. Jeromes Creek, Md. 3 1973 44,35744 95,382 
St. Michaels Harbor, Md. 3 1964 16,72345 70 
St. Patricks Creek, Md. 3 1956 15,75246 2,188 
St. Peters Creek, Md. 3 15 1963 46,74047 5,096 
Smith Creek, Md.3 1936 5,252 279 
Susquehanna River at and below Havre de Grace, Md. 3 1974 293,57048 350,193 
Susquehanna River at Williamsport, Pa.3 1974 57,03149 - 
Tilghman Island Harbor, Md.3 1972 56,83050 833 
Town Creek, Md.3 1950 43,220 2,713 
Tuckahoe River, Md. 3 24 1923 9,727 1,955 
Tyaskin Creek, Md.: 24 1923 16,29751 18,530 
Upper Machodoc Creek, Va. 3 1971 20,281 13,715 
Warwick River, Md.3 1973 22,04152 85,128 
Waterway from Little Choptank River to Choptank River, Md.' 1939 305 - 
Entire project inactive. 
Project being restudied. 
Completed. 
Includes $8,476 expended on previous project. 
Includes $31,065 expended on previous project. 
Excluded $3,998 contributed funds. 
Includes $37,500 expended on previous project. 
Includes $50,000 expended on previous project. 
Includes $7,463 expended on previous project. 
Includes $61,321 for previous project. 
Includes $30,000 expended on previous project. 
Includes $87,740 expended on previous project. 
Includes $2,839 expended on previous project. 
Because local interests could not furnish a suitable 
public landing as required, they requested the State of 
Maryland to construct the improvement under its small 
boat program. 
Authorized by Chief of Engineers. 
Awaiting local cooperation. 
Includes $79,626 expended on previous project. Excludes 
$8,414 contributed funds. 
Includes $24,321 expended on previous project. 
Excludes $10,306 contributed funds. 
Excludes $2,200 contributed funds and includes 
$27,668 emergency relief funds. 
Includes $5,000 expended on previous project. 
Excludes $1,100 contributed funds. 
23. 
24. 
25. 
26. 
27. 
28. 
29. 
30. 
31. 
32. 
33. 
34. 
35. 
36. 
37. 
38. 
39. 
40. 
41. 
42. 
43. 
44. 
Excludes $5,000 contributed funds. 
Abandonment recommended in 1926 (H. Doc. 467, 69th 
Cong., 1st sess.). 
Includes $2,000 expended outside project limits. 
Excludes $111,581 expended by Navy Department and 
$54,000 from contributed funds. 
Excludes $565 contributed funds. 
Excludes $1,000 contributed funds. 
Includes $20,640 expended on previous project. 
Project complete except for dikes. 
Includes $25,000 expended on previous project. 
Includes $19,170 Works Progress Administration funds. 
Abandonment recommended in 1903 (River and 
Harbors Committee Doc. 32, 61st Cong., 2d sess.). 
Includes $10,617 expended on previous project. 
Project complete except for improvements authorized 
by River and Harbor Acts of 1945 and 1954. 
Includes $20,500 for previous project. 
Excludes $101,162 Public Health Service funds 
expended for waterchestnut removal. 
Excludes $389,000 contributed funds. 
Includes $19,000 expended on previous project. 
Includes $87,757 expended on previous project. 
Includes $9,762 expended on previous project. 
Excludes $24,125 contributed funds. 
Excludes $600 contributed funds. 
Includes $26,500 for previous project. 
4-38 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
19. 
20. 
21. 
22.

BALTIMORE, MD., DISTRICT 
45. Excludes $600 contributed funds. 49. Excludes $40,000 contributed funds. 
46. Excludes $1,000 contributed funds. 50. Includes $30 expended on previous project and excludes 
47. Excludes $6,984 contributed funds. $14,200 contributed funds. 
48. Includes $22,905 Works Progress Administration funds. 51. Includes $10,158 expended on previous project. 
and $97,390 expended on previous project. 52. Includes $6,000 for previous project. 
TABLE 4- E OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Section 21 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Colonial Beach, Va. 1 1950 - - 
Oxford, Md. 2 3 1974 91,3334 - 
1. Entire project inactive. 
2. Authorized by Chief of Engineers. 
3. Completed. 
4. Excludes $78,802 contributed funds. 
TABLE 4-F LACKAWANNA RIVER BASIN, PENNSYLVANIA 
(See Section 28 of Text) 
DAMS AND RESERVOIRS 
Miles Reservoir Estimated 
Nearest Above Height Capacity Lands and non-federal 
Name City River Mouth in feet (acre-feet) Construction damages1 Total costs 
Aylesworth Carbondale Aylesworth 1.0 90 1,700 2,153,559 114,641 2,268,200 - 
Creek 
Fall Brook Carbondale Fall Brook 5.0 67 1,400 - - 1,500,0002 - 
1. Includes relocations. 
2. Preliminary estimate. Project deferred for restudy. 
LOCAL FLOOD PROTECTION WORKS 
Miles Estimated 
Above Lands and non-federal 
Location River mouth Type of structure Construction damages Total costs 
Scranton, Pa. Lackawanna 9 Levee and floodwall 2,006,800 - 2,006,800 4,090,0(00 
3. Includes $760,000 for required lands and relocations for 
Federal portion of project and $3,300,000 for dredging of 
Lackawanna River and constructing channel improvements 
on Roaring Brook and Stafford Meadow Brook 
by Commonwealth of Pennsylvania. 
4-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 4-G LACKAWANNA RIVER BASIN, PENNSYLVANIA 
COST OF NEW WORK AND MAINTENANCE TO JUNE 30, 1975 
(See Section 28 of Text) 
New Work Maintenance Percentage 
of 
Construction 
Completed' 
Unit Appropriated Cost Cost 
Reservoirs: 
Aylesworth $2,268,200 $2,268,200 $155,098 100 (1970) 
Fall Brook 46,100 46,100 - - 
Local flood protection: 
Scranton2 2,006,800 2,006,800 100 (1969) 
Total $4,321,100 $4,321,100 $155,098 
1. Year operationally completed indicated in parentheses. 
2. Project complete. 
TABLE 4-H SOUTHERN NEW YORK FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
DAMS AND RESERVOIRS1 
Estimated Federal Cost 
Miles Reservoir 
Nearest Kb ove Height Capacity Lands and 
Name City River Mouth in Feet (are-feet)Construction I)amages' Total 
Davenport Center4 Oneonta Charlotte Creek 
West Oneonta4 Oneonta Otego Creek 
East Sidney3 Sidney Ouleout Creek 
Copes Corner4 Sidney Butternut Creek 
Whitney Point3 Binghamton Otselic River 
Arkport' Hornell Canisteo River 
Almond3 Hornell Canacadea Creek 
Total 
5
2
4
3
1 
50
3 
100 
86 
146 
75 
95 
113 
90 
52,500 
34,500 
33,550 
37,900 
86,440 
7,900 
14,800 
$17,490,000 
8,800,000 
5,279,894 
13,250,000 
3,978,533 
1,777,732 
4,746,587 
$55,322,746 
$ 7,510,000 
2,800,000 
587,244 
2,750,000 
1,096,467 
132,268 
954,024 
$15,830,003 
$25,000,000 
11,600,000 
5,867,138 , 
16,000,000 
5,075,0006 
1,910,000 
5,700,611 
$71,152,749 
1. All dams are in New York State; all are earthfill type 4. Deferred for restudy. 
except East Sidney. 5. Exclusive of $182,366 for recreational facilities. 
2. Includes relocations. 6. Exclusive of $346,539 for recreational facilities. 
3. Project completed 7. Exclusive of $59,600 for recreational facilities. 
LOCAL FLOOD PROTECTION WORKS 
Estimated Federal Cost 
Miles - Estimated 
Location Above Lands and non-federal 
New York River Mouth Type of Structure Construction Damages Total Costs 
Chenango 40 Levee and channel 
improvement 
Tioughnioga 12 Wall, levee, and channel 
realinement 
Whitney Point' Tioughnioga 10 
Binghamton' Susquehanna 328 
96,944 
605,000 
Levee and channel 441,653 
realinement 
Wall, levee, and conduit 2,844,6822 
34,056 
56,199 
12,442 
131,000 11,000 
661,199 68,000 
424,096 62,500 
107,318 2,952,0002 I 711,000 
4-40 
Oxford' 
Lisle'

BALTIMORE, MD., DISTRICT 
TABLE 4-H (Continued) LOCAL FLOOD PROTECTION WORKS 
Estimated Federal Cost 
Miles i Estimated 
Location Above Lands and non-federal 
New York River Mouth Type of Structure Construction Damages Total Costs 
Elmira' Chemung 27 Wall, levee, and conduit 6,599,130 139,175 6,738,305 922,000 
Corning' Chemung 44 Wall, levee, flume, and 3,164,000" 153,000 3,322,000; 686,471 
conduit 
Painted Post' Cohocton - Wall, levee, and channel 402,948 11,233 414,181 50,800 
realinement 
Addison' Canisteo 8 Wall, levee, and channel 814,236 12,814 827,050 125,000 
realinement 
Bath' Cohocton 21 Wall and levee 638,332 - 638,332 43,700 
Avoca' Cohocton 30 Levee, channel improve- 406,589 29,785 436,374 69,300 
ment, and realinement 
Canisteo' Canisteo 36 Levee and wall 1,125,750 57,361 1,183,111 35,000 
Hornell' Canisteo 42 Wall, levee, and channel 3,993,452' 565,246 4,558,698 - 
realinement 
Total $21,102,716 $1,183,630 $22,286,346 $2,784,771 
1. Project complete. and $34,729 contributed funds by city of Corning on 
2. Excludes contributed funds of $160,095 by city of Monkey Run. 
Binghamton and $3,000 by village of Port Dickinson. 4. Excludes contributed funds of $15,000 by city of Hornell. 
3. Excludes $250,000 of construction by State of New York 
TABLE 4-I SOUTHERN NEW YORK FLOOD CONTROL PROJECTS 
COST OF NEW WORK AND MAINTENANCE TO JUNE 30, 1975 
(See Section 30 of Text) 
Cost to June 30, 1975 Percentage 
of 
Unit New Work Maintenance Construction 
Completed' 
Reservoirs: 
Davenport Center 2 
West Oneonta3 
East Sidney3 
Copes Corner2 
Whitney Point3 
Arkport 3 
Almond3 
Local flood protection: 
Oxford3 
Lisle3 
Whitney Point Village3 
Binghamton3 4 
Elmira" 
Corning3 5 
Painted Post 3 
Addison3 
Bath3 
Avoca3 
Canisteo3 
Hornell3 6 7 
Almond Village2 9 
Total'o 
$ 286,400 $ - 
189,100 
6,049,504 
160,700 
5,421,539 
1,910,000 
5,760,211 
131,000 
661,199 
424,096 
2,952,000 
6,738,305 
3,322,000 
414,181 
827,050 
638,332 
436,374 
1,183,111 
4,558,698 
24,622 
$42,088,422 
1,029,789 
1,289,414 
481,228 
991,965 
66,061 
247,729 
117,878 
174,681 
81,319 
240,491 
17,890 
32,462 
181,777 
284,709 
1,002,639 
$6,240,032 
100 (1950) 
100 (1942) 
100 (1939) 
100 (1949) 
100 (1938) 
100 (1948) 
100 (1948) 
100 (1943) 
100 (1950) 
100 (1955) 
100 (1938) 
100 (1947) 
100 (1948) 
100 (1939) 
100 (1948) 
100 (1941)8 
4-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
1. Year operationally completed indicated in parentheses. 
2. Cost for preliminary work only. 
3. Financially complete. 
4. Does not include $163,096 contributed funds. 
5. Includes Monkey Run. Excludes $250,000 of construction 
by State of New York and $34,729 contributed 
funds by City of Corning. 
TABLE 4-J SUSQUEHANNA RIVEI 
6. Includes Canacadea Creek, Chauncey Run, and Crosby 
Creek. 
7. Does not include $15,000 contributed funds. 
8. Installation of gates on outlets completed in 1955. 
9. Local cooperation withdrawn, project authorization 
expired May 26, 1953. 
10. Does not inclue $212,825 contributed funds. 
R FLOOD CONTROL PROJECTS. 
NEW YORK AND PENNSYLVANIA 
(See Section 31 of Text) 
DAMS AND RESERVOIRS 1 
Estimated Federal Cost 
Miles Reservoir Estimated 
Nearest Above Height Capacity Lands and non-federal 
Name City River Mouth in feet (acre-feet) Construction damages2 Total costs 
Cowanesque Corning, Cowanesque 2 145 95,700 57,705,000 34,895,000 92,600,000 - 
N.Y. River 
Tioga- Corning, Tioga River 20 125 130,000 107,000,000 50,700,000 157,700,000 
Hammond N.Y. 
Total 164,705,000 85,595,000 250,300,000 - 
1. All dams are in Pennsylvania and of earthfill type. 
2. Includes relocations. 
LOCAL FLOOD PROTECTION WORKS 
Miles Estimated 
Above Lands and non-federal 
Location River Mouth Type of structure Construction damages Total costs 
Cortland, N.Y. Tioughnioga 30 Channel improvement $ 324,486 - $ 324,486 $ 52,300 
Nichols, N.Y. Susquehanna 297 Levee 1,487,800 - 1,487,800 270,000 
Elkland, Pa. Cowanesque 12 Levee 1,297,850 - 1,297,850 228,000 
Total $3,110,136 - $3,110,136 $550,300 
TABLE 4-K SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, 
NEW YORK AND PENNSYLVANIA 
COST OF NEW WORK AND MAINTENANCE TO JUNE 30, 1975 
(See Section 31 of Text) 
New Work Maintenance 
Percentage 
of 
Construction 
Unit Appropriated Cost Completed' 
Reservoirs: 
Cowanesque 
Tioga-Hammond 
$14,103,700 
57,692,800 
$13,936,975 
53,830,684 
15 
34 
4-42

TABLE 4-K 
(Cont'd) 
BALTIMORE, MD., DISTRICT 
SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, 
NEW YORK AND PENNSYLVANIA 
COST OF NEW WORK AND MAINTENANCE TO JUNE 30, 1975 
(See Section 31 of Text) 
New Work Maintenance 
Percentage 
of 
Construction 
Unit Appropriated Cost Completed' 
Local flood protection: 
Cortland2 $ 324,486 $ 324,486 $ - 100 (1963) 
Nichols' 1,487,800 1,487,800 - 100 (1971) 
Elkland2 1,297,850 1,297,850 - 100 (1966) 
Total $74,906,636 $70,877,795 $ - 
1. Year operationally completed indicated in parentheses. 
2. Financially complete. 
TABLE 4-L WEST BRANCH OF SUSQUEHANNA RIVER, PA. 
ADDITIONAL INFORMATION ON INDIVIDUAL UNITS OF PROJECT 
(See Section 34 of Text) 
Reservoir Curwensville Alvin R. Bush Foster Joseph Sayers 
Nearest large community Curwensville, Pa. Renovo, Pa. Blanchard, Pa., 
Stream distance from mouth of 308 miles 235 miles 207 miles 
Susquehanna River 
Drainage area above dam 365 sq. mi. 226 sq. mi. 339 sq. mi. 
Reservoir: 
Spillway elevation above m.s.l. 1,228 ft. 937 ft. 658 ft. 
Flood control capacity: 124,200 acre-ft. 75,000 acre-ft. 99,000 acre-ft. 
Total area of reservoir 3,020 acres 1,430 acres 3,650 acres 
Reservoir length at spillway crest 14 miles 8.8 miles 9.7 miles 
Conservation pool area 540 acres 160 acres 370 acres 
Relocation required Railroad, cemetery, high- Highway, utilities, cemetery Railroad, highway, 
way, utilities cemetery, utilities 
Dam: 
Type Earthfill Earthfill Earthfill 
Top elevation above m.s.l. 1,257.0 ft. 967,7 ft. 683.0 ft. 
Height above streambed 131 ft. 165 ft. 100 ft. 
Design freeboard 4.9 ft. 5 ft. 5.3 ft 
Top length 2,850 ft. 1,350 ft. 6,835 ft. 
Spillway: 
Location Adjacent saddle Adjacent right abutment Adjacent saddle 
Type Uncontrolled overflow Uncontrolled chute Uncontrolled overflow 
Height above streambed 102 ft. 135 ft. 74.0 ft. 
Width 480 ft. 250 ft. 600 ft. 
Design discharge 164,000 c.f.s. 127,000 c.f.s. 203,000 c.f.s. 
Outlet works: 
Location Left abutment Right abutment Left abutment 
Type Controlled Controlled Controlled 
No. of conduits 1 1 1 
No. of gates 3 3 3 
Gate size 5.5 by 12 ft. 5 by 10 ft. 5.5 by 12 ft. 
Outlet Capacity 10,000 c.f.s. 8,120 c.f.s. 9,500 c.f.s. 
Length of stilling basin 82 ft. - 104 ft. 
Estimated Federal Cost (June 1975): 
Construction $10,225,450 $5,586,978 $18,693,036 
Lands and damages 10,170,610 1,516,022 12,214,027 
Total $20,396,060 $7,103,000 $30,907,063 
4-43

TABLE 4-M 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost To June 30, 1975 
See Annual Operation and 
Project Report For Construction Maintenance 
Almond Village, N.Y.' 2 
Bainbridge, N.Y.3 4 
Bath, N.Y. 2 3 
Bayard, W. Va.3 
4 
Bridgewater, Va.3 
4 
Conklin-Kirkwood, N.Y.3 
4 
Copes Corner Lake, N.Y.2 6 
Cortland, N.Y.3 7 
Davenport Center Lake, N.Y.2 6 
Elkland, Pa.3 
Endicott, Johnson City, and Vestal, N.Y.3 
Fall Brook Lake, Pa.6 9 
Forest Heights, Md.3 4 
Genegantslet Lake, N.Y." 
Greene, N.Y.3 
4 
Harpers Ferry, W.Va. 12 
Kingston-Edwardsville, Pa.3 
Kitzmiller, Md. 3 4 
Moorefield, W. Va. 12 
Nichols, N.Y.3 
Norwich, N.Y.3 4 
Painted Post, N.Y. 2 3 
Plymouth, Pa. 3 
Savage River Dam, Md.3 7 
Scranton, Pa.3 
Sixes Bridge Lake, Md. & Pa. 
South Plymouth Lake, N.Y.6 
Sunbury, Pa. 3 
Swoyersville and Forty Fort, Pa.3 
Unadilla, N.Y. 3 
Upper Marlboro, Md. 3 
4 
Washington, D.C. and vicinity 
West Onconta Lake, N.Y. 2 6 
Wilkes-Barre, Hanover Township, Pa.3 
Williamsport, Pa. 3 
1. Local cooperation withdrawn, project authorization expired 
May 26, 1953. 
2. Unit of Southern New York Flood Control Projects. 14. 
3. Completed. - 15. 
4. Authorized by Chief of Engineers. 16. 
5. Excludes $182,672 Public Works Acceleration funds 17. 
and $4,290 contributed funds. 
6. Deferred for restudy. 18. 
7. Unit of Susquehanna River Flood Control Projects. 19. 
8. Excludes $154,694 contributed funds. 
9. Unit of Lackawanna River Basin Projects. 20. 
10. Excludes $87,720 contributed funds. 
11. Reclassified to the inactive category June 2, 1971. 21. 
12. Inactive. Recommended for abandonment in survey 
report on Potomac River dated April 30, 1944. (H. Doc. 
622, 79th Cong., 2d sess.). 22. 
13. Includes $1,162,548 emergency relief funds and 
excludes $225,877 emergency relief funds expended 
prior to adoption of project. 
Excludes $6,616 contributed funds. 
Includes $4,357 emergency relief funds. 
Includes $200,000 expended from contributed funds. 
Excludes $106,180 flood control and coastal emergency 
funds expended in FY 1971 and 1972. 
Excludes $140,504 contributed funds. 
Excludes $132,578 contributed funds. Includes $228 
expended on outstanding liability in FY 1970. 
Cost of previous project. Includes $106,500 emergency 
relief funds. 
Includes $872,715 emergency relief funds. Excludes 
$36,375 emergency relief funds expended for new work 
before adoption of project. 
Includes $1,887 emergency relief funds and excludes 
$110,835 contributed funds. 
4-44 
1970 
1959 
1970 
1965 
1953 
1955 
1970 
1970 
1970 
1971 
1966 
1970 
1964 
1954 
1951 
1937 
1957 
1965 
1941 
1974 
1950 
1970 
1958 
1954 
1971 
1974 
1953 
1953 
1968 
1970 
1965 
1953 
1970 
1958 
1957 
24,662 
382,000 
638,332 
55,2185 
136,500 
71,000 
160,700 
324,486 
286,400 
1,297,850 
6,121,5348 
46,100 
430,00010 
214,578 
37,000 
4,471,39413 
501,50014 
7,928 
1,487,800 
94,500 
414,181 
1,911,68915 
2,271,93916 
2,006,800 
100,036 
6,063,00018 
2,728,113 
1,000000'9 
590,013 
331,92720 
189,100 
3,853,45721 
12,819,89322 
17,890
-

BALTIMORE, MD., DISTRICT 
TABLE 4-N EMERGENCY FLOOD CONTROL ACTIVITIES - 
REPAIRS, FLOOD FIGHTING, AND RESCUE WORK 
(PUBLIC LAW 99, 84th CONG., AND ANTECEDENT LEGISLATION) 
(See Section 39 of Text) 
Project 
Advance Preparation 
Flood Emergency Operations 
Repair and Restoration: 
Binghamton, N.Y. 
Silver Creek, Oneonta, N.Y. 
Repair and Restoration: Tropical Storm Agnes 
Addison, N.Y. 
Avoca, N.Y. 
Canisteo, N.Y. 
Conklin-Kirkwood, N.Y. 
Corning, N.Y. 
Endicott, Johnson City & Vesta, N.Y. 
Elmira, N.Y. 
Hornell, N.Y. 
Nichols, N.Y. 
Owego, N.Y. 
Painted Post, N.Y. 
Athens, Pa. 
Codorus Creek, Pa. 
Lawrenceville, Pa. 
Kingston-Edwardsville, Pa. 
Plymouth, Pa. 
Sunbury, Pa. 
Swoyersville-Forty Fort, Pa. 
Union County, Pa. 
Wilkes-Barre-Hanover Township, Pa. 
Williamsport, Pa. 
TABLE 4-0 FLOOD PLAIN INFORMATION STUDIES 
COMPLETED DURING FISCAL YEAR 1975 
(See Section 43 of Text) 
Location Requesting Agency Date Completed Federal Cost 
Frederick Co., Md. Frederick County Planning February 1975 $50,000 
Potomac River, and Zoning Commission 
Frederick Co., Md. 
Prince William Co., Va. Prince William County May 1975 $30,000 
Little Creek Triangle, Planning Department 
Va. 
Blair Co., Pa. Blair County Planning June 1975 $41,000 
Frankstown Br. Juniata Commission 
River, Williamsburg 
Tioga Co., N.Y. Tioga County Board June 1975 $36,000 
Susquehanna River Owego Legislature
4-45 
Federal Cost 
71,082.43 
88,867.40 
.30 
721.69 
50.42 
11.80 
707.92 
166.31 
-8,297.10 
252.27 
472,555.59 
1,036.48 
225.00 
103.07 
3,328.77 
38.03 
-5,825.36 
1,563.58 
246,236.01 
100,968.16 
318.87 
116,283.39 
44.82 
1,295,113.50 
81,386.77 
-- ---- -----

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 4-P MAINTENANCE, OPERATION, AND CAPITAL OUTLAY 
OF WASHINGTON AQUEDUCT 
COST AND FINANCIAL SUMMARY AS OF JUNE 30, 1975 
(See Section 44 of Text) 
Water Supply Costs: 
Total accrued expenditure costed for fiscal year was $8,230,570, distributed as follows: 
Operating Expenses $ 6,169,753 
Deferred 678,277 
Total Operating Expenses $ 6,848,030 
Total Capital Outlay 1,382,540 
Total Cost for Fiscal Year 1975 $ 8,230,570 
Operating expenses, cost per million gallons 97.36 
Financial Summary: 
Net Appropriations $179,670,304 
Less Unexpended Balance 13,436,694 
Total Costs $166,233,610 
4-46

NORFOLK, VA., DISTRICT* 
This District comprises the State of Virginia, 
except the Potomac, Roanoke and Ohio River 
Basins; the entire area on the eastern shore of 
Virginia except for the project for Pocomoke River, 
Maryland and Virginia. On the west shore of Chesapeake 
Bay, all waterways south of Smith Point, 
Virginia, at the mouth of the Potomac River except 
the project for Little Wicomico River, Virginia. 
North Carolina, only the Chowan River Basin 
downstream to and including the mouth of the 
Meherrin River, and the Dismal Swamp Canal 
Route of the Atlantic Intracostal Waterway to the 
Albemarle Sound. West Virginia, only the James 
River Basin. 
IMPROVEMENTS 
Navigation 
1. Aberdeen Creek, Va. ................ 
2. Atlantic Intracostal Waterway 
Between Norfolk, Va. and 
St. Johns River, Fla. 
(Norfolk District) ................... 
3. Aquatic Plant Control .............. 
4. Baltimore Harbor and 
Channels (Norfolk District) .......... 
4A. Cape Henry Channel, Va. ............ 
4B. Rappahannock Shoal 
Channel, Va ..... ................. 
4C. York Spit Channel, Va........ ...... 
5. Blackwater River, Va. ............... 
6. Chincoteague Harbor of 
Refuge, Va. ........................ 
7. Chowan River, N.C............... ... 
8. Deep Creek (Newport 
News, Va.) ........................ 
9. Delaware Bay-Chesapeake Bay 
Waterway Delaware, Maryland, 
Virginia ........................... 
10. Hampton Roads and Harbors 
of Norfolk and Newport News, 
Va. - Collection and 
Removal of Drift ................... 
11. Hampton Institute, Va ............ . 
12. Hampton Roads, Va. ................ 
12A. Channel to Newport News, Va. ....... 
12B. Norfolk Harbor, Va.................. 
12C. Thimble Shoal Channel, Va. ......... 
13. Hoskins Creek, Va. .................. 
14. James River, Va .................... 
15. Lynnhaven Inlet, Va .............. . 
16. Nansemond River, Va. .............. 
17. Newport News Creek, Va ........... . 
18. Supervision of Harbor of 
Hampton Roads, Va. 
(Prevention of Obstructive 
and Injurious Deposits) ............ 
Page 
5-2 
5-2 
5-3 
5-4 
5-4 
5-4 
5-4 
5-4 
5-5 
5-5 
5-6 
5-6 
5-7 
5-7 
5-8 
5-8 
5-9 
5-10 
5-11 
5-11 
5-12 
5-13 
5-13 
5-14 
Navigation (cont. ) Page 
19. Taskinas Creek, Va. ............... 5-14 
20. Wishart Point Channel, Va. .......... 5-15 
21. Reconnaissance and 
Condition Surveys ................... 5-15 
22. Other Authorized Navigation 
Projects ......................... 5-15 
23. Navigation Work Under 
Special Authorization ............... 5-15 
Beach Erosion Control 
24. Virginia Beach, Va. ................ 5-15 
25. Beach Erosion Control Work 
Under Special Authorization ......... 5-16 
Flood Control 
26. Gathright Lake, James River 
Basin, Va........................ 5-16 
27. Buena Vista, Va. .................... 5-17 
28. Other Authorized Flood 
Control Projects ................... 5-18 
29. Flood Control Work Under 
Special Authorization ............... 5-18 
Multiple-Purpose 
Projects Including Power 
30. Salem Church Lake, Va.............. 5-18 
General Investigations 
31. Surveys ............................ 5-18 
32. Collection and Study of 
Basic Date ........................ 5-18 
33. Research and Development .......... 5-18 
* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referred in text and also 
appear at the end of this chapter. 
5-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. ABERDEEN CREEK, VA. 
Location. Aberdeen Creek is a tidal estuary 
entering the northeast side of York River about 
10 miles upstream from Yorktown, Va., and 17 
miles downstream from West Point, Va. The 
Creek lies in the center of and entirely within 
Gloucester County. (See U.S. Coast and Geodetic 
Survey Charts 78 and 498.) 
Previous projects. For details, see page 356 of 
Annual Report for 1962. 
Existing project. This provides for a channel 6 
feet deep at mean low water and 80 feet wide from 
that depth in York River into Aberdeen Creek for 
a distance of about 0.9 mile with a turning basin 
of the same depth, 400 feet wide and 450 feet long 
at the upper end. The mean range of tide is about 
2.4 feet with estimated variations, induced by 
storms, of from 2.5 feet below to 7 feet above 
mean low water. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. For 
details, see page 356 of Annual Report for 1962. 
Terminal facilities. There are several small 
privately owned docks of wooden construction 
located on Aberdeen Creek and an oyster 
shucking house with a dock at the upper end of 
the turning basin. Limited transfer facilities are 
available at this dock. A marine railway is also 
located on the creek. With the construction of the 
public dock required by local cooperation, these 
facilities are considered adequate for present and 
reasonable prospective commerce. 
Operations and results during fiscal year. A 
maintenance dredging contract commencing on 
October 21, 1974 was completed November 1, 
1974. There were removed 50,426 cubic yards of 
credited material at a direct cost of $113,063. 
Maintenance engineering and design, and 
supervision and administration amounted to 
$12,953. 
Condition at end of fiscal year. The existing 
project was completed October 20, 1962. Periodic 
maintenance dredging will continue to maintain 
full project dimensions. 
2. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN 
NORFOLK, VA., AND ST. 
JOHNS RIVER, FLA. 
(NORFOLK DISTRICT) 
Location. Two inland water routes 
approximately paralleling Atlantic coast south of 
Norfolk, Va., between a point in Southern Branch 
of Elizabeth River, Va., 2,500 feet upstream of 
Norfolk & Western Railway bridge and 
Virginia--North Carolina State line in North 
Landing River, a distance of 27.2 miles; and 64.6 
miles between mouth of Deep Creek, Va., and 
mouth of Pasquotank River, N.C. These routes 
are shown on Coast and Geodetic Survey Charts 
452, 1227, 829, and 830. 
Previous projects. For details, see page 476 of 
Annual Report for 1938. 
Existing project. A channel 12 feet deep at 
mean low water and 90 to 250 feet wide following 
Southern Branch of Elizabeth River, 5.2 miles, 
Virginia Land Cut, 8.3 miles, and North Landing 
River, 13.7 miles; and construction of a tidal 
guard lock at Great Bridge, Va. It also provides 
channels 10 feet deep at mean low water and 80 to 
100 feet wide in Deep Creek, 3.1 miles, Turners 
Cut, 4.3 miles, and Pasquotank River, 35.1 miles; 
maintaining Dismal Swamp Canal, 22.1 miles, to 
about 9 feet deep mean canal level over a width of 
50 feet; protection of banks in Turners Cut with 
sheet piling, and cutting certain sharp points in 
Pasquotank River to shorten its course. (See 
Table 5-C at end of chapter on Data Relative to 
Completed Locks included in Project.) 
Project includes operating and care of 
completed locks, dams, and bridges, under 
maintenance. Southern Branch of Elizabeth River 
and Deep Creek sections of the two routes are 
tidal, mean range being about 3 feet with 
extremes of minus 3.5 and plus 9.6 feet. 
Remaining sections are nontidal with fluctuations 
of 1 to 2 feet in level due to winds. Cost for new 
work for completed project was $3,396,276. 
Protection to canal property at Great Bridge 
portion is considered inactive and excluded from 
foregoing cost. Estimated cost of this portion 
(1954) is $265,000. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. Existing facilities are 
considered adequate. See Annual Report for 1970. 
Operations and results during fiscal 
year. Operation and ordinary maintenance of the 
project, consisting of real estate management 
services, condition and operation studies 
operation and care of locks, bridges, spillways, 
5-2

NORFOLK, VA., DISTRICT 
wharves, canal plant, grounds, roads, buildings, 
etc., with Government plant and hired labor, 
were carried on during the year at a cost of 
$881,679. 
A contract for the lock area lighting at Great 
Bridge Reservation awarded in fiscal year 1974 
was completed on November 25, 1974 at a cost of 
$17,585. 
A contract for water distribution and service 
lines at Great Bridge Reservation awarded in 
fiscal year 1974 was completed on May 9, 1975 at 
a cost of $88,572. In addition, $6,386 was 
incurred for installation of a new water meter for 
the City of Chesapeake. 
A contract to modernize the vehicular traffic 
control system at Great Bridge was completed on 
January 3, 1975, at a cost of $7,350. 
Permanent operating equipment to be used on 
both routes, was purchased at a direct cost of 
$16,463. Maintenance snagging and bank 
trimming operations, with Government plant and 
hired labor, were carried on at several locations on 
both routes intermittently at a direct cost of 
$20,503. 
Maintenance repairs to bulkheads on both 
routes, with Government plant and hired labor, 
were accomplished at a direct cost of $2,036. 
Maintenance engineering and design, supervision 
and administration and real estate activity costs, 
less credits for collections for quarters and 
damages to Government property, amounted to 
$54,276. 
Condition at end of fiscal year. Project is 
complete. For construction details, see Annual 
Report for 1966. Periodic maintenance dredging 
is being done to maintain full project dimensions 
on the Albemarle and Chesapeake Canal Route 
and about a 7-foot usable depth on the Dismal 
Swamp Canal Route which is considered adequate 
for existing traffic. 
3. AQUATIC PLANT CONTROL, 
VA. 
Location. Navigable waters, tributary 
streams, connecting channels, and other allied 
waters in Norfolk District. Areas in which there 
are significant aquatic plant nuisance problems 
include: Back Bay-Eurasian Water Milfoil; 
Rappahannock River - Eurasian Water Milfoil; 
City of Norfolk-Sea Lettuce; and Chickahominy 
River-Elodea. 
Existing project. Provides for control and 
progressive eradication of water-hyacinth, 
alligatorweed, Eurasian water milfoil, and other 
obnoxious aquatic plant growths, from the 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and 
wildlife conservation, public health, and related 
purposes, including continued research for 
development of the most effective and economic 
control measures, to be administered by the Chief 
of Engineers, under the direction of the Secretary 
of the Army in cooperation with other Federal 
and State agencies. 
Local cooperation. Local interests must agree 
to hold the United States free from damages that 
may occur from operations performed in 
connection with his project, and participate to 
extent of 30 percent of cost of program. 
Operations and results during fiscal year. In 
order to evaluate the effects of the July 1973 
herbicide application, on the Walker Dam 
Impoundment, Chickahominy River, Virginia 
two aquatic plant research projects are 
continuing. The first project, entitled "Aquatic 
plant control using herbicides in a large potable 
water supply reservoir" is being conducted by the 
Department of Fisheries and Wildlife Sciences of 
Virginia Polytechnic Institute and State 
University with a funding level of $15,000 per 
year for a period of three years. The second 
research effort, entitled "A determination of the 
effects on phytoplankton and other selected 
parameters induced by an herbicide application to 
Chickahominy Reservoir," is being conducted by 
the Virginia Commission of Game and Inland 
Fisheries on a cost-sharing basis for a period of 
three years. The total Federal share of this 
project is $30,000. 
Conditions at end of fiscal year. The second of 
three years of each of the two projects referenced 
above has been completed. On continuing basis, 
the physical, chemical and biological 
characteristics of the reservoir after herbicide 
application are being monitored. It is anticipated 
that the research efforts underway will evaluate 
the ecological and physiological changes 
associated with the herbicide application. The 
information derived from these studies will 
provide much needed data regarding the 
applicability of treatment methods to other 
similarly affected waters, as well as providing 
substantial information regarding the 
5-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
employment of diquat and potassium endothall in 
potable waters. 
4. BALTIMORE HARBOR AND 
CHANNELS (NORFOLK 
DISTRICT) 
Existing project provides for deep water 
approach channels in Chesapeake Bay and branch 
channels in Baltimore Harbor. Northern portion 
including Baltimore Harbor is under jurisdiction 
of Baltimore District. Portion under jurisdiction 
of Norfolk District is more fully described below. 
4A. CAPE HENRY CHANNEL, VA. 
Location. At mouth of Chesapeake Bay 
opposite Cape Henry. (See Coast and Geodetic 
Survey Chart 1222.) 
Existing project. A channel about 2.3 miles 
long, 1,000 feet wide, and 50 feet deep at mean 
low water through shoal at mouth of Chesapeake 
Bay opposite Cape Henry. Under ordinary 
conditions mean range of tide 2.5 feet and 
extreme 3 feet. Extremes of irregular fluctuation 
due to combined effect of wind and tides, referred 
to mean low water, are minus 2 feet and plus 9.5 
feet. (See Table 5-B for Authorizing Legislation. ) 
4B. RAPPAHANNOCK SHOAL 
CHANNEL, VA. 
Location. In lower Chesapeake Bay opposite 
mouth of Rappahannock River and about 50 miles 
northerly from Atlantic Ocean at entrance of 
Chesapeake Bay. (See Coast and Geodetic Survey 
Chart 1222.) 
Existing project. A channel about 9.9 miles 
long, 1,000 feet wide, and 50 feet deep at mean 
low water between contours of that depth in 
Chesapeake Bay, opposite Rappahannock River. 
Under ordinary conditions mean tidal range is 2.5 
feet and extreme 3 feet. Extremes of irregular 
fluctuation, due to combined effect of wind and 
tides, referred to mean low water, are minus 2 feet 
and plus 9.5 feet. (See Table 5-B for Authorizing 
Legislation.) 
4C. YORK SPIT CHANNEL, VA. 
Location. In lower Chesapeake Bay opposite 
mouth of York River and about 20 miles northerly 
from Atlantic Ocean at entrance of Chesapeake 
Bay. (See Coast and Geodetic Survey Chart 
1222.) 
Previous project. For details, see Annual 
Report for 1932. 
Existing project. A channel about 18.2 miles 
long, 1,000 feet wide, and 50 feet deep at mean 
low water between contours of that depth in 
Chesapeake Bay opposite York Spit. Under 
ordinary conditions mean tidal range is 2.5 feet 
and extreme 3 feet. Extremes of irregular 
fluctuation, due to combined effect of wind and 
tides, referred to mean low water, are minus 2 feet 
and plus 9.5 feet. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. These three channels form 
the access between lower and upper Chesapeake 
Bay. 
Operations and results during fiscal 
year. Operation of the project including 
condition studies and inspections and reports 
amounted to $10,326. 
5. BLACKWATER RIVER, VA. 
Location. The river rises in Prince George 
County, near Petersburg, Va., and flows in a 
general southeasterly direction for 80 miles where 
it unites with the Nottoway River to form the 
Chowan River, which empties into Albemarle 
Sound. The portion under improvement extends 
from its mouth to Franklin, Va., a distance of 
14.5 miles. (See U.S. Geological Survey, Holland 
quadrangle, Va.) 
Previous projects. For details, see page 215 of 
Annual Report for 1969. 
Existing project. Provides for clearing the 
river between Franklin, Va., and the mouth, a 
distance of about 14.5 miles, of obstructions so as 
to afford a condition of easy navigation for boats 
of 7-foot draft and cut-off channels 80 feet wide 
and 11 feet deep at Cherry Grove and Georges 
Bend. The stream is non-tidal. The portion of the 
river under improvement is subject to freshets of 
short duration, causing rises 3 to 4 feet, but the 
general stage of the river remains for the greater 
part of the time at the elevation of Albemarle 
Sound, with which it connects. 
5-4

NORFOLK, VA., DISTRICT 
The 12-foot channel portion of the project is 
inactive. The cost of this portion was last revised 
in 1969 and was estimated to be $253,000. (See 
Table 5-B for Authorizing Legislation.) 
Local cooperation. Local interests have 
furnished all lands, easements, and rights-of-way 
and spoil-disposal areas, for initial construction 
of the cut-off channels at Cherry Grove and 
Georges Bend. 
Terminal facilities. There are about 1,300 feet 
of wooden bulkhead at Franklin, Va., and a 
marine railway that will accommodate vessels up 
to 100 feet in length, all privately owned. These 
facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Engineering and design cost amounted to 
$5,518 with Supervision and Administration 
amounting to $6,819. A contract for the cut-off 
channels at Georges Bend and Cherry Grove was 
completed December 20, 1974. There were 
removed 117,676 cubic yards of credited material 
at a cost of $259,569. Surveys and Layouts, 
Litigations and Real Estate amounted to $14,129. 
Condition at end of fiscal year. Snagging and 
clearing to provide a usable channel for 7-foot 
draft traffic is completed. Periodic maintenance 
will be performed to maintain the 7-foot usable 
depth. The cut-off channels at Cherry Grove and 
Georges Bend were constructed during fiscal year 
1975. The remainder of the project is inactive. 
6. CHINCOTEAGUE HARBOR 
OF REFUGE, VA. 
Location. Chincoteague is located on 
Chincoteague Island in Accomack County on the 
Atlantic Coast of Virginia, approximately 
midway between the entrance to Delaware Bay 
and the Virginia Capes. Chincoteague Island is 
separated from the mainland on the west by 
Chincoteague Channel and from the barrier island 
known as Assateague Island, on the east by 
Assateague Channel and Assateague Bay. The 
harbor of refuge is at the lower end of 
Chincoteague Island. (See U.S. Coast and 
Geodetic Survey Chart No. 1220.) 
Existing project. This provides for a channel 8 
feet deep at mean low water and 60 feet wide from 
that depth in the canal at the lower end of 
Chincoteague Island into an anchorage basin of 
the same depth 235 feet wide and 650 feet long. 
The mean range of tide is about 2.6 feet. Greater 
fluctuations in water level are caused by high 
wind and storms. 
The cost for new work for the completed project 
was $49,239. The existing project was authorized 
by the Chief of Engineers under authority of 
section 107 of the River and Harbor Act of 1960 
and based on the report on file in the Office of the 
Chief of Engineers dated November 30,1960. The 
latest map appears in that document. 
Local cooperation. Fully complied with for 
initial construction. See 1962 Annual Report for 
items of local cooperation. 
Terminal facilities. Adequate public terminal 
facilities have been built by the town of 
Chincoteague. Additional facilities will be 
provided as the need develops. 
Operations and results during fiscal year. Real 
Estate utilization investigations amounted to 
$129 with survey investigations amounting to 
$324. 
$5,648 was expended on a final draft 
environmental impact statement. Administrative 
cost amounted to $1,208. 
Conditions at end of fiscal year. The existing 
project was completed in June 1962. Periodic 
maintenance dredging will continue to maintain 
full project dimensions, as funding permits. 
Shoaled conditions exist at the harbor entrance 
which limit usable depth to about 4 feet at mean 
low water. 
7. CHOWAN RIVER, N.C. 
(NORFOLK DISTRICT) 
Location. Chowan River is a nontidal, 
freshwater stream, formed by the confluence of 
the Nottaway and Blackwater Rivers (both 
entirely in Virginia) at the Virginia-North 
Carolina State line. From the confluence, the 
Chowan River flows south and southeast 52 miles 
to empty into the northwestern end of Albemarle 
Sound 4 miles west of Edenton, N.C. 
Previous projects. For details, see page 614 of 
Annual Report for 1950. 
Existing project. Provides for a channel 12 feet 
deep and 80 feet wide from the mouth of the 
confluence of the Nottaway and Blackwater 
Rivers, Va., including a cut-off channel of like 
dimensions through a sharp bend near 
Riddicksville, N.C. The portion of the project 
downstream of the Meherrin River is under the 
jurisdiction of the Wilmington District. 
5-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
The existing project was adopted by the River 
and Harbor Act of March 2, 1945 (H. Doc. 101, 
76th Cong., 1st sess.) The latest published map is 
in that document. 
Local cooperation. Local interests have 
furnished all lands, easements, and rights-of-way 
and spoil-disposal area for initial construction of 
the cut-off channel near Riddicksville. 
Terminal facilities. Existing facilities for 
loading pulpwood along the river are considered 
adequate. 
Operations and results during fiscal 
year. Engineering and Design cost amounted to 
$4,383 with Supervision and Administration cost 
amounting to $2,156. 
A contract for the cut-off channel near 
Riddicksville was completed January 4, 1975. 
There were removed 35,060 cubic yards of 
credited material at a cost of $77,472. 
Surveys and layouts amounted to $338. 
Condition at end of fiscal year. The cut-off 
channel near Riddicksville, N.C. was constructed 
during fiscal year 1975. Periodic maintenance will 
be performed to maintain a 7-foot usable depth on 
the project. The remainder of the project is 
inactive. 
8. DEEP CREEK, NEWPORT 
NEWS, VA. 
Location. Deep Creek is a tidal estuary of the 
James River, lying wholly in the city of Newport 
News, Va. It is about 3 miles in length, flows in a 
southeasterly direction, and empties into the 
James River on its northerly side about 10.5 miles 
upstream from the mouth of the James River. 
(See U.S. Coast and Geodetic Survey Chart No. 
529.) 
Previous projects. For details, see page 360 of 
Annual Report for 1962. 
Existing project. This provides for an 
approach channel 8 feet deep at mean low water 
and 100 feet wide extending from the 8-foot depth 
contour in James River to a point where the 
natural creek entrance to Deep Creek is 
constricted, a distance of 9,040 feet; thence 8 feet 
deep and 60 feet wide through the constricted 
entrance, a distance of 700 feet; the enlargement 
of the harbor in Deep Creek opposite Menchville, 
extending upstream to a point near Parkers 
Ianding and to the foot of Maxwells Lane, from 
6.4 acres to about 20 acres with depth of 8 feet, 
400 to 740 feet wide and 1,940 feet long. 
IUnder ordinary conditions the mean tidal range 
is 3 feet. The extremes of irregular fluctuations 
referred to mean low water due to the combined 
effect of wind and tides are minus 2 feet and plus 
9.8 feet. 
The cost for new work for the completed project 
was $202,622. 
Local cooperation. Fully complied with for 
initial construction. See 1948 Annual Report for 
items of local cooperation. 
Terminal facilities. There are four privately 
owned piers and one public county pier and 
bulkhead of wooden construction at Menchville. 
One pier is used for pleasure craft only. The 
remainder are commercial. There is also a shore 
landing for the receipt of sand and gravel, several 
privately owned wooden piers and two marinas 
are on the south side of the harbor. The wharves 
have no rail connections, but are served by State 
highways. The existing facilities are considered 
adequate for present commerce. 
Operations and results during fiscal 
year. Engineering and design costs amounted to 
$2,610. Work is continuing on the environmental 
impact statement with $2,302 being expended 
during FY 1975. 
Survey Investigations amounted to $2,230 
with real estate costs amounting to $802 for 
disposal of land. Supervision and administrative 
costs amounted to $1,603. 
Condition at end of fiscal year. Construction of 
the project to a depth of 6 feet at mean low water 
over widths of 50 to 80 feet was commenced in 
March and completed in May 1939. Construction 
of the channel and harbor to project dimensions 
was commenced in March and completed in 
November 1956. Periodic maintenance to restore 
full project dimensions has been delayed pending 
location of a suitable disposal area. Shoaled 
conditions limit usable depth to about 3-feet at 
the harbor entrance. 
9. DELAWARE BAY-CHESAPEAKE 
BAY WATERWAY 
DELAWARE, MARYLAND, 
VIRGINIA (VIRGINIA 
PORTION) (FORMERLY 
WATERWAY ON THE COAST 
OF VIRGINIA) 
Location. Between barrier beach along 
Atlantic Ocean on the east and Virginia portion of 
5-6

NORFOLK, VA., DISTRICT 
mainland peninsula on the west. It extends from 
south end of Chincoteague Bay through a number 
of creeks, thoroughfares and bays, to enter 
Chesapeake Bay in vicinity of Fisherman Island, 
just south of Cape Charles, the southern tip of the 
peninsula, for 83.7 miles. (See Coast and Geodetic 
Survey Charts 1220, 1221, and 1222.) 
Existing project. An inland waterway 6 feet 
deep at mean low water and 60 feet wide from 
Chesapeake Bay to Chincoteague Bay, Va. Mean 
range of tide is about 3 feet. Greater fluctuations 
in water level are caused by high winds and 
storms. (See Table 5-B for Authorizing 
Legislation.) 
A modification of the project approved during 
1970 under Section 201 of the Flood Control Act 
of 1965, authorizes relocation of portions of the 
waterway and widening to 100 feet. The 
modification will also rename the project; 
Delaware Bay - Chesapeake Bay Waterway in 
Delaware, Maryland, Virginir (Virginia Portion). 
Local cooperation. Complied with, except local 
interests are to furnish spoil-disposal areas for 
future maintenance. 
Terminal facilities. Existing facilities are 
considered adequate. For details, see page 224 of 
Annual Report for 1969. 
Operations and results during fiscal 
year. Operation of the project, including 
condition surveys, inspections and reports 
amounted to a cost of $17,281. Maintenance 
dredging, by contract, was commenced March 1, 
1975, and was completed March 21, 1975. There 
were removed 99,194 cubic yards of credited 
material, place measure, at a direct cost of 
$141,013. Marsh seeding at Sloop Channel and 
Burton's Bay by contract was completed at a cost 
of $12,724. Maintenance engineering and design 
and supervision and administration amounted to 
cost of $77,131. 
Condition at end of fiscal year. Existing 
project was completed in 1959. Annual 
maintenance dredging is being done to maintain 
full existing project dimensions. Construction of 
the 1970 modification has not begun. 
10. HAMPTON ROADS AND 
HARBORS OF NORFOLK 
AND NEWPORT NEWS, 
VA.-COLLECTION AND 
REMOVAL OF DRIFT 
Location. Hampton Roads is a natural harbor 
300 miles south of New York and 180 miles south 
of Washington D.C. Its principal tributaries are 
James River, affording a natural deep harbor at 
Newport News, Va.; Elizabeth River, with its 
Southern, Eastern, and Western Branches, 
providing harbors for Norfolk and Portsmouth, 
Va.: and Hampton Creek serving the harbor at 
Hampton, Va. (See Coast and Geodetic Survey 
Charts 400 and 452.) 
Existing project. Collection and removal of 
drift in Hampton Roads and its tributary waters, 
authorizes the Secretary of the Army to allot 
necessary amounts for work from appropriations 
for maintenance and improvement of existing 
river, and harbor works or from other available 
appropriations, and that this work shall be 
carried on as a separate and distinct project. It is 
wholly a work of maintenance. Purpose of work is 
to afford relief from variable conditions of 
obstruction, and no advance estimate of amount 
of work required and its proper cost can be made 
(See Table 5-B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Norfolk Harbor, Va. 
and Channel to Newport News, Va. 
Operations and results during fiscal 
year. Maintenance operations at a direct cost of 
$29.882 with Government plant and hired labor. 
consisted of collection and disposal of an 
estimated 71,150 cubic feet of a variety of floating 
refuse, ranging from discarded furniture to heavy 
timbers and piling. Repair of the incinerator at 
Craney Island Disposal Area was completed 
March 6, 1975. Contract cost in fiscal year 1975 
was $12,300. Engineering and administration 
cost amounted to $19,854. Operation cost of the 
project amounted to $14,004. 
Condition at end of fiscal year. Existing 
project is one of continuous maintenance for 
which no percentage of completion exists. 
Operations under existing project began in July 
1950. Costs for removal of drift before then were 
carried under "Norfolk Harbor, Va." The 
incinerator constructed at Craney Island Disposal 
began operation in fiscal year 1974. 
11. HAMPTON INSTITUTE, VA. 
Location. Hampton Institute is located in the 
City of Hampton, Virginia at the southern end of 
5-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
the peninsula separating the James and York 
Rivers. (See Coast and Geodetic Survey Chart 
12245.) 
Existing project. The existing project consists 
of a 1,500-foot rip rapped revetment constructed 
to elevation +5 feet m.s.l. on a 2:1 slope an 
average of 25 feet riverward of the existing 
shoreline including backfill to reclaim previously 
lost land. The estimated total first cost of the 
improvement is $270,000 and the annual cost is 
$22,000. Non-Federal first costs are estimated at 
$160,400. (See Table 5-B for Authorizing 
Legislation). 
Local cooperation. Local interests have been 
required to: 
(a) Provide without cost to the United 
States all necessary lands, easements and rightsof-
way. 
(b) Hold and save the United States free 
from claims for damages which may result from 
construction and subsequent maintenance of the 
project. 
(c) Assure continued public use of the shore 
upon which the amount of Federal participation is 
based, and its administration for public use 
during the economic life of the project. 
(d) Assure maintenance and repair during 
the useful life of the works as required to serve the 
project's intended purpose. 
(e) Provide and maintain necessary access 
roads, parking areas, and other public use 
facilities open and available to all on equal terms. 
(f) Provide a cash contribution, presently 
estimated at $189,486, equal to 59.5 percent of 
the first cost and assume full responsibility for all 
project costs in excess of the Federal cost 
limitation of $1,000,000. 
Operations and results during fiscal 
year. Engineering and design and supervision 
and administrative costs amounted to $34,412. 
A contract for the shore protection was 
awarded February 20, 1975. 41 percent of the 
project has been completed during FY 1975 at a 
Federal cost of $18,800 and $91,337 non-Federal 
cost. 
Condition at end of fiscal year. Construction of 
the project is continuing. The project is scheduled 
for completion during FY 1976. 
12. HAMPTON ROADS, VA. 
The three projects, Norfolk Harbor, Va., 
Thimble Shoal Channel, Va., and Channel to 
Newport News, Va., are grouped under the above 
heading for construction purposes only. Details of 
each project are given below. 
12A. CHANNEL TO 
NEWPORT NEWS 
Location. West of North entrance to Norfolk 
Harbor Channel connects deep water in James 
River with Hampton Roads. (See Coast and 
Geodetic Survey Chart 400.) 
Previous projects. For details, see page 459 of 
Annual Report for 1938. 
Existing project. Dredging a channel 45 feet 
deep at mean low water and 800 feet wide from 
that depth in Norfolk Harbor Channel about 4.5 
miles to Newport News, and two deepdraft 
anchorage berths opposite Newport News 45 feet 
deep over 1,200-foot swinging radius. Under 
ordinary conditions mean tidal range is 2.7 feet 
and extremes 2.1 and 3 feet. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. Latest published 
description of terminal facilities is in "Port Series 
No. 11 (revised 1959) Part 2" on Ports of Hampton 
Roads, Va., prepared by Board of Engineers for 
Rivers and Harbors. Since 1959, piers 3, 4 and 5 
have been replaced by a new cargo pier, container 
handling facilities have been added and the 
capability of the port handling general cargo and 
coal has increased. 
Operations and results during fiscal 
year. Engineering, inspection and supervision 
and administration amounted to $15,284. 
The removal and disposal of the wreck Bangor, 
in progress at the beginning of fiscal year 1975 
was completed on May 5, 1975, at a direct cost of 
$614,316. 
Condition at end of fiscal year. New work 
dredging of the 40-foot project was commenced in 
March 1929 and completed in June 1931. 
Deepening and widening the channel to 45 feet 
deep and 800 feet wide commenced March 1967 
and was completed in December 1969. New work 
dredging, to a 40-foot depth, of the two 
anchorages opposite Newport News was 
completed in November 1971. Work remaining to 
complete project consists of deepening the two 
deep-draft anchorages opposite Newport News 
from 40 to 45 feet. Periodic maintenance is being 
done to provide full project dimensions on the 
completed portions of the project. 
5-8

NORFOLK, VA., DISTRICT 
12B. NORFOLK HARBOR, VA. 
Location. Norfolk, Va., is 187 miles south of 
Baltimore, Md., and 30 miles from entrance to 
Chesapeake Bay at Cape Charles and Cape 
Henry. Harbor extends 18.3 miles from 45-foot 
contour in Hampton Roads to a point 2,500 feet 
above Norfolk & Western Railway bridge over 
Southern Branch of Elizabeth River. (See Coast 
and Geodetic Survey Charts 400 and 452.) 
Previous projects. For details see page 454 of 
Annual Report for 1938. 
Existing project. A main channel 45 feet deep, 
1,500 feet wide from that depth in Hampton 
Roads near Fort Wool to a point just south of 
Norfolk International Terminal piers; thence at 
same depth 800 feet wide to Lambert Point; 
thence 40 feet deep and 750 feet wide to mouth of 
Southern Branch of Elizabeth River, and 450 feet 
wide up this branch to Belt Line Railroad bridge, 
including an approach and turning area to same 
depth and a maximum width of 830 feet opposite 
Norfolk Naval Shipyard, extending downstream 
3,250 feet from Belt Line Railroad Bridge, thence, 
40 feet deep, 375 feet wide and 1 mile long to 
Norfolk & Western (formerly Virginian) Railway 
bridge; thence, 35 feet deep, 250 feet wide, and 
3.1 miles long to a point 1,900 feet above Norfolk 
& Western Railway (Gilmerton) bridge, with 
adequate widening of channel at bends, a turning 
basin 35 feet deep and 600 by 600 feet at upstream 
end, a turning basin 35 feet deep, 400 to 600 feet 
wide, and 800 feet long at mouth of St. Julians 
Creek, a total of 18.3 miles; a channel in Eastern 
Branch, 25 feet deep, 500 feet wide, and 1.09 
miles long from 40-foot channel at mouth to 
Norfolk & Western Railway bridge; thence, 25 feet 
deep, 300 feet wide, and 0.55 mile long, to 
Campostella Bridge; thence, 25 feet deep, 200 feet 
wide, and 1.2 miles long to Norfolk & Western 
(formerly Virginian) Railway bridge; and for 
maintenance at a depth of 25 feet of existing 
turning basin about 5.5 acres in extent at head of 
existing project just below Norfolk & Western 
(formerly Virginian) Railway bridge; a channel in 
Western Branch, from 40-foot channel in 
Elizabeth River 24 feet deep, 300 feet wide, and 
0.78 mile long, thence 24 feet deep and 200 feet 
wide, for 0.37 mile to West Norfolk Highway 
bridge; thence 18 feet deep, 150 feet wide, 0.57 
mile long; a channel in Scotts Creek between 40- 
foot channel at mouth and a point 100 feet above 
former location of Atlantic Coast Line Railroad 
bridge (about 0.73 mile upstream), 12 feet deep 
and 100 feet wide: anchorage areas on west side of 
40-foot channel opposite Lambert Point and 
south of Craney Island aggregating 173 acres, 
consisting of: One anchorage space 1,500 feet 
square and 38 feet deep; one anchorage space 
1,500 feet square and 35 feet deep; one anchorage 
1,000 feet wide, 3,000 feet long, and 20 feet deep; 
another anchorage of 45 acres, 12 feet deep, near 
Pinner Point; two anchorages opposite Sewells 
Point 45 feet deep over swinging radius of 1,200 
feet; and a trapezoidal-shaped disposal area of 
about 2,500 acres of flats adjacent to the north of 
Craney Island, inclosed by stone-faced levees, 
three sluiceways, in west levee, an access road; 
facilities for unloading of hopper dredged material 
consisting of mooring dolphins, a mooring barge 
anchorage, 100 by 600 feet. 21 feet deep, with 
approach channel 300 by 3,600 feet, 30 feet deep 
connecting anchorage with Norfolk Harbor 45- 
foot channel, and a 28-inch discharge pipeline to 
the leveed area; and facilities for contract 
rehandling of bucket-bredged materials 
consisting of a rehandling basin, 1,000 by 1,000 
feet, 46 feet deep, protected by a spur levee 
extending 2,350 feet from main levee and 
provided with approach-exit channels 200 feet 
wide by 18 feet deep to Norfolk Harbor 45-foot 
channel and a pipeline trestle from rehandling 
basin to leveed area. All depths are referred to 
mean low water. Mean tidal range is 2.7 feet and 
extreme is 3.4 feet. Extremes of irregular 
fluctuations, due to combined effect of tides and 
wind, referred to mean low water, are minus 3.5 
feet and plus 9.6 feet. Eastern Branch, 30-foot 
channel portion is considered inactive. Estimated 
cost (1954) of this portion is $43,000. (See Table 
5-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Latest published 
description of terminal facilities is in "Port Series 
No. 11 (revised 1959) Part 2" on Ports of Hampton 
Roads, Va., prepared by Board of Engineers for 
Rivers and Harbors. Since 1959, numerous 
additions have been made to facilities for handling 
coal and general cargo. Notable additions include 
construction of a coal pier at Norfolk and container 
handling facilities at Norfolk and Portsmouth, Va. 
Operations and results during fiscal 
year. Operation of the project, including 
condition and operation studies, office studies, 
reports, sampling and analysis of bottom 
materials, care of buildings, grounds, utilities, 
roads, levees, plant and hopper dredge pipeline 
5-9

ILerUT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
amounted to a cost of $596,840. 
Maintenance dredging of the 45-foot channel 
by contract was commenced January 29, 1975 
and completed April 10, 1975. There were 
removed 1,286,023 cubic yards of credited 
material place measure, at a direct cost of 
81.019.104. Maintenance dredging of the 
Southern Branch of the Elizabeth River; 35 foot 
channel was commenced July 12, 1974 and 
completed August 11, 1974. There were removed 
211.549 cubic yards of credited material, place 
measure, at a direct cost of $369,412. Bulkhead 
repair costs amounted to $1,871. Dredging ranges 
and buoy service amounted to $13,665. Repair 
costs to the Mooring Dolphins amounted to 
83.076. 
Maintenance levee, floodwall, and sluiceway 
work, by both contract and hired labor was 
accomplished at a direct cost of $10,620. 
Equipment for use at Craney Island Disposal 
Area was purchased at a direct cost of $37,550. 
Maintenance engineering and design and 
supervision and administration costs less 
miscellaneous income amounted to a net cost of 
$101,468. 
Condition at end of fiscal year. For details of 
construction on portion of 'existing project 
completed prior to fiscal year 1966, see Annual 
Report for 1965. Since 1965, new work dredging 
of 45-foot channel from Fort Wool to Norfolk and 
Western Railway Company coal piers commenced 
March 1966 and was completed in August 1967. 
New work dredging of turning basin in 35-foot 
channel opposite St. Julians Creek commenced 
June 1966 and was completed in July 1966. New 
work dredging of 40-foot channel between Norfolk 
and Portsmouth Belt Line Railroad Bridge and 
Norfolk and Western Railway Bridge commenced 
June 1968 and was completed in July 1968. New 
work dredging of the two deep-draft anchorages 
opposite Sewells Point was completed in 
February 1972. Work remaining to complete the 
active portion of the project consists of deepening 
one of the deep-draft anchorages to 45 feet. 
Annual maintenance dredging is being done to 
maintain full project dimensions in the 45-foot 
deep channel from Hampton Roads to Lambert 
Point and the 40-foot deep channel from Lambert 
Point to the Old Virginian Railway Bridge. 
Periodic maintenance dredging is being done to 
maintain full project dimensions in the 35-foot 
deep channel from Old Virginian Railway Bridge 
to the turning basin above Norfolk and Western 
Railway Bridge at GCilmerton. Annual operation 
and maintenance of the Craney Island Disposal 
Facility is continuing. Shoaled conditions exist to 
some extent on the remaining portions of the 
project; however, existing dimensions are 
considered adequate. 
12C. THIMBLE SHOAL 
CHANNEL, VA. 
Location. In lower portion of Chesapeake Bay 
between Hampton Roads and the ocean, 20 miles 
northeast of center of Norfolk Harbor, extending 
southeasterly 12 miles from a point 1.25 miles 
east of Thimble Shoal Lighthouse toward 
entrance to Chesapeake Bay. (See Coast and 
Geodetic Survey Chart 1222.) 
Previous projects. For details, see page 470 of 
Annual Report for 1932. 
Existing project. Provides for dredging a 
channel 12 miles long, 1,000 feet wide, and 45 feet 
deep at mean low water with auxiliary channels 
450 feet wide and 32 feet deep at mean low water 
adjoining each side of 1,000-foot channel. Under 
ordinary conditions mean tidal range is 2.5 feet 
and extreme 3 feet. Extremes of irregular 
fluctuation, due to combined wind and tides, 
referred to mean low water, are minus 3 feet and 
plus 7 feet. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Terminal facilities. Project serves as an 
entrance channel to Hampton Roads. See 
"Norfolk Harbor, Va.," "Channel to Newport 
News, Va.; " etc. 
Operations and results during fiscal 
year. Maintenance dredging of the Thimble 
Shoal Channel was commenced October 1, 1974 
and completed December 31, 1974 by U. S. 
Hopper Dredge Goethals. There were removed 
1,129.143 cubic yards of credited material, at a 
direct cost of $1,614,627. Maintenance 
engineering and design and supervision and 
administration cost amounted to $39,785. 
Condition at end of fiscal year. Existing 
project is complete, except for auxiliary channels 
which are in an inactive status. New work 
dredging of channel 750 feet wide and 40 feet deep 
was commenced in December 1917 and completed 
June 1929. Widening this channel to 1,000 feet at 
same depth was commenced in February and 
completed in April 1957. Deepening this channel 
to 45 feet commenced December 1965 and was 
5-10

NORFOLK, VA., DISTRICT 
completed in May 1970. 
Periodic maintenance dredging is being done to 
maintain a 45-foot depth in the 1,000-foot wide 
main channel. 
13. HOSKINS CREEK, VA. 
Location. A tributary 2.5 miles long flowing 
easterly and entering right bank of 
Rappahannock River in Essex County, Va., 42 
miles upstream from its mouth in Chesapeake 
Bay and one-half mile downstream from town of 
Tappahannock, Va. Creek is 102 miles northerly 
of Norfolk, Va. (See Coast and Geodetic Survey 
Chart 535.) 
Existing Project. A channel 10 feet deep from 
that depth in the Rappahannock River to the 
highway bridge three-quarters of a mile above the 
mouth with widths of 100 feet through the bar in 
Rappahannock River and 80 feet within the creek 
suitably widened at bends, and a turning basin of 
same depth 250 feet long and 200 feet wide at 
public landing one-half mile above the mouth of 
creek. Improved section is 1.1 miles long. Plane 
of reference is mean low water. Tidal ranges are: 
Mean, 1.6 feet; irregular, 2.5 feet; and extreme, 
about 7.5 feet. Federal cost of new work for 
completed project, was $44,100. (See Table 5-B 
for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are two bulkhead 
landings and two wharves. State of Virginia 
operates a small boat launching ramp on the 
creek. Facilities considered adequate for 
navigation. 
Operations and results during fiscal 
year. Engineering and design amounted to 
$3,425. An environmental assessment was 
prepared at a cost of $1,860. Survey 
investigations amounted to $3,776 and $2,481 
was expended for supervision and administration. 
Condition at end of fiscal year. Existing 
project as modified in 1945, was completed in 
December 1948. Periodic maintenance to restore 
project dimensions has been delayed pending 
location of a suitable disposal area. Shoaled 
conditions limit usable depth to about 4-feet in 
the entrance channel. 
14. JAMES RIVER, VA. 
Location. Formed by junction of Cowpasture 
and Jackson Rivers in Botetourt County, Va., 
flows easterly 340 miles, and empties into 
Hampton Roads at Newport News, Va. (See 
Coast and Geodetic Survey Charts 529, 530, and 
531.) 
Previous projects. For details, see page 461 of 
Annual Report for 1938. 
Existing project. A channel 35 feet deep and 
300 feet wide from mouth to Richmond 
Deepwater Terminal; and thence a channel 18 feet 
deep and 200 feet wide from Deepwater Terminal 
to Richmond lock; a mooring basin 35 feet deep, 
180 to 220 feet wide, and 2,100 feet long alongside 
channel opposite waterfront at Hopewell; 
enlargement of turning basin at Richmond 
Deepwater Terminal to 825 feet wide, 2,770 feet 
long, and 35 feet deep; a turning basin in 
Richmond Harbor 200 feet wide, 600 feet long, 
and 18 feet deep; and construction of spur and 
training dikes. Depths of channels are referred to 
mean low water. Total length of channel included 
in project is 87 miles, which is the navigable 
section. Mean tidal ranges under ordinary 
conditions for different parts of river: Mouth, 2.6 
feet; Jamestown, 2 feet; City Point, 2.6 feet; 
Richmond, 3.2 feet. Spring tide ranges under 
ordinary conditions at same localities: Mouth, 3.1 
feet; Jamestown, 2.4 feet; City Point, 3 feet; 
Richmond, 3.2 feet. Ordinary fluctuations of 
stage at Richmond, due to floods, are 6 to 12 feet 
above mean low water. Extreme fluctuations are 
16 to 32 feet. Flood heights below Richmond 
diminish rapidly; the extreme, according to 
available information, is about 11 feet lower at 
Dutch Gap, 14 miles below, and 17 to 18 feet 
lower 20 miles below. Estimated (1971) total cost 
for new work is $71,145,940 including required 
non-Federal costs for conditions of local 
cooperation imposed by River and Harbor Acts of 
1930, 1945 and 1950, estimated (1939) to be 
$1,949,700, and River and Harbor Act of 1962, 
estimated (1971) to be $2,950,000. (See Table 5-B 
for Authorizing Legislation.) 
Local cooperation. Fully complied with for 
conditions imposed by River and Harbor Acts of 
1930, 1945, and 1950. Total estimated cost for all 
requirements of local cooperation under terms of 
these unauthorized acts, including non-Federal 
contributions, was $1,949,700 (1939). River and 
Harbor Act of 1962, imposed conditions that local 
interests furnish lands and rights-of-way for 
construction and future maintenance and aids to 
navigation upon request of Chief of Engineers, 
including suitable spoil disposal areas, necessary 
retaining dikes, bulkheads, and embankments 
5-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
therefor or cost of such retaining works; hold the 
United States free from damages including 
damages to public or private oyster and clam 
grounds, and damages resulting from any change 
in natural course of James River, from blasting 
operations during removal of rock, or from 
changes in ground-water levels; hold the United 
States free from claims for costs resulting from 
provision and operation of bridges or ferries that 
may be required between mainland and any 
islands created by channel cutoffs; alter or 
relocate roads, bridges, waterfront structures, 
sewer, water supply, storm drainage, electric 
power, and other utility facilities; provide, 
maintain, and operate adequate terminal and 
transfer facilities to accommodate foreign and 
domestic commerce expected to develop from 
improved channel; and provide and maintain 
depths in berthing and mooring areas adjacent to 
terminals commensurate with related project 
depth. These conditions have not been complied 
with. 
Terminal Facilities. River's commerce at 
Richmond is handled at city-owned terminals, 
city wharf, Richmond dock, and at 16 privately 
owned wharves within or in immediate vicinity of 
Richmond Harbor. The city's upper terminal 
located on the north bank within the 
manufacturing section of Richmond provides for 
750 feet of concrete wharf and 80,000 square feet 
of warehouse and transit shed. The other terminal 
is located approximately 4 miles downstream 
from the Upper Terminal which provides about 
1250 feet of wharf and 2 concrete warehouses with 
about 190,000 square feet of floor space. This 
deepwater terminal at head of the 25-foot deep 
improved channel serves oceangoing vessels and 
larger ships engaged in coastwide trade. Below 
deepwater terminal the improvement is served by 
42 wharves. Richmond terminals and wharves, 
together with wharves between Richmond and 
the river's mouth, are adequate for river's 
commerce. 
Operations and results during fiscal 
year. Maintenance dredging, by contract, of 
Richmond Harbor, Deepwater Terminal and 
Shoals below Hopewell, Va., was completed 
February 12, 1975. There were removed 1,022,209 
cubic vards of credited material at a direct cost of 
$1 ,091.177. Buoy service, amounted to $3,030. 
Maintenance engineering and administration 
amounted to a cost of $96,631. 
Operation of the project including 
environmental surveys, hydrographic surveys, 
condition surveys and inspections amounted to 
$76,442. 
Condition at end of fiscal year. Construction of 
existing project commenced in 1884 and 
continued intermittently through various 
modifications until 25-foot and 18-foot channels 
were completed in November 1947. See Annual 
Report for 1965 for details on completion dates. 
Annual maintenance dredging is being done to 
maintain 18 and 25-foot controlling depths on the 
project. Work remaining to complete project 
consists of deepening channel from 25 to 35 feet 
from mouth to Richmond Deepwater Terminal 
and widening to 300 feet between Hopewell and 
Deepwater Terminal. Also remaining are 
construction of mooring basin at Hopewell and 
enlargement of turning basin at Richmond 
Deepwater Terminal. Uncompleted portions of 
the project are considered inactive. 
15. LYNNHAVEN INLET, VA. 
Location. On south shore of Chesapeake Bay, 
5 miles west of Cape Henry, and 10 miles east of 
Norfolk, Va. Inlet connects Lynnhaven Roads, a 
part of Chesapeake Bay, with a network of inland 
waters in northern half of city of Virginia Beach. 
(See Coast and Geodetic Survey Chart 1222.) 
Existing project. An entrance channel from 
Chesapeake Bay through Lynnhaven Inlet, 10 
feet deep and 150 feet wide; a mooring and 
turning basin, inside of Lynnhaven Inlet, 10 feet 
deep, 1,100 feet long, and 750 feet wide; a channel 
9 feet deep and 90 feet wide to extend from the 
mooring and turning basin into Broad Bay, via 
Iong Creek - Broad Bay Canal; and a channel 
through the Narrows, connecting Broad and 
I,inkhorn Bays, 6 feet deep and 90 feet wide. 
Depths are referred to mean low water. Mean 
range of tide in Lynnhaven Inlet is about 2 feet 
with extreme fluctuations of 1.5 feet below and 
9.5 feet above mean low water. Range in 
Lynnhaven Bay is a little more than 2 feet. In 
Broad and Linkhorn Bays, fluctuations in water 
level are caused by local winds. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with. For 
details see page 308 of Annual Report for 1965. 
Terminal facilities. Existing facilities are 
considered adequate. For details, see Annual 
Report for 1970. 
5-12

NORFOLK, VA., DISTRICT 
Operations and results during fiscal 
year. Engineering and design amounted to 
$1,715. Work on the final environmental impact 
statement progressed at a cost of $5,132. Survey 
investigations amounted to $3,299. Supervision 
and administration cost amounted to $1,989. 
Condition at end of fiscal year. Construction of 
existing project was commenced in July 1965 and 
completed in January 1966. Periodic maintenance 
dredging is being done at regular intervals to 
provide full project dimensions. 
16. NANSEMOND RIVER, VA. 
Location. This river, a tidal stream, rises in 
Nansemond County, Va., flows northerly 25 
miles, and empties into James River immediately 
above the mouth of the latter stream in Hampton 
Roads. (See U.S. Coast Geodetic Survey Chart 
No. 529.) 
Previous project. See Annual Report for 1935. 
Existing project. This provides for dredging a 
channel between the mouth and a point 0.45 mile 
above the highway bridge at Suffolk, a distance 
of about 18.66 miles, 12 feet deep and 100 feet 
wide, with a turning basin 200 feet square at 
Suffolk; and dredging a channel in the Western 
Branch between its mouth and Reids Ferry, a 
distance of about 2 miles, to a depth of 10 feet 
over a bottom width of 80 feet. Depths of 
channels are referred to mean low water. The 
mean tidal ranges under ordinary conditions for 
different parts of Nansemond River as follows: 
Suffolk bridge, 3.4 feet; Newmans Point, 2.8 feet. 
The extreme ranges under ordinary conditions at 
the same localities are as follows: Suffolk bridge, 
2.8 feet to 4 feet; Newmans Point, 2.3 feet to 3.3 
feet. 
The cost for new work, for the completed 
project was $137,477, exclusive of the amount 
expended on previous projects. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are two wooden 
wharves and about 950 feet of wooden bulkhead 
at Suffolk, Va. There is also one wooden wharf 
and about 550 feet of wooden bulkhead located 
about 9 miles downstream from Suffolk. These 
facilities are privately owned and are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Engineering and design cost amounted to 
$2.855. Work on the environmental assessment 
was completed at a cost of $3,352. Supervision 
and administration cost amounted to $1,222. 
Condition at end of fiscal year. Construction of 
the existing project was completed in February 
1932. Periodic maintenance is needed to restore 
project dimensions on the Western Branch 
Channel, which is shoaled to a usable depth of 
about 4-feet. 
17. NEWPORT NEWS CREEK, VA. 
Location. Newport News Creek, Va., is located 
on the southeastern end of the peninsula between 
the James and York Rivers and within the 
corporate limits of the city of Newport News. (See 
U.S. Coast and Geodetic Survey Charts Nos. 400 
and 1222.) 
Existing project. This provides for a channel 
12 feet deep at mean low water with widths 
varying from 200 to 60 feet from deepwater in 
Hampton Roads to and through the municipal 
boat harbor entrance, thence 12 feet deep at mean 
low water and 150 feet wide to and including a 
turning basin and anchorage of the same depth 
220 feet wide and 400 feet long in the upper end of 
the harbor. The mean tidal range is 2.6 feet and 
the extreme 3.1 feet. The extremes of irregular 
fluctuations due to combined wind and tides 
referred to mean low water, are minus 2 feet and 
plus 9.5 feet. 
The cost for new work, for the completed 
project was $135,600. 
The existing project was adopted by the River 
and Harbor Act of July 24, 1946 (H. Doc. 559, 
79th Cong., 2d sess.). The latest published map is 
in the project document. 
Local cooperation. Fully complied with as to 
initial construction. Local interests are required 
to simultaneously dredge certain areas adjacent 
to the project during periods of future 
maintenance. 
Terminal facilities. There are 4,210 linear feet 
of steel-and-wood bulkhead, and two marine 
railways, which can accommodate vessels up to 
85 feet in length, on Newport News Creek. The 
city of Newport News maintains 400 feet of 
bulkhead open to the public without charge and 
operates a pleasure-boat marina with 18 finger 
piers at which a nominal wharfage fee is charged. 
The remaining facilities are privately owned or 
are leased by the city to private firms. These 
5-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Engineering and design amounted to 
$1,619, with a final environmental assessment 
being completed. 
Supervision and administration cost amounted 
to $319. 
Condition at end of fiscal year. Construction of 
the existing project was commenced in January 
1948, and completed in April 1948. Periodic 
maintenance will be performed to maintain 
project dimensions. 
18. SUPERVISION OF HARBOR 
OF HAMPTON ROADS, VA. 
(PREVENTION OF 
OBSTRUCTIVE AND 
INJURIOUS DEPOSITS) 
Laws enacted for preservation of the Harbor of 
Hamtpon Roads, Va., its adjacent and tributary 
waters, so much of Chesapeake and its tributaries 
as lies within the State of Virginia, and so much 
of the Atlantic Ocean and its tributaries as lies 
within the jurisdiction of the United States, 
within or to the east of the State of Virginia, are 
administered by the Supervisor of the Harbor of 
Hampton Roads. Laws relating to the 
supervision of the Harbor of Hampton Roads are: 
Supervisory Harbors Act of 1888, Rivers and 
Harbors Act of 1899, Rivers and Harbors Act of 
1902, Rivers and Harbors Act of 1905, Rivers and 
Harbors Act of 1950, Federal Water Pollution 
Control Act Amendments of 1972, Marine 
Protection, Research and Sanctuaries Act of 
1972, and the Coastal Zone Management Act of 
1972. 
Supervision was exercised by means of two 
patrol vessels (389 patrols, 3112 man-hours) and 
three to four patrol cars (963 patrols, 7704 manhours). 
Commercial aircraft and U.S. Coast 
Guard helicopters were utilized for aerial 
photographic reconnaissance (12 patrols, 50 manhours). 
Patrols were maintained to detect illegal 
deposits into navigable waters and to make 
scheduled inspections of proposed and current 
projects dealing with dredging, filling and 
construction in navigable waters. An educational 
program continued with a view to preventing 
violations of applicable Federal laws. This 
program was effected through press releases, 
public notices, public talks and personal 
interviews with interested agencies, committees 
and private industries. Agreements were 
continued with various federal, state and local 
agencies having related or similar responsibilities 
and functions to obtain maximum results with 
minimum costs by eliminating duplication of 
effort. 
Summary of legal action during fiscal year: 
Disposition of legal actions to end of fiscal year 
for violations of federal statutes is as follows: 90 
cases referred for litigation; 88 cases closed; and 7 
cases pending. 
19. TASKINAS CREEK, VA. 
Location. On south shore of York River in 
James City County about 24.5 miles above the 
mouth. (See Coast and Geodetic Survey Chart 
495/496.) 
Existing project. Provides for an entrance 
channel 80 feet wide and 6 feet deep from that 
depth in York River to a point just downstream of 
the proposed marina facilities within the creek, a 
distance of about 5,300 feet. Estimated cost 
(1972) for new work is $180,000, including 
$90,000 non-Federal. 
Project also provides for deferred construction 
of a jetty from deep water in York River to the 
mouth of Taskinas Creek to be provided in the 
event that experience shows that the average 
annual cost of maintenance dredging exceeds the 
annual charges of the jetty. Estimated cost (1969) 
of construction of the jetty is $600,000, including 
$300,000 non-Federal. 
Plane of reference is mean low water. Mean 
range of tide is 2.9 feet. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. For details of local 
cooperation, see Annual Report for 1971. 
The Department of Conservation and 
Economic Development, Commonwealth of 
Virginia, indicated in March 1969 that assurance 
of items of local cooperation would be considered 
when development of the proposed York River 
State Park (Taskinas) is begun. 
Terminal facilities. There are no existing 
facilities. York River State Park (Taskinas) will 
include facilities described under local 
cooperation. These facilities will be adequate, 
when developed. 
5-14

NORFOLK, VA., DISTRICT 
Operations and results during fiscal 
year. None. 
Condition at end of fiscal year. Construction 
has not begun. 
20. WISHART POINT CHANNEL, 
VA. 
Location. In Accomack County, about 5 miles 
southeast of Chincoteague Island and 3.5 miles 
east of the town of Temperanceville, near the 
Waterway on the Coast of Virginia. (See Coast 
and Geodetic Survey Chart 1221.) 
Existing project. Provides for a channel 6 feet 
deep and 60 feet wide from the Waterway on the 
Coast of Virginia at the Four Mouths, through 
Ballast Narrows and across Powells Bay to 
Wishart Point, about 2 miles in length. The plane 
of reference is mean low water. Mean Range of 
tide is 2.6 feet. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. For 
details, see page 5-13 of Annual Report for 1971. 
Terminal facilities. There are no terminal 
facilities at Wishart Point other than a boat club 
owned and operated by local waterman and a 
launching ramp and parking area constructed by 
the State and open to the public. With provision 
of the public landing required of local interests, 
facilities are adequate for existing and 
prospective traffic. 
Operations and results during fiscal 
year. Engineering and design cost including 
work on the environmental impact statement and 
local cooperation amounted to $4,159. 
Supervision and administration costs amounted 
to $819. 
Condition at end of fiscal year. Construction of 
the entire project was completed in December 
1971 at a total Federal cost to June 30, 1973 of 
.8118,762 and $30,265 contributed by local 
interests. 
21. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 5-D at end of chapter.) 
22. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 5-E at end of chapter.) 
23. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, 
Public Law 645. 86th Congress 
(Preauthorization). 
Four reconnaissance reports, Jarvis Creek, 
Northumberland County, Onancock River, 
Accomack County, Powhatan Creek, James City 
County, and Tangier Channel and Basin, 
Accomack County, Virginia were in progress at 
the end of the fiscal year. 
Beach Erosion Control 
24. VIRGINIA BEACH, VA. 
Location. On Atlantic seaboard, 22 miles 
north of Virginia-North Carolina State line, 3.5 
miles south of Cape Henry, and 19 miles east of 
Norfolk, Va. (See Coast and Geodetic Survey 
Chart 1227.) 
Existing project. Federal participation in 
restoration and protection of shore of Virginia 
Beach between Rudee Inlet and 49th Street by 
artifical placement of sand to provide a minimum 
beach width of 100 feet at elevation 7 feet above 
mean low water, and maintenance of such beach 
by periodic replenishment of losses to insure 
continuous protection; including construction of a 
groin system to be undertaken at such times as 
estimated annual charges therewith would be less 
than the annual cost of beach replenishment 
alone. The United States shall participate in the 
first cost of the project to the full extent of its 
proportionate share of cost as a landowner, plus 
one third total first cost of restoring and 
protecting all publicly-owned sections of the 
shore. The 1962 modification provided that the 
United States shall further participate in periodic 
beach nourishment of the beach in the amount of 
one third the costs for 25 years from date of 
commencement of operations in placing an initial 
quantity of nourishment material equal to 
deficiency in the design beach at that time. 
Section 103 of the 1962 River and Harbor Act 
increased Federal participation to one-half of the 
cost incurred after October 23, 1962. Estimated 
Federal cost (1975) is $4,480,000. Estimated cost 
to local interests is $4,490,000. Construction of 
5-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
the groin system is not included in above 
estimate. The 1962 estimate for this work was 
$549,000 Federal cost and $531,000 cost to local 
interests. (See Table 5-B for Authorized 
Legislation.) 
Local cooperation. River and Harbor Act of 
September 3, 1954, imposed conditions that local 
interests (a) adopt plan of restoration and 
protection; (b) submit for approval by the Chief of 
Engineers, before commencement of work, 
detailed plans and specifications for the project 
and also arrangements for prosecuting the work; 
(c) assure maintenance of protective and 
improvement measurements during their useful 
life as may be required to serve their intended 
purpose; (d) provide all lands and rights-of-way; 
hold the United States free from damages; (e) 
assure that water pollution that would endanger 
the health of bathers will not be permitted; and (f) 
assure continued public ownership of the shore 
upon which the amount of Federal participation is 
based, and its administration for public use only. 
The modification of the project by the River 
and Harbor Act of October 23, 1962, continued 
the terms of local cooperation specified in the 
original project. The conditions of local 
cooperation have been complied with in the initial 
beach restoration and in the nourishment 
program to date. Conditions pertaining to 
construction of groins have not been complied 
with. A formal agreement with the cooperating 
agency (City of Virginia Beach and the Virginia 
Beach Erosion Commission) for the initial beach 
restoration was entered into on October 19, 1955. 
An amendment to the original agreement, 
covering periodic nourishment, was entered into 
on November 1, 1963. 
Operations and results during fiscal year. New 
work: Sand was stockpiled at Fort Story at a 
Federal cost of $228,809 and $153,640 non- 
Federal cost. 
Condition at end of fiscal year. Beach 
restoration by local interests was commenced in 
June 1952 and completed in August 1953. 
Construction of groins has been deferred 
indefinitely. Local interests acquired their own 
dredging plant and borrow areas and replenished 
the beach until 1975 when the borrow areas could 
not be extended. During fiscal year 1975 a 3-year 
supply of beach nourishment material was 
stockpiled at nearby Fort Story to be transported 
to the beach by local interests. 
25. BEACH EROSION CONTROL 
UNDER SPECIAL 
AUTHORIZATION 
Beach Erosion Control Activities Pursuant to 
Section 103, Public Law 645, 86th Congress 
(Preauthorization) 
Work was accomplished on two planning 
reports as follow: 
(a) Anderson Park, Newport News, 
Virginia, a negative detailed project report was 
completed when the city of Newport News could 
not furnish the necessary cash contributions. 
(b) Hampton Institute, Hampton, Virginia, 
a detailed project report was completed. 
Flood Control 
26. GATHRIGHT LAKE, JAMES 
RIVER BASIN, VA. 
Location. Site of proposed Gathright Dam is 
on Jackson River, a tributary of James River, at 
mile 43.4 in Alleghany County. Gathright Dam 
site is in reach of Jackson River known as the 
Gorge, about 19 miles upstream from Covington, 
Virginia. At the elevation of the top of the 
conservation pool, Gathright Reservoir will 
extend upstream about 9 miles. (See Falling 
Spring and Mountain Grove, Va.-W. Va., 
quadrangles of Geological Survey.) 
Existing project. The Gathright Dam consists 
of a 1,172-foot long, rolled rock fill dam with an 
impervious core with the top at elevation 1684.5; 
outlet works consisting of a concrete intake 
structure located in the right bank 500 feet 
upstream from the axis of the dam, a 1,075-foot 
long outlet tunnel through the right abutment 
and a stilling basin; and a 2,450-foot long, fixed 
crest emergency spillway excavated in a low 
saddle in the divide at Fortney Branch about 2.5 
miles south of the dam. Discharges through the 
outlet tunnel will be controlled by slide gates 
located in the intake structure. The reservoir at 
minimum conservation pool elevation 1554 will 
have an area of 1,780 acres. About 60,700 acrefeet 
of storage between elevation 1554 and 
maximum conservation pool elevation 1582 will 
be provided for water quality control. The 
reservoir area at elevation 1582 will be 2,530 
acres. A total of 302,300 acre-feet of storage 
5-16

NORFOLK, VA., DISTRICT 
between elevation 1582 and the spillway crest 
(elevation 1663.5) will be reserved for flood 
control. At the spillway crest the reservoir will 
have an area of 4,540 acres. Estimated Federal 
cost (1975 is $61,670,000 for construction and 
$6,530,000 for lands and damages, including 
highway, cemetery and utility relocation, a total 
of $68,200,000 for new work. (See Table 5-B for 
Authorizing Legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. Real 
estate activities and aquisition continued at a 
direct cost of $30,392. A major contract for the 
embankment and spillway, awarded in April, 
1973 was continued during the fiscal year at a 
direct cost of $9,718,868. In July 1974 a letter 
contract was awarded to complete the unfinished 
portion of the Outlet Works. This contract was 86 
percent complete at the end of the fiscal year at a 
direct cost of $1,850,000. Hired labor and 
contract costs for relocations and reservoirs 
amounted to $206,183. Contract cost for roads 
and recreation amounted to $279,516. 
Engineering and design continued at a direct 
cost of $158,192. Miscellaneous hired labor work, 
litigation, and construction facilities amounted to 
a direct cost of $7,433. Supervision and 
administration cost of the project amounted to 
$352,923. Costs for lands and damages, surveys 
and layouts, real estate administration activities 
amounted to $88,778. 
Conditions at end of fiscal year. The overall 
project is about 58 percent complete. 
Construction is continuing. 
27. BUENA VISTA, VA. 
Location. The city of Buena Vista is on the left 
of the Maury River, 40 miles below the river's 
origin and about 11 miles upstream of its juncture 
with the main stem of the James River at the 
community of Glasgow. The Maury River Basin 
above Buena Vista contains a drainage area of 
some 649 square miles. The Maury River falls an 
average of 16.6 feet per mile of stream. The 
nearest city to Buena Vista is Lexington, located 
about 8 miles upstream. 
Existing projects. The recommended plan of 
improvement provides for a combination earth 
levee and floodwall along the left bank of the river 
for nearly the full length of the city. The main 
features of the plan are (a) an 11,700-foot 
combination riprapped levee and floodwall, 
extending from high ground just upstream of 
Universal Match Company to high ground 
downstream from General Cable Corporation at a 
point near the Norfolk and Western Railway 
Bridge across the Maury River; (b) an improved 
channel in the Maury River, provided by 
straightening and widening the existing channel 
to a bottom width of 200 feet, for the purpose of 
eliminating a backwater effect upstream of the 
floodwall, which would otherwise increase natural 
flood damage to the property located in that area; 
and, (c) diversion of internal runoff from surface 
sources and from Indian Gap Run and Pedlar Gap 
Run into an abandoned canal bed, appropriately 
improved for a distance of 5,700 feet downstream 
and thence discharged by gravity, into the Maury 
River. 
Local cooperation. Requirements are as 
follows: 
a. Provide, without cost to the United 
States, all lands, easements, rights-of-way, and 
suitable spoil disposal areas necessary for 
construction of the project. 
b. Provide, without cost to the United 
States, all relocations of buildings and utilities, 
highway bridges, sewers, related and special 
facilities, and local betterments, except as 
otherwise warranted for special reasons. 
c. Hold and save the United States free from 
damage due to the construction works. 
d. Maintain and operate all works after 
completion in accordance with regulations 
prescribed by the Secretary of the Army. 
e. Control future flood damages and 
exposure to flood hazards by enforcement of 
ordinances which will permit only uses of the 
flood plain which are consistent with the flood 
hazard. This will include areas outside of the 
proposed protection to be sure other flood 
problems are not allowed to develop. 
f. Provide assurances that encroachment on 
ponding areas inside the wall, or decrease in their 
storage capacity, will not be permitted. 
City Council of Buena Vista, by resolution 
adopted 27 Apr 72, has committed itself to the 
local cooperation. 
Operations and results during fiscal 
year. Engineering and design of Phase I of the 
General Design Memorandum was initiated at a 
cost of $92,216. 
Condition at end of fiscal 
year. Preconstruction planning is continuing. 
5-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
28. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 5-F at end of chapter.) 
29. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended 
(preauthorization). 
a. The negative reconnaissance report, 
Alleghany County High School, Alleghany 
County, Virginia was completed. 
b. The detailed progress report, Covington, 
Alleghany County, Virginia was in progress at 
the end of the fiscal year. 
c. The negative reconnaissance report, 
Eagle Rock and Buchanan, Botetourt County, 
Virginia was completed. 
d. The detailed progress report, Broad Rock 
Creek, Richmond, Virginia was in progress at the 
end of the fiscal year. 
e. The detailed progress report, Reedy 
Creek, Richmond, Virginia was in progress at the 
end of the fiscal year. 
Flood control activities purusant to section 
208, under the 1954 Flood Control Act, Public 
Law 780, 83d Congress, as amended 
(preauthorization). 
a. The reconnaissance report, Gordonsville, 
Louisa County, Virginia was initiated in January 
1975 and in progress at the end of the fiscal year. 
Emergency flood control activities--repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation). 
Fiscal year costs were $39,881 for advance 
preparation, $10,791 for emergency operations. 
Multi-Purpose Projects Including Power 
30. SALEM CHURCH LAKE, VA. 
Location. The Salem Church multiple purpose 
reservoir, to be located on the Rappahannock and 
Rapidan Rivers in Spotsylvania, Stafford, 
Orange, Culpeper, and Fauquier Counties, Va., 
would be created by a concrete gravity dam on 
the Rappahannock River 5.6 miles above 
Fredericksburg, Va., and 113 miles above the 
mouth. At maximum power pool, the lake will 
extend about 26 miles upstream on the 
Rappahannock River and 24 miles on the Rapidan 
River. (See Geological Survey Quadrangles 
"Fredericksburg," "Salem Church," "Storck," 
"Midland," "Richardsville," "Chancellorsville," 
"Remington," "Germanna Bridge," "Mine 
Run," "Culpeper," and "Unionville,") A 
reregulating dam, Fredericksburg Dam, included 
in the project, will be located 2,8 miles 
downstream from the Salem Church Dam. 
Previous projects. For details, see page 264 of 
Annual Report for 1954. 
Existing project. For details of authorized 
project, see Annual Report of 1972. (See Table 5- 
B for Authorizing Legislation.) 
Local cooperation. For details, see Annual 
Report of 1974. 
Operations and results during fiscal 
year. During FY 1975 the project was 
determined to be no longer economically feasible. 
Recommendations were made to terminate 
further planning studies. 
Condition at end of fiscal year. Project has 
been reclassified from active to inactive. 
General Investigation 
31. SURVEYS 
Total cost for surveys during fiscal year was 
$261,952, of which $88,869 was for navigation 
studies, $157,886 for flood control studies. $9,201 
for inventory of dams and $5,996 for 
deauthorization reviews. 
32. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year cost of Flood Plain Management 
Services was $202,150. During the fiscal year, 
work was completed on seven reports as follows: 
Crump Creek, Hanover Co., Va.; Kingsland 
Creek, Chesterfield Co., Va.; Nottoway 
River- Courtland, Southampton Co., Va.; 
Nottoway River- Sussex, Sussex Co., Va.; 
Oldtown Creek, Chesterfield Co., Va.; Pamunkey 
River, Hanover Co.; Va.; Swift Creek and 
tributaries, Chesterfield Co.; Va. At the end of 
the fiscal year, work was in progress on six other 
reports. 
33. RESEARCH AND 
DEVELOPMENT 
Fiscal year cost was $11,281 for hydrological 
studies. 
5-18

NORFOLK, VA., DISTRICT 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total 
Section Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 1975 
Aberdeen Creek, Va. 
(Regular Funds) 
(Contributed 
Funds) 
Atlantic Intracoastal 
Waterway, between 
Norfolk, Va. and the 
St. Johns River, 
Fla. (Norfolk 
District) 
(Regular Funds) 
Aquatic Plant 
Control, Va. 
(Regular Funds) 
Baltimore Harbor 
Channels (Norfolk 
District) 
(Regular Funds) 
Blackwater River, 
Va. (Regular 
Funds) 
Chincoteague Harbor 
of Refuge, Va. 
(Regular Funds) 
(Contributed 
Funds) 
Chowan River, 
N.C. (Regular 
Funds) 
Deep Creek 
(Newport News) 
Va. (Regular 
Funds) 
(Contributed 
Funds) 
Delaware Bay- 
Chesapeake Bay 
Waterway 
Delaware, Maryland, 
Virginia (Virginia 
Portion) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
Recreation 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5,199 
5,199 
3,389 
3,389 
- - 109,643 
- - 109,643 
75,000 63,971 163,297 
13,690 126,016 163,297 
- - 11,300 
- - 11,300 
7,500 - 7,500 
- 7,500 7,500 
- - 3,688,372(1) 
- - 3,688,372(1) 
1,154,648 1,028,789 25,190,358(2) 
1,230,667 1,094,850 24,142,215(2) 
- - 479,947 
- - 479,947 
- 28,000 28,000 
1,322,200 1,223,644 
1,103,006 1,382,424 
11,000 - 
- - 25,000 30,000 85,000 
2,062 814 16,858 10,390 48,241 
- - - - 8,015,070(3) 
- - - - 8,015,070(3) 
489,408 507,184 117,749 10,500 5,127,290(3) 
477,948 518,644 117,749 10,326 5,127,116(3) 
- 5,000 338,102 (-)984 342,118(4) 
- 827 55,256 286,035 342,118(4) 
- - - - 138,704 
- - - - 138,704 
- - - - 49,396 
- - - - 49,396 
- - 1,368 7,309 8,695(5) 
- - 1,386 7,309 8,695(5) 
- - - - 2,140 
- - - - 2,140 
- 5,000 104,297 (-)2,077 10 7,220 
- 557 22,314 84,349 107,220 
- - - - 202,622 
- - - - 202,622 
1,117 4,253 7,167 9,547 240,716 
1,117 4,253 7,167 9,547 240,716 
- - - - 36,000 
- - - - 36,000 
- - - - 850,498 
- - - - 850,498 
321,078 564,585 810,870 235,425 3,767,004 
359,398 447,219 915,511 248,149 3,767,004 
5-19 
2. 
9.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT 
See Total 
Section Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 1975 
10. Hampton Roads Maint. 
11. 
and the Harbors 
of Norfolk and 
Newport News, Va.- 
Collection and 
Removal of Drift 
(Regular Funds) 
Hampton Institute, 
Va. (Regular 
Funds) 
(Contributed 
Funds) 
Hampton Roads, 
Va. (Regular 
Funds) 
(Contributed 
Funds) 
Hoskins Creek, 
Va. (Regular 
Funds) 
(Contributed 
Funds) 
James River, Va. 
(Regular Funds) 
(Contributed 
Funds) 
Lynnhaven Inlet 
(Regular Funds) 
(Contributed 
Funds) 
Nansemond River, 
Va. (Regular 
Funds) 
Newport News 
Creek, Va. 
(Regular Funds) 
Supervision of 
Harbor of Hampton 
Roads, Va. 
(Regular Funds) 
143,000 
70,986 
1,487,300 
4,221,748 
1,417,403 
1,329,107 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
559,000 
88,724 
23,500 
3,816 
62,567 
42,404 
2,450,317 
2,517,514 
1,359,302 
1,219,245 
2,773 
13,773 
3173 
85,500 
143,756 
1c 
40( 
1,64 
1,31 
9,058 
0,000 
1,781 
9,315 3,499, 
9,028 3,808, 
288,815 
399,685 
1,] 
1, 
31,739 
148,028 
4,600 
228,000 
236,252 
207,000 
207,036 
76,000 1,169,199 
76,040 1,169,186 
55,000 78,500 
53,212 76,086 
181,200 181,200 
91,337 91,337 
(-)1,741 54,813,962(6) 
629,600 54,813,962(6) 
214(14) 37,261,198(7) 
019(14) 37,186,539(7) 
- 23,936 
- 23,936 
- 44,100 
- 44,100 
11,543 441,412 
11,543 441,412 
- 500 
- 500 
- 7,639,909(8) 
- 7,639,909(8) 
192,722 15,072,405 
267,280 15,067,777 
26,693 120,956 
26,693 120,956 
- 334,725 
- 334,725 
12,135 560,956(9) 
12,135 560,956(9) 
- 91,647 
- 91,647 
- 15,700 
- 15,700 
- 167,477(10) 
- 167,477(10) 
7,429 257,476(11) 
7,429 257,476(11) 
- 135,600 
- 135,600 
1,938 90,545(12) 
1,938 90,545(12) 
158,080 2,792,528 
158,065 2,792,509 
5-20 
91,723 
91,723 
30,669 
62,141 
463,578 
516,309 
11,731 
11,731 
135,800 
19,512 
4,600 
227,400 
221,060 
12. 
13. 
14. 
15. 
16. 
17. 
18.

NORFOLK, VA., DISTRICT 
TABLE 5-A (Cont.) COST AND FINANCIAL STATEMENT 
See Total 
Section Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 1975 
19. Taskinas Creek, New Work 
Va. (Regular Approp. - 1,795 - - 7,857 
Funds) Cost - 219 1,384 - 7,479 
20. Wishart Point New Work 
Channel, Va. Approp. 50,000 205 - - 118,762 
(Regular Funds) Cost 100,461 7,987 - - 118,762 
Maint. 
Approp. - 6,828 97 4,978 11,901 
Cost - 6,828 97 4,978 11,901 
(Contributed New Work 
Funds) Approp. 5,000 - - - 30,625 
Cost 30,625 - - - 30,625 
24. Virginia Beach, New Work 
Va. (Regular Approp. 111,573 115,420 477,700 232,502 1,477,104 
Funds) Cost 167,950 115,364 477,565 228,809 1,473,411 
Maint. 
Approp. - - - - 20,272 
Cost - - - - 20,272 
(Contributed New Work 
Funds) Approp. - - - 210,000 210,000 
Cost - - - 153,640 153,640 
26. Gathright Lake, New Work 
Va. (Regular Approp. 5,209,527 9,333,800 1,791,900 9,402,300 35,533,527 
Funds) Cost 3,911,791 4,832,127 5,009,557 12,661,892 35,352,802 
27. Buena Vista, Va. New Work 
(Regular Funds) Approp. - - - 250,000 250,000 
Cost - - - 92,216 92,216 
30. Salem Church Lake, New Work 
(Regular Funds) Approp. 495,631 137,300 650,000 (-)265,000 1,896,716(13) 
Cost 626,930 210,262 298,312 179,262 1,884,736(13) 
(1) Includes $292,096 for previous projects. 
(2) Includes $52,804 for previous projects. 
(3) Costs prior to fiscal year 1942 are included in the project 
"Baltimore Harbor and Channels, Md". (Baltimore District). 
Costs listed are for York Spit Channel, Va., Rappahannock 
Shoal Channel, Va., and Cape Henry Channel, Va. 
(4) Includes $14,000 for previous projects. 
(5) In addition, $172 was expended for condition surveys. 
(6) Includes $3,120,313 for previous projects. 
(7) Includes $84,539 for previous projects. 
(8) Includes $763,000 for previous projects. 
(9) Includes $14,796 for condition surveys. 
(10) Includes $30,000 for New Work for previous projects. 
(11) Includes condition surveys. 
(12) Includes $192 for condition surveys. 
(13) Includes $144,785 for previous projects. 
(14) Excludes $1,067,000 transferred to plant repair account. 
5-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 5-B AUTHORIZING LEGISLATION 
Act Work Authorized Documents 
July 14, 1960 (Sec. 107) 
Mar. 3, 1899 
July 25, 1912 
July 25, 1912 
Mar. 3, 1925 
July 3, 1930 
June 26, 1934 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
Fuly 3, 1958 
Dec. 31, 1970 
Mar. 3, 1905 
Mar. 4, 1913 
July 3, 1930 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
Mar. 2, 1907 
Mar. 2, 1945 
July 14, 1960 (Sec. 107) 
Mar. 2, 1945 
Aug. 26, 1937 
June 30, 1948 
ABERDEEN CREEK, VA. (See Section 1 of Text) 
Existing project. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA. AND ST. JOHNS RIVER, FLA. 
(NORFOLK DISTRICT) (See Section 2 of Test) 
Existing project dimensions and original route, waterway 
from Norfolk, Va., to sounds of North Carolina. 
Original route of Norfolk-Beaufort Inlet section. 
Purchase of Albemarle & Chesapeake Co. Canal. 
Purchase of Lake Drummond Canal (Dismal Swamp Canal). 
Construct a tidal lock at Great Bridge at a cost not to 
exceed $500,000. 
Operating and care of works of improvement provided for 
with funds from War Department appropriations for rivers 
and harbors. 
Construct dikes for protection of canal property against 
floodtides. 
BALTIMORE HARBOR AND CHANNELS (NORFOLK 
DISTRICT) (See Section 4 of Text) 
CAPE HENRY CHANNEL, VA. (See Section 4A of Text) 
A channel 42 feet deep and 1,000 feet wide. 
Channel depth increased to 50 feet. 
RAPPAHANNOCK SHOAL CHANNEL, VA. (See Section 4B 
of Text) 
A channel 42 feet deep and 800 feet wide. 
Channel width increased to 1,000 feet and depth increased 
to 50 feet. 
YORK SPIT CHANNEL, VA. (See Section 4C of Text) 
A channel 35 feet deep and 600 feet wide. 
Channel width increased to 1,000 feet. 
Channel depth increased to 37 feet. 
Channel depth increased to 39 feet. 
Channel depth increased to 42 feet. 
Channel depth increased to 50 feet. 
BLACKWATER RIVER, VA. (See Section 5 of Text) 
Clearing river between Franklin, Va., and the mouth, 
to ease navigation of 7-foot boats. 
A channel 12 feet deep and generally 80 feet wide, 
including cut-offs of like dimensions at Cherry Grove 
and Georges Bend and a turning basin of 32 acres at 
Franklin, Va. 
CHINCOTEAGUE HARBOR OF REFUGE, VA. 
(See Section 6 of Text) 
Existing project. 
CHOWAN RIVER, VA. (See Section 7 of Text) 
A channel 12 feet deep and 80 feet wide, including a 
cut-off through a sharp bend near Riddicksville, N.C. 
DEEP CREEK, NEWPORT NEWS, VA. (See Section 
8 of Text) 
Channel 6 feet deep from James River to Hicks Landing 
with widths of 80 feet and 50 feet; a turning basin 6 feet 
deep, 100 feet wide and 105 feet long; an anchorage 
basin 6 feet deep and 6.4 acres in area; and a timber 
jetty 800 feet long on the north side of the anchorage. 
Existing project dimensions and elimination of timber jetty 
DELAWARE BAY - CHESAPEAKE BAY WATERWAY 
DELAWARE, MARYLAND, VIRGINIA 
(Virginia Portion) 
FORMERLY WATERWAY ON THE 
COAST OF VIRGINIA (See Section 19 of Text) 
Approved in 1962. 
H. Doc. 317, 54th Cong., 1st sess. 
and Annual Report, 1896, 
H. Doc. 131, 55th Cong., 3d 
sess., and Annual Report, 
1899, p. 1485. 
H. Doc. 391, 62d Cong., 2d sess. 
H.Doc 589, 62d Cong., 2d sess. 
Rivers & Harbors Committee Doc. 
5, 67th Cong., 2d sess. 
S. Doc. 23, 71st Cong., 1st sess. (1) 
H. Doc. 117, 76th Cong., 1st sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers' report, 
Sept. 21, 1970. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers' report, 
Sept. 21, 1970. 
H. Doc. 186, 57th Cong., 2d sess. 
H. Doc. 1190, 62d Cong., 3d sess. 
H. Doc. 29, 71st Cong., lst sess. 
H. Doc. 741, 79th Cong., 2d sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers' report, 
Sept. 21, 1970. 
H. Doc. 177, 59th Cong., 1st sess. 
H. Doc. 101, 76th Cong., 
1st sess.(1) 
Approved in 1962. 
H. Doc. 101, 76th Cong., 
1st sess.(1) 
H. Doc. 76, 74th Cong., 2d sess. 
H. Doc. 601, 80th Cong. 2d sess. 
-2

NORFOLK, VA., DISTRICT 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
Act Work Authorized Documents 
June 25, 1910 
Mar. 2, 1945 
Oct. 27, 1965 (Sec. 201) 
July 14, 1960 (Sec. 107) 
May 17, 1950 
Oct. 23, 1962 (Sec. 103) 
June 25, 1910 
Aug. 8, 1917 
Jan. 21, 1927 
Oct. 27, 1965 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Sept. 3, 1954 
Oct. 27, 1965 
June 25, 1910 
Aug. 8, 1917 
Mar. 3, 1925 
Aug. 30, 1935 
June 30, 1948 
Oct. 27, 1965 
July 5, 1884 
Mar. 2, 1907 
Mar. 2, 1907 
Mar. 3, 1925 
July 3, 1930 
Mar. 2, 1945 
Mar. 4, 1913 
July 3, 1930 
Existing project adopted. 
Project modified. 
Project widened to 100 feet, partially relocated, 
and incorporated in Delaware Bay-Chesapeake Bay 
Waterway in Delaware-Maryland-Virginia. 
CHINCOTEAGUE INLET ENTRANCE CHANNEL 
HAMPTON ROADS AND HARBORS OF NORFOLK AND 
NEWPORT NEWS, VA. COLLECTION AND 
REMOVAL OF DRIFT (See Section 10 of Text) 
Existing project. 
HAMPTON INSTITUTE, VA. (See Section 
10 of Text) 
Existing Project 
HAMPTON ROADS, VA. (See Section 12 of Text) 
CHANNEL TO NEWPORT NEWS, VA. (See Section 
12A of Text) 
Channel 35 feet deep and 400 feet wide. 
Channel 35 feet deep and 600 feet wide. 
Channel 40 feet deep and 600 feet wide. 
Existing project dimensions. 
NORFOLK HARBOR, VA. (See Section 12B of Text) 
Hampton Roads and Elizabeth River 
A channel 30 feet deep to navy yard. 
Depth of 35 feet to navy yard. 
Depth of 40 feet and width of 750 feet to mouth of 
Southern Branch. 
Widen 40-foot channel to 1,500 feet from 40-foot 
contour in Hampton Roads to a point just south of 
Norfolk International Terminal. 
45 feet deep, Ft. Wool to Lambert Point, 800 feet wide 
Norfolk International Terminal to Lambert Point. 
Southern Branch 
For a channel with a depth of 22 and 25 feet. 
Depth of 40 feet and width of 450 feet from mouth to 
Belt Line R. R. Bridge.. 
Channel 30 feet deep and 375 feet wide to Virginia Ry. 
bridge thence 25 feet deep and generally 200 feet wide 
to Norfolk & Western Ry. bridge. 
Depth of 25 feet and width of 200 feet from Norfolk & 
Western Ry. bridge to a point 2,500 feet above with 
a turning basin 500 feet square. 
Approach and turning area 40 ft. deep and a maximum 
width of 830 feet opposite Norfolk Naval Shipyard thence 
a channel 35 feet deep and 375 and 250 feet wide to a point 
1,900 feet above Norfolk & Western Ry. bridge and a turning 
basin 35 feet deep and 600 by 600 feet at upstream end. 
40 feet deep Belt Line bridge to Old Virginia bridge, 
35-foot deep turning basin opposite St. Julians 
Creek. 
Eastern Branch 
Improvement of Eastern Branch. 
Width of 500 feet and depth of 25 and 22 feet. 
Removal of shoals at mouth. 
Depth of 25 feet and width of 200 feet from Norfolk & 
Western Ry, bridge to Virginia Ry, bridge. 
30-foot channel to a point opposite terminal of 
Imperial Tobacco Co. in Berkley. 
Depth of 25 feet and width of 300 feet from Norfolk & 
Western Ry. bridge to Campostella bridge. 
Western Branch 
Channel 24 feet deep and 300 & 400 feet wide to West 
Norfolk highway bridge. 
For 18-foot channel to a point about 3,000 feet above 
West Norfolk highway bridge. 
H. Doc. 957, 60th Cong., 1st sess. 
H. Doc. 268, 76th Cong., 1st sess. 
Approved in 1970 
Approved in 1972. 
Specified in act. 
Approved in 1974. 
H. Doc. 550, 61st Cong., 2d sess. 
H. Doc. 605, 63d Cong., 2d sess. 
H. Doc. 486, 67th Cong., 4th sess. 
H. Doc. 143 & 187, 89th Cong., 
1st sess.(1) 
H. Doc. 381, 59th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 140, 65th Cong., 1st sess. 
S. Doc. 122, 83d Cong., 2d sess. 
H. Doc. 187, 89th Cong., 1st sess.(1) 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 140, 65th Cong., 1st sess. 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 182, 73d Cong., 2d sess.(3) 
H. Doc. 545, 80th Cong., 
2d sess.(1) 
H. Doc. 187, 89th Cong., 1st sess. 
Annual Report 1885, p. 1015. 
H. Doc. 373, 59th Cong., 1st sess. 
Specified in act. 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 37, 71st Cong., 1st sess.(4) 
H. Doc. 224, 76th Cong., 1st sess. 
H. Doc. 556, 62d Cong., 2d sess. 
H. Doc. 265, 70th Cong., 
5-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 5-B (Cont.) 
Act 
AUTHORIZING LEGISLATION 
Work Authorized 
July 3, 1930 
June 25, 1910 
Aug. 8, 1917 
Sept. 3, 1954 
Oct. 27, 1965 
July 24, 1946 
Aug. 8, 1917 
Sept. 3, 1954 
Oct. 27, 1965 
Mar. 2, 1945 
July 5, 1884 
June 13, 1902 
Mar. 3, 1905 
July 3, 1930 
Aug. 26, 1937 
Mar. 2, 1945 
May 17, 1950 
Oct. 23, 1962 
Oct. 23, 1962 
Aug. 11, 1888 
July 3, 1930 
July 24, 1946 
July 14, 1960 (Sec. 107) 
July 14, 1960 (Sec. 107) 
Sept. 3, 1954 
Oct. 23, 1962 
July 24, 1946 
June 13, 1902 (Sec. 3) 
Aug. 13, 1968 
Scotts Creek 
For existing project dimensions. 
Anchorages 
A 30-foot anchorage at Lambert Point 
A 12-foot anchorage at Pinner Point. 
An anchorage 38 feet deep and 1,500 feet square; anchorage 
35 feet deep and 1,500 feet square; and anchorage 
20 feet deep, 1,000 feet wide, and 3,000 feet long. 
Two anchorages opposite Sewells Point, 45 deep with 
1,200-foot swinging radius. 
Disposal Area 
A trapezoidal-shaped area of about 2,500 acres of 
flats adjacent to and north of Craney Island, including 
levees sluiceways, rehandling basins, and approach and 
exist areas. 
THIMBLE SHOAL CHANNEL, VA. (See Section 12C of Text) 
A channel 40 feet deep and 750 feet wide. 
Channel width increased to 1,000 feet with side channels 
on either side 32 feet deep and 450 feet wide. 
Channel 45 feet deep and 1,000 feet wide. 
HOSKINS CREEK, VA. (See Section 13 of Text) 
A channel 8 feet deep and 100 feet wide in Rappahannock River, 
60 feet wide in creek with turning basin 250 feet long and 
200 feet wide. 
Channel depth increased to 10 feet and width in creek to 
80 feet. 
JAMES RIVER, VA. (See Section 14 of Text) 
Channel 22 feet deep from mouth to Richmond and 
construct spur and training dikes. 
Extension of improvement to Richmond lock gate. 
Form a turning basin by widening channel at Richmond. 
Channel 25 feet deep mouth to Richmond Deepwater 
Terminal. 
Removal of Trigg cofferdam. 
Turning basin at Richmond Harbor. 
Maintaining turning basin at Richmond Deepwater Terminal. 
Channel depth increased to 35 feet to Richmond Deepwater 
Terminal. 
LYNNHAVEN INLET, VA. (See Section 15 of Text) 
Existing project. 
NANSEMOND RIVER, VA. (See Section 16 of Text) 
Channel 12 feet deep, 400 to 200 feet wide, Town Point 
to mouth of Western Branch; thence, 12 feet deep, 100 
feet wide to Suffolk; turning basin 200 feet square 
at Suffolk; and spur dikes and training walls at mouth 
of Western Branch. 
Existing project dimensions 
NEWPORT NEWS CREEK, VA. (See Section 17 of Text) 
Existing Project 
TASKINAS CREEK, VA. (See Section 19 of Text) 
Existing project. 
WISHART POINT CHANNEL, VA. (See Section 20 of Text) 
Existing project. 
VIRGINIA BEACH, VA. (See Section 24 of Text) 
Existing project authorized. 
Project modified. 
GATHRIGHT LAKE, VA. (See Section 26 of Text) 
Existing project. 
BUENA VISTA, VA. (See Section 27 of Text) 
Existing project. 
SALEM CHURCH LAKE, VA. (See Section 30 of Text) 
Existing project. 
H. Doc. 189, 70th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2d sess. 
H. Doc. 605, 63d Cong., 2d sess.(1) 
S. Doc. 122, 83d Cong., 2d sess.(1) 
H. Docs. 187 & 143, 89th Cong., 
H. Doc. 563, 79th Cong., 
2d sess.(1) 
H. Doc. 140, 65th Cong., 1st sess. 
S. Doc. 122, 83d Cong., 2d sess. (1) 
H. Doc. 187, 89th Cong., 1st sess. 
Rivers & Harbors Committee 
Doc. 8, 75th Cong., 1st sess. 
H. Doc. 129, 77th Cong., 1st 
sess. 
S. Ex. Doc. 174, 47th Cong., 
1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1 sess. 
H. Doc. 314, 71st Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 68, 74th Cong., 1st sess.(1) 
H. Doc. 738, 77th Cong., 2d sess. 
H. Doc. 191, 81st Cong., 1st sess. 
H. Doc. 586, 87th Cong., 2d sess. 
H. Doc. 580, 87th Cong., 2d sess. 
Annual report for 1887, p. 1001. 
H. Doc. 184, 70th Cong., 1st sess. 
H. Doc. 559, 79th Cong., 2d sess.(1) 
Approved in 1970. 
Approved in 1969. 
H. Doc. 186, 83d Cong., 1st sess. 
H. Doc. 382, 87th Cong., 2d seas. 
H. Doc. 207, 80th Cong., 1st sess. 
H. Doc. 93-56, 93d Cong., 1st sess. 
S. Doc. 37, 90th Cong., 1st sess.(2) 
5-24 
Documents --

NORFOLK, VA., DISTRICT 
TABLE 5-B (Cont.) AUTHORIZING LEGISLATION 
(1) Contains latest published map. 
(2) Reclassified Inactive. 
(3) Included in emergency relief administration program May 
28, 1935. 
(4) For latest published map, see H. Doc. 1246, 62nd Cong., 
3d sess. 
TABLE 5-C 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., AND ST. JOHNS RIVER, FLORIDA: 
DATA RELATIVE TO THE COMPLETED LOCKS 
(See Section 2 of Text) 
Dinensions 
Greatest Depth on 
Miles Width Length Miter Sills Year 
from of Avail- Opened 
Nor- Location Cham- able Lift Upper Lower Character to Actual 
folk ber for Full (feet) (feet) (feet) of Navi- Cost 
Va. (feet) Width Foundation gation 
(feet) 
12.4 Albemarle and Chesa- 75 600 2.7 (1) (1) Piles in sand 1932 $499,913 
peake Canal (Great and shells 
Bridge, Va.) 
10.7 Dismal Swamp Canal 52 300 12 12 12 Natural earth 1940 348,879 
(Deep Creek) with cutoff 
walls 
33.1 Dismal Swamp Canal 52 300 12 12 13 Natural earth 1941 373,556 
(South Mills, N.C.) with cutoff 
walls 
(1) 16 feet at mean low water. 
5-25 
_ __ ______ ~_ ____

TABLE 5-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 21 in Text) 
Name of Project 
Date Reconnaissance 
or Condition Survey 
Conducted (1) 
Virginia 
Appomattox River 
Broad Creek 
Cape Charles City Harbor 
Chesconessex Creek 
Chincoteague Bay 
Chincoteague Harbor 
Cranes Creek 
Dl)r Creek 
Deep Creek (Accomack) 
Dymers Creek 
Greenvale Creek 
Hampton Creek 
Horn Harbor 
Hoskins Creek 
Jackson Creek 
Lafayette River 
little Machinpongo River 
little River (Creek) 
Locklies Creek 
Lvnnhaven Inlet (Entrance Channel) 
IvLynnhaven Inlet (Narrows) 
Milford Haven 
Mill Creek 
Nandua Creek 
Nansemond River 
Occohannock Creek 
Onancock River 
Oyster Channel 
Pagan River 
Parker Creek 
Parrotts Creek 
Phoebus Channel 
Queens Creek 
Rappahannock River 
Starlings Creek 
Tangier Channel 
Totuskey Creek 
Tylers Beach Channel 
I rhanna Creek 
Whitings Creek 
Willoughby Channel 
Winter Harbor 
York River 
Jan 75 (2) 
Aug 73 (2) 
Sept 74 (2) 
Jun 74 (2) 
J ul 74 (2) 
l)ec 73 (2) 
Feb 75 (2) 
Dec 73 (2) 
Nov 74 (2) 
Aug 74 (2) 
Sep 74 (2) 
Jan 75 (2) 
- 
Jan-Feb 75 (2) 
Oct 73 (2) 
Jan 75 (2) 
Mar-Apr 75 (2) 
(1) Items for which no date is furnished reflect costs for gathering data only. 
(2) Condition. 
5-26 
- --

NORFOLK, VA., DISTRICT 
TABLE 5-E OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 22 of Text) 
Additional 
Expenditure 
For Last Full For New Work 
Report, See Cost to June 30, 1975 Expended From 
Annual Report Contributed 
Project For Construction Maintenance Funds 
Appomattox River, Va. 
Active portion (1) (2) 
Inactive portion 
Broad Creek, Va. (1) 
Cape Charles City Harbor, Va. 
Active portion (1) (3) 
Carters Creek, Va. 
Active portion (1) (4) 
Channel from Phoebus, Va. to deepwater 
in Hampton Roads (1) 
Channel connecting York River, Va. 
Back Creek to Slaights Warf (1) 
Chesconessex Creek, Va. (1) 
Chincoteague Bay, Va. (1) 
Chincoteague Inlet, Va. (1) 
Cockrells Creek, Va. (6) 
Cranes Creek, Va. (1) 
Davis Creek, Va. (1) 
Deep Creek, Accomack Co., Va. (1) 
Dymers Creek, Va. (1) 
Greenvale Creek, Va. (1) (5) 
Hampton Creek, Va. (1) (7) 
Horn Harbor, Va. (1) 
Jackson Creek, Va. (1) 
Kings Creek, Va. (6) 
Lafayette River, Va. (1) 
Little Machipongo River, Va. (1) 
Little River (Creek), Va. (1) (8) 
Locklies Creek, Va. (1) 
Mattaponi River, Va. 
(Active portion) (1) (12) 
Meherrin River, N.C. (1) 
Milford Haven, Va. (1) 
Mill Creek, Va. (1) 
Mulberry Creek, Va. (1) 
Nandua Creek, Va. (1.) 
Occohannock Creek, Va. 
Active portion (1) 
Onancock River, Va. (1) (9) 
Oyster Channel, Va. (1) 
Pagan River, Va. (1) (10) 
Pamunkey River, Va. 
Active portion (1) 
Parker Creek, Va. (1) 
Parrotts Creek, Va. (1) 
Portsmouth Harbor, Va., Channel 
to Nansemond Ordnance Depot (1) 
Queens Creek, Va. (1) 
Quinby Creek, Va. (1) 
Rappahannock River, Va. 
(1) (13) (14) 
Rappahannock River at Bowlers 
Wharf, Va. (6) 
1972 
1962 
1968 
1951 
1944 
1950 
1968 
1973 
1974 
1949 
1950 
1971 
1974 
1953 
1972 
1974 
1964 
1971 
1957 
1969 
1972 
1966 
1928 
1971 
1950 
1950 
1937 
1950 
1950 
1951 
1963 
1971 
1950 
1964 
1974 
1957 
1947 
1968 
1974 
1971 
1950 
$870,341 
17,690 
27,888 
705,685 
28,398 
11,500 
14,855 
25,516 
25,126 
227,000 
6,274 
97,612 
83,000 
5,582 
20,003 
186,237 
13,987 
8,500 
5,593 
79,866 
15,000 
168,623 
11,581 
83,836 
47,734 
24,568 
5,445 
2,393 
6,988 
13,859 
187,914 
119,717 
51,425 
31,376 
15,530 
37,045 
165,566 
26,949 
104,176 
414,633 
$698.,214 
37,500 
298,809 
3,277 
25,250 
36,358 
12,126 
117,751 
714 
137,124 
21,259 
4,524 
74,777 
545,743 
80,654 
24,305 
26,136 
52,798 
377,054 
6,630 
179,500 
49,591 
21,959 
2,963 
2,458 
23,651 
47,274 
305,975 
167,553 
267,818 
161,183 
98,957 
20,877 
66,162 
11,628 
247,985 
1,713,058 
6,000 
1,200 
2,500 
4,000 
2,910 
62,969 
63,692 
16,955 
- 
1,350 
10,383 
5-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 5-E (Cont.) OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 22 of Text) 
Additional 
Expenditure 
For Last Full For New Work 
Report, See Cost to June 30, 1975 Expended From 
Annual Report Contributed 
Project For Construction Maintenance Funds 
Starlings Creek, Va. (1) 1974 66,242 355,997 2,973 
Tangier Channel, Va. (1) 1974 116,550 525,432 - 
Totuskey Creek, Va. (1) 1970 167,869 431,655 2,000 
Tylers Beach, Va. (1) 1972 63,268 61,026 - 
Urbanna Creek, Va. (1) (11) 1963 55,724 65,291 - 
Whitings Creek, Va. (1) 1971 21,630 68,508 500 
Willoughby Channel, Va. (1) 1953 8,500 26,065 - 
Winter Harbor, Va. (1) 1966 171,334 59,845 5,000 
York River, Va. 1958 
Active portion (1) 180,904 210,980 - 
(1) Completed. 
(2) Includes $22,500 for new work for previous projects. 
(3) Includes $445,291 military funds expended for new work dredging on existing project and $83,041 military funds 
expended for new work on construction of wharf and bulkhead. 
(4) In addition, $700 for maintenance was expended from contributed funds. 
(5) In addition, $1,500 for maintenance was expended from contributed funds. 
(6) Inactive. 
(7) Includes $12.000 for new work for previous projects. In addition, $73,800 for maintenance was expended from 
contributed funds. 
(8) Federal funds expended by the U.S. Navy for new work. 
(9) Includes $33,549 for new work and $24,754 for maintenance for previous projects. 
(10) Includes $20.671 for new work for pievious projects. 
(11) In addition, $61,087 was expended for rehabilitation. 
(12) Includes $51,249 for new work and $60,440 for maintenance for previous projects. 
(13) Includes $197,146 for new work and $113,500 for maintenance for previous projects. 
(14) In addition, $168,091 was expended for major rehabilitation. 
TABLE 5-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 28 of Text) 
Additional 
Expenditure 
For Last Full For New Work 
Report, See Cost to June 30, 1975 Expended From 
Annual Report Contributed 
Project For Construction Maintenance Funds 
Newmarket Creek, Va. 1970 $1,000,000 $5,331 $550,097 
Norfolk Floodwall, Va. 1973 1,851,933 2,941 516,256 
5-28

WILMINGTON, N. C., DISTRICT* 
This district comprises central and eastern 
North Carolina and a portion of south-central 
Virginia, embraced in drainage basins tributary 
to the Atlantic Ocean from the southern boundary 
of Virginia to the Shallotte River, inclusive, with 
exception of the Meherrin River Basin above 
Murfreesboro, N.C., the Chowan River Basin 
above the confluence of the Nottaway and 
Blackwater Rivers, and the Pasquotank River 
and its tributaries for navigation only. It includes 
a portion of the Atlantic Intracoastal Waterway 
from the northern boundary of North Carolina to 
Little River, S.C., and a portion of the waterway 
from Norfolk, Va., to the Sounds of North 
Carolina, south of the north shore of Albemarle 
Sound. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control (R & H 
Act of 1965) ................... 6-2 
2. Atlantic Intracoastal Waterway 
Between Norfolk, Va. and St. Johns 
River, Fla. (Wilmington 
District) ...................... 6-2 
3. Avon Harbor, N.C............... 6-4 
4. Beaufort Harbor, N.C. .......... 6-4 
5. Cape Fear River, N.C., Above 
Wilmington .................. 6-4 
6. Channel Connecting Thoroughfare 
Bay with Cedar Bay, N.C. ...... 6-5 
7. Channel from Back Sound to 
Lookout Bight, N.C. ............ 6-5 
8. Channel from Pamlico Sound 
to Rodanthe, N.C............... 6-6 
9. Drum Inlet, N.C. ................ 6-6 
10. Far Creek, N.C. ............... 6-6 
11. Lockwoods Folly River, N.C..... 6-6 
12. Manteo (Shallowbag) Bay, 
N.C . .......................... 6-7 
13. Morehead City Harbor, N.C. ... 6-8 
14. Ocracoke Inlet, N.C. ............ 6-8 
15. Pembroke Creek, N.C. .......... 6-9 
16. Rollinson Channel, N.C. ......... 6-9 
17. Shallotte River, N.C. ........... 6-9 
18. Silver Lake Harbor, N.C. ....... 6-10 
19. Smiths Creek, Pamlico County, N.C. 6-10 
20. Stumpy Point Bay, N.C. ........ 6-10 
21. Waterway Connecting Pamlico 
Sound and Beaufort Harbor, N.C. 6-11 
22. Waterway Connecting Swanquarter 
Bay with Deep Bay, N.C. ....... 6-11 
23. Waterway-Norfolk, Va. to Sounds 
of N.C ....................... 6-11 
24. Wilmington Harbor, N.C. ....... 6-12 
Navigation (Cont.) Page 
25. Reconnaissance and Condition 
Surveys ...................... 6-12 
26. Other Authorized Navigation 
Projects ..................... 6-12 
27. Navigation Work Under Special 
Authorization ................. 6-12 
Beach Erosion Control 
28. Other Authorized Beach Erosion 
Control Project ................ 6-12 
Flood Control 
29. Black River, Harnett County, 
N .C. ........................... 6-13 
30. Brunswick County Beaches, N.C. 
(Cape Fear to North Carolina-South 
Carolina State Line) ............ 6-13 
31. Cape Fear River Basin, N.C. .... 6-13 
31A. B. Everett Jordan Dam and 
Lake, N.C. (Formerly New 
Hope Lake, N.C.) ............... 6-14 
31B. Howards Mill Lake, N.C. ....... 6-14 
31C. Randleman Lake, N.C. .......... 6-15 
32. Carolina Beach and Vicinity 
N.C. ........................... 6-15 
33. Joyce Creek, Camden County 
N .C. ........................... 6-16 
34. Little Rockfish Creek, Hope 
Mills, N.C. .................... 6-16 
35. Mackay Creek, N.C. ........... 6-17 
36. Neuse River Basin, N.C. ........ 6-17 
36A. Falls Lake, N.C. .............. 6-17 
37. Ocracoke Island, N.C. ......... 6-18 
38. Rockfish Creek, N.C............. 6-19 
39. Scuppernong River, N.C. ....... 6-19 
40. Thoroughfare Swamp, N.C. ..... 6-19 
* All costs and financial statements for projects are listed at the end of this chapter. Other tables referenced in the text also 
appear at the end of this chapter. 
6-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (Cont.) Page 
41. Inspection of Completed 
Flood Control Projects .......... 
42. Other Authorized Flood 
Control Projects ................ 
43. Flood Control Work Under 
Special Authorization ........... 
Multiple-Purpose Projects 
Including Power 
44. Roanoke River Basin, Va. 
and N.C ........................ 6-20 
Multiple Purpose Projects 
Including Power (Cont.) 
44A. John H. Kerr Dam and 
6-20 Reservoir, Va. and N.C........ . 
44B. Philpott Lake, Va. ............. 
6-20 45. Scheduling Flood Control 
Reservoir Operations ........... 
6-20 
46. 
47. 
General Investigations 
Surveys ........................ 
Collection and Study of Basic 
Data ........................... 
Page 
6-20 
6-21 
6-21 
6-22 
6-22 
Navigation 
1. AQUATIC PLANT CONTROL 
(RIVER AND HARBOR ACT OF 
1965) 
Location. Navigable waters, tributary 
streams, connecting channels, and other allied 
waters in Wilmington District. 
Existing project. The existing project provides 
for control and progressive eradication of waterhyacinth, 
alligatorweed, Eurasian watermilfoil, 
and other obnoxious aquatic plant growths from 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and 
wildlife conservation, public health, and related 
purposes, including continued research for 
development of the most effective and economic 
control measures in cooperation with other 
Federal and State agencies in accordance with 
the report of the Chief of Engineers, House Document 
251, 89th Congress, 1st session. The project 
was authorized by Section 302, 1965 River and 
Harbor Act (H. D. 25, 89th Cong., 1st sess.) The 
Act provides that research and planning costs 
shall be borne fully by the United States. 
Local cooperation. Local interests must agree 
to hold the United States free from damages that 
may occur from operations performed in connection 
with this project, and participate to the extent 
of 30 percent of the cost of the program. Requirements 
are being met. 
Operations and results during fiscal year. Herbicidal 
control of Eurasian watermilfoil, continued 
in Kitty Hawk Bay (Dare County) and 
limited areas in the lower Currituck Sound area 
of North Carolina. On May 1, 1974 a contract was 
awarded for aerial application of 2, 4-D to accomplish 
this work. Prior to this, a public hearing 
was conducted in February 1974 by the N.C. 
Department of Natural and Economic Resources 
concerning the watermilfoil problem. No control 
work was performed on alligatorweed. Because 
of environmental considerations, the N.C. 
Department of Natural and Economic Resources 
has asked that chemical treatment of 
alligatorweed cease. The.work was accomplished 
at a Federal cost of $32,586 and contributed cost 
of $12,715. 
Condition at end of fiscal year. The State 
General Design Memorandum was submitted to 
higher authority and approved December 1969. 
The supplemental agreement to contract with the 
State of North Carolina was approved and 
accepted by the State, effective April 1970. 
2. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN 
NORFOLK, VA., AND ST. 
JOHNS RIVER, FLA. 
(WILMINGTON DISTRICT) 
Location. The project is located on the east 
coast of the United States, between Norfolk, Va., 
and St. Johns River, Florida. The section within 
Wilmington District begins at the Virginia- 
North Carolina State line and extends generally 
southerly and southwestwardly to Little River, 
S.C., a total of 308 statute miles. (See Coast and 
Geodetic Survey Charts 830 to 842, inclusive.) 
Previous projects. For details see Annual 
Reports for 1915, 1926, 1932, and 1938. 
Existing project. The authorized project 
provides for a waterway, 12 feet deep, with 
widths varying from 90 feet in land cuts to 300 
feet in open waters; the construction, operation 
and maintenance of suitable bridges; salt-waterintrusion 
preventive measures in the vicinity of 
Fairfield, N.C.; a channel in Peltier Creek, 6 feet 
deep and 50 feet wide from the Intracoastal 
6-2

WILMINGTON, N.C., DISTRICT 
Waterway in Bogue Sound to and including a 
basin in Peltier Creek, 6 feet deep, 200 feet wide, 
and 600 feet long; a channel, 6 feet deep and 90 
feet wide between the Intracoastal Waterway and 
the gorge in Bogue Inlet; a channel, 12 feet deep 
and 90 feet wide to a turning basin, 200 feet wide 
and 350 feet long, at Swansboro; a channel, 6 feet 
deep and 90 feet wide in New River Inlet, and a 
connecting channel of the same dimensions to the 
Intracoastal Waterway near the mouth of New 
River; a channel, 10 feet deep, and 90 feet wide in 
New River, between the Intracoastal Waterway 
and the Seaboard Coast Line Railroad bridge at 
Jacksonville, N.C.; a channel through New Topsail 
Inlet, 8 feet deep and 150 feet wide and a 
channel from New Topsail Inlet to the Intracoastal 
Waterway by way of Old Topsail 
Creek, 7 feet deep and 80 feet wide; a channel, 7 
feet deep and 80 feet wide, in Banks Channel, 
from New Topsail Inlet, paralleling the barrier 
beach, to the Atlantic Intracoastal Waterway; a 
channel, 14 feet deep and 400 feet wide, across the 
ocean bar at Masonboro Inlet, with suitable jetties 
at the entrance, thence 12 feet deep and 90 
feet wide to the channel of the Intracoastal 
Waterway at Wrightsville by way of Banks and 
Motte Channels; a turning basin, 15 feet deep, 300 
feet wide, and 700 feet long, on the east side of 
Banks Channel near Masonboro Inlet, with three 
15-pile dolphins therein; a channel, 6 feet deep, 80 
feet wide, and 8,000 feet long, to and including a 
turning basin of the same depth, 130 feet wide 
and 180 feet long, at Carolina Beach; a yacht 
basin, 230 feet wide, 450 feet long, and 12 feet 
deep, at the town of Southport, connected to the 
waterway by a suitable channel of the same 
depth; and maintenance of the general navigation 
features of the North Carolina State Ports 
Authority Small-Boat Harbor at Southport, consisting 
of an entrance channel, 150 feet wide and 
400 feet long, an eastern harbor-access channel, 
70 feet wide and 430 feet long, a western harboraccess 
channel, 60 feet wide and 185 feet long, to a 
turning basin, 180 feet wide and 550 feet long, all 
to a depth of 6 feet. Length of channels and basins 
total 347.1 miles. A modification providing for 
the replacement of five Federally owned and 
operated highway bridges was authorized in 
December 1970. Estimated Federal Cost is 
$21,500,000 (1975). Plane of reference is mean 
low water. 
In the waterway north of Neuse River, 
variations in water surface due to winds seldom 
exceed 2 feet above or below mean stage. Between 
Beaufort and the Cape Fear River, normal tidal 
range varies from 3.5 feet at the inlets to 1 foot at 
points between. Average range of tide is 4 feet on 
the ocean side of Bogue Inlet and 2.5 feet just inside 
the inlet. At New River, tidal range varies 
from 3.5 feet at the inlet to 1 foot at the head of the 
marshes and zero at Tar Landing, 31 miles above. 
From Cape Fear River, N.C., to Little River, S.C., 
mean tidal range varies between 4.7 feet in Cape 
Fear River and 4 feet at the intermediate inlets, 
and 2 feet at points midway between the inlets. On 
October 15, 1954 (Hurricane Hazel), the tide at 
Holden Beach reached an elevation of 17.6 feet. 
(See Table 6-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date 
except for the modification. The State of North 
Carolina has agreed to keep the bridges toll free 
and upon completion of each bridge, accept 
maintenance, replacement, and ownership 
responsibilities thereof. They have withdrawn 
their offer to contribute 25 percent of the first 
cost. The project is awaiting reauthorization to 
reflect 100 percent Federal funding. 
Operations and results during fiscal year. New 
work: Engineering and design for the replacement 
of five highway bridges continued at a cost 
of $119,158. Environmental impact studies cost 
$9,724. Maintenance: During intermittent 
periods, the U.S. sidecasting dredge Merritt 
removed 47,631 cubic yards from shoals in New 
Topsail Inlet at a cost of $45,580; and, 59,126 
cubic yards from shoals in New River Inlet at a 
cost of $75,640. The hopper vessel Currituck accompanied 
the dredge Merritt on these jobs at a 
cost of $20,865. The dredge Merritt also removed 
miscellaneous shoals at a cost of $3,535. During 
intermittent periods the U.S. snagboat Snell 
maintained survey and dredging ranges and conducted 
clearing and snagging operations at a cost 
of $81,539. Between July 1 and October 25, 1974 
the contract dredge Northwood II removed 377,- 
177 cubic yards from shoals between the Virginia 
line and Little River, S.C. at a cost of $859,510. 
Between April 3 and June 30, 1975 the contract 
dredges Hampton Roads and Marion removed 
180,836 cubic yards from shoals in the through 
waterway between Neuse River and Little River, 
S.C. at a cost of $434,118. Cost in connection with 
prior year contract dredging work was $1,155. 
Engineering and design on prior year contract 
work was $954. Supervision and inspection on 
prior year work was $1,996. Inspection of five 
highway bridges cost $8,965. Bottom sediment 
analysis cost $2,413. Environmental studies cost 
$126,131. Condition and operation studies cost 
$177,234. Five highway bridges and utilities 
were operated and maintained for $467,087. 
Studies and repairs to Masonboro Inlet Jetty 
were made at a cost of $4,354. Litigation expense 
at Core Creek was $7,232. Engineering and 
design on model study cost $84. 
Condition at end offiscal year. The project was 
completed in April 1967, except for the south jetty, 
three tie-up dolphins at Masonboro Inlet, and 
the latest modification. Total cost for existing 
6-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
project to June 30, 1975, $37,069,261, of which 
$11,640,554 was for new work and $25,428,707 
was for maintenance. 
3. AVON HARBOR, N.C. 
Location. The project is located on the east 
coast of North Carolina, 9 miles north of Cape 
Hatteras. (See Coast and Geodetic Survey Chart 
1232.) 
Existing project. The authorized project 
provides for a direct channel 6 feet deep, 100 feet 
wide, and 3.5 miles long from the depth in 
Pamlico Sound southeast to a basin of the same 
depth, 100 feet wide and 300 feet long at Avon. 
Plane of reference is mean low water. Variations 
in the water surface of Pamlico Sound, due to 
winds, seldom range as much as 2 feet above or 
below mean stage; however, severe windstorms 
will double or triple that variation. The original 
project was authorized by the 1945 River and 
Harbor Act (H. D. 316, 76th Cong., 1st sess.) and 
modification for direct channel authorized May 5, 
1965, under Section 107, River and Harbor Act of 
1960. 
Local cooperation. Fully complied with. 
Terminal facilities. There are five wharves in 
the basin at Avon, with a total frontage of about 
300 feet. These facilities are considered adequate 
for present commerce. 
Operations and results during fiscal 
year. Maintenance: Condition and operation 
studies cost $632. Environmental studies cost 
$1,668. 
Condition at end of fiscal year. The project was 
completed July 1965. (For further details, see Annual 
Report for 1962.) 
4. BEAUFORT HARBOR, N.C. 
Location. The project is just inside Beaufort 
Inlet, adjacent to Morehead City Harbor. (See 
Coast and Geodetic Survey Chart 420.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938. 
Existing project. The authorized project 
provides for stopping erosion at Beaufort Inlet by 
jetties and sand fences at Fort Macon and 
Shackleford points and other shore protection; 
channels 15 feet deep at mean low water and 100 
feet wide in Bulkhead and Gallants Channels, except 
for a depth of 12 feet in the upper 5,000 feet of 
Gallants Channel; a harbor of refuge in Town 
Creek 12 feet deep, 400 feet wide, and 900 feet 
long connected to Gallants Channel by a channel 
12 feet deep, 150 feet wide, and 1,400 feet long; a 
basin 12 feet deep, 600 feet wide in front of the 
town of Beaufort except for a channel 15 feet 
deep, 100 feet wide through the basin; a stone 
bulkhead from Town Marsh across Bird Shoal to 
the west end of Carrot Island; and a channel in 
Taylors Creek 15 feet deep, 100 feet wide, extending 
about 2.6 miles easterly from about opposite 
Marsh Street in Beaufort to Lennoxville Point at 
North River, except for an 800-foot-long section 
at the east end which is 12 feet deep. Total length 
of channels is 6.9 miles. Average tidal range is 2.5 
feet at Beaufort and 3.5 feet at the inlet. (See 
Table 6-B for Authorizing Legislation.) 
Local cooperation. Fully complied with except 
for Town Creek, Harbor of Refuge, Section 107 
modification for which a public wharf and mooring 
facilities have not been provided. 
Terminal facilities. There are fifty waterfront 
facilities with a total frontage of 2,000 feet. These 
facilities are adequate for present commerce. 
Operations and results during fiscal 
year. Maintenance: Between April 8 and May 8, 
1975 the contract dredge Richmond removed 80,- 
379 cubic yards from shoals in the harbor at a cost 
of $114,472. Engineering and design on prior 
year contract work cost $1,367. Cost in connection 
with claim for pipeline dredging at Gallants 
Channel was $637. Environmental studies cost 
$753. Condition and operation studies cost $17,- 
540. Contributed funds in the amount of $103,578 
were expended for diking. 
Condition at end of fiscal year. The project was 
completed in October 1965. (For further details 
see Annual Report for 1962.) Costs under existing 
project to June 30, 1975, were $573,389 for new 
work and $1,427,208 for maintenance, including 
$103,578 contributed funds, a total of $2,000,597. 
5. CAPE FEAR RIVER, N.C., 
ABOVE WILMINGTON 
Location. The river is formed by confluence of 
the Deep and Haw Rivers at Moncure, Chatham 
County, N.C., and empties into the Atlantic 
Ocean at Cape Fear, near the southern extremity 
of the State. (See Coast and Geodetic Survey 
Chart 426.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938. 
Existing project. The authorized project 
provides for a channel 25 feet deep and 200 feet 
wide from Wilmington to a turning basin 400 feet 
wide and 550 feet long at Navassa (2.9 miles); a 
channel 12 feet deep and 140 feet wide from 
Navassa to mileboard 30 at Acme, with five 
channel cutoffs, 12 feet deep and 150 feet wide to 
eliminate sharp bends; a channel 8 feet deep from 
mileboard 30 to Fayetteville by constructing 
three locks and dams and by dredging river 
shoals; and recreational facilities at the locks and 
dams. Total length of the project channels is 113.9 
miles. The project was authorized by River and 
6-4

WILMINGTON, N.C., DISTRICT 
Harbor Acts of June 25, 1910; June 26, 1934; 
August 30, 1935; August 26, 1937; October 27, 
1965; and Section 4, Flood Control Act of 1944. 
For further details see Annual Reports for 1962 
and 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. There are eleven waterfront 
facilities on the river, with a total frontage 
of 1,190 feet. 
Operations and results during fiscal 
year. Maintenance: Between June 16-19, 1975, 
the U.S. sidecasting dredge Merritt removed 
4,264 cubic yards from shoals in the river channel 
at a cost of $4,858. Cost in connection with prior 
years dredging was $8,617. Emergency dredging 
to remove shoals at Lock No. 1 with dredge 
Merritt cost $4,480. During intermittent periods, 
the U.S. snagboat Snell conducted snagging 
operations in the channel to Fayetteville at a cost 
of $13,620. Previous year repair to boat ramp cost 
$350. Periodic inspections of locks and dams cost 
$12,805. Supervision and inspection on prior year 
work cost $685. Environmental studies cost $13,- 
147. Operation and maintenance of the three 
locks and dams cost $218,444. Condition and 
operation studies cost $40,676. 
Condition at end of fiscal year. The project was 
completed in June 1970. Total costs of existing 
project to June 30, 1975 were $9,988,723 of which 
$3,610,454 (including $1,226,385 public works) 
was for new work and $6,378,269 for 
maintenance. 
6. CHANNEL CONNECTING 
THOROUGHFARE BAY WITH CEDAR 
BAY, N. C. 
Location. Thoroughfare Bay, the southern end 
of the project, is on the north side of Core Sound, 
about 6 miles west of the end of the peninsula at 
the junction of Core and Pamlico Sounds. It lies 
about 30 miles by boat route through Core Sound 
easterly from Beaufort, N.C. Cedar Bay (actually 
an arm of West Bay on latest U.S. Coast and 
Geodetic Survey map) is the other extremity of 
the project. An extension of U.S. Highway 70, 
beyond Atlantic, N.C., crosses the channel. (See 
U.S. Coast and Geodetic Survey Chart No. 1223.) 
Existing project. This provides for a channel 7 
feet deep and 50 feet wide with increased widths 
at bends, to connect Thoroughfare Bay with 
Cedar Bay. The channel is about 4.3 miles long. 
There is no lunar tide in or at either end of the 
waterway, variations in the level of the water surface 
being due to wind action. Ordinary storms 
will cause a variation of 1 foot above or below the 
mean stage, while severe storms have caused a 
variation of as much as 5 feet. The cost of new 
work to the Federal Government for the completed 
project was $69,610. The project was 
authorized by River and Harbor Acts of March 2, 
1919 and March 2, 1945. (H.D. 1125, 63d Cong., 2d 
sess. and S.D. 87, 76th Cong., 1st sess.) 
Local cooperation. The River and Harbor Act 
of March 2, 1945, provided that local interests 
furnish, free of cost to the United States, suitable 
spoil-disposal areas when and as required for new 
work and for subsequent maintenance. Local interests 
have complied with requirements for construction, 
and will be required to furnish suitable 
spoil-disposal areas for subsequent maintenance. 
Terminal facilities. This is essentially a 
through waterway; therefore, no terminal 
facilities are deemed necessary. However, during 
the shrimping season, about 20 boats use a side 
channel, on the east side of the swing bridge crossing 
the Atlantic-Cedar Island road, for mooring 
purposes. There is also a makeshift dock, at the 
pilings of the old bridge, which provides mooring 
space for two boats. 
Operations and results during fiscal 
year. Maintenance: Environmental studies cost 
$2,700. 
Condition at end of fiscal year. The existing 
project is completed. Dredging a 5-foot channel, 
50 feet wide, was commenced in March and completed 
in April 1921. Dredging to increase the 
depth to 7 feet, same width, was commenced in 
July and completed in October 1959. The total 
costs under the existing project to June 30, 1975, 
were $69,610 for new work and $25,573 for 
maintenance, a total of $95,183. 
7. CHANNEL FROM BACK SOUND TO 
LOOKOUT BIGHT, N.C. 
Location. The project is located on the coast of 
North Carolina, 8 miles east of Beaufort Inlet. 
(See Coast and Geodetic Survey Chart 420.) 
Existing project. The authorized project 
provides for a channel 100 feet wide and 7 feet 
deep from Back Sound, through Shackleford 
Banks to Lookout Bight. The project was 
authorized by River and Harbor Acts of August 
26, 1937, and March 2, 1945. For details see Annual 
Report for 1959. 
Local Cooperation. Fully complied with. 
Terminal facilities: None required. 
Operations and results during fiscal 
year. Maintenance: During intermittent periods 
the dredge Merritt removed 55,667 cubic yards 
from shoals in Bardens Inlet at a cost of $78,261. 
Between March 23 and April 7, 1975 the contract 
dredge Richmond removed 34,530 cubic yards 
from shoals in the channel at a cost of $75,058. 
Work in connection with prior dredging cost 
6-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
$874. Condition and operation studies cost $2,860. 
Environmental impact studies cost $646. Project 
condition surveys cost $9,606. 
Condition at end of fiscal year. The project was 
completed in May 1965. 
8. CHANNEL FROM PAMLICO SOUND 
TO RODANTHE, N.C. 
Location. East coast of North Carolina, 25 
miles north of Cape Hatteras. (See Coast and 
Geodetic Survey Chart 1232.) 
Existing project. A channel 6 feet deep, 100 feet 
wide, and 1.25 miles long from Pamlico Sound to 
a basin at the shore end near Rodanthe of same 
depth, 80 to 100 feet wide, and total length of 
about 1,200 feet. Project authorized by River and 
Harbor Act of 1945. (H.D. 234, 76th Cong., 1st 
sess.) (For further details see Annual Report for 
1950.) 
Local cooperation. Local interests must furnish 
suitable spoil disposal areas for new work 
and maintenance. Fully complied with. 
Terminal facilities. Four terminals with combined 
frontage of 130 feet, along with bulkheaded 
portion, are considered adequate. 
Operations and results during fiscal 
year. Maintenance: Environmental studies cost 
$2,300. 
Condition at end of fiscal year. Project completed 
March 1965. 
9. DRUM INLET, N.C. 
Location. Drum Inlet is an opening through 
the barrier beach which separates Core Sound 
from the Atlantic Ocean. It is about 1,100 feet 
wide and is about 35 miles northeast of Beaufort 
and opposite the village of Atlantic. (See Coast 
and Geodetic Survey Charts 1233 and 419.) 
Existing project. The project provides for a 
channel 12 feet deep at mean low water and 200 
feet wide from the gorge in the inlet to the 
Federally improved channel in Core Sound, 
about 1 mile. The mean range tide is 3.8 feet in the 
ocean and 0.3 foot in Core Sound at Atlantic. The 
project also provides for a channel 150 feet wide 
and 9 feet deep from the gorge in the inlet to deep 
water in the Atlantic Ocean. The Core Sound portion 
of the project was authorized by the River 
and Harbor Act of June 20, 1938 (H. D. 414, 75th 
Cong., 2d sess.). The channel from the inlet to the 
Atlantic Ocean was authorized under Section 107 
of the 1960 River and Harbor Act. 
Local cooperation. Fully complied with. 
Operations and results during fiscal 
year. Maintenance: During December 1-8, 1974 
the U.S. sidecasting dredge Merritt removed 
"4,092 cubic yards from shoals in Drum Inlet at a 
cost of $12,511. During intermittent periods the 
U.S. snagboat Snell maintained survey and 
dredging ranges at a cost of $3,840. Between July 
7 and August 8, 1974, the contract dredge Richmond 
removed 103,772 cubic yards from the 
sound channel at a cost of $169,143. Engineering 
and design on prior year contract work cost $918. 
A study of the impact of Drum Inlet on shoreline 
erosion in the vicinity of Atlantic, N.C. cost $15,- 
517. 
Condition at end of fiscal year: The project was 
completed in February 1972. 
10. FAR CREEK, N.C. 
Location. Flows easterly from Engelhard into 
Pamlico Sound, about 95 miles south of Norfolk, 
Va. (See Coast and Geodetic Survey Chart 1232.) 
Existing project. A channel 12 feet deep and 80 
to 100 feet wide from Pamlico Sound to highway 
bridge at Engelhard, with a turning basin 12 feet 
deep, 200 feet wide and 900 feet long at the head. 
Project was authorized by River and Harbor Acts 
of July 3, 1930, and May 17, 1950. For further 
details see Annual Report for 1962 
Local cooperation: Fully complied with. 
Terminal facilities. Project is served by 12 
waterfront facilities with a total frontage of 2,300 
feet, all privately owned. Existing facilities are 
adequate for present commerce. 
Operations and results during fiscal 
year. Maintenance: Environmental studies cost 
$963. 
Condition at end of fiscal year. Project completed 
June 1957. 
11. LOCKWOODS FOLLY RIVER, N.C. 
Location. The project is located on the south 
coast of North Carolina about 12 miles west of 
Cape Fear River. (See Coast and Geodetic Survey 
Chart 1236 and Geological Survey Map of North 
Carolina.) 
Existing project. The authorized project 
provides for a channel 100 feet wide and 6 feet 
deep at low water from the ocean to the bridge at 
Supply 12.5 miles above, to be obtained by dredging 
through oyster rocks and mudflats. The uncompleted 
river portion of the project above the 
waterway was reclassified to the active category 
in 1971. Lunar tidal ranges in Lockwoods Folly 
River are 4.5 feet at the inlet and 2 feet at the head 
of navigation at Supply. Estimated cost of new 
work is $128,000 (revised 1965). The existing project 
was authorized by the 1890 River and Harbor 
Act. (See Annual Report for 1887, page 1099.) 
Local cooperation. None required. 
6-6

WILMINGTON, N.C., DISTRICT 
Terminal facilities. Thirty-one piers and 
wharves on the Atlantic Intracoastal Waterway 
at Holden Beach, about 1.25 miles west of 
Lockwoods Folly Inlet, with a total frontage of 
about 1,980 feet available. At Dixons Landing, 
about 2 miles upstream of the inlet, there are five 
wharves with a total frontage of 240 feet. 
Numerous natural landings are used for loading 
and unloading small boats. Berthing space in the 
vicinity of Lockwoods Folly Inlet totals about 
2,220 feet. Facilities are considered adequate for 
present commerce. 
Operations and results during fiscal 
year. Maintenance: Engineering and design for 
pipeline dredging accomplished during previous 
year cost $1,857. Communications Center cost 
$1,034. Environmental studies cost $6,036. 
Condition at end of fiscal year. The active portion 
of the project was completed in June 1965. 
12. MANTEO (SHALLOWBAG) BAY, 
N.C. 
Location. The project is located on the 
northeastern side of Roanoke Island, North 
Carolina. (See Coast and Geodetic Survey Chart 
1229.) 
Existing project. The authorized project 
provides for a channel 14 feet deep and 400 feet 
wide from the Atlantic Ocean through Oregon 
Inlet with connecting 12-foot channels, 100 feet 
wide, to Pamlico Sound, Manteo, and Wanchese; 
and a channel 6 feet deep and 100 feet wide connecting 
the Manteo-Oregon Inlet Channel with 
Roanoke Sound. Length of channels is 25.4 miles. 
A newly authorized modification provides for 
stabilization of Oregon Inlet with a dual rubblemound 
jetty system, including means for sand 
transfer to the downdrift beach and bottom 
protection for the highway bridge over Oregon 
Inlet; a channel, 20 feet deep and 400 feet wide, 
through the ocean bar at Oregon Inlet; a channel, 
14 feet deep and 120 feet wide, from the gorge in 
Oregon Inlet to and through Roanoke Sound to 
and including a 15-acre basin of the same depth at 
Wanchese; and a channel, 10 feet deep and 100 
feet wide, from the 12-foot-deep channel in 
Manteo (Shallowbag) Bay through Roanoke 
Sound to and through Albemarle Sound to deep 
water near the northern end of Croatan Sound. 
The estimated Federal cost for the modification is 
$2,700,000 (1975). The project was authorized by 
River and Harbor Acts of June 25, 1910; October 
17, 1940; May 17, 1950; and December 31, 1970; 
and under Section 107 of the 1960 River and Harbor 
Act. 
Local cooperation. For the new modification, 
local interests must: (a) provide all lands, 
easements, and rights-of-way for construction 
and subsequent maintenance of the project, including 
suitable areas required for initial and 
subsequent disposal of spoil and also necessary 
retaining dikes, bulkheads, and embankments 
therefor, or the cost of such retaining works; (b) 
hold and save the United States free from 
damages due to the construction works and subsequent 
maintenance; (c) continue to provide and 
maintain adequate terminal and transfer 
facilities, open to all on equal terms, in accordance 
with plans approved by the Chief of 
Engineers; (d) provide and maintain necessary 
mooring and berthing facilities in any enlarged 
basin, open to all on equal terms, in accordance 
with plans approved by the Chief of Engineers; (e) 
provide and maintain depths in berthing areas 
and local access channels serving the terminals 
commensurate with depths provided in the 
related projects areas; (f) provide and maintain 
necessary stone for bottom protection along the 
bridge over Oregon Inlet or the cost of such 
protection works; (g) accomplish such alterations 
as required in sewer, water supply, drainage, 
electrical power lines, telephone lines, or other 
utility facilities as well as their maintenance; (h) 
establish a competent and properly constituted 
public body empowered to regulate the use, 
growth, and free development of the harbor 
facilities, with the understanding that said 
facilities will be open to all on equal terms; (i) and 
establish regulations prohibiting the discharge of 
untreated sewage, garbage, and other pollutants 
in the water of the harbor by the users thereof, 
which regulations shall be in accordance with 
applicable laws or regulations of Federal, State, 
and local authorities responsible for pollution 
prevention and control. Reasonable assurances 
have been received. 
Terminal facilities. The project is served by 33 
waterfront facilities with a total frontage of 3,320 
feet. Additional wharves and facilities will be 
provided with the enlarged basin at Wanchese. 
Operations and results during fiscal year. New 
work: Advance engineering and design for the 
latest modification cost $114,896. Maintenance: 
During intermittent periods the U.S. sidecasting 
dredge Schweizer removed 182,068 cubic yards 
from shoals in Oregon Inlet at a cost of $122,953. 
During intermittent perods the U.S. snagboat 
Snell maintained dredging and survey ranges at 
a cost of $91,469. During July 1-15, 1974 the contract 
dredge Clarendon removed 147,104 cubic 
yards from shoals in Old House Channel and the 
channel from Oregon Inlet to Wanchese at a cost 
of $158,242. Between May 13 and June 4,1975 the 
contract dredge Richmond removed 114,693 
cubic yards from shoals in the channel from 
Oregon Inlet to Wanchese at a cost of $153,482. 
6-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Engineering and design for pipeline dredging accomplished 
in previous years was $37. Environmental 
studies cost $5,535. Condition and 
operation studies cost $77,903. Model study of 
Oregon Inlet cost $329,899. 
Condition at end of fiscal year. The project is 
complete except for the latest modification. (For 
further details, see Annual Report of 1962.) 
13. MOREHEAD CITY HARBOR, N. C. 
Location. The project is located on the 
northern shore of Bogue Sound, adjacent to 
Beaufort Inlet. (See Coast and Geodetic Survey 
Chart 420.) 
Previous project. For details see page 470 of 
Annual Report for 1935. 
Existing project. The authorized project 
provides for a bar channel 35 feet deep and 400 
feet wide, thence an inner channel 35 feet deep 
and 300 feet wide, a turning basin 35 feet deep, 
and connecting shallow-draft channels. Jetties at 
Beaufort Inlet were reclassified to the "active" 
category on March 8, 1972. A newly authorized 
modification provides for deepening of the 
channel, from the 42-foot-depth contour in the 
Atlantic Ocean through the ocean bar to the gorge 
in Beaufort Inlet, to 42 feet over a bottom width of 
450 feet, thence to a depth of 40 feet in the east leg 
of the turning basin including the 1,200 foot 
diameter turning area, with widths of 600 feet in 
the cutoff channel, and 400 feet wide to the turning 
basin. The estimated Federal cost is $4, 
290,000(1975) for the modificationand$27,500,000 
(1975) for the jetties. In general the project as it 
now exists was authorized by the 1958 River and 
Harbor Act (S. D. 54, 84th Cong., 1st sess.) and the 
River and Harbor Act of December 31, 1970. For 
further details see Annual Report for 1962. 
Local cooperation. For the new modification, 
local interests must: (a) provide, without cost to 
the United States, all lands, easements, and 
rights-of-way required for construction and subsequent 
maintenance of the project and for aids to 
navigation upon the request of the Chief of 
Engineers, including suitable areas determined 
by the Chief of Engineers to be required in the 
general public interest for initial and subsequent 
disposal of spoil and also necessary retaining 
dikes, bulkheads, and embankments therefor, or 
the costs of such retaining works; (b) hold and 
save the United States free from damages due to 
construction and maintenance of the project; (c) 
provide and maintain, at local expense, adequate 
public terminal and transfer facilities, open to all 
on equal terms; (d) provide and maintain, without 
cost to the United States, depths in berthing areas 
and local access channels serving terminals commensurate 
with depths in related project areas; 
(e) accomplish, without cost to the United States, 
such utility and other relocations or alterations as 
necessary for project purposes; (f) prohibit erection 
of any structure within 125 feet of the project 
channels or turning basins; and (g) establish 
regulations prohibiting discharge of pollutants 
into the waters of the channel and harbor by users 
thereof, which regulations shall be in accordance 
with applicable laws or regulations of Federal, 
State, and local authorities responsible for pollution 
prevention and control. Formal assurances 
have been provided. 
Terminal facilities. Twenty-six waterfront 
facilities serve the port, with a total frontage of 
1,250 feet. Marine terminals provide 3,625 feet of 
berthing space, with a depth alongside of 35 feet, 
and facilities for transfer of cargoes between rail 
and water carriers. Improvements to facilities 
were completed in 1969. For further details see 
Port Series No. 12, revised 1971, Corps of 
Engineers. 
Operations and results during fiscal year. New 
Work: Advance engineering and design for latest 
modification cost $52,322. Maintenance: Between 
September 21 and October 5, 1974 the U.S. 
hopper dredge Gerig removed 238,289 cubic 
yards from shoals in the ocean bar and entrance 
channel at a cost of $173,019. Between January 2- 
31, 1975 the U.S. hopper dredge Goethals removed 
190,397 cubic yards from shoals in the ocean 
bar and entrance channel at a cost of $816,843. 
During intermittent periods the U.S. snagboat 
Snell repaired dredging and survey ranges at a 
cost of $2,626. Engineering and design for 
pipeline dredging accomplished in previous 
years was $492. Monitoring for project evaluation 
cost $62,637. Condition and operation studies cost 
$86,122. 
Condition at end of fiscal year. The existing 
project is complete except for the jetties, and the 
latest modification. (For further details, see Annual 
Report for 1962.) Total cost of the existing 
project to June 30, 1975 was $14,428,695 of which 
$1,781,482 was for new work (including $553,477 
public works funds) and $12,647,213 for 
maintenance, including $40,557 contributed 
funds. 
14. OCRACOKE INLET, N.C. 
Location. The inlet connects Pamlico Sound 
with the Atlantic Ocean, about 31 miles 
southwest of Cape Hatteras and 43 miles 
northeast of Cape Lookout. (See U. S. Coast and 
Geodetic Survey Chart No. 1232.) 
Existing project. The authorized project 
provides for a channel across the ocean bar 18 feet 
deep and 400 feet wide, and construction of ajetty 
extending from Ocracoke Island to the Atlantic 
Ocean. Construction of the jetty has been deferred 
for restudy. The project was authorized by the 
6-8

WILMINGTON, N.C., DISTRICT 
River and Harbor Act of July 14, 1960. For 
further details, see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. None required. 
Operations and results during fiscal 
year. Maintenance: Between September 8 and 
December 4, 1974, the U.S. sidecasting dredge 
Schweizer removed 72,372 cubic yards from 
shoals in the inlet channel at a cost of $143,618. 
During intermittent periods the U.S. snagboat 
Snell maintained survey and dredging ranges at 
a cost of $9,353. Supervision and inspection of 
previous year work cost $143. Environmental 
studies cost $6,248. Condition and operation 
studies cost $10,738. 
Condition at end of fiscal year. Construction 
was completed in August 1971. 
15. PEMBROKE CREEK, N.C. 
Location. Pembroke Creek is a small nontidal 
stream flowing south and southeasterly 9/2 miles 
to the western end of Edenton Bay, an indention 
on the north shore at the west end of Albermarle 
Sound. The town of Edenton is at the mouth of the 
creek. 
Existing project. This provides for a channel 12 
feet deep, 80 feet wide, from the improved 
channel in Edenton Bay upstream 500 feet; 
thence 8 feet deep and 50 feet wide to the wharf of 
the United States fish hatchery, two-thirds mile 
above the mouth. The proposed project provides 
for a channel 8 feet deep, 80 feet wide, and 1,800 
feet long at the mouth of Pembroke Creek. The 
existing project was adopted by the River and 
Harbor Act of March 2, 1945 (H. D. 235, 76th 
Cong., 1st sess.). The latest published map is in 
that document. 
Local cooperation. The River and Harbor Act 
of March 2, 1945, provided that local interests 
furnish, free of cost to the United States, suitable 
spoil-disposal areas for the initial work and for 
subsequent maintenance as required. Local interests 
have signified their intention of meeting 
all local cooperation requirements when and as 
required. 
Terminal facilities. There are two piers and 
one marina located on the creek. The facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. New 
Work: Between June 24-28, 1975, the contract 
dredge Richmond removed 17,066 cubic yards at 
a cost of $51,381. 
Condition at end of fiscal year. Construction is 
scheduled for completion in FY 76. 
16. ROLLINSON CHANNEL, N.C. 
Location. The project is located about 3.5 miles 
northeast of Hatteras Inlet. (See Coast and 
Geodetic Survey Chart 1232.) 
Existing project. The authorized project 
provides for a channel 12 feet deep, 100 feet wide, 
and about 5.1 miles long from deep water in 
Pamlico Sound to and including a basin of the 
same depth, 80 to 150 feet wide, and 1,450 feet 
long at Hatteras; a rubble-mound breakwater on 
each side of the channel at the entrance to the 
basin; and a channel 10 feet deep and 100 feet 
wide from that depth in Hatteras Inlet gorge to 
Rollinson Channel, in the vicinity of the basin at 
Hatteras. The project was authorized by the 
River and Harbor Acts of August 30, 1935; March 
2, 1945; September 3, 1954; and October 23, 1962. 
For further details see Annual Report for 1961. 
Local cooperation. Complied with to date. 
Terminal facilities. Six waterfront facilities 
serve the channel, with a total frontage of 926 
feet. Existing facilities are adequate for present 
commerce. 
Operations and results during fiscal 
year. Maintenance: Engineering and design for 
pipeline dredging accomplished in previous year 
was $256. Environmental studies cost $2,044. 
Condition at end of fiscal year. The project was 
completed August 22, 1966. (For further details, 
see Annual Report for 1961.) 
17. SHALLOTTE RIVER, N.C. 
Location. A small stream in Brunswick County, 
N.C., rising in the large swamp country 
between Cape Fear and Waccamaw Rivers, 
known as Green Swamp. Stream is about 30 miles 
long and flows southerly into Atlantic Ocean and 
20 miles west of mouth of Cape Fear River. (See 
Coast and Geodetic Survey Chart 835.) 
Previous project. For details see page 1806 of 
Annual Report for 1915. 
Existing project. A channel 4 feet deep at mean 
low water and 36 feet wide from the mouth to 
town of Shallotte. Section under improvement is 9 
miles long. River is tidal, range varying from 5 
feet at mouth to 3 feet at Shallotte. Hurricane 
Hazel in 1954 caused a tide about 16 feet above 
mean sea level in the river at Shallotte Point. Project 
authorized by River and Harbor Acts of 
March 4, 1913, and January 21, 1917. 
Local cooperation. None required. 
Terminal facilities. A marine railway and 
shop at Shallotte Point and another in town of 
Shallotte with facilities for building and repairing 
boats up to about 60 feet long. On Shallotte 
River, there are 17 docks varying from 16 to 321 
6-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
feet of frontage, providing 1,334 feet of wharf and 
docking space. 
Operation and results during fiscal 
year. Maintenance: Between October 31 and 
November 24, 1974, the contract pipeline contract 
dredge Richmond removed 46,573 cubic 
yards from shoals at a cost of $83,254. Environmental 
studies cost $5,973. Project condition 
surveys cost $1,044. 
Condition at end of fiscal year. Project completed 
in 1929. 
18. SILVER LAKE HARBOR, N.C. 
Location. The project is located at the 
southwest end of Ocracoke Island, a portion of the 
Outer Banks on the southeast coast of North 
Carolina, separating Pamlico Sound from the 
Atlantic Ocean. (See Coast and Geodetic Survey 
Chart No. 1232.) 
Existing project. The authorized project 
provides for basin depths of 12 feet in Silver Lake 
Harbor; an entrance channel 12 feet deep and 60 
feet wide, from the basin to Teaches Hole 
Channel; a channel, 12 feet deep and 150 feet 
wide, from the entrance channel through Big 
Foot Slough Bar to the 12-foot contour in Pamlico 
Sound; a channel, 12 feet deep and 150 feet wide, 
from the entrance channel through Teaches Hole 
Channel to the gorge in Ocracoke Inlet; a channel, 
12 feet deep and 150 feet wide, across Bluff Shoal; 
and for rubble-mound training walls on the north 
and south sides of the entrance channel, 300 feet 
and 400 feet long, respectively. Mean tidal ranges 
are 1.9 feet in the throat of Ocracoke Inlet and 1 
foot at Ocracoke. Variations in the water surface 
of Pamlico Sound are generally due to winds and 
seldom exceed 1 or 2 feet above or below mean 
stage. Severe storms have raised the water surface 
as much as 7 feet above normal water level at 
Ocracoke. (See Table 6-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Twelve waterfront 
facilities serve the harbor. These facilities are 
adequate for existing commerce. 
Operations and results during fiscal 
!lear. Maintenance: Between June 8-17, 1975, the 
contract pipeline dredge Richmond removed 47,- 
337 cubic yards of shoals at a cost of $107,648. 
Engineering and design on prior year pipeline 
dtredging contract cost $2,838. Cost for U.S. 
snagboat Snell on prior year work was $724. Cost 
for the U.S. sidecasting dredge Merritt on prior 
year work was $782. Repairs to training walls 
and shore protection cost $8,242. Environmental 
studies cost $579. Condition and operation studies 
cost $10,400. 
Condition at end offiscal year. The project was 
completed July 28, 1970. (For further details see 
Annual Report for 1961.) 
19. SMITHS CREEK (PAMLICO 
COUNTY), N.C. 
Location. Smiths Creek rises in Pamlico County, 
flows generally southerly, and empties into 
Neuse River at the town of Oriental, 25 miles 
southeast of New Bern, N.C. It is about 5 miles 
long but navigable for only 2 or 3 miles above its 
mouth. (See U.S. Coast and Geodetic Survey 
Chart No. 538.) 
Existing project. This project provides for a 
rubblemound breakwater starting at a point on 
the mainland in Oriental and extending 800 feet 
southwesterly; and an entrance channel in 
Smiths Creek, 10 feet deep and 150 feet wide, 
from that depth in Neuse River to and including a 
basin, generally parallel to the breakwater 10 
feet deep, 300 feet wide, and 800 feet long at 
Oriental. The total length of the channel and 
basin is about 5,000 feet. Variations in water level 
due to winds seldom exceed 2 feet above or below 
mean stage. Observations of 4 years duration 
show that the extreme range of wind tides is 8.3 
feet. The existing project was authorized by the 
River and Harbor Acts of June 25, 1910 and 
September 3, 1954. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 16 wharves in 
this harbor, all of timber construction with pile 
foundations. They have a frontage varying from 6 
to 40 feet, the total frontage being about 400 feet. 
None have rail connections. One wharf was built 
by the town and is to be maintained in perpetuity 
as a public wharf. The remaining wharves are all 
privately owned but are generally open to the 
public when not required by their owners. The 
facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
I/ear. Maintenance: Environmental studies cost 
$2,300. Project condition surveys cost $1,659. 
Condition at end of fiscal year. The existing 
project was completed in March 1956. 
20. STUMPY POINT BAY, N.C. 
Location. On Southeastern side of the 
mainland, Dare County, N. C. (See Coast and 
Geodetic Survey Chart 1229.) 
Existing project. A channel 75 feet wide and 10 
feet deep from that depth in Pamlico Sound to a 
basin in the harbor at Lake Worth, 75 to 100 feet 
wide, 550 feet long and 10 feet deep, plus an 
irregularly shaped area providing access to the 
public wharf, together with protective 
6-10

WILMINGTON, N.C., DISTRICT 
breakwaters at entrance to the harbor. Project 
was authorized by 1948 River and Harbor Act 
and under Section 107, 1960 River and Harbor 
Act. 
Local cooperation. Fully complied with. 
Terminal facilities. Bulkheads in existing 
basin provide about 550 linear feet of berthing 
space; and a wholesale fishhouse provides about 
250 feet. Part of the space along the bulkheads is 
publicly owned. Facilities are considered adequate 
for existing commerce, but any appreciable 
increase will require additional facilities. 
Operations and results during fiscal 
year. Maintenance: Environmental studies cost 
$2,300. 
Condition at end of fiscal year. Project completed 
on September 20, 1967. (For further 
details, see Annual Report for 1966.) 
21. WATERWAY CONNECTING 
PAMLICO SOUND AND 
BEAUFORT HARBOR, N.C. 
Location. The project is located in Core Sound, 
west of the outer banks of eastern North Carolina. 
(See Coast and Geodetic Survey Charts Nos. 420 
and 1233.) 
Existing project. The authorized project 
provides for a through channel to Core Sound 7 
feet deep and 75 feet wide from Pamlico Sound to 
Beaufort Harbor; an alternative route of the same 
dimensions through Back Sound by way of 
channels at the east and west ends of Harkers 
Island; a channel 7 feet deep and 70 feet wide 
from the through channel to the local harbor at 
Cedar Island, including the authorized passage 
and future maintenance of a channel through the 
existing private basin, and an access channel 6 
feet deep, 50 feet wide and about 400 feet long to a 
basin the same depth, 60 feet by 100 feet; a 
channel 7 feet deep and 75 feet wide from the 
through channel to Atlantic; a channel 7 feet deep 
and 75 feet wide, with a basin 200 feet by 500 feet, 
the same depth, at Sealevel; a channel 5 feet deep 
and 75 feet wide, with basin 150 feet by 130 feet, 
the same depth, at Davis; a channel 6 feet deep 
and 60 feet wide, with a basin 100 feet by 600 feet, 
the same depth, at Marshallberg; an entrance 
channel 6 feet deep and 60 feet wide, from Back 
Sound to a harbor of refuge 120 feet by 250 feet, 
the same depth, in Brooks Creek at the west end of 
Harkers Island; and a channel 7 feet deep and 70 
feet wide, from the existing side channel at Atlantic, 
N.C., to the mouth of Little Port Brook; thence 
7 feet deep and 50 feet wide, along the Brook to a 
basin 600 feet long, 180 feet wide, and 7 feet deep, 
with a breakwater, beginning at a point between 
the mouth of Little Port Brook and White Point, 
running along the channel approximately 2,000 
feet. Plane of reference is mean low water. The 
length of the authorized channels is about 50.6 
miles. (See Table 6-B for authorizing legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Sixteen small wharves 
serve the waterway. Additional facilities are 
needed along Core Sound. 
Operations and results during fiscal 
year. Maintenance: Between March 12-22, 1975 
the contract dredge Richmond removed 46,493 
cubic yards from shoals at Atlantic Harbor of 
Refuge at a cost of $84,693. Environmental 
studies cost $11,307. Project condition surveys 
cost $10,255. 
Condition at end of fiscal year. The project was 
completed in July 1970 except for Atlantic which 
was completed September 25, 1972. (For further 
details, see Annual Report for 1961.) 
22. WATERWAY CONNECTING 
SWANQUARTER BAY WITH 
DEEP BAY, N.C. 
Location. On north side of Pamlico Sound, 
about 10 miles east of mouth of Pamlico River. 
(See U.S. Coast and Geodetic Survey Chart No. 
1231.) 
Existing project. A channel 60 feet wide and 8 
feet deep from Deep Bay through present 
waterway to Swanquarter Bay, and thence 
through Swanquarter Canal to a basin of the 
same depth, about 500 feet long and 60 to 300 feet 
wide, at head of canal. Project was authorized by 
River and Harbor Acts of June 25, 1910, and 
March 2, 1945. Cost of completed project was 
$110,799. For further details see Annual Report 
for 1950. 
Local cooperation. Fully complied with. 
Terminal facilities. Five waterway facilities 
serve the waterway, with a total frontage of 205 
feet. Existing facilities are adequate for present 
commerce. 
Operations and results during fiscal 
year. Maintenance: Environmental studies cost 
$700. 
Condition at end of fiscal year. Project was 
completed January 24, 1964 
23. WATERWAY-NORFOLK, VA., TO 
SOUNDS OF N.C. 
Location. In southeastern Virginia and 
northeastern North Carolina; from Norfolk, Va., 
to Pamlico Sound, N. C. (See U. S. Coast and 
6-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Geodetic Survey Charts Nos. 1227-1229, and 
1231.) For further description, see Annual Report 
for 1932 (Norfolk, Va., District). 
Existing project. A channel 10 feet deep and 80 
feet wide in Deep Creek, Va.; a channel 9 feet deep 
and 50 feet wide in Turners Cut, Pasquotank 
River and Croatan Sound, N. C.; and 
maintenance of Dismal Swamp Canal. Project 
was authorized by River and Harbor Acts of 
March 3, 1899, March 3, 1925, and June 26, 1934. 
(For further details, see Annual Report for 1946.) 
Local cooperation. None required. 
Terminal facilities. A total of 26 waterfront 
facilities serve the waterway, not including 
facilities in Norfolk Harbor, at northern end of 
waterway. Facilities are adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Preparation of environmental 
impact statement cost $700. 
Condition at end of fiscal year. Project is complete. 
24. WILMINGTON HARBOR, N.C. 
Location. The project is located on the Cape 
Fear River, on southeast coast of North Carolina, 
between the Atlantic Ocean and Wilmington, 
North Carolina. (See Coast and Geodetic Survey 
Chart No. 426.) 
Previous projects. For details, see page 1804 of 
Annual Report for 1915 and page 533 of Annual 
Report for 1938. 
Existing project. The authorized project 
provides for a channel 40 feet deep and 500 feet 
wide from the Atlantic Ocean through the ocean 
bar and entrance channels to Southport, thence 
38 feet deep and 400 feet wide to the upper end of 
the anchorage basin (foot of Castle Street) at 
Wilmington, thence 32 feet deep and 400 feet 
wide, to Hilton Bridge over Northeast (Cape 
Fear) River; a 38-foot-deep anchorage basin at 
Wilmington; a 32-foot-deep turning basin opposite 
the principal terminals; a channel 12 feet 
deep and 100 feet wide, about 3 miles long, in 
Cape Fear River; and a channel 25 feet deep and 
200 feet wide from Hilton Bridge over Northeast 
(Cape Fear) River to a point 1.66 miles above, including 
a turning basin of the same depth, 700 
feet wide and 500 feet long, at a point 1.25 miles 
above the bridge. The project was authorized by 
River and Harbor Acts of July 3, 1930; March 2, 
1945; May 17, 1950; October 23, 1962; and March 
10, 1964; under Section 107 of the 1960 River and 
Harbor Act. (For further details of authorization, 
see 1962 Annual Report.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Forty-three principal 
wharves, piers, and docks at port of Wilmington, 
with a berthing space of about 20,000 linear feet 
serve the harbor. These facilities handle general 
cargo and petroleum products. For further 
details, see Port Series No. 12, part 2, revised 
1971, Corps of Engineers. 
Operations and results during fiscal year. New 
work: Work in connection with a claim of changed 
conditions resulted in $252 less cost. Maintenance 
between January 31 and February 28, 1975, the 
U. S. hopper dredge Goethals removed 789,729 
cubic yards from shoals in the Cape Fear Bar 
Channel at a cost of $789,668. Between July 1 and. 
August 25, 1974 the contract dredge Cherokee 
removed 614,225 cubic yards from shoals in the 
Anchorage Basin at a cost of $348,594. From May 
28 through June 30, 1975, the contract dredge 
Enterprise removed 206,803 cubic yards from 
shoals in the river channel at a cost of $246,223. 
During intermittent periods the U.S. snagboat 
Snell maintained survey and dredging ranges at 
a cost of $7,346. Cost on prior year dredging work 
was $3,407. Engineering and design for 
rehabilitation of Eagle Island Dikes cost $43,332. 
Environmental studies cost $28,064. Condition 
and operation studies cost $127,484. Contributed 
funds in the amount of $172,425 were expended 
for diking. 
Condition at end of fiscal year. Project completed 
July 1973. (For further details, see Annual 
Report for 1962.) Total cost of the existing project 
to June 30, 1975, was $34,171,799 of which $13,- 
720,959 was for new work and $20,450,840 was 
for maintenance, including $295,425 contributed 
funds. 
25. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 6-C.) 
26. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
(See Table 6-D.) 
27. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
(See Table 6-E.) 
Beach Erosion Control 
28. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 6-F.) 
6-12

WILMINGTON, N.C., DISTRICT 
Flood Control 
29. BLACK RIVER, HARNETT 
COUNTY, N.C. 
Location. The river rises near Angier in 
Harnett County, N. C., and flows in a southerly 
direction about 25 miles to its confluence with 
South River. (See Army Map Service quadrangle 
sheet 5254, Fayetteville, N. C.) 
Existing project. The project provides for 5.5 
miles of channel excavation on Black River, 
beginning at a point 8,000 feet below County Road 
1780, with a 35-foot bottom width to the Durham 
and Southern Railroad. Estimated Federal construction 
cost is $261,000 (1973). The project was 
authorized by the Chief of Engineers on 
February 9, 1968, under Section 205, 1948 Flood 
Control Act, as amended. 
Local cooperation. Local interests must 
provide all lands, easements, rights-of-way, utility 
relocations and alterations, and highway or 
highway-bridge construction and alterations 
necessary for project construction; hold and save 
the United States free from damages; and maintain 
and operate project after completion. Estimated 
cost to local interests for rights-of-way is 
$15,000. Formal assurances have been requested. 
Operations and results during fiscal year. New 
work: Detailed engineering and design cost 
$7,205. Environmental studies cost $657. 
Condition at end of fiscal year. Preconstruction 
planning is complete. 
30. BRUNSWICK COUNTY BEACHES, 
N.C. (CAPE FEAR TO NORTH 
CAROLINA-SOUTH CAROLINA 
STATE LINE) 
Location. The project is in Brunswick County, 
on the South Atlantic coast of North Carolina, 
between the mouth of the Cape Fear River and 
North Carolina-South Carolina State Line. (See 
Coast and Geodetic Survey Charts 1236 and 
1237.) 
Existing project. The project provides for integral 
construction of a dune near the building 
line, with a crown width of 25 feet, at an elevation 
of 15 feet above mean sea level, and a 50-foot 
beach berm at elevation 12, along 3,600 feet of 
Yaupon Beach, 43,600 feet of Long Beach, 40,000 
feet of Holden Beach, 28,000 feet of Ocean Isle 
Beach, and 6,000 feet of Sunset Beach; and 
Federal participation in the cost of beach 
nourishment for a period of 10 years. The project 
also provides for 11 groins at Long Beach, 12 at 
Yaupon Beach, and a rock revetment on the sound 
side of Lockwoods Folly Inlet. Approved estimated 
cost for new work (1973) is $42,000,000. A 
request for reclassification to the "inactive" 
category was made in June 1975. The project was 
authorized by the 1966 Flood Control Act (H. D. 
511, 89th. Cong., 2d sess.). 
Local cooperation. Local interests must: (a) 
provide all lands, easements, and rights-of-way, 
including borrow areas, necessary for construction; 
(b) accomplish all relocations and alterations 
to sewage and drainage facilities, buildings, 
streets, utilities, and other structures; (c) hold 
and save the United States free from damages; (d) 
contribute 30 percent of the first costs allocated to 
hurricane protection and 50 percent of those 
allocated to beach stabilization, with credit allowed 
for (a) and (b), currently estimated at $14,800,- 
000; (e) provide periodic nourishment for preservation 
of the protective beach as may be required 
to serve the intended purposes; (f) maintain the 
protective works after completion; (g) provide 
and maintain public ownership, during the 
economic life of the project, of an adequate width 
of beach for public use, with acceptable access, 
parking areas, and other facilities necessary for 
realization of the benefits upon which Federal 
participation is based; (h) adopt and enforce 
ordinances to provide for preservation of the 
improvement and its protective vegetation; (i) 
control water pollution to the extent necessary to 
safeguard the health of bathers; and (j) adequately 
inform affected interests that the project will 
not provide protection against ocean-storm 
surges and wave action greater than those which 
accompanied Hurricane Hazel on October 15, 
1954, nor will the protection have any substantial 
effect on storm tides in the sounds and other 
waters adjacent to the barrier islands, and that, 
during hurricanes and severe northeast storms, 
all normal precautions, including evacuation, 
must be taken as advised by appropriate authority.
Operations and results during fiscal year. New 
work: Engineering and design cost $53,032. Due 
to the defeat of the major portion of the project in 
a public referendum, $116,508 in advance contributed 
funds must be refunded. In order to accomplish 
this, $114,132 in charges were 
transferred from contributed funds to construction 
funds. The refund will be made in FY 76. 
These actions resulted in Federal expenditures of 
$167,164 and contributed funds cost of -$114,132. 
Condition at end of fiscal year. Preconstruction 
planning is complete. Construction is unlikely 
since construction of the major portion of the 
project was defeated in a public referendum by 
the town of Long Beach. 
31. CAPE FEAR RIVER BASIN, N. C. 
Location. Work covered by this project consists 
of a series of dams and reservoirs on tributaries of 
6-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
the Cape Fear River in North Carolina within a 
radius of 100 miles from Raleigh, North Carolina. 
(See Geological Survey Map of North Carolina.) 
Existing project. Public Law 88-253, approved 
December 30, 1963, authorized three principal 
dams and reservoirs and a series of smaller reservoirs 
on tributaries of the Cape Fear River in accordance 
with the comprehensive plans in House 
Document 508, 87th Congress, 2d session. The act 
also provides that the appropriate agencies of the 
Departments of the Army and Agriculture shall 
conduct joint investigations and surveys and 
prepare a report on the upper tributaries of the 
Cape Fear River in the interest of watershed 
protection and flood prevention, and the conservation, 
development, utilization, and disposal of 
water. The report is to be prepared and submitted 
in compliance with provisions of Public Law 87- 
639. A list of the dams and reservoirs included in 
the comprehensive plan follows. Estimates of cost 
as given are based on 1960 price levels, except the 
ones for B. Everett Jordan Dam and Lake, 
Randleman, and Howards Mill Lakes, which 
were revised in 1975. These three projects have 
been authorized for construction in accordance 
with the above authorization. The joint study, to 
be accomplished by the Departments of the Army 
and Agriculture, is underway. 
Local cooperation. Requirements are given in 
the individual project reports. (See Table 6-G on 
Dams and Reservoirs.) 
31A. B. EVERETT JORDAN DAM AND 
LAKE, N.C. (FORMERLY NEW HOPE 
LAKE, N.C.) 
Location. The project is located on the Haw 
River, N.C., 4.3 miles above its mouth, and 2.5 
miles north of Moncure, N.C. 
Existing project. The project provides for an 
earth dam 1,330 feet long with a maximum 
height of 112 feet above the streambed, an uncontrolled, 
unpaved chute spillway, and a controlled 
19-foot-diameter outlet structure. Some saddle 
dikes are required beyond the spillway. The 
reservoir will have a gross storage capacity of 
778,000 acre-feet, of which 543,000 acre-feet will 
be for flood control and a conservation pool of 
235,000 acre-feet for water-quality control, water 
supply, and sedimentation. The reservoir will be 
operated as a unit of a coordinated system for control 
of floods in the Cape Fear River Basin and for 
water supply, water-quality control, and other 
purposes. Estimated cost for new work is $79,- 
300,000 (1975), consisting of $23,768,500 for construction, 
including $2,680,000 presently 
allocated to water supply to be paid for in the 
future by local interests, and $55,531,500 for 
lands and damages, including highway, railroad, 
and utility relocations. The existing project was 
authorized by Public Law 88-253 approved 
December 30, 1963 (H. D. 508, 87th Cong., 2d 
sess.). 
Local cooperation. Local interests must protect 
downstream channels from encroachments and 
obstructions which would adversely affect operation 
of the project; reimburse the Federal Government 
for all costs allocated to municipal and industrial 
water supply, presently estimated at 
$2,680,000 and bear all annual costs for operation, 
maintenance, and major replacements 
allocated to municipal and industrial water supply, 
an amount presently estimated at $7,000 annually. 
Assurances that these obligations for 
water storage would be assumed have been 
received from the Department of Natural and 
Economic Resources, State of North Carolina. 
Operations and results during fiscal year. New 
work: Real estate acquisition continued at a cost 
of $2,332,300. Construction of U.S. 64 was completed 
at a cost of $253,800. Relocation of N.C. 
Roads 1938, 1939, 1906 and 1907 was completed 
at a cost of $332,800. Relocation of N.C. Roads 
1008B, 1743 and 1008C continued at a cost of $1,- 
339,700. Construction of the dam continued at a 
cost of $1,760,800. Status of plans and 
specifications: N.C. Road 751 at Northeast Creek, 
Indian Creek, Lick Branch and 1731, 97 percent; 
N.C. Road 1715 and 1941, 100 percent; N.C. Road 
1726, 99 percent; N.C. Road 1717, 96 percent; 
N.C. Road 1141, 100 percent; N.C. Road 1110, 98 
percent; N.C. Road 1900, 93 percent; Group I and 
II, clearing 80 percent; Group I recreation 
facilities and roads, 80 percent and Group II 
recreation facilities and roads, 100 percent. Total 
Federal expenditures were $6,857,395 and $110,- 
331 contributed funds were expended. 
Condition at end of fiscal year. U.S. 64 relocation 
is 100 percent complete. Norfolk Southern 
Railway relocation is 100 percent complete. 
Relocation of N.C. Roads 1008B and 1743 is 88 
percent complete. Relocation of N.C. Roads 1938, 
1939, 1906 and 1907 are 100 percent complete. 
Relocation of 1008C is 29 percent complete. Contract 
for dam is 99 percent complete. 
31B. HOWARDS MILL LAKE, N. C. 
Location. The project is located on Deep River, 
N. C., about 35 miles south of Greensboro, N. C., 
and about 15 miles southeast of Asheboro, N. C. 
The damsite is in Moore County about 1 mile 
below the Randolph County line, and the main 
body of the reservoir will lie mostly in Randolph 
County. 
Existing project. The authorized project 
provides for the construction of an earth dam 
2,765 feet long with a maximum height of 106 feet 
6-14

WILMINGTON, N.C., DISTRICT 
above the streambed to create a reservoir with 
gross storage of 233,000 acre-feet, consisting of 
159,000 acre-feet for flood control, 50,000 acrefeet 
for conservation, and 24,000 acre-feet for 
sedimentation. Howards Mill Lake is the third 
project of the comprehensive plan of development 
for the Cape Fear River basin, providing reservoir 
storage for flood control and recreation. The 
project items may be modified during detailed 
preconstruction planning. Estimated cost of new 
work is $23,800,000 (1975), consisting of $13,790,- 
000 for construction (including $1,071,000 
presently allocated to general recreation and fish 
and wildlife to be paid for in the future by local interests) 
and $10,010,000 for lands and damages,. 
including relocations. The existing project was 
authorized by the 1968 Flood Control Act (H. D. 
343, 90th Cong., 2d sess.) 
Local cooperation. Local interests must: (a) In 
accordance with the Federal Water Project 
Recreation Act, administer project land and 
water areas for recreation and fish and wildlife 
enhancement; pay, contribute in kind, or repay 
(which may be through user fees) with interest, 
one-half of the separable costs allocated to recreation 
and one-fourth of the separable cost allocated 
to fish and wildlife enhancement, presently estimated 
at $1,071,000; and bear all costs of operation, 
maintenance, and replacements of recreation 
and fish and wildlife facilities, the average 
annual amount presently estimated at $61,000; 
(b) prevent encroachment on downstream 
channels to the extent needed to provide effective 
reservoir operation; and (c) hold and save the 
United States free from damages due to waterrights 
claims resulting from construction and 
operation of the project. 
Operations and results during fiscal year. New 
work: Advanced engineering and design cost 
$134,172. 
Condition at end offiscal year. The project is in 
the preconstruction planning stage. 
31C. RANDLEMAN LAKE, N. C. 
Location. The project is located on Deep River, 
N. C., about 15 miles south of Greensboro and 
about 2 miles upstream from the town of 
Randleman. The damsite and about two-thirds of 
the reservoir would lie in Randolph County. The 
upper one-third of the reservoir would lie in 
Guilford County. 
Existing project. The authorized project 
provides for construction of an earth dam 2,400 
feet long with a maximum height of 110 feet 
above the streambed to create a reservoir with 
gross storage of 105,000 acre-feet, consisting of 
45,000 acre-feet for flood control and a conservation 
pool of 60,000 acre-feet for water supply, 
water-quality control and sedimentation. 
Randleman Lake is the second project of the comprehensive 
plan of development for the Cape Fear 
River Basin, providing reservoir storage for flood 
control, water supply, water-quality control, and 
recreation. The project items may be modified 
during detailed preconstruction planning. Estimated 
cost of new work is $29,300,000 (1975), 
consisting of $13,600,000 for construction 
(including 3,525,000 presently allocated to water 
supply and $1,500,000 allocated to general 
recreation and fish and wildlife to be paid for in 
the future by local interests) and $15,700,000 for 
lands and damages, including relocations. The 
existing project was authorized by the 1968 Flood 
Control Act (H. D. 343, 90th Cong., 2d sess.). 
Local cooperation. Local interests must: (a) In 
accordance with the Federal Water Project 
Recreation Act, administer project land and 
water areas for recreation and fish and wildlife 
enhancement; pay, contribute in kind, or repay 
(which may be through user fees), with interest, 
one-half of the separable costs allocated to recreation 
and one-fourth of the separable cost allocated 
to fish and wildlife enhancement, presently estimated 
at $1,500,000; and bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildife lands and facilities, presently 
estimated at $125,000 annually; (b) pay to the 
United States all costs allocated to water supply, 
in accordance with the Water Supply Act of 1958, 
as amended, presently estimated at $3,525,000 
for construction and $18,000 annually for operation, 
maintenance, and major replacements; (c) 
hold and save the United States free from 
damages due to water-rights claims resulting 
from construction and operation of the project; (d) 
prevent encroachment on downstream channels 
to the extent needed to provide effective reservoir 
operation; (e) undertake all practical measures to 
control pollution of the stream which is subject to 
low-flow augmentation by adequate treatment or 
other methods of controlling wastes at their 
source; and (f) exercise to the full extent of their 
legal capability control against removal of 
streamflow made available for water quality control. 
Reasonable assurances that the requirements 
will be fulfilled have been received. 
Operations and results during fiscal year. New 
work: Advanced engineering and design cost 
$382,145. 
Condition at end offiscal year. The project is in 
the preconstruction planning stage. 
32. CAROLINA BEACH AND 
VICINITY, N. C. 
Location. The project is in New Hanover County, 
about 15 miles southeast of Wilmington, N.C., 
on the peninsula which separates lower Cape 
6-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Fear River from the Atlantic Ocean. (See Coast 
and Geodetic Survey Map 834.) 
Existing project. The authorized project 
provides for construction of a dune with a base 
generally bordering at or near the building line, 
with a crown width of 25 feet at an elevation of 15 
feet above mean low water, together with integral 
construction of a beach berm with a crown width 
of 50 feet at elevation 12, extending about 25,800 
feet from the northern limits of Carolina Beach to 
the southern limits of Kure Beach; initial deposition 
of sufficient material north of Carolina 
Beach to serve as a feeder beach; and Federal participation 
in the cost of beach nourishment for a 
period not to exceed 10 years from the year of initial 
placement. The area South of Carolina Beach 
was reclassified to the inactive category, 
February 1975. Approved estimated cost for new 
work (1975) is $13,100,000. The project was 
authorized by the 1962 Flood Control Act (H. D. 
418, 87th Cong., 2d sess.). 
Local cooperation. Local interests must: (a) 
Provide lands, easements, and rights-of-way for 
construction; (b) make required relocations and 
alterations of streets, utilities, or structures; (c) 
contribute 37.9 percent of the total first cost, with 
credit allowed for (a) and (b); (d) hold the United 
States free from damages; (e) maintain all works 
after completion; (f) maintain continued public 
ownership of the shore; (g) adopt and enforce appropriate 
ordinances to provide for preservation 
of improvement and its protective vegetation; (h) 
control water pollution to extent necessary to 
safeguard health of bathers; and (i) at least annually 
inform iinterests affected that project will 
not provide any substantial protection from ocean 
surges higher in elevation than that of Hurricane 
Hazel, October 15,1954. Requirements have been 
fulfilled to date for the town of Carolina Beach 
portion of the project only. 
Operations and results during fiscal year. New 
work: Economic reanalysis and environmental 
studies cost $37,153 3 
Conditionat endof fiscal year. Construction of 
the project is about 19 percent complete. 
33. JOYCE CREEK, CAMDEN 
COUNTY, N. C. 
Location. Joyce Creek rises in the northeastern 
part of Camden County, N. C., and flows generally 
southward for about 10 miles to Turners Cut 
near South Mills, North Carolina. (See Coast and 
Geodetic Survey Chart 1227 and Army Map Service 
quadrangle sheet, South Mills, N. C.) 
Existing project. The project provides for excavating 
a channel 40 feet wide, from the confluence 
with Turners Cut to County Road 1224 at 
Tar Corner, 3.9 miles; thence a channel, 30 feet 
wide, to the confluence with Mill Run and 
Cypress Run, 1.7 miles; thence on Cypress Run, a 
channel, 10 feet wide, to County Road 1233, 1.8 
miles; and on Mill Run, a 10-foot-wide channel 
from confluence with Joyce Creek to County Road 
1232, 2.2 miles; a total of 9.6 miles. Estimated 
Federal construction cost (1974) is $213,000. The 
project was approved by the Chief of Engineers 
on March 29,1967, under Section 205 of the 1948 
Flood Control Act, as amended. 
Local cooperation. Local interests must 
provide all lands, easements, rights-of-way, utility 
relocations and alterations, and highway or 
highway-bridge construction and alterations 
necessary for construction; hold the United States 
free from damages; maintain and operate the project 
after completion; prevent future encroachment; 
provide a cash contribution of 21.5 percent 
of construction costs, now estimated at $58,300; 
and accomplish associated drainage works 
necessary to realize the benefits from the Federal 
improvement. Local interests have given 
assurances that they will initiate procedures to 
form a drainage district. 
Operations and results during fiscal year. New 
work: Detailed engineering and design cost $4,- 
232. Environmental studies cost $6,130. 
Condition at end of fiscal year. Preconstruction 
planning has been completed. 
34. LITTLE ROCKFISH CREEK, 
HOPE MILLS, N.C. 
Location. Little Rockfish Creek originates 
northwest of Hope Mills, N.C. and flows in a 
southeasterly direction for about 18.2 miles to its 
junction with Rockfish Creek approximately 1 
mile southeast of Hope Mills. (See Army Map Service 
map for Saint Pauls, N.C., Sheet 5253 IV). 
Existing Project. The existing project would 
consist of a gabion structure constructed along 
250 feet of the bank and built to a height of 15 feet 
above the streambed elevation. Backfill would be 
placed behind the gabion to tie in with the existing 
bank. Estimated Federal project cost is 
$100,000. The project was approved by the Chief 
of Engineers in September 1974, under Section 
14 of the 1946 Flood Control Act as amended. 
Local cooperation: Local interests will provide 
all lands, easements, rights-of-way, utility 
relocations and alterations and highway construction 
and alterations necessary for project 
construction; hold and save the United States free 
from damages and adjust all claims concerning 
water rights; maintain and operate the project 
after completion without cost to the United 
States, in accordance with regulations prescribed 
by the Secretary of the Army; prevent future en- 
6-16

WILMINGTON, N.C., DISTRICT 
croachment; contribute, in cash, all construction 
costs, if any, in excess of the $250,000 Federal 
participation statutory limit and encourage landowners 
to adopt land treatment measures adjacent 
to the project to minimize or prevent further 
bank erosion. 
Operations and results during fiscal 
year. New work: Engineering and design was 
initiated at a cost of $4,244. This is the first report 
since authorization. 
Condition at end of fiscal year. Preconstruction 
planning is underway. 
35. MACKAY CREEK, N. C. 
Location. Mackay Creek, also known locally as 
Kendricks Creek, originates in East Dismal 
Swamp, and flows northward for about 7.3 miles 
through Washington County into Albemarle 
Sound. (See U. S. Geological Survey quadrangle 
sheets, Roper North and Roper South, N. C.) 
Existing project. The original project provides 
for clearing and snagging Mackay Creek from 
County Road 1300 upstream 3.2 miles thence excavating 
a channel 60 feet wide, depths 10 to 15 
feet, 2.8 miles to its confluence with Swinson 
Swamp, a total of 6.0 miles; and excavating a 
channel 20 feet wide, depths 5 to 6 feet, along 
Beaverdam Branch from its mouth to County 
Road 1329, a distance of 2.7 miles. The supplement 
to the project, which has been combined 
with the original project described above, consists 
of excavating a 30-foot-bottom-width 
channel along Upper Mackay Creek, from the 
confluence of Swinson Swamp to County Road 
1127, a distance of about 4.1 miles; and excavating 
a 25-foot-bottom-width channel along 
No. 4 canal, from County Road 1127 to Canal 'C' a 
distance of about 2.5 miles. Estimated project 
cost (1974) is $1,043,100, including Federal cost of 
$550,200 and non-Federal costs of $492,900 
($134,900 cash contribution; $153,000 rights-ofway, 
legal fees and roadway structures; and 
$205,000 auxiliary drainage works). The project 
was approved by the Chief of Engineers in 
December 1966 (Detailed Project Report) and on 
June 23, 1969 (Supplement to the Detailed Project 
Report), under Section 205 of the 1948 Flood 
Control Act, as amended. 
Local cooperation. Local interests will provide 
all lands, easements, rights-of-way, relocations 
and alterations, and highway or highway-bridge 
construction necessary; hold and save the United 
States free from damages; maintain and operate 
project; prevent future encroachment; contribute, 
in cash, 16.4 percent of the channel construction 
cost (for both Upper and Lower Mackay 
Creek); accomplish associated drainage works 
necessary to realize the benefits from the Federal 
improvement; and encourage individual land 
owners to adopt land-use treatment measures to 
minimize the deposition of spoil in the channels. 
Operations and results during fiscal year. New 
work: Detailed engineering and design cost 
$2,353. Environmental studies cost $2,035. 
Condition at end of fiscal year. Preconstruction 
planning is complete. 
36. NEUSE RIVER BASIN, N. C. 
Location. Works covered by this project consist 
of a series of dams and reservoirs in the Neuse 
River Basin in North Carolina within a radius of 
50 miles from Raleigh, North Carolina. (See 
Geological Survey Map of North Carolina.) 
Existing project. The Flood Control Act of 1965 
authorized construction of the Falls project as the 
key project in the recommended general plan of 
development of the Neuse River Basin. The plan 
will serve as a guide for immediate and future 
development of the basin's water resources as set 
forth in House Document 175, 89th Congress, 1st 
Session. A list of projects included in the general 
plan of development follows. Estimated costs as 
given are based on 1963 price levels, except for 
Falls Lake which was revised in 1975. (See Table 
6-G on Dams and Reservoirs.) 
36A. FALLS LAKE, N. C. 
Location. The project is on the Neuse River, 
about 10 miles north of the City of Raleigh, North 
Carolina. 
Existing project. The authorized project 
provides for an earth dam 1,900 feet long with a 
maximum height of 92 feet above streambed. The 
dam will have a 30-foot top width. An uncontrolled 
chute spillway, 100-feet wide, will be 
located in the east abutment. The reservoir will 
have a gross storage capacity of 397,000 acre-feet, 
of which 243,000 acre-feet will be for flood control, 
45,000 acre-feet for water-supply for the city 
of Raleigh, 71,000 acre-feet for water-quality control, 
and 38,000 acre-feet for sediment storage. 
The reservoir will be operated as the initial unit of 
a coordinated system for control of floods in the 
Neuse River Basin for water supply, water quality 
control, recreation, and other purposes. Project 
items may be modified in detailed planning. Estimated 
cost of new work is $84,200,000 (1975), 
consisting of $23,450,000 for construction 
(including $7,436,000 presently allocated to 
water supply and $4,851,000 for recreation and 
fish and wildlife enhancement to be paid for in the 
future by local interests) and $60,750,000 for 
lands and damages, including highway, railroad, 
and utility relocations. The project was authorized 
by the 1965 Flood Control Act (H. D. 175, 89th 
Cong., 1st sess.). 
6-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Local interests must prevent 
encroachment on downstream channels that 
would interfere with the operation of the reservoir; 
pay the United States, in accordance with 
the Water Supply Act of 1958, as amended, the 
entire amount of construction cost allocated to 
water supply, presently estimated at $7,436,000, 
and entire amount of operation, maintenance, 
and replacement costs allocated to water-supply, 
presently estimated at $53,000 annually, the final 
amounts to be determined after actual costs are 
known; administer project land and water areas 
for recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay (which may be 
through user fees), with interest, one-half of the 
separable cost of the project allocated to recreation 
and one-fourth of the separable cost allocated 
to fish and wildlife enhancement, the amount involved 
currently being estimated $4,851,000, 
and, bear all costs of operation, maintenance, and 
replacement of recreation and fish and wildlife 
lands and facilities, the amount involved currently 
being estimated at $91,000 on an average annual 
basis. Formal assurances have been requested. 
The N. C. Department of Natural and 
Economic Resources has been authorized by an 
act of legislation to assure payment of all non- 
Federal costs allocable to water supply in all 
Federal projects as required by law. The State 
will require repayment of water supply costs, by 
the users. The State of North Carolina signed an 
agreement on August 13, 1971, to cost share in 
the construction of recreational facilities and to 
operate and maintain the recreational and fish 
and wildlife features of the project. 
Operations and results during fiscal year. New 
work: Wilmington District has overall responsibility 
for the project, with Savannah District 
serving as planning design agent. Wilmington 
District retains the responsibility for reservoir 
mapping, master and recreation planning, reservoir 
clearing and mosquito control, and highway 
and utility relocations. Land acquisition was continued 
at a cost of $3,655,400. Preparation of 
design memoranda for the land requirements 
plan is 100 percent complete; dam and spillway, 
100 percent; outlet works, 100 percent except for 
revisions; I-85 relocation, 100 percent except for 
revisions; Highway 98 relocation, 100 percent; 
N. C. Highway 50 relocation, 100 percent; access 
road, 100 percent; real estate, 100 percent; clearing, 
100 percent; relocation of SR, 100 percent; 
railroad relocations, 100 percent; power line 
relocations, 100 percent; telephone line 
relocations, 100 percent; public service gas line 
relocations, 70 percent; Raleigh raw water lines, 
100 percent; secondary roads relocation, 100 percent 
and construction procedure and diversion 
plan; 100 percent. Revisions to the general design 
memorandum are complete. Plans and 
specifications for the access road are complete; 
dam, spillway and outlet works, 85 percent; SR 
2010, complete except for revisions; N.C. 50, 90 
percent and SR 2002 and 1005, one percent. Total 
Federal cost was $4,191,291. 
Condition at end of fiscal year. Project is in the 
construction stage. 
37. OCRACOKE ISLAND, N.C. 
Location. The project is located on Ocracoke 
Island, a portion of the Outer Banks on the 
southeast coast of North Carolina, separating 
Pamlico Sound from the Atlantic Ocean. (See 
U.S. Coast and Geodetic Survey Chart 1232). 
Existing project. The project provides for: (a) 
Protection of the ocean frontage from hurricane 
and erosion damage, a beach fill with a berm 50 
feet wide at an elevation of 7 feet above mean sea 
level in front of a dike with a top width of 25 feet at 
an elevation of 11 feet above mean sea level, a 
feeder beach near the north end of the island, 
periodic nourishment for an initial period of 10 
years, sand fences, and (b) restoration and 
stabilization of the Ocracoke Village frontage, 
beach fill to provide a berm with top elevation 
equal to that of the existing bank, but not exceeding 
7 feet above mean sea level, vegetation 
and drainage facilities, and periodic nourishment 
for an initial period of 10 years. The sound-shore 
portion of the project was placed in the "inactive" 
category on 1 February 1971. The remaining portion 
was reclassified to the "inactive" category 
November 1974. Estimated total project cost is 
$9,300,000 (1974), including Federal cost of $8,- 
940,000 and non-Federal cost of $360,000. The 
project was authorized by the Flood Control Act 
of 1965 (H. D. 109, 89th Cong., 1st sess.). 
Local cooperation. Local interest must contribute 
7.2 percent of the initial costs of the 
hurricane-protection features and the present 
worth of future maintenance thereof; provide all 
non-Federal lands, easements, and rights-of-way, 
including borrow areas, necessary for construction 
of the project; accomplish all relocations and 
alterations of sewerage and drainage facilities, 
buildings, streets, utilities, and other structures 
made necessary by construction; hold and save 
the United States free from claims for damages 
due to construction, nourishment, or 
maintenance of the projects, including the laying 
of dredge pipelines across the highways or across 
private property; and at least annually inform interests 
affected that the project will not prevent 
inundation or provide any substantial protection 
from ocean surges higher in elevation than those 
of the hurricane of September 14, 1944. Formal 
assurances have been received. 
6-18

WILMINGTON, N.C., DISTRICT 
Operations and results during fiscal 
year. New work: Funds amounting to $59,520 
were revoked. 
Conditions at end of fiscal year. The project is 
in the "inactive" category. 
38. ROCKFISH CREEK, N. C. 
Location. Rockfish Creek is in Sampson, 
Duplin, and Pender Counties, North Carolina. It 
rises about 4 miles north of the Concord community 
and flows southeast for 15 miles to Doctors 
Creek; then to the east, 13 miles, to its confluence 
with Northeast (Cape Fear) River. (See 
Geological Survey quadrangle sheets, Atkinson, 
Rose Hill, and Burgaw, N. C.) 
Existing project. The project provides for 5.7 
miles of clearing and snagging from the mouth of 
Rockfish Creek to U. S. 117, thence excavating 
and straightening 13.9 miles of channel along 
Rockfish Creek, with bottom widths varying 
from 40 to 25 feet; on Doctors Creek, a tributary of 
Rockfish Creek, widening, deepening, and 
straightening 6.9 miles of channel, with bottom 
widths varying from 25 to 15 feet, a total of 26.5 
miles; and construction of a 20-acre shallowwater 
wildlife-mitigation reservoir on Doctors 
Creek about 1 mile downstream of N. C. 41, and a 
25-acre fishery-mitigation reservoir in the 
headwaters of Rockfish Creek. Estimated project 
cost (1974) is $1,006,700, including Federal cost of 
$753,500 and non-Federal cost of $253,200 
($144,600, cash contribution; $60,100, rights-ofway, 
legal fees, and drainage district formulation; 
and $48,500, associated works). The project 
was approved on August 17, 1967, under Section 
205 of the 1948 Flood Control Act, as amended. 
Local cooperation. Local interest must: 
provide all lands, easements, rights-of-way, utility 
relocations and alterations, and highway or 
highway-bridge construction and alterations 
necessary for project construction; hold and save 
the United States free from damages; maintain 
and operate the project after completion; prevent 
future encroachment which might interfere with 
proper functioning of the project; contribute, in 
cash 16.1 percent of the construction costs; and accomplish 
associated drainage works necessary to 
realize the benefits from the Federal improvement. 
Local interests have indicated they are 
willing and able to meet these requirements. 
Operations and results duringfiscal year. New 
work: Detailed engineering and design cost 
$7,744. 
Condition at end of fiscal year. Preconstruction 
planning is complete. 
39. SCUPPERNONG RIVER, N.C. 
Location. The stream rises in the east-central 
portion of Washington County, N. C., flows east 
into Tyrrell County, and thence north into 
Albemarle Sound, a total distance of about 22 
miles. (See Geological Survey quadrangle sheet, 
Creswell, N.C.) 
Existing project. The project provides for excavating 
a 70-foot-bottom-width channel, with 
depths ranging from 9 feet to 12 feet, along 
Scuppernong River from Spruills Bridge to the 
confluence with Mauls Creek, a distance of 2.0 
miles, and excavating a 45-foot-bottom-width 
channel, with depths ranging from 6 feet to 8 feet, 
along Mauls Creek from Scuppernong River to 
County Road 1163, a distance of 1.8 miles. Total 
project length is 3.8 miles. Estimated Federal 
cost of construction is $280,500 (1974). Project 
was approved by the Chief of Engineers, 31 
October 1966 (with modification adding Mauls 
Creek approved 16 June 1967), under Section 205, 
1948 Flood Control Act, as amended. 
Local cooperation. Local interests must 
provide lands, easements, rights-of-way, utility 
relocations and alterations, and highway or 
highway-bridge construction and alterations 
necessary for construction; hold the United States 
free from damages; maintain and operate project 
after completion; contribute, in cash, 19.4 percent 
of construction costs; and prevent future encroachment. 
Formal request has not been made. 
Operations and results during fiscal year. New 
work: Detailed engineering and design cost 
$2,378. Environmental studies cost $10,970. 
Condition at end of fiscal year. Project is in the 
preconstruction stage. 
40. THOROUGHFARE SWAMP, N. C. 
Location. Thoroughfare Swamp rises near the 
Wayne County-Sampson County line and flows 
eastward about 10 miles to its confluence with 
Buck and Yellow Swamps, turns northward and 
flows about 8.5 miles to its confluence with Neuse 
River. (See U. S. Geological Survey quadrangle 
sheet Raleigh, N. C.) 
Existing project. The project provides for 
channel improvement and construction of a dam 
in the Thoroughfare Swamp Basin which includes; 
clearing and snagging 1.2 miles of 
channel; excavating a 20-foot-bottom-width 
channel on Thoroughfare Swamp, 2.5 miles; excavating 
a 10-foot-bottom-width channel on 
Thoroughfare Swamp, 7.3 miles; excavating a 10- 
foot-bottom-width channel, from the mouth of 
Beaverdam Creek, 9.2 miles; excavating an 8- 
foot-bottom-channel from the mouth of Thunder 
Swamp to N. C. Highway 55, a distance of 3.1 
miles; constructing a fishery mitigation reservoir 
on Beaverdam Creek with pertinent features. Estimated 
total project cost (1974) is $773,300, including 
$595,500 Federal cost and non-Federal 
6-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
cost of $177,800 ($103,500 cash contribution, $56,- 
900 lands, and $17,400 auxiliary drainage). The 
project was approved by the Chief of Engineers 
on April 1, 1969, under Section 205 of the 1948 
Flood Control Act, as amended. 
Local cooperation. Local interests must 
provide lands, easements, rights-of-way, utility 
relocations and alterations; hold and save the 
United States free from damages due to construction 
works; maintain and operate the project 
after completion; contribute, in cash, 14.8 percent 
of the construction cost of the flood control and 
drainage improvements; provide for free public 
access to the fishery-mitigation pond, boat 
launching ramp, and parking area; assume full 
responsibility for all project costs in excess of the 
Federal cost limitation of $1,000,000; prevent 
future encroachment; accomplish auxiliary 
drainage work necessary to realize benefits from 
the Federal improvement; and encourage individual 
landowners to apply land-treatment 
measures to lands within the basin to minimize 
soil erosion and subsequent silt deposition in the 
improved channels. Formal request has not been 
made. 
Operations and results during fiscal year. New 
work: Environmental studies cost $1,729. 
Condition at end of fiscal year. Preconstruction 
planning is complete. 
41. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, 
inspections were made for the following projects 
during fiscal year 1975: Ellis Swamp, Gates 
County, N. C.; Gardners Creek, Martin County, 
N. C.; New River, Onslow County, N. C.; Pungo 
Creek, Beaufort County, N. C.; South Creek, 
Beaufort County, N. C.; Pungo River, Beaufort 
County, N. C.; and Filberts Creek, Edenton, N. C.; 
Pantego and Cucklers Creek, Beaufort County, 
N. C.; White Oak Dike, Bladen and Pender Counties, 
N. C.; Ellerbe Creek, Durham County, N. C.; 
Pasquotank Dike, Pasquotank County, N. C.; Perquimans 
River, Perquimans County, N. C.; Core 
Creek, Craven County, N. C.; Princeville Dike, 
Edgecombe County, N. C.; Swift Creek, Pitt 
County, N. C.; Carolina Beach, New Hanover 
County, N. C.; Wrightsville Beach, New Hanover 
County, N. C., Goldsboro, Neuse River, Wayne 
County, N. C.; Broad Creek, Beaufort County, N. 
C.; and Lick Run, Roanoke, Va. Responsible local 
officials were advised of inadequacies in 
maintenance and operation on local flood protection 
works where appropriate. Fiscal year cost 
was $14,000. Total cost to June 30, 1975, was 
$83,559, charged to maintenance. 
42. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 6-H.) 
43. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization). (See Table 6-I.) 
Emergency flood control activities and 
hurricane flood and shore-protection activities at 
Federally authorized projects (Public Law 99, 
84th Congress, and antecedent 
legislation). Federal costs for revision of Flood 
Emergency Manual and equipment were $18,508 
for fiscal year. 
Multiple-Purpose Projects Including Power 
44. ROANOKE RIVER BASIN, 
VA. AND N. C. 
Location. The project is on the Roanoke River 
and its tributaries in Virginia and North 
Carolina within a radius of 100 miles from Danville, 
Virginia. 
Existing project. The Flood Control Act of 1944 
approved a general plan for the comprehensive 
development of the Roanoke River Basin for flood 
control and other purposes, and authorized construction 
of John H. Kerr and Philpott Reservoirs. 
See Tables 6-G for a list of dams and reservoirs 
included in the comprehensive plan. 
Local cooperation. None required. John H. 
Kerr and Philpott Reservoirs are the only projects 
in the comprehensive plan that have been 
authorized for construction. (See Table 6-G on 
Dams and Reservoirs.) 
44A. JOHN H. KERR DAM AND 
RESERVOIR, VA. AND N.C. 
Location. The project is on the Roanoke River, 
about 178.7 river miles above its mouth, in 
Mecklenburg County, Virginia, and 20.3 miles 
downstream from Clarksville, Virginia. The 
reservoir extends upstream on Roanoke River 56 
miles and on Dan River 34 miles. 
Existing project. The authorized project 
provides for a concrete gravity dam with wing 
and saddle dikes on the right and left banks, with 
a total length of about 22,285 feet. The reservoir is 
operated as a unit of a coordinated system of 
reservoirs in the Roanoke River Basin for control 
of floods, generation of hydroelectric power, 
regulation of low-water flow, and for other purposes. 
The power installation is 204,000 kilowatts. 
(For further details see Annual Report for 1962.) 
6-20

WILMINGTON, N.C., DISTRICT 
Estimated cost (1975) is $65,353,000 and $24,- 
521,000 for land and damages, including relocation 
of highways, railroads, and utilities, a total of 
$89,874,000 for new work. The existing project 
was authorized by the 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Expansion and improvement of 
recreational facilities by hired labor and contract. 
Contract work included an on-the-land 
wastewater treatment facility at North Bend 
Park. Total cost for new work was $327,075. 
Maintenance: General operation and 
maintenance of the project was performed. Total 
cost for maintenance was $1,855,820. 
Condition at end of fiscal year. Project is complete 
except for additional recreational facilities, 
resolution of claims against the Government, and 
judgements in real estate condemnation cases. 
Production of power and protection from floods 
are provided by project. 
44B. PHILPOTT LAKE, VA. 
Location. On Smith River, Virginia, 44.3 miles 
above its junction with Dan River, and 35 miles 
upstream from Virginia-North Carolina State 
line in Franklin and Henry Counties. 
Existing project. The authorized project 
provides for a concrete gravity dam 892 feet long 
and with a maximum height of 220 feet. Reservoir 
is operated as a unit of a coordinated reservoir 
system for flood control in the Roanoke River 
Basin, generation of hydroelectric power, regulation 
of low-water flow, and for other purposes. 
The powerhouse has a total installation of 14,000 
kilowatts. (For further details see Annual Report 
for 1962.) Federal cost estimate (1975) is $13,195,- 
000 for construction and $1,157,000 for lands and 
damages, a total of $14,352,000. Existing project 
was authorized by 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Expansion and improvement of 
recreational facilities by hired labor, and contract. 
Design of utility building cost $8,236. 
Maintenance: General operation and 
maintenance of the project was performed at a 
cost of $563,062. 
Condition at end of fiscal year. The project is 
complete except for additional recreational 
facilities, and is providing power and flood 
protection. 
45. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
John H. Kerr Dam and Reservoir and Philpott 
Lake projects, Roanoke River Basin, Virginia 
and North Carolina, began Fiscal Year 1975 with 
both reservoirs slightly above rule curve. At the 
beginning of the fiscal year, Kerr Reservoir was 
at elevation 299.76 feet, mean sea level, or about 
0.3 foot above rule curve. The reservoir fell to 
near elevation 296 by July 7 and fluctuated below 
the rule curve until September 5, at which time it 
rapidly rose to elevation 305.33 by September 10. 
The level was drawn down to near rule curve at 
elevation 299.74 by September 30 and fluctuated 
above and below the rule curve until November 
12. At this time a heavy demand for power caused 
a drawdown from which the low elevation for the 
year was reached at 286.90 on December 4. The 
reservoir rose in December and was near rule 
-curve by January 1, 1975, and continued to rise 
until it reached elevation 302.00 on January 17. 
With above normal rainfall in January and 
February, Kerr Lake level remained well above 
rule curve, but gradually dropped until March 
11. Very heavy rainfall began on this date which 
later caused the reservoir to rise to a new maximum 
elevation of record at 316.84 on March 24, 
only to be exceeded 10 days later on April 3 at 
elevation 318.85. By May 1, the reservoir was 
lowered to within a foot of rule curve. For the 
month of May, Kerr Lake level ranged between 
elevation 301.89 and 304.03, and was drawn down 
to within 0.4 foot of rule curve on June 30 at elevation 
299.87, 
Philpott Lake level remained relatively near 
rule curve for a major portion of the fiscal year. 
The lake elevation of 974.27 feet, mean sea level, 
at the beginning of the fiscal year was about 0.8 
foot above rule curve and fluctuated near, but 
mostly below rule curve until September 5. The 
lake rose to an elevation of 973.68 on September 
12, or about 1.5 feet above rule curve. The level 
remained near rule curve from the latter portion 
of September, until December 6 with the lowest 
elevation for the year occurring on November 29 
at elevation 971.01. From about December 8 to 
the end of the fiscal year, Philpott Lake level fluctuated 
about 1 foot above rule curve with the exception 
of a couple of periods of somewhat higher 
levels. The highest level for the year occurred on 
March 20 at elevation 979.18 which was the second 
highest elevation of record. The lake was at 
elevation 974.08 on 30 June 1975 or about 0.6 foot 
above rule curve. 
In the Roanoke River below Kerr Dam, a 
minimum stage of 13 feet was provided at 
Weldon, N.C., during the entire striped bass 
spawning season. All inflows to Kerr Reservoir 
and Philpott Lake were controlled without having 
to spill water over the spillways or through 
the sluices. A large amount of dump energy was 
sold at Kerr and Philpott during the March-April 
flood periods. Gross generation amounts for the 
6-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
year at Kerr and Philpott projects, respectively 
were 613,702,900 kilowatt-hours and 31,649,300 
kilowatt-hours of electrical energy. Maximum of 
record monthly energy amounts were generated 
in August at Kerr project and in March at 
Philpott. Total cost of functional operation for the 
fiscal year was $66,108 for John H. Kerr project 
and $14,300 for Philpott. 
General Investigations 
46. SURVEYS 
Fiscal year cost was $248,539, of which $69,326 
was for navigation studies; $162,221 was for flood 
control studies; $4,492 for beach erosion studies; 
$2,000 for soil conservation service; $5,500 for 
deauthorization review and $5,000 for cooperation 
with States. 
47. COLLECTION AND STUDY 
OF BASIC DATA 
Flood plain information studies, as authorized 
by Section 206, 1960 Flood Control Act, as amended, 
comprise compilation and dissemination, 
upon the request of a State or a political subdivision 
thereof, of information on floods and flood 
damages, including identification of areas subject 
to inundation by floods of various magnitudes 
and frequencies, and general criteria for 
guidance of Federal and non-Federal interests 
and agencies in the use of flood-plain areas; and 
provide advice to other Federal agencies and 
local interests for their use in planning to 
ameliorate the flood hazard. Total costs for the 
fiscal year were $290,092. Total costs to June 30, 
1975 were $1,446,899. (See Table 6-J for Completed 
Flood-Plain Studies.) 
6-22

WILMINGTON, N.C., DISTRICT 
TABLE 6-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Aquatic Plant 
Control (R&H Act of 
1965) 
(Regular Funds) 
(Contributed Funds) 
2. Atlantic Intracoastal 
Waterway between 
Norfolk, Va. & St. 
Johns River, Fla. 
(Regular Funds) 
3. Avon Harbor 
4. Beaufort Harbor, 
N. C. 
(Contributed Funds) 
5. Cape Fear River, 
N. C., above 
Wilmington 
6. Channel connecting 
Thoroughfare 
Bay with Cedar 
Bay, N.C. 
7. Channel from Back 
Sound to Lookout 
Bight, N. C. 
8. Channel from 
Pamlico Sound to 
Rodanthe, N.C. 
9. Drum Inlet, N. C. 
(Regular Funds) 
(Contributed Funds) 
10. Far Creek, N.C. 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp.. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Costs 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
7,900 
7,922 
3,400 
3,299 
1,254,563 
1,239,585 
87,000 
70,768 
266,800 
262,090 
33,447 
33,447 
650 
650 
90,000 
89,382 
299,990 
286,158 
13,500 
13,500 
10,000 25,900 7,000 
6,850 6,730 32,586 
4,300 7,630 
1,119 948 
100,000 250,000 
- 85,738 
2,598,700 1,287,650 
1,620,216 2,406,930 
- 2,890 
- 2,890 
12,715 
-50,000 
128,882 
2,568,700 
2,318,392 
2,300 
2,300 
94,800 
93,726 
31,809 
29,378 
11,924,6411 
11,839,261 
25,838,74622 
25,536,341 
74,096 
74,096 
87,695 
87,695
3 
- - - 598,389 
- - - 598,389
4 
64,755 18,100 146,400 1,348,1154 
14,367 84,720 134,769 1,336,484 
- - 103,578 103,578 
- - 103,578 103,578 
- - - 3,759,57355 
- - - 3,759,573 
6 
228,900 359,900 338,500 6,407,6026 
201,279 394,286 317,682 6,386,447 
- - - 69,610 
- - - 69,610 
- - 2,700 25,573 
- - 2,700 25,573 
- - - 88,328 
- - - 88,328 
173,458 78,787 167,305 921,844 
173,458 78,787 167,305 921,844 
- - - 42,029 
- - - 42,029 
- 750 2,300 4,747 
- 750 2,300 4,747 
- -109 - 152,619 
1,256 173 - 152,619 
299,783 193,939 29,100 982,706 
299,782 34,172 201,929 981,945 
- - - 13,500 
- - - 13,500 
- - - 159,904 
- - - 159,904 
219,500 - 2,300 519,586 
219,500 - 963 518,249 
6-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
11. Lockwoods Folly 
River, N. C. 
12. Manteo (Shallowbag) 
Bay, N. C. 
13. Morehead City 
Harbor, N. C. 
(Contributed Funds) 
14. Ocracoke Inlet, 
N. C. 
15. Pembroke Creek, 
N. C. 
16. Rollinson Channel, 
N. C. 
17. Shallotte River, 
N. C. 
18. Silver Lake 
Harbor, N. C. 
19. Smiths Creek, 
(Pamlico County), 
N.C. 
20. Stumpy Point Bay, 
N. C. 
21. Waterway connectting 
Pamlico Sound 
and Beaufort Harbor 
N.C. 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
3,800 
3,800 
594,400 
579,103 
59,600 
26,964 
816,700 
813,980 
181,789 
26,543 
24,543 
90,300 1,054 
90,300 1,054 
- 60,000 
- 10,104 
250,600 1,098,075 
262,496 1,069,922 
73,000 
64,130 
1,018,200 
1,018,895 
40,557 
40,557 
13i 
13 
27,000 
48,671 
1,462,469 
1,457,045 
7,106 
6,450 
- 
7,621 1 
7,271 1 
-113,957 
127,100 
110,717 
134,212 
9,712 
67,582 
172,025 
27,137 
237,042 
452 
452 
10,500 
22,400 
-6,100 
113,900 
-8,037 
1,392 
2,730 
2,730 
14,900 
8,927 
65,000 
114,896 
1,048,100 
939,520 
50,000 
52,322 
1,152,900 
1,141,739 
49,749 
49,749 
256,845 
250,872 
1,511,335 
1,511,335 
6,882,012 
6,739,278 
1,843,479 
1,825,966 
12,912,423 
12,891,213 
40,557 
40,557 
- - 346,240 
- - 346,240 
58,135 170,100 391,884 
50,791 170,100 391,884 
50,000 - 60,000 
1,993 51,381 53,374 
- - 589,105 
- - 589,105 
74,800 2,300 426,002 
75,150 2,300 426,002 
9,000 - 27,181 
9,000 - 27,181 
6,735 96,244 133,068 
6,735 90,271 127,095 
- - 184,284 
- - 184,284 
56,431 145,000 834,319 
70,931 131,214 820,533 
- - 113,273 
- - 113,273 
2,269 3,959 34,403 
2,269 3,959 34,403 
- - 268,381 
- - 268,381 
- 2,300 225,760 
4,500 2,300 225,760 
- - 477,067 
- - 477,067 
2,616 106,255 798,722 
2,616 106,255 798,722 
- - 2,452 
- - 2,452 
6-24 
1167 
-

WILMINGTON, N.C., DISTRICT 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
22. Waterway Connecting 
Swanquarter Bay 
with Deep Bay 
N.C. 
23. Waterway, Norfolk, 
Va., to Sounds of 
N. C. 
24. Wilmington Harbor, 
N. C. 
(Regular Funds) 
(Contributed Funds) 
29. Black River, N.C. 
30. Brunswick County 
Beaches, Cape Fear 
River to N.C.-S.C. 
Line 
(Regular Funds) 
Contributed Funds) 
31A. B. Everett Jordan 
Dam and Lake, N.C. 
(Regular Funds) 
Contributed Funds) 
31B. Howards Mill Lake, 
N. C. 
31C. Randleman Lake, 
N. C. 
32. Carolina Beach and 
Vicinity, N. C. 
(Regular Funds) 
Contributed Funds) 
33. Joyce Creek, N. C. 
34. Little Rockfish 
Creek, Hope Mills, 
N.C. 
35. Mackay Creek, N. C. 
36A. Falls Lake, N. C. 
37. Ocracoke Island, 
N. C. 
38. Rockfish Creek, 
N. C. 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
620 
620 
12,000 
1,278 
25,432 
1,219,000 
798,702 
11,000 
49,700 
2,810 
60,000 
130,175 
9,533,300 
8,602,675 
460,227 
563,840 
181,400 
57,266 
439,400 
157,903 
-196 
239 
1,449 
297,000 
19,470 
3,177,100 
627,512 
79,400 
7,617 
69,500 
9,075 
1,897 
1,897 
2,300 
700 
- - 2,300 
5,361 5,361 700 
433,000 -50,812 - 
379,188 49,128 -252 
1,549,500 1,322,500 1,777,100 
1,052,547 2,197,082 1,594,118 
112,000 - 181,500 
11,000 112,000 172,425 
-135,000 - 4,500 
1,094 6,269 7,862 
25,000 355,710 -19,700 
13,531 121,419 167,164 
31,513 65 -114,132 
15,057,000 4,110,000 4,025,000 
8,729,469 8,741,384 6,857,395 
446,489 219,342 13,640 
433,245 138,474 110,331 
135,000 102,000 130,000 
215,180 141,782 134,172 
-130,000 435,000 35,000 
116,192 151,776 382,145 
- 4,290 50,000 
- 20,483 37,153 
-230,000 
392 
- 3.500 
1,924 10,362 
- - 10,000 
- - 4,244 
-320,000 - 4,500 
3,176 11,293 4,388 
-1,742,000 3,739,000 4,419,700 
1,377,087 3,464,726 4,191,291 
-55,000 55,000 -59,520 
5,497 6,766 - 
150,000 - -490,100 
4,286 21,704 7,744 
6-25 
110,799 
110,799 
15,250 
13,650 
751,196 
751,196 
2,886,910 
2,885,310 
10 
18,351,18910 
18,346,573 
11 
20,986,280 
20,758,029 
304,500 
295,425 
78,939 
78,939 
361,010 
302,114 
270,000 
153,492 
48,099,200 
47,905,195 
1,721,389 
1,718,080 
548,400 
548,400 
906,588 
902,317 
1,458,358 
1,444,538 
790,988 
779,672 
66,650 
66,149 
12 
10,000 
4,244 
130,900 
129,290 
11,136,100 
10,576,233 
129,592 
129,592 
159,447 
157,721

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
39. Scuppernong River, New Work: 
N.C. Approp. - - 21,000 7,000 73,905 
Cost - - 14,652 13,348 73,905 
40. Thoroughfare Swamp, New Work: 
N. C. Approp. 6,000 13,242 - - 132,767 
Cost 7,700 560 10,921 1,729 131,977 
44A. Roanoke River Basin, New Work: 
Va., and N. C., John Approp. 52,600 43,000 398,000 315,000 88,439,427 
H. Kerr Dam and Cost 65,979 71,877 63,176 327,075 88,100,660 
Reservoir Maint: 
Approp. 1,491,300 2,201,277 1,676,100 1,761,300 20,362,021 
Cost 1,325,326 1,508,961 2,392,922 1,855,820 20,277,339 
44B. Roanoke River Basin New Work: 
Va., and N. C., Approp. 11,900 176,000 - 85,000 14,027,384 
Philpott Lake, Va. Cost 11,481 45,155 130,233 8,236 13,949,589 
Maint: 
Approp. 509,900 511,623 557,200 525,200 6,646,463 
Cost 437,101 471,160 632,444 563,062 6,643,494 
1. Includes $198,707 for previous projects. 10. Includes $4,625,614 for new work on previous pro- 
2. Includes $107,634 for previous projects. jects. 
3. Includes $25,000 for previous projects. 11. Includes $602,614 for previous projects. 
4. Includes $12,854 for previous projects. 12. Includes preauthorization study funds: FY 73, 
5. Includes $149,119 for previous projects. $1,149: FY 74, $1,387; and preconstruction planning 
6. Includes $8,178 for previous projects. funds: FY 75, $7,464. 
7. Includes preauthorization study costs: FY 69, $406; 13. Includes preauthorization study costs: FY 73, 
FY 70, $3,752; FY 71, $342; FY 72, $1,658. $1,149; FY 74, $1,387 and preconstruction planning costs: FY 
8. Includes $44,484 for previous projects. 75, $1,708. 
9. Includes $284,557 for previous projects. 
TABLE 6-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., and ST. JOHNS RIVER, FLA. 
(See Section 2 of text) 
Original route of the Norfolk-Beaufort Inlet section. 
Purchase of canal. 
Change in route; following changes approved by Secretary of 
War, Apr. 14, 1919: 
Albemarle Sound-Pamlico Sound section: Changed from 
"Alligator River-Rose Bay route" to "Alligator River-Pungo 
River route." 
Pamlico Sound-Neuse River section: Changed from "Pamlico 
Sound-Brant Shoal Neuse River route" to "Goose Creek-Bay 
River route." 
Alligator River-Pungo River route (proposed land cut connecting 
the rivers): Changed from a straight line to a bent line 
approaching nearer town of Fairfield, N. C. 
A 12-foot channel 90 feet wide from Beaufort to Cape Fear 
River, N. C., including highway bridge and tidal lock. 4 
An 8-foot channel 75 feet wide from Cape Fear River to 
Winyah Bay, S. C. 
Construct a suitable bridge near Fairfield, N. C. 
Operating and care of works of improvement provided for with 
funds from War Department appropriations for rivers and 
harbors. 
Increasing dimensions of waterway to 12 feet deep and 90 feet 
wide. 
A 12-foot side channel 90 feet wide to Swansboro. 
H. D. 391, 62d Cong., 2d sess. 
H. D. 589, 62d Cong., 2d sess. 
H. D. 1478, 63d Cong., 3d Sess., 
and H. D. 1136, 64th Cong., 1st 
sess. 
Approved by Secretary of War, 
May 15, 1919. 
H. D. 450, 69th Cong., 1st sess. 
H. D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 5, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 6, 75th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 16, 75th Cong., 1st sess. 
6-26 
July 25, 1912 
July 25; 1912 
Aug. 8, 1917 
July 18, 1918 
Jan. 21, 1927 
July 3, 1930 
Mar. 4, 19332 
June 26, 19343 
Aug. 26, 1937 
Aug. 26, 1937

WILMINGTON, N.C., DISTRICT 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 20, 1938 
June 20, 1938 
Mar. 2, 1945 
June 30, 1948 
May 17, 1950 
May 17, 1950 
Sept. 3, 1954 
Nov. 29, 1963, 
sec. 107 
July 14, 1960 
Apr. 7, 1966, 
sec. 107 
July 14, 1960 
Nov. 7, 1966 
Nov. 7, 1966 
Dec. 31, 1970 
Mar. 3, 1881 
Mar. 2, 1907 
Mar. 3, 1925 
July 3, 1930 
Mar. 2, 1945 
May 17, 1950 
May 21, 1965, 
sec. 107 
July 14, 1960 
A yacht basin near Southport, 12 feet deep, 230 feet wide, and 
450 feet long, with connecting channel. 
A 6-foot channel 90 feet wide from New River Inlet to Inland 
Waterway. 
Six mooring basins. 
A 12-foot channel in New River 
Vicinity of Fairfield, drainage. 
Masonboro Inlet and connecting channels, including jetties at 
6 
the inlet. 
A 12-foot channel and basin in Peltier Creek. 7 
*A 6-foot channel 90 feet wide from Intracoastal Waterway to 
Bogue Inlet gorge. 
An 8-foot channel 150 feet wide through New Topsail Inlet, 
thence a 7-foot channel 80 ft. wide to Intracoastal Waterway 
by way of Old Topsail Creek; and a 7-foot channel 80 
feet wide in Banks Channel from New Topsail Inlet, parallelling 
barrier beach, to Intracoastal Waterway. 
Maintenance of a channel, 6 feet deep, 80 feet wide, and 8,000 
feet long, from the through channel of the waterway to and 
including a basin of the same depth, 130 feet wide and 180 
feet long, at Carolina Beach. 
Maintenance of general navigation features of N. C. State Ports 
Authority Small Boat Harbor at Southport. 
Replacement of Federally-owned and operated highway bridges 
at Coinjock, Fairfield, Wilkerson Creek, Hobucken, and Core 
Creek. 
BEAUFORT HARBOR, N. C. (See Section 4 of text) 
A 9-foot channel 200 feet wide through Bulkhead Channel to 
Beaufort; a 6-foot channel 100 feet wide to North River and 
Core Sound; and construct jetties on Shackleford Point. 
Repairs to Fort Macon jetties and additional jetties and 
shore protection. 
Bulkhead across Bird Shoal. 
Increase in depth to 12 feet in Bulkhead Channel, Gallants 
Channel, and in front of Beaufort. 
Increase in width and length of basin in front of Beaufort, 
all to 12 feet deep. 
Increase in depth to 12 feet and in width to 100 feet in 
Taylors Creek; transfer to Beaufort Harbor project. 
Channels 15 feet deep, 100 feet wide in Bulkhead, Gallants 
and Taylors Creek channels, and through turning basin in 
front of Beaufort; and harbor of refuge in Town Creek, 12 
feet deep, 400 feet wide, and 900 feet long connected to 
Gallants Channel by channel 12 feet deep, 150 feet wide, 
and 1,400 feet long. 
SILVER LAKE HARBOR, N. C. (See Section 18 of text) 
Entrance channel, 5 feet deep and 50 feet wide, from Pamlico 
Sound to the 3-foot contour in the lake, and training wall at 
entrance. 
Channel, 10 feet deep, and anchorage basin of same depth, 
100 feet wide across Big Foot Slough and 60 feet wide in 
entrance. 
Basin depth of 12 feet in Silver Lake Harbor; channels 12 
feet deep, 150 feet wide, in Teaches Hole and Big Foot 
Slough Channels and across Bluff Shoal; entrance channel, 
same depth, 60 feet wide; and training wall on south side 
of entrance channel. 
Rivers and Harbors Committee 
Doc. No. 3, 70th Cong., 1st 
sess. 
H. D. No. 325, 76th Cong., 1st 
sess. 
Detailed Project Report 
July 9, 1965. 
6-27 
H. D. 549, 75th Cong., 3d sess.' 
H. D. 691, 75th Cong., 3d sess.' 
H. D. 660, 76th Cong., 3d sess.' 
H. D. 421, 80th Cong., 1st sess.' 
H. D. 723, 80th Cong., 2d sess.' 
H. D. 341, 81st Cong., 1st sess.' 
H. D. 379, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1963. 
Detailed Project Report 
July 1965. 
H. D. 515, 89th Cong., 2d sess.l 
H. D. 514, 89th Cong., 2d sess.' 
H. D. 142, 92nd Cong., 1st sess. 
Annual Report, 1881, p. 1013 
Specified in act. 
Rivers and Harbors Committee 
Doc. 8, 68th Cong., 2d sess.' 
H. D. 776, 69th Cong., 2d sess.' 
H. D. 334, 76th Cong., 1st sess.' 
H. D. 111, 81st Cong., 1st sess. 
Detailed Project Report 
Apr. 1965. 
July 3, 1930 
Oct. 17, 1940 
Feb. 7, 1967, 
sec. 107 
July 14, 1960

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
WATERWAY CONNECTING PAMLICO SOUND AND 
BEAUFORT HARBOR, N. C. (See Section 23 of text) 
Aug. 30, 1935 A 7-foot channel 75 feet wide from Pamlico Sound to Beaufort H. D. 485, 72d Cong., 2d sess. 
Harbor via Wainright Channel. 
Aug. 26, 1937 A 7-foot side channel 75 feet wide to Atlantic. Rivers and Harbors Committee 
Doc. 92, 74th Cong., 2d sess. 
Mar. 2, 1945 Channels 7 feet deep, 75 feet wide, at east and west ends of H. D. 99, 77th Cong., 1st sess.' 
Harkers Island and side channel 5 feet deep, 75 feet wide, 
with basin 150 by 130 feet, same depth, at Davis. 
Mar. 2, 1945 A 7-foot side channel 75 feet wide, with basin 200 by 500 feet S. D. 247, 77th Cong., 2d sess.' 
same depth, at Sealevel. 
May 17, 1950 A 6-foot side channel 60 feet wide, with basin 100 feet by H. D. 68, 81st Cong., 1st sess.l 
about 600 feet, same depth, at Marshallberg. 
July 11, 1963, A side channel 7 feet deep, 70 feet wide to local harbor at Detailed Project Report 
sec. 107 Cedar Island and an access channel 6 feet deep, 60 feet Dec. 12, 1968. 
July 14, 1960 wide and about 400 feet long to a basin same depth, 60 by 
100 feet. 
Sept. 22, 1967, An entrance channel 6 feet deep, 60 feet wide, from Back Detailed Project Report 
sec. 107 Sound to harbor of refuge 120 by 250 feet, same depth, at March 13, 1967. 
July 14, 1960 west end of Harkers Island in Brook Creek. 
Feb. 24, 1969 A channel 7 feet deep, 70 feet wide, from existing side channel Detailed Project Report 
sec. 107 at Atlantic to a basin 600 by 180 feet, same depth, with a Dec. 21, 1967. 
July 14, 1960 breakwater, between mouth of Little Port Brook and White 
Point. 
1. Contains latest published maps. N. C. 
2. Public Law No. 443, 72d Cong. 6. Jetties on each side of Masonboro Inlet. 
3. Permanent Appropriations Repeal Act. 7. A 6- by 50-foot channel provided under Section 3, 
4. Tidal lock in land cut between Myrtle Sound and River and Harbor Act of March 2, 1945; 12- by 90-foot project 
Cape Fear River. classified as inactive. 
5. A 12- by 90-foot channel in New River from In- 8. Included in the Public Works Administration 
tracoastal Waterway to and including a basin at Jacksonville, program, Jan. 3, 1934. 
TABLE 6-C RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 25 of Text) 
Project Date Survey Conducted 
Channel From Back Sound to Lookout Bight, N. C. May 1975 
Edenton Harbor, N. C. June 1975 
Knobbs Creek, N. C. September 1974 
Neuse River, N. C. November 1974 
Shallotte River, N. C. February 1975 
Smiths Creek, (Pamlico County). N. C. April 1975 
Waterway Connecting Pamlico Sound and Beaufort Harbor, N.C. May 1975 
6-28

WILMINGTON, N.C., DISTRICT 
TABLE 6-D OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 26 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Aquatic Plant Controls,' 
(R&H Act of 1958 and 1962) 1969 70,664 - 
Atlantic Beach Channels, N.C. 1 1966 18,501 5,438 
Bay River, N.C. 1 1950 44,382 49,627 
Belhaven Harbor, N.C.' 1974 126,687 33,036 
Black River, N.C. 1969 12,358 124,846 
Cashie River, N.C. 1950 40,403 15,905 
Chowan River, N.C. 1950 - - 
Contentnea Creek, N.C, 1 1941 64,395 32,247 
Edenton Harbor, N.C. 1 1960 73,750 47,395 
Fishing Creek, N.C. 1 1922 22,715 8,633 
Harbor of Refuge, N.C. 1934 1,363,799 32,854 
Knobb's Creek, N.C. 1,2 1961 80,500 46,746 
Mackay Creek, N.C. 1 1938 13,375 6,273 
Mann's Harbor, N.C. 1973 7,265 - 
Neuse River, N.C. 1 1973 477,223 305,358 
Newbegun Creek, N.C. 1928 4,802 247 
Northeast (Cape Fear) River, N.C. 1 1950 10,688 61,139 
Pamlico and Tar Rivers, N.C. 1 1966 674,651 746,759 
Perquimans River, N.C. 1 1910 13,750 414 
Roanoke River, N.C. 1 1973 404,584 427,805 
Scuppernong River, N.C. 1 1950 81,164 79,990 
Smiths Creek (Wilmington), N.C. 1 1950 8,507 18 
South River, N.C. 1 1936 12,452 21,865 
Swift Creek, N.C. 1 1940 1,600 5,422 
Trent River, N.C. 1 1968 115,199 143,579 
Wallace Channel, Pamlico Sound, N.C. 1965 132,834 85,221 
Wrights Creek, N.C. 1 1965 64,825 2,348 
1. Completed. 
2. Transferred from Norfolk District; Meherrin River, 
N.C., Transferred to Norfolk District. 
6-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public Law 86-645 (preauthorization) 
TABLE 6-E (See Section 27 of Text) 
Study Identification Fiscal Year Cost 
Calico Creek, N. C. 4,544 
Davis, N. C. 8,422 
Lockwoods Folly and Shallotte River Inlets 11,925 
Neuse River, N. C. 317 
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
TABLE 6-F (See Section 28 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cape Lookout, N. C. 
(Outer Banks between Ocracoke 
Inlet and Beaufort Inlet, N. C.) 1968 - - 
Fort Macon State Park, N. C. 1973 620,000 - 
6-30

DAMS AND RESERVOIRS 
See Miles Height Reservoir Power Estimated 
Section Project Name Nearest City River Above of Type Capacity Development Construction Cost Lands Total 
in Text Mouth Dam (ft) (acre-feet) (kilowatts) and Damages 
31 Cape Fear B. Everett Jordon2 Moncure, N.C. Haw 4.3 112 E 778,000 - $23,768,5003 $55,531,500 $79,300,000 
River Basin, Howards Mill2 Carthage, N.C. Deep 55.0 106 E 233,000 - 13,790,00012 10.010,000 23,800,000 
N. C. Randleman2 Randleman, N.C. Deep 85.0 110 E 105,000 - 13,600,000'a 15,700,000 29,300,000 
Small reservoirs - Various - 20 to 70+ E 923,000 -- -38,454,000 
36. Neuse River Falls2 Falls, N.C. Neuse - 92 E 397,000 - 23,450,000 60,750,000 84,200,000 
Basin, N. C. Wilson Mills Wilson Mills, N.C. Neuse - 81 C,E 201,000 - - 13,000,000 
Beulahtown Kenly, N.C. Little - 50 E 81,000 - - -9,300,000 
Bakers Mills Princeton, N.C. Little - 53 E 36,000 - - - 6,600,000 
Little Buffalo Kenly, N. C. Little Buffalo Creek - 51 E 13,000 - - -1,100,000 
Buckhorn Wilson, N.C. Contentnea Creek - 63 E 119,000 - - -17,300,000 
Wiggins Mill Wilson, N.C. Contentnea Creek - 42 E 35,000 - - 6,700,000 
Stantonsburg Stantonsburg, N.C. Tisnot Swamp . - 36 E 48,000 - - -5,100,000 
Great Swamp Fremont, N.C. Great Swamp - 39 E 18,000 - - 1,800,000 
Black Creek Wilson, N.C. Black Creek - 33 E 17,000 - - - 1,500,000 
Aycock Swamp Fremont, N.C. Aycock Swamp - 37 E 7,000 - - - 550,000 
Hillsboro Durham, N.C. Eno - 136 E 123,000 - - 8,100,000 
Orange Durham, N.C. Little - 107 E 57,000 - - - 3,500,000 
44. Roanoke River John H. Kerr, Va., and Boydton, Va. Roanoke 178.7 144 CG.E 2,808,000 204,000 65,353,000 24,521,000 89,874,000 
Basin, Va. and N.C.2 
N.C. Philpott, Vat Bassett, Va. Roanoke 336.2 220 CG" 249.800 14,000 13,195,000 1,157,000 14,352,000 
Gaston, Va. and N.C.6 Roanoke Rapids, N.C. Roanoke 144.9 108 CG,E 432,000 54,000 27,000,000 3,500,000 30,500,000 
Roanoke Rapids, N.C.7 Roanoke Rapids, N.C. Roanoke 137.0 75 CG 59,300 83,000 31,300,000 800,000 32,100,000 
Smith Mountain, Va.s Altavista, Va. Roanoke 314.2 244 CG 825,000 41,000 28,000,000 3,800,000 31,800,000 
Leesville, Va.9 Altavista, Va. Roanoke 293.7 95 CG,E 76.900 20,000 9,100,000 1,000,000 10,100,000 
Taber, Va. Altavista, Va. Roanoke 275.0 54 CG 34,000 12,000 8,000,000 1,700,000 9,700,000 
Melrose, Va. Brookneal, Va. Roanoke 262.9 110 CG,E 120,000 43,000 17,700,000 6,000,000 23,700,0000 
Randolph, Va. Chase City, Va. Roanoke 227.8 147 CG,E 350,000 48,000 22,100,000 4,700,000 26,800,000 
Stuart, Va. and N.C. Spray, N.C. Roanoke 297.2 138 E 163,000 15,000 9,000,000 1,100,000 10,100,000 
Schoolfield, Va. and N.C. Danville, Va. Roanoke 265.9 126 CG,E 248,000 80,000 27,800,000 6,400,000 36,000,000 
1. Includes highway, railroad, and utility relocations. 
2. For details, see individual report. 
3. Includes $2,680,000 presently allocated to water 
supply to be reimbursed in the future by local interests. 
4. Includes $7,436,000 presently allocated to water 
supply and $4,851,000 recreation and fish and wildlife. 
5. Exclusive of transmission lines. 
6. Construction completed in 1963 by Virginia Electric 
and Power Co. 
7. Based on modified plan developed in fiscal year 1949. 
Construction completed June 1955 by Virginia Electric and 
SPower Co. 
8. Construction completed in Feb. 1966 by Appalachian 
Power Co. 
9. Construction completed in June 1963 by Appalachian 
Power Co. 
10. Includes cost of earth dam on Whipping Creek. 
11. Authorizing legislation provided for earth dam; concrete 
gravity dam constructed. 
12. Includes $1,071,000 presently allocated to recreation 
and fish and wildlife. 
13. Includes $3,525,000 presently allocated to water 
supply and $1,500,000 allocated to recreation and fish and 
wildlife. 
0
r
zzz 
c==4 
d== 
Key 
E - Earth 
CG - Concrete Gravity 
TABLE 6-G

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 6-H OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 42 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Adkin Branch, Lenoir County, N.C.' 1974 66,076 
Bodie Island, N. C. (Outer Banks between 
Virginia State Line and Hatteras Inlet, 
N. C.) 1968 - - 
Broad Creek, Beaufort County, N.C.' 1972 283,846 - 
Conetoe Creek, N. C.' 1960 29,867 - 
Conoho Creek, N.C.' 1974 79,782 - 
Contentnea Creek, N. C.' 1939-1943 50,889 - 
and 1958 
Contentnea Creek, N. C.' 1972 4,250 - 
Core Creek, N. C.1 1965 233,223 - 
Ellerbe Creek, Durham County, N. C.' 1963 223,413 - 
Ellis Swamp, Gates County, N. C.' 1971 138,117 - 
Filberts Creek, N. C.' 1970 32,288 - 
Gardners Creek, N. C.' 1972 54,597 - 
Goldsboro, Neuse River, N.C. 1974 50,430 235,787 
Hominy Swamp' 1973 107,472 - 
Hyde County Dike, N. C. (Mainland areas 
of N. C., excluding Washington and New 
Bern) 1968 - - 
Lick Run, Roanoke, Va.' 1974 1,280,317 - 
Mill Creek, N. C.' 1973 116,395 - 
Moccasin Swamp, N. C.' 1973 36,680 - 
Moyock Creek, N. C.' 1973 64,416 - 
Nahunta Swamp, N. C.' 1973 65,673 - 
Neuse River Barrier, N. C. (New Bern 
N. C. and vicinity) 1968 - - 
New River, N. C.' 1950 & 1956 51,896 - 
New River, Onslow County, N. C.' 1972 580,977 - 
North River Dike, N. C. (Beaufort Inlet 
to Bogue Inlet) 1968 - - 
Northeast (Cape Fear) River, N. C.' 1961 95,873 - 
Pantego Creek and Cucklers Creek, N.C. 1963 517,948 - 
Pasquotank River, N. C. 1960 80,931 - 
Perquimans River, N. C.' 1961 6,366 - 
Pungo Creek, N. C.' 1972 582,270 - 
Pungo River, N. C.' 1971 247,202 - 
Six Runs Creek, Sampson County, N.C.' 1971 64,977 - 
South Creek, N. C.' 1971 194,367 - 
Sweetwater Creek, N. C.' 1973 64,584 - 
Swift Creek, Pitt and Craven Counties, 
N. C.' 1966 611,096 - 
Tar River, N. C. 1964 81,266 61,473 
Tar River, N. C.' 1947 18,624 - 
Tar River and tributaries, N. C.' 1943 22,660 - 
Tar River, Princeville, N. C. 1967 390,249 - 
Topsail Beach and Surf City, N. C. 
(Bogue Inlet to Moore Inlet) 1968 - - 
Tranters Creek, N.C.' 1974 139,339 - 
Trent River, N. C.' 1953 64,769 - 
White Oak Dike, Bladen and Pender 
Counties, N. C.' 1963 214,286 
6-32

WILMINGTON, N.C., DISTRICT 
TABLE 6-H 
(Cont.) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 41 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project . Report For Construction Maintenance 
Wrightsville Beach, N. C. 1973 1,061,302 
1. Project authorized by Chief of Engineers under 
special continuing authority. 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(Preauthorization) 
TABLE 6-I (See Section 43 of Text) 
Study Identification Fiscal Year Cost 
Cashie River, Windsor, N. C. 5,000 
Collie Swamp, N. C. 8,229 
Deep Creek, N. C. 22,190 
Green Mill Run, N. C. 12,992 
Parker Creek, N. C. 20,445 
Peters Creek, N. C. 6,285 
FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
TABLE 6-J (See Section 47 in Text) 
Requesting Date Federal 
Location Agency Completed Cost 
Eden, N. C. Eden, N. C. Oct 1974 43,000 
Franklin, Nash and Granville Counties 
N. C., Tar River State of N. C. Oct 1974 55,000 
Greenville, N.C., Tar River and Greenville, N.C. Jun 1975 30,000 
Tributaries 
Montgomery Counties, Va., South Montgomery County, Va. Jun 1975 51,000 
Fork Roanoke River 
Roanoke, Va., Garnard Branch Roanoke, Va. Jun 1975 20,000 
South Boston, Va., Dan River South Boston and Oct 1974 40,000 
State of Va. 
Tarboro, N.C., Tar River and Tarboro, N.C. Jun 19751 20,000 
Tributaries 
1. Presented to the requesting agency at a later date. 
6-33

CHARLESTON, S. C., DISTRICT* 
This district comprises all of South Carolina 
(except local watersheds draining into the Savannah 
River), western-central North Carolina, and 
a very small portion of southwestern Virginia. It 
embraces the drainage basins tributary to the 
Atlantic Ocean between Little River and Port 
Royal Sound, except watersheds of Mackay and 
Skull Creeks, and excluding Hilton Head Island. 
IMPROVEMENTS 
Navigation Page 
1. Adams Creek, S.C. ............. 7-1 
2. Aquatic Plant Control, N.C. 
and S.C . ...................... 7-2 
3. Atlantic Intracoastal Waterway 
Between Norfolk, Va., and St. Johns 
River, Fla ..................... 7-2 
4. Charleston Harbor, S.C. ........ 7-3 
5. Cooper River, Charleston Harbor, 
S.C. (St. Stephen Project) ....... 7-3 
6. Georgetown Harbor, S.C. ....... 7-4 
7. Little River Inlet, N.C. and 
S.C . ........................... 7-4 
8. Murrells Inlet, S. C............. 7-5 
9. Port Royal Harbor, S.C. ........ 7-5 
10. Shipyard River, S. C............ 7-5 
11. Village Creek, S. C. ............ 7-6 
12. Reconnaissance and Condition 
Surveys ....................... 7-6 
13. Other Authorized Navigation 
Projects ....................... 7-6 
14. Navigation Activities Pursuant 
to Section 107, Public Law 86-645 
(Preauthorization) .............. 7-6 
15. Navigation Work Under Special 
Authorization ................. 7-6 
16. 
17. 
Beach Erosion Control 
Hunting Island Beach, S. C. .... 
Beach Erosion ControlWork Under 
Special Authorization ........... 
Flood Control 
18. Yadkin River, N. C. ............. 
18A. W. Kerr Scott Dam and Reservoir, 
Yadkin River, N. C. ........... 
18B. Reddies River Lake, N. C. ....... 
19. Sugar and Briar Creeks, N. C. 
(Little Sugar Creek, Charlotte, 
N.C.) ...................... 
20 Kingstree Branch, Williamsburg 
County, S. C ................... 
21. Roaring River, Wilkes County, 
N . C ........................... 
22. Flood Control Work Under 
Special Authorization ........... 
23. Other Authorized Flood Control 
Projects ........................ 
General Investigations 
24. Surveys ........................ 
25. Collection and Study of Basic 
D ata ........................... 
26. Research and Development ..... 
Navigation 
1. ADAMS CREEK, S. C. 
Location. The project is located in Charleston 
County, on the southeastern end of Wadmalaw 
Island near the village of Rockville. The estuarial 
creek flows generally southward into Bohicket 
Creek and from there into the North Edisto River 
and then into the Atlantic Ocean. 
Existing project. The project provides for a 
stable all-tide channel 10-feet deep and 80-feet 
wide extending from that depth in Bohicket 
Creek to a turning basin in the vicinity of the uppermost 
dock at Rockville, a distance of 1.45 
miles. The channel was dredged to a 2-foot 
overdepth and follows the general alignment of 
* All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
7-1 
7-6 
7-7 
7-7 
7-7 
7-8 
7-8 
7-9 
7-9 
7-9 
7-9 
7-10 
7-10 
7-10

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
the natural channel. (See Table at End of Chapter 
for Acts Authorizing Existing Project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are two marinas 
located on Adams Creek with docking and fueling 
facilities. There is also a ship repair yard which 
has docking and fueling facilities as well as a 
marine railway. All these facilities are privately 
owned but are open to all on an equal basis. Existing 
facilities are considered adequate for present 
and near future commerce. 
Operations and results during fiscal 
year. None. 
Condition at end of fiscal year. Existing project 
was completed in February 1973. Federal 
costs to date have been $125,697, including 
$17,700 for Detailed Project Report. 
2. AQUATIC PLANT CONTROL, N. C. 
AND S. C. 
Location. The project areas include navigable 
waters, tributary streams, connecting channels, 
and other allied waters in the Charleston District. 
Existing project. The project provides for control 
and progressive eradication of waterhyacinth, 
alligatorweed, Eurasian watermilfoil 
and other obnoxious aquatic plant growths from 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in combined interest of navigation, flood 
control, drainage, agriculture, fish and wildlife 
conservation, public health and related purposes, 
including continued research for development of 
most effective and economic control measures in 
cooperation with other Federal and State agencies 
in accordance with report of Chief of 
Engineers. The act provides that research and 
planning cost shall be borne fully by the United 
States. (See Table at End of Chapter for Acts 
Authorizing Existing Project.) 
Local cooperation. Local interests must agree 
to hold the United States free from damages that 
may occur from operations performed in connection 
with this project, and participate to extent of 
30 percent of cost of field operations. Requirements 
are being met in South Carolina. 
Operations and results during fiscal year. New 
Work: The spraying operations began on 2 July 
1974 and ended on 12 September 1974. Spraying 
operations during the following season began on 
30 June 1975. During this period, approximately 
30 miles of the Black River, 17 miles of the North 
Fork Edisto River, 15 miles of the Little Pee Dee 
River, and 10 miles of the Black Mingo Creek 
were treated. Alligatorweed flea beetles were 
abundant on each of the project streams during 
late summer. The herbicide was applied to only 
those mats of alligatorweed which exhibited little 
or no flea beetle damage. Costs incurred were 
$18,726 for engineering and $5,620 for 
operations. 
Condition at end of fiscal year. The combination 
of herbicides, alligatorweed flea beetles and 
flooding have resulted in the effective control of 
alligatorweed on the project streams. 
3. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN NORFOLK, 
VA., AND ST. JOHNS RIVER, 
FLA. (CHARLESTON DISTRICT) 
Location. The project starts on Little River 
near the North Carolina-South Carolina State 
line and extends generally south along the coast of 
South Carolina 62 miles to Winyah Bay; thence 
63.5 miles to Charleston; thence 84.5 miles to and 
including Port Royal Sound; a total of 210 miles. 
(See U.S. Coast and Geodetic Survey Charts Nos. 
835, 836 and 838.) 
Previous projects. For further details see page 
613 of Annual Report for 1932. 
Existing project. The project provides for a 
waterway 12 feet deep and not less than 90 feet 
wide with a branch channel of the same dimensions 
to McClellanville, and construction of three 
bridges crossing the waterway in Horry County, 
South Carolina. (See Table at End of Chapter for 
Acts Authorizing Existing Project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are rail-water terminals 
at Georgetown, Charleston, Johns Island 
and Port Royal, and numerous open-pile wharves 
mostly for shipping agricultural products, fish, 
oysters, pulpwood, wood products, and petroleum 
products. Marinas are located at convenient intervals 
along the waterway where limited 
supplies and repair facilities are available for 
both commercial vessels and pleasure craft. 
Facilities are considered adequate for existing 
commerce and recreation requirements. 
Operations and results during fiscal 
year. Maintenance: Contract costs were $2,232,- 
416. Disposal areas with spillways were constructed 
by Parkhill-Goodloe, Inc., July 1974- 
January 1975, at a cost of $446,127. Maintenance 
dredging was performed by Parkhill-Goodloe, 
Inc., during July 1974-June 1975, removing 
2,493,723 cubic yards of material for $1,786,289. 
Clearing and snagging by the U. S. maintenance 
vessel Snell and hired labor was performed at a 
cost of $13,121. Surveys and supervision costs 
were $310,864. 
Condition at end of fiscal year. Existing project 
was completed in 1940; three bridges were 
7-2

CHARLESTON, S.C., DISTRICT 
completed in 1936. Federal costs of existing project 
to date have been $7,345,888 for new work 
and $17,890,855 for maintenance, for a total of 
$25,236,743. 
4. CHARLESTON HARBOR, S. C. 
Location. The harbor is located on the coast of 
South Carolina about 15 miles south of the midpoint 
of the coastline, 50 miles southwest of 
Winyah Bay, S.C. and 80 miles northeast of the 
mouth of Savannah River. (See U. S. Coast and 
Geodetic Survey Charts Nos. 1239 and 470.) 
Previous projects. For further details see page 
1808 of Annual Report for 1915; page 579 of Annual 
Report for 1926 and page 562 of Annual 
Report for 1938. 
Existing project. The authorized project 
provides for a channel 35 feet deep with varying 
widths from the Atlantic Ocean to the mouth of 
Goose Creek, a total of 21.9 miles, together with a 
35-foot depth by 500-foot width channel via Town 
Creek. Also, a 10-foot depth by 110-foot width 
channel on the Mount Pleasant side of the harbor 
into Shem Creek to U.S. Highway 17 bridge, and 
a 30-foot anchorage basin in the lower harbor 
between Castle Pinckney and Fort Moultrie. A 
40-foot channel estimated to cost $6,060,000 was 
authorized to be executed when found necessary 
in the interests of national defense from the 40- 
foot contour in Atlantic Ocean to U. S. Naval 
Base. For further details see page 425 of Annual 
Report for 1962. (See Table at End of Chapter for 
Acts Authorizing Existing Project.) 
Local cooperation. Local interests have fully 
complied with their responsibility to date but are 
experiencing difficulty in securing suitable disposal 
areas for dredged material for continued 
future maintenance. 
Terminal facilities. Piers and slips extend for 
about 1 mile along the eastern waterfront of the 
City of Charleston with an additional mile of 
marginal wharves. The South Carolina State 
Ports Authority operates 8 piers for fruit, wood, 
cold storage facilities and general cargo, a grain 
elevator and a beltline railway which serves the 
entire Cooper River waterfront. Modern facilities 
are also at wharves of 7 major petroleum companies 
including storage tank farms. Modern 
facilities for marine repairs and servicing are 
available at Detyens Shipyard, located approximately 
10 miles northeast of Charleston on 
the Wando River. The U.S. Navy Department has 
modern facilities for construction and 
maintenance of naval vessels including atomic 
submarines. Loading docks and storage areas for 
missile-carrying type vessels have also been constructed 
and are being operated by the U.S. 
Navy. For further details see Port Series No. 13, 
Corps of Engineers. 
Operations and results during fiscal 
year. Maintenance: The pipeline dredges Clinton, 
Cherokee and Hampton Roads performed 
maintenance dredging and dike repairs by contracts 
during July 1974-June 1975, removing 
2,217,533 cubic yards of material for a total cost of 
$1,849,353. The hopper dredge Goethals and 
hired labor performed maintenance dredging in 
the entrance channel during February-March 
1975, removing 334,696 cubic yards of material at 
a cost of $370,602. Surveys and supervision costs 
were $231,422. 
Condition at end of fiscal year. Jetties protecting 
the entrance channel across the bar were completed 
in 1895. The existing project was completed 
in October 1962, except for the national 
defense portion. 
Federal costs under the existing project to date 
have been $3,328,349 for new work and $42,750,- 
079 for maintenance, a total of $46,078,428. 
5. COOPER RIVER, 
CHARLESTON HARBOR, S. C. 
(ST. STEPHEN PROJECT) 
Location. Cooper River is located in Charleston 
and Berkeley Counties, S.C., and empties into 
the Atlantic Ocean at Charleston. 
Existing project. The major cause of the shoaling 
problem in Charleston Harbor is the diversion 
of fresh water from the Santee River through 
Pinopolis Dam into the salt water of Charleston 
Harbor, causing density currents which trap 
sediments resulting in a phenomenal rate of 
deposition. The most practical and economical 
solution of the shoaling problem is to redivert 
most of the Santee River waters above Pinopolis 
Dam back into the lower Santee River through a 
canal beginning at Lake Moultrie and extending 
to the Santee River in the vicinity of St. Stephen, 
South Carolina. The existing project for Cooper 
River as authorized by the River and Harbor Act 
(See Table at End of Chapter for Acts Authorizing 
Existing Projects) provides that the discharge 
through the existing Pinopolis Hydro 
Plant be reduced to an average of 3,000 cubic feet 
per second. This flow would not establish a density 
current in the harbor. The excess water then 
impounded in Lake Moultrie would be directed 
through a new canal above St. Stephen, South 
Carolina, to enter the Santee River at a point well 
below the Lake Marion Spillway (Wilson Dam). A 
new hydroelectric facility would be constructed 
on the new canal where the ground elevations 
decrease to become swampland adjacent to the 
Santee River. This plant would replace those 
7-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
features made ineffective at Pinopolis through Terminal facilities. Terminal facilities at the 
curtailment of flows. The power production flow port of Georgetown, suitable for oceangoing 
of 24,500 cfs at the new powerplant, plus the vessels, consist of one marginal concrete pier and 
proposed 3,000 cfs average release planned for one of creosoted-timber construction. For 
Pinopolis, would approximate the existing total intracoastal waterway traffic there are a number 
Pinopolis flow capacity. The three generators at of smaller wharves and landings along the 
the new plant would be rated at 28,000 kilowatts Georgetown waterfront on the old channel. For 
each, for a total of 84,000 kilowatts. In the interest further details see Port Series No. 13, 1970, Corps 
of fish and wildlife resources of the area, the plan of Engineers. 
would also provide for construction of a herring Operations and results during fiscal 
lift at the new powerhouse site and a relocated year. Maintenance: Disposal area diking was 
fish hatchery. performed by contract during November 1974- 
Estimated cost of the project (1975) is April 1975 at a cost of $77,625. The pipeline 
$79,000,000, all Federal. (See Table at End of dredge Arlington performed maintenance dredg- 
Chapter for Acts Authorizing Existing Project.) ing in the Sampit River by contract during June 
Local cooperation. None needed. 1975, removing 70,000 cubic yards of material for 
Operations and results during fiscal $164,961. Maintenance dredging in the entrance 
.peraio.schannel year. Funds were received for and Sampit River was performed by initiation of con- hopper dredges Hyde and Gerigdurin 
struction during FY 75, however, primary expen- ptber 1974 an Jnuary-February 1975, 
ditures were for continued engineering andSreepmteomvinbge r6 4297,249 1 acnudb icJ aynaurdarsy a-Ft eab crousatr oyf $1492735,-, design and for negotiation of a project agreement 556. Surveys and supervision costs were $176,- 
contract with the South Carolina Public Service 6. Surveys and supervision costs were $176,- 
Authority. Engineering and design costs were 
$460,607; supervision and administration costs 
were $46,068. The EIS was filed with CEQ in 
January 1975. 
Condition at end of fiscal year. Preconstruction 
planning was completed at the end 
of FY 74. The General Design Memorandum was 
completed in January 1972 and work is 
proceeding on schedule on other phases of the 
project. Initiation of physical construction is 
planned for FY 76. 
6. GEORGETOWN HARBOR, S.C. 
Location. The harbor is located on the coast of 
South Carolina 50 miles northeast of Charleston 
Harbor and 90 miles southwest of entrance to 
Cape Fear River, North Carolina. (See U.S. Coast 
and Geodetic Survey Chart No. 787.) 
Previous projects. For further details see page 
1806 of Annual Report for 1915; page 549 of 
Annual Report for 1938; and page 442 of Annual 
Report for 1944. 
Existing project. The authorizations provide 
for a channel 27 feet deep with varying widths of 
600 feet to 400 feet from the Atlantic Ocean to and 
including a turning basin at the U.S. Highway 
No. 17 bridge over Sampit River, a total of 17.9 
miles. The project also provides for the continued 
maintenance to a depth of 18 feet and a width of 
400 feet for the bypassed portion of Sampit River 
opposite the City of Georgetown. (See Table at 
End of Chapter for Acts Authorizing Existing 
Project.) 
Local cooperation. Fully complied with. 
Condition at end of fiscal year. The existing 
project was completed in 1951. The jetties were 
completed in 1903-04. 
Federal costs for the existing project to date 
have been $4,615,903 for new work and 
$16,100,799 for maintenance, a total of 
$20,716,702. 
7. LITTLE RIVER INLET, N. C. 
AND S. C. 
Location. The project is located near the North 
Carolina-South Carolina state line. Little River 
enters the Atlantic Ocean at Little River Inlet at 
the state line and affords the only connection 
between the Atlantic Intracoastal Waterway and 
the ocean along 68 miles of coastline between 
Shallotte, N.C., to Georgetown, S.C. 
Existing project. The project provides for an 
entrance channel 12 by 300 feet across the ocean 
bar; thence a 10 by 90-foot inner channel to the 
Atlantic Intracoastal Waterway. The entrance 
channel would be stabilized by jetties extending 
seaward 3,200 feet and 3,000 feet long on the 
north and south sides of the inlet, respectively. 
Estimated costs of the project (1974) is 
$9,550,000 Federal cost and $1,890,000 non- 
Federal cost ($850,000 contributed funds and 
$1,040,000 for lands.) 
Local cooperation. In a letter dated 26 April 
1971, the Horry County (South Carolina) Planning 
and Promotion Commission gave assurances 
of cooperation. Since certain lands to be furnished 
by non-Federal interests lie in North Carolina, a 
letter dated 4 August 1971 has been supplied by 
7-4

CHARLESTON, S.C., DISTRICT 
the Brunswick County (North Carolina) Commissioners, 
agreeing to provide to the United 
States the necessary project lands lying in North 
Carolina. 
Terminal facilities. There are seven marinas, 
numerous private docks, and several public boat 
ramps located in or near Little River. It is expected 
that existing facilities will expand and 
new ones will be added as demands for services 
exceed current capacity. 
Operations and results during fiscal 
year. Sidecasting dredge Merritt performed 
emergency maintenance dredging during April- 
May 1975, removing 34,380 cubic yards of 
material. Expenditures for new work amounted 
to $290,779 for engineering and design and 
$8,223 for supervision and administration; 
maintenance expenditures amounted to $30,121. 
8. MURRELLS INLET, S.C. 
Location. The project is located on the coast of 
South Carolina in Georgetown County, about 13 
miles southwest of the City of Myrtle Beach. The 
inlet is the ocean entrance through a barrier 
beach to several tidal streams in the Murrells 
Inlet-Garden City estuarine area. 
Existing project. The project provides for an 
entrance channel 12 by 300 feet across the 
seaward bar; thence a 10 by 90-foot inner channel 
to a turning basin at the old Army crash boat 
dock. The entrance channel would be stabilized 
by ocean jetties extending seaward 3,300 feet and 
2,300 feet on the north and south sides of the inlet, 
respectively. The recreational project includes a 
walkway on the south jetty with access road and 
parking area. (See Table at End of Chapter for 
Acts Authorizing Existing Project.) 
Estimated costs of the project (1975) is 
$6,902,000 Federal cost and $1,410,000 non- 
Federal cost ($620,000 contributed funds and 
$790,000 for lands.) 
Local cooperation. A letter of intent to provide 
local cooperation has been received from the 
Georgetown County Board of Commissioners, 
and appears in the project document (H. D. 92- 
137.) 
Terminal facilities. There are five marinas 
and numerous private docks located about the 
Murrells Inlet harbor. There are several public 
boat ramps in the area. Facilities are expected to 
be expanded and new ones added as demands for 
services outstrip capacity. 
Operations and results during fiscal 
year. Sidecasting dredge Merritt performed 
emergency maintenance dredging during 
March-April 1975, removing 58,808 cubic yards 
of material. Funds were expended in the amounts 
of $359,187 for new work and $29,165 for 
maintenance operations. 
9. PORT ROYAL HARBOR, S. C. 
Location. The harbor is located on the coast of 
South Carolina 57 miles southwest of Charleston 
Harbor and 23 miles northeast of entrance to 
Savannah River, Georgia. (See U.S. Coast and 
Geodetic Survey Chart No. 571.) 
Existing project. The authorized project 
provides for a channel from the ocean through 
Port Royal Sound to Port Royal, South Carolina, 
27 feet deep and 500 feet wide across the ocean 
bar and in Port Royal Sound for approximately 
12.7 miles, thence 24 feet deep and 300 feet wide 
in Beaufort River and Battery Creek for 
approximately 8.3 miles to and including a turning 
basin 27 feet deep and 600 feet wide opposite 
the wharf of the South Carolina State Ports 
Authority. (See Table at End of Chapter for Acts 
Authorizing Existing Project.) 
Local cooperation. Fully complied with. 
Terminal facilities. The South Carolina State 
Ports Authority constructed a marginal concrete 
wharf and operates modern terminal facilities 
which are considered adequate for present commerce 
of the port. 
Operations and results during fiscal 
year. Maintenance: The hopper dredge Gerig 
and hired labor performed maintenance dredging 
in the entrance channel during August- 
September 1975, removing 607,938 cubic yards of 
material for $340,375. Surveys and supervision 
costs were $27,624. 
Condition at end of fiscal year. The existing 
project was completed in 1959. 
10. SHIPYARD RIVER, S. C. 
Location. This waterway is a tidal tributary of 
Charleston Harbor, South Carolina. It has its 
source about one-half mile below the U.S. Naval 
Base, whence it flows southerly about 3 miles and 
empties into Cooper River about three-fourths 
mile above Drum Island. (See U.S. Coast and 
Geodetic Survey Chart No. 470.) 
Previous projects. For details see page 610 of 
Annual Report for 1932 and page 463 of Annual 
Report for 1944. 
Existing project. The authorized project 
provides for a channel 30 feet deep from Cooper 
River to Airco Alloys & Carbide, a Division of Air 
Reduction Company Inc.'s plant including two 
turning basins; one opposite Gulf Oil Corporation 
terminal and another at the upper end of project. 
(See Table at End of Chapter for Acts Authorizing 
Existing Project.) 
7-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Fully complied with. 
Terminal facilities. In the lower threequarters 
of a mile of the channel are large 
marginal wharves of the Gulf Oil Corporation 
and Shipyard River Terminal Company. These 
wharves accommodate deep-draft, oceangoing 
vessels for handling petroleum products and fertilizer 
materials. In the upper channel is Airco 
Alloys & Carbide, a Division of Air Reduction 
Company, Inc.'s wharf for handling ores. 
Operations and results during fiscal 
year. Maintenance: The pipeline dredge Clinton 
performed maintenance dredging by contract 
during July 1974, removing 61,892 cubic yards of 
material for $111,628. Surveys and supervision 
costs were $11,561. 
Condition at end of fiscal year. The existing 
project was completed in 1951. Federal costs 
under the existing project to date have been 
$487,824 for new work and $5,353,215 for 
maintenance, a total of $5,841,039. 
11. VILLAGE CREEK, S. C. 
Location. Village Creek is located on the 
northeastern end of St. Helena in Beaufort 
County, approximately 12 miles from the town of 
Beaufort. This creek, which is about 600 feet wide 
at its confluence with Morgan River and St. 
Helena Sound at a point 7 miles from the Atlantic 
Ocean, extends in a southwesterly direction a distance 
of 6.8 miles to its headwaters. 
Existing project. The authorized project 
provided for a channel 8 feet deep and 80 feet 
wide from the mouth of Village Creek upstream 
to the Porpoise Fish Company Terminal for a distance 
of 2.2 miles. (See Table at End of Chapter 
for Acts Authorizing Existing Project.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal 
year. Fiscal year costs were $2,838 for condition 
surveys. 
Condition at end offiscal year. The project was 
completed in April 1966. 
12. RECONNAISSANCE AND 
CONDITION SURVEYS 
Condition surveys were made during FY 75 at a 
cost of $7,514. 
13. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 7-C.) 
14. NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 
(PREAUTHORIZATION) 
The project for Town Creek near McClellanville, 
Charleston County, South Carolina, 
authorized 12 February 1974, provides for dredging 
the ocean bar at the mouth of Five Fathom 
Creek to a depth of 12 feet and Town Creek to 10 
feet. Dredging of the ocean bar was completed in 
FY 74, and Town Creek was dredged in FY 75. 
Cost incurred during FY 75 was $132,340, includes 
$8,600 contributed funds. Work was completed 
on a favorable Reconnaissance Report and 
work was initiated on the detailed study on Folly 
River, Charleston County, S. C., during the fiscal 
year at a cost of $9,142. 
15. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Snagging and clearing for navigation (Sec. 3 of 
1945 River and Harbor Act, Public Law 14, 79th 
Cong.) 
Fiscal year cost was $9,572 for Little River, 
Horry County, S. C. 
Beach Erosion Control 
16. HUNTING ISLAND BEACH, S. C. 
Location. Hunting Island is a state park comprising 
about 1,850 acres of wooded land and is 
located along the southeastern shore of South 
Carolina in Beaufort County, 16 miles east of the 
town of Beaufort, 9 miles southwest of Edisto 
Beach, and 35 miles northeast of Tybee Roads at 
the mouth of Savannah River. (See U.S. Coast and 
Geodetic Chart No. 793.) 
Existing project. The authorized project 
provides for periodic nourishment of about 10,000 
feet of beach on the northern part of the island 
with initial placement of 750,000 cubic yards of 
sand for advance nourishment, and construction 
of one prestressed concrete groin at the north end 
of the island. Federal participation in periodic 
nourishment is limited to a period of 10 years. 
(See Table at End of Chapter for Acts Authorizing 
Existing Project.) 
Local cooperation. All requirements of local 
cooperation have been met by the State of South 
Carolina and accepted by the Chief of Engineers. 
The state contributed 30 percent of the cost of the 
initial project construction and a similar percentage 
of the costs of the first periodic nourishment 
which was done between May 1971 and August 
1971. Funds were appropriated for a second 
renourishment in FY 74 and matching funds 
7-6

CHARLESTON, S.C., DISTRICT 
were received to cover the State's share of the 
total cost. The contract for the work was not let in 
FY 74 since all bid amounts exceeded the Government 
estimate by an unacceptable amount. 
Operations and results during the fiscal 
year. Following a second advertisement for 
renourishment, bids were opened on 26 
November 1974 and the contract was awarded on 
5 December 1974. Work was started in February 
1975 and completed in June 1975. FY 75 expenditures 
were $627,656 including construction 
cost. 
Condition at end of fiscal year. The first two 
renourishments were designed to restore the 
feeder beach to the condition prevailing after the 
initial beach nourishment. These renourishments 
were completed in August 1971 and June 1975. 
Total Federal cost for the project through 30 June 
1975 was $1,450,328 (excluding $603,778 contributed 
funds). 
17. BEACH EROSION CONTROL UNDER 
SPECIAL AUTHORIZATION 
Activities Pursuant to Section 103, Public Law 
87-874 (Preauthorization). 
The reconnaissance report on Edisto Beach and 
the detailed study of Pawleys Island were completed 
during FY 75. In FY 75, $1,872 was spent 
on Edisto Beach and $1,952 was spent on Pawleys 
Island. Work was also done on the Sullivans 
Island Reconnaissance Report with costs 
creditable to FY 76. 
Flood Control 
18. YADKIN RIVER, N. C. 
Location. The river rises on the eastern slope of 
the Blue Ridge Mountains in western North 
Carolina, flows generally easterly about 100 
miles to the vicinity of Donnaha, North Carolina, 
thence southeasterly 104 miles to its confluence 
with Uwharrie River near Badin, North 
Carolina, where its name changes to Great Pee 
Dee River. (See U.S. Geological survey map of 
North Carolina.) 
Existing project. The Flood Control Act of July 
24, 1946, authorized construction of four floodcontrol 
dams in the upper Yadkin River Basin, 
two on the Yadkin River above Wilkesboro, North 
Carolina, and two on Reddies River, a tributary 
stream. Studies made subsequent to authorization 
established the economic advantage of 
providing needed flood-control storage in only 
two reservoirs, one on the Reddies and one on the 
Yadkin. Present planning considers only the tworeservoir 
plan. Cost for the Yadkin River Reservoir 
(W. Kerr Scott Dam and Reservoir constructed 
1962) and for Reddies River Lake is set 
forth in Table 7-D. (See Table at End of Chapter 
for Authorizing Legislation.) 
Funds of $131,500 were expended on the Reddies 
River Lake Project for project planning and 
preparation of a definite project report which was 
completed in March 1950. An economic restudy of 
the Reddies River Lake Project was submitted 
and approved in July 1968. Individual reports on 
W. Kerr Scott Dam and Reservoir and Reddies 
River Lake Project follow. 
18A. W. KERR SCOTT DAM AND 
RESERVOIR, YADKIN RIVER, N. C. 
Location. W. Kerr Scott Dam and Reservoir is 
on Yadkin River, North Carolina, about 6 miles 
upstream from Wilkesboro. At full flood-control 
pool elevation (1,075 feet mean sea level), the 
reservoir extends 15.7 miles upstream to Wilkes- 
Caldwell County line. 
Existing project. The project consists of a 
rolled earthfill dam 1,740 feet long, with top of 
dam at elevation 1,107.5 feet mean sea level, or 
about 148 feet above streambed elevation; a 
spillway near the north abutment of the dam in a 
rock cut with crest elevation 1,075; and outlet 
works consisting of an intake structure, control 
tower, and a circular concrete conduit 12.25 feet 
in diameter through the base of the dam near the 
south abutment. The reservoir has a gross capacity 
of 153,000 acre-feet of which 112,000 acre-feet 
are reserved for flood control, 33,000 acre-feet 
will be used when required for water supply, and 
8,000 acre-feet being contained in the minimum 
pool. (See Table at End of Chapter for Acts 
Authorizing Existing Project.) 
Local cooperation. Fully complied with. For 
details see page 413 of Annual Report for 1963. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Operation and 
maintenance cost $435,785. 
During the fiscal year the project had a visitation 
of 843,927. All recreation facilities continue 
to be utilized beyond their maximum capabilities 
during fair weather. Acquisition of additional 
lands and construction of recreational facilities 
authorized under the Appalachia Program has 
resulted in the project having the capability to 
accommodate approximately 250,000 additional 
visitors annually. The majority of visitor 
requirements continues to be for camping and 
picnicking facilities. Flood control storage was 
utilized seven times during FY 75. Floods in 
March and June were of sufficient magnitude 
that downstream flooding was significantly 
reduced as a result of the project operation. During 
March, three floods occurred. Maximum pool 
elevation attained for the most severe flood was 
7-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
1047.3. This is a rise of 17.3 feet above normal pool 
elevation of 1030.0. Two less severe floods occurred 
in June. The maximum pool elevation attained 
for these floods was 1035.3. Estimated 
flood damages prevented by the project for all 
floods in FY 75 were $3,376,000. 
Condition at end of fiscal year. The project was 
commenced in August 1960 and placed in operation 
for flood control and water storage purposes 
in February 1963. 
18B. REDDIES RIVER LAKE, N.C. 
Location. Reddies River flows into the Yadkin 
River near the town of North Wilkesboro, North 
Carolina, and is a tributary to the Yadkin-Pee 
Dee River. The authorized lake and damsite are 
located entirely in Wilkes County, North 
Carolina. 
Existing project. Reddies River Lake is the 
second unit in the authorized plan for the upper 
Yadkin River Basin. The first unit, W. Kerr Scott 
Reservoir, is located about 5 miles upstream from 
the mouth of the Reddies River and was completed 
in 1962. The Reddies damsite is located on 
Reddies River at mile 1.7, near the town of North 
Wilkesboro. Total tributary area above the damsite 
is 94.5 square miles. Project works contemplate 
construction of a rolled-earth dam about 
165 feet high with a saddle spillway and a gated 
outlet conduit. The conservation pool will cover 
about 680 acres and the flood control pool about 
1,335 acres. The project was authorized by the 
Flood Control Act of 1946; however, the project 
was deferred for restudy in 1950. An economic 
restudy was submitted in FY 69 and approved in 
FY 70. Preconstruction planning funds were appropriated 
in FY 70, but the funds were held in 
budgetary reserve throughout FY 70. Work 
began in January 1971 on the General Design 
Memorandum and Phase I was completed in 
March 1975. The Site Selection Design Memorandum 
was completed in May 1972 while the 
Hydrology and Hydraulic Analysis Design 
Memorandum was completed in March 1973. A 
public meeting was held in October 1972 to solicit 
the public's views on this project. Phase II 
General Design Memorandum is scheduled for 
completion in April 1977. (See Table at End of 
Chapter for Acts Authorizing Existing Project.) 
Estimated cost of the project (1973) is 
$22,200,000 of which $4,812,000 is reimbursable 
for water supply under the Water Supply Act of 
1958, and $1,950,000 for recreation. 
Local cooperation. The State of North Carolina 
was requested to reaffirm their earlier letters of 
intent to fulfill the local cooperation requirements 
necessary for water supply and 
development of recreation facilities. The State 
replied favorably in September 1974 concerning 
local cooperation for recreation and in November 
1974 concerning water supply. 
Operations and results during fiscal year. New 
Work: Preliminary planning for advanced 
engineering and design is continuing. Engineering 
and design costs were $90,280; supervision 
and administration costs were $19,239. 
Condition at end of fiscal year. Advanced 
planning studies are underway. 
19. SUGAR AND BRIAR CREEKS, N; C. 
(Little Sugar Creek, Charlotte, N. C.) 
Location. Little Sugar Creek, a tributary of 
Sugar Creek has its source about one-half mile 
northwest of the Charlotte, North Carolina, city 
limits whence it flows generally southwest 
through the eastern portion of Charlotte, for a distance 
of about 11 miles, continuing southwardly 
about 7 miles to its confluence with Sugar Creek 
near the North Carolina-South Carolina State 
line. Briar Creek, a tributary of Little Sugar 
Creek, has its source near the Charlotte city 
limits, whence it flows southwesterly a distance of 
about 9 miles through the eastern portion of 
Charlotte to its confluence with Little Sugar 
Creek near the southerly city limits of Charlotte. 
Existing project. Originally, the project 
provided for channelization of Little Sugar and 
Briar Creeks for a combined distance of 7.6 miles 
beginning at Archdale Drive near the southerly 
city limits and continuing northeast to Princeton 
Avenue on Little Sugar Creek and to Randolph 
Road on Briar Creek. The Little Sugar Creek 
channel would have a 50-foot wide bottom from 
Archdale Drive to the Briar Creek confluence 
and 40-foot wide bottom to the upstream limit. 
Briar Creek would have a 30-foot bottom width 
throughout the project length. Briar Creek portion 
was deleted in September, 1970 at the request 
of local interests. Briar Creek portion has 
been placed in an inactive status at the request of 
local interest. (See Table at End of Chapter for 
Acts Authorizing Existing Project.) 
Local cooperation. Local interest must provide 
lands, easements, rights-of-way, utility 
relocations and alterations, and highway or 
highway-bridge construction and alterations 
necessary for construction; hold the United States 
free from damages; maintain and operate the project 
after completion; prevent future encroachment 
and notify affected interests annually that 
the improvement will not provide complete flood 
protection. 
7-8

CHARLESTON, S.C., DISTRICT 
Operations and results during fiscal 
year. Coordination continued with representatives 
of local interests for lands, easements, and 
rights-of-way. The project is in the preconstruction 
planning stage. Fiscal year cost was $71,396. 
Approval was given to separate $76,000 and prior 
fiscal year costs for the deleted Briar Creek portion 
of the project and renaming the project Little 
Sugar Creek, Charlotte, N. C. 
Condition at end of fiscal year. Project is in 
advance engineering and design stage. 
20. KINGSTREE BRANCH, 
WILLIAMSBURG COUNTY, S. C. 
Location. Kingstree Branch is located in 
Williamsburg County, South Carolina, and 
originates northeast of the town of Kingstree and 
flows southward through the town to its confluence 
with the Black River. The total length of 
Kingstree Branch is about 6.6 miles. 
Existing project. The project provides for 
channel enlargement from the Black River to a 
point 1.8 miles upstream. The project was 
authorized 16 August 1972 under Section 205 of 
the 1948 R&H Act as amended. (See Table at End 
of Chapter for Authorizing Legislation.) 
Local cooperation. Local interest must provide 
lands, easements, rights-of-way, utility 
relocations and alterations, and highway or 
highway bridge construction and alterations 
necessary for construction; hold and save the 
United States free from damages; maintain and 
operate the project after completion; prevent 
future encroachments; notify affected interests 
annually that the improvement will not provide 
complete flood protection; and prevent unwise 
and uneconomical future development of the 
flood plain area through flood plain management 
techniques. 
Operations and results during fiscal year. The 
project is in the preconstruction planning stage 
awaiting local assurances. 
Condition at end of fiscal year. Project is in 
advance engineering and design stage waiting 
for local interest to secure the last six easements. 
Fiscal Year costs were $9,539. 
21. ROARING RIVER, WILKES COUNTY, 
N.C. 
Location. Roaring River, located in Wilkes 
County, North Carolina, originates northeast of 
North Wilkesboro and northwest of Elkin and 
flows generally southeast from the confluence of 
its middle and east prongs for approximately 5.8 
miles to the Yadkin River. 
Existing project. The project is authorized to 
undertake Phase I design memorandum stage of 
advanced engineering and design to determine 
the economic feasibility for a multiple-purpose 
earth fill dam rising 159 feet high and 970 feet 
long about 2.9 miles above the confluence of Roaring 
River with the Yadkin River. (See Table at 
End of Chapter for Acts Authorizing Existing 
Project.) 
Local cooperation. Recreation, water supply 
and water quality interests must administer project 
land and water areas for recreation, pay, contribute 
in kind, or re-pay (which may be through 
user fees) with interest, one-half of the separable 
costs allocated to recreation, bear all costs of 
operation, maintenance and replacement of 
recreational facilities, repay all costs, operation, 
maintenance and replacements allocated to 
water supply, require effective treatment and 
control measures at all sources of pollution to 
assure the maintenance of water quality, and give 
assurances that releases for water quality control 
will be legally protected from withdrawals for 
other purposes. 
Operations and results during fiscal year. The 
project is in the preconstruction planning stage 
awaiting completion of Phase I design memorandum 
studies. 
Condition at end of fiscal year. Project is in advance 
engineering and design stage, incurring 
Fiscal Year 75 costs of $88,166. 
22. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 
205, Public Law 685, 84th Congress, as amended 
(Preauthorized). 
(See Table 7-E.) 
Emergency Flood Control Activities - - Repair, 
Flood Fighting and Rescue Work (Public Law 99, 
84th Congress, and Antecedent Legislation.) 
Federal cost for the fiscal year was $17,097 for 
advance preparation, and $6,825 for determination 
of storm damages. 
Snagging and Clearing of Navigable Streams 
and Tributaries in Interest of Flood Control (Section 
208 of 1954 Flood Control Act, Public Law 
708, 83rd Congress, Preauthorization.) 
None. 
23. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 7-F.) 
7-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
General Investigations 
24. SURVEYS 
Total cost for the fiscal year was $175,014, of 
which $145,169 was for navigation studies, 
$22,420 for flood control studies, $3,988 for 
watershed studies in coordination with the U.S. 
Soil Conservation Service, and $3,437 for review 
and deauthorization. 
25. COLLECTION AND STUDY OF 
BASIC DATA 
Cost during fiscal year was $263,161 for flood 
plain information studies. (See Table 7-G at End 
of Chapter for Completed Flood Plain Studies.) 
26. RESEARCH AND DEVELOPMENT 
Hydrologic studies. Costs of collecting stream 
flow data, with storm and hydrologic studies, 
during the fiscal year were $2,500. 
7-10

CHARLESTON, S.C., DISTRICT 
TABLE 7-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY75 June 30, 1975 
1. Adams Creek, S.C. 
2. Aquatic Plant 
Control, N.C. and 
S.C. 
3. Atlantic Intracoastal 
Waterway 
between Norfolk, 
Va. and the St. 
Johns River, Fla. 
4. Charleston Harbor, 
S.C. 
5. Cooper River, 
Charleston Harbor, 
S.C. (St. Stephen 
Project) 
6. Georgetown Harbor, 
S.C. 
7. Little River Inlet 
N.C. and S.C. 
8. Murrells Inlet, 
S.C. 
9. Port Royal Harbor, 
S.C. 
10. Shipyard River, 
S.C. 
11. Village Creek, S.C. 
New Work: 
Approp. 
Cost 
New Work: 
Federal Funds 
Approp. 
Cost 
New Work: 
Contributed Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 2,( 
Cost 
New Work: 
Approp. 
Cost 
Approp. 2,( 
Cost 2, 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 1, 
New Work: 
Federal Funds 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Federal Funds 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 42,000 -4,003 
- 108,020 - 
10,900 
28,116 
6,000 
2,847 
036,100 
566,098 
636,000 
329,023 
287,900 
215,017 
945,000 
418,274 
167,500 
167,500 
291,300 
250,300 
15,000 30,000 
16,530 23,091 
- 125,697 
- 125,697 
26,700 
24,346 
197,600 
182,337 
- 6,400 4,828 52,028 
7,111 2,580 - 43,380 
- - - 7,455,3781 
- - - 7,455,378 
967,500 1,185,000 2,090,000 17,985,9462 
2,217,501 1,037,302 2,556,401 17,960,277 
- - - 9,914,8043 
- - - 9,914,8044 
2,684,200 4,096,280 2,328,600 43,613,4884 
2,667,850 4,629,089 2,451,377 43,152,068 
455,000 497,000 750,000 2,349,900 
381,264 568,923 506,675 2,008,961 
1,983,000 734,000 
1,710,715 1,093,230 
- 131,000 
- 58,639 
6,000 121,400 
4,765 113,063 
- 225,000 
- 110,438 
- 43,000 
- 43,000 
149,200 153,000 
149,200 153,000 
280,200 56,000 
277,200 254,834 
38,000 
38,000 
1,855,000 
842,904 
262,428 
299,002 
80,000 
30,121 
276,000 
359,187 
75,000 
29,165 
368,000 
367,999 
265,000 
123,189 
- 5,000 
- 2,838 
7,061,7555 
7,061,755 
17,250,6586 
16,215,355 
393,428 
357,641 
263,124 
203,673 
501,000 
469,625 
196,569 
150,734 
1,786,100 
1,786,100 
2,813,034 
2,813,033 
491,9747 
491,974 
5,495,192 
5,353,215 
26,5008 
26,500 
90,230 
88,068 
7-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 7-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
16. Hunting Island New Work: 
Beach, S.C. Federal Funds 
Approp. - - 610,000 50,000 1,465,800 
Cost 202,640 4,980 21,884 627,656 1,450,328 
New Work: 
Contributed Funds 
Approp. - - 266,000 - 603,778 
SCost 91,255 . - - 266,000 603,778 
18A. W. Kerr Scott Dam New Work: 
and Reservoir, N.C. Approp. 32,900 - 6,000 - 8,695,8269 
(Wilkesboro Cost 32,752 41 6,138 - 8,695,826 
Reservoir, N.C.) Maint. 
Approp. 336,100 411,200 380,000 437,000 3,147,311 
Cost 333,144 403,949 391,713 435,785 3,135,932 
18B. Reddies River Lake, New Work: o10 
N.C. Approp. 109,300 125,000 158,000 108,000 746,80010 
Cost 133,705 146,964 149,589 109,519 844,544 
19. Sugar and Briar New Work: 11 
Creeks, N.C. Approp. -2,000 -560,562 50,000 75,000 198,85711 
(Little Sugar Creek, Cost 8,394 1,534 49,400 71,396 194,653 
Charlotte, N.C.) 
20. Kingstree Branch, New Work: 
S.C. Approp. - -183,000 -150,000 - 36,650 
Cost 3,650 9,344 13,746 9,539 36,279 
21. Roaring River New Work: 
Wilkes County, Federal Funds 
N.C. Approp. - - - 115,000 115,000 
Cost - - - 88,166 88,166 
Maint. 
Approp. - - - - - 
Cost - - - - - 
1. Includes $109,490 for new work for previous project. 8. Excludes $3,000 in FY 69 for reconnaissance study to 
2. Includes $69,422 for maintenance of previous projects. determine economic feasibility of modifying the existing pro- 
3. Includes $6,586,455 for new work for previous pro- ject. 
jects. 9. Includes $666,900 Recreation Facilities on completed 
4. Includes $401,989 for maintenance of previous pro- projects. 
jects. In addition $600 for maintenance expended from con- 10. Includes $131,500 expended in 1951. For definite protributed 
funds. ject report see FY 1951 Annual Report. 
5. Includes $2,445,852 for new work for previous pro- 11. Prior costs for Briar Creek portion amounting to $76,- 
jects. 000 have been separated from the total appropriations in ex- 
6. Includes $114,556 for maintenance of previous pro- penditures. 
jects.
7. Includes $4,150 for new work on previous projects. 
TABLE 7-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Auth. by Chief of Engrs. 
on Sep. 24, 1969, under 
auth. of Sec 107, R&H Act 
of 1960, as amended. 
R&H Act of Oct. 27, 1965 
ADAMS CREEK, S.C. (See Section 1 of text) 
Consists of a stable all-tide channel 10-feet deep and 
80-feet wide extending the distance of 1.45 miles. 
AQUATIC PLANT CONTROL (See Section 2 of text) 
Provides for control and progressive eradication of water 
hyacinth, alligatorweed, Eurasian watermilfoil and other 
obnoxious aquatic plant growths from navigable waters, 
tributary streams, connecting channels, and other allied 
waters of the U.S., in combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, public health and related purposes, including 
continued research for development of most effective and 
economic control measures in cooperation with other Federal 
and State agencies. 
Detailed Project Report. 
Sec. 302, 1965 River & Harbor 
Act (H.D. 251, 89th Cong., 
1st sess.) 
7-12

TABLE 7-B (Continued) 
CHARLESTON, S.C., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of Sept. 19, 1890 
R&H Act of June 13, 1902 
R&H Act of Mar. 2, 1907 
R&H Act of Mar. 2, 1919 
R&H Act of Mar. 3, 1925 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 1935 
2 
R&H Act of Aug. 30, 19352
2 
R&H Act of Aug. 30, 1935 
R&H Act of Aug. 26, 1937 
R&H Act of Mar. 2, 1945 
R&H Act of June 18, 1878 
R&H Act of Aug. 8, 1917 
R&H Act of July 18, 1918 
R&H Act of Jan. 21, 1927 
R&H Act of Oct. 17, 1940 
R&H Act of Mar. 2, 1945 
R&H Act of Sept. 3, 1954 
R&H Act of July 14, 1960 
R&H Act of Aug. 13, 1968 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFORK, VA., AND ST. JOHNS 
RIVER, FLA. (See Section 3 of text) 
Channel from Minim Creek to Winyah Bay. 
Channel from Charleston to a point opposite 
McClellanville. 
Branch channel to McClellanville. 
Extending the channel to Minim Creek, thence 
through the Estherville-Minim Canal to 
Winyah Bay. 
Cut across the Santee Delta at Four Mile Creek. 
Widening and deepening the waterway from 
Charleston to Beaufort. 
A waterway 8 feet deep and 75 feet wide from 
Cape Fear River to Winyah Bay. 
Construction of bridges across the waterway in 
Horry County, S. C. 
Cutoff between Ashepoo and Coosaw Rivers. 
Enlarging the channel from Winyah Bay to Charleston 
including the branch channel to McClellanville, to 
depth of 10 feet and bottom width of 90 feet. 
Increasing dimensions of waterway to 12 feet deep 
90 feet wide. 
Anchorage basin 125 feet wide, 335 feet long, 12 feet 
deep, near Myrtle Beach, S.C.4 
CHARLESTON HARBOR, S.C. (See Section 4 of text) 
5 
2 jetties 
Increase in depth to 30 feet with width of 500 feet 
between the jetties and 1,000 feet seaward thereof. 
The 40-foot channel to the Naval Base. Act provided 
that the 40-foot channel should not be undertaken 
"until the proposed new drydocks at this navy yard, 
carrying a depth of 40 feet of water over the blocks, 
has been authorized." This dock was authorized in the 
Naval Appropriation Act approved July 1, 1918 
(40 Stat. L. 725) 
A 30-foot channel from the sea to Goose Creek via 
Cooper River, together with a 30-foot channel 
through Town Creek, for commercial purposes. The 
act also provided that the 40-foot channel be 
prosecuted only as found necessary for national 
defense. 
The 35-foot channel depth from the sea to the head 
of the project via Cooper River and Town Creek, 
also a channel in Shem Creek to Mount Pleasant, 
110 feet wide and 10 feet deep, including a 
turning basin at the upper end. 
An anchorage area 30 feet deep in the water area 
between Castle Pinckney and Fort Moultrie. 6 
Deepen the 30-foot channel north and east of 
Drum Island to 35 feet. 
Shem Creek Channel modified by extending 
1,150 feet upstream and downstream from 
mouth to Atlantic Intracoastal Waterway. 
COOPER RIVER, CHARLESTON, S. C. 
(ST. STEPHEN PROJECT) (See section 5 of text) 
Redivert most of the Santee River waters above 
Pinipolis Dam into the lower Santee River through 
a canal beginning at Lake Moultrie and extending 
to the Santee River in the vicinity of St. 
Stephen, South Carolina. 
Annual Report, 1889, p. 1184. 
H.D. 84, 56th Cong., 1st sess. 
and Annual Report, 1900, p. 1908 
Annual Report, 1903, p. 1133. 
H.D. 178, 63d Cong., 1st sess. 
H. D. 237, 68th Cong., 1st sess. 
S. D. 178, 68th Cong., 2d sess. 
H. D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 14, 72d Cong., 1st sess. 
H. D. 129, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 11, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 6, 75th Cong., 1st sess.3 
H. D. 327, 76th Cong., 1st sess. 
Annual Report 1878, pp. 5 5 3 -5 7 2 . 
H. D. 288, 62d Cong., 2d sess. 
H. D. 1966, 64th Cong., 2d sess., 
pt. 1, pp. 21-29, 57, 58 and 
61-63. 
H. D. 249, 69th Cong., 1st sess. 
H. D. 259, 76th Cong., 1st sess. 
H. D. 156, 77th Cong., 1st sess. 
S. D. 136, 83d Cong., 2d sess. 
H. D. 35, 86th Cong., 1st sess. 
River & Harbor Act of 1968, 
S. D. 88, 90th Cong. 
7-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 7-B (Continued) 
Acts 
AUTHORIZING LEGISLATION 
Work Authorized 
R&H Act of Aug. 5, 1886 
R&H Act of June 25, 1910 
R&H Act of Mar. 2, 1945 
R&H Act of June 30, 1948 
Auth. by Senate Public 
Works Comm. and the 
House Public Works 
Comm. on Oct. 12, 1972, 
under auth. of Sec 201, 
PL 89-298, 1965 
1965-FC Acts. 
Water Resources Development 
Act of 1974 
Auth. by the House Committee 
on Public Works 
on Nov. 10, 1971, and 
the Senate Committee on 
Public Works on Nov. 18, 
1971, under auth. of 
Sec. 201, PL 89-298, 
1966 FC Acts. 
Water Resources Development 
Act of 1974 
R&H Act of Sept. 3, 1954 
R&H Act of July 3, 1930 
R&H Act of Aug. 20, 1935 
R&H Act of Aug. 26, 19378 
R&H Act of Mar. 2, 1945 
GEORGETOWN HARBOR, S. C. (See Section 6 of text) 
Jetties and earthen dike to protect south 
jetty. 
Previous project channel dimensions and training 
wall. 
27-foot channel from ocean, including a turning 
basin in Sampit River. 
Cutoff and side channel in Sampit River. 
LITTLE RIVER INLET, N. C. and S. C. 
(See Section 7 of text) 
Provides for an entrance channel 12 feet by 300 
feet across the ocean bar; thence 10 foot by 90 
foot inner channel to the Atlantic Intracoastal 
Waterway. 
Authorized emergency dredging operations as the 
Chief of Engineers determines necessary to 
maintain channel depths sufficient to permit 
free and safe movement of vessels until such time 
as the authorized project is constructed. 
MURRELLS INLET, S. C. (See Section 8 of text) 
Provides for an entrance channel 12 feet by 300 
feet across the seaward bar; thence 10 foot by 
90 foot inner channel to a turning basin 
at the old Army crash boat dock. 
Authorized emergency dredging operations as the 
Chief of Engineers determines necessary to 
maintain channel depths sufficient to permit 
free and safe movement of vessels until such time 
as the authorized project is constructed. 
PORT ROYAL HARBOR, S. C. (See Section 9 of text) 
A channel from the ocean through Port Royal Sound 
to Port Royal, S. C.; 27 feet deep and 500 feet wide 
across the ocean bar and in Port Royal Sound for 
approximately 12.7 miles, thence 24 feet deep and 
300 feet wide in Beaufort River and Battery Creek 
for approximately 8.3 miles to and including a 
turning basin 27 feet deep and 600 feet wide opposite 
wharf of the S. C. State Ports Authority. 
SHIPYARD RIVER, S. C. (See Section 10 of text) 
Channel depths of 12 and 20 feet. 
28-foot channel from Cooper River to the Gulf Oil 
Corp.'s terminal, and the deepening of the channel 
above that point to 20 feet from the depth of 12 
feet previously authorized without local 
cooperation. 
Enlargement of the channel to a depth of 30 feet and 
a width of 200 feet up to the Gulf Oil Corp.'s 
terminal, with a turning basin 30 feet deep at 
the latter point. 
Extension of the existing 30-foot channel to vicinity 
of the Pittsburgh Metallurgical Co. plant, with a 
turning basin at the upper end. 
H. Ex. Doc. 258, 48th Cong., 
2d sess., and Annual Report 
1885, pp. 1154-1170, and H. 
Ex. Doc. 117, 50th Cong., 2d 
sess., and Annual Report 1889, 
pp. 1110-1115. 
H. D. 398, 58th Cong., 2d sess., 
and Annual Report 1904, pp. 
1591-1609. 
H. D. 211, 76th Cong., 1st sess. 
S. D. 21, 81st Cong., 1st sess. 
H. D. 362-2, 92d Cong. 
H.D. 10203, 93d Cong., 2d sess. 
H. D. 137, 92d Cong. 
H. D. 10203, 93d Cong., 2d sess. 
River & Harbor Act (H. D.469, 
81st Cong., 2d sess.) 
Rivers and Harbors Committee, 
Doc. 13, 71st Cong., 2d sess. 
Rivers and Harbors Committee, 
Doc. 13, 71st Cong., 2d sess. 
Rivers and Harbors Committee, 
Doc. 38, 75th Cong., 1st sess. 
H. D. 93, 79th Cong., 1st sess. 
7-14 
Documents 1 +r + " 
I

CHARLESTON, S.C., DISTRICT 
TABLE 7-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Auth. on Nov. 24, 1965, 
by Chief of Engrs. under 
the Auth. of Sec. 107 
of R&H Act of 1960, as 
amended. 
R&H Act of Oct. 27, 1965 
Flood Control Act of 
July 24, 1946 
Flood Control Act of 
July 24, 1946 
Flood Control Act of 
July 24, 1946 
Auth. by Chief. of 
Engrs. on Apr. 6, 1966 
under auth. of Sec. 205, 
FC Act of 1948, as 
amended. 
Auth. by Chief of 
Engrs. on June 5, 1972 
under auth. of Sec. 205 
FC Act of 1948 as 
amended. 
Water Resources Development 
Act of Mar. 7, 1974 
VILLAGE CREEK, S. C. (See Section 11 of text) 
A channel 8 feet deep and 80 feet wide from the 
mouth of Village Creek upstream to Porpoise Fish 
Company terminal for a distance of 2.2 miles. 
HUNTING ISLAND BEACH, S. C. (See Section 16 of text) 
Provides for periodic nourishment for about 10,000 
feet of beach on the northern part of the island 
with initial placement of 750,000 c.y. of sand for 
advance nourishment, and construction of one 
prestressed concrete groin at the north end of the 
Island. 
YADKIN RIVER, N. C. (See Section 18 of text) 
Construction of four (4) flood control dams in upper 
Yadkin River basin, two (2) on Yadkin River above 
Wilkesboro, N. C., and two (2) on Reddies River, N. C. 
a tributary stream. 
W. KERR SCOTT DAM AND RESERVOIR, YADKIN 
RIVER, N. C. (See Section 18A of text) 
Project consists of an earthfill dam 1,740 feet long 
with crest elevation 1,107.5 feet mean sea level, 
or about 148 feet above stream bed elevation. 
REDDIES RIVER LAKE, N. C. (See Section 18B of text) 
Reddies damsite is located on the Reddies River at mile 
1.7, near the town of North Wilkesboro, N. C. 
Detail Project Report 
9 
H. D. 323, 88th Cong., 2d sess. 
Sec. 10, PL-526, 79th Cong., 
2d sess., S. D. 31, 81st Cong., 
1st sess. 
S. D. 31, 81st Cong., 1st sess., 
Definite Project Report 
S. D. 31, 81st Cong., 1st sess., 
Definite Project Reports 
SUGAR AND BRIAR CREEKS, N. C. (See Section 19 of text) 
Excavation of a 50-foot wide channel up Little Sugar Detail Project Report 
Creek from Archdale Road to station 40+41 which 
is beyond the confluence of Little Sugar and Briar 
Creeks and 40 feet wide up to station 166+28 at 
Princeton Avenue (end of project). 
KINGSTREE BRANCH, WILLIAMSBURG COUNTY, S. C. 
(See Section 20 of text) 
Originates northeast of the town of Kingstree and Detail Project Report 
flows southward through the town to its confluence 
with the Black River. The total length of Kingstree 
Branch is about 6.6 miles. 
ROARING RIVER, WILKES COUNTY, N. C. 
(See Section 21 of text) 
Project is authorized to undertake the phase I design H. D. 10203, 93d Cong., 2d sess 
memorandum stage of advanced engineering and design. 
1. Included in Public Works Administration program, 
Sept. 6, 1933. 
2. Included in Emergency Relief Administration 
program, May 28, 1935. 
3. Contains latest published maps. 
4. Inactive. 
5. Completed under previous projects. 
6. For national defense. 
7. Contains latest published maps. 
8. Included in Emergency Relief Administration 
Program, May 28, 1935. 
9. Contains latest published maps. 
7-15

TABLE 7-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Abbapoola Creek, S.C. 1947 - - 
Aquatic Plant Control, N.C. and S.C. 1968 368,700 1 
Ashley River, S.C.' 1955 260,996 504,337 
Beresford Creek, S.C. 1947 - - 
Congaree River, S.C. 1950 364,824 541,860 
Edisto River, S.C. ' 1938 33,103 900 
Great Pee Dee River, S.C."3 1950 183,712 269,673 
2,4 
Little Pee Dee River, S.C. 1919 19,550 25,650 
Lumber River, N.C. and S.C. 1897 19,000 - 
Lynches River and Clark Creek, S.C. 1910 9,500 - 
Mingo Creek, S.C. 1950 29,050 7,150 
Russell Creek. S.C. 1947 - - 
Salkahatchie River, S.C.1 1896 15,841 - 
Santee River, N.C. and S.C.' 1950 99,750 178,544 
Waccamaw River, N.C. and S.C." 1970 262,814 264,913 
Wateree River, S.C."2 1940 60,000 151,784 
Yadkin River, N.C.2 '4 1892 102,809 - 
1. Completed. 4. Abandonment recommended in 1926 (H. D. 467, 69th 
2. No Commerce reported. Cong., 1st sess.). 
3. Curtailment recommended in 1926 (H. D. 467, 69th 
Cong., 1st sess.). 
TABLE 7-D DAMS AND RESERVOIRS 
(See Sections 18 and 21 of text) 
Design and Cost 
Project Name River Construction Land Relocations Total 
Yadkin River W. Kerr Scott Yadkin $ 5,335,169 $ 1,873,657 $ 1,487,000 $ 8,695,8261 
N.C. Dam and 
Reservoir 
Reddies Reddies 16,538,000 2,620,000 3,042,000 22,200,000 
Roaring River Roaring Roaring 2 
Lake River River 18,740,000 2,000,000 660,000 21,400,000 
1. Actual 
2. Estimate 1975. 
7-16

CHARLESTON, S.C., DISTRICT 
FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Preauthorization studies pursuant to Sec. 205. 
(See Section 22 of text.) 
FISCAL YEAR COSTS 
Gills Creek, S. C. 0 
Johns Island, S. C. 1 
Kingstree Branch, S. C. 9,539 
Leith's Creek, N. C. 16,167 
Little River, Laurens County, S. C. 12,599 
Mill Creek, McDowell County, N. C. 8,600 
Richardson Creek, N. C. 10,685 
Scotts Creek, Newberry, S. C. 2 51,274 
Soules Swamp, N. C. 1,020 
Turkey Creek, Berkeley County, S. C. 65,638 
1. Study being held in abeyance at request of local in- review and approval. 
terest. 3. Study awaiting funding by OCE. 
2. Detailed Project Report has been submitted to OCE for 
TABLE 7-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Buck Creek, N.C. and S.C. 1'2 1970 298,167 - 
California Branch, S.C.1 1971 8,821 - 
Cowpens Swamp, S.C.1'2 1960 18,679 - 
Crabtree Swamp, S.C. 1' 1969 97,000 - 
Edisto River, S.C.1'2 1969 127,660 - 
Gapway Swamp, N.C. and S.C."2 1969 339,197 
1,2 
Old Field Swamp, N.C. 1969 86,600 - 
Reedy River, S.C. 1974 4,500 - 
Sawmill Branch, S.C."2 1971 248,605 - 
Shot Pouch Creek, Sumter County, S.C. 1'2 1971 77,400 - 
Simmons Bay, N.C. 1963 186,434 - 
Simpson Creek, S.C.2 1957 81,000 - 
1,2 
Todd Swamp, S.C. 1964 29,000 - 
Turkey Creek, Sumter County, S.C."2 1974 319,667 - 
Waccamaw River, N.C. and S.C. 1961 67,821 - 
1. Authorized by Chief of Engineers. 
2. Completed. 
3. Discontinued due to lack of interest. 
7-17 
TABLE 7-E 
STUDY IDENTIFICATION

TABLE 7-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
FLOOD PLAIN STUDIES COMPLETED 
DURING FISCAL YEAR 
(See Section 25 of text) 
Location Requesting Date Federal 
Agency Completed Cost 
Broad River, Saluda River, Central Midlands Regional Aug 1974 50,000 
Congaree River, Richland & Planning Council, Columbia, 
Lexington Counties, S.C. S.C. 
Stoney Branch and Tributaries, City of Rock Hill, S.C. Sep 1974 40,000 
Rock Hill, S.C. 
Richardson Creek and Bearskin City of Monroe, N.C. Oct 1974 30,000 
Creek, Monroe, N.C. 
7-18

SAVANNAH, GA., DISTRICT* 
The district comprises drainage basins 
tributary to the Atlantic Ocean between Port 
Royal Sound, S.C., and Cumberland Sound, Ga. 
and Fla., including the Atlantic Intracoastal 
Waterway between these points. This area covers 
the headwaters of the Savannah River in 
southwestern North Carolina, a considerable portion 
of western South Carolina, eastern Georgia, 
and a small portion of northeastern Florida. 
IMPROVEMENTS 
Page 
8-1 
8-2 
8-3 
8-3 
8-4 
8-5 
8-6 
8-7 
8-7 
8-7 
8-7 
Navigation j 
1. Altamaha, Oconee, and Ocmulgee 
Rivers, Ga. ..................... 
2. Aquatic Plant Control .......... 
3. Atlantic Intracoastal Waterway 
Between Norfolk, Va., and St. Johns 
River, Fla. (Savannah District) .. 
4. Brunswick Harbor, Ga. ......... 
5. Darien Harbor, Ga. ............. 
6. Savannah Harbor, Ga ........... 
7. Savannah River Below 
Augusta, Ga. ................. 
8. Reconnaissance and Condition 
Surveys ........................ 
9. Other Authorized Navigation 
Projects ...................... 
10. Navigation Work Under Special 
Authorization .................. 
Beach Erosion Control 
11. Tybee Island, Ga. ............... 
Flood Control 
12. Dunn Branch, Woodbine, 
Camden County, Ga. ............ 
13. Peacock Creek, Liberty County, 
Ga ............................ 
Navigation 
1. ALTAMAHA, OCONEE, AND 
OCMULGEE RIVERS, GA. 
Location. These rivers are entirely within the 
State of Georgia. (See National Oceanic and Atmospheric 
Administration Survey Map of 
Georgia, formerly U. S. Geological Survey map of 
Georgia.) For full description of these rivers, seer 
page 636, Annual Report for 1932. 
Flood Control (cont.) 
14. Inspection of Completed Flood 
Control Projects ................ 
15. Other Authorized Flood Control 
Projects ...................... 
16. Flood Control Work Under Special 
Authorization .................. 
Multiple-Purpose Projects 
Including Power 
17. Savannah River Basin, Ga. 
and S.C ........................ 
17A. Clark Hill Lake, Ga. and S.C. ... 
17B. Hartwell Lake, Ga. and S.C. .... 
17C. Richard B. Russell Dam and Lake, 
Ga. and S.C. (Formerly Trotters 
Shoals Lake, Ga. and S.C.) ...... 
18. West Point Lake, Chattahoochee 
River Basin, Ga. and Ala. ....... 
General Investigations 
19. Surveys ........................ 
8-8 20. Collection and Study of Basic 
Data ........................... 
8-8 21. Research and Development ..... 
Page 
8-8 
8-8 
8-8 
8-9 
8-9 
8-9 
8-10 
8-10 
8-10 
8-10 
8-10 
Previous projects. Prior projects for the 
Altamaha River have been adopted, and expenditures 
made under them, by River and Harbor 
Acts of March 3, 1881, and September 19, 1890; 
for the Oconee River by River and Harbor Acts of 
June 18, 1878, September 19, 1890, and March 3, 
1905; for the Ocmulgee River, by River and Harbor 
Acts of August 14, 1876, and September 19, 
1890. 
* All costs and financial statements for projects are listed at the end of this chapter. Other tables referenced in the text also 
appear at the end of this chapter. 
8-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
For further details, see page 1815, Annual 
Report for 1915, and page 589, Annual Report for 
1938. 
Existing project. The authorized project 
provides for an appropriation of $40,000 annually 
for the Altamaha, Oconee, and Ocmulgee Rivers, 
to maintain a 3-foot depth during ordinary 
summer low water and to gradually increase 
channel depth, so far as practicable without 
sacrificing the maintenance work. This project 
covers the entire Altamaha River (including a 
channel between the river and Darien, Ga.), a 
length of 137 miles, the lower 139 miles of the 
Oconee River, and the lower 199 miles of the 
Ocmulgee River. The Altamaha River has a mean 
tidal range of 6.4 feet at its mouth which gradually 
decreases to mile 33 above, where there is no 
perceptible tidal effect. At Doctortown, mile 59, 
ordinary floods attain a height of about 10 feet 
above low water, and extreme floods, a height of 
about 15 feet above low water. 
On the Oconee River at Dublin the ordinary 
fluctuations attain a height of 22 feet, and the extreme 
fluctuations a height of 32 feet, above low 
water. On the Ocmulgee River at Macon the 
ordinary fluctuations attain a height of 15 feet, 
and the extreme fluctuations a height of 25 feet, 
above low water. There is no approved estimated 
cost for improvement or for maintenance. 
Published maps of these rivers are in the 
following documents: Altamaha River, House 
Executive Document 283, Fifty-first Congress, 
second session; Oconee River, House Executive 
Document 211, Fifty-first Congress, first session; 
Ocmulgee River, House Executive Document 
215, Fifty-first Congress, first session; and Lower 
Altamaha River and Darien Harbor, Ga., House 
Document 610, Seventy-seventh Congress, second 
session. (See Table 8-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Along these rivers there 
are numerous natural shore landings which are 
considered ample for existing commerce. 
Facilities for recreational boats have been constructed 
in recent years at several points. 
Operations and results during fiscal 
year. Maintenance: Hired labor snagging work 
was performed by crane barge No. 2 with towboat 
Tomkins and during period February 18, 1975 to 
May 18,1975 removed 3,705 snags at a cost of $55,- 
823. This snagging was performed with contributed 
funds from Georgia Power Company. 
Other cost incurred, including condition and 
operation studies, hydrographic surveys, and 
water pollution and environmental studies, 
amounted to $2,330. (See Table 8-A for Cost and 
Financial Statement.) 
Condition at end of fiscal year. The existing 
project is such that the percentage of completion 
cannot be stated. Channel depths have been increased 
by excavating rock shoals and sandbars, 
by constructing contraction and bank-protection 
works, and by closing cutoffs. Navigation has 
been rendered safer by removing obstructions. 
Many of the closing dams and contractions and 
bank-protection works need repairs. The draft 
Environmental Impact Statement was filed with 
CEQ on July 11, 1975. 
To June 30, 1975, costs under the existing project 
were $60,847 for new work and $1,707,587 for 
maintenance, of which $69,356 were contributed 
funds, a total of $1,768,434. (See Table 8-A for 
Cost and Financial Statement.) 
2. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary 
streams, connecting channels, and other allied 
waters in Savannah District. 
Existing project. The project provides for control 
and progressive eradication of waterhyacinth, 
alligatorweed, Eurasian water milfoil, 
and other obnoxious aquatic plant growths, from 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in the combined interests of navigation, 
flood control, drainage, agriculture, fish and 
wildlife conservation, public health, and related 
purposes, including continued research for 
development of most effective and economic control 
measures in cooperation with other Federal 
and State agencies in accordance with report of 
Chief of Engineers, House Document 251, 89th 
Congress, 1st session. The authorizing act 
provides that research and planning costs shall be 
borne fully by the United States. (See Table 8-B 
for Authorizing Legislation.) 
Local cooperation. Local interests must agree 
to hold the United States free from damages that 
may occur from operations performed in connection 
with this project and participate to the extent 
of 30 percent of the cost of the program. Requirements 
are being met. 
Operations and results during fiscal 
year. Georgia Game and Fish Commission, who 
maintain surveillance of potential aquatic plant 
problem areas, reported aquatic plant infestation 
in the Satilla River and in other river basins in the 
State of Georgia. Cost during the fiscal year was 
$999. (See Table 8-A for Cost and Financial Statement.) 
8-2

SAVANNAH, GA., DISTRICT 
3. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN NORFOLK 
VA., AND THE ST. JOHNS 
RIVER, FLA. (SAVANNAH DISTRICT) 
Location. This 161 mile section of waterway 
connects Port Royal Sound, S. C., with 
Cumberland Sound, Ga. and Fla. (See NOAA 
charts 11489 - 11507, formerly Coast and 
Geodetic Survey Charts 838-841, inclusive.) 
Previous projects. (Between Savannah, Ga., 
and Fernandina, Fla.) For details see Annual 
Reports for 1915 and 1938. 
Existing project. The project provides for a 
waterway 12 feet deep at mean low water and not 
less than 90 feet wide between Port Royal Sound, 
S.C., and Savannah, Ga.; 12 feet deep at mean 
low water, with widths of 90 feet in land cuts and 
narrow streams and 150 feet in open waters, 
between Savannah, Ga., and Cumberland Sound, 
Ga. and Fla.; and a suitable anchorage basin at 
Thunderbolt, Georgia. Mean tidal range between 
Port Royal, S. C., and Cumberland Sound, Ga. 
and Fla., is from 6 to 8 feet, with fluctuations from 
1 and one-half to 2 and one-half feet, due to winds 
and lunar phases. (See Table 8-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Exclusive of adequate terminal 
facilities at ports of entry, this improvement 
serves numerous wharves, some of which 
are open to the public on equal terms. Facilities 
are considered ample for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Government cost for 
preparation of plans and specifications for dredging 
in the Atlantic Intracoastal Waterway to be 
advertised early in the next fiscal year amounted 
to $20,671. The government cost for condition and 
operation studies, water pollution and environmental 
studies amounted to $51,862. Survey 
of waterway and inspection reports amounted to 
$232. District overhead and other miscellaneous 
costs amounted to $8,358. Total cost for the year 
amounted to $81,123. (See Table 8-A for Cost and 
Financial Statement.) 
Condition at end of fiscal year. The main 
channel of the existing project, completed in 
1941, is maintained at 12 feet. The former main 
channel, now an alternate route through the 
westerly end of the South Channel and northerly 
end of Wilmington River, will be maintained to a 
depth of 7 feet mean low water for traffic points 
north and south of Savannah Harbor. The draft 
Environmental Impact Statement was filed with 
CEQ on February 25, 1975. 
Costs of the existing completed project to June 
30, 1975, were $763,599 for new work and $9,098,- 
692 for maintenance, a total of $9,862,291. (See 
Table 8-A for Cost and Financial Statement.) 
4. BRUNSWICK HARBOR, GA. 
Location. The Harbor entrance is 70 statute 
miles south of the entrance to Savannah Harbor, 
Ga., and 25 statute miles north of the entrance to 
Fernandina Harbor, Florida. (See NOAA Chart 
11215, formerly Coast and Geodetic Survey Chart 
447.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938. 
Existing project. The project provides for a 
stone jetty 4,350 feet long at the entrance to East 
River and the following channels: 32 feet deep 
and 500 feet wide across the bar; 30 feet deep and 
400 feet wide through St. Simons Sound, 
Brunswick River, and East River to the foot of 
Second Avenue; 30 feet deep and 300 feet wide in 
Turtle River to the Allied Chemical Co. wharf, 
formerly the Atlantic Refining Co.; 27 feet deep 
and 350 feet wide in East River from Second 
Avenue to its confluence with Academy Creek; 24 
feet deep and 150 feet wide in Academy Creek; a 
channel in Back River 20 feet deep and 150 feet 
wide from St. Simon Sound to the mouth of Mill 
Creek; and a channel in Terry Creek 10 feet deep 
and 80 feet wide from its mouth to a point 
immediately above the wharf of Glynri Canning 
Company. All depths refer to mean low water. 
Mean tidal range on the bar is 6.5 feet, at the city 
of Brunswick 7.3 feet, and 7.6 feet at the upper 
end of the harbor. For further details see Annual 
Report for 1962. 
Local cooperation. Complied with to date. 
Terminal facilities. Twenty-eight wharves 
and piers, almost all privately owned, have a 
berthing space of 11,444 feet. In addition, the Port 
of Brunswick and the State of Georgia have a 
transit shed and modern docks with 1,500 feet of 
aprons on East River. A tank farm for handling 
residual oil has been constructed on Brunswick 
Port Authorities' property. For further details 
see-Port Series No. 14, Corps of Engineers (revised 
1972). 
Operations and results during fiscal 
year. Maintenance: The U.S. sidecaster dredge 
Schweizer removed 81,370 cubic yards of 
material from the bar channel during the period 
of April 10, 1975 to May 15, 1975 at a total cost of 
$49,596, including inspection, overhead, and 
other government costs. The U.S. hopper dredge 
Davison removed 158,579 yards of material from 
the bar channel during the periods of September 
12, 1974 to October 15, 1974 and December 18, 
1874 to January 14, 1975 at a total cost of 
$367,212, including inspection, overhead and 
8-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
other government costs. A contract for 
maintenance dredging of East River and the 
closure of Academy Creek was awarded March 
21, 1975. The contract dredge Natchez removed 
315,000 cubic yards of material from East River 
and the contract dredge Two Brothers completed 
twenty percent of the Academy Creek closure at a 
total cost for the fiscal year of $233,044 including 
inspection, overhead and other government costs. 
A contract was awarded May 13, 1974 and completed 
June 19, 1975 for the construction of a 
drainage canal and dike on Academy Creek at a 
total cost this fiscal year of $63,998, including inspection, 
overhead, and other government costs. 
Routine condition surveys, water, air, and environmental 
studies, inspection and reports, and 
other essential activities amounted to $49,031. 
Distribution of Engineer yard and radio communications 
cost and other year end adjustments 
amounted to $21,686. Contributed credits received 
for dredging amounted to $16,578. Total 
operation and maintenance cost amounted to 
$765,567. (See Table 8-A for Cost and Financial 
Statement.) 
Condition at end of fiscal year. The existing 
project was completed in December 1960. 
General condition of the harbor works is satisfactory, 
providing maintenance dredging continues. 
Costs for existing completed project to June 30, 
1975, were $16,074,916, of which $3,430,143 was 
for new work including $10,000 contributed 
funds and $12,644,773 for maintenance, including 
$66,233 contributed costs. (See Table 8-A 
for Cost and Financial Statement.) 
5. DARIEN HARBOR, GA. 
Location. Darien Harbor is 18.5 statute miles 
north of Brunswick Harbor, Ga. and comprises 
the lower 12 miles of Darien River, from the town 
of Darien, where the channel width is about 300 
feet, to Doboy Sound, where the river channel 
width is about 1,000 feet. (See NOAA Charts 
11510 and 11502 formerly U.S. Coast and 
Geodetic Survey Charts Nos. 574 and 1242.) 
Previous projects. For details see Annual 
Reports for 1915, 1950 and 1968. 
Existing project. This provides for the removal 
of the seven shoals between Darien and Doboy 
Sound by dredging, to secure a depth of 12 feet at 
mean low water, and for constructing wing dams 
at five of these shoals to maintain the depth of the 
improved channel. The channel width to be maintained 
was not specified, but should be about 150 
feet. Mean tidal range is 7 feet on the bar and 6.5 
feet at Darien. Estimated cost of the improvement, 
made in 1890, was $170,000, exclusive of 
amount expended on previous project. No estimate 
for annual cost of maintenance has been 
necessary. The latest published map is in House 
Document 1354, Sixty-second Congress, third 
session. 
Local cooperation. None required. 
Terminal facilities. There are four privately 
owned wharves and one small municipal wharf. 
All are open pile-and-timber structures. The 
municipal wharf is open to the public and the 
privately owned wharves are open to the public 
only on the consent of the lessee or owner. All 
wharves have highway connections but no rail 
connections. Existing facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: No maintenance dredging 
was done in the Darien Harbor during FY 75, but 
condition surveys were conducted at a total cost of 
$3,038 for the fiscal year. 
Condition at end of fiscal year. The existing 
project was completed in 1905. 
Costs of the existing project to June 30, 1975 
were $199,723 for new work and $182,904 for 
maintenance, a total of $382,627. (See Table 8-A 
for Cost and Financial Statement.) 
6. SAVANNAH HARBOR, GA. 
Location. Harbor entrance is 75 statute miles 
south of Charleston Harbor, S.C., and 70 statute 
miles north of Brunswick Harbor, Ga. (See 
NOAA Chart 11512, formerly Coast and Geodetic 
Survey Chart 440.) 
Previous projects. For details see Annual 
Reports for 1915 and 1938. 
Existing project. The project provides for a 
channel 40 feet deep and 600 feet wide across the 
ocean bar about 7.0 miles; 38 feet deep and 500 
feet wide to the Seaboard Coast Line terminal; 38 
feet deep and 400 feet wide to the vicinity of Garden 
City (Georgia Ports Authority terminal); and 
36 feet deep and 400 feet wide to the vicinity of 
Savannah Sugar Refining Corporation, about 
22.6 miles; and 30 feet deep and 200 feet wide to a 
point 1,500 feet below the Atlantic Coastal 
highway bridge, about 1.5 miles, a total length of 
31.1 miles; two turning basins 34 feet deep by 900 
feet wide by 1,000 feet long in the vicinity of the 
Seaboard Coast Line terminal, and American Oil 
Company terminal; one turning basin 34 feet 
deep by 980 feet wide by 1,000 feet long in the 
vicinity of Garden City terminal of the Georgia 
Ports Authority; two turning basins 30 feet deep 
by 600 feet wide by 600 feet long near Savannah 
Sugar Refining Corporation terminal and at the 
extreme upper limit of the project near Continental 
Can Company terminal. The project also 
provides for sediment control works consisting of 
a tide gate structure across Back River: a sedi- 
8-4

SAVANNAH, GA., DISTRICT 
ment basin 40 feet deep, 600 feet wide, about 2 for this fiscal year amounted to $1,134,568, inmiles 
long, with an entrance channel 38 to 40 feet . cluding government cost. A continuing contract 
deep and 300 feet wide; a drainage canal across was awarded February 14, 1974 for construction 
Argyle Island 15 feet deep and 300 feet wide; con- of fresh water diversion channels and it was comtrol 
works and canals for supplying fresh water to pleted November 30, 1975. Under this contract 
the Savannah National Wildlife Refuge; and the clamshell dredge removed 441,340 cubic 
facilities to mitigate damages to presently im- yards of material at a total cost this fiscal year of 
proved areas other than refuge lands. Mean $562,653, including inspection, overhead and 
range of tide is 7.9 feet at the upper end of the har- other government cost. A contract was awarded 
bor and 6.9 feet at the lower end. Extreme ranges June 11, 1973 for repair and erosion protection of 
are about 11.1 and 10.7 feet, respectively. Latest the east bank at Fort Jackson and the cost for this 
(FY-75) estimate of total Federal Cost for new fiscal year amounted to $62,409. Engineering and 
work modification is $23,792,000 ($13,292,000 for design, supervision, and other cost, for the tide 
the Widening and Deepening of Channels and gate structure, fresh water control stuctures, and 
Turning Basin which includes $192,000 U. S. diversion channels amounted to $286,127. The 
Coast Guard costs, and $10,500,000 for the Sedi- total cost for new work during this fiscal year 
ment Basin and Appurtenant Works). Estimated amounted to $3,921,110. (See Table 8-A for Cost 
local cost for Widening and Deepening is and Financial Statement.) 
$367,000 and for the Sediment Control Works is 
$455,000. 
Local cooperation. Local interests must 
provide suitable spoil areas and retaining dikes 
for construction and future maintenance of the 
project. The Chatham County Commissioners, as 
local assurers, have met all requirements to date. 
Terminal facilities. Fifty piers and wharves 
adequately serve existing waterborne commerce 
of the port. These facilities, with use of dolphins, 
have a combined berthing space of 29,600 feet 
with water depths alongside ranging up to 34 feet 
at mean low water. Included in the berthing 
space are two container berths with 48 acres of 
handling area. All have railway and highway 
connections. LASH facilities are located at the 
entrance to the harbor and have depths ranging 
up to 38 feet mean low water. The berthing space 
of LASH facilities is included in the above combined 
berthing space. For further details, see 
Port Series No. 14, Corps of Engineers (revised 
1972) and Annual Report for 1962. 
Operations and results during fiscal year. New 
Work: Activities in connection with Sediment 
Basin and Appurtenant Works modification and 
bar channel improvements continued with the 
U.S. hopper dredge Goethals removing 1,146,262 
cubic yards of material from the bar channel 
under the Widening and Deepening authority 
during the period from July 31, 1974 to 
September 29, 1974 at a total cost of $1,090,645, 
including inspection, overhead, and other government 
cost. Other government cost for design, 
engineering, and real estate activities amounted 
to $51,227. A continuing contract was awarded 
March 29, 1972 for construction of the tide gate 
structure and access road, and the cost for this 
fiscal year amounted to $733,481, including 
government cost. Another continuing contract 
was awarded October 9, 1973 for the construction 
of fresh water canals and structures and the cost 
Maintenance: The U.S. pipeline dredge Henry 
Bacon dredging the inner harbor channels and 
turning basins between McQueens Cut and 
Rhodes Cut during this fiscal year removed 
5,522,920 cubic yards of shoal material at a cost of 
$2,998,532, including inspection and other 
government cost. The contract pipeline dredge 
Dauntless during the period from November 3, 
1974, to June 3, 1975 removed 1,980,984 cubic 
yards of shoal material from the lower channel 
reaches of the Savannah River at a total cost of 
$1,227,761, including inspection and other 
government administrative cost. The U.S. hopper 
dredge Hyde removed 96,503 cubic yards of shoal 
material from the bar channel during the period 
from November 14, 1974 to January 14, 1975 at a 
total cost of $298,397, including inspection, 
overhead and other government costs.. Dragging 
and sweeping by government plant for removing 
underwater obstructions amounted to $22,604. 
(Credits received from agitation dredging of 
private shipping interest slips amounted to 
$47,995.) Distribution of Engineer Yard cost 
amounted to $219,643. Condition surveys, water 
quality monitoring, water and air pollution 
studies, environmental studies, sedimentation 
probe testing, inspection and reports, and government 
supervision and administration costs were 
$184,509. Total operation and maintenance cost 
for the fiscal year, not including agitation credit, 
amounts to $4,903,451 (See Table 8-A for Cost and 
Financial Statement.) 
Condition at end of fiscal year. The existing 
project is incomplete. Training walls, jetties, and 
other structures are in fair condition. Authorized 
channels are maintained by a planned dredging 
program with work at critical areas when 
necessary. 
Costs of existing project to June 30, 1975, were 
$29,506,676 Federal cost and $305,248 contributed 
funds for new work and $61,066,672 
8-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Federal cost and $846,096 contributed funds for 
maintenance, a total of $91,724,692. (See Table 8- 
A for Cost and Financial Statement.) 
7. SAVANNAH RIVER BELOW 
AUGUSTA, GA. 
Location. Savannah River is formed by the 
confluence of the Tugaloo and Seneca Rivers on 
the boundary line between South Carolina and 
Georgia. It flows southeast 314 miles, forming the 
boundary line between the two states, and empties 
into the Atlantic Ocean 16.6 miles below 
Savannah, Ga. (See NOAA Charts 11514 and 
11515, formerly Geological Survey maps of South 
Carolina and Georgia.) 
Previous project. For details see Annual 
Reports for 1915 and 1938. 
Existing project. The authorized project 
provides for a channel 9 feet deep and 90 feet wide 
(at ordinary summer flow of 5,800 second-feet at 
Augusta, Ga.) from the upper end of Savannah 
Harbor to the head of navigation at Augusta, 3 
miles above Fifth Street Bridge, a total distance 
of about 181 miles. A lock and dam is located approximately 
15 miles below the upper limit of the 
project at New Savannah Bluff. Improvement is 
to be obtained by construction of contraction 
works, closure of cutoffs, bank protection, dredging, 
removal of snags, overhanging trees and 
wrecks, and open-river regulation. Mean tidal 
variation at the mouth of the river is 7 feet. 
Freshet variation above the normal pool level 
(elevation 114.5 mean sea level) of New Savannah 
Bluff lock and dam at mile 187 is ordinarily about 
13 feet with an extreme of 34 feet. Latest approved 
project cost estimate for providing a 9-foot 
channel (Sept. 1963) is $6,576,000 exclusive of 
amounts expended on previous projects. Recreation 
facilities at New Savannah Bluff lock and 
dam cost $17,000. For further details see Annual 
Report for 1962. 
Local cooperation. Complied with to date. The 
City Council of Augusta, Ga., and the Georgia and 
South Carolina Ports Authorities have agreed to 
act as local assurer. 
Terminal facilities. The only water terminals 
served by this improvement are at Augusta, 
Sylvania, and at or near Savannah. Augusta 
provided a municipal dock valued at $50,000 and 
Georgia Ports Authority constructed a State port 
at Augusta, Ga., costing about $418,000. These 
facilities were expanded in 1965 at an additional 
cost of about $250,000. In addition, Swann Oil 
Company of Georgia maintains a terminal below 
Augusta and Allied Chemical Co. maintains a terminal 
at Sylvania. These are supplemented by 
natural landings along the river and extensive 
facilities at Savannah. 
Operations and results during fiscal 
year. Maintenance: A contract was awarded 
September 5, 1974 and completed January 31, 
1975 for the placing of 2,150 tons of dumped stone 
bank revetment at two sites on the Savannah 
River at a total cost for the fiscal year of $115,316 
including inspection, overhead and other government 
cost. Snagging operations performed by 
U.S. crane barge No. 2 with towboat Tomkins 
removed 5,708 snags during periods of July 1, 
1974 to November 29, 1974 at a cost which 
amounted to $59,765. Routine maintenance and 
operation of the New Savannah Bluff Lock and 
Dam and its recreational area, which accommodated 
207,650 visitors, amounted to $139,063. 
Routine condition surveys, real estate activities, 
water pollution and environmental studies, inspection 
and reports and other administrative 
costs amounted to $7,643. Distribution of 
Engineer Yard cost and other year end adjustments 
amounted to $9,071. Credits received 
for housing of lock employees amounted to $2,525. 
Total operation and maintenance cost for the 
fiscal year amounted to $328,333. (See Table 8-A 
for Cost and Financial Statement.) 
Condition at end of fiscal year. In general, 
open-channel works are in good condition. Project 
depth of 9 feet was maintained 70 percent of fiscal 
year. 
Costs of existing project to June 30, 1975, were 
$13,983,283 of which $6,646,551 was for new 
work and $7,336,732 for maintenance. (See Table 
8-A for Cost and Financial Statement.) 
8. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 8-C.) 
9. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 8-D.) 
10. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645, as amended (Preauthorization 
Studies). Fiscal year costs for preauthorization 
studies were $60,940. Reconnaissance reports 
were completed for Belleville Point, Ga., and 
Cedar Point, Ga., and a detailed study was initiated 
for Wilmington River Bar Channel, Ga. 
Beach Erosion Control 
11. TYBEE ISLAND, GA. 
Location. Tybee Island is located directly 
8-6

SAVANNAH, GA., DISTRICT 
south of Savannah River entrance, about 17 miles 
east of the City of Savannah, Georgia. (See NOAA 
Charts 11512, 11513 and 11509, formerly U. S. 
Coast and Geodetic Survey Charts Nos. 440,1230, 
and 1241, and on maps included in H. D. 92-105, 
92d Cong.) The only portion of the island that has 
been developed is bounded on the north by the 
south channel of the Savannah River, on the east 
by the Atlantic Ocean, and on the south and west 
by Tybee Creek and other small tidal streams. 
This area, hereinafter referred to as "Tybee 
Island," is occupied by the town of Savannah 
Beach. The ocean face of this area has had a wide 
sandy beach. Tybee Island is about 3.5 miles long 
from its northerly tip to the mouth of Tybee Creek 
with an average width of about 0.5 mile. Behind 
the beach lies a line of sand dunes, a number of 
which have been removed during the years to 
make room for improvements and for various 
other reasons. Those that remain are from 10 to 20 
feet high. The ground elevation west of the dunes 
is from 10 to 18 feet and slopes westward to the 
salt marsh. 
Existing project. The approved project plan of 
improvement provides for an 800-foot rock groin 
at the north end of the island, with a 225-foot tie-in 
to high ground. An additional 1,200-foot extension 
of this groin is deferred, as are two additional, 
intermediate groins (480 feet long); these 
will be added at a later date, if needed. The plan 
also provides for the initial restoration of approximately 
13,300 feet of beach, from the vicinity 
of 18th Street to the new terminal groin located 
at the northern end of the island. Periodic 
nourishment will be provided as needed to maintain 
suitable beach dimensions. 
Local cooperation. Local interests must: (a) 
contribute in cash the required percentage of the 
first cost, including costs for construction, 
engineering, and design, and administration; and 
excluding the cost of lands, easements, rights-ofway, 
and relocations; of all items of work to be 
provided by the Corps of Engineers, presently 
estimated at 51.0 percent or $2,830,000 (FY 75 
estimate) to be paid in a lump sum prior to start of 
construction or in installments prior to the start 
of pertinent work items in accordance with construction 
schedules as required by the Chief of 
Engineers, the final apportionment of cost to be 
made after the actual costs have been determined; 
(b) contribute in cash the required percentage 
of beach nourishment costs for the first 10 
years of project life, now estimated at 51.0 percent 
of $126,300 annually, such nourishment costs 
for the first 3-year period of the project, estimated 
at $378,900, to be provided for advance nourishment 
at the time of first construction, and following 
contributions to be made prior to each 
nourishment operation; (c) provide maintenance 
and repair of the groins, and provide, after the 
first 10 years of project life, periodic nourishment 
of the restored beach as may be required to serve 
the intended purpose during the life of the project; 
(d) provide without cost to the United States 
all lands, easements, rights-of-way, and 
relocations required for construction and subsequent 
nourishment of the project; (e) hold and 
save the United States free from claims for 
damages that may result from construction, 
maintenance, and nourishment of the project; (f) 
control water pollution to the extent necessary to 
safeguard the health of bathers; and (g) provide 
without cost to the United States access and 
facilities necessary for realization of the public 
benefits upon which Federal participation is 
based, and maintain continued public use of the 
beach and administer it for public use during the 
life of the project; and provided further, that construction 
on the project shall not be started until 
local interests furnish lands for beach access and 
parking, satisfactory to the Chief of Engineers, 
for the reach from 1st Street to the terminal 
groin. To date, local cooperation is being provided 
as required. 
Operations and results during fiscal 
year. Federal cost of activities during the year 
amounted to $392,875 and $351,690 was expended 
from non-Federal contributions. (See Table 8- 
A for Cost and Financial Statement.) 
Condition at end of fiscal year. The final Environmental 
Impact Statement was filed with 
CEQ on November 13, 1973. The initial construction 
contract for the terminal groin was awarded 
September 13, 1974 in the amount of $980,642. 
The groin was completed and formally accepted 
on June 17, 1975. The contract for initial beach fill 
and advance nourishment was awarded June 18, 
1975 in the amount of $2,175,000. Contract completion 
was scheduled for mid fiscal year 1976. 
Total project cost is estimated to be $5,540,000, 
which includes $2,830,000 in non-Federal, contributed 
funds. Costs to date of existing project 
were $495,321 (Federal funds) and $426,690 (contributed 
funds). 
Flood Control 
12. DUNN BRANCH, WOODBINE, 
CAMDEN COUNTY, GA. 
Location. Dunn Branch is located in the lower 
Coastal Plains Province in the Satilla River Basin 
in southwestern Georgia. It rises just outside the 
southwestern portion of the City of Woodbine and 
flows in an easterly direction through the city to 
its confluence with the Satilla River. The stream 
is approximately 12,000 feet long and drains most 
of the city of Woodbine. 
8-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. The plan of improvement consists 
of excavating a channel along Dunn Branch 
beginning at a point 1,300 feet above its confluence 
with the Satilla River and extending upstream 
to just below North Brewster Avenue, a 
total distance of approximately 2,900 feet. 
Local cooperation. Local officials have furnished 
the requirements of local cooperation. 
Operation and results during fiscal 
year. Preconstruction planning and preparation 
of plans and specifications were completed, and a 
contract was awarded June 4, 1975. Cost for the 
fiscal year was $20,159. 
Condition at end of fiscal year. Planning has 
been completed and construction is scheduled to 
begin early in fiscal year 1975. Total costs to date 
of the project were $46,459, which includes 
$26,300 for preauthorization studies. (See Table 
8-A for Cost and Financial Statement.) 
13. PEACOCK CREEK, LIBERTY 
COUNTY, GA. 
Location. Peacock Creek is located in the 
eastern portion of Liberty County and empties 
into the Atlantic Ocean through North Newport 
River. Peacock Creek and tributaries drain a portion 
of the Fort Stewart Military Reservation and 
sizeable swamps in the vicinity of Hinesville, 
Flemington, and McIntosh, Georgia. 
Existing project. The approved plan of 
improvement provides for channel clearing and 
excavation of approximately 6.8 miles on Peacock 
Creek, 3.3 miles on Captain Fleming Swamp, 4.8 
miles on the main stem of Melvin Swamp, 4.2 
miles on the minor stems of Melvin Swamp, 3.6 
miles on the main stem of Goshen Swamp, and 1.7 
miles on the minor stems of Goshen Swamp. 
Adequate waterway openings beneath state, 
Federal, and county maintained roads and lateral 
and on-farm drainage will be provided by local 
interests. 
Local cooperation. The County Commission of 
Liberty County has furnished the requirement of 
local cooperation. 
Operations and results during fiscal 
year. Construction was completed during the 
fiscal year 1974. Total cost for the fiscal year 1975 
was -$30,023 due to receipt of contributed funds 
for prior year non-Federal cost. 
Condition at end offiscal year. Construction of 
the project improvements was complete. Costs of 
the project were $582,156 which includes $45,000 
preauthorization studies, but does not include 
$37,691 contributed funds. (See Table 8-A for 
Cost and Financial Statement.) 
14. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Physical inspections of the Augusta and Macon 
levees were made during the fiscal year. Cost for 
fiscal year was $1,239. (See Table 8-A Cost and 
Financial Statement.) 
15. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 8-E.) 
16. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended 
(PreauthorizationS tudies). 
Preauthorization studies on Bay Gall Creek, 
Ga., Brooklyn Branch, Ga., and Oates Creek, Ga. 
were continued and studies initiated on Little 
Lotts Creek, Ga., during the fiscal year. Reconnaissance 
Reports on Little Lotts Creek, Ga., were 
completed. The total cost for the fiscal year 
amounted to $136,839. 
Emergency flood control activities - - repair, 
flood fighting, and rescue work, (Public Law 99, 
84th Congress and antecedent legislation). 
Revisions to emergency manuals, emergency 
planning, and other expenditures cost $36,721. 
Multiple-Purpose Projects Including Power 
17. SAVANNAH RIVER BASIN, GA. 
AND S.C. 
Location. Works covered by this project consist 
of a series of 11 dams and lakes on Savannah 
River and its tributaries in Georgia and South 
Carolina. (See Geological Survey maps of Ga. and 
S.C.) 
Existing project. The Flood Control Act of 1944 
approved the general plan for comprehensive 
development of the Savannah River Basin for 
flood control and other purposes (H. D. 657, 78th 
Cong., 2d sess.) and authorized construction of the 
Clark Hill Project on the Savannah River in 
Georgia and South Carolina as the initial step of 
this development. The Flood Control Act of 1950 
authorized construction of Hartwell Lake under 
the general plan. Trotters Shoals which will 
replace Goat Island and Middleton Shoals was 
authorized for construction by the Flood Control 
Act of 1966 at an estimated cost of $84,900,000. 
Clark Hill and Hartwell Lakes are the only projects 
in the comprehensive plan that have been 
constructed. (See Table 8-F on Dams and Lakes at 
end of chapter.) 
8-8

SAVANNAH, GA., DISTRICT 
Duke Power Company has completed construction 
of the Keowee-Toxaway power complex on 
the Keowee River in the headwaters of Hartwell 
Lake and is constructing the Jocassee pumpstorage 
power project in the headwaters of the 
Keowee-Toxaway project. The Keowee-Toxaway 
power complex is located on the Newry - - Old 
Pickens site identified in the approved comprehensive 
plan. Individual reports on Clark Hill, 
Hartwell, and Richard B. Russell (formerly 
Trotters Shoals) Lakes follow. 
Local cooperation. None required. 
17A. CLARK HILL LAKE, GA. AND S.C. 
Location. Clark Hill Lake is located at mile 
237.7 on Savannah River about 22 miles upstream 
from Augusta, Ga. (See Geological Survey 
maps of Georgia and South Carolina.) 
Existing project. The authorized project 
provides for construction of Clark Hill Dam and 
Lake, the final cost of which was $79,156,300. The 
dam has a concrete section 2,282 feet long with a 
maximum/ height of 200 feet, and a controlled 
spillway 1,096 feet long. The concrete section is 
flanked on the west side by a rolled-earth 
embankment of 2,069 feet, and on the east side by 
a similar embankment of 1,329 feet. Total length 
of the dam is 5,680 feet. At maximum power pool 
elevation 330, the lake covers 70,000 acres. It 
provides a total storage capacity of 2,900,000 
acre-feet allocated as follows: flood control 
390,000 acre-feet; hydroelectric power 1,045,000 
acre-feet; and dead storage 1,465,000 acre-feet. 
Seven 40,000-kilowatt generators have a combined 
generating capacity of 280,000 kilowatts, 
with an average annual output of 700 million 
kilowatt-hours of electrical energy. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Cost of recreational activities during the 
fiscal year from Construction General funds 
(Code 710) amounted to $32,827. Gross generation 
of electric energy for the fiscal year was 
921,780,500 kilowatt-hours, most of which was 
delivered to the Southeastern Power Administration. 
Flood damages prevented amounted to 
$465,000. 
Maintenance: Operation and maintenance 
costs during the fiscal year amounted to 
$1,415,778. 
Condition at end offiscal year. Construction is 
complete except for providing additional 
recreational development. 
17B. HARTWELL LAKE, GA. AND S.C. 
Location. Hartwell Lake is on the Savannah 
River 305 miles above its mouth and 89 miles upstream 
from Augusta, Georgia. (See Geological 
Survey maps of Ga. and S.C.) 
Existing project. The dam is a concrete 
gravity-type structure, 1,900 feet long with a 
maximum height of 204 feet and a controlled 
spillway 568 feet in length. The concrete section is 
flanked on the east and west abutments by earth 
embankments totaling 13,390 feet in length and 
by a saddle dike 2,590 feet long also on the west 
side. Total length of the dam is 17,880 feet. At 
maximum power pool elevation of 660 feet the 
lake covers 55,950 acres. Total capacity of the 
lake is 2,843,000 acre-feet of storage allocated as 
follows: flood control 293,000 acre-feet; 
hydroelectric power 1,416,000 acre-feet; and 
dead storage 1,134,000 acre-feet. Four 66,000- 
kilowatt generators having generating capacity 
of 264,000 kilowatts have been installed. A fifth 
generator is planned for installation in the future 
which would then provide a total generating 
capacity of 330,000 kilowatts. Latest approved 
project estimate (Aug. 1968) is $88,300,000. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Cost of activities during the fiscal year 
amounted to $142,402 expended from Construction 
General funds (Code 710). Work consisted of 
construction of miscellaneous recreational 
facilities. Gross generation of electrical energy 
for the fiscal year amounted to 557,176,000 
kilowatt-hours, most of which was delivered to 
the Southeastern Power Administration. Flood 
damages prevented during the fiscal year 
amounted to $123,000. 
Maintenance: Operation and maintenance 
costs during the fiscal year amounted to 
$2,136,396. 
Condition at end of fiscal year. Construction is 
complete except for providing additional 
recreational development. 
17C. RICHARD B. RUSSELL DAM AND 
LAKE, GA. AND S.C., (FORMERLY 
TROTTERS SHOALS LAKE, 
GA. AND S.C.) 
Location. Richard B. Russell Dam is on the 
Savannah River 275.1 miles above its mouth, 29.9 
miles below Hartwell Dam and about 37.4 miles 
above Clark Hill Dam (See NOAA Survey maps 
of Ga. and S.C.) 
Existing project. The authorized project 
provides for construction of Richard B. Russell 
Dam and Lake substantially in accordance with 
the recommendations of the Chief of Engineers at 
an estimated cost of $84,900,000. The latest approved 
(FY 75) cost estimate for the project is 
$190,000,000, of which $153,200,000 is for con- 
8-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
struction, $17,200,000 for lands and damages, 
and $19,600,000 for engineering and design and 
supervision and administration. 
Operations and results during fiscal year. Advanced 
engineering and design having been completed, 
Congressional funding for a new construction 
start was appropriated for this project in 
FY75. The initial construction contract was 
awarded November 15, 1974, in the amount of 
$645,038, which provided for construction of an 
access road to the damsite and office facilities for 
construction purposes. The contract time was 360 
calendar days. Design memoranda completed in 
FY-75 were as follows: (1) Real Estate - Area II, 
(2) Geology, (3) Concrete Dam, and (4) Turbines, 
Governors, Generators. Real Estate acquisition 
and planning for other project features 
continued in an orderly sequence. Contracts for 
sluice gate fabrication and first stage river diversion 
were scheduled for award during second 
quarter FY 76. Total cost for the fiscal year 
amounted to $1,337,677. (See Table 8-A for Cost 
and Financial Statement.) 
18. WEST POINT LAKE, 
CHATTAHOOCHEE RIVER 
BASIN, GA. AND ALA. 
The West Point Lake located on the Chattahoochee 
River, 2.8 miles upstream from West 
Point, Ga., was authorized by the Flood Control 
Act of 1962 (H. D. 570, 87th Cong., 2d sess.). The 
project is being designed and constructed for 
flood control, power, recreation, fish and wildlife 
development and streamflow regulation for 
downstream navigation. It is being designed and 
constructed by Savannah District for Mobile District. 
For complete information see Mobile District. 
General Investigations 
19. SURVEYS 
Fiscal year cost was $903,502, of which 
$120,559 was for navigation studies; $773,049 for 
flood control studies; and $9,894 for special 
studies. 
20. COLLECTION AND STUDY 
OF BASIC DATA 
Work was continued under the Flood Plain 
Management Services on the compilation of information 
on floods, potential flood damages, and 
identification of those areas subject to inundation. 
Fiscal year expenditures for these activities were 
as follows: Preparation of Flood Plain Information 
Reports, $118,800; Guides, Pamphlets and 
Supporting Studies $149,950, and flood plain 
management and technical services, $125,240. 
During FY 75 the Oconee River Basin Flood 
Plain Information Pilot Study - Phase I was initiated. 
The study is the first of its kind for the 
Corps of Engineers. It is intended to address the 
flood plains, within the study limits, in various 
degrees of detail necessary to identify flood potential 
and the impacts thereof. Throughout the 
fiscal year the Flood Plain Management Services 
also conducted Flood Insurance Studies for the 
Federal Insurance Administration. (See Table 8- 
G for Flood Plain Studies completed during FY.) 
21. RESEARCH AND DEVELOPMENT 
Hydrologic studies during the fiscal year cost 
$13,982. 
8-10

SAVANNAH, GA., DISTRICT 
TABLE 8-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Altamaha, Oconee 
and Ocmulgee Rivers, 
Ga. 
2. Aquatic Plant 
Control (1965 
R&H Act) 
3. Atlantic Intracoastal 
Waterway between 
Norfolk Va., and 
the St. Johns River, 
Fla. 
4. Brunswick Harbor, 
Ga. 
5. Darien Harbor, Ga. 
6. Savannah Harbor, 
Ga. 
7. Savannah River 
below Augusta, 
Ga. 
11. Tybee Island, Ga. 
12. Dunn Branch, 
Woodbine, Camden 
County, Ga. 
13. Peacock Creek, 
Liberty County, 
Ga. 
14. Inspection of 
Completed Flood 
Control Works 
17A. Clark Hill Lake, 
Ga. and S.C. 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
50,500 
63,779 
2,000 
218 
72,700 
61,788 
(-3,500) 
655 
35,700 
46,281 
(-541) 
418 
2,000 
2,330 
1,000 
999 
391,700 585,600 434,300 72,000 
499,863 113,990 939,793 81,123 
586,700 750,600 983,400 898,500 
662,286 728,187 1,117,309 765,567 
3,500 6,356 79,174 
3,500 6,356 76,136 3,038 
1,434,700 2,622,000 3,898,000 3,748,000 
2,415,431 2,498,729 4,250,493 3,921,110 
2,790,600 2,526,200 2,765,000 4,911,700 
1,971,085 3,128,169 2,982,546 4,903,451 
463,000 233,600 617,200 330,000 
538,354 267,142 707,964 328,333 
- 70,000 616,000 175,000 
- 60,890 41,556 392,875 
- - - 110,900 
- - - 20,159 
22,434 
2,000 
1,769 
47,900 
101,512 
1,282,800 
1,208,414 
21,667 
6,100 
5,045 
312,000 
290,287 
1,410,700 
1,197,984 
322,000 
482,707 
2,000 
996 
900,000 
929,145 
1,135,800 
1,343,376 
14 (-38,000) 
(-30,023) 
(-1,000) 
1,239 
165,000 
32,827 
1,369,400 
1,415,778 
8-11 
821,4571 
821,457 
1,750,182 
1,750,1812 
11,959 
11,958 
958,0964 
958,0964 
9,234,3215 
9,233,4905 
4,063,608 
6 
4,063,608 
12,826,9017 
12,632,954 
199,723 
199,723 
182,904 
182,904 
37,259,021 
36,767,060 
9 
61,373,8159 
61,365,566 
10 
6,740,03110 
6,740,031 
7,339,350 
7,336,732 
13 
861,000 
495,321 
16 
137,20016 
46,459
15 
586,46715 
582,156 
20,518 
20,467
11 81,814,60711 
81,649,911 
16,237,503 
16,172,978

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 8-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 73 FY 75 June 30, 1975 
17B. Hartwell Lake, Ga. New Work: 
and S.C. Approp. 59,000 - 40,000 296,000 88,448,u00 
Cost 68,849 23,645 16,890 142,402 88,770,409 
Maint. 
Approp. 1,425,300 2,104,900 1,566,800 1,944,000 13,369,309 
Cost 1,348,806 1,553,563 1,879,395 2,136,396 13,117,834 
17C. Richard B. Russell New Work: 
Dam and Lake, Ga. Approp. 756,500 (-550,000) 696,000 1,705,000 4,292,500 
and S.C. (Formerly Cost 77,572 67,017 147,049 1,337,677 3,296,980 
Trotters Shoals) 
1. Includes $760,610 for previous projects. 10. Includes $93,480 for previous projects. Includes 
2. Includes $111,950 for previous projects. $1,634,562 from Public Works Fund. 
3. Does not include $69,350 contributed funds. 11. Does not include $395,634 accelerated Public Works 
4. Includes $194,497 for previous projects. Funds. Includes $2,531,300 appropriated under Code 710 of 
5. Includes $134,798 for previous projects. which $2,366,604 has been expended. 
6. Includes $643,465 for previous projects and includes 12. Does not include $276,200 accelerated Public Works 
$97,521 expended from Public Works Funds for existing pro- Funds. Includes $1,203,500 appropriated under Code 710 of 
ject. Does not include $10,000 contributed funds. which $1,025,902 has been expended. 
7. Includes $54,414 for previous projects. Includes 13. Does not include $426,690 contributed funds. 
$4,995 expended from Public Works Funds for existing pro- 14. Contributed fund reimbursement for prior year nonject. 
Excludes $66,233 contributed by Brunswick and Ga. Federal cost. 
Port Authorities. 15. Does not include $37,691 contributed funds. In- 
8. Includes $7,260,384 for previous projects. Does not in- cludes$45,000 for preauthorization studies. 
clude $46,847 for removal of sunken vessels and $305,248 con- 16. Includes $26,300 for preauthorization studies. 
tributed funds. 
9. Includes $298,894 for previous projects. Does not include 
$846,096 contributed funds. 
TABLE 8-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Acts of July 25, 1912 
and March 2, 1945 
R&H Act of Oct. 27, 1965 
Section 302 
R&H Act of June 3, 1896 
R&H Act of Mar. 3, 1899 
R&H Act of July 13, 1892 
R&H Act of Mar. 3, 1905 
R&H Act of July 25, 1912 
R&H Act of Aug. 8, 1917 
R&H Act of Mar. 2, 1919 
R&H Act of Mar. 2, 1919 
ALTAMAHA, OCONEE AND OCMULGEE RIVERS, 
GA. (See Section 1 of Text) 
Channel 3 feet deep and 60 to 100 feet wide. 
AQUATIC PLANT CONTROL (See Section 2 of Text) 
Provides for control and progressive eradication of obnoxious 
aquatic plant growths. 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND ST. JOHNS 
RIVER, FLA. (SAVANNAH DISTRICT) 
(See Section 3 of Text) 
Section from Beaufort, S.C. to Savannah, Ga. route No. 2 
adopted. 
Route No. 1 adopted. 
Section from Savannah, Ga. to Fernandina, Fla. Original 
7-foot channel. 
Provided for Skidaway Narrows. 
Incorporated alternative routes previously improved as 
separate projects and the auxiliary channels. 
Section from Cumberland Sound, Ga. and Fla. to St. Johns 
River, Fla. Consolidation of the 3 sections shown above, 
into "Waterway between Beaufort, S.C. and St. Johns River, 
Fla." 
Section from Beaufort, S.C. to Cumberland Sound, Ga. and 
Fla. Removing logs and snags from Generals Cut. 
Improving Back River to provide a channel 7 feet deep and 
150 feet wide. 
H. D. 443, 62d Cong., 2d sess. 
H. D. 610, 77th Cong., 2d sess. 
H. D. 251, 89th Cong., 1st sess. 
H. D. 295, 53d Cong., 3d sess. 1 
H. D. 295, 53d Cong., 3d sess. 
H. D. 41, 52d Cong., 1st sess. 
H. D. 450, 58th Cong., 2d sess. 
H. D. 1236, 60th Cong., 2d sess. 
H. D. 581, 63d Cong., 2d sess. 
H. D. 1391, 62d Cong., 3d sess.' 
8-12

SAVANNAH, GA., DISTRICT 
TABLE 8-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 26, 1937 
R&H Act of Aug. 26, 1937 
R&H Act of June 20, 1938 
R&H Act of Mar. 2, 1945 
R&H Act of Mar. 3, 1879 
R&H Act of Mar. 2, 1907 
R&H Act of Mar. 2, 1919 
R&H Act of July 3, 1930 
R&H Act of July 3, 1930 
R&H Act of June 20, 1938 
R&H Act of May 17, 1950 
R&H Act of Sep. 19, 1890 
R&H Act of Mar. 2, 1907 
R&H Act of June 25, 1910 
R&H Act of July 25, 1912 
R&H Act of Aug. 8, 1917 
R&H Act of Jan. 21, 1927 
R&H Act of Jan. 21, 1927 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 1935 
R&H Act of Mar. 2, 1945 
Channel 75 feet wide between Beaufort, S.C. and Savannah, S. D. 178, 68th Cong., 2d sess. 
Ga. 
Channel from Baileys Cut to Dover Creek. 
A 7-foot protected channel around St. Andrews Sound. 
Cong., 1st sess. 
A 12-foot channel between Beaufort, S.C. and Savannah, Ga. 
via Beaufort River and Port Royal Sound 
A 12-foot channel between Savannah, Ga. and Fernandina, 
Fla. various cutoffs; and anchorage basin at Thunderbolt, 
Ga. 
An alternate route 9 feet deep and 150 feet wide in that 
part of Frederica Ri- ~. Ga. not now traversed by the main 
route, at no additional cost to the United States. 
BRUNSWICK HARBOR, GA. (See Section 4 of Text) 
Construction of East River jetty. 
Channels in the inner and outer harbors of 30-foot depth at 
mean high water, with widths varying from 150 feet in 
Academy Creek to 400 feet across the outer bar, extension 
of training wall in East River and construction of 2 spur 
dikes. 
Channels 27 feet deep at mean low water over the bar and at 
Brunswick point; and 24 feet deep at mean low water in the 
inner harbor and provides for a cut from Academy Creek to 
Turtle River, if deemed advisable. 
S. D. 43, 71st Cong., 2d sess. 
Senate committee print, 74th 
Rivers and Harbors Committee 
Doc. 6, 75th Cong., 1st sess. 
H. D. 618, 75th Cong. 3d sess. 
H. D. 114, 77th Cong., 1st sess. 
Annual Report, 1880, p. 959 
H. D. 407, 59th Cong., 1st sess. 
H. D. 393, 64th Cong., 1st sess. 
A channel in Back River 20 feet deep and 150 feet wide. S. D. 57, 71st Cong., 2d sess. 
Increased channel dimensions of the bar, Brunswick Point, 
East River, and Turtle River, as given in the then existing 
project. 
A 10-foot channel in Terry Creek. 
Increased channe1 dimensions of the bar, St. Simons Sound, 
Brunswick River, East River, and Turtle River, as given in 
the existing project. 
DARIEN HARBOR, GA. (See Section 5 of Text) 
Provide a channel 12 feet deep between Darien and Doboy 
Sound. 
SAVANNAH HARBOR, GA. (See Section 6 of Text) 
Tentative provisions for a 26-foot channel from the 
Quarantine Station to the Seaboard Air Line Ry. Bridge. 
Definite provision for the 26-foot channel. 
A 21-foot channel from the Seaboard Air Line Ry. Bridge to 
the foot of Kings Island. 
A 30-foot depth from the sea to the Quarantine Station. 
A 21-foot channel above Kings Island. 
Channel 30 feet deep, with general width 500 feet, from the 
ocean to the Quarantine Station, thence 26 feet deep, 
general width 400 feet, to the Seaboard Air Line Ry. Bridge, 
thence 21 feet deep and 300 feet wide to Kings Island. 
Widening at West Broad and Barnard Streets; anchorage 
basin; mooring dolphins; regulating dam across South Channel; 
relocation of the inland waterway; dredging Drakies Cut 
to 13 feet; widening to 525 ft. at Kings Island; extension of 
training walls, revetments, and jetties. Consolidation of 
projects relating to Savannah Harbor. 
Channel 26 feet deep and 300 feet wide from the Seaboard 
Air Line Ry. Bridge to the foot of Kings Island. 
Authorized the 30-foot project and eliminated from the project 
(a) the relating dam across South Channel; (b) the 
relocation of the Inland Waterway; and (c) the further 
extension of training walls, revetments, and jetties. 
Deepening the channel and turning basin above the Seaboard 
Air Line Ry. Bridge from 26 to 30 feet and widening the 
channel opposite the Atlantic Coast Line Terminals to a 
maximum of 550 feet for a length of 5,000 feet. 
S. D. 132, 71st Cong., 2d sess. 
H. D. 690, 75th Cong., 3d sess.l 
H. D. 110, 81st Cong., 1st sess.l 
H. D. 260, 48th Cong., 2d sess. 
H. D. 181, 59th Cong., 1st sess. 
H. D. 563, 62d Cong., 2d sess. 
H. D. 1471, 64th Cong., 2d sess. 
H. D. 261, 69th Cong., 1st sess. 
H. D. 262, 69th Cong., 1st sess. 
S. D. 39, 71st Cong., 1st sess. 
H. D. 276, 73d Cong., 2d sess. 
H. D. 283, 76th Cong., 1st sess. 
8-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 8-B (Continued) 
Acts 
AUTHORIZING LEGISLATION 
Work Authorized 
R&H Act of Nov. 7, 19 
R&H Act of July 24, 11 
R&H Act of Sep. 3, 19 
R&H Act of Oct. 23, 1 
R&H Act of Oct. 27, 1 
R&H Act of Oct. 27, 19 
R&H Act of Sept. 19, 1 
R&H Act of June 25, 1 
R&H Act of July 3, 191 
R&H Act of Aug. 30, 1 
R&H Act of Aug. 26, 1 
R&H Act of May 17, 1, 
SPWC Resolution of 
June 22, 1971 and 
HPWC of June 23, 19' 
under authority of 
Sec. 201 of FC Act of 
1965. 
Flood Control Act 
of 1948 
45 Deepening the channels to 36 feet deep and 500 feet wide 
across the ocean bar; 34 feet deep and generally 400 feet 
wide, increased to 550 feet opposite the Atlantic Coast 
Line Terminals, with a turning basin 34 feet deep at the 
Mexican Petroleum Corp. Refinery; and with such modifications 
thereof as the Secretary of War and the Chief of 
Engineers may consider desirable. 
946 Extending channel 30 feet deep, 200 feet wide, upstream 
from Atlantic Creosoting Terminal to a point 1,500 feet 
below the Atlantic Coastal Highway Bridge, with turning 
basin 30 feet deep at upper end. 
54 Deepening the channel to 34 feet and widening to 400 feet, 
from the upper end of the presently authorized 34-foot 
channel in the vicinity of the American Oil Company 
Refinery wharf, to the Savannah Sugar Refining Corp. 
with a turning basin at the upper end of the proposed 
improvement, made by widening the channel to 600 feet 
for a length of 700 feet and providing approaches. 
962 Enlargement of turning basin near Kings Island to a width 
of 900 feet and a length of 1,000 feet, with suitable 
approaches, at a depth of 34 feet. 
965 Deepening the bar channel from 36 feet to 40 feet, the 
channel between the bar channel and Garden City Terminal 
from 34 feet to 38 feet, and the channel from the Garden 
City Terminal to the vicinity of the Savannah Sugar Refining 
Corp., from 30 feet to 36 feet; widening the bar channel 
from 500 feet to 600 feet, the channel between Fort Pulaski 
and Atlantic Coast Line Terminal from 400 feet to 500 feet, 
and the channel between Garden City Terminal and the 
Savannah Sugar Refining Corp. from 200 feet to 400 feet; 
providing necessary wideners of the bends; constructing a 
new turning basin 900 feet wide by 1,000 feet long by 34 
feet deep opposite the Atlantic Coast Line Terminals; and 
enlargement of existing turning basin at the American Oil 
Company Terminal from 600 feet wide by 600 feet long to 
900 feet wide by 1,000 feet long. 
)65 Providing sediment control works consisting of tide gate 
structure across Back River; sediment basin 40 feet deep, 
600 feet wide, about 2 miles long, with entrance channel 
38 to 40 feet deep and 300 feet wide; drainage canal across 
Argyle Island 15 feet deep and 300 feet wide: control works 
and canals for supplying fresh water to Savannah National 
Wildlife Refuge; and facilities to mitigate damages to presently 
improved areas other than refuge lands. 
SAVANNAH RIVER BELOW AUGUSTA, GA. 
(See Section 7 of Text) 
890 For a 5-foot channel. 
910 Special improvement by bank protection work of 20 or 25 
miles of the river immediately below Augusta. 
30 The present 6-foot channel project and Lock and Dam. 
995 Provision made for locating the lock and dam at New 
Savannah Bluff. 
937 Conditions of local cooperation modified. 
950 Provides for a 9-foot channel 
TYBEE ISLAND, GA. (See Section 11 of Text) 
Project will provide for beach erosion control, consisting 
of beach restoration, groin system, and periodic beach 
72 nourishment. 
DUNN BRANCH, WOODBINE, CAMDEN COUNTY, GA. 
(See Section 12 of Text) 
Provided for channel excavation of approximately 
2,900 feet. 
H. D. 227, 79th Cong., 1st sess. 
H. D. 678, 79th Cong., 2d sess. 
H. D. 110, 83d Cong., 1st sess.1 
S. D. 115, 87th Cong., 2d sess. 
H. D. 226, 89th Cong., 1st sess. 
H. D. 263, 89th Cong., 1st sess. 
H. D. 255, 51st Cong., 2d sess. 
and Annual Report, 1890; 
p. 1328 
H. D. 962, 60th Cong., 1st sess. 
H. D. 101, 70th Cong., 1st sess. 
Senate Committee Print, 
73d Cong., 2d sess. 
Rivers and Harbors Committee, 
Doc. 39, 75th Cong., 1st sess. 
S. D. 6, 81st Cong., 1st sess. 
H. D. 105, 92d Cong. 
DPR Appvd, Jan 31, 1974 by 
Chief of Engineers. 
8-14 
Documents 
I

SAVANNAH, GA., DISTRICT 
TABLE 8-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
PEACOCK CREEK, LIBERTY COUNTY, GA. 
(See Section 13 of Text) 
Flood Control Act of Provided for channel clearing and excavation of approxi- DPR Appvd. Nov 28, 1969 by 
1962 mately 6.8 miles. Chief of Engineers. 
CLARK HILL LAKE, GA. AND S.C. 
(See Section 17A of Text) 
Flood Control Act Approved the general plan for the comprehensive develop- H. D. 657, 78th Cong., 2d sess. 
of Dec. 22, 1944 ment of the Savannah River Basin and provided for con- P. L. 534, 78th Cong., 2d sess: 
struction of the Clark Hill Project. 
HARTWELL LAKE, GA. AND S.C. 
(See Section 17B of Text) 
Flood Control Act Provided for construction of Hartwell Project. H. D. 657, 78th Cong., 2d sess. 
of May 17, 1950 P. L. 516, 81st Cong., 2d sess. 
Flood Control Act Provided for the completion of the Hartwell Project. P. L. 85-500, 85th Cong., 2d sess. 
of July 3, 1958 
RICHARD B. RUSSELL DAM AND LAKE, GA. 
AND S.C. (Formerly Trotters Shoals Lake, GA. and S.C.) 
(See Section 17C of Text) 
Flood Control Act Provided for construction of the Trotters Shoals Project. S. D. 52, 89th Cong., 1st sess. 
of Nov. 7, 1966 
1. Contains latest published maps. 
TABLE 8-C RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 8 of Text) 
Project Date Survey Conducted 
Fancy Bluff Creek, Ga. 
St. Marys River, Ga. and Fla., and North River, Ga. FY 1971 (Recon) 
Satilla River, Ga. FY 1971 (Recon) 
8-15

TABLE 8-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 9 in Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
2 
Aquatic Plant Control (R&H Act 1962) 1968 25,700 
Fancy Bluff Creek, Ga.1' 2 1935 8,000 7,200 
St. Marys River, Ga. and Fla., and North 
River, Ga. 1951 15,688 62,436 
Sapelo Harbor, Ga.2'3 4 1929 17,906 17,094 
Satilla River, Ga."2 1951 9,452 49,672 
3,4,5 
Savannah River above Augusta, Ga 1929 69,600 5,870 
Savannah River at Augusta, Ga.3'4'6 1929 200,556 17,444 
1. Channel adequate for commerce. 5. About 84 percent completed. Owing to construction of 
2. Completed. 2 power dams which submerged much of the work under the 
3. Project recommended for abandonment in H. D. 467, present and former projects, this improvement cannot be 
69th Cong., 1st sess. completed as originally planned. 
4. No commerce reported. 6. Excludes $185,000 contributed funds ($172,151 for 
construction and $12,849 for operation and maintenance). 
TABLE 8-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 15 in Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Augusta, Savannah River, Ga.' 1941 643,016 - 
Broadway Lake, Anderson County, S.C. 1974 - - 
Curry Creek Dam and Lake, Ga. 1974 - - 
Macon, Ga.' 1955 380,043 - 
1. Completed. 
TABLE 8-F SAVANNAH RIVER BASIN, GA. AND S.C. 
DAMS AND LAKES 
(See Section 17 of Text) 
Estimated Cost 
Name River Federal Non-Federal Total 
Clark Hill, Ga. and S.C. Savannah $79,156,0004 $79,156,000' 
Hartwell, Ga. and S. C. Savannah 89,240,000 89,240,0003 
Goat Island, Ga. and S.C.5 Savannah 36,400,000 36,400,0003 
Middleton Shoals, Ga. and S.C. Savannah 16,500,000 16,500,0003 
Chattooga units (4), Ga. and S.C. Chattooga 41,700,000 41,700,0003 
Tallow Hill, Ga. Broad 39,000,000 39,000,0003 
Anthony Shoals, Ga. Broad 18,100,000 18,100,000 
Newry-Old Pickens, S.C. Keowee 29,500,000 29,500,000 
1. Final cost. (Excludes $127,000 for preauthorization 
study.) 
2. Approved Aug. 1963. (Excludes $73,000 for 
preauthorization study.) 
3. Approved July 1954. 
4. Excludes Code 710 funds. 
5. Replaced by Richard B. Russell Dam and Lake 
(Formerly Trotters Shoals Lake). 
6. Site of Duke Power Co. Keowee-Toxaway Project. 
8-16

SAVANNAH, GA., DISTRICT 
TABLE 8-G FLOOD PLAIN INFORMATION STUDIES COMPLETED 
DURING FISCAL YEAR 1975 
(See Section 20 of Text) 
Project 
Almand Creek 
Big Indian Creek 
Big Indian Creek 
Jacks, Grubby and 
Mountain Creeks 
Little Cotton Indian 
Polebridge Creek 
(Restudy) 
Sandy Run Cr., Bay Gall 
Cr., and Tributaries 
Snapfinger Creek 
(Restudy) 
Sugar Creek (Restudy) 
Walker Creek and 
Mosely Bay 
Location 
Metropolitan Atlanta, Ga 
Houston County, Ga. 
Perry, Ga. 
Monroe, Ga. 
Henry County, Ga. 
Metropolitan Atlanta, Ga. 
Houston County, Ga. 
Metropolitan Atlanta, Ga. 
Metropolitan Atlanta, Ga. 
Wayne County, Ga. 
Requesting 
Agency 
Atlanta Regional Commission 
Houston County, Ga. 
Perry, Ga. 
Monroe, Ga. 
Atlanta Regional Commission 
Atlanta Regional Commission 
Houston County, Ga. 
Atlanta Regional Commission 
Atlanta Regional Commission 
Jesup and Wayne County, Ga. 
8-17 
Date 
Completed 
Feb 75 
Jun 75 
Oct 74 
May 75 
May 75 
May 75 
Jun 75 
May 75 
Mar 75 
Jan 75 
Federal 
Cost 
$4,500 
$31,000 
$15,000 
$10,000 
$21,500 
$12,500 
$21,000 
$ 9,000 
$ 7,000 
$ 7,000

JACKSONVILLE, FLA., DISTRICT* 
With the exception of a small area in the northeastern 
section of Florida, this district comprises 
a portion of south-central Georgia and all of peninsular 
Florida, embracing the watersheds tributary 
to the Atlantic Ocean and the Gulf of Mexico 
from, and including the harbor at Fernandina, 
Florida, to and including the Aucilla River. It also 
includes Puerto Rico and the Virgin Islands. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control (R&H Act of 
1965)............................. 9-2 
2. Arecibo Harbor, P.R ................ 9-2 
3. AIWW Norfolk to St. Johns River..... 9-2 
4. CanaveralHarbor, Fla................ 9-3 
5. Charlotte Harbor, Fla................ 9-3 
6. Cross Florida Barge Canal ........... 9-4 
7. Fernandina Harbor, Fla.............. 9-5 
8. Fort Myers Beach, Fla................ 9-5 
9. Fort Pierce Harbor, Fla.............. 9-5 
10. Intracoastal Waterway, 
Caloosahatchee River to 
Anclote River, Fla ................. 9-6 
11. Intracoastal Waterway, Jacksonville 
to Miami, Fla....................... 9-6 
12. Jacksonville Harbor, Fla.............. 9-7 
13. Mayaguez Harbor, P.R............... 9-8 
14. Miami Harbor, Fla................... 9-9 
15. New Pass, Sarasota, Fla.............. 9-10 
16. Okeechobee Waterway, Fla........... 9-10 
17. Oklawaha River, Fla ................ 9-11 
18. Palm Beach Harbor, Fla.............. 9-11 
19. Ponce de Leon Inlet, Fla.............. 9-12 
20. Ponce Harbor, P.R................... 9-12 
21. Removing the Water Hyacinth 
from Navigable Waters in the 
State of Florida ................... 9-13 
22. St. Augustine Harbor, Fla ........... 9-13 
23. St. Lucie Inlet, Fla.................. 9-13 
24. San Juan Harbor, P.R................ 9-14 
25. Tampa Harbor, Fla................... 9-15 
26. Navigation Projects on which 
Reconnaissance and Condition 
Surveys only were Conducted 
during Fiscal Year ................. 9-16 
27. Other Authorized Navigation 
*All cost and financial statements for projects are listed at 
the end of this chapter. All other tables are referenced in text 
and also appear at the end of this chapter. 
Navigation (cont.) 
Projects.......................... 
28. Navigation Work under Special 
Authorization..................... 
Beach Erosion Control 
Page 
9-16 
9-16 
29. Brevard County, Fla ................ 9-16 
30. Broward County, Fla., Beach 
Erosion Control and Hillsboro 
Inlet, Fla., Navigation Project ....... 9-17 
31. Dade County, Fla.................... 9-17 
32. Duval County, Fla.................. 9-18 
33. Palm Beach County, Fla., from 
Martin County line to Lake Worth 
Inlet and from South Lake Worth 
Inlet to Broward County line ........ 9-18 
34. Pinellas County, Fla.................. 9-19 
35. Virginia Key and Key Biscayne, Fla.... 9-19 
36. Other Authorized Beach Erosion 
S Control Projects .................. 9-20 
37. Beach Erosion Control Activities 
Under Special Authorization ........ 9-20 
Flood Control Page 
38. Central and Southern Florida......... 9-20 
39. Four River Basins, Fla. .............. 9-22 
40. Portugues and Bucana Rivers, P.R..... 9-23 
41. Inspection of Completed Flood 
Control Projects .................. 9-24 
42. Other Authorized Flood Control 
Projects.......................... 9-24 
43. Flood Control Work under Special 
Authorization.................... . 9-24 
General Investigations 
44. Surveys........................... 9-24 
45. Collection and Study of Basic Data .... 9-24

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. AQUATIC PLANT CONTROL 
(R&H ACT OF 1965) 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
Jacksonville District. 
Existing project. The authorized project provides 
for control and progressive eradication of 
water hyacinth, alligatorweed, Eurasian watermilfoil, 
and other obnoxious aquatic plant 
growths from navigable waters, tributary 
streams, connecting channels, and other allied 
waters of the United States, in combined interest 
of navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health, 
and related purposes, including continued research 
for development of most effective and 
economical control measures in cooperation with 
other Federal and State agencies in accordance 
with report of Chief of Engineers, House Document 
251, 89th Congress, 1st session. The authorizing 
act provides that research and planning 
costs shall be borne fully by the United States. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must hold 
the United States free from damages that may 
occur from operations performed in connection 
with this project and contribute 30 percent of cost 
of operations. Compliance with requirements of 
local cooperation is on schedule. 
Operations and results during fiscal year. New 
work: There were 45,275 acres of hyacinths 
sprayed during the year (8,182 acres by the Corps 
and 37,093 acres by the State). Costs incurred 
were $54,729 for engineering and $550,857 for 
operations. 
Condition at end of fiscal year. Operations by 
the Corps and the State of Florida are in progress. 
About 274,000 acres of acquatic plant 
growth have been treated in Florida under the 
project. 
2. ARECIBO HARBOR, P. R. 
Location. The harbor is located on the north 
shore of Puerto Rico about 40 miles west of San 
Juan Harbor. (See Coast and Geodetic Survey 
Chart No. 903.) 
Previous project. For details see page 504 of 
1956 Annual Report. 
Existing project. The project provides for a 
channel 25 feet deep and 400 feet wide, with flare 
at entrance and widening at inner end to form 
a maneuvering area, and a stone breakwater 
1,200 feet long. Plane of reference is mean low 
water. Mean tidal range is 1.1 feet. (See Table 9-B 
for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$288,000. 
Terminal facilities. A bulkhead wharf 688 by 
220 feet providing a deep-water berthing space of 
approximately 500 feet, and a 300 by 100 foot 
transit shed. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging in entrance channel and 
turning basin commenced Sept. 30, 1974 and was 
completed Nov. 13, 1974. U.S. Dredge Hyde 
removed 120,122 cubic yards of material at a cost 
of $343,243. Engineering and design and supervision 
and administration costs were $3,949 and 
$1,371 respectively. Hired labor surveys, inspections, 
and reports cost $2,958. 
Condition at end of fiscal year. Project was 
completed in 1944. Breakwater was repaired in 
1952. Wave action has since caused minor 
damage. Total Federal costs under existing project 
through June 30, 1975, were $1,128,075 for 
new work and $876,431 for maintenance, a total of 
$2,004,506. 
3. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND 
ST. JOHNS RIVER, FLA. (JACKSONVILLE 
DISTRICT) 
Location. That part of Intracoastal Waterway 
between southerly limit of Fernandina Harbor, 
Florida, at junction of Lanceford Creek and 
Amelia River, and St. Johns River, Fla. (See 
Coast and Geodetic Survey Chart No. 841-SC.) 
Previous project. For details see page 605 of 
1938 Annual Report. 
Existing project. Channel 12 by 90 to 150 feet 
from Fernandina Harbor to St. Johns River about 
22 miles long. Plane of reference is mean low 
water. Mean tidal range is 6 feet at Fernandina 
and 3.8 feet at St. Johns River. 
Existing project was authorized by River and 
Harbor Acts of 1913 (HD 898/62/2) and 1938 (HD 
618/75/3). 
Local cooperation. Fully complied with to date. 
Terminal facilities. None along this section of 
the waterway. None are currently required. 
Operations and results during fiscal year. 
Maintenance: Engineering and design costs were 
$7,381. Hired labor surveys, inspections and reports 
cost $954. 
Condition at end of fiscal year. Project was 
completed in 1941. Total costs under the existing 
project to June 30, 1975, have been $263,659 for 
new work and $1,015,178 for maintenance, a total 
of $1,278,837. 
9-2

JACKSONVILLE, FLA., DISTRICT 
4. CANAVERAL HARBOR, FLA. 
Location. The harbor is located on the east 
coast of Florida in Canaveral Bight, about 146 
miles south of the entrance to Jacksonville Harbor 
and 69 miles north of the entrance to Fort 
Pierce Harbor. (See Coast and Geodetic Survey 
Charts Nos. 456 and 1245.) 
Existing project. The authorized project provides 
for maintenance of the 37-foot and 36-footdepth 
entrance channel and 35-foot-depth turning 
basin; construction and operation of a sand transfer 
plant; relocation of the perimeter dike about 
4,000 feet westward and extension of the harbor 
westward; two entrance jetties 100 feet long (constructed 
of native stone core and granite sides 
and cap); a lock; a channel and turning basin 31 
feet deep near the relocated dike; and a barge 
canal 12 by 125 feet from the turning basin to the 
Atlantic Intracoastal Waterway. Plane of reference 
is mean low water (ocean) for harbor dike 
and lock, and mean low water (Banana River) for 
barge canal. The project is about 11.5 miles long. 
Mean tidal range is 3.5 feet at the entrance and 
practically non-tidal in Banana and Indian Rivers. 
(See Table 9-C for Data Relative to Lock.) 
Estimated cost (1975) of new work is $16,860,000 
Federal cost and $3,691,000 non-Federal cost 
($1,090,000 contributed funds and $2,601,000 
other costs); and $700,000 costs to NASA. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must: provide 
all lands, rights-of-way, spoil-disposal areas, 
retaining dikes, and embankments; hold United 
States free from damages; provide and maintain 
four-land bridge and roadway subject to Federal 
contribution of 65.3 percent of cost of constructing 
bridge and 51.2 percent of constructing 
roadway; provide public terminal and transfer 
facilities; and make alterations as required in 
berthing facilities. For further details see Senate 
Document 140, 87th Congress, 2d session. Compliance 
by local interests is on schedule. Non-Federal 
contribution for new work is $1,090,000. 
Terminal facilities. South of the barge canal 
and west of the turning basin is a 1,500-foot-long 
concrete bulkhead having a 12-foot-depth berthing 
area which accomodates shrimp and commercial 
fishing boats. A 300-foot extension of the concrete 
bulkhead has been completed. Two finger 
piers at the west end of the bulkhead are available 
for charter boats. On the south side of the 
east turning basin is a 1,060-foot-long marginal 
wharf, complete with utilities, operated by the 
Canaveral Port Authority. In addition to the 
existing two 30,000 sq. ft. newsprint warehouses, 
a new 60,000 sq. ft. newsprint warehouse has 
been constructed and is ready for use. On the 
south shore of the ship canal, parallel to the channel 
are 1,200 feet of oil docking facilities, complete 
with pipelines to the storage tanks, as well 
as bulk cement unloading facilities with storage 
capacity of 170,000 barrels. New silos and a new 
offloading cement facility have been completed on 
the north side of the harbor. At the easterly end 
of the barge canal is a terminal for handling bulk 
construction materials. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
work: Contract for constructing harbor extension 
was completed in Sept. 74 at a cost of $456,368. 
Engineering and design and supervision and ad-, 
ministration costs were $2,047 and $12,113, respectively. 
Maintenance: During the period July 2-31, 1974, 
U.S. Dredge Goethals removed 504,282 cubic 
yards of material from entrance channel at a cost 
of $839,044. From October 31 - November 18, 1974 
U.S. Dredge Comber removed 223,986 cubic yards 
of material at a cost of $201,288. During the 
period May 1-27, 1975 U.S. Dredge Davison removed 
349,276 cubic yards of material from inner 
channel at a cost of $617,685. Maintenance dredging 
of inner channel and turning basin was included 
in contract for new work construction of 
harbor extension. Dredge Dauntless removed 
80,702 cubic yards of material at a contract cost of 
$115,614. Operation and maintenance of district 
communications network amounted to $10,658. 
Cost of condition and operation studies were 
$33,365. Costs for termination of contract for dewatering 
and gate maintenance of Canaveral 
Lock were $685. Engineering and design and 
supervision and administration costs were $4,564 
and $3,056, respectively. Hired labor surveys, inspections, 
and reports cost $29,553. 
Operation and care: The lock was operated and 
buildings and grounds maintained at a hired labor 
cost of $194,117. 
Condition at end of fiscal year. The existing 
project is about 44 percent completed. The perimeter 
dike and jetties are in good condition. 
Work remaining to complete the project is 
extension of the harbor, part of which is underway, 
and construction of the sand transfer plant. 
5. CHARLOTTE HARBOR, FLA. 
Location. The harbor is located in a large bay 
on the west coast of Florida. The entrance is 68 
miles south of the entrance to Tampa Bay and 
150 miles north of Key West. (See Coast and 
Geodetic Survey Chart No. 1255.) 
Previous projects. For details, see page 457 of 
1959 Annual Report. 
Existing project. The authorized project pro- 
9-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
vides for a channel 32 feet by 300 feet, increased 
to 700 feet at the bend, from the Gulf of Mexico to 
Port Boca Grande, thence 10 feet by 100 feet from 
deep water at Port Boca Grande to and including 
a turning basin 200 feet square at the municipal 
terminal at Punta Gorda. Plane of reference is 
mean low water. The project is about 29.5 miles 
long. 
Mean tidal range is one foot at Port Boca 
Grande and 1.4 feet at Punta Gorda. Extreme 
range is about 3 feet at Port Boca Grande and 3.8 
feet at Punta Gorda. Strong southwesterly winds 
raise water level about 1.5 feet; strong northerly 
and easterly winds lower it about one foot. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local cooperation is fully complied 
with to date. Non-Federal contribution for 
new work was $15,563. 
Terminal facilities. Existing facilities consist of 
a phosphate wharf at Port Boca Grande and a 
municipal earthfill pier about 850 feet long at 
Punta Gorda, both open to the public. Railway 
connections are available at Port Boca Grande, 
and highway and railway connections are available 
at Punta Gorda. There is a tank farm at Port 
Boca Grande for storage and rehandling of 
bunker fuel oil and numerous facilities are available 
in the area for docking and servicing small 
craft. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: During the period Jan. 16-31, 1975, 
U.S. Dredge Gerig removed 239,186 cubic yards 
of material from the entrance channel at a cost of 
$200,426. Operation and maintenance of district 
communications network amounted to $5,329. 
Cost of condition and operation studies were 
$13,647. Engineering and design and supervision 
and administration costs were $8,632 and $54, 
respectively. Hired labor surveys, inspections, 
and reports cost $1,912. 
Condition at end of fiscal year. The project was 
completed in 1959. 
Total costs under existing project for June 30, 
1975, have been $420,169 for new work and 
$2,549,386 for maintenance, a total of $2,969,555. 
In addition, $15,563 was expended from contributed 
funds for new work in Boca Grande entrance 
channel. 
6. CROSS FLORIDA BARGE CANAL 
Location. The proposed canal extends up the 
St. Johns River, past Palatka, thence up the 
valley of the Oklawaha River, across the divide 
south of Ocala, and down the valley of the 
Withlacoochee River to the Gulf of Mexico, about 
95 miles north of Tampa, Florida. 
Existing project. The authorized project provides 
for a lock canal with project depth of 12 feet 
and minimum bottom width of 150 feet, with five 
locks and two earth dams. Project including the 
section in the St. Johns River is 184 miles long. 
(See Table 9-D for Locks and Dams.) 
Operation and maintenance of the locks and 
dams is a Federal responsibility. Estimated cost 
of new work (1970) is $179,000,000 Federal, and 
$19,500,000 non-Federal for lands, rights-of-way, 
and other costs. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction of canal; 
hold United States free from damages; and operate 
and maintain all highway bridges and roadways 
built in connection with project. Assurances 
of local cooperation were accepted by the District 
Engineer on November 13, 1963. Compliance by 
local interests is on schedule. 
Terminal facilities. None. 
Operations and results during fiscal year. (See 
Table 9-E for work accomplished.) 
Regulation. 
(a) Lake Oklawaha. This area continues to be 
regulated by the Corps of Engineers pending 
final disposition of constructed facilities of the 
Cross Florida Barge Canal. During Fiscal Year 
1975 the lake continued to be regulated at 18.0 
feet m.s.l., except for a two-month experimental 
winter drawdown to elevation 15.0 feet. The purpose 
of the drawdown was to apply a management 
technique in the interest of fisheries and 
noxious aquatic plant control. Lowering of the 
pool began January 2, 1975 at a rate of .35-foot per 
day. Refilling commenced on March 1, 1975 at a 
rate of .10-foot per day. During FY 1975 a total of 
1,134,000 acre-feet of water was discharged 
through the Rodman Spillway for regulatory purposes. 
Another 27,000 acre-feet were used for 
lockages through Buckman Lock. 
(b) Lake Rousseau. This area is regulated on a 
yearly schedule of 27.5 feet by discharging 
through the Inglis Bypass Spillway, supplemented 
during periods of excessive inflow, with 
additional releases through the Inglis Dam Spillway. 
During Fiscal Year 1975, discharge through 
the Inglis Bypass Spillway totalled 895,000 acrefeet 
and varied from a low of 520 c.f.s. to a high of 
1,530 c.f.s. Inglis Dam discharge totaled 286,000 
acre-feet and varied from a low of zero to a high of 
2,500 c.f.s. Another 8,100 acre-feet was used for 
lockage through Inglis Lock. 
Condition at end of fiscal year. Construction of 
project commenced February 25, 1964, and is 
28 percent completed. Inglis Lock, Dam, and Spillway; 
Rodman Dam and Spillway; Eureka Lock, 
Dam, and Spillway; Henry H. Buckman Lock; and 
9-4

JACKSONVILLE, FLA., DISTRICT 
canal from Palatka to Lake Ocklawaha and from 
Withlacoochee River to Gulf of Mexico, including 
Inglis Bypass Channel, are completed. Construction 
work on the project was terminated in FY 
1971 by order of the President. 
7. FERNANDINA HARBOR, FLA. 
Location. Entrance to the harbor is located on 
the northeast coast of Florida about 95 miles 
south of the entrance to Savannah Harbor, 
Georgia, and 22 miles north of the entrance to 
Jacksonville Harbor, Florida. (See Coast and Geodetic 
Survey Chart No. 453.) 
Existing project. The authorized project provides 
for a 32-foot-depth channel (maximum channel 
in active status: 28 feet) generally 300-400 feet 
wide from deep water in the ocean to the junction 
of Lanceford Creek with Amelia River; an 800- 
foot-wide turning basin at the first bend below 
Lanceford Creek; and two jetties, 19,150 and 
11,200 feet long. Plane of reference is mean low 
water. The project is 7 miles long. Mean tidal 
range is 5.8 feet on the bar and 6 feet in the inner 
harbor. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are two large 
wharves operated by industrial plants; twelve 
wharves serving fishing boats, recreational craft, 
and other vessels; three oil handling wharves 
with pipelines; and a Municipal Marina and 
Sportsman's Wharf with public facilities for small 
craft. Total berthing space is approximately 4,065 
feet. Most terminals are served by rail, and all 
have highway access. Facilities are considered 
adequate for existing commerce. (See Port Series 
No. 16 (Part 2), 1964.) 
Operations and results during fiscal year. 
Maintenance: From Jan. 15 - Feb. 15, 1975, U.S. 
Dredge Davison removed 75,915 cubic yards of 
material from the entrance channel at a cost of 
$322,661. Cost of condition and operation studies 
were $26,681. Mitigation of shore damages 
amounted to $2,165. Engineering and design and 
supervision and administration costs were $25,125 
and $154, respectively. Hired labor surveys, inspections, 
and reports cost $10,379. 
Condition at end of fiscal year. The active 
portion of the existing project is complete. Jetties 
are in very poor condition and are badly in need of 
repair. Remaining work is to deepen the inner 
harbor channel and turning basin to 32 feet when 
and if the presently inactive 1950 authorization is 
reactivated. The outer harbor channel has been 
deepened to 34 feet in development of a military 
project. 
8. FORT MYERS BEACH, FLA. 
Location. Fort Myers Beach is on Estero Island 
near the mouth of the Caloosahatchee River, 
about 20 miles below Fort Myers and 110 miles 
south of Tampa, Florida. (See Coast and Geodetic 
Survey Charts Nos. 855-SC and 1255.) 
Existing project. The authorized project provides 
for a channel 12 feet deep by 150 feet wide 
from that depth in San Carlos Bay into Matanzas 
Pass, thence 11 by 125 feet in Matanzas Pass to 
and including a turning basin 2,000 feet upstream 
from the upper shrimp terminals. Plane of reference 
is mean low water. Project is 2.5 miles long. 
Mean tidal range is 1.7 feet. Spring range is 
about 2.3 feet. Strong northerly winds lower the 
water surface 1 to 2 feet; strong southerly winds 
have an opposite effect. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was $1,095. 
Terminal facilities. There are three shrimppacking 
houses and several fish-packing houses, 
two marine railways, a fuel terminal and an ice 
manufacturing plant in the area. There are several 
commercial facilities for servicing shrimp 
boats. Recreational-craft facilities include nine 
marinas, a boat and motor testing laboratory, and 
numerous privately owned piers and wharves. All 
terminals have highway access. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. New 
work: Miscellaneous supervision and administration 
costs in connection with recently completed 
dredging were $119. 
Maintenance: Hired labor surveys, inspections, 
and reports cost $4,862. 
Condition at end of fiscal year. The project is 
complete. 
9. FORT PIERCE HARBOR, FLA. 
Location. On east coast of Florida, about 218 
miles south of entrance to St. Johns River and 
about 124 miles north of entrance to Miami Harbor. 
(See Coast and Geodetic Survey Chart No. 
582.) 
Existing project. The authorized project provides 
for a channel generally 27 feet by 350-200 
feet to Station 130, thence 25 feet by 200 feet to a 
turning basin 25 feet by 900 feet, maintenance of 
two jetties and shore revetments, and a 6-foot by 
1,200-foot fishing walkway atop the south jetty. 
Plane of reference is mean low water. The project 
is about 3.5 miles long. 
Mean tidal range is 2.6 feet at the entrance and 
0.7 foot at terminals. (See Table 9-B for Authorizing 
Legislation.) 
9-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
For further details see 1961 Annual Report. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$18,574. 
Terminal facilities. Two earth-filled piers 
forming a slip 200 feet by 300 feet with bulkhead 
wharf at inner end, affording a berthing space of 
about 1,653 feet. The south pier and bulkhead 
wharf are municipally owned. There is a precooling 
plant, a warehouse, and a fruit packing 
house available. North pier is served by railway 
and both piers by highway connections. North of 
the turning basin local interests have provided 
deep-draft berthing and pier facilities. Also available 
is a bulkhead wharf with a depth of 20 feet 
with ample room for open storage and with tank 
storage for petroleum products in the rear. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Final costs on recently completed 
entrance channel dredging contract amounted to 
$25,460. Supervision and administration costs 
were $225. Hired labor surveys, inspections, and 
reports cost $8,395. 
Condition at end of fiscal year. The project was 
completed in 1938 except for the fishing walkway 
atop the south jetty which was completed by local 
interests in 1968. Local interests installed lighting 
atop the jetty in 1969. 
Jetties and revetments are in good condition. 
10. INTRACOASTAL WATERWAY, 
CALOOSAHATCHEE RIVER TO 
ANCLOTE RIVER, FLA. 
Location. The waterway extends from the 
mouth of the Caloosahatchee River at Punta 
Rassa, Florida, to the mouth of Anclote River, 
Florida, following in general an almost continuous 
series of protected inside waterways along the 
gulf coast of Florida. (See Coast and Geodetic Survey 
Charts Nos. 856-SC, 857-SC, and 858.) 
Previous projects. For details, see page 767 of 
1945 Annual Report. 
Existing project. The authorized project provides 
for a channel 9 feet deep by 100 feet wide 
from Caloosahatchee River to Anclote River; 
deepening the existing channel at Caseys Pass to 
9 feet; a channel 6 feet deep by 80 feet wide (Cats 
Point Channel) along the southeastern side of 
Boca Ciega Bay past Frenchman Creek and Gulfport; 
maintenance of bulkheads, revetments, and 
two jetties built at Caseys Pass under previous 
project; and improvement and maintenance of 
Sunshine Skyway Channel. Plane of reference is 
mean low water. The project includes about 160 
miles of channels. 
Mean ranges of tide are 1.7 feet at Punta 
Rassa, 1 foot at Port Boca Grande, 1.4 feet in 
Tampa Bay at Anna Maria, and 2 feet at entrance 
to Anclote River. Extreme ranges are about 4.5 
feet at Punta Rassa, about 3 to 4 feet between 
Port Boca Grande and Corey Causeway over Boca 
Ciega Bay, and about 5.5 feet at entrance to 
Anclote River. Southerly winds over the area 
generally raise water level by 1 to 1.5 feet; northerly 
winds lower water level by 1 to 2 feet. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for constructing Cats 
Point and Sunshine Skyway Channels was $9,707 
and $4,766, respectively. 
Terminal facilities. Existing facilities include 
one municipal concrete pier, one railway pier, one 
freight wharf, one marginal wharf 500 feet long 
on terminal island, and eleven privately owned 
landings, all at Sarasota. Municipal pier and 
freight wharf are open to the public. All piers 
have highway connections. There are six wharves 
along Boca Ciega Bay and a number of small privately 
owned piers and wharves at various points 
along waterway for use of commercial fishing 
boats and recreational craft. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. New 
work: Miscellaneous supervision and administration 
costs amounted to $1,021. 
Maintenance: Maintenance of channel slopes 
and berms in land cut thru city of Venice cost 
$6,163. Costs incurred in connection with recently 
terminated contract for dredging in waterway 
where required were $25,300. Replacement of 
waterway signs cost $3,028 and operation of district 
communications network cost $5,329. Engineering 
and design and supervision and administration 
costs were $19,662 and $15,397, respectively. 
Hired labor surveys, inspections, and 
reports cost $45,698. 
Condition at end of fiscal year. Existing project 
is complete. Jetties at Caseys Pass are in 
need of repiar. 
Total Federal costs under existing project 
through June 30, 1975, were $7,556,273 for new 
work and $1,253,975 for maintenance, a total of 
$8,810,248. In addition, $14,473 contributed funds 
were expended for Sunshine Skyway and Boca 
Ciega Bay channels. 
11. INTRACOASTAL WATERWAY, 
JACKSONVILLE TO MIAMI, FLA. 
Location. The waterway extends from Jacksonville 
to Miami, Florida, following the St. Johns 
River to the mouth of Pablo Creek and thence 
following in general an almost continuous series 
9-6

JACKSONVILLE, FLA., DISTRICT 
of protected inside waterways along the Atlantic 
coast of Florida to Miami. (See Coast and Geodetic 
Survey Charts Nos. 841-SC, 843-SC, 845-SC, 
and 847-SC.) 
Previous projects. For details, see pages 618- 
619 of 1938 Annual Report. 
Existing project. The authorized project provides 
for a channel 12 feet by 125 feet from Jacksonville 
to Miami, modified to 10-foot-depth from 
Fort Pierce to Miami by Chief of Engineer's report 
of July 22, 1960; side channels at Sebastian 
and Daytona Beach and turning basins at Sebastian 
and Vero Beach, all to an 8-foot-depth; and 
operation and maintenance of the Palm Valley 
highway bridge. Project is 370 miles long, including 
21 miles in Jacksonville Harbor. Mean range 
of the tide is 3.8 feet at St. Johns River, 0.7 foot in 
the Indian River at Fort Pierce, 1.8 feet in Lake 
Worth at Port of Palm Beach terminals, 2.3 feet at 
the Port Everglades terminals, and 2 feet in Biscayne 
Bay. The extreme range is about 7 feet at 
St. Johns River, 1.5 feet at Fort Pierce, and 3 feet 
in Biscayne Bay. Plane of reference is mean low 
water. Tidal effect is imperceptible at points 
along waterway distant from inlets. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are a number of privately 
owned piers, wharves, and landings at 
various points along waterway. Terminals with 
railway connections are available at Jacksonville, 
Fort Pierce, West Palm Beach, Port Everglades, 
and Miami. Municipal piers or wharves have been 
constructed at Titusville, Cocoa, Melbourne, and 
Vero Beach for handling general freight and at St. 
Augustine, Daytona Beach, New Smyrna Beach, 
Eau Gallie, West Palm Beach, Delray Beach, Fort 
Lauderdale, and Miami for use of recreational 
craft. Yacht basins, open to the public, have been 
provided at Jacksonville Beach, Daytona Beach, 
Titusville, Eau Gallie, Vero Beach, Fort Pierce, 
West Palm Beach, Fort Lauderdale, Hollywood, 
and Miami. Facilities are considered adequate for 
existing commerce. (For further details on facilities 
at Jacksonville, see Port Series No. 15, 1969, 
and at Palm Beach, Port Everglades, and Miami, 
see Port Series No. 16, Revised 1972.) 
Operations and results during fiscal year. 
Maintenance: Dredging in waterway between St. 
Lucie Inlet and Bakers Raulover commenced 
June 2, 1975. Mobilization costs were $112,200. 
Replacement of waterway signs cost $11,163 and 
operation and maintenance of district communications 
network cost $10,658. Engineering and design 
and supervision and administration costs 
were $128,962 and $2,972, respectively. Hired 
labor surveys, inspections, and reports cost 
$102,915. 
Operation and care: The highway bridge near 
Palm Valley was operated and maintained by 
hired labor at a cost of $38,354. 
Condition at end of fiscal year. The existing 
project as modified by the Chief of Engineers is 
complete except for construction of the channel 
and turning basin at Sebastian, Florida, which is 
in an inactive status. 
Total Federal costs under existing project 
through June 30, 1975, were $16,953,980 for new 
work, $10,247,614 for maintenance, and $989,537 
for operation and care, a total of $28,191,130, regular 
funds. In addition, $2,199,842 has been expended 
from public works funds for new work. 
Non-Federal costs for lands, spoil areas, rights-ofway, 
and other costs are estimated at $3,195,000. 
12. JACKSONVILLE HARBOR, FLA. 
Location. The authorized project comprises the 
lower 24.9 miles of St. Johns River which empties 
into the Atlantic Ocean near the northeasterly 
corner of the Florida peninsula. (See Coast and 
Geodetic Survey Chart No. 636-SC.) 
Previous projects. For details, see page 607 of 
Annual Report, 1938. 
Existing project. The authorized project provides 
for a channel 38 feet by 400-1,200 feet 
from the ocean to mile 20 via Dame Point - Fulton 
Cutoff, thence 34 feet to Commodore Point, and 
thence 30 feet deep to the F.E.C. Railway bridge 
at Jacksonville, including a 30-foot channel in 
Arlington Cut and in the Old Dame Point-Fulton 
Channel; maintenance of the existing 42-foot and 
40-foot-depth entrance channel; maintenance of 
jetties at channel entrance; and construction of 
training walls and revetments. Plane of reference 
is mean low water. The project is about 26.8 miles 
long. 
Mean tidal range is 5.3 feet on the bar, 4.9 feet 
at Mayport, 2.6 feet at Dame Point, and 1.1 feet at 
Jacksonville. The extreme range varies from 
about 9 feet on the bar to about 1.5 feet at Jacksonville. 
Strong northeasterly winds raise the 
water level about 2 feet at Mayport and Jacksonville. 
Strong southwesterly winds lower the 
water about 1.5 feet at Mayport and 1 foot at 
Jacksonville. 
Estimated cost of new work (1975) is $49,025,000 
Federal cost exclusive of amounts expended on 
previous projects and $3,797,000 non-Federal cost 
($950,000 contributed funds and $2,847,000 for 
lands, rights-of-way, and other costs). Of this 
amount, completed modifications amounted to 
$12,425,000 Federal costs and $11,000 non-Federal 
costs for lands, easements, and rights-of-way. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests have fully 
9-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
complied with requirements of local cooperation 
for work performed to date. For work authorized 
by the 1965 River and Harbor Act, local interests 
must contribute 2.6 percent of the contract price 
plus supervision and administration for work to 
be provided by the Corps; provide all lands and 
rights-of-way; save the United States free from 
damages; and provide and maintain public terminal 
and transfer facilities. Assurances of local 
cooperation for this work were accepted February 
11, 1966. Estimated non-Federal contribution 
for new work is $950,000. 
Terminal facilities. There are approximately 
100 waterfront facilities serving the port, including 
29 commercially operated, four of which 
are open to the public. There are 12 commercial 
oil terminals and four oil docks operated by the 
Navy Department. Rail connections are available 
to all but one of the oil terminals and to most commercial 
facilities. Jacksonville Shipyards have 
facilities for building and repairing large vessels, 
and numerous facilities are available for repairing 
and servicing small craft. 
Jacksonville Port Authority operates municipal 
docks at two locations, Talleyrand and Blount 
Island. Over six hundred thousand (600,000) square 
feet of warehousing have been completed and are 
in operation at Talleyrand. There is a 4,500-foot 
marginal wharf. Paved open storage of 102 acres 
is in use, as well as two 27.5 ton capacity container 
cranes. The facility has extensive rail and 
highway connections. 
On Blount Island a total of 3,000 feet of marginal 
wharf has been constructed (the last 400' 
completed in 1975) and nearly 110 acres of open 
storage have been paved. Paving and drainage of 
an additional 27 acres of container storage areas 
has been completed. Two transit sheds were 
erected with a total of 360,000 square feet of 
space and three cranes now servicing the berthing 
area. They include a 100-ton and 50-ton gantry 
and a 45-ton twin-lift container crane. Delivery of 
a pair of roll on/roll off ramps was accepted for 
servicing container vessels. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 15, Rev. 1969, 
Corps of Engineers.) 
Operations and results during fiscal year. 
New work: Contract costs relative to recently 
completed dredging of channel from Mile 10.7 to 
Mile 14.4 were $18,613. Channel enlargement 
from Mile 14.4 to Mile 17.3 commenced November 
12, 1974 and from Mile 17.3 to Mile 18.8 commenced 
May 19, 1975. Contract costs were 
$2,125,541 and $330,600, respectively. Engineering 
and design and supervision and administration 
costs were $199,017 and $21,923, respectively. 
Hired labor surveys, inspections, and reports cost 
$3,070. 
Maintenance: Contract costs incurred in connection 
with maintenance portion of contract for 
deepening channel from Mile 14.4 to Mile 17.3 
were $106,950. From December 13, 1974 to June 
30, 1975 Dredges Dauntless and Cherokee removed 
680,000 cubic yards of material from 30 
foot channel of Blount Island and 38 foot project 
at a cost of $847,032. Operation and maintenance 
of district communications network cost $7,105. 
Engineering and design and supervision and 
administration costs were $44,394 and $15,702, 
respectively. Hired labor surveys, inspections, 
and reports cost $157,395. 
Condition at end of fiscal year. Construction of 
the modification to the project, authorized by 
1965 River and Harbor Act, is 49 percent completed. 
Jetties are in good condition; revetments 
and training walls are in fair condition. Work remaining 
to complete the active portion of the project 
is deepening of the channel to 38 feet from 
Mile 14.4 to Mile 20. 
Total Federal costs under existing project 
through June 30, 1975, were $30,086,358 for new 
work, $23,500,241 for maintenance, a total of 
$53,586,599, regular funds. In addition, $290,013 
has been expended from public works funds for 
new work. 
13. MAYAGUEZ HARBOR, P.R. 
Location. The project is on the west coast of 
Puerto Rico, about 110 miles by water from San 
Juan Harbor. (See Coast and Geodetic Survey 
Chart No. 931.) 
Existing project. The authorized project provides 
for a 30-by 1,000-foot approach channel to 
the deep water terminal, decreasing to a 500 foot 
width opposite westerly end of terminal, thence 
the same width to easterly end of terminal. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. A modern deep-water terminal 
is located in the northeast section of the 
harbor consisting of a bulkhead wharf about 1,270 
feet long with a storage transit-shed 800 by 60 
feet immediately shoreward. The Puerto Rico 
Industrial Development Company, an agency of 
the Commonwealth of Puerto Rico, owns a bulkhead 
wharf of about 200 feet in line with the 
existing deep-water terminal plant located within 
the industrial harbor area. In addition, IBEC 
Packing Company, Inc., owns and operates a dock 
of about 200 feet for docking tuna fish boats. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: During the period July 17-25, 1974, 
U.S. Dredge Hyde removed 26,423 cubic yards of 
9-8

JACKSONVILLE, FLA., DISTRICT 
material from the approach and terminal channels 
at a cost of $92,947. Engineering and design 
coa st was $1,220. Hired labor sn vv -cand 
reports cost $1,027. 
Condition at end of fiscal year. Project was 
completed in 1934. 
14. MIAMI HARBOR, FLA. 
Location. Miami is near the northerly end of 
Biscayne Bay, about 71 miles south of the entrance 
to Palm Beach Harbor. Miami River has its source 
in the Everglades and flows southeasterly to 
enter Biscayne Bay at Miami. (See Coast and Geodetic 
Survey Charts Nos. 547 and 1248.) 
Existing project. The authorized project provides 
for a 38-foot by 500-foot channel from the 
ocean to the outer end of the north jetty, thence 
36 feet by 400 feet wide through the entrance and 
across Biscayne Bay to and including a turning 
basin at the municipal terminals; a 36-foot depth 
turning basin at Fisher Island; two rubblestone 
jetties at the entrance; a channel 15 feet by 200 
feet from the mouth of Miami River to the turning 
basin at the municipal terminals; a channel 8 feet 
by 200 feet from the mouth of Miami River to the 
Intracoastal Waterway and thence 100 feet wide 
to Government Cut; a channel 15 feet deep in 
Miami River varying in width from 250 feet at 
mouth to 90 feet inland; and a channel 12 feet by 
100 feet from Miami to a harbor of refuge in Palmer 
Lake. Plane of reference is mean low water, 
except for a 15-foot channel in Miami River where 
depths are based on flood conditions. Total length 
of the project is about 15.3 miles. 
Mean tidal variation is 2.5 feet at entrance and 
2 feet in the bay. Extreme variation is about 4.5 
feet at entrance and 3 feet in Biscayne Bay. 
Strong easterly winds raise the water level about 
1.5 feet at entrance and 1 foot in the bay. Strong 
westerly winds lower water level about 1 foot at 
entrance and about 0.5 foot in the bay. 
Estimated cost (1973) of 1968 modification to 
the project is $14,400,000 Federal (Corps of 
Engineers) cost and $1,860,000 non-Federal cost 
($1,330,000 contributed funds and $530,000 other 
costs). (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide 
all lands and rights-of-way; provide and 
maintain public terminal facilities; hold and save 
the United States free from damages; accomplish 
utility and other relocations and alterations as 
required; establish regulations prohibiting discharge 
of pollutants into the waters of the channel 
and harbor by users thereof; contribute 8.2 
percent of the construction cost of the 1968 
modification, including engineering and design 
and supervision and administration costs; contribute 
one-third of the initial cost of deepening the 
channel from Miami River to the harbor of refuge 
in Palmer Lake; provide and maintain suitable 
depths in harbor of refuge and construct and 
maintain adequate mooring facilities therein; and 
in time of storm have refuge open to all free of 
charge. Estimated contributed funds for new 
work are $1,330,000. 
Assurances of local cooperation for the 1968 
modification to the project were accepted December 
18, 1968. 
Terminal facilities. Existing facilities consist of 
82 piers and wharves, of which two are on Fisher 
Island, 12 at Miami Beach, four along the south 
side of MacArthur Causeway, one along the west 
side of Biscayne Bay at Miami, and 43 on Miami 
River. Nineteen facilities are open to the public 
for handling general cargo, eleven of which accommodate 
deep-draft vessels. All general cargo 
wharves have highway and railway connections 
except the causeway terminal which has highway 
connections only. A municipal yacht anchorage 
basin and wharf are open to the public for recreational 
craft. Of the remaining piers and wharves, 
five are used for handling petroleum products, 22 
are used in connection with ship repair activities, 
and 19 are used for mooring vessels or handling 
private freight. In addition, numerous landing 
facilities in and around Miami are designed for 
and used exclusively by recreational craft. 
Metropolitan Dade County is actively engaged 
in developing port facilities on Dodge Island in 
Biscayne Bay. Completed and in use are approximately 
6,700 feet of deep water berthing space (30 
ft. m.l.w.) with dredging to 36 feet not yet completed, 
and 4,390 feet (25 ft. m.l.w.). Eight passenger 
terminals can each accommodate and process 
900 persons through customs. There are 6 transit 
cargo sheds, 2 at 200,000 square foot, one a 120,000 
square feet, one at 80,000 square feet, and 2 at 
36,000 square feet for a total of 672,000 square 
feet. There are presently in use ten berths for 
roll-on trailerships. A slip 800 feet by 400 feet on 
the south side of the island has been completed 
and is being utilized for oceanographic research 
vessels. 
Upon completion, facilities are expected to be 
adequate for current commerce. (See Port Series 
No. 16, Revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. New 
work: Dredging in entrance channel and turning 
basin continued. Contract costs were $5,045,394. 
Engineering and design and supervision and 
administration costs were $26,684 and $201,076, 
respectively. 
Condition at end of fiscal year. Construction of 
the modification to the project, authorized by 
River and Harbor Act of 1968, is 80 percent com- 
9-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
plete. Work remaining to complete the project is: 
(a) deepening entrance channel and turning basins 
which is underway; (b) widening of the mouth of 
Miami River; (c) providing a channel 15 feet by 
200 feet from the mouth of the river to the municipal 
turning basin; (d) providing a channel 8 feet by 
200 feet from the mouth of the river to the Intracoastal 
Waterway, thence 100 feet wide to 
Government Cut; and (e) providing a channel 12 
feet by 100 feet from Miami River to a harbor of 
refuge in Palmer Lake. Items (b), (d), and (e) are in 
an inactive status. 
South and north jetties are in fair condition. 
Maintenance dredging is required in the turning 
basin at the municipal terminals. 
15. NEW PASS, SARASOTA, FLA. 
Location. Sarasota Bay is a tidal lagoon along 
west coast of Florida immediately south of Tampa 
Bay. New Pass is a gulf inlet across the bay from 
Sarasota, Fla. (See Coast and Geodetic Survey 
Chart No. 857-SC.) 
Existing project. The authorized project provides 
for an entrance channel 10 feet deep and 150 
feet wide in the Gulf of Mexico diminishing to 8 
feet deep by 100 feet wide through New Pass and 
extending across Sarasota Bay to the Intracoastal 
Waterway with side channels to, and turning 
basins at, Payne Terminal and city pier. Plane of 
reference is mean low water. Mean range of tide 
is 1.3 feet in Sarasota Bay; mean spring range is 
1.7 feet. Project is about 4 miles long. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work amounted 
to $45,811. 
Terminal facilities. Consist of Payne Terminal, 
a slip 200 by 650 feet, and city pier, 400 feet long 
with two finger piers equipped with adequate 
facilities at each location. 
Operations and results during fiscal year. 
Maintenance: Final costs on recently completed 
contract for dredging entrance channel were 
$24,713. 
Condition at end of fiscal year. Project was 
completed in 1964. 
16. OKEECHOBEE WATERWAY, FLA. 
Location. The waterway traverses the southern 
part of the Florida peninsula via the Caloosahatchee 
River, Lake Okeechobee, and St. Lucie 
Canal, connecting coastal waterways along the 
Gulf and Atlantic shores. (See Coast and Geodetic 
Survey Charts Nos. 855-SC and 856-SC.) 
Previous projects. For details, see page 785 of 
1949 Annual Report. 
Existing project. The authorized project provides 
for replacing the old locks on the St. Lucie 
Canal by a single new lock; a channel 10 feet by 
100 feet from Ft. Myers for about 5 miles upstream, 
thence 8 feet by 80 to 100 feet to the 
Intracoastal Waterway, Jacksonville to Miami, 
near Stuart; an 8-foot depth basin at Stuart; a side 
channel at Ft. Myers; operation and care of St. 
Lucie Lock; and maintenance of features completed 
under previous projects as follows: a 12- 
foot by 200-foot channel from the Gulf to Punta 
Rassa, thence 10 feet by 100 feet to Fort Myers 
with a 10-foot depth basin at Fort Myers; a 6-foot 
by 80-foot channel along the south shore of Lake 
Okeechobee from Clewiston to St. Lucie Canal; a 
6-foot by 60-foot channel in Taylor Creek from the 
town of Okeechobee to the Lake; and operation 
and care of Moore Haven and Ortona Locks. 
(See Table 9-B for Authorizing Legislation.) 
For further details see 1962 Annual Report. 
Local cooperation. Fully complied with for completed 
portion of project. Non-Federal contribution 
amounted to $502,277. 
Terminal facilities. There are 3 freight piers, 1 
municipal recreation pier, 4 privately owned 
piers, and a municipal yacht basin on the Caloosahatchee 
River near Fort Myers. The Corps has 
provided a boat basin, launching ramp, and a 120- 
foot wharf on the Caloosahatchee River about 
one-quarter mile below Ortona Lock. Commercial 
yacht basins are provided on the south side of the 
Caloosahatchee River about halfway between 
Ortona and Moore Haven Locks and about 3 miles 
east of LaBelle. A commercial/municipal yacht 
basin is provided on the north side of the St. 
Lucie Canal at Indiantown. 
There are numerous small wooden-pile landings 
along the Caloosahatchee River, on St. Lucie 
Canal, and on the St. Lucie River, including one 
railroad terminal pier, a municipal pier, and a pier 
for handling petroleum products at Stuart. Also, 
550 feet of wharves have been provided on the 
west side of Taylor Creek immediately landward 
of Hurricane Gate No. 6 and 150 feet on the east 
side of the creek. A yacht basin has been provided 
on the west side of the creek immediately landward 
of the hurricane gate. The installations on 
Taylor Creek are privately owned, but are open 
to the public. A breakwater protected harbor is 
available at Pahokee. There is a 440-foot marginal 
wharf on the Industrial Canal at Clewiston; a 125- 
foot wharf at LaBelle; a 150-foot wharf at Belle 
Glade; a 125-foot wharf at Moore Haven; a 50-foot 
wharf at Alva; and a 30-foot wharf on Taylor 
Creek at the town of Okeechobee. A docking 
facility for loading raw sugar was constructed in 
1967 on Herbert Hoover Dike near Belle Glade. 
All have highway and/or railway connections. 
Facilities are considered adequate for existing 
9-10

JACKSONVILLE, FLA., DISTRICT 
commerce. 
Operations and results during fiscal year. (See 
Table 9-F for work accomplished.) 
Condition at end of fiscal year. The project is 
complete except for providing the 8-foot depth 
basin at Stuart, which is inactive. 
Total Federal costs under the existing project 
through June 30, 1975, were $4,420,107 for new 
work, $3,847,161 for maintenance, and $3,546,346 
for operation and care, a total of $11,813,614. 
17. OKLAWAHA RIVER, FLA. 
Location. The river has its source in a system 
of large lakes in the central part of the Florida 
peninsula and flows generally northerly, then 
easterly, emptying into St. Johns River 22 miles 
above Palatka. The extreme head of the system is 
considered to be Lake Apopka, 120 miles above 
the river's mouth. 
Previous projects. For details, see page 613 of 
1938 Annual Report. 
Existing project. The authorized project provides 
for a channel 6 feet deep from the river 
mouth to the head of Silver Springs Run; clearing 
a channel to Lake Griffin; maintaining dikes to 
obtain a navigable depth of about 4 feet to Leesburg 
and construction of a lock and dam at Moss 
Bluff. The project length is about 85.7 miles in the 
river and 5.4 miles in Silver Springs Run. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Numerous private and 
public landings and boat-launching ramps are 
located along the river. Public recreation-craft 
basins and boat-launching ramps are near Silver 
Springs and State Road 40 and 316 bridges. There 
is a municipal wharf on Lake Griffin at Leesburg. 
Facilities are considered adequate for existing 
commerce. A dam has created Lake Ocklawaha 
(13,000 acres) with egress to the St. Johns River 
through Buckman Lock. Along the lake are 4 
launching ramps: Payne Landing, Orange Springs, 
Kenwood Landing, and Recreation Site 2B. Access 
below the dam is at the Oklawaha Boat 
launch ramp and at State Road 19. 
Operations and results during fiscal year. 
Maintenance: Snagging and clearing channel 
between St. Johns River and Moss Bluff cost 
$41,107. Dredging in 4-foot channel below Moss 
Bluff cost $2,999. Removal of shoals in Okiawahid 
River cost $91,996. Engineering and design and 
supervision and administration costs were $2,955 
and $14,398, respectively. Hired labor surveys, 
inspections, and reports cost $2,444. 
Condition at end of fiscal year. The project is 
complete except for providing a 6-foot depth 
channel from the mouth of the river to the head of 
Silver Springs Run, which is in an inactive status. 
The Moss Bluff lock and dam structure was replaced 
under the Four River Basins, Fla., flood 
control project. 
Total Federal costs under the existing project 
through June 30, 1975, have been $311,352 for 
new work and $1,747,775 for maintenance, (excluding 
$11,414 under provisions of the permanent 
indefinite appropriation), a total of $2,059,127. 
18. PALM BEACH HARBOR, FLA. 
Location. The authorized project is located on 
the east coast of Florida about 71 miles north of 
the entrance to Miami Harbor and about 264 
miles southeasterly from the entrance to Jacksonville 
Harbor. (See Coast and Geodetic Survey 
Charts Nos. 291 and 1248.) 
Existing project. The authorized project provides 
for an entrance channel 35 feet by 400 feet 
merging with an inner channel 33 feet by 300 feet 
to and including a turning basin; bank revetment; 
and restoring jetties. Plane of reference is mean 
low water. The project is about 1.6 miles long. 
Mean range of tide in the ocean at the entrance 
is 2.8 feet and at the turning basin, 2.2 feet. Extreme 
range of tide is about 4.5 feet at the inlet 
and 3 feet at the terminals. Seven-foot tidal 
ranges have occurred during storms. For details, 
see 1962 Annual Report. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
For requirements, see 1961 Annual Report. Non- 
Federal contribution for new work was $509,506. 
Terminal facilities. There are two slips with 
wharves, three warehouses, with a total of approximately 
138,500 square feet, and four steel 
storage tanks for petroleum products connected 
with terminals by pipelines. Rail and highway 
connections, water supply, and other facilities 
have been provided in warehouses and shipside 
of slips. Facilities afford total berthing space of 
approximately 4,700 feet. The wharves are owned 
by Port of Palm Beach District. New plans for the 
port include additional roll on/roll off facilities, 
additional marginal wharf and construction of a 
container handling facility. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 16, Revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Contract costs relative to recently 
completed dredging in entrance channel were 
$30,063. Operation of district communication network 
cost $5,329. Mitigation of shore damages 
amounted to $6,551. Engineering and design and 
supervision and administration costs were $4,790 
and $393, respectively. Hired labor surveys, in- 
9-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
spections, and reports cost $33,337. 
Condition at end of fiscal year. The project was 
completed in 1967. Jetties and revetment are in 
good condition. 
19. PONCE DE LEON INLET, FLA. 
Location. Ponce de Leon Inlet is on the Atlantic 
coast of Florida about 65 miles south of St. Augustine 
Harbor and 57 miles north of Canaveral Harbor. 
(See Coast and Geodetic Survey Chart No. 
1245.) 
Existing project. The Authorized project provides 
for an entrance channel 15 feet by 200 feet 
across the ocean bar, thence 12 feet by 200 feet 
and 12 feet by 100 feet through the inlet; thence 
southward in Indian River North 12 feet by 100 
feet, and northward in Halifax River, 7 feet by 
100 feet, each leg continuing to the Intracoastal 
Waterway; ocean jetties on the north and south 
side of the inlet 4,200 feet and 2,700 feet long, respectively; 
and a weir in the north jetty with an 
impoundment basin inside the jetty. Plane of 
reference is mean low water. Mean range of tide 
is 4.1 feet in the ocean and 2.3 feet inside the inlet. 
The project is about 5 miles long. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$2,377,884. 
Terminal facilities. None in the immediate area. 
Operations and results during fiscal year. 
Maintenance: From May 14 to June 30, 1975 U.S. 
Dredge Hyde removed 138,009 cubic yards of 
material from entrance channel at a cost of 
$517,153. Closure of breakthrough near, and 
beach fill from, impoundment basin was completed 
August 25, 1974 at a contract cost of 
$582,198. Engineering and design and supervision 
and administration costs were $34,446 and $6,402, 
respectively. Hired labor surveys, inspections, 
and reports cost $96,801. 
Condition at end of fiscal year. Construction of 
the project is complete. Ocean jetties and weir 
are in good condition. 
20. PONCE HARBOR, P.R. 
Location. Ponce Harbor is on the southcentral 
coast of Puerto Rico, about 150 miles by water 
southeast from San Juan Harbor. (See Coast and 
Geodetic Survey Charts Nos. 902 and 927.) 
Existing project. The authorized project provides 
for a seawall 362 feet long; dredging two 
areas north of the causeway leading to the pier, 
30 feet deep and 18 feet deep and containing 
about 77 and 47 acres, respectively; dredging an 
area off the municipal pier 30 feet deep and containing 
about 18 acres and a breakwater 2,400 
feet long extending southwesterly from Punta 
Carenero. Plane of reference is mean low water. 
Mean tidal range is 0.6 foot; extreme varies 
between about 1 foot below and 2 feet above 
mean low water. Estimated Federal cost of new 
work (1956) is $1,430,000. In addition, $21,960 has 
been expended from contributed funds. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. The United States shall reimburse 
local interests funds contributed for 
dredging and shall undertake, without contribution 
by local interests, remaining dredging included 
in the project. All other portions of improvement 
(bulkhead and seawall) shall be at the 
expense of local interest. Local interests must 
construct 2,362 linear feet of seawall and 4,340 
linear feet of concrete bulkhead wharf; construct 
a rubblemound bulkhead and public landing for 
small boats; cede to a 1-acre plot fronting on the 
rubblemound bulkhead; furnish suitable spoildisposal 
areas; and provide rights-of-way and release 
from damage claims. For further details see 
1949 Annual Report. 
Terminal facilities. The municipality of Ponce 
owns and operates the only deep-draft terminal 
facilities in Ponce Harbor, which consist of a 
municipal pier 515 feet long and 108 feet wide, 
and a bulkhead wharf 2,611 feet long. Both are 
equipped for transfer and storage of freight. An 
additional 1,200 feet of bulkhead wharf and a 72.5 
ton container lift shore crane were recently completed. 
The municipal pier has a steel transit shed 
386 by 85 feet. The bulkhead wharf has four steel 
transit sheds totaling over 103,000 square feet. 
Three concrete and steel warehouses are available 
providing 80,000 square feet for general storage. 
Open storage areas for structural steel, lumber, 
and other bulk and package commodities are 
also provided. Bulk cement is handled and loaded 
into cement cargo ships by the use of a private 
pipeline loading facility. A tuna fish processing 
and canning factory is located on the premises, 
with direct access to the bulkhead wharf. Existing 
facilities are open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: During the period July 1-16, 1974, 
and September 18-30, 1974 U.S. Dredge Hyde removed 
64,293 cubic yards of material to restore 
30-foot project depth at a cost of $291,775. Engineering 
and design cost was $3,439. Hired labor, 
surveys, inspections, and reports cost $12,805. 
Condition at end of fiscal year. The existing 
project is about 13 percent complete. Work remaining 
for the Federal portion of the project 
consists of completing the dredging of the 30-foot 
maneuvering area next to the municipal bulkhead 
terminal; dredging the 18-foot area; dredging the 
9-12

JACKSONVILLE, FLA., DISTRICT 
30-foot area serving the municipal pier; and constructing 
a breakwater extending southwesterly 
from Carenero Point. A study completed in 1959 
found that completion of the remaining work was 
not justified at that time. 
21. REMOVING THE WATER 
HYACINTH FROM NAVIGABLE 
WATERS IN THE STATE OF 
FLORIDA. 
Location. Water hyacinth is found in freshwater 
streams and lakes in various parts of the 
district. 
Existing project. The authorized project provides 
for destruction or removal of water hyacinth 
in navigable waters of the State so far as 
they constitute an obstruction to navigation and 
commerce, using any mechanical, chemical, or 
other means not injurious to cattle, and use of log 
booms to close sloughs and backwaters as an 
auxiliary means. No estimate of the final cost of 
work has been made. (See Table 9-B for Authorizing 
Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Spraying operations continued during 
the year. (See Table 9-G for Spraying Operations.) 
Condition at end of fiscal year. The project is 
for maintenance. During the year, 24,113 acres of 
hyacinths were sprayed in approximately 2,000 
miles of waterways. Hyacinths in Lake Okeechobee 
and in St. Johns River Watershed are under 
reasonable control. 
22. ST. AUGUSTINE HARBOR, FLA. 
Location. The harbor is on the east coast of 
Florida, about 35 miles south of the entrance to 
St. Johns River and about 180 miles north of Fort 
Pierce Harbor. (See Coast and Geodetic Survey 
Charts Nos. 1243 and 1244.) 
Previous project. For details see page 412 of 
Annual Report for 1958. 
Existing project. The authorized project provides 
for a channel 16 feet by 200 feet along the 
best natural alinement as may exist from time to 
time across the new inlet bar, thence 12 feet deep 
to the Intracoastal Waterway; a sandtrap groin 
on the north side of the inlet extending seaward 
from the shore of Vilano Beach, and a sand-tight 
jetty on the south side of the channel extending 
seaward from the shore of Conch Island parallel 
to and coextensive with the groin, future landward 
extension of the groin and jetty; and a channel 
10 feet by 100 feet in San Sebastian River 
from the Intracoastal Waterway to King Street 
bridge, with a turning basin near the upper end. 
Length of the inlet channel is about 1.5 miles, and 
length of the San Sebastian River channel is 
about 2.6 miles. Plane of reference is mean low 
water. The mean tidal range is 4.5 feet in the 
ocean at St. Augustine Inlet and 4.2 feet at the 
city waterfront. Strong northerly winds, mostly 
in the winter, lower the water surface about 1 
foot. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work amounted 
to $137,500. 
Terminal facilities. There are several timber 
docks on the Matanzas waterfront of St. Augustine. 
In this area of the harbor is a concrete dock 
which serves as a municipal yacht pier. It has fuel 
facilities, 19 slips and accomodates boats up to 60- 
ft. in length. A large public boat ramp is also 
available. The principal terminals are the numerous 
shrimp docks in the San Sebastian River 
which flows southward through the city into the 
Matanzas River south of the bridge; these consist 
of timber wharves, with frame and corrugated 
iron warehouses thereon, and 9 marine railways 
for small boats. There is also a marine supply 
facility and several boat yards. The present terminals 
have highway connections and several of 
the shrimp docks have rail connections. They are 
considered adequate for existing commerce and 
recreational craft. 
Operations and results during fiscal year. 
Maintenance: From January 2 to March 15, 1975 
U.S. Dredge Merritt removed 97,218 cubic yards 
of material from the entrance channel at a cost of 
$153,000. From March 10 to April 10, 1975 U.S. 
Dredge Schweizer removed 47,864 cubic yards of 
material from the entrance channel at a cost of 
$146,000. From May 27 to June 30, 1975 U.S. 
Dredge Davison removed 84,395 cubic yards of 
material from the entrance channel at a cost of 
$206,693. Engineering and design and supervision 
and administration costs were $6,626 and $180, 
respectively. Hired labor surveys, inspections, 
and reports cost $47,501. 
Condition at end of fiscal year. Project is complete. 
The groin is in fair condition except for the 
300 feet which has subsided to about elevation 3.0 
feet, mean low water. The jetty is in fair condition. 
Total Federal costs under the existing project 
through June 30, 1975, were $1,405,131 for 
new work and $1,172,115 for maintenance, a total 
of $2,577,246. 
23. ST. LUCIE INLET, FLA. 
Location. The inlet is on the east coast of Florida 
about 19 miles south of the entrance to Fort 
Pierce Harbor, Florida, and 100 miles north of the 
9-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
entrance to Miami Harbor, Florida. (See Coast 
and Geodetic Survey Chart No. 1247.) 
Previous project. For details see page 764 of 
Annual Report for 1949. 
Existing project. The authorized project provides 
for extending the north jetty about 500 
feet and modifying existing jetty to provide a 
sand bypass weir section about 500 feet long; excavation 
of a sand impoundment basin adjacent to 
the bypass weir in the north jetty; construction of 
a south jetty consisting of a rubblemound structure 
about 2,400 feet long with a walkway for recreational 
fishing; channel between existing bar 
cut and the Intracoastal Waterway 10 by 500 feet 
through the bar cut, tapering to 150 feet through 
the inlet, and 100 feet wide and 7 feet deep to the 
Intracoastal Waterway; and transfer of 380,000 
cubic yards of material to the south beach during 
each two year maintenance period. Plane of reference 
is meal low water. Total project length is 
about 1.9 miles. Mean tidal range is 2.6 feet on the 
ocean side and about 1 foot on the land side of the 
inlet. 
The estimated cost of the 1974 modification 
(1975) to the project is 3,800,000 Federal (Corps of 
Engineers) cost and $1,330,000 non-Federal cost 
($1,080,000 contributed funds and $250,000 other 
costs). (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must: contribute 
19.9 percent of construction cost allocated 
to navigation in the combined project, 23.2 percent 
allocated to beach erosion, and 50 percent of 
construction cost of jetty fishing walkway; provide 
39.8 percent of the annual maintenance cost 
allocated to navigation and 23.2 percent of the 
annual costs for maintenance dredging allocated 
to beach erosion control for periodic beach nourishment 
and 100 percent of the annual jetty maintenance 
costs allocated to beach erosion control; 
maintain jetty fishing walkway; agree that each 
five years the amount of local cost sharing for 
maintenance is to be adjusted; provide all lands, 
easements, and rights-of-way; hold United States 
free from damages; provide marina with mooring 
facilities and utilities; provide and maintain 
depths in berthing area and local access and feeder 
channels commensurate with the depths provided 
in the project; accomplish such alterations 
as required in sewer, water supply, drainage, and 
other utility facilities; and take action to place in 
effect statutes and/or regulations which will protect 
the water quality for the authorized uses of 
the project. Assurances of local cooperation for 
the 1974 modification have not yet been requested 
from the local sponsor. 
Terminal facilities. A municipal pier provides 
facilities for docking and servicing charter fishing 
and small recreational craft. At Stuart there is a 
dock for handling bulk petroleum products and 
several marinas which provide facilities for mooring, 
servicing and minor repair of small craft. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging in the 6-foot inner channel, 
as required, commenced September 25, and 
was completed October 16, 1974. Dredge Merritt 
removed 20,545 cubic yards of material at a cost 
of $44,245. Contract costs for maintenance dredging 
in entrance channel were $328,560. Operation 
of district communications network cost $1,776. 
Engineering and design and supervision and administration 
costs were $5,404 and $7,502, respectively. 
Hired labor surveys, inspections, and 
reports cost $20,319. 
Condition at end of fiscal year. Work required 
to complete the project is construction authorized 
in House Document 294/93/1. Total Federal 
costs under existing project through June 30, 
1975, were $96,913 for new work and $1,074,383 
for maintenance, a total of $1,171,296. 
24. SAN JUAN HARBOR, P.R. 
Location. San Juan Harbor is on the north coast 
of Puerto Rico, about 30 miles west of Cape San 
Juan and 1,100 miles southeast of Miami, Fla. (See 
Coast and Geodetic Survey Chart No. 908.) 
Previous projects. For details, see Annual 
Reports for 1915, 1916, and 1938. 
Existing project. Entrance channel 38 by 800 
feet across the outer bar to channel bend with a 
45- by 500-foot section within this channel, thence 
[36 by 1,200-880 feet to inner harbor extending to 
intersection of Graving Dock and Army Terminal 
Channels; a channel 35 by 600 feet to San Antonio 
Channel with an area 35 by 3,001, 100 by 2,800 
feet in San Antonio Channel; a channel 36 by 300 
feet in Army Terminal Channel with turning 
basin; a channel 30 by 400 feet from inner harbor 
to Graving Dock with turning basin; 32- by 300- 
foot Puerto Nuevo Channel from Army Terminal 
basin to Graving Dock basin; and 36-foot-deep 
anchorage off Isla Grande. Plane of reference is 
mean low water. 
Mean tidal range is 1.1 feet. Existing project 
was authorized by 1958 River and Harbor Act 
(HD 38/85/1) and prior acts. For additional information, 
see 1962 Annual Report. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$100,000. 
Terminal facilities. There are 28 piers and bulkhead 
wharves in the harbor capable of docking 
deep-draft vessels, which have an aggregate 
berthing length of about 23,736 feet; however, 
due to limiting depths it is estimated that berth- 
9-14

JACKSONVILLE, FLA., DISTRICT 
ing space available for deep-draft vessels is about 
23,645 feet. Eleven piers and bulkhead wharves 
are on the north shore, 2 front Graving Dock turning 
basin and channel, 9 are at the eastern side 
and 3 at the western side of the Army Terminal 
basin and channel, and 3 on the south shore of San 
Antonio Channel. One pier and bulkhead wharf 
are privately owned, 7 are U.S. Government property, 
and 19 owned by the Commonwealth of 
Puerto Rico. Twenty piers and wharves are 
equipped with mechanical transfer facilities. Five 
wharves are equipped with a special crane for the 
handling of loaded containers. Nineteen are open 
to general public. 
There is an aggregate length of about 1,339 feet 
of berthing space at Catano Point used principally 
by small vessels within the 18-foot draft range. 
This space is also open to the public. In addition, 
there are 10 piers and bulkhead wharves with 
approximately 6,910 feet of berthing space owned 
and operated by different agencies of the Federal 
Government. This space is not open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging in Army Terminal turning 
basin and in Graving Dock Channel and turning 
basin started July 10, 1974. Bucket Dredge 
No. 506 removed 1,671,895 cubic yards of material 
at a contract cost of $1,599,869. From July 27 to 
September 17, 1974 U.S. Dredge Hyde removed 
147,200 cubic yards of material from Army Terminal 
Channel at a cost of $558,997. Engineering 
and design and supervision and administration 
costs were $25,191 and $48,838, resp1ively 
Hired labor surveys, inspections, and reports cost 
$85,848. 
Condition at end of fiscal year. Project is complete. 
Annual dredging generally restores project 
dimensions. 
Total Federal costs under the existing project 
through June 30, 1975, were $12,600,216 for new 
work and $5,368,873 for maintenance, a total of 
$17,969,089 regular funds. In addition, $427,068 
was expended for new work and $24,737 for maintenance 
from public works funds and $100,000 for 
new work from contributed funds. Existing project 
includes the entrance channel and turning 
basin to Army Terminal which cost $1,543,712; 
this expenditure was made from military appropriations 
and is not included in above costs. 
25. TAMPA HARBOR, FLA. 
Location. Tampa Harbor is in a large natural 
indentation of the Gulf of Mexico about midway 
of the west coast of Florida. The entrance is about 
220 miles north of Key West and about 330 miles 
southeast of Pensacola. (See Coast and Geodetic 
Survey Charts Nos. 586, 587, and 1257.) 
Previous projects. For details, see page 665 of 
1938 Annual Report. 
Existing project. The authorized project provides 
for a channel from the Gulf of Mexico to 
Port Sutton and Tampa; 46 feet by 700 feet from 
the Gulf of Mexico to Mullet Key; 44 feet by 600 
feet in Mullet Key Cut Channel; 44 feet by 500 
feet in Tampa Bay from Mullet Key Cut to Hillsborough 
Bay and Port Tampa Channels; 44 feet 
by 500 feet in Hillsborough Bay from junction 
with Tampa Bay and Port Tampa Channels to the 
junction with Port Sutton entrance channel, 
thence 42 feet by 400 feet to the junction with 
Seddon and Garrison Channels; 44 feet by 400 
feet in Port Sutton entrance channel; 42 feet by 
400 feet in Sparkman Channel; 40 feet by 300 feet 
in Ybor Channel; 42 feet by 400 feet in Port 
Tampa Channel; 44 feet by L400-500,feet in East 
Bay entrance channel; 44 feet by 300 feet in East 
Bay approach channel; 30 feet by 300 feet in 
Seddon and Garrison Channels; 30 feet by 200 
feet in Alafia River; 9 feet by 100 feet in Hillsborough 
River to a point 2,000 feet above Columbus 
River bridge; a breakwater; turning basins at 
Port Sutton, Ybor Channel, Port Tampa, East 
Bay, mouth of Hillsborough River, and in Alafia 
River; and maintenance of a channel 12 feet by 
200 feet in Hillsborough River and 44 feet by 200 
feet in Port Sutton terminal channel. (The 46-foot 
and 44-foot depth portions of the project include a 
5-foot underkeel clearance. Special studies on the 
project concluded that a 4-foot underkeel is sufficient. 
Therefore, a 1-foot overdepth has been 
placed in an inactive status, resulting in active 
project depths of 45 and 43 feet, respectively.) 
Plane of reference is mean low water. The project 
is about 67 miles long, including 10 miles in Hillsborough 
River and 3.6 miles in Alafia River. 
Mean range of tide is 1.3 feet at the lower end 
of the bay, 1.6 feet at Port Tampa, and 1.8 feet at 
Tampa. Extreme range is about 3.8 feet at the 
lower end of the bay and 4.8 feet at Tampa. 
Strong southwesterly winds raise the water level 
about 1.5 feet. Strong northerly winds, which 
usually occur in the winter, lower the water level 
about 2 feet. Estimated cost of new work (1975) of 
the 1970 modification to the project is $142,000,000 
Federal (Corps of Engineers) cost and $1,105,000 
non-Federal cost ($900,000 contributed funds 
and $205,000 other costs). (See Table 9-B for 
Authorizing Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. Local cooperation has been 
fully complied with for work completed to date. 
For work authorized by the River and Harbor Act 
of 1970, local interests must: provide all lands, 
easements, and rights-of-way; hold United States 
free from damages; provide and maintain adequate 
9-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
public terminal and transfer facilities open to all 
on equal terms; and establish regulations prohibiting 
discharge of pollutants into project 
waters. In addition, for work provided by HD 401/ 
91/2, local interests must: accomplish utility and 
other relocations or alterations necessary for project 
purposes; prohibit erection of any structure 
within 125 feet of project channels or turning 
basins; contribute 0.6 percent of construction 
cost; and provide a Port Sutton Channel 44 feet 
by 200 feet by 4,000 feet for Federal maintenance. 
For work provided by HD 150/91/1, local interests 
must also provide and maintain depths in berthing 
areas and local access channels serving the 
terminals commensurate with the depth provided 
in the related project areas. Assurances of local 
cooperation for the 1970 authorization were approved 
by the Secretary of the Army on January 
10, 1973. 
Terminal facilities. There are 78 commercial 
piers and wharves at Tampa, including those on 
Hillsborough River and Old Tampa Bay at Rattlesnake, 
Florida. Municipal terminals (called Metroport) 
on Ybor Channel consist of a slip 778 feet 
long, 250 feet wide, with a wharf on both sides, of 
which one has a steel-frame transit shed. Most 
facilities have railway connections. Municipal 
terminals, one city wharf, and about 10 privately 
owned terminals are open to the public. There are 
17 commercial oil terminals and 2 privately 
owned cement storage facilities. The Tampa Port 
Authority operates an 800-head capacity cattleloading 
wharf located on the east side of Sparkman 
Channel. Ship repair facilities are available. 
Considerable expansion of the port of Tampa is 
now underway. Eastern Associated Terminal 
operates phosphate-loading facilities accomodating 
barges and ocean vessels on East Bay. The 
Seaboard Coast Line Railroad began operating 
their new phosphate elevator, called "Rockport," 
in July 1970, replacing their facilities at Port 
Tampa and Seddon Island. River-Gulf Terminal 
operates a phosphate terminal at Port Sutton 
located just west of their bulk facility handling 
potash. International Mineral and Chemical Company 
also operates a phosphate terminal at Port 
Sutton. Under development is a new general 
cargo area on the East Bay Channel and Turning 
Basin known as Holland Terminal. Three 600-ft. 
berths have been completed and are in operation. 
Expansion plans call for additional berths in the 
future. Upon completion, facilities are expected 
to be adequate for existing commerce. (See Port 
Series No. 17, revised 1967.) 
Operations and results during fiscal year. New 
work: Planning for deepening channels continued. 
Engineering and design and supervision and administration 
costs were $255,527 and $259, respectively. 
Hired labor surveys, inspections, and 
reports cost $92. 
Maintenance: Operation of district communication 
network cost $10,658. Engineering and 
design and supervision and administration costs 
were $1,164 and $182, respectively. Hired labor 
surveys, inspections and reports cost $121,484. 
Condition at end of fiscal year. The project is 19 
percent completed. Work remaining is 'that authorized 
by the River and Harbor Act of 1970 (HD 
401/91/2). 
Total Federal costs under the existing project 
through June 30, 1975, were: Main project: 
$23,636,211 for new work and $8,818,002 for maintenance, 
a total of $32,454,213 regular funds. In 
addition, $1,329,300 was expended for new work 
from public works funds, $1,463,000 from emergency 
relief funds, and $14,842 from contributed 
funds. On Hillsborough River $270,466 was expended 
for new work. 
26. NAVIGATION PROJECTS ON WHICH 
RECONNAISSANCE AND CONDITION 
SURVEYS ONLY WERE CONDUCTED 
DURING FISCAL YEAR 
(See Table 9-H.) 
27. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 9-I.) 
28. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, 
Public Law 86-645 (Preauthorization) 
(See Table 9-J.) 
Beach Erosion Control 
29. BREVARD COUNTY, FLA. 
Location. The project is on the east coast of 
Florida at approximately the midpoint of the 
peninsula. (See Coast and Geodetic Survey 
Charts Nos. 1245 and 1246.) 
Existing project. The authorization provides 
for a protective and recreational beach with a 
berm 50 feet wide at elevation 10 feet above mean 
low water and a natural seaward slope as would 
be shaped by wave action, along 14,600 feet of 
beach at the city of Cape Canaveral and 10,600 
feet of beach at Indialantic and Melbourne Beach, 
and for periodic nourishment of the restored 
beach at Indialantic and Melbourne Beach limited 
initially to a period of 10 years. Nourishment of 
the restored beach at the city of Cape Canaveral 
would be provided by the authorized sand trans- 
9-16

JACKSONVILLE, FLA., DISTRICT 
fer plant planned for construction at Canaveral 
Harbor. The project also provides for improvement 
of the Federally owned shores for beach 
erosion control or hurricane protection to be accomplished 
by the Federal agencies involved, 
subject to their own determination of economic 
justification. The areas involved include 4.9 miles 
of shore at Kennedy Space Center, 4.0 miles at 
Cape Kennedy Air Force Station, and 2.3 miles at 
Patrick Air Force Base. 
Mean tidal range in the area is 3.5 feet. Estimated 
cost of the project (1975) is $3,460,000 Federal 
cost and $3,510,000 non-Federal cost 
($3,460,000 cash contribution and $50,000 for 
lands). (See Table 9-B for Authorized Legislation.) 
Local cooperation. Local interests must contribute 
50 percent of all first costs of the work and 
50 percent of the nourishment cost at Indialantic 
and Melbourne Beach for the first 10 years of the 
project life; provide lands and rights-of-way; provide, 
after the first 10 years of project life, periodic 
nourishment of the restored beach at Indialantic 
and Melbourne Beach during project life; 
maintain continued public ownership of the shore 
upon which the amount of Federal participation is 
based; control water pollution; and hold the 
United States free from damages. Assurances of 
local cooperation were approved by the Secretary 
of the Army on July 9, 1973. 
Operations and results during fiscal year. New 
work: Contract costs for providing initial beach 
fill at city of Canaveral were $405,200. Engineering 
and design costs were $68,562. 
Condition at end of fiscal year. Construction'of 
the project commenced April 15, 1974, and is 15 
percent complete. 
30. BROWARD COUNTY, FLA. 
BEACH EROSION CONTROL 
AND HILLSBORO INLET, FLA., 
NAVIGATION PROJECT 
Location. Broward County is on lower east 
coast of Florida, 300 miles south of Jacksonville 
and about 30 miles north of Miami. Hillsboro Inlet 
is in northern part of Broward County. (See Coast 
and Geodetic Survey Chart No. 1248.) 
Existing project. The authorization provides 
for Federal participation toward cost of a shore 
restoration and protection project and a project 
to provide and maintain a channel adequate for 
small craft navigation. Plan provides for restoration 
of a protective and recreational beach at four 
locations generally 100 feet wide with berm elevation 
of 10 feet above mean low water, a navigation 
channel 8 by 100 feet from the Intracoastal 
Waterway to a point 1,500 feet oceanward in 
Hillsboro Inlet, thence 10 by 150 feet in the ocean; 
jetties on north and south sides of ocean entrance; 
a permanently based floating dredge; and on a 
deferred basis, a trestle-mounted sand-transfer 
plant, if needed. Navigation portion of the project 
is in an inactive status. Mean range of tide in area 
is 2.5 feet. Plane of reference is mean low water. 
Cost estimate for new work (1975) is $3,400,000 
Federal and $11,200,000 non-Federal cash contribution. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
90.5 percent of the first cost of beach restoration 
in the reach between north county line and 
Hillsboro Inlet, 90 percent of first cost allocated 
to beach restoration, and 50 percent of first cost 
allocated to navigation for reach between Hillsboro 
Inlet and Port Everglades and 72.4 percent 
of beach restoration in reach between Port Everglades 
and south county line; provide all lands 
and rights-of-way; obtain approval of Chief of 
Engineers of plans and specifications if local interests 
construct beach erosion features; and 
furnish assurances that they will hold the United 
States free from damages, provide and maintain 
adequate public landing or wharf at Hillsboro 
Inlet, establish a public body to cooperate financially 
and to provide and operate local facilities 
for navigation, control water pollution, maintain 
ownership of publicly owned shores, and maintain 
all project works except the jetties (maintenance 
of the channel to revert to the United States if 
sand-transfer plant is constructed). Assurances of 
local cooperation were accepted November 22, 
1968. Estimated contributed funds for new work 
is $11,200,000. 
Operations and results during fiscal year. New 
work: Miscellaneous engineering and design costs 
relative to recent payment to local interests for 
providing initial beach fill from Hillsboro Inlet to 
Port Everglades were $8,129. 
Condition at end of fiscal year. Project is being 
constructed by local interests and is about 26 percent 
complete. 
31. DADE COUNTY, FLA. 
Location. Dade County is on the southeast 
coast of Florida. Project area consists of that part 
of the Atlantic shoreline of the county from Government 
Cut north to Bakers Haulover Inlet and 
at Haulover Beach Park. (See Coast and Geodetic 
Survey Chart No. 1248.) 
Existing project. Project provides for a protective 
and recreational beach having a dune at 
elevation 11.5 feet and a level berm 50 feet wide 
at elevation 9 feet, mean low water, for beach 
erosion control and hurricane protection between 
Government Cut and Bakers Haulover Inlet; a 
protective and recreational beach with a berm 
9-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
.elevation of 9 feet, mean low water, and a berm 
width up to 50 feet for beach erosion control at 
Haulover Beach Park; and Federal participation 
in the initial construction and in periodic nourishment 
of both the above reaches for the first 10 
years of project life. Plane of reference is mean 
low water. Mean range of tide in the area is 2.5 
feet. 
Estimated cost of the project (1975) is $38,200,000 
Federal cost and $28,600,000 non-Federal cost 
$28,200 cash contribution and $400,000 other 
costs). 
Project was authorized by Flood Control Act of' 
1968 (HD 335/90/2). * 
Local cooperation. Local interests must (a) contribute 
for the first cost of the work: between 
Government Cut and Bakers Haulover Inlet 
amounts ranging from 60.2 percent of the cost of 
the fill within the project limit with existing 
shorefront ownership to 39.3 percent of the cost 
of this fill with public shorefront ownership, and 
100 percent of the cost of fill required landward of 
the project limit; and for the work at Haulover 
Beach Park, contribute 21.3 percent of the entire 
first cost excluding costs for lands, easements, 
rights-of-way, relocations, and preproject work, 
but including credit for preproject work; (b) contribute 
in case for the first 10 years of project life, 
amounts ranging from 88.9 percent of the nourishment 
cost for the beach, with existing onwership, 
to 60.7 percent with public ownership, and the 
entire maintenance cost for the dune, all between 
Government Cut and Bakers Haulover Inlet; (c) 
provide all lands and rights-of-way; (d) hold United 
States free from damages; (e) assure continued 
public ownership and use of the shore upon which 
the amount of Federal participation is based; (f) 
assure maintenance of the groin, and after the 
first 10 years of project life, periodic nourishment 
of the protective beach and maintenance of the 
dune during the economic life of the project; (g) 
assure that water pollution will not be permitted; 
(h) prevent removal or relocation by man of fill 
from the beach berm and dune; (i) prevent the 
erection of barriers to the littoral movement of 
material that would interfere with the nourishment 
of the beach; (j) maintain at the parks qualifying 
for 70 percent Federal participation a zone 
that excludes permanent human habitation; (k) at 
least annually inform interests affected that the 
project will not provide complete protection from 
a hurricane tide level equal to or higher in elevation 
than that of the hurricane of September 1926; and 
(1) establish in public ownership for public use the 
beaches within project limits as a requirement for 
Federal participation .,in the allocated beach 
erosion control costs of improvement of shores 
presently in private ownership. Assurances of 
local cooperation have been requested from the 
local sponsor. 
Operations and results during fiscal year. New 
work: Preconstruction planning continued. Engineering 
and design costs were $173,541. 
Condition at end of fiscal year. Construction of 
the project has not commenced except for completion 
by local interests of Bal Harbour Village 
segment. 
32. DUVAL COUNTY, FLA. 
Location. On upper east coast of Florida, within 
20 miles of Florida-Georgia State line. Ocean 
shoreline is about 16 miles long. (See Coast and 
Geodetic Survey Chart No. 1243.) 
Existing project. Provides for Federal participation 
toward cost of constructing with artificial 
fill, a beach 60 feet wide at elevation 11 feet above 
mean low water with a natural slope seaward, and 
for periodic nourishment for 10 years. Federal 
participation to be 100 percent of the first cost of 
construction applicable to the Federal shore and 
50 percent applicable to the other publicly owned 
shore and 55.5 percent of periodic nourishment 
costs for first 10 years of project life. Mean tidal 
range at south jetty in St. Johns River is 4.9 feet. 
Estimated cost of new work (1975) is $11,700,000 
Federal and $9,500,000 non-Federal ($8,320,000 
contributed funds and $1,180,000 for other costs). 
Project was authorized by River and Harbor 
Act of 1965 (HD 273/89/1). 
Local cooperation. Local interests must contribute 
50 percent of first cost of constructing non- 
Federal publicly owned shores; contribute 44.5 
percent of periodic nourishment costs for first 10 
years of project life; provide all lands, rights-ofway, 
and relocations; hold the United States free 
from damages; control water pollution; and furnish 
assurances that they will maintain continued 
public ownership of the shore upon which the 
amount of Federal participation is based during 
economic life of project. Assurances of local cooperation 
were accepted on November 29, 1973. 
Estimated contributed funds for new work is 
$8,320,000. 
Operations and results during fiscal year. New 
work: Preconstruction planning continued. Engineering 
and design costs were $84,496. 
Condition at end of fiscal year. Construction of 
the project has not commenced. 
33. PALM BEACH COUNTY, FLA., FROM 
MARTIN COUNTY LINE TO LAKE 
WORTH INLET AND FROM SOUTH 
LAKE WORTH INLET TO BROWARD 
COUNTY LINE. 
Location. Palm Beach County is on east coast of 
9-18

JACKSONVILLE, FLA., DISTRICT 
Florida about 300 miles south of Jacksonville and 
70 miles north of Miami. Northerly reach of the 
project is separated from the southerly reach by 
Palm Beach Island. Project consists of about 12.2 
miles of ocean coastline. (See Coast and Geodetic 
Survey Charts 1247 and 1248.) 
Existing project. Provides for Federal participation 
toward the cost of a local shore project for 
restoration of beaches to a general width of 100 
feet with a berm elevation of 10 feet above mean 
low water, and periodic nourishment for 10 years 
from the year of initial nourishment, as follows: 
4.8 percent of the cost for the Martin County line 
-Jupiter Inlet segment; 11.6.percent of cost for 
Jupiter Inlet-Lake Worth Inlet segment; and 5.1 
percent of cost for South Lake Worth Inlet-Boca 
Raton Inlet segment. Mean range of tide is 2.'8 
feet in the Atlantic Ocean at Palm Beach and 2.3 
feet at Boca Raton Inlet. Estimated cost (1965) is 
$343,000 Federal and $4,777,000 non-Federal. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must obtain 
approval by Chief of Engineers of plans and specifications 
prior to commencement of work and furnish 
assurances that they will maintain public 
ownership of publicly owned shores, maintain 
protective measures and provide periodic 
nourishment of protective beaches, and control 
water pollution. 
Operations and results during fiscal year. 
Reimbursement in the amount of $915,859 was 
made to local interests for the Federal portion of 
the initial beach fill at Delray Beach. Engineering 
and design and supervision and administration 
costs were $7,548 and $35, respectively. 
Condition at end of fiscal year. Local interests 
provided initial beach fill at Delray Beach which 
was completed in August 1973. No other construction 
work has commenced on the project. 
34. PINELLAS COUNTY, FLORIDA 
Location. Pinellas County is on the Gulf coast 
of Florida, about midway of the peninsula. It extends 
northerly about 39 miles from the main 
entrance to Tampa Bay to the vicinity of the 
mouth of Anclote River. (See Coast and Geodetic 
Charts Nos. 858 and 1257.) 
Previous project. For details see page 429 of 
Annual Report for 1965. 
Existing project. The authorized project provides 
for Federal participation in preserving and 
protecting the shores of Pinellas County, Florida, 
by: restoration of 5,000 feet of beach at Clearwater 
Beach Island; restoration of 49,000 feet of 
beach at Sand Key; restoration of 9,200 feet of 
beach at Treasure Island; construction of 600 feet 
of revetment at Long Key; and advance nourishment 
of Long Key and periodic nourishment of 
each island. Estimated cost (1975) is $1,630,000 
Federal funds and $7,620,000 non-Federal funds. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must: (a) contribute 
in cash the required percentages of the 
first costs of work provided by the Corps of Engineers, 
the percentages varying with the type of 
beach ownership; 94.1 to 50 percent of the beach 
restoration at Clearwater Beach; 98.1 to 50 percent 
of the improvement at Sand Key; 94.3 to 50 
percent of the improvement at Treasure Island; 
and 50 percent of the first cost of the revetment 
at Long Key; (b) contribute in cash an amount 
computed in accordance with the cost sharing 
provision contained in P.L. 826, 84th Congress, as 
amended by P.L. 87-874, for beach nourishment 
cost for the first 10 years of the project life; (c) 
provide lands, easements, and rights-of-way; (d) 
assure maintenance and repair of the stone revetment 
.on Long Key; (e) assure periodic nourishment 
of the restored beaches; (f) assure public 
ownership of beaches; (g) assure against water 
pollution; (h) hold the United States free from 
damages; and (i) provide beach for public use. 
Non-Federal contribution is estimated at 
$7,620,000. Assurances of local cooperation were 
accepted March 22, 1967. 
Operations and results during fiscal year. New 
work: Planning on the project continued. Engineering 
and design.and supervision and administration 
costs were $36,546 and $436, respectively. 
Conditions at end of fiscal year. Construction 
eg9 pr ,ommenced ii, n1g969 and is 26 percent 
completed. Total costs under existing project 
through June 30, 1975, were $417,318 Federal 
funds and $417,318 contributed funds, all for new 
work. 
35. VIRGINIA KEY AND KEY 
BISCAYNE, FLA. 
Location. The project is located on islands off 
the southeast coast of Miami, Florida, bordered 
on the east by the Atlantic Ocean and on the west 
by Biscayne Bay. The shoreline covered by the 
project is about 3.7 miles long. (See Coast and 
Geodetic Survey Chart No. 1248.) 
Existing project. The authorized project provides 
for Federal participation of 70 percent of 
the cost of periodic nourishment of 1.8 miles of 
beach on Virginia Key and 1.9 miles of beach on 
Key Biscayne for an initial period of 10 years, and 
70 percent of the initial cost of three groins on 
Virginia Key and one groin on Key Biscayne, construction 
of which is subject to future determination 
of their need. Mean range of tide in the 
Atlantic Ocean at Miami Beach is 2.5 feet. Estimated 
cost (1975) is $3,120,000 Federal funds and 
$1,330,000 non-Federal funds. (See Table 9-B for 
9-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Authorizing Legislation.) 
Local cooperation. Local interests must (a) contribute 
in cash 30 percent of the periodic nourishment 
costs for the first 10 years of project life and 
30 percent of deferred construction costs of 
groins; (b) control water pollution; (c) maintain 
continued public ownership of the shore; (d) provide 
lands and rights-of-way; (e) hold the United 
States free from damages; (f) provide a beach zone 
prohibiting permanent human habitation; (g) provide 
recreational beaches; (h) satisfy adequate 
criteria for conservation and development of 
natural resources of the environment; (i) extend 
said area landward a sufficient distance to include, 
where appropriate, protective dunes, 
bluffs, or other natural features which serve to 
protect the uplands from damage; (j) provide full 
park facilities; (k) the above items shall meet with 
the approval of the Chief of Engineers; and (1) 
should groins be constructed, local interests must 
meet conditions a through e above, maintain 
groins, and provide related beach nourishment as 
may be necessary. Basic and supplemental assurances 
of local cooperation were accepted June 7, 
1965, and May 15, 1967, respectively. 
Operations and results during fiscal year. New 
work: Contract payment in connection with recently 
completed beach nourishment and groin 
work at Virginia Key, included with contract for 
dredging Miami Harbor entrance channel and 
turning basin, amounted to $115,073. Engineering 
and design and supervision and administration 
costs were $7,409 and $22,490, respectively. 
Condition at end of fiscal year. Construction 
of the project commenced January 9, 1969. 
Project is 47 percent completed. 
36. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 9-K.) 
37. BEACH EROSION CONTROL 
ACTIVITIES UNDER SPECIAL 
AUTHORIZATION 
(See Table 9-L.) 
Flood Control 
38. CENTRAL AND SOUTHERN 
FLORIDA 
Location. The project is located generally 
within the southeastern eighteen counties of 
Florida covering an area of about 15,200 square 
miles. It is comprised of the Upper St. Johns 
River basin in the northeastern section of project, 
Kissimmee River basin in central section above 
the Lake Okeechobee-Everglades area in the central 
and southwestern section, and the east coast 
Everglades area in southeastern section. 
Previous projects. Completed works for control 
of Lake Okeechobee were included in and constructed 
under the navigation project for 
Okeechobee Waterway, Fla. (formerly Caloosahatchee 
River and Lake Okeechobee drainage 
area, Fla.), and under provisions of River and Harbor 
Acts of July 3, 1930, and August 30, 1935. For 
further information, see Annual Reports, 1948 
and 1949. 
Existing project. The authorized project is for 
flood relief and water conservation and provides 
principally for: an east coast protective levee 
extending from the Homestead area north to the 
eastern shore of Lake Okeechobee near the St. 
Lucie Canal; three conservation areas for water 
impoundment in the Everglades area west of the 
east coast protective levee with control structures 
to effect transfer of water as necessary; 
local protective works along the lower east 
coast; encirclement of the Lake Okeechobee 
agricultural area by levees and canals; enlargement 
of portions of Miami, North New River, 
Hillsboro, and West Palm Beach Canals; enlargement 
of the existing Lake Okeechobee levees and 
construction of new levees on the northeast and 
northwest shore of the lake; increased outlet 
capacity for improved control of Lake Okeechobee; 
floodway channels in the Kissimmee 
River basin, with suitable control structures to 
prevent overdrainage; an interrelated system of 
canals, levees, pumping stations, and structures 
in southwest Dade County to control water 
levels; and facilities for regulating floods in the 
Upper St. Johns River basin; a system of canals 
and control structures for gravity drainage of 
Martin County and distribution of available 
water supplies to portions of Martin and St. Lucie 
Counties; and works to improve the supply, distribution, 
and conservation of water resources in 
central and southern Florida, including the Lake 
Okeechobee agricultural area, Everglades National 
Park, and other related areas. The project 
will provide water control and protection from 
recurrence of the devastating floodwaters from 
the Everglades and local sources, for the highly 
developed urban area along the lower east coast 
of Florida and for the productive agricultural 
areas around Lake Okeechobee (including towns 
around lake), in the Upper St. Johns and Kissimmee 
River basins, and in South Dade County. 
Project also provides for navigation improvements 
suitable for recreational craft, consisting 
of locks and channel dredging in the upper Kissimmee 
and St. Johns River basins. 
The project includes a total of 917 miles of 
levees, 950 miles of canals, 30 pumping plants, 
192 floodway control and diversion structures, 
9-20

JACKSONVILLE, FLA., DISTRICT 
57 railroad bridge relocations, and 2 highway 
bridge relocations. 
The project also provides that upon completion, 
local interests assume operation and maintenance 
of all completed works except levees, 
channels, locks, and control works for regulation 
of Lake Okeechobee and the main control structures 
of conservation areas, which will be operated 
and maintained by the United States. 
The principal features of the hurricane gates, 
constructed under previous projects for Okeechobee 
Waterway and maintained under existing 
project since July 1, 1950, are set forth in Table 
9-M. See also Table 9-N for principal features of 
locks and dams. 
Estimate of cost for new work (1975) is 
$543,000,000 Federal funds and $130,000,000 
contributed funds, exclusive of river and harbor 
funds expended on previous projects. Local 
interests' costs in reviewing plans and specifications 
are expected to be $460,000. In addition, 
estimated cost to local interests of lands, rightsof-
way, and relocations is $110,500,000. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. (See Table 9-0 for local cash 
contribution.) Local interests must also: provide 
lands, rights-of-way, and spoil disposal areas; hold 
the United States free from damages; bear the 
cost of maintenance and operation of all works 
except those having to do with regulation of Lake 
Okeechobee and the main control structures of 
conservation areas; construct and maintain lateral 
drainage facilities; prohibit encroachment on 
flood-carrying capacity of the improved channels; 
and assume cost of construction of all new highway 
bridges, relocations of existing bridges, and 
alterations to utilities incident to construction of 
the project. In addition, for small boat navigation 
channels, local interests must provide, maintain, 
and operate adequate public landings, sanitary 
and access facilities, and establish regulations 
prohibiting discharge of pollutants into the 
waters of the locks and channels by users thereof. 
Assurances of local cooperation have been 
accepted by the District Engineer for all items of 
work authorized to date except those for the 
Small Boat Navigation feature added in 1970 
under Section 201 of the Flood Control Act of 
1965. 
Total estimated contributed funds amount to 
$130,000,000. 
Operations and results during fiscal year. (See 
Table 9-P for work accomplished.) 
Operating and care. a. Features completed 
under previous navigation project for Okeechobee 
Waterway and being maintained under this 
project are: a levee about 70 miles long following 
in general the south shore of Lake Okeechobee 
and a north shore levee 15.8 miles long; spillways 
at Ortona and St. Lucie locks; 5 hurricane gates; 
20 gated drainage culverts through the levee; and 
16 spillways along St. Lucie Canal. 
b. Features completed under existing project 
that are to be maintained with operation; and 
maintenance funds are: (1) Levees 47, 48, 49, and 
50-total length 63 miles and enlargement of 
existing levees L-D1, L-D2, L-D3, L-D4, and L-D9, 
(2) spillway structures S-10, S-11, S-12, S-18C, S-77, 
and S-78, (3) C-43, Sec. 4 (Caloosahatchee River), 
and (4) W. P. Franklin Lock and Dam. 
In addition to the actual facilities listed above it 
is necessary under Operation and Maintenance to 
continue meteorological studies, water level 
records, stream gaging stations, etc., for proper 
regulation of the level of Lake Okeechobee and 
storage of water in Conservation Areas 1, 2, and 3. 
Regulation. 
(A) General Fiscal Year 1975 started as a 
severe drought was ending in South Florida. 
Heavy rains began in the last week of June 1974 
and continued through August causing a complete 
turn about in the hydrologic conditions in 
the lower half of the state. The south Florida area 
went from a condition of drought to that of an 
over abundance of water in a six-week period. 
Lake Okeechobee rose from an elevation of 11.1 
feet on June 23 to 15.4 on August 7 and remained 
above schedule for three months despite regulatory 
discharges to Caloosahatchee River and St. 
Lucie Canal. The Caloosahatchee outlet was 
opened from July 23 to September 15, releasing 
712,039 acre-feet to the Gulf. St. Lucie outlet was 
open from July 30 until August 21 discharging an 
additional 246,564 acre-feet to the east coast. The 
combine regulatory discharge, including flow to 
the south through the agriculture canal, was 
1,099,000 acre-feet. Water deliveries to Everglades 
National Park from July through September 
was four times the minimum required for 
water supply. The total delivery for the year was 
477,200 acre-feet. Then as rapidly as the rains 
began in June they stopped in September. Water 
levels began a steady decline that was not reversed 
until mid-May 1975. Over south Florida, 
the January through April rainfall was less than 
25 percent of normal. However, owing to the preceding 
wet summer and fall, the spring dry conditions 
were not nearly as severe as those experienced 
in 1973 and 1974. 
(B) Corps of Engineers. 
(1) Lake Okee.chobee. The water level in Lake 
Okeechobee began a four-foot rise in the last 
week of June which continued through July. The 
lake was above regulation schedule from July 23 
to September 15 thus requiring releases for Flood 
Control. At the beginning of the fiscal year the 
9-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
lake was at elevation 12.23 feet m.s.l., about one 
foot below normal. From there it continued rising 
to a yearly high of 15.60 feet m.s.l., on October 1, 
slightly above schedule but about 1.3 feet above 
the normal stage for that date. From this high the 
stage receded from lack of rainfall and reached a 
yearly low of 11.71 feet m.s.l., on May 14, 1975. 
This was 2.8 feet below the regulation schedule 
and 1.5 feet below normal. During June, the lake 
began rising again and reached elevation 12.44 
feet by the end of this fiscal year. See Table 9-Q' 
for more statistical information on Lake Okeechobee 
water supply and water use data. 
(2) Water Conservation Area No. 1. Regulatory 
releases totaling 266,000 acre-feet were made 
from this area to Water Conservation Area 2A 
during the period July through September. 
Water levels were above schedule from July 1 to 
October 12, 1974 but fell to 2.5 feet below schedule 
by May 1975. Rainfall was 8.94 inches below normal 
for the seven month period October 1974 through 
April 1975. Rainfall for the fiscal year totaled 40.93 
inches which is 5.55 inches below normal. See ' 
Table 9-R for more statistical information on the 
areas water supply and water use data. 
(3) Water Conservation Area 2A. The water 
level in conservation area 2A rose from 11.40 feet 
at the beginning of the fiscal year to a peak of 
14.20 on August 28, 1974. Water levels were 
above regulation stages from July 20 to September 
8, 1974 requiring regulatory releases totaling 
378,000 acre-feet; (299,400 acre-feet through S-11). 
By the end of September 1974 the water level 
began receding and reached a low for the year of 
10.65 on May 6, 1975. See Table 9-R for more 
statistical information on the area's water supply 
and water use data. 
(4) Water Conservation Area No. 3A. This area 
was above its seasonal regulation schedule from 
August 17 to September 15, 1974. At the beginning 
of FY-75 the stage read 8.50 feet m.s.l., 
about a foot below schedule. It began rising in 
late May 1974 reaching a high of 10.60 on September 
9, 1974 then slowly receded to about 7.00 feet 
m.s.l., in May of 1975. It ended the fiscal year 
where it began, at elevation 8.50 feet m.s.l. 
A total of 477,200 acre-feet was released from the 
pool through S-12 to Everglades National Park. 
This was nearly twice the minimum deliveries as 
outlined under PL-91-282. Rainfall for the area, 
September 1974 through April 1975 was 10.18 
inches below normal. See Table 9-R for more 
statistical information on this area's water supply 
and water use data. 
(C) Central and Southern Florida Flood Control 
District. Project canals, structures, and pumping 
stations were operated by the Flood Control District 
in accordance with design criteria to supply 
irrigation water to the agricultural areas, maintain 
desirable canal levels, and prevent salinity 
problems in coastal areas. During the fiscal year 
about 1,484,000 acre-feet of water were pumped 
by the Flood Control District as follows: 266,000 
acre-feet to Lake Okeechobee; 515,200 acre-feet 
to Water Conservation Area No. 1; 176,900 acrefeet 
to Water Conservation Area No. 2A; 525,360 
acre-feet to Water Conservation Area 3A. In 
addition 395,600 acre-feet were discharged by 
gravity flow to Water Conservation Areas 2A 
and 3A, via pumping station gravity spillways. 
During the fiscal year the Flood Control District 
released 1,090,000 acre-feet of water from 
Lake Okeechobee via the agricultural canals for 
irrigation and to hold optimum levels in the 
agricultural canals. From March through June, a 
total of 120,270 acre-feet of water transferred 
from Lake Okeechobee to Water Conservation 
Areas 2A and 3A to maintain floor levels in the 
Conservation Area canals and for release to the 
east coast and the Everglades National Park. 
Condition at end of fiscal year. The project was 
about 39 percent complete. Planning for the 
entire project began in November 1948 and has 
been continued. For construction completed prior 
to Fiscal Year 1975, see Annual Reports for 1960- 
1974. All Federally maintained features of the 
project were generally in good condition at the 
end of the fiscal year. (For status of work under 
contract at end of fiscal year see Table 9-S.) 
Total Federal costs under the existing project 
through June 30, 1975, were $210,709,729 for new 
work, $12,690,880 for maintenance, a total of 
$223,400,609. In addition, $39,632,287 has been 
expended from contributed funds for new work. 
39. FOUR RIVER BASINS, FLA. 
Location. The Four River Basins area covers 
about 6,000 square miles within 14 counties in 
central and southwest peninsular Florida. Project 
includes all or part of the four main stream basins 
- the Hillsborough, Oklawaha, Withlacoochee, 
and Peace Rivers-and all of three smaller 
coastal basins north of Tampa, Florida, drained 
by the Pithlachascotee and Anclote Rivers and 
Lake Tarpon. 
Existing project. The authorized project provides 
for improvements for control of floods and 
drainage, and for water conservation through 
construction of necessary canals, levees, reservoirs, 
and control structures. More specifically, 
the project provides for: Green Swamp Area-a 
conservation area and three storage reservoirs 
with necessary canals and control structures; 
Hillsborough River-four flood-storage reservoirs, 
with necessary channels, control structures, 
and levees; Oklawaha River-a levee on 
the north shore of Lake Apopka, improvement of 
9-22

JACKSONVILLE, FLA., DISTRICT 
part of the river channel and a west bank levee 
below Moss Bluff lock and dam, and replacement 
of the lock and dam; Withlacoochee River-one 
flood-storage reservoir with outlet canals and 
control structures; Peace River-Peace Creek 
canal and control structures and improvements 
to the existing water control and drainage 
features; Gulf Coastal Areas -Lake Tarpon: outlet 
canal and control structure; Anclote River: 
control structure and channel improvement; 
Pithlachascotee River: reservoir with outlet 
canals and control structures. (See Table 9-T on 
Moss Bluff Lock.) 
Estimated cost for new work (1975) is 
$128,000,000 Federal funds and $70,300,000 contributed 
cost ($23,800,000 contributed funds; 
$29,650,000 for lands and damages; and $16,850,000 
for relocations). (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must furnish 
all lands, and rights-of-way; provide all alterations 
or replacements of public and private utilities, 
roads, bridges (except railroad bridges), etc; 
hold the United States free from damages; operate 
and maintain all project works after completion; 
construct and maintain such associated 
works as are necessary to realize benefits made 
available by the project works; and contribute in 
cash 17 percent of the first cost of construction 
($23,800,000). 
Operations and results during fiscal year. 
New work: Construction of Canal 231, Phases I 
and II and construction of Seaboard Coast Line 
Railroad Bridge B-196 and Section 3A of Tampa 
Bypass Canal was completed in April 1975. Contract 
costs were $512,307 and $452,118, respectively. 
Construction of C-135 Section 3B commenced 
April 14, 1975 and construction of S-162 commenced 
May 12, 1975. Contract costs were 
$451,863 and $55,250, respectively. 
Contract costs for obstruction removal was 
$74,650. 
Costs of dredging under bridges covered under 
contract with the State of Florida were $93,832. 
Costs relative to recently completed contract 
for modifying culvert slide gate at Moss Bluff 
Lock were $51,244. 
Contract for construction of S-161 and C-136 
was awarded June 26, 1975, however construction 
has not started. 
Engineering and design and supervision and 
administration costs were $963,115 and $122,765 
respectively. 
Hired labor surveys, inspections, and reports 
cost $20,904. 
Condition at end of fiscal year. Construction 
of the project commenced April 18, 1966, and is 
21 percent complete. See Table 9-U for construction 
of major features of the project completed to 
date. 
40. PORTUGUES AND BUCANA 
RIVERS, P.R. 
(This project authorized as Lago de Cerrillos, 
Lago de Portugues, and Channel Improvement at 
Ponce) 
Location. Portugues and Bucana Rivers originate 
on the southern slopes of Cordillera Central 
divide of Puerto Rico and flow from this central 
ridge of the island to the Caribbean Sea. Their 
drainage areas are 22.6 and 31.4 square miles, 
respectively. Ponce, the second largest city in 
Puerto Rico, is located in the lower coastal area 
along Portugues River and is the only urban 
community in the two basins. 
Existing project. The authorized project provides 
for two multiple-purpose reservoirs for 
flood control, water supply, general recreation, 
and fish and wildlife enhancement - one on 
Portugues River and the other on Cerrillos River, 
a tributary to the Bucana River; enlargement of 
about 5.7 miles of the Bucana River, with an 
additional 0.2-mile tieback levee at the upstream 
terminus of the improvement; enlargement of 
2.1 miles of the Portugues River, with an additional 
0.5 mile of tieback levee at the upstream 
terminus of the improvement; and a 1.3 mile division 
channel connecting Portugues River to lower 
Bucana River. Estimated cost of the project (1975) 
is $113,000,000 Federal cost and $29,400,000 non- 
Federal cost ($20,556,000 for lands and damages; 
$3,144,000 for relocations; and $5,700,000 for highway 
bridges). (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must provide 
all lands, easements, and rights-of-way; hold 
the United States free from damages; operate 
and maintain all project works after completion; 
repay construction cost allocated to water supply 
in accordance with Water Supply Act of 1958; pay 
one-half of the separable cost allocated to recreation 
and fish and wildlife enhancement; prohibit 
discharge of inadequately treated sewage and 
other pollutants into the reservoir; and prevent 
encroachment on downstream channels. Assurances 
of local cooperation have not been accepted. 
Operations and results during fiscal year. New 
work: Planning on the project continued. Engineering 
and design and supervision and administration 
costs were $129,000 and $9,977, respectively. 
Hired labor surveys, inspections, and reports 
cost $557. 
9-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Condition at end of fiscal year. Construction 
of the project commenced in September 1975. 
41. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The following features transferred to the Central 
and Southern Florida Flood Control District 
and the Southwest Florida Water Management 
District were inspected quarterly during the year 
at a total cost of $6,000: 14 pumping stations, 
approximately 123 control structures, approximately 
690 miles of canals, approximately 750 
miles of levees, and improvements of Arch Creek, 
including control structure. 
42. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 9-V.) 
43. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood Control Activities Pursuant to Section 
205, Public Law 685, 84th Congress, as amended 
(Preauthorization) 
(See Table 9-W.) 
Emergency Flood Control Activities--repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress and antecedent legislation) 
Federal costs for Fiscal Year 1975 were $48,167 
for Advance Preparation for Flood Emergencies. 
General Investigations 
44. SURVEYS 
Hired labor costs during the fiscal year (all 
Federal funds) were: navigation studies, $59,912; 
flood control studies, $118,142; beach erosion 
studies, $258,786; and special studies, $1,903,425, 
for a total of $2,340,265. 
45. COLLECTION AND STUDY OF 
BASIC DATA 
Hired labor costs for flood plain management 
services incurred during the fiscal year were: 
Flood Plain Management Services (Jacksonville 
District) $60,040; Flood Plain Management Services 
(Technical) $44,759; Espiritu Santo Rio, P.R., 
$37,655; Moultrie, Georgia, Okapilco, $22,000; 
NW Putnam and SW Clay Counties, $24,000; Rio 
Grande de Loiza, P.R., $15,701; Rutland, Dunnellon, 
and Withlacoochee Rivers, $16,000; Sumter 
Co., Withlacoochee River, $24; Virgin Islands 
Tidal Areas, $15,000. (See Table 9-X for Flood 
Plain Management Services Completed this fiscal 
year.) 
9-24

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Aquatic Plant New Work: 
Control (R&H Approp. 
Act of 1965) Cost 
(Federal Funds) 
(Contrib. Funds) New Work: 
Approp. 
Cost 
2. Arecibo Harbor, New Work: 
P.R. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
3. Atlantic Intra- New Work: 
coastal Waterway Approp. 
between Norfolk, Cost 
Virginia and St. Maint: 
Johns River, Fla. Approp. 
(Federal Funds) Cost 
4. Canaveral Har- New Work: 
bor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
5. Charlotte Har- New Work: 
bor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
6. Cross-Florida New Work: 
Barge Canal Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
7. Fernandina Har- New Work: 
bor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
8. Fort Myers New Work: 
Beach, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
9. Fort Pierce New Work: 
Harbor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
10. Intracoastal New Work: 
Waterway Approp. 
Caloosahatchee Cost 
River to Anclote Maint: 
River, Fla. Approp. 
(Federal Funds) Cost 
11. Intracoastal New Work: 
Waterway, Approp. 
Jacksonville to Cost 
Miami, Fla. 
(Federal Funds) 
146,000 
203,685 
74,927 
74,927 
1,644 
1,644 
1,970 
1,970 
95,600 
229,765 
1,395,263 
892,285 
5,112 
5,122 
4,073,900 
4,382,595 
585,740 
562,190 
9,737 
9,832 
10,178 
102,003 
11,772 
- 1,127 
38,605 
34,949 
3,000 
1,258 
46,366 
46,366 
163,500 
143,647 
66,410 
66,410 
342,639 
309,365 
141,000 
141,000 
66,600 
66,600 
1,631 
1,631 
18,878 
823,381 
1,322,800 
14,295 
14,295 
888,966 
523,471 
471,342 
250,050 
249,930 
41,536 
416 
87,294 
439,018 
32,830 
44,873 
44,873 
6,284 
6,284 
125,000 
15,577 
843,509 
843,574 
380,047 
380,047 
910,000 
1,253,191 
656,159 
673,868 
131,686 
131,806 
-1,400 
5,942 
3,353 
150,975 
492,798 
3,000 
6,285 
301,000 
140,012 
381,900 2,211,166 
446,857 2,211,127 
158,729 842,7671 
158,729 842,7671 
- 1,128,0752 
- 1,128,0752 
351,521 876,431 
351,521 876,431 
- 361,2258 
- 361,225' 
8,335 1,015,178 
8,335 1,015,178 
-143,000 7,341,910' 
470,528 7,341,910' 
2,046,400 8,993,104 
2,049,629 8,992,440 
- 533,1695 
- 533,1695 
230,000 2,549,386 
230,000 2,549,386 
- 61,759,048 
425,573 61,176,578 
791,000 4,512,298 
863,646 4,501,355 
- 3,288,816 
- 3,288,816 
387,165 2,977,178 
387,165 2,977,178 
- 6,500 158,1406 
119 154,6986 
4,862 170,566 
4,862 170,566 
- 356,056 
- 356,056 
- 33,941 1,709,125 
34,080 1,709,125 
- 18,574 
- 18,574 
- 8,111,9577 
1,021 8,071,7527 
- 40,000 1,705,135' 
120,577 1,704,724' 
- 19,248,598 
- 19,248,598 
9-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30,1975 
11. (cont.) Maint: 
Approp. 
Cost 
12. Jacksonville New Work: 
Harbor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
13. Mayaguez New Work: 
Harbor, P.R. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
14. Miami Harbor, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
15. New Pass, New Work: 
Sarasota, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
16. Okeechobee New Work: 
Waterway, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
17. Oklawaha New Work: 
River, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
18. Palm Beach Har- New Work: 
bor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
19. Ponce de Leon New Work: 
Inlet, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
607,054 
258,150 
5,281,100 
5,864,400 
1,084,520 
662,840 
26,238 
152,065 
2,610 
4,641 
258,600 
75,870 
2,082 
2,082 
346,498 
1,254 
166,127 
245,077 
612,400 
634,514 
3,700 
2,044 
19,760 
20,820 
188,753 
194,390 
287,110 
169,910 
50,000 
207,373 
610,803 
615,202 
5,600,000 
4,349,584 
737,307 
1,138,009 
221,155 
110,559 
2,950,000 
1,403,547 
2,244 
2,244 
144,041 
13,089 
11,146 
196,000 
151,796 
756,865 
540,683 
116 
414,450 
263,899 
8,899 
9,386 
99,298 
235,000 
234,704 
59,800 
120,523 
593,353 
1,019,784 
3,000,000 
2,081,893 
1,248,272 
1,244,039 
54,159 
73,900 
73,900 
6,278,000 
5,874,632 
4,280 
4,280 
514,559 
525,097 
535,104 
517,332 
35,992 
440,410 
694,900 
-9 
15,331 
138,081 
256,708 
215,143 
9,712 
747,864 
301,660 
11,822 
583,000 11,629,32810 
407,224 11,453,55210 
4,738,000 38,177,39111 
2,633,310 33,896,50811 
1,458,300 24,457,5901" 
1,178,578 24,043,64012 
- 102,813 
- 102,813 
193,500 638,693 
65,454 454,141 
- 168,187 
- 168,187 
95,194 440,169 
95,194 440,169 
4,770,000 24,043,213'" 
$4,841,355 21,980,5881 
- 2,077,001 
- 2,077,001 
428,803 1,956,246" 
431,799 1,768,577" 
- 45,81115 
- 45,81115 
4,998 566,136 
24,713 566,136 
-63,000 20,643,41918 
46,733 20,642,38216 
608,000 14,911,25217 
623,225 14,907,099 
- 503,700 
126 502,277 
- 315,26418 
- 315,26418 
157,200 1,788,51819 
155,899 1,759,18919 
- 6,904,031"20 
- 6,904,03120 
84,500 2,184,386"1 
80,463 2,133,938" 
-31,122 1,953,277 
9 1,953,277 
790,500 1,773,364 
1,237,000 1,773,364 
- 2,415,600 
-9 2,877,883 
9-26

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
Ponce de Leon Maint: 
Inlet, Fla. Approp. 
(Contrib. Funds) Cost 
20. Ponce Har- New Work: 
bor, Puerto Rico Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
21. Removing Water Maint: 
Hyacinth Approp. 
(Federal Funds) Cost 
22. St, Augustine New Work: 
Harbor, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
23. St. Lucie New Work: 
Inlet, Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
24. San Juan New Work: 
Harbor, P.R. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
25. Tampa Harbor, New Work: 
Fla. (Main Approp. 
Project) Cost 
(Federal Funds) Maint: 
Approp. 
Cost 
(Contrib. Funds! New Work: 
Approp. 
Cost 
29. Brevard County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
30. Broward County, New Work: 
Fla., Beach Erosion Approp. 
Control and Hills- Cost 
boro Inlet, Fla., Maint: 
Navigation Project Approp. 
(Federal Funds) ost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
31. Dade County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
32. Duval County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
- 1,379,000 1,379,000 
- - - 
223,120 
11,610 
352,200 
377,078 
52,804 
52,845 
3,118 
3,118 
198,600 
49,720 
1,713,223 
699,696 
69,500 
17,955 
993,100 
311,220 
19,471 
230,981 
436,500 
404,430 
4,612 
4,612 
59,331 
59,331 
763,905 
30,105 
298,000 
310,622 
427,300 
1,450,427 
2,000 
59,727 
1,705 
2,500 
1,786 
266,000 
265,909 
335,000 
353,534 
234,700 
234,700 
90,314 
90,314 
261,538 
383,179 
586,000 
624,041 
446,294 
446,294 
399,992 
115,915 
626,000 
104,400 
-100,000 
571,596 
-714 
22 
- 187,882 
- 187,882" 
307,928 937,368 
308,019 937,368 
560,000 4,856,370 
554,388 4,836,560 
- 1,476,434" 
- 1,476,434" 
560,000 1,172,115 
560,000 1,172,115 
- 123,60224 
- 123,60224 
407,806 1,074,383 
407,806 1,074,383 
75,000 75,000 
- 13,774,968" 
- 13,774,968" 
,093,800 5,825,556" 
,318,743 5,438,340" 
250,000 27,374,803" 
254,975 27,281,561" 
133,488 8,835,109" 
133,488 8,835,109" 
44,563 
903 
271,162 
202,600 
8,129 
1,758,841 
1,758,841 
150,000 
131,589 
120,000 
108,160 
200,000 
173,541 
130,000 
84,496 
58,502 
14,842 
521,492 
506,826 
626,000 
307,000 
893,100 
892,650 
1,786 
1,786 
1,758,8411 
1,758,8411 
350,000 
305,130 
250,000 
192,656 
9-27

TABLE 9-A (Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
33. Palm Beach New Work: 
County, Fla. from Approp. 
Martin County line Cost 
to Lake Worth 
Inlet to Broward 
County line 
(Federal Funds) 
34. Pinellas County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
(Contrib. Funds) New Work: 
35. Virginia Key and 
Key Biscayne, Fla. 
(Federal Funds) 
(Contrib. Funds) 
38. Central and 
Southern Florida 
(Federal Funds) 
(Contrib. Funds) 
39. Four River 
Basins, Fla. 
(Federal Funds) 
(Contrib. Funds) 
40. Portugues and 
Bucana Rivers, 
P.R. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
940,834 
923,442 
99,300 
21,000 
138,800 
34,739 
246,900 
36,041 
258,000 
15,516 
8,599,200 
8,702,561 
1,022,700 
1,084,257 
1,704,819 
1,423,205 
3,257,300 
5,043,866 
708,042 
919,626 
397,200 
282,170 
-16,000 
87,919 
88,067 
681,500 
130,238 
117,000 
55,739 
6,305,000 
4,092,292 
1,427,500 
1,107,653 
781,710 
532,757 
216,000 
13,739 
15,000 
13,739 
235,000 
791,777 
124,800 
339,333 
2,600,000 
4,127,977 
1,560,000 
1,762,027 
814,350 
699,984 
154,166 
18,592 
289,000 
18,390 
940,834 
923,442 
769,693 
417,455 
705,183 
417,318 
- 1,567,353 
101,475 1,463,484 
- 672,922 
43,497 627,207 
5,072,200 
7,341,073 
2,417,000 
2,139,159 
774,710 
1,566,244 
6,239,000 2,286,000 2,562,800 
2,782,063 2,970,471 2,502,881 
1,279,570 - 2,285,610 
406,341 516,781 295,167 
420,000 92,368 1,285,000 
516,904 104,337 139,534 
211,075,397" 
210,709,729" 
13,101,861 
12,690,888 
39,756,205 
39,632,287 
30,171,300 
27,094,389 
6,746,772 
4,386,785 
2,194,568 
1,042,945 
1. Work-in-kind. 
2. Excludes $288,000 contributed funds for new work. 
3. Includes $97,566 for previous project. 
4. Excludes $700,000 contributed by NASA in connection 
with construction of lock and $1,003,000 contributed funds for 
new work. 
5. Includes $113,000 for new work on previous project; 
excludes $15,563 expended for new work on existing project 
from contributed funds. 
6. Includes $10,128 cost for reconnaissance and detailed 
project reports prepared under Section 107 modification to the 
project. Excludes $1,095 contributed funds for new work. 
7. Includes $515,479 for new work for previous projects; 
$8,472 for new work on Sunshine Skyway Channel; and $9,707 
for new work for Cats Point Channel. Excludes $14,473 contributed 
funds for new work. 
8. Includes $450,749 for maintenance for previous project. 
9. Includes $94,776 for work for previous projects. 
10. Includes $213,222 for maintenance on previous projects 
and $3,179 operating and care under provisions of permanent 
indefinite appropriation. 
11. Includes $3,520,137 new work on previous project and 
$290,013 for new work expended from public works funds. 
12. Includes $543,399 maintenance on previous projects. 
13. Includes $2,202,126 expended from public works funds 
for new work. 
14. Includes $343,497 work-in-kind. 
15. Excludes $45,811 contributed funds for new work. 
16. Includes $16,222,275 for new work under previous project, 
$335,147 for recreational facilities (Code 710), and $27,574 
for reconnaissance and detailed project report prepared under 
Section 107 modification to the project. 
17. Includes $7,581,150 for maintenance for previous projects. 
Excludes $1,000 for maintenance from contributed funds 
on previous projects and $67,558 which represents services 
rendered without reimbursement. 
18. Includes $3,912 for new work for previous projects. 
19. Includes $11,414 for operating and care under provisions 
of the permanent indefinite appropriation. 
20. Includes $80,000 new work from public works funds. 
Excludes $509,506 contributed funds. 
21. Includes $30,000 for maintenance from public works 
funds. 
22. Includes $11,588 expended for restudy but excludes 
$21,960 expended for new work from contributed funds. 
23. Includes $71,303 for new work on previous project. 
Excludes $137,500 contributed funds. 
24. Includes $26,689 for new work under previous project. 
25. Includes $747,684 for new work under previous project. 
Excludes $100,000 expended for new work from contributed 
funds. 
26. Includes $44,730 for maintenance under previous project.
27. Includes $853,050 for new work under previous project. 
Excludes $270,466 for new work for Hillsborough River and 
$13,939 for new work from contributed funds. 
28. Includes $17,107 for maintenance under previous project.
29. Excludes $15,543 for property received without reimbursement 
and R&H Funds expended on previous projects (see 
cost and financial statement for Okeechobee Waterway, Fla., 
project for these costs). Excludes $100,000 advanced by local 
interests toward federal costs. 
9-28

JACKSONVILLE, FLA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
October 27, 1965 
August 26, 1937 
March4, 1913 
June 20, 1939 
March 2,1945 
October 23, 1962 
July 25, 1912 
March 3, 1925 
July 3, 1930 
August 26, 193 
May 17, 1950 
P.L. 675/77, 
July 23, 1942 
June 14, 1880 
July 13, 1892 
March 2, 1907 
June 25, 1910 
March 3, 1925 
June 20, 1938 
March 2, 1945 
May 17, 1950 
July 14, 1960 
Auth. by Chief of 
Engineers 
December 6, 1968, 
under Sec. 107 of 
1960 R&H Act. 
Def. Act of 
March 4, 1931 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and progressive eradication of obnoxious aquatic plants, 
and continued research to develop best method of control 
ARECIBO HARBOR, P.R. (See Section 2 of Text) 
Construction of breakwater 1,200 feet long and dredging 
channel 25 feet deep and 400 feet wide with flare at entrance 
and widening at inner end to form a maneuvering area 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA. AND THE ST. JOHNS RIVER, FLA. 
(See Section 3 of Text) 
Channel 7 x 100 feet 
Channel 12 feet deep and 90-150 feet wide with cut-offs. 
CANAVERAL HARBOR, FLA. (See Section 4 of Text) 
Entrance channel jetties, a turning basin enclosed by a dike, 
and a barge canal with a lock 
Maintain improved channel, turning basin, enlarge barge channel 
and lock, relocate dike, provide channel and turning basin west 
of 35-foot turning basin, construct and operate sand-transfer plant 
CHARLOTTE HARBOR, FLA. (See Section 5 of Text) 
Channel 24 x 300 feet through Gulf through Boca Grande 
entrance 
Depth of 27 feet at entrance and width of 500 feet at 
the bend. 
Channel 10 x 100 feet to Punta Gorda and a turning basin 
Depth of 30 feet at entrance and width of 700 feet at bend 
Depth of 32 feet in entrance channel 
CROSS-FLORIDA BARGE CANAL (See Section 6 of Text) 
Barge Canal 12 x 150 feet 
FERNANDINA HARBOR, FLA. (See Section 7 of Text) 
Entrance jetties 
Raising and extending jetties to provide 19-foot depth 
Improvement of inner harbor to obtain 20- to 24- foot depth 
and 400- to 600-foot channel width 
Combining improvement of Fernandina Harbor and Cumberland 
Sound under the general heading of Fernandina Harbor 
Provided for a 26-foot channel 
Provided for the 28-foot channel and turning basin 
Provided for reducing the maximum width of turning basin 
from 1,000 to 800 feet, for shifting channel line in this 
vicinity 50 feet northwesterly and for including in 
authorized project small area dredged by Rayonier, Inc. 
Provided for 32-foot channel and turning basin 
FORT MYERS BEACH, FLA. (See Section 8 of Text) 
12 x 150-foot channel in San Carlos Bay, thence 11 x 125 feet 
in Matanzas Pass to upper shrimp terminals 
Ex:ension of 11- x 125-foot channel easterly about 2,000 feet 
t, and including a turning basin adjacent to natural deep 
water in Matanzas Pass 
FORIT PIERCE HARBOR, FLA. (See Section 9 of Text) 
Expenditure of $20,000 for dredging channel, maintenance by 
local interests 
H. Doc. 251, 89th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 43, 75th Cong., 1st sess. 
H. Doc. 898, 62d Cong., 
2d sess. 
H. Doc. 618, 75th Cong., 
3d sess. 
H. Doc. 367, 77th Cong., 
1st sess. 
S. Doc. 140, 87th Cong., 
2d sess. 
H. Doc. 699, 62d Cong., 
2d sess. 
H. Doc. 113, 66th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 1, 70th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 95, 74th Cong., 2d sess. 
H. Doc. 186, 81st Cong., 
1st sess. 
H. Doc. 109, 79th Cong., 
1st sess. 
Annual Report 1879 
Annual Report 1891 & 1896 
H. Doc. 388, 59th Cong., 
1st sess. 
H. Doc. 227, 68th Cong., 
1st sess. 
H. Doc. 284, 87th Cong., 
1st sess. 
H. Doc. 284, 87th Cong., 
1st sess. 
H. Doc. 662, 80th Cong., 
2d sess. 
H. Doc. 183, 86th Cong., 
1st sess. 
Specified in Act 
9-29 
TABLE 9-B

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
War Dept. Approp. Act, 
March 4, 1933 
August 30, 1935 
March 2, 1945 
June 30, 1948 
May 17, 1950 
September 3, 1954 
May 10-16, 1957 
Auth. March 1, 1962, 
by Senate and House 
Public Works 
Committees 
Auth. by Chief of 
Engineers 
March 1, 1963, 
under Sec. 107 of 
1960 R&H Act 
Expenditure of up to $30,000 for dredging channel 
Maintaining channels, jetties, and revetments, and enlarging 
channels and turning basin to existing project dimensions 
INTRACOASTAL WATERWAY, CALOOSAHATCHEE RIVER 
TO ANCLOTE RIVER, FLA. (See Section 10 of Text) 
9- x 100-foot channel; deepening channel at Caseys Pass to 9 feet; 
and construction.of highway bridge at Venice 
Original route may be modified at no excess cost to United States 
Any route in Venice-Lemon Bay area may be used 
Use of alternate Route C-1 in Venice-Lemon Bay area 
Local interests to bear costs of Venice Avenue highway bridge and 
any other necessary crossing over Route C-1 
Sunshine Skyway Channel to be improved and maintained to 
9 x 100 feet 
Specified in Act 
H. Doc. 252, 72d Cong., 
1st sess. and Rivers and 
Harbors Committee Doc. 21, 
74th Cong., 1st sess. 
H. Doc. 371, 76th Cong, 
1st sess. 
Specified in Act 
Specified in Act 
Specified in Act 
H. Doc. 109, 85th Cong., 
1st sess. 
6- x 80-foot channel in Boca Ciega Bay 
INTRACOASTAL WATERWAY, JACKSONVILLE TO 
MIAMI, FLA. (See Section 11 of Text) 
January 21, 1927 Channel 8 x 75 feet from Jacksonville to Miami 
July 3, 1930 Channel width of 100 feet 
PARA June 26, 1934 Operation and care of Palm Valley Bridge 
August 26, 1937 Turning basin at Jacksonville Beach 
March 2, 1945 Channel 12 x 125 feet 
Do. Side channel and turning basin at Sebastian 
Do. Turning basin at Vero Beach 
July 3, 1958 Maintenance of side channel at Daytona Beach 
Chief of Engineers Channel 10 x 125 feet from Ft. Pierce to Miami 
Report of July 22, 1960, 
Mod. 12-foot channel 
H. Doc. 586, &9th Cong., 
2d sess. 
S. Doc. 71, 71st Cong., 2d sess. 
Specified in Act 
H. Doc. 180, 75th Cong., 
1st sess. 
H. Doc. 740, 79th Cong., 
2d sess. 
H. Doc. 336, 76th Cong., 
1st sess. 
H. Doc. 261, 76th Cong., 
lstsess. 
H. Dec. 222, 85th Cong., 
1st sess. 
March 2, 1907 
June 14, 1880 
June 3, 1896 
June 25, 1910 
June 5, 1920 
July 3, 1930 
August 30, 1935 
JACKSONVILLE HARBOR, FLA. (See Section 12 of Text) 
ST. JOHNS RIVER, FLA., OPPOSITE THE CITY OF 
JACKSONVILLE 
The 24-foot area from Hogan Creek to Florida East Coast 
Railroad bridge 
ST. JOHNS RIVER, FLA. 
Jetties at entrance (maintenance only) 
Extension of jetties etc. (maintenance only) 
Main channel 30 by 300-600 feet; anchorage basin at Mayport; 
and training walls and revetments 
ST. JOHNS RIVER, FLA., JACKSONVILLE TO THE OCEAN 
Consolidation of above projects 
Widening bend at Dame Point to 900 feet 
Widening Drummond, Trout, and Six Mile (now Long Branch) 
Creeks Cut to 400 feet; and Terminal Channel 30 by 400 feet 
H. Doc. 663, 59th Cong., 
1st sess. 
Annual Report 1879, p. 767 
H. Ex. Doc. 346, 53d Cong., 
3d sess., and Annual Report 
1895, p. 1586 
H. Doc. 611, 61st Cong., 
2d sess. 
Specified in Act 
H. Doc. 483, 70th Cong., 
2d sess. 
S. Comm. print, 74th Cong., 
1st sess. 
9-30

TABLE 9-B (Continued) 
JACKSONVILLE, FLA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts 
March 2, 1945 
Do. 
Do. 
October 27, 1965 
August 30, 1935 
July 3, 1930 
PWA Program 
September 6, 1933 
June 13, 1902 
March 2, 1907 
March 4, 1913 
March 3, 1925 
July 3, 1930 
August 30, 1935 
August 26, 1937 
March 2, 1945 
Do. 
July 14, 1960 
August 13, 1968 
Auth. by Chief of 
Engineers 
August 28, 1963, 
under Sec. 107 of 
1960 R&H Act 
Work Authorized 
Maintenance of existing channel widths; widening Terminal 
Channel to 590 feet; the 28-foot area between Laura St. and 
St. Elmo W. Acosta Bridge; channel along south side of 
Commodore Point; and basin at Naval Reserve Armory 
Main channel 34 feet deep via Terminal Channel 
Dame Point-Fulton Cutoff 34 by 500 feet 
Maintain existing entrance channel depths of 40 an$ 42 feet; 
deepen main ship channel to 38 feet to Mile 20 and widen 
channel near Mile 5 and near Mile 7 
MAYAGUEZ HARBOR, P.R. (See Section 13 of Text) 
Approach channel 30 feet deep to and alo'ng deep water terminal 
MIAMI HARBOR, FLA. (See Section 14 of Text) 
MIAMI RIVER 
The 15-foot channel in Miami River, 150 feet wide at the mouth 
The channel at the Dinner Key Airport 
MIAMI HARBOR 
An 18-foot channel in a landcut across the peninsula and 
construction of the north jetty 
Construction of the south jetty and increase of channel width 
to 100 feet 
Modification of local cooperation requirements imposed by 
the Act of July 25, 1912 
A channel 25 feet deep with present widths from the ocean to 
Biscayne Bay, thence 200 feet wide across the bay to but not 
including the municipal turning basin, and extension of both jetties 
A channel width of 300 feet across the bay and enlarging the 
municipal turning basin, with expenditures thereon limited to 
$200,000 
A depth of 30 feet from the ocean to and in the turning basin, with 
the existing authorized project widths, including the 300-foot 
width in the channel across the bay 
Extending the turning basin 200 feet to the southward 
The Virginia Key improvement 
For incorporation of the project for Miami River in that for 
Miami Harbor, the widening at the mouth of Miami River to 
existing project widths; the channels from the mouth of Miami 
River to the turning basin and to Government Cut; and the 
channel from Miami River to the harbor of refuge, provided 
that local interests contribute one-third of the cost 
Deletion of Virginia Key development and the Dinner Key approach 
channel; widening the existing ship channel by easing the ocean 
bend and increasing the width of the 300-foot-wide section to 
400 feet, enlarging the existing turning basin 300 feet along both 
the south and northeasterly sides, and dredging a turning basin 
along the north side of Fisher Island about 39 acres in extent and 
30 feet in depth 
Enlarging existing entrance channel to 38 x 500 feet, deepening 
existing 400-foot-wide channel across Biscayne Bay to 36 feet; 
deepening existing turning basins at Biscayne Blvd. terminal and 
Fisher Island to 36 feet 
NEW PASS, SARASOTA, FLA. (See Section 15 of Text) 
10- x 150-foot entrance channel; 8-l100-fbot inner'channes; and 
8-foot-deep turning basins at Payne Terminal and City Pier 
H. Doc. 662, 56th Cong., 
1st sess. (Annual Report 
1900, p. 1987) 
Specified in Act 
Specified in Act 
H. Doc. 510, 67th Cong., 
4th sess. 
Rivers and Harbors Committee 
Doc. 15, 71st Cong., 2d sess. 
Sen. Comm. Print, 
73d Cong., 2d sess. 
Rivers and Harbors, Committee 
Doc. 86, 74th Cong., 2d sess. 
S. Doc. 251, 79th Cong., 
2d sess. 
H. Doc. 91, 79th Cong., 
1st sess. 
S. Doc. 71, 85th Cong., 
2d sess. 
S. Doc. 93, 90th Cong., 
2d sess. 
9-31 
Documents 
H. Doc. 322, 77th Cong., 
1st sess. 
S. Doc. 230, 78th Cong., 
2d sess. 
S. Doc. 179, 79th Cong., 
2d sess. 
H. Doc. 214, 89th Cong., 
1st sess. 
H. Doc. 215, 72d Cong., 
1st sess. and Rivers and 
Harbors Committee Doc. 1, 
73d Cong., 1st sess. 
Specified in Act 
S. Doc. 95, 72d Cong., 1st sess. 
and specified in Act

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
PARA June 26, 1934 
August 26, 1937 
March 2, 1945 
Do. 
Auth. by Chief of 
Engineers 
November 5, 1968, 
under Sec. 107 of 
1960 R& H Act 
September 19, 1890 
March 2, 1907 
June 25, 1910 
July 25, 1912 
July 27, 1916 
PARA June 26, 1934 
March 13, 1934 
December 10, 1934 
August 30, 1935 
March 2, 1945 
May 17, 1950 
July 14, 1960 
October 27, 1965 
March 3, 1925 
August 30, 1935 
March 2, 1945 
March 3, 1899 
OKEECHOBEE WATERWAY, FLA. (See Section 16 of Text) 
Operation and care of locks and dams provided for with funds from 
R& H appropriations 
New lock and weir structure in St. Lucie Canal 
Deepening to 8 feet from Ft. Myers to Jacksonville-Miami waterway 
near Stuart via channel across lake from Clewiston 
Channel to yacht basin at Ft. Myers and a basin at Stuart 
Enlarge existing 8- x 90-foot section of Okeechobee Waterway for 
about 5 miles upstream from Ft. Myers to 10 x 100 feet 
OKLAWAHA RIVER, FLA. (See Section 17 of Text) 
Clearing obstructions for channel 4 feet deep from mouth to 
Leesburg 
Channel 6 feet deep from mouth to head of Silver Springs Run 
Maintenance of levels in the lakes at head of river 
Acceptance of certain artificial waterways in lieu of portions of 
natural river bed 
Operation and care of lock and dam provided for with funds from 
appropriations for rivers and harbors 
PALM BEACH HARBOR, FLA. (See Section 18 of Text) 
Maintenance of improvement previously constructed by local 
interests 
Deepening the channels and turning basin, as constructed by local 
interests, to 20 feet 
Authorized the work previously approved by Public Works 
Administration, and widening the channels to existing project 
dimensions, enlarging the 700-foot-square turning basin eastward, 
removing the obstructive point on south side of the inlet, revetting 
the banks of the inlet, and restoring existing jetties. 
Deepening the channels and turning basin to 25 feet 
Extending the turning basin 550 feet southward over a 900-foot 
width, with a flare to the east; provided that local interests may 
be reimbursed not to exceed $305,000 for work done by them on 
this modification subsequent to July 1, 1949 
An entrance channel 35 feet deep, 400 feet wide, and 0.8 mile long, 
merging with an inner channel 33 feet deep, 300 feet wide, and 0.3 
mile long, thence flaring into a turning basin, 1,400 feet north-south 
by a minimum of 1,200 feet east-west. 
PONCE DE LEON INLET, FLA. (See Section 19 of Text) 
Widening and deepening channels; jetties on north and south 
side of inlet; a weir in the north jetty and an impoundment basin 
inside the weir 
PONCE HARBOR, P.R. (See Section 20 of Text) 
Dredging 3 continuous areas, aggregating 153 acres, to depths of 
30, 18, and 9 feet, and construction of a seawall, costs to be shared 
by U.S. and local interests 
Modified conditions of local cooperation to provide that U.S. 
undertake all dredging at Federal expense and return local funds 
previously contributed for dredging, all other portions of the 
improvement hereafter to be at the expense of local interests 
Eliminated previously authorized 9-foot dredging area, and provided 
for dredging 30-foot-depth area of 18 acres off the municipal pier 
and for construction of the breakwater off Punta Carenero 
REMOVING THE WATER HYACINTHS FROM NAVIGABLE 
WATERS IN THE STATE OF FLORIDA (See Section 21 of Text) 
Construction and operation of a suitable vessel and use of log 
Specified in Act 
Rivers and Harbors Committee 
Doc. 28, 75th Cong., 1st sess. 
H. Doc. 696, 76th Cong., 
3d sess. 
H. Doc. 736, 79th Cong., 
2d sess. 
Annual Report 1889, p. 1360 
H. Doc. 782, 59th Cong., 
1st sess. 
Specified in Acts 
Specified in Act 
Specified in Act 
H. Doc. 185, 73d Cong., 
2d sess. 
Recommended by Chief of 
Engineers to Public Works 
Administration 
October 17, 1934 
H. Doc. 185, 73d Cong., 
2d sess. and Rivers and 
Harbors Committee Doc. 42, 
74th Cong., 1st sess. 
H. Doc. 530, 78th Cong., 
2d sess. 
H. Doc. 705, 80th Cong., 
2d sess. 
H. Doc. 283, 86th Cong., 
1st sess. (contains latest 
published map) 
H. Doc. 74, 89th Cong., 
1st sess. 
H. Doc. 532, 67th Cong., 
4th sess. 
Rivers and Harbors Committee 
Doc. 18, 72d Cong., 1st sess. 
H. Doc. 745, 79th Cong., 
2d sess. 
Annual Report 1899 
9-32

TABLE 9-B (Continued) 
JACKSONVILLE, FLA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 13, 1902 
March 3,1905 
June 20, 1938 
May 17, 1950 
March 2, 1945 
November 7, 1966 
H.R. May 9, 1974 
S. R. May 31, 1974 
August 8, 1917 
September 22, 1922 
July 3, 1930 
August 30, 1935 
August 26, 1937 
October 17, 1940 
March 2, 1945 
July 3, 1958 
March 3, 1899 
March 3, 1905 
June 25, 1910 
August 8, 1917 
booms for removal of water hyacinths in the navigable waters of 
the State 
Extermination and removal of water hyacinths by any mechanical, 
chemical, or other means 
Prohibits use of any chemical process injurious to cattle 
ST. AUGUSTINE HARBOR, FLA. (See Section 22 of Text) 
Channel 27 x 200 feet protected by a groin 
Channel 16 x 200 feet across bar, and thence 12 feet deep to 
Intracoastal Waterway; jetty on south side of inlet; future 
landward extension of groin and jetty; and channel 10 x 100 feet 
in San Sebastian River 
ST. LUCIE INLET, FLA. (See Section 23 of Text) 
Channel 10 x 200 feet 
Modification to maintain existing channel 6 x 100 feet 
Extending north jetty and modifying existing jetty to provide a 
sand bypass weir section; excavation of sand impoundment basin; 
construction of south jetty with walkway for recreational fishing; 
channel 10 x 500 feet thru bar cut, tapering to 150 feet thru the 
inlet, and 100 feet and 7 feet deep to the Intracoastal Waterway; 
and transfer of 380,000 cubic yards of material to the south beach 
during each two-year maintenance period 
SAN JUAN HARBOR, P.R. (See Section 24 of Text) 
Anchorage (inner harbor) area of 206 acres and San Antonio Channel 
to 30-foot depth 
Substitution of a 68-acre area 30 feet deep along southeasterly side 
of anchorage area, for one 25 acres in extent and of same depth 
extending easterly from eastern end of the San Antonio project 
channel 
Modified condition of local cooperation 
Entrance channel across outer bar 38 feet deep and 800 feet wide, 
and thence across bay to anchorage area (Anegado Reach Channel) 
30 feet deep and 700 feet wide and increasing anchorage area to 
239 acres to 30-foot depth 
Widening Anegado Reach Channel and increasing anchorage area to 
329 acres 
Removal to 8-foot depth of Anegado, Largo, and Capitanejo Shoals, 
and dredging to 30-foot depth the entrance channel and turning 
basin to the Graving Dock 
Maintenance of the 30-foot depth entrance channel and turning 
basin to the Army Terminal 
Deepening portions of entrance and approach channels and basins 
to Army Terminal and San Antonio Pier areas to 35-45 feet; 
new 32-foot depth Puerto Nuevo Channel; new 36-foot depth 
anchorage 
TAMPA HARBOR, FLA. (See Section 25 of Text) 
TAMPA BAY 
For a channel 27 feet deep from the Gulf of Mexico to Port Tampa, 
500 feet wide across the bar and 300 feet wide in the bay 
For a channel depth of 26 feet with sufficient width from the Gulf 
of Mexico to Port Tampa 
TAMPA AND HILLSBOROUGH BAYS 
For a depth of 24 feet in Hillsborough Bay 
For a 27-foot depth from Gulf of Mexico up to and in the several 
channels of Hillsborough Bay, the widths to be 500 feet on the bar, 
Specified in Act 
Specified in Act 
H. Doc. 555, 75th Cong., 
3d sess. 
H. Doc. 133, 81st Cong., 
1st sess. 
H. Doc. 391, 77th Cong., 
1st sess. 
H. Doc. 508, 89th Cong., 
2d sess. 
H. Doc. 294, 93d Cong., 
1st sess. 
H. Doc. 865, 63d Cong., 
2d sess. 
Specified in Act 
H. Doc. 45, 71st Cong., 
2d sess. 
R. & H. Comm. Doc. 38, 
74th Cong., 1st sess. 
R. & H. Comm. Doc. 42, 
75th Cong., 1st sess. 
H. Doc. 364, 76th Cong., 
1st sess. 
Specified in Act 
H. Doc. 38, 85th Cong., 
1st sess. 
H. Doc. 52, 55th Cong., 
3d sess. (Also printed in 
Annual Report 1899, 
p. 1640). Channel dimensions 
specified in Act 
Specified in Act 
H. Doc. 634, 61st Cong., 
2d sess. 
H. Doc. 634, 61st Cong., 
1st sess. 
9-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 3, 1899 
September 22,1922 
July 3, 1930 
August 30, 1935 
June 20, 1938 
Do. 
March 2, 1945 
Do. 
Do. 
May 17, 1950 
September 3, 1954 
October 23, 1962 
December 31, 1970 
Do. 
Do. 
Do. 
Do. 
Do. 
300 feet in Tampa Bay, Ybor, and Garrison Channels, and 200 feet 
in Hillsborough Bay, Sparkman, and Seddon Channels, with turning 
basins at the mouth of Hillsborough River and at Ybor Estuary 
HILLSBOROUGH RIVER 
For a 12-foot channel to within 100 feet of the Lafayette St. highway 
bridge (maintenance only; new work completed under a previous 
project under the title Improving Hillsborough Bay, Fla.) 
TAMPA HARBOR 
Consolidation of the above projects to form a single project for 
Tampa Harbor 
Increasing the depth of Egmont Channel to 29 feet and the width of 
Sparkman Channel to 300 feet 
For a depth of 32 feet and a width of 600 feet on Egmont Bar, 
a depth of 30 feet and a width of 400 feet in Mullet Key Cut, 
and a depth of 30 feet and a width of 300 feet in all other project 
channels in Tampa Harbor (except in Hillsborough River and in the 
channel leading to Alafia River); and for a turning basin 2,000 feet 
long and 500 feet in maximum width at the entrance to the Port 
Tampa terminals 
For widening the bend between Sparkman Channel and Cut D of 
Hillsborough Bay Channel by 250 feet; widening Ybor Channel 
to 400 feet and extending the turning basin at the west end of 
Garrison Channel (mouth of Hillsborough River) easterly for 
300 feet 
For construction of a breakwater at Peter 0. Knight Field, Davis 
Islands, its maintenance to be assumed by local interests 
For widening Sparkman Channel to 400 feet and Ybor Channel to 
500 feet; widening the bend between Sparkman and Garrison 
Channels an additional 250 feet to extend the turning basin 
westerly; and widening the bend between Seddon and Garrison 
Channels by 150 feet (in lieu of 300 feet previously authorized) 
to extend the turning basin easterly 
For a channel 9 feet deep and 100 feet wide in the Hillsborough 
River for about 2.4 miles above the upper end of the existing 
12-foot channel, and for the removal of obstructions thence to 
the Florida Avenue Bridge 
For a channel 25 feet deep and 150 feet wide from the Hillsborough 
Bay channel to and including a turning basin in the Alafia River. 
(Revoked by Act of May 17, 1950) 
For deepening Egmont Channel to 36 feet; enlarging Mullet Key Cut, 
Tampa Bay Channel, Hillsborough Bay Channel, Port Tampa 
Channel and Port Tampa turning basin to present project 
dimensions; deepening Sparkman Channel and Ybor turning basin 
to 34 feet; a channel 30 feet deep and 200 feet wide from 
Hillsborough Bay Channel to and including a turning basin in 
Alafia River, 700 feet wide and 1,200 feet long (in lieu of the 
improvement previously authorized;) and substantial widening 
at entrance, bends, and turns 
Entended removal of obstructions in Hillsborough River to City 
Water Works Dam. Maintenance of cleared channel to be assumed 
by local interests 
Channel and turning basin at Port Sutton 30 feet deep, Ybor Channel 
34 x 400 feet 
For federal maintenance of Port Sutton Channel, 280 feet wide and 
an irregularly shaped turning basin both to a depth of 34 feet 
Enlarge entrance channel across Egmont Bar to 46 x 700 feet from 
the Gulf to Mullet Key; 
Enlarge Mullet Key Cut Channel to 44 x 600 feet; 
Enlarge Tampa Bay Channel to 44 x 500 feet from Mullet Key Cut 
through Tampa Bay to the junction of Hillsborough Bay and 
Port Tampa Channels; 
Enlarge Hillsborough Bay Channel to 44 x 500 feet from the 
junction with Tampa Bay and Port Tampa Channels to the 
junction with Port Sutton entrance channel, and thence 
deepening to a depth of 42 feet at the existing width of 400 
feet to the junction with Seddon and Sparkman Channels; 
Enlarge Port Sutton entrance channel to 44 x 400 feet; 
H. Doc. 545, 55th Cong., 
2d sess. and Annual Report 
1898, pp. 1357-1360 
Specified in Act 
H. Doc. 100, 70th Cong., 
1st sess. 
S. Doc. 22, 72d Cong., 1st sess. 
S. Doc. 164, 75th Cong., 
3d sess. 
Sen. Comm. Print, 
76th Cong., 1st sess. 
S. Doc. 183, 78th Cong., 
2d sess. 
H. Doc. 119, 77th Cong., 
1st sess. 
S. Doc. 16, 77th Cong., 
1st sess. 
H. Doc. 258, 81st Cong., 
1st sess. 
H. Doc. 567, 81st Cong., 
2d sess. 
H. Doc. 529, 87th Cong., 
2d sess. 
H. Doc. 150, 91st Cong., 
1st sess. 
H. Doc. 401, 91st Cong., 
2d sess. 
Do. 
Do. 
Do. 
Do. 
9-34

TABLE 9-B (Continued) 
JACKSONVILLE, FLA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
BEACH EROSION 
CONTROL PROJECT 
August 13, 1968 
October 27, 1965 
August 13, 1968 
October 27, 1965 
October 23, 1962 
November 7, 1966 
October 23, 1962 
FLOOD CONTROL 
PROJECTS 
June 30, 1948 
September 3, 1954 
July 14, 1960 
October 23, 1962 
Enlarge Port Sutton turning basin to a depth of 44 feet and a 
turning diameter of 1,200 feet; 
Deepening Sparkman Channel to 42 x 400 feet; 
Deepening Ybor Channel to 40 x 300 feet; 
Enlarge turning basin at the entrance to Ybor Channel to a depth 
of 42 feet and an additional width of 200 feet on the southwest 
edge of the present basin; 
Deepening Port Tampa Channel to 42 feet at its existing width 
from the junction with Hillsborough and Tampa Bay Channels 
to the turning basin; 
Deepening the Port Tampa turning basin to 42 feet over its 
existing length of 2,000 feet and width of 900 feet; 
An entrance channel in East Bay 44 x 400 and 500 feet north 
from the Port Sutton turning basin for a distance of about 
2,000 feet; 
A turning basin in East Bay at a depth of 44 feet and with a 
turning diameter of 1,200 feet; 
An approach channel in East Bay 44 x 300 feet north from the 
East Bay turning basin for a distance of about 2,500 feet; and 
Maintenance of Port Sutton Terminal channel to 44 x 200 feet 
for a distance of 4,000 feet; 
BREVARD COUNTY, FLA. (See Section 29 of Text) 
S
Federal participation in cost of shore protection project 
BROWARD COUNTY, FLA., BEACH EROSION CONTROL 
AND HILLSBORO INLET, FLA., NAVIGATION PROJECT 
(See Section 30 of Text) 
Improvement for beach erosion control in Broward County, Fla., } 
and a combined beach erosion and navigation improvement to 
Hillsboro Inlet and the shore south thereof to Port Everglades 
DADE COUNTY, FLA. (See Section 31 of Text) 
Federal participation in cost of shore protection and hurricaneflood 
control project 
DUVAL COUNTY, FLA. (See Section 32 of Text) 
Federal participation in cost of shore protection project 
PALM BEACH COUNTY, FLA., FROM MARTIN 
COUNTY LINE TO LAKE WORTH INLET AND FROM 
SOUTH LAKE WORTH INLET TO BROWARD COUNTY LINE 
(See Section 33 of Text) 
Federal participation in cost of local shore protection project 
and sand-transfer plant. 
PINELLAS COUNTY, FLA. (See Section 34 of Text) 
Federal participation in cost of shore protection project 
VIRGINIA KEY AND KEY BISCAYNE, FLA. (See Section 35 of Text) 
Federal participation in cost of shore protection project and i 
construction of four groins 
CENTRAL AND SOUTHERN FLORIDA (See Section 38 of Text) 
First phase of comprehensive plan for flood control and other 
purposes 
Modification and expansion of authorization to include entire 
comprehensive plan of improvement 
Canals, levees, and water-control and drainage structures in the 
Nicodemus Slough area, Glades County 
Flood protection on Boggy Creek, near Orlando 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
i. Doc. 352, 90th Cong., 
2d sess. 
I. Doc. 91, 89th Cong., 
1st sess. 
H. Doc. 335, 90th Cong., 
2d sess. 
H. Doc. 273, 89th Cong., 
1st sess. 
H Doe. 164, 87th Cong., 
1st sess. 
H. Doc. 519, 89th Cong., 
2d sess. 
H. Doc. 561, 87th Cong., 
2d sess. 
H. Doc. 643, 80th Cong., 
2d sess. (contains latest 
published map) 
H. Doc. 643, 80th Cong., 
2d sess. 
S. Doc. 53, 86th Cong., 
1st sess. 
S. Doc. 125, 87th Cong., 
2d sess. 
9-35

TABLE 9-B (Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Do. 
Do. 
October 23, 1962 
Do. 
October 27, 1965 
Do. 
August 13, 1968 
Do. 
Approved 
December 17, 1970 
under the provisions 
of Section 201 of the 
Flood Control Act 
of 1965 
October 23, 1962 
December 31, 1970 
Flood protection in the Cutler Drain area, near Miami S. Doc. 123, 87th Cong., 
2d sess. 
Flood control and drainage works for South Dade County S. Doc. 138; 87th Cong., 
2d sess. 
Project for Shingle Creek between Clear Lake and Lake S. Doc. 139, 87th Cong., 
Tohopekaliga for flood control and major drainage, including 2d sess. 
development of Reedy Creek Swamp 
Improvement of easterly section of West Palm Beach Canal for S. Doc. 146, 87th Cong., 
flood control and major drainage 2d sess. 
Primary works for flood control and major drainage in southwest S. Doc. 20, 89th Cong., 
Dade County 1st sess. 
Primary works for flood control and major drainage in H. Doc. 102, 88th Cong., 
Hendry County 1st sess. 
Gravity drainage in Martin County and distribution of available S. Doc. 101, 90th Cong., 
water supplies to portions of Martin and St. Lucie Counties 2d sess. 
Improvement of supply, distribution, and conservation of water H. Doc. 369, 90th Cong., 
resources in Central and Southern Florida, including Lake 2d sess. 
Okeechobee agricultural area, Everglades NationalPark, and 
other related areas 
Navigation improvements suitable for recreational craft H. Doc. 394, 91st Cong., 
2d sess. 
FOUR RIVER BASINS, FLA. (See Section 39 of Text) 
Control of floods and improvement of drainage, and for water . H. Doc. 585, 87th Cong., 
conservation through construction of necessary canals, levees, 2d sess. 
reservoirs, and control structures 
PORTUGUES AND BUCANA RIVERS, P.R. (See Section 40 of Text) 
LAGO de CERRILLOS, P.R. 
Multiple purpose dam and lake for flood control, water supply, and H. Doc. 422, 91st Cong., 
recreation 2d sess. 
LAGO de PORTUGUES, P.R. 
Multiple purpose dam and lake for flood control, water supply, and 
recreation 
PONCE, P.R. 
Diversion and enlargement of existing channels through Ponce for 
flood control 
9-36

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-C CANAVERAL HARBOR, FLA. PROJECT 
DATA RELATIVE TO LOCK 
(See Section 4 of Text) 
Distance to nearest town 9.9 miles via 12-foot barge 
canal and Intracoastal 
Waterway 
Name of nearest town Cocoa, Fla. 
Distance from Intracoastal Waterway 6.5 miles 
Lock Dimensions 90' wide; 600' long' 
Lift Varies with tide 
Depth of sills (mlw, ocean) 14 feet 
Character of foundatiqn Piles in sand 
Year completed and opened to navigation 1965 
Contract cost $2,966,539 
'56 x 400 feet authorized. At request of NASA lock was creased width. Operation and maintenance of lock is a Federal 
constructed 90' wide with NASA bearing additional cost responsibility. 
($700,000). Length increased to 600' to be compatible with in 
TABLE 9-D CROSS-FLORIDA BARGE CANAL PROJECT 
LOCKS AND DAMS 
(See Section 6 of Text) 
R.N. 
Henry H. Buckman Eureka Lock Bert Dosh Dunnellon Inglis Lock 
Lock & Dam Lock Lock and Dam 
Nearest town Palatka, Sparr, Ocala, Dunnellon, Inglis, 
(miles) 11.2 15.8 8.9 2.5 3.2 
'Miles from Atlantic 
Intracoastal 
Waterway 90.4 111.4 127.7 156.5 168.6 
Lock dimensions (ft.)' 84 x 600 84 x 600 84 x 600 84 x 600 84 x 600 
Normal lift (ft.) 20 20 0-15' 12-27' 28 
Depth over sills 
at normal pool 
levels: 
Upper (ft.) 14 17 16-31' 16-31' 18 
Lower (ft.) 15 14 16 18 15 
Character of Piles in Piles in Piles in Rock Rock 
foundation sand sand sand 
Kind of dam Movable Movable None None Movable 
Type const. Earth8 Earth8 - - Earth' 
Percent complete 100 100 0 0 100 
Estimated contract 
cost $6,094,000 $7,975,000 $7,430,000 $9,500,000 $7,800,000 
1Clear width and greatest available length. 
Pool level varies with natural ground water profile from 
minimum elevation 40 to maximum elevation 55. 
8With concrete spillway and movable gates. 
9-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-E CROSS-FLORIDA BARGE CANAL 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 6 of Text) 
Work Performed Cost 
New work: 
Payment on completed contracts 
Inglis Dam and Spillway $ 43,302 
St. Johns Lock 359,658 
Adjustment on final pay estimate 
Bank Protection at Job No. 16 -44,166 
Hired labor surveys, inspections, and reports 2,639 
Engineering and design 34,634 
Supervision and administration 29,506 
Total 425,573 
Maintenance: 
Operation and maintenance of communications 
network 16,588 
Removal of debris, mosquitoes, and plant life 
from reservoirs 20,885 
Analysis of hydrologic-meteorologic data for 
scheduling releases from Lake Ocklawaha and 
Inglis Bypass 4,696 
Reimbursement to USGS for data collection 31,100 
Water quality surveillance 11,031 
Acquisition and maintenance of plant, tools, 
and equipment 49,274 
Maintenance of canal slopes and berms 221,750 
Collection for quarters and user fees -2,105 
Snagging and clearing 57,570 
Sanitary facilities at Lake Ocklawaha 11,032 
Safety barriers at Rodman Dam 3,580 
Engineering and design 19,077 
Supervision and administration 42,483 
Hired labor surveys, inspections and reports 53,193 
Maintenance of roads 1,720 
Trash removal 11,837 
Total 553,711 
Operation and care: 
Inglis, Eureka and Buckman Locks, Rodman Dam, 
Inglis Bypass and Spillway, and buildings and 
grounds, and recreational facilities were maintained 
by hired labor at a cost of 309,935 
9-38

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-F OKEECHOBEE WATERWAY 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 16 of Text) 
Work Performed Cost 
New work: 
Construction of 10-foot channel upstream from Ft. Myers 
(completed August 13, 1972) $ 15,594 
Recreational facilities W. P. Franklin Lock, North - 
Hired labor 29,852 
Engineering and design 253 
Supervision and administration 1,160 
Total applied cost 46,859 
Maintenance: 
District communications network 21,316 
Repair and replacement of project signs 8,060 
Snagging and clearing navigation channels 28,046 
Acquisition and maintenance of plant and equipment 187 
Operation and maintenance of recreation facilities 13,561 
Collection for Quarters (-) 2,640 
Downstream safety barriers for S-77, 78 and St. Lucie 
Spillway and removal and replacement of timber guidewall 
at Ortona Lock 16,144 
Update Master Plans 30,184 
Engineering and design 69,067 
Supervision and administration 54,629 
Hired labor surveys, inspections, and reports 47,769 
Total applied cost 286,323 
Operation and care: 
Hired labor cost of operating Moore Haven, Ortona, and 
St. Lucie Locks and maintenance of structures and grounds 336,902 
9-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-G 
REMOVING THE WATER HYACINTH FROM NAVIGABLE WATERS 
IN THE STATE OF FLORIDA 
SPRAYING OPERATIONS 
(See Section 21 of Text) 
Locality Acres Sprayed Cost 
St. Johns River and tributaries 15,803 $306,970 
Okeechobee Waterway and tributaries 8,310 193,879 
Acquisition and maintenance of airboats, 
engines, and work tools - 38,566 
Operation of communications network - 7,105 
Supervision and Administration - 7,868 
Total 24,113 554,388 
NAVIGATION PROJECTS ON WHICH RECONNAISSANCE AND 
CONDITION SURVEYS ONLY WERE CONDUCTED DURING FISCAL YEAR 
TABLE 9-H (See Section 26 of Text) 
Date Cost Incurred 
Survey During 
Project Conducted Fiscal Year' 
Anclote River, Fla. May 1975 18 
Cedar Keys Harbor, Fla. May 1975 52 
Channel from Naples to 
Big Marco Pass; 12-foot 
Channel Gordon Pass to 
Naples, Fla. April 1975 1,720 
Christiansted Harbor, V.I. January 1975 217 
Clearwater Pass, Fla. August 1974 502 
Crystal River, Fla. March 1975 1,769 
Eau Gallie Harbor, Fla. May 1975 2,980 
Everglades Harbor, Fla. February 1975 91 
Horseshoe Cove, Fla. January 1975 160 
Melbourne Harbor, Fla. June 1975 1,755 
Pass-A-Grille Pass, Fla. February 1975 9,473 
Port Everglades Harbor, Fla. June 1975 12,052 
St. Johns River, Jacksonville 
to Lake Harney, Fla. February 1975 850 
St. Petersburg Harbor, Fla. January-March 1975 3,943 
Suwannee River, Fla. June 1975 151 
Withlacoochee River, Fla. April 1975 55 
'Costs of surveys included with maintenance costs under 
Section "Other Authorized Navigation Projects." 
9-40

JACKSONVILLE, FLA., DISTRICT 
LTABf 9-I OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 27 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Anclote River, Fla. 
Aquatic Plant Control, Fla. 
(R&H Acts of 1958 & 1962) 
Atlantic Gulf Ship Canal, Fla. 
Bakers Haulover Inlet, Fla.' 
Bayport, Fla.5 
Cedar Keys Harbor, Fla." " 
Channel from Naples to Big Marco Pass; 
12-foot channel Gordon Pass to 
Naples, Fla.' 
Christiansted Harbor, St. Croix, V.I.8 
Clearwater Pass, Fla.' 
Courtenay Channel, Fla.' 
Crystal River, Fla.' 
Eau Gallie Harbor, Fla.' 
Everglades Harbor, Fla.' 
Fajardo Harbor, P.R.5 
Guayanes Harbor, P.R.5 
Gulf Intracoastal Waterway, 
St. Marks to Tampa Bay, Fla. 
Homosassa River, Fla.", " 
Horseshoe Cove, Fla.5 
Hudson River, Fla.' 
Intracoastal Waterway, Miami to 
Key West, Fla.' 
Johns Pass, Fla.' 
Key West Harbor, Fla.' 
Kissimmee River, Fla.' 
Lake Crescent and Dunns Creek, Fla.5 
Largo Sound Channel, Fla.' , " 
Little Manatee River, Fla.5 
Manatee River, Fla. 
Melbourne Harbor, Fla.' 
New River, Fla.' 
Orange River, Fla.' 
Ozona, Fla., channel and turning basin' 
Palm Beach, Fla., side channel and basin5 
Pass-A-Grille Pass, Fla. ' " 
Pithlachascotee River, Fla. 
Port Everglades Harbor, Fla. 
Rice Creek, Fla.' 
St. Johns River, Jacksonville to 
Lake Harney, Fla. 
St. Petersburg Harbor, Fla. 
St. Thomas Harbor, V.I.5 
Snagging and clearing under authority of 
Section 3 of River and Harbor Act of 
March 2, 1945 
Steinhatchee River, Fla.' 
Suwannee River, Fla. 
Withlacoochee River, Fla. 
1974 267,427 506,664 
1968 
1939 
1965 
1972 
1966 
1971 
1964 
1974 
1940 
1941 
1970 
1964 
1945 
1945 
1974 
1937 
1967 
1974 
1963 
1969 
1972 
1931 
1931 
1966 
1949 
1970 
1970 
1956 
1962 
1963 
1946 
1966 
1973 
1974 
1957 
1963 
1966 
1949 
1965 
1940 
1963 
1969 
2,619,7002 
5,099,153 
243,235$ 
58,495' 
168,5698 
305,290' 
303,317 
46,3499 
22,846 
25,000 
9,627 
221,50910 
38,850 
3,999 
347,521 
9,889 
243,079 
80,59812 
1,548,89213 
23,479 
10,276 
117,44315 
11,90318 
123,350 
17,696 
36,518 
2,000 
105,527 
41,29718 
400,000 
6,655,77319 
85,20820 
1,171,24321 
255,60823 
1,989 
39,288 
135,053 
76,41828 
614,91227 
2,779 
31,153 
248,861 
8,291 
512,240 
24,796 
41,353 
12,066 
697 
94,852 
2,996 
14,810 
359,701 
25,202 
8,166 
11,431 
160,445 
43,688 
17,997 
1,946 
13,779 
219,913 
675,155 
3,137 
608,72722 
90,35524 
197,23425 
5,790 
118,870 
301,970 
9-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-I (Continued) 
1. Complete. 
2. Excludes $918,205 contributed funds. 
3. Excludes $243,235 for contributed funds 
4. Includes $41,222 for reconnaissance and detailed project 
reports under Section 107 of the R&H Act of 1960. 
5. Inactive. 
6. Includes $82,500 expended under previous project but 
excludes $1,473 contributed funds. 
7. Excludes $159,975 contributed funds. 
8. Project as modified by Chief of Engineers in report of 
June 30, 1961, is complete. Previously authorized depth of 25 
feet in inactive status. 
9. Excludes $42,783 contributed funds for new work. 
10. Excludes $36,000 contributed funds. 
11. In addition, $1,000 expended from contributed funds. 
12. Project authorized December 2, 1964, by Chief of Engineers 
under Section 107 of 1960 R&H Act and by Section 110 
of the 1966 R&H Act. Cost of new work excludes $53,732 contributed 
funds. 
13. Includes $27,500 for new work under previous 
project. Excludes $35,371 contributed funds. 
14. Authorized April 20, 1964 by Chief of Engineers under 
Section 107 of 1960 R&H Act. 
15. Includes $25,008 for detailed project report but excludes 
$86,716 expended from contributed funds. 
16. Expended on restudy. 
17. Authorized November 19, 1964, by Chief of Engineers 
under Section 107 of R&H Act of 1960. 
18. Excludes $41,297 contributed funds. 
19. Excludes $323,456 contributed funds. 
20. Excludes $93,000 contributed funds. 
21. Beresford cutoff and completion of cutoffs and easing 
of bends in Putnam, Lake, and Volusia Counties in inactive 
status. Includes $29,566 for new work under previous project. 
22. Includes $25,838 under previous project. 
23. Includes $32,689 under previous project. 
24. Includes $20,532 under previous project. 
25. In addition $1,672 expended from contributed funds. 
26. Includes $10,154 expended under previous project. 
27. Includes $30,000 expended under previous project. 
9-42

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-J NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
PURSUANT TO SECTION 107, PUBLIC LAW 86-645 
(PREAUTHORIZATION) 
(See Section 28 of Text) 
Study Identification Fiscal Year Costs 
Reconnaissance Reports: 
Blount Island turning basin, 
Jacksonville Harbor, Fla. 5,000 
Stokes Landing Channel, Palatka, Fla. 16,855 
Wiggins Pass, Fla. 4,080 
Detailed Project Reports: 
Boot Key Harbor, Fla. 13,662 
Doctors Pass, Naples, Fla. 5,000 
Longboat Pass, Fla. 11,531 
TABLE 9-K OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
(See Section 36 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cape Florida State Park 1969 34,8621 - 
Fort Pierce, Fla. 1972 327,4482 
Key West, Fla. 1963 96,340' 3,794 
Lee County, Fla. 1971 - - 
Lido Key, Fla. 1971 - - 
Mullet Key, Fla. 1973 436,201' - 
Palm Beach County, Fla., from 
Lake Worth Inlet to South 
Lake Worth Inlet 1970 195,1405 6,257 
San Juan, Puerto Rico 1965 -_ 6 
1. Includes $2,462 cost of reconnaissance and detailed 
project reports, but excludes $13,818 contributed funds. 
2. Excludes $300,083 in property or services furnished by 
local interests in lieu of cash contribution. 
3. Excludes $192,168 contributed funds. 
4. Excludes $202,978 contributed funds. 
5. Excludes $781,188 in property or services furnished by 
local interests in lieu of cash contribution. 
6. Excludes $22,400 contributed cost for preauthorization 
studies. 
TABLE 9-L BEACH EROSION CONTROL UNDER SPECIAL AUTHORIZATION 
ACTIVITIES PURSUANT TO SECTION 103, PUBLIC LAW 87-874 
(PREAUTHORIZATION) 
(See Section 37 of Text) 
Study Information Fiscal Year Costs 
Detailed Project Report: 
El Tuque Beach, P.R. 448 
Munoz Rivera Park, P.R. 908 
9-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 9-L (Continued) 
ACTIVITIES PURSUANT TO SECTION 111, PUBLIC LAW 90-483' 
Study Information Fiscal Year Costs 
Fernandina Harbor, Fla. 2,165 
Palm Beach Harbor, Fla. 6,551 
'These costs are included with maintenance costs of the 
applicable projects. 
CENTRAL AND SOUTHERN FLORIDA PROJECT 
TABLE 9-M PRINCIPAL FEATURES OF HURRICANE GATES 
(See Section 38 of Text) 
Nearest Town Depth Character 
Gate' Over of Year 
No. Distance Sills Founda- Corn- Actual 
Name (miles) (ft.) tion pleted Cost 
2. Clewiston, Fla. 0.5 10 Pile 1935 $309,748 
3. Lake Harbor, Fla. 0.5 10 Rock 1935 316,938 
4. Belle Glade, Fla. 4.0 10 Rock 1935 350,025 
5. Canal Point, Fla. 0.0 10 Rock 1935 262,465 
6. Okeechobee, Fla. 0.5 7 Pile 1936 373,273 
'All are 50 feet wide with available length unlimited. They control. Moore Haven Lock serves as Hurricane Gate Strucare 
constructed of concrete with steel sector gates and have no ture 1. 
lift. Gate No. 6 has an auxiliary culvert spillway with automatic
9-44

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-N CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF LOCKS AND DAMS 
(See Section 38 of Text) 
Miles 
From Lock Elevation of Character Kind Type 
Nearest Nearest Dimensions Normal Normal Pool Depth of of of of Percent Contract 
Town Town (ft.) lift (ft.) surface (ft.) sills (ft.) foundation Dam Construction Complete Cost 
W. P. Franklin At Olga 
Lock and Dam' 
S-65 Lock Frostproof 
S-65A Lock Avon Park 
S-65B Lock Sebring 
S-63C Lock Sebring 
S-65D Lock Okeechobee 
S-65E Lock Okeechobee 
Moore Haven Moore Haven 
Lock (HGS-1 
Mod.) 
S-310 Clewiston 
(HGS-2 Mod.) 
S-193 Okeechobee 
(HGS-6 Mod.) 
S-308B Pahokee 
Lock on Flamingo 
Buttonwood 
Canal 
S-57 Ashton 
S-58 Ashton 
S-59 Kissimmee 
S-60 Ashton 
S-61 St. Cloud 
S-62 Ashton 
S-63 Ashton 
S-63A Ashton 
S-96 Sebastian 
S-96A Sebastian 
S-53 Eau Gallie 
S-55 Christmas 
S-157 Sebastian 
S-158 
0 56 x 400 2.5 3.0 
23 30 x 90 
26 30 x90 
20 30 x 90 
25 30 x 90 
14 30 x90 
10 30 x 90 
0.5 50 x 250 
0.5 50 x 60 
0.5 50 x 60 
11 56 x 400 
2 20 x 60 
9 20 x 90 
5 20 x 90 
6 20 x 90 
6 20 x90 
6 30 x 90 
10 20 x 90 
12 20 x90 
14 20 x 90 
14 20 x 60 
16 20 x 60 
8 20 x 60 
12 20 x 60 
4 20 x 60 
4.2 50.5 
6.3 46.3 
6.0 40.0 
7.2 34.0 
5.8 26.8 
4.6 21.0 
9.4 20.5 
5.0 20.5 
7.5 20.5 
4.0 20.5 
2.0 2.0 
1.0 62.0 
2.0 64.0 
3.0 58.0 
2.0 64.0 
2.0 55.0 
3.0 61.0 
5.0 62.0 
4.5 57.0 
4.0 24.0 
7.5 25.0 
3.5 17.5 
10.0 14.0 
20.0 20.0 
Titusville 15 20 x 60 4.5 4.0 
14 Piles in Movable Reinforced 
clay concrete 
6 Earth, None Reinforced 
founda- concrete 
tion, sand rigid frame 
6 Earth, None Reinforced 
founda- concrete 
tion, sand rigid frame 
6 Earth, None Reinforced 
founda- concrete 
tion, sand rigid frame 
6 Earth, None Reinforced 
founda- concrete 
tion, sand rigid frame 
6 Earth, None Reinforced 
founda- concrete 
tion, sand rigid frame 
6 Earth, None Reinforced 
founda- concrete 
tion, sand 
11 Piles in None Steel sheet pile 
sand lockwalls 
12.9 Slab on None Reinforced 
sand concrete 
7.5 Piles in , None Reinforced 
sand and - concrete 
slab on sand 
18 Slab on Fixed Reinforced 
sand concrete 
6 Slab on None Steel sheet pile 
sand lockwalls 
6 Earth, None Concrete and 
founda- steel sheet 
tion, sand pile 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
6 Do. None Do. 
100 $3,803,655 
100 
100 
100 
100 
100 
100
0
0
0 
50
0
0
0
0
0 
100
0
0
0
0
0
0
0
0
0
o
o
o
o
O0 
o
O0 
$1,194,132 
$1,492,495 
$ 921,819 
$1,092,424 
$1,130,835 
$1,269,282 
$ 180,000' 
$3,750,000' 
$ 255,000' 
$8,653,000' 
$ 715,000' 
$ 975,000' 
$ 975,000' 
$ 975,000' 
$ 975,000' 
$ 684,217 
$ 975,000' 
$ 975,000' 
$ 954,000' 
$ 855,000' 
$ 813,000' 
$ 789,000' 
$ 809,000' 
$1,029,000' 
$ 930,000' 
'Operation and care of W. P. Franklin Lock and Dam (S-79) is a Federal responsibility. 
Estimated. 
9-45

TABLE 9-0 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
CENTRAL AND SOUTHERN FLORIDA PROJECT 
LOCAL COOPERATION 
(See Section 38 of Text) 
Flood Control Act Work Authorized O/oC ash Contribution' 
June 30, 1948 First phase of comprehensive plan 15.0 
Sept. 3, 1954 Second phase of comprehensive plan 20.0 
July 14, 1960 Nicodemus Slough area 31.5 
Oct. 23, 1962 West Palm Beach Canal 12.8 
Boggy Creek Basin 29.7 
Shingle Creek Basin 25.9 
South Dade County area 19.2 
Reedy Creek Swamp 50.0 
Oct. 27, 1965 Southwest Dade County 46.0 
Hendry County area 19.5 
Aug. 13, 1968 Martin County 
Flood Control Features 34.0 
Irrigation Features 49.0 
Recreation Features 42.0 
Water Resources 20.0 
Water Resources - Recreation Facilities 50.0 
Approved Dec. 17, 1970 Navigation improvements suitable for 50.0 
under Provisions of recreational craft 
Section 201 of 1965 
Flood Control Act 
1Computed on total contract' cost and supervision and 
administration except for Reedy Creek Swamp which is computed 
on all costs, including engineering and design and land.
9-46

JACKSONVILLE, FLA., DISTRICT 
CENTRAL AND SOUTHERN FLORIDA PROJECT 
TABLE 9-P OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 38 of Text) 
Work Performed Cost 
New Work: 
Construction of: 
Locks $4,142,459 
Channels and canals 228,198 
Levees 655,821 
Pumping plants 56,400 
Floodway control and diversion structures 2,390,775 
Stores 2,006 
Engineering and design 1,001,055 
Supervision and administration 400,517 
Hired labor surveys, inspections, and reports 30,086 
Total applied cost 8,907,317 
Maintenance: 
Operation and care of facilities, buildings and grounds 19,679 
Operation of communications network 17,763 
Real estate management service 3,115 
Repairs and replacement of project signs 10,821 
Patrol, inspections, and maintenance of Herbert Hoover Dike 768,672 
Collection and analyses of hydrologic and meteorologic data 223,045 
Costs reimbursable to U.S. Geological Survey for O&M of gaging stations 37,700 
Periodic and miscellaneous surveys, inspections, repairs, and operations 94,411 
Water quality studies 243,176 
Repair crown road, Herbert Hoover Dike 21,221 
Remove weed growth and replant grass on levee slopes, Herbert Hoover Dike 10,493 
Review of C&SF Flood Control District permit applications 6,119 
Rebuild and regrade levee slopes as required, Herbert Hoover Dike 16,352 
Cleanout landside toe ditches and berms on Herbert Hoover Dike 8,521 
Repair or replace culverts, Herbert Hoover Dike 9,739 
Repair fences, Herbert Hoover Dike 46,835 
Maintenance recreation area, W. P. Franklin Lock 41,795 
Maintenance berms, fences and shrubs on C-43 45,610 
Clean silt, hyacinth and other growths and debris from landside entrance channel 
to all culverts, approach channels, and HGS and floodway channels 4,405 
Repair and riprap eroded berms, Herbert Hoover Dike 56,953 
Remove trees and riprap slopes, Herbert Hoover Dike 4,568 
Repair revetment, St. Lucie Canal 5,366 
Operations W. P. Franklin Lock (S-79) 100,104 
Operation and maintenance of spillways: 
St. Lucie (S-80); Moore Haven (S-77); 
Ortona (S-78); S-10, 11, & 12 47,400 
Operation hurricane structures 16,708 
Operation and maintenance of drainage culverts 10,715 
Repair to W. P. Franklin Lock 4,007 
Dewater, repair, sandblast and paint S-79 gates 99,129 
Mow grass on levee slopes Herbert Hoover Dike 15,359 
Top trees Herbert Hoover Dike 41,784 
Maintenance of airboat 2,216 
Collection for subsistence and quarters (-)1,401 
Engineering and design 3,344 
Supervision and administration 103,435 
Total applied cost 2,139,159 
9-47

TABLE 9-Q 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
CENTRAL AND SOUTHERN FLORIDA PROJECT 
LAKE OKEECHOBEE 
WATER SUPPLY AND WATER DATA 
(See Section 38 of Text) 
Fiscal Rainfall Evaporation Net Water Total Ag Canal 
Year (inches) (inches) Supply (AF) Inflow (AF) Outflow (AF) 
1975 44.04 60.90 2,162,000 2,558,000 1,033,000 
1974 39.64 60.50 768,700 2,136,630 829,000 
1973 33.48 61.24 (-)83,800 1,313,200 631,500 
1972 47.27 58.68 1,561,000 1,972,200 313,000 
1971 33.05 61.68 (-)205,800 920,100 753,400 
Normals 49.88 56.22 1,740,000 2,456,000 546,000 
CENTRAL AND SOUTHERN FLORIDA PROJECT 
TABLE 9-R WATER CONSERVATION AREAS 
WATER SUPPLY AND WATER USE DATA 
(See Section 38 of Text) 
Fiscal Rainfall Evaporation Net Water Inflow Releases Seepage 
Year (inches) (inches) Supply (AF) (AF) to East (AF) (AF) 
WATER CONSERVATION AREA NO. 1 
1975 40.93 46.6 508,500 516,700 46,150 150,500 
1974 51.03 53.1 602,900 335,900 38,000 182,600 
1973 35.80 52.4 159,000 120,600 48,900 136,600 
1972 58.28 E45.7 632,000 417,300 21,800 204,300 
1971 35.99 48.6 249,000 203,900 72,000 105,700 
Normals 56.48 - - - - 
WATER CONSERVATION AREA NO. 2A 
1975 36.71 46.4 618,800 526,400 44,600 134,000 
1974 45.74 50.6 442,870 369,100 42,660 105,600 
1973 35.09 52.4 24,100 127,500 20,600 95,800 
1972 51.00 E45.7 581,000 494,100 0 109,300 
1971 36.19 49.0 110,800 213,800 60,400 95,200 
Normals 50.84 - - - 
WATER CONSERVATION AREA NO. 3A 
1975 37.74 51.8 557,600 784,600 26,300 356,000 
1974 38.11 50.2 927,200 803,400 56,100 307,700 
1973 33.78 53.4 (- )74,500 436,000 13,000 324,500 
1972 48.37 E45.7 1,198,600 851,000 0 342,000 
1971 34.97 48.8 (-)163,200 495,400 30,400 352,000 
Normals 50.43 - - - - 
E - Estimated 
9-48

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-S CENTRAL AND SOUTHERN FLORIDA PROJECT 
STATUS OF WORKS UNDER CONTRACT AT END OF FISCAL YEAR 
(See Section 38 of Text) 
Construction Approx. o/o 
Feature Started Complete 
Channels and canals: 
C-20 (Part) Aug. 1973 99 
C-21 Do. 99 
Levees: 
L-D1 & D3 connecting canals Aug. 1973 99 
S-308 Tieback Levees Feb. 1974 46 
Structures: 
S-25B Jul. 1973 66 
S-169 Aug. 1973 99 
S-235 Aug. 1973 99 
S-308B Feb. 1974 46 
S-308C Do. 46 
S-25 June 1975 0 
S-25A Do. 0 
FOUR RIVER BASINS, FLORIDA, PROJECT 
TABLE 9-T MOSS BLUFF LOCK 
(See Section 39 of Text) 
Nearest town 20 miles 
Name of nearest town Ocala, Fla. 
Distance above mouth of River 65.5 miles 
Lock dimensions 30 x 125 feet 
Normal lift 18.0 feet 
Elevation of normal pool surface 58 feet 
Depth of sills 12 feet 
Character of foundation Piles in sand 
Kind of dam None 
Type of construction Reinforced concrete 
Percent complete 100 
Estimated Cost (including dam and spillway) $2,032,000 
9-49

TABLE 9-U 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
FOUR RIVER BASINS, FLORIDA, PROJECT 
CONDITION AT END OF FISCAL YEAR 
(See Section 39 of Text) 
Date transferred to 
Construction Southwest Florida 
Feature Period for Operation and Maintenance 
Bridges: 
B-194 July 1968- Mar. 1970 Not transferred 
Alteration of Facilities B-195 May 1971- Jan. 1973 Do. 
B-594 Jan. 1973-Jan. 1974 Do. 
Alteration of Facilities B-196 Oct. 1972-Jan. 1975 Do. 
Channels and Canals: 
C-135 May 1967-Dec. 1968 Dec. 1968 
C-135, Sec. 1A July 1966-Aug. 1967 Oct. 1967 
C-135, Sec. 1B May 1968-Sep. 1972 Do. 
C-135, Sec. 1C & 2 Jan. 1971- Dec. 1973 Not transferred 
C-135, Sec. 3A Dec. 1972- Apr. 1975 Not transferred 
C-231, Phase I July 1973-Apr. 1975 Not transferred 
C-231, Phase II July 1973-Jan. 1974 Do. 
C-331 July 1967-Sep. 1968 Sep. 1968 
C-531 Apr. 1966-Jan. 1969 Apr. 1969 
C-534 June 1970-July 1971 Nov. 1971 
Structures: 
S-160 May 1967- Dec. 1968 Dec. 1968 
S-353 July 1967-Sep. 1968 Nov. 1968 
Moss Bluff Lock and Spillway Apr. 1967- Mar. 1969 Not transferred 
8-551 July 1970-Feb. 1972 Sep. 1968 
Levees: 
L-212, Sec. 1 June 1968- July 1970 Not transferred 
L-212, Sec. 2 July 1970- Sep. 1971 Do. 
9-50

JACKSONVILLE, FLA., DISTRICT 
TABLE 9-V OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 42 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Arch Creek, Dade County, Fla. 1960 66,4851 
Biscayne Bay, Fla., Hurricane 
Protection2 1966 - 
Hillsborough Bay, Fla.2 1969 - 
Hogtown Creek, Fla. 1972 83,299- 
Phillippi Creek Basin, Fla.2 1966 - 
1. Excludes $11,734 cost of preauthorization studies. Pro- 2. Inactive. 
ject was authorized February 20, 1959, by Chief of Engineers 3. Includes $44,282 for reconnaissance and detailed prounder 
Section 205 of the 1948 Flood Control Act as modified by ject reports. 
P.L. 685, 84th Congress.
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
PURSUANT TO SECTION 205, PUBLIC LAW 685, 
(PREAUTHORIZATION) 
(See Section 43 of Text) 
Study Identification Fiscal Year Costs 
Reconnaissance Report: 
Half Moon Lake, Putnam County, Fla. 
Pinellas Park, Fla. 
TABLE 9-X FLOOD PLAIN INFORMATION STUDIES COMPLETED 
DURING FISCAL YEAR 
(See Section 45 of Text) 
Location Requesting Agency Date Completed Federal Cost 
Sumter County Southwest Florida Water Sept. 1974 $17,000 
Withlacoochee River Water Management District 
St. Thomas, St. Croix, and Office of Governor June 1975 15,000 
St. Johns, Tidal Areas Virgin Islands 
Planning Office 
9-51 
TABLE 9-W 
2,570
2

MOBILE, ALA., DISTRICT* 
This district comprises a small portion of 
southeastern Tennessee, western Georgia, 
western Florida, all of Alabama south of 
Tennessee River Basin, eastern Mississippi, and a 
small portion of southeastern Louisiana embraced 
in drainage basins tributary to the Gulf of 
Mexico, west of Aucilla River Basin, to and including 
Pearl River Basin. It includes a section of 
the Gulf Intracoastal Waterway from St. Marks, 
Florida, to Lake Borgne Light No. 29, Louisiana. 
IMPROVEMENTS 
Navigation 
1. Apalachicola Bay, Fla. ............ 
2. Aquatic Plant Control (R&H Act 
of 1965) ......................... 
3. Bayou Coden, Ala. ................. 
4. Bayou La Batre, Ala. ............ 
5. Biloxi Harbor, Miss. .......... 
6. Black Warrior and Tombigbee 
Rivers, Ala. ...................... 
7. Dauphin Island Bay, Ala. ....... , 
8. Dog and Fowl Rivers, Ala. ........ 
9. East Pass Channel from Gulf of 
Mexico into Choctawhatchee Bay, 
Fla............................ 
10. Escambia-Conecuh Rivers, Fla. 
and Ala........................ 
11. Gulf Intracoastal Waterway 
between Apalachee Bay, Fla., 
and Mexican border (Mobile 
District)... .................... 
12. Gulfport Harbor, Miss.............. 
13. Mobile Harbor, Ala. .............. 
14. Panama City Harbor, Fla. ........ 
15. Pascagoula Harbor, Miss. ......... 
16. Pass Christian Harbor, Miss. ..... 
17. Pearl River, Miss., and La. ........ 
18. Pensacola Harbor, Fla. ........ 
19. Perdido Pass, Ala. ................ 
20. Removing Water Hyacinth, Mobile 
District..................... 
21. Waterway Connecting Tombigbee 
and Tennessee Rivers, Ala., 
and Miss....................... 
22. Reconnaissance and Condition 
Surveys ......................... 
23. Other Authorized Navigation 
Projects ...................... 
Page 
10-2 
10-2 
10-3 
10-3 
10-4 
10-4 
10-6 
10-6 
10-7 
10-7 
10-7 
10-8 
10-9 
10-10 
10-10 
10-11 
10-11 
1l_ 1 
Navigation (Cont.) 
24. Navigation Work Under Special 
Authorization .................. 
Page 
10-14 
Beach Erosion Control 
25. Authorized Beach Erosion Control 
Project .......................... 10-14 
Flood Control 
26. Jackson and East Jackson, Miss. ... 10-14 
27. Okatibbee Lake, Miss ............. 10-14 
28. Tallahala Creek Lake, Pascagoula 
River, Miss. ................ . 10-15 
29. Edinburg Lake, Miss. ............. 10-15 
30. Tombigbee River, Miss. and 
A la .............................. 10-16 
31. Tombigbee River Tributaries, 
Miss. and Ala .................... 10-16 
32. Inspection of Completed Flood 
Control Projects .................. 10-17 
33. Other Authorized Flood Control 
Projects .......................... 10-17 
34. Flood Control Work Under Special 
Authorization ................... 10-17 
10-12 Multiple Purpose Projects Including Power 
35. Alabama-Coosa Rivers, Ala., and 
10-13 Ga. ............................... 10-17 
35A. Carters Lake, Ga. ................. 10-18 
35B. Claiborne Lock and Dam, Ala. .... 10-19 
10-13 35C. Jones Bluff Lock and Dam, Ala. 10-19 
35D. Millers Ferry Lock and Dam, 
10-14 Ala............................. 10-19 
36. Allatoona Lake, Coosa River 
10-14 Basin, Fa. ....................... 10-20 
*All cost and finance statements for projects are listed at the end of this chapter. All other tables are referenced in text and also 
appear at the end of this chapter. 
10-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Multiple Purpose Projects 
Including Power (Cont.) Page 
37. Apalachicola, Chattahoochee, and 
Flint Rivers, Ala., Ga., and Fla., ... 10-20 
37A. Lake Sidney Lanier, Ga. .......... 10-22 
37B. George W. Andrews Lock and Dam, 
Ala. and Ga. .................... 10-22 
37C. Jim Woodruff Lock and Dam, Ga. 
and Fla. .......................... 10-23 
37D. Spewrell Bluff Lake, Ga. ......... 10-23 
37E. Walter F. George Lock and Dam, 
Ala. and Ga. ...................... 10-24 
Multiple Purpose Projects 
Including Power (Cont.) Page 
37F. West Point Lake, Chattahoochee 
River Basin, Ga. and Ala...........10-24 
38. Reservoir Operations .............. 10-25 
General Investigations 
39. Surveys ......................... 10-25 
40. Collection and Study of Basic 
Data ............................ 10-25 
41. Research and Development ........ 10-25 
Navigation 
1. APALACHICOLA BAY, FLA. 
Location. The project is on the coast of 
northwest Florida 160 miles east of Pensacola 
Harbor. (See Coast and Geodetic Survey Chart 
1262.) 
Previous project. For details, see page 1833, Annual 
Report for 1915, and page 689, Annual 
Report for 1938. 
Existing project. The authorized project 
provides for: (a) A channel 10 feet deep and 100 
feet wide from the 10-foot depth in Apalachicola 
Bay, across St. George Island, to within 300 feet of 
the gulf shore, thence increasing uniformly in 
width to 200 feet at the shore and continuing with 
that width to the 10-foot depth in the Gulf of Mexico, 
with twin jetties extending from the dune line 
to the outer end of the channel; (b) an inner bar 
channel, 10 feet deep and 100 feet wide, in 
Apalachicola Bay; (c) a boat basin 200 feet by 880 
feet and nine feet deep at Apalachicola, Florida, 
with a connecting channel nine feet deep and 80 
feet wide through Scipio Creek to Apalachicola 
River; (d) a channel known as Link Channel, 10 
feet deep and 150 feet wide, in Apalachicola Bay; 
(e) a channel generally parallel to the shore at 
Eastpoint, Florida, six feet deep, 100 feet wide, 
and about 6,000 feet long, with a connecting 
channel six feet deep and 100 feet wide to water at 
the same depth in St. George Sound; (f) a channel 
nine feet deep and 100 feet wide through 
Bulkhead Shoals, connecting Apalachicola Bay 
with St. George Sound; and (g) a 6-foot by 100-foot 
channel about one mile long, generally parallel to 
the shore at Two Mile, Florida, with a 6-foot by 
100-foot connnecting channel to water of the same 
depth in Apalachicola Bay. (See Table 10-B for 
authorized modifications of Two Mile project.) 
Mean range of tide thorughout this harbor is 1.6 
feet. Extreme range, except during storms, is 
about three feet. Plane of reference is mean low 
water. (See Table 10-B for authorizing legislation.) 
Local cooperation. Requirements have been fully 
complied with. 
Terminal facilities. Facilities consist of pileand-
timber wharves which are considered adequate 
for existing commerce. 
Operations and results during fiscal year. New 
work: Engineering, design, supervision and administration 
for the authorized modification to 
Two Mile project cost $28,437. 
Maintenance: Contract work for environmental 
studies cost $930 and hydraulic studies cost 
$6,650. Hired labor cost included $5,581 for environmental 
studies, $850 for water quality 
studies and $180 for supervision and administration. 
Condition at end of fiscal year. The existing 
project, authorized by the 1954 River and Harbor 
Act, was completed in 1959, including reimbursement 
to local' interests for approved work, as 
authorized by the 1958 River and Harbor Act. 
Improvements at Two Mile except for 
modifications authorized in 1975 were completed 
in September 1964. Total Federal costs under existing 
project as of June 30, 1975 were $964,400 
for new work and $1,236,142 for maintenance, a 
total of $2,200,542. 
2. AQUATIC PLANT CONTROL (RIVER 
AND HARBOR ACT OF 1965) 
Location. Navigable water, tributary streams, 
connecting channels and other allied waters in 
Mobile District. 
Existing project. The authorized project 
provides for control and progressive eradication 
of water hyacinth, alligatorweed, Eurasian 
watermilfoil and other obnoxious aquatic plant 
growths from navigable water, tributary 
streams, connecting channels, and other allied 
waters of the United States, in the combined interest 
of navigation, flood control, drainage, 
agriculture, fish and wildlife conservation, 
10-2

MOBILE, ALA., DISTRICT 
public health, and related purposes, including 
continued research for developnment of the most 
effective and economical control measures to be 
administered by the Chief of Engineers, under 
the direction of the Secretary of the Army, in 
cooperation with other Federal and State agencies. 
Research and planning cost prior to construction 
shall be borne fully by the United 
States. (See Table 10-B for authorizing legislation.) 
Local cooperation. Local interests shall agree to 
hold and save the United States free from claims 
that may occur from control operations and to 
participate to the extent of 30 percent of such 
operations. Requirements are being met in 
Florida, Louisiana, and Georgia. 
Operations and results during fiscal year. 
Treatment of aquatic plant growth of infested 
areas in Florida and Alabama cost $16,000 and 
$1,687, respectively. 
Research under contract with Auburn University 
cost $16,283. 
Planning, engineering, design, supervision 
with the States of Alabama, Georgia, Florida, 
Louisiana and Mississippi cost $21,849. 
Condition at end of fiscal year. Field surveys for 
General Design Memorandum for the State of 
Mississippi have been completed. Total Federal 
costs under the existing project as of June 30, 
1975 were $253,965. Contributed funds for 
maintenance amount to $21,225. 
3. BAYOU CODEN, ALA. 
Location. The project is located in a small tidal 
stream on the southern coast of Mobile County, 
Alabama, emptying into Mississippi Sound about 
7.6 miles northwest of Cedar Point, the southern 
tip of western mainland shore of Mobile Bay. (See 
Coast and Geodetic Survey Chart 1266.) 
Previous project. For details see Annual Report 
for 1945, page 843. 
Existing project. The project provides for a 
channel eight feet deep by 60 feet wide extending 
from La Belle Avenue bridge south for about 
3,000 feet through the bayou to Portersville Bay, 
thence eight feet deep by 100 feet wide extending 
about 2.3 miles westward across Portersville Bay 
to connect with the Bayou La Batre channel, and a 
turning basin eight feet deep by 60 feet wide by 
100 feet long on the west side of the bayou channel 
about 500 feet south of the La Belle Avenue 
bridge. Mean tidal range is 1.75 feet, and extreme, 
except during storms, is 3.5 feet. Plane of 
reference is mean low water. Estimated (1975) 
Federal cost for construction is $264,000 exclusive 
of $100,000 for non-Federal costs. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Requirements of local 
cooperation have been fully complied with for all 
work authorized prior to 1969. For work 
authorized in 1969, local interests must furnish 
suitable lands for spoil-disposal and aids to 
navigation; provide adequate public terminals; 
provide adequate depths in berthing areas; 
regulate the discharge of pollutants into the 
water of the harbor; alter any utility facilities 
within the project area; hold the United States 
free from damages; and assume responsibility for 
all project cost in excess of $500,000. Local interests 
have indicated their willingness to comply.
Small privately-owned pile-and-timber piers 
used in connection with fishing industry in this 
locality are adequate for existing commerce. A 
marina which will accommodate about 12 small 
recreational craft, and a slip with facilities for 
loading oyster shells are located near the mouth of 
the bayou, and are maintained by the Alabama 
Department of Conservation. 
Operations and results during fiscal year. New 
work: Engineering, design, supervision, and administration 
cost $34,811. Contributed funds in 
the amount of $59,400 were expended for diking 
of spoil areas. 
Maintenance: None 
Condition at end of fiscal year. That portion of 
the project authorized prior to the 1969 modification 
was completed in 1956. Construction 
authorized in 1969 was initiated 31 March 1975 
and is scheduled for completion in September 
1975. Total Federal costs under existing project 
as of June 30, 1974 were $74,323 for new work and 
$38,879 for maintenance, a total of $113,202 contributed 
funds amount to $59,400. 
4. BAYOU LA BATRE, ALA. 
Location. Bayou La Batre is a tidal stream 
about 10 miles long, emptying into Mississippi 
Sound on the southern coast of Mobile County, 
Ala., about 10 miles northwest of Cedar Point, the 
southern tip of the western mainland shore of 
Mobile Bay. (See Coast and Geodetic Survey 
Chart 1267.) 
Previous projects. For details see Annual 
Report for 1945, page 844. 
Existing project. The authorized project 
provides for a 12-foot by 100-foot channel from 
the 12-foot depth in Mississippi Sound to a point 
about 2,800 feet south of the highway bridge, 
thence a channel 12 feet deep by 75 feet wide to 
the bridge, an overall distance of about 33,500 
feet, with the channel widened at a point 0.6 mile 
below the bridge to provide a turning basin 12 
feet deep and about 2.6 acres in area. Mean tidal 
range is 1.75 feet, and extreme, except during 
10-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
storms, is 3.75 feet. Plane of reference is mean low 
water. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Wooden wharves have been 
provided at seafood processing plants and public 
launching ramps are available. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: The contractor's dredge Everette 
Fisher, operating during the period 28 June to 18 
July, 1974 removed 342,050 cubic yards of 
material at a cost of $166,000. Additional contract 
work consisted of $1,427 for channel surveys, 
$6,175 for hydraulic studies and $270 for environmental 
studies. Hired labor costs amounted 
to $3,335 for channel surveys, $353 for environmental 
studies and $9,357 for engineering 
design, supervision and administration. 
Condition at end of fiscal year. The existing 
project was modified December 30, 1966 under 
the discretionary authority of the Chief of 
Engineers to include a turning basin. The project 
was completed in March 1967. Total Federal 
costs under existing project as of June 30, 1975 
were $311,095 for new work and $842,016 for 
maintenance, a total of $1,153,111. Contributed 
funds from local interests amount to $10,500. 
5. BILOXI HARBOR, MISS. 
Location. The project is located on Mississippi 
Sound in southeastern Mississippi, 32 miles by 
water west of Pascagoula Harbor, Mississippi, 
and 14 miles east of Gulfport Harbor, Mississippi 
(See Coast and Geodetic Survey Chart 1267.) 
Previous projects. For details see page 584, Annual 
Report for 1962. 
Existing project. The authorized project 
provides for a continuous channel 12 feet deep, 
150 feet wide and 23 miles long from the Gulf Intracoastal 
Waterway through Mississippi Sound 
east of Deer Island, Biloxi Bay, Back Bay, Cranes 
Neck, and a land cut to Gulfport Lake, including a 
500-foot by 2,600-foot basin in the lake, thence a 
12-foot deep by 100-foot wide channel for about 
two miles westward from the west end of the lake, 
terminating in a 300-foot by 500-foot basin; a 12- 
foot by 100-foot channel from the main channel in 
Big Lake to and up Bayou Bernard to the Air 
Force oil terminal at about mile 2.6; a 12-foot by 
150-foot spur channel from the main channel in 
Biloxi Bay for about one mile, terminating in a 
400-foot by 600-foot turning basin opposite Ott 
Bayou; a 12-foot by 150-foot lateral channel 
westward about 2.2 miles to Biloxi's south waterfront; 
a 10-foot by 150-foot channel from Mississippi 
Sound, passing west of Deer Island to a 
point where it connects to the 12-foot by 150-foot 
lateral channel at Biloxi's south waterfront. Construction 
for the modifications authorized by 
River and Harbor Act of Nov. 7, 1966 was commenced 
in FY 1974 and completed in Feb. 1975. 
Cost of modification as authorized by the 1966 
River and Harbor Act was $664,390. That portion 
of the project providing for an entrance channel 
six feet deep, 50 feet wide, and about 1,800 feet 
long into Old Fort Bayou, as authorized by the 
1945 River and Harbor Act, is inactive and excluded 
from the foregoing cost estimate. Estimated 
cost (1954) of this portion was $6,000. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of wooden 
piling-and-timber piers for small craft and 
fishing boats, a bulk gasoline terminal, several 
boat ways, and concrete products plant are 
available. 
Operations and results d i ut'/if fiscal year. New 
work: Channel dredging, engineering, design, 
supervision and administration cost $650,058. 
Maintenance: Completion of contract dredging 
reported on in FY 1974 cost $20,224. Other contract 
cost included $4,310 for channel surveys and 
$11,195 for hydraulic studies. Hired labor costs 
included $2,977 for channel surveys, $23,288 for 
engineering, design, supervision and administration; 
and, $303 for other miscellaneous costs, and 
$2,253 for project condition surveys. 
Condition at end of fiscal year. The existing 
project, prior to the modification authorized in 
1966, was commenced in 1931 and completed in 
1962. Total Federal costs under existing project 
as of June 30, 1975 were $909,773 for new work 
and $1,848,464 for maintenance, a total of 
$2,758,237. Contributed funds for new work 
amount to $73,427. 
6. BLACK WARRIOR AND TOMBIGBEE 
RIVERS, ALA. 
Location. Black Warrior River rises in 
northern Alabama above Birmingham and flows 
generally southwesterly to unite with the Tombigbee 
River at Demopolis, Alabama. Thence, the 
Tombigbee flows south, uniting with the 
Alabama River to form the Mobile River 45 miles 
above the head of Mobile Bay. Distance by water 
from Mobile to the vicinity of Birmingham is 
about 415 miles. 
Previous projects. For details see page 732, Annual 
Report for 1938. 
Existing project. The authorized project 
provides essentially for a canalized channel nine 
feet deep and 200 feet wide from the mouth of the 
Tombigbee River, 45 miles above Mobile, to the 
vicinity of Birmingham, via the Tombigbee and 
10-4

MOBILE, ALA., DISTRICT 
Black Warrior Rivers, to mile 430.4 on Sipsey 
Fork, mile 429.6 on Mulberry Fork and mile 
407.8 on Locust Fork, and for maintenance by 
snagging of Mobile River above the mouth of 
Chickasaw Creek, a total waterway distance of 
about 408 miles. The total lift of 257 feet is accomplished 
by six locks and dams. The original 
construction program, consisting of 17 dams with 
18 lifts, was completed in 1915. Replacement of 
the original structures with new locks and dams, 
under the modernization program is as follows: 
William Bacon Oliver replaced locks 10, 11, and 
12; Demopolis replaced locks 4, 5, 6, and 7; 
Warrior replaced locks 8 and 9; Coffeeville 
(Jackson) replaced locks 1, 2, and 3; and Holt 
replaced locks 13, 14, 15, and 16. Thus, 16 of the 
original locks have been replaced by five new 
locks. Bankhead Lock and Dam (Lock 17) is under 
rehabilitation to replace the existing double lift 
lock with a single lift lock. The Jackson Lock and 
Dam wildlife refuge, authorized in 1960, will include 
4,250 acres within the reservoir area and 
along its boundaries. (See Table 10-B for 
authorizing legislation.) 
Tidal influence extends upstream from Mobile 
101.6 miles to the old lock 1, where tidal effect is 
apparent only at low stages of the river. At Mobile 
the mean and extreme tidal ranges are 1.5 and 3.6 
feet, respectively. These are at times slightly increased 
by the effect of winds. The greatest fluctuation 
of river stages is at Demopolis, Ala., the 
maximum being 59.7 feet. Maximum fluctuations 
at other points are 40 feet at lock 1, 100.6 
miles from Mobile; 57.8 feet at Tuscaloosa, 346.1 
miles from Mobile; 13 feet at Birmingport, 404.9 
miles from Mobile; and 27 feet at Cordova, 424.3 
miles from Mobile. Ordinary fluctuations at these 
points are at old lock 1, 20 feet; at Demopolis, 35 
feet; at Tuscaloosa, 40 feet; at Birmingport, four 
feet; and at Cordova, seven feet. Works of improvement 
reduced the amount of fluctuations at 
different points by three to 10 feet. Estimated cost 
(1975) of new work is $125,311,000 exclusive of 
amounts expended on previous projects and 
recreation facilities. Additionally, estimated 
costs of major rehabilitations at John Hollis 
Bankhead Lock and Dam is $46,000,000, and cost 
of providing recreation facilities at completed 
projects (Code 710) is $902,300. 
Local cooperation. Requirements of local 
cooperation have been fully complied with to 
date. 
Terminal facilities. Docks, storage facilities, 
and handling equipment have been provided as 
required at most loading and unloading points 
along the waterway. These include facilities for 
handling petroleum and petroleum products, 
coal, ores, sand and gravel, pulpwood, manufactures, 
and various other commodities. While most 
terminal facilities are privately owned, many are 
available for use by the general public. Facilities 
are considered adequate for existing commerce. 
(See Table 10-C of existing locks and dams.) 
Operations and results during fiscal year. New 
work: 
John Hollis Bankhead Lock and Dam: 
Rehabilitation of lock and dam: Lands and 
damages cost $13,918; locks $9,173,423; permanent 
operating equipment $12,482; engineering, 
design, supervision and administration $506,823; 
miscellaneous and other costs $69,033. 
Warrior Lock and Dam: Recreational facilities 
provided at completed project (Code 711) cost 
$19,482. 
Recreational attendance at locks and dams during 
CY 1974 totaled 3,733,000 recreational user 
days. 
Maintenance: The U.S. pipeline dredge 
Collins, operating in Black Warrior and Tombigbee 
Rivers a total of 188 days, removed 
$2,548,120 cubic yards of material at a cost of 
$1,452,888. 
The U.S. Snagboat Ros, operating a total of 136 
days in Black Warrior and Tombigbee Rivers, 
removed 3,146 obstructions from the channel at a 
cost of $378,039. Cost of Environmental studies 
amounted to $52,023; Channel surveys, $133,924; 
hydraulic studies, $55,738; evaluation of completed 
structures, $92,135; transfer to National 
Weather Service, $60,700; land acquisition, 
$11,500; maintenance of radio communication 
equipment, $40,203; bank stabilization, $36,456; 
plant rental, $38,138; sedimentation studies, 
$31,246; miscellaneous plant utilization $30,887; 
resurfacing of roads $17,409; engineering, 
design, supervision and administration $56,021; 
and, miscellaneous and other costs $33,925. 
Credit to operation amounted to $3,815. 
Other maintenance costs for the system include: 
Jackson Lock and Dam, $137,354; 
Demopolis Lock and Dam, $139,104; Warrior 
Lock and Dam, $121,259; Oliver Lock and Dam, 
$210,098; Bankhead Lock and Dam, $364,600; 
Holt Lock and Dam, $260,345; and reservoir 
operation, $553,708. 
Condition at end of fiscal year. Work on the project, 
commenced in 1887, was essentially completed 
in 1915. Since then three of the original 
locks and dams (10, 11, and 12) were replaced by 
William Bacon Oliver (Tuscaloosa) Lock and 
Dam which was opened to navigation in August 
1939; four original locks and dams (4, 5, 6, and 7) 
were replaced by Demopolis Lock and Dam 
which was opened to navigation in August 1954; 
two original locks and dams (8 and 9) were replaced 
by Warrior Lock and Dam which was opened 
to navigation in October 1957; three original locks 
10-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
and dams (1, 2, and 3) were replaced by 
Coffeeville Lock and Dam which was opened to 
navigation in August 1960; and four original 
locks and dams (13, 14, 15, and 16) were replaced 
by Holt Lock and Dam which was opened to 
navigation in June 1966. Rehabilitation of the 
spillway at John Hollis Bankhead Lock and Dam 
commenced in 1966, and physically completed 6 
February 1970. Replacement of the double lift 
lock with a single lift lock at John Hollis 
Bankhead Lock and Dam commenced in April 
1970 and is scheduled for completion in FY 1976. 
The cost to June 30, 1975 for replacement of the 
lock was $43,447,057. The power plant at John 
Hollis Bankhead Lock and Dam was built and is 
operated by the Alabama Power Co. Total 
Federal costs under existing project as of June 30, 
1975 were $146,455,442 for new work and 
$62,892,563 for maintenance, a total of 
$209,348,005. 
7. DAUPHIN ISLAND BAY, ALA. 
Location. The project is located between 
Dauphin and Little Dauphin Island on the west 
side of the entrance to Mobile Bay, about 30 miles 
south of Mobile, Alabama and 55 miles west of 
Pensacola, Florida. (See Coast and Geodetic Survey 
Chart 1266.) 
Existing project. The authorized project 
provides for: (a) A channel seven feet deep and 
150 feet wide from Mobile Bay to an anchorage 
basin of the same depth, and about seven acres in 
area, in the marsh just north of Fort Gaines on 
Dauphin Island; a channel four feet deep and 40 
feet wide from the anchorage basin to Dauphin 
Island Bay; and a jetty and revetment to protect 
the entrance channel; and (b) an anchorage basin 
seven feet deep and 500 feet square at Dauphin 
Island Village, with an entrance channel of like 
depth, 100 feet wide and about 8,300 feet long, extending 
to the 7-foot hydrographic contour in 
Mississippi Sound. Mean tidal range is 1.1 feet, 
and extreme, except during storms is about four 
feet. Plane of reference is mean low water. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Requirement of local 
cooperation have been fully complied with to 
date. 
Terminal facilities. Several privately-owned 
wharves for handling seafood, a public dock and 
mooring slip, and a pier for recreational craft are 
located on the village basin. A marina, public 
launching ramp, and a number of private piers 
are located on the bay. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: The contractors dredge, Everette 
Fisher, operating during the period 31 July to 5 
August 1974 removed 55,605 cubic yards of 
material from Village channel at a cost of 
$70,000. Other contract costs included $2,966 for 
channel surveys and $260 for environmental 
studies. Hired labor costs included $2,704 for 
dragline work: $5,270 for channel surveys, $3,800 
for environmental studies, $3,417 for supervision 
and administration, $225 for miscellaneous and 
other costs and $110 for project condition surveys. 
Condition at end of fiscal year. The project was 
completed in July 1959. Total Federal costs under 
existing project as of June 30, 1975 were $292,565 
for new work and $406,096 for maintenance, a 
total of $698,661. 
8. DOG AND FOWL RIVERS, ALA. 
Location. Dog and Fowl Rivers are primarily 
tidal streams emptying into the west side of 
Mobile Bay, 8.5 and 17 miles, respectively, south 
of central Mobile. 
Existing project. The Dog River project 
provides for an 8-foot deep by 150-foot wide 
channel from about 3,000 feet east of the Mobile 
Bay ship channel to and up Dog River, a total distance 
of 26,200 feet, thence six feet by 100 feet for 
12,300 feet to a point about 2,400 feet above the 
mouth of Halls Mill Creek, and a 6-foot by 100- 
foot spur channel from the main channel to the 
mouths of Perch and Halls Mill Creeks. Overall 
length of the improvement is about 7.8 miles. 
The Fowl River project provides for a channel 
eight feet deep and 100 feet wide from Mobile Bay 
into and up Fowl River to deep water about 6,700 
feet above its mouth. Total length of the channel is 
about 2.6 miles. Plane of reference is mean low 
water. Mean range of tide is about 1.5 feet in Dog 
River. Extreme range during storms is about 3.6 
feet. This project was completed in November, 
1973. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Existing facilities consist 
of a boatyard for fabricating steel vessel hulls, 
nine marinas, four marine ways, a yacht basin on 
Dog River; two marinas on Fowl River, and 
numerous timber piers and docks on both rivers. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Disbursement of contributed funds amounted to 
$10,980. 
Condition at end of fiscal year. The existing 
project was commenced in August 1973 and completed 
in November 1973. Total Federal costs for 
new work on the existing project as of June 30, 
1975 were $190,695. Contributed funds for new 
work amounted to $70,100. Maintenance work 
was not performed in FY 1975. 
10-6

MOBILE, ALA., DISTRICT 
9. EAST PASS CHANNEL FROM 
GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FLA. 
Location. East Pass Channel is located in the 
entrance from the Gulf into Choctawhatchee Bay 
at eastern end of Santa Rosa Island, 48 miles east 
of the entrance into Pensacola Bay and 49 miles 
west of the new entrance to St. Andrews Bay. (See 
Coast and Geodetic Survey Chart 1264.) 
Previous project. For details see page 672 of Annual 
Report for 1937. 
Existing project. The authorized project 
provides for a 12-foot by 180-foot channel from 
the Gulf of Mexico into Choctawhatchee Bay, and 
a 6-foot by 100-foot channel from East Pass 
Channel into Old Pass Lagoon. The project consists 
also of two converging jetties spaced 1,000 
feet apart at the seaward end. The west jetty is 
provided with a low weir section 1,000 feet long to 
permit passage of littoral drift into a dredged 
deposition basin 500 feet by 1,500 feet located 
between the west jetty and the navigation 
channel. Mean range of tide is 1.3 feet; extreme 
range, except during storms, is 2.5 feet. Plane of 
reference is mean low water. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Responsibilities of local 
cooperation have been complied with to date. 
Terminal facilities. Small privately-owned 
pile-and-timber piers used in connection with the 
fishing industry in this locality are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Contract work for the year 
amounted to $3,800 for hydraulic studies. Hired 
labor cost included $71,699 for the removal of 
119,895 cubic yards of material from Lagoon and 
Entrance Channel, $7,600 for engineering, 
design, supervision and administration; and, 
$1,482 for miscellaneous and other costs. 
Condition at end of fiscal year. Construction of 
the 1965 modification was commenced October 
1967 and completed January 1969. Total Federal 
costs under existing project as of June 30, 1975 
were $916,715 for new work and $1,726,649 for 
maintenance, a total of $2,643,364. Contributed 
maintenance funds from local interests amount to 
$398,000. 
10. ESCAMBIA AND CONECUH 
RIVERS, FLA. AND ALA. 
Location. The river is a single stream which 
rises in central Alabama, flows southwesterly to 
the Florida State line, thence southerly through 
Florida to Escambia Bay, an arm of Pensacola 
Bay. That part of stream in Alabama is known as 
Conecuh River and that in Florida as the Escambia 
River. (See Coast and Geodetic Chart 1265.) 
Previous projects. For details see page 
Annual Report for 1961. 
Existing project. The project provides for a 10- 
foot wide by 100-foot deep channel in Escambia 
Bay for 5.5 miles to the mouth of Escambia River, 
thence up Escambia River to about mile 7, thence 
a channel five feet deep for 50.9 miles to the 
Florida State line, and thence improvement of 
Conecuh River to the mouth of Patsaliga Creek, a 
distance of 79.5 miles. The project, including the 
portion in Escambia Bay, is 142.5 miles long. 
Plane of reference is mean low water. Mean range 
of tide at the mouth of the river is 1.5 feet and extreme 
range, except during storms, is three feet. 
Ordinary seasonal fluctuation at the state line 
does not exceed eight feet. The highest flood stage 
on record (1919) was 31.3 feet at the state line and 
50.6 feet at River Falls, Alabama, 137.5 miles 
above the mouth. The existing project was completed 
in 1960 at a cost of $137,324. (See Table 10- 
B for authorizing legislation.) 
Local cooperation. Responsibilities of local 
cooperation have been fully complied with to 
date. 
Termin l facilitices. Chemstrand Corporation, 
at mile 7, provides a barge slip and facilities for 
handling and storing industrial chemicals and 
other materials received at their plant. Gulf 
Power Company, at mile 4, maintains a slip, 
marginal wharf, and facilities for handling coal. 
These facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Contract work amounted to $260 
for hydraulic studies. Hired labor cost included 
$199 for channel surveys, $438 for supervision 
and administration and $5,621 for project condition 
surveys. 
Condition at end of fiscal year. The existing 
project, prior to adoption of the modification 
authorized by the 1958 River and Harbor Act, 
was commenced in 1881 and completed in 1882. 
Construction of the modification authorized in 
the 1958 River and Harbor Act was commenced 
and completed in 1960. Total Federal costs under 
existing project as of June 30, 1975 were $137,324 
for new work and $291,090 for maintenance, a 
total of $428,414. 
11. GULF INTRACOASTAL 
WATERWAY BETWEEN 
APALACHEE BAY, FLA., 
AND MEXICAN BORDER 
(MOBILE DISTRICT.) 
Location. The project extends westward from 
Apalachee Bay, Florida, along the Gulf coast to 
the Rigolets, Louisiana, via a series of coastal 
10-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
lakes, bays, sounds, and land cuts. (For further 
details see Annual Report for 1962.) 
Previous projects. For details see page 906, Annual 
Report for 1930. 
Existing project. The authorized project 
provides for a waterway 12 feet deep and 125 feet 
wide at mean low water from Apalachee Bay, 
Florida, to Mobile Bay, Alabama, and 12 feet 
deep and 150 feet wide from Mobile Bay, 
Alabama, to the Rigolets, Louisiana (Lake 
Borgne Light No. 29), and for a tributary channel 
(Gulf County Canal), 12 feet deep, 125 feet wide 
and about six miles long connnecting Intracoastal 
Waterway at White City, Florida, with St. Joseph 
Bay. The waterway between the 12-foot depth 
contours in Apalachee Bay and Lake Borgne 
Light No. 29 at the Rigolets is 379 miles long. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Responsibilities of local 
cooperation have been fully complied with for the 
work authorized prior to 1966. For modification 
of the Gulf County Canal which was authorized by 
the 1966 River and Harbor Act, local interests 
must provide without cost to the United States all 
lands, easements, and rights-of-way required for 
construction and subsequent maintenance of the 
project and for aids to navigation, and provide 
retaining dikes, bulkheads, and embankments 
required in connection with disposal of spoil, or 
the costs of such retaining works; hold and save 
the United States free from all damages due to 
construction and maintenance of the project, including 
damages to wharves, piers, bridges, and 
other structures; provide and maintain at local 
expense adequate terminal and transfer facilities 
open to all on equal terms; provide and maintain 
without cost to the United States depths in 
berthing areas commensurate with depths 
provided in related project area; and accomplish 
without cost to the United States such alterations 
as required in sewer, water supply, drainage, and 
other facilities as well as their maintenance. 
Terminal facilities. Facilities are available for 
public use at Carrabelle, Apalachicola, Panama 
City, and Pensacola, Florida; Mobile and Bayou 
La Batre, Alabama; and Pascagoula, Biloxi, Gulfport, 
Pass Christian, and Bay St. Louis, Mississippi. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Carrabelle-ApalachicolaB ay section: 
Environmental studies cost $54,134 and 
engineering, design, supervision and administration 
cost $1,342. 
Apalachicola Bay - St. Andrew Bay section: 
Hired labor removed 501 obstructions at a cost of 
$81,848, performed channel surveys at a cost of 
$4,003 and constructed spoil dike for $1,174. 
Engineering, design, supervision and administration 
cost $247. 
St. Andrew Bay - Choctawhatchee Bay section: 
Contract cost amounted to $96,857 for bank 
stabilization. Hired labor cost dredging of 282,- 
466 cubic yards of material at a cost of $296,878, 
and $39,502 for snagging and clearing. Other 
hired labor costs included $15,651 for 
maintenance of radio communication equipment, 
$167,650 for placement of 1,500 tons of stone for 
bank stabilization, $9,778 for construction of spoil 
dike, $15,087 for channel surveys, $26,274 for 
engineering, design, supervision and administration, 
and $486 for miscellaneous cost. 
Pensacola Bay - Mobile Bay section: Contract 
work consisted of placement of 12,083 tons of 
stone protection at a cost of $744,933 and dredging 
of 13,699 cubic yards of material at a cost of 
$11,677. Channel survey cost $19,180 and field 
survey cost $6,226. Contract engineering and 
design amounted to $1,058. Hired labor costs for 
channel surveys and engineering and design 
amounted to $12,833. 
Mobile Bay - Rigolets section: Channel surveys 
cost $11,103. Supervision and inspection cost $94. 
Direct charges to Mobile Area Office cost $25,106 
and to Panama City Area Office the cost was 
$3,868. 
Condition at end of fiscal year. The existing 
project is complete except for the portion between 
Apalachicola Bay and St. Marks, Florida, which 
is deferred for restudy. Modification of the Gulf 
County Canal to provide a 12-foot by 125-foot 
channel was commenced July 1968 and completed 
June 1969. Total costs of the existing project 
to June 30, 1975, were $21,288,129, of which 
$6,434,694 was for new work and $14,853,435 for 
maintenance. 
12. GULFPORT HARBOR, MISS. 
Location. The project is located on Mississippi 
Sound in southeastern Mississippi, about 44 and 
90 miles by water west of Pascagoula Harbor, 
Mississippi, and Mobile Harbor, Alabama, 
respectively, and 78 miles east of New Orleans 
(via Gulf Intracoastal Waterway). (See Coast and 
Geodetic Survey Chart 1267.) 
Previous projects. For details see page 747, Annual 
Report for 1938, and page 995, Annual 
Report for 1948. 
Ex i.'t ing pr'ojct. The authorized project 
provides for: (a) A channel 32 feet deep, 300 feet 
wide, and about eight miles long across Ship 
Island Bar, a channel 30 feet deep, 220 feet wide, 
and about 11 miles long through Mississippi 
Sound, and an anchorage basin at Gulfport 30 feet 
deep, 1,320 feet wide, and 2,640 feet long; and (b) 
maintenance of the existing commercial small- 
10-8

MOBILE, ALA., DISTRICT 
boat harbor about 26 acres in area, and a straightapproach 
channel, 100 feet wide and about 4,300 
feet long, from deep water in Mississippi Sound to 
a small-boat basin, all at a depth of eight feet. Under 
ordinary conditions mean tidal range is about 
1.75 feet, and extreme range, except during 
storms, is about 3.5 feet. Plane of reference is 
mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation . Conditions of local cooperation 
have been fully complied with to date. 
Tetr iral jacilitics. Existing modern 
railconnected terminal facilities at this port are 
considered adequate for existing commerce. (See 
Port Series 19, revised in 1969.) 
Operations a l(dl results duIring! fiscal year. 
Maintenance: The contractor's dredge, Duplex, 
operating during the period 1 July to 28 October 
1974, removed 4,313,353 cubic yards of material 
from the Sound Channel and Anchorage Basin at 
a cost of $913,828. Additional contract work consisted 
of $63,855 for special studies, $302 for 
channel surveys, $8,075 for hydraulic studies and 
$26,177 for engineering and design relative to the 
hopper dredging. Hired labor costs consisted of 
removing 123,253 cubic yards of material by 
hopper dredging from the Outer Bar channel 
during the period 16 February to 15 March 1975; 
$34,392 for channel surveys; $1,033 for environmental 
studies; $5,750 for maintenance of 
radio equipment; $603 for miscellaneous equipment 
and furniture; 22,393 for engineering and 
design and $18,846 for supervision and administration. 
Condition at end of fiscal year. Main harbor 
was commenced 1932 and completed April 1950. 
Maintenance for small boat harbor and approach 
channel, constructed by local interests in 1950 
was authorized by 1958 River and Harbor Act. 
Total Federal costs under existing project as of 
June 30, 1975 were $635,758 for new work and 
$13,021,991 for maintenance, a total of 
$13,657,749. 
13. MOBILE HARBOR, ALA. 
Location. The project is located along the lower 
five miles of Mobile River, in southwestern 
Alabama, 91 miles by water west of Pensacola 
Harbor, Florida, 90 miles east of Gulfport Harbor, 
Mississippi, and 144 miles by water 
northeast of mouth of Mississippi River. (See 
Coast and Geodetic Survey Chart 1266.) 
Precious projects. For details see page 503, Annual 
Report for 1963. 
Existing project. The authorized project 
provides for: (a) A 42-foot by 600-foot channel 
about 1.5 miles long across Mobile Bay; (b) a 40- 
foot by 400-foot channel in Mobile Bay to mouth of 
Mobile River; (c) a 40-foot channel in Mobile 
River to highway bridge, varying from 500 to 775 
feet wide; (d) a 25-foot channel from highway 
bridge to and up Chickasaw Creek to a point 400 
feet south of mouth of Shell Bayou, widths being 
500 feet in Mobile River and 250 feet in 
Chickasaw Creek; (e) a turning basin 40 feet deep, 
2,500 feet long, and 800 to 1,000 feet wide, opposite 
Alabama State Docks; (f) a turning basin 
40 feet deep, 800 feet wide, and 1,400 feet long opposite 
Magazine Point; (g) a 27-foot by 150-foot 
channel from Mobile Bay Channel along 
Arlington pier to a turning basin 800 feet long 
and 600 feet wide opposite Brookley Air Force 
Base ocean terminal, and continuing thence to a 
turning basin 250 feet wide and 800 feet long in 
Garrows Bend, thence a 22-foot by 150-foot 
channel to the causeway linking McDuffie Island 
to the mainland; (h) a channel 40 feet deep and 400 
feet wide from the main ship channel in Mobile 
Bay and extending northwesterly for about 5.3 
miles to the shore of Mobile Bay, thence a land cut 
40 feet deep, 300 feet wide and 1.9 miles long to 
and including a turning basin 40 feet deep, 300 
feet wide, and 1,200 feet long; and (i) maintenance 
of Three Mile Creek by snagging, from its intersection 
with Industrial Canal to Mobile River. 
The project provides also for an anchorage area 
32 feet deep, 100 feet wide, and 2,000 feet long opposite 
site formerly occupied by the U.S. Quarantine 
Station at McDuffie (Sand) Island. Prior to 
widening the Mobile Bay Channel as authorized 
in 1954, the Quarantine Station anchorage area 
was maintained to a project width of 200 feet. 
Construction by local interests of a solid-fill 
causeway across Garrows Bend Channel between 
McDuffie Island and the mainland is also provided 
for under existing project. Total length of the 
bay and river channels is about 41.7 miles. Plane 
of reference is mean low water. Under ordinary 
conditions mean tidal range at the lower end of 
the improvement is 1.2 feet and at the upper end 
1.5 feet. Extreme tidal range is 3.4 feet at the 
lower end and 3.6 feet at the upper end. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Requirements of local 
cooperation have been fully complied with to 
date. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate 
for existing commerce. (See Port Series No. 
18, revised in 1970.) 
Operations and results duringfiscal year. New 
work: Engineering and design of Theodore 
Channel cost $230,340. 
Maintenance: The contractor dredge Orleans, 
performing maintenance dredging from 
Bankhead Tunnel to Mobile River Bridge, during 
10-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
the period 7 July to 21 October 1974 removed 1,- 
627,054 cubic yards of material and the contractor 
dredge Paul F. Jahncke, removed 612,203 
cubic yards from Mobile Bay during the period 30 
May to 30 June 1975 at a cost of $1,361,027. Other 
contract costs consisted of $64,630 for channel 
surveys, $5,660 for environmental studies, $21,- 
500 for hydraulic studies, $53,630 for special 
studies and $2,757 for engineering and 
design. Hired labor costs consiLed of $452,059 for 
the removal of 550,255 cubic yards of material 
from the Outer Bar channel by hopper dredge 
between the period of 24 July 1974 to 28 February 
1975; $144,962 for maintenance of radio equipment, 
$91,474 for channel surveys, $35,463 for environmental 
studies, $55,181 for special studies, 
$3,428 for miscellaneous and other costs, $58,149 
for engineering and design and $150,680 for 
supervision and administration. In addition there 
was a credit to operation for $3,927. 
Condition at end of fiscal year. The existing 
project was commenced in 1931 and completed in 
July 1965. For details see Annual Report for 1965. 
Total Federal costs under existing project as of 
June 30, 1975 were $8,101,298 for new work and 
$24,856,294 for maintenance, a total of 
$32,957,592. Contributed funds for maintenance 
amount to $12,000. 
14. PANAMA CITY HARBOR, FLA. 
Location. The project is located on the 
northwest coast of Florida, 102 miles east of entrance 
to Pensacola Harbor. (See Coast and 
Geodetic Survey Chart 1263.) 
Previous project. For details see page 710, Annual 
Report for 1938. 
Existing project. The authorized project (as 
modified) provides for a channel about 3.7 miles 
long extending from deep water in the bay 
(intersection of Bay Harbor and Dyers Point 
Channel) across Lands End to the Gulf of Mexico, 
300 feet wide and 40 feet deep in the bay and 
across Lands End, and 450 feet wide, 42 feet deep 
and about 1.1 miles long in the approach channel 
in the Gulf, protected by two jetties, each about 
700 feet long; branch channels 38 feet deep and 
300 feet wide, leading from the inner end of the 
main entrance channel westward to the Port 
Authority terminal at Dyers Point and eastward 
to the Bay Harbor terminal, about 3.4 and 3.6 
miles in length, respectively; turning and 
maneuvering areas comprising about 55 acres opposite 
Dyers Point, and 42 acres opposite Bay 
Harbor, both at a depth of 38 feet; and an anchoring 
and loading basin for LASH type intermodal 
carriers, 40 feet deep and containing about 177 
acres in St. Andrew Bay near the inner end of the 
main entrance channel; a channel in Watson 
Bayou, 100 feet wide and 10 feet deep from that 
depth in St. Andrew Bay to the highway bridge, 
about 1.75 miles. The east and west jetties have 
been reworked and are presently about 2,075 and 
2,700 feet long, respectively. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Available terminal 
facilities are considered adequate for existing 
commerce. (See Port Series No. 19, revised in 
1969.) 
Operations and results during fiscal year. New 
work: Engineering and design for recentlyauthorized 
change in project dimensions cost 
$55,451. 
Maintenance: Hydraulic studies by contract 
amounted to $140. Hired labor costs amounted to 
$133 for channel surveys; $3,594 for project condition 
surveys and $13 for supervision and administration. 
Condition at end of fiscal year. The existing 
project (prior to modifications) was completed in 
November 1949. Repairs to jetties were commenced 
in June 1961 and completed October 
1968. Total Federal costs under existing project 
as of June 30, 1975 were $1,281,620 for new work 
and $3,126,969 for maintenance, a total of 
$4,408,589. 
15. PASCAGOULA HARBOR, MISS. 
Location. The project is located along lower 6.8 
miles of Pascagoula River, the lower six miles of 
Dog River, and in Bayou Casotte (about four miles 
east of the mouth of Pascagoula River), in 
southeastern Mississippi, about 61 miles by water 
west of Mobile Harbor, Alabama, and about 44 
miles by water east of Gulfport Harbor, Mississippi. 
(See Coast and Geodetic Survey Chart 
1267.) 
Previous projects. For details see page 741, Annual 
Report for 1938. 
Existing project. The authorized project 
provides for (a) An entrance channel 40 feet deep 
and 350 feet wide from the Gulf of Mexico 
through Horn Island Pass, including an impounding 
area for littoral drift, 40 feet deep, 200 feet 
wide, and about 1,500 feet long adjacent to the 
channel at the west end of Petit Bois Island; (b) a 
channel 38 feet deep and 350 feet wide in Mississippi 
Sound and Pascagoula River to the 
railroad bridge at Pascagoula, including a turning 
basin 2,000 feet long and 950 feet wide 
(including channel area) on the west side of the 
river below the railroad bridge; (c) a channel 38 
feet deep and 225 feet wide from the ship channel 
in Mississippi Sound to the mouth of Bayou 
Casotte, thence 38 feet deep and 300 feet wide for 
about one mile to a turning basin 38 feet deep, 
10-10

MOBILE, ALA., DISTRICT 
1,000 feet wide, and 1,750 feet long; (d) a 22-foot 
deep by 150-foot wide channel up Pascagoula 
River from the railroad bridge to the mouth of 
Dog River, thence up Dog River to Highway 63 
bridge; and (e) a 12-foot by 125-foot channel from 
the highway bridge, via Robertson and Bounds 
Lakes, to mile 6 on Dog River. Under ordinary 
conditions mean tidal range is 1.75 feet, and extreme 
range is 3.75 feet. Plane of reference is 
mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminalf c ilities. Modern rail-connected terminal 
facilities at this port are considered adequate 
for existing commerce. (See Port Series No. 
19, revised in 1969.) 
Operatiouns and results during fiscal year. 
Maintenance: The contractor's dredge, C.S.E. 
Paul F. Jalbc ke, performed maintenance dredging 
during the period 15 January to 11 March 
1975, and removed 814,753 cubic yards of 
material at a cost of $439,000. Other contract cost 
amounted to $23,440 for special studies, $6,688 
for channel survey, $13,500 for hydraulic studies 
and $5,186 for engineering and design. Hired 
labor costs amounted to $204,197 for removal of 
454,407 cubic yards of material by hopper dredging 
from the Outer Bar channel; $3,256 for environmental 
studies; $668 for special studies; 
$19,584 for channel surveys; $4,600 for 
maintenance of radio equipment; $1,337 for miscellaneous; 
$36,866 for engineering and design; 
and, $122,177 for supervision and administration. 
Condition at ,end of fiscal year. The existing 
project was completed in August 1965. Total 
Federal costs of existing project to June 30, 1975 
were $5,668,543 for new work and $9,550,898 for 
maintenance, a total of $15,219,941. Contributed 
funds for maintenance amounted to 190,100. 
16. PASS CHRISTIAN HARBOR, MISS. 
Locatioun. The project is on Mississippi Sound in 
southeastern Mississippi, nine miles west of Gulfport 
Harbor, Mississippi, and 68 miles east of 
New Orleans, Louisiana (via Gulf Intracoastal 
Waterway). (See Coast and Geodetic Survey 
Chart 1268.) 
Existing project. The authorized project 
provides for maintenance of a harbor within existing 
bulkheads and breakwaters constructed by 
local interests, and maintenance of an entrance 
channel, both to a depth of seven feet. The entrance 
channel is 100 feet wide and the harbor is 
about 1,000 feet along the shore by 700 feet wide. 
Mean range of tide is 1.75 feet and extreme range 
is 3.5 feet. Plane of reference is mean low water. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Available facilities consist 
of wooden piers for recreational and commercial 
small craft, public launching ramp, and two 
public docks with electric hoists. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Completion of contract dredging 
previously reported on in FY 1974 cost $30,249. 
Other work performed by contract included $140 
for hydraulic studies. Hired labor costs for 
engineering, design, supervision and administration 
amounted to $971. 
Condition at end of fiscal year. The existing 
project was completed in June, 1959. Total 
Federal costs of existing project to June 30, 1975 
were $59,319 for new work and $123,966 for 
maintenance, a total of $183,285. 
17. PEARL RIVER, MISS. AND LA. 
Location. Pearl River rises in east central Mississippi 
and flows southwest about 172 miles to 
Jackson, Mississippi, thence southeast about 269 
miles to the head of its delta, whence West Pearl 
River flows about 34 miles to the Rigolets, a tidal 
pass connecting Lake Pontchartrain with Lake 
Borgne, an arm of the Gulf of Mexico. 
Previous projects. For details see page 750, Annual 
Report for 1938 and page 463, Annual 
Report for 1965. 
Existing project. The authorized project 
provides for a channel from the mouth of West 
Pearl River for 58 miles to the mouth of Bogalusa 
Creek at Bogalusa, Louisiana, seven feet deep at 
low water with a bottom width of 100 feet in the 
river sections and 80 feet in the canal section; with 
locks 65 by 310 feet clear inside dimensions. The 
plan of improvement may be divided into three 
sections as follows: the river section from the 
mouth of West Pearl River to mile 28.5 at Holmes 
Bayou with a channel seven feet deep and 100 feet 
wide to be obtained by dredging, snagging, and 
construction of cutoffs and easement of critical 
bends at eight locations below lock one along 
Pearl River in its reach from its mouth to mile 26, 
all at a depth of seven feet; the canal section from 
mile 28.5 to 48.7 at Pools Bluff with a channel 
seven feet deep and 80 feet wide to be obtained by 
construction of three locks in the canal with sills 
across Bogue Chitto at mile 44 and across the 
river at mile 48.7; the river section from mile 48.7 
to 58 at the mouth of Bogalusa Creek to be obtained 
by dredging, snagging and easing of 
bends. At Bogalusa the mean variation of water 
surface is 10 feet and extreme, 23 feet. Plane of 
reference is mean low water. 
Estimated cost of the project (1974) is 
$9,334,494 including $8,274,494 for im- 
10-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
provements completed prior to 1966, and 
$1,060,000 for modifications authorized by the 
1966 River and Harbor Act. Estimated (1975) 
cost for providing recreational facilities (Code 
710 is $222,200. (See Table 10-D for features of 
locks included in existing projects.) 
Local cooperation. Fully complied with. 
Terminal facilities. The city of Bogalusa 
provides a barge terminal consisting of a wharf, 
transit shed, and access road at Richardson's Landing 
at the head of the project. A privately-owned 
wharf at the Pearl River Highway Bridge near 
Pearl River Station, Louisiana, is used for unloading 
logs. Only natural landings exist at 
various locations on the river. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Work performed under contract 
included $6,650 for hydraulic studies and $8,429 
for environmental studies. Hired labor costs included 
$17,940 for channel surveys, $4,331 for environmental 
studies, $5,819 for maintenance of 
locks, $10,400 transfer to National Weather Service, 
$4,007 for hydraulic studies, $2,965 for project 
utilities, $2,145 for miscellaneous, less credit 
to operation of $1,786. In addition, specific costs 
for various lock operations amounted to $38,357 
for Lock No. 1, $7,626 for Lock No. 2 and $16,371 
for Lock No. 3. 
Condition at end of fiscal year. The existing 
project, prior to adoption of modifications 
authorized by the 1966 River and Harbor Act, 
was commenced in October 1938 and completed 
in January 1956. All locks were opened to navigation 
in November 1953. No work has been initiated 
on modifications (cut-offs and easements 
of bends below Lock 1) authorized by the 1966 
Act. Total Federal costs under existing project as 
of June 30, 1975 were $8,418,465 for new work 
and $3,531,780 for maintenance, a total of 
$11,950,245. Contributed funds for new work 
amount to $65,000. 
18. PENSACOLA HARBOR, FLA. 
Location. The project is located in a landlocked 
bay on the coast of northwest Florida about 50 
miles east of the entrance to Mobile Bay. (See 
Coast and Geodetic Survey Charts 490 and 1265.) 
Preiows projects. For details see Annual 
Report for 1938. 
Existing project. The authorized project 
provides for: (a) A 35-foot by 500-foot entrance 
channel about five miles long, from the Gulf of 
Mexico to lower Pensacola Bay; (b) a 33-foot by 
300-foot bay channel; (c) two 33-foot by 300-foot 
parallel approach channels to opposite ends of the 
inner-harbor channel; (d) an inner-harbor 
channel 500 feet wide, 33 feet deep, and 3,950 feet 
long; (e) a 30-foot by 250-foot approach channel to 
the pierhead line south of Muscogee wharf; and (f) 
a 15-foot by 100-foot entrance channel into Bayou 
Chico, thence a channel of 14 feet deep, 75 feet 
wide, and about 4,400 feet long to a turning basin 
14 feet deep and 500 feet square. Me range of tide 
throughout the harbor is about 1.1 feet near the 
entrance and about 1.6 feet at the head of bay. Extreme 
tidal range, except during storms, is about 
three feet. Plane of reference is mean low water. 
Modification of the Bayou Chico project to 
provide for enlarging the entrance channel to 21 
by 100 feet, the bayou channel to 20 by 100 feet, 
and deepening the turning basin to 20 feet has 
been deferred for restudy. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Termnal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate 
for existing commerce. (See Port Series No. 
19, revised in 1969.) 
Operations and results during fiscal year. 
Maintenance: Work performed under contract 
included $2,250 for environmental studies and 
$5,700 for hydraulic studies. Hired labor costs included 
the removal of 343,481 cubic yards of 
material by the hopper dredge Gehrig from the 
Outer Bar channel during the period 31 January 
to 14 February 1975 at a cost of $180,859, $14,078 
for the maintenance of radio equipment, $22,799 
for channel surveys, $2,248 for environmental 
studies, $378 for miscellaneous, $576 for 
engineering and design, $1,682 for supervision 
and administration, and $1,179 for project condition 
surveys. 
Condition at end of fiscal year. New work is 
completed except those features which are 
deferred for restudy. The modification authorized 
in 1962 was commenced in March and completed 
in May 1965. Total Federal costs of the existing 
project to June 30, 1975 were 875,005 for 
new work and $3,178,226 for maintenance, a total 
of $4,053,231. 
19. PERDIDO PASS CHANNEL, ALA. 
Location. The project is located about midway 
between Pensacola, Florida and Mobile, 
Alabama. (See Coast and Geodetic Chart 872.) 
Existing project. The existing project provides 
for a channel 12 feet deep and 150 feet wide for 
about 1,300 feet from the Gulf of Mexico into the 
inlet, thence nine feet deep and 100 feet wide for 
about 2,200 feet to the highway bridge, where the 
channel branches into two arms, each having 
dimensions of 9 by 100 feet, one of which extends 
about, 3,400 feet into Terry Cove and the other 
about 3,200 feet into the southern arm of Perdido 
10-12

i MOBILE, ALA., DISTRICT 
Bay. The project also provides for two jetties spaced 
600 feet apart at the seaward end. The east jetty 
has a low weir section 1,000 feet long to permit 
passage of littoral drift into a dredged deposition 
basin 800 feet by 1,200 feet located between the 
east jetty and the navigation channel. (See Table 
10-B for authorizing legislation. 
Local cooperation. Requirements of local 
cooperation have been fully complied with to 
date. 
Terminal facilities. Six marinas, numerous 
timber piers, docks, and several launching ramps 
are available. These facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Completion of contract dredging 
previously reported on in FY 1974 cost $173,507. 
Other contract work included $402,261 for 
rehabilitation of jetties, $3,352 for channel survey, 
$8,114 for hydraulic studies, $2,000 for excavation 
and $2,460 for engineering and design. 
Hired labor costs amounted to $2,578 for channel 
surveys. $192 miscellaneous cost, $5,364 for 
engineering and design and $16,674 for supervision 
and administration. 
Condition at end of fiscal year. The existing 
project was commenced in May 1968 and completed 
in March 1969. Total Federal costs of the 
existing project to June 30, 1975 were $629,860 
for new work and $1,901,812 for maintenance, a 
total of $2,531,672. Contributions from local interest 
amount to $510,000 for new work and 
$10,325 for maintenance. 
20. REMOVING WATER HYACINTH, 
MOBILE DISTRICT 
Location. The project is for all streams 
tributary to the Gulf Coast in Mobile District. 
Existing project. The authorized project 
provides for extermination or removal of plants 
from navigable waters of Florida, Alabama, Mississippi, 
Louisiana, andTexas, so far as they are or 
may become an obstruction to commerce, by any 
mechanical, chemical, or other means whatsoever; 
for construction and operation of boats 
equipped with suitable machinery for such 
removal, and construction and operation of log 
booms to prevent plants drifting from one stream 
to another. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. The 
U.S. spray plant and hired labor operations along 
the Mobile Delta from July 1 to December 16, 
1974 sprayed the following streams: Apalachee 
River, Big Bay John, Big Briar Creek, Big Catfish 
Bayou, Big Lizzard Creek, Blakley River, 
Chicory Creek, Dead Lake, Duck's Bayou, Jim's 
Creek, Little Bay John, Little Bay Torro, Little 
Briar Creek, Louis Creek, Lower Crab Creek, 
Maple Creek, McVoys Lake, Mifflin Lake, Mike's 
Creek, Mudhole Creek, Negro Lake, One Mile 
Creek, Owl Creek, Railroad Creek, Smith Bayou, 
Tensaw River and Williams Creek, all at a cost of 
$29,444. 
Condition at end of fiscal year. The existing 
project, which is for maintenance, was commenced 
about 1899, and work has been carried on since 
that time. Total Federal costs for the project 
through June 30, 1975 amount to $901,939. 
21. WATERWAY CONNECTING 
TOMBIGBEE AND TENNESSEE 
RIVERS, ALA. AND MISS. 
Locatioin. The waterway extends from mile 215 
in Pickwick pool on the Tennessee River, southerly 
through northeastern Mississippi and western 
Alabama, a total of 253 miles, to the confluence of 
the Black Warrior and Tombigbee Rivers at 
Demopolis, Alabama. 
Pr'e ci ots Jprojccts. For details see Annual 
Report for 1953. 
Ex.ristig project. The authorized project 
provides for a waterway 253 miles long, connecting 
the Tennessee and Tombigbee Rivers via the 
East Fork of Tombigbee River and Mackeys and 
Yellow Creeks. The plan of improvement consists 
of three sections: (1) the river section, a 9-foot by 
300-foot channel for 168 miles between 
Demopolis and Amory, Mississippi; (2) the lateral 
canal section, 12 feet by 300 feet for 45 miles from 
Amory to Bay Springs; and (3) the divide section, 
a 12-foot by 300-foot channel (except in the 27 
mile-long divide cut in which the bottom width 
would be 280 feet) for 40 miles from Bay Springs 
through the dividing ridge to the Tennessee 
River; the total lift of 341 feet to be accomplished 
by 10 locks. Estimated (1975) Federal cost for 
new work is $1,210,000,000, including $325,000 
for work by the U.S. Coast Guard, plus 
$130,100,000 non-Federal cost for relocations. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Local interests must make 
and maintain alterations in highways and 
highway bridges and in sewer, water-supply, and 
drainage facilities and provide and maintain 
suitable and adequate river and canal terminals. 
Officials of the State of Mississippi were notified 
of these requirements on December 13, 1949, and 
officials of the State of Alabama were notified on 
December 20, 1949. Legislation enabling boards 
of supervisors of the various counties concerned to 
enter into agreements with the United States 
relative to navigation projects was adopted by the 
State of Mississippi in 1950. A compact between 
the States of Alabama, Mississippi, Tennessee, 
10-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Kentucky, and Florida has been formed for the 
purpose of promoting the project. The name of 
this organization is the Tennessee- Tombigbee 
Waterway Development Authority. 
During its 1962 session the Mississippi 
Legislature authorized the formation of the Tombigbee 
River Valley Waterway Management District. 
The District was organized in accordance 
with the enabling legislation and is empowered to 
fulfill the requirements of local cooperation for 
the portion of the project in Mississippi. A 
satisfactory resolution has been furnished. During 
its 1967 session the Alabama Legislature 
authorized formation of a public corporation to be 
named the Tombigbee Valley Development 
Authority for the purpose of further development 
of the Tombigbee River and tributary streams. 
The organization was formed in accordance with 
the enabling legislation and in a referendum held 
5 December 1967 the voters of Alabama authorized 
a bond issue not to exceed $10,000,000 to 
finance participation in this project and the Tombigbee 
River and Tributaries project. A satisfactory 
resolution has been furnished. 
Terminal facilities. None. 
Operations and results during fiscal year. New 
work: Total cost of new work during the fiscal 
year was $35,831,936, of which $20,621,345 was 
for work performed at Gainesville Lock and Dam; 
$2,067,081 at Demopolis Lake, $4,808,377 at 
Aliceville Lock and Dam; $2,422,716 at Columbus 
Lock and Dam, $1,317,167 at Aberdeen Lock and 
Dam. Canal Section cost included: Lock A, 
$1,067,636; Lock B, $1,170,661; Lock C, $612,007; 
Lock D, $311,031; Lock E, $392,205. Additionally, 
environmental impact studies cost $1,030,328 
and Tennessee Tombigbee Waterway Area Office 
costs amounted to $11,382. 
Condition at end of fiscal year. Total Federal 
costs under the existing project as of June 30, 
1975 were $61,324,705 for new work. Construction 
formally began December 12, 1972 and 
overall project is about five percent complete. 
22. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 10-E.) 
23. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 10-F.) 
24. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645, as amended (Preauthorization). 
Fiscal year cost for preauthorization 
studies were: $3,434 for Fanning Bayou, Bay 
County, Florida; $8,838 for Bayou La Batre 
Feeder Channel and $4,100 for Mobile- 
McIntosh Barge Channel, both in Alabama; 
$1,384 for Eastpoint and $398 for St. George 
Island, both in Apalachicola Bay, Florida; and, 
$4,006 for Cadet Bayou, Mississippi. 
Beach Erosion Control 
25. AUTHORIZED BEACH EROSION 
CONTROL PROJECT 
(See Table 10-G.) 
Flood Control 
26. JACKSON AND EAST JACKSON, 
MISS. 
Location. The project is on the Pearl River at 
Jackson, Mississippi, about 278 miles above 
mouth of the river. 
Existing project. The project provides for improvement 
of Pearl River at Jackson, Mississippi, 
for flood control, and includes two levee systems 
totaling 69,080 feet in length, with four gated outlets; 
two pumping stations; and 5.34 miles of 
channel rectification, including three cut-offs 
with a total length of 2.2 miles in the Pearl River. 
Estimated cost (1975) is $7,130,400 excluding 
$718,000 non-Federal contributions. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Engineering, design, supervision and administration 
cost $28,005. 
Condition at end of fiscal year. Construction 
began in July 1964 and all contract work was 
completed during fiscal year 1968. Work remaining 
to be done consists of continuing studies. 
Work on Prairie Branch Canal bank protection 
was completed in October 1968. Total Federal 
costs of the existing project as of June 30, 1975 
were $7,082,831, all for new work. Contributions 
from local interests amount to $718,000, for new 
work. 
27. OKATIBBEE LAKE, MISS. 
Location. The project is located on Okatibbee 
Creek 37.7 miles above its mouth, in Lauderdale 
County, Mississippi, seven miles northwest of 
Meridian. 
Existing project. The project provides for a dam 
and reservoir for flood control, water supply, 
water quality control, fish and wildlife, and 
recreation. The dam consists of a compacted 
earth fill 6,540 feet long with the top elevation 
10-14

MOBILE, ALA., DISTRICT 
369.8 feet above mean sea level, with top width of 
18 feet. The spillway, which is located 1,500 feet 
east of the east end of the dam, is an unpaved free 
overflow type 1,500 feet long with a fixed crest at 
elevation 359. A sluice intake structure near the 
center of the dam serves two 6.5-foot diameter 
concrete conduits. Storage allocated for water 
supply and water quality control varies seasonally 
from 21,400 acre-feet to 34,300 acre-feet 
between a minimum elevation of 328 and top-ofconservation 
pool elevation varying from 339 to 
343. Storage varying from 46,500 acre-feet to 
59,500 acre-feet between the top of the conservation 
pool and elevation 352 has been reserved exclusively 
for storage of flood waters. Cost of construction 
for initial project completed in FY 1973 
was $9,020,300. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Complied with to date. 
Operations and results during fiscal year. 
Maintenance: Environmental and water quality 
studies cost $12,050; hydraulic studies, $5,808; 
reservoir regulation studies, $7,802; maintenance 
of public use facilities, $19,395; utilities, $8,657; 
administration facilities, $17,636; permanent 
operating equipment, $25,714, engineering and 
design, $3,848; supervision and administration, 
$73,721; and, miscellaneous and other costs 
amounted to $27,861. Rains in headwater areas 
during December 1974, January and February 
1975, resulted in rises in pool elevations a maximum 
of 6.0 feet and a total impounding of 58,800 
acre feet. Natural stages at Arundel were reduced 
as much as 2.9 feet. Natural stages at Meridian 
were reduced 7.3 feet and at Enterprise 2.6 feet. 
Due to flood control the reduction in flood losses 
was estimated to be $68,900 to rural properties. 
Recreation attendance at the reservoir during CY 
1974 totaled 796,100 recreational user days. 
Condition at end of fiscal year. Construction 
began in June 1965, and was completed in 
November 1968. 
28. TALLAHALA CREEK LAKE, 
PASCAGOULA RIVER, MISS. 
Location. The project is on Tallahala Creek, 
81.1 miles above its mouth, in Jasper County, Mississippi, 
13 miles north of Laurel. 
Existing project. The project provides for a dam 
and reservoir for flood control, water supply, 
water quality control, recreation, and fish and 
wildlife enhancement. The dam will consist of a 
compacted earth fill 8,000 feet long, with top 
elevation 343.5 feet above mean sea level, or a 
maximum of 71.5 feet above streambed elevation, 
with a top width of 18 feet, and a 300-foot long saddle 
dike with maximum height of 15 feet in the 
left abutment. The spillway which is 6,000 feet 
northeast of the left abutment, will consist of an 
unpaved, free-overflow type, 500 feet long, with 
fixed crest at elevation 335.0. A sluice intake 
structure near the center of the dam will serve an 
8-foot diameter, horseshoe-shaped concrete conduit. 
The reservoir at maximum pool elevation 
306.5 will have an area of 4,900 acres and a total 
capacity of 63,000 acre-feet of which 35,900 acrefeet 
between elevations 288.5 and 302.0 will be 
used for water supply, 20,000 acre-feet between 
elevations 302.0 and 306.5 will be used for water 
quality improvement, and 7,100 acre-feet below 
elevation 288.5 will consist of dead storage. A 
volume varying seasonally from 50,000 to 70,000 
acre-feet between elevations 306.5 and 315.0 will 
be reserved for flood storage. Estimated cost 
(1975) is $39,500,000 excluding $3,066,000 non- 
Federal contributions. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Local interests must: reimburse 
the United States one-half the separable 
first cost of the project allotted to general recreation 
and fish and wildlife enhancement, and bear 
all costs of operation, maintenance, and 
replacements therefor, and administer land and 
water areas of the project allocated to recreation 
and fish and wildlife enhancement; reimburse 
the United States' construction cost, and bear all 
annual operation and maintenance costs 
allocated to water supply; prevent encroachment 
and obstruction of downstream channels that 
would adversely affect operation of the project; 
and comply with and enforce conditions relating 
to water quality control in Tallahala Creek as 
stipulated by the Corps of Engineers with the advice 
of the Department of Health, Education, and 
Welfare. Resolutions by the Pat Harrison 
Waterway District October 28, 1965, and 
January 27, 1966, and by the City Council of 
Laurel October 20, 1965 indicated willingness for 
complying with requirements of local cooperation. 
Operation and results during fiscal year. New 
work: Lands and damages cost $1,238; engineering, 
design, supervision and administration, cost 
$245,437. 
Condition at end of fiscal year. Construction has 
not been initiated. 
29. EDINBURG LAKE, PEARL RIVER, 
MISS. 
Location. The project would be located on Pearl 
River about two miles east of Edinburg, Mississippi, 
and about 130 river miles above Jackson, 
Mississippi. 
Existing project. The project provides for a dam 
and reservoir for flood control, water quality control, 
general recreation, fish and wildlife 
10-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
enhancement, and area redevelopment. The dam 
will consist of a compacted earth-fill and concrete 
structure 7,154 feet long including spillway section 
and retaining walls. The top of dam elevation 
would be 412.5 feet above mean sea level with a 
maximum height of 54 feet above the existing 
stream bed. Top width of dam would be 32 feet. 
The gated spillway would have a length of 292 
feet with the crest at elevation 375. Flow over the 
crest would be regulated by six tainter gates, 42 
feet long and 23 feet high. To provide for maximum 
releases of about 594 c.f.s. for all pool levels 
of conservation storage, two sluices would be 
provided in the right abutment of the spillway. 
The reservoir at maximum pool elevation 395.6 
(100-year flood pool) would have a pool area of 
27,000 acres and a total reservoir storage capacity 
of 486,000 acre-feet. Of this amount, normal 
sedimentation storage would be 40,600 acre-feet; 
water quality, 90,200 acre-feet; recreation, 69,000 
acre-feet; and flood control, 286,200 acre-feet. 
Normal pool elevation 282.0 would result in a 
16,000 acre pool during the recreation season. 
The estimated cost of the project (1975) is 
$53,300,000 including $3,210,000 non-Federal 
contributions. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Local interests would be required 
to pay, contribute in kind, or repay (which 
may be through user fees) with interest, one-half 
the separable first costs of the project allocated to 
recreation and one-quarter of costs allocated to 
fish and wildlife enhancement, an amount 
presently estimated to be $3,210,000 for the initial 
development; and bear all costs of operation, 
maintenance and replacement incurred therefor, 
presently estimated to be $93,000 annually for initial 
development. The final amount of each is to 
be determined after actual costs are known. 
Operation and results during fiscal year. 
Engineering, design, supervision and administration 
cost $234,028. 
Condition at end of fiscal year. Construction has 
not been initiated. 
30. TOMBIGBEE RIVER, MISS. AND 
ALA. 
Location. The project is located on the Tombigbee 
River and its tributaries between the junction 
of Browns and Mackeys Creeks in Itawamba 
County, Mississippi, and the mouth of the Noxubee 
River in Alabama. 
Existing project. The existing project provides 
for the alleviation of floods in Itawamba County, 
Mississippi, for a distance of 53 miles along the 
East Fork of the Tombigbee River, from Walkers 
Bridge at the junction of Browns and Mackeys 
Creeks to the Monroe County line, by clearing the 
banks of trees and underbrush to flood stage, the 
removal of drift jams and the excavation of 13 cutoff 
channels; and for additional channel improvements 
and related works for flood control of 
the Tombigbee River and tributaries above the 
mouth of and including the Noxubee River in accordance 
with plans approved by the Chief of 
Engineers, to protect people and valuable 
agricultural property from overflow waters of 
the Tombigbee River. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with on work 
done under the 1936 Flood Control Act. Work to 
be done under authority of the 1941 Flood Control 
Act requires local interest to provide all lands, 
easements, and rights-of-way for project construction; 
hold and save the United States free 
from damages due to construction of the project; 
and maintain and operate all the works after completion 
in accordance with regulations prescribed 
by the Secretary of the Army. 
Operations and results during fiscal year. 
Maintenance: Hired labor snagging and clearing 
cost $403. 
Condition at end of fiscal year. The project for 
Itawamba County, as authorized in the 1936 
Flood Control Act, was completed during fiscal 
year 1940. No work has been done on the extension 
of the project authorized in the 1941 Flood 
Control Act. The over-all project, as modified, is 
therefore about 47 percent completed. 
31. TOMBIGBEE RIVER 
TRIBUTARIES, MISS. AND ALA 
Location. The Tombigbee River rises in extreme 
northeast Mississippi and flows southerly 
through eastern Mississippi and western 
Alabama, emptying into the Mobile River about 
45 miles above its mouth at Mobile, Alabama. 
Tributaries to be improved for flood control are 
all in northeast Mississippi and northwest 
Alabama. 
Existing project. The authorized project 
provides for improvement of 22 tributaries of the 
Tombigbee River by means of channel enlargement, 
channel cut-offs, and channel clearing and 
snagging. Approved estimate of cost (1975) for 
new work is $68,773,000; consisting of 61,600,000 
Federal funds, and $7,173,000 non-Federal funds 
including $1,473,000 to be contributed by local interests. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction; make 
all road, highway bridge, and utility changes, 
alterations, additions, and relocations necessary 
for the project; hold the United States free from 
10-16

MOBILE, ALA., DISTRICT 
damages; prevent future encroachments along 
the improved channels; maintain all works after 
completion; and contribute $1,473,000 in cash or 
equivalent work. 
Operations during fiscal year. New work: 
Relocations cost $10,513; channel improvements 
cost $66; and engineering, design, supervision 
and administration cost $120,650. 
Condition at end of fiscal year. Construction 
commenced in June 1965, and the overall project 
is about seven percent complete. 
32. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Local flood-protection works for which inspection 
is performed under this heading consist of 
levee projects at West Point, Georgia, on the Chattahoochee 
River; Montezuma, Georgia, in the 
Flint River Basin; Elba and Geneva, Alabama, in 
the Choctawhatchee River Basin; Rome, Georgia, 
and Collinsville, Alabama, in the Alabama- 
Coosa River Basin; and channel rectification projects 
on Black Creek, Gadsden, Alabama, in the 
Alabama-Coosa River Basin; Old Town Creek, 
Tupelo, Mississippi; Big Brown Creek, Donovan 
Creek, Twenty Mile Creek, and Mantachie Creek, 
Fulton, Mississippi; and Luxapalila Creek, 
Alabama, in the Tombigbee River Basin; 
Sowashee Creek, Meridian, Mississippi, in 
Chickasawhay River Basin; Jackson and East 
Jackson, Mississippi, in the Pearl River Basin; 
Clanton, Alabama; Little Cove Creek, Glencoe, 
Alabama; Autauga Creek, Prattville, Alabama; 
Armuchee Creek, Armuchee, Georgia; Town 
Creek, Americus, Georgia; and Lake Douglas at 
Bainbridge, Georgia, in the Apalachicola- 
Chattahoochee-Flint Rivers Basin; and a 
drainage project in Jackson County, Florida. Projects 
at Rome and Montezuma, Georgia, and 
Collinsville, Alabama, include pumping stations. 
Inspections were made during FY 1975 to determine 
the extent of compliance with approved 
regulations for maintenance and operation of 
twenty of the projects. Responsible local officials 
were advised of inadequacies in maintenance and 
operation of the local flood protection works under 
their jurisdiction where appropriate. Followup 
for compliance of the deficient projects continued 
during the year. Fiscal year costs were 
$16,088. Total cost to June 30, 1975 was $113,132 
charged to maintenance. 
33. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 10-H) 
34. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended 
(Preauthorization). 
(See Table 10-I) 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation, and disaster 
relief activities under Public Law 875). 
(See Table 10-I) 
Multiple-Purpose Projects Including Power 
35. ALABAMA-COOSA RIVERS, 
ALA. AND GA. 
Location. Alabama River is formed 18 miles 
above Montgomery, Alabama, by the junction of 
the Coosa and Tallapoosa Rivers. It then flows 
southwesterly through Alabama 318 miles and 
unites with the Tombigbee River about 45 miles 
north of Mobile, in southwestern Alabama, to 
form the Mobile River. (See Geological Survey 
maps for central and southwest Alabama.) The 
Coosa River is formed at Rome, Georgia, in 
northwest Georgia, by the junction of the 
Oostanaula and Etowah Rivers, which have their 
sources in southeastern Tennessee and northern 
Georgia. From Rome the Coosa River flows 
southwesterly through Georgia and Alabama 286 
miles and unites with the T'allapoosa River near 
Montgomery, Alabama, at about the center of the 
State, to form the Alabama River. (See Geological 
Survey maps for northeast Alabama, southeast 
Tennessee, and northwest Georgia.) 
Previous projects. Projects for Alabama River: 
for details see page 1837, Annual Report for 1915; 
page 725, Annual Report for 1938; and page 592, 
Annual Report for 1944. Projects for Coosa River: 
for details see page 1837, Annual Report for 1915; 
page 728, Annual Report for 1938; and page 594, 
Annual Report for 1944. 
Existing project. The authorized project 
provides for full development of the Alabama- 
Coosa Rivers and tributaries for navigation, flood 
control, power, recreation, and other purposes, in 
accordance with plans under preparation by 
Chief of Engineers, subject to modifications 
thereof which may be advisable for increasing 
development of hydroelectric power. (See Table 
10-B for authorizing legislation.) Public Law 436, 
83rd Congress, suspended authorization of the 
comprehensive plan, insofar as it provides for 
development of Coosa River, to permit non- 
Federal interests to develop the Coosa River by 
construction of a series of dams in accordance 
with conditions of a license issued pursuant to 
10-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Federal Power Act and in accordance with certain 
other provisions and requirements of the 
aforementioned public law. The present phase of 
improvement, now under construction, provides 
for construction of Jones Bluff and Millers Ferry 
multiple-purpose improvements, Claiborne Lock 
and Dam, and supplemental channel work 
providing for a nine-foot deep navigation channel 
from the mouth of the Alabama River to 
Montgomery, Alabama, and for construction of 
Carters Dam, a multiple-purpose improvement 
on Coosawattee River, Georgia. Estimated cost 
(1975) for new work on Alabama-Coosa Rivers is 
$275,314,400, consisting of $271,801,300 for 
structures, and $3,513,100 for supplemental 
channel improvements, exclusive of amounts expended 
on previous projects. 
Local cooperation. Requirements of local 
cooperation will be determined as formulation of 
plans for development of projects progress. No action 
in the matter of local cooperation has been initiated. 
Terminal facilities. On the east bank of the 
river a natural landing connects with city streets 
at Montgomery. Wofford Oil Company has a 
small wharf about 10 miles below Montgomery 
equipped for handling petroleum products. 
There are also various natural landings along the 
river. Facilities and natural landings on 
Alabama River are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
work: Construction continued on Carters Dam, 
Millers Ferry Lock and Dam, Claiborne Lock and 
Dam, and Jones Bluff Lock and Dam. Expenditures 
for work on Alabama River Channel consisted 
of channel and canal work, $265,587; lands 
and damages, $190; engineering and design, 
$15,106; supervision and administration, 
$19,909. Coosa River Partnership cost for 
Montgomery flood protection amounted to 
$17,728. Work at Claiborne cost $93,029; Jones 
Bluff $9,288,682; Millers Ferry $279,735 and 
Carters $9,224,348. Total cost of new work 
amounted to $19,204,314. 
Maintenance: The U.S. Pipeline Dredge Collins, 
performing maintenance dredging, removed 
54,915 cubic yards of material at a cost of $34,227. 
The contractors dredges Cayman and Manchac 
removed 605,959 and 137,000 cubic yards of 
material, respectively, all for a cost of $432,035. 
The U.S. Snagboat Ros worked 20 days and 
removed 150 obstructions at a cost of $79,962. 
Channel surveys cost $44,192. Environmental 
studies cost $13,281. Hydraulic studies cost 
$15,983. Maintenance of public use facilities cost 
$57,322. Maintenance and care of Claiborne Lock 
and Dam cost $155,553. Maintenance and care of 
recreation facilities cost $110,707. Coosa and 
Tallapoosa River regulation cost $30,427. 
Engineering, design, supervision, administration 
and other miscellaneous costs amounted to 
$73,031. Operation of Millers Ferry and Jones 
Bluff projects costs $973,722 and $253,754, 
respectively. Total fiscal year cost for entire project 
was $21,478,510 of which $19,204,314 was for 
new work and $2,274,196 for maintenance. 
Detailed information on operations and costs 
applicable to the individual dam projects is 
presented under their respective project titles 
elsewhere in this report. 
Condition at end of fiscal year. Construction 
was initiated on Carters Dam in April 1962, on 
Millers Ferry Lock and Dam in April 1963, 
Claiborne Lock and Dam in May 1965, and Jones 
Bluff Lock and Dam in March 1966. Carters Dam 
is 98 percent complete and is scheduled for completion 
in FY 1976. The authorized nine-foot 
navigation channel to Montgomery, Alabama 
was opened to traffic in January 1972. Overall 
construction is essentially complete at Millers 
Ferry and Claiborne Locks and Dams. Construction 
of Jones Bluff Lock and Dam is about 85 percent 
complete, and the overall project is 96 percent 
complete with completion scheduled for 
1976. (See Table 10-J). 
35A. CARTERS LAKE, GA. 
Location. The damsite is in Murray County, 
Georgia, on the Coosawattee River 26.8 miles 
above its junction with Conasauga River, one of 
the headwater tributaries of the Alabama- 
Coosa system. It is 60 miles north of Atlanta near 
the town of Carters, Georgia. The reservoir will 
be in both Murray and Gilmer Counties. 
Existing project. The authorized project consists 
of a 1,950-foot long rockfill dam across the 
river, three saddle dikes on the left bank, a 258- 
foot long high-level, gated spillway on the left 
bank, a power house on the right bank having two 
conventional units with a generating capacity of 
125,000 kilowatts each and two pump-generating 
units of the same size, and a regulating dam 2,855 
feet long with a gated spillway 208 feet long 1.5 
miles downstream from the main dam. The lake 
will have an area of 3,220 acres, at maximum 
power pool elevation 1,072, total capacity of 
472,800 acre-feet, of which 134,900 acre-feet will 
be usuable for power and 95,700 acre-feet reserved 
for flood control and 242,200 acre-feet dead 
storage. The approved estimated (1975) cost is 
$106,000,000. For other information see description 
of Alabama-Coosa project. 
Operations and results during fiscal year. Total 
cost of new work amounted to $9,224,348 of which 
lands and damages cost $10,672; reservoirs, 
$1,836; dam construction $623,128; power plant, 
$6,702,017; roads, and railroads, $374,629; 
10-18

MOBILE, ALA., DISTRICT 
recreation facilities, $754,061; buildings, 
grounds and utilities, $62,441; permanent 
operating equipment, $30,210; engineering and 
design, $163,710; supervision and administration, 
$488,065; miscellaneous, $17,759. Credit to 
operations amounted to $181. 
Condition at end of fiscal year. Construction 
commenced in April 1962, is 98 percent complete, 
and is scheduled for completion in FY 1976. 
35B. CLAIBORNE LOCK AND DAM, 
ALA. 
Location. The site is in Monroe County at mile 
81.8 on the Alabama River, 15 miles northwest of 
Monroeville and 5.7 miles upstream from the 
U.S. Highway 84 bridge. 
Existing project. The authorized project consists 
of a short earth dike on the right bank, a combination 
of a fixed-crest and gated spillway extending 
across the river channel and into the left 
bank, a navigation lock and mound on the left 
bank, and an earth dike extending across the left 
overbank to high ground. Normal upper pool will 
be at elevation 35 and the minimum pool will be at 
elevation 32 to provide storage for reregulation of 
Millers Ferry powerplant releases. The 60-mile 
long reservoir will have an area of 5,850 acres and 
a volume of 96,360 acre-feet. The approved estimated 
(1975) cost is $28,151,500. For other information 
see description of Alabama-Coosa 
project. 
Operations and results during fiscal year. Total 
cost of new work amounted to $93,029. New work 
performed under contract amounted to $88,888 
for recreation facilities. New work performed 
with hired labor included $596 for buildings, 
grounds and utilities; $823 for engineering and 
design and $2,721 for supervision and administration. 
Recreation attendance at Claiborne 
Lake during CY 1974 totaled 253,300 user days. 
Condition at end of fiscal year. Construction 
began in May 1965 and was scheduled for completion 
in FY 1973. The project is 99 percent complete. 
35C. JONES BLUFF LOCK AND DAM, 
ALA. 
Location. The site is in Lowndes and Autauga 
Counties at mile 245.4 on the Alabama River, 26 
miles west of Montgomery. 
Existing project. The authorized project 
provides for a navigation lock, a gated spillway, 
and a power plant located at mile 245.4. The normal 
upper pool will be at elevation 125.0 and the 
minimum lower pool due to the Millers Ferry 
Lock and Dam at elevation 80.0. The structures 
will consist of earth dikes and a power plant on 
the right bank, a gated spillway in the river 
channel, a lock and mound on the left bank, and 
an earth dike extending upstream parallel to the 
Western Railway of Alabama. The total length of 
the structures will be about 14,962 feet with maximum 
height above the foundation at the power 
plant intake about 101 feet. The power plant will 
contain four 17,000-kw. units. The 88-mile long 
reservoir will have an area of 12,300 acres at normal 
pool level and a total capacity of 234,200 acrefeet. 
The lock will have a chamber 84 feet wide 
and 600 feet long and will provide a 12-foot depth 
over the lower miter sill. The approved estimated 
(1975) cost is $74,800,000. For other information 
see description of Alabama-Coosa project. 
Operat ion . and re sults duringfiscal year. Total 
cost of new work amounted to $9,288,682, which 
included land and damages, $24,130; reservoirs 
$27; dams $555,187; power plant $7,480,912; 
roads, railroads and bridges, $3,955; recreation 
facilities $118,282; buildings, grounds and 
utilities $30,878; permanent operating equipment, 
$67,934; engineering and design, $542,939; 
and supervision and administration, $544,257. 
Credit to operation amounted to $79,819. 
Maintenance: Operation and maintenance cost 
amounted to $253,754. Recreation attendance at 
Jones Bluff Lake during CY 1974 totaled 181,100 
user days. 
Condition at end of fiscal gear. Construction 
began in March 1966, is 85 percent complete, and 
is scheduled for completion in 1976. The first 
powerhouse unit was placed in operation in June 
1975. 
35I). MILLERS FERRY LOCK AND 
I)AM, AILA. 
Location. The site is in Wilcox County at mile 
142.2 on the Alabama River, 10 miles northwest 
of Camden, Alabama, and 30 miles southwest of 
Selma. 
E.ristitg project. The project consists of an 
earth dike on the right bank, a concrete, gravitygated 
spillway in the river channel, a lock and 
mound on the left bank, an earth dike extending 
downstream parallel to the lock to the 
powerhouse intake section, and an earth dike extending 
normal to the river. Normal upper pool 
will be at elevation 80. The powerplant contains 
three 25,000 kilowatt units. The 103-mile long 
reservoir will have an area of 17,200 acres at normal 
pool level and a total capacity of 331,800 acrefeet. 
The lock will have chamber dimensionsof 84 
by 600 feet with 13-foot depth over the miter sills. 
The approved estimated (1975) cost is 
$62,849,800. For other information see description 
of Alabama-Coosa project. 
Ope ria tionls anl t results duringfiscal year. Total 
cost of new work amounted to $279,735 of which 
10-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
lands and damages cost $287; roads, railroads 
and bridges, $48,546; buildings, grounds and 
utilities $269,985; engineering and design $377; 
supervision and administration, $4,537; miscellaneous. 
$29,444. Credits to construction 
amounted to $73,441. 
Maintenance: Operation and maintenance of 
lock, dam, powerhouse, reservoir, and administration 
incidentals thereto cost $973,722. 
Gross power generation at project was 
380.(),243,000 kilowatt-hours, of which 376,800,000 
kilowatt-hours were delivered to Southeastern 
Power Ad ministration. Recreation attendance at 
William "Bill" I)annelly Reservoir during CY 
1974 totaled 1,989,100 user days. 
('ondition (it (ll 0/ f.is'cail !Jea('r. Construction 
began in April 1963. The lock was placed in temporary 
ol)eration in June 1968 and opened to full 
use in November 1969. The powerhouse units 
were placed on line during April and May 1970. 
The overall project is about 99 percent completed. 
The remaining work to be done consists mainly of 
construction of recreational facilities. 
36. ALLATOONA LAKE, COOSA 
RIVER BASIN, GA. 
Local ion. The project is on Etowah River in 
Bartow County, Georgia, about 48 miles upstream 
from Rome, Georgia, about five miles due 
east of Cartersville, Georgia, and about 2,000 feet 
downstream from mouth of Allatoona Creek. The 
reservoir extends about 28 miles up the Etowah 
River at maximum power-pool elevation of 840 
feet above mean sea level. 
Existing project. The authorized project 
provides for a dam and reservoir for flood control, 
regulation of streamflow for navigation, and 
development of hydroelectric power. Height 
above the river bottom of the concrete, gravitytype 
dam is about 190 feet from elevation 690 feet 
to 880 feet above mean sea level. The spillway, 
with crest at elevation 835, is controlled by nine 
tainter gates, 40 feet wide by six feet high, and 
two tainter gates, 20 feet wide by six feet high; 
having a combined discharge capacity of 321,000 
cubic feet per second with the water surface at 
elevation 870.3. One 48-inch diameter sluicing 
conduit with a free discharge valve and four 
sluices, 5 feet-8 inches wide by 10 feet high, are included 
in dam. Installed generating capacity consists 
of two 36,000 kilowatt units and one 2,000 
kilowatt unit, or a total of 74,000 kilowatts. Ultimate 
installed capacity will be 110,000 
kilowatts. The reservoir, covering 19,200 acres at 
elevation 860, has a storage capacity of 670,000 
acre-feet. Cost was $31,427,300, excluding an estimated 
(1975) $3,470,800 for addition of recreation 
facilities at the completed project (Code 711 
and 712 funds). (See Table 10-B for authorizing 
legislation.) 
Local co(tprat ion. None required (Sec. 2, Flood 
Control Act of June 28, 1938, applies). 
Ope rat i. s, and resalt.S d(ringfiscal yJIe ar. New 
work: Recreation facilities (Code 711) provided 
cost $84,404. 
Maintenance: Operation and ordinary 
maintenance of the dam, reservoir, powerhouse, 
service and recreational activities, and administration 
incidental thereto cost $1,316,101. 
Gross power generation at Allatoona Reservoir 
was 190,636,200 kilowatt-hours, of which 
186,750,700 kilowatt-hours were delivered to 
Southeastern Power Administration. 
Recreational attendance at Allatoona Lake during 
CY 1974 totaled 6,739,100 recreational user 
days. Rains in headwater areas during February 
and March 1975, resulted in rises in pool elevation 
a maximum of 8.6 feet and a total impoundment 
of 134,100 acre-feet. Natural stages at Kingston 
were reduced as much as 9.1 feet, and at Rome 5.7 
feet, during this time, with corresponding reductions 
in flood losses estimated at $437,900 rural 
and $340,900 urban. 
Condition at end of'fisca l year. Construction of 
the existing project began in March 1944 and was 
completed in October 1955. 
37. AIPALACHICOLA, 
CHATTAHOOCHEE, AND FLINT 
RIVERS, ALA., GA., AND FLA. 
Locat ion. The Apalachicola River is formed at 
the southwest corner of the State of Georgia by 
the junction of the Chattahoochee and Flint 
Rivers and flows south 108 miles emptying into 
Apalachicola Bay. Florida River enters the 
Apalachicola River from the east at mile 45.4 and 
the River Styx also enters from the east at mile 
36.7 and Chipola River enters from the west at 
mile 28.2. (See Coast and Geodetic Survey Chart 
1262.( The Chattahoochee River, 418 miles long, 
rises in northeast Georgia and flows 
southwesterly to West Point, and thence southerly 
to join the Flint River at the southwest corner of 
Georgia, forming the Apalachicola River. (See 
Geological Survey maps for northwest Georgia.) 
The Flint River, 330 miles long, rises in west central 
Georgia, flows generally southeasterly to 
Albany, and thence southwest to the southwest 
corner of the State, where it joins the Chattahoochee 
River to form the Apalachicola River. 
(See Geological Survey maps for southwest 
Georgia.) 
Prerious projects. For details see page 484 of 
Annual Report for 1963. 
E.xisting project. The authorized project 
provides for development of the Apalachicola, 
10-20

MOBILE, ALA., DISTRICT 
Chattachoochee, and Flint Rivers for navigation, 
flood control, hydropower, and recreation. 
Navigation features of the existing project consist 
of a continuous 9-foot by 100-foot channel in the 
Apalachicola River from the intersection of the 
Gulf Intracoastal Waterway to the confluence of 
the Chattahoochee and Flint Rivers, 104 miles, 
thence to Columbus, Georgia, on the Chattahoochee 
River, 164 miles, and to Bainbridge, 
Georgia, on the Flint River, 29 miles, and a 3-foot 
by 100-foot channel on the Flint River from Bainbridge 
to Albany, Georgia, 74 miles, thence a 
channel suitable for light draft vessels at 
moderate states to Montezuma, Georgia, 79 miles, 
to be accomplished by dredging, contraction 
works, and construction of three locks and dams 
(Jim Woodruff, George W. Andrews, and Walter 
F. George) along the nine-foot depth channel, two 
multipurpose darns (West Point and Lake Sidney 
Lanier on the Chattahoochee River), three multipurpose 
dams (Lower Auchumpkee Creek, 
Lazer Creek, and Spewrell Bluff) on the Flint 
River, and minor improvements of certain 
streams tributary to the Apalachicola River. 
Plane of reference is mean low water. 
Hydropower and flood control storage is provided 
at Sidney Lanier, Lazer Creek, Lower 
Auchumpkee Creek, Spewrell Bluff, Walter F. 
George, and West Point, and hydropower is 
provided at Jim Woodruff. For further details see 
Annual Report for 1962. (See Table 10-B for 
authorizing legislation.) 
Estimated cost (1975) for new work is $594- 
204,600, including $4,488,000 for channel improvement 
in the Apalachicola River, and 
$338,198 for cost of lands for wildlife at the 
Walter F. George project, and exclusive of 
amounts expended on previous projects. Additionally, 
the costs of adding recreational 
facilities at completed projects (Code 710) is estimated 
to be $6,771,300 for Lake Sidney Lanier, 
$2,998,000 for Walter F. George Lock and Dam, 
$797,300 for George W. Andrews Lock and Dam, 
and $2,511,000 for Jim Woodruff Lock and Dam. 
Mean range of tide at the mouth of Apalachicola 
River is 1.5 feet. At the point where the river is 
formed the variation between low and high water 
is about 37 feet. On the Chattahoochee River, 
variation between average low and high water is 
about 20 feet, and extreme fluctuation is 65.3 feet 
at Eufaula. On the Flint River the extreme fluctuation 
of stage due to flood is 40 feet, while 
average variation between low and high water is 
about 21.5 feet. 
Local coop eration. Fully complied with to date. 
Termilal .failities. About 200 feet of public 
docks, in addition to private wharves, are 
available at Apalachicola, Florida. There are 
numerous constructed and natural landings 
along the entire system for launching small craft. 
For details of other terminal facilities, which are 
considered adequate for existing commerce, see 
individual project descriptions. See also Table 10- 
L on locks and dams and multiple-purpose 
development included in existing project. 
Operatioins aend results during fiscal year. New 
work: (See report for individual project cost.) 
Maintenance: The U.S. pipeline dredge 
Goth rie, removed 1,086,298 cubic years of 
material from the Apalachicola River and 
378,077 cubic yards of material from the Chattahoochee 
River, all at a cost of $1,205,234. The 
contractor's pipeline dredge Congaree, operating 
in the Apalachicola and Chattahoochee Rivers 
removed 205,120 and 29,155 cubic yards of 
material, respectively, all at a cost of $419,660. 
The U.S. snagboat Montgomiery, operating in the 
Apalachicola River removed 1,713 obstructions, 
and operating in the Chattahoochee River removed 
3,713 obstructions, 1,700 cubic yards of rock 
and 9,937 cubic yards of material, all for a cost of 
$478,266. Other costs include: Surveys, $85,789; 
Environmental studies, $29,853; Hydraulic 
studies, $52,703; Engineering design, supervision 
and administration, $73,624; Spoil dike, 
$31,074, and repairs to pile dikes, $69,473. Miscellaneous 
and other costs amounted to $162,194. 
Operation and care of George W. Andrews Lock 
cost $154,026 and is included as part of the overall 
project. 
Ope riations a rnd ma intenauce locks and dams: 
Walter F. George Lock and Dam cost $1,458,482; 
Jim Woodruff Lock and Dam, $1,533,674; Lake 
Sidney Lanier, $1,265,112; West Point Dam, 
$138,253. Total FY 75 cost for entire project was 
$16,891,292 of which $9,733,875 was new work 
and $7,157,417 was operation and maintenance. 
Detailed information on operations and costs 
applicable to the individual dam projects is 
presented under their respective project titles 
elsewhere in this report. 
Con dition at e, d of fiscal year. Improvement of 
Apalachicola River channel by dredging to 
provide project dimensions throughout is complete. 
All major construction on Lake Sidney 
Lanier Dam, George W. Andrews Lock and Dam, 
Jim Woodruff Lock and Dam, and Walter F. 
George Lock and Dam, is complete. Planning is in 
progress on Spewrell Bluff and Lazer Creek 
Dams. Channel rectification in Apalachicola 
River was completed December 1970. More 
detailed information concerning condition at the 
end of fiscal year for individual locks and dams 
and multiple-purpose developments comprising 
the system is presented under their respective 
project titles elsewhere in this report. Work 
remaining to complete the project consists of 
minor land acquisition at Lake Sidney Lanier and 
10-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
George W. Andrews Lock and Dam; completion 
of recreational facilities (Code 710) at Lake 
Sidney Lanier, George W. Andrews Lock and 
Dam, Jim Woodruff Lock and Dam, and Walter 
F. George Lock and Dam; construction of Lazer 
Creek, Spewrell Bluff and Lower Auchumpkee 
Creek Dam; and completion of construction of 
West Point Dam. (See Table 10-K for fiscal year 
costs for new work on overall project.) 
37A.LAKE SIDNEY LANIER, GA. 
Location. The dam is on the Chattahoochee 
River about 348.9 miles above its mouth, 50 miles 
above Atlanta and five miles northwest of Buford, 
Georgia. The reservoir extends about 47 miles upstream 
along the Chattahoochee River, and about 
21 miles up the Chestatee River, which enters the 
Chattahoochee River 14.5 miles above the dam. 
Existing project. The authorized project 
provides for a rolled-earthfill dam 1,630 feet long, 
with crest at elevation 1,106 feet mean sea level, 
or about 192 feet above streambed elevation; 
three earth saddle dikes with a total length of 
5,406 feet; a chute spillway with crest at elevation 
1,085; a powerhouse in a deep cut with steel 
penstocks in tunnels, and concrete intake structure 
at the upstream end of the tunnels; and a 
flood control sluice tunnel paralleling the power 
tunnels. The reservoir has a gross capacity of 
2,554,000 acre-feet of which 637,000 acre-feet of 
storage is reserved for flood control storage. The 
power installations consist of one generating unit 
of 6,000 kilowatts and two units of 40,000 
kilowatts each, or a total of 86,000 kilowatts. The 
project provides for maintenance, including 
recreational facilities at completed project is 
$6,771,300. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Construction of recreational facilities at 
the completed project (Code 711) cost $266,376. 
Maintenance: Operation and maintenance cost 
$1,265,112. Gross power generation at project 
was 233,007,000 kilowatt-hours, of which 
226,850,200 kilowatt-hours, were delivered to 
Southeastern Power Administration. 
Recreational attendance at Lake Sidney Lanier 
during CY 1974 totaled 13,686,600 recreational 
user days. Rains in headwater area during 
February and March 1975 resulted in rises in 
pool elevation a maximum of 2.3 feet and a total 
impoundment of 159,200 acre-feet. Natural 
stages at Norcross, Georgia, were reduced 9.9 feet 
and 6.7 feet at Atlanta, with corresponding 
reductions in flood losses estimated at $427,900 
rural. 
Condition at end of fiscal year. Construction 
commenced in March 1950 and was completed in 
June 1960. The reservoir was in useful operation 
for flood control in February 1956. The first 
power generating unit was placed on-the-line 
June 19, 1957; the second on July 26, 1957; and the 
third on October 10, 1957. The project is essentially 
complete except for adding additional 
recreational facilities. 
37B. GEORGE W. ANDREWS LOCK AND 
DAM, ALA. AND GA. 
Location. The project is on the Chattahoochee 
River about 46.5 miles above its mouth and about 
one mile below the town of Columbia, Alabama, 
near the head of Jim Woodruff Reservoir. (See 
Geological Survey maps for southeast Alabama.) 
The pool extends up the navigation channel about 
28 miles upstream to Walter F. George Lock and 
Dam. 
Existing pruoject. This single-purpose project 
provides for a concrete fixed-crest spillway 340 
feet long extending into the right bank with a 
crest at elevation 102 feet mean sea level, a concrete 
gate spillway adjacent to the lock 280 feet 
long with crest at elevation 82 feet mean sea level, 
a single-lift lock with usuable chamber dimensions 
of 82 feet by 450 feet, and a maximum lift of 
25 feet. Depths are 13 feet over the lower sill 
and 19 feet over the upper sill at normal pool 
elevation. The underlying foundation is 
limestone. Estimated cost (1975) of adding 
recreational facilities at the completed project 
(Code 710) is$797,300. The project provides for 
maintenance, including operation and care. The 
House Committee on Public Works, by resolution 
adopted May 19, 1953, approved the plan as 
proposed by the Chief of Engineers for a high 
dam at Walter F. George site and a low dam at the 
upper Columbia site in lieu of a low dam at the 
Fort Benning site and a high dam at the upper 
Columbia site, construction of which was 
authorized by the 1946 River and Harbor Act as 
the initiation and partial accomplishment of the 
plan for full development of the Apalachicola, 
Chattahoochee, and Flint River system. (See 
Table 10-B for authorizing legislation.) 
Local coop rat ion. Local interests must operate 
all movable span bridges, provide suitable public 
terminals, and hold the United States free from 
damages. These conditions are being complied 
with. 
Termimal fiacilities. At Columbia, Alabama, 
there is a public wharf with concrete deck for 
handling general cargo and a bulk petroleum terminal 
with an unloading dock. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Recreational attendance at George W. Andrews 
Lock and Dam during CY 1974 totaled 215,900 
10-22

MOBILE, ALA., DISTRICT 
recreational user days. Maintenance: Operation 
and maintenance cost included under overall 
Apalachicola, Chattahoochee and Flint project. 
Condition (it end of fiscal year. Construction of 
the lock and dam began in March 1959 and was 
completed in November 1963. Work remaining 
consists of construction of recreational facilities 
under Code 711. 
37C. JIM WOODRUFF LOCK AND DAM, 
GA. AND FLA. 
Location. The project is located on the 
Apalachicola River 107.6 miles above its mouth, 
about 1,000 feet below confluence of the Chattahoochee 
and Flint Rivers, and 1.5 miles 
northwest of Chattahoochee, Florida. Reservoir 
extends about 46.5 miles upstream along the 
Chattahoochee River to the vicinity of Columbia, 
Alabama, and about 47 miles upstream along 
Flint River, or 17 miles above Bainbridge, 
Georgia. (See Geological Survey maps for 
southwest Georgia.) 
Ex isting project. The authorized project 
provides for a concrete open-crest spillway 1,634 
feet long on the right bank, with a crest at elevation 
79 feet mean sea level; a single-lift lock with 
usuable chamber dimensions of 82 by 450 feet, a 
maximum lift of 33 feet, and depth over the sills of 
14 feet; a gated spillway 766 feet long with the 
bridge at elevation 107 feet mean sea level, or 
about 67 feet above the streambed elevation; a 
powerhouse with an intake section constituting a 
portion of the dam; an earth section 506 feet long 
to accommodate the switchyard and substation; 
and an overflow dike section 2.130 feet long on the 
left bank, with a crest at elevation 85. The underlying 
foundation is limestone. At the normal 
pool elevation of 77, the reservoir has a total 
capacity of 406,160 acre-feet. The lower installation 
consists of three units of 10,000 kilowatts 
each, or a total of 30,000 kilowatts. Project 
provides for maintenance, including operation 
and care. Estimated cost (1975) of adding 
recreational facilities at the completed project is 
$2,511,000. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Required cooperation is being 
fulfilled. Easements for rights-of-way and 
spoil-disposal areas were provided as required 
along the Apalachicola River. Adequate public 
terminals were constructed by local interests at 
Bainbridge, Georgia, on the Flint River; and at 
Columbia, Alabama, on the Chattahoochee River. 
Facilities are being planned for other localities on 
the project. 
Triinl f.cilitis . A public wharf with concrete 
deck for handling general cargo, a bulk 
storage terminal for petroleum, a grain elevator, 
and private riverside facilities at Bainbridge, 
Georgia, on the Flint River, are considered adequate 
for existing commerce. 
()pcr(/t iHons andr e(s lt/s d ,rin'( fiscal y aHr.u Ni ew 
work: Recreational facilities provided at completed 
project (Code 711) cost $69,001. 
Maintenance: operation and maintenance cost 
$1,533,674. Power generation at Jim Woodruff 
Lock and Dam 235,549,000 kilowatt-hours, of 
which 231,939,000 kilowatt-hours were delivered 
to Southeastern 1Power Administration. 
Recreational attendance at Lake Seminole during 
CY 1974 totaled 2,993,100 recreational user 
days. 
Cond it /i it oi (1 of fisc( I c i r. Construction of 
the lock was commenced in 1947, and completed 
in 1957. The lock was opened to navigation in May 
1954, and the pool was raised to project level in 
January 1957. The first power-generating unit 
was placed on-the-line on February 1, the second 
on March 1, and the third on April 26, 1957. 
37D SPIEWRELL BLUFF LAKE, GA. 
Location. The dam is on the Flint River in 
Talbot and Upson Counties, Georgia, about nine 
miles west of Thomaston. The lake will extend 
into Meriwether, Pike, and Spalding Counties. 
E.xistingl project. The authorized project 
provides for: a dam 2,475 feet long with maximum 
height of 211.0 feet, a 326-foot long gated 
spillway with six tainter gates 38 feet high and 45 
feet wide, concrete non-overflow abutments 1,149 
feet across the main channel including 268 feet 
for the power intake, with an earth-rock fill dike 
580 feet long to high ground on the left bank, a 
420-foot saddle dike on the left bank, and a power 
plant with three 50,000-kw units located in the 
left bank. The reservoir would have an area of 13,- 
330 acres at maximum power pool elevation of 
695 mean sea level. Usuable storage of 241,510 
acre-feet would be provided for power generation 
between elevations 665 and 695 and 195,010 acrefeet 
would be reserved between elevations 695 
and 706.5 for flood storage. Approved estimated 
(1975) cost is $183,000,000, of which $109,400,000 
is for construction and design, and $56,260,000 
for lands, damages, and relocations. (See Table 
10-B for authorizing legislation.) 
Local coo peJrat ion. Local interest must maintain 
and operate all utility and highway facilities 
which may be relocated or otherwise altered as 
part of the improvement, provide suitable public 
terminal facilities, and hold the United States 
free from damages. Local agencies and 
organizations have indicated their willingness 
and ability to comply. 
Op rtions a( r's Ilts (t1urinfgfisc1l c(ir. New 
work: Engineering, design, supervision and administration 
cost $2,772. 
10-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Codit ion at (,nd of fisca l y cr. Construction has 
not been initiated. 
37E. WALTER F. GEORGE LOCK AND 
I)AM, ALA. AND GA. 
Loca tion. The project is on the Chattahoochee 
River about 75.2 miles above its mouth and about 
1.5 miles above Fort Gaines, Georgia. (See 
Geological Survey maps for southwest Georgia.) 
Existing proje ct. The authorized project 
provides for a concrete dam, gated spillway, and 
single-lift lock, with earth embankments at 
either side. The non-overflow section of the dam 
includes a powerhouse and an intake structure. 
The gated spillway is 708 feet long with a fixed 
crest at elevation 163 feet mean sea level. The two 
earth embankments, of almost equal lengths, 
have a total length of 12,128 feet, with a crest 
elevation at 215, and a maximum height of about 
68 feet. The non-overflow section of the concrete 
dam is 200 feet long, with the deck of the 
powerhouse section at elevation 208. The lock, 
with usuable chamber dimensions of 82 feet by 
450 feet, has a lift of 88 feet with the normal upper 
pool elevation at 190. Depths are 13 feet over the 
lower sill and 18 feet over the upper sill at normal 
pool elevation. The underlying foundation is 
limestone. Total reservoir capacity is 
934,400 acre-feet, with 244,400 acre-feet reserved 
for power. The power installation concists of four 
units of 32,500 kilowatts each, or a total of 130,000 
kilowatts. The project provides for maintenance, 
including operation and care. Estimated cost 
(1975) of adding recreational facilities at the completed 
project (Code 710) is $2,998,000. (See Table 
10-B for authorizing legislation.) 
Local coopcrtalion. Local interests must maintain 
and operate all utility and highway facilities 
which may be relocated or otherwise altered as 
part of the improvement, provide suitable public 
terminal facilities, and hold the United States 
free from damages. Local agencies and other 
organizations have indicated their willingness 
and ability to comply. 
T7'ri mll / fa cilitics. Public wharves at Eufaula 
and Phenix City, Alabama, and Columbus, 
Georgia, are considered adequate for existing 
commerce. 
Op( rat ions a rtle! slts duringf iscal jyctar. New 
work: Recreation facilities provided at completed 
project (Code 711) cost $91,857. Maintenance of 
the project for operation and care was $1,458,482. 
Gross power generation at Walter F. George Lock 
and Dam was 510,584,000 kilowatt-hours, of 
which 503,158,000 kilowatt-hours was delivered 
to Southeastern Power Administration. 
Recreational attendance during CY 1974 totaled 
2,949,900 recreational user days. 
Condition at end of fiscal year. Construction 
was completed in 1963. The lock was opened to 
navigation in June 1963. The first power 
generating unit was placed on-the-line in March, 
the second in May, the third in September, and 
the fourth in November 1963. 
37F. WEST POINT LAKE, 
CHATTAHOOCHEE RIVER BASIN, 
GA. AND ALA. 
Location. The damsite is on the Chattahoochee 
River 2.8 miles upstream from West Point, 
Georgia, 201.4 miles above the mouth of the Chattahoochee 
River, and 309.2 miles above the mouth 
of the Apalachicola River. At the full power pool 
elevation of 635 feet above mean sea level, the 
reservoir would lie in Troup and Heard Counties, 
Georgia, and in Chambers and Randolph Counties, 
Alabama. (See Geological Survey maps of 
Georgia and Alabama.) 
Existing project. The authorized project is to 
provide for flood control, power, recreation, fish 
and wildlife development, and streamflow 
regulation for downstream navigation. The project 
provides for a gravity-type concrete dam 896 
feet long with earth embankments at either end 
1,111 feet long east and 5,243 feet long on the west 
end. The total length of the dam and spillway will 
be 7,250 feet. The main dam will consist of a concrete 
non-overflow section, 185 feet long on the 
west side and an earth embankment retaining 
wall on the east side; a gravity concrete spillway 
390 feet long, including piers and abutments, 
with six tainter gates, each 50 feet by 41 feet. A 
monolith intake-powerhouse section and erection 
bay 321 feet long will be constructed directly west 
and adjacent to the spillway. At the full powerpool 
elevation of 635 the reservoir will provide a 
total storage of 605,000 acre-feet of which 307,000 
acre-feet will be usable. During the critical flood 
season, it is planned to operate the reservoir with 
maximum power pool elevation at 625 feet to 
provide flood storage between elevations 625 and 
635. The initial power installation will be 73,375 
kilowatts and the ultimate will be 108,375 
kilowatts. Units 1, 2 and 3 were placed in operation 
in March and April, 1975. 
Approved estimated cost of new work (1975) is 
$118,000,000, of which $77,612,500 is for construction 
and design; $18,864,500 for lands and 
damages; and $21,723,000 for relocations. (See 
Table 10-B for authorizing legislation.) 
Local coop ,ration. None required. 
Operations a ndl results during fiscal year. New 
work: During fiscal year 1975 real estate acquisition 
and dam and power plant construction were 
continued, and reservoir clearing was essentially 
completed. 
10-24

MOBILE, ALA., DISTRICT 
Total cost for new work amounted to $9,303,869 
of which $172,800 was for real estate; $1,363,200 
for relocations; $489,000 for reservoirs; $354,800 
for dams, $1,403,300 for power plant; $3,324,400 
for recreation facilitites; $339,600 for buildings, 
grounds and utilities; $289,800 for permanent 
operating equipment; and, $1,188,169 for 
engineering, design, supervision and administration. 
Maintenance: Operation and care of the project 
cost $138,253. 
Condition at e nd of fiscal year. Construction of 
the project, which was initiated in June 1966, was 
about 89 percent complete at the end of the fiscal 
year. 
38. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Mobile District monitors flood control 
operations of Alabama Power Company's Weiss, 
H. Neely Henry, and Logan Martin Dams on 
Coosa River, Alabama, and their Lewis Smith 
Dam on Sipsey Fork (headwaters of Black 
Warrior River, Alabama). for compliance with 
regulation plans prepared in accordance with 
Public Law 436, 83rd Congress, and Federal 
Power Commission licenses. Fiscal year cost for 
these activities on the Weiss, H. Neely Henry, and 
Logan Martin Dams are included under operation 
and maintenance costs for the Alabama- 
Coosa Rivers. Fiscal year cost for the Lewis Smith 
Dam is included under the overall operation and 
maintenance costs for the Black Warrior- 
Tombigbee Rivers System. Other fiscal year costs 
amounted to $6,929 for miscellaneous investigations 
on Crooked Creek, Alabama, in connection 
with license application on Tallapoosa 
River from Alabama 'ower Comapny, also included 
in maintenance cost for Alabama-Coosa 
Rivers. 
General Investigations 
39. SURVEYS 
Fiscatl 1yc r cost 'wa.$s 779,. 2(0f 'rll i $27 J'l,O1 
a(1 for 10aigation stui(0e, $15,,024 (lSfor.lool 
co,,trol st ldics, $50,927 t (les f/0o be1c r (c (r ion 
t u(1ic5, $GI, ilfor re iu' of (0om pletd projcts 
(A 11(1100/0 D(o )o), $,8h7 for (1( ulthoriiz( tion 
re,'ic', $229, s' tfor d(1(1tailed (cotomO ict st1(1i.'s, 
(11d -$1foir cot prtelhclsi r' rirer b(si st~iies. 
40. COLLECTION ANDI) STUDY OF 
BASIC I)ATA 
Collection and study of basic data continued 
during the fiscal year with the completion of eight 
Flood Plain Information Reports, several Special 
Flood Hazard Information Reports and one Flood 
Insurance Report in addition to providing 
technical services, all at a cost of $299,287. (See 
Table 10-L for listing of studies completed during 
FY 1975. For listing of previous reports see page 
10-50 Annual Report for 1974). 
41. RESEARCH AND DEVELOIPMENT 
Research and development in the Mobile District 
cost $5,792, all of which was for plant 
stabilization studies. 
10-25

TABLE 10-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Apalachicola Bay, 
Fla. 
2. Aquatic Plant Control 
(Regular Funds) 
(Contributed Funds) 
3. Bayou Coden, Ala. 
(Contributed Funds) 
4. Bayou La Batre, Ala. 
(Regular Funds) 
(Contributed Funds) 
5. Biloxi Harbor, Miss. 
(Contributed Funds) 
6. Black Warrior & 
Tombigbee Rivers, Ala. 
7. Dauphin Island Bay, 
Ala. 
8. Dog and Fowl 
Rivers, Ala. 
(Regular Funds) 
(Contributed Funds) 
9. East Pass Channel 
From Gulf of Mexico 
into Choctawhatchee 
Bay, Fla. 
(Regular Funds) 
(Contributed Funds) 
Funding FY72 
New Work: 
Approp. 
Cost 1,816 
Maint: 
Approp. 55,161 
Cost 50,549 
New Work: 
Approp. 20,647 
Cost 13,873 
Maint: 
Contrib. -3,690 
Cost -3,690 
New Work: 
Approp. 
Cost 532 
Maint: 
Approp. 327 
Cost 327 
New Work: 
Contrib. - 
Cost 
New Work: 
Approp. - 
Cost 
Maint: 
Approp. 74,842 
Cost 27,999 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. - 
Cost 2,034 
Maint: 
Approp. 325,629 
Cost 119,306 
Maint: 
Contrib. - 
Cost 
New Work: 
Approp. 3,634,573 
Cost 4,908,586 
Maint: 
Approp. 2,417,700 
Cost 2,386,559 
New Work: 
Approp. - 
Cost 
Maint: 
Approp. 39,300 
Cost 1,660 
New Work: 
Approp. -63,850 
Cost 3,308 
New Work: 
Contrib. - 
Cost 
New Work: 
Approp. - 
Cost 
Maint: 
Approp. 221,163 
Cost 216,225 
New Work: 
Contrib. - 
Cost 5,287 
Total Cost to 
FY73 FY74 FY75 June 30, 1975 
- 5,000 65.000 
1,983 
105,600 
104,501 
24,000 
23,024 
31,185 
13,902 
8Q 
28,437 
15,700 
14,191 
53,000 
55,819 
264,000 
34,811 
1,354 
2,557 
7,823 
13,000 
20,061 
-94,500 
4,847 
527 
527 
20,899 
186,917 
-60,997 
650,058 
65,139 
64,550 
78,600 
73,427 
8,100,000 
9,795,161 
4,228,600 
4,303,485 
17,874 
88,752 
10,980 
- 
80 - 
- 100,000 
- 59,400 
- -_ 
45,842 170,000 
91,135 6,159 
7 14,332 
17,409 164,398 
223,564 164,565 
8,921,450 15,558,356 
6,498,642 16,571,380 
2,973,462 2,923,950 
2,918,989 2,957,250 
92,030 73,000 
128,630 2,962 
93,000 -31,185 
9,304 156,336 
70,100 - 
- 59,120 
1,138,7961 
1,099,013 
1,407,5262 
1,404,908 
279,287 
253,965 
21,225 
21,225 
348,335 
74,323 
38,879 
38,879 
100,000 
59,400 
311,095 
311,095 
842,341 
842,016 
10,500 3 
10,500 
954,1554 
954,155 
1,945,5625 
1,944,973 
78,600 
73,427 
147,096,2666 
147,062,373 
63,001,7947 
62,942,563 
292,565 
292,565 
406,296 
406,096 
190,965 
190,965 
70,100 
70,100 
916,715 
916,715 
100,596 165,500 
104,414 164,625 
83,127 1,727,189 
84,582 1,726,649 
- 398,000 
- 398,000 
10-26

MOBILE, ALA., DISTRICT 
TABLE 10-A(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
10. Escambia-Conecuh 
Rivers, Fla. and Ala. 
11. Gulf Intracoastal 
Waterway between 
Apalachee Bay, Fla. 
and Mexican Border 
12. Gulfport Harbor, Miss. 
13. Mobile Harbor, Ala. 
(Regular Funds) 
(Contributed Funds) 
14. Panama City 
Harbor, Fla. 
15. Pascagoula Harbor, 
Miss. 
(Regular Funds) 
(Contributed Funds) 
16. Pass Christian 
Harbor, Miss. 
17. Pearl River, Miss. 
and La. 
(Regular Funds) 
(Contributed Funds) 
18. Pensacola Harbor,, Fla. 
19. Perdido Pass 
Channel, Ala. 
Funding FY72 FY73 FY74 FY75 June 30, 1975 
New Work: 
Approp. - - - - 208,4998 
Cost - - - - 208,499 
Maint: 
Approp. 1,607 4,829 11,705 5,621 403,2769 
Cost 1,607 3,669 11,481 6,519 402,790 
New Work: 
Approp. - - - - 6,480,29910 
Cost - - - - 6,480,299 
Maint: 11 
Approp. 633,800 874,222 1,427,000 1,085,800 14,961,22411 
Cost 583,740 811,391 679,132 1,923,085 14,918,572 
New Work: 12 
Approp. - - - - 904,77512 
Cost - - - - 904,775 
Maint: 13 
Approp. 108,222 398,968 1,012,788 934,942 15,336,38813 
Cost 645,657 439,513 654,648 1,297,830 15,334,288 
New Work: 14 
Approp. - - 120,000 190,000 14,798,93714 
Cost 65,125 230,340 14,784,402 
Maint: 15 
Approp. 1,674,700 1,966,499 1,851,500 1,717,239 29,176,39915 
Cost 2,303,484 1,725,603 1,130,862 2,496,673 28,952,975 
Maint: 
Contrib. - - - - 12,000 
Cost - - - - 12,000 
New Work: 16 
Approp. - - 110,000 32,900 1,490,94416 
Cost - - 81,685 55,451 1,485,180 
Maint: 17 
Approp. 234,297 191,686 64,060 3,594 3,640,59017 
Cost 234,063 187,834 69,668 3,880 3,640,573 
New Work: is 
Approp. - - - - 6,572,98518 
Cost - - - - 6,572,985 
Maint: 19 
Approp. 744,415 453,091 641,100 833,819 9,965,89819 
Cost 259,953 1,030,794 689,868 880,499 9,964,022 
Maint: 
Contrib. 70,100 - 120,000 190,100 
Cost 60,000 10,100 - 120,000 190,100 
New Work: 
Approp. - - - - 59,319 
Cost - - - - 59,319 
Maint: 
Approp. -6,514 - 81,551 - 124,109 
Cost 950 - 50,048 31,360 123,966 
New Work: 20 
Approp. - -9,829 - 8,562,90820 
Cost 47,187 1,540 - - 8,562,908 
Maint: 21 
Approp. 219,100 554,276 163,500 121,946 3,707,73421 
Cost 186,136 390,513 376,215 131,526 3,699,952 
New Work: 
Contrib. - - - - 65,000 
Cost 670 - - - 65,000 
New Work: 
Approp. - - - - 1,469,69322 
Cost - - - - 1,469,693 
Maint: 23 
Approp. 16,902 361,582 54,200 231,126 3,306,42223 
Cost 14,253 360,733 56,018 231,749 3,304,875 
New Work: 
Approp. - - - - 629,860 
Cost . 629,860 
10-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-A(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY72 FY73 FY74 FY75 June 30, 1975 
(Regular Funds) 
(Contributed Funds) 
20. Removing Water 
Hyacinth 
(Mobile District) 
21. Waterway Connecting 
Tombigbee and 
Tennessee Rivers, Ala. 
and Miss. 
22. Jackson & East 
Jackson, Miss. 
(Regular Funds) 
(Contributed Funds) 
27. Okatibbee Lake,, Miss. 
28. Tallahala Creek 
Lake, Pascagoula 
River, Miss. 
29. Edinburg Lake, Miss. 
30. Tombigbee River, 
Miss. and Ala. 
31. Tombigbee River 
Tributaries, 
Miss. and Ala. 
(Regular Funds) 
(Contributed Funds) 
35. Alabama-Coosa 
Rivers, Ala. 
and Ga. 
35A. Carters Dam and 
Reservoir, Ga. 
35B. Claiborne Lock and 
Dam, Ala. 
35C. Jones Bluff Lock 
and Dam, Ala. 
Maint: 
Approp. 409,200 126,176 925,047 210,977 1,902,012 
Cost 191,588 400,563 520,121 616,503 1,901,812 
New Work: 
Contrib. - - - - 510,000 
Cost - - - 510,000 
Maint: 
Contrib. 10,325 - - - 10,325 
Cost 10,325 - - - 10,325 
Maint: 
Approp. 33,678 36,300 38,000 30,000 902,671 
Cost 29,847 40,388 37,824 29,444 901,939 
New Work: 
Approp. 5,002,900 8,305,000 14,401,000 31,530,997 62,886,25124 
Cost 3,681,423 5,591,252 12,855,400 35,831,936 61,522,356 
Maint: 
Approp. - - - - 234,33125 
Cost - - - - 234,331 
New Work: 
Approp. - -430,000 - - 7,130,500 
Cost 23,141 9,377 7,015 28,005 7,082,831 
New Work: 
Contrib. - - - - 718,000 
Cost - - - - 718,000 
New Work: 
Approp. 13,800 - -2,734 - 9,017,628 
Cost 54,952 -4 8 - 9,017,628 
Maint: 
Approp. 172,700 258,100 172,400 215,100 1,287,092 
Cost 167,567 242,090 179,417 202,492 1,249,953 
New Work: 
Approp. 357,900 400,000 352,734 -143,877 1,206,757 
Cost 219,091 388,117 105,809 246,675 1,182,034 
New Work: 
Approp. - - 100,000 158,000 258,000 
Cost - - 8,871 234,028 242,899 
New Work: 
Approp. - - - - 134,801 
Cost - - - - 134,801 
Maint: 
Approp. 40,000 250,500 466,800 - 907,000 
Cost 35,308 109,307 611,760 403 906,311 
New Work: 
Approp. 911,000 690,000 725,000 -780,000 5,321,925 
Cost 908,204 947,113 711,229 131,229 5,115,146 
New Work: 
Contrib. - - - - 48,700 
Cost 18,000 - - - 48,700 
New Work: 
Approp. 12,991,828 36,911,250 27,073,000 13,311,672 268,273,40826 
Cost 14,399,539 28,045,207 35,642,985 19,204,314 267,398,352 
Maint: 
Approp. 1,497,115 2,098,184 2,152,300 2,407,300 13,675,57427 
Cost 1,415,851 1,683,138 2,392,395 2,274,196 13,265,122 
New Work: 
Approp. 9,259,300 20,900,000 12,148,000 6,500,000 103,046,340 
Cost 9,563,226 13,827,000 18,727,981 9,224,348 102,683,612 
New Work: 
Approp. 746,250 125,000 - 27,872,450 
Cost 1,248,802 1,102,078 255,102 93,029 27,864,064 
New Work: 
Approp. 2,957,800 10,740,000 14,760,000 7,000,000 65,773,800 
Cost 2,711,584 9,855,379 15,290,468 9,288,682 65,736,243 
10-28

MOBILE, ALA., DISTRICT 
TABLE 10-A(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY72 FY73 FY74 FY75 June 30, 1975 
35D. Millers Ferry Lock 
and Dam, Ala. 
36. Allatoona Lake, 
Coosa River Basin, 
Ga. 
37. Apalachicola, 
Chattahoochee, 
and Flint Rivers, 
Ala. and Ga. 
37A. Lake Sidney 
Lanier, Ga 
37B. George W. Andrews 
Lock and Dam, 
Ala. and Ga. 
37C. Jim Woodruff Lock 
and Dam. Ga. and 
Fla. 
37D. Sprewell Bluff Lake, 
Ga. 
37E. Walter F. George 
Lock and Dam, 
Ala. and Ga. 
37F. West Point Lake, 
Chattahoochee River 
Basin, Ga. and Ala. 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
100,210 
99,249 
4,828 
796,138 
655,455 
642,526 
-18,000 
24,847 
1,111,300 
984,852 
15,458,800 
18,348,424 
6,723,359 
6,222,790 
-2,400 
198 
1,193,316 
1,029,755 
33 
33 
46,600 
13,876 
1,334,219 
1,198,613 
1,714,600 
300,930 
744,800 
22,369 
2,077,200 
1,926,226 
12,607,600 
17,959,110 
178,668 
162,363 
3,820,000 
2,546,007 
756,870 
765,121 
171,878 
130,940 
1,061,139 
1,123,119 
27,005,122 
30,487,043 
6,277,747 
6,066,213 
372,000 
96,841 
1,078,447 
1,189,148 
33 
33
63,122 
27,346 
1,092,301 
1,160,973 
-1,576,000 
33,689 
-54,000 
134,058 
1,868,275 
1,911,787 
28,560,000 
29,880,377 
239,000 274,300 
249,091 253,754 
- 45,000 
1,122,353 279,735 
751,300 990,000 
748,919 973,722 
81,600 948,100 
93,312 84,404 
1,086,300 1,302,100 
1,104,603 1,316,101 
17,391,937 10,067,000 
16,700,753 9,733,875 
5,767,850 
6,011,600 
212,000 
233,505 
1,093,400 
1,075,201 
-15 
33 
33
13,588 
10,711 
1,391,700 
1,189,536 
-69,000 
88,310 
9,300 
489,288 
1,255,900 
1,328,293 
17,236,111 
15,877,734 
792,178 
764,457 
62,614,778 
62,452,793 
4,290,885 
4,246,476 
33,828,89528 
32,919,773 
12,975,943 
12,925,083 
312,765,51429 
309,377,112 
6,887,554 65,097,49830 
7,157,417 64,821,483 
1, 377,000 48,020,75631 
266,376 47,656,433 
1,158,000 12,385,727 
1,265,112 12,316,216 
- 13,038,42732 
- 13,038,42732 
33 33 
33 33 33 33 
69,001 
1,313,000 
1,533,674 
2,772 
240,000 
91,857 
1,434,000 
1,458,482 
9,450,000 
9,303,869 
147,700 
138,253 
47,605,65734 
47,600,924 
14,251,481 
14,194,213 
2,169,600 
2,154,715 
86,837,5373, 
86,578,293 
16,809,88436 
16,746,621 
107,911,411 
105,166,194 
147,700 
138,253 
1. Includes $134,613 for previous projects and $28,500 
for DPR on Two-Mile. 
2. Includes $168,766 for previous projects. 
3. Estimated cost for providing spoil dikes for work 
authorized by 1965 River and Harbor Act. 
4. Includes $44,382 for previous projects of which $5,000 
was contributed funds. 
5. Includes $96,509 for previous projects of which 
$10,200 was contributed funds. 
6. Includes $606,931 for previous projects and $554,110 
for recreational facilities (Code 710) on completed projects. 
7. Includes $50,000 for previous projects. 
8. Includes $71,175 for previous projects. 
9. Includes $110,700 for previous projects. 
10. Includes $45,605 for previous projects. 
11. Includes $65,137 for previous projects. 
12. Includes $269,017 for previous projects. 
13. Includes $2,312,297 for previous projects and 
$442,836 Special O and M funds. 
14. Includes $6,683,104 for previous projects, $14,000 
Public Work funds, and $41,242 Emergency Relief funds. 
15. Includes $4,096,681 for previous projects and 
$494,136 Special O and M funds. 
16. Includes $203,560 for previous projects. $581,959 
10-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-A(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY72 FY73 FY74 FY75 June 30,1975 
Public Works funds, and $457,467 rehabilitation of jetties un- 29. Includes $1,883,193 Federal funds and $1,924 conder 
existing project. tributed funds for previous projects; $4,508,570 Code 710 
17. Includes $513,604 for previous projects. funds for recreational facilities at completed projects 
18. Includes $904,442 for previous projects. ($2,867,338 for Lake Sidney Lanier, $1,123,497 for Jim 
19. Includes $412,624 for previous projects, $124,565 Woodruff, $84,014 for George W. Andrews, and $857,955 for 
Special 0 and M funds, and $829,472 Emergency Work Walter F. George). 
Funds. 30. Includes $2,246,233 for previous projects. 
20. Includes $144,443 for previous projects and $143,971 31. Includes $2,867,338 for recreational facilities (Code 
for recreation facilities (Code 710) on completed projects. 710). 
21. Includes 168,172 for previous projects. 32. Includes $84,014 for recreational facilities (Code 
22. Includes 594,688 for previous projects. 710). 
23. Includes 126,649 for previous projects. 33. Included under maintenance for overall 
24. Includes 197,651 for previous projects. Apalachicola, Chattahoochee and Flint Rivers project. 
25. Includes $234,331 for previous projects. 34. Includes $1,123,497 for recreational facilities (Code 
26. Includes 3,692,483 for previous projects. 710). 
27. Includes 2,978,050 for previous projects. 35. Includes $857,955 for recreational facilities (Code 
28. Includes $1,492,125 for recreational facilities (Code 710). 
710). 36. Includes $200,000 for flood protection. 
TABLE 10-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
APALACHICOLA BAY, FLA. (See Section 1 of Text) 
Channel 18 feet deep through West Pass and Link Channels, 
10 feet deep across the inner bar, and 9 feet deep 
through Bulkhead Shoals. 
Modify project to provide for channel 10 feet deep from 
mouth of inner bar channel to Gulf via Link and West 
Pass Channels, and 10-foot depth in Bulkhead Shoals 
Channel. 
At Eastpoint, Fla., a channel 6 feet deep, 100 feet wide, 
and about 6,000 feet long, parallel to shore, with 
connecting channel 6 feet deep and 100 feet wide to St. 
George Sound, and at Apalachicola, Fla., a small-boat 
basin 200 feet and 9 feet deep, with a connecting 
channel 9 feet deep and 80 feet wide through Scipio 
Creek to the Apalachicola River. 
Modify project to provide for a channel 10 feet deep and 
100 feet wide from the 10-foot depth in Apalachicola 
Bay across St. George Island to within 300 feet of the 
Gulf shore, thence increasing uniformly in width to 200 
feet at shore and continuing at this width to the 10-foot 
depth in the Gulf, with two jetties extending from the 
dune line on St. George Island to the outer end of 
channel, and for abandonment of West Pass Channel upon 
completion of channel through St. George Island. 
Modify improvement of Apalachicola Bay, Fla., authorized 
by River and Harbor Act of Sept. 3, 1954 to provide 
that the Secretary of the Army shall reimburse local 
interests for such approved work as they may have done 
based upon the reduction in the amount of material 
which will have to be removed to provide project 
dimensions at such time as Federal dredging of the 
channels is undertaken. 
A channel 6 feet deep, 100 feet wide and about 1 mile long, 
parallel to shore at Two Mile, Fla., with a 6-by 100-foot 
connecting channel to water of the same depth in 
Apalachicola Bay. 
Modify existing Two Mile project to provide a channel 
6 feet deep and 100 feet wide extending from the eastern 
end of the existing Two Mile channel and generally 
paralleling the shoreline for a distance of about 8,800 
feet to intersect with the Gulf Intracoastal Waterway 
about 1,650 feet south of Gorrie Bridge at Apalachicola, 
and, a breakwater built to elevation 7.0 feet above mean 
low water along the seaward side of the existing channel 
parallel to the shore at Two Mile. The total length of the 
H. Doc. 422, 59th Cong., 
1st Sess. 
H. Doc. 106, 69th Cong., 
1st Sess. 
H. Doc. 156, 82d Cong., 
1st Sess. 
H. Doc. 557, 82d Cong., 
2d Sess. 
DPR 
DPR 
10-30 
Mar. 2, 1907 
Jan. 21, 1927 
Sept. 3, 1954 
Sept. 3, 1954 
July 3, 1958 
Nov. 21, 19631 
Feb. 5, 19751

MOBILE, ALA., DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Work Authorized 
breakwater would be about 6,800 including two 1,000 foot 
legs paralleling the existing entrance channel. 
AQUATIC PLANT CONTROL (See Section 2 of Text) 
Aquatic plant control for N.C., S.C., Ga., Fla., Ala., Miss., 
and La. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
June 2, 19691 
Oct. 27, 1965 
July 3, 1930 
June 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
May 17, 1950 
July 14, 1960 
Nov. 7, 1966 
July 5, 1884 
Mar. 3, 1899 
Sept. 19, 1890 
Sept. 19, 1890 
Documents 
BAYOU CODEN, ALA. (See Section 3 of Text) 
Channel 4 by 40 feet. 
Channel 8 by 60 feet to connect'with Bayou La Batre 
channel. 
BAYOU LA BATRE, ALA. (See Section 4 of Text) 
A 12- by 100-foot channel from that depth in Mississippi 
Sound to a point about 2,800 feet south of the highway 
bridge, thence a channel 12 by 75 feet to the bridge, an 
overall distance of about 33,500 feet. 
BILOXI HARBOR, MISS. (See Section 5 of Text) 
Channel 10 feet deep and 150 feet wide from Mississippi 
Sound west and north of Deer Island to deep water in 
Back Bay of Biloxi. 
Relocation of channel. 
Entrance channel 6 feet deep and 50 feet wide into Old 
Fort Bayou. 
Entrance channel 8 feet deep and 100 feet wide through 
Cranes Neck into Bayou Bernard. 
Maintain channel 6 feet deep and 40 feet wide from Biloxi 
Harbor to Ott Bayou. 
Continuous channel 12 feet deep from Mississippi Sound to 
the Air Force terminal on Bayou Bernard via Back Bay 
and Cranes Neck. 
A 23-mile-long through channel 12 feet deep and 150 feet 
wide from the Gulf Intracoastal Waterway through: 
Mississippi Sound, Biloxi Bay (east of Deer Island), Back 
Bay, Big Lake, and via land cut to Gulfport Lake, 
including a 500- by 2,600-foot turning basin in the lake, 
thence, a channel 12 by 100 feet from the western end of 
Gulfport Lake for about 2 miles to a 300- by 500-foot 
turning basin; adoption for maintenance of a 12- by 150- 
foot spur channel from the main channel in Biloxi Bay, 
westward about 1 mile to a 400- by 600-foot turning basin 
opposite Ott Bayou, and abandonment of the existing 6- by 
40-foot channel into Ott Bayou; continuation of maintenance 
of the 12-by 150-foot lateral channel westward about 2.2 
miles from the main channel in Biloxi Bay to a point 
opposite Oak Street; continuation of maintenance of the 
channel west of Deer Island. 
BLACK WARRIOR AND TOMBIGBEE RIVERS, ALA. 
(See Section 6 of Text) 
Original appropriation for improving Black Warrior River. 
Original project for slack-water improvement authorized by 
Secretary of War, Apr. 19, 1887. 
Construction of the first locks between Tuscaloosa and 
Demopolis. 
(Maintenance of the section of Tombigbee River below 
lock 1 to its mouth (66 miles) included in the existing 
project.) 
Construction of locks and dams 1, 2, and 3. Merging of 
the individual project for the Black Warrior and Warrior 
Rivers and the Tombigbee River below Demopolis. 
10-31 
Acts 
H. Doc. 37, 85th Cong., 
1st Sess. 
Public Law 87-874, 
87th Cong. 
H. Doc. 251, 89th Cong., 
1st Sess. 
H. Doc. 824, 77th Cong., 
2d Sess. 
DPR 
H. Doc. 327, 88th Cong., 
2d Sess. 
H. Doc. 754, 69th Cong., 
2d Sess. 
H. Doc. 639, 75th Cong., 
3d Sess. 
H. Doc. 258, 76th Cong., 
1st Sess. 
H. Doc. 326, 76th Cong., 
1st Sess. 
H. Doc. 256, 81st Cong., 
1st Sess. 
H. Doc. 271, 86th Cong., 
2d Sess. 
H. Doc. 513, 89th Cong., 
2d Sess. 
Annual Report, 1887, 
pt. 2, p. 1302. 
H. Doc. 178, 56th Cong., 
2d Sess., and Annual 
Report, 1901, pt. 3, 
p. 1858. 
H. Doc. 165, 57th Cong.,

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
Mar. 3, 1909 
Aug. 22, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
June 26, 1934 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
July 14, 1960 
Mar. 2, 1945 
Sept. 3, 1954 
May 19, 19691 
Oct. 24, 1951 
Oct. 27, 1965 
July 3, 1958 
Construction of locks and dams 14, 15, 16, and 17. 
Provides for reconstruction of obsolete structures, modified 
in plan and location, to provide efficient and economical 
maintenance and operation. 
Lift of lock 17 changed to 63 feet, and construction of locks 
and dams 18 and 19 eliminated from the project. 
Extension of slack-water improvement to Sanders Ferry 
on Mulberry Fork and Nichols Shoal on Locust Fork. 
Raising of various dams 2 feet and raising the lock walls 2 
feet at lock 1 to provide a minimum depth of 8 feet at 
low water, widening the channel to 150 feet where 
practicable. 
For snagging Mobile River from the mouth of Chickasaw 
Creek to the junction of the Alabama and Tombigbee 
Rivers. 
Increase channel dimensions to 9 by 200 feet; construct 
crest gates at lock and dam 17; add flashboards at all 
dams; Sunflower Bend Cutoff. 
Construction of a lock and dam below Tuscaloosa to replace 
original locks and dams 10, 11, and 12. 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Recreation facilities. 
Construction of a lock and dam near Demopolis to replace 
existing dams 4, 5, 6, and 7. 
Provide increased spillway capacity at dam 1. 
Coffeeville Lock and Dam Wildlife Refuge. 
DAUPHIN ISLAND BAY, ALA. 1(See Section 7 of Text) 
A channel 7 feet deep and 150 feet wide from Mobile Bay 
to an anchorage basin of same depth, about 7 acres in 
area, in marsh just north of Fort Gaines on Dauphin 
Island; a channel 4 feet deep and 40 feet wide from 
anchorage basin to Dauphin Island Bay; and a jetty 
and revetment to protect entrance channel; and (b) an 
anchorage basin 7 feet deep and 500 feet square at 
Dauphin Island Village, with an entrance channel of 
like depth, 100 feet wide and about 8,300 feet long, 
extending to 7-foot hydrographic contour in Mississippi 
Sound. 
DOG AND FOWL RIVERS, ALA. (See Section 8 of Text) 
To provide small craft navigation on west side of Mobile 
Bay. 
EAST PASS CHANNEL FROM GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FLA. (See Section 9 of Text) 
Maintenance of 12-foot channel from Choctawhatchee Bay 
into Gulf, and maintenance of 6-foot channel into Old 
Pass Lagoon. 
Construction of twin jetties. 
(Present project dimensions.) 
ESCAMBIA AND CONECUH RIVERS, FLA. AND ALA. 
(See Section 10 of Text) 
A 10- by 100-foot channel in Escambia Bay for 5.5 miles 
to mouth of Escambia River, thence up Escambia River 
to about mile 7, thence a channel 5 feet deep for 50 
miles to Florida State line, and thence improvement of 
Conecuh River to mouth of Patsaliga Creek, a distance 
of 80.5 miles. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FLA., AND MEXICAN BORDER 
(Mobile District) (See Section 11 of Text) 
10-32 
1st Sess., and Annual 
Report, 1902, p. 1293. 
Public Law 317. 
H. Doc. 72, 62d Cong., 
1st Sess. 
Annual Report, 1918, 
p.876. 
H. Doc. 728, 71st Cong., 
3d Sess. 
H. Doc. 56, 73d Cong., 
1st Sess., and Rivers 
and Harbors Committee 
Doc. 45, 73d Cong. 
Rivers and Harbors 
Committee Doc. 26, 
74th Cong., 1st Sess. 
H. Doc. 276, 76th Cong., 
1st Sess. 
H. Doc. 382, 76th Cong., 
1st Sess. 
S. Doc. 50, 86th Cong., 
1st Sess. 
H. Doc. 333, 76th Cong., 
1st Sess. 
H. Doc. 394, 82d Cong., 
2d Sess. 
DPR 
H. Doc. 470, 81st Cong., 
2d Sess. 
H. Doc. 194, 88th Cong., 
2d Sess. 
H. Doc. 75, 85th Cong., 
1st Sess.

MOBILE, ALA., DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 26, 1937 
June 25, 1910 
Aug. 30, 1935 
June 25, 1910 
Aug. 30, 1935 
July 3, 1930 
July 3, 1930 
July 3, 1930 
July 23, 1942 
June 17, 1943 
Mar. 2, 1945 
May 17, 1950 
Nov. 7, 1966 
Mar. 3, 1899 
Mar. 2, 1907 
Feb. 27, 1911 
Jan. 21, 1927 
July 23, 1930 
June 30, 1948 
APALACHICOLA BAY TO ST. MARKS RIVER, FLA. 
A channel 9 feet and 100 feet wide at mean low water 
from Apalachicola Bay, Fla., via St. George Sound, 
Carrabelle, Crooked, and Ochlockonee Rivers and 
Ochlockonee and Apalachee Bays to St. Marks River, Fla. 
APALACHICOLA RIVER TO ST. ANDREW BAY, FLA. 
A channel 5 feet deep at mean low water and 65 feet 
wide at the bottom. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
CHOCTAWHATCHEE BAY TO WEST BAY, FLA. 
A channel 9 feet deep at mean low water and 100 feet wide 
at the bottom. 
A channel 6 feet deep at mean low water, with no 
reference to width. 
CHOCTAWHATCHEE BAY TO PENSACOLA BAY, FLA. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
PENSACOLA BAY, FLA., TO MOBILE BAY, ALA. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
MOBILE BAY, ALA., TO NEW ORLEANS, LA. 
A channel 300 feet wide and 10 ffeet from the 10 
foot contour in Mobile Bay to the 10-foot contour 
in Mississippi Sound. 
A channel 100 feet wide and 9 feet deep from Lake 
Pontchartrain to Mississippi Sound. 
APALACHEE BAY, FLA., TO NEW ORLEANS, LA 
A channel 12 feet deep and 125 feet wide at mean low 
water, except in the section between Mobile, Ala., 
and New Orleans, La., where the width is to be 
150 feet. 
Conditional acquisition of Gulf County Canal, Fla., 
and enlargement of the canal to 9 feet deep and 100 
feet wide. 
Construction of a movable span in the Georgia, Florida 
& Alabama R.R. bridge crossing the Ochlockonee River. 
Abandonment and closure of original channel between 
Big Lagoon and Pensacola Bay and construction of a 
new channel to enter the bay north of original 
entrance. 
Authorized enlargement of Gulf County Canal to 12 by 
125 feet. 
GULFPORT HARBOR, MISS. (See Section 12 of Text) 
A channel 19 feet deep and 300 feet wide from the 
anchorage basin at Ship Island to Gulfport, Miss., and an 
anchorage basin next to the shore end 19 feet deep and not 
less than 2,640 feet by 1,320 feet in area. 
Combined Ship Island Pass with Gulfport Harbor project. 
Increased depth to 26 feet and width to 300 feet across 
Ship Island Bar and depth to 19 feet in channel from 
Anchorage basin at Ship Island to Anchorage basin at 
Gulfport. 
Authorized relocation of channel across Ship Island Bar. 
Increased depth to 27 feet and width to 300 feet across 
Ship Island Bar, 26 feet deep and 220 feet wide through 
Miss. Sound and depth of 26 feet in the Anchorage Basin 
at Gulfport. 
Increased depth of 32 feet and width to 300 feet across 
10-33 
H. Doc. 291, 75th Cong., 
1st Sess. 
H. Doc. 670, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 52, 
72d Cong., 2d Sess. 
H. Doc. 259, 72d Cong., 
1st Sess. 
H. Doc. 565, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 42, 
73d Cong., 2d Sess. 
H. Doc. 42, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
71st Cong., 1st Sess. 
H. Doc. 341, 71st Cong., 
2d Sess. 
Public Law 675, 77th 
Cong. and H. Doc. 96, 
79th Cong., 1st Sess. 
H. Doc. 257, 76th Cong., 
1st Sess., and Public 
Law 75, 78th Cong. 
H. Doc. 442, 76th Cong., 
1st Sess. 
H. Doc. 325, 81st Cong., 
1st Sess. 
Public Law 89-789, 89th 
Cong., 2d Sess. 
H. Doc. 120, 55th Cong., 
3d Sess. 
H. Doc. 2, 60th Cong., 
1st Sess. 
H. Doc. 692, 69th Cong., 
2d Sess. 
H. Doc. 112, 81st Cong.,

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
Sept. 3, 1954 
July 26, 1970 (SR) 
Dec. 15, 1970 (HR) 
Aug. 30, 1935 
Mar. 2, 1945 
June 30, 1948 
June 14, 1972 
Mar. 4, 1913 
Mar. 4, 1915 
May 17, 1950 
Sept. 3, 1954 
Ship Island Bar, 30 feet deep and 220 feet wide through 
Miss. Sound, and a depth of 30 feet in the Anchorage 
Basin at Gulfport. 
Maintenance of the existing commercial small-boat harbor 
and an approach channel 100 feet wide and 4,300 feet 
long, from deep water in Miss. Sound to the small-boat 
basin, all at a depth of 8 feet. 
MOBILE HARBOR, ALA. (See Section 13 of Text) 
For improvement of Threemile Creek by snagging from 
Mobile River to the Industrial Canal. 
Adoption of existing channel through Garrows Bend from 
Choctow Point to Arlington pier, 27 feet deep and 150 
feet wide, with 2 turning basins. Adoption of the 
existing channel alongside Arlingtoh pier from the 
Mobile Bay Channel to turning basin at the inner end 
of Garrows Bend Channel, 27 feet deep and 150 feet wide. 
A channel 25 feet deep and generally 500 feet wide in 
Mobile River from the highway bridge to the mouth of 
Chickasaw Creek, thence 25 feet deep and 250 feet wide in 
Chickasaw Creek to a point about 400 feet below Shell 
Bayou. 
Enlarging Mobile Bar Channel to 42 by 600 feet. 
Enlarging Mobile Bay Channel to 40 by 400 feet. 
Deepening Mobile River Channel below highway bridge to 
40 feet over present widths, including existing 
turning basins and anchorage areas. Widening river 
channel opposite Magazine Point to provde a 40- by 800- 
by 1,400-foot turning basin. 
Closure of Garrows Bend Channel by construction and 
operation of an earth-filled causeway across said channel 
(work to be done by local interests). 
To provide a channel 40 feet deep and 400 feet wide from 
the main ship channel in Mobile Bay and extending 
northwesterly for about 5.3 miles to the shore of Mobile 
Bay, thence a land-cut 40 feet deep, 300 feet wide and 
about 1.9 miles long to and including a turning basin 40 
feet deep and approximately 42 acres, and 40 feet deep, 
300 feet wide and 1200 feet long, located adjacent to the 
proposed channel near Bay shoreline. 
PANAMA CITY HARBOR, FLA. (See Section 14 of Text) 
Channels 27 and 29 feet deep. Abandonment of project 
adopted by act of June 25, 1910. 
Maintenance of a channel in Watson Bayou 100 feet wide 
and 10 feet deep from that depth in St. Andrew Bay to 
the highway bridge. 
Channels 32 and 34 feet deep. 
Channels 38, 40, and 42 feet deep. 
PASCAGOULA HARBOR, MISS. (See Section 15 of Text) 
Provides for through channel from the Gulf to mile 4 on 
Dog River, 25 by 300 feet through Horn Island Pass, 
thence 22 by 225 feet across Mississippi Sound and up 
Pascagoula River to the railroad bridge, thence 22 by 
150 feet in Pascagoula River above bridge, and up Dog 
River to mile 4, all subject to financial participation 
by local interests. 
Waived requirement for financial participation by local 
interests. 
Cutoff channel, 12 by 125 feet, from State Highway 63 
bridge to mile 4 on Dog River, via Robertson and 
Bounds Lakes. 
Modification to provide for channel dimensions of 35 by 
325 feet through Horn Island Pass, thence 30 by 275 feet 
across Mississippi Sound and up Pascagoula River to the 
railroad bridge, and a turning basin just below the 
bridge. 
1st Sess. 
S. Doc. 123, 84th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 69, 
74th Cong., 1st Sess. 
H. Doc. 739, 79th Cong., 
2d Sess. 
H. Doc. 74, 83d Cong., 
1st Sess. 
H. Doc. 74, 83d Cong., 
2d Sess. 
(Under provision of 
Section 201 of the 
1965 Flood Control 
Act) 
H. Doc. 33, 73d Cong., 
1st Sess. 
H. Doc. 555, 76th Cong., 
3d Sess. 
H. Doc. 559, 80th Cong., 
2d Sess. 
H. Doc. 196, 92d Cong., 
2d Sess. 
H. Doc. 682, 62d Cong., 
2d Sess. 
River and Harbor 
Committee Doc. 12, 
63d Cong., 2d Sess. 
H. Doc. 188, 81st Cong., 
1st Sess. 
H. Doc. 98, 86th Cong., 
1st Sess. 
10-34

MOBILE, ALA., DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
July 14, 1960 
July 14, 1960 
Oct. 23, 1962 
Mar. 2, 1945 
June 14, 1880 
Apr. 21, 1900 
Aug. 30, 1935 
Nov. 7, 1966 
June 13, 1902 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Aug. 27, 1962 
Oct. 27, 1965 
Reimbursement of local interests for work done on Dog 
River cutoff ($44,000). 
Modification to provide for maintenance of 12- by 125-foot 
channel to mile 6 on Dog River, and maintenance of 30- by 
225-foot side channel from main ship channel in 
Mississippi Sound to the mouth of Bayou Casotte, thence 
30 by 300 feet in Bayou Casotte to a turning basin of the 
same depth 1 mile above the mouth. 
Deepening the Horn Island Pass channel to 38 feet and 
deepening the main ship channel in Mississippi Sound, 
the river channel to the railroad bridge, and the 
turning basin all to 33 feet. 
Enlarging Horn Island Pass Channel to 40 by 350 feet, 
provision of an impounding area adjacent to and east of 
channel 40 feet deep, 200 feet wide, and about 1,500 feet 
long, enlarging main channel in Mississippi Sound and 
river channel to railroad bridge to 38 by 350 feet, and 
deepening turning basin in river and Bayou Casotte 
channels and basin to 38 feet. 
PASS CHRISTIAN HARBOR, MISS. (See Section 16 of Text) 
Provides for improvement and maintenance of a harbor within 
existing bulkheads and breakwaters constructed by local 
interests, and of an entrance channel, both to a depth of 
7 feet. Entrance channel is 100 feet wide and harbor is 
about 1,000 feet along the shore by 700 feet wide. 
PEARL RIVER, MISS. AND LA. (See Section 17 of Text) 
Provided for a 5-foot channel. 
Legalized construction of a fixed highway bridge at 
Rockport. 
A channel from the mouth of West Pearl River for 58 
miles to the mouth of Bogalusa Creek at Bogalusa, 
La., 7 feet deep at low water with a bottom width 
of 100 feet in the river sections and 80 feet in 
the canal section; with locks 65 by 310 feet clear 
inside dimensions. 
Construction of cut-offs and easement of critical 
bends at eight locations below lock 1 with no 
increase in project depth. 
PENSACOLA HARBOR, FLA. (See Section 18 of Text) 
A channel 30 feet deep at mean low water and 500 feet 
wide from the Gulf of Mexico to the dock line at the 
east end of the city of Pensacola, and also provided 
that $150,000 may be used in constructing or purchasing 
a seagoing suction dredge. 
Modified the existing project for the present inner 
channels and the deepening of the entrance channel 
to 32 feet. 
Improvement of Bayou Chico. 
Modified improvement of Bayou Chico, Fla. 
Maintenance of the entrance channel from the Gulf of 
Mexico to lower Pensacola Bay, a distance of about 5 
miles to dimensions of 35 feet deep and 500 feet wide; 
maintenance of a channel along the south side of the 
aircraft carrier mooring basin, a distance of about 2.5 
miles, to dimensions of 33 feet deep and 300 feet wide; 
a bay channel 33 feet deep, 300 feet wide, and about 2.1 
miles long; parallel approach channels to opposite ends 
of the inner-harbor channel, about 1.3 and 1.4 miles in 
length, each 33 feet deep, 300 feet wide, and flared at 
the junctions with the inner-harbor channel; and 
deepening the existing 500-foot wide inner-harbor channel 
to a depth of 33 feet and lengthening it to 3,950 feet. 
PERDIDO PASS CHANNEL, ALA. (See Section 19 of Text) 
A 12- by 150-foot channel stabilized by twin rubblemound 
H. Doc. 253, 72d Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 96, 
74th Cong., 2d Sess. 
H. Doc. 743, 79th Cong., 
2d Sess. 
H. Doc. 528, 87th Cong., 
2d Sess. 
S. Doc. 94th Cong., 
10-35 
H. Doc. 98, 86th Cong., 
1st Sess. 
Chief of Engineers Report 
dated Nov. 3, 1960. 
H. Doc. 560, 87th Cong., 
2d Sess. 
H. Doc. 214, 77th Cong., 
2d Sess. 
H. Doc. 98, 45th Cong., a Sass. 
H. Doc. 145, 65th Cong., 
1st Sess. 
H. Doc. 408, 75th Cong., 
2d Sess. 
H. Doc. 482, 89th Cong., 
2d Sess.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
June 18, 1902 
Mar. 2, 1907 
July, 25, 1912 
July 27, 1916 
July 24, 1946 
jetties, from the Gulf of Mexico into Perdido Pass, 2d Sess. 
thence 9 by 100 feet into Perdido Bay with a spur channel 
of the same dimensions into Terry Cove. 
REMOVING WATER HYACINTHS, MOBILE DISTRICT 
(See Section 20 of Text) 
Appropriations made for the States of Florida and Louisiana 
and provided for the extermination or removal of plants, 
the building of boats, and the establishment of booms. 
Use of any mechanical, chemical, or other means whatsoever. 
Appropriation made for Florida, provided that no chemical 
process injurious to cattle shall be used. 
Appropriation made available for the State of Mississippi, 
and also made available for use in that State the 
operating plant pertaining to the work of Louisiana. 
Appropriation made available for the State of Alabama. 
WATERWAY CONNECTING TOMBIGBEE AND 
TENNESSEE RIVERS, ALA. AND MISS. 
(See Section 21 of Text) 
A waterway connecting Tennessee and Tombigbee Rivers via 
East Fork of Tombigbee River, Mackeys and Yellow Creeks. 
Plan of improvement consists of three sections: river 
section, 9- by 300-foot channel for 168 miles between 
Demopolis and Amory, Miss.; canal section, 12 by 300 
feet for 45 miles from Amory to Bay Springs; divide section, 
12 by 300 feet (except in the 26 mile-long divide cut in 
which bottom width would be 280 feet) for 40 miles from 
Bay Springs through dividing ridge to Tennessee. Total 
lift of 341 feet to be accomplished by 10 locks. 
FLOOD CONTROL 
JACKSON AND EAST JACKSON, MISS. (See Section 22 
of Text) 
Provides for improvement of Pearl River at Jackson, Miss., 
for flood control, to be obtained by construction of 
levees about 62,620 feet long, three pumping stations, 
and 5.04 miles of channel rectification including a 
cutoff 2.3 miles long in Pearl River. 
OKATIBBEE LAKE, MISS. (See Section 27 of Text) 
Provides for a dam and reservoir for flood control, 
water supply, water quality control, and recreation. 
TALLAHALA CREEK LAKE, PASCAGOULA RIVER, 
MISS. (See Section 28 of Text) 
Provides for a dam and reservoir for flood control, water 
supply, water quality control, recreation, and fish and 
wildlife enhancement. 
EDINBURG LAKE, MISS. (See Section 29 of Text) 
Provides for a dam and reservoir for flood control, 
water quality control, general recreation, fish and 
wildlife enhancement, and area redevelopment. 
TOMBIGBEE RIVER, MISS. AND ALA. (See Section 30 
of Text) 
Provides for alleviation of floods from the Tombigbee 
River by clearing, snagging, and excavation of 13 
cut-off channels, and other related channel improvements. 
TOMBIGBEE RIVER TRIBUTARIES, MISS. AND ALA. 
(See Section 31 of Text) 
Provides for improvement of 22 tributaries of Tombigbee 
River. 
MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
ALABAMA-COOSA RIVERS, ALA. AND GA. (See Section 
35 of Text) 
H. Doc. 441, 86th Cong., 
2d Sess. 
H. Doc. 549, 87th Cong., 
2d Sess. 
H. Doc. 143, 90th Cong., 
1st Sess. 
H. Doc. 282, 92d Cong., 
2d Sess. 
Special Report on Record 
in OCE. (Public Law 
222, 77th Cong., 1st 
Sess. 
H. Doc. 167, 84th Cong., 
1st Sess. 
10-36 
H. Doc. 91, 55th Cong., 
1st Sess. 
H. Doc. 486, 79th Cong., 
2d Sess. 
July 14, 1960 
Oct. 23, 1962 
June 7, 1968 
Mar. 7, 1974 
Aug. 18, 1941 
July 23, 1958

MOBILE, ALA., DISTRICT 
TABLE 10-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
June 28, 1954 
Aug. 18, 1941 
Dec. 22, 1944 
Mar. 2, 1945 
July 24, 1946 
Dec. 22, 1944 
July 24, 1946 
Dec. 22, 1944 
July 24, 1946 
May 19, 1953 
Dec. 22, 1944 
July 24, 1946 
Dec. 22, 1944 
Dec. 30, 1965 
May 19, 1953 
Dec. 22, 1944 
Oct. 23, 1962 
Provides for full development of Alabama-Coosa Rivers 
and tributaries for navigation, flood control 
power, recreation, and other purposes. 
Authorized construction of Carters Lake, Ga., 
Claiborne Lock and Dam, Ala., Jones Bluff Lock 
and Dam, Ala., and Millers Ferry Lock and Dam, Ala. 
Suspended comprehensive plan to permit non-Federal 
interests to develop Coosa River by constructing 
series of dams. 
ALLATOONA LAKE, COOSA RIVER BASIN, GA. (See 
Section 36 of Text) 
Provides for dam and reservoir for flood control, regulation 
of stream flow for navigation, development of hydroelectric 
power and recreation. 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT 
RIVERS, ALA., GA. AND FLA. (See Section 3' of Text) 
Development of Apalachicola, Chattahoochee, and Flint 
Rivers for navigation, flood control, hydropower, and 
recreation. 
Modified general plan for full development of 
Apalachicola, Chattahoochee, and Flint River System 
and authorized construction of Lake Sidney Lanier 
multipurpose reservoir. 
Authorized recreation facilities. 
LAKE SIDNEY LANIER, GA. (See Section 37A of Text) 
Modification of general plan for development of 
Apalachicola, Chattahoochee, and Flint Rivers 
to provide construction of dam and reservoir. 
Provision of recreation facilities. 
GEORGE W. ANDREWS LOCK AND DAM, ALA. AND GA. 
(See Section 37B of Text) 
Construction of high dam at Walter F. George site 
and low dam at George W. Andrews site. 
Approval of plan proposed in Act of July 24, 1946. 
Provided recreation facilities. 
JIM WOODRUFF LOCK AND DAM, GA. AND FLA. 
(See Section 37C of Text) 
Authorized construction. 
Provided recreation facilities. 
SPEWRELL BLUFF LAKE, GA. (See Section 37D of Text) 
Authorized construction. 
WALTER F. GEORGE LOCK AND DAM, ALA. AND GA. 
(See Section 37E of Text) 
Authorized construction of high dam at Walter F. George 
site and low dam at Columbia site. 
Recreation facilities added. 
WEST POINT LAKE, CHATTAHOOCHEE RIVER 
BASIN, GA. AND ALA. (See Section 37F of Text) 
Authorized construction for flood control, power, 
recreation, fish and wildlife development, and 
streamflow regulation for downstream navigation. 
H. Doc. 300, 80th Cong., 
1st Sess. 
H. Comm. Public Works. 
H. Doc. 300, 80th Cong., 
1st Sess. 
H. Doc. 567, 87th Cong., 
2d Sess. 
H. Comm. on Public Works. 
H. Doc. 570, 87th Cong., 
2d Sess. 
10-37 . 
H. Doc. 414, 77th Cong., 
1st Sess. 
Public Law 436, 83rd 
Cong. 
Public Law 228, 77th 
Cong., 1st Sess. 
H. Doc. 674, 76th Cong., 
3d Sess. 
H. Doc. 324, 7th Cong., 
1st Sess. 
H. Doc. 300, 80th Cong., 
1st Sess. 
H. Doc. 300, 80th Cong., 
1st Sess. 
1. Authorized by Chief of Engineers under Section 107 of 1960 River and Harbor Act.

TABLE 10-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
BLACK WARRIOR AND TOMBIGBEE RIVERS, ALA. 
(See Section 6 of Text) 
William John Hollis 
Coffeeville Demopolis Warrior Bacon Oliver Holt Bankhead 
Lock Lock Lock Lock Lock Lock 
and Dam and Dam and Dam and Dam and Dam and Dam' 
Miles above Mobile 2 116.7 213.2 261.1 338.2 347.0 365.5 
Nearest town (Alabama) Coffeeville Demopolis Eutaw Tuscaloosa Tuscaloosa Oak Grove 
Distance (miles) 3 2 6 (within city) 6 15 
Lock: 
Greatest length available 
for full width (feet) 600.0 600.0 600.0 460.0 600.0 600.0 
Width of chamber (feet) 110 110 110 95 110 110 
Maximum lift (feet) 34 40 22 28 64 68 
Depth over sills at low 
water (feet) 13.0 13.0 13.2 12.0 13.0 14.0 
Character of foundation Rock Rock Sand, clay Hard shale Shale, Sandstone 
sandstone 
Kind of spillway Fixed-Gated Fixed Gated Fixed Gated Gated 
Type construction 
Damck Concrete Concrete Concrete Concrete Concrete Concrete 
Dam Concrete Concrete Earth- Concrete Concrete Concrete 
Concrete 
Year completed 1965 1962 1962 1940 1969 Under const. 
Year opened to navigation 1960 1954 1957 1939 1966 1975 
Actual cost of lock and dam $21,597,2643 $19,774,5833 $13,295,5533 $4,450,874 $28,100,0003 $43,447,0574 
1. Single lift lock. 
2. Navigation mileage from foot of Government Street, 
Mobile, Ala. 
3. Excludes cost of adding recreation facilities. 
4. Cost to date (FY 75) tor replacement of single lift lock 
scheduled for completion in FY 76. Excludes $1,435,636 cost 
of land submerged, damage to structures, and cost of spillway. 
Also excludes $3,824,859 cost of original double lift lock. 
10-38

MOBILE, ALA., DISTRICT 
TABLE 10-D LOCKS IN PEARL RIVER PROJECT 
(See Section 17 of Text) 
Lock Pearl River Lock No. 1 Pearl River Lock No. 2 Pearl River Lock No. 3 
Miles above mouth 29.7 40.8 44.0 
Nearest town Pearl River, La. Bush, La. Sun, La. 
Miles to nearest town 9 3 2 
Greatest length available 310 310 310 
for full width (feet) 
Width of chamber (feet) 65 65 65 
Lift (feet) 26.7 15 11 
Depth over sills at low 10 10 10 
water (feet) 
Character of foundation Sand, gravel, silt, clay Sand, gravel, silt, clay Sand, gravel, silt, clay 
Type of construction Concrete and steel Concrete and steel Concrete and steel 
Year completed 1949 1950 1950 
Date opened for navigation November 1953 November 1953 November 1953 
Actual cost of lock $2,119,100 $1,967,537 $1,497,539 
TABLE 10-E RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 22 of Text) 
Cost During 
Project Date of Survey Fiscal Year 
Bon Secour, Ala. March 1975 $1,710 
Cadet Bayou, Miss. January 1975 4,102 
Carrabelle Harbor, Fla. July 1974 5,835 
East Pearl River, Miss. October 1974 8,226 
Fly Creek, Ala. April 1975 1,117 
LaGrange Bayou, Fla. March 1975 2,584 
Panacea Harbor, Fla. July 1974 3,415 
Pascagoula River, Miss. March 1975 6,903 
Port St. Joe, Fla. November 1974 9,018 
St. Marks River, Fla. July 1974 4,704 
Wolf and Jordan Rivers, Miss. May 1975 1,959 
Total 49,5731 
1. Other cost of surveys, included under 0 & M for Island Bay, Ala., $110; Escambia Bay, Ala., $5,621; Panama 
respective projects are: Biloxi Harbor, Miss., $2,253; Dauphin City, Fla., $3,594; Pensacola Harbor, Fla., $1,179. 
10-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-F OTHER AUTHORIZED NAVIGATION 
(See Section 23 of Text) 
PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Aquatic Plant Control (1958 & 62 Acts) 1968 $324,814 
Bayou Galere, Miss.' 1946 
Blackwater River, Fla. 1971 41,650 $235,554 
Bluff Creek, Miss.2 1963 1,000 6,883 
Bogue Chitto, La.' 1909 14,913 12,930 
Bon Secour River, Ala. 1969 118,615 28,306 
Cadet Bayou, Miss. 1973 87,921 77,730 
Cahaba River, Ala.' 1894 45,000 
Carrabelle Harbor, Fla. 1971 503,331 325,114 
East Pearl River, Miss. 1973 37,128 306,0704 
Fly Creek, Ala. 1973 29,000 60,793 
Grand Lagoon, Panama City, Fla. 1972 128,0015 
Holmes Creek, Fla. 1931 8,562 36,800 
LaGrange Bayou, Fla. 1972 289,496 70,9586 
Leaf and Chickasawhay River, Miss.' 2 1919 23,090 42,676 
Noxubee River, Miss.2 1902 47,528 14,472 
Ocholockonee (Ochlockney) River, Ga. and Fla.' 2 1900 5,000 
Old Town Creek, Miss.2 1887 3,000 
Oostanaula and Coosawatee River, Ga.' 2 1907 32,656 
Panacea Harbor, Miss. 1973 129,3837 13,240 
Pascagoula River, Miss.3 1956 15,000 173,522 
Pearl River, Miss., Edinburg to Jackson' 1911 31,872 36,991 
Port St. Joe, Fla. 1973 1,980,8628 1,379,736 
St. Marks River, Fla. 1965 1,710,809 32,564 
Tallapoosa River, Ala.' 2 1893 43,972 
Upper Chipola River, Fla., from Mariana to 
its mouth' 2 1941 36,781 63,193 
Wolf and Jordan Rivers, Miss. 1973 29,195 303,972 
1. Recommended for deauthorization in H. Doc. 192, 
94th Congress, 1st Session. 
2. Abandonment recommended in H. Doc. 467, 69th 
Cong. 
3. Existing project provides for maintenance only, 
$15,000 spent on previous project. 
4. Includes $28,200 for previous projects. 
5. Includes $80,000 contributed funds. 
6. Includes $2,161 for previous project. 
7. Includes $7,000 for contributed funds. 
8. Includes $20,000 for contributed funds. 
10-40

MOBILE, ALA., DISTRICT 
TABLE 10-G OTHER AUTHORIZED BEACH EROSION CONTROL PROJECT 
(See Section 25 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Harrison County, Miss., shore protection' 1953 $1,133,000 
1. Completed. 
TABLE 10-H OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 33 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Alabama River at Montgomery, Ala.' 1965 $36,658 
Armuchee Creek, Ga.2 1966 115,547 
Baldwin and Hannon Sloughs, 
Montgomery, Ala.' 1973 55,995 
Beaver Creek, Montezuma, Ga.2 1958 149,815 
Black Creek, Gadsden, Ala.2 1953 125,389 
Clanton, Ala.2 1964 274,024 
Collinsville, Ala.2 1940 71,119 
Lake Douglas, Decatur County, Ga.2 1970 164,998 
Little Cove Creek, Glencoe, Ala.2 1965 113,849 
Pearl River, Miss., and La., Jackson, Miss.2 3 1937 
Prattville, Autauga Creek, Ala. 2 1946 649,280 
Rome, Coosa River, Ga.2 1955 384,550 
Sowashee Creek, Meridian, Miss.2 1956 142,637 
Town Creek, Americus, Ga. 2 1965 340,409 
Trussville, Ala.2 1965 141,334 
West Point, Chattahoochee River, Ga.2 1955 599,637 
Yellow Jacket Creek, Hogansville, GA. 2 1966 330,734 
1. Engineering, design, supervision, and administration 
(no construction work has been done. 
2. Completed. 
3. Work authorized before 1941 
done on project proposed in 1941. 
completed. No work 
10-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 34 of Text) 
(a) Study Fiscal Year Costs 
Bayou LaBatre, Ala. $ 3,506 
Cave Springs, Ga. 4,919 
Gordon Creek, Hattiesburg, Miss. 33,634 
Town Branch, Summerville, Ga. 40,382 
(b) Advance Preparation $55,966 
(c) Emergency Operations $95,774 
TABLE 10-J ALABAMA-COOSA RIVERS, ALA. AND GA. 
DEVELOPMENT PROPOSED UNDER EXISTING PROJECT 
(See Sections 35 and 36 of Text) 
Claiborne Millers Ferry Jones Bluff Carters Allatoona 
Proposed Structures Lock and Dam Lock and Dam Lock and Dam Lake Dam3 Dam 
Miles above mouth of river 81.11 42.21 245.41 26.82 47.84 
Nearest town Claiborne, Ala. Camden, Ala. Benton, Ala. Carters, Ga. Cartersville, Ga. 
Distance (miles) 7 10 3 2 4 
Greatest lock length available for 
full width (feet 600 600 600 - - 
Width of lock chamber (feet) 84 84 84 - - 
Maximum lift (feet) 30 48 47 - - 
Elevation of normal pool surface Varies seasonally 
(mean sea level) 35 80 125 1072 from 823-840 
Depth over sills at low water 13 Upper 15 Upper 15 - - 
(feet) Lower 13 Lower 12 
Character of foundation Rock Rock Rock Rock Rock 
Kind of spillway Gated and Gated Gated Gated Gated 
Fixed Crest 
Height of dam (feet) 95.5 99.5 94 451 190 
Type of construction Concrete Concrete Concrete Rock-fill Concrete 
Earth Core 
Total reservoir capacity 
(acre-feet) 96,360 331,800 234,200 472,800 670,050 
Power development (kw) - 75,000 68,000 500,000 74,000 
Percent complete 100 99 85 98 100 
Estimated cost: 
Construction and design $26,989,400 $58,264,600 $69,217,000 $103,749,000 $23,816,000 
Land and damages (including 
relocations) $ 1,162,100 $ 4,585,200 $ 5,583,000 $ 2,251,000 $ 7,611,200 
Total estimated cost (1975) $28,151,500 $62,849,800 $74,800,000 $106,000,000 $31,427,3005 
1. Above mouth of Alabama River (river miles). 
2. Above mouth of Coosawattee River (river miles). 
3. Reregulation dam (Carters) 25.3 (river miles). 
4. Above mouth of Etowah River (river miles). 
5. Excluding $3,470,800 for additional recreation facilities. 
10-42

MOBILE, ALA., DISTRICT 
TABLE 10-K APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, ALA., GA., AND FLA., 
LOCKS AND DAMS AND MULTIPLE-PURPOSE DEVELOPMENT INCLUDED IN EXISTING PROJECT 
(See Section 39 of Text) 
Jim George W. Walter R. Lower 
Woodruff Andrews George West Point Lake Auchumpkee Lazer Spewrell 
Lock Lock Lock Lake Sidney Creek Creek Bluff 
and Dam and Dam and Dam Lanier Lake Lake Lake 
Miles above mouth 107.61 46.52 75.02 201.42 348.32 233.43 255.83 263.83 
Nearest town Chattahoochee, Columbia, Ala. Ft. Gaines, West Point, Buford, Ga. Roberta, Ga. Thomaston, Manchester, 
Fla. Ga. Ga. Ga. Ga. 
Distance (miles) 1 1 2 2.8 5 7 8 8 
Greatest lock length 450 450 450 - - - - 
available for full width 
(feet) 
Width of chamber (feet) 82 82 82 - - - - 
Maximum lift (feet) 33 25 88 - - - - - 
Elevation of normal pool 77 102 190 (Summer) 635 (Summer 1070 417 543 700 
surface (msl) 185 (Winter) 625 (Winter) 
Depth over sills at low 14 13 13 - - - - 
water (feet) 
Character of foundation Limestone Limestone Limestone Rock Rock Rock Rock Rock 
Kind of spillway Fixed-gated Fixed-gated Gated Gated Fixed Gated Gated Gated 
Height of dam (feet) 67 62 114 95 192 130 142 180 
Type of construction Concrete Concrete Concrete Concrete Earth Concrete Concrete Concrete 
and Earth and Earth and Earth and Earth and Earth and Earth 
Total reservoir capacity 367,300 18,180 934,400 604,500 2,554,000 548,000 342,000 486,200 
(acre-feet) 
Power development 30,000 - 130,000 73,3754 86,000 81,000 87,000 150,000 
(kilowatts) 
Percent complete 100 100 100 89 100 - - - 
Year opened to navigation 1954 1962 1963 - - - - 
Estimated cost: 
Construction and design $43,634,000 $12,559,900 $63,860,400 $ 99,135,500 $24,644,000 $ 71,200,000 $ 82,980,000 $109,400,000 
Lands and damages $ 2,866,600 $ 396,700 $21,399,600 $ 18,864,500 $20,156,000 $ 33,800,000 $ 22,020,000 $ 49,600,000 
(including relocations) 
Total (1975 est.) $46,500,000 $12,956,600 $85,260,0005 $118,000,000 $44,800,000 $105,000,000 $105,000,000 $159,000,000 
1. Above mouth of Apalachicola River (river miles). 4. Initial installation (ultimate will be 108,375 kw). 
2. Above mouth of Chattahoochee River (river miles). 5. Includes $333,198 cost of land for wildlife refuge. 
3. Above mouth of Flint River (river miles).

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 10-L COMPLETED FLOOD PLAIN INFORMATION, FLOOD HAZARD 
INFORMATION AND FLOOD INSURANCE REPORTS FOR FY 19751 
(See Section 40 of Text) 
Study 
Flood Plain Information Reports 
Pintlalla Creek, Vicinity of 
Montgomery, Ala. 
Willeo Creek, Vicinity of 
Roswell, Ga. 
Rottenwood Creek, Vicinity 
of Marietta, Cobb County, Ga. 
Perdido & Tributary Bays, 
Alabama & Florida 
Sandy & Blue Creeks, 
Vicinity of Ponce De Leon, Fla. 
Strong River-Sellers & 
Terrapin Creeks, Mendenhall, Miss. 
Robbins Branch, Magnolia Creek, 
Meridian, Miss. 
Hanging Moss Creek & White 
Oak Creek, Jackson, Miss. 
Special Flood Hazard Information Repo 
Big Escambia Creek, 
Flomaton, Ala. 
Poley Bridge, Clanton, Ala. 
Philips Inlet to St. Andrew 
Bay, Fla. 
Little River, Cherokee 
County, Ga. 
Holly Creek, Town Branch, 
Chatsworth, Murray County, Ga. 
Upper Chattahoochee, Vicinity 
of Helen, White County, Ga. 
Little Cedar Creek, Cave 
Spring, Ga. 
Flood Insurance Report 
Forest Park, Ga. 
Date Federal 
Requesting Agency Completed Cost 
Central Alabama Regional 
Planning & Development Comm. 
Atlanta Regional Commission 
Atlanta Regional Commission 
Escambia County, Santa Rosa County 
or Regional Planning Commission 
Florida Department of Natural 
Resources 
City of Mendenhall 
City of Meridian 
City of Jackson 
rts 
South Alabama Regional Planning 
Commission or City of Flomaton 
Chilton County Chamber of 
Commerce 
Panama City & Bay County 
Georgia Department of Natural 
Resources 
City of Chatsworth 
Georgia Department of Natural 
Resources 
City of Cave Spring 
Jun 75 
Jun 75 
Jul 74 
Jun 75 
May 75 
Sep 74 
Sep 74 
Jun 75 
Jun 75 
Nov 74 
Nov 74 
Apr 75 
Oct 74 
Jun 75 
Apr 75 
$27,000 
22,500 
23,000 
20,000 
21,000 
25,100 
25,000 
25,300 
8,500 
4,500 
5,000 
15,000 
6,500 
22,000 
2,500 
(Prepared for Federal Insurance Aug 74 38,500 
Administration, HUD) 
1. For listing of reports completed by Mobile District for FY 1965 thru FY 1974 see FY 1974 Annual Report, page 10- 50. 
10-44

NEW ORLEANS, LA., DISTRICT* 
District comprises a portion of Louisiana, 
including drainage area of Red River south of 
Fulton, Ark., in Arkansas and Texas, embraced 
in drainage basins tributary to Mississippi River 
and Gulf of Mexico, except Mississippi River 
above mile 322 above Head of Passes, drainage 
area of Ouachita-Black River Basin, and small 
eastern and western portions of Louisiana" 
tributary to Pearl River and Sabine River and 
Lake. 
It includes sections of the Gulf Intracoastal 
Waterway from Lake Borgne Light 29 at the 
mouth of Pearl River to Sabine River, and the 
Passes of the Mississippi River. It exercises 
jurisdiction over flood control work on 
Mississippi River from mile 322 AHP to Gulf 
of Mexico; on Red River including its south 
bank levees and tributaries from Index, 
Ark., to its junction with Old River and 
Atchafalaya River; Atchafalaya River; and in 
Atchafalaya Basin; and maintenance of project 
navigation channel of Mississippi River 
below mile 322 AHP, under supervision of 
President, Mississippi River Commission, 
and Division Engineer, Lower Mississippi 
Valley Division. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control 
Program, La. ..................... 
2. Atchafalaya River and Bayous 
Chene, Boeuf, and Black, La. ..... 
3. Atchafalaya River, Morgan City 
to Gulf of Mexico, La. ........... 
4. Barataria Bay Waterway, La. .... 
5. Bayou Lafourche and Lafourche- 
Jump Waterway, La. ............ 
6. Bayou Teche and Vermilion 
River, La. ....................... 
7. Bayou Teche, La. ................ 
8. Calcasieu River and Pass, La. .... 
9. Calcasieu River at Coon 
Island, La. .................... 
10. Calcasieu River at Devil's 
Elbow, La. ...................... 
11. Freshwater Bayou, La .......... 
12. Gulf Intracoastal Waterway 
between Apalachee Bay, Fla., 
and Mexican Border (New 
Orleans Dist.) ................. 
13. Houma Navigation Canal, La. .... 
14. Mermentau River, Bayou 
Nezpique, and Bayou Des Cannes, 
La. ....................... 
15. Mermentau River, La. ........... 
16. Mississippi River, Baton Rouge 
to Gulf of Mexico, La. ........... 
Page 
11-2 
11-3 
11-4 
11-4 
11-4 
11-6 
11-6 
11-7 
11-8 
11-9 
11-9 
11-10 
11-13 
11-14 
11-15 
11-15 
Navigation (cont.) 
17. Mississippi River-Gulf 
Outlet, La. .................... 
18. Mississippi River-Gulf Outlet, 
Michoud Canal, La. .............. 
19. Mississippi River Outlets, 
Venice, La. ...................... 
20. Overton-Red River Waterw 
ay, La ......................... 
21. Petit Anse, Tigre, and 
Carlin Bayous, La. ............... 
22. Red River below Fulton, Ark. .... 
23. Red River emergency bank 
protection ..................... 
24. Red River Waterway- 
Mississippi River to Shreveport, 
La. ........................ 
25. Red River Waterway-Shreveport, 
La., to Daingerfield, Tex. ........ 
26. Removing water-hyacinth, La. ... 
27. Waterway from Empire, La., 
to Gulf of Mexico .............. 
28. Waterway from Intracoastal 
Waterway to Bayou Dulac, La. 
(Bayous Grand Caillou and 
LeCarpe, La.) .................. 
29. Other authorized navigation 
projects ........................ 
30. Navigation work under 
special authorization ............. 
* All cost and financial statements and authorizing legislation for projects are listed at the end of this chapter. All other tables 
are referenced in text and also appear at the end of this chapter. 
11-1 
Page 
11-17 
11-18 
11-18 
11-19 
11-20 
11-20 
11-21 
11-21 
11-23 
11-24 
11-25 
11-25 
11-26 
11-26

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Flood Control 
31. Bayou Bodcau and tributaries, 
Ark. and La. ................. 
32. Bayou Bodcau Reservoir, La. ..... 
33. Bayou Pierre, La. ............... 
34. Brush Bayou, La.' ................ 
35. Caddo Lake, La. ................. 
36. Choctaw Bayou and tributaries, 
La. ...................... 
37. Cooper Lake and Channels, Tex... 
38. Ferrells Bridge Dam-Lake 
O'the Pines, Tex. ................ 
39. Garland City, Ark. .............. 
40. Harvey Canal, Bayou 
Barataria Levee, La. ............ 
41. Lake Pontchartrain and vicinity, 
La. (hurricane protection) ........ 
42. Larose to Golden Meadow, La. 
(hurricane protection) ........... 
43. Mississippi River Delta at and 
below New Orleans, La. (New 
Orleans to Venice, La., hurricane 
protection) ................. 
Page Flood Control (cont.) Page 
44. Morgan City and vicinity, La. 
11-26 (hurricane protection) ........... 11-33 
11-27 45. Red River below Denison Dam 
11-27 (New Orleans Dist.) ............ 11-34 
11-27 46. Red River below Denison Dam, 
11-28 levees and bank stabilization 
(New Orleans Dist.) ............ 11-34 
11-28 47. Wallace Lake, La ............... 11-35 
11-28 48. Wright Patman Dam and 
Lake, Tex ..................... 11-35 
11-29 49. Inspection of completed flood 
11-30 control projects ................ 11-35 
50. Other authorized flood control 
11-30 projects ....................... 11-36 
51. Flood control work under 
11-30 special authorization ........... 11-36 
11-32 General Investigations 
52. Surveys ....................... 
53. Collection and study of 
basic data ....................... 
11-32 54. Research and development ....... 
11-36 
11-36 
11-36 
Navigation 
1. AQUATIC PLANT CONTROL 
PROGRAM 
Location. Lakes and streams in State of 
Louisiana. 
Existing project. Provides for control and 
progressive eradication of water-hyacinth, 
alligatorweed, and other obnoxious aquatic plant 
growth from navigable waters, tributary 
streams, connecting channels, and other allied 
waters in North Carolina, South Carolina, 
Georgia, Florida, Alabama, Mississippi, 
Louisiana, and Texas, in combined interests of 
navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health, and 
related purposes, including continued research 
for development of most effective and economic 
control measures. 
The modification of 1965 provides for 
comprehensive program for control and 
progressive eradication of water-hyacinth, 
alligatorweed, Eurasian water milfoil, and other 
obnoxious plant growths from navigable 
waterways, tributary streams, connecting 
channels, and other allied waters of the United 
States, in combined interest of navigation, flood 
control, drainage, agriculture, fish and wildlife 
conservation, public health, and related 
purposes, including continued research for 
development of most effective and economic 
control measures. Research and planning costs 
undertaken pursuant to 1965 Act shall be borne 
fully by the United States and shall not be 
included in costs to be shared by local interests. 
Local cooperation. Local interests must hold 
and save the United States free from claims and 
participate in project to extent of 30 percent of 
cost of operations. State of Louisiana, 
Department of Public Works, and Louisiana Wild 
Life and Fisheries Commission furnished a joint 
assurance of local cooperation, which was 
approved Apr. 29 and accepted May 4, 1959. 
Under provisions of continuing contract, local 
agencies will perform work in kind, 
approximating 30 percent of cost of program. 
Operations and results during fiscal year. 
Combined efforts by Corps of Engineers crews 
and crews of the State of Louisiana, Wild Life and 
Fisheries Commission, continued against aquatic 
vegetation problems throughout the State. 
Water-hyacinth control requires maintenance 
work in all areas, and water-hyacinth persists as 
the most serious aquatic pest. Control 
maintenance by the Corps of cleared areas 
continued in the Mermentau River, Bayou 
Lacassine, Bayou Queue de Tortue, in the Bayou 
Teche basin south of U. S. Highway 190, 
including the lakes west of the Atchafalaya 
Floodway, in the feeder areas of the Port Allen- 
Morgan City Route of the Gulf Intracoastal 
Waterway, and in the feeder areas to the Gulf 
Intracoastal Waterway in Coastal Louisiana. 
Louisiana Wild Life and Fisheries Commission 
crews continued maintenance efforts in the major 
lakes and streams of north Louisiana, in the 
Atchafalaya Floodway, in the Louisiana portion 
11-2

NEW ORLEANS, LA., DISTRICT 
of the Toledo Bend Reservoir, and the Pearl River 
Basin within Louisiana. During the fiscal year, 
21,368 acres of water-hyacinths and 
alligatorweed were destroyed. State of Louisiana 
crews destroyed 11,365 acres of water-hyacinths 
and alligatorweed by chemical treatment. Corps 
of Engineers crews destroyed 10,003 acres of 
water-hyacinths and alligatorweed by chemical 
and mechanical methods. The alligatorweed flea 
beetle (agasicles) continued to overwinter in large 
numbers in the southern part of the State and is 
reducing the total area of alligatorweed. The 
stem boring moth (vogtia) has also been found on 
alligatorweed and its population is increasing. 
The submersed aquatic weed, Hydrilla 
verticillata, has been located in two additional 
areas in south Louisiana and its growth and 
spread is being carefully monitored. 
Condition at end of fiscal year. Operations 
under 1958 River and Harbor Act, initiated May 
1959, are complete. Operations under 1965 Act 
were initiated in Fiscal Year 1968. Waterways 
are being cleared, then maintained -as required. 
2. ATCHAFALAYA RIVER AND 
BAYOUS CHENE, BOEUF, AND 
BLACK, LA. 
Location. The improvement is located in the 
parishes of Assumption, Terrebonne, and St. 
Mary, La., in the vicinity of Morgan City, along 
Bayous Chene, Boeuf, and Black, and the Lower 
Atchafalaya River to the Gulf of Mexico. (See 
Mississippi River Commission alluvial maps, 
Morgan City, Belle Isle, and Point au Fer 
quadrangles, Coast and Geodetic Survey Chart 
1276, and navigation maps of Intracoastal 
Waterway and Atchafalaya River system.) 
Existing project. Provides for enlargement and 
extension of project, Atchafalaya River, Morgan 
City to the Gulf of Mexico, La., to obtain 
navigation channels 20 feet deep over a bottom 
width of 400 feet from vicinity of U. S. Highway 
90 crossing over Bayou Boeuf to the Gulf of 
Mexico via Bayou Boeuf, Gulf Intracoastal 
Waterway, Bayou Chene, Avoca Island Cutoff, 
the lower Atchafalaya River, Atchafalaya Bay to 
the Gulf of Mexico, and from near U. S. Highway 
90 to Bayou Chene via Bayou Black and the Gulf 
Intracoastal Waterway. The 400-foot channel 
extends into the Gulf of Mexico to the 20-foot 
contour, and the width in Bayou Boeuf would be 
reduced to 300 feet where necessary because of 
industrial development on both sides of the bayou. 
Estimated cost for new work (July 1975) is 
$20,400,000 Federal and $2,400,000 non-Federal. 
In addition, Coast Guard is to provide navigation 
aids at an estimated cost of $42,000. 
Local cooperation. The local agency must 
provide without cost to the United States, all 
lands, easements, and rights-of-way for 
construction and subsequent maintenance of the 
project and for aids to navigation upon the 
request of the Chief of Engineers, including 
suitable areas required in the general public 
interest for initial and subsequent disposal of 
spoil, and also necessary retaining dikes, 
bulkheads, and embankments therefor or the cost 
of such retaining works; accomplish and 
maintain all modifications to roads, bridges, 
pipelines, cables, and any other utilities and 
improvements necessary for the construction and 
subsequent maintenance of the project; and hold 
and save the United States free from damages 
due to construction and maintenance of the 
project. In addition, the provisions of Public Law 
91-646 and Public Law 91-611 are applicable. 
Assuring Agency: Morgan City Harbor and 
Terminal District. 
The Water Resources Act of 1974 modified the 
project to provide (a) 25 percent local 
contribution of the cost of spoil disposal retaining 
dikes, bulkheads, and embankments and (b) 
waiver of requirement (a) if political subdivisions 
are participating in and are in compliance with 
approved plan in area of dredging activity for 
construction, modification, expansion, or 
rehabilitation of waste treatment facilities, and if 
applicable water quality standards are not being 
violated. 
Basic assurance was approved on behalf of 
United States on Dec. 10, 1973, and amended 
assurance containing the applicable provisions of 
Public Law 91-646 and Public Law 91-611 was 
approved on behalf of United States on Feb. 25, 
1974. 
Terminal facilities. Two large and three small 
public wharves at Morgan City are open for use 
by all without charge. In addition, there are 
numerous privately owned facilities on both 
banks of the lower Atchafalaya River in Morgan 
City and Berwick, La., and along Bayou Boeuf 
and the Gulf Intracoastal Waterway. Fabrication 
and repair facilities are located on Bayous Boeuf 
and Black. Adequate acreage is available for 
expansion of existing terminals and construction 
of new terminals along Bayous Chene, Boeuf, and 
Black, and the Gulf Intracoastal Waterway. 
Public and private terminals in the project area 
are adequately connected with rail, water, and 
highway transportation facilities. No additional 
public wharves are required. 
Operations and results during fiscal year. New 
work by hired labor consisted of real estate 
activities and engineering work associated with 
the Federal Water Pollution Control Act of 1972. 
Contract work for initial dredging in the 
Atchafalaya Bay and Bar Channel, La., 
continued from last fiscal year and was 
11-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
completed Dec. 5, 1974, with 12,647,602 cubic 
yards of material removed this fiscal year. 
Condition at end of fiscal year. Construction 
was initiated on the Atchafalaya Bay and gulf 
reach in April 1974. The project is 16 percent 
complete. 
3. ATCHAFALAYA RIVER, MORGAN 
CITY TO GULF OF MEXICO, LA. 
Location. Atchafalaya River is the outlet of Red 
River and diverted flow from Mississippi River. 
It begins about 4.5 miles west of Old River 
navigation lock on northern boundary of Pointe 
Coupee Parish, and flows generally south about 
135 miles and empties into Atchafalaya Bay, an 
inlet of the gulf. Section under improvement is 
from 20-foot contour in Atchafalaya Bay, 4 miles 
beyond mouth of Atchafalaya River, to 20-foot 
contour in Gulf of Mexico. (See Coast and 
Geodetic Survey Chart 1276, Mississippi River 
Commission alluvial valley maps, Morgan City, 
Belle Isle, and Point au Fer quadrangles, and 
navigation maps of Gulf Intracoastal Waterway 
and Atchafalaya River system.) 
Existing project. A 20- by 200-foot channel from 
20-foot contour in Atchafalaya Bay to 20-foot 
contour in Gulf of Mexico. Project depth refers to 
mean low water. Normal range of tide is 10 
inches; extreme range, 14 inches; hurricane 
range, 10 feet. The existing project, prior to the 
modification of August 1968, was completed at a 
cost of $501,963. 
Local cooperation. Fully complied with, except 
for modification of project in connection 
with Atchafalaya River and Bayous Chene, 
Boeuf, and Black, La., which is reported 
separately. 
Terminal facilities. At Morgan City there are 
several small private wharves and two large and 
three small public ones open for use of all without 
charge. There are no warehouses needed, as 
business section is on riverfront and all freight is 
transferred directly from boats to stores. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Hired labor work consisted of condition and 
operations studies, reconnaissance surveys, and 
channel patrol. 
A contract for dredging in the Atchafalaya 
Bay and Bar channel was initiated May 28, 1975. 
The contract dredge Port Arthur removed 
881,262 cubic yards of shoal material as of 
Jun. 30, 1975. 
Condition at end of fiscal year. Construction 
was initiated in Fiscal Year 1911 and completed 
in Fiscal Year 1914. 
4. BARATARIA BAY WATERWAY, LA. 
Location. In Jefferson Parish, La., and extends 
about 37 miles southerly from junction of Gulf 
Intracoastal Waterway and Bayou Barataria 
near Lafitte Post Office. From its origin it 
extends southerly through Bayou Barataria, 
Bayou Dupont, a land cut (known as Dupre Cut) 
through marsh area, Bayou Cutler, Bayou St. 
Denis, and Barataria Bay to east end of Bayou 
Rigaud. At its southerly terminus it also connects 
with Barataria Pass and through that pass with 
the Gulf of Mexico. (See Coast and Geodetic 
Survey Charts 1050, 1116, and 1237, Geological 
Survey maps Barataria, Bay Dogris, Wilkinson 
Bay, and Barataria Pass.) 
Previous project. For details see page 562 of 
Annual Report for 1963. 
Existing project. A channel about 37 miles long 
with a 12-foot depth and 125-foot width from its 
beginning at Gulf Intracoastal Waterway to 
Grand Isle, La., following route of previous 
project to mile 15.5 in Bayou St. Denis; thence by 
a relocated channel along western shore of 
Barataria Bay and through Barataria Pass to 12- 
foot-depth contour in the gulf, with an extension 
of project to include westerly 4.3 miles of Bayou 
Rigaud. Normal range of tide is 30 inches at 
mouth and 6 inches at head. Elevation of water 
surface near mouth, due to hurricanes, has been 
over 6 feet. Existing project was completed at a 
cost of $1,499,648. 
Local cooperation. Fully complied with. 
Terminal facilities. Six privately owned 
wharves at Lafitte; three privately owned 
facilities at Grand Isle; and wharfage in Bayou 
Rigaud at Grand Isle constructed by shrimping 
industry are available to all boats without charge. 
About 7 miles below Lafitte there is a large oil 
terminal for transferring production of Lafitte 
field to barges. Adjacent to Bayou Barataria and 
along Bayou Rigaud adequate sites are available 
for future use. 
Operations and results during fiscal year. 
Condition and operation studies, surveys and 
channel patrol were conducted by hired labor. 
Maintenance dredging of the channel between 
mile 12.0 to mile 28.2 (not continuous) continued 
from last fiscal year and was completed Jul. 19, 
1974, with 176,809 cubic yards of material 
removed this fiscal year by contract. 
Condition at end of fiscal year. Construction 
was initiated in May 1960 and completed in 
November 1963. 
5. BAYOU LAFOURCHE AND 
LAFOURCHE-JUMP WATERWAY, LA. 
Location. Prior to 1902, Bayou Lafourche was 
11-4

NEW ORLEANS, LA., DISTRICT 
an outlet of Mississippi River, its head being at 
Donaldsonville, La., 80 miles above New Orleans. 
It flows southerly 107 miles to Gulf of Mexico. 
iSee Coast and Geodetic Survey Charts 1116 and 
1274; Mississippi River Commission alluvial 
valley maps; Donaldsonville, White Castle, 
Napoleonville, Thibodaux, and Lac des 
Allemands quadrangles; and Geological Survey 
maps, Houma, Cutoff, Lake Felicity, Mink 
Bayou, Leeville, and Belle Pass quadrangles.) 
Previous projects. For details see page 564 of 
1963 Annual Report. 
Existing project. Provides for permanent 
closure of head of bayou without a lock, a channel 
6 feet deep and 60 feet wide from Canal 
Boulevard in Thibodaux to Lockport, and from 
Larose to Gulf of Mexico with ajettied entrance at 
Belle Pass, and the closure of Pass Fourchon. 
These improvements are about 50.5 miles long, 
and the modification of Jul. 14, 1960, provides for 
an additional 66 miles of improvement as follows: 
a 12- by 125-foot channel, extending from Gulf 
Intracoastal Waterway at mile 37.2 west of 
Harvey Lock to enter Bayou Lafourche below 
highway bridge at Leeville at about mile 12; a 12- 
by 125-foot channel in Bayou Lafourche from 
point of junction with proposed 12- by 125-foot 
channel to 12-foot-depth contour in gulf; 
modification and extension of existing jetties 
from 6- by 12-foot contour, if found advisable to 
reduce maintenance dredging in the gulf; and a 
channel 9 by 100 feet in Bayou Lafourche from 
Leeville to vicinity of lower limits of Golden 
Meadow; and a 12- by 125-foot channel from 
Bayou Lafourche at Leeville from point where 
auxiliary channel connects with Bayou 
Lafourche through Southwestern Louisiana 
Canal to and through Bayou Rigaud to connect 
with enlargement of Bayou Rigaud 
recommended under project "Barataria Bay 
Waterway, La." Normal range of tide is 10 inches 
at mouth and 3 inches at head; from severe rains, 
3 to 10 feet at head; from hurricanes, up to 10 feet 
at mouth. Estimated cost for new work (July 
1975) is $11,400,000 Federal and $4,850,000 non- 
Federal. In addition, Coast Guard is to provide 
navigation aids at an estimated cost of $34,000. 
Excavation of a channel 6 feet deep and 60 feet 
wide from Thibodaux to Gulf Intracoastal 
Waterway at Lockport is considered inactive and 
excluded from foregoing cost estimate. 
Estimated cost of this portion (July 1974) is 
$733,000. 
Local cooperation. Original assurances 
received and accepted on all items of work in the 
project. Provisions of Public Law 91-611 are not 
applicable; however, provisions of Public Law 91- 
646 are applicable. Supplemental assurances 
covering Public Law 91-646 have been executed 
by the Jefferson Parish Council and Lafourche 
Parish Police Jury; however, the Louisiana 
Department of Public Works has not executed 
supplemental assurances. 
Golden Meadow to gulf: Local agency has 
acquired all rights-of-way and furnished rightsof-
entry. 
Leeville to Grand Isle: No action is apparent on 
this stretch by either the Lafourche Parish Police 
Jury, the Jefferson Parish Council, the local 
assurers, or the State of Louisiana, Department of 
Public Works. Rights-of-way are not available 
due to multiplicity and other complications of 
ownership. 
Terminal facilities. There are numerous 
private warehouses, wharves, and stiff-leg 
derricks for handling cane along bayou. At 
Lockport, Barker Barge Line has a barge wharf 
with covered shed, and Southern Pacific Railroad 
maintains a large wharf with covered shed. At 
Golden Meadow each of the seafood canneries has 
docking facilities suitable for its needs. Four oil 
companies have docks at Leeville for transferring 
production of Leeville oil fields to barges. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
work by hired labor consisted of general 
engineering and planning. 
Condition at end of fiscal year. Construction of 
existing project was initiated in Fiscal Year 1939 
and is 10 percent complete. Dredging between 
Larose, La., and Gulf of Mexico was completed in 
1939, and that segment between Lockport and 
Napoleonville, La., is in an inactive status due to 
lack of right-of-way and spoil area. Jetties at 
mouth of Belle Pass were completed in 1939, and 
later damaged by storm action, which required 
placement of additional stone adjacent to both 
sides of steel sheet pile jetties in 1940, and repair 
and extension of jetties in 1941. During Fiscal 
Year 1948, stone jetties were repaired and 
extended inland about 700 feet from shoreline; 
and steel sheet pile section was strengthened for 
about 250 feet gulfward of stone jetties, by 
placement of stone on both gulf and bayou sides. 
On May 31, 1949, an automatic tide gage for 
recording hurricane and storm tides was 
installed. Modification of Jul. 14, 1960, was 
initiated in February 1963 and is 10 percent 
complete, with 12- by 125-foot channel completed 
in September 1963 from Leeville to 12-foot 
contour in Gulf of Mexico, the 9- by 100-foot 
channel completed in August 1966 from Golden 
Meadow to Leeville, and the 9- by 100-foot 
channel from Golden Meadow to Leeville 
completed in August 1966. 
Total cost of existing project to Jun. 30, 1975, 
was $2,130,142 of which $1,315,831 was for new 
work and $814,311 for maintenance. In addition, 
11-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
$75,563 has been expended for rehabilitation 
(Code 820). 
The Greater Lafourche Port Commission 
requested, and was granted, a permit to dredge a 
new channel 20 by 300 feet wide west of the 
existing channel from mile 0.76 in Bayou 
Lafourche to the 20-foot depth in the gulf, and to 
close the existing jettied channel after completion 
of the new channel. This work was completed in 
March 1968 and the Port Commission must 
maintain the channel at no less than 12 by 125 
feet. 
6. BAYOU TECHE AND VERMILION 
RIVER, LA. 
Location. Bayou Teche has its source in Bayou 
Courtableau, in St. Landry Parish, and flows 
southeasterly 125 miles to its confluence with 
lower Atchafalaya River, about 10.5 miles above 
Morgan City, La. Vermilion River, also called 
Bayou Vermilion, is formed by junction of Bayous 
Fusilier and Bourbeau, west of Arnaudville, La., 
and flows southwesterly 72 miles to western end 
of Vermilion Bay. Bayou Teche is connected with 
Vermilion River by Bayou Fusilier at 
Arnaudville; and by Ruth Canal, an artificial, 
privately owned, nonnavigable waterway, 
constructed for diversion of water from Bayou 
Teche to Vermilion River for rice irrigation. 
(Coast and Geodetic Survey Charts 1116 and 
1277; Mississippi River Commission alluvial 
valley maps; and Geological Survey maps.) 
Existing project. A navigable channel 51 miles 
long and 8 by 80 feet from 8-foot-depth contour in 
Vermilion Bay to Gulf Intracoastal Waterway, 
thence 9 by 100 feet to head of navigation (mile 52) 
at Lafayette, La. (fixed bridge at Louisiana State 
Highway 729, formerly State Highway 1092), 
with additional enlargement below Abbeville 
necessary to provide adequate capacity for 
floodflows; improvement of Vermilion River 
from Lafayette, La., mile 52, to its junction with 
lower end of Ruth Canal, mile 57.2, by both 
widening and deepening to provide a channel 6 by 
60 feet, mean gulf level, in order to provide 
adequate capacity for flood discharges from 
upper Vermilion River Basin, and also serve 
irrigation interests by conducting flow of Ruth 
Canal to lower Vermilion River during rice 
season. Clearing and enlargement of channel 
from Ruth Canal to Bayou Fusilier by both 
widening and deepening to provide a cross section 
about 50 percent larger than that of existing 
channel. This improvement is required in 
interest of flood control in upper Vermilion 
Basin. Enlargement of channel of Bayou Teche 
from its head in Bayou Courtableau to a point 
about 21 miles downstream thereof, by widening 
and deepening to provide a channel of 35-foot 
bottom width at minus 2 and minus 3, mean gulf 
level. Increasing height of Keystone Dam by 3 
feet (later revised to 1.5 feet) by installation of a 
fixed crest spillway. (See individual report for 
Bayou Teche, La.) In connection with these 
improvements, the project also provides for 
replacement of an existing pontoon bridge at 
Woodlawn over Vermilion River with a verticallift 
structure and lengthening and strengthening 
approaches to five existing movable bridges over 
Vermilion River below Lafayette, La., located at 
Louisiana State Highway 43 at Perry, La.; 
Southern Pacific Railroad at Abbeville, La.; 
Louisiana State Highway 25 at Abbeville, La.; 
Milton, La.; and U. S. Highway 90 (Pinhook 
Bridge) just below Lafayette, La. Similar work on 
existing fixed spans over nonnavigable streams is 
provided for on 11 bridges over Bayou Vermilion 
above Lafayette, La., and three over upper Bayou 
Teche. New work completed in 1957 cost 
$2,891,922. Project was reclassified "Operation 
and Maintenance, General" under category, 
"Navigation (Locks, Dams, Reservoirs, and 
Canals)" by authority of Chief of Engineers, 
Apr. 23, 1956. 
Local cooperation. Fully complied with for new 
work. 
Terminal facilities. Privately owned, publicly 
operated terminals are located on Bayou Teche at 
Franklin, Jeanerette, New Iberia, and 
Arnaudville. Other privately owned boat 
landings are located at frequent intervals 
throughout the bayou and public landing is 
permitted without charge. Facilities on the 
Vermilion River include a public wharf and two 
privately owned barge landing piers at Abbeville 
equipped for barge truck transfers of general 
commodities, seven landings for the transfer of 
petroleum products, and several private landings 
all along the waterway suitable for small craft. 
The Vermilion Sugar Company maintains a 
barge slip at its mill. Present facilities are 
adequate for existing commerce and there is 
ample space available for construction of more 
wharfage. 
Operations and results during fiscal year. 
Hired labor forces continued condition and 
operation studies, surveys, and snagging and 
clearing above Lafayette, La. 
Condition at end of fiscal year. Construction 
commenced March 1944 and was completed 
March 1957, when Keystone Dam was raised to 
provide an increase of 1.5 feet in pool elevation, in 
order to increase flow through Ruth Canal into 
Vermilion River. Work was accomplished under 
navigation improvement "Bayou Teche, La." 
7. BAYOU TECHE, LA. 
Location. Has its source in Bayou Courtableau, 
11-6

NEW ORLEANS, LA., DISTRICT 
in St. Landry Parish, flows southeasterly for 125 
miles, and joins lower Atchafalaya River about 
10.5 miles above Morgan City, La. (See Coast and 
Geodetic Survey Chart 1116, Mississippi River 
Commission alluvial valley maps, Palmetto, 
Opelousas, Carencro, Arnaudville, St. 
Martinville, Loreauville, Derouen, Jeanerette, 
Foster, and Belle Isle quadrangles.) 
Previous projects. For details see page 569, 1963 
Annual Report. 
Existing project. Provides for a channel 8 feet 
deep and 80 feet wide on the bottom from mouth 
of stream to New Iberia, La., mile 54.5, thence 6 
feet deep and 60 feet wide on the bottom to 
Keystone Lock, 18 miles, and thence 6 feet deep 
and 50 feet wide on the bottom from Keystone 
Lock to Arnaudville, La., 34 miles, to be secured 
by dredging, removing snags and overhanging 
trees, and construction of a lock and dam and 
regulating works. (See Table 11-C on Keystone 
Lock.) 
Raising pool level by 1.5 feet above Keystone 
Dam by installation of a fixed crest spillway on 
dam is provided for in flood control project for 
Bayou Teche and Vermilion River, La. Under 
project, flood control, Mississippi River and 
tributaries, East and West Calumet floodgates, 
with a width of 45 feet and sill elevation of minus 
9.02 feet, mean low gulf level, were constructed in 
Bayou Teche at east and west approaches to Wax 
Lake Outlet from February 1949 to September 
1950, and a lock was constructed in lower 
Atchafalaya River in vicinity of Berwick, La., 
from November 1948 to September 1951. (See 
Table 11-C on Berwick Lock.) 
Normal range of tide is 10 inches at mouth; 4 
inches just below Keystone Lock; extreme, 12 
inches at mouth; 6 inches just below Keystone 
Lock; and zero above lock; due to freshets, 4 to 5 
feet at mouth; 12 to 15 feet just below Keystone 
Lock, and 2 to 7 feet above Keystone Lock. 
Estimated cost for new work (1954) is 
$1,080,000, exclusive of amount expended on 
previous projects and estimated cost (1954), 
$371,400 for widening and deepening channel 
between miles 50.06 and 72, Keystone Lock and 
Dam, which is inactive. 
Local cooperation. Fully complied with. 
Terminal facilities. Small, privately owned 
wharves are available at all towns along bayou; 
public landing is permitted without charge. 
There are privately owned terminals for 
transferring crude oil to barges near towns of 
Charenton, Jeanerette, Oliver, and St. 
Martinville. Facilities considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Hired labor continued operation and 
maintenance of Keystone Lock and facilities and 
condition and operation studies. 
Condition at end of fiscal year. Construction 
was initiated in 1891 and completed July 1928, 
except widening channel to bottom width of 80 
feet from mile 50.06 to New Iberia, and to bottom 
width of 60 feet from New Iberia to Keystone 
Lock, which is inactive. For further details see 
Annual Report for 1966. 
Total cost under existing project to Jun. 30, 
1975, was $3,223,469 of which $708,626 was for 
new work, $1,413,506 for maintenance, and 
$1,107,880 for operating care, including $91,389, 
permanent indefinite appropriation. 
8. CALCASIEU RIVER AND PASS, LA. 
Location. Calcasieu River has its source in 
southwestern Louisiana, and flows southerly to 
the gulf. About 25 miles from the gulf it 
debouches into Calcasieu Lake, which is about 18 
miles long. Connection between lake and gulf, 
about 7 miles long, is known as Calcasieu Pass. 
(See Coast and Geodetic Survey Charts 591 and 
592; Geological Survey maps, Edna, Thompson 
Bluff, Hecker, Moss Bluff, Lake Charles, West 
Lake, Moss Lake, Hackberry, Sweet Lake, 
Brown's Lake, Holly Beach, Grand Bayou, and 
Cameron quadrangles; and Corps navigation 
maps of Intracoastal Waterway and Atchafalaya 
River system.) 
Previous project. For details see 1936 and 1938 
Annual Reports, pages 719 and 819, respectively. 
Existing project. Provides for a channel 40 by 
400 feet(35.9 miles long) from Lake Charles to sea 
end of jetties in Gulf of Mexico; an approach 
channel 42 by 800 feet from sea end of jetties to 42 
feet deep in the gulf; extension of 35- by 250-foot 
channel from its present upstream limit at mile 
34 to vicinity of U. S. Highway 90 Bridge (mile 
36.2); a 750- by 1,000-foot turning basin at upper 
end with a 35-foot depth; improvement of river 
from Lake Charles to Phillips Bluff (52.6 miles) 
by removing logs, snags, overhanging trees, and 
by dredging; maintenance of existing 12- by 200- 
foot channel in old channel of Calcasieu River at 
Cameron, La., which connects with project at 
mile 2.25; and reconstruction and extension of 
existing jetties initially to seaward end of east 
jetty, and further extension to 15-foot-depth 
contour if found advisable to reduce maintenance 
dredging costs. Improvement is 113.6 miles long. 
Normal range of tide is 10 inches at mouth, 
diminishing to zero at Phillips Bluff; extremes 
range from 14 inches to zero. 
Cost of existing project, completed in 1968, 
except for extension of jetties, if necessary, to 15- 
foot-depth contour, was $27,311,396. Estimated 
cost of this extension (July 1967) is $10,300,000. 
11-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Estimated cost for new work (July 1975) is 
$19,518,000 Federal, and $1,409,000 non- 
Federal. In addition, Coast Guard is to provide 
navigation aids at an estimated costof $404,700. 
Local cooperation. Local interests furnished all 
rights-of-way and spoil-disposal areas for 
completed features. For construction and future 
maintenance of modification authorized by 1960 
River and Harbor Act, local interests must 
furnish lands, rights-of-ways, and spoil-disposal 
areas; alter pipelines, cables, wharves, oil wells, 
and any other facilities and hold and save the 
United States free from damages. Assurances 
were accepted and right-of-entry was furnished 
for the modification. The local agency is presently 
finalizing transfer to the United States of the few 
remaining tracts with acceptable title evidence. 
Assuring Agency: Lake Charles Harbor and 
Terminal District. 
Terminal facilities. Facilities at Port of Lake 
Charles are owned by Lake Charles Harbor and 
Terminal District and operated by a board of 
commissioners. In addition to municipally owned 
terminals, there are several privately owned and 
operated wharf structures on existing ship 
channel. (For further details, see Port Series No. 
19, vol. 1, "Port St. Joe, Fla., Pensacola, Fla., 
Baton Rouge, La., Panama City, Fla., 
Pascagoula, Miss., Lake Charles, La., Gulfport, 
Miss.," revised 1957, and Folio of Navigation 
Maps Intracoastal Waterway, New Orleans to 
Port Arthur, 1968, 13th edition, published by 
Mississippi River Commission.) 
Operations and results during fiscal year. 
Maintenance by hired labor: Work consisted of 
condition and operation studies, operation and 
maintenance of the salt-water barrier, and 
maintenance dredging. The U. S. dredge 
Langfitt removed 17,651,717 cubic yards of 
material from mile 0 to station 540+00 in 
the Bar Channel from Aug. 26, 1974, through 
Jan. 16, 1975. 
Maintenance by contract: A contract for 
maintenance dredging, mile 15.5 to 36.0, 
including turning basins, mile 29.5 to 36.0 and 
Clooney Island Loop was awarded Jun. 24, 1975, 
but work was not initiated. 
Condition at end of fiscal year. Construction 
under the existing project was initiated in Fiscal 
Year 1939 and completed October 1968, except 
extension of the jetties to 15-foot-depth contour, 
which has been deferred until found advisable to 
accomplish same. See Table 11-D at end of 
chapter for work accomplished under each 
modification. A turning basin or ship anchorage 
for vessels using waterway was constructed from 
April to June 1952, between St. Johns Island and 
vicinity of Cameron, La., about 1.1 miles. 
Calcasieu Pass jetties, initiated under previous 
project and completed in May 1942, extended to 
10-foot-depth contour. East jetty, about 8,620 feet 
long, was built to about 6 feet above mean low gulf 
and extends seaward from existing gulf shoreline 
for 6,820 feet. West jetty, 8,050 feet long, was built 
to about 4 feet above mean low gulf and extends 
seaward from existing gulf shoreline for 6,795 
feet. 
Total cost of existing project to Jun. 30, 1975, 
was $53,989,611, of which $27,311,396 was for 
new work and $26,678,215, for maintenance. In 
addition, $107,837 has been expended for minor 
rehabilitation (Code 820). 
9. CALCASIEU RIVER AT COON 
ISLAND, LA. 
Location. In Calcasieu Parish, southwestern 
Louisiana, at about mile 32.2 on the Calcasieu 
River, 1.5 miles downstream from the Port of 
Lake Charles. 
Existing project. Provides for enlargement of 
the existing locally constructed Coon Island ship 
channel and turning basin to provide a 40- by 200- 
foot channel and a 40- by 750- by 1,000-foot 
turning basin to allow for more efficient use of the 
existing channel. Estimated cost of new work is 
$950,000 Federal, including $56,400 
preauthorization study cost, and $66,000 
non-Federal. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-ofway 
required for construction and subsequent 
maintenance of the project, and for aids to 
navigation, including suitable areas for initial 
and subsequent disposal of spoil, and also 
necessary retaining dikes, bulkheads, and 
embankments therefor or the costs of such 
retaining works; accomplish without cost to the 
United States such alterations as required in 
sewer, water supply, drainage, and other utility 
facilities, as well as their maintenance; hold and 
save the United States free from damages 
resulting from the construction and maintenance 
of the project, and, in particular, erosion beyond 
the rights-of-way furnished; assume 
responsibility for all costs in excess of the $1 
million Federal cost limitation; prohibit 
construction of any wharf, pier, or other structure 
within 150 feet of the edge of the authorized 
channel and turning basin limits; establish 
regulations prohibiting the discharge of 
pollutants in the channel by users thereof; be in 
accordance with the applicable laws for pollution 
prevention and control; comply with the 
provisions of Public Laws 91-611 and 91-646. 
Agreement of assurance containing all 
requirements of local cooperation, including the 
applicable requirements of Public Laws 91-611 
and 91-646, was approved on behalf of the United 
11-8

NEW ORLEANS, LA., DISTRICT 
States on Oct. 24, 1973. 
Assuring Agency: Lake Charles Uarbor and 
Terminal District. 
Terminal facilities. Facilities at Port of Lake 
Charles are owned by Lake Charles Harbor and 
Terminal District and operated by a board of 
commissioners. Privately owned industries along 
the Calcasieu River have developed terminal and 
transfer facilities to meet their specific needs. 
Operations and results during fiscal year. New 
work by hired labor consisted of general 
engineering. 
Condition at end of fiscal year. Construction 
was initiated Jul. 16, 1973, and was completed 
Apr. 5, 1974. 
10. CALCASIEU RIVER AT DEVIL'S 
ELBOW, LA. 
Location. In southwest Louisiana on the east 
side of the Calcasieu River and Pass, La., project 
and about 12 miles south of Lake Charles. 
Existing project. Provides for a 40- by 400-foot 
channel extending a distance of about 2.8 miles, 
from the existing ship channel in Calcasieu River 
at mile 22.6 eastward through Devil's Elbow and 
in the land cut into the industrial park, and a 
turning basin at the head of the channel, 40 feet 
deep, 1,000 feet wide, and 1,000 feet long. 
Estimated cost for new work (July 1974) is 
$5,360,000 Federal and $490,000 non-Federal. In 
addition, Coast Guard is to provide navigation 
aids at an estimated cost of $68,000. 
Local cooperation. Assuring Agency: Lake 
Charles Harbor and Terminal District. All 
assurances for the project have been received, 
and were accepted Dec. 6, 1973, wherein they 
agreed to provide without cost to the United 
States, all lands, easements, and rights-of-way for 
construction and subsequent maintenance of the 
project and for aids to navigation upon request of 
the Chief of Engineers, including suitable areas 
determined by the Chief of Engineers to be 
required in the general public interest for initial 
subsequent disposal of spoil, and also necessary 
retaining dikes, bulkheads, and embankments 
therefor, or the costs of such retaining works; 
accomplish without cost to the United States such 
utility and other relocations or alterations as 
necessary for project purposes; hold and save the 
United States free from damages due to 
construction and maintenance of the project; 
provide and maintain at local expense adequate 
public terminal and transfer facilities open to all 
on equal terms in accordance with plans 
approved by the Chief of Engineers; provide and 
maintain depths in berthing areas commensurate 
with the depth provided in the project channel; 
prohibit erection of any structure within 125 feet 
of the project channel authorized at the time of 
construction; establish regulations prohibiting 
discharge of pollutants into the waters of the 
channel and harbor by users thereof, which 
regulations shall be in accordance with 
applicable laws or regulations of Federal, State, 
and local authorities responsible for pollution 
prevention and control and regulate and promote 
the wise use, growth, and development of the area 
surrounding the channel for waterborne 
commerce and comply with the provisions of 
Public Law 91-646 and Sec. 221 of Public Law 
91-611. 
Terminal facilities. There are public terminal 
facilities at the Port of Lake Charles, mile 34.0 of 
the Calcasieu River ship channel, including 
storage sheds, rail and highway service, and 
transfer equipment. Privately owned industrial 
facilities along the channel have been developed, 
including a major tanker terminal (about mile 29) 
and a dock to serve the aluminum complex at the 
industrial park. Additional public facilities in the 
industrial park will be provided when needed. 
Operations and results during fiscal year. 
Preparation of the GDM was completed and 
submitted for approval in November 1974. The 
GDM was approved, subject to comments on 
Mar. 13, 1975. Comments are being resolved. 
Condition at end offiscal year. Construction has 
not been initiated. 
11. FRESHWATER BAYOU, LA. 
Location. In Vermilion Parish, La., between 
Atchafalaya and Calcasieu Rivers, from Gulf 
Intracoastal Waterway, mile 161.2 west of 
Harvey Lock, to 12-foot contour in Gulf of Mexico 
near Freshwater Bayou. Waterway is routed 22.6 
miles along Schooner Bayou Cutoff, Schooner 
Bayou, Six Mile Canal, Belle Isle Canal, and 
Freshwater Bayou. 
Existing project. Provides for dredging a new 
12- by 125-foot channel from Gulf Intracoastal 
Waterway, mile 161.2 west of Harvey Lock, to 12- 
foot contour in Gulf of Mexico near Freshwater 
Bayou, construction of an 84- by 600-foot lock 
with a depth of 16 feet over sill near Gulf of 
Mexico; and construction of jetties from shoreline 
to 6-foot-depth contour in Gulf of Mexico, if 
maintenance dredging of channel without jetties 
proves to be more expensive than construction 
and maintenance of jetties. Until such 
determination has been made, offshore channel 
should be dredged and maintained to provide a 
12- by 250-foot channel. In event jetties are 
provided, offshore section should then be 
maintained to 12- by 125-foot project in jettied 
reach, and 250 feet beyond. Cost of existing 
project, completed in 1968, except for 
11-9

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
construction of jetties at a later date, if necessary, 
was $7,116,224 Federal and a $16,060 cash 
contribution. Estimated cost of construction of 
jetties (July 1971) is $3,118,100. Estimated total 
Federal cost is $10,400,000 (1971) and the total 
non-Federal cost for' the existing project is 
$171,000. In addition, the Coast Guard is to 
provide navigational aids at an estimated cost of 
$19,100. 
Local cooperation. Fully complied with. 
Terminal facilities. Extensive public and 
private terminal and transfer facilities do not 
exist in area, and none would be required for 
improved channel. Private terminals exist at site 
of oil and gas operations in area and sufficient 
private and public wharf facilities are along Gulf 
Intracoastal Waterway and its connecting 
waterways. Sites are available along proposed 
improvement for construction of any additional 
private and public terminals that might be 
required for utilization of channel. 
Operations and results during fiscal year. 
Maintenance by hired labor consisted of 
operation and ordinary repairs to lock, condition 
and operation studies, reconnaissance surveys, 
and channel patrol. Maintenance by contract: A 
contract for dredging, miles 12.7 to -3.60, 
commenced Aug. 6, 1974, and was completed 
Oct. 11, 1974, with a total of 830,221 cubic yards 
of shoal material removed. 
Condition at end of fiscal year. Construction 
was initiated April 1963 and completed August 
1968, except for construction of jetties at a later 
date, if required to reduce the cost of maintenance 
dredging. 
12. GULF INTRACOASTAL WATERWAY 
BETWEEN APALACHEE BAY, FLA., 
AND MEXICAN BORDER (NEW 
ORLEANS DIST.) 
Location. Section of Gulf Intracoastal 
Waterway within New Orleans District extends 
from Lake Borgne Light 29 near mouth of 
Rigolets, to Sabine River, La. and Tex. Section 
from Lake Borgne Light 29 to Mississippi River 
follows Rigolets and Lake Pontchartrain to lake 
end of State-owned Inner Harbor Navigation 
Canal, thence via this canal to Mississippi River, a 
distance of 40.5 miles. Public Law 675, 77th 
Cong., modified project to provide for a land cut 
through marsh from Rigolets to a point on Inner 
Harbor Navigation Canal about 2.25 miles from 
Mississippi River, eliminating passage through 
Lake Pontchartrain and five drawbridges, a 
distance of 30.8 miles to Mississippi River by this 
route. From Inner Harbor Navigation Canal to 
entrance to Harvey Lock, route follows 
Mississippi River for 5.5 miles. Section from 
Mississippi River to Atchafalaya River, La., 
leaves Mississippi River through Harvey Lock 
about 3.3 miles above Canal Street and follows 
Harvey Canal No. 1 and Bayou Barataria to 
Bayou Villars, a land cut south of Lake Salvador 
to Harvey Canal No. 2, Harvey Canal No. 2 to 
Larose, La., and a land cut to Houma, La., thence 
over a land cut south of Bayous Black and 
Cocodrie, thence through Bayou Cocodrie and a 
land cut to Bayou Black; thence through Bayous 
Black, Chene, and Boeuf to Atchafalaya River, 
about 0.5 mile south of Morgan City, La., a total of 
95.5 miles. Alternative connection with 
Mississippi River near Algiers, La., about 10.3 
miles below Harvey Lock, consisting of a lock and 
land cut about 9 miles long intersecting 
Intracoastal Waterway at about mile 6 is 
complete. An alternative route from Mississippi 
River follows Bayou Plaquemine passing Indian 
Village, La., and continuing on through lower 
Grand River to and through a lock at Bayou 
Sorrel in East Atchafalaya Basin protection 
levee, thence through levee borrow pit to Berwick 
Bay; and thence through Berwick Bay to Morgan 
City, La., a total of 56 miles. This alternative route 
was enlarged from vicinity of Morgan City to 
Indian Village, La., and extended from Indian 
Village, La., through Bayou Grosse Tete and a 
new land cut to and through a new terminal lock 
and entrance channel to Mississippi River near 
Port Allen, La., a total of 65 miles. Section from 
Atchafalaya River to Vermilion River, La., 
begins at western end of Mississippi-Atchafalaya 
section and follows Atchafalaya River about 2.5 
miles, portions of Little Wax Bayou, Possum 
Bayou, cutoffs, a land cut passing through North 
Bend Plantation to Bayou Bartholomew, Bayou 
Bartholomew to Little Bay, a land cut skirting 
north edge of Cote Blanche Island and west edge 
of Weeks Island to Vermilion River, about 24 
miles below Abbeville, La., a total of about 63.6 
miles. Franklin Canal, St. Mary Parish, La., 
extends southwesterly from Franklin, La., on 
Bayou Teche, for 5.5 miles to Bayou Portage, a 
section of "The Inland Waterway from Franklin 
to the Mermentau River, La.," and through bayou 
for 0.75 mile to Gulf Intracoastal Waterway, 121 
miles west of Harvey Lock. Section from 
Vermilion River to Mermentau River, La., begins 
at western end of Atchafalaya-Vermilion section 
and follows Vermilion River 1.3 miles, a part of 
Schooner Bayou Cutoff canal, and a land cut 
running generally northwesterly to Mermentau 
River at a point about 0.5 mile above its entrance 
into Grand Lake and about 16 miles below town of 
Lake Arthur, La., a total of about 42.7 miles. 
Vermilion Lock was constructed about 1.75 miles 
west of Vermilion River to prevent ingress of salt 
water from Vermilion Bay. Section from 
Mermentau River to Calcasieu River, La., begins 
at western end of Vermilion-Mermentau section 
11-10

NEW ORLEANS, LA., DISTRICT 
and follows Mermentau River upstream for about 
1.5 miles, a land cut running west-southwesterly 
to Lake Misere, passing north of lake and Bayou 
Misere, westerly to Sweet Lake, south and west of 
Sweet Lake, northwesterly to Bayou Tete Bois, 
through Bayou Tete Bois, Black Bayou, and 
cutoffs to a point on Calcasieu River about 16.6 
miles below city of Lake Charles, La., a total of 
about 37.1 miles. Calcasieu Lock was constructed 
near intersection of Calcasieu River and 
Intracoastal Waterway, mile 238 west of Harvey 
Lock, Calcasieu Parish, about 16.6 miles below 
Lake Charles, La. Section from Calcasieu River to 
Sabine River, La. and Tex., begins at western end 
of Mermentau-Calcasieu section, and follows 
Calcasieu River upstream about 1.6 miles, a land 
cut running southwesterly 2.8 miles, thence west 
22 miles to Sabine River at a point about 3 miles 
below Orange, Tex., a total of about 27.1 miles. 
(See Coast and Geodetic Survey Charts 878-884, 
inclusive; Mississippi River Commission alluvial 
valley map and Rigolets, Chef Menteur, St. 
Bernard, New Orleans, Barataria, Baton Rouge, 
Grosse Tete, Chicot Lake, Foster, Napoleonville, 
Morgan City, Belle Isle, Bayou Sale, Jeanerette, 
and Derouen quadrangles; Geological Survey 
maps, Cutoff, Houma, Gibson, Abbeville, Forked 
Island, Grand Lake East, Grand Lake West, Lake 
Charles, Sulphur, and Orange quadrangles; and 
folio of navigation maps of Intracoastal 
Waterway, gulf section, Port Arthur, Tex., to 
New Orleans, La.) 
Previous projects. For details see page 544 of 
1963 Annual Report. 
Existing project. Provides for a waterway, 
within the district, from Lake Borgne to Sabine 
River by the following improvements: a channel 
16 feet deep and 150 feet wide, from Mississippi 
River to Atchafalaya River, except in vicinity of 
Houma, miles 50.5 to 63.5, which is to be 
maintained at 12 by 125 feet; a channel 16 by 150 
feet through bypass route around Houma, La., 
miles 50.5 to 63.5, and through alternative 
connection in Mississippi River below Algiers, 
La., about 9 miles long, a channel 16 by 200 feet 
from Atchafalaya River to Sabine River; a 
channel 12 by 150 feet in section between Lake 
Borgne Light 29 and New Orleans (via land cut 
through marsh and Inner Harbor Navigation 
Canal), 33.1 miles long; an alternative route 9 feet 
deep and 100 feet wide between Lake Borgne 
Light 29 and New Orleans (via Rigolets, Lake 
Pontchartrain, and Inner Harbor Navigation 
Canal), 40.5 miles long; a channel 12 feet deep and 
125 feet wide for Plaquemine-Morgan City 
alternative route from Mississippi-Atchafalaya 
section of waterway, in vicinity of Morgan City, 
through lower Atchafalaya River (Berwick Bay) 
and borrow pit of East Atchafalaya protection 
levee to and through Bayou Sorrel Lock which 
was constructed under existing project "Flood 
control, Mississippi River and tributaries," 
thence through Lower Grand River to Indian 
Village, and thence by way of Bayou Grosse Tete 
and a new land cut to and through a new terminal 
lock and entrance channel to Mississippi River 
near Port Allen, La., opposite lower limit of Port 
Baton Rouge; a channel 9 feet deep and 100 feet 
wide from Indian Village on Plaquemine- 
Morgan City alternative route through Bayou 
Plaquemine and Plaquemine Lock to Mississippi 
River at Plaquemine, La., improvement of 
Franklin Canal as a connecting channel from 
Gulf Intracoastal Waterway (mile 121) to 
Franklin, La., to afford a channel 8 feet deep and 
generally 60 feet wide with a width of 100 feet in 
its upper 300 feet; and a saltwater guard lock 
(Calcasieu Lock) in waterway at mile 238 west of 
Harvey Lock. Project also provides for: widening 
at bends; passing places; mooring basins; locks or 
guard locks; such railroad bridges over artificial 
cuts as are necessary; purchase of pipeline 
dredge; construction and operation of new 
drainage canals and pumping facilities to restore 
parish drainage systems where intercepted; 
construction of movable bridges at Missouri 
Pacific Railroad and State Highways 31 and 996 
(in lieu of State Highway Bridge 31, a tunnel was 
constructed, and additional cost over estimated 
cost of bridge was borne by local interest); fixedtrestle 
bridges for crossing proposed landside 
drainage canals; lift bridges at Louisiana 
Highway 168, Port Allen, La., at Texas & Pacific 
Railway, Port Allen, La., and at Texas & Pacific 
Railway, Morley, La.; and for annual payments to 
Board of Commissioners of Port of New Orleans 
for use of a portion of Inner Harbor Navigation 
Canal. Length of waterway within district is 
384.1 miles via northerly or Port Allen route, and 
299.4 miles via southerly or Harvey Canal route. 
Normal range of tide, 10 inches; extreme range, 
14 inches. A severe storm may cause a high tide of 
from 6 to 9 feet. 
Estimated cost for new work, exclusive of 
amounts expended on previous projects, is 
$123,233,827 Federal and $21,497,000 non- 
Federal, divided as follows: Algiers Lock and 
canal, completed June 1961, $15,895,924 Federal 
and $2,185,000 non-Federal; Plaquemine- 
Morgan City route, completed October 1963, 
$26,869,372 Federal and $2,250,000 non-Federal; 
and remainder of waterway (July 1975), 
$80,468,531 Federal and $17,062,000 non- 
Federal, including $53,000,000 Federal and 
$16,900,000 non-Federal for modification 
(authorized by Public Law 87-874), October 1962, 
and $12,000,000 Federal and $162,000 non- 
Federal for replacement of Vermilion Lock. In 
addition, the Coast Guard is to provide navigation 
aids at an estimated cost of $72,000. 
11-11

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Construction of bulkheads and jetties at Lake 
Borgne and Chef Menteur, La., is considered 
inactive and excluded from foregoing cost 
estimate. Estimated cost (1956) of this item is 
$440,000. Construction of a double-leaf bascule, 
four-lane highway bridge provided for under this 
project has become unnecessary because portion 
of project over which bridge was to be 
constructed was incorporated in project 
"Mississippi River-Gulf Outlet" which provides 
for a larger bridge. Bayou Sorrel and Bayou 
Boeuf Locks were constructed and are being 
maintained and operated with flood control, 
Mississippi River and tributaries funds. 
Therefore, construction, maintenance, and 
operation costs are not included in approved 
estimates referred to heretofore. 
(See Table 11-E for locks on Gulf Intracoastal 
Waterway in New Orleans District.) 
Local cooperation. Algiers Lock and Canal: 
All assurances required for construction were 
furnished. Local agency has failed to convey all 
fee and easement tracts with acceptable title 
evidence to the United States. However, 
authority has been received to accept the interests 
conveyed as best available from local agency with 
the understanding that the United States rely 
upon assurances of local cooperation should any 
claims against the United States occur as a result 
of failure of local agency to complete transfer of 
title. 
Plaquemine-Morgan City alternative route: All 
assurances required for construction were 
furnished. Title by United States has been 
acquired to all but 35 tracts, for which local 
agency failed to comply fully with curative 
requirements in title certificate. Authority was 
given to accept the tracts conveyed as best 
available from local interests and to rely upon 
assurances of local cooperation furnished by local 
agency should any claims against the United 
States occur as a result of failure of local agency to 
complete transfer of title. Louisiana Department 
of Public Works has furnished assurances for 
maintenance and improvement. 
Modification authorized by River and Harbor 
Act of 1962: Local interests must furnish lands, 
rights-of-way, and spoil-disposal areas for 
enlargement and future maintenance of project, 
make alterations to utilities; construct, maintain, 
and operate all bridges desired in connection with 
bypass channel around Houma, La., and hold the 
United States free from damages. Assurances 
were requested in April 1963; however, none of 
the 11 local agencies involved has furnished 
assurances requested. Main objection to 
participation is requirement that local interests 
be responsible for alteration of utilities. 
Replacement of Vermilion Lock: The Vermilion 
Parish Police Jury was requested to execute an 
Agreement of Local Cooperation on Oct. 26, 1972, 
agreeing to provide without cost to the United 
States all lands, easements, and rights-of-way 
required for construction and subsequent 
maintenance of the replacement lock and 
approach channels thereto, and hold and save the 
United States free from damages due to 
construction and maintenance of the project, 
including erosion of the channel beyond the 
rights-of-way furnished for the replacement lock 
and the approach channels thereto and comply 
with the provisions of Public Law 91-646 and Sec. 
221 of Public Law 91-611. The Police Jury, by 
letter dated Dec. 6, 1972, stated that they could 
not execute the assurances because of lack of 
sufficient funds with which to comply. However, 
another request was made on Oct. 20, 1974, which 
resulted in an informal notification that 
assurances would be furnished in a short time. No 
further problems are anticipated in this regard. 
The Louisiana Department of Public Works is 
still coordinating efforts to this end. 
Terminal facilities. Large terminal and 
transfer facilities, suitable for receiving and 
shipping commodities by barge, are available at 
principal cities in Louisiana; namely, New 
Orleans, Baton Rouge, Harvey, Morgan City, and 
Lake Charles. Facilities at New Orleans are on 
Inner Harbor Navigation Canal. Canal and 
facilities were leased from Board of 
Commissioners, Port of New Orleans, Apr. 1, 
1944, and are now operated by the United 
States, toll free, 24 hours per day. At Morgan 
City, on Atchafalaya River, there are two 
large and three small wharves open to all 
without charge. Otherwise, facilities are confined 
to privately owned piers, wharves, or 
oil docks. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. New 
work by hired labor: The Vermilion Lock GDM 
is scheduled for submission to LMVD in Fiscal 
Year 1976. The GDM is essentially 80 percent 
complete and work is being prosecuted on the 
basis of a new lock 110 feet wide by 1200 feet long 
with a sill at - 15.0, mean low gulf. 
Maintenance by hired labor: Real estate 
activities, condition and operation studies, 
condition surveys, and channel patrol continued. 
Locks, bridges, and waterways were operated 
and maintained. Repairs to fender systems were 
made at the following locks: Algiers, Calcasieu, 
Harvey, Industrial Canal, Port Allen, and 
Vermilion. Replacement of bulkhead at Connely 
Property, Houma, La., continued from last fiscal 
year and was completed Dec. 6, 1974. 
(a) Calcasieu Lock: Hired labor work conducted 
during the fiscal year consisted of placement of 
.11-12

NEW ORLEANS, LA., DISTRICT 
2,400 tons of riprap at the lock, reinforcement 
work on road embankment, and placement of 
3,600 tons of riprap at the north guidewall of the 
Salt Water Barrier Control Structure. 
(b) Industrial Canal Lock: Maintenance by 
hired labor consisted of installation of new fire 
protection system and cleaning of all gate pits. 
(c) Port Allen Lock: Hired labor forces 
conducted dredging work by removing silt from 
area behind floating guidewall. 
(d) Vermilion Lock: Hired labor forces 
installed two new metal sluice gatds. 
Maintenance by contract: Dredging under one 
contract included removing 999,818 cubic yards 
of shoal material intermittently from the 
following locations: Wax Lake Crossover; 
intersection Gulf Intracoastal Waterway (mile 
98.3) and Atchafalaya River; Twenty Grand 
Point area; and vicinity of Bayou Shaffer, 
during the period Jul. 19 through Oct. 9, 1974. 
The contract dredge Conical removed 7,940 cubic 
yards of material from above Bayou Sorrel Lock 
during the period Jul. 9 through Aug. 8, 1974. The 
dredge George D. Williams removed a total of 
141,644 cubic yards of material from below 
Bayou Sorrel Lock and the extension below 
Bayou Sorrel Lock during the period Jul. 13 
through Sep. 14, 1974. The dredges Manchac and 
Lafitte removed 374,645 cubic yards of material 
from the New Orleans Harbor lock forebays and 
tailbays from Jul. 1 through Nov. 8, 1975. 
Painting steel and replacing timbers at Harvey 
Lock continued from last fiscal year and was 
completed Aug. 28, 1974. Contract work for 
repairs to the Florida Avenue Bridge continued 
from last fiscal year and was completed Jul. 12, 
1974. Maintenance dredging in the Atchafalaya 
River-Vermilion River section, mile 145.9 to mile 
174.9 (not continuous) commenced Aug. 26, 1974, 
and was completed Jun. 15, 1975, with a total of 
1,811,022 cubic yards of shoal material removed. 
A contract for replacement of lock gate and other 
incidental work at Harvey Lock was initiated 
Nov. 18, 1974, and is 70 percent complete. 
Restoration of the Plaquemine Lock office 
building, commenced in May 1975, is 85 percent 
complete. A contract for dredging at New 
Orleans Harbor and various locations was 
commenced in June 1975 but no work was 
accomplished to date on dredging lock forebays. 
Condition at end of fiscal year. Construction 
was initiated July 1929 and project, as modified, 
is 47 percent complete. For information on 
completion of segments of waterway, see 1965 
Annual Report, pages 523 and 524. 
Work remaining to complete the project 
consists of enlarging waterway as provided by 
1962 River and Harbor Act, and replacement of 
Vermilion Lock. Construction of bulkheads at 
Lake Borgne and Chef Menteur are inactive 
features as this work has not been necessary. 
Total cost of existing project to Jun. 30, 1975, 
was $133,169,195, of which $58,728,406 was for 
new work, $35,140,899 for maintenance, and 
$39,299,890 for operation and care of locks and 
bridges. In addition, $340,159 for new work and 
$7,005 for maintenance has been expended from 
contributed funds. 
13. HOUMA NAVIGATION CANAL, LA. 
Location. Extends from Gulf Intracoastal 
Waterway at mile 59.5 west of Harvey Lock 
southerly about 16 miles, thence southeasterly 
10.5 miles to Terrebonne Bay, and 9.5 miles 
across bay to deep water in Cat Island Pass. At 
mile 11.3 above Cat Island Pass, Houma 
Navigation Canal crosses Bayou Petit Caillou, 
and 20 miles above Cat Island Pass it crosses 
Bayou Grand Caillou. No other major waterways 
are crossed by Houma Navigation Canal. (See 
Army Engineer and Geological Survey 
quadrangle maps; Coast and Geodetic Survey 
Charts 1050, 1116, and 1116A; and Coast and 
Geodetic Charts 1274 and 1275, and sheet 7 of 
"Navigation Maps of Intracoastal Waterway, 
Gulf Section, New Orleans, La., to Port Arthur, 
Tex.," published by Mississippi River 
Commission.) 
Existing project. Provides that United States 
assume maintenance and operation of Houma 
Navigation Canal, constructed by Parish of 
Terrebonne, to dimensions of 15 by 150 feet. 
Normal range of tide is 10 inches at mouth and 4 
inches at Houma; extreme range is 14 inches at 
mouth and 6 inches at Houma; wind and tide, 1 to 
3 feet at mouth; flood, 3 to 4 feet in upper section. 
Local cooperation. Local interests must furnish 
lands and rights-of-way for maintenance of canal 
and for establishment and maintenance of aids to 
navigation; furnish suitable spoil-disposal areas; 
provide alterations to facilities; hold and save the 
United States free from damages; and maintain 
and operate all bridges under construction or to 
be constructed across the canal. Local interests 
(under Chief of Engineers' interpretation of H. 
Doc. 583, 87th Cong., 2d sess.) will not be required 
to convey title of canal to United States. 
Assurances were furnished and accepted Apr. 12, 
1963. Local cooperating body has furnished 
temporary disposal areas as required for 
maintenance dredging of canal. 
Terminal facilities. Privately owned and 
operated facilities are adequate for existing 
commerce which is mainly seafood plants; oil 
companies and oil company supplies; sugar 
refining; and marine repair shops and towing. 
Southern Pacific Lines has dock facilities in 
11-13

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Houma, La. Ample space exists for expansion of 
existing facilities, or for the construction of new 
wharves and appurtenances. 
Operations and results during fiscal year. 
Hired labor forces continued routine surveys and 
condition and operation studies. A contract for 
maintenance dredging from mile 11.6 to Cat 
Island Pass, mile -3.9, continued from last fiscal 
year and was completed Aug. 28, 1974, with a 
total of 2,249,345 cubic yards of material removed 
this fiscal year. 
Condition at end of fiscal year. Maintenance by 
the United States commenced in November 1964. 
14. MERMENTAU RIVER, BAYOU 
NEZPIQUE, AND BAYOU DES 
CANNES, LA. 
Location.Mermentau River is formed by 
junction of Bayous des Cannes and Nezpique, 2.25 
miles above Mermentau, La., and flows 
southwesterly and empties into the Gulf of 
Mexico. Bayou Nezpique rises in Evangeline 
Parish, flows southerly, and empties into 
Mermentau River. Bayou des Cannes rises in 
Evangeline Parish, flows south-southwesterly, 
and empties into Mermentau River. (See Coast 
and Geodetic Survey Charts 1116 and 1278, and 
Geological Survey maps, Evangeline, Hathaway, 
Mermentau, Jennings, Lake Arthur, Gueydan, 
Thornwell, Latania Lake, Catfish Lake, Grand 
Cheniere, and Bayou Labauve quadrangles.) 
Previous project. For details see page 637, 1961 
Annual Report. 
Existing project. Provides a 12- by 125-foot 
channel in Mermentau River from Gulf 
Intracoastal Waterway to Lake Arthur; a 12- by 
200-foot channel through Lake Arthur and a 12- 
by 125-foot channel from upper end of Lake 
Arthur to junction of,the Mermentau River and 
Bayous Nezpique and des Cannes; replacement of 
existing Lake Arthur highway bridge over 
Mermentau River with new bridge constructed to 
current highway standards and with vertical and 
horizontal clearances of 50 and 200 feet, 
respectively; and enlargement and realinement 
of Bayous Nezpique and des Cannes, to provide a 
12- by 125-foot waterway from Interstate 
Highway 10 to the Mermentau River. Mean 
range of tide on Mermentau River near mouth is 
10 inches and near head about 3 inches, extreme 
ranges being 14 and 5 inches, respectively. 
Variation of water surface near mouth may be as 
much as 7 or 8 feet, due to hurricanes on gulf and 
near head from 8 to 12 feet, due to freshets. Under 
ordinary conditions, range of tide on Bayous 
Nezpique and des Cannes is about 3 inches at 
mouth and zero at head. Estimated cost of new 
work (1971) for replacement of bridge is 
$3,630,000 Federal and $740,000 non-Federal, 
cash contribution. Estimated cost of enlargement 
and realinement of channels is $2,640,000 
Federal and $930,000 non-Federal. In addition, 
the Coast Guard is to provide navigation aids at a 
cost of $51,000. 
Local cooperation. Local interests shall agree to 
provide all lands for construction and 
maintenance and dredged material areas or the 
costs of such areas; hold and save the United 
States free from damage due to the project; 
design and construct a replacement highway 
bridge at Lake Arthur, La.; bear 17.1 percent of 
the costs ($740,000 cash contribution), and 
operate and maintain the bridge; provide 
and maintain terminal facilities; and accomplish 
and maintain all modifications to utilities. 
All assuring agencies, with the exception 
of the Highway Department, must 
furnish Supplemental Assurances covering 
the provisions of Public Law 
91-646. All Supplemental Assurances have 
been furnished. 
The improvement of the Mermentau River or of 
Bayou Nezpique or Bayou des Cannes may be 
undertaken independently as the local 
cooperation therefor is provided, concurrent 
with, or subsequent to, replacement of the Lake 
Arthur highway bridge. 
Assuring Agencies: Cameron Parish, 
Vermilion Parish, Jefferson Davis Parish, 
Arcadia Parish, and Louisiana Department of 
Public Works. All assurances for the project have 
been received, with the Louisiana Department of 
Public Works executing assurances for 
Vermilion and Cameron Parishes. 
Terminal facilities. Several small, privately 
owned wharves at Grand Cheniere and a public 
terminal at town of Lake Arthur. Privately 
owned terminals for transferring crude oil to 
barges are: one on Lake Arthur near town of Lake 
Arthur; one on Mermentau River near town of 
Mermentau; two on Bayou Nezpique near 
Jennings; and four on Bayou des Cannes, one near 
Evangeline, one at Mermentau, and two near 
Jennings. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. New 
Work: Replacement of the Mermentau River 
bridge at Lake Arthur, Abbeville highway, 
Louisiana, route 14, continued from prior fiscal 
year and work is 98 percent complete. A contract 
for construction of four channel cutoffs, mile 
56.88 to mile 60.94 continued from last fiscal year 
and was completed Oct. 16, 1974. 
Condition at end of fiscal year. Construction 
of the bridge was initiated in May 1972 
and realinement of channels commenced April 
1974. 
11-14

NEW ORLEANS, LA., DISTRICT 
15. MERMENTAU RIVER, LA. 
Location. Work covered by this project is 35 to 
70 miles southeast of Lake Charles, La., along 
lower Mermentau River below Grand Lake, mile 
25, to Gulf of Mexico; Inland Waterway from 
Vermilion Bay to White Lake, White Lake to 
Grand Lake, and from Schooner Bayou to 
Intracoastal Waterway-Gulf section (Schooner 
Bayou Cutoff); North Prong of Schooner Bayou; 
and waterway from White Lake to Pecan Island, 
La., and artificial canal, extending from 5-footdepth 
contour in White Lake, almost due south for 
about 1.8 miles to Pecan Island. (See Coast and 
Geodetic Survey Charts 1277 and 1278, and 
Geological Survey maps.) 
Existing project. Flood control, navigation, 
irrigation, and salinity control in coastal marsh of 
lower Mermentau River Basin and channel 
enlargement of lower Mermentau River below 
Grand Lake, mile 25, to a minimum section of 
3,000 square feet below mean low gulf level for 
discharge of flood flows; construction of a sectorgated 
control structure at Catfish Point, mile 24 
above mouth of Mermentau River, for discharge 
of flood flows and control of tidal flows and 
saltwater intrusion in Mermentau River; channel 
enlargement and realinement of Inland 
Waterway from Vermilion Bay to White Lake, 
12.04 miles, and from White Lake to Grand Lake, 
6.14 miles, to a minimum section of 3,000 square 
feet below mean low gulf level or interflow 
between lakes and discharge of flood flows; 
construction of a sector-gated control structure in 
enlarged channel immediately north of 
abandoned Schooner Bayou Lock reservation for 
discharge of flood flows and control of tidal flows 
and saltwater intrusion; channel enlargement of 
North Prong of Schooner Bayou and Schooner 
Bayou Cutoff, 6.69 miles, to 6 by 60 feet, mean low 
gulf level, for navigation purposes; and 
maintenance of existing 5- by 40-foot, mean low 
gulf level, waterway from White Lake to Pecan 
Island, La., 1.8 miles long, for navigation. In 
addition, project provides for incorporation of 
that section of project, "Inland Waterway from 
Franklin, La., to Mermentau River," west of 
Vermilion Bay, a waterway that includes 
Schooner Bayou Lock. Project was reclassified as 
an "Operation and Maintenance, General" project 
under category, "Navigation (Locks, Dams, 
Reservoirs, and Canals)" by authority of Chief of 
Engineers, Apr. 23, 1956. Because of failure of 
both east and west gates, Schooner Bayou Lock 
was closed by a dike across east approach channel 
and traffic routed through new control structure. 
Under ordinary conditions mean range of tide on 
Mermentau River near mouth is 1.6 feet and near 
head about 3 inches. Variation of water surface 
near the mouth may be as much as 7 or 8 feet, due 
to hurricanes on the gulf, and near head from 8 to 
12 feet, due to freshets. Cost of new work, 
completed in 1956, was $4,631,910. 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned and 
operated facilities are adequate along the 
Mermentau River and Bayous Nezpique and des 
Cannes for the principal commodities 
transported, which is petroleum and its products. 
A public wharf is located at Lake Arthur, La., but 
due to insufficient use it has not been maintained 
and in its present condition is not usable. Sites for 
future expansion of these facilities are available 
and will be provided by non-Federal interests as 
required. 
Operations and results during fiscal year. 
Hired labor continued condition and operation 
studies, reconnaissance surveys, channel patrol, 
and operation and maintenance of Schooner 
Bayou and Catfish Point Control Structures. 
Dewatering structures 1 and 2 at Schooner 
Bayou Control Structures commenced Mar. 17, 
1975, and was completed May 20, 1975. 
Condition at end of fiscal year. Construction of 
project began April 1947 and was completed July 
1952. New work dredging was accomplished 
from April 1947 to June 1952. Catfish Point 
Control Structure was constructed from 
November 1948 to August 1951. Reservation 
comprises 9.7 acres. Schooner Bayou Lock and 
Control Structures: Schooner Bayou Lock and 
Dam were completed in 1913 and 1914, 
respectively, and the Lockmaster's house in 1917. 
Lock was closed to navigation May 7, 1951, and 
abandoned by authority of Chief of Engineers on 
Oct. 9, 1951. Permanent closure of lock channel 
and tie-in dikes was completed September 1951. 
Construction of control structures was 
accomplished from August 1949 to May 1951. 
Reservation comprises 6.9 acres. 
16. MISSISSIPPI RIVER, BATON ROUGE 
TO GULF OF MEXICO, LA. 
Location. This reach of the river flows 
southeasterly through southeastern portion of 
Louisiana. At Head of Passes, approximately 
233.1 miles below Louisiana Highway 
Commission bridge at Baton Rouge, river 
branches into three main passes: Southwest Pass, 
South Pass, and Pass a Loutre, two of which, 
Southwest Pass and South Pass, are improved 
under existing project. Head of Passes to mouths 
of Southwest and South Passes are 20.1 and 13.5 
miles, respectively. Mouth of Southwest Pass is 
141 miles west of Mobile, Ala., and 349 miles east 
of Galveston, Tex. Mouth of South Pass is 18.5 
miles northeast of mouth of Southwest Pass. (See 
Coast and Geodetic Survey Charts 1269, 1271, 
and 1272; Mississippi River Commission alluvial 
valley map, and Zachary, Baton Rouge, White 
11-15

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Castle, Donaldsonville, Thibodaux, Mount Airy, 
Bonnet Carre, Hahnville, New Orleans, St. 
Bernard, Barataria, Pointe a la Hache, Black 
Bay, Empire, Forts, West Delta, East Delta, and 
Southwest Pass quadrangles and 1974 folio of 
flood control and navigation maps, Mississippi 
River, Cairo, Ill., to Gulf of Mexico, La., published 
by Mississippi River Commission.) 
Previous projects. For details see page 552 of 
Annual Report for 1963. 
Existing project. Provides for channel 
dimensions as follows: Between a line one-tenth 
mile below Louisiana Highway Commission 
bridge at Baton Rouge 129.3 miles to upper port 
limits of New Orleans, 40 by 500 feet mean low 
water; within limits of port of New Orleans, 
where that authority has jurisdiction over both 
banks of river, a distance of 17.8 miles, 35 by 1,500 
feet, measured from a line generally 100 feet from 
face of left bank wharves, but not closer than 100 
feet to wharves on right bank; within 35- by 1,500- 
foot channel in port limits of New Orleans, 40 by 
500 feet; from lower limits of port of New Orleans 
86.7 miles to Head of Passes, 40 by 1,000 feet; 
Southwest Pass, 17.5 miles from Head of Passes to 
jetty channel, 40 by 800 feet; 4.1 miles in the 
Southwest Pass bar and jetty channel, 40 by 600 
feet; South Pass from Head of Passes to outer ends 
of jetties, 13.5 miles, 30 by 450 feet; and 1.2 miles 
in the South Pass bar channel, 30 by 600 feet. 
Plane of reference through New Orleans and below 
is mean low gulf. Plane of reference above 
New Orleans is low water reference plane. General 
plane of improvement of Southwest Pass provides 
for contracting pass to uniform cross section 
with about 1,420-foot surface width by means of 
jetties, spur dikes, and bulkheads; for channel 
maintenance by dredging from Cubits Gap, mile 
3.5 AHP through the gulf entrance channel, mile 
21.5 BHP; for construction of small revetted 
openings through narrow portions of banks of 
pass for purpose of strengthening and 
nourishment of banks; for closure of minor outlets 
not required for maintenance of banks; for 
construction of sills to prevent enlargement of the 
Venice Jump and Cubits Gap; for repairs to sill 
across Pass a Loutre and bank revetment at Head 
of Passes; for construction of dikes with a view to 
reducing width of river above Head of Passes; for 
construction of a submerged deflecting dike 
above Head of Passes; and for other minor work. 
East jetty is about 24,950 feet long and westjetty 
19,699 feet. Jetties are composed of a 
substructure of brush mattresses, orginally built 
to about elevation of mean low gulf, surmounted 
with a superstructure of concrete blocks and 
large riprap and for stone rubble mound of core 
and cover stone. Spur dikes are composed of 
cribwork of round piling filled with willows and 
stone, or with a curtain of round piles along 
upstream face. General plan of improvement of 
South Pass provides for construction and 
maintenance of jetties and spur dikes; 
maintenance of a sill across Pass a Loutre, and for 
seaward extension of east jetty at mouth of pass; 
removal of west dike and construction of spur 
dikes and bank revetment at Head of Passes; 
removal of false point at head of South Pass to 
bottom elevation of minus 45 feet and revetment 
of new bank line and construction and 
maintenance of east and west headland structure 
at Head of Passes. East jetty foundation is 12,070 
feet long; inner east jetty is 11,170 feet long; west 
jetty is 7,820 feet long; and inner west jetty is 
4,710 feet long. Jetties are composed of a 
substructure of brush mattresses surmounted by 
a superstructure of stone and/or concrete blocks 
and large riprap. Spur dikes are composed of 
cribwork of round piling filled with willows and 
stone. Plane of reference is mean low gulf. 
Variation of water surface is 16 inches at mouths 
and 10 inches at head of the passes, due to tides. 
Extreme range of tides at mouths of passes due to 
hurricanes is about 10 feet. At New Orleans 
extreme range of water surface is about 20 feet 
due to floods. At Baton Rouge extreme range is 
about 45 feet due to floods. 
Estimated cost of existing project(July 1975) is 
$76,900,000 Federal. In addition, Coast Guard is 
to provide navigation aids at an estimated cost of 
$28,900. 
Local cooperation. None required, except for 
modification of project in connection with 
Mississippi River-Gulf Outlet, which is reported 
separately. 
Terminal facilities. Piers, wharves, or docks 
serve the Port of New Orleans. Most wharves on 
east or left bank parallel riverbank forming 
nearly a continuous covered quay about 10 miles 
long. Public wharves controlled by Board of 
Commissioners, Port of New Orleans (the Dock 
Board), cover 62 percent of improved waterfront. 
These facilities include a shipside grain elevator, 
general cargo and cotton wharves, fruit l.andings, 
bunkering facilities, terminal warehouses, 
railroad terminals, marine railways, and 
drydocks. (For further details see Port Series No. 
20, "The Port of New Orleans, La." revised 1970.) 
A foreign trade zone is located in Port of New 
Orleans. City of Baton Rouge has a reinforced 
concrete dock for deep-sea vessels with 
mechanical-handling facility. Attached to 
downstream end of wharf is a floating wharf boat 
231 by 40.5 feet, of 2,000-ton capacity. Facilities 
are served by a transfer boat and municipal 
terminal having a capacity of 40 cars per day. 
Private terminals for handling oil, grain, bauxite 
ore, and other products are at points on both sides 
of river between New Orleans and Baton Rouge. 
Facilities are considered adequate for existing 
11-16

NEW ORLEANS, LA., DISTRICT 
commerce. (For further details, see "Port 
Facilities" included in "Flood Control and 
Navigation Maps of the Mississippi River, Cairo, 
Ill., to the Gulf of Mexico, La.," published 
annually by Mississippi River Commission, and 
Port Series No. 19, vol. 1, "Port St. Joe, Fla., 
Pensacola, Fla., Baton Rouge, La., Panama City, 
Fla., Pascagoula, Miss., Lake Charles, La., 
Gulfport, Miss.," revised 1957.) 
Operations and results duringfiscal year. New 
work: None. 
Maintenance: (a) Baton Rouge to New Orleans: 
U. S. dredges Jadwin and Langfitt removed 
13,081,385 cubic yards from Baton Rouge front 
and 10 crossings at a cost of $2,562,100. 
(b) New Orleans Harbor: Leased dredges under 
two contracts removed 2,206,830 cubic yards of 
shoal material from the harbor at a cost of 
$629,600. In addition, the Board of 
Commissioners of the Port of New Orleans, under 
reciprocal agreement, removed 624,066 cubic 
yards from the harbor area. Traffic lights to 
govern movement of vessels within the harbor 
were operated at a cost of $85,000. 
(c) Southwest Pass: The U. S. dredges Langfitt, 
McFarland, Gerig, and Goethals removed 
26,700,808 cubic yards of material at Head of 
Passes, vicinity 1.0 BHP to 15.5 BHP and 
between mile 18.8 BHP and the gulf at a cost of 
$6,648,300. Six dredges under three unit price 
contracts removed 12,435,783 cubic yards of 
material between miles 0.8 AHP and 18.8 BHP at 
a cost of $4,556,100. Repairs to east jetty, 
Southwest Pass, under two contracts were 
completed at a cost of $2,298,500. Contract work 
for repairs to survey platforms, from mile 0.6 
AHP to mile 19.8 BHP, commenced Apr. 7, 1975, 
and is 90 percent complete, with cost of $279,800 
for the fiscal year. 
(d) South and Southwest Passes: Hired labor 
repairs were made to parallel stone dikes, outlets, 
and miscellaneous pile dike structures at a cost of 
$341,500. 
(e) Venice suboffice and Langfitt wharf: 
Repairs made to wharf and operation of Venice 
suboffice cost $114,400. 
(f) Other items of expense were: Real estate 
land acquisition and expense, $36,200; condition 
surveys, passes, $456,800; hydrographic surveys, 
Mississippi River, $97,000; reconnaissance 
surveys, $70,400, supervision and 
administration, $948,700; engineering and 
design, $131,400; and engineering observations 
and studies, $311,400, including $109,000 
expended for Southwest Pass model study. 
Condition at end of fiscal year. The existing 
project is 45 percent complete. Deepening 
Southwest Pass to 40 feet mean low gulf, as 
authorized by the modification of Mar. 2, 1945, 
was completed in September 1963. Deepening the 
channel to 40 feet mean low water from Baton 
Rouge to New Orleans and to 40 feet mean low 
gulf in New Orleans Harbor, as authorized by the 
modifications of Oct. 23, 1962, was completed in 
August 1963. Work remaining is construction of 
lateral permeable pile dikes in Southwest Pass 
from mile 1.8 to 2.8 on east bank and mile 10.1 to 
14.4 and 19.1 to 20.2 on west bank. This work has 
been placed in deferred status. 
17. MISSISSIPPI RIVER-GULF OUTLET, 
LA. 
Location. In State of Louisiana and extends 
from existing Inner Harbor Navigation Canal at 
a point 7,500 feet north of existing lock and about 
11,000 feet from Mississippi River, to a turning 
basin south of Michoud, La., and then as a land 
and water cut from turning basin south of 
Michoud, La., southeasterly to and along south 
shore of Lake Borgne and through marshes to and 
through Chandeleur Sound to 38-foot contour in 
Gulf of Mexico. (See Coast and Geodetic Survey 
Charts 1115, 1116, 1267, 1268, 1269, 1270, and 
1271.) 
Existing project. Provides for a seaway canal, 
36 by 500 feet, extending 76 miles as a land and 
water cut from Michoud southeasterly to and 
along south shore of Lake Borgne, and across 
Chandeleur Sound to Chandeleur Island and 
increasing gradually to 38 by 600 feet in Gulf of 
Mexico, with protective jetties at entrance, a 
permanent retention dike through Chandeleur 
Sound, and a wing dike along islands as required. 
It also provides for an inner tidewater harbor 
consisting of 1,000- by 2,000-foot turning basin 36 
feet deep at landward end of seaway canal, and a 
connecting channel 36 by 500 feet wide extending 
westerly along Gulf Intracoastal Waterway from 
turning basin to Inner Harbor Navigation Canal, 
including construction of a suitable highway 
bridge with approaches to carry Louisiana State 
Highway 47 (formerly 61) over channel. Plan 
further provides for future construction of a 
channel and lock in the vicinity of Meraux to 
furnish an additional connection between 
tidewater harbor and Mississippi River. 
Estimated cost for new work (July 1975) is 
$320,000,000 Federal and $92,500,000 non- 
Federal. In addition, Coast Guard is to provide 
navigation aids at an estimated cost of $533,000. 
This does not include modification for Mississippi 
River-Gulf Outlet, Michoud Canal, which is 
reported separately. 
Local cooperation. Original assurances 
furnished and accepted. Local agency has 
furnished Supplemental Assurance covering 
Public Law 91-646. Rights-of-entry for entire 
11-17

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
project were furnished by local agency which is in 
process of actively conveying to the United States 
title to remaining tracts. 
Terminal facilities. The only facility on the 
waterway is the Public Bulk Terminal of New 
Orleans constructed by Board of Commissioners, 
Port of New Orleans, on left descending bank at 
mile 63. Two new-container ship berths have 
commenced operation at the Industrial Canal end 
of the seaway. 
Operations and results during fiscal year. New 
work by hired labor: Engineering studies, 
surveys, field investigations, and planning for 
new lock continued. 
New work by contract: Contract work for 
capping south stone dike, stations 2649+00 to 
2700+00, was initiated Jul. 6, 1974, and 
suspended Jul. 11, 1974, due to work of higher 
priority. Work resumed Jun. 6, 1975, and is 74 
percent complete. 
Maintenance by hired labor consisted of 
condition and operation studies, channel patrol, 
and preparation of plans and specifications. 
Maintenance by contract: Contract dredging, 
stations 2650+00 to 3980+00 (not continuous), 
continued from last fiscal year and was 
completed Oct. 18, 1974, with a total of 6,650,800 
cubic yards of shoal material removed this fiscal 
year. 
Condition at end of fiscal year. Construction 
was initiated March 1958 and entire project is 21 
percent complete. The channel was opened to 
navigation Jul. 25, 1963, and completed Jan. 20, 
1968. Paris Road Bridge was opened to traffic 
Jul. 21, and completed Nov. 14, 1967. 
Approximately 3 miles of first- and second-lift 
stone dikes have been constructed on north side of 
channel and approximately 8.27 miles of first-lift 
and 7.34 miles of second-lift stone dikes have been 
constructed on south side of channel in Breton 
Sound. Principal work required to complete 
project is construction of new ship lock, raising 
and extending dikes, and construction of 
foreshore protection. 
18. MISSISSIPPI RIVER-GULF OUTLET, 
MICHOUD CANAL, LA. 
Location. The improvement is located in the 
coastal marsh area adjacent to Lake Borgne and 
within the corporate limits of the city of New 
Orleans. (See U. S. Coast and Geodetic Survey 
Chart No. 1269.) 
Existing project. Provides a deep-draft 
navigation channel in the Gulf Intracoastal 
Waterway and Michoud Canal by enlargement to 
a depth of 36 feet over a bottom width of 250 feet 
from the Mississippi River-Gulf Outlet Channel 
to and including a turning basin 800 feet square 
at the north end of Michoud Canal. Estimated 
cost of new work (July 1973) is $3,670,000 Federal 
and $1,060,000 non-Federal. In addition, Coast 
Guard is to provide navigation aids at an 
estimated cost of $9,000. 
Local cooperation. Local interests must provide 
without cost to the United States, all lands, 
easements, and rights-of-way required for 
construction and subsequent maintenance of 
project and for aids to navigation upon the 
request of the Chief of Engineers, including 
suitable areas determined by the Chief of 
Engineers, to be required in the general public 
interest for initial and subsequent disposal of 
spoil, and also retaining dikes for disposal of spoil 
from maintenance dredging, if required; 
accomplish without cost to the United States such 
utility or other relocations or alterations as 
necessary for project purposes; and hold and save 
the United States free from damages due to the 
construction and subsequent maintenance of the 
project, including any erosion beyond the rightsof-
way furnished. 
Assuring Agency: Board of Commissioners of 
the Port of New Orleans. All assurances have 
been furnished. 
Terminal facilities. There are no public 
wharves located in the area; however, the 
developer of the area states that the corporation 
has retained a tract of land at the north end of the 
Michoud Canal for construction of a public wharf 
for seagoing and other marine traffic, which 
would be available to industries without frontage 
on waterways. Several private facilities are 
located on the canal and others are anticipated in 
the future. The Gulf Intracoastal Waterway 
intersects the Mississippi River-Gulf Outlet 
approximately 1.5 miles westward from the 
Michoud Canal. This outlet provides a direct 
tidewater route for ocean shipping. 
Operations and results during fiscal year. 
Contract work for initial dredging in the Gulf 
Intracoastal Waterway, Michoud Canal and 
Turning Basin continued from last fiscal year 
and was completed Nov. 12, 1974, with a total of 
3,194,754 cubic yards of material removed this 
fiscal year. 
Condition at end of fiscal year. Construction 
commenced Mar. 21, 1974, and the channel was 
completed this fiscal year and opened to traffic in 
November 1974. 
19. MISSISSIPPI RIVER OUTLETS, 
VENICE, LA. 
Location. In the coastal marsh area and in the 
vicinity of the Mississippi River at about miles 10 
to 11 above the Head of Passes. (See U. S. Coast 
and Geodetic Survey Chart No. 1272.) 
11-18

NEW ORLEANS, LA., DISTRICT 
Existing project. Provides for additional 
navigation outlets in the vicinity of Venice, La., 
by enlargement of the existing channels of 
Baptiste Collette Bayou and Grand-Tiger Passes 
to 14 by 150 feet with entrance channels in open 
water 16 by 250 feet and jetties to the 6-foot-depth 
contour, if and when justified, to reduce cost of 
maintenance dredging. Estimated cost of new 
work (July 1975) is $9,240,000 Federal and 
$2,100,000 non-Federal. In addition, Coast Guard 
is to provide navigation aids at an estimated cost 
of $88,000. 
Local cooperation. Provides without cost to the 
United States all lands, easements, and rights-ofway 
required for construction and subsequent 
maintenance of the project and for aids to 
navigation upon the request of the Chief of 
Engineers, including suitable areas determined 
by the Chief of Engineers to be required in the 
general public interest for initial and subsequent 
disposal of spoil, and also necessary retaining 
dikes, bulkheads, and embankment therefor or 
the costs of such retaining works; accomplish 
without cost to the United States such alterations 
as required in pipelines, cables, and other 
improvements, as well as their maintenance; and 
hold and save the United States free from 
damages due to the construction and 
maintenance of the project, including but not 
limited to erosion beyond the rights-of-way 
furnished, and damages to oyster beds and other 
fisheries. 
Assuring Agency: Plaquemines Parish 
Commission Council. Basic assurances for the 
project have been furnished. Amended 
assurances covering Public Laws 91-646 and 91- 
611 are expected to be received prior to initiation 
of construction. 
Terminal facilities. In the Venice area, each 
operator of a construction, repair, or supply 
facility provides dock and transfer facilities to 
meet his own needs or arranges to use those of 
another. These facilities are considered adequate 
for the anticipated traffic. If new industry or 
supply facilities are established, they would 
provide any needed terminal facilities for their 
use. Ample areas for future expansion are 
available. 
Operations and results during fiscal year. The 
GDM was approved on May 29, 1975, subject to 
comments. The final Environmental Impact 
Statement to the Council on Environmental 
Quality is expected to be filed next fiscal year. 
Condition at end offiscal year. Construction has 
not commenced. 
20. OVERTON-RED RIVER WATERWAY, 
LA. 
Location. In State of Louisiana between 
junction of the Old and Mississippi Rivers and 
Shreveport, La., along the Old and Red Rivers, 
through land cuts and natural channels on the 
south bank of Red River. (See Geological Survey 
State maps and Mississippi River Commission 
alluvial valley quadrangle maps.) 
Existing project. Provides for a navigation 
route from the Mississippi River at its junction 
with Old River, through Old River to mile 31 of 
the Red River; developing a channel about 31 
miles long, 200 feet wide, and 9 feet deep. 
Improvements consist of revetments, dikes, and 
dredging designed to preserve favorable, and 
correct unfavorable channel alinement and 
depth. In addition to the existing project, the 
authorized work included a navigation route 
from mile 31 of the Red River to Shreveport, La., 
via a lateral canal excavated along the south bank 
of the Red River. However, the portion of the 
authorized project above mile 31 was reclassified 
to inactive status as approved by Office of the 
Chief of Engineers, letter dated Oct. 18, 1971. 
Estimated cost for new work (lower 31 miles only) 
(July 1975) is $21,200,000 Federal and $83,000 
non-Federal. 
Local cooperation. Furnish all necessary lands, 
easements, rights-of-way, and spoil disposal 
areas for new work and subsequent maintenance 
when and as required; make all necessary 
changes in existing highways and highway 
bridges and approaches thereto, and all 
necessary changes in public utilities except 
railroad facilities; take such measures as are 
necessary to insure that non-Federal interests 
will maintain parts of all railroads, highways, 
bridges and utilities affected by the 
improvement; establish, maintain, and operate 
adequate terminal and transfer facilities; and 
hold and save the United States free from 
damages incident to construction, maintenance, 
and operation of the improvement. Assurances of 
local cooperation were furnished for the lower 31 
miles by Red River Waterway Commission, 
governing body of the Red River Waterway 
District, on Mar. 9, 1967, and accepted on behalf 
of the United States on Oct. 6, 1967. The 
Commission executed supplemental assurances 
covering Public Law 91-646 which were accepted 
on Oct. 11, 1973. 
Terminal facilities. None. Will be furnished if 
necessary. 
Operations and results during fiscal year. 
Hired labor forces conducted investigations, 
surveys, bank stability analyses, and preparation 
of plans and specifications. Articulated concrete 
mattress revetment was placed at twolocations. 
Condition at end of fiscal year. Construction of 
the lower 31 miles was initiated Nov. 12, 1968, 
and is 34 percent complete with 28,380 linear feet 
of bank protected. 
11-19

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
21. PETIT ANSE, TIGRE, AND CARLIN 
BAYOUS, LA. 
Location. Bayou Tigre is a tributary of Bayou 
Carlin; Bayou Carlin is a tributary of Bayou Petit 
Anse. Bayou Petit Anse has its source in Iberia 
Parish about 5 miles northwest of New Iberia. It 
flows southwesterly for about 15 miles to its 
intersection with Gulf Intracoastal Waterway, 
thence for about 3 miles to Vermilion Bay. Bayou 
Tigre has its source in Vermilion Parish about 6 
miles northeast of Abbeville and flows southerly 
about 7 miles to its junction with Bayou Carlin. 
Bayou Carlin has its source in Lake Peigneur in 
Iberia Parish and flows southerly about 7.5 miles 
to its confluence with Bayou Petit Anse at a point 
about 2.3 miles above Intracoastal Waterway. 
(See U. S. Coast and Geodetic Survey Chart 1116, 
Corps of Engineers, Mississippi River 
Commission alluvial valley maps and Derouen 
quadrangle, and U. S. Geological Survey map, 
Abbeville, N.E., quadrangle.) 
Existing project. Provides for a harbor of 
refuge at Delcambre, dredging a channel in 
Bayou Petit Anse 9 feet deep and 80 feet wide 
from Intracoastal Waterway to north end of 
Avery Island; a channel 7 feet deep and 60 feet 
wide from Intracoastal Waterway via McIlhenny 
Canal (Avery Canal) to deep water in Vermilion 
Bay; and a channel 9 feet deep over a bottom 
width of 80 feet in Bayou Carlin from Bayou Petit 
Anse to Lake Peigneur. Total length of 
improvement is 16.1 miles. Under ordinary 
conditions mean range of tide is about 10 inches. 
All work under existing project was completed in 
1962 at a cost of $344,389. In addition, $47,858 
was expended from public works funds. 
Local cooperation. Fully complied with. 
Terminal facilities. There is a large oil 
terminal at head of improvement on Bayou Petit 
Anse and several private docks and crane hoists. 
(Terminal facilities are further described in 
H. Doc. 225, 72d Cong., 1st sess.) Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. New 
work by hired labor consisted of general 
engineering and surveys for preparation of plans 
and specifications. 
Condition at end of fiscal year. All work under 
project, as existent at that time, was completed in 
1939; and work authorized by River and Harbor 
Act of Mar. 2, 1945, for a 9- by 80-foot channel was 
completed in 1947, except dredging in vicinity of 
Texas & New Orleans Railroad bridge and 
Louisiana State Highway Department bridge 
crossing Bayou Carlin, which was accomplished 
during 1949, as was reinforcement of bridge piers 
under reimbursable agreement, authorized by 
River and Harbor Act of Jun. 30, 1948. 
Modification of project authorized by River and 
Harbor Act of Jul. 14, 1960, was completed 
Mar. 30, 1962. 
Jefferson Island Salt Co. has partially complied 
with furnishing a 9- by 80-foot canal connecting 
Bayou Carlin with their salt mine, as provided in 
authorizing document. Chief of Engineers has 
accepted a 9- by 60-foot channel as partial 
completion and this 9- by 60-foot channel has been 
excavated for full length prescribed. 
Total cost under existing project to end of fiscal 
year was $926,441, of which $344,389 was for new 
work and $582,052 for maintenance. In addition, 
$47,858 was expended from public works funds 
for new work. 
22. RED RIVER BELOW FULTON, ARK. 
Location. Red River rises in arid regions of 
eastern New Mexico, flows easterly and 
southeasterly for 1,300 miles, and enters 
Atchafalaya River at its confluence with Old 
River. (See Geological Survey State maps and 
Mississippi River Commission alluvial valley 
quadrangle maps.) 
Previous projects. For details see page 572, 1957 
Annual Report. 
Existing project. Continuing improvement of 
Red River from Fulton, Ark., to Atchafalaya 
River, La., 455.6 miles, by systematic clearing of 
banks, snagging, dredging shoals, building 
levees (either along or in cooperation with 
riparian states), closing outlets, revetting caving 
banks, and preventing injurious cutoffs. Lower 
end of this project, exclusive of Overton-Red 
River Waterway is at Old River, 7.6 miles west of 
Mississippi River. No proposed channel 
dimensions are given. Floods ordinarily cause 
fluctuations of stage between high and low water 
of from 30 to 45 feet; unusual floods occasionally 
increase this range about 10 feet. 
Local cooperation. None required. 
Terminal facilities. None. 
Operations and results during fiscal year. 
Hired labor forces conducted stream gaging and 
reconnaissance surveys and channel patrol. 
Condition at end of fiscal year. Maintenance in 
recent years provides for navigation to 
Shreveport, La., at medium and high stages. 
From January to July, prevailing stage is 6 feet 
and over, and controlling depths are about 4 feet 
to Fulton, 5 feet to Shreveport, and 6 feet to 
Alexandria. During remainder of year stages 
near zero may be expected, with controlling 
depths less than 1 foot from Fulton to Shreveport, 
1 to 2 feet from Shreveport to Alexandria, and 
4 feet from Alexandria to mouth of Black 
River. 
11-20

NEW ORLEANS, LA., DISTRICT 
23. RED RIVER EMERGENCY BANK 
PROTECTION 
Location. In northwest Louisiana, southwest 
Arkansas, and northeast Texas, along the Red 
and Old Rivers between the Mississippi River and 
the head of the levee system above Index, Tex. 
Existing project. Provides for realining the 
banks by means of cutoffs and training works and 
for stabilizing banks by means of revetments, 
dikes, and other methods as emergency 
conditions may require in advance of developing 
the design for the entire Red River Waterway 
project. Estimated cost for new work (July 1975) 
is $44,700,000 Federal and $460,000 non-Federal. 
Local cooperation. Local interests are required 
to: (1) provide without cost to the United States all 
lands, easements, and rights-of-way necessary for 
construction and subsequent maintenance of the 
project, including suitable areas determined by 
the Chief of Engineers to be required in the 
general public interest for disposal of spoil, and 
provide necessary retaining dikes, bulkheads, 
and embankments therefor, or the cost of such 
retaining works, and also including all additional 
lands, or rights in land, required to insure public 
control of the recreational development; (2) hold 
and save the United States free from damages 
due to the construction and subsequent 
maintenance of the project; (3) maintain all the 
project works upstream of the navigation 
improvement at Shreveport, La., after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; (4) 
provide without cost to the United States all 
relocations of utilities, bridges (except railroad), 
sewers, pipelines, and any other alterations of 
existing improvements which may be required 
for construction of the project; (5) where the 
appraised value of the land provided for 
recreational development under (1) above 
amounts to less than 50 percent of the total first 
cost of the recreational development, make 
additional contributions sufficient to bring the 
non-Federal share to at least that level, which 
additional contribution may consist of the actual 
cost of carrying out an agreed-upon portion of the 
development, or a cash contribution, or a 
combination of both; (6) operate and maintain for 
the life of the Federal project the recreational 
areas and all facilities installed pursuant to the 
agreement, except that facilities which are 
integral parts of a structure operated and 
maintained by the Federal Government shall be 
operated and maintained under whatever costsharing 
arrangement applies to the operation and 
maintenance of the basic structure; and (7) assure 
access to recreational developments to all on 
equal terms. 
Assuring Agency: The Red River Waterway 
Commission. All assurances for the Louisiana 
portion of the project have been furnished. 
Operations and results duringfiscal year. Work 
by hired labor consisted of preparing plans and 
specifications, surveys, general engineering, and 
a model study. Bank stabilization work was 
completed at three locations: Fausse, La., mile 
178.2-L; East Point, La., mile 239.0-L; and 
Dillard Bend, Ark., mile 354.0-R. Realinement 
and bank stabilization work continued from last 
fiscal year at three locations, Clarence Cutoff, 
La., mile 178.1 to 182.5, 84 percent complete; 
Coushatta, La., mile 220.0-L, 61 percent 
complete, and Kateland Cutoff, La., mile 131.0 to 
135.0, 9 percent complete. Work was initiated this 
fiscal year on three contracts for bank 
stabilization and channel realinement: Brown 
revetment-Wadlow levee setback, mile 153.5, 
commenced Apr. 24, 1975, and is 59 percent 
complete; Coushatta Cutoff, La., mile 220.6 to 
mile 222.5, commenced Aug. 5, 1974, and is 62 
percent complete; and Morameal, La., mile 257.0- 
L, commenced Aug. 5, 1974, and is 43 percent 
complete. A contract for construction of 1.02 
miles of revetment at Cadney, La., was awarded 
Jun. 5, 1975, but work was not initiated. 
Condition at end of fiscal year. Construction 
was initiated in October 1972 and is 34 percent 
complete. 
24. RED RIVER WATERWAYMISSISSIPPI 
RIVER TO 
SHREVEPORT, LA. 
Location. From east central to northwest 
Louisiana along the Red and Old Rivers between 
the Mississippi River and Shreveport, La. 
Existing project. Provide a navigation route 
from the Mississippi River at the junction with 
Old River via Old and Red River to Shreveport, 
La., developing a channel approximately 210 
miles long, 9 feet deep, and 200 feet wide. The 
development will include five locks and dams, 
realinement and contraction of the river as 
necessary to develop an efficient channel, and 
bank stabilization as necessary to hold the newly 
developed channel in position. Facilities to 
provide opportunities for recreation and for fish 
and wildlife development are an integral part of 
the project. Estimated cost for new work (July 
1975) is $950,000,000 Federal and $18,500,000 
non-Federal, including $4,500,000 contributed 
funds. The Federal cost excludes $990,000 for 
aids to navigation by U. S. Coast Guard. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-ofway 
required within the State of Louisiana for 
construction and subsequent maintenance of the 
project and for aids to navigation upon the 
11-21

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
request of the Chief of Engineers, including 
suitable areas determined by the Chief of 
Engineers to be required in the general public 
interest for initial and subsequent disposal of 
spoil, and provide necessary retaining dikes, 
bulkheads, and embankments therefor, or the 
cost of such retaining works, and also including 
all additional lands, or rights in land, required to 
insure public control of the recreation 
development; hold and save the United States 
free from damages due to the construction works 
and subsequent operation and maintenance, 
including but not limited to those resulting from 
dredging, changes in groundwater level, and 
wave action; provide a proportionate share of the 
cost of bridge alterations over existing channels 
in accordance with the principles of Section 6 of 
the Bridge Alteration Act (Truman-Hobbs) of 
Jun. 21, 1940, as amended by the Act of Jul. 16, 
1952; assume all obligations of owning, 
maintaining, and operating all railway and 
highway bridges altered or constructed as part of 
the navigation project; with such obligation for 
each bridge to be assumed by local interests upon 
final completion of alteration or construction of 
that bridge; provide without cost to the United 
States such alterations as required in pipelines, 
and in sewer, water supply, drainage, and other 
utility facilities, as well as their maintenance; 
provide and maintain at local expense adequate 
public terminal and transfer facilities open to all 
on equal terms; and provide and maintain 
without cost to the United States depths in 
berthing areas and local access channels serving 
the terminals commensurate with the depths 
provided in the related project area; obtain 
without cost to the United States any water rights 
that may be found necessary for operation of the 
project in the interest of navigation; where the 
appraised value of the land provided for 
recreational development amounts to less than 50 
percent of the total first cost of the recreational 
development, make additional contributions 
sufficient to bring the non-Federal share to at 
least that level; which additional contribution 
may consist of the actual cost of carrying out an 
agreed-upon portion of the development or a cash 
contribution, or a combination of both; operate 
and maintain for the life of the Federal project 
the recreational areas and all facilities installed 
pursuant to the agreement, except that facilities 
which are integral parts of a structure operated 
and maintained by the Federal Government shall 
be operated and maintained under whatever costsharing 
arrangement applies to the operation and 
maintenance of the basic structure; and assure 
access to recreational developments to all on 
equal terms; and further, that it will participate 
in the bank stabilization element of the Red River 
Waterway, Louisiana, Texas, Arkansas, and 
Oklahoma Project, to the extent that it will: 
Provide without cost to the United States all 
lands, easements, and rights-of-way necessary for 
construction and subsequent maintenance of the 
project, including suitable areas determined by 
the Chief of Engineers to be required in the 
general public interest for disposal of spoil, and 
provide necessary retaining dikes, bulkheads, 
and embankments therefor, or the cost of such 
retaining works, and also including all additional 
lands, or rights in land, required to insure public 
control of the recreational development; 
Hold and save the United States free from 
damages due to the construction and subsequent 
maintenance of the project; 
Maintain all the project works upstream of the 
navigation improvements at Shreveport, La., 
after completion in accordance with regulations 
prescribed by the Secretary of the Army; 
Provide without cost to the United States all 
relocations of utilities, bridges (except railroad), 
sewers, pipelines, and any other alterations of 
existing improvements which may be required 
for construction of the project; 
Where the appraised value of the land provided 
for recreational development, amounts to less 
than 50 percent of the total first cost of the 
recreational development, make additional 
contributions sufficient to bring the non-Federal 
share to at least that level; which additional 
contribution may consist of the actual cost of 
carrying out an agreed-upon portion of the 
development, or a cash contribution, or a 
combination of both; 
Operate and maintain for the life of the Federal 
project the recreational areas and all facilities 
installed pursuant to the agreement, except that 
facilities which are integral parts of a structure 
operated and maintained by the Federal 
Government shall be operated and maintained 
under whatever cost-sharing arrangement 
applies to the operation and maintenance of the 
basic structure; and 
Assure access to recreational development to 
all on equal terms. 
Assuring Agency: The Red River Waterway 
Commission. All assurances for the project have 
been furnished including amended assurances 
covering the requirements of Public Laws 91-611 
and 91-646. 
Terminal facilities. Adequate facilities are to 
be provided and maintained by local interests. 
Operations and results duringfiscal year. Work 
by hired labor consisted of planning and 
preparing design memorandum, preparing plans 
and specifications, surveys, general engineering, 
and model studies. 
New work by contract: Contract work for stone 
trenchfill revetment at Choctaw Bayou Bend, 
11-22

NEW ORLEANS, LA., DISTRICT 
La., mile 72.0 to 72.5, continued from last fiscal 
year and is 74 percent complete. Four contracts 
for construction were awarded as follows: Vick 
revetment, mile 65.8 to 62.3, commenced Nov. 15, 
1974, and is 70 percent complete; St. Agnes 
revetment, mile 53.0 to 50.8 commenced Mar. 6, 
1975, and is 16 percent complete. The remaining 
two were not initiated this fiscal year; Choctaw 
Bayou Bend Cutoff, mile 69.2 to 72.0 awarded 
Jun. 27, 1975, and St. Maurice revetment, mile 
172.3-L, awarded Jun. 25, 1975. 
Condition at end of fiscal year. Construction 
was initiated in July 1973, and project is 1 percent 
complete. 
25. RED RIVER WATERWAYSHREVEPORT, 
LA., TO 
DAINGERFIELD, TEX. 
Location. The project is located in northwest 
Louisiana and northeast Texas along Twelvemile 
Bayou and Cypress Bayou and through Caddo 
Lake and Lake 0' the Pines. It passes through 
Caddo Parish, La., and Harrison and Marion 
Counties, Tex. 
Existing project. The project provides for a 9- 
foot-deep by 200-foot-wide navigation channel 
extending from Red River at Shreveport, La., 
through Twelvemile and Cypress Bayous to a 
turning basin in Lake 0' the Pines (Ferrells 
Bridge Reservoir) downstream of U. S. Highway 
259 bridge near Daingerfield, Tex. There are 
four locks and adjacent dams that will provide the 
required lift of about 80 feet. Two of the locks will 
be constructed in combination with the existing 
Caddo Lake and Ferrells Bridge Dams. Existing 
channels of Twelvemile Bayou and Cypress 
Bayou will be realined and stabilized as 
necessary to develop and maintain an efficient, 
navigable channel. Supplemental water to 
compensate for lockage losses in this reach will be 
provided by a reservoir to be constructed in the 
vicinity of Harvard, Tex., or by other means. 
Estimated cost of new work (July 1975) is 
$305,000,000 Federal and $16,300,000 non- 
Federal, including a cash contribution of 
$3,400,000. In addition, the Coast Guard is to 
provide navigation aids at an estimated $330,000. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-ofway 
required within the State of Louisiana for 
construction and subsequent maintenance of the 
project and for aids to navigation upon the 
request of the Chief of Engineers, including 
suitable areas determined by the Chief of 
Engineers to be required in the general public 
interest for initial and subsequent disposal of 
spoil, and provide necessary retaining dikes, 
bulkheads, and embankments therefor, or the 
cost of such retaining works, and also including 
all additional lands, or rights in land, required to 
insure public control of the recreation 
development; hold and save the United States 
free from damages due to the construction works 
and subsequent operation and maintenance, 
including, but not limited to those resulting from 
dredging, changes in groundwater level, and 
wave action; provide a proportionate share of the 
cost of bridge alterations over existing channels 
in accordance with the principles of Sec. 6 of the 
Bridge Alteration Act (Truman-Hobbs) of Jun. 
21, 1940, as amended by the Act of Jul. 16, 1962; 
assume all obligations of owning, maintaining, 
and operating all railway and highway bridges 
altered or constructed as part of the navigation 
project, with such obligation for each bridge to be 
assumed by local interests upon final completion 
of alteration or construction of that bridge; 
provide without cost to the United States such 
alterations as required in pipelines and in sewer, 
water supply, drainage, and other utility 
facilities, as well as their maintenance; provide 
and maintain at local expense adequate public 
terminal and transfer facilities open to all on 
equal terms; and provide and maintain without 
cost to the United States depths in berthing areas 
and local access channels serving the terminals 
commensurate with the depths provided in the 
related project area; obtain without cost to the 
United States any water rights that may be found 
necessary for operation of the project in the 
interest of navigation; where the appraised value 
of the land provided for recreational development 
amounts to less than 50 percent of the total first 
cost of the recreational development, make 
additional contributions sufficient to bring the 
non-Federal share to at least that level; which 
additional contribution may consist of the actual 
cost of carrying out an agreed-upon portion of the 
development or a cash contribution, or a 
combination of both; operate and maintain for the 
life of the Federal project, the recreational areas 
and all facilities installed pursuant to the 
agreement, except that facilities which are 
integral parts of a structure operated and 
maintained by the Federal Government shall be 
operated and maintained under whatever costsharing 
arrangement applies to the operation and 
maintenance of the basic structure and assure 
access to recreational developments to all on 
equal terms and, further, that it will participate 
in the bank stabilization element of the Red River 
Waterway, Louisiana, Texas, and Oklahoma 
Project, to the extent that it will: 
Provide without cost to the United States all 
lands, easements, and rights-of-way necessary for 
construction and subsequent maintenance of the 
project, including suitable areas determined by 
the Chief of Engineers to be required in the 
general public interest for disposal of spoil, and 
provide necessary retaining dikes, bulkheads, 
11-23

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
and embankments therefor or the cost of such 
retaining works, and also including all additional 
lands, or rights in land, required to insure public 
control of the recreational development; 
Hold and save the United States free from 
damages due to the construction and subsequent 
maintenance of the project; 
Maintain all the project works upstream of 
the navigation improvements at Shreveport, 
La., after completion in accordance with 
regulations prescribed by the Secretary of the 
Army; 
Provide without cost to the United States all 
relocations of utilities, bridges (except railroad), 
sewers, pipelines, and any other alterations of 
existing improvements which may be required 
for construction of the project; 
Where the appraised value of the land provided 
for recreational development, amounts to less 
than 50 percent of the total first cost of the 
recreational development, make additional 
contributions sufficient to bring the non-Federal 
share to at least that level; which additional 
contribution may consist of the actual cost of 
carrying out an agreed-upon portion of the 
development, or a cash contribution, or a 
combination of both; 
Operate and maintain for the life of the Federal 
project the recreational areas and all facilities 
installed pursuant to the agreement, except that 
facilities which are integral parts of a structure 
operated and maintained by the Federal 
Government shall be operated and maintained 
under whatever cost-sharing arrangement 
applies to the operation and maintenance of the 
basic structure; and 
Assure access to recreational development to 
all on equal terms. 
Assuring Agencies: Louisiana: Red River 
Waterway Commission has executed all required 
assurances including amended assurances 
covering the requirements of Public Laws 91-611 
and 91-646. 
Texas: The Texas Water Development Board 
has stated that it does not possess the necessary 
authority with which to apply funds to this 
project. The Development Board suggested that 
the Cypress Valley Navigation District, the 
Northeast Texas Municipal Water District, and 
the Titus County Fresh Water Supply District 
No. 1 be contacted concerning the required 
assurances. A meeting was held in November 
1974 of all interested local agencies and 
representatives of the U. S. Army Corps of 
Engineers, New Orleans District. It was agreed 
that the attorney employed by the Harrison 
County Commissioner's Court would determine 
what action could be most advantageously taken 
to present desired legislation, if possible, to the 
1975 Texas Legislature. This proposed action was 
to be coordinated with the Texas Water 
Development Board representative for further 
dissemination to all others concerned as to action 
taken. The proposed action was not completed 
prior to adjournment of the 1975 Texas 
Legislature. The Texas Water Development 
Board has again been requested to coordinate the 
efforts to have the local cooperation and funding 
aspects of this portion of the project settled. Thus 
far, the Texas Water Development Board has 
been reluctant to be the coordinating agency. 
Efforts to settle this matter are continuing. 
Terminal facilities. Adequate facilities are to 
be provided and maintained by local interests. 
Operations and results during fiscal year. 
Economic reanalysis of project is being made by 
hired labor forces. 
Condition at end of fiscal year. Construction has 
not been initiated. 
26. REMOVING WATER-HYACINTH, LA. 
Location. Lakes and streams tributary to the 
gulf coast. 
Existing project. Removal of plants from 
navigable waters of Florida, Alabama, 
Mississippi, Louisiana, and Texas, so far as they 
are or may become an obstruction to navigation, 
by any mechanical, chemical, or other means 
whatsoever; for construction and operation of 
boats equipped with suitable machinery for such 
removal; and construction and operation of booms 
to prevent plants drifting from one stream to 
another. 
Local cooperation. None required. 
Operations and 'results during fiscal year. 
Maximum use of funds available was made by 
using chemical methods of destruction with 
mechanical equipment held in reserve for use 
only when hyacinth jams necessitate it. 
Maintenance continued in main waterways and 
principal tributaries to prevent water-hyacinth 
obstructions and damage to navigation. 
Preventive maintenance work was carried out in 
secondary streams and feeder areas whenever 
possible. In some cases where alligatorweed has 
previously kept water-hyacinth fringes confined 
along the banks, attack of the alligatorweed flea 
beetles (agasicles) has reduced its 
competitiveness and water-hyacinths are 
multiplying and spreading in the waterways. A 
total of 16,340 acres of water-hyacinth were 
treated by chemical and mechanical methods in 
Bayou Black, Lake Cataouatche and feeder 
streams, Lake des Allemands area, the Port 
Allen-Morgan City Route and Alternate Route of 
the Gulf Intracoastal Waterway, Lake Dauterive 
11-24

NEW ORLEANS, LA., DISTRICT 
and Grand Lake areas, Bayou Penchant-Bayou 
Copasaw area, the Gulf Intracoastal Waterway, 
Bayou Lafourche, Bayou Lacassine, and Bayou 
Teche. Due to very mild winters and the 
freshening effect of high waters, the quantity of 
water hyacinths in the coastal area has increased 
dramatically, as has interference with petroleum 
production and fur trapping. 
Condition at end of fiscal year. From 1900 to 
1902 a boat with suitable machinery for 
destroying hyacinth by crushing was operated. 
From that time until 1937 hyacinths were 
destroyed through use of a solution of arsenic and 
caustic soda which was sprayed on vegetation. 
The vegetation was removed by hand crews, andvegetation 
movement was controlled by booms 
and barricades. Use of arsenic was discontinued 
and hand removal supplanted by use of 
mechanical equipment in conjunction with 
chemical spray (2,4-dichlorophenoxy-acetic 
acid). Use of booms and barricades has been 
discontinued. Present methods of control are by 
means of chemical spraying supplemented by 
mechanical rotary saw-type destroyers for 
opening access paths through solidly jammed 
hyacinth mats. 
27. WATERWAY FROM EMPIRE, LA., TO 
GULF OF MEXICO 
Location. Waterway from Empire, La., to Gulf 
of Mexico via Bayous Long and Fontanelle. (See 
Geological Survey, Empire quadrangle.) 
Existing project. Improvement provides for 
construction and maintenance of a waterway, 10 
miles long, from State-owned canal and lock at 
Empire, La., to Gulf of Mexico, to provide a 
channel 9 by 80 feet, and for initial construction of 
rubblestone jetties inshore of 6-foot-depth 
contour, with landward extensions thereof as 
required to prevent flanking, and for seaward 
extensions to 9-foot-depth contour if and when it 
becomes apparent that such extensions will be 
more economical than maintenance dredging of 
entrance channel. Normal range of tide is from 16 
to 40 inches; hurricane tides may exceed 6 feet. 
Construction was completed at a cost of 
$1,068,142; except for an estimated $1,573,000 for 
extension of jetties to 9-foot-depth contour to be 
constructed if necessary. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Hired labor work consisted of general 
engineering. 
Condition at end of fiscal year. Project is 
physically complete, unless at a later date it is 
found necessary to extend jetties to 9-foot-depth 
contour. Project construction was initiated in 
July 1948 and completed in June 1950, during 
which period the 9- by 80-foot channel from 
Empire, La., to Gulf of Mexico, 10 miles, was 
excavated by contract. A total of 4,061 linear feet 
of jetties was constructed by contract to 6-footdepth 
contour, 1,818 linear feet on east jetty and 
2,243 linear feet on west jetty, from Jun. 23, 1949, 
to Feb. 18, 1950, and Feb. 2 to Mar. 1, 1971. 
28. WATERWAY FROM INTRACOASTAL 
WATERWAY TO BAYOU DULAC, LA. 
(Bayous Grand Caillou and LeCarpe, La. 
Location. Bayou LeCarpe is a tidal stream 
which rises about 1.5 miles southeast of Houma in 
Terrebonne Parish and flows southerly into 
Bayou Pelton, thence into Bayou Grand Caillou, 
which flows southwesterly into Calliou Bay, a 
total distance of about 40 miles. (See Coast and 
Geodetic Survey Chart 1116 and Geological 
Survey maps of Houma, Dulac, Bayou DuLarge, 
and Dog Lake quadrangles.) 
Existing project. As modified, provides for a 10- 
by 45-foot channel in Bayou LeCarpe from Gulf 
Intracoastal Waterway 2.6 miles to Houma 
navigation canal; a 5- by 40-foot channel through 
Bayou Pelton and Bayou Grand Caillou to Bayou 
Dulac, a distance of about 13.7 miles. Between 
miles 2.6 and 5, this project coincides with or is 
adjacent to 15- by 150-foot Houma navigation 
canal. Normal range of tide is 3 to 10 inches; from 
winds, 1 to 3 feet. Cost of new work, completed in 
August 1964, was $129,662. 
Local cooperation. Local interests must furnish 
lands, easements, and rights-of-way necessary for 
enlargement and subsequent maintenance of 
Bayou LeCarpe and provide alterations to 
facilities, and hold the United States free from 
damage. Assurances were furnished and 
accepted. Local agency made available spoil 
areas for maintenance dredging of Bayou 
LeCarpe. None of these areas will be transferred 
to the United States. 
Terminal facilities. Many terminal and 
transfer facilities are in Houma and along 
waterways which flow through area between 
Houma and Gulf of Mexico. All facilities are 
privately owned and operated. Facilities are 
adequate for existing commerce and for 
reasonably prospective commerce. Ample space 
exists for expansion of existing facilities or for 
construction of new wharves and appurtenances. 
Operations and results during fiscal year. 
Hired labor work consisted of surveys and 
preparation of plans and specifications. A 
contract for maintenance dredging at Bayou 
LeCarpe was awarded Jun. 19, 1975, but work 
was not initiated. 
Condition at end of fiscal year. The 5- by 40-foot 
channel was constructed from January 1938 to 
11-25

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
August 1938, and modification of October 23, 
1962, for enlargement of 2.54 miles of Bayou 
LeCarpe to 10 feet by 45 feet was initiated in May 
and completed August 1964. 
29. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 11-F. 
30. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, 
Public Law 86-645, as amended 
(preauthorization). 
Preauthorization studies cost for fiscal year 
was $1,830 for Bayou Barataria-Bayou Perot, La. 
Flood Control 
31. BAYOU BODCAU AND 
TRIBUTARIES, ARK. AND LA. 
Location. In left bank flood plain of Red River. 
Bayou Bodcau rises in vicinity of Hope, Ark., and 
flows southerly through Bayou Bodcau Reservoir 
and Bodcau Lake to join Cypress Bayou and form 
Red Chute Bayou, continues through Red Chute 
Bayou, Flat Lake, and Loggy Bayou to Red River, 
about 40 miles below Shreveport, La. 
Existing project. Cypress Bayou-Red Chute 
Bayou levee: Extend existing levee from about 8 
miles southeast of Benton, La., proceeding 
southerly to junction of Cross and Red Chute 
Bayous, and then parallel to Red Chute Bayou on 
the right descending bank to its junction with 
Cutoff Bayou for a total distance of 
approximately 25 miles; construct landside 
drainage channel and several culverts with flap 
gates on Red Chute Bayou; construct cutoff on 
Red Chute Bayou just south of Louisiana 
Highway 527; construct approximately 5 miles of 
levee on left descending bank of Red Chute Bayou 
extending south from Louisiana Highway 612, 
and relocate utility lines as needed. 
Flat River-Loggy Bayou levee: Extend from 
lower end of existing Red River levee in vicinity of 
Ninock, La., along high (left descending) bank of 
Red River to a point on right descending bank of 
Loggy Bayou, about 1 mile above its mouth, 
thence generally along right descending bank of 
Loggy Bayou, Red Chute, Cutoff Bayou, and Flat 
River to Taylortown to tie into existing Red River 
levee; close Flat River near its junction with 
Cutoff Bayou and install one 36-inch round 
corrugated metal pipe with automatic flap gate to 
drain isolated pockets and provide uninterrupted 
drainage; construct drainage structures on Flat 
River near its junction with Red Chute Bayou and 
along alinement of the Loggy Bayou in the 
vicinity of Grassy Lake; and make necessary 
utility relocations. 
Flat River channel improvement: Enlarge to 
average bottom width of 50 feet with flat side 
slopes and deepen by 2 to 6 feet from the 
confluence with Cutoff Bayou to junction with 
Cooper Bayou, 11.6 miles, including required 
relocations and modifications of utilities. 
Estimated cost for new work (July 1975) is 
$12,800,000 Federal and $3,100,000 non-Federal. 
Local cooperation. Provides lands, easements, 
and rights-of-way for construction, including 
flowage easements over 10,900 acres of bottom 
lands above U. S. Highway 80 that will be 
adversely affected by the levee; provide all 
relocation of pipelines, utilities, roads, bridges, 
and other facilities; hold and save the United 
States free from damages; provide assurances 
that encroachment on improved channels or on 
ponding areas will not be permitted, and that, if 
ponding areas and capacities are impaired, 
substitute storage capacity or equivalent 
pumping capacity will be provided promptly 
without cost to the United States; and maintain 
and operate all works after completion. 
Accomplish the associated drainage works 
necessary to insure effective use and realization 
of the benefits of the improvement and comply 
with the provisions of Public Laws 91-611 and 
91-646. 
Assuring Agency: Bossier Levee District and 
Nineteenth Louisiana Levee District. All 
assurances have been furnished by Bossier Levee 
District. Assurances have been executed by 
Nineteenth Louisiana Levee District. Louisiana 
Department of Public Works has furnished 
assurances agreeing to lend all financial 
assistance needed by the Nineteenth Louisiana 
Levee District. Supplemental assurances were 
accepted from both levee districts on Apr. 1, 
1974, complying with Public Laws 91-611 and 
91-646 requirements. 
Operations and results during fiscal year. New 
work by hired labor forces consisted of 
preparation of plans and specifications and 
general engineering. The memorandum for 
Cypress Bayou-Red Chute Bayou levee was 
submitted to higher authority in November 1972. 
Comments by higher authority were answered by 
New Orleans District and returned on Jun. 29, 
1973, for resolution. Further comments by higher 
authorities were answered by New Orleans 
District and returned Jun. 27, 1975. The 
memorandum for Flat River-Loggy Bayou levee 
and the Flat River channel improvement was 
submitted to higher authority in June 1973 and 
comments by higher authority are presently 
being resolved. A contract for construction of 
approximately 6.6 miles of new levee on the west 
bank of Red Chute Bayou and Cypress Bayou 
11-26

NEW ORLEANS, LA., DISTRICT 
above U. S. Highway 80 was initiated Oct. 3, 1974, 
with preliminary work accomplished during the 
fiscal year. 
Condition at end of fiscal year. Construction 
was initiated in October 1974 and is 7 percent 
complete. 
32. BAYOU BODCAU RESERVOIR, LA. 
Location. In Red River Basin on Bayou Bodcau 
in Bossier Parish, La., 72 miles above mouth of 
Loggy Bayou and 35 miles northeast of 
Shreveport, La. (See Geological Survey State 
map, scale 1:500,000.) 
Existing project. An earth-fill dam rising 76 
feet above streambed with a reservoir providing a 
flood control storage capacity of 357,000 acrefeet. 
Outlet works are in south abutment, and an 
uncontrolled spillway is on north abutment. 
Reservoir controls 656 square miles, or 53 
percent, of entire drainage area of Bayou Bodcau. 
Construction of a floodway for diversion of Bayou 
Bodcau and Cypress Bayou to improve flood 
protection was authorized by 1936 Flood Control 
Act. This authorization was modified by 1938 
Flood Control Act, which authorized construction 
of a reservoir and other flood control works in lieu 
of construction of a floodway for diversion of 
Bayou Bodcau and Cypress Bayou, La., to 
improve flood protection, and further modified 
by War Department Civil Appropriation Act of 
1939 which provided that reservoir and other 
flood control works on Bayou Bodcau and Cypress 
Bayou, La., authorized by Flood Control Act of 
1938 shall be constructed in accordance with 
revised plans and cost estimates in Office, Chief of 
Engineers. Cost of new work completed in 1961, 
except construction under Code 711, was 
$4,098,740. Estimated cost for Code 711 (July 
1975) is $1,022,000 
Local cooperation. None required. 
Operations and results during fiscal year. 
Operation and ordinary maintenance of the dam 
and reservoir were continued throughout the 
fiscal year. A contract for construction of a 
masonry restroom, Type E, commenced Oct. 28, 
1974, and was completed Jan. 30, 1975. Number 
of visitor-days of recreational use, 331,500 
(calendar year 1974). (See Table 11-G for 
reservoir operations.) 
Condition at end of fiscal year. Construction 
was initiated April 1947 and completed April 
1961, except construction under Code 711. 
33. BAYOU PIERRE, LA. 
Location. In Red River Basin below 
Shreveport, La., along channel of Bayou Pierre 
from its mouth at Grand Ecore, La., upstream 30 
miles to its confluence with Bayou Wincy. (See 
Geological Survey State map, scale 1:500,000.) 
Existing project. Provides for widening 
channel at intervals, totaling 12.9 miles, and 
snagging of 29.7 miles, to reduce flood damage 
and improve sanitary and living conditions over a 
wide area. Cost of new work, completed in 1939, 
was $299,529. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Condition and operation studies were continued 
by hired labor. Maintenance by hired labor 
consisted of snagging and clearing operations. 
Condition at end of fiscal year. Construction 
was initiated in Fiscal Year 1938 and completed 
in Fiscal Year 1939. 
34. BRUSH BAYOU, LA. 
Location. Rises in the southwestern portion of 
Shreveport, La., in Caddo Parish. The stream 
flows in a generally southerly direction 
approximately 9 miles to a junction with Boggy 
Bayou. 
Existing project. The plan of improvement 
consists of the enlargement and realinement of 
the channel between miles 1.20 and 7.42. Between 
miles 1.20 and 2.18 the channel would be 
radically realined, and above the point, the 
enlarged channel would generally follow the 
existing alinement. Bottom widths for the 
improved channel vary from 100 feet at mile 1.20 
to 20 feet at mile 7.42. Construction of the project 
would require modification of two highway 
bridges, one railway bridge, and numerous 
pipelines and power lines. Estimated cost of new 
work (July 1975) is $1,000,000 Federal and 
$2,020,000 non-Federal, including $920,000 
contributed funds. Includes $80,500 
preauthorization study cost. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-ofway 
necessary for the construction of the project; 
hold and save the United States free from claim 
for damages due to the construction works; 
maintain and operate all works, including 
measures for beautification, after completion in 
accordance with regulations prescribed by the 
Secretary of the Army; bear all cost for the 
project in excess of the Federal limitation of 
$1,000,000; provide without cost to the United 
States all relocations and alterations of all drains, 
bridges (except railroad bridges) and roads, 
pipelines, sewers, utility lines, and other facilities 
made necessary by the project; prevent 
encroachment on improved channels, and adopt 
and enforce flood plain regulations to restrict 
development of areas lying below the elevation of 
the 100-year-frequency flood under project 
conditions; comply with the provisions of Public 
11-27

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Laws 91-611 and 91-646. Caddo Parish Police 
Jury is assuring agency. Assurances have been 
received and accepted. 
Operations and results during fiscal year. New 
work by hired labor consisted of preparation of 
plans and specifications and general engineering. 
Condition at end of fiscal year. Construction has 
not commenced. 
35. CADDO LAKE, LA. 
Location. In Caddo Parish, about 19 miles 
northwest of Shreveport, La., at foot of Caddo 
Lake and at head of Twelve Mile Bayou. 
Existing project. Replacement of existing dam 
with new dam having same flow characteristics 
and located as near as practicable downstream of 
the old dam, built under navigation project 
"Cypress Bayou and Waterway between 
Jefferson, Tex., and Shreveport, La." New dam 
will be capable of being raised in the future if 
desirable and justified. Estimated cost of new 
work (July 1975) is $3,587,800 Federal and 
$218,000 non-Federal. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
General engineering work was conducted by 
hired labor forces during the fiscal year. New 
work: A contract for final road construction was 
initiated in January 1975 and is 13 percent 
complete. 
Condition at end of fiscal year. Construction of 
project, commenced in August 1968, was 
completed in June 1971. 
36. CHOCTAW BAYOU AND 
TRIBUTARIES, LA. 
Location. Choctaw Bayou drainage area is 
located in Pointe Coupee, West Baton Rouge, and 
Iberville Parishes between the west Mississippi 
River levee and Morganza. Floodway. Choctaw 
Bayou is formed by the confluence of Bayou 
Chalpin and Stumpy Bayou, about 12 miles west 
of Port Allen. From this point, the bayou flows 
southeasterly about 7.5 miles and enters Morgan 
City-Port Allen Route of Gulf Intracoastal 
Waterway at mile 56.1 through a land cut 0.6 mile 
long. (See Mississippi River Commission alluvial 
map; New Roads and Grosse Tete quadrangles.) 
Existing project. Provides for channel 
improvement by excavation of Choctaw Bayou, 
miles 0.0 to 7.5, Bayou Chalpin, miles 7.5 to 9.5, 
and Bayou Cholpe, miles 9.5 to 12.6; channel 
improvement by clearing and snagging Bayou 
Cholpe, miles 12.6 to 13.2 and thence 2.5 miles 
where it becomes a part of the main channel at 
mile 15.9, Bayou Sterling, miles 13.2 to 15.9, 
Chamberlin Canal from its confluence with 
Choctaw Bayou at mile 4.6 upstream for 2.7 
miles, and Stumpy Bayou from its confluence 
with Choctaw Bayou at mile 7.2 upstream for 14.1 
miles. Estimated cost of new work (July 1974) is 
$950,000 Federal and $614,000 non-Federal, 
including $300,000 contributed funds. Includes 
$72,000 preauthorization study cost. 
Local cooperation. Local interests must provide 
without cost to the United States all lands, 
easements, and rights-of-way necessary for the 
construction of the project; hold and save the 
United States free from damages due to the 
construction works; maintain and operate all 
works after completion in accordance with 
regulations prescribed by the Secretary of the 
Army; provide all modifications to bridges, 
pipelines, utility lines, and other facilities made 
necessary by the project; provide a cash 
contribution in the amount of 25.5 percent of the 
construction cost, presently estimated at 
$300,000; or construct such additional items of 
work as may be agreed to be equivalent to the 
specified cash contribution; prevent 
encroachment on improved channels; and 
construct the associated works needed to insure 
effective use and realization of the benefits of the 
improved outlet system, without bar, however, to 
any assistance that may be available under other 
Federal and local assistance and conservation 
programs. 
Assuring Agency: The Louisiana Department 
of Public Works, West Baton Rouge Parish Police 
Jury, and the Pointe Coupee Parish Police Jury. 
All assurances for the project have been 
furnished. 
Operations and results during fiscal year. A 
contract for channel improvement and 
enlargement continued from last fiscal year with 
a total of 404,769 cubic yards of material removed 
this fiscal year. Work has been temporarily 
stopped due to high river stages. 
Condition at end of fiscal year. Construction 
was initiated in June 1973 and work is 77 percent 
complete. 
37. COOPER LAKE AND CHANNELS, 
TEX. 
Location. Cooper Dam and Reservoir is about 4 
miles southeast of Cooper, 13 miles north of 
Sulphur Springs, Tex., and is at mile 23.2 on 
South Sulphur River, which rises in Fannin 
County, Tex., and flows generally east for about 
80 miles to its confluence with North Sulphur 
River to form Sulphur River. 
Existing project. Provides for construction of an 
earth-fill dam with maximum height of about 73 
feet, 15,882 feet long at its crest, one controlled 
(service) spillway, and an emergency 
11-28

NEW ORLEANS, LA., DISTRICT 
uncontrolled spillway. Reservoir area will be 
22,740 acres at top of flood control pool, 5,084 
acres at top of sediment pool, and 19,305 acres at 
top of water-supply pool. The reservoir will 
contain 131,400 acre-feet of flood control storage 
space, 273,000 acre-feet of municipal and 
industrial water supply space, and 37,000 acrefeet 
of sediment storage. Also provides for 
channel clearing, realinement, and enlargement; 
enlargement and extension of existing levees; and 
construction of appurtenant drainage works 
along main stem of Sulphur River above mile 126; 
channel clearing, realinement, and enlargement 
and levee enlargement and modification of 
appurtenant drainage works on Cuthand Creek 
below mile 24, on Sulphur River below mile 70, 
except in proposed Cooper Reservoir, miles 29 to 
42, and on Middle Sulphur River below mile 8 
channel clearing and realinement of Brushy 
Creek below mile 5; and levee enlargement on 
North Sulphur River between miles 1 and 5. 
Uncompleted channel and levee improvements 
lying between the damsite and Texas Highway 37 
will be deleted in the interest of accommodating 
Texas Water Plan. Estimated Federal cost for 
new work (July 1975) is $61,800,000, which 
includes $25,600,000 to be reimbursed by water 
supply users over a 50-year period and $3,180,000 
non-Federal, including a $2,800,000 cash 
contribution for modifications to accommodate 
the Texas Water Plan. This estimate is based on a 
reservoir containing 273,000 acre-feet of water 
supply. 
Local cooperation. Except for Cooper 
Reservoir, local interests must furnish lands and 
rights-of-way, and alter and relocate highways 
and related facilities and utilities, except 
railroads, for construction; hold and save the 
United States free from damages; maintain and 
operate all works after completion, and preserve 
channel capacities by preventing encroachment. 
Local agencies furnished rights-of-way for first 
two phases of work on levees and channels 
downstream from Cooper Dam. Right-of-way 
acquisition for part II, for channels and levees 
downstream from Cooper Dam, is essentially 
complete, except for that required below mile 
140.4, Sulphur River (Magnolia Pipeline 
Crossing). Right-of-way acquisition for this 
portion of project is inactive pending resolution of 
a controversy among local interests as to the 
responsibility for relocation of the pipeline. 
Deletion of the Texas Water Plan from future 
project planning will require the reinstatement 
of about 19 miles of levee and channel 
improvements below the damsite, to include 
right-of-way acquisition in this reach. 
Assuring Agencies are the following counties 
in Texas: Delta, Hunt, Franklin, Lamar, Morris, 
Hopkins, Titus, and Red River. Basic assurances 
have been received. Supplemental assurances 
covering Public Law 91-646 have not been 
received for Delta, Lamar, Morris, or Red River 
County. 
Operations and results during fiscal year. 
Surveys, planning, and negotiations with 
cooperating agencies were continued by hired 
labor. Work on the detail design memorandum 
for the dam and reservoir is continuing and is 
expected to be completed in Fiscal Year 1976. 
Land acquisition and work on the environmental 
impact statement continued. The project is 
currently under a court injunction, issued May 
26, 1971, which prevents further construction 
work on the project until a final environmental 
impact statement is prepared and filed with the 
Council on Environmental Quality. 
Condition at end of fiscal year. Construction of 
project began July 1958 and is 23 percent 
complete, with 14.2 miles of South Sulphur River 
and 6.3 miles of Middle Sulphur River channels 
excavated; and 3.4 miles of levee embankment on 
South Sulphur River and 7.3 miles of levee 
embankment constructed on Middle Sulphur 
River, all upstream from Cooper Reservoir. 
About 10.5 miles of levee on North Sulphur River, 
8.2 miles of levee on Sulphur River, 14 miles of 
levee on Cuthand Creek, and 4.2 miles of levee on 
Brushy Creek were strengthened; 0.5 mile of 
levee on Kickapoo Creek was enlarged; and 15.3 
miles of new channel in Cuthand Creek, 0.8 mile 
of new channel in Brushy Creek, and 0.2 mile of 
cutoff channel in Kickapoo Creek were 
excavated; all downstream from Cooper 
Reservoir. Modification of Texas and New 
Orleans Railroad Co.'s trestle 93.77, Middle 
Sulphur River, was completed August 1959, and 
modification of St. Louis Southwestern Railway 
Co.'s trestles 533.74 and 542.61, South Sulphur 
River, January 1960. 
38. FERRELLS BRIDGE DAM-LAKE O' 
THE PINES, TEX. 
Location. On Cypress Creek in Marion, 
Harrison, Upshur, Morris, Camp, and Titus 
Counties, Tex., 8 miles west of Jefferson, Tex. 
Existing project. An earth-fill dam 10,600 feet 
long and 77 feet high includes a 200-foot spillway 
with a capacity of 68,200 cubic feet per second. 
Reservoir controls runoff from 850 square miles 
of drainage area, and has a gross storage capacity 
of 842,100 acre-feet, including 587,200 acre-feet 
flood control storage, 3,800 acre-feet conservation 
storage, and 251,100 acre-feet for municipal and 
industrial water supply. Reservoir extends 28 
miles upstream. Project affords substantial flood 
protection of Cypress Creek Valley from damsite 
to confluence with Red River and, together with 
operation of other reservoirs proposed in Red 
11-29

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
River Basin, will provide flood protection along 
main stem of Red River below Denison Dam. 
Estimated cost for new work (July 1975) is 
$16,831,700 Federal, including $4,070,200 for 
Code 711 and $399,739 accelerated public works 
funds. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work by hired labor consisted of preparation of 
plans and specifications for recreation facilities. 
Maintenance by hired labor consisted of 
operation and maintenance of dam and reservoir 
area, and public use facilities. 
New work by contract: A contract for 
construction of three washhouses, one Type B and 
two Type D, was awarded in May 1975 but work 
was not initiated this fiscal year. 
Maintenance by contract: A contract for 
bituminous surfacing of roadways, trailer 
campsites, and parking areas continued from 
prior fiscal year and was completed Aug. 23, 
1974. 
Number of visitor-days of recreational use, 
4,497,500 (Calendar Year 1974). 
Condition at end of fiscal year. Construction 
commenced in January 1955 and was completed 
in June 1960, except completion of real estate 
activities and construction under Code 711. The 
project is 82 percent complete. 
39. GARLAND CITY, ARK. 
Location. Red River is formed in West Texas 
and flows easterly along Texas-Oklahoma State 
line into southwestern Arkansas at Fulton where 
the river turns and flows southward to above 
Shreveport, La., and then southeastward to join 
with Old River and form Atchafalaya River. 
Garland City is in Miller County, Ark., on right 
bank of Red River about mile 372 (1957 mileage). 
Existing project. Bank protection works 
consisting of a pile revetment on left bank of Red 
River above railway bridge or equivalent 
protective works, rock groins between the 
bridges, riprap around east bank railway pier, 
pile dikes on right bank of Red River above 
railway bridge, channel excavation on right bank 
in vicinity of railway bridge and a board 
revetment or equivalent work near anticipated 
natural cutoff to be constructed for protection of 
railway and highway bridges over Red River at 
Garland City, Ark. Estimated cost for new work 
(July 1969) is $1,340,000 Federal and $6,000 non- 
Federal. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. A 
contract for stone and pile dike reinforcement at 
mile 382.0 continued from last fiscal year and was 
completed Jul. 10, 1974, with a total of 28,863 tons 
of quarry-run stone placed. 
Condition at end of fiscal year. Construction 
commenced March 1962 and was completed July 
1974. 
40. HARVEY CANAL, BAYOU 
BARATARIA LEVEE, LA. 
Location. In Jefferson Parish, La., on the right 
bank of the Mississippi River opposite New 
Orleans and bounded on the east by Harvey 
Canal, on the west and south by Bayou des 
Familles, and on the north by the towns of 
Marrero and Harvey. 
Existing project. To provide flood protection by 
construction of new levees and enlargement of 
existing non-Federal levees along Harvey Canal 
and Bayou Barataria from mile 1.8 on Harvey 
Canal to Louisiana Highway No. 45 near Crown 
Point, a distance of approximately 9.2 miles. 
Estimated cost for new work (July 1972) is 
$1,000,000 Federal, and $5,020,000 non-Federal, 
including a cash contribution of $750,000. 
Local cooperation. Provide lands, easements, 
and rights-of-way for construction of the project, 
including necessary modifications and/or 
relocation of existing facilities; hold and save the 
United States free from damages due to the 
construction works; construct an additional 
pumping station with an initial capacity of not 
less than 154 cubic feet per second as provided in 
the plan of improvement, and future extensions to 
pumping capacities as may be necessary for the 
development of the area; and maintain and 
operate all works after completion. The Jefferson 
Parish Council furnished an Act of Assurance 
dated Apr. 20, 1967, which was accepted by the 
United States on Oct. 13, 1967. The local agency 
has acquired and made available necessary 
rights-of-way for construction purposes. 
Operations and results during fiscal year. New 
work by hired labor consisted of general 
engineering. 
Condition at end of fiscal year. Construction of 
Phase I commenced in September 1971 and was 
completed November 1973. Construction has not 
commenced on Phase II. 
41. LAKE PONTCHARTRAIN AND 
VICINITY, LA. (HURRICANE 
PROTECTION) 
Location. In southeastern Louisiana, vicinity of 
New Orleans, in St. Charles, Jefferson, Orleans, 
St. Bernard, and St. Tammany Parishes, 
comprising lower land and water area between 
Mississippi River alluvial ridge and the 
Pleistocene escarpment to north and west. The 
11-30

NEW ORLEANS, LA., DISTRICT 
dominant topographic feature is Lake 
Pontchartrain, a shallow landlocked tidal basin, 
about 640 square miles in area and averaging 12 
feet deep, connecting with lesser Lake Maurepas 
to the west and through Lake Borgne and 
Mississippi Sound to the gulf to the east. The lake 
drains about 4,700 square miles of tributary area. 
(See Geological Survey quadrangles Yscloskey 
and Malheureaux Point, Drum Bay, Door Point, 
Lake Eugenie, Oak Mound Bayou, Mitchell Keys, 
Lake Eloi, and Morgan Harbor; Engineer 
quadrangles Slidell, Covington, Ponchatoula, 
Springfield, Denham Springs, Donaldsonville, 
Mt. Airy, Bonnet Carre, Spanisli Fort, Chef 
Menteur, Rigolets, St. Bernard, New Orleans, 
and Hahnville; and Coast and Geodetic Survey 
Charts 1115 and 1116.) 
Existing project. Provides for control of 
hurricane tides by construction of two 
independent units; the Lake Pontchartrain 
barrier plan involves construction of a barrier 
levee along eastern boundary of the lake with 
navigation and hurricane flood control structures 
in Chef Menteur Pass, the Rigolets, and at 
Seabrook. These protective works, together with 
strengthening and extension of existing 
protective works and the construction of the 
Seabrook Lock, will afford full protection to the 
south shore of Lake Pontchartrain from Bonnet 
Carre Spillway to the eastern limit of Orleans 
Parish levee along the Gulf Intracoastal 
Waterway and the Inner Harbor Navigation 
Canal. The Chalmette area plan consists of 
improving existing protection along east bank 
Inner Harbor Navigation Canal from the lock to 
Florida Avenue, then constructing a new levee to 
Mississippi River-Gulf Outlet, thence along south 
bank of gulf outlet to Bayou Lawler, then turning 
south and tieing into Mississippi River levee at 
Violet, La. The approved Chalmette area plan 
was modified, under the discretionary authority 
of the Chief of Engineers, to provide for 
enlargement of the protected area by 
construction of a levee from the Mississippi River 
levee near Caernarvon, La., to the vicinity of 
Verret, La., thence to and along the Mississippi 
River-Gulf Outlet to a junction with the approved 
levee at the Bayou Lawler crossing of the 
Mississippi River-Gulf Outlet, and elimination of 
the levee in the approved plan from the Bayou 
Lawler and Mississippi River-Gulf Outlet to 
Violet, La. Navigable drainage structures will be 
provided at Bayous Bienvenue and Dupre. 
Strengthening existing seawall at Mandeville on 
the north shore will insure that future hurricanes 
will not seriously damage this resort community. 
Estimated cost for new work (July 1975) is 
$242,000,000 Federal and $110,000,000 non- 
Federal, including cash contribution of 
$81,860,000, which includes $9,230,000 estimated 
to be capitalized value of operation and 
maintenance of Rigolets navigation lock and 
appurtenant channel. 
Local cooperation. Provide all rights-of-way; 
bear 30 percent of first cost, consisting of fair 
market value of providing all lands, easements, 
and rights-of-way, including borrow and spoil 
disposal areas for construction, accomplish 
alteration and relocation of roads, railroads, 
pipelines, cables, wharves, drainage structures, 
and other facilities; maintain and operate all 
works after completion; and hold and save the 
United States free from damages. See H. Doc. No. 
231, 89th Cong., 1st sess. for more detailed 
requirements of local cooperation. 
Assuring Agency: The Orleans Levee District, 
Lake Borgne Basin Levee District, St. Bernard 
Parish Police Jury, Louisiana Department of 
Public Works, Pontchartrain Levee District, and 
St. Tammany Parish Police Jury. Basic 
assurances were received from the following: 
Orleans Levee District for the entire barrier plan 
and that portion of the Chalmette area plan in 
Orleans Parish; Pontchartrain Levee District for 
the barrier plan; Lake Borgne Levee District and 
St. Bernard Parish Police Jury for the Chalmette 
area plan in St. Bernard Parish. Supplemental 
assurances covering Public Law 91-646 have 
been received from the Orleans Levee District 
and the Pontchartrain Levee District. Approval 
of Pontchartrain's supplemental assurance is 
being delayed pending receipt of supporting 
documents. Lake Borgne Basin Levee District 
and St. Bernard Parish Police Jury have 
executed the supplemental assurance. The 
Governor of Louisiana executed an assurance 
containing all required provisions of local 
cooperation, including Public Law 91-646, for 
and on behalf of St. Tammany Parish. Approval 
of this assurance is being delayed pending receipt 
of supporting documents. Louisiana Department 
of Public Works is assisting in obtaining the 
required documents. 
Operations and results during fiscal year. 
Preparation of design memorandums and plans 
and specifications continued by hired labor and 
contract. Preparation of eight design 
memorandums is under way. 
New work by contract: Construction of two 
control structures continued from prior fiscal 
year and were completed; Bayou Bienvenue, 
Orleans Parish, which was completed in 
September 1974, and one at Bayou Dupre, St. 
Bernard Parish, which was completed in July 
1974. Contract work for erosion protection of 
Bayou Bienvenue Closure Dam was initiated and 
completed in December 1974 with placement of 
126,090 cubic yards of hydraulic fill. New 
Orleans East: Contract work at South Point to 
11-31

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Gulf Intracoastal Waterway continued from last 
fiscal year and was completed Dec. 3, 1974. Work 
consisted of construction of 8.0 miles of levee and 
replacement of three drainage structures. Work 
was initiated on two contracts as follows: East 
bank of Michoud Canal, stations 664+73.3 to 
774+60, for construction of 2.0 miles of floodwall 
and incidental work, commenced Jul. 1, 1974, and 
is 80 percent complete, and Paris Road to South 
Point, Orleans Parish, for construction of 6.3 
miles of levee including drainage structures, 
commenced Jul. 9, 1974, and is 15 percent 
complete. A contract for Chalmette Unit, 
Caernarvon floodwall and levee, stations 1567+49 
B/L to 1577+18.99, with construction of 1,100 
linear feet of I and T type floodwall and other 
incidental work, commenced Jun. 2, 1975, and is 
16 percent complete. 
Condition at end of fiscal year. Construction 
started May 1967 and is 24 percent complete, 
with 8.6 miles of reinforced concrete floodwalls, 
17.2 miles of first-lift levees completed in the New 
Orleans east area, 1.2 miles of floodwall and 27.6 
miles of first-lift levees, 11.9 miles of second-lift 
levees, and two control structures completed in 
the Chalmette area. 
Work under contract at the end of the fiscal 
year provides for completion of 6.3 miles of levee 
and construction of 2.2 miles of floodwall. 
42. LAROSE TO GOLDEN MEADOW, LA. 
(HURRICANE PROTECTION) 
Location. In coastal section of Louisiana, along 
Bayou Lafourche, and includes lands on both 
banks of the bayou from Larose to 2 miles south of 
Golden Meadow. (See Geological survey 
quadrangles Cut-off, Lake Felicity, Bay Dosgris, 
Golden Meadow Farms, Bay Tambour, Mink 
Bayou, Caminada Pass, Leeville, Belle Pass, 
Pelican Pass, and Calumet Island; Engineer 
quadrangles New Orleans, Hahnville, Pointe-ala-
Hache, Barataria, and Fort Livingston; and 
Coast and Geodetic Survey Charts 1115 and 
1116.) 
Existing project. Provides a loop levee about 40 
miles long along both banks of Bayou Lafourche 
from Larose to South Golden Meadow; 
enlargement of 3 miles of existing levee at Golden 
Meadow; floodgates for navigation and hurricane 
protection in Bayou Lafourche at upper and 
lower bayou crossings; about 8 miles of low 
interior levees to regulate intercepted drainage 
and seven multibarreled culverts controlled by 
flapgates. Estimated cost for new work (July 
1975) is $22,800,000 Federal and $9,700,000 non- 
Federal, including a cash contribution of 
$5,690,000. 
Local cooperation. Provide lands, easements, 
rights-of-way, and spoil disposal areas for 
construction and future maintenance; alter 
pipelines, cables, wharves, oil wells, and any 
other facilities for construction; prevent 
encroachment on ponding areas unless substitute 
storage capacity or equivalent pumping capacity 
is provided promptly without cost to the United 
States; maintain and operate all works after 
completion; contribute in cash and equivalent 
work 30 percent of total project cost, including 
cost for furnishing rights-of-way, relocations, 
etc.; and hold and save the United States free 
from damages. 
Assuring Agency: The South Louisiana Tidal 
Water Control Levee District. All assurances for 
the project have been furnished. 
Operations and results during fiscal year. Work 
has commenced on the detailed design 
memorandums for the two floodgates. A contract 
for construction of 3.83 miles of first-lift levee, 
section A west, commenced Feb. 18, 1975, and is 
46 percent complete. 
Condition at end of fiscal year. Construction 
commenced in February 1975. 
43. MISSISSIPPI RIVER DELTA AT AND 
BELOW NEW ORLEANS, LA. (NEW 
ORLEANS TO VENICE, LA., 
HURRICANE PROTECTION) 
Location. Includes land subject to inundation 
by hurricane tides extending along both banks of 
the Mississippi River below New Orleans from 
vicinity of Phoenix to Venice, La. 
Existing project. Provides for improvements 
along Mississippi River below New Orleans, La., 
for prevention of hurricane tidal flood damages 
by increasing heights of existing back levees and 
modifying existing drainage facilities where 
necessary in three separate reaches: City Price to 
Empire, 15 miles, 4,340 acres protected; Empire 
to Venice, 21 miles, 4,900 acres protected; 
Phoenix to Bohemia (construction initiated by 
local agency), 16 miles, 5,470 acres protected, and 
construction of a barrier levee on the east bank of 
the Mississippi River from Bohemia to mile 10 
AHP with enlargement of the west bank 
Mississippi River levee from Fort Jackson to 
Venice. 
Estimated cost of new work (July 1975) is 
$85,400,000 Federal and $36,600,000 non- 
Federal, including $28,050,000 cash 
contributions or equivalent work. 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction and 
future maintenance; provide alterations to 
facilities, and maintain and operate project after 
completion; prevent any encroachment on 
ponding areas unless substitute storage capacity 
or equivalent pumping capacity is provided 
11-32

NEW ORLEANS, LA., DISTRICT 
promptly without cost to the United States; 
contribute in cash or equivalent work not less 
than 30 percent of total project cost; and hold and 
save the United States free from damages. 
Assuring Agency: Plaquemines Parish 
Commission Council. All assurances required for 
the project have been furnished. 
Operations and results during fiscal year. New 
work by hired labor: Planning and studies for the 
project continued. 
New work by contract: Construction of a 
control structure at Reach B-1, Empire 
Floodgate continued from last fiscal year and is 
93 percent complete. A contract for Reach B-2, 
first lift, stations 1+52.5 to 248+00 was initiated 
Jul. 31, 1974, and is 25 percent complete. Contract 
work for Reach B-1, first shape-up, stations 
177+00 to 373+68.56 was initiated Jul. 12, 1974, 
and is 94 percent complete. Construction of the 
first-lift levee, Reach B-1, stations 374+90 to 
639+76.70 (not continuous) continued from last 
fiscal year and is 65 percent complete. A contract 
for Reach B-2 first-lift levee, stations 244+00 to 
474+58 was awarded May 7, 1975, but 
construction was not initiated. Contract work for 
Reach B-i, Lower Venice levee extension 
commenced in August 1974 and was completed 
January 1975 with construction of 500 linear feet 
of new levee. 
Condition at end of fiscal year. Construction 
began on the project in September 1968 and it is 
currently estimated that the total project is about 
25 percent complete. First-lift and first shape-up 
work is continuing on Reach B-1. First-lift 
construction is continuing on Reach B-2. The 
Empire floodgate is completed. First-lift and first 
shape-up have been completed on Reach C by 
local interests, and construction of the second-lift 
may be initiated during Fiscal Year 1976. Initial 
construction of the east bank barrier section 
should be possible by Fiscal Year 1976 and initial 
construction on Reach A is expected by Fiscal 
Year 1978. 
44. MORGAN CITY AND VICINITY, LA. 
(HURRICANE PROTECTION) 
Location. In south-central Louisiana, Morgan 
City proper, and the adjacent areas. It includes 
the land south of Grand Lake, Six Mile Lake, and 
Lake Palourde extending from Morgan City 
westward to Charenton drainage and navigation 
canal. Lower Atchafalaya River and Wax Lake 
Outlet, the principal outlets for Atchafalaya 
Basin Floodway, traverse the area. Gulf 
Intracoastal Waterway crosses the area in an 
east-west direction. Numerous bayous and 
artificial canals excavated for drainage purposes 
or for access to oil developments exist throughout 
the area. (See Engineer quadrangles Bayou Sale, 
Jeanerette, Foster, Belle Isle, Point Au Fer, 
Morgan City, and Lake Decade; and Coast and 
Geodetic Survey Chart 1116.) 
Existing project. Morgan City: Construction of 
about 5.6 miles of new levees along shore of Lake 
Palourde and west bank of Bayou Ramos and 
about 0.5 mile of new levee from Southern Pacific 
railroad embankment near Wyandotte to tie in 
with Bayou Boeuf lock levee, and construction of 
three gravity drainage structures. 
Franklin and vicinity: Enlargement of about 
21.4 miles of back levee and construction of about 
3.5 miles of new levees to effect a complete closure 
of area to be protected, construction of one 
floodgate and eight gravity drainage structures, 
and alteration of existing drainage facilities 
where necessary. Normal range of tide is 1.6 feet. 
Storm and hurricane tide have produced 
elevations up to 10 feet while northerly storms 
during winter depress the gulf level as much as 3 
feet below mean sea level. During low water 
periods on Atchafalaya River, generally 
September through November, the effect of tide 
extends about 35 miles above Morgan City. 
Estimated cost for new work (July 1975) is 
$7,940,000 Federal and $3,560,000 non-Federal, 
including $670,000 cash contributions. 
Local cooperation. Local interests must furnish 
lands, easements, and rights-of-way for 
construction and future maintenance, provide 
relocations and alterations required for project; 
provide all interior drainage and pumping plants 
required for reclamation and development of 
protected areas; maintain and operate all project 
works after completion, provide assurances that 
encroachment on existing ponding areas will be 
prevented unless substitute storage capacity or 
equivalent pumping capacity is provided 
promptly, without cost to the United States; 
contribute in cash or equivalent work not less 
than 30 percent of project cost, the final 
determination to be made after construction is 
complete; and hold and save the United States 
free from damages due to construction works. 
Assuring Agency: St. Mary Parish Police Jury. 
Basic assurances for the project have been 
furnished. Assuring agency has not executed 
required amended assurance containing the 
provisions of Public Law 91-646 and Sec. 221 of 
Public Law 91-611 because of lack of funds with 
which to comply. Louisiana Department of Works 
has been requested to assist. 
Operations and results during fiscal year. 
General engineering only was accomplished by 
hired labor forces during the fiscal year. 
Preparation of the GDM for the Morgan City area 
remains approximately 70 percent complete, 
with no work accomplished during the fiscal year 
because of lack of local support. 
11-33

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Condition at end offiscal year. Construction has 
not commenced. 
45. RED RIVER BELOW DENISON DAM 
(NEW ORLEANS DIST.) 
Location. On Red River and its tributaries 
below Denison Dam, in Oklahoma, Arkansas, 
Texas, and Louisiana: (See Geological Survey 
State maps and folio "Maps of Red River"-1958 
edition.) 
Existing project. Flood Control Act of 1946 
approved general plan for flood control on Red 
River below Denison Dam, Tex. and Okla., which 
provides for construction of six flood control 
reservoirs in combination with existing or 
authorized Federal and non-Federal levee 
improvements, modified as required, and 
channel stabilization at locations where levee 
setbacks are impossible or uneconomical. This act 
further authorized incorporation of several 
separate existing projects for flood control along 
Red River below Denison, above jurisdiction of 
Mississippi River Commission, into this project. 
By Public Law 780, 83d Cong., 2d sess., as 
amended by Public Law 218, 84th Cong., 1st sess., 
and Public Law 645, 86th Cong., 1st sess., plan of 
improvement was amended to include additional 
projects as indicated in following lists of 
reservoirs and local protection works considered 
in general flood control plan for the Red River 
below Denison Dam, and existing flood control 
projects incorporated into project in New Orleans 
District. (See Table 11-H for new projects and 
Table 11-I for incorporated projects.) 
Local cooperation. See individual reports 
herein. 
46. RED RIVER BELOW DENISON DAM, 
LEVEES AND BANK STABILIZATION 
(NEW ORLEANS DIST.) 
Location. Along the main stem of the Red River 
from the head of the levee system immediately 
above Index, Ark., through the southwest corner 
of Arkansas to the vicinity of Boyce, La., on the 
right bank, and Pineville, La., on the left bank. 
Existing project. Raising and strengthening 
existing and authorized Red River levees to 
provide protection against flooding and bank 
protection works at locations where levee 
setbacks are impossible or uneconomical. The 
plan consists of raising and strengthening 
existing and authorized Red River levees to 
provide against a flood approximately 20 percent 
greater than the flood of 1945, the flood of record, 
as modified by authorized reservoirs. Bank 
protection works are to be constructed at 
locations where levee setbacks are impossible or 
uneconomical. Estimated cost for new work (July 
1975) is $48,700,000 Federal and $360,000 non- 
Federal, including $100,000 contributed funds. 
Local cooperation. Local interests must furnish 
lands, easements, rights-of-way, and spoil 
disposal areas necessary for construction; hold 
and save the United States free from damages; 
and maintain and operate works after 
completion. Local interests have been prompt in 
furnishing levee rights-of-way upon request, 
except for the following three items of low 
priority: McKinney Bayou Drainage District, 
enlargement of approximately 4 miles of 
intermittently low levee; Garland Levee District, 
enlargement of approximately 1.3 miles of levee; 
and Red River Levee District No. 1, enlargement 
of approximately 4.3 miles of levee. The local 
agencies are convinced that the flow line lowering 
produced by completed reservoirs has made this 
work unnecessary. 
Assuring Agencies: Red River-Bayou Pierre 
Levee and Drainage District, North Bossier 
Levee District, Red River Water Commission, 
Bossier Levee District, Caddo Levee District, 
Cane River Levee and Drainage District, 
Garland Levee District, Hempstead County 
Levee District No. 1, Miller County Levee 
District No. 2, Red River Levee District No. 1, 
Nineteenth Louisiana Levee District, and Long 
Prairie Levee District. All basic assurances 
received. Supplemental assurances covering 
Public Law 91-646 have been received from all 
agencies. 
Operations and results during fiscal year. 
Hired labor forces continued investigations, 
surveys, and preparation of plans and 
specifications. 
Stone trenchfill revetment work was 
completed this fiscal year at the following 
locations: Halfmoon, Ark., mile 328.5 (1967 
mileage) with 6,000 linear feet of bank protected; 
Benton, La., mile 297.0 (1967 mileage) with 3,600 
linear feet of bank protected; Williams, La., mile 
241.0 (1967 mileage) with 6,400 linear feet of 
bank protected; Douglas Island Bend, La., mile 
278.4 (1967 mileage) with 1,250 linear feet of 
bank protected. A contract for Cupples 
reinforcement and levee setback was initiated 
Jan. 20 and completed Apr. 24, 1975, with 
construction of 1,800 linear feet of levee setback 
and 1,200 feet of trenchfill revetment. 
Construction of stone trenchfill revetment 
continued from last fiscal year at Harmon, La., 
and is 91 percent complete. Construction 
commenced Jul. 9, 1975, for stone trenchfill 
revetment work at Oak, Ark., mile 247.4 (1967 
mileage) and is 95 percent complete. Three 
contracts were awarded this fiscal year as 
follows: Construction of stone trenchfill 
revetment at Bourbeaux, La., mile 155.7 (1967 
mileage) commenced Feb. 28, 1975, and is 69 
11-34

NEW ORLEANS, LA., DISTRICT 
percent complete; construction of stone trenchfill 
revetment on the right descending bank at 
Cadoche, La., commenced Apr. 15, 1975, and 
is 8 percent complete, and construction pile 
and stone trenchfill revetment at Fulton, Ark., 
mile 401.0-L (1967 mileage), commenced 
Jun. 25, 1975, with preliminary work 
only accomplished. 
Condition at end of fiscal year. Construction 
was initiated in February 1948 and is 56 percent 
complete, with approximately 149 miles of left 
bank and 235 miles of right bank levees 
improved. About 36.8 miles of banks are 
protected with stone and pile dikes, standard 
board, riprap trench-fill revetments, and four 
cutoffs. 
47. WALLACE LAKE, LA. 
Location. In Red River Basin on Cypress 
Bayou, Caddo and De Soto Parishes, La., 66 miles 
above mouth of Bayou Pierre and about 14 miles 
southeast of Shreveport, La. (See Geological 
Survey State map, scale 1:500,000.) 
Existing project. An earth-fill dam 4,940 feet 
long at top, including 644 feet of spillway and 
outlet works, rising 48 feet above streambed, with 
a reservoir providing storage of 96,100 acre-feet, 
including a conservation pool of 7,800 acre-feet. 
Outlet works and uncontrolled spillway are 
centered about 1,250 feet north of south 
abutment. Reservoir controls 260 square miles, or 
about 20 percent of total drainage area of Bayou 
Pierre, Cypress Bayou, and tributaries 
combined, and affords protection against floods 
for an area of about 90,000 acres of valley below 
dam. Cost for new work completed in 1946 was 
$1,219,371, including $17,164 for Code 711. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Hired labor continued operation and ordinary 
maintenance of the dam. (See Table 11-G for 
reservoir operations.) 
Condition at end of fiscal year. All construction 
work on project was completed in December 
1946. 
Main portion of dam was constructed during 
Fiscal Year 1943; stabilization of railroad 
embankment was accomplished from June to 
November 1946; and placing of fill in closure 
section of dam was accomplished from November 
to December 1946. Recreational facilities at the 
lake were closed in May 1972. 
48. WRIGHT PATMAN DAM AND LAKE, 
TEX. 
Location. On Sulphur River in Cass and Bowie 
Counties, Tex. Dam is 45 miles above mouth of 
Sulphur River, and about 8 miles southwest of 
Texarkana, Tex. 
Existing project. An earth-fill dam 18,500 feet 
long and 100 feet high, including a spillway 200 
feet wide and outlet works with a capacity of 
27,600 cubic feet per second. Reservoir controls 
runoff from 3,400 square miles of drainage area, 
and has a storage capacity of 2,654,300 acre-feet, 
of which 145,300 acre-feet are for conservation 
and remainder of flood control. Estimated cost 
for new work (July 1975) is $48,310,000 which 
includes $4,610,061 Code 711, $399,939 
accelerated public works funds, and $11,338,004 
to be reimbursed by local interests, over a period 
not to exceed 50 years, for water supply storage, 
and including $1,997,604 for pro rata share of 
original reservoir cost. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work by hired labor consisted of preparation 
of plans and specifications for metal guard 
fence. 
Maintenance by hired labor consisted of 
operation and maintenance of dam and reservoir 
area. 
New work by contract: A contract for 
construction of a metal beam guard fence and 
other incidental work commenced Apr. 7, 1975, 
and is 95 percent complete. 
Maintenance by contract: A contract for 
bituminous surfacing of roadways, trailer 
campsites, and parking areas continued from 
prior fiscal year and was completed Aug. 23, 
1974. 
Number of visitor-days of recreational use, 
2,447,000 (calendar year 1974). 
Condition at end of fiscal year. Construction 
was initiated in August 1948 and completed in 
March 1962, except real estate activities, 
construction under Code 711, and conversion of 
120,000 acre-feet to water supply storage after 
completion of Cooper Reservoir. 
49. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed flood control projects 
along the Red River from the northern boundary 
of the District to Alexandria, La., was included in 
the joint annual inspection with local interests 
during the months of September and October 
1974. Flood-fight sectors included in this area are 
the Arkansas, Shreveport, and Middle Red which 
contain a total of 438 miles of levee. The Sulphur 
River sector which contains numerous relatively 
short and discontinuous levees along the Sulphur 
River was inspected in October by the Area 
Engineer. In addition, spot inspections of these 
11-35

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
projects were made at various times during the 
year on an as-needed basis. 
Fiscal year costs were $44,227. Total costs to 
Jun. 30, 1975, were $237,264. 
50. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 11-J. 
51. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 11-K. 
General Investigations 
52. SURVEYS 
Cost of work during fiscal year was $1,892,000, 
of which $166,000 was for seven navigation 
studies, $1,726,000 for seven flood control 
studies. 
53. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain information studies as authorized 
by Sec. 206, 1960 Flood Control Act, as amended, 
comprise compilation and dissemination, upon 
the request of a state or a political subdivision 
thereof, of information on floods and flood 
damages, including identification of areas 
subject to inundation by floods of various 
magnitudes and frequencies, and general criteria 
for guidance of Federal and non-Federal 
interests and agencies in the use of flood plain 
areas; and provide advice to other Federal 
agencies and local interests for their use in 
planning to ameliorate the flood hazard. Fiscal 
year costs were $89,907 for flood plain management 
services, $27,684 for technical services, 
and $126,250 for flood plain information reports. 
54. RESEARCH AND DEVELOPMENT 
Hydrological studies were made during the 
fiscal year at a cost of $4,778. 
11-36

NEW ORLEANS, LA., DISTRICT 
TABLE 11-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
1. Aquatic Plant 
Control Program, 
La. 
2. Atchafalaya 
River, Bayous 
Chene, Boeuf, 
and Black, La. 
3. Atchafalaya 
River, Morgan 
City to Gulf of 
Mexico, La. 
4. Barataria Bay 
Waterway, La. 
5. Bayou Lafourche 
and Lafourche- 
Jump Waterway, 
La. 
6. Bayou Teche & 
Vermilion 
River, La. 
7. Bayou Teche, 
La. 
New Work 
Approp. $ 381,700 $ 299,700 $ 443,700 $ 350,000 $ 6,215,9001 
Cost 334,626 298,667 331,256 291,107 5,988,9632 
New Work 
Approp. 873,000 1,130,000 2,800,000 1,075,000 5,998,000 
Cost 61,947 55,809 2,119,133 3,261,400 5,580,9413 
New Work 
Approp. - - - - 501,963 
Cost - - - - 501,963 
Maint. 
Approp. 612,100 481,600 2,075,000 419,350 8,236,234 
Cost 445,209 651,835 2,091,972 433,789 8,236,141 
New Work 
Approp. - - - - 1,572,6854 
Cost - - - - 1,572,6854 
Maint. 
Approp. 514,900 277,000 1,078,338 
Cost 496,402 293,346 1,023,541 
New Work 
Approp. 53,000 -100,000 10,000 
Cost 17,473 35,942 52,860 
Maint. 
Approp. 31,000 -1,807 - 
Cost 35,929 183 - 
New Work 
Approp. - - - 
Cost - - - 
Maint. 
Approp. 54,800 50,600 120,500 
Cost 55,630 37,106 117,265 
New Work 
Approp. - - - 
Cost - - - 
Maint. 
Approp. 93,000 71,200 113,600 
Cost 72,079 84,938 122,766 
50,000 3,797,6365 
110,989 3,797,6285 
50,000 1,640,0246 
34,353 1,568,7666 
- 829,7567 
- 829,7567 
- 2,891,222 
- 2,891,222 
103,000 1,101,354 
110,325 1,086,719 
- 754,3308 
- 754,3308 
60,000 2,529,3759 
61,072 2,521,3869 
8. Calcasieu River New Work 
and Pass, La. Approp. - - - - 27,807,31010 
Cost - - - - 27,807,310 
' 0 
Maint. 
Approp. 3,950,100 4,500,300 360,200 2,605,000 26,911,96911 
Cost 2,538,032 5,890,467 363,194 2,588,815 26,873,06511 
9. Calcasieu River New Work 
at Coon Island, La. Approp. 26,289 903,500 - - 959,889 
(Regular Funds) Cost 16,041 15,121 876,421 9,427 946,32712 
(Contrib. Funds) New Work 
Contrib. - - 70,900 -4,900 66,000 
Cost - - 70,900 -4,900 66,000 
10. Calcasieu River New Work 
at Devil's El- Approp. 20,000 130,000 -12,000 200,000 338,000 
bow, La. Cost 19,325 52,226 32,441 25,608 129,600 
11. Freshwater New Work 
Bayou, La. Approp. - - - - 7,116,22413 
Cost - - - - 7,116,22413 
Maint. 
Approp. 534,950 452,100 500,000 604,000 3,008,750 
Cost 294,744 693,780 349,061 731,422 2,985,160 
11-37

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
12. Gulf Intracoastal 
Waterway 
between 
Apalachee Bay, 
Fla., & Mexican 
Border (New 
Orleans Dist.) 
New Work 
Approp. 
Cost 
84,400 -37,000 200,000 100,000 63,096,92514,5,16,'7 
24,905 46,181 105,524 184,331 63,049,10414,15,16,17 
Maint. 
Approp. 4,165,019 3,965,900 5,380,700 5,440,650 76,106,40618,20 
Cost 3,679,687 4,269,457 4,554,782 6,037,261 75,443,99619,20 
13. Houma Naviga- Maint. 
tion Canal, La. Approp. 552,900 741,700 1,339,500 435,000 4,924,734 
Cost 298,052 618,063 1,228,544 932,384 4,924,718 
14. Mermentau River, New Work 
Bayou Nezpique, Approp. 1,993,000 1,930,000 700,000 2,034,000 6,920,55521 
and Bayou Des Cost 88,707 1,175,439 2,027,678 935,054 4,470,10721 
Cannes, La. 
15. Mermentau River, 
La. 
16. Mississippi 
River, Baton 
Rouge to the 
Gulf of 
Mexico, La. 
17. Mississippi 
River-Gulf 
Outlet, La. 
(Regular Funds) 
Maint. 
Approp. 
Cost 
New Work 
- 114,51922 
- 114,51922 
Approp. - - - - 4,631,91023 
Cost - - - - 4,631,91023 
Maint. 
Approp. 479,200 488,100 711,700 470,000 6,428,16224 
Cost 421,647 521,496 723,634 456,788 6,387,70124 
New Work 
Approp. - - - - 34,916,99725 
Cost - - - - 34,916,99725 
Maint. 
Approp. 6,287,300 8,683,900 21,957,644 19,747,800 145,568,30226,28 
Cost 5,733,180 8,914,014 21,710,647 19,487,142 144,480,52827,28 
New Work 
Approp. 794,000 900,000 580,000 1,000,000 68,070,000 
Cost 977,891 851,238 668,982 877,651 67,696,802 
Maint. 
Approp. 2,826,803 1,809,800 2,534,100 1,940,000 30,843,489 
Cost 1,855,696 2,626,817 1,347,034 3,287,071 30,824,293 
(Contrib. Funds) New Work 
Contrib. 436,000 - - - 1,118,97729 
Cost 218,318 217,682 - - 1,118,97729 
18. Mississippi New Work 
River-Gulf Approp. 149,000 -69,000 1,380,000 1,060,000 2,570,000 
Outlet, Michoud Cost 35,945 48,415 491,448 1,863,993 2,476,86130 
Canal, La. 
19. Mississippi New Work 
River Outlets, Approp. 99,000 90,000 5,000 60,000 304,000 
Venice, La. Cost 91,407 44,499 66,617 33,762 275,655 
20. Overton-Red River New Work 
Waterway, La. Approp. 1,315,000 1,000,000 720,000 1,800,000 7,472,522 
Cost 1,077,163 1,307,729 765,661 1,545,088 7,043,015 
21. Petit Anse, New Work 
Tigre & Carlin Approp. - - - - 392,24731 
Bayous, La. Cost - - - - 392,24731 
Maint. 
Approp. 
Cost 
17,000 582,053 
16,999 582,052 
11-38

NEW ORLEANS, LA., DISTRICT 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
22. Red River below New Work 
Fulton, Ark. Approp. - - - - 
Cost - - - - 
Maint. 
Approp. 32,500 10,300 14,000 10,000 
Cost 22,642 21,329 12,094 8,830 
23. Red River New Work 
Emergency Bank Approp. 1,933,100 5,949,900 1,920,000 4,480,000 
Protection Cost 301,827 1,375,424 5,250,325 6,037,588 
24. Red River New Work 
Waterway- Approp. 913,000 1,600,000 5,860,000 10,000,000 
Mississippi Cost 881,018 1,351,681 2,896,567 6,974,191 
River to Shreveport, 
La. 
25. Red River New Work 
Waterway- Approp. - - 70,000 - 
Shreveport, La. Cost - - 812 61,553 
to Daingerfield, 
Tex. 
26. Removing Water- Maint. 
Hyacinth, La. Approp. 433,300 429,200 435,000 555,000 
Cost 435,272 429,200 433;313 524,980 
27. Waterway from New Work 
Empire, La., to Approp. - - - - 
Gulf of Mexico Cost - - - - 
Maint. 
Approp. 
Cost 
28. Waterway from New Work 
Intracoastal Approp. 
Waterway to Cost 
Bayou Dulac, La. 
(Bayou Grand 
Caillou & LeCarpe, 
La.) 
31. Bayou Bodcau 
and tributaries, 
Ark. & La. 
32. Bayou Bodcau 
Reservoir, La. 
19,822 
20,104 
Maint. 
Approp. 103,038 
Cost 103,038 
New Work 
Approp. 258,000 
Cost 15,151 
New Work 
Approp. -23 
Cost 1,990 
3,200 
2,689 
3,000 
3,206 
1,963,80632 
1,963,80632 
2,092,508 
2,089,005 
16,183,000 
13,101,782 
18,373,000 
12,133,457 
70,000 
62,365 
10,408,608 
10,376,901 
1,068,142 
1,068,142 
561,106 
305 561,106 
129,622 
129,622 
- - 20,000 175,352 
- - 13,414 168,766 
-250,000 820,000 -200,000 1,067,000 
45,754 154,936 355,847 899,373 
- - - 4,208,41733 
- - - 4,208,41733 
Maint. 
Approp. 
Cost 
33. Bayou Pierre, La. New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
92,800 
94,295 
26,400 
23,601 
34. Brush Bayou, La. New Work 
Approp. - 
Cost 7,278 
35. Caddo Lake, La. New Work 
Approp. 100,200 
Cost 221,192 
88,100 72,200 125,000 
67,089 77,295 148,828 
14,600 1 
16,664 1 
- 1( 
2,255 
-5,900 
90,562 
10,000 
12,618 
10,000 
8,199 
971,907 
970,229 
299,52934 
299,52934 
437,210 
435,409 
)0,000 - 180,500 
51,144 32,436 164,08035 
7,478 66,000 3,587,778 
9,414 14,834 3,509,611 
11-39

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
36. Choctaw Bayou and New Work 
tributaries, La. Approp. -3,000 101,000 250,000 -105,000 785,000 
(Regular Funds) Cost 3,608 53,298 518,163 64,749 732,90636 
(Contrib. Funds) New Work 
Contrib. - - 210,594 - 210,594 
Cost - - - 138,632 138,632 
37. Cooper Lake and New Work 
Channels, Tex. Approp. 1,451,000 1,800,000 1,920,000 2,200,000 14,470,000 
Cost 1,583,334 1,701,463 1,987,740 2,084,347 14,109,774 
38. Ferrells Bridge New Work 
Dam-Lake 0' the Approp. 103,800 188,863 -1,637 230,863 13,953,55337 
Pines, Tex. Cost 25,178 242,152 43,026 35,857 13,751,68838,39 
Maint. 
Approp. 434,400 446,400 478,500 515,500 4,652,067 
Cost 401,931 434,035 455,371 559,507 4,604,855 
39. Garland City, New Work 
Ark. Approp. - - - - 1,340,000 
Cost 7,269 - 121,227 54,675 1,335,842 
40. Harvey Canal, New Work 
Bayou Barataria Approp. 3,000 - - - 1,000,002 
Levee, La. Cost 488,354 396,241 34,574 7,036 988,111 
(Regular Funds) 
(Contrib. Funds) New Work 
Contrib. 440,460 - 2,750 - 443,210 
Cost 10,619 212,050 189,595 - 412,264 
41. Lake Pontchar- New Work 
train and vicinity, Approp. 13,946,000 14,840,000 2,660,000 -2,080,000 58,159,000 
La. (Hurricane Cost 10,670,775 8,380,165 7,012,290 8,888,575 57,664,904 
Protection) (Regular 
Funds) 
(Contrib. Funds) New Work 
Contrib. - 1,150,000 - - 1,650,000 
Cost - 1,150,000 - - 1,650,000 
42. Larose to Golden New Work 
Meadow, La. Approp. 99,000 280,000 505,000 1,200,000 2,492,000 
(Hurricane Cost 77,570 74,030 112,490 1,239,348 1,843,61440 
Protection) 
43. Mississippi New Work 
River Delta at Approp. 3,406,000 4,675,000 6,600,000 2,200,000 22,535,000 
and below New Cost 2,507,637 1,712,671 3,369,611 7,771,915 21,011,151 
Orleans, La. (New Orleans 
to Venice, La., 
Hurricane Protection) 
(Regular 
Funds) 
(Contrib. Funds) New Work 
Contrib. - - - - 366,430 
Cost 15,625 - - - 279,861 
44. Morgan City and New Work 
vicinity, La. Approp. 397,000 160,000 335,000 -1,146,000 593,000 
(Hurricane Cost 60,927 36,953 45,853 20,460 548,1634 
Protection) 
46. Red River below New Work 
Denison Dam, Approp. 1,999,000 3,220,000 3,240,000 2,880,000 28,210,00042 
Levees and Bank Cost 3,198,098 2,945,600 1,999,830 4,163,354 27,206,80142 
Stabilization (New 
Orleans Dist.) 
11-40

NEW ORLEANS DISTRICT, LA. 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
47. Wallace Lake, La. New Work 
Approp. - - - - 1,219,37143 
Cost - - - 1,219,37143 
Maint. 
Approp. 53,300 53,400 41,400 94,000 621,300 
Cost 47,425 50,359 43,257 86,285 606,526 
48. Wright Patman New Work 
Dam and Lake, Approp. 34,823 61,000 12,000 - 35,191,86644 
Tex. Cost 27,850 69,103 39,844 795 35,186,19545 
Maint. 
Approp. 519,200 522,000 612,000 937,600 6,396,140 
Cost 482,308 558,876 538,088 962,170 6,311,649 
1. Includes $1,935,100 for Code 740. 
2. Includes $1,711,223 for Code 740. 
3. Includes $37,348 for advance engineering and design. 
4. Includes $73,037 for previous project. Excludes $2,000 
contributed funds expended. 
5. Includes $47,551 for previous project. 
6. Includes $252,935 for previous projects; excludes 
$75,563 expended for rehabilitation (Code 820) in Fiscal Year 
1961.
7. Includes $15,445 for previous projects. 
8. Includes $45,704 for previous projects. 
9. Includes $91,389 permanent indefinite appropriation. 
10. Includes $495,914 for previous project; excludes 
$107,837 expended for minor rehabilitation in Fiscal Year 
1963. 
11. Includes $194,851 for previous project. 
12. Includes $56,400 for preauthorization studies. 
13. Excludes $16,060 contributed funds. 
14. AE&D funds for replacement of Vermilion lock. 
15. Includes $4,320,698 for new work on previous project. 
Included in these totals are $353,541 N.I.R.A. funds (new 
work); and $1,070,433 permanent indefinite appropriation. 
Included is repayment of advance funds for construction of 
Franklin Canal in the amount of $35,103. In addition, 
$1,413,133 was expended for transfer to drainage district of 
ownership of Plaquemines Parish pumping station, and 
drainage canals and all drainage responsibility and 
obligations vested in the United States by Public Law 14, 79th 
Cong., 1st sess. 
16. Excludes contributed funds of $340,159. 
17. Inner Harbor Navigation Canal Lock was constructed 
at a cost of $8,648,492 (non-Federal). 
18. Does not include allotment of $60,000 (9613123). 
19. Does not include expenditures of $36,630 (9613123). 
20. Includes $454,259 for maintenance and $548,948 for 
operation and care for previous project, including $75,000 
from appropriation for maintenance and operation of dam 
and other improvements of navigable waters. Excludes 
$7,005 contributed funds. 
21. Includes $57,555 ($29,974 of which was from Public 
Works funds) for new work on previous project. 
22. Includes $114,519 for maintenance of previous project. 
23. Excludes $10,904 for new work on White Lake to 
Pecan Island section of existing project. 
24. Excludes $10,742 for maintenance on White Lake to 
Pecan Island section of existing project. Excludes $2,000 
contributed funds. Includes $13,163 of R&H funds and 
$109,714 accelerated Public Works Act funds. 
25. Includes $1,729,989 for previous project. 
26. Does not include allotment of $40,000 (9613123). 
27. Does not include expenditures of $63,370 (9613123). 
28. Includes $169,055 for previous projects and $3,379,676 
from permanent indefinite appropriation. 
29. Contributed by Board of Commissioners, Port of New 
Orleans, for providing fill for future industrial sites adjacent 
to turning basin and for dredging cable and pipeline 
crossings. 
30. Includes $12,940 for advance engineering and design. 
31. Includes $47,858 accelerated Public Works Act funds. 
32. Includes $1,553,878 for previous projects. 
33. Includes $109,677 for Code 711. 
34. Includes $38,529 from emergency relief funds. 
35. Includes $80,500 for preauthorization studies. 
36. Includes $72,000 for preauthorization studies. 
37. Includes $1,207,486 for Code 711 and $399,739 
accelerated Public Works Act funds. Excludes $1,711,200 
contributed funds. 
38. Includes $1,005,621 for Code 711, and $399,739 
accelerated Public Works Act funds, excludes $4,137 
reimbursed in Fiscal Year 1973. 
39. Claim Northeast Texas Municipal Water District 
$16,546. Three payments of $12,410 less real estate charges of 
$1,325, making a total of $2,811 reimbursed in Fiscal Year 
1972, Fiscal Year 1973, and Fiscal Year 1974. 
40. Includes $67,823 for advance engineering and design. 
41. Includes $31,222 advance engineering and design. 
42. Includes $212,105 expended by Tulsa District for cost 
of Index, Ark., Tex. unit. Excludes $100,000 contributed 
funds expended. 
43. Includes $17,164 for Code 711. 
44. Includes $802,573 for Code 711 and $399,939 
accelerated Public Works Act funds. 
45. Includes $796,903 for Code 711, and $399,939 
accelerated Public Works Act funds. 
11-41

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Aug. 13, 1968 
Water Resources 
Development 
Act, Mar. 7, 
1974 
Jun. 25, 1910 
Jul. 3, 1958 
Aug. 30, 1935 
Jul. 14, 1960 
Nov. 22, 1967 
AQUATIC PLANT CONTROL PROGRAM, LA. 
(See Sec. 1 of Text) 
Control and progressive eradication of water-hyacinth, 
alligatorweed, and other obnoxious aquatic plant growth 
from navigable waters in tributary streams, connecting 
channels, and other allied waters in southeastern United 
States. 
Research and planning costs prior to construction to be 
borne fully by the United States and not included in 
costs shared by local interests. 
Provides for comprehensive program for control and progressive 
eradication of water-hyacinth, alligatorweed, 
Eurasian water milfoil, and other obnoxious plant growths 
from navigable waterways, tributary streams, connecting 
channels, and other allied waters of the United States. 
ATCHAFALAYA RIVER, BAYOUS CHENE, BOEUF, 
AND BLACK, LA. (See Sec. 2 of Text) 
20- by 400-foot navigation channels connecting Gulf Intracoastal 
Waterway, Gulf of Mexico, and Bayous Chene, 
Boeuf, and Black. 
The non-Federal interests shall contribute 25 percentum 
of the costs of areas required for initial and subsequent 
disposal of spoil, and of necessary retaining dikes, 
bulkheads, and embankments therefor. This requirement 
shall be waived if applicable waste treatment 
facilities are constructed and water quality standards are 
not being violated. 
ATCHAFALAYA RIVER, MORGAN CITY TO GULF 
OF MEXICO, LA. (See Sec. 3 of Text) 
A 20- by 200-foot channel from 20-foot contour in Gulf 
of Mexico. 
BARATARIA BAY WATERWAY, LA. (See Sec. 4 
of Text) 
A channel about 37 miles long with a 12-foot depth and 
125-foot width from Gulf Intracoastal Waterway to Grand 
Isle, La., to mile 15.5 in Bayou St. Denis; a channel along 
western shore of Barataria Bay and through Barataria 
Pass to 12-foot depth contour in the gulf, with an extension 
of project to include westerly 4.3 miles of Bayou Rigaud. 
BAYOU LAFOURCHE AND LAFOURCHE-JUMP 
WATERWAY, LA. (See Sec. 5 of Text) 
Permanent closure of head of bayou, without a lock; a 
channel 6 feet deep and 60 feet wide from Gulf Intracoastal 
Waterway at Larose to Gulf of Mexico by Belle Pass; 
closure of Pass Fourchon; and a jettied entrance at mouth of Bell 
Pass. 
Auxiliary channel 12 by 125 feet from Gulf Intracoastal 
Waterway (mile 37.2) to Bayou Lafourche vicinity Leeville 
12- by 125-foot channel improvement in Bayou Lafourche 
from Leeville to 12-foot contour in Gulf of Mexico; 9- by 
100-foot channel improvement in Bayou Lafourche from 
Leeville to Golden Meadow; 12- by 125-foot channel from 
Leeville through Southwestern Louisiana Canal to and 
through Bayou Rigaud; and restore and extend jetties from 
6- to 12-foot contour when justified to effect reduction in maintenance 
dredging. 
Bayou Lafourche, between Canal Boulevard in Thibodaux, 
Lafourche Parish, La., and the head of the bayou at its 
junction with the Mississippi River levee at Donaldsonville, 
Ascension Parish, La., is declared nonnavigable. 
H. Doc. 37, 85th Cong., 
1st sess. 
Public Law 874, 87th Cong., 
2d sess. 
Public Law 298, 89th Cong., 
2d sess. 
H. Doc. 155, 90th Cong., 
1st sess. 
Public Law 93-251, Sec. 58, 
93d Cong., 2d sess. 
H. Doc. 669, 61st Cong., 
2d sess.' 
H. Doc. 82, 85th Cong., 
1st sess. 
H. Doc. 45, 73d Cong., 
1st sess. 
H. Doc. 112, 86th Cong., 
1st sess.2 
Public Law 90-149. 
11-42

TABLE 11-B 
(Continued) 
NEW ORLEANS, LA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 18, 1941 
Sep. 19, 1890 
Mar. 2, 1907 
Mar. 2, 1919 
Jun. 26, 19343 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 24, 1946 
Jul. 14, 1960 
Jul. 14, 1960 
Adopted by Committee 
Resolutions 
Dec. 15, 1970, and 
Dec. 17, 19705 
BAYOU TECHE AND VERMILION RIVER, LA. 
(See Sec. 6 of Text) 
A navigable channel 51 miles long and 8 by 80 feet from 
8-foot-depth contour in Vermilion Bay to Gulf Intracoastal 
Waterway, thence 9 by 100 feet to head of navigation (mile 
52) at Lafayette, La., with additional enlargement below 
Abbeville necessary to provide adequate capacity for 
flood flows. 
BAYOU TECHE, LA. (See Sec. 7 of Text) 
Improve stream from its mouth to St. Martinville by removing 
obstructions and dredging. 
Construct lock and dam and extend improvement to Arnaudville, 
La. 
Increase channel dimensions from mouth to Keystone Lock. 
Operation and care of lock and dam provided for with funds 
from War Department appropriations for rivers and 
harbors. 
CALCASIEU RIVER AND PASS, LA. (See Sec. 8 of Text) 
Channel 30 by 250 feet from Lake Charles docks to gulf, 
repair and extend existing jetties to about 10-foot-depth 
contour, with a channel 30 by 250 feet between jetties; dredging 
approach channel 32 by 400 feet in gulf from sea ends of 
jetties to 32-foot-depth contour; and provision for extension 
of jetties to 15-foot-depth contour, if such action would 
be more economical than maintenance of approach channel 
by dredging. 
Channel 30 by 250 feet around Clooney Island. 
Channel depth of 35 feet from wharves of Lake Charles 
Harbor and terminal district, including Clooney Island Loop, 
to jetty channel, a uniformly increasing depth of 35 to 
37 feet in jetty channel, and a depth of 37 feet in approach 
channel in Gulf of Mexico. 
An approach channel 42 by 800 feet from end of jetty to 
42-foot contour in gulf; a jetty channel 400 feet wide, 
varying from 40 feet deep at shoreline to 42 feet deep at 
seaward end of jetty; a channel 40 by 400 feet from shoreline 
(mile 0) to Port of Lake Charles (mile 34.4); enlarge 
existing turning basin at mile 29.6 to 40 feet deep; a 
mooring basin (mile 3) 350 by 2,000 by 40 feet; a 35- by 
250-foot extension of existing ship channel from Port of 
Lake Charles (mile 34.4) to vicinity of U. S. Highway 90 
Bridge; a turning basin at upper terminus, 750 by 1,000 by 
35 feet; and maintenance of 12- by 200-foot channel from 
ship channel to Cameron, La. 
CALCASIEU RIVER AT COON ISLAND, LA. (See 
Sec. 9 of Text) 
Enlargement of existing locally constructed ship channel 
and turning basin to provide a 40- by 200-foot channel 
and a 40- by 750- by 1,000-foot turning basin. 
CALCASIEU RIVER AT DEVIL'S ELBOW, LA. (See 
Sec. 10 of Text) 
A channel 40 by 400 feet for 2.8 miles and a turning basin 
at the head 40 by 1,000 feet and 1,000 feet long. 
S. Doc. 93, 77th Cong., 
1st sess. 2 
Annual Report, 1889, 
p. 1532. 
H. Doc. 527, 59th Cong., 
1st sess. 
H. Doc. 1329, 62d Cong., 
3d sess.4 
H. Doc. 299, 75th Cong., 
1st sess. 
H. Doc. 465, 77th Cong., 
1st sess. 
S. Doc. 190, 79th Cong. 
2d sess. 
H. Doc. 436, 86th Cong., 
2d sess. 
Authorized by Chief 
of Engineers, May 3, 1973, 
under Sec. 107 of the 
River and Harbor Act 
of 1960, as amended. 
S. Doc. 111, 91st Cong., 
2d sess.2 
11-43

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 14, 1960 
Mar. 3, 1925 
Jan. 21, 1927 
Jul. 3, 1930 
Jun. 26, 19343 
Jul. 23, 1942 
Mar. 2, 1945 
Jul. 24, 1946 
Jul. 24, 1946 
Jul. 24, 1946 
Oct. 23, 1962 
Mar. 3, 1909 
Oct. 23, 1962 
FRESHWATER BAYOU, LA. (See Sec. 11 of Text) 
A new 12- by 125-foot channel from Gulf Intracoastal Waterway, 
mile 161.2 west of Harvey Lock to 12-foot contour 
in Gulf of Mexico near Freshwater Bayou; construction of an 
84- by 600-foot lock with a depth of 16 feet over sill near 
Gulf of Mexico; and construction of jetties from shoreline 
to 6-foot-depth contour in Gulf of Mexico, if maintenance 
dredging of channel without jetties proves to be more 
expensive than construction and maintenance of jetties. 
Until such determination has been made, offshore channel 
should be dredged and maintained to provide a 12- by 
250-foot channel. In event jetties are provided, offshore 
section should then be maintained to 12- by 125-foot project 
in jettied reach, and 250 feet beyond. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FLA., AND MEXICAN BORDER 
(NEW ORLEANS DISTRICT) (See Sec. 12 of Text) 
Construct waterway from New Orleans, La., to Galveston 
Bay, Tex. 
Extension of waterway to Corpus Christi, Tex. 
A channel 9 by 100 feet from Lake Pontchartrain to 
Mississippi Sound. 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers and 
harbors. 
Enlarge waterway from 9 by 100 feet to 12 by 125 feet from 
Apalachee Bay, Fla., to Corpus Christi, Tex., and its 
extension to vicinity of Mexican border, except between 
Mobile Bay, Ala., and New Orleans, La., where width shall 
be 150 feet; and rental of Inner Harbor Navigation Canal 
facilities. 
Alternative connection with Mississippi River in vicinity 
of Algiers at New Orleans. 
Enlarge and extend Plaquemine-Morgan City route from 
Mississippi-Atchafalaya section of waterway, in vicinity 
of Morgan City, to and through a new terminal lock and 
entrance channel to Mississippi River in vicinity of Port 
Allen, opposite lower limit of Port of Baton Rouge. 
Restore, improve, and maintain Franklin Canal as a terminal 
branch channel, 8 by 60 feet, from its confluence with 
Gulf Intracoastal Waterway to Franklin, La. 
A salt-water guard lock in waterway at mile 238 west of 
Harvey Lock. 
Enlarge waterway to 16 by 150 feet from Mississippi River 
to Atchafalaya River, except in vicinity of Houma 
(mile 50.5 to 63.5); of Houma bypass (mile 50.5 to 63.5) and 
of Algiers alternative canal; and enlarge waterway from 
Atchafalaya River to Sabine River to 16 by 200 feet. 
Replacement of Vermilion Lock. 
HOUMA NAVIGATION CANAL, LA. (See Sec. 13 of Text) 
Assumption of maintenance and operation of Houma Navigation 
Canal, constructed by Terrebonne Parish, to dimensions 
of 15 by 150 feet. 
11-44 
H. Doc. 435, 86th Cong., 
2d sess.2 
H. Doc. 238, 68th Cong., 
1st sess. 
H. Doc. 238, 68th Cong., 
1st sess. 
H. Doc. 341, 71st Cong., 
2d sess. 
H. Doc. 96, 79th Cong., 
1st sess.; H. Doc. 230, 
76th Cong., 1st sess.6 
S. Doc. 188, 78th Cong., 
2d sess. 
S. Doc. 242, 79th Cong., 
2d sess. 
S. Doc. 189, 79th Cong., 
2d sess. 
S. Doc. 231, 79th Cong., 
2d sess. 
H. Doc. 556, 87th Cong., 
2d sess. 
Approved by Secretary 
of the Army, May 16, 
1967. 
H. Doc. 583, 87th Cong., 
2d sess.2

TABLE 11-B 
(Continued) 
NEW ORLEANS, LA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
Aug. 18, 1941 
Jul 24, 1946 
Mar. 2, 1945 
Oct. 23, 1962 
MERMENTAU RIVER, BAYOU NEZPIQUE, AND 
BAYOU DES CANNES, LA. (See Sec. 14 of Text) 
A 12- by 125-foot channel in Mermentau River from Gulf Intracoastal 
Waterway to Lake Arthur; a 12- by 200-foot 
channel through Lake Arthur; a 12- by 125-foot channel from 
upper end of Lake Arthur to junction of the Mermentau River 
and Bayous Nezpique and des Cannes; replacement of existing 
Lake Arthur highway bridge; and enlargement and realinement 
of Bayous Nezpique and des Cannes, to provide a 
12- by 125-foot waterway from Interstate Highway 10 to 
Mermentau River. 
MERMENTAU RIVER, LA. (See Sec. 15 of Text) 
Channel enlargement, lower Mermentau River, from mile 15 
to Gulf of Mexico, and construction of a lock and control 
spillway at Catfish Point, mile 24. 
Channel enlargement; lower Mermentau River below Grand 
Lake, mile 25; construct a gated-control structure at 
or near Grand Cheniere, mile 7; enlarge and realine Inland 
Waterway from Franklin, La., to Mermentau River, La., 
from Vermilion Bay to White Lake, via new channel, and from 
White Lake to Grand Lake; enlarge channel of North Prong 
of Schooner Bayou; construct a gated-control structure in 
new channel near Schooner Bayou lock; and include project 
"Waterway from White Lake to Pecan Island, La.," and portion 
of project "Inland Waterway from Franklin, La., to 
Mermentau River," west of Vermilion Bay in modified project 
"Mermentau River, La." 
MISSISSIPPI RIVER, BATON ROUGE TO GULF OF 
MEXICO, LA. (See Sec. 16 of Text) 
Combines projects of Mississippi River, Baton Rouge to New 
Orleans, Mississippi River, South Pass, and Southwest 
Pass, adding thereto project for Mississippi River from 
New Orleans to Head of Passes, to provide a single project, 
"Mississippi River, Baton Rouge to the Gulf of Mexico," 
with channel dimensions as follows: Baton Rouge to New 
Orleans, 35 by 500 feet; port limits of New Orleans, 35 by 
1,500 feet; New Orleans to Head of Passes, 40 by 1,000 
feet; Southwest Pass, 40 by 800 feet; Southwest Pass 
Bar Channel, 40 by 600 feet; South Pass, 30 by 450 feet; 
South Pass Bar Channel, 30 by 600 feet. 
Deepen existing channel from 35 to 40 feet by 500 feet wide 
from one-tenth mile below Louisiana Highway Commission 
bridge at Baton Rouge to upper limits of Port of New 
Orleans, and also 40 by 500 feet within presently 
authorized 35- by 1,500-foot channel in port limits of 
New Orleans. 
MISSISSIPPI RIVER-GULF OUTLET, LA. (See 
Sec. 17 of Text) 
Construct a seaway canal 36 feet deep and 500 feet wide from 
Michoud to 38-foot contour in gulf and an inner tidewater 
harbor consisting of a 1,000- by 2,000-foot turning basin 
36 feet deep and a connecting channel 36 feet deep and 
500 feet wide to Inner Harbor Navigation Canal and provides, 
when economically justified, for construction of a lock to 
Mississippi River at Meraux, La. 
MISSISSIPPI RIVER-GULF OUTLET, MICHOUD 
CANAL, LA. (See Sec. 18 of Text) 
Construct a deep-draft navigation channel in the Gulf 
Intracoastal Waterway and Michoud Canal by enlargement 
to a depth of 36 by 250 feet from the Mississippi River- 
Gulf Outlet channel to and including a turning basin 
800 feet square at the north end of Michoud Canal. 
H. Doc. 245, 82d Cong., 
1st sess. 
S. Doc. 97, 90th Cong., 
2d sess. 
11-45 
H. Doc. 239, 89th Cong., 
1st sess.2 
S. Doc. 94, 77th Cong., 
1st sess. 
S. Doc. 231, 79th Cong., 
2d sess. 
H. Doc. 215, 76th Cong., 
1st sess.2 
S. Doc. 36, 87th Cong., 
1st sess. 
Mar. 29, 1956 
Aug. 13, 1968

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 13, 1968 
Jul. 24, 1946 
May 17, 1950 
Aug. 13, 1968 
Aug. 30, 19358 
Aug. 26, 1937 
Mar. 2, 1945 
Jun. 30, 1948 
Jul. 14, 1960 
Jul. 13, 1892 
MISSISSIPPI RIVER OUTLETS, VENICE, LA. (See 
Sec. 19 of Text) 
Enlargement of existing channels of Baptiste Collette 
Bayou and Grand-Tiger Passes to 14 by 150 feet with 
16 by 250-foot entrance channels in open water and 
jetties, if justified. 
OVERTON-RED RIVER WATERWAY, LA. (See 
Sec. 20 of Text) 
Construct 9- by 100-foot channel for 206 miles from Mississippi 
River, mile 301 AHP, through Old and Red Rivers 
to mile 31, thence by lateral canal through land cuts and 
existing waterways across Mississippi-Red River backwater 
area along south bank of Red River floodplain to 
Shreveport, and construct nine locks and pumping plant 
on Red River near Shreveport. 
Extend Overton-Red River Waterway 9- by 100-foot channel 
from Mississippi River to north bank of Black River, 
mile 35.5. 
Provides for the navigation channel to be 200 feet wide. 
PETIT ANSE, TIGRE, AND CARLIN BAYOUS, LA. 
(See Sec. 21 of Text) 
A channel in Bayou Petit Anse 60 feet wide and 9 feet deep 
from Intracoastal Waterway to a point 3.2 miles upstream, 
thence 40 feet wide and 5 feet deep to highway bridge at 
head of Avery Island; and a channel in Bayou Carlin 
40 feet wide and 5 feet deep from Bayou Petit Anse to 
Lake Peigneur. 
A channel in Bayou Petit Anse 9 feet deep and 80 feet wide 
from Intracoastal Waterway to north end of Avery Island 
and a channel 5 feet deep and 40 feet wide from Intracoastal 
Waterway to Vermilion Bay by way of McIlhenny 
Canal (Avery Canal). 
A channel in Bayou Carlin 9 feet deep and 80 feet wide from 
Bayou Petit Anse to Lake Peigneur. 
Protecting piers of railway bridge crossing Bayou Carlin at 
Delcambre, La. 
A harbor of refuge at Delcambre and a channel 7 feet deep 
and 60 feet wide from Gulf Intracoastal Waterway via 
McIlhenny Canal (Avery Canal) to deep water in Vermilion 
Bay. 
RED RIVER BELOW FULTON, ARK. (See 
Sec. 22 of Text) 
Improve Red River from Fulton, Ark., to Atchafalaya 
River, La., 455.6 miles, by systematic clearing of banks, 
snagging, dredging shoals, building levees, either along or 
in cooperation with riparian states, closing outlets, revetting 
caving banks, and preventing injurious cutoffs. 
RED RIVER EMERGENCY BANK PROTECTION (See 
Sec. 23 of Text) 
Realining the banks by dredging cut-offs and training 
works and stabilizing banks by means of revetments and 
dikes. 
RED RIVER WATERWAY-MISSISSIPPI RIVER TO 
SHREVEPORT, LA. (See Sec. 24 of Text) 
Develop a channel 9 by 200 foot, approximately 210 miles 
long from Mississippi River at junction of Old River via 
Old River and Red River to Shreveport, La., consisting 
of realinement, bank stabilization, and construction of 
five locks and dams. 
H. Doc. 304, 90th Cong., 
2d sess. 
H. Doc. 304, 90th Cong., 
2d sess. 
11-46 
H. Doc. 361, 90th Cong., 
2d sess.2 
H. Doc. 320, 80th Cong., 
1st sess. 
S. Doc. 117, 81st Cong., 
1st sess. 
H. Doc. 304, 90th Cong., 
2d sess. 7 
H. Doc. 225, 72d Cong., 
1st sess. 
Rivers and Harbors Committee, 
Doc. 40, 75th Cong., 
1st sess. 
H. Doc. 594, 78th Cong., 
2d sess.2 
Public Law 858, 80th Cong., 
2d sess. 
H. Doc. 70, 85th Cong., 
2d sess. 
H. Doc. 378, 74th Cong., 
2d sess. 
Aug. 13, 1968 
Aug. 13, 1968

TABLE 11-B 
(Continued) 
NEW ORLEANS, LA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 13, 1968 
Mar. 3, 1899 
Jun. 13, 1902 
Jul. 25, 1912 
Jul. 24, 1946 
Aug. 30, 1935 
Oct. 23, 1962 
Oct. 27, 1965 
Jun. 28, 1938 
Jun. 22, 1936 
Jun. 30, 1948 
RED RIVER WATERWAY-SHREVEPORT, LA., TO 
DAINGERFIELD, TEX. (See Sec. 25 of Text) 
Develop a channel 9 by 200 foot, extending from Red River 
at Shreveport, La., through Twelvemile and Cypress 
Bayous to a turning basin in Lake 0' the Pines-Ferrells 
Bridge Dam, downstream of U. S. Highway 259 Bridge 
near Daingerfield, Tex., consisting of realinement, bank 
stabilization, and construction of four locks and dams. 
REMOVING WATER-HYACINTH, LA. (See 
Sec. 26 of Text) 
Appropriations for Florida and Louisiana and extermination 
or removal of plants, building of boats, and establishment 
of booms. 
Authorized use of mechanical, chemical, or other means 
whatsoever. 
Made appropriation available for State of Mississippi 
and also made available for use in that State operating 
plant pertaining to work in Louisiana. 
WATERWAY FROM EMPIRE, LA., TO GULF OF 
MEXICO (See Sec. 27 of Text) 
Construction and maintenance of a waterway, 10 miles 
long, from State-owned canal and lock at Empire, La., to 
Gulf of Mexico, to provide a channel 9 by 80 feet, and for 
initial construction of rubblestone jetties inshore of 6-foot 
depth contour, with landward extensions thereof as required 
to prevent flanking, and for seaward extensions 
to 9-foot-depth contour if and when it becomes apparent 
that such extensions will be more economical than 
maintenance dredging of entrance channel. 
WATERWAY FROM INTRACOASTAL WATERWAY 
TO BAYOU DULAC, LA. (Bayous Grand Caillou and 
LeCarpe, La.) (See Sec. 28 of Text) 
Channel 5 by 40 feet from Intracoastal Waterway at Houma 
through Bayou LeCarpe, Bayou Pelton, and Bayou Grand 
Caillou to Bayou Dulac, about 16.3 miles. 
Channel 10 by 45 feet in Bayou LeCarpe from Gulf Intracoastal 
Waterway to Houma navigation canal. 
BAYOU BODCAU AND TRIBUTARIES, ARK. 
AND LA. (See Sec. 31 of Text) 
Extend Cypress Bayou-Red Chute Bayou levee, construct 
stream closure landside drainage channel and three culverts 
on Red Chute Bayou, and clearing and snagging channel; 
extend Flat River-Loggy Bayou levee, close Flat River near 
junction with Cutoff Bayou, and construct control structures 
on Flat River near junction with Red Chute Bayou; and 
enlarge Flat River channel to 20 to 35 feet, a distance of 
11.6 miles. 
BAYOU BODCAU RESERVOIR, LA. (See Sec. 32 of Text) 
Provides for construction of a reservoir and other flood 
control works. 
BAYOU PIERRE, LA. (See Sec. 33 of Text) 
Widening channel at intervals totaling 12.9 miles, and 
snagging of 29.7 miles. 
BRUSH BAYOU, LA. (See Sec. 34 of Text) 
Enlargement and alinement of existing channel between 
(mile 1.20) and (mile 7.42), a distance of 6.22 miles. 
Bottom widths for the improved channel vary from 100 
feet at mile 1.20 to 20 feet at mile 7.42. 
11-47 
H. Doc. 304, 90th Cong., 
2d sess. 
H. Doc. 91, 55th Cong., 
3d sess. 
H. Doc. 697, 79th Cong., 
2d sess.Y 
H. Doc. 206, 72d Cong., 
1st Sess. 
H. Doc. 583, 87th Cong., 
2d Sess.2 
H. Doc. 203, 89th Cong., 
1st sess. 
H. Doc. 378, 74th Cong., 
2d sess. 
H. Doc. 378, 74th Cong., 
2d sess.2 
Approved Sep. 6, 1973, 
under authority of 
Sec. 205, Flood Control 
Act of 1948, 
as amended.

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
Jun. 30, 1948 
CADDO LAKE, LA. (See Sec. 35 of Text) 
Replacement of existing dam with new dam having same 
flow characteristics and located as near as practicable 
downstream from the old dam, built under navigation 
project "Cypress Bayou and Waterway between Jefferson, 
Tex., and Shreveport, La." 
CHOCTAW BAYOU AND TRIBUTARIES, LA. (See 
Sec. 36 of Text) 
Channel improvement by excavation of Choctaw Bayou, 
Bayou Chalpin, and Bayou Chalpe and clearing and 
snagging. 
COOPER LAKE AND CHANNELS, TEX. (See 
Sec. 37 of Text) 
Construction of earth-fill dam and reservoir area; channel 
clearing, realinement, and enlargement; enlargement and 
extension of existing levees; construction of appurtenant 
drainage works along main stem of Sulphur River above 
mile 126; channel clearing, realinement, and enlargement 
and levee enlargement and modification of appurtenant 
drainage works on Cuthand Creek below mile 24, on Sulphur 
River below mile 70, except in proposed Cooper Reservoir, 
miles 29 to 42, and on Middle Sulphur River below mile 8; 
channel clearing and realinement of Brushy Creek below 
mile 5; and levee enlargement on North Sulphur River between 
miles 1 and 5. 
FERRELLS BRIDGE DAM-LAKE O' THE PINES, 
TEX. (See Sec. 38 of Text) 
Provides for construction of an earth-fill dam and 
reservoir area. 
GARLAND CITY, ARK. (See Sec. 39 of Text) 
Bank protection works consisting of a pile revetment on 
left bank of Red River above railway bridge or equivalent 
protective works, rock groins between the bridges, riprap 
around east bank railway pier, pile dikes on right bank 
of Red River above railway bridge, channel excavation on 
right bank in vicinity of railway bridge, and a board revetment 
or equivalent work near anticipated natural cutoff 
to be constructed for protection of railway and highway 
bridges over Red River at Garland City, Ark. 
HARVEY CANAL, BAYOU BARATARIA 
LEVEE, LA. (See Sec. 40 of Text) 
Provides for construction of new levees and enlargement 
of existing non-Federal levees along Harvey Canal 
and Bayou Barataria from mile 1.8 on Harvey Canal to 
Louisiana Highway 45 near Crown Point. 
LAKE PONTCHARTRAIN AND VICINITY, LA. 
(HURRICANE PROTECTION) (See Sec. 41 of Text) 
Control of hurricane tides by construction of two independent 
units, the Lake Pontchartrain Barrier plan and the 
Chalmette Area plan. 
11-48 
S. Doc. 39, 89th Cong., 
1st sess. 
Approved Apr. 11, 1968, 
under authority of 
Sec. 205, Flood Control 
Act of 1948, 
as amended. 
H. Doc. 488, 83d Cong., 
2d sess. 2 
H. Doc. 602, 79th Cong., 
2d sess.2 
H. Doc. 167, 87th Cong., 
1st sess. 
Approved by Chief of 
Engineers on Jan. 22, 
1964, under authority 
of Sec. 205, Flood 
Control Act of 1948, 
as amended. 
H. Doc. 231, 89th Cong., 
1st sess. 
Aug. 3, 1955 
Jul. 24, 1946 
Jul. 14, 1960 
Jun. 30, 1948 
Oct. 27, 1965

TABLE 11-B 
(Continued) 
NEW ORLEANS, LA., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized 
Oct. 27, 1965 
Oct. 23, 1962 
Oct. 27, 1965 
H. Doc. 184, 89th Cong., 
1st sess. 
H. Doc. 550, 87th Cong., 
2d sess. 
H. Doc. 167, 89th Cong., 
1st sess. 
LAROSE TO GOLDEN MEADOW, LA. (HURRICANE 
PROTECTION) (See Sec. 42 of Text) 
A loop levee about 36 miles long along both banks of Bayou 
Lafourche from Golden Meadow to Larose; enlargement 
of 3 miles of existing levee at Golden Meadow; floodgates 
for navigation and hurricane protection in Bayou Lafourche 
at upper and lower bayou crossings; about 8 miles of low 
interior levees to regulate intercepted drainage; and 
seven multibarreled culverts controlled by flapgates. 
MISSISSIPPI RIVER DELTA AT AND BELOW 
NEW ORLEANS, LA. (NEW ORLEANS TO VENICE, LA., 
HURRICANE PROTECTION) (See Sec. 43 of Text) 
Improvements along Mississippi River below New Orleans, 
La., for prevention of hurricane tidal flood damages by increasing 
heights of existing back levees and modifying existing 
drainage facilities where necessary in three separate 
reaches. 
MORGAN CITY AND VICINITY, LA. (HURRICANE 
PROTECTION) (See Sec. 44 of Text) 
Construction of new levees along Lake Palourde and Bayou 
Ramos, levee to tie-in with Bayou Boeuf lock levee and three 
gravity drainage structures in Morgan City unit and enlargement 
of bank levee, construction of new levee, and construction 
of one floodgate and five gravity drainage structures 
in Franklin and vicinity unit. 
RED RIVER BELOW DENISON DAM, LEVEES 
AND BANK STABILIZATION (NEW ORLEANS 
DISTRICT) (See Sec. 46 of Text) 
Levee and bank stabilization. 
Deauthorization of Mooringsport Dam and Reservoir on 
Cypress Creek; realining and stabilizing the banks of the 
Red River; and recreational facilities from the Mississippi 
River to Denison Dam, Okla. and Tex. 
WALLACE LAKE, LA. (See Sec. 47 of Text) 
Construction of an earth-fill dam and a reservoir. 
WRIGHT PATMAN DAM AND LAKE, TEX. 
(See Sec. 48 of Text) 
Construction of an earth-fill dam and a reservoir. 
1. For latest published map, see H. Doc. 410, 56th Cong., 
1st sess. 
2. Contains latest published map. 
3. Permanent Appropriation Repeal Act. 
4. For latest published map, see H. Doc. 288, 66th Cong., 
1st sess. 
5. Authorized under provision of Sec. 201 of Flood 
Control Act of 1965. 
6. Not mentioned in authorizing act. 
7. Portion of existing project above mile 31 was 
reclassified to inactive status as approved by Office, Chief of 
Engineers, letter dated Oct. 18, 1971. 
8. Included in Public Works Administration Program, 
Sep. 6, 1933. 
11-49 
Documents 
H. Doc. 602, 79th Cong., 
2d sess. 
H. Doc. 304, 90th Cong., 
2d sess. 
H. Doc. 378, 74th Cong., 
2d sess. 
H. Doc. 602, 79th Cong., 
2d sess. 
Jul. 24, 1946 
Aug. 13, 1968 
Jun. 22, 1936 
Jul. 24, 1946 
Z

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-C BAYOU TECHE, LA., LOCKS 
(See Sec. 7 of Text) 
Pertinent Data 
Keystone Lock 
Miles from New Iberia, La. 
Miles from Intracoastal Waterway 
Width of chamber 
Length available for full width 
Lift 
Depth on miter sill at mean low gulf level 
Character of foundation 
Kind of dam 
Type of construction 
Year completed 
Cost 
Berwick Lock 
Miles north of Berwick, La. 
Miles below mouth of Bayou Teche 
Width of chamber 
Length available for full width 
Lift 
Depth on miter sill at mean low gulf level 
Character of foundation 
Type of construction 
Open to navigation 
Completed 
Cost (flood control, MR&T funds) 
18 
82.5 
36 feet 
160 feet 
8 feet 
8 feet 
Timber piles 
Timber, rockfill 
Concrete 
1913 
$257,720 
1.7 
9
45 feet 
300 feet 
0-14.5 feet 
9
Timber piles 
Reinforced concrete 
November 1950 
September 1951 
$2,100,000 
CALCASIEU RIVER AND PASS, LA. 
WORK ACCOMPLISHED UNDER EACH 
MODIFICATION 
(See Sec. 8 of Text) 
Modification Started Completed 
Aug. 26, 1937 Fiscal Year 1939 April 1941 
Mar. 2, 1945 September 1948 June 1949 
Jul. 24, 1946 September 1948 April 1953 
Jul. 14, 1960 April 1962 October 1968 
11-50 
TABLE 11-D

NEW ORLEANS, LA., DISTRICT 
TABLE 11-E GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FLA., AND MEXICAN 
BORDER (NEW ORLEANS DIST.)-LOCKS 
(See Sec. 12 of Text) 
Pertinent Data 
Algiers Lock 
Miles below New Orleans, La. (Canal St.) 
Miles from Mississippi River 
Width of chamber 
Length available for full width 
Lift 
Depth on sill at mean low gulf level 
Character of foundation 
Type of construction 
Opened to navigation 
Cost 
Miles from New Orleans, La. (Canal St.) via Harvey Lock 
Miles from Mississippi River via Plaquemine Lock 
Width between abutments 
Length available for full width 
Lift 
Depth on sill at mean low gulf level 
Character of foundation 
Type of construction 
Opened to navigation 
Cost (flood control, MR&T funds) 
7
0.38 
75 feet 
800 feet 
0-18 feet 
13 feet 
Timber piles 
Reinforced concrete 
April 1956 
$5,215,700 
Bayou Boeuf Lock
96.6 
56.7 
75 feet 
1,156 feet 
0-11.3 feet 
13 feet 
Concrete slab on medium to stiff clay 
Reinforced concrete gatebays and earth chamber 
September 1954 
$2,754,000 
Bayou Sorrel Lock 
Miles from New Orleans, La. (Canal St.) via Harvey Lock 
Miles from Mississippi River via Plaquemine Lock 
Width of chamber 
Length available for full width 
Lift 
Depth on sill at mean low gulf level 
Character of foundation 
Type of construction 
Opened to navigation 
Completed 
Cost (flood control, MR&T funds) 
Miles below Lake Charles, La. 
Miles from Calcasieu River 
Width between abutments 
Length available for full width 
Lift 
Depth on sill at mean low gulf level 
Character of foundation 
Type of construction 
Opened to navigation 
Cost 
Miles above New Orleans, La. (Canal St.) 
Miles from Mississippi River 
Width of chamber 
Length available for full width 
Lift 
Depth on miter sill at mean low gulf level 
Character of foundation 
Type of construction 
Opened to navigation 
Cost 
135 
18 
56 feet 
797 feet 
0-21 feet 
14 feet 
Timber piles 
Reinforced concrete gatebays and earth chamber 
June 1951 
October 1952 
$4,700,948 
Calcasieu Lock 
16.6 
0.5 
75 feet 
1,206 feet 
0-4 feet 
13 feet 
Concrete slab on preconsolidated stiff clay 
Reinforced concrete gatebays and earth chamber 
December 1950 
$2,133,527 
Harvey Lock 
3.3 
0.13 
75 feet 
425 feet 
0-19.6 feet 
12 feet 
Timber piles 
Reinforced concrete 
1934 and completed 1935 
$1,775,132 
11-51

TABLE 11-E 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FLA., AND MEXICAN 
BORDER (NEW ORLEANS DIST.)-LOCKS 
(See Sec. 12 of Text) 
Pertinent Data 
Inner Harbor Navigation Canal Lock 
Miles below New Orleans, La. (Canal St.) 
Miles from Mississippi River 
Width of chamber 
Length available for full width 
Lift 
Depth on miter sill at mean low gulf level 
Character of foundation 
Type of construction 
Opened to navigation 
Cost (non-Federal) 
Completed and opened to navigation 
Closed permanently 
Cost 
Miles above New Orleans, La. (Canal St.) 
Miles from Mississippi River 
Width of chamber 
Length available for full width 
Lift 
Depth on miter sill at mean low gulf level 
Character of foundation 
Type of construction 
Completed and opened to navigation 
Cost 
Miles from Abbeville, La. 
Miles from Vermilion River 
Width between abutments 
Length available for full width 
Lift 
Depth on sill at mean low gulf level 
Character of foundation 
Kind of dam 
Type of construction 
Opened to navigation 
Cost 
Replacement of lock approved by the Secretary of Army, 
May 16, 1967; estimated Federal cost 
2.9 
0.6 
75 feet 
640 feet 
0-17.4 feet 
31.5 feet 
Timber piles 
Reinforced concrete 
February 1923 
$8,648,492 
Plaquemine Lock
1909 
September 29, 1961 
$1,302,006 
Port Allen Lock
132.5 
0.23 
84 feet 
1,202 feet 
45 feet 
13.75 feet 
Concrete slab on clay 
Reinforced concrete 
July 1961 
$13,902,222 
Vermilion Lock
26 
1.75 
56 feet 
1,182 feet 
0-5 feet, either direction 
11.3 feet 
Timber piles 
Reinforced concrete spillway dam, vertical cast steel 
gates, timber-pile foundation 
Reinforced concrete 
1933 and completed 1934 
$330,765 
$12,000,000 
11-52

NEW ORLEANS, LA., DISTRICT 
TABLE 11-F OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Alteration of Berwick Bay Bridge' 
Amite River and Bayou Manchac, La.2,s3 
Bayou Bonfouca, La.2,4 
Bayou Dorcheat, Loggy Bayou, and Lake Bisteneau, La.4,5,67 
Bayou Dupre, La.2,4 
Bayou Grosse Tete, La.2' 9 
Bayou Lacombe, La.2 ,4 
Bayou La Loutre, St. Malo, and Yscloskey, La.2 4 
Bayou Plaquemine Brule, La.4 
Bayou Queue de Tortue, La. 4 
Bayou Segnette Waterway, La. 
Bayou Terrebonne, La.3,4,10 
Bayou Vermilion, La.3,4 
Big Pigeon and Little Pigeon Bayous, La.45 
Calcasieu River Salt Water Barrier, La.4"' 
Cane River, La.4,5,7 
Chefuncte River and Bogue Falia, La.2 ,4 
Cypress Bayou and Waterway between Jefferson, Tex. 
and Shreveport, La. 
Grand Bayou Pass, La.4 
Inland Waterway from Franklin to Mermentau River, La.4 
Intracoastal Waterway from the Mississippi River 
to Bayou Teche, La.' 3 
Lake Charles Deep Water Channel, La.' 4 
Little Caillou Bayou, La.4 
Navigation work under special authorization (Calcasieu 
Pass channel in Old River Bend at Cameron, La.)'5 
Pass Manchac, La.4 
Red River Waterway, La., Ark., Okla., and Tex.' 6 
Sulphur River, Ark. and Tex. 45 ,7 
Tangipahoa River, La.2'6 
Tickfaw, Natalbany, Ponchatoula, and Blood Rivers, La.2 ,3,4 
Vinton Waterway, La.' 7 
Waterway from White Lake to Pecan Island, La.' 8 
1. Transferred to Department of Transportation. 
Authorized under Truman-Hobbs Act. 
2. Channel adequate for commerce. 
3. Includes previous project costs. 
4. Completed. 
5. Inactive. 
6. No commerce reported. 
7. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
8. Includes $56 cost incurred in 1969. 
9. Completed except that portion above mile 10.3 
providing for widening from 40 feet to 60 feet, which is 
inactive. 
10. By Public Law 88-404, that portion of Bayou 
Terrebonne between point where Barrow Street crosses said 
stream and a line determined by prolonging and extending 
eastern right-of-way line of New Orleans Boulevard southerly 
to south bank of said stream was declared nonnavigable. 
11. Operation and maintenance of the structure reported 
under project "Calcasieu River and Pass, La." 
12. Excludes $50,000 contributed funds. 
13. Not completed; superseded for most of its length by 
present 12- by 125-foot Gulf Intracoastal Waterway, which 
coincides with or parallels it. 
14. Maintenance project; no future work schedules. 
15. Work is under continuing authority. 
16. Emergency bank protection on this project is reported 
separately as "Red River Emergency Bank Protection." Two 
reaches, "Red River Waterway-Mississippi River to 
Shreveport, La.," and "Red River Waterway-Shreveport, La., 
Daingerfield, Tex.," are also reported separately. 
17. No work performed; local interests have not provided 
rights-of-way and dumping privileges. 
18. Not completed; incorporated in navigation project 
"Mermentau River, La." 
11-53 
1967 
1950 
1974 
1887 
1968 
1969 
1967 
1970 
1950 
1970 
1958 
1961 
1947 
1936 
1973 
1910 
1967 
1971 
1950 
1960 
1956 
1950 
1973 
1957 
1950 
1969 
1919 
1973 
1973 
1950 
1948 
28,234 
30,997 
5,000 
38,915 
29,392 
4,716 
96,916 
33,410 
33,355 
238,828 
120,089 
34,900 
4,197,262 
2,500 
58,342 
202,817 
7,676 
249,052 
77,761 
1,374 
45,989 
61,211 
8,115 
10,904 
$- 
63,534 
290,192 
104,1878 
123,454 
92,276 
223,616 
36,780 
28,315 
213,455 
251,691 
200,169 
37,169 
2,000 
192,011 
452,61112 
14,480 
552,780 
11,669 
241,896 
751,485 
139,755 
10,039 
202,925 
92,163 
10,742

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 11-G RESERVOIR OPERATIONS 
See 
Section Storage 
in Text Project (acre-feet) Inflow' Outflow' 
32 Bayou Bodcau Jul. 1, 1974 48,712 2 1,953 
Reservoir, La. Jun. 30, 1975 25,634 261 1,569 
Feb. 14, 1975(maximum) 131,491 - - 
Feb. 4, 1975 (maximum) - 10,070 - 
Feb. 14, 1975 (maximum) - - 2,713 
38 Ferrells Bridge Jul. 1, 1974 283,098 - 25 
Dam-Lake 0' the Jun. 30, 1975 287,712 795 1,029 
Pines, Tex. Feb. 8, 9, 1975 375,018 - - 
(maximum) 
Feb. 3, 1975 (maximum) - 20,661 - 
Feb. 4, 1975 (maximum) - - 3,160 
47 Wallace Lake, Jul. 1, 1974 7,676 - - 
La. Jun. 30, 1975 8,985 171 171 
Feb. 6, 1975 (maximum) 35,970 - - 
Feb. 3, 1975 (maximum) - 5,207 - 
Feb. 6, 1975 (maximum) - - 1,990 
48 Wright Patman Jul. 1, 1974 533,290 2,476 9,861 
Dam and Lake, Jun. 30, 1975 346,212 805 1,007 
Tex. Feb. 13, 1975(maximum) 767,336 - - 
Feb. 7, 1975 (maximum) - 69,937 - 
Nov. 8, 1974 (maximum) - - 10,853 
1. Cubic feet per second. 
11-54

NEW ORLEANS, LA., DISTRICT 
TABLE 11-H RED RIVER BELOW DENISON DAM (NEW 
ORLEANS DISTRICT): NEW PROJECTS 
(See Sec. 45 of Text) 
Drainage Conserva- Flood 
Area tion Control Estimated 
(square Storage (acre- Federal 
Project Stream miles) (acre-feet) feet) Cost 
Bayou Bodcau and tributaries, 
Ark.2 - 1,158 - - $ 12,800,0003 
Bayou Nicholas-Coushatta, La. - - - - 70,7174 
Bayou Pierre in vicinity of Shreveport, 
La.5 - - - 243,3363 
Caddo Lake, La.1 Caddo Lake - - - 3,270,0002 
Campti-Clarence Area in 
Natchitoches Parish, La. Red River - - - 1,572,9573 
Cooper Lake and Channels, Tex.1 South Sulphur River 476 37,0006 131,400 61,800,0003 
East Point, La. - - - - 486,0693 
Ferrells Bridge-Lake 
0' the Pines, Tex.' Cypress Creek 850 3,800 587,2006 16,831,7003,7 
Garland City, Ark. - - - 1,340,0003 
Maniece Bayou, Ark. - - - - 970,0323 
McKinney Bayou, Ark.8 - - - 1,456,7003 
Posten Bayou, Ark. and 
La.2 9 - - - 560,000 
Red River below Denison Dam 
levees and bank stabilization, 
Tex., Ark., and La. (New 
Orleans District)'3 - - - - 48,700,0003 
Wright Patman Dam & 
Lake, Tex.1 Sulphur River 3,400 145,300 2,509,000 48,310,00010 
Total $198,411,511 
1. Details presented in individual report herein. 
2. Construction on this project not started. 
3. In addition, non-Federal funds are: 
Bayou Bodcau and tributaries, Ark. and La. ........................................ ....... $3,100,000 
Bayou Pierre in vicinity of Shreveport, La. (cash contribution) ..................................... 89,047 
Caddo Lake, La. ................................ ................................................ 218,000 
Campti-Clarence Area in Natchitoches Parish, La. ........................................ 480,000 
Cooper Lake and channels, Tex. (excludes $25,600,000 for reimbursement for water supply; 
includes cash contribution of $2,800,000) ............................... ....................... 3,180,000 
East Point .................................................... ...................... ........... 67,000 
Ferrells Bridge Dam-Lake 0' the Pines, Tex. (cash contribution) ................................ 1,711,200 
Garland City, Ark. .............................................. 6,000 
Maniece Bayou, Ark. (cash contribution) ..................................................... 39,293 
McKinney Bayou, Ark. (cash contribution) ........................................................ 18,700 
Red River below Denison Dam, levees and bank stabilization, Tex., Ark., and La. (includes 
$100,000 cash contribution) ............................................ 343,000 
4. For last full report, see Annual Report for 1964. 
5. For last full report, see Annual Report for 1951. 
6. Joint-use pool (sediment). 
7. Includes $4,070,200, Code 711, and $399,739 accelerated Public Works funds. 
8. Inactive. 
9. Deauthorized by resolution Dec. 17, 1970, which also authorized new project "Posten Bayou, Ark.," under provision of 
Sec. 201 of Flood Control Act of 1965. 
10. Includes $4,610,100, Code 711, and $399,939 accelerated Public Works funds, and $11,338,004 to be reimbursed by local 
interests over a period not to exceed 50 years for water supply storage and pro rata share of original reservoir cost. 
11-55

TABLE 11-I 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
RED RIVER BELOW DENISON DAM (NEW 
ORLEANS DISTRICT): INCORPORATED PROJECTS 
(See Sec. 45 of Text) 
For Last 
Flood Estimated Full Report 
Control Federal See Annual 
Project Type of Work Act Cost Report For 
Aloha-Rigolette Area, Grant and Rapides 
Parishes, La. Levee and appurtenances 1941 $ 1,653,2371 1956 
Bayou Bodcau Reservoir, La. Flood-control reservoir 1938 5,120,7401,2 (3) 
Bayou Bodcau, Red Chute, and Loggy 
Bayou, La. Channel improvement 194k 319,2001 1948 
Bayou Pierre, La. Channel enlargement 1936 299,5291 (3) 
Black Bayou Lake, La.4'5 Flood-control reservoir 1936 714,000 1945 
Colfax, Grant Parish, La. Cutoff 1938 70,3481,6 1938 
Grant Parish, below Colfax, La. Levees 1938 38,8091 1941 
Hempstead County levee district 
No. 1, Ark. Levee enlargement 1938 88,0061 1941 
Natchitoches Parish, La. Levee and appurtenances 1936 1,529,927"1, 1956 
Pineville, Red River, La. Levee and appurtenances 1941 232,4261 1953 
Red River in vicinity of 
Shreveport, La. Bank protection 1944 3,908,0001 1953 
Red River Parish, La. Levee enlargement 1936 149,4351 1939 
Saline Point, La. Cutoff 1936 124,1111 1945 
Wallace Lake, La. Flood-control reservoir 1936 1,219,3711,2 (3) 
Total $15,467,134 
1. Actual cost. 
2. Includes amounts indicated for recreational facilities 
under Code 711, Bayou Bodcau Reservoir, La., $1,022,000; 
Wallace Lake, La., $17,164. 
3. Included in this report. 
4. Work not started. 
5. Inactive. 
6. Completed under provisions of Sec. 7 of Flood Control 
Act of 1928, as amended by Sec. 9 of Flood Control Act of 1936, 
and included in 1939 Annual Report of President, Mississippi 
River Commission, p. 2214. 
7. In addition, $250,000 was expended from contributed 
funds. 
11-56

NEW ORLEANS, LA., DISTRICT 
TABLE 11-J OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Sec. 50 of Text) 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Aloha-Rigolette Area, Grant and Rapides Parishes, La., 2 1956 $1,653,189 $ 
Amite River and Tributaries, La.2 1964 3,034,2553 
Bayou Bodcau, Red Chute, and Loggy Bayou, La."2 1948 319,200 
Bayou Choupique, La.2,4 1954 129,930 
Bayou Nicholas, Coushatta, La.2,4 1964 70,717 
Bayou Pierre in vicinity of Shreveport, La."2 1951 243,3363 
Bayou Rapides, La.2'4 1952 95,179 
Black Bayou Reservoir, La.15 ,6 1945 - 
Black Bayou-Pine Island Area, La.2'4 1963 336,063 
Campti-Clarence Area in Natchitoches Parish, La.2 1969 1,572,957 
Colfax, Grant Parish, La.,"7 1938 70,348 
East Point, La.2 1969 486,069 
Grant Parish below Colfax, La.",2 1941 38,809 
Hempstead County Levee District No. 1, Ark.",2 1941 88,006 
Maniece Bayou, Ark.'"2 1970 970,9323 
McKinney Bayou, Ark.",6 1964 1,021,2633 
Natchitoches Parish, La." 1956 1,529,4783 
Pineville, Red River, La."2 1953 232,426 
Posten Bayou, Ark.s 1973 - 
Red River Parish, La."2 1939 149,435 
Red River in vicinity of Shreveport, La.",2 1953 3,908,000 
Saline Point, La.",2 1945 124,111 
Twelvemile Bayou, La.2'4 1966 335,433 
1. Authorized under project "Red River Below Denison 
Dam." 
2. Completed. 
3. In addition, the following was expended from 
contributed funds: 
Amite River and tributaries ........... $ 430 
Bayou Pierre in vicinity of Shreveport, 
La . .. ........................ 89,047 
Maniece Bayou, Ark. .................. 39,293 
McKinney Bayou, Ark. ................ 18,700 
Natchitoches Parish, La. ............. 250,000 
4. Authorized by Chief of Engineers: (Sec. 205, 1948 
Flood Control Act, as amended.) 
5. Construction not initiated. 
6. Inactive. 
7. Completed under provisions of Sec. 7, Flood Control 
Act 1928, as amended by Sec. 9, Flood Control Act 1936, and 
included in 1939 Annual Report of President, Mississippi 
River Commission, p. 2214. 
8. Posten Bayou Project, authorized by Senate and House 
resolutions, Dec. 17 and 15, 1970, deletes the plan authorized 
by the Flood Control Act dated Aug. 3, 1955. 
11-57

TABLE 11-K 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
EMERGENCY FLOOD CONTROL ACTIVITIES 
REPAIR, FLOOD FIGHTING, AND RESCUE 
WORK (PUBLIC LAW 99, 84th CONG., AND 
ANTECEDENT LEGISLATION) 
(See Sec. 51 of Text) 
Project and Location 
Advance preparation for flood emergency 
Emergency Operations: 
Public Law 84-99-1973 Flood 
Public Law 84-99-1974 Flood 
Public Law 84-99-1975 Flood 
Hurricane Carmen 
Rehabilitation: 
Atchafalaya Bayou Floodway 
Bonnet Carrd Spillway 
Lafourche Parish 
McKinney Bayou Floodgate 
Mississippi River Levees 
Old River 
Red River Levee 
Red River Levee, Index, Ark., to Lake Long, La. 
Red River, Coushatta 
Red River, Cupples 
Red River, Lake End 
Revetment & Foreshore Protection 
Sulphur River Levee, Cooper and Cuthand Creek 
Total 
11-58 
Federal Cost 
FY 75 
$ 51,816 
442,150 
1,691,567 
11,857,490 
60,237 
550,555 
5,495 
128,963 
1,362 
2,581,675 
4,404,943 
348,910 
60,069 
753 
49,069 
27,630 
2,983,463 
9,475 
$25,255,622

VICKSBURG, MISS., DISTRICT* 
The district comprises western Mississippi, 
southern Arkansas, northeastern Louisiana, and 
a very small portion of southwestern Tennessee, 
embraced in drainage basins of eastern 
tributaries of Mississippi River south of Horn 
Lake Creek to and including Buffalo River: 
western tributaries between White and Red 
Rivers, including Arkansas River Basin below a 
point 3 miles upstream from Pine Bluff and 
Arkansas River below mile 36.1 near Pendleton, 
Ark.; and Ouachita and Black Rivers in Arkansas 
and Louisiana. 
IMPROVEMENTS 
Navigation Page 
1. Lake Providence Harbor, La. ...... 12-1 
2. Ouachita and Black Rivers below 
Camden, Ark. ................... 12-2 
3. Yazoo River, Miss. ............... 12-2 
4. Other authorized navigation 
projects ......................... 12-3 
5. Navigation work under special 
authorization .................... 12-3 
Flood Control 
6. Ouachita River and Tributaries, Ark. 
and La. ......................... 12-3 
6A. Blakely Mountain Dam- 
Lake Ouachita, Ouachita 
River, Ark. ..................... 12-4 
6B. DeGray Lake, Caddo River, 
Ark. ............................ 12-4 
Flood Control (cont.) Page 
6C. Narrows Dam-Lake Greeson, 
Little Missouri River, Ark. ......... 12-4 
6D. Bayou Bartholomew and Tributaries, 
Ark. and La. .................... 12-5 
6E. Monroe Floodwall, La ............. 12-5 
6F. Ouachita River Levees, La. ........ 12-6 
7. Inspection of completed flood 
control projects .................... 12-6 
8. Other authorized flood control 
projects .......................... 12-6 
9. Flood control work under special 
authorization ..................... 12-6 
General Investigations 
10. Surveys ......................... 12-7 
11. Collection and study of basic data .. 12-7 
12. Research and development ......... 12-7 
Navigation 
1. LAKE PROVIDENCE HARBOR, LA. 
Location. In Hagaman Chute, a secondary 
channel of the Mississippi River at mile 483.4 
above Head of Passes, and about 3 miles south of 
Lake Providence, La. 
Existing project. A dredged harbor channel 
about 0.7 mile long and 150 feet wide with a 
project depth of 9 feet in Hagaman Chute from 
the Mississippi River. Channel was widened to 
400 feet in front of and upstream from port area, a 
distance of 800 feet, to provide a turning basin. 
Local interests constructed retaining dikes to 
provide the disposal area for material excavated 
from channel and turning basin. Resulting 
hydraulic fill provides a raised port area. Federal 
cost of completed work was $198,859, excluding 
preauthorization study costs of $9,678. Total non- 
Federal cost was $233,400, including cost of 
retaining dikes, and a cash contribution of 
$35,000. In addition, local interests have spent 
$1,022,000 for port facilities. 
* All cost and financial statements and authorizing legislation for projects are listed at the end of this chapter. All other tables 
are referenced in text and also appear at the end of this chapter. 
12-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Local cooperation. Fully complied with. 
Terminal facilities. Local interests provided 
port facilities. 
Operations and results during fiscal year. 
Leased dredge G. A. Mc Williams removed 271,819 
cubic yards of material for maintenance in 
harbor channel and turning basin. 
Condition at end of fiscal year. The project was 
completed in 1963 and is being maintained. 
2. OUACHITA AND BLACK RIVERS 
BELOW CAMDEN, ARK. 
Location. Ouachita River rises in Polk County, 
Ark., and flows southeasterly and southerly about 
600 miles. Below its confluence with the Tensas 
and Little Rivers at Jonesville, La., it is called 
Black River, which enters Red River 35.5 miles 
from the Mississippi River. 
Previous projects. See page 683 of Annual 
Report for 1962 for details. 
Existing project. See page 684 of Annual Report 
for 1962 for details of existing 6.5-foot navigation 
project. New work for completed project cost 
$4,574,551, exclusive of amounts expended under 
previous projects. Modified project and project 
for Red River below Fulton, Ark., provide for a 
channel 9 feet deep and 200 feet wide in Red River 
between Old River and mouth of Black River, and 
in Black and Ouachita Rivers from mouth of 
Black River to Camden, Ark. This is being 
accomplished by construction of four new locks, 
84 feet by 600 feet; new dams; channel 
realinement; and measures to preserve Catahoula 
Lake for migratory waterfowl. Jonesville Lock 
and Dam replaced existing Lock and Dam No. 2; 
Columbia Lock and Dam replaced existing Lock 
and Dams Nos. 3, 4, and 5; Felsenthal Lock and 
Dam will replace existing Lock and Dam No. 6; 
and Calion Lock and Dam will replace existing 
Lock and Dam No. 8. The River and Harbor Act 
of 1970 authorized establishment of wildlife 
refuges along Bayou D'Arbonne (14,700 acres) in 
connection with Columbia Lock and Dam and at 
Felsenthal Lock and Dam (65,000 acres). The 
Bayou D'Arbonne refuge was increased to 18,000 
acres at the request of the Bureau of Sport 
Fisheries and Wildlife. Approved (1975) 
estimated cost for new work for 9-foot navigation 
project is $177,420,000, including $173,000,000 
Federal and $4,420,000 non-Federal for lands, 
damages, and relocations. 
Local cooperation. Local cooperation for all 
completed work in Louisiana has been furnished 
in a timely manner. It is anticipated that local 
interests in Louisiana will be able to supply the 
necessary rights-of-way for construction of the 
cutoffs and bend widenings. Local interests in 
Arkansas have furnished the rights-of-way for 
the Felsenthal access road, lock, dam, and 
disposal area, and it is anticipated that the 
remaining rights-of-way will be furnished when 
needed. All assurances from local interests in 
Arkansas including supplemental assurances 
(Public Law 91-646) have been accepted. The 
State of Louisiana has not furnished 
supplemental assurances; however, they are 
anticipated in the near future. 
Terminal facilities. Public loading docks are at 
Columbia, La., and Camden, Ark. Privately 
owned docks and loading and unloading facilities 
are at Columbia, Monroe, and Sterlington, La., 
and El Dorado, Calion, and Camden, Ark. Two 
grain-handling facilities and a petroleumloading 
facility are in the vicinity of Jonesville, 
La., and a grain-handling facility is in the vicinity 
of Acme, La. 
Operations and results during fiscal year. 
Extensive flooding during the last half of the 
fiscal year hampered progress of going contracts. 
Planning and design for other features in the 
Jonesville and Columbia pools are continuing. 
Planning and design for Calion and Felsenthal 
Locks and Dams are in progress. The Columbia 
and Jonesville Locks were in operation, and a 9- 
foot navigation channel to Sterlington, La., was 
maintained. The remaining portion of the 
navigation channel was maintained at the 
existing 6.5-foot project depth. 
Channel surveys taken after the 1973, 1974, and 
1975 highwater seasons indicated extensive 
scouring in the vicinity of existing locks and dams 
at Jonesville and Columbia, La. 
Condition at end of fiscal year. The 6.5-foot 
project is complete and is being maintained. 
Planning and design for the 9-foot navigation 
project started in fiscal year 1962 and are 
continuing. Construction at Columbia Lock and 
Dam started in February 1964. The dam was 
completed in November 1968, and the lock was 
completed in January 1970 and was placed in 
service in May 1972. Construction at Jonesville 
Lock and Dam started in May 1967. The lock and 
dam were completed in January 1972 and were 
placed in service in March 1972. A 9-foot 
navigation channel to Lock and Dam No. 5 at 
Sterlington, La., was established in June 1972. 
(See Table 12-C on locks and dams, Ouachita and 
Black Rivers, Ark. and La.) 
Two construction contracts for major channel 
repairs at Jonesville and Columbia Locks and 
Dams are scheduled for award early in Fiscal 
Year 1976. 
3. YAZOO RIVER, MISS. 
Location. Formed by junction of Tallahatchie 
and Yalobusha Rivers in Leflore County, Miss., 
12-2

VICKSBURG, MISS., DISTRICT 
flows about 169 miles southerly and 
southwesterly, and enters Mississippi River at 
Vicksburg, Miss. (See Mississippi River alluvial 
valley quadrangle maps.) 
Previous projects. See page 681 of Annual 
Report for 1961 for details. 
Existing project. The Yazoo River Navigation 
project consists of a 9-foot channel from its mouth 
to Greenwood, Miss., mile 164.9 (present 
mileage), with a minimum width of 150 feet. The 
project includes a single lock (84 feet by 600 feet) 
and a dam located near Vicksburg, dredging and 
channel realinement; 600,000 acre-feet of 
additional storage in Sardis Lake to augment low 
flows in the Yazoo River, and recreation features. ' 
Total estimated (1975) Federal cost of 9-foot 
project is $119,000,000. Total estimated non- 
Federal cost is $1,470,000. 
Local cooperation. None required on previous 
project. In connection with the 9-foot navigation 
project, local interests will be required to: 
a. Provide all lands, easements, rights-of-way, 
and flowage rights in overflow areas required for 
construction and subsequent maintenance of the 
project, except at Sardis Lake; 
b. Provide land for aids to navigation upon the 
request of the Chief of Engineers; 
c. Provide suitable areas determined by the 
Chief of Engineers to be required in the general 
public interest for initial and subsequent disposal 
of spoil, necessary retaining dikes, bulkheads, 
and embankments therefor, or the cost of such 
retaining works; 
d. Hold and save the United States free from 
damages due to the construction works and 
subsequent operation and maintenance, 
including but not limited to those resulting from 
dredging, change in groundwater level, and wave 
action; 
e. Provide and maintain, without cost to the 
United States, adequate public terminal and 
transfer facilities, including berths and access 
channels, open to all on equal terms; 
f. Accomplish alterations and relocations as 
required, except for those required for increasing 
capacity of Sardis Lake, including a portion of the 
cost of alteration of the State highway bridge at 
Belzoni, to be determined subsequent to 
authorization in accordance with the principles of 
Sec. 6 of the Bridge Alteration Act of Jun. 21, 
1940, as amended; 
g. Contribute or repay to the United States an 
amount equal to one-half the separable cost of 
recreation features and assume responsibility for 
operation and maintenance of these facilities to be 
provided as a part of this project; and 
h. Comply with the provisions of the Uniform 
Relocation Assistance and Real Property 
Acquisition Policies Act of 1970 (Public Law 91- 
646) and Sec. 221 of Public Law 91-611. 
Terminal facilities. At Greenwood there is a 
privately owned dock and a grain-loading 
facility. There are privately owned facilities for 
loading grain at Belzoni and Satartia. At Yazoo 
City there is a privately owned, grain-loading 
facility, a private log-loading facility, a private 
dock to handle dry and liquid fertilizer, and a 
public terminal. At Mississippi Valley Portland 
Cement Company plant near Redwood, Miss., 
there is a privately owned dock to unload stone 
and shell. 
Operations and results during fiscal year. 
Maintenance clearing and snagging was done as 
required on the old authorized project. 
Condition at end of fiscal year. Entire river is 
navigable (no work done on new authorization). 
4. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 12-D. 
5. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, 
Public Law 87-645, as amended 
(preauthorization). 
A detailed project report was initiated on 
Rosedale Harbor, Miss., in February 1975. Fiscal 
year cost was $37,421. 
Flood Control 
6. OUACHITA RIVER 
TRIBUTARIES, ARK. AND LA. 
AND 
Location. Improvements comprising 
comprehensive project are on main stem 
Ouachita River, Ark. and La., on its tributaries, 
Caddo and Little Missouri Rivers, and in Pine 
Bluff, Ark. Description of Ouachita River Basin 
is presented in greater detail on page 690 of 
Annual Report for 1962. 
Existing project. The authorized general plan 
for flood control and other purposes in the 
Ouachita River Basin includes the projects listed 
in Table 12-E. The 1966 Flood Control Act 
modified the Bayou Bartholomew and 
Tributaries, Ark. and La., project to include 10 
water-retention lakes in the western tributaries 
of Bayou Bartholomew in Arkansas and six local 
levee units along the main stem of the bayou in 
Louisiana. 
Local cooperation. Fully complied with for 
completed features of comprehensive project. 
(See individual statements for further details.) 
12-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Operations and results during fiscal year. 
Operations for Blakely Mt. Dam-Lake Ouachita, 
DeGray Lake, Narrows Dam-Lake Greeson, 
Bayou Bartholomew and Tributaries, Monroe 
Floodwall, and Ouachita River Levees are shown 
in individual reports herein. 
Condition at end of fiscal year. Pertinent data 
on those features which are complete or not 
started are in Table 12-E. Conditions of Blakely 
Mt. Dam-Lake Ouachita, DeGray Lake, and 
Narrows Dam-Lake Greeson are given in the 
following individual reports: 
6A. BLAKELY MOUNTAIN DAM-LAKE 
OUACHITA, OUACHITA RIVER, ARK. 
Location. This project is on Ouachita River, 
Ark., at head of Lake Hamilton (pool of Carpenter 
Dam), 486 miles above mouth of Black River, and 
approximately 10 miles northwest of Hot 
Springs, Ark. 
Previous project. See page 693 of Annual 
Report for 1962 for details. 
Existing project. A lake of 2,768,000 acre-feet 
storage capacity for flood control and other 
purposes with an installed power capacity of 
75,000 kilowatts. Remaining work consists of 
completion of public-use facilities. Latest 
approved (1975) estimated project cost is 
$37,470,000. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Power production totaled 290,034,000 kilowatthours, 
of which 288,554,000 kilowatt-hours were 
delivered to Arkansas Power and Light Co., 
under contract between that company and 
Southwestern Power Administration. Pool 
elevation of 581.2 feet above mean sea level, or 3.2 
feet above maximum power pool, on Jun. 30, 1975, 
was maximum pool elevation for fiscal year. 
Storage in the flood control pool amounted to 
131,100 acre-feet. Peak inflow was 93,200 cubic 
feet per second on Mar. 28, 1975. On Jun. 30, 1975, 
pool elevation was 577.1 feet above mean sea level, 
and storage in the power pool amounted to 
1,249,200 acre-feet. 
Condition at end of fiscal year. Project was 
started in August 1947 and was completed for 
beneficial use in October 1955, except for publicuse 
facilities. Generation of power and operation 
and maintenance activities are continuing. 
Remote control equipment has been installed to 
operate the power plants at DeGray Lake and 
Narrows Dam-Lake Greeson. 
6B. DEGRAY LAKE, CADDO RIVER, ARK. 
Location. On Caddo River (mile 8), a tributary 
of Ouachita River, in a narrow, rocky gorge in 
Clark and Hot Spring Counties, approximately 
7 miles north of Arkadelphia, Ark. 
Existing project. Provides for a lake of 881,900 
acre-feet storage capacity for flood control, water 
supply, pollution abatement, and power with an 
installed power capacity of 68,000 kilowatts (one 
conventional 40,000-kilowatt generating unit and 
one 28,000-kilowatt generating unit with 
reversible pump-type turbine). Latest approved 
(1975) estimated first cost is $69,400,000, 
including $5,800,000, for water supply, to be 
reimbursed by local interests, exclusive of 
interest. 
Local cooperation. None required for flood 
control and power features. Fully complied with 
for water supply feature. 
Operations and results during fiscal year. 
Power production totaled 134,470,000 kilowatthours, 
of which 132,957,000 kilowatt-hours were 
delivered to Arkansas Power and Light Co., 
under contract between that company and 
Southwestern Power Administration. A pool 
elevation of 410.6 feet above mean sea level, or 2.6 
feet above maximum power pool, on Mar. 30, 
1975, was maximum pool elevation for the fiscal 
year. Storage in the flood control pool amounted 
to 36,000 acre-feet. Peak inflow was 30,600 cubic 
feet per second on Nov. 24, 1974. On Jun. 30, 1975, 
pool elevation was 406.7 feet above mean sea level, 
and storage in the power pool amounted to 
376,200 acre-feet. 
Condition at end of fiscal year. Construction 
started in June 1962 and was essentially complete 
in December 1971. All major construction is 
complete including the remote control for the 
power plant from Blakely Mt. Dam-Lake 
Ouachita. Items of work not yet under contract 
include recreational facilities and minor road 
construction. 
6C. NARROWS DAM-LAKE GREESON, 
LITTLE MISSOURI RIVER, ARK. 
Location. Narrows Dam is on the Little 
Missouri River, Ark., 105 miles above the mouth 
and 5 miles northwest of Murfreesboro, Ark. 
Existing project. Provides a lake of 407,900 
acre-feet storage capacity for flood control and 
other purposes with power installation of 25,500 
kilowatts in three units of 8,500 kilowatts each. 
Remaining work consists of completion of publicuse 
facilities. Latest approved (1975) estimated 
cost is $16,077,000, excluding $1,738,700 for third 
generating unit and remote control equipment. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Power production totaled 59,815,000 kilowatthours, 
of which 59,185,280 were delivered to 
Southwestern Electric Power Company under 
12-4

VICKSBURG, MISS., DISTRICT 
contract between that company and 
Southwestern Power Administration. Pool 
elevation of 550.0 feet above mean sea level, or 2.0 
feet above maximum power pool, on Jul. 1, 1975, 
was maximum pool elevation for fiscal year. 
Storage in the flood control pool amounted to 
14,500 acre-feet. Peak inflow was 23,200 cubic 
feet per second on Feb. 1, 1975. On Jun. 30, 1975, 
pool elevation was 547.6 feet above mean sea level, 
and storage in the power pool amounted to 
199,300 acre-feet. 
Condition at end of fiscal year. Project was 
started in May 1947 and was completed for 
beneficial use in May 1950. The third power 
generating unit was completed in January 1970. 
Installation of remote control equipment was 
completed in June 1972. Generation of power, 
operation, and maintenance is continuing. 
Remote control equipment has been installed for 
operation of the power plant from Blakely Mt. 
Dam-Lake Ouachita. 
6D. BAYOU BARTHOLOMEW AND 
TRIBUTARIES, ARK. AND LA. 
Location. Bayou Bartholomew rises in 
Jefferson County, Ark., about 10 miles northwest 
of Pine Bluff and flows southerly about 370 miles 
to join the Ouachita River upstream from 
Sterlington, La. 
Existing project. Project includes 10 waterretention 
lakes in the western tributaries of 
Bayou Bartholomew in Arkansas and six local 
levee units along the main stem of Bayou 
Bartholomew in Louisiana. However, because of 
public opposition to construction of the loop 
levees, preconstruction planning of the six loop 
levees has been deferred until such time as there 
is sufficient support for such levees by local 
interests. Channel improvements previously 
authorized are deferred until it is determined 
that the quality and quantity of water 
downstream will not be adversely affected. Latest 
approved (1975) estimated cost of new work is 
$33,480,000 including $32,100,000 Federal and 
$1,380,000 non-Federal. 
Local cooperation. Local interests will be 
required to: 
a. Furnish free of cost to the United States all 
lands, easements, and rights-of-way necessary for 
construction of the improvements, with the 
exception of lands for the 10 lakes along the west 
escarpment of the Bayou Bartholomew Basin; 
b. Hold and save the United States free from 
damages due to the construction works; 
c. Maintain and operate the levee works in 
accordance with regulations prescribed by the 
Secretary of the Army; 
d. Agree not to construct permanent irrigation 
dams in Bayou Bartholomew with crest 
elevations more than 5 feet above the thalweg of 
the stream; and 
e. Comply with the provisions of the Uniform 
Relocation Assistance and Real Property 
Acquisition Policies Act of 1970 (Public Law 91- 
646) and Sec. 221 of Public Law 91-611. 
Also, local interests must furnish assurances 
satisfactory to the Secretary of the Army that, in 
accordance with the Federal Water Project 
Recreation Act, they will: 
a. Administer project land and water areas for 
recreation and fish and wildlife enhancement; 
b. Pay, contribute in kind, or repay, which may 
be through user fees, with interest, one-half of the 
separable cost of the lake projects allocated to 
recreation and fish and wildlife enhancement; 
and 
c. Bear all costs of operation, maintenance, and 
replacement of recreation and fish and wildlife 
lands and facilities. 
Operations and results during fiscal year. 
Preconstruction planning and design have been 
deferred pending favorable benefit-cost ratios. 
Condition at end of fiscal year. Initial field data 
have been obtained and analyzed; sites have been 
selected for the individual lakes; and preparation 
of general design memorandum has been 
deferred due to lack of economic justification. 
6E. MONROE FLOODWALL, LA. 
Location. Monroe, La., lies within the alluvial 
valley of the Mississippi River and on the east 
bank of the Ouachita River. The city is located in 
the north-central part of Louisiana, in Ouachita 
Parish. 
Existing project. Provides for construction of 
floodwall to close the 1,750-foot opening 
extending from Bry Avenue to Grammont Street. 
Floodwall will provide complete flood protection 
to the city of Monroe. Approved (1975) estimated 
Federal cost of new work is $2,420,000. Non- 
Federal cost is $206,000. 
Local cooperation. Assurances of local 
cooperation have been furnished by the Tensas 
Basin Levee District, agreeing to furnish all 
lands, easements, and rights-of-way necessary for 
construction of the project; accomplish all 
relocations and alterations of streets, buildings, 
equipment, utilities, and other obstructions made 
necessary by the construction works; hold and 
save the United States free from damages due to 
the construction works; maintain and operate all 
of the works after completion in accordance with 
regulations prescribed by the Secretary of the 
Army; comply with the provisions of the Uniform 
Relocation Assistance and Real Property 
12-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Acquisition Policies Act of 1970 (Public Law 91- 
646), and Sec. 221 of Public Law 91-611. 
Operations and results during fiscal year. 
Planning and design were completed. 
Condition at end of fiscal year. Plans and 
specifications for this work are complete; funds 
are available and bids will be invited as soon as 
rights-of-way for construction are made available 
in the first quarter of Fiscal Year 1976. The 
construction contract is scheduled for award in 
October 1975 with a scheduled completion date of 
December 1976. 
6F. OUACHITA RIVER LEVEES, LA. 
Location. East bank of Ouachita River between 
Bastrop, La., and Sandy Bayou. Loop levees on 
the west bank at West Monroe, Columbia, and 
Bawcomville. 
Existing project. There are 105.9 miles of levee 
on the east bank and 11.6 miles of levee in the 
three loops on the west bank. Approved (1975) 
estimated Federal cost is $7,500,000. Estimated 
non-Federal cost is $16,000. 
Local cooperation. Local interests have 
furnished assurances that they will: 
a. Furnish all lands, easements, and rights-ofway 
necessary for construction of the project; 
b. Accomplish all relocations and alterations of 
streets, buildings, equipment, utilities, and other 
obstructions made necessary by the construction 
works; 
c. Hold and save the United States free from 
damages due to construction works; 
d. Maintain and operate all the works after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; and 
e. Comply with the provisions of the Uniform 
Relocation Assistance and Real Property 
Acquisition Policies Act of 1970 (Public Law 91- 
646). 
Operations and results during the fiscal year. A 
construction contract to enlarge 10.4 miles of 
levee (Item 1, Monroe to Sandy Bayou) was 
awarded in July 1974. High water in the winter of 
1974 and spring of 1975 has delayed completion. 
Condition at end of fiscal year. The completed 
levee system does not provide the degree of 
protection intended in the original project. The 
authorized plan of improvement includes 40.4 
miles of levee enlargement, a 5.7-mile extension, 
and gravel surfacing required to provide the 
needed protection. 
Other inadequacies in the levee system, which 
cannot be corrected under existing project 
authority, are being emphasized in a letter report 
which is scheduled for submission in the latter 
part of Fiscal Year 1976. The remaining 
construction has been deferred pending the 
outcome of the Ouachita Basin study. 
7. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was 
accomplished at a cost of $118,315 for the fiscal 
year. Total cost as of end of Fiscal Year 1975 is 
$495,443. 
8. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 12-F. 
9. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities--repair, 
flood fighting, and rescue work. (Public Law 99, 
84th Cong., and antecedent legislation.) 
See Table 12-G. 
Snagging and clearing of navigable streams and 
tributaries in the interest of flood control (Sec. 208 
of 1954 Flood Control Act, Public Law 780, 83d 
Cong.). 
No activity during the fiscal year. 
Emergency bank protection (Sec. 14 of 1946 
Flood Control Act, Public Law 526, 79th Cong.). 
A project to stabilize approximately 2,000 feet 
of bank erosion at Lake Providence, La., was 
approved in October 1973; however, due to 
problems on finalizing assurances of local 
cooperation with Louisiana State Highway 
Department, a contract for this work will not be 
awarded until Fiscal Year 1976. Expenditures 
amounted to $1,931. 
Request for investigation of emergency bank 
protection at three -bridges in Washington 
County, Miss., was approved. Study funds are not 
available. 
A project to stabilize the banks of the 
Homochitto River to protect the U. 8. Highway 
98 bridge was approved in June 1975. 
Construction funds are not available. 
A request for protection for the Belmont bridge 
over the Little Tallahatchie River in Panola 
County, Miss., was received in May 1975 and a 
reconnaissance report has been initiated. 
A request for protection for a Holmes County, 
Miss., bridge over Black Creek was received in 
June 1975 and a reconnaissance report has been 
initiated. 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended 
(preauthorization). 
The detailed project report on Gould, Ark., 
12-6

VICKSBURG, MISS., DISTRICT 
dated January 1975, was returned by higher 
authority as being ineligible under this authority. 
Restudy of a reconnaissance report on east 
bank, Yazoo River, at mile 73 below Yazoo City, 
Miss., was terminated. 
A detailed project report was continued on 
Hatcher Bayou and Durden Creek, Warren 
County, Miss. Expenditures amounted to 
$45,160. 
A reconnaissance report was completed and a 
detailed project report initiated on Lead Bayou, 
Bolivar County, Miss. 
General Investigations 
10. SURVEYS 
Total cost for surveys during the fiscal year was 
$393,332 of which $250,561 was for Pine Bluff, 
Ark., flood control study; $52,326 for Lower 
Mississippi Region comprehensive study; $4,306 
for study of Gulf Coast deepwater port facilities; 
$3,281 for deauthorization review; $81,229 for 
inventory of dams; and $1,630 for coordination 
with Soil Conservation Service. 
11. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain information studies are authorized 
by Sec. 206 of the 1960 Flood Control Act, 
as amended. The studies are made upon request 
of another Federal agency, a State, 
or political subdivision thereof. They comprise 
compilation and dissemination of information 
on floods and flood damages, including identification 
of areas subject to inundation by 
floods of various magnitudes and frequencies, and 
general criteria for guidance of Federal 
and non-Federal interests and agencies in 
the use of flood plain areas, and provide advice 
to other Federal agencies and local interests 
for their use in planning to ameliorate the 
flood hazard. 
Fiscal year costs for flood plain management 
services were $292,563, which include $114,689 
($69,172, VXD, and $45,517, LMVD) for flood 
plain management services, $53,464 for technical 
services, and $124,410 for flood plain information 
reports. 
The Hot Springs, Ark., Flood Plain 
Information Report was completed at a total cost 
of $35,881. 
12. RESEARCH AND DEVELOPMENT 
Hydrologic studies: Collecting 
and rainfall data and making 
hydrologic studies during fiscal 
$5,914. 
streamflow 
storm and 
year cost 
12-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 12-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 Jun 30, 1975 
1. Lake Providence 
Harbor, La. 
2. Ouachita and Black 
Rivers Below Camden, 
Ark. (6.5-foot 
navigation project) 
Ouachita and Black 
Rivers Below Camden, 
Ark. (9-foot 
navigation project) 
3. Yazoo River, Miss. 
6A. Blakely Mt. Dam- 
Lake Ouachita, Ouachita 
River, Ark. 
6B. DeGray Lake, 
Caddo River, Ark. 
6C. Narrows Dam-Lake 
Greeson, Little Missouri 
River, Ark. 
6D. Bayou Bartholomew 
and Tributaries, 
Ark. and La. 
6E. Monroe Floodwall, 
La. 
6F. Ouachita River 
Levees, La. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
$- 
53,000 
53,000 
1,466,600 
1,401,010 
5,245,400 
7,881,541 
31,400 
40,400 
191,600 
25,548 
838,100 
829,879 
1,207,499 
2,162,906 
540,200 
533,955 
39,101 
15,582 
434,300 
603,625 
144,000 
155,068 
129,000 
17,477 
159,400 
77,494 
$- 
116,900 
83,900 
1,377,700 
1,289,397 
8,050,000 
3,744,828 
1,600 
1,600 
163,668 
2,306,900 
1,685,826 
3,300,000 
2,640,903 
775,700 
696,491 
118,362 
1,864,400 
1,239,210 
36,298 
505,000 
15,067 
300,000 
139,550 
63,700 
96,700 
3,600,500 
3,708,547 
8,095,000 
11,406,070 
2,600 
2,600 
35,341 
1,723,200 
2,674,677 
583,000 
1,214,771 
853,683 
891,109 
-102 
2,040 
1,263,017 
1,834,674 
2,232 
495,000 
23,771 
$- $ 208,5371 
- 208,5371 
77,000 634,300 
77,000 634,300 
- 5,248,6192 
- 5,248,6192 
1,536,000 
1,680,965 
8,000,000 
5,521,936 
39,200 
39,200 
736,000 
173,090 
1,928,400 
1,642,384 
1,400,000 
946,961 
987,600 
860,890 
432,000 
106,681 
1,310,600 
1,355,576 
8,438 
3,081 
152,000 
490,866 
28,730,326 
28,703,987 
76,937,000 
73,235,336 
359,6613 
359,6613 
794,215 
794,215 
32,755,944 
32,123,685 
13,050,492 
12,686,096 
61,900,992 
60,982,476 
3,455,183 
3,263,785 
15,585,229 
15,251,445 
10,549,337 
10,406,227 
974,000 
967,047 
984,000 
230,148 
1,106,400 
731,681 
1. Actual costs include $198,859 Public Works Acceleration 
Act funds and $9,678 expended for planning and design; 
excludes $35,000 contributed funds, $198,400 cost of retaining 
dikes, and $1,022,000 local interests' costs for port facilities. 
2. Includes $674,068 for new work on previous projects. 
3. All costs are for previous projects. 
12-8

TABLE 12-B 
VICKSBURG, MISS., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 14, 1960, 
as amended 
May 17, 1950 
Jul. 14, 1960 
Dec. 31, 1970 
Mar. 3, 1875 
Aug. 13, 1968 
LAKE PROVIDENCE HARBOR, LA. (See Section 1 
of Text) 
Dredging 0.7-mile channel and turning basin in an old chute 
of the Mississippi River, with the dredged material used to 
fill in a port area provided by local interests. 
OUACHITA AND BLACK RIVERS BELOW 
CAMDEN, ARK. (See Section 2 of Text) 
Modification of existing project to provide for 9-foot channel 
and deepening canal to Felsenthal, Ark. 
Modification of 9-foot project to provide four new locks and 
dams and channel improvements. . 
Migratory waterfowl refuges on Bayou D'Arbonne in connection 
with the pool of the Columbia Lock and Dam and in 
the pool of the Felsenthal Lock and Dam. 
YAZOO RIVER, MISS. (See Section 3 of Text) 
Four-foot channel from mouth to Greenwood, Miss., 
189 miles. 
Nine-foot channel from mouth to Greenwood, mile 154.9 
(present mileage), with a lock and dam near Vicksburg, 
channel improvements, additional storage space in Sardis 
Lake to augment low river flows, and recreation features. 
OUACHITA RIVER AND TRIBUTARIES, ARK. 
AND LA. (See Section 6 of Text) 
Authorized DeGray Lake; Murfreesboro Lake; extension of 
floodwall at Monroe to partially close the existing gap; local 
protection at Bawcomville, La. (subsequently constructed 
under Sec. 6, Act of May 15, 1928, with local interests 
contributing one-third of cost); Bayou Bartholomew 
channel improvement, including Deep Bayou and Overflow 
Creek; Pine Bluff local protection; local protection at 
Calion, Ark.; and incorporation, into the Ouachita River 
and Tributaries project, of all existing projects and 
portions thereof in the basin above the lower end of the 
levees on the east bank of the Ouachita River. In addition, 
the Chief of Engineers authorized on Nov. 14, 1966, 
additional work on the levees. 
BAYOU BARTHOLOMEW, ARK. AND LA. 
(See Section 6D of Text) 
Authorized channel improvements on Bayou and Tributaries 
(see above) 
Modified 1950 authorization to include 10 lakes in the west 
escarpment in Arkansas and 6 local levees in Louisiana, 
and acquisition of lands for mitigation of fish and wildlife 
losses. The previously authorized channel improvement 
was deferred until it is determined that the quality 
and quantity of water downstream will not be adversely 
affected. 
MONROE FLOODWALL, LA. (See Section 6E of Text) 
Partial closure of gap in floodwall 
Closure of gap in floodwall (Plan C) 
Closure of gap in floodwall (Plan B) 
S. Doc. 117, 81st Cong., 
1st sess. 
S. Doc. 117, 81st Cong., 
1st sess. 
H. Doc. 506, 89th Cong., 
2d sess. 
S. Doc. 117, 81st Cong., 
2d sess. 
H. Doc. 328, 88th Cong., 
2d sess. 
H. Doc. 328, 88th Cong., 
2d sess. 
12-9 
Approved Sep. 12, 1962, 
under authority of Sec. 107 
of the River and Harbor Act 
of 1960, as amended. 
S. Doc. 117, 81st Cong., 
1st sess. 
S. Doc. 112, 86th Cong., 
2d sess. 
Report of the Chief of 
Engineers dated Nov. 25, 
1970, and H. Doc. 92-109, 
92d Cong., 1st sess. 
H. Doc. 342, 90th Cong., 
2d sess. 
May 17, 1950 
May 17, 1950 
Nov. 7, 1966 
May 17, 1950 
Oct. 27, 1965 
Nov. 7, 1966

TABLE 12-C OUACHITA AND BLACK RIVERS, ARK. AND LA. 
(9-FOOT PROJECT), LOCKS AND DAMS 
(See Section 2 of Text) 
Min. 
Depth 
Greatest on 
Available Lower 
Miles Length Max. Elev. Miter 
Above Width for Full Lift Normal Sill at 
Miles Mouth of Width at Pool Normal Perfrom 
of Lock of Lock Low Surface Pool Character cent 
Nearest Black Chamber Chamber Water (feet Level or Kind of Com- Estimated 
Location Town River (feet) (feet) (feet) rsl) (feet) Foundation Dam Type of Construction plete Cost 
Jonesville, La. 10 25 84 600 30 34 14 Piling Movable Tainter gated dam; bascule gated 100 $ 41,482,0001 
navigation pass; steel mitering 
lock gates 
Columbia, La. 5 132 84 600 18 52 13 do do Tainter gated dam; fixed crestnavi- 100 32,603,000 
gation pass; steel mitering lock gates 
Felsenthal, Ark. 1 243 84 600 18 65 13 Earth do Tainter gated dam; gated navigation (2) 57,037,000 
pass; steel mitering lock gates 
Calion, Ark. 7 298 84 600 12 77 13 do do do (2) 41,878,000 
Total $173,000,000 
1. Includes $6,113,700 for Catahoula Lake diversion 
channel and control structure. 
2. Construction not started. 
0
y0
yx 
n
x
O
zz 
ID 
co 
CF 
-1

VICKSBURG, MISS., DISTRICT 
TABLE 12-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Bayou Bartholomew, La. and Ark.1,2,3,4 1931 $ 45,874 $ 42,857 
Bayous D'Arbonne and Corney, La.,2, 1941 19,000 37,804 
Big Black River, Miss."4' 1895 15,000 
Big Sunflower River, Miss.l,4A,67 1942 560,027 459,328 
Boeuf River, La." 34, 7, ,8,9 1949 30,000 103,737 
Homochitto River, Miss.4 1910 15,482 8,518 
Little Missouri River, Ark.1,4' 1873 19,992 
Little River, La.14 5 1 1890 1,500 
Little Tallahatchie River, Miss."7 1913 19,000 
Mouth of Yazoo River, Miss.1,7,11 1953 1,179,211 145,217 
Removing snags and wrecks from Mississippi 
River below mouth of Missouri River and 
from Old and Atchafalaya Rivers" 1948 - 272,500 
Saline River, Ark.",3,4 1931 26,900 12,792 
Tallahatchie and Coldwater Rivers 
Miss.14 5 1939 43,481 173,066 
Tensas River and Bayou Macon, La." 8,12 1949 38,367 85,352 
Yalobusha River, Miss.1,4,5,13 1937 7,000 15,936 
1. Completed. 
2. Abandonment recommended in H. Doc. 1692, 
64th Cong., 2d sess., and H. Doc. 467, 69th Cong., 
1st sess. 
3. Channels adequate for existing commerce. 
4. Inactive project. No commerce. 
5. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
6. Project curtailment recommended by elimination 
of work between Pentecost and mouth of Hushpuckena 
River. (Abandonment of entire project erroneously 
recommended in H. Doc. 467, 69th Cong., 1st sess.) 
7. See report of Mississippi River Commission for 
operations in connection with Yazoo Basin. 
8. Report of New Orleans District, pp. 919-920 for 
Fiscal Year 1949. 
9. Project curtailment recommended by elimination of 
work above Girard, La. (Abandonment of entire project 
recommended erroneously in H. Doc. 467, 69th Cong., 
1st sess.) 
10. Due to decline of traffic, local interests not sufficiently 
interested to provide rights-of-way and dumping 
privileges. 
11. No additional funds available under this project. 
Work is being carried on under appropriation flood control, 
Mississippi River and tributaries. 
12. Inactive. Channel adequate for commerce. 
13. See report of Mississippi River Commission 
for operations in connection with Yazoo Basin flood control 
project including channel clearing and rectification and 
Grenada Lake on Yalobusha River. 
12-11

TABLE 12-E 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
OUACHITA RIVER AND TRIBUTARIES: 
EXISTING PROJECT 
(See Section 6 of Text) 
For Last Estimated 
Full Report Federal 
See Annual New Work 
Project Report For Cost 
Blakely Mt. Dam-Lake Ouachita, Ark. (1) $ 37,470,000 
DeGray Lake, Ark. (1) 69,400,0002 
Narrows Dam-Lake Greeson, Ark. (1) 16,077,000 
Calion, Ark. 1960 970,9963 
Columbia, La. 1941 204,7403 
Existing levees and extensions thereto from Bastrop, La., to mouth of 
Boeuf River and at West Monroe, La. 1961 3,025,1813 
Little Missouri River below Murfreesboro, Ark. 1957 354,8023 
Ozan Creek, Ark. 1957 57,7423 
Terre Noire Creek, Ark. 1948 123,7003 
Pine Bluff, Ark., local protection 1954 172,5823 
Monroe, La., floodwall extension (Plan B) (1) 2,420,000 
Bayou Bartholomew and Tributaries, Ark. and La. (1) 32,100,000 
Ouachita River Levees (additional work) (1) 7,500,000 
Total $169,876,7434 
1. See individual reports herein. 4. Excludes the authorized Murfreesboro Lake, Ark., 
2. Includes $5,800,000 for water supply, to be reimbursed project, which is inactive. The latest estimated cost (1954) was 
by local interests. $4,190,000. 
3. Actual cost of completed project. 
TABLE 12-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Big Black River, Miss.1 1956 $910,185 $670,750 
Big Choctaw Bayou, La.2 1966 248,823 
Buffalo River, Miss.3 1940 - 
Homochitto River, Miss.' 1956 205,000 144,650 
Natchez Port Area, Miss.2 1969 538,000 
Murfreesboro Dam and Lake 3 1951 - 
1. Completed. 
2. Authorized by Chief of Engineers under authority 
of Sec. 205, Flood Control Act of 1948, as 
amended, and is complete. 
3. Deferred indefinitely because of insufficient justification 
under present conditions. 
12-12

VICKSBURG, MISS., DISTRICT 
TABLE 12-G FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
(Emergency Flood Control Activities) 
(See Section 9 of the Text) 
Project Federal Cost 
Advance preparation $ 55,838 
Emergency operations 1,912,367 
Rehabilitation: 
Arkabutla Dam 531,373 
Arkansas River Levees 367,475 
Enid Dam 580,781 
Greenwood Local Protection 131,245 
Grenada Dam 429,399 
Jonesville, La. 295,027 
Leflore County (Non-Federal) Levees 196,169 
Leflore County (Non-Federal) Levees 2,950 
Mississippi River Channel Improvements 10,467,349 
Mississippi River Levees 677,588 
Red River Backwater 6,174 
Sardis Dam 540,524 
Tallahatchie County (Non-Federal) Levees 35,000 
Tensas Basin-Boeuf and Tensas 328,117 
Terre Noire Creek Levees 70,479 
Will M. Whittington Auxiliary Channel 55,573 
Yazoo Backwater 83,731 
Yazoo Basin, Tallahatchie River 106,270 
Yazoo City Local Protection 403,677 
Yazoo River Main Stem 3,659 
Total $17,280,765 
12-13

MEMPHIS, TENN., DISTRICT* 
This district comprises a portion of 
southeastern Missouri and southern Illinois, 
western portions of Kentucky and Tennessee, a 
small portion of northern Mississippi, and the 
northeastern portion of Arkansas; includes area 
embraced in drainage basins of eastern 
tributaries of the Mississippi River south of Ohio 
River Basin to Nonconnah and Horn Lake 
Creeks, inclusive, and those of western 
tributaries south of Little River diversion 
channel and Commerce, Mo., including St. 
Francis River Basin and White River and 
tributaries below Peach Orchard Bluff, Ark., on 
the right bank and below Augusta, Ark., on the 
left bank; also includes left bank Mississippi 
River levee from vicinity of Memphis south to 
about mile 620, and right bank levees from Cape 
Girardeau, Mo., to about mile 605. 
IMPROVEMENTS 
Navigation 
1. Helena Harbor, Ark. ............. 
2. Hickman Harbor, Ky. ............ 
3. New Madrid Harbor, Mo. ......... 
4. Osceola Harbor, Ark. ............. 
5. White River, Ark. (below 
Newport) ...................... 
6. Wolf River (Memphis Harbor), 
Tenn. ........................... 
7. Other authorized navigation 
projects ........................ 
8. Navigation work under special 
authorization ................... 
Flood Control 
9. Dyersburg, Tenn. (Southwest) ..... 
Page 
13-1 
13-2 
13-2 
13-2 
13-2 
13-3 
13-3 
13-3 
Flood Control (cont.) 
10. Treasure Island, Mo. ............. 
11. Big Creek Canal, Millington, 
Tenn ......................... 
12. West Hickman area, Ky. .......... 
13. Inspection of completed flood 
control projects ................. 
14. Other authorized flood control 
projects ........................ 
15. Flood control work under special 
authorization ................... 
General Investigations 
16. Surveys ........................ 
17. Collection and study of basic data .. 
13-3 18. Research and development ........ 
Page 
13-4 
13-4 
13-5 
13-5 
13-5 
13-5 
13-6 
13-6 
13-6 
Navigation 
1. HELENA HARBOR, ARK. 
Location. In Phillips County, Ark., on right 
bank of Mississippi River about 663 miles above 
Head of Passes, La. 
Existing project. Authorized by Chief of 
Engineers, Sep. 20, 1962, under authority of Sec. 
107 of the River and Harbor Act of 1960, as 
amended. Provides for maintenance of access 
channel with a depth 9 feet below low water, 
between miles 659 and 663 above Head of Passes, 
La., by dredging, and for enlarging the upstream 
0.6 mile to dimensions of 9 feet deep by 
approximately 450 feet wide. Remainder of 
channel conforms to project width of the main 
channel of Mississippi River. River stages 
recorded at Helena gage (zero is 141.70 feet msl) 
since 1871 have ranged between minus 3.0 and 
plus 60.21 feet with an average annual 
fluctuation of 40.6 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 10 terminals 
within the harbor, two of which are publicly 
owned. Others are a rail incline, a small boat 
dock, grain terminals, a petroleum products 
terminal, a midstream grocery and refueling 
service, a fuel unloading facility, and a fertilizerloading 
facility. 
*All cost and financial statements and authorizing legislation for projects are listed at the end of this chapter. All other tables 
are referenced in text and also appear at the end of this chapter. 
13-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Operations and results during fiscal year. 
Leased dredge Diesel removed 271,029 cubic 
yards in maintaining project channel. 
Expenditure was $94,412. 
Condition at end of fiscal year. Project is 
complete and maintained to project dimensions. 
2. HICKMAN HARBOR, KY. 
Location. In Fulton County, Ky., on left bank of 
Mississippi River about 922 miles above Head of 
Passes, La. 
Existing project. Authorized by Chief of 
Engineers, Jul. 12, 1962, under authority of Sec. 
107 of the River and Harbor Act of 1960, as 
amended. Provides for dredging and 
maintaining harbor channel 250 feet wide with 
depth of 9 feet below low water, from main 
channel of Mississippi River at mile 922 AHP 
along former city waterfront about 1.1 miles, 
with the upper 600 feet forming a turning basin 
500 feet wide. New work was completed in Fiscal 
Year 1963. River stages recorded since 1929 at 
Hickman gage (zero is 264.73 feet msl) have 
ranged between minus 0.4 and plus 51.5 feet with 
average annual fluctuation of 38 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Within harbor are 
terminals for handling petroleum products, sand 
and gravel, timber, and grain, all private; there is 
about 0.2 mile of surfaced, public mooring and 
launching area. 
Operations and results during fiscal year. 
Leased dredge BDCO No. 32 removed 295,946 
cubic yards in maintaining project channel. 
Expenditure was $92,180. 
Condition at end of fiscal year. Project is 
complete and maintained to project dimensions. 
3. NEW MADRID HARBOR, MO. 
Location. New Madrid County, Mo., on right 
bank of the Mississippi River about 889 miles 
above Head of Passes, La. 
Existing project. Construction and subsequent 
maintenance of a harbor channel 150 feet wide 
with a depth of 9 feet below low water from the 
head of New Madrid Bar, about mile 889 AHP, 
along the city waterfront downstream for a 
distance of about 9,400 feet, with a 250-footradius 
turning basin at the downstream end. The 
project was authorized by the Chief of Engineers, 
Feb. 21, 1968, under Sec. 107 of the River and 
Harbor Act of 1960, as amended. 
Local cooperation. Fully complied with. 
Terminal facilities. Within the harbor are 
privately owned terminals for handling 
petroleum products, logs and lumber, and 
soybeans and grain. Terminal facilities are 
considered adequate for present and immediately 
foreseeable commerce. 
Operations and results during fiscal year. 
Leased dredge BDCO No. 32 removed 182,683 
cubic yards in maintaining project channel. Cost 
for maintenance was $71,005. 
Condition at end of fiscal year. Project is 
complete and maintained to project dimensions. 
4. OSCEOLA HARBOR, ARK. 
Location. Mississippi County, Ark., on the right 
bank of the Mississippi River at about 784 miles 
above Head of Passes, La. 
Existing project. The project was authorized by 
'the Chief of Engineers, Sep. 30, 1971, under Sec. 
107 of the River and Harbor Act of 1960, as 
amended. Harbor channel construction consisted 
of removal of 689,705 cubic yards of material 
from the harbor channel to provide a navigation 
channel 250 feet wide and 9 feet deep from the 
Mississippi River navigation channel at the 
downstream end of the old chute of Island 30, 
upstream along the old bendway channel for a 
line distance of 6,500 feet. A 250-foot-radius 
turning basin is provided at the upstream end of 
the harbor channel. The excavated material 
removed from the channel was placed on the top 
bank between the old bendway channel and the 
main line Mississippi River levee to form a floodfree 
industrial park to be developed by local 
interests. Latest published map is in 1974, 42d 
edition, Flood Control and Navigation Maps of 
the Mississippi River, prepared under the 
direction of President, Mississippi River 
Commission. 
Local cooperation. Fully complied with. 
Terminal facilities. Public terminal facilities 
have been provided by Osceola Riverport 
Authority. 
Operations and results during fiscal year. 
Construction was completed in November 1974 at 
a total cost of $269,115. 
Condition at end of fiscal year. Project is 
complete and being maintained to project 
dimensions. 
5. WHITE RIVER, ARK. (BELOW 
NEWPORT) 
Location. Rises in northwestern Arkansas and 
flows 686 miles first north into Missouri, thence 
southeasterly through Arkansas to the 
Mississippi River 64 miles below Helena, Ark. 
(See Mississippi River Commission alluvial 
valley maps, scales 1:62,500 and 1:500,000, and 
maps of White River, vicinity of Batesville, Ark., 
to Mississippi River, scale 1:62,500.) White River 
enters Memphis District at foot of Peach Orchard 
13-2

MEMPHIS, TENN., DISTRICT 
Bluff, Ark., 165 miles above its mouth; but 
Memphis District is responsible for maintenance 
of navigation channel as far upstream as 
Newport, Ark., mile 255. 
Previous projects. For details, see page 1874, 
Annual Report for 1915, and page 938, Annual 
Report for 1938. 
Existing project. Maintenance of a channel 4.5 
feet deep by 100 feet wide between mouth of river 
and Batesville, 296 miles, by snagging, dredging, 
and contraction works. Maintenance 
discontinued after Fiscal Year 1951 due to 
negligible traffic; dredging and snagging 
resumed in 1962. White River channel from 
mouth to mile 10 has been improved and is being 
maintained as part of the Arkansas River Project. 
The existing project was modified by OCE, Mar. 
11, 1968, under authority of Sec. 107 of the 1960 
River and Harbor Act, as amended, to provide a 
125-foot-wide channel with minimum depth of 5 
feet and a depth of 8 feet at a stage of 12 feet on the 
Clarendon gage. This modification has been 
completed and increased dimensions extend from 
the mouth to Augusta, at mile 199. In February 
1971, OCE authorized maintenance from 
Augusta to Newport. 
Local cooperation. Fully complied with. 
Terminal facilities. Consist of terminals for 
handling riprap stone, sand and gravel, logs, 
soybeans, wheat, and rice at Augusta (mile 198); 
logs, soybeans, wheat, and rice at Des Arc (mile 
143); logs, lumber, soybeans, and rice at 
Clarendon (mile 99); soybeans at Crocketts Bluff 
(mile 68); soybeans, rice, sand, gravel, and 
crushed stone at St. Charles (mile 57); riprap 
stone at Benzal (mile 7.5), and public launching 
ramp at I-40 bridge. 
Operations and results during fiscal year. 
Dredging was performed at various locations 
between mile 10 and mile 255 to provide project 
width and depth. Leased dredge, Dredge II, 
moved 1,038,111 cubic yards in maintaining 
project channel. Maintenance costs were 
$656,598. 
Condition at end of fiscal year. The project, 
authorized in 1892, is for maintenance, and 
completion is not contemplated. Project depth at 
low water is maintained by dredging as required. 
6. WOLF RIVER (MEMPHIS HARBOR), 
TENN. 
Location. Rises near western edge of Tippah 
County, Miss., and flows generally northwesterly 
through Shelby County, Tenn., entering the 
Mississippi River above Memphis, Tenn. (mile 
738.7 AHP). The lower 3.5 miles of channel, 
parallel to the Mississippi River along the 
Memphis waterfront, became a slack-water 
harbor when Wolf River was diverted through 
Mud Island to the Mississippi River by a flood 
control project, Wolf River and tributaries, under 
the Flood Control Act of 1958. (See Mississippi 
River Commission alluvial valley maps, scales 
1:62,500 and 1:500,000, and folio of Flood Control 
and Navigation Maps of the Mississippi River, 
Cairo, Ill., to Gulf of Mexico, scale 1:62,500, 
revised annually.) 
Previous projects. For details see pages 701 and 
702, Annual Report for 1962. 
Existing project. The project provides a channel 
9 feet deep at low water from mouth to mile 3, 
with bottom widths of 250 feet from mouth to Keel 
Avenue (mile 1.75) and 200 feet from Keel Avenue 
to mile 3. 
Local cooperation. Fully complied with. 
Terminal facilities. Twenty terminals along 
project channel. One terminal is operated by 
Coast Guard, two by contract carriers, and 17 are 
operated privately. 
Operations and results during fiscal year. 
Maintenance dredging was performed with one 
leased dredge, the Diesel, which moved 132,177 
cubic yards of material to maintain project 
channel at a cost of $54,995. 
Condition at end of fiscal year. Project is 
complete and maintained by dredging as 
required. 
7. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 13-C. 
8. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, 
Public Law 86-645, as amended 
(preauthorization). 
Fiscal year costs were $7,463 for a study and 
report on Mississippi River, Caruthersville 
Harbor, Mo. 
Flood Control 
9. DYERSBURG, TENN. (SOUTHWEST) 
Location. The city is situated on the bank of the 
North Fork of the Forked Deer River 5 miles 
upstream from the confluence of the North Fork 
and Forked Deer River. The project is located in 
the Finley Street area in the southwestern section 
of Dyersburg north of the river in the low area 
between U. S. Highway 51 and U. S. Highway 51 
Bypass. 
Existing project. Authorized Jun. 27, 1972, 
under authority of Sec. 205 of the Flood Control 
13-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Act of 1948, as amended. Construction of a levee 
beginning at the Highway 51 Bypass and 
extending 2,000 feet northeast, then 2,200 feet 
east to the levee around the sewage treatment 
plant on the south and east sides, and construction 
of a levee from the northeast corner of the 
treatment plant northeasterly to high ground just 
south of the Illinois Central Railroad. Excavation 
of 23 acres on the landside of the levee to elevation 
254.0 feet msl for providing additional storage 
and construction of a 100-cfs pumping station and 
an 8- by 8-foot concrete box culvert with sluice 
gate to evacuate interior drainage from the 
excavated sump. Construct an 84-inch 
corrugated metal culvert with flap gate to 
evacuate interior drainage from an area 
northeast of the sewage treatment plant. 
Construction of landside drainage ditches along 
the levee to divert drainage to excavated area and 
transition existing ditches into excavated sump to 
insure proper operation of the project as 
designed. Construct an outlet channel into North 
Fork, Forked Deer River. Construction scars and 
waste areas will be graded to blend into the 
existing terrain. The levees and excavated areas 
will be seeded and/or sodded and fertilized to 
provide erosion protection and improve the 
appearance of the area. After completion of the 
final grading, the entire sump area will be 
landscaped with water-tolerant trees. 
Local cooperation. Provide without cost to the 
United States all lands, easements, rights-of-way, 
utility relocations and alterations, and highway 
or highway bridge construction and alterations 
necessary for project construction. Hold and save 
the United States free from damages due to the 
construction works. Maintain and operate the 
project after completion without cost to the 
United States in accordance with regulations 
prescribed by the Secretary of the Army. Bear all 
costs of project construction in excess of the 
$2,000,000 Federal cost limitation. Prevent 
future encroachment which might interfere with 
proper functioning of the project for flood control. 
Restrict fills on lands below elevation 269 feet on 
landside of the levee outside of the proposed 
renewal area and future sewage treatment plant, 
and adopt flood plain regulations necessary to 
insure compatibility between future 
development and the degree of flood protection 
afforded in the project area. Comply with the 
provisions of the Uniform Relocation Assistance 
and Real Property Acquisition Policies Act of 
1970, Public Law 91-646. Accept the 
responsibility and liability to fully comply with 
the provisions of Sec. 221 of the Flood Control Act 
of 1970, Public Law 91-611. The city of 
Dyersburg, Tenn., has provided the necessary 
assurances of local cooperation requirements. 
Operation .and results during fiscal year. A 
contract for construction was awarded in Fiscal 
Year 1974. Actual construction began this fiscal 
year; cost to date $1,081,490. 
Condition at end of fiscal year. Construction is 
approximately 66 percent complete. Scheduled 
completion is August 1976. 
10. TREASURE ISLAND, MO. 
Location. In Dunklin County, Mo., in the Little 
River Drainage District of the St. Francis River 
Basin near Hornersville, Mo. 
Existing project. Authorized by the Chief of 
Engineers, Feb. 21, 1973, under authority of Sec. 
205, Flood Control Act of 1948, as amended. 
Provides for the installation of a 150-cfs 
electrically powered pumping plant. The new 
pumping units, combined with the existing 25-cfs 
pump, will have a total capacity of 175 cfs. 
Provides flood protection for 7,800 acres of land, 
of which 7,100 are cleared. 
Local cooperation. Local interests have 
furnished the required assurances. 
Operations and results during fiscal year. A 
contract for construction was awarded in August 
1974 with actual work commencing shortly 
thereafter. Expenditure was $121,645. 
Condition at end of fiscal year. Approximately 
30 percent complete. Scheduled completion is 
August 1976. 
11. BIG CREEK CANAL, MILLINGTON, 
TENN. 
Location. Big Creek, a tributary of the 
Loosahatchie River, lies within the southwest 
Tennessee counties of Tipton and Shelby. The 
portion of stream covered by the project is near 
the city of Millington and the adjacent Naval Air 
Station. 
Existing project. Approved Dec. 14, 1973, 
under authority of Sec. 2, Flood Control Act of 
1937, as amended by Sec. 208 of the 1954 Flood 
Control Act. The project consists of channel 
cleanout on Big Creek Canal extending from 
Highway 51 upstream to the Naval Air Station 
for a distance of about 12,700 feet. The channel 
restoration work consists of removal of felled 
trees and other debris resulting from bank 
caving. 
Local cooperation. Shelby County, Tenn., 
provided assurances that it will provide without 
cost to the United States all lands, easements, 
rights-of-way, utility relocations and alterations, 
and highway or highway bridge construction and 
alterations necessary for project construction; 
hold and save the United States free from 
damages due to the construction works and adjust 
all claims concerning water rights; maintain and 
13-4

MEMPHIS, TENN., DISTRICT 
operate the project after completion without cost 
to the United States in accordance with 
regulations prescribed by the Secretary of the 
Army; prevent future encroachment which 
might interfere with proper functioning of the 
project for flood control; comply with provisions 
of the Uniform Relocations Assistance and Real 
Property Acquisition Policies Act of 1970; and 
comply with provisions of Sec. 221, Public Law 
91-611. In addition, the sponsor will be required 
to be responsible for and defray all project 
construction costs exceeding $250,000. 
Operation and results during fiscal year. A 
contract for construction was awarded. 
Expenditure was $3,968. 
Condition at end of fiscal year. Construction 
work scheduled for initiation and completion in 
Fiscal Year 1976. 
12. WEST HICKMAN AREA, HICKMAN, 
KY. 
Location. The project is located in the western 
section of the city of Hickman, Fulton County, Ky. 
The area is protected from flooding by the 
Mississippi River by a levee and floodwall on the 
west. 
Existing project. Authorized Nov. 9, 1973, 
under authority of Sec. 205 of the 1948 Flood 
Control Act, as amended. The plan of 
improvement consists of installing a flap gate on 
the existing box culvert through the old levee to 
prevent backwater flooding from Bayou du 
Chien, excavation of a 3.8-acre sump area, and 
construction of a 190-cfs pumping plant to reduce 
flooding from interior runoff. About 800 feet of 
interior channel will be reshaped through the 
excavated sump area, 190 feet of new outlet ditch 
will be built from the pump discharge to the 
existing outlet ditch, and 300 feet of the existing 
ditch is to be cleaned out and/or enlarged. 
Local cooperation. Provide without cost to the 
United States all lands, easements, rights-of-way, 
utility relocations and alterations, and highway 
or highway bridge construction and alterations 
necessary for project construction; hold and save 
the United States free from damages due to the 
construction works and adjust all claims 
concerning water rights; maintain and operate 
the project after completion without cost to the 
United States in accordance with regulations 
prescribed by the Secretary of the Army; assume 
full responsibility for all project costs in excess of 
the Federal cost limitation; prevent future 
encroachment which might interfere with proper 
functioning of the project for flood control; 
provide a contribution toward construction costs 
where special local benefits will accrue in 
accordance with existing policies for regularly 
authorized projects; provide a cash contribution 
for project costs assigned to project features other 
than flood control; comply with the provisions of 
the Uniform Relocation Assistance and Real 
Property Acquisition Policies Act of 1970, Public 
Law 91-646; and accept the responsibility and 
liability to fully comply with the provisions of Sec. 
221 of the Flood Control Act of 1970, Public Law 
91-611. The city of Hickman has furnished the 
required local cooperation assurances. 
Operations and results during fiscal year. A 
contract for construction was awarded in July 
1974. Expenditure was $608,906. 
Condition at end of fiscal year. Approximately 
49 percent complete. Scheduled for completion in 
1976 "T" quarter. 
13. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspected 91 completed projects at a fiscal year 
cost of $96,350. Total costs to Jun. 30, 1975, were 
$226,686. 
14. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 13-D. 
15. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended 
(preauthorization). Fiscal year costs for 
preauthorization (detailed project) studies were 
$4,404 for Beech Creek, Wickliffe, Ky.; $20,293 
for Cowpen Creek, Horn Lake, Miss.; $4,768 for 
Cypress Creek, Memphis, Tenn.; $4,881 for Days 
Creek, Memphis, Tenn.; $76,264 for Drinkwater 
Sewer, Mo.; $13,773 for Inter-River Drainage 
District, Vicinity of Qulin, Mo.; $13,981 for 
Helena, Ark.; $20,131 for Huntingdon, Tenn.; 
$3,450 for Martin Branch, Clarendon, Ark.; 
$37,665 for North Fork of Big Creek, Millington, 
Tenn.; $24,627 for Rocky Creek, Miss.; $20,432 for 
Southaven Creek, Miss.; $4,000 for Tar Creek, 
Tenn.; $31,581 for West Helena, Ark.; and 
$25,636 for Whitemans Creek, Jonesboro, Ark. 
Emergency bank protection (Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.) Bank 
protection on Wolf River at Interstate 240 at a 
cost of $121,676. 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). Federal 
costs were $31,993 for advance preparation; 
$3,191,929 for flood emergency activities; and 
$10,059 for postflood disaster reports. 
13-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Expenditures for rehabilitation of flooddamaged 
protective works were $163,268 for 
levee repair in Dyer County, Tenn.; $20,257 for 
Castor River levee repairs; $3,055,008 for repair 
of Mississippi River levees; $39,111 for repairs on 
LaForge, Mo., and Barfield, Ark., revetments; 
$248,703 on Mississippi River at Commerce, Mo.; 
$23,626 on Mississippi River near Blytheville, 
Ark.; $26,313 on Farrenburg levee north of New 
Madrid, Mo.; $917,558 on Island 63 Bar 
revetment, Miss.; $25,485 on West Levee at 
Mound City, Ill.; $15,499 on Robinson Crusoe 
Dikes, Tenn.; and $2,497,800 on Island 15 Neck, 
Tenn. 
In addition, for Office of Emergency 
Preparedness, costs (reimbursable) were $7,827 
at Jonesboro, Ark.; $841 in counties of Missouri; 
$565 in counties of Arkansas; $817 in counties of 
Tennessee; and $73,355 at Forrest City, Ark. 
General Investigations 
16. SURVEYS 
Costs during fiscal year were $43,353 for White 
River, Ark., navigation study and $57,800 for the 
Memphis Metropolitan Area study. 
17. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain information studies as authorized 
by Sec. 206, 1960 Flood Control Act, as amended, 
comprise compilation and dissemination, upon 
the request of a state or political subdivision 
thereof, of information on floods and flood 
damages, including identification of areas 
subject to inundation by floods of various 
magnitudes and frequencies, and general criteria 
for guidance of Federal and non-Federal 
interests and agencies and local interests for their 
use in planning to reduce the flood hazard. Fiscal 
year cost for flood plain management services 
was $230,248, which included $93,997 for flood 
plain management services; $34,100 for technical 
services; and $702,150 on seven flood plain 
information reports. 
18. RESEARCH AND DEVELOPMENT 
Hydrologic studies were made during the year 
at a cost of $5,210. 
13-6

MEMPHIS, TENN., DISTRICT 
TABLE 13-A 
See 
Section 
in Text Project 
1. Helena Harbor, 
Ark. 
2. Hickman Harbor, 
Ky. 
3. New Madrid 
Harbor, Mo. 
4. Osceola Harbor, 
Ark. 
5. White River, 
Ark. 
6. Wolf River, 
Memphis Harbor, 
Tenn. 
9. Dyersburg, Tenn. 
(Southwest) 
10. Treasure Island, 
Mo. 
11. Big Creek 
Canal, Millington, 
Tenn. 
12. West Hickman, 
Ky. 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 Jun. 30,1975 
62,900 
60,381 
567 
-6,878 
51,500 
49,462 
15,000 
8,354 
274,400 
272,935 
77,500 
80,172 
36,370 
8,548 
-171 
5,829 
74,000 
76,099 
88,912 
88,912 
74,300 
77,483 
1,153 
340,488 
311,911 
88,600 
87,692 
100,000 
58,962 
20,000 
2,105 
-94 
1,400 
88,200 
88,827 
100,000 
178,400 
74,330 
1,304 
375,600 
273,756 
218,000 
219,784 
1,431,100 
29,500 
313,800 
25,023 
51,000 
4,658 
734,000 
97,828 
- $ 90,847 
- 90,847 
93,600 712,300 
94,412 712,140 
- 149,827 
- 149,827 
-7,000 480,648 
92,180 479,828 
- 196,373 
- 196,373 
-33,000 354,500 
71,005 354,435 
234,615 269,115 
238,804 269,115 
- 169,9941 
- 169,9942 
553,000 4,595,103 
656,598 4,565,553 
- 586,500 
- 586,500 
55,500 3,252,888 
54,995 3,252,383 
150,000 1,799,971 
1,081,490 1,259,766 
70,000 413,629 : 
121,645 158,602; 
62,000 113,000 
3,968 8,626 
745,000 1,519,9924 
608,906 747,7264 
1. Excludes $25,000 expenditures for early construction; 
includes $20,245 for preauthorization studies 
on Sec. 107 Project. 
2. Excludes $17,500 contributed funds expended. 
3. Includes $9,829 for 
Sec. 205 Project. 
4. Includes $40,992 for 
Sec. 205 Project. 
preauthorization 
preauthorization 
13-7 
studies on 
studies on

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 13-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
HELENA HARBOR, ARK. (See Sec. 1 of Text) 
Channel 9 feet deep at low water between miles 659 and 
663 AHP. 
HICKMAN HARBOR, KY. (See Sec. 2 of Text) 
Channel 9 feet deep at low water and 250 
wide at mile 922 AHP along former city waterfront 
1.1 miles, with upper 600 feet forming turning basin 
500 feet wide. 
feet 
Approved Sep. 20, 1962.' 
Approved Jul. 12, 1962.1 
Jul. 14, 1960, 
as amended 
Jul. 14, 1960, 
as amended 
Jul. 13, 1892 
Jul. 14, 1960, 
as amended 
Aug. 30, 1935 
Jul. 3, 1958 
Jun. 30, 1948, 
as amended 
Jun. 30, 1948, 
as amended 
Aug. 28, 1937, 
as amended 
Jun. 30, 1948, 
as amended 
NEW MADRID IJARBOR, MO. (See Sec. 3 of Text) 
Channel 9 feet deep at low water and 150 feet wide at 
mile 889 AHP, along city waterfront 9,400 feet with a turning 
basin 250 feet wide. 
OSCEOLA HARBOR, ARK. (See Sec. 4 of Text) 
Channel 9 feet deep at low water and 250 feet wide, 6,500 feet 
upstream along the old bendway channel. 
WHITE RIVER, ARK. (See Sec. 5 of Text) 
Open channel work, mouth to Batesville. 
Channel enlargement, mile 10 to Augusta. 
WOLF RIVER, TENN. (See Sec. 6 of Text) 
Channel 9 feet deep at low water and 250 feet wide to mile 
1.75; 200 feet wide to mile 3.5; thence 125 feet wide to 
mile 5.5. 
Flood control work in lieu of navigation improvements 
above mile 3. 
DYERSBURG, TENN. (SOUTHWEST) (See Sec. 9 of Text) 
Levee and pumping station. 
TREASURE ISLAND, MO. (See Sec. 10 of Text) 
Installation of a 150-cfs pumping plant. 
BIG CREEK CANAL, MILLINGTON, TENN. (See Sec. 11 
of Text) 
Channel cleanout between Highway 51 and Naval Air 
Station for about 12,700 feet. 
WEST HICKMAN, KY. (See Sec. 12 of Text) 
Installation of flap gate on existing culvert; 190-cfs 
pumping station; and minor channel work. 
Approved Feb. 21, 1968.1 
Approved Sep. 30, 1971.1 
Annual Report, 1893, 
page 2112. 
Approved Mar. 11, 1968.1 
H. Does. 26, 72d Cong., 
1st sess., and 45, 74th 
Cong., 1st sess. 
H. Doc. 76, 85th Cong., 
1st sess. 
Approved Jun. 27, 1972..3 
Approved Feb. 21, 1973. 2 
Approved Dec. 14, 1973, 
under authority of Sec. 2, 
Flood Control Act of 1937, as 
amended by Sec. 208 of 1954 
Flood Control Act. 
Approved Nov. 9, 1973.2 
1. Authorized under authority of Sec. 107 of the 
River and Harbor Act, as amended. 
2. Authorized under authority of Sec. 205 of the 1948 
Flood Control Act, as amended. 
3. Contains latest published map. 
13-8 
Jul. 14, 1960, 
as amended 
Jul. 14, 1960, 
as amended

MEMPHIS, TENN., DISTRICT 
TABLE 13-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Forked Deer River, Tenn., including South Fork, 2 1912 $25,000 $ 12,818 
Obion River, Tenn.1,3 1911 28,716 
Removing snags and wrecks from Mississippi River below 
mouth of Missouri River and from Old and Atchafalaya 
Rivers45 1948 - 318,833 
St. Francis and L'Anguille Rivers and Blackfish 
Bayou, Ark.' 2 1942 92,000 300,449 
1. No commerce. 4. Completed. 
2. Existing project is for maintenance only. 5. No funds available under this project. Work being 
3. Recommended for abandonment in H. Doc. 467, carried on under "Appropriation, Flood Control, Mississippi 
69th Cong., 1st sess. River and tributaries." 
TABLE 13-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Big Creek and L'Anguille River, White River Basin, Ark.' 1937 $ - $ - 
Clarendon to Laconia Circle, White River Basin, Ark.' 1937 - 
Cottonwood Slough pumping plant, Ill.2 3 1964 147,000 
Dyersburg, Tenn.2,3 1962 229,649- 
Memphis, Wolf River, and Nonconnah Creek, Tenn. 3 1960 11,141,199 
Mounds and Mound City, Ohio River Basin, Ill.5 1955 1,132,704 
Nixon Creek, Tenn.2,3 1952 62,821 
1. Inactive, awaiting local cooperation. 
2. Authorized by Chief of Engineers under small project 
authority, Sec. 205, Flood Control Act of 1948, as 
amended. 
3. Completed. 
4. Includes $21,863 contributed funds. 
5. Work being completed under Mississippi River and 
Tributaries project. 
13-9

ST. LOUIS, MO., DISTRICT* 
This district comprises those portions of 
southwestern Illinois and eastern Missouri 
embraced in drainage basin of Mississippi River 
and its western tributaries, exclusive of the 
Missouri River, from the mouth of the Ohio River 
to mile 300, and of its eastern tributaries to 
Hamburg Bay at mile 261 on left bank, exclusive 
of tributary basin of Illinois Waterway upstream 
of new La Grange Lock and Dam at mile 80.15 
above confluence of the Illinois and Mississippi 
Rivers. District also includes drainage basin in 
Missouri tributary to the Little River diversion 
channel. Report on the Mississippi River between 
the Missouri River and mile 300 is included in 
separate report on the Mississippi River between 
the Missouri River and Minneapolis, Minn. 
Report on the portion of the Illinois River 
downstream of new La Grange Lock and Dam is 
included in report of the Chicago District on the 
Illinois Waterway, Illinois and Indiana. 
IMPROVEMENTS 
Navigation 
1. Illinois Waterway, Ill. 
(St. Louis Dist.) .................. 
2. Kaskaskia River, Ill. .............. 
3. Mississippi River between Missouri 
River and Minneapolis, Minn. 
(St. Louis Dist.) ................. 
4. Mississippi River between Ohio and 
Missouri Rivers, Mo. and Ill. ...... 
5. Other Authorized Navigation 
Projects ........................ 
Flood Control 
6. Columbia Drainage and Levee 
District No. 3, Ill ............... 
7. East St. Louis and vicinity, Ill. ... 
8. Harrisonville and Ivy Landing 
Drainage and Levee District No. 2, 
Ill ............................... 
9. Kaskaskia Island Drainage 
and Levee District, Ill. ............ 
10. Kaskaskia River, Ill. .............. 
10A. Carlyle Lake, Ill. .................. 
10B. Lake Shelbyville, Ill. ............. 
10C. Vandalia Drainage and Levee 
District No. 21, Ill. ............... 
10OD. Dively Drainage and Levee District 
No. 23, Ill. ..................... 
11. McGee Creek Drainage and Levee 
District, Ill. ...................... 
12. Meramec River Basin, Mo. ........ 
12A. Meramec Park Lake, Mo .......... 
Page Flood Control (cont.) 
12B. Union Lake, Mo .................. 
14-2 13. Mississippi River Agricultural 
14-2 Area 8, Mo. ...................... 
14. Mississippi River at St. Louis, 
Mo .............................. 
14-2 15. Perry County Drainage and 
Levee Districts Nos. 1, 2, and 3, 
14-2 M o. .............................. 
16. Rend Lake, Big Muddy River, 
14-3 Ill . .............................. 
17. Upper Mississippi River Basin 
(St. Louis Dist.) ................ 
17A. Wood River Drainage and 
14-3 Levee District, Ill. ................ 
14-3 18. Inspection of completed flood 
control projects ................... 
19. Other authorized flood control 
14-4 projects ......................... 
20. Flood control work under 
14-4 special authorization ............. 
14-5 
14-5 
14-6 
14-6 
14-7 
14-7 
14-7 
14-7 
Multiple-Purpose Project 
Including Power 
21. Clarence Cannon Dam and 
Reservoir, Salt River, Mo. ........ 
General Investigations 
22. Surveys ........................ 
23. Collection and study of basic 
data ........................... 
24. Research and development ........ 
Page 
14-8 
14-8 
14-9 
14-9 
14-10 
14-10 
14-10 
14-11 
14-11 
14-11 
14-11 
14-12 
14-12 
14-12 
*All cost and financial statements and authorizing legislation for projects are listed at the end of this chapter. All other tables 
are referenced in text and also appear at the end of this chapter. 
14-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Navigation 
1. ILLINOIS WATERWAY, ILL. 
(ST. LOUIS DIST.) 
See report on Illinois Waterway, Ill. and Ind., 
under Chicago District. 
2. KASKASKIA RIVER, ILL. 
Location. The river rises in Champaign County, 
Ill., about 5 miles northwest of Urbana, in eastcentral 
part of the State. It flows southwesterly 
about 325 miles and empties into Mississippi 
River about 8 miles above Chester, Ill., or about 
118 miles above mouth of Ohio River. (See 
Cincinnati sheet of maps of United States 
published by Army Map Service, scale 
1:500,000.) 
Previous project. For details see Annual Report 
for 1896, page 171. 
Existing project. Improvement for navigation 
will provide a channel 9 feet deep and 225 feet 
wide from mouth to Fayetteville, Ill. 
Improvement will consist of enlarging present 
channel where required, making overbank 
cutoffs to eliminate sharp bends, and 
construction of a dam at about mile 0.8 with 
a single lock 84 feet wide and 600 feet long, 
at an estimated total Federal project cost 
(1975) of $124,060,000. Non-Federal cost is 
$7,665,000, of which $1,500,000 is local 
contribution. 
Local cooperation. State of Illinois passed 
legislation authorizing Illinois Department of 
Public Works and Buildings to enter into 
assurances of local cooperation with the United 
States. These assurances have been furnished and 
were accepted Nov. 23, 1965. The State is 
continuing with land acquisition. 
Operations and results during fiscal year. 
Construction of the canal and lock and dam 
was continued. Work was continued on highway 
and railroad alterations. Engineering and 
design was continued on remaining construction 
items. 
Maintenance. Hired labor performed operation 
and maintenance of the project. 
Condition at end of fiscal year. Project is about 
73 percent complete. 
3. MISSISSIPPI 
MISSOURI 
MINNEAPOLIS 
DIST.) 
RIVER BETWEEN 
RIVER AND 
MINN. (ST. LOUIS 
See section of this annual report entitled 
"Mississippi River between Missouri River and 
Minneapolis, Minn." 
4. MISSISSIPPI RIVER BETWEEN 
OHIO AND MISSOURI RIVERS, MO. 
AND ILL. 
Location. Mississippi River rises in Lake 
Itasca, Minn., and from that lake flows southerly 
about 2,340 miles and empties into the Gulf of 
Mexico. Portion included in this report embraces 
the 195-mile section known as middle Mississippi, 
between tributary Ohio and Missouri Rivers 
about 974 to 1,169 miles from the gulf. See folder 
by Corps of Engineers of Navigation Charts, 
Middle and Upper Mississippi River, Cairo, Ill., 
to Minneapolis, Minn. 
Previous projects. For details see page 1879 of 
Annual Report for 1915, and page 1014 of Annual 
Report for 1938. 
Existing project. The existing project provides 
for obtaining and maintaining a minimum 
channel depth of not less than 9 feet, a minimum 
width of not less than 300 feet at low water, with 
additional widths in bends from mouth of Ohio 
River (about 974 miles from gulf) to northern 
boundary of city of St. Louis, mile 191, thence 200 
feet wide, with additional width in bends to 
mouth of Missouri River, mile 195; to be obtained: 
(1) by regulating works, for closing secondary 
channels, contracting river by building new 
banks where river width is excessive and 
protecting new and old banks from erosion where 
necessary to secure permanency at an estimated 
total Federal cost (1975) of $144,000,000; (2) by 
dredging to maintain project channels; (3) by 
construction of works authorized for Chain of 
Rocks reach in 1945 River and Harbor Act, which 
approved a comprehensive plan for development 
of the river at Chain of Rocks to provide for 
construction of a lateral canal at an estimated 
total Federal project cost (1975) of $58,700,000; 
and (4) by construction of a fixed-crest rockfill 
dam about 900 feet below Chain of Rocks Bridge, 
authorized by 1958 River and Harbor Act, at cost 
of $4,353,000, excluding $7,000 costs to Coast 
Guard for aids to navigation. Estimated total 
Federal project cost (1975) is $207,053,000. A 
small boat harbor opposite Chester," Ill., is 
inactive and excluded from foregoing cost 
estimate. Estimated cost (July 1960) of this 
portion is $166,600 including $55,000 non- 
Federal contribution, and excluding $1,000 Coast 
Guard cost. See H. Doc. 669 (76th Cong., 3d sess.) 
for report of Chief of Engineers dated Feb. 27, 
1940, containing a general plan for improvement 
of Mississippi River between Coon Rapids Dam 
and mouth of Ohio River for purposes of 
navigation, power development, flood control, 
and needs of irrigation. 
Local cooperation. None required. 
Terminal facilities. Existing facilities are 
considered adequate for existing commerce. 
14-2

ST. LOUIS, MO., DISTRICT 
Operations and results during fiscal year. 
Regulating Works: Contract work was 
continued on stone dike construction as was 
engineering and design and supervision and 
administration. Chain of Rocks: Construction of 
guidewalls and tie-down of upper sill is under 
way. 
Maintenance. Work consisted of 3,400 feet of 
dike repair and 65,570 feet of revetment repair. 
U. S. plant and hired labor performed channel 
dredging at 35 locations, removing 6,070,000 
cubic yards of material from main channel. 
Channels dredged had a combined length of 
29.9 miles, an average width of 290 feet, and 
an average gain in depth of 3.6 feet. Condition 
and operation studies, recreation planning, 
engineering and design, and operation 
and maintenance of Lock and Dam 27 
continued. 
Condition at end of fiscal year. Construction on 
existing project began in 1881 and project has 
been in beneficial use practically from its inception. 
Project on Dam 27 is complete. Work on the 
project is about 51 percent complete. Work required 
to complete the project includes construction 
of 164,635 linear feet of dikes; 185,700 linear 
feet of revetment; removal of 100,000 cubic yards 
of rock; removal of 100,000 cubic yards by dredging; 
upper and lower guidewalls at Lock 27; and 
alterations to sills. Channel as a whole has been 
greatly improved by the work completed to date. 
Dredging is required at low stages to remove temporary 
shoals and maintain required channel 
depths. Navigation season formerly extended 
from mid-February to mid-December, the river 
is generally closed by ice the remainder of year. 
However, in recent years increased demands of 
commerce and use of steel-hull boats have combined 
to extend navigation season throughout the 
year except when blocked by heavy ice or gorges. 
River is generally above 10-foot stage, St. Louis 
gage, from latter part of February to the latter 
part of August, during which time project 
channel depths generally prevail without dredging. 
Mean stage of river, St. Louis gage, was 17.58 
feet for Fiscal Year 1974 and 12.04 feet for Fiscal 
Year 1975. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 14-C.
Flood Control 
6. COLUMBIA DRAINAGE 
LEVEE DISTRICT NO. 3, ILL. 
AND 
Location. In Monroe County, Ill., on left bank of 
the Mississippi River between river miles 156 and 
166 above mouth of the Ohio River. (See St. Louis, 
Mo., map published by Army Map Service, scale 
1:250,000.) 
Previous project. For details, see page 653 of 
Annual Report for 1959. 
Existing project. Project area contains about 
13,600 acres protected from major floods of the 
Mississippi River, Columbia Creek, and Fountain 
Creek by levees. However, when Mississippi 
River stage exceeds 20 feet on the St. Louis, Mo., 
gage, substantial damage results from 
impoundment of precipitation which falls on the 
area, runoff from adjacent hill land, and 
Mississippi River seepage. The 1962 Flood 
Control Act (H. Doc. 543, 87th Cong., 2d sess.) 
provides for construction of two pumping stations 
to reduce interior flooding. Estimated cost (1975) 
is $3,800,000. 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way for 
construction; hold and save the United States free 
from damages; maintain and operate project, 
including pumping plants, after completion; 
prevent encroachment on improved channels and 
ponding areas and, if ponding area and capacities 
are impaired, provide substitute storage capacity 
or equivalent pumping capacity promptly 
without cost to the United States and comply with 
applicable provisions of Public Law 91-611 and 
Public Law 91-646. The proposed sponsors, the 
Commissioners of the Columbia Drainage and 
Levee District No. 3, have furnished assurances 
of local cooperation. 
Operations and results during fiscal year. 
Preconstruction planning is complete. 
Condition at end of fiscal year. General design 
memorandum was revised in accordance with 
recommendations of higher authority. Contract 
for the Franey Lake pumping station was 
awarded. 
7. EAST ST. LOUIS AND VICINITY, 
ILL. 
Location. Project is in St. Clair and Madison 
Counties, Ill., on the left bank of the Mississippi 
River between river miles 175 and 195 above the 
Ohio River. Project includes all bottomlands 
between bluffs on the east and Mississippi River 
and Chain of Rocks Canal on the west, and 
extends from Cahokia diversion channel on the 
north to Prairie du Pont Creek on the south. (See 
Corps of Engineers Navigation Charts, Middle 
and Upper Mississippi River, Cairo, Ill., to 
Minneapolis, Minn.) 
Existing project. The 1936 Flood Control Act 
authorized raising and enlarging existing levee 
systems by construction or reconstruction of 19.8 
14-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
miles of levee, including 3.1 miles of floodwall, 
together with necessary appurtenant works 
consisting of gravity drainage structures, 
highway and railroad closure structures, 
alterations and reconstruction of existing 
pumping plants, alterations to railroad bridges 
and approaches at levee crossings, service roads 
on levee crown, and seepage control measures. 
Work under this authorization will provide the 
area protection against a flood of about 200-year 
frequency. The completed 10 miles of levee along 
Chain of Rocks Canal and Lock 27 provide flood 
protection on the landward side integral with and 
to the same degree as the East St. Louis levee. 
Estimated cost (1974) of work under this 
authorization is $22,551,000. The Flood Control 
Act of 1965 modified existing project to provide 
for channel improvements, diversion ditches, 
flood plain detention areas, a reservoir on Little 
Canteen Creek, and a pumping plant to 
considerably reduce damages resulting from 
interior flooding. This act also authorized 
reconstruction of a channel stabilization dam in 
Cahokia Creek diversion channel to provide 
protection to adjacent levees and bridges from 
scour and eventual loss. Estimated total Federal 
project cost of work under this authorization is 
$52,100,000 (1975), $18,400,000 for Cahokia 
Creek Dam, and $33,700,000 for Interior Flood 
Control. Non-Federal cost is $15,100,000. 
Local cooperation. Local interests have fully 
complied with the requirements of local 
cooperation for work under the 1936 
authorization. For work authorized by Flood 
Control Act of 1965, local interests must provide 
lands, easements, and rights-of-way for 
construction; hold and save the United States free 
from damages due to the construction works; 
make relocations of and modifications to highway 
bridges, streets, roads, sewers, and utilities; 
maintain and operate all the works after 
completion including removal of silt and debris 
from impoundment areas and channels in 
accordance with regulations prescribed by the 
Secretary of the Army; prevent encroachment on 
improved channels, ponding areas, and detention 
areas including the reservoir, and if 
encroachment occurs or capacities are impaired, 
provide substitute storage or equivalent pumping 
capacity promptly without cost to the United 
States; and at least annually notify interests 
affected that the project provides partial 
protection from the larger floods. The State of 
Illinois has agreed to sponsor the interior 
drainage project and the low water dam. In 
addition to requirements listed above, the sponsor 
would have to comply with the applicable 
provisions of Public Law 91-611 and Public Law 
91-646. 
Operations and results during fiscal year. 
Engineering and design on minor repairs to 
pumping station was continued on work 
authorized by the Flood Control Act of 1936. 
Planning was continued on project modifications 
authorized by Flood Control Act of 1965. 
Condition at end of fiscal year. Work 
authorized by Flood Control Act of 1936 is 
essentially complete. 
8. HARRISONVILLE AND IVY 
LANDING DRAINAGE AND LEVEE 
DISTRICT NO. 2, ILL. 
Location. The district is in Monroe County, Ill., 
on the left bank of the Mississippi River between 
river miles 141 and 156 above the mouth of Ohio 
River. (See St. Louis, Mo., map published by 
Army Map Service, scale 1:250,000.) 
Previous project. For details, see page 676 of 
Annual Report for 1957. 
Existing project. Project area contains about 
27,800 acres protected from floods of the 
Mississippi River and Fountain Creek by levees. 
However, when Mississippi River stage exceeds 
15 feet on the St. Louis, Mo., gage, substantial 
damage results from impoundment of 
precipitation which falls on the area, runoff from 
adjacent hill land, and Mississippi River seepage. 
The Flood Control Act of 1962 provides for 
construction of two pumping stations to reduce 
interior flooding. Estimated total Federal project 
cost (1975) is $5,290,000. 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way for 
construction; hold and save the United States free 
from damages; maintain and operate project, 
including pumping plants, after completion; 
prevent encroachment on improved channel and 
ponding areas and, if ponding areas and capacity 
are impaired, provide substitute storage capacity 
or equivalent pumping capacity promptly 
without cost to the United States and comply with 
the provisions of Public Law 91-611 and Public 
Law 91-646. The sponsors have furnished 
assurances of necessary cooperation. 
Operations and results during fiscal year. 
Preconstruction planning is complete. 
Condition at end of fiscal year. Project 
constructed under authority of Flood Control Act 
of 1936 is complete. On modifications authorized 
by Flood Control Act of 1962, contracts were 
awarded for levee raising and a 600 cubic feet per 
second pumping station. 
9. KASKASKIA ISLAND DRAINAGE 
AND LEVEE DISTRICT, ILL. 
Location. In Randolph County, Ill., on the right 
bank of the Mississippi River between miles 111 
14-4

ST. LOUIS, MO., DISTRICT 
and 116 above the mouth of the Ohio River. (See 
Paducah, Ky., Ill., Mo., Ind., map published by 
Army Map Service, scale 1:250,000.) 
Previous project. For details, see page 1375 of 
Annual Report for 1950. 
Existing project. Project area contains about 
9,460 acres only partially protected against flood 
stage of 38.5 feet on the Chester, Ill., gage. 
Flooding occurs about once in every 7.3 years 
with an average duration of 26 days, causing 
substantial damage. The 1938 Flood Control Act 
(H. Doc. 519, 87th Cong., 2d sess.) provides for 
enlarging and raising the existing levee about 8 
feet to provide protection against a flood having a 
frequency of once in 50 years. Estimated cost 
(1975) is $6,880,000. 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way for 
construction; hold and save the United States free 
from damages; maintain and operate project 
after completion and comply with provisions of 
Public Law 91-611 and Public Law 91-646. Local 
interests have certified that assurances of local 
cooperation will be executed at the appropriate 
time and have reaffirmed their willingness to 
comply with the terms of local cooperation. 
Operations and results during fiscal year. 
Preconstruction planning was initiated. 
Condition at end of fiscal year. Phase I of the 
general design memorandum is being prepared. 
10. KASKASKIA RIVER, ILL. 
Location. The river rises in Champaign County, 
Ill., about 5 miles northwest of Urbana, in eastcentral 
part of the State. It flows generally 
southwesterly about 325 miles and empties into 
the Mississippi River about 8 miles above 
Chester, Ill., or 118 miles above mouth of Ohio 
River. (See Nashville and Cincinnati sheets of 
maps of United States, published by Army Map 
Service, scale 1:500,000; also Geological Survey 
quadrangle maps, 1:62,500.) 
Existing project. The project provides for 
construction of a dam at Carlyle and five levee 
projects between Carlyle and New Athens 
authorized by 1936 Flood Control Act, and 
construction of a dam at Shelbyville, six levee 
projects along river between Cowden and 
Vandalia, and a local protection project at New 
Athens, all authorized by 1958 Flood Control Act. 
Under the plan, Carlyle Lake and Lake 
Shelbyville would be operated as a multiplepurpose 
project for local and Mississippi River 
flood control, domestic and industrial water 
supply, releases in the interest of navigation on 
the Mississippi River, fish and wildlife 
conservation, and recreation. The 11 levee 
projects would provide protection to about 54,610 
acres of land. In view of inclusion of previously 
authorized Carlyle Lake and the levees between 
Carlyle and New Athens in recommended plan, 
general comprehensive plan for flood control and 
other purposes in Upper Mississippi River Basin, 
approved by 1938 Flood Control Act, was 
modified by deleting Carlyle Lake and levees 
between Carlyle and New Athens. Flood Control 
Act of 1965 modified the Flood Control Act of 
1958 to: (a) delete requirement that local interests 
make a cash contribution to the cost of levees 
between Cowden and Vandalia because of 
changed land use, and (b) require that local 
interests make a cash contribution equal to full 
cost of acquisition of flowage easements in those 
lands acquired by the United States which, upon 
completion of the levee in District No. 22, will not 
be required for construction, operation, and 
maintenance of Carlyle Lake. (See Table 14-D.) 
Operations and results during fiscal year. 
Construction continued on Carlyle Lake and Lake 
Shelbyville. Construction is complete on New 
Athens. Preliminary planning is essentially 
complete on Vandalia Drainage and Levee 
District No. 21. Construction on Dively Drainage 
and Levee District No. 23 was initiated. 
Maintenance: Continued on Carlyle and 
Shelbyville. 
Condition at end of fiscal year. See individual 
reports for Carlyle Lake, Lake Shelbyville, 
Vandalia Drainage and Levee District No. 21, 
and Dively Drainage and Levee District No. 23. 
Due to lack of local interest and support at this 
time, Levee Districts Nos. 3, 4, 8, 10, 13, 22, 27, 28, 
and 28A are inactive. 
10A. CARLYLE LAKE, ILL. 
Location. Dam is on Kaskaskia River at mile 
107, about 1 mile upstream from Carlyle, Ill. 
Reservoir extends northeastward through 
Clinton, Marion, Bond, and Fayette Counties, Ill., 
to river mile 153. (See Cincinnati sheet of maps of 
United States published by Army Map Service, 
scale 1:500,000. Also see Geological Survey 
quadrangle maps, scale 1:62,500.) 
Existing project. The project consists of a 
compacted earth-fill dam with a concrete 
spillway section. Spillway structure consists of an 
ogee overflow section surmounted by four 38- by 
39-foot tainter gates. Dam crest is 67 feet above 
streambed and 6,570 feet long. Because of 
topography near dam, it was necessary to 
construct two earth-fill saddle dams east of 
Carlyle, in order to contain maximum pool level 
proposed for reservoir. A loop levee was 
constructed for protection of Keyesport, Ill. 
Relocation or alterations were required to 
Chicago, Burlington, and Quincy Railroad, 
14-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
highways, pipelines, oil field facilities, water 
supply facilities, power and telephone lines, and 
cemeteries. Maximum reservoir area is 57,500 
acres and maximum storage capacity is 983,000 
acre-feet; permanent pool area is 26,000 acres. 
Estimated total Federal project cost (1975) is 
$42,720,000 of which $8,723,400 is for lands and 
damages. Non-Federal local contribution toward 
cost of project is $3,635,000 for water supply. 
Estimated Federal cost for Code 711 recreation 
facilities is $1,771,700, non-Federal cost is 
$787,000. 
Local cooperation. In accordance with 
provisions of authorizing act, cost of storage to be 
allocated to water supply in Carlyle Lake and 
annual cost of operation and maintenance of such 
storage would be reimbursed by the users. State 
of Illinois executed a contract with the United 
States providing for payment of 7.85 percent of 
cost of project and 8.62 percent of actual Federal 
costs for operation and maintenance. Percentages 
set forth were determined by separable costremaining 
benefits methods. Contract was 
approved by the Secretary of the Army. State of 
Illinois is currently making payments 
thereunder. 
Operation and results during fiscal year. All 
major items of work are essentially complete. 
Acquirement of flowage easement lands which 
were damaged due to shoreline erosion was 
continued. Revetment is being placed on the 
shoreline in the state parks to prevent further 
erosion damage. Upgrading of sanitary facilities 
was performed at recreation areas. 
Maintenance. Hired labor forces performed 
operation and maintenance of Carlyle Lake. 
Condition at end of fiscal year. Construction 
was initiated in November 1958. The dam is 
complete. To date, 37,459 acres of land have been 
acquired in fee, and an additional 25,339 acres in 
easements. Project is essentially complete. 
10B. LAKE SHELBYVILLE, ILL. 
Location. Dam is on the Kaskaskia River at 
mile 221.8, about one-half mile upstream from 
Shelbyville, Ill. Lake will extend northeastward 
through Shelby, Moultrie, and Coles Counties, 
Ill., to approximate river mile 275. (See Decatur 
sheet of maps of United States published by 
Army Map Service, scale 1:250,000, and 
Geological Survey quadrangle maps, scale 
1:62,500.) 
Existing project. The project provides for 
construction of a compacted earth-fill dam with a 
concrete spillway section. Spillway structure will 
consist of an ogee overflow section surmounted by 
three 45- by 37-foot tainter gates. Dam crest will 
be about 108 feet above streambed and about 
3,000 feet long. Relocations or alterations are 
required to railroads, highways, cemeteries, and 
miscellaneous utilities. Maximum storage 
capacity will be 684,000 acre-feet. Estimated 
total Federal project cost (1974) is $44,000,000, of 
which $12,115,000 is for lands and damages. 
Local contribution toward cost of project is 
$16,800,000, of which $4,300,000 is for water 
supply. Estimated Federal cost for Code 711 
recreation facilities is $3,534,000, non-Federal 
cost is $2,314,000. 
Local cooperation. Local interests must 
contribute toward cost of this project 7.06 percent 
of total cost for water-supply benefits provided, 
6.86 percent of total cost for land enhancement, 
and 9.65 percent of total cost plus 5.75 percent of 
total cost of Carlyle Lake for recreation and fish 
and wildlife benefits. A contract was entered into 
between State of Illinois and the United States 
under which the State will act as local sponsor to 
make contributions for this project. State of 
Illinois is currently making payments 
thereunder. 
Operations and results during fiscal year. 
Planning and design continued. Construction was 
continued on recreation facilities. 
Maintenance. Hired labor forces performed 
operation and maintenance of Lake Shelbyville. 
Condition at end of fiscal year. Project is 97 
percent complete. Lands acquired to date are 
34,408 acres in fee and 6,100 acres in easements. 
10C. VANDALIA DRAINAGE AND 
LEVEE DISTRICT NO. 21, ILL. 
Location. The levee district is in Fayette 
County, Ill., on the east bank of the Kaskaskia 
River, between miles 155.5 and 172.0. (See 
Decatur sheet of maps of United States, 
published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for 
construction for 20.9 miles of earth levee, 
drainage structures, and necessary closure 
structures, which will afford flood protection to 
approximately 11,430 acres of agricultural land. 
Estimated total Federal project cost (1975) is 
$11,500,000. Non-Federal cost is $1,260,000. 
Local cooperation. Local interests must provide 
without cost to the United States, all lands, 
easements, and rights-of-way necessary for the 
construction of the project; provide necessary 
relocations and alterations to highways, roads, 
and bridges; relocate and adjust all utilities; 
construct necessary drainage ditches; hold and 
save the United States free from damages due to 
the construction works; and maintain and operate 
all works after completion in accordance with 
regulations prescribed by the Secretary of the 
14-6

ST. LOUIS, MO., DISTRICT 
Army. In addition, local interests must comply 
with the applicable provisions of Public Law 91- 
611 and Public Law 91-646. 
Operations and results during fiscal year. 
Preconstruction planning is essentially complete. 
Condition at end offiscal year. Construction has 
not commenced. 
leD. DIVELY DRAINAGE AND LEVEE 
DISTRICT NO. 23, ILL. 
Location. The levee district is in Fayette 
County, Ill., on the east bank of the Kaskaskia 
River between miles 172.4 and 174.0. (See 
Decatur sheet of maps of United States, published 
by Army Map Service, scale 1:250,000.) 
Existing project. Project provides for 
construction of 3.5 miles of earth levee, drainage 
structures, and necessary closure structures, 
which will afford flood protection to 
approximately 1,420 acres of agricultural land. 
Estimated total Federal project cost (1974) is 
$1,820,000. Non-Federal cost is $100,000. 
Local cooperation. Local interests must 
provide, without cost to the United States, all 
lands, easements, and rights-of-way necessary for 
construction of the project; provide necessary 
relocations and alterations for highways, roads, 
and bridges; relocate and adjust all utilities and 
construct necessary drainage ditches; hold and 
save the United States free from damages due to 
the construction works; maintain and operate all 
works after completion, in accordance with 
regulations prescribed by the Secretary of the 
Army. The Board of Commissioners of the Dively 
Drainage and Levee District has executed 
assurances in compliance with Public Law 91-611 
and Public Law 91-646. 
Operations and results during fiscal year. 
Construction was initiated. 
Condition at end of fiscal year. Project is 55 
percent complete. 
11. MC GEE CREEK DRAINAGE AND 
LEVEE DISTRICT, ILL. 
Location. The levee district is in Brown and 
Pike Counties, Ill., on the right bank of Illinois 
River between miles 67.2 and 75.1 above the 
Mississippi River. (See Kansas City sheet of maps 
of United States, published by Army Map 
Service, scale 1:500,000.) 
Existing project. Project provides for 
reconstruction of 14.7 miles of levee, construction 
of a new pumping plant, closure structure, and 
seepage control measures. Project will provide 
protection to about 12,080 acres of agricultural 
land against a flood of about 50-year frequency. 
Estimated total Federal project cost (1975) is 
$11,300,000. Non-Federal cost is $510,000. 
Project was authorized by 1962 Flood Control Act 
(H. Doc. 472, 87th Cong., 2d sess.). 
Local cooperation. Local interests must furnish 
assurance satisfactory to the Secretary of the 
Army that they will furnish without cost to the 
United States all lands, easements, rights-of-way, 
and ponding and spoil-disposal areas necessary 
for construction of the project; hold and save the 
United States free from damages due to the 
construction works; bear the expense of 
relocating and altering highways, highway 
bridges (except underpinning), utilities, 
buildings, interior drainage facilities, pipelines, 
and other structures, except railroad bridges and 
approaches; prescribe and enforce regulations 
satisfactory to the Secretary of the Army to 
prevent encroachment on the improved channels 
and ponding areas; and maintain and operate all 
the works after completion in accordance with 
regulations prescribed by the Secretary of the 
Army. In addition, local interests must comply 
with the applicable provisions of Public Law 91- 
611 and Public Law 91-646. 
Operations and results during fiscal year. 
Preconstruction planning is continuing. 
Condition at end of fiscal year. Construction has 
not commenced. 
12. MERAMEC RIVER BASIN, MO. 
Location. The basin lies within the State of 
Missouri and comprises 3,980 square miles. The 
river is a west bank tributary of the Mississippi 
River at mile 161 above mouth of Ohio River. 
Major streams in the basin include the Meramec, 
Big, and Bourbeuse Rivers. The basin extends 
about 100 miles southwesterly from St. Louis into 
the Ozark Highlands. (See St. Louis, Mo., and 
Rolla sheets of maps of the United States, published 
by Army Map Service, scale 1:250,000.) 
Existing project. The project provides for the 
construction of Meramec Park and Union Lakes, 
authorized by the 1938 Flood Control Act; and 
Pine Ford, Irondale, and I-38 Lake projects, and 
19 angler-use sites, authorized by the 1966 Flood 
Control Act. Under the plan, Irondale and I-38 
Lakes will reduce flood damages in the upper Big 
and Bourbeuse Rivers. Meramec Park, Union, 
and Pine Ford Lakes will substantially reduce 
flooding in the lower basin area and will lower 
flood crests on the Mississippi River. Project will 
also provide water supply, water quality control, 
recreation, and fish and wildlife conservation. 
(See Table 14-D for additional data on this 
comprehensive project.) 
12A. MERAMEC PARK LAKE, MO. 
Location. Dam will be at mile 108.7 on 
14-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Meramec River in Franklin County near 
Sullivan, Mo. Reservoir will be mainly in 
Crawford, Franklin, and Washington Counties, 
Mo. (See St. Louis, Mo., sheet of maps of the 
United States, published by Army Map Service, 
scale 1:250,000.) 
Existing project. Project as authorized by 1938 
Flood Control Act provides for construction of an 
earth dam about 167 feet high with a crest length 
of 3,000 feet. Reservoir will provide 1 million 
acre-feet of storage and provide flood protection 
for 11,862 acres of flood plain in the Meramec 
River valley above the mouth of Bourbeuse River, 
and partial protection for 20,209 acres of land 
below the Bourbeuse. Project will also provide 
water supply, water quality control, storage, and 
recreation, and fish and wildlife benefits. 
Estimated total project cost (1975) is 
$115,000,000, including $20,180,000 local 
reimbursement for water supply. 
Local cooperation. Local interests must 
contribute toward cost of project for storage 
allocated to water supply in accordance with the 
Water Supply Act of 1958. State of Missouri, 
acting through its State Water Resources Board 
and under authority of the General Assembly of 
State of Missouri, executed assurances for water 
supply on Aug. 23, 1967. The assurances were 
reviewed by the Office of the Attorney General, 
State of Missouri, and it is his opinion that the 
State of Missouri has the legal authority and 
financial capability to execute said assurances. 
These assurances have been approved by the 
Chief of Engineers. A water-supply contract will 
be entered into with the sponsor before any use of 
the water-supply storage provided under this 
contract. 
Operations and results during fiscal year. 
Construction was completed on an 
administration visitor center building, overlook 
area, sewage treatment system, and access road. 
Planning on additional features is continuing. 
Condition at end of fiscal year. Construction 
will continue. To date 21,456 acres have been 
acquired in fee and an additional 1,006 acres in 
easements. 
12B. UNION LAKE, MO. 
Location. Dam will be on Bourbeuse River at 
mile 32.6, about 55 miles west of St. Louis. River 
is a major tributary of the Meramec. Lake will 
extend about 53 miles up Bourbeuse River. (See 
St. Louis, Mo., sheet of maps of the United States, 
published by Army Map Service, scale 
1:250,000.) 
Existing project. Project as authorized by the 
1938 Flood Control Act provides for construction 
of a compacted earth-fill dam with a concrete 
chute spillway in natural rock upstream of the 
right abutment. Dam will be 148 feet high and 
2,100 feet long. Construction of new roads, 
improvement of existing roads, and alterations to 
pipeline, power and telephone lines, and 
construction of recreational facilities are 
included. Maximum reservoir area will be 16,600 
acres and maximum storage capacity will be 
528,000 acre-feet. Estimated total project cost 
(1975) is $60,000,000, of which $5,920,000 is a 
local reimbursement for water supply. 
Local cooperation. Local interests must 
contribute toward cost of project for storage 
allocated to water supply in accordance with the 
Water Supply Act of 1958. The State of Missouri 
demonstrated sufficient interest and approval of 
the basin plan to warrant the assumption at this 
time that necessary local cooperation will be 
forthcoming. 
Operations and results during fiscal year. 
Preconstruction planning was curtailed due to 
lack of funds. 
Condition at end of fiscal year. Construction has 
not started. Advance participation on relocation 
of Highway 185 with the State of Missouri is in 
final design stage. 
13. MISSISSIPPI RIVER AGRICULTURAL 
AREA 8, MO. 
Location. Area 8 is in Lincoln and Pike 
Counties, Mo., on west bank of Mississippi River 
between river miles 249 and 261 above the Ohio 
River. Small community of Elsberry lies within 
the area. (See Quincy sheet of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. The 1966 Flood Control Act 
(H.Doc. 510, 89th Cong., 2d sess.) authorized the 
raising and enlarging of existing levees to 
provide 24.4 miles of riverfront, flank, and back 
levees and construction of appurtenant works 
consisting of drainage structure, highway and 
railroad closure structures, and alterations to 
existing pumping plants. Project will afford 
protection to the area against a flood of 50-year 
frequency. Estimated total Federal project cost 
(1975) is $9,270,000. Non-Federal cost is 
$1,200,000. 
Local cooperation. Prior to construction, local 
interests must furnish assurances satisfactory to 
the Secretary of the Army that they will provide 
without cost to the United States all lands, 
easements, and rights-of-way necessary for the 
construction of the project; hold and save the 
United States free from damages due to 
construction works; maintain and operate the 
projects after completion in accordance with 
regulations prescribed by the Secretary of the 
14-8

ST. LOUIS, MO., DISTRICT 
Army; accomplish, without expense to the United 
States, alterations and relocations to all utilities, 
roads, highways, and interior ditching as 
required; and prohibit encroachment on 
improved channels or on ponding areas; and that 
if ponding areas and capacities are impaired, 
substitute storage capacity or equivalent 
pumping capacity will be provided promptly, 
without cost to the United States. In addition, 
local interests must comply with the applicable 
provisions of Public Law 91-611 and Public Law 
91-646. The Elsberry Drainage District has 
indicated a willingness to meet the terms of local 
cooperation for Area 8, upon request. 
Operations and results during fiscal year. 
Preconstruction planning was continued. 
Condition at end of fiscal year. Construction has 
not commenced. 
14. MISSISSIPPI RIVER AT ST. LOUIS, 
MO. 
Location. Protective works will be on right 
bank of Mississippi River from Maline Creek to 
Carr Street, between miles 187.2 and 180.2; and 
from Poplar Street to Chippewa Street, between 
miles 179.2 and 176.3. Area to be protected 
includes low-lying lands along riverfront of St. 
Louis between river and higher ground. (See 
Corps of Engineers Navigation Charts, Middle 
and Upper Mississippi River, Cairo, Ill., to 
Minneapolis, Minn.) 
Existing project. Project provides for 
construction of 21,200 feet of earth levee, 34,400 
feet of reinforced concrete floodwall, closure 
structures, underseepage relief measures, 28 
pumping stations, and alterations to 44 sewer 
systems. Project will provide protection to 
heavily industrialized area along riverfront from 
Maline Creek to Carr Street and from Poplar 
Street to Chippewa Street against a flood of about 
200-year frequency. Estimated total Federal 
project cost (1974) is $77,570,000. Non-Federal 
cost is $7,740,000 which includes $1,840,000 
contributed funds. 
Local cooperation. Formal assurances as 
required by authorizing act were received from 
City of St. Louis. The assurances are applicable to 
Reaches 3 and 4 of project and supplemented by 
assurances of Metropolitan St. Louis Sewer 
District. Assurances by Sewer District are 
applicable to maintenance and operation of 
sewerage, drainage, and pumping facilities 
constructed as part of project, and to local 
cooperation requirement that new drainage and 
sewerage facilities constructed within limits of 
protected flood plains will function at all river 
stages up to design flood, without cost to the 
United States. Included in local cooperation 
requirements is a required contribution equal to 
3.6 percent of first cost of construction of Reach 3. 
Assurances were accepted by the District 
Engineer, Oct. 22, 1958. City furnished rights-ofway 
required for all work currently under 
contract and indicated they will be able to fulfill 
requirements for remaining work as required. 
Operations and results during fiscal year. 
Planning and design continued. Construction 
continued on floodwalls and pumping plants. 
Condition at end of fiscal year. Construction of 
Reach 3 was initiated in March 1959 and Reach 4 
in August 1963. Project is 99 percent complete. 
15. PERRY COUNTY DRAINAGE AND 
LEVEE DISTRICTS NOS. 1, 2, & 3, MO. 
Location. Districts are in Perry County, Mo., 
and Randolph County, Ill., on the right bank of 
the Mississippi River between river miles 95 and 
111 above the mouth of the Ohio River. (See 
Paducah, Ky., Ill., Mo., Ind., map published by 
Army Map Service, scale 1:250,000.) 
Previous project. For details, see page 475 of 
Annual Report for 1968. 
Existing project. Project area contains about 
26,881 acres protected from floods of the 
Mississippi River by levees. However, when 
Mississippi River stage exceeds 13 feet on the 
Chester, Ill., gage, substantial damage results 
from impoundment of precipitation or seepage, 
or a combination thereof. Authorized project 
provides for construction of four pumping 
stations to reduce interior flooding. Estimated 
total Federal project cost (1975) is $3,900,000. 
Non-Federal cost is $35,000. 
Local cooperation. Prior to construction, local 
interests must furnish assurances satisfactory to 
the Secretary of the Army that they will provide 
without cost to the United States all lands, 
easements, and rights-of-way necessary for the 
construction of the project; hold and save the 
United States free from damages due to the 
construction works; maintain and operate the 
project, including pumping station, after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; clean 
silt and debris from the ditches to provide an 
unrestricted flow to the pumping stations; 
prevent obstruction or encroachment of the 
channels; comply with the provisions of Public 
Law 91-611 and Public Law 91-646; at least 
annually inform interests affected that the 
project will not provide absolute protection 
against flood damage. Each of the Districts 
concerned has indicated a willingness to meet the 
conditions of local cooperation upon request. 
Operations and results during fiscal year. 
Preconstruction planning was continued. 
14-9

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Condition at end of fiscal year. Construction has 
not commenced. 
16. REND LAKE, BIG MUDDY RIVER, 
ILL. 
Location. The lake is in Franklin and Jefferson 
Counties in southern Illinois. The dam is on Big 
Muddy River, 103.7 miles upstream from its 
confluence with the Mississippi River, and about 
3 miles northwest of Benton, Ill. (See Belleville 
sheet of maps of United States, published by 
Army Map Service, scale 1:250,000, and 
Geological Survey quadrangle maps, 1:62,500.) 
Existing project. The project provides for 
construction of an earth dam, ungated concrete 
spillway, relocation of roads and utilities, 
recreational facilities, access roads, and service 
facilities. In addition, two subimpoundment 
dams were constructed on upper arms of 
reservoir to enhance fish and wildlife value of 
project. Reservoir will have an area of 24,800 
acres, and a storage capacity of 294,000 acre-feet. 
Project will provide flood control, water supply, 
low-flow regulation, conservation of fish and 
wildlife, recreation, and area redevelopment. 
Estimated total Federal project cost (1974) is 
$44,700,000, of which $12,010,000 is for lands and 
damages. Non-Federal local contribution for 
water supply is $10,000,000. Estimated Federal 
cost for Code 711 recreation facilities is 
$1,080,000; there is no non-Federal cost. 
Local cooperation. Agreement was reached 
among State of Illinois, Rend Lake Conservancy 
District, and the Corps that: (1) State of Illinois 
and Rend Lake Conservancy District jointly and 
severally sponsor this project, (2) State of Illinois 
enters into a contract with the Corps to pay 
$10,000,000 for water supply features of the 
project, and (3) State of Illinois and Rend Lake 
Conservancy District enter into contract by 
which the Conservancy District will be granted 
authority to distribute water from the water 
supply storage in this project. Legislation to 
implement the above agreements was passed by 
the Illinois General Assembly and approved by 
the Governor. Assurances of local cooperation 
and water supply contract have been executed 
and approved by the Secretary of the Army. 
Operations and results during fiscal year. 
Construction was continued on recreation 
facilities in the South Marcum and Spillway 
recreation areas and on the upgrading of sanitary 
facilities in the Sandusky recreation area. 
Maintenance. Hired labor forces performed 
operation and maintenance of Rend Lake 
Reservoir. 
Condition at end of fiscal year. Construction is 
complete on the main dam, road, railroad, utility 
relocations, and first four recreation areas. 
Project is 92 percent complete. Lands acquired to 
date are 39,837 acres in fee and 906 acres in 
easements. 
17. UPPER MISSISSIPPI RIVER BASIN 
(ST. LOUIS DIST.) 
Location. Area is in the Mississippi River Basin 
above Ohio River, exclusive of Missouri River 
Basin, in St. Louis District. (See Geological 
Survey state maps for Illinois and Missouri and 
quadrangle maps; also, St. Louis, Quincy, Rolla, 
and Paducah sheets of maps of the United States, 
published by Army Map Service, scale 
1:250,000.) 
Existing project. Flood Control Act of 1938 
approved general comprehensive plan for flood 
control and other purposes in Upper Mississippi 
River Basin described in Flood Control 
Committee Doc. 1, 75th Cong., lst sess., with such 
modifications thereof as in discretion of 
Secretary of War and Chief of Engineers may be 
advisable. Individual projects in St. Louis 
District considered in comprehensive plan are 
listed in Table 14-E. 
Operations and results during fiscal year. See 
individual reports for details of projects. 
Condition at end of fiscal year. Total cost for St. 
Louis District projects under this authorization is 
$22,142,802. 
17A. WOOD RIVER DRAINAGE AND 
LEVEE DISTRICT, ILL. 
Location. The district is in Madison County, Ill., 
on left bank of Mississippi River between river 
miles 195 and 203 above Ohio River. District 
includes bottomlands between river and bluffs 
and extends from Cahokia diversion channel on 
the south to opposite Lock and Dam 26 at Alton, 
Ill., on the north. Small industrial cities of 
Hartford, Wood River, Roxana, and East Alton 
and part of Alton riverfront, lie within the 
district. (See Corps of Engineers Navigation 
Charts, Middle and Upper Mississippi River, 
Cairo, Ill., to Minneapolis, Minn.) 
Previous project. For details see Annual Report 
for 1968. 
Existing project. Project area contains about 
13,700 acres protected from major floods of the 
Mississippi River by levees. However, when 
Mississippi River stage exceeds 30 feet on the St. 
Louis, Mo., gage, substantial damage results 
from impoundment of precipitation which falls 
on the area, runoff from adjacent hill land, and 
seepage from the Mississippi River. The 1965 
Flood Control Act provides for a pumping station 
with collector ditches and necessary appurtenant 
14-10

ST. LOUIS, MO., DISTRICT 
facilities for removal of water impounded by 
existing levee. Estimated total Federal project 
cost (1975) is $1,060,000. Estimated non-Federal 
cost is $385,000 for land and damages. 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way for 
construction; hold and save the United States free 
from damages due to the construction works; 
maintain and operate all the works after 
completion in accordance with regulations 
prescribed by the Secretary of the Army; and 
prevent encroachment on improved channels or 
ponding areas and, if ponding areas and 
capacities are impaired, provide substitute 
storage or equivalent pumping capacity 
promptly without cost to the United States and 
comply with the applicable provisions of Public 
Law 91-611 and Public Law 91-646. The proposed 
sponsor, Wood River Drainage and Levee 
District, has indicated that it does not have the 
financial capability to sponsor the interior 
drainage program. 
Operations and results during fiscal year. 
Preconstruction planning, previously suspended 
pending resolution of local cooperation 
requirements, was resumed. 
Condition at end of fiscal year. Construction has 
not started. 
18. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was 
accomplished at a cost of $275,400 for the fiscal 
year. Total cost as of end of Fiscal Year 1975 is 
$1,490,474. 
19. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 14-F. 
20. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended 
(preauthorization). 
Federal cost for fiscal year for continuing 
detailed project report on Carbondale, Ill., was 
$12,257; total cost is $70,151 for reconnaissance 
detailed project report. 
Other reports were made on Harrisonville, Ill., 
$29,210; Hardin, Ill., $4,925; Louisiana, Mo., 
$9,408; and Salt River, Mo., $1,056. 
Snagging and clearing of navigable streams and 
tributaries in interest of flood control (Sec. 208 of 
1954 Flood Control Act, Public Law 780, 83d 
Cong.) 
Study initiated and completed on Kaskaskia 
River, Ill., for $4,997. 
Emergency flood control activities--repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal costs for fiscal year were $55,522 for 
advance preparations, $2,125,517 for emergency 
operations, and $4,833,128 for rehabilitation. 
Multiple-Purpose Project 
Including Power 
21. CLARENCE CANNON DAM AND 
RESERVOIR, SALT RIVER, MO. 
Location. Salt River rises in Schuyler County, 
- about 12 miles south of Missouri-Iowa State line. 
It flows southeasterly about 192 miles and 
empties into Mississippi River about 2 miles 
above Louisiana, Mo., or about 284 miles above 
mouth of Ohio River. (See Kansas City and 
Quincy sheets of maps of United States published 
by Army Map Service, scale 1:500,000 and 
Geological Survey quadrangle maps, 1:250,000.) 
Previous project. For details, see page 645 of 
Annual Report for 1963. 
Existing project. Project provides for 
construction of a multiple-purpose reservoir, 
including power, flood control, water supply, 
navigation storage, pollution abatement, fish and 
wildlife conservation, and recreation. Dam 
consists of a compacted earth embankment with a 
concrete spillway controlled by tainter gates. 
Dam and spillway are about 1,700 feet long. 
Spillway structure consists of an ogee overflow 
section surmounted by four 50- by 30-foot tainter 
gates. Reservoir will have a storage capacity of 
1,428,000 acre-feet for use of flood control, future 
domestic and industrial water supply, sediment 
storage, and power generation. Project document 
plan provides for installation of two 27,000 
kilowatt units, one conventional and one 
reversible, to be used for pumped storage 
operations. Total Federal project cost estimate 
(1975) is $215,000,000 of which $16,600,000 is for 
lands and damages, and $9,500,000 is for water 
supply. 
Local cooperation. In accordance with 
provisions of Water Supply Act of 1958, the cost of 
storage allocated to water supply would be 
reimbursed by the local sponsor. State of 
Missouri, acting through its State Water 
Resources Board and under authority of the 
General Assembly of State of Missouri by 
legislation passed in 1965, will sponsor this 
project. This legislation provides that the Water 
Resources Board is authorized to make 
reasonable assurances and enter into contracts 
with appropriate Federal departments for 
purposes of discharging non-Federal 
14-11

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
responsibilities relating to municipal and 
industrial water supply storage as permitted by 
applicable Federal legislation on water resources 
projects. Assurances were executed by State 
Board on Apr. 8, 1965. Assurances were reviewed 
by Office of the Attorney General, State of 
Missouri, and it is his opinion that the State of 
Missouri has the legal authority and financial 
capability to execute said assurances. These 
assurances have been approved by Chief of 
Engineers. A water supply contract will be 
entered into with the sponsor before any use of the 
water supply storage provided under this project. 
No local contribution for recreation, including 
recreation aspects of fish and wildlife, is 
required. 
Operations and results during fiscal year. The 
contracts for the turbines, generators, Main Dam 
and Spillway, and a railroad relocation are well 
under way. The Phase I Main Dam and abutment 
exploration and the administration building and 
overlook area contracts are completed. Planning 
on additional project features is continuing. 
Condition at end of fiscal year. Project is 29 
percent complete. Lands acquired to date are 
51,525 acres in fee and 7,459 acres in easements. 
General Investigations 
22. SURVEYS 
Fiscal year costs were $75,556 for four 
navigation studies, $947,026 for twelve flood 
control studies, $2,264 for one comprehensive 
basin study, $68,482 for inventory of dams, and 
$4,469 for review of deauthorization. 
23. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain information studies are authorized 
by Sec. 206 of the 1960 Flood Control Act, as 
amended. The studies are made upon request of 
another Federal agency, a State, or political 
subdivision thereof. They comprise compilation 
and dissemination of information on floods and 
flood damages, including identification of areas 
subject to inundation by floods of various 
magnitudes and frequencies, and general criteria 
for guidance of Federal and non-Federal 
interests and agencies in the use of flood plain 
areas, and provide advice to other Federal 
agencies and local interests for their use in 
planning to ameliorate the flood hazard. 
Fiscal year costs for flood plain management 
services were $205,272, which include $63,875 for 
flood plain management services, $14,612 for 
technical services, and $126,785 for flood plain 
information reports. 
24. RESEARCH AND DEVELOPMENT 
Hydrologic studies: Collecting streamflow and 
rainfall data and making storm and hydrologic 
studies during fiscal year cost $857. 
14-12

ST. LOUIS, MO., DISTRICT 
TABLE 14-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
Kaskaskia River 
Ill. (Regular 
Funds) 
(Contrib. Funds) 
4. Mississippi River 
between Ohio and 
Missouri Rivers 
6. Columbia Drainage 
& Levee District 
No. 3, 
Ill. 
7. East St. Louis and 
Vicinity, Ill. 
8. Harrisonville & 
Ivy Landing 
Drainage & Levee 
District No. 2, 
Ill. 
9. Kaskaskia Island 
Drainage & Levee 
District, Ill. 
10A. Carlyle Lake, Ill. 
(Regular Funds) 
Code 711 Funds 
(Contrib. Funds) 
10B. Lake Shelbyville, 
Ill. (Regular 
Funds) 
Code 711 Funds 
(Contrib. Funds) 
10C. Vandalia Drainage 
& Levee District 
No. 21, Ill. 
2. 
Total Cost to 
Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
$ 8,881,500 
9,771,824 
439,000 
415,753 
375,000 
122,933 
5,300,000 
5,390,984 
5,807,200 
6,242,677 
20,000 
8,894 
$25,184,300 
25,196,991 
58,900 
56,515 
96,279 
109,700 
1,574,600 
1,571,379 
5,301,000 
5,134,107 
5,000
0 
646,900 
413,881 
5,000 
3,782 
103,900 
44,238 
2,078,900 
1,517,554 
32,737
0 
192,263 
191,336 
804,000 
1,469,091 
1,133,900 
834,543 
594,182 
1,250,271 
61,874 
60,085
7 
424,000 
32,363 
50,000 
9,280 
1,676,600 
1,935,807 
19,544
0 
127,886 
87,716 
3,295,000 
3,014,792 
972,000 
1,159,168 
1,000,000 
231,955 
92,969 
88,706 
5,000 
4,998 
100,100 
278,018 
27,837 
54,888 
1,274,400 
1,722,055 
30,000 
52,275 
104,681 
102,641 
3,265,000 
1,232,730 
1,236,000 
1,297,338 
360,000 
457,231 
90,000 
87,193
00 
14-13 
512,700 1,462,400 
801,965 622,288 
- 101,000 
1,112 98,623 
$12,791,200 
8,526,236 
150,700 
147,315 
578,789 
12,700 
8,688,900 
4,078,283 
5,568,900 
4,470,604 
418 
$ 4,700,000 
8,045,277 
521,300 
535,983 
47,207 
452,218 
10,040,000 
10,526,719 
4,612,100 
5,215,046 
100,000 
112,342 
1,370,000 
1,174,036 
375,000 
377,482 
82,000 
65,239 
400,000 
743,368 
28,000 
15,534 
1,415,000 
1,419,953 
166,012 
36,295 
149,988 
98,307
0 
1,288,680 
72,100 
160 
1,459,000 
1,449,190
0 
98 
116,000 
82,412 
25,000 
24,995 
$ 90,651,000' 
90,577,7801 
1,169,900 
1,155,566 
1,159,079 
733,151 
135,914,0002 
131,851,4432 
111,418,977 
111,125,4603 
215,0004 
211,6544 
26,554,8885 
25,441,8616 
581,0007 
580,9997 
82,000 
65,239 
39,250,000 
39,249,852 
105,837 
79,702 
8,983,800 
8,884,135 
3,494,661 
3,334,937 
774,404 
679,585 
44,000,000 
42,902,024 
72,100 
160 
5,694,000 
5,621,670 
16,745,638 
15,865,073 
360,842 
318,396 
471,000 
470,993

TABLE 14-A 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
10D. Dively Drainage 
& Levee District 
No. 23, Ill. 
11. McGee Creek 
Drainage & Levee 
District,Ill. 
12A. Meramec Park 
Lake, Mo. 
12B. Union Lake, Mo. 
Code 760 Funds 
13. Mississippi River 
Agricultural Area 
No. 8, Ill. 
14. Mississippi River 
at St. Louis, Mo. 
(Regular Funds) 
(Contrib. Funds) 
15. Perry County 
Drainage & Levee 
District Nos. 1, 
2, & 3, Mo. 
16. Rend Lake, Big 
Muddy, Ill. 
(Regular Funds) 
Code 711 Funds 
(Contrib. Funds) 
17A. Wood River 
Drainage & Levee 
District, Ill. 
21. � Clarence Cannon 
Dam and Reservoir, 
Salt River, Mo. 
Total Cost to 
Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
$ 300,000 
19,867 
97,400 
79,509 
3,216,000 
3,373,433 
-183,100 
100,198 
70,000 
46,234 
1,200,000 
1,052,370 
5,413 
$ 140,000 
22,408
0 
19,198 
3,680,000 
3,690,997 
942,000 
46,881 
158,000 
141,188 
122,000 
160,971 
1,540,000 
1,207,150 
93 
95,000 
94,849 
$ 705,000 
698,463
0 
1,593 
5,215,000 
5,122,151 
24,900 
44,094 
-16,812
0 
195,000 
180,508
0 
342,518 
180,000 
171,775 
3,371,900 2,669,000 2,200,000 3,416,000 
3,346,991 2,247,541 2,399,803 3,655,331 
- - - 32,400 
- - - 143 
379,000 591,100 727,908 892,500 
285,297 658,791 731,188 841,728 
114,277 800,000 480,000 800,296 
879,780 104,234 29,558 161,043 
209,154 100,000 241,298 238,704 
201,374 47,127 178,454 211,541 
- -5,000 - 25,000 
1,040 4,388 5,424 5,592 
5,668,900 9,200,000 17,650,000 16,585,000 
5,881,049 9,126,190 15,609,714 16,545,618 
1. Excludes $10,461 expended on previous project. 
2. Excludes previous project cost of $1,416,620. 
3. In addition $3,109 was expended for rehabilitation. 
4. Excludes $2,828,200 for previous project. 
5. Includes $3,134,000 for work authorized by Flood 
Control Act of 1965. 
6. Includes $2,219,419 for work authorized by Flood 
Control Act of 1965. 
7. Excludes $4,375,400 for previous project. 
8. Includes $200,000 for definite project under 1938 
Flood Control Act. 
9. Includes $183,638 for definite project study under 1938 
Flood Control Act. 
10. Excludes $240,000 Contributed Funds Other and 
$240,000 actual cost. 
11. Excludes $6,800,700 for previous project. 
12. Excludes $550,000 Area Development Administration 
Funds allotted to the State of Illinois for increased construction 
costs of Interstate Highway 57 to meet project 
requirements, and excludes $449,093 Area Redevelopment 
Administration Funds allotted to the Corps. 
13. Includes $6,103,711 credit to State of Illinois for 
work in kind. 
14. Excludes $14,629,821 for previous project and 
$23,000 contributed funds. 
15. Includes $216,628 for definite project study under 
1938 Flood Control Act. 
14-14 
$ 130,000 
127,661 
33,000 
30,040 
2,122,000 
2,043,317 
336,200 
308,312 
120,000 
104,357 
2,770,000 
3,079,719 
4,285 
19,543 
$ 1,420,000 
1,009,019 
347,400 
347,341 
19,003,0008 
18,894,2678 
3,144,6389 
2,224,2319 
141,188 
141,188 
507,000 
492,069 
77,570,000 
77,326,914 
1,600,16610 
1,592,534 
275,00011 
266,62411 
43,700,90012 
43,324,73012 
32,400 
143 
2,849,300 
2,772,308 
3,830,640 
8,030,80113 
789,155 
638,495 
100,00014 
79.95214 
65,009,52815 
62,828.74515

ST. LOUIS, MO., DISTRICT 
TABLE 14-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 19071 
Mar. 3, 19051 
Mar. 2, 19071 
Jun. 25, 1910 
Jan. 21, 1927 
Jul. 3, 1930 
Mar. 2, 1945 
Sep. 3, 19543 
Jul. 3, 19584 
Oct. 23, 1962 
Jun. 22, 1936 
Oct. 27, 1965 
Oct. 23, 1962 
Oct. 23, 1962 
Jul. 3, 1958 
KASKASKIA RIVER, ILL. (See Section 2 of Text) 
Construct canal, lock, and dam to provide a 9-foot 
navigation channel from mouth to Fayetteville, Ill. 
MISSISSIPPI RIVER BETWEEN OHIO AND 
MISSOURI RIVERS (See Section 4 of Text) 
Project for regulating works in 1881. (To obtain 
a minimum depth of 8 feet). 
Dredging introduced as part of the project. 
These acts practically abrogated that part of project 
for middle Mississippi which proposed regulating 
works. 
Regulating works restored to project and appropriations 
begun with a view to completion of improvement 
between Ohio and Missouri Rivers within 12 years 
at an estimated cost of $21 million, exclusive of 
amounts previously expended. 
For 9 feet deep and 300 feet wide from Ohio River to 
northern boundary of city of St. Louis. 
Project between northern boundary of St. Louis and 
Grafton (mouth of Illinois River) modified 
to provide a channel 9 feet deep and generally 
200 feet wide with additional width around bends. 
Modified to provide construction of a lateral canal with 
lock at Chain of Rocks. 
Modified to provide construction of a small-boat 
harbor opposite Chester, Ill. 
Modified to provide construction of a fixed crest rockfill 
dam 900 feet below Chain of Rocks Bridge. 
COLUMBIA DRAINAGE AND LEVEE DISTRICT 
NO. 3, ILL. (See Section 6 of Text) 
Construct pumping plants and other modifications 
to reduce interior flooding. 
EAST ST. LOUIS AND VICINITY, ILL. (See Section 7 
of Text) 
Raise and enlarge existing levee. 
Construct pumping plant and other modifications 
to reduce interior flooding. 
HARRISONVILLE AND IVY LANDING DRAINAGE AND 
LEVEE DISTRICT NO. 2, ILL. (See Section 8 of Text) 
Construct pumping plants and other modifications to 
reduce interior flooding. 
KASKASKIA ISLAND DRAINAGE AND LEVEE 
DISTRICT, ILL. (See Section 9 of Text) 
Raise and enlarge existing levee. 
KASKASKIA RIVER, ILL. (See Section 10 of Text) 
Deletes Carlyle Reservoir and levees from New Athens to 
Carlyle from Upper Mississippi River Basin Plan and 
reauthorizes them as a part of the Kaskaskia River Plan. 
Construct dam at Shelbyville and six levee projects between 
Cowden and Vandalia and a local protection 
project at New Athens. 
14-15 
S. Doc. 44, 87th Cong., 
1st sess. 
Annual Report, 1881, 
p. 1536. 
H. Doc. 50, 61st Cong., 
1st sess., and H. Doc. 168, 
58th Cong., 2d sess.2 
Rivers and Harbors Committee 
Doc. 9, 69th Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 12, 70th Cong., 
1st sess. 
H. Doc. 231, 76th Cong., 
1st sess. 
H. Doc. 230, 83d Cong., 
1st sess. 
S. Doc. 7, 85th Cong., 
1st sess. 
H. Doc. 543, 87th Cong., 
2d sess. 
Special report on record 
in OCE. 
H. Doc. 329, 88th Cong., 
2d sess. 
H. Doc. 542, 87th Cong., 
2d sess. 
H. Doc. 519, 87th Cong., 
2d sess. 
H. Doc. 232, 85th Cong., 
1st sess.

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 14-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
Oct. 23, 1962 
Jun. 28, 1938 
Nov. 7, 1966 
Nov. 7, 1966 
Aug. 9, 1955 
Adopted by Senate 
and House Committe 
resolutions, 
Oct. 12, 19725 
Oct. 23, 1962 
Jun. 28, 1938 
Oct. 27, 1965 
Oct. 23, 1962 
Oct. 27, 1965 
Deleted requirement that local interests make a cash contribution 
to cost of levees between Cowden and Vandalia. 
Requires that local interests make a cash contribution 
equal to full cost of acquisition of flowage easements 
in those lands acquired by the United States 
which, upon completion of the levee in District 
No. 22, will not be required for construction, 
operation, and maintenance of Carlyle Lake. 
MC GEE CREEK DRAINAGE AND LEVEE 
DISTRICT, ILL. (See Section 11 of Text) 
Reconstruct existing levee and construct pumping 
plant to reduce flooding. 
MERAMEC RIVER BASIN, MO. (See Section 12 
of Text) 
Construct reservoirs and local protection projects. 
Construct Pine Ford, Irondale, and I-38 dams and 
19 Angler-use sites. 
MISSISSIPPI RIVER AGRICULTURAL 
AREA 8, MO. (See Section 13 of Text) 
Raise and enlarge existing levee and alter pumping 
plant to reduce flooding. 
MISSISSIPPI RIVER AT ST. LOUIS, MO. (See Section 
14 of Text) 
Construct floodwall and appurtenant structures to 
afford protection to city of St. Louis. 
PERRY COUNTY DRAINAGE AND LEVEE 
DISTRICTS NOS. 1, 2, & 3, MO. (See 
Section 15 of Text) 
Construct pumping plants and other modifications 
to reduce interior flooding. 
REND LAKE, BIG MUDDY RIVER, ILL. (See Section 
16 of Text) 
Construct dam at Benton, Ill., and subimpoundment 
dams on upper arms of reservoir. 
UPPER MISSISSIPPI RIVER BASIN (See Section 
17 of Text) 
Construct reservoirs and local protection projects. 
WOOD RIVER DRAINAGE AND LEVEE DISTRICT, 
ILL. (See Section 17A of Text) 
Construct pumping station to reduce interior 
flooding. 
CLARENCE CANNON DAM AND RESERVOIR, 
SALT RIVER, MO. (See Section 21 in Text) 
Modified act of 28 Jun. 1938 by deleting the reservoir 
therefrom and reauthorizing it as a separate 
multiple-purpose project. 
Changes name of project from Joanna Dam to 
present designation. 
H. Doc. 351, 88th Cong., 
2d sess. 
H. Doc. 472, 87th Cong., 
2d sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 525, 89th Cong., 
2d sess. 
H. Doc. 510, 89th Cong., 
2d sess. 
S. Doc. 57, 84th Cong., 
1st sess. 
H. Doc. 360, 92nd Cong., 
2d sess. 
H. Doc. 541, 87th Cong., 
2d sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 150, 88th Cong., 
1st sess. 
H. Doc. 507, 87th Cong., 
2d sess. 
Public Law 89-298, 
89th Cong. 
1. Also joint resolution, Jun. 29, 1906. 
2. Contains latest published map. 
3. Inactive. 
4. All work completed. 
5. Authorized under provision of Sec. 201 of the Flood Control 
Act of 1965. 
14-16

ST. LOUIS, MO., DISTRICT 
TABLE 14-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Cuivre River, Mo.' 1883 $ 12,000 $ - 
Moccasin Springs, Mo. 1969 76,4362 
Wabash Railroad Bridges, Illinois River, 
Meredosia, and Valley City, Ill.3 1961 2,653,194 
1. Inactive. River declared nonnavigable by act of 2. Excludes $56,605 contributed funds. 
Mar. 23, 1900. 3. Completed. 
TABLE 14-D LAKES, LEVEES, AND RECREATION FACILITIES 
Estimated 
See Required Total Estimated 
Section Estimated Non-Federal Cost (Date to 
in Text Project Name Federal Cost Cost Revision) 
10. Kaskaskia River, Ill. Lakes: 
Carlyle' $42,720,000 $ 3,635,000 $ 46,355,000 (1975) 
Shelbyville' 44,000,000 16,800,000 60,800,000 (1974) 
Levees: 
Village of New Athens 2 2,140,000 133,700 2,273,700 (1975) 
District No. 21 11,500,000 1,260,000 12,760,000 (1975) 
(Vandalia District)' 
District No. 23 1,820,000 100,000 1,920,000 (1974) 
(Dively District)' 
Districts Nos. 22, 27, 3,620,000 450,000 4,070,000 (1963) 
28, and 28A 
(Cowden to Vandalia)3 
Districts No. 3, 4, 8, 7,590,000 853,000 8,443,000 (1959) 
10, and 13 
(Carlyle to New Athens)3 
12. Meramec River Basin, Mo. Lakes: 
Meramec Park' 94,820,000 20,180,0005 115,000,000 (1975) 
Union' 54,080,000 5,920,0005 60,000,000 (1975) 
Pine Ford 4 59,355,000 15,845,0005 75,200,000 (1975) 
Irondale4 32,010,000 5,290,0005 37,300,000 (1975) 
I-384 15,400,000 1,300,0006 16,700,000 (1975) 
Recreation facilities: 
Angler-use sites4 1,125,000 1,125,000 2,250,000 (1975) 
1. Separate reports are included herein. 
2. See 1971 Annual Report for details. 
3. Inactive. 
4. See 1967 Annual Report for details. 
5. Local interests are required to reimburse the Federal 
Government over a period not to exceed 50 years. 
14-17

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 14-E LEVEES
For Last Full Report Total Cost to Date 
See Anual Report Under This 
Projects1 for Authorization 
Mississippi River: 
Wood River Levee Project, 11.23 1968 $14,629,821 
Stringtown Fort/Chartres and Ivy 
Landing, Ill. 1957 2,123,700 
Kaskaskia Island Levee Project, Ill. 1949 297,460 
Grand Tower Levee Project, Ill. 1959 4,677,900 
Miller Pond Levee Project, Ill. 1955 164,183 
Illinois River: 
Meredosia Lake and Willow Creek Levee, Ill. 1944 249,738 
1. All work under 1938 basin plan authorization 
completed or superseded by 1962 or 1965 Flood 
Control Act. 
2. Excludes $23,000 local contribution. 
3. See individual report herein. 
14-18

ST. LOUIS, MO., DISTRICT 
TABLE 14-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Jun. 30, 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Angler-use sites, Meramec Basin, Mo. 
Big Swan Drainage and Levee District, Illinois River, Ill. 1 
Cache River Diversion, Ill. 
Cape Girardeau, Mo., reaches Nos. 1, 3, and 42 
Cape Girardeau, Mo., No. 23 
Chouteau, Nameoki, and Venice Drainage and Levee 
District, Ill.3 
Clear Creek Drainage and Levee District, Ill.4 
Community of Eldred, Illinois River, Ill.' 
Community of Meredosia and Willow Creek, and Coon Run 
Drainage and Levee Districts, Illinois River, Ill.1 
Degonia and Fountain Bluff Levee and Drainage 
District, Ill. 3 
East Cape Girardeau and Clear Creek Drainage 
District, Ill.4 
Eldred and Spankey Drainage and Levee District, 
Illinois River, Ill.' 
Emergency bank protection for certain highway and 
railroad facilities at Price Landing, Mo. (see 
Flood Control Act of 1944) 5 
Emergency repairs to levees on Mississippi, Illinois, and 
Kaskaskia Rivers and flood fighting and rescue work 
(Sec. 5, Flood Control Act of 1941, as amended)5 
Emergency protection for certain highway and 
railroad facilities at Chester, Ill., bridge 
(Sec. 12, Flood Control Act of 1944)3 
Emergency protection for Illinois approach, Chain of Rocks 
Bridge (Sec. 12, Flood Control Act of 1944)3 
Fort Chartres and Ivy Landing Drainage District No. 5, Ill. 
Fort Chartres and Ivy Landing Drainage District No. 5 
and Stringtown Drainage and Levee District No. 4, Ill. 
Hartwell Drainage and Levee District, Illinois River, Ill.' 
Hillview Drainage and Levee District, Illinois River, Ill.' 
Indian Creek area, Illinois River, Ill.' 
Keach Drainage and Levee District, Illinois River, Ill.' 
Meredosia Lake and Willow Creek, 11.1 
Mississippi River Agricultural Area No. 10, Mo. 
Mississippi River Agricultural Area No. 12, Mo. 
Mississippi River, Alton to Gale, Ill., underseepage measures 
North Alexander Drainage and Levee District, Ill. 
Nutwood Drainage and Levee District, Illinois River, Ill.' 
Prairie du Pont Levee and Sanitary District, Ill. 
Prairie du Rocher and vicinity, Ill. 
Preston Drainage and Levee District, Ill. 
Richland Creek, Ill. 
Scott County Drainage and Levee District, Illinois River, Ill.' 
Ste. Genevieve Levee District No. 1, Mo. 
St. Louis County Drainage and Levee District, Mo. 
Urban areas at Alton, Ill. 
Village of New Athens, Ill. 
Valley City Drainage & Levee District, Ill.3 7 
Weidmer Chemicals Drainage and Levee District, Mo. 
1967 $ - $ - 
1953 
1959 
1965 
1955 
1964 
1959 
1963 
1950 
1953 
1952 
1946 
1970 
1971 
1944 
1967 
1967 
1957 
1970 
1959 
1959 
1969 
1949 
1938 
1960 
1971 
1967 
1938 
2,837,114 
22,000 
5,157,805 
185,700 
4,984,500 
5,889,500 
1,920,600 
50,000 
1,033,279 
50,000 
25,000 
1,154,800 
249,738 
85,422 
939,569 
6,005,1276 
3,882,600 
1,866,910 
401,000 
192,000 
1,928,000 
91,952 
i. Projects authorized or modified by Flood Control Act 
of Oct. 23, 1962 (see H. Doc. 472, 87th Cong., 2d sess., 
for details). 
2. Inactive project. 
3. Completed. 
4. Completed except for seepage control measures, 
which are inactive. 
5. Work complete, now performed under Public Law 99. 
6. Includes $5,235,927 for previous project. 
7. Authorized by Chief of Engineers (Sec. 205, 1948 Flood 
Control Act, as amended). 
14-19

GALVESTON, TEX., DISTRICT* 
Galveston District comprises drainage basins 
of all short streams arising in coastal plain of 
Texas and flowing into Gulf of Mexico, including 
entire basins of Buffalo Bayou, San Jacinto, 
San Bernard, Lavaca, Navidad, Mission, and 
Aransas Rivers. It embraces Agua Dulce, San 
Fernando, and Olmos Creek Basins draining into 
Baffin Bay, and coastal area south thereof to 
the Rio Grande and east of western Boundary 
of Starr County, Tex. It includes lower basins of 
major streams flowing into Gulf of Mexico: 
Sabine River, Tex. and La., downstream from 
U.S. Highway 190 crossing at Bon Wier, Tex.; 
Neches River downstream from Town Bluff 
gaging station; Trinity River downstream from 
Texas State Highway 19 crossing at Riverside, 
Tex.; Brazos River downstream from confluence 
with Navasota River; Colorado River downstream 
from gaging station at Austin, Tex.; 
Guadalupe River downstream from confluence 
with San Marcos River; San Antonio River 
downstream from confluence with Escondido 
Creek; Nueces River downstream from confluence 
with Frio and Atascosa Rivers. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control (Southwestern 
Division) ................... 
2. Brazos Island Harbor, Tex........... 
3. Cedar Bayou, Tex. ............... 
4. Corpus Christi Ship Channel, Tex..... 
5. Freeport Harbor, Tex................ 
6. Galveston Harbor and Channel, Tex. . 
7. Gulf Intracoastal Waterway 
Between Apalachee Bay, Fla., 
and the Mexican Border ............. 
8. Houston Ship Channel, Tex.......... 
9. Matagorda Ship Channel, Tex........ 
10. Sabine-Neches Waterway, Tex........ 
11. Texas City Channel, Tex............. 
12. Trinity River and Tributaries, Tex.... 
12.AAnahuac Channel, Tex............... 
12.B Channel to Liberty, Tex.............. 
12.C Wallisville Lake, Tex................ 
13. Other Authorized Navigation 
Projects............................ 
14. Navigation Work under Special 
Authorization ..................... 
Beach Erosion Control 
15. Corpus Christi Beach, Tex. 
(Restoration Proiect) ................ 
Page 
15-2 
15-2 
15-2 
15-3 
15-4 
15-5 
15-6 
15-7 
15-8 
15-8 
15-9 
15-9 
15-10 
15-10 
15-10 
15-11 
15-11 
Flood Control Page 
16. Buffalo Bayou and Tributaries, Tex.. 15-12 
17. Clear Creek, Tex................... 15-12 
18. Freeport and Vicinity, Tex. 
Hurricane-Flood Protection......... 15-13 
19. Guadalupe River (Remove Log 
Jams), Tex.......,.................15-13 
20. Highland Bayou, Tex............... 15-13 
21. Lower Rio Grande Basin, Tex....... 15-13 
22. Peyton Creek, Tex ............... 15-14 
23. Port Arthur and Vicinity, Tex., 
Hurricane-Flood Protection ......... 15-14 
24. Taylors Bayou, Tex .............. 15-15 
25. Texas City and Vicinity, Tex., 
Hurricane-Flood Protection ......... 15-15 
26. Vince and Little Vince 
Bayous, Tex. ...................... 15-15 
27. Inspections of Completed 
Flood Control Works .............. 15-16 
28. Other Authorized Flood 
Control Projects .................. 15-16 
29. Flood Control Work under 
Special Authorization ............. 15-16 
General Investigations 
30. Surveys ........................... 15-16 
15-11 31. Collection and Study of Basic Data.. 15-16 
* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text 
and also appear at the end of this chapter. 
15-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. AQUATIC PLANT CONTROL (SOUTHWESTERN 
DIVISION) 1965 ACT 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
Texas and the Sabine River Watershed of 
Louisiana. 
Previous project. For details see page 699 of 
Annual Report for 1963. 
Existing project. A comprehensive project to 
provide for control and progressive eradication of 
water-hyacinth, alligatorweed, Eurasian watermilfoil, 
and other obnoxious aquatic plant 
growths, from navigable waters, tributary 
streams, connecting channels, and other allied 
waters in Texas in the combined interest of 
navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, public health, and 
related purposes, including continued research for 
development of the most effective and economic 
control measures. (See Table 15-C Other 
Authorized Navigation Projects paragraph for 
completed project authorized by 1958 and 1962 
River and Harbor Acts.) (Also see Table 15-B for 
authorizing legislation.) Estimated cost for new 
work is: Federal (Corps) $1,270,000 and non- 
Federal $483,000. 
Local cooperation. Sec. 302, 1965 River and 
Harbor Act, applies. Non-Federal work contribution 
estimated at $483,000. 
Operations and results during fiscal year. Engineering 
and design and supervision and administration 
cost $7,376 and $4,136. Reimbursement 
to State for Government's share of cost of $62,852 
for eradication was made. In addition, the State 
performed $22,975 of eradication for which credit 
as work-in-kind was given. 
Condition at end of fiscal year. Aquatic plant 
control work continued in the Nueces River Basin, 
North Coastal Area, Guadalupe River Basin, 
Sabine River Basin, Trinity River Basin, Cypress 
Creek Basin, and the Neches River Basin. Work 
was initiated in the South Coastal area. 
2. BRAZOS ISLAND HARBOR, TEX. 
Location. At extreme south end of coast of 
Texas, about 7 miles north of mouth of Rio 
Grande and about 5 miles east of Brownsville, 
Tex. (See National Ocean Survey Chart 11301.) 
Previous project. For details see page 1017 of 
Annual Report for 1932. 
Existing project. Provides for channel dimensions 
in various sections of the waterway as shown 
in Table 15-F. 
Project also provides for dual jetties at the gulf 
entrance, a north jetty 6,330 feet long a south 
jetty 5,092 feet long, and a 1,000-foot extension to 
existing north jetty and for maintenance of 3rd 
fishing harbor constructed by local interests. 
Under ordinary conditions, mean tidal range is 
about 1.5 feet, and extreme range is about 2 feet. 
All depths refer to mean low tide. To some extent, 
height of tides is dependent on the wind, and 
during strong "northers" in winter season, water 
surface in southern end of Laguna Madre may be 
raised 4 feet or more above mean low tide in the 
gulf. Estimated cost for new work is: $23,064,000 
Federal (Corps), excluding expenditures on previous 
projects, and non-Federal $2,080,000 
including $1,683,258 contributed and $396,742 
lands. (See Table 15-B for authorizing legislation.) 
Local cooperation. Complied with except as 
required by section 101, 1960 River and Harbor 
Act. Non-Federal contributions, $1,683,258. 
Terminal facilities. Numerous terminal facilities 
for bulk and liquid cargo are available. (See Port 
Series No. 26, revised 1969). Facilities are 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design and supervision 
and administration cost $11,617 and $111,017. 
Condition and operation studies, inspections and 
reports, and project condition surveys including 
real estate activities cost $54,379. A test disposal 
area for pipeline dredging entrance channel cost 
$23,943. Miscellaneous maintenance by hired 
labor totaled $845. (See Table 15-H for dredging 
operations.) 
Condition at end of fiscal year. Existing project 
is about 50 percent complete. Work remaining 
consists of widening Brownsville Channel from 
Goose Island to Brownsville turning basin, 
deepening southeast corner of Brownsville turning 
basin to 36 feet, and extending north jetty 1,000 
feet. (See Table 15-E for total cost of existing 
project to June 30, 1975.) 
3. CEDAR BAYOU, TEX. 
Location. The bayou is about 30 miles long. It 
flows to the south and empties into northwest 
corner of upper Galveston Bay, about 1.5 miles 
below mouth of San Jacinto River and about 28.5 
miles north of Galveston, Tex. (See National 
Ocean Survey Chart 11326.) 
Previous project. For details see Annual Report 
for 1938. 
Existing project. (See Table 15-F for existing 
project dimensions provided for in this waterway.) 
Project also includes jetties at mouth of bayou 
provided for under previous project. Under 
ordinary conditions mean tidal range is about 0.6 
foot and extreme range 1.2 feet. Height of tides is 
dependent largely on the wind, and during strong 
"northers" in winter season, water surface may be 
15-2

GALVESTON, TEX., DIST. 
depressed 2 feet below mean low tide. Channel 
from Mile 3.0 to Mile 11.0 is in inactive category. 
Channel from the inner end of the previously 
completed work to Mile 3.0, a point just above the 
U.S. Steel Company dock, has been reclassified to 
acive. Estimated cost for new work $643,000 
Federal (Corps) and $135,000 non-Federal, 
consisting of $25,000 cash contribution and 
$110,000 lands and damages. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. Fully complied with except 
for the inactive portion. Non-Federal contribution 
was $25,000. 
Terminal facilities. U.S. Steel Company has a 
barge dock at bayou mile 2.8, and there are a few 
small wharves, privately owned, for local use at 
various places along Cedar Bayou. Facilities are 
considered adequate for existing commerce. 
Operation and results during fiscal year. New 
Work: Engineering and design and supervision 
and administration for dredging Cedar Bayou 
Mile -0.1 to Mile 3.0 cost $947 and $26,943. Cost 
for dredging this portion of the channel was 
$482,838. Maintenance: Repairs to reference line 
cost $7,140. Project condition surveys cost $613. 
Condition at end of fiscal year. Channel was 
complete to project dimensions from Houston 
Ship Channel to first bend in Cedar Bayou above 
the mouth in 1931. Dredging from Mile -0.1 to 
Mile 3.0 was completed in March 1975. (See Table 
15-E for total cost of existing project to June 30, 
1975.) 
4. CORPUS CHRISTI SHIP CHANNEL, TEX. 
Location. This project, formerly known as the 
Port Aransas-Corpus Christi Waterway, Tex., 
was changed to Corpus Christi Ship Channel, Tex. 
by 1968 River and Harbor Act. This is a consolidation 
of old improvements of Port Aransas, 
Tex., and channel from Aransas Pass to Corpus 
Christi, Tex. Aransas Pass is on southern portion 
of Texas Coast, 180 miles southwest of Galveston 
and 132 miles north of mouth of Rio Grande. 
Aransas Pass connects Corpus Christi Bay and 
Aransas Bay with the gulf. Waterway extends 
from deep water in the gulf through Aransas Pass 
jettied entrance, thence westerly 20.75 miles to 
and including a turning basin at Corpus Christi, 
thence westerly 1.75 miles through Industrial 
Canal to and including turning basin at Avery 
Point, thence westerly 4.25 miles to and including 
a turning basin near Tule Lake, thence northwesterly 
1.8 miles to and including a turning basin 
at Viola, Tex. (See National Ocean Survey Charts 
11308, 11309, 11311, and 11314.) 
Previous Project. For details see page 1861 of 
Annual Report for 1915. 
Existing project. (See Table 15-F for existing 
project dimensions provided for in various 
channels and basins comprising this waterway.) 
Project also provides for two rubblestone jetties 
at Aransas Pass entrance, extending into the gulf 
from St. Joseph and Mustang Islands, project 
lengths of which are 11,190 and 8,610 feet, 
respectively. Project further provides for a stone 
dike on St. Joseph Island about 20,991 feet long, 
connecting with north jetty and extending up this 
island to prevent a channel being cut around jetty. 
Project also provides for a breakwater at the 
entrance to the harbor area at Port Aransas, and 
for the realignment of the existing 12-foot by 
100-foot project channel to Port Aransas. The 
breakwater consists of two overlapping sections. 
The one on the east side of the realigned entrance 
channel has a length of 830 feet and the second, 
located on the west side of the entrance channel, 
has a length of 1,290 feet. The channel to Port 
Aransas was relocated in the 300-foot clear 
distance between the overlapping sections. The 
portion of the channel remaining inside the breakwaters 
was widened to 150 feet. Under ordinary 
conditions, mean tidal range at Aransas Pass is 
about 1.1 feet and extreme range about 2 feet, and 
at Corpus Christi mean range about 1 foot and 
extreme about 1.5 feet. Heights of tides are 
dependent largely on strength and directions of 
winds, and during strong "northers" in the winter 
season water surface may be depressed as much as 
3 feet below mean low tide. Estimated cost for new 
work is: Federal (Corps) $49,324,515, including 
$456,515 for Port Aransas Breakwaters and 
exclusive of amount expended on previous 
projects; and non-Federal $11,738,068 (includes 
$768 for Port Aransas Breakwaters) including 
$3,118,840 contributed funds and value of useful 
work performed, $1,615,228 lands, $5,019,000 
relocations and $1,985,000 other costs. In 
addition, non-Federal cost to levee disposal areas 
on the 45-foot project was $232,000. (See Table 
15-B for authorizing legislation.) 
Local cooperation. Fully complied with except 
for provisions of Sec. 101 of 1968 River and 
Harbor Act. Non-Federal contributions estimated 
at $3,118,840, excluding the $232,000 for construction 
of leveed disposal areas on the 45-foot 
project. 
Terminal facilities. Terminal facilities on 
Harbor Island at head of Aransas Pass, Ingleside, 
Corpus Christi, La Quinta, Avery Point, and 
Viola, are considered adequate for existing 
commerce. (See Port Series, No. 25, revised 1968, 
Corps of Engineers.) 
Operations and results during fiscal year. New 
Work: Engineering and design and supervision 
and administration for the 45-foot project cost 
$345,980 and $408,337. Cost for a dredging 
contract completed in FY 1974 was $11,396. (See 
15-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Table 15-H for dredging operations.) 
Maintenance: Engineering and design and 
supervision and administration cost $32,516 and 
$18,665. Condition and operation studies, and 
inspections and reports, including real estate 
activities cost $122,517. Miscellaneous maintenance 
including repair of directional signs, and 
channel reference lines by hired labor totaled $450. 
A test disposal area for pipeline dredging entrance 
channel cost $43,952. (See Table 15-H for 
dredging operations.) 
Condition at end of fiscal year. The project is 
about 66 percent complete exclusive of inactive 
portions. The Port Aransas-Corpus Christi 
40-foot project was initiated in 1963 and 
completed in 1966. The Jewel Fulton Canal was 
initiated in 1962 and completed in 1963. The Port 
Aransas Breakwaters were completed in July 
1973. The work remaining consists of deepening 
entrance channel to 47 feet; deepening all other 
deep-draft channels to 45 feet; widening of 
channels and basins; constructing a turning point 
on main channel at junction with La Quinta 
channel and constructing a mooring area at Port 
Ingleside with dolphins. Preconstruction planning 
on 45-foot project has been completed, dredging of 
La Quinta Channel to 40 feet was completed in 
June 1973, entrance and jetty channels have been 
dredged to project depth and width except for a 
small quantity of dredging in the outside 
quarters, and dredging of channel from Harbor 
Island to mile 8.5 at 45-foot depth has been 
completed. Completion of La Quinta Channel to 
45 feet will be by separate contract. (See Table 
15-E for total cost of existing project to June 30, 
1975.) 
5. FREEPORT HARBOR, TEX. 
Location. Formed by improvement of Brazos 
River, Tex., from mouth to about 6 miles 
upstream to Freeport, Tex. (See National Ocean 
Survey Charts 11321 and 11322.) 
Previous projects. For details see page 1860 of 
Annual Report for 1915, and page 872 of Annual 
Report for 1938. 
Existing project. Existing project dimensions 
for various channels and basins are shown in 
Table 15-F on channel dimensions at end of 
chapter. (See also Table 15-B authorizing legislation.) 
Existing project also provides for: Dual jetties 
and a diversion canal for the Brazos River, 
including a dam, a lock in the dam and necessary 
auxiliary equipment. Also provides for rehabilitation 
of southwest jetty and the relocation of the 
northeast jetty (about 640 feet to the northeast); 
realignment of the channel between the Jetty 
Channel and Brazosport Turning Basin; realignment 
of the channel between Brazosport Turning 
Basin and Upper Turning Basin; relocation of 
Upper Turning Basin; and public use facilities 
adjacent to the Freeport Jetties. The 30-foot 
channel from Upper Turning Basin to Stauffer 
Chemical Plant, including the turning basin, and 
lock in diversion dam are in the inactive category. 
Under ordinary conditions mean tidal range is 
about 1.5 feet and extreme range about 2.5 feet. 
Except under extreme conditions, rises on river 
and in diversion channel do not cause greater 
variations in water surface than those caused by 
tidal action. Estimated cost of new work is: 
$25,527,000 Federal (Corps); and $5,575,000 
non-Federal, including $918,303 contributed 
funds, $360,249 contributed work, $3,443,448 
lands, and $853,000 levees and spillways. 
Local cooperation. Fully complied with except 
for inactive portion and Section 101 of River and 
Harbor Act of 1970. River and Harbor Act of 1970 
requires local interests provide necessary lands, 
easements, and rights-of-way required for public 
use facilities; and when the appraised value of 
land, easements, and rights-of-way amounts to 
less than 50 percent of the total first cost of the 
development, make additional contributions 
sufficient to bring the non-Federal share to at 
least that level. The cash contribution is presently 
estimated at $160,000 which combined with land, 
estimated $120,000, is 50 percent of the cost of 
public use facilities. Cash contribution at time of 
authorization estimated at $95,000 in addition to 
providing land estimated at $70,000. Total contribution 
estimated at $1,278,552. 
Terminal facilities. Small privately owned 
wharves, two oil docks, one acid dock, two shell 
unloading docks and one caustic dock. Brazos 
River Navigation District has one large dock with 
four transit sheds over rail facilities permitting 
all-weather work. Facilities considered adequate 
for existing commerce. (See Port Series No. 26, 
revised 1969, for additional facilities.) 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued on 
the 45-foot project at a cost of $177,238. 
Maintenance: Engineering and design and 
supervision and administration cost $93,557 and 
$154,790. Condition and operation studies, 
inspections and report, and real estate activities 
cost $47,416. A contract for bend easing was 
initiated at a cost of $5,000. Miscellaneous maintenance, 
including repair of directional signs by 
hired labor, totaled $1,052. A test disposal area 
for pipeline dredging entrance channel cost 
$25,943. (See Table 15-H for dredging operations.) 
Condition at end of fiscal year. Existing project 
is 16 percent complete (exclusive of inactive 
portions). Work remaining consists of realigning, 
deepening and widening the Outer Bar and Jetty 
15-4

GALVESTON, TEX., DIST. 
Channels; relocating the northeast jetty; rehabilitating 
the southwest jetty; realigning and 
deepening the harbor channel between the jetty 
channel and the Upper Turning Basin; relocating 
and enlarging the Upper Turning Basin; constructing 
a turning point near the northwesterly 
end of the jetty channel; enlarging Brazosport 
Turning Basin; deepening Brazos Harbor Channel; 
and enlarging and deepening Brazos Harbor 
Turning Basin. Preconstruction planning is in 
progress on this remaining work. The 38--36 foot 
project was initiated in 1961 and completed in 
1962. (See Table 15-E for total cost of existing 
project to June 30, 1975.) 
6. GALVESTON HARBOR AND CHANNEL, 
TEX. 
Location. A consolidation of authorized improvements 
at Galveston, Tex., which includes 
projects formerly identified as Galveston Harbor, 
Tex.; Galveston Channel, Tex.; and Galveston 
seawall extension. Entrance to Galveston Harbor 
is on Gulf of Mexico on the northern portion of the 
Texas Coast. Galveston Channel extends from a 
point in Galveston Harbor between Bolivar 
Peninsula and Fort Point to and along wharf front 
of Galveston, Tex., and is about 5 miles long and 
1,200 feet wide. (See National Ocean Survey Chart 
11324 /5.) 
Previous projects. For details see page 1854 of 
Annual Report for 1915. 
Existing project. Provides for channel dimensions 
in sections of the waterway shown in Table 
15-F. (Also see Table 15-B for authorizing 
legislation.) 
Also provided are: two rubble-mound jetties, 
the south one extending from Galveston Island 
and the north one extending from Bolivar 
Peninsula, for distances of 35,900 feet and 25,907 
feet, respectively, into the Gulf of Mexico; a 
concrete seawall from the angle at Sixth Street 
and Broadway, in the city of Galveston, to the 
south jetty, and a 16,300-foot extension of the 
concrete seawall in a southwesterly direction from 
61st Street; for 11 groins along the gulf shore 
between 12th Street and 61st Street; and for 
maintenance of seawall from the angle at 6th 
Street and Broadway to the south jetty. Under 
ordinary conditions, mean tidal range in Galveston 
harbor is 1.6 feet on outer bar and 1.4 feet on 
inner bar with extreme ranges of 2.3 and 2.1 feet, 
respectively. Mean tidal range in Galveston 
channel is about 1.3 feet and extreme range about 
2 feet under ordinary conditions. Height of tides in 
both Galveston harbor and channel is dependent 
largely on the wind, and during strong "northers" 
water surface may be depressed 2 feet below mean 
low tide. Estimated cost of new work is: 
$19,924,900 Federal (Corps); and $4,211,000 
non-Federal, including $3,620,275 contributed 
funds, $564,725 lands, and $26,000 levees and 
spillways. 
Local cooperation. Complied with except for 
inactive portions. 
Terminal facilities. None on Galveston Harbor, 
which is entrance channel leading to terminal 
facilities on Galveston, Texas City, and Houston 
Ship Channels. Galveston Channel terminal 
facilities are mostly on south side of channel. 
Principal wharves, owned by city of Galveston, 
extend from 10th to 41st Street (see Port Series 
No. 23, revised 1969). A containership terminal 
equipped with a crane capable of stacking 
containers three units high on the deck of any 
normal containership has been completed and 
placed into operation by the city of Galveston at 
Piers 10 and 11, on the south side of Galveston 
Channel. The city of Galveston has also placed 
into operation a barge terminal equipped with two 
35-ton and one 5-ton cranes for loading and 
unloading barges on Lash and Seabee ships at 
Pier 35 and a docking and a holding area for Lash 
and Seabee barges on Pelican Island, directly 
across the channel from Piers 35 and 36. Present 
facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
Work: Engineering and design and supervision 
and administration for the 40-foot Galveston 
Channel cost $31,484 and $12,047. Cost for 
dredging the 40-foot channel was $313,561. 
Maintenance: Engineering and design and 
supervision and administration cost $21,536 and 
$244,056. Condition and operation studies, 
inspections and reports, and project condition 
surveys, including real estate activities, cost 
$114,451. Miscellaneous maintenance totaled 
$6,010. A security fence at Fort San Jacinto 
disposal area cost $6,990. A test disposal area for 
pipeline dredging entrance channels cost $28,943. 
Final cost for a dredging contract completed in FY 
1974 was $59,176. Adjustment of FY 1974 cost for 
the U.S. Hopper Dredge GERIG was -$195,142. 
(See Table 15-H for dredging operations.) 
Condition at end of fiscal year. Existing project 
is complete, exclusive of inactive portions and 
deepening of the Galveston Channel to 40 feet. 
Dredging of Galveston Channel to 36' depth was 
completed in November 1966. Dredging of the 
realigned entrance and Outer Bar Channel was 
initiated in 1965 and completed in October 1967. 
Rehabilitation of the Beach Front Groins was 
completed June 1, 1970. Dredging of Galveston 
channel to 40 feet was initiated in February 1975. 
(See Table 15-E for total cost of existing project to 
June 30, 1975.) 
15-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
7. GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FLA., AND 
MEXICAN BORDER (GALVESTON 
DIST.) 
Location. Extends from a point on Sabine River 
about 3 miles below Orange, Tex., to Brownsville, 
Tex., about 421 miles; a navigation channel, 
about 7 miles long, in Colorado River, extending 
from Matagorda, Tex., to Gulf of Mexico; a 
tributary channel in San Bernard River, extending 
from Intracoastal Waterway crossing to State 
highway bridge some 30 miles above crossing; a 
tributary channel in Colorado River extending 
from Intracoastal Waterway upstream 15.5 miles; 
a tributary channel extending about 14 miles from 
Intracoastal Waterway to Palacios, Tex.; a 
tributary channel extending about 2 miles from 
Intracoastal Waterway to Rockport, Tex.; a 
tributary channel extending about 6 miles from 
Intracoastal Waterway near Port Aransas, Tex., 
to town of Aransas Pass, Tex.; a tributary 
channel about one-fourth mile long extending 
from Intracoastal Waterway near Port O'Connor, 
Tex., into Barroom Bay; a tributary channel 
extending about 38.8 miles from Intracoastal 
Waterway via Seadrift to a point in Guadalupe 
River 5.5 miles below Victoria, Tex.; a harbor of 
refuge for small craft at Seadrift; a channel 
extending from gulf to Port Mansfield, Tex., 
about 11 miles; and a tributary channel in Arroyo 
Colorado extending from Intracoastal Waterway 
to a point near Harlingen, Tex., about 31 miles; 
side channels in vicinity of Port Isabel, Tex., and 
a small boat basin at Port Isabel, Tex., and a 
tributary channel extending from Intracoastal 
Waterway main channel at a point in West Galveston 
Bay into Offatts Bayou about 2.2 miles 
with a west turnout (wye connection) 12 feet deep 
and 125 feet between Offatts Bayou Channel and 
the Gulf Intracoastal Waterway. (See National 
Ocean Survey Charts 11302, 11303, 11305, 11306, 
11308, 11309, 11314, 11315, 11317, 11319, 11322, 
11326, and 11331.) 
Previous project. For details see page 1859 of 
Annual Report for 1915. (West Galveston Bay 
and Brazos River Canal, Tex.) 
Existing project. Existing project dimensions 
provided for in main channel of waterway: A 
channel 12 feet deep (below mean low tide) and 125 
feet wide from the Sabine River to Brownsville, 
Texas. Relocation of channel 12 feet deep by 125 
feet wide in Matagorda Bay, miles 454.3 to 471.3, 
relocation of channel 12 feet deep by 125 feet wide 
in Corpus Christi Bay, miles 539.4 to 549.7 
(mileage is west of Harvey Lock Louisiana); and 
alternate channel, 12 feet deep (below mean low 
tide) and 125 feet wide via Galveston Channel and 
Galveston Bay to the Galveston causeway; 
maintenance of existing channel 12 feet deep by 
125 feet wide through Lydia Ann Channel, 
between Aransas Bay and Aransas Pass; 
provisions of such passing places, widening of 
bends, locks and guard locks, Railway bridges 
over artificial cuts as are necessary, and the 
tributary channels shown in tabulation. The 
authorized channel 16 feet deep and 125 feet wide 
from Sabine River to Houston Ship Channel is 
inactive (See Table 15-G on existing project 
dimensions provided for in tributary channels; 
also Table 15-B on authorizing legislation.) 
Mean tidal variation is 0.5 foot at Orange, 1 
foot at Port Arthur, 1.3 feet in Galveston Bay, 1.5 
feet at Freeport, 1 foot in Matagorda Bay, 1 foot 
in San Antonio Bay, 1 foot at Corpus Christi, 1.5 
feet at Port Isabel, and 1.5 feet at Brownsville. 
Extreme ranges of tide under ordinary conditions 
are 1 foot at Orange, 1.5 feet at Port Arthur, 2 feet 
in Galveston Bay, 2 feet at Freeport, 1.5 feet in 
Matagorda and San Antonio Bays, 1.5 feet at 
Corpus Christi, 2 feet at Port Isabel, and 1.5 feet 
at Brownsville. Height of tides is dependent 
largely on wind. Strong north winds have 
depressed water surface as much as 2 feet below 
mean low tide. Estimated cost for new work is: 
$61,389,880, Federal (Corps), including $8,414 for 
Port Isabel Side Channel, $46,559 for Port Isabel 
Small Boat Basin, and $356,466 for Offatts 
Bayou, and excluding expenditures on previous 
projects; non-Federal $12,293,224 ($395,000 
voluntarily expended on Gulf Intracoastal Waterway, 
$46,559 contributed funds for Port Isabel, 
$49,665 contributed funds for Offatts Bayou, 
$5,195,000 lands for Gulf Intracoastal Waterway, 
$11,000 lands for Port Isabel, $4,454,000 
relocations for Gulf Intracoastal Waterway and 
$2,142,000 other costs Gulf Intracoastal Waterway.) 
Local cooperation. Fully complied with except 
for inactive portions, and provisions of section 
101, 1962 River and Harbor Act, section 301, 1965 
River and Harbor Act, and section 101, 1968 
River and Harbor Act. Non-Federal contributions 
were $395,000 for Gulf Intracoastal Waterway, 
$46,559 for Port Isabel, Tex., and $49,665 for 
Offatts Bayou, Tex. 
Terminal facilities. There are terminal facilities 
at Aransas Pass, Port Arthur, Galveston, Port 
Isabel, and Brownsville. See Port Series No. 22 
(revised 1969), Port Series No. 23 (revised 1969), 
Port Series No. 25 (revised 1968) and Port Series 
No. 26 (revised 1969), Corps of Engineers. Local 
interests constructed terminal facilities at Port 
Mansfield and Port Harlingen. There are 
numerous privately owned piers and wharves 
along the waterway. A 330-foot navigation 
district owned general cargo dock, a 770-foot 
private dock and a 760-foot private timber trestle 
has recently been completed at the upper end of 
the Channel to Victoria. Facilities are adequate for 
15-6

GALVESTON, TEX., DIST. 
existing commerce. 
Operation and results during fiscal year. New 
Work: Preconstruction planning continued on the 
Chocolate Bayou Channel at a cost of $26,696. 
Preconstruction planning continued on Mouth of 
Colorado River at a cost of $141,660. Preconstruction 
planning continued on the Relocation 
of the Main Channel across Corpus Christi Bay at 
a cost of $18,136. Supervision and administration 
cost for Offatts Bayou was reduced by $679 
because of liquidated damages assessed the 
contractor. 
Maintenance: The Brazos River Floodgates and 
the Colorado River Locks were operated and 
maintained at a cost of $155,410 and.$187,000. 
Engineering and design for the above structures 
cost $39,518 and $27,180. In addition, supervision 
and administration for the above structures cost 
$71,919 and $62,383. General repairs at the 
Brazos River Floodgates to the guidewalls totaled 
$8,221. General repairs to the roads at Brazos 
River Floodgates and Colorado River Locks cost 
$10,000 and $10,000. Construction of barge 
mooring anchors at Brazos River Floodgates 
totaled $96,720. Condition and operation studies, 
inspections and reports, real estate activities and 
project condition surveys on the Main Channel 
and Tributaries cost $317,681. Engineering and 
design and supervision and administration for the 
Main Channel and Tributaries cost $172,523 and 
$353,896. Repairs by hired labor to levee slopes 
and drainage structures along the Channel to 
Victoria totaled $13,350. Directional signs and 
channel reference lines were repaired by hired 
labor at a cost of $3,546. Final cost for dredging 
during Fiscal Year 1974 in Matagorda Bay totaled 
$1,562. Final cost for settlement of a claim on 
dredging during Fiscal Year 1974 on the Colorado 
River Flood Discharge Channel totaled $2,243. 
Final cost for settlement of a claim on dredging 
during Fiscal Year 1973 from Mile 308 to High 
Island totaled $11,721. (See Table 15-H for 
dredging operations.) 
Condition at end of fiscal year. Existing project 
is about 75 percent complete, exclusive of inactive 
portions. Removal of the railroad bridge across 
the canal at Mud Bayou was completed and 
operation and care of the facility was discontinued 
on April 14, 1969. Deepening the existing 6 foot 
by 60 foot side channels at Port Isabel to 12 feet 
was completed February 22, 1972. Offatts Bayou 
channel was completed January 1974. Work 
remaining consists of the following: A channel 12 
feet deep and 125 feet wide through a relocated 
route in Matagorda Bay and a channel 12 feet 
deep and 125 feet wide through a relocated route 
in Corpus Christi Bay (Texas Section); dredging 
Chocolate Bayou channel; and constructing a salt 
water barrier in Chocolate Bayou channel; 
constructing of jetties at mouth of Colorado 
River; dredging a navigation channel from gulf to 
turning basin at Matagorda, Tex.; constructing a 
dam across present diversion channel; and 
constructing a new diversion channel to Matagorda 
Bay. (See Table 15-E for total cost of 
existing project to June 30, 1975.) 
8. HOUSTON SHIP CHANNEL, TEX. 
Location. Connects Galveston Harbor, at a 
point opposite Port Bolivar, with city of Houston, 
Tex., extending 50 miles northwesterly across 
Galveston Bay through San Jacinto River and 
Buffalo Bayou to a turning basin at head of Long 
Reach with light-draft channel 7 miles long from 
turning basin to Main Street, Houston. (See 
National Ocean Survey Charts 11324/5, 11327, 
11328, and 11329.) 
Previous project. For details see page 1856 
Annual Report for 1915. 
Existing project. Provides for construction of 
certain cut-offs, for easing sharp bends, for 
construction of an earthen dam across the upper 
end of Turkey Bend, for the construction of 26,000 
lineal feet of pile dike to protect the channel in 
upper Galveston Bay (which is inactive), for 
construction of such off-channel silting basins as 
deemed necessary by the Chief of Engineers, and 
for dimensions in various channels and basins of 
the Waterways. (See Table 15-F on channel 
dimensions.) (Also see Table 15-B for authorizing 
legislation.) Mean tidal range under ordinary 
conditions is 0.6 foot to 1.3 feet in lower part of 
Galveston Bay; 0.6 foot to 1.3 feet in upper bay; 
and 0.5 to 1 foot in San Jacinto River and Buffalo 
Bayou. Extreme ranges under ordinary conditions 
are about 2 feet, 1.2 feet, and 1 foot respectively. 
Freshets caused rises of over 12 feet in Buffalo 
Bayou; however, this condition has not occurred 
since completion of Addicks and Barker Dams for 
Flood control on upper watershed of Buffalo 
Bayou. Height of tides is dependent largely on the 
wind, and during strong "northers" in winter 
sason the water surface may be depressed 2 feet 
below mean low tide. 
Local cooperation. Complied with except for 
inactive portions. 
Terminal facilities. City of Houston and Port of 
Houston Authority operate modern terminals 
which supplement privately owned wharves, 
piers, and docks, as described in Port Series No. 
24 (dated 1959) Corps of Engineers. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design (including model 
studies) and supervision and administration cost 
$236,414 and $87,171. Condition and operation 
studies, inspections and reports, and project 
condition surveys including real estate activities, 
15-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
cost $68,990. Adjustment of cost for miscellaneous 
maintenance by hired labor was -$442. 
Adjustment of cost for tide gages was -$1,450. 
Cost for a dredging contract completed in FY 1974 
was $41,705. Mobilization cost on a dredging 
contract awarded in late June 1975 was $5,000. 
(See Table 15-H for dredging operations.) 
Condition at end of fiscal year. Existing project 
is 100 percent complete, exclusive of inactive 
portions. The 40-foot project was completed in 
March 1966. Dredging a channel in Greens Bayou 
was completed October 5, 1970. (See Table 15-E 
for total cost of existing project to June 30, 1975.) 
9. MATAGORDA SHIP CHANNEL, TEX. 
Location. This is a consolidation of shallow 
draft channel improvements of "Channel from 
Pass Cavallo to Port Lavaca, Tex.," and deep 
draft channel improvements authorized under 
"Matagorda Ship Channel, Tex." Bar at Pass 
Cavallo is 125 miles southwest of Galveston 
entrance and 54 miles north of Aransas Pass. It 
connects Matagorda Bay with the gulf. Project 
extends across Matagorda Bay and Lavaca Bay to 
towns of Port Lavaca and Point Comfort. These 
two towns are on opposite sides of Lavaca Bay 
and both are about 26 miles northwest from Pass 
Cavallo. (See National Ocean Survey Chart 
11316.) 
Existing project. Existing project dimensions 
provided for in various channels and basins are 
listed in Table 15-F on channel dimensions. (Also 
see Table 15-B for authorizing legislation.) 
Project also provides for dual jetties at 
entrance, south jetty extending 6,000 feet to 
24-foot depth in the gulf and north jetty extending 
5,900 feet to 24-foot depth. Under ordinary 
conditions mean tidal range is about 1 foot and 
extreme range about 2 feet. Height of tide is 
dependent largely on the wind, and during strong 
"northers" in winter season the water surface may 
be depressed 2 feet below mean low tide. 
Estimated cost for new work is: $18,058,777 
Federal (Corps), and $12,859,000 non-Federal, 
including $12,259,619 contributed funds, $182,800 
for lands, $220,000 for relocations, and $196,581 
other costs. 
Local cooperation. Fully complied with. Local 
interests have contributed $12,259,619. 
Terminal facilities. Privately owned facilities at 
Port Lavaca, municipal owned facilities at mouth 
of Lynn Bayou, privately owned and publicly 
owned facilities at Point Comfort, Tex. These 
facilities are considered adequate for present 
commerce. Facilities at Point Comfort consist of a 
channel, turning basin with wharfs, oil dock and 
loading equipment, all owned by Aluminum Co. of 
American; and a wharf built by local interest at 
Point Comfort turning basin. 
Operation and results during fiscal year. Maintenance: 
Engineering and design and supervision 
and administration cost $7,159 and $207,990. 
Condition and operation studies, and inspections 
and reports, cost $72,093. Replacement cost for 
temporary hopper dredge range tower totaled 
$3,675, a test disposal area for pipeline dredging 
entrance channels cost $23,943. Hired labor in 
connection with channels was $7,554. (See Table 
15-H for dredging operations.) 
Condition at end of fiscal year. The project is 
100 percent complete. The 36-foot project was 
initiated in 1962 and completed in March 1967. 
10. SABINE-NECHES WATERWAY, TEX. 
Location. This is a consolidation of old 
improvements of "Harbor at Sabine Pass and 
Port Arthur Canal" and "Sabine-Neches Canal, 
including Sabine River to Orange and Neches 
River to Beaumont, Tex." Sabine Pass is on Gulf 
of Mexico about 58 miles east of Galveston and 
280 miles west of Southwest Pass, Mississippi 
River. It connects Sabine Lake with gulf. Port 
Arthur canal extends 7 miles from near upper end 
of Sabine Pass to Port Arthur docks at mouth of 
Taylors Bayou. Near its upper end, SabineNeches 
canal joins and extends to mouths of Neches and 
Sabine Rivers. Waterway next extends up Neches 
River to Beaumont and up Sabine River to 
Orange. (See National Ocean Survey Charts 
11341, 11342, and 11343.) 
Previous projects. For details see page 1863 of 
Annual Report for 1915, page 985 of Annual 
Report for 1916, and page 873 of Annual Report 
for 1926. 
Existing project. Existing project dimensions 
provided for in various channels and basins are set 
forth in Table 15-F on channel dimensions. (Also 
see Table 15-B authorizing legislation.) Project 
also provides for two stone jetties at Sabine Pass 
entrance from the gulf, western jetty to be 21,905 
feet long and eastern jetty 25,310 feet long. 
Project further provides for removal of guard lock 
in Sabine-Neches Canal, construction of suitable 
permanent protective works along Sabine Lake 
frontage owned by city of Port Arthur to prevent 
dredged material from entering Sabine Lake and 
to prevent erosion of material deposited, reconstruction 
of Port Arthur Bridge, and relocation 
of Port Arthur field office. Mean tidal 
variation at entrance is about 1.5 feet, at Port 
Arthur about 1 foot, and at Orange and Beaumont 
about five-tenths foot. Prolonged north winds 
during winter season have depressed water 
surface as much as 3.4 feet below mean low tide 
while tropical disturbances have caused heights as 
much as 8 feet above mean low tide. 
Local cooperation. Complied with except for 
15-8

GALVESTON, TEX., DIST. 
inactive portions. 
Terminal facilities. See volume 2, Port Series 
No. 22 (revised 1969), Corps of Engineers. There 
are 3 wharves and piers in addition to the facilities 
included in the referenced Port Series. Facilities 
are considered adequate for present commerce. 
Operation and results during fiscal year. Maintenance: 
Engineering and design and supervision 
and administration cost $22,792 and $322,384. 
Condition and operation studies, inspections and 
reports, project condition surveys, and real estate 
activities cost $186,480. Miscellaneous maintenance 
totaled $4,779. Dredge Disposal Areas 
located adjacent to populated areas along the 
Neches River were sprayed for mosquito control at 
a cost of $14,109. Cost for retaining levee 
roadways, North and South Disposal areas 
totaled $208,104. A test disposal area for pipeline 
dredging entrance channels cost $27,218. Adjustments 
of cost were made on dredging contracts 
completed in FY 74 for -$21,594. (See Table 15-H 
for maintenance dredging operations.) 
Condition at end of fiscal year. Existing project 
is complete except for inactive portions. Removal 
of obstructive bridge at Port Arthur was 
completed May 28, 1969. The high-level fixed 
bridge across Sabine-Neches Canal was completed 
October 9, 1970. Deepening Project to 40 feet was 
completed on April 10, 1972. (See Table 15-E for 
total cost of existing project to June 30, 1975.) 
11. TEXAS CITY CHANNEL, TEX. 
Location. Texas City is on mainland of Texas 
on west side of Galveston Bay, about 10 miles 
northwest of city of Galveston. (See National 
Ocean Survey Charts 11324/5.) 
Previous projects. For details see page 1856 of 
Annual Report for 1915. 
Existing project. Existing project dimensions 
provided for in various channels and basins are set 
forth in Table 15-F on channel dimensions. (Also 
see Table 15-B authorizing legislation.) 
Project also provides for easing the approach to 
the turning basin; a pile dike 28,200 feet long, 
parallel to and north of the channel; and a rubblemound 
dike, 27,600 feet long, along the southerly 
side of the pile dike. Under ordinary conditions 
mean tidal range is about 1.3 feet and extreme 
range is about 2 feet. Height of tide is dependent 
largely on the wind and during strong "northers" 
water surface may be depressed 2 feet below mean 
low tide. Estimated cost for new work is Federal 
(Corps) $8,671,000, excluding expenditures on 
previous projects, and non-Federal $552,700, 
including $28,741 contributed funds, $248,000 
work contribution, $177,959 lands, and $98,000 
levees and spillways. 
Local cooperation. Fully complied with, except 
for Section 201 of Flood Control Act of 1965 and 
H.D. 92-199. Non-Federal contributions $276,741. 
Terminal facilities. Privately owned terminal 
facilities are on the mainland at inner end of this 
channel and are considered adequate for existing 
commerce. A deep-draft canal and turning basin 
extending about 1.9 miles southwestward from 
south end of Texas City Turning Basin have been 
constructed by local interests. See Port Series No. 
23 (revised 1969), Corps of Engineers. 
Operations and results during fiscal year. New 
Work: Preconstruction planning was continued on 
the Texas City Industrial Canal at a cost of 
$83,306. 
Maintenance: Engineering and design and 
supervision and administration cost $15,804 and 
$24,980. Condition and operation studies, inspections 
and reports, and project condition 
surveys cost $33,320. (See Table 15-H for 
dredging operations.) 
Condition at end of fiscal year. Project is 
complete except for widening a portion of the 
Texas City Turning Basin from 1,000 feet to 1,200 
feet; for realigning the Texas City turning basin 
to a location 85 feet easterly from its present 
position; and for enlargement through widening 
and deepening to 40 feet of the Industrial Canal 
and basins. Preconstruction planning is in 
progress on this work. The 40-foot channel was 
completed in June 1967. (See Table 15-E for total 
cost of existing project to June 30, 1975.) 
12. TRINITY RIVER AND TRIBUTARIES, 
TEX. 
Location. The main stem of the Trinity River is 
formed at Dallas by the confluence of the West 
Fork and the Elm Fork at river mile 505.5. The 
mouth of the Trinity is about one-half mile west of 
Anahuac, Texas. (See Geological Survey base 
map, Texas, scale 1:500,000.) 
Previous project. For details of abandoned 
locks and dam construction see page 986 of 
Annual Report for 1932. 
Existing project. See individual detailed reports 
on Anahuac Channel, Channel to Liberty and 
Wallisville Lake. Project includes the existing 
Federal project designated as "Mouth of Trinity 
River, Texas," which was completed in 1907 at a 
cost of $80,000 (no cost to local interest). Project 
is not being maintained. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. See individual detailed 
reports on Channel to Liberty and Wallisville 
Lake. There is no local cooperation required for 
Anahuac Channel. 
Terminal facilities. Privately owned wharves 
and piers at Anahuac, Moss Bluff, Wallisville, 
and Liberty, Texas, are adequate for existing 
15-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
commerce. 
Operations and results during fiscal year. New 
Work: Not applicable. 
Condition at end of fiscal year. The restudy of 
the navigation benefits is complete. (See Table 
15-E for total cost of existing project to 30 June 
1975.) 
12A. ANAHUAC CHANNEL, TEX. 
Location. Extends from 6-foot depth in 
Galveston Bay to Anahuac, Tex., opposite mouth 
of Trinity River, 38 miles north of Galveston, Tex. 
(See National Ocean Survey Chart 11323.) 
Existing project. No project dimensions 
authorized by 1905 River and Harbor Act. A 6- by 
80-foot channel, 16,000 feet long was dredged in 
1905. At present a 6- by 100-foot channel is 
maintained. Under ordinary conditions tidal range 
is 0.6 to 1.2 feet. Height of tide is dependent 
largely on wind. Strong north winds depress water 
surface 1.5 feet below mean sea level. Latest 
published map is in House Document 440, 56th 
Congress, 1st session. 
Local cooperation. None required. 
Terminal facilities. Privately owned wharves 
and piers are the only terminal facilities at 
Anahuac. 
Operations and results during fiscal year. Maintenance: 
Engineering and design and supervision 
and administration cost $5,009 and $9,078. 
Condition and operation studies, inspections and 
reports, and project condition surveys cost 
$12,372. (See Table 15-H for dredging operations.) 
Condition at end of fiscal year. Project was 
completed in 1911. 
12B. CHANNEL TO LIBERTY, TEX. 
Location. Improvement is located in Galveston 
Bay and tidal reach of lower Trinity River. (See 
Geological Survey Maps for Anahuac, Cove, Moss 
Bluff, and Liberty, Texas.) 
Previous projects. For details see page 986 of 
Annual Report for 1932. 
Existing project. Provides for a 6-foot channel 
from Anahuac to Liberty which was completed in 
1925. A navigable channel from the Houston Ship 
Channel near Red Fish Bar in Galveston Bay to 
Liberty, Texas, with depth of 9 feet and width of 
150 feet, extending along the east shore of Trinity 
Bay to the mouth of the Trinity River at Anahuac, 
thence in the river channel to a turning basin at 
Liberty, Texas, and a protective embankment 
along the west side of the channel in Trinity Bay. 
(See Table 15-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
portion of "Channel to Liberty" between Houston 
Ship Channel and 1 mile below Anahuac, Tex., as 
required by 1946 River and Harbor Act (H. Doc. 
634, 79th Cong., 2nd sess.), but not complied with 
for remaining portion of "Channel to Liberty" as 
required by River and Harbor Act of 1945 (H. 
Doc. 403, 77th Cong., 1st sess.), at an estimated 
total cost of $550,000, of which $460,000 is for 
lands and rights-of-way and $90,000 for pipeline 
relocations for 9- by 150-foot channel. 
Terminal facilities. Privately owned wharves 
and docks at Anahuac, Wallisville, Texas Gulf 
Sulphur Co.'s slip, Moss Bluff and Liberty, Tex., 
are adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Supervision and administration cost 
$2,270. Condition and operation studies, inspections 
and reports, cost $25,669. 
Condition at end of fiscal year. The 6-foot 
Channel to Liberty was completed in 1925. The 
9-foot Channel to Liberty has been dredged from 
junction with Houston Ship Channel to a point 
one mile below Anahuac, Texas. Work remaining 
consists of dredging a 9- by 150-foot channel from 
one mile below Anahuac, Texas to Liberty, Texas. 
12C. WALLISVILLE LAKE, TEX. 
Location. Dam is at river mile 3.9, about 4 miles 
northwest of Anahuac, Tex. (See National Ocean 
Survey Chart 11323.) 
Existing project. Provides for construction of a 
39,220-foot dam to store water to elevation 4 feet 
above mean sea level, with an 84- by 600-foot 
navigation lock in a cutoff channel; and extension 
of authorized channel to Liberty from its present 
terminus at channel mile 23.2 to Texas Gulf 
Sulphur channel at channel mile 33.6. Dam is 
composed of a nonoverflow section 16,820 feet 
long with a crest elevation varying from 13.0 to 
10.0 feet above mean sea level, and an overflow 
section 22,400 feet long. All but 1,500 feet of 
overflow section has a crest elevation of 5.5 feet 
above mean sea level. The two remaining portions 
of overflow section have crest elevations of 4.0 feet 
above mean sea level. Both the overflow and 
nonoverflow sections basically are earthern levees 
with full or partially riprapped side slopes and 
paved roadways on their crest. Lock is at channel 
mile 28.3, has a sill depth of minus 16.17 feet 
below mean sea level, a normal lift of 4 feet and is 
founded in piles of clay. Dam controls a drainage 
area of 1,262 square miles below Livingston Dam 
(non-Federal project at channel mile 99.2) and has 
a storage capacity of 58,000 acre-feet. Under 
ordinary conditions mean tidal range in bay is 
from 0.6 foot to 1.2 feet. Height of tide is 
dependent largely on wind. Strong northerly 
winds depress water surface 1.5 feet below mean 
sea level. Total estimated cost of project is 
$28,800,000 Federal (Corps) and $18,000 non- 
15-10

GALVESTON, TEX., DIST. 
Federal for lands for construction of portion of 
channel to Liberty. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. Local interests must contribute 
an amount equal to cost allocated to water 
supply, one-half of cost allocated to salinity 
control and cost allocated to recreation less cost of 
basis facilities and less 15 percent of total project 
cost. Local interest contribution is estimated at 
$4,956,000. For improvement of the navigation 
channel, exclusive of reservoir features, local 
interests must provide lands, disposal areas, and 
adequate terminal and transfer facilities, make 
necessary relocations of utilities crossing natural 
river channel and give assurances that they will 
hold and save the United States free from claims 
for damages, including but not limited to damages 
due to salt water intrusions, that may result from 
construction and operation of the navigation improvements. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision 
and administration cost $106,908 and $49,694. 
Land payments and administration cost for 
Federal purchase of land totaled $41,002. Cost for 
construction of dam and lock structure was 
$45,970. 
Condition at end of fiscal year. The project is 75 
percent complete. A contract for construction of 
access road, Big Hog intake structure, intake 
canal and access bridge was completed in October 
1968. Work started July 8, 1970 on construction 
of the lock and dam, roads, diversion channel, and 
navigation channel. Work on this contract was 
suspended on February 26, 1973 because of an 
injunction halting construction. Protective work 
on the lock and dam was permitted and was 
completed on April 15, 1973. An exception to the 
injunction was granted for plugging oil wells 
which was completed in August 1973. Notice of 
appeal to the Court of Appeals for the Fifth 
Circuit was filed on 26 April 1973. On 26 August 
1974, the Court of Appeals reversed the 
judgement and remanded the case with directions 
that a revised or supplemental statement be 
prepared and judged anew. When the supplement 
has been filed with CEQ, it will be submitted to 
the district court. 
13. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 15-C. 
14. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION. 
Navigation activities pursuant to section 107, 
Public Law 86-645 (preauthorization). Fiscal year 
costs for preauthorization studies were $21,362 for 
Gulf Intracoastal Waterway-Channel to Aransas 
Pass, Tex. 
15. CORPUS CHRISTI BEACH, TEX. (RESTORATION 
PROJECT) 
Location. Corpus Christi Beach, a shore area 
having a length of about 2 miles, is located on the 
west side of Corpus Christi Bay in Nueces County 
at Corpus Christi, Texas. (See National Ocean 
Survey Charts 11309 and 11311.) 
Existing project. The plan of improvement 
provided for initial restoration of eroded areas of 
Corpus Christi Beach, over a shore length of 1.4 
miles, located on the easterly side of Rincon 
Peninsula, with periodic nourishment as required. 
Estimated cost of new work is: Federal (Corps) 
$1,560,000 and non-Federal $1,610,000 ($1,560, 
000 contributed funds and $50,000 lands). (See 
Table 15-B for authorizing legislation.) 
Local cooperation. Local interests are required 
to agree to contribute in cash, prior to 
construction, the required percentage of the first 
cost (including the costs for construction, engineering 
and design, supervision and administration, 
and excluding the cost of lands, 
easements, rights-of-way, and relocations) of all 
items of work to be provided by the Corps of 
Engineers, presently estimated at 50 percent or 
$1,046,000, to be paid in a lump sum prior to start 
of construction or in installments prior to the start 
of pertinent work items in accordance with 
construction scheduled as required by the Chief of 
Engineers, the final apportionment of cost to be 
made after the actual costs have been determined; 
contribute in cash the required percentage of 
beach nourishment costs for the first 10 years of 
project life, now estimated at 50 percent of 
$102,800 annually, such nourishment costs for the 
first 5-year priod of the project, estimated at 
$514,000, to be provided for advance nourishment 
at the time of first construction, and following 
contributions to be made prior to each nourishment 
operation; provide without cost to the U.S. 
all lands, easements, rights-of-way, and relocations 
required for construction and subsequent 
nourishment of the project, now estimated 
at $50,000; provide after the first 10 years of 
project life periodic nourishment of the restored 
beach as may be required to serve the intended 
purpose during the life of the project; provide 
without cost to the U.S. access and facilities 
necessary for realization of the public benefits 
upon which Federal participation is based and 
maintain continued public ownership of the beach 
and administer it for public use during the life of 
the project; prohibit water pollution which would 
affect the health of bathers; and hold and save the 
U.S. free from claims for damages that may result 
from construction, maintenance, and nourishment 
15-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
of the project. 
Operations and results during fiscal year. Preconstruction 
planning was continued at a cost of 
$49,508. 
Condition at end of fiscal year. Preconstruction 
planning is in progress. Combined Phase I and II 
design memorandum was submitted in May 1975. 
Flood Control 
16. BUFFALO BAYOU AND TRIBUTARIES, 
TEX. 
Location. Improvements are on Buffalo Bayou 
watershed, a part of San Jacinto River watershed, 
in Harris County, west and northwest of city of 
Houston, Tex. (See Geological Survey quadrangle 
sheets for Harris County.) 
Existing project. Provides for improvement of 
Buffalo Bayou and its tributaries above turning 
basin (Houston) of Houston Ship Channel to 
control floods for protection of city of Houston, 
and prevent deposition of silt in turning basin of 
ship channel by construction of detention 
reservoirs, enlargement and rectification of 
channels and construction of control works. 
Estimated cost for new work is: Federal (Corps) 
$92,800,000 and non-Federal $59,078,000 for 
lands and relocations. (See Table 15-I on Buffalo 
Bayou and tributaries.) (Also Table 15-B for 
authorizing legislation.) 
Local cooperation. Section 203, 1954 Flood 
Control Act applies. Local interests have accomplished 
all required local cooperation on Brays 
Bayou and White Oak Bayou. On Buffalo Bayou, 
local interests purchased interests that the United 
States had in 7 miles of recified channel below 
Barker and Addicks Dams for $256,651. Of the 
remaining required rights-of-way on Buffalo 
Bayou, local interests have acquired about 40 
percent. About 53 percent of required bridge 
relocations and 3 percent of the required utility 
relocations have been accomplished. Advance of 
$4,400,000 by the Harris County Flood Control 
District was refunded in September 1956. Public 
Law 86-53 authorized reimbursement of $38,726 
to Galveston, Houston and Henderson Railroad 
Co. for bridge alterations at Brays Bayou. Non- 
Federal contributions totaled $63,661 for project 
betterments. 
Operations and results during fiscal year. New 
Work: White Oak Bayou: Engineering and 
design, including real estate, and supervision and 
administration cost $18,899 and $67,198. Channel 
rectification between Mile 0.0 to Mile 1.07 cost 
$2,380,000. Relocations of railroad bridges 
(MK&T-Mile 0.13 and Mile 0.3) cost $764. 
Buffalo Bayou: Supervision and Administration 
cost $478. 
Maintenance: Addicks Dam and Barker Dam 
were operated and maintained at a cost of 
$247,846 and $143,861. Miscellaneous repairs and 
work by hired labor totaled $2,743 for Addicks 
Dam and $3,460 for Barker Dam. Landscaping 
and project cleanup for Addicks Dam and Barker 
Dam totaled $20,000. Supervision and administration 
and real estate activity at Addicks Dam 
and Barker Dam totaled $2,956 and $1,127. 
Condition at end of fiscal year. Existing project 
is about 62 percent complete. Construction of 
Barker Dam was completed in February 1945. 
Construction of Addicks Dam and 7.4 miles of 
channel rectification downstream from Addicks 
and Barker Dams was completed in October 1948. 
Modification of Barker and Addicks Dams consisting 
of gating of two uncontrolled conduits in 
each dam, was completed in fiscal year 1963. 
Channel rectification on Brays Bayou was 
completed in FY 1969 except for minor clean-up 
between Southwest Freeway and Westheimer 
Road. Channel rectification of White Oak Bayou 
is about 91 percent complete. 
17. CLEAR CREEK, TEX. 
Location. Lies about midway between the two 
metropolitan centers of Houston on the north and 
Galveston-Texas City on the south. The stream 
forms the boundary between Harris and Brazoria 
Counties, and between Harris and Galveston 
Counties. It empties into Clear Lake and then 
flows into the west side of Galveston Bay. The 
watershed, with an area of about 250 square miles, 
is about 45 miles long and varies in width from 
about 2.0 miles at its upper end to a maximum of 
about 13.5 miles near its midpoint, and is located 
in Fort'Bend, Brazoria, Harris, and Galveston 
Counties. 
Existing project. Project provides for enlargement 
and rectification of the existing Clear Creek 
channel and from the upper end of Clear Lake at 
Mile 3.8 to improved channel Mile 34.8, a distance 
of 31 miles. A number of bridges, pipelines, and 
other structures which now obstruct flood flows 
will require relocation or alteration. Estimated 
cost of new work is: Federal (Corps) $27,900,000 
and non-Federal $14,070,000, consisting of 
$8,800,000 lands and $5,270,000 for relocations. 
(See Table 15-B for authorizing legislation.) 
Local cooperation. Section 201 of 1968 Flood 
Control Act applies. 
Operations and results during fiscal year. Preconstruction 
planning was continued at a cost of 
$161,772. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
15-12

GALVESTON, TEX., DIST. 
18. FREEPORT AND VICINITY, TEX. (HURRICANE-
FLOOD PROTECTION) 
Location. Freeport is in southern part of 
Brazoria County on Gulf of Mexico at mouth of 
Brazos River, about 43 miles southwest of 
Galveston, Tex. 
Existing project. Authorized plan provides for 
hurricane-flood protection for a highly industrialized 
area and community of about 39,000 
persons. Major features of project consist of improvements 
to 42.8 miles of existing levees, two 
interior drainage pumping plants and 2.1 miles of 
new levee. Estimated cost for new work is: 
$25,600,000 Federal (Corps) and non-Federal 
$10,972,000 consisting of $7,314,t00 cash, 
$1,260,000 lands, and $2,398,000 relocations. (See 
Table 15-B for authorizing legislation.) 
Local cooperation. Sec. 203, 1962 Flood Control 
Act applies. Bond issues have been passed to 
finance local interests share of the project. Local 
interests have acquired about 65 percent of lands 
needed and are proceeding with acquisition of 
lands. Non-Federal contribution estimated 
$10,972,000 is required. 
Operations and results during fiscal year. Engineering 
and design and supervision and administration 
costs totaled $308,774 and $209,488. 
Construction continued on Old River & Freeport 
Harbor Levee (Sta 132 +00 to 139 +00) South, Sta 
126 +00 to 137 +00 North, and Tidal gate at a 
cost of $2,781,627. Construction continued on Old 
River and Freeport Harbor North Levee (Sta 
137+00 to 299+41) at a cost of $1,189,670. 
Erosion control on the East Bank of the Brazos 
River Levee was performed at a cost of $300,020. 
Cost for the Oyster Creek Levee was $7,000. 
Contract cost for East Bank Brazos River Levee 
(Sta 128 +00 to 381 + 21) and South Storm Levee 
(Sta 0+00 to 46 +00) was decreased $3,510. Cost 
on a contract for Old River and Freeport Harbor 
South Levee (Sta 139+00 to 278+54) was 
$279,044. Velasco Pumping Plant was financially 
completed at a cost of $727. Supply contract for 
pumps for the Velasco Pumping Plant was 
completed at a cost of $3,326. Hired labor work 
and miscellaneous purchase orders totaled 
$1,377. 
Condition at end of fiscal year. Project is about 
56 percent complete. 
19. GUADALUPE RIVER (REMOVE LOG 
JAMS), TEX. 
Location. The portion of the Guadalupe River 
under consideration is located in Victoria, 
Calhoun and Refugio Counties, Texas, and 
extends from the Missouri Pacific Railroad bridge 
at about river mile 22 to its mouth at Guadalupe 
Bay. 
Existing project. The project provides for the 
removal of log jams and snags in numerous 
locations along the river that restrict the flow and 
cause flooding on lands adjacent to the stream. 
Estimated cost for work is: Federal (Corps) 
$410,000. (See Table 15-B for authorizing 
legislation.) 
Local cooperation. Section 212, 1970 Flood 
Control Act applies. 
Operations and results during fiscal year. Engineering 
and design and supervision and administration 
cost $17,250 and $47,304. Removal 
of the log jams was completed at a cost of 
$254,370. 
Conditions at end of fiscal year. Removal of the 
log jams was completed in June 1975. Work 
remaining is the burning of the logs after a 
reasonable drying time. 
20. HIGHLAND BAYOU, TEX. 
Location. Rises near Arcadia, in Galveston 
County, Tex., and flows into Jones Bay, an arm of 
West Bay. The watershed, with an area of about 
38 square miles lies entirely within Galveston 
County and is about 14 miles long and varies in 
width from about 0.3 miles at its lower end to a 
maximum of about 5 miles near its midpoint. 
Existing project. Plan of improvement provides 
for enlargement and rectification of Highland 
Bayou Channel and construction of a diversion 
dam in Highland Bayou, with a diversion channel 
extending southerly from the diversion dam and 
emptying into Jones Bay, which lies on the north 
side of West Bay. Estimated cost of new work is: 
Federal (Corps) $12,100,000 and non-Federal 
$3,210,000 consisting of $1,735,000 lands and 
$1,475,000 for relocations. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. Section 204, 1965 Flood 
Control Act applies. 
Operations and results during fiscal year. New 
work: Engineering and design and supervision 
and administration cost $151,970 and $69,766. 
Dredging of the diversion channel from Mile 0.0 to 
5.9 cost $2,074,780. 
Condition at end of fiscal year. Initial construction 
contract was awarded in June 1974, project is 
25 percent complete. 
21. LOWER RIO GRANDE BASIN, TEX. 
Location. The project is located in Lower Rio 
Grande Basin of Texas in Willacy, Hidalgo, and 
Cameron Counties. 
Existing project. Proposed improvement 
(Phase I of a 3-phase comprehensive plan for flood 
control, drainage, and land treatment prepared by 
the United States Department of Agriculture) 
15-13

REPORT OF THE CHIEF OF ENdINEERS, U.S. ARMY 1975 
provides for 164 miles of floodwater channels 
designated as the Willacy-Hidalgo Floodwater 
Bypass, the Laguna Madre Floodwater Channel, 
and the North Floodway Channel. Phase II (1,394 
miles of lateral channels) and III (land treatment 
programs) of the comprehensive plan would not be 
addressed by the Corps of Engineers. Estimated 
cost of new work is: Federal (Corps) $80,600,000 
and non-Federal $13,000,000, consisting of 
$5,000,000 lands, and $8,000,000 relocations. The 
authorizing legislation authorizes the Corps of 
Engineers to undertake Phase I design memorandum 
stage of advanced engineering and design 
only. (See Table 15-B for authorizing legislation.) 
Local cooperation. Section 68, 1974 Water 
Resources Development Act applies. Additionally, 
local interests will be required to contribute a 
portion of the cost allocated to major drainage. 
Operations and results during fiscal year. New 
work: Preconstruction planning was initiated at a 
cost of $104,847. 
Condition at end of fiscal year. Preconstruction 
planning on Phase I design memorandum is in 
progress. 
22. PEYTON CREEK, TEX. 
Location. The entire Peyton Creek watershed of 
about 104 miles lies within Matagorda County, 
Texas. Cottonwood Creek, one of the headwater 
tributaries, rises about 4 miles north of Bay City, 
flows south and southeast for a distance of about 
15 miles to its junction with another headwater 
tributary, Bucks Bayou, to form Peyton Creek. 
Peyton Creek continues southeasterly for about 16 
miles to Lake Austin, which in turn, empties into 
Matagorda Bay via Live Oak Slough. Live Oak 
Slough and Dry Creek are tributaries to 
Cottonwood Creek. The total watershed is about 
25 miles long and varies in width, from about .25 
mile at its upper end to about 8 miles at its 
midpoint and lower end. 
Existing project. Project provides for enlargement 
and rectification of 13.40 miles of Peyton 
Creek, 9.13 miles of Bucks Bayou, 7.73 miles of 
Cottonwood Creek, 7.75 miles of Live Oak Slough, 
and 2 miles of Dry Creek; for the construction of a 
plug in Cottonwood Creek above Bay City; and for 
construction of a diversion dam 2.10 miles long 
from Cottonwood Creek to Bucks Bayou. Also 
provided is construction of salt water barrier in 
lower reaches of Peyton Creek and major drainage 
outlets to serve agricultural lands in Peyton Creek 
Watershed. Estimated cost for new work is 
Federal (Corps) $10,200,000 and $2,459,000 non- 
Federal, consisting of $29,000 cash contribution, 
$1,194,000 for lands, $1,132,000 for relocations 
and $104,000 other. 
Local cooperation. Section 201 of 1965 Flood 
Control Act and HD 92-341 applies. 
Operations and results during fiscal year. Preconstruction 
planning was continued at a cost of 
$47,840. 
Condition at end of fiscal year. By resolution 
adopted December 9, 1974, Commissioners Court 
of Matagorda County, local sponsor, requested 
that the project be deferred as an overall lack of 
interest in the project would make it impossible 
for them to provide the necessary local 
cooperation. It was recommended that the project 
be placed in the "inactive" category in February 
1975. 
23. PORT ARTHUR AND VICINITY, TEX. 
(HURRICANE-FLOOD PROTECTION) 
Location. Port Arthur is on west shore of 
Sabine Lake in extreme southeast part of Texas, 
about 14 miles from the gulf. Area under 
consideration is comprised of about 38,500 acres, 
and includes cities of Port Arthur and Groves, 
towns of Griffing Park, Pear Ridge, and 
Lakeview, and adjacent industrial areas. 
Existing project. Authorized plan provides for: 
Raising and reconstructing 6.3 miles of existing 
concrete and steel sheet-pile seawall; constructing 
0.3 mile of new concrete and sheet-pile seawall; 
raising and improving 7.5 miles of existing earth 
levees; constructing 20.3 miles of new earth levees 
and constructing five interior drainage pumping 
plants. Estimated cost for new work is: Federal 
(Corps) $65,300,000 and non-Federal $27,986,000 
consisting of $18,245,000 cash contribution, 
$4,571,000 for lands and $5,170,000 for relocations. 
Additional non-Federal cost for pumping 
station betterments and levee realignment 
betterments is $638,000. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. Section 203, 1962 Flood 
Control Act applies. Non-Federal contributions 
estimated at $27,986,000 are required. An 
additional $638,000 will be contributed for project 
betterments requested by local interests. 
Operation and results during fiscal year. New 
work: Engineering and design and supervision 
and administration cost $539,017 and $437,571. 
Procurement of pumps and equipment for 
Alligator Bayou Pumping Plant cost $8,247. 
Storage of pumps cost $9,416. Construction was 
continued on Alligator Bayou Pumping Plant at a 
cost of $3,222,669. Construction of levee (Sta 
1541+20 to 1609+00) was completed at a fiscal 
year cost of $22,659. Construction of levee, 2nd 
stage (Sta 1448+00 to 1465 +00) was completed 
at a fiscal year cost of $39,173. Construction of 
levee, Sabine Tank Farm and Taylors Bayou 
Area, 2nd stage (Sta 859+00 to 1211+30) 
continued at a cost of $2,009,953. Construction of 
Sabine-Neches Floodwall (Sta 583+75 to 
621+97) continued at a cost of $277,946. 
15-14

GALVESTON, TEX., DIST. 
Construction of levee, Atlantic Refinery Area, 2nd 
stage, (Sta 110 +00 to 202 +20) was initiated at a 
cost of $573,786. Supply contract for trash rake 
units for Alligator Bayou Gravity Structure cost 
$99,991. Supply contract for gates and miscellaneous 
equipment for Alligator Bayou Gravity 
Structure cost $351,116. Miscellaneous purchase 
orders and hired labor work cost $1,395. Resettlement 
expense for land acquisition (PL 
91-646) cost $300. In addition, local interests 
performed $408,332 of relocation work. 
Condition at end of fiscal year. Construction on 
the project was initiated in March 1966. The 
project is approximately 54 percent complete. 
24. TAYLORS BAYOU, TEX. 
Location. Watershed of Taylors Bayou is in 
extreme southeast corner of Texas adjoining 
basins of Neches River and Sabine Lake on the 
east. City of Port Arthur is about 8 miles from the 
main stream of Taylors Bayou. 
Existing project. Improvement of Taylors 
Bayou by enlarging and rectifying approximately 
53 miles of natural and artificial channels on 
Taylors Bayou and tributary water courses; the 
construction of a diversion channel, 2.9 miles 
long, from Mile 2.1 on Taylors Bayou to Taylors 
Bayou Outfall Canal at Mile 0.9; a salt water gate 
across the diversion channel to prevent the 
intrusion of salt water into Taylors Bayou; and 
enlargement of the Gulf Intracoastal Waterway 
from the Outfall Canal to Port Arthur Canal, a 
distance of approximately 1.3 miles. Estimated 
cost for new work is: Federal (Corps) $20,600,000 
and non-Federal $11,135,000, including $7,014, 
000 cash contribution, $2,453,000 lands, and 
$1,668,000 for relocations. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. Section 204, 1965 Flood 
Control Act, applies. Non-Federal contributions 
estimated at $7,014,000 are required. 
Operation and results during fiscal year. New 
work: Preconstruction planning continued at a 
cost of $91,563. 
Condition at end of fiscal year. The General 
Design Memorandum, which included the reevaluation 
of benefits, was approved October 31, 
1969. Preconstruction planning is in progress. 
25. TEXAS CITY AND VICINITY, TEX. 
(HURRICANE-FLOOD PROTECTION) 
Location. On the west and southwest shore of 
Galveston Bay, about 9 miles northwest of 
Galveston, Texas. Project fronts on the west side 
on Galveston Bay and protects a land area of 
about 36 square miles. 
Existing project. Plan provides for construction 
of improvements at Texas City and Vicinity, 
Texas, for control of storm tides. Improvements 
consist of 15.9 miles of new levees, 1.3 miles 
concrete floodwall, related drainage and stoplog 
structures, one tide control structure, and two 
pumping plants. Estimated cost for new work is: 
Federal (Corps) $29,100,000 and non-Federal 
$12,472,000 for seawall with closure structures, 
including $10,987,000 cash contribution, $27,000 
work contribution, and $1,458,000 for lands. 
Additional non-Federal cost for ramps in lieu of 
closure structures is $142,000. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. Requirements are in Sec. 
203, 1958 Flood Control Act. Based on 1974 
estimates, local interests must contribute 
$12,472,000 toward the project, and, at their 
option, an additional $142,000 for ramps in lieu of 
closure structures. Local interests have acquired 
95 percent of all lands required. 
Operation and results during fiscal year. Engineering 
and design including real estate costs, 
and supervision and administration costs were 
$199,078 and $69,971. Construction of Floodwall 
(Sta 504+98 to 537+50) performed at a cost of 
$2,051,120. Repairs to the road on the levee cost 
$8,091. Alteration of Monsanto's facilities were 
performed at a cost of $14,446. Relocation 
contracts cost $40,237. Miscellaneous purchase 
orders and hired labor work totaled $2,334. In 
addition, contributed lands in the amount of 
$72,250 were received. 
Condition at end of fiscal year. The project is 
about 78 percent complete. 
26. VINCE AND LITTLE VINCE BAYOUS, 
TEX. 
Location. Watershed of Vince Bayou and tributary, 
Little Vince Bayou, has an area of about 17 
square miles and lies entirely within Harris 
County. Vince Bayou is a minor tributary of 
Buffalo Bayou in San Jacinto River Basin on 
upper gulf coast of Texas. 
Existing project. Provides for enlarging and 
rectifying channel of Vince Bayou from mouth to a 
point about 7.3 miles upstream and Little Vince 
Bayou from mouth to a point about 4.2 miles 
upstream, a total distance in both streams of 
about 11.5 miles. Estimated cost for new work is: 
Federal (Corps) $9,500,000 and non-Federal 
$4,865,000, consisting of $2,905,000 for lands and 
$1,960,000 for relocations. (See Table 15-B for 
authorizing legislation.) 
Local cooperation. Sec. 203, 1962 Flood Control 
Act, applies. Local interests have acquired all real 
estate for Vince Bayou channel rectification and 
about 95 percent of all required relocations. On 
Little Vince Bayou, local interests have acquired 
80 lercent of the real estate and accomplished 3 
15-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
percent of the required relocations. 
Operations and results during fiscal year. Engineering 
and design, including real estate cost, 
and supervision and administration cost $14,614 
and $4,219. Turfing on Vince Bayou, Mouth to 
Mile 1.9, was fiscally completed at a cost of $70. 
Condition at end of fiscal year. Two railroad 
bridges on Vince Bayou have been relocated and 
work on channel rectification on Vince Bayou 
between Mile 1.9 and 3.8 was completed Oct. 70. 
The project is about 37 percent complete. 
27. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections of completed flood control protection 
projects operated and maintained by local 
interests were made on Tranquitas Creek, Kingsville, 
Texas, (December 1974 and June 1975); 
Colorado River, Matagorda, Texas (November 
1974 and May 1975); Hurricane-Flood Protection 
at Freeport and Vicinity, Texas (November 1974 
and May 1975); Lavaca-Navidad Rivers, Hallettsville, 
Texas (December 1974 and June 1975); 
Little Cypress Bayou, Orange, Texas (September 
1974 and April 1975); San Diego Creek at Alice, 
Texas (December 1974 and June 1975); Galveston 
Seawall at Galveston, Texas (October 1974 and 
May 1975); Buffalo Bayou and Tributaries, 
Buffalo Bayou Rectified Channel and Brays 
Bayou Channel at Houston, Texas (November 
1974 and May 1975); Guadalupe River Levee at 
Victoria, Texas (December 1974 and June 1975); 
Channel to Victoria, Gulf Intracoastal Waterway, 
Access Road and Missouri Pacific railroad bridge 
(December 1974 and June 1975); Hurricane-Flood 
Protection at Port Arthur and Vicinity, Texas 
(September 1974 and April 1975); Big Hog Intake 
Bayou at Wallisville, Texas (September 1974 and 
April 1975); and Hurricane-Flood Protection at 
Texas City and Vicinity, Texas (October 1974 and 
May 1975) at a cost of $13,000. 
28. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
See Table 15-D. 
29. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Congress and antecedent legislation) 
Fiscal year Federal costs were $9,786 for advance 
preparation, and $1,489,300 for restoration 
of flood control works and government cost 
resulting from flood damages. Location and cost 
for the restoration work were as follows: Harris 
County, Texas $1,235,732 and Liberty County, 
Texas $253,569. 
General Investigations 
30. SURVEYS 
Cost of surveys during fiscal year: navigation, 
$314,753; flood control, $308,160; hurricane, 
$563,252; deauthorization review program, 
$18,000; and coordination with other agencies- 
Soil Conservation Service, $2,200 and Bureau of 
Reclamation, $2,659. 
31. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain management and technical services 
were performed at a cost of $78,446 and $45,075, 
respectively. Work was initiated on Bens Branch, 
Montgomery County, Texas, at a cost of $24,940; 
on Brazos River, Fort Bend County, Texas, at a 
cost of $35,890; on Colorado River, La Grange, 
Texas, at a cost of $9,391; on Willow Fork, Fort 
Bend and Harris Counties, Texas, at a cost of 
$17,824; on Sam Bell Gully, Montgomery 
County, Texas, at a cost of $18,641, and 
on White Oak Creek, Montgomery County, 
Texas, at a cost of $27,230. Work was 
completed on Caney Creek, Montgomery County, 
Texas, at a cost of $16,541; and on Bear Branch, 
Montgomery County, Texas, at a cost of $6,031. 
Work continued on West Fork, San Jacinto River, 
Montgomery County, Texas, at a cost of $6,368. 
(See Table 15-K for Completed Flood Plain 
Information Reports.) 
Fiscal year cost was $19,306 for hydrologic 
studies. Three water level recorders were 
purchased for monitoring hurricane tides. 
15-16

GALVESTON, TEX., DISTRICT 
TABLE 15-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Aquatic Plant 
Control (Southwestern 
Division) 
1965 Act 
2. Brazos Island 
Harbor, Texas 
3. Cedar Bayou, 
Texas 
4. Corpus Christi 
Ship Channel, 
Texas (Regular 
Funds) 
(Contributed 
Funds) 
5. Freeport Harbor, 
Texas 
6. Galveston Harbor 
and Channel, 
Texas 
7. Gulf Intracoastal 
Waterway Between 
Apalachee Bay' 
Fla., and the 
Mexican Border 
(Galv. Dist.) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
25,600 
47,667 
-112 
526,460 
682,718 
494,809 
471,199 
62,992 
111,700 
13,735 
797,482 
329,690 
864,649 
1,229,308 
52,000 
54,517 
482,197 
523,902 
-63,746 
195,215 
15,284 
-4,600 
89,860 
4,850,000 
4,649,942 
1,598,299 
1,886,016 
200,000 46,000 
- 185,759 
401,000 
667,033 
1,222,762 
1,457,677 
-112,926 
698,169 
126,402 
3,886,236 
3,903,054 
390,036 
390,225 
70,000 
2,428 
680,793 
657,848 
65,005 
167,988 
5,406,285 
4,096,097 
42,000 
70,286 
517,210 
194,741 
191,177 
23,372 
3,123 
660 
3,484,883 
3,823,196 
1,516,089 
1,607,080 
-14,241 
32,385 
98,000 
69,515 
835,466 
835,816 
570,000 
58,360 
1,758,944 
1,789,668 
-124,700 
455,660 
5,149,431 
6,537,830 
52.000 408,6001 
74,364 368,6381 
- 10,471,5292 
- 10,471,5292 
700,376 13,620,2653 
1,016,625 13,613,6953 
- 2,170,080 
- 2,170,080 
-50,000 681,2634 
510,728 681,263 4, 6 
613 952,7455 
7,753 952,745 
3.856,000 33,650,8687 
3,536,328 32,652,115 7 8 
669,132 31,129,407 9 
678,226 31,127,928 
- 3,576,684 
- 3,576,684 
-13,615 1,619,521 
- 1,619,521 
151,947 2,223,68210 
177,238 2,220,48810,11 
1,163,053 12,304,01112 
1,152,878 12,293,836 
- 8,935 
- 8,935 
1,130,000 27,906,86913 
357,092 26,554,74913, 14 
1,225,488 34,347,12215 
1,228,152 34,347,12215 
- 7,969,329 
- 7,969,329 
-215,134 44,122,00116 
185,813 44,084,58216, 17 
4,833,799 78,658,14618 
4,997,300 78,609,006 
- 434,638 
- 434,638 
15-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 15-A (Continued) COST AND FINANCIAL STATEMENT 
See Project Funding FY 72 FY 73 FY 74 FY 75 Total Cost to 
Section June 30, 1975 
in Text 
8. Houston Ship 
Channel, Texas 
(Regular Funds) 
(Contributed 
Funds) 
9. Matagorda Ship 
Channel, Texas 
(Regular Funds) 
bContributed 
unds) 
10. Sabine-Neches 
Waterway, Texas 
(Regular Funds) 
(Contributed 
Funds) 
11. Texas City 
Channel, 
Texas 
12. Trinity River 
and Tributaries, 
Texas 
15. Corpus Christi 
Beach, Texas 
(Restoration 
Project) 
16. Buffalo Bayou 
and Tributaries, 
Texas 
17. Clear Creek, 
Texas 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
1,840,577 991,021 
2,178,246 1,025,160 
4,513 
200,828 
1,146,583 
647,652 
200,828 
2,638,678 
4,139,239 
2,749,900 
3,061,529 
-5,026 
175,779 
583,700 
413,383 
8,486,099 
8,178,988 
321,300 
211,254 
483,500 
119,373 
220,800 
199,458 
99,300 
34,083 
16,821 
909,828 
1,371,921 
-12,962 
8,162 
2,931,282 
1,415,285 
- - 835,873 
- - 835,873 
-- 35,760,38219 
- - 35,760,38219 
1,661,403 2,370,860 50,115,63920 
1,579,965 2,484,743 50,103,74820 
- - 2,591,93921 
- - 2,591,939 2 1 
- - 18,058,777 
-- 1,058,777 
399,698 1,827,260 11,475,712 22 
435,472 1,836,981 11,475,433 2 2 
-6,873 
10,559 
3,432,865 
4,806,996 
160,000 158,000 
- 205,059 
- 44,000 
- 39,256 
68,468 18,814 
238,818 18,814 
2,920,000 
2,984,097 
119,040 
297,318 
753,000 
1,237,636 
310,000 
284,678 
335,000 
418,016 
684,313 
684,538 
57,600 
29,117 
243,000 
412,152 
528,200 
584,543 
- 12,259,619 23 
- 12,259,61923 
- 56,136,81524 
- 56,136,81524 
4,082,097 62,268,329 25 
4,204,741 62,248,543 25 
-11,410 2,680,94226 
- 2,680,94226 
-54,429 360,611 
58,512 360,611 
80,000 5,582,372 27 
83,306 5,580,93427, 28 
1,053,248 9,695,36729 
1,052,939 9,695,058 
- 726,158 
- 726,158 
215,000 25,859,676 30 
243,574 25,704,729 30, 31 
183,138 4,618,58632 
177,618 4,613,06632 
23,000 80,600 
49,508 78,625 
2,335,000 
2,467,339 
425,000 
421,993 
54,869,994 3 3 
54,865,837 33, 34 
4,242,413 
4,239,142 
75,000 137,500 161,714 473,514 
89,834 187,825 161,772 473,514 
15-18

GALVESTON, TEX., DISTRICT 
TABLE 15-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
18. Freeport and 
Vicinity, Texas, 
Hurricane Flood 
Protection. 
(Regular Funds) 
(Contributed 
Funds) 
19. Guadalupe River 
(Remove Log 
Jams), Texas 
20. Highland Bayou, 
Texas 
21. Lower Rio 
Grande Basin, 
Texas 
22. Peyton Creek, 
Texas 
23. Port Arthur and 
Vicinity, Texas, 
Hurricane Flood 
protection 
(Regular Funds) 
(Contributed 
Funds) 
(Advance 
Contributed 
Funds) 
24. Taylors Bayou, 
Texas 
25. Texas City and 
Vicinity, Texas, 
Hurricane-Flood 
Protection 
(Regular Funds) 
(Contributed 
unds) 
26. Vince and Little 
Vince Bayous, 
Texas 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
511,500 2,730,000 940,000 3,600,000 14,838,042 
1,487,206 1,672,501 2,176,623 3,560,451 14,314,046 
-232,285 
24,800 
14,790 
-200,700 
98,677 
-158,675 65 
-5 10 
10,005 1 
31,000 74 
71,165 9 
- - 2 
- - 1 
5,206,009 7,872,000 1,31 
5,773,410 4,400,434 4,40 
1,700,000 
1,805,044 
400,000 
273,543 
75,700 
160,629 
1,733,400 
1,365,505 
660,000 
561,820 
-180,000 
32,831 
1,300,000 
754,995 
-400,000 
-273,543 
161,000 
223,683 
1,852,000 
1,543,047 
500,000 
658,687 
400,000 
331,705 
- 1,750,000 
9,365 1,517,092 
0,000 248,000 
4,856 318,924 
0,000 2,114,000 
5,582 2,296,516 
- 164,400 
- 104,847 
0,000 46,377 
8,537 47,840 
5,500 5,734,000 
9,405 5,597,936 
3,970,000 
3,674,675 3 5 
378,449 
364,229 
3,515,136 
3,052,986 
164,400 
104,847 
66,377 
66,377 
36,570,509 
35,218,184 
600,000 1,200,000 8,760,000 
500,436 1,995,303 8,602,74236 
94,200 
98,168 
1,240,000 
1,817,928 
800,000 
778,964 
73,300 
499,192 
100,000 
91,563 
1,355,000 
1,710,196 
650,000 
660,635 
-15,000 
18,903 
951,898 
935,222 
23,212,400 
22,522,869 
8,885,100 
8,727,996 37 
3,285,100 
3,279,259 
1. Excludes $106,189 credit for contributed work. 
2. Includes $675,855 for previous projects. Excludes 
$1,806,619 contributed funds, of which $123,361 represents 
previous projects and $1,683,258 is for existing project. 
3. Includes $48,966 for reconnaissance surveys. 
4. Includes $39,087 for previous projects. 
5. Includes $69,784 for previous projects. Includes 
$5,219 for reconnaissance surveys. 
6. Excludes $25,000 expended from contributed funds. 
7. Includes $1,372,534 for previous projects. Includes 
$456,515 for Sec. 107 project for Port Aransas Breakwaters. 
8. In addition, $768 expended from contributed funds 
for Port Aransas Breakwaters. 
9. Includes $62,452 for previous projects. Includes 
$49,072 for reconnaissance surveys. Excludes $152,555 from 
contributed funds. 
10. Includes $147,098 for previous projects. 
11. In addition $758,303 expended from contributed 
funds. 
12. Includes $4,551 for reconnaissance surveys. 
13. Includes $8,421,996 for previous projects. 
14. In addition, $3,586,174 expended from contributed 
funds. 
15. Includes $86,126 for previous projects and $12,242 
for reconnaissance surveys. 
16. Includes $706,709 for previous projects. Includes 
Sec. 107 project for Port Isabel Small Boat Basin in amount 
of $46,559. Includes Sec. 107 project for Port Isabel Side 
Channel in amount of $8,414. Includes Sec. 107 project for 
Offatts Bayou in amount of $356,466. 
17. In addition, $46,559 expended from contributed 
funds for Port Isabel Small Boat Basin and $49,665 expended 
from contributed funds for Offatts Bayou. 
18. Includes $1,526,564 for previous projects, and 
$221,443 for reconnaissance surveys. Excludes $18,135 from 
contributed funds. 
19. Includes $4,105,157 for previous projects. 
20. Includes $1,213,142 for previous projects and 
$35,010 for reconnaissance surveys. Excludes $200,000 from 
contributed funds on previous projects. In addition, $17,939 
expended from contributed funds. 
21. Includes $1,209,179 for previous projects. 
15-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 15-A (Continued) COST AND FINANCIAL STATEMENT 
22. Includes $38,725 for reconnaissance surveys. 
23. Excludes $182,800 for contributed lands. 
24. Includes $5,180,832 for previous projects. 
25. Includes $2,379,677 for previous projects and 
$20,769 for reconnaissance surveys. 
26. Includes $577,507 for previous projects. 
27. Includes $366,823 for previous projects. 
28. In addition $28,741 expended from contributed 
funds. 
29. Includes $195,083 for previous projects and $10,503 
for reconnaissance surveys. 
30. Includes $1,966,306 for previous projects. 
31. In addition, $66,000 expended from contributed 
funds. 
32. Includes $543,662 for previous projects and $11,772 
for reconnaissance surveys. 
33. Federal funds of $4,400,000 repaid to Harris County 
Flood Control District. Cost and financial data formerly reported 
under advanced funds transferred to Federal funds 
and are included herein. 
34. In addition, $63,661 contributed funds expended for 
Brays Bayou Channel and $12,900 Federal funds and 
$19,104 contributed funds expended for enlargement of 
Clodine Ditch. 
35. Excludes $1,036,105 estimated value of contributed 
lands and $1,423,810 for relocations. 
36. Excludes $2,823,904 estimated value of contributed 
lands and $3,990,317 for relocations. 
37. Excludes $1,070,194 estimated value of contributed 
lands, and $26,649 credit given local sponsor for workin-
kind. 
15-20

GALVESTON, TEX., DIST. 
TABLE 15-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
July 3, 1930 
May 24, 1934 
(PWA) 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
May 17, 1950 
July 14, 1960 
July 3, 1930 
Mar. 3, 1899 
June 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 19132 
Sept. 23, 1922 
July 3, 1930 3 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Provides for control of progressive eradication of aquatic 
plant growth from the navigable waters and streams in the 
U.S. 
BRAZOS ISLAND HARBOR, TEXAS (See Section 2 of Text) 
Jetties and jetty channel, inside channels and basins. 
Local cooperation requirements modified to provide 
contribution of funds to cover cost of original dredging 
of all inside channels and basins. 
Deepen jetty channel to 31 feet and inner channels and 
Brownsville and Port Isabel turning basins to 28 feet. 
Enlarge Port Isabel turning basin. 
Deepen entrance channel to 35 feet; deepen to 33 feet 
channel across Laguna Madre; deepen to 32 feet channels 
from Laguna Madre to turning basins at Brownsville and 
Port Isabel; widen turning basins; and dredging present 
shallow-draft channel south of Port Isabel from railroad 
bridge to Laguna Madre and connecting channel to Port 
Isabel turning basin. 
Additional connecting channel between Port Isabel and 
Brownsville channels; and transfer shallow-draft channels 
at Port Isabel to GIWW. 
Deepen to 38 feet in outer bar channels and 36 feet in all 
other authorized channels and basins; extend existing 
turning basins at Brownsville and Port Isabel; and 
construct small-boat basin with a connecting channel 
next to Brownsville ship channel. 
Widen Brownsville Channel to 300 feet at a depth of 36 feet 
from former Goose Island passing basin to turning basin 
extension, thence at a width of 500 feet and same depth 
to turning basin proper, deepen to 36 feet in area in 
southeast corner of turning basin, maintain two existing 
basins of fishing harbor, and a connecting channel, and 
construct a third basin, with necessary connecting channel, 
and extend Brazos Island Harbor north jetty seaward 
1,000 feet. 
CEDAR BAYOU, TEXAS (See Section 3 of Text) 
Channel 10 feet deep and 100 feet wide from Houston Ship 
Channel to a point on bayou 11 miles above mouth. 
CORPUS CHRISTI SHIP CHANNEL, TEXAS 
(See Section 4 of Text) 
Acquisition of old curved portion of north jetty previously 
constructed by private parties. 
Complete north jetty in accordance with builder's plans. 
Complete north jetty in accordance with builder's plans. 
Connect old curve jetty to St. Joseph Island, and construct 
south jetty. 
Dredge roadstead in Harbor Island Basin to 20 feet deep and 
construct 10,000 linear feet of stone dike on St. Joseph 
Island. 
Channel between jetties and Harbor Island Basin to 25 feet 
deep, extend jetties seaward, extend dike on St. Joseph 
Island 9,100 feet, and dredge approach channel 12 feet 
deep to town of Port Aransas. 
Dredging channel from Aransas Pass to Corpus Christi, 25 
feet deep, 200 feet bottom width. 
Deepen entrance channel from gulf to Harbor Island and 
provide an inner basin at Harbor Island of reduced area 
but greater depth. 
H. Doc. 251, 89th Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 16, 71st Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 10, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 32, 75th Cong., 1st sess. 
H. Doc. 335, 76th Cong. 
1st sess. 
H. Doc. 347, 77th Cong., 
1st sess. 
H. Doc. 627, 79th Cong., 
2d sess. 
H. Doc. 192, 81st Cong., 
1st sess. 
H. Doc. 428, 86th Cong., 
2d sess.1 
S. Doc. 107, 71st Cong., 
2d sess. 1 
Specified in act 
Specified in acts. 
Specified in act. 
Rivers and Harbors Committee, 
Doc. 5, 59th Cong., 2d sess. 
H. Doc. 1094, 61st Cong., 
3d sess. 
H. Doc. 1125, 62d Cong., 
3d sess. 
H. Doc. 321, 67th Cong., 
2d sess. 
H. Doc. 214, 70th Cong., 
1st sess. 
15-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 15-B (Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
Aug. 30, 19354 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
June 20, 1938 
Mar. 2, 1945 
June 30, 1948 
Sept. 3, 1954 
Sept. 3, 19545 
Sept. 3, 1954 
July 3, 1958 
July 3, 1958 
July 3, 1958 
July 3, 1958 
July 4, 1960 
As amended by 
Dec. 31, 1970) 
Channel from Aransas Pass to Corpus Christi Channel with 
depth 30 feet. 
Enlarge all channels from gulf to western end of basin 
dredged by Humble Oil and Refining Co., at its docks 
on Harbor Island. 
Maintain channel and maneuvering basin between breakwater 
and western shoreline of Corpus Christi Bay. 
Maintain 30-foot depth of approach channel, turning basin 
at Corpus Christi, Industrial Canal and turning basin at 
Avery Point. 
Maintain and deepen to 32 feet channel from deep water 
at Port Aransas to and including turning basin at 
Corpus Christi. 
Extend main turning basin at Corpus Christi westward 
2,500 feet at its present width and depth, deepen existing 
Industrial Canal and turning basin to 32 feet and extend 
this canal at a depth of 32 feet and general width of 150 
feet, westward along Nueces Bay shore to a turning basin 
32 feet by 900 feet, and 1,000 feet long near Tule Lake. 
Provide depth of 34 feet in all project channels and basins 
from Port Aransas to and including Tule Lake turning basin, 
for a width of 250 feet from Port Aransas to breakwater at 
Corpus Christi, for a width of 200 feet in Industrial Canal 
and in channel between Avery Point and Tule Lake turning 
basins, and widen Avery Point turning basin to 1,000 feet. 
Deepen entrance channel to 38 feet from gulf to outer end 
of jetty; 38 feet decreasing to 36 feet thence to station 
90 north jetty; and 36 feet in all other deep water channels 
and basins except 2,000-foot undredged part of inner basin 
at Harbor Island, and a width of 400 feet in channel from 
Port Aransas to Maneuvering basin at Corpus Christi. 
An anchorage basin 12 feet deep, from 300 to 400 feet wide, 
and 900 feet long in Turtle Cove at Port Aransas, Texas. 
Branch channel 32 feet by 150 feet, extending northerly 
from main channel in vicinity of Port Ingleside, along 
north shore of Corpus Christi Bay to Reynolds Metals Co. 
plant and turning basin 32 feet deep and 800 feet square 
near plant in general vicinity of La Quinta, Texas. 
An entrance channel 36 by 400 feet on a tangent alinement 
from 400-foot channel in Corpus Christi Bay,near Corpus 
Christi breakwater, to flared approach channel to Corpus 
Christi turning basin. 
Deepen and widen LaQuinta Channel to 36 by 200 feet; enlarge 
LaQuinta turning basin to 36 by 800 by 1,000 feet; 
a flared entrance to channel; and widening at curves. 
Deepen entrance channel to 42 feet from gulf to outer end of 
jetty; 40 feet in all other deep-water channels and basins 
except undredged northward extension of inner basin at 
Harbor Island and branch channel to LaQuinta; and widen 
Industrial Canal to 400 feet with flared entrances to 
Corpus Christi and Avery Point turning basins. 
Channel 40 by 200 feet extending 2.2 miles from Tule Lake 
turning basin to a turning basin 40 feet deep, 700 to 900 
feet wide, 1,000 feet long at Viola, Texas. 
Depth of 12 feet and a width of 100 feet in locally dredged 
Jewel Fulton Canal from LaQuinta Channel to a turning 
basin 12 by 200 by 400 feet, and assumption of maintenance 
by United States. 
Construction of a breakwater at entrance to harbor area at 
Port Aransas, and realignment of existing 12-foot by 
100 foot project channel. 
Rivers and Harbors Committee 
Doc. 9, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Does. 35, 72d Cong., 1st sess. 
and 40, 73d Cong., 2d sess. 
H. Doc. 130, 72d Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 13, 74th Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 63, 74th Cong., 1st 
sess. 
H. Doc. 574, 75th Cong., 3d 
sess. 
H. Doc. 544, 78th Cong., 2d 
sess. 
H. Doc. 560, 80th Cong., 
2d sess. 
H. Doc. 654, 81st Cong., 
1st sess. 
H. Doc. 89, 83rd Cong., 
1st sess. 
H. Doc. 487, 83rd Cong., 
2d sess. 
S. Doc. 33, 85th Cong., 
1st sess. 
H. Doc. 361, 85th Cong., 
2d sess. 
H. Doc. 361, 85th Cong., 
2d sess. 
H. Doc. 361, 85th Cong., 
2d sess. 
Sec. 107, Public Law 86-645 
15-22

GALVESTON, TEX., DISTRICT 
AUTHORIZING LEGISLATION 
TABLE 15-B (Continued) 
Acts Work Authorized Documents 
July 26, 1968 
Mar. 3, 1899 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 1913 
Aug. 8, 1917 
Mar. 3, 1925 6 
July 3, 1930 
Aug. 30, 19357 
Aug. 30, 1935 
May 17, 1950 
July 3, 1958 
Oct. 5, 1961 
Dec. 31, 1970 
Aug. 5, 1886 
June 13, 1902 
Mar 3, 1905 
Mar. 2, 1907 
Provides for a project depth of 45 feet in the existing deepdraft 
channels and basins, for construction of a new deepdraft 
turning point, for construction of a deep-draft mooring 
area and mooring facilities, and for widening of the 
channels and basins at certain locations. The Act also 
deauthorized the undredged northward extension of Inner 
Basin at Harbor Island and the undredged west turnout (Wye 
connection) between the LaQuinta Channel and the main 
channel of the waterway. 
FREEPORT HARBOR, TEXAS (See Section 5 of Text) 
Dredging and other work necessary in judgment of Secretary 
of War for improving harbor; for taking over jetties and 
privately built works at mouth of river. 
Examination authorized. Work later confined to maintenance 
of jetties. 
Repairs to jetties and dredging. 
Construct seagoing hopper dredge. 
Purchase of one 15-inch pipeline dredge and equipment, 
its operation for 3 years, operation of seagoing dredge 
one-half time for 3 years, and repairs to jetties. 
Diversion dam, diversion channel, and necessary auxiliary 
works. 
Maintenance of diversion channel at expense of local 
interest. 
Deepening channels and basins. 
Maintenance of present project dimensions of channels 
and basins at Federal expense. 
Deepen outer bar channel to 38 feet from gulf to a point 
within jetties, thence 36 feet in authorized channels to 
and including upper turning basin. 
Relocate outer bar channel on straight alignment with jetty 
channel and maintain Brazos Harbor entrance channel 
and turning basin (constructed by local interests). 
Modification of HD 1469. Revoking certain provisions of 
local cooperation. 
Relocation of entrance channel and deepen to 47 feet; 
enlargement to a depth of 45 feet and relocation of jetty 
channel and inside main channel; deepening to 45 feet 
of channel to Brazosport; enlargement of the widened 
area at Quintana Point to provide a depth of 45 feet with 
a 750-foot diameter turning area; Brazosport turning basin 
to 45 feet deep with a 1,000 foot turning area; a new 
turning basin with a 1,200-foot diameter turning area and 
45 feet deep; deepening Brazosport channel to 36 feet and 
Brazosport Turning Basin to 36 by 750 feet diameter; flared 
approaches from Brazos Harbor Channel; relocation of north 
jetty and rehabilitation of south jetty. 
GALVESTON HARBOR AND CHANNEL, TEXAS (See 
Sec. 6 of Text) 
Construct 2 rubblestone jetties at entrance to Galveston 
Harbor. 
A channel 1,200 by 30 feet from Bolivar Roads (outer end of 
old inner bar near Fort Point) to 51st St. 8 
Purchase or construct hydraulic pipeline dredge. 
Extension of jetties to present project length and 
construction and operation of a dredge. 
S. Doc. 99, 90th Cong. 
2d sess.' 
Specified in act. 
H. Doc. 1087, 60th Cong., 
2d sess. 
Specified in act. 
Specified in act. 
H. Doc. 1469, 63d Cong., 
3d sess. 
Rivers and Harbors Committee 
Doc. 10, 68th Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 18, 70th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 15, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Does. 15, 72d Cong., 1st 
sess., and 29, 73d Cong., 
2d sess. 
H. Doc. 195, 81st Cong., 
1st sess. 
H. Doc. 433, 84th Cong., 
2d sess. 
P.L. 394, 87th Cong. 
H. Doc. 289, 93d Cong., 
2d sess.1 
H. Doc. 85, 49th Cong., 1st 
sess., and Annual Report, 
1886, p. 1311. 
H. Doc. 264, 56th Cong., 
2d sess. 
Specified in act. 
H. Doc. 340, 59th Cong., 2d 
sess., and Rivers and Harbors 
Committee Doc. 11, 59th Cong., 
2d sess. 
15-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 15-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
June 25, 19109 
July 27, 1916 
July 18, 1918 
Sept. 22, 1922 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
April 4, 1938 
June 30, 1948 
May 17, 1950 
July 3, 1958 
June 23, 1971 
(House Res.) 
Nov. 18, 1971 
(Sen. Res.) 
Mar. 2, 1907 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 26, 1937 
June 20, 193813 
June 20, 1938 
June 20, 1938 
June 20, 1938 
Extension of Galveston Channel from 51st to 57th Sts., 
with depth of 30 feet and width of 700 feet. 
Conditional extension of Galveston Channel between 
51st and 57th Sts., 30 feet deep and 1,000 feet wide. 
Extend seawall at Galveston from angle at 6th St. and 
Broadway to vicinity of Fort San Jacinto. 
Deepen harbor channel to 35 feet and widen to 800 feet. 
Further extension of seawall at Galveston to a junction 
with south jetty; and repairing seawall in front of Fort 
Crockett Reservation. 
Deepen Galveston Channel to 32 feet; and maintain 
Galveston Harbor channels to dimensions of 800 feet 
wide, 35 feet deep on outer bar and 34 feet deep on 
inner bar.1 0 
Maintain State Highway Ferry Landing Channels to 
dimensions of 12 by 100 feet. 
Construct 13 groins along gulf shore from 12th to 61st Sts. 
in city of Galveston at a limited cost of $234,000 (10 
groins constructed). 
Deepen Galveston Channel to 34 feet (Bolivar Roads to 
43d St.). 
Deepen Galveston entrance channel to 36 feet. 
Completion of project for construction of 13 groins. 
Deepen Galveston Harbor to 38 feet from gulf to a point 
2 miles west of seaward end of north jetty; thence 36 
feet to Bolivar Roads; revoking authority for maintenance 
of ferry channels; and Galveston channel to 36 feet deep 
from Bolivar Roads to 43d St. 
Construct extension of Galveston seawall from 61st St., 
southwesterly 16,300 feet along gulf shore. 
Deepen Galveston Harbor to 42 feet from gulf to a point 
2 miles west of seaward end of north jetty and 40 feet 
thence to Bolivar Roads. 
Deepen Galveston Channel to 40 feet from Bolivar Roads to 
43d St. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FLA. AND MEXICAN BORDER 
(GALV. DIST.) (See Section 7 of Text)1 2 
Channel 4 by 100 feet from West Galveston Bay across 
Chocolate Bay to 4 feet of water in Chocolate Bay. 
Channel 9 by 100 feet, Sabine River to Galveston Bay, and 
a 20-inch pipeline dredge. Such passing places, widening 
at bends, locks or guard locks and railway bridges over 
artificial cuts as are necessary. 
Channel 9 by 100 feet, Galveston Bay to Corpus Christi. 
Maintenance of a flood-discharge channel in Colorado River. 
Channel 9 by 100 feet in San Bernard River, Texas. 
Channel in Colorado River, 9 by 100 feet, with basin. 
Channel 9 by 100 feet from Palacios through Trepalacios 
and Matagorda Bays. 
Channel 9 by 200 feet from main channel to harbor at 
Rockport and improve harbor to 9-foot depth. 
H. Doc. 768, 59th Cong., 2d 
sess. 
H. Doc. 328, 61st Cong., 2d 
sess. 
H. Doc. 1390, 62d Cong., 3d 
sess. 
H. Doc. 758, 65th Cong., 2d 
sess. 
H. Doc. 693, 66th Cong., 2d 
sess. 
H. Doc. 307, 69th Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 31, 72d Cong., 1st sess. 
H. Doc. 400, 73d Cong., 2d 
sess. 
Rivers and Harbors Committee 
Doc. 61, 74th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 57, 74th Cong., 1st sess. 
P.L. 463, 75th Cong. 
H. Doc. 561, 80th Cong., 
2d sess. 
H. Doc. 173, 81st Cong., 
1st sess. 
H. Doc. 350, 85th Cong., 
2d sess. 
H. Doc. 121, 92d Cong., 
1st sess. 
(Sec. 201, PL 89-298) 
H. Doc. 445, 56th Cong., 
1st sess. 
H. Doc. 238, 68th Cong., 
1st sess. 
H. Doc. 238, 68th Cong. 
1st sess. 
S. Committee print, 75th 
Cong., 1st sess. 
H. Doc. 640, 75th Cong., 3d 
sess. 
H. Doc. 642, 75th Cong., 
3d sess. 
H. Doc. 564, 75th Cong. 
3d sess. 
H. Doc. 641, 75th Cong. 
3d sess. 
15-24

GALVESTON, TEX., DISTRICT 
TABLE 15-B (Continued) AUTHORIZATION LEGISLATION 
Acts Work Authorized Documents 
June 20, 1938 
Mar. 23, 1939 
July 23, 1942 
Mar. 2, 1945 
Mar. 2, 19459 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 194514 
July 24, 1946 
July 24, 1946 
May 17, 1950 
May 17, 1950 
May 17, 1950 
July 12, 1952 
Sept. 3, 19549 
Sept. 3, 1954 
Sept. 9, 1959 
July 14, 1960 
July 4, 1960 
(As amended 
Dec. 31, 1970) 
Channel 6 by 100 feet from main channel to Aransas Pass, 
Tex. 
Enlarge waterway to a depth of 12 feet and a width of 
125 feet from Sabine River to Corpus Christi. 
Enlarge waterway from Corpus Christi to vicinity of 
Mexican border to provide a depth of 12 feet and 
width of 125 feet throughout. 
Channel 6 by 60 feet from GIWW to a point in Chocolate 
Bayou near Liverpool. 
Channel 6 feet deep and 60 feet wide from main channel 
near Port O'Connor, Tex., into Barroom Bay. 
Enlarge channel from main channel to Aransas Pass, Tex., 
providing a depth of 9 feet and width of 100 feet. 
Channel 12 by 125 feet from main channel to Red Fish 
Landing, Tex., with basin. 
Channel 12 feet deep and 125 feet wide from main 
channel to vicinity of Harlingen, Tex., via Arroyo 
Colorado, with basin. 
Fill a portion of shallow-draft channel adjacent to Port 
Isabel Turning Basin, construct a channel to connect 
shallow-draft channel with main channel near shoreline 
of Laguna Madre, and enlarge shallow-draft 
channel west of this connection, all of 12 feet deep 
and bottom width of 125 feet. 
Reroute main channel to north shore of Red Fish Bay 
between Aransas Bay and Corpus Christi Bay; deepen 
tributary channel from Port Aransas to Aransas Pass, 
Tex. 12 feet and extend basin at same depth. 
Deauthorized 6 by 60 foot channel in Chocolate Bayou and 
reauthorized the 4 by 100-foot channel. 
Alternate channel across South Galveston Bay between 
Port Bolivar and Galveston causeway. 
"Red Fish Landing" changed to "Port Mansfield, Tex." 
Incorporate as part of Intracoastal Waterway a channel 9 by 
100 feet from main channel via Seadrift to point on 
Guadalupe River 3 miles above Victoria, Tex., authorized 
by River and Harbor Act of 1945. 
Small craft harbor 9 by 200 by 1,000 feet at Seadrift with 
an entrance channel 9 by 100 ft. 
Widen tributary channel between Port Aransas and 
Aransas Pass, Tex., to 125 feet; straighten and widen to 
125 feet connecting channel to Conn Brown Harbor, 
and maintain Conn Brown Harbor at Federal expense, 
all to 12 feet deep. 
Improve channels and basins comprising channel to Port 
Mansfield constructed in part by Federal Government 
and in part by local interests; constructing turnout 
curves at Gulf Intracoastal Waterway intersection and 
bend easing at entrance to turning basin; construct 
parallel jetties at gulf entrance; maintenance of 
locally dredged jetty channel 16 by 250 feet; and 
maintenance of small craft basin. 
Entrance channel 7 feet deep by 75 feet wide from main 
channel to Gulf of Mexico to inside shoreline at Port 
Isabel, Tex., an inner channel 6 feet deep by 50 feet 
wide from entrance channel to East Harbor Basin, 
and an irregular-shaped harbor basin 6 feet deep having 
a surface area of about 7 acres. 
Deepen the existing 6-foot channel at Port Isabel to 
12 feet and removing the submerged bars at each 
end of the island to a depth of -12 feet MLT. 
H. Doc. 643, 75th Cong., 3d 
sess. 
H. Doc. 230, 76th Cong., 1st 
sess. 
P.L. 675, 77th Cong. 
H. Doc. 337, 76th Cong., 
1st sess. 
H. Doc. 428, 76th Cong., 1st 
sess. 
H. Doc. 383, 77th Cong., 1st 
sess. 
S. Doc. 248, 78th Cong., 2d 
sess. 
H. Doc. 402, 77th Cong., 1st 
sess. (See Public Law 14, 
79th Cong.) 
H. Doc. 627, 79th Cong., 
2d sess. 
H. Doc. 700, 79th Cong., 
2d sess. 
H. Doc. 768, 80th Cong., 2d 
sess. 
H. Doc. 196, 81st Cong., 1st 
sess. 
P.L. 516, 81st Cong. 
P.L. 527, 82d Cong., 2d 
sess. 
H. Doc. 478, 81st Cong., 
2d sess. 
H. Doc. 376, 83d Cong., 
2d sess. 
S. Doc. 11, 86th Cong., 
1st sess. 
Sec. 107, P.L. 645, 86th 
Cong. 
Sec. 107, P.L. 86-645 
15-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 15-B (Continued) AUTHORIZATION LEGISLATION 
Work Authorized 
July 4, 1960 
(As amended 
Dec. 31, 1970) 
Oct. 23, 196215 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 27, 1965 
Aug. 13, 1968 
Mar. 5, 1905 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
June 30, 1948 
Deepening the existing channel to 12 by 125 feet, and extend 
southeasterly from the Gulf Intracoastal Waterway main 
channel in West Galveston Bay, into Offatts Bayou, a 
distance of 2.2 miles, and a west turnout 12 by 125 feet 
between the proposed Offatts Bayou Channel and the Gulf 
Intracoastal Waterway. 
Improve main channel 16 feet deep and 150 feet wide from 
Sabine River to Houston Ship Channel; with two relocations; 
relocate main channel in Matagorda Bay and Corpus Christi 
Bay; and maintain existing Lydia Ann Channel. 
Deepen and widen channel to Palacios; construct two protective 
breakwaters; maintain and deepen existing basins; and 
deepen, enlarge and maintain existing approach channel to 
basin No. 2. 
Eliminates requirement of local interests to construct bridge 
at mile 29.2 turning basin at Victoria, and maintain turning 
basins at Victoria and Seadrift; provide: Federal construction 
of vertical-lift railroad bridge at Missouri-Pacific Railroad 
mainline crossing, mile 29.2; construction and future 
maintenance of basin near Victoria, Texas, and maintenance 
of basin constructed by local interests at Seadrift, Tex. 
Modify existing Federal navigation project to provide a channel 
extending from Gulf Intracoastal Waterway through 
Chocolate Bay and Chocolate Bayou to project channel 
mile 8.2 thence to a turning basin near channel mile 13.2 
and for salt water barrier in Chocolate Bayou about 3.7 
miles upstream from basin (channel mile 16.9). 
Entrance channel 15 feet deep and 200 feet wide at the 
mouth of Colorado River Chan. protected by an east 
jetty, 3,500 feet long extending to 12-foot depth and a 
west jetty 2,900 feet long extending to 5-foot contour; 
make channel 12 feet by 100 feet from gulf shore to 
Matagorda, including recreation facil., a turning basin 
12 feet by 300 feet wide and 1,450 feet long, and a new 
diversion channel 250 feet wide and varying in depth 
from 20 to 23 feet including a closure dam across the 
present river channel. 
HOUSTON SHIP CHANNEL, TEXAS (See Section 8 
of Text) 
Easing or cutting off sharp bends and construction of a 
pile dike. 1 6 
A channel 30 feet deep, widen bend at Manchester and 
enlarge turning basin. 
A light-draft extension of channel to mouth of White Oak 
Bayou1 7 
Widen channel through Morgan Point and to a point 
4,000 feet above Baytown and widen certain bends. 
Deepen to 32 feet in main channel and turning basin, and a 
400-foot width through Galveston Bay. 
Deepen to 34 feet in main channel and widen from 
Morgan Point to turning basin. 
Branch channel 10 by 60 feet behind Brady Island. 
Widen channel from Morgan Point to lower end of 
Fidelity Island with turning points at mouth of 
Hunting Bayou and lower end of Brady Island. 
Widen channel from lower end of Fidelity Island to 
Houston turning basin and dredge off-channel silting 
basins. 
Deepen to 36 feet from Bolivar Roads to and including 
main turning basin at Houston, Texas, including turning 
points at Hunting Bayou and Brady Island. 
Sec. 107, Public Law 86-645 
H. Doc. 556, 87th Cong., 2d 
sess. 
H. Doc. 504, 87th Cong., 2d 
sess. 
H. Doc. 288, 87th Cong., 2d 
sess. 
H. Doc. 217, 89th Cong., 1st 
sess. 
S. Doc. 102, 90th Cong., 2d 
sess. 
Rivers and Harbors Committee 
Doc. 35, 61st Cong., 2d sess. 
H. Doc. 1632, 65th Cong., 3d 
sess. 
H. Doc. 93, 67th Cong., 1st 
sess. 
H. Doc. 13, 71st Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 28, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 58, 74th Cong., 1st 
sess. 
H. Doc. 226, 76th Cong., 1st 
sess. 
H. Doc. 256, 76th Cong., 1st 
sess. 
H. Doc. 737, 79th Cong., 2d 
sess. 
H. Doc. 561, 80th Cong., 2d 
sess. 
15-26 
Acts Documents

TABLE 15-B (Continued) 
GALVESTON, TEX., DISTRICT 
AUTHORIZATION LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 18 
July 14, 1960 
Oct. 27, 1965 
June 25, 1910 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
July 3, 1958 
July 3, 1958 
July 25, 1912 
Sept. 22, 1922 
Sept. 22, 1922 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 26, 1937 
Deepen to 40 feet from Bolivar Roads to Brady Island, 
construct Clinton Island turning basin, a channel 
8 by 125 feet at Five Mile Cut, and improve shallowdraft 
channel at Turkey Bend. 
Barbour Terminal at Morgan Point. 
Restoring existing locally dredged channel from mile 0 
to 0.34 to 36 feet deep and dredging a 15-12 ft. channel 
from mile 0.34 to 2.81, in Greens Bayou. 
MATAGORDA SHIP CHANNEL, TEXAS (See Section 9 
of Text) 
Channel to Port Lavaca, Texas 7 feet deep and 80 feet 
bottom width. 
Extend 7-foot channel to shoreline of Lavaca Bay at 
mouth of Lynns Bayou. 
Deepen and widen channel to present project dimensions. 
Extend channel 6 by 100 feet from Port Lavaca via 
Lavaca Bay, Lavaca and Navidad Rivers to Red Bluff, 
a distance of 20 miles. 
A harbor of refuge 9 feet deep near Port Lavaca and an 
approach channel 100 feet wide and equal depth. 
Deepen to 12 feet and widen to 125 feet Port Lavaca 
Channel and approach channel to harbor of refuge; 
deepen to 12 feet Port Lavaca turning basin and 
basins at harbor of refuge. 
An entrance channel 38 by 300 feet, a channel 36 by 
200 feet, 22 miles long across Matagorda and Lavaca 
Bays to Point Comfort, Texas, a turning basin 36 feet 
deep and 1,000 feet square at Point Comfort, and dual 
jetties at entrance from gulf. 
SABINE-NECHES WATERWAY, TEXAS (See Section 10 
of Text) 
Existing project dimensions of jetties, a 26-foot channel 
through Sabine Pass, Port Arthur Canal and Port Arthur 
turning basin; and a 26-foot turning basin at Port Arthur. 
A depth of 25-feet in Sabine-Neches Canal, Neches River 
to Beaumont and Sabine River to Orange, including 
cutoffs and widening channels. 
Deepen channels to 30 feet from gulf to Beaumont, with 
increased widths and an anchorage basin in Sabine Pass. 
Deepen Port Arthur east and west turning basins and 
approach channel to 30 feet. Take over and deepen to 
30 feet channel connecting west turning basin with 
Taylors Bayou turning basin. For a 30-foot depth in 
channel from mouth of Neches River to cutoff in 
Sabine River near Orange. 
Removal of guard lock in Sabine-Neches Canal. 
Widen Sabine Pass and jetty channel, Port Arthur Canal, 
and Sabine-Neches Canal. For dredging 2 passing 
places in Sabine-Neches Canal, easing of bends, removal 
and reconstructing Port Arthur field office, extending 
Beaumont turning basin upstream 200 feet above new 
city wharves, and an anchorage basin in Sabine Pass. 
A depth of 32 feet in channels from gulf to Beaumont 
turning basin, including all turning basins at Port 
Arthur. 
Deepen channels to 34 feet with increased widths from 
gulf to Beaumont turning basin. 
Construct suitable permanent protective works along 
Sabine Lake. Maintain Taylors Bayou turning basin. 
Maintain channel from Sabine River to Orange Municipal 
wharf. 
H. Doc. 350, 85th Cong., 2d 
sess . 
Sec. 107, Public Law 86-645. 
H. Doc. 257, 89th Cong., 1st. 
sess. 
H. Doc. 1082, 60th Cong., 2d 
sess. 
Rivers and Harbors Committee 
Doc. 28, 74th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 37, 75th Cong., 1st sess. 
H. Doc. 314, 76th Cong., 1st 
sess. 
H. Doc. 731, 79th Cong., 2d 
sess. 
H. Doc. 131, 84th Cong., 1st 
sess. 
H. Doc. 388, 84th Cong., 2d 
sess.1 
H. Doc. 773, 61st Cong., 2d 
sess. 
H. Doc. 975, 66th Cong., 3d 
sess. 
S. Doc. 152, 67th Cong., 2d 
sess. 
H. Doc. 234, 68th Cong., 1st 
sess. 
H. Doc. 287, 69th Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 27, 72d Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 12, 74th Cong., 1st 
sess. 
Specified in Act. 
Rivers and Harbors Committee 
Doc. 3, 75th Cong., 1st 
sess. 
15-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
TABLE 15-B (Continued) AUTHORIZATION LEGISLATION 
Acts Work Authorized Documents 
Aug. 26, 1937 
June 20, 193819 
Oct. 17, 1940 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 194620 
July 24, 194621 
July 24, 1946 
May 17, 1950 
Sept. 3, 195422 
Oct. 23, 196223 
Dredging 500 feet from eastern end of Harbor Island and 
abandonment of channel south and west of Harbor Island. 
Increased widths of channels from gulf to Beaumont 
turning basin and channel connecting Port Arthur west 
turning basin and Taylors Bayou turning basin, deepen 
Beaumont turning basin and Beaumont turning extension 
to 34 feet; and dredge a new cutoff from Smith's Bluff 
cutoff to McFadden Bend. 
Abandon Orange turning basin; dredge a channel 25 by 
150 feet, suitably widened on bends to highway bridge, 
and dredge a cutoff channel opposite Orange. 
Extend Beaumont turning basin upstream 300 feet. 
Widen Port Arthur west turning basin to 600 feet. 
Dredge a channel from Beaumont turning basin to 
vicinity of Pennsylvania Shipyard. 
Deepen Sabine Pass outer bar channel to 37 feet, Sabine 
Pass jetty channel to 36 feet at inner end, deepen to 
36 feet Sabine Pass Channel, Port Arthur Canal, Port 
Arthur east and west turning basins, Taylors Bayou 
turning basin, and channel from Port Arthur west 
turning basin to Taylors Bayou turning basin, and 
channel from Port Arthur west turning basin to 
to Taylors Bayou turning basin, deepen to 36 feet 
and widen to 400 feet Sabine-Neches Canal from Port 
Arthur Canal to mouth of Neches River except through 
Port Arthur bridge; deepen Neches River channel from 
mouth to Beaumont turning basin to 36 feet widening 
to 350 feet from Smith's Bluff to Beaumont turning 
basin; deepen junction area on Neches River at 
Beaumont turning basin to 36 feet; and widen Sabine- 
Neches Canal between Neches and Sabine Rivers to 
150 feet. 
Improve Cow Bayou, Texas, by construction of a channel 
100 feet wide and 13 feet deep extending from navigation 
channel in Sabine River to a point 0.5 mile above county 
bridge at Orangefield, Texas, with a turning basin. 
Improve Adams Bayou, Texas, to provide a channel 12 
feet deep and 100 feet wide extending from 12-foot 
depth in Sabine River to first county highway bridge 
across bayou. 
Deepen to 36 feet and widen to 400 feet the Sabine-Neches 
Canal near Port Arthur bridge; reconstruct Port Arthur 
Bridge and relocate Port Arthur field office. 
Rectification of certain reaches of existing Sabine Pass 
Channel, Sabine-Neches Canal, and Neches River and 
Sabine River Channel; widen to 350 feet entrance 
channel to Port Arthur turning basins; widen curve at 
junction of Port Arthur and Sabine-Neches Canals; 
relocate and enlarge Sabine Pass anchorage basin to 
34 by 1,500 by 3,000 feet; widen to 200 feet Sabine- 
Neches Canal from mouth of Neches River to mouth 
of Sabine River and Sabine River Channel to upper end 
of existing project at Orange, except for channel around 
Harbor Island at Orange; deepen to 30 feet Sabine River 
Channel from cutoff near Orange municipal slip to upper 
end of project, except around Harbor Island; and enlarge 
area at entrance to Orange municipal slip to provide a 
maneuvering basin. 
Improve outer bar channel to 42 and 40 feet for all inland 
channels to Port Arthur and Beaumont; width of 500 feet in 
Port Arthur Canal and 400 feet in Neches River Channel to 
Beaumont with three turning points in Neches River; a 
channel, 12 by 125 feet, extending in Sabine River to Echo; 
and replace an obstructive bridge at Port Arthur, Texas. 
Deauthorization of uncompleted portion of channel between 
Port Arthur west turning basin and Taylors Bayou turning 
basin and enlargement of entrance channel to Port Arthur 
turning basins. 
15-28 
Rivers and Harbors Committ 
Doc. 20, 75th Cong., 1st 
sess. 
H. Doc. 581, 75th Cong., 3d 
sess. 
S. Doc. 14, 77th Cong., 1st 
sess. 
H. Doc. 685, 76th Cong., 
3d sess. 
S. Doc. 60, 77th Cong., 
1st sess. 
S. Doc. 158, 77th Cong., 
2d Sess. 
H. Doc. 571, 79th Cong., 
2d sess. 
H. Doc. 702, 79th Cong., 
2d sess. 
H. Doc. 626, 79th Cong., 
2d sess. 
H. Doc. 174, 81st Cong., 
1st sess. 
S. Doc. 80, 83d Cong., 
2d sess. 
H. Doc. 553, 87th Cong. 
2d sess. 1

TABLE 15-B (Continued) 
GALVESTON, TEX., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 4, 1913 
July 3, 1930 
Aug. 30, 193524 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
June 30, 1948 
July 14, 1960 
Oct. 12, 1972 
(Sen. Res. ) 
Oct. 12, 1972 
(House Res.) 
Mar. 3, 1905 
July 25, 1912 
Sept. 22, 1922 
Mar. 2, 1945 
July 24, 1946 
Oct. 23, 1962 
Oct. 27, 1965 
Dec. 15, 1970 
(House Res.) 
Dec. 17, 1970 
(Sen. Res.) 
TEXAS CITY CHANNEL, TEXAS (See Section 11 of Text) 
A channel 300 by 30 feet and construct a pile dike 28,200 H. Doc. 1390, 62d Cong., 
feet long north to channel. 3d sess. 
A harbor 800 by 30 feet at Texas City, and construct a H. Doc. 107, 71st Cong., 
rubblemound dike. 1st sess. 
Extension of rubblemound dike to shoreline. Rivers and Harbors Committee 
Doc. 4, 73d Cong., 1st sess. 
Deepen channel and harbor to 32 feet. Rivers and Harbors Committee 
Doc. 46, 73d Cong., 2d sess. 
Deepen channel and harbor to 34 feet. Rivers and Harbors Committee 
Doc. 62, 74th Cong., 1st sess. 
Extend harbor 1,000 feet southward, 800 by 34 feet. Rivers and Harbors Committee 
Doc. 47, 75th Cong., 1st sess. 
Deepen channel and harbor to 36 feet, widen channel to H. Doc. 561, 80th Cong., 2d 
400 feet and harbor to 1,000 feet and changing name sess.1 
of project to "TEXAS CITY CHANNEL, TEXAS." 
Deepen channel and turning basin to 40 feet and construct H. Doc. 427, 80th Cong., 2d 
16-foot Industrial Barge Canal. sess. 
Widen the existing main turning basin to 1,200 feet including H. Doc. 199, 92d Cong., 2d 
relocation of the basin 85 feet to the east; provide a 40-foot sess. 
deep channel in the Industrial Canal at widths of 300-400 (Sec. 201, PL 89-298) 
feet, with a turning basin at the head of the canal 40 feet 
deep, 1,150 feet long, and 1,000 feet wide, and easing of the 
bend at the entrance to the canal, and deauthorization of 
shallow-draft Industrial Barge Canal not incorporated in the 
plan of improvement above. 
TRINITY RIVER AND TRIBUTARIES, TEXAS (See Section 12 
of Text) 
Anahuac Channel. 
6-foot channel to Liberty. 
Abandon improvements above Liberty and terminate all improve-H. Doc. 989, 66th Cong., 
ments by lock and dam, leaving a 6-foot channel from Liberty 3d sess. 
to mouth. 
Provides for a navigable channel from the Houston Ship H. Doc. 403, 77th Cong., 
Channel near Red Fish Bar in Galveston Bay to Liberty, sess. 
Texas, with project depth of 9 feet deep and 200 feet 
wide in Galveston and Trinity Bays to the mouth of 
Trinity River and 9 feet deep and 150 feet wide in the 
river section, with a turning basin at Liberty. 
Modification of the project to provide for a channel 9 feet H. Doc. 634, 79th Cong., 
deep and 150 feet wide from the Houston Ship Channel sess. 
near Red Fish Bar in Galveston Bay extending along the 
east shore of Trinity Bay to the mouth of the Trinity 
River at Anahuac, including protective spoil embankment 
on the bay side of the channel in lieu of the 9 by 200-foot 
channel in Galveston and Trinity Bays. 
Provides for the multiple-purpose Wallisville Reservoir, in- H. Doc. 215, 87th Cong., 
cluding a navigation lock in the Wallisville dam at Channel sess.1 
Mile 28.30 and advancement of the Channel to Liberty 
from one mile below Anahuac (Mile 23.2) to the Texas 
Gulf Sulphur Company's slip at Channel Mile 35.8, and 
incorporation into existing project Anahuac Channel and 
mouth of Trinity River Projects. 
Reevaluation of navigation benefits. H. Doc. 276, 89th Cong., 
CORPUS CHRISTI BEACH, TEXAS (RESTORATION 
PROJECT (See Section 15 of Text) 
Restoration and periodic nourishment of 1.4 miles of beach. 
1st 
2d 
1st 
1st 
sess. 
H. Doc. 415, 91st Cong., 2d 
sess. (Sec. 201, PL 89-298)1 
15-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 15-B (Continued) AUTHORIZATION LEGISLATION 
Acts Work Authorized Documents 
June 20, 1938 
Sept. 3, 1954 
Oct. 27, 1965 
Aug. 13, 1968 
Oct. 23, 1962 
Dec. 31, 1970 
Oct. 27, 1965 
Mar. 7, 1974 
Oct. 12, 1972 
(House and Sen. 
Res.) 
Oct. 23, 1962 
Oct. 27, 1965 
July 3, 1958 
BUFFALO BAYOU AND TRIBUTARIES, TEXAS (See 
Section 16 of Text) 
Barker & Addicks Reservoirs, Texas. 
Clearing, straightening, enlarging and lining of Buffalo 
Bayou, Brays, and White Oak Bayous. 
Extend upper limits of White Oak Bayou upstream about 
2.1 miles from BRI RR bridge to mouth of Cole Creek. 
CLEAR CREEK, TEXAS (See Section 17 of Text) 
Channel enlargement and rectification from upper end 
of Clear Lake at Mile 3.8 to improved channel Mile 34.8. 
FREEPORT AND VICINITY, TEXAS (HURRICANE FLOOD 
PROTECTION) (See Section 18 of Text) 
Improvements to 42.8 miles of existing levees, 2.1 miles of new 
levees and 2 interior drainage pumping plants. 
GUADALUPE RIVER (Remove Log Jams), TEXAS 
(See Section 19 of Text) 
Removal of log jams in numerous locations along the river. 
HIGHLAND BAYOU, TEXAS (See Section 20 of Text) 
Enlargement and rectification of Highland Bayou 
Channel, construction of diversion dam, and 
diversion channel. 
LOWER RIO GRANDE BASIN, TEXAS (See Section 
21 of Text) 
Undertake the phase 1 design memorandum stage of 
advanced engineering and design of the project 
involving the Willacy-Hidalgo Floodwater Bypass, the 
Laguna Madre Floodwater Channel, and the North 
Floodway Channel in Lower Rio Grande Basin, in 
Willacy, Hidalgo, and Cameron Counties, Texas. 
PEYTON CREEK, TEXAS (See Section 22 of Text) 
Enlargement and rectification of flood control channels 
along Peyton Creek, Bucks Bayou, Cottonwood Creek, 
Live Oak Slough, and Dry Creek; installation of plug 
in Cottonwood Creek; diversion channel from Cottonwood 
Creek to Bucks Bayou; construction of salt water barrier 
in lower reaches of Peyton Creek; and major drainage 
outlets to serve agricultural lands in Peyton Creek 
watershed. 
PORT ARTHUR AND VICINITY, TEXAS (HURRICANEFLOOD 
PROTECTION (See Section 23 of Text) 
Raising and reconstructing 6.3 miles of existing seawall; 
constructing 0.3 mile of new seawall, 20.3 miles new 
levees and five pumping plants; and raising and improving 
7.5 miles of existing levees. 
TAYLORS BAYOU, TEXAS (See Section 24 of Text) 
Enlarging and rectifying channels; construction of 
diversion channel; a salt water gate; enlargement of 
GIWW 1.3 miles and alteration of State Highway 
87 bridge. 
TEXAS CITY AND VICINITY, TEXAS (HURRICANEFLOOD 
PROTECTION (See Section 25 of Text) 
Construction of improvements for control of storm tides, 
consisting of new and enlarged levees and floodwalls 
approximately 14.1 and 2.1 miles in length; related 
drainage and stoplog structures; a navigation opening 
and pumping plants. 
H. Doc. 456, 75th Cong., 2d 
sess. 
H. Doc. 250, 83d Cong., 2d sess. 
H. Doc. 169, 89th Cong., 1st 
sess. 
H. Doc. 351, 90th Cong., 2d 
sess. 
H. Doc. 495, 87th Cong., 2d sess. 1 
Sec. 212, P.L. 91-611 
1 
H. Doc. 168, 89th Cong., 1st sess. 
Sec. 68, P.L. 93-251 
H. Doc. 341, 92d Cong., 2d sess. 
(Sec. 201, P.L. 89-298) 
H. Doc. 505, 87th Cong., 2d 
1 
sess. 
H. Doc. 206, 89th Cong., 1st sess.1 
H. Doc. 347, 85th Cong., 2d 
sess.1 
15-30

GALVESTON, TEX., DISTRICT 
TABLE 15-B (Continued) AUTHORIZATION LEGISLATION 
Acts Work Authorized Documents 
VINCE AND LITTLE VINCE BAYOUS, TEXAS 
(See Section 26 of Text) 
Oct. 23, 1962 Enlarging and rectifying channel of Vince Bayou and Little H. Doc. 441, 87th Cong., 
Vince Bayou upstream for a total of 11.5 miles for both 2d sess. 1 
streams. 
1. Contains latest published maps. 
2. Extension of north jetty 1,950 feet and south jetty 
1,265 feet considered inactive. 
3. Dredging 2,000- by 650-foot northerly extension of 
inner basin deauthorized. 
4. Included in Public Works Administration program 
Sept. 6, 1933 and Feb. 16, 1935. 
5. West leg of Wye junction with main channel deauthorized. 
6. Construction of lock in diversion dam at local expense 
considered inactive. 
7. Dredging upper .5 mile of channel to vicinity of 
Stauffer Chemical plant considered inactive. Included in 
Public Works Administration program Sept. 6, 1933. 
8. Dredging 43rd to 51st Sts. inactive. 
9. Inactive. 
10. Deepening 43rd to 57th Sts. inactive. 
11. Previously authorized Sept. 6, 1933 by Public 
Works Administration. 
12. H. Doc. 230, 76th Cong., 1st sess. and project 
documents contain latest published maps. 
13. Dredging upper 3.5 miles inactive. 
14. Dredging upper 5 miles is inactive. 
15. Portion of 16-foot by 150-foot channel from Sabine 
River to Houston Ship Channel placed in inactive category. 
16. Construction of pile dike considered inactive. 
17. Considered inactive from Hill Street Bridge to 
mouth of White Oak Bayou. 
18. Deepening channel to 40 feet from Southern Pacific 
Slip to Brady Island is inactive. 
19. Complete widening of channel between Port Arthur 
west turning basin and Taylors Bayou turning basin deauthorized 
by 1962 R&H Act. 
20. Complete deepening of channel between Port Arthur 
west turning basin and Taylors Bayou turning basin 
deauthorized by 1962 R&H Act. 
21. Channel extension above Cow Bayou turning basin 
near Orangefield considered inactive. 
22. Widening to 350 feet entrance channel to Port 
Arthur turning basins deauthorized by 1962 R&H Act. 
23. The 12-foot channel in Sabine River from Orange 
to Echo, Texas is inactive. 
24. Previously authorized Sept. 6, 1933, by Public 
Works Administration. 
15-31

TABLE 15-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Aquatic Plant Control (1958 and 1962 River 
and Harbor Acts) 6 1967 38,252 - 
Bastrop Bayou, Tex. 2 ' 3 1931 9,920 27,129 
Brazos River, Tex., from Velasco to Old 
Washington 3 1924 216,989 4 223,010 
Channel to Port Bolivar, Tex.1 6 1974 133,925 11818,45212 
Clear Creek and Clear Lake, Tex.6 1974 66,934 453,41713 
Corpus Christi, Tex., Channel to Navy 
Seaplane Base, Encinal Peninsula 6 1968 1,194,344 26,467 
Dickinson Bayou, Texas 6 1954 33,942 61,6515 
Double Bayou, Tex.6 1974 226,558 554,61314, 15 
East Bay Bayou (Hanna Reef), Tex.3 1922 2,476 847 
Johnson Bayou, La.6 ' 7 1933 2,261 54,042 
Little Bay, Texass 1957 - 1,65610 
Oyster Creek, Texas6 , 9 1922 6,942 7,556 
Sabine Riv. & Tribs., Texas (Echo to 
Morgan Bluff) 3 1971 
1. Excludes $1,672 work contributions. under Department of Army permit. 
2. Widening from 60 feet to 100 feet at 4-foot depth 9. No commerce reported. 
is inactive. 10. Reconnaissance surveys included, $1,651. 
3. Inactive. 11. Includes $48,711 for previous projects. 
4. Includes $123,676 from previous project. 12. Includes $46,101 for previous projects and $2,311 
5. Reconnaissance surveys included, $4,098. for reconnaissance surveys. 
6. Completed 13. Includes $9,229 for reconnaissance surveys. 
7. Channel adequate for existing commerce. 14. Includes $6,871 for reconnaissance surveys. 
8. Aransas County Navigation District, Rockport, 15. Excludes $3,022 from contributed funds. 
Tex. constructed project as authorized by 1950 River and 16. Uncompleted portion is inactive. 
Harbor Act (H. Doc. 114, 81st Cong., 1st sess.) in 1955 
TABLE 15-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Colorado River, Matagorda, Texas 2 1963 273,757 
Lavaca-Navidad Rivers, Texas: 
Hallettsville Project 1961 256,043 - 
General channel project 1952 21,086 - 
Liberty Local Protection Project, Texas 1 1971 98,517 - 
Mill Creek, Texas 1 1952 24,753 - 
San Diego Creek, Alice, Texas2 1963 135,175 
Tranquitas Creek, Kingsville, Texas2 1956 130,239 - 
1. Inactive. 
2. Completed. 
15-32

GALVESTON, TEX., DIST. 
TABLE 15-E TOTAL COST OF EXISTING PROJECT TO JUNE 30, 1975 
See 
Section Project Funds New Work Maintenance Rehabilitation Total 
in Text 
2. Brazos Island Harbor, 
Texas 
3. Cedar Bayou, Texas 
4. Corpus Christi Ship 
Channel, Texas 
5. Freeport Harbor, 
Texas 
6. Galveston Harbor and 
Channel, Texas 
7. Gulf Intracoastal 
Waterway between 
Apalachee Bay, Florida 
and the Mexican Border 
(Galveston District) 
8. Houston Ship Channel, 
Texas 
10. Sabine-Neches 
Waterway, Texas 
11. Texas City Channel, 
Texas 
12. Trinity River and 
Tributaries, Texas 
Regular 
Public works 
Contributed 
Total cost of project 
Regular 
Contributed 
Total cost of project 
Regular 
Public works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public works 
Contributed 
Total 
Value of useful work 
performed 
Total cost of project 
Regular: 
Channel 
Seawall 
Public works 
Contributed 
Total cost of project 
Regular 
Public works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public works 
Contributed 
Total cost of project 
Regular 
Public works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public works 
Contributed 
Total cost of project 
Regular 
Contributed 
Total cost of project 
$ 6,947,114 
2,848,560 
1,683,258 
11,478,932 
642,176 
25,000 
667,176 
30,955,294 
324,287 
1,620,289 
32,899,870 
1,716,695 
276,720 
34,893,285 
1,956,815 
116,575 
758,303 
2,831,693 
360,249 
3,191,942 
9,378,544 
8,754,209 
3,586,174 
21,718,927 
42,911,396 
466,477 
96,224 
43,474,097 
395,000 
139,776 
44,008,873 
29,042,293 
2,612,932 
1,382,760 
33,037,985 
49,592,331 
1,363,652 
2,103,435 
53,059,418 
32,000 
116,760 
53,208,178 
5,077,815 
136,296 
28,741 
5,242,852 
23,738,423 
66,000 
23,804,423 
$13,613,695 
13,613,695 
882,961 
882,961 
31,065,476 
152,555 
31,218,031 
31,218,031 
12,294,039 
12,294,039 
12,294,039 
34,083,825 
163,847 
13,121 
34,260,793 
77,082,442 
18,135 
77,100,577 
77,100,577 
48,890,606 
17,939 
48,908,545 
59,868,866 
360,611 
60,229,477 
60,229,477 
9,499,975 
9,499,975 
4,069,404 
4,069,404 
$2,170,080 
2,170,080 
3,576,684 
3,576,684 
3,576,684 
8,935 
8,935 
8,935 
7,373,356 
595,973 
7,969,329 
1,270,511 
1,270,511 
1,270,511 
726,158 
726,158 
$22,730,889 
2,848,560 
1,683,258 
27,262,707 
1,525,137 
25,000 
1,550,137 
65,597,454 
324,287 
1,772,844 
67,694,585 
1,716,695 
276,720 
69,688,000 
14.259,789 
116,575 
758,303 
15,134,667 
360,249 
15,494,916 
50,835,725 
9,514,029 
13,121 
3,586,174 
63,949,049 
121,264,349 
466,477 
114,359 
121,845,185 
395,000 
139,776 
122,379,961 
77,932,899 
2,612,932 
1,400,699 
81,946,530 
109,461,197 
1,363,652 
2,464,046 
113,288,895 
32,000 
116,760 
113,437,655 
15,303,948 
136,296 
28,741 
15,468,985 
27,807,827 
66,000 
27,873,827 
15-32

Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
2. Brazos Island 
Harbor, Texas 
3. Cedar Bayou, 
Texas 
4. Corpus Christi 
Ship Channel, 
Texas 
Outer Bar and Jetty Channel 38-36 
Padre Island to Long Island 36 
Long Island to Goose Island 36 
Goose Island to Turning Basin Extension 36 
Turning Basin Extension 36 
Brownsville Turning Basin 36 
Port Isabel Channel via East Turnout 36 
West Wye, from Brownsville 
Channel 36 
Port Isabel Turning Basin 36 
Fishing Boat Harbor: 
West Basin 15 
Middle Basin 15 
East Basin 15 
Connecting Channel 15 
Entrance Channel 15 
Houston Ship Channel to Bayou 
Mile 3.0 10 
Bayou Mile 3.0 to Mile 11.07 10 
Aransas Pass Outer Bar Channel 47 
Aransas Pass Jetty Channel 45 
Inner Basin at Harbor Island 45 
Channel to Port Aransas 12 
Port Aransas Turning Basin 12 
Anchorage Basin at Port Aransas 12 
Inner Basin to Mile 8.5 45 
Mile 8.5 to LaQuinta Junction 45 
LaQuinta Junction to Corpus Christi 
Turning Basin 45 
Corpus Christi Turning Basin 45 
Industrial Canal 45 
Avery Point Turning Basin 45 
Channel to Chemical Turning Basin 45 
Chemical Turning Basin 45 
Tule Lake Channel 45 
Tule Lake Turning Basin 45 
Viola Channel 45 
Viola Turning Basin 45 
Channel to La Quinta 45 
La Quinta Turning Basin 45 
Turning Point at La Quinta 
Channel Junction 45 
Jewel Fulton Canal 12 
Jewel Fulton Turning Basin 12 
Mooring Area at Ingleside: 
Mooring Area Ia) 45 
Mooring Area b) 45 
5. Freeport Harbor, Outer Bar Channel 
Texas Jetty Channel 
Quintana Turning Basin 
Channel to Brazosport Turning 
Basin 
47 
45 
45 
45 
300 
200 
200 
300 
500 
1,000 
200 
200 
1,000 
370-305 
370-305 
370 
270 
100 
100 
100 
700 
600-730 
730-1,720 
100-150 
200-4002 
300-400 
600 
600 
400-600 
800 
400 
975 
400 
1,2005 
300 
1,200 
300-350 
1,200 
300-400 
1,200 
1,2503 
100 
200 
150 
150 
400 
400 
7504 
400 
38-36 
36 
36 
36 
36 
36 
36 
36 
36 
15 
15 
15 
15 
15 
10 
47 
45 
45 
12 
12 
12 
45 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
40 
12 
12 
38 
36 
36 
300 
200 
200 
200 
500 
1,000 
200 
200 
1,000 
370-305 
370-305 
370 
265 
100 
100 
700 
600 
Irregular 
100 
2002 
300-400 
600 
400 
400 
1,000 
400 
1,000 
350 
1,0505 
200 
900 
200-250 
700-900 
300-400 
1,200 
100 
200 
300 
200 
200-350 
2.5 
2.1 
9.6 
3.2 
1.3 
2,670 0.5 
1.4 
0.8 
1,300 0.2 
1,470 0.3 
1,200 0.2 
1,470 0.3 
1,230 0.2 
770 0.1 
5.7 
1.8 
1.0 
1,550 -
0.1 
200 - 
900 0.2 
8.5 
3.6 
8.6 
5,423 1.0 
1.1 
1,150 0.2 
0.6 
1,690 0.3 
3.1 
1,000 0.2 
1.8 
1,000 0.2 
5.6 
800 0.1 
- 0.8 
400 0.1 
- 3.0 
- 0.8 
- 1.2 
01 
AI 
0
0'T
b
C
C
n031 
x1 
tM 
0: 
'T
LO 
z
z
Cl) 
V 
VJ 
TABLE 15-F CHANNEL DIMENSIONS

Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
Freeport Harbor, 
Texas (Cont'd) 
Galveston Harbor 
and Channel, 
Texas 
Houston Ship 
Channel, Texas 
Matagorda Ship 
Channel, Texas 
Brazosport Turning Basin 
Channel to Upper Turning Basin 
Upper Turning Basin 
Channel to Stauffer Chemical Plant 
Stauffer Turning Basin 
Brazos Harbor Channel 
Brazos Harbor Turning Basin 
Entrance Channel 
Outer Bar Channel 
Inner Bar Channel 
Anchorage Basin 
Bolivar Roads Channel 
Galveston Channel: 
Bolivar Roads Channel 
to 43rd St. 
43rd St. to 51st St. 7 
51st St. to 57th St. 7 
Bolivar Roads to Morgan Point 
Morgan Point to Bogav Bayou 
Boggy Bayou to Greens Bayou 
Greens Bayou to Sims Bayou 
Hunting Bayou Turning Point 
Clinton Island Turning Basin 
Sims Bayou to Southern Pacific Slip 
Southern Pacific Slip to Houston 
Turning Basin 4 
Houston Turning Basin 
Upper Turning Basin 
Brady Island Channel 
Barbour Terminal Channel 
Turning Basin 
Five-Mile Cut Channel 
Light-Draft Channel: 
Upper Turning Basin to Jensen Drive 
Turkey Bend Channel 
Jensen Drive to White Oak Bayou 
Greens Bayou Channel: 
Mile O to Mile 0.36 
Mile 0.36 to Mile 1.57 
Mile 1.57 to Mile 2.737 
Outer Bar and Jetty Channel 
Channel to Point Comfort 
Approach Channel to Turning Basin 
Turning Basin 
Channel to Port Lavaca 
Lynn Bayou Turning Basin 
Channel to Harbor of Refuge 
North-South Basin 
East-West Basin 
Channel to Red Bluff 
6. 
8. 
01 
01 
c01 
9. 
667 
600 
500 
675 
1,375 
1,592 
3,100 
1,000 
1,000 
45 
45 
45 
30 
30 
36 
36 
42 
42 
40 
36 
40 
40 
32 
32 
40 
40 
40 
40 
40 
40 
40 
0 & 366 
36 
36 
10 
16 
16
8 
10 
10 
10 
36 
15 
12 
38 
36 
36 
36 
12 
12 
12 
12 
12
6 
0.1 
1.4 
0.1 
1.1 
0.1 
0.5 
0.1 
4.7 
1.7 
3.2 
1.81 
1.0 
3.9 
26.2 
12.8 
2.4 
5.3 
0.6 
2.9 
0.6 
0.2 
0.9 
1.5 
0.2 
1.9 
1,0004 
375 
1,200 4 
200 
500 
200 
750 4 
800 
800 
800 
2,8751 
800 
1,125 
1,200 
1,000 
400 
400 
300 
300 
900-1,00015 
80015 
300 
300 
400-1,000 
150 
60 
100 
1,100 
125 
60 
60 
60 
175 
100 
100 
300 
300-2008 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
36 
36 
36 
30 
25 
30 
30 
42 
42 
40 
36 
40 
36 
40 
40 
40 
40 
40 
40 
40 
366 
36 
36 
10 
16 
16
8 
10 
10 
36 
15 
38 
36 
36 
36 
12 
12 
12 
12 
12
6 
744-800 
350-375 
600 
200 
500 
200 
525-675 
800 
800 
800 
2,875 
800 
1,200 
400 
400 
300 
300 
948-1,00015 
965-1,07015 
300 
300 
400-1,000 
150 
60 
100 
1,100 
125 
60 
60 
175 
100 
300 
300-2008 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
0
zV
ITJ 
yC
c3 
- 4.1 
- 0.8 
0.3 
1.3 
3.2 
20.9 
1.1 
0.2 
4.1 
0.1 
1.9 
0.3 
0.3 
20.2 
1,000 
532 
1,682 
1,750 
TABLE 15-F (Continued) CHANNEL DIMENSIONS

Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
10. Sabine-Neches 
Waterway, Texas 
N
0W1o 
11. Texas City 
Channel, Texas 
Sabine Bank Channel 
Sabine Pass Outer Bar Channel 
Sabine Pass Jetty Channel 
Sabine Pass Anchorage Basin 
Sabine Pass Channel 
Port Arthur Canal 
Entrance to Port Arthur Turning 
Basins 
Port Arthur East Turning Basin 
Port Arthur West Turning Basin 
Channel connecting Port Arthur 
West Turning Basin and 
Taylors Bayou Turning Basin 
Taylors Bayou Turning Basin 
Sabine-Neches Canal, Port Arthur 
Canal to Neches River 
Turning Point at Mile 19.5 
Neches River, Mouth to 
Maneuvering Area at 
Beaumont Turning Basin 
Turning Point, Mile 31.1 
Turning Point, Mile 36.6 
Turning Point, Mile 40.3 
Channel Extension, Mile 40.3 
Maneuvering Area at Beaumont 
Turning Basin 
Beaumont Turning Basin 
Beaumont Turning Basin Extension 
Beaumont Turning Basin 
Extension to End of Project 
Channel Vicinity 
Bethlehem Steel Company 
Sabine-Neches Canal, Neches River 
to Sabine River 
Sabine River Channel, Mouth to 
Foot of Green Ave. 
Orange Turning Basin 
Orange Municipal Slip 
Old Channel Around Harbor Island 
Channel to Echo 9 
Adams Bayou 
Cow Bayou 
Orangefield Turning Basin 
Texas City Channel 
Turning Basin 
Industrial Barge Canal :11 
Channel from Texas City Turning 
Basin to Mile 1.7 
Turning Basin 
42 
42 
40 
40 
40 
40 
40 
40 
40 
800 
800 
800-500 
1,500 
500 
500 
275-678 
420 
600 
40 200-250 
40 150-1,000 
40 
40 
40 
40 
40 
40 
36 
40 
34 
34 
30 
30 
30 
30 
30 
25 
12 
12 
13 
13 
40 
40 
400 
900 4 
400 
1,0004 
1,0004 
1,000 4 
350 
Irregular 
500 
350 
200 
200 
200 
Irregular 
200 
150-200 
125 
100 
100 
300 
400 
1,000-1,200 
42 
42 
40 
40 
40 
40 
40 
40 
40 
800 
800 
800-500 
1,500 
500 
500 
275-678 
370-547 
350-550 
40 200-250 
40 90-1,233 
40 
40 
40 
40 
40 
40 
36 
40 
34 
34 
30 
30 
30 
30 
30 
25 
12 
13 
13 
40 
40 
400 
9004 
400 
1,000 
1,000 
1,300 
350 
Irregular 
160-535 
300 
200 
200 
200 
Irregular 
150-200 
150-200 
100 
100 
300 
400 
1,000 
3,000 
14.7 
3.4 
4.1 
5.6 
- 6.2 
- 0.3 
1,765 0.3 
1,610 0.3 
O 
- 0.6 
3,470 0.7 
- 11.2 12 3 
-m 
t' 
700 
930 
1,530 
1,256 
18.3 
12 
12 
12 
0.2 
1,300 0.2 
1,500 0.3 
- 0.4 
1 
0
PTj 
z0H 
z
tx 
tM 
v 
- 0.7 
- 4.4 
- 9.5 .1 
550 0.3 o' 
2,435 
- 10 
500 
4,253 
0.5 
2.4 
1.7 
7.0 
0.1 
6.8 
0.8 
40 300-400 
40 1,000 
TABLE 15-F (Continued) CHANNEL DIMENSIONS

TABLE 15-F (Continued) 
Adopted Project Dimensions Improved Project Dimensions 
See Depth in Feet Bottom Depth in Feet Bottom 
Section (Below Mean Width (Below Mean Width Length 
in Text Project Section of Waterway Low Tide) (Feet) Low Tide) (Feet) Feet Miles 
12. Trinity River Multiple Purpose Channel to 
and Tributaries, Fort Worth 13 12 200 - - - - 
Texas Channel to Liberty14 9 150 6 100 - 41.4 
Anahuac Channel 6 100 6 100 - 5.8 
1 Average. 
2 Includes 100-foot channel width. 
3 Includes 450-foot channel to Corpus Christi. 
4 Diameter. 
5 Includes 350-foot channel width. 
6 Deepening Houston Ship Channel to 40 feet from Southern 
Pacific Slip to Brady Island and construction of 
26,000 lineal feet of pile dike in upper Galveston Bay 
are in inactive category. 
7 Inactive. 
01 8 300-foot width through Matagorda Peninsula. 
9 Inactive category. 
10 Upper 0.7-mile is in Inactive category. 
11 Channel dredged 34 feet deep by 250-200 feet wide by 
9,908 feet long and basin 34 feet deep by 1,000 feet 
wide by 1,150 feet long by local interests. 
12 Included in channel length. 
13 Not constructed. 
14 9-foot x 150-foot channel completed from Houston Ship 
Channel to a point one mile below Anahuac, a distance of 
23.2 miles. Upper end not connected to river channel to 
prevent salt water intrusion into river. 
15 Includes 300-foot channel width. 
r
LTJ 
0
zV
C
M 
I 
u 
T
y 
CHANNEL DIMENSIONS

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS PROVIDED FOR IN TRIBUTARY CHANNELS 
(See Section 7 of Text) 
TABLE 15-G 
Authorized Project Dimensions Improved Project Dimensions 
Tributary Channel 
Depth 
(Feet Below 
Mean 
Low Tide) 
Length 
Miles Feet 
Offats Bayou 
Main Channel 
West Wye 
Chocolate Bayou Channel 
12-Foot Channel via East 
Turnout 2 
West Turnout 
9-Foot Channel 
Turning Basin 
San Bernard River Channel 5 
Colorado River Channel 6 
Turning Basin 
Silting Basin 
7 
Mouth of Colorado River 
Navigation Channel, GIWW 
to Gulf 
Turning basin at Matagorda 
8 
Channel to Palacios 
Turning Basin No. 1 
Turning Basin No. 2 
Connecting Channel 
Channel to Barroom Bay 
Channel to Victoria: 
Main Channel via East 
Turnout 
Turning Basin 
West Turnout Channel 
Channel to Seadrift via South 
Turnout 
Turning Basin 
North Turnout from Channel to Victoria 
Harbor of Refuge at Seadrift 9 
Channel 
Basin 
Channel to Rockport 
Turning Basin 
Channel to Aransas Pass 
Turning Basin 
Channel to Conn Brown Harbor 
Conn Brown Harbor 
10 
Channel to Port Mansfield 
Entrance Channel 
Approach Channel to Hopper 
Dredge Turning Basin 
Hopper Dredge Turning Basin 
Channel Across Padre Island 
and Laguna Madre 
Turnout Channels, East Side of 
Main Channel, GIWW 
North Turnout 
South Turnout 
Channel West Side of Main Channel, 
GIWW, to P.T. of Turnout Channels 
Turnout Channels, West Side of 
Main Channel, GIWW: 
North Turnout 
South Turnout 
12 
12 
12 
12
99 
9
999 
15-12 
12 
12 
12 
12 
12
6
999 
99 
9
9
9
99 
12 
12 
12 
12 
16 
16 
16 
14 
12 
12 
14 
12 
12 
125 
125 
125 
125 
100 
600 
100 
100 
400 
150 
200-100 
350 
125 
200 
300 
150-480 
60 
100 
600 (avg) 
100 
100 
250 
100 
100 
200 
200 
475 
125 
300 
125 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
12 
12 
10 
10
9
999 
12 
12 
12 
12
9
99 
999 
99 
12 
12 
12 
12 
2613 
2613 
2613 
14 
12 
12 
14 
12 
12 
125 
125 
100 
125 
2.3 
0.4 
8.2 
0.8 
100 26.0 
100 15.5 
400 0.1 
150 1.0 
125 
200 
300 
130-400 
16.1 
0.1 
0.2 
0.1 
100 34.8 
500 (avg) 0.1 
100 0.8 
100 
200 
100 
2.0 
0.5 
2,200 
500 
635 
1,130 
800 (avg) 
230 
200 2.1 - 
342 (avg) 0.2 1,255 
125 6.1 - 
300 0.4 2,212 
125 0.2 - 
300 0.3 1,800 
250 
100 
300 
100 
100 
100 
100 
200 
200 
0.8 
0.4 - 
0.1 300 
7.7 - 
0.6 - 
0.6 - 
0.3 - 
0.6 - 
0.6 
15-38 
Depth 
(Feet Below 
Mean 
Low Tide) 
Bottom 
Width 
(Feet) 
Bottom 
Width 
(Feet)

GALVESTON, TEX., DIST. 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS PROVIDED FOR IN TRIBUTARY CHANNELS 
TABLE 15-G (Continued) 
(See Section 7 of Text) 
Authorized Project Dimensions Improved Project Dimensions 
Depth Depth 
Tributary Channel (Feet Below Bottom (Feet Below Bottom 
Mean Width Mean Width Length 
Low Tide) (Feet) Low Tide) (Feet) Miles Feet 
Channel from P.T. of Turnout 
Channels to Approach Channel 
to Main Turning Basin 14 125 14 125 0.6 
Approach Channel to Main Turning 
Basin 14 200 14 200 0.3 - 
Main Turning Basin 14 400 14 400 0.2 1,250 
Turning Basin Extension 14 1,000 14 1,000 0.1 580 
Small Craft Basin 8 160 8 160 0.2 860 
Shrimp Basin 12 350 12 350 0.3 1,450 
Channel to Harlingen via South Turnout 
From Main Channel, GIWW 12 125 12 12511 25.812 
Turning Basin Near Rio Hondo 12 400 12 400 0.1 500 
North Turnout from Main Channel 12 200 12 200 0.7 - 
Port Isabel Side Channels 
Main Channel 12 125 12 125-90 0.6 - 
Main Channel 12 233-60 12 233-60 0.4 - 
South Leg 12 125 12 125 0.2 - 
Port Isabel Small Boat Harbor 
Entrance Channel 7 75 7 75 1.4 - 
Harbor Channel 6 50 6 50 0.3 - 
Boat Basin 6 Variable 6 7 2-501 0.2 1,308 
1 Includes the construction of a salt water barrier at 
mile 16.9. 
2 Constructed 10 feet deep by 100 feet wide by local 
interests. East turnout channel constructed 150 feet 
wide. 
3 Constructed by local interests. 
4 Authorized to mile 13.4. 
5 Authorized to mile 31 above mouth (channel mile 29.41). 
Upper 3.4 miles are in inactive category. 
6 Includes a discharge channel from Matagorda, Texas, to 
the gulf which was dredged by local interests in 1939. 
(Maintenance will be discontinued upon completion of 
improvements authorized by R&H Act of 1968.) 
7 Authorized by R&H Act of 1968. Also provides for a 
dam across the present discharge channel, a new 250- 
foot wide by 20 to 23-foot deep discharge channel into 
Matagorda Bay, and a 15-foot by 200-foot wide entrance 
channel with parallel jetties from the gulf shoreline into 
the Gulf of Mexico. East jetty to be 3,500 feet long and 
west jetty 2,900 feet long. 
8 Includes two protective breakwaters at entrance to turning 
basins. 
9 Inactive. 
10 Also provides for two stone jetties at the gulf entrance 
about 1,000 feet apart. (North jetty constructed 2,300 
feet long and south jetty constructed 2,270 feet long.) 
11 South turnout is 200 feet wide. 
12 Authorized to mile 31. Mile 25.8 to mile 31 is in inactive 
category. 
13 Dredged 26 feet deep to accommodate U.S. Hopper 
Dredge A. MACKENZIE. 
15-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975

DREDGING OPERATIONS

TABLE 15-H


Brazos Island
Harbor, Texas


Entrance Channel (U.S. hopper dredge Davidson)

Jul 1 - Aug 31, 1974

160,361

231,189

Entrance Channel (U.S. hopper dredge McFarland)

Mar 26 - Apr 9, 1975

303,438

186,240


Brownsville Channel

Jul 1 - Aug 23, 1974

1,025,111

397,395

Corpus Christi Ship Channel, Texas (Maintenance)

Mile 8.5 to Laa Quinta Junction w/new work

Jul 1, 1974 - Jun 30, 1975

924,224

460,126

Corpus Christi Ship Channel, Texas (New Work)

Outer Bar and Jetty Channel (U.S. hopper dredge McFarland)

Jan 15 - Feb 28 and Mar 14- 25, 1975

2,198,579

959,063

Freeport Harbor, Texas 

Outer Bar and Jetty Channel (U.S. hopper dredge McFarland)

Nov 20 - Dec 27, 1974

1,010,361

492,100

Inside channels and Basins

April 11 - Jun 30, 1975

547,003

333,020


Galveston Harbor
and Channel,
Texas


Entrance, Inner Bar and Outer Bar Channels (U.S. hopper dredge McFarland)

Jul 8 - Aug 14, Aug 27 - Sep 25, 1974 and May 7 - 13, 1975

1,702,292

942,132

Gulf Intracoastal
Waterway between
Apalachee Bay,
Fla., and Mexican
Border (Galveston
District)

Port Mansfield Entrance Channel (U.S. hopper dredge Davidson)

Aug 5 to 15, 1974 and  Aug 21 - Sep 12, 1974

81,216

144,608

High Island to Port Bolivar

Jul 1 - Oct 12, 1974

1,405,960

508,265

Channel to Port Mansfield

Jul 1 - Sep 15, 1974

728,025

307,100

Arroyo Colorado to mud Flats and Channel to Port Mansfield

Jun 27 - 30, 1975


357,773

147,510


Freeport to San Bernard River

Jun 14 - 30, 1975

433,548

248,770

Colorado River to Matagorda Bay


Jul 1 -13, 1974 

413,835

69,219

San Antonio Bay to Aransas Bay

Jul 1 - Aug 18, 1974

425,222

184,146

Colorado River Channel, Mile 6.3 to 15.4 

Apr 30 - Jun 30, 1975 

601,979

462,200

Port Isabel to Arroyo Colorado and Channel to Harlingen

Jun 3- 30, 1975
 
354,628

249,020

Brazos River Crossing and Vicnity

Jan 4 - Feb 21, 1975

442,404

184,217


North Deer Island to Bastrop Bayou

Jul 1, 1974 - Apr 23, 1975

2,111,196

625,983

Corpus Christi
Bay to Mud Flats

Jul 1 - Nov 15, 1974

1,328,594

321,389

Houston Ship Channel, Texas

Morgan Point to Carpenter Bayou

Apr 8 - Jun 30, 1975

2,467,573

1,579,000


Buoy 56 to Buoy
65 and Five Mile
Cut Channel

Jul 1 - Aug 12, 1974

493,831

235,355




GALVESTON, TEX., DIST.

TABLE 15-H (Continued)


Houston Ship Channel, Texas


Sims Bayou to Houston Turning Basin and Light Draft Channels

June 14 - 30, 1975 

138,385

233,000


Matagorda Ship
Channel, Texas

Entrance Channel (U.S. hopper dredge McFarland)

Dec 28, 1974 - Jan 14, 1975 and Apr 9 - May 6, 1975

1,463,473

638,360


Channel to Port Lavaca and Harbor of Refuge

Oct 19 - Nov 15, 1974

1,204,173

251,343

Matagorda Penninsula to Point Comfort

Jul 1 - Aug 15, 1974

3,117,950

624,864

Sabine-Neches
Waterway,
Texas


Sabine Bank Channel
(U.S. hopper dredge
Essayons)



Nov 1, 1974 - Feb 12, 1975


4,667,000

1,884,577

Outer Bar and Jetty Channel (U.S. hopper dredge McFarland)

Aug 14 - 27, 1974 and Sep 25 - Nov 20, 1974

2,520,638

820,158

Middle Reach, Neches River Channel

Jul 1 - Aug 1, 1974

534,196

149,737

Sabine-Neches Cannal

Apr 1 - Jun 30, 1975

2,144,600

585,997



Texas City Channel, Texas

Texas City Channel
and Turning Basin


Aug 24, 1974 - Jan 2, 1975

3,258,398

978,835

Trinity River and Tributaries, Texas


Anahuac Channel

May 16 - Jun 22, 1975

169,487

123,220



TABLE 15-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
FLOOD PLAIN INFORMATION REPORTS 
COMPLETED THIS FISCAL YEAR 
(See Section 31 of Text) 
Location 
Flood Plain Information 
Report, Caney Creek, Tex. 
Flood Plain Information 
Report, Panther and Bear 
Branches, Tex. 
Requesting Agency 
Montgomery County 
Montgomery County 
Date Completed 1 
December, 1974 
December, 1974 
1 Month and year report was furnished to the requesting agency. 
15-42 
Federal Cost 
$ 59,962 
48,014 
- -

FORT WORTH, TEX., DISTRICT* 
District includes that portion of Texas south 
of Red River drainage basin exclusive of 
drainage basin of Rio Grande and its 
tributaries above and including Pecos River; 
exclusive of drainage basins of all short 
streams arising in coastal plain'of Texas and 
flowing into the Gulf of Mexico, including entire 
basins of Buffalo Bayou, San Jacinto, San 
Bernard, Lavaca, Navidad, Mission, and 
Arkansas Rivers; exclusive of lower basins of 
major streams flowing into the gulf as follows: 
Sabine River, Tex. and La., downstream from 
U.S. Highway 190 crossing at Bon Wier, Tex.; 
Neches River downstream from Town Bluff 
gaging station; Trinity River downstream from 
Texas State Highway 45 crossing at Riverside, 
Tex.; Brazos River downstream from confluence 
with Navasota River; Colorado River 
downstream from gaging station at Austin; 
Guadalupe River downstream from confluence 
with San Marcos River; San Antonio River 
downstream from confluence with Escondido 
Creek; Nueces River downstream from confluence 
with Frio and Atascosa Rivers; and exclusive 
of Agua Dulce, San Fernando, and 
Olmos Creek basins draining into Baffins Bay 
and coastal area south thereof to Rio Grande 
and east of western boundary of Starr County, 
Tex. District also includes that portion of 
western Louisiana in Sabine River drainage 
basin upstream from U.S. Highway 190 crossing 
at Bon Wier, Tex., and portion of eastern 
New Mexico included in drainage basins of 
Brazos and Colorado Rivers. 
IMPROVEMENTS 
Navigation 
1. Neches and Angelina Rivers, Tex. 
2. Town Bluff Dam-B. A. Steinhagen 
Lake, Tex....................... 
3. Trinity River and Tributaries, Tex. 
4. Trinity River Project, Tex. (With 
and Without Navigation) ........... 
5. Other authorized navigation 
projects ........................... 
Flood Control 
6. Abilene Channel Improvement, Tex. 
7. Aquilla Lake, Tex. ................ 
8. Aubrey Lake, Tex. ................ 
9. Bardwell Lake, Tex............... 
10. Belton Lake, Tex. ................. 
11. Benbrook Lake, Tex............... 
12. Big Fossil Creek, Tex. ............ 
13. Brazos River Basin, Tex. ......... 
14. Canyon Lake, Tex. ................ 
15. Carl L. Estes Dam and Lake, Tex. 
16. Duck Creek Channel Improvement, 
Tex. ............................ 
17. Elm Fork Floodway, Tex. ........ 
18. Fort Worth Floodway (Clear Fork) 
Tex. ............................. 
Page 
16-2 
16-2 
16-2 
16-3 
16-5 
16-5 
16-6 
16-6 
16-6 
16-6 
16-7 
16-7 
16-7 
16-8 
16-8 
16-8 
16-9 
16-9 
Flood Control (cont.) 
19. Fort Worth Floodway (West Fork) 
Tex. ............................ 
20. Grapevine Lake, Tex ............ 
21. Greenville, Tex. ................... 
22. Guadalupe and San Antonio Rivers, 
Tex. ............................ 
23. Hords Creek Lake, Tex. .......... 
24. Lake Brownwood Modification, Tex. 
25. Lakeview Lake, Tex. ............. 
26. Lewisville Dam, Tex.............. 
27. Lavon Lake, Tex.................. 
28. Lavon Lake Modification and East 
Fork Channel Improvement, Tex. 
29. Millican Lake, Tex. ............... 
30. Navarro Mills Lake, Tex. ......... 
31. 0. C. Fisher Dam and Lake, Tex... 
32. Proctor Lake, Tex. ................ 
33. Rutledge Hollow Creek, Tex. ...... 
34. Sabine River Basin, Tex.......... 
35. San Antonio Channel Improvement, 
Tex. ............................ 
36. San Gabriel River, Tex. ........... 
37. Somerville Lake, Tex. ............. 
38. Stillhouse Hollow Dam, Tex....... 
39. Three Rivers, Tex. ................ 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text 
and also appear at the end of this chapter. 
16-1 
Page 
16-9 
16-9 
16-10 
16-10 
16-10 
16-10 
16-11 
16-11 
16-12 
16-12 
16-13 
16-13 
16-13 
16-13 
16-14 
16-14 
16-14 
16-14 
16-15 
16-15 
16-16

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (cont.) 
40. Trinity River and Tributaries, Tex. 
41. Waco Lake, Tex. .............. 
42. Inspection of completed flood 
control projects .................. 
43. Scheduling flood control reservoir 
operations ....................... 
44. Other authorized flood control 
projects ......................... 
45. Flood control work under special 
authorization .................... 
Page 
16-16 
16-16 
16-17 
16-17 
Page 
Multiple-Purpose Projects 
Including Power 
46. Sam Rayburn Dam and Reservoir, 
Tex. ............................ 16-17 
47. Whitney Lake, Tex ............... 16-18 
General Investigations 
16-17 48. Surveys ......................... 
49. Collection and study of basic data 
16-17 50. Research and development ........ 
Navigation 
1. NECHES AND ANGELINA RIVERS, 
TEX. 
Location. Neches River rises 60 miles 
southeast of Dallas, Tex., and flows generally 
southeast 416 miles to Sabine Lake 4 miles east 
of Port Arthur, Tex. Angelina River flows 
southeast 200 miles to its confluence with 
Neches River 126 miles above its mouth. 
Authorized features are located as follows: 
Rockland Dam on Neches River about 3 miles 
west of Rockland, Tex.; Sam Rayburn Dam on 
Angelina River about 10 miles northwest of 
Jasper, Tex,; Dam A on Neches River about 4 
miles west of Horger, Tex,; Town Bluff Dam 
on Neches River about one-half mile north of 
Town Bluff, Tex. (See Geological Survey base 
map, Northeast Texas, scale 1:500,000.) 
Existing project. Provides for dams and 
lakes, at Rockland and Sam Rayburn damsites 
on Neches and Angelina Rivers, respectively, 
which will give a large measure of flood 
protection to agricultural lands in lower river 
valley and to city of Beaumont, Tex., reduce 
hazards to navigation resulting from floods, 
and provide a regulated flow in lower river to 
supply municipal, agricultural, and industrial 
demands. In addition, these proposed projects 
will permit development of a large amount of 
firm power and afford opportunities for recreation. 
Plan also provides for construction of 
Dam A, on Neches River below Rockland Dam, 
for development of power and Town Bluff 
Dam, below confluence of Angelina and Neches 
Rivers, to regulate daily fluctuations in discharge 
from turbines in upper projects and to 
develop a limited amount of power. Construction 
of Rockland and Dam A Lakes and power 
facilities at Town Bluff Dam-B. A. 
Steinhagen Lake is to be deferred until 
justified by future conditions. Estimated cost 
for new work, revised in 1972 for Town Bluff 
Dam-B. A. Steinhagen Lake and Sam 
Rayburn Dam and Reservoir and in 1954 for 
Dam A and Rockland Lakes, is $128,091,000 
including $5 million non-Federal cost. (See 
Table 16-D for flood control works included in 
comprehensive plan.) 
2. TOWN BLUFF DAM--B. A. 
STEINHAGEN LAKE, TEX. 
Location. Dam is on Neches River about 12.4 
miles below mouth of Angelina River, one-half 
mile north of Town Bluff, Tex., and 93 river 
miles north of Beaumont, Tex. 
Existing project. For description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Estimated cost of project 
is $9,888,000, including $2 million contributed 
by local interests. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Regular Funds: Routine operation and 
maintenance continued. 
Condition at end of fiscal year. Construction 
started March 1947 and project was ready for 
beneficial use in April 1951. Recreation 
facilities under Code 710 remain. 
3. TRINITY RIVER AND 
TRIBUTARIES, TEX. 
Location. The river basin lies in the eastern 
half of the State of Texas and extends about 
360 miles generally along a northwestsoutheast 
axis, from Archer County on the 
northwest to Chambers County and the Trinity 
Bay on the Gulf of Mexico on the Southeast. 
Maximum width of the basin, in the 
headwaters, is about 100 miles. All or part of 
36 counties are included in the basin. 
Existing project. Projects authorized by the 
River and Harbor Act of 1965 (H. Doc. 276, 
89th Cong., 1st Sess.) consist of the Trinity 
River Project (Multiple-Purpose Channel, Advance 
Participation High Level Bridges, 
16-2 
16-18 
16-18 
16-18

FORT WORTH, TEX., DISTRICT 
Tennessee Colony Lake, Dallas Floodway Extension, 
& West Fort Floodway), Aubrey Lake, 
Lakeview Lake, Roanoke Lake, Duck Creek 
Channel Improvement and Elm Fork 
Floodway. Estimated Federal cost of these improvements 
is $2,321,120,000, including $1,- 
000,000 for U.S. Coast Guard aids to navigation. 
Non-Federal cost for land acquisition and 
relocations for local protection projects is $112,- 
300,000. Estimated total cost of improvements 
is $2,433,420,000. 
ROANOKE LAKE: Damsite at river mile 
32.0 on Denton Creek, a tributary to Elm Fork 
of Trinity River in Denton County and about 
one-half mile northwest of Roanoke, Texas. An 
earthfill dam 15,200 feet long including a 328 
foot concrete ogee type spillway, with maximum 
height of 97 feet above streambed, which 
controls 604 square miles of drainage area. The 
lake provides a total storage capacity of 249,- 
900 acre-feet, of which 223,700 are for flood 
control and 26,200 for sediment reserve. Estimated 
cost is $62,300,000. Local interests are 
required to reimburse the Federal Government 
for cost allocated to water supply storage, 
presently estimated at $50,340,000, one-half of 
the separable cost allotted to recreation at $5,- 
980,000 exclusive of interest and future recreation. 
Separate information is furnished on the 
Trinity River Project, Aubrey Lake, Lakeview 
Lake, Elm Fork Floodway and Duck Creek 
Channel Improvement elsewhere in this 
chapter. 
4. TRINITY RIVER PROJECT, TEX. 
(WITH AND WITHOUT 
NAVIGATION) 
WITH NAVIGATION 
Location. The Trinity River basin lies in the 
eastern half of the State of Texas. It extends 
about 360 miles, generally along a northwestsoutheast 
axis, from Archer County on the 
northwest to Chambers County and Trinity 
Bay on the Gulf of Mexico on the southeast. 
Maximum width of the basin, in the 
headwaters, is about 100 miles. Eighteen counties 
are included in the project. The Tennessee 
Colony dam site is located at river mile 339.2 
on the Trinity River about 16 miles west of 
Palestine, Texas. The reservoir extends into 
Freestone, Anderson, Henderson and Navarro 
Counties. Dallas Floodway Extension is located 
on the Trinity River in the city of Dallas, 
Dallas County, Texas. West Fork Floodway is 
located on the Trinity River and extends 
through the urban areas of the cities of Fort 
Worth, Arlington, Grand Prairie, Irving and 
Dallas, and includes Dallas and Tarrant Counties, 
Texas. 
Existing project. The project was authorized 
by the River and Harbor Act of 1965 (H. Doc. 
276, 89th Cong., 1st Sess.) Presently the estimated 
cost of the improvements is $1,941,- 
320,000, including $1,000,000 for the U.S. 
Coast Guard aids to navigation, $71,000,000 
non-Federal cost for land acquisition and 
relocation required for the local protection 
features, and $8,320,000 for Advance Participation 
on High Level Bridges. 
MULTIPLE-PURPOSE CHANNEL: The 
navigation channel will have a minimum width 
of 200 feet with a minimum depth of 12 feet 
and will extend from the Houston ship channel 
in Galveston Bay a distance of 362.8 miles to 
the 400 foot square turning basins in Fort 
Worth. Nineteen locks and fifteen navigation 
dams, excluding the Wallisville lock and dam 
which was authorized separately. Sixteen locks 
from Wallisville Lake to and including the first 
lock above Dallas will be 84 feet wide by 600 
feet long with the last three locks between 
Dallas and Fort Worth being 84 feet wide by 
400 feet long. Relocation of all utilities, 
highways, railroads and bridges. Relocation or 
alterations of bridges will provide a minimum 
of 300 feet between the piers and a minimum 
vertical clearance of 52 feet above the water 
surface. Estimated Federal cost of the improvements 
is $1,411,320,000, including $8,- 
320,000 for the Advance Participation on High 
Level Bridges. 
TENNESSEE COLONY LAKE: The plan 
of improvement provides for the construction of 
an earthfilled dam with a maximum height of 
113 feet above the streambed and a total length 
of 29,500 feet, including a 520 foot controlled 
concrete ogee type spillway, Navigation Lock 
10-B located in the right abutment of the dam 
and Lock and Dam 11 in the upper portion of 
the reservoir. The reservoir will have a total 
controlled storage of 3,366,800 acre-feet and a 
water surface area of 119,500 acres at the top 
of the flood control pool and 73,540 acres at the 
top of the conservation pool. The total storage 
includes 2,144,300 acre-feet for flood control, 
1,032,500 acre-feet for conservation and 190,- 
000 acre-feet for sediment reserve. Estimated 
Federal cost of the improvement is $408,000,- 
000. 
DALLAS FLOODWAY EXTENSION: The 
plan of improvement provides for enlargement 
and realignment of the Trinity River from the 
existing Dallas Floodway downstream approximately 
8.6 miles. The enlargement and 
realignment of three tributary channels for a 
total distance of about 10.5 miles through the 
16-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
leveed areas. Construction of a parallel levee 
system through the lower areas consisting of 
about 10.2 miles along the left bank, 14.6 miles 
along the right bank of the main and diversion 
channels with a minimum distance of 2,000 
feet between levees along the main channel. 
Relocation of all utilities, alteration of bridges 
and the acquisition of rights-of-way. The estimated 
Federal cost is $23,000,000 and estimated 
non-Federal cost is $19,000,000 for a 
total estimated cost of $42,000,000 for the improvement. 
WEST FORK FLOODWAY: The plan of improvement 
provides for realignment and 
enlargement along the West Fork of the Trinity 
River from the mouth of the West Fork in 
the existing Dallas Floodway upstream to the 
existing Fort Worth Floodway, a distance of 31 
miles. The enlargement and realignment of approximately 
16.7 miles of tributary channels 
through the leveed areas. The construction of a 
parallel levee system through the low areas 
consisting of about 34 miles of levee along the 
left bank and 9.1 miles along the right bank of 
the main and tributary channels with the distance 
varying from 1,000 feet to 3,000 feet 
between levees along the main channel. 
Relocations of all utilities, alteration of bridges 
and acquisition of rights-of-way. Estimated 
Federal cost is $27,000,000 and the estimated 
non-Federal cost is $52,000,000 for a total estimated 
cost of $79,000,000 for the improvement. 
Local cooperation. Local interests are required 
to reimburse the Federal Government 
as follows: 1. With respect to the Multiple- 
Purpose Channel, for navigation and flood control, 
the share apportioned to navigation of the 
actual Federal cost for all lands, easement and 
rights-of-way required for construction and 
maintenance of the project and aids to navigation; 
a proportionate share of the cost of bridge 
alteration over existing channels in accordance 
with the principles of Section 6 of the Bridge 
Alterations Act (Truman-Hobbs) of 21 June 
1940 as amended; the share apportioned to 
navigation of the actual Federal cost for 
alterations of sewer, water supply, drainage, 
pipelines and other utility facilities; and onehalf 
of the separable cost allocated to recreation 
and fish and wildlife enhancement. This 
reimbursement is presently estimated at $100,- 
731,000 for navigation and $7,314,000 for 
recreation (excluding future recreation 
facilities), and $14,211,000 for flood control for 
a total of $122,256,000 exclusive of interest. 2. 
With respect to Tennessee Colony Lake for cost 
allocated to water supply storage and one-half 
of the separable cost allotted to recreation and 
fish and wildlife enhancement. This reimbursement 
is presently estimated at $81,183,000 for 
water supply and $13,510,000 for recreation 
(excluding future recreation facilities), for a 
total cost of $94,693,000, exclusive of interest. 
3. With respect to the local protection projects, 
local interests will provide without cost to the 
United States all lands, easements and rightsof-
way necessary for construction, maintenance 
and operation of the project; relocation of all 
buildings and utilities, bridges (except 
railroad), sewers, pipelines and any existing 
improvements. 4. Local interests will also 
maintain and operate the local protection projects 
after their completion; and share the annual 
operation and maintenance cost allocated 
for Navigation, Tennessee Colony. 
WITHOUT NAVIGATION 
In the FY 1974 Appropriation Act, Congress 
recommended funds to continue planning of the 
flood control, water supply, and recreational 
aspects of the project. Congress did not feel 
that funds should be recommended for additional 
navigation aspects of the project in 
view of the results of the recent referendum. 
Eight counties are included in the project. The 
Tennessee Colony dam site is located at river 
mile 341.7 on the Trinity River about 24 miles 
west of Palestine, Texas. The lake extends into 
Freestone, Anderson, Henderson, and Navarro 
Counties. Dallas Floodway Extension is located 
on the Trinity River in the city of Dallas, 
Dallas County, Texas. West Fork Floodway is 
located on the Trinity River and extends 
through the urban areas of the cities of Fort 
Worth, Arlington, Grand Prairie, Irving, and 
Dallas, and includes Dallas and Tarrant Counties, 
Texas. 
The current estimated cost of the improvements 
is $867,000,000, including $134,- 
000,000 non-Federal cost for land acquisition 
and relocations required for the local protection 
features. 
RESERVOIR REGULATION 
CHANNEL: The reservoir regulation channel 
will extend about 93 miles from Tennessee 
Colony Lake to Fort Worth, Texas, for flood 
control releases from upstream lakes. Estimated 
Federal cost of the improvements is 
$167,000,000. 
TENNESSEE COLONY LAKE: The plan 
of improvement provides for the construction of 
an earthfilled dam with a maximum height of 
129 feet above the streambed and a total length 
of 43,000 feet with a gated concrete spillway. 
The lake will have a total controlled storage of 
5,161,500 acre-feet and a water surface area of 
164,800 acres at the top of the flood control 
16-4

FORT WORTH, TEX., DISTRICT 
pool and 97,960 acres at the top of the conservation 
pool. The total storage includes 3,073,- 
600 acre-feet for flood control, 1,841,500 acrefeet 
for conservation and 246,400 acre-feet for 
sediment reserve. Estimated Federal cost of 
the improvement is $509,000,000. 
DALLAS FLOODWAY EXTENSION: The 
plan of improvement provides for enlargement 
and realignment of the Trinity River from the 
existing Dallas Floodway downstream approximately 
8.6 miles. The enlargement and 
realignment of three tributary channels for a 
total distance of about 10.5 miles through the 
leveed areas. Construction of a parallel levee 
system through the lower areas consisting of 
about 10.2 miles along the left bank, 14.6 miles 
along the right bank of the main and diversion 
channels with a minimum distance of 2,000 
feet between levees along the main channel. 
Relocation of all utilities, alteration of bridges 
and the acquisition of rights-of-way. The estimated 
Federal cost is $19,000,000 and estimated 
non-Federal cost is $27,000,000 for a 
total estimated cost of $46,000,000 for the improvement. 
WEST FORK FLOODWAY EXTENSION: 
The plan of improvement provides for 
realignment and enlargement along the West 
Fork of the Trinity River from the mouth of 
the West Fork in the existing Dallas Floodway 
upstream to the existing Fort Worth Floodway, 
a distance of 31 miles. The enlargement and 
realignment of approximately 16.7 miles of 
tributary channels through the leveed areas. 
The construction of a parallel levee system 
through the low areas consisting of about 34 
miles of levee along the left bank and 9.1 miles 
along the right bank of the main and tributary 
channels with the distance varying from 1,000 
feet to 3,000 feet between levees along the main 
channel. Relocations of all utilities, alteration 
of bridges and acquisition of rights-of-way. Estimated 
Federal cost is $38,000,000 and the estimated 
non-Federal cost is $107,000,000 for a 
total estimated cost of $145,000,000 for the improvement. 
Local cooperation. Local interests are required 
to reimburse the Federal Government 
as follows: 1. With respect to the Reservoir 
Regulation Channel, for recreation, one-half of 
the separable costs allocated to recreation and 
fish and wildlife enhancement. This reimbursement 
is presently estimated at $2,369,000 (excluding 
future recreation facilities) exclusive of 
interest. 2. With respect to Tennessee Colony 
Lake for costs allocated to water supply storage 
and one-half of the separable costs allocated to 
recreation and fish and wildlife enhancement. 
This reimbursement is presently estimated at 
$116,882,000 for water supply and $12,686,000 
for recreation (excluding future recreation 
facilities), for a total of $129,568,000 exclusive 
of interest. 3. With respect to the local protection 
projects, local interests will provide 
without cost to the United States (except for 
channel portions thereof) all lands, easements, 
and rights-of-way necessary for construction, 
maintenance, and operation of the projects, 
relocations (except railroads) and reimburse 
the Federal Government for one-half of the 
separable costs allocated to recreation and fish 
and wildlife enhancement. This reimbursement 
is presently estimated at $932,000 (excluding 
future recreation facilities) exclusive of interest. 
4. Local interests will also maintain and 
operate the local protection projects after their 
completion; and share the annual operation and 
maintenance cost allocated to water supply and 
recreation. The annual maintenance and operation 
is presently estimated at $2,229,000 for 
local interests. 
Operation and results during fiscal year. 
Regular funds, preconstruction planning continued. 
Advance Participation on High Level 
Bridges. Construction is continuing on Loop 12 
bridge, and construction was completed on Interstate 
Highway 45, Interstate Highway 635 
and State Highway 31 bridges. 
Condition at end of fiscal year. Preconstruction 
planning for the Trinity River Project is 
59 percent complete. Advance Participation on 
High Level Bridges is 93 percent complete. 
5. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 16-B. 
Flood Control 
6. ABILENE CHANNEL 
IMPROVEMENT, TEX. 
Location. On Elm Creek, a tributary of 
Brazos River, and its tributaries, Little Elm, 
Cat Claw, Cedar, Lytle, and Buttonwillow 
Creeks, in the urban areas of Abilene, Taylor 
County, Tex. 
Existing project. Provides for diversion dike, 
channel clearing and snagging, drainage structures, 
and channel improvements on Elm, Little 
Elm, Cat Claw, Cedar, Lytle, and Buttonwillow 
Creeks, together with necessary 
alterations to railroad and highway bridges, 
and urban and private company utilities. Project 
was authorized by Flood Control Act of 
1962. 
Local cooperation. Unsatisfactory assurances 
were received from local interest and 
reclassification of the project was made from 
16-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
the active category to the inactive category on 
20 July 1970. 
Operations and results during fiscal year. All 
planning was suspended as of 31 January 1970 
due to not receiving satisfactory assurances 
from local interests. 
Condition at end of fiscal year. Preconstruction 
planning is 95 percent complete. 
7. AQUILLA LAKE, TEX. 
Location. On Aquilla Creek in Hill County, 
Tex., with the dam at river mile 23.3, about 6.8 
miles southwest of Hillsboro, Tex., and about 
24.0 miles north of Waco, Tex. (See U.S. 
Geological Survey maps, Aquilla and Peoria, 
Tex., quadrangle scale 1:24,000.) 
Existing project. Plan of improvement 
provides for an earthfill dam 104.5 feet high 
and 11,800 feet long with an uncontrolled concrete 
spillway 1,200 feet long on the left abutment, 
creating a lake with a total storage 
capacity of 146,000 acre-feet, including 86,700 
acre-feet for flood control, 33,600 acre-feet for 
water supply, and 25,700 acre-feet for sediment 
reserve. Drainage area above damsite is 294 
square miles. Estimated cost is $47,800,000. 
Local cooperation. Section 301, Water Supply 
Act of 1958, Federal Water Project Recreation 
Act of 1965 and Section 221, Flood Control Act 
of 1970 apply. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. Preconstruction 
planning is complete. 
8. AUBREY LAKE, TEX. 
Location. Damsite is located at river mile 
60.0 on the Elm Fork of the Trinity River, 
Denton County, between Sanger and Aubrey, 
Texas and 30 miles upstream from Lewisville 
Dam. 
Existing project. The plan of improvement 
provides for construction of an earthfilled dam 
with a maximum height of 131 feet above the 
streambed, a length of 15,250 feet including an 
uncontrolled broadcrested spillway 100 feet 
long, controlling 682 square miles of drainage 
area. The lake will have a total controlled 
storage of 1,064,600 acre-feet, with a water surface 
area of 36,900 acres. The total storage includes 
260,800 acre-feet for flood control, 749,- 
200 acre-feet for water supply, and 54,600 acrefeet 
for sediment reserve. Estimated Federal 
cost of the project is $175,000,000. Project was 
authorized by River and Harbor Act of 1965 
(H. Doc. 276, 89th Cong., 1st Sess.). 
Local cooperation. The Water Supply Act of 
1958 as amended and the Federal Water Project 
Recreation Act of July 1965. Formal 
assurances received, 28 July 1969 for water 
supply and 31 July 1969 for recreation. 
Operations and results during fiscal year. 
Regular funds, new work: Preconstruction 
planning completed. 
Condition at end of fiscal year. Construction 
new start for fiscal year 1975, engineering and 
design is continued. 
9. BARDWELL LAKE, TEX. 
Location. Dam is on Waxahachie Creek, 5 
river miles upstream from its confluence with 
Chambers Creek, a tributary of the Trinity 
River, and about 5 miles south of Ennis, Ellis 
County, Tex. 
Existing project. For a description of completed 
improvement and authorizing act see 
Annual Report of 1969. Estimated cost of project 
is $12,941,000. 
Local cooperation. Local interests must reimburse 
the Federal Government for costs 
allocated to increased water supply storage under 
the terms of the Water Supply Act of 1958. 
In Contract approved by the Secretary of the 
Army on 24 June 1963 the Trinity River 
Authority, a State agency, agreed to fulfill all 
requirements of local cooperation. To date the 
authority has paid $50,066 toward principal 
and $95,713 toward annual cost of operation 
and maintenance of project, including cost of 
operating 10-foot conduit. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Benefits accrued to Bardwell project: Accumulated 
flood damages prevented through 
fiscal year 1975 were $5,896,200. 
Condition at end of fiscal year. Construction 
of project was started August 1963 and completed 
for beneficial use in November 1965. 
Recreation facilities under Code 710 remain. 
10. BELTON LAKE, TEX. 
Location. Dam is on Leon River about 16.7 
miles above confluence of Leon and Lampasas 
Rivers and about 3 miles north of Belton, Tex. 
(See Geological Survey base map, scale 1:500,- 
000 and Geological Survey, Belton sheet, scale 
1:62,500.) 
Existing project. For a description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Estimated cost of project 
is $18,410,000. 
16-6

FORT WORTH, TEX., DISTRICT 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. A contract with Brazos 
River Authority, a State agency, for remaining 
water supply storage in reservoir was approved 
by Secretary of the Army on 15 January 1958, 
at an estimated cost of $1,602,822. To date 
$408,138 has been paid. Under the contract 
Brazos River Authority must also pay annually 
11.2 percent of actual annual cost of operation 
and maintenance. To date $182,750 has been 
paid. An interim contract with Brazos River 
Authority for emergency use of water supply 
storage in project was approved by Secretary 
of the Army on 2 January 1957. Amount of 
$152,435 paid by authority on 21 March 1957 
for use of these facilities was credited to interest 
and principal payable under formal 
water supply contract. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Raising water supply pool: Engineering and 
design and construction were completed. Minor 
real estate activities continued. 
Benefits accrued to Belton project: Accumulated 
damages prevented through fiscal 
year 1975 were $84,588,100. 
Condition at end of fiscal year. Construction 
started June 1949 and project was ready for 
beneficial use in March 1954. Raising water 
supply pool: Construction started in July 1970 
and the pool raise is complete. Recreation 
facilities under Code 710 remain. 
11. BENBROOK LAKE, TEX. 
Location. Dam is in Tarrant County, Tex., on 
Clear Fork of Trinity River 15 river miles upstream 
from its confluence with West Fork of 
Trinity River about 10 miles southwest of 
downtown Fort Worth, Tex. 
Existing project. For description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Estimated cost of project 
is $14,544,000. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. No water supply storage 
is included in project. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Benefits accrued to system consisting of Benbrook 
Lake and Fort Worth Floodway: Accumulated 
flood damages prevented through 
fiscal year 1975 are estimated at $37,339,500. 
Condition at end of fiscal year. Construction 
of project was started May 1947 and ready for 
beneficial use in September 1952. Recreation 
facilities under Code 710 remain. 
12. BIG FOSSIL CREEK, TEX. 
Location. In city of Richland Hills, Tarrant 
County, Tex., on Big Fossil Creek, a tributary 
of West Fork, Trinity River. 
Existing project. For a description on completed 
improvement and authorizing act see 
annual report of 1969. Final cost of the improvement 
was $2,118,000 ($1,917,100 Federal 
and $200,900 local interest.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Completed project is being operated and maintained 
by the city of Richland Hills, Texas. Accumulated 
flood damages prevented through 
"fiscal year 1975 are estimated at $4,967,700. 
Condition at end of fiscal year. Construction 
was started in May 1964 and completed in 
September 1966. 
13. BRAZOS RIVER BASIN, TEX. 
Location. The Brazos River Basin extends 
from eastern New Mexico southeastwardly and 
diagonally across the State of Texas to the Gulf 
of Mexico. The basin has an overall length of 
about 640 miles and a maximum width of 
about 120 miles. Its total area is about 44,640 
square miles, of which 1,800 lie within four 
counties in New Mexico and 42,840 within 72 
counties in Texas. 
Existing project. The Flood Control Act of 3 
September 1954 authorized the basinwide plan 
of improvement for the Brazos River Basin as 
outlined in House Document 535, 81st Congress, 
2d Session, and appropriation of $40 
million was authorized for partial accomplishment 
of the plan. The Flood Control Act of 
1962 added the North and South Fork Lakes 
(San Gabriel River), and the Flood Control Act 
of 1968 added Aquilla Dam and Lake (Aquilla 
Creek) and Millican and Navasota Lakes 
(Navasota River) to the Brazos River Basin 
plan of improvement. Public Laws 86-645, 88- 
253, 89-42, 90-17, 90-483, 91-282, 92-222, and 
93-251 increased monetary authorization $21, 
$30, $14, $9, $2, $5, $20, and $19 million 
respectively, bringing total authorization to 
$160 million. The plan provides for construction 
of the following lakes for flood control and 
allied purposes in the Brazos River Basin, Texas: 
Waco Lake on Bosque River, Proctor Lake 
on Leon River, Stillhouse Hollow Lake on Lampasas 
River, Granger, North Fork and South 
Fork Lakes on San Gabriel River, Somerville 
Lake on Yegua Creek, Millican and Navasota 
Lakes on Navasota River, and Aquilla Lake on 
Aquilla Creek. The plan further provides for 
16-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
modification of existing Belton Lake project by 
installation of hydroelectric power generating 
facilities. The plan also provided for construction 
of a levee and related work on west side of 
the Brazos River to afford protection for 
Burleson County Levee Improvement District 
No. 1 and local flood works at Lampasas, Texas, 
but due to lack of receipt of required 
assurances of local cooperation within five-year 
limitation period the authorization for these 
improvements expired. Project maps are in the 
Senate Project Documents. The estimated cost 
of the basinwide plan of improvement is $653,- 
839,000. Aquilla, Millican, Proctor, Somerville, 
Stillhouse Hollow, Waco, and San Gabriel 
River Lakes projects are reported separately. 
Detailed planning has not been initiated on 
other projects in the plan of improvement. (See 
Table 16-E for Flood Control Works included 
in Basinwide Plan). 
14. CANYON LAKE, TEX. 
Location. Dam is on Guadalupe River, 303 
miles above its mouth, and about 12 miles 
northwest of New Braunfels, Comal County, 
Tex. 
Existing project. For a description of completed 
improvement and authorizing act see 
Annual Report of 1969. Estimated cost of project 
is $21,732,000, including $1,400,000 contributed 
by local interests. 
Local cooperation. Local interests 
(Guadalupe-Blanco River Authority) will utilize 
water impounded for water supply and 
streamflow regulation for development of electric 
power. In a formal contract approved by 
Chief of Engineers on 24 October 1957, 
Guadalupe-Blanco River Authority agreed to 
fulfill all requirements of local cooperation. Required 
contribution of $1,400,000 was made in 
full by Guadalupe-Blanco River Authority. In 
addition, $22,848 was contributed for installation 
and operation of reservoir leakage gages. 
Under the contract the authority must pay 34.8 
percent of actual annual cost of operation and 
maintenance. To date $420,124 has been paid. 
Operations and results during fiscal year. 
Regular funds: Routine operation and 
maintenance continued. 
Benefits accrued to Canyon project: Accumulated 
damages prevented through fiscal 
year 1975 were $17,447,600. 
Condition at end of fiscal year. Construction 
started April 1958 and project completed for 
beneficial use June 1964. Recreation facilities 
under Code 710 remain. 
15. CARL L. ESTES DAM 
AND LAKE, TEX. 
Location. The dam site is located at river 
mile 475.6 on the Sabine River, 38.9 miles 
downstream from the existing Iron Bridge 
Dam, and 55 miles east of Dallas, Texas. The 
project is located in parts of Woods, Rains and 
Van Zandt counties. 
Existing project. The plan of improvement 
provides for an earth and rock fill dam 90 feet 
high and 26,300 feet long including a gated 
spillway, 232 feet long, on the right bank. The 
dam will create a lake with a total controlled 
storage of 1,375,000 acre-feet, including 984,- 
500 acre-feet for flood control, 370,000 acre-feet 
for water supply, and 20,400 acre-feet for sediment 
reserve. The project was authorized by 
the Flood Control Act of 1970 (P.L. 91-611) 
substantially in accordance with recommendations 
as outlined in House Document No. 91- 
429 (91st Congress) and is a unit in the comprehensive 
basinwide plan of water resource 
development. Estimated cost of project is $155,- 
000,000. 
Local cooperation. Water Supply Act of 1958, 
Federal Water Project Recreation Act of 1965, 
and Section 221 of the Flood Control Act of 
1970 apply. The Sabine River Authority of 
Texas and the Texas Water Development 
Board are the local project sponsors. 
Operations and results during fiscal year. 
Preconstruction planning continued. Hydrology 
Design Memorandum approved June 1975. 
Phase II General Design Memorandum and 
Environmental Impact Statement continued. 
Condition at end of fiscal year. Preconstruction 
planning is 30 percent complete. 
16. DUCK CREEK CHANNEL 
IMPROVEMENT, TEX. 
Location. In Garland, Dallas County, Texas 
on Duck Creek, a tributary of the Trinity River 
between river mile 10.4 and 17.5. 
Existing project. Provides for realignment 
and enlargement of 6.6 miles of channel improvement 
consisting of concrete walls, 
modification of drainage facilities, 2 railroad 
bridges, 9 street bridges and relocation of all 
utilities. Estimated Federal cost of these 
modifications is $9,000,000 and estimated cost 
to local interests is $6,500,000, a total of $15,- 
500,000. Existing project was authorized by 
River and Harbor Act of 1965 in House Document 
276, 89th Congress, 1st Session. 
Local cooperation. Local interests must 
provide without cost to the United States all 
16-8

FORT WORTH, TEX., DISTRICT 
lands, easements and rights-of-way necessary 
for construction, and all alterations and 
relocations of existing buildings, utilities, 
bridges (except railroad bridges), sewers, 
pipelines and any other existing improvements; 
hold the United States free from damages due 
to the construction work, operate and maintain 
all features after completion of the project. 
Operations and results during fiscal year. 
Regular funds, new work: Construction contracts 
were awarded for the relocation of MKT 
Railroad and the AT&SF Railway, and continued 
engineering and design. The AT&SF 
Railway contract has been modified to provide 
an option for actual construction, the option to 
be exercised within a period not to exceed 3 
years from 15 June 1973. The funds for the option 
portion of the contract have been 
deobligated. 
Condition at end of fiscal year. Construction 
started in June 1972, and the project is 4 percent 
complete. Construction of the contract has 
been suspended pending local interests 
providing items required for local cooperation. 
17. ELM FORK FLOODWAY, TEX. 
Location. The project is located in Dallas and 
Denton Counties, Texas. A portion of the improvement 
will be in and adjacent to the cities 
of Dallas, Irving and Farmers Branch, Texas. 
Existing project. Improvement of the Elm 
Fork of the Trinity River from the mouth to 
Lewisville Dam and along Denton Creek, a 
tributary of the Elm Fork to Grapevine Dam. 
The plan of improvement provides for enlargement 
and realignment of about 22 miles of the 
Elm Fork, enlargement and realignment of 
about 20 miles of tributary channels, construction 
of about 39 miles of new levee, rehabilitation 
of about 2 miles of existing levees, 
modification of 14 street and highway bridges, 
4 railroad bridges and alteration of utilities. 
Estimated Federal cost of these modifications 
is $30,500,000, and non-Federal estimated cost 
is $34,800,000, a total of $65,300,000. Project 
was authorized by the River and Harbor Act of 
1965 (H. Doc. 276, 89th Cong. 1st Sess.) 
Local cooperation. Local interests are required 
to provide (without cost to the Federal 
Government) except for the main channel 
thereof, all lands, easements, utilities and 
bridge relocations (except railroad bridges) 
necessary for construction and operation of the 
project. Assurances were signed 20 March 1969 
by the Trinity River Authority, a State agency, 
that they would provide items required of local 
interests. 
Operations and results during fiscal year. 
Regular funds, new work: Preconstruction 
planning was completed in 1973. Further 
studies have been suspended until a definite 
plan has been accepted by local interests. 
Condition at end of fiscal year. Preconstruction 
planning is complete. 
18. FORT WORTH FLOODWAY 
(CLEAR FORK) TEX. 
Location. In Fort Worth, Tarrant County, 
Tex., on Clear Fork of Trinity River between 
miles 1.6 and 10.4. 
Existing project. For a description of completed 
improvement and authorizing act, see 
Annual Report of 1971. Final cost of improvement 
was $4,110,751 Federal. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Regular funds: All channel improvement construction 
is complete. 
Condition at end of fiscal year. Construction 
was initiated in January 1966 and completed 
September 1971. 
19. FORT WORTH FLOODWAY 
(WEST FORK) TEX. 
Location. In Fort Worth, Tarrant County, 
Tex., on West Fork of Trinity River between 
miles 564.5 and 570.4. 
Existing project. For a description of completed 
improvement and authorizing act, see 
Annual Report of 1971. Final cost of improvement 
was $3,304,839 Federal. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Regular funds: All construction was completed 
in June 1971. 
Condition at end of fiscal year. Construction 
was initiated in March 1965 and was completed 
in June 1971. 
20. GRAPEVINE LAKE, TEX. 
Location. Dam is in Tarrant County, Tex., on 
Denton Creek, 11.7 river miles upstream from 
its confluence with Elm Fork of Trinity River 
and about 20 miles northwest of city of Dallas, 
Tex. 
Existing project. For description of completed 
improvement and authorizing act see 
Annual Report for 1962. Estimated cost of project 
is $18,896,000, including $2,040,000 contributed 
by local interests. 
16-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. A contract with Dallas 
County Park Cities Water Control and Improvement 
District No. 2 for 50,000 acre-feet of 
water supply storage was approved by 
Secretary of the Army on 21 March 1955. Park 
Cities paid the required $607,000. A contract 
with city of Dallas for 85,000 acre-feet of water 
supply storage was approved by the Secretary 
of the Army on 17 March 1954. Dallas paid required 
$1,433,026. A Contract with city of 
Grapevine, Tex., for 1,250 acre-feet of water 
supply storage was approved by Secretary of 
the Army on 14 September 1953, at an estimated 
cost of $22,654. To date Grapevine has 
paid $22,654. Above contracts include payment 
of operation and maintenance costs as follows: 
Dallas County Park Cities Water Control and 
Improvement District No. 2, a pro rata part of 
the actual annual cost, which part to be not less 
than $2,000 nor more than $3,000; Dallas, 9.2 
percent of actual annual cost; and Grapevine, 
its pro rata part of actual annual cost 
(estimated at $79.55 annually and included in 
total annual payment). Following operation and 
maintenance payments have been made: Park 
Cities $66,482, Dallas $161,708, and Grapevine 
$1,591. 
Operations and results during fiscal year. 
Condition at end of fiscal year. Construction 
of project was started December 1947 and 
ready for benefical use in July 1952. Recreation 
facilities under Code 710 remain. 
21. GREENVILLE, TEX. 
Location. In Greenville, Hunt County, Tex. 
on Long Branch of the Sabine River. 
Existing project. Provide for realignment and 
enlargement of 3.34 miles of improved channel 
along Long Branch. Estimated Federal cost is 
$852,000, and estimated cost to local interests 
is $154,000, a total of $1,006,000. Existing project 
was authorized by the Rivers and Harbors 
Act of 1970 in House Document 91-429, 91st 
Congress, 2nd Session. 
Local cooperation. Local interests must 
provide without cost to the United States all 
lands, easements and rights-of-way necessary 
for construction, and all alterations and 
relocations of existing buildings, utilities, 
bridges (except railroad), sewers, pipelines and 
any other existing improvements; hold the United 
States free from damages due to construction 
work; and operate and maintain all 
features after completion of the project. 
Operations and results during fiscal year. 
Plans and specifications were approved in 
December 1974. 
Condition at end of fiscal year. Preconstruction 
planning is complete. 
22. GUADALUPE AND SAN 
ANTONIO RIVERS, TEX. 
Location. Improvements are Gonzales Lake 
on lower San Marcos River, a tributary of 
Guadalupe River and channel improvement of 
San Antonio River and tributaries at San Antonio, 
Tex. 
Existing project. Flood Control Act of .1954 
(H. Doc. 344, 83d Cong., 2d Sess.) adopted plan 
of improvement on Guadalupe and San Antonio 
Rivers. Plan provides for construction of Gonzales 
Lake on San Marcos River for flood control 
and water supply and local flood protection 
for cities of San Antonio and Kenedy, Tex. Due 
to lack of local cooperation, authorization for 
Kenedy Channel improvement expired 5 May 
1964. Existing project maps are in project 
document. Estimated cost for new work is 
$125,800,000 including $49,700,000 non- 
Federal cost on local flood protection projects. 
(See Table 16-F on flood control works.) 
23. HORDS CREEK LAKE, TEX. 
Location. On Hords Creek, a tributary of 
Pecan Bayou, about 13.5 miles west of 
Coleman, Tex., and about 27.8 miles upstream 
from mouth of Hords Creek. (See Geological 
Survey sheets, Grosvenor and Zephyr, scale 
1:62,500.) 
Existing project. For description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Estimated cost of project 
is $4,337,000 including $105,000 contributed 
by local interests. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Benefits accrued to Hords Creek project: Accumulated 
flood damages prevented through 
fiscal year 1975 were $937,200. 
Condition at end of fiscal year. Construction 
of project was started January 1947 and completed 
for beneficial use in April 1948. Recreation 
facilities under Code 710 remain. 
24. LAKE BROWNWOOD 
MODIFICATION, TEX. 
Location. The dam will be located at river 
mile 57 on Pecan Bayou, a tributary of the 
Colorado River, eight miles north of 
Brownwood, Texas. The lake will be located in 
Brown and Coleman counties. 
16-10

FORT WORTH, TEX., DISTRICT 
Existing project. The project will insure the 
safety of the existing non-federal Lake 
Brownwood and preserve its flood control, 
water supply, and related values. Modification 
measures consist of a new embankment 130 
feet high and 1,870 feet long, new outlet works, 
and erosion control measures in the spillway 
channel. The total controlled storage of the existing 
lake is 118,900 acre-feet including 85,900 
acre-feet for water supply and 33,000 acre-feet 
for sediment reserve. Storage capacity will not 
be altered by this project. The modification 
project was authorized by the Flood Control 
Act of 1968 (P.L. 90-483) substantially in accordance 
with recommendations of the Chief of 
Engineers as contained in House Document No. 
90-350. Estimated cost of project is $20,670,000 
including $8,270,000 non-federal cost. 
Local cooperation. Water Supply Act of 1958 
and Section 221 of the Flood Control Act of 
1970 apply. Brown County Water Improvement 
No. 1 is the local sponsor. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Conditions at end of fiscal year. Preconstruction 
Planning 60 percent complete. 
25. LAKEVIEW LAKE, TEX. 
Location. Dam site is located at river mile 
11.2 on Mountain Creek, a right bank tributary 
of the West Fork of the Trinity River, and is 
adjacent to the city limits of Grand Prairie, 
Dallas County, Texas, which is one of the 
rapidly growing cities in the Dallas-Fort 
Worth metropolitan area. 
Existing project. The project provides for 
construction of an earthfill dam with a maximum 
height of 105 feet above the streambed 
and a total length of 24,200 feet, including a 
200-foot uncontrolled ogee type spillway, which 
will control 232 square miles of drainage area. 
The reservoir will have a total controlled 
storage of 304,000 acre-feet and a water surface 
area of 10,940 acres at the top of the flood 
control pool and 7,470 acres at the top of the 
conservation pool. The total storage includes 
122,800 acre-feet for flood control, 143,200 
acre-feet for conservation and 38,000 acre-feet 
for sediment reserve. Estimated Federal cost of 
the project is $174,000,000. Project was 
authorized by River and Harbor Act of 1965 
(H. Doc. 276, 89th Cong., 1st Sess.), and is a 
unit in the general comprehensive plan for 
development and control of the water resources 
of the Trinity River basin. 
Local cooperation. Prior to initiation of construction, 
responsible local interests must give 
assurances satisfactory to the Secretary of the 
Army that they will: (a) reimburse the United 
States for the water supply storage in the project 
on terms which will permit paying out the 
costs allocated thereto as determined by the 
Chief of Engineers in accordance with the 
provisions of the Water Supply Act of 1958, as 
amended, and (b) obtain without cost to the 
United States all water rights necessary for 
operation of the project in the interest of water 
supply. The Trinity River Authority, a State 
agency, is the principal proponent of the project, 
and by letters dated 2 October 1961 and 9 
August 1962 and in informal discussions has 
stated that it is the intent of this organization 
to sponsor and to comply on items of cooperation 
required of local interests. 
Operations and results during fiscal year. 
Regular funds, new work: Congress had requested 
a restudy of the Lakeview Project. This 
restudy was completed by FWD and was 
forwarded by OCE OSA on 18 July 1973. OSA 
forwarded it to the Chairman of the House 
Subcommittee on Public Works on 16 January 
1974. Preconstruction planning is complete. 
Condition at end of fiscal year. Construction 
new start for fiscal year 1975, engineering and 
design is continued. 
26. LEWISVILLE DAM, TEX. 
Location. In Denton County, Tex. on Elm 
Fork of Trinity River 30 river miles above its 
confluence with Trinity River and about 22 
miles northwest of city of Dallas, Tex. at a site 
downstream from old Garza Dam. 
Existing project. For description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Estimated cost of project 
is $27,527,000 including $3,677,000 contributed 
by local interests. 
Local cooperation. A contract with city of 
Dallas for 415,000 acre-feet of water supply 
storage and rights and interests to Garza Dam 
and Reservoir was approved by the Secretary 
of the Army on 16 July 1953. Local contributions 
have been made in full. A contract 
with city of Denton, Tex., for remaining 21,000 
acre-feet of water supply storage was approved 
by the Secretary of the Army on 20 May 1954, 
with an estimated cost of $250,064. To date 
Denton has paid $250,064. Under above contracts, 
cities of Dallas and Denton must pay annually 
21.9 and 1 percent, respectively, of actual 
annual cost of operation and maintenance. 
To date Dallas has paid $715,068 and Denton 
$31,201. 
Operations and results during fiscal year. 
Regular funds: Routine operation and 
maintenance continued. 
16-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Benefits accrued to system comprised of 
Lewisville Lake, Grapevine Lake, and Dallas 
Floodway: Accumulated flood damages 
prevented through fiscal year 1975 were $311,- 
988,500. 
Condition at end of fiscal year. Construction 
of project was started November 1948 and 
ready for beneficial use in November 1954. 
Recreation facilities under Code 710 remain. 
27. LAVON LAKE, TEX. 
Location. Dam is in Collin County, Tex., on 
East Fork of Trinity River 55.9 miles above its 
confluence with Trinity River and about 22 
miles northeast of Dallas, Tex. 
Existing project. For description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Estimated cost of project 
is $15,470,000. For information concerning 
Lavon Lake Modification and East Fork 
Channel Improvement project, see individual 
project. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. A contract with North 
Texas Municipal Water District for water 
supply storage, including cost of intake structure, 
was approved by Secretary of the Army 8 
July 1954, at an estimated cost of $1,405,753. 
Contract was revised in 1973 and final revised 
contract amount is $1,445,261.67. To date the 
district has paid $382,317. Under the contract 
North Texas Municipal Water District must 
pay annually 13.6 percent of actual annual cost 
of operation and maintenance. To date the district 
has paid $258,858. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Benefits accrued to Lavon project: Accumulated 
flood damages prevented through 
fiscal year 1975 were $46,474,800. 
Condition at end of fiscal year. Construction 
of project was started January 1948 and ready 
for beneficial use in September 1953. Project is 
complete. See section 26 for Lavon Lake 
Modification and East Fork Channel Improvement 
authorized by Flood Control Act of 1962. 
28. LAVON LAKE MODIFICATION 
AND EAST FORK CHANNEL 
IMPROVEMENT, TEX. 
Location. Existing dam is in Collin County, 
Tex., on East Fork of Trinity River, 55.9 miles 
above its confluence with Trinity River and 
about 22 miles northeast of Dallas, Tex. 
Channel improvement of East Fork extends 
from its mouth to river mile 31.8. 
Existing project. Reservoir modification 
provides for raising top of existing dam from 
elevation 502.0 to 514.0 and lengthening existing 
dam from about 9,499 feet to about 19,- 
493 feet; modification of existing concrete 
spillway structure; enlargement of existing 
reservoir area, involving acquisition of additional 
rights-of-way; relocation and alteration 
of highways, county roads, railroads and 
utilities; and provision of recreational facilities. 
East Fork Channel and floodway improvements 
consist of 25 miles of channel 
enlargement and straightening of the East 
Fork between river mile 0.0 and 31.8; replacement 
of inadequate levee-sluice structures; 
rehabilitation of existing levees; acquisition 
and clearing of land areas as required for 
rights-of-way along improved channel and existing 
levees; alteration of existing railroad, 
highway and county road bridges crossing the 
improved channel as well as relocation of existing 
utility lines; and strengthening and raising 
about 202,400 linear feet of levees of seven 
existing levee districts. Reservoir will provide 
a total storage capacity of 748,200 acre-feet 
(275,600 are for flood control, 380,000 for water 
supply storage, and 92,600 for sedimentation 
reserve). Estimated Federal cost of the 
modification and improvement is $60,200,000 
and estimated cost to local interests is $220,000 
for lands and damages and relocations, a total 
of $60,420,000. 
Local cooperation. Local interests must reimburse 
the Federal Government for costs 
allocated to increased water supply storage under 
the terms of the Water Supply Act of 1958. 
The North Texas Municipal Water District has 
contracted for 43 percent of the water supply 
(approved 22 September 1967 by the Secretary 
of the Army) and has submitted assurances to 
contract for the 57 percent for future water 
supply. Reimbursement is currently estimated 
at $31,493,000. 
Levee Districts 4 and 5, which comprise the 
lower 10 miles of the East Fork Channel, 
entered into agreements as required by section 
221 of the Flood Control Act of 1970 on 28 
January 1972 and have furnished all necessary 
construction easements. 
Levee Districts 6, 8, 10, 13, and 15, which 
comprise the upper 15 miles of the East Fork 
Channel, declined to provide the necessary 
assurances and were issued a 5-year notice of 
deauthorization for this portion of the project 
on 17 October 1972 in accordance with section 
201 of the Flood Control Act of 1962. On 8 
December 1972, this portion of the project was 
reclassified from "active" to "inactive" 
category. 
16-12

FORT WORTH, TEX., DISTRICT 
Operations and results during fiscal year. 
Regular funds: Construction contracts were 
awarded for Landscaping Part II; Landscaping 
for Recreation Facilities, Part I; Revegetation; 
Turfing for Recreation Facilities; Turfing Embankment 
Part II; construction was completed 
on South Access Road; Landscaping and Turfing 
Part I; Cemetery Modification; Spillway 
Bridge Repair; Reservoir Clearing, Embankment 
& Spillway Modifications. Construction 
continuing on Relocation State Highway 24, 
FM Highway 546 & 1377, Relocation AT&SF 
Railroad, & Recreation Facilities, Part II. 
Condition at end of fiscal year. 'Construction 
was initiated in May 1970 and is 90 percent 
complete. 
29. MILLICAN LAKE, TEX. 
(Planning transferred. See Little Rock, Ark., 
District). 
30. NAVARRO MILLS LAKE, TEX. 
Location. Dam is in Navarro County, ex., at 
river mile 63.9 on Richland Creek, a tributary 
of Trinity River, about 16 miles southwest of 
Corsicana, Tex. 
Existing project. For description of completed 
improvement and authorization acts see 
Annual Report for 1965. Estimated cost of project 
is $12,546,000 including $300,000 contributed 
by local interests. 
Local cooperation. The Water Supply Act of 
1958, as amended applies. A formal contract 
with the Trinity River Authority was approved 
3 March 1966, by the Secretary of the Army at 
an estimated cost of $2,260,800. To date the 
Authority has paid $240,625 for water supply 
and $235,440 for operation and maintenance. 
Operation and results during fiscal year. 
Routine operation and maintenance continued. 
Benefits accrued to Navarro Mills project: 
Accumulated flood damages prevented through 
fiscal year 1975 were $22,285,100. 
Condition at end of fiscal year. Construction 
started December 1959 and project completed 
for beneficial use March 1963. Preconstruction 
planning for Alteration of FM Highway 3164 
in Woolf Creek Park was completed. P&S completed 
and approved December 1973. Construction 
pending awaiting allocation of funds. 
Recreation facilities under Code 710 remain. 
31. O. C. FISHER DAM 
AND LAKE, TEX. 
Location. Dam is on North Concho River, a 
tributary of Concho River, about 6.6 miles 
above mouth of North Concho River near city 
of San Angelo, Tex. (See Geological Survey 
base map, Texas, scale 1:500,000, and sheet 
Wall, scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Name was changed 
from San Angelo Dam and Reservoir 3 
January 1975 by Public Law 93-634. Estimated 
cost of project is $17,111,000. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. A water-supply contract 
with Upper Colorado River Authority for 
water-supply storage in reservoir was approved 
by Secretary of the Army on 11 October 1948. 
The Authority has contributed $860,444 toward 
cost of project and $64,324 toward operation 
and maintenance for a 50-year period. The 
Authority must pay additional consideration of 
$1 a year for useful life of project, beginning 1 
January 1965. 
Operations and results during fiscal year. 
Regular funds: Routine operation and 
maintenance continued. 
Benefits accrued to 0. C. Fisher Dam & 
Lake project: Accumulated flood damages 
prevented through fiscal year 1975 were $2,- 
375,600. 
Condition at end of fiscal year. Construction 
of project was started May 1947 and ready for 
beneficial use February 1952. Recreation 
facilities under Code 710 remain. 
32. PROCTOR LAKE, TEX. 
Location. Dam is at river mile 238.9 on Leon 
River, a tributary of Brazos River, about 8 
miles northeast of Comanche in Comanche 
County, Tex. 
Existing project. For description of completed 
improvement and authorization act see 
Annual Report of 1969. Estimated cost of project 
is $16,249,000. 
Local cooperation. The Water Supply Act of 
1958 applies. A formal contract with the 
Brazos River Authority, a State agency, was 
approved by Secretary of the Army, 1 July 
1960, and was modified and was approved 9 
May 1966, at an estimated cost of $1,707,900. 
To date the Authority has paid $41,299 for 
water supply and $43,491 for operation and 
maintenance. 
Operations and results during fiscal year. 
Regular funds: Routine operation and 
maintenance were continued. 
Benefits accrued to Proctor project: Accumulated 
flood damages prevented through 
fiscal year 1975 were $4,486,800. 
16-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Condition at end of fiscal year. Construction 
of project was started July 1960 and completed 
for beneficial use 1963. Recreation facilities under 
Code 710 remain. 
33. RUTLEDGE HOLLOW CREEK 
CHANNEL IMPROVEMENT, 
POTEET, TEXAS 
Location. In Poteet, Atascosa County, Texas, 
on Rutledge Hollow Creek, a tributary of the 
Atascosa River in the Nueces River Basin. 
Existing project. For description of completed 
improvements and authorization act see 
Annual Report of 1969. The Federal cost was 
$105,300 and local interests cost was $75,000. A 
total cost of $180,300. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
The City of Poteet, Texas, continued routine 
operation and maintenance during the fiscal 
year. 
Condition at end of fiscal year. Construction 
was started in June 1968 and was completed in 
October 1968. 
34. SABINE RIVER BASIN, TEX. 
Location. The Sabine River Basin extends in 
a general northwest--southeast direction from 
Collin and Rockwell Counties about 35 miles 
northeast of Dallas, Texas, about 165 miles to 
the eastern boundary of the State; thence 
southerly in Texas and Louisiana about 145 
miles to the head of Sabine Lake near Orange, 
Texas. The basin is about 300 miles long and 
varies in width from a minimum of 16 miles to 
a maximum of 48 miles, with a drainage area 
of approximately 9,756 square miles of which 
2,330 square miles are located in Louisiana and 
7,426 square miles in Texas. 
Existing project. The River and Harbor Act 
of 1970 authorized the plan of improvement for 
the Sabine River Basin as outlined in House 
Document 91-429, 91st Congress, 2d Session 
and appropriation of $40,000,000 was authorized 
for partial accomplishment of the plan. The 
plan provides for construction of Carl L. Estes, 
Lake Fork and Big Sandy Lakes. The plan 
further provides for Local Flood Protection for 
the City of Greenville, Texas. The estimated 
cost of the basinwide plan of improvement is 
$326,900,000. (See Table 16-G for Flood Control 
Works included in Basinwide Plan.) 
35. SAN ANTONIO CHANNEL 
IMPROVEMENT, TEX. 
Location. Floodway is in city of San Antonio, 
Bexar County, Tex., on San Antonio River and 
San Pedro, Apache, Alazan, and Martinez 
Creeks. 
Existing project. Provides for clearing, 
widening, deepening, and straightening about 
31 miles of river and creek channels to carry 
standard project flood discharges, construction 
of channel walls, and paving, conduit, and construction 
and alteration of railroad bridges. Estimated 
Federal cost of these modifications is 
$42,700,000 and estimated cost to local interests 
is $49,700,000 which includes $1,200,000 
cash contributions and $48,500,000 for lands, 
damages, and construction, a total of $92,400,- 
000. Existing project was authorized by 1954 
Flood Control Act (H. Doc. 344, 83d Cong., 2d 
Sess.). Latest published map is in project document. 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction, 
including purchase and removal of buildings, 
relocation or reconstruction of bridges (exclusive 
of railway bridges), channel dams 
where applicable, and utility lines; hold the 
United States free from damages; maintain 
and operate all works after completion; and 
provide a cash contribution for enhancement 
benefits of 2.65 percent of actual Federal construction 
cost. San Antonio River Authority 
furnished assurances that it will comply with 
all requirements of local cooperation. These 
assurances were accepted by the District 
Engineer on 15 April 1957. To date $542,000 
has been contributed by San Antonio River 
Authority. In addition, $30,000 has been contributed 
and accepted, under the authority of 
Civil Functions Appropriations Act of 1958, for 
vehicular crossings over the San Antonio 
channel. 
Operations and results during fiscal year. 
Regular funds: Construction was continued on 
Apache Creek Channel Improvement, Unit 5-2. 
Construction contract was awarded for Apache 
Creek, Unit 5-3. Engineering and design 
studies continued. 
Condition at end of fiscal year. Construction 
was started in October 1957 and the project is 
49 percent complete. 
36. SAN GABRIEL RIVER, TEXAS 
Location. System of three reservoirs in 
Williamson County in the central portion of 
Brazos River Basin. Granger Dam at river 
mile 31.9 on San Gabriel River, about 7 miles 
east of Granger, Tex.; North Fork Dam at 
river mile 4.3 on North Fork of San Gabriel 
River, about 3.5 miles northwest of 
Georgetown, Tex.; and South Fork Dam at 
river mile 4.7 on South Fork of San Gabriel 
16-14

FORT WORTH, TEX., DISTRICT 
River, about 3 miles southwest of Georgetown, 
Tex. 
Existing project. Granger Lake was authorized 
by 1954 Flood Control Act, and North and 
South Fork Lakes were authorized by 1962 
Flood Control Act. Estimated total Federal 
cost of project is $118,000,000. Plan of improvement 
provides for the following: Granger: An 
earthfilled dam 16,320 feet long, with maximum 
height of 115 feet above streambed, 
which controls 709 square miles of drainage 
area. Reservoir provides a total storage capacity 
of 244,200 acre-feet, of which 162,200 acrefeet 
are for flood control, 37,900 acre-feet for 
water supply storage, and 44,100 acre-feet for 
sediment reserve. Estimated cost of project is 
$62,600,000. North Fork: A rockfill dam 5,950 
feet long with maximum height of 165 feet 
above streambed, which controls 246 square 
miles of drainage area. Reservoir provides a 
total storage capacity of 130,800 acre-feet, of 
which 87,600 acre-feet are for flood control, 
29,200 acre-feet for water supply storage, and 
14,000 acre-feet for sediment reserve. Estimated 
cost of project is $28,600,000. South 
Fork: A rockfill dam 5,120 feet long with maximum 
height of 152 feet above streambed, 
which controls 123 square miles of drainage 
area. Reservoir provides a total storage capacity 
of 82,600 acre-feet (45,700 for flood control, 
28,900 for water supply storage, and 8,000 for 
sediment reserve). Estimated cost of project is 
$26,800,000. 
Local cooperation. Construction is subject to 
condition that local interests reimburse the 
Federal Government for costs allocated to 
water supply at Granger, North Fork, and 
South Fork Lakes. Reimbursement currently 
estimated at $13,115,000 for Granger, $7,911,- 
000 for North Fork, and $7,935,000 for South 
Fork, for a total of $28,961,000, exclusive of interest. 
Brazos River Authority, a State agency, 
is the local interests' sponsor of project, and by 
letter dated 18 April 1966, indicated its acceptance 
of the proposed plan of development and 
its willingness to pay for the costs allocated to 
water supply in each reservoir in the ultimate 
plan. Such water supply assurances for 
Granger and North Fork Lakes were approved 
24 May 1968 as satisfactory in accordance with 
requirements of the Water Supply Act of 1958, 
as amended. Contract negotiations for South 
Fork Lake will be deferred until the need for 
water supply develops and the reservoir is 
scheduled for construction. 
Operations and result during fiscal year. 
Regular funds: Construction was initiated on 
county road relocations-Part II and Cemetery 
relocation at North Fork. Construction continued 
on relocation of utilities and on the outlet 
works at both North Fork and Granger. 
Construction was completed on the cemetery 
relocation at North Fork. Real Estate activities 
and engineering and design continued at 
Granger and North Fork. 
Condition at end of fiscal year. Project is 
about 25 percent complete. 
37. SOMERVILLE LAKE, TEX. 
Location. Dam is on Yegua Creek 20 miles 
upstream from its confluence with Brazos 
River and about 2 miles south of Somerville, 
Tex. 
Existing project. For description of completed 
improvements and authorization act see 
Annual Report of 1969. Estimated cost of project 
is $30,227,000. 
Local cooperation. The Water Supply Act of 
1958, as amended, applies. A contract with the 
Brazos River Authority, a State agency, for 
water supply storage was approved 10 May 
1962, by the Secretary of the Army, at an estimated 
cost of $4,871,815. Also under the contract, 
the Authority must pay annually 28.655 
percent of the actual annual cost of operation 
and maintenance. 
Operations and results during fiscal year. 
Regular funds: Routine operation and 
maintenance continued. 
Benefits accrued to Somerville project: Accumulated 
damages prevented through fiscal 
year 1975 were $15,828,400. 
Condition at end of fiscal year. Construction 
started in June 1962 and project was ready for 
beneficial use in January 1967. Recreation 
facilities under Code 710 remain. 
38. STILLHOUSE HOLLOW DAM, 
TEX. 
Location. Dam is on Lampasas River 16 
miles upstream from its confluence with Little 
River, a tributary of the Brazos River, and 
about 5 miles southwest of Belton, Tex. 
Existing project. For description of completed 
improvements and authorization act see 
Annual Report of 1969. Estimated cost of project 
is $23,670,000. 
Local cooperation. The Water Supply Act of 
1958 applies. A contract with the Brazos River 
Authority, a State agency, for water supply 
storage was approved 13 April 1962, by the 
Secretary of the Army, at an estimated cost of 
$6,912,430. To date the Authority has paid 
$86,138. Also under the contract the Authority 
must pay annually 27.748 percent of the actual 
16-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
annual cost of operation and maintenance. To 
date the Authority has paid $28,668. 
Benefits accrued to Stillhouse Hollow Project: 
Accumulated estimate of flood damages 
prevented through fiscal year 1975 is $8,670,- 
900. 
Conditions at end of fiscal year. Construction 
was initiated in July 1962 and the project was 
ready for beneficial use in February 1968. 
Recreation facilities under Code 710 remain. 
39. THREE RIVERS, TEX. 
Location. The project is located in and adjacent 
to the city of Three Rivers, Live Oak 
County, Texas, midway between San Antonio 
and Corpus Christi, Texas, on the left bank of 
the Frio River, two miles below the mouth of 
the Atascosa River and two miles above the 
confluence with the Nueces River. 
Existing project. The local flood protection 
project consists of an earthfill levee 4.5 miles in 
length and appurtenant water control 
measures. The project was authorized in 1971 
under Section 201 of the 1965 Flood Control 
Act in accordance with the recommendations of 
the Chief of Engineers as contained in House 
Document 92-153. Estimated cost of the project 
is $4,350,000 including $490,000 non-federal 
cost. 
Local cooperation. Prior to initiation of construction, 
local interests will give assurances 
satisfactory to the Secretary of the Army that 
they will: (a) Provide without cost to the United 
States all lands, easements, rights-of-way, and 
borrow areas necessary for construction, 
maintenance, and operation of the project; (b) 
Provide without cost to the United States all 
bridge relocations, except railroad bridges, and 
all buildings, structures, and any other 
alterations of existing structures or improvements 
which may be required for construction 
of the project: (c) Hold and save the 
United States free from damages due to construction 
of the project; (d) Acquire without 
cost to the United States, easements on lands 
adjacent to the city to allow flooding on some 
lands not now in the flood plain, and hold and 
save the United States free from claims as a 
result of this additional flooding; (e) Provide 
assurances that encroachment on interior and 
exterior drainage and ponding areas will not 
be permitted without offsetting the encroachment 
by substitute storage or equivalent pumping 
capacity, without cost to the United 
States; (f) Agree to publicize flood plain information 
in the area concerned and to provide 
this information to zoning and other regulatory 
agencies and public information media for 
their guidance and appropriate action, including 
adoption of such regulations as may be 
necessary to insure compatibility between 
future developments and protection levels 
provided by the project; and (g) Maintain and 
operate all works after completion in accordance 
with regulations prescribed by the 
Secretary of the Army. The city of Three 
Rivers is the local sponsor. 
Operations and results during fiscal year. 
Preconstruction planning was initiated. 
Condition at end of fiscal year. Preconstruction 
Planning 15 percent complete. 
40. TRINITY RIVER AND 
TRIBUTARIES, TEX. 
Location. Seven improvements are in upper 
portion of Trinity River Basin (Benbrook, 
Lavon, Grapevine and Lewisville Lakes, and 
Dallas, Fort Worth and Richland Hills local 
flood protection projects) within a 50-mile 
radius of Dallas, Tex., and two (Navarro Mills 
and Bardwell Lakes) are in Richland- 
Chambers Creek watershed, within 25-mile 
radius of Corsicana, Tex. 
Existing project. All improvements are in 
operation. Information for each project is furnished 
elsewhere in this chapter. Estimated 
cost of improvements is $130,256,840 including 
$6,017,000 local interests contributions for 
water supply storage in reservoirs, and $10,- 
593,900 non-Federal cost on local flood control 
projects. (See Table 16-H regarding flood control 
works included in comprehensive plan and 
local flood protection works.) 
41. WACO LAKE, TEX. 
Location. Dam is on Bosque River, 4.6 river 
miles above its confluence with Brazos River, 
at city of Waco, McLennan County, Tex. 
Existing project. For description of completed 
improvements and authorization act see 
Annual Report of 1969. Estimated cost of project 
is $53,603,000 including $250,000 contributed 
by local interests and $2,500,000 other 
non-Federal cost. 
Local cooperation. Section G of the Flood 
Control Act of December 1944 applies. A contract 
with the Brazos River Authority, a State 
agency, for water supply storage and the contract 
with the city of Waco transferring the existing 
Lake Waco to the Government for their 
water supply storage, was approved by the 
Secretary of the Army on 15 April 1958. To 
date the Authority for their portion of the 
water supply storage has paid $767,341. Also 
under the contract the Authority and the City 
must pay 14.607 and 2.087 percent respectively 
of the actual cost of operation and 
16-16

FORT WORTH, TEX., DISTRICT 
maintenance. To date the Authority has paid 
$295,420 and the City has paid $41,079. 
Operations and results during fiscal year. 
Regular funds: Routine operations and 
maintenance continued. 
Benefits accrued to Waco project: Accumulated 
damages prevented through fiscal 
year 1974 were $41,516,500. 
Condition at end of fiscal year. Construction 
was started in July 1958, and project was 
ready for beneficial use in February 1965. 
Recreation facilities under Code 710 remain. 
42. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS. 
Inspection of completed local flood protection 
projects is made periodically in compliance 
with section 208.10 of title 33, Code of Federal 
Regulations, which contains regulations for 
operation and maintenance of local floodprotection 
works approved by Secretary of the 
Army in accordance with authority in section 
3, Flood Control Act of 22 June 1936. See Table 
16-I for inspections made this fiscal year. 
Inspection costs for fiscal year from regular 
funds for maintenance were $16,045. Total 
costs to 30 June 1975 were $178,370. 
43. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with Flood Control Act of 1944 
expenditures were made for scheduling flood 
control reservoir operations and preparation of 
reservoir regulation manual for Marshall Ford 
Dam, on the Colorado River, near city of 
Austin, Tex., and for preparation of reservoir 
regulation manual for Twin Buttes Dam, on 
Middle and South Concho Rivers near city of 
San Angelo, Tex. Marshall Ford Dam was 
authorized by 1937 River and Harbor Act. Project 
was constructed jointly by Bureau of 
Reclamation and Lower Colorado River 
Authority and was completed during fiscal 
year 1942. Twin Buttes Reservoir was authorized 
for construction by Department of Interior 
by Public Law 152, 85th Congress. Construction 
was initiated in June 1960; closure of dam 
started in June 1962; deliberate impoundment 
was started 23 January 1963. 
Accumulated . damages prevented by 
Marshall Ford Reservoir through fiscal year 
1975 were $62,758,600. During filling stage 
Twin Buttes Reservoir will consist of two 
separate pools, one on South Concho River and 
the other on Middle Concho River and Spring 
Creek. Equalizing channel between these two 
pools is at elevation 1925.0. Costs for fiscal year 
from regular funds for maintenance were $40, 
334. 
44. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 16-C.) 
4o. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 
205, Public Law 858, 80th Congress, as amended 
(preauthorization) 
Fiscal year costs were: Munday, $499,563; 
Laredo, $4,531; and $4,923 for Miscellaneous 
Reports, Texas Local Flood Protection. 
Emergency flood control, hurricane-flood, and 
shore protection activities (Public Law 99, 84th 
Cong., and antecedent legislation) 
Fiscal year costs were $36,873 for advance 
preparation and $64,848 for repair and restoration, 
a total of $101,721. 
1Miulti-Purpose Projects Including Power 
46. SAM RAYBURN DAM AND 
RESERVOIR, TEX. 
Location. Dam is on Angelina River 25.2 
miles upstream from its confluence with 
Neches River and about 10 miles northwest of 
Jasper, Tex. 
Existing project. For description of completed 
improvements and authorization act see 
Annual Report 1969. Estimated cost of project 
is $68,683,000 including $3,000,000 contributed 
by local interests. 
Local cooperation. A contract with the Lower 
Neches Valley Authority, a State agency, to 
contribute $3,000,000 toward the first cost and 
ar. additional $200,000 annually for 50 years 
after completion of the project was approved 
by the Secretary of the Army on 22 January 
1957. Contribution of $3,000,000 was made in 
full and annual payments to date of $1,800,000 
have been made by the Authority. 
A contract with the City of Lufkin for water 
supply storage was approved 27 May 1969 by 
the Secretary of the Army at an estimated cost 
of $220,000. To date the City has paid $19,275. 
Also under the contract the City of Lufkin 
must pay annually 0.692 percent of the annual 
cost of operation and maintenance. To date the 
City has paid $14,106. 
Operations and results during fiscal year. 
Regular funds: Continued routine operation 
ar d maintenance. 
Benefits accrued to Sam Rayburn project: 
16-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Accumulated damages prevented through 
fiscal year 1975 were $39,660,700. 
Condition at end of fiscal year. Construction 
was started August 1956 and project ready for 
beneficial use in March 1965. Recreation 
facilities under Code 710 remain. 
47. WHITNEY LAKE, TEX. 
Location. Dam is on Brazos River, about 442 
miles above mouth of river, 5.5 miles southwest 
of Whitney, Tex., and about 38 miles upstream 
from city of Waco, Tex. (See Geological Survey 
sheets: Waco, Cleburne and Granbury scale 
1:125,000, and Whitney, Blum, and Morgan, 
sc le 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing acts see 
Annual Report for 1962. Estimated cost of project 
is $46,306,000. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds: Continued routine operation 
and maintenance. 
Raise power pool; construction is complete. 
Benefits accrued to Whitney project: Accumulated 
damages prevented through fiscal 
year 1975 were $86,910,600. 
Condition at end of fiscal year. Construction 
of project was started June 1946 and ready for 
flood control use in December 1951. First 
power was placed on-the-line in June 1953. 
Raise power pool is complete. 
General Investigations 
48. SURVEYS 
Fiscal year costs were $604,518 for flood control 
studies, $10,000 for coordination with other 
agencies, a total of $614,518. 
49. COLLECTION AND STUDY OF 
BASIC DATA 
Work was continued under the Flood Plain 
Management Services on the compilation of information 
on floods and potential flood 
damages, including identification of those areas 
subject to inundation. Fiscal year expenditures 
for these activities totaled $285,868. (See Table 
16-J on completed flood plain studies.) 
50. RESEARCH AND 
DEVELOPMENT 
Fiscal year costs were $1,993 for hydrologic 
studies. 
16-18

FORT WORTH, TEX., DISTRICT 
TABLE 16-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
2. Town Bluff Dam- New Work: 
B. A. Steinhagen 
Lake, Tex. 
4. Trinity River 
Project, Tex. 
(Includes Advance 
Participation on High 
Level Bridges) 
6. Abilene Channel 
Improvement, Tex. 
7. Aquilla Lake, Tex. 
8. Aubrey Lake, Tex. 
9. Bardwell Lake, 
Tex. 
10. Belton Lake, Tex. 
11. Benbrook Lake, Tex. 
12. Big Fossil Creek, 
Tex. 
(Federal Funds) 
(Contributed 
Funds) 
14. Canyon Lake, Tex. 
(Federal Funds) 
15. Carl L. Estes 
Dam & Lake 
16. Duck Creek Channel 
Improvement, Tex. 
17. Elm Fork Floodway, 
Tex. 
18. Fort Worth Floodway 
(Clear Fork), Tex. 
19. Fort Worth Floodway 
(West Fork), Tex. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
1,500 
1,500 
250,200 
245,638 
3,224,000 
2,367,579 
99,300 
102,016 
382,700 
397,125 
7,500 
6,887 
263,949 
241,228 
549,200 
455,368 
272,742 
341,722 
500,500 
495,886 
454,842 
319,760 
17,500 
17,500 
344,437 
327,444 
417,275 
87,096 
223,400 
211,341 
(-)114,249 
20,618 
(-)40,161 
403,200 
308,695 
4,968,000 
3,367,033 
265,000 
273,425 
350,000 
337,613 
946 
409,900 
275,742 
42,000 
89,088 
348,900 
341,167 
167,647 
152,401 
458,800 
618,029 
79,000 
75,814 
383,800 
383,151 
970,000 
223,878 
153,000 
156,559 
480,000 425,900 
569,741 340,235 
969,000 800,000 
2,611,436 1,308,442 
310,000 596,000 
305,738 506,697 
383,000 2,500,000 
395,342 663,922 
384,954 370,190 
537,540 343,692 
900 4,255 
49,670 906 
389,636 488,500 
369,965 454,925 
2,000 
22,637 - 
451,000 495,100 
392,059 498,426 
(-)500 - 
2,686 - 
421,000 430,700 
431,415 403,750 
- 430,000 
- 413,128 
(-)870,000 (-)130,275 
49,902 3,322 
25,000 - 
25,514 7,964 
16-19 
6,602,737 
6,602,7371 
4,095,214 
3,995,095 
15,313,212 
14,537,771 
457,002 
457,002 
1,360,300 
1,187,876 
3,805,700 
1,969,577 
10,934,505 
10,934,505 
2,148,987 
2,117,009 
15,949,814 
15,945,5602 
3,750,903 
3,685,330 
12,449,550 
12,449,5503 
4,062,355 
3,993,210 
1,917,100 
1,917,100 
8,900 
8,900 
18,922,5084 
18,922,508 
3,014,784 
2,980,453 
430,000 
413,128 
633,098 
610,295 
662,400 
646,450 
410,751 
410,751 
3,304,839 
3,304,839

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 16-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text 
20. 
Project 
Grapevine Lake, Tex. 
21. Greenville, Tex. 
23. Hords Creek Lake, 
Tex. 
24. Lake Brownwood 
Modification, Tex. 
25. Lakeview Lake, Tex. 
26. Lewisville Dam, Tex. 
27. Lavon Lake, Tex. 
28. Lavon Lake 
Modification & East 
Fork Channel 
Improvement, Tex. 
29. Millican Lake, 
Tex. 
30. Navarro Mills Lake, 
Tex. 
31. 0. C. Fisher Dam 
and Lake, Tex. 
32. Proctor Lake, Tex. 
33. Rutledge Hollow 
Creek Channel 
Improvement, 
Poteet, Tex. 
Total Cost To 
Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Maint. 
Approp. 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
20,500 431,000 
20,027 344,985 
317,829 487,300 
310,966 484,493 
11,900 - 
1,564 10,236 
3,000 - 
6,829 
152,664 200,900 
145,955 176,196 
7,055 16,886 
64,600 - 
73,585 4,056 
607,146 537,000 
466,299 686,799 
10,000 - 
10,000 - 
267,040 409,100 
259,564 348,158 
10,305,162 16,890,000 
7,348,999 9,953,106 
See Little Rock District. 
69,000 - 
13,703 55,297 
212,417 310,600 
192,985 280,860 
449,000 423,400 
487,723 393,039 
2,300 - - - 
2,777 - - - 
214,282 290,300 307,000 318,400 
214,446 275,666 319,141 299,990 
3,000 - - 610 
3,000 - - - 
226,319 284,000 362,921 392,900 
232,081 269,445 375,050 315,729 
- - - 47,410 
- - - 8,373 
9,431,907 
9,431,9079 
2,529,005 
2,481,095 
15,909,687 
15,909,687 
3,281,555 
3,255,291 
14,409,585 
14,408,975 
2,493,772 
2,405,793 
200,120 
113,673 
16-20 
107,000 76,335 
190,328 3,324 
813,795 784,300 
725,568 830,113 
295,000 - 
32,088 29,808 
22,000 - 
22,000 - 
222,808 216,600 
254,206 198,942 
- 250,000 
- 225,180 
90,000 - 
53,573 36,486 
- 168,510 
- 32,911 
675,000 668,220 
597,778 679,649 
449,462 547,300 
496,196 516,355 
6,295,000 2,192,000 
9,412,675 7,503,461 
9,807,756 
9,731,5855 
4,690,414 
4,630,639 
306,900 
73,696 
2,602,367 
2,602,3676 
2,168,909 
2,150,681 
250,000 
225,180 
980,000 
980,000 
18,365,016 
18,229,4177 
5,928,609 
5,854,9998 
12,528,700 
12,528,700 
4,105,209 
4,051,878 
53,269,962 
51,769,032

FORT WORTH, TEX., DISTRICT 
TABLE 16-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
35. San Antonio Channel New Work: 
Improvement, Tex. 
(Federal Funds) 
(Contributed Funds) 
36. San Gabriel River, 
Tex. 
37. Somerville Lake, 
Tex. 
38. Stillhouse Hollow 
Dam, Tex. 
39. Three Rivers, Tex. 
41. Waco Lake, Tex. 
46. Sam Rayburn Dam 
and Reservoir, Tex. 
47. Whitney Lake, Tex. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,029,800 
973,102 
27,000 
27,000 
2,986,100 
2,366,664 
312,648 
317,016 
275,106 
267,442 
6,325 
8,388 
212,656 
236,566 
1,760,000 
540,255 
43,000 
7,403,000 
5,271,281 
498,506 
3102,073 
35',500 
317,499 
6,847 
7,409 
341,400 
285,116 
1,000,000 
2,055,933 
30,000 
73,000 
6,997,000 
7,875,909 
2,500 
191,247 
627,751 
629,214 
811 
419,000 
461,184 
2,6l 
2,8 c 
9,4 
8,8( 
41 
4
3( 
31 
- f 
-
- 4,500 
4,500 
370,872 
363,085 
72,600 
62,058 
1,165,297 
1,179,298 
362,275 
355,594 
641,545 
594,376 
500,0 00 485,673 44 
458,64 32 536,304 4: 
10,54 2 
967,604 
985,76" 
387,00() 
537,37 p 
787,800 
661,122 
(-)25 
1,238,275 1,2 
1,151,807 1,2 
(-)2,400 
72,488 
882,000 1,0( 
1,038,518 9,
55,896 20,465,045 
86,996 20,457,561 
54,000 525,000 
54,000 525,000 
14,642 31,958,142 
00,000 29,464,416 
40,275 25,092,232 
40,156 25,243,204 
93,900 2,775,497 
95,746 2,726,150 
- 19,933,887 
- 19,933,88710 
61,900 1,943,308 
17,574 1,876,874 
60,000 60,000 
59,578 59,578 
(-)896 49,253,471 
- 49,253,47111 
42,500 3,701,826 
14,992 3,656,268 
- 60,502,070 
25 60,502,07012 
39,400 7,891,694 
19,783 7,775,302 
8,510 42,710,605 
- 42,702,09513 
02,800 8,995,376 
40,909 8,918,266 
'Excludes $2,000,000 contributed funds expended. 
2Excludes $47,309 receipts from reconveyance of land, 
deposited to miscellaneous receipts. 
3Excludes $322,346 receipts from reconveyance of land, 
deposited to miscellaneous receipts. 4Excludes $1,422,848 expended for new work from 
contributed funds, including $22,848 "Contributed Funds, 
Other" for installation and operation of gages for leakage 
study. 
5Excludes $146,795 receipts from reconveyance of land 
deposited to miscellaneous receipts, and $2,040,026 for new 
work expended from contributed funds. 6Excludes $105,079 expended from contributed funds. 
7Excl ude:s receipts from reconveyance of land of 
$426,606 which were deposited to miscellaneous receipts, 
and $3,6'76,661 for new work expended from contributed 
funds. 8Inclua des $130,000 under appropriation 96X5125. 
9Exc;ludes $300,000 expended from contributed func7. 
'0 Inclludes receipts from disposals and revocation of 
funds re lated thereto. 
"Ex ludes $2,750,000 expended for contributed funds. 
12Incl udes $400,000 ARA funds. Excludes $3 million 
expended from contributed funds. 
'3Exfludes ,$188,282 receipts from reconveyance of 
lands de1 posited to miscellaneous receipts. 
16-21

TABLE 16-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Dam A Lake, Neches River, Texas' 1952 21,700 - 
Rockland Lake, Neches River, Texas' 1952 510,200 - 
Inactive. 
OTHER AUTHORI:EED FLOOD CONTROL PROJECTS 
TABLE 16-C (See Section 44 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Belton Lake, Leon River, Tex.(Mod)2' 
Beals Creek, Big Spring, Tex. 7 
Big Sandy Lake, Sabine River, Tex.5 
Blieders Creek Lake, Tex.3 1965 37,600 
Brownwood Channel Improvement, Tex.' 
Clopton Crossing, Tex.8 
Gonzales Lake, San Marcos River, Tex. 4 
Lake Fork Lake, Sabine River, Tex.' 
Navasota Lake, Navasota River, Tex.' 
Pecan Bayou Lake, Pecan Bayou, Tex.' 
Running Water Draw, Plainview, Tex. 6 
'Authorized by Flood Control Act of 1968. Awaiting 
availability of funds. 
'Deferred for restudy due to lack of economic 
justification. Authorized by Flood Control Act of 1954. 
'Inactive. Authorized by Flood Control Aclt of 1960. 
4Inactive. Authorized by Flood Control Act of 1954. 
5Authorized by Flood Control Act of 1970. 6Authorized by House Document 192, 91st/1 Congress. 7Authorized by House Document 153, 92nd/1 Congress. 
8Water Resources Development Act of 1974. 
16-22

FORT WORTH, TEX., DISTRICT 
NECHES AND ANGELINA RIVERS, TEXAS: FLOOD CONTROL 
WORKS INCLUDED IN COMPREHENSIVE PLAN 
TABLE 16-D (See Section 1 of Text) 
Rockland Sam Rayburn Dam A Town Bluff 
Stream Neches Angelina Neches Neches 
Nearest city Rockland Jasper Horger Town Bluff 
Drainage area square miles 3,557 3,449 3,758 7,573 
River-miles above mouth of Neches River 160.4 151.3 142 113.7 
Height (feet) 106 120 49 45 
Type Earthfill Earthfill Concrete and earth Concrete and earth 
Flood control storage capacity (acre-feet) 1,020,100 1,145,000 None None 
Power and regulation of flow (acre-feet) 1,125,500 1,400,600 Pondage 77,600 
Powerhead and sediment reserve (acre-feet) 1,141,700 1,452,000 None 16,600 
Total storage (acre-feet) 3,287,300 3,997,600 Pondage 94,200 
Power development (kw.) 13,500 52,000 2,700 2,935 
Estimated cost (1975) $46,300,0001 $68,683,0002 $3,220,0001 $9,888,0003 
'Estimated cost as of July 1954. 
2Includes $3 million contributed funds. 
'Includes $2 million contributed funds. 
NOTE: See individual reports for further details. 
16-23

BRAZOS RIVER AND TRIBUTARIES, TEXAS: 
FLOOD CONTROL WORKS INCLUDED IN BASINWIDE PLAN 
TABLE 16-E (See Section 13 of Text) 
Proctor 
Leon 
Proctor 
1,265 
238.9 
86 
Concrete 
and earth 
Modification 
of Belton 
Leon 
Belton 
3,560 
16.7 
192 
Earthfill 
Stillhouse 
Hollow 
Lampasas 
Belton 
1,318 
16.0 
200 
Earthfill 
Granger 
San Gabriel 
Granger 
709 
31.9 
115 
Earthfill 
North Fork 
San Gabriel 
Georgetown 
246 
4.3 
165 
Rockfill 
South Fork 
San Gabriel 
Georgetown 
123 
4.7 
152 
Rockfill 
Somerville 
Yegus Creek 
Somerville 
1,006 
20 
80 
Earthfill 
Aquilla 
Aquilla 
Aquilla 
294 
20.7 
97 
Concrete 
and earth 
Millican 
Navasota 
Navasota 
2,120 
24.1 
83 
Concrete 
and earth 
Navasota 
Navasota 
Norman Lee 
1,341 
83.4 
111 
Concrete 
and earth 
310,100 610,000 390,600 162,200 87,600 45,700 337,700 111,500 784,800 550,700 
Dams 
and 
Lakes 
Stream 
Nearest city 
Drainage Area 
(square miles) 
Miles above 
mouth 
Height (feet) 
Type 
Flood control 
storage 
capacity 
(acre-feet) 
Water-supply 
storage 
capacity 
(acre-feet) 
Sedimentation 
reserve 
capacity 
(acre-feet) 
Capacity, total 
(acre-feet) 
Estimated 
total cost 
(1975) 
Waco 
Bosque 
Waco 
1,652 
4.6 
140 
Concrete 
and earth 
553,300 
104,100 
69,000 
726,400 
31,900 
630,400 
44,100 
244,200 
14,000 
130,800 
143,900 59,700 680,200 1,315,400 
8,000 25,900 
82,600 507,500 
28,100 
199,300 
$53,603,000' $16,249,000 $8,290,0002 3 $23,670,000 $62,600,000 $28,600,000 $26,800,000 $30,227,000 $47,800,000 
92,400 
1,557,400 
69,500 
1,935,600 
$160,000,000 $196,000,000 
'Includes $250,000 non-Federal contribution and $2,500,000 other non- 
Federal costs. 
2Includes undetermined amount of local contribution for conservation 
storage. 
'Deferred for restudy. Estimate as of July 1958. 
372,700 204,900 37,900 29,200 28,900 
81,900 
1,097,600 
31,400 
32,700 
374,200 
O
O 
C
0
C
y
�3 x
x
C
z
z

FORT WORTH, TEX., DISTRICT 
GUADALUPE AND SAN ANTONIO RIVERS, TEXAS: 
FLOOD CONTROL WORKS INCLUDED IN PLAN OF IMPROVEMENTS 
TABLE 16-F (See Section 22 of Text) 
Gonzales Dam and Lake1 
Stream 
Nearest city 
Drainage area square miles 
Distance above mouth (miles) 
Height (feet) 
Type 
Flood control storage capacity (acre-feet) 
Water-supply storage capacity (acre-feet) 
Sedimentation reserve capacity (acre-feet) 
Capacity, total (acre-feet) 
Estimated cost: 
Construction 
Lands and damages 
Total (July 1964) 
San Marcos 
Gonzales 
1,344 
5.4 
102 
Concrete and earth 
413,200 
100,800 
25,000 
539,000 
$21,834,000 
11,566,000 
$33,400,000 
Local Flood Protection Works 
Miles Estimated 
Above Type Lands and Cost 
Location Stream Mouth Structure Construction Damages (1975) 
San Antonio San Antonio River 221.8 Channel $43,900,000 $48,500,000 $92,400,0002 
and tributaries 237.3 rectification 
'Project classified inactive. 2Includes $49,700,000 non-Federal costs. 
SABINE RIVER AND TRIBUTARIES, TEXAS 
FLOOD CONTROL WORKS INCLUDED IN BASINWIDE PLAN 
TABLE 16-G (See Section 34 of Text) 
Dams and Lakes Carl L. Estes Lake Fork Big Sandy 
Stream Sabina Lake Fork Big Sandy 
Nearest town Grand Saline Quitman Big Sandy 
Drainage area (square miles) 1,146 507 196 
Miles above mouth 475.6 28.1 15.3 
Height 90.5 106.5 94.5 
Type Concrete and earth Concrete and earth Earth 
Flood control storage capacity (acre-feet) 984,500 472,600 196,000 
Water supply storage capacity (acre-feet) 370,100 621,500 215,300 
Sedimentation reserve capacity (acre-feet) 20,400 18,900 6,900 
Total capacity (acre-feet) 1,375,000 1,113,000 418,200 
Estimated cost (1975) $155,000,000 $111,000,000 $60,900,000 
Local Flood Protection Works 
Miles 
Above Estimated Cost 
Location Stream Mouth Type Structure (1975) 
Greenville Long Branch 1.5 to 5.0 Channel Rectification $ 852,000 
16-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
FLOOD 
TABLE 16-H 
TRINITY RIVER AND TRIBUTARIES, TEXAS: 
CONTROL WORKS INCLUDED IN COMPREHENSIVE PLAN 
(See Section 40 of Text) 
Dams and Lakes Benbrook Lavon Grapevine Lewisville Navarro Mills Bardwell 
Stream Clear Fork East Fork Denton Creek Elm Creek Richland Creek Waxahachie 
Nearest city Benbrook Lavon Grapevine Lewisville Dawson Ennis 
Drainage area (sq. miles) 429 770 695 1,600 320 178 
Miles above mouth 15.0 55.9 11.7 30.0 63.9 5.0 
Height (feet) 130 69 137 125 81.7 82.4 
T1ype Earthfill Concrete Earthfill Earthfill Earthfill Earthfill 
gravity 
and earth 
Flood control storage 170,350 275,600 238,250 525,200 143,200 79,600 
capacity (acre-feet) 
Water supply storage 72,500 100,000 161,250 436,000 53,200 42,800 
capacity (acre-feet) 
Sedimentation reserve 15,750 47,800 36,000 28,500 15,800 17,600 
capacity (acre-feet) 
Capacity, total (acre-feet) 258,600 423,400 435,500 989,700 212,200 140,000 
Estimated Cost: 
Total (1975) $14,544,000 $15,470,000 $18,896,0001 $27,527,0002 $12,546,0003 $12,941,000 
'Includes $2,040,000 non-Federal costs. 
2Includes $3,677,000 non-Federal costs. 
3Includes $300,000 non-Federal costs. 
Local Flood Protection Works 
Miles 
Above Estimated Cost 
Location Stream Mouth Type Structure (1975) 
Fort Worth Clear and West Forks 560 Levee and channel clearing $16,366,8404 
Dallas Elm Fork and Trinity River 505 Levee channel clearing and 9,848,0005 
modification of interior drainage. 
Richland Hills Big Fossil Creek 1.5 Levee and channel improvement 2,118,0006 
and interior drainage structures. 
4Includes $8,837,000 non-Federal costs. 
Ilncludes $1,498,000 non-Federal costs. 
6Includes $ 200,900 non-Federal costs. 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
TABLE 16-I (See Section 42 of Text) 
Location Dates of Inspection 
Dallas Floodway, Texas 11 Dec 74 
Fort Worth Floodway, Texas 3 Dec 74 
Pleasanton Floodway, Texas 10 Dec 74 
Completed portions of San Antonio Channel 
Improvements, Texas 19-21 Nov 74 
Big Fossil Creek, Texas 5 Dec74 
Poteet Channel Improvement, Texas
16-26

FORT WORTH, TEX., DISTRICT 
FLOOD PLAIN INFORMATION STUDIES COMPLETED DURING FISCAL YEAR 
TABLE 16-J (See Section 44 of Text) 
Location Requesting Agency Date Corpleted Federal Cost 
Marine Creek, Texas Water Development Board Sep 1974 $25,300 
Fort Worth, Tex. 
Hackberry Creek & Texas Water Development Board De: 1974 30,000 
Cottonwood Branch, 
Dallas Co, Tex. 
Colorado River & Texas Water Development Board Feb 1975 38,000 
County Club Creek 
Austin, Tex. 
Marys & South Mary's Creeks, Texas Water Development Board 'May 1975 28,000 
Fort Worth, Tex. 
Cienegas Creek & Texas Water Development Board May 1975 28,000 
Cantu Branch, Del Rio, Tex. 
San Antonio River Texas Water Development Board Jun 1975 33,000 
(County Line to IH 410) 
xar County, Tex. 
16-27

ALBUQUERQUE, N. MEX. DISTRICT* 
The district comprises watershed of Canadian 
River and tributaries entering river west of 
Texas-New Mexico State line; watershed of 
Arkansas River and tributaries entering river west 
of and including Walnut Creek, Kans.; watershed of 
Rio Grande and tributaries entering river west of 
and including Pecos River and its tributaries; and 
watershed of Mimbres River and its tributaries in 
New Mexico. 
IMPROVEMENTS 
Flood Control 
Page 
1. Albuquerque Diversion Channels 
Project, N. Mex. ........... ..... 17-1 
2. Alpine, Tex ....................... 17-2 
3. Arkansas River and Tributaries above 
John Martin Dam, Colo ............. 17-2 
3A. LaJunta (Anderson and King Arroyos), 
Colo. .............................. 17-3 
3B. Florence, Colo. ..................... 17-3 
3C. Portland, Colo...................... 17-4 
3D. Pueblo (Dry Creek), Colo ............ 17-4 
3E. Arkansas River Floodway, Brewster to 
Florence, Colo ...................... 17-4 
3F. Arkansas River Channelization Test 
Reach ............................. 17-4 
3G. La Junta (Reach 2-Urban), Colob........ 17-5 
3H. Fountain Lake, Colo. ............... 17-5 
4. Conchas Lake, N. Mex. ............. 17-5 
5. Dodge City, Kansas ............... 17-6 
6. E1Paso, Tex. ...................... 17-7 
7. Great Bend, Kans. .................. 17-7 
8. John Martin Reservoir Project, Colo. .. 17-8 
9. Las Animas, Colo................... 17-8 
10. Las Cruces, N. Mex ................. 17-9 
11. LosEsteossLake, N. Mex............ 17-9 
12. Pecos, Tex.......................17-10 
Flood Control (cont.) 
Page 
13. Rio Grande Basin, N. Mex............ 17-10 
13A. Abiquiu Dam, Rio Chama, N. Mex. .... 17-11 
13B. Cochiti Lake, N. Mex. ............. 17-11 
13C. Galisteo Dam, N. Mex. ............. 17-11 
13D. Jemez Canyon Dam, N. Mex. ......... 17-12 
13E. Rio Grande Floodway, N. Mex. ...... 17-12 
13F. Truth or Consequences Unit 
(Hot Springs), N. Mex................ 17-13 
14. Trinidad Lake, Colo ................. 17-13 
15. Two Rivers Dam, N. Mex............. 17-14 
16. Inspection of completed flood 
control projects ................... 17-14 
17. Scheduling flood control 
reservoir operations ............... 17-14 
18. Other authorized flood 
control projects ................... 17-15 
19. Flood control work under 
special authorizations .............. 17-15 
General Investigations 
20. 
21. 
22. 
23. 
Surveys............. ......... 17-15 
Collection and study of basic data ...... 17-15 
Research and development ........... 17-15 
Inventory of dams ................... 17-15 
Flood Control 
1. ALBUQUERQUE DIVERSION 
CHANNELS PROJECT, N. MEX. 
Location. In area which comprises watersheds of 
ephemeral streams entering a 15-mile reach of Rio 
Grande from the east at Albuquerque, N. Mex., 
and vicinity. Combined drainage area of tributaries 
is about 276 square miles. Sandia Range of the 
Rocky Mountains, which is about 12 miles east of 
Rio Grande, forms eastern border of watersheds. 
Crest of mountain range rises more than a mile over 
river to an elevation of 10,692 feet above mean sea 
level. (See Geological Survey Map, Albuquerque, 
N. Mex., quadrangle, scale 1:62,500.) 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear 
at the end of this chapter. 
17-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. For description of complete 
improvement and authorizing legislation see 
Annual Report for 1973. Federal cost is 
$17,300,000. Non-Federal cost, including required 
cash contribution of $530,000 is $11,060,000. 
Local cooperation. For details of local 
cooperation requirements see Annual Report for 
1973. 
Operations and results during fiscal year. 
Correction of design deficiencies in North Diversion 
Outlet Works were completed. Ordinary 
maintenance and operation continued. The North 
and South Diversion Channels prevented an 
estimated $255,600 annual flood damages during 
FY 1974. The estimated total accumulated flood 
damages prevented through FY 1974 amount to 
$4,706,000. Peak floodflows recorded during FY 
1975 were: North Diversion Channel near Alameda, 
3,000 c.f.s. (1,150 acre feet) on 20 Sept. 1974. No 
information available for South Diversion Channel 
at this time. 
Condition at end of fiscal year. Construction of 
the north and south diversion channels began in 
March 1965, and was completed in March 1972. 
2. ALPINE, TEX. 
Location. At Alpine, Paisano and West Moss 
Creeks in the vicinity of Alpine, Texas. (See 
Geological Survey Map, Alpine, Tex., quadrangle, 
scale (1:24,000). 
Existing project. The plan of improvement is an 
earthfill dam 6,300 feet long and 77 feet high on 
Alpine Creek for flood control, industrial and 
municipal water supply and recreation. A storage 
capacity of 12,710 acre-feet at spillway crest would 
include 4,530 acre-feet for flood control 5,100 
acre-feet for water supply, 1,000 acre-feet for 
recreation and 2,080 acre-feet for sediment 
retention. West Moss Creek flows to the reservoir 
would be controlled by a saddle dam 2,100 feet long 
and 42 feet high. A diversion channel would 
intercept flows up to 4,000 c.f.s. from Paisano 
Creek, carry them about three miles, and empty 
into Alpine Lake. A diversion channel would also 
intercept West Moss Creek flows and diver them 
into the saddle dam area. A conveyance channel 
3,900 feet long between the West Moss and Alpine 
Creeks would prevent permanent pooling behind 
the saddle dam on Moss Creek. Estimated Federal 
cost is $5,630,000. (See Table 17-B for authorizing 
legislation.) 
Local cooperation. Prior to construction, local 
interests must furnish assurances satisfactory to 
the Secretary of the Army they will: (1) acquire all 
lands, easements, rights-of-way and relocations, 
except railroads (all relocations in compliance with 
PL 91-646); (2) administer, maintain and operate 
the works after completion in accordance with 
regulations; (3) prior to construction, enter into a 
contract whereby all construction and interest costs 
incurred by the Federal Government allocated to 
water supply will be repayed in accordance with the 
Water Supply Act of 1958, as amended; (4) pay, 
contribute in kind, or repay with interest, one-half 
of the separable first cost of the project allocated to 
recreation and one-fourth of the separable first cost 
of the project allocated to fish and wildlife 
enhancement. Included therein is an amount for 
lands, easements, rights-of-way, and relocations for 
which will be given credit toward their 
reimbursable half of the separable first cost of 
recreation and one-fourth of the separable first cost 
of the project allocated to fish and wildlife 
enhancement; (5) bear all costs of operation, 
maintenance, and replacement of flood control, 
water supply, recreation and fish and wildlife areas 
and facilities on an average annual basis; (6) provide 
storage rights and hold and save the United States 
free from water rights claims due to construction 
and operation of the project. (Non-Federal first 
cost is $440,000.) 
Operations and conditions at the end of the fiscal 
year. Not applicable. 
3. ARKANSAS RIVER AND 
TRIBUTARIES ABOVE JOHN 
MARTIN DAM, COLO. 
Location. Improvements are on Arkansas River 
and tributaries in Colorado. More definite locations 
and descriptions of individual projects are in 
following paragraphs and individual reports by 
projects. 
Existing project. The Water Resources 
Development Act of 1974 authorized flood control 
phase of comprehensive plan of development of 
water resources of Arkansas River basin above 
John Martin Dam in Colorado. (PL 93-251, 93rd 
Congress, H.R. 10203 March 7, 1974) The plan of 
improvement consists of channel and levee 
improvements on the main stem of the Arkansas 
River from Brewster to Florence (a distance of 6 
miles) and from Pueblo to Las Animas (a distance of 
76 miles); Fountain Dam and Lake; and local 
protection projects at Florence, Portland, Pueblo 
(Dry Creek), and La Junta (Anderson and King 
Arroyos). It was recommended that along with the 
construction of the local protection project of La 
Junta the proposed channelization project include a 
reach, designated as reach 2-urban, to provide 
complete flopod protection for the city and urban 
area of La Junta. In addition, further studies will be 
made taking into consideration all structural and 
non-structural alternatives for flood-control and 
allied purposes to determine the environmental 
impact of the proposed improvements on the main 
stem of the Arkansas River from Pueblo to Las 
17-2

ALBUQUERQUE, N. MEX., DISTRICT 
Animas. These studies would be conducted prior to 
detailed design and construction of the 
improvements, and a report would be submitted to 
Congress dealing with the environmental effects of 
the improvements and alternatives. Also 
authorized was the construction of a short reach of 
the channel project to be used as a part of the study 
to evaluate the environmental impact of the channel 
improvement. The reach selected as most 
appropriate for the study was the 7-mile reach 
upstream from the local protection project at La 
Junta. This project is designated as Arkansas River 
Channelization Test Reach. (See Table 17-B for 
authorizing legislation.) 
Local cooperation. Prior to construction, local 
interests furnish assurances satisfactory to the 
Secretary of the Army, for the local protection 
projects at Florence, Portland, Pueblo (Dry 
Creek), La Junta (Anderson and King Arroyos), La 
Junta (reach 2-urban, Arkansas River), and 
Arkansas River Floodway, Brewster to Florence, 
meet the following requirements: (1) acquire 
easements and rights-of-way necessary for 
construction of the project, including easements 
required for flood zoning purposes in ponding areas; 
(2) hold and save the United States free from 
damages due to the construction works and free 
from claims as a result of flooding from residual 
interior drainage during operation of the project; 
(3) maintain and operate the works after completion 
in accordance with regulations prescribed by the 
Secretary of the Army; (4) make any alteration to 
existing improvements, other than railroad bridges 
and approaches connected therewith; (5) 
periodically inform all concerned that some flooding 
will continue to occur due to flows greater than 
design magnitude; (6) prohibit encroachment on the 
capacities of the interior drains and ponding areas 
and the flood-carrying capacities of the improved 
channels, and if ponding areas and capacities are 
impaired, provide substitute storage or equivalent 
pumping capacity; (7) take steps to prevent 
encroachment upon existing defined waterways 
tributary to the project, by zoning or other means, 
such as enlargement or other modification of the 
existing waterway facilities, to prevent minor flood 
problems on these tributary waterways from 
developing into problems of serious proportions; (8) 
provide guidance and leadership in preventing 
unwise and uneconomical future development of the 
flood plain areas by encouraging prudent use of 
floodproofing, land regulation planning, or other 
flood plain management techniques to reduce flood 
losses; and (9) hold and save the United States free 
from water right claims due to construction and 
operation of the project. For additional 
requirements see individual projects on following 
pages. 
All operations and costs for projects in authorized 
plan are in individual reports following. 
3A. LA JUNTA (ANDERSON AND KING 
ARROYOS), COLO. 
Location. Anderson and King arroyos, 
tributaries of the Arkansas River at La Junta, 
Otero County, Colorado. (River Mile 1,198.1 above 
the mouth) (See Geological Survey Map, La Junta, 
quadrangle, scale 1:24,000.) 
Existing Project. Plan of improvement is to 
provide approximately 9,490 feet of channel 
improvements for Anderson and King arroyos to 
safely convey their flood flows through the urban 
areas of La Junta to the Arkansas River. This 
project and the Arkansas River channelization 
project (reach 2-urban, Arkansas River) are needed 
to fully solve La Junta's flood problems. Estimated 
Federal cost is $1,600,000. (See Table 17-B for 
authorizing legislation.) 
Local cooperation. See the general requirements 
of local cooperation in Section 3. Estimated 
non-Federal cost is $150,000. 
Operation and condition at the end of the fiscal 
year. Not applicable. 
3B. FLORENCE, COLO. 
Location. At Florence, Fremont County, 
Colorado, on the Arkansas River. (See Geological 
Survey Maps, Canon City and Florence, 
quadrangles, scale 1:24,000.) 
Existing project. Consists of a single-purpose 
flood control system of detention dams, diversion 
dikes, and channels to collect, regulate, and 
discharge flood water runoff into The Arkansas 
River. The plan of improvement consists of four 
elements: Chandler Creek Diversion to Oak Creek 
Reservoir, Oak Creek Dam and Reservoir, Oak 
Creek Outfall Channel, and Coal Creek Dam and 
Reservoir. 
Oak Creek Dam, about 2.3 miles upstream from 
the Oak Creek and the Arkansas River confluence, 
will be an earthfill structure 4,440 feet long and 118 
feet maximum height. The spillway will be 1,650 
feet wide with an uncontrolled outlet conduit of 8.5 
feet in diameter. The flood storage of 17,160 
acre-feet at spillway crest elevation, includes 1,600 
acre-feet for sediment. A 2,600-foot long Chandler 
Creek diversion channel would be constructed 
adjacent to a dike 2,100 feet in length to convey 
flood waters from Chandler Creek to Oak Creek 
dam. 
Coal Creek Dam, about 1.3 miles from the 
confluence of Coal Creek and the Arkansas River 
will be an earthfill structure 1,230 feet long, and 75 
feet high. The spillway width will be 500 feet and 
the uncontrolled outlet conduit is 4-foot diameter. 
The flood control storage will be about 5,660 
acre-feet at spillway crest elevation, including 420 
acre-feet for sediment. Coal Creek Dam flows 
17-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
would follow Coal Creek to the Arkansas River. 
Estimated Federal cost is $7,270,000. (See Table 
17-B for authorizing legislation.) 
Local cooperation. In addition to the general 
requirements of local cooperation in Section 3, 
prevent encroachment on the diversion and outlet 
channels and maintain: (a) the Oak Creek outlet 
channel design capacity of 3,300 c.f.s.; (b) the Coal 
Creek outlet design channel capacity of 450 c.f.s. to 
the existing Coal Creek floodway; and the capacity 
of the existing Coal Creek floodway to at least 1,500 
c.f.s. through the city of Florence. Estimated 
non-Federal cost is $940,000. 
Operations and condition at the end of the fiscal 
year. Not applicable. 
3C. PORTLAND, COLO. 
Location. At Portland, Fremont County, 
Colorado, on the right bank of the Arkansas River 
at river mile 1,318.0 above the mouth. (Geological 
Survey Map, Florence, quadrangle, scale 1:24,000.) 
Existing project. The plan of improvement is to 
provide a levee approximately 3,380 feet long on 
the right bank of the river. A 200 foot long floodwall 
would be required to protect the Portland water 
works where right-of-way is restricted. 
Channelization of the Arkansas River would 
require excavation for 3,250 feet of channel with a 
base width of 150 feet to 260 feet. A short levee 
would be constructed between State Highway 120 
bridge and D&RGW railroad bridge to prevent 
floodflows on Hardscrabble Creek from entering 
Florence. The Hardscrabble Creek channel would 
be enlarged at the railroad bridge and the bridge 
lengthened 140 feet. Estimate of Federal cost is 
$1,090,000. (See Table 17-B for authorizing 
legislations.) 
Local cooperation. See general requirements for 
local cooperation in Section 3. Estimated 
non-Federal cost is $60,000. 
Operations and results at the end qf the fiscal 
yea r. Not applicable. 
3D. PUEBLO (DRY CREEK), COLO. 
Location. At Pueblo, Pueblo County, Colorado 
on Dry Creek and Fountain Creek which join the 
Arkansas River at Pueblo. Fountain Creek enters 
the Arkansas River at river mile 1,283.2 above the 
mouth. (Geological Survey Map, Pueblo, 
quadrangle, scale 1:25,000.) 
Existing project. Plan of improvement is to 
provide levee and channel improvement on Dry 
Creek. Dry Creek will be widened to a 150-foot 
bottom for 3,800 feet above the mouth. Levees will 
be required along both banks of the channel for 
about 2,000 feet. Riprap channel stabilizers, placed 
at intervals of 500 feet would hold the design grade 
of the channel. The estimated Federal cost is 
$153,000. (See Table 17-B for authorizing 
legislation.) 
Local cooperation. See general requirements of 
local cooperation in Section 3. Estimated 
non-Federal cost is $23,000. 
Operations and results at the end of the fiscal 
year. Not applicable. 
3E. ARKANSAS RIVER FLOODWAY 
BREWSTER TO FLORENCE, COLO. 
Location. A six mile reach on the Arkansas River 
from Brewster to Florence, Colorado. (See 
Geological Survey Map, Canon City, quadrangle, 
scale 1:24,000.) 
Existing project. Plan of improvement will 
provide about 32,280 feet of levee along the south 
bank of the Arkansas River beginning about 3.5 
miles above Florence and terminating about 2.5 
miles downstream at the mouth of Cocklebur 
Creek. The levee will average 8 feet in height and 
the interior drainage will flow through a 5-mile 
long, 10-foot bottom width landslide channel, and 
empty into the Arkansas River at State Highway 
67. Estimated Federal cost is $951,000. (See Table 
17-B for authorizing legislation.) 
Local cooperation. In addition to the general 
requirements in Section 3, local interests are to 
contribute in cash 1.25 percent of the total first cost 
of Federal construction of the floodway and major 
drainage project. Estimated non-Federal cost is 
$299,000. 
Operation and conditions at the end of the fiscal 
year. Not applicable. 
3F. ARKANSAS RIVER CHANNELIZATION 
TEST REACH. 
Location. Beginning at the upstream end of the 
La Junta Local Protection Project and extending 
approximately 7 miles upstream on the Arkansas 
River. (Geological Survey map, La Junta, 
quadrangle, scale 1:24,000.) 
Existing project. Plan of improvement is a 7 mile 
reach of Arkansas River Channelization. This reach 
will include flood control levees with tiebacks and 
landside drains of sufficient length to test their 
water salvage capabilities. One oxbow fishery and 
an area suitable for wildlife management studies 
are included. This pilot study will show the 
environmental impact of channelization and related 
works on the river's physical appearance and 
conditions in the control of floods and salvage of 
water. Remedial measures will be proposed to 
enhance or preserve unique environmental 
elements affected by the channelization. 
Environmental groups, individuals, state and local 
governments will be invited to participate in 
determining the environmental impact of the 
channelization. Estimated Federal cost is 
17-4

ALBUQUERQUE, N. MEX., DISTRICT 
$4,886,000. (See Table 17-B for authorization 
legislation.) 
Local cooperation. The general requirements for 
local cooperation in Section 3 except article (7) and 
the following additional articles: (1) provide a cash 
contribution in the amount of 0.75 percent of the 
total cost of Federal construction of the flood 
control and major drainage project, presently 
estimated at $36,000; (2) allow public access to 
recreation and fish and wildlife areas provided by 
the project; (3) pay, contribute in kind, or repay 
(which may be through user fees) with interest, 
one-half of the separable first cost of the project 
allocated to recreation and fish and wildlife 
enhancement; and (4) bear all costs of operation, 
maintenance, and replacement of recreation and 
fish and wildlife areas and facilities, estimated on an 
average annual basis. Estimated non-Federal cost 
is $3,324,000. 
Operations and conditions at the end of the fiscal 
year. Not applicable. 
3G. LA JUNTA (REACH 2-URBAN), 
COLO. 
Location. At La Junta, Otero County, Colorado, 
and is on both banks of the Arkansas River. 
(Geological Survey Map, La Junta, quadrangle, 
scale 1:24,000.) 
Existing project. Plan of improvements at La 
Junta and vicinity include the construction of a 
portion of the Arkansas River Channelization 
through La Junta to safely convey the river 
floodflows through the city. Improvements include 
a north bank levee 3 miles long with an upstream tie 
back of 1,600 feet and a downstream tie back of 
4,000 feet. The south bank levee will be 2 miles long 
with a downstream tie back levee. The upstream 
levee ties into the Anderson Arroyo. The upper 2 
miles of the channel will be widened to 1,500 feet, 
however, the lower 1.2 miles, will be concrete lined 
through a highly developed area, with a bottom 
width of 800 feet. Estimated Federal cost is 
$5,654,000. (See Table 17-B for authorizing 
legislation.) 
Local cooperation. In addition to the general 
requirements for local cooperation in Section 3 and 
the following: (1) provide a cash contribution in the 
amount of 0.11 percent of the total cost of Federal 
construction of the flood control and major drainage 
project; (2) allow public access to recreation and fish 
and wildlife areas provided by the project; (3) pay, 
contribute in kind, or repay (which may be through 
user fees) with interest, one-half of the separable 
cost of the project allocated to recreation and fish 
and wildlife management; (4) bear all costs of 
operation, maintenance, and replacement of 
recreation and fish and wildlife areas and facilities, 
estimated on an average annual basis. Estimated 
non-Federal cost is $3,462,000. 
Operations and conditions at the end of the fiscal 
year. Not applicable. 
3H. FOUNTAIN LAKE, COLO. 
Location. About 1.5 miles upstream from Pueblo, 
Colorado on Fountain Creek. (Geological Survey 
Map, Pueblo, quadrangle, scale 1:125,000.) 
Existing project. Plan of improvement is an 
earthfill dam about 12,905 feet long and rising 172 
feet above the stream bed. The storage capacity of 
the project would be 247,000 acre-feet of which 
187,000 acre-feet would be for flood control, 40,000 
acre-feet for sediment retention, and 20,000 
acre-feet for recreation and fish and wildlife. An 
uncontrolled, concrete, ogee-type service spillway 
will be located in the right abutment. The outlet 
conduit will be a 12-foot diameter concrete 
structure with vertical hydraulic gates. Estimated 
Federal cost is $60,000,000. (See Table 17-B for 
authorizing legislation.) 
Local cooperation. Prior to construction, local 
interests must furnish assurances satisfactory to 
the Secretary of the Army that they will in 
accordance with the Federal Water Project 
Recreation Act; (1) administer land and water areas 
for recreation and fish and wildlife enhancement; (2) 
pay, contribute in kind, or repay (which may be 
through user fees) with interest, one-half of the 
separable cost allocated to recreation and fish and 
wildlife enhancement (excluding the cost of water 
and water rights needed for the project); (3) bear all 
costs of operation, maintenance, and replacement of 
recreation and fish and wildlife lands and facilities, 
estimated on an average annual basis. (4) Provide 
the water required for initial filling and 
replenishment of the recreation pool by purchase of 
water or water rights in a manner consistent with 
Federal and State laws, to assure effective 
operation of the project for recreation and fish and 
wildlife enhancement, with the provision that 
one-half of the cost thereof will be credited against 
the non-Federal obligation for assuming one-half 
the separable costs for recreation and fish and 
wildlife enhancement. (5) Prevent encroachments 
on the channel of Fountain Creek below the project 
and maintain a minimum channel capacity of 15,000 
c.f.s. (6) Hold and save the United States free from 
water rights claims due to construction and 
operation of the project. Hold and save the United 
States free from damage due to construction and 
operation of the project. Estimated non-Federal 
cost is $1,100,000. 
Operations and conditions at the end of the fiscal 
year. Not applicable. 
4. CONCHAS LAKE, CANADIAN 
RIVER, N. MEX. 
Location. Dam is in San Miguel County, N. Mex., 
on Canadian River, about one-fourth mile 
17-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
downstream from confluence of Canadian and 
Conchas Rivers. (See Geological Survey State map 
of New Mexico, scale 1:500,000, and Geological 
Survey topographic map, Tucumcari quadrangle, 
scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
Annual Report for 1973. Federal cost was 
$15,811,171, including $2,279,326 for initiating 
construction of project under authority of 
Emergency Relief Appropriation Act of 1935. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Operation of reservoir continued. Reservoir was 
operated for storage of floodwaters and releases for 
irrigation purposes. No flood damages were 
prevented during fiscal year 1974; however, 
$63,800 sediment damages were prevented. 
Estimated total accumulated flood and sediment 
damages prevented by project through fiscal year 
1974 were $1,026,900. Estimated irrigation benefits 
for fiscal year 1974 were $369,800. Estimated total 
accumulated irrigation benefits through fiscal year 
1974 were $6,362,600. Pool evaluation at start of 
fiscal year was 4180.47 feet with corresponding 
storage of 176,519 acre-feet. Total releases for fiscal 
year were 76,439 acre-feet. Releases of 72,802 
acre-feet were made to Arch Hurley Conservancy 
District and 1,769 acre-feet to Bell Ranch. Pool 
elevation on June 30, 1975 was 4,165.78 feet with 
corresponding storage of 107,608 acre-feet. 
Sediment deposition during the year was 340 
acre-feet. 
Condition at end of fiscal year. Existing project 
was essentially complete in 1940. Reservoir and 
appurtenances are in good condition and in 
operation. Irrigation of some lands under project 
was begun in November 1945. 
5. DODGE CITY, KANS. 
Location. At Dodge City, Ford County, Kans., 
on Arkansas River about 130 miles downstream 
from Colorado-Kansas State line. (See Geological 
Survey map for Dodge quadrangle, scale 
1:125,000.) 
Existing project. About 7 miles of levees of about 
8.3 feet average height on both banks of Arkansas 
River (4.3 miles on left bank and 2.6 miles on right 
bank) and enlargement of river channel to form a 
floodway about 470 feet wide which will convey a 
flow of 40,000 cubic feet per second through city. 
Levees will be protected by flexible-type steel 
jetties. Four reaches of floodwalls about 100 feet 
long will be provided to insure continuity between 
levees and bridge abutments. Project also includes 
relocation of a railroad bridge and grade raise. 
Appurtenant works include interior drainage 
structures and fencing, a pumping plant for disposal 
of sanitary sewage during high water periods, and 
minor alterations to local roads and a sanitary 
sewerline. As result of the very damaging flood of 
June 1965 on the Arkansas River, which peaked at 
about 82,000 c.f.s. at Dodge City, consideration was 
given to modification of project design to increase 
protection to maximum extent practicable without 
causing substantial increase in Federal and 
non-Federal costs. Plan adopted is based on a 
design flow of 40,000 c.f.s. with the added 
requirement that top of levees would not be lower 
than the profile for 60,000 c.f.s. flow. The top of 
levee profile for 60,000 c.f.s. would increase the 
floodway capacity so it would not be necessary to 
raise the bridges on Second Street and 14th 
Avenue. The bridge crossings would require 
sandbagging during floods of 60,000 c.f.s. 
magnitude. Revised frequency curves prepared 
since 1965 flood indicate 40,000 c.f.s. flow would 
occur once in 250 years. These frequency curves 
also show that a 90-year frequency has a discharge 
of about 48,000 c.f.s., and such a flow could be 
safely passed through the floodway as presently 
designed. 
Estimated Federal cost is $6,670,000. Cost of 
lands and damages is responsibility of local 
interests. (See Table 17-B for authorizing 
legislation.) 
Local cooperation. In addition to usual 
requirements, local interests must acquire 
easement for flood-zoning purposes in areas that 
would be used for ponding of interior drainage 
waters and hold United States free from claims as a 
result of flooding from residual interior drainage 
during operation of project; alter existing 
improvements, other than railroads, including 
provision of a sewage disposal pumping plant; 
inform all individuals concerned about residual 
flooding problem involved owing to temporary 
ponding; and provide assurances that encroachment 
on improved river channels, interior drains, and 
ponding areas will not be permitted; and if ponding 
areas and capacities are impaired, provide 
substitute storage capacity or equivalent pumping 
capacity. A bond issue for flood control purposes 
was approved by the voters October 12, 1965. 
Formal assurances were received March 25, 1970. 
Local interests executed an agreement on 21 May 
1973 in compliance with Section 221, 1970 Flood 
Control Act and PL 91-646 Uniform Relocations 
Assistance Act of 1970. Estimated non-Federal cost 
is $1,030,000. 
Operations and results during fiscal year. 
Construction was initiated with the contract award 
in April 1975 for the channels, levees and 
floodwalls. 
Condition at end of fiscal year. Construction is 
continuing and is 10 per cent complete. 
17-6

ALBUQUERQUE, N. MEX., DISTRICT 
6. EL PASO, TEX. 
Location. At El Paso, El Paso County, Tex., 
which is on left bank of Rio Grande in reach that 
forms part of international boundary between 
United States and Republic of Mexico. (Geological 
Survey map for El Paso, Tex.; New Mexico 
quadrangle, scale 1:250,000.) 
Existing project. Consists of a single-purpose 
flood control system of detention dams, diversion 
dikes, and channels to collect, regulate and 
discharge arroyo runoff into Rio Grande. Runoff 
from tributary arroyos on eastern, southern, and 
western slopes of adjacent Franklin Mountains 
often inundates sections of city arnd its outlying 
suburban developments. Project is divided into four 
independent elements: Northwest area, Central 
area, and two units (Copper System and Bluff 
Channel) in Southeast area. A post-authorization 
change for the Northwest Area was submitted on 5 
June 1973. The changed plan satisfies the 1933 U.S. 
and Mexico agreement on limited tributary 
discharge into the Rio Grande in El Paso, Texas. 
Deferred elements now include five reservoirs, 
outlet conduit, and diversion channels in Northwest 
area and Bluff Channel in Southeast area to 
intercept arroyo flows above area of principal 
damage and convey them to Rio Grande. Estimated 
Federal cost is $35,500,000. (See Table 17-B for 
authorizing legislation.) 
Local cooperation. In addition to usual 
requirements, loral interests must alter existing 
improvements, other than railroads or 
improvements constructed and maintained by 
United States, prevent encroachment on all of 
project works which would reduce their design 
capacities; take steps to prevent encroachment 
upon existing defined waterways tributary to 
project by zoning or other means such as 
enlargements, or other modifications, of existing 
waterway facilities to prevent minor flood problems 
in these tributary waterways from developing into 
problems of serious proportions; and inform all 
concerned that project is designed to control floods 
originating above structures and that some residual 
flooding may be expected from precipitation 
occurring below structures. Estimated non-Federal 
cost is $12,500,000. 
Operations and results during fiscal year. 
Northgate and Range Dams went into operation 
during latter part of fiscal year 1973. No flood 
damage prevention benefits occurred during fiscal 
year 1974. During this fiscal year flows into 
Northgate Dam were insufficient to induce storage. 
At Range Dam, between 10 July 1974 and 23 
October 1974 several storms caused inflows. 
Maximum gage height was 6.60 feet with a 
corresponding storage of 53 acre-feet on 10 July 
1974. 
Conditions at end of fiscal year. Preconstruction 
planning is complete. Construction was continued 
in the Central Area. Sunrise and Mountain Park 
System were completed and placed in operation. A 
contract was awarded for construction of Pershing 
Dam and Phase I, Mountain Ave. Conduit. 
Construction was continued at Government Hill 
Outfall. Plans and Specifications for 
McKelligon-Fillmore System were continued. 
Planning, Phase II GDM and FDM for Oxidation 
Pond Dam and Buena Vista Diversion, for the 
Northwest Area is continuing. Planning for the 
Southeast Area will be resumed when the City of El 
Paso completes their alternate studies of this area. 
The construction for the Central Area of the project 
is about 35 percent complete. 
7. GREAT BEND, KANS. 
Location. At Great Bend, Barton County, Kans., 
on left bank of Arkansas River at river mile 873, 
about 4.5 miles upstream from confluence of Walnut 
Creek with Arkansas River. (See Geological 
Survey map, Great Bend quadrangle, scale 
1:250,000.) 
Existing project. Consists of Walnut Creek 
Diversion of 7.1 miles of leveed channel. Little 
Walnut Creek to be diverted into Walnut Creek 
Diversion Channel. The Little Walnut Creek 
Diversion consists of 1.5 miles of channel 
improvement, a left bank levee 2.1 miles long, and a 
right bank levee 2.3 miles long. Arkansas River 
levees and channel improvement consist of a left 
bank levee approximately 6.4 miles long and a right 
bank levee about 6.2 miles long. A tieback levee 6.0 
miles long on the left bank of Arkansas River 
upstream from junction with Walnut Diversion 
Channel; alteration or relocation of two railroad 
bridges; and appurtenant facilities. Project will 
protect city of Great Bend and vicinity from 
Arkansas River flows up to 84,000 cubic feet per 
second and Walnut Creek flows of 46,000 cubic feet 
per second. Estimated Federal cost is $15,900,000. 
(See Table 17-B for authorizing legislation.) 
Local cooperation. In addition to usual 
requirements, local interests must comply with the 
requirements of Section 221, 1970 Flood Control 
Act and PL 91-646 Uniform Relocation Assistance 
Act of 1970; provide easements for flood zoning 
purposes in ponding areas; hold United States free 
from claims as a result of flooding from residual 
interior runoff during operation of project; inform 
periodically all concerned that some flooding will 
continue to occur because of temporary ponding; 
prohibit any encroachment on design capacities of 
river channel, diversion channels, interior drains, 
and ponding areas; and if ponding area capacities 
are impaired, provide promptly, without cost to 
United States, substitute storage or equivalent 
pumping capacity; alter existing improvements, 
other than railroad bridges and approaches 
connected therewith; provide fences on both sides 
of Walnut diversion channel for structural 
17-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
protection and as a safety measure during periods 
of high flow. In addition, construction of the flood 
control works will be initiated concurrently with or 
subsequent to replacement of U.S. Highway 281 
bridge across Arkansas River. A bond issue to 
finance requirements was defeated in special 
election on 10 August 1965. Since defeat of initial 
bond issue, City Council initiated a campaign to 
better acquaint people in community with proposed 
project. On April 2, 1968, a bond issue was again 
defeated. Governing Body of Great Bend is 
proceeding with further studies to again present 
bond issue to the people. Formal assurances of local 
cooperation have not been requested. However, the 
Mayor and City Council have taken the position 
that these assurances will be furnished and that 
requirements will be met when requested. 
Estimated non-Federal cost is $3,400,000. 
Operation and results during fiscal year. Project 
planning continued during the fiscal year. Work is 
continuing on the Plan Formulation Memorandum, 
Phase I of the GDM. 
Condition at end of fiscal year. Preconstruction 
planning is about 45 percent complete. 
8. JOHN MARTIN RESERVOIR 
PROJECT, COLO. 
Location. On Arkansas River 1,159 miles 
upstream from its mouth, 300 miles downstream 
from its source, in Bent County, about 18 miles 
upstream from city of Lamar, Colo. (See Geological 
Survey maps for Lamar and Las Animas (Colo.) 
quadrangles, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
Annual Report for 1973. Federal cost is 
$15,182,380. 
Local cooperation. Section 2 Flood Control Act of 
June 28, 1938, applies. 
Operations and results during fiscal year. 
Routine maintenance and operation continued. 
Regulation of conservation storage continued under 
rules and regulations of Arkansas River Compact. 
No flood damages were prevented during fiscal 
year 1974; however, $173,600 sediment damages 
were prevented. Estimated total flood and 
sediment damages prevented by project through 
fiscal year 1974 were $73,136,400. Estimated 
irrigation benefits for fiscal year 1974 were 
$142,000. Estimated total accumulative irrigation 
benefits through fiscal year 1974 were $19,039,100. 
Maximum pool elevation of 3,792.41 feet with 
corresponding storage of 8,758 acre-feet occurred 
on 7 April 1975. Total releases for fiscal year were 
50,250 acre-feet. Releases attributed to irrigation 
benefits amounted to 8,626 acre-feet. Reservoir 
was empty July 1, 1974 until November 12, 1974 
when winter storage began. Sediment deposition 
was 600 acre-feet. 
Condition at end of fiscal year. Storage and 
operation of reservoir for irrigation began in March 
1943. Construction of dam and appurtenances was 
completed in October 1948 and are in good condition 
and in operation. A letter of intent for cost sharing 
has been received from State of New Mexico, for 
additional recreation facilities at the project. 
9. LAS ANIMAS, COLO. 
Location. At Las Animas, Bent County, Colo., at 
river mile 1,175 on Arkansas River, just upstream 
from its confluence with Purgatoire River, a major 
tributary that enters Arkansas River from south. 
(See Geological Survey map, Lamar, Colo.; Kans. 
quadrangle, scale 1:250,000.) 
Existing project. Consists of a levee 9.3 miles 
long on south bank of Arkansas River and a levee 
about 1 mile long on north bank. Appurtenant 
works include levee protection measures; an 
interior drainage system consisting of outlet 
structures, a ditch, and ponding areas; and intake 
structures for irrigation canals. Design flood is 
140,000 cubic feet per second, which is equivalent to 
flood of record (June 1921 flood with peak drainage 
of 187,000 cubic feet per second, reduced by 
regulatory effect of Barrier Dam, (now replaced by 
Pueblo Dam) near Pueblo, Colo. Estimated Federal 
cost is $4,300,000. (See Table 17-B for authorizing 
legislation.) 
Local cooperation. In addition to usual 
requirements, local interests must at least annually 
inform individuals concerned about residual flood 
problem involved owing to temporary ponding; 
prevent encroachment on river channel, which 
would reduce design flow capacity through leveed 
section and on ponding areas and interior drains; 
and if ponding area is impaired, provide substitute 
storage or equivalent pumping capacity promptly 
without cost to United States; and alter existing 
improvements, other than railroad bridges and 
approaches in connection therewith. Local interests 
will also be required to comply with Section 221, 
1970 Flood Control Act and PL 91-646 Uniform 
Relocation Assistance Act of 1970. In addition, 
construction will begin concurrent with or 
subsequent to replacement of United States 
Highway 50 bridge across Arkansas River. 
Construction of U.S. Highway 50 bridge across 
Arkansas River has been completed. 
Inasmuch as the flood control project extends 
beyond the corporate city limits of Las Animas, 
Colorado, the Arkansas River Conservancy 
District, Las Animas, Colorado, a political 
subdivision duly constituted and organized under 
the laws of the State of Colorado, is the sponsoring 
agency which will furnish required local 
cooperation. Conservancy District has jurisdiction 
and power to levy taxes both in the city and in those 
areas outside city limits affected by the project. 
Prior to authorization of project, the Conservancy 
17-8

ALBUQUERQUE, N. MEX., DISTRICT 
District pledged in writing that it favored project 
and would furnish required local cooperation. 
Estimated non-Federal cost is $280,000. 
Operations and results during fiscal year. Land 
acquisition continued during the year. 
Condition at end of fiscal year. Plans and 
specifications are complete. Award of channel 
clearing, levee and floodwall contract dependent on 
completion of land acquisition. 
10. LAS CRUCES, N. MEX. 
Location. On tributaries of Rio Grande at Las 
Cruces, Dona Ana County, N. Mex., about 87 miles 
downstream from Elephant Butte Dam. (See 
Geological Survey Map for Las Cruces, N. Mex., 
quadrangle, scale 1:62,500.) 
Existing project. Consists of Las Cruces Dam 
which extends across Alameda and Las Cruces 
Arroyos. The dam will be provided with an 
uncontrolled outlet and spillway. Las Cruces Dam, 
about 1,000 feet east of Las Cruces city limits, will 
be earthfill construction 15,570 feet long and 67 feet 
high with both slopes protected. Discharges from 
dam will be conveyed downstream in channel of 
Alameda Arroyo to the Dona Ana Drain. Reservoir 
capacity is 13,200 acre-feet at maximum water 
surface and 8,203 acre-feet at spillway crest. 
Controlled drainage area is 28.9 square miles. 
Estimated Federal cost is $4,390,000. (See Table 
17-B for authorizing legislation. ) 
Local cooperation. In addition to usual 
requirements, local interests must alter existing 
improvements, other than railroads; prevent 
encroachment upon the outlet channel from Las 
Cruces Dam to Dona Ana Drain to maintain a 290 
cubic feet per second channel capacity; design 
construct and maintain a minimum 290 cubic feet 
per second multi-purpose outlet channel from the 
Corps' outlet channel along the existing Dona Ana, 
Mesilla and Del Rio Drains to the Rio Grande; 
inform citizens that residual flooding may occur 
downstream of the dam; and prevent encroachment 
on the reservoir area that would reduce its storage. 
The estimated non-federal cost is $1,710,000. Local 
interests signed on agreement satisfying all 
requirements on 15 December 1972. All lands have 
been acquired. 
The City of Las Cruces requested the Campus 
Dam portion be deleted from the project. The New 
Mexico State University plans to solve the Campus 
Arroyo flood problem. 
Operations and results during fiscal year. Major 
accomplishments during the fiscal year were the 
completion of embankment contract and a portion of 
the outlet channel. 
Condition at end of fiscal year. Construction on 
the project was initiated in June 1973 and is about 
96 percent complete. 
11. LOS ESTEROS LAKE, N. MEX. 
Location. Los Esteros Lake is in Guadalupe 
County, on Pecos River, at river mile 766.4 
approximately 7 miles north of Santa Rosa, N. 
Mex. (See U.S. Geological Survey map, Corazon, 
N. Mex., sheet, scale 1:125,000.) 
Existing project. Authorized plan of 
improvement consists of an earth and rock fill dam 
1,950 feet long and 212 feet maximum height above 
the steambed. Project purposes are flood control, 
irrigation and sediment retention. An unlined, open 
rock cut about 1,000 feet back from the left 
abutment serves as an uncontrolled spillway. The 
outlet works, located in the left abutment, consists 
of a control tower, intake structure with gates, and 
a 10 foot diameter concrete tunnel with a terminal 
flip bucket energy dissipater. Storage capacity at 
the spillway crest is 449,000 acre-feet which 
includes 82,000 storage, 200,000 acre-feet irrigation 
storage and 167,000 acre-feet flood control storage. 
Surface area of the reservoir at the spillway crest is 
10,740 acres. Contributing drainage area at the 
damsite is 2,479 square miles. 
Authorized project also includes modification of 
the existing Alamogordo Dam and Reservoir on the 
Pecos River, (river mile 710.8) about 56 miles 
downstream from Los Esteros Lake. This 
modification provided for a reservoir capacity of 
210,000 acre-feet by raising the dam embankment 
10.5 feet and constructing an emergency spillway 
through the ridge on the right abutment. Changes 
to the service spillway were to limit the discharge 
to the capacity of the existing chute spillway and 
tainters. Project document also reallocated the 
storage in Alamogordo Dam and Reservoir to 
exclusive flood control use. 
Subsequent to project authorization, the Bureau 
of Reclamation modified the existing structure to 
its feasible limit without major reconstruction. This 
modification consisted of raising the dam height 16 
feet, altering the existing service spillway to limit 
the discharge to 56,000 c.f.s., and constructing an 
uncontrolled emergency spillway in the left 
abutment. The spillway capacity is 206,000 c.f.s. 
Storage allocation studies in response to 
authorizing document provides for transfer of all 
but 20,000 acre-feet of irrigation storage to Los 
Esteros Lake with remainder of storage in 
Alamogordo Reservoir reserved for flood control 
purpose. This transfer will be done under terms of 
the Pecos River Compact with consent of the 
Carlsbad Irrigation District. 
The estimated Federal (Corps of Engineers) cost 
for Los Esteros Lake is $23,700,000. (See Table 
17-B for authorizing legislation.) 
Local cooperation. In addition to first costs, 
operation and maintenance of both reservoirs will 
be responsibility of Federal Government; however, 
Carlsbad Irrigation District will be required to 
17-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
contribute to operation and maintenance costs an 
annual amount equal to what they now pay toward 
Alamogordo Dam. Carlsbad Irrigation District also 
will be required to agree to use of Alamogordo 
Reservoir for flood-control purposes. Because they 
will realize equivalent benefits from storage 
capacity in Los Esteros Lake, they will be required 
to continue to fulfill their repayment obligation. 
Project was authorized subject to the provision 
that "no appropriation shall be made for 
construction of Los Esteros Lake until satisfactory 
arrangements have been made by the State of New 
Mexico for the transfer of irrigation storage from 
the Alamogordo Reservoir." Engineer advisors to 
Pecos River Compact Commission have completed 
water studies to determine the effects of project on 
water supply in Pecos River basin. Corps, U.S. 
Bureau of Relcamation, Carlsbad Irrigation 
District, and engineer advisors to Texas and New 
Mexico commissioners participated in studies. 
Completed studies have been approved and 
accepted by Pecos River Compact Commission and 
State Engineer of New Mexico. A memorandum of 
agreement has been executed between the Corps of 
Engineers and the U.S. Bureau of Reclamation who 
has executed an agreement with the Carlsbad 
Irrigation District for transfer of this irrigation 
storage from the Alamogordo Reservoir to Los 
Esteros Lake. Ft. Sumner Irrigation District 
submitted a formal protest of the agreement 
between U.S. Bureau of Reclamation and Carlsbad - 
Irrigation District. The State Engineer approved 
the transfer of irrigation storage. After lower court 
decisions, the New Mexico Supreme Court upheld 
State Engineer approval of transfer of irrigation 
storage on 18 October 1974. 
Operations and results during fiscal year. 
Construction was completed on the Phase I of the 
access road. A contract was awarded 25 June 1975 
for construction of the outlet works, embankment, 
spillway, project buildings and Phase II of the 
access road. 
Condition at end of fiscal year. Construction and 
real estate activities continued during the fiscal 
year. 
12. PECOS, TEX. 
Location. At Pecos, Reeves County, Texas on 
the Pecos River streams and tributaries at mile 
312. (Geological Survey Maps, Pecos East and 
Pecos West, quadrangles, scale 1:24,000.) 
Existing project. The authorized project 
consisted of a combination of diversions, floodways, 
and levees to protect the city and agricultural lands 
from floods originating on Hurd's Well Draw, 
Cottonwood Creek, Nine Mile Draw and Salt Draw, 
together with a levee to protect the city from Pecos 
River overflows. Cost of Salt Draw Floodway 
rights-of-way exceeded the city's financial 
capability so a modified plan was proposed and 
accepted by the city, which eliminated the Salt 
Draw Floodway and the Nine Mile Draw wing 
levees that protected only the agricultural lands. 
The modified plan diverts Cottonwood Creek and 
Hurd's Well Draw into Sand Lake and then to the 
Pecos River north of the city. Levees on the north 
and east sides protects the city from Pecos River 
overflows. Estimated Federal cost is $5,600,000. 
Local cooperation. Prior to construction 
responsible local agencies give satisfactory 
assurances to the Secretary of the Army that they 
will: (1) provide all lands, easements, and 
rights-of-way necessary for construction of the 
project; (2) hold and save the United States free 
from damages due to the construction works 
including any damage which may result from 
temporary ponding of interior runoff and effects on 
sewage systems; (3) maintain and operate the 
works after completion in accordance with 
regulations prescribed by the Secretary of the 
Army; and (4) make any alterations to existing 
improvements, other than railroads, which may be 
required because of the construction works. 
Estimated non-Federal cost is $812,000. 
Operations and conditions at the end of the fiscal 
year. Preconstruction planning continued. 
Hydrology design memorandum was completed. A 
contract was awarded for the Phase I general 
design memorandum in October 1974. 
13. RIO GRANDE BASIN, N. MEX. 
Location. Improvements are on Rio Grande and 
tributaries in New Mexico. More definite locations 
and descriptions of individual projects are in 
following paragraphs and individual reports by 
projects. 
Existing project. Flood Control Act of 1948 
authorized flood control phase of comprehensive 
plan of development of water resources of Rio 
Grande basin in New Mexico (H. Doc. 243, 81st 
Cong., 1st sess.) with exception of Chiflo Dam and 
Reservoir and spillway gate structure at Chamita 
Dam. Although recommended Chiflo Dam and 
Reservoir was deleted from authorized plan, it was 
excluded without prejudice to future consideration 
by Congress. It was requested at that time, by 
States of Colorado and Texas, that project be 
deferred for restudy regarding required storage 
and methods of operation. By same act, Congress 
also authorized for construction irrigation phase of 
comprehensive plan as recommended by Bureau of 
Reclamation (H. Doc. 653, 81st Cong., 2nd sess.). 
The act also stipulated that work should be 
prosecuted in accordance with joint agreement 
approved by Secretary of the Army and Acting 
Secretary of the Interior on November 21, 1957. In 
addition, under that agreement Bureau of 
Reclamation was given responsibility for 
construction, operation, and maintenance of 
17-10

ALBUQUERQUE, N. MEX., DISTRICT 
channel rectification, and drainage rehabilitation 
and extension phases of unified plan of 
improvement. Authority for Chamita Dam and 
Reservoir was abrogated when Cochiti Dam and 
Reservoir was authorized. (See Table 17-B for 
authorizing legislation and Table 17-C for existing 
projects.) 
All operations and costs for projects in authorized 
plan are in individual reports on the following 
pages. 
13A. ABIQUIU DAM, N. MEX. 
Location. Project is one unit of flood control 
phase of comprehensive plan for Rio Grande and 
tributaries, New Mexico. Abiquiu Dam is on Rio 
Chama near town of Abiquiu, N. Mex., about 32 
miles upstream from confluence of Rio Chama and 
Rio Grande. (See Geological Survey Map for plan 
and profile of Rio Chama, N. Mex., from mouth to 
mile 103, sheet 1, and Army Map Service, Aztec, N. 
Mex.; Colorado NJ 13-10, scale 1:250,000.) 
Existing project. For description of completed 
improvements and authorizing legislation see 
Annual Report for 1973. Federal cost is 
$21,272,300. 
Operations and results during fiscal year. 
Routine maintenance and operation continued. 
Storage and flows were regulated in accordance 
with regulations prescribed by Rio Grande 
Compact Commission. On 1 July 1974 the pool 
elevation was 6,116.53 feet with a corresponding 
storage 4,006 acre feet. The reservoir was 
regulated for flood control from 3 July 1974 until 28 
August 1974 and 23 April 1975 through 30 June. 
1975 to prevent flood damage in the Rio Chama. 
The maximum pool (6193.86 feet) and storage 
(110,280 acre-feet) occured on 3 June 1975. On 30 
June 1975 the pool elevation was 6,170.60 feet with 
a corresponding storage of 53,740 acre-feet. On 14 
December 1974 a release of 14,690 acre-feet of San 
Juan Chama water was made from El Vado 
reservoir and stored temporarily for the city of 
Albuquerque, NM. There was 1,340 acre-feet of 
sediment deposition during the year. 
No flood damages prevented during fiscal year. 
Sediment damages prevented were $78,400. 
Accumulated flood and sediment damages 
prevented by the project since completion were 
$4,291,400 through fiscal year 1974. 
Condition at end of fiscal year. Project was 
placed in operation in February 1963. 
13B.COCHITI LAKE, N. MEX. 
Location. Dam is at river mile 340 on Rio Grande 
(river mile 0 being at intersection of New 
Mexico-Texas State line with international 
boundary at El Paso, Tex.), near village of Cochiti, 
which is about 50 miles upstream from 
Albuquerque, N. Mex. (See Geological Survey 
Maps, Cochiti Dam, N. Mex., quadrangle and Santo 
Domingo Pueblo, N. Mex., quadrangle, scale 
1:24,000.) 
Existing project. Consists of an earthfill dam 
about 5.4 miles long with a maximum height of 251 
feet above streambed. Project will extend generally 
in an east-west line across Rio Grande to a point 
about 2 miles east of Rio Grande and then 
southward across Santa Fe River. An uncontrolled 
spillway with a 460-foot-long ogee-weir and a 
160-foot notch 10.5 feet deep in center will be at end 
of embankment on south side of Santa Fe River. 
Operational releases for flood control and irrigation 
will be made through a 3-barrel gated conduit in left 
abutment on Rio Grande. No outlet will be provided 
on Santa Fe River. Dead storage in Santa Fe River 
and Canada de Cochiti arms of reservoir will be 
eliminated by means of conveyance channels. 
Construction will also involve relocation of a 
gravel-surfaced Forest Service road and an 
irrigation headworks and canal. Reservoir will have 
a storage capacity of 442,000 acre-feet for flood 
control, 110,000 acre-feet for sediment, and 50,000 
acre-feet for recreation a total of 602,000 acre-feet. 
Storage capacity for permanent pool for recreation 
will be provided by slightly modifying the operating 
procedures. Modification of project structures, 
except for specific recreation facilities, will not be 
necessary because of permanent pool. Estimated 
Federal cost is $93,500,000. (See Table 17-B for 
authorizing legislation.) 
Operations and results during fiscal year. With 
the construction complete on the embankment and 
allied facilities the project was reclassified from a 
construction to an operation project in June 1975. 
On 30 June 1975 the pool elevation was 5,312.71 feet 
with a corresponding storage of 37,898 acre-feet. 
The maximum pool elevation was 5,313.05 feet with 
a storage of 38,250 acre-feet on 26 June 1975. The 
reservoir was operated for flood control from 18 
June through 20 June 1975. 
No flood damages prevented during fiscal year 
1974, because the project was not in operation. 
Conditions at end of fiscal year. The 
embankment contract was completed. Planning was 
completed for the visitor's center and Cochiti 
Recreation Area facilities. Plans and specifications 
were continued at Tetilla Park Recreation Area. 
Plans and specifications were completed for 
Operator's Quarters and Cochiti Recreation Area. 
The overall project is about 92 percent complete. 
13C. GALISTEO DAM, N. MEX. 
Location. Dam is at river mile 12 on Galisteo 
Creek, a tributary of Rio Grande. Definite project 
site is about 8 miles upstream of project document 
site. Reservoir will extend upstream from dam for 
about 4 miles to near village of Waldo, N. Mex. (See 
17-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Geological Survey Map, San Pedro 1, N. Mex. 
quadrangle scale 1:24,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
Annual Report for 1973. Federal cost was 
$14,220,053. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Operation of the project began on October 11, 1970. 
The reservoir was empty on 1 July 1974. Outflow 
from the project ranged from zero to the maximum 
inflow and discharge of 760 c.f.s. on 16 September 
1974. There was 22 acre-feet of sediment deposition 
during the year and the reservoir was empty on 30 
June 1975. 
Condition at end of fiscal year. Construction of 
the project was initiated in July 1965 and physically 
completed in September 1970. 
13D.JEMEZ CANYON DAM, N. MEX. 
Location. In Sandoval County, N. Mex., on 
Jemez River about 2 miles upstream from 
confluence of Jemez River and Rio Grande, about 5 
miles northwest of Bernalillo, N. Mex. (See 
Geological Survey Map for Bernalillo quadrangle, 
scale 1:125,000.) 
Existing project. For description of completed 
improvements and authorizing legislation see 
Annual Report for 1973. Estimated federal cost is 
$4,177,417. 
Operations and results during fiscal year. 
Routine maintenance and operation continued. On 1 
July 1974 the reservoir was empty. The reservoir 
was regulated for sediment control for short 
periods during April, May and June. The maximum 
pool elevation for the year was 5166.82 feet with a 
storage of 5,428 acre-feet on 27 April 1975. 
Sediment deposition during the year was 300 
acre-feet. No flood damages prevented by the 
project during fiscal year 1974. Sediment benefits 
during fiscal year 1974 were $11,200. Estimated 
total accumulated flood and sediment damages 
prevented by the project through fiscal year 1974 
were $1,984,200. 
Condition at eud of fiscal year. Construction of 
project was initiated May 1950 and completed May 
1954. 
13E.RIO GRANDE FLOODWAY, N. MEX. 
Location. Project is one unit of flood control 
phase of comprehensive plan of improvement for 
Rio Grande Basin in New Mexico. It is on Rio 
Grande and covers section of river commencing 
near Truth or Consequences (formerly Hot 
Springs) at about river mile 123 and extends 
upstream to lower end of Rio Grande Canyon about 
14 miles upstream from Espanola, N. Mex., about 
river mile 394. (See Table 17-D on Rio Grande 
Floodway.) 
Existing project. Consists of flood protection and 
major drainage improvements by channel 
rectification, levee enlargement and construction, 
and bank stabilization work where needed to 
protect levees. Construction of project is a joint 
undertaking by Bureau of Reclamation and the 
Corps. Portions to be done by Corps will consist of 
levee enlargement, construction, and bank 
protection work, with channel-rectification and 
drainage-rehabilitation work the responsibility of 
Bureau of Reclamation. Levees constructed by 
local interests exist through reach of river involved, 
but are not uniform as to grade, section, or 
standard of construction, and in many places are 
threatened by meandering river. (See Table 17-D 
on existing project and Table 17-B for authorizing 
legislation.) 
Local cooperation. In addition to usual 
requirements, local interests are responsible for all 
highway, bridge, and public utility relocations or 
replacements required in construction of project. 
Local interests will also be required to comply with 
requirements of Section 221, 1970 Flood Control 
Act and PL 91-646 Uniform Relocation Assistance 
Act of 1970. Total costs for all requirements for 
completed Albuquerque unit under terms of project 
authorization were $75,000. There were no 
non-Federal costs in connection with construction 
of Cochiti to Rio Puerco unit of floodway. Espanola 
Valley unit was inactive for several years; however, 
in December 1963, local interests reaffirmed need 
for flood protection for city of Espanola, and 
indicated in writing that they were willing and able 
to provide necessary rights-of-way for levees and 
make utility relocations required in construction of 
project. Project was reclassified to active category, 
and funds were appropriated for initiation of 
preconstruction planning in fiscal year 1966. 
Right-of-entry was obtained in May 15, 1967, from 
the Indian Pueblo of Santa Clara, the principal 
landowner affected by the project. The negotiations 
between the city and Santa Clara Pueblo to obtain 
formal assurances failed to materialize. The city 
was notified that the five-year period in which to 
comply with their requirements had begun on 
August 2, 1973. The city has not given indication 
they plan positive action to resolve the problem. 
Operations and results during the fiscal year. 
Preconstruction planning for the Espanola Valley 
unit of the floodway was completed. The failure to 
obtain formal assurances resulted in the District 
reporting on 2 November 1972 funds available for 
construction to be excess. 
Flood damages prevented by the completed 
floodway project for fiscal year 1974 were $95,200. 
Estimated total accumulated flood damages 
prevented by the floodway project through fiscal 
year 1974 amounted to $1,313,200. The peak flow of 
the Rio Grance through the middle valley was 6,280 
17-12

ALBUQUERQUE, N. MEX., DISTRICT 
c.f.s. at Albuquerque on 24 May 1975 and 7,820 
c.f.s. at San Acacia on 26 May 1975. 
Condition at end of fiscal year. Construction of 
Albuquerque and Cochiti to Rio Puerco units of Rio 
Grande Floodway project is complete. San Acacia 
to Bosque del Apache unit is deferred for restudy. 
The Truth or Consequences (Hot Springs) Unit was 
reclassified to the active category on 18 July 1973 
based on a letter of intent to cooperate from the city 
of Truth or Consequences dated May 31, 1973 and 
Sierra County, dated June 4, 1973. 
Hydrology and general design memoranda for 
Espanola Valley unit have been approved. 
Preconstruction planning was completed and 
five-year notice issued on August 2, 1972. 
13F. TRUTH OR CONSEQUENCES 
(HOT SPRINGS) UNIT, N. MEX. 
Location. Vicinity City of Truth or Consequences 
(Hot Springs), New Mexico. 
Existing project. Plan of improvement will 
include 4 miles of 20 foot high levees with positive 
seepage control, an interior drainage system, and 5 
miles of diversion channels. The diversion channels 
would be required for control of floods on tributary 
arroyos at and in the vicinity of Truth or 
Consequences. Estimated Federal cost is 
$11,400,000. (See table 17-B for authorizing 
legislation.) 
Local cooperation. Prior to construction local 
interests must furnish assurances satisfactory to 
the Secretary of the Army that they will: (1) 
acquire all lands, easements, and rights-of-way 
necessary for construction and operation of the 
project; (2) hold and save the United States free 
from damages due to the construction works and 
free from claims as a result of flooding from residual 
interior drainage during operation of the project; 
(3) maintain and operate the works after 
completion; (4) make any alteration to existing 
improvements, other than railroad bridges and 
approaches connected therewith, which may be 
required because of the construction works; (5) 
Provide guidance and leadership by encouraging 
prudent use of flood proofing, land regulation 
planning, or other flood plain management 
techniques to reduce the flood losses. 
Letters of intent have been received from the 
City of Truth or Consequences (dated 31 May 1973) 
and the County of Sierra (dated 4 June 1973). 
Estimated non-Federal cost is $2,640,000. 
Operations and condition at the end of fiscal 
year. Capability for initiation of preconstruction 
planning has been reflected for next fiscal year. 
14. TRINIDAD LAKE, COLO. 
Location. On Purgatoire River about 161 miles 
above its junction with Arkansas River. Project is 
about 4 miles upstream from city of Trinidad, Colo. 
(See Geological Survey Map, Trinidad, Colo., 
quadrangle, scale 1:24,000.) 
Existing project. Consists of an earthfill 
structure 6,610 feet long, with a maximum height of 
200 feet above streambed, an uncontrolled spillway 
1,000 feet wide in left abutment, and a 10-foot 
diameter, gate-controlled conduit in right abutment 
with discharge capacity of 5,870 cubic feet per 
second with water surface at top of flood control 
pool. Reservoir provides for storage of 51,000 
acre-feet for flood control, 39,000 acre-feet for 
sediment, 20,000 acre-feet irrigation, and 4,500 
acre-feet for recreation, a total of 114,500 acre-feet. 
Reservoir controls a drainage area of 606 square 
miles and will be operated for flood and sediment 
control, irrigation, and recreation purposes. 
Estimated Federal cost is $43,800,000 (CE) & 
$160,000 (USBR). (See Table 17-B for authorizing 
legislation.) 
Local cooperation. Requirements based on 
approved general design memorandum studies: 
Repayment by Purgatoire River Water 
Conservancy District of first cost allocated to 
irrigation established as 29.28 percent of total 
project cost generally in accordance with Federal 
reclamation law procedures, except that repayment 
of irrigation first cost may extend over a period not 
to exceed 75 years including a 5-year development 
period which results in an actual amortization 
period of 70 years; contribution of $21,400 annually 
by State of Colorado for replacement of evaporation 
and seepage losses from permanent fishery pool; 
Purgatoire River Water Conservancy District 
(representing the irrigators) is required to bear 
19.82 percent of annual joint-use operation and 
maintenance costs and 2.52 percent of major 
replacement costs presently estimated at $13,600 
annually; in addition, estimated annual cost to City 
of Trinidad for maintenance of channel of 
Purgatoire River through city is $1,100. In addition 
conservancy district must make arrangements for 
transfer of Model Land and Irrigation Co.'s storage 
rights from existing Model Reservoir to Trinidad 
Reservoir. Storage for recreation purposes not 
included in authorized project plan; however, 
project document noted that substantial benefits 
would be derived from such use and that there was 
strong local support for such storage. Provision was 
made in project plan for 4,500 acre-feet of 
permanent storage for recreation; however, since 
flows of Purgatoire River are fully appropriated, 
water rights will have to be acquired by 
non-Federal interests. Estimated cost of initial 
filling of pool is $250,000 and replacement of 
evaporation losses will cost an estimated $21,400 
per year. Lands and facilities for recreation will be 
provided at Federal expense, but cost of water 
rights will be borne by the State of Colorado. 
Non-Federal cost is $6,686,000. 
17-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Assurances of local cooperation received from 
City of Trinidad and Purgatoire River Water 
Conservancy District were formally accepted May 
11, 1967, after execution of irrigation repayment 
contract. Stipulated decree changing place of 
storage of water rights decreed to existing Model 
Reservoir from that reservoir to proposed Trinidad 
Reservoir was conditionally approved by Las 
Animas County, Colorado, District Court April 15, 
1965, subject to ultimate execution and approval of 
irrigation repayment contract, which qualifying 
condition is now removed. Purgatoire River Water 
Conservancy District, representing water users, 
signed prime irrigation repayment contract 
January 21, 1967. Prime contract was then signed 
by Regional Director, Region 7, Bureau of 
Reclamation February 10, 1967, under delegated 
authority of U.S. Department of Interior. Contract 
is dated February 10, 1967. Irrigation repayment 
contract was confirmed by decree of Las Animas 
County, Colorado, District Court entered into 
March 21, 1967, and 30-day period of appeal 
required by Colorado statutes expired with no 
appeals being filed. 
Operations and results during fiscal year. Real 
estate acquisition was completed. Planning 
continued on master plan. Construction continued 
on embankment contract. Construction was 
completed for State Highway #12 relocation. 
Condition at end of fiscal year. Progress on the 
embankment contract is continuing. The project is 
about 74 per cent complete. 
15. TWO RIVERS DAM, N. MEX. 
Location. About 14 miles southwest of Roswell, 
N. Mex., on Rio Hondo. Rio Hondo is formed at 
confluence of Rio Ruidoso and Rio Bonito, near 
village of Hondo, N. Mex., in foothills region of 
Sierra Blanca in southeastern part of Lincoln 
County, N.Mex., and flows generally easterly to its 
confluence with Pecos River near Roswell, N. Mex. 
(See Geological Survey Map, Hondo Reservoir 
quadrangle, scale 1:24,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
Annual Report for 1973. Federal cost was 
$4, 790,838. 
Local cooperation. Complied with. Total cost to 
local interests was $144,000, of which $60,000 was 
for construction of access road and $84,000 for lands 
and rights-of-way. 
Operations and results during fiscal year. 
Routine maintenance and operation continued. The 
reservoir was operated for flood control from 22 
September 1974 through 29 October 1974. The 
maximum pool elevation and storage occurred on 23 
October 1974. The reservoir was empty on 1 July 
1974 through 21 September 1974 and 28 October 
1974 until 30 June 1975. The maximum pool 
elevation was 3,981.80 feet with a corresponding 
storage of 361 acre-feet for Diamond A Dam and 
3,959.70 feet with a corresponding storage of 1,228 
acre-feet for Rocky Arroyo Dam. There were no 
flood damages prevented by the project during 
fiscal year 1974; however, sediment damages 
prevented were $1,700. Estimated total 
accumulated flood and sediment damages 
prevented through fiscal year 1974 were 
$2,347,000. There was 420 acre-feet of sediment 
deposition during the fiscal year. 
Condition at end of fiscal year. Project is 
complete and was placed in operation July 1963. 
16. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Included under this heading is inspection of 
completed flood control projects transferred to local 
interests for operation and maintenance. Projects 
in Colorado and New Mexico were inspected. Fiscal 
year cost was $22,631 and total cost to June 30, 
1975, was $102,263. 
17. SCHEDULING FLOOD 
CONTROL RESERVOIR 
OPERATIONS 
Pursuant to section 7, Flood Control Act of 1944, 
expenditures were made for preparation of 
regulation manual for Pueblo reservoir, located on 
the Arkansas River above Pueblo and scheduling 
flood control reservoir operations for Platoro Dam 
on Conejos River near town of Platoro, Conejos 
County, Colo. Platoro Dam was authorized by 
Interior Appropriation Act of 1941 (see H. Doc. 
693, 76th Cong., 3d sess.). Construction of project 
was completed by Bureau of Reclamation in fiscal 
year 1952. 
On 1 July 1974 the pool elevation was 9,982.5 feet 
with a corresponding storage of 20,257 acre-feet. 
The maximum elevation of the year was 10,007.7 
feet on 27 June 1975 with a storage of 36,680 
acre-feet. The reservoir was operated for flood 
control from 19 May 1975 until 27 May 1975. On 30 
June 1975 the pool elevation was 10,007.5 with a 
corresponding storage of 36,526 acre-feet. Flood 
control continued from 4 June 1975 until 23 June 
1975 when prescribed regulation for flood control 
was suspended. Peak flow at Mogote gage without 
the project would have been 2,760 cubic feet per 
second and with the project 2,210 cubic feet per 
second on 4 June 1975. The peak at Otowi gage was 
8,867 cubic feet per second. There were no flood 
and sediment damages prevented by the project 
during fiscal year 1974. Total accumulated flood 
damages prevented were $1,473,000 through fiscal 
year 1974. Fiscal year costs were $5,436 and total 
costs to June 30, 1975 were $60,345. 
17-14

ALBUQUERQUE, N. MEX., DISTRICT 
18. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS. 
See Table 17-E 
19. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization.) 
Engineering and Design studies were completed 
for Granada, Colorado. Engineering and design 
studies were continued during the fiscal year on 
projects at Holly, Colorado, and Kinsley and 
Lamed, Kansas, all on the Arkansas River. The 
total respective costs through the fiscal year were: 
Holly, Colorado, $2,542; Kinsley, Kansas, $16,989 
and Lamed, Kansas 28,345. A project studied 
during the fiscal year was San Louis, Colorado for a 
Federal cost of $5,000. 
Emergency flood control activities repair, flood 
fighting, and rescue work. (Public Law 99, 84th 
Cong., and antecedent legislation) 
Federal costs for fiscal year were $32,347 for 
advance preparation, and $23,610 for flood 
emergency operations, and $18,439 for repair and 
restoration. 
Emergency bank protection (Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Federal costs for fiscal year were $685 to 
complete the emergency bank protection work for 
Pojoaque Pueblo, Tesuque Pueblo and Tonque 
Arroyo at San Felipe Pueblo, all in New Mexico. 
Snagging and clearing of navigable streams and 
tributaries in the interests of flood control. (Sec. 
208 of the 1954 Flood Control Act, PL 780, 83d 
Congress) 
Federal costs for fiscal year were $1,409 for 
completing snagging and clearing work on Part I 
Gallinas River, Las Vegas, New Mexico and $6,478 
to initiate work on Part II Galinas River, Las 
Vegas, New Mexico. 
General Investigations 
20. SURVEYS 
Fiscal year costs were $475,832 of which $460,661 
was for flood control studies and $15,171 for special 
studies (coordination studies with other agencies). 
21. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $106,203 for flood plain 
management and technical services and $214,746 
for continuation of flood plain information studies at 
Luna County, N. Mex., Part I, Taos County, N. 
Mex., Part I, Laguna Pueblo, N. Mex., Part I, 
Acoma Pueblo, N. Mex., Albuquerque Arroyos 
Part 3, Alamosa, Colo., Pueblo Colo., Parts 4 and 6, 
and Pojaoque River, Santa Fe County, N. Mex., 
Part I. One study was initiated at Cottonwood 
Creek, Colo. Albuquerque Arroyos Parts 4 and 5 
were completed during the fiscal year. 
22. RESEARCH AND 
DEVELOPMENT 
Hydrologic studies involving collection and study 
of basic data, such as streamflow data, collection of 
suspended sediment samples, recording rain gage 
data, hydrometeorological studies, and sedimentation 
studies continued. Fiscal year costs were 
$1,785. 
23. INVENTORY OF DAMS 
Included under this heading is the program of 
inventory of dams enacted into law (HR 15951) 9 
August 1972. The area of responsibility for the 
district is the state of New Mexico and the Federal 
cost for the fiscal year was $4,268. 
17-15

TABLE 17-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
Albuquerque 
Diversion Channels 
Project, N. Mex. 
(Federal Funds) 
(Contributed 
Funds) 
(Other Contributed 
Funds) 
4. Conchas Lake, 
N. Mex. 
5. Dodge City, Kans. 
6. E1 Paso, Tex. 
7. Great Bend, Kans. 
8. John Martin 
Reservoir, Colo. 
9. Las Animas, Colo. 
10. Las Cruces, N. Mex. 
(Other Contributed 
Funds) 
11. Los Esteros Lake, 
N. Mex. 
12. Pecos, Texas 
13. Rio Grande Basin 
N. Mex. 
13A. Abiquiu Dam, 
N. Mex. 
13B. Cochiti Lake, 
N. Mex. 
13C. Galisteo Dam, 
N. Mex. 
1. 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
893 
15,400 
87,994 
- 17,299,038 
249 17,296,822 
107,776 
104,657 
37,776 
11,649 
1,455,446 
1,782,139 
i
P 
Funding 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
509,685 
410,930 
-357,000 
93,917 
11,843,000 
1,760,925 
-6,000 
76,494 
402,638 
404,024 
42,000 
21,638 
1,418,000 
90,187 
1,500,000 
213,929 
253,985 
307,258 
17,129,700 
16,352,114 
257 
50,623 
53,571 
447,600 
508,362 
1,407,000 
81,874 
1,600,000 
872,323 
136,000 
171,686 
9,000 
7,188 
448,630 
462,785 
558,000 
96,207 
1,440,000 
1,573,281 
301,028 
312,251 
499,000 
78,080 
1,191,700 
2,465,769 
198,600 
66,271 
394,278 
370,077 
2,586 
447,500 
46,551 
891,700 
262,818 
301,713 
229,566 
22,959,200 
23,020,852 
-_ 
8,054 
11,276 
110,784 
94,853 
956,216 
180,000 
124,178 
1,840 
271,810 
267,631 
15,100,000 
13,458,477 
551 
43,800 
55,431 
389,000 
447,090 
-_ 
532,057 
2,050,000 
3,069,121 
13,908 
12,318 
213,000 
200,676 
-9 
1,750 
524,000 
490,323 
-78,000 
22,332 
817,000 
2,316,417 
1,300,000 
-1,906,564 
162,000 
198,430 
3,287 
266,263 
285,832 
9,040,000 
10,882,276 
70,000 
64,821 
-506 
5,953 
57,000 
57,171 
17-16 
548,356 
545,237 
854,644 
854,644 
13,309,1761 
13,309,1761 
5,169,472 
5,152,092 
1,924,142 
1,131,073 
9,787,200 
9,690,434 
13,908 
12,318 
554,100 
527,312 
15,182,3802 
15,182,3272 
5,419,800 
5,368,456 
742,000 
356,410 
4,389,500 
4,293,436 
99,100 
95,905 
4,734,562 
4,289,722 
435,370 
415,998 
21,272,299 
21,267,178 
2,177,906 
2,166,892 
86,174,254 
85,571,791 
70,000 
64,821 
14,220,058 
14,220,053 
307,477 
305,276 
95,905

TABLE 17-A (Continued) 
See 
Section 
in Text 
13D. Jemez Canyon 
Dam, N. Mex. 
13E. Rio Grande 
Floodway, N. Mex. 
14. Trinidad Lake, 
Colo. 
15. Two Rivers Dam, 
N. Mex. 
Project 
ALBUQUERQUE, N. MEX., DISTRICT 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 72 
206,848 
161,156 
343,600 
1,646 
FY 73 
96,444 
137,180 
-300,000 
FY 74 
132,260 
143,431 
-41,835 
595 
Total Cost to 
FY 75 June 30, 1975 
165,000 
176,274 
4,177,417 
4,177,417 
1,386,351 
1,383,340 
- 4,899,8683 
- 4,899,8684 
1,248,500 8,500,000 6,948,800 5,650,000 32,100,758 
1,370,569 5,032,879 11,175,180 5,220,688 30,977,136 
- - - - 4,790,838 
S- - - 4,790,838 
74,300 
73,493 
63,280 
61,252 
54,400 
56,416 
55,000 
57,182 
616,412 
616,236 
1. Includes $3,492,696 maintenance and improvement costs and Cochiti to Rio Puerco units and for preconstruction planning 
and $869,978 for emergency relief excludes $2,279,326, cost of of Espanola Valley unit. Excludes $1,000,041 transferred to 
initiating project under the authority of Emergency Relief Bureau of Reclamation under memorandum agreement between 
Appropriation Act of 1935 and $222,669, the cost for work that agency and the Corps. Does not include funds referenced in 
performed with funds transferred to the Corps under Public footnote 3. 
Works Acceleration jact of 1962. , 4. Includes costs for completed Albuquerque and Cochiti to 
2. Excludes $59,977 emergency relief funds for new work. Rio Puerco units and for preconstruction planning of Espanola 
Includes $9,000 for Code 710. Valley unit. Excludes costs incurred by Bureau of Reclamation 
from funds transferred to that agency under the memorandum 
3. Includes funds appropriated for completed Albuquerque agreement covering construction of Cochiti to Rio Puerco unit. 
TABLE 17-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
ALPINE, TEX. (See Section 2 of Text) 
Earthfill dam 6,300 feet long and 77 feet high, with a flood 
control storage capacity of 12,710 acre-feet. A diversion 
channel 3 miles long, a conveyance channel 0.7 miles long 
will divert flood flows into Alpine Lake. 
ARKANSAS RIVER BASIN ABOVE JOHN MARTIN DAM, COLO. 
(See Section 3 of Text) 
Authorized to undertake the Phase I design memorandum stage of 
advanced engineering and design of the project for flood 
protection and other purposes on the Arkansas River and 
tributaries above John Martin Dam, Colorado at an estimated 
cost of $1,140,000. 
LA JUNTA (ANDERSON AND KING ARROYOS), COLO. 
(See Section 3A of Text) 
Channelization of Anderson and King Arroyos to convey flood 
flows through the city and into the Arkansas River. 
FLORENCE, COLO. (See Section 3B of Text) 
Two earthfill structures and two diversion channels to protect 
the city from flood flows. Coal Creek Dam is 1,230 feet long 
and 75 feet high and Oak Creek Dam is 4,440 feet long, 118 
feet high, with flood control storage capacities of 5,660 
acre-feet and 17,160 acre-feet, respectively. 
PORTLAND, COLO. (See Section 3C of Text) 
0.7 mile of intermittent levees and floodwalls on right bank 
of Arkansas River, and 0.6 mile of channel improvement. 
PUEBLO (DRY CREEK), COLO. (See Section 3D of Text) 
Channelization of Dry Creek for 0.7 mile with 0.4 mile of 
levees on each bank to convey floodflows through the city 
into the Arkansas River. 
Section 201 of PL 89-298 
H. Doc. 93-145, 93rd Cong., 
1st sess. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
17-17 
Oct. 27, 1965 
May 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
_ _

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 17-B (Continued) 
Acts 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Oct. 23, 1962 
Oct. 27, 1965 
Oct. 27, 1965 
Oct. 22, 1965 
Oct. 23, 1962 
Sept. 3, 1954 
Sept. 3, 1954 
June 30, 1948 
AUTHORIZING LEGISLATION 
Work Authorized 
ARKANSAS RIVER FLOODWAY, BREWSTER TO 
FLORENCE, COLO. (See Section 3E of Text) 
A south bank levee 5.9 miles long beginning about 3.5 miles above 
Florence, Colorado and ending about 2.5 miles below the city. 
ARKANSAS RIVER CHANNELIZATION TEST REACH 
(See Section 3F of Text) 
A 7 mile reach of flood control levees with tie backs and 
landside drains to test their water salvage capabilities. 
A pilot study to show the environmental impact of 
channelization and related works on the river's physical 
appearance and conditions in the control of floods and 
salvage of water. 
LA JUNTA (REACH 2-URBAN), COLO. (See Section 3G of Text) 
A north bank levee 3 miles long with tie back levees and a 
south bank levee 2 miles long with a tie back levee along 
the Arkansas River through La Junta, Colorado. 
FOUNTAIN LAKE, COLO. (See Section 3H of Text) 
Earthfill dam 12,905 feet long and 172 feet high with a total 
storage capacity of 247,000 acre-feet at spillway crest. 
The outlet conduit will be a 12-foot diameter concrete structure. 
DODGE CITY, KANS. (See Section 5 of Text) 
7 miles of levees and enlargement of river channel to 470 
foot wide floodway through city. Based on design flow of 
40,000 c.f.s. with added requirements for top of levees to 
not be lower than profile of60,000 c.f.s. flow. 
EL PASO, TEX. (See Section 6 of Text) 
A single-purpose flood control system of detention dams, 
diversion dikes and channels to collect, regulate and 
discharge arroyo runoff into the Rio Grande. Consists of 
four independent units (NW Area, Central Area, and two 
units, Copper System and Bluff Channel of the SE Area). 
GREAT BEND, KANS. (See Section 7 of Text) 
7.7 miles of leveed channel to divert Walnut and Little Walnut 
Creeks around the city; 6 miles of improved channel with 
levees along the Arkansas River and a 4.3 mile long tieback 
levee on left bank of Arkansas River along with other 
improvements and alterations. 
LAS ANIMAS, COLO. (See Section 9 of Text) 
About 10.6 miles of levees on both banks of Arkansas River 
including interior drainage system to protect the city from 
flood flows up to 140,000 c.f.s. 
LAS CRUCES, N. MEX. (See Section 10 of Text) 
Two earthfill dams, one 15,570 ft. long and the other 1,790 ft. 
long, with uncontrolled outlets and spillways located east of 
city to intercept flood flows from Alameda, Las Cruces and 
Campus Arroyos. Discharges from dams to be conveyed through 
city to Rio Grande by an unlined trapezoidal channel. 
LOS ESTEROS LAKE, N. MEX. (See Section 11 of Text) 
An earthfill dam with maximum height of 218 ft. and 1,865 ft. 
long for the purpose of flood control, irrigation and 
sedimentation storage located on Pecos River 7 miles north 
of Santa Rosa, N. Mex. Includes modification of existing 
Alamogordo Dam (USBR project) 29 miles southeast of 
Santa Rosa, N. Mex. on Pecos River. 
PECOS, TEX. (See Section 12 of Text) 
A combination of diversions, floodways, and levees to protect 
the city and agricultural lands from flood waters, together 
with a levee to protect the city from Pecos River overflows, 
RIO GRANDE BASIN, N. MEX. (See Section 13 of Text) 
Authorized to be appropriated $3,500,000 to be expended by 
the Dept. of the Army for partial accomplishment of 
approved general comprehensive plan for the Rio Grande Basin 
in N. Mex. and Colorado. 
Documents 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 93-143 and Public 
Law 93-251, 93rd Cong. 
H. Doc. 498, 87th Cong., 
2d sess. 1 
H. Doc. 207, 89th Cong., 
1st sess. 
H. Doc. 182, 89th Cong., 
1st sess.1 
H. Doc. 165, 89th Cong., 
1st sess. 
S. Doc. 117, 87th Cong., 
2d. sess. 
H. Doc. 339, 84th Cong., 
2d sess.' Sec. 203, 
Public Law 780, 83d 
Cong., 2d sess. 
H. Doc. 339, 84th Cong., 
2nd sess. Public Law 
780, 83rd Cong., 2nd 
sess. 
H. Doc. 243, 81st Cong., 
1st sess. 
17-18

TABLE 17-B (Continued) 
ALBUQUERQUE, N. MEX., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
July 14, 1960 
July 14, 1960 
March 26, 1964 
June 30, 1948 and 
May 17, 1950 
June 30, 1948 
May 17, 1950 
July 3, 1958 and 
Dec. 11, 1944 
Oct. 27, 1965 
Authorized to be appropriated an additional $39,000,000 
for Dept. of the Army for prosecution of comprehensive 
plan for the Rio Grande Basin. 
Authorized Cochiti Dam on Rio Grande and Gallisteo Dam on 
Galisteo Creek as additions to authorized comprehensive 
plan for Rio Grande Basin (Cochiti Dam was authorized 
in lieu of Low Chamita Dam of Chamita Reservoir Project 
on Rio Chama under "substitute plan"). Also authorized 
to be appropriated an additional $58,300,000 for Dept. of 
the Army for this addition to comprehensive plan for the 
Rio Grande Basin. 
COCHITI LAKE, N. MEX. (See Section 13B of Text) 
Earthfill dam 5.1 miles in length and maximum of 251 ft. in 
Height with controlled outlet and uncontrolled spillway, 
located on Rio Grande and across Santa Fe River. For 
flood control, sediment storage and irrigation release 
purposes. Authority for Low Chamita Dam on Rio Chama was 
abrogated when Cochiti Dam was authorized. 
Project was modified to provide for conservation and 
development of fish and wildlife resources and recreation, 
about 50,000 acre-feet of water for initial filling of a 
permanent pool of 1,200 surface acres in the reservoir, and 
thereafter sufficient water annually to offset evaporation 
from such area. 
RIO GRANDE FLOODWAY, N. MEX. (See Section 13E of Text) 
Channel rectification, levee enlargement and construction, 
and bank stabilization on Rio Grande between river mile 
123 and 394 (See Table 17E.) 
TRUTH OR CONSEQUENCES (HOT SPRINGS), N. MEX. 
(See Section 13F of Text) 
Approved comprehensive plan for Rio Grande Basin is set forth 
in the Report of the Chief of Engineers dated April 5, 1948, 
for flood control of Rio Grande basin. 
In addition to previous authorizations, the completion of 
the plan approved in the Flood Control Act of 1948, for 
the Rio Grande Basin, at an estimated cost of $39,000,000. 
TRINIDAD LAKE, COLO. (See Section 14 of Text) 
Earthfill dam 6,610 feet long and maximum of 200 feet in height 
with controlled outlet and uncontrolled spillway for flood 
control, sediment storage, irrigation and recreation purposes 
on Purgatoire River. Authorization of Trinidad Dam provides 
for abrogation of channel improvement project through city of 
Trinidad, Colo. at time construction of dam is initiated. 
Relieved City of Trinidad of responsibility for cash 
contribution toward cost of constructing Trinidad Dam. 
Public Law 516, 81st Cong., 
2d sess. 
S. Doc. 94, 86th Cong., 
Substitute Plan - S. Doc. 
94, 86th Cong., 
2d sess.1 
Public Law 88-293, 
88th Cong. 
H. Doc. 243, 81st Cong., 
1st sess.' and Public Law 
516, 81st Cong. 2d sess. 
H. Doc. 243, 81st Cong., 
1st sess. 
H. Doc. 243, 81st Cong., 
1st sess. 
H. Doc. 325, 84th Cong., 
2d sess. and H. Doc. 387, 
78th Cong., 2d sess. 
Public Law 89-298, 
89th Cong., Sec. 201. 
'Contains latest published maps. 
TABLE 17-C 
Project 
RIO GRANDE BASIN, N. MEX. 
RIO GRANDE BASIN, N. MEX.: EXISTING PROJECT 
(See Section 13 of Text) 
River 
Miles 
Above 
Mouth 
Nearest 
Town 
Drainage 
Area 
(square 
Mile) 
Abiquiu Dam Rio Chama 
Jemez Canyon Dam Jemez 
30 Espanola, 
2 Bernalillo, 
N. Mex. 
2,147 Earthfill 325 feet high, 
1,217,000 acre-feet 
capacity 
1,034 Earthfill 136 feet high, 
110,750 acre-feet 
capacity 
17-19 
Description 
Total 
Estimated 
Cost 
$21,272,300 
4,177,417

TABLE 17-C 
(Continued) 
Project 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
RIO GRANDE BASIN, N. MEX. 
RIO GRANDE BASIN, N. MEX.: EXISTING PROJECT 
(See Section 13 of Text) 
River 
Miles 
Above 
Mouth 
Nearest 
Town 
Drainage 
Area 
(square 
Mile) 
Rio Grande Floodway Rio Grande 
Cochiti Lake 
Galisteo Dam 
Rio Grande 
123 to 3941 
3401 
Galisteo Creek 
Cochiti, 
N. Mex. 
12 Waldo, 
N. Mex. 
- Channel rectification, 
levee enlargement and 
construction 
8,491 Earthfill 251 high feet, 
602,000 acre-feet 
capacity 
596 Earthfill, 158 feet high, 
89,000 acre-feet 
capacity 
23,844,0002 
93,500,000 
14,220,053 
'River mile 0 is at intersection of New Mexico-Texas State line with international boundary at E1 Paso, Texas. 
2Does not include non-Federal costs. 
TABLE 17-D RIO GRANDE FLOODWAY, N. MEX.: EXISTING PROJECT 
(See Section 13E of Test) 
Reach Location 
(river miles)' 
Truth or Consequences unit (formerly Hot Springs) 
San Acacia to Bosque del Apache unit 
Cochiti to Rio Puerco unit (not including Albuquerque unit) 
Albuquerque unit 
Espanola Valley unit 
123 to 129 
155 to 226 
236 to 340 
286 to 305 
366 to 394 
'River mile 0 being at intersection of New Mexico-Texas State line with international boundary at El Paso, Texas. 
2Deferred for restudy. 
3In addition, 1,650,000 incurred by the Bureau of Reclamation in this reach. 
4In addition, $75,000 incurred by local interests in this reach. 
5In addition, estimated cost to local interests is $69,000 (1970). 
TABLE 17-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Project 
Alamogordo diversion channel, Tularosa (closed) 
Basin, New Mexico 
Colorado Springs, Fountain que Bouille River, 
Colo. (Templeton Gap Floodway)' 
Creede, Willow Creek, Colo. (floodway)' 
Pinon Canyon Dam, Trinidad, Colo. 
(Sec. 212)1 
Pueblo Arkansas River, Colo. (floodway) 
levee extension)' 
Socorro diversion channel, tributaries of 
Rio Grande, New Mexico' 
For Last 
Full Report 
See Annual 
Report For 
1966 
1959 
1952 
1954 
1965 
Cost to June 30, 1975 
Construction 
189,356 
881,262 
219,789 
130,678 
201,958 
2,259,328 
1Completed. 
2Responsibility of local interests. 
17-20 
Description 
Total 
Estimated 
Cost 
Estimated 
Cost 
$11,400,600 
6,200,000 
(1960)2 
2,658,0003 
3,130,0004 
456,000 
(1970) 5 
Operation and 
Maintenance2 
_

LITTLE ROCK, ARK., DISTRICT* 
This District comprises northern and western 
portions of Arkansas, a portion of southern Missouri, 
and a small portion of eastern Oklahoma 
embraced in drainage basins of Arkansas River 
and tributaries above and exclusive of Pine Bluff, 
Ark., and below mouth of Poteau River, near Fort 
Smith, Ark., and drainage basins of White River 
and tributaries above Peach Orchard Bluff, Ark. 
In addition, Little Rock District has responsibility 
for planning, design, construction, and operation 
and maintenance of that portion of 
McClellan-Kerr Arkansas River Navigation 
System below Pine Bluff. Also, Little Rock District 
has responsibility for planning of Millican 
Lake project, Tex. Memphis District is responsible 
for nayigation maintenance on White River 
below Newport, Ark., and mouth of Wild Goose 
Bayou. White River downstream from mouth of 
Wild Goose Bayou is a part of McClellan-Kerr 
Arkansas River Navigation System. 
IMPROVEMENTS 
Navigation 
1. Arkansas River Basin, Ark., Okla., 
and Kans. ..................... 
2. Bank Stabilization & Channel 
Rectification Ark. ............. 
3. David D. Terry Lock and Dam 
(No. 6), Ark. ................. . 
4. Lock and Dam No. 2, Ark. ..... 
5 Lock and Dam No. 3, Ark. ..... 
6. Lock and Dam No. 4, Ark. ..... 
7. Lock and Dam No. 5, Ark. ..... 
8. Lock and Dam No. 9, Ark. ..... 
9. Lock and Dam No. 13, Ark. . . 
10. Maintenance and Repair Fleet and 
Marine Terminals, Ark. ....... 
11. Murray Lock and Dam (No. 7), 
Ark. ........................... 
12. Norrell Lock and Dam (No.1) and 
Entrance Channel, Ark. ..... 
13. Toad Suck Ferry Lock and Dam 
(No. 8), Ark ................ 
14. Other Authorized Navigation 
Projects ....................... 
15. 
16. 
17. 
18. 
Flood Control 
Bell Foley Lake, Ark. ......... 
Blue Mountain Lake, Ark. ..... 
Clearwater Lake, Mo ......... 
Little Rock Levee, Ark. (East 
End-Fourche Bayou) ....... 
Page Flood Control (cont) 
19. Millican Lake, Tex ............ 
18-2 20. Nimrod Lake, Ark. ........... 
21. Pine Mountain Lake, Ark. ..... 
18-2 22. Village Creek, Jackson and 
Lawrence Counties, Ark. ....... 
18-3 23. White River Basin (Little Rock 
18-3 District) ...................... 
18-3 24. Inspection of Completed Flood 
18-3 Control Projects ............... 
18-3 25. Other Authorized Flood Control 
18-3 Projects ..................... 
18-3 26. Flood Control Work under Special 
Authorization ................. 
18-4 
Page 
18-6 
18-6 
18-6 
18-7 
18-7 
18-8 
18-8 
18-8 
Multiple-Purpose Projects Including Power 
18-4 27. Beaver Lake, Ark ............. 18-9 
28. Bull Shoals Lake, Ark. ........ 18-9 
18-4 29. Dardanelle Lock and Dam (No. 10), 
Ark. ............ ............ 18-9 
18-4 30. Greers Ferry Lake, Ark. ....... 18-9 
31. Norfork Lake, Ark............. 18-10 
18-4 32. Ozark Lock and Dam (No. 12), 
Ark . ......................... 18-10 
33. Table Rock Lake, Mo.......... 18-11 
18-4 
18-4 
18-5 34. 
35. 
18-5 36. 
General Investigations 
Surveys ..................... 
Collection and Study of Basin Data 
Research and Development .... 
18-11 
18-11 
18-11 
* All costs and financial statements for projects are listed in table 18-A at end of this chapter. All other tables are referenced in 
text and also appear at end of this chapter. 
18-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. ARKANSAS RIVER BASIN, ARK., 
OKLA., AND KANS. 
Location. Arkansas River rises in Rocky Mountains 
near Leadville, Colo., and flows 
southeastward 1,459 miles through Colorado, 
Kansas, Oklahoma, and Arkansas to join Mississippi 
River 584 miles above Head of Passes, La. 
(See Geological Survey state maps, scale 1:500,- 
000, and flood control and navigation maps of 
Mississippi River, Cairo, Ill., to Gulf of Mexico, 
1970 edition, scale 1:62,500.) 
Previous projects. For details see page 1066, 
Annual Report for 1932, and pages 744, 864, and 
881, Annual Report for 1943. 
Existing project. Provides for improvement of 
Arkansas River Basin by construction of coordinated 
developments for navigation, hydroelectric 
power, flood control, water supply, sediment 
control, recreation, and fish and wildlife 
propagation. McClellan-Kerr Arkansas River 
Navigation System provides a channel 9 feet deep 
and 447.5 miles long, beginning at mouth of 
White River, which enters Mississippi River 599 
miles above Head of Passes, La., thence 10 miles 
upstream to mouth of Wild Goose Bayou; thence 9 
miles by a land cut, designated as Arkansas Post 
Canal to mile 42 (1943 survey) on Arkansas River; 
thence 378.2 miles along channel of latter stream 
to mouth of Verdigris River at navigation mile 
397.2; thence 50.3 miles up Verdigris River to 
head of navigation at Catoosa, Okla. Waterway is 
canalized throughout its length by 17 locks and 
dams with total lift of 420 feet. Dardanelle, 
Ozark, Robert S. Kerr, and Webbers Falls are 
multiple-purpose projects including power. Lock 
chambers are 110 by 600 feet. A minimum 
channel width of 150 feet is provided for Verdigris 
River, 250 feet for Arkansas River, and 300 
feet for Arkansas Post Canal and White River. 
Other coordinated developments consist of 15 
lakes, of which 13 are in Tulsa District, Kansas 
and Oklahoma, and two in Little Rock District. 
Pertinent data and estimated Federal cost are 
summarized in Tables 18-C and 18-D, Arkansas 
River Basin; Ark., Okla., and Kans.: 
Navigation/Lakes. For authorization see Table 
18-B, Authorizing Legislation. 
Local cooperation. For McClellan-Kerr Arkansas 
River Navigation System, local interests must 
provide adequate terminal and transfer facilities 
and bear increased cost of maintenance and 
operation of all altered rail and highway routes, 
including bridges and appurtenances, utilities, 
and other existing improvements, other than 
federally owned. For lakes see requirements for 
each individual lake. 
Terminal facilities. Public port facilities were 
in operation at Pine Bluff, Little Rock, Dardanelle, 
and Fort Smith, Ark., and Muskogee and 
Catoosa (Tulsa), Okla. Port authorities have been 
organized to develop public facilities at North 
Little Rock, Russellville, Clarksville, and Van 
Buren, Ark. Private commercial port facilities 
are complete and in operation at seven locations 
in Arkansas and at five locations in Oklahoma. 
Ten additional private port facilities are being 
developed along improved waterways in the State 
of Arkansas and one in Oklahoma. 
Operations and results during fiscal year. Blue 
Mountain, Canton, Dardanelle Lock and Dam 
(No. 10), Dardanelle Marine Terminal, David D. 
Terry Lock and Dam (No. 6), Elk City, Eufaula, 
Fall River, Fort Gibson, Keystone, W. D. Mayo 
Lock and Dam (No. 14), Chouteau Lock and Dam 
(No. 17), Newt Graham Lock and Dam (No. 18), 
Robert S. Kerr Lock and Dam and Reservoir (No. 
15), Webbers Falls Lock and Dam (No. 16), and 
Oologah; Locks and Dams Nos. 2, 3, 4, 5, 9, and 13, 
Markham Ferry, Murray Lock and Dam (No. 7), 
Nimrod, Norrell Lock and Dam (No. 1), Ozark 
Lock and Dam (No. 12), Pensacola, Pine Bluff 
Marine Terminal, Robert S. Kerr Marine Terminal, 
Tenkiller Ferry, Toad Suck Ferry Lock 
and Dam (No. 8), Toronto, and Wister were in 
operation. Construction continued on powerplant 
at Ozark and on bank stabilization. For details of 
McClellan-Kerr Arkansas River Navigation 
System and lakes in Oklahoma and Kansas, see 
report of Tulsa District. Details of McClellan- 
Kerr Arkansas River Navigation System and 
lakes in Arkansas are shown on following pages. 
Condition at end offiscal year. See Tables 18-C 
and 18-D, Arkansas River Basin; Ark., Okla., and 
Kans.: Navigation/Lakes for status of individual 
items, navigation project, lakes, and basin plan. 
2. BANK STABILIZATION & CHANNEL 
RECTIFICATION, ARK. 
Location. Several bank stabilization and 
channel rectification projects are laid out in 
various reaches extending from fixed point to fixed 
point on Arkansas River from 33.7 to 362 miles 
above mouth and across the Arkansas-White 
cutoff, a 4- to 5-mile natural channel joining 
Arkansas and White Rivers about 18 and 12 miles 
above their respective mouths. 
Existing project. Bank stabilization and 
18-2

LITTLE ROCK, ARK., DISTRICT 
channel rectification is a part of McClellan-Kerr 
Arkansas River Navigation System. See table 18- 
E for reach and location of each bank stabilization 
and channel rectification project. Estimated 
cost is $119,300,000 for existing project in Little 
Rock District. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. See requirements for entire 
project under Section 1. 
Operations and results during fiscal year. 
Inspection was made of all existing works, and 
surveys made of damaged portions. Engineering 
and design studies continued for new work and 
repairs to damaged works. Operations by reaches 
are summarized in table 18-F. 
Condition at end of fiscal year. Emergency 
bank stabilization and channel rectification work 
on Arkansas River in Little RoCk District was 
begun in March 1950 and completed in August 
1961. Remaining bank stabilization and channel 
rectification work proposed for existing project 
was begun in February 1961. Completed work is 
98 percent of that proposed for existing project in 
Little Rock District. Condition of each reach is 
summarized in table 18-G. 
3. DAVID D. TERRY LOCK AND DAM 
(NO. 6), ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1. 
Operations and results during fiscal year. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in January 1965 and lock and dam was 
placed in operation in August 1968. 
4. LOCK AND DAM NO. 2, ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1. 
Operations and results during fiscal year. 
Operation and maintenance continued. Construction 
of minor completion items conitinued. 
Condition at end of fiscal year. Construction 
began in May 1963. Lock was placed in operation 
in April 1967 and dam was placed in operation in 
March 1968. 
5. LOCK AND DAM NO. 3, ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1. 
Operations and results during fiscal year. 
Construction of minor completion items continued. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in May 1964 and lock and dam was placed 
in operation in December 1968. 
6. LOCK AND DAM NO. 4, ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1. 
Operations and results during fiscal year. 
Construction continued on minor completion 
items. Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in May 1964 and lock and dam was placed 
in operation in December 1968. 
7. LOCK AND DAM NO. 5, ARK. 
Location, previous project, existing project, local 
'cooperation, and terminal facilities. See Section 
1. 
Operations and results during fiscal year. 
Construction of minor completion items continued. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in November 1964 and lock and dam was 
placed in operation in December 1968. 
8. LOCK AND DAM NO. 9, ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1. 
Operations and results during fiscal year. Continued 
construction of minor completion items. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in April 1965 and lock and dam was placed 
in operation in July 1969. 
9. LOCK AND DAM NO. 13, ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1.
Operations and results during fiscal year. Continued 
construction of minor completion items. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in October 1965 and lock and dam was 
placed in operation in April 1969. 
18-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
10. MAINTENANCE AND REPAIR 
FLEET AND MARINE TERMINALS, 
ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1.
Operations and results during fiscal year. Continued 
acquisition of equipment. 
Condition at end of fiscal year. Construction of 
Pine Bluff Marine Terminal began March 1968 
and it was placed in operation in April 1969. Construction 
of Dardanelle Marine Terminal began 
June 1968 and it was placed in operation in 
November 1969. 
11. MURRAY LOCK AND DAM (NO. 7), 
ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1.
Operations and results during fiscal year. Continued 
construction of minor completion items. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in November 1964 and lock and dam was 
placed in operation in October 1969. 
12. NORRELL LOCK AND DAM (NO. 1) 
AND ENTRANCE CHANNEL, ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1.
Operations and results during fiscal year. 
Construction continued on minor completion 
items. Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in May 1963 and lock and dam was placed 
in operation in June 1967. 
13. TOAD SUCK FERRY LOCK AND DAM 
(NO. 8), ARK. 
Location, previous project, existing project, local 
cooperation, and terminal facilities. See Section 
1.
Operations and results during fiscal year. Continued 
construction of minor completion items. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in July 1965 and lock and dam was placed 
in operation in November 1969. 
14. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 18-H, Other Authorized Navigation 
Projects. 
Flood Control 
15. BELL FOLEY LAKE, ARK. 
Location. Bell Foley Damsite is at mile 27.6 on 
Strawberry River in Sharp County, 5 miles east 
of Poughkeepsie, Ark. (See Geological Survey 
map, "Poughkeepsie, Ark.," scale 1:125,000.) 
Existing project. Provides for construction of an 
earth embankment dam approximately 2,570 
feet long and 150 feet high above the streambed. 
There will be an uncontrolled spillway through a 
natural saddle in the right abutment. A multiplelevel 
intake and a 10-foot-diameter by 1,200-footlong 
conduit will be used for flood and low-flow 
release. Lake will be one unit of a comprehensive 
plan for flood control, recreation, and fish and 
wildlife purposes in White River Basin. It will 
control runoff from 519 square miles. Capacity 
will be 518,200 acre-feet, of which 350,000 will be 
for flood control and 168,200 will be for conservation. 
Estimated cost of project is $56,800,000. For 
authorization see Table 18-B, Authorizing 
Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 and Federal Water Project Recreation 
Act apply. Assurances of local cooperation were 
furnished by Arkansas Soil and Water Conservation 
Commission by letter dated July 3, '1974. By 
letter dated July 8, 1975, Governor David Pryor 
stated that the Arkansas constitution restricts 
any State official from giving a commitment, unless 
there is first a specific appropriation by the 
legislature to meet the obligation. 
Operations and results during fiscal year. 
Preconstruction planning was deferred. 
Condition at end of fiscal year. Preconstruction 
planning is 80 percent complete. Project is less 
than 1 percent complete. 
16. BLUE MOUNTAIN LAKE, ARK. 
Location. See Table 18-D, Arkansas River 
Basin, Ark., Okla., and Kans.: Lakes. 
Existing project. Estimated cost is $5,322,000, 
of which $551,000 is Code 711 funds. For further 
information see pages 906 and 907 of 1962 Annual 
Report. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 applies. 
18-4

LITTLE ROCK, ARK., DISTRICT 
Operations and results during fiscal year. 
Operation and maintenance of project continued. 
Additional recreational facilities were constructed. 
Six notable rises occurred on Petit Jean 
River during fiscal year. Flooding was prevented 
on an average of 11,640 acres of improved land for 
each flood. Results of flood regulation on river 
stages at Danville are set forth in Table 18-I, 
Flood Modifications, Blue Mountain Lake. Danville 
is 25.6 miles downstream and just 
downstream from mouth of Dutch Creek, which 
is the principal tributary of Petit Jean River. 
Estimated monetary benefits for last fiscal 
year attributed to Blue Mountain Lake for 
prevention of flood damages were $896,000, a 
total of $8,069,000 to June 30, 1975. Pool elevation 
at start of fiscal year was 386.97 feet above mean 
sea level, corresponding to 34,030 acre-feet of 
total storage. At end of fiscal year pool elevation 
was 386.81 feet above mean sea level, corresponding 
to 33,490 acre-feet of total storage. Maximum 
pool level during fiscal year was 404.06 feet 
above mean sea level, corresponding to 121,050 
acre-feet of total storage. Minimum pool level 
during fiscal year was 383.95 feet above mean sea 
level, corresponding to 24,480 acre-feet of total 
storage. Seasonal conservation pool, elevation 
387.00, was used April 15 to May 1. Conservation 
pool was lowered gradually during warm months 
as an aid in control of mosquitoes. Sufficient 
releases were made from lake during low-water 
periods to meet water requirements downstream. 
Condition at end of fiscal year. Project is complete 
except for additional recreation facilities. 
Construction of project began in May 1940, and it 
was ready for beneficial use in March 1947. 
17. CLEARWATER LAKE, MO. 
Location. See Table 18-J, White River Basin. 
Existing project. Estimated cost is $10,527,000, 
of which $789,000 is Code 711 funds. For further 
information see pages 897 and 898 of 1962 Annual 
Report. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 applies. 
Operations and results during fiscal year. 
Operation and maintenance of project continued. 
Additional recreation facilities were constructed. 
Four notable rises occurred on Black River above 
Clearwater Lake. Flooding was prevented on an 
average of 15,475 acres of cultivated land for each 
rise. Results of regulation on river stages at Poplar 
Bluff, 46.4 miles downstream, are set forth in 
Table 18-I, Flood Modifications, Clearwater 
Lake. 
Estimated monetary benefits attributed to 
Clearwater Lake for prevention of flood damages 
were $1,429,000, a total of $15,331,000 to June 30, 
1975. Pool elevation at start of fiscal year was 
499.79 feet above mean sea level, corresponding 
to 32,330 acre-feet of total storage. At end of fiscal 
year pool elevation was 497.11 feet above mean 
sea level, corresponding to 27,216 acre-feet of 
total storage. Maximum pool elevation was 
521.80 feet above mean sea level, corresponding 
to 98,810 acre-feet of total storage. Minimum pool 
level was 493.80 feet above mean sea level, corresponding 
to 21,590 acre-feet of total storage. 
Seasonal conservation pool, elevation 498.00, was 
used on May 1 to June 1. Conservation pool elevation 
was fluctuated during warm months as an 
aid in control of mosquitoes. Releases made from 
lake during low-water periods were sufficient to 
supply municipal water for Poplar Bluff and 
other usages. 
Condition at end of fiscal year. Project is complete 
except for additional recreational facilities. 
Construction of project began in June 1940 and 
was ready for beneficial use in March 1948. 
18. LITTLE ROCK LEVEE, ARK. (EAST 
END-FOURCHE BAYOU) 
Location. On right bank of Arkansas River 
between river miles 164.5 and 161.2 or navigation 
miles 115.9 and 112.0 in eastern part of city of Little 
Rock, Ark. (See Geological Survey map of Little 
Rock, Ark.) 
Existing project. Provides for levee 7.2 miles 
long beginning at high ground in Little Rock opposite 
river mile 164.5 and extending 
downstream along Arkansas River to river mile 
161.2 near Fourche Bayou, and thence upstream 
along left bank of bayou to mile 14.5 where it connects 
to high ground. Project also provides a 
sump and borrow area 3,000 feet long on landside 
of levee fronting on Arkansas River, a channel 
cutoff in Fourche Bayou at a bend which is crossed 
by levee, two pumping stations on Arkansas 
River side, and five drainage structures through 
levee. A 30,000 gallon per minute pumping station 
in conjunction with excavated and natural 
sump area is constructed on Fourche Creek near 
end of levee where gravity drainage through two 
36-inch culverts is blocked by high stages. Completed 
levee cost $1,188,277, of which $883,277 
was Federal and $305,000 local interest cost for 
rights-of-way. Estimated cost of additional 
18-0

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
pumping station and sump area is $473,000, of 
which Federal cost is $457,000 and local interest 
cost is $16,000 for a cash contribution toward construction 
cost to compensate for any encroachment 
on sump area occurring after District 
Engineer's report. Estimated cost of project is 
$1,708,277, of which $1,387,277 is Federal and 
$321,000 is local interest cost of rights-of-way and 
cash contribution. For authorization see Table 
18-B, Authorizing Legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936 applies. 
Operations and results during fiscal year. 
Operation and maintenance performed by local 
interest. 
Condition at end offiscal year. Levee, two pumping 
stations, sump area, channel cutoff, and five 
drainage structures completed and transferred 
to local interests for maintenance and operation, 
December 1950. Construction was initiated in 
June 1973 and completed February 1975. 
19. MILLICAN LAKE, TEX. 
Location. Damsite is located at river mile 24.1 
on the Navasota River, about 18 miles southwest 
of Bryan, Tex., and about 7 miles north of 
Navasota, Tex. 
Existing project. The plan of improvement 
provides for construction of a concrete and 
earthfilled dam, with a maximum height of 83 
feet above the streambed, with a total length of 
25,300 feet, including a gate controlled ogee-type 
spillway, 472 feet long, controlling 2,120 square 
miles of drainage area. The lake will have a total 
controlled storage of 1,557,400 acre-feet, with a 
water surface area of 66,000 acres. The total 
storage includes 784,800 acre-feet for control, 
680,200 acre-feet for water supply, and 92,400 
acre-feet for sediment reserve. Estimated 
Federal cost of the project is $160,000,000. Project 
was authorized by River and Harbor Act of 
1968 (H. Doc. 341, 90th Cong., 2d sess.). 
Local cooperation. The Water Supply Act of 
1958, as amended, and the Flood Control Act of 
1936, as amended, apply. The Brazos River 
Authority, a State agency, by letter dated July 22, 
1969, certified assurances required of local interests 
for water supply. The Governor of Texas 
by letter dated December 19, 1969, reaffirmed 
the State's intent to participate for recreation and 
fish and wildlife cost. 
Operations and results during fiscal year. 
Preconstruction planning continued. A special 
lignite appraisal was made. 
Condition at end of fiscal year. Preconstruction 
planning is 48 percent complete. 
20. NIMROD LAKE, ARK. 
Location. See Table 18-D, Arkansas River 
Basin, Ark., Okla., and Kans.: Lakes. 
Existing project. Estimated cost is $4,330,000, 
of which $558,000 is Code 711 funds. For further 
information see pages 908 and 909 of 1962 Annual 
Report. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 applies. 
Operations and results during fiscal year. 
Operation and maintenance of project continued. 
Additional recreation facilities were constructed. 
Six notable rises occurred on Fourche La Fave 
River during fiscal year. Flooding was prevented 
on an average of 3,173 acres of improved land. 
Results of flood regulation of river stages at Aplin 
are set forth in Table 18-I, Flood Modifications, 
Nimrod Lake. Aplin is 13.7 miles downstream 
from dam and just downstream from mouth of 
South Fourche La Fave River, which is principal 
tributary. 
Estimated monetary benefits for fiscal year 
1975 attributed to Nimrod Lake for prevention of 
flood damages were $287,000 making a total of 
$5,009,000 to June 30, 1975. Pool elevation at start 
of fiscal year was 361.98 feet above mean sea 
level, corresponding to 173,280 acre-feet of total 
storage. At end of fiscal year pool elevation was 
345.60 feet above mean sea level, corresponding 
to 43,980 acre-feet of total storage. Maximum 
pool level for the project and during fiscal year 
was 365.05 feet above mean sea level, corresponding 
to 210,450 acre-feet of storage. Minimum 
pool level during fiscal year was 342.08 feet above 
mean sea level, corresponding to 29,290 acre-feet 
of total storage. Seasonal conservation pool, elevation 
345.00, was used May 1 to May 15. Conservation 
pool was lowered gradually during warm 
months as an aid in control of mosquitoes. Sufficient 
releases were made from lake during lowwater 
periods to meet water requirements 
downstream. 
Condition at end of fiscal year. Project is complete 
except for additional recreation facilities. 
Construction of project began in January 1940 
and was ready for beneficial use in January 1942. 
21. PINE MOUNTAIN LAKE, ARK. 
Location. Damsite is at mile 35.7 on Lee Creek 
and 12 miles north of Van Buren, Ark. (See 
18-6

LITTLE ROCK, ARK., DISTRICT 
Geological Survey map "Winslow, Ark.-Okla.," 
scale 1:125,000.) 
Existing project. Provides for construction of a 
lake for flood control, water supply, and recreation. 
Lake would control runoff from 168 square 
miles. Capacity would be 124,160 acre-feet, of 
which 40,320 would be for flood control, 81,340 
for water supply, and 2,500 for sediment reserve. 
Estimated cost is $23,200,000, of which local interests 
will repay $13,800,000 for water supply 
storage. Project was authorized by Flood Control 
Act of 1965. 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Federal Water Project Recreation Act apply. 
Operations and results during fiscal year. 
Preconstruction planning was resumed. 
Condition at end of fiscal year. Planning is 43 
percent complete. Project is 3 percent complete. 
22. VILLAGE CREEK, JACKSON AND 
LAWRENCE COUNTIES, ARK. 
Location. A tributary on the left bank of the 
White River, rising in Randolph County in 
northeast Arkansas and flowing southward 
through Jackson and Lawrence Counties to join 
the White River at mile 250.7, about 7 miles south 
of Newport, Ark. (See Mississippi River Commission 
alluvial valley map, scales 1:500,000 and 
1:62,500.) 
Existing project. The project provides for an 
improvement for flood control and drainage in 
the Village Creek Basin. It will consist of a 
cleared and enlarged channel for Village Creek 
from mile 61.2 to its mouth and a system of group 
laterals and on-farm drainage facilities to be constructed 
by local interest. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936 applies. Requirements fully complied 
with. 
Condition at end of fiscal year. Preconstruction 
planning was initiated. 
23. WHITE RIVER BASIN (LITTLE ROCK 
DISTRICT) 
Location. Improvements are on White River 
and tributaries, Arkansas and Missouri. More 
definite location of individual items is shown in 
Table 18-J, White River Basin. 
Existing project. A general comprehensive plan 
for flood control and other purposes in White 
River Basin. Plan now includes nine lakes, of 
which four are flood control only projects and five 
are multiple-purpose projects. Beaver, Table 
Rock, Bull Shoals, Norfork, Clearwater, Greers 
Ferry, and Bell Foley Lakes were selected and 
approved for construction by Chief of Engineers, 
and individual reports on these seven lakes are 
presented on subsequent pages. Lakes in plan are 
listed in Table 18-J, White River Basin. For 
authorization see Table 18-B, Authorizing 
Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 applies, Water Supply Act of 1958, as 
amended, applies to Beaver, Greers Ferry, and 
Norfork. 
Operations and results during fiscal year. Five 
notable rises occurred above Beaver, Table Rock, 
and Bull Shoals Dams on upper White River and 
above Norfork Dam on North Fork River during 
fiscal year. Regulation of flow on North Fork 
River in Norfork Lake and on upper White River 
in Beaver-Table Rock-Bull Shoals Lake 
system during fiscal year prevented flooding on 
an average of 48,564 acres of improved land for 
each rise, of which 39,198 and 9,366 was credited 
to Beaver-Table Rock-Bull Shoals system and 
Norfork, respectively. Flood modifications on 
White River at Calico Rock, 17 miles downstream 
from mouth of North Fork River and 59 miles 
downstream from Bull Shoals Dam, and at Newport, 
102 miles downstream from Calico Rock, 
are set forth in Table 18-K, White River Flood 
Modifications. 
Estimated monetary flood control benefits for 
fiscal year 1975 attributed to Beaver, Table Rock, 
Bull Shoals, and Norfork Lakes for prevention of 
flood damages were $1,548,000, $3,787,000, $2,- 
253,000, and $395,000, respectively, a total of $7,- 
983,000. Total flood damages prevented by lakes 
through fiscal year 1975 amounted to $55,785,- 
000, of which $6,170,000 accrues to Beaver, $17,- 
754,000 to Table Rock, $23,051,000 to Bull Shoals, 
and $8,810,000 to Norfork. Pool elevation at 
Beaver Lake at start of fiscal year was 1125.52 
feet above mean sea level, corresponding to 1,- 
813,100 acre-feet of total storage. At end of fiscal 
year pool elevation was 1117.41 feet above mean 
sea level, corresponding to 1,580,000 acre-feet of 
total storage. Maximum pool elevation was 
1127.04 feet above mean sea level, corresponding 
to 1,859,300 acre-feet of total storage. Minimum 
pool elevation was 1115.85 feet above mean sea 
level, corresponding to 1,537,700 acre-feet of total 
storage. Pool elevation of Table Rock Lake at 
start of fiscal year was 923.05 feet above mean sea 
level, corresponding to 3,065,900 acre-feet of total 
storage; and at end of fiscal year was 915.44 feet 
above mean sea level, corresponding to 2,720,900 
acre-feet of total storage. Maximum pool eleva- 
18-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
tion during fiscal year was 924.03 feet above 
mean sea level, corresponding to 3,112,500 acrefeet 
of total storage. Minimum pool elevation during 
fiscal year was 913.49 feet above mean sea 
level, corresponding to 2,637,600 acre-feet of total 
storage. Pool elevation of Bull Shoals Lake at 
start of fiscal year was 678.93 feet above mean sea 
level, corresponding to 4,354,900 acre-feet of total 
storage; and at end of fiscal year was 653.15 feet 
above mean sea level, corresponding to 3,009,800 
acre-feet of total storage. Maximum pool elevation 
was 678.93 feet above mean sea level, corresponding 
to 4,354,900 acre-feet of total storage. 
Minimum pool elevation was 649.45 feet above 
mean sea level, corresponding to 2,846,400 acrefeet 
of total storage. Pool elevation of Norfork 
Lake at start of fiscal year was 568.65 feet above 
mean sea level, corresponding to 1,656,500 acrefeet 
of total storage. At end of fiscal year pool 
elevation was 550.91 feet above mean sea level, 
corresponding to 1,227,300 acre-feet of total 
storage. Maximum pool elevation was 568.65 feet 
above mean sea level, corresponding to 1,656,500 
acre-feet of total storage. Minimum pool elevation 
was 550.91 feet above mean sea level, corresponding 
to 1,227,300 acre-feet of total storage. 
Delivered 2,957,981,100 kilowatt-hours of electrical 
energy to Southwestern Power Administration 
for marketing, of which 278,569,- 
000; 879,110,000; 1,480,043,000; and 320,259,100 
kilowatt-hours were generated at Beaver, Table 
Rock, Bull Shoals, and Norfork powerplants, 
respectively. Peak demands of 128,000 kilowatts 
occurred November 16, 1974 at Beaver; 232,000 
kilowatts on November 11, 1974 at Table Rock; 
397,000 kilowatts on August 5, 1974 at Bull 
Shoals; and 80,000 kilowatts on July 1974 at Norfork. 
There was sufficient power storage at all 
times to supply scheduled loads. Installed 
capacities of plants are 112,000; 200,000; 340,000; 
and 70,000 kilowatts at Beaver, Table Rock, Bull 
Shoals, and Norfork, respectively. During fiscal 
year 1,609,660; 4,734,120; 7,979,580; and 2,006,- 
020 acre-feet of water was released through turbines 
at Beaver, Table Rock, Bull Shoals, and 
Norfork, respectively. At start of fiscal year there 
were 161,200; 363,900; 1,306,900; and 405,300 
acre-feet of flood control storage in use at Beaver, 
Table Rock, Bull Shoals, and Norfork, respectively. 
At end of fiscal year there were 71,900; 38,200; 
and 23,900 acre-feet of storage capacity available 
for storage of floodflows in Beaver, Bull Shoals, 
and Norfork power pools, respectively, and 18,- 
900 acre-feet of flood control storage in use at 
Table Rock. Capacities available in power pools 
before each flood are shown in Table 18-K, White 
River Flood Modifications. During fiscal year 
21,900 acre-feet of water was released from Norfork 
Lake for Fish and Wildlife Service trout 
hatchery; 14,600 acre-feet was released from 
Table Rock Lake for Missouri Conservation Commission 
trout hatchery; Beaver Water District 
withdrew 6,436 million gallons from Beaver 
Lake; and Water and Sewer Improvement District 
No. 3 of Mountain Home, Ark., withdrew 
303 million gallons from Norfork Lake. 
Condition at end of fiscal year. Beaver, Table 
Rock, Bull Shoals, Norfork, Clearwater, and 
Greers Ferry Lakes are essentially complete and 
in operation. Preconstruction planning was 
deferred on Bell Foley. Progress on these lakes is 
in individual reports. Preconstruction planning 
for Water Valley Lake and Lone Rock Lake has 
not been initiated. 
24. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and 
maintenance of flood control works, Part 208 of 
Title 33, Code of Federal Regulations, provide for 
periodic inspection of completed projects 
transferred to local interests for operation and 
maintenance. Inspections of local flood protection 
projects, shown in Section 25 as completed projects, 
were made October-March to determine extent 
of compliance with approved regulations for 
maintenance and operation of these projects. 
Responsible officials of improvement districts 
concerned were advised of inadequacies in 
maintenance and operation of local flood protection 
works under their jurisdiction where appropriate. 
Fiscal year cost was $89,031. Total cost 
to end of fiscal year was $428,491. 
25. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 18-L, Other Authorized Flood Control 
Projects. 
26. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal cost for fiscal year was $176,394, of 
which $40,100 was for advance preparation and 
$1,925, $42,017, $15,387, $63,510, and $13,455 
was for flood emergency operations at Batemen 
Levee District, Butler County Levee District No. 
7, Jackson County Levee District, Little Red 
18-8

LITTLE ROCK, ARK., DISTRICT 
Levee District No. 2, and Conway County Levee 
District No. 3, respectively. 
Emergency bank protection for Little Rock 
waste water sewer line (Section 14, Flood Control 
Act of 1946, Public Law 526, 79th Cong.) Arkansas 
River, Little Rock, Ark. Costs for fiscal year 
were $3,600. 
Multiple-Purpose Projects Including Power 
27. BEAVER LAKE, ARK. 
Location. See Table 18-J, White River Basin. 
Existing project. Estimated cost is $49,403,000, 
of which $2,982,000 is Code 711 funds, and $1,- 
360,000 is Code 712 funds. For further information 
see pages 788 and 789 of 1966 Annual Report. 
For authorization see Table 18-B, Authorizing 
Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 and Water Supply Act of 1958, as amended, 
apply. 
Operations and results during fiscal year. 
Results of operation of Beaver Lake are shown in 
Section 23 and flood modifications are shown in 
Table 18-K, White River Flood Modifications. 
Operation and maintenance continued. Additional 
recreation facilities were constructed. 
Condition at end of fiscal year. Project is complete 
except for additional recreational facilities. 
Construction of project began in October 1959 
and was placed in operation for flood control in 
December 1963, hydroelectric power generation 
with both units in May 1965, and water supply in 
January 1966. 
28. BULL SHOALS LAKE, ARK. 
Location. See Table 18-J, White River Basin. 
Existing project. Estimated cost with eight 
generating units is $93,400,000, of which $3,485,- 
000 is Code 711 funds and $3,961,000 is Code 712 
funds. For further information see pages 725 and 
726 of 1965 Annual Report. For authorization see 
Table 18-B, Authorizing Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 applies. 
Operations and results during fiscal year. Additional 
recreation facilities were constructed. 
Operation and maintenance of project continued. 
Results of operation of Bull Shoals Lake are 
shown in Section 23 and flood modifications are 
shown in Table 18-K, White River Flood 
Modifications. 
Condition at end of fiscal year. Project is complete 
except for additional recreation facilities. 
Construction of project began in April 1946 and 
was ready for beneficial use for flood control in 
June 1951 and generation of electrical energy in 
September 1952. Units 1 through 8 were placed 
in operation September 1952, September 1952, 
December 1952, June 1953, January 1962, 
February 1962, August 1963, and September 
1963, respectively. 
29. DARDANELLE LOCK AND DAM (NO. 
10), ARK. 
Location. See Table 18-C, Arkansas River 
Basin; Ark., Okla., and Kans.: Navigation. 
Existing project. Project is a unit of McClellan- 
Kerr Arkansas River Navigation System. Dam is 
2,569 feet long and 68 feet high. It has a spillway 
with 20 tainter gates 50 feet long and 39 feet high. 
Navigation lock is 110 by 600 feet with a lift of 54 
feet. Powerhouse contains four 31,000 kilowatt 
generators. Lake has a storage capacity of 486,- 
000 acre-feet. Estimated cost is $84,008,000, of 
which $1,708,000 is Code 711 funds. For 
authorization see Table 18-B, Authorizing 
Legislation. 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Pool 
fluctuated within 2-foot power pondage, elevation 
336.00 to 338.00. Power generation continued. Installed 
capacity is 124,000 kilowatts. Delivered 
892,394,500 kilowatt-hours of electrical energy to 
Southwestern Power Administration for 
marketing. Peak demand of 140,000 kilowatts occurred 
July 2, 1974. Released 28,143,580 acre-feet 
of water through turbines. Major accomplishments 
with regular funds: Operation 
and maintenance continued at cost of $1,634,876. 
Continued design of additional recreation 
facilities. 
Condition at end of fiscal year. Construction 
began June 1957. Power units were placed on line 
April, May, and September 1965, and January 
1966. Lock was placed in operation in December 
1969. 
30. GREERS FERRY LAKE, ARK. 
Location. See Table 18-J, White River Basin. 
Existing project. Estimated cost is $51,174,000, 
of which $4,129,000 is Code 711 funds. For 
further information see page 740 of 1964 Annual 
Report. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 and Water Supply Act of 1958, as amended, 
apply. 
18-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. 
Operation and maintenance continued. Additional 
recreation facilities were constructed. 
Four notable rises occurred on the Little Red 
River above Greers Ferry Dam. Flooding was 
prevented on 4,920 acres of improved land. 
Results of flood regulation on river stages at Judsonia, 
54 miles downstream, are set forth in Table 
18-I, Flood Modifications, Greers Ferry Lake. 
Estimated monetary flood control benefits for 
last fiscal year attributed to Greers Ferry Lake 
for prevention of flood damages were $317,000. 
Total flood damages prevented to June 30, 1975 
were $2,712,000. Pool elevation at start of fiscal 
year was 468.75 feet above mean sea level, corresponding 
to 2,164,500 acre-feet of total storage. 
At end of fiscal year pool elevation was 458.88 feet 
above mean sea level, corresponding to 1,844,300 
acre-feet of total storage. Maximum pool elevation 
was 475.08 feet above mean sea level, corresponding 
to 2,387,400 acre-feet of total storage. 
Minimum pool elevation was 454.90 feet above 
mean sea level, corresponding to 1,724,000 acrefeet 
of total storage. At start of fiscal year there 
was 254,000 acre-feet of flood storage in use and 
at end of fiscal year 66,200 acre-feet of storage 
capacity was available for storage of floodflows in 
power pool. Delivered 300,480,800 kilowatt-hours 
of electrical energy to Southwestern Power Administration 
for marketing. Peak demand of 
110,000 kilowatts occurred July 2, 1974. During 
fiscal year, 1,769,820 acre-feet of water was 
released through turbines; 14,600 acre-feet was 
released for US Fish and Wildlife Service trout 
hatchery; the Community Water System, 
Cleburne County, Ark., withdrew 70 million 
gallons; and the city of Clinton, Ark., withdrew 
204 million gallons from Greers Ferry Lake. 
Condition at end of fiscal year. Project is complete 
except for additional recreation facilities. 
Construction of project began in June 1957, was 
ready for beneficial use for flood control in 
January 1962, and power units 1 and 2 were placed 
in operation in March and May 1964, and 
water supply was placed in operation in April 
1971. 
31. NORFORK LAKE, ARK. 
Location. See Table 18-J, White River Basin. 
Existing project. Estimated cost is $74,590,000, 
of which $2,268,000 is Code 711 funds, $22,700,- 
000 is for addition of power units 3 and 4, and 
$20,900,000 is for highway bridge construction. 
For further information see page 896 of 1962 Annual 
Report. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 and Water Supply Act of 1958, as amended, 
apply. 
Operations and results during fiscal year. 
Operation and maintenance of project continued. 
Additional recreation facilities were constructed. 
Results of operation of Norfork Lake are shown in 
Section 23 and flood modifications are shown in 
Table 18-K, White River Flood Modifications. 
Condition at end of fiscal year. Project is complete 
except for additional recreation facilities. 
Construction of project began in October 1940, 
ready for beneficial use for flood control in June 
1943, and for generation of electrical energy with 
one unit in June 1944. Second unit was added in 
February 1950. Water supply was added as a purpose 
in December 1969. 
32. OZARK LOCK AND DAM (NO. 12), 
ARK. 
Location. See Table 18-C, Arkansas River 
Basin; Ark., Okla., and Kans.: Navigation. 
Existing project. Project is a unit of McClellan- 
Kerr Arkansas River Navigation System. Dam is 
2,200 feet long and 58 feet above streambed. It has 
a spillway with 15 tainter gates 50 feet long and 
46 feet high. Navigation lock is 110 by 600 feet 
with a lift of 34 feet. Powerhouse contains five 20,- 
000 kilowatt generators. Lake has a storage 
capacity of 148,000 acre-feet. In addition, 1 foot of 
power pondage is provided in Pool No.13 between 
elevations 391.00 and 392.00. Estimated cost is 
$84,700,000. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Continue 
construction of powerplant and of minor 
completion items. Delivered 554,653,400 
kilowatt-hours of electrical energy to 
Southwestern Power Administration for 
marketing. Peak demand of 114,000 kilowatts occurred 
February 1, 1975. There was 27,799,560 
acre-feet of water released through the turbines. 
Continued operation and maintenance. 
Condition at end of fiscal year. Construction 
began in December 1964 and is complete. Lock 
and dam was placed in operation in November 
1969. Power units were placed on line as 
follows: Unit 1, November 1972; unit 2, August 
1973; unit 3, October 1973; unit 4, December 
1973, and unit 5, May 1974. Work remaining consists 
principally of modifications to powerplant. 
18-10

LITTLE ROCK, ARK., DISTRICT 
33. TABLE ROCK LAKE, MO. 
Location. See Table 18-J, White River Basin. 
Existing project. Estimated cost is $70,386,000, 
of which $4,946,000 is Code 711 funds. For 
further information see page 893 of 1962 Annual 
Report. For authorization see Table 18-B, 
Authorizing Legislation. 
Local cooperation. Section 2, Flood Control Act 
of 1938 applies. 
Operations and results during fiscal year. 
Operation and maintenance continued. Additional 
recreation facilities were constructed. 
Results of operation of Table Rock Lake are 
shown in Section 23 and flood modifications are 
shown in Table 18-K, White River Flood 
Modifications. 
Condition at end of fiscal year. Project is complete 
except for additional recreation facilities. 
Construction of project began in October 1952, 
was ready for beneficial use for flood control in 
November 1958, and for generation of electrical 
energy with units 1 and 2 in May 1959. Units 3 
and 4 were added in April and June 1961. 
General Investigations 
34. SURVEYS 
Fiscal year cost was $387,824, of which $122,- 
247 was for navigation studies, $210,315 was for 
flood control studies, $38,081 was for special 
studies, and $17,181 was for comprehensive basin 
studies. 
35. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain information studies were completed 
for White River and Village Creek at Newport, 
Ark.; for Village Creek and tributaries at 
Walnut Ridge, Hoxie, Ark.; and for tributaries to 
Faulkner Lake, North Little Rock, Ark. Flood 
plain information studies were initiated for Hicks 
Creek and tributaries, Mountain Home, Ark.; for 
Warm Form Spring River at Thayer, Mo.; for 
Arkansas River and Gar Creek at Ozark, Ark.; 
and for Little Red River and tributaries at Searcy, 
Ark. Technical services and guidance were 
furnished to other Federal and local agencies. 
Fiscal year cost was $242,008. See Table 18-M, 
Flood Plain Studies Completed During Fiscal 
Year. 
36. RESEARCH AND DEVELOPMENT 
During the fiscal year, 128 stream gaging 
stations were operated, of which 58 were operated 
"cooperatively by Geological Survey and Corps, 
and the remaining 70 by Corps. Suspended sediment 
samples were collected at 39 stations during 
fiscal year in cooperation with Geological Survey, 
and suspended loads were determined at certain 
stations. One hundred and twelve rainfall and/or 
river reporting stations were operated in a 
cooperative program by National Weather Service 
and Corps for use in forecasting streamflow 
for flood warning and operation of lake projects. 
Records also were collected at certain 
hydroclimatic rainfall stations under a 
cooperative program of the two agencies. General 
hydrologic studies relating to streamflow frequency 
and distribution were continued. Aeration 
test at Table Rock was conducted for improvement 
of water quality in downstream Lake 
Taneycomo. Bull Shoals Lake and Tailwater 
Study, when completed, will provide a reliable estimate 
of (1) fisherman use in terms of man-hours 
and man-days; (2) fisherman harvest, by species, 
in terms of numbers, lengths, and weights; and 
(3) a comparison of fisherman use estimates on 
Bull Shoals Lake by two methods. Results will be 
of value to Corps of Engineers and other agencies 
involved in wildlife study. Cost for fiscal year was 
$2,237, of which $169 was for engineering studies 
and $2,068 was for hydrologic studies. 
18-11

TABLE 18-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Arkansas River New Work 
Basin, Ark., Approp. 
Okla., & Kans. Dams 
Navigation 
Cost 
Dams 
Navigation 
Maint. 
Approp. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Special Funds 
Cost 
Other 
Contrib. 
Cost 
2. Bank Stabili- New Work 
zation & Channel Approp. 
Rectification. Ark. Cost 
Maint. 
Approp. 
Cost 
3-13. Navigation New Work 
Locks & Dams, Approp. 
Ark. Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Other 
Contrib. 
Cost 
15. Bell Foley New Work 
Lake, Ark. Approp. 
Cost 
16. Blue Mountain New Work 
Lake, Ark. Approp. 
Cost 
Maint. 
Approp. 
Cost 
17. Clearwater New Work 
Lake, Mo. Approp. 
Cost 
Maint. 
Approp. 
Cost 
18. Little Rock, New Work 
Levee, Ark. Approp. 
(East End-Fourche Cost 
Bayou) 
19. Millican Lake New Work 
Tex. Approp. 
Cost 
$31,644,453 $26,873,447 $15,674,952 $9,917,000 $1,405,587,252 
101,359 99,000 -2,639 190,000 146,842,947 
31,543,094 26,774,447 15,677,591 9,727,000 1,258,744,305 
34,229,444 18,729,522 16,869,699 17,323,061 1,402,318,151 
118,349 144,613 69,859 50,081 146,712,887 
34,111,095 18,584,909 16,799,840 17,272,980 1,255,605,264 
21,661,190 24,907,570 26,642,287 24,667,751 171,433,549 
3,083,227 3,299,150 4,351,735 4,086,614 44,446,850 
18,577,963 21,608,420 22,290,552 20,581,137 126,986,699 
20,180,683 21,433,886 30,452,887 26,295,212 170,070,680 
3,011,743 3,106,791 4,503,400 4,142,471 44,192,225 
17,168,940 18,327,095 25,949,487 22,152,741 125,878,455 
-- - - 291,106 
- - - - 291,106 
- - - - 1,609,842 
- 9,818 - - 1,609,842 
-- - - 19,926,755 
- - - - 19,926,755 
- - - - 531,336 
- - - - 531,336 
- 2,350,000 1,155,000 610,000 116,521,184 
756,175 529,372 1,727,792 1,700,509 116,126,575 
- - - - 4,561,666 
- - - - 4,561,666 
12,019,600 9,134,000 9,174,000 4,380,000 375,701,1721 
11,658,723 5,701,368 7,277,193 10,426,987 374,872,847 
7,930,800 9,011,900 9,749,716 8,439,100 51,025,206 
7,317,492 7,958,940 10,865,376 9,621,516 50,928,395 
- - - - 973,385 
106,236 9,818 - - 963,567 
- - - - 531,336 
- - - - 531,336 
268,100 190,000 310,000 424,000 1,420,4092 
161,566 228,994 392,326 410,615 1,403,861 
14,730 - - 27,000 5,067,774 
42,592 17,894 - 2,797 5,043,571 
238,200 249,800 461,000 363,600 3,595,894 
230,676 238,807 416,884 419,113 3,581,787 
51,700 35,000 50 21,810 10,078,0033 
12,674 53,383 25,928 5,752 10,056,683 
468,100 501,400 683,800 522,500 4,763,555 
423,587 459,629 663,757 628,556 4,740,035 
262,899 114,400 - 50,000 1,370,1764 
22,160 13,424 219,897 138,190 1,823,693 
149,000 450,000 350,000 350,000 
77,980 362,165 454,767 392,414 
1,439,000 
1,427,291 
18-12

LITTLE ROCK, ARK., DISTRICT 
TABLE 18-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
20. Nimrod Lake, 
Ark. 
21. Pine Mountain 
Lake, Ark. 
22. Village Creek, 
Jackson & Lawrence 
Counties, Ark. 
23. White River 
Basin (Little 
Rock District) 
27. Beaver Lake, 
Ark. 
28. Bull Shoals 
Lake, Ark. 
29. Dardanelle Lock 
& Dam (No. 10), 
Ark. 
30. Greers Ferry 
Lake, Ark. 
31. Norfork Lake, 
Ark. 
32. Ozark Lock & 
Dam (No. 12), 
Ark. 
33. Table Rock 
Lake, Mo. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
17,860 - -50 98,000 
1,206 16,680 - 47,269 
259,400 325,300 670,400 436,500 
261,183 262,640 650,289 513,852 
94,555 -56,000 1,000 25,000 
30,668 5,587 7,727 25,009 
- - 175,000 85,000 
- - 155,354 103,875 
1,200,610 1,406,000 452,050 1,008,999 
1,019,360 1,241,533 1,502,301 639,866 
8,169,700 8,621,300 10,049,100 8,557,600 
7,349,431 8,259,107 10,940,230 9,073,970 
168,800 - 1,100 73,872 
122,614 46,084 116,404 19,308 
1,135,700 1,309,300 1,409,500 1,165,900 
1,128,931 1,152,934 1,413,117 1,356,776 
136,900 304,945 -8,000 1,848,600 
475,146 228,242 202,474 1,956,880 
1,732,800 1,821,100 2,026,100 1,848,600 
1,471,426 1,902,521 2,145,890 1,956,880 
180,800 -5,000 8,000 335,000 
692,054 429,300 25,737 9,724 
1,815,600 2,196,200 1,851,700 1,570,000 
1,781,360 1,733,497 2,302,210 1,634,786 
151,900 440,000 1,000 122,300 
115,164 242,736 296,481 97,697 
1,364,300 1,441,400 1,879,700 1,375,200 
1,306,794 1,282,090 2,073,283 1,461,405 
183,700 251,000 -12,100 65,645 
24,889 163,727 223,066 31,045 
1,293,600 1,374,400 1,463,700 1,292,600 
1,057,766 1,340,580 1,680,359 1,408,763 
8,838,800 4,400,000 2,480,000 2,630,000 
9,100,438 3,873,262 2,818,122 2,388,952 
780,300 1,031,700 1,296,300 1,276,400 
611,234 1,014,477 1,449,076 1,348,207 
239,510 200,000 160,000 55,122 
107,307 278,367 245,622 59,166 
2,175,200 2,173,700 2,586,300 2,352,800 
1,960,927 2,121,353 2,963,824 2,261,590 
1. Includes $77,762 prior to 1952 and $1,552,416 for 5. Includes $491,928 Public Works acceleration funds. 
general studies. 6. Includes $259,812 Public Works acceleration funds. 
2. Includes $68,309 prior to 1952. 7. Includes $402,162 for general studies. 
3. Includes $47,103 Public Works acceleration funds. 8. Includes $168,012 for general studies. 
4. Includes $883,277 for work completed in 1950. 9. Includes $185,513 Public Works acceleration funds. 
18-13 
4,042,427 
3,991,554 
4,217,878 
4,195,324 
579,555 
579,544 
260,000 
259,229 
5 
291,220,0605 
290,594,844 
74,036,202 
73,661,568 
45,819,177 
45,695,893 
9,058,559 
9,029,899 
6 
90,348,6296 
90,435,398 
17,466,673 
17,449,779 
82,876,3277 
82,230,312 
12,504,432 
12,384,326 
48,315,012 
48,199,197 
11,251,518 
11,222,413 
29,550,628 
29,500,049 
14,608,791 
14,586,142 
84,700,3128 
84,105,864 
5,591,761 
5,584,355 
66,745,8889 
66,699,696 
16,887,106 
16,633,300

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 18-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 28, 1938 
August 18, 1941 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
July 14, 1960 
ARKANSAS RIVER BASIN, ARK., OKLA., & KANS. 
(See Section 1 of Text) 
Approved General comprehensive plan: 
Mannford Reservoir, Okla. 
Oologah Lake, Okla. 
Canton Lake, Okla. 
Tenkiller Ferry Lake, Okla. 
Wister Lake, Okla. 
Blue Mountain Lake, Ark. 
Nimrod Lake, Ark. 
Modified comprehensive plan to include reservoirs in 
Grand (Neosho) River Basin, Okla., and Mo., and in 
Verdigris River Basin: 
Markham Ferry Reservoir, Okla. 
Fort Gibson Lake, Okla. 
Pensacola Reservoir Lake O'The Cherokees, Okla. 
Fall River Lake, Kans. 
Elk City Lake, Kans. 
Toronto Lake, Kans. 
Neodosha Lake, Kans. 
Authorized Chief of Engineers to provide in the Canton 
Lake 69,000 acre-feet of irrigation storage, subject to 
certain conditions. 
Approved multiple-purpose plan: 
Oologah Lake, Okla. 
Markham Ferry Reservoir, Okla. 
Fort Gibson Lake, Okla. 
Blackburn Reservoir, Okla. 
Mannford Reservoir, Okla. 
Taft Reservoir, Okla. 
Bank stabilization 
Dardanelle Lock and Dam, Ark. 
Eufaula Lake, Okla. 
Navigation locks and dams 
Ozark Lock and Dam, Ark. 
Short Mountain Lock and Dam, Okla. 
Webbers Falls Lock and Dam, Okla. 
Tenkiller Ferry Lake, Okla. 
Modified Arkansas River navigation comprehensive plan to 
include bank protection works at Bradens Bend, Okla. 
Modified comprehensive plan authorized in 1938 Flood 
Control Act and multiple-purpose plan authorized in 
River and Harbor Act of 1946 to provide for substituting 
Keystone Lake for Mannford, Blackburn, and Taft 
Reservoirs. 
Authorized incorporation of River and Harbor and Flood 
Control plans into a single plan of development and made 
all previous authorizations applicable to combined 
plan of development. 
June 22, 1936 
December 22, 1944 
October 27, 1965 
October 23, 1962 
June 28, 1938 
LITTLE ROCK LEVEE, ARK. (EAST END-FOURCHE 
BAYOU) (See Section 18 of Text) 
Levees to provide flood protection to people and city H. Doc. 308, 74th Cong., 
property. 1st sess. 
Modified local flood protection project to raise grade H. Doc. 447, 78th Cong., 
and protect additional areas. 2d sess. 
Authorized 45,000 g.p.m. pump station and excavated S. Doc. 55, 89th Cong., 
storage area. 1st sess. 
VILLAGE CREEK, JACKSON AND LAWRENCE COUNTIES, 
ARK. (See Section 22 of Text) 
Authorized clearing and straightening of channel. H. Doc. 352, 87th Cong., 
2d sess. 
WHITE RIVER BASIN (LITTLE ROCK DISTRICT) 
(See Section 23 of Text) 
Approved comprehensive plan for White River Basin: Flood Control Com. 
Lone Rock Lake, Ark., Norfork Lake, Ark., Doc. 1, 75th Cong., 
Clearwater Lake, Mo., Water Valley Lake, Ark., 1st sess. 
Bell Foley Lake, Ark., Greers Ferry Lake, Ark., 
and White River emergency. 
18-14 
Flood Control Com. 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 107 and 440, 
76th Cong., 1st sess. 
H. Doc. 758, 79th Cong., 
2d sess. 
S. Doc. 107, 81st Cong., 
1st sess.

TABLE 18-B (Continued) 
LITTLE ROCK, ARK., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
August 18, 1941 Modified comprehensive plan to include Bull Shoals H. Doc. 917, 76th Cong., 
Lake, Ark., and Mo., Table Rock Lake, Mo., and 3d sess. 
Ark., and Norfork Lake, Ark., and Mo. (power) H. Doc. 290, 77th Cong., 
1st sess. 
September 3, 1954 Authorized power in Greers Ferry Reservoir and added H. Doc. 499, 83d Cong., 
Beaver Lake to the plan. 2d sess. 
March 7, 1974 Authorized highway bridge construction across Flood Control Com. 
Norfork Lake. Doc. 1, 75th Cong., 
1st sess. 
BRAZOS RIVER BASIN (FORT WORTH DISTRICT) 
(See Section 19 of Text) 
August 13, 1968 Authorized a project for the Navasota River, Tex. H. Doc. 341, 90th Cong., 
2d sess. 
18-15

TABLE 18-C 
Feature 
LITTLE ROCK 
DISTRICT 
Norrell L&D No. 1 
Lock No. 2 
Dam No. 2 
L&D No. 3 
L&D No. 4 
L&D No. 5 
David D. Terry L&D No. 6 
Murray L&D No. 7 
Toad Suck Ferry 
L&D No. 8 
L&D No. 9 
Dardanelle L&D No. 10 
L&D No. 11 
Ozark L&D No. 12 
ARKANSAS RIVER BASIN; ARK., OKLA., AND KANS.: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Char- Year 
Up- Upper Depth on Miter acter Opened 
stream Lock Pool Sill of Kind to Total 
from Miles to Dimension Lift (feet, Upper Lower Founda- of Type of Navi- Estimated 
Mouth' Nearest Town (feet) (feet) MSL) (feet) (feet) tion Dam Construction gation Cost 
10.3 
13.3 
40.5 
50.2 
66.0 
86.3 
108.1 
125.4 
155.9 
176.9 
205.5 
8 east of Arkansas 
Post, Ark. 
6 east of Arkansas 
Post, Ark. 
3 southeast Arkansas 
Post, Ark. 
5 north of Grady, Ark. 
7 east of Pine Bluff, 
Ark. 
4 southeast of 
Redfield, Ark. 
12 southeast of Little 
Rock, Ark. 
6 northwest of Little 
Rock, Ark. 
6 west of Conway, Ark. 
3 southwest of 
Morrilton, Ark. 
2 west of Dardanelle, 
Ark. 
- Deleted 
258.0 1 east of Ozark, Ark. 
110 by 600 30 max. 
110 by 600 20 nom. 
28 max. 
110 by 600 20 
110 by 600 14 
110 by 600 17 
110 by 600 18 
110 by 600 18 
110 by 600 16 
110 by 600 19 
110 by 600 54 
110 by 600 34 
142 
162 
182 
196 
213 
231 
249 
265 
284 
338 
16 
18 
18 
18 
18 
18 
18 
18 
18 
17 
15 
14 
14 
14 
14 
14 
14 
14 
14 
14 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Piles in 
sand 
Clay 
Piles in 
sand 
Shale 
Shale 
Shale 
Sandstone 
Fixed Concrete 
overflow 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
372 18 17 Sandstone Movable Gated concrete 
and shale spillway with 
embankment 
ends 
1967 
1967 
1968 
1968 
1968 
1968 
1968 
1969 
1969 
1969 
1969 
1969 
$32,270,0002 
40,460,000 
33,700,000 
40,480,000 
29,360,000 
60,370,000 
32,720,000 
49,270,000 
32,760,000 
84,008,0003 
84,700,000 
C
0C
z
z
n
c3
d 
co

TABLE 18-C (Continued) 
Feature 
L&D No. 13 
TULSA DISTRICT4 
L&D No. 13 (part) 
W. D. Mayo L&D No. 14 
Robert S. Kerr 
L&D No. 15 
Webbers Falls 
L&D No. 16 
Chouteau L&D No. 17 
Newt Graham 
L&D No. 18 
Miles 
Upstream 
from 
Mouth1 
292.8 
319.6 
336.2 
368.9 
403.7 
423.9 
Ne 
7 east c 
Ark. 
ARKANSAS RIVER BASIN; ARK., OKLA., AND KANSAS.: NAVIGATION 
(See Section 1 of Text) 
Elevation Char- 
Upper Depth on Miter acter 
Lock ool Sill of Kind 
Miles to Dimension Lift (feet, Upper Lower Founda- of Type of 
Barest Town (feet) (feet) MSL) (feet) (feet) tion Dam Construction 
)f Fort Smith, 110 by 600 20 392 18 14 Sandstone Movable Gated concrete 
and shale spillway with 
4 east of Redland, 
Okla. 
1 north of Cowlington, 
Okla. 
1 northwest of Gore, 
Okla. 
4 northwest of Okay, 
Okla. 
8 southwest of Inola, 
Okla. 
110 by 600 20 
110 by 600 48 
110 by 600 30 
110 by 600 21 
110 by 600 21 
412 
460 
490 
511 
532 
18 
18 
18 
18 
18 
14 
14 
14 
14 
14 
Rock 
Rock 
Rock 
Rock 
RRoocckk 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Year 
Open 
to 
Navigation 
1969 
1970 
1970 
1970 
1970 
1970 
1970 
Total 
Estimated 
Cost 
$43,712,000 
6,858,000 
32,700,000 
93,327,000 
83,635,000 
31,550,000 
44,150,000 
r
y
y
rd 
03 
n
yJ

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
ARKANSAS RIVER BASIN; ARK., OKLA., AND KANS.: NAVIGATION 
TABLE 18-C (Continued) (See Section 1 of Text) 
Additional features entering into cost of project 
Litl.- .frk i)istr.t: Upstream Lakes: 
Ban , ac'rlizatio:, and cha:." +.':".""iion, mile 33.7 to 362and 
Arkanas Wh:te utof.: ., .. 3c7 tt,6'.2.. ..t..e... .... $119,300,000 Oologah, 90.2 miles upstream from mouti, Verdigris River 
M4 npienraennete c amrpidle rte pa.i.rr.. ..f. ...e..t. .a...n..i. ...."..:... C.,et eerrmmiinna ls, complete .................... ............................. $ 46,683,000 7.8,000 Ieystone, 630.8 miles upstream from mouth, Arkansas Rigver. 
Total. Little P.. ."k...r.....i. .. ................ .... 691,000,00 : com plete................................... ... . ......... 4.000 
Nijt' l(aog fal t ('oast Guard)..................... .. 2268,000 Ecuofmaupllae,t e2 .7.. ..m.. iles upstr.e..a..m.... ..f.r..o.m.... ..m...o..u..t.h..,. ..C...a..n adian River, 122.223.000 
Subtota.l. ............................. ........ 292.746,000 
'sa Dilst,rict. Total, Tulsa District ....................... 600.416,0006 
-hank stabilizatainodn channel rectification, Short Mountain 
tc. Fort Smith, complete .................................. 12,700,000 Total Project Cost 99.7 percent complete.............. $1 293.684 00( 
Maintenance and repair fleet and marine terminals, 
can.l t.e.. ...... ........ .... ......... ............... . 2,750,000 
Subtotal ............. ........................ .... $307,670,000^ 
1. Navigation mileage from mouth of White River except 5. Includes $10,065,000 for additional water supply 
Dam No. 2 is 40.5 miles above mouth of Arkansas River. facilities. 
2. Includes cost of entrance channel. 6. Includes $2,187,000 Code 711 funds. 
3. Includes $1,708,000 Code 711 funds. 
4. Detail report of individual features in Tulsa District 
Report. 
TABLE 18-D
ARKANSAS RIVER BASIN, ARK., OKLA., AND KANS.: LAKES 
(See Section 1 of Text) 
Miles Drainage Height Reservoir Power Year o, Total Above Area of am Capacity Development Percent Estimated 
Lake and State River Mouth Nearest Town (sq mi) (feet) Type (acre-feet) (kilowatts) Complete Cost 
Blue Mountain, Ark. Petit Jean 74.4 Paris,. Ark. 488 115 Earthfill 258,000 -. 1947 $ 5,322,000 
Canton, Okla. North Canadiarn 394.0 Canton. Okla. 12,483 73 Earthfill 386,000 - 1948 11.174,000 
Elk City, Kans. Elk 9.0 Independence. Kans. 634 107 Earthfill 291,000 - 1966 19,042,990 (Table Mound) 
L].f,UPla. Okla.' " Canadian 27.0 Eufaula, Okla. 47,522 114 Earthfill 3,798.000 90,000 1965 122,223,000 
r' Rtver, Kans. Fall 54.0 Fall River, Kans. 585 94 Earthfil 259,000 - 1949 10.494,413 
Fc 'il,bsnOnk,la .' Grand (Neosho) 8.0 Fort Gibson, Okla. 12,492 110 Concrete avity 1,284,400 45,000 1953 55.212.000 
Kevcsneu .Okla.
2
' Arkansas 539.0 Sand Springs, Okla. 74.506 121 Earthfill 1,836,500 70,000 1964 123.840,000 
Markham Ferry. Okla.' Grand (Neosho) 47.0 Pryor, Okla. 11,533 90 Earthfill 444,500 120,000 1964 6,908,756 
Neodesha, Kans.' Verdigris 223.0 Neodesha, Kans. 1,152 74 Earthfill 90,000 -- 0 18,100,000 
Nimrod, Ark. Fourche La Fave 62.6 Danville.. rk. 680 97 Concrete gravity 336,000 - 1942 4,330,000 
Oologah, Okla.' Verdigris 90.2 Claremore. Okla. 4,339 137 Earthfill 1,519,000 - 1974 46,683,000 
I err.tacola, Ois. C ;rand (Neosho) 77.0 Disney, Okla. 10,298 147 Concrete arch 2,197,000 86,400 1941 2,090,000 
Tenkiller Ferry. Okia liboi.s 13.0 Gore, Okla. 1,610 197 Earthfill 1,280,800 34.000 1953 23,932,000 
Toronto. Kans. Verdigr;s 271.5 Toronto, Kans. 730 90 Earthfill 195,300 19-6 0 13,894.002 
Wister. Okla. 'oteau 61.0 Wister, Okla. 993 99 Earthfill 427,900 - 1949 10,501,226 Sr";ttal, exclusivofe Eufaula, Keystone. ,nd Oologah, 87 percent complete 181,001,387 
i Arkansas River Basin, 95 percent complete 1.474.685.38" 
1. Project includes facilities for production of hydroelectric 
power. 
2. Cost included in navigation project. 
3. Added as substitution for Mannford and by deletion of 
Taft and Blackburn Reservoirs (Cherokees). Estimate shown 
is for Federal participation. 
4. Constructed by State of Oklahoma under the name of 
Robert S. Kerr Dam (Lake Hudson). Estimate shown is for 
Federal participation. 
5. Inactive. Estimate is based on 1954 price levels. 
6. Constructed by State of Oklahoma under the name 
Grand River Dam (Lake O' The Cherokees). Estimate shown 
is for Federal participation. 
18-18

LITTLE ROCK, ARK., DISTRICT 
TABLE 18-E BANK STABILIZATION AND CHANNEL RECTIFICATION: 
REACH AND LOCATION 
(See Section 2 of Text) 
Reach Location of Reach 
Fort Smith to Mill Creek Mountain 
Mill Creek Mountain to Morrisons Bluff 
Dardanelle Rock to Morrilton Bridge 
Morrilton Bridge to Fourche La Fave 
Fourche La Fave to Little Rock 
Little Rock to Jefferson County Free Bridge 
Jefferson County Free Bridge to Rob Roy Bridge 
Rob Roy Bridge to Arkansas Post 
Arkansas Post to Mile 33.7 
Arkansas-White Cutoff 
Miles 362.0 to 327.0 
Miles 327.0 to 285.0 
Miles 257.0 to 221.0 
Miles 221.0 to 192.0 
Miles 192.0 to 165.5 
Miles 165.5 to 115.6 
Miles 101.7 to 89.01 
Miles 89.0 to 42.01 
Miles 42.0 to 33.71 
Miles 5.0 to 02 
1. River mileage from 1943 survey. 
2. Arkansas-White Cutoff mileage from 1949 survey. 
TABLE 18-F BANK STABILIATION AND CHANNEL RECTIFICATION: FY 75 
OPERATIONS 
(See Section 2 of Text) 
New Work (Contract) 
Completed Initiated or Con. 
Pilot 
Revet- Revet- Channel Removal Cost 
Reach ments Dikes ments Dikes Excavation of Dikes of 
(river miles) (lin. ft) (lin. ft) (lin. ft) (lin. ft) (cu.yd.) (lin. ft) Work 
362.0 to 327.0 6,119 860 - - - - $276,800 
327.0 to 285.0 8,925 - - - - - 133,400 
257.0 to 221.0 - - 195 5,759 555,000 - 94,000 
221.0 to 192.0 - 350 290 462 - - 200,900 
192.0 to 165.5 - 287 - - - - 20,000 
165.5 to 115.6 - - 1,637 1,594 - - 525,600 
101.7 to 89.0' - - - - - - 
89.0 to 42.01 - - - - 
42.0 to 33.71 - - - - - - - 
-5 to 0
2 
- - - - - - - 
Lands and 
damages - - - - - - 3,400 
1. River mileage from 1943 survey. 
2. Arkansas-White Cutoff mileage from 1949 surveycontract 
work was completed for capping out the Arkansas- 
White River Cutoff closure structure in FY 65. 
18-19 
__

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 18-G BANK STABILIZATION AND CHANNEL RECTIFICATION: 
CONDITION -'JUNE 30, 1975 
(See Section 2 of Text) 
Completed Work Work Underway 
Pilot Pilot 
Channel Revet- Channel Revet- 
Reach Excavation Dike ments Excavation Dike ments Date Percent 
(river miles) (cu. yd.) (lin. ft) (lin. ft) (cu. yd.) (lin. ft) (lin. ft) Begun Complete 
362.0 to 327.0 4,013,769 103,255 171,350 - - - Jan 54 99 
327.0 to 285.0 799,065 59,017 110,153 - - 8,925 Sep 54 72 
257.0 to 221.0 11,977,782 93,307 151,585 555,000 5,759 195 May 50 98 
221.0 to 192.0 2,087,889 95,761 130,429 - 462 290 Mar 50 94 
192.0 to 165.5 450,000 84,101 111,058 - - - Mar 60 98 
165.5 to 115.6 9,860,931 144,741 253,631 - 1,594 1,637 Jun 50 97 
101.7 to 01 19,340,832 239,510 385,588 - - 5,000 1950 98 
Land and 
damages - - - - - - - 95 
1. River mileage from 1943 survey. Includes Arkansas- 
White River closure structure. 
TABLE 18-H OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Black River, Ark., and Mo.' 1950 $ 80,000 $ 915,954 
Current River, Ark., and Mo.' 1964 17,0002 132,178 
Upper White River, Ark.3,4 1952 813,197 1,788,374 
White River, Ark., (above Peach 
Orchard Bluff)"', 1950 - 785,666 
1. Channel adequate for existing commerce. Completion 
not contemplated. 
2. Includes $7,000 for previous project. 
3. Federal operation and maintenance terminated June 
30, 1952, due to lack of commerce. Facilities at Locks and 
Dams Nos. 1, 2, and 3 disposed of in accordance with authority 
in Public Law 996, 84th Cong. 
4. Completed. 
5. Responsibility for maintenance of project downstream 
from Newport, Ark., transferred to Memphis District in FY 
62. 
18-20

FLOOD MODIFICATIONS 
Outflow Estimated 
Coincident Experi- Appre- Crest Estimated 
Date With Peak Maximum Corre- enced ciable Stage Reduc- 
See of Peak Downstream Pool sponding Crest Overflow Without tion in 
Section Peak Inflow Flow Elevation Storage Nearby Stage Begins Dam Stage 
in Text Project Flow (c.f.s) (c.f.s.) (feet, MSL) (acre-feet) Town (feet) (feet) (feet) (feet) 
16 Blue Mountain Lake, Ark. 
11 Nov 12,000 
24 Nov 8,000 
1 Feb 11,400 
23 Feb 5,100 
29 Mar 22,000 
8 May 15,000 
17 Clearwater Lake, Mo. 
23 Feb 21,000 
13 Mar 5,000 
29 Mar 17,200 
26 Apr 13,800 
20 Nimrod Lake, Ark. 
5 Nov 4,500 
11 Nov 17,000 
24 Nov 18,000 
1 Feb 14,000 
19 Mar 11,000 
28 Mar 32,000 
30 Greers Ferry Lake, Ark. 
24 Nov 30,000 
23 Feb 32,000 
18 Mar 50,000 
28 Mar 200,000 
30 
35 
25 
25 
25 
25 
150 
2,450 
180 
160 
300 
150 
300 
20 
20 
20 
20 
850 
1,870 
2,080 
397.79 
401.41 
398.59 
390.48 
404.06 
400.69 
517.30 
502.00 
521.80 
513.00 
348.00 
355.80 
362.00 
355.68 
352.45 
365.05 
460.68 
462.76 
465.24 
474.70 
80,721 Danville, Ark. 19.9 
102,700 do 21.9 
85,310 do 18.7 
46,700 do 19.4 
121,050 do 24.3 
98,070 do 17.7 
81,270 Poplar Bluff, Mo. 13.7 
37,000 do 12.6 
98,810 do 18.7 
66,440 do 13.8 
56,550 Aplin, Ark. 
112,000 do 
173,510 do 
110,960 do 
85,350 do 
210,450 do 
8.6 
12.2 
19.2 
21.3 
12.2 
30.1 
1,900,400 Judsonia, Ark. 24.25 
1,966,300 do 21.18 
2,046,300 do 29.14 
2,373,400 do 35.90 
18.0 
18.0 
18.0 
18.0 
18.0 
18.0 
12.0 
12.0 
12.0 
12.0 
17.0 
17.0 
17.0 
17.0 
17.0 
17.0 
30.0 
30.0 
30.0 
30.0 
24.3 
24.2 
24.2 
22.1 
28.8 
24.2 
19.6 
13.6 
20.6 
18.3 
13.5 
28.5 
30.7 
31.6 
21.4 
34.5 
31.7 
30.8 
36.0 
43.8 
4.4 
5.5 
5.5 
2.7 
4.5 
6.5 
5.9 
1.0 
1.9 
4.5 
r: 
r
0 
4.9 
16.3 
11.5 
10.3 
9.2 
4.4 
7.5 
9.6 
6.9 
7.9 
TABLE 18-I

TABLE 18-J WHITE RIVER BASIN 
(See Section 23 of Text) 
Miles Drainage Reservoir Power Total 
Above Area Height of Dam Above Streambed Capacity Development Estimated 
Lake River Mouth Nearest Town (sq mi) and Type (acre-feet) (kilowatts) Cost' 
Beaver2 White 609.0 Eureka Springs, Ark. 1,186 228 feet concrete-gravity and earthfill 1,952,000 112,000 $ 49,403,000 
Bell Foley2 Strawberry 27.2 Poughkeepsie, Ark. 519 136 feet concrete-gravity and earthfill 518,000 (3) 56,800,000 
Bull Shoals2 White 418.6 Cotter, Ark. 6,036 258 feet concrete-gravity 5,408,000 340,000 93,400,000 
Clearwater 2 Black 257.4 Piedmont, Mo. 898 154 feet earthfill 413,000 (3) 10,527,000 
Greers Ferry2 Little Red 79.0 Heber Springs, Ark. 1,146 243 feet concrete-gravity 2,844,000 96,000 51,174,000 
Lone Rock5 Buffalo 3.6 Norfork, Ark. 1,331 216 feet concrete-gravity 687,000 (3) 29,460,000 
Norfork 2 North Fork 4.8 Norfork, Ark. 1,806 222 feet concrete-gravity 1,983,000 70,000 74,590,000 
Table Rock2 White 528.8 Branson, Mo. 4,020 252 feet concrete-gravity and earthfill 3,462,000 200,000 70,386,000 
Water Valley6 Eleven Point 12.6 Pocahontas, Ark. 1,152 157 feet earthfill 1,563,000 (4) 18,300,000 
Total 818,000 454,040,000 
1. July 1970 price levels unless otherwise noted. 5. To be restudied. Estimated cost based on July 1954 
2. For details of this project, see individual report. price levels. 
3. None. 6. To be restudied. Estimated cost based on November 
4. Includes provisions for future power installation. 1965 price levels. 
BRAZOS RIVER BASIN, TEXAS 
Millican Navasota 24.1 Navasota, Tex. 2,120 83 feet concrete-gravity and earthfill -(3) 160,000,000 
O
0O
zO
r
Tj 
z
Cl)

LITTLE ROCK, ARK., DISTRICT 
TABLE 18-K WHITE RIVER FLOOD MODIFICATIONS 
(See Section 23 of Text) 
Outflow Coincident Storage Available 
Project and With Peak Down- Maximum Pool Corresponding in Power Pool 
Date of Peak Inflow stream Flow Elevation Storage at Start of Flood 
Peak Inflow (c.f.s.) (c.f.s.) (feet, MSL) (acre-feet) (acre-feet) 
Beaver 
4 Nov 60,000 3,960 1126.28 1,836,100 35,100 
22 Feb 37,000 3,260 1122.46 1,722,600 11,700 
18 Mar 21,000 2,870 1123.36 1,748,800 0 
28 Mar 29,000 5,060 1124.90 1,794,500 0 
Table Rock 
4 Nov 100,000 6,400 924.03 3,112,500 0 
22 Feb 52,000 1,230 918.70 2,864,500 28,000 
18 Mar 39,000 10,400 918.62 2,860,900 0 
28 Mar 43,000 11,070 919.36 2,894,200 0 
Bull Shoals 
4 Nov 105,000 7,020 658.41 3,252,700 201,600 
10 Nov 70,000 3,690 664.49 3,553,000 0 
10 Jan 33,500 10,130 658.96 3,279,100 0 
22 Feb 34,000 1,250 656.85 3,179,000 22,900 
18 Mar 50,000 7,030 663.60 3,508,000 0 
28 Mar 43,000 6,490 667.67 3,717,700 0 
Norfork 
4 Nov 22,500 1,850 554.00 1,295,700 0 
10 Nov 22,000 2,470 555.58 1,331,600 0 
10 Jan 43,000 1,810 557.09 1,336,500 0 
22 Feb 20,200 1,280 554.31 1,302,700 0 
18 Mar 24,000 1,370 556.72 1,357,900 0 
28 Mar 29,000 2,710 554.89 1,433,200 0 
Calico Rock, Ark.' Newport 2 
Estimated Crest Estimated Crest 
Stage Without Estimated Stage Without Estimated 
Date Peak Experienced Norfork, Beaver, Reduction Experienced Norfork, Beaver, Reduction 
Inflow at Crest Stage Table Rock, and in Stage Crest Stage Table Rock, and in Stage 
Bull Shoals (feet) Bull Shoals (feet) (feet) (feet) Bull Shoals (feet) (feet) 
4 Nov 11.1 38.2 27.1 15.8 29.4 13.6 
10 Jan 13.9 25.0 11.1 21.2 25.6 4.4 
22 Feb 12.9 27.8 14.9 21.8 28.1 6.3 
18 Mar 15.2 25.6 10.4 25.7 29.0 3.3 
28 Mar 18.5 30.0 11.5 31.5 32.3 .8 
1. Appreciable overflow begins at 19 feet. 
2. Appreciable overflow beings at 18 feet. 
18-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 18-L OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Black River, Poplar Bluff, Mo., to 
Knobel, Ark.' 1958 $ 584,315 
Carden's Bottom Drainage District No. 2, 
Arkansas River, Ark.' 1951 919,955 
Clarksville, Ark.' 1962 271,717 - 
Conway County Drainage and Levee District 
No. 1, Arkansas River, Ark.' 1959 187,440 
Conway County Levee Districts Nos. 1, 
2, and 8, Arkansas River, Ark.' 1952 1,018,840 
Conway County Levee District No. 6, 
Arkansas River, Ark.' 1952 390,952 
Crawford County Levee District, Arkansas 
River, Ark.' 1954 2,001,820 - 
Crooked Creek, Lake and Levee, Ark. 1969 -- 
East Poplar Bluff and Poplar Bluff, Mo.' 1958 304,699 - 
Faulkner County Levee District No. 1, 
Arkansas River, Ark.' 1941 99,511 - 
Fort Smith, Arkansas River, Ark.' 1951 1,077,546 - 
From North Little Rock to Gillett, Ark. 
(above Plum Bayou)' 1954 845,300 - 
Fourche Creek, Little Rock, Ark. 1973 22,890 - 
Holla Bend Bottom, Arkansas River, Ark. 2 1962 17,610 
Lone Rock Lake, White River, Ark. 4 
- 130,653 
McLean Bottom Levee District No. 3, 
Arkansas River, Ark.' 1950 422,549 
Near Dardanelle, Arkansas River, Ark.' 1953 198,069 - 
Newport, White River, Ark.' 1941 314,276 - 
North Little Rock, Arkansas River, Ark.' 1958 512,001 - 
Petit Jean River, Ark.'1 1966 84,350 - 
Roland Drainage District, Arkansas River, 
Ark.' 1950 269,907 
Skaggs Ferry, Black River, Ark.' 1941 81,023 - 
South Bank Arkansas River (Head Fourche 
Island to Pennington Bayou), Ark.' 1964 1,404,852 
South Bank Arkansas River, Little Rock to 
Pine Bluff, Ark., Tucker Lakes' 1961 409,115 
Van Buren, Arkansas River, Ark.' 1952 438,222 
Village Creek, White River, and Mayberry 
Levee Districts, Ark.3 1972 1,567,156 
Water Valley Lake, White River, Ark., 
and Mo.4 - 414,011 - 
West of Morrilton, Arkansas River, Ark.' 1962 1,269,959 
1. Completed. 4. Deferred for restudy. Flood Control Com. Doc. 1, 75th 
2. Deauthorized. Cong., 1st sess. 
3. See H. Doc. 577, 87th Cong., 2d sess., for description of 5. Authorized by Chief of Engineers. 
project. 
TABLE 18-M FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 35 of Text) 
Location Requesting Agency Date Completed Federal Cost 
Newport, Ark. City of Newport, Ark. Jul 74 $36,000 
Walnut Ridge-Hoxie, Ark. Cities of Walnut Ridge and 
Hoxie, Ark. Nov 74 39,700 
North Little Rock, Faulkner City of North Little Rock, 
Lake, Ark. Ark. Mar 75 37,900 
18-24

TULSA, OKLA., DISTRICT* 
This District comprises southern Kansas, small 
portions of southwestern Missouri and western 
Arkansas, northern Oklahoma, northern portion 
of Texas Panhandle, and small portions of 
northeastern New Mexico and southeastern 
Colorado, embraced in drainage basin of 
Arkansas River and tributaries above mouth of 
Poteau River, inclusive, and below mouth of 
Walnut Creek near Great Bend, Kans., exclusive 
of that portion of watershed of South Canadian 
River and its tributaries west of Texas-New 
Mexico State line; and a portion of western 
Arkansas, northern portion of Texas, and 
southern portion of Oklahoma embraced in 
drainage basin of Red River and its tributaries 
above Fulton, Ark. In addition, Tulsa District has 
responsibility for planning, design, construction, 
and operation and maintenance of that portion of 
McClellan-Kerr Arkansas River Navigation 
System in Oklahoma. 
IMPROVEMENTS 
Navigation 
1. McClellan-Kerr Arkansas River 
Navigation System, Ark. and Okla. 
2. Bank Stabilization and Channel 
Rectification, Arkansas River, 
Ark. and Okla. ................ 
3. Low Head Locks and Dams, Okla. 
3A. Lock and Dam No. 13, Channel 
Improvement, Arkansas River 
Basin, Okla. ................... 
3B. W. D. Mayo Lock and Dam, 
Arkansas River Basin, Okla. ... 
3C. Chouteau Lock and Dam, 
Verdigris River Basin, Okla. ... 
3D. Newt Graham Lock and Dam, 
Verdigris River Basin, Okla. ... 
4. Maintenance and Repair Fleet 
and Marine Terminals, Okla. .. 
5. Other Authorized Navigation 
Project .. ................... 
6. Navigation Work under Special 
Authorization ................. 
Flood Control 
7. Arcadia Lake, Deep Fork River 
Basin, Okla.................... 
8. Ark-Red Basins Chloride Control, 
Okla., Tex., and Kans. ......... 
8A. Experimental Chloride Control 
Project, Red River Basin, Tex. 
8B. Ark-Red Basins Chloride Control, 
Supplemental Studies, Okla. ... 
Page Flood Control (cont) 
8C. Ark-Red Basins Chloride Control, 
19-2 Tex.. .......................... 
8D. Ark-Red Basins Chloride Control, 
Okla., Tex., and Kans. ......... 
19-3 9. Big Hill Lake, Verdigris River 
19-4 Basin, Kans. ................ 
10. Big Pine Lake, Red River Basin, 
Tex. ......................... 
19-4 11. Birch Lake, Verdigris River Basin, 
Okla. ......................... 
19-4 12. Candy Lake, Verdigris River 
Basin, Okla. ................. 
19-4 13. Canton Lake, Arkansas River 
Basin, Okla. ................. 
19-4 14. Cedar Point Lake, Grand (Neosho) 
River Basin, Kan ............. 
19-5 15. Clayton Lake, Little River Basin, 
O kla. .......... ................. 
19-5 16. Copan Lake, Verdigris River 
Basin, Okla. ................... 
19-5 17. Council Grove Lake, Grand 
(Neosho) River Basin, Kans. .... 
18. DeQueen Lake, Little River Basin, 
A rk. ................ ......... 
19-5 19. Dierks Lake, Little River Basin, 
Ark ........................... 
19-5 20. El Dorado Lake, Walnut River 
Basin, Kans. ................. 
19-6 21. El Dorado, Kans. .............. 
22. Elk City Lake, Verdigris River 
19-6 Basin, Kans. .................. 
*All cost and financial statements (table 19-A) for projects are listed at the end of this chapter. All other tables are referenced in 
text and also appear at the end of this chapter. 
19-1 
Page 
19-6 
19-6 
19-7 
19-7 
19-8 
19-8 
19-8 
19-8 
19-9 
19-9 
19-9 
19-10 
19-10 
19-10 
19-11 
19-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (cont) 
23. Fall River Lake, Verdigris River 
Basin, Kans. .................. 
24. Flat Rock Creek, Tulsa, Okla. .. 
25. Fort Supply Lake, North Canadian 
River Basin, Okla. .......... 
26. Gillham Lake, LittlelRiver Basin, 
Ark ...................... 
27. Great Salt Plains Lake, Arkansas 
River Basin, Okla. ............. 
28. Heyburn Lake, Arkansas River 
Basin, Okla. ......... ..... 
29. Hugo Lake, Kiamichi River 
Basin, Okla ............. 
30. Hulah Lake, Verdigris River 
Basin, Okla. ................... 
31. John Redmond Dam and 
Reservoir, Grand (Neosho) River 
Basin, Kans. .................. 
32. Kaw Lake, Arkansas River 
Basin, Okla. ................... 
33. Lake Kemp, Wichita River 
Basin, Tex ..... ............ 
34. Lukfata Lake, Little River 
Basin, Okla. and Ark. ......... 
35. Marion, Kans ............... 
36. Marion Lake, Grand (Neosho) 
River Basin, Kans. ............. 
37. Millwood Lake, Little River 
Basin, Ark ................ 
38. Mud Creek, Idabel, Okla...... 
39. Oologah Lake, Verdigris River 
Basin, Okla. ............ 
40. Optima Lake, North Canadian 
River Basin, Okla. ............. 
41. Pat Mayse Lake, Red River 
Basin, Tex. .................... 
42. Pensacola Lake, Grand (Neosho) 
River Basin, Okla. ............ 
43. Pine Creek Lake, Little River 
Basin, Okla. and Ark. ......... 
44. Prosperity Lake, Spring River 
Basin, Mo . .................... 
45. Red River Below Denison Dam 
(Tulsa District) ................ 
46. Shidler Lake, Arkansas River 
Basin, Okla..................... 
47. Skiatook Lake, Verdigris River 
Basin, Okla. .................. 
Page Flood Control (cont) 
48. Spring Creek, Springdale, Ark. 
19-11 49. Toronto Lake, Verdigris River 
19-12 Basin, Kans................... 
50. Turtle Creek, Yukon, Okla. 
19-12 51. Waurika Lake, Red River Basin, 
Okla ......................... 
19-12 52. Winfield, Kans. .............. 
53. Wister Lake, Poteau River 
19-13 Basin, Okla. ................ 
54. Inspection of Completed Flood 
19-13 Control Projects ............ 
55. Scheduling Flood Control 
19-13 Reservoir Operations .......... 
56. Other Authorized Flood Control 
19-13 Projects ..................... 
57. Flood Control Work under 
Special Authorization .......... 
19-14 
19-14 Multiple-Purpose Projects 
19-14 Including Power 
58. Broken Bow Lake, Little River 
19-15 Basin, Okla. and Ark ......... 
19-15 59. Denison Dam-Lake Texoma, Red 
River Basin, Tex. and Okla. .... 
19-15 60. Eufaula Lake, Canadian River 
Basin, Okla.................... 
19-16 61. Fort Gibson Lake, Grand 
19-16 (Neosho) River Basin, Okla.... 
62. Keystone Lake, Arkansas River 
19-16 Basin, Okla. ................... 
63. Markham Ferry Reservoir, 
19-16 Grand (Neosho) River Basin, 
Okla . ........................ 
19-17 64. Robert S. Kerr Lock and Dam and 
Reservoir, Arkansas River Basin, 
19-17 Okla. ..................... 
65. Tenkiller Ferry Lake, Illinois 
19-17 River Basin, Okla .............. 
66. Webbers Falls Lock and Dam, 
19-17 Arkansas River Basin, Okla. ... 
19-18 
General Investigations 
19-18 67. Surveys ....................... 
68. Collection and Study of Basic Data 
19-18 69. Research and Development .... 
Navigation 
1. McCLELLAN-KERR ARKANSAS 
RIVER NAVIGATION SYSTEM, ARK. 
AND OKLA. 
Location. Arkansas River rises in Rocky Mountains 
near Leadville, Colo., and flows 
southeastward 1,459 miles through Colorado, 
Kansas, Oklahoma, and Arkansas to join Mississippi 
River 584.0 miles above Head of Passes, 
La. (See Geological Survey state maps, scale 
1:500,000, and flood control and navigation maps 
of Mississippi River, Cairo, Ill., to Gulf of Mexico, 
1970 edition, scale 1:62,500.) 
19-2 
Page 
19-19. 
19-19 
19-19 
19-19 
19-20 
19-20 
19-20 
19-20 
19-20 
19-20 
19-21 
19-21 
19-22 
19-22 
19-22 
19-23 
19-23 
19-23 
19-24 
19-24 
19-24 
19-24

TULSA, OKLA., DISTRICT 
Existing project. Provides for improvement of 
Arkansas River Basin by construction of coordinated 
developments for navigation, hydroelectric 
power, flood control, water supply, water 
quality control, sediment control, recreation, and 
fish and wildlife propagation. McClellan-Kerr 
Arkansas River Navigation System provides a 
channel 9 feet deep and 447.5 miles long, beginning 
at mouth of White River, which enters Mississippi 
River 599.0 miles above Head of Passes, 
La.; thence 10.0 miles upstream to mouth of Wild 
Goose Bayou; thence 9.0 miles by a land cut, 
designated as Arkansas Post Canal to mile 42.0 
(1943 survey) on Arkansas River; thence 378.2 
miles along channel of latter stream to mouth of 
Verdigris River at navigation mile 392.2; thence 
50.3 miles up Verdigris River to head of navigation 
at Catoosa, Okla. Waterway is canalized 
throughout its length by 17 locks and dams with 
total lift of 420 feet. Dardanelle, Ozark, Robert S. 
Kerr, and Webbers Falls are multiple-purpose 
projects including power. Lock chambers are 110 
by 600 feet. A minimum channel width of 150 feet 
is provided for Verdigris River, 250 feet for 
Arkansas River, and 300 feet for Arkansas Post 
Canal and White River. Other coordinated 
developments consist of 15 lakes, of which 13 are 
in Tulsa District, Kansas and Oklahoma, and two 
in Little Rock District, Arkansas. The authorized 
features of the multiple-purpose plan within the 
Tulsa District are listed in table 19-C. Amounts 
authorized to be appropriated for combined cofnprehensive 
and multiple-purpose plan total $1,- 
411,667,000. 
Local cooperation. For the navigation system, 
local interest must provide adequate terminal 
and transfer facilities and bear increased cost of 
maintenance and operation of all altered rail and 
highway routes, including bridges and appurtenances, 
utilities, and other existing improvements, 
other than federally owned. For 
lakes see requirements for each individual lake. 
Terminal facilities. Public port facilities were 
in operation at Pine Bluff, Little Rock, and Fort 
Smith, Ark., and Muskogee and Catoosa (Tulsa), 
Okla. Port authorities have been organized to 
develop public facilities at North Little Rock. 
Dardanelle, Russellville, Clarksville, and Van 
Buren, Ark. Private commercial port facilities 
are complete and in operation at seven locations 
in Arkansas and at four locations in Oklahoma. 
Ten additional private port facilities are being 
developed along improved waterways in the State 
of Arkansas and two in Oklahoma. 
Operations and results during fiscal year. Blue 
Mountain, Canton, Dardanelle Lock and Dam 
(No. 10), Dardanelle Marine Terminal, David D. 
Terry Lock and Dam (No. 6), Elk City, Eufaula, 
Fall River, Fort Gibson, Keystone, W. D. Mayo 
Lock and Dam (No. 14), Chouteau Lock and Dam 
(No. 17), Newt Graham Lock and Dam (No. 18), 
Robert S. Kerr Lock and Dam and Reservoir (No. 
15), Webbers Falls Lock and Dam (No. 16), and 
Oologah; Locks and Dams Nos. 2, 3, 4, 5, 9, and 13, 
Markham Ferry, Murray Lock and Dam (No. 7), 
Nimrod, Norrell Lock and Dam (No. 1), Ozark 
Lock and Dam (No. 12), Pensacola, Pine Bluff 
Marine Terminal, Robert S. Kerr Marine Terminal, 
Tenkiller Ferry, Toad Suck Ferry Lock 
and Dam (No. 8), Toronto, and Wister were in 
operation. Construction continued on powerplant 
at Ozark and on bank stabilization. For details of 
McClellan-Kerr Arkansas River Navigation 
System and lakes in Arkansas see report for Little 
Rock District. Details of McClellan-Kerr 
Arkansas River Navigation System and lakes in 
Oklahoma and Kansas are shown on following 
pages. 
Condition at end of fiscal year. Status of individual 
items are reported separately in this 
chapter. 
2. BANK STABILIZATION AND 
CHANNEL RECTIFICATION, 
ARKANSAS RIVER, ARK. AND OKLA. 
Location. On Arkansas River between Robert 
S. Kerr Damsite and Fort Smith, Ark., river 
miles 336.2 and 295.4, respectively. (See 
Geological Survey maps for Sans Bois, Okla., 
Sallisaw, Okla., and Fort Smith, Ark.-Okla., 
quadrangles, scale 1:125,000.) 
Existing project. Bank stabilization and 
channel rectification is a part of the McClellan- 
Kerr Arkansas River Navigation System. For 
description of completed improvement and 
authorizing legislation see Annual Report for 
1970. Federal cost was $12,700,000 for existing 
project located in Tulsa District. 
Local cooperation. See section 1 of this report. 
Operations and results during fiscal year. 
None. Operation and maintenance of project 
structures is reported under appropriate navigation 
locks and dams. 
Condition at end of fiscal year. Construction 
began in May 1952 and completed December 
1969. 
19-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
3. LOW HEAD LOCKS AND DAMS, 
OKLA. 
There are three lock and dam units on the 
Arkansas and Verdigris Rivers in addition to 
Robert S. Kerr and Webbers Falls. With some 
channel cutoffs and enlargement work they 
provide a navigable channel 9 feet deep from Fort 
Smith, Ark., to vicinity of Catoosa, Okla., where a 
turning basin is provided. Total estimated cost, 
including turning basin and channel cutoffs and 
enlargement is $108,500,000. (See table 19-B for 
authorizing legislation.) 
3A. LOCK AND DAM NO. 13, CHANNEL 
IMPROVEMENT, ARKANSAS RIVER 
BASIN, OKLA. 
Location. Fort Smith, Ark., to W. D. Mayo Lock 
and Dam. 
Existing project. Consists of channel cutoffs and 
enlargement work to provide a navigable channel 
9 feet deep with a minimum width of 250 feet 
from Fort Smith, Ark., to W. D. Mayo Lock and 
Dam. 
Local cooperation. None. 
Terminal facilities. None. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Condition at end offiscal year. Existing project 
located in Tulsa District is complete. 
3B. W. D. MAYO LOCK AND DAM, 
ARKANSAS RIVER BASIN, OKLA. 
Location. Arkansas River at navigation mile 
319.6, about 9 miles southwest of Fort Smith, 
Ark. 
Existing project. For description of completed 
improvement, see Annual Report for 1972. Project 
is a unit of the McClellan-Kerr Arkansas 
River Navigation System. 
Local cooperation. See section 1 of this report. 
Terminal facilities. None. 
Operations and results during fiscal year. Major 
accomplishments with regular 
funds: Landscaping of public-use areas was completed. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in May 1966 and the project placed in 
useful operation in October 1970. Lock and dam 
became operational for navigation December 
1970. 
3C. CHOUTEAU LOCK AND DAM, 
VERDIGRIS RIVER BASIN, OKLA. 
Location. Verdigris River at navigation mile 
6.5, about 7 miles north of Muskogee in Wagoner 
County, Okla. 
Existing project. For description of completed 
improvement, see Annual Report for 1972. Project 
is a unit of the McClellan-Kerr Arkansas 
River Navigation System. 
Local cooperation. See section 1 of this report. 
Terminal facilities. Barge fleeting area and 
grain loading facilities are adequate for present 
traffic. 
Operations and results during fiscal year. New 
work: Recreation facilities and beautification 
$95,191. Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in July 1966 and the project placed in 
useful operation in November 1970. Lock and 
dam became operational for navigation in 
December 1970. 
3D. NEWT GRAHAM LOCK AND DAM, 
VERDIGRIS RIVER BASIN, OKLA. 
Location. Verdigris River at navigation mile 
26.7, about 8 miles southwest of Inola in Wagoner 
County, Okla. 
Existing project. For description of completed 
improvement, see Annual Report for 1972. Project 
is a unit of the McClellan-Kerr Arkansas 
River Navigation System. 
Local cooperation. See section 1 of this report. 
Terminal facilities. The Port of Catoosa offers 
storage and loading facilities consisting of cargo 
wharf, warehouse, terminal building, liquid 
loading facility, and fertilizer (dry bulk) facility. 
Facilities are considered adequate for present 
commerce. 
Operations and results during fiscal year. New 
work: Recreation facilities and beautification 
$514,366. Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in October 1966 and the project placed in 
useful operation in September 1970. Lock and 
dam became operational for navigation in 
December 1970. 
19-4

TULSA, OKLA., DISTRICT 
4. MAINTENANCE AND REPAIR 
FLEET AND MARINE TERMINALS, 
OKLA. 
Includes two terminals in the Little Rock District, 
and one terminal in the Tulsa District 
located between Fort Smith, Ark., and Catoosa, 
Okla. (See table 19-B for authorizing legislation.) 
Information on this project follows: 
ROBERT S. KERR MARINE TERMINAL, 
OKLA. 
Location. Five miles south of Sallisaw, Okla., on 
the left side of Robert S. Kerr Lock and Dam and 
Reservoir. 
Existing project Consists of wharf, office and 
storage building, storage space, and operating 
areas for servicing of floating plant and storage of 
machinery, equipment, and supplies to maintain 
the navigation facilities. Estimated cost is $2,- 
760,000 excluding cost of facilities to be provided 
for the US Coast Guard on a reimbursable basis. 
Local cooperation. See section 1 of this report. 
Operations and results during fiscal year. 
Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in May 1967 and the terminal became 
operational in October 1970. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECT 
Red River from Fulton, Ark., to mouth of 
Washita River. For description of completed improvement 
and authorization see Annual Report 
for 1924. Cost for construction was $378,574 and 
operation and maintenance $182,157. Curtailment 
of project was recommended in H. Doc. 947, 
64th Cong., 1st sess. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
Fiscal year costs for continuation of Detailed 
Project Report were $9,639 for Poteau River, 
Fort Smith, Ark., channel and turning basin to 
serve Port of Fort Smith. Studies for Big and Little 
Sallisaw Creeks, Sallisaw, Okla., entrance 
channel and turning basin to serve Port of 
Sallisaw were discontinued. 
Flood Control 
7. ARCADIA LAKE, DEEP FORK RIVER 
BASIN, OKLA. 
Location. On Deep Fork River, mile 213.6 in the 
metropolitan area of Oklahoma City and Edmond, 
Okla., about 1.5 miles west of Arcadia, in 
Oklahoma County, Okla. (See Geological Survey 
map for Arcadia, Okla., quadrangle, scale 1:24,- 
000.) 
Existing project. Plan of improvement provides 
for flood control, water supply, water quality control, 
and recreation by construction of an earthfill 
dam approximately 72 feet high and 4,300 feet 
long with an ogee-weir spillway controlled by 
four 40- by 35-foot tainter gates. Outlet works 
would consist of one 4- by 4-foot sluice and one 24- 
inch pipe for future water supply. The lake would 
have a total capacity of 73,200 acre-feet (42,100 
for conservation and 31,100 for flood control and 
sedimentation reserve), and control a drainage 
area of 105 square miles. Estimated Federal cost 
is $45,200,000. (See table 19-B for authorizing 
legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, Federal Water 
Project Recreation Act of 1965, and Section 221, 
Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. Phase I of the 
General Design Memo is 80 percent complete. 
8. ARK-RED BASINS CHLORIDE 
CONTROL, OKLA., TEX., AND KANS. 
Location. On certain tributary streams of 
Arkansas and Red Rivers in the western half of 
Tulsa District. 
Existing project Provides for construction of 
two experimental water quality study projects; 
supplemental planning studies of the Great Salt 
Plains area on Salt Fork of the Arkansas River 
and along Jonah Creek of Red River; construction 
of three low-flow dams, and two brine storage 
lakes, together with necessary pumping plants 
and pipelines in the Wichita River watershed; 
and construction of three fresh water lakes with 
outlet diversion channels, seven brine storage 
lakes and subsurface cutoff walls, collection con- 
19-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
duits, pipeline, and pumping facilities in the 
Arkansas and Red River Basins. (See table 19-B 
for authorizing legislation.) Project features on 
which preconstruction planning, construction, or 
maintenance and operation has been initiated are 
reported below. 
8A. EXPERIMENTAL 
CONTROL PROJECT, 
BASIN, TEX. 
CHLORIDE 
RED RIVER 
Location. Part of project is on Prairie Dog 
Town Fork of Red River, in Hall County, about 
0.5 mile east of Estelline, Tex., and part of project 
is in South Wichita River watershed in King 
County, about 6 miles east of Guthrie, Tex. (See 
Army Map Service maps for Plainview and Lubbock, 
Tex.) 
Existing project. Experimental structures to 
determine feasibility of controlling and abating 
chloride flows by applying a counterbalancing, 
hydrostatic head on two brine springs. Structures 
consist of an earthen dike and a weir around a 
large spring near Estelline, Tex., and a concrete 
plug, pipe, and weir at one of several salt springs 
near Guthrie, Tex. Project will include instrumentation 
and performance of tests to determine 
effectiveness of construction work. Federal 
cost was $300,028. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Operation of project near Guthrie, Tex., was discontinued 
in 1966. Structure near Estelline, Tex., 
was operated and maintained in a serviceable 
condition. 
Condition at end of fiscal year. Structure near 
Estelline, Tex., was completed and placed in permanent 
operation in 1966. 
8B. ARK-RED BASINS CHLORIDE 
CONTROL, SUPPLEMENTAL 
STUDIES, OKLA. 
Location. On Salt Fork of Arkansas River 
about 12 miles east of Cherokee, Alfalfa County, 
Okla. (See sectional aeronautical chart, Wichita 
sheet, scale 1:500,000.) Also, on Jonah Creek of 
Red River about 12 miles northwest of Childress, 
Childress County, Tex. (See Geological Survey 
map for Estelline, Tex., 1961, quadrangle, scale 
1:62,500.) 
Existing project. Provides for field investigations 
required to fully substantiate the 
effectiveness of proposed chloride control structures 
including a fresh water impoundment dike 
at Great Salt Plains on Salt Fork of the Arkansas 
River and a brine collection system, evaporation 
pond, and deep well injection tests on Jonah Creek 
of Red River. Additional water quality monitoring 
stations in the two basins together with field 
tests are required to develop engineering data 
needed for selection and design of efficient control 
plans. Estimated cost is $2,860,000. 
Local cooperation. None required. 
Operations and results during fiscal year. At 
the Great Salt Plains, data collection and routine 
operation and maintenance were essentially completed. 
At Jonah Creek construction of advanced 
testing facilities was initiated in June 1973. 
Testing facilities consist of an expanded subsurface 
collection system and surface facilities to 
collect and dispose of natural brines by deep well 
injection. 
Condition at end of fiscal year. Investigations 
began in January 1968 and are complete. 
8C. ARK-RED BASINS CHLORIDE 
CONTROL, TEX. 
Location. On headwater tributaries of Wichita 
River in King, Knox, Foard, and Cottle Counties, 
and on the Canal Creek tributary of Pease River, 
Foard County, Tex. 
Existing project. Provides for a system of three 
low-flow dams with attendant pumping and 
pipeline facilities discharging into two offchannel 
brine storage reservoirs. Each low-flow 
dam will be equipped with an inflatable fabrictype 
weir located in the spillway section which 
would be deflated to pass relatively good quality 
high flows downstream. Total estimated Federal 
cost is $4,000,000. (See table 19-D on Wichita 
River Control Plan, Tex.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Engineering studies required for preconstruction 
planning continued. 
Condition at end of fiscal year. Preconstruction 
planning is essentially complete. 
8D. ARK-RED BASINS CHLORIDE 
CONTROL, OKLA., TEX., AND KANS. 
Location. On tributaries of the Arkansas and 
Red Rivers in Texas, Oklahoma, and Kansas: 
Area I, Great Salt Plains, Salt Fork of the 
Arkansas in Alfalfa County, Okla.; Area II-III, 
Big and Little Salt Plains of the Cimarron River 
in parts of Woods, Woodward, and Harper Counties, 
Okla., and Clark and Comanche Counties, 
Kans.; Area IV, Salt Creek of the Cimarron River 
19-6

TULSA, OKLA., DISTRICT 
in Blaine County, Okla.; Area VI, Elm Fork of 
Red River, Harmon County, Okla.; Area IX, 
North and Middle Pease Rivers, Cottle County, 
Tex.; Area XIII-XIV, Jonah and Salt Creeks of 
Prairie Dog Town Fork of Red River, Childress 
County, Tex.; and Area XV, Little Red River of 
Prairie Dog Town Fork of Red River, Hall County, 
Tex. 
Existing project. The plan of improvement consists 
of three fresh water lakes with outlet 
channels to divert fresh water, two brine lakes 
and modification of the existing Great Salt Plains 
Lake to control salt pollution from four major 
sources in the Arkansas River Basin, and four 
brine lakes and four collection systems with 
attendant pumping facilities to control salt pollution 
from five major sources in the Red River 
Basin. Estimated Federal cost is $544,000,000. 
(See table 19-E on Ark-Red River chloride control 
plan.) 
Local cooperation. Prior to construction of the 
chloride control projects and pending establishment 
of a public policy on division of responsibility 
between Federal and non-Federal interests, 
assurances satisfactory to the Secretary of the 
Army will be furnished by responsible non- 
Federal interests to provide that these interests 
will continue and strengthen efforts to reduce 
manmade salt pollution, hold and save the United 
States free from damages due to water rights 
claims and to construction and operation of the 
project works, and participate in the cost of 
recreation and fish and wildlife enhancement in 
accordance with the Federal Water Project 
Recreation Act. 
Operations and results during fiscal year. 
None. 
Condition at end of fiscal year. Phase I of the 
General Design Memo is underway. 
9. BIG HILL LAKE, VERDIGRIS RIVER 
BASIN, KANS. 
Location. On Big Hill Creek, river mile 33.3, 
about 5 miles east of Cherryvale, Kans. (See 
Geological Survey maps for Mount Valley and 
Parsons, Kans., quadrangles, scale 1:62,500.) 
Existing project. Provides for an earthfill dam 
about 4,425 feet long, 83 feet above streambed. 
The 400-foot uncontrolled spillway will be located 
in the right abutment. Outlet works will include a 
drop inlet intake structure, a 7-foot 3-inchdiameter 
conduit, and a stilling basin. An 18- 
inch-diameter pipe will be provided for water 
supply releases. The lake will have a total capacity 
of 40,600 acre-feet, (13,100 for flood control and 
27,500 for conservation and sedimentation 
reserve), and will control runoff from a drainage 
area of 37 square miles. Big Hill Lake will be 
operated as a unit of a five-lake system for flood 
control in the Verdigris River Basin in Kansas, 
with a seven-lake system in Verdigris River 
Basin in Oklahoma. Estimated cost is $9,960,000. 
(See table 19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Section 221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
Engineering studies and planning for land acquisition 
continued. Major accomplishments 
with regular funds: Lands and damages $32,000; 
engineering and design $98,000; and buildings, 
grounds, and utilities $379,000. 
Condition at end of fiscal year. Construction 
began in April 1974. The project is 19 percent 
complete. 
10. BIG PINE LAKE, RED RIVER BASIN, 
TEX. 
Location. On Big Pine Creek (mile 16.5) approximately 
2 miles northwest of Clarksville, Red 
River County, Tex. (See Geological Survey maps 
for Woodland, Manchester, and Kiomatia, Tex., 
quadrangles, scale 1:62,500 and Army Map Service 
map, Texarkana, Tex., scale 1:25,000.) 
Existing project. Plan of improvement provides 
for an earthfill dam 7,900 feet long, including an 
uncontrolled concrete chute spillway. Dam will 
rise to a height of 78.5 feet above streambed. Outlet 
works will consist of a 4-foot-diameter inlet 
conduit and a stilling basin. A 30-inch water 
supply pipe and a 24-inch low-flow pipe will be 
constructed through the dam. The lake will have 
a total capacity of 174,400 acre-feet, of which 74,- 
450 acre-feet will be allocated for flood control 
and 99,500 acre-feet for conservation and 
sedimentation reserve. Channel downstream will 
be improved by clearing and snagging to increase 
its capacity. The lake will control a drainage area 
of 95 square miles. Estimated cost is $22,800,000. 
(See table 19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Section 221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. Phase I of the 
General Design Memo is 95 percent complete. 
19-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
11. BIRCH LAKE, VERDIGRIS RIVER 
BASIN, OKLA. 
Location. On Birch Creek, river mile 0.8, about 
1.5 miles south of Barnsdall in Osage County, 
Okla. (See Geological Survey map for Barnsdall, 
Okla., quadrangle, scale 1:24,000.) 
Existing project. Plan of improvement provides 
for an earthfill dam 3,315 feet long and 97 feet 
high with an uncontrolled spillway, controlled 
outlet works, and supporting facilities. Total lake 
capacity will be 58,180 acre-feet (39,000 for flood 
control, 15,820 for water supply and low-flow 
regulation, and 3,360 for sedimentation reserve). 
Drainage area above damsite is 66 square miles. 
Birch Lake will be operated as a unit of a sevenlake 
system for flood control in the Verdigris 
River Basin in Oklahoma. Estimated cost is $13,- 
000,000. (See table 19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Section 221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
Engineering studies continued. Major accomplishments 
with regular funds: Land acquisition 
$170,000; dams $1,816,000; roads, 
railroads, and bridges $72,000; and buildings, 
grounds, and utilities $254,000. 
Condition at end of fiscal year. Construction 
began in November 1973. The project is 44 percent 
complete. 
12. CANDY LAKE, VERDIGRIS RIVER 
BASIN, OKLA. 
Location. On Candy Creek, river mile 1.9, a 
tributary of Bird Creek in Verdigris River Basin. 
Damsite is about 1 mile northeast of Avant, Osage 
County, Okla. (See Geological Survey map for 
Avant, Okla., quadrangle, scale 1:24,000.) 
Existing project. Plan of improvement provides 
for an earthfill dam about 4,210 feet long, including 
an uncontrolled concrete spill.way, with a 
maximum height of 102 feet above streambed. 
Outlet works will consist of a gated intake structure, 
a 10- by 11.25-foot conduit, and a stilling 
basin. A 24-inch low-flow pipe and an 18-inch 
water supply pipe will be provided. The lake will 
have a total capacity of 96,520 acre-feet (44,160 
for conservation and sediment reserve and 31,260 
for flood control). Drainage area above the damsite 
is 43 square miles. Candy Lake will be 
operated as a unit of a seven-lake system for flood 
control in the Verdigris River Basin in 
Oklahoma. Estimated cost of project is $21,000,- 
000. (See table 19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, and Section 
221 of the Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. Preconstruction 
planning is 99 percent complete. 
13. CANTON LAKE, ARKANSAS RIVER 
BASIN, OKLA. 
Location. On North Canadian River Basin, 
Okla., about 394 miles above its mouth and about 
2 miles north of Canton, Blaine County, Okla. (See 
sectional aeronautical chart, Wichita sheet, scale 
1:500,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 590 of Annual Report for 1969. Estimated 
Federal cost is $11,174,000, of which $486,000 is 
Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Four noteworthy rises occurred above the lake. 
Operation of Canton Lake prevented downstream 
flooding on an average of 3,700 acres of land. Estimated 
monetary benefits attributed to Canton 
Lake operations for prevention of flood damages 
total $5,640,000 to June 30, 1975. (See table 19-F 
for pool elevations and storages during fiscal 
year.) 
Condition at end of fiscal year. Construction 
began in December 1940 and project placed in 
useful operation in April 1948. Work required to 
complete the project consistsof additional recreation 
facilities. 
14. CEDAR POINT LAKE, GRAND 
(NEOSHO) RIVER BASIN, KANS. 
Location. On Cedar Creek, mile 4.2, a tributary 
of Cottonwood River, about 1.5 miles south of 
Cedar Point in Chase County, Kans. (See 
Geological Survey map for Cottonwood Falls, 
Kans., quadrangle, scale 1:125,000.) 
Existing project. Provides for flood control and 
water quality control- by construction of an 
earthfill dam 7,120 feet long, including an uncontrolled 
spillway section 300 feet wide, rising 117 
feet above streambed. Outlet works will consist of 
a gated intake structure, a 12-foot conduit, and 
19-8

TULSA, OKLA., DISTRICT 
two 24-inch-diameter intakes, one for low flow 
and one for water supply. The lake will have a 
total capacity of 108,600 acre-feet (37,100 for 
flood control and 71,500 in conservation pool), and 
control a drainage area of 119 square miles. 
Cedar Point Lake will be operated as the final 
unit of a four-lake system for flood control in 
Grand (Neosho) River Basin, consisting of this 
project and the completed John Redmond Reservoir 
and Council Grove and Marion Lakes. Estimated 
Federal cost is $23,700,000. (See table 19- 
B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. Phase I of the 
General Design Memo is 99 percent complete. 
15. CLAYTON LAKE, LITTLE RIVER 
BASIN, OKLA. 
Location. On Jackfork Creek, river mile 2.8, a 
tributary of Kiamichi River, about 2.5 miles 
north of Clayton, Pushmataha County, Okla. (See 
Geological Survey map for Tuskahoma, Okla., 
quadrangle, scale 1:125,000 and Army Map Service 
map, McAlester, Okla., scale 1:250,000.) 
Existing project. Provides for a rolled earthfill 
dam about 14,400 feet long, with a maximum 
height of 100 feet above the streambed. An uncontrolled 
spillway 200 feet wide will be constructed 
near the right abutment. Outlet works will con - 
sist of an oblong conduit, 9 by 12.25 feet, and a 2.5- 
by 5.25-foot pipe will be installed for low-flow 
regulation. The lake will provide 128,200 acrefeet 
of storage for flood control and 302,400 acrefeet 
for conservation and sediment reserve, a total 
of 430,600 acre-feet, and control a drainage area 
of 275 square miles. Clayton Lake will be 
operated as a unit of a three-lake system for flood 
control in the Kiamichi River Basin, including 
Hugo and Tuskahoma Lakes thereby reducing 
Red River floodflows. Estimated cost of project is 
$38,100,000. (See table 19-B--Red River below 
Denison Dam (Tulsa District)-for authorizing 
legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Section 221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Land 
acquisition $1,085,000; engineering and design 
$162,000. 
Condition at end offiscal year. Construction has 
not started. 
16. COPAN LAKE, VERDIGRIS RIVER 
BASIN, OKLA. 
Location. On Little Caney River, river mile 7.4, 
a tributary of Caney River in Verdigris River 
watershed, about 2 miles west of Copan, 
Washington County, Okla. (See Geological Survey 
maps of Nowata, Okla., and Sedan and Independence, 
Kans., quadrangles, scale 1:125,000 
and Army Map Service maps, Tulsa, Okla., 
Wichita, Kans., and Joplin, Mo.,scale 1:250,000.) 
Existing project. Provides for an earthfill dam 
7,730 feet long, including a gated spillway section, 
and a levee 17,000 feet long, for protection of 
Caney, Kans. Maximum height above streambed 
will be 73 feet. A concrete spillway, controlled by 
four 50- by 35.5-foot tainter gates, will provide for 
operation of lake for flood control. Outlet works 
will include a 36-inch low-flow pipe and a 12-inch 
future water supply pipe. The lake will have a 
total capacity of 227,700 acre-feet (43,400 for conservation 
and sediment reserve, and 184,300 for 
flood control). Drainage area above damsite is 505 
square miles. Copan Lake will be operated as a 
unit of a seven-lake system for flood control in 
Verdigris River Basin in Oklahoma. Relocated 
Oklahoma State Highway 10 will cross the top of 
the dam. Estimated cost is $64,900,000. (See table 
19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, and Section 
221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Land 
acquisition $2,697,000; relocations $63,000. 
Condition at end of fiscal year. Construction 
began in November 1972. The project is 13 percent 
complete. 
17. COUNCIL GROVE LAKE, GRAND 
(NEOSHO) RIVER BASIN, KANS. 
Location. On Grand (Neosho) River about 450 
miles above mouth and about 1.5 miles northwest 
of Council Grove, Morris County, Kans. (See 
Geological Survey maps for Parkerville and Eskridge, 
Kans., quadrangles, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 519 of Annual Report for 1969. Estimated 
Federal cost is $11,741,000, of which $294,000 is 
Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
19-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Additional recreation facilities were constructed. 
During low-flow water periods, releases totaling 
4,800 acre-feet were made for water quality control. 
Five noteworthy rises occurred on Grand 
(Neosho) River above the lake. Operation of Council 
Grove Lake prevented downstream flooding 
on an average of 5,200 acres of land. Estimated 
monetary benefits attributed to Council Grove 
Lake operations for prevention of flood damages 
total $5,064,000 to June 30, 1975. (See table 19-F 
for pool elevations and storages during fiscal 
year.) 
Condition at end of fiscal year. Construction 
began in July 1960 and project placed in useful 
operation in October 1964. Work required to complete 
the project consists of additional recreation 
facilities. 
18. DEQUEEN LAKE, LITTLE RIVER 
BASIN, ARK. 
Location. On Rolling Fork River, river mile 
22.8, a tributary of Little River, in Sevier County, 
about 4 miles northwest of DeQueen, Ark. (See 
Geological Survey map for DeQueen, Ark., 
quadrangle, and Army Map Service map, 
McAlester, Okla., scale 1:250,000.) 
Existing project. Provides for an earthfill dam, 
2,360 feet long, constructed to 160 feet above 
streambed. An uncontrolled spillway, 200 feet 
wide, will be about 1,400 feet east of main embankment. 
Outlet works consist of a gated conduit, 
12 feet in diameter. The lake will control 169 
square miles of drainage area and provide a total 
storage of 136,100 acre-feet (101,200 for flood control 
storage and 34,900 for conservation and 
sedimentation reserve.) DeQueen Lake will be 
operated as a unit of a seven-lake system for flood 
control in Little River watershed, thereby reducing 
Red River floodflows. Estimated cost of project 
is $16,700,000. (See table 19-B-Red River 
below Denison Dam (Tulsa District)-for 
authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, and Section 301, Water Supply Act of 
1958, as amended, apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Embankment, 
spillway, and outlet works $1,742,000. 
Eight noteworthy rises occurred above the lake. 
The structure reduced downstream flooding on 
an average of 1,100 acres. Lake operations for 
prevention of flood damages total $208,000 to 
June 30, 1975. 
Condition at end of fiscal year. Construction 
began April 1966. The project is 84 percent complete. 
19. DIERKS LAKE, LITTLE RIVER 
BASIN, ARK. 
Location. On Saline River, river mile 56.6, a 
tributary of Little River, about 5 miles northwest 
of Dierks, Howard County, Ark. (See Geological 
Survey map for DeQueen, Ark., quadrangle, and 
Army Map Service map, McAlester, Okla., scale 
1:250,000.) 
Existing project. Provides for an earthfill dam, 
2,760 feet long, about 153 feet above streambed. 
An uncontrolled spillway 800 feet wide will be in 
a saddle at west end of dam. Outlet works consisting 
of a gated 6- by 9-foot oblong conduit, one 
24-inch low-flow pipe, and one 30-inch water 
supply pipe will be provided. The lake will control 
a drainage area of 114 square miles and provide 
for storage of 67,100 acre-feet for flood control 
and 29,700 acre-feet for water supply, conservation, 
and sedimentation reserve, a total of 96,800 
acre-feet. Dierks Lake is operated as a unit of a 
seven-lake system for flood control in Little River 
watershed, thereby reducing Red River 
floodflows. Estimated cost of project is $15,800,- 
000. (See table 19-B-Red River below Denison 
Dam (Tulsa District)--for authorizing legislation.) 
Local cooperation. Section 2, Flood Contro Act 
of 1938, and Water Supply Act of 1958, as amended, 
apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Embankment, 
spillway, and outlet works $323,000; 
and recreation facilities $279,000. Eight 
noteworthy rises occurred above the lake. The 
structures in place reduced flooding on 1,300 
acres of land. Lake operations for prevention of 
flood damages total $440,000 to June 30, 1975. 
Condition at end of fiscal year. Construction 
began in June 1968. The embankment closure 
was made on May 8, 1975 and the project placed 
in useful operation. 
20. EL DORADO LAKE, WALNUT RIVER 
BASIN, KANS. 
Location. On Walnut River, river mile 100.2, a 
tributary of Arkansas River, about 2 miles 
northeast of El Dorado, Butler County, Kans. (See 
19-10

TULSA, OKLA., DISTRICT 
Geological Survey maps for El Dorado and De 
Graff, Kans., quadrangles, scale 1:24,000.) 
Existing project. Provides for an earthfill dam 
16,600 feet long, including a gated spillway with 
five 40-foot-wide by 35-foot-high tainter gates. 
Dam will be 89 feet above streambed. The lake 
will control 234 square miles of drainage area and 
provide a total storage of 236,200 acre-feet (79,- 
200 for flood control storage, 154,100 for conservation, 
and 2,900 for sedimentation reserve). Outlet 
works will consist of a 24-inch low-flow pipe 
and a 24-inch water supply pipe. El Dorado Lake 
will be operated as a unit of a three-lake system 
for flood control in the Walnut River Basin. Estimated 
cost of project is $71,900,000. (See table 
19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, Federal Water 
Recreation Act of 1965, and Section 221 of the 
Flood Control Act of 1970 apply. 
Operations and results during fiscal year. Land 
acquisition continued and construction on embankment, 
spillway, and outlet works was initiated. 
Condition at end of fiscal year. Construction 
began in October 1973. The project is 14 percent 
complete. 
21. EL DORADO, KANS. 
Location. West Branch of Walnut River at El 
Dorado, Butler County, Kans. (See Geological 
Survey map for El Dorado, Kans., quadrangle, 
scale 1:24,000). 
Existing Project. A local protection project to 
improve West Branch channel for 1.6 miles 
through the city of El Dorado. Improved channel 
will be 8,400 feet long, 13 feet deep with a bottom 
width of 150 feet. Spoil bank levee will be 16,800 
feet long, and training levee 4,900 feet long will be 
constructed at upper end of project. Estimated 
Federal cost is $2,690,000 and estimated non- 
Federal cost is $1,240,000. 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; maintain 
and operate completed works; perform all 
relocations except railroads; and acquire fee title 
to lands for borrow and ponding purposes and 
flowage easements over lands for ponding only, as 
may be required. 
Operations and results during fiscal year. 
Preconstruction planning was suspended. 
Condition at end of fiscal year. Phase I of the 
General Design Memo is 40 percent complete. 
22. ELK CITY LAKE, VERDIGRIS RIVER 
BASIN, KANS. 
Location. On Elk River, river mile 8.7, about 7 
miles northwest of Independence, Montgomery 
County, Kans. (See Geological Survey maps for 
Caney-NE, NW, and SW, and Benton, Kans., 
quadrangles, scale 1:24,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 593 of Annual Report for 1969. Federal cost 
was $19,042,990. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
During low-flow water periods, releases totaling 
1,333 acre-feet were made for water quality control. 
Six noteworthy rises occurred above the 
lake. Operation of the lake prevented 
downstream flooding on an average of 5,100 acres 
of land. Estimated monetary benefits attributed 
to Elk City Lake for prevention of flood damages 
total $9,065,000 to June 30, 1975. (See table 19-F 
for pool elevations and storages during fiscal 
year.) 
Condition at end of fiscal year. Construction 
began in February 1962 and project placed in 
useful operation in March 1966. 
23. FALL RIVER LAKE, VERDIGRIS 
RIVER BASIN, KANS. 
Location. On Fall River about 54 miles above its 
confluence with Verdigris River and about 4 
miles northwest of Fall River, Greenwood County, 
Kans. (See Geological Survey map for Eureka, 
Kans., quadrangle, scale 1:125,000; and Severy, 
Kans., quadrangle, scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 593 of Annual Report for 1969. Estimated 
Federal cost is $10,494,413, of which $49,652 is 
Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Seven noteworthy rises occurred above the lake. 
Operation of the lake prevented downstream 
flooding on an average of 3,900 acres of land. Estimated 
monetary benefits attributed to Fall 
River Lake operations for prevention of flood 
damages total $16,130,000 to June 30, 1975. (See 
table 19-F for pool elevations and storages during 
fiscal year.) During low-flow water periods, 
19-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
releases totaling 864 acre-feet were made for 
water quality control. 
Condition at end of fiscal year. Construction of 
dam began in May 1946 and project placed in full 
operation in April 1949. 
24. FLAT ROCK CREEK, TULSA, OKLA. 
Location. Flat Rock Creek and its tributary, 
Valley View Creek, in the Bird Creek Basin, 
Tulsa County, Okla. (See Geological Survey map 
for Tulsa, Okla., quadrangle, scale 1:24,000.) 
Existing project. Flood protection for the urban 
area of north Tulsa, Okla. Plan provides for approximately 
7,300 feet of channel improvements 
with quarry-run stone bank protection on Flat 
Rock Creek and 4,600 feet of concrete-lined 
channel on Valley View Creek. Project was approved 
for construction under authority of Section 
205 of the Flood Control Act of 1948, as 
amended. Total Federal cost is $1,000,000; non- 
Federal cost $1,363,000. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Major 
accomplishments with available 
funds: Channel improvement, engineering and 
design, and supervision and administration, 
$295,449. 
Condition at end of fiscal year. Construction 
began in October 1973 and is essentially complete 
for flood control. Work remaining consists of concrete 
end sills. 
25. FORT SUPPLY LAKE, NORTH 
CANADIAN RIVER BASIN, OKLA. 
Location. On Wolf Creek, river mile 5.5, a 
tributary of North Canadian River, about 12 
miles northwest of Woodward, Woodward County, 
Okla. (See sectional aeronautical chart, 
Wichita sheet, scale 1:500,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 594 of Annual Report for 1969. Estimated 
Federal cost is $7,735,000, of which $226,000 is 
Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Two noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 200 
acres of land. A total of 188 acre-feet was made 
available for water supply. Estimated monetary 
benefits attributed to Fort Supply Lake 
operations for prevention of flood damages total 
$2,345,000 to June 30, 1975. (See table 19-F for 
pool elevations and storages during fiscal year.) 
Condition at end of fiscal year. Construction 
began in October 1938 and completed in March 
1952. Project placed in full flood control operation 
in May 1942. 
26. GILLHAM LAKE, LITTLE RIVER 
BASIN, ARK. 
Location. Damsite is on Cossatot River, river 
mile 49.0, in Howard County, about 5 miles 
northeast of Gillham, Sevier County, Ark. (See 
Geological Survey map for DeQueen, Ark.-Okla., 
quadrangle, scale 1:125,000; and Atimony, 
Gillham NE, Vandervoort, and Empire, Ark., 
quadrangles, scale 1:24,000.) 
Existing project. Plan provides for a modified 
rockfill dam about 2,850 feet long, (including 
spillway and dike) 160 feet above streambed. 
Gate-controlled spillway, 240 feet gross width, 
located in a saddle immediately west of dam, contains 
four 50- by 42-foot tainter gates. Outlet 
works consist of a 10-foot-diameter concrete-lined 
tunnel controlled by two 4.5- by 10-foot slide gates 
and a stilling basin, a 24-inch supply pipe, and a 
30-inch low-flow pipe. The lake will provide a 
total storage of 221,800 acre-feet (188,700 for 
flood control, 33,100 for conservation storage and 
sedimentation reserve), and will control a 
drainage area of 271 square miles. Gillham Lake 
will be operated as a unit of a seven-lake system 
for flood control in Little River watershed, 
thereby reducing Red River floodflows. Estimated 
cost of project is $17,600,000. (See table 
19-B-Red River below Denison Dam (Tulsa 
District)-for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, and Water Supply Act of 1958, as amended, 
apply. Tri-Lakes Water District furnished a 
resolution of intent to repay costs allocated to 
water supply storage. 
Operations and results during fiscal year. Major 
accomplishment with regular funds: Embankment 
$1,350,048. Ten noteworthy rises occurred 
above the lake reducing flood damages on 
an average of 1,600 acres of land. Lake operations 
for prevention of flood damages total $911,000 to 
June 30, 1975. 
Condition at end of fiscal year. Construction 
began in June 1963. The embankment closure 
was made on May 8, 1975 and the project placed 
in pseful operation. 
19-12

TULSA, OKLA., DISTRICT 
27. GREAT SALT PLAINS LAKE, 
ARKANSAS RIVER BASIN, OKLA. 
Location. On Salt Fork of Arkansas River, mile 
103.3, about 12 miles east of Cherokee, Alfalfa 
County, Okla. (See sectional aeronautical chart, 
Wichita sheet, scale 1:500,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 594 of Annual Report for 1969. Federal cost 
was $4,626,270. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Three noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 3,000 
acres of land. Estimated monetary benefits attributed 
to Great Salt Plains Lake operations for 
prevention of flood damages total $13,234,000 to 
June 30, 1975. (See table 19-F for pool elevations 
and storages during fiscal year.) 
Condition at end of fiscal year. Construction of 
dam was initiated September 1938 and completed 
July 1941. Project placed in full flood control 
operation in May 1941. 
28. HEYBURN LAKE, ARKANSAS 
RIVER BASIN, OKLA. 
Location. On Polecat Creek, a minor tributary 
to Arkansas River near Sapulpa, Creek County, 
Okla. (See Geological Survey maps for Nuyaka, 
Hominy, and Claremore, Okla., quadrangles, 
scale 1:250,000; and Bristow and Kiefer, Okla., 
quadrangles, scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 599 of Annual Report for 1969. Estimated 
Federal cost is $2,507,000 (including $135,300 for 
construction of channel improvement on Polecat 
and Rock Creeks and $133,000 Code 711 funds). 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Rural Water District No. 1, Creek County, Okla., 
used 700 acre-feet of water from the lake. Seven 
noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 1,700 
acres of land. Estimated monetary benefits attributed 
to lake operations for prevention of flood 
damages total $2,905,000 to June 30, 1975. (See 
table 19-F for pool elevations and storages during 
fiscal year.) 
Condition at end of fiscal year. Construction 
was started March 1948 and the project was placed 
in useful operation in September 1950. 
Channel improvements below lake were completed 
in September 1952. Project is complete. 
29. HUGO LAKE, KIAMICHI RIVER 
BASIN, OKLA. 
Location. On Kiamichi River, river mile 17.6, 
about 7 miles east of Hugo, Choctaw County, 
Okla. (See Geological Survey map for Alikchi, 
Okla., quadrangle, scale 1:125,000.) 
Existing project. Provides for an earthfill dam 
and gated concrete spillway about 10,200 feet 
long, 101 feet above streambed. Spillway and outlet 
works are combined in a concrete structure in 
the flood plain near the center of dam. The concrete 
structure consists of six 40- by 50-foot 
tainter gates, a 48-inch low-flow pipe, and a 48- 
inch water supply pipe. The lake will have a total 
capacity of 966,500 acre-feet, (809,200 for flood 
control and 157,300 for conservation and 
sedimentation reserve), and will control runoff 
from 1,709 square miles. Hugo Lake operates as a 
unit of the three-lake system for flood control in 
the Kiamichi River Basin, including Clayton and 
Tuskahoma Lakes. Estimated cost is $37,100,000. 
(See table 19-B-Red River below Dension Dam 
(Tulsa District)-for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, and Water Supply Act of 1958, as amended, 
apply. State of Oklahoma through its Water 
Resources Board and local interests furnished 
resolutions of intent to repay costs allocated to 
water supply storage. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Land 
acquisition $160,000; recreation facilities $2,028,- 
000; dam $179,000; and relocations $127,000. 
Four noteworthy rises occurred on the Kiamichi 
River above the lake. The project reduced the 
damaging effects of floods on 6,500 acres of land 
below the damsite, amounting to $2,350,000 to 
June 30, 1975. Operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in October 1967 and the project was placed 
in useful operation in January 1974. 
30. HULAH LAKE, VERDIGRIS RIVER 
BASIN, OKLA. 
Location. On Caney River, river mile 96.2, 
about 15 miles northwest of Bartlesville, near 
Hulah, Osage County, Okla. (See Geological Survey 
maps for Pawhuska, Okla., and Sedan, Kans., 
quadrangles, scale 1:125,000.) 
19-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 595 of Annual Report for 1969. Estimated 
Federal cost is $11,470,000, of which $395,000 is 
Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Six noteworthy rises occurred above the lake. 
Operation of the lake prevented downstream 
flooding on an average of 22,200 acres of land. Estimated 
monetary benefits attributed to Hulah 
Lake operations for prevention of flood damages 
total $39,758,000 to June 30, 1975. During lowwater 
periods, releases totaling 1,040 acre-feet 
were made for water quality control. A total of 
2,060 acre-feet of water was withdrawn by city of 
Bartlesville, Okla. (See table 19-F for pool 
elevations and storages during fiscal year.) 
Condition at end of fiscal year. Construction 
began in May 1946 and completed in June 1950. 
Project placed in full flood control operation in 
September 1951. 
31. JOHN REDMOND DAM AND 
RESERVOIR, GRAND (NEOSHO) 
RIVER BASIN, KANS. 
Location. Dam is on Grand (Neosho) River, 
river mile 343.7, about 2 miles northwest of 
Burlington, Coffey County, Kans. (See Geological 
Survey maps for Burlington and Emporia, Kans., 
quadrangles, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see Annual 
Report for 1970. Estimated cost is $28,372,- 
000, of which $391,000 is Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
During low-flow periods releases totaling 2,402 
acre-feet were made from reservoir for water 
quality control. Seven noteworthy rises occurred 
above the reservoir. Flooding was prevented on 
an average of 17,800 acres of land. Estimated 
monetary benefits attributed to reservoir 
operations for prevention of flood damages total 
$27,358,000 to June 30, 1975. (See table 19-F for 
pool elevations, and storages during fiscal year.) 
Condition at end of fiscal year. Construction 
was initiated in July 1959 and completed in 
December 1965. Project placed in flood control 
operation in July 1964 and is complete except for 
additional recreation facilities. 
32. KAW LAKE, ARKANSAS RIVER 
BASIN, OKLA. 
Location. On Arkansas River, river mile 653.7, 
about 8 miles east of Ponca City, Kay County, 
Okla. (See Geological Survey map for Charley 
Creek, Okla., quadrangle, scale 1:24,000.) 
Existing project. Earthfill dam about 9,467 feet 
long, 121 feet high with a gate-controlled 
spillway. Two 5.7- by 10-foot sluices through 
spillway section provide for low-flow regulation 
and a 48-inch-diameter water supply pipe is 
located in the right nonoverflow. Flow over 
spillway is controlled by eight 50- by 47-foot 
tainter gates. A 24-foot road crosses the embankment. 
The lake will have a total storage capacity 
of 1,348,000 acre-feet (866,000 for flood control 
and 482,000 for conservation and sedimentation 
reserve). A powerhouse substructure and intake 
monolith for possible future power is located 
between the spillway weir and the right nonoverflow 
section. Drainage area above damsite 
contains 46,530 square miles and will control 
runoff from a normal contributing area of 7,250 
square miles. Kaw Lake will be operated as a unit 
of a coordinated lake system for flood control in 
Arkansas River Basin. Estimated cost is $111,- 
100,000. (See table 19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, and Water Supply Act of 1958 apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Land 
acquisition $1,995,000; relocations $6,024,000; 
dam $2,472,000; recreation facilities $2,583,000; 
and reservoir $608,000. One noteworthy rise occurred 
above the structure reducing flood 
damages on 200 acres of land. 
Condition at end of fiscal year. Construction 
began in June 1966 and the project is 84 percent 
complete. 
33. LAKE KEMP, WICHITA RIVER 
BASIN, TEX. 
Location. On Wichita River, river mile 126.7, 
about 40 miles southwest of Wichita Falls, Tex. 
(See aeronautical chart, Dallas, Tex., scale 1:500,- 
000 and Army Map Service map, Wichita Falls, 
Tex., scale 1:250,000.) 
Existing project. Reconstruct and expand existing 
non-Federal lake by raising dam 16 feet 
and providing a new spillway and outlet works. 
The dam is 8,890 feet long and 115 feet above 
streambed. The lake provides a total storage of 
19-14

TULSA, OKLA., DISTRICT 
567,900 acre-feet (248,300 for flood control and 
319,600 for conservation and sedimentation 
reserve), and control a drainage area of 2,086 
square miles. Existing spillway was abandoned 
and blocked off by improved embankment, and a 
new uncontrolled spillway constructed near the 
right abutment. New outlet works consist of two 
5-foot-8-inch by 13-foot hydraulically operated 
slide gates, a 13-foot-diameter conduit, a stilling 
basin, and a 6-inch low-flow pipe. Lake Kemp 
operates as a unit of a coordinated lake system for 
flood control in the Wichita and Red River Basins. 
Estimated Federal cost is $7,751,000 and estimated 
non-Federal cost is $1,360,000. (See table 
19-B for authorizing legislation.) 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Two noteworthy rises occurred above the lake 
reducing flood damages on an average of 4,600 
acres of land. Estimated monetary benefits attributed 
to reservoir operations for prevention of 
flood damages total $2,842,000 to June 30, 1975. 
(See table 19-F for pool elevations and storages 
during fiscal year.) 
Condition at end of fiscal year. Construction 
began in April 1970 and the project placed in 
useful operation in October 1972. 
34. LUKFATA LAKE, LITTLE RIVER 
BASIN, OKLA. AND ARK. 
Location. On Glover Creek at mile 17.3, about 
6.5 miles north of Glover, McCurtain County, 
Okla. (See Geological Survey map for Lukfata, 
Okla., quadrangle, scale 1:125,000; and Bethel, 
Smithville, Golden, and Broken Bow, Okla., 
quadrangles, scale 1:62,500.) 
Existing project. Plan provides for construction 
of a rockfill dam about 2,600 feet long, rising 176 
feet above the original streambed. An uncontrolled 
420-foot saddle spillway will be about 
2,000 feet from the left end of the embankment. 
Outlet works will consist of a 12-foot conduit and a 
stilling basin. The lake will provide a total 
storage of 252,100 acre-feet (208,630 for flood control, 
43,470 for conservation and sedimentation 
reserve), and will control a drainage area of 252 
square miles. Lukfata Lake will be operated as a 
unit of a seven-lake system for flood control in Little 
River watershed, thereby reducing Red River 
floodflows. Estimated cost of project is $29,200,- 
000. (See table 19-B-Red River below Denison 
Dam (Tulsa District)-for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Section 221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
Engineering studies continued. 
Condition at end of fiscal year. Construction has 
not started. 
35. MARION, KANS. 
Location. On Mud Creek at Marion, the county 
seat of Marion County, Kans. 
Existing project. Provides for construction of a 
diversion channel 9,026 feet in length, an 
overflow protection levee 17,875 feet in length, 
and structures to control interior drainage and 
low streamflows. Railroad and highway bridges 
would be altered or relocated as required. 
Estimated Federal cost is $4,500,000 and 900,000 
non-Federal cost. (See table 19-B for authorizing 
legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; hold the 
United States free from damages; maintain and 
operate all works after completion; perform all 
relocations except railroads; acquire fee title to 
lands for borrow and ponding purposes and 
flowage easements over lands for ponding only; 
and prevent encroachment on existing and 
improved channel. 
Operations and results during fiscal year. 
Construction planning was initiated. 
Condition at end of fiscal year. Project 
construction can start when local interests 
provide land and rights-of-way. 
36. MARION LAKE, GRAND (NEOSHO) 
RIVER BASIN, KANS. 
Location. On Cottonwood River, river mile 
126.7, about 3 miles northwest of Marion, Marion 
County, Kans. (See Geological Survey map for 
Newton, Kans., quadrangle, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 597 of Annual Report for 1969. Federal cost 
of project was $13,317,538. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
During low-flow water periods, releases totaling 
3,066 acre-feet were made from the lake for water 
quality control. Four noteworthy rises occurred 
above the lake. Flooding was prevented on an 
average of 900 acres of land. Estimated monetary 
19-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
benefits attributed to Marion Lake operations for 
prevention of flood damages total $23,783,000 to 
June 30, 1975. (See table 19-F for pool elevations 
and storages during fiscal year.) 
Condition at end of fiscal year. Construction 
began in June 1964 and the project placed in flood 
control operation February 1968. 
37. MILLWOOD LAKE, LITTLE RIVER 
BASIN, ARK. 
Location. On Little River, river mile 16.0, approximately 
7 miles east of Ashdown, Little River 
County, Ark., and about 2 miles northeast of 
Millwood, Little River County, Ark. (See 
Geological Survey maps NI-8 and 15-4 for El 
Dorado, Ark., and McAlester, Okla., 
quadrangles, scale 1:250,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 597 of Annual Report for 1969. Estimated 
cost of project is $46,331,000, of which $1,915,000 
is Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Additional recreation facilities were constructed. 
A total of 21,161 acre-feet was released from the 
lake for water supply to Southwest Arkansas 
Water District. Seven noteworthy rises occurred 
above the lake. Flooding was prevented on an 
average of 6,200 acres of land. Estimated 
monetary benefits attributed to Millwood Lake 
operations for prevention of flood damages total 
$2,689,000 to June 30, 1975. (See table 19-F for 
pool elevations and storages during fiscal year.) 
Condition at end of fiscal year. Construction 
began in September 1961 and the project was 
placed in full flood control operation in August 
1966. Work required to complete project consists 
of additional recreation facilities. 
38. MUD CREEK, IDABEL, OKLA. 
Location. Mud Creek, tributary of the Red 
River, McCurtain County, Okla. (See Geological 
Survey map for Idabel, Okla., quadrangle, scale 
1:24,000.) 
Existing project. Plan of improvement is to 
provide approximately 8,950 feet of channel improvements 
for flood protection for the urban 
area of Idabel, Okla. The project was approved 
for construction under authority of Section 205 of 
the Flood Control Act of 1948. Estimated Federal 
cost is $500,000; non-Federal cost $580,000. 
Local cooperation. Section 3, Flood Control Act 
of 1956 and Section 221 of the Flood Control Act of 
1970 apply. 
Operations and results during fiscal year. 
Preconstruction planning continued. Fiscal year 
cost was $35,010. 
Condition at end of fiscal year. Contract plans 
and specifications are essentially complete. 
39. OOLOGAH LAKE, VERDIGRIS 
RIVER BASIN, OKLA. 
Location. On Verdigris River about 10 miles 
northwest of Claremore, Rogers County, Okla., 
and about 2 miles southeast of Oologah, Rogers 
County, Okla. (See Geological Survey maps for 
Claremore and Nowata, Okla., quadrangles, 
scale 1:125,000.) 
Existing project. For description of completed 
improvement, see Annual Report for 1972. 
Oologah Lake is a unit of the McClellan-Kerr 
Arkansas River Navigation System and a unit for 
flood control in the Verdigris River Basin. Estimated 
cost is $46,672,596. (See table 19-B for 
authorizing legislation.) 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Routine 
operation and maintenance continued. A total of 
8,750 acre-feet of water was released from the 
lake for water supply. Six noteworthy rises occurred 
above the lake. Flooding was prevented on 
an average of 7,000 acres of land. Estimated 
monetary benefits attributed to Oologah Lake 
operations for prevention of flood damages total 
$29,380,000 to June 30, 1975. (See table 19-F for 
pool elevations and storages during fiscal year.) 
Condition at end of fiscal year. After construction 
of right abutment access road, project was 
placed in standby status in October 1951. Construction 
was resumed in December 1955 and 
completed in May 1963 for initial development. 
Construction for utimate development was initiated 
July 1967. The project for ultimate 
development is complete. 
40. OPTIMA LAKE, NORTH CANADIAN 
RIVER BASIN, OKLA. 
Location. On North Canadian River, river mile 
623.2, about 4.5 miles northeast of Hardesty, Texas 
County, Okla. (See Geological Survey map for 
Optima Dam, Okla., quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 15,200 feet 
long and 120 feet high, with an uncontrolled 
19-16

TULSA, OKLA., DISTRICT 
spillway in a saddle on the right abutment. Outlet 
works will consist of a gated conduit, a 24-inch 
low-flow bypass, and a 24-inch water supply pipe. 
The lake will control a drainage area of 5,029 
square miles and provide for storage of 71,800 
acre-feet of water for flood control, 76,200 acrefeet 
for water supply, and 81,500 acre-feet for 
sedimentation reserve, for a total storage of 229,- 
500 acre-feet. Estimated cost is $41,800,000. (See 
table 19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, applies. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Land. 
acquisition $1,248,000; relocations $1,952,000; 
and dam $4,407,000. 
Condition at end of fiscal year. Construction 
began in March 1966 and the project is 61 percent 
complete. 
41. PAT MAYSE LAKE, RED RIVER 
BASIN, TEX. 
Location. On Sanders Creek, mile 4.6, a 
tributary of Red River, about 12 miles north of 
Paris, Lamar County, Tex. (See Geological Survey 
map for Grant, Tex., quadrangle, scale 1:62,- 
500 and Army Map Service map, Texarkana, 
Tex., scale 1:250,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see Annual 
Report for 1970. Estimated cost is $9,260,- 
000, of which $54,000 is Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Twelve noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 1,000 
acres of land. Estimated monetary benefits attributed 
to Pat Mayse Lake operations for 
prevention of flood damages total $1,840,000 to 
June 30, 1975. A total of 7,940 acre-feet was 
released for water supply to city of Paris, Tex. 
(See table 19-F for pool elevations and storages 
during fiscal year.) 
Condition at end of fiscal year. Construction 
began in March 1965 and project was placed in 
full flood control operation September 1967. Project 
is complete except for additional recreation 
facilities. 
42. PENSACOLA LAKE, GRAND 
(NEOSHO) RIVER BASIN, OKLA. 
Location. On Grand (Neosho) River, next to 
town of Disney, Mayes County, Okla. (See 
Geological Survey maps for Pryor, Wyandotte, 
and Vinita, Okla., and Siloam Springs, Ark., 
quadrangles, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 606 of Annual Report for 1969. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Flood control storage in project was operated by 
Grand River Dam Authority (an agency of State 
of Oklahoma) under direction of the Corps. Six 
noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 5,200 
acres of land. Estimated monetary benefits attributed 
to Pensacola Lake operations for prevention 
of flood damages total $28,618,000 to June 30, 
1975. (See table 19-F on pool elevations and 
storages during fiscal year.) 
Condition at end of fiscal year. Project is complete. 
43. PINE CREEK LAKE, LITTLE RIVER 
BASIN, OKLA. AND ARK. 
Location. On Little River, river mile 145.3, 
about 5 miles northwest of Wright City, McCurtain 
County, Okla. (See Geological Survey maps 
for Alikchi, Okla., quadrangle, scale 1:125,000; 
and Wright City and Pickens, Okla., quadrangles 
NE, NW, SE, and SW, scale 1:24,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see Annual 
Report for 1970. Estimated cost of project is 
$20,295,000. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. New 
work: All major construction complete. Routine 
operation and maintenance continued. Twelve 
noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 15,700 
acres of land. Estimated monetary benefits attributed 
to Pine Creek Lake operation for prevention 
of flood damages total $5,281,000 to June 30, 
1975. (See table 19-F for pool elevations and 
storages during fiscal year.) 
Condition at end of fiscal year. Construction 
began in February 1963 and the project was placed 
in useful operation in June 1969. Work remaining 
consists of recreation facilities. 
44. PROSPERITY LAKE, SPRING RIVER 
BASIN, MO. 
Location. On Center Creek, mile 18.0, Jasper 
County about 33 miles southwest of Carthage, Mo. 
19-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
(See Geological Survey map for Fidelity, Mo., 
quadrangle, scale 1:24,000.) 
Existing project. Provides for a rolled earth embankment 
section integral with a 152-foot gated 
concrete valley spillway and two concrete nonoverflow 
sections. Low-flow releases would be 
made through a low-flow pipe with multilevel inlets 
to the lake. The dam will be 3,700 feet in 
length and rise 80 feet above the streambed. The 
lake will control a drainage area of 207 square 
miles and provide 71,500 acre-feet of storage including 
42,000 acre-feet for flood control, 19,000 
acre-feet for water supply, and 10,500 acre-feet 
for sediment reserve. Prosperity Lake will be one 
unit in comprehensive plan for flood control, 
water supply, recreation, and fish and wildlife 
purposes in the Grand (Neosho) River Basin. Estimated 
cost of project is $30,000,000. (See table 
19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Section 221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
None. 
Condition at end of fiscal year. Funds have not 
been appropriated to initiate Phase I of 
preconstruction planning. 
45. RED RIVER BELOW DENISON DAM 
(TULSA DISTRICT) 
Location. On Red River and its tributaries 
below Denison Dam, in Oklahoma, Arkansas, 
Texas, and Louisiana. (See Geological Survey 
State maps and folio maps of Red River-1958 
edition.) 
Existing project. Provides for construction of 11 
flood control lakes in combination with existing 
or authorized Federal and non-Federal levee improvements, 
modified as required, and channel 
stabilization at locations where levee setbacks are 
impossible or uneconomical. (See table 19-G for 
water control projects included in general flood 
control plan for Red River below Denison Dam 
within Tulsa District.) Total estimated Federal 
cost in Tulsa District is $547,793,780 for construction, 
lands, and damages. (See table 19-B for 
authorizing legislation.) 
Local cooperation. See individual reports. 
46. SHIDLER LAKE, ARKANSAS RIVER 
BASIN, OKLA. 
Location. On Salt Creek, mile 39.2, a tributary 
of Arkansas River, about 1 mile east of Shidler, 
Osage County, Okla. (See Geological Survey map 
for Fairfax, Okla., quadrangle, scale 1:24,000.) 
Existing project. Provides for an earthfill dam 
3,000 feet long, with a maximum height of 106 
feet above streambed. An uncontrolled spillway 
300 feet wide will be east of dam. Outlet works 
will include an uncontrolled circular drop inlet 
with a conduit 8.25 feet in diameter. A 24-inch 
low-flow bypass and a 24-inch water supply line 
will be provided. A roadway will be located along 
crest of dam. The total lake capacity of 108,100 
acre-feet will be allocated, 49,900 acre-feet for 
flood control and 58,200 acre-feet for conservation, 
and will control runoff from 99 square miles. 
Shidler Lake will be operated as a unit of coordinated 
lake system for flood control in Arkansas 
River Basin. Estimated cost of the project is $19,- 
400,000. (See table 19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, as amended, 
and Section 221, Flood Control Act of 1970 apply. 
Operations and results during fiscal year. 
Engineering studies continued. 
Condition at end of fiscal year. Engineering 
studies continued. 
47. SKIATOOK LAKE, VERDIGRIS 
RIVER BASIN, OKLA. 
Location. On Hominy Creek, mile 14.3, a 
tributary of Bird Creek, in Verdigris River Basin 
about 5 miles west of Skiatook, Osage County, 
Okla. (See Geological Survey map for Avant, 
Okla., quadrangle, SE, scale 1:24,000 and Army 
Map Service map, Enid, Okla., scale 1:250,000.) 
Existing project. Provides for an earthfill dam 
3,590 feet long, 143 feet high with a crown width 
of 32 feet. The uncontrolled 100-foot spillway will 
be located in the right abutment. Outlet works 
will consist of a controlled intake structure, 8- by 
5-foot conduit, stilling basin, 2.5- by 5-foot lowflow 
conduit, and a 24-inch water supply pipe. 
The lake will provide a total storage of 513,500 
acre-feet (319,400 for conservation storage, 182,- 
300 for flood control, and 11,800 for sedimentation 
reserve), and will control a drainage area of 
354 square miles. Skiatook Lake will be operated 
as a unit of a seven-lake system for flood control in 
the Verdigris River tributaries in Oklahoma. Estimated 
cost of project is $63,800,000. (See table 
19-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of 1938, Water Supply Act of 1958, and Section 
221, Flood Control Act of 1970 apply. 
19-18

TULSA, OKLA., DISTRICT 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Lands 
and damages $1,393,000; roads, railroads, and 
bridges $97,000; project office buildings $280,- 
000; and relocations $626,000. 
Condition at end of fiscal year. Construction 
began in January 1974. The project is 10 percent 
complete. 
48. SPRING CREEK, SPRINGDALE, ARK. 
Location. On Spring Creek, a tributary of the 
Illinois River in the Arkansas River Basin. (See 
Geological Survey map for Fayetteville, Ark., 
quadrangle, scale 1:25,000.) 
Existing project. Flood protection for the urban 
areas of Springdale, Ark. Plan provides for approximately 
10,000 feet of improved channel, 
clearing and snagging, and alteration of the St. 
Louis and San Francisco Railway bridge. The 
project was approved for construction under the 
authority of Section 205 of the Flood Control Act 
of 1948, as amended. Federal cost is $1,000,000; 
non-Federal cost $1,036,000. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Major 
accomplishments with regular 
funds: Channel improvement, engineering and 
design, and supervision and administration $28,- 
741. 
Condition at end of fiscal year. Construction 
started in April 1973 and was completed in May 
1975. 
49. TORONTO LAKE, VERDIGRIS RIVER 
BASIN, KANS. 
Location. On Verdigris River about 271.5 miles 
above its mouth and 4 miles south and east of 
Toronto, Woodson County, Kans. (See Geological 
Survey map for Fredonia, Kans., quadrangle, 
scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
pages 600 and 601 of Annual Report for 1969. 
Federal cost was $13,894,000. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
During low-flow water periods, releases totaling 
942 acre-feet were made for water quality control. 
The city of Toronto, Kans., used 58 acre-feet 
of water from the lake. Eight noteworthy rises occurred 
above the lake. Flooding was prevented on 
an average of 5,600 acres of land. Estimated 
monetary benefits attributed to operation of 
Toronto Lake for prevention of flood damages 
total $17,347,000 to June 30, 1975. (See table 19-F 
for pool elevations and storages during fiscal 
year.) 
Condition at end of fiscal year. Construction 
began November 1954 and project placed in full 
operation March 1960. 
50. TURTLE CREEK, YUKON, OKLA. 
Location. Turtle Creek, tributary of North 
Canadian River, Yukon, Canadian County, Okla. 
(See Geological Survey maps for Richland, 
Bethany, Minco NE, and Mustang, Okla., 
quadrangles, scale 1:24,000.) 
Existing project. Plan of improvement is to 
provide approximately 23,000 feet of channel improvements 
for flood protection for the urban 
area of Yukon, Okla. The project was approved 
for construction under authority of Section 205 of 
the Flood Control Act of 1948. Estimated Federal 
cost is $2,000,000; non-Federal cost $1,905,000. 
Local cooperation. Section 3, Flood Control Act 
of 1936 and Section 221 of the Flood Control Act of 
1970 apply. 
Operations and results during fiscal year. 
Preconstruction planning continued. Fiscal year 
cost was $393. 
Condition at end of fiscal year. Contract plans 
and specifications have not started. 
51. WAURIKA LAKE, RED RIVER 
BASIN, OKLA. 
Location. Beaver Creek, mile 27.0, a tributary 
of Red River, about 6 miles northwest of Waurika, 
Jefferson County, Okla. (See Geological Survey 
map for Hastings, Okla.-Tex., quadrangle, scale 
1:62,500.) 
Existing project. Plan provides for an earthfill 
dam 16,500 feet long, including an uncontrolled 
spillway 200 feet long, and 106 feet above 
streambed. Outlet works will include a gated conduit 
13.5 feet in diameter, a 48-inch water supply 
pipe, and a 12-inch low-flow pipe. The lake will 
provide a total storage of 328,600 acre-feet (170,- 
200 for conservation storage, 117,000 for flood 
control, and 41,400 for sedimentation reserve), 
and will control a drainage area of 562 square 
miles. Waurika Lake will be operated as a unit of 
a coordinated lake system for flood control in Red 
River Basin. Estimated cost is $79,700,000. (See 
table 19-B for authorizing legislation.) 
19-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Section 2, Flood Control Act 
of 1938, and Water Supply Act of 1958, as amended, 
apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Lands 
and damages $2,240,000; embankment, spillway, 
and outlet works $2,404,000; and relocations $2,- 
047,000. 
Condition at end of fiscal year. Construction 
began in July 1971. The project is 31 percent complete. 
52. WINFIELD, KANS. 
Location. On Walnut River at Winfield, Cowley 
County, Kans. (See Geological Survey map, 
Burden, Kans., quadrangle, scale 1:24,000.) 
Existing project. Enlarge and extend existing 
levee to 23,050 feet long. Interior drainage will be 
provided through a 72-inch gated pipe. Estimated 
Federal cost is $690,000 and estimated 
non-Federal cost is $560,000. (See table 19-B for 
authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; maintain 
and operate completed works; perform all 
relocations, except railroad; and acquire fee title 
to lands for borrow and ponding purposes and 
flowage easements over lands for ponding only as 
may be required. 
Operations and results during fiscal year. 
Preconstruction planning was suspended. 
Condition at end of fiscal year. Phase I of the 
General Design Memo is 30 percent complete. 
53. WISTER LAKE, POTEAU RIVER 
BASIN, OKLA. 
Location. On Poteau River, river mile 60.9, 
about 2 miles south of Wister, Leflore County, 
Okla. (See Geological Survey map for Winding 
Stair, Okla., quadrangle, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 601 of Annual Report for 1969. Federal cost 
was $10,501,226. 
Local cooperation. Completed as required. 
Operations .and results during fiscal year. 
Routine operation and maintenance continued. 
Ten noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 14,300 
acres of land. Estimated monetary benefits attributed 
to Wister Lake operations for prevention 
of flood damages total $37,104,000 to June 30, 
1975. A total of 381 acre-feet of water was 
withdrawn from the lake by Heavener Utilities 
Authority. (See table 19-F for pool elevations and 
storages during fiscal year.) 
Condition at end of fiscal year. Construction 
began April 1946 and completed May 1949. Project 
placed in full flood control operation in October 
1949. 
54. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Semiannual inspection of completed local flood 
protection projects operated and maintained by 
local interests are made periodically to determine 
extent of compliance with approved regulations 
for operation and maintenance. (See table 19-H 
for inspection of local flood control projects.) 
Fiscal year cost was $31,708. Total cost to June 30, 
1975 was $332,477. 
55. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Flood Control Act of 1944 authorized the 
Secretary of War to prescribe regulations for use 
of storage allocated for flood control or navigation 
at all reservoirs constructed wholly or in part 
with Federal funds. Under the purview of this 
act, operation of the flood control storage included 
in reservoirs shown in table 19-I is prescribed 
by the Corps. Work accomplished consists of 
operating activities necessary in basin-wide coordination 
of functional scheduling of releases from 
reservoirs operated by other agencies and 
preparation of flood control operation and 
maintenance manuals for projects underway. 
Fiscal year cost from regular funds for 
maintenance was $106,906. 
56. OTHER AUTHORIZED 
CONTROL PROJECTS 
FLOOD 
See table 19-J. 
57. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Cong., as amended, 
(preauthorization). 
See table 19-K. 
Emergency flood control activities--repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal cost for fiscal year was $777,180, of 
which $39,626 was for advance preparation, 
$204,400 for flood emergency operations, and 
$533,154 for repair and restoration. 
19-20

TULSA, OKLA., DISTRICT 
Snagging and clearing of navigable streams and 
tributaries in interest offlood control (Section 208, 
Flood Control Act of 1954, Public Law 780, 83d 
Cong.) 
None. 
Emergency bank protection (Section 14, Flood 
Control Act of 1946, Public Law 526, 79th Cong.) 
Federal cost for fiscal year was $60,778 as 
follows: Arkansas River, Tulsa, Okla., $807; Caddo 
Creek, Carter County, Okla., $1,808; Hominy 
Creek Bridge, Osage, Okla., $7,233; Hominy 
Creek, Osage County Road, Okla., $6,120; State 
Highway 41 Bridge, Foreman, Ark., $1,170; 
Washita River, Carter County, Okla., $3,365; and 
Wildhorse Creek, Washita River, Okla., $40,275. 
Flood insurance activities (Section 1301-1377, 
Housing and Urban Development Act of 1968, 
Public Law 90-448, as amended.) 
In coordination with flood control activities, 10 
flood insurance studies were made in accordance 
with Interagency Agreement (IAA)H-2-73 at 
fiscal year cost of $80,523 under Housing and Urban 
Development reimbursable orders. 
Multiple-Purpose Projects 
Including Power 
58. BROKEN BOW LAKE, LITTLE RIVER 
BASIN, OKLA. AND ARK. 
Location. On Mountain Fork River, river fiile 
20.3, about 9 miles northeast of Broken Bow, Mc- 
Curtain County, Okla. (See Geological Survey 
maps for Broken Bow and Smithville, Okla., 
quadrangles, scale 1:62,500.) 
Existing project. For description of completed 
improvements and authorizing legislation see 
pages 19-17 and 19-26 of Annual Report for 1971. 
Estimated Federal cost is $41,283,000, of which 
$40,000 is Code 711 funds. 
Local cooperation. Section 2, Flood Control Act 
of 1938, and Water Supply Act of 1958, as amended, 
apply. 
Operations and results during fiscal year. Major 
accomplishments with regular funds: Lowflow 
outlet facility, water supply intake, and 
overlook area development was completed. Routine 
operation and maintenance continued. 
Eleven noteworthy rises occurred above the lake. 
Operation of the lake prevented downstream 
flooding on an average of 9,500 acres of land. Estimated 
monetary benefits attributed to Broken 
Bow Lake operations for prevention of flood 
damages total $6,312,000 to June 30, 1975. During 
low-flow water periods, releases totaling 
4,344 acre-feet were made to supplement water 
for a State park and other uses. Delivered 25,549,- 
100 kilowatt-hours of electric energy to 
Southwestern Power Administration for distribution 
and sale, and released 1,420,552 acrefeet 
of water through turbines. (See table 19-F for 
pool elevations and storages during fiscal year.) 
Condition at end of fiscal year. Construction 
began in November 1961 and project placed in 
useful operation in October 1968. Power units 1 
and 2 were placed in operation in January and 
June 1970, respectively. Work remaining consists 
of additional recreation facilities. 
59. DENISON DAM-LAKE TEXOMA, 
RED RIVER BASIN, TEX. AND OKLA. 
Location. On Red River, river mile 725.9, about 
5 miles northwest of Denison, Tex. (See 
Geological Survey maps for Denison, Tex., and 
Tishomingo, Okla., quadrangles, scale 1:125,000; 
and Denison Dam and Gordonville, Tex., 
quadrangles, scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 603 of Annual Report for 1969. Hydroelectric 
development consists of two units having an 
installed capacity of 70,000 kilowatts. Ultimate 
installation planned is for five units with a total of 
175,000 kilowatts. Lake Texoma operated as a 
unit of a coordinated lake system for flood control 
in the Red River Basin. Estimated costs are 
shown on table 19-L. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Additional recreation facilities were constructed. 
Estimated monetary benefits attributed to 
Denison Dam-Lake Texoma operation for 
prevention of flood damages downstream to 
Fulton, Ark., total $35,528,000 to June 30, 1975. 
(See table 19-F for pool elevations and storages 
during fiscal year.) A total of 1,603 acre-feet was 
made available for water supply to the city of 
Denison, Tex., and Red River Authority of Texas. 
Delivered 393,143,000 kilowatt-hours of electric 
energy to Southwestern Power Administration 
for distribution and sale, and released 4,213,640 
acre-feet of water through turbines. 
Condition at end of fiscal year. Construction 
was started in August 1939 and was completed 
for the dam, spillway, and outlet works in 
February 1944. Impoundment of power pool 
began January 1944 and commercial power 
generation was started March 1945 with first 
19-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
unit operating. Authorized work is complete except 
for additional recreation facilities, installation 
of third power unit, and additional perimeter 
access roads. 
60. EUFAULA LAKE, CANADIAN RIVER 
BASIN, OKLA. 
Location. On Canadian River about 12 miles 
east of Eufaula, McIntosh County, Okla. (See 
Geological Survey maps for Okmulgee, Canadian, 
McAlester, and Sans Bois, Okla., 
quadrangles, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see Annual 
Report for 1970. Estimated Federal cost is 
$122,223,000, of which $971,000 is Code 711 
funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Construction of additional recreation facilities 
continued. Four noteworthy rises occurred above 
the lake. Flooding was prevented on an average of 
14,800 acres of land. A total of 1,201 acre-feet of 
water was released to Pittsburg and Haskell 
County Water Authorities and the State Board of 
Affairs. Estimated monetary benefits attributed 
to Eufaula Lake operations for prevention of flood 
damages total $21,787,000 to June 30, 1975. (See 
table 19-F for pool elevations and storages during 
fiscal year.) Delivered 465,320,800 kilowatthours 
of electric energy to Southwestern Power 
Administration for distribution and sale, and 
released 5,595,413 acre-feet of water through turbines. 
Condition at end of fiscal year. Construction 
began in December 1956 and project placed in 
full flood control operation in February 1964. 
Project is complete except for additional recreation 
facilities. Commercial power was generated 
on unit 1 July 1964, on unit 2 September 1964, and 
on unit 3 August 1964. 
61. FORT GIBSON LAKE, GRAND 
(NEOSHO) RIVER BASIN, OKLA. 
Location. On Grand (Neosho) River about 5 
miles north and east of Fort Gibson, Muskogee 
County, Okla. (See Geological Survey maps for 
Muskogee and Pryor, Okla., quadrangles, scale 
1:125,000; and Wagoner, Okla., quadrangle, scale 
1:62,500.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 604 of Annual Report for 1969. Estimated 
Federal cost is $55,212,000, of which $1,397,000 is 
Code 711 funds and $12,400,000 is for addition of 
power units 5 and 6. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Construction of additional recreation facilities 
continued. Six noteworthy rises occurred above 
the lake. Flooding was prevented on an average of 
5,000 acres of land. Estimated monetary benefits 
attributed to Fort Gibson Lake operations for 
prevention of flood damages total $21,939,000 to 
June 30, 1975. (See table 19-F for pool elevations 
and storages during fiscal year.) Delivered 328,- 
840,200 kilowatt-hours of electric energy to 
Southwestern Power Administration for distribution 
and sale, and released 6,048,305 acrefeet 
of water through turbines. 
Condition at end of fiscal year. Construction 
began in March 1942 with construction of temporary 
field office buildings, but further construction 
at project was held in abeyance during 
World War II. Construction of concrete dam and 
spillway, largest single feature of project, started 
in May 1946 and was completed in June 1950. 
Fourth generator installed and project placed in 
full operation in September 1953. Project is complete 
except for additional recreation facilities. 
62. KEYSTONE LAKE, ARKANSAS 
RIVER BASIN, OKLA. 
Location. On Arkansas River near Sand 
Springs, Okla., and about 15 miles west of Tulsa, 
Okla. (See Geological Survey map for Hominy, 
Okla., quadrangle, scale 1:125,000; Skedee and 
Yale, Okla., quadrangles, scale 1:62,500; and 
Keystone Dam, quadrangle, scale 1:24,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see Annual 
Report for 1970. Estimated cost is $123,840,- 
000, of which $1,216,000 is Code 711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Additional recreation facilities were constructed. 
Delivered 463,108,900 kilowatt-hours of electric 
energy to Southwestern Power Administration 
for distribution and sale, and released 6,239,158 
acre-feet of water through turbines. Six 
19-22

TULSA, OKLA., DISTRICT 
noteworthy rises occurred above the lake. 
Flooding was prevented on an average of 10,700 
acres of land. A total of 196 acre-feet of water was 
withdrawn by Gulf Oil Corp. Estimated 
monetary benefits attributed to operation of 
Keystone Lake for prevention of flood damages 
total $76,342,000 to June 30, 1975. (See table 19-F 
for pool elevations and storages during fiscal 
year.) 
Condition at end of fiscal year. Construction 
began in January 1957 and the project placed in 
flood control operation in September 1964. No. 1 
generating unit became operational on May 21, 
1968 and No.2 on May 2, 1968. Project is complete 
except for additional recreation facilities. 
63. MARKHAM FERRY RESERVOIR, 
GRAND (NEOSHO) RIVER BASIN, 
OKLA. 
Location. On Grand (Neosho) River, about 8 
miles southeast of city of Pryor, Mayes County, 
Okla. (See Geological Survey maps for Pryor and 
Vinita, Okla., quadrangles, scale 1:125,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 605 of Annual Report for 1969. Cost was $6,- 
908,756. 
Local cooperation. None required. 
Operations and results during fiscal year. Six 
noteworthy rises occurred above the reservoir. 
Flooding was prevented on an average of 2,100 
acres of land. Estimated monetary benefits attributed 
to the operation of Markham Ferry 
Reservoir for flood damage prevention total $3,- 
200,000 to June 30, 1975. (See table 19-F for pool 
elevations and storages during fiscal year.) 
Condition at end of fiscal year. Federal participation 
in project is complete. 
64. ROBERT S. KERR LOCK AND DAM 
AND RESERVOIR, ARKANSAS 
RIVER BASIN, OKLA. 
Location. On Arkansas River at navigation 
mile 336.2, about 8 miles south of Sallisaw, 
Leflore County, Okla. (See Geological Survey 
maps for Robert S. Kerr Dam, Keota, Vian, 
Sallisaw, Stigler NE, and Webbers Falls, Okla., 
quadrangles, scale 1:24,000 and Army Map Service 
map, Fort Smith, Ark., scale 1:250,000.) 
Existing project. For description of completed 
improvement and authorizing legislation see Annual 
Report for 1972. Robert S. Kerr Lock and 
Dam and Reservoir is a unit of the McClellan- 
Kerr Arkansas River Navigation System. Estimated 
cost is $93,327,000. 
Local cooperation. See section 1 of this report. 
Terminal facilities. Docks for loading coal, 
built by Garland Coal and Mining Company and 
Sierra Coal Corp., provide facilities adequate for 
present traffic. 
Operations and results during fiscal year. New 
work: All major construction complete. Routine 
operation and maintenance continued. Delivered 
884,538,600 kilowatt-hours of electric energy to 
Southwestern Power Administration for distribution 
and sale, and released 25,054,640 acrefeet 
of water through turbines. 
Condition at end of fiscal year. Construction 
began in April 1964 and the project placed in full 
flood control operation in October 1970. Lock and 
dam became operational for navigation in 
December 1970. Power units 1, 2, 3, and 4 were 
placed in operation in October, July, September, 
and November 1971, respectively. Work remaining 
consists of public-use facilities at the damsite. 
65. TENKILLER FERRY LAKE, 
ILLINOIS RIVER BASIN, OKLA. 
Location. On Illinois River about 7 miles 
northwest of Vian and 7 miles northeast of Gore, 
Sequoyah County, Okla. (See Geological Survey 
maps for Muskogee and Tahlequah, Okla., and 
Ark., quadrangles, scale 1:125,000; and Webbers 
Falls, Okla., quadrangle, scale 1:62,500.) 
Existing project. For description of completed 
improvement and authorizing legislation see 
page 607 of Annual Report for 1969. Estimated 
cost is $23,932,000, of which $1,094,000 is Code 
711 funds. 
Local cooperation. Completed as required. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Additional recreation facilities were constructed. 
Four noteworthy rises occurred above the lake. 
Operation of the lake prevented downstream 
flooding on an average of 3,600 acres of land. Estimated 
monetary benefits attributed to 
Tenkiller Lake operations for prevention of flood 
damages total $7,868,000 to June 30, 1975. (See 
19-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
table 19-F for pool elevations and storages during 
fiscal year.) Delivered 215,463,100 kilowatthours 
of electric energy to Southwestern Power 
Administration for distribution and sale, and 
released 1,569,522 acre-feet of water through turbines. 
Released 2,501 acre-feet of water to Kerr- 
McGee Corp. 
Condition at end of fiscal year. Construction 
began in June 1947 and completed in July 1953. 
Commercial sale of power started November 
1953, with unit 2. Unit 1 installed December 
1953. Work required to complete project consists 
of additional recreation facilities. Work on repair 
and extension of spillway apron began in July 
1960 and was completed in August 1961. 
66. WEBBERS FALLS LOCK AND DAM, 
ARKANSAS RIVER BASIN, OKLA. 
Location. On Arkansas River at navigation 
mile 368.8, about 5 miles northwest of Webbers 
Falls, Muskogee County, Okla. (See Geological 
Survey maps for Webbers Falls, Keefeton, and 
Wagoner, Okla., quadrangles, scale 1:62,500 and 
Army Map Service map, Fort Smith, Ark., scale 
1:250,000.) 
Existing project. An earthfill dam, powerplant, 
navigation lock, and appurtenant facilities, with 
a slackwater pool 37 miles long extending to 
Chouteau Lock and Dam on the Verdigris River. 
Structure is 4,370 feet long and 84 feet high and 
includes a gated concrete spillway, concrete nonoverflow 
and power intake section, and a lock 
flanked by earth embankments. Spillway has 
twelve 50- by 41-foot radial-type gates. Navigation 
lock is 110 feet wide and 600 feet long with a 
normal lift of 30 feet. The normal pool elevation is 
490 feet mean sea level. Hydroelectric development 
consists of three generating units with an 
installed capacity of 60,000 kilowatts. Delivered 
409,045,500 kilowatt-hours of electric energy to 
Southwestern Power Administration for distribution 
and sale, and released 17,812,561 acrefeet 
of water through turbines. Project is a unit of 
the McClellan-Kerr Arkansas River Navigation 
System. Estimated cost is $83,300,000. (See table 
19-B for authorizing legislation.) 
Local cooperation. See section 1 of this report. 
Terminal facilities. Cargo pier, mooring 
dolphins, warehouse, terminal building, and fuel 
facility built by Muskogee City-County Port 
Authority; liquid cargo loading facility and steel 
unloading facility built by Frontier Steel Company, 
provide facilities adequate for present traffic. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
Condition at end of fiscal year. Construction 
began in January 1965, and the project was placed 
in useful operation in November 1970. Lock 
and dam became operational for navigation in 
December 1970. Power units 1, 2, and 3 were placed 
in operation in August, November, and 
December 1973, respectively. The project is 99 
percent complete. 
General Investigations 
67. SURVEYS 
Fiscal year cost was $982,590, of which $263,- 
259 was for navigation, $610,544 for flood control, 
$45,967 for coordination with other agencies, 
$24,970 for comprehensive studies, $32,386 for 
review of authorized projects, $4,475 for inventory 
of dams, and $989 for deauthorization 
reviews. 
68. COLLECTION AND STUDY OF BASIC 
DATA 
Fiscal year cost was $187,994 for flood plain information 
studies. (See table 19-M for completed 
flood plain information reports.) 
69. RESEARCH AND DEVELOPMENT 
Fiscal year cost was $6,855 for hydrologic 
studies. 
19-24

TULSA, OKLA., DISTRICT 
TABLE 19-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June30,1975 
2. Bank Stabilization 
& Channel Rectification, 
Arkansas River, 
Ark. & Okla. 
3. Low Head Locks 
& Dams, Okla. 
(Federal Funds) 
Contributed 
Funds) 
7. Arcadia Lake, 
Deep Fork River 
Basin, Okla. 
8A. Experimental 
Chloride Control 
Project, Red River 
Basin, Tex. 
8B. Ark-Red Basins 
Chloride Control, 
Supplemental 
Studies, Okla. 
8C. Ark-Red Basins 
Chloride Control, 
Tex. 
9. Big Hill Lake, 
Verdigris River 
Basin, Kans. 
10. Big Pine Lake, 
Red River Basin, 
Tex. 
11. Birch Lake, 
Verdigris River 
Basin, Okla. 
12. Candy Lake, 
Verdigris River 
Basin, Okla. 
13. Canton Lake, 
Arkansas River 
Basin, Okla. 
14. Cedar Point Lake 
Grand (Neosho) River 
Basin, Kans. 
15. Clayton Lake, 
Little River 
Basin, Okla. 
16. Copan Lake, 
Verdigris River 
Basin, Okla. 
New Work 
Approp. $ - $ - $ - $ - $ 12,700,038 
Cost - - - - 12,700,038 
Maint. 
Approp. - - - - 2,689,734 
Cost - - - - 2,689,734 
New Work 
Approp. 1,749,700 2,603,000 1,673,000 299,000 118,008,387 
Cost 2,269,369 1,901,553 1,456,374 1,076,263 117,445,581 
Maint. 
Approp. 2,540,100 3,221,200 3,146,300 3,054,800 13,240,964 
Cost 2,648,392 2,300,598 4,157,001 2,899,304 12,705,119 
New Work 
Contrib. - - - - 119,330 
Cost - - - - 119,330 
New Work 
Approp. 139,000 177,600 180,000 185,000 681,600 
Cost 27,519 220,426 168,448 221,732 638,125 
New Work 
Approp. - - - - 300,028 
Cost - - - - 300,028 
Maint. 
Approp. -2,854 14,400 4,455 6,816 62,947 
Cost 5,766 6,497 7,727 6,736 54,948 
New Work 
Approp. 410,000 -30,000 34,200 -5 2,863,895 
Cost 278,583 11,860 246,864 687 2,863,896 
New Work 
Approp. 377,900 116,500 1,314,800 1,435,005 4,369,205 
Cost 333,731 134,813 1,058,855 1,434,835 4,064,026 
Maint. 
Approp. 443,871 466,500 767,178 463,126 2,243,675 
Cost 416,964 464,964 336,182 495,848 1,816,000 
New Work 
Approp. 453,800 385,000 400,100 337,000 1,867,166 
Cost 151,047 140,446 539,128 709,932 1,831,819 
New Work 
Approp. 124,300 152,000 130,000 267,000 673,300 
Cost 48,735 226,750 128,071 246,879 650,435 
New Work 
Approp. 216,000 850,000 1,225,000 2,950,000 5,544,170 
Cost 214,275 701,948 843,385 2,700,212 4,762,990 
New Work 
Approp. 5,000 - 139,000 5,000 530,004 
Cost 8,459 80 112,365 31,396 529,754 
New Work 
Approp. -2,000 2,000 1 - 10,666,171 
Cost 7,281 18,408 1,611 - 10,666,171 
Maint. 
Approp. 270,000 256,051 784,057 619,698 5,015,271 
Cost 243,628 277,661 740,051 588,948 4,922,489 
Major rehab. 
Approp. - - - - 291,106 
Cost - - - - 291,106 
New Work 
Approp. 230,900 54,700 170,000 140,000 700,600 
Cost 61,638 204,338 132,809 188,436 658,309 
New Work 
Approp. 313,800 150,000 1,240,000 647,000 2,919,300 
Cost 221,555 148,475 708,299 1,282,073 2,903,920 
New Work 
Approp. 996,100 980,063 2,026,000 3,915,000 9,240,999 
Cost 384,132 1,457,152 2,635,031 3,021,337 8,255,78? 
19-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 19-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30,1975 
17. Council Grove 
Lake, Grand 
(Neosho) River 
Basin, Kans. 
18. DeQueen Lake, 
Little River 
Basin, Ark. 
19. Dierks Lake, 
Little River 
Basin, Ark. 
20. El Dorado Lake, 
Walnut River 
Basin, Kans. 
21. El Dorado, Kans. 
22. Elk City Lake, 
Verdigris River 
Basin, Kans. 
23. Fall River Lake, 
Verdigris River 
Basin, Kans. 
24. Flat Rock Creek, 
Tulsa, Okla. 
25. Fort Supply Lake, 
North Canadian 
River Basin, 
Okla. 
26. Gillham Lake, 
Little River 
Basin, Ark. 
27. Great Salt Plains 
Lake, Arkansas 
River Basin, 
Okla. 
28. Heyburn Lake, 
Arkansas River 
Basin, Okla. 
29. Hugo Lake, Kiamichi 
River Basin, Okla. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
13,600 42,000 2,104 - 11,573,608 
16,446 55,945 20,313 - 11,573,608 
196,000 335,708 389,101 299,144 2,319,245 
201,212 219,650 467,698 340,337 2,305,254 
1,715,800 2,206,853 2,738,600 1,783,000 14,486,853 
963,980 1,473,046 2,445,298 2,192,126 13,090,737 
4,337,700 3,800,000 1,550,000 605,000 14,969,623 
4,133,411 3,093,665 1,833,675 1,137,008 14,859,492 
- - - 8,606 8,606 
- - - 6,799 6,799 
-409,790 1,467,139 2,629,200 4,418,000 9,492,3491 
139,940 744,206 3,033,080 4,186,895 8,834,337 
- - 28,900 40,000 68,900 1 
- - 24,760 42,428 67,187 
- - - - 19,042,990 
- - -19 - 19,042,990 
211,990 279,720 256,045 222,829 1,870,386 
227,157 197,330 331,317 218,475 1,854,704 
- 10,000 -19 - 10,504,393 
- - 9,980 - 10,494,393 
139,000 202,253 249,902 195,694 2,806,117 
115,067 170,992 297,395 192,883 2,795,331 
234,600 500,000 148,332 - 1,000,000 
36,554 21,123 536,565 295,449 998,599 
- 2,500 -97 - 7,595,225 
- 1,721 683 - 7,595,225 
182,300 169,253 206,145 150,093 2,964,008 
171,492 162,015 197,762 173,808 2,956,301 
276,400 1,603,511 2,530,000 1,950,000 16,115,011 
229,602 664,808 3,173,845 1,350,048 15,141,902 
- - - 5,000 5,000 
- - - 3,448 3,448 
- - - - 4,626,270 
- - - - 4,626,270 
107,300 106,725 136,122 124,481 2,155,326 
104,036 114,138 133,054 123,915 2,148,754 
-4,600 - -39 - 2,502,694 
25,741 406 395 - 2,502,694 
140,210 149,675 156,093 163,274 1,987,101 
128,652 145,645 161,789 171,336 1,981,731 
8,151,600 4,150,000 4,600,000 805,000 34,980,571 
7,016,886 3,750,381 3,172,892 2,772,946 33,943,169 
- - 115,535 350,253 465,788 
- - 105,006 313,782 418,788 
19-26

TULSA, OKLA., DISTRICT 
TABLE 19-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30,1975 
30. Hulah Lake, 
Verdigris River 
Basin, Okla. 
31. John Redmond Dam & 
Reservoir, Grand 
(Neosho) River 
Basin, Kans. 
32. Kaw Lake, Arkansas 
River Basin, Okla. 
33. Lake Kemp, Wichita 
River Basin, Tex. 
34. Lukfata Lake, 
Little River Basin, 
Okla. & Ark. 
35. Marion, Kans. 
36. Marion Lake, Grand 
(Neosho) River 
Basin,Kans. 
37. Millwood Lake, 
Little River 
Basin, Ark. 
39. Oologah Lake, 
Verdigris River 
Basin, Okla. 
40. Optima Lake, North 
Canadian River 
Basin, Okla. 
41. Pat Mayse Lake, 
Red River Basin, 
Tex. 
42. Pensacola Lake, 
Grand (Neosho) 
River Basin, 
Okla. 
43. Pine Creek Lake, 
Little River Basin, 
Okla. & Ark. 
46. Shidler Lake, 
Arkansas River 
Basin, Okla. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
1 - - - 11,166,477 
293 - - - 11,166,477 
220,800 266,948 272,224 221,300 3,275,362 
207,557 222,257 270,436 266,989 3,249,160 
- - - - 135,718 
- - - - 135,718 
30,000 56,000 673 - 28,099,537 
27,140 45,771 14,128 - 28,099,537 
247,300 340,973 492,602 374,358 2,810,139 
265,226 303,271 508,350 375,434 2,772,901 
13,267,500 24,385,000 21,900,000 11,190,000 93,699,350 
12,966,830 22,270,124 18,559,072 14,846,037 91,115,781 
3,475,600 1,364,000 -125,408 8,000 7,633,280 
2,871,071 1,601,557 253,242 6,811 7,629,818 
- 45,259 87,843 93,651 226,753 
- 45,259 85,071 95,532 225,862 
51,950 150,000 300,000 65,000 1,180,985 
114,062 103,756 145,629 218,631 1,176,576 
49,700 102,400 62,100 178,000 392,200 
15,537 134,837 63,807 92,310 306,509 
- - - - 13,317,538 
- - - - 13,217,538 
324,500 277,871 418,427 451,758 2,750,240 
320,882 275,938 406,270 460,066 2,190,913 
170,400 340,000 128,892 347,420 45,222,594 
61,485 359,367 125,946 104,956 44,886,634 
733,800 788,951 942,225 725,954 4,403,646 
718,125 584,220 1,146,526 764,921 4,348,020 
568,524 1,461,000 0 25,000 46,682,6022 
793,210 848,122 505,303 176,733 46,672,596 
467,800 473,329 531,004 564,946 4,522,797 
430,618 434,280 588,036 548,889 4,467,457 
1,545,300 2,013,464 4,150,000 8,850,000 23,266,438 
1,654,196 1,743,428 4,363,561 8,344,256 22,593,897 
-1,532 8,000 477 - 9,214,905 
10,123 4,188 4,289 - 9,214,905 
213,300 192,793 269,167 226,320 1,539,392 
178,185 217,339 282,476 248,216 1,531,932 
- - - - 52,126 
- - - - 52,126 
6,937 3,250 3,654 4,876 172,316 
8,518 1,715 5,039 5,026 172,316 
- 25,000 9,732 6,000 20,301,412 
107,273 131,464 140,116 15,253 20,301,396 
235,200 264,542 307,287 293,123 1,517,867 
205,974 243,817 336,878 271,904 1,468,160 
5,000 116,800 50,000 29,100 533,196 
1,659 46,705 123,248 29,038 532,946 
19-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 19-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30,1975 
47. Skiatook Lake, 
Verdigris River 
Basin, Okla. 
48. Spring Creek, 
Springdale, Ark. 
49. Toronto Lake, 
Verdigris River 
Basin, Kans. 
51. Waurika Lake, Red 
River Basin, Okla. 
52. Winfield, Kans. 
53. Wister Lake, 
Poteau River 
Basin, Okla. 
58. Broken Bow Lake, 
Little River Basin, 
Okla. & Ark. 
59. Denison Dam-Lake 
Texoma, Red River 
Basin, Tex. & Okla. 
60. Eufaula Lake, 
Canadian River 
Basin, Okla. 
61. Fort Gibson Lake, 
Grand (Neosho) 
River Basin, 
Okla. 
62. Keystone Lake, 
Arkansas River 
Basin, Okla. 
64. Robert S. Kerr Lock 
& Dam & Reservoir, 
Arkansas River 
Basin, Okla. 
65. Tenkiller Ferry 
Lake, Illinois 
River Basin, Okla. 
New Work 
Approp. 32,500 225,000 1,948,000 4,200,000 7,087,482 
Cost 3,724 89,211 1,955,983 2,766,168 5,447,958 
New Work 3 
Approp. - 460 0 - 1,000,000 
Cost 3,032 98,885 635,051 28,741 1,000,000 
New Work 
Approp. - - - - 13,894,002 
Cost - - - - 13,894,002 
Maint. 
Approp. 168,200 138,155 134,223 135,934 1,756,276 
Cost 159,000 148,046 124,967 140,793 1,750,738 
New Work 
Approp. 641,640 4,975,970 7,400,000 8,840,000 23,794,750 
Cost 1,110,103 1,947,415 8,884,797 7,465,865 20,837,090 
New Work 
Approp. - - 28,000 48,900 76,900 
Cost - - 23,194 53,039 76,233 
New Work 
Approp. - - - - 10,501,226 
Cost - - - - 10,501,226 
Maint. 
Approp. 262,300 228,045 209,898 192,817 3,333,787 
Cost 281,032 232,788 233,880 193,822 3,328,410 
New Work 
Approp. 32,073 45,000 - - 41,243,105 
Cost 590,983 253,457 2,180 2,339 41,222,431 
Maint. 
Approp. 411,600 392,087 419,322 495,962 2,460,660 
Cost 410,786 394,578 417,685 478,876 2,435,214 
New Work 
Approp. -1 107,500 -5,956 475,000 68,263,9654 
Cost 80,372 125,167 23,759 298 67,789,263 
Maint. 
Approp. 1,447,300 1,562,048 1,892,495 1,676,681 23,129,967 
Cost 1,473,783 1,479,370 1,962,241 1,792,700 23,060,914 
Minor rehab. 
Approp. - - - - ' 46,237 
Cost - - - - 46,237 
New Work 
Approp. 731 76,500 - -920 121,479,9955 
Cost 3,161 12,928 60,464 2,187 121,479,994 
Maint. 
Approp. 1,205,000 1,300,022 1,370,480 1,590,564 11,866,078 
Cost 1,201,876 1,190,483 1,491,292 1,527,108 11,739,820 
New Work 6 
Approp. 79,000 1,500 -613 - 42,410,365 
Cost 51,953 64,547 1,262 - 42,410,365 
Maint. 
Approp. 904,800 1,004,117 948,902 1,115,562 13,071,638 
Cost 859,628 963,448 1,052,601 1,091,844 13,023,162 
New Work 
Approp. 64,840 272,947 4,003 5,000 123,094,367 
Cost 85,116 150,922 111,094 11,568 123,100,842 
Maint. 
Approp. 955,500 1,173,190 1,023,516 1,171,458 8,743,743 
Cost 918,056 987,762 1,173,018 1,218,986 8,675,891 
New Work 
Approp. 928,001 90,000 37,500 - 93,327,050 
Cost 1,212,853 128,549 163,155 20,220 93,270,658 
Maint. 
Approp. 1,874,200 2,226,081 1,737,692 1,411,227 7,732,700 
Cost 1,576,957 1,531,813 2,627,031 1,449,434 7,651,834 
New Work 
Approp. -8,231 85,500 -1,958 65,000 23,664,8058 
Cost 15,317 27,084 57,004 15 23,599,820 
Maint. 
Approp. 622,400 612,459 634,654 779,104 8,587,288 
Cost 625,854 613,365 650,977 777,715 8,562,954 
19-28

TULSA, OKLA., DISTRICT 
TABLE 19-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30,1975 
66. Webbers Falls Lock New Work 
& Dam, Arkansas Approp. 7,192,100 6,392,000 1,146,008 1,443,000 83,634,877 
River Basin, Okla. Cost 7,539,999 5,009,531 2,655,606 1,385,077 83,305,127 
Maint. 
Approp. 1,008,663 974,797 1,583,839 1,502,642 5,377,241 
Cost 682,955 1,175,241 1,296,447 1,904,511 5,332,481 
1. Excludes $850,000 contributed funds. 5. Excludes $299,803 contributed funds and $13,211,728 
2. Excludes $81,460 contributed funds and $1,348,816 special funds. 
special funds. 6. Excludes $134,919 contributed funds. Includes $49,581 
3. Excludes $161,000 contributed funds. Public Works acceleration funds. 
4. Includes $433,539 Emergency Relief funds. Excludes- 7. Excludes $5,366,231 special funds. 
S$1,256,068 from special contributed funds. 8. Excludes $946 contributed funds. Includes $39,999 
Public Works acceleration funds. 
19-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 19-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
December 31, 1970 
October 23, 1962 
November 7, 1966 
December 31, 1970 
March 7, 1974 
October 23, 1962 
October 23, 1962 
October 23, 1962 
October 23, 1962 
May 17, 1950 
October 23, 1962 
October 27, 1965 
October 23, 1962 
October 23, 1962 
July 24, 1946 
ARCADIA LAKE, OKLA. (See Section 7 of Text) 
Construction of reservoir for flood control, water supply, 
water quality control, and recreation purposes. 
ARKANSAS-RED RIVER BASINS WATER QUALITY 
CONTROL, TEX., OKLA., AND KANS. 
(See Section 8 of Text) 
Construction of experimental water quality study projects 
near Estelline and Guthrie, Tex. 
Project for water quality control, designated as Part I. 
Project for water quality control, designated as Part II. 
Modify 1966 and 1970 Acts-Initiated construction of Area 
VIII features of the project consisting of low flow dam, 
pumping station and pipeline, and brine dam. 
BIG HILL LAKE, KANS. (See Section 9 of Text) 
Construction of reservoir for flood control, water supply, 
and recreation purposes. 
BIG PINE LAKE, OKLA. (See Section 10 of Text) 
Construction of reservoir for flood control, water supply, 
recreation, and fish and wildlife purposes. 
BIRCH LAKE, OKLA. (See Section 11 of Text) 
Construction of reservoir for flood control, water supply, 
water quality control, recreation, and fish and wildlife 
purposes. 
CANDY LAKE, OKLA. (See Section 12 of Text) 
Construction of reservoir for flood control, water supply, 
water quality control, recreation, and fish and wildlife 
purposes. 
CEDAR POINT LAKE, KANS. (See Section 14 of Text) 
Construction of reservoir for flood control and 
conservation purposes. 
COPAN LAKE, OKLA. (See Section 16 of Text) 
Construction of reservoir for flood control water supply, 
water quality control, recreation, and fish and wildlife 
purposes. 
EL DORADO LAKE, KANS. (See Section 20 of Text) 
Construction of reservoir to provide flood control and 
conservation purposes. 
KAW LAKE, OKLA. (See Section 32 of Text) 
Construction of dam and appurtenant facilities. 
LAKE KEMP, TEX. (See Section 33 of Text) 
Reconstruct and expand existing non-Federal reservoir. 
LOW HEAD LOCKS & DAMS (See Section 3 of Text) 
Construction of three lock & dam units, including turning 
basin, channel cutoffs and enlargement to provide a 
navigable channel 9 feet deep with a minimum width of 250 
feet from Ft. Smith, Ark., to vicinity of Catoosa, Okla. 
H. Doc. 299, 91st Cong., 
2d sess. 
S. Doc. 105, 87th Cong., 
2d sess. 
S. Doc. 110, 89th Cong., 
2d sess. 
Chief of Engineers Report, 
May 6, 1970 
PL 91-611 
PL 93-251 
H. Doc. 572, 87th Cong., 
2d sess. 
H. Doc. 71, 88th Cong., 
1st sess. 
H. Doc. 563, 87th Cong., 
2d sess. 
H. Doc. 563, 87th Cong., 
2d sess. 
H. Doc. 442, 80th Cong., 
2d sess. 
H. Doc. 563, 87th Cong., 
2d sess. 
H. Doc. 232, 89th Cong., 
1st sess. 
S. Doc. 143, 87th Cong., 
2d sess. 
S. Doc. 144, 87th Cong., 
2d sess. 
H. Doc. 758, 79th Cong., 
2d sess. 
19-30

TULSA, OKLA., DISTRICT 
TABLE 19-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
December 12, 1970 
July 24, 1946 
July 28, 1938 
July 24, 1946 
March 7, 1974 
June 22, 1936 
March 7, 1974 
July 24, 1946 
August 3, 1955 
July 3, 1958 
October 23, 1962 
August 13, 1968 
October 27, 1965 
October 23, 1962 
December 30, 1963 
July 24, 1946 
December 31, 1970 
October 27, 1965 
MARION, KANS. (See Section 35 of Text) 
Local protection works for flood control: diversion channel, 
levee and appurtenant structures. 
MAINTENANCE & REPAIR FLEET & MARINE 
TERMINALS (See Section 4 of Text) 
Wharf, office and storage building, storage space, and 
operating areas for floating maintenance and repair fleet. 
OOLOGAH LAKE, OKLA. (See Section 39 of Text) 
Construction of reservoir for flood control, navigation, and 
water supply purposes. 
Installation of hydroelectric power facilities. 
Reassigns the storage provided for hydroelectric power 
production to municipal and industrial water supply. 
OPTIMA LAKE, OKLA. (See Section 40 of Text) 
Construction of reservoir for flood control, irrigation, 
recreation, and conservation purposes. 
PROSPERITY LAKE, MO. (See Section 44 of Text) 
Undertake the Phase I design memorandum stage of 
advanced Engineering and Design. 
RED RIVER BELOW DENISON DAM (TULSA 
DISTRICT) (See Section 45 of Text) 
Construct Boswell, Hugo, and Millwood Lakes, and Bank 
Stabilization. 
Walnut Bayou Channel Improvements. 
Modify Millwood; construct Pine Creek, Lukfata, Broken 
Bow, DeQueen, Gillham, and Dierks Lakes. 
Construct Clayton and Tuskahoma Lakes. 
Modify 1946 Act-Construct bank stabilization, Index, Ark., 
to Denison Dam. 
SHIDLER LAKE, OKLA. (See Section 46 of Text) 
Construction of reservoir for flood control, water supply, 
water quality control, and recreation purposes. 
SKIATOOK LAKE, OKLA. (See Section 47 of Text) 
Construction of reservoir for flood control, water supply, 
water quality control, recreation, and fish and wildlife 
purposes. 
WAURIKA LAKE, OKLA. (See Section 51 of Text) 
Construction of reservoir for flood control, irrigation, 
and conservation purposes. 
WEBBERS FALLS LOCK & DAM, OKLA. 
(See Section 66 of Text) 
Construction of dam, powerplant, navigation lock, and 
appurtenant facilities. 
Construct a bridge and necessary approach facilities across 
Spaniard Creek, Muskogee, Okla. 
WINFIELD, KANS. (See Section 52 of Text) 
Raise existing levee. 
H. Doc. 256, 91st Cong., 
2d sess. 
H. Doc. 758, 79th Cong., 
2d sess. 
Flood Control Com. Doc. 1, 
75th Cong., 1st sess. 
H. Doc. 758, 79th Cong., 
2d sess. 
H. Doc. 251, 93d Cong., 
2d sess. 
H. Doc. 308, 74th Cong., 
1st sess. 
H. Doc. 361, 93d Cong., 
2d sess. 
H. Doc. 602, 79th Cong., 
2d sess. 
H. Doc. 488, 83d Cong., 
2d sess. 
H. Doc. 170, 85th Cong., 
2d sess. 
S. Doc. 145, 87th Cong., 
2d sess. 
H. Doc. 304, 90th Cong., 
2d sess. 
H. Doc. 242, 89th Cong., 
1st sess. 
H. Doc. 563, 87th Cong., 
2d sess. 
S. Doc. 33, 88th Cong., 
1st sess. 
H. Doc. 758, 79th Cong., 
1st sess. 
PL 91-611 
H. Doc. 232, 89th Cong., 
1st sess. 
19-31

TABLE 19-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
ARKANSAS RIVER BASIN: MULTIPLE-PURPOSE PLAN 
(See Section 1 of Text) 
Feature River River Mile Nearest Town 
Locks and Dams: 
W. D. Mayo, No. 14 Arkansas 319.61 Redland, Okla. 
Robert S. Kerr, No. 15 Arkansas 336.2, Cowlington, Okla. 
Webbers Falls, No. 16 Arkansas 368.81 Gore, Okla. 
Chouteau, No. 17 Verdigris 403.71 Okay, Okla. 
Newt Graham, No. 18 Verdigris 423.9 Inola, Okla. 
Appurtenant Navigation Features: 
Channel cutoffs and 
enlargements Verdigris (2 Muskogee to Catoosa, Okla. 
Dredging Arkansas 
Bank stabilization and 
channel rectification Arkansas 295.4 to Fort Smith Ark., to 
336.2 Robert S. Ierr Lock & Dam 
Robert S. Kerr1 
Marine Terminal Arkansas 339.0 Sallisaw, Okla. 
Lakes: 
Canton North Canadian 394.0 Canton, Okla. 
Elk City Elk River 8.7 Elk City, Kans. 
Eufaula Canadian 27.0 Eufaula, Okla. 
Fall River Fall River 54.0 Fall River, Okla. 
Fort Gibson Grand (Neosho) 8.0 Fort Gibson, Okla. 
Keystone Arkansas 539.0 Sand Springs, Okla. 
Markham Ferry Grand (Neosho) 47.0 Locust Grove, Okla. 
Neodesha 3 Verdigris 223.0 Neodesha, Kans. 
Oologah Verdigris 90.2 Oologah, Okla. 
Pensacola Grand (Neosho) 77.0 Disney, Okla. 
Tenkiller Illinois 13.0 Vian, Okla. 
Toronto Verdigris 271.5 Toronto, Kans. 
Wister Poteau 60.9 Wister, Okla. 
1. Navigation miles-McClellan-Kerr 
Navigation System. 
2. As required for channel 9 feet deep. 
Arkansas River 3. See Table 19-J "Other Authorized Flood Control Projects." 
19-32

TULSA, OKLA., DISTRICT 
TABLE 19-D ARKANSAS-RED RIVER BASINS CHLORIDE CONTROL 
WICHITA RIVER CHLORIDE CONTROL PLAN 
(See Section 8C of Text) 
Low Flow Brine Low Flow Low Flow Brine 
Lake Lake Lake Lake Lake 
Feature (Area VII) (Area VII) (Area VIII) (Area X) (Areas VIII & X) 
Stream North Fork Canal South Fork Middle Fork Trib to N. Fork 
Wichita Riv Creek Wichita Riv Wichita Riv Wichita Riv 
River mile 209.0 1.6 60.8 3.1 191.3 
County Cottle Foard King Foard Knox 
Nearest town Stewart Crowell Benjamin Foard City Truscott 
Drainage area, 
sq mi 489.0 46.0 440.0 161.0 29.0 
Dam: 
Height, ft 38.0 137.0 33.0 41.0 140.0 
Length, ft 650 17,500 3,100 1,260 13,800 
Uncontrolled spillway, 
width, ft 294 100 287 182 100 
Deflatable dam, 
height, ft 12 - 14 14 - 
Outlet works None 36-inch pipe None None 36-inch pipe 
Storage, acre-feet: 
Maximum pool 7,400 235,000 5,320 4,035 202,500 
Top of deflatable dam 3,200 - 1 2,820 620 - 
Brine storage 2,500 167,130 2,500 400 156,000 
Area, acres: 
Maximum pool 710 5,870 600 500 7,100 
Top of deflatable dam 360 - 1 340 80 - 1 
Brine storage 360 4,940 340 80 5,750 
Pumping facility: 
Capacity, g.p.m. 9,000 - 9,000 9,000 - 
Pipeline, 36-inch, 
length, mi 13.0 - 9.5 5.8 - 
1. Includes 100-year event after 100 years accumulation 
of brine. 
19-33

TABLE 19-E ARKANSAS-RED RIVER BASINS CHLORIDE CONTROL 
OKLA., TEX., AND KANS. 
(See Section 8D of Text) 
Fresh Fresh Brine Fresh Brine 
Water Brine Water Lake Water Brine Brine Brine Lake Brine 
Lake Lake' Lake (Area II Lake Lake Lake Lake (Areas XIII Lake 
(Area I) (Area I) (Area II) and III) (Area III) (Area IV) (Area VI) (Area IX) and XIV) (Area XV) 
Stream 
River mile 
County 
Nearest town 
Drainage area, 
sq mi 
Dam: 
Height, ft 
Length, ft 
Spillway: 
Location 
Type 
Width, ft 
Outlet works: 
Type 
Size 
Diversion channel: 
Length, mi 
Depth, ft 
Bottom width, ft 
Storage, acre-feet: 
Max pool 
Brine storage 
Area, acres: 
Max pool 
Brine storage 
Pumping facility: 
Capacity, g.p.m. 
Pipeline, in. 
Length, ft 
Salt Fork, Salt Fork, Buffalo Cr, Cimarron Cimarron Salt Cr, Fish Cr, Canal Cr, Dry Salt Cr, Little 
Arkansas Arkansas Cimarron River River Cimarron Elm Fork Pease Red River Red River 
River River River River River River 
112.7 103.3 4.0 279.1 301.5 21.7 6.3 1.6 8.6 14.0 
Alfalfa Alfalfa Woods & Woodward Harper & Blaine Harmon Foard Childress Hall 
Woodward & Harper Woods 
Cherokee, Jet, Freedom, Freedom, Protection, Southard, Erick, Crowell, Memphis, Turkey, 
Okla. Okla. Okla. Okla. Kans. Okla. Okla. Tex. Tex. Tex. 
2,904.0 296.0 
46.0 - 
55,400 - 
Valley 
Fuse Plug Ogee Weir 
500 290 
Uncontrolled 
Weir 
455.0 
95.0 
80,000 
130.0 7,000.0 
90.0 
8,450 
101.0 
22,100 
18.0 
60.0 
12,000 
29.3 46.0 
131.0 157.0 
3,100 22,000 
- Abutment Abutment Saddle Saddle Saddle Saddle 
- Ogee Weir Ogee Weir Uncon- Uncon- Uncon- Uncontrolled 
trolled trolled trolled 
- 1,000 1,200 150 100 400 
Gated Gated Gated Gated Gated 
- Conduit Conduit Conduit Conduit Conduit Conduit Conduit 
- 11' dia. 36" dia. 20' dia. 36" dia. 36" dia. 36" dia. 36" dia. 
72 
11.0 
87.0 
7.0 
15.0 
20.0 
30.7 
159.5 
13,230 
C
O
4 
137.0 
125.0 
7,500 
Saddle 
Uncontrolled 
200 300 
Gated 
Conduit 
36" dia. 
-- } - 
- 19.2 
- 21.0-25.0 
- 25.0-60.0 
- - 228,000 617,000 1,740,000 31,250 104,000 372,000 167,000 239,000 2 
- 278,000 - 287,000 - 24,500 74,320 313,630 130,740 55,580 
- 5,820 16,800 42,000 1,300 2,050 
30,500 - 10,400 - 1,080 1,670 
7,550 
6,920 
3,250 
2,950 2,704 
- 1,970 5,500 8,203 
(3 pumps) (2pumps) (3 pumps) 
- 8,10, & 14& )24 14, 16, 
12 24 
- 25,400 146,000 83,000 
1. Features of the modified project are the same as for the 
existing project, unless noted. 
-L 
(0 4

TULSA, OKLA., DISTRICT 
TABLE 19-F POOL ELEVATIONS AND STORAGES DURING FISCAL YEAR 
See 
Section 
in Text Project Start End Maximum Minimum 
13. Canton Lake, Arkansas 
River Basin, Okla. 
3C Chouteau L&D, Verdigris 
River Basin, Okla. 
17. Council Grove Lake, 
Grand (Neosho) River 
Basin, Kans. 
19. Dierks Lake, Little 
River Basin, Ark. 
22. Elk City Lake, Verdigris 
River Basin, Kans. 
23. Fall River Lake, Verdigris 
River Basin, Kans. 
25. Fort Supply Lake, North 
Canadian River Basin, 
Okla. 
27. Great Salt Plains Lake, 
Arkansas River Basin, 
Okla. 
29. Hugo Lake, Kiamichi 
River Basin, Okla. 
30. Hulah Lake, Verdigris 
River Basin, Okla. 
31. John Redmond Dam & 
Reservoir Grand (Neosho) 
River Basin, Kans. 
33. Lake Kemp, Wichita 
River Basin, Tex. 
36. Marion Lake, Grand 
(Neosho) River Basin, 
Kans. 
37. Millwood Lake, Little 
River Basin, Ark. 
3D Newt Graham L&D, 
Verdigris River 
Basin, Okla. 
39. Oologah Lake, Verdigris 
River Basin, Okla. 
41. Pat Mayse Lake, Red 
River Basin, Tex. 
43. Pine Creek Lake, Little 
River Basin, Okla. & Ark. 
28. Heyburn Lake, Arkansas 
River Basin, Okla. 
49. Toronto Lake, Verdigris 
River Basin, Kans. 
53. Wister Lake, Poteau 
River Basin, Okla. 
58. Broken Bow Lake, 
Little River Basin, 
Okla. & Ark. 
59. Denison Dam-Lake 
Texoma, Red River 
Basin, Tex. & Okla. 
60. Eufaula Lake, Canadian 
River Basin, Okla. 
61. Fort Gibson Lake, 
Grand (Neosho) River 
Basin, Okla. 
62. Keystone Lake, Arkansas 
River Basin, Okla. 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
1614.87 
113,400 
511.14 
22,890 
1270.18 
38,830 
1615.29 
116,700 
510.98 
22,520 
1277.51 
66,820 
1615.39 
117,500 
517.75 
41,620 
1278.89 
68.050 
450.10 517.53 517.53 
2 19,600 19,600 
793.41 794.06 821.75 
39,870 42,390 250,290 
949.53 948.65 968.72 
26,600 24,320 110,900 
2003.88 2003.97 2004.87 
13,660 13,830 15,570 
1124.97 1126.32 1127.64 
31,160 43,920 58,560 
404.28 
154,600 
733.29 
35,730 
1037.92 
72,330 
1132.53 
769,500 
1350.43 
86,160 
259.43 
211,740 
532.47 
24,220 
643.61 
733,400 
451.88 
129,900 
438.22 
54,580 
761.66 
6,765 
902.39 
24,370 
483.45 
111,700 
598.31 
901,290 
616.75 
2,711,300 
586.65 
2,502,000 
555.22 
388,900 
728.58 
776,400 
404.85 
162,300 
732.94 
34,440 
1044.37 
140,730 
1137.83 
184,800 
1352.30 
98,150 
259.08 
201,480 
532.32 
23,980 
640.78 
638,800 
452.50 
133,700 
439.78 
60,770 
761.68 
6,784 
902.50 
24,690 
485.75 
136,900 
599.78 
922,050 
617.91 
2,814,100 
585.80 
2,412,700 
554.54 
375,460 
727.29 
737,800 
423.50 
537,100 
757.86 
208,300 
1049.12 
207,700 
1137.83 
184,800 
1352.95 
102,570 
265.12 
414,180 
536.58 
30,910 
657.37 
1,320,300 
456.99 
163,400 
462.62 
224,020 
776.78 
32,050 
924.06 
137,300 
496.47 
303,420 
606.23 
1,025,920 
621.04 
3,112,000 
595.27 
3,553,000 
581.73 
1,270,705 
754.26 
1,885,500 
19-35 
1603.03 
42,260 
510.41 
21,230 
1269.21 
36,080 
448.50
1 
785.62 
16,020 
947.31 
21,140 
2002.79 
11,720 
1124.18 
24,670 
403.44 
143,900 
732.45 
32,680 
1035.90 
55,680 
1126.16 
97,210 
1349.29 
79,330 
254.78 
97,136 
527.73 
17,640 
634.47 
455,100 
450.73 
122,900 
437.30 
51,170 
760.80 
6,018 
900.23 
20,120 
471.93 
28,400 
590.05 
802,970 
613.94 
2,473,700 
580.64 
1,913,700 
551.41 
318,270 
716.96 
476,600

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 19-F (Continued) POOL ELEVATIONS AND STORAGES 
DURING FISCAL YEAR 
See 
Section 
in Text Project 
63. Markham Ferry 
Reservoir, Grand 
(Neosho) River Basin, 
Okla. 
42. Pensacola Lake, Grand 
Neosho) River Basin, 
kla. 
64. Robert S. Kerr L&D & 
Reservoir, Arkansas 
River Basin, Okla. 
65. Tenkiller Ferry Lake, 
Illinois River Basin, 
Okla. 
3B W. D. Mayo L&D, 
Arkansas River Basin, 
Okla. 
66. Webbers Falls L&D, 
Arkansas River Basin, 
Okla. 
18. DeQueen Lake, Little 
River Basin, Ark. 
26. Gillham Lake, Little 
River Basin, Ark. 
32. Kaw Lake, Arkansas 
River Basin, Okla. 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Elevation (feet, MSL) 
Storage (acre-feet) 
Start 
619.31 
203,690 
End 
620.11 
212,590 
744.96 745.33 
1,670,200 1,688,000 
Maximum 
635.55 
436,130 
754.86 
2,189,000 
460.19 460.06 461.00 
502,000 496,200 537,700 
637.73 632.58 
730,900 661,700 
412.55 412.87 
15,060 15,570 
655.62 
1,011,900 
419.83 
29,690 
489.82 490.09 490.76 
163,300 166,200 173,600 
368.5
5 
439.4 
154 
935.7
0 
369.9
8 
463.02 
4,379 
941.0 
362 
410.0 
6,240 
498.72 
28,730 
950.6 
309 
TABLE 19-G RED RIVER BELOW DENISON DAM FLOOD CONTROL PLAN 
(TULSA DISTRICT) 
(See Section 45 of Text) 
Project River Site' Nearest Town 
Boswell Lake2 Boggy Creek 18.9 Boswell, Okla. 
Tuskahoma Lake2 Kiamichi River 118.5 Tuskahoma, Okla. 
Clayton Lakes Jackfork Creek 2.8 Clayton, Okla. 
Hugo Lake3 Kiamichi River 17.6 Hugo, Okla. 
Pine Creek Lake3 Little River 145.3 Wright City, Okla. 
Lukfata Lake3 Glover Creek 17.3 Glover, Okla. 
Broken Bow Lake s Mountain Fork River 20.3 Broken Bow, Okla. 
DeQueen Lake3s Rolling Fork River 22.8 DeQueen, Ark. 
Gillham Lake3 Cossatot River 49.0 Gillham, Ark. 
Dierks Lakes Saline River 56.6 Dierks, Ark. 
Millwood Lakes Little River 16.0 Millwood, Ark. 
Bank Stabilization2 Red River 485.3 Index, Ark. 
Bank Stabilization Red River 330.4 Index, Ark. 
Walnut Bayou Red River 509.2 Foreman, Ark. 
1. River mile above mouth. 
2. See Table 19-J "Other Authorized Flood Control Projects." 
3. Project is reported separately herein. 
19-36 
Minimum 
618.56 
196,290 
739.13 
1,416,000 
458.10 
418,100 
625.22 
570,900 
411.09 
12,900 
487.23 
137,000 
367.00
0 
438.60 
132 
936.7 
55

TULSA, OKLA., DISTRICT 
TABLE 19-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 54 of Text) 
Inspection Date 
Project 1974 1975 
Jenks Levee, Okla. May April 
Tulsa-West Tulsa Levees, Okla. December April 
Carthage Levee, Mo. April - 
Enid Diversion Channel and Levee, Okla. June April 
Hutchinson Levee, Kans. June May 
Wichita and Valley Center, Kans. March - 
South Deer Creek Levee, Okla. August April 
Polecat Creek Channel Improvement, Okla. October April 
Florence Levee, Kans. June May 
Sand Creek Channel Improvement, Kans. September - 
Walnut Bayou Channel Improvement, Ark. November November 
Oklahoma City Floodway, Okla. October April 
Cherry and Red Fork Creeks, Okla. May April 
Coffeyville Levee, Kans. August April 
TABLE 19-I SCHEDULING FLOOD CONTROL RESERVOIR OPERATIONS 
(See Section 55 of Text) 
Individual Projects Location Construction Agency Year Completed 
Pensacola Lake Grand (Neosho) River, Okla. Grand River Dam Authority, 1940 
State of Oklahoma 
Altus Dam & Reservoir North Fork of Red River, Okla. Bureau of Reclamation 1948 
Fort Cobb Dam & Reservoir Pond (Cobb) Creek, Okla. Bureau of Reclamation 1959 
Foss Dam & Reservoir Washita River, Okla. Bureau of Reclamation 1961 
Markham Ferry Reservoir Grand (Neosho) River, Okla. Grand River Dam Authority, 1964 
State of Oklahoma 
Norman Dam & Reservoir Little River, Okla. Bureau of Reclamation 1964 
Cheney Dam & Reservoir North Fork of Ninnescah River, Bureau of Reclamation 1965 
Kans. 
Lake Meredith Canadian River, Tex. Bureau of Reclamation 1965 
Arbuckle Dam & Reservoir Rock Creek, Okla. Bureau of Reclamation 1967 
19-37

TABLE 19-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 56 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Augusta, Kans.' 2 1938 - 
Carthage, Mo.3 1958 346,416 - 
Cherry & Red Fork Creeks, Okla.3 1970 261,448 - 
Cow Creek, Kans.4 6 1971 363,720 - 
Crutcho Creek, Okla.4 8 1972 213,016 - 
Deer Creek, Okla.3 1965 37,932 - 
Douglass Lake, Kans.5 1966 - - 
Enid, Okla.3 1963 743,612 14,599 
Florence, Kans.3 1965 369,782 - 
Hutchinson, Kans.3 1956 3,497,718 - 
Iola, Kans.3 1939 22,290 - 
Jenks, Okla.3 1950 344,797 - 
Joe Creek, Tulsa, Okla.4 7 - 181,197 - 
John Redmond Wildlife Refuge, Kans.4 1970 - - 
Neodesha Lake, Kans.4 1952 97,910 - 
Oklahoma City, Okla.3 1960 8,047,512 - 
Sand Creek, Kans.3 1968 493,534 - 
Sand Lake, Okla.5 1963 - - 
Towanda Lake, Kans.5 1966 - - 
Tulsa and West Tulsa, Okla.3 1954 2,785,070 - 
Turkey Creek, Okla.4 1968 - - 
West Branch Chisholm Creek, Kans.3 1965 364,200 - 
Wichita and Valley Center, Kans.3 1960 12,247,379 - 
Winfield, Kans.2 1937 - - 
Bank Stabilization, Red River Below Denison3 1953 222,105 - 
Bank Stabilization, Index, Ark., to 
Denison Dam, Tex.5 1970 - - 
Boswell Lake, Okla.5 1952 - - 
Tuskahoma Lake, Okla.5 1963 - - 
Walnut Bayou, Ark.3 1963 317,675 - 
Stillwater Creek & Tributaries, Okla.9 1974 264,916 - 
1. Reported by Memphis District in 1937; by Little Rock 
District in 1938 and 1939. 
2. Completed by Kansas Works Progress Administration. 
3. Completed. 
4. Inactive. 
5. Awaiting appropriation of funds. 
6. Notice of expiration of authorization after 5 years 
issued December 29, 1970. 
7. Notice of expiration of authorization after 5 years 
issued November 29, 1971. 
8. Notice of expiration of authorization after 5 years 
issued June 13, 1972. 
9. Notice of expiration of authorization after 5 years 
issued November 12, 1974. 
19-38

TULSA, OKLA., DISTRICT 
TABLE 19-K FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Section 205 PL 858, 80th Cong., as amended (Preauthorization) 
(See Section 57 of Text) 
Study Identification 
Arkansas River & Bull Creek, Nickerson, Kans. 
Berry Hill Creek, Tulsa, Okla. 
Fish & Anderson Creeks, Sand Springs, Okla. 
Fry Creek, Bixby, Okla. 
Gypsum & Dry Creeks, Kans. 
Lost Creek, Seneca, Mo. 
Sager Creek, Siloam Springs, Ark. 
Sycamore Creek, Coffeeville, Kans. 
Turkey Creek, Dover, Okla. 
Whiskey & Rock Creeks, Independence, Kans. 
Wolfe Creek, Lawton, Okla. 
Fiscal Year 
Cost 
8,468 
9,934 
7,993 
13,702 
5,530 
6,659 
4,899 
9,133 
5,112 
20,005 
4,984 
TABLE 19-L DENISON DAM--LAKE TEXOMA: ESTIMATED COST 
(See Section 59 of Text) 
Facility Estimated Cost 
$ 
Initial development including two power units 
with provisions for ultimate installation of 
five power units 64,941,000 
Modification No. 2 - Additional public-use 
facilities 4,620,000 
Installation of third power unit 13,630,000 
Modification No. 4 - Additional work 1,028,000 
Improve perimeter access roads 3,000,000 
Total 87,219,0002 
1. Includes $1,212,000 for Willis Bridge and $434,000 for 2. Estimated Federal cost is $86,007,000 and non-Federal 
emergency relief work. cost was $1,212,000. 
TABLE 19-M FLOOD PLAIN INFORMATION STUDIES COMPLETED 
DURING FISCAL YEAR 
(See Section 68 of Text) 
Date Federal 
Location Requesting Agency Completed Cost 
$ 
Derby-Mulvane, Kans., (Ark Riv) Kansas Water June 1975 13,200 
Resources Board 
Catoosa, Okla., (Port of Catoosa) Rogers County June 1975 4,000 
19-39 
- -

KANSAS CITY, MO., DISTRICT* 
This district comprises a portion of southwestern 
Iowa; northwestern, central, and western 
Missouri; northern Kansas; southern Nebraska; 
and a portion of northeastern Colorado 
embraced in drainage basin of the Missouri 
River and tributaries from Rulo, Nebraska, to 
the mouth. Report on navigation project for 
section of Missouri River from Sioux City, Iowa, 
to Rulo, Nebraska, is in report of Omaha 
District. 
IMPROVEMENTS 
Navigation Page 
1. Missouri River, Sioux City, Iowa, to 
Mouth (Rulo, Nebr., to Mouth) ........ 20-2 
2. Other Authorized Navigation 
Projects ........................ 20-3 
Flood Control 
3. Blue River Channel, Kansas City, Mo.. 20-3 
4. Brookfield Lake, Yellow Creek, Mo. .. 20-3 
5. Chariton-Little Chariton Basins, 
Mo. (1965 Act) .................. .. 20-3 
6. Clinton Lake, Wakarusa River, Kans. . 20-4 
7. Elk Creek, Clyde, Kans. ............ 20-4 
8. Fort Scott Lake, Marmaton 
River, Kans .................... 20-4 
9. Grove Lake, Soldier Creek, Kans..... 20-5 
10. Gypsum, Gypsum Creek, Kans ...... 20-5 
11. Harlan County Lake, Republican 
River, Nebr....... . . ............. 20-5 
12. Hillsdale Lake, Big Bull Creek, Kans. . 20-6 
13. Indian Lake, Blue River, Kans. ....... 20-6 
14. Kanopolis Lake, Smoky Hill River, 
Kans. ............ ............ 20-7 
15. Kansas City, Kansas River, Kans. 
(1962 Mod.) ....................... 20-7 
16. Lawrence, Kansas River, Kans. ...... 20-8 
17. Little Blue River Channel, Mo. ....... 20-8 
18. Little Blue River Lakes, Mo. ......... 20-8 
19. Long Branch Lake, Little Chariton 
River Basin, Mo. .................. 20-9 
20. Melvern Lake, Marais des Cygnes 
(Osage) River, Kans ................ 20-9 
21. Mercer Lake, Weldon River, Mo. ...... 20-10 
Flood Control (cont.) Page 
22. Milford Lake, Republican River, 
K ans .... ......... .............. 20-10 
23. Missouri River Levee System, Iowa, 
Nebr., Kans., and Mo. (Rulo, Nebr. 
to M outh) ... ..................... 20-11 
24. Onaga Lake, Vermillion Creek, Kans. .20-11 
25. Pattonsburg Lake, Grand River, Mo. .20-11 
26. Perry Lake Area (Road 
Improvements), Kans ... ......... 20-12 
27. Perry Lake, Delaware River, Kans. ... .20-12 
28. Pick-Sloan Missouri Basin Program 
(Kansas City Dist.) . ............ 20-13 
29. Pomme de Terre Lake, Pomme de 
Terre River, Mo................ 20-13 
30. Pomona Lake, One Hundred Ten 
Mile Creek, Kans ............... 20-14 
31. Rathbun Lake, Chariton River, Iowa .. 20-14 
32. Rathbun Lake, Fish Hatchery, Iowa .. 20-15 
33. Smithville Lake, Little Platte 
River, Mo. ......................... 20-15 
34. Tomahawk Lake, Blue River, Kans. ... .20-15 
35. Tuttle Creek Lake, Big Blue 
River, Kans. .............. .. .20-16 
36. Tuttle Creek Lake, Road Improvements, 
Kans ............ ...... 20-16 
37. Wilson Lake, Saline River, Kans ...... 20-17 
38. Wolf-Coffee Lake, Blue River, Kans. . .20-17 
39. Inspection of Completed Flood 
Control Projects ..................20-17 
40. Other Authorized Flood Control 
Projects ......................... 20-18 
41. Flood Control Work Under Special 
Authorization ...................... 20-18 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
20-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Multiple Purpose Projects 
Including Power 
42. Harry S. Truman Dam and 
Reservoir, Osage River, Mo. ......... 20-18 
43. Stockton Lake, Sac River, Mo....... .20-19 
44. 
45. 
General 
Investigations 
Surveys ........................... 20-20 
Collection and Study 
of Basic Data ................ ...... 20-20 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IOWA, 
TO MOUTH (RULO, NEBR., TO MOUTH) 
Location. Jefferson, Madison, and Gallatin 
Rivers conjoin at Three Forks, Mont., to form 
the Missouri River, which flows southeasterly 
2,315 miles (1960 mileage) across or along seven 
States to the Mississippi River, 17 miles above 
St. Louis. For description see page 1149, Annual 
Report for 1932. Practically entire length of 
section from Kansas City to mouth is within the 
State of Missouri. The river is commercially 
navigable from Sioux City to the .mouth, a 
distance of 732 miles. The portion of project in 
Kansas City District extends from Rulo, Nebraska 
to the mouth, a distance of 498 miles. 
Previous projects. For details see page 1891 of 
Annual Report for 1915, and pages 1153 and 1175 
of Annual Report for 1938. 
Existing project. A channel of 9-foot depth and 
width not less than 300 feet, to be obtained by 
revetment of banks, construction of permeable 
dikes to contract and stabilize waterway, cutoffs 
to eliminate long bends, closing minor channels, 
removal of snags, and dredging as required. 
Section under improvement (mouth to upper end 
of Rulo Bend) is 498.4 miles (1960 mileage) long. 
Ordinary and extreme fluctuations of stage are 
16 and 38 feet, respectively. Estimated cost for 
new work is $259,200,000 (July 1975) exclusive of 
amounts expended on previous projects. (See 
table 20-C for authorizing legislation and table 
20-B for total cost of existing projects to June 30, 
1975.) 
Local cooperation. Project provides that cooperation 
from benefited localities may be required, 
in case a comprehensive plan is adopted 
by Congress for an apportionment of expense, 
where any improvement confers special benefit; 
and receipt of contributions from private parties, 
to be expended with Government funds upon 
authorized works where such would be in 
interest of navigation, is authorized by 1915 
River and Harbor Act. Secretary of the Army 
approved general principle of cooperative construction 
on Missouri River below Kansas City on 
basis that 25 percent of cost of any special 
installation shall be paid by the United States 
and 75 percent by local interests. Total contributed 
by local interests in cooperation with the 
United States from 1918 to June 30, 1964, was 
$675,663, of which $8,647 was returned to contributors. 
Local interests must share in cost of 
recreation facilities in accordance with provisions 
of the Federal Water Project Recreation Act of 
1965. Local interests have contributed $164,185 
for cost sharing on construction of recreation in 
addition to constructing portions of the facilities. 
Terminal facilities. Facilities for transferring 
grain, petroleum products, and other commodities 
are maintained by private interests at 
various locations on this section of the river. 
Facilities are listed in table 20-D. 
Operations and results during fiscal year. 
Regular funds, new work: Construction by 
contract of 39 dikes and 21 dike extensions 
totaling 13,173 linear feet, and 111 lengths of 
revetment totaling 64,183 linear feet at a total 
cost of $3,600,603. Engineering and design, 
supervision and administration, and survey and 
layout of channel and bank stabilization works 
was accomplished at a cost of $265,303. Construction 
of recreation facilities on a cost sharing 
basis in accordance with Public Law 89-72 was 
continued at a cost of $44,217. Work consisted of 
construction of boat ramps, parking areas, and 
engineering for development of future facilities. 
Maintenance: Repair by contract of 51,761 linear 
feet of dike and 198,384 linear feet of revetment, 
at a cost of $4,576,286. In addition, following 
work was accomplished by hired labor: Repair of 
1,812 linear feet of dikes and 9,910 linear feet of 
revetment, a cost of $583,778; maintenance of 
U. S. Government dredges in standby status at a 
cost of $399,223; removal of 2,003,251 cubic yards 
of material at 17 localities by contract dredge at a 
cost of $2,200,036; real estate management, 
$3,126; surveys and mapping, $640,720; stream 
gaging, environmental studies and special working 
data, $780,267; engineering and design, 
$184,870; surveys and layout of construction, 
$35,304; and supervision and administration, 
$279,379. Income from grants, sale of maps and 
charts, outleasing of reservoir land, and miscellaneous 
receipts totaled $277. 
Condition at end of fiscal year. Work on this 
section of the project (Rulo, Nebr., to mouth) is 
about 84 percent complete. Although additional 
20-2

KANSAS CITY, MO., DISTRICT 
dikes and revetment are required to attain full 
project dimensions, a channel with a minimum 
depth of 8.0 feet is available throughout the navigation 
season (generally Mar. thru Nov.). River 
access sites have been completed at eleven 
locations as follows: Nodaway Park, mile 462.1; 
Atchison, Kansas (Independence Park, mile 
423.0); Leavenworth Park, mile 397.7; River 
Front Park, mile 363.0; La Benite Park, mile 
353.0; Lexington State Park, mile 316.5; Miami 
River Front Park, mile 263.0; Stump Island at 
Glasgow, mile 226.0; Taylor's Landing, mile 
185.2; Mokane Park, mile 134.5; and Waverly, 
Mo., mile 283.6. Planning for construction of 
additional recreational facilities is progressing. 
2. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 20-E. 
Flood Control 
3. BLUE RIVER CHANNEL, KANSAS 
CITY, MO. 
Location. Along the Blue River and tributaries 
in Jackson County, Missouri. 
Existing project. Preliminary plans consist of 
12.0 miles of improved channel along the Blue 
River within Kansas City, Missouri. The new 
channel would have bottom widths ranging from 
70 feet to 213 feet, with sections and appurtenant 
structures designed to fit local conditions. 
Project was authorized by 1970 Flood Control 
Act (H. Doc. 91-332, 91st Cong., 2d sess.). 
Estimated Federal cost of construction (1975) is 
$78,200,000 and estimated non-Federal cost of 
lands, damages and relocations is $11,900,000. 
Local cooperation. Section 2, Flood Control 
Act of June 22, 1936, applies. The City of Kansas 
City, Missouri, passed a resolution February 23, 
1968, updated on September 13, 1974, to provide 
the required assurances of local cooperation 
when requested. 
Operations and results during fiscal year. 
Regular funds, new work: Phase II design 
memorandum was initiated and was underway. 
Condition at end of fiscal year. Preconstruction 
planning was 29 percent complete. 
4. BROOKFIELD LAKE, YELLOW CREEK, 
MO. 
Location. Damsite is on Yellow Creek, a 
tributary of the Grand River, about 5 miles 
northeast of Brookfield, in Linn County, 
Missouri. 
Existing project. Preliminary plan provides for 
an earthfill dam about 4,800 feet long and 
approximately 90 feet high with an uncontrolled 
service spillway in the right abutment. Total 
reservoir storage capacity would be 215,600 
acre-feet, of which 117,200 acre-feet would be 
available for flood control, 20,900 acre-feet for 
sediment reserve and 77,500 acre-feet of multipurpose 
storage for water quality control and 
recreation. Project was authorized by the 1965 
Flood Control Act (H. Doc. 241, 89th Cong., 1st 
sess.). Estimated cost (1973) is $22,900,000. 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938, applies. Local interests are 
required to share in cost of recreation facilities in 
accordance with Federal Water Project Recreation 
Act of 1965. 
Operations and results during fiscal year. Due 
to questionable economic justification, preparation 
of the site selection design memorandum 
was deferred pending findings of the Grand 
River Basin reanalysis which was underway. 
Condition at end of fiscal year. Grand River 
Basin reanalysis was nearing completion. 
5. CHARITON-LITTLE CHARITON 
BASINS, MO. (1965 ACT) 
Location. Project is in Chariton and Little 
Chariton River Basins in north-central Missouri, 
the Mussel Fork unit is in Chariton County, the 
Little Chariton River unit in Chariton and 
Randolph Counties, and Shoal Creek unit in 
Putnam County. 
Existing project. Plans provide for improving 
and realining Little Chariton River channel 
downstream from the confluence of the East 
Fork and Middle Fork of the Little Chariton 
River. Middle and East Forks of Little Chariton 
River and lower 2 miles of Silver Creek, a 
tributary of East Fork, would be improved by 
realining and enlarging existing channel for a 
total of about 51 miles. Channel of Mussel Fork, a 
tributary of Chariton River would be straightened 
and improved for about 23 miles. Lower 5 
miles of Shoal Creek was shortened to about 2 
miles by construction of a cutoff to new Chariton 
River channel constructed under a previous 
project. Project was authorized by 1965 Flood 
Control Act (H. Doc. 238, 89th Cong., 1st sess.). 
Because an environmentally acceptable plan 
could not be formulated and due to lack of 
economic justification, Mussel Fork and Little 
Chariton River units were reclassified to the 
"inactive" status in FY 1972. The inactive 
program estimate (1971) is $9,346,000 of which 
$7,910,000 is Federal and $1,436,000 for lands, 
damages, and relocations to be borne by local 
20-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
interests. A revised plan was formulated for the 
Shoal Creek unit to alleviate the environmental 
impact. Estimated cost (1975) of the active 
program is $538,000, of which $485,000 is Federal 
and $53,000 for lands and damages to be borne by 
local interests. 
Local cooperation. Section 3, Flood Control 
Act of June 28, 1938, applies. The Shoal Creek 
Drainage District have given formal assurances 
of intent to cooperate. The Shoal Creek Drainage 
District has furnished all rights-of-way for the 
Shoal Creek unit. 
Operations and results during fiscal year. 
Regular funds, new work: Work on the channel 
construction advanced to 89 percent complete. 
Condition at end of fiscal year. Construction of 
Shoal Creek unit is nearing completion. 
6. CLINTON LAKE, WAKARUSA RIVER, 
KANS. 
Location. Damsite is on Wakarusa River about 
4 miles southwest of Lawrence, Kansas, in 
Douglas County. Lake extends into Shawnee and 
Osage Counties, Kansas. 
Existing project. Plans provide for an earthfill 
dam about 9,250 feet long to be constructed to an 
average height of about 85 feet, with an 
uncontrolled spillway in left abutment. Total 
reservoir storage capacity would be 397,200 
acre-feet (258,300 for flood control, 28,500 for 
sediment reserve, and 110,400 of multipurpose 
storage for municipal and industrial water supply 
and recreation). Estimated Federal cost of 
construction" (1975) is $58,300,000. Local interests 
will be required to make reimbursement for 
water supply storage in the estimated amount of 
$7,061,000. Project authorized by 1962 Flood 
Control Act (S. Doc. 122, 87th Cong., 2d sess.). 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938, applies. Reimbursement 
will be required for water supply storage to be 
provided in accordance with Water Supply Act of 
1958. 
Operations and results during fiscal year. 
Regular funds, new work: Land acquisition 
consisted of 504 acres in fee and 396 acres 
flowage and road rights-of-way easements at a 
cost of $1,097,887. Relocation of Phase I Douglas 
County roads was initiated and advanced to 48 
percent complete at a cost of $500,000. Relocation 
of utilities was continued at a cost of 
$222,479. Boundary surveys and marking, by 
contract, were continued at a cost of $153,133. 
Stage I lake clearing was initiated at a cost of 
$10,000. Forestation work was continued by the 
U. S. Forest Service at a cost of $40,000. 
Purchase of permanent operating equipment was 
continued at a cost of $7,298. Contract for 
construction of dam was advanced 34 percent at a 
cost of $5,297,186. Design work, by contract, 
cost $53,539. Hired labor operations consisted of 
boundary surveys and marking, installation of 
observation devices, real estate management and 
other operation and maintenance during construction, 
surveys and layouts, and design and 
supervision of construction at a cost of $847,642. 
Condition at end of fiscal year. Entire project 
is about 51 percent complete. Construction of 
administrative facilities and left abutment access 
roads and cemetery relocation is complete. 
Relocation of roads and utilities, lake clearing 
and boundary surveys and marking are underway. 
Construction of dam is 72 percent complete. 
Lands totaling 22,054 acres, including the town 
of Richland, Kansas, having been acquired in fee 
and flowage and road rights-of-way easements 
acquired for 792 acres. Planning is underway on 
design memorandums and contract plans for 
other construction features. 
7. ELK CREEK AT CLYDE, KANS. 
Location. At Clyde, Cloud County, Kansas, on 
the right bank of Elk Creek about 1 mile north 
and west of its confluence with the Republican 
River, and about 15 miles east of Concordia, 
Kansas. 
Existing project. Improvements previously 
constructed consist of a levee along the north and 
east side of the city to tie into high ground, and 
channel improvement work. Project was selected 
for construction under authority of Section 205, 
1948 Flood Control Act, as amended. Estimated 
Federal cost of construction, including remedial 
work, is $932,000. Non-Federal costs of lands, 
damages, and relocations were $176,000. 
Local cooperation. Section 3, Flood Control 
Act of June 2, 1936, applies. All rights-of-way 
were furnished for original construction. Additional 
rights-of-way were obtained for rehabilitation 
work. 
Operations and results during fiscal year. 
Regular funds, new work: Contract for channel 
rehabilitation, which was awarded in May 1974, 
was completed in September 1974. 
Condition at end of fiscal year. Construction of 
the original project was completed in August 
1963 at a total Federal cost of $394,028. Contract 
for channel rehabilitation was complete. 
8. FORT SCOTT LAKE, MARMATON 
RIVER, KANS. 
Location. Damsite is on Marmaton River about 
55 miles above its mouth and about 5 miles west 
20-4

KANSAS CITY, MO., DISTRICT 
of Fort Scott, Bourbon County, Kansas. 
Existing project. Plans provide for a dam 
about 5,500 feet long to be constructed to an 
elevation about 69 feet above valley floor, with 
an uncontrolled spillway. Total reservoir storage 
capacity would be 249,900 acre-feet (163,600 for 
flood control, 11,900 for sediment reserve, and 
74,400 of multipurpose storage for water supply, 
water quality control, fish and wildlife, and 
recreation). Project is a unit of the Pick-Sloan 
Missouri Basin program for flood control and 
other purposes in Missouri River Basin, authorized 
by Flood Control Act of 1954 (H. Doc. 549, 
81st Cong., 2d sess.). Estimated cost (1975) is 
$46,900,000. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. Reimbursement at an estimated 
cost of $1,565,000 will be required by local 
interests for water supply storage to be provided 
in accordance with Water Supply Act of 1958. 
Operations and results during fiscal year. 
Regular funds, new work: Minor miscellaneous 
planning costs of $272 were incurred. 
Condition at end of fiscal year. Preconstruction 
planning, including contract plans for the initial 
construction contracts, are essentially complete. 
9. GROVE LAKE, SOLDIER CREEK, 
KANS. 
Location. Damsite is on Soldier Creek about 7 
miles northwest of Topeka, Kansas, in Shawnee 
County, with lake extending upstream into 
Jackson County. 
Existing project. Preliminary plans provide for 
an earthfill dam about 9,300 feet long and about 
82 feet high, with an uncontrolled flat crest 
spillway. Total reservoir storage capacity would 
be 291,700 acre-feet (136,100 for flood control, 
29,000 for sediment reserve, and 126,600 of 
multipurpose storage for water supply and 
recreation). Local interests will be required to 
make reimbursement for water supply storage in 
the estimated amount of $9,875,000. Project 
authorized by 1962 Flood Control Act (S. Doc. 
122, 87th Congress, 2d sess.). Estimated cost of 
construction (1975) is $84,500,000. 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938, applies. The city of Topeka, 
Kansas, has furnished assurances for water 
supply storage to be provided in accordance with 
Water Supply Act.of 1958. 
Operations and results during fiscal year. 
Regular funds, new work: Preconstruction 
planning was underway and nearing completion. 
10. GYPSUM, GYPSUM CREEK, KANS. 
Location. At Gypsum, Saline County, Kansas, 
on the left bank of Gypsum Creek, 10 miles south 
of its confluence with Smoky Hill River, 15 miles 
southeast of Salina, Kansas. 
Existing project. Plan consists of a levee 
around the city, a diversion channel, and channel 
improvement work. Project was selected for 
construction under Section 205, 1948 Flood 
Control Act, as amended by Section 61 of 1974 
Water Resources Development Act. Estimated 
Federal cost of construction (1975) is $1,762,800, 
and estimated non-Federal cost of lands, damages, 
relocations, and construction is $275,300. 
Local cooperation. City Council adopted resolutions 
of intent to sponsor the project on 
January 3, 1966 and November 3, 1970. Section 
3, Flood Control Act of June 22, 1936 and Section 
221 Flood Control Act of 1970 apply. The city of 
Gypsum has expended funds on planning its 
share of project costs, implemented work toward 
acquisition of rights-of-way, and received commitments 
from the county and State Highway 
Commission for construction and alterations of 
highway bridges involved. 
Operations and results during fiscal year. 
Regular funds, new work: A supplemental 
Detailed Project Report was submitted in 
August 1974. In January 1975, an AE contract 
was awarded for preliminary and completed 
design of channels and levees. The draft 
Environmental Impact Statement was filed with 
the Council on Environmental Quality in August 
1974 and the final EIS filed in May 1975. 
Condition at end of fiscal year. An environmental 
assessment recommended a partial 
change in levee and channel alinements. Based on 
supplemental DPR, an AE is in process of 
preparing plans and specifications. 
11. HARLAN COUNTY LAKE, 
REPUBLICAN RIVER; NEBR. 
Location. Dam is on main stem of Republican 
River about 235 miles above confluence of stream 
with Smoky Hill River. Site is in Harlan County, 
about 3 miles east of Republican City and 13 
miles west of Franklin, Nebraska. 
Existing project. An earthfill dam about 107 
feet above streambed and a total length of 11,827 
feet, including a gate-controlled, concrete, 
gravity-type spillway section near center of dam, 
impounds floodwater within reservoir which 
provides storage capacity of 850,000 acre-feet 
(500,000 for flood control and 350,000 for 
irrigation and sedimentation allowance). Project 
is a unit of the Pick-Sloan Missouri Basin 
program for flood control and other purposes in 
Missouri River Basin authorized by 1938 Flood 
20-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Control Act (Flood Control Committee Doc. 1, 
75th Cong., 1st sess.), as modified by 1941 Flood 
Control Act (H. Doc. 842, 76th Cong., 3d sess.), 
to include this project, and expanded by 1944 
Flood Control Act (H. Doc. 475, and S. Docs. 191 
and 247, 78th Cong., 2d sess.). Initial cost of 
constructing the completed project was $45,279,- 
532. Total estimated Federal cost of project 
(1975) including $1,017,623 for major rehabilitation 
work and $404,000 supplemental recreation 
development (Code 710), is $46,701,155. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operation and results during fiscal year. 
Regular funds, new work: Supplemental recreation 
facilities consisting of preparation of plans 
and specifications for Hunters Cove public use 
area development and initiation of installation of 
pre-cast curbs was accomplished at a cost of 
$34,837. Maintenance: Work performed by 
contract for repair of the water tower was 
completed at a cost of $10,272. Installation of 
new piezometer tubes was accomplished by hired 
labor at a cost of $9,505. Air conditioning of the 
administration building and repair of flooring in 
two buildings was accomplished by hired labor at 
a cost of $4,137. A tractor and backhoe, rotary 
mower, radio and miscellaneous grounds and 
reservoir equipment were replaced at a cost of 
$17,521. Routine operation, ordinary maintenance, 
real estate management services, engineering 
and design, and supervision cost $392,- 
970. Income from sale of water and collections for 
subsistence, quarters, services, etc., and other 
income totaled $3,495. Proceeds from rentals of 
reservoir lands and recreational fees of $183,136 
were deposited in the U.S. Treasury. Local 
governmental units will be paid 75 percent of 
$174,186 received from lease rentals. 
Condition at end of fiscal year. Construction of 
project was initiated in August 1946 and 
construction of embankment and gravity spillway 
section was completed December 1952. 
Construction of supplemental recreation facilities 
is underway. 
12. HILLSDALE LAKE, BIG BULL CREEK, 
KANS. 
Location. Damsite is about 12 miles above 
mouth of Big Bull Creek, a tributary of Marais 
des Cygnes River, and about 5 miles north of 
Paola, Miami County, Kansas. 
Existing project. Preliminary plans provide for 
an earthfill embankment about 12,000 feet long 
(including approximately 3,300 feet of dike 
section) and about 75 feet above valley flood plain 
and a gravity type uncontrolled spillway section. 
The total reservoir storage capacity would be 
160,000 acre-feet (81,000 for flood control, 11,000 
for sediment reserve, and 68,000 for multipurpose 
storage for water supply, downstream 
power, water quality control, and recreation). 
Local interests will be required to make 
reimbursement for water supply storage estimated 
at $17,708,000. At present, recreation 
development has been reduced to minimum 
facilities due to lack of sponsor. Project was 
authorized by 1954 Flood Control Act (H. Doc. 
549, 81st Cong., 2d sess.). Estimated Federal 
cost of construction (1975) is $52,500,000. 
Local cooperation. Section 2, Flood Control 
Act 1938, applies. Local interests must make 
reimbursement for water supply storage in 
accordance with Water Supply Act of 1958 and 
share in separable cost allocated to recreation in 
accordance with Federal Water Project Recreation 
Act of 1965. The Kansas Water Resources 
Board signed a contract in January 1974, 
approved by the Secretary of the Army in April 
1974, for the entire 53,000 acre-feet of water 
supply storage. Local interests have shown no 
interest in sponsoring recreational development 
at this time. 
Operations and results during fiscal year. 
Regular funds, new work: Land acquisition 
consisted of acquiring 1,794 acres in fee and 37 
acres of easements for a total amount of 
$1,626,000. The contract for administrative 
facilities was awarded and advanced to 20 
percent complete at a cost of $147,000. Engineering 
and design, by contract, was accomplished 
for $40,000. Hired labor operations consisted of 
installation of observation devices, real estate 
management, engineering and design and supervision 
and administration at a total cost of 
$440,000. 
Condition at end of fiscal year. The administrative 
facilities are under contract, construction 
plans for Stage I embankment are complete and 
2,033 acres of fee land and 37 acres of easements 
acquired. 
13. INDIAN LAKE, BLUE RIVER, KANS. 
Location. The damsite of project is located on 
Indian Creek in Johnson County, Kansas, about 
14 miles above the confluence of Indian Creek 
and the Blue River near the Kansas-Missouri 
State line. Most of the project is located within 
the city limits of Overland Park, Kansas. 
Existing project. Preliminary plans provide for 
an earthfill dam about 4,800 feet long and 80 feet 
high with an uncontrolled outlet through the dam 
and an uncontrolled limited service spillway. 
Preliminary plans are based on a total storage 
capacity of 22,900 acre-feet (10,500 for flood 
control, 9,500 for recreation and releases for the 
20-6

KANSAS CITY, MO., DISTRICT 
preservation of fish, wildlife and esthetics, and 
2,900 for sediment reserve). Local interests will 
be required to make reimbursement estimated at 
$5,700,000 for recreation cost sharing. Project 
was authorized by 1970 Flood Control Act (H. 
Doc. 332, 91st Cong. 2d sess.). Estimated 
Federal cost of construction (1975) is 
$40,900,000. 
Local cooperation. Section 2, Flood Control 
Act of June 1938, applies. Reimbursement will be 
required for recreation provided in accordance 
with Federal Water Project Recreation Act of 
1965. 
Operation and results during fiscal year. 
Regular funds, new work: Recreation Resources 
Appendix to Phase I Design Memorandum was 
completed. Surveying, mapping and design 
studies were underway. 
Condition at end of fiscal year. A review to 
evaluate recent developments within the Blue 
River system was conducted in the latter part of 
FY 1975. A report on this review recommended 
that the Indian Lake project be placed in an 
inactive status. 
14. KANOPOLIS LAKE, SMOKY HILL 
RIVER, KANS. 
Location. Dam is on Smoky Hill River about 19 
miles west and 16 miles south of Salina, Kansas, 
and about 205 river miles above mouth of stream. 
Existing project. An earthfill dam about 131 
feet above streambed and a total length of 15,360 
feet, including 4,070 feet of dike section on left 
abutment and 2,550 feet of dike section on right 
abutment, impounds floodwater within reservoir 
which provides storage capacity of 450,000 
acre-feet, (400,000 for flood control and 50,000 
for recreation and streamflow regulation). Outlet 
works and spillway are in right abutment. 
Project is a unit of the Pick-Sloan Missouri Basin 
program for flood control and other purposes in 
Missouri River Basin authorized by 1938 Flood 
Control Act (Flood Control Committee Doc. 1, 
75th Cong., 1st sess.) as modified by 1941 Flood 
Control Act, and expanded by 1944 Flood Control 
Act (H. Doc. 475, and S. Docs. 191 and 247, 78th 
Cong., 2d sess.). Initial cost of constructing the 
completed project was $12,327,735. Total estimated 
Federal cost of project (1975) including 
$274,000 supplemental recreational development 
(Code 710) is $12,601,735. 
Local cooperation. Section 2, Flood Control 
Act 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: No work accomplished 
during fiscal year. Maintenance: Work performed 
by contract consisted of installation of 
new hydraulic tanks and pumps and repair of 
administration building roof at a cost of $9,456 
and $3,081 respectively. A flail mower, miscellaneous 
office, grounds, reservoir and garage 
equipment were replaced at a cost of $8,823. 
Routine operation, ordinary maintenance, real 
estate management services, and supervision 
and administration cost $342,958. Income from 
collections for subsistence, quarters, services, 
etc., and other income totaled $2,642. Proceeds 
from rentals of reservoir lands and recreational 
fees of $108,448 were deposited in the U.S. 
Treasury. Local governmental units will be paid 
75 percent of the $101,975 received from lease 
rentals. 
Condition at end of fiscal year. Construction of 
project was initiated June 1940 and dam and 
spillway were completed and ready for use in 
May 1948. Construction of supplemental recreation 
facilities is underway. 
15. KANSAS CITY, KANSAS RIVER, KANS. 
Location. Along the Kansas River at Kansas 
City, Kansas. 
Existing project. Provides for raising existing 
levees and floodwall protection in Argentine, 
Armourdale, and Central Industrial units, and 
includes necessary bridge alterations and modification 
of appurtenant facilities. Existing project 
was authorized by 1962 Flood Control Act (S. 
Doc. 122, 87th Cong., 2d sess.). Estimated 
Federal cost of construction (1975) is $47,500,000 
and estimated non-Federal cost of lands, damages, 
and relocations is $6,500,000. 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936, applies. Assurances of local 
cooperation were received December 4, 1968. 
Rights-of-way for the first stage contract, in the 
Argentine unit and the Armourdale unit, have 
been furnished. 
Operations and results during fiscal year. 
Regular funds, new work: Financial completion 
of contracts for the upstream portion of the 
Argentine unit was accomplished at a cost of 
$30,980. Contract for the major portion of the 
Armourdale unit was advanced 68 percent at a 
cost of $4,886,640. Contract payment of $12,191 
was made to City of Kansas City, Kansas for 
provision of relief well discharge facilities in new 
pumping plant in Armourdale unit. Design work, 
by contract, cost $47,216. Hired labor operations 
consisted of supervision and administration and 
continuation of planning on other units of the 
project at a cost of $501,867. 
Condition at end of fiscal year. Construction of 
the upstream portion of Argentine unit was 
completed. Construction of the first phase of the 
20-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Armourdale unit was 77 percent complete. 
Preparation of plans for the Central Industrial 
unit was underway. 
16. LAWRENCE, KANSAS RIVER, KANS. 
Location. On Kansas River about 50 miles 
above its mouth at Lawrence, Douglas County, 
Kansas. 
Existing project. Levees along both banks of 
Kansas River and right bank of Mud Creek, 
channel improvement for Mud Creek and Brook 
Street channel, bank protection, .and appurtenant 
facilities for protection of North Lawrence 
and South Lawrence, Kansas. Project was 
authorized by 1954 Flood Control Act (H. Doc. 
642, 81st Cong., 2d sess.). Estimated Federal 
cost of construction (1975) is $11,600,000 and 
estimated non-Federal cost of lands, damages, 
and relocations is $2,410,000. 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936, applies. Board of 
Commissioners of city of Lawrence furnished 
required assurances June 8, 1965. All required 
rights-of-way for construction along the left bank 
of the Kansas River in North Lawrence have 
been furnished. 
Operations and results during fiscal year. 
Regular funds, new work: Based on studies of 
alternate plans for Mud Creek, it appeared that 
one of the alternate plans should be recommended 
because of its lower cost and environmental 
acceptability. In the FY 1975 appropriations, 
Congress directed the Corps to construct 
the original plan. The Mud Creek Recreation 
Resources Appendix was in progress. 
Condition at end of fiscal year. Construction of 
the project was initiated July 31, 1967. Left bank 
levee upstream from Massachusetts Avenue and 
downstream levee along left bank was completed. 
Planning was underway for the Mud 
Creek unit. 
17. LITTLE BLUE RIVER CHANNEL 
IMPROVEMENT, LITTLE BLUE RIVER, 
MO. 
Location. The project is located on the Little 
Blue River from the head of Missouri River 
Levee Unit R 351 upstream to the vicinity of 
Wildwood Creek. 
Existing project. The proposed improvements 
will consist of straightening and enlarging the 
Little Blue River channel from the head of 
Missouri River Levee Unit R 351, near Blue Mills 
Road, upstream to the vicinity of Wildwood 
Creek, reducing the length of this section from 
20.4 to about 15 miles. Bottom widths, sections, 
and appurtenant structures will be designed to 
fit local conditions. Alteration of two railroad and 
four highway bridges will be required. Improvements 
in the vicinity of Lake City will consist of 
diversion of West Fire Prairie Creek westward 
into the Little Blue River and construction of a 
levee along the north side of the diversion ditch 
and along the north bank of the Little Blue River 
below the new confluence of the diversion ditch. 
Project was authorized by Flood Control Act 
approved August 13, 1968, (H. Doc. 169, 90th 
Cong., 1st sess.). Estimated Federal cost of 
construction (1975) is $28,000,000 and estimated 
non-Federal cost is $3,500,000. 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936, applies to the Little Blue 
River channel improvement works. Jackson 
County, Missouri, passed a bond issue in 1967 
which included funds for sponsorship of the 
project. Assurances of local cooperation were 
furnished 31 July 1973 and rights-of-way 
requirements for the first stage of construction 
were furnished on 6 June 1973. 
Operations and results during fiscal year. 
Regular funds, new work: A contract for the first 
stage of construction was awarded on 20 
December 1974. Plans and specifications for 
succeeding stages were underway. 
Condition at end of fiscal year. Stage I 
construction was underway. 
18. LITTLE BLUE RIVER LAKES, MO. 
Location. This project consists of two lakes in 
Jackson County, Missouri, located in Kansas 
City, Missouri, and suburban communities. The 
Blue Springs Lake site is on the East Fork of the 
Little Blue River about one-half mile south of 
U. S. Highway 40 and the Longview Lake site is 
on the main stem at approximately 109th Street. 
Existing project. The Blue Springs dam will be 
an earthfill embankment about 2,500 feet long 
and rising about 75 feet above the streambed, 
with an uncontrolled service spillway and 
uncontrolled outlet conduit. The total reservoir 
storage capacity will be 21,600 acre-feet (15,700 
for flood control, 5,600 for multipurpose storage 
for water quality and recreation, and 300 for 
sedimentation). 
The Longview dam will be an earthfill 
embankment about 1,900 feet long and rising 
about 120 feet above the streambed, with an 
uncontrolled service spillway and an uncontrolled 
outlet conduit. The total reservoir storage 
capacity will be 46,900 acre-feet (24,300 for flood 
control and 20,600 for multipurpose storage for 
water quality and recreation and 2,000 for 
sedimentation). Project was authorized by Flood 
Control Act approved August 13, 1968 (H. Doc. 
169, 90th Cong., 1st sess.). Estimated Federal 
20-8

KANSAS CITY, MO., DISTRICT 
cost of construction (1975) is $93,900,000. 
Local cooperation. Section 2 of the Flood 
Control Act of June 28, 1938, applies. Local 
interests must share in separable cost allocated 
to recreation in accordance with Federal Water 
Project Recreation Act of 1965. 
Operations and results during fiscal year. 
Regular funds, new work: Land acquisition 
consisted of 1,389 acres in fee. The spillway and 
outlet works and embankment design memorandums 
were completed. Preparation of the 
relocation design memorandum was underway. 
Condition at end of fiscal year. Preconstruction 
planning was underway and a total of 5,370 acres 
of fee simple and 6 acres of flowage easements 
land acquired. Advance land acquisition is 
approximately 55 percent complete. 
19. LONG BRANCH LAKE, LITTLE 
CHARITON RIVER, MO. 
Location. Damsite is on East Fork of Little 
Charitbn River in north-central Missouri about 1 
mile west of Macon in Macon County. 
Existing project. Plans provide for an earthfill 
dam about 3,800 feet long and about 71 feet high 
with an uncontrolled outlet conduit and an 
uncontrolled service spillway in right abutment. 
Total reservoir storage capacity would be 65,000 
acre-feet (29,000 for flood control, 4,000 for 
sediment reserve, and 32,000 of multipurpose 
storage for water supply, water quality control, 
fish and wildlife, and recreation). Local interests 
will be required to make reimbursement estimated 
at $5,093,000 for water supply storage and 
$2,261,000 for recreation cost sharing. Project 
was authorized by 1965 Flood Control Act (H. 
Doc. 238, 89th Cong., 1st sess.). Estimated cost 
(1975) is $19,600,000. 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938, applies. Local interests 
must make reimbursement for water supply 
storage in accordance with Water Supply Act of 
1958 and share in separable cost allocated to 
recreation in accordance with Federal Water 
Project Recreation Act of 1965. The city of 
Macon, Mo. signed contracts for water supply in 
June 1972 and recreational development in May 
1972. Both contracts approved by the Secretary 
of the Army in September 1972. Missouri State 
agencies have indicated their intent to sponsor 
future water supply and have expressed their 
desire and intent to sponsor recreational development 
in lieu of city of Macon. 
Operations and results during fiscal year. 
Regularfunds, new work: Fee simple title to 993 
acres of land and 45 acres of flowage easements 
were acquired at a cost of $450,237. The access 
road and administrative facilities contract was 
completed at a cost of $53,966. Design for the 
pumping plant relocation was initiated by 
contract at a cost of $795. Construction contract 
for the dam and access road was awarded and 
work advanced to 10 percent complete at a cost of 
$625,896. Installation of observation devices was 
initiated at a cost of $40,590. Permanent 
operating equipment was procured at a cost of 
$5,589. Design work by contract was accomplished 
at a cost of $64,378. Hired labor activities 
consisted of operation and maintenance during 
construction, engineering and design and supervision 
and administration of construction at a 
cost of $461,355. 
Condition at end of fiscal year. Entire project 
is about 26 percent complete. Acquisition of 5,328 
acres of land in fee simple and flowage easements 
of 64 acres was completed through June 30, 1975. 
Construction of access road and administrative 
facilities is complete. Features Design Memorandum 
is complete. Embankment contract is 10 
percent complete. Planning is underway on 
design memorandums and contract plans on 
other construction features. 
20. MELVERN LAKE, MARAIS DES 
CYGNES (OSAGE) RIVER, KANS. 
Location. Damsite is on Marais des Cygnes 
(Osage) River in Osage County, Kansas, about 2 
miles west of Melvern, Kansas. 
Existing project. An earthfill dam about 9,700 
feet long and about 98 feet high with an uncontrolled 
chute-type spillway in left abutment. 
Total reservoir storage capacity would be 
363,000 acre-feet (200,000 for flood control, 
26,000 for sediment reserve, and 137,000 of 
multipurpose storage for water quality control 
and recreation). Project is a unit of the 
Pick-Sloan Missouri Basin program for flood 
control and other purposes in Missouri River 
Basin, authorized by 1954 Flood Control Act (H. 
Doc. 549, 81st Cong., 2d sess.). Initial cost of 
constructing the completed project was $37,404,- 
000. Total estimated Federal cost of project 
(1975) including $347,000 supplemental recreational 
development (Code 710) is $37,751,000. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: Land acquisition 
consisted of deficiency judgments totaling $368,- 
628. State Highway 170 Relocation contract was 
financially completed at a cost of $109,155. 
Modification of warehouse, completion of storage 
building, construction and removal of bridge was 
accomplished by contract at a cost of $131,340. 
20-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Recreation facilities were advanced to 99 percent 
complete at a cost of $811,109. Forestation work 
was continued at a cost of $145,876. Hired labor 
operations consisted of boundary marking, 
procurement of equipment for operation of 
project, engineering and design and supervision 
and administration accomplished at a cost of 
$308,795. Maintenance: Wind damage to the 
water treatment plant was repaired by contract 
at a cost of $24,060. Road repair work was 
accomplished by hired labor at a cost of $8,359. 
Hired labor forces repaired breakwater at a cost 
of $3,700 and wind damage in the administrative 
area was accomplished at a cost of $8,128. 
Miscellaneous office, grounds, reservoir and shop 
equipment was replaced at a cost of $4,775. 
Routine operation, ordinary maintenance, real 
estate management services, engineering and 
design and supervision and administration, cost 
$411,128. Income for collections for subsistence, 
quarters, services, etc., totaled $1,878. Proceeds 
from rentals of reservoir lands and recreational 
fees of $68,294 were deposited in the U. S. 
Treasury. Local governmental units will be paid 
75 percent of $61,838 received from lease rentals. 
Condition at end of fiscal year. Construction of 
the project was initiated July 13, 1967 and is 
approximately 99 percent complete. Acquisition 
of 23,447 acres of land in fee simple and flowage 
easements for 1,087 acres has been accomplished. 
All work is complete except recreation 
facilities. Supplemental recreation facilities have 
not been initiated to date. 
21. MERCER LAKE, WELDON RIVER, MO. 
Location. The project is located in the Grand 
River Basin on the Weldon River in north-central 
Missouri about 3 miles southwest of Mercer and 6 
miles north of Princeton, in Mercer County, with 
the lake extending upstream into Decatur and 
Wayne Counties in Iowa and to within about 60 
miles of Des Moines, Iowa. 
Existing project. Preliminary plans provide for 
an earthfill dam about 6,700 feet long and 91 feet 
high with an uncontrolled service spillway in the 
right abutment. Preliminary plans are based on 
providing a total storage capacity of 625,700 
acre-feet (326,000 for flood control, 235,800 of 
multipurpose storage for water supply, water 
quality control, and recreation, and 63,900 for 
sediment reserve). Local interest will be required 
to make reimbursement estimated at 
$3,900,000 for recreation cost sharing. Project 
was authorized by 1965 Flood Control Act (H. 
Doc. 241, 89th Cong., 1st sess.). Estimated 
Federal cost of construction (1973) is $40,000,- 
000. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. Reimbursement will be 
required for recreation provided in accordance 
with Federal Water Project Recreation Act of 
1965. 
Operations and results during fiscal year. 
Regular funds, new work: Due to questionable 
economic justification preparation of the site 
selection design memorandum was deferred 
pending findings of the Grand River Basin 
reanalysis which was underway. 
Condition at end of fiscal year. Grand River 
Basin reanalysis was nearly complete. 
22. MILFORD LAKE, REPUBLICAN RIVER, 
KANS. 
Location. Damsite is on Republican River near 
village of Alida and about 8 miles downstream 
from Milford, Geary County, Kansas, and about 
10 miles above confluence of Republican and 
Smoky Hill Rivers which form Kansas River near 
Junction City, Kansas. 
Existing project. An earthfill dam about 6,300 
feet long and 125 feet high with an uncontrolled 
service-chute spillway in a saddle on right 
abutment. Total reservoir storage capacity is 
1,160,000 acre-feet (700,000 for flood control, 
160,000 for sediment reserve and 300,000 of 
multipurpose storage for water supply, water 
quality control, and recreation). Water supply 
storage is included in project at request of 
Governor of Kansas under provisions of Federal 
Water Supply Act of 1958. Local interests will be 
required to make reimbursement for water 
supply storage in the estimated amount of 
$13,467,000. Project is a unit of the Pick-Sloan 
Missouri Basin program for flood control and 
other purposes in Missouri River Basin authorized 
by 1954 Flood Control Act (H. Doc. 642, 81st 
Cong., 2d sess.). Initial cost of constructing the 
completed project was $48,268,843. Total estimated 
Federal cost of project (1975) including 
$716,000 supplemental recreational development 
(Code 710) is $48,984,843. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. Local interests must make 
reimbursement for water supply storage in 
accordance with Water Supply Act of 1958. 
Operations and results during fiscal year. 
Regular funds, new work: Supplemental recreation 
facilities consisting of development of the 
Rolling Hills Area was completed at a cost of 
$24,120. Maintenance: Installation of seismic 
instrumentation was performed by contract at a 
cost of $12,944. Road repair was accomplished by 
contract at a cost of $8,388. Forestation was 
performed by contract at a cost of $15,000. Hired 
labor activities consisting of stilling basin repair, 
20-10

KANSAS CITY, MO., DISTRICT 
road resealing, installation of seismic instrumentation 
were accomplished at a cost of $8,646. 
Purchases of tractor hi-loader, playground 
equipment and miscellaneous office, ground, 
reservoir, garage, and shop equipment totaled 
$13,958. Routine operation, ordinary maintenance, 
real estate management services, engineering 
and design, and supervision and administration, 
cost $399,529. Income from crop disposals 
totaled $6,371. Proceeds from rentals of 
reservoir lands, recreational fee income, and 
other non-operating income of $57,933 were 
deposited in the U. S. Treasury. Local governmental 
units will be paid 75 percent of the 
$52,353 received from lease rentals. 
Condition at end of fiscal year. Construction of 
project began July 7, 1961. The entire project is 
complete and is operating for flood control. 
Construction of supplemental recreation facilities 
is underway. 
23. MISSOURI RIVER LEVEE SYSTEM, 
IOWA, NEBR., KANS., AND MO. 
(RULO, NEBR., TO MOUTH) 
Location. On both banks of Missouri River 
from Sioux City, Iowa, about 760 miles to mouth 
near St. Louis, Missouri. Portion of project in 
Kansas City District extends from Rulo, Nebraska, 
498 miles to mouth. 
Existing project. A series of levee units and 
appurtenant works along both sides of Missouri 
River from Sioux City, Iowa, to the mouth, for 
protection of agricultural lands and small 
communities against floods. Cost estimate (1975) 
for active portion of project from Rulo, Nebraska, 
to mouth is $162,300,000, of which $147,100,- 
000 is Federal cost for construction and $15,200,- 
000 for lands and damages to be borne by local 
interests. Remaining portion of project consists 
of units on which planning and construction were 
deferred pending completion of restudy to assure 
that additional levee construction is economically 
justified. One unit, R 414, is in the "deferred" 
category. Cost estimate for deferred and inactive 
portion of project Rulo, Nebraska, to mouth is 
$253,558,000, of which $233,412,000 is Federal 
cost for construction and $20,146,000 for lands 
and damages to be borne by local interests. Unit 
prices for the deferred unit are based on 1964 
price levels. Unit prices for the inactive units are 
based on 1964 price levels. (See table 20-C for 
authorizing legislation.) 
Local cooperation. Section 3, Flood Control 
Act of 1936, applies. Fully complied with for all 
completed units and units under construction. 
Sponsor for Unit L 246 has filed Commissioner's 
report for the amended Plan of Reclamation and 
has option to purchase all rights-of-way. Sponsor 
for Unit L 345-330 has settled major part of 
condemnations for right-of-way acquisition. The 
District advised the sponsor to suspend further 
condemnation proceedings pending development 
of an alternate plan to lessen the adverse impact 
on the environment. 
Operations and results during fiscal year. 
Regular funds, new work: Planning and studies 
on unconstructed units continued at a cost of 
$245,046. 
Condition at end of fiscal year. Construction of 
project was initiated in June 1948. Status of 
individual units of active portion of project at end 
of fiscal year is shown in table 20-F on Missouri 
River levee system. 
24. ONAGA LAKE, VERMILLION CREEK, 
KANS. 
Location. The project is located on Vermillion 
Creek in Pottawatomie County, Kansas, about 35 
miles northwest of Topeka, Kansas. 
Existing project. Preliminary plans provide for 
an earthfill dam about 8,600 feet long and about 
90 feet high above valley floor with an 
uncontrolled service spillway. The total reservoir 
storage capacity would be 328,000 acre-feet 
(217,000 for flood control, 21,000 for sediment 
reserve, and 90,000 multipurpose storage for 
water supply and recreation). Local interests will 
be required to make reimbursement for water 
supply storage in the estimated amount of 
$15,585,000. Project was authorized by 1962 
Flood Control Act (S. Doc. 122, 87th Cong., 2d 
sess.). Estimated Federal cost of construction 
(1975) is $57,200,000. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. Reimbursement will be 
required for water supply storage to be provided 
in accordance with Water Supply Act of 1958. 
Operations and results duiring fiscal year. 
Regular funds, new work: Preconstruction 
planning advanced to 90 percent completion. 
Condition at end of fiscal year. Preconstruction 
planning was underway and nearing completion. 
25. PATTONSBURG LAKE, GRAND RIVER, 
MO. 
Location. Damsite is on Grand River, a major 
tributary of Missouri River, in north-central 
Missouri about 5 miles upstream from Gallatin, 
Missouri, in Daviess County. Lake would extend 
upstream into DeKalb, Gentry, and Harrison 
Counties. 
Existing project. Preliminary plan provides for 
an earthfill dam about 6,500 feet long and about 
103 feet high with an uncontrolled service 
20-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
spillway in right abutment. Total reservoir 
storage capacity would be 2,720,000 acre-feet 
(1,430,000 for flood control, 334,000 for sediment 
reserve, and 956,000 of multipurpose storage for 
recreation and supplemental water supply for 
water quality control and other related purposes). 
Project was authorized by 1965 Flood 
Control Act (H. Doc. 241, 89th Cong., 1st sess.). 
Estimated cost (1973) is $167,870,000 including 
$27,200,000 for raising Interstate Highway 35 
crossing above the proposed lake and $7,670,000 
for relocation of the town of Pattonsburg, 
Missouri. 
The Public Works Appropriation Act, 1967, 
included funds to initiate advance participation 
with the Missouri State Highway Commission in 
constructing Interstate Highway 35 to an 
elevation that will provide adequate clearance 
over the Pattonsburg Lake pool, thereby 
eliminating necessity for subsequent raising. 
The town of Pattonsburg is to be relocated 
prior to appropriation of construction funds for 
the lake. Preliminary site would be along Interstate 
Highway 35 two miles northeast of its 
present location. 
Local cooperation. The State of Missouri has 
been authorized by the Bureau of Public Roads to 
acquire rights-of way in the vicinity of the lake 
and determination of rights-of-way requirements 
is complete. 
Operations and results during fiscal year. 
Preliminary results of the Grand River basin 
reanalysis which was initiated in the fall of 1973 
to determine the effects of changed economic 
conditions in the basin on authorized projects 
indicated that the most favorable of the 
Pattonsburg Lake alternatives was so marginal 
economically that a recommendation for construction 
of the project was unlikely. With 
construction of Pattonsburg Lake unlikely, the 
State of Missouri is proceeding with plans to 
construct a low level crossing for Interstate 
Highway 35 in the Pattonsburg area. 
Condition at end of fiscal year. A reanalysis of 
the Grand River Basin plan was underway. 
26. PERRY LAKE AREA (ROAD 
IMPROVEMENTS), KANS. 
Location. The proposed road improvements 
are in three segments at different locations in 
Jefferson County, Kansas, around the Perry 
Lake area. Segment A extends from U. S. Highway 
24 at Perry, Kansas, 2.5 miles north and 
west to the east end of the Perry damsite access 
road. Segment B extends from the north side of 
the Jefferson Point State Park north and west 
about 5.5 miles to highway K-92 about 2 miles 
west of Ozawkie, Kansas. Segment C extends 
from K-92, about 2 miles east of Ozawkie, north 
about 8.1 miles to highway K-4, K-16, about 2 
miles east of Valley Falls, Kansas. Total 
improvement length is about 16.1 miles. 
Existing project. Plans call for improving 
segments A and B to existing Kansas State 
Highway Commission secondary road standards 
for roads with an average daily traffic (ADT) of 
400 to 750. Segment C will be improved to the 
State standards for roads with a 100 to 250 ADT. 
Additional right-of-way required for this project 
was authorized to be acquired at Federal 
expense. Project was authorized by River Basin 
Monetary Authorization Act of 1971 (Public Law 
92-222). Estimated Federal cost of construction 
(1975) is $4,920,000. 
Local cooperation. County to maintain roads 
after completion. 
Operations and results during fiscal year. 
Design memorandum for additional road rightsof-
way to be acquired was completed. Preparation 
of plans, by contract, was underway. 
Condition at end of fiscal year. Preparation of 
plans was essentially completed. 
27. PERRY LAKE, DELAWARE RIVER, 
KANS. 
Location. Damsite is on Delaware River about 
5 miles above mouth in Jefferson County, 
Kansas, and about 3 miles north of Perry, 
Kansas. 
Existing project. An earthfill dam about 7,750 
feet long constructed to an elevation about 95 
feet above valley floor with gated-outlet works 
and an uncontrolled spillway in left abutment. 
Total reservoir storage capacity is 770,000 
acre-feet (480,000 for flood control, 140,000 for 
sediment reserve and 150,000 of multipurpose 
storage for water supply, water quality control, 
and recreation). Water supply storage is included 
in project plan at request of State of Kansas 
under provisions of Federal Water Supply Act of 
1958. Local interests will be required to make 
reimbursement for water supply storage in the 
estimated amount of $8,290,000. Project is a unit 
of the Pick-Sloan Missouri Basin program for 
flood control and other purposes in Missouri 
River Basin, authorized by 1954 Flood Control 
Act (H. Doc. 642, 81st Cong., 2d sess.). Initial 
cost of constructing the completed project was 
$47,928,394. Total estimated Federal cost of 
project (1975) including $816,000 supplemental 
recreational development (Code 710) is $48,744,- 
394. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
20-12

KANSAS CITY, MO., DISTRICT 
Operations and results during fiscal year. 
Regular funds, new work: A portion of embankment 
of the railroad relocation work has failed. 
Under the five-year maintenance clause in this 
contract the government is liable for cost to 
repair this failure. Engineering studies for this 
work were initiated at a cost of $12,140. 
Construction contracts for development of public 
use areas were completed at a cost of $5,163. 
Engineering and design and supervision and 
administration of construction was accomplished 
by hired labor at a cost of $3,683. Supplemental 
recreation facilities consisting of construction 
contract for changehouse and camp pads in two 
areas by hired labor forces were completed at a 
cost of $52,266. Maintenance: Master plan 
revision by contract, was completed at a cost of 
$6,965. Hired labor work in connection with 
Master Plan revision amounted to $11,470. Hired 
labor forces accomplished renewal of oil packing 
glands and road resealing at a cost of $4,098. 
Road repair by contract was completed at a cost 
of $147,483. Forestry development and maintenance 
were performed, by contract, with U. S. 
Forest Service at a cost of $34,692. Purchases of 
riding mower, two walkie-talkies and miscellaneous 
office, grounds, reservoir, garage, and shop 
equipment totaled $13,337. Routine operation, 
ordinary maintenance, engineering and design, 
and supervision and administration, cost $547,- 
098. Income from sale of water, collections for 
subsistence, quarters, services, etc., totaled 
$2,960. Proceeds from rentals of reservoir lands 
and recreational fees of $68,706 were deposited 
in the U. S. Treasury. Local governmental units 
will be paid 75 percent of the $50,767 received 
from lease rentals. 
Condition at end of fiscal year. Construction 
began in March 1964 and all construction has 
been completed except for recreation facilities. 
Fee simple title has been acquired for 39,327 
acres of real estate and flowage easement 
acquired on 3,207 acres. Construction of supplemental 
recreation facilities is underway. 
28. PICK-SLOAN MISSOURI BASIN 
PROGRAM (KANSAS CITY DIST.) 
Location. Flood control improvements included 
in this project are on and along Missouri 
River and several principal tributaries of 
Missouri River and in States comprising Missouri 
River Basin. 
Existing project. The Pick-Sloan Missouri 
Basin program for flood control and other 
purposes in Missouri River Basin provides for 
levees along Missouri River between Sioux City, 
Iowa, and the mouth, flood-protection works at 
certain municipalities, and reservoirs on main 
stem of Missouri River and on tributaries for 
control of floodflows at damsite. (See table 20-C 
for authorizing legislation.) (See also table 20-G 
on Kansas City District projects included in 
Pick-Sloan Missouri Basin program.) 
Operations and results during fiscal year. 
Regular funds, new work: Operations, together 
with costs and expenditures, for those projects 
on which plans were in preparation or construction 
was initiated, are shown in individual 
reports. Under sections 7 and 9, 1944 Flood 
Control Act, the Corps is responsible for detailed 
scheduling of operations of storage capacity 
reserved for or assigned to flood control in 
reservoirs constructed by Bureau of Reclamation 
as well as those constructed by the Corps. 
Maintenance (scheduling of flood control reservoir 
operation) cost $218,167. 
Condition at end of fiscal year. See individual 
reports. 
29. POMME DE TERRE LAKE, POMME DE 
TERRE RIVER, MO. 
Location. Dam is on main stem of Pomme de 
Terre River, about 44 miles above mouth of 
stream in Hickory County, Missouri, lake 
extending upstream into Polk County, Missouri. 
Site is about 3 miles south of Hermitage, 
Missouri, and 20 miles north of Bolivar, Missouri. 
Existing. project. An earth and rockfill dam 
about 4,630 feet long constructed to about 155 
feet above riverbed and a dike section on left 
abutment about 2,790 feet long, impounds 
floodwater within reservoir which provides 
storage capacity of 650,000 acre-feet (407,000 for 
flood control and 243,000 for sedimentation and 
multipurpose). Project is a unit of the Pick- 
Sloan Missouri Basin program for flood control 
and other purposes in Missouri River Basin, 
authorized by 1938 Flood Control Act (Flood 
Control Committee Doc. 1, 75th Cong., 1st sess.), 
as modified by Flood Control Acts of December 
22, 1944, and September 3, 1954 (H. Doc. 475, 
and S. Does. 191 and 247, 78th Cong., 2d sess. 
and H. Doc. 549, 81st Cong., 2d sess.). Initial cost 
of constructing the completed project was 
$14,954,952. Total estimated Federal cost of 
project (1975) including $329,140 area redevelopment 
and $1,924,000 supplemental recreational 
development (Code 710) is $17,208,092. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: Supplemental recreation 
facilities work consisting of construction 
by hired labor of camp pads and privy at a cost of 
$8,326 and initiation of plans and specifications 
20-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
for construction of shower-latrine building at a 
cost of $11,706. Supervision and administration 
amounted to $3,169. Maintenance: Cost of 
contract with U. S. Forest Service for development 
and maintenance was $30,600. Installation 
of bearings in the emergency gate was initiated 
by contract at a cost of $3,558. Boundary 
marking was performed by contract at a cost of 
$105,005. Installation of piezometer tubes was 
completed at a cost of $9,869. Purchases of a 
rotary mower, pump, compactor roller and 
miscellaneous office, ground, reservoir, garage, 
and shop equipment totaled $13,426. Routine 
operation, ordinary maintenance, real estate 
management services, and supervision and administration, 
cost $429,237. Income from collections 
for subsistence, quarters, services, etc., 
totaled $1,527. Proceeds from rentals of reservoir 
lands and recreational fees of $38,813 were 
deposited in the U. S. Treasury. Local governmental 
units will be paid 75 percent of the $8,909 
received from lease rentals. 
Condition at end of fiscal year. Construction of 
project was initiated January 1957 and placed in 
operation in October 1961. Project is complete. 
Construction of supplemental recreation facilities 
is underway. 
30. POMONA LAKE, ONE HUNDRED TEN 
MILE CREEK, KANS. 
Location. Dam is on One Hundred Ten Mile 
Creek, a tributary of Marais des Cygnes (Osage) 
River, 7 miles above mouth of stream in Osage 
County, Kansas, about 7 miles northwest of 
Pomona, Kansas, and 34 miles upstream from 
Ottawa, Kansas. 
Existing project. An earthfill dam 7,750 feet 
long constructed to an average height of about 85 
feet above streambed, with gated-outlet works 
and an ungated chute-type spillway near left 
abutment. Total reservoir storage capacity is 
230,000 acre-feet (160,000 for flood control, 
14,000 for sediment reserve, and 56,000 of 
multipurpose storage for water quality control 
and recreation). This project is a unit of 
Pick-Sloan Missouri Basin program for flood 
control and other purposes in Missouri River 
Basin, authorized by 1954 Flood Control Act (H. 
Doc. 549, 81st Cong., 2d sess.). Initial cost of 
constructing the completed project was $13,272,- 
108. Total estimated Federal cost of project 
(1975) including $755,000 supplemental recreational 
development (Code 710) is $14,027,108. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: Supplemental recreation 
facilities consisting of site preparation and 
acquisition of materials, by hired labor forces, for 
erection of a metal shower-latrine building was 
accomplished at a cost of $9,210. Plans and 
specifications for supplemental recreation facilities 
in three recreation areas were completed by 
contract and hired labor at a cost of $38,379. 
Supervision and administration was accomplished 
at a cost of $3,022. Maintenance: Master 
plan revision, by contract, was completed at a 
cost of $1,044. The administration building roof 
damaged by high winds was repaired by contract 
at a cost of $3,455. Forestry development and 
maintenance was accomplished, by contract, at a 
cost of $15,000. Costs for procurement of a rotary 
mower, pump, tractor and miscellaneous office, 
grounds, reservoir, garage and shop equipment 
totaled $15,075. Hired labor activities consisted 
of road resealing and wind damage repair in the 
administrative area accomplished at a cost of 
$21,624. Routine operation, ordinary maintenance, 
real estate management services, and 
supervision and administration cost $386,354. 
Income from collections for subsistence, quarters, 
services, etc. totaled $1,310. Proceeds from 
sale of water, rentals of reservoir lands, and 
recreational fees of $15,423 were deposited in the 
U. S. Treasury. Local governmental units will be 
paid 75 percent of the $10,058 received from 
lease rentals. 
Condition at end of fiscal year. Construction 
began July 1959 and project was placed in 
operation in October 1963. Construction of 
supplemental recreation facilities is underway. 
31. RATHBUN LAKE, CHARITON RIVER, 
IOWA 
Location. Damsite is on Chariton River about 7 
miles north of Centerville and 1 mile north of 
town of Rathbun, Appanoose County, Iowa. 
Existing project. An earthfill dam 10,600 feet 
long constructed to an elevation about 86 feet 
above valley floor, with gated-outlet works and 
an uncontrolled service chute with paved sill 
spillway about a mile upstream from left 
abutment. Total reservoir storage capacity is 
552,000 acre-feet (339,000 for flood control, 
24,000 for sediment reserve and 189,000 of multipurpose 
storage for navigation, water quality 
control, and recreation). Project authorized by 
1954 Flood Control Act (H. Doc. 561, 81st Cong., 
2d sess.). Initial cost of constructing the 
completed project was $27,036,000. Total estimated 
Federal cost of project (1975) including 
$373,000 supplemental recreational development 
(Code 710) is $27,409,000. 
Local cooperation. Section 2, Flood Control 
20-14

KANSAS CITY, MO., DISTRICT 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: The contract for repair 
of roads damaged during construction was 
completed. Maintenance: Forestry development 
and maintenance was accomplished by contract 
with U. S. Forest Service at a cost of $54,200. 
Procurement of an equipment trailer and 
miscellaneous office, ground, reservvoir, garage 
and shop equipment totaled $12,085. Routine 
operation, ordinary maintenance, supervision 
and administration cost $407,041. Income from 
collections for subsistence, quarters, services, 
etc., and crop disposal, amounted to $6,697. 
Proceeds of $105,875 were deposited in the U. S. 
Treasury. Local governmental units will be paid 
75 percent of the $44,014 received from lease 
rentals. 
Condition at end of fiscal year. Construction of 
project began September 26, 1964. Land acquired 
consists of 33,908 acres in fee simple and 
2,164 acres in flowage and road easements. The 
project is completed except for consummating a 
water supply contract. Supplemental recreation 
facilities have not been initiated to date. 
32. RATHBUN LAKE (FISH HATCHERY), 
IOWA (1974 MOD.) 
Location. Downstream from Rathbun Lake. 
Existing project. Payment to Iowa Conservation 
Commission in contribution toward cost of a 
fish hatchery to be constructed for the purpose of 
restoring fish losses resulting from the construction 
of Rathbun, Saylorville, Coralville and Red 
Rock Lakes in Iowa. Section 102 of the Water 
Resources Development Act of 1974 authorized 
this work as a modification of the project 
authorization for Rathbun Lake. The original 
project was authorized by the 1954 Flood Control 
Act. Federal contribution for the Fish Hatchery 
is $700,000. 
Local cooperation. The Fish Hatchery will be 
constructed by the Iowa Conservation Commission. 
Condition at end of fiscal year. Official ground 
breaking for construction of the Fish Hatchery 
by the Iowa Conservation Commission was held 
in March 1974. The Federal contribution of 
$700,000 was made in June 1975. 
33. SMITHVILLE LAKE, LITTLE PLATTE 
RIVER, MO. 
Location. Damsite is on Little Platte River 
about 1 mile northeast of Smithville and about 5 
miles north of Kansas City, in Clay and Clinton 
Counties, Missouri. 
Existing project. Plans provide for an earthfill 
dam about 4,200 feet long and 95 feet high with 
an uncontrolled service spillway. A dike about 
2,000 feet long would be constructed across a 
saddle in left abutment. Total reservoir storage 
capacity would be 246,500 acre-feet (92,000 for 
flood control, 52,300 for sediment reserve, and 
102,200 of multipurpose storage for water 
supply, water quality control, and recreation). 
Local interests will be required to make reimbursement 
estimated at $2,060,000 for water 
supply storage and $5,394,000 for recreation cost 
sharing. Project was authorized by 1965 Flood 
Control Act (H. Doc. 262, 89th Cong., 1st sess.). 
Estimated Federal cost of construction (1975) is 
$68,100,000. 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938, applies. Reimbursement 
will be required for water supply storage to be 
provided in accordance with Water Supply Act of 
1958 and for recreation provided in accordance 
with Federal Water Project Recreation Act of 
1965. 
Operations and results during fiscal year. 
Regular funds, new work: Land acquisition 
consisted of 2,702 acres in fee and 8 acres flowage 
easements at a cost of $3,287,000. Contract for 
construction of the dam and access roads was 
advanced to 50 percent complete at a cost of 
$5,637,000. A contract for boundary, surveys and 
marking was awarded and advanced to 97 
percent complete at a cost of $47,000. A contract 
with the Missouri State Highway Commission 
was initiated at a cost of $174,000. Engineering 
and design, by contract, was accomplished at a 
cost of $34,000. Hired labor operations consisted 
of installation of observation devices, real estate 
management, engineering and design and supervision 
and administration at a cost of $744,000. 
Purchase of permanent operating equipment was 
initiated at a cost of $5,000. 
Condition at end of fiscal year. Lands totaling 
7,572 acres in fee and 54 acres of flowage easements 
have been acquired. Construction of the 
dam and access roads was 50 percent complete. 
The boundary, surveys and marking contract 
was 97 percent complete. Planning was underway 
for other construction features. 
34. TOMAHAWK LAKE, BLUE RIVER, 
KANS. 
Location. The damsite for the project is located 
on Tomahawk Creek immediately upstream of 
115th Street in Leawood, Johnson County, 
Kansas; the lake is located in Leawood and 
Overland Park, Kansas. 
Existing project. Preliminary plans provide for 
20-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
an earthfill dam about 2,850 feet long and 80 feet 
high with an uncontrolled outlet through the dam 
and an uncontrolled service spillway. Preliminary 
plans are based on a total storage capacity 
of 35,900 acre-feet, with 15,800 acre-feet for flood 
control, 15,300 acre-feet for future water supply, 
recreation and releases for the preservation of 
fish, wildlife and esthetics and 4,800 acre-feet for 
sediment reserve. Local interest will be required 
to make reimbursement estimated at $6,570,000 
for recreation cost sharing and $4,200,000 for 
water supply. Project was authorized by 1970 
Flood Control Act (H. Doc. 332, 91st Cong. 2d 
sess.). Estimated Federal cost of construction 
(1975) is $44,400,000. 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938 applies. Reimbursement will 
be required for recreation provided in accordance 
with Federal Water Project Recreation Act of 
1965. Reimbursement will be required for water 
supply provided in accordance with the Water 
Supply Act of 1958. 
Operations and results during fiscal year. 
Regular funds, new work: Phase I General 
Design Memorandum, Recreation Resources 
Appendix and Surveying and Mapping have been 
completed. Phase II General Design Memorandum 
was begun. 
Condition at end of fiscal year. A review to 
evaluate recent developments relative to the 
Blue River system was conducted during the 
latter part of FY 1975. A report on this review 
recommended that the Tomahawk Lake project 
be placed in an inactive status. 
35. TUTTLE CREEK LAKE, BIG BLUE 
RIVER, KANS. 
Location. Dam is on main stem of Big Blue 
River, about 12 miles above mouth of stream in 
Riley and Pottawatomie Counties, Kansas. Site 
is about 12 miles northwest of Manhattan, 
Kansas. 
Existing project. A dam 7,500 feet long and 
157 feet high. Project is unit of the Pick-Sloan 
Missouri Basin program for flood control and 
other purposes in Missouri River Basin authorized 
by 1938 Flood Control Act (Flood Control 
Committee Doc. 1, 75th Cong., 1st sess.), as 
modified by 1941 Flood Control Act, and 
expanded by Flood Control Act of December 22, 
1944 (H. Doc. 475, and S. Does. 191 and 247, 78th 
Cong., 2d sess.). Total reservoir storage capacity 
is 2,346,000 acre-feet (1,933,000 for flood control, 
228,000 for sediment reserve and 185,000 for 
multipurpose storage, low flow regulation, and 
recreation). Initial cost of constructing the 
completed project was $80,051,031. Total estimated 
Federal cost of project (1975) including 
$369,000 supplemental recreational development 
(Code 710) is $80,420,031. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: Supplemental recreation 
facilities consisted of completion of construction 
of comfort station at a cost of $5,604. 
Maintenance: Work performed by contract included 
boundary monumentation, $147,712; stilling 
basin repair, $218,300; installation of seismic 
instrumentation, $11,958; forestry development 
and maintenance by U. S. Forest Service, 
$20,000 and road repair, $122,391. Hired labor 
forces accomplished installation of seismic instrumentation, 
$2,388; archaeological salvage, 
$1,000; boundary marking $3,784; and road 
resealing, $14,078. Wind study equipment and 
miscellaneous office, grounds, reservoir, garage 
and shop equipment were replaced at a cost of 
$7,939. Routine operation, ordinary maintenance, 
real estate management services, engineering 
and design and supervision and administration 
cost $446,841. Proceeds from rentals of 
reservoir lands and recreation fees of $8,191 
were deposited in the U. S. Treasury. Local 
governmental units will be paid 75 percent of the 
$6,885 received from lease rentals. 
Condition at end of fiscal year. Construction of 
project began in October 1952 and the project 
was placed in operation in fiscal year 1963. 
Project is complete. Construction of supplemental 
recreation facilities is underway. 
36. TUTTLE CREEK LAKE (ROAD 
IMPROVEMENTS), KANS. (1974 MOD.) 
Location. The proposed road improvements 
are located in Pottawatomie County, Kansas, in 
the Tuttle Creek area. 
Existing project. The proposed plan provides 
for improving a portion of FAS 1208 road 
extending from the intersection with Kansas 
State Highway 13, in section 5, township 9 south, 
range 8 east, thence north and west to the 
intersection with county road in section 14, 
township 8 south, range 7 east, approximately 
5.78 miles. Section 18 of the Water Resources 
Development Act of 1974 authorized this work as 
a modification of the Tuttle Creek Lake project. 
The original project was authorized by the 1938 
Flood Control Act as modified. The Federal cost 
of construction is limited to $500,000 and 
estimated non-Federal cost is $214,300. 
Local cooperation. Pottawatomie County, by 
letter dated 29 July 1974, indicated their intent 
to sponsor the project. Pottawatomie County will 
be required to provide at least 30 percent of the 
20-16

KANSAS CITY, MO., DISTRICT 
project cost. Operations and results during fiscal 
year. Regular funds, new work: Road improvement 
design memorandum was initiated and 
underway. 
Condition at end of fiscal year. Preconstruction 
planning work was underway. 
37. WILSON LAKE, SALINE RIVER, KANS. 
Location. Dam is on Saline River about 130 
miles above its mouth, near eastern edge of 
Russell County, Kansas, about 50 miles west of 
Salina, 10 miles north of Wilson, and 20 miles 
east of Russell, Kansas. 
Existing project. An earthfill dam about 5,600 
feet long and 160 feet high with a gated-outlet 
works, chute spillway, and structural provision 
for irrigation. Total reservoir storage capacity is 
776,000 acre-feet (511,000 for flood control, 
40,000 for sediment reserve and 225,000 multipurpose 
storage for irrigation and low flow 
regulation). Project is a unit of the Pick-Sloan 
Missouri Basin program for flood control and 
other purposes in Missouri River Basin, authorized 
by 1944 Flood Control Act (H. Doc. 475, and 
S. Docs. 191 and 247, 78th Cong., 2d sess.). 
Report of Chief of Engineers on justification of 
Wilson Dam and Reservoir, submitted in 
compliance with Public Law 505, 84th Congress, 
published as Senate Document 96, 86th Congress, 
was approved July 14, 1960 (Public Law 
645, 86th Cong.). Initial cost of constructing the 
completed project was $20,015,023. Total estimated 
Federal cost of project (1975) including 
$125,000 supplemental recreational development 
(Code 710) is $20,140,023. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, maintenance: Work performed by 
contract consisted of master plan revision, $6,976 
and forestry development and maintenance by 
U. S. Forest Service, p15,000. Hired labor forces 
repaired sandstone drains, $643; modified low 
flow gate, $3,823; and repaired road, $2,458. 
Hired labor work, in connection with master plan 
revision by contract, amounted to $5,350. An 
equipment trailer, riding mower and miscellaneous 
office, ground, reservoir, and shop equipment 
were replaced at a cost of $11,969. Routine 
operation, ordinary maintenance, real estate 
management services, and supervision and 
administration cost $330,056. Income from collections 
for subsistence, quarters, services, etc., 
crop disposals and other income totaled $3,653. 
Proceeds from rentals of reservoir lands and 
recreational fees of $27,016 were deposited in the 
U. S. Treasury. Local governmental units will be 
paid 75 percent of the $10,489 received from 
lease rentals. 
Condition at end of fiscal year. Construction of 
project began April 1, 1961, and project was 
placed was placed in operation January 1, 1965. 
Land acquisition was 21,481 acres in fee simple 
and 12,526 acres in flowage and access road 
easements. Construction of supplemental recreation 
facilities is underway. 
38. WOLF-COFFEE LAKE, BLUE RIVER, 
KANS. 
Location. The project is located across the 
junction where Coffee and Wolf Creeks conjoin to 
form the Blue River immediately west of new 
U. S. Highway 69 and about 3 miles south of 
Stanley, in Johnson County, Kansas. 
Existing project. Preliminary plans provide for 
an earthfill dam about 4,800 feet long and 109 
feet high with an uncontrolled outlet through the 
dam and an uncontrolled service spillway. 
Preliminary plans are based on a total storage 
capacity of 67,300 acre-feet (29,200 for flood 
control, 29,000 acre-feet are for recreation, 
water supply, and releases for the preservation 
of fish, wildlife and esthetics, and 9,100 for the 
sediment reserve). Local interest will be required 
to make reimbursement estimated at 
$6,750,000 for recreation cost sharing and 
$7,200,000 for water supply. Project was 
authorized by 1970 Flood Control Act (H. Doc. 
332, 91st Cong., 2d sess.). Estimated Federal 
cost of construction (1975) is $51,500,000. 
Local cooperation. Section 2, Flood Control 
Act of June 28, 1938, applies. Reimbursement 
will be required for recreation provided in 
accordance with Federal Water Project Recreation 
Act of 1965. 
Operations and results during fiscal year. 
Regular funds, new work: Real estate, geology, 
construction materials and Phase II Design 
Memorandums were underway. 
Condition at end offiscal year. Preconstruction 
planning was approximately 50 percent complete. 
39. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and 
subsequent acts require local interests to furnish 
assurances that they will maintain and operate 
certain local protection projects after completion 
in accordance with regulations prescribed by the 
Secretary of the Army. District Engineers are 
responsible for administration of these regulations 
within boundaries of their respective 
district. (See table 20-H on inspection of 
20-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
completed flood control projects.) 
Fiscal year cost was $141,730. 
40. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
See table 20-I. 
41. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation) 
Federal costs for fiscal year were $145,911 for 
advance preparation, $54,964 for emergency 
operations, and $667,707 for rehabilitation. 
Emergency Bank Protection (Sec. 14, 1946 
Flood Control Act, Public Law 526, 79th Cong., 
July 24, 1946) as amended. 
Operations under this heading were as follows: 
Villisca, Iowa-During the fiscal year construction 
was completed on an emergency bank 
protection project to protect the sewage treatment 
at Villisca, Iowa. The plant was threatened 
by erosion by the Nodaway River. Fiscal year 
cost was $4,895. 
Saline River, Tescott, Kansas-A project was 
constructed to provide protection for Tescott, 
Kansas, sewage lift station. The lift station was 
threatened by erosion caused by the Saline 
River. Fiscal year cost was $21,518. 
Big Nemaha River, Nebraska-During "the 
fiscal year plans and specifications were drafted 
for an authorized project to provide protection 
for a county bridge in Richardson County, 
Nebraska. Fiscal year costs were $928. 
Long Branch Creek, Nebraska-During the 
fiscal year plans and specifications were drafted 
for an authorized project to provide protection 
for a bridge in the city of Humboldt, Nebraska. 
Fiscal year costs were $998. 
North Fork of Big Nemaha River, Nebraska- 
During the fiscal year plans and specifications 
were drafted for an authorized project to provide 
protection for a county bridge in Richardson 
County, Nebraska. Fiscal year costs were $812. 
Nodaway River, Iowa-Negative feasibility 
reports were prepared on eight proposed 
projects to protect county bridges in Adams and 
Page Counties in Iowa. Fiscal year costs were 
$3,752. 
Nodaway River, Missouri-A negative feasibility 
report was prepared for a proposed project 
to protect county bridge in Nodaway County in 
Missouri. Fiscal year costs were $353. 
102 River, Missouri-Negative feasibility reports 
were prepared on two proposed projects to 
protect county bridges in Andrew County, 
Missouri. Fiscal year costs were $4,193. 
Smoky Hill River, Kansas-A negative feasibility 
report was prepared for a proposed project 
to protect city sewage lagoon in Assaria, Kansas. 
Fiscal year costs were $859. 
Republican River, Kansas-A negative feasibility 
report was prepared for a proposed project 
to protect a county bridge over Pete's Creek at 
Clifton, Kansas, in Washington County, Kansas. 
Fiscal year costs were $910. 
Wakarusa River, Kansas-A negative feasibility 
report was prepared for a proposed project 
to protect city water wells at Eudora, Kansas. 
Fiscal year costs were $1,237. 
Snagging and Clearing (Sec. 208, 1954 Flood 
Control Act, Public Law 780, 83d Cong.) 3 
September 1954, as amended. 
Operations during the fiscal year under this 
heading consisted of an Architect-Engineer (AE) 
firm conducting snagging and clearing studies on 
5 projects as follows: 
Crooked Creek, Red Cloud, Nebraska-AE 
conducted field reconnaissance and flood damage 
investigations and initiated work on an Effect 
Assessment. Fiscal year cost was $14,028. 
Big Blue River, Saline-Seward Counties, 
Nebraska-AE made initial field reconnaissance 
and flood damage investigations and initiated 
work on the Effect Assessment. Fiscal year cost 
was $6,841. 
Big Blue River, Saline-Gage Counties, Nebraska-
AE made initial field reconnaissance 
and flood damage investigations and initiated 
work on the Effect Assessment. Fiscal year cost 
was $7,053. 
South Grand River, Henry County, Mo.-AE 
conducted field reconnaissance of the project 
area. Fiscal year cost was $627. 
South Grand River, Bates and Cass Counties, 
Mo. - AE conducted field reconnaissance of the 
project area. Fiscal year cost was $657. 
Small Flood Control Projects Not Specifically 
Authorized by Congress (Sec. 205, 1948 Flood 
Control Act, Public Law 858, 80th Cong., June 
30, 1948) as amended. See detailed reports for 
operation at Elk Creek at Clyde, Kansas and 
Gypsum, Kansas. Negative reports were completed 
for five other locations at a cost of $6,933. 
Multiple Purpose Projects Including Power 
42. HARRY S. TRUMAN DAM AND 
RESERVOIR, OSAGE RIVER, MO. 
20-18

KANSAS CITY, MO., DISTRICT 
Location. Damsite is on main stem of Osage 
River about 1.5 miles northwest of Warsaw, 
Benton County, Missouri. Reservoir extends into 
Bates, Henry, Hickory, St. Clair, and Vernon 
Counties, Missouri. 
Existing project. Provides for an earthfill dam 
about 5,000 feet long to be constructed to an 
average height of about 96 feet, including a 
gate-controlled overfall spillway section and a 
power installation consisting of six inclined 
pump-generating units with capacity of 160,000 
kilowatts. Reservoir storage capacity would be 
5,202,000 acre-feet (3,918,000 for flood control, 
244,000 for sediment reserve, and 1,040,000 
multipurpose storage for power, low-flow regulation, 
and recreation). This project is a unit of the 
Pick-Sloan Missouri Basin program for flood 
control and other purposes in Missouri River 
basin. Project was authorized by 1954 Flood 
Control Act (H. Doc. 549, 81st Cong., 2d sess.), 
as modified by 1962 Flood Control Act (H. Doc. 
578, 87th Cong., 2d sess.). Estimated cost (1975) 
is $413 million. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: Relocation of Minuteman 
Communication Cable affected by road 
relocations was accomplished by Whiteman Air 
Force Base at a cost of $5,331. Forestation 
planning was continued by the U. S. Forest 
Service at a cost of $17,000. Selective clearing 
was accomplished at a cost of $12,357. Permanent 
operating equipment was procured at a cost 
of $5,531. Design work was accomplished by 
contract at a cost of $308,358. Contracts for 
relocation of State and county roads were 
continued at a cost of $12,947,022. Relocation of 
Missouri-Kansas-Texas Railroad lines was initiated, 
by contract, at a cost of $605,200. 
Relocation of cemeteries was continued at a cost 
of $2,372. Work under contract for relocation of 
municipal facilities of the city of Osceola was 
continued at a cost of $1,937. Work under 
contract for relocation of municipal facilities of 
the city of Clinton was initiated at a cost of 
$87,839. Boundary resurveying, by contract, was 
initiated at a cost of $442,764. Stage III 
construction of spillway, powerplant substructure, 
and continuation of embankment was continued 
at a cost of $1,525,280. Contract for 
procurement of turbines was continued at a cost 
of $2,227,735. Stage IV construction of Sterrett 
Creek embankment was continued and 67 
percent of the work completed at a cost of 
$3,185,800. Procurement of generators and other 
powerplant equipment was continued at a cost of 
$1,816,795. Stage V construction for completion 
of the powerhouse was initiated and 15 percent of 
the work completed at a cost of $7,639,288. Hired 
labor operations consisted of installation of 
boundary surveys and marking, observation 
devices, real estate management, provision of 
temporary construction facilities, preparation of 
as-built drawings, engineering and design, and 
supervision and administration of construction at 
a cost of $3,663,876. Land acquisition consisted of 
11,309 acres of land in fee simple and 8,660 acres 
flowage, road and railroad rights-of-way easements 
at a cost of $8,674,219. 
Condition at end of fiscal year. Entire project 
is about 44 percent complete. Construction of 
relocation of Missouri Highway M-13 was 
initiated September 1964 and is complete. Three 
other contracts for relocation of State roads are 
complete. Removal of unsuitable material from 
east abutment of damsite, construction of right 
and left abutment access roads, temporary office 
and overlook, permanent operations building and 
operator's quarters, first, second, and third 
stage excavation and embankment, and three 
contracts for relocation of cemeteries are 
complete. Acquisition of 148,940 acres of land in 
fee simple and flowage, road and railroad 
rights-of-way easements acquired for 22,541 
acres. Contract for procurement of turbines is 99 
percent complete. Nine contracts for relocation 
of State and county roads are underway. 
Contracts for relocation of Missouri-Kansas- 
Texas Railroad Company's facilities are underway. 
Contract for relocation of municipal 
facilities for city of Osceola is 84 percent 
complete. Work under contract for relocation of 
municipal facilities of the city of Clinton is 5 
percent complete. Boundary surveying and 
marking, by contract and hired labor, is 
underway. Work on Stage IV construction was 
69 percent complete. Stage V construction for 
completion of the powerhouse is 15 percent 
complete. Contract was awarded for construction 
of a visitor center. Planning is underway on 
design memorandums and contract plans for 
other construction features. 
43. STOCKTON LAKE, SAC RIVER, MO. 
Location. Damsite is on Sac River about 49.5 
miles above its confluence with Osage River, and 
about 2 miles east of Stockton, Cedar County, 
Missouri, lake extending into Dade and Polk 
Counties. 
Existing project. A rock-shell dam with 
impervious core about 5,100 feet long constructed 
to an average height of about 128 feet, 
with a gated overfall spillway and a 45,200-kilowatt 
power installation. Total reservoir storage 
capacity is 1,674,000 acre-feet (774,000 for flood 
control, 25,000 for sediment reserve and 875,000 
20-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
multipurpose storage for power and recreation). 
Project is a unit of Pick-Sloan Missouri Basin 
program for flood control and other purposes in 
Missouri River Basin, authorized by 1954 Flood 
Control Act (H. Doc. 519, 81st Cong., 2d sess.). 
Initial cost of constructing the completed project 
was $74,630,300. Total estimated Federal cost of 
project (1975) including $1,200,000 for downstream 
channel work and $1,222,000 for supplemental 
recreational development (Code 710) is 
$77,052,300. 
Local cooperation. Section 2, Flood Control 
Act of 1938, applies. 
Operations and results during fiscal year. 
Regular funds, new work: Procurement of. 
powerplant equipment was continued at a cost of 
$3,250. Hired labor operations consisted of 
boundary surveys and marking, preparation of 
as-built drawings, miscellaneous operating expenses, 
engineering and design and supervision 
and administration of construction at a cost of 
$7,353. Maintenance: Work performed by contract 
consisted of road repair work and forestry 
development and maintenance accomplished at a 
cost of $139,316. Riding mower, and miscellaneous 
office, ground, reservoir and shop equipment 
were replaced at a cost of $15,919. Routine 
operation, ordinary maintenance, supervision 
and administration cost $941,326. Income from 
collections for subsistence, quarters, service, 
etc., totaled $1,832. Proceeds of $59,520 were 
deposited in the U. S. Treasury. Local governmental 
units will be paid 75 percent of the 
$19,308 received from lease rentals. 
Condition at end of fiscal year. Construction of 
project began October 1963 and project is 
essentially complete. Acquisition of 58,788 acres 
of land in fee simple and flowage easements 
acquired for 2,621 acres. Relocation of roads, 
powerlines, cemeteries, and municipal facilities 
are complete. Construction of embankment, 
access and service roads, administrative facilities, 
operators' quarters, and tree planting are 
complete. Construction of spillway and powerplant 
is complete. Contracts for procurement of 
miscellaneous powerplant equipment and relocation 
of telephone lines are underway. Remaining 
work consists of proposal to acquire flowage 
easements on land and to construct a channel 
cutoff at Horseshoe Bend downstream from the 
dam to assure downstream channel capacity of 
8,000 c.f.s. for powerplant operation. Supplemental 
recreation facilities have not been 
initiated to date. 
General Investigations 
44. SURVEYS 
Fiscal year costs were $434,021 for flood 
control studies, $37,669 for review of authorized 
projects, $32,237 for inventory of dams, and 
$17,147 for special studies. 
45. COLLECTION AND STUDY OF 
BASIC DATA 
(Flood Plain Management Services) 
Flood Plain Information Reports. 
Flood Plain Information Report on Beaver 
Creek at Atwood, Kansas, was completed in 
January 1975 and was presented to the public in 
March 1975. Fiscal year cost was $3. 
Flood Plain Information Report on Republican 
River and Unnamed Stream at McCook, Nebraska, 
was completed in October 1974. The report 
was presented to the public in February 1975. 
Fiscal year cost was $5. 
Flood Plain Information Report on Big Creek, 
Ellis, Kansas, was completed in November 1974. 
Presentation to the public was in February 1975. 
Fiscal year cost was $25. 
Flood Plain Information Report on Pottawatomie 
Creek, Volume III, Garnett to Osawatomie, 
Kansas, was completed in January 
1975. It was presented to the public in April 
1975. Fiscal year cost was $12. 
Flood Plain Information Report on Big Shoal 
Creek, Kansas City, Missouri, was completed in 
September 1974, and was presented to the public 
in January 1975. Fiscal year cost was $4. 
Flood Plain Information Report on Line Creek 
was completed in May 1975 and presented to the 
public in September 1975. Fiscal year cost was 
$5.
Flood Plain Information Report on Nodaway 
River, Clarinda, Iowa, was started in March 1974 
and will be completed in fiscal year 1976. Fiscal 
year cost was $16,587. 
Flood Plain Information Report on Kansas 
River at Edwardsville, Kansas, was started in 
March 1974 and will be completed in fiscal year 
1976. Fiscal year cost was $23,792. 
Flood Plain Information Report on Big Blue 
River at Marysville, Kansas, was started in 
October 1974, and was converted to a Flood 
Insurance Study in June 1975. Fiscal year cost 
was $29,555. 
Flood Plain Information Report on Cedar 
Creek in Johnson County, Kansas, was started in 
July 1974 and will be completed in fiscal year 
1976. Fiscal year cost was $36,513. 
Flood Plain Information Report on Little Blue 
River, Grandview, Missouri, was completed in 
June 1975. Presentation to the public will be 
made in July 1975. Fiscal year cost was $29,396. 
20-20

KANSAS CITY, MO., DISTRICT 
Flood Plain Information Report on Todd 
Creek, Kansas City, Missouri, will be completed 
in July 1975. The report will be presented to the 
public in September 1975. Fiscal year cost was 
$33,600. 
Flood Plain Information Report on Round 
Grove Creek, Kansas City, Missouri, will be 
completed in July 1975. Presentation to the 
public will be made in September 1975. Fiscal 
year cost was $24,646. 
Flood Plain Information Report on Mill Creek, 
Johnson County, Kansas, was started in June 
1974 and will be completed in fiscal year 1976. 
Fiscal year cost was $21,000. 
Flood Plain Information Report on Marais des 
Cygnes River, Volume II, Ottawa to Osawatomie, 
Kansas was presented to the public in 
April 1975. 
Technical Services. The Flood Plain Reports 
section provided site investigations and flood 
hazard evaluations to military and non-military 
Federal agencies, State and local governmental 
agencies, and to individuals and businesses, 
comprising separate inquiries. Fiscal year cost 
was $53,020. 
Special Flood Hazard Report for Deer Creek, 
Topeka, Kansas was presented to the city in 
February 1975. 
Special Flood Hazard Report for Half Day 
Creek, Topeka, Kansas was presented to the city 
in February 1975. 
Special Flood Hazard Report for Indian Creek, 
Topeka, Kansas was presented to the city in 
February 1975. 
Special Flood Hazard Report for Pawnee 
Creek, Hastings, Nebraska, was presented to the 
public in February 1975. 
Comprehensive Flood Damage Prevention 
Planning. Studies and discussions with the cities 
of Prairie Village, Kansas; Salina, Kansas; 
Kansas City, Missouri; St. Charles, Missouri; 
and Red Cloud, Nebraska, were completed. 
Studies concerning different aspects of local 
drainage is a continuing part of our program. 
Total fiscal year cost of Flood Plain Management 
Services, including $67,073 cost of the 
management services unit, was $335,236. 
20-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project Funding 
1. Missouri River, New Work: 
Sioux City, Iowa Approp. 
to Mouth (Rulo, Cost 
Nebr., to Mouth) Maint. 
(Federal Funds) Approp. 
Cost 
(Contributed New Work: 
Funds) Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Consolidated New Work: 
Summary) Approp. 
Cost 
Maint. 
Approp. 
Cost 
3. Blue River Channel New Work: 
Kansas City, Approp. 
Mo. Cost 
4. Brookfield Lake New Work: 
Yellow Creek, Approp. 
Mo. Cost 
5. Chariton-Little New Work: 
Chariton Basins, Approp. 
Mo. Cost 
6. Clinton Lake, New Work: 
Wakarusa Approp. 
River, Kans. Cost 
(Contributed New Work: 
Funds) Approp. 
Cost 
(Consolidated New Work: 
Summary) Approp. 
Cost 
7. Elk Creek, New Work: 
Clyde, Kans. Approp. 
Cost 
8. Fort Scott Lake, New Work: 
Marmaton Approp. 
River Kans. Cost 
9. Grove Lake New Work: 
Soldier Creek, Approp. 
Kans. Cost 
10. Gypsum, Gypsum New Work: 
Creek, Kans. Approp. 
Cost 
11. Harlan County New Work: 
Lake, Repubhlican Approp. 
River, Nebr. Cost 
Maint. 
Approp. 
Cost 
12. Hillsdale Lake, 
Big Bull 
Creek, Kans. 
13. Indian Lake, 
Blue River, Kans. 
Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
2,510,400 8,300,000 1,950,000 3,450,000 
2,706,279 6,187,915 3,575,136 3,910,123 
9,633,817 9,413,400 7,512,800 9,432,000 
9,447,910 7,635,091 9,418,282 9,681,990 
18,701 25,000 28,046 - 
30,595 18,701 - 28,350 
2,529,101 
2,736,874 
9,633,817 
9,447,910 
198,600 
106,526 
42,600 
56,284 
3,812,500 
3,665,729 
3,812,500 
3,665,729 
2,314 
3,594 
223,400 
237,695 
8,102 
21,598 
601,400 
585,891 
8,325,000 
6,206,616 
9,413,440 
7,635,091 
50,000 
10,000 
35,800 
90,657 
-90,000 
22,702 
7,420,000 
5,799,897 
119,048 
7,539,048 
5,799,897 
293,735 
18,643 
1,284 
308,500 
319,399 
30,000 
28,221 
388,814 
410,915 
1,978,046 
3,575,136 
7,512,800 
9,418,282 
15,000 
55,000 
30,000 
112,777 
183,000 
15,551 
6,437,000 
7,111,897 
9,900 
6,437,000 
7,121,797 
226,500 
43,611 
1,000 
931 
389,000 
297,370 
130,000 
10,789 
6,000 
393,000 
366,455 
3,450,000 
3,938,473 
9,432,000 
9,681,990 
280,000 
280,000 
25,000 
76,190 
2,090 
333,425 
8,050,000 
8,229,164 
83,410 
8,050,000 
8,312,574 
412,782 
272 
45,000 
140,064 
106,265 
211,000 
34,837 
448,350 
430,910 
303,900 505,900 700,000 2,150,000 
168,379 137,421 497,696 2,252,944 
- - - 50,000 
- - - 50,000 
20-22 
225,659,190' 
225,600,372 
199,052,5142 
198,713,4212 
808,616 
783,920 
22,642 
22,642 
226,467,8064 
226,384,292 
199,075,1565 
198,736,0635 
345,000 
345,000 
451,400 
451,128 
696,690 
636,962 
30,572,500 
29,642,995 
119,048 
93,310 
30,691,548 
29,736,305 
932,263 
881,172 
756,000 
755,273 
1,553,900 
1,550,338 
284,102 
260,462 
45,693,216 
45,535,2506 
5,210,879 
5,160,302 
1,017,623 
1,017,623 
4,453,800 
3,850,029 
50,000 
50,000

KANSAS CITY, MO., DISTRICT 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
14. Kanopolis Lake, 
Smoky Hill 
River, Kans. 
15. Kansas City, 
Kansas River, 
Kans. (62 Mod.) 
16. Lawrence, Kansas 
River, Kans. 
(Contributed 
Funds) 
(Consolidated 
Summary) 
17. Little Blue River 
Channel Improvement, 
Little Blue 
River, Mo. 
18. Little Blue River 
Lakes, Little Blue 
River, Mo. 
19. Long Branch 
Lake, Little 
Chariton River, 
Mo. 
20. Melvern Lake 
Osage (Marais des 
Cygnes) River, 
Kans. 
21. Mercer Lake, 
Weldon River, 
Mo. 
22. Milford Lake, 
Republican River, 
Kans. 
23. Missouri River 
Levee System, 
Iowa, Nebr., 
Kans., and Mo. 
24. Onaga Lake, 
Kans. 
25. Pattonsburg Lake 
Grand River, Mo. 
(Advance Highway 
Relocation) 
(Advance Town 
Relocation) 
(Consolidated 
Summary) 
26. Perry Lake Area 
(Road Improvements), 
Kans. 
Funding 
New Work: 
pprop. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Costp 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
250,100 
243,331 
1,871,600 
1,822,067 
-414,700 
240,126 
-414,700 
240,126 
134,000 
128,883 
262,600 
263,614 
2,760,000 
2,994,065 
5,000 
55,436 
2,046 
5,000 
57,482 
104,016 
25,913 
323,700 361,400 
306,776 361,676 
2,625,000 4,284,000 
1,956,961 5,478,894 
135,000 - 
45,869 66,480 
854 
135,000 
46,723 
775,000 
262,979 
2,229,200 4,680,000 4,881,000 
3,412,388 4,671,512 2,790,358 
396,500 1,420,000 1,410,200 
273,342 967,043 1,930,255 
66,480 
500,000 
491,974 
2,327,000 
4,396,514 
2,050,000 
1,702,80u 
4,898,200 5,900,000 2,645,600 115,000 
4,885,688 4,569,667 3,064,146 1,874,903 
59,600 
106,973 
450,506 
459,576 
407,400 
340,751 
2,269,500 
2,816,584 
221,400 
211,749 
296,500 
88,368 
49,700 
5,552 
346,200 
93,920 
103,000 386,500 
102,180 375,465 
160,700 46,945 
135,902 114,533 
356,247 45,000 
331,840 44,730 
439,000 685,000 
454,433 698,356 
724,000 -100,000 
487,158 171,260 
309,361 203,000 
215,400 274,929 
102,000 -991,000 
93,969 5,015 
-7,771 - 
27,072 46,846 
94,229 -991,000 
121,041 51,861 
100,000 -4,000 
- 36,058 
459,760 
458,272 
25,000 
74,829 
-2,000 
24,120 
420,400 
452,094 
223,000 
245,046 
166,000 
201,021 
1,484 
12,459 
13,943 
400,000 
146,809 
20-23 
12,538,227 
12,546,112 
3,702,510 
3,679,237 
13,207,600 
13,066,182 
4,815,300 
4,787,587 
2,900 
2,900 
4,818,200 
4,790,487 
1,678,116 
1,058,069 
18,017,200 
17,939,113 
5,576,700 
5,127,280 
36,883,810 
36,849,124 
949,260 
935,917 
432,245 
432,237 
48,543,569 
48,539,629 
3,166,724 
3,145,999 
39,470,281 
39,454,404 
1,562,761 
1,553,274 
407,500 
381,249 
91,929 
91,929 
499,429 
473,178 
496,000 
182,867

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 20-A (Continued) 
See 
Section 
in Text Project 
27. Perry Lake, 
Delaware River, 
Kans. 
28. Pick- Sloan Mo. 
Basin program 
29. Pomme de Terre 
Lake, Pomme de 
Terre River, Mo. 
30. Pomona Lake, One 
Hundred Ten Mile 
Creek, Kans. 
31. Rathbun Lake, 
Chariton River, 
Iowa 
32. Rathbun Lake (Fish 
Hatchery), Iowa 
(1974 Mod.) 
33. Smithville Lake, 
Little Platte 
River, Mo. 
34. Tomahawk Lake, 
Blue River, Kans. 
35. Tuttle Creek Lake 
Big Blue 
River, Kans. 
36. Tuttle Creek Lake 
(Road Improvements), 
Kans. 
(1974 Mod.) 
37. Wilson Lake, 
Saline River, 
Kans. 
38. Wolf-Coffee Lake, 
Blue River, 
Kans. 
39. Inspection of 
Completed 
Flood Control 
Projects 
42. Harry S. Truman 
Dam & Reservoir 
Osage River, Mo. 
COST AND FINANCIAL STATEMENT 
Funding 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
463,841 
439,800 
372,112 
216,800 
216,400 
78,004 
52,259 
403,000 
385,298 
6,508 
333,200 
289,315 
1,095,731 
372,400 
328,507 
257,900 
354,846 
30,800 
76,011 
472,500 
475,589 
9,994 
64,206 
309,800 
326,596 
99,300 
38,024 
193,800 
190,357 
53,393 
419,849 
584,200 
585,019 
204,000 
203,109 
468,400 
321,763 
364,700 
385,296 
63,996 
16,453 
454,700 
498,581 
468,000 
306,343 
411,300 
439,423 
3,955,000 
2,688,555 
96,963 
36,426 
503,086 
584,123 
329,100 
358,489 
252,376 
252,593 
156,000 
162,826 
135,000 
321,740 
789,000 
727,348 
211,000 
208,916 
179,000 
399,118 
453,200 
445,030 
16,000 
50,048 
442,500 
439,191 
48,000 
572,335 
474,600 
453,422 
3,268,200 
4,468,609 
2,000 
60,669 
570,200 
444,113 
390,300 
384,842 
155,000 
216,059 
160,000 
160,638 
73,252 
694,150 
762,183 
218,000 
218,167 
23,201 
605,000 
590,168 
346,000 
50,611 
451,600 
441,242 
20,410 
30,382 
445,150 
466,629 
700,000 
700,000 
9,890,000 
9,927,910 
78,000 
72,509 
4,000 
5,604 
917,040 
996,391 
3,000 
2,084 
386,450 
372,621 
454,000 
422,814 
142,000 
141,730 
26,224,900 26,464,000 31,600,000 43,130,000 
26,276,138 27,149,645 31,709,982 43,168,704 
20-24 
48,079,394 
48,045,588 
2,786,084 
2,720,447 
55,5698 
55,569 
3,098,8239 
3,095,615 
16,473,003 
16,473,001 
3,714,812 
3,673,978 
13,896,304 
13,586,145 
3,103,633 
3,076,413 
27,036,410 
27,027,861 
1,914,118 
1,894,945 
700,000 
700,000 
18,471,100 
18,417,228 
78,000 
72,509 
80,377,831 
80,377,468 
4,777,279 
4,716,940 
3,000 
2,084 
20,107,018 
20,107,018 
2,840,146 
2,809,514 
960,676 
929,490 
1,010,275 
1,010,005 
181,288,900 
180,351,532

KANSAS CITY, MO., DISTRICT 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
43. Stockton Lake, New Work: 
Sac River, Mo. Approp. 4,961,800 735,000 - 2,000 74,632,300 
Cost 4,627,145 2,059,195 579,563 10,634 74,611,220 
Maint. 
Approp. 360,200 597,500 945,000 1,075,200 2,977,900 
Cost 324,045 619,365 895,002 1,094,729 2,933,142 
1. Includes $8,665,594 costs of new work for previous 6. Includes cost of materials furnished without charge 
project. in the amount of $24,198. 
2. Includes $738,109 for maintenance of previous 7. Includes cost of materials furnished without charge 
project. in the amount of $7,885. 
3. Includes $8,665,594 for new work for previous 8. Cover 96X3122 constructions, general, funds allotted 
project and $808,616 from contributed funds. to the 'Republican River Basin Reservoirs (Medicine Creek 
4. Includes $8,665,594 for new work for previous Reservoir), Colo., Nebraska, and Kansas.' 
project and $755,570 from contributed funds. 9. Covers 96X3123 operation and maintenance, general, 
5. Includes $738,109 for maintenance of previous funds allotted to 'Scheduling of Flood Control Reservoir 
project, $22,642 from contributed funds and $200,000 Fiscal Operations.' 
Year 1968 Supplemental Appropriation Funds. 
MISSOURI RIVER, SIOUX CITY, IOWA, TO MOUTH 
(RULO, NEBR., TO MOUTH) 
TABLE 20-B TOTAL COST OF EXISTING PROJECT TO JUNE 30, 1975 
(See Section 1 of Text) 
Funds New Work Maintenance Total 
Regular $197,391,032 $196,477,470 $393,868,502 
Emergency 2,362,599 190,401 ' 2,553,000 
Public works 17,181,146 114,180 17,295,326 
Accelerated public works - 393,261 393,261 
Maintenance and operation of 
dams and other improvements 
of navigable waters 800,000 800,000 
Total $216,934,777 $197,975,312 $414,910,089 
20-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 20-C AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 25, 1912 
Aug. 8, 1917 
Mar. 3, 1925 
Jan. 12, 1927 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Dec. 31, 1970 
June 22, 1936 
Dec. 22, 1944 
July 24, 1946 
Sept. 3, 1954 
Aug. 18, 1941 
Dec. 22, 1944 
MISSOURI RIVER, SIOUX CITY IOWA, TO MOUTH 
(RULO, NEBR., TO MOUTH) (See Section 1 of Text) 
Project adopted for securing a permanent navigable 
channel of 6-foot depth from Kansas City, Mo. to mouth. 
Fixed upstream limit of improvement at upper 
end of Quindaro Bend (374.8 miles from mouth) and 
provided for dredging. 
For a minimum width of 200 feet, with a reasonable 
additional width around bends. 
Appropriation of $12 million authorized for existing 
project. 
Appropriation of $15 million additional authorized; 
additional allotments totaling $29,153,108 were 
made by Public Works Admiistration under provisions 
of National Industrial Recovery Act of 1938, and 
$9,669,791 allotted under provisions of Emergency 
Relief Appropriation Act of 1935. 
Completion of improvement from mouth.to Sioux 
City, Iowa. 
Securing a navigable channel of 9-foot depth and 
a minimum width of 300 feet. 
BLUE RIVER BASIN (KANSAS CITY DISTRICT) 
Adopted plan for Blue River Basin and authorized 
$40,000,000 for initiation and partial 
accomplishment. 
KANSAS CITYS ON MISSOURI AND KANSAS RIVERS, 
MO. AND KANS. 
Levees and floodwalls for protection of Kansas Citys, 
at an estimated construction cost not to exceed 
$10 million, estimated cost of lands and damages 
$8 million. 
Modified and extended project to provide construction 
of cutoffs and protection for additional areas at an 
estimated additional cost of $8,445,000. 
Authorized Chief of Engineers to include necessary railroad 
bridge and approach alterations as a Federal 
responsibility. 
Alternate plan of improvement proposed by local interests 
for Armourdale unit (downstream section). 
MISSOURI RIVER LEVEE SYSTEM, IOWA, NEBR., KANS., 
AND MO. (See Section 27 of Text) 
Levees along both sides of river from Sioux City 
to Kansas City. 
Extended project from Kansas City to the mouth 
provided for increased protection. 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(KANSAS CITY DIST.) (See Section 32 of Text) 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, Nebr., 
other supplemental flood control works on upper 
Republican River, and authorized $7 million additional 
expenditure. 
20-26 
H. Doc. 1287, 61st Cong., 
3d sess. (contains latest 
published map). 
H. Doc. 463, 64th Cong., 
1st sess. (contains latest 
published map). 
H. Doc. 1120, 60th Cong., 
2d sess. 
H. Doc. 238, 73d Cong., 
2d sess. (contains latest 
published map). 
H. Doc. 214, 76th Cong., 
1st sess. (contains latest 
published map). 
H. Doc. 91-332, 91st Cong., 
2d sess. 
H. Doc. 195, 73d Cong., 
2d sess. 
H. Doc. 342, 78th Cong., 
1st sess. 
H. Doc. 821, 76th Cong., 
3d sess. 
H. Doc. 475 and S. Does. 
191 and 347, 78th Cong., 
2d sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 
1st sess. 
H. Doec. 842, 76th Cong., 
3d sess. 
June 28, 1938 
Aug. 18, 1941

TABLE 20-C (Continued) 
KANSAS CITY, MO., DISTRICT 
AUTHORIZED LEGISLATION 
Acts Work Authorized Documents 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sept. 3, 1954 
May 2, 1956 
July 3, 1958 
July 14, 1960 
Dec. 30, 1963 
June 18, 1965 
May 12, 1967 
Aug. 13, 1968 
Dec. 24, 1970 
Dec. 23, 1971 
Mar. 7, 1974 
Expanded general comprehensive plan for Missouri River 
Basin and authorized $200 million additional 
expenditure. 
Additional expenditure of $150 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Additional expenditure of $250 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Expanded general comprehensive plan for Missouri River 
Basin and authorized $217,710,000 additional 
expenditure. 
Modified general comprehensive plan for Missouri River 
Basin by deletion of construction of Red Willow Dam and 
Reservoir, Nebr., and addition of construction of Wilson 
Dam and Reservoir, Kans. 
Expanded general comprehensive plan for Missouri River 
Basin and authorized $200 million additional 
expenditure. 
Additional expenditure of $207 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Additional expenditure of $80 million for prosecution of 
general comprehensive plan for Missouri River Basin and 
modified plan to include bank protection or rectification 
works below Garrison Dam. 
Additional $116 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Additional $20 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
Change comprehensive plan name to Pick-Sloan Missouri 
Basin program. 
Additional $101,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri 
Basin program. 
Additional $72,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri 
Basin program. 
1. Contains latest published maps of Missouri River 
Division. 
20-27 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong., 
2d sess. 
H. Docs. 642 and 549, 
81st Cong., 2d sess. 
H. Doc. 409, 84th Cong., 
2d sess. 
S. Doc. 91-1100, 91st Cong., 
2d sess. 
S. Doc. 92-222, 92nd Cong., 
1st sess.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Missouri River Navigation Charts July 74 
TABLE 20-D MISSOURI RIVER SIOUX CITY TO MOUTH: TERMINAL FACILITIES 
(See Section 1 of Text) 
Miles 
Description of Facility 1 Above Bank Nearest Town 
Mouth 2 
Existing facilities: 
Grain loading 
Grain loading 
Transfer of sand and gravel 
Grain loading 
Grain loading 
Chemical unloading 
Fertilizer unloading 
Grain loading 
Bulk handling; publicly owned, 
privately operated 
Loading dock 
Grain wharf 
Fertilizer unloading and loading 
Transfer of sand and gravel 
Shipyard and ways for construction, 
repairing, and launching floating 
equipment 
Grain loading 
Flour loading 
Unloading dock, molasses and 
liquid fertilizer 
Loading dock 
Transfer of sand and gravel 
Docking 
Loading dock 
Oil loading (standby) 
Grain loading 
Oil loading facilities 
Nitrogen fertilizer solutions 
Grain loading 
Warehouse, bulk handling dock, and 
unloading platform 
Grain loading 
Scrap steel loading 
Warehouse and loading platform 
Transfer of sand and gravel 
Transfer of sand and gravel 
Fuel oil unloading facilities 
Grain loading 
Fuel loading 
Sand and gravel 
Grain loading 
Grain loading 
Barge docking 
Transfer of sand and gravel 
Steel products 
Oil unloading and vessel refueling 
Fertilizer unloading 
Loading dock 
Cement loading 
Dock (Company) 
Grain loading 
Transfer of sand and gravel 
Transfer of sand and gravel 
Grain loading 
Grain loading 
Transfer of sand and gravel 
Grain loading 
Grain loading 
Grain loading 
Grain elevator, conveyor, and dock 
Transfer of sand and gravel 
Transfer of sand and gravel 
Bulk handling 
Barge docking 
488.0 
447.8 
447.5 
446.6 
446.0 
445.43 
423.2 
423.1 
422.9 
421.1 
396.1 
396.05 
395.8 
395.7 
386.5 
386.4 
386.2 
385.05 
377.5 
376.4 
375.6 
373.1 
373.0 
368.3 
368.2 
367.7 
367.1 
367.0 
366.9 
365.9 
365.7 
365.4 
364.3 
364.2 
364.1 
362.5 
361.7 
361.0 
360.6 
360.0 
357.6 
356.6 
355.7 
355.5 
354.8 
345.3 
318.2 
317.9 
317.2 
293.3 
293.0 
286.9 
270.0 
262.7 
249.3 
226.4 
226.3 
197.0 
196.8 
196.3 
Right 
Left 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Left 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Left 
Right 
Right 
Left 
Right 
Right 
Left 
Left 
Right 
Left 
Left 
Left 
Right 
Right 
Left 
White Cloud, Kans. 
St. Joseph, Mo. 
St. Joseph, Mo. 
St. Joseph, Mo. 
St. Joseph, Mo. 
St. Joseph, Mo. 
Atchison, Kans. 
Atchison, Kans. 
Atchison, Kans. 
Atchison, Kans. 
Leavenworth, Kans. 
Leavenworth, Kans. 
S. Leavenworth, Kans. 
S. Leavenworth, Kans. 
Wolcott, Kans. 
Wolcott, Kans. 
Wolcott, Kans. 
Waldron, Mo. 
Parkville, Mo. 
Parkville, Mo. 
Parkville, Mo. 
Kansas City, Kans. 
Kansas City, Kans. 
Kansas City, Kans. 
Kansas City, Kans. 
Kansas City, Kans 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Randolph, Mo. 
Kansas City, Mo. 
Kansas City, Mo. 
Sugar Creek, Mo. 
Sugar Creek, Mo. 
Sugar Creek, Mo. 
Sugar Creek, Mo. 
Sugar Creek, Mo. 
Missouri City, Mo. 
Lexington, Mo. 
Lexington, Mo. 
Lexington, Mo. 
Waverly, Mo. 
Waverly, Mo. 
Carrollton, Mo. 
Wakenda, Mo. 
Miami, Mo. 
Brunswick, Mo. 
Glasgow, Mo. 
Glasgow, Mo. 
Boonville, Mo. 
Boonville, Mo. 
Boonville, Mo. 
20-28

KANSAS CITY, MO., DISTRICT 
TABLE 20-D (Cont'd) MISSOURI RIVER SIOUX CITY TO MOUTH: TERMINAL FACILITIES 
(See Section 1 of Text) 
Description of Facility 1 
Miles 
Above 
Mouth 2 
Bank Nearest Town 
Transfer of sand and gravel 
Transfer of sand and gravel 
Transfer of sand and gravel 
Oil unloading 
Transfer of sand and gravel 
Transfer of sand and gravel 
Transfer of sand and gravel 
Coal unloading 
Transfer of sand and gravel 
Loading dock 
Transfer of sand and gravel 
Transfer of sand and gravel 
Transfer of sand and gravel 
Transfer of sand and gravel and bulk 
cargo dock 
Transfer of sand and gravel 
Transfer of sand and gravel 
Marine railway 
Transfer of sand and gravel 
186.4 
181.2 
157.4 
148.6 
143.7 
143.5 
124.6 
117.1 
96.9 
81.7 
68.2 
43.8 
28.0 
27.9 
27.8 
17.1 
8.6 
8.5 
Left 
Left 
Right 
Left 
Right 
Left 
Left 
Right 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Rocheport, Mo. 
Huntsdale, Mo. 
Marion, Mo. 
Jefferson City, Mo. 
Jefferson City, Mo. 
Jefferson City, Mo. 
Mokane, Mo. 
Chamois, Mo. 
Hermann, Mo. 
New Haven, Mo. 
Washington, Mo. 
Chesterfield, Mo. 
St. Charles, Mo. 
St. Charles, Mo. 
St. Charles, Mo. 
Musicks Ferry, Mo. 
Ruegg, Mo. 
Ruegg, Mo. 
1. Privately owned and operated unless indicated. 2. 1960 adjusted milage. 
TABLE 20-E OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 2 of Text) 
For Last Cost To June 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Fort Leavenworth Bridge removal 1965 270,393 - 
Kansas River Navigation, Ks. 1974 - - 
Gasconade River, Mo. 1931 139,003 85,077 
Osage River, Mo., lock and dam 1952 658,076 850,495 
1. Improvement adequate for existing needs. Project 
for maintenance only. 
2. Curtailment of project in H. Doc. 467, 69th Cong., 1st 
sess. 
3. Operation of lock and dam placed in standby status. 
20-29 
'-- ---- --------------

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 20-F MISSOURI RIVER LEVEE SYSTEM 
(See Section 23 of Text) 
Unit 
Miles of 
Levee 
R 513-512 Richardson Co. D. D. #7 
R 500 Iowa Point D. D. #4 
Kimsey Holly Creek 
L 497 Forest City L. D. 
L 488 Holt Co. D. D. #7 
R 482 Burr Oak D. D. #3 
L 476 Amazonia L. D. 
R 471-460 Elwood-Gladden L. D. 
L 455 S. St. Joseph L. D. 
L 448-443 Halls L. D. 
R 440 Atchison & Doniphan Co. D. D. 
L 408 Farley-Beverly D. D. 
L 400 Waldron L. D. 
L 385 Riverside-Quindaro D. D. 
R 351 Atherton L. D. 
L 345-330 Orrick L. D. 
L 325-319 Henrietta-Crooked River D. D. 
L 246 Brunswick-Dalton D. D. 
L 15 North Point L. D. 
Remaining units 
19.1 
4.1 
1.7 
13.4 
11.5 
8.3 
5.7 
14.5 
15.6 
16.8 
10.6 
12.5 
7.4 
6.5 
13.4 
43.4 
35.0 
20.0 
40.0 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Preliminary planning underway 
Complete 
Initial contract plans complete 
Planning underway 
Planning underway 
Planning underway 
Detailed planning not initiated 
20-30 
Status

KANSAS CITY, MO., DISTRICT 
TABLE 20-G KANSAS CITY DISTRICT PROJECTS INCLUDED IN 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(See Section 28 of Text) 
Project 
Estimated 
Federal 
Cost 
Abilene, Smoky Hill River, Kansas 
Arlington Lake, Gasconade River, Missouri 
Bartley, Republican River, Nebraska 
Beatrice, Big Blue River, Nebraska 2 
Fort Scott Lake, Marmaton River, Kansas 
Garnett Lake, Pottawatomie Creek, Kansas 4 
Hackleman Corners Lake, Cedar Creek, Missouri 2 
Harlan County Lake, Republican River, Nebraska 
Harry S. Truman Dam and Reservoir, Osage River, Missouri 
Hillsdale Lake, Big Bull Creek, Kansas 
Indianola, Republican River, Nebraska 
Kanopolis Lake, Smoky Hill River, Kansas 
Lawrence, Kansas River, Kansas 
Manhattan, Kansas River, Kansas 
Melvern Lake, Osage (Marais des Cygnes) River, Kansas 
Melvern Lake and Pomona Lake (Road Improvement), 
Kansas (1974 Authorization) 
Milford Lake, Republican River, Kansas 
Missouri River Levee System, Rulo to the Mouth 3 
Osawatomie, Osage (Marais des Cygnes) River, Kansas 
Ottawa, Osage (Marais des Cygnes) River, Kansas 
Perry Lake, Delaware River, Kansas 
Pioneer Lake, Arikaree River, Colorado and Kansas' 
Pomme de Terre Lake, Pomme de Terre River, Missouri 5 
Pomona Lake, Osage River Basin, Kansas 
Rathbun Lake (Fish Hatchery), Chariton River, Iowa 
(1974 Modification) 
Richland Lake, Gasconade River, Missouri 1 
Salina, Smoky Hill River, Kansas 
Stockton Lake, Sac River, Missouri 
Topeka, Kansas River, Kansas 
Tuttle Creek Lake, Big Blue River, Kansas 
Tuttle Creek Lake (Road Improvement), Kansas 
(1974 Modification) 
Wilson Lake, Saline River, Kansas 
1. 1954 estimate. 
2. 1960 estimate. 
3. Active portion of project. Deferred portion of project 
is currently estimated to cost (1964) $1,690,000 Federal and 
$122,000 non-Federal. Inactive portion of project is currently 
estimated to cost (1964) $231,722,000 Federal and $20,024,- 
000 non-Federal. 
$ 1,099,350 
27,200,000 
118,269 
685,000 
46,900,000 
38,600,000 
18,100,000 
46,701,155 
413,000,000 
52,500,000 
67,275 
12,601,735 
11,600,000 
2,488,585 
37,751,000 
500,000 
48,984,843 
147,100,000 
2,036,624 
4,462,661 
48,744,394 
20,000,000 
17,208,092 
14,027,108 
700,000 
33,300,000 
3,878,668 
77,052,000 
21,177,136 
80,420,031 
500,000 
20,140,023 
$ 287,000 
9,500 
524,000 
1,565,000 
88,858,000 
17,708,000 
7,592 
2,410,000 
265,000 
214,300 
15,200,000 
348,300 
876,000 
1,960,000 
17,057,000 
10,383,492 
214,300 
4. 1969 estimate. 
5. Active portion of project. Inactive portion of the 
project for power modification is currently estimated to cost 
(1954) $7,300,000. 
20-31 
Estimated 
Non-Federal 
Cost

TABLE 20-H 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 39 of Text) 
Location 
Missouri River Main Stem 
Missouri River Levees: R513-512, R500, Kimsey Holly Creek, L497, L488, 
R482, L476, R471-460, L455, L448-443, R440, L408, L400 and R351 
Kansas Citys, Missouri and Kansas: Argentine, Armourdale, 
Birmingham, CID (Mo & Kans), East Bottoms, Fairfax-Jersey 
Creek, North Kansas City Units, and GSA Federal Complex 
Missouri River at New Haven, Missouri and Mouth of Osage 
Diversion Levee 
Grand River at Brunswick, and Grand River at Salt Creek, Missouri 
Missouri River, Atchison, Kansas 
Nemaha River, Tecumseh, Nebraska 
Shoal Creek, Proctorville, Missouri 
Osage River, Kansas and Missouri 
Ottawa, Kansas 
Osawatomie, Kansas 
Kansas River and Minor Tributaries 
Topeka, Kansas; Auburndale, North Topeka, Oakland, Soldier 
Creek, South Topeka, and Waterworks Units 
Manhattan, Kansas 
Lawrence, Kansas 
Big Stranger Creek, Kansas 
Desoto, Kansas, Bridge Protection 
Republican River, Nebraska and Kansas 
Bartley, Nebraska 
Indianola, Nebraska 
McCook, Nebraska 
Inavale, Nebraska 
Elk Creek, Clyde, Kansas 
Smoky Hill, Salina, and Solomon Rivers 
Smoky Hill River, Solomon, Kansas, Bridge Protection 
Abilene, Kansas 
Salina, Kansas 
Salt Creek at Barnard, Kansas 
Blue and Delaware Rivers, Kansas 
Seward, Nebraska 
Mouth of Delaware River, Kansas 
Frankfort, Kansas 
Fairbury, Nebraska 
Chariton River, Iowa and Missouri 
Chariton River, Missouri 
Platte River, Missouri 
Bedford, Iowa, 102 River 
Hopkins, Missouri, East Fork, 102 River 
Easton-Saxton, Bridge Protection 
Villisca, Iowa 
Fort Riley, Kansas 
Aug-Sep-Oct-Nov and 
Mar-Apr-May-Jun 
Sep-Oct and Nov 
Apr-May-Jun 
May 
May 
Apr 
Apr 
May 
Nov and Apr 
Apr 
Mar 
Mar 
May 
Mar 
Mar 
Sep 
Sep and Apr 
May 
Apr 
Mar 
Mar 
Mar 
Mar 
Mar 
Apr 
Mar 
Mar 
Apr 
Jun 
Jun 
Jun 
Jun 
Jun 
Mar 
20-32 
Month Inspected

KANSAS CITY, MO., DISTRICT 
TABLE 20-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 40 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Abilene, Kans.1 1965 1,099,350 - 
Arlington Lake, Mo.2 1948 8,651 - 
Atchison, Kans. 1 1973 4,099,590 - 
Bartley, Nebr. 1 1953 118,269 - 
Beatrice, Big Blue River, Nebr."1 4 1965 16,317 - 
Bedford, East Fork, 102 River, Iowa1 1974 582,381 - 
Big Blue River, Seward, Nebr.' - 126,887 - 
Big Stranger Creek, Kans.' 4 - 337,131 - 
Braymer Lake, Shoal Creek, Mo. 3 1966 - - 
Chariton River, Mo. (1944 Act) 1 1973 8,052,990 - 
Dry Fork and East Fork Lakes, 
Fishing River, Mo.2 1974 51,989 - 
East Muddy Creek, Mo. 1966 - - 
Fairbury, Little Blue River, Nebr.' 1973 726,966 - 
Frankfort, Black Vermillion River, Kans.' 1966 1,271,025 - 
Garnett Lake, Pottawatomie Creek, Kans.2 1973 71,466 - 
Hackleman Corners Lake, Cedar Creek, Mo.3 
Hays, Big Creek, Kans. 2 1974 499,200 - 
Indianola, Nebr.' 1950 67,275 - 
Kansas Citys on Missouri and Kansas 
Rivers, Mo.1 1971 41,645,410 - 
Lower Grand River, Mo. 1966 - - 
Manhattan, Kansas River, Kans.' 1967 2,488,585 - 
Marysville, Kans. 5 - 133,682 - 
Merriam, Turkey Creek, Kans.5 1970 39,708 - 
Mill Lake, Blue River, Mo. 1971 - - 
Missouri River at New Haven, Mo.1 ' 4 - 139,883 - 
Osawatomie, Pottawatomie Creek, Kans.1 1973 2,036,624 - 
Ottawa, Osage (Marais des Cygnes) 
River, Kans.1 1966 4,462,661 - 
Pioneer Lake, Kans.2 1952 95,692 - 
Platte River, Mo., Channel Improvement 2 1973 222,193 - 
Richland Lake, Mo.2 1948 8,651 - 
Salina, Smoky Hill River, Kans.' 1967 3,878,668 - 
Salt Creek, Barnard, Kans.1, 4 - 127,860 - 
Smithville Channel, Little Platte River, Mo.2 1973 6,896 - 
Stonehouse Creek, Jefferson Co., Kans.' , 4 1972 246,955 - 
Topeka, Kansas River, Kans.1 1974 21,174,593 - 
Trenton Lake, Thompson River, Mo.3 1966 - 
Upper Grand River, Mo. 1966 - 
1. Completed. 
2. Inactive. 
3. Deferred for restudy. 
4. Authorized by the Chief of Engineers under section 
205, Public Law 858, 80th Congress, as amended. 
5. Deauthorized for lack of local cooperation. 
20-33

OMAHA, NEBR., DISTRICT* 
This district comprises portions of Montana, in drainage basin of Missouri River along main 
Wyoming, North Dakota, South Dakota, Colora- stem and tributaries to Rulo, Nebr. 
do, Nebraska, Iowa, and Minnesota, all embraced 
IMPROVEMENTS 
Navigation Page 
1. Fort Peck Lake, Mont................. 21-2 
2. Missouri River, Sioux City, 
Iowa to Rulo, Nebr. ................ 21-2 
3. Other Authorized Navigation 
Projects ............................. 21-3 
4. Navigation Work Under Special 
Authorization ....................... 21-3 
Flood Control 
5. Bear Creek Lake, Colo........... 
6. Big Sioux River at Sioux City, 
Iowa and S. Dak ................ 
7. Billings, Mont................. 
8. Boulder, Colo. ................ 
...... 21-3 
...... 21-3 
...... 21-3 
...... 21-4 
9. Bowman- Haley Lake, N. Dak.........21-4 
10. Chatfield Lake, Colo. ................ 21-4 
11. Cherry Creek Lake, Colo ............... 21-5 
12. Fall River Basin, S. Dak...............21-5 
13. Frazer-Wolf Point, Mont ............. 21-6 
14. Great Falls, Mont................... .21-6 
15. Little Papillion Creek, Nebr............21-6 
16. Miles City, Mont ................... 21-6 
17. Missouri River, Garrison Dam 
to Lake Oahe, N. Dak................. 21-6 
18. Missouri River, Kenslers Bend, 
Nebr. to Sioux City, Iowa.............21-7 
19. Missouri River Levee System, 
Sioux City, Iowa to Mouth (Sioux 
City, Iowa to Rulo, Nebr.) ............. 21-7 
20. Mud Creek, Broken Bow, Nebr.........21-7 
21. Papillion Creek and Tributaries, 
Nebr............................21-7 
22. Pick-Sloan Missouri River Basin 
Program (Omaha Dist.) ................ 21-8 
23. Pipestem Lake, N. Dak............... 21-8 
Flood Control (cont.) Page 
24. Sacred Heart Hospital, 
Yankton, S. Dak ................ .21-9 
25. Salt Creek & Tributaries, Nebr........21-9 
26. Sheridan, Yellowstone River, Wyo ..... 21-9 
27. South Platte River Basin, Colo. ....... 21-9 
28. Inspection of Completed Flood 
Control Works ..................... 21-10 
29. Scheduling Flood Control 
Reservoir Operations................. 21-10 
30. Other Authorized Flood Control 
Projects ............................ 21-10 
31. Flood Control Activities Under 
Special Authorization ................ 21-10 
Multiple Purpose Projects Including Power 
32. Big Bend Dam-Lake Sharpe, 
Missouri River Basin, S. Dak.........21-10 
33. Eagle Bay & Fort Yates Highway 
Bridges, N. Dak .................... 21-11 
34. Fort Randall Dam-Lake Francis 
Case, Missouri River Basin, 
S. Dak ........................... 21-11 
35. Garrison Dam-Lake Sakakawea, 
Missouri River Basin, N. Dak..........21-11 
36. Gavins Point Dam-Lewis and Clark 
Lake, Missouri River Basin, Nebr. 
and S. Dak. ........................ 21-12 
37. Gavins Point Dam-Lewis and Clark 
Lake-Relocation of Niobrara, Nebr.... 21-12 
38. Oahe Dam-Lake Oahe, Missouri 
River Basin, S. Dak. and N. Dak ...... 21-12 
General Investigations 
39. 
40. 
41. 
Surveys ........................... 21-13 
Collection & Study of Basic Data ...... 21-13 
Research and-Development ........... 21-13 
*All cost and financial statements for projects are listed at the end of 'his chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
21-1 
i

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. FORT PECK LAKE, MONT. 
Location. Reservoir is in Missouri River Valley 
in McCone, Valley, Garfield, Phillips, Petroleum, 
and Fergus Counties, Mont. Dam is approximately 
1,771.5 miles above mouth of Missouri 
River. Nearest towns are Glasgow, 17 miles 
northwest, and Nashua, 9 miles north. 
Existing project. A hydraulic earthfill dam 
with a maximum height of 250.5 feet and a reservoir 
for flood control, irrigation, navigation, 
hydroelectric power, and other purposes, with a 
gross storage capacity of 18,900,000 acre-feet at 
maximum operating pool. See page 818 of 1965 
Annual Report and page 905 of 1958 Annual 
Report for project details. Estimated cost of 
overall project (October 1975) is $157,238,420 
including $687,000 Code 710 funds. 
Local cooperation. None required. 
Terminal facilities. None. 
Operation and results during fiscal year. Regular 
funds, new work: None. Regular funds, 
maintenance: Design studies continued for powerhouse 
improvements. Contract for powerhouse 
slope repair was completed. Upgrading of sanitary 
facilities was initiated. Fort Peck Lake was 
operated in conjunction with the other Missouri 
River reservoirs for flood control, navigation, 
power production, and other multi-purpose uses. 
Generating facilities produced 1,356,036,000 net 
kilowatt-hours of electricity. Total cost of 
Operation and Maintenance during the Fiscal 
Year was $3,239,800; however, reimbursement 
from the Bureau of Reclamation for the prorata 
share cost of Operation and Maintenance of the 
power plant, reimbursement for furnishing operator's 
village facilities, and property disposals 
reduced net cost to $1,728,400. 
Condition at end of fiscal year. Work started 
on original project in October 1933 and on second 
power plant in August 1956. The project was 
completed in 1965. On 30 June 1975, the pool was 
at elevation 2250.0 and 18,951,000 acre-feet of 
water was impounded in the reservoir. 
2. MISSOURI RIVER, SIOUX CITY, IOWA 
TO MOUTH (SIOUX CITY IOWA 
TO RULO, NEBR.) 
Location. Jefferson, Madison, and Gallatin 
Rivers conjoin at Three Forks, Mont., to form 
Missouri River, which flows southeasterly 2,315.1 
miles (1960 milage) across or along seven states 
to Mississippi River, 17 miles above St. Louis. 
River is boundary between states of Missouri, 
Kansas, Nebraska, and Iowa. For description see 
page 1149, Annual Report for 1932. 
Previous projects. For details see page 1893, 
Annual Report for 1915, and page 1175, Annual 
Report for 1938. 
Existing project. Provides for a channel of 
9-foot depth and width not less than 300 feet, to 
be obtained by revetment of banks, construction 
of rock dikes to contract and stabilize waterway, 
cutoffs to eliminate long bends, closing minor 
channels, removal of snags and dredging as 
required. Estimated cost of new work Sioux City 
to Rulo, Nebr. (October 1975) is $190,800,000 exclusive 
of amounts expended on previous projects. 
(See table 21-C for authorizing legislation, 
and Table 21-E for Terminal Facilities). 
Operations and results during fiscal year. Regular 
Funds, New Work: Consisted of 1,700 cubic 
yards of point removal for channel correction was 
accomplished with hired labor forces. 
Regular funds, maintenance: Consisted of construction 
by contract, of restoring and replacement 
of 2,046 linear feet of dikes and 17,200 
linear feet of stone fill revetments. Work by hired 
labor forces consisted of 700 cubic yards of point 
removal for channel correction; 8,375 tons of 
stone salvaged from obsolete structures to repair 
7,625 linear feet of dikes and revetments; and 
removal of minor amounts of debris and snags. 
Condition at end of fiscal year. Construction 
was initiated on this section of the project (Sioux 
City to Rulo) in fiscal year 1928; and the 
scheduled completion date is fiscal year 1981 for 
Bank Stabilization and fiscal year 1981 for the 
Recreation Feature. The work was approximately 
97.8 percent complete at end of the fiscal year. 
Work remaining to complete this section of 
project (Sioux City to Rulob) consists of construction 
of additional bank stabilization structures, 
strengthening of existing structures to improve 
their effectiveness and to prevent their deterioration 
prior to final stabilization of banks, refinement 
construction consisting of minor dike and 
revetment extensions and underwater sills to redistribute 
flow velocities in order to develop more 
stable navigation project dimensions, and construction 
of recreation facilities. A reliable 
channel suitable for navigation is available 
through this section. Controlling depth at 
ordinary stages of the river is 8 '/2 feet, with 
additional depths available during high stages. 
Commercial navigation was inaugurated on this 
section in May 1939, and common carrier transportation 
service was inaugurated in October 
1946. Seven riverside recreation sites are complete 
and in operation. Enlargement of two of the 
site areas to provide company facilities is under 
consideration. Local interests have assumed 
operation and maintenance of the recreation 
sites. (See table 21-B for total cost of work under 
existing project to June 30, 1975). 
21-2

OMAHA, NEBR., DISTRICT 
3. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 21-D. 
4. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Small Navigation Projects Not Specifically 
Authorized by Congress (Sec. 107 of the River 
and Harbor Act of 1960, as amended, Public Law 
645, 86th Congress). 
No work this fiscal year. 
Flood Control 
5. BEAR CREEK LAKE, COLO. 
Location. Damsite is on Bear Creek in Jefferson 
County, Colorado about 8 miles above the 
confluence of Bear Creek with the South Platte 
River at Denver. 
Existing project. Project consists of an 
earthfill dam 170 feet high, with a crest length of 
about 5,120 feet, and a supplementary earthfill 
dike with a height of 80 feet and a crest length of 
1,930 feet, to the south of the main dam, and an 
uncontrolled earth and rock-cut emergency spillway. 
The lake will provide storage capacity of 
26,290 acre-feet for flood control and 2,000 
acre-feet for sediment and recreation. Authorized 
by 1968 Flood Control Act (Senate Document 87, 
90th Congress). Estimated cost is $69,700,000 
(October 1975) of which $410,000 is future non- 
Federal reimbursement for recreation cost sharing. 
Other non-Federal costs, for acquisition of 
water for recreation pool, are estimated at 
$240,000. 
Local cooperation. Local interests will be required 
to: a. In accordance with the Federal 
Water Project Recreation Act: (1) administer 
land and water areas for recreation and fish and 
wildlife enhancement; (2) pay, contribute in kind, 
or repay with interest, one-half of the separable 
cost allocated to recreation and fish and wildlife 
enhancement; (3) bear all costs of operation, 
maintenance, and replacement of recreation and 
fish and wildlife lands and facilities including 
water replacement; (4) provide the water required 
for initial filling and replenishment of evaporation 
losses of the recreation pool by purchase or other 
means consistent with Federal and State laws, to 
assure effective operation of the project for 
recreation and fish and wildlife enhancement; b. 
hold and save the United States free from 
damages due to water-rights claims resulting 
from construction and operation of the project; c. 
prevent encroachment on the flow-carrying capacity 
of the channel below the reservoir to the 
extent necessary to provide for effective reservoir 
operation in the interest of flood control; d. adequately 
inform affected interests, at least annually, 
that the project will not provide complete 
flood protection; and e. provide guidance and 
leadership in preventing unwise and uneconomical 
future development of the flood plain areas 
by encouraging prudent management techniques 
to reduce future flood losses. 
Operations and results during fiscal year. Design 
studies continued by hired labor. Land 
acquisition continued. Construction of relocations 
and outlet works continued. Embankment and 
spillway construction initiated. 
Condition at end of fiscal year. Construction of 
the project was initiated in October 1973 and 
advanced to 26 percent complete. Land acquisition 
is 54 percent complete. Relocations are 34 
percent complete. Construction of the dam is 8 
percent complete. Planning is underway on 
remaining relocations and public use facilities. 
6. BIG SIOUX RIVER AT SIOUX CITY, 
IOWA AND S. DAK. 
Location. Near mouth of Big Sioux River in 
the vicinity of Sioux City, Woodbury County, 
Iowa and North Sioux City, Union County, 
South Dakota. 
Existing project. The project provides for 
channel improvement by enlargement and minor 
realignment along the existing channel upstream 
from the Interstate Highway 29 bridge to a point 
approximately 1,300 feet upstream of the Chicago, 
Milwaukee, St. Paul and Pacific Railroad 
Bridge. Levees will provide a high degree of 
protection to North Sioux City, South Dakota 
and the Riverside Area of Sioux City, Iowa. 
Stone revetment will be placed along the 
improved channel at locations of potential 
erosion. Estimated cost is $6,640,000 (October 
1975) of which $6,350,000 is Federal and 
$290,000 is non-Federal cost. 
Local cooperation. Section 3 of the Flood 
Control Act approved 22 June 1936 applies. 
Contracts required by Section 221 of the Flood 
Control Act of 1970 to provide local cooperation 
will be executed prior to initiation of construction. 
Operation and results during fiscal year. Preparation 
of the General Design Memorandum 
continued. 
Condition at end of fiscal year. General Design 
Memorandum was about 95 percent complete. 
7. BILLINGS, MONT. 
Location. At Billings and vicinity on Yellowstone 
River, Mont., 346 river miles upstream 
from its confluence with the Missouri River. 
21-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. The original plan as authorized 
by the 1950 Flood Control Act (H. Doc. 216, 
81st Cong. 1st sess.) consisted of a system of 
channels and levees by means of which floodwaters 
approaching the city from the west, east 
and south would be diverted away from the area 
subject to flooding. A restudy of the project, 
limited to the Western Unit at the request of 
local interests, resulted in reclassification of the 
Western Unit to "active" status and the Eastern 
and Southern Units to "inactive" status. The 
proposed Western Unit involves the interception 
of west to east drainage courses west of Billings 
and diverting their flows to the Yellowstone 
River above the city. The estimated cost of the 
Western Unit is $3,620,000 (October 1975) of 
which $2,500,000 is Federal and $1,120,000 is 
non-Federal cost. 
Local cooperation. Section 3 of the Flood Control 
Act approved 22 June 1936 applies. City 
officials requested the restudy and agreed to 
furnish the local cooperation requirements for the 
project. Yellowstone County officials are interested 
because the project will lie outside the city 
limits. 
Operation and results during fiscal year. No 
work accomplished during the fiscal year. 
Condition at end of fiscal year. Restudy of 
Western Unit to determine economic feasibility 
was complete. Western Unit classified active and 
Eastern and Southern Units classified inactive. 
8. BOULDER, COLO. 
Location. Along Boulder and Sunshine Creeks 
within the confines of the City of Boulder, 
Boulder County, Colorado. 
Existing project. The project consists of channel 
enlargement and bank protection on Sunshine 
Creek from its mouth upstream for about 1,500 
feet and on Boulder Creek from the junction of 
Sunshine Creek downstream approximately 3.5 
miles to the Colorado and Southern Railway 
Bridge. Project was authorized by the Flood 
Control Act of 1950 (House Document 669, 80th 
Congress). Estimated cost of the improvement is 
$7,830,000 (October 1975) of which $5,020,000 is 
Federal cost and $2,810,000 is non-Federal cost. 
Local cooperation. Section 3 of the Flood 
Control Act approved 22 June 1936 applies. 
Local interests are considering alternative plans 
for protection. 
Operation and results during fiscal year. Activities 
limited to furnishing local interests 
information and data on the flood study. 
Condition at end of fiscal year. General Design 
Memorandum is essentially complete pending 
local interests decision to proceed. 
9. BOWMAN-HALEY LAKE, N. DAK. 
Location. Damsite is on North Fork of Grand 
River in southwestern North Dakota, about 6 
miles above Haley, N. Dak. 
Existing project. A dam and reservoir with a 
storage capacity of about 19,780 acre-feet for 
sediment storage, fish and wildlife conservation, 
and recreation, and future water supply for communities 
of Bowman, Reeder, Scranton, and 
Gascoyne, N. Dak. Also provided will be 73,200 
acre-feet of exclusive flood control storage. 
Project was authorized by 1962 Flood Control 
Act. 
Final cost is $4,372,174 (July 1973) of which 
$3,572,447 is ultimate Federal cost and $799,727 
future non-Federal reimbursement for water 
supply. 
Local cooperation. Local interests must prevent 
encroachment on capacity of North Fork 
channel below reservoir; obtain water rights for 
storage; pay the United States for costs allocated 
to water supply; and hold the United States free 
from damages. Assurances of local cooperation 
were approved June 19, 1964. With respect to 
water rights, requirements have been complied 
with. Negotiation of a contract for future water 
supply is pending. 
Operation and results during fiscal year. Regular 
funds, maintenance: Operation and maintenance 
activities included sedimentation and 
reservoir regulation studies and intermittent 
inspections of the dam and structures. 
Condition at the end of fiscal year. Construction 
was initiated July 1964, and the nroject was 
completed in 1970. 
10. CHATFIELD LAKE, COLO. 
Location. On South Platte River, just below 
the mouth of Plum Creek, about eight miles upstream 
from Denver, Colorado. 
Existing project. Consists of rolled earth-fill 
dam with a maximum height of 148 feet and a 
reservoir with flood control capacity of 211,200 
acre-feet and sediment capacity of 23,800 acrefeet, 
which will be used for recreation, and an 
enlarged channel from the dam downstream to 
Denver to accommodate reservoir flood releases. 
Project was authorized by 1950 Flood Control 
Act. 
The Water Resources Act of 1974 (PL 93-251) 
authorized participation with local interests in 
acquisition of lands and development of recreation 
facilities immediately downstream of the 
Chatfield Dam in lieu of a portion of the channel 
improvement. Estimated cost is $91,750,000 
(October 1975) of which $86,400,000 is Federal 
21-4

OMAHA, NEBR., DISTRICT 
cost for construction and $2,450,000 is local cost 
in connection with the downstream channel 
improvement and $2,900,000 is local cost for 
acquisition of water for the recreation pool. 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936 applies to the downstream 
channel improvement. The Colorado Water Conservation 
Board provided assurances of local 
cooperation for the downstream improvement of 
December 13, 1967. Local interests must provide 
water for filling the sediment reserve pool for 
recreation use which the state agreed to on April 
25, 1967. 
Operations and results during fiscal year. Continued 
design by hired labor. Continued real 
estate acquisition. Construction of embankment 
and spillway completed. Continued construction 
of recreation facilities. 
Condition at end of fiscal year. Construction of 
the project was initiated in August 1967 and 
advanced to 85 percent completion by the end of 
the fiscal year. Acquisition of land is 95 percent 
complete. Relocations are essentially complete. 
Construction of the spillway and the final earthwork 
contract are complete. Construction of 
recreation facilities is about 36 percent complete. 
Planning is underway for remaining dam facilities, 
downstream channel and public use facilities. 
11. CHERRY CREEK LAKE, COLO. 
Location. Damsite is on Cherry Creek in Arapahoe 
County, Colo., approximately 6 miles 
southeast of Denver, Colo. just outside of city 
limits. Cherry Creek joins South Platte River 
within city limits of Denver. 
Existing project. A rolled-earthfill dam with 
maximum height of 140 feet above streambed 
and 14,300 feet long. Project includes a reinforced 
concrete outlet works and an uncontrolled side 
channel spillway canal discharging into adjacent 
Toll Gate Creek, thus by-passing city of Denver. 
Cherry Creek project provides reservoir storage 
capacity of 93,900 acre-feet below spillway canal 
invert and surcharge storage of 134,470 acre-feet 
above this elevation. Initial plan for operation is 
for flood control only. Plan of operation in 
ultimate development for, multiple-purpose uses 
includes 10,000 acre-feet for sediment storage, 
85,000 acre-feet for conservation purposes, and 
surcharge for flood control purposes. Estimated 
cost of project is $15,053,364 (October 1975) 
including $383,450 Code 710 funds (recreational 
facilities on completed projects). (See table 21-C 
for authorizing legislation). 
Local cooperation. None required except for 
recreation cost-sharing under the Code 710 program. 
Operations and results during fiscal year. Operation 
and maintenance activities include administration 
of project area, continuation of 
sediment studies and stream gaging activities, 
and continuation of miscellaneous items of 
ordinary repair and maintenance. 
Condition at end of fiscal year. Construction 
began in fiscal year 1946 and was completed in 
June 1961 exclusive of recreation facilities. 
12. FALL RIVER BASIN, S. DAK. 
Location. In Custer and Fall River Counties, 
S. Dak., in and near town of Hot Springs. Hot 
Springs unit is in town of Hot Springs, immediately 
south of junction of Cold Brook and Hot 
Brook which combine to form Fall River; Cold 
Brook Lake unit is approximately 1.25 miles 
north of town of Hot Springs on Cold Brook; and 
Cottonwood Springs Lake unit is approximately 
4.5 miles west of town of Hot Springs on Cottonwood 
Springs Creek, one-half mile upstream from 
its confluence with Hot Brook. 
Existing project. Project as authorized by 
1941 Flood Control Act, is a plan of flood 
protection on Fall river and tributaries, S. Dak., 
substantially in accordance with recommendations 
of Chief of Engineers in House Document 
655, 76th Congress, 3d session. The general plan 
of improvement provides flood protection for Hot 
Springs, S. Dak. The Hot Springs channel 
improvement unit consisted of widening, deepening 
and straightening 6,000 feet of channel of 
Fall River. The Cold Brook Lake unit, an earthfill 
dam with appurtenant structures, controls an 
area of 70.5 square miles. The Cottonwood 
Springs Lake unit consists of an earthfill dam 
with appurtenant structures and controls an area 
of 26 square miles. Final cost is $5,661,932 (July 
1974), of which $5,519,432 is Federal cost for 
construction and $142,500 is local cost for lands 
and relocations. 
Local cooperation. Local cooperation was required 
only for the Hot Springs Channel Improvement. 
These requirements have been fully 
complied with. 
Operations and results during fiscal year. Construction 
of project complete. Routine operation 
and maintenance activities were continued on the 
Cold Brook and Cottonwood Springs dams and 
structures. 
Condition at end of fiscal year. Construction of 
Hot Springs unit was completed during fiscal 
year 1951. Construction of Cold Brook unit dam 
and appurtenances was complete in fiscal year 
1953 with exception of a road and parking area 
which were completed in fiscal year 1955. 
Construction of the Cottonwood Springs unit 
dam was completed in fiscal year 1970 with the 
21-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
exception of the recreation facilities which were 
completed in fiscal year 1972. 
13. FRAZER-WOLF POINT, MONT. 
Location. Along the Missouri River approximately 
4 miles southwest of Frazer, Montana. 
Existing project. Proposed project consists of 
stonefill dike construction on the right bank and 
segmented bank protection on the left bank 
extending .25 mile upstream to .50 downstream 
of the Frazer-Wolf Point Irrigation Unit intake 
structure. The estimated cost of the project (July 
1974) is $400,000. 
Local cooperation. Section 3 of the Flood 
Control Act approved 22 June 1936 applies. 
Operations and results during fiscal year. Preconstruction 
planning was continued. 
Condition at end of fiscal year. Construction 
was not started. 
14. GREAT FALLS, MONT. 
Location. In Great Falls, Cascade County, 
Montana at confluence of the Sun and Missouri 
Rivers. 
Existing project. Provides for levees along 
both banks of the Sun River, along the left bank 
of the Missouri River, and along the right bank 
of the Missouri River at the water works; and an 
interceptor ditch and closed conduit to collect 
and convey side-hill runoff to the Sun River. 
Project was authorized by 1958 Flood Control 
Act and amended by the 1965 Flood Control Act 
to waive the requirement that local interests 
contribute in cash a percentage of the construction 
costs of all items of work provided by the 
United States. Estimated cost is $12,870,000 
(October 1975) of which $9,650,000 is Federal 
cost of construction and $3,220,000 is local cost 
for lands, relocations and a cash contribution for 
replacement of a storm sewer conduit desired by 
local interests. 
Local cooperation. Section 3. Flood Control 
Act of June 22, 1936 applies. In addition local 
interests must zone the unleveed portion of the 
flood channel through the damage area to 
preserve its capacity and to prevent further encroachments 
and contribute in cash $103,000 representing 
the estimated cost of replaced storm 
drainage facilities which will be incorporated into 
the closed conduit of the Watson Coulee 
interceptor. West Great Falls Flood Control and 
Drainage District provided assurances on 17 
January 1968. State Supreme Court decision on 
assessments required a change in state law which 
was enacted in 1973. Local interests are in the 
process of complying with the new law. 
Operations and results during fiscal year. All 
work suspended pending resolution of local cooperation 
requirements. 
Condition at end of fiscal year. Construction 
was not started. 
15. LITTLE PAPILLION CREEK, NEBR. 
Location. In Douglas County along Little 
Papillion Creek from a point south of Irvington, 
Nebr., through metropolitan Omaha to its confluence 
with Papillion Creek. 
Existing project. Provides for channel improvement 
along Little Papillion Creek. Project 
was authorized by 1962 Flood Control Act. 
Estimated cost is $5,523,111 (October 1975), of 
which $3,643,111 is Federal cost for construction 
and $1,880,000 is local cost for lands and 
relocations. 
Local cooperation. Section 3. Flood Control 
Act of June 22, 1936 applies. All rights-of-way 
have been furnished. 
Operation and results during fiscal year. Preparation 
of O&M manual essentially completed. 
Condition at the end of fiscal year. Construction 
began October 1965. Project completed in 
January 1973 except preparation of O&M manual. 
16. MILES CITY, MONTANA 
Location. On the right banks of the Tongue 
and Yellowstone Rivers at Miles City, Montana. 
Existing project. The plan authorized by the 
Flood Control Act of 1950 provides for construction 
of levees along the right banks of the Tongue 
and Yellowstone Rivers starting about 2,000 feet 
upstream from the Interstate 94 embankment 
and extending approximately five miles downstream. 
The project was reclassified from deferred 
to active status in February 1975. Estimated 
cost is $2,370,000 (October 1975) of which 
$2,110,000 is Federal cost and $260,000 non- 
Federal cost. 
Local cooperation. Section 3 of the Flood 
Control Act approved 22 June 1936 applies. 
Operations and results during fiscal year. Restudy 
of the project was completed. 
Condition at end of fiscal year. Restudy of 
project complete. 
17. MISSOURI RIVER, GARRISON DAM 
TO LAKE OAHE, N. DAK. 
Location. Along the channel of Missouri River 
between Garrison Dam and headwaters of Oahe 
Reservoir in North Dakota. 
Existing project. Consists of bank stabiliza- 
21-6

OMAHA, NEBR., DISTRICT 
tion and rectification works required to stabilize 
banks of Missouri River in specific areas and 
prevent further loss of agricultural lands through 
erosion. Estimated total cost (October 1975) is 
$9,465,000 of which $9,200,000 is Federal and 
$265,000 Non-Federal. Project was authorized by 
Flood Control Act of 1963 and 1968. 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936, applies. Sponsorship of 
project is being provided by North Dakota State 
Water Commission. 
Operations and results during fiscal year. New 
construction work was performed in the Dry 
Point, Square Butte and Bismarck Mandan 
areas. 
Condition at end of fiscal year. Construction 
was initiated January 1965 and project is 85 
percent complete. 
18. MISSOURI RIVER, KENSLERS BEND, 
NEBR., TO SIOUX CITY, IOWA 
Location. Project is along Missouri River between 
Ponca Bend, Nebr., and combination 
bridge at Sioux City, Iowa. 
Existing project. Authorized by 1941 Flood 
Control Act and modified by 1948 Flood Control 
Act provides for construction of dikes, revetments 
and channel improvement along Missouri 
River from Miners Bend and vicinity, S. Dak. 
and Nebr., to Sioux City, Iowa. Federal cost of 
new work under project is $11,294,414. 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. 
Maintenance: maintenance by hired labor consisted 
of the repair and/or replacement of 115 
linear feet of dikes and 633 linear feet of revetment. 
Hired labor also salvaged 2,975 tons of 
stone and removed 7,232 tons of debris. 
Condition at end of fiscal year. Project was 
started in June 1946 and completed in June 1961. 
19. MISSOURI RIVER LEVEE SYSTEM, 
IOWA, NEBRASKA, KANSAS AND 
MISSOURI (SIOUX CITY, IOWA 
TO RULO, NEBR.) 
Location. On both banks of the Missouri River 
from Sioux City, Iowa to St. Louis, Missouri, a 
distance of approximately 760 miles. Portion of 
the project in Omaha District extends from Sioux 
City, Iowa to Rulo, Nebraska. 
Existing project. A series of levee units and 
appurtenant works along both sides of Missouri 
River from Sioux City, Iowa, to mouth, for 
protection of agricultural lands and small communities 
against floods. Cost estimate for active 
portion of project from Sioux City, Iowa to Rulo, 
Nebr. (October 1975) is $29,000,000 of which 
$25,900,000 is Federal cost for construction and 
$3,100,000 local costs for lands and damages. 
(See table 21-C for authorizing legislation). 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936 applies. Fully complied with 
for all completed units. Local interests have 
furnished assurances of their willingness and 
ability to fullfill local cooperation requirements 
for two units not yet under construction. 
Operation and results during fiscal year. Design 
studies on units L-611-614 and R-616 
continued. 
Condition at end of fiscal year. Construction of 
project was initiated June 1948. Levee Units 
L-627-624; L-594; R-580; L-575; R-573; R-562; 
L-561-550; R-548; L-536; R-520; L-601 and 
R-613 are complete. 
20. MUD CREEK, BROKEN BOW, NEBR. 
Location. On the South and North Branches of 
Mud Creek just above their confluence near the 
western city limits of Broken Bow, Nebraska and 
continuing on Mud Creek through the city of 
Broken Bow. 
Existing Project. Diversion of the South 
Branch of Mud Creek into the North Branch 
upstream of Broken Bow and channel improvement 
of Mud Creek through the city. Levees are 
proposed at the upstream end of the project to 
train flood flows into the channel with a drop 
structure to prevent channel degradation. Project 
was authorized by the Chief of Engineers on 30 
December 1968, under authority provided by 
Section 205 of the 1948 Flood Control Act, as 
amended. Final cost is $2,020,000, of which 
$1,000,000 is Federal and $1,020,000 is local 
interest cost. 
Local cooperation. The Broken Bow City 
Council has fulfilled all local cooperation requirements. 
Operations and results during fiscal year. Construction 
completed. 
Condition at end of fiscal year. Construction of 
the project was initiated in August 1973, was 
completed in April 1975. Preparation of O&M 
manual in progress. 
21. PAPILLION CREEK AND TRIBUTARIES, 
LAKES, NEBR. 
Location. The Papillion Creek basin is located 
in Washington, Douglas, and Sarpy Counties, 
Nebraska. Big Papillion Creek rises west of Blair, 
flows southeasterly through metropolitan Omaha 
area where it is joined by the Little Papillion 
Creek just above Offutt AFB, forming Papillion 
21-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Creek. The combined creek flows along the side 
of Offutt AFB to its confluence with the Missouri 
River. 
Existing project. The project consists of a 
series of 20 dams and reservoirs on tributaries of 
Papillion Creek. Project for flood control, recreation, 
and water quality control was authorized by 
the 1968 Flood Control Act. (House Document 
349, 90th Congress). Estimated cost of the improvements 
is $103,400,000 (October 1975) of 
which $97,624,000 is ultimate Federal cost and 
$5,776,000 is future non-Federal reimbursement 
for recreation facilities cost sharing. 
Local cooperation. Local interests will be required 
to: (a) maintain the Papillion Creek channels 
downstream from the damsites free of obstructions 
and available to accommodate reservoir 
releases and uncontrolled flow; (b) insure 
that all new bridge construction, and future 
modification of existing bridges, downstream 
from reservoirs of the proposed system, shall 
have hydraulic capacity acceptable to the Chief of 
Engineers; (c) provide guidance and leadership in 
preventing unwise and uneconomical future 
development of the flood plain areas by encouraging 
prudent use of flood proofing, land regulation 
planning, or other flood plain management techniques 
to reduce flood losses; (d) hold and save 
the United States free from all damages arising 
from water-rights claims resulting from the construction 
and operation of the reservoirs; (e) exercise, 
to the full extent of their legal capability, 
control against removal of streamflow made 
available for water quality control; and (f) in 
accordance with the Federal Water Project 
Recreation Act: (1) administer project land and 
water areas for recreation and fish and wildlife 
enhancement; (2) pay, contribute in kind, or 
repay (which may be through user fees) with 
interest, one-half of the separable first cost of the 
project allocated to recreation and fish and wildlife 
enhancement; and (3) bear all costs of 
operation, maintenance, and replacement of lands 
and facilities for recreation and fish and wildlife 
enhancement. 
Operations and results during fiscal year. Continued 
construction at Dam No. 16, and Dam No. 
11. 
Condition at end of fiscal year. Construction of 
the project, initiated in FY 1972, was advanced 
to 17 percent completion. Dams No. 16 and 11 
are 85 and 61 percent complete, respectively. 
Design studies are in progress on remaining 
work. 
22. PICK-SLOAN MISSOURI BASIN PROGRAM 
(OMAHA DIST.) 
Location. Flood control improvements in this 
project are along Missouri River and several of 
its principal tributaries and in States comprising 
Missouri River Basin. 
Existing project. General comprehensive plan 
for flood control and other purposes in Missouri 
River Basin provides for levees along Missouri 
River between Sioux City, Iowa, and mouth and 
reservoirs on main stem of Missouri River and 
tributaries for control of floodflows at damsites. 
(See table 21-C for authorizing legislation; also 
see table 21-F on projects in Omaha District 
included in comprehensive plan). 
Operations and results during fiscal year. See 
individual reports. 
Condition at end of fiscal year. See individual 
reports. 
23. PIPESTEM LAKE, N. DAK. 
Location. On Pipestem Creek in Stutsman 
County, North Dakota, 3 miles upstream from 
where Pipestem Creek joins the James River at 
Jamestown, North Dakota. 
Existing project. Authorized by 1965 Flood 
Control Act. Consists of a rolled earthfill dam approximately 
102 feet high with a crest length of 
4,000 feet. The outlet works consists of a gated 
reinforced concrete conduit. The reservoir will 
provide 146,880 acre-feet of storage. The multipurpose 
pool will provide space for silt storage 
and 892 acres of water surface for fish, wildlife 
and recreation needs. Estimated cost (October 
1975) is $9,285,000. Non-Federal cost for recreation 
facilities cost sharing is $172,500. 
Local cooperation. Local interests are required 
to administer project land and water areas for 
recreation and fish and wildlife enhancement and 
to bear the first cost of associated improvements 
in the wildlife management area; pay, contribute 
in kind, or repay, with interest, one-half of the 
separable cost of the project allocated to 
recreation and fish and wildlife enhancement; and 
bear all costs of operation, maintenance, and 
replacement of recreation and fish and wildlife 
lands and facilities. 
Operation and results during fiscal year. Land 
acquisition and relocations completed. Construction 
of recreation facilities essentially completed. 
Contracts for multi-purpose building and boundary 
fencing initiated. 
Condition at end of fiscal year. Construction of 
the project initiated FY 1970 and is 98 percent 
complete. Land acquisition, embankment and 
outlet works complete. Recreation essentially 
complete. Multi-purpose building and boundary 
fencing in progress. 
21-8

OMAHA, NEBR., DISTRICT 
24. SACRED HEART HOSPITAL, EMERGENCY 
BANK STABILIZATION, 
YANKTON, S. DAK. 
Location. Project is along the left bank of the 
Missouri River at Yankton, South Dakota. 
Existing project. The project consists of bank 
protection along the left bank of the Missouri 
River to protect Yankton Sacred Heart Hospital 
from a severe erosion problem. Project was 
authorized by the Water Resources Development 
Act of 1974. Estimated cost of the improvement 
is $252,000 (October 1975) of which $250,000 is 
Federal Cost and $2,000 is non-Federal cost. 
Local cooperation. Section 40 of the Water 
Resources Development Act approved 7 March 
1974 applies. Local sponsorship has not been 
established. 
Operation and results during fiscal year. Work 
consisted of preparing General Design Memorandum. 
Condition at end of fiscal year. General Design 
Memorandum essentially complete. Commitment 
from a local sponsor still pending. 
25. SALT CREEK AND 
TRIBUTARIES, NEBR. 
Location. Salt Creek Basin comprises an area 
of about 1,627 square miles in and around 
Lincoln in southeastern Nebraska. 
Existing project. The authorized project consists 
of a system of 10 dams and reservoirs, 
channel clearing, enlarging and realignment, 
levees and necessary bridge alterations. Project 
for flood protection was authorized by 1958 Flood 
Control Act, as recommended by Chief of 
Engineers in House Document 396, 84th Congress, 
2d session. Final cost of improvements for 
the active program is $11,895,621 (July 1972), of 
which $11,724,621 is Federal cost and $171,000 
non-Federal cost. 
Pursuant to Senate Resolution adopted August 
7, 1964, which authorized a review of Salt 
Creek survey report, proposed improvements in 
the Wahoo Creek Basin, including two of the 
authorized dams along Salt Creek downstream 
from Lincoln, above Lincoln, and ultimate plan 
through Lincoln were placed in "deferred" 
classification pending completion of the review. 
Local cooperation. Fully complied with for the 
completed levee and channel improvement part of 
the project. For the dams, local interests are 
required to operate and maintain the permanent 
pools for fish and wildlife conservation and 
assume all costs related to utilization of the 
permanent pools for recreational purposes and 
insure public access to the pools. 
Operations and results during fiscal year. Regular 
funds, maintenance: Operation and maintenance 
activities included sedimentation and 
reservoir regulation studies and intermittent 
inspections of the dams and structures. 
Condition at the end of fiscal year. Construction 
of the project began in the spring of 1962. 
All work under the active portion of the project, 
consisting of the 10 dams and reservoirs and the 
channel improvements and levees through 
Lincoln, was completed in 1969. 
26. SHERIDAN, YELLOWSTONE 
RIVER, WYO. 
Location. At Sheridan and vicinity on both 
sides of Goose and Little Goose Creeks approximately 
11.6 miles above junction of Goose Creek 
with Tongue River. 
Existing project. Overall plan of improvement 
for flood protection at Sheridan consists of a system 
of levees and floodwalls in combination with 
alterations of channels of Goose and Little Goose 
Creeks. Area subject to flooding will be protected 
by approximately 37,700 feet of levee, 4,810 feet 
of floodwall, and 30,140 feet of channel improvements 
including a concrete chute. Project was 
authorized by Flood Control Act of May 17, 1950 
(H. Doc. 216, 81st Cong., 1st sess.). Estimated 
Federal cost (July 1974) is $2,619,000. Estimated 
local cost (July 1974) is $281,000 for relocations, 
lands and damages. 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936, applies. Fully complied 
with for all work completed. Local interests 
proceeding to fulfill requirements for Stage III on 
Goose Creek above the mill cutoff. 
Operations and results during fiscal year. Planning 
for Stage III continued. 
Condition at end of fiscal year. Project is 75 
percent complete. Stage I, the mill cutoff and 
drop structures on Goose Creek and channels and 
levees below the mill cutoff and Stage II levees 
and channels on Little Goose Creek are complete 
and have protected the areas in which they are 
located. Stage III will be initiated upon availability 
of right-of-way. 
27. SOUTH PLATTE RIVER BASIN, COLO. 
Location. Flood control improvements in this 
project are along the South Platte River and its 
tributaries in Colorado. 
Existing project. General plan for flood control 
and other purposes provides for construction of 
Chatfield Lake on the South Platte River, Bear 
Creek Lake on Bear Creek and levee and channel 
improvements on the South Platte River. (See 
table 21-C for authorizing legislation). 
21-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. See 
individual reports. 
Condition at end of year. See individual 
reports. 
28. INSPECTION OF COMPLETED FLOOD 
CONTROL WORKS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests furnish assurances 
that they will maintain and operate certain 
local protection projects after completion in accordance 
with regulations prescribed by Secretary 
of the Army. District Engineers are 
responsible for administration of these regulations 
within boundaries of their respective 
districts. 
Inspections of completed local protection projects 
whhich have been turned over to local 
interests for raintenance and operation during 
the fiscal year are set forth in table 21-G on 
inspections of co~mpet e tocal protection projects. 
Fiscal year costs were $118,150. 
29. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections ? and 9, Flood Control Act of 
December 22, 44, Corps of Engineers is responsible 
f:r ~tai~ d scheduling of operations of 
storage capacity reserved for or assigned to flood 
control in reservoirs constructed by Bureau of 
Reclamation as well as those constructed by 
Corps of Engineers. Fiscal year costs were 
$170,535 and total costs to June 30, 1975 were 
$2,465,721. 
30. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS. 
See table 21-H. 
31. FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
Emergency Flood Control Activities - Repair, 
Flood Fighting and Rescue Work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal costs for fiscal year were $90,063 for 
advance preparation, $4,139 for emergency operations, 
and $438,764 for repair and restoration. 
Small Flood Control Projects Not Specifically 
Authorized by Congress (Sec. 205, 1948 Flood 
Control Act as amended, Public Law 858, 80th 
Cong., June 30, 1948). 
See detailed report for operations on Mud 
Creek, Broken Bow, Nebraska. See Table 21-I for 
preauthorization studies on potential projects. 
Emergency Bank Protection (Sec. 14, 1946 
Flood Control Act, Public Law 526, 79th Cong., 
July 24, 1946). 
Operations under this heading were as follows: 
Minatare, Nebraska Sewage Lagoons -- Rock 
reinforcement for protection of sewage lagoons by 
contract at a fiscal year cost of $364. 
West Nishnabotna River, Mills County, Iowa 
Abutment protection and erosion control measures 
for West Nishnabotna River bridge No. 2, 
near Hastings, Iowa. Fiscal year cost was 
$24,290. 
East Nishnabotna River, Page County, Iowa. 
Abutment protection and erosion control measures 
for East Nishnabotna River bridge near 
Essex, Iowa. Fiscal year cost was $29,491. 
West Nishnabotna River, Mills County, Iowa. 
Abutment protection and erosion control measures 
for West Nishnabotna River bridge in Mills 
County, near Malvern, Iowa. Fiscal year cost 
was $34,489. 
Negative reconaissance reports were submitted 
for two emergency bank protection projects at a 
fiscal year cost of $2,059. 
Snagging and Clearing Projects for Flood Control 
(Sec. 208 of the 1954 Flood Control Act, 
Public Law 780, 83rd Cong. ). 
No activities this fiscal year. 
Aquatic Plant Control (Sec. 302, Public Law 
298, 89th Congress). 
Aquatic plant control studies were continued 
at a cost of $6,108 for the fiscal year. 
Streambank Erosion Control Evaluation and 
Demonstration Act of 1974 (Sec. 32, Public Law 
251, 93rd Congress). 
Erosion control studies were continued on the 
Missouri River, Fort Randall Dam to Sioux City, 
Iowa at a fiscal year cost of $18,374. 
Multiple-Purpose Projects Including Power 
32. BIG BEND DAM-LAKE SHARPE, 
MISSOURI RIVER BASIN, S. DAK. 
Location. On Missouri River, 987.4 miles 
above mouth, near Fort Thompson, S. Dak., and 
approximately 20 miles upstream from Chamberlain, 
S. Dak. Dam is in upstream reach of Fort 
Randall Reservoir and reservoir extends upstream 
to Pierre, S. Dak. 
Existing project. A rolled-earthfill dam 95 feet 
high, a hydroelectric generating plant consisting 
of eight 58,500 kilowatt units, and a chute-type 
gated spillway. Reservoir provides gross storage 
of 1,910,000 acre-feet. Project was authorized by 
1944 Flood Control Act as part of general 
comprehensive plan for flood control and other 
21-10

OMAHA, NEBR., DISTRICT 
purposes in Missouri River Basin. Estimated 
cost (October 1975) is $107,012,000 including 
$142,000 Code 710 funds. 
Local cooperation. None required. 
Operations and results during fiscal year. Regular 
funds, new work: Visitors Center completed. 
Construction contracts were awarded for additional 
Crow Creek Indian Community Facilities 
authorized by PL 92-222. Regular funds, maintenance: 
Project was operated in conjunction 
with other Missouri River reservoirs for flood 
control, navigation, power production and other 
multiple uses. During FY 1975, 1,062,674,000 net 
kilowatt-hours of electricity were produced. 
Condition at end of fiscal year. Construction 
was initiated September 1959 and is 99 percent 
complete. Land acquisition complete except for 
minor acquisitions. Planning underway for remaining 
minor relocation items. On 30 June 1975 
pool elevation was at 1420.1 and 1,750,000 acrefeet 
of water were impounded. 
33. EAGLE BAY AND FORT YATES 
HIGHWAY BRIDGES, N. DAK. 
Location. Across the Missouri River in the 
vicinity of Fort Yates, N. Dak. and across the 
Little Missouri River in the vicinity of Eagle Bay 
in Dunn County, N. Dak. 
Existing project. The comprehensive plan for 
flood control and other purposes in the Missouri 
River Basin, as authorized by the Act of June 28, 
1938 (52 Stat. 1215), and as modified and expanded 
by subsequent Acts, was further modified 
by the 1970 Flood Control Act to authorize the 
Secretary of the Army, acting through the Chief 
of Engineers, to construct a highway bridge 
across the Missouri River at an appropriate location 
midway between Bismarck, North Dakota, 
and Mobridge, South Dakota, and to construct a 
highway bridge over the Little Missouri River at 
the Garrison Reservoir (Lake Sakakawea) in the 
vicinity of Eagle Bay in Dunn County, North 
Dakota. 
Local cooperation. After construction non-Federal 
interests are to own, operate toll free, and 
maintain the bridge and approach facilities. On 1 
June 1972 a cost reimbursable contract was 
entered into with the State of North Dakota 
which provides for design, construction and non- 
Federal requirements for ownership, operation 
and maintenance. 
Operation and results during the fiscal year. 
Site investigations completed for the Missouri 
River crossing in the vicinity of Ft. Yates. 
Condition at the end of the fiscal year. Preliminary 
site report completed for both bridges. 
Detailed site investigations for Missouri River 
crossing in the vicinity of Ft. Yates essentially 
complete. Detailed structural design deferred due 
to Indian Tribal Council objection to construction 
of the bridges. 
34. FORT RANDALL DAM-LAKE FRANCIS 
CASE, MISSOURI RIVER BASIN, S. DAK. 
Location. On Missouri River in Charles, Mix 
and Gregory Counties, S. Dak., about 82 miles 
above Yankton, S. Dak. Site is 880 miles above 
mouth of Missouri River and 148 miles above 
Sioux City, Iowa. 
Existing project. A rolled-earthfill dam with a 
maximum height of 165 feet and a reservoir for 
flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross 
storage capacity of 5,600,000 acre-feet at maximum 
operating pool. The power installation 
consists of eight units nominally rated at 40,000 
kilowatts each. 
Project authorized by Flood Control Act of 
1944 as part of general comprehensive plan for 
flood control and other purposes in Missouri 
River Basin. Estimated cost of project is 
$199,498,140 (October 1975), of which $198,778,- 
140 is Federal cost for construction including 
$1,376,000 Code 710 funds, and $720,000 local 
cost for approaches to Platte-Winner Bridge. 
Local cooperation. None required. 
Operations and results during fiscal year. Regular 
funds, new work: Planning of additional 
recreation facilities was accomplished using Code 
710 funds. Regular funds, maintenance: Project 
was operated in conjunction with other Missouri 
River reservoirs for flood control, navigation, 
power production, and other miltiple uses. Produced 
1,869,660,000 net kilowatt-hours of electricity. 
Condition at end of fiscal year. Construction 
began in May 1946 and was completed in 1969 
except for Code 710 work. Work remaining to 
complete limited to recreation facilities using 
Code 710 funds. On June 30, 1975, reservoir pool 
was at elevation 1362.3 feet mean sea level and a 
total volume 4,365,000 acre-feet of water was impounded. 
35. GARRISON DAM-LAKE SAKAKAWEA, 
MISSOURI RIVER BASIN, N. DAK. 
Location. On Missouri River in McLean and 
Mercer Counties, N. Dak., about 11 miles south 
of Garrison, N. Dak., and 9 miles west of Coleharbor, 
N. Dak. 1,389.9 miles above mouth of 
river and 75 miles above Bismarck, N. Dak. 
Existing project. A rolled-earthfill dam 11,300 
feet long with a maximum height of 202 feet and 
21-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
a reservoir for flood control, irrigation, navigation, 
hydroelectric power, and other purposes 
with a gross storage capacity of 24,200,000 acrefeet. 
It provides five power units rated at 80,000 
kilowatts each, three flood control tunnels and a 
gated spillway. Existing project was authorized 
by 1944 Flood Control Act as part of general 
comprehensive plan for flood control and other 
purposes in Missouri River Basin, and by Public 
Works Appropriation Act, 1968. Estimated 
Federal cost (October 1975) is $300,678,000 
including $770,000 Code 710 funds and $4,208,000 
for major rehabilitation. Non-Federal contribution 
in connection with widening Snake Creek 
Embankment was $784,000. 
Local cooperation. None required except costsharing 
with State of North Dakota for widening 
of Snake Creek embankment. 
Operations and results during fiscal year. Regular 
funds, new work: Public use facilities were 
continued with Code 710 funds. Regular funds, 
maintenance: Garrison Reservoir was operated in 
conjunction with the other Missouri River reservoirs 
for flood control, navigation, power production, 
and other multiple purpose uses. Construction 
of Williston levee repair and road rehabilitation 
were completed. Generating facilities produced 
2,921,342,000 net kilowatt hours of electricity. 
Condition at end of fiscal year. Construction of 
the project initiated April 1946 was completed in 
1966, except for additional recreational development 
utilizing Code 710 funds. Planning is in 
progress for recreational facilities, centralization 
of controls, and minor remaining items. On June 
30, 1975, pool elevation was 1851.3 and 23,125,- 
000 acre-feet of water was impounded. 
36. GAVINS POINT DAM-LEWIS AND 
CLARK LAKE, MISSOURI RIVER 
BASIN, NEBR. AND S. DAK. 
Location. On Missouri River in Yankton County, 
S. Dak., and Knox County, Nebr., about 4 
miles upstream from Yankton, S. Dak., and 
about 811.1 miles above mouth of river. 
Existing project. A concrete and rolled-earthfill 
dam with a maximum height of 74 feet and a 
reservoir for flood control, irrigation, navigation, 
hydroelectric power, and other purposes with a 
gross storage capacity of 515,000 acre-feet at 
maximum operating pool. The power installation 
consists of three units nominally rated at 33,333 
kilowatts each. Existing project was authorized 
by 1944 Flood Control Act as part of general 
comprehensive plan for flood control and other 
purposes in Missouri River Basin. Cost estimate 
(October 1975) is $49,110,050, including $1,053,- 
500 Code 710 funds (recreational facilities on 
completed projects). 
Local cooperation. None required. 
Operations and results during fiscal year. Regular 
funds, maintenance: Project was operated in 
conjunction with other Missouri River reservoirs 
for flood control, navigation, power production 
and other multiple purpose uses. Construction of 
Visitors Center initiated. Three generating units 
were in commercial operation and produced 
768,398,000 net kilowatt hours of electricity 
during fiscal year. Recreational areas were 
extensively used by the public. 
Condition at end of fiscal year. Construction of 
original project was initiated in March 1952 and 
was completed in 1964. Design studies are in 
progress for centralization of controls and maintenance 
items. Construction of Visitors Center in 
progress. Project is providing its multiple purpose 
benefits for flood control, navigation, 
power, and other uses. On June 30, 1975, pool 
elevation was 1205.4 and 385,000 acre-feet of 
water was impounded. 
37. GAVINS POINT DAM-LEWIS AND 
CLARK LAKE-RELOCATION OF 
NIOBRARA, NEBR. 
Location. On the Missouri River in Knox 
County, Nebr. 
Existing project. Project provides for alleviation 
of seepage and groundwater problems in the 
vicinity of Niobrara, Nebraska by relocating the 
town and acquisition of the Niobrara State Park. 
Authorized by the 1970 Flood Control Act and 
amended by the Water Resources Development 
Act of 1974. Estimated cost of the project is 
$14,500,000 (October 1975). 
Local cooperation. None required. 
Operations and results during fiscal year. Construction 
of the relocated townsite was continued. 
Land acquisition in the existing town was 
continued. 
Condition at end of fiscal year. Construction of 
the project was initiated under a cost reimbursable 
contract with the Village of Niobrara 
awarded 28 November 1972. Grading and streets 
for the initial 155 residential lots is essentially 
complete. Land acquisition in the existing town 
is essentially complete. Planning is underway for 
remaining development. 
38. OAHE DAM-LAKE OAHE, MISSOURI 
RIVER BASIN, S. DAK. AND N. DAK. 
Location. Dam is on Missouri River in Hughes 
and Stanley Counties, S. Dak., about 6 miles 
northwest of Pierre, S. Dak., and 1,072.3 miles 
above mouth of river. 
21-12

OMAHA, NEBR., DISTRICT 
Existing project. A rolled-earthfill dam with 
maximum height of 245 feet and reservoir for 
flood control, irrigation, navigation, hydroelectric 
power, and other purposes with a gross 
storage capacity of 23,500,000 acre-feet at maximum 
operating pool. It contains seven power 
units nominally rated at 85,000 kilowatts each. 
Existing project was authorized by 1944 Flood 
Control Act as part of general comprehensive 
plan for flood control and other purposes in 
Missouri River Basin. Estimated cost (October 
1975) is $345,473,000 including $273,000 Code 
710 funds. 
Local cooperation. None required. 
Operations and results during fiscal year. Regular 
funds, new work: Acquisition of reservoir 
lands continued. Preparation of plans and specifications 
continued for remaining work. Continued 
development of recreation facilities and boundary 
monumentation. Regular funds, maintenance: 
Oahe Reservoir project was operated in conjunction 
with the other Missouri River reservoirs for 
flood control, navigation, power production and 
other multiple purpose uses. Generating facilities 
produced 2,971,964,000 net kilowatt hours of 
electricity. 
Condition at end of fiscal year. Construction 
was initiated August 1948 and is 99 percent 
complete. Land acquisition is 97 percent complete. 
All power units on line and producing 
power. Design studies in progress for centralization 
of controls. On June 30, 1975, pool elevation 
was 1614.5 and 21,560,000 acre-feet of water 
impounded. 
General Investigations 
39. SURVEYS 
Fiscal year cost was $1,585,001 of which 
$1,393,007 was for flood control studies, $81,803 
was comprehensive basin studies, $23,009 for 
review of authorized projects, $47,101 for inventory 
of dams and $40,581 for coordination studies 
with other agencies. 
40. COLLECTION AND STUDY OF 
BASIC DATA 
(PrecipitationS tudies) 
Harlan, Iowa storm study completed at a cost 
of $7,640. 
(Flood Plain Management Services) 
Flood Plain Information Reports 
The following flood plain information reports 
were completed and presented to sponsors in FY 
1975, at a fiscal year cost of $14,193. Missouri 
River, Bismarck, N. Dak., $66; Beaverhead 
River, Dillon, Mont., $9,025; Yellowstone River, 
Livingston, Mont., $1,894; and Bear Butte 
Creek, Sturgis, S. Dak., $3,208. 
Flood plain information reports were in preparation 
for Salt and Wahoo Creeks, Ashland, 
Nebr.; Warm Slough and Platte River, Central 
City, Nebr.; Little Sioux River, Cherokee, Iowa; 
Big Sioux River, Sioux City, Iowa; Elkhorn 
River and Rawhide Creek, Fremont, Nebr.; Big 
Thompson River, Larimer - Weld County, 
Colo.; North Platte River, Natrona County, 
Wyo.; and Cache La Poudre River, Windsor 
County, Colo.; Council Bluffs, Iowa; Estes Park, 
Colo.; Floyd River and Willow Creek, LeMars, 
Iowa; Floyd River, Vol III, Sioux City, Iowa; 
and Big Sioux River, Sioux Falls, S. Dak. Fiscal 
year costs were $156,427. 
Flood Plain Management 
Flood plain management service costs for the 
Omaha District were $75,071 and the costs for 
the Missouri River Division office were $33,661 
during the fiscal year. 
Technical Services 
The costs for providing site investigations and 
flood hazard evaluations to military and non-military 
Federal agencies, State and local governmental 
agencies, and to individuals and businesses 
were $52,455. 
(Hydrologic Studies) 
Costs for hydrologic studies for the fiscal year 
were $4,814. 
41. RESEARCH AND DEVELOPMENT 
(Civil Works and Investigations) 
Fiscal year costs for civil works investigations 
amounted to $3,308. 
21-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 21-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Missouri River 
at Fort Peck, 
Mont. 
2. Missouri River, 
Sioux City, 
Iowa to Rulo, 
Nebr. 
5. Bear Creek Lake, 
Colo. 
6. Big Sioux River 
at Sioux City, 
Iowa 
7. Billings, Mont. 
8. Boulder, Colo. 
9. Bowman- Haley 
Lake, N. Dak. 
10. Chatfield Lake, 
Colo. 
11. Cherry Creek 
Lake, Colo. 
12. Fall River 
Basin, S. Dak. 
13. Frazer-Wolf 
Point, Mont. 
14. Great Falls, 
Mont. 
15. Little Papillion 
Creek, Nebr. 
16. Miles City, Mont. 
17. Missouri River, 
Garrison Dam 
to Lake Oahe, 
N. Dak. 
18. Missouri River, 
Kenslers Bend, 
Nebr., to Sioux 
City, Iowa 
Total Cost To 
Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,275 
909,700 
1,227,682 
744,500 
1,486,396 
4,660,300 
4,421,028 
442,600 
399,615 
19,900 
30,843 
93 
148,900 
52,646 
334,773 
341,178 
42,500 
31,393 
9,925,700 
11,117,513 
300 
21,302 
88,300 
70,171 
40,000 
315,515 
40,300 
40,314 
-1,550,800 
2,725 
45,411 
87,474 
42,700 
36,361 
505,400 
891,674 
218,800 
214,181 
19,460 
34,918 
375,000 
520,721 
156,100 
161,544 
10,995 
1,719,510 
1,378,497 
2,475,000 
2,285,894 
3,941,000 
4,389,224 
2,030,000 
1,320,120 
78,000 
46,672 
310 
510 
80,000 
74,253
11 
56,400 
64,727 
10,125,000 
9,938,929 
5,000 
190 
91,200 
107,459 
-6,028 
5,971 
49,100 
42,039 
713 
70,000 
56,483 
25,000 
12,692 
-11,000 
203 
1,567 
5,000 
4,772 
430,000 
539,917 
63,000 
64,284 
-3
43 
1,578,400 
1,680,954 
500,000 
945,072 
4,257,000 
4,402,251 
3,310,000 
3,649,615 
41,904 
-130,000 
7,523 
40,000 
30,548 
7,110,000 
7,949,622 
1,189 
83,400 
69,400 
1,458,900 
1,728,376 
350,000 
753,281 
2,869,000 
3,199,137 
11,860,000 
12,300,802 
48,800 
69,510 
25,000 
8,244 
48,000 
59,032 
6,325,000 
8,367,095 
828 
228,000 
242,537 
86,200 
102,195 
375,000 
7,686 
-88 
10,131 
374 
600,000 
686,888 
37,000 
35,505 
21-14 
157,238,424 
157,238,424 
23,210,310 
22,970,308 
187,860,9911 
187,822,7171 
78,679,4192 
78,639,5042 
18,582,600 
18,148,250 
288,700 
258,565 
74,967 
74,967 
173,900 
142,666 
4,372,174 
4,372,174 
262,543 
259,781 
73,958,700 
73,856,517 
15,056,215 
15,053,364 
1,497,511 
1,496,138 
5,519,432 
5,519,432 
373,141 
367,961 
400,000 
20,378 
345,112 
336,112 
3,643,111 
3,642,888 
79,700 
79,607 
7,285,400 
7,186,848 
11,294,414 
11,294,414 
3,541,069 
3,536,383

OMAHA, NEBR., DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding 
19. Missouri River, New Work: 
Levees, Iowa, Approp. 
Nebr., Kans. Cost 
20. Mud Creek, New Work: 
Broken Bow, Nebr. Approp. 
Cost 
(Contributed Funds) Contrib. 
Cost 
21. Pappillion Creek New Work: 
& Tribs., Nebr. Approp. 
Cost 
23. Pipestem Lake, New Work: 
N. Dak. Approp. 
Cost 
24. Sacred Heart New Work: 
Hospital, Yankton, Approp. 
S. Dak. Cost 
25. Salt Creek and New Work: 
Tributaries, Approp. 
Nebr. Cost 
Maint. 
Approp. 
Cost 
26. Sheridan, New Work: 
Yellowstone Approp. 
River, Wyo. Cost 
32. Big Bend Dam- New Work: 
Lake Sharpe, Approp. 
Missouri River Cost 
Basin, S. Dak. Maint. 
Approp. 
Cost 
33. Eagle Bay-Fort New Work: 
Yates Highway Approp. 
Bridges, N. Dak. Cost 
34. Fort Randall New Work: 
Dam-Lake Francis Approp. 
Case, Missouri Cost 
River Basin, Maint. 
S. Dak. Approp. 
Cost 
35. Garrison Dam- New Work: 
Lake Sakakawea, Approp. 
Missouri River Cost 
Basin, N. Dak. Maint. 
(Federal Funds) Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
(Contributed Major Rehab. 
Funds) Contrib. 
Cost 
36. Gavins Point New Work: 
Dam-Lewis & Approp. 
Clark Lake, Cost 
Missouri River Maint. 
Basin, S. Dak. Approp. 
and Nebr. Cost 
37. Gavins Point New Work: 
Dam- Lewis & Approp. 
Clark Lake, Nebr. & Cost 
S. Dak.-Relocation 
of Niobrara, Nebr. 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
157,900 
151,107 
446,900 
8,820 
1,986,100 
1,983,778 
1,630,600 
2,021,326 
38,800 
41,915 
167,800 
76,389 
1,503 
2,223,500 
772,448 
1,150,300 
1,158,161 
347,600 
5,391 
6,500 
9,838 
2,279,400 
2,152,181 
34,800 
34,042 
2,564,700 
2,324,192 
893,700 
859,273 
280,000 
257,260 
23,800 
3,418 
2,026,700 
2,082,546 
744,800 
195,000 
292,843 
-59,400 
27,192 
3,760,000 
4,432,443 
3,052,000 
3,446,408 
621 
146,600 
235,509 
149,965 
17,575 
70,000 
1,682,246 
1,428,045 
1,200,269 
36,552 
288,126 
1,036 
2,234,785 
2,389,555 
65,000 
33,691 
2,460,395 
2,814,187 
200,000 
235,641 
21,256 
2,297,465 
1,899,530 
2,179,000 
59,508 
11,000 
22,000 
492,572 
5,280,000 
5,228,638 
2,230,000 
1,792,764 
123,000 
121,505 
139,000 
9,380 
521,000 
953,804 
1,555,000 
1,568,719 
282,000 
198,184 
13,022 
3,240 
2,620,000 
2,419,279 
99,986 
68,679 
2,915,000 
2,641,823 
-250,000 
8,691 
-68,039 
-6 
8 
2,505,000 
2,742,659 
1,150,000 
3,421,734 
149,088 
172,299 
411,497 
285,000 
284,317 
6,391,000 
5,919,163 
417,000 
747,034 
125,000 
8,348 
280,000 
281,542 
- 240,000 
9,745 
344,000 
-273,544 
1,821,000 
2,002,015 
-3,000 
126,110 
425,000 
130,419 
2,620,000 
2,869,128 
105,000 
97,936 
2,810,000 
3,499,553 
-35,390 
-24,331 
24,981 
2,516,000 
2,590,666 
3,665,390 
4,228,296 
21,637,388 
21,634,980 
1,000,000 
1,000,000 
285,000 
284,317 
19,317,100 
17,989,971 
9,259,600 
9,067,608 
125,000 
8,348 
11,847,6213 
11,847,6213 
1,108,475 
1,108,092 
1,978,965 
1,965,847 
106,738,500 
105,909,628 
11,030,074 
10,980,089 
663,152 
617,811 
197,977,162 
197,672,078 
25,564,292 
25,432,550 
292,534,917 
292,446,354 
27,913,620 
27,777,310 
4,208,310 
4,208,310 
686,961 
686,961 
49,070,054 
49,070,054 
20,141,415 
19,899,125 
7,739,1904 
7,709,5384 
21-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
38. Oahe Dam-Lake New Work: 
Oahe, Missouri Approp. 2,135,400 1,974,000 550,000 532,000 344,193,400 
River Basin, Cost 2,416,401 1,460,172 1,281,279 522,602 343,933,785 
S. Dak. & N. Dak. Maint. 
Approp. 1,814,700 2,190,900 2,967,000 2,575,000 19,870,825 
Cost 1,774,566 2,120,092 2,383,914 3,107,892 19,654,357 
1. Includes $18,325,581 National Industrial Recovery 4. Does not include $200,000 allotted to Special Studies, 
Act funds, $8,625,718 emergency relief funds, and $1,181,125 General Investigations for study on relocation of Niobrara, 
for previous project. Nebraska. 
2. Includes $235,122 for previous project and $200,000 
fiscal year 1968 supplemental appropriation funds. 
3. Includes $123,000 of government cost applicable to 
that portion of the project which is currently being carried in 
a deferred status. 
TABLE 21-B MISSOURI RIVER, SIOUX CITY, IOWA TO RULO, NEBRASKA 
TOTAL COST OF EXISTING PROJECT TO JUNE 30, 1975 
(See Section 2 of Text) 
Cost 
Funding New Work Maintenance Total 
Regular Funds $160,871,418 $78,639,504 $239,510,922 
Public Works Funds 18,325,581 0 18,325,581 
Emergency Relief Funds 8,625,718 0 8,625,718 
Total Funds 187,822,717 78,639,504 266,462,221 
TABLE 21-C AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
MISSOURI RIVER, SIOUX CITY, IOWA TO RULO, NEBR. 
(See Section 2 of Text) 
Appropriation of $12 million authorized for existing project. 
Appropriation of $15 million additional allotments totalling 
$29,153,108 made by Public Works Administration under 
provisions of National Industrial Recovery Act of 1938, 
and $9,669,791 allotted under provisions of Emergency 
Relief Appropriations Act of 1935. 
For completion of project from mouth of Sioux City, Iowa. 
For a channel of 9-foot depth and 300-foot width. 
CHERRY CREEK LAKE, COLO. (See Section 11 of Text) 
Initiation and partial accomplishment of project. 
Completion of plan approved in Act of Aug. 18, 1941. 
H. Doc. 1120, 60th Cong., 
2d Sess. 
H. Doc. 238, 73rd Cong., 2d 
Sess. 
H. Doc. 214, 76th Cong., 1st 
Sess. 
H. Doc. 426, 76th Cong., 1st 
Sess. 
H. Doc. 426, 76th Cong., 1st 
Sess. 
21-16 
Jan. 12, 1927 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 18, 1941 
Dec. 22, 1944

OMAHA, NEBR., DISTRICT 
TABLE 21-C (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Dec. 22, 1944 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sept. 3, 1954 
May 2, 1956 
July 3, 1958 
July 14, 1960 
Dec. 30, 1963 
June 18, 1965 
May 12, 1967 
Aug. 13, 1968 
June 19, 1970 
Dec. 24, 1970 
Dec. 23, 1971 
Mar. 7, 1974 
Aug. 18, 1941 
Dec. 22, 1944 
May 17, 1950 
May 12, 1967 
Aug. 13, 1968 
1970 
Dec. 23, 1971 
Mar. 7, 1974 
General comprehensive plan, Missouri River Basin. 
PICK-SLOAN MISSOURI BASIN PROGRAM (OMAHA DIST.) 
(See Section 20 of Text) 
Adopted general comprehensive plan for Missouri River Basin 
and authorized $9 million for initiation and partial 
accomplishment 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, Nebr., 
and authorized additional $7 million. 
Expanded general comprehensive plan for Missouri River 
Basin and authorized additional $200 million. 
Authorized additional $150 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Authorized additional $250 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Expanded general comprehensive plan for Missouri River 
Basin and authorized additional $217,710,000. 
Modified general comprehensive plan for Missouri River 
Basin by deletion of construction of Red Willow Dam and 
Reservoir, Nebr., and addition of construction of Wilson 
Dam and Reservoir, Kans. 
Expanded general comprehensive plan for Missouri River 
and authorized additional $200 million. 
Authorized additional $207 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Authorized additional $80 million for prosecution of general 
comprehensive plan for Missouri River Basin and modified 
the plan to include work protection and rectification 
works below Garrison Dam. 
Authorized additional $116 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Authorized additional $20 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Authorized additional $38 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Authorized additional $109 million for prosecution of 
general comprehensive plan for Missouri River Basin. 
Change comprehensive plan name to Pick-Sloan Missouri Basin 
Program. 
Authorized additional $101 million for prosecution of 
Pick--Sloan Missouri Basin Program. 
Authorized additional $72 million for prosecution of Pick-Sloan 
Missouri Basin Program. 
MISSOURI RIVER LEVEE SYSTEM, IOWA, NEBR., KANS., 
AND MO. (See Section 26 of Text) 
Levees along both sides of river from Sioux City to 
Kansas City. 
Extended project from Kansas City to mouth and provided for 
increased protection. 
SOUTH PLATTE RIVER BASIN, COLO. (See Section 33 of Text) 
Adopted plan of improvement for South Platte River Basin 
and authorized $26 million for initiation and partial 
accomplishment. 
Authorized additional $2 million for prosecution of plan. 
Authorized additional $12 million for prosecution of plan 
and Bear Creek Lake. 
Authorized additional $21 million for prosecution of plan. 
Authorized additional $37 million for prosecution of plan. 
Authorized additional $15 million for prosecution of plan. 
H. Doc. 821, 76th Cong., 3d 
Sess. 
H. Doc. 475, 78th Cong., 2d 
Sess. 
S. Docs. 191 and 247, 78th 
Cong., 2d Sess. 
H. Doc. 669, 80th Cong., 2d 
Sess. 
21-17 
H. Doc. 475, and S. Does. 191 
and 247, 78th Cong., 2d Sess. 
Flood Control Committee Doc. 1, 
75th Cong., 1st Sess. 
H. Doc. 842; 76th Cong., 3d 
Sess. 
H. Doc. 475, and S. Does. 191 
and 247, 78th Cong., 2d Sess. 
H. Does. 549 and 642, 81st 
Cong., 2d Sess. 
H. Doc. 84th Cong., 2d 
Sess. 
S. Doc. 91-1100, 91st Cong., 
2d Sess. 
- --- - -- I- ------

TABLE 21-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Big Sioux River, S. Dak., and Iowa1 1952 
Missouri River, Sioux City, Iowa to 
Fort Benton, Mont.2 1948 3,123,141 644,863 
Small Navigation Project at 
Sioux City, Iowa2 1970 129,500 46,100 
1. Deferred 
2. Complete 
TABLE 21-E MISSOURI RIVER, SIOUX CITY, IOWA TO RULO, NEBR. 
TERMINAL FACILITIES 
(See Section 2 of Text) 
As of 30 June 1975 
Miles 
Above 
Description of Facility Mouth Bank Nearest Town 
Marina Inn Motel 
Sioux City Municipal Dock 
Kay Kee Feed Co. 
Big Soo Terminal Dock 
Jebro Inc. 
Terra Chemical Int. 
Borden Chemical Co. 
Smith Douglas Div. 
Blenco (N.F.O.) 
Agrico Chemical Co. 
Consolidated Storage Inc. 
Agrico Chemical Co. 
Ft. Calhoun Stone Co. Terminal 
Grain Loading (Far-Mar-Co.) 
Boat Ways (Penzien, Inc.) 
Cement Unloading 
Cargo Carriers, Inc. 
Greater Omaha Marina 
Omaha Municipal Dock, Sioux City 
& New Orleans (Cargill Molasses) 
N.F.O. 
Farmland Industries 
Grain Loading--Salt and Fertilizer 
Unloading (Cargill Grain) 
Terminal Packaging Corp. (Anti-Freeze) 
Tallow Loading-Molasses and Salt 
Unloading (National Molasses and 
Morton Salt) 
Liquid Fertilizer Unloading and 
Loading (Allied Chemical) 
Plattsmouth Municipal Dock 
Grain Loading (Far-Mar-Co.) 
Rock Dock 
Liquid Fertilizer Unloading-- 
Steinhart Terminal Bulk 
Grain Loading (N.F.O.) 
732.0 
731.4 
731.2 
727.8 
727.5 
718.7 
716.6 
680.6 
648.5 
648.2 
647.7 
640.4 
624.8 
624.5 
624.2 
624.0 
617.9 
616.3 
616.3 
614.5 
614.4 
614.1 
612.2 
595.3 
591.6 
584.5 
574.4 
562.6 
562.5 
Right 
Left 
Left 
Left 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
Left 
Left 
Left 
Right 
Right 
Right 
Right 
Right 
Right 
Right 
South Sioux City, Nebr. 
Sioux City, Iowa 
Sioux City, Iowa 
Sioux City, Iowa 
Sioux City, Iowa 
Sioux City, Iowa 
Sioux City, Iowa 
Blenco, Iowa 
Blair, Nebr. 
Blair, Nebr. 
Blair, Nebr. 
Ft. Calhoun, Nebr. 
Omaha, Nebr: 
Omaha, Nebr. 
Omaha, Nebr. 
Omaha, Nebr. 
Omaha, Nebr. 
Omaha, Nebr. 
Omaha, Nebr. 
Council Bluffs, Iowa 
Council Bluffs, Iowa 
Council Bluffs, Iowa 
Omaha, Nebr. 
LaPlatte, Nebr. 
Plattsmouth, Nebr. 
Rock Bluff, Nebr. 
Union, Nebr. 
Nebraska City, Nebr. 
Nebraska City, Nebr. 
21-18

OMAHA, NEBR., DISTRICT 
MISSOURI RIVER, SIOUX CITY, IOWA TO RULO, NEBR. 
TERMINAL FACILITIES 
(See Section 2 of Text) 
TABLE 21-E (Continued) As of 30 June 1975 
Miles 
Above 
Description of Facility Mouth Bank Nearest Town 
Nebraska City Municipal Dock 562.4 Right Nebraska City, Nebr. 
Grain Loading (Bartlett Grain Co.) 562.4 Right Nebraska City, Nebr. 
Steinhart Terminal Dock 562.3 Right Nebraska City, Nebr. 
Grain Loading (Consolidated Blenders) 561.8 Right Nebraska City, Nebr. 
Grain Loading (Continental Grain Co.) 535.5 Right Brownville, Nebr. 
Patterson Barge Terminal Inc. 503.03 Left Mound City, Missouri 
TABLE 21-F PICK-SLOAN MISSOURI BASIN PROGRAM 
(See Section 23 of Text) 
Estimated Estimated 
Project Federal Cost Non-Federal Cost 
Garrison Dam, Lake Sakakawea, N. Dak. 1 $300,678,300 $784,000 
Missouri River Levee System, Iowa, Nebr., 
Kansas and Missouri (Sioux City, Iowa to 
Rulo, Nebr.) 1', 25,900,000 3,100,000 
Oahe Dam-Lake Oahe S. Dak., & N. Dak.' 345,473,000 - 
Big Bend Dam-Lake Sharpe, S. Dak. 1 106,870,000 - 
Fort Randall Dam, Lake Francis Case, S. Dak.1 198,778,140 720,000 
Gavins Point Dam, Lewis & Clark Lake, S. Dak. 
& Nebr.1 49,110,100 
Gavins Point Dam, Lewis & Clark Lake, S. Dak. 1 
& Nebr.-Relocation of Niobrara, Nebr. 14,500,000 - 
Omaha, Nebraska2 5,903,640 362,000 
Council Bluffs, Iowa2 2,557,680 145,800 
Missouri River, Garrison Dam to Lake Oahe, 
N. Dak.1 9,200,000 265,000 
1Details presented on individual report. 
2 Completed. 3Active portion of project. 
21-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 21-G INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
(See Section 28 of Text) 
Location Inspection Dates 
Montana 
Glasgow, Milk River 10 Sep 74 - 
Saco, Beaver Creek 10 Sep 74 - 
Harve, Milk River 11 Sep 74 - 
Harve, Scott Coulee-Bull Hook Dam 12 Sep 74 - 
Clyde Park, Shields River 15 Sep 74 - 
Three Forks, Lower Madison River 14 Sep 74 - 
Forsythe, Yellowstone River 18 Sep 74 - 
West Glendive, Yellowstone River 19 Sep 74 - 
Vaughn, Sun River 13 Sep 74 - 
*Shields River, Grannis Bridge, Near Livingston - - 
*Shields River, Chadborne Bridge, Near 
Livingston - - 
*Yellowstone River, Water Plant, Livingston Sep 74 - 
*Yellowstone River, Hiway 23 Bridge, Near Sidney Sep 74 - 
*Yellowstone River, Reedpoint Bridge Sep 74 - 
*Yellowstone River, Greycliff Bridge Sep 74 - 
*Yellowstone River, Springdale Bridge Sep 74 - 
*Yellowstone River, Custer Co. Bridge, Near 
Miles City Sep 74 - 
*Yellowstone River, Bank Protection, Billings Sep 74 - 
*Yellowstone River, Yellowstone Co. Bridge, Near 
Billings Sep 74 - 
*Yellowstone River, Voges Bridge, Near Big Timber Sep 74 - 
*Jefferson River, Willow Creek Bridge, Near 
Three Forks Sep 74 - 
*Jefferson River, Bank Protection, Near Waterloo Sep 74 - 
*Big Hole River, Pennington Bridge, Near 
Twin Bridges Sep 74 - 
*Ruby River, Wheatly Bridge, Near Twin Bridges Sep 74 - 
*Big Horn River, Two Leggin Bridge, Near Hardin Sep 74 - 
*Missouri River, Bank Stabilization, Fort Benton Sep 74 - 
Wyoming 
Greybull, Big Horn River 16 Sep 74 - 
Sheridan, Big and Little Goose Creeks 17 Sep 74 - 
*Shoshone River, Bank Protection, Lovell Sep 74 
North Dakota 
Williston 2 Dec 74 - 
Mandan, Lower Heart River 30 Sep 74 - 
Marmarth, Little Missouri River 1 Oct 74 - 
Scranton, Buffalo 30 Sep 74 - 
South Dakota 
Sioux Falls, Big Sioux River 12 Dec 74 20 Jun 75 
Belle Fourche, Belle Fourche River 30 Oct 74 - 
Rapid City, Cedar Canyon Dam 30 Oct 74 - 
Hot Springs, Fall River Channel 31 Oct 74 - 
Herreid, Spring Creek 29 Oct 74 - 
Cold Brook 31 Oct 74 - 
Cotton Wood Springs 31 Oct 74 - 
*Missouri River, Bank Protection, Greenwood Oct 74 - 
*Bad River, Bank Protection, Fort Pierre Oct 74 - 
*Big Sioux River, Schofield Bridge, Near 
Flandreau Oct 74 20 Jun 75 
*Big Sioux River, Fink Bridge, Near Flandreau Oct 74 20 Jun 75 
21-20

OMAHA, NEBR., DISTRICT 
TABLE 21-G (Continued) INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
(See Section 28 of Text) 
Location Inspection Dates 
Colorado 
Aurora, Westerly Creek - - 
*Plum Creek, Bank Stabilization, Aurora - - 
*South Platte River, Bank Protection, Denver - - 
Nebraska 
Omaha, Missouri River 1 Oct 74 16 May 75 
Waterloo, Elkhorn River 16 Aug 74 1 May 75 
West Point, Elkhorn River 15 Aug 74 6 May 75 
Pierce, Elkhorn River 19 Aug 74 13 May 75 
Clarkson, Middle Fork, Maple Creek 15 Aug 74 7 May 75 
Hooper, Elkhorn River 15 Aug 74 6 May 75 
Norfolk, North Fork, Elkhorn River - 12 Dec 74 14 May 75 
Madison, Union & Taylor Creeks 20 Aug 74 12 May 75 
*Missouri River, Bank Protection, Near Aten - - 
*Platte River, M.U.D. Protection, Cedar Island Aug 74 14 May 75 
*Platte River, Bank Protection, Louisville Aug 74 4 Apr 75 
*Elkhorn River, Q Street Bridge, Near Gretna Aug 74 20 Feb 75 
*Elkhorn River, Ray Bridge, Near Norfolk Aug 74 13 May 75 
*North Platte River, Bank Stabilization, Minatare Nov 74 - 
*Logan Creek, Bank Protection, Near Bancroft Aug 74 20 Feb 75 
*Battle Creek, Bank Protection, Battle Creek Aug 74 13 May 75 
Schuyler, Platte River - - 
Schuyler, Lost Creek & Platte River - 20 May 75 
Little Papillion, Little Papillion Creek 8 Oct 74 12 May 75 
Gering Valley, Gering Drain & Tributaries 6-7 Nov 74 - 
Macy, Blackbird Creek 15 Nov 74 30 Apr 75 
Lincoln, Salt Creek & Tributaries 27 Nov 74 5 Mar 75 
Meadow Grove, Buffalo Creek 19 Aug 74 23 May 75 
Columbus, Loup River - 20 May 75 
Broken Bow, Mud Creek - 21 May 75 
Iowa 
Council Bluffs, Missouri River 15 Oct 74 6 May 75 
Ida Grove, Maple River-Odebolt Creek 29 Jul 74 29 Apr 75 
Sioux City, Floyd River 10 Dec 74 5 May 75 
Hawarden, Dry Creek 9 Aug 74 28 Apr 75 
Red Oak, Nishnabotna River 26 Nov 74 29 Apr 75 
Hamburg L-575, Nishnabotna River 2 Dec 74 21 Apr 75 
Intercounty D.D., Little Sioux River 1-2 Oct 74 15-16 Apr 75 
Nagel D.D., Little Sioux River 3 Oct 74 16 May 75 
Bennett - McDonald - Smithland D.D., Little 
Sioux River 4 Oct 74 16 May 75 
*Big Sioux River, Bank Protection, Sioux City Oct 74 22 May 75 
*West Nishnabotna River, Mills Co. Bridge, 
Near Malvern Dec 74 6 Jun 75 
*West Nishnabotna River, Mills Co. Bridge, 
Near Hastings Dec 74 6 Jun 75 
*East Nishnabotna River, Page Co. Bridge, 
Near Essex Dec 74 6 Jun 75 
*Missouri River, Marina, Sioux City Oct 74 
Missouri River Levees 
L-624 & L-627, Mosquito Creek & Sieck Levees 16 Oct 74 4 Apr 75 
L-601, Watkins Levee District 8 Aug 74 7 Apr 75 
L-601, Miller-Sturgeon Levee District 8 Aug 74 7 Apr 75 
L-601, Missouri River Levee District #1 3 Dec 74 11 Apr 75 
L-594, Waubansie Drainage District 13 Aug 74 9 Apr 75 
21-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 21-G (Continued) INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
(See Section 28 of Text) 
Location Inspection Dates 
Missouri River Levees (cont.) 
L-594, Pleasant Valley Levee District 13 Aug 74 9 Apr 75 
L-575, Benton--Washington Levee District 14 Aug 74 11 Apr 75 
L-575, Northwest Atchison Levee District 9 Dec 74 21 Apr 75 
L-575, McKissock Island Levee District 9 Dec 74 21 Apr 75 
L-575, Buchannan Levee District 9 Dec 74 21 Apr 75 
L-561, L-550, L-536, Atchison County 
Levee District 4-5 Dec 74 27-28 Mar 75 
R-613, Sarpy Co. Soil & Water Cons. D. 17 Oct 74 3-4 Mar 75 
R-562, Peru Levee District 28 Aug 74 25 Apr 75 
R-548, Brownville-Nemaha Levee District 6 Dec 74 24 Apr 75 
R-548, Little Nemaha Levee District 6 Dec 74 24 Apr 75 
R-520, Richardson Co. Levee Dist. #8 25 Nov 74 23 Apr 75 
R-573, Otoe County Drainage Dist. #2 7 Aug 74 2 May 75 
* Denotes Section 14 Projects 
TABLE 21-H OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Belle Fourche, Cheyenne River, S. Dak.1 1940 37,410 - 
Blackbird Creek near Macy, Nebr.2 1970 262,479 - 
Buffalo Creek, Meadow Grove, Nebr. 2 1974 293,016 - 
Buffalo Creek, Scranton, N. Dak. 2 1960 102,980 - 
Castlewood Lake, Qherry Creek and 
Tributaries, Colo. 1943 56,721 - 
City of Aurora, Westerly Creek, Colo.2 1955 150,000 - 
Clarkson, Nebraska, Maple Creek2 1967 191,281 - 
Council Bluffs, Iowa (Act of 1936) 1939 325 - 
Council Bluffs, Iowa (Act of 1944)2 1954 2,557,680 - 
Davids Creek Lake, Iowa (Act of 1968)3 1972 4,865,000 - 
Dayton, Wyo.3 1956 - - 
Dry Creek, Hawarden, Iowa2 1964 400,000 - 
East Nishnabotna River, Red Oak, Iowa2 1963 400,000 - 
Floyd River, Sioux City, Iowa2 1970 11,556,667 - 
Forsyth, Mont.2 1950 255,177 - 
Gering Valley, Nebr. 2 1971 5,989,663 - 
Giles Creek, Elkhorn, Nebr. 3 1952 - - 
Glasgow, Mont.2 1939 16,832 - 
Greybull, Wyo. 2 1960 248,507 - 
Harve, Mont.2 1958 1,837,167 - 
Herreid, Spring Creek, S. Dak. 2 1954 50,216 - 
Hooper, Nebr. 2 1968 326,667 - 
Ida Grove, Iowa 2 1972 522,344 - 
Jamestown Reservoir, N. Dak.2 1950 40,000 - 
Linton, N. Dak. 3 1973 43,136 - 
Little Nemaha River, Nebr.3 1973 129,290 - 
Little Sioux River and Tributaries, Iowa 2 1970 15,482,919 - 
Loup River, Columbus, Nebr. 2 1973 1,000,000 - 
Lower Big Sioux River, Iowa and S. Dak. 3 1966 - - 
Lower Heart River, N. Dak. 2 1964 1,961,173 - 
McCook Lake, S. Dak.2 1958 147,627 - 
21-22

OMAHA, NEBR., DISTRICT 
TABLE 21-H (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Madison, Nebr. Union and Taylor Creeks 2 
Mandan, Heart River, N. Dak.2 
Marmarth, N. Dak. 2 
Miles City, Mont. 
Missouri River, Aten, Nebr.2 
Missouri River, Niobrara, Nebr.2 
Morrison, Bear Creek, Colo. 3 
Mott, N. Dak. 3 
Nishnabotna River at Hamburg, Iowa2 
Norfolk, Nebr. 2 
Omaha, Nebr.2 
Pierce, Nebr.2 
Platte River near Schuyler, Nebr.2 
Platte River and Lost Creek, Schuyler, Nebr.2 
Red Dale Gulch, Rapid City, S. Dak.2 
Saco, Mont. 2 
Shell Creek, Nebr. 3 
Shields River, near Clyde Park, Mont.2 
Shoshone River, Lovell, Wyo.2 
Sioux Falls, S. Dak. 2 
Vaughn, Mont., Sun River2 
South Platte River Levees and Channel 
Improvements, Cltfield Lake to 
Ft. Morgan, Colo.o 
Waterloo, Nebr. 2 
West Point, Nebr. 2 
Yellowstone River, W. Glendive, Mont. 2 
1967 
1960 
1960 
1956 
1951 
1945 
1950 
1948 
1971 
1954 
1967 
1948 
1971 
1960 
1958 
1962 
1951 
1963 
1966 
1971 
1957 
1970 
1966 
1960 
234,839 
676,916 
169,498 
578,791 
99,370 
30,000 
236,000 
3,400,504 
5,903,640 
296,597 
74,940 
257,398 
120,482 
67,793 
71,314 
25,747 
14,350 
5,288,707 
457,582 
10,000 
237,883 
149,597 
230,294 
5,633 
-
- 
1. Completed as a Public Works Administration project. 
2. Project Complete. 
3. Inactive. 
TABLE 21-I FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
(See Section 31 of Text) 
Fiscal Year 
Study Cost 
(Flood Control Activities Pursuant to Section 205, Public Law 858, 
80th Congress, as Amended) (Preauthorization) 
Casper, Wyo. -North Platte River $1,225 
Pender, Nebr.-Logan Creek 36,052 
Columbus, Nebr.-Lost Creek 6,133 
Rapid City, S. Dak. 14,381 
Sturgis, S. Dak. 37,665 
Schuyler, Nebr.-Platte River & Lost Creek -5,510 
TOTAL $89,946 
21-23

OHIO RIVER* 
For actual construction of locks and dams, and 
operation and care of completed structures, river 
is divided into three sections under immediate 
supervision and direction of district engineers at 
Pittsburgh, Huntington and Louisville. 
Pittsburgh section extends 127 miles from head 
of river at Pittsburgh, Pa., to a point immediately 
upstream from New Martinsville, W.Va., and includes 
Emsworth, Dashields, Montgomery, New 
Cumberland and Pike Island locks and dams, 
locks and dams 12, and 13, and Hannibal locks 
and dam. Huntington section extends 311 miles 
from mile 127 to 438 immediately upstream from 
Foster, Ky., and includes locks and dams 15, 16, 
Willow Island, 17, Belleville, Racine, Gallipolis, 
Greenup and Captain Anthony Meldahl locks and 
dams. Louisville section extends 543 miles from 
mile 438 to mouth of river, and includes 
Markland and McAlpine locks and dams (with 
Louisville and Portland Canal), Cannelton, Newburgh 
and Uniontown locks and dams and locks 
and dams 50 to 53 inclusive. The Nashville District 
has been assigned the design and construction 
of Smithland locks and dam located in the 
Louisville District. 
IMPROVEMENTS 
Navigation Page 
1. Construction of locks and dams on 
Ohio River ................................... . 22-1 
Navigation (Cont'd) Page 
2. Open channel work, Ohio River... 22-4 
1. CONSTRUCTION OF LOCKS 
AND DAMS ON OHIO RIVER 
Location. Ohio River is formed by junction of 
Allegheny and Monongahela Rivers at 
Pittsburgh, Pa., and flows generally southwesterly 
for 981 miles to join Mississippi River near 
Cairo, Ill. For description of river see page 1227, 
1932 Annual Report. 
Previous projects. For details see page 1907 of 
Annual Report for 1915. 
Existing project. Provides for improvement of 
entire river by construction of locks and dams to 
provide a channel depth of 9 feet and for widening 
Louisville and Portland Canal at Louisville, Ky. 
Project provides for a lock with usable dimensions 
of 110 by 600 feet at each of the dams and, in 
addition, an auxiliary lock 56 by 360 feet is 
available at Emsworth, Dashields, Montgomery, 
and McAlpine locks and dams with an auxiliary 
lock at Gallipolis being 110 by 360 feet. Dashields 
is a fixed dam, while Emsworth, Montgomery, 
and Gallipolis are fixed dams with movable 
crests. Remaining dams are movable type, with 
navigable pass varying in width from 600 to 1,248 
feet. In addition to navigable pass, movable-type 
dams are also provided with one or more 
regulating weirs. At McAlpine locks and dam a 
canal (Louisville and Portland) extends along left 
bank for 2 miles, with locks at lower end. 
Modifications to existing project under purview 
of Section 6, March 3, 1909 Act, provide for fixed 
dams with movable crests with two locks (110 by 
1,200 feet and 110 by 600 feet) at New 
Cumberland, Pike Island, Hannibal, Willow 
Island, Belleville, Racine, Greenup, Captain 
Anthony Meldahl, Markland, Cannelton, Newburgh, 
Uniontown, and Mound City, two locks 
110 by 1,200 feet at Smithland, 110 by 1,200 foot 
temporary locks in addition to the existing locks 
at locks and dams 52 and 53, and reconstruction to 
provide a 110 by 1,200 foot lock in addition to existing 
locks and a fixed dam with two sections of 
movable crest at McAlpine locks and dam, widening 
Louisville and Portland Canal to 500 feet. 
Operation and care of locks and dams were included 
in project July 1, 1935, under provisions of 
Permanent Appropriations Repeal Act of June 
26, 1934. Estimated Federal cost of new work (existing 
project) (1975), exclusive of Gallipolis locks 
*Tributary navigation projects and all flood control projects in Ohio River Basin are in reports of districts included in Ohio 
River Division. 
22-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
and dam reported under Kanawha River project 
is $1,549,593,303, estimated non-Federal cost is 
$14,864,000. Foregoing estimate does not include 
expenditures on previous projects. Various items 
previously included in this project are considered 
inactive or unnecessary and are excluded from 
foregoing cost estimate. See page 693, Annual 
Report, 1968 for items and estimated cost. Under 
authority of 1910 River and Harbor Act, 
Louisville and Portland Canal was widened to 200 
feet; locks and dams 40 and 42 eliminated; locks 
and dams 1 and 2 replaced by Emsworth locks 
and dam; lock and dam 3 replaced by Dashields 
locks and dam; and locks and dams 4, 5, and 6 
replaced by Montgomery locks and dam. Locks 
and dams 24, 25, and 26 were replaced by 
Gallipolis locks and dam authorized by August 
30, 1935 Act, and constructed under project for 
improving lower Kanawha River. Locks and 
dams 7, 8, and 9 were replaced by New 
Cumberland locks and dam, locks and dams 10 
and 11 were replaced by Pike Island locks and 
dam, lock and dam 14 replaced by Hannibal locks 
and dam, which is presently under construction, 
locks and dams 18, 19 and 20 were replaced by 
Belleville locks and dam, locks and dams 21, 22 
and 23 were replaced by Racine locks and dam, 
locks and dams 27, 28, 29, and 30 were replaced 
by Greenup locks and dam, locks and dams 31, 32, 
33, and 34 were replaced by Captain Anthony 
Meldahl locks and dam, locks and dams 35, 36, 37, 
38, and 39 were replaced by Markland locks and 
dam, the Louisville and Portland Canal widened 
to 500 feet, and locks and dams 43, 44 and 45 were 
replaced by Cannelton locks and dam, presently 
under construction, locks and dams 46 and 47 
were replaced by Newburgh locks and dam 
presently under construction, locks and dams 48 
and 49 were replaced by Uniontown locks and 
dam, presently under construction, as 
modifications to existing project under purview 
of section 6, March 3, 1909 Act, reducing total 
number of structures to 25. Table 22-D contains 
data relative to various features of locks and dams 
included in existing project. For list of principal 
towns and cities along Ohio River with their 
mileage below Pittsburgh, Pa., see page 1060 Annual 
Report, 1962. See Table 22-C for licenses. 
Terminal facilities. Modern public terminals, 
with warehouses, equipped with operating 
machinery for transferring materials, have been 
constructed by private interests at some of the 
larger cities and towns. A list of terminals on Ohio 
River is revised annually as of June 30, and can be 
obtained from Division Engineer, U.S. Army 
Engineer Division, Ohio River, Cincinnati, Ohio. 
Operations and results during fiscal year. New 
work by contract and hired labor: 
Hannibal locks and dam: Dedication of Hannibal 
Locks and Dam is scheduled for September 
1975; construction of locks started August 1967 
and was completed August 1971; dam work was 
begun in July 1970 and is 97 percent complete; 
contract for removal of Lock and Dam 14 is complete; 
removal of L/D 13 is 75 percent complete; 
contract for removal of L/D 12 was let in April 
1975, and is scheduled for completion in 
November 1975; contracts for Wheeling Island 
bank protection, mooring piers at upper pool, 
landscaping, and recreation facilities are all 
scheduled for completion by November 1975; 27 
tracts of land acquired; $10,500,594. 
Willow Island locks and dam: Construction initiated 
in January 1967, is 90 percent complete. 
Contract for construction of the locks, awarded in 
October 1968 is complete; contract for construction 
of the dam, awarded in December 1971, is 82 
percent complete; contract for Public Use 
Facilities at St. Marys and New Martinsville, W. 
Va., awarded in June 1974 and is 98 percent complete; 
contract for Municipal Facilities, St. 
Marys, Sistersville, W. Va. and New Matamoras, 
Ohio, awarded in March 1975 and is 48 percent 
complete; engineering and design for remaining 
construction work continued; 142 tracts of land 
acquired; $9,461,887. 
Belleville locks and dam: All construction work 
complete; $129. 
Racine locks and dam: Construction initiated in 
June 1964, is 98 percent complete. All major construction 
is essentially complete; engineering and 
design work continued for construction of 
remaining recreational facilities and mooring 
facilities; $175,426. 
Greenup locks and dam: All major construction 
work complete; miscellaneous recreational work 
completed; $11,063. 
Markland locks and dam: Project is complete 
except for additional recreation facilities under 
the completed project program. Contract for 
recreation facilities Big Bone Site was advanced 
to 99 percent completion; cost was $204,522 for 
recreation facilities under the completed projects 
program. 
In connection with the Markland Locks and 
Dam, the Congress has authorized the appropriation 
of funds for the design and construction of a 
public highway bridge across the navigation 
structure by the Federal-Aid Highway Act of 
1970 (Public Law 91-605) and the State of Indiana 
and the Commonwealth of Kentucky have agreed 
to construct necessary approach roads, within 
their respective States, to connect the bridge with 
existing public highways. The said bridge and 
approach roads design and later construction is 
being accomplished by the Louisville District under 
the terms of a four-party contract with the 
22-2

OHIO RIVER 
Department of Transportation. Federal 
Highway Administration, the State of Indiana, 
and the Commonwealth of Kentucky that requires 
the latter three parties to be jointly responsible 
for the entire cost of the bridge and approach 
roads. Contract for construction of the 
bridge and roads is scheduled for award in July 
1975. 
McAlpine locks and dam: Project is complete 
except for alteration of lift section of railroad 
bridge that spans the upper end of the Louisville 
and Portland canal which work is presently 
deferred, and remote control system for dam 
gates. Contract for remote control system for dam 
gates remained at 99 percent complete; $24,945. 
Cannelton locks and dam: Project is 96 percent 
complete. Project dedication ceremony was held 
on 24 November 1974. Construction of dam and 
locks emergency dam and land acquisition 
remained at 99 percent completion. Maintenance 
dredging during construction was completed. 
Contract for replacement of damaged dam gate 
No. 12 was advanced to 50 percent completion. 
Contract for remote control system of dam gates 
and for mooring facilities were awarded and advanced 
to 53 percent and 23 percent completion, 
respectively. Contract for stone protection 
downstream of locks on Indiana bank was awarded 
and completed. Engineering & design of 
remaining project features continued; $1,286,- 
029. 
Newburgh locks and dam: The Newburgh 
Bank Protection Works project was combined 
with the locks and dam project by the Water 
Resources Development Act of 1974. Project is 90 
percent complete. Construction of dam was advanced 
to 95 percent completion. The navigation 
pool was raised to new project level in January 
1975 and old locks and dams 46 and 47 were deactivated 
in April 1975. Boundary line marking advanced 
to 84 percent completion and contract for 
Cypress Creek clearing was awarded and completed. 
Maintenance dredging during construction 
continued while dredging at upstream guard 
wall for operation of draft curtains was started 
and completed. Contract for mooring facilities 
was awarded and advanced to 18 percent completion. 
Two contracts for interim emergency 
repairs for the caving bank at the Town of Newburgh 
were awarded and completed. Engineering 
& design of remaining project features continued; 
$8,068,025. 
Uniontown locks and dam: Project is 92 percent 
complete. Construction of dam was advanced to 
98 percent completion. The navigation pool was 
raised to new project level in January 1975 and 
old locks and dams 48 and 49 were deactivated in 
April 1975. Land acquisition was advanced to 78 
percent completion and boundary line marking 
was advanced to 80 percent completion. Contract 
for rock brm downstream of the fixed weir section 
of the dam advanced to 98 percent completion. 
Maintenance dredging during construction 
continued. Engineering & design of remaining 
project features continued; $12,514,942. 
Smithland locks and dam: Project is 46 percent 
complete. Contract for construction of locks 
awarded in June 1971 is 88 percent complete. 
Phase IV of contract for reservoir mapping was 
completed during first quarter of FY 1973. Land 
acquisition is 36 percent complete. Contract for 
construction of dam awarded in August 1974 is 11 
percent complete. Three contracts awarded for 
steel sheet piling are 58 percent complete. 
Engineering and design about 81 percent complete; 
$27,467,730. 
Lock and Dam No. 53 (Temporary lock): Project 
is 25 percent complete. Seven supply contracts 
for used and new steel sheet piling advanced 
to 75 percent completion. Contract for 
construction of the temporary lock, work on the 
dam and dredging the approach channels was 
awarded in July 1974 and advanced to 10 percent 
completion. Engineering & design related to construction 
continues; $8,092,840. 
Operation and maintenance, general: Locks 
and dams operated as required and necessary 
repairs and improvements made thereto and to 
operator's quarters, grounds and esplanades. 
Costs were $3,425,458 for Pittsburgh District, 
$3,472,301 for Huntington District and $5,359,- 
096 for Louisville District. 
Condition at end of fiscal year.Navigation 
system of 25 locks and dams is in operation and 9- 
foot navigation throughout length of river is 
generally available at all times. At certain unstable 
bars project depth is maintained by dredging, 
supplemented by contraction works. (See 
"Open Channel Work, Ohio River".) Table 22-D 
shows cost and year of completion of locks and 
dams now in operation. Existing project does not 
provide adequate facilities for present-day 
navigation due to obsolescence of structures. 
Since repair and modernization of these facilities 
would be extremely costly, replacement and 
reconstruction is being accomplished as rapidly 
as funds are made available for the purpose. Construction 
of lock and dam replacement program 
was initiated in fiscal year 1955. New 
Cumberland, Pike Island, Hannibal, Belleville, 
Racine, Greenup, Captain Anthony Meldahl, 
Markland, McAlpine, Cannelton, Newburgh and 
Uniontown replacement locks and dams are in 
operation, replacing 32 old low-lift locks and 
dams. Construction of Willow Island locks and 
dam to replace locks and dams 15, 16 and 17 was 
initiated in fiscal year 1967; and Smithland locks 
and dam to replace locks and dams 50 and 51 was 
22-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
initiated in fiscal year 1971. For total cost of existing 
project, see Table 22-B. 
2. OPEN CHANNEL WORK, OHIO RIVER 
Location. Under jurisdiction of district 
engineer in whose district the work is located. 
Portion of river included in project extends 974.7 
miles from head of river at Pittsburgh, Pa., to 
mouth of Cache River (Mound City, Ill.). Open 
channel improvement from mouth of Cache River 
to mouth of Ohio River is under jurisdiction of 
Mississippi River Commission. 
Existing project. Before completion of canalization 
project, no project depth had been fixed by 
Congress under project for open channel work, 
but in order to properly aid packet and-barge 
navigation it was necessary to secure a low-water 
channel with a minimum depth of from 4 to 6 feet, 
and a width, depending upon difficulty of running 
channel, of from 400 to 600 feet; also to permit 
movement of large coal tows, which movement 
occurred at stages of water exceeding 10 
feet, it was necessary to remove points of projecting 
bars which formed at various locations along 
river. Accomplishment of this purpose involved 
concentration of current by closing back channels 
at islands with low dams, contraction and 
straightening wide, open channels by low dikes, 
dredging bars and shoals, and removal of snags 
and wrecks. Incidental to direct improvement of 
Ohio River is construction and maintenance of ice 
piers as required for protection of river crafts. 
Stage of extreme high water on Ohio River varies 
from 46 feet at Pittsburgh, Pa., to 80 feet at Cincinnati, 
Ohio, with 57.2 feet at Louisville, Ky. 
(head of falls), 53.8 feet at Evansville, Ind., and 
59.5 feet at Cairo, Ill. (mouth of river). Estimated 
cost of new work (1960) is $16,160,000, exclusive 
of following items which are considered inactive: 
Ice piers authorized by 1927 River and Harbor 
Act; reforestation of sloughs on Kentucky Peninsula 
near Evansville, Ind., authorized by 1930 
River and Harbor Act; dredging to widen 
channel at certain points; and placing revetment 
at various points. Estimated cost of these items 
(1954) is $6,565,000. Operation of snag boats on 
Ohio River below Pennsylvania State line was included 
in project July 1, 1935, under provisions of 
Permanent Appropriations Repeal Act of June 
26, 1934. See Table 22-E for authorizing legislation. 
Local cooperation. River and Harbor Act of 
January 21, 1927, authorizing construction of ice 
piers for general open channel work, imposes condition 
that before work is begun on any pier, local 
interests convey to the United States free of cost 
such riparian rights an may be deemed necessary 
in connection with the improvement at locality 
(H. Doc. 187, 67th Cong., 2d sess.) Existing ice 
piers are adequate for present purposes and local 
cooperation is not needed since no additional construction 
is under consideration. River and Harbor 
Act of July 3, 1930, provides for reforestation 
of sloughs of Kentucky Peninsula and bank 
protection and that no expense shall be incurred 
by the United States for acquiring lands required 
for purpose of this improvement (H. Doc. 409. 
69th Cong., 1st sess.). However, since no serious 
overbank erosion has occurred since bank revetment 
in 1933-34, reforestation is not considered 
justifiable at this time and no local cooperation is 
required. 
Operations and results during fiscal 
year.Operation and maintenance, general: 
Dredging, where required to provide an adequate 
and dependable channel of project depth at 
minimum pool conditions, was executed. Dike 
and revetments maintained and routine work of 
maintaining navigation aids, removing snags, 
making channel studies, hydrographic surveys 
and mapping was performed as required. 
Channel soundings, hydrographic surveys, 
stream gaging operations, channel inspections 
and aids to navigation, and miscellaneous inspections 
and reports cost $590,688. Dredging by 
hired labor: Huntington District 325,430 cubic 
yards at $492,181 and Louisville District, 577,917 
cubic yards at $366,324, and dredging by contract: 
Huntington District 75,626 cubic yards at 
$89,995; and Louisville District 1,756,877 cubic 
yards at $1,451,205. Contract repair of the revetment 
at Kentucky Peninsula was accomplished in 
the fiscal year at a cost of $113,816 and hired 
labor maintenance thereon was accomplished at a 
cost of $6,554. 
Condition at end of fiscal year. New work under 
this project is substantially complete, since it is 
not anticipated that work on inactive portion of 
project will be accomplished. In addition to 
dredging, local stabilization of channel has been 
effected at various points by construction of dikes 
and revetment. Work which remains consists of 
dredging to widen channels at certain points to 
project depth. 
22-4

OHIO RIVER 
TABLE 22-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Construction of New Work 
Locks and Dams Approp. 73,073,993 78,826,981 83,294,605 69,472,436 1,154,578,087 ' 
on Ohio River Cost 79,680,911 78,275,081 80,203,716 77,860,198 1,147,606,637 
Maint. 
Approp. 11,954,891 11,967,569 12,470,410 11,869,807 305,530,346 
Cost 9,960,757 12,188,625 13,033,404 12,425,070 304,518,783 
Rehab. 
Approp. - - - - 1,283,510 
Cost - - - - 1,283,510 
2. Open Channel New Work 
Work, Ohio River Approp. - - - - 15,962,260 
Cost - - - - 15,962,260 
Maint. 
Approp. 1,470,003 2,411,571 2,503,602 2,843,355 58,596,426 
Cost 1,462,792 2,102,064 3,230,621 3,104,209 58,534,056 
Rehab. 
Approp. - - - - 944,649 
Cost - - - - 944,649 
1. Includes $17,003,761 for previous 6-foot canalization fur such purposes, and $267 transferred to project without 
project. reimbursement. 
2. Includes $36,943,217 expended from 1885 to 1937 on 8. Includes $1,040,236 Public Works funds. 
operation and care of work of improvement under provisions 9. Includes $1,000 for removal of obstructions in Lickof 
permanent indefinite appropriations for such purposes. ing River under authority of section 3, R&H Act of 1930. 
3. Includes $215,812 public works acceleration, ex- 10. Includes $100,000 placed in FY 1971 Budget Reserve. 
ecutive 1963. 11. Excludes $3,899 transferred from project without 
4. Includes $38,766 public works acceleration, ex- reimbursement. 
ecutive 1963. 12. Surplus property valued at $3,553 transferred to pro- 
5. Excludes $251,785 contributed funds for new work. i,<1 without reimbursement. 
6. Excludes $250,118 contributed funds for new work. 13. Excludes $2,140 transferred to project without reim- 
7. Excludes $1,621,349 expended in operation of snag bursement. 
boats under provisions of permanent indefinite appropriation 
TABLE 22-B CONSTRUCTION OF LOCKS AND DAMS ON OHIO RIVER 
TOTAL COST OF EXISTING PROJECT TO JUNE 30, 1975 
(See Section 1 of Text) 
Operations and 
Maintenance, 
Funds New Work General Rehabilitation Total 
Regular $1,125,929,859 $265,435,900 $1,283,510 $1,392,649,269 
Public Works 3,258,368 - - 3,258,368 
Emergency Relief 1,198,837 19,000 - 1,217,837 
Maintenance and Operation - 2,081,900 - 2,081,900 
Public Works Acceleration, 215,812 38,766 - 254,578 
Executive 1963 
Total $1,130,602,8761 5 $267,575,5662 4 6 $1,283,510 $1,399,461,9523 
1Excludes surplus property valued at $297,385 permanent indefinite appropriation. 
transferred to project without reimbursement. 5Excludes $3,899 transferred from project without reim- 
2Excludes surplus property valued at $73,832 transferred bursement. 
to project without reimbursement. 6Excludes $2,140 transferred to project without reim- 
3Excludes $250,118 contributed funds for new work. bursement. 
4Excludes $36,943,217 expended from 1885 to 1937 under
22-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 22-C FEDERAL POWER COMMISSION LICENSES AT 
LOCKS AND DAMS, OHIO RIVER 
Markland Dam McAlpine Dam 
F.P.C. License 2,211 289:1,000 
License Public Service Co. Louisville Gas and 
of Indiana Electric Co. 
Annual Charge $45,950.00 $95,000 (#289) 
$6.60 (#1,000) 
Collections to end of 
fiscal year 1975 $365,711.64 $4,465,304.60 
22-6

OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool Depth on Year Actual Cost 
Miles Width Length Eleva- Miter Sills Character of Foundation Percent Opened to Date of 
Lock Below Distance from of Available Lift tion Com- to Navi- Each Lock 
and Pitts- Nearest Town (ham- For Full (feet) (feet, Upper Lower Lock Dam plete gation and Dam 
Dam burgh her Width mean feet) (feet) 
(feet) (feet) sea 
level) 
1 Replaced - - - - - - 870,034 
6.2 Emsworth locks and dam, 
Emsworth, Pa. 
Replaced 
Replaced 
13.3 Dashields locks and dam, 
1.6 miles below Sewickley, 
Pa. 
Replaced 
Replaced 
Replaced 
31.7 Montgomery locks and 
dam, 1.4 miles above 
Industry, Pa. 
- Replaced 
- Replaced 
54.4 New Cumberland locks and 
dam, Stratton, Ohio 
- Replaced 
- Replaced 
- Replaced 
84.3 Pike Island locks and dam, 
2 miles upstream from 
Warwood, W. Va. 
12 87.4 Warwood, W. Va. 
13 96.1 McMechen, W. Va. 
14 - Replaced 
126.4 Hannibal locks and dam, 
1.6 miles upstream from 
New Martinsville, W. Va. 
15 129.1 New Martinsville, W. Va. 
16 146.5 Bens Run, W. Va. 
161.7 Willow Island, locks and 
110 600 18.0 710.0 
56 360 
110 600 
56 360 10.0 692.0 
110 600 
56 360 17.5 682.0 
110 1,200 
110 600 20.5 664.5 
110 1,200 
110 600 17.8 644.0 
110 600 8.4 626.2 
110 600 7.3 617.8 
110 1,200 
110 600 21.0 623.0 
110 600 7.8 602.2 
110 600 7.8 594.4 
110 1,200 
17.0' 4 12.93 
15.51 12.93 
13.41 17.5' 
Rock Rock and piles 100 1921 5,861,7652 
976,767 
1,144,588 
Rock Rock 
16.0' 14.6 Rock and piles Rock and piles 100 
7.0' 14.88 Rock 
17.0' 18.03 Rock 
Rock 
Rock 
15.4 11.0 Piles in sand Piles in sand 100 
and gravel and gravel 
13.8 10.4 Piles in sand Rock piles in 100 
and gravel sand and 
gravel 
38.0 17.0 Rock 
15.4 11.0 
15.4 ' 11.2 
Rock 
Rock 
Rock 
Rock 
Rock 
100 1929 3,528,955 
1,071,472 
1,080,132 - 
1,123,442 
1936 5,737,611 
1,075,000 
1,167,456 
100 1959 38,827,544 
- - 1,177,100 
1,138,000 
- 1,162,165 
100 1963 56,607,962 
1916 1,166,104 
1911 1,222,389 
1,133,371 
93 1972 81,118,8606 
100 1916 1,180,478 
100 1917 1,275,532 
TABLE 22-D 
2
3
4
5
6
7
8
9 
10 
11

TABLE 22-D 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool Depth on Year Actual Cost 
Miles Width Length Eleva- Miter Sills Character of Foundation Percent Opened to Date of 
Lock Below Distance from of Available Lift tion Com- to Navi- Each Lock 
and Pitts- Nearest Town ('ham- For Full (feet) (feet, Upper Lower Lock Dam plete gation and Dam 
Dam burgh her Width mean feet) (feet) 
(feet) . (feet) sea 
level) 
dam, 2.7 miles above 
Waverly, W. Va. 
17 167.5 4.5 miles above Marietta, 
Ohio 
- Replaced 
- Replaced 
- Replaced 
203.9 Belleville locks and dam, 0.3 110 
mile below Reedsville, 110 
Ohio 
- Replaced 
- Replaced 
- Replaced 
237.5 Racine locks and dam, 1.5 110 
miles below Letart Falls, Ohio 110 
- Replaced 
- Replaced 
Replaced 
279.2 Gallipolis locks and dam, 0.7 110 
miles below Hogsett, W. Va. 110 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
341.0 Greenup locks and dam, 4.9 110 
miles below Greenup, Ky. 110 
- Replaced 
- Replaced 
18 
19 
20 
21 
22 
23 
24 
25 
26 
27 
28 
29 
30 
31 
32 
33 
34 
35 
36 
37 
110 
110 
110 600 20.0 602.0 35.0 15.0 Rock and piles 
110 600 8.2 586.6 15.4 11.0 Rock 
1,200 
600 22.0 582.0 
1,200 
600 22.0 560.0 
600 
360 26.0 538.0 
1,200 
600 30.0 515.0 
- , 
1,200 
600 30.0 485.0 
37.0 15.0 Rock and piles 
18.0 15.0 Rock and piles 
18.0 12.0 Rock 
18.0' 13.0 Rock 
18.0' 15.0 Rock 
Rock 90 1972 66,886,3507 
Rock 100 1918 1,362,891 
S-- 927,091 
1,213,848 
936,696 
Rock 100 1968 62,153,959 
- - -1,484,562 
1,218,798 
1,851,488 Z 
Rock 98 1971 64,830,164 
-- - 1,187,542 
1,925,205 
1,307,241 
Rock 100 1937 8 
- - - 2,015,601 
-- - 1,063,133 
-- -- 1,088,802 
-- 1,579,618 
Rock 100 1959 55,742,030 
- - - 1,359,231 
- -2,951,216 e, 
-- -1,937,166 
-- 3,437,057 
Rock 100 1962 74,164,520 
1,894,942 
3,704,535 
1,297,924 
- Replaced 
Replaced 
436.2 Captain Anthony Meldahl 
locks and dam, 2.2 miles 
above Foster, Ky. 
Replaced 
Replaced 
Replaced

OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool Depth on Year Actual Cost 
Miles Width Length Eleva- Miter Sills Character of Foundation Percent Opened to Date of 
Lock Below Distance from of Available Lift tion Com- to Navi- Each Lock 
and Pitts- Nearest Town Cham- For Full (feet) (feet, Upper Lower Lock Dam plete gation and Dam 
Dam burgh her Width mean feet) (feet) 
(feet) (feet) sea 
level) 
38 Replaced 2,857,040 
531.5 Markland locks and dam, 1 110 1,200 
mile above Markland, Ind. 110 600 
Replaced 
Eliminated 
604.4 McAlpine locks and dams. 
(Reconstruction of locks 
and dam 41.) 
Replaced 
Replaced 
35.0 455.0 
110 1,200 
110 600 37.0 420.0 
56 360 
Replaced 
720.7 Cannelton locks and dam, 3 110 1,200 25.0 383.0 
miles above Cannelton, Ind. 110 600 
Replaced 
776.1 Newburgh locks and dam, 110 1,200 
16 miles above Evansville, 110 600 16.0 358.0 
Ind. 
Replaced 
Replaced 
Replaced 
846.0 Uniontown locks and dam 110 1,200 
3.5 miles below Union- 110 600 22.0 342.0 
town, Ky. 
50 876.8 1 mile below Weston, Ky. 110 600 10.0 320.0 
51 903.1 0.6 mile below Golconda, Ill. 110 600 8.0 310.0 
918.5 Smithland locks and dam, 2 110 1,200 
miles above Smithland, Ky. 110 1,200 22.0 324.0 
52 938.9 1.4 miles below Brookport, 110 600 12.0 302.0 
Ill. 
938.9 1.4 miles below Brookport, 110 1,200 12.0 302.0 
Ill. (New Lock) 
53 962.6 10.8 miles above Mound 110 600 13.4 290.0 
City, Ill. 
962.6 10.8 miles above Mound 110 1,200 13.4 290.0 
City, Ill (New Lock) 
50.0 15.0 Rock 
49.0 
19.0 
19.0 
12.0 
11.0 
11.0 
Rock 
38.0 13.0 Rock 
32.0 16.0 Rock 
Piles 100 1963 63,011,493 
- 2,222,448 
--- 7,658,1349 
Rock 10010 1961 45,724,932 
--- 2,592,242 
2,819,930 
- 3,202,890 
Rock 97 1972 94,719,354 
C
x
0 
3,129,028 
Pile 90 1975 93,837,28711 
4,415,526 
3,062,710 
3,325,964 
34.0 12.0 Rock Rock 92 1975 90,504,17412 
17.4 11.0 Rock Rock and pile 100 1928 3,751,762 
15.4 11.0 Rock and pile Pile 100 1929 4,370,566 
34.0 12.0 Rock 
15.4 11.0 Pile 
15.4 11.0 Pile 
15.4 9.61 Pile 
15.4 9.6 Pile 
Rock 46 
Pile 100 
- 109,329,33513 
1928 4,461,747 
Pile 100 1969 10,197,518 
Pile 100 1929 5,410,668 
25 -9,300,147 
TABLE 22-D 
(Continued) 
39 
40 
41 
43 
44 
45 
46 
47 
48 
49

(Continued) to ocIcuIo 1 o 1 1 exi 
Lock Dimensions Upper 
Normal 
Greatest Pool Depth on Year Actual Cost 
Miles Width Length Eleva- Miter Sills Character of Foundation Percent Opened to Date of 
Lock Below Distance from of Available Lift tion Com- to Navi- Each Lock 
and Pitts- Nearest Town Cham- For Full (feet) (feet, Upper Lower Lock Dam plete gation and Dam 
Dam burgh ber Width mean feet) (feet) 
(feet) (feet) sea 
level) 
974.2 Mound City locks and dam, 110 1,200 
1 mile below Mound City 110 600 31.0 302.0 46.0 15.0 Pile Pile - 1,539,47014 
Ill. 
54 974.2 Mound City, Ill - - 
Total 1,140,612,40215 
'Depths are on emergency dam foundation and are controlling depths. 
2
Change from fixed dam to lift-gate dam completed in 1938. 
3
Depths are on poiree dam foundation and are controlling depths. 
4
Land chamber. 
5
River chamber. 
SWill replace locks and dams 12 and 13. 
TWill replace locks and dams 15, 16 and 17. 
"Roller-gate dam. Cost not included in total. Constructed under project for improving 
lower Kanawha River. 
9
Lock and dam 41 completed with 110-by 600-foot lock in 1921. Completed with 
new dam and raised canal and lock walls in 1928. Auxiliary 56-by 360-foot lock constructed 
in 1929-30. Reconstruction and modernization began 1956, renamed 
McAlpine locks and dam in 1960. Operation of auxiliary lock suspended in 1971. 
1
oComplete except for deferred alteration of railroad bridge. 
"Adjusted figure. Now includes $52,061 for Newburgh Bank Protection. 
l2Will replace locks and dams 50 and 51. 
'Dam below not yet constructed. Depth on lower miter sill at lower water. 
4
Will replace locks and dams 52 and 53 and eliminate 54 from project. 
1
5
Exclusive of $6,994,235, details below. 
Additional Features Entering into Cost of Project 
Louisville and Portland Canal and Indiana chute (under $ 5,359,203 
previous project) 
Examinations, surveys contingencies, plants and 966,232 
miscellaneous 
Recreation facilities, pool area, Gallipolis locks and dams 668,800 
6,994,235 
Total $1,147,606,637 
N 
0
0
z
O
41 
Mz 
MJ 
l J 
V 
v 
T
Va 
V , 
TABLE 22-D OHIO RIVER LOCKS AND DAMS

OHIO RIVER 
TABLE 22-E AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
OPEN CHANNEL WORK, OHIO RIVER (See Section 2 of Text) 
Project adopted by this act originally covered entire 
length of Ohio River from its mouth near Cairo to 
Pittsburgh, a distance of 981 miles. It provided for 
removal of all obstructions which tend to endanger 
steamboat navigation. 
Construct ice piers as a part of project, with funds H. Doc. 187, 67th Cong., 2nd sess. 
allotted from appropriations for general open channel 
work. 
Reforestation of sloughs on Kentucky Peninsula near H. Doc. 409, 69th Cong. 1st sess. 
Evansville, Ind., and a 200-foot strip along upstream 
bank and for bank protection, at an estimated cost of 
$200,000. 
Act of Mar. 3, 1827 modified to include maintenance H. Doc. 434, 84th Cong., 2nd sess. 
of existing Licking River Channel within lower 3-mile 
limit of River slack water, at an estimated increase of 
$1,000 in cost of average annual maintenance. 
22-11 
March 3, 1827 
Jan. 21. 1927 
July 3, 1930 
July 3, 1958

NASHVILLE, TENN., DISTRICT* 
This district comprises portions of southern 
Kentucky, southwestern Virginia, western North 
Carolina, northern Georgia and Alabama, 
northeastern Mississippi and practically all of 
Tennessee except western portion, and embraces 
drainage basins of Tennessee and Cumberland 
Rivers and their tributaries. 
IMPROVEMENTS 
Flood Control (cont) 
1. Construction of Locks and Dams, 
Ohio River ....................................... 23-1 
2. Cumberland River, Tenn. and Ky. 23-1 
3. Tennessee River, Tenn., Ala., and 
K y................................... ............ 23-3 
4. Tennessee-Tombigbee Waterway, 
Alabama and Mississippi ............ 23-4 
5. Other authorized navigation 
projects .................... .................... 23-5 
Alteration of Bridges 
6. Authorized Alteration of Bridges 23-5 
Flood Control 
7. Martins Fork Lake, Ky................. 23-5 
8. Middlesboro, Cumberland River 
Basin, K y......................................... 23-6 
9. Ohio River Basin (Nashville 
Dist.) ..................................... 23-6 
10. Inspection of completed flood 
control projects............................ 23-6 
11. Other authorized flood control 
projects...................................... ... 23-6 
12. Flood control work under special 
authorization................................... 23-6 
Multiple-Purpose Power Projects 
13. Center Hill Lake, Ohio River 
Basin, Tenn..................................... 23-6 
14. Dale Hollow Lake, Ohio River 
Basin, Tenn. and Ky...................... 23-7 
15. J. Percy Priest Dam and 
Reservoir, Ohio River Basin, 
Tenn.................................... 23-7 
16. Laurel River Lake, 
Ohio River Basin, Ky..................... 23-8 
17. Wolf Creek Dam-Lake 
Cumberland, Ohio River 
Basin, Ky ........................................ 23-8 
18. Other authorized multiplepurpose 
power projects .............. 23-9 
General Investigations 
19. 
20. 
21. 
Surveys........................................... 
Collection and study of basic data 
Research and development .......... 
23-9 
23-9 
23-9 
Navigation 
1. CONSTRUCTION OF LOCKS 
AND DAMS, OHIO RIVER 
For report on this improvement see this 
heading under Ohio River. 
2. CUMBERLAND RIVER, TENN. 
AND KY. 
Location. Formed by junction of Poor and 
Clover Forks in Harlan County, Ky., about 694.2 
miles above its mouth, and flows west to Burnside, 
Ky., from whence it makes a loop 
southwestward into Tennessee, passes Nashville, 
and returns northwestward to Kentucky, emptying 
into Ohio River near Smithland, Ky. (See 
Geological Survey base maps of Tennessee and 
Kentucky.) 
Previous projects. For details see pages 1898 
and 1901 of Annual Report for 1915, and page 
1208 of Annual Report for 1938. 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
23-1 
Navigation Page Page

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. Below Nashville: For information 
concerning construction of locks and 
dams A, B, C, D, E and F, required dredging and 
related costs to secure 6 foot navigation, see pages 
1069 and 1070 of Annual Report for 1962. Improvement 
of Cumberland River between mouth 
and Nashville was authorized for 9-foot navigation; 
increased project depth to be obtained by 
construction of three moderate height dams with 
lockage facilities, designated as Kuttawa 
(Eureka), Dover, and Cheatham, to replace existing 
locks A to F inclusive below Nashville and 
lock 1 above Nashville. (See table 23-B for 
authorizing legislation.) Subsequent authorities 
provided for construction of hydroelectric powergenerating 
facilities at Cheatham Dam, river 
mile 148.7, and modification of project for navigation 
on Cumberland River, Tenn. and Ky., to 
provide, in lieu of previously authorized works at 
Kuttawa, mile 32.2, and Dover, mile 100.1, for 
construction of a multiple-purpose improvement 
consisting of a dam, lock, and powerplant near 
mile 30.6 on lower Cumberland River and a canal 
fQr navigation and other purposes connecting this 
reservoir with reservoir formed by Kentucky 
Dam on the Tennessee River. The project is 
known as Barkley Dam and Lake Barkley. Provision 
of interconnecting canal, involving excavation 
of a channel through narrow watershed 
divide about 2.5 miles upstream from damsite, 
permits alternative routes available for navigation 
between either Cumberland or Tennessee 
Rivers and Ohio River, and affords integrated 
operation of Barkley and Kentucky Reservoirs 
through diversion of flows in interests of flood 
control and power production. Estimated cost of 
modified project for 9-foot navigation and 
multiple-purpose development is $176,930,200 
(October 1975). (See table 23-C for listing of principal 
features.) 
Under flood conditions as regulated by upstream 
reservoirs, extreme fluctuation in stage of 
river below Nashville, Tenn., varies at different 
localities from about 16 to 55 feet above minimum 
pool levels. Ordinary fluctuations vary with 
power flows from as much as the allowable 3-foot 
drawdown below normal pool elevation 385 at 
Cheatham Lock and Dam to a range of about 7 
feet at Nashville. Seasonal variation in normal 
headwater levels at Lake Barkley is 5 feet, which 
in combination with power flows produces fluctuations 
up to 10 feet below Cheatham Lock and 
Dam. 
Above Nashville: See pages 1693 thru 1696 of 
Annual Report for 1950 for information including 
statistical data on locks and dams 1 to 17 
and 21. Completion information is shown on 
pages 1454 of the report for 1951. See Table 23-B 
for Authorizing Legislation. Construction of Old 
Hickory, Carthage, and Celina Dams above 
Nashville was also authorized for navigation and 
power. The dam and reservoir authorized for 
construction on Cumberland River near 
Carthage, Tenn., has been redesignated as Cordell 
Hull Dam and Reservoir. Cost of Old Hickory 
and Cordell Hull projects, including locks, is estimated 
as $133,701,700 (October 1975). Estimated 
cost of Celina Dam (1959) is $39,100,000. 
(See table 23-C at end of chapter for listing of 
principal features.) 
Under flood conditions as presently regulated, 
including effect of surcharge operation of Old 
Hickory project, extreme fluctuations of stage in 
this section of river vary from a range of 35 feet at 
Nashville (mile 191) to a maximum of 46 feet immediately 
below Old Hickory Dam (mile 216.2), 
and from an 8-foot variation in headwater at dam 
to 36 feet in vicinity of Carthage, Tenn., (mile 
313.5), present head of navigation; with 
variations up to 35 feet at Celina, Tenn. (mile 
380.8) and 29 feet in tailwater at Wolf Creek Dam 
(mile 460.9). Maximum fluctuations under ordinary 
conditions from power flows vary from 
about 7 feet at Nashville to 14 and 3 feet, respectively, 
in tailwater and headwater of Old Hickory 
Dam, and at other key points as follows: 13 feet at 
Carthage; 18 feet at Celina; and 19 feet at Wolf 
Creek Dam. 
Further details on project authorization for 
river sections below and above Nashville are 
shown on Table 23-B. 
Local cooperation. Fully complied with for 6- 
foot navigation project. Under modified project 
for 9-foot navigation and multiple-purpose 
development, recreation features of reservoir 
components are subject to certain conditions of 
non-Federal cost-sharing under Federal Water 
Project Recreation Act of 1965. 
Terminal facilities. There are 37 terminals on 
the Cumberland River (1 municipally owned and 
open for public use; 3 government owned 
facilities and 33 privately owned facilities). A 
total of 22 terminals have railroad conniections. 
Principal commodities handled are petroleum 
products, sand gravel, coal, coke, iron and steel. 
Nine terminals are set up to handle various types 
of commodities. Facilities considered adequate 
for existing commerce. For further information 
see page 695 of Annual Report for 1969. 
Operations and results during fiscal year. New 
work: Below Nashville: Contract for construction 
of public use facilities at Hurricane Creek, Site 
24, Lake Barkley was fiscally completed during 
FY 1975. Costs for new work under Code 711 
were $11,915. 
Above Nashville: The final recreation contract 
under Code 712 program at Shutes Branch Site, 
Old Hickory Project, is 83% complete. Construction 
of recreation facilities at three sites was com- 
23-2

NASHVILLE, TENN., DISTRICT 
pleted at Cordell Hull during FY 1975. Contract 
for construction of project overlook, right bank 
access road completion, and additional recreation 
facilities is essentially complete. Contract for 
Parking Area and Ramp at Brimstone Creek 
awarded in FY 1975. Miscellaneous items of work 
under various features were accomplished by 
hired labor. The land acquisition program for the 
Cordell Hull Project is complete except for one 
tract of land and payment of deficiency 
judgments. Costs for new work were $2,167,234. 
Operation and Maintenance: Barkley, 
Cheatham, Cordell Hull, and Old Hickory locks 
and dams were operated as required. Operation 
and Maintenance improvements at Barkley includes 
repairs to upper miter gates, dredging 
above and below lock, snagging, and installation 
of steel mooring cells. Contract for Dredging 
Cumberland City Canal completed in FY 1975. 
Contract awarded for Reservoir Manager's Office 
and scheduled for completion 76 T Qtr. Work 
at Cheatham includes making major repairs to 
upper and lower miter gates. Lock closed to 
navigation 16 July and reopened 8 August 1974. 
Contract for tow haulage unit completed. Reservoir 
Manager's Office completed in FY 1975. 
Contract for Cordell Hull lock equipment storage 
building completed in FY 1975. Work completed 
at Old Hickory includes painting generator room 
and resurfacing recreation sites. Contract awarded 
in FY 1975 for construction of warehouse and 
boathouse and scheduled for completion in FY 
1976. Installation of tow haulage unit underway 
at Old Hickory Lock. Total net energy generated 
at Barkley Dam (741,408,850 kw-hr) was made 
available through Department of the Interior to 
the Tennessee Valley Authority, Southern Illinois 
Power Cooperative, Big Rivers Rural Electric 
Cooperative Corporation, and Indiana Statewide 
Rural Electric Cooperative, Inc., Hoosier Energy 
Division. Total 'net energy generated at 
Cheatham Dam (171,362,900 kw-hr), Cordell 
Hull (477,368,000 kw-hr) and Old Hickory (572,- 
035,230 kw-hr) was made available for distribution. 
Power revenues were $1,448,000, $653,400, 
$2,274,979, and $1,230,900 respectively. Benefits 
attributable to Barkley effect in reduction of 
flood flows on Cumberland and lower Ohio and 
Mississippi River during year are estimated as 
$1,610,100.Activities under reservoir management 
program comprising malaria control, 
shoreline sanitation, land management and disposal, 
and maintenance of public-use facilities 
continued. Except for dredging contract noted 
above under Barkley project the channel snagging 
and dredging was done by hired labor. 
Condition at end of fiscal year. Below 
Nashville: Construction of Cheatham lock and 
dam was completed in November 1960. See page 
1078 of 1962 Annual Report for chronology of construction. 
Acquisition for Barkley project includes 
69,750.7 acres in fee, 24,277.6 acres in 
easements and 2,926 acres under use permit with 
exception of permanent transfer of about 5,946 
acres in fee (Land between the Lakes Project) and 
a use permit (flowage rights) over about 537 acres 
(Cumberland Steam Plant) from T.V.A., all land 
and land rights for the project have been 
procured. Project considered complete during 
FY 1974 and in full operation. Lock was opened to 
navigation on July 8, 1964. The four power units 
were placed in commercial operation January 21, 
February 4, March 7, and March 30, 1966. Total 
new work costs for this section to June 30, 1975 
were $179,472.066 including $685,000 public 
works funds. 
Above Nashville: Old Hickory project provides 
a through channel for 9-foot navigation on the 
Cumberland above Nashville to vicinity of 
Carthage, Tenn., at river mile 313.5. Lock and 
dam 8, placed in an inoperative status November 
30, 1951, was inundated with partial impoundment 
of Cordell Hull Reservoir. Full impoundment 
during FY 1973 extends the 9-foot 
waterway to Celina, river mile 380.8. Old Hickory 
project was completed for full beneficial use 
December 1957 with placement of last power unit 
in commercial operation. Further details are 
given on page 1080 of Annual Report for 1962. 
Construction of Cordell Hull project, started May 
1963, is 95 percent complete, see "New Work 
above Nashville", for detail of work currently underway. 
Total lands acquired 27,163 acres (26,- 
695 in fee and 468 acres in easements). Acquisition 
of one additional tract approximately 6.1 
acres will complete land requirements. Total new 
work costs for this section to June 30, 1975, were 
$129,849,657. Operation and maintenance of 
structures: Barkley, Cheatham, Cordell Hull, and 
Old Hickory locks were in operation at end of 
year; structures , channels, and appurtenances 
were maintained in serviceable condition. Total 
costs of existing project for entire stream were 
$367,794,869 of which $309,321,723 (including 
$685,000 from public works funds) were for new 
work and $58,473,146 for operation and 
maintenance. Surplus property valued at $79,313 
was transferred from project without reimbursement. 
Benefits attributable to reduction of flood 
flows by the Barkley project to date amount to 
$12,958,100. Power revenues received to date: 
Barkley, $18,633,000; Cheatham, $12,828,000; 
Cordell Hull, $3,296,000; and Old Hickory, $27,- 
843,000. 
3. TENNESSEE RIVER, TENN., ALA., 
AND KY. 
Location. Formed by junction of French Broad 
and Holston Rivers in eastern Tennessee, 4.4 
23-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
miles above Gay Street Bridge at Knoxville, flows 
southwest into northern Alabama, thence in a 
generally westerly course across north Alabama, 
to northeast boundary of Mississippi, thence 
nearly due north across Tennessee and Kentucky, 
entering Ohio River at Paducah, 652.1 miles from 
junction of French Broad and Holston Rivers. 
(See Geological survey base map of Tennessee 
River Basin.) 
Previous projects. For details see pages 1902- 
1906, Annual Report for 1915; pages 1190-1194, 
1196-1216, and 1220-1222, Annual Report for 
1929; and page 1216, Annual Report for 1938. 
Existing project. Originally provided for permanent 
improvement of river for a navigable 
depth of 9 feet at low water from mouth about 650 
miles to Knoxville, Tenn. Only work performed 
by the Corps was construction of lock at General 
Joe Wheeler Dam and miscellaneous appurtenant 
improvements at a new work cost of $2,244,- 
236. Tennessee Valley Authority program 
provided for obtaining authorized 9-foot project 
by construction of high dams and locks and 
utilization of certain locks and dams previously 
constructed under jurisdiction of the Corps. (See 
Table 23-B for Authorizing Legislation.) Subsequent 
construction by that agency of Melton Hill 
Dam extends navigable channel of Tennessee 
River system up the Clinch River about 38 miles 
above damsite (mile 23.1) to vicinity of Clinton, 
Tenn. (See table 23-D on Tennessee River.) 
In accordance with general navigation laws 
placing control and supervision over navigable 
waters under direction of Secretary of the Army, 
Corps of Engineers operates and maintains all 
locks, and maintains navigation channels and 
safety harbors by performing all necessary 
maintenance dredging and snagging operations. 
For information concerning other functions of the 
Corps under division of responsibilities for 
Tennessee River since adoption of Tennessee 
Valley Authority Act of 1933, see page 1084 of 
Annual Report for 1962. 
Local cooperation. Authorization requires no 
local cooperation in construction of alternate 
system of low dams. It does, however, provide that 
if high dams are built before the United States 
builds projected locks and low dams which are to 
be replaced, the United States shall contribute to 
cost of substituted structures an amount equal to 
estimated cost of works of navigation for which 
substituiton is made. 
Terminalfacilities. There are 144 terminals on 
the Tennessee River (9 municipally owned, 20 
government owned facilities and 115 privately 
owned facilities). A total of 69 terminals have 
railroad connections. Principal commodities 
handled are petroleum products, sand, gravel, 
coal, coke, grain, chemicals, iron and steel. 
Thirty-three, terminals handle various types of 
commodities. Facilities considered adequate for 
existing commerce. A list of terminals is revised 
annually and can be obtained from Division 
Engineer, Ohio River Division, Corps of 
Engineers, Cincinnati, Ohio. For further information 
see page 698 of Annual Report for 1969. 
Operations and results during fiscal year. 
Channel work by government plant and hired 
labor consisted of dredging and snagging at 
various locations, dredging safety harbors and 
access channels, and maintenance and replacement 
of pile dolphins in safety harbors. Fleet 
work also included dredging of forebays and 
cleaning powerhouse trashracks, and dredging 
lock chambers and lower approaches. Cost of 
channel maintenance was $87,667. Operation and 
maintenance of structures: All locks were 
operated and lock appurtenances and standby 
plant maintained as required. Major 
maintenance work includes major repairs to 
gates at main lock at Melton Hill, major overhaul 
to gate and valve operating machinery at Wilson 
Lock, storage building at Wilson Lock, and unwatering 
and repair of Fort Loudoun Lock. 
Condition at end offiscal year. Existing project 
is complete. Construction under the project was 
commenced January 1933 and completed 
September 1944. Additional work includes construction 
of Melton Hill project (mile 23.1 Clinch 
River) completed in FY 1963, added 61 miles of 9 
foot channel to the Tennessee River system for a 
total of about 711 miles of nine foot navigation 
channel. Construction of additional and modified 
navigation features by TVA, completion and 
operation dates, are shown on pages 698 and 699 
of Annual Report for FY 1969. See table 23-E for 
total cost of existing project to June 30, 1975. 
4. TENNESSEE-TOMBIGBEE 
WATERWAY, ALABAMA AND 
MISSISSIPPI 
Location. West Central Alabama and 
Northeastern Mississippi; in Marengo, Sumter, 
Greene and Pickens Counties, Alabama, and 
Noxubee, Lowndes, Clay, Monroe, Itawamba, 
Prentiss and Tishomingo Counties, Mississippi. 
Existing project. Provides for a waterway 232 
miles in length, connecting the Tombigbee and 
Tennessee Rivers by way of the East Fork of Tombigbee 
River, Mackeys and Yellow Creeks, affording 
a channel not less than 9 feet deep and 280 
feet in bottom width, with 10 locks each having 
clear chamber dimensions of 110x600 feet. Construction 
of the divide section, including Bay 
Springs lock and dam, is assigned to the 
Nashville District; whereas, the prosecution of 
work on the river and canal sections is under the 
23-4

NASHVILLE, TENN., DISTRICT 
jurisdiction of the Mobile District. Only activities 
of the Nashville District are reported hereon. Estimated 
Federal cost of new work under jurisdiction 
of the Nashville District is $582,848,000 (October 
1975). 
Local cooperation. Authorization requires local 
interests to construct, maintain and operate all 
highway bridges, construct and maintain all 
highway relocations or alterations, make and 
maintain alterations as required to sewer, water 
supply and drainage facilities, assume cost of 
operation and maintenance of utility crossings, 
provide and maintain as required suitable and 
adequate river and canal terminals in accordance 
with plans approved by the Secretary of the 
Army and the Chief of Engineers. 
Operations and results during fiscal year. 
Engineering and design continued. 
Condition at end of fiscal year. Contract for 
dredging Yellow Creek embayment was awarded 
in April 1974 and scheduled for completion during 
FY 1976. A/E contracts covering design and 
engineering in connection with relocation of 
Southern and ICG railroads were continued. Contract 
for real estate surveying and mapping was 
awarded in January 1974 and scheduled for completion 
during FY 1976. Progress on detailed 
design studies and feature design memoranda is 
progressing satisfactorily. Acquisition has been 
completed on 194 surface tracts, embracing 6,007 
acres which represents about 43 percent of tracts 
required for the project. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 23-F. 
Alteration of Bridges 
6. AUTHORIZED ALTERATION OF 
BRIDGES 
Work on Woodland Street bridge, under 
Truman-Hobbs Act, was initiated in 1965 and 
completed in 1966. Costs were$987,632. For 
details see page 922 of Annual Report for 1967. 
Flood Control 
7. MARTINS FORK LAKE, KY. 
Location. Dam planned at mile 15.6 on Martins 
Fork of Clover Fork, Cumberland River, about 10 
miles southeast of city of Harlan, with reservoir 
extending about 6 miles upstream within Harlan 
County, southeastern Kentucky. 
Existing project. Multiple-purpose improvement 
combining flood control with water quality 
control and recreation development adopted by 
1965 Flood Control Act (H. Doc. 244, 89th Cong.), 
in general accordance with recommendations. 
Dam will be concrete type, about 504 feet long 
and rising 97 feet above streambed. Outlet works 
provide for release of water from reservoir at 
varying levels. Drainage area above damsite is 
55.7 square miles. At full pool level, spillway 
crest at elevation 1341 above mean sea level, 
reservoir will cover 578 acres and contain 21,120 
acre-feet of storage capacity. Provision is made 
for 17,450 acre-feet of reservoir capacity between 
elevations 1341 and 1300 for control of floods in 
winter and spring season, and 14,360 acre-feet 
(El. 1341-1310) during summer and fall, in conjunction 
with which storage of 3,090 acre-feet 
would be available on a seasonal basis to meet 
streamflow requirements for water quality control 
and fish life below the dam. A minimum permanent 
pool of 3,670 acre-feet, 274 acres in extent, 
will thus be provided during potential flood 
seasons; and during late spring and summer 
when flood storage can be reduced, the lake is to 
be operated generally at a higher level (El. 1310) 
to maintain a larger surface area of 340 acres for 
recreation and to provide the required seasonal 
storage for releases of water during critical lowflow 
periods. Project will prevent major portion 
of average annual flood losses at Harlan and 
result in significant stage reductions with related 
benefits along rural reaches and at other urban 
areas downstream. Estimated cost of project, including 
planned initial recreation development, 
is $17,800,000 (October 1975). 
Local cooperation. Federal Water Project 
Recreation Act of 1965 applies in regard to non- 
Federal participation in recreation development, 
in addition to which local interests are to provide 
certain safeguards to ensure functioning of reservoir 
as intended. At this time, assurances have not 
been received for any non-Federal participation 
in the recreational development on this project as 
required under P.L. 89-72. Therefore, initially 
recreation will not be developed to the full potential 
and only minimum facilities will be provided. 
Operations and results during fiscal year. 
Engineering and design continued. 
Condition at end of fiscal year. Contract for 
phase I road relocations and contract for phase II 
portion of road relocations scheduled for completion 
in FY 1976. Work under contract for subsurface 
investigations was completed in FY 1975. 
Work on the master plan design memorandum is 
50 percent complete. Contract for construction of 
dam was awarded during latter part of FY 1975. 
Contract for relocation of Harlan County schools 
to be completed in FY 1976. Total acquisition to 
date involves 46 surface tracts embracing 1,675 
acres which represents 73 percent of tracts re- 
23-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
quired for the project. Acquisition of land is 
scheduled for completion in FY 1976. 
8. MIDDLESBORO, CUMBERLAND 
RIVER BASIN, KY. 
Location. At Middlesboro, Ky., on Yellow 
Creek, a tributary entering Cumberland River 
about 660 miles above its mouth. 
Existing project. A system of canals and levees 
around one side of town, arranged so as to divert 
most headwaters of Yellow Creek away from present 
channel through heart of city. Protection is 
thus afforded in large measure to life and property 
within business district and a large part of 
residential section. For project details, see page 
1088 of Annual Report for 1962. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Work on levees, canals, and appurtenances 
was accomplished by hired labor. No 
flooding was experienced. 
Condition at end of fiscal year. New work under 
existing project was completed in March 1945. 
Construction of canal and levee system, initiated 
in May 1938, was completed and improvement 
placed in operation in December 1939. Relocation 
work was completed in September 1940. Flood 
damages prevented to date amount to $13,674,- 
900. 
9. OHIO RIVER BASIN 
(NASHVILLE DISTRICT) 
Location. A series of levees, floodwalls, channel 
improvements, and reservoirs in Ohio River 
Basin within Nashville District. 
Existing project. The general comprehensive 
plans approved for flood control and other purposes 
in Ohio River Basin is set forth in legislation 
listed in Table 23-B. Individual projects, local 
protection projects and lakes, considered in comprehensive 
plan within Nashville District are 
listed in Table 23-G. 
10. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts, requires local interests furnish 
assurances they will maintain and operate certain 
local protection projects after completion in 
accordance with regulations prescribed by 
Secretary of the Army. District Engineers are 
responsible for administration of these 
regulations within their respective districts. 
Maintenance inspections were made during 
fiscal year of completed protective works in 
localities transferred to local interests for 
maintenance and operation. Local interests were 
advised, as necessary, of measures required to 
maintain projects in accordance with standards 
prescribed by regulations. Fiscal year cost was 
$12,865. Total cost to June 30, 1975 was $29,352. 
For project inspection data see table 23-H. 
11. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 23-I. 
12. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control and coastal emergencies (Public 
Law 99, 84th Cong., and antecedent legislation) 
Actual Federal costs for fiscal year were $24,- 
165 for advance preparation (flood emergency 
manual revision) and emergency operations. 
Total costs to June 30, 1975 were $323,413. 
Multiple-purpose Power Projects 
13. CENTER HILL LAKE, OHIO 
RIVER BASIN, TENN. 
Location. Dam is on Caney Fork River, 26.6 
miles above its confluence with Cumberland 
River (mile 309.2) at Carthage, Tenn. It is in 
DeKalb County, Tenn., about 55 miles east of 
Nashville, and 14 miles southeast of Carthage, 
Tenn. Reservoir extends about 64 miles up main 
stream and about 10 miles up Falling Water 
River and lies within DeKalb Putnam, White, 
and Warren Counties, Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric 
powerplant, and reservoir for primary purposes 
of flood control and power production, with a permanent 
pool for public use and conservation purposes. 
In addition to main dam structure, provision 
was made for a rolled-earth dike to close a 
saddle in reservoir rim near damsite. For further 
details, see page 1099 of 1962 Annual Report. Estimated 
cost of project including $7,520,000 code 
710 funds is $51,991,400 (October 1975). 
Local cooperation. None required on completed 
project; future recreation development subject to 
certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 
1965. 
Operations and results during fiscal year. New 
work: Contract for construction of visitors center, 
dock, and paving at Edgar Evins State Park 
awarded latter part of FY 1975 and scheduled for 
completion in FY 1976. Contract for boathouse at 
Rock Island State Park awarded latter part of FY 
1975 and scheduled for completion in FY 1976. 
23-6

NASHVILLE, TENN., DISTRICT 
Contract for recreation facilities at Rock Island 
State Park to be completed in FY 1976. 
Operation and Maintenance: Dam was 
operated and structure and its appurtenances 
maintained as required. Operation of powerplant 
was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy 
generated (491,474,200 kw-hr) was made 
available through Department of the Interior to 
Tennessee Valley Authority for distribution. 
Benefits attributable to reservoir effect in reduction 
of floodflows on Cumberland;lower Ohio and 
Mississippi Rivers estimated as $19,981,400. Activities 
under reservoir management program, 
comprising shoreline sanitation, malaria control, 
conservation, land management and disposal, 
and operation and maintenance of public-use 
facilities continued. Boundary line survey work 
completion scheduled in FY 1976. Contract 
awarded latter part of FY 1975 for study of area 
control center for Cumberland River 
powerplants. 
Condition at end offiscal year. Project was completed 
for full beneficial use April 1951. For 
chronology of construction and major items of 
work performed, see page 1101 of Annual Report 
for 1962. Flood damage reductions to date 
amount to $46,325,700. Power revenues total 
$27,610,829. 
14. DALE HOLLOW LAKE, OHIO 
RIVER BASIN, TENN. AND KY. 
Location. Dam is on Obey River, 7.3 miles above 
its confluence with Cumberland River (mile 
380.9) at Celina, Tenn. It is in Clay County, Tenn., 
and about 80 miles northeast of Nashville, Tenn., 
28 miles north of Cookeville, Tenn., and 3 miles 
east of Celina, Tenn. Reservoir extends about 51 
miles up main stream, 10 miles up East Fork, and 
6 miles up West Fork of Obey River, and lies 
within Cumberland and Clinton Counties, Ky., 
and Clay, Pickett, Overton, and Fentress Counties, 
Tenn. 
Existing project. A concrete gravity-type dam, 
hydroelectric powerplant, and reservoir for 
primary purposes of flood control and power 
production with a permanent pool for public use 
and conservation purposes. See page 1096 of 1962 
Annual Report for project details. Estimated cost 
of project including $2,880,000 code 710 funds is 
$28,852,200 (October 1975). 
Local cooperation. None required on completed 
project; future recreation development subject to 
certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 
1965. 
Operations and results during fiscal year. New 
work: Shower facilities were added at Willow 
Grove Dock, Lillydale and Obey River Park. Contract 
was awarded the latter part of FY 1975 for 
the Marina Complex at Dale Hollow State Park. 
This is a cost sharing contract between the Commonwealth 
of Kentucky and the Corps of 
Engineers. 
Operation and maintenance: Dam was 
operated and structure and its appurtenances 
maintained as required. Operation of powerplant 
was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy 
generated (180,049,715 kw-hr) was made 
"available through Department of the Interior to 
Tennessee Valley Authority for distribution. 
Benefits attributable to reservoir effect in reduction 
of flood flows on Cumberland, lower Ohio and 
Mississippi Rivers estimated as $9,643,300. Activities 
under reservoir management program involved 
shoreline sanitation, malaria control, conservation, 
land management, and maintenance of 
public-use facilities. Boundary line survey work 
was continued with completion scheduled during 
FY 1976. 
Condition at end of fiscal year. Project was commenced 
in March 1942 and completed for flood 
control operation in October 1943. Powerplant 
(initial 2-unit development) was completed April 
1949 and third unit installed and placed in operation 
December 1953. For further details and information 
on other major items of work, see page 
1098 of Annual Report for 1962. Flood damage 
reductions to date amount to $31,230,900. Power 
revenues total $20,203,309. 
15. J. PERCY PRIEST DAM AND 
RESERVOIR, OHIO RIVER 
BASIN, TENN. 
Location. Damsite is on Stones River, 6.8 miles 
above its confluence with Cumberland River 
(mile 205.9); in Davidson County, Tenn.; and 
about 7 miles east of Nashville, Tenn. Reservoir 
extends southeasterly from dam about 32 miles 
along main stream, 10 miles up East Fork, 6.5 
miles up West Fork, and for shorter distances up 
other tributaries of Stones River; and lies within 
Davidson, Rutherford, and Wilson Counties, 
Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric 
powerplant, and reservoir for primary purposes 
of flood control, power production and recreation. 
For further details see page 703 of 1969 Annual 
Report. Estimated cost of project including $3,- 
790,000 under code 710 funds is $57,251,300 (October 
1975). 
23-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Recreation development 
subject to certain conditions of non-Federal costsharing 
under Federal Water Project Recreation 
Act of 1965. 
Operations and results during fiscal year. New 
work: Connection of water and sewage lines at 
Anderson Road site was completed. Contract for 
development of recreation facilities at Poole 
Knobs essentially complete. Contract for comfort 
station at Hamilton Creek to be completed in FY 
1976. Public Use facilities at Seven Points essentially 
complete. The above work is being accomplished 
under the Code 710 program. 
Operation and maintenance: Dam was 
operated and structures and appurtenances 
maintained as required. Benefits attributable to 
reservoir effect in reduction of flood flows on 
Cumberland, lower Ohio and Mississippi Rivers 
estimated as $28,871,500. Total net energy 
generated (104,362,500 kw-hr) was made 
available through Department of the Interior to 
Tennessee Valley Authority for distribution. Activities 
under reservoir management program involved 
shoreline sanitation, malaria control, conservation, 
land management and maintenance of 
public-use facilities. Contract awarded in latter 
part of FY 1975 for Service Base Expansion and 
scheduled for completion in FY 1976. 
Condition at end of fiscal year. Substructure, 
initiated in 1963, was completed in 1968. Closure 
of dam was completed in December 1967, with 
project effective for flood control. Completion of 
the powerplant was accomplished in February 
1970, and recreation facility construction is 
scheduled for completion during FY 1976. Total 
reservoir lands acquired from private interests is 
33,351.00 acres in fee and 589.00 acres in easement 
including flowage rights reserved over 229 
acres in fee disposal of Sewart Air Force Base. 
With exception of recreation facilities under code 
710 noted above this project was considered complete 
June 30, 1975. Flood damage reductions to 
date amount to $35,268,000. Power revenues total 
$11,244,033. 
16. LAUREL RIVER LAKE, 
OHIO RIVER BASIN, KY. 
Location. Damsite is at mile 2.3 on Laurel 
River, a tributary of Cumberland River, in southcentral 
Kentucky. The two streams meet about 9 
miles below Cumberland Falls, a prominent 
physiographic feature at head of Lake 
Cumberland which is formed by Wolf Creek 
Dam. Reservoir will extend 19.2 miles upstream 
to site of Corbin, Ky., water-supply dam and lie 
within Laurel and Whitley Counties. 
Existing project. Project approved in general 
accordance with recommendations of House 
Document 413, 86th Congress, by 1960 Flood Control 
Act, as amended by Public Law 88-253, was 
designed for purposes of flood control, power, and 
recreation as an integral unit of a coordinated 
plan for development of water resources of 
Cumberland River Basin. With the view of a net 
gain in power potential on a system basis, the plan 
of improvement incorporated appropriate flood 
control storage in the proposed project and corresponding 
adjustment in operations of Wolf 
Creek Dam-Lake Cumberland for flood control 
and power, which in effect constituted a transfer 
of reservoir capacity without entailing a change 
in flood control benefits. Further detailed study 
giving full consideration to power capabilities 
and marketing arrangements indicated the advantage 
of maintaining present storage allocation 
at Wolf Creek and use of all available storage 
capacity of Laurel River Reservoir for power. As 
modified within discretionary authority of the 
Chief of Engineers, the project is under construction 
in primary interests of power production and 
recreation, at an estimated cost of $45,600,000 
(October 1975). 
Local cooperation. None required. 
Operations and results during fiscal year. Work 
completed includes relocation of Kentucky and 
Cumberland Valley RECC power lines, and Corbin 
City water lines. Fabrication of turbine and 
generators was continued. Placement of concrete 
for powerhouse was continued and first stage portion 
85 percent complete. Turbine manufactures 
erection subcontractor began on-site installation 
of spiral case in March. Carrier current equipment 
and powerline current transmitter receiver 
equipment contracts completed in FY 1975. Acquisition 
action was completed on 129 acres. 
Condition at end of fiscal year. Construction of 
right bank access road, initiated in December 
1964, completed in August 1965. Contract for construction 
of diversion and power tunnels, started 
in April 1966, was completed in December 1967. 
Stage 1 Dam construction was initiated in April 
1968 and completed in June 1969. Stage II Dam 
construction commenced in August 1969 and 
completed in September 1972. Lands acquired 
for project purposes total 8,501 acres. Project as a 
whole is about 71 percent complete. Powerhouse 
contract awarded in June 1973 and is approximately 
50 percent complete. 
17. WOLF CREEK DAM-LAKE 
CUMBERLAND, OHIO RIVER 
BASIN, KY. 
Location. Wolf Creek Dam is on Cumberland 
River at mile 460.9 (above mouth) in Russell 
County, Ky., about 10 miles southwest of 
Jamestown and 12 miles north of Albany, Ky. 
23-8

NASHVILLE, TENN., DISTRICT 
Lake Cumberland extends 101 miles up main 
stream, 48 miles up South Fork of Cumberland 
River, in Russell, Clinton, Wayne, Pulaski, Mc- 
Creary, Laurel, and Whitley Counties, Ky. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric 
powerplant, and reservoir for primary purposes 
of flood control and power production, with a permanent 
pool for public-use and conservation purposes. 
See page 1094 of 1962 Annual Report for 
project details. Estimated cost of project is $187,- 
357,200 (October 1975). This estimate includes 
$1,970,000 code 710 funds and $106,000,000 for 
major rehabilitation initiated during FY 1975. 
Local cooperation. None required on completed 
project; future recreation development subject to 
certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 
1965. 
Operations and results during fiscal year. New 
work: Activity involving the integrity of the 
structure began in 1968 when a leak or seepage 
developed in the embankment. Hired labor work 
and contractural exploratory drilling was continued 
through FY 1975. Work continued under 
the phase III subsurface investigation contract. 
Contract was awarded the latter part of FY 1975 
for the concrete diaphragm wall, increments 1 
and 3. Hired labor work completed on shower 
facilities at Cumberland Point recreation site. 
Operation and maintenance: Dam was 
operated and structures and appurtenances 
maintained as required. Operation of powerplant 
was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. The lake level was maintained 
below elevation 700.0 feet m.s.l. instead of 
the normal 723.0 feet m.s.l., whenever 
hydrologically possible in order to prevent excessive 
hydrostatic pressure on earthen embankment. 
During periods of severe flooding storage 
was utilized to elevation 730.0 feet m.s.l. with no 
known adverse effects. The maintenance of the 
lower generating level throughout the year, 
slightly reduced the hydropower generating 
potential by requiring above normal sluice 
releases and by reducing the available head. 
Total net energy generated (1,113,141,000 kw-hr) 
was made available through Department of the 
Interior to Tennessee Valley Authority for distribution. 
Benefits attributable to reservoir effect 
reduction of floodflows on Cumberland, lower 
Ohio and Mississippi Rivers estimated as $72,- 
858,400. Activities under reservoir management 
program involved shoreline sanitation, malaria 
control, land management, and maintenance of 
public-use facilities. Contract awarded latter 
part of FY 1975 for reservoir managers office. 
Condition at end of fiscal year. Project commenced 
August 1941 and was completed for full 
beneficial use August 1952. For chronology of 
construction and major items of work performed 
see page 1095 of 1962 Annual Report. Flood 
damage reductions to date amount to $129,923,- 
200. Power revenues total $50,200,065. 
18. OTHER AUTHORIZED MULTIPLEPURPOSE 
POWER PROJECTS 
(See table 23-J.) 
General Investigations 
19. SURVEYS 
Fiscal year costs were $4,578 for coordination 
with Soil Conservation Service on review of 
watershed studies. 
20. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $48,874 for flood plain 
information studies, $14,058 for technical services 
to others, and $34,780 for flood plain 
management services, totalling $77,712. Flood 
plain studies completed during fiscal year are in 
table 23-K. 
21. RESEARCH AND DEVELOPMENT 
Fiscal year costs were $870 for miscellaneous 
hydrologic studies involving collection and 
processing of streamflow and railfall data. 
23-9

TABLE 23-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
2. Cumberland River, 
Tenn. and Ky.' 
3. Tennessee River, 
Tenn., Ala. and Ky.6 
4. Tenn-Tombigbee 
Waterway, Alabama 
& Mississippi 
7. Martins Fork 
Lake, Ky. 
8. Middlesboro, 
Cumberland River 
Basin, Ky. 
9. Cumberland, Ky. 
13. Center Hill Lake, 
Ohio River Basin, 
Tenn. 
14. Dale Hollow Lake, 
Ohio River Basin, 
Tenn. & Ky. 
15. J. Percy Priest Dam 
and Reservoir, 
Ohio River Basin, 
Tenn. 
16. Laurel River Lake, 
Ohio River Basin, 
Ky. 
17. Wolf Creek Dam and 
Lake Cumberland, 
Ohio River Basin, Ky. 
Big South Fork 
National River 
and Rec. Area, 
Ky. and Tenn. 
1. Includes $9,707,354 for abandoned and/or replaced 
works under the old Cumberland River system. (Amount includes 
$826,253 for new work and $3,266,706 for maintenance 
on previous projects. 
2. Includes $61,733 public works acceleration funds. 
3. Includes $61,733 public works acceleration funds. In 
addition, surplus property valued at $84,354 transferred from 
project without reimbursement. 
23-10 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
8,153,467 
9,430,213 
4,113,900 
4,065,397 
2,229,900 
2,173,201 
655,400 
515,717 
397,200 
193,829 
29,400 
23,850 
-445,310 
73 
501,458 
863,599 
1,076,000 
1,375,702 
-23,215 
8,141 
910,200 
1,067,614 
804,625 
1,362,175 
750,800 
738,212 
6,108,674 
5,459,282 
4,100 
83,480 
1,964,186 
1,458,904 
7,371,922 
6,452,604 
4,524,239 
4,251,245 
2,547,300 
2,503,293 
1,000,000 
887,756 
815,000 
824,378 
50,000 
51,224 
920,961 
1,451,372 
1,241,200 
1,238,212 
55,039 
38,783 
1,118,900 
1,080,928 
859,000 
1,818,958 
919,000 
850,070 
4,575,000 
2,677,704 
101,665 
68,019 
2,391,661 
2,006,055 
3,605,395 
3,790,192 
5,400,100 
4,831,010 
2,716,100 
2,644,630 
4,198,000 
2,176,909 
2,267,600 
995,602 
116,000 
126,061 
1,206,500 
695,067 
1,127,500 
1,176,562 
42,000 
37,900 
1,160,000 
1,183,475 
532,005 
804,418 
931,000 
943,119 
3,100,000 
4,566,443 
10,500 
43,133 
2,980,000 
3,290,523 
500,000 
84,603 
50,000 
3,88$ 
1,121,745 
2,179,149 
6,270,600 
6,975,818 
2,720,300 
2,907,022 
9,600,000 
10,754,077 
773,000 
1,936,829 
36,000 
24,344 
2,005,000 
1,070,588 
1,083,600 
1,127,693 
745,500 
69,151 
1,312,700 
1,472,045 
982,255 
- 1,327,390 
1,031,700 
997,034 
4,650,000 
5,134,694 
1,500 
3,464 
1,485,800 
1,987,304 
4,500,000 
2,157,628 
310,000 
241,770 
310,980,6472 
310,147,9763 
62,097,8091 
61,739,853 
16,251,428 
16,251,428 
45,560,451 
45,471,496 
400,000 
400,000 
16,350,050 
15,231,1098 
4,846,800 
4,306,563 
817,830y 
817,830 
773,844 
760,4551' 
66,642 
66,642 
51,409,67311 
49,489,74512 
13,421,0871 
13,300,62214 
27,197,4271' 
26,489,97216 
13,251,727" 
13,130,7461' 
55,667,320 
55,579,2271's 
5,171,406 
5,047,3352" 
34,388,574 
33,784,76221 
79,841,12822 
79,840,067" 
22,143,36124 
21,915,77725 
5,000,000 
2,242,231 
360,000 
245,658

NASHVILLE, TENN., DISTRICT 
TABLE 23-A (Conti aued) COST AND FINANCIAL STATEMENT 
4. Includes $13,500 for special recreation use fees and 
$333,000 for maintenance and operation of dams and other 
improvements of navigable waters. 
5. Includes $13,500 for special recreation use fees and 
$333,000 for maintenance and operation of dams and other 
improvements of navigable waters. 
6. Includes $14,007,193 for new work and $4,005,175 for 
maintenance on previous projects. 
7. In addition, surplus property valued at $99,588 
transferred from project without reimbursement. 
8. Surplus property valued at $2,252 transferred to project 
without reimbursement. 
9. Includes $38,876 Emergency Relief Funds. 
10. In addition, surplus property valued at $4 
transferred to project without reimbursement. 
11. Includes $35,896 public works acceleration funds. 
12. Includes $35,896 public works acceleration funds. In 
addition surplus property valued at $55,528 transferred to 
project without reimbursement. 
13. Includes $20,400 funds for special recreation use. 
fees. 
14. Includes $20,400 funds for special recreation use 
fees. In addition, surplus property valued at $16,568 
transferred to project without reimbursement. 
15. Includes $51,789 public works acceleration funds. 
16. Includes $51,789 public works acceleration funds. In 
addition, surplus property valued at $28,223 transferred to 
project without reimbursement. 
17. Includes $25,400 funds for special recreation use 
fees.
18. Includes $25,400 funds for special recreation use 
fees. In addition, surplus property valued at $9,853 
transferred to project without reimbursement. 
19. In addition, surplus property valued at $384,000 
transferred to project without reimbursement. 
20. In addition, surplus property valued at $14,654 
transferred to project without reimbursement. 
21. In addition, surplus property valued at $5,801 
transferred to project without reimbursement. 
22. Includes $96,920 public works acceleration funds. 
23. Includes $96,920 public works acceleration funds. In 
addition, surplus property valued at $46,488 transferred to 
project without reimbursement. 
24. Includes $82,048 public works acceleration funds 
and $20,700 funds for special recreation use fees. 
25. Includes $82,048 public works acceleration funds 
and $20,700 funds for special recreation use fees. In addition, 
surplus property valued at $66,469 transferred from project 
without reimbursement. 
23-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 23-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 13, 1892 
June 25, 1910 
August 30, 1935 
July 24, 1946 
June 19, 1952 
September 3, 1954 
July 14, 1960 
August 5, 1886 
March 2, 1907 
March 2, 1919 
June 5, 1920 
July 3, 1930 
June 26, 19342 
July 24, 1946 
July 3, 1930 
May 18, 1933 
August 28, 1937 
June 28, 1938 
August 18, 1941 
December 22, 1944 
CUMBERLAND RIVER BELOW NASHVILLE 
Provision made for lock A 
Provision made for locks B to F, and for dredging below 
lock F. 
Repairing dams A to F, inclusive, and surmounting same 
with movable crests. 
Provision of 9-foot channel by the construction of 3 
moderate height dams below Nashville; via, Kuttawa 
(Eureka), Dover, and Cheatham. 
Provision for hydroelectric power production as a function 
of Cheatham Dam. 
Construction of Barkley (Lower Cumberland) dam and 
reservoir project for navigation, flood control, hydroelectric 
power, and related purposes in lieu of Kuttawa 
and Dover navigation-only structures. 
Authorized change in alignment of Illinois Central Railroad. 
CUMBERLAND RIVER ABOVE NASHVILLE 
Provision made for locks and dams; the Secretary of War 
to determine the final plan of improvement. 
Dimensions of the locks fixed in accordance with reports 
of Mar. 30, 1887, and Nov. 25, 1890. 
Adoption of the report of the Board of Engineers, dated 
Feb. 26, 1906, limiting the lock and dam construction to 
locks and dams 1 to 7, and 21. 
Provision made for locks and dams 8 to 17 
Authorizes work to proceed in Tennessee without waiting 
for action of local interests in Kentucky. 
Raising dam 1, 3 feet 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Construction of Old Hickory, Cordell Hull (Carthage), and 
Celina Dams above Nashville for navigation and the 
development of power resources. 
TENNESSEE RIVER 
Authorized navigable depth of 9 feet from mouth about 
650 miles to Knoxville, Tennessee to be obtained by 
construction of low dams. 
Authorized TVA to construct such dams in the Tennessee 
River as will provide a 9 foot channel. 
OHIO RIVER BASIN, NASHVILLE DISTRICT 
Construct levees, floodwalls, and drainage structures for 
protection of cities and towns in Ohio River Basin. 
Project to be selected by Chief of Engineers with 
approval of Secretary of War at a cost not to exceed 
$24,877,000 for construction. 
Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable 
at discretion of Secretary of War and Chief of Engineers, 
and for initiation and partial accomplishment of plan, 
authorized $75 million for reservoirs and $50,300, for 
local flood protection works. 
Additional $45 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $70 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Annual Report, 1890, P. 
2151 
H. Does, 758, 60th Cong., 
1st sess.; and 1481, 60th 
Cong., 2d sess.' 
H. Doc. 38, 73d Cong., 1st 
sess. 
H. Doc. 761, 79th Cong., 
2d sess. 
S. Doc. 81, 83d Cong., 2d 
sess. 
H. Doc. 56, 86th Cong., 2d 
sess. 
Annual Report 1884, p. 
1663. 
Annual Report 1888, p. 
1622, and Annual Report 
1892, p. 1933. 
H. Doc. 699, 59th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 10, 63d 
Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 26, 70th 
Cong., 2d sess. 
H. Doc. 761, 79th Cong., 
2d sess. 
H. Doc. 328, 71st Cong., 
2d sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
H. Doc. 762, 77th Cong., 
2d sess. 
23-12

NASHVILLE, TENN., DISTRICT 
TABLE 23-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Document 
July 24, 1946 Additional $125 million for further prosecution of H. Doc. 506, 78th Cong., 
comprehensive plan. 1st sess. 
May 17, 1950 Additional $100 million for prosecution of comprehensive 
plan for Ohio River Basin. 
December 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for flood control and other purposes 
in Ohio River Basin. 
June 18, 1965 Additional $89 million for further prosecution of H. Doc. 6755, 89th Cong., 
comprehensive plan for Ohio River Basin. 1st sess. 
August 13, 1968 Additional*$35 million for further prosecution of S. 3710, 90th Cong., 2d 
comprehensive plan for Ohio River Basin. sess. 
June 19, 1970 Additional $69 million for further prosecution of H. R. 15166 91st Cong., 
comprehensive plan for Ohio River Basin. 2d sess. 
March 7, 1974 Authorized establishing Big South Fork National River and H.R. 10203 93rd Cong. 
Recreation Area, Ky. and Tenn. Total area not to exceed Water Resources 
125,000 acres. Develop. Act 
of 1974 
March 7, 1974 Additional $120 million for further prosecution of H.R. 10203 93rd Cong. 
Comprehensive Plan for Ohio River Basin. River Basin Monetary 
Authorization Act 
of 1974 
TENNESSEE-TOMBIGBEE RIVERS 
July 24, 1946 Construction of waterway to connect above rivers and H. Doc. 486, 79th Cong., 
provide a 9 foot channel and minimum bottom width 2d sess. 
of 170 feet in river and canal sections and 150 feet in 
the divide cut, with locks 110 by 600 feet clear inside 
dimensions. 
Subsequent studies determined most practical plan consists Page 1343, Part I, FY 
of channel with bottom width of 300 feet (280 feet in 1968 House Hearings. 
divide cut), fewer locks with higher lifts resulted in 
reducing number of lifts from 18 to 10 and reduced 
length from 260 to 232 miles. 
1. Contains latest published maps. Included in Public 
Works Administration program Sept. 6, 1933. 
2. Permanent Appropriation Repeal Act. 
23-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 23-C CUMBERLAND RIVER, TENN. AND KY.: PRINCIPAL FEATURES 
(See Section 2 of Text) 
Dam and Reservoir Barkley Cheatham Old Hickory Cordell Hull Celina 
Nearest town 
Miles above mouth of river 
Lock dimensions (feet)1 
Lift at normal pool 
levels (feet) 
Depths on guardsills at 
minimum pool levels (feet) 
Character of foundation 
Dam: 
Type 
Height 
Length, exclusive of 
lock section (feet) 
Spillway: 
Gross length (feet) 
Net length 
opening (feet) 
Crest gates: 
Type 
Number 
Size (feet) 
Operating levels at dam 
(feet, mean sea level): 
Maximum regulated 
Normal operation: 
Full pool 
Minimum pool 
Minimum pool in advance 
of floods 
Reservoir area (acres) 
Reservoir capacity 
(acre-feet): 
Flood control 
Power drawdown 
Dead storage 
Total 
Canel: 
Length (miles) 
Bottom width (feet) 
Depth at minimum 
pool level (feet) 
Power development: 
Number of units 
Generator rating 
(kilowatts) 
Total installation 
(kilowatts) 
Percent of project 
completion 
Year opened to navigation 
Kuttawa, Ky., 
11 miles. 
30.6 
110 by 800 
57 
11, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
157 
9,959 
804 
660 
Tainter 
12 
55 by 50 
Ashland City, 
Tenn., 9 miles. 
148.7 
110 by 800 
26 
14, upper; 
17, lower 
Rock 
Concrete 
gravity 
75 
800 
480 
420 
Tainter 
7
60 by 27 
375 
359 
354 
346 
93,430 
1,213,0003 4 
259,000 
610,000 
2,082,000 
Old Hickory, 
Tenn., 3 miles. 
216.2 
84 by 400 
60 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
98 
3,6052 
325 
270 
Tainter 
6
45 by 41 
4503 
385 
382 
7,450 
19,8007 
84,200 
104,000 
442 
27,450 
125,0005 
63,000 
357,000 
545,000 
Carthage, Tenn., 
5 miles. 
313.5 
84 by 400 
59 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
93 
1,1382 
291 
225 
Tainter 
5
45 by 41 
5083 
508 
501 
499 
13,920 
85,6005 6 
20,500 
204,800 
310,900 
Celina, Tenn., 5 
miles. 
385.4 
Rock 
Concrete 
gravity and 
earthfill 
86 
2,298 
290 
250 
Tainter 
5
50 by 37 
5553 
550 
549 
13,150 
59,0005 
10,000 
179,000 
248,000 
1.75 
400 
11 
32,500 
130,000 
s
19649 
12,000 
36,000 
8
1952 
25,000 
100,000 
8
1954 
33,333 
100,000 
23,000 
69,000 
95 
1973 
23-14

NASHVILLE, TENN., DISTRICT 
TABLE 23-C 
(Continued) 
CUMBERLAND RIVER, TENN. AND KY.: PRINCIPAL FEATURES 
(See Section 2 of Text) 
Dam and Reservoir Barkley Cheatham Old Hickory Cordell Hull Celina 
Estimated cost 1 ' $145,698,200 $31,232,000 $54,501,700 $79,200,000 $39,100,000 
1. Clear width and length available for full width. 
2. Exclusive of lock section. 
3. Surcharge. 
4. Normal operation (elev. 375-359) during nonflood 
season; flood control allowance to be increased to 1,472,000 
acre-feet (elev. 375-354) during season of major floodflows. 
5. Surcharge storage. 
6. During flood season (elev. 508-501); minimum 51,800 
acre-feet (elev. 508-504) with normal operation during nonflood 
season. 
7. Daily pondage allowance; run-of-river project. 
8. Completed for full beneficial use. 
9. Temporary operation of lock only. 
10. Includes recreation facility costs. 
23-15

TABLE 23-D TENNESSEE RIVER 
(See Section 3 of Text) 
Lock Dimensions 
Length Minimum Depth 
Width Avail- List on Guard Sills 
of able for Year 
Miles Cham- Full Nor- Maxi- Opened Cost of 
Above Miles from her Width mal mum Lower Upper Character of Navi- Kind Type of Each Lock 
Project' Mouth Nearest Town (feet) (feet) (feet) (feet) (feet) (feet) Foundation gation of Dam Construction and Dam 
Kentucky 22.4 0.5 above Gilbertsville, 110 600 56 73.3 12.7 11.0 Limestone 1942 Fixed Concrete and 2 
Ky. earthfill 
Pickwick Landing 206.7 4.4 above Hamburg, 110 600 55 63.0 12.8 10.0 Limestone 1937 Fixed Concrete and 
Tenn. = earthfill 
Wilson: 
Auxiliary lock 259.4 2.9 above Florence, 60 292 94 100.0 11.04 11.2 Limestone 1927 Fixed Concrete and $46,973,5405 
Ala. 300 earthfill 
Main lock 259.4 2.9 above Florence, 110 600 94 100.0 13.0 13.0 Limestone 1959 - 
Ala. 
General Joe Wheeler: 
Auxiliary lock 274.9 18.4 above Florence, 60 400 48 51.5 13.2 14.7 Limestone 1934 Fixed Concrete and 1,796,2956 
Ala. earthfill 
Main lock 274.9 18.4 above Florence, 110 600 48 51.5 13.0 13.0 Limestone 1963 Fixed Concrete and 
Ala. earthfill 
Guntersville: 
Auxiliary lock 349.0 9.1 below Guntersville, 60 360 39 45.0 11.8 13.0 Limestone 1937 Fixed -7 
Ala. 
Main lock 349.0 9.1 below Guntersville, 110 600 39 45.0 12.7 13.0 Limestone 1965 Fixed Concrete and 
Ala. earthfill 
Nickajack: 
Auxiliary lock 424.7 39.4 below Chatta- 110 600 39 41.0 13.0 13.0 Limestone 1967 Fixed Concrete 
nooga, Tenn. 
Main lock 424.7 39.4 below Chatta- 110 800 39 41.0 13.0 13.0 Limestone Fixed Concrete 
nooga, Tenn. 
Chickamauga 471.0 6.9 above Chatta- 60 360 49 53.0 13.0 10.0 Limestone 1939 Fixed - 
nooga, Tenn. 
Watts Bar 529.9 6.8 above Breedenton, 60 360 58 70.0 11.8 12.0 Shale 1941 Fixed Concrete and 
Tenn. earthfill 
Fort Loudon 602.3 1.3 above Lenoir City, 60 360 72 80.0 11.8 12.0 Limestone 1943 Fixed Concrete and 
Tenn. earthfill 
Melton Hill 23.1 22.1 above Kingston, 75 400 54 60.0 13.0 13.0 Limestone 1963 Fixed Concrete 
(Clinch R.) Tenn. 
1. H. Doc. 328, 71st Cong., 2d sess., contains table, pp. 98 and 99, giving pertinent 
information concerning low dams contemplated under 1930 project. Annual 
Report for 1938, pp. 1218 and 1219, contains similar information pertaining to low 
dams in addition to existing locks and dams, including those constructed or under 
construction by Tennessee Valley Authority. 
2. Lock and dam constructed by Tennessee Valley Authority. 
3. Lock and dam constructed by Tennessee Valley Authority. Design for lock 
prepared with Corps forces and funds. 
4. Tailwater in canal; flight of 2 locks. 
5. Constructed by the Corps under authority of sec. 124, National Defense Act 
of June 3,:1916 (H. Doc. 1262, 64th Cong., 1st sess.). Actual costoflock and dam. 
6. Actual cost of lock only as constructed by the Corps; dains constructed by 
Tennessee Valley Authority. 
7. Constructed by Tennessee Valley Authority. 
O
y0
r
zn
x
O
z r 
t-a 
cII 
gtN

NASHVILLE, TENN., DISTRICT 
TABLE 23-E TENNESSEE RIVER, TENN., ALA., AND KY. 
TOTAL COST OF EXISTING PROJECTS TO JUNE 30, 1975 
(See Section 3 of Text) 
Channel Operation & 
Funds New Work Maintenance Maintenance Total 
Regular $2,244,236 $4,293,891 $37,172,428 $43,710,555 
Maintenance and operation - - 11,665 11,665 
Increase of compensation, - 5 - 5 
rivers and harbors, 1919 
(certified claims) 
Total $2,244,236 $4,293,896 $37,184,093 $43,722,225 
1. In addition, surplus property valued at $99,588 was on operation and care of works of improvement under 
transferred from the project without reimbursement. Ex- provisions of appropriation for such purposes. 
cludes $2,889,149 expended between 1890 and June 30, 1935, 
TABLE 23-F OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Caney Fork River, Tenn.' 1895 $ 27,828 $ - 
Clinch River, Tenn., and Va.2 3 1923 53,949 7,873 
Duck River, Tenn.1' 1887 13,000 
Elk River, Ala. and Tenn.' 4 1904 4,000 
French Broad and Little Pigeon Rivers, Tenn.2 5 1931 249,605 33,554 
Hiwassee River, Tenn.2 4 1923 113,311 9,754 
Holston River, Tenn.' ' 1911 5,714 
Little Tennessee River, Tenn.' 1888 5,510 
Obey River, Tenn.1 1887 11,500 
Red River, Tenn.' 1884 5,000 
South Fork of Cumberland River, Ky.1 1892 11,967 
1. Completed. 4. Recommended for abandonment in H. Doc. 467, 69th 
2. Inactive. Cong., 1st Sess. 
3. Recommended for abandonment in H. Doc. 532, 64th 5. Recommended for abandonment in H. Doc. 428 and 
Cong., 1st Sess. 489, 64th Cong., 1st Sess. 
TABLE 23-G OHIO RIVER BASIN (NASHVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS 
(See Section 9 of Text) 
Estimated Cost 
Type of 
Location Protection Federal Non-Federal Total 
Middlesboro Levees $1,080,000 $240,000 $1,320,000 
(Yellow Creek, Ky.)' 
Cumberland, Ky.2 Channel 
Improvement 511,800 240,000 751,800 
23-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
RESERVOIRS 
Total 
Estimated 
Tributary Basin and Reservoir Stream Cost 
Center Hill Lake, Tenn.2 Caney Fork River $51,991,400 
Dale Hollow Lake, Tenn. and Ky.3 Obey River 28,852,200 
J. Percy Priest Dam & Reservoir, Tenn.3 4 Stones River 57,251,300 
Wolf Creek Dam--Lake Cumberland, Ky.3 Cumberland River 81,357,200 
Rossview, Tenn. and Ky.' 2 Red River 12,590,0005 
Three Islands, Tenn.6 Harpeth River 19,900,0005 
Laurel River Lake, Ky.6 Laurel River 45,600,000 
Martins Fork Lake, Ky. Martins Fork 17,800,000 
1. See "Other authorized flood control projects." 
2. Inactive. 
3. Details of this project are in individual report. 
4. Formerly Stewarts Ferry Reservoir. 
5. Last revised in 1958. 
6. See "Other authorized multiple-purpose power projects." 
TABLE 23-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 10 of Text) 
Project Date of Inspection 
Barbourville, Ky. Nov 1974 and May 1975 
Corbin, Ky. Nov 1974 and May 1975 
Lake City, Tenn. Nov 1974 and May 1975 
Middlesboro, Ky. (Yellow Creek) Nov 1974 and May 1975 
Middlesboro, Ky. (Diversion Canal) Nov 1974 and May 1975 
Paint Rock River, Ala. Nov 1974 and May 1975 
Pineville, Ky. Nov 1974 and May 1975 
Spring City, Tenn. Nov 1974 and May 1975 
TABLE 23-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Barbourville, Ky.3 1963 $2,088,147 
Chattanooga, Tenn. and Rossville, Ga.' 1949 180,997 
Coal Creek and tributaries (Lake City), Tenn.3 1962 460,134 
Corbin (Lynn Camp Creek), Ky. 1969 567,703 
Middlesboro (Yellow Creek), Ky.,2 1949 26,309 
Paint Rock River, Ala.3 1967 544,173 
Pineville, Ky.3 1963 1,669,1764 
Rossview Reservoir, Ohio River Basin, Tenn. and Ky.2 - 6,779 
1. Authorization expired Dec. 31, 1953 (Public Law 314, 
82d Cong.) 
2. Inactive. 
3. Completed. 
4. Exclusion of $9,950 contributed funds. 
23-18

NASHVILLE, TENN., DISTRICT 
TABLE 23-J OTHER AUTHORIZED MULTIPLE-PURPOSE PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Barkley Dam and Lake Barkley, Ky. and Tenn.' 3 $143,758,004 $14,343,467 
Celina Dam, Ky.' 222,5762 
Cheatham lock and dam, Tenn.' 3 30,593,561 12,857,596 
Cordell Hull lock and dam, Tenn.' - 74,785,981 2,084,675 
Old Hickory lock and dam, Tenn.' 3 - 51,080,500 15,175,754 
Three Islands Reservoir, Ohio River Basin, Tenn.4 - 111,8552 
Laurel River Lake, Ky. - 33,784,763 
1. Details given under "Cumberland River, Tenn. and 
Ky."
2. Engineering and design. 
3. Completed for beneficial use. 
4. Inactive. 
TABLE 23-K FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 20 of Text) 
Location Requesting Agency Date Complete Federal Cost 
Bellevue-Kingston Cheatham County June 1975 $31,999 
Springs, Tenn. Dixon County 
Williamson County 
Hartsville, Tenn. City of Hartsville May 1975 $16,188 
23-19

LOUISVILLE, KY., DISTRICT* 
This district comprises a portion of southwestern 
Ohio, west central Kentucky, a small portion of 
north central Tennessee, Indiana except northern 
part, and southeastern Illinois except Cairo- 
Mounds-Mound City area, all included in 
drainage basin of Ohio River and its tributaries 
(exclusive of Tennessee and Cumberland Rivers) 
from mile 438 (below Pittsburgh) immediately 
upstream from Foster, Ky., to mouth. 
IMPROVEMENTS 
Navigation 
1. Construction of Locks and Dams, 
Ohio River..................................... 
2. Green and Barren Rivers, Ky...... 
3. Kentucky River, Ky.................... 
4. Ohio River, open-channel work 
5. Other authorized navigation 
Page 
24-2 
24-2 
24-2 
24-3 
projects ......................................... 24-3 
6. Navigation work under special 
authorization................................... 24-3 
Flood Control 
7. Barren River Lake, Ky................. 24-3 
8. Big Blue Lake, Ind ..................... 24-4 
9. Big Pine Lake, Ind ..................... 24-4 
10. Big Walnut Lake, Ind ................ 24-4 
11. Booneville Lake, Ky....................... 24-5 
12. Boone County, Ky. (Bank 
Protection & Repair Roads).......... 24-5 
13. Brookville Lake, Ind ...................... 24-5 
14. Buckhorn Lake, Ky........................ 24-6 
15. Caesar Creek Lake, Ohio.............. 24-6 
16. Cagles Mill Lake, Ind .................... 24-6 
17. Camp Ground Lake, Ky................ 24-7 
18. Carr Fork Lake, Ky....................... 24-7 
19. Cave Run Lake, Ky........................ 24-8 
20. Cecil M. Harden Lake, Ind........... 24-8 
21. Clarence J. Brown Dam & 
Reservoir, Ohio............................... 24-9 
22. Clifty Creek Lake, Ind ............... 24-9 
23. Dayton, Ky................................ 24-9 
24. Eagle Creek Lake, Ky................... 24-10 
25. East Fork Lake, Ohio.................... 24-10 
26. Evansville, Ind.......................... 24-10 
27. Falmouth Lake, Ky........................ 24-11 
28. Frankfort, Ky. 
(N. Frankfort Area)....................... 24-11 
Flood Control (Continued) Page 
29. Greenfield Bayou Levee, 
Ind .......... ... ........................ ......... 24-12 
30. Green River Lake, Ky ................... 24-12 
31. Helm Lake, Ill................................ 24-12 
32. Huntington Lake, Ind................. 24-13 
33. Indianapolis, Ind......................... 24-13 
34. Island Levee, Ind. ....................... 24-14 
35. Lafayette Lake, Ind .................... 24-14 
36. Levee Unit No. 5, Wabash River, 
Ind..................................... 24-14 
37. Lincoln Lake, Ill.......................... 24-15 
38. Louisville, Ky.................................. 24-15 
39. Louisville Lake, Ill......................... 24-15 
40. Marion, Ind .................................. 24-16 
41. Mason J. Niblack Levee, Wabash 
River, Ind........................................ 24-16 
42. Mill Creek, Ohio............................. 24-17 
43. Mississinewa Lake, Ind.............. 24-17 
44. Monroe Lake, Ind ..................... 24-17 
45. Newport-Wilders, Ky ................. 24-18 
46. Nolin Lake, Ky ............................ 24-18 
47. Ohio River Basin 
(Louisville District.)....................... 24-18 
48. Patoka Lake, Ind....................... 24-19 
49. Red River Lake, Ky....................... 24-19 
50. Rough River Lake and Channel 
Improvement, Ky........................... 24-20 
51. Salamonie Lake, Ind...................... 24-20 
52. Saline River and Tributaries, Ill. 24-20 
53. Southwestern Jefferson County, Ky. 24-21 
54. Taylorsville Lake, Ky.................... 24-21 
55. Wabash River Basin...................... 24-22 
56. West Fork of Mill Creek Lake, 
Ohio.................. ........................... 24-22 
57. West Terre Haute, Ind.................. 24-22 
58. Inspection of completed flood 
control projects ......................... 24-23 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
24-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
IMPROVEMENTS (continued) 
Flood Control (continued) Page 
59. Other authorized flood control 
projects............................................ 24-23 
60. Flood control work under special 
authorization................................ 24-23 
General Investigations Page 
61. Surveys............................... 24-23 
62. Collection and study of basic data 
63. Research and development .......... 24-23 
Navigation 
1. CONSTRUCTION OF LOCKS 
AND DAMS, OHIO RIVER 
For report on this improvement see this 
heading under Ohio River. 
2. GREEN AND BARREN RIVERS, 
KY. 
Location. Green River rises in Casey County, 
Ky., flows northwesterly 370 miles, and empties 
into Ohio River about 8 miles above Evansville, 
Ind. Barren River rises in Monroe County, Ky., 
flows northwesterly 130 miles, and empties into 
Green River one-half mile above lock 4 and 149.5 
miles above mouth of Green River. 
Existing project. Six locks and dams on Green 
River and one on Barren River to give, with 
channel work in pools of dams, a navigable depth 
of 9 feet and width of 200 feet from Ohio River to 
mile 103 Green River, 3.2 miles upstream from 
Paradise, Ky.; a navigable depth of 5.5 feet from 
mile 103 Green River to Mammoth Cave, Ky., 
mile 197.8 Green River, and from mouth of 
Barren River mile 149.5 Green River, to Bowling 
Green, Ky., mile 30.1 Barren River. (See table 24- 
C for principal data concerning locks and dams.) 
Fluctuations in stage vary considerably at 
different locks. At.lock 3, Green River, ordinary 
high stages are from 12 to 15 feet above pool level, 
and at lock 1, Barren River, from 7 to 10 feet 
above pool. Maximum stages of record are 34 feet 
above normal pool stage at lock 3, Green River, 
and 29 feet at lock 1, Barren River, obtained during 
floods of 1937 and 1913, respectively. (See 
table 24-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Considered adequate for 
existing commerce. (See table 24-D on terminal 
facilities.) 
Operations and results during fiscal year.Consisted 
of operation and maintenance of locks and 
dams, 1 to 3, Green River, and removal of shoals, 
snags, and slides as required to maintain adequate 
channel for existing traffic between mouth 
of Green River and dam 4 at mile 149 Green 
River. Operation activity was discontinued at 
lock 4 Green River and lock and dam 1 Barren 
River in January 1974. The residences and 
associated buildings and certain real estate at 
both locations were disposed of in January 1975. 
Routine maintenance was performed. 
Condition at end offiscal year. Locks and dams 
1 and 2, Green River, and lock and dam 1, Barren 
River, were in good condition. Lock and dam 3 
and lock 4, Green River were in poor condition. 
Dam 4, Green River, failed May 24, 1965, when 
120 feet washed out. Breach later widened, and 
repairs are deferred pending completion of survey 
report for navigation on Green River. Pool of 
dam 1, Barren River, is maintained for local 
small boat use, but navigation through lock is 
suspended because of loss of lower pool. Operation 
of locks 5 and 6, Green River, was discontinued 
August 1951, as they were no longer used by river 
traffic. Controlling project depth in lower 103 
miles of Green River is 9 feet; controlling depth 
from mile 103 to Bowling Green, Ky. is 5.5 feet. 
Under permit issued by District Engineer on 
August 20, 1963, private interests dredged 
channel of Green River to extend 9-foot depth to 
coal loading terminal at mile 105.7. Channel of 
Green River from mouth of Barren River at mile 
149.5 to Mammoth Cave, Ky., at mile 197.8, is no 
longer maintained and is blocked by deactivated 
locks and dams 5 and 6. 
3. KENTUCKY RIVER, KY. 
Location. Formed by confluence of its North 
and Middle Forks about 4 miles east of Beattyville 
in east central Kentucky, (South Fork joining 
the main stream at that place), flows 
northwesterly and empties into Ohio River at 
Carrollton, Ky., mile 545.8 below Pittsburgh, Pa. 
(See Geological Survey Chart for State of Kentucky; 
scale 1:500,000.) 
Existing project. Provides for 14 locks and fixed 
dams to give, in connection with improvement of 
Ohio River, slack water navigation of 6 feet 
minimum depth from Ohio River to points on the 
three forks a short distance above Beattyville, 
Ky. Length of 6-foot-depth project on main 
system of Kentucky River is 258.6 miles to confluence 
of Middle and North Forks. Cost of completed 
new work is $4,176,749. River frequently 
24-2 
__ __ __

LOUISVILLE, KY., DISTRICT 
rises to 35 feet high or more. Extreme height at 
lock 1 due to flood backwater from Ohio River is 
60.3 feet, while extreme floods reach height of 
47.6 feet at lock 4, and 35.5 feet at lock 14. At some 
intermediate locks extreme height of floods exceeds 
40 feet. All flood heights refer to upper pool 
gages. Existing project was adopted by 1879 
River and Harbor Act (H. Ex. Doc. 47, 45th 
Cong., 3d sess., and Annual Report, 1879, p. 1398). 
Operation and care of locks and dams were included 
in project July 1, 1935, under provisions of 
Permanent Appropriations Repeal Act of June 
26, 1934. 
Licenses. Federal Power Commission license 
No. 539, to Kentucky Utilities Co., at dam 7, Kentucky 
River, Annual charge, $4,708; total collections 
through fiscal year 1975, $215,941. 
Terminal facilities. Facilities for bulk commodities 
and gasoline are at various points and 
considered adequate for existing traffic. List 
appears on page 1110, Annual Report for 1962. 
(See table 24-E on locks and dams, Kentucky 
River, Ky.) 
Operations and results during fiscal year. 
Regular funds: Operation and maintenance of the 
14 locks and dams, and removal of shoals, snags, 
and slides as required to maintain an adequate 
channel for existing traffic between mouth of 
river and Beattyville, Ky. in pool of dam No. 14. 
Rehabilitation: Completed minor structural 
rehabilitation work, details in Annual Reports 
for 1963, 1964, and 1965. Maintenance items accomplished 
were repairs to lower gate valve rods 
at lock 13, replacement of miter timbers on the 
upper gates and repairs to the land wall filling 
valves and intake screens at lock 11, repairs to the 
floor of lock chamber and to the lower gate 
diagonals at lock 8, repairs to upper and lower 
gates, timbers, and valves at lock 3, and removal 
of tilted upper guard walls at locks 2 and 6. 
Condition at end of fiscal year. Existing project 
was completed in 1917. Work accomplished was 
rehabilitation of the five old State locks and dams 
and construction of new locks and dams 6 to 14 inclusive. 
Canalization system of Kentucky River is 
in poor condition. Repairs were made to 
deteriorated locks and dams as required to keep 
locks in operation and maintain pool levels above 
dams except in extreme dry weather, when some 
pools fall below normal levels. Channel work was 
performed as required to relieve critical 
hardship conditions for existing river traffic. 
Controlling navigable depth in section covered by 
existing project was 6 feet at end of fiscal year. 
4. OHIO RIVER, OPEN-CHANNEL 
WORK 
For report on this improvement see this 
heading under Ohio River. 
5. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See table 24-L at end of chapter. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to section 107, 
Public Law 86-645 (preauthorization). 
Fiscal year costs were $1,881. The detailed project 
report for navigation on Green and Barren 
Rivers was terminated in May 1975, due to failure 
to obtain assurance of local cooperation. 
Flood Control 
7. BARREN RIVER LAKE, KY. 
Location. Dam is on Barren River, 79.5 miles 
above its confluence with Green River and 10 
miles northeast of Scottsville, Ky. At flood control 
pool, reservoir extends upstream about 40 miles 
in Barren and Allen Counties, Ky. 
Existing project. A reservoir for flood control 
and allied purposes. Dam is rolled earth and rock 
fill, 146 feet high and 3,970 feet long, with gatecontrolled 
outlet works and uncontrolled opencut 
spillway. Total storage capacity is 815,200 
acre-feet (768,600 for flood control and 46,600 for 
water supply storage). For further details see 
page 1125 of Annual Report for 1962. Estimated 
cost of new work (1969) is $28,281,000 including 
$3,251,000 for construction of recreation facilities 
under the completed project program. Project 
was authorized by Flood Control Act of 1938. 
Local cooperation. None required by authorizing 
act. Under provision of Water Supply Act of 
1958, contract with city of Glasgow for water 
supply storage was approved by Secretary of 
Army on October 4, 1965. Terms require city to 
pay $23,433, which is project cost allocated to 
water storage plus capitalized prepayment of 
proportionate share of operation, maintenance, 
and major replacement costs. 
Operation and results during the fiscal year. 
New work: Contract for sanitation facilities, consisting 
of restrooms, washhouses, sewage treatment 
with necessary water and sewage lines at 
Site 11, Bailey's Point was awarded and advanced 
to about 18 percent complete, under recreation 
facilities at completed projects program. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 
1975 flood season prevented damages of $4,857,- 
000. 
Condition at end of fiscal year. Construction 
started in March 1960 and all major construction 
and relocation items were completed in October 
24-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
1964. Project was placed in operation in March 
1964. Land acquisition complete. 
8. BIG BLUE LAKE, IND. 
Location. The damsite is on the Big Blue River 
42.1 miles above the mouth, and about 7 miles 
downstream from Carthage, Indiana. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be concrete and 
earthfill 63 feet high and with 11,476 feet earth 
and 524 feet of concrete having 5 tainter gates and 
four gated sluices for water control. Total storage 
capacity will be 85,700 acre-feet of which 75,100 
feet will be for flood control. A levee of 10,670 feet 
and 'T' wall of 460 feet will provide protection for 
the town of Carthage, Indiana. Estimated cost of 
new work (1975) is $48,100,000 Federal and $10,- 
807,000 non-Federal. Project was authorized by 
1968 Flood Control Act. 
Local cooperation. Local interests must agree to 
administer project land and water areas for 
recreation and fish and wildlife enhancement: 
pay, contribute in kind, or repay with interest 
(which may be through user fees) one half of 
separable costs allocated to recreation and fish 
and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildlife lands and facilities. Local interests 
must agree to prevent encroachments on 
channel between dam and mouth of Big Blue 
River. 
Operations and results during fiscal year. 
General Design Memorandum Phase I was initiated 
and advanced to 20 percent completion. 
Condition at end of fiscal year. Construction has 
not started. 
9. BIG PINE LAKE, IND. 
Location. Damsite is in Warren County, Ind., 
2.5 miles above mouth of Big Pine Creek, a 
tributary of Wabash River, and is about 2 miles 
northwest of Attica and 21 miles southwesterly 
from Lafayette, Ind. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be concrete and 
earthfill, 132 feet high and 4,620 feet long, with 
gate-controlled concrete gravity spillway and 
gated sluices. Total storage capacity will be 210,- 
500 acre-feet of which 201,500 feet will be for 
flood control (winter months). Estimated cost of 
new work (1975) is $46,688,000 of which $42,091,- 
000 is Federal cost including $2,591,000 for 
recreation facilities under the completed projects 
program, and $4,597,000 is non-Federal contribution. 
Project was authorized by 1965 Flood 
Control Act. 
Local cooperation. Local interests must agree to 
administer project land and water areas for 
recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay with interest 
(which may be through user fees) one-half of 
separable costs allocated to recreation and fish 
and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildlife lands and facilities. Local interests 
must also agree to prevent encroachments 
on channel between dam and mouth of Big Pine 
Creek. State of Indiana has indicated intent to 
fulfill requirements but later suggested consideration 
of an alternate site for the dam. 
Operations and results during fiscal year. 
Preconstruction engineering and design studies 
continued. General Design Memorandum was advanced 
to 95 percent completion. 
Condition at end offiscal year. Preconstruction 
planning is 97 percent complete overall. Design 
Memoranda for Hydrology & Hydraulics and 
Site Selection, are approved. 
10. BIG WALNUT LAKE, IND. 
Location. Damsite is on Big Walnut Creek, a 
tributary of the Eel River 22.4 miles above the 
mouth of Big Walnut Creek and 1 mile north of 
Greencastle, Indiana. The lake will lie in Putnam 
County. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be a concrete gravity 
section with gated overflow spillway located at 
mid-channel flanked by rolled earth fill sections 
about 17,000 feet total length and 112 feet maximum 
height with two gate controlled sluices 
through the base of the concrete section. Total 
storage capacity will be 275,000 acre feet of which 
136,700 feet is allocated for flood control. Estimated 
cost of new work (1975) is $89,449,000, of 
which $53,791,000 is Federal including $8,691,- 
000 for recreation facilities under the completed 
projects program and $35,658,000 is non-Federal 
contribution. Project was authorized by 1963 
Flood Control Act. 
Local cooperation. Local interests must agree 
to administer project land and water areas for 
recreation and fish and wildlife enhancement: 
pay, contribute in kind, or repay with interest 
(which may be through user fees) one-half of 
separable costs allocated to recreation and fish 
and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildlife lands and facilities. Local 
interests must also agree to prevent encroachments 
on channel between dam and mouth 
of Big Walnut Creek and Eel Rivers. 
Operations and results during fiscal year. 
General Design Memorandum, Phase I was continued 
and advanced to 80 percent completion. 
24-4

LOUISVILLE, KY., DISTRICT 
Condition at end offiscal year. Special study is 
complete. 
11. BOONEVILLE LAKE, KY. 
Location. Damsite is on South Fork of Kentucky 
River, 16.9 miles above confluence with and 
271.6 miles above mouth of Kentucky River. 
Reservoir will be in Clay and Owsley Counties, 
Ky., about 130 air miles southeast of Louisville. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be earthfill, 160 
feet high and 1,200 feet long, with gate-controlled 
outlet works and gated open-cut spillway. Total 
storage capacity will be 318,000 acre-feet, of 
which 302,000 acre-feet will be for flood control. 
Estimated Federal cost of new work (1975) is 
$60,700,000. Project was authorized by Flood 
Control Acts of June 28, 1938, and December 22, 
1944. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Preconstruction engineering and design studies 
continued. Hydropower feasibility study was 
completed and Formulation Report on Power 
Feasibility was started. 
Condition at end of fiscal year. Final General 
Design Memorandum with appended Land Requirements 
Plan-Public Use is complete. General 
Design Memorandum revisions to comply with 
the Federal Water Pollution Control Act 
Amendments of 1972 deferred pending completion 
of report on power feasibility. 
12. BOONE COUNTY, KY. (Bank 
Protection & Repair Roads) 
Location. On the left bank of Ohio River about 
506.5 and 515.0 miles below Pittsburgh, Pennsylvania 
in Boone County, Ky. These locations are 
in northern Kentucky, about 30 miles southeast 
of Cincinnati, Ohio. 
Existing project. Provides bank protection for 
public and private facilities threatened by erosion 
and repairs damage to River Road and Huff 
Road in Boone County, Kentucky. Estimated 
Federal total cost of new work (1975) is $794,000. 
Project was authorized by Water Resources 
Development Act of 1974. 
Local cooperation. None required. 
Operation and results during fiscal year. None. 
Condition at end offiscal year. Construction has 
not started. 
13. BROOKVILLE LAKE, IND. 
Location. Damsite is on East Fork of 
Whitewater River, 2.4 miles above confluence 
with West Fork, and about one and one-half miles 
north of Brookville, Ind. The reservoir will be in 
Franklin and Union Counties, Indiana. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be earthfill, 182 
feet high and 3,004 feet long, with gate-controlled 
outlet works, and uncontrolled open spillway. 
Total storage capacity will be 359,600 acre-feet 
(214,700 for flood control, 89,300 for water supply 
and 35,500 for conservation). A minimum pool of 
20,100 acre-feet will be maintained. Estimated 
cost of new work (1975) is $62,044,000, of which 
$38,300,000 is Federal cost and $8,395,000 is non- 
Federal contribution for water supply storage 
and $15,349,000 for construction of recreation 
facilities under the completed projects program. 
Project was authorized by 1938 Flood Control 
Act. 
Local cooperation. None required by authorizing 
act. Contract with State of Indiana for water 
supply storage under provisions of Water Supply 
Act of 1958 was approved by Secretary of Army 
August 5, 1965. Under terms of contract, State 
will pay initial costs allocated to water supply 
feature of project plus capitalized prepayment of 
proportionate share of operation and 
maintenance costs. 
Operations and results during fiscal year. 
Engineering studies continued. Acquired 2 tracts 
of land. Utility relocations were continued for 
Indiana-Michigan Electric Co., Public Service 
Co., and Fayette-Union Co. REMC and advanced 
to 99 percent completion, 85 percent completion 
and 40 percent completion, respectively. Construction 
of the dam was advanced to 93 percent 
completion. Continued recreation development 
contracts for roads, ramps and parking areas, 
Ease Shore Scenic Drive, and public access 
buildings and facilities for Mounds Beach and 
Camp Area with progress advanced to 99 percent 
completion, 21 percent completion and 97 percent 
completion, respectively. Advanced construction 
of access buildings in the tailwater area and shop 
and overlook to 83 percent completion. Contract 
for relocation of Union County Roads, Sites U-1, - 
2 and -8 and for protection of Liberty Water 
Works was awarded and advanced to 12 percent 
completion. Maintenance: Routine maintenance 
was performed. Operation for flood control during 
the 1975 flood season prevented damages estimated 
at $528,000. 
Condition at end of fiscal year. Engineering 
studies are 93 percent complete. 472 tracts of land 
of estimated 474 required for project have been 
acquired. Relocation of Indiana Highway 101, 
Site S-1; relocation Franklin County Road, Site 
F-l; relocation of cemeteries; Gulf Refining Company 
pipeline, General Telephone Company, and 
Public Service Company facilities; pool clearing 
and construction of outlet works are complete. 
24-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Construction of dam is 93 percent complete. Project 
is about 84 percent complete overall and was 
placed in operation January 1974. 
14. BUCKHORN LAKE, KY. 
Location. Dam is on Middle Fork of Kentucky 
River, 43.4 miles above mouth, and 0.5 mile upstream 
from Buckhorn, Perry County, Ky. Reservoir 
extends upstream about 34 miles and lies in 
Leslie and Perry Counties, Ky. 
Existing project. A reservoir for flood control 
and recreation. Dam is earth and rockfill type, 
with gate controlled outlet work's. Total storage 
capacity is 168,000 acre-feet, of which 157,600 
acre-feet is for flood control. For further details, 
see page 1120 of Annual Report for 1962. Estimated 
cost of new work (1969) is $12,250,300 including 
$921,000 for construction of recreation 
facilities under the completed project program. 
Existing project was authorized by general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. 
Local cooperation. Department of Parks of 
Commonwealth of Kentucky has undertaken 
management of lands and recreational facilities 
in accordance with license granted by Secretary 
of the Army on June 29, 1962. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Contract for partial 
monumentation of project was advanced to about 
90 percent completion. Contract for resurfacing 
roads and parking lots was completed. Routine 
maintenance was performed. Operation for flood 
control during the 1975 flood season prevented 
damages estimated at $3,193,000. 
Condition at end of fiscal year. Construction 
started in September 1956 and reservoir was 
placed in operation in August 1960. All major 
construction and relocation items have been completed. 
Land acquisition is complete. 
15. CAESAR CREEK LAKE, OHIO 
Location. Damsite is on Caesar Creek, about 3.0 
miles above its confluence with Little Miami 
River, in Warren County, Ohio, about 3.5 miles 
southeast of Waynesville, Ohio, and 10.5 miles 
northeast of Lebanon, Ohio. Reservoir will be in 
Warren, Clinton, and Green Counties, Ohio. 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. It 
includes an earth and rockfill dam, four saddle 
dams, outlet works and an uncontrolled saddle 
spillway. Total storage capacity of reservoir will 
be 242,200 acre-feet, of which 148,500 acre-feet 
would be reserved for flood control storage. Estimated 
cost of new work (1975) is $64,206,000 including 
$9,806,000 for construction of recreation 
facilities under the completed project program. 
Existing project was authorized by general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. 
Local cooperation. None required. However, 
the State of Ohio requested inclusion in the project 
of storage for future municipal and industrial 
water supply uses. Contract with State of Ohio for 
water supply storage under provisions of Water 
Supply Act of 1958, as amended, was approved by 
Secretary of the Army May 20, 1970. Under 
terms of contract, State will reimburse the 
Federal Government for costs allocated to water 
supply storage over a period not to exceed 50 
years after use of this storage is initiated plus estimated 
annual amount for cost of operation, 
maintenance and major capital replacements required 
for the water supply facilities. 
Operation and results during fiscal year. 
Engineering and design studies continue. Acquired 
19 tracts of land. Construction of outlet 
works, dam, spillway, access roads and relocation 
Warren County Road, Site W-4 advanced to 71 
percent completion and contract for office, shop 
building and site development was advanced to 
99 percent completion. Awarded contracts for 
cemetery relocation and relocation of Texas 
Eastern Transmission Company and Consolidated 
Gas Supply Corporation facilities. 
Condition at end of fiscal year. Engineering 
studies are 81 percent complete. 391 tracts of land 
of estimated 451 required for project have been 
acquired. Construction of saddle dams and 
relocation Warren County Road, Site W-3 is complete. 
Project is about 42 percent complete 
overall. 
16. CAGLES MILL LAKE, IND. 
Location. Dam is on Mill Creek, 2.8 miles above 
its confluence with Eel River, in Putnam County, 
Ind., and about 25 miles east of Terre Haute, Ind. 
Reservoir extends upstream about 11 miles and is 
in Putnam and Owen Counties, Ind. 
Existing project. A reservoir for flood control 
and recreation. Dam is earth and rockfill embankment. 
Total storage capacity is 228,100 acrefeet, 
of which 201,000 acre-feet are for flood control. 
For details see Annual Report for 1962, page 
1136. Estimated cost of new work (1969) is $4,- 
255,800 including $148,000 for construction of 
recreation facilities under the completed project 
program. Existing project was selected for construction 
under general authorization for Ohio 
River Basin in 1938 Flood Control Act. 
Local cooperation. None required. State of Indiana 
has undertaken development and management 
of recreation facilities for use of the public 
in reservoir area in accordance with license 
24-6

LOUISVILLE, KY., DISTRICT 
granted by Secretary of the Army on January 17, 
1952. 
Operations and results during fiscal year. New 
work: None. Maintenance: Contract for partial 
monumentation of the project was advanced to 
about 99 percent completion; and routine 
maintenance was performed. Operation for flood 
control during the 1975 flood season prevented 
damages of $1,731,000. 
Condition at end of fiscal year. Construction 
started in July 1948 and completed in June 1953. 
17. CAMP GROUND LAKE, KY. 
Location. The damsite is in central Kentucky on 
Beech Fork, about 49.1 miles above its confluence 
with Rolling Fork, which stream is a tributary to 
Salt River, in Washington County about 11 miles 
northeast of Bardstown and about 34 miles 
southeast of Louisville, Ky. 
Existing project. A reservoir for flood control 
and allied purposes. The project consists of a 
rolled-earth dam with an uncontrolled open-cut 
spillway through the left abutment, and a gate 
controlled outlet conduit. A detached dam is required 
in a saddle between the main dam and the 
spillway. Total storage capacity will be 360,740 
acre-feet for flood control, water supply, water 
quality and recreation. Estimated cost of new 
work (1975) is $65,500,000 of which $10,658,400 
would be reimbursed by non-Federal interests. 
Project was authorized for phase I design 
memorandum stage of advanced engineering and 
design by the Water Resources Development Act 
of 1974 (Section 1). 
Local cooperation. Local interests must agree to 
administer project lands, facilities, and water 
areas for recreation, including fish and wildlife 
enhancement; pay, contribute in kind, or repay 
(which may be through user fees) with interest, no 
less than one-half of the separable first costs 
allocated to recreation; bear all costs of operation, 
maintenance and replacement of fish and wildlife 
and recreation use lands and facilities; repay all 
cost allocated to water supply; effect proper 
measures for control of pollution at the source to 
assure the effectiveness of the water quality 
storage provided; exercise, to the full extent of the 
water quality storage provided; exercise, to the 
full extent of their legal capability, control 
against removal of stream-flow resulting from 
the reservoir storage provided for water quality 
control; prevent encroachment of flow-carrying 
capacities of stream channels below the reservoir 
to the extent needed to provide reasonably effective 
reservoir operations; and periodically (at 
least annually) notify interests affected that the 
project will not provide complete flood protection 
and that backwater floods from the Ohio River 
will not be substantially reduced by the project. 
Operation and results during fiscal year. 
General Design Memorandum Phase I was initiated 
and advanced to 19 percent completion. 
Condition at end of fiscal year. Construction has 
not started. 
18. CARR FORK LAKE, KY. 
Location. Damsite is 8.8 miles above mouth of 
Carr Fork, a tributary of North Fork of Kentucky 
River, 16 miles upstream from Hazard, Ky. The 
reservoir lies entirely within Knott County. 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. 
Dam will be rock and earth fill with impervious 
core, 720 feet long and 130 feet high, with uncontrolled 
open cut spillway through left abutment. 
Outlet works has two control gates and 8-foot 
diameter conduit to stilling basin. Total storage 
capacity will be 47,700 acre-feet (31,600 for flood 
control and 4,300 for water quality control). A 
higher level seasonal pool for recreation will be 
provided. Estimated Federal cost of new work 
(1975) is $47,741,000 including $1,791,000 for 
recreation facilities under the completed projects 
program. Project was authorized by 1962 Flood 
Control Act. 
Local cooperation. None required for reservoir 
project. Division of Flood Control and Water 
Usage of Commonwealth of Kentucky gave 
assurance that encroachments on downstream 
channel capacity will be prevented. 
Operations and results during fiscal year. 
Engineering and design studies continued. Acquired 
12 tracts of land. Relocations, by contract, 
continued as follows: Kentucky Highways 160, 
Part 2 and 582 and Knott County Road 1410, Sites 
K-4A & B, completed; Knott County Roads, Site 
K-5, -6, -7, advanced to 97 percent completion; 
and Kentucky Highway 160, Site S-2, advanced to 
89 percent completion. Repairs to Smithboro 
Bridge on Kentucky Highway 15, Part II, have 
been extended due to continuous settlement of the 
left abutment and are 53 percent complete. Utility 
relocation contract with Thacker & Grigsby 
Telephone Company advanced to 20 percent completion. 
Construction of dam & spillway has advanced 
to 80 percent completion. Recreation contracts 
for ramps, roads, beach, buildings and 
utilities at Irishman Creek advanced to 60 percent 
completion. Contract for additional facilities 
at Irishman Creek, Littcarr, and Dam Site was 
awarded and advanced to 22 percent completion. 
Contracts for operators quarters and shop 
building were awarded and advanced to 97 percent 
and 20 percent completion respectively. 
Revised design report for the Defeated Creek 
Sediment Dam was completed. Maintenance: 
24-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Routine maintenance was performed. 
Condition at end of fiscal year. Relocations of 
State Highway 15, Site S-1, Parts 1 and 2; State 
Highway 1231, Knott County Roads Sites K-1, -2, 
-3A, -3B and 4, cemeteries and Inland Gas Company 
pipeline and construction of outlet works 
are complete. 712 tracts of land of estimated 723 
required for project have been acquired. Project 
is about 83 percent complete overall. 
19. CAVE RUN LAKE, KY. 
Location. Damsite is on Licking River, about 4 
miles upstream from U.S. Highway 60 near 
Farmers, Ky., and 7. miles upstream from U.S. 
Highway 60 near Farmers, Ky., and 7 miles 
southwest of Morehead, Ky. Reservoir will be in 
Rowan, Bath, Morgan, and Menifee Counties, Ky. 
Existing project. Plan provides for construction 
of a reservoir for flood control and allied purposes. 
Dam will be rolled earthfill, with gate controlled 
outlet works and uncontrolled open 
spillway. Total storage capacity will be 614,100 
acre-feet (438,500 for flood control and 28,300 for 
water quality control). Estimated Federal cost of 
new work (1975) is $67,163,000 of which $12,663,- 
000 is U.S. Forest Service cost. Project was 
authorized by Flood Control Acts of June 22, 
1936, and June 28, 1938. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Engineering and design studies continued. Acquired 
241 tracts of land. Completed relocation 
contracts for Kentucky State Highway 985, Site 
S-51, Morgan County Roads, Sites C-1, -3, -5, and 
Kentucky Highway 801, Site S-4; sedimentation 
survey contract and lake area clearing contract. 
Road relocations, by contract, advanced to partial 
completion as follows: Kentucky State Highway 
519, Site S-31 and Connecting Road, Site S-2A, 99 
percent complete; Kentucky Highways 1274, Site 
S-2, 2nd Section, 1240, Site S-8 and Morgan County 
Road 1009, Site C-4, 99 percent complete; 
repair State Highways 801 and 1274, 94 percent 
complete; Menifee County Road - Forest Service 
Road 129 - Phase I, 76 percent complete; and 
Morgan County Roads 1254, Site C-1; 56, Site C-3, 
Country Club Access Road and Hog Branch 
Road, 74 percent complete. Awarded and advanced 
to partial completion as follows: relocation 
of State Highway 7, Site S-6; 1161, Site S-7; 
191, Site C-2; and Morgan County Road, Sites C-7 
& -8, 28 percent complete; and Menifee County 
Road - Forest Service Road 129, Phase II, 12 percent 
complete. Contract for operators quarters 
and utilities was advanced to 94 percent completion. 
Advanced relocation of Mountain RTCC 
facilities to 91 percent completion and relocation 
of Licking Valley REC facilities to 58 percent 
completion. Boundary line marking continued to 
82 percent completion. 
Condition at end of fiscal year. 1,314 tracts of 
land of estimated 1,393 required have been acquired. 
Outlet works; dam; relocated State 
Highways 1274, Site S-2, 1st Section; State 
Highway 801, Site S-4D at Dam: State Highway 
985, Site S-51 and Morgan County Road; Site C-5; 
relocation of Bath, Menifee, Morgan and Rowan 
County cemeteries; relocation of Clark RECC, 
East Kentucky Power Coop, General Telephone 
Company, Grayson RECC, West Liberty Sewage 
Plant and Columbia Gas Transport facilities are 
completed. Project is about 85 percent complete 
overall. Maintenance: Routine maintenance was 
performed. Operation for flood control during the 
1975 flood season prevented damages of $3,833,- 
000. 
20. CECIL M. HARDEN LAKE, 
IND. 
Location. Dam is on Raccoon Creek, 32.4 miles 
above its confluence with Wabash River, and 25 
miles northeast of Terre Haute, Ind. At flood control 
pool, reservoir extends uupstream about 15 
miles in Parke and Putnam Counties, Ind. 
Existing project. A rolled earth dam and reservoir, 
for flood control and allied purposes. Total 
storage capacity is 132,800 acre-feet of which 
116,600 acre-feet are for flood control. For 
details, see Annual Report for 1962, page 1132. 
Estimated Federal cost of new work (1969) is $6,- 
279,800 including $19,700 for construction of 
recreation facilities under the completed projects 
program. Project was selected for construction 
under general authorization for Ohio River Basin 
in 1938 Flood Control Act. 
Local cooperation. Department of Conservation, 
State of Indiana, has undertaken management 
of lands and recreational facilities in accordance 
with license granted by Secretary of the 
Army on April 19, 1961. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Routine maintenance 
was performed. Planning for additional costshared 
recreation development under the completed 
projects program was continued. Flood 
damages of $235,000 were prevented during the 
1975 flood season. 
Condition at end of fiscal year. Construction of 
all major items of work completed December 
1961. Reservoir has been in operation since 
August 1960. Land acquisition is complete. Contract 
with the State of Indiana for additional costshared 
recreation development under the completed 
projects program was approved by the 
Secretary of the Army May 17, 1974. 
24-8

LOUISVILLE, KY., DISTRICT 
21. CLARENCE J. BROWN DAM 
& RESERVOIR, OHIO 
Location. Damsite is just east of Springfield, 
Clark County, Ohio, at mile 7.3 of Buck Creek, a 
tributary of Mad River. 
Existing project. Plan provides for construction 
of a reservoir for flood control and allied purposes. 
It includes an earthfill dam, 6,620 feet long 
and 72 feet high, with gated outlet works and 
open cut spillway through right abutment with 
concrete chute. Total storage capacity of reservoir 
will be 63,700 acre-feet (32,900 for flood control 
and 20,800 for water quality control). Estimated 
Federal cost of new work (1975) is $22,- 
095,000. Project was authorized by 1962 Flood 
Control Act. 
Local cooperation. Local interests must provide 
assurances against detrimental channel encroachment 
below dam to mouth of Buck Creek. 
Assurances from city of Springfield, Springfield 
Conservancy District, and Clark County, Ohio, 
were accepted March 5, 1964. 
Operations and results during fiscal year. 
Engineering and design studies continued. 
Relocation of Ohio Edison Co. facilities and Shell 
Oil Co. gas lines were advanced to 60 and 82 percent 
completion, respectively. Contract for 
recreation buildings advanced to 97 percent completion. 
Contract for landscaping at Croft Site 
and upper reaches of the lake was awarded and 
advanced to 85 percent completion. Project is 
about 97 percent complete overall. Maintenance: 
Routine maintenance was performed. Operation 
for flood control during the 1975 flood season 
prevented damages of $260,000. 
Condition at end offiscal year. Land acquisition 
and all major project features are complete. The 
project was placed in operation January 1974. 
22. CLIFTY CREEK LAKE, IND. 
Location. The dam site is 1.5 miles southwest of 
Hartsville, Ind., 18.4 miles above mouth of Clifty 
Creek, tributary of East Fork of White River, and 
is 12 miles northeast of Columbus, Ind. and 37 
miles southeast of Indianapolis, Ind. Lake area 
lies in Bartholomew and Decatur Counties. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be earth and rock 
fill 14,630 feet long with main dam section 102 
feet high and low section at left abutment 24 feet 
high with an open cut spillway having a concrete 
ogee crest weir with 440 feet base width through 
the left abutment and a gate controlled outlet conduit 
through the base of the dam. Total storage 
capacity will be 56,400 acre-feet, of which 44,100 
acre-feet will be for flood control (winter months). 
Estimated cost of new work (1975) is $35,946,000 
of which $32,124,000 is Federal cost including 
$1,424,000 for recreation facilities under the completed 
projects program, and $3,822,000 is non- 
Federal contribution. Project was authorized by 
1965 Flood Control Act. 
Local cooperation. Local interests must agree 
to administer project land and water areas for 
recreation and fish and wildlife enhancement: 
pay, contribute in kind, or repay (which may be 
through user fees) with interest one-half the 
separable costs allocated to recreation and fish 
and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildlife lands and facilities. Local interests 
must also agree to prevent encroachments 
on channel below dam on Clifty Creek and East 
Fork of White River to mouth of Muscatatuck 
River. State of Indiana has indicated intent to 
fulfill requirements. 
Operations and results during fiscal year. 
Preconstruction engineering and design studies 
continued. Supplement to General Design 
Memorandum covering preservation of the Fall 
Creek environmental area and deletion of water 
quality storage advanced to 80 percent completion. 
Condition at end of fiscal year. Aerial survey 
and mapping is complete. General Design 
Memorandum and Design Memoranda for 
Hydrology and Hydraulics, Site Selection and 
Land Requirements Plan, Public Use, are complete. 
Construction has not started. 
23. DAYTON, KY. 
Location. In Campbell County, Ky. on left bank 
of Ohio River from mile 467.0 to mile 469.2 and 
across the river from Cincinnati, Ohio. 
Existing project. Provides for construction of 
8,170 feet of levee, two pumping stations with 
gravity drainage structures and major 
relocations of storm and sanitary sewers serving 
the community. Estimated cost of new work 
(1975) is $6,730,000 Federal and $2,481,000 non- 
Federal. 
Local cooperation. Section 3 of the Flood Control 
Act of June 22, 1936 applies. Preliminary 
assurances of cooperation were received from 
City of Dayton, Kentucky on May 3, 1966. City is 
in process of acquiring rights-of-way for the project. 
Operations and results during fiscal year. 
Minimum planning continued as necessary for 
coordination with City Dayton's planning for 
right-of-way acquisition. 
Condition at end of fiscal year. General Design 
Memorandum is complete. Construction has not 
started. 
24-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
24. EAGLE CREEK LAKE, KY. 
Location. Damsite is 43.6 miles above mouth of 
Eagle Creek, tributary of Kentucky River, and 
about 37 miles north of Lexington, Ky. and about 
38 miles southeast of Cincinnati, Ohio. Lake will 
lie in Grant and Owen Counties. 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. 
Dam will be earth and rockfill, 130 feet high and 
1,210 feet long with a saddle dam 600 feet long 
and 10 feet high. Outlet works will be slide gate 
controlled, and spillway will be uncontrolled open 
cut. Storage capacity will be 172,600 acre-feet of 
which 119,600 acre-feet will be for flood control. 
Estimated cost of new work (1974) is $27,800,000. 
Project was authorized by Flood Control Act of 
1962. 
Local cooperation. None required for reservoir 
project. Kentucky Division of Flood Control and 
Water Usage has given assurance that 
downstream channel encroachments will be 
prevented. 
Operation and results during fiscal year. 
Preconstruction engineering and design studies 
continued. General Design Memorandum, Phase 
I, revised for project formulation in compliance 
with Water Resources Council, Principles and 
Standards for Planning Water and Related Land 
Resources, concluded that Eagle Creek Lake was 
not economically justified. Project was 
reclassified from the "active" to the "inactive" 
category April 23, 1975. 
Condition at end of fiscal year. Project 
reclassified to the "inactive" category. 
25. EAST FORK LAKE, OHIO 
Location. Damsite is on East Fork of Little 
Miami River between Batavia and 
Williamsburg, Ohio, about 6.0 miles above 
Batavia and 32.6 miles above mouth of the Little 
Miami River. Entire project lies in Clermont 
County, Ohio. 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. It 
includes an earthfill dam, outlet works, an uncontrolled 
saddle spillway and a dike to close a saddle 
north of spillway. Total storage capacity of reservoir 
will be 294,800 acre-feet, of which 210,600 
acre-feet will be reserved for flood control 
storage. Estimated cost of new work (1975) is 
$55,512,000 including $13,312,000 for construction 
of recreation facilities under the completed 
project program. Existing project was authorized 
by generl1 authorization for Ohio River Basin 
in 1938 Flood Control Act. 
Local cooperation. None required. However, 
the State of Ohio requested inclusion in the project 
of storage for future municipal and industrial 
water supply uses. Contract with State of Ohio for 
water supply storage under provisions of Water 
Supply Act of 1958, as amended, was approved by 
Secretary of the Army May 20, 1970. Under 
terms of contract, State will reimburse the 
Federal Government for costs allocated to water 
supply storage over a period not to exceed 50 
years after use of this storage is initiated plus estimated 
annual amount for cost of operation, 
maintenance and major capital replacements required 
for the water supply facilities. 
Operations and results during fiscal year. Acquired 
1 tract of land. Engineering and design 
studies continued. Boundary line marking advanced 
to 94 percent completion. Contract for 
dam, saddle dam, spillway and access road advanced 
to 65 percent completion. 
Condition at end of fiscal year. Engineering 
studies are 75 percent complete. 365 tracts of land 
of estimated 367 required for project have been 
acquired. Construction of outlet works and access 
road is complete. Status of contracts as noted in 
preceding paragraph. Project is about 59 percent 
overall. 
26. EVANSVILLE, IND. 
Location. In Vanderburgh County, Ind., on 
right bank of Ohio River, 792.2 miles below 
Pittsburgh, Pa. 
Existing project. Construction of a system of 
levees and concrete floodwalls, together with 
pumping plants for disposal of interior drainage, 
at Evansville. For further details, see Annual 
Report for 1962, page 1127. Project will provide 
protection for city of Evansville, Ind., against 
Ohio River floods equal to 1937 flood (maximum 
of record), with a 3-foot freeboard. Estimated 
total cost of new work (1975) is $42,918,000 including 
non-Federal cost of $6,218,000. Existing 
project selected for construction under general 
authorization for Ohio River Basin in 1937 Flood 
Control Act. 
Local cooperation. Section 3 of Flood Control 
Act of June 22, 1936, as amended applies. Fully 
complied with for Howell unit 1 and Knight 
Township sections. Assurances for Pigeon Creek 
section, unit 1, were executed February 11, 1963. 
Authorization-of-entry for Section 1 of Pigeon 
Creek Section Unit 2 has been furnished. 
Operations and results during fiscal year. 
Engineering and design studies continued and 
plans and specifications for levee and floodwall, 
Cedar Street to Stringtown Road was advanced to 
about 30 percent completion, and for pumping 
plants, Delaware, Dresden and North 6th Avenue 
to about 30 percent completion. Design 
Memorandum for North 1st Avenue and 
24-10

LOUISVILLE, KY., DISTRICT 
Stringtown Road pumping plants was advanced 
to about 90 percent completion. Construction contract 
for Sewers - Pennsylvania Avenue to Cedar 
Street was advanced to 75 percent completion. 
Construction contract for Levee and Floodwall 
was awarded and advanced to about 17 percent 
completion. Operation of the completed portions 
of the project for flood control prevented damages 
estimated at $558,000 during the 1975 flood 
season. 
Condition at end of fiscal year. Knight 
Township, Howell- Unit 1, and Pigeon Creek Unit 
1 are complete. Construction of Pigeon Creek 
Unit 2 was started in April 1974. Howell-Unit 2 
construction not started. General Design 
Memorandum and Supplement on Pigeon Creek 
Unit 2, and Design Memorandum for Delaware, 
Dresden and North 6th Avenue are approved. 
Project is about 24 percent complete overall. 
27. FALMOUTH LAKE, KY. 
Location. The dam site is on the Locking River, 
about 60.6 miles upstream from its confluence 
with the Ohio River. This site, in Pendleton County, 
is about 9 miles above Falmouth, Ky., about 35 
miles south of Cincinnati, Ohio, and about 50 
miles north of Lexington, Ky. The lake area lies in 
Pendleton, Bath, Bracken, Fleming, Harrison, 
Nicholas and Robertson Counties. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be earth and rockfill 
about 1,320 feet long and 147 feet maximum 
height with an uncontrolled open-cut spillway 
through the right abutment and a gate controlled 
outlet conduit through the base of the dam. Total 
storage capacity will be 898,300 acre-feet, of 
which 648,600 acre-feet will be for flood control. 
Estimated cost of new work (1975) is $104,380,- 
000, of which $94,794,000 is Federal cost including 
$2,690,000 for recreation facilities under 
the completed projects program and $9,586,000 is 
non-Federal reimbursement for recreation 
facilities. The project was authorized by the 
Flood Control Acts of 1936 and 1938. 
Local cooperation. Local interests must agree to 
administer project lands and water areas for 
recreation; pay, contribute in kind, or repay 
(which may be through user fees) with interest, 
one-half of the separable cost of the project 
allocated to recreation; bear all costs of operation, 
maintenance and replacement of recreation 
facilities provided the sizing and responsibility 
for development, operation, maintenance and 
replacement of recreation features of the reservoir 
may be modified in accordance with the 
alternatives cited in the Federal Water Project 
Recreation Act, dependent on the intentions of 
non-Federal interests regarding participation in 
costs of this feature at the time of construction 
and subsequent thereto. 
Operation and results during fiscal year. 
Preconstruction engineering and design studies 
were discontinued in August 1974 because the 
Fiscal Year 1975 Appropriation Act contained no 
funds for the Falmouth project. 
Condition at end of fiscal year. Special Report 
and Design Memorandum, Hydrology & 
Hydraulics are complete. Planning suspended 
and will be resumed if and/or when additional appropriations 
are made for the project. 
28. FRANKFORT, KY. (North 
Frankfort Area) 
Location. The authorized Frankfort project is 
located in Franklin County, north-central Kentucky, 
and lies on both banks of Kentucky River, 
66 miles above mouth. The North Frankfort Area 
is located on the right bank of the river and is 
comprised of the Thorn Hill, Old Capitol and Distillery 
Sections of Frankfort. 
Existing project. Plan is a portion of authorized 
project for Frankfort. It provides for 770 feet of 
concrete wall, 3,300 feet of earth levee, two pumping 
plants, and other necessary appurtenances 
to protect 430 acres of urban and suburban land 
in the North Frankfort section of city, against 
maximum flood of record (1937) with 3-foot 
freeboard. Project was authorized by general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. Estimated total cost of North 
Frankfort project (1975) is $3,252,100 of which 
$272,100 is non-Federal cost for lands and 
damages, and alterations to utilities. In addition, 
the Commonwealth of Kentucky contracted to 
relocate a road on the levee crown in the vicinity 
of the Jones Run Pumping Plant. The final cost to 
the State for the road was $55,980. Local interests 
operation of this portion of the project for flood 
control prevented damages of $342,000 during 
the 1975 flood season. Remainder of project for 
Frankfort is deferred. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. City has completed acquisition 
of rights-of-way and appropriate 
authorizations of entry have been furnished. Project 
was transferred to City for operation and 
maintenance on March 15, 1971. 
Operations and results during fiscal year. 
Engineering and design studies continued. 
Letter Report on and plans and specifications for 
Additional Capacity at Jones Run Pumping Plant 
were completed. Landscaping for the completed 
earth levee has been deleted due to the inability of 
the City of Frankfort to relocate an overhead 
power line in the area. 
24-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Condition at end offiscal year. Project is essentially 
complete. Remaining work consists of the 
replacement of two pumps at the Jones Run Pumping 
Plant for additional pumping capacity. 
29. GREENFIELD BAYOU LEVEE, 
IND. 
Location. In southern Vigo County, Ind., from 
mile 188.1 to 200.0 above mouth of Wabash River, 
on left bank below Terre Haute, Ind. 
Existing project. Provides for construction, 
reconstruction, enlargement or setback, of total 
13.7 miles of earth levee, three drainage structures, 
and necessary road ramps. Levee would 
protect 11,370 acres of land, including communities 
of Hutton and Vigo, from flood equal to 
that expected on an average of seven times per 
100-year period. Estimated total cost of new work 
(1975) is $4,457,000, of which $777,000 is non- 
Federal cost for lands and damages, and road and 
utility relocations. Project was authorized by 
1946 Flood Control Act. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Assurances of cooperation 
were accepted from the Greenfield Bayou 
Levee and Ditch Association on January 15, 1964. 
In connection with the Greenfield Bayou Levee 
project, the Secretary of the Army has determined 
that the Indiana Flood Control Act meets 
local cooperation requirements relative to the 
prevention of encroachments in the floodway. 
Operations and results during fiscal year. 
Minimum planning continued as required for 
coordination with Levee and Ditch Association. 
Condition at end of fiscal year. Design 
Memorandum Report on Economics and General 
Design Memorandum are complete. Construction 
has not started. 
30. GREEN RIVER LAKE, KY. 
Location. Damsite is 305.7 miles above mouth 
of Green River in Taylor County, Ky., about 8 
miles south of Campbellsville. Reservoir lies in 
Taylor and Adair Counties. 
Existing project. Provides for construction of 
reservoir for flood control and allied purposes. 
Dam is earth and rock fill, 141 feet high and 2,350 
feet long. Outlet works is slide gate-controlled 
and spillway open and uncontrolled. Total 
storage capacity is 723,200 acre-feet (560,600 for 
flood control and 64,500 for low-flow augmentation). 
Estimated cost of new work (1973) is $38,- 
170,200 including $5,065,000 for construction of 
recreation facilities under the completed project 
program. Existing project was authorized under 
general authorization for Ohio River Basin in 
1938 Flood Control Act. 
Local cooperation. None required by authorizing 
act. Taylor County, by lease approved by 
Secretary of Army February 15, 1968, has undertaken 
operation and maintenance of Smith Ridge 
public access area. Under provision of Water 
Supply Act of 1958, contract with City of 
Campbellsville for water supply storage was approved 
by Secretary of Army April 23, 1969. 
Terms require City to repay, with interest and annual 
charges for operation, maintenance and major 
replacement, the investment cost of $85,765 
allocated to its water supply storage space. Total 
payments received through fiscal year 1975, $3,- 
584,000. The Department of Parks of the Commonwealth 
of Kentucky, by lease approved by 
Secretary of Army, 4 October 1971, has undertaken 
the management of the Lone Valley public 
access area. 
Operations and results during fiscal year. New 
work: None. Maintenance: Contract for repairs to 
the retreat channel was advanced to about 91 percent 
completion, and routine maintenance was 
performed. Operation for flood control prevented 
damages estimated at $2,783,000 during the 1975 
flood season. 
Condition at end of fiscal year. Construction 
began in August 1965 and all major construction 
and relocation items were completed in 1972. Project 
was placed in operation February 17, 1969. 
Project including all land acquisition complete in 
1973. 
31. HELM LAKE, ILL. 
Location. Damsite is on Skillet Fork of the Little 
Wabash River 71.9 miles above the mouth of 
Skillet Fork, in Marion County, Indiana and is 
about 21 miles east of Centralia, Illinois. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be earthfill 77 feet 
high and 3,250 feet long with uncontrolled opencut 
spillway and gate-controlled outlet works. 
Total storage capacity will be 173,500 acre-feet of 
which 114,500 feet is allocated for flood control. 
Estimated cost of new work (1974) is $35,000,000 
of which $12,977,000 would be reimbursed by 
non-Federal interests. Project was authorized by 
1968 Flood Control Act. 
Local cooperation. Local interests must agree to 
administer project land and water areas for 
recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay with interest 
(which may be through user fees) one-half 
separable costs allocated to recreation and fish 
and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildlife lands and facilities. Local interests 
must agree to prevent encroachments on 
channel between dam and mouth of Skillet Fork 
24-12

LOUISVILLE, KY., DISTRICT 
and mouth of the Little Wabash River. Department 
of Business and Economic Development, 
State of Illinois, furnished preliminary 
assurances, in the form of a letter of intent, expressing 
the State's intention to assume the 
responsibilities for non-Federal costs for water 
supply and recreation at the proposed Helm 
Lake. Illinois Division of Waterways withdrew 
the State's support for the Helm Lake project in 
May 1974. 
Operations and results during fiscal year. 
Preconstruction planning was initiated and 
Draft General Design Memorandum, Phase I, 
was advanced to about 10 percent completion. 
Further preconstruction planning was suspended 
in June 1974, as the result of the statement 
presented by the State of Illinois to the 
House/Senate Appropriations Committees, May 
1, 1974 that the State cannot support the Helm 
project, as presently planned. 
Condition at end of fiscal year. Preconstruction 
planning has been suspended pending fulfillment 
of local cooperation requirements. 
32. HUNTINGTON LAKE, IND. 
Location. Damsite is on Wabash River, about 2 
miles from Huntington, Ind., and 411.4 miles 
above mouth. Reservoir will be in Huntington 
and Wells Counties, Ind. 
Existing project. Provides for construction of a 
reservoir for flood control and recreation. Dam 
consists of a rolled earth embankment 4,700 feet 
long and 89 feet high, a concrete spillway and outlet 
section 155 feet long, and a concrete gravity 
section 310 feet long. Spillway is controlled by 
three gates, and outlet works by six sluices. Plan 
also provides for local protection of Markle, Ind. 
Total storage capacity of reservoir is 153,100 
acre-feet, of which 149,000 acre-feet is reserved 
for flood control storage. Estimated project cost 
for new work (1975) is $19,393,000, of which $19,- 
200,000 is Federal cost and $193,000 non-Federal 
contribution. Project was authorized by Flood 
Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of 
project first cost. State of Indiana has met this 
obligation. 
Operations and results during fiscal year. New 
work: None. Maintenance: Contract for resurfacing 
roads and parking lots was completed. 
Routine maintenance performed. Planning for 
additional cost-shared recreation development 
under the completed projects program was continued. 
Operation for flood control prevented 
damages estimated at $674,000 during the 1975 
flood season. 
Condition at end of fiscal year. All major construction 
complete. Land acquisition complete 
except for remaining condemnation proceedings. 
Project was placed in operation January 9, 1969. 
Contract with the State of Indiana for additional 
cost-shared recreation development under the 
completed projects program was approved for 
the Secretary of the Army May 17, 1974. 
33. INDIANAPOLIS, IND. 
Location. In Marion County, Ind., on White 
River, 232 to 250 miles above the mouth. 
Existing project. Project is in two parts, 
Warfleigh and Fall Creek. Fall Creek Section I 
extends from Washington Street to 10th Street 
and includes 6,350 feet of channel improvement 
of White River, 1,180 feet of concrete wall, 2,050 
feet of earth levee, 1,530 feet of roadway levee, 
reconstruction of Michigan Street bridge, and extension 
of 10th Street bridge. Fall Creek Section 
includes 1,200 feet of channel improvement of 
White River above 10th Street, 6,400 feet of 
channel improvement of Fall Creek from mouth 
to 16th Street, 12,011 feet of new earth levee and 
levee enlargements along Fall Creek and White 
River, and reconstruction of Indiana Ave. bridge 
over Fall Creek. Warfleigh section comprises 
channel improvement of White River from 
Northwestern Boulevard to Broad Ripple Dam 
and levee along left bank of White River, 
reconstruction of Kessler Boulevard and Westfield 
Road bridges and raising of Monon Railroad 
bridge. Project also includes necessary sewer and 
drainage outlet changes. Project will protect urban 
areas in Indianapolis along Fall Creek and 
White River against a flood equal to that of 1913, 
the maximum on record. Estimated Federal cost 
of project (1970) is $11,600,000, estimated non- 
Federal cost is $2,030,000. Project was authorized 
by Flood Control Acts of June 22, 1936 and July 
24, 1946. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, as amended, applies and is fully 
complied with for Fall Creek Section I. Federal 
project for Indianapolis conforms to comprehensive 
flood control plan adopted by local interests 
after flood of 1913. Local interests accomplished 
portions of plan before authorization of Federal 
project and after Federal construction of Fall 
Creek Section I expressed desire to continue with 
construction of Fall Creek Section II, which they 
later built generally in accordance with the 
authorized Federal project. Local interests indicated 
intent to fulfill requirements for 
Warfleigh section. 
Operations and results duringfiscal year. Revision 
of the Report on Economics on Warfleigh 
Section continued. 
Condition at end of fiscal year. Fall Creek Section 
I is complete. Fall Creek Section II was con- 
24-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
structed by local interests generally in accordance 
with project plan. Economic study of 
Warfleigh Section is complete. 
34. ISLAND LEVEE, IND. 
Location. In Sullivan County, Ind., from 169.4 
to 179 miles above mouth of Wabash River, across 
river from Hutsonville and York, Ill. 
Existing project. Provides for construction 9.3 
miles of earth levee, four drainage structures, 
and related appurtenances. Levee will generally 
parallel left bank of Wabash River from miles 179 
to 170 and then extend along north bank of Turman 
Creek to tie in at high ground. Project will 
protect 5,010 acres of flood plain from floodflow 
having a frequency of 7 times per 100 years. Estimated 
total cost of new work (1975) is $3,505,- 
000, of which $345,000 is non-Federal cost for 
lands, damages, and bridge and utility 
alterations. Project was authorized by 1946 Flood 
Control Act. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936 as amended, applies. The Island 
Levee Association was reorganized to the Island 
Levee Conservancy District by court decree on 
October 19, 1971. In connection with another Indiana 
project, the Secretary of the Army has 
determined that the Indiana Flood Control Act 
meets local cooperation requirements relative to 
the prevention of encroachments in the floodway. 
Conservancy District is in process of acquiring 
authorization-of-entry. 
Operations and results during fiscal year. 
Minimum planning continued as required for 
coordination with Conservancy District. 
Conditions at end of fiscal year. Construction 
has not started. Project is about 6.3 percent complete 
overall. 
35. LAFAYETTE LAKE, IND. 
Location. Damsite is in Tippecanoe County, 
Ind., 4 miles east of Lafayette, and 7.2 miles above 
mouth of Wildcat Creek, tributary of Wabash 
River. Reservoir will also extend into Clinton, 
Tippecanoe, and Carroll Counties. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be earthfill, 3,700 
feet long and 120 feet high, with gate controlled 
outlet works and uncontrolled open-cut spillway. 
Storage capacity will be 331,880 acre-feet, of 
which 89,430 acre-feet will be for water quality 
pool and 242,450 acre-feet for flood control 
storage. Estimated cost of new work (1975) is 
$104,822,000, of which $88,900,000 is Federal 
first cost. $3,855,000 is Federal cost for construction 
of recreation facilities under completed project 
program, and $12,067,000 is non-Federal 
contribution for recreation facilities. Project was 
authorized by 1965 Flood Control Act. 
Local cooperation. Local interests must agree to 
administer project land and water areas for 
recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay (which may be 
through user fees) with interest one-half the 
separable costs allocated to recreation and fish 
and wildlife enhancement; and bear all costs of 
operation, maintenance, and replacement of 
recreation and fish and wildlife lands and 
facilities. Local interests must also agree to prevent 
encroachments on channel of Wildcat Creek 
from dam to mouth. State of Indiana indicated intent 
to fulfill requirements. 
Operations and results during fiscal year. 
Engineering and design studies are restricted 
pending release of funds from Budgetary 
Reserve. Design Memorandum, Real Estate, Initial 
Construction Area remained at 25 percent 
completion. All planning work on project 
suspended in Nov 72 as the result of exhaustion of 
funds. Environmental study initiated and advanced 
to 50 percent completion with partial 
release of Budgetary Reserve funds. 
Condition at end of fiscal year. General Design 
Memorandum and feature design memoranda 
for Outlet Works, Dam and Spillway, Concrete 
Aggregates and Stone Portection Sources and 
Land Requirement Plan-Public Use are complete. 
Land acquisition and construction cannot 
be started until appropriated funds are released 
from Budgetary Reserve. 
36. LEVEE UNIT NO. 5, WABASH 
RIVER, IND. 
Location. In Gibson and Posey Conties, Ind., on 
left bank of Wabash River, from 58 to 94.5 miles 
above mouth. 
Existing project. Provides for construction of 
41.9 miles of earth levee; drainage structures, 
pumping plants together with alterations to three 
railroad bridges crossing Wabash River. Project 
will provide protection for 44,000 acres of farm 
land and towns of Lyle, Skelton, and Griffin, Ind., 
against a flood equal to that expected on an 
average of seven times in each 100-year period. 
Estimated total cost of new work (1975) is $8,255,- 
500, of which $905,500 is non-Federal cost for 
lands and damages and road and utility 
relocations. Project was authorized by Flood Control 
Acts of 1936 and 1946. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Assurances were executed 
by Superintendent of Levee District on 
January 8, 1962. Completed portions of the project 
(Levees) were transferred to the Levee Dis- 
24-14

LOUISVILLE, KY., DISTRICT 
trict for operation and maintenance October 15, 
1969. 
Operations and results during fiscal year. Contract 
for Alterations of I. C. RR Bridge and Approaches 
is essentially complete. Engineering 
and design studies continued. Design Memorandum 
Pumping Plant, Coffee Bayou was advanced 
to 98 percent completion. Contract for Emerson 
Ditch pumping plant was advanced to about 99 
percent completion. Contract for drainage structures 
at Wabash River Section, Part 1 and Black 
River Section was awarded and completed. Flood 
damages estimated at $1,192,000 were prevented 
during the 1975 flood season. 
Conditions at end of fiscal year. All sections of 
levee and required alterations of the Penn Central 
Railroad and the Southern Railroad are complete. 
Alterations of the Illinois Central Railroad 
are essentially complete. 
37. LINCOLN LAKE, ILL. 
Location. Damsite is in Cumberland County, 
Ill., on Embarras River (tributary of Wabash 
River) 106.2 miles above its confluence with the 
Wabash River, 10 miles south of Charleston, Ill., 
and 53 miles southeast of Decatur, Ill. Lake area 
will extend into Coles and Douglas Counties. 
Existing project. Reservoir for flood control and 
allied purposes. Dam will be earthfill, 2,500 feet 
long and 112 feet high, with gate controlled outlet 
works and uncontrolled open cut spillway with 
concrete chute. Total storage capacity will be 
471,000 acre-feet of which 358,400 acre-feet will 
be for flood control and 49,600 acre-feet for water 
supply, water quality control and minimum 
release. Estimated cost of new work (1975) is 
$102,213,000, of which $86,846,000 is Federal 
cost including $2,883,000 for recreation facilities 
under the completed projects program and $15,- 
367,000 is non-Federal contribution and reimbursement 
for water supply and recreation 
facilities. Project was authorized by 1965 Flood 
Control Act. 
Local cooperation. Local interests must agree to 
administer project land and water areas for 
recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay (which may be 
through user fees) with interest one-half the 
separable costs allocated to recreation and fish 
and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildlife lands and facilities; reimburse 
the allocated construction and annual 
operation and maintenance costs allocated to 
water supply storage; prevent channel encroachments 
tending to reduce present channel 
capacities; hold and save the United States free 
from damages from water-rights claims 
resulting from construction and operation of the 
reservoir; exercise, to the full extent of their legal 
capability, control against removal from stream 
flow made available by reservoir storage for 
water quality control purposes; and contribute to 
the control of pollution of the stream subject to 
low-flow augmentation by adequate treatment or 
other methods of controlling wastes at their 
source. State of Illinois will be the responsible 
cooperating agency for all assurances. 
Operation and results during fiscal year. 
Engineering and design studies were suspended 
as the result of the statement presented by the 
State of Illinois to the House Appropriations 
Committee, May 15, 1973, that the State cannot 
support the Lincoln Lake project as presently 
planned. 
Condition at end offiscal year. Preconstruction 
planning is essentially complete. Land acquisition 
or construction has not started pending 
fulfillment of local cooperation requirements. 
38. LOUISVILLE, OHIO RIVER 
BASIN, KY. 
Location. Louisville is located in Jefferson 
County, Ky. on the left bank of the Ohio River, 607 
miles below Pittsburgh, Pa. 
Existing project. Local protection works consist 
of a system of levees, concrete walls, and pumping 
plants. For further information see 1962 Annual 
Report pages 1121 and 1122. Remedial construction 
consists of Improvements to Trash Raking 
Installation at Beargrass Creek Pumping Plant. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Local 
interests performed routine maintenance of the 
project. 
Condition at end of fiscal year. Construction of 
the project was started in March 1947 and completed 
in March 1956. Remedial construction at 
Beargrass Creek Pumping Plant is complete. 
39. LOUISVILLE LAKE, ILL. 
Location. Damsite is on the Little Wabash 
River 164.8 miles above the mouth and about 3.5 
miles northwest of Louisville, and 23 miles south 
of Effingham, Illinois. The lake area lies in Clay 
and Effingham Counties. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be a rolled earth 
and concrete gravity type about 10,000 feet long 
and 69 feet maximum height, with a gate controlled 
over-flow spillway in the concrete section 
of the dam and three gate controlled sluices in the 
base of the dam. Total storage capacity 230,800 
acre-feet of which 148,000 acre-feet will be for 
24-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
flood control. A low dike 4,400 feet long will be 
constructed parallel to a railroad on the right 
abutment. Estimated Federal cost of new work 
(1975) is $50,462,000, including $381,000 for 
recreation facilities under the completed projects 
program, and $10,860,000 reimbursable by non- 
Federal interests for water supply and recreation. 
Project was authorized by 1968 Flood Control 
Act. 
Local cooperation. Local interest must agree to 
administer project land and water areas for 
recreation and fish and wildlife enhancement: 
pay, contribute in kind, or repay with interest 
(which may be through user fees) one-half of 
separable costs allocated to recreation and fish 
and wildlife enhancement; bear all costs of operation, 
maintenance, and replacement of recreation 
and fish and wildlife lands and facilities; reimburse 
the allocated construction costs allocated to 
water supply storage; bear all costs of operation, 
maintenance and replacement of water supply 
storage facilities; prevent channel encroachments 
tending to reduce present channel 
capacities; hold and save the United States free 
from damages from water-rights claims 
resulting from construction and operation of the 
reservoir; exercise, to the full extent of their legal 
capability, control against removal from stream 
flow made available by reservoir storage for 
water quality control purposes; and contribute to 
the control of pollution of the stream subject to 
low-flow augmentation by adequate treatment or 
other methods of controlling wastes at their 
source. The State of Illinois will be the respopsible 
cooperating agency for all required 
assurances. 
Operations and results during fiscal year. 
Preconstruction planning was continued. Draft 
General Design Memorandum, Phase I, Plan 
Formulation was completed, submitted and 
returned for resubmission after resolution of 
comments. 
Condition at end of fiscal year. Design 
Memorandums, Hydrology and Hydraulics, 
Draft of Site Selection and Draft General Design 
Memorandum are complete. 
40. MARION, INDIANA 
Location. In Grant County, Indiana on left bank 
of Mississinewa River beginning at mile 36.7 and 
extending upstream to mile 38.0. 
Existing project. Provides for the construction 
of 5,600 feet of earth levee, 750 feet of concrete 
wall, one pumping plant and other necessary appurtenances. 
Project will protect an area of 107 
acres against a 1913 flood with three foot 
freeboard. Project was authorized by 1968 Flood 
Control Act. Estimated cost of new work (1975) is 
$2,930,000 and $880,000 non-Federal. 
Local cooperation. Section 3 Flood Control Act 
of 1936 as amended applies. City of Marion, Indiana, 
furnished preliminary assurances, in the 
form of a letter of intent expressing its intention 
to fulfill the requirements of local cooperation. In 
connection with another Indiana project, the 
Secretary of the Army has determined that the 
Indiana Flood Control Act meets local cooperation 
requirements relative to the prevention of encroachments 
in floodways. 
Operations and results during fiscal year. 
Preconstruction planning was continued and 
Draft General Design Memorandum, Phase I, 
was advanced to about 50 percent completion. 
Condition at end of fiscal year. Draft General 
Design Memorandum, Phase I, is about 50 percent 
complete. 
41. MASON J. NIBLACK LEVEE, 
WABASH RIVER, IND. 
Location. In Knox and Sullivan Counties, Ind. 
on left bank of Wabash River, between miles 
134.8 and 151.8 above mouth. 
Existing project. Construction of two sections of 
earth levee totaling 18 miles in length, three pumping 
plants for disposal of interior drainage, and 
other necessary appurtenances. Line of protection, 
including high ground between the two levee 
sections, is 18.9 miles long. Project protects 15,- 
900 acres of agricultural land against a flood 
equal to that expected to occur seven times in a 
100-year period. Estimated cost of new work 
(1975) is $4,503,200, of which $109,200 is non- 
Federal cost, and $1,554,000 is Federal cost of 
completed levee. The levee project was authorized 
by the 1946 Flood Control Act; pumping 
facilities were authorized by 1968 Flood Control 
Act. 
Local cooperation. Section 3 of Flood Control 
Act of June 22, 1936, as amended, applies. Fully 
complied with for levees and pumping plants. 
Operations and results during fiscal year. 
Construction contract for pumping facilities was 
awarded in December 1974 with work on the site 
to start after July 1, 1975. Operation by local interests 
for flood control prevented damages estimated 
at $550,000. 
Condition at end of fiscal year. Construction of 
levees is complete and this portion of project was 
transferred to Mason J. Niblack Levee District in 
January 1965 for operation and maintenance. 
Preconstruction planning for pumping facilities, 
consisting of Design Memorandum and plans and 
specifications is complete. 
24-16

LOUISVILLE, KY., DISTRICT 
42. MILL CREEK, OHIO 
Location. Proposed project is located along the 
18-mile length of Mill Creek and three-fourth 
mile length of East Fork in Hamilton County, 
Ohio. Lower Mill Creek is in the commercial and 
industrial heart of the Cincinnati metropolitan 
area in the southwestern portion of the State. 
Existing project. Nineteen miles of channel improvement, 
12 miles of levees, 9 pumping plants, 
modification of 38 bridges, and the addition of 3 
pumping units at the present Mill Creek Barrier 
Dam, located near the Ohio River, are included in 
the project. Acquisition and development with 
appropriate landscaping of 620 acres along the 
creek will be provided for high-density urban 
oriented recreational use. Estimated cost of new 
work (1975) is $113,882,000, of which $21,582,000 
is non-Federal. 
Local cooperation. Section 3, Flood Control Act 
of 1936 as amended applies. In addition, local interests 
must provide without cost to the United 
States all modifications and relocations of 
buildings, utilities, street and foot bridges, 
sewers, and related and special facilities as 
necessary for construction of project; prevent encroachment 
on improved channels and on ponding 
areas which would impair capacities; at 
least annually inform interests affected as to 
degree of protection afforded by project, and 
provide guidance and leadership in preventing 
unwise and uneconomical development of flood 
plain areas by encouraging prudent use of floodproofing, 
land regulation planning or other flood 
plain management techniques to reduce flood 
losses. Further, with respect to the recreational 
aspects of the project, local interests are required 
to furnish assurances that they will, if necessary, 
pay or contribute in kind, a portion of the cost of 
recreational facilities which, when added to the 
cost of recreation land, would amount to at least 
50 percent of the total first cost of the recreation 
land and recreational facilities, and assure access 
to the recreation facilities to all on equal terms. 
The Millcreek Valley Conservancy District furnished 
a Letter of Intent to discharge its responsibilities 
of local cooperation on July 17, 1969. 
Operations and results during fiscal year. Continued 
preconstruction planning and completed 
Draft General Design Memorandum, Phase II. 
Condition at end of fiscal year. Design 
Memorandum, Hydrology & Hydraulics and 
Draft General Design Memorandum, Phase I, are 
complete. 
43. MISSISSINEWA LAKE, IND. 
Location. Damsite is 7.1 miles above mouth of 
Mississinewa River, which flows into Wabash 
River about 2 miles upstream from Peru, Ind. At 
flood control pool level, reservoir extends upstream 
about 28 miles, in Wabash, Grant, and 
Miami Counties, Ind. 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. It 
includes an earthfill dam 137 feet high and 8,100 
feet long, gate controlled outlet works, and an uncontrolled 
open spillway through right abutment. 
Total storage capacity of reservoir is 368,400 
acre-feet, of which 345,100 acre-feet is reserved 
for flood control storage. Estimated project cost 
for new work (1975) is $24,343,000 of which $24,- 
100,000 is Federal cost and $243,000 non-Federal 
contribution. Project was authorized by Flood 
Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to 1 percent of 
project first cost. State of Indiana assumed this 
obligation. 
Operations and results during fiscal year. New 
work: Completed sedimentation survey. 
Maintenance: Routine maintenance was performed. 
Continued planning for additional costshared 
recreation development under the completed 
projects program. Operation for flood control 
prevented damages of $2,377,000 during 
1975 flood season. 
Condition at end of fiscal year. Construction is 
complete and land acquisition is complete except 
for outstanding condemnation proceedings. Project 
was placed in operation in May 1968. Contract 
with the State of Indiana for additional costshared 
recreation development under the completed 
projects program was approved for the 
Secretary of the Army May 17, 1974. 
44. MONROE LAKE, IND. 
Location. Dam is on Salt Creek, a tributary of 
White River, 25.9 miles above mouth, and 2 miles 
east of Harrodsburg, Monroe County, Ind. At 
flood control pool level, reservoir will extend upstream 
44 miles in Monroe, Brown, and Jackson 
Counties. 
bxisting project. A reservoir for flood control 
and allied purposes. Dam is earth core and rock 
shell, with gate-controlled outlet works and uncontrolled 
open spillway. Total storage capacity 
is 441,000 acre-feet (258,800 is for flood control 
and 159,900 for low flow augmentation). Estimated 
cost of new work (1972) is $14,815,754 of 
which $8,015,323 is non-Federal contribution. 
Project was authorized by 1958 Flood Control 
Act, modifying comprehensive plan for Ohio 
River Basin. 
Local cooperation. Section 3, 1944 Flood Control 
Act applies. Local interests must contribute 
54.1 percent of project cost, this being the proportion 
allocated to low-flow regulation feature, plus 
24-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
a capitalized amount representing that part of 
average annual maintenance and operation cost 
allocated to low-flow regulation. State of Indiana 
assumed this cost-sharing obligation. 
Operations and results during fiscal year. New 
work: None. Maintenance: Routine maintenance 
was performed. Planning for additional costshared 
recreation development under the completed 
projects was continued. Operation for flood 
control prevented damages of $919,000 during 
1975 flood season. 
Condition at end of fiscal year. Project is complete 
and was placed in operation in February 
1965. Contract with the State of Indiana for additional 
cost-shared recreation development under 
the completed projects program was approved 
for the Secretary of the Army May 17, 
1974. 
45. NEWPORT-WILDERS, KY. 
Location. City of Wilders, Ky. is located immediately 
upstream from Newport, Ky., on the 
right bank of the Licking River about 2.3 miles 
above its confluence with the Ohio River in 
Campbell County. Newport and Wilders are in 
the metropolitan area of Cincinnati, Ohio. 
Existing project. Construction of the Newport 
local protection project was completed and 
transferred to local interests for operation and 
maintenance in September 1951. The proposed 
project at Wilders consists of construction of 
earth levee and floodwall, five pumping plants, 
and other necessary appurtenances. Estimated 
cost of new construction (1975) is $9,290,000 
Federal and $761,000 non-Federal. Project 
selected for construction under general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. 
Local cooperation. Section 3, Flood Control Act 
of 1936, as amended applies. Fully complied with 
for the Newport local protection project. The City 
of Wilders, will be the responsible cooperating 
agency for the Wilders project. 
Operations and results during fiscal year. 
Preliminary planning and coordination with 
local interests continued. 
Condition at end of fiscal year. Local interests 
have expressed no contemporary desires for construction 
of the project. 
46. NOLIN LAKE, KY. 
Location. Dam is on Nolin River 7.8 miles above 
its confluence with Green River, about 70 air 
miles southwest of Louisville, Ky. Reservoir extends 
upstream about 57 miles and is in Edmonson, 
Grayson, Hart, and Hardin Counties, Ky. 
Existing project. A reservoir for flood control 
and allied purposes. Dam is rockfill-earth core 
type, with gate controlled outlet works, and uncontrolled 
open spillway. Total storage capacity 
is 609,400 acre-feet of which 545,600 acre-feet is 
for flood control. For further details of project, 
see Annual Report for 1962, page 1124. Estimated 
Federal cost of new work (1969) is $16,- 
080,200 including $1,500,000 for construction of 
recreation facilities under the completed projects 
program. Project selected for construction under 
general authorization for Ohio River Basin in 
1938 Flood Control Act. 
Local cooperation. None required for authorized 
project. State of Kentucky contributed $18,195 
for increased width of dam for public road. 
Operations and results during fiscal year. New 
work: Design of additional sanitation facilities at 
Wax and Moutardier sites was continued under 
the completed projects program. Maintenance: 
Contract for installation of sewage treatment 
facilities at Dam Site, Wax and Moutardier sites 
was essentially completed. Contract for relocation 
of water lines in the operations area was completed; 
contract for repairs to stilling basin was 
awarded and advanced to about 8 percent completion. 
Routine maintenance was performed. 
Operation for flood control during the 1975 flood 
season prevented damages estimated at $2,064,- 
000. 
Condition at end of fiscal year. All major construction 
items have been completed and the project 
was placed in operation in March 1963. Acquisition 
of mineral tracts complete. 
47. OHIO RIVER BASIN 
(LOUISVILLE DISTRICT) 
Location. Works covered by this project are a 
series of levees, floodwalls, channel improvements, 
and reservoirs in Ohio River Basin 
within Louisville District. 
Existing project. Individual projects considered 
in comprehensive plan within the 
Louisville District. (See Table 24-B on Authorizing 
Legislation at end of chapter). 
Operations and results during fiscal year. Only 
minor costs were incurred except for those projects 
for which individual reports are given. 
Economic studies of Russell and Allison Levee, 
Wabash River, Ill., and Shawneetown, Ill. were 
continued. 
Condition at end of fiscal year. Surveys, explorations, 
engineering studies, and preparation 
of detailed plans were well advanced for those units 
in general comprehensive plan for flood control 
in Ohio River Basin which are under con- 
24-18

LOUISVILLE, KY., DISTRICT 
sideration for construction in the near future. 
Status of projects selected for construction is 
given in individual reports. 
Economic reports on Russell and Allison Levee, 
Wabash River, Ill. and Shawneetown, Ill. are underway. 
48. PATOKA LAKE, IND. 
Location. Damsite is in Dubois County, Ind., 
118.3 miles above mouth of Patoka River, and 50 
miles west-northwest of New Albany, Ind. Reservoir 
will extend into Dubois, Orange and Crawford 
Counties. 
Existing project. Reservoir for flood control and 
allied purposes. Dam will be earth and rock fill, 
1,550 feet long and 85 feet high, with gatecontrolled 
outlet works and uncontrolled open 
spillway. Total storage capacity will be 301,600 
acre-feet (121,100 for flood control and 167,500 
for water supply and water quality control). Estimated 
cost of new work (1975) is $66,048,000 of 
which $42,700,000 is Federal cost, $749,000 is 
Federal cost for construction of recreation 
facilities under completed project program, and 
$22,559,000 is non-Federal contribution for 
water supply storage and recreation facilities. 
Project was authorized by 1965 Flood Control 
Act. 
Local cooperation. Local interests are required 
to reimburse the Federal Government for costs 
allocated to water supply storage over a period 
not to exceed 50 years after use of this storage is 
initiated, presently estimated at 29.31 percent of 
the joint-use facilities costs, exclusive of interests, 
plus $287,000 for the cost of operating and maintaining 
water supply storage for a period of 50 
years, plus $42,000 for the cost of major capital 
replacements required for water supply storage 
space for a period of 50 years. Local interests are 
also required to pay, contribute in kind, or repay 
(which may be through user fees) with interest, 
one-half of the separable first cost of the project 
allocated to recreation. Present laws of the State 
of Indiana require that agency to make cash contributions 
during construction of the project. 
Local interests must also agree to prevent encroachments 
on channel of Patoka River from 
dam to mouth, and to pay allocated initial and annual 
maintenance and operation costs for water 
supply storage. Formal assurances of local 
cooperation, executed by the Indiana Natural 
Resources Commission, were accepted August 
27, 1970. Contracts with State of Indiana for 
water supply and recreation were approved by' 
the Secretary of the Army November 2, 1970. 
Operations and results during fiscal year. 
Engineering studies continued. Acquired 80 
tracts of land. Construction contract for Outlet 
Works and Access Road was advanced to about 99 
percent completion. Construction contract for 
Shop and Office Buildings was essentially completed. 
Contract for dam, saddle dam and 
spillway and relocation Dubois County Road, Site 
D-1, Part 1 was awarded and advanced to about 
13 percent completion. 
Condition at end of fiscal year. Engineering 
studies continued. 381 tracts of land of estimated 
475 required for project have been acquired. Construction 
of shop and office buildings are complete. 
Project is about 26 percent complete 
overall. 
49. RED RIVER LAKE, KY. 
(DOWNSTREAM SITE). 
Location. Damsite is 42.3 miles above mouth of 
Red River, a tributary of Kentucky River, and 
about 4.3 miles northeast of Slade, Powell County, 
Ky. 
Existing project. Provides for construction of 
reservoir for flood control and allied purposes. 
Dam will be earth and rock, 141 feet high and 
1,800 feet long, with gate controlled outlet works 
and uncontrolled open spillway. Estimated cost of 
project (1975) is $40,346,000, including $5,146,- 
000 for recreation facilities under the completed 
projects program. Project was authorized by 
Flood Control Act of 1962. 
Local cooperation. None required for reservoir 
project. Kentucky Division of Flood Control and 
Water Usage gave assurances that downstream 
channel encroachments will be prevented. 
Provisions of Water Supply Act of 1958, as 
amended, applies to proposed allocation of water 
supply storage for future municipal and/or industrial 
use in Federal reservoirs. The Commonwealth 
of Kentucky will be the responsible 
cooperating agency. Draft water supply contract 
providing for an estimated storage of 24,770 
acre-feet, submitted to the Commonwealth in 
July 1972 has not been executed. The Commonwealth 
on 20 May 1974 indicated that the 
water supply storage was to be for future use. 
Operations and results during fiscal year. 
Engineering and design and real estate studies 
continued. General Design Memorandum and 
Land Requirements Plan, Public Use, are complete. 
Plans and specifications for access road 
remained at 40 percent completion. Design 
Memoranda for outlet works, and dam and 
spillway remained at 50 percent completion and 5 
percent completion, respectively. Coordination 
with Commonwealth of Kentucky and interested 
citizens' groups with respect to environmental 
aspects of the project continued. 
Condition at end of fiscal year. Design 
Memorandum, Hydrology and Hydraulics, 
24-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
General Design Memorandum and Land Requirements 
Plan, Public Use, are complete. Land 
acquisition and construction have not started. 
50. ROUGH RIVER LAKE AND 
CHANNEL IMPROVEMENT, KY. 
Location. Dam is on Rough River, 89.3 miles 
above its confluence with Green River at 160.3 
miles above Ohio River, and about 60 miles 
southwest of Louisville, Ky. Reservoir extends 
upstream about 30 miles and is in Breckinridge, 
Hardin, and Grayson Counties, Ky. Channel improvement 
work is on Rough River, Barnett 
Creek, and West Fork.of Barnett Creek. 
Existing project. Reservoir is for flood control 
and allied purposes. Dam is rolled earthfill type, 
with gate controlled outlet works. Storage capacity 
is 334,380 acre-feet, of which 314,210 acre-feet 
is for flood control. Project also includes channel 
clearing of lower Rough River, and channel improvement 
on Barnett Creek, a tributary of Rough 
River. For further details see page 1126 of Annual 
Report for 1962. Estimated cost of new work 
(1969) is $11,337,100 including $1,808,000 for 
construction of recreation facilities under the 
completed projects program. Existing project 
was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. Modification of previously approved 
plan to include channel improvement items was 
authorized by 1944 Flood Control Act. 
Local cooperation. None required for construction 
of reservoir unit. Provisions of section 3, 
Flood Control Act of 1936, are applicable to 
channel improvements. Assurances obtained 
from Ohio County for channel improvement. 
Department of Parks, Commonwealth of Kentucky, 
has undertaken management of certain 
lands and recreation facilities in accordance with 
license granted by Secretary of the Army on 
August 18, 1961. 
Operations and results during fiscal year. New 
work: Contract for additional sanitation facilities 
at Axtel and North Fork was advanced to about 
72 percent completion under completed projects 
program. Maintenance: Contract for installation 
of sewage treatment facilities at Axtel and North 
Fork sites was essentially completed. Routine 
maintenance was performed. Operation for flood 
control during the 1975 flood season prevented 
damages estimated at $1,758,000. 
Condition at end of fiscal year. Construction 
started in November 1955 and reservoir was placed 
in operation in June 1959. Land acquisition 
and all major items of construction and relocation 
are complete. 
51. SALAMONIE LAKE, IND. 
Location. Damsite is 3.1 miles above mouth of 
Salamonie River which enters Wabash River 
about 6 miles upstream from Wabash, Ind. Reservoir 
extends upstream about 27 miles at flood control 
pool and lies in Wabash and Huntington 
Counties, Ind. 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. It 
includes an earthfill dam with a maximum 
height of 133 feet and a length of 6,100 feet, gate 
controlled outlet works with a 16-foot diameter 
conduit and an uncontrolled open spillway 
through right abutment. Total storage capacity 
of reservoir is 263,600 acre-feet, of which 250,500 
acre-feet is for flood control storage. Estimated 
project cost for new work (1975) is $16,406,500, of 
which $163,900 is non-Federal contribution and 
$16,242,600 Federal cost. Project was authorized 
by Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of 
project first cost. State of Indiana assumed this 
obligation. 
Operations and results during fiscal year. New 
work: None. Maintenance: Performed routine 
maintenance. Continued planning for additional 
cost-shared recreation development under the 
completed projects program. During 1975 flood 
season, operation for flood control prevented 
damages of $1,549,000. 
Condition at end of fiscal year. Land acquisition 
and all major construction and relocation contracts 
are complete. Reservoir was placed in 
operation in spring 1967. Contract with the State 
of Indiana for additional cost-shared recreation 
development under the completed projects 
program was approved for the Secretary of the 
Army May 17, 1974. 
52. SALINE RIVER AND 
TRIBUTARIES, ILL. 
Location. Saline River, which flows into Ohio 
River at mile 867.4 below Pittsburgh, Pa., and 10 
miles below Shawneetown, Ill., is formed by confluence 
of its South and Middle Forks 27 miles 
above its mouth. North Fork joins main stream at 
stream mile 17.2. Project area is in Gallatin, 
Hamilton, and Saline Counties in southeastern Illinois. 
Existing project. Provides for 9.9 miles of 
channel enlargement on Saline River, 1.2 miles of 
clearing and cleaning and 29.8 miles of channel 
enlargement on North Fork, 12.2 miles of channel 
enlargement on Middle Fork, and 14.2 miles of 
24-20

LOUISVILLE, KY., DISTRICT 
clearing and cleaning on South Fork. Project will 
protect agricultural areas along 67.3 miles of improved 
channel from headwater floods with an 
expected frequency of once in 2 years, and lesser 
floods occurring more frequently. Project was 
authorized by 1958 Flood Control Act, and deletion 
of cash contributions by local interests was 
authorized by 1962 Flood Control Act. Estimated 
total cost of new work (1975) is $8,651,000, of 
which $991,000 is non-Federal cost for lands and 
damages, and bridge and utility relocations. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, as amended applies. Saline 
Valley Conservancy District furnished 
assurances of cooperation on March 2, 1966. 
Authorizations-of-entry for five sections of project 
have been furnished. Conservancy District is 
acquiring rights-of-way for the remaining section. 
Operations and results during fiscal year. 
Preparation of plans and specifications for South 
Fork Clearing continued. Construction contracts 
for lower and middle section of North Fork 
Channel remedial work, and upper section North 
Fork, Channel were completed. Construction contract 
for Middle Fork Channel was advanced to 
94 percent completion. 
Condition at end of fiscal year. Contracts for 
enlargement of Saline River Channel; North 
Fork Channel-lower, middle and upper sections 
and remedial work are complete. Project is about 
92 percent complete overall. 
53. SOUTHWESTERN JEFFERSON 
COUNTY, KY. 
Location. In Jefferson County, Kentucky on left 
bank of Ohio River from mile 616 to 628.6. 
Existing project. Provides for the construction 
of 68,500 feet of levee, 1,550 feet of concrete wall, 
five pumping plants, and other necessary appurtenances. 
Project will provide protection to 
24,100 acres against 1937 flood of record with 
three foot freeboard. Estimated cost of new work 
(1975) is $48,122,000, of which $37,100,000 is 
Federal, $11,022,000 is non-Federal. Project was 
authorized under Flood Control Act of August, 
1968. Recreation, as a project purpose, has been 
deferred until such time as the water quality 
problem on Pond Creek is corrected. 
Local cooperation. Section 3 Flood Control Act 
of 1936 as amended applies. In addition, local interests 
must agree to administer project land and 
water areas for recreation and fish and wildlife 
enhancement; and to pay, contribute in kind or 
repay (which may be through user fees) with interest 
one-half of the separable first cost of the 
project allocated to recreation and fish and 
wildlife enhancement; and bear all costs of operation, 
maintenance and replacement of lands and 
facilities for recreation and fish and wildlife 
enhancement. Jefferson County Fiscal Court expressed 
intent to fulfill requirements by resolution 
dated April 4, 1967. Formal assurances of 
local cooperation for the flood protection portion 
of the project were executed by resolution of 
Jefferson County Fiscal Court, adopted 
September 17, 1971, and assurances for the 
recreation portion of the project were executed by 
similar resolution, adopted September 14, 1971. 
Operations and results during fiscal year. 
Engineering studies continued. Plans and 
specifications for levee and floodwall 2nd Section 
were essentially completed. Design Memoranda 
for Riverport and Lower Mill Creek and for Upper 
Mill Creek and Kosmosdale pumping plants 
advanced to 95 percent and 85 percent completion, 
respectively. Authorization-of-entry for 
levee and floodwall 1st Section has been furnished. 
Construction contract for this sectirn advanced 
to 43 percent completion. 
Condition at end of fiscal year. Special Report, 
Document Plan and Relationship to Flood Plain 
Development, General Design Memorandum and 
Land Requirements Plan, Public Use Recreation 
Resource Appendix, Supplemental Design 
Memorandum, Upper Mill Creek Crossing and 
plans and specifications for levee and floodwall, 
1st Section, are complete. Construction was 
started in October 1973 and project is 6 percent 
complete overall. 
54. TAYLORSVILLE LAKE, KY. 
Location. Dam site is in Spencer County, Ky., 
60.0 miles above the confluence of Salt River and 
Ohio River, four river miles above Taylorsville 
and 36.9 river miles above Shepherdsville, Ky. 
Existing project. A reservoir for flood control 
and allied purposes. Dam will be an earth and 
rock fill structure, 164 feet high and 1,280 feet 
long. Outlet works will be slide gate controlled 
and spillway will be uncontrolled open cut. Total 
storage capacity will be 291,670 acre-feet (211,- 
230 for flood control, winter months) and 52,245 
for water quality and Fish & Wildlife. Estimated 
Federal cost of new work (1975) is $62,554,000, of 
which $3,177,000 is for recreation facilities under 
the completed projects program, and $10,648,000 
is non-Federal responsibility for recreation 
facilities. Project was authorized by 1966 Flood 
Control Act. 
Local cooperation. Local interests must agree to 
administer project land and water areas for 
recreation; pay, contribute in kind, or repay 
(which may be through user fees) with interest 
one-half of the separable first costs of the project 
allocated to recreation; bear all costs of operation, 
24-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
maintenance, and replacement of recreation 
lands and facilities. Local interests must also 
agree to prevent encroachments on flow-carrying 
capacities of stream channels below the reservoir 
to the extent needed to provide reasonably effective 
reservoir operation. Commonwealth of Kentucky 
has indicated intent to fulfill requirements 
for recreation cost-sharing and has assumed 
responsibility for channel encroachments and 
pollution control. The Commonwealth furnished 
assurance agreements covering prevention of encroachment 
on capacity of stream channels in 
April and May 1973 and executed the recreation 
cost-sharing contract in April 1973. 
Operations and results during fiscal year. 
Engineering and design studies continued. Acquired 
34 tracts of land. Design Memorandum, 
Utilities Relocations and plans and specifications 
for the outlet works were completed. Master plan 
remained at 80 percent complete. Plans and 
specifications for the shop and office building 
were started and advanced to 5 percent completion. 
Contract for North and South Access Roads 
and Tailwater Access Road advanced to 35 percent 
completion. 
Condition at end of fiscal year. General Design 
Memorandum and other preconstruction planning 
items are complete. Feature Design 
Memoranda for outlet works, dam, spillway and 
connector road, state and county road relocations, 
and utilities relocations and plans and 
specifications for the outlet works are also complete. 
60 tracts of land of estimated 400 required 
for project have been acquired. Construction was 
started in June 1974 and project is about 8 percent 
complete overall. 
55. WABASH RIVER BASIN 
Location. Works covered by this project are 
located in the Wabash River Basin, a drainage 
area of 33,100 sq. mi., covering parts of Indiana, 
Illinois and Ohio. 
Existing project. Individual projects considered 
in comprehensive plan. (See Table 24-B 
on Authorizing Legislation at end of chapter). 
Operations and results during fiscal year. See 
individual listings for Big Blue Lake, Ind., Big 
Walnut Lake, Ind., Helm Lake, Ill., Louisville 
Lake, Ill., and Marion, Ind. projects. 
Condition at end of fiscal year. See individual 
listings of projects. 
56. WEST FORK OF MILL CREEK 
LAKE, OHIO 
Location. Dam is on West Fork of Mill Creek 6.5 
miles above its junction with Mill Creek and 2 
miles northeast of Mount Healthy, Ohio, and 10 
miles north of downtown Cincinnati. Reservoir 
extends upstream about 3 miles and is in 
Hamilton County, Ohio. 
Existing project. An earth embankment dam 
and a reservoir for flood control, recreation, and 
reduction of pumping requirements at Mill Creek 
barrier dam in Cincinnati. Total storage capacity 
of reservoir is 11,300 acre-feet, of which 9,850 
acre-feet is for flood control. For further details 
see page 1119 of Annual Report for 1962. Federal 
cost of completed new work is $3,092,942, non- 
Federal cost is $570,801 which includes $50,000 
contributed in fulfillment of project authorization. 
Latest published map is in House Document 
198, 80th Congress, 1st session. Existing project 
selected for construction under additional 
authorization for Ohio River Basin in 1946 Flood 
Control Act. 
Local cooperation. Local interests were to 
release necessary land under their control, give 
assurance that future channel encroachment 
below damsite would be prevented. For enlargement 
of reservoir to include a conservation pool, 
local interests would contribute one-half additional 
cost of such pool, including one-half cost 
of relocation of sanitary sewer, and agree to hold 
the United States free from damages resulting 
from its provision. Board of county commissioners 
of Hamilton County, Ohio, adopted a 
resolution October 8, 1947, signifying willingness 
to fulfill requirements including provision of conservation 
pool. Assurances were executed on 
same date. A contract with the United States for 
relocation of sanitary sewer outside reservoir 
area in order to include conservation pool in project 
was accepted by Hamilton County, in which 
the United States paid one-half cost of such 
relocation work. Hamilton County Commissioners 
furnished $50,000, required as a local 
contribution toward additional cost of providing 
conservation pool. Hamilton County Park District 
has undertaken development and management 
of recreation facilities in reservoir area for 
use of the public in accordance with license 
granted by Secretary of the Army on October 31, 
1951. 
Operations and results during fiscal year. 
Routine maintenance was performed. Operation 
for flood control during 1975 flood season 
prevented damages estimated at $195,000. 
Condition at end of fiscal year. Construction 
started March 1949 and reservoir was placed in 
operation in December 1952. Project is complete. 
57. WEST TERRE HAUTE, IND. 
Location. In Vigo County on right bank of 
Wabash River about 215 miles above mouth. 
Existing project. Provides for construction of 
24-22

LOUISVILLE, KY., DISTRICT 
about 2.5 miles of earth levee, traffic ramps, and 
facilities for disposal of interior drainage. It will 
provide protection to town of West Terre Haute 
against a flood expected to occur an average of 
once each 100-year period. Estimated Federal 
cost of new work (1975) is $1,080,180 for construction 
and non-Federal cost of lands and damages is 
$150,000, a total cost of $1,230,180. Existing project 
was authorized under 1938 Flood Control 
Act. 
Local cooperation. Section 3, Flood Control Act 
of 1936, as amended, applies. West Vigo Levee 
Association, Inc., furnished assurances by letter 
dated May 16, 1963. Authorization-of-entry was 
furnished on May 17, 1968. Operation and 
maintenance of the completed portions of the project 
has been transferred to the West Vigo Levee 
Association, Inc. 
Operations and results during fiscal year. 
Engineering and design is essentially complete. 
Contract for Pumping Plant is complete except 
for testing pumps. 
Condition at end of fiscal year. Levees and 
Floodwall are complete. Pumping plant is essentially 
complete except for testing pumps. Project 
is essentially complete. 
58. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to maintain and 
operate completed local protection projects in accordance 
with regulations prescribed by 
Secretary of Army. Inspections were made to 
determine extent of compliance and to advise 
local interests as necessary to measures required 
to correct deficiencies. (See table 24-K on local 
protection projects and channel improvements.) 
Fiscal year costs were $143,547. Total costs to 
June 30, 1975 were $856,308. 
59. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 24-I. 
60. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION. 
Flood control and coastal emergencies (pursuant 
to Public Law 99, 84th Cong., and antecedent 
legislation). 
Costs during fiscal year were $13,477 for advance 
preparation, $9,350 for flood emergency 
operations and $32,068 for repair of damaged 
levees. 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization). 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (Sec. 208, 
1954 Flood Control Act, Public Law 780, 83rd 
Congress). 
(See Table 24-J). 
General Investigations 
61. SURVEYS 
Fiscal year costs were $1,201,609 of which 
$149,749 was for navigation studies, $619,891 for 
flood control studies, $155,517 for the Wabash 
River Basin Authorization Report, $95,410 for 
review of authorized projects, $127,769 for inventory 
of dams, $3,002 for watershed studies, $43,- 
125 for coordination with the Ohio River Basin 
Commission, $7,126 for cooperation with states, 
and $20 for special study survey. 
62. COLLECTION AND STUDY OF 
BASIC DATA. 
Fiscal year costs were $221,371 for flood plain 
information studies, $46,469 for technical services 
for others, $102,326 for flood plain management 
services, and $4,579 for Special Flood 
Hazard Information Report, totaling $374,745. 
Flood plain studies completed are listed in Table 
24-M. 
Fiscal year costs for hydrology studies were 
$1,400. 
63. RESEARCH AND DEVELOPMENT. 
None. 
24-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-A COST AND FINANCIAL STATEMENT 
See 
Section Total 
in Text Project 
2. Green and Barren 
Rivers, Ky. 
3. Kentucky River, Ky. 
7. Barren River Lake, 
Ky. 
8. Big Blue Lake, Ind. 
9. Big Pine Lake, Ind. 
10. Big Walnut Lake, 
11. Booneville Lake, 
Ky. 
13. Brookville Lake, 
Ind. (Federal Funds) 
(Contributed Funds) 
14. Buckhorn Lake, Ky. 
15. Caesar Creek Lake, 
Ohio 
16. Cagles Mill Lake, 
Ind. 
17. Camp Ground Lake, 
Ky. 
18. Carr Fork Lake, Ky. 
i
I 
1 Funding FY 72 FY 73 FY 74 FY 75 30 Jun 75 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost * 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,422,208 
709,504 
1,047,130 
1,001,761 
-39,500 
38,204 
374,400 
350,176 
127,530 
15,757 
245,000 
142,543 
4,404,900 
4,110,200 
697,800 
878,716 
-14,000 
224,282 
261,500 
229,908 
2,885,400 
2,140,122 
173,200 
144,951 
4,416,500 
5,050,785 
331,012 
1,148,563 
1,295,188 
1,160,749 
105,000 
31,028 
689,000 
463,502 
296,376 
233,957 
-3,000 
1,828 
-25,300 
82,300 
6,950,000 
3,818,972 
1,870,000 
1,183,257 
-1,280 
3,271 
392,800 
259,660 
5,800,000 
4,904,896 
212,700 
156,965 
5,900,000 
4,961,482 
996,400 
921,789 
1,331,500 
1,506,354 
-2,567 
81,275 
360,500 
609,384 
143,743 
178,000 
80,343 
175,000 
64,975 
5,300,000 
6,301,004 
63,900 
57,278 
815,400 
1,311,738 
-13,273 
850 
285,800 
419,078 
2,200,000 
2,827,315 
197,700 
266,471 
4,000,000 
4,768,949 
462,260 
589,364 
1,667,440 
1,745,659 
1,019,000 
248,055 
508,700 
506,970 
100,000 
81,816 
780,000 
272,239 
360,000 
434,729 
9,000 
88,985 
2,025,000 
4,074,384 
158,400 
159,764 
368,100 
390,975 
345,400 
313,163 
5,168,360 
5,402,142 
17,100 
16,617 
197,500 
187,490 
80,000 
64,613 
4,687,000 
4,550,690 
72,600 
71,455 
24-24 
13,808,2221 
13,808,2721 
14,271,5482 
14,260,6332 
4,176,749 
4,176,749 
24,647,3173 
24,613,8803 
556,956 
556,956 
26,264,4374 
25,487,3705 
3,403,8116 
3,374,236 
100,000 
81,816 
1,644,376 
1,128,526 
470,000 
546,610 
999,700 
959,747 
32,639,900 
31,788,115 
222,300 
217,042 
8,117,000 
7,300,796 
11,753,3387 
11,753,3387 
2,604,612 
2,531,158 
23,423,360 
22,568,360 
17,100 
16,617 
4,143,5818 
4,143,5818 
1,770,999 
1,737,441 
80,000 
64,613 
38,672,500 
37,803,669 
72,600 
71,455

LOUISVILLE, KY., DISTRICT 
TABLE 24-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 75 
19. Cave Run Lake, Ky. 
20. Cecil M. Harden Lake, 
Ind. 
21. Clarence J. Brown 
Dam & Reservoir, 
Ohio 
22. Clifty Creek Lake, 
Ind. 
23. Dayton, Ky. 
24. Eagle Creek Lake, 
Ky. 
25. East Fork Lake, 
Ohio 
26. Evansville, Ind. 
27. Falmouth Lake, Ky. 
28. Frankfort, Ky. 
(Contributed Funds) 
29. Greenfield Bayou 
Levee, Ind. 
30. Green River Lake, 
Ky. 
31. Helm Lake, Ill. 
32. Huntington Lake, 
Ind. (Federal 
Funds) 
(Contributed Funds) 
33. Indianapolis, Ind. 
34. Island Levee, Ind. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
6,180,800 
5,801,040 
159,200 
161,844 
4,674,000 
3,731,218 
102,000 
80,870 
57,000 
4,417 
164,000 
148,541 
3,809,200 
3,837,984 
315,100 
142,174 
99,300 
96,358 
4,114 
5,565 
399,700 
614,685 
396,300 
364,474 
-28,700 
46,464 
223 
170,200 
164,059 
248,600 
28,492 
8,245,000 
6,779,967 
148,300 
146,899 
3,805,000 
4,155,659 
100,000 
62,267 
11,742 
19,300 
110,297 
4,200,000 
1,951,707 
369,000 
161,776 
110,624 
115,909 
2,287 
-8,106 
27,690 
298,000 
21,265 
225,000 
204,141 
418,000 
406,833 
75,000 
-30,000 
27,700 
508 
162,700 
162,836 
8,557,616 
7,547,387 
70,600 
65,700 
192,500 
8,267 
156,500 
151,637 
2,200,000 
3,196,797 
71,200 
63,405 
200,000 
81,266 
-45,000 
1,691 
125,000 
14,398 
1,901,000 
3,100,000 
588,000 
544,276 
150,000 
120,906 
2,172 
-285,000 
12,029 
-49,616 
546,000 
402,968 
-30,000 
41,616 
41,006 
26,809 
803 
211,200 
189,834 
65 - 
208,000 
30,866 
-420,000 
18,306 
3,300,000 47,429,716 
5,409,856 46,153,379 
181,700 252,300 
182,030 247,730 
250,000 6,722,3189 
1,773 6,289,85810 
225,900 1,475,596 
201,661 1,443,665 
1,537,000 21,712,700 
1,677,321 21,333,245 
168,600 239,800 
170,862 234,267 
61,900 956,900 
138,131 785,043 
- 164,745" 
4,158 156,289 
-119,000 703,300 
20,137 701,835 
7,279,000 25,407,17112 
8,182,996 25,026,495 
1,664,000 9,081,45613 
1,663,849 8,510,532" 
23,268 737,01314 
103,297 735,96414 
- 2,894,487 
16,762 2,848,238 
- 161,098 
- 161,098 
- 192,971 
2,213 157,612 
- 33,105,184 
187 33,105,184 
570,800 2,421,871 
705,585 2,361,639 
-3,384 41,616 
- 41,616 
141,179 19,401,045'5 
2,700 19,193,99216 
- 193,800 
- 193,405 
169,100 946,066 
190,713 935,957 
- 1,939,36317 
- 1,939,36317 
25,000 
14,157 
229,527 
207,206 
24-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 75 
35. Lafayette Lake, 
Ind. 
36. Levee Unit No. 5, 
Wabash River, Ind. 
37. Lincoln Lake, Ill 
38. Louisville, Ohio 
River Basin, Ky. 
(Contributed Funds) 
39. Louisville Lake, 
Ill. 
40. Marion, Ind. 
41. Mason J. Niblack 
Levee, Ind. 
42. Mill Creek, Ohio 
43. Mississinewa Lake 
Ind. (Federal Funds) 
(Contributed Funds) 
44. Monroe Lake, Ind. 
(Federal Funds) 
(Contributed Funds) 
45. Newport-Wilders, 
Ky. 
46. Nolin Lake, Ky. 
47. Ohio River Basin, 
Louisville District 
48. Patoka Lake, Ind. 
(Contributed Funds) 
49. Red River Lake, Ky. 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
59,676 
88,300 
1,092,520 
354,400 
307,329 
85,000 
221,981 
243,500 
131,287 
60,000 
35,078 
99,300 
35,215 
-7,000 
22,179 
158,900 
158,172 
175 
147,400 
138,273 
137,430 
327,300 
356,089 
88 
15,137 
1,361,600 
1,523,838 
385,400 
729,797 
152,900 
181,208 
48,283 
554,000 
487,031 
52,500 
74,801 
8,500 
36,729 
98,968 
230,100 
253,209 
-38,400 
14,166 
235,055 
283,259 
25,000 
21,618 
169,200 
154,883 
542 
-2,597 
-1,563 
181,100 
181,294 
4,939 
94,000 
163,357 
990,000 
529,384 
11,945 
25,185 
2,900,000 
2,709,757 
1,575,800 
1,176,292 
397,000 
129,799 
75,000 
39,187 
97,499 
143,065 
-226,000 
62,342 
500 
3,062 
1,000 
1,633 
50,000 
130,051 
10,000 
23,258 
95,000 
56,028 
390,000 
198,207 
90,000 
48,540 
172,100 
182,543 
440 
262,000 
10,478 
166,500 
171,029 
6,000 
-976 
2,617 
487,000 
943,005 
15,000 
13,654 
2,863,400 
3,011,916 
2,388,500 
1,418,356 
-310,000 
186,851 
143,274 976,547 
39,762 834,098 
10,000 6,127,167 
219,493 5,970,885 
- 1,340,900 
19,711 1,331,250 
-474 25,005,137 
- 25,005,137 
- 1,716,700 
- 1,716,301 
763,100 1,371,70018 
159,022 727,333 
85,000 125,000 
49,540 72,798 
724,000 2,444,600 
549 1,681,980 
400,000 1,124,354 
588,650 1,105,332 
146,000 23,788,30019 
6,264 23,578,2862 
184,900 1,124,710 
184,941 1,113,887 
- 239,200 
150 238,067 
289,000 7,365,76521 
3,993 6,829,2362 
224,100 1,385,620 
201,851 1,355,393 
- 8,018,700 
- 8,018,700 
- 11,165 
3,491 8,6562 
69,000 15,165,064 u 
69,002 15,165,059U 
603,100 4,181,2102 
625,055 4,127,8382 
- 1,516,142 
- 1,509,583 
3,617,000 12,085,000 
3,459,999 11,742,915 
3,170,000 8,331,700 
1,483,363 5,173,381 
174,200 1,813,100 
269,628 1,775,128 
24-26

LOUISVILLE, KY., DISTRICT 
TABLE 24-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 75 
50. Rough River Lake & New Work 
Channel Improvement, Approp. 5,000 29,000 306,000 195,000 10,549,1962 
Ky. Cost 18,135 24,712 27,203 328,986 10,397,326n 
Maint. 
Approp. 407,300 1,014,550 505,700 572,800 4,392,1982 
Cost 383,277 600,391 915,916 608,370 4,347,507s 
51. Salamonie Lake, Ind. New Work 
(Federal Funds) Approp. 11,000 - 82,293 283,000 '16,610,043 
Cost 37,390 688 238 16,244,2833 
Maint. 
Approp. 177,700 178,350 166,700 187,700 1,305,078 
Cost 168,348 176,198 177,372 182,593 1,294,602 
(Contributed Funds) New Work 
Contrib. - - 170,800 
Cost 372 404 - - 164,184 
52. Saline River & New Work 
Tributaries, Ill. Approp. 1,552,500 1,896,500 1,340,000 -109,000 7,170,000 
Cost 1,812,662 1,117,008 1,327,893 914,192 7,030,765 
53. Southwestern New Work 
Jefferson County, Approp. 223,000 384,414 781,000 1,320,000 2,985,414 
Ky. Cost 140,777 166,712 610,910 1,044,434 2,213,711 
54. Taylorsville Lake, New Work 
Ky. Approp. 299,000 800,000 1,606,000 1,612,000 4,915,000 
Cost 207,035 205,834 1,821,000 1,593,767 4,422,560 
55. West Fork of Mill New Work 
Creek Lake, Ohio Approp. - - - 150,000 3,242,94131 32 
Cost - - - 120 3,093,06131 
Maint. 
Approp. 110,800 97,800 89,400 140,000 1,242,633 
Cost 86,176 118,426 104,614 131,725 1,233,081 
57. West Terre Haute, New Work 
Ind. Approp. 415,100 -30,000 -15,500 -10,000 1,080,180 
Cost 303,713 148,808 15,014 4,967 1,032,193 
1. Includes $85,000 public works funds. 
2. Includes $2,000 emergency relief funds $19,000 
"Maintenance and Operation of dams and other improvements 
of navigable waters" funds, and $3,842,667 expended 
from 1888 to June 30, 1936 for operating and care of 
works of improvement under provisions of permanent indifinite 
appropriation for such purpose. 
3. Includes $203,127 allotted in prior years from appropriation 
"Maintenance and Operation of dams and other 
Improvements of vanigable waters", and $6,405,372 expended 
between July 5, 1885 and June 30, 1937 on operation and care 
of works of improvement under provisions of permanent indifinite 
appropriation for such purposes. 
4. Includes 1,238,500 Code 711 funds. 
5. Includes 451,100 Code 711 funds. 
6. Includes 100,000 Supplemental funds. 
7. Includes 61,451 public work acceleration executive 
1963 funds, $130,220 Code 711 funds and $243,619 Code 712 
funds.
8. Includes $35,814 Code 711 funds. 
9. Includes $19,683 Code 711 funds (regular) and $442,- 
500 Code 711 funds (cost-sharing). 
10. Includes $19,683 Code 711 funds (regular) and $10,- 
040 Code 711 funds (cost-sharing). 
11. Includes $12,426 allotted to Bellevue - Dayton and 
used in study of that project. 
12. Includes $58,571 for preconstruction planning 
engineering and design completed before FY 1953. 
13. Includes $11,812 emergency relief funds. 
14. Includes $263,821 for preconstruction planning 
engineering and design completed before FY 1953. 
15. Includes $207,179 Code 711 funds (cost-sharing). 
16. Includes $385 Code 711 funds (cost-sharing). 
17. Includes $2,889 contributed funds expended for new 
work. 
18. Includes $638,100 advance funding for Government 
participation in the construction of U.S. Route 45 relocation 
by the State of Illinois. 
19. Includes $215,000 Code 711 funds (cost-sharing). 
20. Includes $5,193 Code 711 funds (cost-sharing). 
21. Includes $1,185 Code 711 funds (regular) and $511,- 
000 Code 711 funds (cost-sharing). 
22. Includes $1,185 Code 711 funds (regular) and $14,471 
Code 711 funds (cost-sharing). 
23. Includes $5,165 for cost through FY 1941 for Definite 
Project Report for Wilders, Ky. 
24. Includes $568,000 Code 711 funds, $21,897 public 
works acceleration executive 1960 funds and $18,195 contributed 
funds expended on new work. 
25. Includes $22,000 Special Recreation Use Fees. 
26. Includes $196,306 public works acceleration executive 
1963 funds and $818,815 Code 711 funds. 
27. Includes $196,306 public works acceleration executive 
1963 funds and $666,964 Code 711 funds. 
28. Includes $21,500 Special Recreation Use Fees. 
29. Includes $366,000 Code 711 funds (cost-sharing). 
30. Includes $238 Code 711 funds (cost-sharing). 
31. Excludes $50,000 contributed funds expended for 
new work. 
32. Includes $150,000 Code 711 funds (cost-sharing). 
24-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 11, 1888 
Mar. 3, 18931 
July 13, 1892 
July 13, 1902 
Mar. 3, 19052 
Mar. 3, 1909 
July 3, 19302 
June 26, 19343 
Aug. 30, 19352 
Sept. 3, 1954 
Aug. 28, 1937 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
July 3, 1958 
GREEN AND BARREN RIVERS, KY. (See Section 2 of Text) 
Purchase of original improvement. 
Construction of Lock 2, Green River. 
Construction of Lock 5, Green River. 
Construction of Lock 6, Green River. 
Appropriated $5,000 for continuing improvements of Green 
River above mouth of Big Barren River, with provision 
"That the Secretary of War may, in his discretion expend 
such portion of said amount as may be necessary for removal 
of snags in Nolin River." 
Construct new Lock 1 and new Lock and Dam 2, Green River. 
Construct new locks at Dam 5, Green River, and Dam 1 Barren 
River; modification of Dam 5, Green River, widen bends 
in Bear Creek, Ky. 
Operation and care of locks and dams with War Department 
Appropriations for rivers and harbors. 
Improvement of Nolin River. 
Channel enlargement lower 103 miles of Green River. 
Revocation of authorities for improvement of Bear Creek 
and Nolin River. 
OHIO RIVER BASIN (Louisville Dist.) (See Section 48 
of Text) 
Construct levee, floodwalls, and drainage structures 
for protection of cities and towns in Ohio River Basin, 
projects to be selected by Chief of Engineers with approval 
of Secretary of War, at a cost not to exceed $24,877,000 
for construction. 
Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable in 
discretion of Secretary of War and Chief of Engineers, and 
for initiation and partial accomplishment of plan, 
authorized $75 million for reservoirs and $50.3 million for 
local protection works, individual projects to be 
selected and approved by Chief of Engineers subject to 
provision that authorization shall include diversion of 
Cache River above Cairo, Illinois and protection of area 
north of Cairo drainage district by levees at an estimated 
cost of $2 million. 
Additional $45 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $70 million for further prosecution of 
comprehensive plan for Ohio River Basin, including plan 
of improvement for flood control and other purposes in 
Kentucky River Basin. 
Flood protection works at Taylorsville, Kentucky at an 
estimated cost of $129,350 
Channel improvement of lower Rough River & Barnett Creek 
at an estimated cost of $360,000. 
Additional $125 million for further prosecution of 
comprehensive plan, including plan of improvement for 
flood control in Wabash River Basin, Illinois and Indiana 
at an estimated cost of $9,629,000. 
Also, West Fork of Mill Creek at an estimated cost of 
$1,527,000. 
Additional $100 million for prosecution of comprehensive 
plan for Ohio River Basin, including necessary bank 
stabilization measures at New Harmony Bridge, Indiana, 
at an estimated cost of $500,000. 
Flood Control Act of 1958 modified comprehensive plan to 
provide for Monroe Reservoir on Salt Creek, White River 
Basin, Indiana, at an estimated cost to United States of 
$4,359,000; cost to local interests, $5,141,000. 
H. Ex. Doc. 111, 49th Cong., 
2nd Sess., Annual Report 1887, 
p. 1903. 
Annual Report, 1891, p. 2439. 
Annual Report, 1891, p. 2478. 
S. Doc. 82, 83d Cong., 2nd Session. 
Rivers and Harbors Committee 
Doc. 2, 71st Cong., 1st 
Session, and H. Doc. 685, 69th 
Cong., 2nd Session. 
H. D. 480, 72d Cong., 2nd 
Session. 
S. D. 83d Cong., 2nd 
Sessions. 
Flood Control Committee 
Document 
1, 75th Cong., 1st Session. 
Flood Control Committee 
Document 
1, 75th Cong., 1st Session. 
H. Doc. 504, 78th Cong., 2nd 
Sess. 
S. D. 105, 78th Cong., 1st 
Sess. 
H. D. 535, 78th Cong., 2nd 
Sess. 
H. D. 197, 80th Cong., 1st 
Sess. 
H. D. 198, 80th Cong., 1st 
Sess. 
H. D. 192, 85th Cong., 1st 
Sess. 
24-28

LOUISVILLE, KY., DISTRICT 
TABLE 24-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Flood Control Act of 1962 deleted Jessamine Creek Reservoir 
on Kentucky River, Kentucky, form comprehensive plan for 
Ohio River Basin. 
Additional $150 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $38 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $69 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $120 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
WABASH RIVER BASIN (See Section 55 of Text) 
Construction of five multiple-purpose reservoirs and one 
local protection project in Wabash River Basin, Ill. and 
Ind., with proviso that construction of Big Walnut Lake, 
Ind. project must be approved by the President. 
Authorization of $50,000 for initiation and partial 
accomplishment of project. 
H. D. 423, 87th Cong., 2nd 
Sess. 
Public Law 88-253, 88th Cong., 
1st Sess. 
Public Law 89-42, 89th Cong., 
1st Sess. 
Public Law 90-17, 90th Cong., 
1st Sess. 
Public Law 90-483, 90th Cong., 
2nd Sess. 
Public Law 91-282, 91st Cong., 
2nd Sess. 
Public Law 93-251, 93rd Cong., 
2nd Sess. 
S. D. 96, 90th Cong., 2nd Sess. 
1. Deficiency act. 
2. Authorization for Nolin River and Bear Creek revoked 
by Act of Sept. 3, 1954. 
3. Permanent Appropriations Repeal Act. 
24-29 
Oct. 23, 1962 
Dec. 30, 1963 
June 18, 1965 
May 12, 1967 
Aug. 13, 1968 
June 19, 1970 
Mar. 7, 1974 
Aug. 13, 1968

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-C GREEN AND BARREN RIVERS, KY.: PRINCIPAL DATA 
CONCERNING LOCKS AND DAMS 
(See Section 2 of Text) 
Greatest Elevation Depth Depth 
Length of on Lower on Upper 
Miles Width of of Lift at Normal Miter Miter 
Lock Location of from Lock Lock Normal Pool Sill at Sill at 
and Nearest Mouth of Chamber Available Pool Above Normal Normal 
Dam Town River (feet) for Full (feet) Mean Pool Pool 
Width Sea Level Level Level 
(feet) (feet) (feet) (feet) 
GREEN RIVER 
New 1 Spottsville, Ky. 9.1 84.0 600.0 11.81 349.1 11.3 12.1 
New 2 0.3 miles below Calhoun, Ky. 63.1 84.0 600.0 14.3 363.4 11.7 15.0 
3 0.3 miles below Rochester, Ky. * 108.5 35.8 137.5 17.0 380.4 5.6 7.3 
4 Woodbury, Ky. 149.02 35.8 138.0 16.4 396.8 6.5 7.1 
5 0.3 miles below Glenmore, Ky. 168.13 56.0 360.0 15.2 412.0 9.3 12.0 
6 2.8 miles above Brownsville, Ky. 181.73 36.0 " 145.0 9.2 421.1 8.8 8.0 
BARREN RIVER 
1 0.3 miles above Greencastle, Ky. 15.04 56.0 360.0 15.2 412.0 9.3 12.0 
Lock 
and Character of Type of Type of Year Cost of lock 
Dam Foundation Dam Construction Completed and Dam 
GREEN RIVER 
New 1 Shale and coal Fixed Concrete masonry' 19566 $5,101,9787 
New 2 Shale Fixed Concrete masonry 19568 4,799,2719 
3 Rock Fixed Wood crib 1833-36 121,377 
4 Rock Fixed2 Wood crib 1839 125,718 
5 Piles and rock Fixed'0 Concrete masonry 1934 1,020,868"1 
6 Gravel Fixed Wood crib, concrete cap 1905 168,415 
BARREN RIVER 
1 Gravel Fixed Wood crib, concrete cap 1841 871,56512 
Piles in gravel - - 1934 
1. At normal pool dam 48, Ohio river, Elev. 337.3 Green 
River datum (Elev. 338.0 Ohio River datum). 
2. Breaching of dam on May 24, 1965, stopped through 
traffic to Bowling Green, Ky. 
3. Operation discontinued Aug. 1, 1951. 
4. Distance from mouth of Green River is 164.5 miles. 
Lock closed to navigation as the result of loss of pool at Green 
River lock and dam 4 on May 24, 1965. 
5. New cellular concrete masonry dam constructed 
1970-71 with O&M General funds at cost of $822,000. 
6. New lock 1, placed in operation May 25, 1956, old dam 
1, completed 1835-40, replaced with new dam in 1971. 
7. Does not include $179,110 cost of old lock and dam 1. 
8. New lock and dam 2, placed in operation June 18, 
1956. 
9. Does not include $295,696 cost of old lock and dam 2. 
10. With movable A-frame crest 3 feet high. 
11. Does not include $179,434 cost of old lock and dam 5. 
12. Includes $729,269 for new large lock completed in 
1934. 
24-30

LOUISVILLE, KY., DISTRICT 
TABLE 24-D GREEN AND BARREN RIVERS, KY.: TERMINAL FACILITIES 
(See Section 2 of Text) 
River Mile Purpose Nearest Town 
Green 81.5 Receiving coal South Carrollton, Ky. 
Green 85.25 Loading coal South Carrollton, Ky. 
Green 85.9 Loading coal South Carrollton, Ky. 
Green 97.7 Loading coal Rockport, Ky. 
Green 99.5 Loading coal Paradise, Ky. 
Green 105.7 Loading coal Rochester, Ky. 
Green 108.1 Loading coal Rochester, Ky. 
Barren1 29.7 Receiving gasoline Bowling Green, Ky. 
Barren I 29.9 Receiving gasoline Bowling Green, Ky. 
1. Not active. 
24-31

TABLE 24-E KENTUCKY RIVER, KY.: LOCKS AND DAMS 
(See Section 3 of Text) 
Lock 
Greatest Elevation 
Available of Normal Depth on 
Dam Nearest Town Miles Clear Length Lift of Pool Above Lower Foundation Year Cost 
from Width (full width Lock Mean Meter Sill Completed 
Mouth (feet) of lock (feet) Sea Level (feet) 
feet) (feet) 
11 3.8 miles above Carrollton, Ky. 4.0 38 145 8.22 430.0 4.8 Rock and clay 18393 $ 
21 Lockport, Ky. 31.0 38 145 13.9 443.9 6.1 Rock 18393 
31 Gest, Ky. 42.0 38 145 13.2 457.1 6.5 Rock 18443 1,350,3854 
41 1 mile below Frankfort, Ky. 65.0 38 145 13.2 470.3 6.3 Rock 18443 
51 2.8 miles below Tyrone, Ky. 82.2 38 145 15.0 485.3 6.4 Rock 18443 
61 21.6 miles below High Bridge, Ky. 96.2 52 147 14.0 499.3 6.4 Rock and piles 1894 314,847 
71 0.8 miles below High Bridge, Ky. 117.0 52 147 15.3 514.6 6.8 Rock 1897 290,788 
81 4.7 miles above Camp Nelson, Ky. 139.9 52 146 18.7 533.6 6.0 Rock 1900 275,463 
95 Valley View, Ky. 157.5 52 148 17.3 550.6 6.6 Rock 1907 237,646 
105 1 mile below Ford, Ky. 176.4 52 148 17.0 567.6 6.0 Rock 1907 221,500 
115 17.2 miles below Irvine, Ky. 201.0 52 148 18.0 585.6 6.0 Rock 1906 296,593 
126 Ravenna, Ky. 220.0 52 148 17.0 602.6 6.0 Rock 1910 425,693 
136 2.2 miles below Willow, Ky. 239.9 52 148 18.0 620.6 6.0 Rock 1915 461,476 
14s Heidelberg, Ky. 249.0 52 148 17.0 637.6 6.0 Rock 1917 392,902 
m 
1. Fixed dam, crib, construction, concrete cap. 
2. At normal pool McAlpine Dam, Ohio River elev. 421.8 
Kentucky River datum (Elev. 420 Ohio River datum). 
3. Reconstruction completed by United States in 1882. 
4. Built by State of Kentucky. Cost e(v en is for repairs by 
United States to locks and dams 1 through 5. Original construction 
costs to State were: L&D 1, $220,300; L&D 2, $151,- 
983; L&D 3, $135,857; L&D 4, $131,607, L&D 5, $137,436. 
5. Fixed dam, concrete construction 
6. Fixed dam, concrete construction, wooden crest. 
O
0
O
z
z
C' 
v 
c3 
"
3V 

LOUISVILLE, KY., DISTRICT 
TABLE 24-F OHIO RIVER BASIN (LOUISVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS 
(See Section 47 of Text) 
Estimated Cost' 
Type of 
Location 2 Construction Federal Non-Federal Total 
Adams Levee, Ind. (Wabash River)3 
Alton, Ind.3 
Aurora, Ind.3 
Barnett Creek, Ky. (Rough River Basin)' 6 
Bellevue, Ky.3 
Bonpas Creek, Ill. (Wabash River Basin) 
Bromley, Ky. 3 
Brookport, Ill.3 8 
California (Cincinnati), Ohio3 
Cannelton, Ind.3 9 
Carrollton, Ky.3 
Caseyville, Ky.3 
Cave-in Rock, Ill.3 
Cincinnati, Ohio3 to 
Unit 2 
Unit 4 remainder 
Cleves, Ohio3 
Clinton, Ind. (Wabash River)3 
Cloverport, Ky.3 
Concordia, Ky.3 
Covington, Ky.3 11 
Dayton, Ky.3 
6 
Deer Creek Prairie Levee, Ind. 
(Wabash River)3 
Delphi, Ind. (Wabash River' 13 
Derby, Ind.3 
Elizabethtown, Ill.3 
England Pond Levee, Ill. (Wabash River)' 4 
Evansville, Ind.6 
Fletcher and Sunshine Garden Levee, 
Ind. (Wabash River Basin)3 
Frankfort, Ky. (Kentucky River)3 
North Frankfort area 6 
South Frankfort area3 
Benson Creek area3 
Golconda, Ill.3 
16 
Grandview, Ind.3 
Greenfield Bayou Levee, Ind. 
(Wabash River) 6 
Harrisburg, Ill.3 13 
Hawesville, Ky.3 17 
Honey Creek Levee, Ind. 
(Wabash River)3 
Island Levee, Ind. (Wabash River)6 
Jackson, Ky. (Kentucky River Basin)3 10 
Jeffersonville-Clarksville, Ind.9 
Lawrenceburg, Ind.3 
Leavenworth, Ind.3 
Levee Unit 1, Eel River, Ind. 
(Wabash River Basin)3 
Levee Unit 2, Eel River, Ind. 
(Wabash River Basin)3 
Levee Unit 1, Little Wabash River, Ill. 
Levee 
Levee 
Wall and Levee 
Channel improvement 
Wall and Levee 
Channel improvement 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Wall and barrier dam 
Wall and Levee 
Wall 
Levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Wall and Levee 
Wall and levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Cutoff channel 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Levee 
Levee 
$ 292,000 
255,000 
4,300,000 
1,570,000 
1,080,000 
1,250,000 
597,493 
1,750,000 
2,068,391 
2,220,000 
396,000 
661,000 
10,150,935 
16,800,000 
14,900,000 
1,240,000 
77,000 
728,000 
590,000 
7,866,300 
6,730,000 
213,000 
144,563 
553,000 
559,000 
734,498 
36,700,000 
548,000 
2,980,000 
1,950,000 
660,000 
565,333 
580,000 
3,680,000 
870,015 
969,318 
653,000 
3,160,000 
130,952 
4,226,361 
2,433,414 
1,470,000 
204,000 
2,090,000 
2,850,000 
$ 14,000 
40,000 
1,190,000 
400,000 
630,000 
925,000 
8,500 
720,000 
29,105 
97,000 
35,000 
125,000 
1,309,146 
2,900,000 
621,000 
67,000 
9,000 
193,000 
55,000 
1,051,102 
2,481,000 
10,000 
17,164 
67,000 
153,000 
107,000 
6,218,000 
26,000 
272,100 
180,000 
140,000 
10,900 
133,000 
777,000 
20,000 
42,593 
32,000 
345,000 
3,000 
590,888 
284,725 
266,000 
40,000 
$ 306,0004 
295,000 
5,490,000 
1,970,000 
1,710,0007 
2,175,000 
605,993 
2,470,000 
2,097,496 
2,317,000 
431,000 
786,000 
11,460,081 
19,700,000 
15,521,000 
1,307,000 
86,000 
921,000 
645,000 
8,917,402 
9,211,00012 
223,0004 
161,727 
620,000 
712,000 
841,498 
42,918,00012 
574,0004 
3,252,10012 
2,130,00015 
800,00015 
576,233 
713,000 
4,457,00012 
890,015 
1,011,911 
685,000 
3,505,00012 
133,952 
4,817,249 
2,718,139 
1,736,000 
244,000 
715,000 2,805,000 
164,000 3,014,00018 
24-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-F 
(Continued) 
OHIO RIVER BASIN (LOUISVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS 
(See Section 47 of Text) 
Estimated Cost 1 
Type of 
Location 2 Construction Federal Non-Federal Total 
(Wabash River Basin) 
Levee Unit 2, Little Wabash River, Ill. 
(Wabash River Basin) 
Levee Unit 6, Wabash River, Ill. 
(Wabash River Basin) 
Levee Unit 17, Ind. 
(Wabash River Basin) 
Levee Unit 1, White River, Ind. 
(Wabash River Basin) 
Levee Unit 2, White River, Ind. 
(Wabash River Basin) 
Levee Unit 7, White River, Ind. 
(Wabash River Basin) 
Lewisport, Ky. 3 
Louisville, Ky.3 6 19 
Ludlow, Ky.3 
Madison, Ind.3 
Mason J. Niblack Levee, Ind. 
(Wabash River)6 
Mauckport, Ind. 3 
McGinnis Levee, Ind. 
(Wabash River Basin)3 
Metropolis, Ill.3 
Milton, Ky.3 
Moscow, Ohio 3 
New Albany, Ind.3 
10 
New Amsterdam, Ind. 3 
New Harmony Bridge 
New Harmony, Ind. (Wabash River)3 
New Richmond, Ohio 3 
Newport, Ky. 3 9 
Owensboro, Ky. 3 
Paducah, Ky.3 9 
Patriot, Ind.3 
Prestonville, Ky. 3 
Raccoon Levee, Ind. (Wabash River) 3 
Reevesville, Ill. (Cache River)3 21 
Rising Sun, Ind.3 
Rochester and McCleary's Bluff Levee, 
Ill. (Wabash River)14 
Rockport, Ind.3 
Rome, Ind.3 
Rough River, Ky.5 
6 
Russell and Allison Levee, Ill. 
(Wabash River)3 
Shawneetown, Ill. 3 
Shufflebarger Levee, Ind. 
(Wabash River Basin)3 
Smithland, Ky.3 
Sturgis, Ky. (Tradewater River) 14 
Sugar Creek Levee, Ind. (Wabash River) 
Taylorsville, Ky. (Salt River)3 22 
Tell City, Ind.3 19 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee and pumping 
plants 
Levee 
Levee 
Wall and levee 
Wall 
Levee 
Wall and levee 
Levee 
Bank protection 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Levee 
Rockport, 
Wall and levee 
Levee 
Channel improvement 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Levee 
Levee 
Wall and levee 
3,410,000 
1,160,000 
1,580,000 
2,180,000 
724,000 
1,490,000 
610,000 
24,884,000 
2,540,000 
3,820,000 
4,394,000 
506,000 
1,820,000 
3,070,000 
2,480,000 
1,170,000 
5,375,471 
476,000 
962,000 
616,000 
3,200,000 
7,512,987 
886,000 
4,761,532 
753,000 
1,710,000 
426,000 
600,300 
896,000 
1,079,236 
466,000 
359,000 
136,000 
56,000 
118,000 
3,546,0007 
1,216,000 
1,698,0007 
116,000 2,296,00018 
73,000 797,00018 
88,000 1,578,00018 
243,000 
2,600,000 
745,000 
360,000 
109,200 
105,000 
104,000 
431,000 
41,000 
372,000 
740,000 
13,000 
99,000 
25,000 
720,000 
298,506 
195,000 
232,000 
372,000 
55,000 
37,000 
40,000 
280,000 
100,000 
133,000 
67,000 
5,340,000 2,025,000 
1,810,000 
2,380,000 
864,000 
1,826,778 
418,000 
373,050 
932,229 
853,0004 
27,484,00012 
3,285,000 
4,180,000 
4,503,20012 
611,000 
1,924,000 
3,501,000 
2,521,000 
1,542,000 
6,115,471 
489,000 
1,061,00020 
641,000 
3,920,000 
7,811,493 
1,081,000 
4,993,532 
1,125,000 
1,765,000 
463,0004 
640,300 
1,176,000 
1,179,236 
599,000 
426,000 
7,365,0004 
361,000 2,171,000 
90,000 2,470,000 
414,000 
93,000 
29,000 
63,309 
32,707 
1,278,000 
1,919,778 
447,0004 
436,359 
964,936 
24-34

LOUISVILLE, KY., DISTRICT 
TABLE 24-F 
(Continued) 
OHIO RIVER BASIN (LOUISVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS 
(See Section 47 of Text) 
Estimated Cost
1 
Type of 
Location 2 Construction Federal Non-Federal Total 
Tolu, Ky.3 Levee 303,000 35,000 338,000 
Tri-pond Levee, Ill. (Wabash River) Levee 2,050,000 191,000 2,241,00020 
Troy, Ind.3 Wall and levee 502,000 133,000 635,000 
Uniontown, Ky.3 23 Levee 1,070,926 72,153 1,143,079 
Utica, Ind.3 Levee 1,570,000 120,000 1,690,000 
Vevay, Ind.3 Levee 1,170,000 146,000 1,316,000 
Vincennes, Ind. (Wabash River)3 Wall and levee 6,426,000 285,000 6,711,000 
West Point, Ky.3 Wall and levee 3,283,000 400,000 3,683,0004 
Westport, Ky.3 Wall 1,610,000 41,000 1,651,000 
West Terre Haute, Ind. (Wabash River)6 Levee 1,080,180 150,000 1,230,18012 
Wilders, Ky.3 Wall and levee 9,290,000 761,000 10,051,00012 
WABASH RIVER BASIN 
LOCAL PROTECTION PROJECT 
(See Section 55 of Text) 
Marion, Ind. Wall and levee 2,930,000 880,000 3,810,00012 
1. Latest cost estimate revision 1954, unless otherwise 
noted.
2. All projects are on Ohio River unless otherwise noted. 
3. Also see "Other authorized flood control projects". 
4. Latest cost estimate revision 1960. 
5. Part of Rough River Reservoir and Channel Improvement 
Project, Ky. 
6. Details of this project are in individual report. 
7. Latest cost estimate revision 1973. 
8. Complete. See Annual Report for 1958 for details. 
9. Complete. See Annual Report for 1959 for details. 
10. Complete. See Annual Report for 1957 for details. 
11. Complete. See Annual Report for 1965 for details. 
12. Latest cost estimate revision 1975. 
13. Complete. See Annual Report for 1953 for details. 
14. Complete. See Annaul Report for 1972 for details. 
15. Latest cost estimate revision 1964. 
16. Complete. See Annual Report for 1960 for details. 
17. Complete. See Annual Report for 1955 for details. 
18. Latest cost estimate revision 1961. 
19. Complete. See Annual Report for 1962 for details. 
20. Latest cost estimate revision 1971. 
21. Substitute project for Belknap, Karnak, and Ullin, 
Ill., complete. See Annual Report for 1954 for details. 
22. Complete. See Annual Report for 1952 for details. 
23. Complete. See Annual Report for 1956 for details. 
24-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-G OHIO RIVER BASIN (LOUISVILLE DISTRICT): RESERVOIRS 
(See Section 47 of Text) 
Total 
Estimated 
Tributary Basin and Reservoirs Stream Cost 
Great Miami River: 
Brookville Lake, Ind.' 2 3 East Fork of Whitewater River $62,044,000 
Metamora Lake, Ind.4 5 West Fork of Whitewater River 35,300,000 
Green River: 
Mining City Lake, Ky.4 
6 Green River 69,100,000 
Nolin Lake, Ky.' 6 7 Nolin River 16,080,200 
Barren River Lake, Ky.' 7 Barren River 28,281,000 
Green River Lake, Ky.' 8 Green River 38,170,200 
Rough River Lake, Ky.' 7 9 Rough River ' 11,337,000 
Kentucky River: 
Booneville Lake, Ky.' 3 South Fork of Kentucky River 60,700,000 
Buckhorn Lake, Ky.' 7 Middle Fork of Kentucky River 12,250,300 
Carr Fork Lake, Ky.' 3 North Fork of Kentucky River 44,200,000 
Licking River: 
Cave Run Lake, Ky.' 3 10 Licking River 67,163,000 
Falmouth Lake, Ky.' 3 11 Licking River 104,380,000 
Little Miami River: 
Caesar Creek Lake, Ohio' 3 12 Caesar Creek 64,206,000 
East Fork Lake, Ohio' 3 13 East Fork of Little Miami River 55,512,000 
Mill Creek: 
West Fork of Mill Creek Lake, West Fork of Mill Creek 3,092,942 
Ohio' '14 
Wabash River: 
Cagles Mill Lake, Ind.' 7 Mill Creek 4,255,800 
Mansfield Lake, Ind.' 7 Raccoon Creek 6,279,800 
Monroe Lake, Ind.' '5 Salt Creek 14,815,754 
1. Details of this project given in individual report. 
2. Includes $8,395,000 reimbursable by non-Federal interests 
for water supply. 
3. Estimated cost revised 1975. 
4. Also see listing of this project under "Other Authorized 
Flood Control Projects". 
5. Estimated cost revised 1954. 
6. Non-Federal cost is $18,195 additional. 
7. Estimated cost revised 1969. 
8. Estimated cost revised 1973. 
9. Part of Rough River Lake and Channel Improvement. 
Details of this project are in individual report. 
10. Includes $12,663,000 by U.S. Forest Service for 
recreation facilities. 
11. Includes $9,586,000 reimbursable by non-Federal interests 
for recreation facilities. 
12. Includes $5,695,000 reimbursable by non-Federal interests 
for water supply. 
13. Includes $3,379,000 reimbursable by non-Federal interests 
for water supply. 
14. Non-Federal cost is $570,801 additional. 
15. Includes $8,015,323 non-Federal cost. 
24-36

LOUISVILLE, KY., DISTRICT 
TABLE 24-H WABASH RIVER BASIN.(LOUISVILLE DISTRICT): RESERVOIRS 
(See Section 55 of Text) 
Wabash River: 
Big Blue Lake, Ind.1 2 Big Blue River $60,175,000 
Big Walnut Lake, Ind.' 3 Big Walnut Creek 78,491,000 
Downeyville Lake, Ind.4 Flatrock and Little 
Flat Rock Rivers 80,262,000 
Helm Lake, 11.1 5 Skillet Fork 46,988,000 
Louisville Lake, Ill.' 6 Little Wabash River 50,462,000 
1. Details of this project given in individual report. terests for water supply and $9,452,000 reimbursable for 
2. Includes $4,980,000 reimbursable by non-Federal in- recreation facilities. 
terests for water supply and $8,790,000 reimbursable for 5. Includes $11,105,000 reimbursable by non-Federal inrecreation 
facilities. terests for water supply and $7,866,000 reimbursable for 
3. Includes $18,005,000 reimbursable by non-Federal in- recreation facilities. 
terests for water supply and $13,279,000 reimbursable for 6. Includes $8,996,000 reimbursable by non-Federal inrecreation 
facilities, terests for water supply and $1,864,000 reimbursable for 
4. Includes $29,167,000 reimbursable by non-Federal in- recreation facilities. 
24-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to June 30, 1975 
See Annual Operation and 
Project Report For Construction Maintenance 
Aurora, Ohio River Basin, Ind.' - $ 35,420 
Bellevue, Ohio River Basin, Ky,' - 12,853 
Brevoort Levee, Wabash River, Ind.' 1954 1,230,873 
Bromley, Ohio River Basin, Ky.' 
Brookport, 11.2 1958 597,493 
California (Cincinnati) Ohio River Basin, 
Ohio' - 16,465 
Cannelton, Ohio River Basin, Ind.2 1959 2,068,391 
Carrollton, Ohio River Basin, Ky.' - 9,713 
Caseyville, Ohio River Basin, Ky.' 
Cave-in-Rock, Ohio River Basin, Ill.' 
Cincinnati, Ohio River Basin, Ohio2 1957 10,150,935 
Cincinnati (Unit 2) Ohio River Basin, Ohio' 
Cincinnati (Unit 4 remainder) Ohio River 
Basin, Ohio' 
Cleves, Ohio River Basin, Ohio' - 6,343 
Clinton, Ohio River Basin, Ind. (Wabash 
River)' - 6,848 
Cloverport, Ohio River Basin, Ky.' 
Concordia, Ohio River Basin, Ky.' 
Covington, Ohio River Basin, Ky.2 1965 7,862,937 
Deer Creek Prairie Levee, Indiana (Wabash 
River)' 
Delphi, Ohio River Basin, Ind. (Wabash 
River)2 1953 7,862,937 
Derby, Ohio River Basin, Ind.' 
Elizabethtown, Ohio River Basin, Ill.' 
England Pond Levee, Wabash River, 11.2 1972 734,498 
English, Ind. (Little Blue River)2 3 1965 372,353 
Fletcher and Sunshine Gardens, Levee, 
Indiana (Wabash River Basin)' - 3,361 
Frankfort, Ohio River Basin,'Ky. (Kentucky 
River) 4 
Gill Township Levee Unit, Indiana (Wabash 
River)2 1948 561,200 
Golconda, Ohio River Basin, 11.2 1960 565,333 
Grandview, Ohio River Basin, Ind.' - 8,497 
Grassy Creek, Jackson County, Ind.3 1953 70,304 
Harrisburg, Ohio River Basin, 11.2 1952 870,015 
Hawesville, Ohio River Basin, Ky.2 1955 969,318 
Honey Creek Levee, Ohio River Basin, Ind. 
(Wabash River)' 
Indian Creek, Corydon, Ind.2 3 1964 300,143 
Jackson, Ky. (Kentucky River Basin) 1957 130,952 
Jeffersonville-Clarksville, Ohio River 
Basin, Ind.2 1959 4,226,361 
Lawrenceburg, Ohio River Basin, Ind.2 1953 2,433,414 
Leavenworth, Ohio River Basin, Ind.' 
Lebanon Junction, Ky.2 3 1967 130,417 
Levee Units 1 and 2, Eel River, Ohio 
River Basin, Ind. (Wabash River Basin)1' 
Levee Unit 2, White River, Ind.' 
24-38

LOUISVILLE, KY., DISTRICT 
TABLE 24-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last 
Full Report Cost to June 30. 1975 
See Annual Operation and 
Project Report For Construction Maintenance 
Levee Unit 3, East Fork of White 
River, Ind.' 1938 275 
Levee Unit 1, Wabash River, Ill.' 1973 60,000 
Levee Units 1 and 2, Wabash River, Ill.' 1938 
Levee Units 3 and 4, Wabash River, I11.' 1938 216 
Levee Unit 6, Ohio River Basin, Ill. 
(Wabash River)' - 9,922 
Levee Unit 8, White River, Ind.2 1952 700,534 
Levee Units 9 and 10, White River, Ind.' 1939 
Lewisport, Ky.' 
Louisville, Ohio River Basin, Ky.2 1962 24,743,365 
Ludlow, Ohio River Basin, Ky.' - 14,503 
Lyford Levee Unit, Wabash River, Ind.2 1944 267,391 
Madison, Ohio River Basin, Ind.' 
Mason J. Niblack Levee, Ohio River Basin, 
Ind. (Wabash River)2 1965 1,554,712 
Mauckport, Ohio River Basin, Ind.' 
McGinnis Levee, Ohio River Basin, Ind. 
(Wabash River Basin)' 1950 71,049 
Metamora Lake, Ohio River Basin, Ind. 
(Great Miami River)' 
Metropolis, Ohio River Basin, Ill.' - 10,575 
Milton, Ohio River Basin, Ky.' 
Mining City Lake, Ohio River Basin, 
Ky. (Green River)' 350,474 
Moscow, Ohio River Basin, Ohio' 
Mount Carmel, Ill. (Wabash River)2 1972 1,980,675 
Muncie, White River, Ind. 2 1956 887,835 
Neon-Fleming, Kentucky River, Ky.2 3 1963 86,532 
New Albany, Ohio River Basin, Ind.2 1957 5,375,471 
New Amsterdam, Ohio River Basin, Ind.' 
Newburgh, Indiana5 1974 52,061 
New Harmony Bridge, Indiana3 1959 297,624 
New Harmony, Ohio River Basin, Ind., 
(Wabash River)' 
Newport, Ohio River Basin, Ky.2 1959 7,512,987 
New Richmond, Ohio River Basin, Ohio' - 7,104 
Orleans, Ind. 1972 13,158 
Owensboro, Ohio River Basin, Ky.' 
Paducah, Ohio River Basin, Ky.2 1959 4,761,552 
Panther Creek, Ky.2 3 1970 254,031 
Patriot, Ohio River Basin, Ind.' 
Portland, Salamonie River, Ind.2 3 1962 237,657 
Prestonville, Ohio River Basin, Ky.' 
Raccoon Creek Levee, Ind. (Wabash River)' 
Reevesville, Ohio River Basin, Ill. 
(Cache River)2 1954 600,300 
Rising Sun, Ohio River Basin, Ind.' 
Rochester and McCleary's Bluff Levee, 
Ill., (Wabash River)2 1972 1,079,236 
Rockport, Ohio River Basin, Ind.' 
Rome, Ohio River Basin, Ind.' 
Rosiclare, Ill. (Ohio River)2 1954 622,544 
24-39

TABLE 24-I 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to June 30. 1975 
See Annual Operation and 
Project Report For Construction Maintenance 
Russell and Allison Levee, Illinois 
(Wabash River)6 - 48,152 
Salyersville, Licking River, Ky.' 1946 12,000 
Shawneetown, Ohio River Basin, I11.6 - 27,287 
Shoals, East Fork of White River, Ind.' 1938 
Sufflebarger Levee, Ohio River Basin, Ind. 
(Wabash River Basin)' 1950 64,487 
Smithland, Ohio River Basin, Ky.' 
Sturgis, Ky.2 1972 1,826,776 
Sugar Creek Levee, Ohio River Basin, Ind. 
(Wabash River Basin)' 1961 28,061 
Taylorsville, Ohio River Basin, Ky. (Salt 
River)2 1952 373,050 
Tell City, Ohio River Basin, Ind.2 1956 932,229 
Terre Haute (Conover Levee), Ind. 
(Wabash River)2 1965 14,913 
Tolu, Ohio River Basin, Ky.' 
Town Creek, Harrodsburg, Ky.2 3 1967 56,505 
Tri-Pond Levee, Wabash River, Ill.1 1972 65,510 
Troy, Ohio River Basin, Ind.' 
Uniontown, Ohio River Basin, Ky.2 1956 1,070,926 
Utica, Ohio River Basin, Ind.' 
Vevay, Ohio River Basin, Ind.' 
Vincennes, Ind.7 1964 3,308,940 
West Point, Ohio River Basin, Ky.' - 4,490 
Westport, Ohio River Basin, Ky.' 
1. Inactive. 
2. Completed. 
3. Authorized by Chief of Engineers under Sec. 205,1948 
Flood Control Act as amended. 
4. Deferred portion of project. For active portion, see individual 
report. 
5. The Water Resources Development Act of 1974 
modified the Newburgh Locks & Dam project to include the 
bank protection works at Newburgh, Indiana. 
6. To be restudied. 
7. Partially completed to form a useful unit. Remaining 
portion of project inactive. 
24-40

LOUISVILLE, KY., DISTRICT 
TABLE 24-J FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Fiscal Year Cost 
Flood Control: 
Amanda Station, Ohio' $ 5,000 
Eagle Creek @ Indianapolis, Ind.2 14,292 
East Fork Deer Creek, Slaughters, Ky.2 8,750 
Great Miami River, Ross, Ohio' 5,632 
Nicholasville, Ky.2 27,090 
Union Township Levee, Ind.' 5,000 
Snagging and Clearing for Flood Control: 
Muscatatuck River, York, Ind.' 203 
Salamonie River, Ind.3 1,355 
Upper Wabash River, Adams County, Ind.2 1,298 
Emergency Bank Protection: 
Wabash River near Merom, Ind.4 500 
1. Reconnaissance Report. 3. Construction completed. 
2. Detailed Project Report. 4. Construction funds received. 
24-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-K INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 58 of Text) 
Fall Spring 
Local Protection Projects Inspection 1974 Inspection 1975 
Brevoort Levee, Ill. Oct May 
Brookport, Ill. Nov Jun 
Cannelton, Ind. Oct May 
Cinncinnati, Ohio Sep Apr 
Covington, Ky. Sep Apr 
Delphi, Ind. Aug Apr 
England Pond Levee, Ill. Oct May 
Evansville, Ind. Oct May 
Frankfort, Ky. Sep Apr 
Gill Township Levee, Ind. Aug Apr 
Golconda, Ill. Oct May 
Harrisburg, Ill. Oct May 
Hawesville, Ky. Sep May 
Indianapolis, Ind. Aug Apr 
Jeffersonville-Clarksville, Ind. Dec Jul 
Lawrenceburg, Ind. Sep Apr 
Lebanon Junction, Ky. Nov Jun 
Levee Unit No. 5, Ind. Nov Jun 
Levee Unit No. 8, Ind. Aug Apr 
Louisville, Ky. Nov Jun 
Lyford Levee, Ind. Sep Apr 
Mt. Carmel, Ill. Nov Jun 
Muncie, Ind. Aug Apr 
New Albany, Ind. Nov Jun 
Newport, Ky. Sep Apr 
Niblack Levee, Ind. Oct May 
Paducah, Ky. Nov Jun 
Reevesville-Cache River, Ill. Nov Jun 
Rochester-McCleary's Bluff Levee, Ill. Nov Jun 
Rosiclare, Ill. Oct May 
Shawneetown, Ill. Nov May 
Sturgis, Ky. Nov May 
Taylorsville, Ky. Nov Jun 
Tell City, Ind. Oct May 
Terre Haute (Conover Levee), Ind. Sep Apr 
Uniontown, Ky. Oct May 
Vincennes, Ind. Oct May 
West Terre Haute, Ind. Sep Apr 
24-42

LOUISVILLE, KY., DISTRICT 
TABLE 24-K INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(Continued) (See Section 58 of Text) 
Dates of 
Channel Improvement Inspection 
Brazil (Big Walnut Creek), Ind. Sep 1974 
Cypress Creek, Ky. Oct 1974 
Edwardsport, Ind. Sep 1974 
English (Little Blue River), Ind. Jul 1974 
Harrodsburg (Town Creek), Ky. Jul 1974 
Indian Creek at Corydon, Ind. Jul 1974 
Jackson, Ky. (No. Fork Ky. River) Dec 1974 
Muscatatuck River, Ind. Jul 1974 
Neon-Fleming, Ky. Oct 1974 
Panther Creek, Ky. Oct 1974 
Plum Creek, Ky. Jul 1974 
Portland, Ind. (Salamonie River) Aug 1974 
Triplett Creek, Morehead, Ky. Jul 1974 
Troublesome Creek, Ky. Dec 1974 
Whitesburg (No. Fork Ky. River), Ky. Dec 1974 
Bank Revetments 
Cloverport, Ky. (Ohio River) Sep 1974 
Newburgh, Ind. (Ohio River) Oct 1974 
Fiscal year costs were $143,547. Total costs to 30 June 1974 were $856,308. 
24-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 24-L OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Operation and 
Name of Project Report For Construction Maintenance 
Licking River, Ky. 1901 $ 13,045 $ - 
Rough River, Ky. 1 2 1952 105,500 101,196 
Tradewater River, Ky. 2 3 1958 18,568 33,331 
White River, Ind.2 3 1909 119,312 
1. Disposal of Federally owned property authorized by 2. Completed. 
Secretary of Army Sept. 1, 1959, pursuant to authorization in 3. No commerce reported. 
Public Law 996, 84th Cong. (70 Stat. 1062). 
TABLE 24-M FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 62 of Text) 
Date Federal 
Location Requesting Agency Completed Cost 
Little River, Allen Co., Allen County Plan Sept 1974 $28,000 
Indiana Commission and City of 
Fort Wayne 
Indian Creek, Marion Marion County Planning June 1975 20,000 
County, Indiana Department and Indianapolis 
Flood Control 
District 
Henderson County, Kentucky Henderson County Plan Sept 1974 18,000 
Ohio River Commission 
Elizabethtown, Kentucky, City of Elizabethtown June 1975 22,000 
Valley Creek & Tribs. 
Frankfort, Kentucky, Franklin County Planning May 1975 30,600 
Kentucky River Commission and City of 
Frankfort 
Springfield, Ohio, Mad Clark County Regional June 1975 45,000 
River & Buck Creek Planning Commission 
24-44

HUNTINGTON, W. VA., DISTRICT 
All cost and financial statements for projects 
are listed at the end of this chapter. All other 
tables are referenced in text and also appear 
at the end of this chapter. 
This district comprises central and southeastern 
Ohio, all but northern panhandle and northeastern 
portion of West Virginia, eastern Kentucky, 
a portion of midwestern Virginia, a very 
small portion of northwestern North Carolina, 
embraced in drainage basin of Ohio River and its 
tributaries from about mile 127 (below Pittsburgh, 
Pa.) to mile 438, immediately upstream 
from Foster, Ky. 
IMPROVEMENTS 
Page Flood Control (cont) 
1. Construction of locks and dams on 
Ohio River ..................... 25-2 
2. Kanawha River, W. Va. ......... 25-2 
3. Portsmouth State Park Marina, 
Ohio ............................ 25-2 
4. Open-Channel Work, Ohio River . 25-3 
5. Other authorized navigation projects 
.......................... 25-3 
Flood Control 
6. Alum Creek Lake, Ohio ......... 25-3 
7. Athens, Ohio ................... 25-3 
8. Beech Fork Lake, W. Va. ........ 25-4 
9. Bluestone Lake, Ohio River Basin, 
W. Va. ........................ 25-4 
10. Burnsville Lake, Ohio River Basin, 
W. Va ....................... 25-5 
11. Chillicothe, Ohio ............... 25-5 
12. Coal River Basin, W. Va. ........ 25-5 
13. Deer Creek Lake,Ohio River Basin, 
Ohio ............................ 25-6 
14. Delaware Lake, Ohio River Basin, 
Ohio ............................ 26-6 
15. Dewey Lake, Ohio River Basin, Ky. 25-7 
16. Dillon Lake, Ohio River Basin, Ohio 25-7 
17. East Lynn Lake, Ohio River Basin, 
W. Va. ......................... 25-7 
18. Fishtrap Lake, Ohio River Basin, 
Ky. ............................. 25-8 
19. Grayson Lake, Ky. ............. 25-9 
20. John W. Flannagan Dam and Reservoir, 
Ohio River Basin, Va. ...... 25-9 
21. Kehoe Lake, Ky ................. 25-9 
22 Lower Guyandot River Basin, 
W. Va. ......................... 25-10 
23. Martin, Ky. ..................... 25-10 
24. Massillon, Ohio ................ 25-10 
25. Mill Creek Lake, Ohio ........... 2511 
26. Muskingum River Lakes, Ohio ... R 25-11 
27. Newark, Ohio .................. 25-12 
28. North Branch Kokosing River 
Lake, Ohio .................... 25-12 
29. North Fork of Pound River Lake, 
Va. ............................. 25-13 
30. Ohio River Basin (Huntington 
District) ...................... 25-13 
31 Paint Creek Lake, Ohio River Basin 25-13 
32. Paintsville Lake, Ky. ............ 25-14 
33. Panther Creek Lake, W. Va. ..... 25-14 
34. R. D. Bailey Lake, W. Va. ....... 25-15 
35. Roseville, Ohio ................. 25-15 
36. Salt Creek Lake, Ohio ........... 25-16 
37. Summersville Lake, Ohio River 
Basin, W. Va .................. 25-16 
38. Sutton Lake, Ohio River Basin 
W. Va. ......................... 25-16 
39. Tom Jenkins Dam, Ohio River Basin 
Ohio ............................ 25-17 
40. Tug Fork Valley, Ky., Va., and 
W. Va. ..................... 25-17 
41. Utica Lake, Ohio ............... 25-17 
42. Yatesville Lake, Ky ............. 25-18 
43. Inspection of completed flood control 
projects ...................... 25-19 
44. Other authorized flood control 
projects ...................... 25-19 
45. Flood control work under special 
authorization .................. 25-19 
25-1 
Navigation Page

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
General Investigations Page 
46. Surveys ........................ 5-19 
47. Collection and study of basic data 25-19 
General Investigations (cont.) Page 
48 Research and development ...... 25-19 
Navigation 
1. CONSTRUCTION OF LOCKS 
AND DAMS ON OHIO RIVER 
See this heading under Ohio River Portion 
2. KANAWHA RIVER, W. VA. 
Location. River is 97 miles long, formed by 
junction of New and Gauley Rivers, a short distance 
above Kanawha Falls, W. Va., flows generally 
northwesterly and empties into Ohio River 
at Point Pleasant, W. Va. 
Previous projects. For details see pages 90-98 
of Annual Report for 1875, page 1913 of Annual 
Report of 1915, and page 1309 of Annual Report 
for 1938. 
Existing project. Three dams on Kanawha River 
with twin locks having usable dimensions of 56 
by 360 feet, and one dam on Ohio River near 
Gallipolis, Ohio, with one lock 110 by 600 feet 
and one lock 110 by 360 feet, to furnish 9-foot 
navigable depth from mouth to a point 90.57 
miles above. For authorization of existing pro 
ject see page 1152 of Annual Report for 1962. 
New work for existing project as completed cost 
$22,872,770. 
Local cooperation. None required. 
Licenses. Under licenses issued by Federal 
Power Commission, the Kanawha Valley Power 
Corp. constructed hydroelectric plants at the 
three locks and dams on Kanawha River. License 
charges under License No. 1175 for London and 
Marmet Locks and Dams are $32,000 annual fee 
and $1,312,000 cumulative collections through 
CY 1974 for each installation, and for Winfield 
Locks and Dam, License No. 1290, are $40,000 
annual charge and $3,592,000 cumulative collections 
through CY 1974. 
Terminal facilities. There are 84 terminals 
from 30 miles east of Charleston, W. Va. to the 
mouth. Terminals are constructed principally of 
steel and wood mooring piles and steel sheet pile 
mooring cells. Nineteen of these terminals have 
railroad connections. One terminal, paved warf, 
is owned by city of Charleston. Remaining terminals 
are privately owned. Principal commodities 
handled are coal, chemicals, acids, cement, 
gasoline and oil, and sand and gravel, for further 
information see Annual Report for 1962, 
page 1152. 
Operations and results during fiscal year. 
Operations and maintenance, general: Locks and 
dams were operated as required and necessary 
repairs and improvements were made thereto, 
and to appurtenant structures and grounds. 
During the fiscal year 46,152 cubic yards of material 
dredged from the lower lock approaches 
and navigation channel by both contract and 
hired labor at a cost of $107,600. Channel inspections 
were conducted periodically. 
Condition at end of fiscal year. Construction of 
project began in 1931 and was completed in 
1937. All structures are in operation and available 
depth for navigation is 9 feet from mouth of 
river to head of improvement. Above improved 
portion of river, minimum depth in channel is 
less than 1 foot. For details of locks and dams see 
page 1153 of Annual Report for 1962. (See Table 
25-B for total cost of existing project to June 
30, 1976.) 
3. PORTSMOUTH STATE PARK 
MARINA, OHIO 
Location On the Ohio River, about 7 miles 
southwest of Portsmouth, Ohio along the Ohio 
side of the river. The marina is located in the 
pool of the Captain Anthony Meldahl Locks and 
Dam. 
Existing project. Provides for a small boat harbor 
and marina with an entrance and access 
channel 1,000 feet long, 100 feet wide and 6 feet 
deep; service channel 300 feet long, 100 feet wide 
and 6 feet deep; launching and maneuvering area 
400 feet long, 150 feet wide and 6 feet deep; 1,200 
linear feet of stone revetment; and a bulkhead 
retaining wall 370 feet long. Project authorized 
by Chief of Engineers, 12 January 1970, under 
25-2

HUNTINGTON, W.VA., DISTRICT 
the provisions of Section 107 of the River and 
Harbor Act of 1960, as amended. Total estimated 
cost of the part development is $2,500,000 of 
which $475,000 is the Federal cost for the jointly 
developed boat harbor and marina. 
Local cooperation. Director of Ohio Department 
of Natural Resources, by letter July 15, 
1971, agreed to furnish the general requirements 
of local cooperation for projects constructed 
under Section 107 of the River and Harbor Act 
of 1960, as amended. 
Operation and results during fiscal year. Contract 
for construction of the jointly developed 
facility, initiated by the sponsor in December 
1973, is complete. 
Condition at end of fiscal year. Contract for 
work, awarded in late June 1973, is complete. 
4. OPEN-CHANNEL WORK, OHIO 
RIVER 
See this heading under Ohio River portion. 
5. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 25-C.
Flood Control 
6. ALUM CREEK LAKE, OHIO 
Location. Damsite is in Delaware County, Ohio, 
on Alum Creek, a tributary of Big Walnut Creek, 
26 miles above mouth of Alum Creek and 15 miles 
north of Columbus, Ohio, and 157 miles above 
mouth of Scioto River. 
Existing project. Provides for construction of a 
rolled earth-filled dam 93 feet high and 10,000 
feet long with a gate controlled spillway located 
in right abutment. Reservoir will provide a total 
storage of 134,800 acre-feet; control a drainage 
area of 123 square miles; and neccessitate relocation 
or reconstruction of 15.0 miles of highways, 
12.1 miles of power lines, 9.6 miles of telephone 
lines, two oil and gas transmission lines 
and 6 cemeteries containing 2,024 graves. Reservoir 
will be operated as a unit of coordinated 
reservoir system for protection of Columbus, 
Ohio, lower Alum Creek and Scioto and Ohio 
Valleys, generally. Project authorized for construction 
under 1962 Flood Control Act. Total 
estimated cost of new work (1975) is $49,300,000, 
which is to be appropriated and expended by the 
Government. The sponsor will reimburse the 
Government $26,075,000, exclusive of interest, 
for costs allocated to water supply. 
Local cooperation. Non-Federal interests must 
operate and maintain proposed fish and wildlife 
recreation facilities; reimburse Federal Government 
for cost of water supply feature, presently 
estimated at $26,075,000, exclusive of interest; 
and pay for operation and maintenance of water 
supply facilities, estimated to be $34,000 annually. 
The State of Ohio has expressed its intent to 
operate, maintain and further develop all recreation 
facilities. 
Operations and results during fiscal year. New 
work: Construction contracts completed during 
the fiscal year are: construction of dam, initiated 
in August 1970; reconstruction Rte 36 in the reservoir 
area, awarded by the State of Ohio, initiated 
in April 1973. Government share of the total 
cost for reconstructing the reservoir section of 
Rte 36 is $450,000; relocations of County roads 
DC21-1 Seg. 2, DC21-2, DC21-3 and BRT 77-1, 
initiated in September 1973; cemetery removal, 
Part III, initiated in January 1974; and clearing 
contract, initiated in May 1973. Contract for 
Landscape Planting at Africa and Berlin Cemeteries 
initiated Jun.74; Recreation Facilities, 
Phase I, initiated in September 1974 and is 96% 
complete; Relocation of Delaware County Roads 
DC10-1/DC97-1 (Part I), DC72-1 (Part II), BRT 
76-1 and 76-2 intitated in September 1974 and 
Engineering studies for remaining work continued. 
Acquired 34 tracts of land. 
Condition at end of fiscal year. Construction 
contracts active at end of fiscal year are: Landscape 
Planting at Africa and Berlin Cemeteries; 
Recreation Facilities, Phase I, 96% complete; 
Relocation of Delaware County Roads DC 10-1/ 
DC 97-1 (Part I), DC 72-1 (Part II), BRT 76-1 and 
76-2, 68% complete. Acquired 391 of 394 tracts of 
land required for the project. 
7. ATHENS, OHIO 
Location. In Athens County, Ohio, on Hocking 
River, about 37 miles above confluence with Ohio 
River. 
Existing project. Provides for clearing and excavating 
about 26,000 linear feet of a new channel 
for Hocking River; install culverts and flap 
valves; construct gate well, outlet and inlet structures; 
and landscaping. Project will reduce average 
annual damages at Athens by 86 percent. 
Total estimated cost of riew work is $8,180,000. 
Federal cost is $5,170,000 and non-Federal cost is 
$3,010,000 for lands and damages and utility relocations. 
Project was authorized by 1965 Flood 
Control Act (H. Doc. 287, 89th Cong.). 
25-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Responsible local interests 
must provide lands, easements, and rights-ofway; 
hold the United States free from damages; 
maintain project after completion; provide necessary 
relocations; and prevent any encroachments 
on capacities of channel within limits of 
project. All local requirements were met prior to 
initiating construction. 
Operations and results during fiscal year. New 
work: Inspections and engineering studies made 
of eroded areas of completed channel work. During 
a rise on August 30, 1974, theproject reduced 
the stage at Athens by 4.3 feet, as the river crested 
at 13.9 feet. A reduction of 4.1 feet was effected 
by the project during a subsequent rise on September 
3,1974, as the river crested at 15.9 feet. 
During the rise of February.1975, the project reduced 
the stage at Athens by 3.8 feet, as the river 
crested at 20.4 feet. The project prevented flood 
damages of an estimated $2,697,000 during the 
fiscal year. 
Condition at end of fiscal year. All work complete. 
8. BEECH FORK LAKE, W. VA. 
Location. Damsite is in Wayne County, W. Va., 
on Beech Fork Creek, A tributary of Twelvepole 
Creek, 3.7 miles above mouth of Beech Fork 
Creek and 19.6 miles above confluence of Twelvepole 
Creek and the Ohio River. 
Existing project. Provides for construction of a 
rolled earth-fill dam about 86 feet high and 1,080 
feet long; an uncontrolled spillway landward 
from left abutment of dam; and an outlet tunnel 
through left abutment of dam with control structure 
at upstream end. Reservoir will provide for 
a total storage of 37,540 acre-feet, control a drainage 
area of 78 square miles and necessitate construction 
of 5.1 miles of telephone and power 
lines, 9.2 miles of pipe lines, 2.69 miles of State 
roads, 1 school, and 41 cemeteries containing 
about 1,690 graves. Reservoir will be operated as 
a unit of coordinated reservoir system for protection 
of Lavalette, W. Va., and Twelvepole and 
Ohio Valleys, generally. Existing project was 
authorized under 1962 Flood Control Act. Estimated 
Federal cost of new work (1975) is 
$33,800,000. 
Local coopertion. None required by law. 
Operations and results during fiscal year. New 
work: Contract for construction of dam and appurtenant 
works, initiated in February 1973, is 
72 percent complete; Contract for construction of 
Highway Relocation and Bowen Recreation, 
initiated in January 1975, is 14 percent complete; 
Contract for Reservoir Clearing, initiated January 
1975, is 41 percent complete. Engineering 
studies were continued. 125 tracts of land acquired.
Condition at end of fiscal year. Contract for 
construction of the dam is 72 percent complete; 
Contract for Highway Relocation and Bowen 
Recreation is 14 percent complete; Contract for 
Reservoir Clearing is 41 percent complete. Engineering 
studies were continued. Acquired 480 of 
487 tracts of land required for the project. 
9. BLUESTONE LAKE, OHIO 
RIVER BASIN, W. VA. 
Location. Dam is on New River in Summers 
County, W. Va., about 2.5 miles above Hinton, 
W. Va., and 1 mile from confluence of New and 
Greenbrier Rivers. Reservoir is in Summers 
County, W. Va., and Giles County, Va. 
Esisting Project. A concrete gravity dam with 
a maximum height of 180 feet and an overall 
length of 2,048 feet, consisting of 790 feet of spillway 
section, 330 feet of powerhouse intake structure, 
and 928 feet of nonoverflow sections and 
abutments. Reservoir extends about 36 miles upstream 
from dam and provides for gross storage 
of 631,000 acre-feet. Estimated Federal cost of 
project is $30,158,000, which includes estimate 
for future recreational work under completed 
projects program, of which $475,000 is non-Federal. 
Existing project was authorized by Flood 
Control Acts of June 22, 1936, and June 28,1938. 
For further details see page 1453 of Annual Report 
for 1939, and pages 1173 and 1174 of Annual 
Report for 1962. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operations and maintenance, general: Reservoir 
was operated for benefit of flood control as required, 
and necessary repairs were made to 
structures and appurtenances. Facilities for accommodation 
and protection of visiting public 
were maintained in good condition. 
The lake was operated for New and Kanawha 
River control during the rise of March 1975, 
126,500 acre-feet of water were stored in the 
lake, resulting in a reduction of 3.5 feet on the 
New River at Hinton. The project was responsible 
for a reduction of 6.9 feet on the Kanawha 
River at Charleston during this rise. Project 
prevented flood damages of an estimated $1,253,- 
000 during the fiscal year. 
25-4

HUNTINGTON, W. VA., DISTRICT 
Condition at end of fiscal year. Dam is complete 
and reservoir is in operation as a unit of 
coordinated reservoir system for protection of 
New, Kanawha and Ohio Valleys, generally. 
Construction of dam was initiated in January 
1942 and completed in April 1952. Total land 
acquired was 21,931 acres in fee and flowage 
easements over 546 acres. 
10. BURNSVILLE LAKE, OHIO 
RIVER BASIN, W. VA. 
Location. Damsite is in Braxton County, W. 
Va., on Little Kanawha River 1.7 miles above 
Burnsville, W. Va., and 124.19 miles above confluence 
of Little Kanawha and Ohio Rivers. 
Existing project. Provides for construction of 
an earth embankment dam approximately 80 
feet high and 1,000 feet long with a gated spillway 
at the left abutment of dam. The outlet 
works will be an integral part of the spillway, 
comprised of 5 sluices and one low flow sluice. 
Reservoir will provide for a total storage of 65,- 
400 acre-feet, control a drainage area of 165 
aquare miles and necessitate relocation of 6.12 
miles of State roads; 6.85 of power and telephone 
lines, 2 schools and 14 cemeteries containing 
1,336 graves. Reservoir will be operated as a 
unit of coordinated reservoir system for protection 
of town of Burnsville and Little Kanawha 
and Ohio Valleys generally. Existing project 
selected for construction under general authorization 
for Ohio River Basin in 1938 Flood Control 
act. Estimated Federal cost of new work 
(1975) is $44,400,000. 
Local cooperation.None required by law. 
Operations and results during fiscal year. An 
environmental assessment contract, total cost 
$160,697, awarded in October 1972, is complete. 
Contract for construction of the dam and appurtenant 
work, initiated in August 1973, is 83 percent 
complete, cemetery relocation, Part II, 
initiated in May 1974 is complete. Contract for 
construction of Water Supply line initiated March 
1975 and is 94 percent complete. Engineering 
studies continued. 84 tracts of land acquired. 
Condition at end of fiscal year. Contract work 
on construction of the dam, initiated in August 
1973, is 83 percent complete, cemetery relocation 
Part II initiated in May 1974 is complete, Water 
Supply lines initiated in March 1975 is 94 percent 
complete. Engineering studies continued. 
Acquired 326 of 329 tracts of land required for 
the project. 
11. CHILLICOTHE, OHIO 
Location. In Ross County along the right bank 
of the Scioto River, 69 miles above the mouth. 
Existing project. Consists of 10,805 feet of earth 
levee, four gate openings and four pump stations. 
Construction of the project was authorized under 
the 1962 Flood Control Act. Total estimated cost 
for new work (1975) is $13,030,000 of which 
$10,700,000 is to be allocated and expended by 
the Government. The sponsor, in addition to contributing 
$2,330,000 in non-Federal costs, will 
reimburse the Government $260,000 for their 
share of recreational development costs. New 
Work: A contract for construction of Local Protection 
Project, Part I, was awarded in June 1975. 
Local cooperation. Responsible local interests 
must provide lands, easements, and rights-ofway; 
hold the United States free from damages; 
maintain project after completion; and provide 
necessary relocations. In addition, local interests 
fulfilled the following pre-construction requirements: 
construction of westbound lane of proposed 
U.S. Route 35-50 highway to a design grade 
3 feet above standard flood elevation; remedial 
work to U.S. Route 23 highway bridge; backfilling 
of existing gravel pits; and widening channel 
of Scioto River an additional 200 feet at low 
water elevation for a distance of 22,000 feet. 
Operations and results during fiscal year. New 
work: The initial contract, Local Protection Part 
I, was awarded in June 1975. 
Condition at end of fiscal year. Construction 
contract for Local Protection, Part I,. was awarded 
in June 1975. 
12. COAL RIVER BASIN, W. VA. 
Location. Work covered by the project is located 
in the Coal River Basin covering portions of 
Boone, Raleigh and Logan Counties, W. Va. The 
total drainage area of the basin is approximately 
899 square miles. 
Existing project. Provides for cleaning out 
approximately 41 miles of channel of Coal River 
and its tributaries. Streams vary in width from 
25 to 100 feet and depth of cleanl out varies from 
3 to 4 feet. Volume of material to be removed is 
estimated to be in excess of 580,000 cubic yards. 
Project authorized under authority of 1970 River 
and Harbor Act (P.L. 91-611, 91st Cong.). Estimated 
Federal cost of project (1975) is $2,860, 
000. Non-Federal cost is $320,000. 
Local cooperation. Responsible non-Federal 
interests must furnish necessary lands, disposal 
25-5

REPORT OF THE CHEIF OF ENGINEERS, U.S. ARMY 1975 
areas, easements and rights of ivay and hold and 
save the United States free from damages due to 
dredging operations. 
Operations and results during fiscal year. 
Phase I of General Design Memorandum (draft) 
by A/E contract was completed in December 
1974. Bids were opened in June 1975 for rental of 
equipment and operator for initial reach of profect 
(Sylvester-Whitesville). Bids were rejected 
as excessive. 
Conditions at end of fiscal year. Bids were 
opened in June 1975 for rental of equipment and 
operator for initial reach of project (Sylvester- 
Whitesville). Bids were rejected as excessive. 
13. DEER CREEK LAKE, OHIO RIVER 
BASIN, OHIO 
Location. Dam is in Pickaway County, Ohio, on 
Deer Creek, a tributary of Scioto River, 21.0 
miles above mouth of Deer Creek and 105.8 miles 
above mouth of Scioto River. 
Existing project. A rolled earth-fill dam 93 feet 
high and 3,880 feet long, with a 741-foot concrete 
gravity channel section; a gated spillway in channel 
section controlled by three 42- by -32 foot 
tainter gates; outlet works consisting of five 5-by 
5.5-foot gated sluices through concrete spillway 
section discharging into stilling basin; and an 
earth dike 15 by 4,600 feet in a saddle 3.8 miles 
southwest of dam site. Reservoir provides a total 
storage of 102,540 acre-feet and controls a drainage 
area of 278 square miles. For further project 
details see Annual Report for 1965, page 939. 
Existing project was selected for construction 
under general authorization for Ohio River Basin 
in 1938 Flood Control Act. Estimated Federal 
cost for new work is $20,280,000. 
Local cooperation. Non-Federal interests must 
operate and maintain proposed fish and wildlife 
facilities. The State of Ohio has expressed its 
intent to operate, maintain and further develop 
all recreation facilities. 
Operations and results during fiscal year. New 
work: Contract for construction of On-The-Land 
Wastewater Treatment Facilities 98 percent 
complete. This work is being accomplished under 
the completed pIrojects program. 
Operation and Maintenance, General: Reservoir 
was operated for flood control, as required, 
and necessary repairs were made to structures 
and appurtenances. The rise of February 1975 
resulted in the storage of 31,000 acre-feet of 
water in the lake. During March 1975, the project 
was operated for Deer Creek and Scioto River 
control resulting in a reduction of 0.4 feet at Higby, 
as the Scioto River crested at 13.2 feet. Project 
prevented flood damages of an estimated 
$311,000 during the fiscal year. 
Condition at end of fiscal year. All major construction 
work complete. Remaining work consists 
of completion of contract for On-The-Land 
Wastewater Treatment Facilities at Clark's 
Run camping area. Work being performed under 
completed projects program. 138 tracts of land 
required for the project have been acquired. 
14. DELAWARE LAKE, OHIO RIVER 
BASIN, OHIO 
Location. Dam is on Olentangy River about 6 
miles above and north of Delaware, Ohio, and 32 
miles above confluence of Olentangy and Scioto 
Rivers at Columbus, Ohio. Reservoir is in Delaware, 
Marion, and Morrow Counties, Ohio. 
Existing project. A rolled-earthfill dam having 
a gate controlled gravity ogee-type spillway in 
channel containing five outlet conduits. Dam is 
about 18,600 feet long, having a maximum height 
of 92 feet. Completed project provides for storage 
of 132,800 acre-feet from a tributary drainage 
area of 381 square miles. For further details see 
Annual Report for 1962, page 1160. Existing 
project was authorized by 1938 Flood Control 
Act. Federal cost of project as completed was 
$7,631,821. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control, as required, 
and necessary repairs were made to 
structures and appurtenances. During the rise 
of February 1975, 42,200 acre-feet of water were 
stored in the lake. This resulted in a reduction 
of 2.0 feet on the Scioto River at Columbus as the 
river crested at 22.4 feet. The project prevented 
an estimated $789,000 during the fiscal year. 
Condition at end of fiscal year. Dam and its 
appurtenances are complete and reservoir is in 
operation as a unit of coordinated reservoir system 
for protection of Olentangy, Scioto, and 
Ohio Valleys, generally. Construction of dam 
was started in April 1946 and completed in July 
1948. All construction operations were completed 
in October 1951. Total real estate requirements 
were completed which include acquisition of 
7,703 acres in fee and flowage easements over 
2,428 acres. 
25-6

HUNTINGTON, W. VA., DISTRICT 
15. DEWEY LAKE, OHIO 
RIVER BASIN, KY. 
Location. Dam is on John Creek, about 7 miles 
southeast of Paintsville, Ky., and 5.4 miles above 
confluence of Johns Creek and Levisa Fork of Big 
Sandy River. 
Existing project. A rolled-earthfill dam having 
a maximum height of 118 feet and a total length 
of 913 feet; controlled outlet works discharging 
through a tunnel in left abutment; and uncontrolled 
spillway discharging through a channel 
excavated in left or west abutment; and a rolledearthfill 
dike which blocks a low divide to Brandykeg 
Creek and Levisa Fork. Reservoir provides 
storage of 93,300 acre-feet, and controls a 
drainage area of 207 square miles. For further 
project details see Annual Report for 1965, page 
940. Existing project was selected for construction 
under general authorization for Ohio River 
Basin in 1938 Flood Control Act. Estimated cost 
is $9,022,000, which includes estimate for future 
recreational work under completed projects program, 
of which $470,000 is non-Federal. 
Local cooperation. None required by law. 
Operations and results during fiscal year. New 
work: Contract for construction of Recreation 
Facilities at German Bridge was awarded in late 
June 1975. Work has not been initiated. The work 
to be accomplished under the completed projects 
program. 
Operation and maintenance, general: Reservoir 
was operated for flood control, as required, 
and necessary repairs were made to structures 
and appurtenances. Facilities for accommodation 
and protection of visiting public were 
maintained in good condition. The project was 
operated for downstream control during two 
rises in March 1975. During the first rise in 
March, reductions effected by the project were 
2.1 feet at Paintsville and 1.4 feet at Louisa. Flood 
storage also occurred during the rise of April 
1975. Project prevented flood damages of an estimated 
$1,456,000 during the fiscal year. 
Condition at end offiscal year. Dam is complete 
and is being operated as a unit of coordinated 
reservoir system for protection of Levisa Fork, 
Big Sandy and Ohio Valleys, generally. Construction 
of dam was initiated in March 1946 and 
completed in July 1949. Contract for construction 
of Recreation Facilities at German Bridge was 
awarded in late June 1975. Work has not been 
initiated. Work to be performed under completed 
projects program. Total acreage involved has 
been acquired and consists of 12,437 acres in fee 
and flowage easements over 1,165 acres. 
16. DILLON LAKE, OHIO RIVER 
BASIN, OHIO 
Location. Dam is on Licking River, Ohio, 5.8 
miles above confluence of Licking and Muskingum 
Rivers at Zanesville, Ohio 
Existing project. A rolled-earthfill dam with 
a maximum height and length of 118 and 1,400 
feet, respectively; controlled-outlet works discharging 
through a 20-foot conduit in right abutment; 
an ungated 280-foot spillway adjacent to 
left abutment of dam; and two rolled earthfill 
dikes. Reservoir provides for storage of 261,110 
acre-feet and controls an area of 748 square 
miles. For further project details see Annual 
Report for 1962, page 1162. Existing project was 
selected for consideration under general authorization 
for Ohio River Basin in 1938 Flood Control 
Act. Estimate of Federal cost for new work 
is $34,518,000, which includes estimate for future 
recreational work under completed projects 
program, of which $2,150,000 is non-Federal. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control, as required, 
and necessary repairs were made to 
structures and appurtenances. During the flood 
of February 1975 the project was operated for 
downstream control. The Muskingum River 
crested at 19.4 feet at Zanesville and 11.6 feet at 
McConnelville. Reductions effected by the reservoir 
were 2.5 feet and 1.4 feet at Zanesville and 
McConnelsville, respectively. Project prevented 
flood damages of an estimated $4,879,000 during 
the fiscal year. 
Condition at end of fiscal year. Dam is complete 
and reservoir is in operation as a unit of 
coordinated reservoir system for protection of 
Zanesville, Ohio, and Muskingum and Ohio Valleys, 
generally. Construction of project was initiated 
in July 1946 with relocation of Baltimore 
and Ohio Railroad in reservoir. Total acreage 
involved has been acquired and consists of 7,797 
acres in fee and flowage easements over 5,282 
acres. 
17. EAST LYNN LAKE, OHIO RIVER 
BASIN, W. VA. 
Location. Damsite is in Wayne County, W. Va., 
on East Fork of Twelvepole Creek, 10 miles above 
mouth of East Fork and 42 miles above confluence 
of Twelvepole Creek and Ohio River. 
25-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. An earthfill dam having a 
maxium height of 113 feet, top length of 638 feet 
and top width of 32 feet; an uncontrolled spillway 
with a crest length of 230 feet near left abutment; 
and a 13-foot reinforced tunnel in right 
abutement with control structure at upstream 
end. Reservoir provides a total storage tf 82,500 
acre-feet from a drainage area of 133 square 
miles, and necessitates relocation or reconstruction 
of 13.3 miles of state roads; 15.5 miles of 
powerlines; 10.6 miles of telephone lines; 27.8 
miles of gas lines; 34 cemeteries containing approximately 
2,460 graves; and construction of 
one school building. Reservoir operated as a unit 
of coordinated reservoir system for protection of 
towns of East Lynn and Wayne, W. Va., and 
Twelvepole Creek and Ohio River Valleys, generally. 
Existing project selected for construction 
under general authorization for Ohio River Basin 
in Flood Control Act of 1938. Estimated Federal 
cost for new work (1975) is $34,400,000. 
Local cooperation. None required by law. 
Operations and results during fiscal year. New 
work: All major items of construction are complete. 
Acquired 3 easement tracts. Negotiations 
continued toward settlement with a major mineral 
owner. 
Operations and maintenance, general: Reservoir 
was operated for benefit of flood control, as 
required, and necessary repairs were made, to 
structures and appurtenances. The project was 
operated for Twelvepole Creek Control during 
two rises in March 1975. During the second rise 
in March, the project was responsible for a reduction 
of 6.6 feet at Wayne as Twelvepole Creek 
crested at 20.1 feet. The project was operated for 
downstream control during the rise of April 
1975. Project prevented flood damages of an 
estimated $1,176,000 during the fiscal year. 
Condition at end of fiscal year. All major construction 
is complete. Remaining work consists 
of: Cemetery remedial work; remaining environmental 
enhancement; and construction of additional 
recreation facilities at East Fork and Overlook 
Point; and settlement with a major mineral 
owner. One surfact tract of land of 549 tracts 
required for the project remains to be acquired. 
18. FISHTRAP LAKE, OHIO RIVER 
BASIN, KY. 
Location. Dam is on Levisa Fork in Pike County, 
Ky., about 2.6 miles above confluence of Levisa 
and Russel Forks and 103 miles above mouth 
of Levisa Fork. 
Existing project. A rockfill dam with a maximum 
height of 195 feet, an overall length of 1,100 
feet, and top width of 32 feet. An excavated spillway 
is located at left abutment and controlled by 
four 57- by 35-foot tainter gates. Reservoir provides 
for a total storage of 164,360 acre-feet and 
controls a drainage area of about 395 square 
miles. Its construction requires abandonment of 
17.7 miles of branch line of one railroad and raising 
and relocation of about 4.3 miles of track of 
another railroad. Other relocations are: 37.8 
miles of roads; 8.5 miles of telephone lines; 13.5 
miles of powerlines; 2.1 miles of gas pipelines; 
and 48 cemeteries containing about 2,300 graves. 
Reservoir will be operated as a unit of coordinated 
reservoir system for protection of Levisa 
Fork and Big Sandy River Valleys, generally, 
and to a lesser degree, Ohio River Valley. Existing 
project was selected for construction under 
general authorization for Ohio River Basin in 
1938 Flood Control Act. Estimate of cost for new 
work is $53,854,000 
Local cooperation. None required by law. 
Operations and results during fiscal year. New 
Work: All major construction work is complete. 
A contract for construction of Recreation Facilities 
and Remedial Work was initiated in June 
1974 and is 85 percent complete. Operation and 
maintenance, general: Reservoir was operated 
for benefit of flood control, as required, and necessary 
repairs were made to structures and appurtenances. 
During a rise in March 1975 the 
project was operated for Levisa Fork and Big 
Sandy River flood control, resulting in a reduction 
of 6.2 feet at Pikeville. A subsequent rise 
in March 1975 resulted in the storage of 48,000 
acre-feet of water in the lake. During this rise: 
a reduction of 8.8 feet at Pikeville was effected 
by the project as Levisa Fork crested at 30.5 feet. 
The project was operated for downstream control 
during the rise of April 1975. Project prevented 
flood damages of an estimated $5,146,000 during 
the fiscal year. 
Condition at end of fiscal year. All major work 
complete. Remaining work consists of: Remainder 
of recreational facilities and remedial work 
at the dam which was awardedTn June 1974 and 
is 85 percent complete; landscaping; and real 
estate deficiencies. Entire project 99 percent 
complete. 1,300 tracts of land required for the 
project have been acquired. 
25-8

HUNTINGTON, W. VA., DISTRICT 
19. GRAYSON LAKE, KY. 
Location. Dam is on Little Sandy River, Ky., 
48.5 miles above its confluence with Ohio River 
and 11 stream miles above town of Grayson, Ky. 
Existing project. A random earthfill dam with 
a maximum height of 120 feet and a total crest 
length of 1,460 feet; controlled outlet works discharging 
through a 14-foot diameter horseshoe 
tunnel in left abutment; and an uncontrolled 200- 
foot spillway beyond left abutment. Reservoir 
provides for total storage of 119,000 acre-feet; 
controls a drainage area of 196 square miles, and 
necessitated relocation or reconstruction of 14.9 
miles of roads, 17.6 miles of powerlines, 2.6 miles 
of telephone lines, about 0.06 mile of gaslines, 
and 47 cemeteries having about 1,200 graves. 
Reservoir will be operated as a unit of coordinated 
reservoir system for protection of Grayson, 
Ky., and Little Sandy and Ohio River Valleys 
generally. Existing project was selected for construction 
under general authorization for Ohio 
River Basin in 1960 Flood Control Act. Estimate 
of cost for new work is $20,715,400, which includes 
estimate for future recreational work 
under completed projects program, of which 
$645,000 is non-Federal. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control, as re-. 
quired, and necessary repairs were made to 
structures and appurtenances. The project was 
operated for Little Sandy River control during 
a rise in March 1975. A reduction of 13.1 feet at 
Grayson was effected by the project as the Little 
Sandy River crested at 21.4 feet. During a subsequent 
rise in March the Little Sandy River at 
Grayson crested at 21.4 feet again and the reduction 
effected by the project was 14.1 feet. 
During the rise of April 1975, the project was 
operated for downstream control. Project prevented 
flood damages of an estimated $2,013,000 
during the fiscal year. 
Condition at end of fiscal year. All major construction 
work complete. 484 tracts of land required 
for the project have been acquired. 
20. JOHN W. FLANNAGAN DAM 
AND RESERVOIR, OHIO 
RIVER BASIN, VA. 
Location. Dam is on Pound River in Dickenson 
County, Va., about 1.8 miles above confluence of 
Russel Fork and Pound River and 150 miles. 
above mouth of Big Sandy River. 
Existing project. A rockfill dam having a maximum 
height of 252 feet, top length of 970 feet, 
and top and base width of 30 and 1,030 feet, respectively. 
Outlet tunnel located near left abutment 
with control structure at upstream end. 
A spillway controlled by six tainter gates is constructed 
in a saddle about 0.3 mile upstream from 
damsite. Reservoir provides for about 145,700 
acre-feet of storage and controls about 222 square 
miles of drainage area. For further details see 
Annual Report for 1966, page 1024. Existing project 
was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. Project was modified, after construction 
began to provide water quality control 
features by adding control gates to previously 
uncontrolled spillway, thus increasing total storage 
capacity by about 39,000 acre-feet. Estimateed 
cost for new work is $22,088,000, which includes 
mate for future recreational work under 
completed projects program, of which $585,000 
is non-Federal. 
Local cooperation. None required by law. 
Operations and results during fiscal year.New 
work: All construction work complete. Operation 
and maintenance, general: Reservoir was operated 
for Flood control, as required, and necessary 
repairs were made to structures and appurtenances. 
The project was operated for Russell 
Fork, Levisa Fork, and Big Sandy River control 
during two rises in March 1975. During the second 
rise in March, Levisa Fork at Pikeville crested 
at 30.5 feet and the reduction effected by the 
project was 4.3 feet. The project was also operated 
for downstream control during the rise of 
April 1975. Project prevented flood damages of 
an estimated $2,866,000 during the fiscal year. 
Condition at end of fiscal year. All major construction 
complete. 381 tracts of land required 
for project have been acquired. 
21. KEHOE LAKE, KY. 
Location. Damsite is in Carter County, Kentucky, 
on Tygarts Creek, a tributary of Ohio 
River, 48.5 miles above mouth of Tygarts Creek 
and 1.7 miles above Kehoe, Kentucky. 
Existing project. Provides for construction 
of a rock fill dam 101 feet high and 1,265 feet 
long; and uncontrolled spillway approximately 
1,500 feet upstream of right abutment of dam; 
an upstream controlled outlet works with a tun- 
25-9

REPORT'OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
nel through left abutment.Reservoir will provide 
for a total storage of 48,048 acre-feet, control a 
drainage of 127 square miles and necessitate the 
relocation of 2.8 miles of State highways,0.2 mile 
of County roads, abandon or relocate 12.0 miles 
and replace 4.0 miles of power lines, abandon or 
relocate 7.0 miles and replace 3.2 miles of telephone 
lines, and 15 cemeteries containing approximately 
510 graves. Reservoir will be operated 
as a unit of coordinated reservior system 
for the protection of town of Kehoe and Tygarts 
and Ohio Valley, generally. Total estimated cost 
of new work (1975) is $34,900,0P0 which is to be 
appropriated and expanded by the Government. 
The sponsor will reimburse the Government 
$3,030,000 for their share of initial recreational 
development. Project was authorized by 1966 
Flood Control Act (H. Doc. 517, 89th Cong.). 
Local cooperation. Local interests must contribute 
that portion of recreation costs that exceed 
the portion permitted to be borne by the 
Federal Government under Public Law 89-72. 
Sec. 221 assurances .signed by Commonwealth 
oTKentucky and ap- proved by the Federal Gov 
ernment. 
Operations and results during fiscal year. Engineering 
studies were continued. 
Condition at end offiscal year. Preconstruction 
planning is complete. 
22 LOWER GUYANDOT RIVER 
BASIN, W. VA. 
Location. Work covered by the project is located 
in the lower Guyandot River and its tributaries. 
The project will include portions of Wyoming, 
Logan and Lincoln Counties, W. Va., below 
the R. D. Bailey Lake project. 
Existina projects. Provides for channel cleanout 
and snagging and clearing for selected streams 
in the lower Guyandot River Basin, which will 
generally be limited to removal of major mainstream 
channel restrictions and the cleanout of 
the lower reaches of tributary streams. 
Local cooperation. Responsible non-Federal 
interests shall, prior to initiation of remedial 
operations, agree in accordance with provisions 
of Sec. 221 of the 1970 Flood Control Act that 
they will furnish the necessary lands, disposal 
areas, easements and rights-of-way and hold and 
save the United States free from damages due to 
the cleanout operations. 
Operations and results during fiscal year. New 
work: In September 1974, construction of the 
R. D. Bailey cofferdam was accelerated in order 
to provide temporary flood storage to reduce 
flood stages downstream. Since the accelerated 
construction of the cofferdam would provide a 
greater degree of protection than the channel 
cleanout, it was requested and approved that 
funds appropriated for the channel cleanout be 
used toward completion of the permanent cofferdam. 
Condition at end of fiscal year. Funds appropriated 
for the channel cleanout were used toward 
the accelerated construction of the permanent 
cofferdam at the R. D. Bailey Lake Project. 
23. MARTIN, KY. 
Location. In Floyd County, Ky., on Beaver 
-Creek at confluence of Right and Left Forks, 5.5 
miles above its junction with Levisa Fork. 
Existing project.Channel improvement of 4.5 
miles of Beaver Creek from 2.3 miles above the 
mouth to junction of Right and Left Forks. Improved 
channel to have a bottom width of 75 feet 
with placement of riprap along outside of all 
curves, and channel bottoms and both sides 
through three bridges. Project will reduce stages 
of major floods at Martin about 5.7 feet. Total estimated 
cost of new work (1975) is $4,700,000. 
Federal cost is $4,390,000 and non-Federal is 
$310,000 for lands and damages and utility adjustments. 
Project authorized by 1965 Flood Control 
Act (H. Doc. 246, 89th Cong.). 
Local cooperation. Responsible local interests 
must provide necessasry lands, easements, and 
rights-of way; hold the United States free from 
damages, maintain project after completion; provide 
necessary relocations; and prevent any encroachments 
on capacities of channel within limits 
of project. By letter, October 26, 1971, the Fiscal 
Court of Floyd County, Ky., furnished an amendment 
to the resolution of assurances of local 
cooperation. 87 percent of tracts required by the 
project have been acquired by the sponsor. 
Operations and results during fiscal year. Preconstruction 
planning complete. 
Condition at end offiscal year. Preconstruction 
planning is complete. 
24. MASSILLON, OHIO 
Location. In Stark County, on Tuscarawas River, 
200 miles above mouth of Muskingum River. 
Existing project. Imporvement of channel of 
25-10

HUNTINGTON, W.VA., DISTRICT 
Tuscarawas River, together with construction of 
drainage facilities, levees, and pump stations 
consists of: 12,800 linear feet of channel rectification 
and improvements; 4,300 feet of new channel; 
two reinforced concrete presure conduits 
with a total length of 4,300 feet; 15,900 feet of 
earth levee; 200 feet of contrete wall; four pump 
stations; and three gate openings. For further 
details see Annual Report for 1962, page 1156. 
Existing project was selected for construction 
under general authorization for Ohio River Basin, 
in 1938 Flood Control Act. Project was constructed 
at a total Federal cost of $8,139,406. 
Local cooperation. None required by law. See 
Annual Report for 1962, page 1156, for details 
of local contributions for work beyond scope of 
project. 
Operations and results during fiscal year. Operation 
and maintenance, general: Routine inspections 
of improved channel were conducted 
and snagging and clearing work by hired labor 
was performed to maintain channel in a satisfactory 
condition. 
Condition at end of fiscal year. Construction of 
project began in July 1940, was completed for 
beneficial occupancy in October 1951. Drainage 
structures and appurtenances including pressure 
conduits, gate openings, and pump stations 
have been turned over to the city for maintenance 
and operations. Improved channels and levees 
maintained by the United States are in good 
condition. 
25. MILL CREEK LAKE, OHIO 
Location. Damsite is in Union and Delaware 
Counties, Ohio, on Mill Creek, a tributary of 
Scioto River, 1.5 miles above mouth of Mill Creek 
and 157 miles above mouth of Scioto River. 
Existing project. Provides for the construction 
of a rolled earthfill dam 85 feet high above 
streambed, and 11,800 feet long; a gated spillway 
controlled by three 34- by 34-foot tainter gates 
located in right abutment of dam; outlet works 
consisting of three 5- by 5-foot multi-level intakes; 
three sections of earth filled dike, 11,400 
feet long covering a total distance of 16,300 feet, 
average height of 7.3 feet; and one levee, average 
height 25.0 feet and 4,120 feet long with pump 
station and appurtenances for protection of Ostrander, 
Ohio. Reservoir will provide a total 
storage of 84,694 acre-feet; control a drainage 
area of 181 square miles; and necessitate relocation 
or reconstruction of 1.6 miles of Federal 
highways, 7.0 miles of County roads, 22.5 miles 
of power lines, 38.5 miles of telephone lines, and 
5 cemeteries containing 1,310 graves. Reservoir 
will be operated as a unit of coordinated reservior 
systems for protection of Scioto and Ohio 
River Valleys, generally, and contribute to reductions 
of flooding at industrial and population 
centers of Columbus and Chillicothe. Project 
authorized for construction under 1962 Flood 
Control Act. Estimated Federal cost of project 
(1975) is $67,000,000. 
Local cooperation. Local interests are required 
to operate and maintain fish and wildlife facilities.
The State of Ohio had previously expressed 
its intent to operate, maintain and further develop 
all recreation facilities, but by letter dated 
January 8, 1973, the Govenor of Ohio announced 
withdrawal of support for the project. 
Operations and results during fiscal year. 
Engineering studies suspended. Preconstruction 
planning completed. 
Condition at end of fiscal year. Engineering 
studies suspended due to withdrawal of state 
support. Preconstruction planning complete. The 
State of Ohio awarded a contract for reconstruction 
of State Route 36 in March 1972. The state 
was advanced $594,474.48 by the Government for 
that portion of the route to be reconstructed within 
the reservoir boundary. All of these funds 
have been expended. All remaining work on this 
project has been suspended due to withdrawal 
of support for the project by the Governor of the 
State. 
26. MUSKINGUM RIVER LAKES, OHIO 
Location. Muskingum River lies in southeastern 
Ohio and, with its tributaries, drains about 
8,000 square miles. Its headwaters rise about 25 
miles south of Lake Erie and it flows into Ohio 
River at Marietta, Ohio, 172.2 miles below Pittsburgh, 
Pa. 
Existing project. Construction, operation, and 
maintenance of 14 reservoirs and appurtenant 
works in Muskingum River Basin. It was originally 
authorized by Public Works Administration 
February 20, 1934, to include 15 reservoirs 
as set forth in an official plan prepared by the 
Corps and adopted by Muskingum Watershed 
Conservancy District of Ohio, the sponsoring 
agency. Project was operated and maintained by 
conservancy district from July 1938 to August 
1939 when it was taken over by Corps for maintenance 
and operation in accordance with provisions 
of 1939 Flood Control Act. For further 
25-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
details see page 1157, Annual Report for 1962. 
Estimated cost of new work is $44,353,000, which 
includes estimate for future recreational work 
under the completed projects program, of which 
$1,625,000 is non-Federal. See table on page 1159 
of the Annual Report for 1962, which gives the 
principal features of the 14 reservoirs. 
Local cooperation. Fully complied with. For 
details see Annual Report for 1942, page 1257. 
Operations and results during fiscal year. New 
work: Planning and construction of recreational 
facilities was continued under the completed projects 
program. Operations and Maintenance, 
General: Contract for construction of Brewster 
Levee, Beach City Lake, initiated in June 1973, 
is 77% complete. Reservoir was operated for benefit 
of flood control, as required, and necessary repairs 
were made to structures and appurtenances. 
The reservoirs were operated to reduce flooding 
downstream during the rise of February 
1975. River crests and reductions effected by the 
reservoirs were: Coshocton, 11.2 and 10.1 feet; 
Dresden, 18.1 and 11.1 feet; Zanesville, 19.4 and 
10.1 feet; McConnelsville, 11.6 and 4.6 feet. During 
the fiscal year Muskingum River Reservoir 
System prevented flood damages estimated at 
$77,522,000. 
Condition at end of fiscal year. Construction of 
project, initiated in January 1935, was completed 
in November 1938. All construction contracts, 
initiated in fiscal year 1974 and 1975 are complete 
except the Brewster Levee contract, which 
is 77 percent complete.. Remaining construction 
work consists of planning and construction of recreational 
facilities at Atwood Lake, the cost of 
which is to be cost-shared by the State of Ohio. 
27. NEWARK, OHIO 
Location. In Licking County at junction of 
North and South Forks of Licking River, 29 miles 
above its confluence with Muskingum River at 
Zanesville, Ohio. 
Existing project. Provides for 31,500 linear feet 
of channel improvements of Licking River, North 
and South Forks of Licking River, and Raccoon 
Creek; and pump station for disposal of interior 
drainage. Project provides protection for city of 
Newark against floods 22 percent greater than 
that of 1913 (one of the greatest of record) with a 
3-foot freeboard. Existing project was selected 
for construction under general authorization for 
Ohio River Basin in 1938 Flood Control Act. Federal 
cost of completed project is $845,916. The existing 
Newark Local Protection Project was modified 
by the Flood Control Act of 1968- HD 337/ 
90/2 - to include improvement of the interior 
drainage facilities, construction of the Log Pond 
Run diversion, and modification of the North 
Fork Channel. The estimated final cost of this 
part of the project, less the North and South 
Forks of Licking River, (1975) is $3,290,000, of 
which $2,770,000 is Federal. 
Local cooperation. For the existing project has 
been fully complied with. Cost for all requirements 
under terms of the existing project authorization 
was $21,000. 
Operations and results during fiscal year. New 
work: Preconstruction planning is 75 percent 
complete. The General Design Memorandum, 
completed and submitted in July 1972, was returned 
for revision due to environmental impact 
relationship between the North Fork channel 
portion of the project and Utica Lake project. 
Supplement No. 1 to the GDM was submitted in 
November 1975. An environmental assessment 
and analysis contract, awarded in late June 1973 
for Newark and Utica Lake projects, is complete. 
Condition at end offiscal year. Existing project 
was initiated in July 1940 and completed for beneficial 
occpancy in November 1941, and pump 
facilities and levees turned over to the city for 
maintenance and operation. Preconstruction 
planning, for modified project, is 75 percent complete. 
Supplement No. 1 to the GDM, for Log 
Pond Run Diversion,was submitted in November 
1975, 
28. NORTH BRANCH KOKOSING 
RIVER LAKE, OHIO 
Location. Damsite is in Knox County, Ohio, on 
North Branch of Kokosing River, about 9.1 miles 
above confluence of Kokosing and North Branch 
Rivers, and 2.2 miles northwest of Fredericktown, 
Ohio. 
Existing project. A rolled earthfill dam, 70 feet 
high and 1,400 feet long with an uncontrolled 
spillway adjacent to right abutment. Reservoir 
provides for a total storage of 14,885 acre-feet, 
controls a drainage area of 44.5 square miles,and 
necessitated relocation of 5.05 miles of telephone 
and power lines and 2.65 miles of county roads. 
Reservoir operated for protection of Fredericktown 
and Mt. Vernon, Ohio, valleys of North 
Branch and Kokosing Rivers and to a lesser degree, 
Muskingum and Ohio River Valleys. Existing 
project was selected for construction under 
25-12

HUNTINGTON, W.VA., DISTRICT 
general authorization for Ohio River Basin in 
1962 Flood Control Act. Estimated Federal cost 
of new work is $6,545,300. 
Local cooperation. None required by law. 
Operations and results during fiscal year. New 
work: All major construction is complete. 
Condition at end of fiscal year. All major construction 
work is complete. 56 tracts of land required 
for the project have been acquired. Entire 
project essentially complete. 
29. NORTH FORK OF POUND 
RIVER LAKE, VA. 
Location. Dam is in Wise County, Va., on North 
Fork of Pound River about 1.1 miles upstream 
from confluence of North and South Forks which 
join to form Pound River. 
Existing project. A rockfill dam, with height of 
130 feet, crest length of 600 feet and crest width of 
32 feet; an uncontrolled spillway in a saddle about 
1,000 feet upstr;eam from dam; and an outlet tunnel 
in right abutment with control structure at 
upstream end. Reservoir provides for about 11, 
300 acre-feet of storage, and controls a drainage 
area of 17.6 square miles. For further details see 
Annual Report for 1965, page 951. Existing project 
was authorized under 1960 Flood Control 
Act. Estimated Federal cost of project is $6,187, 
000. 
Local cooperation. None required by law. 
Operations and results during fiscal year. Construction 
of utility and operations building, awarded 
June 1973, is complete. The government 
contributed $55,000 toward the construction of 
recreational facilities at one site by the Wise 
County, Va., Board of Supervisors. The government's 
part of this work is complete. Reservoir 
was operated for flood control, as required, and 
necessary repairs were made to structures and 
appurtenances. The project was operated to prevent 
downstream flooding during two rises in 
March 1975. During the rise of March 1975 a reduction 
of 3.8 feet was effected at Pound. Project 
prevented an estimated $37,000 during the fiscal 
year. 
Condition at end offiscal year. Construction of 
the project, initiated March 1963, is essentially 
complete. 128 tracts of land required for the project 
have been acquired. 
30. OHIO RIVER BASIN 
(HUNTINGTON DISTRICT) 
Location. Works covered by this project are a 
series of levees, floodwalls, channel improvements, 
and dams and lakes in Ohio River Basin 
within Huntington District. 
Existing project. Individual projects considered 
in comprehensive plan within Huntington 
District. (See Table 25-D on local protection projects; 
Table 25-E on dams and lakes; and Table 
25-F on authorizing legislation.) 
Operations and results during fiscal year. 
None. Completed local protection projects, operated 
and maintained by local interests, other than 
those for which individual reports have been included, 
prevented flood damages of an estimated 
aggregate total of $1,136,000 during fiscal year. 
Condition at end of fiscal year. Preliminary 
surveys and plans are complete for a number of 
projects included in comprehensive plan. Status 
of projects selected for construction under this 
authorization is in individual reports. (See Table 
25-G on project costs to June 30, 1975.) 
31. PAINT CREEK LAKE, OHIO RIVER 
BASIN, OHIO 
Location. Damsite is in Ross County, Ohio, on 
Paint Creek, a tributary of Scioto River, 37 miles 
above mouth of Paint Creek and 100 miles above 
mouth of Scioto River. 
Existion projects. A rock and random-fill dam 
with maximum height above streambed of 118 
feet and 700 feet long; a gate controlled spillway 
191 feet wide, 1,000 feet from right abutment; an 
outlet tunnel in right abutment with control 
structure at upstream end; and one random rockfill 
dike at right abutment of spillway, 1,400 feet 
long and 70 feet high. Reservoir provides storage 
of 145,000 acre-feet and control a drainage area 
of 573 square miles. For further details, see Annual 
Report for 1965, page 955. Reservoir is operated 
as a unit of coordinated reservoir system for 
protection of Chillicothe, Ohio, Paint Creek Basin 
and Scioto and Ohio Valleys, generally. The project 
was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. Estimated Federal cost of project 
(1975) is $26,700,000. 
Local cooperation. Local interests are required 
to operate and maintain fish and wildlife facilities. 
The State of Ohio expressed its intent to operate, 
maintain and further develop all recreation 
facilities but in fiscal year 1975 indicated 
that a lack of funds precluded an agreement at 
this time to operate the recreational areas. 
Operations and results during fiscal year. New 
25-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
work: Contract for construction of dam,dikes, 
spillway, access road and Deer Park recreational 
facilities, awarded April 1970, advanced to completion. 
Contracts for construction of recreational 
facilities at Rattlesnake Creek site, initiated 
November 1971 and at Taylor Road site, initiated 
August 1972, are complete. Contract for reservoir 
clearing, initiated November 1972, is complete. 
Contract for municipal remedial work at 
Greenfield, Ohio, initiated January 1973, is complete. 
An environmental assessment contract, 
awarded July 1972, is complete. A contract with 
Detroit, Toledo and Ironton Railroad Company 
for remedial work to their facilities to accomodate 
the project was awarded June 1972. Work 
performed by the company, at an estimated cost 
of $220,000, is complete. Contract for Buildings, 
Grounds,, and Utilities and Recreation Facilities 
was initiated in August 1974 and is 56 percent 
complete. 
Operation and Maintenance, General: During 
the rise of February 1975 the project was operated 
for Paint Creek and Scioto River control. 
Paint Creek at Bourneville crested at 9.9 feet as 
the project effected a reduction of 6.2 feet. The 
project was operated for downstream control 
during the rise of March 1975. Project prevented 
damages of an estimated $179,000 during the fiscal 
year. 
Condition at end of fiscal year. Contracts for 
construction of dam and appurtenances, relocation 
of DT&I Railroad Company facilities, by the 
company, environment assesssment, construction 
of recreational facilities at Rattlesnake 
Creek and Taylor Road sites, clearing, municipal 
remedial work at Greenfield, Ohio, are complete. 
Contract for construction of Buildings, Grounds, 
Utilities and recreational facilities was initiated 
in August 1974 and is 56 percent complete. 242 of 
257 tracts of land required for the project have 
been acquired. 
32. PAINTSVILLE LAKE, KY. 
Location. Damsite is in Johnson County, Ky., on 
Paint Creek, a tributary of Levisa Fork of Big 
Sandy River, 8.0 miles above mouth of Paint 
Creek, about 4.0 miles west of Paintsville, Ky. 
Existing project. Provides for construction of a 
rockfiUl dam with maximum height of 153 feet 
above streambed and crest length of 1,560 feet; an 
uncontrqlled spillway about 1,000 feet southwest 
of right abutment; and outlet works, consisting of 
a 10-foot diameter tunnel in right abutment with 
control structure at upstream end. Reservoir will 
provide a total storage of 76,462 acre-feet, control 
a drainage area of 92.5 square miles and neccessitate 
relocation or reconstruction of 6.9 miles of 
highways, 5.0 miles of powerlines, 7.0 miles of 
telephone lines, and 99 cemeteries containing 
1,800 graves. Reservoir will be operated as a unit 
of coordinated reservoir system for protection of 
town of Paintsville, lower Paint Creek Valley and 
Levisa Fork, Big Sandy and Ohio Valleys, generally. 
Total estimated cost for new work (1975) is 
$38,200,000 which is to be appropriated and expended 
by the Government. The sponsor will reimburse 
the Government $1,613,000 for their 
share of initial recreational development. Project 
was authorized by 1965 Flood Control Act (H. 
Doc. 246, 89th Cong.). 
Local cooperation. Local interests must contribute 
50 percent of recreation costs under current 
policy Public Law 89-72. 
Operations and results during fiscal year. Construction 
of project initiated with award of contract 
for cemetery removal, Part I, June 1973. 
Work advanced to completion. Contract for construction 
of access-bypass road awarded June 
1973. Work initiated in July 1973 is 80 percent 
complete. Environmental analysis contract 
awarded January 1973, is complete. Engineering 
studies continued. 52 tracts of land acquired. 
Condition at end of fiscal year. Contract for 
cemetery removal, Part I, is complete and contract 
for construction of access-bypass road is 80 
percent complete. Environmental assessment 
contract is complete. 113 of 291 tracts of land required 
for the project have been acquired. 
33. PANTHER CREEK LAKE, W. VA. 
Location. Damsite is in McDowell County, 
West Virginia, on Panther Creek, a tributary of 
Tug Fork of the Big Sandy River, approximately 
6.1 miles above the mouth of Panther Creek. 
Existing project. Provides for construction of a 
rock fill dam 200 feet high and 900 feet long; an 
uncontrolled spillway adjacent to right abutment; 
and an outlet tunnel in right abutment 
with control structure at upstream end. Reservoir 
will provide for a total storage of 16,880 acrefeet, 
control a drainage area of 23.6 square miles 
and necessitate the relocation of 3.4 miles of State 
secondary roads. The reservoir will be operated 
to give appreciable flood protection to the Matewan-
Williamson-Kermit area along Tug Fork; 
decrease the possibility of overtopping of the par- 
25-14

HUNTINGTON, W. VA., DISTRICT 
tially protected local protection project at Williamson, 
West Virginia; and provide flood protection 
for Tug Fork, Big Sandy and Ohio Valleys, 
generally. Total estimated cost of new work 
(1975) is $27,400,000, which is to be appropriated 
and expended by the Federal Government. The 
sponsor will reimburse the Government $795,000 
for their share of initial recreational development. 
Project was authorized by 1965 Flood Control 
Act (H. Doc. 246, 89th Cong.). 
Local cooperation. Local interests must contribute 
50 percent of recreation costs under current 
policy Public Law 89-72. 
Operations and results during fiscal year. 
Engineering studies continued. 
Condition at end of fiscal year. Engineering 
studies continued. 
34. R. D. BAILEY LAKE, W.Va. 
Location. Damsite is in Wyoming County, 
W. Va., on Guyandot River about 108 miles above 
confluence with Ohio River, and about 1.3 miles 
east of Justice, W. Va. 
Existing project. Provides for construction of a 
rolled rockfill dam with maximum height of 305 
feet and length of 1,330 feet; a 400-foot crest uncontrolled 
spillway in a saddle in right abutment 
and outlet works comprised of an 18-foot-diameter 
circular tunnel in left abutment. Reservoir 
will provide a total storage of 203,700 acre-feet; 
control a drainage area of 540 square miles; and 
necessitate relocation or reconstruction of 25.3 
miles of railroad track; 14.0 miles of State highways; 
60 cemeteries containing 1,590 graves; 
12.42 miles of powerlines with one substation; 
9.86 miles of telephone lines; 4 schools; and relocation 
and adjustment to oil and gas lines and 
facilities of 5 oil and gas companies. Reservoir 
will be operated as a unit of coordinated reservoir 
system for protection of Logan, W. Va., and Guyandot 
and Ohio River Valleys, generally. Existing 
project selected for construction under general 
authorization for Ohio River Basin in 1962 
Flood Control Act. Estimated Federal cost for 
new work (1975) is $148,000,000. 
Local cooperation. None required by law. 
Operations and results during fiscal year. Construction 
of project was initiated in June 1967 
with the award of first phase of railroad relocation. 
All railroad relocations and affected highway 
relocation work was contracted by the N&W 
Railroad Company and status of work is as follows: 
Segment 3, awarded in April 1968 and Segments 
4, 5 and 6, awarded in September 1968, 
were completed during the fiscal year and Segments 
7 thru 12 are essentially complete, contract 
for track and signal work, awarded in July 1973, 
is complete. Contracts by the Government: Contract 
for experimental test excavation of spillway 
and test fills, awarded in February 1973, is complete; 
contract for construction of dam and spillway, 
awarded in November 1973, is 47 percent 
complete; Environmental Analysis contract, awarded 
in June 1973, is complete; and contract 
for construction of outlet works, abutment excavation 
and roadwork, awarded in April 1972, is 
92 percent complete. Contract for Wyoming 
County school relocation work, awarded in February 
1973 by the Wyoming County Board of Education, 
is 98 percent complete. Engineering 
studies for remaining work continued. 66 tracts 
of land acquired. 
Condition at end of fiscal year. All railroad relocation 
work is essentially complete. The railroad 
company diverted traffic over the relocated 
line June 29, 1974. Contract for experimental test 
excavation of spillway and t est fills, initiated in 
March 1973, is complete; construction of outlet 
works, initiated in May 1972, is 92 percent complete; 
construction of dam and spillway, initiated 
in January 1974, is 47 percent complete and environmental 
analysis contract, initiated in June 
1973, is complete. Relocation of Wyoming County 
schools, awarded in February 1973, is 98 percent 
complete. 1,433 of 1,562 tracts of land required by 
the project have been acquired. 
35. ROSEVILLE, OHIO 
Location. In Muskingum and Perry Counties, 
Ohio, on Moxahala Creek, about 6 miles above its 
confluence with Jonathan Creek, a tributary of 
Muskingum River. 
Existing project. Protection of Roseville by 
channel rectification and levee construction. Provides 
7,290 feet of channel improvement; 6,400 
feet of levee and railroad embankment enlargement; 
and necessary appurtenances for disposal 
of interior drainage. Project was selected for construction 
under general authorization for Ohio 
River Basin, in 1938 Flood Control Act. Federal 
cost of project as completed is $910,785. 
Local cooperation. Fully complied with. Total 
cost of all requirements under terms of project 
authorization was $62,000 (1961). 
Operations and results during fiscal year. Op- 
25-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
eration and maintenance, general: Routine inspections 
of improved protion of project were conducted. 
Condition at end of fiscal year. Construction 
of project, initiated August 1959, is complete. A 
minor amount of real estate audit work remains 
to be completed. 
36. SALT CREEK LAKE, OHIO 
Location. Damsite is in Ross County, Ohio, on 
Salt Creek, a tributary of Scioto River, 15 miles 
above mouth of Salt Creek, and 12 miles southeast 
of Chillicothe, Ohio. 
Existing project. Plan provides for construction 
of a rolled earthfill dam, 96 feet high and 1,490 
feet long with an uncontrolled spillway in a saddle 
near left abutment, and an intake structure 
with three gated sluices 5 by 9 feet, discharging 
through a 12.5-foot diameter conduit into a stilling 
basin. Reservoir will provide for a total storage 
of 114,000 acre-feet; control a drainage area 
of 285 square miles and necessitate relocation of 
6.8 miles of State roads, 7.1 miles of county roads, 
and three cemeteries. Reservoir will be operated 
as a unit of coordinated reservoir system for protection 
of Salt Creek Valley and Scioto and Ohio 
River Valleys, generally. Project authorized by 
1962 Flood Control Act. Estimated Federal cost 
for new work, (1975) is $46,100,000. 
Local cooperation. Project authorization provides 
that non-Federal interests operate and 
maintain proposed fish and wildlife recreation 
facilities. The State of Ohio initially expressed its 
intent to operate, maintain and further develop 
all recreation facilities, but has temporarily 
withdrawn their support from this project pending 
a review of additional environmental information. 
Operations and results during fiscal year. Engineering 
studies continued. An environmental 
assessment contract awarded September 1972, is 
complete. 
Condition at end offiscal year. Preconstruction 
planning is complete. Contract for environmental 
assessment is complete. 
37. SUMMERSVILLE LAKE, OHIO 
RIVER BASIN, W. VA. 
Location. Dam is on Gauley River at Ruckers 
Bend, Nicholas County, W. Va., about 34.5 miles 
above confluence of Gauley and New Rivers at 
Gauley Gridge, W. Va. 
Existing project. A rockfill dam having a maximum 
height of 357 feet, top length of 2,280 feet 
and top and base width of 40 and 1,400 feet, respectively; 
and outlet tunnel in right abutment 
with control structure at downstream end; an uncontrolled 
spillway, with a crest length of 1,250 
feet; 3,500 feet west of right abutment in low 
point in rim of reservoir; and two earthfill dikes 
which prevent diversion of water into Meadow 
Creek Valley. Reservoir provides for about 
413,800 acre-feet of storage and controls a drainage 
of 803 square miles. For further details see 
Annual Report for 1965 page 957. Existing pro-' 
ject was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood 
Control Act. Estimated cost for new work is 
$48,080,000. 
Local coopertion. None required by law. 
Operations and results during fiscasl year. Operations 
and maintenance, general: Reservoir 
was operated for flood control, as required, and 
necessary repairs were made to structures and 
appurtenances. The project was operated for 
Gauley and Kanawha River control during the 
rise of March 1975. The Kanawha River at 
Charleston crested at 20.6 feet and the reduction 
effected by the project was 1.8 feet. 
Condition at end of fiscal year. All construction 
work, with the exception of future recreation 
work, is complete. Remaining work will be accomplished 
under the completed projects program, 
cost shared by the State of West Virginia. 
414 tracts of land required for the project have 
been acquired. 
38. SUTTON LAKE, OHIO RIVER 
BASIN, W. VA. 
Location. Dam is on Elk River, W. Va., 1 mile 
above town of Sutton, W. Va., and about 101 miles 
above mouth of Elk River. 
Existing project. A concrete gravity dam having 
a maximum height of 220 feet; and an overall 
length of 1,178 feet, consisting of 280 feet of spillway 
section and 898 feet of nonoverflow sections 
and abutments. Reservoir provides for storage of 
265,300 acre-feet and controls a drainage area of 
537 square miles. Existing project was selected 
for construction under generael authorization for 
Ohio River Basin in 1938 Flood Conitrol Act. For 
further details, see page 1166, Annual Report for 
1962. Estimated Federal cost of new work including 
remaining recreational work prograinmed 
for future years under completed projects pro- 
25-16

HUNTINGTON, W.VA., DISTRICT 
gram is $36,837,000. 
Local cooperation. None required by law. 
Under terms of an existing agreement, Baltimore 
& Ohio Railroad Co. paid $62,800 toward 
relocation for a modified slope and other betterments. 
Operations and results during fiscal year. New 
work: Planning for construction of recreation 
facilities under completed projects program was 
continued. Contract for upgrading recreational 
facilities, awarded February 1973, is complete. 
Operations and maintenance, general: Reservoir 
was operated for flood control, as required, and 
necessary repairs were made to structures and 
appurtenances. The rise of March 1975 resulted 
in the storage of 12,700 acre-feet of water in the 
lake. The Kanawha River at Charleston crested 
at 20.6 feet. The reduction effected by the project 
was 0.6 foot. 
Condition at end of fiscal year. Construction of 
project, initiated in October 1949, and dam operation 
effected February 1960. All construction 
complete except planning and construction of 
recreation facilities under completed projects 
program. Contract for upgrading existing recreatioal 
facilities is complete. 606 tracts of land 
required for the project have been acquired. 
39. TOM JENKINS RESERVOIR, 
OHIO RIVER BASIN, OHIO 
Location. Dam is on East Branch of Sunday 
Creek, a tributary of Hocking River, Ohio, about 
3 miles north of village of Glouster and 57.2 miles 
above mouth of Hocking River. 
Existing project. A rolled-earthfill dam having 
a maximum height of 84 feet and a total length of 
944 feet, controlled outlet works discharging 
through a tunnel in left abutment; and an uncontrolled 
spillway in ridge running south from 
damsite. Existing project was authorized under 
1944 Flood Control Act. For further details see 
pages 1164 and 1165 in Annual Report for 1962. 
Federal cost of completed work was $2,086,500. 
Local cooperation. For details see page 1165, 
Annual Report for 1962. In fiscal year 1964 
$64,660 contributed funds was received from 
State of Ohio. 
Operations and results during fiscal year. Operation 
and maintenance, general: Reservoir was 
operated for flood control, as required, and necessary 
repairs were made to structures and appurtenances. 
During The rise of February 1975, 
a reduction of 0.9 feet was effcted by the reservoir 
as the Hocking River crested at 20.4 feet. Project 
prevented flood damages of an estimated $574, 
000 during the fiscal year. 
Condtion at end of fiscal year. Construction of 
project was initiated in March 1948 and completed 
in February 1950. Reservoir provides substantial 
protection to Sunday Creek Valley as 
well as serving as a unit of coordinated reservoir 
system for protection of Hocking and Ohio Valleys. 
Reservoir also provided an assured source of 
water supply to villages, industries and coal mining 
operations in Sunday Creek Valley. 
40. TUG FORK VALLEY, KY., 
VA., AND W. VA. 
Location. Work covered by the project is located 
in the Tug Fork Basin. The Tug Fork and 
Levisa Forks form the Big Sandy River at Louisa, 
Kentucky. 
Existing project. Study would evaluate the potential 
for providing all communities in the Tug 
Fork Valley with comprehensive flood protection 
by a combination of local flood protection works 
and residental flood proofing. Tug Fork Basin 
covers an area of 1,555 square miles. Project authorized 
by Water Resources Development Act of 
1974 and is limited to the preparation of a Phase I 
General Design Memorandum. Estimated Federal 
cost of new work (1974) is $38,400,000. 
Local cooperation. Local interests will be advised 
of the assurance requirements, under Section 
221 P.L. 91-611, at the time of the formulation 
of specific projects. 
Operations and results during fiscal year. The 
Plan of Study was completed in April 1975. Preconstruction 
planning continues. 
Conditions at end of fiscal year. The Plan of 
Study was completed in April 1975. Preconstruction 
planning continues. 
41. UTICA LAKE, OHIO 
Location. Damsite is on North Fork of Licking 
River in Knox County, Ohio, 18.6 miles above the 
mouth of North Fork and 47.7 miles above the 
mouth of Licking. 
Existing project. Provides for construction of a 
rolled earth-fill dam having a maximum height 
of 73 feet, crest length of 4,880 feet and top width 
32 feet; an uncontrolled, spillway in right abutment; 
and outlet works consisting of a dry type 
25-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
intake structure controlled by multiple level gate 
openings. Reservoir will provide for a total storage 
of 82,000 acre-feet from a drainage area of 
113.8 square miles and will necessitate the construction 
or relocation of 4.8 miles of railroads; 
6 miles of county and State roads; 0.9 mile of gas 
lines and one compressor station; 10.1 miles of 
power lines; 17.6 miles of telephone lines; and 2 
cemeteries containing approximately 450 graves 
The reservoir, with existing Newark, Ohio, local 
protection project and proposed improvements 
thereto, will serve to further protect the city of 
Newark from severe and frequent flooding. The 
reservoir also will be operated as a unit of a coordinated 
reservoir system for the protection of 
North Fork of Licking, Licking, Muskingum and 
Ohio Valleys generally. Existing project selected 
for construction under 1968 Flood Control Act. 
Total estimated cost of new work (1975) is 
$62,500,000 which is to be appropriated and expended 
by the Government. The Sponsor will reimburse 
the Government $17,250,000 exclusive 
of interest, for costs allocated for water supply 
and $2,750,000 for their share of initial recreational 
development. 
Local cooperation. Project requires that non- 
Federal interests operate and maintain the proposed 
recreation and fish and wildlife facilities at 
an average annual cost of $136,000; pay for operation 
and maintenance of water supply portion 
of project ($9,600); reimburse the Federal Government 
for cost of water supply facilities, currently 
estimated at $17,250,000; and reimburse 
the Federal Government for one-half the separable 
costs allocated to recreation and fish and 
wildlife development, presently estimated to be 
$2,750,000 initially and $4,955,000 ultimately. 
In a press release dated 7 March 1972, the State of 
Ohio announced temporary withholding of final 
support of this and certain other Ohio projects 
pending adoption of flood plain zoning regulations 
by benefited downstream communities. The 
State by letter of 8 January 1973 also indicated 
that State support was being withheld pending 
completion of the environmental impact statement. 
As a result of the above, preparation of the 
environmental assessment is the only significant 
activity underway. 
Operations and results during fiscal year. Preconstruction 
planning continued. An environmental 
assessment and analysis contract, awarded 
in late June 1973, is 85 percent complete. 
Condition at end of fiscal year. Engineering 
studies continued. Preconstruction planning is 70 
percent complete. Environmental assessment 
and analysis contract is 85 percent complete. 
42. YATESVILLE LAKE, KY. 
Location. Damsite is in Lawrence County, Ky., 
on Blaine Creek, a tributary of Big Sandy River, 
about 5 miles west of Louisa, Ky., and 18.5 miles 
above mouth of Blaine Creek. 
Existing project. Provides for construction of 
an earthfill dam with maximum height of 104 
feet above streambed and crest length of 770 feet; 
an uncontrolled spillway located approximately 
one-half mile east of right abutment; and outlet 
works consisting of a 13-foot diameter tunnel 
through left abutment of dam with control structure 
at upstream end. Reservoir will provide a 
total storage of 86,951 acre-feet, control a drainage 
area of 208 square miles and necessitate relocation 
or reconstrucstion of 5.97 miles of State 
and 3.9 miles of County highways, abandon or 
relocate 36.0 miles and replace 15.0 miles of 
power lines, abandon or relocate 28.0 miles and 
replace 15.0 miles of telephone lines, 93 cemeteries 
(1,346 graves) and abandon 2 one-room 
schools. Reservoir will be operated as a unit of 
coordinated reservoir system for protection of 
town of Yatesville, lower Blaine Creek Valley 
and Big Sandy and Ohio Valleys, generally. Total 
estimated cost for new work (1975) is $48,600,000 
which is to be allocated and expended by the 
Government. The sponsor will reimburse the 
Government $1,295,000 for their share of initial 
recreational development. Project was authorized 
by 1965 Flood Control Act (H. Doc. 246, 89th 
Cong.) 
Local cooperation. Local interests must contribute 
that portion of recreation costs that exceed 
that portion permitted to be borne by the 
Federal Government under Public Law 89-72. 
Operations and results during fiscal year. Construction 
of the project initiated during fiscal 
year 1974 with award of a contract for construction 
of an access road. Contract awarded January 
1974 and is complete. Environmental Analysis 
contract, awarded in January 1973, is complete. 
16 tracts of land acquired. 
Condition at end of fiscal year. Construction 
of access road, initiated in March 1974, is complete. 
Environmental Analysis contract is complete. 
69 of 499 tracts required for the project 
have been acquired. 
25-18

HUNTINGTON, W.VA., DISTRICT 
43. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to furnish assurances 
that they will maintain and operate certain 
local protection projects after completion in 
accordance with regulations prescribed by Secretary 
of the Army. District Engineers are responsible 
for administration of these regulations 
within their respective districts. Maintenance 
inspections were made during fiscal year of completed 
units of projects transferred to local interests 
for maintenance and operation. Local interests 
were advised, as necessary, of measures required 
to maintain those projects in accordance 
with standards prescribed by regulations. Fiscal 
year cost was $120,251. Total cost to June 30, 
1975, was $525,944. (See Table 25-H on inspection 
of flood control projects.) 
44. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 25-I. 
45. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
For flood control activities pursuant to section 
205, Public Law 853, 80th Congess, as amended 
(Preauthorization). 
See Table 25-J. 
For snagging and clearing navigable streams 
and tributaries in interest of flood control (sec. 
208, 1954 Flood Control Act, Public Law 780, 
83rd Cong.). 
See Table 25-J. 
Flood control and coastal emergencies activities 
Public Law 99, 84th Cong., and antecedent legislation. 
Fiscal year costs were $20,038 for advance 
preparation. 
General Investigations 
46. SURVEYS 
Fiscal year costs were $871,485, of which $621, 
400 was for flood control studies, $196,775 for 
comprehensive basin studies, $3,003 for coordination 
studies and $50,307 for review of completed 
projects. 
47. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $294,782. Nine flood 
plain studies: Ohio River, Mason County, Kentucky; 
Ohio River, Bracken County, Kentucky; 
Ohio River, Lewis County, Kentucky; Ohio River, 
Washington County, Ohio; Ohio River, Meigs 
County, Ohio; Ohio River, Pleasants County, West 
Virginia; Ohio River, Tyler County, West Virginia; 
Ohio River, Boyd County, Kentucky; and 
Ohio River, Gallia County, Ohio, were completed 
during the fiscal year. 
48. RESEARCH AND 
DEVELOPMENT 
No funds were expended during the fiscal year 
for hydrologic studies. 
25-19

TABLE 25-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
Funding 
See 
Section 
in Text Project 
2. Kanawha River, 
W. Va. 
3. Portsmouth State 
Park Marina, Ohio 
6. Alum Creek Lake, 
Ohio 
7. Athens, Ohio 
8. Beech Fork Lake, 
W. Va. 
9. Bluestone Lake, 
Ohio River Basin, 
W. Va. 
10. Burnsville Lake, 
Ohio River Basin, 
W. Va. 
11. Chillicothe, Ohio 
12. Coal River Basin, 
W. Va. 
13. Deer Creek Lake, 
Ohio River Basin, 
Ohio 
14. Delaware Lake, 
Ohio River Basin, 
Ohio 
15. Dewey Lake, 
Ohio River Basin, 
Kentucky 
16. Dillon Lake, Ohio 
River Basin, Ohio 
17. East Lynn Lake, 
Ohio River Basin, 
W. Va. 
18. Fishtrap Lake, 
Ohio River Basin, 
Ky. 
FY 72 
Totals to 
FY 73 FY 74 FY 75 30 June 1975 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
545,821 
372,358 
293,674 
5,338 
405,593 
618,118 
670,400 
21,980 
181,270 
371,118 
370,920 
100,000 
211,998 
550,494 
521,680 
53,953,60727 
53,881,53228 
2,357,204 
2,296,88129 
25-20 
27, 167,3821.2 
27,167,382 
* 1,674,175 1,365,260 1,380,087 1,870,068 27,154,5973 
1,458,536 1,645,583 1,349,730 1,783,812 27,025,4023, 4 
130,3945 
130,3945 
39,000 200,000 200,000 0 471,083 
529 4,553 307,085 117,965 461,499 
11,604,600 13,800,000 3,156,000 3,860,000 39,700,963 
11,791,775 8,888,480 6,963,348 4,761,369 38,988,0396 
55,023 122,138 177,161 
54,007 122,167 176,1747 
35,000 10,000 5,170,0008 
551,292 39,978 1,118 1,157 5,167,3039 
1,286,000 4,100,000 4,777,500 4,925,000 19,663,500 
1,410,296 3,302,501 4,978,501 5,278,173 19,255,02310 
17,453 150,000 29,357,94511 
22,675 29,207,94512 
497,655 471,284 487,642 379,671 4,119,089 
247,276 412,356 656,489 439,843 4,028,970' 3 
993,900 2,150,000 6,192,000 10,475,000 22,000,266 
990,124 2,283,992 6,040,471 10,337,104 21,548,94914 
100,000 150,000 304,099 629,099 
73,036 71,878 99,667 365,719 619,300 
74,500 125,000 500 166,991 366,991 
13,861 99,052 85,966 76,904 275,784 
400,000 25,000 515,613 105,000 20,375,339's, 16 
482;325 470,433 270,516 493,573 20,335,48417,18 
148,361 149,729 135,299 238,403 1,012,746 
134,922 154,552 132,592 229,099 991,69419 
7,631,821 
7,631,821 
118,824 168,641 115,671 174,199 1,738,271 
117,755 148,886 135,809 168,533 1,731,54620 
87,335 44,850 45,677 502,000 7,518,19821 
113,208 68,265 77,910 13,385 6,989,55622 
317,800 316,906 472,581 450,432 2,988,246 
224,154 346,778 501,856 450,402 2,951,12323 
220,000 30,438,13524 
30,218,135 
149,772 134,257 138,288 144,079 1,278,654 
110,366 123,536 117,395 153,965 1,275,186 
2,515,600 1,697,400 364,000 250,000 26,275,215 
3,020,372 1,798,743 712,992 228,648 26,153,99225 
152,110 243,923 354,619 338,356 1,179,744 
148,861 253,746 308,537 381,203 1,163,96526

TABLE 25-A (Cont'd) 
HUNTINGTON, W.VA., DISTRICT 
COST AND FINANCIAL STATEMENT 
in 
Totals to 
FY 72 FY 73 FY 74 FY 75 30 June 1975 
125,000 
455,266 
226,773 
212,877 
15,294 
12,603 
279,696 
292,295 
164,725 
87,347 
25,000 
91,556 
264,701 
253,122 
-3,602 
378 
470,390 
269,314 
-10,000 
116,602 
Text Project Funding 
19. Grayson, Lake, Ky. New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
20. John W. Flannagan New Work 
Dam and Reservoir, Approp. 
Ohio River Basin, Va. Cost 
Maint. 
Approp. 
Cost 
21. Kehoe Lake, Ky. New Work 
Approp. 
Cost 
22. Lower Guyandot New Work 
River, W. Va. Approp. 
Cost 
23. Martin LPP, Ky. New Work 
Approp. 
Cost 
24. Massillon, Ohio New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
25. Mill Creek Lake, New Work 
Ohio Approp. 
Cost 
26. Muskingum River New Work 
Dams and Lakes, Approp. 
Ohio Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
27. Newark, Ohio New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
28. North Branch New Work 
Kokosing River Approp. 
Lake, Ohio Cost 
Maint. 
Approp. 
Cost 
29. North Fork of Pound New Work 
River Lake, Va. Approp. 
Cost 
Maint. 
Approp. 
Cost 
30. Ohio River Basin New Work 
Aprop. 
Cost 
31. Paint Creek Lake, New Work 
Ohio River Basin, Approp. 
Ohio Cost 
Maint. 
Approp. 
Cost 
6,726 
7,528 
213,000 
103,557 
1,574 
73,939 
1,726,335 
1,539,822 
87,675 
91,033 
7,541 
10,022 
1,853,300 
1,652,683 
2,872 
4,066 
153,322 
145,958 
4,964,100 
3,724,391 
46,257 
43,809 
25-21 
11,173 
10,246 
-43,119 
456,680 
91,529 
43,670 
2,514,810 
1,918,513 
30,000 
18,088 
6,459 
1,123 
153,000 
334,648 
11,189 
11,189 
372,335 
161,411 
2,962,000 
2,885,771 
104,369 
106,195 
See 
Section 
524,100 -780,000 
9,224 293 
95,000 
148,431 
328,141 
318,141 
155,200 
147,574 
335,399 
479,977 
338,000 
67,976 
25,000 
3,181 
5,307 
4,729 
23,521 
145,747 
-77 
65,023 
2,864.306 
2,978,951 
80,000 
22,895 
5,104 
10,440 
50,000 
79,513 
69,124 
47,533 
25,000 
51,152 
198,486 
386,266 
1,391,000 
1,113,742 
109,821 
109,561 
55,000 
33,988 
327,096 
338,691 
234,500 
33,640 
313,962 
382,692 
-90,000 
63,381 
-899 
24,101 
2,367 
16,656 
4,832 
105,000 
2,343,454 
3,127,895 
10,000 
78,984 
10,781 
9,434 
1,000 
21,078 
65,776 
72,997 
3,773 
219,370 
247,152 
762,000 
25,805,97746 
201,029 
196,768 
18,770,37930 
18,739,13631 
1,723,161 
1,697,94632 
20,322,39233 
20,114,00534 
2,414,783 
2,395,74235 
1,040,425 
891,377 
24,101 
24,101 
200,300 
189,838 
8,139,40636 
8,139,40636 
161,771 
148,434 
1,602,702 
1,602,702 
41,309,26237 
41,204,26238 
20,163,417 
20,039,15839 
61,94540 
61,94540 
1,138,591 
1,138,517 
552,876 
551,529 
6,546,30041 
6,542,998 
146,088 
131,719 
6,186,97642 
6,186,90143 
1,447,128 
1,439,55144 
355,86145 
355,86145 
25,991,100 
461,476 
456,33347

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 25-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Totals to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 30 June 1975 
32. Paintsville Lake, 
Ky. 
33. Panther Creek 
Lake, W. Va. 
34. R. D. Bailey Lake, 
W. Va. 
35. Roseville, Ohio 
36. Salt Creek Lake, 
Ohio 
37. Summersville Lake, 
Ohio River Basin, 
W. Va. 
38. Sutton Lake, Ohio 
River Basin, W. Va. 
39. Tom Jenkins Dam, 
Ohio River Basin, 
Ohio 
40. Tug Fork Valley, 
Ky., W. Va., and Va. 
41. Utica Lake, Ohio 
42. Yatesville Lake, 
Ky. 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
249,264 
190,385 
355,000 2,320,000 1,725,000 5,773,264 
535,113 2,150,397 1,881,707 5,542,48048 
50,000 
741 
-27,121 
22,138 
22,879 
22,879 
17,376,000 16,782,600 21,210,000 17,600,000 108, 183,93449 
12,831,505 16,047,373 25,310,229 19,739,707 107,282,52549,50 
5,332 
8,257 
104,120 
129,663 
2,500 
179,833 
329,919 
382,630 
-3,500 
775 
395,084 
427,296 
79,504 
87,009 
268,100 
199,920 
74,500 
38,081 
3,368 
2,670 
-81,100 
107,315 
200,303 
373,254 
374,649 
359,181 
434,697 
200,598 
937,876 
625,541 
120,992 
97,306 
70,000 
92,273 
1,589 
2,287 
50,000 
73,468 
5,000 
13,561 
337,776 
353,476 
34,400 
252,071 
471,372 
782,366 
89,933 
113,020 
150,000 
145,000 
69,227 
4,563 
4,563 
910,785 
910,785 
915,348 
915,348 
1,090,120 
49,745 1,072,600 
-1,000 
701 
485,795 
486,723 
3,000 
22,009 
668,787 
696,954 
48,078,873 
48,075,409 
2,622,186 
2,594,26651 
36,839,71652 
36,839,66053 
4,496,281 
4,453,28954 
2,086,05355 
2,086,05355 
216,958 1,260,781 
133,704 1,173,53356 
125,000 
96,238 
-53,050 
45,956 
275,000 
96,238 
757,550 
730,613 
200,000 1,000,000 1,725,000 3,824,500 
92,929 879,353 1,991,302 3,803,09057 
1. Includes $4,294,612 for new work for previous projects. 
2. Includes $4,498,636 emergency relief funds and 
$9,004,800 public works funds. 
3. Includes $3,883,513 for maintenance for prevoius 
projects. 
4. Excludes surplus property valued at $11,556 
transferred from project without reimbursement. 
5. Public works acceleration funds. 
6. Excludes surplus property valued at $261 transferred 
from project without reimbursement. 
7. Excludes surplus property valued at $2,586 transferred 
from project withour reimbursement. 
8. Excludes $40,110 contributed by local interests. 
9. Excludes surplus property valued at $23 transferred 
from project without reimbursement. 
10. Excludes surplus property valued at $174 transferred 
from project without reimbursement. 
11. Includes $9,698 public works acceleration; $186,153 
Code 711; and $543,960 emergency relief funds. 
12. Includes $9,698 public works acceleration; $36,153 Code 
711; and $543,960 emergency relief funds. 
13. Excludes surplus property valued at $464 transferred to 
project without reimbursement. 
14. Excludes surplus property valued at $9,543 transferred 
to project without reimbursement. 
15. Excludes $225,090 contributed funds. 
16. Includes $580,613 Code 711 funds. 
17. Includes surplus property valued at $393 transferred 
from project without reimbursement. 
18. Includes $542,271 Code 711 funds. 
25-22

TABLE 25-A (Cont'd) 
HUNTINGTON, W.VA., DISTRICT 
COST AND FINANCIAL STATEMENT 
19. Excludes surplus property valued at $65 transferred to 
project without reimbursement. 
20. Excludes surplus property valued at $1,555 transferred 
from project without reimbursement. 
21. Includes $23,087 public works acceleration and 
$993,696 Code 711 funds. 
22. Includes $23,087 public works acceleration and 
$465,054 Code 711 funds. 
23. Excludes surplus property valued at $447 transferred 
from project without reimbursement. 
24. Includes $542,271 Code 711 funds. 
25. Excludes surplus property valued at $554 transferred 
from project without reimbursement. 
26. Excludes surplus property valued at $554 transferred to 
project without reimbursement. 
27. Includes $10,000 Code 712 funds. 
28. Includes $10,000 Code 712 funds. Excludes surplus 
property valued at $5,009 transferred from project without 
reimbursement. 
29. Excludes surplus property valued at $2,250 transferred 
to project without reimbursement. 
30. Includes $5,000 Code 711 funds. 
31. Includes $930 Code 711 funds.. 
32. Excludes surplus property valued at $2,448 transferred 
from project without reimbursement. 
33. Includes $323,958 Code 711 funds. 
34. Includes $115,783 Code 711 funds. 
35. Excludes surplus property valued at $41 transferred 
from project without reimbursement. 
36. Excludes $477,813 contributed funds. 
37. Includes $27,190,000 National Industrial Recovery Act 
Funds and $509,331 Code 711 funds. 
38. Includes $27,190,000 National Industrial Recovery Act 
Funds and $485.331 Code 711 funds. 
39. Excludes surplus property valued at $2,361 transferred 
to project without reimbursement. 
40. Public works acceleration funds. 
41. Excludes surplus property valued at $11,639 
transferred to project without reimbursement. 
42. Includes $64,308 Code 711 funds. 
43. Includes $64,233 Code 711 funds. 
44. Excludes property valued at $562 transferred to project 
without reimbursement. 
45. Includes $10,920 emergency relief funds. 
46. Excludes surplus property valued at $8,546 transferred 
from project without reimbursement. 
47. Excludes surplus property valued at $955 transferred to 
project without reimbursement. 
48. Excludes surplus property valued at $6,657 transferred 
from project without reimbursement. 
49. Includes $5,534 Consolidated Funds, Army. 
50. Excludes surplus property valued at $22,057 
transferred to project without reimbursement. 
51. Excludes surplus property valued at $15,085 
transferred to project without reimbursement. 
52. Includes $1,674,468 Code '711 funds. 
53. Includes $1,674,412 Code 711 funds. 
54. Excludes surplus property valued at $1,143 transferred 
from project without reimbursement. 
55. Includes $8,064 Code 711 funds. Includes $30,000 public 
works acceleration funds. Excludes $639,660 contributed 
funds. 
56. Excludes surplus property valued at $978 transferred 
from project without reimbursement. 
57. Excludes surplus property valued at $784 transferred 
from project without reimbursement. 
25-23 
_

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 25-B 
KANAWHA RIVER, W. VA.: 
TOTAL COST OF EXISTING PROJECT TO JUNE 30, 1975 
(See Section 2 of Text) 
Operations & 
Maintenance, 
Project New Work General Rehabilitation Total 
Regular $ 9,369,3341,2 $23,141,889 $32,511,223 
Public 9,004,800 9,004,800 
Emergency Relief 4,498,636 4,498,636 
Public Works - $130,394 130,394 
Acceleration, 
Executive, 1963 
Total $22,872,7703 $23,141,8894 $130,394 $46,145,053 
1. $5,159,879 expended between July 1884 and June 30, 
1936, on operation and care of work improvement under provisions 
of permanent indefinite appropriations for such purposes, 
of which $1,276,366 expended on existing project. 
2. Includes $3,883,513 expended for mainteriance on previous 
projects. 
TABLE 25-C 
3. Excludes $4,294,612 expended for New Work on previous 
projects. 
4. Excludes surplus property valued at $11,389 transferred 
to project without reimbursement. 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last 
Full Report 
See Annual 
Project Report For 
Big Sandy River, W. Va. and Ky., including 
Levisa and Tug Forks. 19 
Elk River, W. Va.3 19 
Gauley River, W. Va.4 19 
Guyandot River, W. Va.5 19 
Little Kanawha River, W. Va.6 19 
Muskingum River, Ohio 7 19 
New River, Va. and W. Va.5 18 
Scioto River at Portsmouth, Ohio9 19 
1. Excludes $131,473 contributed by local interest for 
maintenance of lock 1 in fiscal years 1953-62, inclusive, in 
addition $98,512 expended from operation and maintenance 
funds for repair of lock and dam 3 for local water supply and 
recreation. In addition, $140,068 expended from funds transferred 
from Department of Commerce, under accelerated 
public works program, for repairs of eroded bank at lock 3 on 
Big Sandy River, at Louisa, Ky. 
2. Operation and maintenance suspended June 30, 1952. 
3. Work closed September 1902. Property transferred to 
Kanawha River improvements. 
4. Work closed September 1902. Abandonment recommended 
in H. Doc. 467, 69th Cong. 
Cost to June 30, 1975 
Construction 
Operation and 
Maintenance 
)52 1,586,236 1,471,2991 
)03 30,259 
)03 14,761 
115 27,500 
)60 470,536 1,023,854 
)55 301,912 6,171,8978 
399 109,691 
X53 10,951 16,593 
5. Work suspended. 
6. Operation and maintenance suspended June 30, 1951. 
7. Collections from licensed non-Federal hydroelectric 
utilities for use of dams on Muskingym River for fiscal years 
1923-1953 were $79,154. 
8. Excludes $5,663 and $378, respectively, contributed 
funds for reconstruction of dam 10, and intermittent operation 
of lock 1 for benefit of Marietta Boat Club, Inc., subsequent 
to June 30, 1954. 
9. Private Law 945, August 31, 1954, authorized Secretary 
of Treasurer to pay Portsmouth Sand and Gravel Co. $75,000 
in full settlement of claims against Government for damages 
resulting from change in Scioto River Channel. 
25-24

HUNTINGTON, W. VA., DISTRICT 
TABLE 25-D 
OHIO RIVER BASIN (HUNTINGTON DISTRICT) 
LOCAL PROTECTION PROJECTS 
(See Section 30 of Text) 
Type of 
Location, 2 Protection 
Estimated Cost3 
Federal Non-Federal 
Aberdeen, Ohio 
Ashland, Ky. 
Athalia, Ohio 
Augusta, Ky. 
Belpre, Ohio 
Brooklyn, W. Va. 
Buena Vista, Ohio 
Burlington, Ohio 
Catlettsburg, Ky 
Ceredo-Kenova, W. Va. 
Chambersburg, Ohio 
Chesapeake, Ohio 
Cheshire, Ohio 
Chilo, Ohio 
Clifton, W. Va. 
Coal Grove, Ohio 
Dover, Ky 
Friendly, W. Va. 
Fullerton, Ky. 
Galax (New River Basin), Va. 
Gallipolis, Ohio 
Greenup, Ky. 
Hanging Rock, Ohio 
Hartford, W. Va. 
Henderson, W. Va. 
Higginsport, Ohio 
Hockingport, Ohio 
Huntington, W. Va. 
Ironton, Ohio 
Letart, W. Va. 
Letart Falls, Ohio 
Manchester, Ohio 
Mapleshade, Ohio 
Marietta, Ohio 
Mason, W. Va. 
Massillon (Muskingum River Basin), 
Ohio5 
Maysville, Ky. 
Middleport, Ohio 
Miller, Ohio 
Millwood, W. Va. 
Newark (Muskingum River Basin), 
Ohio 5 
New Martinsville, W. Va. 
New Matamoras, Ohio 
Newport, Ohio 
Normal, Ky. 
Parkersburg, W. Va. 
Point Pleasant, W. Va. 
Pomeroy, Ohio 
Portland, Ohio 
Portsmouth-New Boston, Ohio 
Proctorville, Ohio 
Racine, Ohio 
Ravenswood, W. Va. 
Ripley, Ohio 
Riverview, W. Va. 
Roseville (Muskingum River Basin), 
Ohio 5 
Russell, Ky. 
Wall and levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Channel improvement 
and levee 
Wall and levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Channel improvement, 
wall and levee 
Wall and levee 
Wall and levee 
Levee 
Wall and levee 
Channel improvement 
and levee 
Channel improvement 
and levee 
Wall and levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Wall and levee 
Resettlement 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Channel improvement 
Levee (backwater 
protection) 
$ 1,430,000 
3,717,655 
630,000 
1,220,000 
3,570,000 
5,200,000 
593,000 
146,000 
3,854,361 
2,756,956 
1,600,000 
330,000 
419,000 
899,000 
230,000 
888,000 
648,000 
655,000 
1,090,000 
480,536 
2,670,000 
2,660,000 
467,000 
2,880,000 
437,000 
944,000 
568,000 
7,172,840 
2,628,006 
938,000 
992,000 
1,330,000 
1,330,000 
14,000,000 
1,040,000 
8,139,406 
6,493,747 
6,260,000 
519,000 
843,000 
3,615,916 
4,670,000 
2,090,000 
318,000 
648,000 
6,652,827 
2,918,780 
16,500,000 
1,040,000 
9,806,424 
2,700,000 
985,000 
1,470,000 
1,940,000 
881,000 
910,785 
237,193 
$ 55,000 
313,000 
187,000 
620,000 
448,000 
226,000 
197,000 
117,000 
300,000 
265,000 
53,000 
139,000 
147,000 
120,000 
113,000 
55,000 
585,000 
61,000 
178,000 
185,000 
839,000 
512,000 
155,000 
222,000 
188,000 
320,000 
242,000 
1,509,3006 
669,000 
123,000 
126,000 
377,000 
298,000 
822,000 
238,000 
477,8137 
563,7008 
A90,000 
173,000 
134,000 
541,000 
643,000 
285,000 
84,000 
235,000 
300,000 
278,000 
346,000 
104,000 
525,00012 
120,000 
106,000 
810,000 
115,000 
62,000 
10,000 
$ 1,485,000 
4,030,6554 
817,000 
1,840,000 
4.018.000 
5,426,000 
790,000 
263,000 
4,154,3614 
3,021,9564 
1,653,000 
469,000 
566,000 
1,019,000 
343,000 
943,000 
1,233,000 
716,000 
1,268,000 
666,5364 
3,509,000 
3,172,000 
622,000 
3,102,000 
625,000 
1,264,000 
810,000 
8,682,1404 
3,297,0064 
1,061,000 
1,118,000 
1,707,000 
1,628,000 
14,822,000 
1,278,000 
8,617,2194 
7,057,4474 
6,750,0009 
692,000 
977,000 
4,156,9164, 1o 
5,313,000 
2,375,000 
402,000 
883,000 
6,952,8274 
3,196,7804 
16,846,000 
1,144,000 
10,331,4244 
2,700,000 
1,105,000 
1,576,000 
2,750,000 
996,000 
972,7854, 10 
247,193 
25-25 
Total

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OHIO RIVER BASIN (HUNTINGTON DISTRICT) 
LOCAL PROTECTION PROJECTS 
TABLE 25-D (Cont'd.) (See Section 30 of Text) 
Type of Estimated Cost3 
Location', 2 Protection Federal Non-Federal Total 
St. Marys, W. Va. Wall and levee 1,510,000 139,000 1,649,000 
Sardis, Ohio Levee 285,000 60,000 345,000 
Sciotoville, Ohio Wall and levee 1,460,000 377,000 1,837,000 
Sistersville, W. Va. Wall and levee 1,770,000 269,000 2,039,000 
South Point, Ohio Wall and levee 992,000 117,000 1,109,000 
South Portsmouth, Ky. Levee 370,000 137,000 507,000 
Syracuse, Ohio Levee 1,220,000 100,000 1,320,000 
Vanceburg, Ky. Wall and levee 2,490,000 685,000 3,175,0009 
Waverly, W. Va. Wall and levee 3,480,000 251,000 3,731,000 
Williamstown, W. Va. Wall and levee 2,580,000 136,000 2,716,000 
Zanesville (Muskingum River), Ohio Wall and levee 8,110,000 13,000,000 21,110,000 
1. All projects are on Ohio River, unless otherwise noted. 
2. Also see"Other authorized flood control projects," for 
all projects except: Massillon, Newark, and Roseville, Ohio. 
3. Latest cost estimate revised 1954, unless otherwise 
noted. 
4. Construction completed. 
5. For details see individual report. 
6. Includes $2,300 construction funds contributed by local 
interests. 
7. Construction funds contributed by Massillon Conser 
vancy District. 
8. Includes $38,700 construction funds contributed by 
local interests. 
9. Latest cost estimate revised, 1960. 
10. Includes construction costs expended in fiscal year 
1963 and 1964 on original project. 
11. Includes estimate for modified project. 
12. Includes $15,150 construction funds contributed by 
local interests. 
25-26

HUNTINGTON, W. VA., DISTRICT 
OHIO RIVER BASIN (HUNTINGTON DISTRICT) DAMS AND LAKES 
TABLE 25-E (See Section 30 of Text) 
Tributary basin Total estimated 
and reservoir Stream cost 
Big Sandy: 
Dewey, Ky.2 Johns Creek $ 9,022,0003 
Fishtrap, Ky. 2 Levisa Fork 53,854,000 
Haysi, Va.5 Russell Fork 10,100,000 
John W. Flannagan, Va.2 Pound River 22,088,000 
Guyandot: 
Mud River, W. Va.5 Mud River 10,600,000 
Hocking: 
Logan, Ohio5 Clear Creek 4,230,000 
Tom Jenkins, Ohio2 East Branch of Sunday Creek 2,086,5003,6 
Kanawha: 
Big Bend, W. Va.5 Greenbrier River 13,900,000 
Birch, W. Va.5 Birch River 6,450,000 
Bluestone,W. Va.2 New River 30,158,0003 
Moores Ferry, Va.5 New River 25,600,000 
Poca, W. Va.5 Pocatalico River 21,600,000 
Summersville, W. Va.2 Gauley River 48,080,0003 
Sutton, W. Va.2 Elk River 36,837,0003 
Little Kanawha: 
Burnsville, W. Va.2 Little Kanawha River 44,400,0004 
Leading Creek, W. Va.5," Leading Creek 40,400,00012 
West Fork, W. Va.5 ," West Fork 39,700,00012 
Muskingum: 
Dillon, Ohio2 Licking River 34,518,0003 
Frazeysburg, Ohio5 Wakatomika Creek 7,200,0007 
Millersburg, Ohio5 Killbuck Creek 12,000,000 
Muskingum River Lakes 
(System of 14 reservoirs)2 On various streams 44,353,0003 
Scioto: 
Big Darby Creek, Ohio Big Darby Creek 70,300,0008 
Deer Creek, Ohio2 Deer Creek 20,280,0003 
Delaware, Ohio2 Olentangy River 7,631,8213 
Paint Creek, Ohio2 Paint Creek 26,700,0004 
Rocky Fork, Ohio Rocky Fork 4,410,0001o 
Twelvepole Creek: 
East Lynn, W. Va.5,9 East Fork 34,400,0004 
1. Latest cost estimate revision 1954, unless otherwise noted. 
2. For details see individual report. 
3. Construction completed. 
4. Latest cost estimate revision 1975. 
5. Also see "Other Authorized Flood Control Projects." 
6. Excludes $785,000 contributed by local interests. 
7. Latest cost estimate revision 1960. 
8. Latest cost estimate revision 1963. 
9. See annual report ofr 1950 for individual report. 
10. Total cost $6,349,000, additional $1,939,000 to be contributed by local interests. 
11. See annual report for 1974 for individual report. 
12. Latest cost estimate revision 1974. 
25-27

TABLE 25-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 28, 1937 
June 28, 1938 
Aug. 11, 1939 
Aug. 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Dec. 30, 1963 
June 18, 1965 
Aug. 13, 1968 
June 19, 1970 
Mar. 7, 1974 
OHIO RIVER BASIN-HUNTINGTON DISTRICT (See Section 
30 of Text) 
Construct levees, floodwalls, and drainage structures for 
protection of cities and towns in Ohio River Basin. Projects 
to be selected by Chief of Engineers with approval of 
Secretary of War at a cost not to exceed $24,877,000 for 
construction. 
Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable in 
discretion of Secretary of War and Chief of Engineers, and 
for initiation and partial accomplishment of plan, authorized 
$75 million for reservoirs and $50,300,000 for local flood 
protection works. 
Provides Muskingum River Valley dams and reservoirs as set 
forth in official plan of Muskingum watershed conservancy 
district shall be included in flood control plan of Ohio 
River Basin. 
Additional $45 million for prosecution of comprehensive plan 
for Ohio River Basin. 
Additional $70 million for further prosecution of comprehensive 
plan for Ohio River Basin, including Burr Oak Reservoir on 
Hocking River, Ohio at an estimated cost of $400,000. 
Additional $125 million for further prosecution of 
comprehensive plan including local flood protection works 
at Galax, Va., on Chestnut Creek, at an estimated cost of 
$276,125. 
Additional $100 million for prosecution of comprehensive plan 
for Ohio River Basin 
Additional $150 million for further prosectuion of 
comprehensive plan for flood control and other purposes in 
Ohio River Basin. 
Additional $89 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $35 million for further prosectuon of comprehensive 
plan for Ohio River Basin. 
Additional $69 million for further prosecuton of comprehensive 
plan for Ohio River Basin 
Additional $120 million for further presecution 
comprehensive plan for Ohio River Basin 
25-28 
Flood Control Committee Doc. 1, 
75th Cong., 1st Sess. 
Flood Control Committee Doc. 1, 
75th Cong., 1st Sess. 
H. Doc. 762, 77th Cong., 2nd Sess. 
H. Doc. 506, 78th Cong., 1st Sess. 
H. Doc. 6755, 89th Cong., 
1st Sess. 
S. 3710, 90th Cong. 
H. Doc. 15166, 91st Cong. 
2nd Sess. 
H. Doc. 10203, 93rd Cong., 
2nd Sess.

HUNTINGTON, W. VA., DISTRICT 
TABLE 25-G 
OHIO RIVER BASIN (HUNTINGTON DISTRICT) 
PROJECT COSTS TO JUNE 30, 1974 
(See Section 30 of Text) 
New Work 
Total 
Appropriated 
Project to June 30, 1975 
Local protection projects: 
Aberdeen, Ohio 
Augusta, Ky. 
Coal Grove, Ohio 
Columbus, Ohio 
Greenup, Ky. 
Manchester, Ohio 
Middleport, Ohio 
Ripley, Ohio 
Reservoirs and Lakes: 
Big Walnut, Ohio 
Birch, W. Va. 
Clendenin, W. Va. 
Frazeysburg, Ohio 
Haysi, Va. 
Leading Creek, W. Va. 
Rocky Fork, Ohio 
West Fork, W. Va. 
Total Ohio River Basin 
Total Cost 
to 
June 30, 1975 
$ 1,334 
11,5771 
3,389 
11,2372 
4,962 
17,7211 
9,7833 
7,523 
110,622 
45,7361 
33,000 
5,000 
2,656 
272,8805 
91,321 
663,1925 
1,291,0334 
$ 1,334 
11,5771 
3,389 
11,2372 
4,962 
17,7211 
9,7833 
7,523 
110,622 
45,7361 
33,000 
5,000 
2,656 
272,8805 
91,321 
663,1925 
1,291,9334 
1. Allocation and costs for feasibility study 
2. Includes $9,137 emergency relief funds. 
3. Includes $1,783 emergency relief funds. 
4. Includes $10,920 emergency relief funds (Basin total). 
5. Allocation and costs for Phase I GDM Draft. 
25-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
INSPECTION OF FLOOD CONTROL PROJEJCTS 
TABLE 25-H (See Section 44 of Text) 
Flood Control Works Inspected Dates of Inspection 
Ashland, Ky. 
Athens, Ohio 
Barboursville, W. Va. 
Beaver Creek, Langley, Ky. 
Beaver Creek, Wayland to Garrett, Ky. 
Bramwell, W. Va. 
Cairo, W. Va. 
Catlettsburg, Ky. 
Ceredo-Kenova, W. Va. 
Chillicothe, Ohio 
East Rainelle, W. Va. 
Fishing Creek, Pine Grove, W.:Va. 
Fourpole Creek, Huntington, W. Va. 
Galax, Va. 
Grahn, Ky. 
Griffithsville-Yawkey, W. Va. 
Hitchins, Ky. 
Huntington, W. Va. 
Inez, Ky., Rock Castle Creek 
Ironton, Ohio 
Jacksonburg, W. Va. 
Massillon, Ohio 
Maysville, Ky. 
McDowell - Drift, Ky. 
Montcalm, W. Va. 
Mount Vernon, Ohio 
Newark, Ohio 
Nimishillen Creek, Canton, Ohio 
Olive Hill, Ky. 
Paint Creek, Washington Court House, Ohio 
Parkersburg, W. Va. 
Point Pleasant, W. Va. 
Portsmouth - New Boston, Ohio 
Prestonsburg, Ky. 
Princeton, W. Va. 
Richwood - Fenwick, W. Va. 
Roseville, Ohio 
Russell, Ky. 
Smithfield, W. Va. 
South Williamson, Ky. 
Utica, Ohio 
West Union, W. Va. 
Williamson, W. Va. 
Apr. 1976, Oct. 1975 
Sep. 1975 
Jan. 1974 
Mar. 1976 
Mar. 1976 
Sep. 1975 
Sep. 1975 
May 1976, Oct. 1975 
Apr. 1976, Sep. 1975 
Nov. 1975 
Aug. 1975 
Sep. 1975 
Aug. 1973 
Sep. 1975 
Jan. 1975 
Nov. 1974 
Jan. 1975 
Apr. 1976, Oct. 1975 
Oct. 1975 
Apr. 1976, Sep. 1975 
Sep. 1975 
Nov. 1975 
Apr. 1976, Sep. 1975 
Mar. 1976 
Sep. 1975 
Aug. 1975 
Apr. 1976, Jun. 1975 
Dec. 1974 
Nov. 1975 
Nov. 1975 
May 1976, Oct. 1975 
May 1976, Oct. 1975 
Apr. 1976. Sep. 1975 
Feb. 1976, May 1975 
Sep. 1975 
Aug. 1975 
Apr. 1976, May 1975 
Apr. 1976, Sep. 1975 
Sep. 1975 
May 1976, Oct. 1975 
Jul. 1975 
Sep. 1975 
May 1976, Oct. 1975 
25-30

HUNTINGTON, W. VA., DISTRICT 
TABLE 25-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Local Protection projects: 
Aberdeen, Ohio - 1,334 - 
Ashland, Ky.3 1954 3,703,9524 
Athalia, Ohio' 
Athens, Ohio3 - 5,166,146 - 
Augusta, Ky.' 11,577 - 
Belpre,Ohio' 
Brooklyn, W.Va.' 
Buena Vista, Ohio' 
Burlington, Ohio' 
Catlettsburg, Ky.3 1963 3,854,361 
Ceredo-Kenova, W. Va.3 1955 2,753,5514 
Chambersburg, Ohio' 
Chesapeake, Ohio' 
Cheshire, Ohio' 
Chilo, Ohio' 
Clifton, W. Va.' 
Coal Grove, Ohio' - 3,389 - 
Columbus, Ohio' - 11,237 - 
Dover, Ky.' 
East Rainelle, W. Va.3 1962 614,598 - 
Friendly, W. Va.' 
Fullerton, Ky.' - -- 
Galax, Virginia3 1953 480,536 - 
Gallipolis, Ohio' 
Greenup, Ky.' - 4,962 - 
Hanging Rock, Ohio' 
Hartford, W. Va.' 
Henderson, W. Va.' 
Higginsport, Ohio' 
Hockingport, Ohio' 
Huntington, W. Va.3 1956 7,172,8404 
Ironton, Ohio3 1952 2,604,6464 
Letart, W. Va.' 
Letart Falls, Ohio' 
Manchester, Ohio' - 17,721 
Marietta, Ohio' 
Mason, W. Va.' 
Maysville, Ky.3 1959 6,493,7474 - 
Middleport, Ohio' - 9.783 - 
Miller, Ohio' 
Millwood, W. Va.' 
New Martinsville, W. Va.' 
New Matamoras, Ohio' 
New Port, Ohio' 
Normal, Ky.' 
Parkersburg, W. Va.3 1955 6,652,8274 
Pt. Pleasant, W. Va.3 1953 2,919,5804 - 
Pomeroy, Ohio' 
Portland, Ohio' 
Portsmouth-New Boston, Ohio3 1956 9,806,4244 - 
Princeton, W. Va.3 1962 808,750 - 
Proctorville, Ohio' 
Racine, Ohio' 
Ravenswood, W. Va.' 
Ripley, Ohio' - 7,523 - 
Riverview, W. Va.' 
Russell, Ky.3 1953 237,193 - 
St. Marys, W. Va. 1' 
Sardis, Ohio' 
Sciotoville, Ohio1' 
Sisterville, W. Va.' 
South Point, Ohio' 
South Porthsmouth, Ky.' 
25-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 25-I (Cont'd) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Syracuse, Ohio' 
Vanceburg, Ky.' - - 
Waverly, W. Va.'1 -. 
Williamson, W. Va.3 1964 1,056,166 
Williamstown, W. Va.' - - 
Zanesville, Ohio' 
Reservoirs and Lakes: 
Big Bend, W. Va.' 
Big Darby, Ohio' 1969 3,349,568 - 
Birch, W. Va.2 - 45,736 - 
Frazeysburg, Ohio' - 5,000 - 
Haysi, Va.' - 2,656 - 
Leading Creek, W. Va.' 1974 272,880 - 
Logan, Ohio2 - 
Millersburg, Ohio' 
Moores Ferry, Va.2 
Mud River, W. Va.' 
Poca, W. Va.' - 
Rocky Fork, Ohio' 1950 91,321 - 
West Vork, W. Va.' 1974 663,192 - 
1. Inactive 
2. Deferred 
3. Completed 
4. Includes cost of floodwall rehabilitation 
25-32

HUNTINGTON, W. VA., DISTRICT 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
TABLE 25-J (See Section 45 of Text) 
Flood Control activities pursuant to Section 205 
P.L. 858, 80th Congress, as amended (preauthorization) 
Study Identification Federal Year Costs 
Cabin Creek, W. Va. $ 500 
Cheery River-Fenwick-Richwood, W. Va. 4,895 
Laurelville, Ohio 200 
Peck Creek, Va. 2,798 
Snagging and clearing navigable stream and 
tributaries in the interest of flood control 
(Sec. 208, 1954 Flood Control Act, P.L. 780, 
83rd Congress). 
Project and Location 
Paint Creek, Pax, W. Va. 120 
Reedy, W. Va. 4,932 
Salt Creek, Laurelville, Ohio 5,912 
Emergency Bank Protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 
79th Congress). 
Project and Location 
Pomeroy, Ohio $14,010 
25-33

PITTSBURGH. PA., DISTRICT* 
This District comprises part of eastern Ohio, River and tributaries above mile 127 (below 
western Pennsylvania southwestern New York, Pittsburgh), immediately upstream from New 
northern West Virginia, and northwestern Martinsville, W.Va. 
Maryland embraced in drainage basin of Ohio 
IMPROVEMENTS 
Navigation 
1. Allegheny River, Pa .................... 
2. Construction of locks and dams, 
Ohio River..................................... 
3. Monongahela River, Pa. and 
W. Va....................................... 
4. Open-channel work, Ohio River... 
5. Tygart River Lake, W.Va............. 
6. Other authorized navigation 
projects.......................................... 
Flood Control 
7. Allegany, N .Y ................................. 
8. Berlin Lake, Ohio River Basin, 
O hio.................................................. 
9. Chartiers Creek, Pa.................... 
10. Conemaugh River Lake, Ohio River 
Basin, Pa........................ .......... 
11. Crooked Creek Lake, Ohio River 
Basin, Pa........................ .......... 
12. DuBois, Pa ...................................... 
13. East Branch, Clarion River Lake, 
Ohio River Basin, Pa................... 
14. Elkins, W .Va.................................. 
15. Girtys Run, Millvale, Pa............... 
16. Johnstown, Pa................ ........... 
17. Kinzua Dam and Allegheny 
Reservoir, Ohio River Basin, Pa. 
and N.Y ........................................... 
18. Loyalhanna Lake, Ohio River Basin, 
Pa..................................................... 
19. Mahoning Creek Lake, Ohio River 
Basin, Pa...................... ............ 
Pc'age Flood Control (cont.) 
26-2 20. Michael J. Kirwan Dam and 
Reservoir, Ohio.... ............... 
26-2 21. Mosquito Creek Lake, Ohio River 
Basin, Ohio.................... ............ 
26-2 22. Muddy Creek Dam, Pa................ 
26-3 23. Ohio River Basin (Pittsburgh 
26-3 District)........................................... 
24. Punxsutawney, Ohio River Basin, 
26-3 Pa ....................................... 
25. Ridgway and vicinity, Pa.............. 
26. Rowlesburg Lake, W. Va.............. 
26-3 27. Shenango River Lake, Ohio River 
Basin, Pa. and Ohio ..................... 
26-4 28. Stonewall Jackson Lake, W. Va... 
26-4 29. Tenmile Creek at Marianna, Pa. 
30. Tionesta Lake, Ohio River Basin, 
26-5 Pa..................................... ... 
31. Union City Lake, Pa...................... 
26-6 32. Woodcock Creek Lake, Pa............ 
26-6 33. Youghiogheny River Lake, Ohio 
River Basin, Pa. and Md............... 
27-7 34. Youngstown, Ohio........................ 
26-7 35. Inspection of completed flood 
26-7 control projects...................... 
26-8 36. Other authorized flood control 
26-8 
projects. ......................... 
37. Flood control work under special 
authorization................................... 
General Investigations 
26-9 38. 
39. 
26-9 40. 
Surveys............................................ 
Collection and study of basic data 
Research and development........... 
Page 
26-10 
26-10 
26-11 
26-11 
26-11 
26-12 
26-12 
26-13 
26-13 
26-15 
26-15 
26-15 
26-16 
26-17 
26-17 
26-18 
26-18 
26-18 
26-18 
26-18 
26-18 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
26-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. ALLEGHENY RIVER, PA. 
Location. Rises in northern Pennsylvania, 
flows northwestward into New York, thence 
generally southwestward to Pittsburgh, Pa., 
where it joins with Monongahela River to form 
the Ohio. It is 325 miles long. (See Geological Survey 
Charts for western Pennsylvania and 
southwestern New York.) 
Existing project. Provides for eight locks and 
dams to afford slack-water navigation from 
Pittsburgh, Pa., 72 miles to above East Brady, 
Pa. Controlling depth through canalized portion 
is 9 feet at normal pool level, and channel width 
varies from minimum of 200 feet to full width of 
river at mouth. Cost of new work for completed 
project is $18,157,860. (See tables 26-B and 26-C 
for authorizing legislation and locks and dams on 
Allegheny River, Pa.) 
Local cooperation. Fully complied with. 
Terminal facilities. City of Pittsburgh constructed 
a modern wharf for river freight. There 
are numerous privately maintained terminals 
and docks, consisting of tipples, various types of 
hoists, chutes, and pipelines for use in loading and 
unloading coal, stone, sand, gravel, petroleum 
products, steel products, and other commodities. 
Transshipment of freight between river and 
railroads is handled at privately owned river-torail 
terminals. Existing private terminals are 
adequate for shipments and receipt in Pittsburgh 
District of type of commerce now in existence. 
Operations and results during fiscal year. 
Operation and maintenance, general: Locks were 
operated as required and necessary repairs made 
to structures to maintain them in serviceable condition 
at cost of $1,170,498; maintenance repairs 
at locks and dams were accomplished at cost of 
$535,521. 
Condition at end offiscal year. Existing project 
is complete, last lock was placed in service in 
1938. All locks and dams are in good condition. 
Navigation channel has been widened at certain 
points and, in general, maintained to project 
depth, thus affording adequate depth for passage 
of commercial tows. 
2. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
See this heading under Ohio River portion. 
3. MONONGAHELA RIVER, PA. AND 
W. VA. 
Location. Formed by junction of Tygart and 
West Fork Rivers about 1 mile south of Fairmont, 
W. Va., and flows northerly for 128.7 miles to its 
junction with Allegheny River, forming Ohio 
River at Pittsburgh, Pa. (See Geological Survey 
Charts for southwestern Pennsylvania and 
northern West Virginia.) 
Previous project. For details see Annual Report 
for 1963, page 1070. 
Existing project. Provides for improvement of 
river by 10 locks and dams to afford slack-water 
navigation for its entire length from Pittsburgh 
to above Fairmont, W. Va. Original locks and 
dams 7, 8 and 9 were replaced by new locks and 
dams 7 and 8 in 1925. Increased traffic 
necessitated enlargement and improvement of 
locks and dams 1 to 6 between Pittsburgh and 
Rices Landing, Pa., by building two parallel 
chambers and fixed concrete dams during 1905 
and 1932. Locks and dam 1 were eliminated in 
1938 by raising Emsworth Dam, Ohio River. 
Reconstruction of lock 2 was completed in 1953 to 
provide two modern navigation chambers. Construction 
of Maxwell locks and dam and the 
reconstruction of dam 4 have allowed for removal 
of obsolete locks and dams 5 and 6. Recently 
authorized Grays Landing lock and dam and 
Point Marion replacement lock will replace existing 
obsolete lock and dam 7 and lock 8, respectively. 
Small and antiquated original locks and 
dams 10 to 15, inclusive, have been replaced by 
three modern structures. Morgantown lock and 
dam, initial step in replacement program, was 
completed in 1950 replacing locks and dams 10 
and 11. Hildebrand lock and dam, next upstream, 
was completed in 1959 replacing locks and dams 
12 and 13. Raising crest of dam 8 was also completed 
in 1959 as part of upper river improvement 
and eliminates restricted depth in upper reach of 
pool. Opekiska lock and dam, the final step in the 
replacement program, was completed in 1967 
replacing locks and dams 14 and 15. Completion 
of this final link in upper river replacement 
program provides for entire river length of 
minimum channel depth of 9 feet, varying in 
width from a minimum of 250 feet to practically 
full width at mouth. Estimated cost for new work 
(1975), exclusive of amounts expended on 
previous projects is $213,900,000. (See tables 26- 
B, 26-D, and 26-E for authorizing legislation and 
locks and dams on Monongahela River, Pa. and 
W. Va., and total costs of existing project to end of 
fiscal year.) 
Local cooperation. None required. 
Terminal facilities. City of Pittsburgh constructed 
a modern wharf for freight. Boat landings 
are maintained by some municipalities 
along the river. A large number of tipples at 
mines and various types of hoists at manufacturing 
plants and sand and gravel supply companies 
are maintained for private use in loading 
26-2

PITTSBURGH, PA., DISTRICT 
and unloading coal, coke, billets, steel products, 
sand, gravel, and other commodities. These terminals 
and docks are not available for general 
commerce. A number of docks and pipelines are 
also privately maintained for petroleum and acid 
products. Marine ways are maintained by some of 
the larger industries. There are also several terminals 
for rail-to-river and river-to-rail transfer. 
Facilities considered adequate for existing commerce. 
Operations and results during fiscal year. New 
work: Preconstruction planning was initiated on 
Grays Landing lock and dam, to replace obsolete 
lock and dam 7 and Point Marion lock, to replace 
lock 8. Operation and maintenance, general: 
Locks were operated as required and necessary 
repairs were made to maintain them in a serviceable 
condition at cost of $2,717,527; 
maintenance repairs to locks and dams cost $901,- 
193. Study for replacement of locks and dams for 
lower reach of river remains suspended pending 
accomplishment of a systems analysis approach 
for navigation planning. 
Condition at end of fiscal year. Project is complete 
except for concluding actions relative to outstanding 
judgments in connection with acquisition 
of land for the reconstruction of dam 4, construction 
of Grays Landing lock and dam and construction 
of new lock at Point Marion lock and 
dam (lock and dam 8). A controlling depth of 9 
feet is maintained for entire length of river, varying 
in width from a minimum of 250 feet to full 
width of river at mouth. 
4. OPEN-CHANNEL WORK, OHIO 
RIVER 
See this heading under Ohio River portion. 
5. TYGART RIVER LAKE, W. VA. 
Location. On Tygart River in Taylor County, 
W. Va., about 22.7 miles above mouth of river at 
Fairmont, W. Va. It is 2.25 miles upstream from 
Grafton, W. Va., and about 78 miles south of 
Pittsburgh, Pa. Reservoir is in Taylor and Barbour 
Counties, W. Va. (See Geological Survey 
Charts for Fairmont, Thornton, and Belington, 
W. Va.) 
Existing project. A reservoir for low water 
regulation and flood control. Dam is concrete 
gravity type with an uncontrolled center spillway 
flanked by abutment sections joining valley sides. 
Project was authorized by Public Works Administration 
January 11, 1934, and adopted by 
1935 River and Harbor Act. For further project 
description see Annual Report for 1962. Completed 
project cost $18,431,844. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control and low 
water regulation, as required, and project structures 
were maintained in a serviceable condition 
throughout the year at cost of $359,113. Inflow 
into the lake was much above normal during the 
summer-fall period and downstream flow 
schedule was easily maintained. Lake levels were 
near the summer pool elevation throughout the 
summer recreation season, falling to about seven 
feet below summer pool by the end of August. 
Significant flood reductions during January, 
March, and April 1975 were effected by Tygart 
Dam along the Monongahela and Upper Ohio 
Rivers. Estimated flood control benefits achieved 
by this reservoir for the fiscal year were $1,438,- 
100. Total flood control benefits for this reservoir 
through June 30, 1975 are $168,984,000. Some 
reservoir management activity was continued 
comprising sanitation measures, real estate 
management and operation and maintenance of 
public-use facilities. This work was limited in 
scope as State of West Virginia has jurisdiction 
over recreation in reservoir area. 
Condition at end of fiscal year. Authorized project 
is complete. Reservoir is in operation for low 
water control in Monongahela River and for purpose 
of flood protection in Monongahela and Ohio 
Valleys. Construction of dam was started in 1935 
and placed in operation in 1938. Land acquired 
for project consists of 2,662.9 acres in fee simple 
and flowage easements over 1,216.9 acres. 
6. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 26-F on other authorized navigation 
projects. 
Flood Control 
7. ALLEGANY, N. Y. 
Location. In Cattaraugus County, New York on 
the right bank of the Allegheny River, approximately 
four miles west of Olean, N. Y. (See 
Geological Survey Chart for Olean, N. Y.) 
Existing project. Provides for construction of an 
earth dike along Fivemile Creek about 2,250 feet 
long, relocation of about 1,400 feet of channel of 
Lippert Run, a tributary of Fivemile Creek at the 
lower end of the village, and a deflection dike 
about 620 feet along the Lippert Run relocation, 
together with appurtenant drainage facilities. 
Project was authorized by 1946 Flood Control 
Act. Estimated Federal cost for new work (1975) 
is $980,000; estimated non-Federal cost $133,000. 
26-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Local interests would be required 
to provide without cost to the United 
States all lands, easements and rights-of-way 
necessary for construction of the project; hold and 
save the United States free from damages due to 
the construction works; bear the costs of utility 
and highway adjustments in accordance with 
project allocation of these items; and maintain 
and operate the works after completion in accordance 
with regulations prescribed by the 
Secretary of the Army. The Department of Public 
Works, State of New York, the local cooperation 
agency, stated in letter dated February 14, 1964 
that they are prepared to recommend participation 
in a project provided the engineering is considered 
sound and the project is economically 
justified. 
Operations and results during fiscal year. 
Phase I, General Design Memorandum completed; 
negative benefit-cost ratio findings. 
Condition at end of fiscal year. Recommendation 
being made to place project in inactive 
category due to economic infeasibility. 
8. BERLIN LAKE, OHIO RIVER 
BASIN, OHIO 
Location. Dam is on Mahoning River about 73 
miles above its confluence with Shenango River. 
Tt is about 10 miles above existing Milton Reservoir 
Dam and 35 miles upstream from Warren, 
Ohio. Reservoir is in Portage, Mahoning, and 
Stark Counties, Ohio. (See Geological Survey 
Charts for Warren, Ravenna, and Alliance, Ohio.) 
Existing project. A reservoir for flood control 
and water supply. Dam consists of a partially controlled, 
concrete gravity, center spillway flanked 
by rolled-earthfill abutment sections joining 
valley sides. Project selected for construction under 
general authorization for Ohio River Basin in 
1938 Flood Control Act. For further project 
description, see Annual Report for 1962, page 
1233. Federal cost of completed project was $6,- 
288,676. Construction of additional recreation 
facilities for completed project is estimated to 
cost $2,411,700 (1975) making the total project 
cost estimate $8,700,376. 
Local cooperation. None required by law. 
Operations and results during fiscal year. New 
work: Contract to enlarge the sewage treatment 
plant at Mill Creek recreation area was completed. 
Contract was initiated for construction of 
Bonner Road Access Area, with scheduled completion 
date early 1976. Operation and 
maintenance, general: Reservoir was operated as 
required and necessary repairs were made to 
structures and appurtenances at cost of $446,134. 
Inflow into the reservoir was much above normal 
during the summer-fall period. However, pursuant 
to the safety inspection of Milton Dam being 
conducted by a consulting engineer hired by 
the City of Youngstown, Lake Milton was held at 
a low level throughout the summer-fall period. 
The loss of Lake Milton storage necessitated a 
revision of the minimum flow schedule for 
Leavittsburg. The flow schedule was reduced 50 
cubic feet per second. Rainfall was above normal 
during the summer-fall period and the 
Leavittsburg flow reduction was only 38 c.f.s. for 
13 days during the latter half of July 1974. Lake 
Milton was held at a low level during the winterspring 
season of 1974-75 and did not reach 
summer pool level until 19 June 1975. The 
Leavittsburg flow reduction was 17 c.f.s. for 11 
days in May 1975. Lake levels remained above 
normal throughout the summer recreation 
season, although falling steadily to about 4 feet 
below summer pool by the end of August 1974. 
Estimated flood control benefits achieved by this 
reservoir for the fiscal year were $9,160,000; total 
benefit through 30 June 1975, $109,776,000. 
Water supply storage in this reservoir for the 
Mahoning Valley Sanitary District for domestic 
consumption was reserved under contract request 
amounting to 15 million gallons per day for 
the fiscal year; however, there was no actual 
withdrawal for water supply during this fiscal 
year. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management, and operation and 
maintenance of public-use facilities continued. 
Condition at end of fiscal year. Authorized project 
is complete and in operation for flood control 
and low water regulation purposes in industrialized 
Mahoning Valley below. Construction 
of dam was started January 1942 and completed 
June 1943. Land acquired for project consists 
of 6,885.3 acres in fee simple and easements 
over 1,098.7 acres. Remaining work consists of 
provision on project lands of additional recreation 
facilities required to serve public needs. 
9. CHARTIERS CREEK, PA. 
Location. Within Washington and Allegheny 
Counties, southwestern Pennsylvania, a 
tributary of Ohio River. (See Geological Survey 
Chart for Carnegie, Pa.). 
Existing project. Provides for channel widening, 
deepening and realignment, construction of a 
major channel cutoff, and relocations in two 
separate and independent reaches. Carnegie- 
Bridgeville reach of improvement in Allegheny 
County would be-about 13.4 miles long and 
Canonsburg-Houston reach in Washington County 
about 4.7 miles long. PL 93-231, signed 
December 29, 1973, changed the name of 
Carnegie-Bridgeville reach to the "James G. 
Fulton Flood Protection Project". Proposed im- 
26-4

PITTSBURGH, PA., DISTRICT 
provements would contain within banks, all 
floods up to the 1912 maximum of record, but 
with some residual damage, and would greatly 
reduce flood stages and damages resulting from 
higher floods. Project was authorized by Flood 
Control Act of 1965. Estimated cost for new work 
(1975) is $37,500,000, of which $28,400,000is 
Federal cost and $9,100,000 non-Federal cost. 
Local cooperation. Responsible local interests 
must provide lands, easements, rights-of-way, 
and spoil-disposal areas for construction; bear 
cost of all relocations and alterations of sewer, 
water, gas, oil, electric powerlines, and other 
utility alterations; railroad track shifts; highway 
and street modifications; and construction of new 
or reconstruction of existing highway bridges 
made necessary by construction work; hold United.
States free from damages; establish channel 
limit lines within each county along entire 
waterway downstream from existing improvements 
at Washington, Pa., and prevent any 
encroachment which would reduce floodcarrying 
capacity of the channel so defined; inform 
affected interests at least annually that project 
will not provide complete protection from 
floods greater in magnitude than that which occurred 
in September 1912; and maintain and 
operate project works after completion. Board of 
County Commissioners, Washington County, 
local cooperating agency for Canonsburg- 
Houston reach of improvement and Chartiers 
Valley District Flood Control Authority, local 
cooperating agency for James G. Fulton Flood 
Protection Project provided formal assurance.of 
local cooperation which were accepted by District 
Engineer on July 12, 1967 and November 27, 
1967, respectively. Tri-party contract between 
Allegheny County Sanitary Authority, Chartiers 
Valley District Flood Control Authority and United 
States of America covering relocation of 
sanitary sewer facilities in James G. Fulton Flood 
Protection Project was approved April 4, 1968. 
Local interests have completed acquisition of 
rights-of-entry and arrangements for utility adjustments 
for Units 1, 2, 3 and 5 of James G. 
Fulton Flood Protection Project and for Unit 1 of 
Canonsburg-Houston reach. Local requirements 
for remaining two units are expected to be furnished 
when required. Non-federal contributions 
have been made in the amount of $3,859,690. 
Operations and results during fiscal year. New 
Work: James G. Fulton Flood Protection 
Project-Construction of Unit 3 under contract 
which was started in July 1971, was completed. 
Canonsburg-Houston Reach--Environmental 
improvements to project advanced to 62% completion 
under contract. Estimated flood control 
benefits achieved by the Chartiers Creek project 
through 30 June 1975 totaled $2,314,000. 
Condition at end offiscal year. James G. Fulton 
Flood Control Project-Construction of Unit 1 
was started in July 1968 and completed in 
September 1970 and turned over to local interests 
for operation and maintenance on June 25, 1971. 
Construction of Unit 2 was started in April 1970 
and was completed in April 1973. Construction of 
Unit 3 was started in July 1971 and was completed 
in December 1974. Construction of Unit 5 
was started in June 1972 and was completed in 
December 1973. Plans and specifications for Unit 
4 are complete. Canonsburg-Houston Reach- 
Construction of Unit 1 was started in December 
1968 and completed in March 1970 and turned 
over to local interests for operation and 
maintenance on August 10, 1970. Construction 
plans and specifications for Unit 2, the remaining 
unit of this reach, are complete. 
10. CONEMAUGH RIVER LAKE, 
OHIO RIVER BASIN, PA. 
Location. Dam is on Conemaugh River in Indiana 
and Westmoreland Counties, Pa., 7.5 miles 
above junction of Conemaugh River and 
Loyalhanna Creek, which form head of 
Kiskiminetas River. It is about 2 miles northeast 
of Tunnelton, Pa., and about 42 miles east of 
Pittsburgh, Pa. Reservoir is in Westmoreland 
and Indiana Counties, Pa. (See Geological Survey 
Charts for Latrobe, New Florence, and Elders 
Ridge, Pa.) 
Existing project. A flood control reservoir dam 
of concrete gravity type with a gate-controlled 
center spillway flanked by abutment sections 
joining valley sides and an earth embankment ending 
in right abutment. Project authorized by 
Flood Control Acts of 1936 and 1938. For further 
project description see Annual Report for 1962, 
page 1217. Completed project cost $45,684,411. 
Construction of additional facilities at recreation 
area is estimated to cost $6,000 (1975), raising the 
total project cost to $45,690,411. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control as required, 
and necessary repairs were made to 
structures and appurtenances at cost of $342,796. 
Reservoir levels were maintained near the 
minimum pool elevations throughout the 
summer-fall recreation season except for short 
periods when excess runoff was stored. Various 
flood reductions during January, February, and 
March 1975 were effected. Estimated flood control 
benefits achieved by this reservoir for fiscal 
year were $3,925,000; total flood control benefits 
through June 30, 1975 are $433,051,000. Activities 
under reservoir management program 
26-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
comprising sanitation measures, conservation, 
land management and operation and 
maintenance of public-use facilities were continued. 
Condition at end of fiscal year. Authorized project 
is complete. Reservoir is in operation as a unit 
of coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood 
heights in upper Ohio Valley, generally. Construction 
of dam and appurtenances was started 
in April 1949 and completed in December 1952. 
Furnishing and erection of 2 gantry cranes and 
14 crest gates by contract were started in 
November and December 1951, and completed in 
August and September 1953, respectively. 
Relocation of main line of Conemaugh division, 
Pennsylvania Railroad, was started by contract 
in April 1946 and completed in September 1950. 
Land acquired for dam, reservoir and railroad 
relocation consists of 7,635.1 acres in fee simple 
and flowage easements over 513.2 acres. 
11. CROOKED CREEK LAKE, OHIO 
RIVER BASIN, PA. 
Location. Dam is on Crooked Creek 6.7 miles 
above junction of creek with Allegheny River 
near Ford City, Pa., and about 32 miles northeast 
of Pittsburgh, Pa. (See Geological Survey Charts 
for Freeport and Elders Ridge, Pa.) 
Existing project. A flood control reservoir dam 
of earthfill type with separate uncontrolled saddle 
spillway and tunnel outlet works. Project was 
authorized by Flood Control Acts of 1936 and 
1938. For further project description see Annual 
Report for 1962, page 1213. Completed project 
cost $4,204,888. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operation and maintenances general: Reservoir 
was operated for benefit of flood control, as required, 
and necessary repairs were made to 
structures and appurtenances at cost of $237,078. 
Reservoir levels were maintained near the 
minimum pool elevations throughout the 
summer-fall recreation season except for short 
periods when excess runoff was stored. Estimated 
flood control benefits achieved by this 
reservoir for the fiscal year were $1,390,000; total 
benefits through June 30, 1975 are $101,569,000. 
Activities under reservoir management program 
comprising sanitation measures, conservation, 
land management, and operation and 
maintenance of certain public-use facilities continued. 
This work was limited in scope as Commonwealth 
of Pennsylvania has jurisdiction over 
recreation in reservoir area. 
Condition at end offiscal year. Authorized project 
is complete. Reservoir is in operation as a unit 
of coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood 
heights in upper Ohio Valley, generally. Construction 
of dam was started in March 1938 and 
completed October 1940. Land acquisition for 
project consists of 2,563.57 acres in fee simple and 
easements over 98.19 acres. 
12. DUBOIS, PA. 
Location. City of DuBois is on Sandy Lick 
Creek, 20 miles above its mouth at Brookville, 
Pa., and approximately 80 miles northeast of 
Pittsburgh, Pa. (See Geological Survey Charts for 
DuBois and Penfield, Pa.) 
Existing project. Consists of widening, deepening 
and straightening the channel of Sandy Lick 
Creek for a distance of about 20,000 feet from 
Larkeytown (Falls Creek) Bridge to Shaffer Road 
Bridge, with a supplemental pilot channel, 4,600 
feet downstream of Larkeytown (Falls Creek) 
Bridge. Improvement will contain a discharge of 
3,800 second-feet, equal to the maximum flood of 
record. Project was authorized by Flood Control 
Act of 1965. Estimated Federal cost for new work 
(1975) is $4,370,000; estimated non-Federal costs 
of lands and damages and utility adjustments are 
$850,000. 
Local cooperation. Local interests must provide 
without cost all lands and rights-of-way for construction 
and future maintenance; hold United 
States free from damages; and at least annually 
notify interests affected that project will not 
provide complete flood protection. Formal 
assurances of local cooperation executed by the 
City of DuBois on May 25, 1971 and the evidence 
of legal ability of the City to fulfill the assurances 
were accepted by the District Engineer on 
August 19, 1971. Arrangements for utility adjustments 
were completed and by letter dated 
April 24, 1972 the City of DuBois furnished unqualified 
right-of-entry for construction of Unit 
1. The City of DuBois granted the government 
right-of-entry for construction of Unit 2 on 19 
August 1974 and a compatible utility adjustment 
schedule was received. 
Operations and results during fiscal year.New 
work: Work on the supplement to the general 
design memorandum covering a study of the 
Beaver Run flood plain was completed and approved. 
Construction of Unit 2 was started under 
contract and as of 30 June 1975 was about 10 percent 
complete; estimated completion September 
1976. 
Condition at end of fiscal year. Construction of 
the first unit of the project was started on May 10, 
1972, completed on September 30, 1973 and 
transferred to City of DuBois for operation and 
maintenance on December 11, 1973. Construction 
26-6

PITTSBURGH, PA., DISTRICT 
of Unit 2 is progressing on schedule. 
13. EAST BRANCH, CLARION RIVER 
LAKE, OHIO RIVER BASIN, PA 
Location. Dam is in Elk County, Pa., on East 
Branch of Clarion River above Middle Fork, 7.3 
miles above junction of East and West branches of 
Clarion River at Johnsonburg, Pa., and about 105 
miles northeast of Pittsburgh, Pa. Reservoir is in 
Elk County, Pa. (See Geological Survey Chart for 
Mount Jewett, Pa.) 
Existing project. A reservoir for flood control 
and low water regulation. Dam isrolled-earthfill 
type with gate-controlled concrete tunnel under 
right abutment and a paved uncontrolled 
spillway on left abutment slope. Project was 
selected for construction under general 
authorization for Ohio River Basin in Flood Control 
Acts of 1938 and 1944. For further project 
description see Annual Report for 1962, page 
1206. Federal cost of completed project was $9,- 
382,773. Estimated cost (1975) of construction of 
additional recreation facilities for completed project 
is $171,800 raising total project cost to $9,- 
554,473. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for flood control and low-water 
regulation, as required, and necessary repairs 
were made to structures and appurtenances at 
cost of $202,754. Inflow into the lake was much 
above normal during the summer-fall period and 
the downstream flow schedule was easily maintained. 
The pool elevation generally fell through 
August, September, October, and November. 
Substantial reductions in flow during January, 
February, March, and June 1975 were effected 
by East Branch Dam along the Clarion River and 
to a lesser extent on the Allegheny and Ohio 
Rivers. Estimated flood control benefits achieved 
by this reservoir during fiscal year were $412,- 
000; total benefits through June 30, 1975, $26,- 
425,000. Some reservoir management activity 
was performed throughout the year comprising 
sanitation measures, conservation, land management 
and operation of public-use facilities. Work 
was limited in scope as bulk of reservoir lands are 
owned by Commonwealth of Pennsylvania. 
Condition at end offiscal year. Authorized project 
is complete. Reservoir is in operation for low 
water regulation purposes in Clarion River valley 
below and for flood control as a unit of coordinated 
reservoir system for protection of 
Pittsburgh and upper Ohio Valley, generally. 
Construction of dam was started in June 1947 and 
completed in July 1952. Land acquired for project 
consists of 287.2 acres in fee simple and flowage 
easements over 1,290.6 acres. 
14. ELKINS, W. VA. 
Location. On Tygart River in north-central 
Randolph County, W. Va., about 155 miles south 
of Pittsburgh, Pa. It is at downstream end of a 
long, broad reach of upper Tygart Valley, about 
75 miles above mouth of river. (See Geological 
Survey Chart for Elkins, W. Va.) 
Existing project. Provides flood protection by 
diverting flood discharges from upstream arm of 
loop of natural river channel into an artificial 
cutoff channel, thereby bypassing city of Elkins. 
Improvement is designed to accommodate discharges 
equivalent to maximum flood of 
reasonable expectancy. Project was authorized 
by 1938 Flood Control Act. For further project 
description see Annual Report for 1962, page 
1222. Federal cost of completed project is $1,772,- 
627; estimated non-Federal costs for lands, 
easements, and rights-of-way is $40,000. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Operation and maintenance, general: Routine inspections 
were made. Flood damages prevented 
by project for fiscal year 1974 were $716,000 
(corrected figure); none incurred during fiscal 
year 1975; cumulative total flood damages 
prevented to 30 June 1975, $1,991,000 (corrected 
figure). 
Condition at end of fiscal year. Project construction 
was started May 1946 and completed 
May 1949. Completed works, except that portion 
of channel maintained by Federal Government, 
has been operated and maintained by city of 
Elkins since March 31, 1949. Land acquired for 
project consists of 32 acres in fee simple and 
flowage easements over 526.04 acres. 
15. GIRTYS RUN, MILLVALE, PA. 
Location. Girtys Run rises in the Fox Ridge 
area of the southern portion of McCandless 
Township, Allegheny County, and flows generally 
southeast through Ross and Shaler Townships 
and the Borough of Millvale to enter the 
Allegheny River from the right bank at River 
Mile 3.6 above the "Point" at Pittsburgh. (See 
U.S. Geological Survey Chart for Pittsburgh, Pa., 
East.) 
Existing project. To decrease flooding conditions 
in the Borough of Millvale area, project 
would consist of lowering the existing channel 
bottom within the limits of the existing walls. The 
lowering would be accomplished by a 16-foot 
average bottom width of cut in rock or overburden 
averaging 4 feet in depth in the lower 
2,750 feet of the project and 2-1/2 feet in depth for 
26-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
the remaining portion. Existing masonry walls of 
the channel would be replaced and/or stabilized 
where required. Project was authorized for construction 
by the Chief of Engineers under 
authority of Section 205 of the 1948 Flood Control 
Act as amended. Estimated Federal cost for new 
work (1975) is $2,000,000; estimated non-Federal 
cost of lands, easements and rights-of-way, utility 
adjustments, and amount in excess of $2 million 
limitation established by Section 205 of the 1948 
Flood Control Act as amended, is $543,000. 
Local cooperation. Responsible local interests 
must provide, without cost to the United States, 
all lands, easements, rights of way, and borrow 
and spoil-disposal areas as necessary for construction; 
bear cost of all necessary relocations, 
removals, alterations and adjustments of 
buildings, highway and highway bridges, and 
water, sanitary sewer, and other utilities and 
related or special facilities; hold the United 
States free from damages due to the construction; 
establish and enforce channel limit lines to prevent 
encroachment on the improved channel; 
maintain and operate the project works after 
completion; at least annually notify affected interests 
that the project will not provide complete 
flood protection. Formal assurances of local 
cooperation, executed by the Borough of Millvale 
on June 17, 1975, were accepted by the District 
Engineer on June 20, 1975. The Commonwealth 
of Pennsylvania and the County of Allegheny, 
Pennsylvania, have each agreed to provide to the 
Borough of Millvale 50% of all estimated non- 
Federal costs. 
Operations and results during fiscal year. Final 
Detailed Project Report was approved April 22, 
1975. Final Environmental Impact Statement 
was filed with the Council of Environmental 
Quality on May 2, 1975. Plans and Specifications 
were completed and are under review. 
Condition at end of fiscal year. Final Detailed 
Project Report was approved; final Environmental 
Impact Statement filed with Council of Environmental 
Quality; Plans and Specifications 
were completed. 
16. JOHNSTOWN, PA. 
Location. In southwestern Cambria County, 
Pa., about 58 miles east of Pittsburgh, Pa. It is in a 
deep and comparatively narrow valley at junction 
of Stony Creek and Little Conemaugh River, 
which unite to form Conemaugh River. (See 
Geological Survey Chart for Johnstown, Pa.) 
Existing project. Provides for increased 
channel capacity by enlarging and realigning 
channels and protecting banks with concrete 
pavement. Improvement designed to accommodate 
discharges equivalent to those of March 
1936 flood, maximum natural flow of record, 
minimum of overbank flow and to practically 
eliminate damages therefrom. Project was 
authorized by Flood Control Acts of 1936 and 
1937. For further project descript; n see Annual 
Report for 1962, page 1215. Con pleted project 
cost $8,865,388. 
Local cooperation. Section 2, Flood Control Act 
of June 28, 1938, applies. 
Operations and results during fiscal year. 
Operation and maintenance, general: Routine inspections 
were made. Fiscal year cost of 
maintenance was $28,994. Flood damages 
prevented by project for fiscal year were estimated 
to be $112,000; cumulative total flood 
damages prevented to end of fiscal year are $91,- 
665,000. 
Condition at end of fiscal year. Project construction 
began in August 1938 and was completed 
November 1943. Footer protection for unit 
4 was completed in November 1949. For further 
details see page 1216 of Annual Report for 1962. 
Land acquired for project consists of flowage 
easements over 192 acres. 
17. KINZUA DAM AND ALLEGHENY 
RESERVOIR, OHIO RIVER BASIN, 
PA. AND N.Y. 
Location. Dam site is on Allegheny River 9 
miles above Warren, Pa., and 198 miles above 
mouth of river at Pittsburgh, Pa. Reservoir is in 
Warren and McKean Counties, Pa., and Cattaraugus 
County, N.Y. (See Geological Survey 
Charts for Warren and Kinzua, Pa.-N.Y., and 
Randolph and Salamanca, N.Y.) 
Existing project. Provides for construction of a 
reservoir for flood control, low water regulation, 
and recreation. Dam consists of a combination 
concrete gravity structure and rolled earth embankment 
with gate-controlled spillway and discharge 
conduits controlled by slide-gates in 
gravity section. For further details see Annual 
Report for 1962, page 1202. Project was authorized 
by Flood Control Acts of 1936, 1938, and 1941. 
Estimated cost of new work (1975) is $110,720,- 
000, including $2,020,000 for recreation facilities. 
Local cooperation. None required by law. 
Licenses. The Federal Power Commission 
granted a license to Pennsylvania Electric Company 
and Cleveland Electric Illuminating Company 
on December 28,1965, for the joint construction, 
operation and maintenance of a 325- 
megawatt pumped-storage installation (FPC 
Project No. 2280). The project is complete. 
Operations and results during fiscal year. New 
work: Land acquisition and negotiation of 
26-8

PITTSBURGH, PA., DISTRICT 
settlements continued; phase Ii landscaping at 
BcEid recreation area was essentially compieted 
under contract. Operation and 
maintenance, general: Reservoir was operated 
for benefit of flood control and low water regulation, 
as required, and necessary repairs were 
made to structures and appurtenances at cost of 
$1,314,975. Contract for repairs to the stilling 
basin was completed. Inflow into the reservoir 
was much above normal during the summer-fall 
period and the downstream flow schedule was 
easily maintained. Water levels were near the 
summer pool elevation throughout the recreation 
season. Significant flood reductions during 
January, February, March, and April 1975 were 
effected by Kinzua Dam along the Allegheny and 
Ohio Rivers. Estimated flood control benefits 
achieved by this reservoir for the fiscal year were 
$2,722,000; total to 30 June 1975, $258,941,000. 
Activities under reservoir management program 
comprising sanitation measures, conservation, 
land management, and operation and 
maintenance of public-use facilities were continued. 
Condition at end of fiscal year. Construction of 
project, initiated in February 1960 is essentially 
complete. Construction of dam was started in 
September 1960 and completed in December 
1965. Land acquired for project consists of 2,- 
651.44 acres in fee simple and flowage easements 
over 22,420.4 acres. 
18. LOYALHANNA LAKE, OHIO 
RIVER BASIN, PA. 
Location. Dam is on Loyalhanna Creek, 4.5 
miles above junction of creek with Conemaugh 
River at Saltsburg, Pa., and about 29 miles east of 
Pittsburgh, Pa. Reservoir is in Westmoreland 
County, Pa. (See Geological Survey Chart for 
Latrobe.) 
Existing project. A flood control reservoir dam 
of concrete gravity type with a gate controlled 
center spillway flanked by abutment sections 
joining valley sides, and an earth embankment 
section ending in left abutment. Project was 
authorized by Flood Control Acts of 1936 and 
1938. For further project description see Annual 
Report for 1962, page 1219. Completed project 
cost $5,452,862. Estimated cost of construction 
(1975) of recreation facilities is $68,000, raising 
the cost of project to $5,520,862. 
Loc l cooperation. None required by law. 
Op, itio,,s and results dr: j f 
Opei. Ooin .nd maintenalce, general: Reservo. 
was operated for benefit of flood control, as required, 
and necessary repairs were made to 
structures and appurtenances at cost of $228,142. 
Reservoir levels were maintained near the 
minimum pool elevation throughout the summerfall 
recreation season as inflows remained 
moderate. Estimated flood control benefits 
achieved by this reservoir for the fiscal year were 
$681,000; total benefits to 30 June 1975, $141,- 
163,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and 
maintenance of public-use facilities continued. 
Condition at end offiscal year. Authorized project 
is complete. Reservoir is in operation as a unit 
of coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood 
heights in upper Ohio Valley, generally. Construction 
of dam was started in October 1939 and 
completed in June 1942. Land acquired for project 
consists of 3,334.9 acres in fee simple and 
flowage easements over 86.7 acres. 
19. MAHONING CREEK LAKE, 
OHIO RIVER BASIN, PA. 
Location. Dam is on Mahoning Creek in 
Armstrong County, Pa., 21.6 miles above junction 
of creek with Allegheny River. It iS about 6.50 
miles southeast of New Bethlehem, Pa., and about 
51 miles northeast of Pittsburgh, Pa. Reservoir is 
in Armstrong, Indiana, and Jefferson Counties, 
Pa. (See Geological Survey Charts for Rural 
Valley and Smicksburg, Pa.) 
Existing project. A flood control reservoir dam 
of concrete gravity type with a gate-controlled 
center spillway flanked by abutment sections 
joining valley sides. Project was authorized by 
Flood Control Acts of 1936 and 1938. For further 
project description see Annual Report for 1962, 
page 1210. Completed project cost $6,421,345. Estimated 
(1975) cost of construction of recreation 
facilities is $34,000, raising total cost of project to 
$6,455,345. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control, as required, 
and necessary repairs were made to 
structures and appurtenances at cost of $261,222. 
Lake levels were maintained near the minimum 
pool .elevations throughout the summer-fall 
recreation season except for short periods when 
excess runoff was stored. Estimated flood control 
benefits achieved by this reservoir for the fiscal 
year were $2,348,000; total to 30 June 1975, $124,- 
740,000. Activities under reservoir management 
and maintenance of public-use facilities were 
continued. 
Condition at end offiscal year. Authorized project 
is complete. Reservoir is in operation as a unit 
of coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood 
26-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
heights in upper Ohio Valley, generally. Construction 
of dam was started in February 1939 
and completed in June 1941. Land acquired for 
project consists of 2,532.6 acres in fee simple and 
flowage easements over 83.5 acres. 
20. MICHAEL J. KIRWAN DAM AND 
RESERVOIR, OHIO 
Location. Dam site is on West Branch of 
Mahoning River which joins Mahoning River at 
Newton Falls, Ohio. It is 11 miles above mouth of 
branch and about 15 miles upstream from 
Warren, Ohio. Reservoir is in Portage County, 
Ohio (See Geological Survey Charts for Ravenna, 
Garrettsville, Chagrin Falls, and Kent, Ohio.) 
Existing project. Provides for construction of a 
reservoir for flood control, low-water regulation 
and recreation. Dam consists of a rolled-earth embankment 
structure with gate-controlled outlet 
works and an uncontrolled side-hill spillway 
through left abutment. For further description 
see Annual Report for 1962, page 1231 (West 
Branch Reservoir, Mahoning River, Ohio). Project 
was authorized by 1958 Flood Control Act 
(H. Doc. 191, 85th Cong., lst sess.), with local contribution 
requirements modified by Flood Control 
Act of 1960. Federal cost of completed project 
was $17,355,097. Local interests contributed $3,- 
230,000 during period of construction bringing 
total project cost to $20,585,097. Construction of 
additional recreational facilities for completed 
project is estimated to cost $54,000 (1975) raising 
total project cost to $20,639,097. 
Local cooperation. Local interests must contribute 
$5,200,000 for water for pollution abatement 
and for municipal and industrial water 
supply purposes, of which $3,230,000 was paid in 
cash during construction. Unpaid balance at time 
project is placed in operation, $1,970,000, will be 
paid in cash at that time or on an annual basis. Of 
the unpaid balance of contributed funds due and 
payable, payment in full of Trumbull County's 
share in the amount of $663,040 has been received. 
Mahoning County elected to pay their 
share ($1,306,960) in 50 annual installments of 
$50,323.32, including interest, and has paid 
$182,974.40 toward principal to date. Local interests 
have now contributed $4,076,014.40 
towards total of $5,200,000 non-Federal costs. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control and low 
flow augmentation, as required, and necessary 
repairs were made to structures and appurtenances 
at cost of $215,509. Inflow into the 
reservoir was above normal during the summerfall 
period and water levels remained above normal 
through the summer recreation season, falling 
to two feet below summer pool by Labor Day. 
Significant flood reductions during July and 
December 1974, January, February, March, and 
June 1975 were effected by Kirwan Dam along 
the Mahoning River. Estimated flood control 
benefits achieved by this reservoir for the fiscal 
year were $4,624,000. Total flood control benefits 
for this reservoir through June 30, 1975 are $15,- 
024,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management, and operation and 
maintenance of public-use facilities continued. 
Condition at end of fiscal year. Authorized project 
is complete and in operation for flood control 
and low water regulation purposes. Construction 
of dam and access road was started in May 1963 
and completed in November 1966. Land acquired 
for project consists of 6,298.7 acres in fee simple 
and flowage easements over 27.8 acres. Future 
work consists of provision on project lands of additional 
recreational facilities as required to 
serve public needs. 
21. MOSQUITO CREEK LAKE, OHIO 
RIVER BASIN, OHIO 
Location. Dam is on Mosquito Creek, 9 miles 
above junction of creek with Mahoning River at 
Niles, Ohio, and about 18 miles northwest of 
Youngstown, Ohio. (See Geological Survey 
Charts for Bristolville and Kinsman, Ohio, and 
Pennsylvania.) 
Existing project. A reservoir for flood control, 
low water regulation and water supply storage. 
Dam is rolled-earthfill type with outlet facilities 
through dam, and an uncontrolled natural 
wasteway to discharge overflow from reservoir. 
Project was selected for construction under 
general authorization for Ohio River Basin in 
1938 Flood Control Act. For further project 
description see Annual Report for 1962, page 
1228. Completed project cost $4,035,400. Construction 
of additional recreational facilities for 
completed project is estimated to cost $1,641,000 
(1975) raising total project cost to $5,676,400. 
Local cooperation. None required by law. 
Operations and results during fiscal year. 
Operation and maintenance, general: Reservoir 
was operated for benefit of flood control and low 
flow regulation as required, and necessary 
repairs were made to structures and appurtenances 
at cost of $238,892. Inflow into the 
lake was much above normal during the summerfall 
period. Storage was released to augment 
Berlin and Kirwan outflows for maintenance of 
the minimum flow schedule for Youngstown. 
Significant flood reductions during July and 
December 1974, January, February, March, and 
June 1975 were effected by this reservoir along 
26-10

PITTSBURGH, PA., DISTRICT 
the Mahoning River. Regulated flows at 
Youngstown, Ohio, for 122 days during the period 
July-November 1974 and May-June 1975 averaged 
658 cubic feet per second, representing 227 
percent of the natural low flow. This is the 21st 
complete year in which the City of Warren, Ohio 
diverted their water supply from Mosquito Creek 
Lake. Water withdrawal was 5.087 billion gallons 
or 15,604 acre-feet, equivalent to 13.9 million 
gallons per day. Estimated flood control benefits 
achieved by this reservoir for the fiscal year were 
$2,226,000. Total flood control benefits for this 
reservoir through June 30, 1975 are $24,092,000. 
Activities under reservoir management program 
comprising sanitation measures, conservation, 
land management and operation and 
maintenance of certain public-use facilities continued. 
This work was limited in scope as State of 
Ohio has jurisdiction over recreation in reservoir 
area. 
Condition at end of fiscal year. Authorized project 
is complete and in operation for flood control 
and low water regulation purposes in industrialized 
Mahoning and Beaver Valleys 
below. Construction of dam was started in July 
1943 and was ready for beneficial use January 
1944. Land acquired for project consists of 11,- 
180.6 acres in fee simple and flowage easements 
over 276.1 acres. State of Ohio has a license from 
Secretary of the Army for development and 
operation of recreation facilities in reservoir 
area. 
22. MUDDY CREEK DAM, PA. 
Location. In Crawford County, northwestern 
Pennsylvania, on Muddy Creek, a tributary of 
French Creek. Damsite is about 9 miles above 
mouth of Muddy Creek and about 15 miles 
northeast of Meadville, Pa. (See Geological Survey 
Chart for Union City, Pa. - N. Y.) 
Existing project. Provides for construction of 
flood control reservoir dam of rolled earth embankment 
non-gated type with uncontrolled sidehill 
type spillway. The uncontrolled lower outlet 
works will consist of a cut and cover conduit in the 
valley floor with invert at elevation 1160 m.s.l. 
The upper outlet works will be built at the right 
abutment to accommodate an invert elevation 
1188 m.s.l. Dam will be 6,900 feet long at top rising 
64 feet above streambed and provide for gross 
capacity of 19,400 acre-feet from a drainage area 
of 61.5 square miles. The project will be operated 
as one of three-reservoir system for reduction of 
flood stages in French Creek Basin between damsite 
and mouth, Allegheny River from Franklin, 
Pa., to Pittsburgh, Pa., inclusive, and upper Ohio 
River Valley. Existing project was authorized by 
1962 Flood Control Act. Estimated Federal cost 
for new work (1975) is $23,600,000. 
Local cooperation. Local interests must inform 
affected interests in French Creek Basin at least 
annually, in a manner satisfactory to District 
Engineer, that system of reservoirs of which 
Muddy Creek Dam is a part, will not provide 
protection against maximum floods. Pennsylvania 
Department of Forests and Waters has 
assumed responsibility of local cooperation for 
project. 
Operations and results during fiscal year. New 
work: Preconstruction planning was continued. 
Condition at end of fiscal year. Construction not 
started. General design and highways relocation 
design memoranda are complete. Real estate 
design memorandum for land required for 
relocation of State Route L. R. 697 is complete 
and plans for this relocation are 90 percent complete. 
Draft of supplement to general design 
memorandum covering conservation pool has 
been completed; negative report to be submitted. 
23. OHIO RIVER BASIN 
(PITTSBURGH DIST.) 
Location. Levees, floodwalls, channel improvements, 
and reservoirs/lakes in Ohio River 
Basin within Pittsburgh District. 
Existing project. Individual projects considered 
in comprehensive plan within Pittsburgh 
District. (See tables 26-B, 26-G and 26-H on Acts 
authorizing existing projects, local protection 
projects and reservoirs.) 
Operations and results during fiscal year. New 
work: None by the United States except as stated 
in individual projects. Completed local protection 
projects operated and maintained by local interests, 
other than those projects for which individual 
reports have been included, prevented 
flood damages of an estimated $7,812,000 during 
the fiscal year. 
Condition at end of fiscal year. Preliminary 
surveys and plans are complete for a number of 
projects included in comprehensive plan. Status 
of projects selected for construction under this 
authorization is given in individual reports. 
24. PUNXSUTAWNEY, OHIO RIVER 
BASIN, PA. 
Location. Borough of Punxsutawney is on 
Mahoning Creek in Jefferson County, Pa., about 
85 miles northeast of Pittsburgh, Pa. It is on a 
comparatively wide, alluvial flood plain about 52 
miles above mouth of stream and 30 miles above 
Mahoning Creek flood control dam. (See 
Geological Survey Charts for Punxsutawney and 
Smicksburg, Pa.) 
Existing project. Provides flood protection by 
channel enlargement, dikes, and walls. Improve- 
26-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
ment is designed to accommodate discharges 20 
percent greater than that of maximum flood of 
record. Project was authorized by 1938 Flood 
Control Act. For further project description see 
Annual Report for 1962, page 1209. Federal cost 
of completed project is $3,586,107. Non-Federal 
cost was $180,485. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Operation and maintenance, general: Operation 
activities and routine investigations and inspections 
were made. Flood damages prevented by 
project for fiscal year were estimated to be $2,- 
744,000; cumulative total to end fiscal year, $15,- 
659,000. 
Condition at end of fiscal year. Construction 
was accomplished by four construction units. 
Construction was started May 1946 and completed 
June 1950. Land acquired for project consists 
of perpetual easements over 72.6 acres. Completed 
works, except that portion of channel 
maintained by the Federal Government, have 
been operated and maintained by borough of 
Punxsutawney since July 31, 1950. 
25. RIDGWAY AND VICINITY, PA. 
Location. On Clarion River in and adjacent to 
borough of Ridgway, Elk County, Pa., approximately 
95 miles northeast of Pittsburgh, Pa. 
(See Geological Survey Chart for Ridgway, Pa.) 
Existing project. Provides for widening, 
deepening and realignment of existing channel 
beginning immediately upstream of mouth of Elk 
Creek and continuing downstream for approximately 
8,500 feet. Project was authorized 
for construction by Chief of Engineers under 
authority of section 205 of the 1948 Flood Control 
Act as amended. Estimated Federal cost of new 
work (1975) is $2,000,000; estimated non-Federal 
cost of lands, utility relocations and construction 
adjustments is $721,000. 
Local cooperation. Responsible local interests 
must provide without cost all lands, easements, 
rights-of-way and spoil disposal areas necessary 
for construction of project; bear cost of adjustments 
to utilities; hold and save United States 
free from damages due to construction work and 
maintenance of project; establish channel limit 
lines and prevent encroachment on the channel so 
delineated; at least annually, notify interests 
affected that improvement will not provide complete 
protection from floods greater than design 
conditions; and maintain project works after 
completion. By resolution passed September 14, 
1967, borough of Ridgway signified its intention 
to provide required assurances of local cooperation 
when request is made therefor. In letter of 
April 11, 1968 the borough expressed willingness 
to withstand Federal costs of the project exceeding 
the $1,000,000 limitation authorized by 
Section 205 of the Flood Control Act of 1948, as 
amended; however, since the Water Resource 
Development Act of 1974 (P.L. 93-251) increased 
the Federal limitation to $2,000,000 under certain 
specified conditions, which are considered 
applicable to the Ridgway Project, local cooperation 
assurances are being reviewed. 
Operations and results during fiscal year. New 
work: Review and reanalysis of project continued. 
Flood damages prevented by project for fiscal 
year were estimated to be $539,000; cumulative 
total to end fiscal year, $2,485,000. 
Condition at end of fiscal year. Review and 
reanalysis of project is continuing as a result of 
comments and recommendations from Pennsylvania 
Department of Environmental 
Resources, Federal and other agencies invited to 
comment upon the Environmental Impact Statement. 
26. ROWLESBURG LAKE, W. VA. 
Location. In Preston and Tucker Counties, 
north central West Virginia on Cheat River, a 
tributary of Monongahela River. Dam site is at 
upstream limits of town of Rowlesburg, W. Va. 
(See Geological Survey Chart for Kingwood, W. 
Va.) 
Existing project. Provides for construction of 
flood control reservoir dam of concrete gravity 
type with controlled outlets works and spillway 
1,695 feet in length and 271 feet high above 
streambed. Reservoir surface at full level would 
be 9,140 acres. Gross controlled reservoir storage 
would amount to 831,700 acre-feet from a 
tributary drainage area of 936 square miles. 
Authorized project purposes are flood control, 
water quality control, recreation, and hydroelectric 
power production. About 299,600 acre-feet of 
storage would be available for flood control during 
winter months and 250,800 acre-feet during 
the summer. Storage for control of water quality, 
production of hydroelectric power, and other uses 
of 571,500 acre-feet would, for the most part, 
serve several purposes simultaneously. Existing 
project was authorized by 1965 Flood Control 
Act. Estimated total cost for new work (1975) is 
$216,000,000, exclusive of power facilities. 
Local cooperation. Local interests are required 
to reimburse the Federal Government for the 
costs allocated to water quality control (cooling) 
presently estimated at $4,822,000, exclusive of interest. 
Also, in accordance with P.L. 89-72, 
Federal Water Project Recreation Act, local interests 
are required to bear one-half of the 
separable costs allocated to recreation and fish 
and wildlife enhancement, presently estimated at 
26-12

PITTSBURGH, PA., DISTRICT 
$2,823,000, exclusive of interest, and bear all cost 
of operation, maintenance and replacement, at an 
estimated cost of $470,000 annually. In addition, 
local interests are required to provide assurances 
that they will provide adequate direct waste 
treatment at the source within a reasonable 
period of time and preserve existing and 
augmented low flows for the intended water 
quality purposes. State of West Virginia, by letter 
of January 4, 1968, assumed this latter obligation 
and by letter dated April 10, 1970 declined participation 
in the recreation program under P. L. 
89-72. 
Operations and results during fiscal year. New 
work: Engineering studies were continued. 
Condition at end of fiscal year. The re-. 
evaluation of the project, as requested by the 
Governor of West Virginia, and work on completion 
of the general design memorandum continue. 
Storage of water for flow augmentation is being 
reconsidered by the U.S. Environmental Protection 
Agency. 
27. SHENANGO RIVER LAKE, OHIO 
RIVER BASIN, PA. AND OHIO 
Location. Dam is on Shenango River about 0.8 
mile above Sharpsville, Pa., and about 33 miles 
above junction of river with Mahoning River, 
which unite near New Castle, Pa., to form Beaver 
River. Reservoir is in Mercer County, Pa., and 
Trumbull County, Ohio. (See Geological Survey 
Chart for Kinsman, Ohio, and Shenango, Pa.) 
Existing project. A reservoir for flood control, 
low-flow augmentation, and recreation. Dam consists 
of a concrete gravity structure with gatecontrolled 
outlet works and an uncontrolled 
center spillway section. For further project 
description, see Annual Report for 1962, page 
1230. Project was authorized by 1938 Flood Control 
Act. Estimated cost for new work (1975) is 
$38,698,000 which includes $1,798,000 for future 
recreation facilities. 
Local cooperation. None required by law. 
Operations and results during fiscal year. New 
work: Payment of awards on land condemnation 
actions and for out of court settlements on certain 
tracts of land were effected. Contract for construction 
of Shenango public access areas, phases 
III and IV were completed. Operation and 
maintenance, general: Reservoir was operated 
for benefit of flood control and low flow augmentation, 
as required, and necessary repairs were 
made to structures and appurtenances at cost of 
$479,921. Inflow into the reservoir was much 
above normal during the summer-fall period and 
the downstream flow schedule, by providing 
augmentation of Pymatuning reservoir outflows, 
was easily maintained. Reservoir levels were 
near the summer pool elevation throughout the 
summer recreation season. Substantial flow 
reductions during November 1974, January, 
February, March, and June 1975 were effected 
by Shenango Dam along the Shenango River. Estimated 
flood control benefits achieved by this 
reservoir for the fiscal year were $245,000. Total 
flood control benefits for this reservoir through 
June 30, 1975 are $5,128,000. Activities under 
reservoir management program comprising 
sanitation measures, conservation, land management 
and operation and maintenance of publicuse 
facilities were continued. 
Condition at end offiscal year. Authorized project 
is essentially complete. Reservoir is in operation 
for low water regulation purposes in 
Shenango River valley below and for flood control 
as a unit of a coordinated reservoir system for 
protection of Shenango River valley and the 
Beaver and upper Ohio River valley, generally. 
Construction of dam was started in March 1963 
and completed in May 1965. Land required for 
project consists of 14,632.2 acres in fee simple and 
flowage easements over 197.7 acres. Future work 
consists of provision on project lands of additional 
recreation facilities as required to serve the 
public needs. 
28. STONEWALL JACKSON LAKE, W. VA. 
Location. In Lewis County, northern West 
Virginia, on the West Fork River, which joins the 
Tygart River at Fairmont, West Virginia to form 
the Monongahela River. Damsite is located at 
Brownsville, West Virginia, about 4 miles south 
of Weston and 72 miles above mouth of West Fork 
River at Fairmont, W. Va. (See Geological Survey 
Charts for Weston and Crawford, W. Va.) 
Existing project. Provides for construction of a 
reservoir for flood control, water supply, water 
quality control, area redevelopment and recreation. 
Dam would be of the concrete gravity type, 
95 feet high and 620 feet long. Outlet works will 
consist of five multi-level sluices, spillway will be 
uncontrolled. Storage capacity will be 74,650 
acre-feet controlling an area of 102 square miles. 
Project was authorized by 1966 Flood Control 
Act. Estimated initial Federal cost for new work 
(1975) is $106,000,000 (includes $8,950,000 reimbursement 
by non-Federal interests). 
Local cooperation. Local interests are required 
to make arrangements for repayment, under the 
provisions of the Water Supply Act of 1958, as 
amended, of that part of the construction cost and 
annual operation, maintenance and replacement 
costs allocated to municipal and industrial water 
supply, an amount presently estimated at $1,175,- 
000, for construction; and $4,800 annually for 
operation, maintenance and replacements. Also, 
26-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
in accordance with the Federal Water Project 
Recreation Act, local interests are required to administer 
project land and water areas for recreation 
and fish and wildlife enhancement, pay, contribute 
in kind or repay (which may be through 
user fees) with interest, one-half of the separable 
first cost of the reservoir project allocated to 
recreation and fish and wildlife enhancement, an 
amount presently estimated at $7,775,000; bear 
all costs of operation, maintenance and replacement 
of recreation and fish and wildlife lands and 
facilities, the amount involved being currently estimated 
on an average annual basis to be $170,- 
000; exercise to the full extent of their legal 
capability, control against removal of streamflow 
made available for water quality control; and contribute 
to the control of pollution of streams subject 
to low-flow augmentation by adequate treatment 
or other methods of controlling wastes at 
their source. The State on November 3, 1965 
provided assurances that it will exercise, to the 
full extent of its legal capability, control against 
removal of streamflow made available for water 
quality control; and contribute to the control of 
pollution of streams subject to low-flow augmentation 
by fully enforcing its laws which require 
adequate treatment or other methods of controlling 
wastes at their sources. The State of West 
Virginia reaffirmed the preceding assurances by 
letter dated July 7, 1970. Formal assurances from 
State of West Virginia together with certification 
from State Attorney General that the State has 
legal and financial ability to furnish such 
Assurances, were requested by letter dated 
August 3, 1971. Revised assurances, which 
deleted the requirement that the State of West 
Virginia "hold and save the United States free 
from damages resulting from water-rights 
claims due to construction and operation of the 
project" in conformance with PL 92-222, were requested 
from the State of West Virginia by letter 
dated January 13, 1972. The Governor of West 
Virginia signed the assurances on May 29, 1973. 
The assurances are ready for execution by the 
Government. The State of West Virginia on July 
1, 1969 furnished a letter of intent that it desires 
to participate in the recreational development of 
the project in accordance with the provisions of 
the Federal Water Project Recreation Act of 
1965. Draft of contract was given to State of West 
Virginia representatives on February 3, 1971. 
State law required approval of contract by the Attorney 
General. State submitted contract to Attorney 
General on March 1, 1971 for review. A 
revised draft of the recreation agreement 
between the Government and the State of West 
Virginia was forwarded to Director, Department 
of Natural Resources and the Deputy Attorney 
General, State of West Virginia on May 12, 1971. 
The State considered the planned initial recreation 
too costly to operate and suggested a revised 
plan to provide for more concentrated initial 
recreation development. A revised draft contract 
for cost sharing under PL 89-72 was submitted to 
the Director of Natural Resources for execution 
on March 10, 1972. To date, there has been no 
further action by the State of West Virginia. The 
City of Weston has executed the contract between 
the City and the United States, covering the 
water supply aspects of the project as it affects the 
City of Weston, which was forwarded to them on 
March 8, 1972. The contract has been approved 
by the State Attorney General and is now ready 
for execution by the Government. Although 
recognizing the potential benefit of including 
storage in the project for future water supply, the 
Clarksburg City Council, Clarksburg Water 
Board and Harrison County Court are unable to 
submit proper assurances of their intent to repay 
the allocated costs for the appropriate storage. 
Since there is no indication that acceptable 
assurances will be obtained from the City of 
Clarksburg for reimbursement, water supply 
storage for the City of Clarksburg has been 
deleted from the project. Legislation relieving 
Stonewall Jackson Lake, W. Va. of the requirements 
of Sec. 221, P.L. 96-611 was contained 
in Water Resources Development Act of 
1974 signed by the President on March 7, 1974. 
Operations and results during fiscal year. New 
work: Engineering and design studies continued. 
Plans and specifications for highway relocations 
(W.Va. Rt 30 Sec 1) were completed. Design 
memorandum for relocation of US Rt 19 was completed 
and approved. Work continues. Preparation 
of design memorandum covering Rt 30 Sec 2 
and remaining highways continues. Preparation 
of design memorandum for Power and Communications 
lines relocation continues. Preparation 
of plans for Phase I piping for Equitable Gas 
Company's compressor station was completed. 
Condition at end of fiscal year. General design 
and real estate design memoranda have been approved 
as a basis for continued planning and 
design. Architect-engineering firm has completed 
plans and specifications for site grading 
relative to relocation of Equitable Gas Company's 
compressor station. Design memorandum covering 
gas wells, lines and appurtenant facilities has 
been completed. Design memorandum covering 
relocation of Baltimore and Ohio Railroad 
facilities in project area has been completed and 
approved. Engineering and design studies continue 
along with efforts to secure required local 
cooperation agreement relative to recreation. 
26-14

PITTSBURGH, PA., DISTRICT 
29. TENMILE CREEK AT MARIANNA, 
PA. 
Location. On Tenmile Creek in and near 
Marianna and vicinity, Washington County, Pa., 
and about 13 miles southeast of the City of 
Washington, Pa. (See Geological Survey Chart 
for Amity, Pa.) 
Existing project. Flood protection along Tenmile 
Creek in villages of East Marianna and West 
Zollarsville by channel widening, deepening and 
minor realignment for a distance of 7,761 feet 
with the lower end of improvement beginning 
5,035 feet downstream of existing Jefferson 
Avenue highway bridge which connects the 
villages of East Marianna and West Zollarsville, 
Pa. Improvement is designed to eliminate 
damages from floods up to the magnitude of that 
of March 1963 with slight residual damage. Project 
was authorized for construction by Chief of 
Engineers under authority of section 205, 1948 
Flood Control Act, as amended. Estimated 
Federal cost for new work (1975) is $1,450,000; estimated 
non-Federal cost of lands, damages and 
relocations is $22,000. 
Local cooperation. Local interests must provide 
lands, rights-of-way and spoil disposal areas for 
construction; adjust utilities; hold United States 
free from damages; establish channel limit lines 
and prevent encroachment in channel so 
delineated; and maintain project works after 
completion in accordance with regulations 
prescribed by Secretary of the Army. Formal 
assurances of local cooperation provided by 
Bethlehem Township, the local cooperating agency, 
were accepted by District Engineer on May 
24, 1968. Financial and legal ability of township 
to fulfill the assurances have been provided. 
Operations and results during fiscal year. New 
work: Environmentally oriented problems consisting 
of economic restrictions and effects to the 
stream's aquatic ecosystem were resolved. 
Condition at end offiscal year. Construction not 
started. A new Environmental Impact Statement 
is being prepared and Plans and Specifications 
for the project are being modified to conform with 
current criteria. 
30. TIONESTA LAKE, OHIO RIVER 
BASIN, PA. 
Location. Dam is on Tionesta Creek, 1.25 miles 
above junction of creek with Allegheny River at 
Tionesta, Pa., and about 78 miles northeast of 
Pittsburgh, Pa. Reservoir is entirely in Forest 
County, Pa. (See Geological Survey Charts for 
Tionesta, Tidioute and Sheffield, Pa.) 
Existing project. A flood control reservoir dam 
of earthfill type with separate uncontrolled saddle 
spillway and tunnel outlet works. Project was 
authorized by Flood Control Acts of 1936 and 
1938. For further project description see Annual 
Report for 1962, page 1203. Federal cost of completed 
project was $5,213,401. Construction of additional 
recreation facilities for completed project 
is estimated to cost $1,679,700 (1975), raising 
total project cost estimate to $6,893,101. 
Local cooperation. None required by law. 
Operations and results during fiscal year. New 
work: Construction of Tionesta recreation area- 
Phase V-sewage and water systems, flush type 
comfort stations and site improvements was completed. 
Construction of Sewage System, Public 
Use Facilities, Phase VI was started under contract 
and advanced to 61% completion. Operation 
and maintenance, general: Reservoir was 
operated for benefit of flood control and low flow 
augmentation, as required, and necessary repairs 
were made to structures and appurtenances at a 
cost of $272,718. Reservoir levels were maintained 
near the minimum pool elevation 
throughout the summer-fall recreation season except 
for short periods when excess runoff was 
stored. Various flood reductions were effected by 
this reservoir during January, February, and 
March 1975. Estimated flood control benefits 
achieved by this reservoir for this fiscal year were 
$1,578,000. Total flood control benefits for this 
reservoir through June 30, 1975 are $137,284,000. 
Activities under reservoir management program 
comprising sanitation measures, conservation, 
land management and operation and 
maintenance of public-use facilities continued. 
Condition at end of fiscal year. Authorized project 
is complete. Reservoir is in operation as a unit 
of coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood 
heights in upper Ohio Valley, generally. Construction 
of dam was started in May 1938 and 
completed in January 1941. Land acquired for 
project consists of 2,797.3 acres in fee simple and 
flowage easements over 13.0 acres. Future work 
consists of provision on project lands of additional 
recreational facilities as required to serve public 
needs. 
31. UNION CITY LAKE, PA. 
Location. In Erie County, northwestern Pennsylvania, 
on French Creek, a tributary of 
Allegheny River. Damsite is 24 miles upstream 
from Cambridge Springs, Pa., and 41 miles upstream 
from Meadville, Pa. (See Geological Survey 
Chart for Union City, Pa.-N. Y.) 
Existing project. Provides for construction of 
flood control reservoir dam of earth embankment 
nongated type with uncontrolled side-channel 
spillway. Outlet works will consist of a lower out- 
26-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
let located in valley floor constructed of reinforced 
concrete conduit 8 feet by 4.5 feet and an 
upper outlet consisting of an uncontrolled slot 9.5 
feet wide through the north end of the ogee weir in 
the spillway. Dam will be 1,420 feet long at top 
rising 88 feet above streambed and provide gross 
capacity of 47,640 acre-feet from a drainage area 
of 222 square miles. Project was modified to 
provide for a conservation pool and addition of 
recreation facilities. On 5 November 1974, a 
referendum proposal was defeated by the constituents 
of Erie County in regard to the costsharing 
for constructing of recreation facilities. 
In view of the foregoing, all action toward implementation 
of the authorized project modification 
has been discontinued. Reservoir will be 
operated as one of three-reservoir system for 
reduction of flood stages in French Creek Basin 
between damsite and mouth, Allegheny River 
from Franklin, Pa., to Pittsburgh, Pa., inclusive, 
and upper Ohio River Valley. Existing project 
was authorized by 1962 Flood Control Act. Estimated 
Federal cost for new work (1975) is $23,- 
300,000. 
Local cooperation. Local interests are required 
to inform affected interests in French Creek 
Basin at least annually, that the system of reservoirs 
of which Union City Lake is a part will not 
provide protection against maximum floods. 
Also, in accordance with Public Law 89-72, 
Federal Water Project Recreation Act, local interests 
are required to bear one-half of the 
separable costs allocated to recreation, presently 
estimated at $3,788,000, exclusive of interest, and 
bear all cost of operation, maintenance and 
replacement at an estimated cost of $121,000. On 
November 10, 1964, the Department of Forests 
and Waters of the Commonwealth of Pennsylvania 
furnished formal assurances of local 
cooperation in respect to notifying local interests 
at least annually that the system of reservoirs will 
" not provide protection against maximum floods. 
A referendum on the ballot during the November 
1974 election regarding the approval to costshare 
the maintenance of a summer pool was 
defeated by the local voters. 
Operations and results during fiscal year. New 
work: Settlements in connection with the acquisition 
of land were completed; construction of an 
overlook and public access facilities at the dam 
was completed under contract. Operation and 
maintenance, general: Maintenance of the structure 
and appurtenances was performed during 
the year at cost of $92,927. This dam acted as an 
uncontrolled detention type dam during the fiscal 
year. Significant flood reductions during 
November 1974, January, February, March, and 
June 1975 were effected by Union City Dam along 
French Creek. Estimated flood control benefits 
achieved by this reservoir for the fiscal year were 
$1,088,000. Total flood control benefits for this 
reservoir through June 30, 1975 are $3,785,000. 
Condition at end of fiscal year. Initial highway 
relocations were completed in October 1968 and 
remaining highway relocations were completed 
in May 1972. Construction of the dam was started 
in July 1968 and completed in September 1971. 
Land acquired for project consists of 465.2 acres 
in fee simple and flowage easements over 2,152.6 
acres. 
32. WOODCOCK CREEK LAKE, PA. 
Location. In Crawford County, northwestern 
Pennsylvania, on Woodcock Creek, a tributary of 
French Creek. Damsite is about 4.1 miles above 
mouth of Woodcock Creek and about 5 miles 
northeast of Meadville, Pa. (See Geological Survey 
Chart for Meadville, Pa.) 
Existing project. Provides for construction of 
flood-control reservoir dam of rolled earth embankment 
type, gate controlled outlet works with 
a 6 foot wide by 7.75-foot-high conduit and uncontrolled 
saddle spillway on the left abutment. Dam 
will be 4,650 feet long at top rising 90 feet above 
streambed and provide for gross capacity of 20,- 
000 acre-feet from a drainage area of 46 square 
miles. Reservoir will be operated as one of threereservoir 
system for reduction of flood stages in 
French Creek Basin between damsite and mouth, 
Allegheny River from Franklin, Pa., to 
Pittsburgh, Pa., inclusive, and upper Ohio River 
Valley. Project was authorized for flood control 
and recreation by 1962 Flood Control Act. 
Storage for water quality control was added to 
the project during the preconstruction planning 
stage. Estimated Federal cost for new work 
(1975) is $18,525,000. 
Local cooperation. Local interests must inform 
affected interests in French Creek Basin at least 
annually, in a manner satisfactory to District 
Engineer, that a system of reservoirs of which 
Woodcock Creek Lake is a part, will not provide 
protection against maximum floods. Pennsylvania 
Department of Forests and Waters 
assumed responsibility of local cooperation for 
project. 
Operations and results during fiscal year. New 
work: Work on the operation and maintenance 
complex and Bossard Run recreation facilities 
(right bank) was completed. Additions and 
alterations at recreation areas continued under 
contract. Work at Stainbrook Outlet was 67% 
completed. Preparation of the master plan was 
completed and submitted for approval. Operation 
and maintenance, general: Maintenance of the 
structure and appurtenances was performed at a 
cost of $180,854. Filling of this reservoir began on 
January 22, 1974 and minimum pool elevation, 
26-16

PITTSBURGH, PA., DISTRICT 
1162.5, was reached on January 24, 1974. Inflow 
into the lake was much above normal during the 
summer-fall period and the downstream flow 
schedule was easily maintained. Lake levels were 
near the summer pool elevation throughout the 
summer recreation season. Various flood reductions 
during July and November 1974, January, 
February, March, and June 1975 were effected 
by this reservoir along French Creek. Estimated 
flood control benefits achieved by this reservoir 
for the fiscal year were $128,000; total through 
June 30, 1975, is $189,000. 
Condition at end of fiscal year. Authorized project 
is essentially complete. Reservoir is in operation 
for reduction of flood stages in French Creek 
Basin between damsite and mouth, Allegheny 
River, from Franklin, Pa. to Pittsburgh, Pa., inclusive, 
and upper Ohio River Valley. Construction 
of dam was started in July 1970 and completed 
in July 1973. Remaining major item of 
work is the construction of the operation and 
maintenance complex and the Bossard Run 
recreation facilities which is 23 percent complete. 
Land acquired for project consists of 1,733.2 acres 
in fee simple and flowage easements over 0.6 acre. 
33. YOUGHIOGHENY RIVER LAKE, 
OHIO RIVER BASIN, PA. AND MD. 
Location. Dam is on Youghiogheny River about 
74.2 miles above its junction with Monongahela 
River at McKeesport, Pa. It is 1.2 miles upstream 
from Confluence, Pa., and about 57 miles 
southeast of Pittsburgh, Pa. Reservoir is in 
Fayette and Somerset Counties, Pa., and Garrett 
County, Md. (See Geological Survey Charts for 
Confluence, Pa., Accident, Md., West Virginia 
and Pennsylvania.) 
Existing project. Reservoir for flood control, 
navigation aid, and pollution abatement purposes. 
Dam is rolled-earthfill type with separate 
uncontrolled side channel spillway and tunnel 
outlet works. Project was selected for construction 
under general authorization for Ohio River 
Basin in 1938 Flood Control Act. For further project 
description see Annual Report for 1962, page 
1223. Federal cost of completed project was $9,- 
674,904. Construction of additional recreation 
facilities for completed project is estimated to 
cost $1,929,400 (1975), making total project cost 
estimate $11,604,304. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Construction of Phase III Tub Run recreation 
area, consisting of water and sewage 
systems, flush type comfort station and camping 
spurs was completed; construction of Phase IV, 
Tub Run recreation area, consisting of parking 
facilities, comfort stations, water and sewage 
systems and sewage ejector station was also completed. 
Operation and maintenance, general: 
Reservoir was operated for benefit of flood control, 
as required, and necessary repairs were 
made to structures and appurtenances at cost of 
$585,682. Inflow into the lake was above normal 
during the summer-fall period. The downstream 
flow schedule was maintained through 
November by use of 110,000 acre-feet of storage 
withdrawn from the lake. The pool level fell 12 
feet by Labor Day, about 8 feet above the normal 
for that date. Significant flood reductions during 
December 1974, February and April 1975 were 
effected by Youghiogheny Dam along the 
Youghiogheny and Upper Ohio Rivers. Estimated 
flood control benefits achieved by this 
reservoir for the fiscal year were $723,000. Total 
flood control benefits for this reservoir through 
June 30, 1975 are $96,787,000. Activities under 
reservoir management program comprising 
sanitation measures, conservation, land management, 
and operation and maintenance of publicuse 
facilities were continued. 
Condition at end of fiscal year. Authorized project 
is complete. Reservoir is in operation for flood 
control, navigation, and pollution abatement purposes. 
For flood control, reservoir is operated as a 
unit of coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood 
heights in upper Ohio Valley, generally. Construction 
of dam was started June 1940 and completed 
May 1944. Land acquired for project consists 
of 3,914.9 acres in fee simple. A license was 
issued Commonwealth of Pennsylvania covering 
fish conservation and management in Pennsylvania 
portion of reservoir. Future work consists 
of provision on project lands of additional 
recreational facilities as required to serve public 
needs. 
34. YOUNGSTOWN, OHIO 
Location. In Mahoning County within city 
limits of Youngstown, along lower reaches of 
Crab Creek, a tributary of Mahoning River. (See 
Geological Survey Chart for Youngstown, Ohio.) 
Existing project. Provides for widening, 
deepening, and paving, with some realignment, 
channel of lower Crab Creek for about 2.2 miles 
above its mouth. Project would eliminate 
damages in Crab Creek area from all floods up to 
that of January 1959 flood of record and would 
greatly reduce damages that might be associated 
with greater floods. Project was authorized by 
Flood Control Act of 1962. Estimated Federal 
cost for new work (1975) is $3,695,000; estimated 
non-Federal cost of lands, damages, and construction 
adjustments is $500,000. 
Local cooperation. Fully complied with. 
26-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. New 
work: Settlement was reached on contractor's 
claim for suspension of work. 
Condition at end of fiscal year. Construction of 
project was started in June 1970 and was completed 
in March 1973. Transfer of project to City 
of Youngstown for operation and maintenance 
remains to be accomplished. 
35. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests furnish 
assurances that they will maintain and operate 
certain local protection projects after completion 
in accordance with regulations prescribed by 
Secretary of the Army. District Engineers are 
responsible for administration of these 
regulations within boundaries of their respective 
districts. During this fiscal year maintenance inspections 
were made of 32 projects transferred to 
local interests for maintenance and operation as 
listed in table at end of chapter. Local interests 
were advised as necessary, of measures required 
to maintain these projects in accordance with 
standards prescribed by regulations. Inspection 
of completed flood control works and dates of inspections 
are set forth in table 26-I. 
Fiscal year costs were $48,681. Total cost to 
June 30, 1975 was $297,378. 
36. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 26-J on other authorized flood control 
projects. 
37. FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization) 
(See table 26-K on flood control work under 
special authorization.) 
Flood control and coastal emergencies (Public 
Law 99, 84th Cong., and antecedent legislation) 
Fiscal year costs were $250,260, of which $23,- 
139 was for advance preparation, $149,691 for 
emergency operations and $77,430 for rehabilitation. 
General Investigations 
38. SURVEYS 
Fiscal year costs were $597,601, of which $525,- 
073 was for flood control studies, $16,884 for 
special studies and $55,644 for review of 
authorized projects. 
39. COLLECTION AND STUDY OF 
BASIC DATA 
Collection and study of basic data for flood 
plain information studies were made during the 
fiscal year at a cost of $312,381. (See Table 26-L 
Completed Flood Plain Studies.) 
40. RESEARCH AND DEVELOPMENT 
Hydrologic studies consisting of collection and 
analysis of hydrologic and hydraulic data were 
performed during year at cost of $5,924. 
26-18

PITTSBURGH, PA., DISTRICT 
TABLE 26-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Allegheny River, 
Pa. 
3. Monongahela 
River, Pa. and 
W. Va. 
5. Tygart River Lake, 
W. Va. 
7. Allegany, N.Y. 
8. Berlin Lake 
Ohio River Basin, 
Ohio 
Federal Funds) 
Contributed 
unds) 
9. Chartiers 
Creek, Pa. 
Federal Funds) 
Contributed 
unds) 
10. Conemaugh River 
Lake Ohio 
River Basin, Pa. 
11. Crooked Creek 
Lake, Ohio 
River Basin, Pa. 
12. Dubois, Pa. 
13. East Branch, 
Clarion River 
Lake, Ohio 
River Basin, Pa. 
14. Elkins, W. Va. 
15. Girtys Run, 
Millvale, Pa. 
16. Johnstown, Pa. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
822,700 
809,637 
127,839 
113,414 
2,215,600 
2,319,080 
164,200 
167,334 
196,700 
441,449 
347,000 
289,259 
2,669,800 
2,675,502 
698,433 
1,216,197 
142,400 
145,812 
120,300 
118,127 
497,200 
71,985 
162,300 
138,038 
-2,100 
884 
48,000 
23,009 
1,179,600 
1,001,519 
15,083 
38,417 
2,199,300 
2,313,247 
202,200 
185,526 
30,000 
174,217 
365,900 
377,709 
4,885,000 
4,761,587 
574,217 
723,665 
315,200 
137,078 
267,050 
119,126 
700,000 
582,475 
159,700 
167,013 
300 
450 
16,740 
1,453,300 
1,584,822 
-11,712 
1,371 
2,592,000 
2,532,799 
243,000 
251,567 
3,815 
46,000 
18,884 
425,500 
471,552 
2,400,000 
2,803,318 
308,300 
119,936 
211,600 
297,430 
159,600 
231,280 
460,000 
478,926 
155,000 
169,185 
9,000 
7,718 
68,000 
65,442 
1,717,200 
1,706,019 
175,000 
141,197 
3,540,200 
3,618,721 
396,300 
359,113 
32,000 
56,945 
158,000 
120,131 
440,300 
446,134 
100,000 
-78,000 
1,330,588 
32,740 
249,900 
342,796 
156,400 
237,078 
500,000 
314,587 
195,300 
202,754 
10,000 
10,475 
120,000 
138,624 
18,157,860' 
18,157,8601 
24,411,7202 
24,334,5182 
127,973,0233 
127,911,7233 
72,611,9144 
72,574,1574 
18,431,8445 
18,431,8446 
2,908,663 
2,858,157 
64,866 
63,626 
8,182,3766 
8,111,8627 
3,755,996 
3,746,638 
100,000 
18,589,203 
18,250,384 
3,859,690 
3,553,818 
45,684,4118 
45,684,4118 
2,001,132 
1,995,943 
4,204,8889 
4,204,8889 
2,093,682 
2,088,846 
2,370,200 
1,599,489 
9,524,60110 
9,524,60110 
1,745,707 
1,745,500 
1,772,627 
1,772,627 
75,987 
75,111 
246,000 
245,999 
8,865,38811 
8,865,38811 
26-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 26-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
Maint. 
Approp. 11,600 2,000 52,000 20,000 519,896 
Cost 12,977 2,041 42,558 28,994 519,359 
17. Kinzua Dam & New Work 
Allegheny Approp. -25,000 390,000 90,000 375,000 108,684,49312 
Reservoir, Ohio Cost 768,823 790,147 163,511 379,052 108,552,67612 
River Basin, Pa. Maint. 
and N.Y. Approp. 303,800 1,767,150 399,500 1,221,700 4,554,192 
Cost 276,426 384,253 1,727,892 1,314,975 4,547,869 
(Contributed New Work 
Funds) Contrib. - 100,000 - - 100,000 
Cost - 89,550 10,450 - 100,000 
18. Loyalhanna New Work 
Lake, Ohio Approp. - - - - 5,452,86213 
River Basin, Pa. Cost - - - - 5,452,86213 
Maint. 
Approp. 144,400 146,850 146,000 234,250 2,108,802 
Cost 137,068 151,482 150,396 228,142 2,100,574 
19. Mahoning Creek New Work 
Lake, Ohio Approp. - - - - 6,421,34514 
River Basin, Pa. Cost - - - - 6,421,34514 
Maint. 
Approp. 223,300 230,100 307,800 236,900 2,356,864 
Cost 139,858 266,552 333,993 261,222 2,354,845 
Rehab. 
Approp. - - - - 47,033 
Cost - - - - 47,033 
20. Michael J. Kirwan New Work 
Dam and Reservoir, Approp. 18,900 16,030 - - 17,355,0971' 
Ohio Cost 85,665 25,150 - - 17,355,09715 
(Federal Funds) Maint. 
Approp. 203,400 159,550 213,150 192,100 1,571,028 
Cost 420,205 180,906 190,613 215,509 1,567,655 
(Contributed Funds) New Work 
Contrib. - - - - 3,230,000 
Cost - - - - 3,230,000 
21. Mosquito Creek New Work 
Lake, Ohio Approp. - - - 65,000 4,100,40016 
River Basin, Ohio Cost - - - 64,797 4,100,19717 
Maint. 
Approp. 109,900 141,678 206,900 184,800 1,945,838 
Cost 156,319 167,531 155,029 238,892 1,943,588 
22. Muddy Creek New Work 
Dam, Pa. Approp. 54,313 - 5,000 1,200 385,513 
Cost 46,610 22,370 5,000 647 384,960 
23. Ohio River New Work 
Basin, Pittsburgh, Approp. -63,513 - - - 985,19718 
Pa. District Cost 27,275 - - - 985,19718 
Consolidated 
24. Punxsutawney, New Work 
Ohio River Approp. - - - - 3,586,10719 
Basin, Pa. Cost - - - - 3,586,10719 
Maint. 
Approp. 30,400 - 10,000 21,000 284,700 
Cost 32,822 24,516 522 30,398 284,287 
25. Ridgway New Work 
and vicinity, Approp. -3,500 - -12,000 - 114,464 
Pa. Cost 4,760 3,242 7,239 4,106 108,368 
26. Rowlesburg New Work 
Lake, W.Va. Approp. -94,000 200,000 - -1,200 2,739,884 
Cost 293,092 97,829 142,403 101,900 2,671,314 
27. Shenango River New Work 
Lake, Ohio Approp. 1,513,000 1,308,352 291,000 19,000 37,841,90120 
River Basin, Pa. Cost 1,026,967 375,481 1,063,244 518,304 37,562,40321 
and Ohio Maint. 
Approp. 279,300 495,450 376,500 456,200 2,356,647 
Cost 271,318 377,449 476,590 479,921 2,343,502 
26-20

PITTSBURGH, PA., DISTRICT 
TABLE 26-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
28. Stonewall New Work 
Jackson Lake Approp. 2,476,700 1,026,000 -1,280,000 446,000 4,272,200 
W. Va. Cost 657,995 557,461 536,800 570,206 3,502,336 
29. Tenmile Creek New Work 
at Marianna, Pa. Approp. 248,300 -695,000 - - 94,800 
Cost 5,736 13,548 3,960 2,657 94,641 
30. Tionesta Lake, New Work 
Ohio River Approp. -53,200 285,000 273,000 213,000 6,711,00522 
Basin, Pa. Cost 194,658 183,247 308,347 229,166 6,590,70623 
Maint. 
Approp. 243,600 228,650 234,650 267,400 3,225,854 
Cost 255,759 223,580 246,224 272,718 3,222,660 
31. Union City New Work 
Lake, Pa. Approp. 1,628,600 360,000 500,000 - 14,548,800 
Cost 2,084,028 304,806 308,753 357,889 14,536,851 
Maint. 
Approp. - 12,500 73,000 90,500 176,000 
Cost - 5,883 76,283 92,927 175,093 
32. Woodcock Creek New Work 
Lake, Pa. Approp. 4,866,000 5,400,000 993,000 338,000 18,862,700 
Cost 5,626,799 3,601,558 2,721,837 795,637 18,646,057 
Maint. 
Approp. - 21,850 176,400 177,000 375,250 
Cost - 20,372 172,831 180,854 374,057 
'33. Youghiogheny New Work 
River Lake, Approp. 62,700 335,000 301,000 34,000 10,898,27224 
Ohio River Cost 192,643 106,370 322,828 237,092 10,894,45825 
Basin, Pa. and Md. Maint. 
Approp. 316,600 260,850 463,000 581,250 3,859,960 
Cost 310,622 274,036 452,551 585,682 3,841,920 
34. Youngstown, New Work 
Ohio Approp. 1,638,500 214,500 43,280 - 3,694,711 
Cost 1,300,749 351,126 152,674 981 3,679,$80 
(Contributed Funds) New Work 
Contrib. - - - - 152,200 
Cost 2,850 26,583 8,475 - 91,501 
1. Includes $2,453,737 from emergency relief funds and 
$1,250,049 from public works funds. 
2. Includes $64,354 public works acceleration, executive 
funds (1963). 
3. Includes $5,420,541 for new work for previous project. 
4. Includes $22,549 public works acceleration, executive 
funds (1963) and $742 for maintenance for previous 
project. 
5. Includes $1,999,995 emergency relief funds and $10,- 
000,000 public works funds. 
6. Includes $1,084,000 Code 711 funds and $809,700 
Code 712 funds. 
7. Includes $1,013,486 Code 711 funds and $809,699 
Code 712 funds. 
8. Includes $5,351 from emergency relief funds. 
9. Includes $63,788 from emergency relief funds. 
10. Includes $141,828 Code 711 funds. 
11. Includes $33,423 from emergency relief funds. 
12. Includes $2,791 from emergency relief funds. 
13. Includes $7,339 from emergency relief funds. 
14. Includes $25,671 emergency relief funds. 
15. Includes $53,900 Code 711 funds. 
16. Includes $65,000 Code 711 funds. 
17. Includes 64,797 Code 711 funds. 
18. Includes 8,914 from emergency relief funds. 
19. Excludes $180,485 for new work expended from contributed 
funds. 
20. Includes $963,100 Code 711 funds. 
21. Includes $1,345,206 Code 711 funds. 
22. Includes $1,221,704, Code 711, $275,900 Code 712 and 
$24,201 emergency relief funds. 
23. Includes $1,101,403 Code 711, $275,900 Code 712 and 
$24,201 emergency relief funds. 
24. Includes $1,223,368 Code 711 funds. 
25. Includes $1,219,554 Code 711 funds. 
26-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 26-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 5, 1886 
June 3, 1896 
July 25, 1912 
July 3, 1930 
Aug. 30, 19351 
Aug. 30, 19351 
June 26, 19342 
Mar. 3, 1899 
June 13, 1902 
Mar. 3, 1905 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 4, 1913 
Sept. 22, 1922 
July 3, 1930 
Jan. 31, 19313 
June 26, 19344 
May 17, 1950 
ALLEGHENY RIVER, PA, (See Section 1 of Text) 
For lock and dam 1. (Fixed dam contemplated. 
Sept. 29, 1891 Secretary of War authorized change 
to a movable dam.) 
For locks and dams 2 and 3 
For locks and dams 4 to 8, inclusive 
For a depth of 9 feet in the lower 61 miles. 
Replace lock and dam 1 by a dredged channel, 9 feet 
deep and 200 feet wide up to lock 2, and construct 
new locks and dams 2 and 3, to replace existing locks 
and dams 2 and 3. 
Construct lock and dam 9, raising crest of dam 8, and 
dredging a navigable channel in head of pool 8. 
Annual Report 1886,p.1545,and 
Annual Report, 18 9 1,p.2366. 
H. Doc. 204, 54th Cong., 
1st sess. and Annual Report, 
1896, p. 2212 
H. Doc. 540, 62nd Cong., 2d 
sess. 
H. Doc. 356, 71st Cong., 
2d sess. 
Rivers and Harbors Committee, 
Doc. 16, 72d Cong., 
1st sess. 
H. Doc. 721, 71st Cong., 
3d sess., and Rivers and 
Harbors Committee, Doc. 27, 
73d Cong., 2d sess. 
Operation and care of locks and dams provided for with 
funds from War Department appropriation for rivers 
harbors. 
MONONGAHELA RIVER,PA.AND W. VA.(See Section 3 of Text)Annual Report 
Enlarge and improve lock and dam 6; additional works at p. 2423. 
lock 3; new repair steamer and new dredge boat with 
equipment; all at an estimated cost of $185,556. 
Rebuild lock and dam 2 at estimated cost of $655,961. Annual Report, 1 
(Estimate increased in 1910 to $698,961). p. 1756. 
Acquisition of land and additional improvements at Annual Report, 1 
5 and 6 at a cost of $7,850. p. 460. 
Rebuild lock and dam 3 at estimated cost of $589,196. H. Doc. 209, 58th 
2d sess. 
Reconstruct lock and dam 5 at estimated cost of $756,042. H. Doc. 209, 58th 
Reconstruct lock and dam 6 at estimated cost of 
$356,400. (Estimate increased in 1916 to 
418,860.) 
Additional improvements at estimated cost as follows: 
Guide walls and guard walls, 1 to 6, $1,255,130; 
Lengthen land chamber of lock 3 to 720 feet, $787,722; 
New chamber (360 feet long), lock 4, $699,786;Lock and 
dam 7, $1,161,241; Lock and dam 8, $1,165,758; Lock and dam 
7 (second chamber), $419,126; Lock and dam 8 )second 
chamber), $504,465; Reconstruct dam 4, $397,211; Marine 
ways, repair plant, office and warehouse, $250,000, for a 
total of $6,640,439. 
Construct new locks and dam 2.5 miles below existing 
structure, at estimated cost of $2,175,000 in lieu of 
work authorized at old lock and dam 4. 
Chief of Engineers authorized to locate new locks and 
dam 4 above existing structure and on such site as 
they may deem most desirable. 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Modification of existing project as follows: 
Provide 2 new locks and dams similar to 
Morgantown lock and dam to replace existing locks 
and dams 12 to 15, inclusive. 
Provide a movable crest on existing dam 8 to raise 
existing pool-full elevation 4 feet. 
Provide a navigation channel of 300-foot minimum 
bottom width and a 9-foot project depth above 
lock and dam 8. 
Provide an extension of navigable channel of upper 
Monongahela River, into lower Tygart River for 2.1 
miles at a maximum bottom width of 200 feet and a 
9-foot project depth. 
909, 
904, 
Cong., 
Cong., 
2d sess. 
H. Doc. 1217, 62d Cong., 
3d sess. 
H. Doc. 288, 67th Cong., 
2d sess. 
Rivers and Harbors Committee 
Doc. 22, 70th Cong., 
2d sess. 
S. Doc. 100, 81st Cong., 
1st sess. 
26-22

PITTSBURGH, PA., DISTRICT 
TABLE 26-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
OHIO RIVER BASIN (Pittsburgh Dist.) (See Section 23 of Text) 
Aug. 28, 1937 Construct levees, floodwalls, and drainage structures Flood Control Committee 
for protection of cities and towns in Ohio River Basin. Doc. 1, 75th Cong., 1st 
Projects to be selected by Chief of Engineers with Sess. 
approval of Secretary of War at a cost not to exceed 
$24,877,000 for construction. 
June 28, 1938 Approved general comprehensive plan for flood control and Flood Control Committee 
other purposes in Ohio River Basin as may be advisable in Doc. 1, 75th Cong., 1st 
discretion of Secretary of War and Chief of Engineers, Sess.s 
and for initiation and partial accomplishment of plan, 
authorized $75 million for reservoirs and $50,300,000 
for local flood protection works. 
Aug. 18, 1941 Additional $45 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Dec. 22, 1944 Additional $70 million for further prosecution of H. Doc. 762, 77th Cong., 
comprehensive plan for ohio River Basin, including 2d sess. 
additional projects in tributary basins. 
July 24, 1946 Additional $125 million for further prosecution of H. Doc. 506, 78th Cong., 
comprehensive plan including additional projects 1st Sess. 
in tributary basins. 
May 17, 1950 Additional $100 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Dec. 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for flood control and other 
purposes in Ohio River Basin. 
June 18, 1965 Additional $89 million for further prosecution of H. Doc. 6755, 89th Cong., 
comprehensive plan for Ohio River Basin. 1st Sess. 
Aug. 13, 1968 Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
June 19, 1970 Additional $69 million for further H. Doc. 15166, 91st 
prosecution of comprehensive plan Cong., 2nd Sess. 
for Ohio River Basin. 
1. Included in the Emergency Relief Administration 
program April 8, 1935. 
2. Permanent Appropriations Repeal Act. 
3. Public Res. 117,71st Cong., 3d sess. 
4. Permanent Appropriations Repeal Act. 
26-23

TABLE 26-C ALLEGHENY RIVER, PA.: LOCKS AND DAMS 
(See Section 1 of Text) 
Dimensions 
Upper 
Avail- Normal Depths on Miter 
Width able Lift at Pool Ele- Sills at Normal Character of Type of Year 
of Length Normal vation Pool Level' Foundation Construction Per- Opened 
Miles Cham- to Full Pool (feet, cent to 
Above ber Width Level mean sea Lower Upper Kind of Com- Navi- Estimated or 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 
2 6.7 Aspinwall, Pa. 56 360 11.0 721.0 12.0 10.9 Rock Rock Fixed Concrete Concrete 100 19342 $ 1,763,485 
3 14.5 Cheswick, Pa. 56 360 13.5 734.5 10.8 11.8 Rock Pile-rock Fixed Concrete Concrete 100 19342 1,875,665 
4 24.2 Natrona, Pa. 56 360 10.5 745.0 10.0 8.5 Rock Rock Fixed Concrete Concrete 100 1927 1,707,690 
5 30.4 Freeport, Pa. 56 360 11.8 756.8 10.5 10.3 Piling Crib-pile Fixed Concrete Concrete 100 1927 1,940,537 
6 36.3 Clinton, Pa. 56 360 12.2 769.0 10.6 10.8 Rock Crib-pile Fixed Concrete Concrete 100 1928 1,523,959 
7 45.7 Kittanning, Pa. 56 360 13.1 782.1 9.8 10.9 Piling Crib-pilingFixed Concrete Concrete 100 1930 1,460,008 
8 52.6 Templeton, Pa. 56 360 17.9 800.0 10.4 13.8 Rock Rock-pile Fixed Concrete Concrete 100 1931 2,848,920 
9 62.2 Rimer, Pa. 56 360 22.0 822.0 10.5 11.3 Rock Rock Fixed Concrete Concrete 100 1938 2,510,373 
Total $15,630,637 
Abandoned lock and dam 1 591,187 
Abandoned lock and dam 2 544,929 
Abandoned lock and dam 3 310,103 
Demolishing old dam 1 26,001 
Dredging channel 1,005,003 
Total $18,157,860 
dAll depths as shown are on guard sills and are controlling 
depth. 
O
O
MM
O 
2Dates shown represent replacement structures.

TABLE 26-D MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS 
(See Section 3 of Text) 
Dimensions 
Upper 
Avail- Normal Depths on Miter 
Width able Lift at Pool Ele- Sills at Normal Character of Type of Year 
of Length Normal vation Pool Level' Foundation Construction Per- Opened 
Miles Chamin- to Full Pool (feet, cent to 
Above ber Width Level Mean sea Lower Upper Kind of Corn- Navi- Estimated or 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 
2 11.2 Braddock, Pa. 56 360 8.7 718.7 16.0 15.95 Rock Crib pile Fixed Concrete Concrete 100 19532 $ 17,872,212 
3 23.8 Elizabeth, Pa. 
4 41.5 Monessen, Pa. 
61.2 Maxwell locks and dam 
Maxwell, Pa. 
82.2 Grays Landing Lock 
and dam, Grays 
Landing, Pa. 
7 85.0 Greensboro, Pa. 
8 90.8 Point Marion, Pa. 
102.0 Morgantown lock and 
dam, Morgantown, 
W. Va. 
108.0 Hildebrand lock and dam, 
6 miles above Morgantown, 
W. Va. 
115.4 Opekiska lock and dam, 
13.4 miles above 
Morgantown, W.Va. 
Marine ways, etc. 
Abandoned lock and dam 1 
Abandoned lock and dam 4 
Abandoned lock and dam 5 
Abandoned lock and dam 6 
Abandoned lock and dam 7 
Abandoned lock and dam 8 
Abandoned lock and dam 9 
Abandoned lock and dam 10 
Abandoned lock and dam 11 
Abandoned lock and dam 12 
Abandoned lock and dam 13 
Abandoned lock and dam 14 
110 720 
563 360 
720 
563 360 
720 
843 720 
8.2 726.9 11.6 11.9 Rock Crib pile Fixed Concrete Concrete 100 19072 
16.6 743.5 10.7 20.0 Piles Piles Movable Concrete Concrete 100 19322 
19.5 763.0 15.0 20.5 Rock Rock Movable Concrete Concrete 100 1964 
84 720 15.0 778.0 15.0 26.0 Rock Rock 
56 
56 
84 
360 
360 
600 
15.0 
19.0 
17.0 
Fixed Concrete Concrete 
778.0 10.0 10.5 Rock Rock Fixed Concrete Concrete 100 19252 
797.0 10.0 14.5 Rock Rock Movable Concrete Concrete 100 19252 
814.0 14.5 17.8 Rock Rock Movable Concrete Concrete 100 1950 
84 600 21.0 835.0 15.0 14.0 Rock Rock Movable Concrete Concrete 100 1959 
84.0 600 22.0 857.0 14.0 17.75 Rock Rock Movable Concrete Concrete 100 1964 
1,681,538 
17,373,767 
30,110,889 
55,400,000 
2,639,804 
41,408,4954 s 
8,778,000 
12,506,829 
25,179,622 
250,000 
1,019,907 
780,816 
1,074,812 
770,449 
213,776 
245,900 
191,000 
210,445 
227,668 
200,550 
190,691 
210,127 
C1

MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS 
(See Section 3 of Text) 
C
y
O
� 
Dimensions 
Upper 
Avail- Normal Depths on Miter 
Width able Lift at Pool Ele- Sills at Normal Character of Type of Year 
of Length Normal vation Pool Level' Foundation Construction Per- Opened 
Miles Cham- to Full Pool (feet, cent to 
Above her Width Level Mean sea Lower Upper Kind of Com- Navi- Estimated or 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 
Abandoned lock and dam 15 175,829 
Dredging 587,899 
Tot, $219,301,025 
1. All depths as shown are on guard sills and are controlling depths. 
2. Dates shown for locks and dams Nos. 2 to 8, inclusive, represent reconstruction.
3. 2 chambers. 
4. Includes $3,322,057 for raising crest of dam and estimated $36,000,000 for 
z
Mz
C17 
replacement of existing lock. 
5. Estimated. iR 
6. Includes estimated $15,200,000 for reconstruction of dam. 
7. Includes $16,967,114 for reconstruction of locks. 
c,1 
TABLE 26-D (Continued) 
t@C

PITTSBURGH, PA., DISTRICT 
TABLE 26-E MONONGAHELA RIVER, PA. AND W. VA.: 
TOTAL COSTS OF EXISTING PROJECT TO END OF FISCAL YEAR 
(See Section 3 of Text) 
Operation and 
Maintenance, 
Funds New Work General Total 
Regular $122,491,182 $51,954,279 $174,445,461 
Maintenance and operation - 150,000 150,000 
Public Works acceleration, executive (1963) - 22,549 22,549 
Total $122,491,182 $52,126,828 $174,618,0101 
'Excludes $20,446,587 expended between July 7, 1897 and under provisions of permanent indefinite appropriation for 
June 30, 1937, on operation and care of works of improvement such purposes. 
TABLE 26-F OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Allegheny River, Pa. open-channel work I 1934 197,000 133,840 
Beaver and Mahoning Rivers, Pa. and Ohio2 1938 
Buckhannon River, W. Va.3 4 1893 5,500 
Cheat River, W. Va.3 4 1895 12,997 
Lake Erie-Ohio River Canal, Ohio and Pa. 1972 1,342,000 
Pittsburgh Harbor, Pa. 1922 110,663 81,613 
Youghiogheny River, Pa. and Md. 1971 47,1955 185,668 ' 
1. Completed. 
2. January 23, 1939, Chief of Engineers recommended 
constructing a waterway from Ohio River through Beaver, 
Mahoning, and Grand River Valleys to Lake Erie (H. Doc. 
178, 76th Cong., 1st Sess.). 
3. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st Sess. 
4. No commerce reported. 
5. Previous project data. 
6. Includes $1,700 expended under previous project. 
26-27

TABLE 26-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OHIO RIVER BASIN (PITTSBURGH DISTRICT): 
LOCAL PROTECTION PROJECTS 
(See Section 23 of Text) 
Estimated Cost s 
Type of 
Locationx Protection Federal Non-Federal Total 
Adena, Ohio (Short Creek)2 
Allegany, N.Y., unit I (Allegheny River)2 
Allegany, N.Y., unit II (Five Mile Creek area) 
Bellaire, Ohio2 
Benwood, W. Va.2 7 
Brackenridge, Tarentum and Natrona, Pa. 
(Allegheny River)2 
Brilliant, Ohio2 
Brockway, Pa. (Allegheny River Basin)2 
Clarington, Ohio 2 
Coraopolis, Pa.2 
Dillonvale, Ohio (Short Creek)2 
Elkins, W. Va. (Monongahela River Basin)4 5 
Empire and Stratton, Ohio2 
Follansbee, W. Va.2 
Freeport, Pa. (Allegheny River)2 
Industry, Pa.2 
Johnsonburg, Pa. (Allegheny River Basin) 5 
Johnstown, Pa. (Allegheny River Basin)4 5 
Kittanning, Pa., part I (Allegheny River)2 5 
Kittanning, Pa. part II (Allegheny River)2 
Lake Chautauqua and Chadakoin River, N.Y. 
(Allegheny River Basin)2 
Latrobe, Pa. (Allegheny River Basin)2 5 
Leetsdale, Pa.2 
Martins Ferry, Ohio2 
6 
McKees Rocks, Pa.2 
Mingo Junction, Ohio2 
Moundsville, W. Va. 2 
Neville, Island, Pa.2 
New Cumberland, W. Va. 2 
New Kensington and Parnassus, Pa. 
(Allegheny River)2 
Olean, N.Y. (Allegheny River)2 5 
Pittsburgh, Pa. (Golden Triangle)2 
Pittsburgh, Pa. (North Side) 2 
Pittsburgh, Pa. (The Strip)2 
Portville, N.Y. (Allegheny River)2 5 
Powhatan Point, Ohio2 
Proctor, W. Va.2 
Punxsutawney, Pa. (Allegheny River Basin)4 6 
Ridgway, Pa. (Allegheny River Basin)2 5 
Rochester, Pa. 2 
St. Marys, Pa. (Allegheny River Basin)2 
Smiths Ferry, Pa.2 
Warwood, W. Va.2 
Wellsburg, W. Va. 2 
Wellsville, Ohio, sec. 12 5 
Wellsville, Ohio, sec. II2 5 
West Bridgewater, Pa.2 
Wheeling, W. Va.2 7 
Wheeling, W. Va. (North Wheeling)2 
Channel 
Levee 
Channel and levee 
Wall and levee 
Wall 
Wall 
Wall 
Wall and levee 
Wall and levee 
Wall 
Channel 
Channel diversion 
Internal drainage 
facilities 
Wall' 
Wall 
Wall,levee,and channel 
Wall 
Channel 
Wall 
Wall 
Channel 
Channel 
Levee 
Wall and levee 
Wall 
Wall 
Wall and levee 
Wall and levee 
Wall and levee 
Wall 
Levee 
Wall 
Wall 
Wall 
Levee 
Levee 
Levee 
Channel and levee 
Channel 
Wall 
Channel 
Wall 
Wall 
Wall and levee 
Wall and levee 
Wall and levee 
Wall 
Wall and levee 
Wall 
26-28 
$ 283,000 
697,000 
980,000 
7,660,000 
8,500,000 
11,800,000 
3,240,000 
477,000 
2,710,000 
3,080,000 
388,000 
1,772,6273 
760,000 
2,670,000 
1,480,000 
1,560,000 
674,6643 
8,865,3883 
130,3173 
5,940,000 
6,640,000 
207,6593 
1,270,000 
8,630,000 
5,470,000 
1,920,000 
3,070,000 
3,210,000 
2,760,000 
7,900,000 
3,217,5313 
9,390,000 
22,400,000 
10,700,000 
2,070,4843 
4,720,000 
334,000 
3,586,1073 
628,8883 
3,350,000 
559,000 
2,120,000 
1,740,000 
3,270,000 
483,9103 
157,6333 
2,340,000 
19,700,000 
11,700,000 
$ 67,000 
65,000 
133,000 
1,870,000 
3,180,000 
3,080,000 
276,000 
167,000 
249,000 
466,000 
58,000 
40,000 
22,000 
232,000 
21,000 
136,000 
130,000 
2,000 
352,000 
1,310,000 
44,400 
141,000 
836,000 
197,000 
310,000 
605,000 
1,830,000 
421;000 
148,000 
597,000 
429,000 
1,760,000 
2,560,000 
353,000 
397,000 
121,000 
180,4853 
72,000 
622,000 
17,000 
229,000 
376,000 
1,160,000 
113,000 
517,000 
3,460,000 
2,700,000 
$ 350,0001" 
762,00012 
1,113,000" 
9,530,000 
11,680,000"1 
14,880,000 
3,516,000 
644,000 
2,959,000 
3,546,000 
446,000'" 
1,812,627 
782,000'" 
2,902,000 
1,501,000 
1,696,000 
804,664 
8,865,3883 
132,317 
6,292,000 
7,950,000" 
252,059 
1,411,000 
9,466,000 
5,667,000 
2,230,000 
3,675,000 
5,040,000 
3,181,000 
8,048,000 
3,814,531 
9,819,000 
24,160,000 
13,260,000 
2,423,484 
5,117,000 
455,000 
3,766,592' 
700,888 
3,972,000 
576,000" 
2,349,000 
2,116,000 
4,430,000 
596,910 
157,6333 
2,857,000 
23,160,0001' 
14,400,000

PITTSBURGH, PA., DISTRICT 
TABLE 26-G 
(Continued) 
OHIO RIVER BASIN (PITTSBURGH DISTRICT): 
LOCAL PROTECTION PROJECTS 
(See Section 23 of Text) 
Estimated Cost8 
Type of 
Location' Protection Federal Non-Federal Total 
Wheeling, W. Va. (Wheeling Island)2 Wall and levee 13,300,000 2,470,000 15,770,000 
Woodlands, W. Va.2 Levee 206,000 28,000 234,000 
'All projects are on the Ohio River unless otherwise 6Latest cost estimate revision 1954 unless otherwise 
noted. noted. 
2Also see "Other authorized flood control projects." 9Latest cost estimate revision 1959. 
3Actual cost. '�"Latest cost estimate revision 1960. 
4Reported in detail in an individual report. "Latest cost estimate revision 1965. 
5Completed. '2 Latest cost estimate revision 1966. 
6Reported in detail in Annual Report for 1941. " Latest cost estimate revision 1974. 
7Reported in detail in Annual Report for 1954. '4 Latest cost estimate revision 1975. 
TABLE 26-H OHIO RIVER BASIN (PITTSBURGH DISTRICT): RESERVOIRS 
(See Section 23 of Text) 
Total Esti- 
Tributary Basin and Reservoir Stream mated Cost 
Allegheny: 
Conemaugh River, Pa.' Conemaugh River $ 45,684,4112 
Crooked Creek, Pa.1 Crooked Creek 4,204,8882 
East Branch Clarion River, Pa.1 Clarion River 9,524,6012 
Kinzua Dam and Allegheny Reservoir,Pa.and N.Y.1 Allegheny River 108,685,0006 
Loyalhanna, Pa.' Loyalhanna Creek 5,452,8622 
Mahoning Creek, Pa.' Mahoning Creek 6,421,3452 
Redbank, Pa.3 Redbank Creek 39,800,0004 
Tionesta, Pa.' Tionesta Creek 6,893,1016 
Beaver: 
Berlin, Ohio' Mahoning River 8,700,4006 
Eagle Creek, Ohio 3 Eagle Creek 12,700,0004 
Mosquito Creek, Ohio' Mosquito Creek 5,676,0006 
Shenango River, Pa. and Ohio' Shenango River 38,698,0006 
Monongahela: 
Youghiogheny River, Pa., and Md.' Youghiogheny River 11,604,3006 
'Reported in detail in an individual report. 
2Completed, actual cost. 
3Also see "Other authorized flood control projects." 
4Latest cost estimate revision 1954. 
"Latest cost estimate revision 1974. 
6Latest cost estimate revision 1975. 
26-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 26-I INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 35 of Text) 
Project Dates of Inspection 
Amsterdam, Ohio 
Big Run, Pa. 
Bradford, Pa. 
Brookville, Pa. 
Buckhannon, W. Va. 
Burgettstown-Slovan, Pa. 
Butler, Pa. 
Chartiers Creek, Pa. 
Colliers, W. Va. 
Eldred, Pa. 
Friendsville, Md. 
Granville, Pa. 
Johnsonburg, Pa. 
Kittanning, Pa. 
Latrobe, Pa. 
Leetonia, Ohio 
Oil City, Pa. 
Olean, N.Y. 
Portage, Pa. 
Portville, N.Y. 
Reynoldsville, Pa. 
Ridgway, Pa. 
Salamanca, N.Y. 
Stonewood-Nutter Fort, W.Va. 
Sykesville, Pa. 
Tarentum, Pa. 
Turtle Creek, Pa. 
Washington, Pa. 
Wellsville, Ohio 
Weston, W.Va. 
Wilmore, Pa. 
Youngstown, Ohio 
March 1975 
June 1975 
June 1975 
June 1975 
April 1975 
May 1975 
April 1975 
May 1975 
March 1975 
November 1974 
April 1975 
May 1975 
June 1975 
None 
May 1975 
March 1975 
May 1975 
November 1974 
October 1974 
May 1975 
June 1975 
June 1975 
November 1974 
April 1975 
June 1975 
April 1975 
April 1975 
May 1975 
March 1975 
April 1975 
May 1975 
March 1975 
26-30 
- --- --- -~- ---I-- ---I-I --- --- -~--1 ~-

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 26-J OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Adena, Ohio,' 8 9 13,452 
Allegany, N.Y., unit I (Allegheny 
River)' - 4,100 
Amsterdam, Ohio4 6 1964 183,072 
Bellaire, Ohio' - 76,487 
Benwood, W. Va.2 1954 81,028 
Big Run, Pa.4 
6 1965 364,208 
Black Fork at Hendricks, W. Va.6 1972 6,800 
Brackenridge, Tarentum, and 
Natrona, Pa.' 8 9 H 
Bradford, Pa.4 1962 7,601,763 
Brilliant, Ohio' 8 9 
Brockway, Pa.' 8 9 n - 194 
Brookville, Pa.4 1963 964,976 
Buckhannon, W. Va.3 - 37,488 
Buckhannon W. Va.4 1972 1,568,661 
Burgettstown, Pa.4 6 - 83,129 
Butler, Pa.4 1970 1,556,181 
Clarington, Ohio' 8 9 - 
Coraopolis, Pa.' 8 9 
Dillonvale, Ohio' 8 9 o - 16,884 
Eagle Creek Reservoir, Ohio' - 100,000 
Empire and Stratton, Ohio - 33,031 
Follansbee, W.Va.' 8 9 HFreeport, 
Pa.' 8 9 11 
Friendsville, Md.4 6 41,529 
Granville, Pa.4 6- 75,908 
Industry, Pa.' s 9 
- 
Johnsonburg, Pa.4 1958 674,664 
Kittanning, Pa., part I4 1949 130,317 
Kittanning, Pa., part II' 
Lake Chautauqua and Chadakoin River, 
N.Y.7 1956 190,722 
Latrobe, Pa.4 1951 207,659 
Latrobe, Pa.4 1970 2,556,652 
Leetonia, Ohio4 6 - 89,299 
Leetsdale, Pa.4 6 8 " 
Martins Ferry, Ohio' 1941 25,164 
McKees Rocks, Pa.' 
Mingo Junction, Ohio' 8 9 1O - 
Moundsville, W.Va.' 
Neville Island, Pa.' 8 9 " 
New Cumberland, W. Va.' 8 o 1 " 
New Kensington and Parnassus, Pa.' 8 9 HOakdale, 
Pa.6 - 14,127 
Oil City, Pa.4 6 - 43,595 
Olean, N.Y.4 1954 3,217,531 
Pittsburgh, Pa. (Golden Triangle)' 
Pittsburgh, Pa. (North Side)' 
Pittsburgh, Pa. (The Strip)' 
Portage, Pa.4 6 1965 150,386 
Portville, N.Y.4 1954 2,070,484 
Powhatan Point, Ohio' 
Proctor, W. Va.' 
26-31

PITTSBURGH, PA., DISTRICT 
TABLE 26-J (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Redbank Creek Lake, Pa.' 8 9 - 156,337 
Reynoldsville, Pa.4 1959 385,494 - 
Ridgway, Pa.4 1964 628,888 
Rochester, Pa.' 8 9 "1 
Rouseville, Pa.6 1,642 
Salamanca, N.Y.4 1972 2,880,535 
Slovan, Pa.4 6 - 57,811 
Smith Ferry, Pa.' 8 9 11 
St. Marys, Pa.' 8 9 t - 13,529 
Sykesville, Pa.4 6 184,246 
Tarentum, Pa.4 6 1964 136,591 
Turtle Creek, Pa.4 1972 15,350,552 
Uniontown, Pa.' 1956 
Wallace, W. Va.6 - 11,035 
Warwood, W. Va.' 
Washington, Pa.4 1964 789,093 
Wellsburg, W. Va.' s 9 10 11 6,387 
Wellsville, Ohio, Sec. I4 1956 483,910 
Wellsville, Ohio, Sec. II4 1956 157,633 
West Bridgewater, Pa.' 8 9 - - 
Wheeling, W. Va. (North Wheeling)' - 
Wheeling, W. Va. (Wheeling Island)' - 21,700 
Wheeling, W. Va.' 1954 189,067 
Wilcox, Pa.5 16,761 
Wilmore, Pa.4 6 96,853 
Woodlands, W. Va.' 
1. Inactive. 
2. To be restudied. 
3. Local interests failed to meet requirements of 
cooperation, authority for project expired Feb. 20, 1951. 
4. Completed. 
5. Local interests failed to meet requirements of local 
cooperation, authority for project expired Mar. 5, 1955. 
6. Authorized by Chief of Engineers. 
7. Local interests failed to meet requirements of local 
cooperation, authority for project expired Mar. 2, 1970. 
8. Recommended for deauthorization. 
9. Lacks local support. 
10. No longer required. 
11. No longer economically justified. 
26-32

PITTSBURGH, PA., DISTRICT 
TABLE 26-K FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 37 of Text) 
Study Identification Fiscal Year Costs 
Homestead (Whitaker) Run, Munhall, Pa. (detailed project report) $ 4,927 
Root Creek, Bolivar, N.Y. (detailed project report) 4,374 
Sulphur Run, Latrobe, Pa. (detailed project report) 3,661 
Westons Mills, N.Y. (detailed project report) 44,856 
TABLE 26-L COMPLETED FLOOD PLAIN STUDIES 
(See Section 38 of Text) 
Date Federal 
Location Requesting Agency Completed Cost 
Fayette County, Pa. 
Monongahela River 
Green County, Pa. 
Monongahela River 
Clarion County, Pa. 
Allegheny River 
Port Allegany, Pa. 
Allegheny River & 
Lillibridge Creek 
Johnstown & Vic., Pa. 
Conemaugh River 
& Tributaries 
Venango County, Pa. 
Allegheny River 
Forest County, Pa. 
Allegheny River 
Fayette County Planning 
Commission 
Greene County Planning 
Commission 
Clarion County Planning 
Commission 
Borough of Port Allegany 
Cambria & Somerset County 
Planning Commissions 
Venango County Planning 
Commission 
Forest County Planning 
Commission 
July 1974 
July 1974 
September 1974 
September 1974 
June 1975 
June 1975 
June 1975 
26-33 
$25,000 
$15,000 
$30,000 
$30,000 
$30,000 
$55,000 
$40,000

ST. PAUL, MINN., DISTRICT* 
This district comprises western Wisconsin, 
westerly portion of Upper Peninsula of Michigan, 
major portion of Minnesota, northern and eastern 
North Dakota, and small portions of northeastern 
South Dakota and northern and northeastern Iowa 
embracing drainage basins of Mississippi River and 
tributaries from its source to mile 614 above mouth 
of Ohio River; Red River of the North and tributaries; 
those streams north of Missouri River Basin 
in North Dakota; U.S. waters of Lake of the Woods 
and its tributaries; and U.S. waters at Lake Superior 
and its tributary basin west of Au Train Bay, 
including Isle Royale in Lake Superior. That section 
of Mississippi River above mile 614 is included in 
report on Mississippi River between Missouri River 
and Minneapolis, Minn. 
IMPROVEMENTS 
Navigation 
1. Ashland Harbor, Wis. ............ 
2. Bayfield Harbor, Wis............. . 
3. Beaver Bay Harbor, Minn. ......... 
4. Big Bay Harbor, Mich ........... 
5. Black River Harbor, Mich........... 
6. Cornucopia Harbor, Wis. ............ 
7. Duluth-Superior Harbor, Minn. and 
W is............................... 
8. Grand Marais Harbor, Minn......... 
9. Grand Traverse Bay Harbor, Mich. . 
10. Keweenaw Waterway, Mich...... ... 
11. Knife River Harbor, Minn.......... 
12. Lac La Belle Harbor, Mich. ........ 
13. Lutsen Harbor, Minn. .............. 
14. Marquette Harbor, Mich.......... . 
15. Minnesota River, Minn............ 
16. Mississippi River between Missouri 
River and Minneapolis, Minn. ...... . 
17. Ontonagon Harbor, Mich ......... 
18. Port Wing Harbor, Wis........... 
19. Presque Isle Harbor, Mich. .......... 
20. Reservoirs at Headwaters of 
Mississippi River, Minn............. 
21. St. Croix River, Minn. & Wis...... . 
22. Saxon Harbor, Wis. ................ 
23. Two Harbors, Minn ............... 
24. Warroad Harbor and River, Minn. ... 
25. Reconnaissance and condition 
surveys ............................ 
26. Other authorized navigation 
projects... .................... 
27. Navigation work under special 
authorization .................... 
Page 
27-2 
27-2 
27-3 
27-3 
Beach Erosion 
28. Beach Erosion Control work under 
special authorization ................ 
Flood Control 
27-3 29. Big Stone Lake and Whetstone 
27-4 River, Minn. and S. Dak............ 
30. Burlington Dam, Souris River, 
27-4 N. Dak...................... 
27-4 31. Eau Galle River, Wis ........... 
27-5 32. Homme Lake and Dam, N. Dak...... 
27-5 33. Kindred Lake, Sheyenne River, 
27-6 N. Dak.......... ........... 
27-6 34. Lac qui Parle Lake, Minnesota 
27-6 River, Minn. ..... .......... 
27-7 35. La Farge Lake and channel 
27-7 improvement, Wis.................. 
36. Lake Ashtabula and Baldhill Dam, 
27-7 Sheyenne River, N. Dak............ 
27-8 37. Lake Traverse and Bois de Sioux 
27-8 River, S. Dak. and Minn............. 
27-8 38. Mankato and North Mankato, 
Minn................................ 
27-9 39. Minot, N. Dak..................... 
27-9 40. Prairie du Chien, Wis............. 
27-10 41. Red Lake River, Minn., including 
27-10 Clearwater River, Minn............. 
27-10 42. Red River of the North drainage 
basin, Minn., S. Dak., & N. Dak. .... 
27-11 43. Red River of the North at Oslo, 
M inn .... ....................... 
27-11 44. Red River of the North at Pembina, 
N. Dak .................. ........ 
27-11 45. Rochester, Minn. .................. 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text 
and also appear at the end of this chapter. 
27-1 
Page 
27-11 
27-11 
27-12 
27-12 
27-12 
27-13 
27-13 
27-13 
27-14 
27-15 
27-15 
27-15 
27-16 
27-16 
27-17 
27-17 
27-18 
27-18

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (cont.) 
46. Roseau River, Minn. .......... 
47. Rushford, Minn. .. . ......... 
48. State Road and Ebner Coulees, 
W is ............... ...... .... 
49. Twin Valley Lake, Wild Rice River, 
M inn............... .... 
50. Wild Rice River-South Branch and 
Felton Ditch, Minn. ................ 
51. Winona, Minn................. 
52. Zumbro River, Minn. . .. ... . 
Page 
27-18 53. Inspection of completed flood 
- control projects.................... 
27-19 54. Other authorized flood control 
projects.... .................... 
27-19 55. Flood control work under special 
authorization. ...... .. 
27-19 
27-20 
27-20 
27-21 
56. 
57. 
58. 
General Investigations 
Surveys................... 
Collection and study of basic data... 
Research and development ........ 
Page 
27-21 
27-21 
27-21 
27-21 
27-22 
27-22 
Navigation 
1. ASHLAND HARBOR, WIS. 
Location. At head of Chequamegon Bay, on 
south shore of Lake Superior, about 65 miles east 
of Duluth, Minn. (See Lake Survey Chart 964.) 
Existing project. A west channel 20 and 21 feet 
deep and an east basin 25 and 27 feet deep, both 
extending lakeward from 75 feet outside harborline, 
all protected by an 8,000-foot breakwater. 
For additional details see page 1008 of Annual 
Report for 1965. (See table 27-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. City of Ashland owns 4,150 
feet of waterfront for future public needs. 
Wharves for handling coal, ore, limestone, logs, 
and pulpwood are served by railroads. Facilities 
are considered adequate for existing commerce. 
Handling of ore and logs has been discontinued for 
the present. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $4,619. Work 
continued on engineering for contained dike disposal 
at a cost of $3,978. Environmental review by 
contract proceeded at a cost of $3,965. Repairs 
were made to the breakwaters by the Derrickbarge 
Coleman at a cost of $56,126, and 1,338 tons 
of rock were placed. Administrative costs were 
$12, 910. 
Condition at end of fiscal year. Work authorized 
prior to 1960 act was completed in 1950. Work 
authorized by 1960 act was completed in November 
1962. Breakwater is in generally good condition, 
except for settled portions. At end of fiscal 
year, controlling depths were 16 feet in 1,800-foot 
west portion of West Channel, and authorized 
depths in remainder of project. 
2. BAYFIELD HARBOR, WIS. 
Location. On the west channel leading to Chequamegon 
Bay, on the south shore of Lake Superior 
at Bayfield, Wis., and is 16 miles north of 
Ashland, Wis. (See Lake Survey Chart 961.) 
Existing project. Provides for a small-boat harbor 
by extending city pier L about 103 feet and the 
city breakwater pier approximately 139 feet; 
constructing parapets about 2 feet in height on the 
outside walls of the city pier L, a portion of the 
city pier, and the city breakwater pier; and 
dredging the municipal harbor basin, which is protected 
by the above piers and breakwaters, 350 
feet wide by 800 feet long to a depth of 10 feet. 
(For additional details see page 1233 of Annual 
Report for 1961.) Existing project was authorized 
by the River and Harbor Act approved May 17, 
1950 (H. Doc. 260, 81st Cong,, 1st sess., contains 
the latest published map). 
Local cooperation. Fully complied with. Local 
interests have furnished easements on 0.59 acre of 
land. 
Terminal facilities. Within and adjacent to the 
project area there are eight privately owned 
wharves, one boat repair yard pier, two piers 
where a charge is made for berthing space, and 
the city-owned L and breakwater which provide 
berthing space. In the southerly portion of the 
harbor is a city marina with three finger piers for 
recreational craft and a header dock. Included is a 
launching ramp. The facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $2,699. Work was 
completed on engineering for a breakwater design 
deficiency at a cost of $11,429. Environmental 
review was completed at a cost of $3,630. Administrative 
costs totaled $3,607. 
Condition at end of fiscal year. Existing project 
was completed in August 1960 and project depths 
are available. A design deficiency is recognized 
since the present breakwater does not prevent 
waves caused by northeast winds from entering 
the harbor and reaching the marina. Unsafe 
27-2

ST. PAUL, MINN., DISTRICT 
harbor conditions result during storms. Studies 
have been completed. It appears that a breakwater 
outside the harbor area would effectively 
reduce wave action. City owned harbor breakwaters 
were damaged by a storm in March 1975. 
3. BEAVER BAY HARBOR, MINN. 
Location. The harbor is located on the north 
shore of Lake Superior 51 miles northeasterly 
from Duluth, Minn., and 56 miles southwesterly 
from Grand Marais, Minn. (See Lake Survey Chart 
No. 97.) 
Existing project. Project as modified provides for 
two rubblemound breakwaters totaling 560 feet in 
length and for a harbor basin approximately 2 
acres in size, and 8 feet deep. See page 1659 of 
Annual Report for 1945 for improvements authorized 
by the River and Harbor Act approved March 
2, 1945 (H. Doc. No. 446, 78th Cong., 2d sess.). 
This document contains the latest published map. 
Estimated Federal cost (1974) for new work is 
$1,530,000, and non-Federal cost is $106,000. 
Local cooperation. See page 1659 and 1660 of 
Annual Report for 1945. Local interests furnished 
local assurances in November 1969. 
Operations and results during fiscal year. New 
work: Preconstruction planning was continued at a 
cost of $35,520. 
Condition at end of fiscal year. Preconstruction 
planning in progress. An alternate site is being 
studied at the request of local interests due to 
shoreline changes. 
4. BIG BAY HARBOR, MICH. 
Location. On south shore of Lake Superior 33 
miles northwesterly from Marquette, Mich., and 
38 miles easterly from Portage entry to Keweenaw 
Waterway. (See Lake Survey Chart 94.) 
Existing project. Provides for two converging 
piers extending from shore, an entrance channel 
between piers and a rectangular harbor basin. 
Project depths are 12 feet in entrance channel and 
10 feet in harbor basin. For details see page 1009 
of Annual Report for 1965 and page 1261 of Annual 
Report for 1962. Existing project was authorized 
by 1945 River and Harbor Act (H. Doc. 446, 78th 
Cong., 2d sess., contains latest published map). 
Local cooperation. Fully complied with. 
Terminal facilities. A State-owned launching 
ramp and dock for small craft. 
Operations and results during fiscal year. Maintenance: 
Condition surveys and engineering 
studies were performed at a cost of $1,103. 
Work on engineering for contained dike disposal 
proceeded at a cost of $2,800. Derrickbarge 
Markus removed 5,360 cubic yards of material to 
restore project depths at a cost of $16,462. Investigations 
for mitigation of shore damages cost 
$38,946. Administrative costs were $3,580. 
Condition at end of fiscal year. Project was completed 
in June 1961 except for protection at inner 
end of east breakwater, completed in November 
1961. A contract for repair of breakwater, damaged 
by storms, was completed in August 1969. 
Controlling depths at end of fiscal year were about 
9 feet in lake approach, 10 feet in entrance channel 
and 10 feet in basin. A reconnaissance report was 
completed in July 1971 concerning erosion of the 
beach adjacent to the harbor. A detailed project 
report is being prepared to develop an acceptable 
plan for mitigation measures. 
5. BLACK RIVER HARBOR, MICH. 
Location. At mouth of Black River on south 
shore of Lake Superior 39 miles westerly from 
Ontonagon, Mich., and 47 miles easterly from Ashland, 
Wis. (See Lake Survey Chart 95.) 
Existing project. Two converging breakwaters, 
an entrance channel between breakwaters, an 
inner channel, and an irregular harbor basin. For 
additional details see page 1092 of Annual Report 
for 1966. Project depths are 12 feet in the approach 
channel and 8 feet in the river channel and 
basin. Project was authorized by 1945 River and 
Harbor Act (H. Doc. 446, 78th Cong., 2d sess., 
contains latest published map). 
Local cooperation. Fully complied with. Local 
interests furnished easements on 0.85 acre of land. 
Terminal facilities. Wharves constructed on both 
sides of river. Wharf on east bank has frontage of 
400 feet and on west bank, a frontage of 750 feet. 
Operation and results during fiscal year. Maintenance: 
Condition surveys and engineering 
studies were performed at a cost of $557. Work 
continued on engineering for diked disposal at a 
cost of $3,700. About 5,670 cubic yards of material 
was dredged by Derrickbarge Markus to restore 
project depths, at a cost of $24,436. Breakwaters 
were repaired by Derrickbarge Markus at a cost of 
$5,238. Administrative costs were $4,769. All 
work was done by hired labor. 
Condition at end of fiscal year, Project was 
completed in June 1958. A triangular-shaped rock 
shoal 50 feet wide at easterly end extends along 
southerly side of channel. Project depths were 
available at the end of the fiscal year in lake 
approach channel and in harbor basin. Controlling 
depths inside the breakwater in the inner channel 
were 9.5 feet. 
27-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
6. CORNUCOPIA HARBOR, WIS. 
Location. At mouth of Siskiwit River on South 
shore of Lake Superior, 49 miles east from Duluth, 
Minn. (See Lake Survey Chart 96.) 
Existing project. Provides for an entrance 
channel between piers; an irregular-shaped turning 
basin; two inner channels; and reconstruction 
and Federal maintenance of deflection dike and entrance 
piers constructed by local interests. Project 
depths are 10 feet between piers and 8 feet in 
turning basin and inner channels.. For additional 
details see page 1010 of Annual Report for 1965. 
(See table 27-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. About 1,000 linear feet of 
privately owned docking space is available. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $2,219. Engineering 
for contained dike disposal continued at a total 
cost of $3,700. Work on environmental review was 
completed at a cost of $1,397. Breakwaters were 
repaired by Derrickbarge Markus at a cost of 
$11,558. Dredge Gaillard removed 4,120 cubic 
yards of material from shoal areas at a cost of 
$27,905. Administrative costs were $6,557. 
Condition at end of fiscal year. Work authorized 
by earlier act was completed in 1939; that for later 
modification in July 1958 except for extension of 
east pier, completed in September 1963. Controlling 
depths at the end of the fiscal year were 9 feet 
in the harbor entry and 7 feet in the basins. 
7. DULUTH-SUPERIOR HARBOR, 
MINN. AND WIS. 
Location. At extreme western end of Lake Superior. 
Cities of Duluth, Minn., and Superior, 
Wis., are on north and south sides, respectively. 
(See Lake Survey Chart 966.) 
Previous projects. See page 1246 of Annual 
Report for 1962. 
Existing project. Provides for rebuilding canal 
piers at Duluth entry, replacement or construction 
of piers and breakwater at Superior entry and 
dredging approaches and channels within harbor, 
St. Louis Bay, and St. Louis River. Channels vary 
in depth from 32 to 28 feet in entrances, are 27 
feet deep in iron-ore route channels, and are from 
20 to 23 feet in inner channels. (See table 27-B for 
authorizing legislation.) 
For details of authorized channel dimensions and 
dimensions of structures, see page 1246 and 1247 
of Annual Report for 1962 and page 1011 of Annual 
Report for 1965. Portion of project for deepening 
Twenty-first Avenue West Channel is inactive. 
Estimated cost (1967) of this portion was $577,000. 
Local cooperation. Fully complied with for active 
portion of project. 
Terminal facilities. There are 113 docks or terminals 
including some 54 major ones; all but one 
are privately owned. Facilities for handling iron 
ore, coal, limestone, petroleum, steel and scrap 
iron, cement, general cargo, and grain are believed 
adequate for most existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys, and engineering 
studies, miscellaneous inspections and reports, 
buildings, grounds, and recreation operations cost 
$108,911. Environmental project review cost 
$4,219. Dredge Gaillard removed 14,050 cubic 
yards of material from shoal areas during 
November and December 1974 at a cost of 
$221,168. Derrickbarge Marcus also performed 
dredging at a cost of $2,935. Breakwater repairs 
included the placing of 642 tons of rock were 
accomplished by the Derrickbarge Coleman at a 
cost of $131,471. Park, pier, and recreational 
maintenance was performed at a cost of $19,336. 
Rock from stockpile decreased $16,216. Administrative 
costs were $102,750. Investigation for 
shoreline erosion cost $4,000. Acquisition of 
Government furnished material by contract for 
contained diked disposal cost $256,486. Contract 
work for an in-lake disposal study and for archeological 
investigation cost $169,728. Engineering 
and administrative costs for contained diked disposal 
by hired labor cost $214,193. 
Condition at end of fiscal year. Work authorized 
prior to 1960 Act was completed in June 1956. 
Under the 1960 Act, work on the outer harbor, 
included in House Document 150, was completed in 
June 1965. Work on the inner harbor, included in 
House Document 196, started in May 1963, was 
completed in November 1968 except for the 21st 
Avenue West channel portion which is inactive. 
Project depths are available in completed portions 
of the harbor except for scattered shoals in various 
locations. A detailed project report was completed 
in November 1974 concerning erosion of a one-half 
mile of reach of beach adjacent and south of the 
Duluth Ship Canal. 
The United States owns 34.90 acres of land in 
fee in Minnesota and Wisconsin, of which 2.15 
acres are used for a vessel yard. Total cost of 
existing project to June 30, 1975 was $27,132,938, 
of which $14,562,063 was for new work and 
$12,570,875 for maintenance. 
8. GRAND MARAIS HARBOR, MINN. 
Location. On north shore of Lake Superior, 106 
miles northeasterly from Duluth, Minn. (See Lake 
27-4

ST. PAUL, MINN., DISTRICT 
Survey Chart 9.) 
Existing project. Provides breakwater piers to 
narrow the entrance; concrete seawalls across 
ledge at southeast corner of harbor; an anchorage 
area and a small-boat basin protected by a rubblemound 
breakwater. Project depths are 16 feet in 
anchorage area increasing to 20 feet near entrance 
and 8 feet in small-boat basin. For additional 
details see page 1014 of Annual Report for 1965. 
(See table 27-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two inactive pulpwood 
wharves and several fish wharves, all privately 
owned. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $567. Environmental 
review cost $3,165. Work on engineering 
for contained dike disposal cost $3,700. Derrickbarge 
Markus performed breakwater repair at a 
cost of $16,870 and dredging at a cost of $8,566. 
Administrative costs were $4,332. 
Condition at end of fiscal year. Existing project 
is complete. Project depths of 16 feet in anchorage 
basin, 18 to 20 feet in entrance channel, and 8 feet 
in small-boat basin are available. Concrete seawall 
and both breakwaters are in good condition. 
Gravel pit along eastern side of harbor is too low 
to prevent waves from rolling into harbor during 
severe storm periods. 
9. GRAND TRAVERSE BAY HARBOR, MICH. 
Location. At mouth of Traverse River oh eastern 
shore of Keweenaw Peninsula about 20 miles 
northeasterly from Portage entry to Keweenaw 
Waterway. (See Lake Survey Chart 94.) 
Existing project. Provides two parallel piers, an 
entrance channel between piers and a harbor 
basin. Project depths are 12 feet between piers 
and 10 feet in basin. Project area extended 200 
feet upstream in 1966. For additional details see 
page 1015 of Annual Report for 1965. Existing 
project was authorized by 1945 River and Harbor 
Act. (H. Doc. 446, 78th Cong., 2d sess., contains 
latest published map.) 
Local cooperation. Fully complied with. Local 
interests furnished easements on 5.1 acres of land. 
Terminal facilities. Several privately owned 
fishing wharves. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $999. Environmental 
review cost $1,696. Breakwater repairs by 
Derrickbarge Markus cost $6,312. Contract cost of 
a prior year was adjusted by $12,105. About 1,280 
cubic yards of material were dredged by Derrickbarge 
Markus to restore project depth at a cost of 
$3,804. Engineering for mitigation of shore 
damage cost $29,261. Administrative costs were 
$2,794. 
Condition at end of fiscal year. Existing project 
was completed in 1950 except for extension of 
north pier completed in 1964. Construction of a 
164-foot extension to the north breakwater was 
completed. Steel cells and piers are in good condition. 
Timber and round wood-pile structures are 
deteriorated but still in serviceable condition. 
Controlling depths were about 10 feet in the 
entrance channel and about 7 feet in the harbor 
basin at the end of the fiscal year. A reconnaissance 
report was completed in January 1972 concerning 
shoreline erosion commencing at the south 
breakwater and extending for about 1 mile south 
of the harbor. A detailed project report is being 
prepared to develop an acceptable plan of remedial 
measures. 
10. KEWEENAW WATERWAY, MICH. 
Location. In Lake Superior across Keweenaw 
Peninsula in upper Michigan. The west entrance is 
169 miles east of Duluth, Minn. (See Lake Survey 
Chart 944.) 
Existing project. A navigable channel, minimum 
width 300 feet, 25 miles long, partially natural and 
partially artificial across Keweenaw Peninsula via 
Portage Lake. For details see page 1121 of Annual 
Report for 1963. Completed cost for new work is 
$5,967,700. Portion of project providing for extension 
of lower entrance breakwater and necessary 
alteration or replacement of structures due to 
deepening channels is inactive and excluded from 
foregoing cost. Estimated cost (1957) of this 
portion was $3,315,000. (See table 27-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. Six coal docks, a petroleum 
dock, and several general merchandise and miscellaneous 
wharves, all privately owned. Facilities, 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys and miscellaneous 
operations were made at a cost of $25,481. Field 
and office studies of diked disposal of dredged 
material progressed at a total cost of $83,372. 
Work also was done on environmental review of 
project at a cost of $8,852. Maintenance of recreation 
facilities was accomplished at a cost of 
$14,171. Dipper dredge GaiUllard removed 103,600 
cubic yards of material from shoal areas at a cost 
of $273,841. Breakwater repairs were accomplished 
by the Derrickbarge Coleman at a cost of 
$119,730, and 1,471 tons of rock were placed. Rock 
27-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
from stockpile totaled $33,741. Administrative 
costs were $87,792. 
Condition at end of fiscal year. Active portion of 
project is complete. Breakwaters are in generally 
good condition except for a weakness occurring in 
about 300 feet of substructure of breakwater at 
lower entrance, and major storm damage repairs 
needed for stone-covered portions of breakwaters 
at upper entrance. Mooring pier at Lily Pond 
requires repairs to halt movement and permit 
dredging to project depth adjacent thereto. The 
flared revetment at the upper entry should be 
modified to restrict wave action from the stilling 
basin entrance. Mooring pier at Portage River 
Harbor of Refuge is in good condition. Annual redredging 
of channels will be required indefinitely. 
Controlling depth is about 24 feet. 
11. KNIFE RIVER HARBOR, MINN. 
Location. Near mouth of Knife River on north 
shore of Lake Superior, 19 miles northeasterly 
from Duluth, Minn., and 7 miles southwest of Two 
Harbors, Minn. (See Lake Survey Chart 96.) 
Existing project. Provides for an entrance channel, 
of varying width, 10 feet deep from that depth 
in Lake Superior; an inner straight channel 8 feet 
deep, 50 feet wide, and 600 feet long with a 
spending beach at its inner end having a radius of 
150 feet; northerly and southwesterly side channels 
8 feet deep, 50 feet wide, and 150 and 250 feet 
long, respectively; and a breakwater 245 feet long 
on south side of entrance including a timber crib. 
For additional details see page 1110 of Annual 
Report for 1963. (See table 27-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. Local 
interests furnished easements on 15.08 acres of 
land. 
Terminal facilities. Local interests have installed 
pile-and-timber docks on both sides of straight 
channel. Lake County has completed construction 
by contract of a marina along the east wing of the 
inner harbor. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $727. Environmental 
review cost $3,672. Dredging was performed 
by Derrickbarge Markus at a cost of 
$24,272. Studies for contained diked disposal were 
performed at a cost of $3,100. Administrative costs 
were $3,729. All work was by hired labor. 
Condition at end of fiscal year. Project was 
completed in June 1958. Breakwater and spending 
beach are in good condition. At end of fiscal year, 
controlling depths were about 9 feet in lake approach, 
8 feet in channel between revetments, and 
8 feet in side channels. A design deficiency is 
recognized at this harbor. The existing breakwater 
does not effectively prevent waves caused by 
northeasterly winds from entering the entrance 
channel. This results in unsatisfactory and unsafe 
harbor entrance conditions during storms. Mooring 
conditions in the main channel and Y-branches 
of the inner harbor are also adversely affected. 
Studies have been completed. It appears construction 
of a breakwater would reduce wave damage 
and improve navigation conditions. 
12. LAC LA BELLE HARBOR, MICH. 
Location. On south shore of Lake Superior on 
eastern shore of Keweenaw Peninsula 41 miles 
northeasterly from Portage entry to Keweenaw 
Waterway. Lac La Belle, Bete Grise Bay, and 
Mendota Ship Canal combine to form the harbor. 
(See Lake Survey Chart 94.) 
Existing project. Provides for construction of 
two parallel piers at the entrance having lengths of 
584 and 682 feet for north and south piers, respectively; 
for an entrance channel between the piers 
50 feet wide and 12 feet deep, about 820 feet long 
with a flared approach; and for an inner canal 50 
feet wide and 10 feet deep, about 730 feet long. 
For additional details see page 1039, Annual 
Report for 1964. Existing project was authorized 
by River and Harbor Act of March 2, 1945 (H. Doc. 
446, 78th Cong., 2d sess., contains latest published 
map). 
Local cooperation. Fully complied with. 
Terminal facilities. Several small, privately 
owned wharves are available in the harbor for use 
of small craft engaged in fishing and recreational 
activities. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $487. Maintenance 
dredging was performed by Derrickbarge Markus 
to restore project depths by removal of 1,200 cubic 
yards of material at a cost of $15,355. In addition, 
425 tons of rock was placed by Derrickbarge 
Markus at a cost of $3,409. Environmental review 
cost $2,774. Administration costs were $4,972. All 
work was by hired labor. 
Condition at end of fiscal year. Project was completed 
in January 1960. Controlling depths were 
about 11 feet in the approach channel and 10 feet 
in the inner channel. 
13. LUTSEN HARBOR, MINN. 
Location. The harbor is located at the mouth of 
the Poplar River on the north shore of Lake 
Superior, 89 miles northeasterly from Duluth, 
Minn., and 17 miles southwesterly from Grand 
Marais, Minn. (See Lake Survey Chart 97.) 
27-6

ST. PAUL, MINN., DISTRICT 
Existing project. Project as modified provides 
for two rubblemound breakwaters totaling 615 feet 
and steel sheet pile ells totaling 250 feet; with an 
excavated harbor basin approximately 350 feet by 
200 feet with an 8-foot depth. For additional details 
see page 1658 of Annual Report for 1945 for 
improvements authorized by the River and Harbor 
Act approved March 2, 1945 (H. Doc. No. 446, 
78th Cong., 2d sess.). This document contains 
latest published map. Estimated Federal cost 
(1975) for new work is $1,910,000 and non-Federal 
cost is $153,000. 
Local cooperation. See page. 1658 of Annual 
Report for 1945. Local interests furnished local 
assurances in December 1969. 
Operations and results during fiscal year. New 
work: Preconstruction planning was continued at a 
cost by hired labor of $53,140. 
Condition at end of fiscal year. Preconstruction 
planning is in progress. Due to private development 
on the authorized site, local interests desire 
that the harbor site be relocated. 
14. MARQUETTE HARBOR, MINN. 
Location. In Marquette Bay on south shore of 
Lake Superior, 160 miles west of Sault Ste. Marie, 
Mich., and 256 miles east from Duluth, Minn. (See 
Lake Survey Chart 935.) 
Existing project. Provides for a breakwater, and 
a harbor basin 26.5 feet deep, giving a protected 
area of 350 acres. Project was modified in 1960 to 
provide a 27-foot depth in harbor area. (See table 
27-B for authorizing legislation.) 
Local cooperation. None required for earlier 
authorizations. Fully complied with for the 1960 
act. 
Terminal facilities. One ore dock, unused at 
present; two coal docks; one petroleum dock; and 
three other unused docks. There are also several 
small fish wharves without railroad connections. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $3,088. Environmental 
review cost $7,936. Breakwater repairs 
including the placing of 175 tons of rock were accomplished 
by the Derrickbarge Coleman during 
June 1975 at a cost of $25,760. Rock for stockpile 
cost $758. Administrative costs were $8,965. All 
work was by hired labor. 
Condition at end of fiscal year. Project authorized 
by earlier acts was completed in 1935. Deepening 
under the 1960 Act was completed in Sep-. 
tember 1966. Rehabilitation of rubblemound portion 
of breakwater was completed in November 
1965. Controlling depth in harbor is about 27 feet. 
15. MINNESOTA RIVER, MINN. 
Location. Rises in Big Stone Lake, Minn. and S. 
Dak., and flows southeasterly about 224 miles to 
Mankato, Minn., thence northeasterly about 106 
miles to join the Mississippi River opposite St. 
Paul, Minn. (For general location see Geological 
Survey map of Minnesota.) 
Previous projects. For details see page 1890 of 
Annual Report for 1915, and page 1105 of Annual 
Report for 1938. 
Existing project. Provides 9-foot depth below 
flat pool level of Mississippi River lock and dam 2 
from mouth to mile 14.7, one-half mile above the 
railway bridge at Savage, Minn., and 4-foot depth 
from mile 14.7 to 25.6 at Shakopee, Minn. For 
details see page 1018 of Annual Report for 1965. 
(See table 27-B for authorizing legislation.) 
Local cooperation. Fully complied with. See also 
page 1074 of Annual Report for 1967. 
Terminal facilities. These are privately owned 
terminals at miles 9, 13.1, 14.5, and two at mile 
14.7. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $1,650. Environmental 
review continued at a cost of $1,933. 
Derrickbarge Hauser performed snagging and 
clearing and dredging operations at a cost of 
$17,008. Administrative costs amounted to 
$13,809. All work was by hired labor. 
Condition at end of fiscal year. Work on project 
for 4-foot depth was completed in 1931. The 
United States owns 10 acres of land in fee 2 miles 
east of Savage, Minn. Rights-of-entry have been 
obtained over 123.08 acres of land over which perpetual 
easements will be conveyed by local interests. 
46.20 acres have been transferred from the 
Department of the Army and Department of the 
Air Force to the project. Navigation from mouth 
to Shakopee was practicable for drafts not in 
excess of 3 feet. A contract for work under 1958 
authorization for a 9-foot channel started in May 
1966 was terminated in January 1967 when 56 percent 
complete. A new contract was awarded and 
is completed. Total costs for existing project to 
June 30, 1975 were $2,752,966, of which $1,940,180 
was for new work and $812,786 for maintenance. 
In addition, cost from contributed funds was 
$139,671 for dredging to 9-foot depth under provisions 
of section 4, River and Harbor Act of 1915, 
and $219,531 for work done for the State of Minnesota 
relative to the modification of project. 
16. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MINN. 
For report on this improvement see chapter on 
27-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Mississippi River between Missouri River and 
Minneapolis, Minnesota. 
17. ONTONAGON HARBOR, MICH. 
Location. On south shore of Lake Superior. It 
consists of improvement of mouth of Ontonagon 
River (See Lake Survey Chart 95.) 
Previous project. For details see page 1931 of 
Annual Report of 1915, and page 1406 of Annual 
Report for 1938. 
Existing project. Provides for approach channel 
16 feet deep, a channel between piers with 17- and 
15-foot depths, an inner basin 12 feet deep, and 
maintenance of channels, basin, and entrance 
piers. Completed project cost $19,619. See page 
1100 of Annual Report for 1966 for details. A modification 
authorized by 1962 River and Harbor Act 
provides for increasing depths of channels, construction 
of an inner basin and a sedimentation 
basin. This portion of project is inactive. Estimated 
cost (1965) of this work is $6,040,000. (See 
table 27-B for authorizing legislation.) 
Local cooperation. None required for earlier 
authorization. See page 1020 of Annual Report for 
1965 requirements of 1962 Act. 
Terminal facilities. There are no publicly owned 
wharves. There are three coal wharves, an oil 
receiving facility, and a few small fish wharves. 
Terminal facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $2,866. Environmental 
review studies were performed for $7,348. 
The Dipper dredge Gaillard removed 29,800 cubic 
yards of material at a cost of $42,434. Repairs 
were made to the breakwaters including placement 
of 914 tons of rock by Derrickbarge Coleman 
at a cost of $46,655. Rock for stockpile cost $4,782. 
Administrative costs were $17,894. Engineering 
for contained diked disposal was performed at a 
cost of $1,800. 
Condition at end of fiscal year. Project under 
earlier act was completed in 1938. The west breakwater 
was damaged by a fall storm and is in need 
of repair. Controlling depths are 17 feet in lake 
approach channel, 10 feet in channel between 
piers, and 6 feet in harbor basin. Work under the 
1962 act has not been done. Total costs to June 30, 
1975 for existing project were $3,115,527, of which 
$47,101 was for new work and $3,068,426 for 
maintenance. 
18. PORT WING HARBOR, WIS. 
Location. On south shore of Lake Superior, 34 
miles easterly from Duluth. (See U. S. Lake 
Survey Chart No. 96, Lake Superior.) 
Existing project. Provides for two parallel piers 
at entrance, 835 and 1,017 feet long, respectively, 
200 feet apart, an entrance channel between piers 
150 feet wide with 15-foot depth, an irregularshaped 
turning basin 15 feet deep at inner end of 
piers from which two inner channels with 8-foot 
depth extend. One of these is 60 feet wide extending 
southerly for 340 feet and one 70 feet wide 
extending easterly 1,170 feet. 
Portion of dredging of entrance channel to complete 
project width and depth is considered unnecessary 
to meet present navigation requirements. 
Estimated cost of this portion of work, last 
revised in 1954, was $22,600. 
Local cooperation. Fully complied with. 
Terminal facilities. There are four privately 
owned fishing wharves which are considered adequate 
for existing conditions. 
Operations and results during fiscal year. Maintenance: 
Conditon surveys cost $661. Work on 
engineering for contained dike disposal cost 
$2,400. Environmental project review proceeded 
at a cost of $379. Derrickbarge Markus placed 130 
tons of rock on the east breakwater in October and 
November 1974 at a cost of $39,861. Dredge 
Galliard removed a total of 32,740 cubic yards to 
maintain project depth at a cost of $56,320. 
Administration costs were $15,179. All work was 
by hired labor. 
Condition at end of fiscal year. Existing project 
is complete except channel between piers has been 
dredged to only a 100-foot width. To complete 
project it would be necessary to widen channel 50 
feet, which is considered unnecessary to meet 
present navigation requirements and therefore 
classified inactive. Piers are in good condition. 
At end of fiscal year controlling depth was 12 
feet in lake approach, and 10 feet between piers 
and in northerly portion of turning basin and 8 feet 
in easterly inner channel. Lands owned by the 
United States total 7.80 acres. 
19. PRESQUE ISLE HARBOR, MICH. 
Location. On south shore of Lake Superior within 
city limits of Marquette and about 3 miles from 
Marquette Harbor. It is in an indentation about 1.5 
miles long and one-half mile wide in shore behind 
Presque Isle Point. (See Lake Survey Chart 935.) 
Existing project. A breakwater off Presque Isle 
Point and dredging harbor to depth of 28 feet in 
inner portion with 30 feet at entrance. For details 
see page 1021 of 1965 Annual Report. (See table 
27-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One merchandise and petro- 
27-8

ST. PAUL, MINN., DISTRICT 
leum receiving wharf and one ore dock. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $11,419. Engineering 
for mitigation of shore damage cost 
$26,385. Engineering for contained dike disposal 
cost $3,000. Repairs were made to breakwaters 
including placement of 541 tons of rock by Derrickbarge 
Coleman at a cost of $21,277. Administrative 
costs were $5,478. 
Condition at end of fiscal year. Project authorized 
by earlier acts was completed in 1939. A 
contract for harbor deepening authorized by 1960 
act was completed in April 1962 except for a 
section where rocks were encountered in southeast 
portion of harbor. Rock removal has been accomplishecd 
intermittently by hired labor and the project 
is completed. Breakwater is in good condition. 
Controlling depth was 28 feet. A reconnaissance 
report was completed in November 1970 concerning 
erosion of the beach north of Picnic Rocks and 
a detailed project report is being prepared. 
20. RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER. 
Location. Reservoirs are on the Mississippi 
River and several of its tributaries in Itasca, 
Beltrami, Hubbard, Aitkin, Cass, and Crow Wing 
Counties, Minn. (See table 27-C on reservoirs.) 
Previous project. For details see page 1888 of 
Annual Report for 1915, and page 1098 of Annual 
Report for 1938. 
Existing project. Provides for reconstruction 
from timber to concrete at Winnibigoshish, Leech 
Lake, Pokegama, Sandy Lake, and Pine River 
Dams, and construction of a concrete dam at Gull 
Lake. Pokegama was built on bedrock and the 
others on pile foundations. A portion of Leech 
Lake Dam from piers 26 to 39 was replaced with 
an earth fill. Constructed three dikes at Winnibigoshish, 
four at Pokegama, two at Sandy Lake, 
and 16 at Pine River. Sandy Lake Dam includes a 
lock 160 feet long, 30 feet wide, with a maximum 
lift of 9.5 feet and a depth of 2.5 feet on lower sill 
at low water which was converted to use as a spillway. 
(See table 27-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None. 
Operations and results during fiscal year. New 
work: At Gull Lake contracts for sewage treatment 
facilities, comfort station, and site work 
totaled $201,604. Archeological investigations 
were done at a cost of $13,693 under contract. At 
Sandy Lake contracts for sewage treatment facilities, 
comfort station, and site work totaled 
$183,146. At Leech Lake contracts for sewage 
treatment facilities, archeological investigations, 
and architect engineering investigations totaled 
$7,719. Engineering and design and supervision 
and administration costs were $43,426. Maintenance: 
Reservoirs were operated as required, recreation 
facilities were maintained, and miscellaneous 
inspections, repairs, and reports were made 
by hired labor including administration at a cost of 
$552,524. Contract work for road repair cost 
$13,086. 
A contract for boundary monumentation for the 
reservoirs cost $47,195. A contract for improvement 
of the discharge channel at Leech Lake cost 
$72,138. 
Condition at end of fiscal year. Existing project 
was completed in 1937. Flowage rights were 
acquired on all lands affected by construction, 
maintenance, and operation of reservoirs. A total 
of 1,861 acres in fee and easements on 296,365 
acres are owned by the United States. Structures 
are in fair condition. Recreation facilities for public 
use are being constructed intermittently at all 
reservoir areas. (See table 27-C for capacities and 
costs by reservoir.) 
21. ST. CROIX RIVER, MINN. & WIS. 
Location. From source in northwestern Wisconsin, 
flows southwesterly and then southerly about 
164 miles to Mississippi River at Prescott, Wis., 
about 41.7 miles below lower Burlington Northern 
railway bridge, Minneapolis, Minn. For its greater 
part, forms boundary between Minnesota and 
Wisconsin. (See Geological Survey map of Minnesota.) 
Existing project. Provides for maintenance of a 
channel, 9 feet in depth and of suitable width from 
mouth to Stillwater, Minn., 24.5 miles, created by 
improvement of upper Mississippi River; a channel 
3 feet deep at mean low water between Stillwater 
and Taylors Falls (27.3 miles); improvement of 
harbor and waterfront at Stillwater; and a smallboat 
harbor at Hudson, Wis. Estimated (1975) 
Federal cost of new work is $577,400. Latest 
authorization (1954) for maintenance work on 
reach between Stillwater and Taylors Falls is 
limited to an expenditure not exceeding $5,000 per 
year. (See table 27-B for authorizing legislation.) 
Local cooperation. Fully complied with for completed 
portion. For Hudson Harbor, see the annual 
report of 1970 for requirements. 
Terminal facilities. At Stillwater there is a concrete 
paved levee and a piling-and-timber trestle 
wharf on right bank. At other points along river, 
landing may be made on banks. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Derrickbarge Hauser removed 4,875 
27-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
cubic yards of material at a cost of $25,361. Environmental 
review cost $211. Administrative 
costs by hired labor were $12,228. 
Conditions at end of fiscal year. All new work 
was completed in 1930, except subsequently authorized 
harbor at Hudson. The United States 
owns 2.75 acres of land in fee at Taylors Falls and 
has easements over 7.57 acres of land at Bayport, 
Minn. Extension to provide a 9-foot channel from 
mouth to Stillwater was completed. August 12, 
1938 when full pool at dam 3 of Mississippi River 
canalization project was reached. Minimum draft 
from Stillwater to Taylors Falls is about 1 foot at 
extreme low water, and from mouth to Stillwater, 
9 feet. 
22. SAXON HARBOR, WIS. 
Location. On south shore of Lake Superior in 
Wisconsin at mouth of Oronto Creek, 27 miles 
southeast of harbor at Bayfield, Wis., and 21 miles 
westerly of harbor at Black River, Mich. It is also 
99 miles east of Duluth-Superior Harbor and 60 
miles west of Ontonagon Harbor, Mich. (See Lake 
Survey Chart 96.) 
Previous project. For details see page 1254 of 
Annual Report for 1962. 
Existing project. Provides for east and west 
breakwaters, an outer channel 10 feet deep, an 
inner basin and side channel 8 feet deep, and 
diversion of Oronto Creek to Parkers Creek by 
three short reaches of channel excavation and a 
levee. For detailed dimensions of features see page 
1025 of Annual Report for 1965. Existing project 
was authorized by 1958 River and Harbor Act (H. 
Doc. 169, 85th Cong., 1st sess., contains latest 
published map.) 
Local cooperation. Fully complied with. 
Terminal facilities. One wharf 300 feet long on 
east side of present harbor basin constructed by 
local interests. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $15,353. Investigation 
of shoreline erosion cost $34,324 by contract 
and $3,086 by hired labor. Work on environmental 
review of the project continued at a cost of $1,558. 
Engineering study on diked disposal was performed 
at a cost of $3,100. Administrative costs were 
$4,535. 
Condition at end of fiscal year. Harbor improvements 
were completed in November 1965 except 
for minor work. The project was fully completed in 
March 1968. Controlling depths are 9 feet in lake 
approach, 9 feet in channel between piers, and 7 
feet in inner basin and side channel. A reconnaissance 
report was completed in August 1971 concerning 
erosion of the shoreline west of the 
harbor. A detailed project report is being prepared 
to develop an acceptable plan for mitigation 
measures. 
23. TWO HARBORS, MINN. 
Location. Harbor is on north shore of Lake 
Superior, 27 miles northeasterly from Duluth, 
Minn. (See Lake Survey Chart 96.) 
Existing project. Narrowing natural entrance by 
construction of two breakwaters, 1,628 and 900 
feet long, from eastern and western points of bay, 
respectively; and dredging a maneuvering area on 
north side of harbor to 28 and 30 feet deep. A 
walkway on east breakwater is provided for public 
recreational use. For details see page 1026 of 
Annual Report for 1965. Areas along easterly and 
northerly edges of channel have not been fully 
deepened. This portion of project was reclassified 
from the "inactive" to "active" category in 1973. 
Estimated cost (1975) of this portion is $152,000. 
Local interests have indicated a need for additional 
study to determine the advisability of further 
harbor improvements. (See table 27-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. A resolution 
dated April 15, 1969 from the city council of 
Two Harbors requested a review of reports on 
Two Harbors to determine whether any further 
improvements are advisable at this time. This 
review is scheduled for the survey program. 
Terminal facilities. No publicly owned wharves. 
Three ore docks, tug wharf, an unused coal dock, 
and merchandise wharf are privately owned. 
Facilities considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $1,027. Breakwater 
repair cost $633. Environmental review cost 
$5,193. Administrative costs were $1,194. All 
work was by hired labor. 
Condition at end of fiscal year. Work authorized 
prior to 1960 act was completed in 1950. The 
timber superstructure of the east breakwater 
above low water depths badly deteriorated since 
its original construction in 1948 and severely 
damaged in a NE storm on December 12, 1968 has 
been repaired. A contract for replacing the timber 
superstructure with a concrete cap and repairing 
the public-use walkway was completed in 1972. 
24. WARROAD HARBOR AND RIVER, MINN. 
Location. At southwestern extremity of Lake of 
the Woods, 36 miles west of mouth of Rainy River. 
(See Lake Survey Chart 84, Lake of the Woods.) 
Existing project. Provides for a channel 8 feet 
27-10

ST. PAUL, MINN., DISTRICT 
deep from landing at Warroad to deep water in 
lake, channel being 9,200 feet long, 200 feet wide 
within harbor, and 300 feet wide out in lake; for a 
turning basin 500 by 900 feet to a depth of 8 feet; 
and for a pile-brush stone jetty on north side of 
channel extending from shore 700 feet into the 
lake. For additional details see page 1027 of 
Annual Report of 1965. Portion of dredging of 
entrance channel and turning basin to complete 
project width and depth is considered unnecessary 
to meet present navigation requirements, and excluded 
from foregoing cost estimate. Estimated 
cost (1954) of this portion is $355,200. (See table 
27-B for authorization legislation.) 
Local cooperation. None required. 
Terminal facilities. There is one publicly owned 
wharf. There are two commercial fish wharves, 
one of which is served by a spur track, and a 
number of minor wharves, all privately owned. 
Facilities are adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $2,333. Maintenance 
dredging was performed under contract at a 
cost of $69,430. A contract for water quality 
surveys cost $13,794. Administrative costs were 
$7,856. 
Condition at end of fiscal year. Project as a 
whole is complete except for inactive portion. Protective 
jetty completed in 1910 and reconstructed 
as a rubble mound in 1929 is in good condition. 
Turning basin at Warroad wharves was completed 
in 1911, and a channel 200 feet wide and 8 feet 
deep in 1915. Controlling depth in river chaniel 
and lake approach channel was 5 feet below 
low-water datum for a minimum width of 100 feet. 
Shore revetment needs minor repairs. A walkway 
on the jetty is provided for public use. 
25. RECONNAISSANCE AND 
CONDITION SURVEYS 
See table 27-D. 
26. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 27-E. 
27. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
See table 27-F. 
Beach Erosion 
28. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
See table 27-G. 
Flood Control 
29. BIG STONE LAKE AND WHETSTONE 
RIVER, MINN. AND S. DAK. 
Location. On Minnesota River near Ortonville 
and Odessa, Minn., and Big Stone City, S. Dak., at 
the outlet of Big Stone Lake and in Big Stone 
and Lac qui Parle Counties, Minn., and Grant 
County, S. Dak. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. Provides for a dam and reservoir 
on Minnesota River above U.S. Highway 75, 
modifications of Big Stone Lake outlet dam and silt 
barrier, bank stabilization along lower 6 miles of 
Whetstone River, channel improvement on Minnesota 
River for 3 miles below outlet control dam at 
Big Stone Lake along with necessary relocations 
and acquisition of lands. These improvements 
would be made for wildlife conservation and development, 
flood control, and recreation. For additional 
details see Annual Report for 1970. Estimated 
Federal cost (1975) for new work is 
$10,700,000 and $175,000 to be contributed by local 
interests. Project was authorized by 1965 Flood 
Control Act (H. Doc. 579, 87th Cong., 2d sess., 
contains latest map; and H. Doc. 193, 88th Cong., 
2d sess.). 
Local cooperation. See Annual Report for 1968 
for requirements. The project requires sponsorship 
from both the States of Minnesota and South 
Dakota. Formal resolution of assurances adopted 
by the Upper Minnesota River Watershed District 
on June 10, 1969 and accepted by the District 
Engineer on November 3, 1969. Formal resolution 
of assurances adopted by the East Dakota Conservancy 
Sub-District for South Dakota on October 
23, 1969 was furnished on November 18, 1969 
and accepted by the District Engineer on 
November 19, 1969. 
Operations and results during fiscal year. New 
Work: The land acquisition program was continued 
at a cost of $176,374. Boundary line surveys for 
monumentation cost $11,470. Contracts for relocation 
of telephone and power lines are underway 
at a cost of $21,356. A contract for the new dam 
above Highway 75 including associated roads and 
raising of an oxidation pond dike was completed 
and miscellaneous work performed at a cost of 
$137,339. Construction of recreation facilities by 
contract was initiated at a cost of $75,630. Engineering 
and design cost $117,448 and supervision 
and administration cost $64,573. Additional engineering 
of $2,002 was accomplished for the Ottertail 
Power Company in modifying plans for the Big 
Stone Lake Outlet Control structure. Costs will be 
reimbursed by the power company. Maintenance: 
Structure was operated and maintained and in- 
27-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
spections and evaluations performed at a cost of 
$37,700. 
Condition at end of fiscal year. Engineering and 
real estate activities were continued. A contract 
for construction of the new dam above Highway 75 
and roads, awarded in June 1972, was brought to 
99-percent completion. Surveys for land lines are 
complete, and the land acquisition program is 99 
percent complete. The first land payment was 
made on November 28, 1969 and 128 tracts have 
been purchased. A general plan between the Secretary 
of the Army and the Secretary of the Interior 
for administering the use of waters, land, or 
interests therein has been consummated. A cooperative 
agreement between the Corps of Engineers 
and the Bureau of Sport Fisheries and Wildlife 
was approved. 
30. BURLINGTON DAM, SOURIS RIVER, 
NORTH DAKOTA 
Location. In Ward County in northwestern 
North Dakota above Burlington, N. Dak., on the 
Souris River. The damsite is northeast of Burlington 
about one-half mile north of the confluence 
of the Souris and Des Lacs Rivers and about 10 
miles above Minot, N. Dak. (For general location, 
see Geological Survey Map of North Dakota.) 
Existing project. Authorized plan of improvement 
as modified by preliminary studies for the 
phase I design memorandum provides for a singlepurpose 
flood control reservoir at the authorized 
site near Burlington on the Souris River, a diversion 
tunnel joining the Des Lacs River to the 
Burlington Reservoir, channel improvements 
between Burlington and Minot and at Sawyer and 
Velva, snagging and clearing of the lower Souris 
River channel, and regulation of future floodplain 
land use downstream from the damsite. Estimated 
Federal cost (1975) for new work is $81,400,000. 
Project was authorized by 1970 Flood Control Act. 
(H. Doc. 321, 91st Cong., 2d sess., contains latest 
published map.) 
Local cooperation. See Annual Report for 1971 
for requirements. On May 26, 1971 the Ward 
County Water Management Board, the local sponsor, 
approved the motion to provide assurances of 
local cooperation. The resolution was furnished the 
District by letter dated June 16, 1971 and accepted 
by the District Engineer August 9, 1971. 
Operations and results during fiscal year. New 
work: Preconstruction planning was continued at a 
cost of $548,258. 
Condition at end of fiscal year. Preconstruction 
planning is in progress. 
31. EAU GALLE RIVER, WIS. 
Location. At and in vicinity of Spring Valley, 
Wis., on Eau Galle River 30 miles above its mouth 
at Chippewa River, and its tributary, Mines 
Creek, which flows through the village. Spring 
Valley is about 45 miles east of St. Paul, Minn., 
and 36 miles west of Eau Claire, Wis. (See Geological 
Survey map for Wisconsin for general location.) 
Existing project. Authorized plan of improvement 
as modified by further studies includes a 
retarding dam and reservoir on Eau Galle River 
immediately upstream from Spring Valley, and 
remedial works on Mines Creek including channel 
enlargement, a low levee, and a drop structure. 
Project provides for earth and rock-fill dam, an 
uncontrolled outlet and an uncontrolled spillway 
emerging above Mines Creek. See page 1030 of 
Annual Report for 1965 for further details. Proposed 
improvements on Burghardt Creek were 
eliminated. Improvements would provide complete 
protection near Spring Valley for standard project 
flood, and below that point in decreasing value in 
proportion to distance from reservoir. Permanent 
conservation pool will serve a local need for a 
recreation area. Estimated Federal cost (1975) for 
new work is $9,040,000. Project was authorized by 
1958 Flood Control Act (S. Doc. 52, 84th Cong., 
1st sess., contains latest published map.) 
Local cooperation. Fully complied with. See 
page 1083 of Annual Report for 1967. 
Operations and results during fiscal year. New 
Work: Engineering and design costs for recreation 
facilities were $20,072. Maintenance: Structure 
was operated and maintained, and inspection and 
evaluations were performed at a cost of $59,530. A 
flood alarm system for the recreation areas was 
installed at a contract cost of $73,812. 
Condition at end of fiscal year. Mines Creek 
improvements were substantially completed in 
1964; minor work was accomplished in 1966. A 
contract for dam, spillway, and discharge channel, 
started July 1, 1965, was completed in October 
1968. Recreational facilities have been provided. 
Remedial work to repair eroded gutters and road 
ditches was completed in September 1973. 
32. HOMME LAKE AND DAM, N. DAK. 
Location. Dam is on South Branch of Park 
River, about 4 miles upstream from Park River, 
N. Dak., and 62.1 miles above mouth of Park 
River. South, Middle, and North Branches, headwater 
streams of Park River, rise in Cavalier 
County in northeastern North Dakota and flow 
easterly to an almost common confluence near 
Grafton, N. Dak., forming main stream which 
27-12

ST. PAUL, MINN., DISTRICT 
flows easterly 35 miles to join Red River of the 
North about 35 miles south of the international 
boundary. (For general location, see Geological 
Survey map of North Dakota.) 
Existing project. See page 1285 of Annual 
Report for 1962. Project was authorized as Park 
River Reservoir by 1944 Flood Control Act (S. 
Doc. 194, 78th Cong., 2d sess.), and redesignated 
Homme Reservoir and Dam by Public Law 435, 
80th Congress, 2d session. Latest published map is 
in project document. 
Local cooperation. Fully complied with. Estimated 
total costs for all requirements of local 
cooperation under terms of project authorization, 
including required non-Federal contributions, are 
$62,800. In addition, local interests contributed 
$16,220 for construction of a water supply outlet 
through dam and incurred other costs of $19,600. 
Operations and results during fiscal year. Maintenance: 
Structure was operated and maintained, 
and inspections and evaluations performed at a 
cost of $42,493. Road and erosion repair by 
contract cost $99,102. 
Condition at end of fiscal year. Project completed 
in June 1956 except for additional recreational 
facilities which have been done intermittently 
since that time. Construction began in April 
1948 and major structures completed in May 1951. 
Structures are in good condition. Government has 
acquired 395 acres of land in fee and easements 
over 7.8 acres of land for project. An additional 6.3 
acres of land have been donated for recreational 
development and 3.75 acres have been acquired 
due to bank erosion bordering the project. 
33. KINDRED LAKE, SHEYENNE RIVER, 
N. DAK. 
Location. In Richland County, N. Dak., on the 
Sheyenne River, about 70 miles above its mouth 
and 5 miles above Kindred, N. Dak. (For general 
location, see Geological Survey map of North 
Dakota.) 
Existing project. Provides for a multiplepurpose 
impoundment for flood control, water 
quality control, recreation, and fish and wildlife 
purposes to control the runoff from 3,014 square 
miles. The improvements will be coupled with a 
revised operating plan for the existing Baldhill 
Dam and with appropriate floodplain management 
measures at communities along the river. See 
Annual Report for 1973 for details. Estimated 
Federal cost (1975) for new work is $40,300,000. 
Project was authorized by 1970 Flood Control Act 
(H. Doc. 330, 91st Cong., 2d sess., contains latest 
published map.) 
Local cooperation. See Annual Report for 1971 
for requirements. The North Dakota State Water 
Commission, in a letter dated September 24, 1968, 
has indicated a willingness to sponsor the project 
and provide assurances of local cooperation. These 
assurances have not been requested. 
Operations and results during fiscal year. Preconstruction 
planning not started. 
Condition at end of fiscal year. Preconstruction 
planning funds not available. A restudy was 
completed under the General Investigations Survey 
Program to provide more information on areas 
of concern expressed by the Department of the 
Interior. Effects of the reservoir upon groundwater 
levels and operation of the project for water 
quality control were studied. 
34. LAC QUI PARLE LAKE, 
MINNESOTA RIVER, MINN. 
Location. Works covered by this project lie 
along Marsh Lake and Lac qui Parle and the Minnesota 
River between head of Marsh Lake and 
Granite Falls, Minn. (For general location, see 
Geological Survey map of Minnesota.) 
Existing project. See page 1291 of Annual 
Report for 1962. 
Local coooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Project was operated and maintained, 
and inspections and evaluation performed at a cost 
of $91,940. Contract work for concrete repair cost 
$184,068, for Marsh Lake dike repair cost 
$124,536. 
Condition at end of fiscal year. Project has been 
operated by the Government since transfer from 
State of Minnesota to the United States in September 
1950. The United States owns fee title to 
516.3 acres of land and easements on 19,826.7 
acres of land. Special easements on 32.8 acres of 
land and 1.3 acres of land in fee were also acquired. 
In 1957, 60.1 acres were withdrawn from 
public lands for use of the Department of the 
Army. Land acquisition is complete. Construction 
under present plan of improvement was started in 
September 1941 and completed in December 1951 
except for recreational facilities. All structures are 
in good condition. 
35. LA FARGE LAKE AND CHANNEL 
IMPROVEMENT, WIS. 
Location. Rises in Monroe County in southwestern 
Wisconsin and flows south and southwest 
through Vernon, Richland, and Crawford Counties 
emptying into Wisconsin River about 16 miles 
above junction of latter stream with Mississippi 
River. (For general location see Geological Survey 
map of Wisconsin.) 
27-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. Provides for a dam and impoundment 
on the Kickapoo River about 1 mile 
upstream from village of La Farge, operated for 
flood control, fish and wildlife conservation, 
general recreation, and a reduction of aggradation 
downstream from the dam. Earth-fill dam 3,960 
feet in length will be 103 feet above the valley 
floor with crest elevation of 895.0 feet above mean 
sea level. An uncontrolled spillway with crest of 
870.5 feet will be about 500 feet long. A 7-footdiameter, 
gate-controlled circular conduit with an 
invert elevation of 800.0 feet. About 29 miles of 
roads and highways will be relocated and recreation 
facilities will be provided at 13 sites totaling 
1,400 acres of land. 
Supplemental protection will be provided at 
Soldiers Grove and at Gays Mills by means of 
about 6,000 feet of levees at each location. Supplementary 
channel improvement and interior drainage 
facilities will be constructed at both locations. 
Estimated Federal cost (1975) for new work is 
$51,500,000. Project was authorized by 1962 Flood 
Control Act (H. Doc. 557, 87th Cong., 2d sess., 
contains latest published map.) 
Local cooperation. None required for construction 
of La Farge Lake. See page 1087 of Annual 
Report for 1967 for requirements for local protection 
works. Local interests have not been requested 
to furnish assurances. 
Operations and results during fiscal year. The 
land acquisition program was continued at a cost 
of $569,554. Reforestation under contract cost 
$1,023. Relocation of utilities by contract cost 
$61,947. A contract was executed in 1971 with the 
State of Wisconsin for preparation of plans and 
specifications and for accomplishing contractual 
work for all highway and road relocations with 
reimbursement by the Government. Construction 
contracts for road work. from La Farge to Rockton 
are underway. Costs for the fiscal year were 
$2,233,051. Contracts for a Master Plan for Resource 
Management and for archeological investigations 
cost $25,926. A contract for a preimpoundment 
water quality and river basin environmental 
study was completed at a cost of $11,632. Contract 
work for construction of the right abutment and 
core trench and a contract for the construction of 
a maintenance building continued. Costs for the 
year were $1,049,900 and $98,800, respectively. 
Miscellaneous construction costs were $85,216. A 
contract for the preparation of design memorandums 
for Soldiers Grove and Gays Mills was continued 
at a cost of $86,822. Engineering and design 
by hired labor cost $282,990. Supervision and administration 
cost $139,847. 
Condition at end of fiscal year. General and Real 
Estate design memorandums and detailed plans 
for the La Farge Dam and spillway and for relocations 
have been completed. Land acquisition 
program under way is 79 percent complete. Land 
acquisition negotiations began in December 1968. 
The first land payment was made on January 15, 
1969 and 342 tracts have been purchased. Construction 
has been initiated. Contracts for excavation 
of the left abutment, for test wells, and for 
construction of the outlet works and right abutment 
have been completed. 
36. LAKE ASHTABULA AND BALDHILL 
DAM, SHEYENNE RIVER, N. DAK. 
Location. Baldhill Dam is on the Sheyenne 
River, 16 miles upstream from Valley City, N. 
Dak., and about 271 miles above mouth. Sheyenne 
River rises in central North Dakota and flows 500 
miles generally southeast to enter Red River of 
the North about 10 miles north of Fargo, N. Dak. 
(For general location see Geological Survey map of 
North Dakota.) 
Existing project. See page 1287 of Annual 
Report for 1962. Project was authorized by Flood 
Control Act of 1944 (S. Doc. 193, 78th Cong., 2d 
sess., contains latest published map). Reservoir 
above Baldhill Dam was designated as Lake 
Ashtabula by Public Law 772, 81st Congress, 2d 
session. 
Local cooperation. See page 1288 of Annual 
Report for 1962. Complied with except for construction 
of Fargo diversion dam and ditch for 
which assurances furnished by city of Fargo were 
approved by the Secretary of War on June 26, 
1947. Necessity for this feature will be reviewed. 
Operations and results during fiscal year. New 
work: Contract work continued for a comfort 
station and parking area at a cost of $56,441. 
Engineering and design, and supervision and 
administration cost $7,942. Maintenance: Project 
operated, minor repairs made to structures, 
recreation facilities maintained, engineering and 
design, and supervision and administration cost 
$201,180. Construction by contract for recreation 
facilities at Eggerts Landing cost $13,186, and at 
Main Public Use Area cost $71,375. 
Condition at end of fiscal year. Project completed 
in March 1956 except construction of recreational 
facilities, which is being accomplished 
intermittently. United States owns 7,816.5 acres 
of land in fee and easements on 666.2 acres. 
Construction initiated in July 1947 and major 
features completed in November 1950. Dam was 
placed in permanent operation in spring of 1951. 
Structures are in good condition. 
27-14

ST. PAUL, MINN., DISTRICT 
37. LAKE TRAVERSE AND BOIS DE SIOUX 
RIVER, S. DAK., AND MINN. 
Location. Works covered by this project lie 
along Lake Traverse and Bois de Sioux River 
between upper end of Lake Traverse at Browns 
Valley, Minn., and the mouth of Bois de Sioux 
River at Breckenridge, Minn. Lake drains through 
river to Red River of the North, and the two 
waters form a portion of boundary between State 
of Minnesota and States of North and South 
Dakota. (For general location, see Geological Survey 
map of Minnesota.) 
Existing project. See page 1289 of Annual 
Report for 1962. Existing project was authorized 
by Flood Control Act of June 22, 1936. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Project was operated, miscellaneous 
inspections and reports made, and minor repairs 
made to structures at a cost of $82,103. 
Conditions at end of fiscal year. Existing project 
was completed in June 1948, except for minor recreation 
facilities. Fee title to 1,144.13 acres and 
easements on 6,155.35 acres of land have been 
acquired. White Rock Dam and Reservation control 
structures are in operation, and structures 
and appurtenances are in good condition. Remedial 
work for repair of apron at White Rock Dam was 
completed in November 1968. Roadways across 
structures are open to public travel. 
38. MANKATO AND NORTH MANKATO, 
MINN. 
Location. Along Minnesota River between miles 
103.5 and 109.5 near Mankato, North Mankato, 
and Le Hillier, in south-central Minnesota. (For 
general location see Geological Survey map of 
Minnesota.) 
Existing project. As modified as a result of 
severe 1965 flood, provides for protection of communities 
of Mankato, North Mankato, and Le 
Hillier by means of levees and floodwalls with 
pumping plants and interior drainage facilities. 
See page 1090 of Annual Report for 1967 for 
further details. Additional channel improvement, 
levees, pumping, and interior drainage features 
have been included in the Mankato unit of the 
project for protection from the high flows of Indian 
Creek. Expansion of Indian Creek improvements 
were made during detailed studies due to revised 
hydraulic conditions. Estimated Federal cost 
(1975) for new work is $32,500,000. Project was 
authorized by 1958 Flood Control Act (H. Doc. 
437, 84th Cong., 2d sess., contains latest published 
map.) Project was modified by 1965 Flood Control 
Act, and by the Water Resources Development 
Act of 1974. 
Local cooperation. Fully complied with for work 
under contract. See Annual Report for 1973 for 
requirements. Resolutions agreeing to provide 
formal assurances of local cooperation, when requested, 
were passed by the city council of North 
Mankato, Mankato, and South Bend Township (Le 
Hillier), respectively, on November 12, 1968. 
Operations and results during fiscal year. Contract 
work for construction at North Mankato from 
the upstream segment downstream to Monroe 
Avenue has been completed. Contract work continued 
for the improvements in Mankato, and for 
Le Hillier. Fiscal year construction costs for 
improvements at Mankato were $927,925, at North 
Mankato were $23,354, and at Le Hillier were 
$1,266,138. Detailed planning for improvements at 
Mankato along the Minnesota River and along 
Indian Creek was continued. Engineering and 
design by hired labor cost $390,608, by contract 
cost $167,309. Supervision and administration cost 
$234,882. 
Condition at end of fiscal year. Work on detailed 
plans virtually completed was suspended in 1962 
due to lack of local cooperation. Following the 
record flood in 1965, work was resumed. General 
Design Memorandum and Supplements 1 and 2 are 
completed. Supplement No. 2 provides for 
construction of local protective works in stages. 
Detailed designs and plans and specifications are 
complete for stage 1 construction at North 
Mankato, and for improvements at Mankato along 
the Blue Earth River and for Le Hillier. Stage 1 
construction in North Mankato is complete. Construction 
by contract in Mankato and Le Hillier is 
underway. Detailed planning for remaining features 
is in progress. 
39. MINOT, N. DAK. 
Location. In Ward County in northwestern 
North Dakota on the Souris River, extending from 
Burlington through Minot to the village of Logan. 
The river meanders through Minot, flowing 
generally from west to east and divides the community 
into two parts. (For general location, see 
Geological Survey map of North Dakota.) 
Existing project. Project provides for channel 
improvement within a 37.0-mile reach of the 
Souris River extending from Burlington to Logan. 
For details see Annual Report for 1973. 
Estimated Federal cost (1975) for new work is 
$19,100,000. Project was authorized in 1970 under 
section 201 of the Flood Control Act of 1965 (H. 
Doc. 91-321, 91st Cong., 1st sess., contains latest 
published map). Resolutions were adopted by the 
Public Works Committees of the Senate on June 
25, 1970 and the House on July 14, 1970. 
27-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. See Annual Report for 1971 
for requirements. The Minot City Council on April 
5, 1971 and the Ward County Commissioners on 
May 19, 1971 provided necessary subassurances of 
local cooperation to the Ward County Management 
Board. On May 26, 1971 the Ward County Water 
Management Board approved the motion to 
provide assurances of local cooperation. The resolution 
was furnished by letter dated June 16, 1971 
and accepted by the District Engineer on August 
9, 1971. 
Operation and results during fiscal year. New 
work: A contract for channel improvement for 
Reach A-2 awarded in September 1973 is underway. 
Another contract for Reach B-1 improvements 
awarded in January 1974 is also underway. 
Contracts for construction in Reaches B-2, C, and 
D were awarded in January, April and June 1975, 
respectively, and construction is underway. Construction 
costs by contract for the year amounted 
to $1,514,102. Construction costs by hired labor 
were $45,977. Engineering and design by hired 
labor cost $405,631 and by contract cost $218,112. 
Supervision and administration costs were 
$227,295. 
Condition at end of fiscal year. Construction of 
Roosevelt Park improvements and snagging and 
clearing Reach A-1 downstream of Minot have 
been completed. Construction contracts awarded 
for reaches A-2, B-1, B-2, C, and D. Preparation of 
plans and specifications for remaining features is 
in progress. 
40. PRAIRIE DU CHIEN, WIS. 
Location. In Crawford County in northwestern 
Wisconsin on the left bank of the Mississippi 
River. (For general location, see Geological Survey 
map of Wisconsin.) 
Existing project. Combines total evacuation 
with flood proofing and land use control measures 
to provide the desired reduction of potential flood 
damages within design limits. Evacuation would 
be accomplished by purchase and relocation of all 
structures not meeting the land use criteria for 
floodway and floodplain areas as established by 
State law and adopted city ordinances. Estimated 
cost (1975) to the United States for new work is 
$3,120,000. Project was authorized by Water Resources 
Development Act of 1974. 
Local cooperation. See Annual Report for 1974 
for requirements. A local assurance agreement 
will be requested after completion of the design 
memorandum. By resolution dated February 17, 
1970 the Prairie du Chien City Council indicated 
support for the project. Then based upon revised 
requirements of local cooperation from that submitted 
earlier, a revised resolution of intent, dated 
September 9, 1970, indicating the willingness and 
ability of the city to meet the requirements of local 
cooperation when requested was obtained. 
Operations and results during fiscal year. Preconstruction 
planning was initiated at a cost of 
$32,995. 
Condition at end of fiscal year. Preconstruction 
planning is in progress. 
41. RED LAKE RIVER, MINN., INCLUDING 
CLEARWATER RIVER, MINN. 
Location. Works covered by this project lie 
along upper reach of Red Lake River and also 
along Clearwater River, a tributary of Red Lake 
River, between a point near Plummer, Minn., and 
a point just above the mouth of Ruffy Brook. Red 
Lake River, principal tributary of Red River of the 
North, has its source at the outlet of Lower Red 
lake in northwestern portion of Minnesota and 
flows westerly about 196 miles to its junction with 
Red River of the North at East Grand Forks, 
Minn. Clearwater River has a general westerly 
course from its source near Ebro, Minn., about 205 
miles to its junction with Red Lake River at Red 
Lake Falls, Minn. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. See page 1281 of Annual 
Report for 1962. Project was authorized by 1944 
Flood Control Act (H. Doc. 345, 78th Cong., 1st 
sess., contains latest published map.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Structures were operated and maintained 
and miscellaneous inspections and reports were 
made by hired labor at a cost of $34,200. 
Condition at end of fiscal year. Construction of 
major improvements on Red Lake River initiated 
in February and the Clearwater River initiated in 
October 1948 were completed in June 1956. Replacement 
of a rock and brush dam on RedLake 
River at Indian boundary with a concrete structure 
and appurtenant work was completed in June 
1959 to restore marshes in the area to better wildlife 
conditions. Construction of a bridge on Clearwater 
Road was completed by the Indian Service 
in July 1965. A contract for improvements on Red 
Lake River was completed in November 1966, and 
a contract for restoration of water levels in Red 
Lake River marshes was completed in July 1967. 
Increased slope protection downstream of the 
control structure was completed in November 
1968. Operation of Red Lake Dam was assumed by 
the Corps on April 1, 1951. Channels are in good 
condition and indicate effectiveness of project as a 
flood control measure. 
27-16

ST. PAUL, MINN., DISTRICT 
42. RED RIVER OF THE NORTH DRAINAGE 
BASIN, MINN., S. DAK. & N. DAK. 
Location. Red River of the North basin, within 
the United States, includes northeastern corner of 
South Dakota and much of eastern North Dakota 
and northwestern Minnesota. Red River of the 
North, formed by confluence of Otter Tail and Bois 
de Sioux Rivers, flows northward through this 
region, forming boundary between North Dakota 
and Minnesota. (For general location of basin, see 
Geological Survey maps of Minnesota and South 
Dakota.) 
Previous project. See page 1278 of Annual 
Report for 1962 for navigation and flood control 
projects in the basin, not part of this project. 
Existing project. Project includes improvements 
for local protection in interests of flood control and 
major drainage accomplished by channel improvement, 
levees, etc., in addition to construction of a 
multiple-purpose reservoir on Otter Tail River to 
control floods and, in conjunction with previously 
authorized Federal reservoir project at Baldhill 
site of Sheyenne River and at Red lake, to increase 
low flows for water supply and pollution abatement. 
(See table 27-H for active units in comprehensive 
basin plan.) 
Project was authorized by Flood Control Acts of 
1948 and 1950. Public Works Authorization Act, 
1957, authorized Chief of Engineers to acquire 
such lands as were beyond legal authority of city 
of Grand Forks to acquire. Section 205 of the Flood 
Control Act of 1970 provided for extension of the 
expiration date for the East Grand Forks project. 
Authorization of the Kindred Lake, Sheyenne River 
project by the 1970 Flood Control Act provided for 
the deletion of channel improvement on the lower 
48.8 miles of the Sheyenne River authorized under 
the Flood Control Acts of 1948 and 1950. Latest 
published map is in House Document 185, 81st 
Congress, 1st session. 
Local cooperation. See page 1039 of Annual 
Report for 1965. Following the flood of 1965, the 
city of East Grand Forks requested reactivation of 
the project and furnished a resolution adopted 
May 11, 1965, indicating its willingness to meet 
the requirements of local cooperation. Expiration 
date for the East Grand Forks project was 
extended to April 17, 1975 permitting local 
interests additional time to furnish assurances of 
local cooperation. A local assurance agreement 
was passed by the city on March 27, 1975 and 
accepted by the acting Director of Real Estate, 
OCE for the Secretary of the Army on April 9, 
1975. 
Operations and results during fiscal year. Maintenance: 
Orwell Lake and Dam were operated as 
required and miscellaneous inspections, reports, 
and repairs were made at a cost of $62,524. A 
contract for a road below the dam was completed 
at a cost of $13,482. 
Condition at end of fiscal year. Major construction 
for all active units except for East Grand 
Forks, Minn., is complete. A total of 1,985 acres of 
land for Orwell Lake and Dam is owned in fee by 
the United States. See page 1281 of Annual Report 
for 1962 for periods of completion at active units of 
project other than Fargo. Work at Fargo, N. Dak., 
started in May 1959, was completed in July 1963. 
(See table 27-H at end of chapter for total costs of 
new work to June 30, 1975.) 
Costs to June 30, 1975 for operation and maintenance 
of Orwell Lake and Dam are $737,365. 
Total costs for active portion of project are 
$7,157,213. In addition, $350,034 was expended 
from contributed funds for work done for local 
interests. 
43. RED RIVER OF THE NORTH AT 
OSLO, MINN. 
Location. In Marshall County in northwestern 
Minnesota on the Red River of the North about 20 
miles north of Grand Forks, North Dakota. (For 
general location, see Geological Survey map of 
Minnesota.) 
Existing project. Provides for construction of a 
levee encircling the village of Oslo and an agricultural 
tract north of the village. Wherever 
possible, the levee will be constructed contiguously 
with an existing emergency levee, and will 
be about 10 feet high and 3.2 miles long with a top 
width of from 10 to 12 feet. The project will also 
provide interior drainage facilities including a 
pumping station, two ponding areas, interceptor 
and outfall sewers, and drainage ditches; highway 
and street ramps; temporary sandbag closures; 
and landscape measures. Total Federal costs 
(1975) for new work are estimated at $1,343,000. 
Project was approved by the Chief of Engineers 
for construction on August 2, 1972 under the 
authority contained in section 205 of the 1948 
Flood Control Act, as amended. 
Local coooperation. See Annual Report for 1973 
for requirements. 
A local assurance agreement required by Public 
law 91-611 was adopted by the village of Oslo on 
October 15, 1972. 
Operation and results during fiscal year. New 
work: Construction by contract continued at a cost 
of $891,506. Engineering and design and supervision 
and administration costs were $40,117. 
Condition at end of fiscal year. A construction 
contract was awarded in June 1974. Construction 
is in progress. 
27-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
44. RED RIVER OF THE NORTH AT 
PEMBINA, N. DAK. 
Location. In Pembina County in the extreme 
northeastern corner of North Dakota at the 
junction of the Pembina River and the Red River 
of the North, about 25 miles south of the international 
boundary. (For general location, see Geological 
Survey map of North Dakota.) 
Existing project. Provides for construction of a 
combination levee and floodwall about 15,600 feet 
in length encircling the city and associated interior 
drainage facilities including a pumping station, 
ponding area, and interceptor sewers and ditches; 
road and street ramps; and a highway and two 
railroad closures. These structural features would 
be supplemented by a sound flood-plain management 
program for South Pembina. Total Federal 
costs (1975) for new work are estimated at 
$2,000,000. Project was approved by the Chief of 
Engineers for construction on October 5, 1971 
under the authority contained in section 205 of the 
1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1972 
for requirements. 
On December 16, 1971, the city of Pembina was 
requested to provide a contractual agreement 
required by Public Law 91-611. The local assurance 
agreement was adopted by the city of 
Pembina on January 31, 1972. 
Operation and results during fiscal year. New 
work: Construction by contract continued at a cost 
of $912,428. Engineering and design and supervision 
and administration costs were $84,863. 
Condition at end of fiscal year. A construction 
contract was awarded in May 1974. Construction is 
in progress. 
45. ROCHESTER, MINN. 
Location. In Olmsted County in southeastern 
Minnesota on the South Fork of the Zumbro River. 
(For general location, see Geological Survey map 
of Minnesota.) 
Existing project. Provides for channel improvement 
supplemented by levees and flood proofing 
measures at and in the vicinity of Rochester, together 
with appropriate floodplain regulation 
measures. Principal project features include 
approximately 3.2 miles of concrete-lined channel, 
3.6 miles of riprap channel, 3.2 miles of grasssloped 
channels, 8,100 feet of levees, three pumping 
stations, interceptor sewers and ditches for 
interior drainage, and flood proofing of three large 
municipal buildings. A river walkway corridor 
system, two new parks, and other environmental 
treatment measures are also included in the proposed 
plan. Estimated cost (1975) to the United 
States for new work is $45,300,000. Project was 
authorized by the Water Resources Development 
Act of 1974 (H. Doc. 156, 93rd Cong., 1st sess., 
contains latest published map.) 
Local cooperation. See Annual Report for 1974 
for requirements. 
Operations and results during fiscal year. Preconstruction 
planning was initiated at a cost of 
$43,382. 
Condition at end of fiscal year. Phase I design 
memorandum stage of preconstruction planning is 
in progress. The Phase II stage will be initiated 
upon fulfilling the requirements of section 1(b), 
Water Resources Development Act of 1974. 
46. ROSEAU RIVER, MINN. 
Location. In Roseau County and northeastern 
Kittson County, in northwestern Minnesota, and 
in south-central Manitoba, Canada. (For general 
location of the works in United States see Geological 
Survey map of Minnesota.) 
Existing project. Provides for improvement of 
Roseau River for flood control consisting of 44.4 
miles of channel improvement, two sections of 
earth levees with lengths of 1.9 and 5.9 miles, 
respectively, 76 side ditch inlet transitions; 
remedial works along 16.6 miles of channel in 
Canada or an acceptable alternative therefor; 
earth plugs provided with flap-gated culverts for 
water control in abandoned channel (loops for 
conservation interests); one new bridge; and alteration 
of the existing dam in Roseau Village. 
Remedial works will be constructed in Canada at 
the expense of the United States. Estimated cost 
(1975) to the United States for new work is 
$13,800,000, including $3,400,000 for cost of work 
in Canada to be accomplished with United States 
funds. Project was authorized by Flood Control 
Act of 1965 (H. Doc. 282, 89th Cong., 1st sess., 
contains latest published map.) 
Local cooperation. See Annual Report for 1968 
for requirements. Local interests have formed a 
Roseau River Watershed District but have not 
been requested to furnish local cooperation. 
Operations and results during fiscal year. New 
work: Planning activities were continued relative 
to coordination of the project plan with Canadian 
interests and the International Joint Commission. 
Engineering and design cost $73,748. Environmental 
studies were continued by contract at a 
cost for the year of $7,791. 
Condition at end of fiscal year. Planning is in 
progress and coordination with Canadian interests 
and the IJC is underway. The general design 
memorandum was submitted in October 1971 and 
approved in March 1972 as a basis for further 
27 18

ST. PAUL, MINN., DISTRICT 
planning and design, subject to comment and resolution 
of international aspects of the project. Preparation 
of plans and specifications is being 
delayed pending approval by the IJC relative to a 
review of the project by the International Roseau 
River Engineering Board estblished by the IJC on 
August 26, 1971. The Board submitted a Final 
Report to the IJC in September 1975. The report 
is currently under review. 
47. RUSHFORD, MINN. 
Location. At confluence of Root River and Rush 
Creek adjacent to city of Rushford in Fillmore 
County in southeastern Minnesota. Confluence of 
streams is 32.5 miles above mouth of Root River, a 
tributary of the Mississippi River. (For general 
location see Geological Survey map of Minnesota.) 
Existing project. Provides for improvements on 
Root River and Rush Creek to protect city of 
Rushford from floods expected to occur once in 200 
years. See page 1095 of Annual Report for 1967 for 
further details. Project was authorized by 1958 
Flood Control Act (H. Doc. 431, 84th Cong., 2d 
sess., contains latest published map.) 
Local cooperation. See page 1095 of Annual 
Report for 1967 for requirements. Assurances of 
local cooperation were accepted on March 8, 1967. 
The project was turned over to local interests on 
December 15, 1968, for operation and maintenance. 
Operations and results during fiscal year. New 
work: A contract for additional riprap on an upstream 
portion of the Root River was completed at 
a cost of $131,732. Engineering and design and 
supervision and administration cost $17,584. 
Studies indicate further erosion problems which 
will require correction. 
Condition at end of fiscal year. Construction of 
general improvements was essentially completed 
in November 1968. Construction of track raise and 
bridge relocation by the railroad was physically 
completed in June 1969. Placing riprap at the railroad 
bridge was completed in November 1969. A 
contract for additional riprap on the Root River 
awarded in June 1974 has been completed. 
48. STATE ROAD AND EBNER COULEES, 
WIS. 
Location. In La Crosse County in west-central 
Wisconsin, on the east side of the city of La 
Crosse. (For general location, see Geological 
Survey map of Wisconsin.) 
Existing project. The plan of improvement for 
State Road Coulee provides for channel deepening 
and enlarging downstream from Hagen Bridge to 
the mouth, and includes an 11,600-foot section of 
concrete-lined, trapezoidal-shaped channel, a 600- 
foot-long concrete flume, a drop structure, a 
stilling basin, five new street bridges, and alteration 
of a railroad bridge. The plan of improvement 
for Ebner Coulee provides for diversion 
works about 8,600 feet long, controlling flood flows 
through a concrete flume, and twin precastconcrete 
conduits into an enlarged Miller Coulee 
channel and thence into a marshy area in the La 
Crosse River floodplain. Estimated cost (1975) to 
the United States for new work is $15,700,000. 
Project was authorized by 1968 Flood Control Act 
(H. Doc. 360, 90th Cong., 2d sess., contains latest 
published map.) 
Local cooperation. See page 826 of Annual 
-Report for 1969. A local assurance agreement will 
be requested after completion of the design memorandum. 
Operations and results during fiscal year. New 
work: Planning for the General Design Memorandum, 
Phase I was continued at a cost of $123,585. 
Condition at end of fiscal year. Preconstruction 
planning is in progress. 
49. TWIN VALLEY LAKE, WILD RICE 
RIVER, MINN. 
Location. In Norman County in west-central 
Minnesota, northeast of the city of Moorhead, on 
the Wild Rice River about 1 mile upstream from 
Twin Valley, Minn. The Wild Rice River is a tributary 
of the Red River of the North. (For general 
location, see Geological Survey map of Minnesota.) 
Existing project. Project provides for a 52,200 
acre-foot impoundment created by an earth-fill 
dam 84 feet high, having a crest length of 7,700 
feet including low-flow outlet works consisting of 
an 11-foot-diameter gated circular conduit through 
the south abutment of the embankment. An emergency 
spillway would have a 680-foot fixed crest 
concrete section with a grass-lined outlet channel 
of about 2,300 feet in length. Storage capacity 
would provide 7,500 acre-feet for conservation and 
sedimentation and 44,700 acre-feet for flood control. 
The proposed works include development of 
three recreation areas along the margin of the lake 
for public use. The Federal Government would 
acquire about 3,500 acres of land necessary for 
carrying out the purposes of the project. 
Estimated Federal cost (1975) for new work is 
$16,200,000. Project was authorized by 1970 Flood 
Control Act (H. Doc. 366, 90th Congress, 2d sess., 
contains latest published map.) 
Local cooperation. See Annual Report for 1971 
for requirements. Local interests have not been 
requested to furnish assurances. The Norman 
County Board of Commissioners, by resolution 
27-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
dated November 7, 1974, has declared its intention 
to provide local cooperation for recreation and fish 
and wildlife enhancement. Both the Norman 
County Board of Commissioners and the Wild Rice 
River Watershed District have indicated the 
capability to provide assurances of local cooperation 
relating to flood control improvements. 
Operations and results during fiscal year. New 
work: Preconstruction planning was continued at a 
cost of $132,805. 
Condition at end of fiscal year. Preconstruction 
planning is in progress. 
50. WILD RICE RIVER-SOUTH BRANCH 
AND FELTON DITCH, MINN. 
Location. In Clay and Norman Counties in westcentral 
Minnesota northeast of the city of Moorhead, 
Minn. The South Branch of the Wild Rice 
River and Felton Ditch drain areas of 253 and 122 
square miles and enter the Wild Rice River at 
points 29.5 and 20.5 miles, respectively, above its 
confluence with the Red River of the North. (For 
general locations, see Geological Survey map of 
Minnesota.) 
Existing project. Provides for increasing the 
capacities of the South Branch and Felton Ditch 
channels by widening the existing channels 
through the floodplain. Debris removal would be 
accomplished in the lower reaches of both streams. 
In addition, short reaches of low dikes would be 
constructed on both banks of Felton Ditch near the 
upper limit of improvement. The plan also includes 
bridge and culvert structure alterations, new 
bridges, multiplate pipe arches, side ditch inlet 
and lateral ditch entry modifications, and a drop 
inlet structure. The project would provide flood 
protection in both watersheds for a 6-percent 
chance flood and outlets necessary for removal of 
crop-damaging surface waters from lateral and 
on-farm drainage systems. Estimated Federal cost 
(1975) for new work is $3,500,000. Project was 
authorized by 1968 Flood Control Act (H. Doc. 98, 
90th Cong., 1st sess., contains latest published 
map.) 
Local cooperation. See page 826 of Annual 
Report for 1969 for requirements. Assurances of 
local cooperation have not been requested. 
Operation and results during fiscal year. New 
work: Preconstruction planning was continued at a 
cost of $138,876. 
Condition at end of fiscal year. Preconstruction 
planning is in progress. 
51. WINONA, MINN. 
Location. At Winona in Winona County in southeastern 
Minnesota on the right bank of the Mississippi 
River about 725 miles above mouth of Ohio 
River. (For general location see Geological Survey 
map of Minnesota.) 
Existing project. See page 833 of Annual Report 
for 1968 for completed upstream improvements 
authorized by the Flood Control Act of 1958 
providing for a continuous flood barrier about 6.1 
miles long with related pumping and interior 
drainage facilities. Federal costs amounted to 
$2,147,131 of which $111,500 was expended for the 
portion then deferred for restudy and $17,316 was 
contributed by local interests. 
Improvement authorized in 1971 under Section 
201 of the Flood Control Act of 1965 (H. Doc. 152, 
92d Cong., 1st sess., contains latest published 
map) provides for levee and floodwall protection 
with necessary interior drainage works for the 
riverfront and the Lake Winona closure reaches, 
as well as a sound floodplain management program 
to prevent unwise development of the area 
bordered by U.S. Highway 61 and Burns Valley 
and Pleasant Valley Creeks. The plan would also 
provide the downstream flood barrier needed to 
prevent Mississippi River backup flows from 
entering Lake Winona and inundating the area 
now only partially protected by the completed 
segment of the project authorized by the 1958 
Flood Control Act. The selected plan would also 
provide control of Burns Valley Creek by means of 
channel improvement, raising and extending the 
existing levee system, a drop structure, an erosion 
control structure, and a sewer line modification. 
Earth levees, averaging 10 feet in height and 
totaling approximately 3.8 miles in length, 
comprise about 85 percent of the proposed flood 
barrier. Concrete floodwalls, also averaging about 
10 feet in height, total about 3,400 feet in length. 
Estimated Federal cost (1975) for new work is 
$16,100,000 and $306,000 is to be contributed by 
local interests. Resolutions authorizing the project 
were adopted by the Public Works Committees of 
the House on July 29, 1971, and the Senate on 
November 18, 1971. 
Local cooperation. Fully complied with for completed 
work. See page 833 of Annual Report for 
1968 for requirements. 
For improvements authorized in 1971 see 
Annual Report for 1972 for requirements. A resolution 
was passed and approved on February 2, 
1970 by the Winona City Council indicating 
support for the plan of improvement and the willingness 
and ability of the city to meet the 
requirements of local cooperation when requested. 
Local interests have not been requested to furnish 
assurances. 
Operations and results during fiscal year. New 
27-20

ST. PAUL, MINN., DISTRICT 
work: Preconstruction planning was continued at a 
cost of $250,919. 
Condition at end of fiscal year. The upstream 
improvement except for a portion of the project 
raising and extending the existing levee downstream 
from the Lake Winona outlet was completed 
in August 1967. At the request of local 
interests, the uncompleted portion of the project 
authorized in 1958 was not constructed in order 
that the scope of the project could be reconsidered 
to allow for the protection of additional lands 
needed by the city for industrial expansion. This 
work was deferred for restudy and now has been 
deauthorized by approval and authorization in 1971 
of additional protection for Winona. Preconstruction 
planning for the improvement authorized in 
1971 is in progress. 
Total costs for the entire project were 
$2,489,550 of which $2,472,234 was from Federal 
funds and $17,316 contributed funds, all for new 
work. 
52. ZUMBRO RIVER, MINN. 
Location. Lower end of Zumbro River, in 
Wabasha County in southeastern Minnesota, 
between Kellogg, Minn., and its mouth at the 
Mississippi River. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. Provides for construction of 
about 15,900 feet of continuous channel improvement 
including two channel cutoffs, the construction 
of a system of continuous set-back levees, 
totaling about 23,500 feet, paralleling both banks 
of the river along the channel enlargement reach, 
and slope protection of riverbank areas susceptible 
to bank erosion, all to alleviate damages from 
flooding. Project was authorized by 1965 Flood 
Control Act (H. Doc. 246, 88th Cong., 2d sess., 
contains latest published map.) 
Local cooperation. See page 827 of Annual 
Report for 1969 for requirements. Formal request 
for assurances was made by letter dated March 15, 
1971 to the Board of County Commissioners, 
County of Wabasha. The resolution of assurances 
was accepted by the District Engineer on January 
12, 1972. 
Local interests involved no longer wish the 
project to provide for a roadway over the top of 
the levees. This obviates the need for a cash contribution 
of 1.5 percent of the actual cost of construction 
for widening the levees to provide for a 
roadway and noted in the project document local 
cooperation requirements. The project plan now 
includes a relocation of the roadway along the land 
side of the north levee at non-Federal cost. 
Operations and results during fiscal year. New 
work: A contract for construction of channel improvements 
was completed at a cost of $19,027. 
Engineering and design and supervision and administration 
cost $3,549. 
Condition at end of fiscal year. Construction of 
the improvement by contract awarded in June 
1972 is complete. 
53. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Projects were inspected to determine that 
project channels are kept clean and unobstructed, 
dikes and revetments are in good condition, and 
structures are in good repair and operable. Deficiencies, 
if any, were minor unless noted. (See 
table 27-I on inspection of completed flood control 
projects.) 
Cost for the year was $32,000. Total cost to June 
30, 1975 was $207,224. 
54. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 27-J. 
55. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization). 
See table 27-K. 
Snagging and clearing of navigable streams and 
tributaries in the interest of flood control (Section 
208 of 1954 Flood Control Act, Public Law 780, 
83rd Congress). 
See table 27-K. 
Emergency bank protection (Section 14 of 1946 
Flood Control Act, Public Law 526, 79th Congress). 
See table 27-K. 
Emergency flood control activities - repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation). 
See table 27-K.
General Investigations 
56. SURVEYS 
Navigation studies continued at a fiscal year cost 
of $80,534. Flood control studies continued at a 
fiscal year cost of $677,131. Special studies in 
coordination with the Soil Conservation Service on 
watershed studies, deauthorization review studies, 
the review of the completed project at Dry Run, 
27-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Iowa, Redwood River at Marshall, Minn. and the 
Kindred Lake, N. Dak., restudy were conducted 
at a fiscal year cost of $115,368. Comprehensive 
basin studies were conducted for the Minneapolis- 
St. Paul area at a fiscal year cost of $127,977. 
Total cost of surveys for the year was $1,001,010. 
57. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $23,121 for International 
Water Studies and $329,814 for Flood Plain Management 
Services, a total of $352,935. See table 
27-L. 
58. RESEARCH AND DEVELOPMENT 
Fiscal year cost was $50,306 for streamflow data 
obtained by Corps gaging beyond cooperative 
stream-gaging program, and for hydraulic laboratory 
work in measurement and analysis of 
sediment load in streams. 
27-22

ST. PAUL, MINN., DISTRICT 
TABLE 27-A 
See 
Section 
In Text Project 
Ashland Harbor, 
Wis. 
2. Bayfield Harbor, 
Wis. 
3. Beaver Bay Harbor, 
Minn. 
4. Big Bay Harbor, 
Mich. 
5. Black River Harbor, 
Mich. 
6. Cornucopia Harbor, 
Wis. 
7. Duluth-Superior 
Harbor, Minn. 
and Wis. 
8. Grand Marais 
Harbor, Minn. 
9. Grand Traverse Bay 
Harbor, Mich. 
10. Kewenaw 
Waterway, Mich. 
11. Knife River Harbor, 
Minn. 
12. Lac La Belle Harbor 
Mich. 
COST AND FINANCIAL STATEMENT 
1 
Total Cost to 
Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
57,894 
57,894 
1,500 
1,019 
7,791 
1,818,200 
625,067 
23,100 
23,100 
219,800 
100,776 
478,314 
412,225 
4,454 
9,510 
17,700 
18,181 
276,000 
263,571 
809,250 
871,891 
58,408 
58,408 
19,300 
96,141 
418,107 
423,279 
13,400 
13,400 
715,236 
114,380 
6,000 
3,360 
27,100 
33,327 
-561,500 
44,211 
6,310 
8,950 
12,000 
14,325 
27-23 
96,476 
109,276 
__ 
12,921 
12,791 
20,000 
20,000 
-_ 
49,250 
48,991 
57,893 
57,893 
33,900 
33,655 
60,950 
76,422 
-73,000 
1,067,414 
60,301 
60,301 
49,900 
91,321 
378,099 
418,992 
17,000 
17,000 
- 1,695,645 
- 1,695,645 
81,319 1,215,651 
81,598 1,214,106 
- 183,855 
- 183,855 
21,235 49,271 
21,365 49,271 
36,000 56,000 
35,520 55,520 
- 340,4331 
340,4331 
62,700 599,010 
62,891 598,894 
383,3502 
383,3502 
38,700 258,506 
38,700 258,506 
- 462,653 
-462,653 
53,091 274,708 
53,336 274,708 
16,109, 258 3 
16,109,2583 
1,216,400 12,586,619 
1,218,981 12,570,8754 
-450,972 
-450,972 
37,200 440,417 
37,200 440.417 
- 197,771 
- 197,771 
32,000 669,483 
32,761 669,482 
- 5,967,141 
-5,967,141 
587,539 6,918,793 
579,498 6,889,4785 
- 271,745 
-271,745 
35,500 147,687 
35,500 147,687 
-269,2706 
-269,2706

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
Maint: 
Approp. 
Cost 
13. Lutsen Harbor, New Work: 
Minn. Approp. 
Cost 
14. Marquette Harbor, New Work: 
Mich. Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
15. Minnesota River New Work: 
Minn. Approp. 
Cost 
Maint: 
Approp. 
Cost 
17. Ontonagon Harbor, New Work: 
Mich. Approp. 
Cost 
Maint: 
Approp. 
Cost 
18. Port Wing Harbor, New Work: 
Wis. Approp. 
Cost 
Maint: 
Approp. 
Cost 
Minor Rehab: 
Approp. 
Cost 
19. Presque Isle Harbor, New Work: 
Mich. Approp. 
Cost 
Maint: 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
20. Reservoirs at Head- New Work: 
waters of Mississip- Approp. 
pi River, Minn. Cost 
Maint: 
Approp. 
Cost 
Maj. Rehab: 
Approp. 
Cost 
21. St. Croix River, New Work: 
Minn. and Wis. Approp. 
Cost 
Maint: 
Approp. 
Cost 
22. Saxon Harbor, Wis. New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
25,181 
25,181 
263,630 
182,818 
97,300 
95,586 
399,200 
288,314 
495 
495 
106,560 
89,798 
351,400 
271,521 
764,700 
597,058 
25,000 
24,886 
37,262 
35,934 
20,077 
20.077 
50,500 
131,312 
14,900 
16,614 
150,400 
186.742 
19,397 
19,397 
35,000 
34,609 
54,201 
52,593 
186,000 
186,000 
195,200 
267.764 
35 7,196 
35 7,196 
4,407 
20,655 
-1,000 
167,963 
889,200 
844,981 
10,900 
11,014 
30,935 
32,263 
44,600 
44,391 
222,750 
43,645 
620,000 
852,897 
61,000 
61,000 
33,587 
33,027 
27-24 
27,000 
26,997 
54,000 
53,140 
44,899 
46,507 
34,400 
34,400 
122,000 
123,779 
114,800 
114,800 
__ 
-_ 
67,000 
67,559 
-_ 
292,000 
449,588 
828,000 
684,943 
37,800 
37,800 
65,400 
61,956 
132,294 
132,291 
89,000 
87,749 
1,282,893 
1,282,893 
1,065,106 
1,065, 106 7 
465,747 
465,747 
2,057,7228 
2,057,7228 
812,786 
812,786 
331,903 9 
331,903 9 
3,181,953 
3,181,75210 
63,393 
63,393 
526,992 
526,992 
145,792 
145,792 
1,190,492 
1,190.492 
468,867 
469,703 
76,500 
76,500 
3,347,82811 
3,310,07911 
8,245,35812 
8,012,70612 
425,000 
425,000 
150,410 
150,410 
591,255 
591,255 
507,507 '3 
507,50713 
241,099 
237,095

ST. PAUL, MINN., DISTRICT 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
23. Two Harbors, Minn. New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
24. Warroad Harbor and New Work: 
River, Minn. Approp. 
Cost 
Maint: 
Approp. 
Cost 
29. Big Stone Lake and New Work: 
Whetstone River, Approp. 
Minn. and S. Dak. Cost 
Maint: 
Approp. 
Cost 
30. Burlington Dam, New work: 
Souris River, Approp. 
N. Dak. Cost 
31. Eau Galle River, New work: 
Wis. Approp. 
Cost 
Maint: 
Approp. 
Cost 
32. Homme Lake and New Work: 
Dam, N. Dak. Approp. 
Cost 
Maint: 
Approp. 
Cost 
34. Lac qui Parle Lakes, New Work: 
Minnesota River, Approp. 
Minn. Cost 
Maint: 
Approp. 
Cost 
35. La Farge Lake and New Work: 
Channel Imp., Approp. 
Wis. Cost 
36. Lake Ashtabula and New Work: 
Baldhill Dam, Approp. 
Sheyenne River, Cost 
N. Dak. 
Maint: 
Approp. 
Cost 
37. Lake Traverse and New Work: 
Bois de Sioux River, Approp. 
S. Dak. and Minn. Cost 
Maint: 
Approp. 
Cost 
38. Mankato and North New Work: 
Mankato, Minn. Approp. 
Cost 
39. Minot, N. Dak. New Work: 
Approp. 
Cost 
40. Prairie du Chein, New Work: 
Wis. Approp. 
Cost 
423,273 
653,557 
300 
2,300 
27,800 
8,139 
1,687,000 
1,528,659 
54,500 
54,500 
775,000 
922,732 
45,300 
48,771 
-500 
716 
80,500 
71,803 
-500 
465 
82,900 
84,645 
1,393,000 
1,385,897 
65,500 
77,502 
405,900 
241,048 
-1,300 
173 
137,900 
79,948 
1,489,600 
1,921,690 
745,500 
703,182 
29,800 
11,661 
562 
20,223 
2,150,000 
2,193,825 
226,000 
222,759 
180,000 
126,601 
56,300 
47,879 
1,129 
31,200. 
38,732 
25,000 
4,964 
216,300 
219,261 
3,200,000 
2,234,894 
20,000 
16,000 
382,200 
353,194 
1,506 
84,100 
152,846 
1,440,000 
1,128,640 
700,000 
473,604 
2,638 
2,000 
-17,875 
4,331 
53,516 
53,436 
1,650,000 
1,755,341 
340,000 
323,146 
6,000 
62,459 
124,100 
84,519 
961 
140,000 
56,756 
:. 2,000 
24,441 
259,000 
119,031 
3,191,000 
4,213,779 
81,000 
75,614 
302,300 
445,571 
2,000 
3,360 
89,000 
87,208 
2,550,000 
2,601,028 
1,569,000 
1,187,341 
14,574 
8,047 
93,333 
93,413 
596,000 
606,192 
37,700 
37,700 
530,000 
548,258 
35,250 
20,072 
160,000 
133,342 
63,000 
141,595 
345,000 
400,544 
4,500,000 
4,636,708 
55,000 
64,383 
318,000 
285,741 
123,000 
82,103 
2,685,200 
3,010,216 
2,230,000 
2,411,117 
33,000 
32,995 
27-25 
3,711,91014 
3,711,27214 
1,324,133 
1,317,606 
86,105 
86,105 
704,309 
704,309 
7,478,000 
7,454,459 
37,700 
37,700 
1,150,500 
1,148,663 
9,039,250 
9,024,072 
429,805 
351,989 
1,396,09715s 
1,396,026's 
801,021 
795,123 
964,873 
964,873 
1,658,363 
1,572,844 
15,272,000 
15,205,001 
3,142,73816 
3,142,73516 
2,558,912 
2,467,486 
1,339,727 
1,339,727 
1,122,819 
1,071,865 
9,980,500 
9,894,837 
5,544,500 
5,073,206 
33,000 
32,995

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
In Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
41. Red Lake River, 
Minn., Including 
Clearwater River, 
Minn. 
42. Red River of the 
North Drainage 
Basin, Minn., 
S. Dak. & N. Dak. 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
43. Red River of the New Work: 
North at Oslo, Approp. 
Minn. Cost 
44. Red River of the New work: 
North at Pembina, Approp. 
N. Dak. Cost 
45. Rochester, Minn. New Work: 
Approp. 
Cost 
46. Roseau River, Minn. New Work: 
Approp. 
, . Cost 
47. Rushford; Minn. * New Work: 
Approp. 
..... CQst 
48. State Roadt& Ebner New Work: 
Coulees, Wis. Approp. 
N .* Cost 
49. Twin Valle? Lake, New Work: 
Wild Rice Ri r, Approp. 
Minn. Cost 
50. Wild Rice River, New Work: 
South Branch and Approp. 
Felton Ditch, Minn. Cost 
51. Winona, Minn. New Work: 
Approp. 
Cost 
52. Zumbro River, Minn. New Work: 
Approp. 
Cost 
24,400 
25,004 
14,665 
48,000 
42,232 
7,700 
12,052 
290,000 
38,029 
25,000 
28,550 
35,100 
35,058 
120,200 
70,043 
95,000 
85,756 
-135,000 
109,586 
100,000 
47,458 
49,700 50,000 
33,087 59,176 
39,700 34,000 
17,272 46,304 
- 10,000 
- 3,498 
45,100 1,120,000 
25,885 609,926 
1. Excludes $56,500 contributed funds. 
2. Excludes $30,000 contributed funds. 
3. Includes $1,547,195 for new work for previous 
projects. 
4. Includes $5,474 for rock in stockpile. 
5. Includes $402,242 expended between 1893 and 
1917 from permanent indefinite appropriations for operation 
and care. Includes $30,260 for rock in stockpile. 
6. Excludes $38,190 contributed funds. 
7. Includes $83,416 for rock in stockpile. 
8. Includes $117,542 for new work for previous project. 
Excludes $359,202 contributed funds. 
9. Includes $284,802 for new work for previous 
projects. 
10. Includes $113,326 for maintenance for previous 
projects. Includes $5,161 for rock in stockpile. 
11. Includes $681,805 for new work for previous 
projects. 
12. Includes $100,857 for maintenance for previous 
projects. 
13. Excludes $50,193 contributed funds. 
14. Includes $48,404 National Industrial Recovery Act 
for new work funds. 
15. Excludes $56,220 contributed funds. 
16. Excludes $208,000 contributed funds. 
17. Excludes $30,020 contributed funds. 
18. Includes cost of the Wahpeton-Breckenridge unit 
$11,239, which is classed as "inactive," and the units on 
which authorization has expired; Maple River, $1,241; 
Moorhead, $27,700; Sheyenne, $37,956. In addition, 
$203,871 special deposit funds and $146,160 in other contributed 
funds have been expended for work done under 
Government contract paid for by local interests. 
19. Excludes $17,316 contributed funds. 
27-26 
3,120,07917 
3,120,079'7 
29,000 
29,002 
63,000 
110,817 
41,000 
18,042 
169,228 
136,760 
-60,000 
40,995 
45,000 
14,791 
54,000 
30,235 
55,000 
57,259 
60,000 
66,299 
86,000 
70,686 
15,000 
565,498 
34,000 
34,200 
100,000 
76,006 
900,000 
931,623 
960,000 
997,291 
44,000 
43,382 
100,000 
81,539 
125,354 
149,316 
100,000 
123,585 
130,000 
132,805 
229,000 
138,876 
230,000 
250,919 
20,000 
22,576 
355,702 
355,702 
6,497,98418 
6,497,98418 
773,634 
737,365 
1,150,200 
1,149,621 
1,398,228 
1,395,091 
44,000 
43,382 
463,000 
444,539 
2,781,333 
2,775,086 
154,000 
153,820 
284,700 
282,327 
362,700 
268,751 
2,473,13119 
2,472,23419 
1,284,100 
1,284,100

ST. PAUL, MINN., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 5, 1886 
Aug. 11, 1888 
Mar. 3, 1899 
June 6, 1900 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 19351 
Mar. 2, 1945 
July 14, 1960 
Aug. 26, 1937 
Sept. 3, 1954 
June 3, 1896 
June 13, 1902 
Mar. 2, 1907 
May 28, 19083 
July 27, 1916 
Mar. 2, 1919 
Jan. 21, 1927 
July 30, 19301 
Aug. 30, 19301 
July 16, 19524 
July 14, 19605 
Oct. 4, 1961 
Mar. 3, 1879 
Aug. 30, 1935 
May 17, 1950 
ASHLAND HARBOR, WIS. (See Section 1 of Text) 
Breakwater 7,900 feet long and dredging to remove a shoal 
Appropriation of $60,000 for 'Continuing improvement on 
enlarged project.' (On completion of Poe lock in 1896, with 
available depth of 20 feet, dredging at Ashland Harbor was 
carried to a similar depth.) 
Detached breakwater extending 4,700 feet out from shore at a 
point 2,600 feet east of main breakwater (prolonged) and 
parallel thereto. 
Project modified by omitting detached breakwater and defining 
depth and extent of channel to be dredged. 
Widening part of present channel for entrance channel and for 
basin in eastern part of harbor. 
Deepening east basin to 25 feet and west channel, as far as 
8th Ave. West, extended, to 21 feet. 
Widening west channel to 750 feet at its westerly end. 
Deepening portions of East Basin and West Channel to 27 and 
21 feet, respectively. 
CORNUCOPIA HARBOR, WIS. (See Section 6 of Text) 
Entrance channel 50 feet wide and 10 feet deep between 
existing piers from bay to a turning basin 200 feet long. 
8 feet deep, with maximum width of 180 feet, with 150 and 
300-foot inner channels each 50 feet wide and 8 feet deep. 
Reconstruction and Federal maintenance of east and west 
entrance piers, a 25-foot extension of west pier and a 
300-foot extension of existing westerly inner channel at a 
depth of 8 feet and a width of 50 feet. 
DULUTH-SUPERIOR HARBOR, MINN., AND WIS. 
(See Section 7 of Text) 
Dredging. 
Rebuilding piers at Superior Entry. 
Enlarge plan for Superior Entry and additional dredging near 
draw span of Burlington Northern railway bridge. 
Dredging additional area for basin inside Duluth entrance 
to 22-foot depth. 
Enlarging Superior Harbor Basin 
Removal of shoal point at southerly end of East Gate Basin 
Howards Bay Channel, 20 feet deep. 
Deepening and widening channels and basins. 
Deepen Superior Front Channel and a portion of East Gate 
Basin to 25 feet. 
Present project dimensions of channels and basin. 
Abandons northerly portion of 21st Avenue West Channel. 
GRAND MARAIS HARBOR, MINN. (See Section 8 of Text) 
Breakwaters and dredging of anchorage area of 26 acres to 
16 feet. 
Sea walls across ledge in southeast corner of harbor, 
enlarging anchorage basin and deepening of entrance. 
Small-boat basin with breakwater. 
H. Ex. Doc. 89, 48th Cong., 2d 
sess. Annual Reports, 1886, 
p. 1674; and 1887, p. 1966. 
H. Doc. 1698, 64th Cong., 2d 
sess. 
S. Doc. 133, 71st Cong., 2d 
sess. 
Rivers and Harbors Committee 
Doc. 46, 82d Cong., 1st sess. 
H. Doc. 337, 77th Cong., 1st 
sess. 
H. Doc. 165, 86th Cong., 1st 
sess. 2 
S. Committee, 75th Cong., 1st 
sess. 
H. Doc. 434, 83d Cong., 2d 
sess. 2 
H. Ex. Doc. 59, 53d Cong., 3d 
sess. and Annual Report, 
1895, p. 2538. 
H. Doc. 82, 59th Cong., 2d 
sess. 
H. Doc. 221, 60th Cong., 1st 
sess. 
H. Doc. 651, 64th Cong., 1st 
sess. 
H. Doc. 1018, 64th Cong., 1st 
sess. 
H. Doc. 245, 69th Cong., 1st 
sess., and Rivers and Harbors 
Committee, Doc. 32, 71st 
Cong., 2d sess. 
H. Doc. 482, 72d Cong., 2d sess. 
H. Doc. 374, 82d Cong., 2d sess. 
H. Doc. 150, 86th Cong., 1st 
sess. 2 
H. Doc. 196, 86th Cong., 1st 
sess. 
2 
H. Ex. Doc. 75, 43d Cong., 2d 
sess. Annual Report, 1875, 
p. 184. 
Rivers and Harbors Committee 
Doc. 22, 72d Cong., 1st sess. 
H. Doc. 187, 81st Cong., 1st 
sess. 2 
27-27 
TABLE 27-B

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 27-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 19, 1890 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 19356 
Mar. 2, 1945 
Sept. 3, 1954 
Mar. 7, 1974 
Mar. 2, 1867 
Aug. 11, 1888 
June 25, 1910 
Aug. 30, 19551 
July 14, 1960 
July 13, 1892 
July 3, 1958 
June 25, 1910 
Aug. 26, 1937 
Oct. 23, 1962 
June 13, 1902 
June 30, 1948 
June 3, 1896 
June 13, 1902 
Aug. 30, 1935 
July 14, 1960 
KEWEENAW WATERWAY, MICH. (See Section 10 of Text) 
Acquisition of waterway; for a 16-foot channel of 70-foot 
bottom width, renew canal revetments, reconstruct and extend 
piers at upper entrance to 30-foot depth of water, and at 
proper time for increase of channel depth to 20 feet with 
bottom width of not less than 120 feet (increase in width 
and depth of channel approved Mar. 15, 1898). 
Anchorage basin just within lower entrance about one-half mile 
long, 800 feet wide, a mooring pier on its westerly side 
2,000 feet in length, and for purchase of necessary land. 
Princess Point Cutoff channel. 
General deepening, widening, and straightening of channels 
and basins to provide 25-foot depth with additional 
overdepth at entrances, extend lower entrance breakwater, 
and necessary alteration or replacement of structures due 
to deepening channels. 
KNIFE RIVER HARBOR, MINN. (See Section 11 of Text) 
Dredging. 
Breakwater and modified channels. 
Construction of measures to correct the design deficiencies which 
results in unsatisfactory entrance and mooring conditions. 
MARQUETTE HARBOR, MICH. (See Section 14 of Text) 
Breakwater, 2,000 feet long. 
Extending the breakwater 1,000 feet. 
Additional 1,500-foot extension to breakwater and removing a 
shoal in northerly part of harbor. 
Deepening harbor basin to 25 feet. 
Deepening harbor to 27 feet. 
MINNESOTA RIVER, MINN. (See Section 15 of Text) 
Open-channel improvement from mouth to Shakopee to obtain 
a channel of 4-foot depth to accommodate vessels with 
3-foot draft. 
Dredging to provide channel of 9-foot depth from mouth to 
mile 14.7. 
ONTONAGON HARBOR, MICH. (See Section 17 of Text) 
Channel 17 feet deep and 150 feet wide through bar and 15 feet 
deep and 100 feet wide between piers, and pier maintenance. 
Modified project widths and provided inner basin. 
Deepening approaches and extending harbor basin. 
PORT WING HARBOR, WIS. (See Section 18 of Text) 
Construction of parallel piers and dredging. 
Dredging inner channels and abandonment of certain 
revetments and channels. 
PRESQUE ISLE HARBOR, MICH. (See Section 19 of Text) 
Breakwater, 1,000 feet long. 
Shore extension, 216 feet long. 
For dredging and rubble mound extension to breakwater 1,600 
feet long. Changed designation of project. 
Deepening harbor from 26 and 28 feet to 28 and 30 feet, 
respectively. 
H. Ex. Doc. 105, 49th Cong., 
2d sess. and Annual Report 
1887, p. 1977. 
H. Doc. 325, 60th Cong., 1st 
sess. 
H. Doc. 835, 63d Cong., 2d sess. 
H. Doc. 55, 73d Cong., 1st 
sess. 2 
H. Doc. 686, 77th Cong., 2d sess. 
and Annual Report for 1949. 
H. Doc. 463, 83d Cong., 2d sess. 2 
H. Ex. Doc. 56, 39th Cong., 2d 
sess., pts. 1 and 2, and Annual 
Report, 1866, pp. 8 and 77. 
Annual Report, 1889, pp. 272 
and 2021. 
H. Doc. 573, 61st Cong., 2d 
sess. 
Rivers and Harbors Committee 
Doc. 20, 72d Cong., 1st sess. 
H. Doc. 154, 86th Cong., 1st 
sess. 2 
Annual Report 1891, p. 2209 
S. Doc. 144, 84th Cong., 2d 
sess. 2 
H. Doc. 602, 61st Cong., 2d 
sess. 
S. Committee print, 74th Cong., 
2d sess. 
H. Doc. 287, 87th Cong., 2d 
sess. 2 
H. Doc. 114, 56th Cong., 1st 
sess. 
H. Doc. 668, 80th Cong., 2d 
sess. 
H. Doc. 318, 54th Cong., 1st 
sess., Annual Report for 1903, 
pp. 474, 1823. 
H. Doc. 473, 72d Cong., 2d 
sess. 
H. Doc. 145, 86th Cong., 1st 
sess. 
27-28

TABLE 27-B (Continued) 
ST. PAUL, MINN., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
Mar. 2, 1907 
June 25, 1910 
July 27, 1916 
June 26, 1934 7 
June 18, 1878 
June 3, 1896 
Jan. 21, 1927 
Aug. 30, 1935 
May 17, 1950 
Aug. 5, 1886 
Aug. 5, 1886 
Aug. 30, 1935 
Nov. 7, 1945 
July 14, 1960 
Mar. 3, 1899 
June 6, 1900 
June 13, 1902"1 
Mar. 3, 1905 
June 25, 1910 
July 25, 1912 
RESERVOIRS AT HEADWATERS OF MISSISSIPPI RIVER, 
MINN. (See Section 20 of Text) 
Reconstruct 4 of the 5 original dams and surveys to determine 
extent of lands overflowed by reservoirs. 
Reconstruct Sandy Lake Dam and construct Gull Lake Reservoir. 
Construct an equalizing canal between Winnibigoshish and Leech 
Lake Reservoirs (no work was done and this part of the 
project abandoned in Act of Mar. 4, 1915.) 
Abandonment of ditches connecting Long Lake, Round Lake, 
and Gull Lake. 
Operation and maintenance provided for with funds from War 
Department appropriations for rivers and harbors. 
ST. CROIX RIVER, MINN. AND WIS. (See Section 21 of Text) 
Dredging, etc., for a 3-foot channel between mouth and 
Taylors Falls. 
Harbor and waterfront at Stillwater. 
A 6-foot channel to Stillwater. 
The 9-foot channel from mouth to Stillwater. 
Small-boat harbor at Hudson. 
TWO HARBORS, MINN. (See Section 23 of Text) 
Breakwater and dredging. 
Construction of two breakwater piers. 
Shore connection to east breakwater and dredging 
maneuvering area. 
Construct new east breakwater and enlargement of 
maneuvering basin. 
Deepen harbor project depths from 26 and 28 feel to 28 and 
30 feet, respectively. 
H. Doc. 363, 61st Cong., 2d 
sess. 
H. Doc. 413, 64th Cong., 1st 
sess. 8 
H. Ex. Doc. 75, pt. 6, 43d 
Cong., 2d Sess; 9 Annual 
Report 1875, p. 372. 
H. Doc. 378, 69th 
Cong., 1st sess. 
H. Doc. 184, 72d Cong., 1st 
sess. 9 
H. Doc. 184, 81st Cong., 1st 
sess.9 
H. Ex. Doc. 94, 48th Cong., 
2d sess. 
Annual Report for 1887, p. 1952. 
Rivers and Harbors Committee 
Doc. 17, 72d Cong., 1st sess. 
H. Doc. 805, 78th Cong., 2d 
sess. 
H. Doc. 146, 86th Cong., 1st 
sess. 
2 
WARROAD HARBOR AND RIVER, MINN. (See Section 24 of Text) 
Dredging bar at mouth of Warroad River. Specified in Act. 
Entrance channel 300 feet wide and 7 feet deep. H. Doc. 92, 56th Cong., 2d 
sess. 10 
Enlarging turning basin. 
Deepening to 8 feet. 
H. Doc. 703, 61st Cong., 2d 
sess. 10 
Included in Public Works Administration program September 6, 1933. 
Contains latest published map. 
Administrative act, section 4. 
Public Law 568, 82d Congress. 
Public Law 388, 87th Congress. 
Included in Emergency Relief Administration program, May 28, 1935. 
Permanent Appropriations Repeal Act. 
For Map, see p. 1978, Annual Report for 1911. 
See H. Doc. 462, 71st Congress, 2d sess., for latest published map. 
Latest published map is opposite p. 1984 in Annual Report for 1911. 
Appropriation. 
27-29 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
I

TABLE 27-C RESERVOIRS AT HEADWATERS OF MISSISSIPPI RIVER 
(See Section 20 of Text) 
Outlet Watershed Area (square miles) Capacity Previous Projects Existing Projects 
at 
Minimum Above Watershed Maximum 
Stages St. Paul (square Original Stage Corn- Corn- Total 
Reservoir (feet)' River (miles) miles) Lake Reservoir (acre-feet) pleted Cost pleted Cost Cost 
Winnibigoshish 6 Mississippi 408 1,442 117 179.4 967,930 1884 $214,000 1900 $ 173,470 $ 387,470 
Leech Lake 0 Leech 410 1,163 173 250.9 743,320 1884 171,805 1902 84,380 256,185 
Pokegama 6 Mississippi 344 660 2 24 35.0 120,750 1884 85,000 1904 126,030 211,030 
Sandy Lake 7 Sandy 267 421 8 16.6 72,500 1895 114,000 1909 117,020 231,020 
Pine River 9 Pine 199 562 18 23.7 177,520 1886 97,000 1907 133,320 230,320 
Gull Lake 5 Gull 168 287 20 20.5 70,820 - - 1913 86,826 86,826 
Surveys and flowage rights -- - 160,939 160,939 
Recreational facilities - - - - 1,746,289 1,746,289 
Total new work - - 681,805 - 2,628,274 3,310,079 
Total operating and care - - 100,857 - 6,944,652 7,045,509 
Permanent indefinite appropriation 
for operating and care, Feb. 1, 1895, 
to end of fiscal year 1936 - - - - 967,197 967,197 
Rehabilitation - - - -425,000 425,000 
Total 2,152,840 - 782,662 - $10,965,123 $11,747,785 
1. Lower operating limits by regulations approved February 4, 1936, as modified December 29, 1944. 
2. Exclusive of area controlled by Winnibigoshish and Leech Lake Dams. 
0 
0
y
x
O
d 
Cm

ST. PAUL, MINN., DISTRICT 
TABLE 27-D RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 25 of Text) 
Project Date Survey Conducted 
Baudette Harbor, Minn. May and June 1975 
Chippewa Harbor, Isle Royale, Mich. March and June 1975 
Eagle Harbor, Mich. May and June 1975 
La Pointe Harbor, Wis. November 1974 and June 1975 
Pine Creek, Angle Inlet, Minn. March and April 1975 
TABLE 27-E OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation And 
Project Report For Construction Maintenance 
Baudette Harbor, Minn.' 1961 36,415 22,769 '2 
Black River, Wis.2 3 1950 67,585 - 
Chippewa Harbor, Isle Royale, Mich. 1959 125,629 1,10213 
Eagle Harbor, Mich.' 1973 205,1644 45,67214 
La Pointe Harbor, Wis. 1,5 130,874 767'3 
Lake Traverse, Minn. and S. Dak. 6'7 1921 92 - 
Mississippi and Leech Rivers, Minn. 1.6 1929 277,615 40,251 
Mississippi River between Brainerd and 
Grand Rapids, Minn.8 1925 47,794 3,891 
Pine Creek, Angle Inlet, Minn. 1'5'9 1964 38,700 2,30313 
Red Lake and Red Lake River, Minn. 1.6 1923 9,070 - 
Red River of the North, Minn. and N. Dak.6'.0 1921 293,344 76,209 
Wisconsin River, Wis. 6 "11 1888 - - 
Zippel Bay Harbor, Minn. 2,8 1928 27,941 11,139 
1. Completed. 
2. Inactive. 
3. Channels adequate for commerce. 
4. Excludes $27,800 contributed funds. 
5. Project authorized by Chief of Engineers under 
small project authority, Section 107, Public Law 86-645. 
6. No commerce reported. 
7. Abandonment recommended in 1915 (H. Doc. 439, 
64th Cong., 1st sess.) and June 24, 1926 (H. Doc. 467, 69th 
Cong., 1st sess.). 
8. Abandonment recommended June 24, 1926 (H. 
Doc. 467, 69th Cong., 1st sess.). 
9. Maintenance dredging performed in FY 1974 in 
conjunction with maintenance contract dredging at Warroad 
Harbor and River, Minn. No breakdown available. 
10. Abandonment recommended in 1915 (H. Doc. 
1666, 63d Cong., 3d sess.). 
11. Originally included in project 'Fox and Wisconsin 
Rivers, Wis.'. Abandonment of improvement of Wisconsin 
River by channel contraction works recommended in 1886 
and 1887 (H. Ex. Doc. 65, 49th Cong., 2d sess.). Expenditures 
included under 'Fox and Wisconsin Rivers, Wis.'. No 
breakdown available. 
12. Includes $1,052 expended in FY 1975 for condition 
surveys. 
13. Expended in FY 1975 for condition surveys. 
14. Includes $523 expended in FY 1975 for condition 
surveys. 
27-31

TABLE 27-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107 Public Law 86-645 
(preauthorization) 
(See Section 27 of Text) 
Study Identification Fiscal Year Costs 
Dakota Harbor, Minn. $27,215 
Lake City Harbor, Minn. 5,000 
Torch Lake Canal, Mich. 6,0001 
Warroad Harbor, Minn. 9,255 
Washburn Harbor, Wis. 5,000 
1 Clearing and snagging under Section 3, River and Harbor Act of March 3, 1945. 
TABLE 27-G BEACH EROSION CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Beach Erosion Control Activities Pursuant to Section 103, 
Public Law 87-874 (Preauthorization) 
(See Section 28 of Text) 
Project Fiscal Year Costs 
Lake Superior at Lake Park, Ashland, Wis. $5,000 
TABLE 27-H RED RIVER OF THE NORTH DRAINAGE BASIN: 
ACTIVE UNITS IN COMPREHENSIVE BASIN PLAN 
(See Section 42 of Text) 
Total 
Cost to Estimated 
Name of Unit JAne 30, 1975 Federal Cost 
Orwell Reservoir (Otter Tail River) Minnesota Reservoir $1,916,753 $1,916:7001 
Wild Rice and Marsh Rivers Minnesota Channel improvement 405,056 405,100 
Rush River North Dakota Channel improvement 287,686 287,700 
Sand Hill River Minnesota Channel improvement 548,778 548,800 
Mustinka River Minnesota Channel improvement 440,788 440,800 
Otter Tail River Minnesota Channel improvement 174,768 174,800 
Red River at Grand Forks North Dakota Levees and floodwall 948,895 948,900 
Red River at East Grand Forks Minnesota Levees, floodwall, 
pumping plants 57,200 6,700,000 
Red River at Fargo North Dakota Channel improvement, 
levees 1,639,924 1,639,9002 
Total cost to date 6,419,848 3 
- 
Total estimated cost 13,062,7004 
'Includes $178,000 for lands and $25,000 for recreation facilities. 
2Includes $67,900 for lands. 
3Costs of $11,239 for the Wahpeton-Breckenridge inactive unit not included. Authorization of the Sheyenne River, Moorhead, and 
Maple River units has expired. Cost of these units also not included total $66,897. 
'The Wahpeton-Breckenridge unit of the project is classed as 'inactive' and is excluded from the estimate. The cost of this unit, 
last revised in 1955, was estimated to be $996,000. The Flood Control Act approved December 31, 1970 (H. Doc. 330-01-2) provided 
for deletion of the Sheyenne River unit, and Authorization of the Maple River and Moorhead units expired at the end of the 5-year 
period within which local interests were required to furnish assurances of local cooperation. Authorization of these units, not 
included, expired on the dates indicated. 
Unit Date Authorization expired Cost to date 
Sheyenne River, N. Dak. 
Maple River, N. Dak. 
Moorhead, Minn. 
December 31, 1970 
October 26, 1961 
October 30, 1961 
27-32 
$37,956 
1,241 
27,700

ST. PAUL, MINN., DISTRICT 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 53 of Text) 
Date Inspected 
Aitkin, Minn . ....... .................... 
Clearwater River, Minn ....................... 
Decorah, Iowa (Dry Run) ...................... 
Elk R iver, M inn . ......... .................. 
Fargo, N. Dak. ......... ........ ............ 
Forest River, N. Dak. ...................... 
Grand Forks, N. Dak. ....................... 
Lost River, Minn. ........... .. ...... ... 
Marsh River, Minn ................. ........ 
M arshall, M inn . ......... . ... ................ 
Mines Creek, Spring Valley, Wis................ 
Minneota, Minn ................. ......... 
Mustinka River, Minn.................... 
Ottertail River, M inn . .......... .............. 
Park River, N . Dak . ......................... 
Red Lake - Clearwater Rivers, Minn........... 
Redwood River, Marshall, Minn. ............... 
Rush River, N. Dak . ............. ............ 
Rush River (Lower Branch), N. Dak. ............ 
Rushford, Minn ........................... 
St. Paul, Minn. ................... .......... 
Sandhill River, M inn. ........... ....... ...... 
Sheyenne River, N. Dak.................. 
South St. Paul, M inn . ......... ............... 
Upper Iowa River, Iowa .................. 
W ild Rice, M inn . ...... .................. 
W inona, M inn . ......... .................... 
November 1974 
November 1974 
September 1974' 
September 1974 
September 1974 
November 19741 
September 1974 
November 1974 
November 1974 
September 1974' 
September 1974 
September 1974 
October 1974 
October 1974 
November 19741 
November 1974 
October 1974 
November 1974 
November 1974 
September 19741 
September 1974 
November 1974' 
November 19741 
September 1974 
September 1974 
November 1974 
September 1974 
' Major Deficiency. 
27-33 
TABLE 27-I 
Project

TABLE 27-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation And 
Project Report For Construction Maintenance 
Ball Park Creek, Bayfield, Wis. 1.2 1956 140,685 - 
Dry Run, Iowa 1 1966 1,790,759 - 
Elk River, Minn. 1,2 1970 259, 700 - 
Guttenberg, Iowa 1 1974 2,361,915 4 - 
Lost River, Minn.1 1967 563,553 - 
Lower Branch Rush River, N. Dak. 1'2 1974 1,000,0006 
Marshall, Minn. 1964 1,802,866 - 
Mellen, Wis.' 1960 7,202 - 
Minneota, Minn. 1.2 1963 161,545 - 
Mississippi River near Aitkin, Minn. 1 1957 1,675,835 - 
Pembina River Lake, N. Dak. 8 1950 50,000 - 
Redwood River below Marshall, Minn. 1'
2 1960 202,400 - 
St. Paul and South St. Paul, Minn.1 1974 8,476,0129 - 
Tongue River Lake, N. Dak. 8 1950 23,695 - 
Upper Iowa River, Iowa 1 1964 888,445 - 
Upper Mississippi River Basin (St. Paul Dist.) 
Black River Lake, Wis. 1o 1950 - - 
Velva, N. Dak. "12 1970 334,628 - 
Warroad River and Bull Dog Creek, Minn. 1974 182,000 - 
1. Completed. 
2. Project authorized by Chief of Engineers under 
small project authority, section 205, 1948 Flood Control 
Act, as amended. 
3. In addition $87,878 was expended from Public Law 
99 funds in the spring of 1969 for emergency protection and 
incorporation into the permanent project. 
4. Final Cost adjustment of -$4,188 made in FY 1975. 
5. Includes $46,034 for the Ruffy Brook unit for 
which authorization expired in April 1966. Excludes 
$246,911 contributed funds. 
6. Excludes $35,000 contributed funds. 
7. Inactive, lack of economic feasibility. Authorization 
of the Odanah, Wis., unit of the overall project on 
the Bad River expired on April 8, 1969. Cost for this unit, 
not included, amounted to $31,941. 
8. Further work deferred pending review of project 
document (inactive). 
9. Includes $4,150 expended in FY 1975 for remedial 
work in pumping plants at South St. Paul. Excludes 
$545,637 contributed funds for new work and $38,000 expended 
by South St. Paul for work in lieu of required cash 
contribution. Excludes an additional $206,629 expended for 
work done at request of local interests. 
10. Has not been selected for construction (inactive). 
11. Preconstruction planning suspended. Local interests 
requested the project be reclassified to inactive due to 
a limitation of their funding capability. The project was 
classified inactive on April 5, 1974. 
27-34

ST. PAUL, MINN., DISTRICT 
TABLE 27-K FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 55 of Text) 
Flood control activities pursuant to section 205, Public Law 858, 
80th Congress, as amended (preauthorization) 
Study Identification Fiscal Year Costs 
Hastings, Minn., Vermillion River $38,4781 
Inver Grove Heights, Minn., Mississippi River 5,000 
Lake Altoona, Wis., Eau Claire River 5,000 
Middle River below Middle River, Minn. 5,000 
Rockford, Minn., Crow River 63,374 
St. Peter, Minn., Minnesota River 58,606 
Snake River below Warren, Minn. 20,981 
1 Preparation of plans and specifications. 
Snagging and clearing navigable streams and 
tributaries in the interest of flood control 
(Sec. 208, 1954 Flood Control Act, P.L. 780, 83rd Congress). 
Project and Location Fiscal Year Costs 
Pembina River, mouth to Walhalla, N. Dak. $4,000 
Poplar River, Minn. 5,500 
Wild Rice River, Cass County, N. Dak. 5,000 
Emergency Bank Protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress). 
Project and Location Fiscal Year Costs 
Zumbro River at Oronoco, Minn. $2,000 
Zumbro River in Wabasha County, Minn. 2,000 
Emergency flood control activities - 
repair, flood fighting, and rescue work 
(Public Law 99, 84th Cong., and antecedent legislation). 
Project Federal Cost 
Advance preparation $ 43,200 
Flood emergency operations 1,480,689 
Emergency Water Supply - Western Lake Superior 260,945 
Total emergency flood control activities 1,784,834 
27-35

TABLE 27-L 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 57 of Text) 
Location Requesting Agency Date Completed Federal Cost 
Aitkin, Minn. City of Aitkin June 1975 $27,100 
Black Earth Creek, Wis. Dane County Regional 
Planning Commission November 1974 28,000 
Crookston, Minn. City of Crookston December 1974 26,273 
Marshall, Minn. City of Marshall December 1974 25,780 
New Richmond, Wis. New Richmond Community Council June 1975 32,229 
Preston, Minn. City Council of Preston June 1975 24,234 
Rice Creek, Minn. Fridley City Council and 
New Brighton Village Council November 1971 27,331 
St. Cloud, Minn. St. Cloud Metropolitan Area 
Planning Commission September 1974 26,940 
Winona, Minn. City of Winona May 1975 27,900 
Wisconsin Dells, Wis. Sauk and Columbia Counties June 1975 44,210 
27-36

ROCK ISLAND, ILL., DISTRICT* 
This district comprises portions of western Illinois, 
southwestern Wisconsin, southern and 
southwestern Minnesota, eastern and central 
Iowa, and northeastern Missouri, embraced in 
drainage basin of Mississippi River and its 
eastern and western tributaries between mile 300 
(above mouth of Ohio River) and*614, and of its 
eastern tributaries only, between Hamburg Bay, 
at mile 261 and 300. This district also includes Illinois 
and Mississippi Canal and drainage basin 
of Bureau Creek, Ill. Section of Mississippi River 
between 300 and 614 is included in report on Mississippi 
River between Missouri River and 
Minneapolis, Minn. 
IMPROVEMENTS 
Navigation Page 
1. Illinois and Mississippi Canal, Ill. 28-1 
2. Mill Creek and South Slough at 
Milan, Ill.......... ........... 28-2 
3. Mississippi River between Missouri 
River and Minneapolis, Minn........ 28-2 
4. Other Authorized Navigation 
Projects ........................ 28-2 
5. Navigation Work under Special 
Authorization ................... 28-2 
Flood Control 
Bettendorf, Iowa ............... 28-2 
Clinton, Iowa .................. 28-2 
Coralville Lake, Iowa .............. 28-2 
Davenport, Iowa .................. 28-3 
East Moline, Ill..................... 28-3 
Fulton, Ill.......................... 28-3 
Marshalltown, Iowa................. 28-4 
Meredosia Levee and Drainage 
District, Ill......................... 28-4 
Flood Control (cont.) Page 
14. Milan, Ill........................... 28-4 
15. Moline, Ill ....................... 28-4 
16. Muscatine, Mad Creek, Iowa ........ 28-4 
17. Ottumwa, Iowa ..................... 28-5 
18. Red Rock Dam and Lake Red 
Rock, Iowa ......................... 28-5 
19. Rockford, Ill........................ 28-5 
20. Rock Island, Ill. ......................... 28-6 
21. Saylorville Lake, Iowa .............. 28-6 
22. Waterloo, Iowa .......... ........... 28-6 
23. Inspection of Completed Flood 
Control Projects ................... 28-6 
24. Other Authorized Flood Control 
Projects ............................ 28-7 
25. Flood Control Work under 
Special Authorization ............ 28-7 
General Investigations 
26. Surveys ............................ 
27. Collection and Study of Basic Data 
28. Research and Development........ 
28-7 
28-7 
28-7 
Navigation 
1. ILLINOIS AND MISSISSIPPI 
CANAL, ILL. 
Location. Extends for 75 miles from Illinois 
River near LaSalle to Mississippi River at Rock 
Island. 
Existing project. See pages 1306-1308 of Annual 
Report for 1962 for details regarding project. 
This obsolete canal is being repaired and 
modified as a condition for its transfer to the State 
of Illinois as part of the State park system. 
Operations and results during fiscal year. Work 
under repair and modification program continued. 
Condition at end offiscal year. Existing project 
completed in 1918. Canal has not been operated 
for navigation since June 1951. Repair and. 
modification program to be accomplished prior to 
disposal of canal initiated in fiscal year 1961, and 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
28-1 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
a number of canal features have been repaired or 
modified. In connection with the repair and 
modification program, fee title to 1,062 acres and 
recreational flowage easements over 309 acres of 
land in Rock River near Rock Falls, formerly under 
navigational flowage easement, have been acquired. 
The State of Illinois accepted title to the 
canal as of August 1, 1970. The River and Harbor 
Act of 1970 authorized the appropriation of 
$6,528,000 for further repair and modification, 
and work is continuing under that authority. 
2. MILL CREEK AND SOUTH 
SLOUGH AT MILAN, ILL. 
Location. Mill Creek and South Slough at 
Milan, Rock Island County, Ill. 
Previous project. See page 1132, Annual Report 
for 1932, and page 1081, Annual Report for 1938. 
Existing project. Provided for diversion of Mill 
Creek into South Slough, flood gates in walls of Illinois 
and Mississippi Canal to carry Mill Creek 
flood waters across canal right-of-way into Rock 
River, levees, and other works for flood protection 
at Milan. Project was modified to restore original 
Mill Creek outlet into Rock River. See table 28-C 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Minor channel maintenance was performed. 
Condition at end offiscal year. Existing project 
was completed in 1932. In 1962-63 $73,366 was 
expended from Illinois and Mississippi 
maintenance funds for restoration of Mill Creek 
outlet into Rock River. 
3. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MINN. 
For report on this improvement see chapter on 
Mississippi River between Missouri River and 
Minneapolis, Minn. 
4. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See table 28-B. 
5. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
During the fiscal year, navigation studies for 
small-boat harbors (preauthorization) at Rock 
Island, Ill., and Hannibal, Mo., were conducted at 
cost of $1,388 and $1,653, respectively, pursuant 
to Section 107 of the River and Harbor Act of 
1960. 
Flood Control 
6. BETTENDORF, IOWA 
Location. On right bank of Mississippi River, 
485.7 miles above mouth of Ohio River, in Scott 
County, Iowa. 
Existing project. Local protection from Mississippi 
River floods to be provided by construction 
of 3 miles of earth levee, railroad raises, 
closure structures, and street raises and ramps. 
Estimated project cost is $5,645,000, including 
$705,000 non-Federal cost for land and 
relocations. See table 28-C for authorizing 
legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests will also 
provide relocations and obtain legal control over 
pondage areas. Local interests will be requested 
to furnish assurances after a firm project plan is 
established. 
Operations and results during fiscal year. 
Preconstruction planning in progress. 
Condition at end of fiscal year. No construction 
performed. Preconstruction planning in 
progress. 
7. CLINTON, IOWA 
Location. On right bank of Mississippi River, 
518.2 miles above mouth of Ohio River, in Clinton 
County, Iowa. 
Existing project. Local protection from Mississippi 
River floods to be provided by construction 
of 8.1 miles of earth levee, 3,080 feet of I-type 
concrete floodwall, 1,250 feet of precast panel 
freeboard wall, interceptor sewer, closure structures, 
ramps, 6 pumping stations, ponding areas, 
and gate wells. Estimated project cost is 
$26,562,000, including $3,462,000 non-Federal 
cost for land and relocations. See table 28-C for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Preconstruction planning in progress. 
Condition at end of fiscal year. Construction is 
scheduled to begin early in next fiscal year. 
8. CORALVILLE LAKE, IOWA 
Location. On Iowa River, several miles upstream 
from Iowa City, in Johnson County, Iowa, 
about 83 miles above mouth of Iowa River. 
Existing project. An earthfill dam rising about 
100 feet above streambed, a 500-foot uncontrolled 
spillway, outlet works to control flow of river to 
28-2

ROCK ISLAND, ILL., DISTRICT 
bankfull stage below dam, and a reservoir 
providing flood control pool of :475,000 acre-feet. 
In addition, a conservation pool is provided which 
varies from 17,000 acre-feet from February 
through June to 53,750 acre-feet from July to 
February of each year. Coralville Lake is used to 
store Iowa River flows temporarily during flood 
periods. Project minimizes flood damages on 
Iowa River from dam to mouth of Cedar River, 
and provides a high degree of protection to lands 
along Iowa River below mouth of Cedar River. 
Project also effects significant reduction of Mississippi 
River flows at Keokuk, Iowa, and reduction 
of flows at Cairo, Ill. Incidental benefits to 
conservation and recreation accrue from project. 
Power is not developed. Project modified to 
provide for highway bridge crossing the lake at 
the Mehaffey site. See table 28-C for authorizing 
legislation. 
Local cooperation. None required, except in 
connection with Mehaffey Bridge, which has 
been fully complied with. 
Operations and results during fiscal year. New 
work: Work in connection with recreational 
facilities continued. Maintenance: Routine 
maintenance activities continued. 
Condition at end of fiscal year. Construction 
began in July 1949 and project has been in operation 
since February 1958. About 24,112 acres of 
land were acquired in fee, and flowage easements 
obtained for 9,573 acres. Construction of 
Mehaffey Bridge began in June 1964 and completed 
in October 1966. 
9. DAVENPORT, IOWA 
Location. Right bank of Mississippi River, 
482.4 miles above mouth of Ohio River, in Scott 
County, Iowa. 
Existing project. Local protection to the city 
from floods on Mississippi River to be provided by 
construction of levees and floodwall. Plan also includes 
interior drainage facilities and pump 
plants, closure structures, and recreational 
facilities. Estimated project cost is $23,345,000, 
including $2,245,000 non-Federal cost for land 
and relocations. See table 28-C for authorizing 
legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests also to 
bear the cost of relocations, bear not less than onehalf 
of the separable first cost for recreational 
development, obtain legal control to prevent encroachment 
on project features, and provide 
pressurized sewers at three locations. Local interests 
will be requested to furnish assurances 
after a firm project plan is established. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end offiscal year. No construction 
performed. Preconstruction planning in 
progress. 
10. EAST MOLINE, ILL. 
Location. On left bank of Mississippi River, 
489.3 miles above mouth of Ohio River, in Rock 
Island County, Illinois. 
Existing project. Local protection from Mississippi 
River floods to be provided by construction 
of 2.4 miles of levee, railroad raises, street 
raises, a closure structure, gravity drainage outlets, 
open ditches, ponding areas, and pumping 
plants. Estimated project cost is $8,775,000, including 
$875,000 non-Federal cost for land and 
relocations. See table 28-C for authorizing 
legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests will also 
provide relocations and obtain legal control over 
pondage areas. Local interests will be requested 
to furnish assurances after a firm project plan is 
established. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. No construction 
performed. Preconstruction planning in 
progress. 
11. FULTON, ILL. 
Location. On left bank of Mississippi River, 
520.1 miles above mouth of Ohio River, in 
Whiteside County, Ill. 
Existing project. Local protection from Mississippi 
River floods to be provided by construction 
of 12 miles of earth levee, railroad raises, 
road ramps, closure structures, gravity drainage 
outlets, ponding areas, storm sewer interceptors, 
and pumping plants. The improvements would 
also protect an adjacent rural area in the Cat Tail 
Drainage District, so as to provide access for the, 
city to high ground. Estimated project cost is 
$10,430,000, including $1,760,000 non-Federal 
cost for land and relocations. See table 28-C for 
authorizing legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests will also 
provide relocations and obtain legal control over 
pondage areas. Local interests will be requested 
to furnish assurances after a firm project plan is 
established. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end offiscal year. No construction 
performed. Preconstruction planning in 
progress. 
28-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
12. MARSHALLTOWN, IOWA 
Location. Right bank of Iowa River in Marshall 
County, Iowa. 
Existing project. Local protection from Iowa 
River floods to be provided by construction of 
levees, floodwalls, and interior drainage 
facilities. Estimated project cost is $10,600,000, 
including $2,190,000 non-Federal cost for rightsof-
way and relocations. See table 28-C for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Operations and results duringfiscal year. Planning 
continued. Construction continued. 
Condition at end offiscal year. Construction initiated 
in May 1972. Planning in progress. Project 
is about 45 percent completed. 
13. MEREDOSIA LEVEE AND 
DRAINAGE DISTRICT, ILL. 
Location. Left bank of Mississippi River, 511 
miles above mouth of Ohio River, in Rock Island 
and Whiteside Counties, Ill. 
Existing project. Local protection to 
agricultural lands from floods on Mississippi 
River to be provided by a combined levee project 
and upgrading of Illinois Highway No. 84, which 
skirts the riverward boundary of the district. 
Total estimated cost of the project is $1,079,400, of 
which the Illinois Division of Highways would 
contribute $180,000, representing the additional 
cost of the standard highway section in place of 
the required levee section. See table 28-C for 
authorizing legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests also to 
assume all cost in excess of $1,000,000 Federal 
limitation. Assurances of local cooperation were 
approved by the Secretary of the Army on May 9, 
1975. 
Operations and results during fiscal year. 
Preconstruction planning in progress. 
Condition at end of fiscal year. No construction 
performed. Preconstruction planning in 
progress. 
earth levee and closure structures, gravity 
drainage outlets, ditches, e nding areas, and a 
pumping plant. Estimated project cost is 
$6,409,000, including $689,000 non-Federal cost 
for land and relocations. See table 28-C for 
authorizing legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests will also 
provide relocations and obtain legal control over 
pondage areas. Local interests will be requested 
to furnish assurances after a firm project plan is 
established. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. No construction 
performed. Preconstruction planning in 
progress. 
15. MOLINE, ILL. 
Location. On left bank of Mississippi River, 
485.7 miles above mouth of Ohio River, in Rock 
Island County, Illinois. 
Existing project. Local protection at Moline 
from Mississippi River floods to be provided by 
construction of 1.5 miles of earth levee, a railroad 
raise, closure structures, aesthetic and 
recreational development, and interior drainage 
facilities consisting of gravity outlets, storm 
sewer interceptors, and pumping plants. Estimated 
project cost is $18,140,000, including $1,- 
740,000 non-Federal cost for land and relocations. 
See table 28-C for authorizing legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests will also 
provide relocations, bear not less than one-half of 
the separable first cost for recreational development, 
and prevent encroachment on ponding 
areas. Local interests will be requested to furnish 
assurances after a firm project plan is established.
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end offiscal year. No construction 
performed. Preconstruction planning in 
progress. 
16. MUSCATINE, MAD CREEK, 
14. MILAN, ILL. IOWA 
Location. On south bank of Rock River, several 
miles from the confluence of that stream with the 
Mississippi River at mile 479.1 above mouth of 
Ohio River, in Rock Island County, Ill. 
Existing project. Local protection against 
direct flooding from Rock River and Mill Creek 
and against backwater flooding from Mississippi 
River to be provided by construction of 5 miles of 
Location. On right bank of Mad Creek, a short 
distance upstream from the confluence of the 
creek with the Mississippi River at mile 455.8 
above the mouth of the Ohio River, in Muscatine 
County, Iowa. 
Previous project. For details of previous project 
on Mad Creek at Muscatine, see page 1338, Annual 
Report 1962. 
28-4

ROCK ISLAND, ILL., DISTRICT 
Existing project. Local protection at Muscatine 
from coincidental floods on Mad Creek and the 
Mississippi River to an industrial area of about 75 
acres. The site is mainly upstream from the 
previous project, but some modification of the 
previous project would be involved. The work 
consists of about one mile of earth levee, a short 
reach of concrete wall, interior drainage 
facilities, and closure structures for streets and a 
railroad. Total estimated project cost is $723,000, 
including non-Federal cost of $73,000 for rightof-
way. See table 28-C for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. No construction 
performed. Preconstruction planning in 
progress. 
17. OTTUMWA, IOWA 
Location. On left bank of Des Moines River at 
the city of Ottumwa, Iowa, 95 miles upstream 
from the confluence of that stream with the Mississippi 
River. 
Existing project. Local protection at Ottumwa 
from basement flooding in the city's main 
business district to be provided by improving the 
discharge efficiency of an interceptor sewer 
through installation of additional gated openings. 
Estimated project cost is $221,000, all Federal. 
See table 28-C for authorizing legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests will also, 
at least annually, notify persons affected by the 
basement flooding that the project does not 
provide complete protection. 
Operations and results during fiscal year. 
Preconstruction planning initiated. 
Condition at end of fiscal year. Construction not 
started. Preconstruction planning in progress. 
18. RED ROCK DAM AND LAKE 
RED ROCK, IOWA 
Location. On Des Moines River, Iowa, chiefly in 
Marion County, but extending into Jasper, 
Warren, and Polk Counties. Dam (Howell) site is 
142.9 miles above mouth of Des Moines River, 
which empties into Mississippi River at mile 
361.4 above mouth of Ohio River. City of Des 
Moines lies northwesterly from site, about 60 
miles upstream. 
Existing project. Provides for a dam consisting 
of a rolled earth-fill embankment and gravitytype 
concrete spillway with crest gates, located 
near center of valley, each end of which is tied into 
embankment by a gravity-type nonoverflow concrete 
section. The dam, at crest elevation of 797 
feet above mean sea level, is about 5,676 feet long 
and maximum height of 110 feet. Gated spillway 
is of concrete founded on bedrock with crest at 
elevation 736. Full flood control level (top of crest 
gates) is at elevation 780. Spillway crest gates are 
41 feet high and 45 feet wide. Outlet works consisting 
of fourteen 5-by-9 foot gated conduits extend 
through spillway section and discharge into 
spillway stilling basin. Nonoverflow concrete sections 
of dam at each end of spillway are gravity 
type, keyed into foundation rock. Drainage area 
above dam site is 12,323 square miles. With pool 
at full flood control elevation, lake area is about 
65,500 acres; lake has a volume of 1,830,000 acrefeet 
of water at that height (1,740,000 for flood 
control and 90,000 for a permanent pool). Impoundment 
of floodwaters by lake results in 
materially reduced flood heights on Des Moines 
River below the dam, and also provides substantial 
supplementary benefits by reducing Mississippi 
River floods. See table 28-C for authorizing 
legislation. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Construction of recreational facilities and 
incidental work continued. Maintenance: Routine 
maintenance activities continued. 
Condition at end of fiscal year. Construction 
began in May 1960. Dam was placed in beneficial 
use for storage of flood water in January 1969. 
Work remaining consists of recreation facilities 
and relocation and remedial items. Land acquired 
for project: 47,607 acres in fee and 28,105 
acres in flowage easements. 
19. ROCKFORD, ILL. 
Location. Kent Creek, a right bank tributary of 
Rock River at the city of Rockford, Winnebago 
County, Ill. 
Existing project. Consists of rolled earth dam 
with outlet works and spillway on North Branch 
Kent Creek in Page Park; 12,000 feet of channel 
cleanout and straightening on North Branch 
Kent Creek; raise of Levings Lake dam on South 
Branch Kent Creek and construction of spillway 
and diversion channel; 10,800 feet of channel 
cleanout and straightening on South Branch 
Kent Creek; and relocations. Estimated cost is 
$9,450,000, including $3,390,000 non-Federal 
cost for lands and relocations. See table 28-C for 
authorizing legislation. 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies. Local interests will also 
bear costs of all relocations and alterations of 
28-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
bridges, buildings, utilities, and prescribe and 
enforce regulations to prevent encroachments on 
improved channels and on ponding areas. 
Negotiations are under way to furnish assurances 
of local cooperation. 
Operations and results during fiscal year. 
Preconstruction planning continued. 
Condition at end of fiscal year. No construction 
performed. Preconstruction planning in 
progress. 
20. ROCK ISLAND, ILL. 
Location. On left bank of Mississippi River, 
482.4 miles above mouth of Ohio River, in Rock 
Island County, Ill. 
Existing project. Local protection from Mississippi 
River floods by construction of levees, 
walls, closure structures, and modification of 
drainage facilities. Estimated project cost is 
$9,065,000, including $1,275,000 non-Federal 
cost for land and relocations. See table 28-C 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations and results duringfiscal year. Planning 
and construction continued. 
Condition at end of fiscal year. Construction initiated 
in June 1971. Project is 82 percent completed. 
Construction of pumping plants remains 
to complete the project. 
21. SAYLORVILLE LAKE, IOWA 
Location. Site is chiefly in Polk County, Iowa, 
but portions will extend into Dallas and Boone 
Counties. Dam is about 213.7 miles above mouth 
of Des Moines River, and about 5 miles upstream 
from north limits of city of Des Moines. 
Existing project. Dam is an earth embankment 
6,750 feet long at crest with a height of 120 feet. 
Outlet works are a single circular concrete conduit, 
22 feet in diameter, located at toe of west 
bluff. Control structure is at upstream end of conduit 
and houses three gates. A stilling basin is 
provided to dissipate energy of discharge from 
outlet conduit. Spillway is in west bluff, weir 430 
feet long. Water flowing over spillway weir will 
discharge into a paved chute and thence into an 
excavated earth channel to the Des Moines River. 
Top of spillway is about 31 feet below top of earth 
embankment section, and flow over weir will be 
uncontrolled when water in reservoir reaches its 
crest. Watershed area above damsite is 5,823 
square miles. With pool at spillway crest elevation, 
lake area will be 16,700 acres and contain 
about 676,000 acre-feet of water at that height 
(602,000 for flood control and 74,000 for a conservation 
pool to maintain minimum flows at 
downstream points). Lake will supplement 
capacity of downstream Lake Red Rock at river 
mile 142.9. The two lakes will provide a large 
degree of flood protection to lower Des Moines 
River Valley. Reaches along Mississippi River 
downstream from mouth of Des Moines River will 
also be benefited. Estimated project cost is 
$91,335,000, including $1,035,000 as a cash 
contribution from the State of Iowa. See table 
28-C for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Construction of Stage III, the remaining 
earthwork for dam, was continued. Construction 
of remedial works to provide flood protection 
from reservoir operation to Polk City, situated in 
Big Creek Valley, was continued. Other relocation 
and remedial work was continued. 
Preconstruction planning for various features 
was continued. 
Condition at end of fiscal year. Construction 
began in June 1965 and is about 72 percent completed. 
Earth embankment portion of dam partially 
completed. Construction of spillway and 
outlet works completed. Construction of remedial 
works in Big Creek Valley in progress. Land acquisition 
in progress, 22,741 acres acquired in 
fee, flowage easements obtained for 795 acres, 
and roadway easements obtained for 18 acres. 
22. WATERLOO, IOWA 
Location. Both banks of Cedar River in Black 
Hawk County, Iowa. 
Existing project. Local protection from Cedar 
River and Black Hawk Creek floods to be provided 
by construction of levees, floodwalls, pumping 
plants, and closure structures on both sides of 
Cedar River and Black Hawk Creek. Estimated 
project cost is $43,345,000, including $9,545,000 
non-Federal costs for rights-of-way and 
relocations. See table 28-C for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Preconstruction planning continued. Construction 
continued. 
Condition at end of fiscal year. Construction 
was started in August 1972 and is in progress. 
Planning in progress. Project is about 24 percent 
completed. 
23. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Federal flood-control regulations (part 208 of 
title 33, Code of Federal Regulations) provide 
28-6

ROCK ISLAND, ILL., DISTRICT 
that the structures and facilities constructed by 
the United States for local flood protection shall 
be continuously maintained in such a manner and 
operated at such times and for such periods as 
may be necessary to obtain the maximum 
benefits. Fiscal year costs were $13,000. (See 
table 28-D for list of completed flood control projects 
inspected.) 
24. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 28-E. 
25. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization). 
See table 28-F. 
Emergency flood control activities - repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
See table 28-G. 
Snagging and clearing of navigable streams and 
tributaries in interest of flood control (sec. 208 of 
1954 Flood Control Act, Public Law 780, 83rd 
Cong.) 
A reconnaissance study was made of a reach of 
channel on Middle River near Bevington, Iowa, in 
which flow is blocked by driftwood and other 
debris, causing overflow at Bevington and on 
agricultural land. The study was terminated 
'because of lack of local support. Cost during the 
fiscal year was $2,628. 
General Investigations 
26. SURVEYS 
Navigation and flood control studies cost 
$538,207. Project deauthorization studies cost 
$6,818. Coordination studies with other agencies 
cost $3,034. Special studies cost $2,764. 
27. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $150,230 for flood plain 
information studies, $38,620 for technical services 
for others, and $50,418 for flood plain 
management services, totaling $239,268. Flood 
plain studies completed during the fiscal year are 
listed in table 28-H. 
28. RESEARCH AND 
DEVELOPMENT 
Collection and study of hydrologic data, including 
storm and sedimentation studies, continued. 
Hydrologic studies during fiscal year cost 
$8,974. 
28-7

TABLE 28-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Illinois and 
Mississippi Canal, 
Ill. 
2. Mill Creek and 
South Slough at 
Milan, Ill. 
6. Bettendorf, Iowa 
7. Clinton, Iowa 
8. Coralville Lake, 
Iowa 
9. Davenport, Iowa 
10. East Moline, Ill. 
11. Fulton, Ill. 
12. Marshalltown, Iowa 
(Regular Funds) 
(Contributed Funds) 
13. Meredosia Levee 
and Drainage 
District, Ill. 
14. Milan, Ill. 
15. Moline, Ill. 
16. Muscatine, 
Mad Creek, 
Iowa 
17. Ottumwa, Iowa 
18. Red Rock Dam 
and Lake Red 
Rock, Iowa 
19. Rockford, Ill. 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
FY 72 
343,400 
501,309 
14,500 
15,828 
109,300 
70,701 
218,600 
204,724 
49,900 
16,838 
365,000 
403,893 
29,800 
19,725 
94,300 
48,592 
119,200 
87,243 
162,200 
215,830 
23,600 
22,582 
79,400 
26,123 
55,000 
936 
2,526,300 
905,898 
417,300 
357,977 
40,000 
67,228 
FY 73 
643,700 
527,782 
14,700 
15,379 
58,000 
102,536 
69,000 
68,065 
60,000 
54,046 
463,500 
381,325 
100,000 
106,975 
50,000 
105,581 
32,000 
61,787 
815,000 
496,698 
84,000 
30,000 
38,960 
-15,000 
27,306 
10,000 
3,286 
28,267 
770,000 
999,904 
426,600 
483,093 
10,000 
7,215 
FY 74 
535,000 
590,202 
8,100 
8,100 
41,000 
46,034 
340,000 
347,175 
39,063 
460,500 
470,146 
130,000 
75,045 
97,000 
60,468 
150,000 
162,882 
910,000 
690,625 
80,000 
72,070 
15,000 
29,992 
118,000 
38,223 
41,500 
22,094 
141,000 
1,292,076 
481,500 
503,129 
137,900 
104,381 
Total Cost to 
FY 75 June 30, 1975 
124,000 
195,881 
19,600 
19,550 
7,000 
9,901 
1,855,000 
1,518,193 
84,500 
17,495 
731,100 
790,883 
240,917 
298,972 
150,000 
198,067 
58,000 
60,496 
1,003,000 
1,727,101 
26,000 
50,000 
140,000 
139,909 
82,000 
168,257 
18,000 
48,756 
10,082 
10,082 
240,000 
976,520 
767,800 
758,857 
75,000 
112,814 
7,605,1431 
7,605,143 
13,074,2382 
13,069,306 
63,7193 
63,7193 
233,153 
233,103 
242,300 
240,947 
2,688,600 
2,341,793 
17,483,788 
17,416,7834 
4,672,605 
4,646,044 
500,717 
500,717 
418,300 
418,300 
497,200 
497,196 
3,871,200 
3,765,140 
84,000 
245,100 
244,100 
259,400 
259,309 
210,000 
209,767 
127,500 
113,053 
10,082 
10,082 
89,034,600 
88,773,444 
2,428,593 
2,407,408 
625,236 
624,584 
28-8

ROCK ISLAND, ILL., DISTRICT 
TABLE 28-A (Continued) . COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
20. Rock Island, Ill. New Work 
Approp. 984,400 2,875,000 1,147,100 135,500 6,432.000 
Cost 1,664,541 2,594,554 1,191,641 331,033 6,388,278 
21. Saylorville Lake, New Work 
Iowa Approp. 5,840,700 12,265,000 13,570,000 9,215,000 65,869,700 
Cost 6,554,128 11,612,266 10,574,630 12,162,675 65,039.666(; 
Maint. 
Approp. - - - 51,800 51,800 
Cost - - - 49,713 49,71: 
22. Waterloo, Iowa New Work 
Approp. 993,100 876,000 1,660,000 4,070,000 8,289,100 
Cost 314,716 558,380 1,686,393 4,724,051 7,970,360 
1. Includes $25,000 Emergency Relief Funds. 3. Includes $85 for previous project. 
2. Includes $4,143,282 for Operating and Care under the 4. Includes cost of Mehaffey Bridge, $1,365,074 (exclutl- 
"Permanent Indefinite Appropriation," and $2,341,169 under ing $100,000 contributed funds). 
the repair and modification program. 5. Excludes $1,035,000 contributed funds. 
TABLE 28-B OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Squaw Chute at Quincy, Ill.' 1967 70,9792 
28,302 
Quincy, Ill., Harbor Access Channel' 1970 35,4773 
1. Completed. Authorized by Chief of Engineers under 
sec. 107, 1960 River and Harbor Act. 
2. Excludes $25,851 contributed funds. 
3. Excludes $35,350 contributed funds. 
28-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 28-C AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
August 13, 1968 
August 13, 1968 
June 28, 1938 
July 14, 1960 
December 31, 1970 
August 13, 1968 
August 13, 1968 
October 27, 1965 
June 30, 1948 
(Section 205) 
MILL CREEK AND SOUTH SLOUGH AT MILAN, ILL. 
(See Section 2 of Text) 
Channel diversion, flood gates, and other work for flood 
protection. 
BETTENDORF, IOWA (See Section 6 of Text) 
Levee, railroad raises, closure structures, and street raises 
and ramps for flood control. 
CLINTON, IOWA (See Section 7 of Text) 
Levee, floodwall, railroad raises, street ramps, closure 
structures, pumping plants, and gravity drainage outlets 
for flood control. 
CORALVILLE LAKE, IOWA (See Section 8 of Text) 
Reservoir for flood control and recreation. 
Highway bridge across Coralville Lake at or near the 
Mehaffey site. 
DAVENPORT, IOWA (See Section 9 of Text) 
Levee, floodwall and pumping plants. 
EAST MOLINE, ILL. (See Section 10 of Text) 
Levee, railroad raises, street raises, closure structure, 
gravity drainage outlets, open ditches, ponding areas, 
and pumping plants for flood control. 
FULTON, ILL. (See Section 11 of Text) 
Levee, railroad raises, road ramps, closure structures, 
gravity drainage outlets, ponding areas, storm sewer 
Interceptors, and pumping plants for flood control. 
MARSHALLTOWN, IOWA (See Section 12 of Text) 
Levees, floodwalls, and interior drainage facilities for 
flood control. 
MEREDOSIA LEVEE AND DRAINAGE DISTRICT, ILL. 
(See Section 13 of Text) 
Levee for flood control. 
Rivers and Harbors Committee 
Doc. 19, 71st Cong., 2nd sess. 
H. Doc. 348, 90th Cong., 2nd sess. 
H. Doc. 348, 90th Cong., 2nd sess. 
Flood Control Committee Doc. 1. 
75th Cong., 1st sess. 
None 
H. Doc. 161, 92nd Cong., 1st sess. 
H. Doc. 348, 90th Cong., 2nd sess. 
H. Doc. 348, 90th Cong., 2nd sess. 
H. Doc. 166, 89th Cong., 1st sess. 
None 
MILAN, ILL. (See Section 14 of Text) 
August 13, 1968 Levee, closure structures, gravity drainage outlets, ditches, 
ponding areas, and a pumping plant for flood control. 
MOLINE, ILL. (See Section 15 of Text) 
October 27, 1965 (Section Levee, railroad raise, closure structures, and interior 
201). Approved by drainage facilities for flood control, and aesthetic and 
Committees on Public recreational development. 
Works of House of 
Representatives and 
Senate June 14, 1972, and 
June 21, 1972, respectively. 
June 30, 1948 
(Section 205) 
MUSCATINE, MAD CREEK, IOWA (See Section 16 of 
Text) 
Levee, wall, interior drainage facilities, and closure 
structures for streets and a railroad for flood control. 
OTTUMWA, IOWA (See Section 17 of Text) 
October 27, 1965 (Section Three gated openings in interceptor sewer. 
201). Approved by 
Committees on Public 
Works of House of 
Representatives and 
Senate 12 October 1972 
H. Doc. 348, 90th Cong., 2nd sess. 
H: Doc. 161, 92nd Cong., 1st sess. 
None 
H. Doc. 197, 92nd Cong., 2nd sess. 
28-10

TABLE 28-C (Continued) 
ROCK ISLAND, ILL., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
RED ROCK DAM AND LAKE RED ROCK, IOWA 
(See Section 18 of Text) 
June 28, 1938 Reservoir for flood control and recreation. Flood Control Committee Doc. 1. 
75th Cong., 1st sess. 
ROCKFORD, ILL. (See Section 19 of Text) 
October 23, 1962 Channel enlargement and realignment, levees, and S. Doc. 142, 87th Cong., 2nd sess. 
appurtenant works for flood control. 
ROCK ISLAND, ILL. (See Section 20 of Text) 
October 23, 1962 Levees, walls, closure structures, and modification of H. Doc. 564, 87th Cong., 2nd sess. 
drainage facilities for flood control. 
SAYLORVILLE LAKE, IOWA (See Section 21 of Text) 
July 3, 1958 Reservoir for flood control and recreation. S. Doc. 9, 85th Cong., 1st sess. 
WATERLOO, IOWA (See Section 22 of Text) 
October 27, 1965 Levees, floodwalls, pumping plants, and closure structures H. Doc. 166, 89th Cong., 1st sess. 
for flood control. 
TABLE 28-D INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 23 of Text) 
Date 
Project inspected 
Hunt Drainage District and Lima Lake Drainage District, Ill. 
Indian Grave Drainage District, Ill. 
Sny Island Levee Drainage District, Ill. 
The Sny Basin, Ill. 
Galena, Galena River, Ill. 
Alpine Dam, Rockford, Ill. 
Kishwaukee River at DeKalb, Ill. 
South Quincy Drainage and Levee District, Ill. 
Drury Drainage District, Ill. 
Subdistrict No. 1 of Drainage Union No. 1 and Bay Island Drainage and 
Levee District No. 1, Ill. 
Henderson County Drainage District No. 1, Ill. 
Henderson County Drainage District No. 2, Ill. 
Henderson County Drainage District No. 3, Ill. 
Penny Slough Drainage and Levee District, Ill. 
Sabula, Mississippi River, Iowa 
Dubuque, Iowa 
Elkport, Turkey River, Iowa 
Des Moines, Iowa 
Van Meter, Iowa 
Black Hawk Creek, Davenport, Iowa 
Muscatine, Iowa (Mad Creek) 
January 1975 
January 1975 
January 1975 
January 1975 
January 1975 
February 1975 
January 1975 
January 1975 
January 1975 
February 
January 
January 
January 
February 
January 
January 
January 
January 
January 
February 
January 
1975 
1975 
1975 
1975 
1975 
1975 
1975 
1975 
1975 
1975 
1975 
1975 
28-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 28-D INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(Continued) (See Section 23 of Text) 
Project 
Date 
inspected 
Muscatine Island Levee District and Muscatine-Louisa County Levee 
District No. 13, Iowa 
Iowa River-Flint Creek Levee District No. 16, Iowa 
Green Bay Levee and Drainage District No. 2, Iowa 
Okabena Creek, Worthington, Minn. 
Des Moines and Mississippi Levee District No. 1, Mo. 
Gregory Drainage District, Mo. 
Canton, Mo. 
Union Township Drainage District, Mo. 
Fabius River Drainage District, Mo. 
Marion County Drainage District, Mo. 
South River Drainage District, Mo. 
Bear Creek at Hannibal, Mo. 
January 1975 
January 1975 
January 1975 
February 1975 
January 1975 
January 1975 
January 1975 
January 1975 
January 1975 
January 1975 
January 1975 
January 1975 
TABLE 28-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Ames Lake, Iowa4 
Bear Creek Dam (City of Hannibal, Mo.)' 
Campbells Island, Mississippi River, 11.2 
Canton, Mo.' 
Carroll County Levee and Drainage 
District No. 1, Ill. 3 
Central City Lake, Iowa 4 
Des Moines and Mississippi 
Levee District No. 1, Mo.' 
Des Moines, Iowa' 
Dubuque, Iowa 
Drury Drainage District, Ill.' 
Elkport, Turkey River, Iowa' 
Evansdale, Iowa7' s 
Fabius River Drainage District, Mo.' 
Fabius River Drainage District, Mo.' 
Freeport, I11.10 
Galena, Galena River, Ill.' 
Green Bay Levee and Drainage 
District No. 2, Iowa' 
1974 
1962 
1969 
1964 
1938 
1970 
1969 
1972 
1974 
1964 
1951 
1972 
1941 
1963 
1973 
1952 
1949 
1,787,31416 
1,670,632 
76,664 
1,496,555 
55,664 
1,492,016 
4,993,2245 
10,567,81117 
1,144,875 
34,2006 
88,019 
60,500 
1,621,841 
607,597 
844,1009 
299,000 
28-12

ROCK ISLAND, ILL., DISTRICT 
TABLE 28-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Green Bay Levee and Drainage 
District No. 2, Iowa' 1967 1,727,711 
Green Island Levee and Drainage 
District No. 1, Iowa3 1938 - - 
Gregory Drainage District, Mo.' 1940 77,100 - 
Gregory Drainage District, Mo.7', � 1964 68,213 - 
Gregory Drainage District, Mo.' 1972 1,538,963 
Hannibal, Mo. 1 1966 110,933 - 
Henderson County Drainage 
District No. 1, Ill.'1 1968 1,453,217 
Henderson County Drainage 
District No. 2, Ill.' 1968 1,043,902 
Henderson County Drainage 
District No. 3, Ill.' 1949 42,700 - 
Henderson River, Ill.12 1964 102,310 - 
Hunt Drainage District and Lima Lake Drainage 
District, Ill. 1972 4,772,498 
Indian Grave Drainage District, Ill.' 1972 3,551,961 - 
Iowa River-Flint Creek Levee District 
No. 16, Iowa' 1972 6,044,693 - 
Jackson, Minn. 7,'0 1973 113,077 - 
Janesville and Indian Ford Dams, Wis.2 1938 - 
Keithsburg Drainage District, Ill.3 1938 - - 
Kishwaukee River at DeKalb, Ill.1,7 1957 123,300 - 
Marion County Drainage District, Mo.' 1967 873,748 - 
Muscatine, Iowa (Mad Creek)' 1962 1,169,042 - 
Muscatine Island Levee District and 
Muscatine-Louisa County Drainage 
District No. 13, Iowa' 1970 3,293,27613 
New Hartford, Iowa7,' � 1966 26,530 - 
Okabena Creek at Worthington, Minn.', 7 1957 72,432 - 
Pecatonica River at Darlington, Wis.4 - - - 
Penny Slough, Rock River, Ill.' 1940 85,800 - 
Rochester Lake, Iowa' 4 . 
Rock River agricultural levees, Ill. -- - 
Rock River, Ill. and Wis., at 
South Beloit, Ill. 1952 
Sabula, Mississippi River, Iowa' 1958 411,915 - 
Sny Basin, Ill.' 1972 14,003,143 - 
Sny Island Levee Drainage 
District, Ill.' 1942 61,400 - 
Sny Island Levee Drainage District, Ill.' 1968 4,956,749 - 
South Quincy Drainage and 
Levee District, Ill.1 1940 61,200 
South Quincy Drainage and 
Levee District, Ill.' 1968 1,231,243 - 
South River Drainage District, Mo.' 1941 55,300 
South River Drainage District, Mo.' 1966 1,106,056 - 
Subdistrict No. 1 of Drainage 
Union No. 1 and Bay Island 
Drainage and Levee District 
No. 1, Ill.1 1967 3,306,695 - 
Union Township Drainage District, Mo.' 1947 109,621 - 
Upper Mississippi River 
Basin (Rock Island District)" 1967 - - 
Van Meter, Iowal 7 1965 113,842 - 
28-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 28-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
1. Completed. 
2. Inactive; project not economically justified. 
3. Inactive; lowlands of district acquired by United States 
in 1947. 
4. Reclassified "inactive". 
5. Excludes $23,323 contributed funds. 
6. Excludes $5,000 contributed funds. 
7. Authorized by Chief of Engineers (sec. 205, 1948 
Flood Control Act). 
8. Section 205 study terminated because of local financing 
problems; project is recommended in a current interim report 
of the Iowa-Cedar River survey. 
9. Excludes $118,000 contributed funds. 
10. Planning discontinued in 1973 because of lack of local 
support. 
Study identification 
Burlington, Iowa 
Chelsea, Iowa 
East Dubuque, Ill. 
Fourmile Creek, Des Moines, Iowa 
Geneseo, Ill. 
Janesville, Wis. 
Marengo, Iowa 
Marion County Drainage District, Mo. 
Monticello, Iowa 
Union Township Drainage District, Mo. 
Webster City, Iowa 
11. Excludes $20,626 contributed funds. 
12. Authority for the Henderson River diversion unit has 
expired; the levee along the north bank of the Henderson River 
has been found to lack economic justification; and the 
Cedar Creek channel improvement has been deferred for 
restudy. 
13. Excludes $220,000 contributed funds. 
14. To be restudied. 
15. Status is as indicated in reports on Coralville, Red 
Rock, Rochester, and Central City Lakes. 
16. Includes $885,000 for disbursement in connection 
with realignment of Interstate Highway 35. 
17. Excludes $145,415 contributedfunds. 
Fiscal year 
costs 
$ 1,404 
39,977 
18,821 
27,282 
68,766 
6,073 
49,660 
75,637 
6,290 
26,506 
97,060 
TABLE 28-G FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Emergency flood control activities - repair, flood fighting, and 
rescue work (Public Law 99, 84th Cong., and antecedent legislation) 
(See Section 25 of Text) 
Project Federal cost 
Advance preparation 
Flood emergency operations 
Rehabilitation: 
Two private levees, Pecatonica River, Ill. 
Five private levees, Edwards River, Ill. 
Nine private levees, Rock River, Ill. 
Donald Bell Levee, Edwards River, Ill. 
Eldon Yager Levee, Rock River, Ill. 
Erie Township Levee, Rock River, Ill. 
$ 58,560 
433,467 
1,960 
10,857 
50,314 
4,776 
46,254 
23,665 
28-14 
TABLE 28-F FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities pursuant to section 205, Public Law 
858, 80th Congress, as amended (preauthorization) 
(See Section 25 of Text)

ROCK ISLAND, ILL., DISTRICT 
TABLE 28-G 
(Continued) 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Emergency flood control activities - repair, flood fighting, and 
rescue work (Public Law 99, 84th Cong., and antecedent legislation) 
(See Section 25 of Text) 
Project 
Four private levees, Henderson County, Ill. 
Sny Island Levee Drainage District, Ill. 
Three private levees, Iowa River, Louisa County, Iowa 
Job Keltner Levee, Iowa River, Iowa 
Lake Odessa, Iowa River, Iowa 
Louisa County Levee District No. 8, Iowa River, Iowa 
Louisa County Levee District No. 14, Iowa River, Iowa 
Brennan and Wheeler Levee, Wyaconda River, Mo. 
Mississippi and Fox River Drainage District No. 2, Mo. 
Nick Reiff Levee, Marion County, Mo. 
Two private levees, South Fabius River, Mo. 
Two private levees, Wyaconda River, Mo. 
Union Township Drainage District, Mo. 
TABLE 28-H FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 27 of Text) 
Requesting Date Federal 
Location agency completed cost 
Mississippi River State of Illinois June 1975 $29,000 
Hancock, Adams, Pike, 
and Calhoun Counties, 
Ill. 
Oconomowoc River, State of Wisconsin June 1975 29,000 
Oconomowoc, Wis. 
Skunk River above State of Iowa June 1975 30,000 
Ames, Iowa 
28-15 
Federal cost 
12,808 
5,622 
99,000 
8,323 
112,911 
195,000 
45,000 
9,453 
124,823 
90,370 
30,922 
258 
17,720

MISSISSIPPI RIVER 
BETWEEN MISSOURI RIVER 
AND MINNEAPOLIS, MINN.* 
Section of river covered in this report is 
divided into three reaches, under supervision 
and direction of district engineers at St. Louis, 
Rock Island, and St. Paul. Section in St. Louis 
District extends 105 miles from Mouth of Missouri 
River to mile 300 above Ohio River; Rock 
Island District extends about 314 miles from 
mile 300 to 614; and St. Paul District extends 
about 244 miles from mile 614 to Soo Line Railroad 
bridge, Minneapolis. 
Location. Mississippi River rises in northern 
part of Minnesota, flows about 2,360 miles 
southerly and empties into Gulf of Mexico. Portion 
included in this report extends about 663 
miles from mouth of Missouri River to Soo Line 
Railroad bridge, Minneapolis. Latest map and 
profile showing this section of river is in House 
Document 669, 76th Congress, 3d session. A 
map showing Lake Pepin is in House Document 
511, 79th Congress, 2d session. A map of section 
Minneapolis to Dubuque is in House Document 
515, 79th Congress, 2d session. A map showing 
location of drainage districts (Bellevue, Iowa, to 
Missouri River) is in Rivers and Harbors Committee 
Document 34, 75th Congress, 1st session. 
Previous projects. See page 1199 of Annual 
Report for 1963. 
Existing project. Provides for a channel of 9- 
foot depth and adequate width between mouth 
of Missouri River (1,179 miles from the gulf) and 
Soo Line Railroad at Minneapolis, by construction 
of a system of locks and dams, supplemented 
by dredging. Project also provides for 
further improvements at St. Paul to provide a 
basin extending downstream from Robert Street 
Bridge for 2.7 miles, and at Minneapolis to provide 
adequate terminal facilities, and for other 
harbor improvements and miscellaneous work. 
Pertinent data for existing and proposed locks 
and dams, harbors, etc., are given in tables 
below. All dams are concrete. Three dams 
(Upper St. Anthony Falls, 1 and 19) are fixed, 
remainder are movable. Estimated cost for new 
work (1974) is $599,198,428, exclusive of 
amounts expended on previous projects. See 
House document 669, 76th Congress, 3d session, 
for a report of Chief of Engineers dated 
February 27, 1940, containing a general plan for 
improvement of Mississippi River between 
Coon Rapids Dam and mouth of Ohio River for 
purposes of navigation, power development, 
flood control, and irrigation needs. (See tables 
28-C, 28-D, 28-E, and 28-G on locks and dams; 
harbor improvements; additional features 
entering into cost of project; and authorizing 
legislation.) 
Local cooperation. Small-boat harbors 
authorized in the River and Harbor Act of 1962 
are subject to conditions that local interests 
make a cash contribution toward cost of construction 
(except in case of Quincy harbor which 
involves maintenance only of an existing harbor); 
furnish lands and rights-of-way for construction 
and future maintenance; hold the 
United States free from damages; provide and 
maintain mooring facilities and utilities; 
reserve accommodations for transient small 
boats; accomplish all necessary relocations or 
alterations; and establish public bodies empowered 
to regulate use, growth, and development 
of harbors. 
The Fort Madison commercial harbor is subject 
to conditions that local interests furnish all 
lands and rights-of-way, including spoil areas 
and retaining works; hold the United States free 
from damages; provide and maintain public terminals 
and transfer facilities; provide and 
maintain depths in berthing areas and in local 
* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
2.9-i

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
access channels; and accomplish utility or other 
relocations or alterations. 
Local cooperation requirements for improvement 
of commercial harbor at Dubuque, Iowa; 
for improvement of Beaver Slough at Clinton, 
Iowa, for navigation; and for general navigation 
facilities at small-boat harbors at Rock 
Island, Ill.; Hannibal, Mo.; Fort Madison, Iowa; 
Davenport (Lindsay Park), Iowa; Muscatine, 
Iowa (including freight terminal approach 
channel); Andalusia, Ill.; Warsaw, Ill.; and 
Moline, Ill. have been complied with. 
Licenses. Federal Power Commission collects 
from non-Federal licensees annually to recompense 
the United States for use of Government 
dams for generation of hydroelectric power. 
Amounts collected are returned to U.S. Treasury. 
(See table at end of chapter for license fees 
collected through fiscal year 1975.) 
Terminal facilities. Considered adequate for 
existing commerce. 
Operations and Results During Fiscal Year: 
St. Paul District, new work: Studies were continued 
under section 107, small navigation project 
authority, for establishment of small-boat 
harbors at Dakota, Minnesota, and Lake City, 
Minnesota, at a cost of $32,215. Recreation facilities 
were constructed at pools 2, 3, and 9 at a 
cost for the fiscal year of $100,707. 
Maintenance: Channel dredging to remove 
shoal areas was performed. Government pipeline 
dredge WILLIAM A. THOMPSON removed 
489,252 cubic yards of material at 13 locations at 
a cost of $979,663. Government Derrickbarge 
No. 767 removed 211,977 cubic yards of material 
at 13 locations for $510,710. Dewatering 
operations and repair work at Lock and Dam 9 
were accomplished at a cost for the year of 
$474,612. Repairs to the stony gate valve at Lock 
and Dam No. 1 cost $34,911, and repairs of 
deteriorated bridge pedestals on the dam at 
Lock and Dam No. 5 cost $49,241. Engineering 
work and miscellaneous surveys, reports, and 
other work were carried on by hired labor for 
$69,634. Total cost of maintenance was 
$2,808,500. 
Operating and Care: Locks and dams were 
operated as required, and necessary repairs 
were made to those appurtenant structures. 
Engineering for the rehabilitation of Lock and 
Dam No. 1 was continued at a cost of $264,915. 
Studies of the Upper Mississippi River by the 
Great River Environmental Action Team 
(GREAT) for resource management were initiated 
at a cost of $318,088, including overhead. 
Other studies, reports, and miscellaneous engineering 
work were accomplished at a cost of 
$593,056. Total cost of operating and care was 
$5,822,245. 
Rock Island District, new work: Planning for 
small-boat harbor at Clinton, Iowa, was performed 
at a cost of $9,983. Minor work in connection 
with recreational facilities was in progress 
at a cost of $1,462. 
Maintenance: Hired labor forces performed 
maintenance activities as follows. Channel 
dredging was performed at 14 locations by U.S. 
cutterhead pipeline dredge Thompson, a total of 
957,000 cubic yards of material having been 
removed at a cost of $467,400. Five small-boat 
harbor and access channel projects were 
dredged by U.S. cutterhead pipeline dredge 
Dubuque at a cost of $115,100. Riprap repairs to 
Hannibal, Mo., small-boat harbor and to Squaw 
Chute channel at Quincy, Ill., were performed at 
a cost of $20,500. Gregory Drainage Ditch, Mo., 
was cleaned out at a cost of $27,800. Work on 
regulating works was performed at a cost of 
$250,900. Repair of submersible and non-submersible 
dikes at Lock and Dam Nos. 12 and 13 
was completed at a cost of $50,000. Repair of the 
spillway at Lock and Dam No. 17 was completed 
at a cost of $51,000. Eroded section of the 
upper approach dike at Lock and Dam No. 17 
was repaired at a cost of $86,000. Governmentowned 
levees damaged during high water were 
repaired at a cost of $129,500. Structural work 
consisted of repairing roller and tainter gates at 
a cost of $14,900; repairing two lock gates at 
Lock and Dam No. 22 at a cost of $46,600; repairing 
one lock gate at Lock and Dam No. 15 at a 
cost of $25,600; redecking the service bridge at 
Lock and Dam No. 22 at a cost of $33,900; sandblasting 
and painting dam gates and bulkheads 
at Lock and Dam No. 13 at a cost of 
$15,300; and the complete winter overhaul of 
Lock and Dam No. 12 at a cost of $305,200. 
Repairs to lock and dam structures damaged by 
towboats were performed at a cost of $63,400. 
Installation of standby generators was completed 
at ten sites at a cost of $65,300. Maintenance 
of public-use areas was performed by 
hired labor forces at a cost of $201,700. Other 
maintenance work was performed at a cost of 
$137,000. Engineering, design, supervision, and 
administration totaled $520,973. 
Operating and care: Operation of the locks 
and dams and routine maintenance and minor 
repairs thereto were performed at a cost of 
$2,819,500. Emergency flood operations were 
performed at a cost of $27,500; real estate management 
services were provided at a cost of 
$67,300; operation and contracted daily maintenance 
of public-use areas were performed at a 
cost of $99,600; and surveys and studies, special 
investigations, structural inspections, forecasting 
and dispatching, stream gaging, and miscellaneous 
studies were performed at a cost of 
$375,600. Channel inspection and patrol of the 
project was performed at a cost of $50,500. 
Supervision and administration and overhead 
29-2

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MINN. 
for operations totaled $755,200. Claims receivable 
totaled $120,800. 
St. Louis District, new work. There were no 
costs for recreation facilities in Pools 24, 25 and 
26. Costs incurred for New Lock and Dam No. 26 
were $24,002 for real estate, $7,088 for Bureau of 
Land Management, $2,024 for relocations, 
$1,755,233 for engineering and design, and 
$162,893 for supervision and administration. 
Maintenance: Costs incurred for the year were 
$654,029 for dredging 1,652,900 cubic yards; 
$935,741 for dike and revetment repairs, $5,649 
for maintenance and repair of dams; $183,377 
for maintenance and repair of locks; $161,786 
for repairs to lock and dam structures damaged 
by towboats; $6,200 for repair of road at Lock 24; 
$10,844 for painting of service bridge and extension 
at Lock 25; $15,136 for maintenance of 
recreation facilities; $29,901 for permanent 
operating equipment, $22,223 for buildings, 
grounds and utilities; $83,301 for engineering 
and design; $1,551 for gage repair; and $242,152 
for supervision and administration. 
Operating and care: The locks and dams were 
operated as required, and necessary repairs 
were made thereto and to appurtenant structures 
at a cost of $2,441,965. 
Costs to St. Louis District were $1,951,240 for 
new work and $4,793,855 for maintenance for a 
total of $6,745,095. 
Condition at End of Fiscal Year: The 9-foot 
channel as a whole is about 89 percent complete. 
For information pertaining to locks, 
dams, and harbors, see tables, "Existing 
Project." 
St. Paul District, Work Completed: Locks and 
dams at St. Anthony Falls and Nos. 1 to 10, 
inclusive, except for relatively minor appurtenant 
work; major improvements of channels 
and harbors at St. Paul and Minneapolis; commercial 
harbors at Lake City, Red Wing, and 
Winona, Minn.; and Prairie du Chien, Wis.; 
small-boat harbors at St. Paul, Hastings, Red 
Wing, Wabasha, and Winona, Minn.; Lansing, 
Iowa; and Bay City, Pepin, and Prairie du 
Chien, Wis.; a remedial drainage ditch at Cochrane, 
Wis.; miscellaneous channel dredging and 
realignment; channel markers; pool clearing; 
and construction of various facilities for recreation 
use. Seepage damages totaling $90,027 were 
paid to 210 claimants. 
Status of Land and Flowage Acquisition: Approximately 
50,293.54 acres of land in fee, 
including 47,305 acres used by the Department 
of the Interior in accordance with a cooperative 
agreement and general plans, and easements of 
15,549.63 acres of land are owned or controlled 
in pools 1 to 10, inclusive, at end of fiscal year. In 
addition, fee title to 12.46 acres and perpetual 
easements on 2.98 acres of land for St. Anthony 
Falls and perpetual easements over 244.39 acres 
of land for harbors have been obtained and 
Department of the Army holds special rights 
over 62,954.74 acres owned by Department of 
the Interior in pools Nos. 3 to 10, inclusive. Land 
acquisition is complete. 
Work Remaining to Complete Portion of Project 
in St. Paul District: Guidewall extension at 
lock No. 3 (the uncompleted guidewall extensions 
at locks Nos. 4, 5, 5A, 7, 8, 9 and 10 were 
reclassified from the "active" to the "inactive" 
category on April 13, 1973); realignment of 
channel at Wilds Bend; construction of smallboat 
harbor at St. Paul (Harriet Island), Minn.; 
and construction of additional recreational 
facilities. 
Condition of channel on 30 June 1974 was 
such that controlling depths of 9 feet at low 
water and minimum widths for long-haul common 
carrier service were available in all pools. 
Except for lock No. 1 which is in poor condition 
due to age and obsolescence, structures are in 
good condition. (See table 28-B for total costs of 
existing project to 30 June 1975.) (St. Paul 
District) 
Rock Island District: Major construction 
items, including all locks and dams, are completed 
and in operation. Other work remaining 
to complete portion of project in Rock Island District 
consists of: Construction of guide wall 
extensions at Nos. 16, 18, and 21; mooring facilities 
at Nos. 11, 12, 14, 15, 16, 17, 18, and 22; upper 
approach improvement at No. 19; upper 
approach dike at No. 20; removal of remainder 
of lateral dam in pool No. 14; rock and/or conglomerate 
excavation in pools Nos. 14,15, 18,19, 
and 21; and construction of seven small-boat 
harbors, commercial harbor at Fort Madison, 
Iowa, and additional recreational facilities. 
Status of land and flowage acquisition: Acquisition 
of land in pools Nos. 11 and 22, inclusive, 
consisting of 93,601 acres in fee and 10,541 acres 
in flowage easement, has been completed. 
The condition of the channel on June 30, 1975, 
was such that controlling depths of 9 feet at low 
water and widths suitable for long-haul common 
carrier service were being maintained in all 
pools. 
St. Louis District work completed. Locks and 
Dams Nos. 24, 25, and 26 (Henry T. Rainey 
Dam), except for guidewall extensions at Locks 
Nos. 24 and 25, have been completed. For information 
pertaining to locks, dams and harbors, 
see table under "Authorizing Legislation." Payments 
for rectification of damages have been 
completed. 
Status of land and flowage acquisitions. Acquisitions 
of lands in Pools Nos. 24, 25, and 26, 
involving 41,451 acres of land in fee and flow- 
29-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
age easements over 6,600 acres, is complete. An 
additional 2,500 acres are to be acquired for the 
New Locks and Dam 26. 1,235 acres have been 
acquired thru FY 75. 
Work remaining to complete. Replace existing 
Locks and Dam No. 26 at Alton, Illinois (the 
existing structure is badly deteriorated and 
inadequate to handle projected increase in river 
traffic). Construction of guidewall extensions at 
Locks Nos. 24 and 25; construction of recreation 
facilities for public use; and construction of 
3,800 linear feet of dikes and 3,100 linear feet of 
revetment upstream of mouth of Missouri River. 
Condition of channel on 30 June 1974 was such 
that controlling depth of nine feet at low water 
and generally suitable widths for long-haul 
common carrier services were maintained in all 
pools and between Locks and Dam No. 26 and 
Missouri River. Construction was scheduled to 
be initiated in the fall of 1974, however, a court 
suit was filed on 6 August 1974. A preliminary 
injunction was issued stopping all design and 
construction on project. 
Total Federal cost of existing project to end of 
Fiscal Year 1975 for the three Districts was 
$459,810,849, of which $222,579,172 was for new 
work, ($147,832,868 regular funds, $51,895,959 
public works funds, and $22,850,345 emergency 
relief funds), $237,190,641 regular funds for 
maintenance, and $41,035 regular funds for 
rehabilitation. 
29-4

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MINN. 
TABLE 29-A COST AND FINANCIAL STATEMENT 
Funding FY 72 FY 73 FY 74 
Total Cost to 
FY 75 June 30,1975 
1. Mississippi River New Work 
between Missouri Approp. 3,239,727 1,750,597 4,371,425 1,110,950 271,300,2711 
River and Cost 2,663,330 1,960,508 4,237,539 2,095,607 272,861,8151 
Minneapolis, Maint. 
Minnesota Approp. 14,000,700 15,905,800 17,231,900 19,895,300 246,906,5372 
(Federal Funds) Cost 12,746,983 14,476,098 18,719,440 20,127,073 245,653,2452 
Rehab. 
Approp. - - - - 41,035 
Cost - - 41,035 - 41,035 
(Contributed New Work 
Funds) Approp. 22,000 - - - 1,246,243 
Cost - 16,585 - - 1,240,828 
1 Includes $49,012,646 for new work on previous projects. 2 Includes $8,472,597 for maintenance of previous projects. 
TABLE 29-B TOTAL COSTS OF EXISTING PROJECT TO JUNE 30, 1975 
Regular Public Work Emergency 
District Cost Funds Funds Relief Funds Total 
St. Paul New Work1 $ 57,369,6802 $24,210,071 $ 9,071,214 $ 90,650,965 
District Maintenance] 95,870,368 - - 95,870,368 
Total 153,240,048 24,210,071 9,071,214 186,521,333 
Rock Island New Work 63,847,0034 17,403,322 11,338,865 92,589,190 
District Maintenance 89,934,60556 - - 89,934,605 
Rehabilitation 41,035 - - 41,035 
Total 153,822,644 17,403,322 11,338,865 182,564,831 
St. Louis New Work 26,616,185 10,282,5667 2,440,266 39,339,017 
Maintenance 51,385,668 - - 51,385,668 
Total 78,001,853 10,282,566 2,440,266 90,724,685 
'Excludes $1,228,541 contributed funds. Includes $7,673 
expended in pool No. 11. 
2Includes $159,359 transferred from Rock Island District 
covering pro rata share of cost of derrick boat Hercules. 
:Includes $762,196 expended between 1930 on operating 
and care of works of improvement under provisions of 
permanent indefinite appropriation for such purposes. 
4$687,709 was transferred to St. Louis District in fiscal 
year 1958. Excludes $201,167 transferred to St. Paul and St. 
Louis Districts covering their pro rata shares of cost of 
derrick boat Hercules. 
5Costs subsequent to fiscal year 1953 included with operating 
and care. 
6Includes $395,442 expended between 1930 and 1936 on 
operating and care of works of improvement under the 
provisions of the permanent indefinite appropriation for 
such purposes. 
7Includes $47,800 transferred from Rock Island District 
covering pro rata cost of derrick boat Hercules and $687,709 
transferred from Rock Island District. 
29-5 
See 
Section 
in Text Project

Lock Dimensions 
Greatest 
Length Percent Estimated Width Availa- Upper Depth on Miles Complete Year Cost of ble for Normal Miter Sill Locks, Opened of Each Lock 
Lock Above Cham- Full Pool Character of Foundation Dams, to and Dam Inand 
Ohio Miles from her Width Lift Eleva- Upper Lower and Work Navi- cluding Work 
Dam River Nearest Town (feet) (feet) (feet) tion' (feet) (feet) Lock Dam in Pool gation in Pool 
St. Anthony 853.9 In city of Minne- 56 
Falls, upper apolis, Minn. 
lock 
St. Anthony 853.3 In city of Minne- 56 
Falls, lower apolis, Minn. 
lock and dam 
Lock and dam 1 847.6 Minneapolis- 56 
St. Paul 56 
Lock and dam 2 815.2 1.3 above 110 
Hastings, Minn. 1108 
Lock and dam 3 796.9 6.1 above 110 
Red Wing, Minn. 
9 Lock and dam 4 752.8 Alma, Wis. 110 
Lock and dam 5 738.1 Minneiska, Minn. 110 
Lock and dam 5A 728.5 3 above Winona, 110 
Minn. 
Lock and dam 6 714.3 Trempealeau, Wis. 110 
Lock and dam 7 702.5 Dresbach, Minn. 110 
Lock and dam 8 679.2 Genoa, Wis. 110 
Lock and dam 9 '647.9 3.3 below 110 
Lynxville, Wis. 
Lock and dam 10 615.1 Guttenberg, Iowa 110 
Lock and dam 11 583.0 3.7 above 110 
Dubuque, Iowa 
Lock and dam 12 556.7 Bellevue, Iowa 110 
Lock and dam 13 522.5 4.3 above Clinton, 110 
Iowa 
Lock and dam 14 493.3 3.7 below 110 
Le Claire, Iowa 
Le Claire lock 493.1 3.9 below 80 
(Canal) Le Claire, Iowa 
Lock and dam 15 482.9 Foot of Arsenal 110 
Island, Rock 110 
Island, Ill. 
400 49.2 799.2 15.7 13.7 
400 26.94 750.0 13.7 10.3 
400 
400 
500 
6008 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
600 
320 
600 
360 
35.94 725.1 13.54 
35.9 - 12.57 
12.2 - 16.0 
12.2 687.2 22.2 
8.0 675.0 17.0 
7.0 667.0 17.0 
9.0 660.0 18.0 
5.5 651.0 18.0 
6.5 645.5 17.0 
8.0 639.0 18.0 
11.0 631.0 22.0 
10.1 
7.6 
15.1 
13:0 
14.0 
13.0 
12.0 
12.5 
12.5 
12.0 
14.0 
9.0 620.0 16.0 13.0 
8.0 611.0 15.0 12.0 
11.0 603.0 18.5 12.5 
9.0 592.0 17.0 13.0 
11.0 583.0 19.0 13.0 
11.0 572.0 20.5 13.5 
11.0 - 17.6 10.9 
16.0 561.0 24.011 11.0 
16.0 - 17.011 11.0 
Some limestone, Limestone 
mainly sandstone. 
No piles. 
Sandstone. No Sandstone 
piles. 
Rock and piles Piles in gravel 
in gravel. 
Piles in sand, Piles in sand, 
silt and clay. silt and clay 
Piles in sand, Piles in sand 
silt and clay. 
Piles in sand Piles in sand 
and gravel, and gravel 
Piles in sand Piles in sand 
and gravel. 
Piles in sand. Piles in sand 
Piles in sand, Piles in sand 
gravel and silt. and clay 
Piles in sand Piles in sand 
and gravel. 
Piles in sand, Piles in sand 
gravel, and and gravel 
broken rock. 
Piles in sand. Piles in sand 
Piles in sand. Piles in sand 
Piles in sand, Piles in sand 
gravel and silt. 
Piles in sand Piles in sand 
and gravel, and gravel 
Piles in sand, Piles in sand 
clay and gravel, and gravel 
Rock. Rock 
Rock. Rock 
Rock. Rock 
1002 - $ 18,203,0003 O 
100 1959 12,382,0005 O 
100 1917 2,358,0006 
100 1930 6,492,0009 
100 1948 
71 1938 7,866,000 
0 
100 1935 4,865,000* 
100 1935 5,081,000* 
Z 
61 1936 7,519,000 
100 1936 4,874,000 
100 1937 5,574,000* 
100 1937 6,061,000* 
100 1938 6,539,000* 
a1 
1u0 
99 
99 
100 
92 
100 
95 
1937 
1938 
1938 
1939 
1922 
1934 
4, U,00UUU 
7,428,000 
5,580,000 
7,502,000 
6,284,000
to 
10,525,000 
LOCKS AND DAMS TABLE 29-C 
r

Lock Dimensions 
Greatest 
Length Percent Estimated 
Width Availa- Upper Depth on Complete Year Cost 
Miles of ble for Normal Miter Sill Locks, Opened of Each Lock 
Lock Above Cham- Full Pool Character of Foundation Dams, to and Dam Inand 
Ohio Miles from ber Width Lift Eleva- Upper Lower and Work Navi- cluding Work 
Dam River Nearest Town (feet) (feet) (feet) tion' (feet) (feet) Lock Dam in Pool gation in Pool 
Lock and dam 16 457.2 1.8 above 110 600 9.0 545.0 17.0 12.0 Piles in sand Piles in sand 98 1937 9,788,000 
Muscatine, Iowa and gravel, and gravel 
Lock and dam 17 437.1 4.2 above 110 600 8.0 536.0 16.0 13.0 Piles in sand Piles in sand 99 1939 5,843,000 
New Boston, Ill. and gravel. 
Lock and dam 18 410.5 6.5 above Burling- 110 600 9.8 528.0 16.5 13.7 Piles in sand. Piles in sand 90 1937 10,308,000 
ton, Iowa 
Lock and dam 19 364.2 Keokuk, Iowa 110 358 38.2 518,2 14.5 9.2 Rock. Rock 100 1913 
110 1,200 15.0 13.0 99 1957 14,813,00012 
Lock and dam 20 343.2 0.9 above 110 600 10.0 480.0 15.0 12.0 Rock. Rock and piles in 97 1936 6,281,000 
Canton, Mo. sand and gravel 
Lock and dam 21 324.9 2.1 below 110 600 10.5 470.0 16.5 12.0 Piles in sand Piles in sand 95 1938 8,065,000 
Quincy, Ill. and gravel, and gravel 
Lock and dam 22 301.2, 1.5 below 110 600 10.2 459.5 18.0 13.8 Rock. Rock 99 1938 5,275,000 
Saverton, Mo. 
Lock and dam 24 273.4 Clarksville, Mo. 110 600 15.0 449.0 19.0 12.0 Rock and piles. Piles in sand 73 1940 8,720,600 
Lock and dam 25 241.4 Cap Au Gris, Mo. 110 600 15.0 434.0 19.0 12.0 Piles in sand Piles in sand 72 1939 11,458,700 
and gravel, and gravel 
Lock and dam 26 202.9 Alton, Ill. 110 600 24.0 419.0 19.0 10.0 Piles to Piles 100 1938 12,824,000 
(Henry T. 110 360 24.0 - 16.0 10.0 bedrock to bedrock 
Rainey Dam) 
New Lock and 200.8 Alton, Ill. 110 1,200 24.0 419.0 23.0 18.0 Piles in bedrock. Piles in bedrock - - 360,000,0001' 
dam 26 
Total, Locks 
and dams $583,259,300 
1Elevation of pools 1 to 22 and at St. Anthony Falls are 
mean sea level 1912 adjustment; pools 24, 26 are mean sea 
level 1929 adjustment. 
2Includes existing dam, owned by Northern States Power 
Co.
3Includes dredging above upper lock. (Federal cost only.) 4Based on pool elevation 723.1 in pool 1 which is crest of 
dam. Pool is normally maintained at elevation 725.1 by 
flashboards. 
5Includes lower approach dredging and dredging between 
upper and lower rock. (Federal cost only.) 61In addition $1,948,000 expended from previous projects 
and $1,349,600 from O & C appropriation for first of twin 
locks. Excludes lock and dam replacement programs. 701d upper guard sill. 
SLandward lock. 9In addition, $1,965,300 expended from previous projects. 
to Existing Le Claire Canal lock is used as auxiliary to lock 
14; previous project cost $540,000. 
11 Depth over upper poiree sill. Depth over upper miter sill is 
27 feet, at lock 15. 
12$640,868 for first lock was reported by Mississippi River 
Power Company, transferred to Government free in lieu of 
improvements destroyed. (Annual Report, 1928, pp. 1118- 
1119.) Present estimate includes $13,132,600 for main lock and 
appurtenant work. 1 3Includes cash contribution of $1 530,000. 
* Excludes uncompleted guidewall extensions reclassified 
from active to inactive on 13 April 1973. 
TABLE 29-C (Cont'd) LOCKS AND DAMS

Project Approximate size (feet) Actual or 
Miles above depth Percent estimated 
Name Ohio River Location Type (feet) Width Length Complete Cost 
Harriet Island Harbor, 
St. Paul, Minn. 
St. Paul Harbor, Minn. 
Hastings Harbor, Minn. 
Red Wing Harbor, Minn. 
Red Wing Harbor, Minn. 
Bay City Harbor, Wis. 
Lake City Harbor, Minn. 
Pepin Harbor, Wis. 
Wabasha Harbor, Minn. 
Alma Harbor, Wis. 
Winona Harbors, Minn. 
Lansing Harbor, Iowa 
Prairie du Chien Harbor, 
Wis. 
Dubuque Harbor, Iowa 
Clinton Harbor, Iowa 
Moline Harbor, Ill. 
Davenport Harbor, Iowa 
(Lindsay Park) 
Rock Island Harbor, 
Ill. 
Davenport Harbor, Iowa 
(Credit Island) 
Andalusia Harbor, Ill. 
Muscatine Harbor, Iowa 
840.2 In city of St. Paul, Minn. 
836.5-839.2 In city of St. Paul, 
839.7 Minn. Channel improvement, 
Small-boat 
harbor and channel 
enlargement. 
813.2 Lower end of city of 
Hastings, Minn. 
791.4 In city of Red Wing, Minn. 
791.1 In city of Red Wing, Minn. 
785.9 Upper end of Bay City, Wis. 
773.0 In city of Lake City, Minn. 
767.1 In city of Pepin, Wis. 
760.0 Upper end of city of 
Wabasha, Minn. 
751.3 Upper end of Alma, Wis. 
726.0 In city of Winona, Minn., 
Latsch Island 
726.2 Crooked Slough 
663.3 Upper end of city of 
Lansing, Iowa 
635.5 Upper end of city of 
Prairie du Chien, Wis. 
635.0 In Marais de St. Friol 
East Channel below 
Hwy bridges. 
579.4 At Dubuque, Iowa 
518.8 Joyce Slough 
488.0 At Moline, Ill. 
484.2 At Davenport, Iowa 
479.8 At Rock Island, Ill. 
478.7 Credit Island Slough 
473.0 
455.5 
455.6 
Andalusia Slough 
At Muscatine, Iowa 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Commercial 
Small-boat 
Small-boat 
Small-boat 
70 925 0 $ 138,0002 
9 400-1,000 2.7(mile) 100 217,100 
300 400 100 230,200 
5 200 
9 300 
5 450 
5 50-100 
5 400 
9 500 
5 50 
5 175-400 
5 300 
5 200 
9 200 
5 400 
5 400 
9 
12
5
5
5 
Entrance channel to 
small-boat harbor. 
Small-boat 
Small-boat 
Small-boat 
Freight terminal 
Approach channel. 
340 
170 
230 
200 
500 100 74,300 
1,200 
800 
5,990 
600 
1,000 
600 
800 
100 
100 
100 
100 
100 
100 
100 
146,8003 
8,700 
39,5004 
93,500 
205,5005 
41,700 
500 100 56,300 
1,000 100 89,800 
6,000 100 
800 100 
84,700 
95,300 
800 100 85,500 
1,000 
frontage 
1,500 
1,800 
660 
1,150 
6 100 1,100 
5 75 1,400 
40 
150 
200 
100 93,100 
100
0 
100 
100 
55,200 
79,400 
110,328 
262,100 
100 31,000 
0 130,000 
435 100 
950 100 
1,890 100 
21,000 
353,000 
C
0
Cd 
y
0
z
z
c
x
Cl 
Cl 
u 
1' 
TABLE 29-D HARBO R IMMPROVEME ENTS

TABLE 29-D (Cont'd) HARBOR IMPROVEMENTS
Project Approximate size (feet) Actual or 
Miles above depth Percent estimated 
Name Ohio River Location Type (feet) Width Length Complete Cost 
Fort Madison Harbor, Iowa 383.7 At Fort Madison, Iowa Small-boat 5 250 900 100 184,200 
Keokuk Harbor, Iowa 363.5 At Keokuk, Iowa Small-boat 5 100-160 1,015 0 394,000 
Warsaw Harbor, Ill. 359.1 At Warsaw, Ill. Small-boat 5 100 600 100 73,000 
Qunicy Harbor, Ill. 327.2 Quincy Bay Small-boat 5 290-300 9,000 0 6 
Hannibal Harbor, Mo. 308.8 At Hannibal, Mo. Small-boat 5 180-260 600 100 129,000 
Total $3,522,228 
Cassville Harbor, Wis., deferred cost estimate $178,000 
(1974); Savannah Harbor, Ill., deferred cost estimate $108,000 
(1974) Bellevue Harbor, Iowa, inactive, cost estimate $122,000 
(1974); New Boston Harbor, Ill., deferred cost estimate $23,000 
(1974) Fort Madison Harbor, Iowa, (Commercial) inactive, 
cost estimate $1 070,000 (1974). 1Grafton Harbor, Ill., deferred, cost estimate $223,000 
(1966). "Harbor opposite Hamburg, Ill." portion is deferred 
and excluded from cost estimate, cost estimated at $116,000 
(1960), including $5,200 for preauthorization study and $2,000 
Coast Guard costs. "Commercial Harbor at Alton, Ill." portion 
is deferred and excluded from cost estimate, cost estimated 
at $306,000 (1960), including $27,000 for preauthorization 
study. "Small Boat Harbor at Alton, Ill." portion is 
considered inactive and excluded from cost estimate, cost estimated 
at $121,000 (1959), including $11,900 for preauthorization 
study and $3,000 Coast Guard costs. 
2In addition, local interests will contribute $138,000. 
3In addition, local interests contributed $3,455. 
4In addition, local interests contributed $9,533. 
5In addition, local interests contributed $32,344. 6Maintenance only, estimated at $5,000 anually. 
1 1 
Ci2 
CI) 
C
yz
ed 
z
0
c~ 
z
d
z
bd 
0
r
Cl) 
v 
M
z
z:

TABLE 29-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
ADDITIONAL FEATURES ENTERING INTO 
COST OF PROJECT 
Facilities for public use, convenience, and safety 
Rectification of damages caused by seepage and backwater 
Regulating works between lock and dam 26 (Henry T. Rainey 
Dam) and Missouri River 
Improvement of Beaver Slough at Clinton, Iowa, for 
navigation 
Miscellaneous 
Total additional features 
Total existing project 
'Excludes $205,000 (1955) for remedial works in Sny Island 
Levee Drainage District, Illinois, to be restudied after completion 
of Sny Basin flood control project. 
2Includes $686,500 for repairs to Stone Arch bridge, 
Minneapolis, Minn. (FY 1969) 3Excludes $227,000 (1965) for inactive remedial measures at 
Sandy Slough, Mo. 
TABLE 29-F LICENSE FEES COLLECTED 
THROUGH FISCAL YEAR 1974 
Annual Collections to 
Dam Licensee Charge June 30, 1975 
St. Anthony Falls Northern States $ 3,300 $ 43,297 
Lower Lock and Dam Power Co. (No. 2056) 
Lock and Dam No. 1 Ford Motor Co. 95,440 4,772,000 
(No. 362) 
Total project $4,815,297 
29-10 
$ 2,754,100 
5,759,7001 
2,396,600 
193,600 
1,312,9002 
12,416,900 
$599,198,428 
__

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MINN. 
TABLE 29-G AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 22, 1922 
July 3, 1930 as 
amended by P.R. No. 
10, Feb. 24, 1932 
June 26, 1934 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 30, 1935 
Aug. 26, 1937 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
None 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
Sept. 3, 1954 
Sept. 3, 1954 
July 3, 1958 
July 3, 1958 
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER 
AND MINNEAPOLIS, MINN. 
Dredging channels to landing places. 
Project adopted from Illinois River to Minneapolis; 
Chief of Engineers granted discretionary authority 
to make such modification in plan as may be deemed 
advisable. 
Operation of snag boats and operation and care of locks 
and dams to be provided for with funds from Department 
of the Army appropriations for rivers and harbors. 
Missouri River established as lower limit of project. 
Extension of 9-foot channel above St. Anthony Falls, 
Minn., including adequate terminal facilities for 
Minneapolis, Minn. 
St. Paul Harbor. 
Determine damages to drainage and levee districts 
caused by seepage and backwater, and cost of making 
rectification thereof. 
Public park and recreational facilities. 
Red Wing, Minn., harbor. 
Remedial works to correct damages caused by seepage 
and backwater at Cochrane, Wis. 
Such changes or additions to payments, remedial works, 
or land acquisitions authorized by River and Harbor 
Act of Aug. 26, 1937 (River and Harbor Committee 
Doc. 34, 75th Cong. 1st sess.), as Chief of 
Engineers deems advisable. 
St. Paul, Minn., channel enlargements small boat 
harbor, and roadway. 
Vertical bridge clearance at Minneapolis to 26 feet 
above estimated stage for discharge of 40,000 c.f.s. 
Winona, Minn., basin. 
Future modification of lock and dam No. 2 for power 
development 
Provides for cash contribution by local interests in lieu 
of alteration of privately owned bridges and utilities 
for St. Anthony Falls project. 
Lake City, Minn., harbor. 
Wabasha, Minn., harbor. 
Payment of damages caused by backwater and seepage, 
pools 3 to 11. 
Hastings, Minn., harbor. 
Lansing, Iowa, harbor. 
Fort Madison, Iowa, harbors. 
Payment of damages caused by pool No. 14 at 
Clinton, Iowa. 
Davenport, Iowa, harbor. 
Muscatine, Iowa, harbor. 
Alma, Wis., harbor. 
Hannibal, Mo., harbor. 
Prairie du Chien, Wis., harbors. 
Opposite Hamburg, Ill., harbor. 1 
Permits such change in location of Winona, Minn., small 
boat basin authorized by River and Harbor Act of 
Mar. 2, 1945 (H. Doc. 263, 77th Cong., 1st sess.), as 
Chief of Engineers deems advisable. 
Construction of Crooked Slough Harbor at Winona, Minn., 
in lieu of previously authorized commercial harbor. 
Payment of damages caused by pool No. 24 at 
Louisiana, Mo. 
Permits modification of vertical bridge clearances and 
authorizes completion of St. Anthony Falls project. 
Small boat and commercial harbors at Alton, Ill.2 
None 
H. Doc. 290, 71st Cong., 2d sess. 
None 
H. Doc. 137, 72nd Cong., 1st sess. 
H. Doc. 137, 72nd Cong., 1st sess. 
Rivers and Harbors Committee Doc. 
44, 74th Cong., 1st sess. 
Rivers and Harbors Committee Doc. 
34, 75th Cong., 1st sess. 
None 
H. Doc. 103, 76th Cong., 1st sess. 
H. Doc 137, 76th Cong., 1st sess. 
None 
H. Doc. 547, 76th Cong., 3d sess. 
S. Doc. 54, 77th Cong., 1st sess. 
H. Doc. 263, 77th Cong., 1st sess. 
H. Doc. 432, 77th Cong., 1st sess. 
H. Doc. 449, 78th Cong., 2d sess. 
H. Doc. 511, 79th Cong., 2d sess. 
H. Doc. 514, 79th Cong., 2d sess. 
H. Doc. 515, 79th Cong., 2d sess. 
H. Doc. 559, 79th Cong., 2d sess. 
S. Doc. 192, 79th Cong., 2d sess. 
H. Doc. 661, 80th Cong., 2d sess. 
S. Doc. 197, 80th Cong., 2d sess. 
H. Doc. 642, 80th Cong., 2d sess. 
H. Doc. 733, 80th Cong., 2d sess. 
H. Doc. 66, 81st Cong., 1st sess. 
H. Doc. 67, 81st Cong., 1st sess. 
H. Doc. 71, 81st Cong., 1st sess. 
H. Doc. 254, 81st Cong., 1st sess. 
None 
H. Doc. 347, 83rd Cong., 2d sess. 
H. Doc. 251, 82nd Cong., 1st sess. 
H. Doc. 33, 85th Cong., 1st sess. 
H. Doc. 136, 84th Cong., 1st sess. 
29-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Table 29-G (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 Payment of lump sum amounts for damages to drainage and H. Doc. 135, 84th Cong., 1st sess. 
levee districts caused by operation of navigation 
pools. 
July 3, 1958 Improvement and maintenance of Beaver Slough at H. Doc. 345, 84th Cong., 2d sess. 
Clinton, Iowa. 
Mar. 3, 1909 Reconstruction of structures as may be necessary to None 
provide adequate facilities for existing navigation. 
July 14, 1960 Construction of Industrial Harbor at Red Wing, Minn. H. Doc. 32, 86th Cong., 1st sess. 
Oct. 23, 1962 Construction of small-boat harbors at Savanna 1 Moline, H. Doc. 513, 87th Cong., 2d sess. 
Andalusia, New Boston 1 Warsaw, Quincy, and Grafton, 
Ill.; Bellevue,' Clinton, 5 avenport, and Keokuk, Iowa; 
St. Paul (Harriet Island), Minn.; and Bay City, Pepin, 
and Cassville,' Wis. 
Oct. 23, 1962 Payment of damages caused by pool 24 at Clarksville, Mo. H. Doc. 552, 87th Cong., 2d sess. 
Oct. 23, 1962 Remedial works at Sandy Slough, Mo. H. Doc. 419, 87th Cong., 2d sess. 
Nov. 7, 1966 Repair of Stone Arch bridge at Minneapolis, Minn. None 
Nov. 7, 1966 Commercial Harbor facilities at fort Madison, Iowa.2 H. Doc. 507, 89th Cong., 2d sess. 
'Deferred. 
2Inactive. 
29-12

CHICAGO, ILLINOIS, DISTRICT* 
This district comprises eastern Wisconsin, 
south central portion of Upper Peninsula of 
Michigan, northeastern and central Illinois, 
and portions of northwestern Indiana and 
southwestern Michigan. Area in Illinois, 
southeastern Wisconsin and northwestern Indiana 
is included in drainage basin of Illinois 
River, above south boundary of Federal property 
at New La Grange lock and dam, exclusive of 
basin of Bureau Creek, Illinois. It also includes 
western shore and southern end of Lake 
Michigan and its tributary drainage basins 
from Peninsula Point, Mich., to drainage basin 
of St. Joseph River, Mich., and waterways 
connecting Illinois River with Chicago and 
Calumet Rivers. 
IMPROVEMENTS 
Navigation Page 
1. Algoma Harbor, Wis ............. 30-2 
2. Big Suamico River, Wis. .......... 30-2 
3. Burns Waterway Harbor, Ind. ..... 30-2 
4. Calumet Harbor and River, Ill. 
and Indiana ...................... 30-3 
5. Chicago Harbor, Ill ............... 30-4 
6. Chicago River, Ill. ................ 30-4 
7. Fox River, Wis. .................. 30-5 
8. Green Bay Harbor, Wis. ........... 30-6 
9. Illinois Waterway, Ill. and Ind. .... 30-6 
10. Indiana Harbor, Ind .............. .30-8 
11. Kenosha Harbor, Wis. ............. 30-9 
12. Kewaunee Harbor, Wis. ........... 30-10 
13. Manitowoc Harbor, Wis. ......... : 30-10 
14. Menominee Harbor & River, 
Mich. and Wis.................... 30-11 
15. Michigan City Harbor, Ind. ....... 30-12 
16. Milwaukee Harbor, Wis............ 30-12 
17. New Buffalo Harbor, Michigan .... 30-13 
18. Northport Harbor, Wis............. 30-13 
19. Oconto Harbor, Wis. ............. 30-14 
20. Port Washington Harbor, Wis ...... 30-14 
21. Racine Harbor, Wis. ............. 30-15 
22. Sheboygan Harbor, Wis. ............ 30-15 
23. Sturgeon Bay & Lake Michigan 
Ship Canal, Wis. ................. 30-16 
24. Two Rivers Harbor, Wis. .......... 30-16 
25. Waukegan Harbor, Ill. ........... 30-17 
26. Reconnaissance and condition 
surveys ......................... 30-17 
27. Other authorized navigation 
projects ......................... 30-17 
Navigation 
28. Navigation work under special 
authorization ...................... 
Alteration of Bridges 
29. Other authorized Bridge 
Alteration ....................... 
Beach Erosion Control 
30. Lake Bluff, Ill ........... ....... 
31. Lake Forest, Ill .................. 
32. Authorized beach erosion 
control projects .................... 
Page 
30-17 
30-18 
30-18 
30-18 
30-18 
Flood Control 
33. Chicago River, Ill. North Branch... 30-18 
34. Farm Creek, Ill. ................. 30-18 
35. Little Calumet River, Ill............ 30-19 
36. Mouth of Sangamon River, Ill ...... 30-19 
37. William L. Springer Lake .......... 30-20 
38. Inspection of completed flood 
control projects ................... 30-21 
39. Other authorized flood control 
projects ......................... 30-21 
40. Flood control work under 
special authorization .............. 30-21 
General Investigations 
41. Surveys ........................... 
42. Collection and study of basic data . 
43. Research and development ........ 
30-21 
30-21 
30-21 
* All cost and financial statements for projects are listed at end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
30-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. ALGOMA HARBOR, WIS. 
Location. On west shore of Lake Michigan, 
about 68 miles from Green Bay via Sturgeon 
Bay Canal and about 115 miles northerly from 
Milwaukee (See U.S. Lake Survey Chart No. 
703). 
Previous projects. For details see page 1199 of 
Annual Report for 1958. 
Existing project. Provides for (a) a north pier 
1102 feet long; (b) a south breakwater 1530 feet 
long; (c) an entrance channel 14 feet deep and 
200 feet wide from that depth in Lake Michigan 
and extending 800 feet landward; (d) a channel 
14 feet deep in the Ahnapee River 80 to 175 feet 
wide for 1200 feet up to the Second Street Bridge; 
(e) an outer basin 14 feet deep, 600 feet long and 
100 to 500 feet wide. For a more detailed description 
see page 1200 of Annual Report for 1958. 
Local cooperation. None required. 
Terminal facilities. Consists of several fishing 
wharves. This harbor has one of the largest 
charter fishing fleets on the Great Lakes. 
Operations and results during fiscal year. 
Maintenance: Inspections, miscellaneous 
reports and engineering and design were performed 
by hired labor at a cost of $4330. 
Repairs to the south breakwater and north 
pier were made by hired labor in October and 
November 1974 at a cost of $45,858. Preparation 
of an Environmental Impact Statement was 
made at a cost of $2812. 
Condition at end of fiscal year. Existing project 
was completed in 1909. Ahnapee River is 
navigable for about 2 miles from its mouth for 
vessels drawing not more than 4 feet. Total cost 
of existing project to end of fiscal year was 
$480,828, of which $99,236 was for new work and 
$381,592 for maintenance. 
2. BIG SUAMICO RIVER, WIS. 
Location. A small stream which flows easterly 
into Green Bay, an arm of Lake Michigan. 
Mouth of the river is about 8 miles north of 
Green Bay Harbor, and about 44 miles 
southwesterly from Menominee Harbor, Mich. 
and Wis. (See Lake Survey Chart 725.) 
Existing project. An entrance channel 8 feet 
deep which extends from that depth in Green 
Bay to 1,800 feet above the river mouth, with 
widths of 100 feet in bay and 60 feet in river, 
total length of channel is about 3,700 feet. 
Project was authorized by 1937 River and 
Harbor Act (H. Doc. 498, 74th Cong., 2d sess.). 
Latest published map is in project document. 
New work for completed project cost $20,243. 
Local cooperation. None required. 
Terminal facilities. Small private wharves 
along lower 1.5 miles of river, used by local 
fishing interests. Ample space is available for 
additional fishing wharves when required. 
Facilities considered adequate for existing commerce. 
Operations and results during fiscal year. 
Site selection studies for the diked disposal program 
were continued by hired labor at a cost of 
$4,170. 
Condition at end of fiscal year. Existing 
project was completed in 1938. Dredging 
channel was started in September 1938 and 
completed in November 1938. 
3. BURNS WATERWAY HARBOR, IND. 
Location. On Indiana shore of Lake Michigan 
in Porter County, 18 miles east of Illinois- 
Indiana State line, 14 miles east of Indiana 
Harbor, 9 miles east of Gary Harbor, 14 miles 
west of Michigan City Harbor, Ind., and 19 
miles southeast of Calumet Harbor, Ill. (See 
Lake Survey Chart 75.) 
Existing project. Provides for (a) a north 
breakwater 4,630 feet long; (b) a west 
breakwater 1,200 feet long; (c) an approach 
channel 30 feet deep and 400 feet wide, extending 
from deep water in Lake Michigan to north 
end of east bulkhead; (d) an outer harbor 28 feet 
deep; (e) an east harbor arm 27 feet deep and 620 
feet wide; and (f) a west harbor arm 27 feet deep 
and 620 feet wide. Project was authorized by 
1965 River and Harbor Act (H. Doc. 160, 88th 
Cong., 1st sess.) Authorizing act also provides 
the Secretary of the Army may reimburse State 
of Indiana for expenditure of funds used to 
construct such portions of project as approved 
by Chief of Engineers and constructed under 
supervision of the Chief of Engineers. 
Estimated costs (1974) are $13,616,000 
Federal (Corps of Engineers) and $76,400,000 
non-federal, a total cost of $90,016,000. 
Local Cooperation. Fully complied with. 
Terminal facilities. Under construction by the 
Port Commission of the State of Indiana. There 
are two steel company docks handling iron ore, 
limestone and finished steel products. 
Operations and results during fiscal year. 
New work: Review of State of Indiana request 
for reimbursement continued at a cost of $6,068. 
Contract accrual of $412,552 was made. Total 
amount due the State has not been resolved. 
Maintenance: Project condition surveys, 
inspections, miscellaneous reports, and engi- 
30-2

CHICAGO, ILL., DISTRICT 
neering and design were made by hired labor at 
a cost of $54,985. Riprap stone was purchased 
for repair of the north breakwater at a cost of 
$126,637. Preparation of an Environmental 
Impact Statement was made at a cost of $3378. 
Condition at end of fiscal year. Construction 
of North Breakwater and Outer West Bulkhead 
was completed in September 1968. Dredging 
was completed in August 1970. Full reimbursement 
has not been made to the State of Indiana. 
4. CALUMET HARBOR AND RIVER, 
ILL. AND IND. 
Location. Northeastern Illinois (Cook County), 
near southern end of Lake Michigan, 12.5 
miles south of Chicago Harbor, and known on 
Great Lakes as South Chicago Harbor, is in 
southerly part of and within corporate limits of 
city of Chicago, except for a part of breakwaters 
and of anchorages behind same, which are in 
Indiana. Calumet River is within Chicago city 
limits. (See Lake Survey Chart 755.) For 
description, see page 1471 of Annual Report for 
1932. 
Previous projects. For details see page 1400 of 
Annual Report for 1962. 
Existing project. (See table 30-C.) 
For a more detailed description see page 1246 
of Annual Report for 1963. 
Estimated cost for new work (1975) is 
$32,845,000 Federal and $20,026,000 non-Federal, 
exclusive of amounts expended on previous 
project. Uncompleted portion of 1935 River and 
Harbor Act costing $1,110,000 (1963), uncompleted 
portion of 1960 River and Harbor Act 
costing $2,700,000 (1972) and breakwater 
closure costing $1,270,000 (1965) are considered 
inactive and are excluded from the present cost 
estimate. (See table 30-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
completed modifications and acts of 1960 and 
1962. For act of August 30, 1935, requirements 
for dredging in front of U.S. Steel Corp. remains. 
Terminal facilities. Calumet River and outer 
harbor: 33 docks handling foreign oversea, lake 
vessels, and river barge cargoes. Most important 
cargoes handled are iron ore, grain, 
petroleum products, coal, limestone, sand, 
gravel, iron and steel products, salt, and general 
overseas cargo. There are two boatyards, one for 
repairs to large lake vessels (this yard has two 
large drydocks), and the other boatyard has one 
floating drydock for repairing and building 
commercial river craft. Government owns two 
docks which are used by the Corps only. There 
are no other publicly owned docks on Calumet 
River, except one owned by the city of Chicago. 
Lake Calumet: Chicago Regional Port District 
owns and leases to others three transit sheds 
and two grain elevators. There are also three 
private docks handling chemicals, iron and 
steel products, and miscellaneous cargo. 
Operations and results during fiscal year. 
New work: 1962 modification: Contract for 
widening and deepening at Chicago and 
Western Indiana Railroad bridge was completed 
2 July 1973. Contract costs were $57,558. 
Engineering and supervision were accomplished 
at a cost of $551. 
Maintenance: A contract for repair of a portion 
of the north pier was completed on 11 September 
1974. Contract costs were $102,424. 
Supervision and inspection costs were $7,388. 
Condition surveys, inspections, miscellaneous 
reports and engineering and design were made 
by hired labor at a cost of $52,521. Dredging was 
performed in the Calumet River from 27 May 
1975 to 30 June 1975 by U.S. Hopper Dredge 
Hoffman with 76,580 cubic yards of material 
being removed at a cost of $148,778 plus $66,649 
contributed by Republic Steel Corp., International 
Harvester Co., and Interlake Steel Corp. 
for removal of flue dust deposits. Repairs to the 
breakwater were made by hired labor in June 
1975 at a cost of $126,271. Preparation of an 
Environmental Impact Statement was continued 
at a cost of $5,574. Under the diked disposal 
program, site selection studies and engineering 
and design were continued at a cost of 
$7,034. 
For a resume of litigation to fix the responsibility 
for illegal deposition in navigable 
waters of a portion of Calumet River (United 
States of America, Plaintiff v. Republic Steel 
Corporation, International Harvester Company 
and Interlake Iron Corporation, defendants) 
and settlement agreement see Annual Report 
for 1962 and 1964. Each defendant was issued a 
permit setting forth conditions pertaining to 
future discharges and deposits. Pursuant 
thereto the three companies paid $25,000 for 
each of the calendar years 1964 through 1972, 
and $16,667 for calendar year 1973. 
Condition at end of fiscal year. Existing 
project is about 69 percent complete. Work 
remaining to complete project consists of 
removing hard materials in outer harbor; 
completing the widening, straightening and 
deepening of isolated remaining sections of 
Calumet River; and closing the gap between 
breakwaters. Timber crib breakwater (6,712 
feet, completed in 1904; concrete superstructure 
completed in 1924) is in fair condition. Cellular 
type steel-sheet pile breakwater (5,007 feet, 
completed in 1935) is in fair condition. Under 
30-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
permit from the Secretary of War, the 
Youngstown Sheet & Tube Co. and its 
predecessors removed all of south pier (completed 
in 1897) and replaced it with a concrete 
dock wall 2,961 feet long and 50 feet southerly of 
pier's original location. Under permits from the 
department, the Defense Plant Corp. built two 
sections of bulkheads on east side of river 
between a point opposite the Semet-Solvay slip 
and south side of former turning basin 3 at 
about 117th Street. United States widened and 
deepened the channel adjoining the new 
bulkhead except through the rock section, where 
widening was done by the corporation. Head of 
navigation for deep-draft vessels in the river is 
at turning basin 5 on north side of 130th Street. 
Total costs of existing project to end of fiscal 
year were $33,281,631, of which $21,608,286 was 
for new work ($18,571,683 regular funds and 
$3,036,603 public works funds), $10,984,344 
regular funds for maintenance and $689,001 
regular funds for rehabilitation. 
5. CHICAGO HARBOR, ILL. 
Location. Northeastern Illinois, 
southern end of Lake Michigan; 85 
southerly from Milwaukee, Wis. (See 
Survey Chart 752.) 
near 
miles 
Lake 
Previous projects. See page 1396 of Annual 
Report for 1962. 
Existing project. (See table 30-C.) 
For more detailed description see page 1242 of 
Annual Report for 1963. Completed Federal cost 
is $4,342,822, exclusive of amounts expended on 
previous projects. (See table 30-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are seven docks for 
handling various types of cargo, including 
overseas general cargo, salt and newsprint. 
Passenger excursion boats use three docks. 
There is one marine service dock for pleasure 
craft and two yacht club docks. City of Chicago 
owns five docks, four of which are used for 
commercial purposes. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections, 
reports and engineering and design were 
performed by hired labor at a cost of $11,504. 
Preparation of an Environmental Impact Statement 
was continued at a cost of $221. Under the 
dike disposal program, site selection studies and 
engineering and design were continued at a cost 
of $1,983. 
Condition at end of fiscal year. Existing 
project is complete. Northerly arm of inner 
breakwater (timber 4,034 feet, with 304 feet of 
shore return on north end, completed in 1875; 
concrete superstructure completed in 1934) is in 
good condition. Southerly arm of inner 
breakwater (timber 2,544 feet, completed in 
1880; concrete superstructure completed in 1930) 
is in good condition after rehabilitation by 
conversion to rubblemound completed in 
August 1966. Exterior breakwater (timber cribs 
5,413 feet, completed in 1889; concrete 
superstructure completed in 1930) is 
deteriorated under water and was rehabilitated 
in 1966 by conversion of lake side of structure to 
rubblemound. Southerly extension 
(rubblemound 2,213 feet, completed in 1917), and 
south arm (rubblemound 1,526 feet, completed 
in 1920; and concrete caisson 1,185 feet completed 
in 1922) are in good condition. Shore-arm 
extension (timber cribs 2,250 feet, completed in 
1917; inner 1,050 feet capped with concrete 
superstructure 1951; next adjoining 1,000 feet 
capped with stone blocks 1956; outer 200 feet 
capped with concrete superstructure 1952) is in 
good condition. Channel side of north pier 
(concrete superstructure, 960 feet, completed in 
1908, repaired in 1949, and rebuilt with steel 
sheet piling in 1965) is in good condition. Water 
level landward of lock is controlled and maintained 
at an elevation lower than that of Lake 
Michigan except during excessive storm runoff. 
Total costs of existing project to June 30, 1975 
were $9,540,208 of which $4,342,822 was for new 
work, $3,870,786 for maintenance, and 
$1,326,600 for rehabilatation. 
6. CHICAGO RIVER, ILL. 
Location. Cook and Lake Counties, Ill., 
navigable portions being wholly in Cook County 
and city of Chicago. (See Lake Survey Chart 
752.) For description, see page 1467 of Annual 
Report for 1932. 
Previous projects. See page 1394 of Annual 
Report for 1962. 
Existing project. Provides for a channel 21 
feet deep in the main river from its mouth at 
Rush Street to the junction of North and South 
Branches (0.7 miles), in the North Branch from 
the junction to North Avenue (2.22 miles), in the 
North Branch Canal (1.04 miles), and in the 
North Branch Turning Basin just south of 
North Avenue; and for a channel 9 feet deep in 
the North Branch from North Avenue to 
Addison Street. All depths are referred to 
normal pool, elevation 576.2 feet above mean 
water level at Father Point, Quebec (International 
Great Lakes Datum-1955). Portion of 
project authorized by River and Harbor Act of 
1946, is in deferred-for-restudy category. Es- 
30-4

CHICAGO, ILL., DISTRICT 
timate (1960) for this portion is $65,000. (See 
table 30-B for authorizing legislation.) 
Local Cooperation. Fully complied with for 
completed modifications. Act of July 24, 1946, 
provided improvement of channel is subject to 
condition that local interests furnish 
assurances they will hold the United States free 
from damages which may result from construction 
and maintenance of improvement. Requirement 
has not been complied with. 
Terminal facilities. There are 23 docks handling 
lake vessel and river barge cargoes. Most 
important cargoes handled are sand, gravel, 
coal, salt, cement, and petroleum products. 
There are three boatyards, two of which are used 
for servicing recreational craft and one engaged 
in constructing and servicing small craft as well 
as small Navy vessels. U.S. Government has 
one dock used by the Corps exclusively. 
Operations and results during fiscal year. 
New work: None. 
Maintenance: FY 1975 costs for rehabilitation 
of the Cherry Ave. revetment in the North 
Branch Turning basin completed by contract in 
FY 1974 were $58,596. Condition surveys, 
inspections, reports and engineering and design 
were performed by hired labor at a cost of 
$27,885. Preparation of an Environmental 
Impact Statement was continued at a cost of 
$6,120. Under the diked disposal program, site 
selection studies, and engineering and design 
were continued at a cost of $1,983. 
Condition at end of fiscal year. Project is 
complete except for dredging the channel 
between North Avenue and Addison Street as 
authorized by 1946 River and Harbor Act. 
Heads of navigation for deep-draft vessels are 
North Avenue on North Branch, and Archer 
Avenue on west fork of South Branch, 5.97 and 
5.52 miles, respectively, from Michigan Avenue 
Bridge. Head of navigation for barge traffic is 
near Touhy Avenue on North Shore Channel, 
about 11 miles from Michigan Avenue Bridge. 
Total costs of existing project to June 30, 1975 
were $4,033,681, of which $544,679 was for new 
work and $3,489,002 for maintenance. 
7. FOX RIVER, WIS. 
Location. Rises in Columbia County, Wis., 
and flows about 176 miles northerly into Green 
Bay. Wolf River, physically main river but by 
designation a tributary of Fox River, rises in 
central part of Forest County, Wis., and flows 
southerly. (See Lake Survey Chart 720 for Lake 
Winnebago and lower Fox River.) 
Previous Projects. See page 1368 of Annual 
Report for 1962. 
Existing project. Deepening and widening 
channel of Fox River from Depere 7 miles above 
mouth to confluence of Wolf River, a total length 
of 59 miles, to be 6 feet, with 9.6 feet in rock cut 
below DePere lock and 7 feet in other rock cuts 
on lower river below Menasha lock; construction 
and reconstruction of 19 locks and 9 dams; a 
concrete retaining wall at Kaukauna; construction 
and maintenance of harbors having depths 
of 6 feet on Lake Winnebago; widening Neenah 
Channel to 100 feet, with a 6-foot depth for about 
1 mile; and dredging, snagging, and otherwise 
improving Wolf River 47 miles from its mouth to 
New London, depth to be 4 feet. 
Cost of completed portion of project is $513,- 
424 for the lower river exclusive of previous 
projects. River and Harbor Act of 1925 portion of 
project is considered inactive and excluded from 
cost estimate. Estimated cost (1924) of this 
portion is $2,886,000. (See Table 30-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Wharf and landing 
facilities are in general, adequate for existing 
needs. (See table 30-D on locks and dams, Fox 
River, Wis.) 
Operation and results during fiscal year. 
Operation and Maintenance: Condition surveys, 
discharge observation, engineering and 
design, and inspection and reports were conducted 
by hired labor at a cost of $215,357. Locks 
and dams were operated as required and necessary 
repairs made to structures at a cost of 
$784,405. Upper and lower gates were rebuilt 
and valves repaired at Cedars Lock at a cost of 
$66,259. Lock gates were rebuilt and valves 
repaired at Little Chute Guard Lock at a cost of 
$17,877. Dredging and snagging from DePere to 
the mouth of the Wolf River, and repair of canal 
banks was accomplished at a cost of $63,476. 
Preparation of an Environmental Impact Statement 
was accomplished at a cost of $54,946. 
Condition at end of fiscal year. Existing 
project is complete except for inactive portion. 
Nineteen original locks and nine original dams 
have been rebuilt. (See existing project for year 
of completion of each.) Structures and dredging 
in pools have increased original depths generally 
about 2 feet. 
Work remaining to complete project consists 
of dredging in upper portion of Wolf River, and 
rock removal and deepening Neenah Channel 
on lower Fox River, which are no longer 
considered necessary. Except for Menasha lock, 
which should be rebuilt, existing locks and 
dams are in generally fair to good condition. 
Costs for existing project to June 30,1975 were 
$513,424 for new work and $15,313,094 for opera- 
30-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
tion and maintenance, a total of $15,826,518. 
Funds in the amount of $3,706,187 were 
expended between July 5, 1884, and June 30, 
1935, on operating and care of works of improvement 
under provisions of permanent indefinite 
appropriation for such purposes. 
8. GREEN BAY HARBOR, WIS. 
Location. At mouth of Fox River, at head of 
Green Bay, about 180 miles from Milwaukee, 
Wis., via Sturgeon Bay Canal, and about 49 
miles southwest of Menominee Harbor, Mich., 
and Wis. (See Lake Survey Chart 725.) 
Previous projects. See page 1366 of Annual 
Report for 1962. 
Existing project. (See table 30-C.) 
For a more detailed description of project see 
page 1216 of Annual Report for 1963. 
Cost of completed portion of project is $9,334,- 
421, Federal, and Non-Federal cost is $490,000 
including $100,000 contributed funds. Inactive 
portion of 1962 River and Harbor Act was 
estimated, in June 1965, at $63,000 (Federal) and 
$90,000 (non-Federal). (Dredging reach from 150 
feet downstream of C. & N. W. Railway Bridge 
through and to 1,700 feet upstream of said 
bridge.) (See table 30-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 16 wharves for 
handling coal, petroleum products, cement, 
limestone, general overseas cargo and miscellaneous 
commodities. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, engineering 
and design, and inspections and reports were 
made by hired labor at a cost of $85,330. Contract 
was awarded on 21 June 1973 for maintenance 
dredging and was completed in April 
1974. FY 1975 costs incurred for the contract 
were $9,520. Dredging was performed by the 
U.S. Hopper Dredge MARKHAM during July, 
August and September 1974, and April and May 
1975 with 821,214 cubic yards of material 
removed at a cost of $910,517. Costs incurred due 
to use of a land disposal area were $335,130 of 
which $94,875 were diked disposal funds. Preparation 
of an E.I.S. was made at a cost of 
$26,268. Under the diked disposal program, site 
selection and engineering and design costs were 
$82,125. 
Condition at end of fiscal year. Existing 
project is complete. The 1962 modification was 
started in Nov. 1966 and completed in Sept 1973. 
Dredging turning basin above Chicago & 
North-western Railway Bridge was commenced 
in August 1938 and completed in Sept. 1938. The 
turning basin was enlarged under authority of 
Section 5 of the River and Harbor Act of 4 March 
1915 in order to provide sufficient area for the 
large ships that use it. The work was performed 
as part of a maintenance dredging contract in 
Sept. and Oct. 1973. East revetment at Grassy 
Island was entirely removed in July 1935. West 
revetment was entirely removed in July 1935. 
Dredging Fox River and entrance channel to 
Tail Point Light was completed in Sept. 1967. 
The total costs of the existing project to June 30, 
1975 were $15,094,414 of which $14,153,614 were 
regular funds and $940,800 Public Works funds; 
$9,334,421 for new work and, $5,759,993 for 
maintenance. The new work costs do not include 
$100,000 contributed funds. 
9. ILLINOIS WATERWAY, ILL. AND 
IND. 
Location. Illinois River (entirely within State 
of Illinois), formed by confluence of Kankakee 
and Des Plaines River, flows southwesterly and 
enters Mississippi at Grafton, Ill., about 38 
miles above St. Louis. Illinois Waterway comprises 
Illinois River from its mouth to confluence 
of Kankakee and Des Plaines Rivers 
(273 miles); Des Plaines River to Lockport (18.1 
miles) and Chicago Sanitary and Ship Canal 
and South Branch of Chicago River to Lake 
Street, Chicago (34.5 miles). Also from a point 
12.4 miles above Lockport, Ill., waterway 
comprises Calumet-Sag Channel and Little 
Calumet and Calumet Rivers to turning basin 5, 
near entrance to Lake Calumet (23.8 miles); and 
Grand Calumet River from junction to 141st 
Street, deep (lake) draft navigation (9 miles) and 
to Clark Street, Gary, Ind. (4.2 miles). 
Previous Projects. For details, see page 1945 of 
Annual Report for 1915 and page 1172 of 
Annual Report for 1932. 
Existing project. See table 30-C and page 
1255 of Annual Report for 1963. Estimated cost 
of new work 1975 is $818,772,000 and includes 
$445,000 for Recreation Facilities under Code 
711. Calumet-Sag Modification, Part II, placed 
in the inactive category in June 1973, cost of 
$132,000,000 (July 1972) Federal and $16,300,- 
000 (July 1972) non-Federal; Calumet-Sag 
Modification, Part III, placed in the deferred-forrestudy 
category in March 1972, cost of $33,000,- 
000 (July 1971) Federal and $20,700,000 (July 
1971) non-Federal; Widen Pekin Bend, a portion 
of work authorized by River and Harbor Act of 
1935, placed in the inactive category, cost of 
$1,360,700 (July 1972) Federal; and, Widen 
Marseilles Canal to 300 feet, a portion of work 
authorized by River and Harbor Act of 1935, 
30-6

CHICAGO, ILL., DISTRICT 
placed in the deferred category, cost of $1,859,- 
300 (July 1972) Federal, are all excluded from 
present cost estimate. 
(See also tables 30-B, 30-E, 30-F and 30- 
G on authorizing legislation; existing and 
proposed locks and dams; lock and dam construction, 
foundations, cost and additional 
features entering into cost of project.) 
Local cooperation. Complied with for completed 
modifications and Part I of Calumet-Sag 
Modification. Required cooperation under October 
23, 1962 Act (Duplicate Locks) is that prior 
to construction local interests agree to assume 
title to and maintain and operate new bridge 
across lower approach to Brandon Road lock 
when bridge is placed in service. Formal 
assurances for the October 23, 1962 Act have not 
been requested. For details see Pages 1412 to 
1414, Annual Report of 1962. 
Terminal facilities. Of the 13 principal cities 
and towns along Illinois River, about five own 
dock frontage, more or less improved for boat 
landings; four own dock frontage with no 
improvements; and four own no frontage except 
at street ends. At Peoria, there is a $400,000 
modem river-rail municipal public terminal 
with available frontage of 1,100 feet; 205 feet 
occupied by a dockhouse and 190 feet by an open 
dock. Dockhouse is served by a wharf boat 45 by 
230 feet, and an escalator capable of handling 
1,000 tons a day. This terminal is served by 
equivalent of a beltline railroad. Grain barge 
loading facilities are available at 26 docks 
between Grafton and Joliet, 21 of which have 
grain elevators. Private coal-loading terminals 
are at Frederick, Havana, Liverpool, Copperas 
Creek, Kingston Lake, and Peoria. Coalunloading 
terminals are at Havana and 
Hennepin powerplants; at mouth of Vermillion 
River near LaSalle and at Joliet. Bulkpetroleum 
terminals are in Havana, Kingston 
Mines, Peoria, Peru, Seneca, and Joliet. Sand 
and gravel plants are at Kingston Lake, 
Onillicothe, Ottawa, Morris, Joliet, and 
Lockport. From Chicago Sanitary and Ship 
Canal, sand, gravel, oil, grain, and gasoline are 
shipped from Lockport, and petroleum products, 
steel and stone from Lemont. Two grain 
elevators are at Lockport. Bulk-petroleum terminals 
are at Argo and Forest View, Ill., and at 
California Avenue, Cicero Avenue, Justice and 
Kedzie Avenue, Chicago; one liquid industrialchemicals 
terminal is at Marseilles, one at 
Seneca, two at Morris, two at Channahon, three 
at Joliet, one at Willow Springs and one at 
Cicero Avenue in Stickney, Ill. Private coalunloading 
terminals are at Ridgeland Avenue, 
Crawford Avenue, Loomis Street, Fisk Street, 
and Addison Street, Chicago, at Western 
Avenue, Chicago, bulk and package sugar are 
handled through American Sugar Refining Co. 
Bulk fertilizer terminals are at Marseilles (two), 
and Joliet. A liquid asphalt terminal is at 
Summit. Cement terminals are at Lemont, 
Summit, Forest View, and at Cicero Avenue in 
Chicago. A scrap iron bulk terminal is at 
California Avenue, Chicago. State of Illinois 
barge terminal, including a 1,500,000-bushel 
grain elevator, is at Damen Avenue, Chicago, on 
South Branch of Chicago River. One sand-andgravel 
distribution yard is on the Calumet-Sag 
Channel. A petroleum-unloading terminal is on 
Little Calumet River at Riverdale, just upstream 
from junction with Sag Channel; and two 
petroleum terminals are at Homan Avenue in 
Blue Island. Plans for further terminals and 
docks between Grafton and Chicago are underway. 
Operations and results during fiscal year. 
New work: Duplicate Locks-Planning was 
continued by government forces with costs of 
$420,666. 
Calumet-Sag Modification, Part I-Channel 
widening: Fiscal adjustments were made on 
completed dredging as follows: Sec V dredging, 
contract 67-27 payment of $9,764. Dredging in 
vicinity of Illinois Central Bridge was completed 
with 194,000 cu. yds. removed at a cost of 
$218,735. 
Railroad Bridge relocations: Fiscal adjustments 
totalling $66,878 were made on real estate 
activities for the Blue Island Group of bridges, 
and $58,401 for Kensington & Eastern RR 
bridge contract. 
Highway Bridge relocations and 
modification: Fiscal adjustment of $16,600 was 
made for Kedzie Ave., Francisco Ave., and 104th 
St. Hwy. Bridge relocations. An adjustment of 
-$18,417 was made on the design contract for 
Western Ave. Bridge Relocation. Work on Indiana 
Ave. Hwy. Bridge relocation continued at a 
cost of $1,390,999. 
Engineering and design and supervision and 
administration costs were $166,532. 
Recreation Facilities under Code 711- 
Planning for restrooms and paving for 
LaGrange and Peoria Locks and Dams was 
continued with fiscal years costs of $15,703, and 
$3,176, respectively. Work on the O'Brien Lock 
& Dam Comfort Station (contract #73-84) was 
started 22 Aug. 1973 with fiscal year costs of 
$85,711. Work is about 94% complete. 
Maintenance: Alton Pool costs by hired labor 
for condition and operation studies were 
$106,285; dredging $401,993; and supervision 
and administration, $54,355. 
All pools above Alton Pool. Condition and 
30-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
operation studies and engineering and design 
were conducted by hired labor at a cost of 
$1,125,046. Government plant and hired labor 
was used to perform remedial bank protection 
work, remove silt, obstructions and snags from 
the channel and remove other debris from forebays 
of locks and sluice gates at dams to maintain 
operation of navigable structures as well as 
assist in the rehabilitation of locks and dams at 
a cost of $548,969. FY 1975 funds in the amount 
of $9763 and $1451 were expended for contract 
dredging performed in FY 1974 in the Little 
Calumet River and Calumet-Sag Channel 
respectively. Preparation of an Environmental 
Impact Statement was accomplished at a cost of 
$174,652. 
Operation and care of lock and dams: The 
locks and dams were operated as required and 
necessary minor repairs were made thereto and 
to appurtenant structures at a cost of $4,614,673. 
FY 1975 funds in the amount of $54,752 were 
expended for resurfacing upper headgate and 
lower headgate respectively at Starved Rock 
and Dresden Island Dams completed in FY74. A 
contract to resurface the lock walls at Marseilles 
Lock was accomplished at a cost of 
$2,189,497. A contract to repair mooring pier 
number one at Lockport Lock was accomplished 
at a cost of $131,051. 
Total operation and maintenance costs were 
$8,849,854 for all pools above Alton Pool. 
Condition at end of fiscal year. The existing 
project, exclusive of the deferred and inactive 
portion and the Calumet-Sag and Duplicate 
Locks modifications, is complete. The Calumet- 
Sag Modification, Part I, was 97 percent complete. 
Preconstruction planning on the Duplicate 
Locks was in progress. Work on Recreation 
Facilities (restrooms and paving areas) was 
completed for LaGrange and O'Brien Locks and 
Dams. Eight locks and six dams are complete, 
and there is a channel 300 feet wide and 9 feet 
deep between Grafton and Lockport, Ill., with 
exception of Marseilles Canal which is 200 feet 
wide. Limiting horizontal clearance is as 
follows: 118 feet at a bridge in the reach from 
Grafton to Utica, Ill.; 110 feet at bridges between 
Utica and Lockport, Ill.; 80 feet at the emergency 
(Butterfly) dam, mile 293.) between Lockport 
and the Sag Junction; 80 feet at a bridge 
between the Sag Junction and Lake Michigan 
via Chicago Sanitary and Ship Canal and 
Chicago River; and 67.0 feet at a bridge between 
the Sag Junction and turning basin 5 in Calumet 
River, via the Calumet-Sag Channel. Work 
remaining on Calumet-Sag Modification, Part I, 
are: continue relocation of one highway bridge; 
and provision for lift on one highway bridge; 
Also, 1962 modification, duplicate locks at seven 
locations, Lockport, Brandon Road, Dresden 
Island, Marseilles, Starved Rock, Peoria, and 
LaGrange has not been started. Work remaining 
on 1935 modification consisting of widening 
of Pekin Bend and widening Marseilles 
Canal has been reclassified to inactive and 
deferred. Calumet-Sag Modification, Part II, 
has been reclassified to inactive. Calumet-Sag 
Modification, Part III, has been deferred-forrestudy. 
(See table 30-H for total cost of existing 
project to June 30, 1975.) 
10. INDIANA HARBOR, IND. 
Location. Northwestern Indiana (Lake County), 
on southwest shore of Lake Michigan, 18 
miles southeast of Chicago Harbor. (See Lake 
Survey Chart 755.) 
Previous projects. For details see page 1943 of 
Annual Report for 1915, and page 1520 of 
Annual Report for 1938. 
Existing project. Provides for a northerly 
rubblemound breakwater, 1,120 feet long, an 
easterly reinforced concrete-caisson breakwater 
201 feet long, an extension of this latter 
breakwater about 2,300 feet to north, and 
construction and placing of a light-house crib; 
an outer harbor entrance channel generally 800 
feet wide with a depth of 29 feet; dredging an 
outer harbor basin to 28 feet deep, and canal 
entrance channel to 27 feet deep; deepening 
main stem of Indiana Harbor canal for a width 
of 190 feet with a depth of 25 feet from outer 
harbor to 100 feet lakeward of Dickey Place; 
widening canal to a bottom width of 260 feet 
with a depth of 22 feet from 100 feet lakeward of 
Dickey Place to The Forks and dredging 
Calumet River Branch from The Forks to 141st 
Street to same width and depth; a channel 22 
feet deep and 160 feet wide in Lake George 
Branch from The Forks to White Oak Avenue; 
maintenance of a channel 20 feet deep and 80 
feet wide in remainder of Calumet River Branch 
south of north line of 141st Street, except 
removal of sewage deposits and other city 
refuse, after completion and acceptance from 
private parties; and construction of a turning 
basin at The Forks 22 feet deep. That part of 
Calumet River Branch Channel from north line 
of 141st Street to Grand Calumet River has not 
been completed by local interest or accepted for 
maintenance by the United States. Cost of 
completed new work exclusive of inactive work 
and amount expended on previous projects are 
$4,848,980, Federal and $782,000 non-Federal, 
which includes a cash contribution of $12,500. 
Uncompleted portion of 1930 R. & H. Act is 
inactive estimated at $234,000 (1965) Federal. 
Uncompleted portion of the 1935 R. & H. Act is 
inactive estimated at $1,288,000 (1965) Federal 
and $595,000 (1965) non-Federal. The work 
authorized by the 1965 R. & H. Act is inactive 
30-8

CHICAGO, ILL., DISTRICT 
estimated at $222,000 (1972) Federal and $256,- 
000 (1972) non-Federal (See table 30-B for 
authorizing legislation). 
Local cooperation. Act of 1937 provides 
enlargement of Indiana Harbor Canal shall not 
be undertaken until local interests furnish a 
right-of-way 300 feet wide and construct substantial 
bulkheads along channel on established 
lines shown on map accompanying Rivers 
and Harbors Committee Document 13, 75th 
Congress, 1st session, provided that improvement 
on one side may proceed in any section on 
fulfillment of conditions for that side of section, 
and provided further, that south of turning 
basin at The Forks (beginning 450 feet south of 
intersection of present Calumet Branch and 
mainstem bulkhead lines), widening and 
deepening by the United States shall be done 
only as rights-of-way and bulkheads on at least 
one side of the channel are continuously 
provided southward from above limit of turning 
basin at The Forks. To provide for 300-foot 
channel, a parcel of land (of about 4.6 acres), 
generally 100 feet wide, lying on east side of 
Calumet River Branch, commencing at north 
side of 141st Street and extending northward 
toward The Forks for about 2,170 feet, has been 
conveyed to and accepted by the United States. 
Local interests constructed about 1,350 feet of 
bulkhead along east side of Calumet River 
Branch, and reconstructed bulkhead on west 
side from The Forks to 141st Street. Defense 
Plant Corp. built a bulkhead along east side of 
canal between Pennsylvania Railroad Co.'s 
bridge and Dickey Place Bridge; the United 
States widened and deepened east side of this 
portion of widening. Youngstown Sheet and 
Tube Co. constructed a bulkhead along west side 
of canal between Indiana Harbor Belt Railroad 
Co. bridge and the Pennsylvania Railroad Co. 
bridge, and the United States widened and 
deepened west side of this portion of widening. 
All prior requirements fully complied with. 
Terminal facilities. Four docks for handling 
iron ore, limestone and taconite; two docks for 
handling steel mill products by barge; eight 
docks for petroleum products; three docks for 
miscellaneous commodities and two docks used 
exclusively for winter mooring of vessels in 
layup. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, illegal deposit 
investigations, engineering and design, and 
inspections and reports were conducted by hired 
labor at a cost of $27,794. Preparation of an 
Environmental Impact Statement was accomplished 
at a cost of $2,506. 
Condition at end of fiscal year. Existing 
project is complete. North breakwater 
(rubblemound, 1,120 feet, completed in 1922) is 
in good condition. East breakwater (concrete 
caisson, 201 feet, completed in 1926) and 
northerly extension (rubblemound, 2,324 feet, 
completed in 1935) are in good condition. Head 
of navigation for commercial vessels is at the 
Baltimore & Ohio Terminal Railroad bridge on 
the Lake George Branch about 3 miles from 
outer harbor, and at 141st Street highway 
bridge about 2,200 feet south of TheForks on the 
Calumet River Branch about 2.5 miles from 
outer harbor. 
The total costs of the existing project to June 
30, 1975 were $9,353,382, of which $7,722,841 
were regular funds, $1,618,041 Public Works 
funds, and $12,500 contributed funds; 
$4,848,980 being for new work and $4,504,402 for 
maintenance. 
11. KENOSHA HARBOR, WIS. 
Location. On west shore of Lake Michigan 
about 35 miles south of Milwaukee and about 54 
miles north of Chicago. (See Lake Survey Chart 
74.) 
Previous projects. See page 1390 of Annual 
Report for 1962. 
Existing project. See table 30-C. For detailed 
description see page 1237, Annual Report for 
1963. Estimated (1975) Federal Cost is $552,000 
exclusive of amounts expended on previous 
projects. Non-Federal estimate is $43,000 (July 
1975) including $3,000 contributed by local 
interests. (See table 30-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves used for 
miscellaneous foreign oversea commodities and 
autos, and also several fishing wharves. While 
these facilities are considered generally adequate 
for existing commerce, more efficient use 
of existing terminals and utilization of 
available frontage for development of additional 
terminals should be made. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections, 
miscellaneous reports, engineering and design 
and preparation of an Environmental Impact 
Statement were made by hired labor at a cost of 
$10,000. Fiscal year costs for a contract awarded 
on 28 June 1974 for construction of a confined 
disposal facility were $2,347,301. Supervision 
and inspection associated with the contract 
were accomplished at a cost of $155,655. Miscellaneous 
engineering and design and preparation 
of an Environmental Impact Statement 
in connection with the diked disposal 
program were accomplished at a cost of $23,775. 
Condition at end of fiscal year. The existing 
project is complete except for dredging 25 foot 
30-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
strips adjacent to the north and south piers 
which will be completed after rehabilitation of 
the piers. The north and south piers were 
completed in 1900, and the breakwater in 1909. 
The north pier is in excellent condition. The 
south pier and breakwater are in generally fair 
condition. The total costs of the existing project 
to June 30, 1975 were $5,730,170, of which 
$5,702,512 were regular funds and $27,658 
Emergency Relief funds; $393,130 being for new 
work, $4,066,765 for maintenance and 
$1,270,275 for rehabilitation. The new work 
costs do not include $3,000 contributed funds. 
12. KEWAUNEE HARBOR, WIS. 
Location. On west shore of Lake Michigan, 
about 105 miles north of Milwaukee and about 
78 miles from Green Bay, via Sturgeon Bay 
Canal. Harbor is at mouth of Kewaunee River. 
(See Lake Survey Chart 73.) 
Previous projects. See page 1375 of Annual 
Report of 1962. 
Existing project. See table 30-C. 
Costs of completed project are $603,021, 
Federal, and $9,000 non-Federal, exclusive of 
amount expended on previous projects. Uncompleted 
portion (estimated $200,000-July 
1965) of 1935 River and Harbor Act is considered 
inactive, and excluded from present cost estimate. 
A portion of 1960 River and Harbor Act 
is also considered inactive and cost of this 
portion, (turning basin at Fisherman's Point) 
was $29,000 (Mar. 1961) and excluded from 
present cost estimate. (See table 30-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two car-ferry slips, a 
petroleum tank farm, a Corps of Engineers 
project office, and several fishing wharves. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections, 
miscellaneous reports and engineering and 
design by hired labor cost $7,120. Repairs to the 
south pier were made by hired labor in April 
1975 at a cost of $13,725. Preparation of an 
Environmental Impact Statement was accomplished 
at a cost of $1,159. Under the diked disposal 
program engineering and design and 
preparation of an Environmental Impact Statement 
were accomplished at a cost of $109,489. 
Condition at end of fiscal year. Active portion 
of existing project is complete. The north pier 
was completed in 1897 and the remaining 
portion is in generally good condition. 
Rehabilitation of the south pier was completed 
in June 1967. Construction of north breakwater 
and shore connection, except for a gap of 150 feet 
about 830 feet from shoreward end, and removal 
of outer 706.5 linear feet of north pier were 
commenced in September 1935 and completed in 
June 1937. Removed 500 linear feet of north pier 
in April-May 1963 and widened and deepened 
the adjacent channel in 1965. Outer end of the 
north pier was struck and severely damaged by 
car ferry vessel in Oct. 1973 and a 24 foot section 
at outer end was subsequently removed thus 
reducing the structure to a length of 626 feet. 
Dredging entrance channel and interior basin 
to existing project depth was commenced in 
April and completed in October 1938. Kewaunee 
River is navigable for about 6.5 miles above 
mouth for craft drawing not more than 4 feet. 
Total cost of existing project to June 30, 1975 
was $2,728,780, of which $603,021 was for new 
work ($183,021 regular and $420,000 emergency 
relief funds) $1,508,459 regular funds for maintenance 
and $617,300 regular funds for 
rehabilitation. 
13. MANITOWOC HARBOR, WIS. 
Location. On West shore of Lake Michigan 
about 79 miles north of Milwaukee and about 
106 miles from Green Bay via Sturgeon Bay 
Canal. (See Lake Survey Chart 735.) 
Previous projects. See page 1379 of Annual 
Report for 1962. 
Existing project. See table 30-C. 
For detailed description see page 1228, Annual 
Report for 1963. Estimated costs (1970) of 
new work for 1968 modification are $81,000 
Federal and $30,000 non-Federal which includes 
a cash contribution of $18,000. Work on the 1968 
modification has been postponed. The portion 
authorized by the 1962 River and Harbor Act is 
inactive and estimated (1970) at $1,150,000, 
Federal, and $105,000 non-Federal. (See table 
30-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
completed modifications. For 1968 modification 
local interests must contribute in cash 18 
percent of the first cost of the general navigation 
facilities, comprising extension of the deep-draft 
channel, such contribution being presently 
estimated at $18,000 (1970 price level), to be paid 
in a lump-sum before construction is started and 
to be subject to final adjustment after actual 
costs have been determined; provide without 
cost to the United States all lands, easements, 
and rights-of-way required for construction and 
subsequent maintenance of the project 
modification upon the request of the Chief of 
Engineers, including suitable areas determined 
by the Chief of Engineers to be required in the 
general public interest for initial and subsequent 
disposal of spoil, and also necessary 
30-10

CHICAGO, ILL., DISTRICT 
retaining dikes, bulkheads, and embankments 
therefor or the costs of such retaining works; 
hold and save the United States free from 
damages that may result from the construction 
and maintenance of the project modification; 
provide and maintain berthing areas at the 
docks adjacent to the improvement with depth 
commensurate with the adjacent Federal project 
depth; accomplish at no cost to the United 
States all relocations and alterations of utilities 
necessary for the project; and assume full 
responsibility for all project first costs in excess 
of the Federal cost limitation of $500,000. 
Terminal facilities. Three car-ferry slips, a 
grain elevator, one shipbuilding yard, and three 
other wharves used for handling coal, building 
materials, cement, and miscellaneous commodities. 
While these facilities are considered 
fairly adequate for existing commerce, it is 
believed the city should provide a suitable wharf 
with warehouse and railway connection open to 
the general public. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections, 
miscellaneous reports and engineering and 
design were made by hired labor at a cost of 
$20,955. Repairs to the north and south breakwaters, 
and north stub pier were made by hired 
labor during August and September 1974 and 
June 1975 at a cost of $126,130. Preparation of 
alt Environmental Impact Statement was 
accomplished at a cost of $2,915. Fiscal year 
costs for a contract awarded on 26 June 1974 for 
construction of a confined disposal facility were 
$1,313,198. Supervision and inspection associated 
with the contract were accomplished at a 
cost of $41,624. Miscellaneous engineering and 
design and preparation of an Environmental 
Impact Statement in connection with the diked 
disposal program were accomplished at a cost of 
$21,095. 
Condition at end of fiscal year. Existing 
project is complete except for the 1962 and 1968 
modifications. The 1962 modification is inactive. 
Work on the 1968 modification has been 
postponed. The breakwaters, completed in 1910, 
are in generally fair condition. Dredging a 
channel through outer basin to existing project 
depth and removal of a portion of old north stub 
pier at the river entrance were completed in 
December 1937. Dredging river channel was 
completed in July 1942. Costs of existing project 
to June 30, 1975 were $481,038 for new work and 
$3,417,508 for maintenance, a total of 
$3,898,546. 
14. MENOMINEE HARBOR AND 
RIVER, MICH. AND WIS. 
Location. On west shore of Green Bay, about 
49 miles northeast of Green Bay Harbor, and 
about 155 miles from Milwaukee via Sturgeon 
Bay Canal. (See Lake Survey Chart 723.) 
Previous projects. See page 1361-2 of Annual 
Report for 1962. 
Existing project. See table 30-C. 
For detailed description see page 1214, Annual 
Report for 1963. The portion authorized by 
1960 River and Harbor Act is inactive and 
estimated (1964) at $442,000, Federal, and 
$105,000 non-Federal. Costs of completed new 
work exclusive of inactive work and amount 
expended on previous projects are $221,053 
Federal and $50,762 non-Federal, which includes 
a cash contribution of $36,762. (See table 
30-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
completed work. 
Terminal facilities. There are 9 wharves for 
handling coal, limestone, pulp and miscellaneous 
commodities. City of Marinette 
provided a public wharf. Facilities are considered 
fairly adequate for existing commerce, 
except that there is need for a public wharf 
owned by city of Menominee, with warehouse 
and railway connection. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections 
and miscellaneous reports were made by hired 
labor at a cost of $12,649. Repair of the circular 
cell pier head at the outer end of the north pier 
was accomplished by hired labor during September 
1974 at a cost of $29,193. Preparation of 
an Environmental Impact Statement was 
accomplished at a cost of $2,946. Site selection 
studies, engineering and design and preparation 
of an Environmental Impact Statement for 
the diked disposal program were conducted by 
hired labor at a cost of $74,718. 
Condition at end of fiscal year. The project in 
effect prior to the modification of March 2, 1945 
was completed in 1938. No additional work was 
necessary under the modification of March 2, 
1945 to provide a depth of 12 feet in the extension 
of the channel to the vicinity of the Marinette 
Yacht Club as project depth or more was 
available. The entrance piers were completed in 
1884, and were rehabilitated (1954-1964) and are 
in excellent condition. Dreding of the channel 
below the Marinette municipal wharf, together 
with enlarging the turning basin to existing 
project depth, was commenced in May 1938 and 
completed in November 1938. The north pier is 
maintained for a length of about 1,202 feet. 
Modification of the project authorized by the 
1960 R. & H. Act is inactive. Construction for the 
1967 Modification was started August 17, 1968 
and completed in October 1968. 
The costs under the existing project to June 
30, 1975 were $221,053 for new work, $1,243,735 
30-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
for maintenance and $1,351,852 for rehabilitation, 
a total of $2,816,640. 
15. MICHIGAN CITY HARBOR, IND. 
Location. Northwest Indiana (in La Porte 
County), on southeast shore of Lake Michigan, 
38 miles southeast of Chicago Harbor. (See Lake 
Survey Chart 75.) For descriptions, see page 
1482 of Annual Report for 1932. 
Previous projects. See page 1407 of Annual 
Report for 1962. 
Existing project. See table 30-C. 
Costs of completed new work are $1,256,257 
Federal, exclusive of amount expended on 
previous project and $37,800 non-Federal, which 
includes a cash contribution of $30,800. (See 
table 30-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Four fish docks, one city 
dock, and one grain elevator in this harbor. 
Commodities handled at this harbor are salt 
and fresh fish. There are three small boatyards, 
which repair and construct recreational craft 
only. One public dock is owned by city and has 
not been used for commercial purposes. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections 
and reports, and engineering and design were 
conducted by hired labor at a cost of $13,437. 
Studies for mitigation of shore damage (Section 
111) were conducted at a cost of $21,096. Site 
selection studies and preparation of an Environmental 
Impact Statement for the diked disposal 
program were conducted at a cost of $1,000. 
Condition at end of fiscal year. Existing 
project is complete. Concrete superstructure, 
1,304 feet, on detached breakwater, completed in 
1925, and entrance piers were completed in 1931. 
Rehabilitation of the detached breakwater by 
conversion to a rubblemound was completed in 
1969 and the structure is in excellent condition. 
Rehabilitation of portions of the entrance piers 
have also been completed and are in excellent 
condition. The remainder of the entrance piers, 
completed in 1930, are in poor condition and are 
being repaired. Under permit from Secretary of 
War, the Northern Indiana Public Service Co. 
removed 615 feet of inner end of west pier and 
about 719 feet of bulkhead south of pier, and 
replaced them with a steel sheet pile bulkhead 
located landward of former dock line. Area 
channelward of new bulkhead was dredged by 
permittee to 18 feet. Head of navigation for 
deepdraft commercial vessels and barges is at 
Franklin Street Bridge at head of project, 1.45 
miles above outer end of west pier. Above this 
point, depths are sufficient only for small 
shallow draft launches. Total costs of existing 
project to June 30, 1975 were $5,617,939, of 
which $1,256,257 was for new work and 
$2,743,012 for maintenance, and $1,618,670 for 
rehabilitation. 
16. MILWAUKEE HARBOR, WIS. 
Location. On west shore of Lake Michigan 
about 85 miles north of Chicago and about 83 
miles west of Grand Haven, Mich. (See Lake 
Survey Chart 743.) 
Previous projects. See page 1385 of Annual 
Report for 1962. 
Existing project. See table 30-C. 
For detailed description see page 1232 of 
Annual Report for 1963. 
Completed new work costs are $6,937,804, 
Federal and $478,000, non-Federal, exclusive of 
amount expended on previous projects. The 
uncompleted portion of the 1935 River and 
Harbor Act was placed in the inactive category 
in June 1973. Estimated costs are $119,000 (July 
1972) Federal and $1,170,000 (July 1972) non- 
Federal for this portion. Uncompleted portion of 
1945 River and Harbor Act is inactive. Estimated 
cost (1960) this portion is $225,000. (See 
table 30-B for authorizing legislation. 
Local cooperation. Complied with for acts of 
March 2, 1945, October 23, 1962, and July 14, 
1960, except inactive portion of 1945 act. Act of 
August 30, 1935, provided that original dredging 
of outer harbor area be done by city of 
Milwaukee and city of Milwaukee be reimbursed 
at actual cost but not to exceed 10 cents per cubic 
yard, place measurement, for original dredging 
done subsequent to authorization of work by 
Congress. Agreement covering dredging was 
executed by Secretary of War, February 23,1934, 
after this work was originally authorized as part 
of public works program. City was reimbursed 
for 10 percent of dredging. 
Terminal facilities. Four car-ferry slips, and 
57 other wharves, private and municipal, used 
for handling coal, grain, building materials, 
cement, petroleum products, and miscellaneous 
commodities. As facilities in inner harbor were 
inadequate for existing commerce, Milwaukee 
Harbor Commission has constructed nine docks 
in the outer harbor for handling general cargo. 
Operations and results during fiscal year. 
Maintenance. Condition surveys, inspection 
and reports and engineering and design were 
performed by hired labor at a cost of $80,641. 
Temporary repairs of the north shore connector 
breakwater, were made during May 1975 at a 
cost of $26,249. Repairs to the north breakwater 
were made by hired labor in June 1975 at a cost 
of $41,036. Preparation of an Environmental 
Impact Statement was made at a cost of $4,092. 
30-12

CHICAGO, ILL., DISTRICT 
Fiscal year costs for a contract awarded on 29 
June 1973 for construction of a confined disposal 
facility were $3,460,406. Supervision and 
inspection associated with the contract were 
accomplished at a cost of $120,280. Miscellaneous 
engineering and design in connection 
with the diked disposal program were accomplished 
at a cost of $11,103. Hired labor costs 
associated with preparation of the confined 
disposal facility for maintenance dredging 
scheduled for early FY 1976 were $5304. 
Condition at end of fiscal year. Existing 
project is complete except for inactive portions. 
The 1962 modification was completed in July 
1967. The 1960 modification was completed in 
November 1962. North breakwater and shore 
connection, 9,954 feet long, was completed in 
August 1925. North pier was completed in 1905 
and construction of south pier was completed in 
November 1910. Construction of south 
breakwater and shore connection was completed 
in October 1929. Before modification of 
August 30, 1935, city of Milwaukee dredged most 
of the area in the outer harbor south of inner 
entrance piers and lakeward of pierhead line to 
more than 21 feet below datum without cost to 
the United States. City of Milwaukee also 
dredged a portion of the area in the outer harbor 
north of inner entrance piers to provide an 
approach channel to the passenger and auto 
pier opposite East Clybourn Street. Work on the 
1945 modification was completed in August 
1957, except for inactive portion which consists 
of dredging the Milwaukee River from Buffalo 
Street to the upper limit of the project at 
Humboldt Avenue. Northerly 3,000 feet of north 
breakwater and the shore connection are in poor 
condition. The remainder of north breakwater is 
in generally good condition. South breakwater 
and shore connections are in generally good 
condition. Costs of existing project were 
$6,937,804 for new work, $11,729,696 for maintenance, 
and $1,891,810 for rehabilitation, a 
total of $20,559,310. 
17. NEW BUFFALO HARBOR, MICH. 
Location. At mouth of Galien River on southeast 
shore of Lake Michigan in Berrien County, 
about 45 miles easterly from Chicago, Ill. (See 
Lake Survey Chart 75.) 
Local cooperation. Local interests must contribute 
in cash 48 percent of the first cost of 
construction of the general navigation facilities, 
such contribution presently estimated (July 
1974 price levels) at $1,230,000 to be paid in a 
lump sum before start of construction, subject to 
final adjustment after actual costs are determined; 
provide lands and rights-of-way for 
construction and future maintenance of project 
and aids to navigation upon request of the Chief 
of Engineers, including suitable spoil-disposal 
areas; hold the United States free from 
damages; provide and maintain necessary 
mooring facilities open to all equally, and 
including dredging berthing areas to depths 
commensurate with related projects depths; and 
reserve mooring facilities adequate for accommodation 
of transient craft. Formal assurances 
were requested in December 1965. Michigan 
State Waterways Commission stated it would 
provide the cash contribution and coordinate 
local efforts to meet other cooperation requirements. 
All local cooperation requirements 
have been met except for a portion of contributed 
funding. 
Existing project. Provides for an entrance 
channel 10 feet deep by 80 to 180 feet wide and 
850 feet long, to mouth of Galien River; new 
north and south breakwaters 1,305 and 740 feet 
long, respectively, and deepening inner channel 
to Galien River to 8 feet and 80 feet wide and 
1,250 feet long. Project was authorized by River 
and Harbor Act of 1962. Estimated costs (1974) 
are $1,350,000 Federal (Corps of Engineers) and 
$2,130,000 non-Federal, which includes a cash 
contribution of $1,230,000. Total project cost is 
$3,480,000. 
Terminal facilities. One village owned boat 
ramp and three privately operated marinas and 
a private boat club facility. 
Operations and results during fiscal year. 
New Work: Engineering and design was completed 
by hired labor at a cost of $5,904. 
Condition at end of fiscal year. Construction 
was started. Costs of existing project to June 30, 
1975 were $1,038,716. Reimbursement from contributed 
funds in amount of $951,935 was made 
during the year. 
18. NORTHPORT HARBOR, WIS 
Location. The Northport Harbor project is 
located on the northern tip of Wisconsin's Door 
County Peninsula. The peninsula is on the east 
side of Wisconsin and separates Green Bay from 
Lake Michigan. 
Existing project. The Northport Harbor project 
was recommended in House Document No. 
168, 92nd Congress, 1st Session. It was 
authorized under Section 201, Public Law 89-298 
by separate resolutions of the Senate and House 
Public Works Committees adopted on 30 June 
1972 and 10 November 1971, respectively. The 
general navigation facilities consist of rubblemound 
breakwater, a harbor entrance channel 
and a maneuver area. Associated recreational 
facilities include safety railings, a parking area 
and sanitary facilities to accommodate recrea- 
30-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
tional fishing from the breakwater. The north, 
east and south breakwater have lengths of 560 
feet, 650 feet and 460 feet, respectively. The 
entrance channel is 100 feet wide and 12 feet 
deep. The maneuver area, located within the 
breakwater, is 100 to 150 feet wide, 450 feet long 
and 12 feet deep. Recreational boating facilities, 
including four launching lanes and berths 
to accommodate transient craft were to be provided 
in connection with the authorized project. 
No facilities to accommodate permanently 
based boats were to be provided. 
Local cooperation. Local cooperation includes 
a cash contribution of 11.6 percent of the first 
cost of the general navigation facilities, as well 
as 50 percent of the first cost of facilities necessary 
to support fishing from the breakwater. In 
addition, local interests are required to provide 
all lands, easements and rights-of-way. Local 
interests must also provide all facilities needed 
to support recreational boating activities. 
Terminal facilities. The existing terminal 
facilities consist of a concrete pier used by the 
Washington Island Ferry Line which operates 
between the mainland and Washington Island. 
The pier is the mainland terminal for loading 
and unloading vehicles, passengers and cargo. 
No storage area or warehouse is located at this 
terminal. 
Operation and results during Fiscal Year. 
Advanced engineering and design studies were 
started and continued during the fiscal year at a 
cost of $39,968. 
Condition at end of Fiscal Year. Phase I General 
Design and Memorandum studies were 
underway. 
19. OCONTO HARBOR, WIS. 
Location. On the west shore of Green Bay, 
about 31 miles northeasterly from Green Bay 
Harbor, Wis., and about 25 miles southwesterly 
from Menominee Harbor, Mich. and Wis., at 
mouth of Oconto River. (See U.S. Lake Survey 
Chart No. 703.) 
Previous projects. For details see page 1187 of 
Annual Report for 1958. 
Existing project. See Table-30 C. 
For detailed description see page 1187, Annual 
Report for 1958. See table 30-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Two municipally owned 
wharves of 400 and 100 foot frontage, respectively, 
for miscellaneous freight, open to general 
public use. Facilities considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections 
and reports, and engineering and design were 
performed by hired labor at a cost of $7,772. 
Repair of the south pier, including placement of 
13,951 tons of riprap stone, was continued by 
hired labor from July to October 1974 at a cost of 
$411,347. 
Condition at end of fiscal year. Existing 
project was completed in 1912. Piers were 
completed in 1885. Dredging channel and 
turning basin to existing project depth was 
commenced in July 1911 and completed in May 
1912. The north pier was rebuilt as a 
rubblemound by local interests in 1967. South 
pier is in poor condition and is being repaired. 
Total costs for existing project to June 30, 1975 
were $46,185 for new work and $832,820 for 
maintenance, a total of $879,005. 
20. PORT WASHING HARBOR, WIS. 
Location. On the west shore of Lake 
Michigan, about 53 miles south of Manitowoc 
and about 29 miles north of Milwaukee. (See 
Lake Survey Chart 74.) 
Previous projects. For details, see page 1938 of 
Annual Report for 1915, and page 1459 of 
Annual Report for 1938. 
Existing project. See table 30-C. 
New work for completed project cost $810,709, 
exclusive of amounts expended on previous 
projects. The 1958 River and Harbor Act portion 
is considered inactive and excluded from foregoing 
costs. Estimated cost of this portion (1960) is 
$2,750,000. (See table 30-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one coal wharf, a 
petroleum tank farm and several fishing 
wharves. City provided a wharf which is open to 
public use. Facilities considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections, 
reports and engineering and design were 
accomplished by hired labor at a cost of $13,171. 
Repairs to the north breakwater made by hired 
labor in May and June 1975 cost $154,571. Preparation 
of an Environmental Impact Statement 
was continued at a cost of $3,253. 
Condition at end of fiscal year. Existing 
project was completed in 1936, except for 
inactive portion of 1958 modification. Construction 
of north breakwater and removal of outer 
portion of north pier were commenced in April 
and completed in December 1934. Dredging 
entrance channels, outer turning basin, and 
interior basins to existing project depth, was 
30-14

CHICAGO, ILL., DISTRICT 
commenced in July and completed in December 
1934. Construction of south breakwater was 
commenced in July and completed in October 
1936. Breakwaters and north stub pier are in 
good condition. Original south pier, completed 
in 1893, was entirely removed in 1932 by private 
interests under permit granted October 25,1930, 
by Secretary of War and replaced with coal 
wharf. A south rubblemound breakwater about 
500 feet long was constructed in 1934 by private 
interests as an extension of their coal wharf in 
accordance with local cooperation requirements 
of House Document 168, 72nd Congress, 1st 
session. 
Total cost of existing project to June 30, 1975 
was $1,516,270 of which $810,709 was for new 
work ($207,714 regular funds and $602,995 
public works funds), and $705,561 regular funds 
for maintenance. 
21. RACINE HARBOR, WIS. 
Location. On west shore of Lake Michigan 
about 26 miles south of Milwaukee and about 64 
miles north of Chicago. (See Lake Survey Chart 
745.) 
Previous projects. See page 1389 of Annual 
Report for 1962. 
Existing project. See table 30-C. 
For detailed description see page 1235, Annual 
Report for 1963. New work for project as 
completed cost $777,775, exclusive of amounts 
expended on previous projects and exclusive of 
inner 300 linear feet of pile pier and 450 linear 
feet of rubblemound, originally part of south 
breakwater but no longer considered necessary. 
(See table 30-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Five wharves used for 
handling coal, limestone, petroleum products, 
and fish. City provided a public wharf. 
Operations and results during fiscal year. 
New Work: Rehabilitation: Rehabilitation of the 
breakwaters was completed with fiscal year 
costs of $53,125. 
Maintenance: Condition surveys, inspections, 
miscellaneous reports and engineering and 
design were performed by hired labor at a cost of 
$12,271. Repair of the north and south breakwaters 
was made by hired labor at a cost of 
$352,979. Fiscal year costs for a contract 
awarded 28 June 1974 for construction of a confined 
disposal facility at Kenosha Harbor were 
$1,994,000. Supervision and inspection associated 
with the contract were accomplished at a 
cost of $53,240. Miscellaneous engineering and 
design and preparation of an Environmental 
Impact Statement in connection with the diked 
disposal program were accomplished at a cost of 
$8137. 
Condition at end of fiscal year. Existing 
project substantially completed in 1946. Construction 
of north breakwater and shore connection 
was completed in November 1918. Removal 
of old north pier was completed in 1913. 
Construction of south breakwater and shore 
connection and removal of old south pier were 
commenced in June 1916 and completed in 
December 1924. Removal of outer shoals, 
widening and deepening channel through outer 
basin to existing project depth and width, and 
dredging river channel began in July and 
completed in November 1946. Concrete 
superstructure on portions of north breakwater 
and shore connections and timber substructures 
of portions of north and south breakwaters and 
south'stub pier are disintegrating and are being 
repaired. Costs of existing project were $777,775 
for new work, $3,998,927 for maintenance and 
$1,253,645 for rehabilitation, a total of 
$6,030,347. 
22. SHEBOYGAN HARBOR, WIS. 
Location: On west shore of Lake Michigan 
about 26 miles south of Manitowoc and about 55 
miles north of Milwaukee. (See Lake Survey 
Chart 735.) 
Previous projects. See page 1381 of Annual 
Report for 1962. 
Existing project. See table 30-C. 
For detailed description see page 1230, Annual 
Report for 1963. New work for project as 
completed cost $648,271, exclusive of amounts 
expended on previous projects. (See table 30-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves for handling 
coal, petroleum products and miscellaneous 
commodities. City provided a public wharf. 
Facilities considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections 
and reports, and engineering and design studies 
performed by hired labor were made at a cost of 
$11,971. Repairs to the north breakwater and 
south pier, were accomplished by hired labor 
during April and May 1975 at a cost of $158,257. 
Preparation of an Environmental Impact Statement 
was made at a cost of $2,108. Under the 
diked disposal program, engineering and design 
and preparation of an Environmental Impact 
Statement were accomplished at a cost of 
$128,459. 
30-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Condition at end of fiscal year. Existing 
project was completed in December 1956. South 
pier was completed in 1904. Construction of 
north breakwater was commenced in October 
1913 and completed in October 1915. Dredging 
turning basin was commenced in October 1928 
and completed in September 1931. Dredging 
entrance channel to existing project depth was 
commenced in June and completed in July 1938. 
Work on 1954 modification was completed in 
December 1956. Piers and breakwaters are in 
generally good condition. Inner 260 feet of south 
pier replaced with a revetment by private 
interests under permit granted July 16, 1931, by 
Secretary of War. Pier is therefore maintained 
only for a length of about 2,490 feet. Sheboygan 
River is navigable about 2.4 miles above its 
mouth for craft drawing not more than 2 feet. 
Costs of existing project were $648,271 for new 
work, $1,881,296 for maintenance and $609,028 
for rehabilitation, and a total of $3,138,595. 
23. STURGEON BAY AND LAKE 
MICHIGAN SHIP CANAL, WIS. 
Location: On west shore of Lake Michigan 
about 52 miles northeast of Green Bay and 
about 128 miles north of Milwaukee. (See Lake 
Survey Chart 728.) 
Previous projects. See page 1373 of Annual 
Report for 1962. 
Existing project. See table 30-C. 
For detailed description, see page 1223, 
Annual Report for 1963. See table 30-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. As the canal and connecting 
channel is a through waterway, only 
terminal facilities are in city of Sturgeon Bay, 4 
miles from west end of revetted portion of canal. 
These facilities consist of two wharves for 
handling coal, petroleum products and miscellaneous 
commodities and four shipbuilding 
yards. City of Sturgeon Bay provided a public 
wharf. There is also a large inactive stone wharf 
about 5 miles northwesterly from city of 
Sturgeon Bay. Two major shipyards are located 
in Sturgeon Bay where repair facilities are 
available including dry docks, marine railways 
and hoists. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Inspections, miscellaneous 
reports and engineering and design were 
performed by hired labor at a cost of $29,623. 
Repair of portions of the south breakwater and 
south canal revetment was accomplished by 
hired labor from September to November 1974 at 
a cost of $324,716. Under the diked disposal program, 
engineering and design and preparation 
of an Environmental Impact Statement were 
accomplished at a cost of $100,503. 
Condition at end of fiscal year. Existing 
project was completed in 1946. Breakwaters 
were completed in 1880, and canal revetments in 
1903. Dredging and rock removal at east 
entrance to canal and dredging in west section 
of canal, to existing project depth, were commenced 
in May and completed in September 
1940. Deepening and widening middle section of 
canal to existing project depth and width was 
commenced in May and completed in August 
1942. Dredging turning basin was commenced 
in June and completed in July 1946. 
Breakwaters are in good condition. North 
revetment and sections of south revetment have 
been rehabilitated and are in good condition. 
Remainder of south revetment is in fair to poor 
condition and requires repair. Costs to June 30, 
1975 for existing project were $736,303 for new 
work, $4,347,835 for Maintenance, and $884,899 
for rehabilitation, a total of $5,969,037. In addition, 
$235,940 was expended between April 25, 
1893, and June 30, 1917, on operating and care of 
works of improvement under provision of permanent 
indefinite appropriations for such 
purposes. 
24. TWO RIVERS HARBOR, WIS. 
Location. On west shore of Lake Michigan 
about 82 miles north of Milwaukee and about 
101 miles from Green Bay via Sturgeon Bay 
Canal. (See Lake Survey Chart 73.) 
Previous projects. See page 1377, Annual 
Report for 1962. 
Existing project. See table 30-C. 
For detailed description see page 1226 of 
Annual Report for 1963. Completed project cost 
$147,463 exclusive of the amount expended on 
previous projects. The 1935 River and Harbor 
Act portion of project is considered inactive. 
Estimated cost of this portion (1954) is $14,000. 
(See table 30-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A coal wharf and several 
fishing wharves. City provided a wharf for 
receipt of petroleum products and public use. 
Facilities considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections 
and reports were performed by hired labor at a 
cost of $21,593. Repairs to portions of the north 
and south piers were made during November 
1974 and April 1975 by hired labor at a cost of 
$133,407. Fiscal year costs for a contract 
awarded 26 June 1974 for construction of a con- 
30-16

CHICAGO, ILL., DISTRICT 
fined disposal facility at Manitowoc Harbor 
were $551,501. Supervision and inspection associated 
with the contract were accomplished at a 
cost of $11,849. Miscellaneous engineering and 
design and preparation of an Environmental 
Impact Statement in connection with the diked 
disposal program were accomplished at a cost of 
$1350. 
Condition at end of fiscal year. Existing 
project is complete except for inactive portion of 
project which consists of dredging a 10-foot 
width along each side of lakeward portion of 
entrance channel between the piers. This 
dredging was omitted to avoid removal of 
necessary riprap along entrance piers. Present 
width of channel is considered adequate for 
present and reasonably prospective commerce. 
South pier was completed in 1883 and is in 
generally good condition. North pier was 
completed in 1908. North revetment, completed 
in 1917, was rebuilt May to August 1962. 
Dredging entrance channel and inner basin to 
existing project depth was commenced in March 
and substantially completed in May 1937. East 
and West Twin Rivers are navigable for about 3 
and 7 miles, respectively, from the harbor piers 
for craft drawing not more than 4 feet. Costs to 
June 30, 1975, for existing project were $147,463 
for new work and $2,773,963 for maintenance, a 
total of $2,921,426. In addition, $58,057 were 
costed for minor rehabilitation. 
25. WAUKEGAN HARBOR, ILL. 
Location. On west shore of Lake Michigan 
about 51 miles south of Milwaukee and about 38 
miles north of Chicago. (See Lake Survey Chart 
74.) 
Previous projects. See page 1392, Annual 
Report for 1962. 
Existing project. See table 30-C. 
For completed modifications see page 1239, 
Annual Report for 1963. The 1970 modification 
provides for deepening the existing entrance 
channel in the outer harbor to 25 feet and 
extending it to that depth in Lake Michigan, at 
widths varying from 380 feet to 500 feet; 
deepening the channel between piers to a depth 
of 23 feet at a width of 180 feet; and deepening 
the inner basin to 23 feet and extending its 
limits approximately 275 feet northward. Cost 
for new work is $604,793 Federal and $88,000 
non-Federal, exclusive of amounts expended on 
previous project. Work authorized by the 1970 
modification was placed in the inactive 
category in December 1972, costs of $2,000,000 
(July 1972) Federal and $1,250,000 (July 1972) 
non-Federal are excluded from cost for new 
work. (See table 30-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
completed modifications. 
Terminal facilities. Four commercial docks 
receive coal, cement and gypsum. In addition, 
there are three publicly owned docks, one owned 
by city and used for fishing, and the other two 
owned by the Waukegan Port District. There is 
one boat yard for recreational craft. City dock is 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys, inspections 
and miscellaneous reports, and engineering and 
design were made by hired labor at a cost of 
$7,860. Repairs to the north breakwater were 
made by hired labor in July 1974 at a cost of 
$11,288. Maintenance dredging by contract was 
performed at a cost of $122,482. Preparation of 
an Environmental Impact Statement was made 
at a cost of $7,335. Under the diked disposal program 
engineering and design and preparation 
of an Environmental Impact Statement were 
made by hired labor at a cost of $5,375. 
Condition at end of fiscal year. Existing 
project is complete except for the 1970 modification 
which is inactive. Anchorage area in 
southwest corner of inner basin (1945 modification) 
was completed in 1966. North pier, completed 
in 1904, is in good condition. South pier, 
completed in 1903, is in good condition. The 
outer 600 feet of breakwater, completed in 1904, 
and the shorearm extension, completed in 1931, 
are in generally good condition except for outer 
100 feet which are in poor condition. Costs to 
June 30, 1975 for existing project were $604,793 
for new work and $2,387,994 for maintenance, a 
total of $2,992.787. 
26. RECONNAISSANCE AND 
CONDITION SURVEYS 
See table 30-I. 
27. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See table 30-J. 
28. NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 
(PRE AUTHORIZATION) 
Studies conducted during fiscal year cost 
$13,442 for Green Bay Harbor, Wis. and $2,694 
for Port Washington Harbor, Wis. 
Alteration of Bridges 
30-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
29. OTHER AUTHORIZED BRIDGE 
ALTERATION 
See table 30-K. 
Beach Erosion Control 
30. LAKE BLUFF, ILL. 
Location. Along western shore of Lake 
Michigan within Lake County and 34 miles 
north of Chicago. (See U.S. Lake Survey Chart 
75.) 
Existing project. Provides for Federal participation 
to the extent of seventy percent of the 
first cost of construction of two new steel sheet 
pile groins and a sand fill beach at Lake Park 
within the village limits of Lake Bluff. Project 
was authorized by the River and Harbor Act of 
September 3, 1954 (H. D. 28/83/1). Estimated 
cost (Feb. 1974) is $157,900 Federal and $67,700 
non-Federal. 
Local cooperation. Fully complied with. 
The Lake Bluff Park District furnished the 
assurances of local cooperation in the agreement 
with the government, signed by the Lake 
Bluff Park District on 27 December 1972. 
Operations and results during fiscal year. 
New work. Work was advertised and the contract 
was awarded. The accrued expenditures 
for the project to June 30, 1975 were $294,889 
Federal funds. 
Condition at end of fiscal year. Construction 
on project is underway. 
31. LAKE FOREST, ILL. 
Location. Along western shore of Lake 
Michigan within Lake County and to the north 
of Chicago. (See Lake Survey Chart 75.) 
Existing project. Provides for Federal participation 
to extent of seventy percent of first 
cost of construction for providing protection to 
the shore in the center of Forest Park by 
replacement of one deteriorated wooden groin, 
the extension of two existing steel sheet piling 
impermeable groins and the construction of one 
new steel sheet piling impermeable groin. 
Project was authorized by 1954 River and 
Harbor Act. Cost of completed work as follows: 
$65,611 Federal and $28,119 non-Federal, a total 
of $93,730. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
City of Lake Forest was reimbursed for the 
Federal share of the cost of improvement. Total 
costs were $61,986. 
Condition at end of fiscal year. Existing 
project was completed on 14 November 1973. 
32. AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
See table 30-L. 
Flood Control 
33. CHICAGO RIVER, ILL. (NORTH 
BRANCH) 
Location. North Branch, Chicago River is 
located in Cook County in northwestern part of 
Chicago, Niles and Morton Grove, Illinois. 
Existing project. Provides for clearing the 
channel of the North Branch of the Chicago 
River, Illinois of fallen trees, roots, and other 
debris and objects which contribute to flooding, 
unsightliness and pollution of the river for a 
distance of approximately 12 miles long 
between the fork formed by the west Fork-North 
Branch intersection just south of Golf Road, in 
Morton Grove, Illinois, and the intersection of 
the North Branch and North Shore Channel 
just south of Foster Avenue in Chicago, Illinois. 
The project was authorized by the River and 
Harbor Act of December 31, 1970 (Sec. 116) and 
amended by River & Harbor Act of 1974 
providing for maintenance of the project. 
Local cooperation. The 1970 Act provides that 
local interests furnished without cost to the 
United States all lands, easements, rights-ofway, 
and spoil-disposal areas necessary for 
construction of the project; hold and save the 
United States free from damages due to the 
construction works; maintain and operate all 
the works after completion without cost to the 
United States; and, agree to bear all costs in 
excess of $200,000 for completing the work. 
Assurance of local cooperation for the 1970 
modification was approved on 31 July 1972. The 
1974 Act amends the 1970 Act so that the United 
States will maintain the channel free of trees, 
roots, debris and objects at a cost not to exceed 
$150,000 per year with non-Federal interests 
paying 25 per centum of the cost of 
maintenance. 
Operations and result during fiscal year. New 
work: No work was done. 
Maintenance: Engineering and design and 
real estate costs associated with the 1974 Act 
were $48,500. 
Condition at end of fiscal year. The project 
was completed 26 May 1973. Total costs of 
existing project to June 30, 1975 were $280,384, 
of which $231,884 was for new work ($191,884 
regular funds and $40,000 public works funds), 
and $48,500 regular funds for maintenance. 
34. FARM CREEK, ILL. 
Location. Farm Creek watershed in Tazewell 
30-18

CHICAGO, ILL., DISTRICT 
County, Ill., is 60 square miles in extent. Stream 
empties into Illinois Waterway at mile 162 
above mouth. 
Existing project. Two compacted-earth flooddetention 
dams, Fondulac Dam on Fondulac 
Creek, Tazewell County, Ill., about 1.5 miles 
easterly of East Peoria, Ill., and Farmdale Dam 
on Farm Creek, Tazewell County, Ill., about 2.5 
miles easterly of East Peoria, Ill., and improvements 
to Farm Creek, Cole Creek, and 
Kerfoot Creek Channels in East Peoria, Ill. 
Fondulac Dam has a maximum height of 67 feet 
above riverbed and a reservoir capacity of 3,780 
acre-feet. Farmdale Dam has a maximum 
height of 80 feet above riverbed and a reservoir 
capacity of 15,500 acre-feet. Linear feet of 
channel improvements are: Farm Creek, 12,000 
feet; Cole Creek, 1,875 feet; Kerfoot Creek, 900 
feet. Project provides complete protection to 
residential, business, and highly developed 
industrial areas to East Peoria, Ill., against 
design flows in Farm, Coke, Kerfoot, and 
Dempsey Creeks of expected frequency once in 
about 100 years. 
Total costs of existing project to June 30, 1975 
were $10,724,603, of which $10,020,833 was for 
new work ($9,859,020 regular funds and 
$161,813 contributed funds), and $703,770 regular 
funds for maintenance. Existing project was 
authorized by 1944 Flood Control Act. (See H.D. 
802, 78th Cong., 2nd, sess.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Maintenance of remedial works 
at Fondulac and Farmdale Dams was 
performed by hired labor at a cost of $36,994. 
Condition surveys and engineering and design 
studies were performed by hired labor at a cost 
of $7,506. 
Condition at end of fiscal year. Existing 
project is complete. 
35. LITTLE CALUMET RIVER, ILL. 
Location: Rises in western LaPorte County, 
Indiana, near Michigan City and flows generally 
westerly through Porter and Lake County, 
Indiana, into Cook County, Illinois, to its 
junction with the Calumet-Sag Channel in 
Calumet Park, Illinois. Approximately 12 miles 
of the Little Calumet River lies within the State 
of Illinois. 
Existing project. Provides for clearing the 
channel of the Little Calumet River, Illinois, 
from its confluence with the Calumet-Sag Channel 
eastward to the Indiana State Line, of fallen 
trees, roots, silt, and other debris and objects 
which contribute to flooding, unsightliness, and 
pollution of the river. Project was authorized by 
Water Resources Development Act of 1974, Section 
66, approved 7 March 1974. 
Estimated Federal Cost (July 1975) is 
$330,000. There are no non-Federal costs. 
Local cooperation: Local interests are required 
to: provide without cost to the Government 
such lands, temporary disposal areas, 
right of entry documents, easements, and 
rights-of-way necessary for completion of the 
project; hold and save the Government free from 
damages that may result due to construction 
and maintenance of the project, except for 
damages due to the fault or negligence of the 
United States or its contractors; and perform the 
necessary maintenance of the project in accordance 
with regulations prescribed by the 
Secretary of the Army in accordance with the 
intent and scope of the project. 
Operations and results during fiscal year. 
None. 
Condition at end of fiscal year. Engineering 
and design was performed by hired labor at a 
cost of $35,062. 
36. MOUTH OF SANGAMON RIVER, 
ILL. 
Location. On east bank of Illinois River, 98 
miles above mouth and 9.4 miles above Beardstown 
Highway Bridge. Project extends for 
several miles upstream from mouth of river. 
This portion of Sangamon River forms boundary 
line between Mason County on the 
northwest and Cass County on the southwest. 
Existing project. Project authorized by 1936 
Flood Control Act (H. Doc. 186, 72nd Congress, 
1st session) provided for excavation of a new 
outlet channel for Sangamon River about 6.7 
miles long and 200 feet wide extending from 
Hager Slouth on Illinois River to mile 6.7 above 
mouth of Sangamon River, and a diversion 
channel and remedial works necessary for 
maintenance of a highwater table in adjacent 
wild game reserve. Further remedial work was 
authorized by Flood Control Act of 1962 (H. Doc. 
472, 87th Cong., 2d sess.). 
Completed costs for work authorized by 1936 
Flood Control Act are $764,490 Federal costs; 
$15,122 contributed funds; lands and damages, 
non-Federal costs $20,000; total $799,612. Estimated 
Federal cost (July 1973) for work authorized 
by the 1962 Flood Control Act is $284,000. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Planning for remedial work was 
authorized by 1962 Act was accomplished at a 
cost of $24,582. 
30-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Maintenance: Preparation of an Environmental 
Impact Statement was accomplished at 
a cost of $8,500. 
Condition at end of fiscal year. Work authorized 
by 1936 Flood Control Act is complete. 
Remedial work authorized by 1962 Flood Control 
Act remains to be completed. Costs of 
existing project to June 30, 1975 were $66,769 for 
new work and $229,120 for maintenance, a total 
of $295,889. 
37. WILLIAM L. SPRINGER LAKE, ILL. 
Location. On Sangamon River, a tributary of 
Illinois River, Damsite is about 1.25 miles 
upstream from Decatur, Illinois. 
Existing project. The project provides for a 
multiple-purpose dam and reservoir at the 
Springer site, about 1.25 miles above Decatur, 
Ill., a sub-impoundment near the mouth of 
Friend's Creek about 7.5 miles above the 
Springer site and a dual use recreation channel 
and floodway from Decatur downstream to the 
mouth of Salt Creek. The proposed Springer 
dam will be compacted earth fill construction 
about 3,650 feet long, 55 feet high and employ 
four tainter gates for impounded water releases. 
The reservoir will have a storage capacity of 
100,600 acre-feet, with allocation of 83,600 for 
flood control, 7,000 for water supply and 10,000 
for sedimentation. The proposed dam for the 
Friend's Creek Sub-impoundment will be a 
compacted earth fill construction about 2,400 
feet long and 54 feet high and employ two 
tainter gates for impounded water releases. The 
reservoir will have a storage capacity of 56,900 
acre-feet, with allocation of 28,800 for flood 
control, 17,100 for water supply, 9,000 for 
recreation and 2,000 for sedimentation. Estimated 
cost (1974) is $110,000,000 and includes 
a future non-Federal reimbursement of$18,430,- 
000. Project was authorized by Flood Control 
Act of 1962 (H. Doc. 472, 87th Congress, 2nd 
Session). 
Local cooperation. 
a. Requirements: Local interests are required 
to: (1) agree to pay the cost allocated to water 
supply, such costs being presently estimated at 
15.02 percent of the total costs, or $16,520,000, in 
accordance with provisions of the Water Supply 
Act of 1958, as amended; (2) agree to pay 
annually the proportionate costs of operation, 
maintenance and periodic replacement of moving 
parts allocated to water supply such costs 
being presently estimated at 13.47 percent of the 
total, of $120,000, subject to any modifications 
to be provided in the water supply contract to be 
executed between the State of Illinois and the 
United States; (3) agree to pay one half of the 
separable costs assigned to recreational stream 
flow regulation, such costs being presently 
estimated at $1,250,000, to be paid in any 
manner described in (1) above; (4) agree to pay 
annually the proportionate costs of operation, 
maintenance, and periodic replacement of 
moving parts allocated to recreational stream 
flow regulation, in accordance with the 
provisions of Public Law 89-72; (5) agree to pay 
one half of the separable first costs assigned to 
recreation in the greenbelt including the project 
recreational developments outside the 
greenbelt, such costs being presently estimated 
at $540,000; (6) agree to operate and maintain 
and insure public access at specified locations 
to: the recreational facilities in the greenbelt, 
including the project recreational developments 
outside the greenbelt and the recreational areas 
adjacent to the multiple-purpose reservoir 
system leased to non-Federal interests all in 
accordance with regulations approved by the 
Secretary of the Army; (7) maintain all roads 
and bridges in the reservoir areas and in the 
greenbelt in accordance with regulations 
prescribed by the Secretary of the Army (8) hold 
and save the United States free from all water 
rights claims resulting from construction and 
operation of the project; (9) provide for adequate 
water pollution control at all sources within the 
watershed in accord with the applicable State- 
Federal Water Quality Standards and 
regulations and procedures of the State to 
prevent pollution of the impounded waters of the 
multiple-purpose reservoir system, and of the 
greenbelt area of the Sangamon River; to insure 
that the reservoir, the recreation areas and the 
greenbelt area enjoy a high quality environment 
for the benefit of all; (10) administer 
project lands and waters within the greenbelt 
area, including the recreational development 
outside the greenbelt, to enhance recreation and 
fish and wildlife and to prevent encroachment 
which would reduce the hydraulic capacity of 
the channel and the greenbelt; (11) provide 
controls against the withdrawal of stream flow 
dedicated to recreational stream flow regulation; 
(12) provide for operation of the existing 
non-Federal dam and reservoir on the 
Sangamon River at Lake Decatur in accordance 
with regulations developed by the State and 
Federal interests and approved by the Secretary 
of the Army, and require future dams within the 
watershed to be operated in a manner which will 
not conflict with the operation of the project; 
and (13) prior to construction; provide 
assurances that waters from the project will not 
be served for the potable consumption of the 
public by the State or by other entities subject to 
its control unless the nitrate concentration of 
such waters is undern or is reduced to fall under, 
30-20

CHICAGO, ILL., DISTRICT 
the maximum allowable concentration (currently 
45 milligrams per liter) specified in the 
"Public Health Service Drinking Water Standards." 
b. Status: The State of Illinois is the local 
sponsor for the project. Formal assurances were 
received on 26 May 1971. A supplement to the 
assurances to incorporate the provisions of the 
Uniform Relocation and Assistance Real 
Property Acquisition Policies Act of 1970 (P.L. 
91-646) was signed by the State on 15 December 
1971. 
Operations and results during the fiscal year. 
Planning in connection with preperation of the 
General Design Memorandum, the Hydraulics 
and Hydrology Design Memorandum and revised 
Environmental Impact Statement was 
accomplished at a cost of $199,675. Real Estate 
acquisition and management cost $44,550. 
Environmental Studies were continued with 
contract costs of $86,765 and hired labor costs of 
$9,320. 
Condition at end of fiscal year. Construction 
has not been started. The project was placed in 
an inactive status in June 1975 due to a lack of 
economic justification. Two tracts of land have 
been acquired. Civil suit against the project is 
pending. 
38. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Annual inspections are made with local interests 
of all projects improved or extensively 
repaired at Federal expense in order to determine 
compliance of local interests with assurances 
given to the United States regarding 
maintenance of the projects, to determine physical 
condition of the levees appurtenances and 
to receive necessary information for use in flood 
emergencies. Inspection of 27 levees was made 
in the Chicago District involving approximately 
172 miles of embankment. Fiscal year 
cost was $35,000. Total cost to June 30, 1975 was 
$419,475. (See table 30-M on inspection of 
completed flood control projects.) 
39. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 30-N. 
40. FLOOD CONTROL UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, 
flood fighting and rescue work (Public Law 99, 
84th Cong. and antecendent legislation) 
(See table 30-0 on emergency flood control 
activities-repair.) 
Snagging and clearing of navigable streams 
and tributaries in interest of flood control (Sec. 
208 of 1954 Flood Control Act, Public Law 780, 
83rd Congress) 
None. 
General Investigations 
41. SURVEYS 
Fiscal year costs were $84,171 for navigation 
studies ($1,066 by North Central Division), 
$394,857 for flood control studies, $240,692 for 
beach erosion studies and $691,329 for special 
studies, comprehensive basin studies and inventory 
of dams $690,714 by North Central 
Division). 
42. COLLECTION AND STUDY OF 
BASIC DATA 
North Central Division fiscal year cost was 
$86,739 for international water studies. 
Fiscal year costs were $299,669 for flood plain 
information studies ($55,290 for North Central 
Division). Work was done on the following studies: 
Berlin, Wisconsin; Deep River, Indiana; 
Joliet, Illinois; Lake County, Hart Ditch, Indiana; 
Lincoln Logan Co., Illinois; Marinette, 
Wisconsin & Menominee, Michigan; West 
Branch, DuPage River, Illinois; Porter County, 
Indiana; and Outagamie & Winnebago 
Counties, Wisconsin. There was work on 
Technical and Flood Plain Management 
Services. (See table 30-P on Completed Flood 
Plain Studies.) 
43. RESEARCH AND DEVELOPMENT 
Cost for hydrologic studies during the fiscal 
year was $2,030. 
30-21

TABLE 30-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Algoma Harbor, 
Wis. 
2. Big Suamico 
River, Wis. 
3. Burns Waterway 
Harbor, Ind. 
[Federal Funds] 
[Contributed 
Funds 
4. Calumet Harbor 
and River, Ill. 
and Ind. 
[Federal Funds] 
[Contributed 
Funds] 
5. Chicago Harbor, 
Ill. 
6. Chicago River, 
Ill. 
7. Fox River, 
Wis. 
8. Green Bay 
Harbor, Wis. 
9. Illinois Waterway, 
Ill. & Ind. 
FY 72 
FY 75 
Funding 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
FY 73 FY 74 
242 
242 
-- 1,000 
431 
3,636 
11,509 
11,509 
17,158 
148,453 
1,003,000 
407,283 
1,733 
4,769 
4,000 
418,620 
8,618 
8,618 
-10,000 
58,109 
141,267 
990,129 
300 
300 
10,071 
1,434 
12,000 
1,102,486 
-441,400 
141,109 
455,700 
170,071 
25,000 
38,000 
30,491 
350,700 
99,405 
612,500 
607,785 
1,272,100 
1,264,670 
256,200 
138,011 
5,653,800 
5,498,138 
5,568,300 
4,901,182 
13,000 
14,142 
29,100 
33,534 
654,000 
592,858 
1,500,000 
1,434,193 
702,000 
375,872 
1,191,167 
540,661 
Total to 
FY 75 June 30, 1975 
292,01047 
- 292,01047 
53,000 381,592 
53,000 381,592 
4,170 
3,331 
185,000 
185,000 
130,000 
28,700 
335,700 
449,990 
66,649 
20,609 
25,767 
25,549 
204,553 
841,000 
905,781 
182,465 
348,207 
1,017,598 
1,532,768 
981,353 
19,900 
13,708 
20,900 
94,583 
1,233,800 
1,202,320 
1,457,600 
1,453,478 
578,300 
2,405,358 
20,243 
20,243 
93,491 
93,491 
13,616,000 
3,616,000 
205,127 
205,127 
15,990 
15,990 
22,565,5671 
22,464,2591 
11,039,5742 
11,029,5742 
689,0013 
689,0013 
836,667 
836,649 
4,788,8274 
4,788,8274 
3,879,786 
3,870,786 
1,326,600 
1,326,000 
1,500,5655 
1,500,5655 
3,598,4656 
3,598,4656 
3,753,3347 
3,753,3347 
19,144,3738 
19,108,5908 
9,731,3959 11 
9,731,39591 
5,774,92010 
5,768,91110 
120,998,75112 
120,960,04712 
5,688,600 5,279,300 8,665,800 93,965,33113 
6,978,030 6,251,607 9,412,487 94,047,26713 
30-22 
16,667

CHICAGO, ILL., DISTRICT 
TABLE 30-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section FY 75 Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
10. Indiana Harbor, 
Ind. 
11. Kenosha Harbor, 
Wis. 
12. Kewaunee Harbor, 
Wis. 
13. Manitowac Harbor, 
Wis. 
14. Menominee Harbor, 
& River, 
Mich. & Wis. 
[Contributed 
Funds] 
15. Michigan City 
Harbor, Ind. 
[Contributed 
Funds] 
16. Milwaukee Harbor, 
Wis. 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
257,000 
221,485 
47,300 
30,131 
-9,725 
77,453 
37,200 
21,406 
-- 66,665 
1,756 
68,000 
13,865 
35,600 
12,206 
134,100 
121,398 
9,725 
360,253 
80,200 
117,331 
82,600 
82,339 
-10,000 
9,219 
-- 4,200 
43,837 
-5,900 
10,667 
91,000 
94,317 
22,945 
138,036 
1,699,000 5,024,376 
497,198 334,365 
- -40,090 
- - 414,625 
- - 414,625 
- - 4,897,1481416 
- - 4,897,1481416 
19,533 30,300 4,506,91115 
19,612 30,300 4,506,91115 
- 846,9691719 
- - 846,9691719 
915,800 1,948,800 4,089,67718 
344,674 2,536,732 4,088,58318 
- - 1,270,275 
- - 1,270,275 
- - 752,33320 
- - 752,33320 
95,911 137,000 1,609,35221 
94,848 131,493 1,596,82321 
-- 617,300 
- - 617,300 
S- 881,16422 
- - 881,16422 
2,027,500 -204,000 3,473,02523 
302,694 1,525,917 3,471,79623 
- - 533,47624 
- - 533,47624 
16,761 124,200 1,288,39825 
19,813 119,506 1,279,92925 
- - 1,351,852 
- - 1,351,852 
- - 36,762 
- - 36,762 
- - 1,543,64626 
- - 1,543,64626 
69,674 4,500 2,743,012 
50,537 35,533 2,743,012 
- - 1,618,670 
- - 1,618,670 
- - 30,800 
- - 30,800 
S- 8,231,02427 
- - 8,231,02427 
347,361 -- 28,600 12,202,12428 
2,448,493 3,749,111 12,189,00128 
- - 1,891,810 
- - 1,891,810 
30-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 30-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
17. New Buffalo 
Harbor, Mich. 
[Federal Funds] 
[Contributed 
Funds] 
18. Northport 
Harbor, Wis. 
19. Oconto 
Harbor, Wis. 
20. Port Washington 
Harbor, Wis. 
21. Racine Harbor, 
Wis. 
22. Sheboygan Harbor, 
Wis. 
23. Sturgeon Bay 
& Lake Michigan 
Ship Canal 
Wis. 
24. Two Rivers 
Harbor, Wis. 
25. Waukegan 
Harbor, Ill. 
Total to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
FY 75 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
8,879 
5,201 
5,201 
125,400 
39,539 
35,400 
17,213 
506,500 
434,986 
35,500 
13,966 
6,700 
24,887 
107,800 
91,188 
85,400 
58,032 
27,047 
334,000 
2,427 
2,427 
-- 50,000 
33,604 
27,606 
30,520 
17,145 
296,169 
30,000 
45,606 
201,367 
202,592 
75,955 
89,344 
128,194 
106,989 
6,716 
289,102 
189,000 
5,093 
238,009 
234,890 
59,621 
62,097 
872,847 
386,683 
53,125 
148,592 
150,792 
198,952 
200,732 
979,116 
112,747 
204,805 
126,396 
500,471 
946,842 
40,000 
39,968 
416,000 
419,119 
170,000 
170,995 
1,919,300 
2,420,627 
310,500 
300,795 
467,300 
454,842 
-150,300 
719,700 
30,100 
154,340 
30-24 
1,038,716 
1,038,716 
1,207,000 
951,935 
40,000 
39,968 
130,75429 
130,75429 
840,98130 
840,98130 
999,20431 
999,20431 
720,68932 
720,68432 
1,205,01533 
1,205,01533 
4,081,60134 
4,078,46434 
1,253,645 
1,253,645 
1,136,08835 
1,136,08835 
1,983,18436 
1,968,42736 
609,028 
609,028 
1,059,72237 
1,059,72237 
4,587,04438 
4,567,56538 
884,899 
884,899 
360,32039 
360,32039 
2,807,38340 
2,807,07640 
58,057 
58,057 
823,02641 
823,02641 
2,408,30942 
2,403,70542

CHICAGO, ILL., DISTRICT 
TABLE 30-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section FY 75 Total to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
30. Lake Bluff, Ill. New Work: 
Approp. - - 157,889 137,000 294,889 
Cost - - 34,354 260,535 294,889 
31. Lake Forest, Ill. New Work: 
Approp. - 66,000 -389 - 65,611 
Cost - 3,625 61,986 - 65,611 
33. Chicago River, Ill. New Work: 
North Branch Approp. 198,600 - -6,716 - 191,884 
[Federal Fund] Cost 25,055 166,829 - - 191,884 
[Contributed New Work: 
Funds] Approp. - 40,000 - - 40,000 
Cost - 37,801 2,199 - 40,000 
Maint.: 
Approp. - - - 50,000 50,000 
Cost - - - 48,500 48,500 
34. Farm Creek, New Work: 
Ill. Approp. - - - - 9,859,02043 
Cost - - - - 9,859,02043 
Maint.: 
Approp. 58,900 60,900 37,600 44,500 703,921 
Cost 60,786 57,687 40,825 44,500 703,770 
35. Little Calumet New Work 
River, Ill. Approp. - - - 40,000 40,000 
Cost - - - 35,062 35,062 
36. Mouth of New Work: 
Sangamon River Approp. - - - - 873,9904445 
Ill. Cost 3,184 4,364 9,395 24,582 831,25944 45 
Maint.: 
Approp. 24,500 25,300 50,000 1,000 459,79846 
Cost 42,141 16,673 51,353 8,500 459,79846 
37. William L. New Work: 
Springer Approp. 198,600 1,000,000 250,000 300,000 4,911,310 
Lake, Ill. Cost 746,825 834,714 737,561 340,311 4,911,310 
1. Includes $855,973 for previous projects. 
2. Excludes contributed funds in settlement pursuant to 
decree [No. 54-C-1608] regarding removal of flue-dust and 
includes $45,230 for previous projects. 
3. In settlement, pursuant to decree [No. 54-C-1608] 
regarding removal of flue-dust. 
4. Includes $446,005 for previous projects. 
5. Includes $955,886 for previous projects. 
6. Includes $109,463 for previous projects. 
7. Includes $3,239,910 for previous projects. 
8. Includes $89,309 for previous projects. 
9. Includes $396,974 for previous projects. 
10. Includes $8,918 for previous projects. 
11. Excludes $100,000 contributed funds. 
12. Includes $2,569,102 for previous projects. 
13. Includes $1,028,468 for previous projects. 
14. Includes $60,668 for previous projects. 
15. Includes $2,509 for previous projects. 
16. Excludes $12,500 contributed funds. 
17. Includes $453,839 for previous projects. 
18. Includes $21,818 for previous projects. 
19. Excludes $3,000 contributed funds. 
20. Includes $149,312 for previous projects. 
21. Includes $88,364 for previous projects. 
22. Includes $400,126 for previous projects. 
23. Includes $54,288 for previous projects. 
24. Includes $312,423 for previous projects. 
25. Includes $36,194 for previous projects. 
26. Includes $287,389 for previous projects. 
27. Includes $1,293,220 for previous projects. 
28. Includes $459,305 for previous projects. 
29. Includes $84,569 for previous projects. 
30. Includes $8,161 for previous projects. 
31. Includes $188,495 for previous projects. 
32. Includes $15,123 for previous projects. 
33. Includes $427,240 for previous projects. 
34. Includes $79,537 for previous projects. 
35. Includes $487,817 for previous projects. 
36. Includes $87,131 for previous projects. 
37. Includes $323,419 for previous projects. 
38. Includes $219,730 for previous projects. 
39. Includes $212,857 for previous projects. 
40. Includes $33,113 for previous projects. 
41. Includes $218,233 on previous projects. 
42. Includes $15,711 on previous projects. 
43. Excludes $161,813 contributed funds. 
44. Excludes $15,122 contributed funds. 
45. Includes $764,490 for previous projects. 
46. Includes $230,678 for previous projects. 
47. Includes $192,744 for previous projects. 
30-25

TABLE 30-B 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
June 13, 1902 
Mar. 3, 1905 
June 25, 1910 
Sept. 22, 1922 
Aug. 30, 193512 
Aug. 30, 193512 
Mar. 2, 19453 
July 14, 1960 
Oct. 23, 1962 
Oct. 27, 1965 
July 11, 1870 
June 14, 1880 
Mar. 3, 1899 
July 25, 1912 
Mar. 2, 1919 
Mar. 3, 1931 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1907 
CALUMET HARBOR AND RIVER, ILL. AND IND. 
[See Section 4 of Text] 
Outer harbor protected by breakwaters. 
Five turning basins 
Provided for shape and dimensions of 
turning basins 
Consolidated the 2 projects for Calumet Harbor and 
Calumet River. 
Detached breakwater, dredging outer harbor to existing project 
depth and dimensions; deepen river-entrance channel and 
river to existing project depths; widen and straighten river 
channel; 5 turning basins to same depth as adjacent channel. 
Dredging areas A and B in south end of Lake Calumet and an 
entrance channel 300 feet wide to 21 feet deep. 
An approach channel to harbor 3,200 feet wide and 28 feet 
deep through shoals outside breakwater and closing 
existing gap between breakwaters. 
Depth of 29 feet in lake approach 28 feet in outer harbor; 
and 27 feet in river entrance up to E.J.&E. Ry. Bridge. 
Deepen widen, and straighten channel in Calumet River from 
E.J.&E. Ry. Bridge to and including turning basin 5, to a 
depth of 27 feet in earth and 28 feet in rock; deepen 
turning basins 1, 3 and 5 to 27 feet; enlarge turning basins 
3 and 5; a channel into Lake Calumet to 27 feet deep for 
3,000 feet and a width of 1,000 feet; and eliminate turning 
basins 2 and 4 from project. 
Modification of Act of Oct. 23, 1962. Protection for Elgin, 
Joliet and Eastern Railway Bridge over the Calumet River, 
to permit dredging to full width of the south draw to depth 
of 27 feet, and temporary protection for the center pier 
and south abutment of the New York, Chicago and St. Louis 
Railroad Bridge [Nickel Plate] to permit dredging of full 
width of south bridge draw to depth of 27 feet prior to its 
replacement. 
CHICAGO HARBOR, ILI. [See Section 5 of Text] 
Inner breakwaters and inner basin. 
Exterior breakwater. 
Present project depth in basin, and entrance to Chicago 
River. 
Shore-arm and southerly extension of exterior breakwater. 
Modification of area to be dredged in inner basin. 
Shore-arm extension of exterior breakwater transferred to 
Lincoln Park Commissioners. 
Resumption of jurisdiction over shore-arm extension 
breakwater and over certain navigable waters in Lake 
Michigan which lie in northwestern part of outer harbor. 
Deepen a lake approach channel to 29 by 800 feet wide for 
6,600 feet; and deepen a channel and maneuver area inside 
harbor entrance to 28 by 1,300 feet wide. 
CHICAGO RIVER, ILL. [See Section 6 of Text] 
For project depth of 21 feet in lieu of that fixed by act 
of June 3, 1896. 
Turning basins. 
Interpreted by Chief of Engineers, April 11, 1908 as 
adopting new work of the then existing project for 
21-foot depth. 
Annual Report, 1896 
pp. 2584 et seq., and 
H. Doc. 277, H. 54th 
Cong., 1st sess. 
H. Doc. 172, 58th Cong., 
2d sess. 
H. Doc. 349, 60th Cong., 
1st sess. 
H. Doc. 494, 72d Cong., 
2d sess. 
H. Doc. 180, 73d Cong., 
2d sess. 
H. Doc. 233, 76th Cong., 
1st sess. 
H. Doc. 149, 86th Cong., 
1st sess. 4 
H. Doc. 581, 87th Cong., 
2d sess. 5 
H. Report No. 973, 89th 
Cong., 1st sess. 
A. Ex. Doc. 114, 41st Cong. 
2d sess., and Annual Report 
1879, pp. 1562-1567 
Annual Report 1870, pp. 
1562-1567. 
Annual Report, 1897, pp. 
2790-2791. 
H. Doc. 710, 62d Cong. 
2d sess. 
H. Doc. 1303, 64th Cong., 
1st sess. 
Public 797, 71st Cong. 
Public 14, 79th Cong. 
H. Doc. 485, 87th Cong., 
2d sess. 4 
Specified in act. 
Specified in act. 
H. Doc. 95, 56th Cong., 
Ist sess. [Annual Report, 
1900, p. 3863, and Annual 
Report, 1909, p. 709]. 
30-26

CHICAGO, ILL., DISTRICT 
TABLE 30-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1919 
July 24, 1946 
Aug. 5, 1886 
Sept. 19, 1890 
June 3, 1896 
June 3, 1896 
June 13, 1902 
Mar. 2, 1907 
Mar. 3, 19259 
June 26, 19341 
July 3, 195811 
June 23, 1866 
July 13, 1892 
June 26, 1910 
Aug. 8, 1917 
Mar. 3, 1925 
Aug. 30, 193513 
Aug. 26, 1937 
Mar. 2, 1945 
Oct. 23, 1962 
Jan. 21, 1927 
July 3, 1930 
June 26, 193410 
Eliminated all work, except maintenance of main river. 
Dredging channel 9 feet deep to within 30 feet of existing 
bulkheads and river banks from North Ave. to Belmont 
Ave., thence 9 feet deep and 50 feet wide to Addison St. 
FOX RIVER, WIS. [See Section 7 of Text] 
Improvement of Fox River. 
Dredging Fond du Lad Harbor on Lake Winnebago. 
Improvement of Wolf River. 
Improvement of Stockbridge, of Calumet 
and Miller Bay, and of Brothertown 
Harbor, on Lake Winnebago. 
Increased depth in rock cuts on lower river, widen Neenah 
Channel, and a concrete retaining wall at Kaukauna. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
Sec. 108. That Federal project structure, appurtenances, and 
real property of Upper Fox River, Wis., be disposed of to 
State of Wisconsin. 
GREEN BAY HARBOR, WIS. [See Section 8 of Text] 
Outer Channel and revetment at Grassy Islands. 12 
Inner channel. 12 
Turning basin at DePere. 
Maintenance of turning basin at DePere. 
Increasing depth of inner channel and turning basin to 18 feet. 
Deepen outer channel to 22 feet with widening and 
straightening inside of Tail Point Bend, widen channel in 
Fox River through city of Green Bay to 22 feet. 
Turning basin above Chicago & North Western Ry. Bridge. 
Turning basin at mouth of East River. 
Deepen and widen 9 miles of entrance channel to 26 by 500 
feet; 3.6 miles of entrance channel to 24 by 300 
feet; and 3.2 miles of existing Fox River to 24 feet 
deep. 
ILLINOIS WATERWAY, ILL. AND IND. 
[See Section 9 of Text] 
Channel 9 feet deep and 200 feet wide from mouth of Illinois 
River to Utica 231 miles, modification of 2 U.S. locks and 
dams, removal of 2 State dams. [Act authorized 
appropriation of not to exceed $3,500,000 for carrying 
on work.] 
Channel 9 feet deep from Utica, Ill., to heads of present 
Federal projects on Chicago and Calumet Rivers, 94.6 
miles to Lake Street, and 96.3 miles to turning 
basin 5, respectively, to be secured by means of 
completed dams, locks, lateral canals, and dredging begun 
by State of Illinois in general accordance with present 
plans of state for that work. Act adopting project 
authorized appropriation of not to exceed $7,500,000 for 
carrying on work. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
H. Doc. 1294, 64th Cong., 
1st sess. 
H. Doc. 767, 78th Cong., 
2d sess. 6 7 
Annual Report, 1885, pp. 
2041-2045 [plan of a 
board approach Dec. 10, 
1884, as modified by 
Corps of Engineers, 
May 14, 1886]. 
H. Ex. Doc. 24, 51st Cong., 
1st sess. Annual Report, 
1890, p. 2390. 
No prior survey or estimates. 
No prior survey or estimates. 
No prior survey or estimates. 
H. Doc. 294, 68th Cong., 
1st sess. 8 
S. Doc. 3910, 85th Cong. 
2d sess. 
Annual Report, 1867, p. 70. 
Unpublished report 
approved Aug. 3, 1892. 
H. Doc. 222, 61st Cong., 
2d sess. 
H. Doc. 1017, 64th Cong., 
1st sess. 
H. Doc. 294, 68th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 40, 72d 
Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 73, 74th 
Cong., 2d sess. 
H. Doc. 95, 76th Cong., 
1st sess. 
H. Doc. 470, 87th Cong., 
2d sess.8 
Rivers and Harbors 
Committee Doc. 4, 69th 
Cong., 1st sess., and S. Doc. 
130, 69th Cong., 1st sess. 
S. Doc. 126, 71st Cong., 
2d sess. 
30-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 30-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
Aug. 30, 193515 
June 14, 1937 
June 20, 1938 
Oct. 23, 1943 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 17, 1953 
July 3, 1958 
Oct. 23, 1962 
Aug. 18, 1968 
June 25, 1910 
Mar. 4, 1913 
Mar. 2, 1919 
Construct modern locks and dams at La Grange and Peoria and 
a channel 9 feet deep and 300 feet wide below Lockport, 
exact location and details of design of all structures to 
be left to discretion of Chief of Engineers, and, for time 
being, that no change be made in water authorized for 
navigation of Illinois River by act of July 3, 1930. 
Also provides for 3 passing places along Sag Channel and 
authorized channel in Calumet-Sag route to turning basin 5, 
and dredging at entrance of Lake Calumet. 
Realign portion of Calumet River and abandonment of 
bypassed section of Calumet River. 
Modifies local cooperation requirements in 1935 act. 
Pay damages to levee and drainage districts due to seepage 
and other factors, not to exceed $503,500. 
Enlarge Calumet-Sag Channel to 160 feet wide and a usable 
depth of 9 feet. Dredge a barge channel 160 feet wide 
with a usable depth of 9 feet in Grand Calumet and Little 
Calumet River Branch of Indiana Harbor Canal to deep 
[lake] draft through 141st St., East Chicago, Ind. 
Construct in Little Calumet River a lock of suitable 
dimensions for large navigation. Rebuild or otherwise 
alter at Federal expense all obstructive railroad bridges 
across Calumet-Sag channel, Little Calumet River, Calumet 
River, Grand Calumet River, and Indiana Harbor Canal, so as 
to provide suitable clearance, except that no Federal funds 
shall be expended for removal or alteration of Illinois 
Central R.R. bridge at mile 11.20 of Little Calumet River. 
Substitute following work for that authorized by act of 
Mar. 2, 1945; replace emergency dam in Chicago Sanitary and 
Ship Canal; enlargement of that canal thence to Sag Junction 
and of Calumet-Sag Channel to afford channels 225 feet wide 
with usable depth of 9 feet; construct along general route 
depth of 9 feet to 225 feet wide between Little Calumet 
River and junction with Indiana Harbor Canal and 160 feet 
wide thence to Clark St., Gary, Ind. with a turning basin 
at Clark St., enlarge Indiana Harbor Canal to 225 feet wide 
and usable depth of 9 feet between Grand Calumet River and 
vicinity of 141st St., inclusive; remove Blue Island lock 
and construct a lock and control works in Calumet River 
near its head, and similar structures in proposed Grand 
Calumet Channel west of Indiana Harbor Canal; alter or 
eliminate railroad bridges across three channels lakeward 
of Chicago Sanitary and Ship Canal, or construct new 
railroad bridges, to provide suitable clearance. 
A small-boat harbor in vicinity of Peoria, Ill., by 
construction of a basin 510 by 250 feet, dredged to 7 feet 
deep. 
$48,933 to reimburse Nutwood Drainage and Levee District for 
additional pumping operation; supplementing $58,750 
authorized in Oct. 1943 act. 
Federal participation in alteration of highway bridges, 
Calumet-Sag Modification, Part I, which constitute 
unreasonable obstructions to navigation, in accordance 
with Public Law 647, 76th Cong., as amended. 
Construct auxiliary locks at Lockport, Brandon Road, 
Dresden Island, Marseilles, Starved Rock, Peoria, and 
La Grange. 
Federal participation in alteration of highway bridges, 
Calumet-Sag Modification, Part II, which constitutes 
unreasonable obstructions to navigation, in accordance 
with Public Law 647, 76th Congress, as amended. 
INDIANA HARBOR, IND. [See Section 10 of Text] 
Outer harbor and maintenance of inner harbor channel. 
Breakwaters. 
Lighthouse crib, present length and aline easterly and 
northerly breakwaters. 
H. Doc. 184, 73d Cong., 
2d sess. 14 
H. Doc. 180, 73d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 19, 75th 
Cong., 1st sess. 
H. Doc. 711, 77th Cong., 
2d sess. 
H. Doc. 145, 76th Cong., 
1st sess. 
H. Doc. 477, 79th Cong., 
2d sess. 
H. Doc. 698, 79th Cong., 
2d sess. 
H. Doc. 144, 81st Cong., 
1st sess. 
H. Doc. 45, 85th Cong., 
1st sess.16 
H. Doc. 31, 86th Cong., 
1st sess. 
Specified in Act. Also 
H. Doc. 45, 85th Cong., 
1st sess. 
H. Doc. 1113 60th Cong., 
2d sess. 
H. Doc. 690, 62d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 6, 65th 
Cong., 2d sess. 
30-28

CHICAGO, ILL., DISTRICT 
TABLE 30-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 20, 1922 
Mar. 3, 1925 
July 3, 193017 
June 30, 1932 
Aug. 30, 193518 
Aug. 26, 1937 
July 14, 1960 
Oct. 27, 1965 
Mar. 3, 1899 
Mar. 2, 1907 
Aug. 30, 193519 
May 17, 1950 
Oct. 23, 1962 
Mar. 3, 1881 
June 25, 1910 
Aug. 30, 193520 
July 14, 1960 
Mar. 2, 1907 
Aug. 30, 193521 
Modify length of channel to be maintained in extension to 
Lake George. 
Authorized Secretary of War to modify project so far as 
relates to length and alinement of breakwaters and to sell 
Youngstown Sheet and Tube Co. about 1,180 linear feet of 
shoreward end of existing north breakwater. 
Existing project channel width and depth in Lake George 
Branch and turning basin at the Forks. 
Authorized Secretary of War to sell Inland Steel Co. about 
1,903 linear feet of southerly end of existing east 
breakwater. 
Extend easterly breakwater, dredge entrance channel and outer 
harbor, deepen channel betweenbulkhead fills, widen main 
stem of canal and portion of Calumet River Branch to 
141st St. 
Modified conditions of local cooperation required before 
enlargement of Indiana Harbor Canal is undertaken 
by United States. 
Increase authorized depths to 29 feet in outer harbor 
entrance channel; 28 feet in outer harbor, and 27 feet in 
canal entrance channel to first E.J.&E. Ry. Bridge. 
Deepen main canal from landward end of canal entrance channel 
to a point lakeward of Dickey Place Bridge over a modified 
channel width of 190 feet, except through bridge 
openings. 
KENOSHA HARBOR, WIS. [See Section 11 of Text] 
Parallel piers and 600 feet of breakwater. 12 
Extending breakwater 200 feet. 
Present project dimensions of entrance channel and basin. 
Channel northwesterly from basin. 
Deepen lake approach channel to 27 feet and 800 feet wide; 
deepen approach channel to 26 feet, entrance channel and 
inner basin to 25 feet. 
KEWAUNEE HARBOR, WIS. [See Section 12 of Text] 
Entrance piers. 12 
Turning basin 
North breakwater remove old north pier, widen and deepen 
entrance channel and turning basin to 20 feet and remove 
outer south shoal. 
Enlarge existing turning basin, extend existing project into 
north basin, and increase depth of north basin to 20 feet 
at a maximum width of 500 feet and eliminate removal of 
outer shoal. 
MANITOWOC HARBOR, WIS. [See Section 13 of Text] 
Breakwaters. 
Present project dimensions of channel through outer basin, 
removal of old north stub pier, and approach channel 
to a proposed city terminal south of shore end of south 
breakwater. 
Public Law 176, 67th Cong. 
Rivers and Harbors 
Committee Doc. 21, 71st 
Cong., 2d sess. 
Public Law 219, 72d Cong. 
Rivers and Harbors 
Committee Doc. 29, 72d 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 13, 75th 
Cong., 1st sess. 
H. Doc. 195, 86th Cong., 
1st sess. 
H. Doc. 227, 89th Cong., 
1st sess.8 
H. Doc. 328, 54th Cong., 2d 
sess. Annual Report, 1897, 
p. 2772, H. Doc. 164, 55th 
Cong. 3d sess. Annual 
Report, 1899, p. 1817. 
H. Doc. 62, 59th Cong., 
2d sess. and Rivers and 
Harbors Committee Doc. 
3, 59th Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 19, 74th 
Cong., 1st sess. 
H. Doc. 750, 80th Cong., 
2d sess. 
H. Doc. 496, 87th Cong., 
2d sess.8 
Annual Report, 1881, 
p. 2082. 
H. Doc. 324, 60th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 43, 72d 
Cong., 1st sess. 
S. Doc. 19, 86th Cong., 
1st sess.8 
H. Doc. 62, 59th Cong., 1st 
sess., as modified by Rivers 
and Harbors Committee 
Doc. 3, 59th Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 39, 73d 
Cong., 2d sess. 
30-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 30-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 26, 1937 
Oct. 23, 1962 
Dec. 31, 1968 
Sec. 107 
July 14, 1960 
Mar. 3, 1871 
June 13, 1902 
Mar. 4, 1913 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
July 14, 1960 
June 27, 1967 
Sec. 107 
July 14, 1960 
Mar. 3, 1889 
Mar. 3, 1905 
Jan. 21, 1927 
Aug. 30, 1935 
Sept. 30, 1966 
Sec. 107 
July 14, 1960 
Aug. 30, 1852 
Mar. 3, 1883 
Mar. 2, 1907 
Sept. 22, 1922 
Aug. 30, 1935 
Channel in river. 
Deepen Lake approach to 25 feet by 800 feet wide, deepen 
outer harbor to 25 feet, river channel to 23 feet to 
8th St., and Upper River Channel to 22 feet to Soo Line R.R. 
Dredge River Channel to 12 feet from Soo Line R.R. 
720 feet upstream. 
MENOMINEE HARBOR AND RIVER, MICH. AND WIS. 
[See Section 14 of Text] 
Entrance piers. 12 
Consolidation of project for harbor and river, and a channel 
18 feet deep. 
Partial restoration of work above bridge which had been 
eliminated by act of May 3, 1905. 
20-foot depth in channel and 18-foot depth in turning basin. 
21-foot depth in channel and turning basin and enlarge 
turning basin. 
Extend channel 12 feet deep to vicinity of Marinette Yacht 
Club. 
Deepen existing approach channel to 26 feet, entrance and 
river channels to 24 feet and enlarge turning basin. 
Deepen 1,100 feet of river channel generally north of 
Marinette Corp. facilities to 19 feet. 
MICHIGAN CITY HARBOR, IND. [See Section 15 of Text] 
East breakwater and old east pier inclosing the outer basin. 
Extension of east pier. 
Extend east pier and construct detached breakwater. 
Lower turning basin. Rebuild west pier as at present located. 
Present project dimensions of entrance channel. 
Existing project depth in channel, and in lower and 
middle turning basins, eliminated improvement of Trail 
Creek above middle turning basin and uncompleted 
portion of detached breakwater, abandonment of old east 
breakwater and old east pier inclosing outer basin. 
Restore and repair westerly 1,000 feet of east breakwater, 
dredging outer basin, and enlarging entrance to basin 
through east pier. 
Dredge river channel 50 feet wide and 6 feet deep from upper 
turning basin to E Street bridge. 
'MILWAUKEE HARBOR, WIS. [See Section 16 of Text] 
North pier. 12 
Inner 7,600 feet of breakwater. 12 
South pier. Extending north breakwater 1,000 feet. 
Extend north breakwater; a south breakwater, present project 
dimensions of inner entrance channel. 
Dredging a portion of outer harbor to 21-foot depth. 
30-30 
Rivers and Harbors 
Committee Doc. 80, 74th 
Cong., 2d sess. 
H. Doc. 479, 87th Cong., 
2d sess. 
Detailed Project Report 
June 1967.8 
Annual report, 1867, p. 132. 
H. Doc. 419, 56th Cong., 
1st sess. 
H. Doc. 171, 70th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 28, 73d 
Cong., 2d sess. 
H. Doc. 228, 76th Cong., 
1st sess. 
H. Doc. 112, 86th Cong., 
1st sess. 
Detailed Project Report 
Dec. 1960.8 
Recommendation of a Board 
of Engineers. Annual 
Report, 1870, p. 123. 
Reports of Boards of 
Engineers, Annual Report, 
1851, pp. 2187-2189; 
Annual Report 1882, 
pp. 2264-2266. 
Annual Report, 1897, 
pp. 2903-2904. 
Joint resolution of Congress 
approved May 13, 1908, 
Public Law 23. 
H. Doc. 279, 69th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 34, 74th 
Cong., 1st sess. 
Detailed Project Report 
June 1965.8 
S. Doc. 175, 25th Cong., 
2d sess. 
Annual Report, 1881, 
p. 2122. 
Annual Report, 1906, 
p. 1752. [No prior survey 
or estimate affecting 
breakwater extensions.] 
H. Doc. 804, 66th Cong., 
2nd sess. 
H. Doc. 289, 72d Cong., 
1st sess.

CHICAGO, ILL., DISTRICT 
TABLE 30-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 194522 
July 14, 1960 
Oct. 23, 1962 
Aug. 2, 1882 
June 25, 1910 
July 11, 1870 
Aug. 14, 1876 
Aug. 30, 193523 
July 3, 195824 
Mar. 2, 1907 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1907 
Jan. 21, 1927 
Aug. 30, 1935 
Sept. 3, 1954 
Mar. 3, 1873 
July 13, 1892 
June 13, 1902 
Aug. 30, 1935 
Mar. 2, 1945 
Dredging river channels to 21-foot depth. 
Deepen South Menomonee and Burnham Canals to 21 feet. 
Deepen an approach channel to 30 feet by 800 feet wide and 
300 feet wide through breakwater; deepen entrance channel 
28 feet through piers, outer harbor to 28 feet south of 
entrance channel, and a channel to 27 feet in Milwaukee 
River to Buffalo St., and in Kinnickinnic River to Chicago 
& North Western Ry. bridges. 
OCONTO HARBOR, WIS. [See Section 19 of Text] 
Piers, except for inner 300 feet of south pier and 250 feet 
of north pier built by city. 12 
Present project dimensions of channel and turning basin. 
PORT WASHINGTON HARBOR, WIS. 
[See Section 20 of Text] 
North pier and south basin. 12 
North basin. 
North breakwater, removal of 650 feet of north pier, outer 
turning basin, present project dimensions of channel 
and basin and extension of south breakwater. 
Extending and raising of north breakwater and placing 
rubble along sides; removing 456 feet of south breakwater 
and dredging in outer basin. 
RACINE HARBOR, WIS. [See Section 21 of Text] 
Breakwaters. 
Remove shoals lakeward of harbor entrance, enlarge 
19-foot channel through outer basin and 19-foot channel in 
river. 
Present project dimensions of channel through outer basin 
and in river. 
SHEBOYGAN HARBOR, WIS. [See Section 22 of Text] 
North breakwater. 
Preserving south pier as part of project, providing turning 
basin, and elimination of proposed south breakwaters. 
Present project dimensions of channel. 
Widen and deepen outer harbor entrance channel to 450 feet, 
widen and deepen river channel from present project limit 
to north side of Jefferson Ave. 
STURGEON BAY AND LAKE MICHIGAN SHIP CANAL, 
WIS. [See Section 23 of Text] 
Breakwaters. 12 
Acquisition of the canal. 
Canal revetments and consolidation of canal and harbor works. 
Present project dimensions of channels and elimination of 
turning basin immediately west of revetted canal. 
Turning basin between city and Bushman wharves. 
S. Doc. 29, 76th Cong., 
1st sess. 
H. Doc. 285, 86th Cong., 
2d sess. 
H. Doc. 134, 87th Cong., 
1st sess.8 
Annual Report, 1881, 
p. 2066. 
H. Doc. 538, 61st Cong., 
2d sess. Plan C. 8 
H. Ex. Doc. 28, 41st 
Cong. 2nd sess., 
and Annual Report, 
1879, p. 119. 
Annual Report, 1876, 
pt. 2, p. 379. 
H. Doc. 168, 72d Cong., 
1st sess., and River and 
Harbors Committee Doc. 
41, 74th Cong., 1st sess. 
H. Doc. 446, 83d Cong., 
2d sess.8 
H. Doc. 62, 59th Cong., 
1st sess., and Annual 
Report 1909, p. 1973. 
Rivers and Harbors 
Committee Doc. 46, 75th 
Cong., 1st sess. 
H. Doc. 816, 77th Cong., 
2d and H. Doc. 255, 
78th Cong., 1st sess.8 
H. Doc. 62, 59th Cong., 
1st sess. 
H. Doc. 475, 68th Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 47, 74th 
Cong., 1st sess. 
H. Doc. 554, 82d Cong., 
2d sess.8 
H. Ex. Doc. 34, 42d Cong., 
2d sess. Annual Report, 
1872, p. 171. 
H. Ex. Doc. 106, 49th Cong., 
2d sess. 
H. Doc. 117, 56 Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 9, 74th 
Cong., 1st sess. 
H. Doc. 421, 78th Cong., 
2d sess.s 
30-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 30-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1871 
Mar. 2, 1907 
Aug. 30, 1935 
July 3, 1958 
June 14, 1880 
Aug. 3, 1882 
June 13, 1902 
July 3, 1930 
Mar. 2, 1945 
Dec. 17, 1970 
Sec. 201 
Oct. 27, 1965 
TWO RIVERS HARBOR, WIS. [See Section 24 of Text] 
South pier, 750 feet of north pier, and about 44 feet of 
north revetment. 12 
Remainder of north pier and stilling basin. 
Deepening entrance channel and inner basin to 18 feet. 
Extend existing project in West Twin River to 18 feet deep 
and in East Twin River to 10 feet deep to 22d Street 
Bridge. 
WAUKEGAN HARBOR, ILL. [See Section 25 of Text] 
Parallel piers and basins. 12 
Modified location of harbor entrance. 
Detached breakwater, extend piers, increase width of harbor 
at inner end of north pier, and dredge channel and basin to 
existing project depth. 
Extension of breakwater to shore, dredging near outer end 
of north pier, and enlarging inner basin. 
Dredge an entrance channel to existing project dimensions 
from outer end of north pier to project depth in lake, 
and dredge an anchorage area in southwest corner of inner 
basin to existing project depth. Abandonment of dredging 
triangular area in southwest corner of inner basin to 
18 feet deep. 
Provides for deepening the existing entrance channel in the 
outer harbor to 25 feet and extending it to that depth in 
Lake Michigan, at widths varying from 380 feet to 
500 feet; deepening the channel between piers to a depth 
of 23 feet at a width of 180 feet, and deepening the inner 
basin to 23 feet and extending its limits approximately 
275 feet northward. 
1. Included in Public Works Administration Program 
Sept. 6, 1943, and Dec. 16, 1933. 
2. Uncompleted portion is inactive [dredging in front of 
U.S. Steel Corp.] 
3. Uncompleted portion is inactive [breakwater closure.] 
4. Contains latest map of harbor. 
5. Contains latest map of river. 
6. Latest published map is in Annual Report for 1914, 
opposite p. 2928. 
7. Contains latest published map of North Branch above 
North Ave. 
8. Contains latest published map. 
9. This portion inactive. 
10. Permanent Appropriations Repeal Act. 
11. Transfer completed June 1962. 
12. Completed under previous project. 
13. Included in Public Works Administration Program, 
Jan. 3, 1934. 
14. Contains latest published map of Illinois and 
DesPlaines Rivers. 
15. Included, in part, in Public Works Administration 
Program, Oct. 31, 1934, and Feb. 28, 1935. 
16. Contains latest published maps of Calumet-Sag 
portion. 
17. Uncompleted portion is inactive [widen and deepen 
Lake George Branch.] 
18. Included in Public Works Administration Program 
Sept. 6, 1933, and July 25, 1934. Uncompleted portion is 
inactive [widen and deepen main channel of canal and 
Calumet River Branch.] 
19. Included in emergency relief program May 28, 1935. 
20. Included in emergency relief program, May 28, 1935. 
Inactive portion; removal of 200 linear feet of north pier 
widening inner 200 feet of channel through outer basin, and 
closing gap in north-shore connection of breakwater. 
21. Superseded by act of October 23, 1962. 
22. Uncompleted portion inactive [dredging Milwaukee 
River from Buffalo St. Bridge to North Humboldt Ave. 
Bridge.] 
23. Work recommended in H. Doc. 168, 72d Cong., 1st 
Sess., included in Public Works Administration Program, 
Sept. 6, 1933. 
24. Inactive. 
30-32 
Annual Report, 1871, p. 123 
[as modified by Chief of 
Engineers, Feb. 27, 1897]. 
H. Doc. 730, 59th Cong., 
1st sess. Modification of 
Plan A. 
Rivers and Harbors 
Committee Doc. 25, 73d 
Cong., 2d sess. 
H. Doc. 362, 84th Cong., 
2d sess.8 
Annual Report, 1880, 
p. 1942. 
Annual Report, 1882, 
pp. 277-2162. 
H. Doc. 343, 56th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 27, 71st 
Cong., 2d sess. 
H. Doc. 116, 77th Cong., 
1st sess. 
H. Doc. 368, 90th Cong., 
2d sess. 8

CHICAGO, ILL., DISTRICT 
EXISTING PROJECTS 
See 
Section 
in Text Project Item Length (feet) Width (feet) Depth (feet) 
4. Calumet Harbor and 
River, Ill. and Ind. 
5. Chicago Harbor, Ill. 
8. Green Bay Harbor, 
Wis. 
9. Illinois Waterway, 
Ill. and Ind. 
11. Kenosha Harbor, 
Wis. 
Northerly breakwater 
Southerly breakwater 
North pier 
Approach channel 
Outer harbor 
River entrance 
Elgin, Joliet & Eastern Railway Bridge 
to turning basin No. 3 
Turning basin No. 3 to turning basin 
No. 5 
Approach into Lake Calumet 
Extension into Lake Calumet 
Turning basins 1, 2 and 5 
Shore arm north breakwater 
North exterior breakwater 
Southerly extension 
Main inner breakwater 
South inner breakwater 
North pier 
Approach channel 
Channel and maneuver area 
Entrance channel 
Inner basin 
Entrance channel 
Entrance channel 
Entrance channel 
Fox River channel 
Turning basin (on Fox River) at mouth 
of East River 
Turning basin abaove C.&N.W. Ry. Bridge 
Upper River channel 
Turning basin at DePere 
Nine locks and six dams with duplicate 
locks at seven locations 
Grafton to Lockport, Ill. 
Lockport to controlling works 
Controlling works to junction with 
Calumet-Sag Channel 
Calumet-Sag Channel to lock in Blue 
Island 
Calumet and Little Calumet Channel, 
from Blue Island to turning basin 5 
Grand Calumet River Channel from 
junction with Little Calumet River 
to and in Indiana Harbor Canal to 
141st, East Chicago, Ind. 
Also, Grand Calumet River Channel 
from junction of Indiana Harbor Canal 
and Grand Calumet River to Clark St. 
in Gary, Ind., with a turning basin at 
Clark St. 
A channel in Chicago Sanitary and Ship 
Canal and South Branch Chicago River 
from Sag-Junction to Lake St. in 
Chicago, Ill. 
Breakwater 
North pier 
South pier 
6,714 - 
5,007 - 
2,450 - 
9,700 3,200 
10,500 3,000 
3,000 290 
21,100 200 
and variable 
8,000 Variable 
4,000 400 
3,000 1,000 
2,250 - 
5,316 - 
4,944 - 
4,338 - 
2,544 - 
960 - 
6,600 800 
2,200 1,300 
7,300 190-470 
1,270 740 
49,632 500 
9,504 300 
9,504 300 
16,896 Varies 
- 1,000 
- 800 
17,424 150 
- 640 
291.1 miles 300 
2.0 miles 200-300 
10.0 miles 225 
16.0 miles 225 
7.7 miles 300 
9.0 miles 9 
4.2 miles 160 
22.1 miles 175-300 
796 
1,077 
1,175 
30-33 
TABLE 30-C 
-
- 
29 
28 
27 
27 
earth 
28 
rock 
27 
27 
27 
27 
29 
28 
21 
21 
26 
26 
24 
24 
24 
20 
18 
18
9
9
9
9
9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 30-C (Cont'd) EXISTING PROJECTS 
See 
Section 
in Text Project Item Length (feet) Width (feet) Depth (feet) 
11. Kenosha Harbor, 
(cont'd.) Wis. 
(cont'd.) 
12. Kewaunee Harbor, 
Wis.' 
13. Manitowoc Harbor, 
Wis. 
14. Menominee Harbor 
and River, Mich. 
and Wis. 
Lake approach channel 
Approach channel 
Entrance channel 
Inner basin 
North Channel to 50th Street Bridge 
North breakwater 
North pier 
South pier 
Approach channel 
Outer basin 
Channel to turning basin 
Turning basin 
Channel to North Basin 
North Basin 
North breakwater 
South breakwater 
North stub pier 
Approach channel 
Outer harbor 
Lower River Channel 
Upper River Channel 
Upper River Extension 
North pier 
South pier 
Approach channel 
Inner channel 
River channel 
Turning basin 
River channel 
River channel 
15. Michigan City, Harbor, Detached breakwater 
Ind. West pier 
East pier 
East breakwater 
Entrance channel 
16. Milwaukee Harbor, 
Wis. 
Main channel 
Outer basin 
Trail Creek 
Trail Creek 
North breakwater 
South breakwater 
North pier 
South pier 
Approach channel 
Entrance channel 
North outer harbor 
South outer harbor 
Milwaukee River 
Milwaukee River to Buffalo Street 
Bridge 
Milwaukee River Buffalo St. to 
Humboldt Ave. 
Menomonee River 
Kinnickinnic River entrance channel 
to C&NW Ry. 
30-34 
2,800 
650 
2,150 
800 
475 
2,980 
626 
1,850 
800 
1,200 
950 
700 
1,000 
300 
2,450 
2,290 
74 
2,600 
1,700 
1,500 
7,000 
720 
1,870 
2,631 
3,000 
3,100 
4,800 
800-200 
1,100 
1,400 
1,304 
835 
2,276 
1,000 
1,900 
2,400 
900 
3,000 
2,300 
9,954 
9,671 
1,656 
1,608 
1,500 
4,300 
4,600 
4,600 
1,100 
2,750 
10,000 
9,000 
4,400 
800 
400 
200 
200-700 
75 
600 
505 
150-156 
500 
100 
500 
800 
800 
180 
Variable 
110-150 
600 
300 
200 
500 
150 
90 
150-425 
120-150 
900 
50-100 
50 
300-800 
250-600 
1,500 
2,200 
250 
Variable 
Variable 
Variable 
350-150 
27 
26 
25 
25 
21 
20 
20 
20 
20 
20 
20 
25 
23 
23 
22 
12 
26 
24 
24 
21 
19 
12 
18 
18 
8-12 
18
6 
30 
28 
212 
28 
27 
21 
21 
21

TABLE 30-C (Cont'd) 
CHICAGO, ILL., DISTRICT 
EXISTING PROJECTS 
See 
Section 
in Text Project Item Length (feet) Width (feet) Depth (feet) 
16. Milwaukee Harbor 
(cont'd.) (cont'd.) 
19. Oconto Harbor, Wis. 
20. Port Washington 
Harbor, Wis. 
21. Racine Harbor, Wis. 
22. Sheboygan Harbor, 
Wis. 
23. Sturgeon Bay and 
Lake Michigan 
Ship Canal, Wis. 
24. Two Rivers Harbor, 
Wis. 
25. Waukegan Harbor, 
Ill. 
Kinnickinnic River C&NW Ry. to 
So. Kinnickinnic Ave. Bridge 
South Menomonee Canal 
Burnham Canal 
North pier 
South pier 
Approach channel 
River channel 
Turning basin 
North breakwater 
North stub pier 
Entrance channel and outer basin 
North basin 
West basin 
North breakwater 
North stub pier 
South breakwater 
Approach channel 
Outer basin 
Root River Channel 
North breakwater 
North stub pier 
South breakwater 
Approach channel 
Entrance channel 
Outer turning basin 
Lower river channel 
Upper river channel 
Approach channel 
Two converging breakwaters (each) 
Approach through breakwaters 
Revetted canal 
Channel through Sturgeon Bay 
Channel through Sturgeon Bay 
Turning Basin 
Approach channel 
North pier 
South pier 
Channel 
Inner Basin 
Channel East Twin Bridge 
North breakwater 
North pier 
South pier 
Entrance channel 
Channel to inner basin 
Inner basin 
Anchorage area 
2,200 150-100 21 
4,350 
1,320 
1,350 
2,200 
2,500 
1,300 
500 
3,817 
125 
2,550 
750 
490 
2,640 
180 
2,616 
680 
1,000 
2,000 
3,832 
120 
2,490 
1,000 
1,860 
1,500 
4,400 
1,300 
1,200 
1,344 
1,880 
6,400 
21,400 
14,600 
1,000 
1,642 
1,720 
1,600 
800 
2,200 
1,900 
1,610 
3,211 
3,250 
1,700 
1,650 
- 3 
100 
100 
150-300 
100 
375 
100-750 
150-185 
100-130 
250 
1,000 
95-190 
450 
475 
400 
140-370 
100-130 
600 
130-200 
130 
250 
500 
500 
200 
200 
100 
380-500 
180 
375-500 
_ 3 
1. For detailed description see page 1224, Annual Report for 1963. 
2. Dredging by city of Milwaukee and reimbursed at 10� per cu. yd. 
3. Area of about6 acres. 
30-35 
21 
21 
15 
15 
15 
21 
18 
18 
23 
21 
19 
25 
21 
20 
21 
15 
23 
23 
22 
22 
22 
20 
18 
18 
18 
10 
25 
23 
23
8

TABLE 30-D FOX RIVER, WIS.: LOCKS AND DAMS 
(See Section 7 of Text) 
Depth at 
Normal Pool 
Miles Avail- Lower 
from Dis- Clear able Breast Miter Character Kind Year 
Green Nearest tance Width Length Lift Wall' Sill of of Type of Com- Actual 
Name of Lock and Dam Bay Town (miles) (feet) (feet) (feet) (feet) (feet) Foundation Dam Construction plete Cost 
DePere lock2 
DePere dam 2 
Little Kaukauna lock2 
Little Kaukauna dam2 
Rapide Croche lock 2 
Rapide Croche Dam 2 
Kaukauna fifth lock2 
Kaukauna fourth lock2 
Kaukauna third lock2 
Kaukauna second lock2 
Kaukauna first lock2 
Kaukauna Dam2 
Kaukauna guard lock 
Little Chute combined lock: 
7.1 DePere 
7.2 DePere 
13.0 DePere 
13.1 DePere 
19.2 Wrightstown 
19.3 Wrightstown 
22.8 Kaukauna 
23.1 Kaukauna 
23.3 Kaukauna 
23.4 Kaukauna 
23.6 Kaukauna 
24.0 Kaukauna 
24.0 Kaukauna 
Lower 24.4 Little Chute 
Upper 25.4 Little Chute 
Little Chute second lock2 26.4 Little Chute 
Little Chute first (guard) lock' 26.5 Little Chute 
Little Chute Dam2 26.6 Little Chute 
Cedars lock2 27.3 Little Chute 
Cedars Dam2 27.4 Little Chute 
Appleton fourth lock2 30.7 Appleton 
Appleton lower dam 2 30.9 Appleton 
Appleton third lock2 31.3 Appleton 
Appleton second lock2 31.6 Appleton 
Appleton first lock2 31.9 Appleton 
Appleton upper dam 32.2 Appleton 
Menasha lock2 37.0 Menasha 
Menasha Dam2 37.8 Menasha 
6
6
2
2
1
1
1
1
1
1 
36.0 146.0 8.9 10.3 12.0 Rock - Concrete 1936 $229,308 
- - - - - Rock Fixed3 4 Concrete 1929 209,536 
36.0 146.0 7.2 8.0 9.5 Clay - Concrete 1938 362,427 
- - - - - Clay and gravel Fixed 3 4 Piers and concrete 1926 179,398 
36.0 146.0 8.3 8.8 9.3 Rock - Concrete 1934 228,738 
- - - - - Rock Fixed 3 4 Concrete 1930 118,975 
35.6 144.0 9.1 6.7 7.4 Rock - Composite 1898 13,3105 
36.6 144.1 10.2 6.9 6.0 Rock - Stone masonry 1879 37,536 
30.6 144.0 10.2 6.9 6.3 Rock - Stone masonry 1879 39,948 
35.0 144.0 9.6 6.0 6.0 Rock - Stone masonry 1903 24,313 
35.1 144.4 11.0 6.9 6.0 Rock - Stone masonry 1883 38,704 
- - - - - Rock Fixed3 4 Concrete 1931 123,763 
40.0 - - 9.4 - Rock - Stone masonry 1891 12,630 
35.4 146.5 10.9 6.0 8.6 Rock 
36.3 144.1 10.6 7.6 6.0 Hardpan 
35.0 144.2 13.8 8.0 6.1 Rock 
35.4 - - 6.6 - Rock 
- - - - - Rock 
35.0 144.0 9.8 6.8 7.3 Rock 
- - - - - Rock 
35.0 144.0 7.6 8.1 7.9 Rock 
- - - - - Rock 
35.0 144.0 8.7 6.0 8.6 Rock 
35.1 144.6 9.6 6.9 6.0 Clay 
35.0 144.7 10.0 6.6 6.0 Rock 
- - - - - Rock 
35.4 144.0 8.5 7.2 8.0 Clay 
- - - - - Hardpan 
- Stone masonry 
- Stone masonry 
- Stone masonry 
- Stone masonry 
Fixed3 4 Concrete 
- Stone masonry 
Fixed 3 4 Concrete 
- Stone masonry 
Fixed3 4 Concrete 
- Stone masonry 
- Stone masonry 
- Stone masonry 
Fixed 3 Concrete 
- Composite 
Fixed 3 Concrete 
1879 102,304 
1879 - 
1881 48,555 
1904 7,8175 
1932 82,554 
1888 34,972 
1933 84,973 
1907 40,893 
1934 73,903 
1900 32,238 
1901 22,940 
1884 36,004 
1940 151,558 
1899 19,3265 
1937 84,686 
0
Cd 
x
0
x
z
z
ri) 
CJ2 
c 
'Depth shown is on breast wall, which is controlling depth for upper pool. 
2 Original structure built prior to assumption of control by United States 
on Sept. 18, 1872. 
3 Provided with sluices. 
4 Flash boards used. 
5Partially rebuilt. 
<p 
0

CHICAGO, ILL., DISTRICT 
TABLE 30-E ILLINOIS WATERWAY: 
EXISTING AND PROPOSED LOCKS AND DAMS 
(See Section 9 of Text) 
Dimensions Depth on Miter Sills 
at Low Water 
Available Lift at 
Miles Width of Length for Low 
Above Chamber Full Width Water' Lower Upper 
Lock Mouth Miles to Nearest Town (feet) (feet) (feet) (feet) (feet) 
LaGrange lock 80.2 7.8 below Beardstown, Ill. 110 600 10.0 13.0 15.5 
Auxiliary lock 80.2 7.8 below Beardstown, Ill. 110 1,200 10.0 13.0 15.5 
Peoria lock 157.7 4.1 below Peoria, Ill. 110 600 11.0 12.0 15.5 
Auxiliary lock 157.7 4.1 below Peoria, Ill. 110 1,200 11.0 14.0 14.0 
Starved Rock lock 231.0 Utica, Ill. 110 600 18.5 14.0 16.8 
Auxiliary lock 231.0 Utica, Ill. 110 1,200 18.5 14.0 13.0 
Marseilles lock 244.6 Marseilles, Ill. 110 600 24.45 14.0 18.6 
Auxiliary lock 244.6 Marseilles, Ill. 110 1,200 24.25 14.0 12.75 
Dresden Island lock 271.5 8 above Morris, Ill. 110 600 21.75 12.25 16.85 
Auxiliary lock 271.5 8 above Morris, Ill. 110 1,200 21.75 14.0 13.0 
Brandon Road lock 286.0 Joliet, Ill. 110 600 34.0 13.8 17.85 
Auxiliary lock 286.0 Joliet, Ill. 110 1,200 34.0 14.0 14.0 
Lockport lock 291.1 Lockport, Ill. 110 600 30.5-39.52 15.0 11.5-22.02 
Auxiliary lock 291.1 Lockport, Ill. 110 1,200 30.5-39.52 14.0 14.6 
T.J. O'Brien lock 326.5 Chicago, Ill. 110 1,000 - 14.0 14.0 
Grand Calumet lock3 329.5 Hammond, Ind. 110 1,000 - 14.0 14.0 
1Lifts and depths on miter sills are those obtained with flat pools. 
2 Variation in lift and depth on upper miter sill at Lockport is due to fluctuation of water surface in the sanitary district canal. 
3 Proposed. 
30-37

TABLE 30-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
ILLINOIS WATERWAY, ILL. AND IND. 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 9 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Illinois River, mouth 
to Utica; channel 
improvement by 
dredging in Illinois 
River below 
Starved Rock, 
modification of 
two U.S. locks 
and dams, and 
removal of two 
State dams. 
LaGrange 
Auxiliary lock 
Peoria 
Auxiliary lock 
Starved Rock 
Auxiliary lock 
Marseilles 
Auxiliary lock 
Dresden Island 
Auxiliary lock 
Brandon Road 
Auxiliary lock 
Lockport 
Auxiliary lock 
T.J. O'Brien 
Lock and dam 
equipment 
Total locks 
and dams 
- - - - - - $ 2,773,4991 
Concrete Piles in sand 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
Concrete 
and sheet 
piling 
Piles in sand 
Piles in sand 
Piles in sand 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
Rock 
Piles in clay 
Movable 
(wicket 
with Aframe-
crest) 
Concrete and 
timber 
Concrete and 
timber 
Movable Concrete and 
(wicket type) timber 
Movable Concrete and 
(tainter gates) structural steel 
Piles in sand 
Piles in sand 
Piles in sand 
Rock 
Movable Concrete and Rock 
(tainter gates) structural steel 
Movable Concrete and Rock 
(tainter gates) structural steel 
Movable Concrete and Rock 
(tainter gates) structural steel 
Movable (Bear Concrete and Rock 
trap)2 structural steel 
Fixed 3 Concrete and 
sheet piling 
Piles in clay 
1939 
1939 
1939 
1933 
2,744,5921 
73,329,000 
3,381,0301 
75,421,000 
885,3151 
73,105,000 
1933 1,853,7251 
80,833,000 
1933 2,503,3761 
59,683,000 
1933 2,031,6831 
156,400,000 
1933 133,6081 
178,229,000 
1960 6,954,7001 
- - 1,250,3041 
- $721,511,832 
30-38 
1 Actual cost. 
2 Six dams completed by the Corps; 48-foot bear trap at Lockport completed by State of Illinois. 
3 Control works.

CHICAGO, ILL., DISTRICT 
TABLE 30-G ILLINOIS WATERWAY, ILL. AND IND. 
ADDITIONAL FEATURES ENTERING INTO COST 
(See Section 9 of Text) 
Dredging: 
Little Calumet and Calumet Rivers 
Calumet-Sag, 3 passing places 
Starved Rock to Lockport 
Starved Rock to Grafton 
Calumet-Sag Channel 
Peoria small boat harbor 
Protection piers at all locks 
Calumet-Sag modification engineerihg and design 
Calumet-Sag modification, supervision and administration 
Rebuild highway bridges 
Rebuild railway bridges: 
Calumet-Sag Channel 
Little Calumet and Calumet Rivers 
Recreation Facilities, Code 711 
Removal of Blue Island lock 
Grand Calumet River controlling works 2 
St. Louis District 
Total additional features 
Total existing project 
$ 2,135,3581 
813,4181 
3,650,635 
2,686,307 
19,259,000 
24,9371 
77,6131 
4,900,000 
5,346,000 
17,177,700 
21,011,9591 
18,362,0411 
445,000 
288,6001 
1,081,6001 
$ 97,260,168 
$818,772,000 
1 Actual cost. 
2 Placed in inactive status 19 November 1974. 
TABLE 30-H ILLINOIS WATERWAY, ILL. AND IND. 
THE TOTAL COST OF EXISTING PROJECT 
TO JUNE 30, 1975 
(See Section 9 of Text) 
New Work Maintenance Rehabilitation Total 
Regular Funds $112,571,274 $92,852,799 $414,625 $205,838,698 
Public Works Funds 3,960,735 - - 3,960,735 
Emergency Relief Funds 1,858,936 - - 1,858,936 
Total $118,390,945 $92,852,799 $414,625 $211,658,3691 
1 Includes $1,735,890 expended between 1927 and 1936 on the operation and care of the works of improvement under the 
provisions of the permanent indefinite appropriation for such purposes. 
30-39

TABLE 30-I 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 26 of Text) 
Date Reconnaissance 
or condition survey 
Name of Project conducted Cost 
Little Bay De Noc, October 1973 $4,457 
Gladstone Harbor & 
Kipling, Mich. 
Pensaukee Harbor, 10,543 
Wis. 
TABLE 30-J OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cedar River Harbor, Mich. 1971 78,2754 - 
Harbors at Washington Island, Wis.' 1950 62,838 23,116 
Little Bay De Noc, Gladstone Harbor 
& Kipling, Mich. 1966 332,832 18,477 
Pensaukee Harbor, Wis. 1966 34,035 85,644 
South Milwaukee Harbor, Wis.2 3 1906 5,000 - 
'Channels adequate for commerce. 
'No commerce reported. 
3Abandonment recommended in 1926 [H. Doc. 467, 69th Cong., 1st Sess.]. 
4 Includes $28,464 for work authorized by Act of Aug. 2, 1882. 
TABLE 30-K OTHER AUTHORIZED BRIDGE ALTERATION 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Calumet River Bridges' 1967 1,625,068 
'Transferred to Department of Transportation in accordance with Section 6[g] of the Act of October 15, 1966, P.L. 89-670. 
30-40

CHICAGO, ILL., DISTRICT 
TABLE 30-L OTHER AUTHORIZED BEACH EROSION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Chicago, Cook County, I1.16 - - - 
Evanston, Cook County, Ill. 1970 474,0523 - 
Green Bay-Marinette, Wis. 7,463 
Kenilworth, Cook County, Ill. 1 7 5,2004 
Lake Michigan - Escanaba, Mich. - 7,000 
Lake Michigan - Lake Forest, Ill. - 7,899 
Lake Michigan - Racine, Wis. - 6,251 - 
Shore of Manitowoc County, Wis.2 - 60,503 - 
Winnetka, Cook County, I11.16- 
1Authorized by River and Harbor Act of 1954. 
2Authorized by River and Harbor Act of 1958. 
3 Includes reimbursements to Evanston of $263,534 in fiscal year 1962, $201,987 in fiscal year 1969, and Government costs of 
$3,200 in fiscal year 1963, $533 in fiscal year 1964, $4,592 in fiscal year 1968 and $206 in fiscal year 1969. 
4 Reimbursement to Kenilworth in fiscal year 1961. 
5 Includes reimbursement of $56,037 to Wisconsin State Highway Commission and Government costs of $4,466, in fiscal 
year 1964. 
6 Inactive. 
7Uncompleted portion is inactive. 
TABLE 30-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 38 of Text) 
Project Location Date of Inspection 
ILLINOIS RIVER, ILLINOIS 
Banner Special Drainage and Levee District Dec. 1975 
Big Lake Drainage and Levee District Dec. 1975 
Coal Creek Drainage and Levee District Nov. 1975 
Crane Creek Drainage and Levee District Nov. 1975 
East Liverpool Drainage and Levee District Dec. 1975 
East Peoria Drainage and Levee District Dec. 1975 
East Peoria Sanitary District Dec. 1975 
Hennepin Drainage and Levee District Dec. 1975 
Kelly Lake Drainage and Levee District Dec. 1975 
Kerton Valley Drainage and Levee District Dec. 1975 
Lacey Drainage and Levee District Dec. 1975 
Langellier Drainage and Levee District Dec. 1975 
Liverpool Drainage and Levee District Dec. 1975 
Lost Creek Drainage and Levee District Nov. 1975 
Pekin and LaMarsh Drainage and Levee District Dec. 1975 
Sanitary District of Beardstown Nov. 1975 
Sea Horn Drainage and Levee District Dec. 1975 
South Beardstown Drainage and Levee District Nov. 1975 
Spring Lake Drainage and Levee District Dec. 1975, 
Thompson Lake Drainage and Levee District Nov. 1975 
Valley Drainage and Levee District Nov. 1975 
West Matanzas Drainage and Levee District Dec. 1975 
SANGAMON RIVER, ILLINOIS 
Clear Lake Special Drainage District Nov. 1975 
Farmers Levee and Drainage District Dec. 1975 
Farmers Levee and Drainage District (Herget) Dec. 1975 
Mason and Menard Drainage District Dec. 1975 
Oakford Special Drainage District Dec. 1975 
30-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 30-N OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
ILLINOIS RIVER, ILL. 
Banner Special Drainage and Levee Districts' 1943 274,822 - 
Big Lake Drainage and Levee Districts' 1943 144,910 - 
Big Prairie Drainage and Levee District 2 
Coal Creek Drainage and Levee District' 1954 1,923,145 - 
Crane Creek Drainage and Levee District 1941 68,898 - 
East Liverpool Drainage and Levee District' 1941 207,826 - 
East Peoria Drainage and Levee District' 1946 279,963 - 
Hennepin Drainage and Levee Districts' 1940 109,593 - 
Kelly Lake Drainage and Levee District 1947 13,153 - 
Lacy Langellier, West Mantanzas and Kerton Valley 
Drainage and Levee District' 1954 1,290,00036 - 
Liverpool Drainage and Levee District' 1943 117,731 - 
Lost Creek Drainage and Levee District4 1938 - - 
Pekin LaMarsh Drainage and Levee District' 1955 158,383 - 
Peoria, 11.10 1973 534,480 - 
Rocky Ford Drainage and Levee District' 1941 108,797 - 
Sea Horn Drainage and Levee District' 1945 32,281 - 
Sid Simpson Flood Control Project' 1968 5,789,800 - 
South Beardstown and Valley Drainage and 
Levee District' 1942 220,729 - 
South Beardstown Drainage and Levee District' 1942 171,839 - 
Spring Lake Drainage and Levee District' 1941 185,980 - 
Thompson Lake Drainage and Levee District 1952 9,465 - 
KANKAKEE RIVER, ILL. AND IND. 
Levee between Shelby Bridge and Baum's Bridge 
in Ind. 1938 
LITTLE CALUMET RIVER, ILL. AND IND. 
Little Calumet River and Tributaries, Ill. 
and Ind. 7 1968 53,136 
SANGAMON RIVER, ILL. 
Bell Drainage District 1946 1,112 - 
Clear Lake Special Drainage District8 1965 103,027 - 
East of Chandlerville 1959 30,588 - 
Farmers Levee and Drainage District' 1942 155,562 - 
Farmers Levee and Drainage District 5 - - 
Mason and Menard Drainage District' 1940 93,808 - 
Near Springfield on Sangamon River, Ill.' 1941 97,743 - 
Oakford Special Drainage District' 1940 38,417 - 
Panther Creek levee 1938 - - 
Tar Creek levee 1946 1,425 - 
SALT CREEK, ILL. 
Donovan levee 1945 1,821 - 
East of Hubly Bridge 1945 572 - 
Lake Fork of Salt Creek 9 s - - 
Lussenhop levee 1945 110 - 
Salt Creek in vicinity of Middletown, Ill. 1940 48 - 
Swiger Whitney, Young, Hobit levee 1945 399 - 
Watts levee 1945 1,031 - 
30-42

CHICAGO, ILL., DISTRICT 
TABLE 30-N (Cont'd) OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
1Completed. 
2 Never activated. 
3Settlement of claim in Nov. 1958 [$4,250] increased cost to $1,290,000. 
4 Reported previously by St. Louis District as completed under provisions of section 6, Flood Control Act of 1928. 
5 Authorized in Flood Control Act of 1962. 
6 Includes $55,976 claims. 
7 Classified inactive in November 1971. 
8 Classified inactive in July 1972. 
9 Classified inactive in July 1972. 
'�Classified inactive in Nov. 1971. 
TABLE 30-0 EMERGENCY FLOOD CONTROL ACTIVITIES 
(See Section 40 of Text) 
Projects and Location Federal Cost 
Advance Preparation $ 59,497 
Flood Emergency Operations, Great Lakes Region 84 
Rehabilitation 
Illinois River, Illinois, 6 Levies 118,253 
LaMoine River, Illinois, 2 Levies 5,708 
Mackinaw River, Illinois, 22 Levies 395,042 
Salt Creek, Illinois 1 Levee 288 
Sangamon River, Illinois, 6 Levies 25,136 
Spoon River, Illinois, 16 Levies 372,365 
Miscellaneous Levies, Ill. 1 Levee 24,083 
TABLE 30-P FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 42 of Text) 
Location Requesting Agency Date Completed Federal Cost 
East Arm L. Cal. River Porter County Board March 1975 $50,500 
and Tributaries, Porter and Northwest Indiana 
Co., Indiana Regional Planning 
Commission 
Menominee River City of Marinette, Wis., January 1975 53,000 
and Green Bay, Marinette, City of Menominee, Town- 
Wisc., and Menominee, Wis. ship of Menominee, Wis. 
West Branch DuPage River DuPage County Board June 1975 60,000 
and Tributaries, DuPage 
County, Ill. 
30-43

DETROIT, MICH., DISTRICT* 
This district is composed of the lower peninsula, 
except for a small area in the southwestern 
corner, and the eastern half of the upper peninsula 
of Michigan; northwestern Ohio; and a small 
part of northern Indiana. It includes Michigan 
waters of Lake Michigan; U.S. waters of eastern 
Lake Superior, Lake Huron, Lake St. Clair, and 
western Lake Erie; and their tributary 
watersheds form Au Train Bay, exclusive, in 
Lake Superior, Peninsular Point, and St. Joseph 
River in Lake Michigan, to Sandusky Bay on 
Lake Erie, exclusive. Unless otherwise indicated, 
all depths stated in this report are referred to low 
water datum as follows: Lake Superior, 600 
feet; Lake Michigan-Huron, 576.8 feet; Lake 
Erie, 568.6 feet; and Lake St. Clair, 571.7 feet. 
Elevations in feet are above mean water level at 
Father Point, Quebec (International Great Lakes 
Datum--1955). 
IMPROVEMENTS 
Navigation 
1. Alpena Harbor, Mich. ......... :.. 
2. Arcadia Harbor, Mich ............ 
3. Au Sable Harbor at Au Sable River 
(Oscoda), Mich .................... 
4. Bayport Harbor, Mich. .......... 
5. Black River (Port Huron), Mich. ... 
6. Bolles Harbor, Mich............... 
7. Caseville Harbor, Mich. ........... 
8. Charlevoix Harbor, Mich. ......... 
9. Clinton River, Mich................ 
10. Detroit River, Mich. ............. 
11. Frankfort Harbor, Mich. ........ 
12. Grand Haven Harbor and Grand 
River, Mich. ..................... 
13. Grand Marais Harbor, Mich. ...... 
14. Hammond Bay Harbor, Mich. ..... 
15. Harbor of Refuge at Harbor Beach, 
Lake Huron, Mich. .............. 
16. Holland Harbor, Mich. .......... 
17. The Inland Route, Mich. .......... 
18. Lake St. Clair, Mich., Channels .. 
19. Leland Harbor, Mich. .......... 
20. Les Cheneaux Islands, Channels 
Mich............. ........ 
21. Lexington Harbor, Mich. ........ 
22. Little Lake Harbor, Mich ....... 
23. Ludington Harbor, Mich. ....... 
24. Manistee Harbor, Mich. ........ 
25. Monroe Harbor, Mich. ............ 
26. Muskegon Harbor, Mich. ........ 
27. Ottawa River Harbor, Mich. 
And Ohio ...................... 
28. Pentwater Harbor, Mich. ....... 
29. Portage Lake Harbor, Mich. .... 
30. Port Austin Harbor, Mich. ...... 
Page 
31-2 
31-2 
31-3 
31-3 
31-3 
31-4 
31-5 
31-5 
31-5 
31-6 
31-6 
31-7 
31-8 
31-8 
31-8 
31-9 
31-9 
31-10 
31-10 
31-11 
31-11 
31-12 
31-12 
31-13 
31-13 
31-14 
31-14 
31-15 
31-16 
31-16 
Navigation (cont.) 
31. Port Clinton, Ohio ............. 
32. Port Sanilac Harbor, Mich. ..... 
33. Rouge River, Mich. ............ 
34. Saginaw River, Mich. ........... 
35. St. Clair River, Mich. .......... 
36. St. Joseph Harbor, Mich. ....... 
37. St. Joseph River, Mich. ......... 
38. St. Marys River, Mich. .......... 
39. Saugatuck Harbor and Kalamazoo 
River, Mich. ..................... 
40. Sebewaing River, Mich. ......... 
41. South Haven Harbor, Mich. ..... 
42. Tawas Bay Harbor, Mich. ....... 
43. Toledo Harbor, Ohio ............ 
44. Whitefish Point Harbor, Mich. .. 
45. White Lake Harbor, Mich. ...... 
46. Reconnaissance and Condition 
Surveys .................. 
47. Other authorized navigation 
projects ........................ 
48. Navigation work under special 
authorization ................. 
Beach Erosion Control 
49. Authorized beach erosion control 
projects ...................... 
Flood Control 
50. Kalamazoo River (Battle 
Creek), Mich ............... 
51. Kalamazoo River (Kalamazoo), 
Mich . ............... ...... 
52. Point Place, Toledo, Ohio ........ 
53. Red Run Drain-Lower Clinton 
River, Mich. ... ............ 
* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
31-1 
Page 
31-16. 
31-16 
31-17 
31-18 
31-19 
31-19 
31-20 
31-20 
31-21 
31-22 
31-22 
31-23 
31-23 
31-24 
31-24 
31-25 
31-25 
31-25 
31-25 
31-25 
31-26 
31-26 
31-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (cont.) 
54. River Rouge, Mich. ............. 
55. Saginaw River, Mich. .......... 
56. Sebewaing, (Sebewaing River), 
Mich. .......................... 
57. Inspection of completed flood 
control projects ................ 
58. Other authorized flood control 
projects ....................... 
Page 
31-28 
31-29 
31-30 
31-30 
Flood Control (cont.) 
59. Flood control work under special 
authorization ................... 
60. Survey of North Central 
Lakes ................... ...... 
General Investigations 
61. Surveys ........................ 
31-30 62. Collection and study of basic 
data ........................... 
Page 
31-31 
31-31 
31-34 
31-34 
Navigation 
1. ALPENA HARBOR, MICH. 
Location. At mouth of Thunder Bay River 
which empties into Thunder Bay, Lake Huron. 
Harbor is 100 miles southeast of Cheboygan Harbor, 
Mich. River has its source in Montmorency 
and Alpena Counties, Michigan. (See Lake Survey 
Chart 53.) 
Previous projects. For details see page 1957 of 
Annual Report for 1915 and page 1548 of Annual 
Report for 1938. 
Existing project. Provides for a bay channel 
200 feet wide and 25 feet deep from deep water in 
Thunder Bay to a point 300 feet lakeward of the 
Alpena Light; thence an entrance channel 24 feet 
deep, narrowing to a width of 100 feet at a point 
700 feet upstream from the light; thence a river 
channel 100 feet wide 23 feet deep to Second 
Avenue Bridge; thence 18.5 feet deep and 75 feet 
wide for 1,600 feet to upper limit of Federal project; 
a turning basin at upstream end of project, 
15 feet deep and 3.7 acres in area; a new turning 
basin at river mouth 19 feet deep, trapezoidal in 
shape, with a maximum width of 700 feet including 
the channel width and a maximum 
length of 900 feet along the channel line, including 
removal of existing rubble breakwater; 
and a breakwater about 550 feet long paralleling 
lakeward side of new turning basin. Work 
authorized by the 1965 River and Harbor Act is 
considered inactive. Estimated cost of this portion 
(1969) is $1,100,000 (Federal) and $48,000 
(non-Federal). (See table 31-B for authorizing 
legislation.) 
Local cooperation. Act of October 27, 1965 is 
subject to condition that responsible local interests 
give assurances that they will provide 
lands, easements, and rights-of-way for construction 
and future maintenance of project and aides 
to navigation upon request of the Chief of 
Engineers, including suitable spoil disposal areas 
and necessary retaining dikes, bulkheads and 
embankments therefore, or the costs of such 
retaining works; hold the United States free from 
damages; provide necessary terminal facilities at 
Abitibi Corp; dredge and maintain areas between 
Federal improvement and terminal facilities to 
depths commensurate with improved Federal 
channel. Local cooperation from previous River 
and Harbor Acts is fully complied with. 
Terminal facilities. Several commercial 
docks along Thunder Bay River used primarily 
for receipt of coal and petroleum products. Also a 
municipal marina basin about 0.25 mile 
southwest of river mouth. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys by 
Government forces cost $4,653. Engineering and 
Design on disposal area for polluted dredging 
was performed at a cost of $19,599. 
Condition at end of fiscal year. Existing project 
was completed in 1936. The modification of 
existing project at Alpena Harbor, as authorized 
by the 1966 River and Harbor Act, was 
reclassified into inactive status May 22, 1969 based 
on an unfavorable benefit-cost ratio. Project 
features are in good condition. Controlling depths 
(June 1972) are 21 feet in the lake channel 18.5 in 
the river channel and 15 feet in the turning basin. 
Total costs to end of fiscal year for existing project 
were $642,574 of which, $318,505 was for new 
work and $324,069 for maintenance. 
2. ARCADIA HARBOR, MICH. 
Location. On east shore of Lake Michigan, 193 
miles northeasterly from Chicago and 15 miles 
northerly from Manistee, Michigan. (See Lake 
Survey Chart 77.) 
Existing project. Provided for maintenance 
dredging of the existing harbor built by private 
interests for a period of five years. The five years 
covered by this project were the calendar years 
1905 to 1909, inclusive. Funds were also appropriated 
and maintenance was performed in 
calendar years 1911, 1912, 1913 and 1915. There 
is at present no approved project for the improve- 
31-2

DETROIT, MICH., DISTRICT 
ment of this harbor. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. Dock facilities are considered 
adequate for existing recreational traffic. 
Operations and results during fiscal 
year. Maintenance: Condition surveys by 
Government forces cost $5,423. 
Condition at end of fiscal year. Existing project 
was completed in 1909. Total cost at end of 
fiscal year for existing project was $193,848. 
3. AU SABLE HARBOR AT AU 
SABLE RIVER (OSCODA), MICH. 
Location. Au Sable River and village of Oscoda, 
Mich., are on west shore of Lake Huron, 8 
miles north of Au Sable Point, northeast limit of 
Saginaw Bay. (See Lake Survey Chart 52.) 
Previous project. For details see pages 336 
and 2453 of Annual Report for 1892. 
Existing project. Riprapping outer 200 feet of 
north pier at mouth of Au Sable River, dredging 
an entrance channel 12 feet deep and dredging 
between piers and upstream to State highway 
bridge 10 feet deep. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small timber pile 
wharves used primarily by commercial 
fishermen and pleasure craft operators; also a 
private marina basin east of U.S. Highway 23 
Bridge. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys by 
Government forces cost $1,444. Engineering and 
design for rehabilitation of North and South Jetties 
was completed at a cost of $32,210. A contract 
was awarded for this work and is approximately 
3% complete, at a cost of $74,999. Supervision and 
administration in connection with contract cost 
was $3,592. Chicago District's Hydraulic Dredge 
Depoe Bay performed maintenance dredging 
removing 9,500 cubic yards place measure of 
shoal material at a cost of $36,097. Repairs to safety 
features were made at a cost of $233. Engineering, 
design, construction layouts, surveys, supervision, 
and administration cost $4,487. 
Condition at end of fiscal year. Existing project 
was completed in 1962. Total costs to end of 
fiscal year for existing project were $1,701,212 of 
which $94,990 was for new work (including $16,- 
400 contributed funds) and $1,606,202 for 
maintenance. 
4. BAY PORT HARBOR, 
MICH. 
Location. On Wild Fowl Bay on east shore of 
Saginaw Bay about 10 miles south of Caseville, 
Mich. (See Lake Survey Chart 52.) 
Existing project. Provides for a channel 6 feet 
deep and 50 feet wide extending 5,750 feet from 6- 
foot contour in Saginaw Bay to intersection of 
private service channels to be dredged by local interests. 
(See table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small wharves 
used primarily by commercial fishermen. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys were performed 
by Government forces at a cost of $731. 
Engineering and design on disposal area for 
polluted dredging was performed at a cost of 
$355. 
Condition at end of fiscal year. Existing project 
was completed in 1967. Total cost of project to 
end of fiscal year is $106,183 of which $93,597 is 
for new work and $12,231 for maintenance. 
5. BLACK RIVER (PORT 
HURON), MICH. 
Location. This river has its source in the 
northern part of Sanilac County, Mich., is about 
60 miles long, and flows in a southeasterly direction 
into the St. Clair River. (See Lake Survey 
Chart 43.) 
Previous projects. For details see page 1441 of 
Annual Report for 1916, and 1554 of Annual 
Report for 1938. 
Existing project. This provides for a channel 
20 feet deep from deep water in St. Clair River to 
the Grand Trunk Western Railroad Bridge, 160 
feet wide at the mouth, decreasing to 100 feet 
about 800 feet from the mouth, thence 100 feet 
wide for 2,600 feet, decreasing to 75 feet for a distance 
of 4,800 feet, widening 2 bends to 100 feet, 1 
at the foot of 12th Street, and the other below the 
Grand Trunk Western Railroad Bridge; for a 
settling basin 75 feet wide and 20 feet deep, beginning 
at the Grand Trunk Western Railroad 
Bridge in Port Huron and extending upstream a 
distance of about 2,300 feet; and then for a distance 
of 2.6 miles as a 100-foot wide river channel, 
8 feet deep to the I-94 bridge where it decreases to 
6 feet deep and continues to the vicinity of the 
31-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Black River Drainage Canal with suitable widening 
where required at bends in the channel. The 
estimated (1974) Federal cost for new work is 
$300,000 excluding $305,000 to be contributed by 
local interests (280,000 cash contribution and 
$25,000 for spoil disposal retaining dikes). The 
project modification authorized by the Act of 
August 30, 1935 is considered to be inactive and is 
excluded from the foregoing cost for new work. 
The cost of this modification was last revised in 
1954 and was estimated to be $194,000 exclusive 
of $194,000 to be contributed by local interests. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
completed portions of project. Assurances required 
by Act of August 30, 1935 have not been 
provided. Responsible local interests must furnish 
assurances that they will contribute one-half 
of the initial cost of the improvements; provide all 
lands or easements necessary to execution of the 
project; remove existing Tenth Street bridge, or 
replace it with a satisfactory structure; and furnish 
assurances that the United States will be 
protected from all claims for damages incident to 
the improvements. Improvement authorized on 
April 23, 1970 under authority of Section 107 is 
subject to the condition that local interests contribute 
in cash 50 percent of the estimated first 
cost of construction of the recommended channel 
improvement, presently estimated at $280,000 
provide without cost to the United States all 
lands, easements, and rights-of-way required for 
the construction and subsequent maintenance of 
the project, including suitable areas required for 
disposal of spoil and any necessary retaining 
dikes, or the cost of such retaining dikes, presently 
estimated at $25,000; hold and save the United 
States free from damages due to the construction 
and maintenance of the improvement; provide 
and maintain without cost to the United States 
necessary small craft mooring and servicing 
facilities, and vehicular parking areas with adequate 
sanitary facilities; and provide adequate 
facilities and establish and enforce regulations 
concerning discharge of untreated sewage, garbage, 
and other pollutants in the waters of the improvement 
by users in accordance with 
applicable laws or regulations of authorities 
responsible for pollution prevention and control. 
Terminal facilities. There are docks on both 
sides of Black River, near its mouth, and between 
these docks and the upper limit of improvement 
there are 5 other docks varying in length from 100 
to 500 feet. All docks are privately owned and are 
restricted to the use of the owners. The facilities 
are considered adequate for existing commerce. 
Public recreational boating facilities constructed 
by the State and local agencies are available as 
are privately owned and operated marinas. 
Operations and results during fiscal 
year. New Work: The contract awarded last 
fiscal year for dredging was started and is approximately 
61% complete at a cost of $209,184. 
The contractor used a 16' hydraulic dredge and 
removed 71,372 cubic yards, place measure, of 
material. Engineering and design during construction 
cost $4,762. Supervision and administration 
of contract was $28,320. 
Maintenance: Condition surveys were performed 
by Government forces at a cost of $1,129. 
Condition at end of fiscal year. All work, except 
that authorized by Act of August 30, 1935 
and the latest modification, has been completed. 
Total costs for existing project to end of fiscal year 
were $937,224 of which 302,057 (includes $128,- 
284 contributed funds) was for new work and 
$431,105 for maintenance. 
6. BOLLES HARBOR, MICH. 
Location. On west shore of Lake Erie at 
mouth of La Plaisance Creek, 7 miles southwest of 
Monroe, Mich. (See Lake Survey Chart 37.) 
Existing project. Provides for an entrnace 
channel in Lake Erie, 8 feet deep and 80 feet wide 
from deep water to a point opposite the outer end 
of existing jetty, thence widening to 100 feet at 
creek mouth; an access channel in La Plaisance 
Creek, 6 feet deep and 100 feet wide at the mouth 
widening to 120 feet and extending to the first 
bend, thence narrowing to 50 feet wide and continuing 
at that width to the La Plaisance Road 
bridge; a steel sheet pile revetment, about 200 feet 
long, located along Michigan State Conservation 
Department property on west side of channel at 
creek mouth. Project also provides for inclusion of 
existing 400--foot long steel sheet pile jetty constructed 
by Michigan State Waterways Commission 
at the mouth of La Plaisance Creek. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. The Monroe Boat Club 
and three marinas provide facilities adequate for 
existing recreational boat traffic. There is also a 
public launching ramp and parking area at Conservation 
Department fishing site at creek 
mouth. 
Operations and results during fiscal 
year. New Work: An adjustment of $59,122 was 
made in the cost of the contract for dredging and 
breakwater construction that was terminated in 
fiscal year 1969. Maintenance: Condition surveys 
were performed by Government forces at a cost of 
$2,388. Engineering and design on confined disposal 
area for polluted dredgin? was continued at 
31-4

DETROIT, MICH., DISTRICT 
a cost of $80,176. 
Condition at end of fiscal year. The existing 
project was completed in 1970. Controlling 
depths (June 1974) were 5 feet in the bay channel 
and 3 to 5 feet in the river channel. Total costs to 
end of fiscal year were $642,609 of which $474,- 
509 was for new work ($255,000 contributed 
funds) and $168,090 for maintenance. 
7. CASEVILLE HARBOR,, MICH. 
Location. At mouth of Pigeon River on south 
shore of Saginaw Bay about 17 miles southwest of 
Port Austin, Mich. (See Lake Survey Chart 5.) 
Existing project. A small craft harbor of 
refuge consisting of a breakwater protected 
channel extending from the 10-foot contour in 
Saginaw Bay into Pigeon River. Project depths 
are 10 and 8 feet. For additional details see page 
1320 of Annual Report for 1963. Widening river 
channel from 50 to 60 feet for about 1,000 feet, 
with widening to 80 feet in upper 300-foot reach, 
is considered inactive. Estimated (1963) cost of 
this portion of project is $30,000. (See Table 31-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Complete public boating 
facilities constructed by State and local agencies 
are available in addition to privately owned and 
operated marinas. 
Operations and results during fiscal 
year. Maintenance: Condition surveys by 
Government forces cost $1,895. Engineering and 
design on disposal area for polluted dredging was 
performed at a cost of $2,115. 
Condition at end of fiscal year. The existing 
project was completed in 1964 except for the inactive 
portion of the project. Total costs to end of 
fiscal year were $640,712 of which 587,314 was 
for new work (including $293,657 contributed 
funds) and $53,398 for maintenance. 
8. CHARLEVOIX HARBOR, 
MICH. 
Location. On east shore of Lake Michigan, 276 
miles northeasterly from Chicago, Ill., and 75 
miles northerly from Frankfort, Mich. (See Lake 
Survey Chart 789.) 
Existing project A channel 18 feet deep from 
that depth in Lake Michigan to that depth in Lake 
Charlevoix; protected where needed by piers and 
revetments. For additional details see page 1476 
of Annual Report for 1962. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small landing 
olaces in Round Lake at Charlevoix for handling 
fish and miscellaneous commodities, a wharf for 
petroleum products at west end of Lake 
Charlevoix, and coal wharves at Advance and 
Boyne City. Charlevoix, Boyne City, and East Jordan 
provide public docks for small craft. 
Facilities considered adequate for existing commerce. 
Operations and results during fiscal 
year. New Work: Preparation of a Detailed Project 
Report was performed by Government forces 
at a cost of $12,400. Maintenance: Condition surveys, 
environmental impact statement, miscellaneous 
inspection services were performed by 
Government forces at a cost of $8,598. The contract 
awarded in Fiscal year 1975 for Rehabilitation 
of Section I South Revetment is approximately 
94% complete at a cost of $356,073. Engineering 
design, construction layouts, supervision and 
administration cost $31,171. 
Condition at end of fiscal year. Existing project 
was completed in 1939. The structures 
recommended for repair as a result of a survey 
conducted in 1964 have been completed. The 
remaining navigation structures are in generally 
good condition. Total costs to end of fiscal year 
were $2,943,364 of which $94,623 was for new 
work, $1,660,593 for maintenance (Emergency 
Bank Protection $46,352), and $1,129,396 for 
rehabilitation. 
9. CLINTON RIVER, MICH. 
Location. Has its source in Oakland County, 
Mich., flows easterly about 60 miles and empties 
into Anchor Bay in northwestern part of Lake St. 
Clair. (See Lake Survey Chart 42.) 
Previous projects. For details see page 1958 of 
Annual Report for 1915, and page 1556 of Annual 
Report for 1938. 
Existing project. An entrance channel in 
Anchor Bay 8 feet deep, 300 feet wide at 8-foot 
depth contour in the bay, gradually decreasing to 
50 feet wide at about 1,000 feet upstream from 
mouth of Clinton River, a length of about 4,600 
feet; a channel 8 feet deep and 50 feet wide in the 
river about 38,700 feet long from entrance 
channel upstream to Mt. Clemens at Cass 
Avenue; closing old channel and making a cutoff 
at Shoemakers Bend; closing Catfish Channel; 
construction of revetments as needed in the river; 
and a harbor basin, 5 feet deep and 11 acres in 
area at entrance along bay channel, protected by 
breakwaters on north and south sides. (See Table 
31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. River is used exclusively 
31-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
by recreational craft. There are numerous public 
and private piers and wharves along river below 
the city. They are considered adequate. 
Operations and results during fiscal 
year. Maintenance: Condition surveys by 
Government forces cost $859. Engineering and 
design on confined disposal area for polluted 
dredging was performed at a cost of $14,998. 
Condition at end of fiscal year. Existing project 
was completed in 1966. Total costs to end of 
fiscal year were $1,254,568 of which $234,546 was 
for new work, $730,269 for maintenance, and 
$289,752 contributed funds for new work. 
10. DETROIT RIVER, MICH. 
Location. One of the Great Lakes connecting 
channels, 31 miles long and flows south from 
Lake St. Clair to Lake Erie. (See Lake Survey 
Chart 41.) 
Previous projects. For details see page 1958 of 
Annual Report for 1915, and page 1541 of Annual 
Report for 1938. 
Existing project. Improving Detroit River 
main channels to provide 25.5-foot draft navigation; 
improving certain auxiliary and side 
channels; and construction of various water level 
and crosscurrent control structures. Details are 
in accompanying table 31-C. Project depths are 
referred to local low water datum planes which 
correspond to low water datums for Lakes St. 
Clair and Erie, 571.7 and 568.6 feet above mean 
water level at Father Point, Quebec (International 
Great Lakes Datum--1955.) (See Table 
31-B for authorizing legislation.) 
Estimated (1975) cost for new work, exclusive 
of amounts expended on previous projects, is 
$145,726,000. 
Local cooperation. Fully complied with for 
completed portions of project. For Trenton 
Channel modification approved May 17, 1950, 
responsible local agencies must furnish lands, 
rights-of-way, and spoil disposal areas for construction 
and future maintenance and hold the 
United States free from damages. Assurances required 
by act of May 17, 1950, have not been 
provided. No local cooperation is required for 
modifications authorized by acts of July 1946 and 
March 1956. For Trenton Channel modification 
approved August 13, 1968, local cooperation requirements 
are to hold and save the United States 
free from damages due to construction and 
maintenance of the improvement; when and 
where needed, provide and maintain depths in 
berthing areas and local access channels serving 
the terminals commensurate with the depths 
provided in the related project areas; accomplish 
alterations to the lower Grosse Ile Bridge and to 
submarine utility crossings, as required by the 
improvement; construct a fully integrated steel 
plant at the Gibraltar site; provide without cost to 
the United States all lands, easements, and 
rights-of-way required for construction and subsequent 
maintenance of the project including 
compensating dikes, and for aids to navigation, 
upon the request of the Chief of Engineers to be 
required in the general public interest for initial 
and subsequent disposal of excavated materials. 
All new work, authorized for Trenton Channel is 
considered inactive. 
Terminal facilities. Numerous commercial 
installations used for handling coal, iron ore, 
limestone, steel products, petroleum products, 
and other items such as overseas general cargo. 
Detail on actual port and harbor facilities is in 
Port Series No. 45 (revised 1961) prepared and 
published as part 2 by Board of Engineers for 
Rivers and Harbors. Information on port and 
steamship services is prepared and published as 
part I by Port Development Staff, U.S. Department 
of Commerce. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, Hi-Fix 
surveys support of Water Control Center and miscellaneous 
inspection services and reports were 
performed by Government forces at a cost of 
$291,054. The U.S. Hopper Dredge Hoffman performed 
maintenance dredging removing 546,589 
cubic yards, bin measure, of shoal material at a 
cost of $291,091. Repairs to the Compensating 
Dikes were performed at a cost of $122,818. Location 
and removal of obstructions in rock channels 
continued during fiscal year by U.S. 
Derrickboats HURON and MICHIGAN at a cost 
of $545,544. Engineering, design, layouts, surveys, 
Supervision and administration cost $13,- 
408. Engineering and Design on confined disposal 
area for polluted dredging was performed 
at a cost of $142,596. 
Condition at the end of fiscal year. Latest 
modification of connecting channels project in the 
Detroit River is complete except for compensating 
works. All work in Trenton Channel is 
complete except extension of turning basin 
authorized by Act of 13 August 1968. Pertinent 
data concerning channels covered by project at 
end of fiscal year is set forth in Table 31-C. 
Costs for existing project were $86,091,444 of 
which $74,499,885was for new work ($72,969,197 
regular funds and $1,530,688 Public Works 
Funds) and $11,591,559 for maintenance. 
11. FRANKFORT HARBOR, MICH. 
Location. On east shore of Lake Michigan, 204 
31-6

DETROIT, MICH., DISTRICT 
miles northeasterly from Chicago and 28 miles 
northerly from Manistee, Mich. (See Lake Survey 
Chart 77.) 
Existing project. Provides for constructing an 
exterior basin in Lake Michigan formed by two 
breakwaters, 450 feet apart at the outer ends, 
diverging at an angle of about 90 degrees, the 
main arm and shore connection on north 
breakwater are 972 and 1,000 feet long, respectively, 
and the main arm and shore connection of 
south breakwater 1,188 and 1,400 feet long, 
respectively; for removing 801 feet of north and 
1,172 feet of south pier; dredging basin 20 feet 
deep and 800 feet wide at entrance, decreasing 
toward new pier heads to 600 feet wide, dredging 
approach and entrance channel through outer 
basin to a depth of 24 feet from deep water in Lake 
Michigan to a point 500 feet landward of opening 
between breakwaters, over the entire width outside 
the breakwaters and to a maximum width of 
500 feet inside the breakwaters; thence to 23 feet 
deep through inner portion of outer basin to outer 
end of north pier, over widths decreasing from 
500 to 160 feet; and thence to 22 feet deep between 
the piers to the inner basin in Lake Betsie; dredging 
an 18-foot deep interior basin in Lake Betsie 
from within 50 feet of existing structures on the 
west and extending eastward about 1,550 feet to 
easterly boundary and from within 50 feet of existing 
structures on the north and extending 
southward 800 feet to the southerly boundary; 
dredging a recreational craft anchorage area 10 
feet deep and 300 feet wide, extending 600 feet 
eastward of the east limit of the interior basin, 
with its north side in line with the north limit of 
the basin. Breakwaters and shore connections are 
built of concrete caissons and piling capped with 
concrete. Inner piers and revetments are built of 
stonefilled timber cribs and piling, all capped 
with concrete, except for 476 feet of south revetment 
which consists of steel sheet piling. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. FUlly complied with. 
Terminal facilities. Two car ferry slips on 
south shore and several docks along north shore of 
Lake Betsie. The city and State provide a 
recreational docking facility on north side of Lake 
Betsie which is open to all on equal terms. There is 
also a marine railway capable of handling small 
craft. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, environmental 
impact statements and miscellaneous 
inspection services were performed by 
Government forces at a cost of $4,862. The U.S. 
Hopper Dredge HAINS performed maintenance 
dredging removing 35,888 cubic yards, bin 
measure, of shoal material, at a cost of $45,113. 
Engineering, design, supervision and adminsitration 
cost $8,425. Engineering and design on 
confined disposal area for polluted dredging was 
continued at a cost of $13,799. Engineering and 
design studies under Section 111 P.L. 90-483 for 
prevention or mitigation of shore damage attributable 
to Federal navigation works was performed 
at a cost of $25,000. 
Condition at end of fiscal year. Existing project, 
with exception of latest modification which 
was completed in 1969, was completed in 1939. 
Breakwaters, shore connections, and revetments 
are in generally good condition. For additional 
details on completion of existing project see page 
1474 of Annual Report for 1962. Total costs for existing 
project to end of fiscal year were $4,047,031 
of which $1,955,159, (including $31,709 contributed 
funds) was for new work, $1,817,096 for 
maintenance, and $274,776 for rehabilitation. 
12. GRAND HAVEN HARBOR AND 
GRAND RIVER, MICH. 
Location. Harbor is on east shore of Lake 
Michigan, 108 miles northeasterly from Chicago, 
Ill., and 23 miles northerly from Holland, Mich. 
River rises in Jackson County, Mich., and flows 
260 miles westerly into Lake Michigan. (See Lake 
Survey Chart 765, and Geological Survey Grand 
Rapids quadrangle.) 
Previous projects. For details see page 1949 of 
Annual Report for 1915, and page 1481 of Annual 
Report for 1938. 
Existing project. An entrance channel 
protected by parallel piers and revetments at 
mouth of Grand River, a deep draft channel in 
river extending to Spring Lake, a turning basin, 
and a shallow draft channel in river extending 
14.5 miles upstream to Bass River. Project depths 
are 23 feet in entrance channel, 21 feet in river to 
turning basin, 18 feet in turning basin and 
channel to Spring Lake, and 8 feet in upper 
Grand River channel. For additional details see 
page 1461 of Annual Report for 1962. Dredging 
on northerly side of inner channel is considered 
inactive. Estimated cost of this portion (1954) is 
$38,600. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves exist for 
handling coal, limestone, sand and gravel, 
petroleum products, fish and miscellaneous commodities. 
There is also a car ferry slip which is inactive. 
The State and local agencies provide 
recreational boating facilities which are open to 
31-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
all on equal terms. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, operation 
of safety features, environmental impact 
statements and miscellaneous inspection services 
were performed by Government forces at a cost of 
$26,252. A contract awarded late last fiscal year 
for maintenance of navigation structures was 
completed at a cost of $15,547. Repair to the 
revetments were made by hired labor at a cost of 
$11,374. The U.S. Hopper Dredge HAINS performed 
maintenance dredging removing 134,943 
cubic yards bin measure of shoal material at a 
cost of $272,757. Maintenance of disposal area 
and pipeline equipment was performed at a cost 
of $8,205. Chicago District's Hydraulic Dredge 
DEPOE BAY performed maintenance dredging 
removing 36,700 cubic yards, place measure, of 
shoal material at a cost of $68,394. Engineering, 
design, maintenance of safety features, construction 
layouts, supervision and administration cost 
$16,266. The contract for construction of a confined 
disposal area was completed at a cost of 
$556,498. Additional hopper dredging handling 
cost was $35,000. Engineering, construction survey 
and layouts, supervision and administration 
in connection with this contract cost $31,682. 
Total fiscal year cost under the Dike Disposal 
Program was $623,180. Engineering and design 
studies under Section 111 P.L. 90-483 for prevention 
or mitigation ofshore damage attributable to 
Federal navigation works was performed at a 
cost of $69,964. 
Condition at end of fiscal year. Existing project 
was substantially completed in 1949. For additional 
details on completion of existing project 
see page 1463 of Annual Report for 1962. Project 
structures are generally in good condition. Total 
costs of existing project to end of fiscal year were 
$12,172,537 of which $1,283,469 was for new 
work, $10,075,455 for maintenance and $813,613 
for rehabilitation. 
13. GRAND MARAIS HARBOR, 
MICH. 
Location. On south shore of Lake Superior, 93 
miles west of Sault Ste. Marie, Mich. (See Lake 
Survey Chart 92.) 
Existing project Provides for a channel 
protected by parallel piers and for closing natural 
entrance channel with a pile dike. Project depths 
are 18 feet between piers and 20 feet in lake approach. 
For additional details see page 1449 of 
Annual Report for 1962. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small piers, a 
Coast Guard Station, and a small boat pier and 
launching ramp built by the State of Michigan 
provide facilities adequate for present traffic. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services were performed by 
Government forces at a cost of $5,794. The 
feasibility study for replacement of the pile dike 
was performed by Government forces at a cost of 
$64,572. Rehabilitation: An adjustment of cost 
was made to the contract for rehabilitation of east 
and west pier in the amount of $1,899. 
Condition at end of fiscal year. Existing project 
is complete except for widening a portion of 
channel from 250 to 300 feet. The 1954 estimated 
cost of this inactive part of the project is $10,000. 
For additional details on condition and completion 
of existing project see page 1292 of Annual 
Report for 1963. 
14. HAMMOND BAY HARBOR, MICH. 
Location. On northwest shore of Lake Huron, 
35 miles southeast of straits of Mackinac. (See 
Lake Survey Chart 60.) 
Existing project. Provides for a harbor of 
refuge, protected by breakwater structures, extending 
to 12-foot depth contour in the lake; for 
dredging a harbor basin 10 feet deep; and for 
dredging an entrance channel 12 feet deep. 
Local cooperation. Fully complied with. 
Terminal facilities. Public facilities being 
planned by State and local agencies. Plans and 
specifications are complete, but construction has 
not started. 
Operations and results during fiscal 
year. Maintenance: Condition surveys were performed 
by Government forces at a cost of $2,618. 
Engineering and design studies under Section 
111 P.L. 90-483 for prevention or mitigation of 
shore damage attributable to Federal navigation 
works was performed at a cost of $19,561. 
Condition at end of fiscal year. Existing project 
was completed in 1965. 
15. HARBOR OF REFUGE AT 
HARBOR BEACH, LAKE 
HURON, MICH. 
Location. On west shore of Lake Huron about 
60 miles north of Port Huron, Mich. (See Lake 
Survey Chart 51.) 
Existing project. Harbor of refuge protected 
by three breakwaters; a main entrance 23 feet 
31-8

DETROIT, MICH., DISTRICT 
deep; and an anchorage area 21 feet deep. For additional 
details see page 1485 of Annual Report 
for 1962. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Coal and limestone are 
received at a private wharf. In addition there is a 
public recreational craft pier, a Coast Guard pier, 
and several small installations engaged in docking 
and servicing light-draft commercial and 
recreational vessels. These facilities satisfy 
current commerce and traffic requirements. 
Operations and results during fiscal 
year. Maintenance: Condition surveys were performed 
by Government forces at a cost of $2,578. 
Engineering and design on confined disposal 
area for polluted dredging was performed at a 
cost of $45,999. 
Condition at end of fiscal year. Existing project 
was completed in 1928. For additional details 
on completion of existing project see page 1485 of 
Annual Report for 1962. The structures are in 
generally good condition. Total cost to end of 
fiscal year were $3,988,177 of which $1,200,598 
for new work, $2,593,075 for maintenance, $194,- 
504 for rehabilitation. 
16. HOLLAND HARBOR, MICH. 
Location. On east shore of Lake Michigan 95 
miles northeasterly from Chicago, Ill., and 23 
miles southerly from Grand Haven, Mich. (See 
Lake Survey Chart 763.) 
Previous project. For details see page 1948 of 
Annual Report for 1915, and page 1478 of Annual 
Report for 1938. 
Existing project. An outer breakwater 
protected approach channel in Lake Michigan, an 
entrance channel to Lake Macatawa protected by 
piers and revetments, a channel through Lake 
Macatawa into Black River, and a turning basin. 
Project depths are 23 feet in outer portion of approach 
channel decreasing to 21 feet at outer end 
of inner piers, 21 feet to upper end of project, and 
18 feet in turning basin. For additional details see 
page 1458 of Annual Report for 1962. Widening 
bend of entrance channel into Lake Macatawa is 
considered inactive. Estimated cost of this portion 
(1956) is $449,500. (See Table 31-B for 
authorizing legislation.) 
Local cooperation, Fully complied with for 
completed portions of project. Work authorized 
by act of 1954 is subject to condition that work on 
either or both proposed modifications may be undertaken 
by the United States provided local interests 
furnish all lands except 1.5 acres of 
Federal lands, easements, rights-of-way, and 
suitable spoil disposal areas for initial work and 
future maintenance; remove buildings and other 
structures, except existing revetments, from 
lands to be furnished; and hold the United States 
free from damages. 
Terminal facilities. Wharves are at inner end 
of Lake Macatawa, and used for handling coal, 
building materials, petroleum products, and miscellaneous 
commodities. Two shipbuilding yards 
are on south shore of the lake. Holland provides a 
public wharf for small craft. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, environmental 
impact statements and miscellaneous 
inspection services were performed by 
Government forces at a cost of $7,675. 
Maintenance of the navigation structures were 
performed by hired labor at a cost of $537. The 
U.S. Hopper Dredge HAINS performed 
maintenance dredging removing 90,155 cubic 
yards, bin measure of shoal material at a cost of 
$90,155 cubic yards, bin measure, of shoal 
material at a cost of $90,798. Engineering, 
design, layouts, surveys, maintenance of safety 
features, supervision and administration cost $9,- 
097. Engineering and design on confined disposal 
area for polluted dredging was continued at a cost 
of $160,282. Engineering and design studies under 
Section 111 P.L. 90-483 for prevention or 
mitigation of shore damage attributable to 
Federal navigation works was performed at a 
cost of $69,901. 
Condition at end of fiscal year. Existing project, 
with exception of widening bend in revetted 
entrance channel authorized by Act of September 
3, 1954, was completed in 1957. All structures are 
generally in good condition. For additional 
details on completion of existing project see page 
1460 of Annual Report for 1962. Cost of existing 
project to end of fiscal year was $771,841 for new 
work ($559,516 regular funds, $176,620 for 
previous project and $35,705 contributed funds), 
$4,065,634 regular funds for maintenance, and 
$502,452 regular funds for rehabilitation, for a 
total of $5,163,307. 
17. THE INLAND ROUTE, MICH. 
Location. A series of interconnected lakes and 
streams stretching across northern tip of Lower 
Peninsula of Michigan, and extends from Conway 
near Lake Michigan to Cheboygan on Lake 
Huron; a distance of 35 miles. Crooked and Indian 
Rivers are connecting channels in the waterway. 
(See Lake Survey Chart 660). 
31-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. Provides for a channel 30 
feet wide and 5 feet deep, with necessary widening 
at bends, through Crooked and Indian Rivers, 
and Crooked, Burt, and Mullett Lakes, and from 
Conway (west end of Crooked Lake) to navigation 
lock at Cheboygan; in Pickerel Channel from 
Pickerel Lake to Crooked Lake. It also provides 
for suitable jetties at head of Indian River. The 
addition of a lock and dam was approved by the 
Chief of Engineers on September 2, 1964, to correct 
a design deficiency. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal Facilities. None for commercial 
cargo handling exist along the Crooked and Indian 
Rivers. Numerous small privately owned 
timber piers and wharves, some equipped with 
covered boat wells for serving and storing 
recreational craft, have been constructed. Landings 
maintained by hotel and resort operators 
are open to the public for transfer of passengers. 
Public docks are at Conway and Oden on Crooked 
Lake; the village of Indian River, Topinabee, and 
Mullett Lake Village on Mullett Lake; and at 
Cheboygan. About 30 highways dead end at the 
water's edge, permitting public access for 
various marine activities. Dock facilities are considered 
adequate for existing traffic. 
Operations and results during fiscal 
year. Maintenance: The navigation lock was 
maintained and operated on a two shift basis from 
15 April 1975 through 15 November 1975. The 
lock was reopened for navigation on 15 April 1975 
and was operated on a two shift basis. During the 
fiscal year, a total of 9,822 vessels passed through 
the lock in 7,540 lockages. Cost for the fiscal year 
was $63,008; all hired labor. Channels and 
Canals: Condition surveys and miscellaneous inspection 
services, cooperative stream gaging 
were performed by Government forces at a cost of 
$28,020. Engineering and design on confined disposal 
area for polluted dredging was performed 
at a cost of $7,999. 
Condition at end of fiscal year. The existing 
project was completed in 1958. The lock and dam 
were completed in fiscal year 1968. For additional 
details see page 1382 of Annual Report 
for 1960. Total costs in end of fiscal year were $1,- 
605,702 of which $770,222 was for new work and 
$687,481 for maintenance with $148,000 contributed 
by local interests. 
18. LAKE ST. CLAIR, MICH. 
CHANNELS 
Location. Lake St. Clair, a section of Great 
Lakes connecting channels, is an expansive 
shallow basin having a vessel track length of 
about 15 miles from mouth of St. Clair River to 
head of Detroit River. (See Lake Survey Chart 
42.) 
Previous projects. For details see page 2882, 
Annual Report for 1896; pages 1957-58, Annual 
Report for 1915; and page 1539, Annual Report 
for 1938. 
Existing project. An improved channel 
through Lake St. Clair 800 feet wide, 27.5 feet 
deep, and about 14.5 miles long; extending from 
mouth of Southeast Bend cutoff channel at lower 
end of St. Clair River to head of Detroit River 
Channel. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. None. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, support 
of Water Control Center, environmental impact 
statements and miscellaneous inspection services 
cost $59,582. The contract awarded last fiscal 
year for construction of diked disposal is approximately 
50% complete at a cost this fiscal 
year of $1,478,545. Purchase of real estate and 
real estate activities cost $347,577. Engineering, 
design, construction layouts, supervision and administration 
cost $225,589. Total fiscal year cost 
under the Diked Disposal Program was $2,051,- 
711. 
Condition at end of fiscal year. Total costs for 
existing project at end of fiscal year were $12,- 
241,889 of which $7,019,237 was for new work 
($6,010,582 regular funds and $1,008,595 public 
works funds) and $5,222,711 for maintenance. 
19. LELAND HARBOR, MICH. 
Location. A light-draft harbor on eastern 
shore of Lake Michigan at mouth of Carp River, 
about 40 miles north of Frankfort, Mich., and 40 
miles southwest of Charlevoix, Mich. (See Lake 
Survey Chart 705.) 
Existing project. Provides for a harbor of 
refuge consistingof a breakwater about 1,200 feet 
long, a protected anchorage and maneuver area 
about 3 acres in extend and 10 feet deep, a 12-foot 
deep flared approach channel decreasing in 
width to 90 feet, an existing south pier 440 feet 
long, a 35-foot long cellular extension to south 
pier, an entrance channel 6 feet deep and 40 feet 
wide extending to mouth of Carp River, and for 
elimination of existing north pier. (See Table 31- 
B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminalfacilities. Privately owned wharves 
31-10

DETROIT, MICH., DISTRICT 
on each side of river below the dam which is 400 
feet above the river mouth. These wharves serve 
the local fishing interests and recreational craft. 
Public facilities are operated by the State and 
local agencies. All available dockage space is 
utilized. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services were performed by 
Government forces at a cost of $6,339. 
Maintenance dredging was performed by 
Chicago District's Hydraulic Dredge DEPOE 
BAY removing 8,000 cubic yards, place measure, 
of shoal material at a cost of $36,056. Engineering, 
design, layouts, surveys, supervision and administration 
cost $3,897. 
Condition at end of fiscal year. The existing 
project was completed in 1932 except for the 
authorization of 1962 which was completed in 
1967. Total cost of existing project to the end of 
fiscal year was $1,355,264, of which $1,027,089 
was for new work and $328,175 for maintenance. 
20. LES CHENEAUX ISLANDS 
CHANNELS, MICH. 
Location. Along the north shore of Lake 
Huron, about 20 miles northeast of Mackinac 
Island, Michigan. (See Lake Survey Chart 601.) 
Existing project Provides for removing 
shoals from Les Cheneaux Islands Channels on 
the presently designated Small Boat Course, including 
the Middle Entrance between Marquette 
and Little LaSalle Islands, to provide a depth of 
seven feet over a minimum width of 100 feet, with 
suitable widening where required at bends in the 
channel. (See Table 31-B for authorizing legislation). 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned 
marinas, open to the public, are located at Hessel 
and Cedarville. There are also numerous other 
docks located on the islands which are not open to 
the general public. These facilities are considered 
adequate for existing commerce and vessel traffic.
Operations and results during fiscal 
year. Maintenance: Condition surveys were performed 
by Government forces at a cost of $1,589. 
Engineering and design on confined disposal 
area for polluted dredging was performed at a 
cost of $3,999. 
Condition at end of fiscal year. Existing project 
was completed during fiscal year 1971. 
21. LEXINGTON HARBOR, MICH. 
Location. On southwest shore of Lake Huron, 
20 miles north of Port Huron, Michigan. (See 
Lake Survey Chart 51.) 
Existing project. Provides for two offshore 
breakwaters opening to the southeast and totaling 
about 2,400 feet long with provisions for 
recreational fishing on the main breakwater; an 
anchorage and maneuver area of about 5 acres, 8 
feet deep; and a flared approach channel 10 feet 
deep, decreasing to 160 feet in width through the 
breakwaters. Project also provides for 
recreational fishing facilities. Estimated (1975) 
Federal cost for new work is $1,900,000 excluding 
$1,225,000 to be contributed by local interests. 
Estimated total cost for local interests is 
$3,160,000 (See Table 31-B for authorization 
legislation.) 
Local cooperation. Responsible local interests 
must furnish assurances that they will contribute 
in cash 39 percent of the first cost of construction 
of the general navigation facilities, such contribution, 
presently estimated at $876,000 to be paid in 
a lump sum before start of construction, subject to 
final adjustment after actual costs are determined; 
provide lands, easements, and rights-ofway 
for construction and future maintenance and 
for aids to navigation upon request of the Chief of 
Engineers, including suitable spoil-disposal 
areas and necessary retaining dikes, bulkheads, 
and embankments therefor or cost of such retaining 
works; hold the United States free from 
damages; provide and maintain necessary mooring 
facilities and utilities including an adequate 
public landing with provision for the sale of motor 
fuel, lubricants, and potable water, and a parking 
lot with adequate sanitary facilities, open to all 
equally; dredging berthing areas to be commensurate 
with the depth of the Federal improvement; 
establish a properly constituted and competent 
public body empowered to cooperate 
financially and to provide and operate essential 
local facilities; reserve spaces within anchorage 
and mooring facilities adequate for accommodation 
of transient craft; pay, contribute in kind, or 
repay (which may be through user fees) with interest, 
one-half of separable cost of structural 
modifications necessary to provide for 
recreational fishing facilities on the main 
breakwater, less one-half of the cost of associated 
parking facilities to be provided locally, the 
amount involved currently estimated at $20,000; 
and bear all costs of maintenance and replacement 
of these modifications the amount involved 
currently estimated at $2,800 on an average annual 
basis; provided that the sizing and responsibility 
for development, maintenance, and 
31-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
replacement of these facilities may be modified in 
accordance with the alternatives provided in the 
Federal Water Project Recreation Act, depending 
on the intentions of non-Federal interests 
regarding participation in the costs of these 
features at the time of construction and subsequent 
thereto. Improvement for navigation may 
be undertaken independently of the public 
recreational fishing facilities on the main 
breakwater whenever funds for that purpose are 
available and required local cooperation has been 
furnished. Assurances of local cooperation were 
furnished by Michigan Department of Natural 
Resources to OCE on 10 May 1974. The cash contribution 
was made on 21 May 1974. The 
assurances were accepted by OCE on 10 July 
1974. 
Terminal facilities. An existing public 
fishing pier of open pile construction is not adequate 
for existing and prospective commerce. 
Complete boating facilities are planned by State 
and local agencies in connection with the harbor 
construction. 
Operations and results during fiscal 
year. New Workl Preconstruction planning was 
completed at a cost of $88,520. A contract was 
awarded for construction of a harbor of refuge in 
the amount of $2,628,355. No work was accomplished 
on this contract this fiscal year. Construction 
layouts and miscellaneous work was 
performed by Government forces at a cost of $3,- 
413. 
Condition at end offiscal year. A contract was 
awarded in 1975. Construction has not started. 
22. LITTLE LAKE HARBOR, MICH. 
Location. On south shore of Lake Superior 21 
miles west of Whitefish Point and 30 miles east of 
Grand Marais, Mich. (See Lake Survey Chart 92.) 
Existing project. Provides for a small-craft 
harbor of refuge by dredging an entrance 
channel 12 feet deep from Lake Superior into Little 
Lake, suitably protected by breakwaters and 
revetments. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Only terminal facility at 
project site consists of a public dock built by State 
of Michigan for light-draft craft. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services were performed by 
Government forces at a cost of $3,860. Engineering, 
design, layouts for contract to be awarded 
next fiscal year were performed at a cost of $8,- 
337. 
Condition at end of fiscal year. This project is 
considered complete; however, because of shifting 
sand the harbor entrance shoals rapidly with 
the result that full project depth is not usually 
available. 
23. LUDINGTON HARBOR, MICH. 
Location. On east shore of Lake Michigan, 156 
miles northeasterly from Chicago, Ill., and 67 
miles northerly from Grand Haven, Mich. (See 
Lake Survey Chart 774.) 
Previous projects. For details see page 1951 of 
Annual Report for 1915, page 1491 of Annual 
Report for 1938, and page 1307 of Annual Report 
for 1963. 
Existing project. Provides for an exterior 
basin in Lake Michigan protected by north and 
south breakwater, north breakwater is 1,800 feet 
long and south breakwater 1,700 feet long, 550 
feet apart at outer ends, diverging at an angle of 
90 degrees, with shore connections, 1,103 and 
2,004 feet long, respectively; for dredging exterior 
basin to 18 feet deep with a maximum 
width of 1,500 feet; for a channel with a depth of 
29 feet from deep water in Lake Michigan 
decreasing to 27 feet at the west end of the north 
pier, over a maximum width of 600 feet; thence a 
channel with a depth of 27 feet, over a minimum 
width of 230 feet with necessary widening at Pere 
Marquette Lake; and for inner piers and 
revetments 1,649 feet long on the north and sufficiently 
long on the south for turn at Pere Marquette 
Lake. The estimated (1975) Federal cost 
for new work is $4,205,000, excluding $9,000 to be 
contributed by local interests. Estimated total 
costs for local interests is $139,000. (See Table 31- 
B for authorizing legislation.) 
Local cooperation. Improvement authorized 
on 31 December 1970 under authority of Section 
201 of the 1965 Flood Control Act is subject to the 
condition that prior to construction, responsible 
local interests should be required to give satisfactory 
assurances that they will; Provide without 
cost to the United States all lands, easements, and 
rights-of-way required for construction and subsequent 
maintenance of the modified project 
upon the request of the Chief of Engineers including 
suitable areas determined by the Chief of 
Engineers to be required in the general public interest 
for initial and subsequent disposal of excavated 
materials and any necessary retaining 
dikes, bulkheads, and embankments therefor, or 
the cost of such retaining works; Hold and save 
the United States free from damages due to the 
construction and maintenance of the modified 
project; Provide and maintain without cost to the 
31-12

DETROIT, MICH., DISTRICT 
United States depths in berthing areas and local 
access channels serving the terminals commensurate 
with the depths provided in the related 
project areas; Accomplish without cost to the United 
States such alterations of submarine utility 
crossings as are required by the modified project; 
Establish regulations prohibiting discharge of 
pollutants into the waters of the harbor by users 
thereof, which regulations shall be in accordance 
with applicable laws or regulations of Federal, 
State, and local authorities responsible for pollution 
prevention and control. 
Terminal facilities. In addition to main terminal 
of Chesapeake & Ohio Railway Co., consisting 
of three car ferry slips, a wharf, and 
warehouses, there are several wharves which 
handle coal, limestone, and miscellaneous commodities. 
Facilities adequate for existing commerce. 
Operations and results during fiscal 
year. New Work: Preconstruction planning on 
the latest modification was continued at a cost of 
$51,992. Maintenance: Condition surveys, operation 
of safety feature and miscellaneous inspection 
services were performed by Government 
forces at a cost of $18,269. Maintenance of safety 
features was performed at a cost of $14,196. 
Maintenance of breakwater was performed by 
Chicago District's plant and forces at a cost of 
$24,999. The U.S. Hopper Dredge HAINS performed 
maintenance dredging removing 40,945 
cubic yards, bin measure, of shoal material at a 
cost of $58,252. Engineering, design, supervision 
and administration cost $2,371. Engineering and 
design studies under Section 111 P.L. 90-483 for 
mitigation of shore damage attributable to 
Federal navigation works was performed at a 
cost of $69,964. 
Condition at end of fiscal year. Existing project 
was completed in 1918. Construction has not 
started on latest authorized project modification. 
Project structures are generally in good condition. 
For additional details on completion of existing 
project see page 1469 of Annual Report for 
1962. Total costs for existing project to end of 
fiscal year were $6,666,948 of which $1,130,867 
was for new work, $5,304,619 for maintenance, 
and $357,913 for rehabilitation. 
24. MANISTEE HARBOR, MICH. 
Location. On east shore of Lake Michigan, 179 
miles northeasterly from Chicago, Ill., and 26 
miles northerly from Ludington, Mich.(See Lake 
Survey Chart 776.) 
Previous projects. For details see page 1952 of 
Annual Report for 1915, and page 1493 of Annual 
Report for 1938. 
Existing project. An entrance channel in Lake 
Michigan protected by a breakwater, piers, and 
revetments; a channel in Manistee River to 
Manistee Lake; and Federal participation in cost 
of replacing Maple Street Bridge. Project depths 
are 25 feet in entrance channel and 23 feet in river 
channel. For additional details see page 1470 of 
Annual Report for 1962. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Installations are on both 
sides of river and on Manistee Lake. Commerce 
handled includes coal, sand, salt, and general 
cargo. In addition, there is a Government wharf 
and a State and city owned recreational craft pier 
which is open to the public. These facilities satisfy 
current commerce requirements. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services cost $5,565. 
Chicago District's plant and forces performed 
maintenance to breakwater at a cost of $24,999. 
The U.S. Hopper Dredge HAINS performed 
maintenance dredging removing 10,296 cubic 
yards, bin measure, of shoal material at a cost of 
$19,184. Engineering, design, layouts, surveys, 
supervision and administration cost $9,684. 
Engineering and design studies under Section 
111 P.L. 90-483 for prevention or mitigation of 
shore damage attributable to Federal navigation 
work was performed at a cost of $25,000. 
Condition at end of fiscal year. Existing project 
was completed in August 1967. For additional 
details on completion of existing project 
see page 1470 of Annual Report for 1962. Navigation 
structures are in generally good condition. 
Total costs for existing project from regular 
funds to end of fiscal year are $6,009,508 of which 
$2,341,523 was for new work, $2,293,821 for 
maintenance, and $1,374,164 for rehabilitation. 
25. MONROE HARBOR, MICH. 
Location. On lower reach of Raisin River, 
which empties into Lake Erie and is 36 miles 
south of Detroit, Michigan. (See Lake Survey 
Chart 376.) 
Existing project. Provides for a channel in 
Lake Erie and Raisin River to city of Monroe, for 
a turning basin, and for riprapping protecting 
dikes at river mouth. Project depths are 21 feet to 
turning basin, 18 feet in turning basin, and 9 feet 
to upstream end of project. For additional details 
see page 1490 of Annual Report for 1962. Project 
feature for riprapping protecting dikes is considered 
inactive. Estimated costs of this feature 
(1954) is $90,000. (See Table 31-B for authorizing 
legislation.) 
31-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned 
docks and a municipal terminal. Port of Monroe 
Authority built a steel and concrete wharf on 
southeast side of turning basin for commercial 
use. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, environmental 
impact statements and miscellaneous 
inspection services were performed by 
Government forces at a cost of $17,446. The U.S. 
Hopper Dredge HAINS performed.maintenance 
dredging removing 158,268 cubic yards, bin 
measure, of shoal material at a cost of $222,354. 
Maintenance of the disposal area was performed 
at a cost of $47,990. Engineering, design, layouts, 
surveys, supervision and administration cost $8,- 
410. Engineering and design on confined disposal 
area for polluted dredging was continued at a cost 
of $42,999. 
Condition at end of fiscal year. Existing project 
was completed in 1936, except for riprapping 
protective dikes on each side of the Bay Channel. 
Due to combined effect of severe storms and continued 
high water, dikes have largely disappeared. 
Total costs to end of fiscal year were 
$4,722,408 of which $987,340 was for new work 
(including $300,000 contributed by the Port Commission 
of Monroe) and $3,735,068 for 
maintenance (including $166,667 contributed 
funds -- $125,000 by Consolidated Paper Company 
and $41,667 by River Raisin Company). 
26. MUSKEGON HARBOR, MICH. 
Location. On east shore of Lake Michigan, 114 
miles northeasterly from Chicago, Ill., and 80 
miles easterly from Milwaukee, Wis. (See Lake 
Survey Chart 767.) 
Previous projects. For details see page 1950 of 
Annual Report for 1915; page 1399, Annual 
Report for 1924; and page 1484; Annual Report 
for 1938. 
Existing project. A breakwater protected outer 
basin in Lake Michigan and an entrance 
channel from Lake Michigan to Muskegon Lake 
protected by piers and revetments. Project 
depths vary from 29 feet in the lakeward portion 
of the outer basin to 27 feet in the channel between 
the inner piers to Muskegon Lake. For additional 
details see page 1303 of Annual Report for 1963. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned 
wharves primarily for commercial use. Details on 
actual port and harbor facilities are in Port 
Series, No. 48 (revised 1961) prepared and 
published as part 2 by Board of Engineers for 
Rivers and Harbors. Information on port administration 
and Federal services, port terminal 
services and charges, and steamship services is 
prepared and published as part I by the Port 
Development Staff, U.S. Department of Commerce. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, operation 
of safety features, environmental impact 
statements and miscellaneous inspection services 
were performed by Government forces at a cost of 
$12,530. Maintenance of safety features cost $886. 
-Maintenance of the breakwater was performed 
by Chicago District's plant and forces at a cost of 
$98,428. Rehabilitation of the revetment was performed 
by rental contract at a cost of $32,396. The 
U.S. Hopper Dredge HAINS performed 
maintenance dredging removing 72,414 cubic 
yards, bin measure, of shoal material at a cost of 
$76,862. Engineering, design, layouts, surveys, 
supervision and administration cost $72,896. Also 
engineering and design was continued for repairs 
to North Pier and Revetment. Engineering and 
design studies under Section 111 P.L. 90-483 for 
prevention or mitigation of shore damage attributable 
to Federal navigation works was performed 
at a cost of $69,964. 
Condition at end of fiscal year. Existing project, 
including latest project modification, was 
completed in 1965. For additional details on completion 
of existing project see page 1465 of Annual 
Report for 1962. The navigation structures 
are in generally good condition. Total costs to end 
of fiscal year were $5,266,407 of which $2,298,702 
was for new work, $2,224,874 for maintenance 
and $742,832 for rehabilitation. 
27. OTTAWA RIVER HARBOR, 
MICH. AND OHIO 
Location. On the Ottawa River at the . esterly 
end of Lake Erie about 3.5 miles northerly from 
the mouth of the Maumee River and Toledo Harbor, 
Ohio; and about three-fourths of a mile 
northerly from the Michigan-Ohio State line. (See 
Lake Survey Charts 374 and 370.) 
Existing project. Provides for dredging a 
channel 8 feet deep, 200 feet wide, and about 15,- 
000 feet long in Maumee Bay from the Toledo 
Harbor ship channel to the mouth of the Ottawa 
River and a channel 6 feet deep, 100 feet wide, and 
about 16,500 feet long in the Ottawa River from 
the river mouth to the Suder Avenue Bridge. Estimated 
(1975) cost for new work is $1,690,000 ex- 
31-14

DETROIT, MICH., DISTRICT 
eluding $1,690,000 to be contributed by local interests. 
Total non-Federal cost (1975) is $2,050,- 
000. (See Table 31-B for authorizing legislation.) 
Local cooperation. Improvement authorized 
on 31 December 1970 under authority of Section 
201 of the 1965 Flood Control Act is subject to the 
condition that local interests contribute in cash 50 
percent of the first cost of Federal construction of 
the general navigation facilities exclusive of aids 
to navigation, a contribution presently estimated 
at 1,690,000, to be paid in a lump sum prior to initiation 
of construction, or in installments over 
the constrution period at a rate proportionate to 
the proposed or scheduled expenditure of Federal 
funds as required by the Chief of Engineers, the 
final apportionment of cost to be made after actual 
costs have been determined: Provide without 
cost to the United States all lands, easements, and 
rights-of-way required for construction and subsequent 
maintenance of the project and for aids to 
navigation upon the request of the Chief of 
Engineers, including suitable areas determined 
by the Chief of Engineers to be required in the 
general public interest for initial and subsequent 
disposal of spoil and any necessary retaining 
dikes, bulkheads, and embankments therefor, or 
the cost of such retaining works: Hold and save 
the United States free from all claims for 
damages incident to the construction, operation, 
and maintenance of the improvements: Accomplish 
without cost to the United States such 
alterations as are required to submarine utility 
crossings: Establish a competent and properly 
constituted public body empowered to regulate 
the use, growth, and development of the harbor 
and related facilities with the understanding that 
said facilities will be open to all on equal terms: 
Provide and maintain without cost to the United 
States necessary mooring facilities and service 
areas, including a public landing with suitable 
supply facilities, a launching ramp, reservation 
of space for transient craft, parking areas with 
adequate sanitary facilities, and access roads, 
open to all on equal terms; the dredging of 
berthing areas to be commensurate with the 
depth of the Federal channel improvements and; 
establish regulations prohibiting discharge of 
pollutants into the waters of the harbor by users 
thereof, which regulations shall be in accordance 
with applicable laws or regulations of Federal, 
State, and local authorities responsible for pollution 
prevention and control: provided, however, 
that if there are no applicable State or Federal 
laws of regulations, local interests shall provide 
adequate waste disposal facilities for all watercraft 
and other users. 
Terminal facilities. There are some 3,285 
recreational boating berths provided at private 
properties, marinas, yacht clubs, and boating 
associations located along the Ottawa River and 
vicinity. Several facilities provide fuel, stores, 
and hoist and repair service for these recreational 
craft. 
Operations and results during fiscal 
year. New Work: Preconstruction planning was 
initiated in fiscal year 1975 at a cost of $10,000. A 
plan of study was prepared. 
Condition at end of fiscal year. Construction 
has not started. 
28. PENTWATER HARBOR, MICH. 
Location. On east shore of Lake Michigan 146 
miles northeasterly from Chicago, Ill., and 14 
miles southerly from Ludington, Mich. (See Lake 
Survey Chart 77.) 
Existing project. Provides for widening old 
entrance channel to 150 feet between parallel 
piers and revetments, channel to extend from 
Lake Michigan to Pentwater Lake, with a depth 
of 16 feet. Piers and revetments are built of stonefilled 
timber cribs and piling and capped with 
concrete. The 200-foot extension to south pier portion 
of project is considered inactive. Estimated 
cost (1954) of this portion is $65,100. (See Table 
31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small privately 
owned wharves on west end of Pentwater Lake. 
The city and Michigan Waterways Commission 
jointly constructed a dock on northwest side of 
Pentwater Lake for public use. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services were performed by 
Government forces at a cost of $9,410. An adjustment 
was made in prior year contract dredging 
cost of $11,773. Engineering, design, after dredging 
surveys, layouts, supervision and administration 
cost $4,717. 
Condition at end of fiscal year. Existing project 
was completed in 1959 except for a 200 foot 
extension to the south pier which is not considered 
necessary under present conditions. For additional 
details see page 1468 of Annual Report 
for 1962. Total costs for existing project at end of 
fiscal year were $1,975,623 of which $179,899 was 
for new work, and $1,783,951 for maintenance. 
31-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
29. PORTAGE LAKE HARBOR, 
MICH. 
Location. On east shore of Lake Michigan 
about 186 miles northeasterly from Chicago and 
about 37 miles northerly from Ludington. (See 
Lake Survey Chart 777.) 
Existing project. Provides for a harbor of 
refuge with an entrance channel from Lake 
Michigan to Portage Lake protected by piers ana 
revetments. Project depth is 18 feet. For additional 
details see page 1297 of Annual Report 
for 1958. Latest published map is in House Document 
588, 64th Congress, 1st. session. (See Table 
31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. There are landing places 
at inner end of Portage Lake. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, environmental 
impact statements and miscellaneous 
inspection services cost $7,388. Construction 
layouts cost $1,799. 
Condition at end of fiscal year. Existing project 
was substantially completed in 1912. For additional 
details on completion of existing project 
see page 1298 of Annual Report for 1958. The 
structures are generally in good condition. 
30. PORT AUSTIN HARBOR, MICH. 
Location. On west shore of Lake Huron at extreme 
southeastern limit of Saginaw Bay, and 29 
miles south of Au Sable River (Oscoda). (See Lake 
Survey Chart 52.) 
Existing project. A harbor of refuge at mouth 
of Bird Creek, consisting of a harbor basin dredged 
to a depth of 10 feet protected by a breakwater 
structure, and for dredging and entrance channel 
to harbor basin to a depth of 12 feet. Existing project 
was authorized by 1945 River and Harbor 
Act (H. Doc. 446, 78th Cong., 2d Sess., contains 
latest published map). 
Local cooperation. Fully complied with. 
Terminal facilities. A number of docks near 
mouth of Bird Creek and a State-owned dock inside 
breakwater. Facilities accommodate 
recreational craft and are considered adequate 
for existing traffic. 
Operations and results during fiscal 
year. Maintenance: Condition surveys by 
Government forces cost $1,022. Engineering and 
design on confined disposal area for polluted 
dredging was performed at a cost of $11,999. 
Condition at end of fiscal year. Existing project 
was completed in 1959. Total cost for existing 
project to end of fiscal year were $1,181,819 of 
which $1,128,334 was for new work (includes 
$172,100 contributed funds) and $53,485 for 
maintenance. 
31. PORT CLINTON HARBOR, 
OHIO 
Location. Comprises lower half-mile of Portage 
River. River empties into Lake Erie 72 miles 
westerly from Cleveland, Ohio. (See Lake Survey 
Chart 3.) 
Existing project. Provides for parallel jetties 
at river mouth and a channel in Lake Erie and 
Portage River with a project depth of 10 feet. For 
additional details see page 1899 of Annual Report 
for 1951. (See Table 31-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. There is one public fish 
dock, one private sand dock, one private fuel, 
lumber and coal dock, and five additional private 
docks. A dock at foot of Madison Avenue is owned 
by village of Port Clinton and open to the public. 
A shipyard builds small boats. Terminal facilities 
are adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys by 
Government forces cost $827. Engineering and 
design on confined disposal area for polluted 
dredging was performed at a cost of $6,165. 
Condition at end of fiscal year. Existing project 
was completed in 1893. For additional details 
on completion, see page 1900 of Annual Report for 
1951. 
32. PORT SANILAC HARBOR, 
MICH. 
Location. On southwest shore of Lake Huron, 
30 miles north of Port Huron, Mich. (See Lake 
Survey Chart 51.) 
Existing project. Provides for a harbor of 
refuge protected by breakwater structures extending 
to 12-foot depth contour in lake; for dredging 
a harbor basin 10 feet deep; for dredging an entrance 
channel 12 feet deep; a 70-foot extension of 
the south breakwater; a 300-foot arm added to the 
north breakwater; and riprap placed at the 
lakeward side of the breakwater additions. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
completed portions of project. For breakwater 
extensions responsible local intrests must furnish 
31-16

DETROIT, MICH., DISTRICT 
assurances that they will contribute in cash 50 
percent of the first cost for construction of the 
recommended improvement, exclusive of aids to 
navigation, if the first cost is less than $2,000,000. 
If the first cost exceeds $2,000,000 contribute the 
amount in excess of $1,000,000 of this first cost. 
The contribution is presently estimated at $380,- 
000. The required amount shall be paid in alump 
sum prior to initiation of construction, the final 
apportionment of cost to be made after actual 
costs have been determined; provide without cost 
to the United States all necessary lands, 
easements, and rights-of-way for construction 
and subsequent maintenance of the project and 
for aids to navigation upon the request of the 
Chief of Engineers; hold and save the United 
States free from all claims for damages incident 
to the construction, operation, and maintenance 
of the improvement; provide and maintain 
without cost to the United States any additional 
mooring facilities, services areas, public landing 
with suitable supply facilities, a launching ramp, 
reservation of space for transient craft, parking 
areas with adequate sanitary facilities, and 
access roads, open to all on equal terms; the 
dredging of berthing areas to be commensurate 
with the depth of the Federal basin improvements; 
establish regulations prohibiting 
discharge of pollutants into the waters of the harbor 
by users thereof, which regulations shall be in 
accordance with applicable laws or regulations of 
Federal, State, and local authorities responsible 
for pollution prevention and control; provided, 
however, that if there are no applicable State or 
Federal laws or regulations, local interest shall 
provide adequate waste disposal facilities for all 
watercraft and other users. Assurances of local 
cooperation were furnished by Michigan Department 
of Natural Resources to OCE on 10 
September 1972. The cash contribution was made 
on 15 February 1973. The assurances were 
accepted by OCE ib 26 October 1972. 
Terminal facilities. There is one privately 
owned dock used principally as a fishing terminal 
by owner and a municipally owned pier for 
recreational craft. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal 
year. New Work: A contract awarded last fiscal 
year for breakwater extension and repairs is approximately 
68% complete at a cost of $314,968. 
Supervision and administration of contract cost 
$16,514. Maintenance: Condition surveys and 
miscellaneous inspection services were performed 
by Government forces at a cost of $1,718. 
Major repair to the breakwater were performed 
under the above contract at a cost of $64,999. 
Engineering and design was completed at a cost 
of $282. Engineering and design on confined disposal 
area for polluted dredging cost $2,868. 
Engineering and design under Section 111 of 
Public Law 90-483 for prevention or mitigation of 
shore damage attributable to Federal navigation 
works cost $23,000. 
Condition at end of fiscal year. Project was 
completed in 1951 except for latest project 
modification work which will be completed in 
1976. Breakwaters are in good condition. 
33. ROUGE RIVER, MICH. 
Location. Rises in. Oakland and Washtenaw 
Counties, Mich., 30 miles long, flows southeasterly 
through Wayne County, and joins Detroit River 
at westerly limit of city of Detroit. (See Lake Survey 
Chart 415.) 
Previous projects. For details see page 1530 of 
Annual Report for 1932, and page 1558 of Annual 
Report for 1938. 
Existing project. Provides for: (a) Main 
channel from Detroit River through Short Cut 
Canal extending to upstream limit of the project, 
a distance of 3.5 miles. Project depths are 25 and 
21 feet in navigation channel, 21 feet in turning 
basin, and 13 feet in upper reach of project. (b) 
Old channel from Detroit River extending to 
junction of Old Channel with Short Cut Canal. 
Project depths are 25, 18, 17, and 21 feet. For additional 
details see page 1324 of Annual Report 
for 1963. In 1973, work authorized by the 1962 
River and Harbor Act was reclassified from the 
active to inactive category. Estimated cost (1972) 
of this work is $880,000. Except for dredging 25- 
foot channel 1,150 feet upstream from mouth of 
Old Channel, work authorized in act of August30, 
1935, is considered inactive. Estimated cost 
(1958) of inactive portion is $255,000. Work 
authorized by act of July 3, 1958 is considered inactive. 
Estimated cost (1960) of this work is $210,- 
000. (See Table 31-B for authorizing legislation. 
Local cooperation. Act of August 30,1935, 
provided that no Federal expenditures be made 
on improvements in old channel until local interests 
provided all necessary rights-of-way and 
furnished guarantees protecting the United 
States against damages to adjacent lands and 
property which may result from dredging 
operations. Except for guarantees protecting the 
United States against damages to adjacent lands 
and property along 25-foot channel, this requirement 
has not been complied with. Act of July 3, 
1958, is subject to condition that local interests 
furnish lands, rights-of-way, and spoil disposal 
areas for construction and future maintenance; 
31-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
hold the United States free from damages; make 
a cash contribution equal to 50 percent of first 
cost of dredging; dredge and maintain area 
between Federal channel and wharves along 
channel to depth necessary for mooring vessels; 
and provide and maintain a steel sheet pile 
bulkhead to protect facilities of Allied Chemical 
and Dye Corp. Except for guarantees protecting 
the United States against damages to adjacent 
lands and property along 25-foot channel, this requirement 
has not been complied with. Act of October 
23, 1962, requires local interests to provide 
lands and rights-of-way for construction upon request 
of the Chief of Engineers; hold the United 
States free from damages; provide terminal 
facilities to accommodate prospective commerce 
considered in report of District Engineer; dredge 
and maintain areas between the Federal improvement 
and terminal facilities to depths commensurate 
with improved Federal channel; make 
alterations in docks, bulkheads and other structures, 
and take such other measures as may be 
necessary to assure stability of banks adjacent to 
channel; and provide bridge protection. The 
assurances of local cooperation for the River and 
Harbor Act of 1962 were furnished by the 
Michigan State Waterways Commission and 
accepted on January 7, 1965. Fulfillment of all 
items of local cooperation has not been accomplished. 
Terminal facilities. Numerous large commercial 
docks for handling various type cargo. 
Details on actual port and harbor facilities are 
contained in the Port Series No. 45 (revised 1961) 
prepared and published as Part 2 by the Board of 
Engineers for Rivers and Harbors. Information 
on port administration and Federal services, port 
and terminal services and charges, and 
steamship services is prepared and published as 
Part 1 by the Port Development Staff, U.S. 
Department of Commerce. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services were performed by 
Government forces at a cost of $26,226. The U.S. 
Hopper Dredge HAINS performed rhaintenance 
dredging removing 109,669 cubic yards, bin 
measure, of shoal material at a cost of $127,118. 
The cost is exclusive of financial participation in 
cost of dredging by industry (obtained as a result 
of studies on illegal deposits of industrial waste) 
in the amount of $246,840 from Ford Motor Company. 
Maintenance of the disposal area was performed 
at a costof $44,249. Raising of the dikes on 
the Rouge River disposal area was performed by 
contract at a cost of $26,869. Engineering, design, 
surveys, supervision and administration cost 
$26,526. Engineering and design on confined disposal 
area for polluted dredging was performed 
at a cost of $61,626. 
Condition at end of fiscal year. Work 
authorized before 1962 modification is complete 
except for deepening old channel to 21 feet from 
Detroit, Toledo and Ironton Railroad Bridge to 
junction with Short Cut Canal. This work is being 
held in abeyance until local interest comply with 
terms of local cooperation. Engineering and 
design on modifications authorized by 1962 River 
and Harbor Act has been deferred pending 
fulfillment of local cooperation requirements. 
For additional details on completion of existing 
project see Annual Report for 1962. Total costs for 
existing project to end of fiscal year were $8,970,- 
908 of which $675,251 was for new work and $8,- 
295,657 for maintenance. In addition, $29,563 
was expended for new work from Emergency 
Relief Act Funds. 
34. SAGINAW RIVER, MICH. 
Location. Formed by union of Tittabawassee 
and Shiawassee Rivers, 22 miles long, and flows 
northerly into extreme inner end of Saginaw Bay, 
Lake Huron. Cities of Saginaw and Bay City are 
on the river. (See Lake Survey Chart 524.) 
Previous projects. For details, see page 1957 
of Annual Report for 1915, and page 1550 of Annual 
Report for 1938. 
Existing project. Provides for an entrance 
channel 27 feet deep and 350 feet wide from 27- 
foot contour in Saginaw Bay to river mouth; 
thence a channel 26 feet deep and 200 feet wide 
about 0.4 mile; thence 25 feet deep and 200 feet 
wide to New York Central Railroad Bridge at 
Bay City; thence 22 feet deep and 200 feet wide to 
C&O Railroad Bridge in Saginaw; thence 16.5 
feet deep and 200 feet wide to upstream limit at 
Green Point. Project also provides for five turning 
basins; one 25 feet deep at Essexville, 600 
feet wide with a maximum length of 1,850 feet; 
one 22 feet deep on east side of channel about 1 
mile upstream from Cass Avenue in Bay City, 650 
feet wide and 1,000 feet long; one 20 feet deep at 
Carrbllton, 100 to 300 feet wide and 900 feet long; 
one 20 feet deep just downstream from C&O 
Bridge in Saginaw, 650 feet wide and 1,000 feet 
long; and one 15 feet deep between Bristol Street 
Bridge and New York Central Railroad Bridge in 
Saginaw. (See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Numerous large commercial 
docks for handling a great variety of 
cargo. Details on actual port and harbor facilities 
31-18

DETROIT, MICH., DISTRICT 
are in Port Series No. 45 (revised 1961) prepared 
and published as part 2 by Board of Engineers for 
Rivers and Harbors. Information on port administration 
and Federal services, port and terminal 
services and charges, and steamship services 
is prepared and published as part I by Port 
Development Staff, U.S. Department of Commerce. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, support 
of USGS Cooperative Stream Gaging, support of 
Water Control Center, Hi Fix Surveys and miscellaneous 
inspection services were performed by 
Government forces at a cost of $118,618. The U.S. 
Hopper Dredge HAINS performed maintenance 
dredging removing 156,271 cubic yards, bin 
measure, of shoal material at a cost of $410,324. 
Maintenance of pump-out facilities was performed 
at a cost of $24,043. Engineering and 
design, surveys, supervision and administration 
cost $5,910. Engineering and design on confined 
disposal area for polluted dredging was performed 
at a cost of $289,484. 
Condition at end of fiscal year. Existing project 
is complete, except for a small part of the 
work authorized by the Act of October 23, 1962. 
Section D (Sixth Street Turning Basin) of the 
1962 Act is complete except for the channel portion, 
which is pending modification. Total costs 
for existing project to the end of the fiscal year 
were $21,041,061 of which $13,954,660 was for 
new work and $7,086,041 was for maintenance. 
35. ST. CLAIR RIVER, MICH. 
Location. A 40 mile long section of Great 
Lakes connecting channels which flows southerly 
from Lake Huron and discharges into Lake St. 
Clair. (See Lake Survey Chart 43.) 
Existing project. Provides for channels 
through St. Clair River, which, at low water 
datum, are suitable for vessels drawing 25.5 feet. 
Project also provides for compensating works, 
consisting of a number (estimated at 31) of submerged 
rock sills, with crests 31 feet below 
datum, and improvement of North Channel outlet, 
100 feet wide and 10 feet deep, for 
recreational craft. Project depths are referred to 
low water datums for Lakes Huron and St. Clair, 
576.8 and 571.7 feet above mean water level at 
Father Point, Quebec; International Great Lakes 
Datum 1955. (See Tables 31-B and 31-C for 
authorizing legislation and features of existing 
project.) 
Act of 21 March 1956, provides for a project 
safe draft of 25.5 feet over full width of channels 
when levels of Lakes Huron and St. Clair are at 
their respective low water datums. Estimated 
cost (1975) for new work is $31,147,000. Project 
features for construction of compensating works, 
consisting of submerged rock sills, was previously 
considered inactive. During fiscal year 1960, 
portion of rock sills (presently estimated at four) 
necessary to compensate for deepening connecting 
channels was reclassified in active category. 
Estimated cost (1975) for these four sills is $10,- 
470. This cost is included in foregoing estimated 
cost of new work. No expense of maintenance will 
probably be required for submerged sills. 
Local cooperation. None required. 
Terminal facilities. This improvement serves 
through commerce between upper and lower 
Great Lakes, and has not materially influenced 
terminal facilities along its route. A number of 
privately owned piers and wharves are at Port 
Huron, Marysville, St. Clair, and Marine City, 
Mich., which handle coal, limestone, petroleum 
products, woodpulp, salt and general cargo. 
These installations satisfy present commerce requirements. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, environmental 
impact statements, operation of 
safety features and miscellaneous inspection services 
were performed by Government forces at a 
cost of $100,574. The U.S. Hopper Dredge HOFFMAN 
performed maintenance dredging removing 
54,512 cubic yards, bin measure, of shoal 
material at a cost of $69,584. Obstructions were 
located at a cost of $105,010, and removed by U.S. 
Derrickboat Huron at a cost of $129,747. Surveys, 
supervision and administration cost $4,189. 
Condition at end of fiscal year. Existing project 
is complete except for construction of submerged 
rock sills and improving north channel 
outlet. Total cost of existing project to end of fiscal 
year was $24,802,732 of which $19,213,246 was 
for new work and $5,589,486 for maintenance. 
36. ST. JOSEPH HARBOR, MICH. 
Location. On east shore of Lake Michigan, 60 
miles easterly from Chicago, Ill., and 24 miles 
southerly from South Haven, Mich. (See Lake 
Survey Chart 758.) 
Previous projects. For details see page 1945 of 
Annual Report for 1915, and page 1470 ofAnnual 
Report for 1938. 
Existing project. Provides for protecting 
mouth of St. Joseph River by two piers, 250 to 325 
feet apart at their inner and outer ends, respectively, 
having lengths of 2,758 feet on north side 
and 2,603 feet on south side; for a channel 21 feet 
deep from Lake Michigan to mouth of Benton 
31-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Harbor Canal, a length of about 6,900 feet withwidths 
of 265 feet at outer end of piers, 190 feet at 
inner end of piers and revetments, thence 
generally 215 feet to lower end of turning basin, 
increasing to 250 feet above the turning basin to 
mouth of Paw Paw River, thence generally 110 
feet in Paw Paw River to mouth of Benton Harbor 
canal; for dredging channel in Benton Harbor 
canal up to west line of Riverview Drive extended 
northerly, to 18 feet deep and 80 feet wide; and a 
turning basin 18 feet deep on north side of 
channel above mouth of Morrison Channel and a 
turning basin 18 feet deep near mouth of Paw 
Paw River. Public Law 88-88th Congress 
declared a portion of Benton Harbor Canal a nonnavigable 
stream. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several commercial 
wharves for handling coal, building materials, 
petroleum products, and miscellaneous commodities. 
A package freight terminal is also 
available. Facilities considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, operation 
of safety features, environmental impact 
statements and miscellaneous inspection services 
were performed by Government forces at a cost of 
$10,413. Maintenance of safety features was performed 
by Government forces at a cost of $2,490. 
The U.S. Hopper Dredge HAINS performed 
maintenance dredging removing 69,638 cubic 
yards, bin measure, of shoal material at a cost of 
$89,754. Preparation of Real Estate Design 
memo for rehabilitation was continued at a cost of 
$22,190. Engineering, design, surveys, supervision 
and administration cost $8,333. Engineering 
and design on confined disposal area for polluted 
dredging was performed at a cost .of $23,999. 
Engineering and design under Section 111 P.L. 
90-483 for prevention or mitigation of shore 
damage attributable to Federal navigation works 
was performed at a cost of $3,000. 
Condition at end of fiscal year. Existing project 
was completed in 1956. The structures are in 
generally good condition. For additional details 
on completion of existing project see page 1454 of 
Annual Report for 1962. Total costs of existing 
project to end of fiscal year were $5,038,508 of 
which $473,372 was for new work, $3,602,921 for 
maintenance and $962,216 for rehabilitation. 
37. ST. JOSEPH RIVER, MICH. 
Location. St. Joseph River rises near 
Hillsdale, Mich., flows southwestward into Indiana, 
thence, northwest, and empties into Lake 
Michigan at St. Joseph. The length is about 170 
miles following the general course and not including 
small bends. It has a drainage area of 
4,586 square miles. Its discharge in cubic feet per 
second varies from about 300 to 21,600, with an 
average of about 3,000. High water occurs in spring, 
with a rise of from 4 to 6 feet, and low water in 
summer. It is a crooked stream with rapid 
current and numerous shoal crossings 24 to 30 inches 
deep, with intervening pools from 4 to 8 feet 
deep. The average width below Berrien Springs 
is from 300 to 400 feet. The navigable part extends 
from the mouth to the dam at Berrien 
Springs, a distance of about 22 miles by river, 
,with a drop at low water of 17 feet from Berrien 
Springs to Lake Michigan. (See U.S. Lake Survey 
Chart No. 7.) 
Existing project. This provides for a channel 2 
to 3 feet deep at low water and from 30 to 50 feet 
wide from the mouth to Berrien Springs, a distance 
of about 22 miles, by building wing dams, 
making cuts through the shoals, and removing 
snags. Fluctuations in water surface due to floods 
vary from about 4 to 6 feet above low water. 
Local cooperation. None. 
Terminal facilities. None, except as use is 
made of St. Joseph Harbor. 
Operation and results during fiscal year. New 
Work: The cost for the shore protection contract 
awarded and completed during fiscal year 1974 
was adjusted in the amount of $83,409. 
Condition at end of fiscal year. Some of the 
worst places had been improved in a temporary 
way from year to year, so that steamboats with 
draft of 3 feet or less operated between St. Joseph 
and Berrien Springs up to 1908. Since 1908 little 
use of the river has been made and this use has 
been confined to the lower 7 miles. On the lower 2 
or 3 miles, sand and gravel are handled on scows 
with loaded drafts of 5 to 6 feet where natural 
depths are adequate for this traffic. From about 3 
to 9 miles above the mouth the available depths at 
usual summer stage are about 3 feet and in the 
remaining portion up to Berrien Springs they are 
but 2 to 2.5 feet. All work has been completed. 
Total costs to end of fiscal year for existing project 
were $418,739 of which $54,555 was for new work 
and $19,185 for maintenance and $344,999 contributed 
funds. 
38. ST. MARYS RIVER, MICH. 
Location. A Great Lakes connecting channel 
about 63 miles long, flows southeasterly between 
State of Michigan and Province of Ontario, 
Canada, from eastern end of Lake Superior into 
31-20

DETROIT, MICH., DISTRICT 
northern end of Lake Huron. (See Lake Survey 
Charts 61, 62, and 63.) At Sault Ste. Marie, Mich., 
about 14 miles downstream from Lake Superior, 
there are four parallel locks and a hydroelectric 
powerplant. 
Previous projects. For details see page 1955, 
Annual Report for 1915; and page 1529, Annual 
Report for 1938. 
Existing project. Channels permitting 25.5- 
foot draft navigation in St. Marys River and Lake 
Superior and Lake Huron approaches thereto; 
constructing and operating four locks and two 
canals; constructing a hydroelectric plant of 14,- 
000 kilowatt capacity (45,000 kilowatt ultimate 
capacity) constructing anchorage areas in river 
above and below locks; and constructing various 
other works in conjunction with project. Original 
State locks were operated and maintained under 
permanent indefinite appropriation from June 
9,1881, to November 2, 1886, after which they 
were destroyed by excavation for the Poe Lock in 
1896. Weitzel Lock, destroyed in 1942 by excavation 
for MacArthur Lock, was operated and 
maintained under the same appropriation from 
September 1, 1881, to June 30, 1935. Poe Lock was 
operated and maintained under the same appropriation 
from August 3, 1896, Davis Lock 
from October 21, 1914, and Sabin Lock from 
September 18, 1919, to end of fiscal year 1935. Poe 
Lock was destroyed by excavation for new Poe 
Lock in 1962. Details of existing project are set 
forth in Table 31-D. 
Project depths are referred to low water datum 
corresponding to sloping surface of river as 
follows: Above locks: When water surface of 
Lake Superior is at elevation 600 feet and at upstream 
side of locks is 577.8 feet above mean 
water level at Father Point, Quebec (International 
Great Lakes Datum 1955). Estimated 
(1973) cost for new work is $164,630. (See Table 
31-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. This improvement serves 
through commerce between Lake Superior and 
lower lakes and has not materially influenced terminal 
facilities at localities along its route. Three 
piers at Sault Ste. Marie receive coal and 
petroleum products. Limestone is shipped from a 
pier at Drummond Island. Vessel refueling 
stations are at Lime Island and Village of Detour; 
they receive coal and petroleum products. Present 
terminals satisfy current traffic requi'ements. 
Operations and results during fiscal 
year. New Work: A contract for widening the 
turns at angle courses 6 and 7 Middle Neebish 
Thannel cost $943,857 and angle courses 1-2 cost 
$1,243,857. The program to monitor the effect of 
dredging to establish pre-dredging conditions 
was initiated in November 1971 and will continue 
throughout the contract period. Engineering, 
design, construction layouts, supervision and administration 
cost $75,427. Maintenance: Operation 
and care of locks: Two canals and four locks 
were operated as required. Necessary repairs 
and improvements were made thereto and to appurtenant 
structures and equipment. Canal was 
open to navigation 365 days from 1 April 1974 
through 31 March 1975. During that period, a 
total of 13,021 vessels, aggregating 100,081,053 
short tons of freight and 186,248 passengers passed 
through the MacArthur, Poe, Davis and Sabin 
Locks. Cost for the fiscal year was $3,413,600. 
Powerhouse and equipment: Two hydroelectric 
powerhouses were operated and maintained. 
Cost, that was done by hired labor during the 
fiscal year was $338,591. Less a deduction of $27,- 
904, for interdepartmental electricity sold. Other 
operation and care items: Buildings and 
grounds were maintained; security measures enforced; 
and condition and operation studies, inspections, 
and reports were made or compiled as 
required, all by hired labor. Cost was $429,457. 
Channels and canals: St. Marys River channels 
and canal approaches were examined by sweeping. 
Removal of shoals in St. Marys River 
channels and canal approaches was accomplished 
by hired labor and U.S. Derrick boats NICOLET 
and HARVEY and the hopper dredge LYMAN 
at a cost of $763,896. Recreational facilities: Information 
center, comfort stations, park fountain, 
observation and overlook platform were 
operated and maintained at a cost of $73,094. A 
total of 285,129 visitors used the observation and 
overlook platform and the information center 
facilities during the fiscal year. 
Condition at end of fiscal year. Project in 
effect prior to modification of 21 March 1956 is 
complete with exception of installation of steel 
guard gates at upper end of MacArthur Lock. 
Work authorized by 1956 modification to provide 
a safe draft of 25.5 feet for both upbound and 
downbound traffic is complete. Cost of existing 
project to 30 June 1975 were: Regular funds 
totaled $237,875,310 of which $155,997,813 was 
for new work and $81,877,497 for maintenance; 
Public Works Funds used for new work was 
$158,401; and Public Works Acceleration Funds 
used for maintenance was $118,000. Total cost to 
end of fiscal year was $158,459,355 for new work 
and $86,501,035 for maintenance; for a Grand 
Total of $244,960,390. 
31-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
39. SAUGATUCK HARBOR AND 
KALAMAZOO RIVER, MICH. 
Location. Harbor is on east shore of Lake 
Michigan, 90 miles northeasterly from Chicago, 
Ill., and 22 miles northerly from South Haven, 
Mich. (See Lake Survey Chart 76.) 
Previous projects. For details see page 1947 of 
Annual Report for 1915, and page 1475 of Annual 
Report for 1938. 
Existing project. Entrance channel protected 
by parallel piers at mouth of Kalamazoo River 
and a river channel to city of Saugatuck. Project 
depths: 16 feet in entrance channel, 14 feet in 
river channel. Additional details on page 1456, 
1962 Annual Report. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal fiacilit ies. At village of Saugatuck 
there are several landing places for recreational 
craft and one for small commercial vessels. At 
village of Douglas there is a landing pier. 
Facilities are considered adequate for present 
traffic. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services were performed by 
Government forces at a eost of $6,975. An adjustment 
was made in the amount of -$416 on the contract 
for repairs to revetment completed last 
year. An adjustment was made in the amount of - 
$10,496 on the contract for maintenance dredging 
completed last year. Engineering and design, 
supervision and administration cost $937. 
Condition at end of fiscal year. Existing project 
was completed in 1911. Piers and revetments 
are in generally good condition. Total cost for existing 
project to end of fiscal year was $2,322,337 
of which $364,527 was for new work and $1,957,- 
810 for maintenance. 
40. SEBEWAING RIVER, MICH. 
Location. At mouth of Sebewaing River on 
south shore of Saginaw Bay about 10 miles south 
of Bay Port, Mich. (See Lake Survey Chart 52.) 
Previous projects. For details see page 1077 of 
Annual Report for 1912. 
Existing project. Provides for an entrance 
channel 8 feet deep, 100 feet wide, and about 15,- 
000 feet long in Saginaw Bay. Existing project 
was authorized by 1896 River and Harbor Act (H. 
Doc. 71, 54th Cong., 1st sess.). 
Local cooperation. None required. 
Terminal facilities. A number of small 
wharves used by fishing vessels and other lightdraft 
craft are along the river. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys were performed 
by Government forces at a cost of $6,729. 
Engineering and design on confined disposal 
area for polluted dredging was performed at a 
cost of $11,999. 
Condition at end offiscal year. Existing project 
was completed in 1903. Total costs to end of 
fiscal year were $345,363 of which 35,573 was for 
new work and $307,790 for maintenance. 
41. SOUTH HAVEN HARBOR, 
MICH. 
Location. On east shore of Lake Michigan, 77 
miles northeasterly from Chicago, Ill., and 24 
miles northerly from St. Joseph, Mich. (See Lake 
Survey Chart 76.) 
Previous projects. For details see page 1947 of 
Annual Report for 1915, and page 1473 of Annual 
Report for 1938. 
Existing project. An entrance channel 
protected by parallel piers and revetments at 
mouth of Black River, a river channel, and a turning 
basin. Project depths are 21 feet in entrance 
channel and 19 feet in river channel and turning 
basin. For additional details see page 1455 of Annual 
Report for 1962. (See Table 31-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves for 
handling coal, building materials, woodpulp, 
fish, and miscellaneous commodities will have 
warehouses. Facilities satisfy current commerce 
requirements. 
Operations and results during fiscal 
year. Maintenance: Condition surveys, environmental 
impact statements and miscellaneous 
inspection services were performed by 
Government forces at a cost of $8,472. 
Maintenance of safety features were performed 
at a cost of $696. The U.S. Hopper Dredge 
HAINS performed maintenance dredging 
removing 51,511 cubic yards, bin measure, of 
shoal material at a cost of $75,272. An adjustment 
of $-345 was made of the contract for rehabilitation 
of South Revetment completed last fiscal 
uear. Engineering, design, surveys, supervision 
and administration cost $11,713. Engineering 
and design on confined disposal area for polluted 
dredging was performed at a cost of $10,999. 
Engineering and design studies under Section 
111, P.L. 90-483 for prevention or mitigation of 
shore damage attributable to Federal navigation 
Sworks were performed at a cost of $3,000. 
31-22

DETROIT, MICH., DISTRICT 
Condition at end of fiscal year. Existing project 
was completed in 1960. For additional details 
on completion of existing project see page 1456 of 
Annual Report for 1962. Piers and revetments 
are in good condition except for those structures 
scheduled for rehabilitation. Total costs for existing 
project to the end of fiscal year were $4,- 
432,385 of which $265,193 was for new work, $2,- 
545,116 for maintenance, and $1,632,076 for 
rehabilitation. 
42. TAWAS BAY HARBOR, 
MICH. 
Location. On northeasterly portion of 
Saginaw Bay, an arm of Lake Huron, adjacent to 
Tawas, Michigan. (See Lake Survey Chart 52.) 
Existing project. Provides for a breakwater 
with four interconnected sections with an 
aggregate length of 1,750 feet with provisions for 
recreational fishing. A defined entrance channel 
and anchorage area are provided for, even though 
no dredging is required. Depths to 12 feet in the 
entrance and 10 feet in the anchorage area are 
presently available. Existing project was 
authorized by August 13, 1968 River and Harbor 
Act. (H. Doc. 189, 90th Congress, 1st Session, contains 
latest published map.) Estimated (1974) 
Federal cost for new work is $1,020,000 excluding 
$1,005,000 to be contributed by local interests. 
Estimated total cost for local interests is 
$1,580,000. 
Local cooperation. Responsible local interests 
must contribute in cash 50 percent of that portion 
of the first cost of Federal construction allocated 
to recreational navigation, exclusive of aids to 
navigation, a contribution presently estimated at 
$1,013,000 less 50 percent of that portion of the 
first cost of parking facilities associated with 
breakwater fishing to be provided locally, the 
amount involved currently being estimated at 
$8,000 the estimated net contribution of $1,005,- 
000 to be paid in a lump sum prior to initiation of 
construction, or in installments over the construction 
period at a rate proportinate to the proposed 
or scheduled expenditure of Federal funds as required 
by the Chief of Engineers, the final apportionment 
of cost to be made after actual costs have 
been determined; provide without cost to the United 
States all lands, easements, and right-of-way 
required for construction and subsequent 
maintenance of the project and for aids to navigation 
upon the request of the Chief of Engineers, 
including suitable areas determined by the Chief 
of Engineers to be required in the general public 
interest for initial and subsequent disposal of 
spoil and any necessary retaining dikes, 
bulkheads, and embankments therefore, or the 
cost of such retaining works; hold and save the 
United States free from all claims for damages 
incident to the construction, operation, and 
maintenance of the improvement; establish a 
competent and properly consitituted public body 
empowered to regulate the use, growth, and 
development of the harbor and related facilities 
with the understanding that said facilities will be 
open to all on equal terms; provide and maintain 
without cost to the United States necessary mooring 
facilities and service area, including a public 
landing with suitable provisions for the sale of 
motor fuel, lubricants, and potable water, 
sanitary facilities, a launching ramp, reservation 
of space for transient craft, parking areas, and 
access roads, open to all on equal terms; the 
dredging of berthing areas to be commensurate 
with the depth of the Federal channel improvements; 
and in addition maintain the existing 
State Pier; establish regulations 
prohibiting discharge of untreated sewage, garbage, 
and other pollutants in the waters of the 
harbor by users thereof, which regulations shall 
be in accordance with applicable laws or 
regulations of Federal, State, and local 
authorities responsible for pollution prevention 
and control; and bear all costs of maintenance, 
operation, and replacement of access facilities, 
parking areas, and sanitary facilities for 
recreational fishing; and provided further the improvement 
for navigation may be undertaken independently 
of the public recreational facilities 
for breakwater fishing whenever the required 
local cooperation for navigation has been furnished. 
Operations and results during fiscal 
year. Preconstruction planning was continued 
at a cost of $112,997. 
Condition at end of fiscal year. Construction 
has not started. 
43. TOLEDO HARBOR, OHIO 
Location. Comprises lower 7 miles of Maumee 
River and channel through Maumee Bay to Lake 
Erie. Maumee River has its source in northern Indiana 
and empties into Lake Erie. Harbor is at 
westerly end of Lake Erie, 99 miles westerly from 
Cleveland, Ohio. (See Lake Survey Chart 374.) 
Previous projects. For details see page 1959 of 
Annual Report for 1915, and page 1565 ofAnnual 
Report for 1938. 
Existing project. A channel 28 feet deep and 
500 feet wide from deep water in Lake Erie about 
18 miles to mouth of Maumee River; including a 
widening of 38.6 acres opposite Chesapeake & 
Ohio Railway and Lakefront Terminal Co. docks; 
31-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
a channel in the river 27 feet deep and 400 feet 
wide from mile 0 (river mouth) to mile 3; thence a 
channel 400 feet wide to mile 6.5 with depths of 27 
feet over a least width of 200 feet and 25 feet over 
remaining 400-foot channel width; thence a 
channel 25 feet deep and 200 feet wide to upper 
limit of project, mile 7; for a turning basin opposite 
American Shipbuilding Co. docks (mile 
2.7) 750 feet wide, 800 feet long, and 20 feet deep; 
a turning basin just upstream of old Fassett 
Street Bridge (mile 6.5) generally semicircular in 
shape with a radius of 730 feet, and 27 feet deep; 
and a turning basin 18 feet deep and 8.25 acres in 
area at upper project limit. Project also provides 
for clearing sailing course between Maumee Bay 
Channel and East Outer Channel, Detroit River, 
to 28 feet deep over a width of 1,200 feet. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Maumee River through 
city of Toledo has been developed extensively for 
deep-draft navigation. Detailed information on 
actual port and harbor facilities are in Port Series 
No. 44 (revisied 1972) prepared and published as 
Part 2, by Board of Engineers for Rivers and Harbors. 
Information on port administration and 
Federal services, port and terminal services and 
charges, and steamship services is prepared and 
published as Part I by the Port Development 
Staff, U.S. Department of Commerce. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal 
year. Maintenance: Miscellaneous inspection 
services, support of Water Control Center, condition 
surveys, Hi-Fix surveys were performed by 
Government forces at a cost of $142,342. The U.S. 
Hopper Dredges HOFFMAN and MARKHAM 
performed maintenance dredging removing 
798,797 and 1,624,294 cubic yards, bin measure, 
of shoal material respectively at a cost of $182,095 
and $874,176. Maintenance of Island disposal 
area and pipeline equipment was performed at a 
cost of $225,881 maintenance of Penn 8 disposal 
area was performed at a cost of $83,145. Removal 
of debris was accomplished at a cost of $53,220. 
Engineering and design, construction layouts, 
supervision and administration cost $14,967. The 
contract awarded last fiscal year for construction 
of a confined disposal area under the Diked Disposal 
Program is approximately 86% complete at 
a cost of $15,321,025. Engineering and design 
support during construction was performed at a 
cost of $66,581. Supervision and administration, 
construction layouts, surveys were performed at 
a cost of $233,369. Total fiscal year cost under the 
Diked Disposal Program was $15,620,975. 
Condition at end of fiscal year. The existing 
project is complete. Total cost of existing project 
was $51,713,741 of which $29,137,288 was 
regular funds (new work and maintenance prior 
to 1903 were not separable at $29,073,948, 
maintenance since 1903 was $36,146,595 and $3,- 
690,000 public works funds were used for new 
work). 
44. WHITEFISH POINT HARBOR, 
MICH. 
Location. On south shore of Lake Superior 40 
miles northwesterly from Sault Ste. Marie, 
Mich., and 53 miles easterly from Grand Marais, 
Mich. (See U.S. Lake Survey Chart No. 92.) 
Existing project. Provides for a harbor of 
refuge protected by two breakwater structures 
and for dredging a harbor basin and entrance 
channel, 12 feet deep. The addition of a 270-foot 
wave absorbing breakwater inside the harbor 
was approved by the Chief of Engineers on 
August 17, 1967 to correct a design deficiency. 
(See Table 31-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one privately 
owned fishing wharf and a small-boat pier and 
launching ramp built by the State of Michigan. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: Condition surveys were performed 
by Government forces at a cost of $1,729. 
Engineering and design on confined disposal 
area for polluted dredging was performed at a 
cost of $824. 
Condition at end of fiscal year. Existing project 
was completed in 1960. The interior 
breakwater and repairs to the shore connection 
were accomplished by contract during fiscal year 
1969. Remaining structures are in generally good 
condition. Total cost of existing project was $889,- 
903, of which $771,639 was for new work and 
$118,264 was for maintenance. 
45. WHITE LAKE HARBOR, MICH. 
Location. On east shore of Lake Michigan 120 
miles northeasterly from Chicago, Ill., and 45 
miles southerly from Ludington, Mich. (See Lake 
Survey Chart 768.) 
Existing project. Parallel piers, revetments, 
and a channel. Channel is 16 feet deep, 200 feet 
wide, 1,950 feet long, and extends from Lake 
Michigan to White Lake. For additional details 
see page 1465 of Annual Report for 1962. (See 
Table 31-B for authorizing legislation.) 
31-24

DETROIT, MICH., DISTRICT 
Local cooperation. None required. 
Terminal facilities. A privately owned 
chemical shipping dock on north side of lake 
about 3 miles from inner end of revetted entrance 
channel. Across lake, at village of Whitehall, 
there are several installations serving light draft 
vessels. These terminals satisfy present 
recreational and commercial traffic requirements. 
Operations and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
inspection services were performed by 
Government forces at a cost of $6,050. Repairs to 
the revetment were made by hired labor and contract 
at a cost of $31,326. The U.S. Hopper 
Dredge HAINS performed maintenance dredging 
removing 44,495 cubic yards, bin measure, of 
shoal material at a cost of $53,222. Engineering, 
design surveys, supervision and administration 
cost $5,902. Engineering and design studies under 
Section 111 P.L. 90-483 for prevention or 
mitigation of shore damage attributable to 
Federal navigation work was performed at a cost 
of $92,964. 
Condition at end of fiscal year. Existing project 
was completed in 1908. Stone was placed on 
the north and south revetments in fiscal year 
1972. The structures are in generally good condition 
except sections B, C and D of the south pier. 
Total cost to end of fiscal year is $1,696,607, of 
which $207,862 was for new work and $1,488,744 
was for maintenance. 
46. RECONNAISSANCE AND 
CONDITION SURVEYS 
See Table 31-E. 
47. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 31-F. 
48. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
Studies during fiscal year were conducted for 
the following harbors: Charlevoix Harbor, 
Michigan $12,400; Detour Harbor, Michigan 
$59,125; Grindstone City $60,125; Sterling State 
Park $25,671. 
BEACH EROSION CONTROL 
49. AUTHORIZED BEACH 
EROSION CONTROL 
PROJECTS 
Beach erosion control projects are authorized 
at Berrien County Shore (St. Joseph) Michigan, 
and Crane Creek State Park, Ohio. For last full 
report see Annual Report for 1963 (Berrien County) 
and 1968 (Crane Creek). 
FLOOD CONTROL 
50. KALAMAZOO RIVER, 
BATTLE CREEK, MICH. 
Location. River drains an area of 1,980 square 
miles in Hillsdale, Jackson, Calhoun, Eaton, 
Barry, Kalamazoo, Van Buren, Allegan, Kent, 
and Ottawa Counties in southwestern Michigan, 
and discharges into Lake Michigan 2 miles 
downstream from village of Saugatuck. City of 
Battle Creek is 108 miles upstream from mouth of 
Kalamazoo River. (See Geological Survey Battle 
Creek quadrangle and Lake Survey Chart 76.) 
Existing project. Flood protection along 
Kalamazoo River at, and in vicinity of, Battle 
Creek, Mich., to consist generally of excavation 
and clearing of Battle Creek Channel to provide 
for an enlarged channel within city of Battle 
Creek extending from above Union Street Bridge 
downstream to its Channel near Liberty Street 
and Washington Avenue to bypass constricted existing 
channel through heart of city; excavation 
and straightening Kalamazoo River Channel 
downstream from confluence of Battle Creek and 
new rerouted Kalamazoo River Channel to below 
Fort Custer Waterworks Bridge; riprapping or 
paving channels at critical locations in new 
enlarged channels where velocity of floodflows 
might be high enough to cause damage; constructing 
new and reinforcing existing highway and 
railroad bridges as required, and constructing 
levees. Project is designed to provide protection 
for city of Battle Creek from such peak-flood discharges 
in channels which would produce, when 
combined, a discharge of about 11,000 cubic feet 
per second below confluence of Battle Creek and 
Kalamazoo River. Estimated (1975) cost for new 
work is $9,700,000, excluding $244,000 to be contributed 
by local interests. Estimated cost (1975) 
to local interests is $4,770,000. 
Local cooperation. Act of September 3, 1954, 
provides that no money shall be expended on construction 
by the United States until responsible 
local interests give assurances they will provide 
lands and rights-of-way for construction; hold the 
United States free from damages; maintain and 
31-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
operate all works after completion, including 
supervision of maintenance and operation of existing 
Monroe Street Dam and headrace on 
Kalamazoo River; prescribe and enforce 
regulations designed to prevent encroachments 
on rights-of-way and improved channels; construct 
new highway bridges across new 
Kalamazoo River cutoff; make all changes and 
additions to streets, necessitated by improvements; 
and contribute toward project in accordance 
with recommendation of Secretary of 
the Army; and provided further that construction 
of initial stage of project as defined in District 
Engineer's report may be undertaken whenever 
funds are available and prescribed local cooperation 
has been provided and whenever local interests 
agree to remove at their own expense concurrently 
with construction of first-stage improvement, 
such buildings from Battle Creek 
Channel as in opinion of District Engineer may 
jeopardize effectiveness of that improvement. 
The first stage of project is defined as entire project 
exclusive of Battle Creek channel portion upstream 
from its junction with Kalamazoo River. 
At time of authorization of improvement the 
Secretary of the Army recommended in the project 
document that a cash contribution of $93,000, 
at report price levels, should be made by non- 
Federal interests. Assurances were furnished by 
city of Battle Creek and formally accepted by the 
United States December 10,1956. Local interests 
made a cash contribution of $125,000 and allowed 
credit for channel construction and bridge 
removal work accomplished by them at old confluence 
of Kalamazoo River and Battle Creek 
channels. Cash contribution received, credits 
allowed for work accomplished by local interests 
and anticipated savings in Federal construction 
costs due to reduced capacity of a portion of Battle 
Creek channel from abandonment of headrace, 
partially offset by increased cost of cutoff channel 
due to increased capacity, were collectively considered 
sufficient for expenditure of funds for 
completion of first stage of project. An additional 
cash contribution will be required before starting 
final stage of project. All local cooperation required 
for first-stage of project has been complied 
with. 
Operations and results during fiscal 
year. New Work: Preconstruction planning for 
the project was continued at a cost of $100. 
51. KALAMAZOO RIVER, 
KALAMAZOO, MICH. 
Location. Rises in southern part of lower 
peninsula of Michigan, flows northwesterlyj85 
miles, and empties into Lake Michigan 2 miles 
downstream from village of Saugatuck. It drains 
an area of 1,980 square miles. City of Kalamazoo 
lies 75 miles upstream from mouth of river. (See 
Geological Survey Kalamazoo quadrangle.) 
Existing project. Provides for flood protection 
at and near Kalamazoo to consist generally of 
widening, deepening, and straightening the river 
channel from immediately above Comstock about 
10 miles to near Cooper. Plan would include 
riprapping channel where necessary to prevent 
erosion at critical locations, reconstruction and 
reinforcement of railroad and highway bridges 
as required, and necessary alterations to existing 
buildings and utilities. Cost estimate for new 
work (July 1975) is $23,300,000 excluding $1,- 
240,000 to be contributed by local interests. Estimate 
of cost to local interests (July 1975) is $3,- 
150,000. (See Table 31-B for authorizing legislation.) 
Local cooperation. Act of July 3, 1958, 
provides that no money shall be expended by the 
United States until responsible local interests 
give assurances they will provide necessary 
lands, easements, and rights-of-way; hold the United 
States free from damages; maintain and 
operate all works after completion in accordance 
with regulations prescribed by the Secretary of 
the Army; prescribe and enforce regulations 
designed to prevent encroachments on rights-ofway 
and improved channels; raise all buildings 
and roadways in disposal areas as necessary to 
meet proposed grades; and make all utility 
changes necessitated by improvements; and 
provided further that Federal construction shall 
not be started until abatement of pollution of 
Kalamazoo River at and near Kalamazoo has 
been initiated by local interests to an extent 
satisfactory to the State of Michigan; and contribute 
in cash 5 percent of estimated first cost of 
work for which the United States would be 
responsible; a contribution presently estimated at 
(July 1975) $1,085,000. 
Operations and results during fiscal 
year. New Work: Preconstruction planning for 
the project was continued at a cost of $10,000. 
Planning continued to develop alternative plans 
which will mitigate the impact of the project on 
the environment. 
Condition at end of fiscal year. Construction 
has not started. 
52. POINT PLACE, TOLEDO, OHIO 
Location. Point Place is located on a peninsula 
in the northeast portion of the city of Toledo, Ohio. 
Its shores are bounded on the east by Maumee 
Bay of Lake Erie and on the west by the Ottawa 
31-26

DETROIT, MICH., DISTRICT 
River. The peninsula extends in a northeasterly 
direction immediately north of the mouth of the 
Maumee River. The study area consists of 210 
acres which includes 25 acres of vacant land. 
Existing project. Provides for flood protection 
consisting primarily of seawall protection for a 
distance of 4,400 feet adjacent to Maumee Bay 
from the midpoint of 134th and 135th Streets to 
the end of 145th Street, modification of 1,900 feet 
of the existing earth levee east of 326th Street extending 
northerly from 145th Street to the 
Michigan-Ohio State line, and construction of an 
1,800-foot levee adjacent to the State line. Cost estimate 
for the work (May 1975) is $1,300,000 excluding 
$460,000 to be contributed by local interests. 
Estimate of cost to local interests (May 
1975) is $560,000. (See Table 31-B for authorizing 
legislation.) 
Local cooperation. Responsible local interests, 
prior to construction, must furnish 
assurances satisfactory to the Secretary of the 
Army that they will: Provide without cost to the 
United States all lands, easements, and rights-ofway 
necessary for construction of the project; 
hold and save the United States free from 
damages due to the construction works; maintain 
and operate all the works after completion in accordance 
with regulations prescribed by the 
Secretary of the Army; accomplish without cost 
to the United States all necessary changes to 
buildings, highway bridges including approaches, 
streets, sewers, and utilities, as may be 
required for construction of the project; bear 30 
percent of the total cost, a sum presently estimated 
at (May 1975) $560,000 which includes 
the cost of lands, easements, rights-of-way, and 
relocations required under paragraphs above, 
and a cash contribution presently estimated at 
$460,000; to be paid either in a lump sum prior to 
initiation of construction, or in installments prior 
to commencement of pertinent work items, in accordance 
with construction schedules as required 
by the Chief of Engineers, the final apportionment 
of cost to be made after actual costs and 
values have been determined; and at least annually 
inform affected interests that the project will 
not provide complete flood protection. 
Operations and results during fiscal 
year. New Work: Preconstruction planning, initiated 
in fiscal year 1974, was continued at a cost 
of $83,000. Alternate plans were developed for 
protection of the Point Place Peninsula which extends 
the limits of protection on Maumee Bay to 
129th Street. The reformulation of plans also 
provides for extensive levee works along the Ottawa 
River shore of the peninsula and the addition 
of pumping facilities to handle interior 
runoff. These changes are being considered in the 
revised project plan due to the record high Lake 
Erie water levels that were experienced following 
project authorization. Limits of the revised 
project would correspond to those established at 
Point Place during the Operation Foresight 
program when it was necessary to provide 
emergency protection works. A discussion of the 
Operation Foresight program is provided in 
paragraph 59, Flood Control Work Under 
Special Authorization. 
Condition at end of fiscal year. Construction 
has not started. 
53. RED RUN DRAIN-LOWER CLINTON 
RIVER, MICH. 
Location. The Clinton River basin has an area 
of 760 square miles and includes parts of 
Macomb, Oakland, St. Clair and Lapeer Counties 
in the Southeastern portion of the lower peninsula 
of Michigan. The project itself is located in the 
southeastern section of the basin. 
Existing project. Provides for abandonment 
of the upper 2 miles of the Red Run Drain in 
Oakland County and for enlarging and paving the 
Red Run Drain from Dequindre Road on the west 
downstream to the Main Branch, Clinton River a 
distance of approximately 8Y2 miles. Bottom 
widths of the channel would vary from 70 to 240 
feet. The Main Branch, Clinton River would be 
widened, deepened and straightened for a distance 
of about 4% miles. The channel width would 
vary from 180 to 200 feet and adjacent lands 
would be maintained as a floodway with a width 
of 500 feet. The authorized plan provides for a rectangular 
concrete-lined channel below this point, 
varying in width from 180 to 210 ufeet, to the existing 
Clinton River Cut-Off Canal, a distance of 
about 2 miles. The Cut-Off Canal would consist of 
a rectangular channel with concrete bottom 210 
feet wide and steel sheet pile walls in the upper 1% 
miles and a trapezoidal concrete-lined channel 
with a 170-foot bottom width and 75-foot wide 
benches placed on each bank over the lower mile 
of the Canal to Lake St. Clair. The authorized 
plan would provide protection for surrounding 
urban areas against rainfall and flood having a 
1.0 percent chance of occurrence render anticipated 
urbanized basin conditions in the year 
2000. The cost estimate for new work (July 1975) 
is $208,000,000 excluding $49,225,000 to be contributed 
by local interests. Estimate of cost to 
local interests (July 1975) is $82,500,000. 
Local cooperation. Prior to construction, local 
interests must furnish assurances satisfactory to 
the Secretary of the Army that they will: Provide 
without cost to the United States all lands, 
easements, rights-of-way, utility relocations, and 
31-27

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
highway bridge alterations necessary for construction 
of the channel improvements; presently 
estimated at (July 1975) $8,550,000 for Red Run 
Drain and (July 1975) $24,635,000 for Lower 
Clinton River; hold and save the United States 
free from damages due to the construction works; 
maintain and operate all the works after completion 
in accordance with regulations prescribed by 
the Secretary of the Army; contribute in cash a 
sum presently estimated at (July 1975) $46,580,- 
000, which, together with items applicable to Red 
Run Drain to be furnished in above, would constitute 
50 percent of all flood control costs for Red 
Run Drain; prevent or restrict development in the 
project area by providing easements or by establishing 
and enforcing flood plain regulations 
where such development would result in the increase 
of damageable property in the flood plain 
or would necessitate modifications, or reduce the 
efficiency of, the project; prevent encroachment 
on the project channels and ponding areas which 
would decrease the effectiveness of the improvements, 
and, if ponding areas and capacities 
are impared, promptly provide substitute 
capacities to restore the effectiveness of the project; 
regulate the quality of the water in the project 
channels by establishing and enforcing water 
quality standards commensurate with Federal, 
State, and local standards; hold and save the United 
States free from damages due to the construction 
and operation of any pollution abatement 
structures constructed by local interests on 
Red Run Drain in Oakland County; and for 
recreation; provide all lands and rights-of-way, 
presently estimated at (July 1975) $90,000, required 
to insure realization of the benefits; make 
additional contributions, presently estimated at 
(July 1975) $2,645,000 to bring the non-Federal 
share of costs to at least 50 percent of the total 
costs of recreation development, which may consist 
of the actual cost of carrying out an agreedupon 
portion of the development, a cash contribution, 
or a combination of both; operate and maintain 
the recreation facilities for the life of the project; 
and provide access to all on equal terms. 
Operations and results during fiscal 
year. Preconstruction planning was initiated at 
a cost of $34,999. 
Condition at end of fiscal year. Construction 
has not started. 
54. RIVER ROUGE, MICH. 
Location. River Rouge basin is in the 
southeastern corner of the lower peninsula of the 
State of Michigan, within Wayne, Oakland and 
Washtenaw Counties. Basin is fan shaped and extends 
about 24 miles from north to south and - 
about 33 miles from east to west. Total area comprises 
about 464 square miles. (See Geological 
Survey, Detroit quadangle.) 
Existing project. Provides for flood protection 
along main stem of Rouge River from navigation 
turning basin to Michigan Avenue consisting of 
channel enlargement and straightening and 
alteration or replacement of existing bridges. 
Channel work includes deepening, widening, 
straightening, and paving existing river channel 
for about 30,300 feet along existing channel. 
Realigned channel will have a length of 22,100 
feet. Channel depths under design discharge conditions 
vary from about 25 feet at navigation turning 
basin to about 20 feet at Michigan Avenue. 
Bridge work involves construction of one new 
railroad bridge and alteration of two railroad 
bridges at Federal expense and construction and 
alteration of highway bridges at local interest expense. 
Project is designed to provide protection 
for a peak-flood discharge of about 24,000 cubic 
feet per second. Estimated (July 1973) Federal 
cost for new work is $26,200,000. Estimated (July 
1974) cost to local interests is $8,700,000. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Responsible local interests 
must furnish areas necessary for construction; 
hold the United States free from damages; maintain 
and operate all works after completion; 
prescribe and enforce regulations designed to 
prevent encroachments on proposed rights-ofway 
and improved channel, and keep nonpilesupported 
bank loads a minimum distance of 50 
feet from top of bank; construct new highway 
bridges as required; and make all alterations and 
additions to highway bridges, utility crossings, 
sewer outlets, and interfering structures within 
proposed channel rights-of-way. The required 
assurances, dated June 10, 1966, were furnished 
by the Wayne County Road Commission and 
accepted by the District Engineer on July 6, 1966. 
Local interests have constructed new bridges at 
Southfield Road and Rotunda Drive; altered and 
extended the Greenfield Road Bridge; and have 
under construction the Michigan Avenue and 
Schaefer Road bridges. The Commission has also 
acquired all of the project right-of-way and local 
interests have completed approximately 20 percent 
of the utility alterations. 
Operations and results during fiscal 
year. New Work: The contract for relocation 
and alteration of Penn Central Railroad Bridge 
awarded last fiscal year was completed at a cost of 
$1,094,865. An adjustment was made in contract 
cost for Section A completed last fiscal year in the 
amount of $117,334. The contract for Section B is 
approximately 71% complete at a cost of $2,341,- 
608. Preconstruction planning for other phases of 
31-28

DETROIT, MICH., DISTRICT 
River Rouge Flood Control Project was continued 
at a cost of $152,329. Supervision and administration 
in connection with these contracts cost $217,- 
813. 
Condition at end of fiscal year. The contract 
for the two span extension of the DT&I Railroad 
Bridge was initiated in fiscal year 1968 and completed 
in fiscal year 1969. The construction of the 
New York Central Railroad Bridge was initiated 
in fiscal year 1968 and was completed in fiscal 
year 1970. The contract for construction of Section 
A was awarded in May 1970 and was completed 
in fiscal year 1975. Section B was awarded 
in June 1972 with a scheduled completion date in 
fiscal year 1977. 
55. SAGINAW RIVER, MICH. 
Location. River including its tributaries, Tittabawassee, 
Shiawassee, Flint and Cass Rivers, 
drains an area of 6,260 square miles in eastcentral 
Michigan and empties into Saginaw Bay,. 
an arm of Lake Huron. Bay City, near mouth of 
river, and Saginaw, 22 miles upstream from 
mouth, are on Federally improved deep-draft 
Saginaw River navigation channel. (See 
Geological Survey Saginaw and Flint 
quadrangles and Lake Survey Chart 524.) 
Existing project. Provides for improvements 
in Saginaw River Basin for flood control and 
other purposes: (a) at Middle Branch and South 
Branch, Cass River, to provide for major 
drainage improvements by channel improvements 
on Middle and South Branches, including 
a short reach of East Branch, at an estimated 
U.S. cost (July 1961) for construction of 
$1,448,000 for Middle and South Branches; 
provided local interests contribute in cash 42 percent 
of first cost of major drainage projecton Middle 
Branch, and 38 percent of first cost of major 
drainage project on South Branch, exclusive of 
cost of rights-of-way and other work required as 
local cooperation, and give assurances satisfactory 
to Secretary of the Army they will construct 
and maintain'local drainage work required to fully 
and effectively utilize improvements to be 
provided under the Federal projects; (b) at 
Vassar on Cass River, to provide for flood protection 
of areas on north and south sides of river by 
channel improvement, levee construction, 
floodwalls, modification of Moore Drain, and 
related work, at an estimated U.S. cost (July 
1961) of $1,700,000 for construction; (c) at 
Frankenmuth on Cass River, to provide for flood 
protection of areas on north side of river by 
channel improvement, levee construction, and 
related work, at an estimated U.S. cost (July 
1974) of $410,900 for construction; (d) at Flint on 
Flint River, to provide for flood protection of 
areas on both sides of main stem of Flint River 
and its tributaries, Swartz and Thread Creeks, by 
channel improvement, bridge alterations, 
floodwall and levee construction, and related 
work, at an' estimated U.S. cost (July 1974) of 
$13,829,100 for construction; provided local interests 
contribute in cash 1 percent of first cost of 
project, exclusive of costs of rights-of-way and 
other work required as local cooperation; (e) at 
Corunna on Shiawassee River, to provide for flood 
protection by channel improvement, levee construction, 
and related work, at an estimated U.S. 
cost (July 1961) of $48,000 for construction; 
provided local interests modify spillway of mill 
dam at Corunna at their own expense, substantially 
in accordance with plan of District 
Engineer and subject to approval of Chief of 
Engineers, or, in lieu thereof, contribute to the 
United States actual cost of modification to be 
performed by the United States; (f) at Owosso on 
Shiawassee River, to provide for flood protection 
by channel improvement at an estimated U.S. 
cost (July 1961) of $425,000 for construction; (g) at 
Midland on Tittabawassee River, to provide for 
flood protection by channel improvement, levee 
construction, and related work, at an estimated 
U.S. cost (July 1974) of $4,060,000 for construction; 
provided local interests contribute in cash 2 
percent of first cost of project, exclusive of costs of 
rights-of-way and other work required as local 
cooperation. 
(h) at Shiawassee Flats along lower reaches of 
the four principal tributaries of Saginaw River, 
to provide for flood protection, including fish and 
wildlife areas, by channel improvement, levees, 
lateral reservoirs with control structures and 
related work, at an estimated U.S. cost (July 
1974) of $30,440,000 for new work, of which $27,- 
300,000 is allocated to flood control and $3,140,- 
000 to fish and wildlife purposes; provided local 
interests contribute in cash 5 percent of cost of 
rights-of-way for flood control and other work required 
as local cooperation, and furnish one-half 
of land required for fish and wildlife areas; 
provided that the Federal allocation for conservation 
does not exceed amount obtained by taking 
28 percent of project cost for Shiawassee Flats 
unit and subtracting therefrom one-half cost of 
lands for conservation; and provided further that 
before starting works for flood control to 
Shiawassee Flats, Chief of Engineers and Director, 
Fish and Wildlife Service, prepare a plan 
mutually acceptable to Secretary of the Army 
and Secretary of the Interior for operation of fish 
and wildlife areas to provide required degree of 
controlled storage of floodwaters while preserving 
the maximum fish and wildlife benefits. 
Total estimated cost for new work, for active por- 
31-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
tion (1974) is $45,600,000 excluding $3,140,000. 
Fish and Wildlife costs and $1,313,000 to be contributed 
by local interests. Total estimated cost 
(1974) to local interests is $6,951,000. 
Local cooperation. Responsible local interests 
must make cash contributions as called for above; 
furnish lands, and rights-of-way, including 
removal of buildings, for construction; hold the 
United States free from damage; maintain and 
operate all works after completion; establish and 
enforce regulations designed to prevent encroachments 
in improved channels; and bear expense 
of constructing highway relocations and 
highway bridges, alter bridge approaches and 
existing highway bridges (except underpinning 
and bridge raising), and alter utilities. Required 
assurances for Flint River at Flint were furnished 
by city of Flint and accepted by the United 
States 23 November 1962. Estimated required 
cash contribution for Flint ($56,000) was furnished 
20 February 1963. An additional $36,000 
was furnished by the City to cover increased construction 
costs. Required assurances for Cass 
River at Frankenmuth were accepted on 8 
September 1964. All necessary lands, easements, 
and rights-of-way have been provided. The 
Midland City Council and the Midland County 
Board of Supervisors have, by resolution, indicated 
their intent to enter into a joint contract to 
provide the assurances of local cooperation for the 
Midland Flood Control Project. 
Operations and results during fiscal 
year. New Work: An adjustment of $43,000 was 
made in the contract for construction of Section 
A. The contract for construction of Cl and D was 
completed at a cost of $782,267. Supervision and 
administration of the contract cost $83,749. 
Preconstruction planning for other phases if 
Flint, Midland and Shiawassee was continued at 
a cost of $271,553, $123,372 and $1,685, respectively. 
Preconstruction planning for Section C-2 
was continued. 
Condition at end of fiscal year. Construction 
at Frankenmuth was completed in 1967. Section 
A of the Flint project was completed in 1967 and 
the Stevenson Street Bridge was completed in 
1968. Section B was initiated in 1968 and completed 
in October 1970. The contract for construction 
of C-1 and D was initiated in 1974 and was 
completed in 1975. 
56. SEBEWAING, SEBEWAING 
RIVER, MICH. 
Location. Sebewaing River drains an area of 
105 square miles in Huron and Tuscola Counties 
on westerly side of Thumb area of Lower Peninsula 
of Michigan and discharges into Saginaw 
Bay, an arm of Lake Huron, 20 miles northeast 
from mouth of Saginaw River. Village of Sebewaing 
is near mouth of river. (See Lake Survey 
Chart 52.) 
Existing project. Enlarging present channel 
of Sebewaing River through village of Sebewaing, 
Michigan, to a capacity of 7,500 cubic feet per 
second from junction of Columbia and State 
drains to a point 4,500 feet lakeward from 
railroad bridge near mouth; altering railroad 
bridge and three highway bridges to permit free 
passage of ice; and removal of present dike on 
south side of channel lakeward from railroad 
bridge. Project is designed to provide protection 
for village of Sebewaing from floods with a frequency 
of once in 15 years and with a magnitude 
greater than the maximum flood of record. (See 
Table 31-B for authorizing legislation.) 
Local cooperation. Complied with except for 
furnishing easements and rights-of-way for 
removal of remaining portion of dike on south 
side of channel lakeward from railroad bridge. 
Operation and results during fiscal 
year. Maintenance: Condition surveys and miscellaneous 
imspection services were performed 
by Government forces at a cost of $10,000. 
Condition at end of fiscal year. Existing project 
was completed in 1948 except for removal of 
remaining portion of old earth dike which is on 
the south side of the channel lakeward from the 
railroad bridge. 
57. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The listed projects were inspected during fiscal 
year 1975. Battle Creek, Kalamazoo River, 
Michigan; Kawkawlin, Kawkawlin River, 
Michigan; Sebewaing, Sebewaing River, 
Michigan; Flint, Flint River, Michigan; 
Frankenmuth, Cass River, Michigan; Mount 
Clemens Spillway and Cutoff Canal, Clinton 
River, Michigan; Red Run, Clinton River, 
Michigan; East Rockwood, Silver Creek, 
Michigan; Estral Beach, Lake Erie, Michigan; 
Reno Beach-Howard Farms, Lake Erie, Ohio; 
LaCarne-Camp Perry, Lake Erie, Ohio; Fort 
Wayne Mechanic St. Dike, St. Marys River, Indiana; 
Burr Oak, Prairie River, Michigan. 
Fiscal year costs were $36,000. Total costs to 
end of fiscal year were $189,668. 
58. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 31-G. 
31-30

DETROIT, MICH., DISTRICT 
59. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Emergency Flood Control Activities: Repair, 
Flood Fighting, and Rescue Work (Public Law 99, 
84th Cong., and Antecedent Legislation). During 
FY 1975 the Detroit District expended approximately 
$72,000.00 making emergency 
repairs to "FORESIGHT" constructed dikes on 
Lake Erie. The "FORESIGHT" program was initiated 
in December 1972 with construction completed 
by the end of Fiscal Year 1974. Lake levels 
on the Great Lakes remain high and the 
FORESIGHT structures are still providing 
protection. The overall project costs exceeded 20 
million dollars. Thru the end of Fiscal Year 1975 
the total estimated accumulated prevented 
damages exceed 91 million dollars. 
In April 1975, the Detroit District became involved 
in a major flood fight in 21 southern counties 
of Michigan. The Detroit District spent approximately 
$211,000 for the flood fight by 
supplying sandbags, equipment and personnel. 
No construction contracts were initiated. 
60. SURVEY OF NORTH CENTRAL 
LAKES 
Field Operations. The following reports on 
the results of field discharge measurements were 
completed: 1973, St. Clair River flow 
measurements: 1973 & 1974, Niagara River 
Cableway measurements: 1974, Upper Niagara 
River flow measurements: 1974, St. Lawrence 
River flow distribution measurements: 1973, 
Detroit River flow measurements: 1974 June, 
Lake Superior control structure 
measurements: Field operations conducted during 
the current fiscal year: August 74, Niagara 
River Cableway Measurements: Upper 
Niagara flow measurements: Lower Detroit 
River Discharge Measurements for Lake Erie 
Wastewater Management Study: Power Canal 
flow measurements (3 sites) in St. Marys River to 
verify power diversion ratings. Winter navigation 
monitoring of ice, and its effect on docks, 
shoreline and navigation in the St. Marys, St. 
Clair and Detroit Rivers. The District also 
monitors daily key water level gages in the St. 
Marys and St. Clair Rivers during the winter 
months to provide advance warning of ice jams 
and potential flooding to area residents and other 
government agencies. 
Approximately one-half of the aforementioned 
field work was conducted cooperatively with the 
Water Survey of Canada and was required for the 
International Joint Commission Boards and Committees. 
The remaining work was carried out in 
support of the Great Lakes-St. Lawrence Seaway 
Navigation Season Extension Demonstration 
Program in support of this District's mission. 
International Activities. The following activities 
were conducted specifically for the International 
Joint Commission boards and committees: 
Members of the Detroit District staff attended 
the appearances of the Great Lakes Boards before 
the Commission. 
International Lake Superior Board of Control. 
The Detroit District Engineer became the United 
States Regulation Representative for the Board 
of Control. In support of the U.S. Section of the 
Board the District made monthly Lake Superior 
outflow recommendations based upon a review of 
the hydrologic factors which influence the future 
regulation of Lake Superior. These recommendations 
were based on a probability forecast of 
water supply using outflows determined by both 
the 1955 Modified Rule of 1949 (the current approved 
operating rule) and Plan SO-901 (a plan 
recommended by the International Great Lakes 
Levels Board. 
Periodic reports of water levels and recommendations 
regarding regulation of Lake Superior 
were furnished to the Board. In conjunction with 
the periodic reports, the Board is being provided 
with a forecast of lake conditions based on various 
future water supply conditions. The technique for 
making this forecast was developed jointly by the 
Detroit District and the Department of Environment, 
Canada. Computation of the effects of Lake 
Superior regulation and deviation from the 
currently approved operating plan on the lower 
lakes is being kept current for the Board's use and 
information. An "Operational Guide" for a new 
operating plan was prepared. Joint Canadian and 
U.S. discharge measurements were made to 
verify the ratings at the three power canal diversions 
of the St. Marys River. In addition, an experimental 
metering section was set up above the 
Compensating Works in an effort to recalibrate 
the control gates. 
International Niagara Board of Control and International 
Niagara Working Committee. A 
member of the Detroit District Staff, acting as 
hydraulic consultant to the Buffalo District and 
to the U.S. section of the Working Committee, 
attended meetings of the Board and the Working 
Committee. During the period measurements 
continued to be made from the Lower Niagara 
River cableway metering section to check the 
Maid-of-the-Mist Pool rating curve. Also reports 
were completed on these measurements and on 
the effect of land fill operations on Lake Erie - 
31-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Niagara River water levels. 
International St. Lawrence River Board of 
Control and St. Lawrence Committee on River 
Gaging. A member of the Detroit District staff, 
acting as hydraulic consultant, attended 
meetings of the Board and River Gaging Committee. 
The Board of Control supported the Buffalo 
District in operating and improving the 
current regulation plan (Plan 1958-D) for Lake 
Ontario. This work included extending the basis 
of comparison and the development of modified 
plans of regulation using new limitation curves 
and minimized Lake St. Louis outflows. 
International Great Lakes Levels Board and 
Working Committee. Members of the Detroit District 
Staff attended numerous meetings of the 
Board, its Working Committee and Subcommittees, 
and these staff members served as 
Chairmen of the Regulation Subcommittee and 
Regulatory Works Subcommittee, and as 
members of the Power and Report Subcommittees. 
In addition, technical and consulting 
support was given to the Shore Property and 
Navigation Subcommittees. 
In connection with its chairmanship of the 
Regulation Subcommittee, the Detroit District 
continued development and testing of regulation 
plans for all the Great Lakes and various combinations 
of lakes. Development of partial regulation 
plans for Lake Erie which was not part of the 
original assignment was continued. At the request 
of the U.S. Section of the IJC, Plan SEO- 
42P (a plan developed by the Great Lakes Levels 
Board) was reviewed and modified. This work led 
to the development of Plan SEO-17P, and a final 
report on this regulation plan was prepared. This 
plan increased the release from Lake Erie above 
the present outflow. To provide for this outflow, a 
channel through Squaw Island would be required. 
The development of the required 
regulatory works was accomplished in conjunction 
with the Buffalo District.All plans developed 
in this series have been developed so as not to require 
any modification in the St. Lawrence River 
Channels. 
The Detroit District staff provided the other 
Subcommittees (Shore Property and Navigation) 
with the necessary support to analyze and 
evaluate all regulation plans presented for 
detailed evaluation. This support included aiding 
the Working Committee of the Board in drafting 
the interim and final report on the nine years of 
study conducted unter the reference of 7 October 
1964, aiding the Board in its public hearings on 
the subject of Great Lakes water level problems, 
and continuing work on the "Optimization 
Plans." 
Coordinating Committee on Great Lakes Basin 
Hydraulics and Hydrologic Data. The Great 
Lakes Hydraulic and Hydrology Branch of the 
District provided ex-officio membership on this 
committee and its subcommittees. Operations 
pertaining to the coordinating of basic hydraulic 
and hydrologic data with Canada continued. 
Work during the period included: continuation 
of a report entitled "History of Water Level 
Gages, Upper Great Lakes," completion of the 
Lake Huron water volume determination, 
preparation of reports on Lakes Michigan - 
Huron Outflow, vertical movement within the 
Great Lakes, and Great Lakes physical data, and 
compilation of a catalog of coordinated data. 
International Field Year for the Great Lakes 
(IFYGL). The Detroit District continued its participation 
in IFYGL and conducted the principal 
investigations of the Terrestrial Water Balance 
Panel. Work included reviewing an IFYGL 
report entitled "Two Nations, One Lake - Science 
in Support of Great Lakes Management," completing 
a data analysis on Lake Ontario over-hand 
precipitation and beginning a data analysis on 
Lake Ontario Storage Terms. 
Hydraulics and Hydrology of the Great 
Lakes. The following studies relative to the 
hydrology of the Great Lakes were continued by 
Great Lakes Hydraulics and Hydrology Branch 
staff members: Studies to improve the existing 
Great Lakes levels forecasting system; and on the 
factors affecting the Great Lakes water balance 
relationship (i.e., runoff, precipitation over 
water, evaporation, ice retardation, etc.) 
In connection with these activities, consulting 
engineering services were provided to the Great 
Lakes Basin Commission (Comprehensive Basin 
Framework Study); to the National 
Oceanographic and Atmospheric Administration 
(NOAA), Lake Survey Center, in connection with 
Great Lakes forecast; and to the International 
Field Year on the Great Lakes in connection with 
the Terrestrial Water Balance Panel (Principal 
investigations are provided by this District for 
the studies being conducted by the Panel.) 
As part of its work, the Great Lakes Hydraulics 
and Hydrology Branch was also involved in the 
following: 
Extension of Navigation Season, Ice Information 
Work Group. The major activity involving 
personnel of the Detroit District during FY 75 
consisted of the ice surveillance program on the 
St. Clair, Detroit and St. Marys Rivers in 
response to the Extension of the Navigation 
Season Program. The program included field 
observations of ice effects on shore structures, floe 
patterns in Soo Harbor, water surface profiles 
31-32

DETROIT, MICH., DISTRICT 
and aerial surveillance, including photographs 
and movies. Also, real time information from 
telemetry water level gages and helicopter flights 
relating to ice jams and potential flooding was 
provided to the District Engineer during critical 
ice conditions. A report on these activities was 
completed and plans for the 1975-76 winter activities 
were started. 
High Levels on the Great Lakes. The Great 
Lakes Hydraulics and Hydrology Branch provided 
technical information regarding high lake 
levels and long-range still water forecasts to 
many interested parties such as: Congressmen, 
State and local officials, news media and concerned 
property owners. Information explaining the 
reasons for the high levels and information regarding 
projected levels was supplied to the public in 
the form of direct answers to numerous inquiries, 
addresses to various civic groups and interviews 
with news media. In addition, the Branch made a 
number of special forecasts due to the extreme 
high levels in the Great Lakes in support of NCD, 
the International Joint Commission (IJC), and to 
answer White House and Congressional inquiries. 
Negotiations were held with Canada and 
the Department of Commerce under the auspices 
of the Coordinating Committee on Basic 
Hydraulic and Hydrologic Data, leading to the 
publishing of an International forecast of Great 
Lakes water levels. In support of these forecasts 
and for use in regulation, funds were provided to 
the Department of Commerce for installation and 
maintenance of eight water level telemeter gages 
at selected sites through the Great Lakes to obtain 
more real-time data. In addition, studies were 
conducted to improve the accuracy and 
timeliness of the precipitation values used in 
forecasting. 
Coastal Engineering. The Great Lakes 
Hydraulics and Hydrology Branch provided 
coastal engineering designs, advise and support 
pertaining to dredge disposal projects, harbors, 
navigation channels, beach erosion, permits 
evaluation, local interests, offshore surveys, environmental 
observations and related studies. 
a. Dredge Disposal Projects. Containment 
areas are needed so spoil dredged from harbors 
and navigation channels will not pollute the Great 
Lakes. These containment areas consist of diked 
inclosures to contain dredged spoil. Dikes are 
designed so storm wave action will not breach 
them and release contaminated material into lake 
waters. Consequently, wind and wave studies are 
required to design dike heights, armor stone 
protection, and determine related environmental 
effects that may be expected. Studies were completed 
for Saginaw River and Harbor Beach, and 
are being completed for Port Austin, Sebewaing, 
South Haven, and St. Joseph River. 
b. Harbors. Hydraulic designs were 
prepared for Ludingtion, Grindstone City, 
Detour, Charlevoix, and Port Sanilac. These 
studies served as the basis for determining 
breakwater requirements, crest elevations and 
entrance orientation to minimize wave heights in 
mooring areas. Model tests were completed for 
Ludington Harbor, since the present entrance 
channel to this harbor precluded sufficiently accurate 
analytical calculation of wave heights in 
the harbor with improved navigation channels. 
c. Beach Erosion. As provided for in Section 
111 of the Rivers and Harbors Act of 1968 studies 
were completed to determine the effect of navigation 
structures and channels on littoral drift, and 
thereby contribute to erosion of adjacent 
shorelines. Consequently, studies of eight Lake 
Michigan Harbors and a Lake Huron Harbor 
were undertaken. It was found that navigation 
projects adversely affected the shoreline at each 
of the harbor sites studied. 
d. Permit Evaluations. A Federal permit is 
required for harbor, shore protection, and other 
similar structures constructed along the Great 
Lakes shoreline. Proposed structures are considered 
to determine if they will damage 
neighboring property, block littoral drift, or 
produce other forseeable adverse effects. Also advice 
is provided concerning the desired work. 
During the year, 155 permits were evaluated. 
e. Coastal Flood Levels. One hundred year 
open coast flood levels for each of the Great Lakes 
were derived. These relationships were provided 
to other agencies, State, and local interests for use 
in delineating flood prone areas, and enacting 
zoning ordinances to encourage prudent use of 
the coastal zone. As expected differences were 
noted between the derived 100 year level and 100 
year water levels previously used. Accordingly, a 
determination will have to be made concerning 
the level to be adopted where a conflict exists. 
f. Local Support. Advise and information 
pertaining to the Great Lakes shoreline were 
provided and exchanged with the Michigan 
D.N.R. and the Ohio D.N.R. Meetings were held 
at Rossford, Lucas Co., Ottawa Co., Sandusky Co, 
Erie Co. in Ohio and at St. Joseph, Michigan to 
provide information and explain how shore 
damage might be minimized and coastal zone 
management improved. 
g. Littoral Environment Observation 
Program (LEO). The LEO Program is a 
cooperative effort between the District, CERC 
and the Michigan DNR, and was started in 1971. 
The program is to provide a reservoir of data on 
some of the natural forces which effect the 
31-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Michigan shoreline, and the response of the 
shoreline to these forces. Wind, wave, littoral 
current, beach profiles, sand samples and other 
optional observations are obtained periodically. 
These data are collected at 11 observation sites on 
Lake Michigan, 5 on Lake Superior, 6 on Lake 
Huron, 1 on Lake Erie and 1 site on Lake St. Clair. 
The Branch maintains LEO sites, trains 
observers, and monitors data before transmittal 
to CERC for reduction, compilation and analysis. 
Data are made available to all shoreline interests 
having a need for it. 
h. Environmental Studies. Support was 
provided in assessing environmental effects of 
Corps projects on the coastal zone. Navigation, 
beach erosion, and diked disposal projects were 
evaluated with a view to possible adverse effects 
on nearby property. Appropriate design changes 
are made concerning mitigation measures to 
eliminate an adverse impact on the environment. 
Findings are incorporated into environmental 
impact statements. Statements have been 
prepared for harbors and dredged disposal sites 
referred to above. 
GENERAL INVESTIGATIONS 
61. SURVEYS 
Fiscal year costs were $2,355,338 for navigation 
studies, $251,428 for flood control studies and 
$159,229 for comprehensive basin studies. 
Special studies continued during fiscal year on 
Great Lakes water levels, soil conservation coordination 
studies and National Wildlife and Scenic 
Rivers System cost $44,999. 
62. COLLECTION AND STUDY OF 
BASIC DATA 
Flood Plain Management Services The past 
year has seen a change in the direction of FPMS 
effort with the increased emphasis assigned to the 
support of the HUD-FIA Flood Insurance Study 
Program. While the District has adjusted its 
sights to broaden its scope of activity, this additional 
responsibility has not detracted from 
routine functions particularly with respect to the 
preparation of characteristic flood plain management 
reports. Production rates are being maintained 
and schedules met, utilizing A-E Contractors 
to the maximum extent possible. To better 
adapt to this concept of involvement, the 
traditional report format has been both altered 
and abbreviated at the same time maintaining 
high standards of technical sufficiency for which 
the District is well known. To distinguish 
between the traditional Flood Plain Information 
Report and the format now adopted, such reports 
are now referred to as Flood Ifazard Information 
Studies (FHI). At the present time, two such 
reports are in various stages of completion - Ottawa 
River-Ten Mile Creek, Berkey, Ohio and 
Raisin River, Raisinville Township, Monroe 
County Michigan. 
To date, since the inception of the Flood Plain 
Information Report Program, some 24 have been 
completed on the basis of previously established 
guidelines. These have involved an expenditure of 
approximately 1.4 million dollars for some 500 or 
more miles of stream reaches throughout the 
Ohio, Indiana and Michigan basins. This year has 
seen the completion of three studies within the 
Grand River Basin, Michigan and one within the 
Maumee, Indiana. These are the Grand River, 
Tallmadge and Georgetown Townships, Ottawa 
County; Grand and Thornapple River, Ada 
Township; Grand River, Ionia; and the Allen 
County Study, Indiana. At the same time three 
additional studies have been programmed, - one 
in Indiana on the St. Joseph River, and two in 
Michigan - one on the Huron River and the other 
on the Thornapple River. 
The Detroit District has evidenced its concerned 
interest in the FIA-HUD Flood Insurance 
Study Program by having embarked on a rather 
prodigious undertaking, involving a total commitment 
of approximately $800,000 of HUD 
money. This is outstanding when compared to the 
slightly larger costs associated with FPI report 
out-put to date and the relatively shorter period of 
involvement. A partial distribution of these 
monies have been made by HUD-FIA. A major 
portion has been obligated primarily through AE 
contractual effort. Six such contracts are in 
various stages of progress. These are for the Lake 
Shore community of Algonac, and the Townships 
of Clay, Harrison, and Ira; the City of Farmington, 
Oakland County; and the Ottawa River- 
Ten Mile Creek, Sylvania Ohio. The District will 
undertake negotiation for three additional 
studies. We anticipate that the reaminder will be 
initiated early next fiscal year, with several being 
done in-house. 
Not withstanding the increased work load, the 
District continues to maintain its eminence in the 
field of non-structural alternatives of Flood Plain 
Management by providing advice and guidance 
to all seeking such assistance. During the past 
year, approximately 175 requests were 
answered. The bulk of these originated with 
Federal agencies in response to the requirements 
of E.O. 11296. This total is somewhat less than 
that of previous years. The trend towards a 
lessening of requests from the civil sector both by 
way of local government and industry is not to be 
construed as a lessening of Corps activity. On the 
31-34

DETROIT, MICH., DISTRICT 
contrary it signifies an assumption of responsibility 
on the part of state agencies, which have 
been given such a mandate through enlightened 
state enabling legislation particularly in the case 
of Michigan and Indiana. 
The statistics and facts alluded to above do not 
reflect the nature of the anacillary activities required 
to assure the successful fruition of all 
studies and investigations. HUD-FIA studies required 
not less than three FIA-COE coordination 
and possibly four meetings to assure that communities 
were properly educated as to the importance 
of the programs and the necessity for assuring 
the utmost of their cooperation in completing 
an acceptable product. Considerable time is 
devoted to follow-up activity to promote support 
of communities in the implementation of the 
various studies so as to assure that time and 
money has been well spent. Advice and assistance 
is provided with respect to the preparation of 
flood plain ordinance and regulations for incorporation 
in land use management planning 
programs. It is our forecast that future demands 
for such services will require continuing support 
of the same or greater magnitude. 
International Water Studies. Fiscal year cost 
was $41,999 for collection and study of basic data 
in connection with international studies. 
31-35

DETROIT, MICH., DISTRICT 
TABLE 31-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Alpena Harbor, 
Mich. 
2. Arcadia Harbor, 
Mich. 
3. Au Sable Harbor, 
Mich. 
4. Bayport Harbor, 
Mich. 
5. Black River 
(Port Huron), 
Mich. 
6. Bolles Harbor, 
Mich. 
7. Caseville 
Harbor, Mich. 
8. Charlevoix Harbor, 
Mich. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
236 4,653 
236 4,653 
424 19,600 
424 19,599 
23,500 
84,400 
8844,,440000 
52,600 
24,450 
136,900 
87,711 
49,000 
100,613 
5,423 
5,423 
135,000 250,300 
181,674 153,062 
2,577 
2,577 
1,563 
437 
248,300 
1,344 
369 
369 
2,577 
2,577 
147,200 
3,214 
22,136 
1,643 
1,643 
1,603 
1,603 
1,579 
1,579 
38,474 
504 
504 
3,000 
3,000 
731 
731 
355 
355 
370,550 
1,129 
1,129 
11,019 
11,019 
2,388 
2,388 
160,000 -228,800 72,350 
52,257 13,523 80,176 
1,440 
1,440 
1,895 
1,895 
91 2,115 
91 2,115 
12,400 
12,400 
337,3941 
337,3941 
304,046 
304,046 
20,024 
20,023 
193,885 
193,848 
209,7762 
209,7762 
1,706,226 
1,606,202 
93,597 
93,597 
12,231 
12,231 
792 
792 
576,9073 
576,9063 
425,013 
425,013 
426,4164 
426,4164 
17,340 
17,340 
150,750 
150,750 
587,3146 
587,3146 
51,192 
51,192 
2,206 
2,206 
94,623 
94,623 
31-36

DETROIT, MICH., DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
Maint. 
Approp. 388,800 
Cost 118,391 
Rehab. 
Approp. -25,000 
Cost 3,253 
Diked 
Disposal 
Approp. 9,800 
Cost 6 
9. Clinton River New Work 
Mich. Approp. - 
Cost - 
Maint. 
Approp. - 
Cost 7,431 
Diked 
Disposal 
Approp. - 
Cost - 
10. Detroit River, New Work 
Mich. Approp. - 
Cost 120 
Maint. 
Approp. 530,100 
Cost 522,765 
Diked 
Disposal 
Approp. 9,200,000 
Cost 267,951 
11. Frankfort Harbor, New Work 
Mich. Approp. - 
Cost - 
Maint. 
Approp. 63,200 
Cost 104,610 
Rehab. 
Approp. 
Cost - 
Diked 
Disposal 
Approp. 294,300 
Cost 798 
12. Grand Haven New Work 
Harbor, Mich. Approp. - 
Cost - 
Maint. 
Approp. 477,300 
Cost 920,189 
Rehab. 
Approp. - 
Cost - 
Diked 
Disposal 
Approp. 298,800 
Cost 9,161 
13. Grand Marais New Work 
Harbor, Mich. Approp. - 
Cost - 
Maint. 
Approp. 1,896 
Cost 1,896 
346,400 1,661,194 
395,842 1,660,593 
- 1,129,396 
- 1,129,396 
604 
-9,794 
170,500 
125,756 
676,200 
669,936 
-7,485,406 
212,121 
25,400 
29,290 
-291,500 
264,300 
505,462 
34,863 
105,000 
105,000 
-16,300 
28,444 
859 
859 
100 15,000 
100 14,998 
- - 
499,500 1,254,000 
503,200 1,263,915 
-803,100 142,500 
431,295 142,596 
- - 
52,000 91,900 
50,500 83,400 
- - 
- - 
-1,900 13,800 
102 13,799 
338,000 475,000 
368,222 488,759 
- - 
- - 
293,000 145,600 
41,196 623,180 
61,497 
5,577 
15,000 
70,366 
31-37 
6
6 
549,7986 
549,7986 
715,171 
715,171 
15,100 
15,098 
76,601,3607 
76,597,1397 
10,538,546 
10,537,596 
1,053,994 
1,053,963 
1,955,1598 
1,955,1598 
1,812,397 
1,802,397 
274,776 
274,776 
14,700 
14,699 
1,283,4699 
1,283,4699 
9,200,29310 
9,198,96510 
813,613 
813,613 
708,400 
708,400 
990,268 
990,268 
1,130,305 
1,129,751

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
14. Hammond Bay 
Harbor, Mich. 
15. Harbor Beach 
Harbor of Refuge, 
Mich. 
16. Holland Harbor 
Mich. 
17. Inland Route, 
Mich. 
18. Lake St. Clair, 
Mich., Channels 
19. Leland Harbor, 
Mich. 
20. Les Cheneaux, 
Islands Channels, 
Mich. 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp . 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
25,000 
115,196 
1,084 
1,084 
235,700 
667,918 
29,400 
1,041 
759,300 
164,193 
294,300 
6,761 
-8,700 
12 
111,300 
89,692 
55,500 
50,492 
25,000 
6,722 
2,046 
2,046 
-50,000 
-41,820 
-996 
-26,300 
258,600 
659,301 
-255,500 
2,014 
2,009 
2,009 
1,069 
1,069 
-800 
1,259 
22,179 
22,179 
2,578 
,578 
46,000 
45,999 
155,000 177,000 
356,984 178,008 
- - 
18,500 163,000 
48,525 160,282 
-6 
71,600 
93,667 
65,800 
65,962 
73,000 96,800 
70,764 99,027 
- - 
- - 
51,500 55,000 
52,347 59,582 
7,808,700 -6,004,800 1,835,000 -373,600 
209,616 171,303 385,381 2,051,711 
42,500 
41,701 
36,200 
36,999 
41,000 34,000 
30,708 44,292 
5,588 
5,588 
741,899 
701,297 
1,018,10211 
1,015,36711 
29,592 
29,592 
1,200,598 
1,200,598 
2,586,205 
2,586,205 
194,504 
194,504 
48,300 
48,299 
771,84112,13 
771,84112,13 
3,876,13212 
3,975,47012 
502,452 
502,452 
220,300 
217,582 
918,222' 4 
918,22214 
687,489 
687,481 
7,675,23715 
7,675,23715 
2,630.08416 
2,630,04616 
3,265,300 
2,819,017 
1,027,089
'7 
1,027,08917 
328,175 
328,175 
70,678 
70,678 
435,283 
399,478 
5,588 
5,588 
31-38

DETROIT, MICH., DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
21. Lexington Harbor, 
Mich. 
22. Little Lake 
Harbor, Mich. 
23. Ludington Harbor, 
Mich. 
24. Manistee Harbor, 
Mich. 
25. Monroe Harbor, 
Mich. 
26. Muskegon Harbor, 
Mich. 
27. Ottawa River 
Mich. And Ohio 
28. Pentwater Harbor, 
Mich. 
29. Portage Lake 
Harbor, Mich. 
30. Port Austin 
Harbor, Mich. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp . 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp . 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
15,000 
16,473 
70,800 
102,514 
39,700 
6,295 
90,700 
82,021 
76,000 
99,953 
155,600 
117,026 
97,800 
107,976 
84,900 
109,098 
16,000 
21,743 
1,069 
1,069 
30,000 
13,797 
84,600 
86,127 
15,000 
36,494 
64,500 
81,891 
85,900 
87,357 
166,700 
205,051 
110,300 
148,339 
122,700 
122,711 
97,800 
83,991 
981 
981 
12,165 360,000 
34,901 91,933 
79,000 12,000 
78,803 12,197 
- 51,992 
- 51,992 
102,600 184,000 
98,601 188,051 
106,000 84,000 
105,684 84,432 
169,000 296,000 
169,024 296,200 
19,800 43,000 
19,800 42,999 
114,700 354,000 
104,700 363,962 
- 10,000 
- 10,000 
70,500 
69,378 
14,988 
1,176 
1,176 
1,000 
2,354 
9,000 
9,187 
1,022 
1,022 
31-39 
472,165 
204,098 
600,47018 
600,47018 
626,598 
626,598 
1,634,19419 
1,622,28319 
5,304,80020 
5,304,61920 
357,913 
357,913 
2,696,52221 
2,696,52221 
2,444,63322 
2,444,73122 
1,374,164 
1,374,164 
987,34023 
987,34023 
3,672,270 
3,672,270 
62,800 
62,799 
2,912,1102 
2,912,1104 
2,671,115 0 
2,671,0812 
742,832 
742,832 
10,000 
10,000 
179,899 
179,899 
1,783,952 
1,783,951 
256,129 
256,129 
970,445 
970,443 
1,128,334@ 
1,128,334w 
41,486 
41,486

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
i 
Total Cost to 
n Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
Diked 
Disposal 
Approp. - 
Cost - 
31. Port Clinton New Work 
Harbor, Ohio Approp. - 
Cost - 
Maint. 
Approp. - 
Cost 2,703 
Diked 
Disposal 
Approp. - 
Cost - 
32. Port Sanilac New Work 
Harbor, Mich. Approp. 148,900 
Cost 14,260 
Maint. 
Approp. 36,300 
Cost 21,955 
Diked 
Disposal 
Approp. 29,400 
Cost 908 
33. Rouge River New Work 
Mich. Approp. - 
Cost 
Maint. 
Approp. 568,300 
Cost 436,947 
Diked 
Disposal 
Approp. 1,030,200 
Cost 45,735 
34. Saginaw River, New Work 
Mich. Approp. 25,000 
(Federal Funds) Cost 2,385 
New Work 
Approp. 
(Contributed Funds) Cost 
Maint. 
Approp. 384,500 
Cost 402,689 
Diked 
Disposal 
Approp. 981,200 
Cost 32,002 
35. St. Clair River, New Work 
Mich. Approp. 
Cost 2,573 
Maint. 
Approp. 396,400 
Cost 385,524 
36. St. Joseph New Work 
Harbor, Mich. Approp. 
Cost 
Maint. 
Approp. 98,800 
Cost 121,626 
Rehab. 
Approp. -25,000 
Cost 235,128 
Diked 
Disposal 
Approp. 333,600 
Cost 1,043 
50,523 
5,185 
13,674 
10,900 
23,995 
-26,400 
367,800 
418,555 
300,000 
33,101 
-6,000 
350,900 
345,968 
-250,000 
46,423 
112,201 
118,495 
103,200 
107,196 
-24,396 
892 
5,371 
88,000 
133,338 
200,000 
7,570 
167,900 
36,852 
-1,710 
382 
473,000 
556,750 
-1,227,177 
29,010 
410,800 
418,585 
-611,500 
41,275 
229,600 
224,875 
82,000 
81,547 
-326,324 
862 
31-40 
TABLE 31-A 
See 
Section 
12,000 
11,999 
827 
827 
6,165 
6,165 
331,432 
25,000 
89,999 
2,868 
2,868 
251,600 
250,988 
61,500 
61,626 
560,300 
558,895 
296,000 
289,484 
400,500 
409,103 
132,200 
136,180 
24,000 
23,999 
12,000 
11,999 
71,950 
71,950 
376,192 
376,192 
6,165 
6,165 
1,236,065" 
1,236,065 
333,152 
270,011 
4,158 
4,158 
675,251n 
675,251n 
8,127,988w 
8,127,376w 
169,523 
169,472 
14,917,12730 
14,917,12730 
13,600 
13,600 
6,682,680 
6,677,217 
415,700 
409,184 
19,213,24631 
19,213,24631 
5,589,684 
5,189,485 
976,48532 
976,48532 
3,571,649 
3,571,646 
1,051,756 
962,216 
31,276 
31,275

DETROIT, MICH., DISTRICT 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
37. St. Joseph River, New Work 
Mich. Approp. 
(Bank Protection) Cost 
(Federal Funds) New Work 
Contributed Funds) Approp. 
Cost 
Maint. 
Approp. 
Cost 
38. St. Marys River, New Work 
Mich. Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
39. Saugatuck Harbor, New Work 
Mich. and Approp. 
Kalamazoo River, Cost 
Mich. Maint. 
Approp. 
Cost 
40. Sebewaing River, New Work 
Mich. Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
41. South Haven New Work 
Harbor, Mich. Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
42. Tawas Bay New Work 
Harbor, Mich. Approp. 
Cost 
Maint. 
Approp. 
Cost 
43. Toledo Harbor, New Work 
Ohio Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
44. Whitefish Point New Work 
Harbor, Mich. Approp. 
Cost 
Maint. 
Approp. 
Cost 
50,000 
50,000 
261,561 
261,561 
600,400 4,250,000 
486,258 3,459,239 
4,468,600 4,045,300 
3,846,771 4,243,034 
196,200 -180,500 
12,683 360 
64,500 88,300 
97,213 90,908 
1,986,220 
1,544,325 
4,028,200 
4,409,808 
83,409 
83,409 
90,000 
2,263,141 
4,897,800 
5,018,638 
-2,600 
57 
103,000 
103,025 
-3,000 
-3,000 
23,966 10,000 
23,966 6,729 
114,300 
114,567 
25,000 
219,625 
92,500 
110,928 
11,554 
54,555 
54,555 
344,970 
344,970 
19,185 
19,185 
159,246,214n 
156,459,355" 
87,092,298 
86,501,035 
13,100 
13,043 
364,527" 
364,5274 
1,957,810M 
1,957,810" 
35,573 
35,573 
300,617 
297,346 
446 12,000 12,446 
446 11,999 12,445 
- - 452,426M 
- - 452,426" 
185,000 98,000 2,654,9753 
184,192 98,808 2,654,92537 
- - 1,644,770 
-- 1,632,076 
381 
381 
64,368 
64,368 
11,000 11,381 
10,999 11,380 
112,997 177,365 
112,997 177,365 
1,422,100 1,028,316 983,076 1,490,200 
1,021,598 952,302 1,535,337 1,575,826 
1,465,000 
30,639 
-696,900 9,233,400 6,026,622 
126,253 154,315 15,620.975 
17,191,8423 
17,191,842" 
20,215,110 
20,214,413 
16,028,122 
15.932.182 
771,639 
771,639 
-3,200 
5,033 
484 
1,726 
55,000 
55,000 
2,000 117,454 
1,729 117,183 
31-41

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
45. White Lake 
Harbor, Mich. 
50. Kalamazoo River, 
Battle Creek, Mich. 
(Federal Funds) 
(Contributed Funds) 
51. Kalamazoo River, 
Kalamazoo, Mich. 
52. Point Place 
Toledo, Ohio 
53. Red Run, Lower 
Clinton River, 
Mich. 
54. River Rouge, 
Mich. 
55. Saginaw River, 
Mich. 
(Federal Funds) 
(Contributed Funds) 
56. Sebewaing River, 
Mich. 
60. Survey of North 
Central Lakes 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
257 824 
257 824 
Funding 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
54,800 44,084 189,500 
55,324 44,084 189,464 
100 
- 35,219 100 
- - 89 
- - 89 
-40,000 -50,000 10,000 
14,786 31,539 10,000 
82,999 
- - 82,999 
- - 34,999 
- - 34,999 
5,250,000 4,119,632 605,000 
4,541,438 3,766,065 3,923,949 
810,100 1,200,000 
212,694 1,378,083 
1,900 
3,190 
390,500 
468,024 
1,375,000 
1,264,116 
56,000 
172 
600 4,000 
959 4,000 
414,300 
458,893 
459,000 
446,267 
380,000 
1,213,788 
36,000 
91,828 
10,000 
10,000 
513,000 
533,053 
1,081 
1,081 
207,862 
207,862 
1,488,780 
1,488,744 
4,363,000 
4,362,900 
125,089 
108,335 
421,466 
421,466 
82,999 
82,999 
34,999 
34,999 
23,066,332 
22,966,783 
10,612,100 
10,611,266 
92,000 
92,000 
365,46239 
365,46239 
281,144 
281,144 
29,015,63140 
29,014,83840 
31-42 
28,000 
41,477 
149,000 
17,320 
3,868,700 
4,419,863

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 31-A (Continued) COST AND FINANCIAL STATEMENT 
1. Includes $18,889 for previous projects. 
2. Includes $114,786 for previous projects, and $16,400 
Contributed Funds for existing project. 
3. Includes $214,133 for new work and $12,008 for 
maintenance for previous project. 
4. Includes $255,000 Contributed Funds. 
5. Includes 293,657 Contributed Funds. 
6. Includes $25,500 for previous projects and $289,752 
Contributed Funds for existing project. 
7. Includes $2,907,254 for previous projects. 
8. Includes $31,709 Contributed Funds. 
9. Includes $311,329 for previous projects. 
10. Includes 13,437 for previous projects. 
11. Includes $89,400 Contributed Funds. 
12. Includes 176,620 for new work $125,598 for 
maintenance. 
13. Includes $35,705 Contributed Funds. 
14. Includes $148,000 Contributed Funds for existing 
project. 
15. Includes 656,000 for previous projects. 
16. Includes 235,346 for previous projects. 
17. Includes 354,139 Contributed Funds. 
18. Includes 57,670 Contributed Funds. 
19. Includes $491,416 for previous projects. 
20. Includes $126,451 for previous projects. 
21. Includes $354,999 for previous projects. 
22. Includes $150,910 for previous projects. 
23. Includes Contributed Funds of $300 000 for new work 
and $166,667 for maintenance. Contributed by: Port 
Commission of Monroe, $300,000; Consolidated Paper Co., 
$125,000; and River Raisin Paper Co., $41,667. 
24. Includes 613,408 for previous projects. 
25. Includes 446,183 for previous projects. 
26. Includes 172,100 Contributed Funds for 
New Work 
27. includes $303,159 Contributed Cost. 
28. Includes $50,083 for previous projects. 
29. Includes $56,608 for previous projects. 
30. Includes $962,556 for previous projects. 
31. Includes 1,671,660 Public Works Funds and $49,419 
Emergency Relief Funds. 
32. Includes 503,113 for previous projects. 
33. Includes 2,904,807 for previous projects. 
34. Includes 90,232 for previous project. 
35. Includes 117,554 for previous projects. 
36. Includes 187,233 for previous projects. 
37. Includes 131,239 for previous projects. 
38. Includes 1,624,695 for previous projects. 
39. Includes 15,000 for previous project. 
40. Includes 3,973,897 for previous projects. 
31-43

DETROIT, MICH., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 19, 1890 
Mar. 2, 1919 
Sept. 2, 1919 
Aug. 30, 1935 
Oct. 27, 1965 
March 3, 1905 
Mar. 2, 1945 
May 20, 1965 
Sept. 19, 1890 
July 13, 1892 
Sept. 22, 1922 
July 3, 1930 
Aug. 30, 1935 
April 23, 1970 
July 6, 1965 
Oct. 23, 1962 
Aug. 14, 1876 
Aug. 2, 1882 
June 13, 1902 
June 20, 1938 
Aug. 5, 1886 
July 19, 1963 
June 13, 1902 
Mar. 3, 1905 
June 25, 1910 
Mar. 4, 1913 
Mar. 2, 1907 
ALPENA HARBOR, MICHIGAN (See Section 1 of Text) 
Channel Depth of 16% Feet Annual Report, p. 2288, 
Rubblemound Breakwater for Protecting Channel H. Doc. 830, 65th Cong., 2d 
on South Side, and Widening Entrance Channel Sess., and Rivers Committee 
Doc. 1, 67th Cong., 1st Sess. 
21 and 18% Foot Channel Depths and Turning Basin Rivers and Harbors Comm. 
Doc. 42, 72d Cong., 1st Sess. 
Present Project Dimensions, New Turning Basin, H. Doc. 151, 88th Cong., 1st Sess.' 
Removal of Old Breakwater, and Construction 
of New Breakwater. 
ARCADIA HARBOR, MICHIGAN (See Section 2 of Text) 
Maintenance of Existing 12-Foot Channel. H. Doc. 194, 58th Cong., 2d 
Sess. 
AU SABLE HARBOR AT AU SABLE RIVER (OSCODA), MICH. 
(See Section 3 of Text) 
Dredging Channels 12 and 10 Feet Deep and H. Doc. 446, 78th Cong., 2d Sess.' 
Riprapping North Pier. 
BAY PORT HARBOR, MICHIGAN (See Section 4 of Text) 
Channel 6 Feet Deep and 50 Feet Wide. Section 107, 1960 River and Harbor 
Act. 
BLACK RIVER (PORT HURON), MICH. (See Section 5 of Text) 
Channel from Mouth of Grand Trunk R.R. Bridge. Annual Report 1889, p. 2291. 
Channel from Grand Trunk R.R. Bridge to No Printed Report 
Washington Ave. 
Consolidation of Projects for Black River at Port H. Doc. 436, 64th Cong., 1st Sess. 
Huron and Mouth of Black River. 
Settling Basin. H. Doc. 162, 71st Cong., 2d Sess. 
Deepening Channel and Settling Basin to 20 Feet, Rivers and Harbors Committee 
and Widening to 100 Feet 2 Bends; 1 at the Foot Doc. 54, 72d Cong., 2d Sess.' 
of 12th St., the Other Below the Grand Trunk R.R. 
Bridge. 
Extension of Existing Channel. Section 107, 1960 River and Harbor 
Act. 
BOLLES HARBOR, MICH. (See Section 6 of Text) 
Entrance Channel in Lake Erie, Access Channel in 
LaPlaisance Creek, Steel Sheet Pile Revetment. 
CASEVILLE HARBOR, MICH. (See Section 7 of Text) 
Channel 10 to 8 Feet Deep Protected by Breakwater. 
CHARLEVOIX HARBOR, MICH. (See Section 8 of Text) 
Channel from Lake Michigan to Round Lake Protected 
Where Needed by Piers and Revetments. 
Channel from Round Lake to Lake Charlevoix. 
Project Depth Increased to 15 Feet. 
Project Depth Increased to 18 Feet. 
CLINTON RIVER, MICH. (See Section 9 of Text) 
Channel in River and Lake St. Clair, Pile Dike, 
Closing Channels and Making Cutoff, and 
Revetments as Needed. 
.Widening Entrance Channel and Constructing 
Protected Harbor Basin. 
DETROIT RIVER, MICH. (See Section 10 of Text) 
Amherstburg Channel and Removal of Grosse Ile 
Shoal. 
Fighting Island Channel. 
Section 107, 1960 River and 
Harbor Act. 
H. Doc. 64th Cong., 1st Sess.' 
S. Ex. Doc. 16, 44th Cong., 
1st Sess., and Annual 
Report 1876, p. 523. 
No Prior Survey or Estimates. 
No Prior Survey Estimatel 
S. Doc. 163, 75th Cong., 3rd Sess.' 
S. Doc. 199, 46th Cong., 2d Sess. 
Annual Report 1880, p. 2062 and 
H. Doc. 210, 44th Cong., 2d Sess. 
and Annual Report 1886, p. 219 
Section 107, 1960 River and Harbor 
Act. 
H. Does. 712, 56th Cong., 1st Sess 
and 40, 58th Cong., 3rd Sess. 
H. Doc. 17, 62d Cong., 1st Sess. 
H. Does. 266. 59th Cong., 2nd Sess. 
31-44 
TABLE 31-B

TABLE 31-B (Continued) 
DETROIT, MICH., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 25, 1910 
Mar. 2, 1910 
July 3, 1930 
Aug. 30, 19352 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
May 17, 1950 
Mar. 21, 1956 
July 14, 1960 
Aug. 13, 1968 
June 23, 18663 
Mar. 3, 1925 
Aug. 26, 1937 
Oct. 27, 1965 
June 23, 1866 
June 14, 1880 
Sept. 19, 1890 
July 13, 1892 
Livingstone Channel 
Channel Depths of 26 and 25 Feet. 
Channel to Wyandotte 21 Feet Deep and 300 
Feet Wide Through Middle Ground Opposite 
Head of Fighting Island. 
Trenton Channel and Turning Basin (West of 
Grosse Ile). 
American Channel North of Belle Isle Between 
Windmill Point and Fairway Slip, Detroit. 
Deepen Westerly 300 Feet of Amherstburg Channel 
and Ballards Reef Channel Below Livingstone 
Channel to 27 Feet to Provide Depths Adequate 
for 24-Foot Draft Navigation When Governing 
Lakes are at Datum, with Necessary Widening 
at Approaches and Bends and Construction of 
Necessary Compensating Works, Detroit River. 
Extend Turning Basin in Trenton Channel 600 Feet, 
Dredge Through East Draw of Lower Grosse Ile 
Bridge, and Extend 300-Foot Width of Channel 
North of Lower Grosse Ile Bridge. 
Channel Depth of 28.5 Feet Throughout 
Downbound and Two-Way Channels, Except 
in Upper (27.7-Foot Depth) and Lower, 
(29-Foot Depth) Livingstone Channel, and 
in Upbound Channel; 27-Foot Depth in 
Ballards Reef Channel Below Junction with 
Livingstone Channel, 27.5-Foot Depth in 
Westerly 300-Foot Width of Limekiln 
Crossing and Amherstburg Reaches, and 28.5- 
Foot Depth in Westerly 300-Foot Width of 
Hackett Beach, with Necessary Compensation 
Works. Also 28.5-Foot Depth in Lake Erie 
from Detroit River to Pelee Passage Shoal, 
Inclusive. 
Trenton Channel; Deepen to 27 Feet, Where 
Necessary, Wyandotte Reach from Detroit 
River to Upper Grosse Ile Bridge, About 
5.5 Miles, Deepen to 28 Feet and Widen to 
300 Feet Below Upper Grosse Ile Bridge to 
and Including a Turning Basin 28 Feet 
Deep and 15 Across in Area Outside 
Project Limits. 
Trenton Channel; Deepen to 28 Feet and 
Widen to 300 Feet from the Upper Turning 
Basin at Trenton to Gibraltar, about 
20,500 Feet Downstream; Construct a Turning 
Basin at Gibraltar at a Depth of 28 Feet, 
Width of 830 Feet, and Length of 1,500 
Feet; Build Compensating Works to Maintain 
Water Levels. 
FRANKFORT HARBOR, MICH. (See Section 11 of Text) 
A New Outlet 12 Feet Deep Protected by 
Piers and Revetments. 
Exterior Breakwaters, Removal of Portions 
of Piers, Project Dimensions of Outer 
Basin. 
Dredge the Area in Lake Betsie. 
Deepen Approach and Entrance Channels, 
Extend Inner Basin, and Dredge 
Recreational Anchorage Area. 
GRAND HAVEN HARBOR, MICH. (See Section 12 of Text) 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
676, 61st Cong., 2d Sess., and 
32, 65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivs and Harbors Committee 
Doc. 1, 72d Cong., 1st Sess.' 
H. Doc. 205, 75th Cong., 1st Sess. 
H. Doc. 734, 79th Cong., 2d Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 30, 81st Cong., 1st Sess.i 
S. Doc. 71, 84th Cong., 1st Sess.' 
H. Doc. 319, 86th Cong., 2d Sess.i 
H. Doc. 338, 90th Cong., 2d Sess.i 
H. Doc. 482, 55th Cong., 2nd Sess. 
H. Doc. 208, 68th Cong., 1st Sess. 
H. Doc. 511, 74th Cong., 2d Sess. 
S. Doc. 16, 89th Cong., 1st Sess.i 
S. Ex. Doc. 42, 35th Cong., 1st 
Sess. 
S. Ex. Doc. 42, 35th Cong., 1st 
Sess. 
S. Ex. Doc. 42, 35th Cong., 1st 
Sess. 
S. Ex. Doc. 42, 35th Cong., 1st 
Sess. 
31-45

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
Aug. 26, 1937 
Mar. 2, 1945 
June 14, 1850 
June 14, 1850 
May 17, 1930 
Mar. 2, 1945 
Mar. 3, 1871 
Aug. 8, 1917 
Jan. 21, 1927 
Aug. 30, 1852 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 3, 1905 
July 3, 1930 
Aug. 30, 1935 
Sept. 3, 1954 
Sept 3, 1954 
Sept. 2, 1964 
Aug. 5, 1886 
July 13, 1892 
June 13, 1902 
Mar. 2, 1919 
July 3, 1930 
Aug. 30, 19332 
Mar. 21, 1956 
Aug. 30, 1935 
Oct. 23, 1962 
Present Project Dimensions of Harbor S. Doc. 88, 71st Cong. 2d Sess. 
Channel to Grand Trunk Car Ferry Slip 
and River Channel, Eliminating all of 
that portion of Grand River Above Bass 
River, Consolidation of Projects for 
Harbor and River. 
Channel to Spring Lake River and Harbors Committee 
Doc. 1, 75th Cong., 3d Sess.1 
Present Project Dimensions of Harbor H. Doc. 661, 76th Cong., 3d Sess.1 
Channel from Car Ferry Slip to Grand 
Trunk Railway Bridge and Turning Basin. 
GRAND MARAIS HARBOR, MICH. (See Section 13 of Text) 
Existing Project, Except for Pile Dike. Specified in Act, Annual Report 
1881, p. 2050. 
For Pile Dike. Annual Report 1895, p. 351. 
800-Foot Extension of West Pier. H. Doc. 751, 80th Cong., 2d Sess. 
HAMMOND BAY HARBOR, MICH. (See Section 14 of Text) 
Harbor of Refuge, breakwaters H. Doc. 446,78th Cong., 
10-foot depth in harbor basin 2d Sess. 
12-foot depth in entrance channel 
HARBOR OF REFUGE AT HARBOR BEACH, 
LAKE HURON, MICH. (See Section 15 of Text) 
Adopted Site and made provision for harbor. Annual Report 1873 p. 292. 
Closing North Entrance and Dredging H. Doc. 1700, 64th Cong., 2d Sess. 
Main Entrance and Anchorage Area. 
Removal of Portion of Breakwater in 
interest of sanitation. 
HOLLAND HARBOR, MICH. (See Section 16 of Text) 
Artificial Channel Between Lakes S. Ex. Doc. 42, 35th Cong., 1st 
Macatawa and Michigan.4 Sess., Annual Report. 
Piers and Revetments.4 Annual Report 1866, p. 106. 
Extending Inner Piers. H. Doc. 272, 51st Cong., 2d Sess., 
and Annual Report 1887, p. 2950. 
Coverging Breakwater. Annual Report 1905, p. 2176. 
Channel to Holland and Turning Basin H. Doc 588, 69th Cong., 2d Sess. 
at Holland. 
Present Project Dimensions of Channels Rivers and Harbors Committee, 
and Turning Basin. Doc. 48, 74th Cong., 1st Sess. 
Widen Bend in Reveted Entrance Channel H. Doc. 282, 83rd Cong., 2d Sees. 
into Lake Macatawa, Dredge Channel in 
Black River, and Widen and Extend 
Turning Basin. 
THE INLAND ROUTE, MICH. (See Section 17 of Text) 
Channel 30 Feet Wide and 5 Feet Deep H. Doc. 142, 82d Cong., 1st Sess. 
Through Lakes and Rivers with Suitable 
Jetties. 
Lock and Dam. Chief of Engineers. 
LAKE ST. CLAIR, MICH., CHANNELS (See Section 18 of Text) 
Two Dikes. Annual Report 1885, p. 2150. 
Deepening Canal and Dredging Channel H. Doc. 297, 51st Cong., 2d Sess. 
at Grosse Point. 
Second Canal for Downbound Vessels. H. Doc. 234, 56th Cong., 2d Sess. 
21-Foot Depth in Grosse Pointe Channel H. Doc. 188, 65th Cong., 1st Sess. 
for About 5.25 Miles. 
25-Foot Depth Through Canals and Channel H. Doc. 253, 70th Cong., 1st Sess. 
Through Lake St. Clair. 
Removal of Center Dike and Widening Rivers and Harbors Committee 
Channel to 700 Feet. Doc. 3, 72d Cong., 1st Seas. 
Deepening Channel to 27.5 Feet and S. Doc. 71, 84th Cong., 1st Sess.' 
Abandonment of Channel Above Mouth of 
Southeast Bend Cutoff Channel. 
LELAND HARBOR, MICH. (See Section 19 of Text) 
Entrance Channel Protected by Piers. Rivers and Harbors Committee 
Doe. 23, 74th Cong., Outer 1st Sess. Breakwater, Anchorage Area. H. Doc, 413, 87th Cong., 2d Sess. 
Approach Channel and Removal of North Pier. 
31-46

TABLE 31-B (Continued) 
DETROIT, MICH., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
LES CHENEAUX ISLANDS CHANNELS, MICH. 
(See Section 20 of Text) 
Mar. 15,1967 Removing shoals and bend 
widening over small boat 
course to provide 7-foot depth 
over 100-foot minimum width. 
LEXINGTON HARBOR, MICH. (See Section 21 of Text) 
Oct. 27, 1965 Approach Channel and Maneuver Area 
Protected by Breakwaters.' 
LITTLE LAKE HARBOR, MICH. (See Section 22 of Text) 
Mar. 2, 1945 12-Foot Deep Channel From Lake Superior into 
Little Lake Breakwaters and Revetments. 
LUDINGTON HARBOR, MICH. (See Section 23 of Text) 
Mar. 2, 1867 Entrance Piers. 
Mar. 3, 1 899 Pier Extension Reconstruction and Repairs 
to Existing Structures. and Present 
Project Dimensions of Channel. 
Mar. 2, 1907 Breakwaters, Shore Connections, and 
Removal of Outer Ends of the Two Inner 
piers. 
Dec. 31, 1970 Deepen Channels and Widen Opening 
Between Breakwaters. 
MANISTEE HARBOR, MICH. (See Section 24 of Text) 
Mar. 2 1867 Entrance Piers. 
Sept. 19, 1890 Extending Channel 8,000 Feet to Connect 
with Manistee Lake, and Further Pier 
Extension. 
July 25, 1912 Depth of 20 Feet in Outer Harbor 570 
Feet Wide to Outer End of South Pier 
18 Feet Deep in River, South Breakwater 
with Shore Connection, and Extend North 
Pier if Required. 
July 3, 1920 23-Foot Depths in Entrance Channel and 
21-Foot Depths in River Channel. 
Mar. 2, 1945 Remove Old South Revetment, Construct New 
South Pier and Revetment, and Widen River 
Entrance Channel. 
July 14, 1960 Present Project Dimensions of Channel Through 
Outer Basin and River, and Federal 
Participation in Cost of Replacing Maple 
Street Bridge. 
MONROE HARBOR, MICH. (See Section 25 of Text) 
Feb. 24, 18356 9-Foot Channel, Protecting Revetments 
and Piers. 
July 3, 1930 21-Foot Channel, Dikes and Turning Basin.7 
July 14, 19328 Modified Conditions of Local Cooperation 
Imposed by Act of July 3, 1930. 
June 13, 1902 
Mar. 3, 1925 
Aug. 30, 1935 
Oct. 23, 1962 
Dec. 17,1970 
Mar. 2, 1867 
MUSKEGON HARBOR, MICH. (See Section 26 of Text) 
Piers and Revetments. 
Breakwaters. 
Repairing Revetments Around Car Ferry Slip. 
Channel Deepening and Present Project 
Dimensions of Channel. 
Piers and Revetments. 
OTTAWA RIVER HARBOR, MICH. AND OHIO 
(See Section 27 of Text) 
6-foot deep, 16,500 foot long channel 
in Ottawa River and 8-foot deep, 
15,000-foot channel in Maumee Bay. 
PENTWATER HARBOR, MICH. (See Section 28 of Text) 
Piers and Revetments, Dredging. 
Section 107,1960 River and 
Harbor Act. 
H. Doc. 301, 88th Cong., 2d Sess.' 
H. Doc. 446, 78th Cong., 2d Sess.' 
Annual Report 1867, p. 114.5 
H. Doc. 273, 54th Cong., 2d Sess., 
and Annual Report 1897, p. 2951.5 
H. Doc. 62, 59th Cong., 1st Sess., 
and Rivers and Harbors 
Committee Dec. 3, 59th Cong., 
2d Sess.5 
H. Doc. 342, 91st Cong., 2d Sess.' 
Annual Report 1867, p. 115. 
Annual Report 1891, p. 2678. 
H. Doc. 599, 62d Cong., 2d Sess. 
S. Doc. 131, 71st Cong., 2d Sess. 
H. Doc. 380, 77th Cong., 1st Sess. 
H. Doc. 358, 86th Cong., 2d Sess. 
Annual Report 1872, p. 237. 
Rivers and Harbors Committee Doc 
22, 71st Cong., 2d Sess. 
Rivers and Harbor Committee Doc. 
12, 72d Cong., 1st Sess., 45, 
75th Cong., 1st Sess.' 
H. Doc. 104, 56th Cong., 2d Sess. 
H. Doc. 494, 67th Cong., 4th Sess. 
Rivers and Harbor Committee Doc. 
64, 75th Cong., 1st Sess. 
H. Doc. 474, 87th Cong., 2d Sess.' 
H. Doc. 396, 91st Cong., 2nd Sess. 
H. Ex. Doc. 70, 39th Cong., 2d 
Sess. 
31-47

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1873 
July 5, 1884 
July 13, 1892 
Mar. 25, 1907 
Mar. 3, 1879 
Mar 2, 1945 
June 10, 1872 
Mar. 2, 1945 
Aug. 8, 1917 
Aug 30,193512,13 
July 3, 1958 
Oct. 23, 1962 
June 25, 1910 
July 3, 1930 
Aug. 26, 1937 
June 20, 1938 
Sept. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
July 13, 1892 
July 8, 1930 
Mar. 2, 1945 
July 24, 1946 
Piers and Revetments, Dredging. 
Piers and Revetments, Dredging. 
Piers and Revetments, Dredging. 
Present Project Depth of Channel. 
PORTAGE LAKE HARBOR, MICH. (See Section 29 of Text) 
Entrance Channel 18 Feet Deep Protected by 
Piers and Revetments. 
PORT AUSTIN (See Section 30 of Text) 
Breakwater, Anchorage Basin, Channel dredging. 
PORT CLINTON HARBOR, OHIO (See Section 31 of Text) 
10-Foot Deep Channel, Jetties. 
PORT SANILAC HARBOR, MICH. (See Section 32 of Text) 
Entrance Channel 12 Feet Deep, Anchorage Basin, 
Breakwater. 
ROUGE RIVER, MICH. (See Section 33 of Text) 
21-Foot Channel via The Shortcut Canal. 
25-Foot Channel at Mouth of Old Channel, 
1,425 Feet Long and Adjacent to Latter, 
and 21-Foot Channel Extending from 
Junction of Old Channel and Shortcut 
Canal into Old Channel to Detroit, Toledo 
& Ironton RR. Bridge. 
Old Channel; 100 Feet Wide from Peerless 
Cement Corp. to Junction with Shortcut 
Canal Widened to 150 Feet at 2 Bends. 
25-Foot Channel Over Modified Limits 
from Detroit River to Jefferson Ave. 
(via Shortcut Canal). 
SAGINAW RIVER, MICH. (See Section 34 of Text) 
Channel 200 Feet Wide, with Depth of 18.5 
Feet in Bay and 16.5 Feet in River. 
Project Depth of 18.5 Feet Extended Up River 
to Saginaw. 
Turning Basin. 
Present Project Channel Dimensions 
from Bay to Sixth Street Bridge in 
Saginaw. 
New Channel in Bay, 350 Feet Wide and 
24 Feet Deep from 24-Foot Contour to 
River Mouth, Project Depth of 24 Feet 
in River Channel Up to Detroit & Mackinac 
Railway Bridge, Project Depth of 22 Feet 
in River Channel Up to Sixth Street Bridge, 
Turning Basins at Essexville and Carrollton, 
and Elimination of Present Channel in Bay. 
Deepen Bay Channel, Deepen River Channel to 
Detroit & Mackinac Bridge, Extend 22-Foot 
Project Above 6th St. Bridge, Deepen 
Essexville Turning Basin, and Construct 
2 New Turning Basins.'4 
Deepen River Channel to 25 Feet, from Detroit & 
Mackinac Bridge to New York Central Railroad 
Bridge. 
ST. CLAIR RIVER, MICH. (See Section 35 of Text) 
20-Foot Channel in the River. 
Deepen Channel to 25 and 26 Feet, and 
Compensating Works. 
Widening Channel at Southeast Bend 
to 700 Feet. 
Widen and Deepen Southeast Bend and 
Improve Outlet of North Channel, 
St. Clair River. 
31-48 
H. Ex. Doc. 70, 39th Cong., 2d 
Sess. 
H. Ex. Doc. 70, 39th Cong., 2d 
Sess. 
H. Ex. Doc. 70, 39th Cong., 2d 
Sess. 
H. Doc. 181, 39th Cong., 2d Sess.9 
Annual Report 1879, p. 1634.10 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report 1875, p. 295, H. 
Doc. 815, 61st Cong., 2d Sess. 
H. Doc. 446, 78th Cong., 2d Sess. 
H. Doc. 2063, 64th Cong., 2nd Sess.1 
H. Doc. 125, 85th Cong., 1st Sess. 
H. Doc. 509, 87th Cong., 2d Sess.' 
H. Doc. 740, 61st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 30, 71st Cong., 2d Sess. 
Rivers and Harbors Committee Dec. 
21, 75th Cong., 1st Sess. 
H. Doc. 576, 75th Cong., 3d Sess. 
H. Doc. 500, 83rd Cong., 2d Sess. 
H. Doc. 544, 87th Cong., 2d Sess. 
H. Doc. 240, 89th Cong., 1st Sess.' 
H. Doc. 207, 51st Cong., 2d Sess. 
H. Doc. 253, 70th.Cong., 1st Sess. 
H. Doc. 309, 77th Cong., 1st Sess. 
H. Doc. 335, 80th Cong., 1st Sess.

TABLE 31-B (Continued) 
DETROIT, MICH., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 21, 1956 
Mar. 3, 1875 
June 14, 1880 
Mar. 3, 1899 
Aug. 30, 1935 
June 2, 1937 
Mar. 2, 1945 
July 3, 1958 
Aug. 11, 1888 
July 11, 1870 
Aug. 5, 1886 
July 13, 1892 
June 13, 1902 
June 13, 1902 
Mar. 3, 1907 
Mar. 3, 1909 
July 25, 1912 
Mar. 4, 1915 
Sept. 22, 1922 
Jan. 21, 1927 
July 3, 1930 
June 26, 193417 
Aug. 30, 1935 
Mar. 7, 1942 
June 15, 1943 
Mar. 2, 1945 
July 24, 1946 
Deepen and Further Improve Channels in 
St. Clair River Between Limits of 27.1 
to 30 Feet to Provide Safe Navigation by 
Vessels with Drafts of 25.5 Feet. A Cutoff 
Channel in Canada at Southeast Bend and 
Abandon Old Southeast Bend Channels. 
ST. JOSEPH HARBOR, MICH. (See Section 36 of Text) 
Interior Revetments.'s 
Benton Harbor Canal.16 
Present Project Dimensions of Piers 
and a Turning Basin. 
Present Project Dimensions of 
Channel and Turning Basin, Near Mouth 
of Paw Paw River. 
Abandon Easterly 1,000 Feet of Canal 
Above West Line of 9th St., 
Turning Basin Above Mouth of Morrison 
Channel and Eliminate Training Basin 
Near Mouth of Paw Paw River. 
Maintenance of Turning Basin Near Mouth 
of Paw Paw River. 
ST. JOSEPH RIVER, MICH. (See Section 37 of Text) 
Provides for a channel from the 
Mouth to Berrien Springs. 
ST. MARYS RIVER, MICH. (See Section 38 of Text) 
Weitzel Lock (Replaced in 1943 by Mac 
Arthur Lock), Widen and Deepen 
Existing State Canal.' 6 
Poe Lock.' 
Dredging Through Shoals Above Falls 
and Shoals Below Falls Between Lower 
End of Canal and Upper Entrance Channel 
into Lake Nicolet (Formerly Hay Lake). 
Enlarging the Old Channel. 
Lake Nicolet and Neebish Channels Work 
in That Section of River Below Locks. 
Davis Lock Second Canal, and Emergency Dam. 
Lease of Waterpower at Falls. Lease 
Entered Into with Michigan Northern 
Power Co. Provided for Construction of 
Remedial and Compensating Works. 
Fourth Lock (Renamed 'Sabin' Lock in 1943). 
Deepen Tailrace of Power Plant. 
Widen Upper Approach to Canals Through 
Vidal Shoals, Extend Anchorage and 
Maneuver Area Below Locks. 
Remove Round Island, Middle Ground, 
Extension of Northwest Canal Pier, and 
Widen Channels Middle Neebish Route. 
Deepen Channels Throughout Downbound Route. 
Operation and Care of Canal and Locks 
Provided for from War Department 
Appropriations for Rivers and Harbors. 
Widen Brush Point Turn and Channel from 
Brush Point to Point Louise. 
Construct New (Mac Arthur) Lock on Site of 
Former Weitzel Lock, Deepen Approach Channels 
to 27 Feet, and Reconstruct Approach Piers. 
Named 'Mac Arthur' Lock and Changed Name 
of 'Fourth' Lock to 'Sabin' Lock. 
Remove Bridge Island and Construct New 
Hydroelectric Power Plant. 
Replace Poe Lock at St. Marys Falls Canal 
with a New Structure 800 Feet Long, 100 Feet 
Wide and 32 Feet Deep, with Necessary 
S. Doc. 71, 84th Cong., 1st Sess. 
H. Ex. Doc. 160, 43rd Cong., 
2d Sess., and Annual Report 
1875, pt. 1, p. 162. 
Annual Report 1880, pp. 2030, 
2031 and 2049-2055. 
H. Doc. 307, 55th Cong., 2d Sess., 
and Annual Report 1898, p. 2496. 
Rivers and Harbors Committee Doc. 
52, 74th Cong., 1st Sess. 
H. Doc. 129, 76th Cong., 1st Sess. 
S. Doc. 95, 84th Cong., 2d Sess.' 
River and Harbor Act 1888. 
Annual Report for 1880, 
pp. 2049-2055. 
Report by Maj. O.M. Poe, Corps 
of Engineers, Not Published. 
H. Ex. Doc. 72, 49th Cong, 2d Sess. 
H. Ex. Doc. 207, 51st Cong., 
2d Sess., and Annual Report 
1891, p. 2810. 
H. Doc. 138, 56th Cong., 2d 
Sess., and 215, 58th Cong., 3d 
Sess. 
H. Doc. 128, 56th Cong., 2d 
Sess. 
H. Doc. 333, 59th Cong., 2d 
Sess. (Plan 3). 
H. Doc. 65, 62d Cong., 1st Sess. 
District Engineer Report, 
Oct. 29, 1920. 
H. Doc. 270, 69th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
River and Harbor Committee Doc. 
53, 74th Cong., 1st Sess. 
H. Doc. 218, 77th Cong., 1st Sess. 
H. Doc. 679, 78th Cong., 2d Sess. 
and H. Doc. 339, 77th Cong., 
1st Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
31-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 21, 1956 
July 9, 1956 
June 3, 1896 
Mar. 2, 1907 
June 25, 1910 
June 3, 1896 
Aug. 11, 1888 
Mar. 3, 1905 
Aug. 30, 1935 
Construction of Nose and Center Piers, and 
Widen and Deepen Channel Across Point Iroquois 
Shoals and in Lake Nicolet to Provide Wider 
Anchorage and Maneuver Areas in St. Marys 
River. 
Deepen to Provide a Project Safe Draft of 25.5 
Feet Over Full Width to Downbound and 2-Way 
Channels (Including Anchorage Areas) and Over 
Westerly 300-Foot Width of Upbound Middle 
Neebish Channel, When Levels of Lake Superior 
and Huron are at Their Respective Low-Water 
Datum. 
Repeal Authorization of Bridge as a Part of 
Project, Authorize Alteration With Cost to 
be Apportioned by Sec. 6, Truman Hobbs Act, 
June 21, 1940. 
SAUGATUCK HARBOR AND KALAMAZOO RIVER, MICH. 
(See Section 39 of Text) 
Entrance Channel, Piers and Revetments. 
Deepening Entrance to 16 Feet. 
Deepening Channel in River to 14 Feet. 
SEBEWAING RIVER, MICH. (See Section 40 of Text) 
Entrance Channel 8 Feet Deep, 100 Feet Wide and 
15,000 Feet Long in Saginaw Bay. 
SOUTH HAVEN HARBOR, MICH. (See Section 41 of Text) 
Channel from Inner End of Piers to 
Highway Bridge. 4 
Present Dimensions of Piers and for a 
Turning Basin. 
Present Project Dimensions of Channel 
and Turning Basin. 
TAWAS BAY, MICHIGAN (See Section 42 of Text) 
1,750 Foot Breakwater, 12 Foot Deep Entrance 
Channel, 10-Foot Deep anchorage area. 
TOLEDO HARBOR, OHIO (See Section 43 of Text) 
A Channel 400 Feet Wide and 21 Feet Deep 
from 25-Foot Contour in Maumee Bay to 
Fassett Street Bridge, 200 Feet Wide and 
19 Feet Deep Above that Point and a 500-Foot 
Turning Basin at Upper End. A stone Revetted 
Earth Dike in Maumee Bay Channel. 
Act 1899 Modified to Insure a Navigable 
Channel to 21 Feet from Fassett Street 
Bridge to Lake. 
Channel 25 Feet Deep and 500 Feet Wide 
from 25-Foot Contour to Mouth of Maumee River 
(300 Feet Wide on Each Side of Center Dike 
in Bay Channel), Thence 400 Feet Wide to 
Fassett Street Bridge, 200 Feet Wide Above 
That Point and a Turning Basin at Upper 
End 18 Feet Deep. 
Widening at Bend at Mouth of River Opposite 
Chesapeake and Ohio Railway Dock. 
Removal of Center Dike in Maumee Bay 
Channel. 
Enlarge Widening at Bend Opposite Chesapeake 
and Ohio Dock and Turning Basin Opposite 
American Shipbuilding Co. Doc. 
Deepen Bay Channel Including Widenings to 28 
Feet, Deepen River Channels to New York Central 
Railroad Bridge to 27 Feet and Construct New 
Turning Basin Below Anthony Wayne Bridge.' 9 
WHITEFISH POINT HARBOR, MICH. (See Section 44 of Text) 
Breakwaters, Entrance Channel, 
Anchorage Basin. 
31-50 
S. Doc. 71, 84th Cong., 1st Sess.' 
None 
H. Doc. 912, 54th Cong., 1st Sess., 
Annual Report 1896, Vol. 2, 
Pt. 5, p. 2739. 
Annual Report 1907, p. 646. 
H. Doc. 635, 61st Cong., 2d Sess. '8 
H. Doc. 71, 54th Cong., 1st Sess. 
No Prior Survey or Estimate. 
H. Doc. 119, 58th Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
9,73d Cong., 1st Sess. ' and 
Unpublished Review Report of 
Chief of Engineers, Dated Dec. 
21, 1934. 
H. Doc. 189, 90th Cong., 1st Sess. 
H. Doc. 198, 55th Cong., 2d Sess. 
and Annual Report 1898, p. 2693. 
H. Doc. 865, 60th Cong., 1st Sess. 
Rivers and Harbors Committee Doc. 
21, 72d Cong., 1st Sess. 
H. Doc, 189, 81st Cong., 1st Sess. 
H. Doc. 620, 81st Cong., 2d Sess. 
H. Doc. 436, 84th Cong., 2d Sess. 
H. Doc. 153, 86th Cong., 1st Sess.' 
H. Doc. 446, 78th Cong., 2d Sess. 
Aug. 13, 1968 
Mar. 3, 1899 
June 25, 1910 
Aug. 30, 1935 
May 17, 1950 
Sept. 3, 1954 
July 3, 1958 
July 14, 1960 
Mar. 2, 1945

TABLE 31-B (Continued) 
DETROIT, MICH., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 17, 1967 
Mar. 2, 1867 
Mar. 3, 1873 
July 5, 1884 
July 13, 1892 
Mar. 2, 1907 
Sept. 3, 1954 
July 3, 1958 
July 3, 1958 
Oct. 12, 1972 
Dec. 30, 1970 
Oct. 23, 1962 
July 3, 1958 
Aug. 18, 1941 
Breakwater Inside Harbor. 
WHITE LAKE HARBOR, MICH. (See Section 45 of Text) 
New Channel, with Piers and Retetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
Present Project Depth of Channel. 
KALAMAZOO RIVER, BATTLE CREEK, MICH. 
(See Section 50 of Text) 
Flood Control Improvements to Kalamazoo River 
in the Vicinity of Battle Creek. 
KALAMAZOO RIVER, KALAMAZOO, MICH. 
(See Section 51 of Text) 
Enlarging and Straightening River Channel, Riprapping 
Channel Where Necessary, Reinforcement and 
Reconstruction of Bridges as Required, and 
Alterations to Existing Buildings and Utilities. 
POINT PLACE, TOLEDO, OHIO 
(See Section 52 of Text) 
Shoreline seawalls and inland levees 
RED RUN DRAIN-LOWER CLINTON 
RIVER, MICH. (See Section 53 of Text) 
Flood control and major drainage 
improvements to Red Run Drain 
and Lower Clinton River. 
RIVER ROUGE, MICH. (See Section 54 of Text) 
Channel Enlargement and Straightening, 
and Alteration or Replacement of Existing 
Bridges. 
SAGINAW RIVER, MICH., FLOOD CONTROL 
(See Section 55 of Text) 
Flood Control Improvements to Saginaw River 
and its Tributaries Including Tittabawassee, 
Shiawassee, Flint, and Cass Rivers. 
SEBEWAING, SEBEWAING RIVER, MICH. 
(See Section 56 of Text) 
Enlarging Present Channel of Sebewaing River, 
Altering Railroad and Highway Bridges, 
Removal of Dike. 
31-51 
Chief of Engineers. 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
No Prior Survey or Estimate.20 
S. Doc. 98, 83rd Cong., 2d Sess. 
S. Doc. 53, 84th Cong., 1st Sess.' 
H. Doc. 363, 92d Cong., 2d Sess. 
H. Doc. 431, 91st Cong., 2d Sess. 
H. Doc. 148, 87th Cong., 1st Sess. 
H. Doc. 346, 84th Cong., 2d Sess.' 
H. Doc. 286, 76th Cong., 1st Sess.)

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 31-B (Continued) AUTHORIZING LEGISLATION 
1. Contains latest published map. 
2. Included in Public Works Administration 
Program, Sept. 6, 1933. 
3. Amended 1868, 1879, and 1892. 
4. Completed under previous project. 
5. Latest published map is in Annual Report for 
1914, p. 2974. 
6. Modified by Act of June 10, 1872. 
7. Riprapping of protecting dikes portion of project 
is inactive. 
8. War Department Appropriations Act. 
9. Latest published maps is in H. Doc. 303, 66th Cong., 
1st Sess. 
10. Latest published map is in H. Doc. 588, 64th 
Cong., 1st Sess. 
11. Contains latest published maps. See also map 
with Rivers and Harbors Committee Doc. 19, 72d 
Cong., 1st Sess. 
12. Including Emergency Relief Administration 
Work authorized May 28, 1935. 
13. Except for dredging 25-foot channel to 1,150 
feet upstream of mouth in old channel, work authorized 
in this act is considered inactive. 
14. 22-foot project extended C&O R.R. Bridge and 
turning basin relocated under authority of Chief of 
Engineers. 
15. Completed under previous projects. Public Law 
130, 75th Cong., 1st Sess. 
16. Completed under previous projects. 
17. Permanent Appropriations Repeal Act. 
18. Latest map published is H. Doc. 608, 64th Cong., 
1st Sess. 
19. 27-Foot project is extended 2,800 feet and 
turning basin relocated under authority of Chief of 
Engineers. 
20. Latest published map is in H. Doc. 2053, 64th 
Cong., 2d Sess. 
31-52 
I

DETROIT, MICH., DISTRICT 
TABLE 31-C FEATURES OF EXISTING PROJECT 
Project 
Datum Planes 
Used by Above Mean 
Length Miles Upbound Water Level 
of from or Down- Project Project at Father 
Channel Mouth of bound Width Depth Point, Quebec Year 
Name of Channel (Feet) River Vessels (Feet) (Feet) (Feet) Complete 
Channel North of Belle Isle 1,2 
Channel at Heat of Detroit River 
Miscellaneous Shoals and 
Obstructions, Belle Isle to 
Fighting Island Channel 
Fighting Island Channel 
Ballards Reef Channel North of 
Junction with Livingstone Channel 
Livingstone Channel Upper 
Livingstone Channel Lower: 
CS 260+00 to 368+87 
CS 368+87 to 492+00 
East Outer Channel 
Misc., Shoals and Obstructions, 
Detroit River to Pelee Passage 
Pelee Passage Shoal 
Amherstburg Channel: 
Upper Section, Ballards 
Reef Channel 
Middle Section 
Lower Section, Hackett Range 
West Outer Channel 
Trenton Channel: 
DETROIT RIVER, MICH. (See Section 10 of Text) 
30 Both 200 
38,800 32 Both 800 
44,500 25 Both 
24,800 17 Both 
12,200 12 Both 
26,000 10 Down 
10,887 
12,313 
42,000 
Down 
Both 
Both 
21.0 571.3 
28.5 571.5-570.9 
- 28.5 570.9-570.3 
800 28.5 569.8 
600 28.5 569.8 
450 27.7 569.8-568.6 
450,800 
800-1,200 
1,200 
- - Both 
- - Both 
6,500 
12,000 
24,000 
21,000 
10 
29.0 
29.0 
28.5 
1964 
1964 
1964 
1962 
1963 
1964 
568.6 1961 
568.6 1961 
568.6 1964 
- 28.5-29.53 568.6 1964 
- 29.5 568.6 - 
Up 
Up 
Up 
Down 
600 27.5 
600 21-27.54 
600 21.28.55 
800 22.0 
Wyandotte Reach 31,500 17 Local 300 
Trenton Reach (Upper) 5,100 - Local 300 
Trenton Reach (Lower) 600 14 Local 250-300 
Grosse Ile Shoal 600 14 Local - 
ST. CLAIR RIVER, MICH. (See Section 35 of Text) 
Channel at Foot of Lake Huron 26,500 44 Both 800 
Channel North of Blue Water Bridge 4,100 39 Both 800 
Port Huron to Stag Island 38,000 38 Both 1,000-1,400 
Widening at Upper and Lower 
Ends of Stage Island) 37,600 31 Both 900-1,000 
St. Clair to Russel Island 77,000 24 Both 1,000 
Russel Island to Southeast Bend 20,600 11 Both 700-1,000 
Southeast Bend CS 324+00 
to 250+00 7,400 5 Both 700 
Cutoff Channel 30,300 - Both 700 
North Channel Outlet 8,000 - Small Craft 100 
569.8-569.5 
569.5-568.9 
568.9.568.6 
568.6 
27.0 569.9-569.7 
28.0 569.7-569.6 
28.0 569.6-568.8 
20.0 569.8 
30.00 576,8-576.5 
30.0 576.4-576.1 
27.4 576.1-574.9 
27.3 574.9-573.8 
27.3 573.8-572-4 
17.2 572.4-572.1 
27.1 573.1-572.0 
27.1 572.1-571.7 
10.0 571.7 
1960 
1960 
1960 
1929 
19646 
1964 
1941 
1904 
1961 
1962 
1961 
1962 
1962 
1962 
1962 
1962 
'This is a Side Channel. 
2Extends from Deep Water Near Windmill Point to a Point Opposite Fairview Slip, about 3,000 Feet. 
3Project Depth 29.5 Feet over Rock Shoals and 28.5 Feet over other than Rock Shoals. 4Project Depth 21 Feet in Easterly 300-Foot Width of Channel and 27.5 Feet in Westerly 300-Foot Width. 
6Project Depth 21 Feet in Easterly 300-Foot Width of Channel and 28.5 Feet in Westerly 300-Foot Width. 6Project Complete Except for Work Authorized by River and Harbor Act of 1950. 
31-53

TABLE 31-D 
REPORT OF THE CHIEF OF, ENGINEERS, U.S. ARMY 1975 
ST. MARYS RIVER, MICH.: EXISTING PROJECT 
(See Section 38 of Text) 
Lock Davis Sabin MacArthur New Poe 
Miles Above Mouth 47 47 47 47 
Clear Width of Chamber Feet 80 80 80 110 
Length Between Gate Quione Feet 1,350 1,350 800 1,200 
Lifts, Feet 21.7 21.7 21.7 21.7 
Depth Over Upper Breast Walls' Feet 24.3 24.3 31 32 
Depth Over Lower Breast Walls' Feet 23.1 23.1 31 32 
Foundation Rock Rock Rock Rock 
Type of Construction Concrete Concrete Concrete Concrete 
Estimated Cost $6,200,0002 $3,275,000' $12,909,440 $39,000,000 
Actual Cost $2,200,0005 $1,750,0006 $12,718,8064,7 $34,813,066 
Completed (Open to Commerce) Oct. 21, 1914 Sept. 18, 1919 July 11, 1943 June 26, 1969 
Emergency Dam for South Canal North Canal 
Miles Above Mouth 47 47 
Estimated Cost -9 $300,000 
Type Steel Stoplogs Recessed Steel Stoplogs Recessed 
Into Lock Masonry Into Lock Masonry 
Cost, Completed -'9 $169,2248 
Year Completed 1943 1922 (Modified 1963) 
'At low water datum 599.5 above and 577.8 below. 
2Includes Cost of North Canal. 
'Includes cost of canal excavations to provide necessary approaches to lock, canal walls, piers, and emergency dam, 
$662,919. 4Excludes cost of deepening and enlarging South Canal, $1,653,378. 
'Excludes cost of North Canal, $2,572,611. 
'Excludes cost of canal excavations to provide necessary approaches to lock, canal walls, piers, and emergency dam, 
$662,919. 7Excluding cost of lower guard gates which were never installed. 
SIncluding engineering office, and inspection. 
9Not separable from cost of locks. 
Note: Limiting draft to locks is determined by depth over breast walls. 
31-54

DETROIT, MICH., DISTRICT 
RECONNAISSANCE & CONDITION 
(See Section 46 of Text) 
Name of Project 
MICHIGAN: 
Belle River 
Caseville Harbor 
Cheyboygan Harbor 
Harrisville 
Mackinac Island Harbor 
Mackinaw City Harbor 
Manistique Harbor 
Pointe Lookout Harbor 
St. James Harbor 
Traverse City 
OHIO: 
Put-In-Bay 
SURVEYS 
Date Survey Conducted 
May 1975 
October 1974 
October 1974 
October 1974 
October 1974 
June 1975 
May 1975 
October 1974 
August 1974 
June 1975 
31-55 
TABLE 31-E 
I I 
--

TABLE 31-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Belle River, Mich. 1907 24,301 8,447 
Black River (Alcona Co.) Mich. 1971 
Channels in the Straits of Mackinac, Mich. 1972 2,832,629 70,828 
Cheboygan Harbor, Mich. 1973 504,236 394,181 
Cross Village, Mich. 1967 
Forestville, Mich. 1969 
Grays Reef Passage, Mich. 1970 190,521 570,871 
Harrisville, Mich.' 1965 1,444,259 89,122 
Kellys Island 1974 119,951 
Mackinac Island Hbr., Mich.2 1969 229,085 60,000 
Mackinaw City Hbr., Mich.3 1969 136,286 6,285 
Manistique, Mich. 1971 1,615,688 1,396,891 
Maumee River above Toledo, Ohio 1873 7,000 
Petoskey 1974 118,239 243,182 
Point Lookout 1974 2,747,084 2,091 
Pine River, Mich. 1907 13,647 7,338 
Put-In-Bay, Ohio 1951 51,609 11,106 
Rogers City, Mich. 1926 5,666 226 
St. James, Beaver Island, Mich.4 1957 49,171 17,066 
Traverse City Harbor, Mich.5 1967 369,557 41,980 
West Harbor, Ohio 1966 
1. Includes Contributed Funds of $129,500. 
2. Includes Contributed Funds of $105,004. 
3. Includes Contributed Funds of $136,286. 
4. Includes Contributed Funds of $7,500. 
5. Includes Contributed Funds of $121,000. 
31-56

DETROIT, MICH., DISTRICT 
TABLE 31-G OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Camp Perry, Ohio' 1967 275,0002 
Grand River, Grandville, Mich.3 1966 - - 
Grand River, Lansing, Mich. 1971 7,300 
Kawkawlin River, Mich.' 1971 1,204,5594 
Mount Clemens, Clinton River, Mich.' 1953 1,136,0085 
Ottawa, Ohio3 1967 - - 
Red Beach-Howard Farms Area, 
Lucas County, Ohio 1953 4,467 
Upper River Rouge, Mich. 6 1968 7,935 
1. Completed. 
2. Includes $125,000 Contributed Funds. 
3. Awaiting appropriation of funds. 
4. Includes $204,559 Contributed Funds. 
5. Includes $202,996 Contributed Funds. 
6. Planning indefinitely suspended due to lack of local 
cooperation. 
31-57

BUFFALO, N.Y., DISTRICT* 
The district comprises a portion of northeastern and St. Lawrence River, with their tributary 
Ohio, northwestern Pennsylvania, and western drainage basins from and including Sandusky 
and northern New York, embracing U.S. waters of Bay, Ohio, to international boundary line east of 
Lake Erie, exclusive of western end, Lake Ontario, Frontier, N.Y. 
IMPROVEMENTS 
Navigation Page 
1. Ashtabula Harbor, Ohio ...................... 32- 2 
2. Black Rock Channel and 
Tonawanda Harbor, N.Y. ..................... 32- 2 
3. Buffalo Harbor, N.Y. ............................ 32- 3 
4. Cape Vincent Harbor, N.Y ................... 32- 4 
5. Cattaraugus Harbor, N.Y. ..................... 32- 5 
6. Cleveland Harbor, Ohio ...................... 32- 6 
7. Conneaut Harbor, Ohio ......................... 32- 7 
8. Dunkirk Harbor, N.Y. .......................... 32- 8 
9. Erie Harbor, Pa. ................................... 32- 9 
10. Fairport Harbor, Ohio ......................... 32-10 
11. Great Sodus Bay Harbor, N.Y ............ 32-11 
12. Huron Harbor, Ohio ............................ 32-12 
13. Irondequoit Bay, N.Y .......................... 32-12 
14. Little Sodus Bay Harbor, N.Y. ............. 32-13 
15. Lorain Harbor, Ohio ........................... 32-13 
16. Oak Orchard Harbor, N.Y .................... 32-14 
17. Oswego Harbor, N.Y. ............................ 32-15 
18. Rochester Harbor, N.Y. ......................... 32-16 
19. Rocky River Harbor, Ohio ...................... 32-16 
20. Sandusky Harbor, Ohio ......................... 32-16 
21. Vermilion Harbor, Ohio ....................... 32-17 
22. Wilson Harbor, N.Y. ............................. 32-18 
23. Reconnaissance and condition 
surveys ....................................... 32-18 
24. Other authorized navigation 
projects .. ......................................... 32-18 
25. Navigation work under special 
authorization .................................... 32-18 
Beach Erosion Control Page 
26. Hamlin Beach State Park, N.Y. ............. 32-18 
27. Lakeview Park, Lorain, Ohio ................. 32-19 
28. Presque Isle Peninsula, Erie, Pa. ............ 32-19 
29. Other authorized beach erosion 
control projects ..................................... 32-20 
30. Beach erosion work under special 
authorization ........................................ 32-20 
Flood Control 
31. Eastlake, Ohio, Chagrin River ............... 32-20 
32. Ellicott Creek, N.Y...............................32-20 
33. Fremont, Ohio, Sandusky River .............32-21 
34. Ithaca, N.Y., Cayuga Inlet .................... 32-21 
35. Mt. Morris Lake, N.Y., Genesee 
River .................................................... 32-22 
36. Red Creek, N.Y. .................................. 32-22 
37. Scajaquada Creek, N.Y. ........................ 32-23 
38. Wellsville, N.Y., Genesee River ............. 32-24 
39. Inspection of completed flood 
control projects ............................... 32-25 
40. Other authorized flood control 
projects ..................................... 32-25 
41. Flood control work under special 
authorization ........................................ 32-25 
General Investigations 
42. Surveys ................................................ 32-25 
43. Collection and study of basic data .......... 32-25 
44. Research and development .................... 32-25 
* All cost and financial statements for projects are listed in Table 32A at the end of this chapter. All other tables are referenced 
in text and also appear at the end of this chapter. 
32-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. ASHTABULA HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth 
of Ashtabula River, 59 miles easterly from 
Cleveland, Ohio. (See Lake Survey Chart 342.) 
Previous projects. For details see page 1963 of 
Annual Report for 1915, and page 1593 of Annual 
Report for 1938. 
Existing project. For description see pages 1297- 
99 of Annual Report for 1966. Actual costs for new 
work for completed portion of project were $11,- 
115,147. Removal of 250 feet of east inner 
breakwater as authorized by 1937 act, at an estimated 
cost of $128,000 (July 1954) and deepening 
triangular-shaped harbor area adjacent 
thereto, as authorized by 1960 act, at estimated 
cost of $427,000 (Feb. 1961) were deferred for 
restudy and are excluded from foregoing estimate. 
By letter dated May 29, 1975, recommendation 
was made to higher authority to reclassify these 
portions of the project from deferred for restudy 
category to the active category. Non-Federal costs 
of $5,696,000 were incurred for construction of 
access roads, docks, storage and handling facilities 
and dockside dredging. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 27 piers and 
wharves, two are owned by city of Ashtabula and 
Coast Guard. Twenty-one facilities are along 
banks of Ashtabula River and six are on south side 
of outer harbor. Twenty-two terminals have 
railroad connections and 15 mechanical-handling 
facilities. Facilities are considered adequate for 
existing commerce. (See Port Series No. 42, revised 
1960, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $10,153. U.S. derrick boat 
Tonawanda repaired about 150 linear feet of the 
west breakwater, rubblemound construction at a 
cost of $55,479. Preparation of an Environmental 
Impact Statement and other miscellaneous costs 
amounted to $47,368. Planning was continued for 
the diked disposal area at a cost of $269,643. 
Condition at end of fiscal year. Existing project 
is about 95 percent complete. West breakwater 
was completed in 1915 except 580 feet of inner end 
which was completed in 1923, and 600 feet of outer 
end which was completed in 1935. East 
breakwater was completed in 1915; 800 feet of 
westerly end was removed and a lakeward extension 
of 700 feet was completed in 1935. Old inner 
east breakwater 1,200 feet long was completed in 
1909, and westerly 600 feet were removed in 1913 
and 350 feet in 1935. The 18- and 16-foot sections 
of river channel and turning basin were deepened 
in 1939. A 25-foot deep approach channel through 
east outer harbor to easterly docks and a turning 
basin were completed in 1960. Deepening of this 
area to 28 feet, as authorized by 1965 act, was initiated 
in July 1967 and completed in June 1968. 
Deepening upper 1,550 feet of river channel to 16 
feet was completed in July 1960. Deepening 29- 
foot entrance channel, 28-foot channel through 
outer harbor, 27-foot approach channel to Penn 
Central Co's. slip, 27-foot channel in Ashtabula 
River to a point 2,000 feet upstream from its 
mouth, and 22-foot areas in east outer harbor, as 
authorized by the 1960 act, was initiated in May 
1962 and completed in June 1963. Harbor structures 
require repairs. Portions of both east and 
west breakwaters, rubblemound construction, 
where slope stone has pulled away, core stone has 
washed away, and deck stones have dropped, require 
major repairs. East breakwater light foundation 
tilted due to displacement of rubblemound 
protection and needs repairs. Approximately one 
mile of the navigation channel at the upriver end 
is not being used and has not been maintained to 
project depth. Work remaining to complete project 
consists of removal of 250 feet of inner breakwater, 
as authorized by 1937 act which is to be restudied; 
deepening triangular-shaped area adjacent 
thereto, as authorized by 1960 act which is also to 
be restudied. Costs of existing project were $11,- 
115,147 (including $536,648 public works funds) 
for new work and $4,803,671 for maintenance, a 
total of $15,918,818. 
2. BLACK ROCK CHANNEL AND 
TONAWANDA HARBOR, N.Y. 
Location. Improvement is essentially that of upper 
13.5 miles of Niagara River from its head at 
Lake Erie, Buffalo, N.Y., to and including 
Tonawanda Harbor, N.Y. It comprises improvements 
formerly designated by three titles; 
via, Lake Erie entrance to Black Rock Harbor and 
Erie Basin, N.Y., Black Rock Harbor and 
Channel, N.Y., and Tonawanda Harbor and 
Niagara River, N.Y. (See Lake Survey Chart 312.) 
Previous projects. For details see items 5 and 7, 
page 1970 of Annual Report for 1915, and page 
1612 of Annual Report for 1938. 
Existing project. For description of existing 
project and Federally owned Black Rock ship lock, 
see page 1548 of Annual Report for 1962. Cost for 
completed portion of new work is $10,457,093. Improvement 
of guide pier at Black Rock lock, as 
authorized by 1935 act, is considered inactive and 
excluded from foregoing cost. Estimated cost 
(1954) of this portion is $931,000. Enlarging of existing 
21-foot turning basin and deepening lower 
1,500 feet of Tonawanda inner harbor from 16 to 
21 feet, authorized by the 1954 act, is to be 
restudied and is excluded from foregoing cost. 
32-2

BUFFALO, N.Y., DISTRICT 
Estimated cost (1961) of this portion is $339,000. 
Non-Federal costs are estimated at $1,540,000 for 
costs incurred by New York State for construction 
of Erie Basin and protecting breakwater, and construction 
and extension of Bird Island pier, and by 
other local interests for relocation of utilities. See 
Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Two facilities are along upstream 
end of channel. Below Black Rock lock and 
at Tonawanda Harbor there are 13 privately owned 
terminals. There are two State-owned barge 
canal terminals at Tonawanda, N.Y., and several 
marine service and supply docks for recreational 
and other small craft. The Corps owns a wharf 
adjacent to Black Rock Lock which is private. Ten 
terminals have railroad connections and six 
mechanical-handling facilities. Facilities considered 
adequate for existing commerce. (Port 
Series No. 41, revised 1971, Corps of Engineers.) 
Operations and results during fiscal year. 
Operation and care (Black Rock Lock): Lock was 
in operation 320 days and closed for underwater 
cleaning and repairs February 4 through April 8, 
1975. Ordinary maintenance and repair of structures 
and grounds were accomplished throughout 
year by Government plant and hired labor. 
Total costs of $1,152,621 were distributed as 
follows: operation and care: operation of lock, ordinary 
maintenance and repair, $324,325; lock, 
guards, and maintenance of grounds, $100,889; 
miscellaneous inspection and condition surveys, 
$40,732. Maintenance (structure repairs); repairs 
to Bird Island pier $231,734; clearing and snagging 
in project channels by Government plant and 
hired labor cost $45,999; planning and contract for 
repairs to electrical system and lower guide wall 
cost $408,942. Construction of a diked disposal 
facility in Buffalo Harbor for confining dredged 
materials from the Black Rock Channel and 
Tonawanda Harbor project was continued at a 
cost of $532,697. 
Condition at end of fiscal year. Existing project 
is about 89 percent complete. Channel from Buffalo 
Harbor north entrance to opposite Sixth 
Avenue, North Tonawanda, is complete. Different 
sections of this channel were completed to project 
depth as follows: Lake Erie section in 1909; Black 
Rock Canal section in 1915; Niagara River section 
from lock to deep water pool above Tonawanda, in 
1913; and Tonawanda section, including turning 
basin, 1921. Channel was further widened as 
follows: Triangular area at Lake Erie entrance to 
canal was completed in 1922 and transferred from 
Buffalo Harbor project in 1945; Lake Erie section 
was widened at bend opposite foot of Georgia 
Street, Buffalo, in 1924; Black Rock Canal section, 
just south of International Bridge at Buffalo, in 
1928, and opposite foot of Maryland Street, Buffalo, 
in 1930; and Niagara River section near 
westerly end of Rattlesnake Island shoal in 1928. 
Rock shoals extending above a depth of 21.4 feet 
were removed from Lake Erie entrance to canal 
and in canal south of Ferry Street Bridge, in 1937. 
Rock shoals extending above a depth of 22 feet 
were removed from Lake Erie entrance to canal, in 
Black Rock Canal, and in Niagara River portion of 
canal in 1948-49. Widening Lake Erie entrance to 
canal was completed in 1958. Tonawanda Creek 
Channel was completed in 1902. Tonawanda Inner 
Harbor Channel was completed in 1904. Enlargement 
of Tonawanda turning basin and extension 
of Bird Island pier were completed in 1936. Lock, 
including wing walls and retaining walls above 
lock, was completed in 1914, and 100-foot east 
wing wall extension in 1927. Guide pier connecting 
with west lower wing wall was completed in 1916, 
except for 200-foot northerly extension and construction 
of concrete platform in the angle. 
Upstream 300 linear feet of lower west guide pier 
were repaired 1951-59. Lock-operating houses were 
completed in 1924. Work remaining to complete 
project is improvement and extension of guide pier 
as authorized by 1935 River and Harbor Act, 
which is considered inactive, and deepening lower 
1,500 feet of Tonawanda Inner Harbor as authorized 
by 1954 River and Harbor Act, which is to be 
restudied. Condition of structures range from poor 
to fair. Repairs to the most critical section of Bird 
Island pier from its northerly terminus at Squaw 
Island to the Peace Bridge (2,800 feet) will be 
completed during 1976. Replacement of original 
electrical equipment has been completed. Planning 
to repair or replace much of the badly 
deteriorated or worn out mechanical systems has 
been initiated. The wing wall at the upper approach 
to the lock has shifted laterally about two 
feet at maximum deflection. Costs of existing project 
were $10,457,093 (including $1,760,000 
emergency relief funds and $6,000 expended for 
deferred portion of project) for new work; $6,642,- 
710 for maintenance; $8,366,753 for operating and 
care; a total of $25,466,556. In addition, $1,356,007 
expended between July 9, 1914, and June 30, 1935, 
on operation and care of works of improvement 
under provisions of permanent indefinite appropriation 
for such purposes. 
3. BUFFALO HARBOR, N.Y. 
Location. At eastern end of Lake Erie, at head 
of Niagara River, 176 miles easterly from 
Cleveland, Ohio. (See Lake Survey Charts 3 and 
314.) 
Previous projects. For details see page 1967 of 
Annual Report for 1915 and page 1606 of Annual 
Report for 1938. 
Existing project. For description see page 1368 
of Annual Report for 1963. New work for com- 
32-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
pleted project cost $18,837,601. Estimated non- 
Federal costs were $9,188,000 for deepening, 
widening, and improving Buffalo River and ship 
canal, constructing piers, retaining walls, and 
dikes and performing dockside dredging. See 
Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 45 wharves and 
piers of which 4 piers, owned by Niagara Frontier 
Port Authority, and 9 privately owned and 
operated facilities are on outer harbor and along 
sides of Lackawanna and Union ship canal, 4 are 
along banks of Buffalo ship canal, and 26 along 
Buffalo River. Coast Guard facilities are at mouth 
of Buffalo River along left bank. City of Buffalo 
owns a slip on right bank of Buffalo River just 
north of Michigan Avenue Bridge for mooring city 
fireboat. Thirty-four terminals have railroad connections 
and 29 mechanical-handling facilities. 
Facilities considered adequate for existing commerce. 
(See Port Series No. 41, revised 1971, 
Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and 
condition surveys by Government plant and hired 
labor cost $64,224. U.S. derrick boat McCauley 
repaired about 30 linear feet of old north and 
south breakwaters, rubblemound construction, at 
a cost of $2,294. Maintenance dredging, Buffalo 
River and ship canal was accomplished by U.S, 
hopper dredge Lyman removing 244,076 cubic 
yards, bin measure, of material at a cost of $476,- 
599. Handling of dredged materials (disposal in diked 
area) was done at a cost of $139,346. Construction 
of a diked disposal area south of existing 
south entrance arm breakwater (Site 4) was initiated 
at a cost of $5,277,540. 
Condition at end of fiscal year. Existing project 
is complete. Stony Point breakwater was completed 
in 1899, a 1,000-foot extension was completed 
in 1914, 1,200 feet of shore end were sold to 
Lackawanna Steel Co. in 1918, and another 1,000- 
foot extension completed in 1935. South 
breakwater was completed in 1903, and a 300-foot 
extension completed in 1935. North breakwater 
was completed in 1901 and old breakwater in 1893. 
South pier was completed in 1869 and rebuilt in 
1962. Removal of three shoals to 27 feet, on direct 
approach to south entrance channel was completed 
in 1954. Deepening to 25 feet in southerly 
part of outer harbor was completed in 1956. During 
1955 and 1956, Buffalo River Channel, Buffalo 
River entrance channel, and ship canal were 
deepened to 22, 23, and 22 feet, respectively. 
Deepening 23-foot project area in outer harbor was 
completed in 1956 except for strips 50 feet wide 
along harbor line and 180 feet wide between 
Merchants Refrigerating Co.'s piers and south end 
of city dike. Widening Buffalo River Channel at 
Ohio Street Bridge was completed in July 1959. 
Deepening north entrance channel to 25 feet in 
earth and 26 feet in rock, removal of 1,000 feet of 
old breakwater, widening southerly portion of Buffalo 
River entrance channel, relocation of Coast 
Guard facilities and construction of a detached 
breakwater, all as authorized by 1945 act, were 
completed in 1962. Removal of shoals and deepening 
of approach to south entrance, south entrance 
channel, and southerly part of outer harbor, all as 
authorized by 1960 act, were initiated in June 
1962 and completed in May 1964. Deepening 27- 
foot project area of north outer harbor including 
the 50- and 180-foot wide strips along harbor line 
as authorized by 1962 act, was initiated in July 
1964 and completed in September 1965. Repairs to 
650 linear feet of superstructure of old breakwater 
were completed in August 1965 under minor 
rehabilitation program. Harbor structures are 
generally in good condition except at various 
points of south breakwater completed in 1902 and 
old breakwater completed in 1889, where slope 
stone on lakeside has been displaced. Repair of 
collapsed 1,400-foot long south pier was completed 
in May 1962. For disposal of dredged materials a 
pilot study experimental diked disposal area was 
constructed in 1968 and another diked disposal 
area at Times Beach was constructed in 1971. 
Costs of existing project were $18,837,601 
(including $655,500 public works funds) for new 
work, $23,391,515 for maintenance and $295,457 
for rehabilitation, a total of $42,524,573. In addition, 
of the $150,000 contributed by local interests 
for construction of the Times Beach Dike, $56,805 
was used towards the cost of the work. The 
remainder was refunded to local interests based on 
favorable contract bids and subsequent change in 
policy for percentage requirements for contributions 
by local interests. 
4. CAPE VINCENT HARBOR, N.Y. 
Location. On south shore of St. Lawrence River 
about 2.5 miles from Lake Ontario and 49 miles 
northerly from Oswego Harbor, N.Y. (See Lake 
Survey Chart 2). 
Previous projects. For details see page 1975 of 
Annual Report for 1915 and page 1634 of annual 
report for 1938. 
Existing project. For description of existing 
project see page 1566 of Annual Report for 1962. 
Actual costs for completed portion of project were 
$275,082. Deepening remainder of 16-foot area of 
project as authorized by 1945 act, at estimated 
cost of $159,000 (1954) is deferred for restudy. See 
Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Two privately owned terminals 
for fish and a United States fish hatchery 
are located along waterfront bordering project. A 
ferry to Wolfe Island, Ontario, uses wharf owned 
32-4

BUFFALO, N.Y., DISTRICT 
by village. A yacht club dock and several other 
privately owned servicing and storage docks are 
for recreational and other small craft. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services by 
hired labor cost $6,000. 
Condition at end of fiscal year. Project is about 
63 percent complete. Construction of a breakwater 
1,381 feet long, completed in 1915, of which 40 feet 
of shore return arm was built in 1901, and deepening 
of 20-foot project area and a portion of 16-foot 
project area completed in 1947. Breakwater is of 
timber-crib, concrete-superstructure type. The 
crib is in good condition but the concrete cap is 
disintegrating and needs repair. 
Deepening of the remainder of the 16-foot area, 
as authorized'by the 1945 act, is classified as 
deferred for restudy and remains to be done to 
complete the project. 
Costs of existing project were $275,082 for new 
work and $59,026 for maintenance, a total of 
$334,108. 
5. CATTARAUGUS HARBOR, N.Y. 
Location. At mouth of Cattaraugus Creek on 
south shore of Lake Erie about 12 miles 
northeasterly from Dunkirk Harbor, N.Y. and 24 
miles southwesterly from Buffalo Harbor, N.Y. 
(See Lake Survey Chart 32). 
Existing project. Provides for navigation, flood 
control and recreational breakwater fishing by 
constructing: (a) arrowhead breakwaters in Lake 
Erie at mouth of Cattaraugus Creek; (b) an entrance 
channel, widening at lakeward end, 100 feet 
wide and eight feet deep from that depth in lake to 
a maneuvering area; (c) an irregular-shaped 
maneuvering area about 300 feet by 600 feet, six 
feet deep; (d) a channel, 100 feet wide, six feet 
deep, from maneuvering area upstream about 1,- 
900 feet; (e) a riprapped friction section extending 
about 750 feet upstream from the navigation 
channel through the Penn Central Co. railroad 
bridge; (f) levee on left bank 425 feet long upstream 
of railroad bridge; (g) development of 
recreational facilities at mouth for breakwater 
fishing. Estimated Federal cost for new work is 
$3,790,000 (Oct. 1975). Estimated non-Federal 
cost for new work is $1,955,000 (Oct. 1975) including 
cash contribution of $1,945,000 and the 
remainder for lands and damages. Existing project 
was authorized by 1968 River and Harbor Act (H. 
Doc. 97, 90th Cong. 1st sess.). 
Local cooperation. Local interests are required 
to contribute in cash 50 percent of that portion of 
the first cost of Federal construction allocated to 
navigation, such contributions presently estimated 
at $1,945,000 to be paid either in a lump 
sum prior to initiation of construction, or in installments 
over the construction period at a rate 
proportionate to the proposed or scheduled appropriation 
of Federal funds, the final apportionment 
of cost to be made after actual costs have 
been determined; provide without cost to the 
United States all lands, easements, and rights-ofway 
required for construction and subsequent 
maintenance of the project and for aids to navigation 
upon the request of the Chief of Engineers, including 
suitable areas determined by the Chief of 
Engineers to be required in the general public interest 
for initial and subsequent disposal of spoil 
and any necessary retaining dikes, bulkheads, and 
embankments therefor, or the cost of such retaining 
works; hold and save the United States free 
from damages due to the construction and 
maintenance of the project; establish a competent 
and properly constituted public body empowered 
to prescribe and enforce regulations pertaining to 
flood control and to regulate the use and development 
of the harbor and related facilities, with the 
understanding that said facilities will be open to 
all equal terms; provide and maintain without 
cost to the United States: depths in the service 
channels to principal docks and berthing areas 
commensurate with those provided in the Federal 
project; and necessary mooring facilities and 
parking and service areas, including a launching 
ramp, sanitary facilities, and an adequate public 
landing or wharf, with provision for the sale of 
motor fuel, lubricants, and potable water, 
available to all on equal terms; contribute in cash 
41 percent of the annual Federal maintenance 
costs, excluding aids to navigation, such contribution 
representing the costs allocated to flood control 
for channels and breakwaters; maintain and 
operate the flood control portion of the project 
above the navigation channel in accordance with 
regulations prescribed by the Secretary of the Army; 
prescribe and enforce regulations to prevent 
encroachment or obstruction of channels and 
rights-of-way necessary to proper functioning of 
the project for flood control; establish regulations 
prohibiting discharge of untreated sewage, garbage, 
and other pollutants in the waters of the 
harbor by users thereof, which regulations shall be 
in accordance with applicable laws or regulations 
of Federal, State, and local authorities responsible 
for pollution prevention and control; and with 
respect to the recreational facilities: pay, contribute 
in kind or repay (which may be through 
user fees) with interest, one-half of the cost of 
modifications necessary to provide for recreational 
fishing on the breakwater, and one-half of the cost 
of associated access facilities, parking areas, and 
sanitary facilities, the amount involved being 
currently estimated at $74,000 subject to final adjustment 
after actual costs have been determined; 
bear all costs of maintenance, operation, and 
32-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
replacement of the modifications and associated 
facilities, the amount involved being currently estimated 
at $6,000 on an average annual basis. 
Assurances will be formally requested upon completion 
of the Design Memorandum. 
Terminal facilities. There is no commercial 
navigation. Terminal facilities consist of private 
docks for recreational craft. 
Operations and results during fiscal year. New 
work. Preconstruction planning was continued. 
Condition at end of fiscal year. Completion of 
preconstruction planning and construction of project 
remain to be done to complete project. 
6. CLEVELAND HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth 
of Cuyahoga River, 176 miles westerly from Buffalo, 
N.Y. (See Lake Survey Chart 354.) 
Previous projects. For details see page 1962, Annual 
Report for 1915, and page 1585, Annual 
Report for 1938. 
Existing project. For description see page 1269 
of Annual Report for 1967. Estimated Federal cost 
of new work is $45,548,400 (Oct. 1975). Non- 
Federal cost estimate is $28,548,000 (Oct. 1975) for 
lands, easements, and rights-of-way, participation 
in replacement of bridges obstructive to navigation, 
removal of other bridges, construction of 
bulkheads, relocation of utilities and dockside 
dredging. Remaining work authorized by 1946 
River and Harbor Act consisting of widening and 
deepening right bank of Cuyahoga River at 
downstream end of Cut 4 is considered inactive 
and excluded from foregoing cost estimate. 
Estimated Federal cost (1966) of this portion is 
$85,600 and non-Federal costs are estimated at 
$5,000,000 (July 1966). See Table 32-B for 
authorizing legislation. 
Local cooperation. City of Cleveland has not 
acquired the necessary lands for completion of 
widening Cuyahoga River at downstream portion 
of Cut No. 4 as a portion of the project modification 
authorized by 1946 act. This remaining work 
is classified inactive. All other conditions fully 
complied with. 
Terminal facilities. There are 72 piers and 
wharves. Eleven are owned by city of Cleveland, of 
which 7 are operated by the Cleveland-Cuyahoga 
County Port Authority. Fourteen are on outer harbor, 
11 on banks of Old River and remaining 47 
along deep-draft section of Cuyahoga River. Fortyseven 
terminals have railroad connections and 39 
mechanical-handling facilities. The Corps owns a 
wharf at foot of East 9th Street. Facilities are considered 
adequate for existing commerce. (See Port 
Series No. 43, revised 1970, Corps of Engineer.) 
Operations and results during fiscal year. New 
work: For work authorized by 1958 act, miscellaneous 
engineering services were accomplished 
at a cost of $2,005. Maintenance: Miscellaneous 
inspection services and condition surveys by 
Government plant and hired labor cost $80,016. 
Maintenance of Cuyahoga and Old River to 23- 
foot depth, by contract, employing clamshell 
bucket dredge, was accomplished and 597,114 
cubic yards, scow measure, of shoaled material 
were removed. Total cost of the contract dredging 
operations was $1,496,306. Snagging and clearing 
in project channels by Government plant and 
hired labor cost $15,843. Repairs to approximately 
800 linear feet of east and west breakwaters by 
U.S. derrick boats Tonawanda, Ohio and 
McCauley cost $822,695. Planning was continued 
for fourth diked disposal area, (Site 14), construction 
of alternate disposal area (Site 12) in the east 
outer harbor was completed and pump-out costs 
for the disposal of 597,114 cubic yards of 
Cuyahoga River and Old River dredgings into the 
diked area, were done at cost of $5,564,242. 
Condition at end of fiscal year. Existing project 
is about 67 percent complete. River entrance 
channel was improved by construction of parallel 
piers 325 feet apart, and dredging to 25 feet deep 
at low-water datum up to Penn Central Co. 
bridge. Piers were completed in 1900 and dredging 
in 1935. An outer harbor, about 1,300 acres in extent, 
was formed by construction of an aggregate 
length of about 30,000 feet of breakwater, including 
converging arms, completed in 1915. 
About 1,770 linear feet of east breakwater and 1,- 
000 linear feet of west breakwater were repaired 
under major rehabilitation program in 1962 and 
1963. Structures are generally in fair condition. 
Sections of east breakwater where cover stone has 
been displaced and settled are in need of repair. 
Several lake storms in connection with high lake 
levels combined to displace several sections of the 
concrete cap of the west breakwater. In addition, 
cracks in the concrete over most of the west 
breakwater indicate possible crib failure. Currently 
about 8,450 linear feet of the east breakwater, 
1,200 linear feet of the west breakwater 
and the entire west pier are in need of repair. 
Main entrance was widened to 700 feet and 
protected by converging arms extending lakeward 
from east and west breakwaters, completed in 
1908. Outer harbor was deepened, 1933-35, to 25 
feet at low-water datum throughout west basin, in 
entrance channel, and over a portion of east basin 
adjacent to entrance channel. Portions of channel 
in Cuyahoga River were widened each year from 
1930 to 1942 and in 1958. Removal of 150 feet of 
easterly end of west breakwater and construction 
of 400 feet of spur breakwater to protect gap in 
west breakwater shore arm were completed in 
1935. A concrete base for a light tower was constructed 
at east end of east breakwater in 1917 in 
lieu of east-end pierhead. Providing a 1,300-foot 
32-6

BUFFALO, N.Y., DISTRICT 
extension of Cuyahoga River channel to present 
project limit was authorized by 1945 River and 
Harbor Act and partially completed with Defense 
Plant Corp. funds during 1942 and remaining portion 
previously classified inactive was deleted 
from project by 1962 act. Old River to Sand 
Products Corp. dock was deepened to 23 feet in 
1952. Replacement of Norfolk & Western Railway 
bridge 25 was completed April 1953. Replacement 
of Penn Central Co. bridge 8 was completed 
December 1953. Replacement of Penn Central Co. 
bridge 9 was completed June 1956 and channel in 
vicinity of structure widened during 1957. 
Replacement of Penn Central Co. bridge 1 was 
completed in January 1957. Replacement of Norfolk 
& Western Railway bridge 15 was completed 
in March 1959. Replacement of Baltimore & Ohio 
Railroad bridge 3 was completed in October 1957. 
Widening near Penn Central Co. bridge 1 was 
completed in September 1957. Widening near 
Baltimore & Ohio Railroad bridge 3 and in vicinity 
of Norfolk & Western Railway bridge 15 and 
deepening Cuyahoga River were completed in July 
1958. Widening Cuyahoga River at upstream portion 
of Cut 4 was completed in October 1959.. 
Widening and deepening Cuyahoga River at Cut 
10 were completed in April 1961. Deepening lake 
approach, entrance channel, lower portion of 
Cuyahoga River to bridge 1 and east and west 
basins (stage 1 of 1960 act) was completed in 
November 1962. Replacement of city of Cleveland 
highway bridge 33 was initiated in August 1963 
and completed in June 1965. Widening portion of 
Cut 14 in Old River vicinity of bridge 33 was completed 
in June 1965. Deepening of 27- and 28-foot 
areas in east basin and 25-foot deep channel 
through remainder of east outer harbor including 
approach channel to Nicholson Terminal all as 
authorized by 1962 act was initiated in April 1964 
and completed in April 1965. Deepening of 
downstream 1000-foot portion of Old River 
channel extension to 23 feet, as authorized by Section 
107 of 1960 River and Harbor Act, was initiated 
in April 1968 and completed in August 
1968. For disposal of dredged materials a pilot 
study experimental diked disposal area was constructed 
in the East basin and another diked disposal 
area adjacent to and easterly thereof were 
constructed during 1968-1969. Work remaining to 
complete existing project consists of: 1958 
act-completion of preconstruction planning for 
and replacement of bridges 19 and 32, and widening 
Cuyahoga and Old River channels; 1960 
act-stage II consisting of deepening of remainder 
of Cuyahoga River from bridge I to and including 
Old River which will be accomplished with similar 
work authorized by 1958 act; section 107 of 1960 
River and Harbor Act-stage II consisting of 
deepening channel extension to 27 feet when Old 
River channel is deepened and completion of inactive 
portion of the 1946 act, the widening of 
Cuyahoga River at downstream end of Cut 4. 
Costs of existing project were $29,939,040 
(including $616,767 public works funds) for new 
work, $55,145,989 (including $125,000 public 
works funds) for maintenance and $464,903 for 
rehabilitation, a total of $85,549,932. In addition, 
$201,960 of contributed funds were expended for 
maintenance. Of this amount $50,000 were expended 
in fiscal years 1935 and 1936. The balance 
of $151,960 was expended for disposal of permit 
dredgings in diked areas. 
7. CONNEAUT HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth 
of Conneaut River, 73 miles easterly from 
Cleveland, Ohio. (See Lake Survey Chart 33.) 
Previous projects. For details see page 1964, Annual 
Report for 1915. 
Existing project. For description see page 1274 
of Annual Report for 1967. Actual costs for new 
work for completed portion of the project were $7,- 
541,369. Entire project modification authorized by 
1966 act providing for a recreational small boat 
harbor is to be restudied. Estimated cost (1970) of 
this modification is $717,000. For completed work 
non-Federal costs were $200,000 for dockside 
dredging and removal of existing dolphins. 
Estimated non-Federal cost of $2,877,000 (1970) 
includes cash contribution of $717,000 and the 
remainder is for construction of service facilities 
for the 1966 project modification classified as 
deferred for restudy. See Table 32-B for authorizing 
legislation. 
Local cooperation. See page 32-6 of Annual 
Report for 1971 for description of requirements of 
local cooperation for project modification as 
authorized by the River and Harbor Act of 1966, 
which is to be restudied. For other project 
modifications all conditions of local cooperation 
fully complied with. 
Terminal facilities. There are seven piers and 
wharves. Six are privately owned and operated 
and located in inner harbor. Remaining facility is 
city owned on the south side of outer harbor. Six 
terminals have railroad connections and four 
mechanical-handling facilities. (See Port Series 
No. 42, revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and 
condition surveys were done by Government plant 
and hired labor at a cost of $11,880. U.S. hopper 
dredges Lyman and Markham removed 485,808 
cubic yards, bin measure, of shoaled material over 
an area of approximately 490,000 square yards of 
the Conneaut River and outer harbor to project 
depths of 22, 27 and 28 feet, at a cost of $325,441. 
Planning was continued for the diked disposal 
area at a cost of $45,779. 
32-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Condition at end of fiscal year. Existing project 
is 91 percent complete. Under existing project a 
length of 4,445 feet of new west breakwater was 
completed in 1916; old east breakwater, 1,050 feet 
long, was extended shoreward 800 feet (completed 
1911) and lakeward 900 feet (completed 1923). 
The 1,670-foot shore arm to west breakwater was 
completed in 1934. Extension of west breakwater 
830 feet lakeward, east breakwater 925 feet 
lakeward, and removal of lake arm of west 
breakwater were completed in 1935; 642 feet of old 
west breakwater were removed in 1916, and 
remaining 600 feet in 1925. Two piers were constructed 
at mouth of Conneaut River. Removal of 
west pier and 459 feet of east pier were completed 
in 1934. East pier is now 1,008 feet long. A channel 
through outer harbor was deepened to 25 and 26 
feet in 1938. Inner 1,200 feet of west breakwater 
was rebuilt to its original elevation during 1941 to 
1952 and is in fair condition. Repairs to 600 feet of 
west breakwater and 1,200 feet of east breakwater 
were completed in 1964. Deepening city dock approach 
channel to 8 feet initiated in September 
1964 and 1,150-foot long shoreward extension of 
east breakwater initiated in July 1965 were completed 
in November 1965. Removal of 995 feet of 
east pier was initiated in November 1965 and completed 
in December 1965. Deepening inner and 
outer harbor channels as authorized by 1962 River 
and Harbor Act was initiated November 1965 and 
completed July 1967. Work remaining to complete 
project consists of construction of recreational 
small boat harbor as authorized by 1966 River and 
Harbor Act which is to be restudied. At several 
places along remainder of west breakwater and 
along east breakwater, slope stone on lakeside is 
disintegrating and pulling away and deck stone is 
settling. Other harbor structures are generally in 
good condition. Costs of existing project were $7,- 
541,369 (including $1,010,500 public works funds) 
for new work, $4,268,021 for maintenance and 
$651,850 for rehabilitation, a total of $12,461,240. 
8. DUNKIRK HARBOR, N.Y. 
Location. On south shore of Lake Erie, 37 miles 
southwesterly from Buffalo, N.Y. (See Lake 
Survey Chart 32.) 
Previous projects. For details see page 1966 of 
Annual Report for 1915, and page 1604 of Annual 
Report for 1938. 
Existing project. Completed deep draft navigation 
project authorized by River and Harbor Acts 
of March 2, 1827 thru June 30, 1948 provided for 
outer entrance channel with depths of 17 feet in 
earth and 18 feet in rock, with at least a width of 
190 feet just inside harbor structures, flaring to a 
width of 320 feet about 600 feet lakeward thereof, 
and extending to deep water; inner entrance 
channel and basin to a depth of 16 feet, west 
channel limit to be prolongation landward of west 
limit of outer entrance channel to a point about 
635 feet landward of centerline of west pier, thence 
extending to a point about 200 feet west of west 
face of city dock on a line parallel to and 25 feet 
south of face of city dock, thence extending 
eastward to a point about 420 feet east of east face 
of city dock, thence northerly about 270 feet 
meeting a line parallel to and 50 feet from channel 
arm of east breakwater; removal of a rock shoal on 
west side of inner entrance channel to a depth of 
17 feet; pier 1,410 feet in length on west side of entrance 
channel, extending to shore (357.5 feet of 
shore end not maintained); and detached 
breakwater extending eastward from entrance 
channel, 2,814 feet in length. Cost of new work for 
completed project was $429,174, including $11,000 
contributed by local interests and exclusive of 
amounts expended under previous projects. 
Small boat harbor as authorized under Section 
201 of Flood Control Act of 1965 provides for constructing 
a detached rubblemound breakwater, 1,- 
100 feet in length, west of the city dock; constructing 
a shore-connected rubblemound breakwater, 
830 feet in length, extending southeasterly from 
the south end of an existing bulkhead of the 
Niagara Mohawk Power Corporation; dredging an 
east access channel approximately 400 feet long, 
between the east end of the proposed detached 
breakwater and the city dock, 8 feet deep and 100 
feet wide, with suitable widening at the bend; 
dredging a west outer access channel approximately 
800 feet long, between the gap formed 
by the west end of the proposed detached 
breakwater and east end of the proposed shoreconnected 
breakwater, 8 feet deep and 100 feet 
wide, flaring to a width of 800 feet at the outer 
end; dredging a west inner access channel approximately 
500 feet long, from the inner end of 
the proposed west outer access channel to the 
junction with the proposed dock front channel, 6 
feet deep and 120 feet wide, flaring to a width of 
about 700 feet at the junction with the proposed 
dock front channel; dredging a dock front channel 
approximately 1,700 feet long, about 100 feet 
south of and parallel to the main alignment of the 
proposed detached breakwater, 6 feet deep and 
100 feet wide, flaring to a width of 230 feet in the 
westerly 450 feet of channel; and dredging an 
irregular-shaped mooring basin for transient 
craft approximately 900 feet long, between the 
proposed dock front channel and proposed detached 
breakwater, 6 feet deep and 100 feet wide. 
Estimated Federal cost of improvements authorized 
under Section 201 of 1965 Flood Control Act is 
$1,070,000 (Oct. 1975). Non-Federal cost estimate 
of $1,070,000 (Oct. 1975) is cash contribution 
toward first cost of construction. In addition, local 
interests will incur costs of $1,942,000 for construction 
of a public dock, launching ramp, berthing 
32-8

BUFFALO, N.Y., DISTRICT 
areas, spoil retaining dikes, parking areas, access 
roads and other service facilities. See Table 32-B 
for authorizing legislation. 
Local cooperation. Fully complied with for completed 
deep draft navigation project. Local interests 
contributed $11,000. For small boat harbor 
project as authorized under Section 201 of 1965 
Flood Control Act, local interests are required to 
contribute in cash 50 percent of first cost of 
Federal construction of general navigation 
facilities, exclusive of aids to navigation, a contribution 
presently estimated at $1,070,000 to be 
paid either in a lump sum prior to initiation of 
construction, or in installments prior to commencement 
of pertinent work items, in accordance 
with construction schedules as required by the 
Chief of Engineers, final apportionment of cost to 
be made after actual costs have been determined; 
also, provide without cost to United States all 
lands, easements, and rights-of-way required for 
construction and subsequent maintenance of project 
and for aids to navigation upon request of the 
Chief of Engineers, including suitable areas determined 
by Chief of Engineers to be required in the 
general public interest for initial and subsequent 
disposal of spoil and necessary retaining dikes, 
bulkheads, and embankments therefor, or costs of 
such retaining works; establish rules to control 
use, growth, and development of harbor and 
related facilities with understanding that said 
facilities will be open to all on equal terms; hold 
and save United States free from damages due to 
construction and maintenance of project; provide 
and maintain without cost to United States all 
depths in service channels to principal docks and 
berthing areas commensurate with those provided 
in Federal project, and necessary access roads, 
mooring facilities, and parking and service areas, 
including a launching ramp, toilet facilities, and 
an adequate public landing or wharf with provision 
for sale of motor fuel, lubricants, and potable 
water available to all on equal terms; reserve 
spaces within harbor adequate for accommodation 
of transient craft; establish regulations prohibiting 
discharge of pollutants into waters of harbor by 
users thereof, which regulations shall be in accordance 
with applicable laws or regulations of 
Federal, State, and local authorities responsible 
for pollution prevention and control; and accomplish 
without cost to United States relocation 
or alteration of Niagara Mohawk Power Corporation 
cooling water discharge facility as necessary 
to protect environmental conditions of harbor in 
accordance with applicable water quality standards 
or regulations of Federal, State, and local 
authorities. Assurances will be formally requested 
upon completion of Design Memorandum. 
Terminal facilities. Three docks are in harbor, 
one is owned by city, a yacht club dock and a 
privately owned marine service dock. Facilities 
considered adequate for existing commerce. 
Operations and results during fiscal year. New 
work: Preconstruction planning was initiated. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $5,009. U.S. hopper dredges Hoffman 
and Lyman removed 45,315 cubic yards, bin 
measure of shoaled material over an area of approximately 
150,000 square yards of the inner and 
outer channels at a cost of $73,433. Preparation of 
an Environmental Impact Statement and other 
miscellaneous costs amounted to $23,558. Planning 
for a diked disposal area cost $14,000. 
Condition at end of fiscal year. Existing project 
is 31 percent complete. Deep draft navigation 
project was completed in 1951. Project structures 
are generally in good condition. About 800 linear 
feet of lake side of west pier completed in 1921 has 
been reinforced with stone riprap, and repairs to 
additional areas where concrete superstructure 
cracked and settled are necessary. Construction of 
small boat harbor, as authorized under Section 
201 of 1965 Flood Control Act, remains to be done 
to complete the project. Costs of existing project 
were $463,040 for new work and $1,112,502 for 
maintenance, a total of $1,575,542. In addition, 
$11,000 contributed funds expended for new work. 
9. ERIE HARBOR, PA. 
Location. On southerly side of bay formed by 
Presque Isle Peninsula, on south shore of Lake 
Erie, 78 miles westerly from Buffalo, N.Y. (See 
Lake Survey Chart 332.) 
Previous projects. For details see page 1965 of 
Annual Report for 1915 and page 1600 of Annual 
Report for 1938. 
Existing project. For description see pages 1363- 
64 of Annual Report for 1963. Actual costs for new 
work for completed portion of project were $2,860,- 
906. Extension of north pier portion as authorized 
by 1899 act is to be restudied and is excluded from 
foregoing cost. Estimated cost (1955) of this portion 
is $1,071,000. Entire project modification 
authorized by 1945 River and Harbor Act, 
providing for deepening channel and basin, both 
23 feet deep, to Penn Central Company coal docks 
at westerly end of harbor, is classified inactive and 
also excluded from foregoing cost. Estimated cost 
(July 1960) of this modification is $1,837,000. A 
portion of work authorized by 1960 act, deepening 
strips adjacent to north and south piers, is to be 
restudied and is also excluded from foregoing cost. 
Estimated cost (July 1962) of this portion is $78,- 
000. Non-Federal costs for completed work were 
$51,000 for providing ore dock and dredging slip 
adjacent thereto. See Table 32-B for authorizing 
legislation. 
Local cooperation. River and Harbor Act of 1945 
authorized an approach channel 23 feet deep, in- 
32-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
cluding a turning basin, to westerly docks, required 
local interests to give assurances they will 
provide and maintain a coal dumper and slip so 
that full utilization can be made of improvement; 
lower waterworks intake line where necessary; and 
hold the United States free from damages. These 
conditions not complied with and authorized work 
classified inactive. All other conditions are fully 
complied with. 
Terminal facilities. Sixteen piers and wharves, 
of which 12 are privately owned and operated. 
Erie International Marine Terminal No. 1 owned 
by Port Commission, city of Erie, is along main 
waterfront on south side of Presque Isle Bay and 
Coast Guard facilities are on north side. Two 
offshore oil docks are on Lake Erie. Eight terminals 
have railroad connections and six 
mechanical-handling facilities. Facilities are considered 
adequate for existing commerce. (See Port 
Series No. 42, revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $16,926. U.S. hopper dredge 
Lyman removed 325,464 cubic yards, bin measure, 
of shoaled material over one mile of entrance 
channel and 30,000 square yards of harbor basin for 
restoration of project depths of 29 and 28 feet 
respectively at a cost of $236,074. Planning was 
continued for the diked disposal area at a cost of 
$140,657. 
Condition at end of fiscal year. Existing project 
is 49 percent complete. Breakwater and piers were 
completed in 1915. A 3,050-foot section of 
rubblemound protection work on peninsula was 
completed in 1921, 5,281 feet of steel-sheet piling 
protection work with stone facing were completed 
in 1930, and two experimental 300-foot stone 
groins and about 1,385 feet of stone-protection 
work at beach 2 were completed in 1943. Construction 
of 2,750 feet of stone-protection work, just 
north of Kelso groin, was completed in 1944. The 
18-foot harbor basin was deepened in 1900. 
Widening and straightening of entrance channel 
was completed in 1936. Deepening entrance 
channel and approach channel to easterly ore dock 
to 25 feet except for small triangular areas along 
southeasterly and southwesterly limits of approach 
channel, was completed in 1939. The 21- 
foot harbor basin was deepened in 1940. Widening 
approach channel to easterly ore dock was completed 
in August 1958. Deepening entrance 
channel to 29 feet, and approach channel and turning 
basin at easterly docks to 28 feet was completed 
in 1962. Deepening approach channel to 
Erie International Marine Terminal No. 1 to a 
depth of 27 feet in soft material and 28 feet in 
hard material, as authorized by 1962 act was initiated 
in June 1966 and completed in August 
1966. Harbor structures are generally in fair condition. 
Concrete superstructure of north and south 
piers completed in 1909, has disintegrated, 
broken, and dropped in various sections, due to 
timber-crib failure at these sections. In outer 200- 
foot section of south breakwater, slope stone on 
channel side has pulled away and dropped. A 
length of 40 linear feet of south pier and 1,141 
linear feet of north pier was reinforced and 
repaired with steel-sheet piling and concrete. Approximately 
1,400 linear feet of steel-sheet piling 
bulkhead with stone facing adjacent to mainland, 
Presque Isle protection works, constructed in 1930, 
in which stone facing settled was completely 
covered with sandfill as provided in shore protection 
project authorized for Presque Isle Peninsula. 
Work remaining to complete project consists of 
completion of deepening strips adjacent to north 
and south piers as authorized by 1960 act, which is 
to be restudied; deepening channel and basin at 
westerly end of harbor as authorized by 1945 act 
which is considered inactive and conditional extension 
of north pier as authorized by 1899 act 
which is to be restudied. Costs of existing project 
were $2,860,906 for new work, $6,079,351 for 
maintenance, and $1,154 for rehabilitation, total 
of $8,941,411. In addition, $154,500 expended from 
contributed funds for maintenance. 
10. FAIRPORT HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Grand River, 33 miles easterly from Cleveland, 
Ohio. (See Lake Survey Chart 346.) 
Previous projects. For details see page 1963 of 
Annual Report for 1915, and page 1590 of Annual 
Report for 1938. 
Existing project. For description see page 1526 
of Annual Report for 1962. Actual costs for new 
work for completed portion of project were $2,590,- 
671. Entire project modification authorized by 
1960 River and Harbor Act, providing for deepening 
lake approach channel, 800-foot wide channel 
through outer harbor and channel in Grand River, 
and enlargement of turning basin, is considered 
inactive and is excluded from foregoing cost. 
Estimated cost (1963) of this modification is $3,- 
170,000. For completed work non-Federal costs 
were $101,000 for bulkheads and dockside dredging. 
Estimated non-Federal cost of $3,821,000 
(1963) is for lands, relocations, utility changes, 
dockside dredging and dock and bulkhead 
modifications for the inactive 1960 project 
modification. See Table 32-B for authorizing 
legislation. 
Local cooperation. River and Harbor Act of 1927 
required local interests to contribute $304,000 
toward cost of extending breakwater 4,000 feet, 
and to dredge approach channel to their proposed 
terminal at their own expense. River and Harbor 
Act of July 3, 1930, waived the condition requiring 
32-10

BUFFALO, N.Y., DISTRICT 
local interests to contribute to cost of breakwater 
extension. Proposed terminal has not been built 
nor required dredging been done. River and Harbor 
Act of 1960 requires local interests make all 
changes in docks, bulkheads and other structures; 
provide and maintain depths between new 
channel limits and terminal facilities; accomplish 
utility alterations; furnish lands and rights-of-way 
for construction; and hold the United States free 
from damages. District Engineer requested Board 
of County Commissioners, Lake County, to furnish 
assurances by January 1, 1963. Assurances 
not received and authorized work classified inactive. 
All other conditions are fully coffiplied with. 
Terminal facilities. Sixteen piers and wharves, 
all along banks of Grand River. One facility is 
onwed by Coast Guard. Nine terminals have 
railroad connections and ten mechanical-handling 
facilities. Facilities considered adequate for existing 
commerce. (See Port Series No. 42, revised 
1972, Corps of Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $13,780. U.S. hopper dredge 
Lyman removed 173,404 cubic yards, bin measure, 
and U.S. hopper dredge Markham removed 230,- 
117 cubic yards, bin measure of shoaled material 
from about one mile of Grand River Channel and 
turning basin and approximately 270,000 square 
yards of the lake approach channel and outer harbor 
for restoration of depths of 25, 24, 21 and 18 
feet at a cost of $437,072. Repairs to approximately 
50 linear feet of the west breakwater by U.S. 
derrick boat Tonawanda cost $10,942. Planning 
was continued for the diked disposal area at a cost 
of $308,891. 
Condition at end of fiscal year. Existing project. 
is about 46 percent complete. Lengths of 400 and 
275 linear feet of east pier were repaired with steel 
sheet piling and sandfilled, in 1949 and 1958, 
respectively. Other end of structure requires extensive 
repairs. River entrance was improved by 
construction of an east pier completed in 1904, 
and removal of old west pier and construction of 
bulkhead, completed in 1939. East breakwater was 
completed in 1931 and west breakwater in 1935. 
River channel was deepened to 21 and 24 feet and 
turning basin to 18 feet in 1939. Outer harbor was 
deepened to 25 feet and river channel widened at 
its mouth in 1940. Deepening 8-foot channel in 
Grand River at upper end of and adjacent to west 
side of 21-foot project channel, was completed in 
1956. Harbor structures require repairs. Concrete 
cap of several cells of cellular section of west 
breakwater requires replacement. At several 
places along remainder of west breakwater the 
slope stone has disintegrated and settled. The 
6,700-foot long, rubblemound east breakwater, 
built in 1932 is in poor condition throughout most 
of its entire length. At several locations of the 
structure, totaling approximately 2,000 linear feet, 
slope stone has disintegrated and settled and core 
stone washed out, leaving large areas of structure 
only slightly above low-water datum. Work 
remaining to complete project consists of completion 
of preconstruction planning for and deepening 
lake approach channel, 800-foot wide channel 
through outer harbor and channel in Grand River, 
and enlargement of turning basin, all as authorized 
by 1960 act which is considered inactive. Costs 
of existing project were $2,590,671 (including 
$187,772 public work funds) for new work, and $6,- 
877, 102 maintenance, a total of $9,467,773. 
11, GREAT SODUS BAY HARBOR, N.Y. 
Location. On Sodus Bay, which is a nearly 
landlocked indentation on south shore of Lake Ontario, 
29 miles westerly from Oswego, N.Y. (See 
Lake Survey Chart 234.) 
Previous projects. For details see page 1972 of 
Annual Report for 1915 and page 1526 of Annual 
Report for 1938. 
Existing project. For description, see page 1380 
of Annual Report for 1963. Actual costs of new 
work for completed portion of project were $249,- 
187. Improvements authorized by 1962 act, consisting 
of deepening lake approach channel, entrance 
channel and inner approach channel are 
classified inactive. Estimated cost (1965) of this 
portion is $900,000. For completed work, costs incurred 
by local interests are not available. 
Estimated non-Federal cost (1965) for work 
authorized by 1962 act is $380,000 for tuning basin 
and dockside dredging. See Table 32-B for 
authorizing legislation. 
Local cooperation. River and Harbor Act of October 
23, 1962, requires local interests provide and 
maintain a 22-foot depth in turning basin at coal 
dock and in berthing areas at coal dock; provide 
adequate coal-loading facilities; and hold the 
United States free from damages. On December 5, 
1962, the District Engineer requested assurances 
be furnished. A resolution by town of Sodus furnishing 
assurances was reviewed and found to be 
incomplete and was returned November 19, 1963. 
Assurances have not been received and authorized 
work has been classified inactive. All other conditions 
fully complied with. 
Terminal facilities. One fish dock which is 
private, a yacht club dock and several other 
privately owned servicing and storage docks are 
for recreational and other small craft. Terminals 
are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $4,787. Repairs to a portion of the 
32-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
west pier were completed by contract at a cost of 
$250,876. Preparation of an Environmental Impact 
Statement cost $26,002. 
Condition at end of fiscal year. Existing project 
is 22 percent complete. Structures are generally in 
good condition except for the east breakwater concrete 
cap where several sections have been displaced 
and the structure breached. 500 linear feet 
of west pier were reinforced with steel-sheet piling 
and concrete in 1958. Lakeward end of west pier 
(550 feet long and 880 linear feet of east pier) were 
reinforced with steel-sheet piling and concrete in 
1962 and 1963 under major rehabilitation 
program. Repairs to 300 linear feet of east pier 
were made during FY 1975. Work remaining to 
complete project consists of deepening lake approach 
channel, entrance channel and inner approach 
channel as authorized by 1962 act, which is 
classified inactive. Costs of existing project were 
$249,187 for new work, $2,046,360 for 
maintenance, and $713,544 for rehabilitation, a 
total of $3,009,091. 
12. HURON HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Huron River, 47 miles westerly from Cleveland, 
Ohio. (See Lake Survey Chart 363.) 
Previous project. For details, see page 1961 of 
Annual Report for 1915, and page 1576 of Annual 
Report for 1938. 
Existing project. For description see page 1347 
of Annual Report for 1963. Estimated cost of new 
work is $2,620,000 (Oct. 1975). Construction of 
detached breakwater, as authorized by the 1962 
act is to be restudied and is excluded from the 
foregoing cost estimate. Estimated cost of the construction 
of breakwater is $12,970,000 (July 1972). 
Estimated non-Federal costs of $163,000 (Oct. 
1975) are for required lands, removal of structures, 
utility changes and dredging slips, all for the 1962 
act. Non-Federal costs for fully completed work 
are not available. See Table 32-B for authorizing 
legislation. 
Local cooperation. River and Harbor Act of 1962 
requires local interests to: dredge areas between 
Federal improvement and terminal facilities; 
regulate moorings; furnish lands and rights-of-way 
for construction; and hold the United States free 
from damages. Formal assurances were requested 
from city of Huron in December 1962. Subsequently, 
the city of Huron requested modifications 
to project limits which were approved in May 
1964. On July 7, 1964, City Manager of Huron was 
advised of approved deviation. On April 12, 1967 
City of Huron advised that the assurances of local 
cooperation can be furnished. By letter dated 
April 13, 1967, the city was informed that 
assurances will be requested upon completion of 
planning. The city of Huron reaffirmed its' 
willingness to cooperate in the project modification 
by letter dated February 15, 1974. All other 
conditions fully complied with. 
Terminal facilities. Six privately owned wharves 
and docks, one along left bank of Huron River and 
remainder along right bank. Four terminals have 
railroad connections and four mechanicalhandling 
facilities. Facilities are regarded as adequate 
for existing commerce. (See Port Series No. 
42, revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. New 
work: Preconstruction planning was continued by 
hired labor. Maintenance: Miscellaneous inspection 
services and condition surveys by Government 
plant and hired labor.cost $10,849. U.S. 
hopper dredge Hoffman removed 143,679 cubic 
yards, bin measure, of shoaled material over approximately 
40,000 square yards of entrance 
channel for restoration of project depth of 25 feet 
at a cost of $114,015. Preparation of an Environmental 
Impact Statement cost $11,136. 
Construction of a diked disposal facility was continued 
at a cost of $3,226,589. 
Condition at end of fiscal year. Existing project 
is 8 percent complete. Harbor structures are 
generally in fair condition. Structures are generally 
in good condition except for the inner 800 feet of 
the west pier where the concrete superstructure 
has cracked and settled. Repairs to 400 linear feet 
of west pier under minor rehabilitation program 
were initiated in August and completed in 
December 1963. Completion of preconstruction 
planning for and deepening lake approach, entrance 
and river channels, and enlargement of turning 
basin as authorized by 1962 River and Harbor 
Act remain to complete project. Construction 
of the detached breakwater authorized by 1962 
River and Harbor Act, has been classified deferred 
for restudy. Costs of existing project were $1,182,- 
112 (including $561,262 public works funds) for 
new work, $6,316,055 for maintenance, and $247,- 
030 for rehabilitation, total of $7,745,197. 
13. IRONDEQUOIT BAY, N.Y. 
Location. On south shore of Lake Ontario, 4 
miles east of Rochester, N.Y. at mouth of Genesee 
River,. Monroe County, N.Y. (See Lake Survey 
Charts 2, 23 and 238.) 
Existing project. Provides for entrance channel 
8 feet deep, an inner channel, access channel and 
mooring area, all 6 feet deep, parallel jetties, 
replacement of existing railroad bridge and 
removal of existing highway bridge. For detailed 
description of features see page 977 of Annual 
Report for 1969. Estimated Federal cost for new 
work is $4,320,000 (Oct. 1975). Estimated non- 
Federal cost for new work is $1,804,000 (Oct. 1975) 
including cash contribution of $1,430,000 and 
remainder for lands and construction of a wharf. 
32-12

BUFFALO, N.Y., DISTRICT 
Existing project was authorized by 1958 River and 
Harbor Act (H. Doc. 332, 84th Cong. 2nd sess.). 
Local cooperation. Assurances were furnished 
and accepted by the District Engineer on August 
12, 1959. The New York State Legislature has 
passed a bill in 1971 prohibiting the closing of the 
highway bridge spanning the entrance to the Bay 
until completion of a new expressway, and after 
that, until further certification by the State 
Transportation Department. This bill in effect 
nullifies that portion of the State's assurances for 
the project concerning relocation of roads and 
utilities. By letter dated May 1, 1974, County of 
Monroe confirmed the amendment of the highway 
law striking the provision requiring that closure of 
Route 18 at the outlet be postponed until completion 
of the Irondequoit Wayne County Expressway. 
Terminal facilities. Facilities consist of private 
docks for recreational craft and privately owned 
servicing and storage handling facilities for 
recreational and other small craft. 
Operations and results during fiscal year. 
Miscellaneous engineering services were performed 
by hired labor. 
Condition at end of fiscal year. Construction has 
not been initiated. The work remaining to be done 
consists of completion of preconstruction planning 
for and construction of the project. 
14. LITTLE SODUS BAY HARBOR, N.Y. 
Location. Little Sodus Bay, on south shore of 
Lake Ontario, 15 miles west of Oswego, N.Y. (See 
Lake Survey Chart 22.) 
Previous projects. For details see page 1973 of 
Annual Report for 1915, and page 1628 of Annual 
Report for 1938. 
Existing project. For description see page 1378 
of Annual Report for 1958. New work for completed 
project cost $69,066. Non-Federal costs of 
$6,000 were incurred for channel dredging. 
Local cooperation. None required. 
Terminal facilities. Docks for small recreational 
craft and one passenger tour boat, all are private. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $5,233. Repairs to a portion of the 
east pier were completed by contract at a cost of 
$88,548. U.S. hopper dredge Lyman removed 19,- 
155 cubic yards, bin measure, of shoaled material 
from about 40,000 square yards of the entrance 
channel at a cost of $52,675. Preparation of an Environmental 
Impact Statement cost $26,657. 
Condition at end of fiscal year. Existing project 
was completed in 1906. Structures are in good condition 
except for a 500-foot section of west pier 
and the entire east breakwater. Repairs to 625 
linear feet of the east pier were initiated in 1972 
and completed in July 1973. A 300-foot section of 
east pier and a 1,127-foot section of west pier were 
repaired during period September 1965 to July 
1967 under major rehabilitation program. Costs of 
completed project were $69,066 for new work, $2,- 
491,529 for maintenance, and $742,822 for 
rehabilitation, a total of $3,303,417. 
15. LORAIN HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Black River, 28 miles westerly from Cleveland, 
Ohio. (See Lake Survey Chart 357.) 
Previous projects. For details, see page 1961 of 
Annual Report for 1915, and page 1580 of Annual 
Report for 1938. 
Existing project. For description see pages 1319- 
22 of Annual Report for 1966. Estimated Federal 
cost of new work is $25,446,000 (Oct. 1975). A portion 
of work authorized by 1960 act, dredging of 
15- to 25-foot wide strips adjacent to the U.S. East 
and West piers is deferred for restudy and estimated 
cost of $60,200 (July 1966) is excluded 
from foregoing cost estimate. Total non-Federal 
cost estimate is $8,103,000 (Oct. 1975) including 
$3,000 contributed by local interests toward construction 
of west breakwater shorearm. For work 
authorized by 1960 act, non-Federal costs are estimated 
to be $8,100,000 for lands, relocations of 
utilities, modifications of existing dock and 
bulkheads, construction of new bulkheads and 
dockside dredging. For work authorized by 1965 
act local interests must make a cash contribution 
presently estimated at $45,000. See Table 32-B for 
authorizing legislation. 
Local cooperation. For work authorized by 1965 
act, local interests must contribute $45,000. Pending 
finalization of planning for bank stabilization 
works, this contribution not received to date. For 
completed work, local interests contributed $3,- 
000. All other conditions fully complied with. 
Terminal facilities. There are 23 piers and 
wharves, of which three are on outer harbor and 
remainder are along banks of Black River. Two are 
owned by the city. Eight terminals have railroad 
connections and 15 mechanical-handling facilities. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 42, revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. New 
work-1960 project modification: Contract 
operations for widening of Black River at Cut 2 in 
the vicinity of Norfolk and Western Railway 
Bridge were initiated in July 1974 and completed 
in August 1974. Replacement of the superstructure 
of the Norfolk and Western Railway Bridge, which 
was initiated in August 1972 was completed in 
April 1975. Maintenance: Miscellaneous inspec- 
32-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
tion surveys and condition surveys by Government 
plant and hired labor cost $11,216. U.S. hopper 
dredge Hoffman removed 136,912 cubic yards, bin 
measure, of shoaled material over approximately 
one mile of Black River Channel and turning 
basin and 90,000 square yards of the approach 
channel and outer harbor for restoration of 29-, 28-, 
27-, 25-, 24-, and 21-foot project depths at a cost 
of $165,982. Repairs to the west breakwater by 
Government plant and hired labor cost $192,156. 
Planning was continued for the diked disposal 
area at a cost of $353,101. 
Condition at end of fiscal year. Existing project 
is about 79 percent complete. An outer harbor as 
provided by constructing breakwaters and 
pierheads completed in 1915, except extension of 
west breakwater to shore, which was completed in 
1921. A channel through outer harbor to entrance 
to Black River was deepened to 25 feet in 1937, 
also a channel 16 feet deep to municipal pier was 
provided in 1936. Deepening outer harbor to 25 
feet was completed in 1946. Entrance to river was 
improved by construction of parallel piers completed 
in 1909. Widening of two bends in river was 
completed in 1934. River channel was deepened to 
24 feet and upstream turning basin opposite 
National Tube Co. dock was deepened to 17 feet 
in 1937 and 1938. Upstream turning basin was 
widened in 1944. Deepening downstream basin in 
bend of Black River immediately upstream of 
Baltimore & Ohio Railroad coal dock to 20 feet 
was completed in 1951. Deepening upper and 
lower portion of Black River (above and below 21st 
Street Bridge) to 27 feet, entrance channel 
between piers 2,200 feet long to 28 feet, an 800-foot 
wide lake approach channel to 29 feet, an 
irregularly shaped area in west outer harbor to 25 
feet and enlarging and deepening turning basin to 
21 feet, were initiated in May 1962 and completed 
in November 1963. Deepening remainder of outer 
harbor, triangular area vicinity of East pier, to 
project depth 28 feet was initiated in April 1966 
and completed in June 1966. Construction of new 
east cellular steel sheet pile breakwater shorearm, 
2,323 feet long with a 134-foot stone shore connection, 
was initiated in January 1963 and completed 
in October 1963. Construction of new cellular steel 
sheet pile outer detached breakwater was initiated 
in August 1964 and completed in June 1966. 
Removal of 250 feet of the lakeward end of the 
East breakwater and construction of a new pierhead 
was completed in November 1965. Removal 
of shoals in lake approach channel was initiated in 
September 1966 and completed in July 1967. Partial 
channel widening and bank stabilization at 
cut 1 was initiated in September 1968 and completed 
in September 1969. Replacement of substructure 
of the Norfolk and Western Railway 
company bridge was initiated in February 1971 
and completed in November 1972. Replacement of 
the superstructure was initiated in August 1972 
and completed in April 1975. Preauthorization 
studies for construction of small boat harbor as 
authorized by the Chief of Engineers on June 4, 
1968 under authority of Section 107 of the 1960 
River and Harbor Act were terminated in 
February 1975. Local interests have indicated that 
there is no further interest in the construction of 
small boat harbor at the study location. Widening 
of Black River at Cut 2 was initiated in July 1974 
and completed in August 1974. Protection works 
are generally in fair condition. Shoreward section 
of west breakwater, completed in 1921, has disintegrated 
and settled and in places is below lowwater 
datum. At various locations on lake face of 
lakeward section of west .breakwater, stones 
shifted leaving holes in the wall, and in many sections 
of east breakwater stones above water have 
deteriorated and shifted. Severe cracks and shifting 
have developed in superstructure of west 
breakwater pierhead. East pier, completed in 1905 
was reduced in length from 1,875 feet to 880 feet in 
November 1964 by removal of lakeward 995 feet. 
Remainder of East Pier is in various stages of disrepair 
where concrete superstructure supported by 
timber cribs has cracked and settled. Work 
remaining to complete project consists of widening 
remaining portion at bends in river channel, including 
construction of bank stabilization works at 
cut I; dredging strips adjacent to east and west 
piers (deferred for restudy); all as authorized by 
1960 act and modified by 1965 act. Costs of existing 
project were $20,100,238 (including $165,000 
public works funds) for new work and $5,754,382 
(including $76,300 public works funds) for 
maintenance, a total of $25,854,620. 
16. OAK ORCHARD HARBOR, N.Y. 
Location. On south shore of Lake Ontario at 
mouth of Oak Orchard Creek, 33 miles westerly of 
Rochester, N.Y. (See Lake Survey Chart 24). 
Previous project. For details see page 628 of Annual 
Report for 1905. 
Existing project. Provides for: (a) detached 
breakwater about 550 feet long, 1,000 feet north of 
and parallel to shore; (b) two parallel jetties about 
220 feet apart between centerlines, west jetty 900 
feet long and east jetty 670 feet long; (c) concrete 
walkway and guard railing on the top of both jetties; 
(d) lake approach channel 10 feet deep from 
that depth contour in lake near each end of 
detached breakwater to the outer ends of the jetties. 
Due to extremely hard material located in the 
east approach channel, a depth of 7 feet was 
authorized. The west approach channel was 
dredged to a depth of 10 feet. This dredging includes 
removal of the outer ends of the remains of 
the old jetties that extend beyond the alinements 
of the new jetties; (e) entrance channel 1,175 feet 
32-14

BUFFALO, N.Y., DISTRICT 
long, 10 feet deep; (f) harbor basin 675 feet long, 
200 to 240 feet wide, 8 feet deep. Estimated 
Federal cost for new work is $1,330,000 (July 
1971). Estimated non-Federal cost for new work is 
$270,000 (July 1971) including cash contribution 
of $170,700 and $24,500 for recreational facilities 
and remainder for lands and construction 
of wharf. Existing project was authorized by the 
1945 River and Harbor Act (H. Doc. 446, 78th 
Cong., 2nd sess.). 
Local cooperation. Assurances were furnished 
and accepted by the District Engineer on 5 
September 1967. Local interests have furnished 
presently estimated cash contribution of $198,200. 
Terminal facilities. There is no commercial 
navigation at Oak Orchard Harbor. Terminal 
facilities consist of private docks for recreational 
craft. 
Operations and results during fiscal year. New 
work: Contract operations initiated in May 1974 
were continued. 
Condition at end of fiscal year. Contract 
operations initiated in May 1974 are 82 percent 
completed. Construction of remainder of existing 
project remains to be done to complete the project. 
17. OSWEGO HARBOR, N.Y. 
Location. On south shore of Lake Ontario, at 
mouth of Oswego River, 59 miles easterly from 
Rochester, N.Y. (See Lake Survey Chart 225.) 
Previous projects. For details see page 1973 of 
Annual Report for 1915, and page 1630 of Annual 
Report for 1938. 
Existing project. For description see pages 1383- 
84 of Annual Report for 1963. Completed portion 
of project cost $7,242,039 and non-Federal costs 
for completed work were $4,440,000 for lands, 
dockside dredging, construction of terminal, 
wharves and cargo handling facilities. Deepening a 
200-foot wide strip along harbor line east of mouth 
of Oswego River, remaining feature of work 
authorized by the 1930 act, and deepening to 22 
feet a 150-foot wide strip along harbor line in west 
outer harbor, remaining feature of work authorized 
by 1940 act, are classified as inactive. 
Estimated Federal costs for this work are $246,000 
(July 1957) and $2,419,000 (July 1966) respectively, 
and estimated non-Federal costs are $500,000 
(July 1966) for dockside dredging for work 
authorized by 1940 act. See Table 32-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Seven piers and wharves in 
harbor and along river channel. In addition, Port 
of Oswego Authority owns two public terminals, 
one of which is west of river and includes a grain 
elevator and warehouse for miscellaneous freight. 
Other terminal is east of river and used for handling 
aluminum and general cargo. A dock owned by 
the State Naval Militia is private. State of New 
York owns a river terminal used for mooring 
vessels. City of Oswego owns shore facilities for 
recreational craft. Facilities considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labot cost $10,813. U.S. hopper dredge 
Lyman removed 100,286 cubic yards, bin measure 
of shoaled material over an area of approximately 
85,000 square yards of the outer harbor, lake approach 
and river channel to project depths of 21, 
24 and 25 feet at a cost of $92,080. U.S. derrick 
boat Ohio repaired approximately 300 linear feet 
of the west breakwater at a cost of $125,062. 
Preparation of an Environmental Impact Statement 
cost $30,295. Planning was continued for the 
diked disposal area at a cost of $204,997. 
Condition at end of fiscal year. Existing project 
is 73 percent complete. Outer west breakwater was 
completed in 1882, and originally 6,032 feet long 
with a 119-foot gap near westerly end, but was 
reduced to 4,359 feet in 1931, and gap was closed 
in 1942. West arrowhead breakwater was completed 
in 1931, and east arrowhead breakwater in 
1932. Old lighthouse pier, a part of west inner 
breakwater, and upper and lower islands in 
Oswego River, were removed in 1931. A depth of 
21 feet was obtained in Oswego River to within 50 
feet of harbor line and in outer harbor east of Erie- 
Lackawanna coal dock, except a strip about 200 
feet wide along harbor line east of river mouth, in 
1932. Channel in Oswego River was widened to 
harbor lines in 1937. A channel, 16 feet deep and 
100 feet wide, with a turning basin at its westerly 
end, was dredged in 1932 in outer harbor west of 
Erie-Lackawanna coal dock. Channel was widened 
to 250 feet and deepened to 21 feet below lowwater 
datum in 1948. Removal of shoals to 25 feet 
in approach to entrance channel was completed in 
1957. Contract for construction of 850-foot long 
detached breakwater at harbor entrance was initiated 
in May 1957 and completed June 1960. 
Deepening lake approach channel to 27 feet, 800- 
foot wide outer harbor channel including harbor 
turning basin to 25 feet and 1,600 feet of lower 
river channel to 24 feet, all as authorized by 1962 
act, was initiated in June 1965 and completed in 
November 1965. Breakwaters are generally in fair 
condition except that slope stone in portions of 
west arrowhead breakwater has disintegrated and 
settled and core stone in a 1,500-foot section of 
west arrowhead breakwater has settled in many 
places. Approximately 1,900 linear feet of 
deteriorated sections of outer west breakwater 
were repaired under minor rehabilitation program 
in 1962. Completion of inactive portions remains 
32-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
to be done to complete project. Costs of existing 
project were $7,242,039 for new work, $2,767,833 
for maintenance, and $307,590 for rehabilitation, 
total of $10,317,462. 
18. ROCHESTER HARBOR, N.Y. 
Location. On south shore of Lake Ontario, at 
mouth of Genesee River, 59 miles westerly from 
Oswego, N.Y. (See Lake Survey Chart 238.) 
Previous project. For details see page 1471 of 
Annual Report for 1915, and page 1623 of Annual 
Report for 1938. 
Existing project. For description see page 1556 
of Annual Report for 1962. Actual cost for new 
work for completed project is $21,191,514. Non- 
Federal costs are estimated at $2,260,000, all for 
1960 act, for lands, relocation of submarine cable 
crossing, relocations of small docks and 
boathouses, dockside dredging, structure 
modifications, and replacement of Baltimore & 
Ohio coal loader. See Table 32-B for authorizing 
legislation. 
Local cooperation. Complied with except provision 
for replacement of coal loading facility as required 
by River and Harbor Act of July 14, 1960. 
Terminal facilities. Rochester-Monroe County 
Port Authority owns a terminal facility at mouth 
of Genesee River. Two privately owned terminals 
are at upper end of channel. Two yacht club docks 
and several privately owned servicing and storage 
docks are for recreational and other small craft. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $4,373. U.S. hopper dredge 
Lyman removed 662,211 cubic yards, bin measure, 
of shoaled material over entire area of entrance 
channel and turning basin and about two miles of 
Genesee River Channel for restoration of improved 
depths of 21, 23, and 24 feet at a cost of $508,292. 
Planning for repairs to the west pier, by contract, 
cost $8,170. Planning was continued for the diked 
disposal area at a cost of $345,050. 
Condition at end of fiscal year. Existing project 
is completed. A length of 1,265 linear feet of west 
pier was reinforced with steel-sheet piling and 
concrete. An additional 1,080 feet of west pier and 
500 linear feet of the east pier is failing, the cribfilling 
stone has escaped and concrete is cracked. 
A length of 550 linear feet of east pier was reinforced 
and repaired with steel-sheet piling and 
concrete during 1954 and 1955 and a 700-foot section 
was repaired in 1971. Present channel was 
completed in 1935. Stage I of work authorized by 
1960 act, consisting of deepening lake approach, 
entrance channel, and lower turning basin, was initiated 
in May and completed August 1962. Stage 
II of work authorized by 1960 act, consisting of 
deepening river channel, upper turning basin, and 
construction of two steel sheet pile cell dolphins, 
was initiated in October 1962 and completed in 
December 1963. Channel is unstable and requires 
annual dredging to maintain adequate depth. 
Costs of existing project were $2,191,514 
(including $56,806 emergency relief funds) for new 
work, and $6,002,826 (including $478 emergency 
relief funds) for maintenance, a total of $8,194,- 
340. 
19. ROCKY RIVER HARBOR, OHIO 
Location. At mouth of Rocky River which empties 
into Lake Erie, 7 miles westerly from 
Cleveland, Ohio. (See Lake Survey Chart 35.) 
Existing project. For description see page 1329 
of Annual Report for 1966. Federal cost for completed 
project was $343,494 and non-Federal cost 
was a cash contribution of $249,346. See Table 32- 
B for authorizing legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $249,346 for new work. 
Terminal facilities. There is no commercial 
navigation at Rocky River. Terminal facilities consist 
of private docks for recreational craft. One 
public dock is owned by city of Lakewood. 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and project condition surveys by Government 
plant and hired labor cost $398. Preparation of an 
Environmental Impact Statement cost $22,602. 
Planning for diked disposal area cost $9,900. 
Condition at end of fiscal year. Existing project 
is completed. East pier, rubblemound construction, 
is generally in fair condition, except for a section 
200 feet long which is badly deteriorated. The 
project modification authorized by 1965 River and 
Harbor Act was selected by the Secretary of the 
Army for inclusion in the Small Authorized Projects 
program. Realignment and extension of 
channel and construction of an anchorage basin, 
as authorized by 1965 act, were initiated in August 
1968 and completed in December 1968. 
Costs of existing project were $343,494 for new 
work and $150,858 for maintenance, a total of 
$494,352. In addition, $249,346 contributed funds 
were expended for new work. 
20. SANDUSKY HARBOR, OHIO 
Location. On south shore of Lake Erie, in 
southeasterly portion of Sandusky Bay, 50 miles 
westerly from Cleveland, Ohio. (See Lake Survey 
Chart 365.) 
Previous projects. For details see page 1960 of 
Annual Report for 1915, and page 1574 of Annual 
32-16

BUFFALO, N.Y., DISTRICT 
Report for 1938. 
Existing project. For description see pages 1511- 
12 of Annual Report for 1962. Actual costs for new 
work for completed project were $6,250,121, excluding 
$325,000 contributed by local interests. 
Non-Federal costs for completed project are estimated 
at $675,000 including $325,000 cash contribution 
and remainder of $350,000 is for dockside 
dredging adjacent to deepened channels authorized 
by 1960 act. See Table 32-B for authorizing 
legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $325,000 for new work. 
Terminal facilities. Fourteen piers and wharves, 
three at west end of harbor and remainder along 
dock channel. One is a base for State-owned fish 
research and patrol boats. One publicly owned 
and six privately owned are used for mooring 
fishing boats and recreational craft and for ferry 
service. Five terminals have railroad connections 
and five mechanical-handling facilities. Facilities 
are considered adequate for existing commerce. 
(See Port Series No. 42, revised 1972, Corps of 
Engineers.) 
Operations and results during fiscal year. 
Maintenance: Miscellaneous inspection services 
and condition surveys by Government plant and 
hired labor cost $10,835. U.S. hopper dredges 
Markham and Hoffman removed 89,963 and 163,- 
151 cubic yards, bin measure, respectively, of 
shoaled material aver approximately 200,000 
square yards of the Bay, Dock, Straight and 
Moseley Channels for restoration of project depth 
of 26, 25, 24, 22 and 21 feet at a cost of $219,412. 
Planning was continued for the diked disposal 
area at a cost of $43,185. 
Condition at end of fiscal year. Existing project 
is complete. Harbor structures are generally in 
good condition except the inner 2,000 linear feet of 
the east jetty protection works, completed in 1922, 
paralleling outer harbor entrance channel has subsided 
and in many places is barely above low water 
datum. The easterly 1,400 linear feet of rock dike 
paralleling the dock channel were rebuilt in 1956. 
In 1963, 500 linear feet of remaining 2,355 linear 
feet, westerly portion, of dike were removed. 
Deepening Moseley, Straight, and Bay Channel, 
deepening and enlarging turning basin, all as 
authorized by 1960 act were initiated in June 1962 
and completed in September 1965. Costs of completed 
existing project were $6,250,121 (including 
$599,500 public work funds) for new work, $5,590,- 
445 for maintenance, and $675,606 for rehabilitation, 
a total of $12,516,172. In addition, $325,000 
expended from contributed funds for new work. 
21. VERMILION HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth 
of Vermilion River, 37 miles westerly from 
Cleveland, Ohio. (See Lake Survey Chart 35.) 
Existing project. Provides for: (a) two parallel 
piers 125 feet apart extending from the shore at 
the mouth of the river to the 10-foot depth in lake. 
The east pier 458.5 feet long and the west pier 1,- 
333.5 feet long; (b) channel 100 feet wide and 12 
feet deep between the piers and to deep water in 
the lake; (c) new outer harbor entrance consisting 
of a cellular steel sheet pile breakwater located 
about 300 feet north of the outer end of the east 
pier. The "T-type" breakwater will have an 
overall length of 864 feet and a crest height of 10 
feet; (d) dual lake approach channels in the outer 
harbor. A 250-foot wide easterly lake approach 
channel 12 feet deep from the 12-foot contour 
lakeward of the detached breakwater to about the 
outer end of the existing east pier. A westerly lake 
approach channel maintained to 8 feet, varying in 
width from 150 feet to 225 feet, extending from the 
lake to the 12-foot easterly lake approach channel, 
(e) extension of the channel at a depth of 8 feet in 
the river from a point near the south shore of the 
Ontario Lagoon to the Liberty Street Bridge, the 
extension to be 100 feet wide for about 1,800 feet, 
thence narrowing to 80 feet in 100 feet and thence 
80 feet wide for approximately 350 feet to the 
bridge. Actual Federal cost for the completed existing 
project was $1,156,118. Estimated non- 
Federal cost for new work is $754,679 including 
cash contribution of $740,679 and remainder for 
relocation of submarine cable and construction of 
public wharf. See Table 32-B for authorizing 
legislation. 
Local cooperation. Fully complied with. Local 
interests contributed $740,679. 
Terminal facilities. Fish is only item of commerce 
regularly handled at Vermilion. There are 
no dock facilities being used for handling other 
commodities. Considerable recreational smallboat 
activity exists and many private docks are 
available for basing, storing, repairing and servicing 
these craft. 
Operations and results during fiscal year. 
New work: Finalization of costs was accomplished. 
Maintenance: Miscellaneous inspection and condition 
surveys by Government plant and hired 
labor cost $4,995. Dredging in project channels 
was accomplished with rented equipment at a cost 
of $14,717. U.S. derrick boat Tonawanda repaired 
approximately 100 linear feet of the east pier at a 
cost of $37,357. Preparation of an Environmental 
Impact Statement cost $22,951. 
Condition at end of fiscal year. Existing project 
is complete. Repairs to piers under minor 
rehabilitation program were initiated in June and 
completed in October 1964. Contract operations 
consisting of new detached breakwater, new 
channel and extension of river channel all as 
32-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
authorized by 1958 act, were initiated on June 11, 
1973 and completed May 24, 1974. Costs of existing 
project were $1,156,118 for new work, $314,- 
263 for maintenance, and $139,775 for rehabilitation, 
a total of $1,610,156. In addition, $740,679 
expended from contributed funds for new work. 
22. WILSON HARBOR, N.Y. 
Location. At mouth of east branch of Twelve 
Mile Creek, which enters Lake Ontario 12 miles 
easterly of mouth of Niagara River, and 67 miles 
westerly of Rochester Harbor, N.Y. (See Lake 
Survey Chart 25). 
Previous project. For details see page 2395 of 
Annual Report for 1889, and page 628 of Annual 
Report for 1905. 
Existing project. Provides for: (a) restoration of 
east and west parallel piers which were originally 
850 and 832 feet long, respectively; (b) entrance 
channel 80 feet wide and 8 feet deep; (c) extension 
of entrance channel approximately 300 feet from 
the inner end of existing channel to a limit opposite 
the lower end of Wintergreen Island, and; 
(d) a channel approximately 3,800 feet long 
through Tuscarora Bay, 6 feet deep with basic 
width of 100 feet, the upper 360 feet of the channel 
narrowing to 80 feet, suitably widened at bends 
and abreast of the proposed location of public 
small boat facilities near East Branch of Twelve 
Mile Creek. Actual Federal cost for the completed 
existing project was $477,904. Estimated non- 
Federal costs are $774,000 which includes costs of 
$16,000 for previously completed work. Remainder 
of non-Federal costs are for work required for 1968 
R & H Act including cash contribution of $166,- 
988. 
Local cooperation. Fully complied with. 
Terminal facilities. One fish dock and a number 
of recreational boating facilities are all privately 
owned and suitable only for small craft. One 
small-craft dock, owned by village of Wilson, is 
open to public. 
Operation and results during fiscal year. 
Maintenance: Miscellaneous inspection and condition 
surveys by Government plant and hired 
labor cost $298. 
Condition at end of fiscal year. Existing project 
is completed. Restoration of east and west parallel 
piers and construction of entrance channel were 
completed in 1950. The project modification 
authorized by the 1968 River and Harbor Act was 
selected by the Secretary of the Army for inclusion 
in the Small Authorized Projects program. Work 
consisted of channel deepening, extension, and 
widening at Wilson Harbor and Tuscarora Bay. 
The work was initiated in May 1972 and completed 
in September 1972. Costs of existing project 
were $477,904 for new work and $58,124 for 
maintenance, a total of $536,028. In addition, 
$166,998 of contributed funds, expended for new 
work. 
23. RECONNAISSANCE AND 
CONDITION SURVEYS 
Surveys were conducted at Barcelona Harbor, 
N.Y., Olcott Harbor, N.Y. and Presque Isle Peninsula, 
Pa. during August, 1974. 
24. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 32-C. 
25. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107 
Public Law 86-645 (Preauthorization) 
Lorain Harbor, Ohio--Fiscal year costs for 
preparation of Detailed Project Report were $2,433 
for a cumulative total cost of $29,569. Local interests 
indicated that there is no further interest 
in construction of small boat harbor. All work 
therefore, was terminated in February 1975. 
Beach Erosion Control 
26. HAMLIN BEACH STATE PARK, N.Y. 
Location. In town of Hamlin, Monroe County on 
south shore of Lake Ontario about 20 miles west of 
Rochester, N.Y. (See Lake Survey Chart 24). 
Existing project. Provides for: (a) construction 
of four new groins; (b) alterations of three existing 
groins; (c) grading of bluffs to a stable slope; and 
(d) placement of 217,000 cubic yards of sand to 
provide a minimum beach width of 100 feet at 
mean lake level. Estimated costs (July 1974) are 
$1,950,000 Federal and $840,000 non-Federal. Existing 
project was authorized by 1958 River and 
Harbor Act (H.D. 138/84/1). 
Local cooperation. Fully complied with. 
Assurances of local cooperation are contained in 
supplemental agreement dated July 22, 1963 
between the State of New York Conservation 
Department, Division of Parks and the Buffalo 
District Corps of Engineers for United States. 
Operations and results during fiscal year. The 
project is being constructed in two stages by the 
New York State Park Commission. Contract 
operations for Stage I, consisting of construction of 
four new groins, modification of existing groin, 
construction of outlet structure and beach 
replenishment were initiated in July 1973 and 
completed in August 1974. Reimbursement of the 
Federal share in the amount of $1,204,095 was 
32-18

BUFFALO, N.Y., DISTRICT 
made to the State of New York for work completed 
under Stage I. Contract operations for 
Stage II consisting of construction of two new 
groins and beach replenishment were initiated in 
October 1974 and are 38 percent completed. 
Condition at end of fiscal year. Contract 
operations for Stage I were initiated in July 1973 
and completed in August 1974. Contract 
operations for Stage II initiated in October 1974 
were continued. Completion of Stage II, and subsequent 
reimbursement to the State of New York, 
remains to be done to complete the project. 
27. LAKEVIEW PARK, LORAIN, OHIO 
Location. In the City of Lorain, Lorain County, 
Ohio, on south shore of Lake Erie between 1,500 
and 3,000 feet west of Lorain Harbor west 
breakwater. (See Lake Survey Chart 357). 
Existing Project. Provides for: (a) construction 
of about 70 feet of seawall with top elevation at 10 
feet above low water datum; (b) construction of a 
new groin 295 feet long; (c) alteration and extension 
of three existing groins to a length of 295 feet 
each; (d) placement of suitable sand fill to develop 
a bathing beach. Estimated Federal cost for new 
work is $1,810,000 (Oct. 1975). Estimated non- 
Federal cost for new work is $770,000 (Oct. 1975). 
Existing project authorized by 1954 River and 
Harbor Act (H. Doc. 229, 83rd Cong. 1st sess.). 
Local cooperation. Local interests are required 
to adopt the recommended plan of protection and 
improvement; submit for approval by the Chief of 
Engineers detailed plans and specifications and 
arrangements for prosecuting the entire work prior 
to the commencement of such work; or advance 
their share of funds for the work in case the 
Federal Government is requested to perform the 
work; provide further that appropriate authority 
give satisfactory measures during the useful life 
thereof as may be required to serve their intended 
purpose; hold and save the United States free 
from claims for damages that may arise before, 
during, or after prosecution of the work; not permit 
water pollution that would endanger the 
health of bathers; maintain continued public 
ownership of the beach and its administration for 
public use only. Assurances of local cooperation 
will be requested upon completion of Design 
Memorandum. 
Operations and results during fiscal year. New 
work. Preconstruction planning was continued. 
Condition at end of fiscal year. Completion of 
preconstruction planning and construction of project 
remain to be done to complete project. 
28. PRESQUE ISLE PENINSULA, ERIE, PA. 
Location. At Erie, Pa., on south shore of Lake 
Erie, 78 miles southwest of Buffalo, N.Y. and 102 
miles east-northeast of Cleveland, Ohio, (See Lake 
Survey Charts 3, 33, and 332). 
Existing project. For description of completed 
portion of existing project see page 1393 of Annual 
Report for 1963. Federal cost of completed portion 
of project as authorized by the 1954 and 1960 R & 
H Acts is $2,145,562 and non-Federal costs are estimated 
to be $2,483,000. 
The Water Resources Development Act of 
March 7, 1974, reinstated and extended authorization 
for the beach erosion control project, as 
provided in the 1960 R&H Act, for a period of five 
years from the date of enactment of the 1974 WRD 
Act, or if the review study of such project is not 
completed prior to the end of such period, until 
such study is completed and a report thereon submitted 
to Congress. Estimated Federal cost of the 
nourishment program authorized by the 1974 
WRD Act is $3,500,000 (Oct. 1975) and the estimated 
non-Federal cost is $1,500,000 (Oct. 1975). 
See Table 32-B for authorizing legislation. 
Local cooperation. Fully complied with for the 
completed project. For the nourishment project as 
authorized by the 1974 WRD Act, local interests 
are required to adopt the recommended plan of 
protection and improvement; provide at their own 
expense all necessary lands, easements and rightsof-
way for accomplishment of the work; provide 
further that the Commonwealth give satisfactory 
assurances that it will: maintain the protective 
and improvement measures including the proposed 
feeder beaches, during the useful life thereof as 
may be required to serve their intended purpose; 
hold and save the United States free from all 
claims for damages that may arise before, during 
or after prosecution of the work; not permit water 
pollution that would endanger the health of 
bathers; maintain continued public ownership of 
the shore and its administration for public use only; 
and, provide to the Government the non- 
Federal funds required for the project construction 
cost promptly upon written notice by the Government 
prior to advertisement for bids for performance 
of project works. Agreement between 
Department of Environmental Resources, Commonwealth 
of Pennsylvania and the Corps of 
Engineers was entered into on January 7, 1975. 
Operations and results during fiscal year. New 
work. Costs of $786,754 were incurred for Phase I 
of the beach replenishment as authorized by the 
1974 WRD Act, Commonwealth of Pennsylvania 
contributed funds in the amount of $338,751 for its 
share of the cost of the nourishment. 
Condition at end of fiscal year. Existing project 
is 52 percent complete. Since project authorization, 
Federal participation in first costs for remaining 
work was changed from one-third share to 70 
percent in accordance with provisions of section 
32-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
103, Public Law 87-874. Construction of project 
works for shore protection as authorized by 1954 
River and Harbor Act was accomplished in two 
stages by separate contracts. Stage 1, completed 
in September 1957, provided for realignment and 
removal of steel-sheet pile bulkhead and placing 
of sandfill. Stage II, completed in October 1956, 
provided for construction of bulkheads and groins. 
Modification to six groins was accomplished in 
1966. Under the periodic nourishment program 
authorized by 1960 River and Harbor Act, the,first 
major beach nourishment was completed in 1961. 
The second beach nourishment was completed in 
1965. Special coarse sand fill was placed in 1966. 
Third nourishment was completed in 1969. Fourth 
and final periodic nourishment of the beach during 
the 10-year period from year of first major 
nourishment operation was completed in 
December 1971. Authority for Federal participation 
expired in May 1971. Phase I of the beach 
replenishment, as authorized by the 1974 WRD 
Act, was completed in June 1975. Additional 
replenishment as authorized by 1974 WRD Act, 
remains to be done to complete the project. In addition, 
costs of $257,985 were incurred during 
fiscal years 1973 and 1974 under Public Law 84-99, 
Flood Control and Coastal Emergencies Appropriation, 
for project rehabilitation as a result of 
damages due to storm and high lake levels. 
29. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See Table 32-D. 
30. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion activities pursuant to section 103, 
Public Law 87-874 (preauthorization). A 
preliminary Economic Study was continued of a 
selected site of the shore in the City of Eastlake, 
Lake County, Ohio, extending one mile easterly of 
the mouth of Chagrin River. The study was undertaken 
with a view towards possible Federal participation 
in protection of private property. The 
cost for the fiscal year was $3,669, for a 
cumulative total cost of $14,700. 
Flood Control 
31. EASTLAKE, OHIO, CHAGRIN RIVER 
Location.' City of Eastlake is in Lake County, 
Ohio. Chagrin River flows northerly through city 
into Lake Erie. (See Army Map Service 
quadrangles for Chesterfield, Eastlake and 
Mayfield Heights and Lake Survey chart 34.) 
Existing project. Provides for: (a) Realignment 
and enlargement of Chagrin River channel from 
deep water in Lake Erie through a part of city of 
Eastlake, a total distance of 10,600 feet with 
depths of 10 feet from deep water in lake to a 
point 1,760 feet above river mouth and 7 feet deep 
in the remainder of channel; (b) construction of 
arrowhead breakwaters in Lake Erie at mouth of 
Chagrin River, the east breakwater 980 feet long 
and west breakwater 1,440 feet long; (c) construction 
of levees for a total length of 10,200 feet; (d) a 
1,400-foot long spur channel 100 feet wide, 6 feet 
deep; (e) an access channel for navigation 200 feet 
long, 50 feet wide and 4 feet deep; (f) development 
of recreational facilities at the river mouth. 
Estimated costs (Oct. 1975) are $12,350,000. 
Federal and $5,609,000 non-Federal including $5,- 
060,000 cash contribution and remainder for 
lands, relocations, parking lot, dock, and ramp. 
Existing project was authorized by 1965 Flood 
Control Act (S.D. 35/89/1). 
Local cooperation. Assurances were furnished 
by the City of Eastlake, Ohio and were accepted 
by the District Engineer on February 27, 1967. 
The Council of the city of Eastlake, by Resolution 
dated February 12, 1974, updated the assurances 
to comply with current requirements. Compliance 
with the assurances will be required upon completion 
of planning. Local interests are required to 
contribute in cash 50 percent of that portion of the 
first cost of Federal construction allocated to 
recreational navigation, such contribution 
presently estimated at $5,060,000 (Oct. 1975) to be 
paid either in a lump sum prior to initiation of 
construction, or in installments prior to start of 
pertinent work items in accordance with construction 
schedules as required by the Chief of 
Engineers, the final apportionment of cost to be 
made after actual costs have been determined. 
Operations and results during fiscal year. 
Preconstruction planning was continued. 
Condition at end of fiscal year. Construction has 
not been initiated. Work remaining to complete 
project consists of completion of preconstruction 
planning and construction of local flood protection 
improvements. 
32. ELLICOTT CREEK, N.Y. 
Location. The proposed channel improvement is 
located on the downstream portion of Ellicott 
Creek in the Town of Amherst, Erie County. (See 
Geological Survey maps of Tonawanda East and 
Buffalo Northeast, N.Y.) 
Existing project. For detailed description of the 
original project as authorized by Section 201 of the 
1970 Flood Control Act, see page 32-24 of Annual 
Report for 1973. Based on the wording of the 
authorization it was required that before real estate 
is acquired or construction started, a further 
report be made to Congress on possible alternative 
methods by which the objectives of the authorized 
32-20

BUFFALO, N.Y., I)ISTRICT 
project might be achieved. As a result of the 
restudy of alternatives completed in the Fall of 
1974, the authorization of the 1970 Flood Control 
Act was modified by the Water Resources 
Development Act of 1974 to provide for: (a) widening, 
straightening and deepening approximately 
4.7 miles of existing creek channel and the existing 
by-pass channel in Ellicott Creek Park; (b) construction 
of a diversion channel, approximately 
one mile long between Maple Road and 
Millersport Highway; (c) construction of a diversion 
channel approximately 4,000 feet long, 
through Pfohl Park; (d) modification of culverts 
on East Niagara Street at Tonawanda Creek; (e) 
foundation protection of 3 highway bridges; (f) 
modification of utilities; and, (g) recreation 
facilities consisting of bike paths and bike hike 
paths, and possible open space park areas. The estimated 
Federal cost of the existing project is $6,- 
850,000 (Oct. 1975). The estimated non-Federal 
cost is $2,420,000 (Oct. 1975). 
Local cooperation. Responsible local interests 
are required to furnish assurances satisfactory to 
the Secretary of the Army that they will (a) 
provide without cost to the United States all 
lands, easements and rights-of-way necessary for 
the construction and maintenance of the project; 
(b) hold and save the United States free from all 
claims for damages incident to construction and 
operation of the project; (c) take over, maintain 
and operate the project, after completion in accordance 
with regulations prescribed by the Secretary 
of the Army; (d) accomplish, without cost to the 
United States, all relocations of highways, 
highway bridges, buildings, utilities and special 
facilities; (e) prescribe and enforce regulations to 
prevent encroachment on channels and on rightsof-
way necessary to proper functioning of the project; 
(f) provide leadership in preventing unwise 
use of flood plains by use of appropriate flood 
plain management techniques to reduce flood 
losses; (g) contribute 50 percent of the first cost of 
recreation facilities and bear all cost for 
maintenance, operation and replacement; and (h) 
establish rules to control the use, growth and 
development of the recreation facilities with the 
understanding that public facilities be open to all 
on equal terms. Formal assurances will be requested 
upon completion of the Feature Design 
Memorandum. 
Operations and results during fiscal year: New 
work: Preconstruction planning was initiated during 
December 1974. 
Condition at end of fiscal year. The 1970 Flood 
Control Act authorized construction of Sandridge 
Dam and downstream channel improvements. It 
also stipulated that before any work is initiated, a 
restudy of alternatives to the dam be undertaken. 
As a result of Restudy of Alternatives, which was 
completed in 1973, recommended revisions were 
submitted in a public notice dated March 18, 
1974. Revisions to the project are described in 
detail in above paragraph, Existing project. The 
authorization of the 1970 Flood Control Act was 
modified by the Water Resources Development 
Act of 1974 to provide for remedial flood control 
measures compatible with the diversion plan contained 
in the report of Restudy of Alternatives. 
Preconstruction planning was initiated in 
December 1974. Completion of preconstruction 
planning and construction remains to be done to 
complete the project. 
33. FREMONT, OHIO, SANDUSKY RIVER 
Location. On Sandusky River in city of Fremont, 
Sandusky County, Ohio. Sandusky River 
flows northerly through city of Fremont and enters 
Sandusky Bay, an arm of Lake Erie, about 14 
miles north of city. (See Geological Survey Map of 
Fremont-East.) 
Existing project. Provides for: (a) Channel 
enlargement and partial realignment in a 10,450- 
foot reach of Sandusky River in city of Fremont 
(including a 2,000-foot long friction channel); (b) 
construction of 18,300 feet of levees and 3,500 feet 
of flood walls; (c) construction of three pumping 
stations along west bank at Minnow Creek, 
Birchard St. and Liberty St. and one pump station 
on east bank at Pine St.; and, (d) construction 
of miscellaneous drainage structures and 
other appurtenant works. Federal costs for completed 
project were $8,568,086. Estimated non- 
Federal costs were $1,005,000 (July 1972) for 
lands, relocations and alterations of streets, 
pipelines and utilities. Existing project was 
authorized by 1962 Flood Control Act (S. Doc. 
136, 87th Cong. 2nd sess.). 
Local cooperation. Assurances were furnished in 
September 1965 and were accepted on 30 
September 1965. 
Operations and results during fiscal year. 
Finalization of contract costs was accomplished. 
Condition at end of fiscal year. Construction of 
the project, by contract, was initiated during 
August 1970, and completed in December 1972. 
Costs of $383,786 were incurred during fiscal years 
1974 and 1975, under Public Law 84-99 Flood Control 
and Coastal Emergencies. 
34. ITHACA, N.Y., CAYUGA INLET 
Location. City of Ithaca is in Tompkins County, 
N.Y. Cayuga Inlet flows northerly through western 
portion of city and enters head of Cayuga Lake at 
Ithaca, N.Y. (See Geological Survey maps of 
Ithaca-West, and Ithaca-East.) 
Existing project. For description of the com- 
32-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
pleted portion of the existing project, see page 32 
of Annual Report for 1971. Due to a deficiency in 
the completed project, OCE on May 21, 1973, 
authorized preparation of design for rectification 
of the project consisting of construction of concrete 
drop structure on Coy Glen channel, a 
tributary, and excavation and placing of riprap at 
Coy Glen. Estimated Federal cost of project is $3,- 
745,000 (Oct. 1975). Estimated non-Federal cost is 
$2,516,000 (Oct. 1975). For the completed portion 
of project the Federal cost was $3,462,000 and non- 
Federal cost was $2,513,000. ($77,000 cash contribution 
and remainder for lands, relocation of 
two highway bridges, access roads, utilities, and 
fishway holding pens). Existing project was 
authorized by 1960 Flood Control Act (H. Doc 204, 
86th Cong. 1st sess.). 
Local cooperation. Fully complied with for completed 
portion of project. Cash contributions, consisting 
of $23,000 toward incremental cost of construction 
of holding pens and fish trapping 
facilities and $77,000 towards first cost of completed 
project have been received. For additional 
improvements to project, local interests must contribute 
in cash an amount equal to 2.1 percent of 
the first cost for construction, the contribution 
presently estimated at $3,000 (Oct. 1975), the final 
apportionment of cost to be made after actual 
costs have been determined; furnish without cost 
to the United States all lands, easements, and 
rights-of-way necessary for construction of the 
project; hold and save the United States free from 
damages due to the construction works; and, 
maintain and operate all the works after completion. 
Intention to provide assurances by the State 
of New York were acknowledged by letter of 
November 26, 1973 from the N.Y. State Dept. of 
Environmental Conservation. Supplement to 
assurances will be requested upon approval of 
Letter Report. 
Operations and results during fiscal year. Planning 
was continued for the rectification of 
deficiency in the completed project. 
Condition at end of fiscal year. The existing 
project initiated in January 1965 was completed in 
June 1970. Since the completion of construction of 
the project, the relocation of Cayuga Inlet 
Channel resulted in shortening the length of and 
thereby increasing the slope in Coy Glen, a small 
tributary of the Inlet. As a result, severe erosion is 
occurring along Coy Glen resulting in continual 
shoaling in the completed Cayuga Inlet channel. 
The rectification of the project by construction of 
a concrete drop structure in Coy Glen channel will 
eliminate the erosion and shoaling problems. 
Completion of engineering and design and construction 
of additional improvements remains to 
be done to complete the project. Costs of $104,005 
were incurred during fiscal years 1973 and 1974, 
under Public Law 84-99, Flood Control and 
Coastal Emergencies Appropriation, as a result of 
damages due to Storm Agnes, June 1972. 
35. MT. MORRIS LAKE, N.Y., 
GENESEE RIVER 
Location. Dam is on Genesee River 66.9 miles 
above river mouth and about 32 miles 
southwesterly of Rochester, N.Y. Reservoir is in 
Livingston and Wyoming Counties, N.Y. (See 
Geological Survey maps of Nunda and Portage, 
N.Y.) 
Existing project. For description of existing 
project as authorized by 1944 Flood Control Act 
see page 1575 of Annual Report for 1962. New 
work for completed project cost $23,365,559. In addition 
$5,000 contributed funds expended for new 
work. 
Local cooperation. None required. Local interests 
contributed $5,000 for new work. 
Operations and results during fiscal year. 
Operations and maintenance: Operation and ordinary 
maintenance of dam, reservoir, and service 
facilities, condition and operation studies and 
miscellaneous reports were accomplished by hired 
labor for $193,580. Debris removal accomplished 
by contract, cost $36,400. Cooperative stream gaging 
program accomplished by Geological Survey 
for $26,817 and Weather Bureau reporting and 
hydroclimatic networks cost $18,644. Preparation 
of an Environmental Impact Statement cost $49,- 
173. 
Condition at end of fiscal year. Existing project 
is complete. Construction of concrete gravity-type 
dam was initiated by contract March 1948 and 
completed May 1952. Clearing of reservoir area 
and construction of all appurtenances are complete. 
Operations and maintenance of dam, reservoir, 
and appurtenances are continued annually. 
36. RED CREEK, N.Y. 
Location. Red creek is a minor tributary of the 
Genesee River located near northern end of river 
basin in Monroe County, N.Y. Project is located 
in city of Rochester and suburban towns of 
Brighton and Henrietta immediately south of 
Rochester. 
Existing project. Provides for: (a) new main 
stem diversion channel 5,200 feet in length, from a 
point on the Genesee River about 3,000 feet upstream 
from the N.Y. State Barge Canal crossing 
and extending to the existing creek channel at a 
point about 500 feet above Crittenden Road; 
above this point, channel enlargement and 
realignment for 6,700 feet along the existing main 
stem and for 3,800 feet along the East Branch; 
channel improvements for 13,600 feet along the 
West Branch; and placement of material ex- 
32-22

BUFFALO, N.Y., DISTRICT 
cavated from the channels, in excess of that required 
for levee embankments, as uncompacted 
fill in low areas adjacent to the improved channel; 
(b) replacement of the existing Erie-Lackawanna 
Railroad Bridge on the main stem downstream of 
the East Branch confluence; replacement of the 
existing Penn Central Railroad Bridge on the 
main stem downstream from Jefferson Road and 
underpin Penn Central Railroad Bridge on the 
West Branch upstream of Bronx Drive; underpinning 
for the existing Lehigh Valley Railroad 
Bridge on the East Branch downstream of West 
Henrietta Road; and pier protection for the 
highway bridge on the East Branch at West 
Henrietta Road; (c) levee along the right bank of 
the new main stem diversion channel upstream of 
Crittenden Road with a gated levee culvert 
through the embankment to the existing channel 
at Crittenden Road; (d) levee with a top width of 
10 feet, 1,700 feet in length, with a gated levee 
culvert, across the upstream end of the West 
Branch to exclude overflow from the Genesee 
River; (e) three levees along East River Road 
located southerly of Ballantyne Road at 
downstream portion of project, 3,000 feet long; 
northerly of Ballantyne Road to Bronx Drive, 1,- 
960 feet long and, at upstream end of project, 
southerly of confluence of new diversion channel 
and Genesee River, 1,080 feet long; (f) an I-type 
steel sheet pile flood wall, 8,038 feet long, located 
between Genesee River and East River Road, 
northerly of Bronx Drive to Hawthorne Road; and, 
(g) modification of utilities to fit enlarged stem 
channels. Estimated Federal costs are $5,530,000 
(Oct. 1975). Estimated non-Federal costs are $6,- 
740,000 (Oct. 1975) for lands, damages, 
relocations, construction of culverts and modification 
of golf course. Existing project was authorized 
by 1966 Flood Control Act (S.D. 107/89/2). 
Local cooperation. Local interests are required to 
provide without cost to United States, all lands, 
easements, and rights-of-way necessary for construction; 
hold and save United States free from 
damage due to construction works; maintain and 
operate all works after completion in accordance 
with regulations prescribed by Secretary of the Army; 
provide without cost to United States all 
relocations of buildings, utilities, roads, sewers, 
and related and special facilities necessary for 
construction of project, including any embankment 
for East River Road in excess of that required 
for a levee, construction of highway bridges 
and a service bridge across relocated main stem 
channel at East River Road and Crittenden Road, 
replacement of existing highway bridges on main 
stem at Town Line Road and at Jefferson Road, 
and replacement of existing culverts on West 
Branch at Crittenden Road, Bronx Drive and New 
York Route 252; prescribe and enforce regulations 
to prevent encroachment on channels and rightsof-
way necessary for proper functioning of project; 
take appropriate regulatory measures to preserve 
the ponding and floodway capacity necessary to 
proper functioning of the project upstream of 
proposed levee culvert; and, take necessary action 
to adopt building regulations or otherwise restrict 
development on unimproved property in Red 
Creek project area to provide that first elevations 
of future construction be at or above 100-year 
stage line. There is opposition to the project from 
the Town of Brighton, however, Monroe County is 
in favor of the project and indicates that it will 
accept total local cooperation responsibility. In 
view of the County's position, the State of New 
York is prepared to participate in the project and 
provide the assurances when required. 
' Operations and results during fiscal year. 
Preconstruction planning was continued. 
Condition at end of fiscal year. Construction has 
not been initiated. Work remaining to complete 
project consists of completion of preconstruction 
planning and construction of local flood protection 
improvements. 
37. SCAJAQUADA CREEK, N.Y. 
Location. Scajaquada Creek is a small stream 
draining to the Black Rock Canal and thence to 
Niagara River at Buffalo, New York. It flows from 
east to west and its drainage area is all in Erie 
County. About 65 percent of the watershed is upstream 
from the city of Buffalo, mostly in the 
towns of Cheektowaga and Lancaster, and the 
village of Depew. (See Geological Survey Maps of 
Buffalo-Northeast, N.Y. and Lancaster, N.Y.) 
Existing project. Provides for: (a) 9,410 feet of 
channel improvement on the main stem of Scajaquada 
Creek and a total of 17,350 feet of channel 
improvement on tributaries, all within the town of 
Cheektowaga; (b) construction of a levee totalling 
about 1,100 feet in length, (c) removal, replacement, 
or enlargement of obstructive bridges, 
culverts, and conduits; and, (d) sealing of sanitary 
sewer manholes subject to submergence. 
Estimated costs (October 1975) are $2,400,000 
Federal and $2,532,500 non-Federal including 
$132,500 for reimbursement of one-half of excess 
non-Federal cost. Existing project authorized by 
1965 Flood Control Act-Section 201. 
Local cooperation. Prior to construction, local 
interests are required to furnish assurances 
satisfactory to the Secretary of the Army that they 
will, (a) provide without cost to the United States 
all lands, easements, rights-of-way, and disposal 
areas necessary for construction of the project; (b) 
hold and save the United States free from 
damages due to the construction works; (c) maintain 
and operate all the works after completion in 
accordance with regulations prescribed by the 
32-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Secretary of the Army; (d) provide without cost to 
the United States all relocations, alterations, or 
replacement of roads, buildings, and utilities, 
highway bridges, footbridges, sewers, and related 
and special facilities which may be required for 
construction of the project, except for such items 
as are abandoned for removal by the United 
States; (e) prescribe and enforce regulations to 
prevent encroachment on channels and rights-ofway 
required for proper functioning of the project; 
(f) at least annually inform affected interests that 
the channel improvement will not provide complete 
flood protection; and; (g) provide guidance 
and leadership in preventing unwise and uneconomical 
future development of the flood plain 
areas by encouraging prudent use of flood proofing, 
and regulation planning, or other flood plain 
management techniques to reduce flood losses; 
provided further that, if the necessary expenditures 
by local interests for lands, easements, 
rights-of-way, and relocations exceed the Federal 
construction cost, the local cooperating agency 
shall be reimbursed one-half of such excess as 
provided by Section 3 of the 1936 Flood Control 
Act. Assurances of local cooperation will be requested 
upon completion of the Phase II Design 
Memorandum. 
Operations and results during fiscal year. 
Preconstruction planning was continued. 
Condition at end of fiscal year. Construction has 
not been initiated. Work remaining to complete 
project consists of completion of preconstruction 
planning and construction of local flood protection 
improvements. 
38. WELLSVILLE, N.Y., GENESEE RIVER 
Location. Village of Wellsville is in Allegany 
County at junction of Dyke Creek and Genesee 
River. (See Geological Survey map of Wellsville, 
N.Y.) 
Existing project. See page 1574 of Annual 
Report for 1962 for description of completed portion 
of existing project as originally authorized by 
Flood Control Act approved May 17, 1950 (H. 
Doc. 232 81st Cong., 1st sess.). Modifications to 
rectify deficiencies in completed project were 
authorized in November 1966 in accordance with 
Design Memorandum for Rectification of Deficiencies 
in Completed Flood Protection Project, 
Wellsville, New York. The rectification of 
deficiencies, which was accomplished under the 
initial phase, consisted of: deepening, enlarging 
and extension of project channels on the Genesee 
River and Dyke Creek; construction of adjacent 
compacted embankment levees; providing stone 
slope protection, derrick stone and drainage 
facilities; modification of existing concrete drop 
structure; and, alteration of an existing steel sheet 
pile weir on Genesee River. 
Additional modifications to rectify deficiencies 
were authorized in June 1975 in accordance with 
Letter Report submitted in October 1974. These 
deficiencies, which are to be rectified under the second 
stage, consist of construction of new steel 
sheet pile energy dissipator levees, channel clearing 
and bank protection at upstream end of project 
on Genesee River; and, channel clearing and 
bank protection in three separate locations near 
upstream end of project on Dyke Creek. 
The total estimated Federal cost of the project 
is $3,220,000 (Oct. 1975) of which $1,060,300 was 
for the completed existing project; $1,177,000 was 
for the completed rectification of deficiencies under 
the initial stage; and $1,032,700 is for the rectification 
of deficiencies to be accomplished under 
the second stage. The total estimated non-Federal 
cost of the project is $379,000 (Oct. 1975) of which 
$170,000 including $50,000 cash contribution was 
for the completed project and the balance of $209,- 
000 were costs incurred for the rectification of the 
deficiencies accomplished under the initial stage. 
Local cooperation. For additional improvements 
to project, local interests must furnish assurances 
that they will submit, for prior approval of the 
United States, all plans for highway improvements 
in the vicinity of Wellsville flood control 
project which involve or require modifications 
of existing facilities of that project, and thereafter 
make such improvements in accordance with 
plans so approved; provide lands, easements, and 
rights-of-way, including ponding areas, and make 
all alterations to utilities, necessary for construction 
of the additional flood control improvements; 
hold the United States free from damages due to 
construction of the additional flood control improvements; 
prescribe and enforce regulations to 
prevent encroachments on project channels as 
modified by the additional improvements; and 
maintain and operate all of the project works after 
completion of additional improvements in accordance 
with regulations prescribed by the Secretary 
of the Army. Assurances have been received and 
were accepted on February 28, 1969. For completed 
portion of project local interests contributed 
$50,000. 
Operations and results during fiscal year. Contract 
operations for initial stage of rectification of 
deficiencies which were initiated in July 1973, 
were completed in August 1974. Planning was initiated 
for rectification of deficiencies to be accomplished 
under the second stage. 
Condition at end of fiscal year. Existing project 
was completed in November 1957 and repairs to 
flood-damaged riprap slopes made in September 
1959. An inspection of completed project disclosed 
that additional work is necessary to improve completed 
project. There has been widespread erosion 
of unprotected portions of channel banks, particularly 
on outside banks at bends and subse- 
32-24

BUFFALO, N.Y., DISTRICT 
quent deposition of eroded material usually along 
inside banks. Contract for the rectification of 
deficiencies was awarded on June 15, 1973 and 
contract operations under the initial stage, which 
were initiated during July 1973, were completed 
during August 1974. Completion of planning and 
construction of additional improvements under 
the second stage remains to be done to complete 
the project. In addition, costs of $374,042 were incurred 
during fiscal years 1973, 1974 and 1975 for 
project rehabilitation under authority of Public 
Law 84-99, Flood Control and Coastal Emergencies. 
39. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed flood control works for 
compliance with Federal requirements were made 
during the year at a cost of $5,000. Total cost to 
June 30, 1975 was $38,170. 
40. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 32-E. 
41. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control and Coastal Emergencies (Public 
Law 99, 84th Cong. as amended by Sec. 206 of 
Flood Control Act of 1962) 
Federal costs for fiscal year were $32,445 for advance 
preparation, $351,856 for emergency operation 
and $26,698 for rehabilitation of two completed 
projects. 
Emergency bank protection (Sec. 14 of 1946 
Flood Control Act, Public Law 526, 79th Cong.) 
Willoughby Hills, Ohio - Fiscal year costs of $7,- 
702 were incurred for completion of unfavorable 
Reconnaissance Report. Surplus funds in the 
amount of $298 were revoked. 
Genesee River, Avon, N.Y. - Funds in the 
amount of $13,000 were allotted in June 1974. 
Costs of $5,000 were incurred during FY 1975 
when work on this project was terminated. The 
balance of funds in the amount of $8,000 were 
transferred to St. Columbans-on-the-Lake, N.Y. 
for preparation of Reconnaissance Report. 
St. Columbans-on-the-Lake, N.Y. - Funds in 
the amount of $8,000 were transferred from the 
project at Genesee River at Avon, N.Y. Costs of 
$2,515 were incurred for initiation of Reconnaissance 
Report. 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization). 
Arcade, N.Y. - Fiscal year costs for completion 
of Reconnaissance Report were $1,769 for a 
cumulative total cost of $5,828. 
Bull Creek, N.Y. - Fiscal year costs for completion 
of unfavorable Detailed Project Report were 
$9,695 for a cumulative total cost of $100,566. 
Cayuga Creek, Lancaster, N.Y. - Fiscal year 
costs for completion of Reconnaissance Report 
were $1,773. 
Dyke Creek, Wellsville, N.Y. - Fiscal year costs 
for completion of Reconnaissance Report were 
$13,000. 
Little River, Cayuga Island, N.Y. - Fiscal year 
costs for completion of Reconnaissance Report 
were $5,000. 
General Investigations 
42. SURVEYS 
Fiscal year costs were $1,685,412 of which $456,- 
172 was for navigation studies, $426,450 was for 
flood control studies, $633,951 for special studies, 
$118,109 for coordination with other agencies, 
$24,351 for comprehensive basin studies and $26,- 
379 for review for deauthorization. 
43. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year cost was $54,000 for work in connection 
with International Water Studies and $223,- 
948 for flood plain management services. 
Flood plain information reports were initiated 
for Grand River, Trumbull County, Ohio, Little 
Black Creek, N.Y. and Nine Mile Creek, N.Y. 
(See Table 32-F of completed flood plain information 
reports at end of chapter). 
44. RESEARCH AND DEVELOPMENT 
Hydrologic studies of the effect of urbanization 
on stream runoff on Grand Island, N.Y., were continued 
at a cost of $5,549 for a cumulative cost of 
$25,500. 
32-25

TABLE 32-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Ashtabula Harbor, 
Ohio 
2. Black Rock Channel 
and Tonawanda 
Harbor, N.Y. 
3. Buffalo Harbor, 
N.Y. 
(Federal Funds) 
(Contributed Funds) 
4. Cape Vincent Harbor, 
N.Y. 
5. Cattaraugus Harbor, 
N.Y. 
6. Cleveland Harbor, 
Ohio 
(Federal Funds) 
(Contributed Funds) 
7. Conneaut Harbor, 
Ohio 
8. Dunkirk Harbor, 
N.Y. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
310,600 
206,165 
478,100 
433,312 
1,304,200 
1,260,258 
16,862 
33,100 
7,781 
30,000 
4,764 
-300,000 
28,467 
3,271,600 
2,449,800 
54,573 
509,700 
307,338 
127,374 
221,502 
668,569 
387,538 
170,300 
382,643 
873,100 1,658,702 831,849 
699,797 1,016,679 1,685,318 
-385,036 
303,703 
-93,195 
-21,177 
4,037 
20,000 
19,364 
-45,000 
15,814 
9,432,865 
2,927,921 
3,056 
137,697 
113,992 
4,874,317 2,290,100 
970,444 5,960,003 
85 6,000 
190 6,000 
110,000 175,000 
108,017 170,914 
-100,000 
1,102 
1,847,210 
6,455,620 
410,161 
617,648 
-12,100 
2,005 
5,419,651 
7,979,102 
366,200 
383,099 
11,680,339' 
11,680,339' 
4,882,666 
4,803,671 
10,515,120' 
10,515,1202 
16,389,848, 
16,365,470' , 
23,115,187 
23,115,1875 
25,605,3876 
25,275,1626 
56,805 
56,805 
295,457 
295,457 
275,082 
275,082 
59,026 
59,026 
335,000 
303,059 
31,503,299' 
31,503,194' 
55,319,0778 
55,145,9898 
201,9609 
201,9609 
464,903 
464,903 
8,346,641' 0 
8,346,641' 0 
4,312,002" 
4,307,804" 
651,850 
651,850 
4,500 
2,616 
5,038 
4,154 
-1,383 
1,617 
45,000 
44,866 
116,000 
116,000 
1,274,424"2 
1,274,29012 
1,288,078" 
1,288,078" 
32-26

BUFFALO, N.Y., DISTRICT 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
9. Erie Harbor, Pa. 
10. Fairport Harbor, 
Ohio 
11. Great Sodus Bay 
Harbor, N.Y. 
12. Huron Harbor, 
Ohio 
13. Irondequoit Bay, 
N.Y. 
14. Little Sodus Bay 
Harbor, N.Y. 
15. Lorain Harbor, 
Ohio 
16. Oak Orchard 
Harbor, NY 
(Federal Funds) 
(Contributed Funds) 
17. Oswego Harbor, 
N.Y. 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
395,900 
187,992 
338,100 
283,108 
155,094 
158,444 
218,015 
262,332 
160 535,000 
960 69,002 
- -15,344 
292,500 
120,455 
136,770 
1,676 
580,400 
182,096 
1,588,900 
1,026,724 
286,100 
179,855 
195,685 
308,694 
-100,000 
4,462 
612,000 
453,945 
3,300,000 
1,223;335 
267,108 
107,587 
150,000 1,073,000 
11,337 17,368 
- 198,200 
217,525 
388,858 
949,602 
682,959 
6,000 
231,770 
70,000 
35,246 
308,100 
393,657 
583,200 
770,685 
63,000 
281,665 
75,000 
107,860 
2,965,487 619,200 
254,186 3,362,589 
-35,000 - 
862 1,698 
122,714 57,000 
613,835 173,113 
1,067,000 20,000 
2,994,843 1,071,905 
480,351 506,200 
389,815 722,455 
350,000 
576,372 717,688 
72,440 46,759 
32-27 
3,597,87314 
3,597,873'" 
6,187,81915 
6,184,25115 
1,154 
1,154 
2,959,61116 
2,959,61116 
6,921,935 
6,877,101 
610,959 ' 
610,9591 
2,069,803 
2,046,360 
713,544 
713,544 
1,453,79518 
1,451,90118 
6,343,003 
6,316,055 
247,030 
247,030 
141,770 
141,770 
301,394' 9 
301,394' 9 
2,491,593 
2,491,529 
742,822 
742,822 
20,398,99720 
20,393,25120 
5,794,429 
5,754,382 
1,680,500 
1,430,265 
198,200 
119,199 
8,430,01624 
8,430,01624

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
18. Rochester Harbor, 
N.Y. 
19. Rocky River Harbor, 
Ohio 
20. Sandusky 
Harbor, Ohio 
21. Vermilion 
Harbor, Ohio 
(Federal Funds) 
(Contributed Funds) 
22. Wilson Harbor, 
N.Y. 
(Federal Funds) 
(Contributed Funds) 
26. Hamlin Beach 
State Park, N.Y. 
27. Lakeview Park, 
Lorain, Ohio 
28. Presque Isle 
Peninsula, Erie, Pa. 
(Federal Funds) 
(Contributed Funds) 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
369,700 
273,427 
639,200 
397,046 
4,600 
4,639 
540,700 
220,544 
198,600 
12,252 
4,500 
2,447 
120,000 
30,499 
166,998 
38,611 
39,700 
883 
53,230 
407,943 
110,500 
85,976 
-96,436 
184,038 
23,389 
25,904 
355,348 
635,202 
624,400 
203,383 
730,000 
111,165 
-173 
5,038 
-12,038 
103,914 
25,506 
154,990 
165,252 
183,156 
90,000 
678,835 
588,176 
27,774 
27,114 
468,700 
463,247 
954,400 
857,715 
38,000 
32,900 
258,600 
273,432 
-75,160 
-39,227 
10,679 
41,338 
S79,000 
79,660 
20,000 -23,858 
97,758 -11,912 
110,322 
-30,000
54 
18,066 
1,379 
1,081 
- 1,255,161 
- 1,248,800 
90,000 30,000 
43,831 84,531 
40,000 750,000 
786,754 
338,571 
310,239 
1,798 
1,798 
32-28 
3,723,81525 
3,713,51725 
307,590 
307,590 
2,439,30826 
2,439,30826 
6,720,7042 
6,620,355 
343,494 
343;494 
155,9582' 
150,8582 
6,727,27029 
6,727,2701
" 
5,598,076 
5,590,445 
675,606 
675,606 
1,156,118 
1,156,118 
740,679 
740,679 
310,175 
310,175 
139,775 
139,775 
535,24629 
535,24629 
166,998 
166,998 
75,0380� 
75,038 � 
1,292,161 
1,285,800 
129,700 
129,299 
2,935,562' 
2,932,316" 
338,571 
310,239 
2,476 
2,476 
298

BUFFALO, N.Y., DISTRICT 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
31. Eastlake-Chagrin New Work 
River, Ohio Approp. 60,000 5,344 140,000 25,000 430,344 
Cost 7,288 17,747 119,473 88,079 430,344 
32. Ellicott Creek, New Work 
N.Y. Approp. 149,000 21,000 10,000 135,000 315,000 
Cost 14,732 149,792 15,746 125,339 305,339 
33. Fremont, Ohio, New Work 
Sandusky River Approp. 6,810,900 -207,400 -20,000 - 8,582,880 
(Federal Funds) Cost 5,961,667 572,816 50,295 1,069 8,568,086 
(Contributed Funds) New Work 
Contrib. 6,944 - - - 6,944 
Cost 6,944 - - - 6,944 
34. Ithaca, N.Y. New Work 
Cayuga Inlet Approp. - - - - 3,494,330 
(Federal Funds) Cost 27,637 741 6,408 19,953 3,489,102 
(Contributed Funds) New Work 
Contrib. - - - - 95,000 
Cost 18,000 77,000 - - 95,000 
35. Mt. Morris New Work 
Lake, N.Y. Approp. - - - - 23,365,559' 
Genesee River Cost - - - - 23,365,55932 
Maint. 
Approp. 106,300 259,800 222,138 359,100 2,173,509 
Cost 104,206 173,236 300,208 324,614 2,127,731 
36. Red Creek, N.Y. New Work 
Approp. - -27,000 53,241 25,000 361,241 
Cost 54,975 2,835 24,064 61,996 361,241 
37. Scajaquada Cr., New Work 
N.Y. Approp. - 5,000 60,307 125,000 190,307 
Cost - 1,760 63,424 121,973 187,157 
38. Wellsville, N.Y. New Work 
Genesee River Approp. - 840,000 - 25,000 2,205,303"' 
Cost 31,490 29,759 890,004 114,668 2,204,521" 
See page 32-30 for footnotes. 
32-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 32-A (Continued) COST AND FINANCIAL STATEMENT 
1. Includes $565,192 for previous projects. 
2. Includes $58,027 for previous projects. 
3. Includes $4,922 emergency relief authority administrative 
costs transferred from new work to maintenance 
upon conversion to programming and budgeting system July 1, 
1953, by direction of Office, Chief of Engineers. 
4. Includes appropriations and costs under appropriation 
titles 96x3123 Operation and Maintenance and 96x5125 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
5. Includes $4,277,586 for previous projects. 
6. Includes $1,883,647 for previous projects. Excludes 
$390,000 contributed funds. 
7. Includes $1,564,154 for previous project and appropriations 
and costs for modification authorized for construction 
under authority of Sec. 107, 1960 R & H Act. 
8. Includes appropriations and costs under appropriation 
titles 96x3123 Operation and Maintenance and 96x5125 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
9. Includes $50,000 contributed funds expended in FY 
1935 and FY 1936. 
10. Includes $805,272 for previous projects. 
11. Includes $39,784 for previous projects. 
12. Includes $811,250 for previous projects. Excludes $11,- 
000 contributed funds expended. 
13. Includes $176,520 for previous projects. 
14. Includes $736,967 for previous projects. 
15. Includes $104,900 for previous projects. Excludes $154,- 
500 contributed funds. 
16. Includes $368,940 for previous projects. 
17. Includes $361,772 for previous projects. 
18. Includes $269,789 for previous project. 
19. Includes $232,328 for previous projects. 
20. Includes $292,203 for new work for previous projects. 
Excludes $3,000 contributed funds. Also excludes appropriation 
of $29,570 and costs of $23,683 reported for modification 
under authority of Section 107, 1960 R & H Act. Costs are included 
in Section 26. 
21. Excludes $249,346 contributed funds. 
22. Includes $38,959 for previous projects. Excludes $5,000 
contributed funds. 
23. Excludes $186,000 Public Works Acceleration Act funds. 
24. Includes $1,187,977 for previous projects. 
25. Includes $945,684 for previous projects. 
26. Includes $247,794 for previous projects. 
27. Includes $617,529 for previous projects and $478 
emergency relief authority administration costs transferred 
from new work to maintenance upon conversion to programming 
and budgeting system, July 1, 1953, by direction of Office, 
Chief of Engineers. 
28. Excludes $325,000 contributed funds expended. 
Includes $477,149 for previous projects. 
29. Includes $57,342 for previous projects. 
30. Includes $16,914 for previous projects. 
31. Excludes $1,327,139 contributed funds. 
32. Excludes $5,000 contributed funds. 
33. Excludes $50,000 contributed funds and $354,475 of 
Public Law 84-99, Flood Control and Coastal Emergency Appropriation 
funds. 
32-30

BUFFALO, N.Y., DISTRICT 
TABLE 32-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 3, 1896 
Mar. 3, 1905 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 26, 1937 
Annual Report, 1895, p. 2 13 2 . 
H. Doc. 654, 01st Cong., 2d sess. 
H. Doc. 997, 64th Cong., 1st sess. 
H. Doc. 43, 73d Cong., 1st sess. 
Rivers and Harbors Committee Doc. 
78, 74th Cong., 2d sess.2 
ASHTABULA HARBOR, OHIO (See Section 1 of Text) 
Construction of breakwater. 
Enlarge outer harbor by extending west breakwater and 
constructing new east breakwater; pierheads on lakeward 
ends of breakwaters; and remove part of old east 
breakwater. 
Extend west breakwater to shore; dredge outer harbor to a 
depth of 20 feet. 
Remove portion of east breakwater, extend breakwaters to 
present project dimensions, and dredging restrictions 
in portion of west basin. 
Dredge channel through outer harbor, channel of approach 
to Penn Central Co. slip, channel in Ashtabula River, 
to and in turning basin, all to present project 
dimensions; remove portion of old east inner 
breakwater; and maintenance to 24-foot depth of 
portion of outer harbor. 
Extend river channel to present project limit. 
Dredging approach channel and turning basin in east 
outer harbor to 25-foot depth. 
A depth of 29 feet in soft and 30 feet in hard material 
in entrance channel to just inside outer ends of 
breakwaters; thence 28 feet in soft and 29 feet in 
hard material in a channel to inner breakwater; thence 
27 feet in soft and 28 feet in hard material in a channel 
extending to Penn Central Co. slip and extending 2000 
feet up Ashtabula River; 22 feet in hard material in 
turning area; and 28 feet in soft and 29 feet in hard 
material in areas adjacent to 250-foot section of inner 
breakwater when that section is removed as now authorized. 
Dredging approach channel and turning basin in east 
outer harbor to 28 feet in soft material and 29 feet 
in hard material. 
BLACK ROCK CHANNEL AND TONAWANDA HARBOR, N.Y. 
(See Section 2 of Text) 
Dredging channel through Horseshoe Reef at outlet of 
Lake Erie and Tonawanda Inner Harbor, to 16 feet. 
Deepening Tonawanda Creek to 16 feet. 
Dredging channel from Buffalo outer harbor to foot of 
Maryland St., Buffalo, to 21 feet. 
Dredging channel from foot of Maryland St., Buffalo, 
to natural deepwater pool upstream from Tonawanda 
Harbor to 21 feet; construction of ship lock and 
bridge; and repair of Bird Island pier and towpath 
wall. 
Dredging channel along Tonawanda Island, with turning 
basin at its downstream end at the foot of the Island, 
to 21 feet. 
Dredging triangular area at junction with Buffalo north 
entrance channel. 
H. Ex. Doc. 83, 50th Cong., 1st sess., 
Annual Report, 1888, p. 2066, and 
Annual Report, 1897, pp. 3116-3120. 
H. Doc. 143, 56 Cong., 1st sess., and 
Annual Report, 1900, p. 4152. 
H. Doc. 125, 56th Cong., 2d sess., and 
Annual Report, 1901, p. 3343. 
H. Doc. 428, 58th Cong., 2d sess. 
H. Doc. 658, 63d Cong., 2d sess. 
H. Doc. 1004, 65th Cong., 2d sess., and 
H. Doc. 92, 79th Cong., 1st sess. 
32-31 
H. Doc. 321, 77th Cong., 1st sess. 
H. Doc. 486, 83d Cong., 2d sess. 
H. Doc. 148, 86th Cong., 1st sess. : 
H. Doc. 269, 89th Cong., 1st sess.4 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 27, 1965 
Aug. 11, 1888 
June 3, 1896 
June 13, 1902 
June 13, 1902 
Aug. 8, 1917 
Mar. 3, 1905 
July 27, 1916 
Mar. 2, 1919 
Mar. 2, 1945

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 32-B (Continued) 
Acts 
Sept. 22, 1922 
Mar. 3, 1925 
June 26, 1934; 
Aug. 30, 1935' 
Mar. 2, 1945 
Sept. 3, 1954 
May 20, 1826 
June 23, 1866 
June 23, 1874 
June 3, 1896 
Mar. 3, 1899 
Mar. 3, 1909 
June 6, 1900 
June 13, 1902 
Mar. 2, 1907 
Mar. 2, 1907' 
June 25, 1910 
July 25, 1912 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935" 
Aug. 30, 1935 
AUTHORIZING LEGISLATION 
32-32 
Work Authorized 
Widening channel at foot of Maryland St., Buffalo. 
Widening canal south of International Bridge and 
removal of westerly end of Rattlesnake Island shoal. 
Operation and care of improvements provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Removal of rock shoals in Lake Erie entrance to canal, 
and in canal south of Ferry Street Bridge, to 22 feet; 
enlargement of North Tonawanda turning basin; extension 
of Bird Island pier; improvement of guide pier at the 
lock; and elimination of upper 150 feet of Tonawanda 
Creek channel from the project. 
Widening Lake Erie entrance to canal. 
Deepen lower 1,500 feet of Tonawanda inner harbor and 
enlarge turning basin. 
BUFFALO HARBOR, N.Y. (See Section 3 of Text) 
Construction of south pier (extended in 1868)" 
Construction of old breakwater." 
Extension of old breakwater." 
Stony Point and south breakwater." 
North breakwater." 
Deepening entrance channel to inner harbor and 
removing rock shoal therein. 
Dredging at entrance to canals at South Buffalo in 
outer harbor.' 
South entrance breakwater." 
Extension of Federal project to Commercial St. and 
removal of Watson elevator site. 9 
Deepening areas A, B, and D in outer harbor to 21 
feet, and area C in north entrance to 23 feet. 
Deepening areas F and G in outer harbor to 21 feet. 
Removal of shoal between entrance channel to Buffalo 
River and Erie Basin to 21 feet. 
Deepening areas H, I, and K in outer harbor to 21 feet. 
Extension of south entrance and south breakwaters, 
deepening outer harbor to present project dimensions, 
and removal of shoals on approach to south entrance. 
Maintenance of channels in Buffalo River and Buffalo 
ship canal to 21 feet, in cooperation with city of 
Buffalo. 
Documents 
H. Doc. 981, 66th Cong., 3d sess. 
H. Doc. 289, 68th Cong., 1st sess. 
H. Doc. 28, 73d Cong., 1st sess. 
H. Doc. 92, 79th Cong., 1st sess." 
H. Doc. 423, 83rd Cong., 2d sess.;'" 
Annual Report, 1868, pp. 222 and 
232. 
Annual Report, 1868, pp. 232-236. 
Annual Report, 1876, pt. 2, pp. 569 
and 573. 
Annual Report, 1895, p. 3153. 
H. Doc. 72, 55th Cong., 1st sess., 
and Annual Report, 1897, p. 3245. 
Specified in acts. 
Specified in act. 
H. Doc. 240, 59th Cong., 1st sess. 
H. Doc. 298, Rivers and Harbors 
Committee Doc. 2, 61st Cong., 
2d sess. 
H. Doc. 550, 62d Cong., 2d sess. 
H. Doc. 1139, 64th Cong., 1st sess. 
H. Doc. 481, 68th Cong., 2d sess. 
Rivers and Harbors Committee Doc. 1, 
71st Cong., 1st sess. 
H. Doc. 46, 73d Cong., 1st sess. 
Rivers and Harbors Committee Doc. 54, 
74th Cong., 1st sess.

BUFFALO, N.Y., DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
July 14, 1960 
Oct. 23, 1962 
Part of east breakwater.9 
Extension of east breakwater. 9 
Reconstruction of piers. 9 
Dredging channel between piers and outer harbor to 
depth of 19 feet; dredging to depth of 23 feet in 
any portion of harbor in discretion of Secretary of 
War. 
Arrowhead breakwater and extension of east breakwater. 
Removal of deflecting arm of old east breakwater and 
closure of gap between old and new east breakwaters. 
Pierhead at easterly end of east breakwater. 
Maintenance and improvement of channels in Cuyahoga and 
Old Rivers to a depth of 21 feet to a point 2,000 
feet upstream from Clark Ave. viaduct and 18-foot 
turning basin. 
Deepening outer harbor and channel between piers to 
present project dimensions, construction of 400-foot 
spur breakwater at gap in shore arm of west 
breakwater; removal of easterly 150 feet of west main 
breakwater; elimination from project of a 298-foot 
southerly extension of west pier; and abandonment of 
inner 932 feet of shore arm of west breakwater. 
H. Doc. 352, 78th Cong., 1st sess." 
H. Doc. 151, 86th Cong., 1st sess. 
H. Doc., 451, 87th Cong., 2d seas. 
Deepening North and Buffalo River entrance channels, 
and deepening and maintaining Buffalo River and 
Buffalo ship canal to present project dimensions. 
Deepening approach to south entrance channel to 30 
feet; deepen to 30 feet in outer area and 29 feet in 
inner area of south entrance channel; and deepen to 
28 feet southerly part of outer harbor. 
Deepening portion of outer harbor to 27 feet over a 
width of 500 feet for 2,500 feet northward from 
28-foot project area, widening within 1,700 feet to 
limits within 150 feet of breakwater axis and 75 feet 
from harbor line and continuing within these limits 
for 7,000 feet. Elimination of 25-foot wide strip 
between presently authorized and proposed easterly 
dredging limits. Elimination of easterly 50-foot 
wide undredged strip in existing 23-foot depth 
project area, extending northerly from 27-foot 
depth area to Buffalo River entrance channel. 
Previously authorized but uncompleted portions of 
work authorized by 1935 act, combined with this 
act as a single improvement. 
CAPE VINCENT HARBOR, N.Y. (See Section 4 of Text) 
Breakwater 1,000 feet long, and shore arm not to exceed 
150 feet. 
Deepening to project dimensions; elimination from 
project of uncompleted portion of breakwater. 
CLEVELAND HARBOR, OHIO (See Section 6 of Text) 
West breakwater. 
32-33 
Annual Report, 1897, pp.3286-3288. 
H. Doc. 363, 76th Cong., 1st sess.' 
Annual Report, 1876, p. 558. 
H. Ex. Doc. 116, 48th Cong., 2d sess., 
and Annual Report, 1886, p. 1865. 
H. Ex. Doc. 189, 50th Cong., 1st sess., 
and Annual Report, 1888, p. 2005. 
H. Doc. 326, 54th Cong., 1st sess., 
and Annual Report, 1896, p. 2949. 
H. Doc. 156, 55th Cong., 3d seas., 
and Annual Report, 1899, pp. 3075 
and 3078. 
H. Doc. 118, 56th Cong., 2d seas. 
No printed report. 
H. Doc. 891, 63d Cong., 2d seas. 
H. Doc. 707, 63d Cong., 2d seas., 
and Rivers and Harbors Committee 
Doc. 84, 74th Cong., 2d seas. 
H. Doc. 477, 72d Cong., 2d seas. 
Mar. 3, 1899 
Mar. 2, 1945 
Mar. 3, 1875 
Aug. 5, 1886 
Aug. 11, 1888 
June 3, 1896 
Mar. 3, 1899 
June 13, 1902 
June 13, 1902 
Mar. 2, 1907 
June 25, 1910 
July 27, 1916 
Aug. 8, 1917 
Aug. 29, 1937 
Aug. 30, 1935"12

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935": 
Mar. 2, 1945 
July 24, 1946 
July 3, 1958 
July 14, 1960 
Oct. 23, 1962 
Dec. 6, 1966 
June 25, 1910 
Aug. 8, 1917 
Maintenance dredging in Cuyahoga and Old Rivers for 
1 year as an emergency measure. 
Maintenance of extension of Cuyahoga River channel. 
Extension, maintenance, and improvement to a depth of 
21 feet of Cuyahoga River channel to present project 
limit."' 6 
Improvement of Cuyahoga and Old Rivers to a depth of 
23 feet and replacement or pier construction of 7 
railroad bridges. 
Deepening channel 25 feet through east basin of outer 
harbor; replacement of Erie-Lackawanna Railroad 
bridge over Cuyahoga River at mile 4.1 and 
widening of channel at that point, with elimination 
of reconstruction of east pier of bridge as 
previously authorized; and replacement of Baltimore 
& Ohio Railroad bridge over Old River near its mouth 
and Willow Avenue Highway Bridge about 800 feet 
above mouth and widening channel at four locations 
along lower 2,000 feet of river. 
Depth of 29 feet in lake approach to main entrance; 
28 feet in entrance channel to lakeward ends of 
piers at mouth of Cuyahoga River; 27 feet in river 
to a point just above its junction with Old River, 
and in Old River to upstream limit of present 
23-foot project; 28 feet in west basin within 
existing project limits as modified to eliminate a 
triangular area at west end and to extend limits to 
a line parallel to and 75 feet from harbor line; 
and 28 feet in westerly 800 feet of east basin. 
An area in east basin 27 feet deep extending about 
3,800 feet easterly of 28-foot area with project 
limits 380 feet from east breakwater and on 
landward side generally by a line 75 feet lakeward 
of and parallel to harbor line. A dock channel to 
Nicholson Cleveland Terminal Co. pier, at easterly 
end of east basin, from 25-foot contour to a limit 
75 feet north of pierhead line, 400 feet wide at 
shoreward end and flared toward the lake. 
Deepening upper end of Old River channel from 21 to 
27 feet. 
CONNEAUT HARBOR, OHIO (See Section 7 of Text) 
Extension of east breakwater, construction of new west 
breakwater; removal of portion of old west breakwater; 
and dredging of outer harbor to 19 feet. 
Realinement of west breakwater; removal of remainder of 
old west breakwater, and deepening outer harbor to 
20 feet. 
Removal of Bessemer & Lake Erie R.R. Co. of inner 
635 feet of west pier. 
Removal of a portion of west breakwater; extension of 
breakwaters to present project dimensions; 
construction of pierheads on outer ends of 
breakwaters; deepening outer harbor to present 
project dimensions; removal of portions of river 
pier, and elimination from project of a 255-foot 
shoreward extension of west breakwater. 
H. Doc. 48, 73d Cong., 1st sess. 
32-34 
Rivers and Harbors Committee 
Doc. 39, 74th Cong., 1st sess. 
Specified in act. 
H. Doc. 95, 79th Cong., 1st sess. 
H. Doc. 629, 79th Cong., 2d sess. 4 
H. Doc. 107, 85th Cong., 1st sess. 
H. Doc. 152, 86th Cong., 1st sess. 
H. Doc. 527, 87th Cong., 2d sess.' 
Sec. 107, 1960 River and Harbor Act 
H. Doc. 653, 61st Cong., 2d sess. 
H. Doc. 983, 64th Cong., 1st sess. 
Aug. 30, 1935"

BUFFALO, N.Y., DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 H. Doc. 415, 87th Cong., 2d sess. 
H. Doc. 484, 89th Cong., 2d sess.' 
Deepening easterly part of outer harbor to 28 feet in 
soft material and 29 feet in hard material; deepening 
remaining triangular area of outer harbor to 22 feet 
in soft material and 23 feet in hard material; 
deepening inner harbor for 2,450 feet upstream of 
outer end of west pier to 27 feet in soft material 
and 28 feet in hard material; removal of east pier; 
extension of east breakwater to shore; and an access 
channel 8 feet deep in outer harbor to city dock. 
Previously authorized but uncompleted portion of 
work authorized by 1917 and 1935 acts combined with 
this act for accompllishment as a single improvement. 
Recreational small-boat harbor provided by: a stone 
dike about 2,200 feet long; access channels 6 feet 
deep, 2,800 feet long and 100 feet wide; closing of 
100-foot gap in existing west breakwater; and 
personnel guard rail on west breakwater. 
DUNKIRK HARBOR, N.Y. (See Section 8 of Text) 
Construction of west pier. 9 
1' 
8 
Breakwater and excavation of entrance channel to 13 feet." 
Deepening of entrance channel and harbor basin to a 
depth suitable for vessels of 16-foot draft. 
Removal of rock reef bordering the inner entrance 
channel. 
Deepening outer entrance channel to present project 
depths; removal of rock shoal on the west side of the 
entrance channel to a depth of 17 feet, and changed 
limits of the inner entrance channel and basin to 
present project dimensions. 
Dec. 15, 1970 Con. 
(House Public Works Comm.) 
June 22, 1971 
(Senate Public Works Comm.) 
Sec. 201 of F.C. Act of 1965 
struction of small boat harbor. H. Doc. 91-423, 91st Cong., 
2d sess. 
ERIE HARBOR, PA. (See Section 9 of Text) 
Breakwaters and piers; dredging entrance channel; and 
brushwqod protection of beach of Presque Isle 
Peninsula. 9 
Deepening channel and harbor basin to 18 feet; repair 
and extension of piers; and plant growth and - 
emergency protection work on peninsula. 
Deepening channel and part of harbor to 20 feet. 
Reconveyed Presque Isle Peninsula to the State of 
Pennsylvania for park purposes. 
Deepening, widening, and straightening entrance channel, 
dredging channel at easterly end of harbor basin, 
deepening a portion of harbor basin, all to present 
project dimensions; elimination of north breakwater 
from project; and limitation of south breakwater to 
a length of 1,200 feet. 
Annual Report, 1915, p. 1965. 
H. Doc. 70, 55th Cong., 1st sess. 
and Annual Report, 1896, p. 3237.' 9 
Rivers and Harbors Cpmmittee Doc. 
26, 61st Cong., 2d sess. 
H. Doc. 52, 73d Cong., 1st sess. 
32-35 
S. Ex. Doc. 42, 35th Cong., 1st sess., 
and Annual Report, 1866, pt. IV, 
p. 155. 
Annual Report, 1871, p. 214. 
H. Doc. 63, 54th Cong., 1st sess. 
H. Doc. 720, 61st Cong., 2d sess.' 
H. Doc. 632, 80th Cong., 2d sess. 
Nov. 7, 1966 
Mar. 2, 1827 
Mar. 2, 1867 
June 3, 1896 
June 25, 1910 
June 30, 1948 
May 26, 1824 
Mar. 3, 1899 
June 15, 1910 
Nov. 28, 192220 
Aug. 30, 1935

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 23, 1962 
Construction of piers and breakwater.9 
H. Doc. 735, 79th Cong., 2d sess. 
Specified in act. 
H. Doc. 345, 83d Cong., 2d sess. 
H. Doc. 199, 86th Cong., 1st sess.' 
H. Doc. 340, 87th Cong., 2d sess.' 
Approach channel and turning basin to the westerly docks. 
Protection of the peninsula south of the waterworks 
settling basin. 
Widen 25-foot deep approach channel to ore dock. 
Depth of 29 feet in the entrance channel to a point 
opposite the inner end of the north pier; thence 28 
feet in soft and 29 feet in hard material in the 
remainder of the entrance channel, within the general 
limits of the 25-foot basin and inner channel 
opposite the ore dock except as modified to eliminate 
from the project a triangular area along the easterly 
side; and a depth of 28 feet over a 300-foot 
westward extension of the 25-foot basin. 
Depth of 27 feet in soft material and 28 feet in hard 
material in approach area to Duquesne Marine 
Terminal. Previously authorized but uncompleted 
portion of work authorized by 1935 act is combined 
with this act as a single improvement. 
FAIRPORT HARBOR, OHIO (See Section 10 of Text) 
Construction of piers. 
Breakwaters and dredging outer harbor to a depth of 
18 feet. 
1,400-foot extension of east breakwater, present 
project dimension of east pier; and deepening of 
harbor to 19 feet. 
4,000-foot extension of east breakwater at limit of 
cost to the United States of $715,000. 
Deepening of outer harbor and entrance channel to 
present project dimensions; extending the west 
breakwater to present project dimensions with 
pierhead at its outer end; removal of west pier; 
and construction of bulkhead on west side of river 
channel. 
Dredging of 21- and 24-foot river channels and 
turning basin in Grand River to present project 
dimensions. 
Dredging of 8-foot river channel. 
Depth of 29 feet in the approach channel from the lake; 
a depth of 28 feet over a width of 800 feet in the 
outer harbor; a depth of 27 feet in soft and 28"feet 
in hard material in Grand River, over a width of 200 
feet to the upstream limit of the turning basin, with 
suitable widening at the bends, thence over widths 
reducing from 200 to 100 feet to the upstream limit 
of the existing Federal project, except in the 8-foot 
channel; enlargement of the turning basin, including 
deepening of the entire basin to 21 feet; and minor 
modification of the existing project limits in the 
outer harbor. 
GREAT SODUS BAY HARBOR, N.Y. (See Section 11 of Text) 
Annual Report, 1876, pt. II, p. 589. 
32-36 
Annual Report, 1889, pp. 2147-2153. 
H. Doc. 347, 54th Cong., 1st sess., 
and Annual Reports, 1896, p. 2956; 
1903, p. 2084; 1905, p. 2349. 
H. Doc. 206, 63d Cong., 1st sess. 
H. Doc. 592, 69th Cong., 2d sess., 
Rivers and Harbors Committee Doc. 
13, 70th Cong., 1st sess. 
H. Doc. 472, 72d Cong., 2d sess. 
Rivers and Harbors Committee Doc. 
79, 74th Cong., 2d sess.' 
H. Doc. 706, 79th Cong., 2d sess.' 
H. Doc. 347, 86th Cong., 2d sess.' 
Mar. 3, 1825 
June 3, 1896 
Mar. 3, 1905 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935"22 
Aug. 26, 1937 
July 24, 1946 
July 14, 1960 
Mar. 2, 1829

BUFFALO, N.Y., DISTRICT 
TABLE 32-B (Continued) 
Acts 
Aug. 2, 1882 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 1935 
Oct. 23, 1962 
Mar. 3, 1905 
Mar. 2, 1919 
Aug. 30, 193522 
Oct. 23, 1962 
Aug. 30, 1852 
June 23, 1866 
Mar. 3, 1871 
Mar. 3, 1881 
June 13, 1902 
Mar. 3, 1899 
Mar. 2, 1907 
June 25, 1910 
AUTHORIZING LEGISLATION 
32-37 
Work Authorized 
Extension of piers to 15-foot contour in the lake. 
Deepening and widening of channel to 18-foot depth and 
150-foot width. 
Widening channel lakeward of piers to 250 feet. 
Dredging channel to present project dimensions. 
Deepening lake approach channel from lake to piers; 
entrance channel 24 feet deep between piers to deep 
water bayward of piers and an inner channel 22 feet 
deep and 200 feet wide in bay to turning basin at 
coal dock. 
HURON HARBOR, OHIO (See Section 12 of Text) 
Extension of west pier; construction of east breakwater; 
removal of part of old east pier; deepening of channel 
to 19 feet; and dredging of sheltered area. 
Widening river to 200 feet; removal of remainder of old 
east pier; construction of new spur pier; enlargement 
of sheltered area; and closure of breach at shore end 
of west pier. 
Extension of west pier with pierhead at its outer end; 
removal of outer end of east breakwater and 
constructing pierhead on new outer end; widening and 
deepening channel to present project dimensions; 
enlargement of turning basin at head of channel; 
shore protection west of west pier; and elimination 
from project construction of spur pier and dredging 
sheltered area outside channel limits. 
Depths of 29 feet in approach channel, 28 feet in 
entrance channel, 27 feet in river channel, 21 feet 
in turning basin, a detached breakwater 1,575 feet 
long 2,000 feet lakeward of outer end of existing 
west pier; and, abandonment of lakeward end of 
existing approach channel. 
LITTLE SODUS BAY HARBOR, N.Y. (See Section 14 of Text) 
West entrance pier.' 
Extension of west pier and construction of west 
breakwater, and dredging channel 12 feet deep, 
400 feet wide.9 
East pier and east breakwater.' 
Extension of piers lakeward to 15.5-foot contour, and 
dredging channel to 15.5 feet. 
Extension of east pier 300 feet lakeward. 
LORAIN HARBOR, OHIO (See Section 15 of Text) 
Breakwaters and extensions of piers to present dimensions. 
Extend 18-foot channel from inner end of piers to Erie 
Avenue Bridge. 
Extend breakwaters and dredge to depth of 19 feet in outer 
harbor. 
Documents 
Annual Report, 1881, p. 2442. 
H. Doc. 192, 68th Cong., 1st sess. 
Rivers and Harbors Committee Doc. 17, 
70th Cong., 1st sess. 
Rivers and Harbors Committee Doc. 23, 
72d Cong., 1st sess. 
H. Doc. 138, 87th Cong., 1st sess. 
H. Doc. 122, 58th Cong., 2d sess. 
H. Doc. 5, 63d Cong., 1st sess. 
H. Doc. 478, 72d Cong., 2d sess. 
H. Doc. 165, 87th Cong., 1st sess.' 
Annual Report, 1874, p. 256. 
Annual Report, 1874, p. 256. 
Annual Report, 1871, p. 234. 
Annual Report, 1881, pp. 2444 and 
2446. 
Annual Report, 1901, p. 3364. 
H. Doc. 131, 55th Cong., 2d sess. 
and Annual Report, 1898, p. 2718. 
H. Doc. 560, 60th Cong., 1st sess. 
H. Doc. 644, 61st Cong., 2d sess.

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 32-B (Continued) 
Acts 
Aug. 8, 1917 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Mar. 2, 1945 
July 14, 1960 
Oct. 27, 1965 
July 11, 1870 
Mar. 2, 1907 
July 3, 1930 
Aug. 30, 1935 
Oct. 17, 1940 
June 30, 1948 
AUTHORIZING LEGISLATION 
Work Authorized 
Extend breakwaters to present project dimensions. 
Deepen outer harbor and river channel to Erie Avenue 
Bridge to 20 feet. 
Extend 20-foot channel to American Shipbuilding Co. 
drydock 2. 
Widen 2 bends in river and enlarge turning basin opposite 
National Tube Co. dock. 2 
Approach channel to municipal pier. 
Deepen outer harbor and river channel to American 
Shipbuilding Co. drydock 2 to present project 
dimensions and extension of river channel to upper 
end of National Tube Co. dock with turning basin 
opposite that dock. Maintenance dredging in Black River 
from American Shipbuilding Co. drydock 2 upper end of 
National Tube Co. dock was authorized Apr. 7, 1934, by 
Public Works Administration. 
Enlarging turning basin opposite National Tube Co. dock 
to present project dimensions. 
Turning basin in bend of Black River immediately 
upstream from Baltimore & Ohio RR coal dock. 
Replace Norfolk and Western Railway swing bridge with a 
vertical lift bridge; construct two detached arrowhead 
breakwaters lakeward of existing breakwaters; construct 
extension of east breakwater to shore; remove 300 feet 
of lakeward end of west breakwater; remove outer 1,100 
feet of east pier; deepen lake approach to 29 feet, 
800-foot wide outer harbor channel to 28 feet, 
southwesterly portion of outer harbor to 25 feet and 
river channel to 27 feet; widen river channel at bends; 
and construct a new turning basin 21 feet deep near 
upstream limit of existing project. 
Construct bank of stabilization works at cut numbered 1 along 
left bank of river channel above Erie Avenue Bridge. 
OSWEGO HARBOR, N.Y. (See Section 17 of Text) 
Construction of outer west breakwater.9 
Repair of outer west breakwater under Plan (A). 9 
Construction of arrowhead breakwaters; deepening outer 
harbor between arrowhead breakwaters, west outer 
harbor east of Erie-Lackawanna coal dock, and Oswego 
River north of Seneca St., to 21 feet; and deepening 
west outer harbor, west of Erie-Lackawanna coal dock, 
to 16 feet. 24 
Widening channel to harbor lines in Oswego River north 
of Seneca St. 
Closing gap in west breakwater; deepening west outer 
harbor, west of east line of Erie-Lackawanna coal 
dock, to project depth. 
Construction of east outer breakwater; removal of inner 
end of east arrowhead breakwater; and dredging 
channel and basin in east outer harbor.25 
Documents 
H. Doc. 980, 64th Cong., 1st sess. 
H. Doc. 985, 64th Cong., 1st sess. 
H. Doc. 587, 69th Cong., 2d sess. 
H. Doc. 469, 72d Cong., 2d sess. 
Senate Committee print, 73d Cong., 
2d sess. 
Rivers and Harbors Committee Doc. 51, 
74th Cong., 1st sess. 
Specified in act. 
H. Doc. 161, 77th Cong., 1st sess. 
H. Doc. 166, 86th Cong., 1st sess.' 
PL 89-298. 
-Annual Report, 1870, pp. 54, 220, 
and 221. 
H. Doc. 55, 58th Cong., 2d sess. 
Rivers and Harbors Committee Doc. 24, 
71st Cong., 2d sess. 
Rivers and Harbors Committee Doc. 7, 
74th Cong., 1st sess. 
H. Doc. 96, 76th Cong., 1st sess. 
H. Doc. 722, 80th Cong., 2d sess. 
32-38 
--

BUFFALO, N.Y., DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 3, 1954 
Oct. 23, 1962 
H. Doc. 487, 81st Cong., 2d sess. 
H. Doc. 471, 87th Cong., 2d sess. 
Construction of detached breakwater at harbor entrance 
and removal of shoals in approach to harbor entrance 
to 25 feet deep. 
Depth of 27 feet in lake approach channel; 25 feet deep 
in outer harbor channel 800 feet wide from entrance 
gap to a turning basin 25 feet deep about 750 by 
1,100 feet, at mouth of Oswego River; depth of 24 
feet in earth and 25 feet in hard material in river 
channel from turning basin to upstream end of Port 
of Oswego Authority's east side terminal, a distance 
of about 1,600 feet; relocation of Federal project 
limits in Oswego River upstream of 24-foot channel 
to Federal project limit at north line of West Seneca 
St., on lines parallel to 50 feet channel ward of 
established harbor lines; elimination of maintenance 
of inner west breakwater; and, elimination of modification 
authorized by River and Harbor Act of 1948. 
ROCHESTER HARBOR, N.Y. (See Section 18 of Text) 
Construction of piers.' 
Extension of piers to 15 foot contour in the lake.' 
Concrete superstructure on piers.9 
Deepening channel to 20 feet. 
Dredging of the entrance channel and turning basin, and 
the elimination of the inner ends of the east and west 
piers, all to present project dimensions. 
Maintenance of the existing channel upstream of the 
Penn Central Co. bridge. 
Depth of 24 feet in the channel from the lake to the west 
pier; a depth of 23 feet between the piers and in the 
lower river to the Penn Central Co. bridge, including 
the existing turning basin; a depth of 21 feet from the 
bridge to the upstream project limit, with suitable 
widening at the bends; and, an upstream turning basin 
21 feet deep and 650 feet wide adjacent to the improved 
channel, with two mooring dolphins. 
ROCKY RIVER HARBOR, OHIO (See Section 19 of Text) 
East pier and dredging of channel. 
Extension of east pier and deepening channel to present 
project dimensions. 
Realign and extend channel and construct an anchorage 
basin. 
SANDUSKY HARBOR, OHIO (See Section 20 of Text) 
Construction of channel protection works. 
Widening of straight and dock channels and deepening to 
19 feet. 
Extension of east jetty to total length of 6,000 feet, 
with pierhead on outer end; deepening of the outer, 
straight, and easterly portion of dock channels to 
21 feet, and westerly portion of dock channel to 
20 feet. 
Annual Report, 1871, p. 211. 
H. Doc. 70, 75th Cong., 1st sess. 
H. Doc. 352, 88th Cong., 2d sess.' 
H. Doc. 362, 55th Cong., 2d sess., 
and Annual Report, 1898, p. 2708. 
H. Doc. 120, 56th Cong., 2d sess. 
H. Doc. 982, 64th Cong., 1st sess. 
32-39 
Annual Report, 1874, p. 247. 
Annual Report, 1881, p. 2437. 
Annual Report, 1905, p. 2383. 
H. Doc. 342, 61st Cong., 2d sess. 
H. Doc. 484, 72d Cong., 2d sess.' 
H. Doc. 139, 76th Cong., 1st sess. 
H. Doc. 409, 86th Cong., 2d sess.' 
Mar. 2, 1829 
Aug. 2, 1882 
June 25, 1910 
Aug. 30, 1935" 
Mar. 2, 1945 
July 14, 1960 
June 10, 1872 
Aug. 26, 1937 
Oct. 27, 1965 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1919

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 32-B (Continued) 
Acts 
Jan. 21, 1927, 
Aug. 30, 1935" 
Mar. 2, 1945 
July 14, 1960 
July 4, 1836 
Mar. 3, 1875 
Mar. 3, 1905 
July 3, 1958 
Mar. 2, 1945 
Aug. 13, 1968 
Sept. 3, 1954 
July 14, 1960 
Mar. 7, 1974 
AUTHORIZING LEGISLATION 
. . 
32-40 
Work Authorized 
Deepening of dock channel to 22 feet. 
Enlargement of turning basin and construction 
of rock dike. 
Maintenance of bay channel to 22 feet; and elimination 
from project of portion of turning basin and rock dike. 
Extending Moseley channel and deepening that channel and 
the outer end of Straight channel to 26 feet, from deep 
water in the lake to the vicinity of Cedar Point dock; 
widening the bend at the junction of the Moseley and 
Straight channels and deepening to 26 feet; deepening 
the Straight Channel to 25 feet from the vicinity of 
Cedar Point dock to junction with Bay channel; 
deepening the Bay channel from junction with the 
Straight channel to the outer end of the Pennsylvania 
coal dock No. 3 to 25 feet, thence from outer end of 
the coal dock to the turning basin to 24 feet in soft 
material and 25 feet in hard, with no Federal 
dredging within 50 feet of the dock; and enlarging 
the turning basin, including removal of approximately 
300 feet of the rock dike, and deepening to 24 feet 
in soft material and 25 feet in hard. 
VERMILION HARBOR, OHIO (See Section 21 of Text) 
Parallel piers and dredging channel to 8 feet deep. 
Deepening of channel to 12 feet. 
Reconstruction of piers. 
New entrance formed by two overlapping arrowhead 
breakwaters and extension of existing river channel 
upstream to Liberty St. Bridge. 
WILSON HARBOR, N.Y. (See Section 22 of Text) 
Entrance channel 80 feet wide and 8 feet deep; and 
restore east and west piers. 
Extend existing channel 300 feet; and construct new 
channel 3,800 feet long through Tuscarora Bay. 
PRESQUE ISLE PENINSULA, ERIE, PA. (See Section 28 of Text) 
Construction of groin system, seawall, bulkhead, 
placement of beach material at waterworks reservation 
and along remainder of peninsula; removal of portions 
of existing structures. 
Periodic nourishment of shore for a 10-year period. 
Periodic nourishment of shore for a 5-year period. 
Documents 
H. Doe. 584, 69th Cong., 2d sess. 
Rivers and Harbors Committee Doc. 2, 
73d Cong., 1st sess. 
H. Doc. 328, 76th Cong., 1st sess. 
H. Doc. 144, 86th Cong., 1st sess." 
Annual Report, 1880, p. 2122. 
Annual Report, 1874, p. 219. 
H. Doc. 252, 58th Cong., 2d sess. 
H. Doc. 231, 85th Cong., 1st sess. 
H. Doc. 679, 76th Cong., 3d sess. 
H. Doc. 112, 90th Cong., 1st sess. 
H. Doc. 231, 83d Cong., 1st sess. 
H. Doc. 397, 86th Cong., 2d sess. 
H. Doc. 796, 93d Cong., 2d sess. ___

BUFFALO, N.Y., DISTRICT 
TABLE 32-B (Continued) AUTHORIZING LEGISLATION 
1. Authorized by Public Works Administration, Sept. 6, 
1933.
2. Removal of 250 feet of inner east breakwater is to be 
restudied. 
3. Deepening of triangular-shaped area in the harbor adjacent 
to inner breakwater is to be restudied. 
4. Contains latest published map. 
5. Permanent Appropriations Repeal Act. 
6. Authorized May 28, 1935 by Emergency Relief Administration 
Act of 1935. 
7. Improvement of guide pier at Black Rock lock is considered 
to be inactive. 
8. To be restudied. 
9. Completed under previous projects. 
10. Also Sundry Civil Act of Mar. 3, 1905. 
11. Authorized in part by Public Works Administration, 
Sept. 6, 1933. 
12. Authorized by Public Works Administration Sept. 6, 
1933. 
13. Previously authorized by Public Works Administration. 
14. First Deficiency Appropriation Act approved April 1, 
1944. 
15. Authorized by Defense Plant Corp., May 19, 1942. 
16. Deepening left half of channel extension considered inactive. 
17. Permit of Secretary of War, Aug. 5, 1927. 
18. Modified 1828 and 1852. 
19. Extension of north pier portion of this modification is to 
be restudied. : 
20. Public 366. 
21. Modified 1830, 1881, and 1890. New work completed 
under previous projects. 
22. Partly included in Public Works Administration 
program, Nov. 15, 1933. 
23. First supplemental National Defense Appropriation 
Act, 1944, approved Dec. 23, 1943. 
24. Deepening a 200-foot strip along harbor line east of 
.mouth of Oswego River is considered inactive. 
25. Modification eliminated by River and Harbor Act of 
Oct. 26, 1962. 
26. Included in Public Works Administration program, 
Nov. 15, 1933. 
32-41

TABLE 32-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 25 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Aquatic Plant Control 1974 1,137 
Barcelona Harbor, N.Y.9 1973 1,193,08316 14,940 
Big (Cunningham) Creek, Ohio' 2 19,7633 
Black River Harbor, N.Y. ' -2 42,401 
Cattaraugus Creek, N.Y. _ 2 57,410 - 
Elk Creek, Pa. - - - 
Geneva-on-the-Lake, Ohio - - - 
Grand View Bay, N.Y.e 1948 1,524 - 
Grasse River (Massena) N.Y.' 7 1891 9,000 - 
Hamlin Beach Harbor, N.Y.6 1973 72,052 - 
Little River at 
Cayuga Island, N.Y.9 1969 46,804A 42,355 
Morristown Harbor, N.Y. 1949 6,2219 9,20212 
Niagara Remedial Works, N.Y. 9 ,10 1966 6,069,395 510,819 
Niagara River, N.Y. 1966 559,45711 138,163 
Ogdensburg Harbor, N.Y. 1973 646,466 738,935 
Olcott Harbor, N.Y. 1974 141,710'" 598,011'" 
Port Bay, N.Y.6 
Port Ontario Harbor, N.Y. 1949 56,904 - 
Pultneyville Harbor, N.Y.'3 1934 68,219 20,087 
Sackets Harbor, N.Y.4 1948 25,01015 2,639 
Sandusky River, Ohio4 1894 58,0003 557 
1. No commerce reported. 
2. Only information available is in index to reports of Chief 
of Engineers. 
3. Amount includes maintenance; not separable. 
4. Abandonment recommended in H. Doc. 467, 69th Cong., 
1st Sess. 
5. Abandonment recommended in Exc. Doc. 16, 35th Cong., 
1st Sess. 
6. To be restudied. 
7. Channel improved by local interests. 
8. Includes local interests contribution of $25,742. 
9. Completed. 
10. Costs of operation and maintenance of this project will be 
settled directly by concerned power agencies. No further appropriations 
will be made to this project. 
11. Includes local interests contribution of $27,563. 
12. Includes local interests contribution of $5,000. 
13. Abandonment recommended in H. Doc. 375, 64th Cong., 
1st Sess. 
14. Inactive. Completion not warranted by present navigation 
traffic. 
15. Includes costs of previous project. 
16. Includes local interests contribution of $7,500. 
17. Includes local interests contribution of $1,500. 
18. Includes local interests contribution of $5,000 and $186,- 
000 Public Works Acceleration Act funds. 
32-42

BUFFALO, N.Y., DISTRICT 
TABLE 32-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
(See Section 29 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cleveland and Lakewood, Ohio: 
Edgewater Park' - - 
White City Park' - - 
Fair Haven Beach State Park, 
Lake Ontario, N.Y.2 
Fort Niagara State Park, N.Y. 3- 
Selkirk Shores State Park, 
Lake Ontario, N.Y.' 1963 58,978 2,898 
Sheffield Lake Community 
Park, Ohio5 
1. Project authorized by River and Harbor Act of 
September 3, 1954 is classified as deferred for restudy. 
2. Project authorized by River and Harbor Act of July 3, 
1954 is classified as deferred for restudy. 
3. Project authorized under provisions of Section 201, 1965 
Flood Control Act. 
4. Federal participation was limited to one-third of first cost 
when project was authorized by 1954 River and Harbor Act. 
Federal participation was changed from one-third to 70 percent 
of remaining work under Public Law 87-874. Uncompleted portion 
of project is classified as deferred for restudy. 
5. Project authorized by River and Harbor Act of October 
23, 1962 is classified inactive. 
32-43

TABLE 32-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 40 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Auburn, N.Y., Owasco Outlet' 1962 371,985- 
Batavia and vicinity, Tonawanda Creek, 
N.Y.' 1957 335,385 - 
Caledonia, Genesee River, N.Y. 1950 - - 
Chittenango Creek and tributaries, 
N.Y.'' 1948 12,464 - 
Dansville and vicinity, Genesee River, N.Y. 1956 12,800 - 
Hammondsport, Oswego River Basin, N.Y.2 1951 18,691"- 
Ithaca, Oswego River Basin, N.Y.: 
Deferred-Cascadilla Creek2 1950 8,159 - 
Deferred-Fall Creek' 1950 12,300 - 
Lackawanna, N.Y., Smokes Creek' 1971 3,538,360"- 
Lancaster, Cayuga Creek, N.Y.' 1954 797,300 - 
Marsh Creek, Geneva, N.Y.'e -226,429 - 
Montour Falls, Oswego River Basin, N.Y.' 1954 1,681,785 - 
Onondaga Creek, Nedrow, N.Y.' 6 1964 330,231 - 
Owasco Inlet and Outlet, Montville and Dry 
Creek, State Ditch and Crane Brook, 
N.Y." 1950 281,559 - 
Syracuse, Oswego River Basin, N.Y.' 1954 3,349,248 - 
Warsaw, N.Y., Oatka Creek' 86 1969 558,317'" 
Watkins Glen, Oswego River Basin, N.Y.' 1958 43,182 - 
1. Completed. project rehabilitation as a result of damages due to storm 
2. To be restudied. Agnes, June 1972. 
3. Local interests required to contribute $25,000. 8. Excludes costs of $6,766 under Public Law 84-99, Flood 
4. Project not considered economically justified and is inac- Control and Coastal Emergencies Appropriation, incurred for 
tive. project rehabilitation as a result of damages due to storm 
5. Inactive portion of work for State ditch has been done by Agnes, June 1972. 
local interests and work on Crane Brook has been deferred at 9. Includes local interests contribution of $48,000. 
the request of local interests. 10. Excludes costs of $26,807 under Public Law 84-99. Flood 
6. Project authorized by Chief of Engineers. Control and Coastal Emergencies Appropriation, incurred for 
7. Excludes costs of $188,732 under Public Law 84-99, Flood project rehabilitation as a result of damages due to storm 
Control and Coastal Emergencies Appropriation, incurred for Agnes, June 1972. 
TABLE 32-F FLOOD PLAIN INFORMATION REPORTS COMPLETED DURING 
FISCAL YEAR 
Location Requesting Agency Date Federal 
Completed Cost 
Cuyahoga River, Ohio Ohio Department of Sep. 1974 $26,000 
Portage County Natural Resources 
Irondequoit Creek, N.Y. New York State Department of .Apr. 1975 61,000 
Environmental Conservation 
Rocky River, Ohio Ohio Department of Oct. 1974 28,000 
East Branch Natural Resources 
32-44

LOS ANGELES, CALIF., DISTRICT* 
This district (total area, about 226,000 square 
miles) comprises those drainage basins tributary 
to the Pacific Ocean that are in California 
between the Mexican boundary and Cape San 
Martin (about 265 miles north of entrance to Los 
Angeles Harbor); lower Colorado River drainage 
basin (below Lee Ferry, Ariz.), which is in 
southeastern California, southeastern Nevada, 
southwestern Utah, western New Mexico, and all 
of Arizona, except the northeastern corner; that 
part of the Great Basin that is in southern Nevada 
and southeastern California; and the United 
States parts of those small drainage basins in 
southern Arizona and southwestern New Mexico 
west of the Continental Divide that drain 
southward into Mexico. 
IMPROVEMENTS 
Navigation 
1. Channel Islands Harbor, 
Calif. ... .. .............. 
2. Morro Bay Harbor, Calif ...... 
3. Oceanside Harbor, Calif ...... 
4. Port Hueneme, Calif ........... 
5. Port San Luis, Calif. .......... 
6. San Diego Harbor, Calif ...... 
7. Santa Barbara Harbor, 
Calif. ......................... 
8. Ventura Marina, Calif. ........ 
9. Reconnaissance and condition 
surveys ....................... 
10. Other authorized navigation 
projects ..................... 
Beach Erosion Control 
11. Imperial Beach, San Diego County, 
Calif ........................ 
12. Inspection of completed beach 
erosion control projects ........ 
13. Other authorized beach erosion 
control projects . .'........ 
14. Beach erosion control work 
under special authorization .... 
Flood Control 
15. Alamo Lake, Bill Williams River, 
A riz ......................... 
16. Cucamonga Creek, Santa Ana 
River Basin, Calif. ............ 
Page Flood Control (cont.) 
17. Gila River Basin, Ariz.: ....... 
33-2 17A. Indian Bend Wash, Ariz. ...... 
33-3 17B. Lower Gila River levee and 
33-3 channel improvements (Gila 
33-4 River and tributaries 
33-5 downstream from Painted Rock 
33-6 Dam), Ariz. ................... 
17C. Painted Rock Dam (Gila River), 
33-7 Ariz. ........................ 
33-7 17D. Phoenix, Ariz., and vicinity 
(including New River) ......... 
33-8 17E. Santa Rosa Wash (Tat 
Momolikot Dam and Lake St. 
33-8 Clair), Ariz. ................... 
17F. Whitlow Ranch Dam, Queen 
Creek, Ariz. .................. 
18. Los Angeles County drainage 
area, Calif .................... 
33-8 19. Lytle and Warm Creeks, Santa 
Ana River Basin, Calif. ........ 
33-8 20. Mojave River Dam, Mojave 
River Basin, Calif. ............ 
33-8 21. Pine and Mathews Canyons 
Dams, Colorado River Basin, 
Nev. .................. 
33-8 22. San Diego River (Mission 
Valley), San Diego River Basin, 
Calif. ....................... 
23. Santa Ana River Basin (and 
Orange County), Calif. ......... 
24. Santa Paula Creek channel 
33-8 and debris basins (including 
Mud Creek), Santa Clara River 
33-9 Basin, Calif. ............. 
*All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
33-1 
Page 
33-10 
33-10 
33-10 
33-10 
33-11 
33-11 
33-12 
33-12 
33-15 
33-15 
33-16. 
33-16 
33-17 
33-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Flood Control (cont.) Page 
25. Sweetwater River, Sweetwater 
River Basin, Calif. ............ 33-18 
26. Tijuana River Basin, 
Calif. ......................... 33-18 
27. University Wash and Spring Brook, 
Riverside, Calif .............. 33-18 
28. Inspection of completed flood 
control projects ............... 33-19 
29. Scheduling flood control reservoir 
operations ................... 33-19 
Flood Control (cont.) 
30. Other authorized flood control 
projects ....................... 
31. Flood control work under special 
authorization ................. 
General Investigations 
32. Surveys ........ .... 
33. Collection and study of basic 
data .......................... 
34. Research and development .... 
Navigation 
1. CHANNEL ISLANDS HARBOR, 
CALIF. 
Location. On coast of southern California about 
a mile northwest of existing harbor of Port 
Hueneme, 65 miles northwest of Los Angeles 
Harbor, and 345 miles south of San Francisco. 
(See Coast and Geodetic Survey Charts 5007 and 
5202.) 
Existing project. A harbor for light-draft 
vessels and beach erosion control works. Ventura 
County, sponsor of project, requested modification 
of document plan of harbor improvement and 
submitted a modified plan that was approved and 
adopted by Chief of Engineers in 1957. The harbor, 
which provides facilities for berthing and 
servicing about 640 small craft and commercial 
fishing boats, includes an entrance channel 20 
feet deep, 300 feet wide, and 1,650 feet longprotected 
by two parallel entrance jetties 1,270 
and 1,300 feet long; an entrance basin 20 feet 
deep, 300 to 750 feet wide, and 1,750 feet long; an 
inner basin 10 feet deep, 900 to 1,400 feet wide, 
and 1,200 to 2,000 feet long; and a side basin 10 
feet deep, 100 to 250 feet wide, and 900 feet long. 
About 6,238,000 cubic yards of dredged material 
from entrance channel, interior basins, and sand 
trap were deposited in feeder-beach area to 
restore downcoast shoreline. A 2,300-foot-long 
offshore breakwater was placed to form a sand 
trap in conjunction with jetties. About 2,000,000 
cubic yards of material are to be dredged each 
biennium from sand trap formed by jetties and 
breakwater. This material will be deposited 
along the downcoast shoreline as long as the area 
remains under Federal ownership or use and requires 
beach erosion control. Plane of reference is 
mean lower low water. Range between mean 
lower low water and mean higher high water is 
5.4 feet. Extreme range is about 8.5 feet. Federal 
first cost of new work on completed project as 
modified was $5,123,345 (excluding $1,361,668 
Navy funds and cost to Coast Guard for installation 
of aids to navigation). Map of modified plan is 
in "Design Memorandum No. 1, General Design 
for Harbor and Shore Protection Works Near 
Port Hueneme, California," prepared by Los 
Angeles District in May 1957. The U.S. Navy is to 
bear 19 percent of the cost of maintenance dredging. 
(See table 33-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A 4-lane launch ramp and 2 
public docks for outdoor motorboats and 
sailboats; paved parking for 200 car trailers; dry 
storage for 200 boats on land; 1,500 boats in slips 
in 5 marinas, with restroom and shower facilities; 
a 3-ton hoist and a 1-ton hoist; 2 boat-repair 
facilities, with a 35-ton hoist (yard and boatways 
for boats up to 100 tons, including facilities for 
repairing and manufacturing boats up to 75 feet 
long); fueling facility; sport-fishing facilities; 3 
restaurants; 670 marina apartments, with 262 
adjoining slips; 175 motel units; 3 yacht club 
buildings; a harbor administration building; 
transient docks, with 35 slips; a 4-lane bridge, 
with a span about 29 feet above sea level for boats 
traversing the harbor to the marina development; 
and a marine sales emporium center, with 500 
boat slips. Completed additional widening of east 
channel in September 1972. A private marina 
development, immediately north of Channel 
Islands Harbor, is constructing 350 waterfront 
homes, with docking facilities, and is constructing 
an additional 250 waterfront homesites. 
Planning for construction of a new public launch 
ramp is under way. An additional 120 apartment 
units are near completion. Several new streets 
and a public park and restrooms are scheduled 
for completion in 1974-75. 
33-2 
Page 
33-19 
33-19 
33-19 
33-19 
33-20

LOS ANGELES, CALIF., DISTRICT 
Operations and results during fiscal year. 
Awarded contract for maintenance dredging. 
Condition at end of fiscal year. Construction 
was started in February 1959. Construction of 
north and south jetties was completed in June and 
September 1959, respectively. Construction of 
detached breakwater was completed in October 
1960. Original harbor dredging was completed in 
August 1961. Last biennial maintenance dredging 
was completed in April 1974. Contract for 
maintenance dredging was awarded in June 
1975. 
2. MORRO BAY HARBOR, 
CALIF. 
Location. On coast of southern California 110 
miles south of Monterey Bay, 120 miles northwest 
of Santa Barbara Harbor, and nearly midway 
between San Francisco and Los Angeles. (See 
Coast and Geodetic Survey Chart 5387.) 
Existing project. Two randomstone entrance 
breakwaters-the upcoast breakwater extending 
1,885 feet south by west from Morro Rock and the 
downcoast breakwater extending west from 
sandspit 1,399 feet, thence northwest 433 feet, a 
total distance of 1,832 feet; an entrance channel 
16 feet deep, 350 feet wide, and 2,500 feet long; a 
Navy channel 16 feet deep, ranging in width from 
350 to 800 feet from entrance channel to City of 
Morro Bay, and 4,500 feet long;, Morro channel 
from City of Morro Bay to lower bay 12 feet deep, 
generally 150 feet wide, and 5,300 feet long; a 
stone dike extending 1,600 feet from Morro Rock 
to mainland; a quarry-waste revetment levee extending 
6,930 feet along waterfront at Morro Bay 
to retain marginal fills; and a stone groin 1,000 
feet long. A rehabilitation plan, to replace 
project-document plan, was approved in August 
1961. Deteriorated structures and channels were 
restored to substantially the dimensions existing 
at completion of original construction, except 
that reconstructed breakwater is 100 feet 
bayward of original alinement and has flatter 
side slopes and heavier armor stone. Breakwater 
head is a trapezoidal prismoid constructed of 
monolithic concrete. Plane of reference is mean 
lower low water. Range between mean lower low 
water and mean higher high water is 5.4 feet. Extreme 
range is about 8.5 feet. Federal first cost 
for new work for completed project was $2,612,- 
093 Navy funds. Federal first cost for rehabilitation 
was $2,128,411. A map of rehabilitation plan 
as approved is in "Design Memorandum, General 
Design for Rehabilitation of North Breakwater 
and Continuing Maintenance of Morro Bay Harbor, 
Near Morro Bay, California," prepared by 
Los Angeles District in December 1960 and revised 
in August 1961. (See table 33-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. None 
required under rehabilitation plan. 
Terminal facilities. Facilities, which are adequate 
for existing commerce, comprise 640 feet of 
existing piers constructed by Navy; 550 feet of 
piers and 150 feet of floating docks constructed by 
San Luis Obispo County; 263 feet of floating docks 
constructed by California Department of Parks 
and Recreation; 732 feet of floating docks constructed 
by City of Morro Bay; 1,348 feet of 
privately owned piers; and 5,315 feet of privately 
owned floating docks. 
Operations and results during fiscal year. 
Completed maintenance dredging at a cost of 
$350,246 regular funds. 
Condition at end of fiscal year. Existing project 
was completed in March 1946. Downcoast 
breakwater and stone dike connecting Morro 
Rock and mainland were completed in 1942; 
retaining levee, marginal fills along waterfront, 
and channel to lower bay, in 1944; the upcoast 
(Morro) breakwater, in 1946; and navigation 
channels were dredged to project dimensions and 
stone groin 800 feet long was constructed in 
August 1956. Rehabilitation work, consisting of 
reconstruction of Morro breakwater, was completed 
in June 1964. Maintenance dredging to 
restore harbor to authorized depths and extension 
of stone groin by 200 feet were completed in 
October 1964. Last maintenance dredging was 
completed in November 1974. 
3. OCEANSIDE HARBOR, CALIF. 
Location. On coast of southern California at 
Oceanside, about 30 miles north of City of San 
Diego. (See Coast and Geodetic Survey Chart 
5101.) 
Existing project. Maintenance of general 
navigation features of Del Mar Boat Basin constructed 
by U.S. Navy and of Oceanside Harbor 
constructed by local interests. These features include 
approach channel common to Del Mar Boat 
Basin and to Oceanside Harbor 700 feetlong, 750 
feet wide, and 20 feet deep; and entrance channel 
to Del Mar Boat Basin 3,800 feet long and 20 feet 
deep, with widths ranging from 300 to 400 feet. 
Other features, which involve Oceanside Harbor 
only, are (a) entrance channel 2,000 feet long, 250 
feet wide, and 20 feet deep; (b) irregularly shaped 
turning basin 400 feet maximum width, 900 feet 
long, and 20 feet deep; (c) a south harbor channel 
ranging from 100 to 150 feet wide, 1,950 feet long, 
and 15 feet deep; (d) a north harbor channel with 
33-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
widths up to 400 feet, 850 feet long, and 10 feet 
deep; (e) 1,000 feet of a south jetty 1,375 feet long; 
(f) a north groin 710 feet long; and (g) 1,200 feet of 
stone revetment adjacent to turning basin and entrance 
channel. Plane of reference is mean lower 
low water. Range between mean lower low water 
and mean higher high water is 5.3 feet. Extreme 
range is about 10.0 feet. The cost of maintenance 
dredging is to be borne equally by the U.S. Navy 
and the Corps of Engineers. (See table 33-B for 
authorizing legislation.) 
Local cooperation. Fully complied with for 
maintenance to date. 
Terminal facilities. Storage for about 759 boats 
(690 berths plus end-of-dock ties); transient 
berthing for about 50 boats; a fuel dock; a boat 
hoist; a launching ramp, which can accommodate 
4 launchings at the same time; parking for 1,400 
cars; temporary parking for about 144 boat 
trailers; a boat-repair facility; a pump-out facility; 
and a Coast Guard cutter. 
Operations and results during fiscal year. Administered 
right-of-way acquisition continued by 
local interests. Awarded contract for 
maintenance dredging. Initiated and completed 
maintenance dredging at a cost of $510,997 
regular funds. 
Condition at end offiscal year. The groin extension 
was completed in June 1968 and the jetty extension 
was completed in July 1968. South jetty 
sealing was completed in August 1968. Contract 
for maintenance dredging was awarded in October 
1974. Last maintenance dredging was completed 
in January 1975. Work remaining consists 
of completing administration of right-of-way acquisition 
by local interests, as required. 
4. PORT HUENEME, CALIF. 
Location. On coast of southern California about 
65 miles northwest of Los Angeles and Long 
Beach Harbors, about 1 mile southeast of Channel 
Islands Harbor, immediately west of the City of 
Port Hueneme, 4 miles southwest of the City of 
Oxnard, and 10 miles southeast of the City of Ventura. 
Existing project. Plan provides for adoption 
and maintenance of existing harbor for deepdraft 
vessels at Port Hueneme, constructed by 
local interests and subsequently acquired by the 
U.S. Navy, consisting of a west jetty about 800 
feet long; an eastjetty about 1,000 feet long; an approach 
channel about 800 feet long, 600 feet wide, 
and 40 feet deep; an entrance channel about 1,550 
feet long, 330 feet wide, and 36 feet deep; a central 
basin 1,080 feet long, 1,025 feet wide, and 32 feet 
deep; and a channel (channel A) 1,850 feet long, 
150 feet wide, and 32 feet deep. It further 
provides that the central basin be deepened to 35 
feet and that channel A be improved by lengthening 
it to 2,830 feet, widening it to 275 feet, and 
deepening it to 35 feet. Plane of reference is mean 
lower low water. Range between mean lower low 
water and mean higher high water is about 5.4 
feet. Extreme range is about 10.0 feet. Latest approved 
estimated (1974) first cost for project is 
$2,334,000 ($1,720,000 Federal and $614,000 non- 
Federal). (See table 33-B for authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way not already 
owned by the United States for construction and 
subsequent maintenance of project and for aids to 
navigation upon request of the Chief of 
Engineers, including suitable spoil-disposal 
areas and necessary retaining dikes, bulkheads, 
and embankments therefor or cost of such retaining 
works; provide and maintain adequate public 
terminal and transfer facilities, open to all on 
equal terms, in accordance with plans approved 
by the Chief of Engineers; provide and maintain 
depths in berthing areas serving the public terminals 
commensurate with depths provided in 
related project areas; accomplish such alterations 
as required in sewer, water supply, drainage, and 
other utility facilities; clear and remove all improvements 
and obstructions from the lands, 
easements, and rights-of-way provided for construction 
and subsequent maintenance of project; 
hold the United States free from damages due to 
construction and maintenance of project, including, 
but not limited to, erosion beyond the 
rights-of-way furnished; and establish 
regulations prohibiting discharge of pollutants 
into the waters of the harbor by users thereof, 
which regulations shall be in accordance with 
applicable laws or regulations of Federal, State, 
and local authorities responsible for pollution 
prevention and control. 
Terminal facilities. Oxnard Harbor District 
owns and operates terminal facilities known as 
the Port of Hueneme. A 1,800-foot-long commercial 
deep-water concrete wharf (wharf No. 1) 
provides berthing space for vessels of 35-foot 
draft at mean lower low water. A utility shallowdraft 
wharf provides 380 feet of mooring space 
along the entrance channel. Ancillary facilities 
include extensive paved and unpaved open 
storage areas; two clear span transit sheds, 
providing 80,000 square feet of covered storage 
area, with ample rail and truck loading capability; 
and an administration building. 
33-4

LOS ANGELES, CALIF., DISTRICT 
Operations and results during fiscal year. 
Awarded contract for and initiated dredging the 
central basin at a cost of $104,790 regular funds 
and $54,800 other contributed funds. Completed 
preparation of project plan and final environmental 
statement. In addition, a reconnaissance and 
condition survey was conducted at a cost of $1,- 
900. 
Condition at end offiscal year. Project plan was 
completed in July 1974. Final environmental 
statement was filed with Council on Environmental 
Quality in August 1974. Work by local interests 
on part of channel A was completed in 
May 1972. Contract for dredging the central 
basin was awarded in March 1975. Dredging the 
central basin is about 52 percent complete. 
5. PORT SAN LUIS, CALIF. 
Location. On coast of southern California at San 
Luis Obispo, 190 miles northwest of Los Angeles 
and 245 miles southeast of San Francisco. (See 
Coast and Geodetic Survey Chart 5386.) 
Existing project. A rubblemound breakwater 
with a top elevation of 6 feet above mean high 
water, a top width of 20 feet, extending 336 feet 
from Point San Luis to Whaler Island and 1,820 
feet southeast from the island, a total distance, including 
the island, of 2,401 feet. The authorized 
project, as modified in 1893 and 1898, was completed 
in August 1913. As authorized in 1965, existing 
project was renamed Port San Luis, Calif., 
and modified to provide for rehabilitation of existing 
breakwater and construction of a 1,500-foot 
extension; construction of a detached breakwater 
4,000 feet long; removal of rock pinnacles; and 
dredging. As authorized by Chief of Engineers in 
August 1970, existing project was further 
modified to provide for a south breakwater 1,600 
feet long; a detached breakwater 3,515 feet long; a 
main channel 300 feet wide, 3,800 feet long, and 
15 feet deep; a southern entrance channel 400 feet 
wide, 1,100 feet long, and 20 feet deep; a northern 
entrance channel 350 to 450 feet wide, 1,300 feet 
long, and 20 feet deep; and an anchorage area 500 
to 750 feet wide, 2,900 feet long, and 15 feet deep. 
Plane of reference is mean lower low water. 
Range between mean lower low water and mean 
higher high water is about 5.3 feet. Extreme 
range is about 9.8 feet. Approved estimated 
(1975) first cost for the modified project is $11,- 
945,000, comprising $6,535,000 Federal 
(including $25,000 for U.S. Coast Guard expenses) 
and $5,410,000 non-Federal. Map of 
modified plan is in "Design Memorandum No. 1, 
General Design for Port San Luis, California," 
prepared by Los Angeles District in August 1969. 
(See table 33-B for authorizing legislation.) 
Local cooperation. Local interests must contribute 
in cash 50 percent of first cost of detached 
breakwater; provide lands, easements, and 
rights-of-way for construction and future 
maintenance of improvements and for aids to 
navigation, including suitable spoil-disposal 
areas and necessary retaining dikes, bulkheads, 
and embankments therefor or cost of such retaining 
works; hold the United States free from 
damages due to construction and maintenance of 
project; provide and maintain adequate service 
frontage and public landing with suitable supply 
facilities, necessary mooring facilities and 
utilities, and access roads, parking areas, and 
other necessary public-use shore facilities, open 
to all on equal terms; operate a general anchorage 
area or mooring facilities with reserved spaces 
adequate for accommodation of transient boats 
and for refuge, open to all on equal terms; secure 
and hold in the public interest all lands bordering 
the development to a width sufficient for proper 
functioning ofjthe harbor; provide and maintain 
adequate public terminal and transfer facilities, 
open to all on equal terms; provide and maintain 
depths in berthing areas commensurate with 
depths provided in the related project areas; 
make such utility and other relocations or 
alterations as may be required for project purposes, 
including removal of the existing Port San 
Luis wharf; provide or arrange for suitable 
marine-repair facilities; and provide a necessary 
access road for construction of general navigation 
facilities and first-stage commercial development. 
Terminal facilities. A commercial and 
recreational pier operated by Port San Luis Harbor 
District; an oil-handling pier operated by Union 
Oil Co.; a recreational pier operated by San 
Luis Obispo County; a small U.S. Coast Guard 
pier; a dual-rail small-craft launcher; a fuel and 
float landing at a 4.5-acre parking area; marine 
elevator-ways; a mobile boat hoist pier structure; 
and a 50-ton capacity mobile boat hoist. 
Operations and results during fiscal year. 
Completed studies of a proposed modification 
developed by local interests to 1970 authorized 
modified project plan. Initiated preparation of 
supplementary project plan to 1970 authorized 
modified project plan. Initiated preparation of 
final environmental statement. In addition, a 
reconnaissance and condition survey was conducted 
at a cost of $900. 
Condition at end of fiscal year. Studies of 
proposed modification developed by local interests 
to 1970 authorized modified project plan 
were completed in June 1975. Supplementary 
project plan to 1970 authorized modified project 
33-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
plan is about 40 percent complete. Final environmental 
statement is about 75 percent complete. 
6. SAN DIEGO HARBOR, CALIF. 
Location. On coast of southern California just 
north of United States-Mexico boundary line, 
about 109 miles southeast of Los Angeles and 
Long Beach Harbors. (See Coast and Geodetic 
Survey Chart 5107.) 
Previous projects. For details, see page 1976 of 
Annual Report for 1915 and page 1642 of Annual 
Report for 1938. 
Existing project. A rubblemound jetty about 
7,500 feet long on Zuniga Shoal; an entrance 
channel 40 feet deep, 800 feet wide, and about 12,- 
000 feet long; removal of Middle Ground Shoal 
and widening entrance channel to the eastward in 
that vicinity to a depth of 36 feet; a bay channel 35 
feet deep, 2,200 feet wide, and about 17,000 feet 
long, from near Whalers Bight to Naval Air Station; 
an anchorage area north of bay channel 
1,200 feet wide, about 12,000 feet long, and 26 and 
35 feet deep in the western and eastern halves, 
respectively; an approach to 26-foot anchorage, 
triangular in shape, 26 feet deep and 800 feet 
wide; an approach to 35-foot anchorage, 
triangular in shape, 35 feet deep and 900 feet 
wide; a seaplane basin 8 feet deep, 1,500 feet wide, 
and about 12,000 feet long, landward of 
anchorage area; a turning basin 35 feet deep, opposite 
municipal piers; a channel 30 feet deep, 
1,500 to 2,500 feet wide, and about 20,000 feet 
long, in southern part of bay; a channel to 
National City and Chula Vista 20 feet deep, 200 
feet wide, and about 2,600 feet long; a seaplane 
basin in southern part of bay 10 feet deep, 5,000 to 
8,500 feet wide, and about 21,000 feet long, using 
part of dredged material to fill an area of about 
110 acres adjacent to southern end of basin; and 
an earthen dike about 7,735 feet longto divert the 
San Diego River from San Diego Bay to Mission 
Bay. Modification of existing project was 
authorized in 1968 and further modification was 
authorized by the Chief of Engineers in May 
1975, as follows: an entrance channel 42 feet deep 
and 800 feet wide, extending from deep water to 
mile 2.4, thence a channel 42 feet deep in the north 
bay, narrowing to 600 feet wide at mile 3.0 and 
continuing at the same depth and width to mile 
6.57, with additional widening on the south side of 
the bend at mile 6.0; a trapezoidal turning basin 
about 2,800 feet long, 2,900 feet wide on the 
western side and 1,900 feet wide on the eastern 
side, all as originally dredged by the Navy; additional 
widening of the north bay channel on the 
south side of the 42-foot channel at the bends at 
miles 3.0, 3.7, 4.6, and 5.3 and on the north side of 
the 42-foot channel and turning basin between 
miles 6.0 and 7.2; dredging the central bay 
channel to a depth of 40 feet between miles 7.2 and 
8.84 and to a depth of 35 feet between miles 8.84 
and 11.67, with a turning basin 40 feet deep 
between miles 8.25 and 8.84; a channel 30 feet 
deep on either side of the 40-foot-deep channel, 
generally between pierhead lines, between 
channel miles 6.8 and 8.5; deepening and extending 
the south bay channel to a depth of 35 feet 
between miles 11.67 and 12.9+, with turning 
basins 35 feet deep between miles 11.67 and 12.24 
and between miles 12.53 and 12.9+; deleting from 
the existing project the uncompleted triangular 
approaches to the 26-foot- and 35-foot-deep 
anchorage areas northward of the channel and 
adjacent to Harbor Island; and deleting from the 
existing project the undredged area at the south 
end of the seaplane basin in south bay. Plane of 
reference is mean lower low water. Range 
between mean lower low water and mean higher 
high water is 5.3 feet. Extreme range is about 9.5 
feet. Approved estimated (1975) first cost for project 
as modified is $18,244,000, comprising $14,- 
734,000 Federal (including $1,529,000 for relocation 
of Navy utilities and $5,000 for aids to 
navigation by Coast Guard) and $3,510,000 non- 
Federal. Dredging done with Navy funds in 1961 
increased depth in entrance channel from project 
depth of -40 feet mean lower low water to -42 feet 
mean lower low water. Map of modified plan is in 
"Design Memorandum No. 1, General Design for 
San Diego Harbor, San Diego County, California," 
prepared by Los Angeles District in 
February 1975. (See table 33-B for authorizing 
legislation.) 
Local cooperation. Local interests must contribute 
in cash 4.1 percent of the first cost of 
dredging, exclusive of the cost of spoil-retaining 
works, such contribution to be made in a lump 
sum prior to construction; provide all lands, 
easements, and rights-of-way for construction 
and subsequent maintenance of project and for 
aids to navigation upon request of the Chief of 
Engineers, including suitable spoil-disposal 
areas and necessary retaining dikes, bulkheads, 
and embankments therefor or cost of such retaining 
works; hold the United States free from 
damages due to construction and maintenance of 
project; provide and maintain adequate public 
terminal and transfer facilities, open to all on 
equal terms; provide and maintain depths in 
berthing areas and local access channels serving 
the terminals commensurate with depths provided 
in related project areas; accomplish such utility 
or other relocations or alterations as necessary 
for project purposes, except for such utilities as 
33-6

LOS ANGELES, CALIF., DISTRICT 
are owned by the United States Navy; and establish 
regulations prohibiting discharge of 
pollutants into the waters of the harbor by users 
thereof, which regulations shall be in accordance 
with applicable laws or regulations of Federal, 
State, and local authorities responsible for pollution 
prevention and control. 
Terminal facilities. Consist of 40,400 feet of 
wharves, exclusive of Government-owned 
wharves, of which 17,220 feet are Port District 
owned and 23,180 feet are privately owned. 
Government-owned wharves at North Island are 
restricted to military use only. 
Operations and results during fiscal year. 
Completed preparation of project plan on 1968 
modification of existing project. Completed 
preparation of final environmental statement. In 
addition, a reconnaissance and condition survey 
was conducted at a cost of $2,500. 
Condition at end of fiscal year. Project plan on 
1968 modification of existing project was completed 
in May 1975. Final environmental statement 
was filed with Council on Environmental 
Quality in May 1975. 
7. SANTA BARBARA HARBOR, 
CALIF. 
Location. On coast of southern California 90 
miles northwest of Los Angeles Harbor and 320 
miles southeast of San Francisco Harbor. (See 
Coast and Geodetic Survey Chart 5261.) t 
Existing project. Maintenance dredging of 
depths existing in 1934 in harbor formed by 
breakwater constructed by local interests. See 
page 1014 of Annual Report for 1969 for detailed 
description of 1962 authorized modification. 
Further modification was authorized in 
December 1970 (Public Law 91-611) to provide 
for dredging and maintenance of existing project 
by the United States. Also, see Annual Report for 
1971 for detailed description of previous 
authorized maintenance. Plane of reference is 
mean lower low water. Range between mean 
lower low water and mean higher high water is 
5.4 feet. Extreme range is about 10 feet. Latest 
approved estimated (1969) first cost for project as 
modified is $6,810,000, comprising $3,480,000 
Federal (including $40,000 for Coast Guard costs) 
and $3,330,000 non-Federal (including cash contribution 
of $3,320,000). Prior to adoption by Congress, 
work was authorized by Public Works Administration. 
(See table 33-B for authorizing 
legislation.) 
Local cooperation. See page 1015 of Annual 
Report for 1969 for items of local cooperation under 
1962 authorized modification of existing 
project. 
Terminal facilities. A wharf 2,000 feet long; a 
pier 335 feet long; a landing float; an open mooring 
and slip anchorage for small craft; and a 
launching ramp for small craft. The wharf, 
which is equipped with unloading facilities, is 
used for general recreational facilities. The pier 
is operated by City of Santa Barbara and is used 
for servicing pleasure craft, light commercial 
boats, and commercial fishing boats. Facilities 
are adequate for existing commerce. 
Operations and results during fiscal year. 
Awarded contract for maintenance dredging. 
Initiated maintenance dredging at a cost of $107,- 
176 regular funds. 
Condition at end of fiscal year. Contract for 
maintenance dredging was awarded in June 
1975. Maintenance dredging is about 57 percent 
complete. Last maintenance dredging was completed 
in June 1974. Work on modified project 
plan is inactive. 
8. VENTURA MARINA, CALIF. 
Location. On coast of southern California about 
65 miles northwest of the City of Los Angeles, 
about 70 miles northwest of Los Angeles and 
Long Beach Harbors, and about 6 miles 
northwest of Channel Islands Harbor. 
Existing project. Maintenance of general 
navigation features of Ventura Marina, constructed 
by local interests, consisting of a north 
jetty 1,254 feet long; a middle jetty 250 feet long; a 
south jetty 1,071 feet long; and an entrance 
channel 1,750 feet long, 300 feet wide, and 20 feet 
deep. Existing project was modified by construction 
of an offshore breakwater 1,500 feet long; 
dredging about 800,000 cubic yards to form a 
sand trap in the lee of the breakwater; and construction 
of recreational fishing facilities on the 
jetty crests. Plane of reference is mean lower low 
water. Range between mean lower low water and 
mean higher high water is 5.4 feet. Extreme 
range is about 10.2 feet. First cost of new work for 
completed project as modified was $3,420,375 
($1,711,539 Federal (excluding $40,000 for Coast 
Guard costs) and $1,708,836 non-Federal). (See 
table 33-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A fuel dock; boat-repair 
facilities, with a 25-ton travelift; 600 boat slips; a 
dry storage area for 90 boats; a 7-lane deluxe 
launch ramp; 2 yacht clubs; an international 
helicopter maintenance base; a restaurant and 
cocktail lounge; carpenter and divers shops; sport 
fishing; sightseeing cruises; yacht sales; marine 
communications; 6 public restroom buildings; an 
administration building; and paved jetties with 
handrails for sport fishing. 
33-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. 
Completed maintenance dredging of entrance 
channel and sand trap at a cost of $531,256 
regular funds. In addition, a reconnaissance and 
condition survey was conducted at a cost of $7,- 
500. 
Condition at end of fiscal year. Dredging sand 
trap was completed in December 1971. 
Breakwater construction was completed in 
February 1972. Final environmental statement 
was filed with Council on Environmental Quality 
in March 1972. Construction of recreational 
facilities was completed in February 1973. 
Maintenance dredging of entrance channel and 
sand trap was completed in August 1974. 
9. RECONNAISSANCE AND 
CONDITION SURVEYS 
See table 33-C. 
10. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See table 33-D. 
Beach Erosion Control 
11. IMPERIAL BEACH, SAN DIEGO 
COUNTY, CALIF. 
Location. On coast of southern California in San 
Diego County, at Imperial Beach. 
Existing project. Plan provides for Federal participation 
by contribution of Federal funds 
toward cost of five groins at about 1,000-foot intervals, 
most northern groin being at north end of 
existing seawall at Naval radio station. However, 
in accordance with 1956 River and Harbor Act, 
construction of any or all improvements in project 
may be undertaken by the Corps under 
arrangements explained under local cooperation. 
Approved estimated (1975) first cost for project is 
$1,630,000 ($876,000 Federal and $754,000 non- 
Federal). (See table 33-B for authorizing legislation.) 
Local cooperation. Local interests must adopt 
project plan of improvement and must also obtain 
approval of Chief of Engineers of detailed plans 
and specifications for prosecuting work prior to 
commencement by local interests; provide lands, 
easements, and rights-of-way; furnish assurances 
they will control pollution of waters to extent 
necessary to safeguard health of bathers, except 
that pollution originating from international 
sewer south of Imperial Beach; maintain protective 
and improvement measures during useful 
life of project; and maintain continued public 
ownership of shore and its administration for 
public use during useful life of project. The Corps 
may agree to construct improvement upon request 
of local interests and may upon receipt of required 
contributed funds and, if needed, advanced 
funds from local interests. 
Operations and results during fiscal year. Continued 
study of alternative plans to authorized 
project. Continued preparation of final environmental 
statement. 
Condition at end of fiscal year. Construction of 
groin No. 1 was initiated in July and completed in 
September 1959; construction of groin No. 2 was 
initiated in December 1960 and completed in 
January 1961; and construction of extension to 
groin No.1 was initiated in May and completed in 
July 1963. Project plan is about 10 percent complete. 
Final environmental statement is about 30 
percent complete. All work on groins Nos. 3, 4, 
and 5 has been postponed, pending results of 
study of alternative plans to authorized project, 
which is about 35 percent complete. 
12. INSPECTION OF COMPLETED 
BEACH EROSION CONTROL 
PROJECTS 
Inspection costs for fiscal year from regular 
funds for maintenance were $28,731. (See table 
33-E on inspection of completed beach erosion 
control projects.) 
13. OTHER AUTHORIZED BEACH 
EROSION CONTROL 
PROJECTS 
See table 33-F. 
14. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to section 
103, Public Law 87-874 (preauthorization) 
See table 33-G on beach erosion control work 
under special authorization. 
Flood Control 
15. ALAMO LAKE, BILL WILLIAMS 
RIVER, ARIZ. 
Location. About 70 miles southeast of 
Kingman, Ariz., in a narrow gorge at river mile 
39 on Bill Williams River, Ariz., a tributary of 
Colorado River. 
33-8

LOS ANGELES, CALIF., DISTRICT 
Existing project. A multiple-purpose dam and 
reservoir. Dam is a rolled-earthfill structure with 
a maximum height of 283 feet above streambed 
and a crest length of about 975 feet. Outlet works 
consist of a concrete-lined tunnel through the left 
abutment of dam; an approach channel; a 
bulkhead gate; a concrete intake structure with 
log racks at upstream tunnel portal; a control 
shaft and gate chamber just upstream from axis 
of dam; and an outlet channel that discharges into 
the river. The detached, broad-crested spillway 
with a crest length of 110 feet, Which is on the 
right abutment, consists of an unlined channel 
110 feet wide and 550 feet long excavated in rock 
and a concrete control sill at the crest. Reservoir 
has a total capacity at spillway crest of 1,045,300 
acre-feet (May 1968), including 200,000 acre-feet 
for sediment. Reservoir regulates runoff from a 
tributary area of 4,770 square miles, reducing 
flow of design flood from 317,000 cubic feet per 
second to a maximum outflow of 7,000 cubic feet 
per second. Latest approved estimated (1967) 
first cost for project is $14,780,000, all Federal. 
(See table 33-B for authorizing legislation.) 
Local cooperation. Local interests must assume 
responsibility for damage claims and adjust 
water-rights claims arising from improvement. 
In addition to providing assurances specified in 
authorizing legislation, local interests would 
limit manmade encroachment on existing 
hydraulic capacity of Bill Williams River channel 
downstream from Alamo Lake to permit maximum 
releases of 7,000 cubic feet per second from 
the reservoir. Arizona Senate Joint Resolution 
No. 1, 26th Legislature, First Regular Session, 
was signed by the Governor on March 15, 1963, to 
furnish required assurances. 
Operations and results during fiscal year. 
Maintained dam in good operating condition; continued 
acquisition of rights-of-way at a cost of 
$38,074 regular funds; administered real estate; 
and completed revision of master plan. 
Condition at end of fiscal year. Construction of 
dam and appurtenances was initiated in March 
1965 and was completed in July 1968. Fish and 
wildlife management plan was completed in 
January 1968. Work remaining consists of minor 
completion items; completing acquisition of 
rights-of-way; and completing reservoirregulation 
manual. 
16. CUCAMONGA CREEK, SANTA 
ANA RIVER BASIN, CALIF. 
Location. In and near the Cities of Upland and 
Ontario and the communities of Alta Loma, 
Cucamonga, and San Antonio Heights, San Bernardino 
and Riverside Counties, Calif. 
Existing project. Plan as modified provides for 
a debris basin on Cucamonga Creek and a concrete 
channel along Cucamonga Creek from the 
debris basin to Prado Dam; an improved San Antonio 
Heights diversion system that would include 
debris basins, concrete diversion channels, 
and a diversion levee to divert West Cucamonga 
Creek headwaters into Cucamonga Creek; a 
collection levee and a debris basin downstream 
from Demens, Thorpe, and Angalls Canyons and 
a concrete outlet channel from the debris basin to 
Cucamonga Creek; a debris basin in Deer Canyon 
and a channel along Deer Creek from the debris 
.basin to Cucamonga Creek; the Hillside debris 
basin in a canyon just west of Deer Canyon with 
an outlet channel to Deer Creek channel; improvement 
of an existing levee along the west 
bank of Day Creek to assure that flows from Day 
Canyon do not enter Deer Creek channel; 
turnouts to mitigate ground water basin 
recharge losses; landscaping appropriate for esthetic 
treatment; and recreational facilities in the 
project area. Subdrainage would be provided 
along specific reaches of the channels. Approved 
estimated (1975) first cost for project is $86,200,- 
000 ($71,000,000 Federal and $15,200,000 non- 
Federal). Map of modified plan is in "Design 
Memorandum No. 2, General Design for Flood 
Control and Recreation, Cucamonga Creek, Santa 
Ana River Basin, San Bernardino and Riverside 
Counties, California," prepared by Los 
Angeles District in June 1973. (See table 33-B for 
authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way, including 
value of lands already acquired; perform alteration 
and modification of highways, roads, streets, 
highway bridges, utilities, and irrigation and 
drainage facilities, deposit funds with the United 
States to cover cost of constructing outlets; hold 
the United States free from damages due to construction 
works and from damages arising from 
water-rights claims resulting from construction, 
operation, and maintenance of project; operate 
and maintain works after completion, including 
removal of debris (detritus) to maintain adequate 
storage capacities in debris basins; and prevent 
any encroachment that would reduce floodcarrying 
capacities of channels and levees or that 
would reduce debris-storage capacities of debris 
basins. 
Operations and results during fiscal year. 
Completed preparation of final environmental 
statement. Completed preparation of plans and 
specifications for first contract, Cucamonga 
Creek channel at Prado Dam; and awarded contract 
for construction. Initiated preparation of 
33-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
plans and specifications for second contract, 
Cucamonga Creek, Hellman Avenue to 
Remington Avenue. 
Condition at end of fiscal year. Final environmental 
statement was filed with Council on 
Environmental Quality in April 1975. Plans and 
specifications for first contract, Cucamonga 
Creek channel at Prado Dam, were completed in 
June 1975 and contract for construction was 
awarded in June 1975. Plans and specifications 
for second contract, Cucamonga Creek, Hellman 
Avenue to Remington Avenue, are about 20 percent 
complete. 
17. GILA RIVER BASIN, ARIZ. 
17A. INDIAN BEND WASH, ARIZ. 
Location. On Indian Bend Wash near 
Scottsdale, Ariz. 
Existing project. Plan provides for a concretelined 
channel extending along Indian Bend Wash 
for about 7 miles from Arizona canal to Salt 
River; two channel-inlet wing levees upstream 
from canal to divert and direct flows into channel; 
a siphon system to carry canal flow under 
channel; and a gated wasteway to divert canal 
flow into channel. Design flood of 40,000 cubic 
feet per second would be controlled by improvement. 
Approved estimated (1975) first cost for 
project is $23,650,000 ($13,200,000 Federal and 
$10,450,000 non-Federal). (See table 33-B for 
authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way, including 
spoil-disposal areas; accomplish modification or 
relocation of highways, roads, bridges, utilities, 
streets, and irrigation facilities; hold the United 
States free from damages due to construction 
works; maintain and operate works after completion; 
prevent any encroachment upon improved 
channel that would reduce its flood-carrying 
capacity; and, at least annually, notify interests 
affected that project will not provide complete 
flood protection. 
Operations and results during fiscal year. Continued 
preparation of project plan. Completed 
preparation of final environmental statement. 
Completed preparation of master plan. Initiated 
acquisition of rights-of-way. 
Condition at end of fiscal year. Project plan is 
about 95 percent complete. Final environmental 
statement was filed with Council on Environmental 
Quality in August 1974. 
17B. LOWER GILA RIVER LEVEE 
AND CHANNEL IMPROVEMENTS 
(GILA RIVER AND 
TRIBUTARIES DOWNSTREAM 
FROM PAINTED ROCK DAM), 
ARIZ. 
Location. Along lower Gila River from Texas 
Hill (river mile 66.5) to Gila siphon (river mile 
8.4). 
Existing project. Plan provides for 99 miles of 
compacted, earthfill, revetted levee-49 miles 
along right bank and 50 miles along left bank. 
Leveed channel, trapezoidal in shape, would have 
a base width of 750 feet. Improvements would accommodate 
a design discharge of 50,000 cubic 
feet per second, measured at Dome (river mile 
14). Latest approved estimated (1974) first cost 
for project is $47,800,000 ($47,100,000 Federal 
and $700,000 non-Federal). (See table 33-B for 
authorizing legislation.) 
Local cooperation. As modified by 1968 Flood 
Control Act (sec. 208, Public Law 90-483), local 
interests must make a cash contribution of $700,- 
000, to be paid either in a lump sum prior to initiation 
of construction or in installments prior to 
start of pertinent work items in accordance with 
construction schedules, except that reasonable 
value of lands, easements, rights-of-way, and 
relocations furnished by local interests shall be 
deducted from required cash contribution; hold 
the United States free from damages due to construction 
works; and maintain and operate works 
after completion. Local interests supplied 
assurances. 
Operations and results duringfiscal year. Work 
modified project plan was reclassified to "inactive" 
category because there would be a major 
reduction in project benefits from authorized 
plan of improvement. 
Condition at end of fiscal year. Final environmental 
statement is about 60 percent complete. 
Work on modified project plan was 
reclassified to "inactive" category in March 1975. 
17C. PAINTED ROCK DAM (GILA 
RIVER), ARIZ. 
Location. On Gila River (mile 126) about 20 
miles downstream from Gila Bend, Ariz., in Gila 
River Basin, which is a part of Colorado River 
Basin. 
Existing project. A rolled-earthfill dam with 
maximum height of 181 feet above streambed, 
crest length of 4,780 feet, and detached broad- 
33-10

LOS ANGELES, CALIF., DISTRICT 
crested spillway with a crest length of 610 feet; 
and a flood control reservoir with a gross capacity 
at spillway crest of 2,491,700 acre-feet (Mar. 
1953), including 200,000 acre-feet for sediment. 
Reservoir regulates runoff from a tributary area 
of 50,800 square miles, reducing flow of standard 
project flood of 300,000 cubic feet per second to a 
maximum outflow of 22,500 cubic feet per second. 
First cost of new work for completed project was 
$19,753,933, all Federal, including $130,838 for 
Code 710 recreation project. (See table 33-B for 
authorizing legislation.) 
Local cooperation. Local interests must adjust 
water-rights claims that might result from improvement 
and keep flood channel of Gila River 
downstream from Painted Rock free from encroachment. 
Operations and results during fiscal year. 
Maintained dam in good operating condition; administered 
real estate; and continued acquisition 
of rights-of-way. 
Condition at end of fiscal year. Construction of 
dam and appurtenances was initiated in 1958 and 
was completed in December 1959. Construction 
of culvert was completed in August 1967. Construction 
of recreational facilities, consisting of 
picnic tables, comfort stations, camping area, 
boat ramp, and miscellaneous items, was 
initiated in August 1972 and was completed in 
December 1972. Work remaining consists of completing 
acquisition of rights-of-way and updating 
master plan. 
17D. PHOENIX, ARIZ., AND 
VICINITY (INCLUDING NEW 
RIVER) 
Location. On Cave Creek and its tributaries and 
on Skunk Creek, Dreamy Draw, New River, and 
Agua Fria River in and adjacent to metropolitan 
Phoenix, Ariz. 
Existing project. Plan provides for four detention 
basins, one each on Cave Creek, an unnamed 
tributary of Skunk Creek, New River, and 
Dreamy Draw; Union Hills diversion channel, 
Arizona canal diversion channel, and diversion 
channel on Skunk Creek to divert floods to Adobe 
detention basin on unnamed tributary of Skunk 
Creek; and channel improvements on Cave Creek, 
Dreamy Draw, Skunk Creek, New River, and 
Agua Fria River. Plan also provides for controlling 
as much of the floodflow as possible in the 
drainage area involved; for diverting residual 
flows in Deer Valley and Cave Creek to Skunk 
Creek; and for improving Skunk Creek, New 
River, and Agua Fria River to accommodate 
those residual flows. Approved estimated (1975) 
first cost is $155,968,000 ($128,000,000 Federal 
and $27,968,000 non-Federal). (See table 33-B for 
authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way, including 
spoil-disposal areas; perform construction, 
alteration, or relocation of highways, roads, 
highway bridges, utilities, and street 
modifications; hold the United States free from 
damages due to construction works; maintain and 
operate works after completion; prevent any encroachment 
upon existing or improved channels 
or within detention basin areas that would reduce 
their flood-carrying or storage capacities; hold 
the United States free from damages arising 
from water-rights claims resulting from construction, 
maintenance, and operation of project; 
and contribute 2.3 percent of construction cost. 
Local interests supplied assurances. 
Operations and results during fiscal year. Continued 
preparation of operation and maintenance 
manual for Dreamy Draw detention basin. Continued 
preparation of project plan. Continued 
preparation of final environmental statement for 
entire project. Completed contract payment for 
construction of Dreamy Draw detention basin at 
a cost of $59,930 regular funds. 
Condition at end of fiscal year. Operation and 
maintenance manual for Dreamy Draw detention 
basin is about 75 percent complete. Project plan is 
about 92 percent complete. Final environmental 
statement for entire project is about 90 percent 
complete. Construction of Dreamy Draw detention 
basin was initiated in October 1972 and was 
completed in August 1973. Final environmental 
statement for Dreamy Draw detention basin was 
filed with Council on Environmental Quality in 
May 1972. 
17E. SANTA ROSA WASH (TAT 
MOMOLIKOT DAM AND LAKE 
ST. CLAIR), ARIZ. 
Location. On Santa Rosa Wash in Papago Indian 
Reservation and about 20 miles south of Casa 
Grande, Ariz. 
Existing project. Plan as modified provides for 
a rolled-earthfill dam with a maximum height of 
75.5 feet above streambed, a crest length of about 
12,500 feet, and a detached spillway with a crest 
length of 1,000 feet; a multiple-purpose reservoir 
with a capacity at spillway crest of 200,000 acrefeet 
(June 1968), comprising 145,000 acre-feet for 
flood control, 15,000 acre-feet for water conservation, 
and 40,000 acre-feet for sediment; and 
development of 1,640 acres of cultivated land in 
Vaiva Vo irrigation project, which is authorized 
33-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
for construction by U.S. Bureau of Indian Affairs 
on Papago Indian Reservation downstream from 
dam. Operation of reservoir would regulate 
runoff from a tributary area of 1,780 square 
miles, reducing flow of standard project flood of 
77,000 cubic feet per second to a maximum outflow 
of 4,960 cubic feet per second. Approved estimated 
(1975) Federal first cost is $12,160,000, 
including $1,560,000 Bureau of Indian Affairs 
costs. Authorized project was modified by Design 
Memorandum No. 2, approved in July 1971, 
which contains a map of modified project plan. 
(See table 33-B for authorizing legislation.) 
Local cooperation. Local interests must establish 
and enforce floodway limits and 
regulations for Santa Rosa Wash on non-Indian 
land downstream from Papago Indian Reservation 
and maintain hydraulic capacity of existing 
channel; hold United States free from damages 
(downstream from Papago Indian Reservation) 
arising from construction, operation, and 
maintenance of project for flood control and arising 
from water-rights claims resulting from construction, 
operation, and maintenance of project 
for flood control. U.S. Bureau of Indian Affairs 
would assure maintenance of hydraulic capacity 
of Santa Rosa Wash on Indian lands downstream 
from Tat Momolikot Dam; and provide for adjusting 
water-rights claims resulting from construction, 
operation, and maintenance of project 
for water conservation, fish, wildlife, and recreation 
purposes. The Papago Tribal Council would 
make available appropriate rights to lands required 
for construction of the dam and reservoir. 
Operations and results during fiscal year. 
Completed contract payment for construction of 
Tat Momolikot Dam and appurtenances. Continued 
acquisition of rights-of-way. Continued 
preparation of operation and maintenance 
manual. Initiated preparation of reservoirregulation 
manual. Costs were $77,511 for construction 
of dam and appurtenances; $8,835 for 
relocations; and $7,611 for acquisition of rightsof-
way--all regular funds. 
Condition at end of fiscal year. Construction of 
access road and modification of Highway Route 
15 were initiated in February 1972 and were completed 
in November 1972. Construction of Tat 
Momolikot Dam and appurtenances was initiated 
in September 1972 and was completed in June 
1974. Final environmental statement was filed 
with Council on Environmental Quality in June 
1971. Operation and maintenance manual is 
about 99 percent domplete. 
17F. WHITLOW RANCH DAM, 
QUEEN CREEK, ARIZ. 
Location. On Queen Creek, Ariz., a tributary of 
Gila River, about 10 miles west of Superior, Ariz. 
Existing project. A flood control dam and reservoir. 
Dam is a compacted-earthfill zoned structure 
with a maximum height of 149 feet above 
streambed and a crest length of 837 feet. Outlet 
works, which are at left abutment, consist of an 
intake structure; an ungated outlet conduit; and 
an outlet-and-diversion structure. The spillway, 
an unlined structure about 4,000 feet north of 
dam, consists of a broad-crested weir about 355 
feet long; an approach channel 1,080 feet long; 
and a downstream channel about 1,300 feet long. 
Reservoir has a total capacity at spillway crest of 
35,900 acre-feet (May 1957), of which 7,000 acrefeet 
are allocated for sediment. Reservoir 
regulates runoff from a tributary area of 143 
square miles, reducing flow of design flood from 
110,000 to 1,000 cubic feet per second. First cost 
of new work for completed project was $1,867,- 
963, all Federal, including $3,758 for Code 710 
recreation project. (See table 33-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintained dam in good operating condition; continued 
acquisition of rights-of-way; administered 
real estate; and continued preparation of 
reservoir-regulation manual. 
Condition at end of fiscal year. Construction 
was started in May 1959 and was completed in 
November 1960. Work remaining consists of completing 
acquisition of rights-of-way; completing 
reservoir-regulation manual; and updating 
master plan. 
18. LOS ANGELES COUNTY 
DRAINAGE AREA, CALIF. 
Location. Along Los Angeles and San Gabriel 
Rivers, Rio Hondo, and Ballona Creek, and 
tributaries thereof in Los Angeles County, Calif. 
Previous project. For details, see pages 1768 to 
1772 of Annual Report for 1941; page 1602 of Annual 
Report for 1942; and page 1535 of Annual 
Report for 1943. 
Existing project. Plan provides for flood control 
improvements in four stream basins in Los 
Angeles County, Calif., as follows: Los Angeles 
River Basin, San Gabriel River Basin, Rio Hondo 
Basin, and Ballona Creek Basin. Provides for 
33-12

LOS ANGELES, CALIF., DISTRICT 
protection of about 325,000 acres in densely populated 
Los Angeles County, including areas in 
Los Angeles, Pasadena, Glendale, Burbank, and 
other cities. Plan provides for construction of 5 
flood control dams (Hansen, Lopez, Santa Fe, 
Sepulveda, and Whittier Narrows); debris basins 
at mouths of 22 canyons; channel improvements 
along 101.3 miles of Los Angeles River, San 
Gabriel River, Rio Hondo, and Ballona Creek; 
and channel improvements along 193.69 miles of 
tributary channels. All units of improvement are 
physically completed in those four stream basins, 
except the one listed below, and are described in 
Annual Report for 1962. 
Unit of improvement not physically completed 
in Rio Hondo Basin is Sierra Madre Wash. Plan 
provides for the construction of about 0.8 mile of 
concrete channel on Sierra Madre Wash 
extending from inlet to existing Santa Anita 
Wash channel. (See table 33-B for authorizing 
legislation and table 33-H for estimated first costs 
for all units of improvement under existing 
project.) 
Local cooperation. Local interests must furnish 
lands and rights-of-way; bear expense of highway 
and highway-bridge modifications; hold the 
United States free from damages; and maintain 
and operate works after completion for following 
units or parts of units: 
Los Angeles River Basin: 
Blanchard Canyon 
Blue Gum Canyon 
Burbank-Eastern System 
Burbank-Western system (lower and upper) 
Caballero Creek 
Compton Creek: 
Hooper Avenue storm drain to 
Main Street 
Los Angeles River to Alameda Street 
Dead Horse Canyon and Royal 
Boulevard channel 
Haines Canyon: Plainview Avenue to 
Tujunga Wash 
Lopez Canyon diversion 
Los Angeles River channel: 
Owensmouth Avenue to Lankershim 
Boulevard 
Stewart and Gray Road to Santa Ana 
Branch, Pacific Electric 
railway bridge 
Santa Ana Branch, Pacific Electric 
railway brige to Pacific 
Ocean 
Pacoima Wash channel 
Sycamore Wash channel 
Tujunga Wash channel 
Verdugo Wash: Concord Street to 
debris basin 
Wilson Canyon and Mansfield Street channel 
Winery Canyon 
San Gabriel River Basin: 
Coyote Creek 
Emerald Wash and Live Oak Wash 
Marshall Creek 
San Gabriel River channel: 
Santa Fe Dam to Whittier Narrows Dam 
Whittier Narrows Dam to the 
Pacific Ocean 
Thompson Creek and San Jose Wash 
(including San Jose Creek) 
Walnut Creek inlet channel 
Walnut Creek system 
Rio Hondo Basin: 
Alhambra Wash channel: Valley 
Boulevard to Rio Hondo 
Arcadia Wash system 
Eaton Wash 
Rio Hondo channel: 
Peck Road to Rosemead Boulevard 
(upper) 
Whittier Narrows Dam to Los Angeles 
River (lower) 
Rubio Canyon diversion 
Santa Anita Wash 
Sawpit Wash 
Sierra Madre Villa channel 
Sierra Madre Wash 
Ballona Creek Basin: 
Ballona Creek channel downstream from 
inlet to Washington Boulevard and 
downstream from La Salle Avenue to the 
lagoon 
Benedict Canyon system 
Centinela Creek 
Sawtelle-Westwood system (including 
Sepulveda channel). 
No local cooperation is required for other units 
or parts of units in existing project. Information 
on amount expended by local interests in connection 
with existing project is in table 33-I, "Project 
Costs to June 30, 1975." 
Operations and results during fiscal year. 
Operations for units in Los Angeles River Basin: 
(a) Compton Creek: Maintained channel in good 
operating condition from Alameda Street to 
Hooper Avenue storm drain. (b) Haines Canyon: 
Maintained debris basin and channel upstream 
from Plainview Avenue in good operating condition. 
(c) Hansen Dam: Completed preparation of 
updated master plan; initiated and completed 
preparation of plans and specifications for 
recreational facilities; maintained dam in good 
operating condition; and administered real estate. 
(d) Lopez Dam: Maintained dam in good 
operating condition and administered real estate. 
33-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
(e) Los Angeles River channel, Lankershim 
Boulevard to Stewart and Gray Road: Maintained 
channel in good operating condition. (f) 
Sepulveda Dam: Maintained dam in good 
operating condition and administered real estate. 
Completed construction of recreational facilities 
at a cost of $47,231 regular funds and $47,231 required 
contributed funds. (g) Tujunga Wash 
channel: Initiated and completed preparation of 
master plan; initiated and completed preparation 
of plans and specifications for phase 1 construction 
of recreational facilities; and awarded contract 
for construction. 
Operations for units in San Gabriel River 
Basin: (a) Santa Fe Dam: Maintained dam in good 
operating condition; administered real estate; 
initiated preparation of plans and specifications 
for recreational facilities; and continued preparation 
of master plan. (b) San Gabriel River 
channel, San Gabriel Canyon to Santa Fe Dam, 
Approach channel to Santa Fe Dam (remedial 
work): Maintained channel in good operating condition. 
(c) Thompson Creek and San Jose Wash 
(including San Jose Creek): Completed paving of 
access berm along channel banks of part la of San 
Jose Creek at a cost of $106,514 regular funds. (d) 
Whittier Narrows Dam: Maintained dam in good 
operating condition; administered real estate; 
and continued preparation of reservoirregulation 
manual. Initiated preparation of plans 
and specifications for recreational facilities for 
Entrada Park and Equestrian Campground and 
area B; and initiated and completed preparation 
of plans and specifications for recreational 
facilities for nature area; area A, phase 2; and 
area E. Awarded second, third, and fourth contracts 
for and initiated construction of 
recreational facilities for nature area; area A, 
phase 2; and area E. Completed construction of 
first contract for recreational facilities, area A, 
phase 1. Costs for construction of recreational 
facilities were $660,550 regular funds and $643,- 
702 required contributed funds. 
Operations for units in Rio Hondo Basin: (a) 
Alhambra Wash: Maintained channel upstream 
from Valley Boulevard in good operating condition. 
(b) Sierra Madre Wash: Continued studies of 
modification to authorized project plan proposed 
by local interests for Sierra Madre Wash channel 
upstream from Acacia Street. 
Operations for unit in Ballona Creek Basin: 
Ballona Creek channel and jetties: Maintained 
channel downstream from Washington 
Boulevard to La Salle Avenue and downstream 
from Los Angeles city boundary to ocean, jetties, 
and Pacific Avenue bridge in good operating condition. 
Condition at end offiscal year. Revision, which 
was continued, of basic operation and 
maintenance manual for channel and debrisbasin 
units in Los Angeles County drainage area 
project is about 99 percent complete, and inserts 
are complete. 
Los Angeles River Basin: (a) Hansen Dam: 
Dam was completed in April 1940. Work remaining 
consists of completing reservoir-regulation 
manual and constructing recreational facilities. 
(b) Lopez Dam: Dam was completed in November 
1954. Work remaining consists of preparing 
reservoir-regulation manual and master plan. (c) 
Los Angeles River channel, Lankershim 
Boulevard to Stewart and Gray Road: Work 
remaining consists of constructing recreational 
facilities. (d) Sepulveda Dam: Dam was completed 
in December 1941. Recreational facilities 
were completed in October 1974. Work remaining 
consists of completing preparation of 
reservoir-regulation manual. (e) Tujunga Wash 
channel: Channel was completed in February 
1952. Work remaining consists of constructing 
recreational facilities. 
San Gabriel River Basin: (a) Santa Fe Dam: 
Dam was completed in January 1949. Work 
remaining consists of completing master plan, 
which is about 90 percent complete; completing 
reservoir-regulation manual; completing plans 
and specifications for recreational facilities; and 
constructing recreational facilities. (b) Whittier 
Narrows Dam: Dam was completed in June 1957. 
Construction of first contract for recreational 
facilities, area A, phase 1, was completed in 
March 1975. Work remaining consists of completing 
revision of operation and maintenance 
manual, which is about 40 percent complete; completing 
preparation of reservoir-regulation 
manual; completing construction of second contract 
for recreational facilities, nature area, 
which is about 99 percent complete; completing 
construction of third contract for recreational 
facilities, area A, phase 2, which is about 40 percent 
complete; completing construction of fourth 
contract for recreational facilities, area E, which 
is about 10 percent complete; and completing 
preparation of plans and specifications for and 
construction of recreational facilities for Entrada 
Park and Equestrian Campground and area B. 
Rio Hondo Basin: Work remaining consists of 
completing plans and specifications for Sierra 
Madre Wash channel upstream from Orange 
Grove Avenue, which are about 88 percent complete, 
and completing construction of unit. Work 
on this unit is being held in abeyance, pending 
results of studies of modification to authorized 
plan proposed by local interests. 
33-14

LOS ANGELES, CALIF., DISTRICT 
19. LYTLE AND WARM CREEKS, 
SANTA ANA RIVER BASIN, 
CALIF. 
Location. Near San Bernardino and Colton, 
San Bernardino County, Calif. 
Existing project. Plan as modified provides for 
a rectangular concrete channel extending for 3.5 
miles along East Branch of Lytle Creek from existing 
Foothill Boulevard inlet structure to confluence 
with Warm Creek; a concrete trapezoidal 
channel on Warm Creek for 1.5 miles from confluence 
with East Branch of Lytle Creek to confluence 
with Santa Ana River; a leveed channel 
extending about 1.8 miles along Santa Ana River 
from mouth of existing East Twin and Warm 
Creeks concrete channel to Mount Vernon 
Avenue crossing;, replacement of 4 railroad 
bridges and 12 highway bridges; 3 new highway 
bridges; inlets for side drainage; and relocation 
and protection of utilities. Design capacities of 
improvements would be: East Branch of Lytle 
Creek, 58,000 cubic feet per second; Warm Creek, 
60,000 to 90,000 cubic feet per second; and Santa 
Ana River, 167,000 to 234,000 cubic feet per 
second. Approved estimated (1975) first cost is 
$38,300,000 ($31,500,000 Federal and $6,800,000 
non-Federal). Authorized project was modified 
by Design Memorandum No. 1, approved in May 
1972, which contains a map of modified project 
plan. (See table 33-B for authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; perform 
construction, modification, or relocation of 
highways and utilities; maintain and operate 
works after completion; hold the United States 
free from damages; adjust water-rights claims 
resulting from project; and prevent any encroachment 
that would reduce flood-carrying 
capacities of levee and channel improvements. 
Operations and results during fiscal year. 
Completed construction of second contract, Lytle 
Creek channel, 5th Street to "I" Street. Completed 
construction of fourth contract, Warm 
Creek and Santa Ana River, railroad bridge 
relocations. Completed preparation of plans and 
specifications for fifth contract, Lytle Creek from 
inlet to 5th Street and Santa Ana River from Interstate 
15 to Mt. Vernon Avenue, and initiated 
construction. Initiated preparation of plans and 
specifications for sixth contract, Santa Ana 
River, East Twin and Warm Creeks to Interstate 
15. Costs for construction of channels were $2,- 
300,038 regular funds and $14,150 other contributed 
funds; and costs for relocations were $2,- 
555,215 regular funds and $343,442 other contributed 
funds. 
Condition at end of fiscal year. Construction of 
first contract, Lytle and Warm Creeks channel, 
"I" Street to Interstate 15 at Warm Creek, was 
initiated in September 1972 and was completed 
in April 1974. Construction of second contract, 
Lytle Creek channel, 5th Street to "I" Street, was 
initiated in December 1972 and was completed in 
July 1974. Construction of third contract, Warm 
Creek channel, Interstate 15 to Interstate 10, was 
initiated in July 1973 and was completed in May 
1974. Construction of fourth contract, Warm 
Creek and Santa Ana River, railroad bridge 
relocations, was initiated in March 1974 and was 
completed in June 1975. Plans and specifications 
for fifth contract were completed in March 1975. 
Construction of fifth contract, Lytle Creek from 
inlet to 5th Street and Santa Ana River from 
Interstate 15 to Mt. Vernon Avenue, initiated in 
May 1975, is about 18 percent complete. Plans 
and specifications for sixth contract are about 50 
percent complete. Final environmental 
statement was filed with Council on Environmental 
Quality in May 1972. 
20. MOJAVE RIVER DAM, 
MOJAVE RIVER BASIN, CALIF. 
Location. On Mojave River at the Forks site, 
just downstream from mouth of Deep Creek and 
about 14 miles upstream from Victorville, in Mojave 
River Basin, Calif. 
Existing project. Project as modified consists of 
a flood control dam and reservoir. Dam is a rolledearthfill 
structure with a maximum height of 200 
feet above streambed, a crest length of 2,200 feet, 
and a detached spillway with a crest length of 200 
feet. Reservoir has a total capacity at spillway 
crest of 89,700 acre-feet (1965), including 11,000 
acre-feet for sediment. Reservoir regulates 
runoff from a tributary area of 215 square miles, 
reducing flow of design flood from 94,000 cubic 
feet per second to a maximum outflow of about 
23,500 cubic feet per second. Approved estimated 
(1975) first cost for project is $18,390,000 ($18,- 
100,000 Federal and $290,000 non-Federal). 
Modification of project was authorized by the 
Chief of Engineers on November 27, 1964. (See 
table 33-B for authorizing legislation.) 
Local cooperation. Local interests must hold the 
United States free from damages from waterrights 
claims resulting from construction and 
operation of project; prevent encroachment 
harmful to existing channel downstream from 
reservoir; and maintain channel capacity of not 
less than 23,500 cubic feet per second through improved 
areas. In addition, local interests have 
agreed to operate and maintain recreational 
33-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
facilities constructed by the United States and to 
construct, operate, and maintain such future 
recreational facilities as may be required in addition 
to those constructed by the United States. 
Local interests contributed $250,000 in consideration 
of land enhancement benefits provided 
by modified project. 
Operations and results during fiscal year. 
Completed contract payment for construction of 
recreational facilities at a cost of $1,750 regular 
funds. Completed contract payment for construction 
of dam and appurtenances at a cost of $17,183 
regular funds. Initiated and completed construction 
of relocations, roads, and permanent 
operating equipment at a cost of $184,089 regular 
funds. Completed preparation of reservoirregulation 
manual. Continued acquisition of 
rights-of-way at a cost of $67,957 regular funds, 
and administered real estate. 
Condition at end of fiscal year. Construction of 
dam and appurtenances was initiated in May 
1968 and was completed in May 1971. Construction 
of recreational facilities was initiated in July 
1972 and was completed in March 1973. Construction 
of relocations, roads, and permanent 
operating equipment was initiated in August 
1974 and was completed in November 1974. Work 
remaining consists of completing acquisition of 
rights-of-way. In accordance with 2d Indorsement, 
ENGCW-OC, Office, Chief of Engineers, 
April 13, 1971, subject: "Environmental Statement, 
Mojave River Forks Recreation Area 
Project," to basic letter, January 15, 1971, the environmental 
statement for recreation is not required. 
21. PINE AND MATHEWS 
CANYONS DAMS, COLORADO 
RIVER BASIN, NEV. 
Location. In Lincoln County, Nev., about 100 
miles north of Hoover Dam and about 17 and 20 
miles, respectively, east of Caliente, Nev. 
Existing project. Reservoirs are 
interdependent units of a project for protection of 
lands and improvements against floods, each unit 
consisting of a dam and a reservoir. Operation of 
Pine Canyon Reservoir regulates runoff from a 
tributary area of 45 square miles, reducing 
standard project flood from 10,500 to 320 cubic 
feet per second. Operation of Mathews Canyon 
Reservoir regulates runoff from a tributary area 
of 34 square miles, reducing standard project 
flood from 8,500 to 260 cubic feet per second. 
First cost of new work for completed project was 
$1,401,248, all Federal. For further project 
description, see page 1355 of Annual Report for 
1967. (See table 33-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintained dams in good condition and administered 
real estate. Continued preparation of 
reservoir-regulation manual for Mathews 
Canyon Dam and completed preparation of reservoir 
regulation manual for Pine Canyon Dam. 
Condition at end of fiscal year. Construction of 
reservoirs was completed in December 1957. 
Work remaining consists of completing preparation 
of reservoir-regulation manual for Mathews 
Canyon Dam. 
22. SAN DIEGO RIVER (MISSION 
VALLEY), SAN DIEGO RIVER 
BASIN, CALIF. 
Location. Along San Diego River in Mission 
Valley, San Diego County, Calif. 
Existing project. Plan provides for about 27,500 
feet of rectangular reinforced-concrete channel 
extending from near Zion Avenue in Grantville to 
just upstream from existing flood control channel 
at Morena Boulevard; two inlet levees at upstream 
end and a transition at downstream end to 
provide a connection with existing channel; and 
short rectangular reinforced-concrete channels 
along downstream reaches of three tributary 
streams (Alvarado, Murphy, and Murray 
Canyons). Improvements would control standard 
project flood of 115,000 cubic feet per second in 
San Diego River, 17,000 cubic feet per second in 
Alvarado Canyon, 14,000 cubic feet per second in 
Murphy Canyon, and 6,000 cubic feet per second 
in Murray Canyon. Approved estimated (1975) 
first cost for project is $49,400,000 ($32,300,000 
Federal and $17,100,000 non-Federal). (See table 
33-B for authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; hold the 
United States free from damages due to construction 
works; maintain and operate works after 
completion; accomplish construction or relocation 
of highways, roads, bridges, utilities, and 
storm drains; prevent encroachment on improved 
channels that would reduce their flood-carrying 
capacities; and contribute 11.5 percent of 
construction costs. 
Operations and results during fiscal year. Continued 
preparation of reformulated project plan. 
Continued studies of alternative plans to 
authorized project to determine a definite plan 
that would be acceptable to local interests. 
Condition at end of fiscal year. Reformulated 
project plan is about 8 percent complete. 
33-16

LOS ANGELES, CALIF. DISTRICT 
23. SANTA ANA RIVER BASIN 
(AND ORANGE COUNTY), 
CALIF. 
Location. On Santa Ana River and tributaries 
and on other streams in Orange, Riverside, and 
San Bernardino Counties, Calif. 
General plan of improvement. Although a single 
comprehensive plan for flood control has been 
developed for Santa Ana River Basin, improvements 
provided are divided into two 
projects in accordance with congressional 
authorizations. Santa Ana River Basin (and 
Orange County) project, the first of these two 
projects, provides for protection of metropolitan 
area of Orange County, which includes some 
areas outside Santa Ana River Basin, and flood 
control on San Antonio, Chino, Lytle, and Cajon 
Creeks. Santa Ana River Basin project, the 
second of these two projects, provides for flood 
control in other areas of basin. Active units of first 
project are described in Annual Report for 1968. 
For pertinent information on second project, see 
table 33-L, "Other Authorized Flood Control 
Projects." 
Existing project. (See table 33-B for authorizing 
legislation and table 33-J for latest approved 
estimated Federal first cost for all units.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Operations for units in existing project: (a) Brea 
Dam: Maintained dam in good operating condition 
and administered real estate. (b) Carbon 
Canyon Dam and channel: Maintained project in 
good operating condition; administered real estate; 
initiated construction of recreational 
facilities; and awarded contract for and initiated 
construction of recreational facilities at a cost of 
$98,880 regular funds and $98,880 required contributed 
funds. Maintained dam in good 
operating condition; administered real estate; 
and completed preparation of master plan. (d) 
Prado Dam: Maintained dam in good operating 
condition; administered real estate; continued 
preparation of reservoir-regulation manual; and 
continued preparation of master plan. (e) San Antonio 
Dam: Maintained dam in good operating 
condition and administered real estate. (f) San 
Antonio and Chino Creeks channel: Maintained 
project in good operating condition; and administered 
real estate. 
Condition at end offiscal year. Work remaining 
consists of completing basic operation and 
maintenance manual, which is about 95 percent 
complete, and completing inserts for channel and 
levee improvements (Lytle and Cajon Creeks 
channel improvements and San Antonio and 
Chino Creeks channel). Other information for 
units in existing project: (a) Brea Dam: Dam was 
completed in March 1942. Work remaining consists 
of updating master plan and completing 
reservoir-regulation manual. (b) Carbon Canyon 
Dam and channel: Construction of project was 
started in May 1959 and was completed in May 
1961. Work remaining consists of completing construction 
of recreational facilities, which is about 
99 percent complete. (c) Fullerton Dam: Dam was 
completed in May 1941. Work remaining consists 
of completing construction of recreational 
facilities, which is about 20 percent complete, and 
completing reservoir-regulation manual. (d) Lytle 
and Cajon Creeks channel improvements: Existing 
project was completed in 1948 and turned 
over to local interests for maintenance in 
September 1949. No work remains. (e) Prado 
Dam: Dam was completed in May 1941. Work 
remaining consists of completing preparation of 
reservoir-regulation manual and master plan, 
which is about 60 percent complete. (f) San Antonio 
Dam: Dam was completed in October 1956. 
Work remaining consists of preparation of 
master plan. (g) San Antonio and Chino Creeks 
channel: Project was completed in November 
1960. Work remaining consists of completing 
operation and maintenance manual, which is 
about 95 percent complete. 
24. SANTA PAULA CREEK 
CHANNEL AND DEBRIS 
BASINS (INCLUDING MUD 
CREEK), SANTA CLARA RIVER 
BASIN, CALIF. 
Location. Along lower Santa Paula Creek, a 
tributary of Santa Clara River, Ventura County, 
Calif. 
Existing project. Plan as modified provides for 
a debris basin on Santa Paula Creek; a concrete 
channel along Santa Paula Creek from Santa 
Paula Creek debris basin to Santa Clara River; a 
debris basin on Mud Creek, a tributary of Santa 
Paula Creek; and a concrete channel along Mud 
Creek from Mud Creek debris basin to confluence 
with Santa Paula Creek. Approved estimated 
(1975) first cost is $19,360,000 ($17,500,000 
Federal and $1,860,000 non-Federal). Authorized 
project was modified by Design Memorandum 
No. 4, approved in April 1973, which contains a 
map of modified project plan. (See table 33-B for 
authorizing legislation.) 
Local cooperation. Local interests must furnish 
rights-of-way; assume responsibility for damage 
claims; provide cost of relocation of public 
utilities; and maintain improvement after completion. 
33-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. Terminated 
construction of second contract, Mupu 
School to Harvard Boulevard, because of a temporary 
court injunction. 
Condition at end of fiscal year. Construction of 
first contract, Harvard Boulevard to Santa Clara 
River, was initiated in August 1973 and was completed 
in February 1974. Construction of second 
contract, Mupu School to Harvard Boulevard, 
was terminated in February 1975. Final environmental 
statement was filed with Council on 
Environmental Quality in September 1972. 
25. SWEETWATER RIVER, 
SWEETWATER RIVER BASIN, 
CALIF. 
Location. Lower Sweetwater River Valley, 
along Sweetwater River from Bonita Mesa Road 
to San Diego Bay, San Diego County, Calif. 
Existing project. Plan provides for about 3.4 
miles of improved trapezoidal channel along 
Sweetwater River from Bonita Mesa Road to San 
Diego Bay as part of a combined flood control and 
highway project. Approved estimated (1975) first 
cost for project is $24,300,000 ($11,900,000 
Federal and $12,400,000 non-Federal). (See table 
33-B for authorizing legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; perform 
construction, modification, or relocation of 
highways (including bridges), utilities, and 
irrigation and drainage facilities; maintain and 
operate works after completion; hold the United 
States free from damages due to construction of 
project; adjust water-rights claims resulting 
from construction of project; and prevent any 
obstruction or encroachment that would reduce 
the flood-carrying capacity of improved channel. 
Operations and results during fiscal year. Continued 
preparation of project plan. Continued 
preparation of final environmental statement. 
Condition at end of fiscal year. Project plan is 
75 percent complete. Plans and specifications are 
about 30 percent complete. Final environmental 
statement is about 86 percent complete. 
26. TIJUANA RIVER BASIN, 
CALIF. 
Location. In the coastal region of southern 
California and Mexico. 
Existing project. Plan provides for a concrete 
trapezoidal channel for Tijuana River from its 
connection at international boundary with a 
similar flood control channel to be constructed by 
the Government of Mexico, thence along United 
States side of boundary and along base of bluffs 
skirting south side of Tijuana River Valley to 
Pacific Ocean; a gated diversion outlet for water 
spreading, with a channel to a settling basin; two 
new bridges; relocation of utilities and roads; inlets 
for side drainage; and two short jetties at 
Pacific Ocean, all to be designed and constructed 
in cooperation with United States Section of International 
Boundary and Water Commission. 
Latest approved estimated (1966) first cost (as 
authorized) for project is $12,600,000, all 
Federal. (See table 33-B for authorizing legislation.) 
Local cooperation. Provide lands, easements, 
and rights-of-way; hold the United States free 
from damages due to construction works; maintain 
and operate works after completion; accomplish 
construction or relocation of highways, 
roads, bridges, utilities, and storm drains; prevent 
encroachment on improved channels that 
would reduce their flood-carrying capacities; and 
contribute 16.1 percent of construction cost. 
Operations and results during fiscal year. Continued 
preparation of final environmental statement. 
Condition at end of fiscal year. Final environmental 
statement is about 95 percent complete. 
All work has been postponed indefinitely, 
pending instructions from International 
Boundary and Water Commission regarding 
resolution of local interests ability to provide 
necessary rights-of-way before proceeding with 
proposed modified plan. 
27. UNIVERSITY WASH AND 
SPRING BROOK, RIVERSIDE, 
CALIF. 
Location. In and near the City of Riverside, 
Riverside County, Calif. 
Existing project. Plan provides for about 2.7 
miles of rectangular concrete channel along 
University Wash from about 400 feet upstream 
from U.S. Highway No. 60 to its confluence with 
Spring Brook, and for about 2.2 miles of rectangular 
concrete channel along Spring Brook 
immediately upstream from U.S. Highway No. 
395 to its confluence with University Wash, with 
a 0.3-mile transition and revetted trapezoidal section 
that terminates at Evans Lake. Plan also 
provides for beautification features. Latest approved 
estimated (1974) first cost for project is 
$10,560,000 ($7,680,000 Federal and $2,880,000 
non-Federal). (See table 33-B for authorizing 
legislation.) 
33-18

LOS ANGELES, CALIF. DISTRICT 
Local cooperation. Provide without cost to the 
United States lands, easements, and rights-ofway 
for construction; perform alterations and 
modifications of highways, roads, streets, bridges 
(except railroad bridges), utilities, and irrigation 
and drainage facilities; hold and save the United 
States free from damages due to construction 
works; maintain and operate works after completion; 
hold and save the United States free from 
damages arising from water-rights claims 
resulting from construction, maintenance, and 
operation of project; prevent any encroachment 
or obstruction that would reduce flood-carrying 
capacities of channels, and prevent any future 
construction or obstruction upstream from 
channel improvements that would cause 
floodflows upstream from channel inlets to 
bypass improved channels; at least annually, inform 
interests affected that project will not 
provide complete flood protection; and provide 
guidance and leadership in encouraging appropriate 
flood plain management measures to 
reduce damages from floods that exceed project 
capacity and to minimize flood damages in areas 
outside the scope of protection afforded by 
project. 
Operations and results duringfiscal year. Work 
on authorized project was reclassified to "inactive" 
category because project was not 
economically justified. 
Condition at end of fiscal year. Work on 
authorized project was reclassified to "inactive" 
category in May 1975. Final environmental statement 
is about 20 percent complete. 
28. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection costs for fiscal year from regular 
funds for maintenance were $197,919. (See table 
33-K on inspection of completed flood control projects.) 
29. SCHEDULING FLOOD 
CONTROL RESERVOIR 
OPERATIONS 
In accordance with section 7, Flood Control Act 
of 1944, studies of reservoir operations for flood 
control were conducted; and preparation of 
regulations for the use of storage allocated for 
flood control was continued for the following 
Bureau of Reclamation projects: Hoover Dam 
and Twitchell Dam. Costs for fiscal year from 
regular funds for maintenance were $5,106. 
30. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 33-L. 
31. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 80-858, as amended (preauthorization) 
See table 33-M on flood control work under 
special authorization. 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation) 
Federal cost for fiscal year was $405,016, of 
which $57,642 were for advance preparation; 
$340,940 were for flood emergency operations; 
and $6,434 were for rehabilitation. 
Flood insurance activities (sections 1301-1377, 
1968 Housing and Urban Development Act, Public 
Law 90-448, as amended) 
In coordination with flood control activities, 11 
flood insurance studies were initiated in 
accordance with inter-Agency Agreement (IAA) 
H-16-75 at fiscal year cost of $346,040 under 
Housing and Urban Development reimbursable 
order. 
32. SURVEYS 
Fiscal year cost was $2,185,014 regular funds, 
of which $813,584 were for navigation studies; 
$73,788 were for beach erosion control studies; 
$1,154,369 were for flood control studies; $21,331 
were for special studies involving coordination 
with other agencies; $1,506 were for inventory of 
dams; $112,062 were for other studies; and $8,374 
were for review of authorized projects. 
33. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year cost for flood plain information 
studies was $308,423 regular funds, comprising 
$20,200 for Rio de Flag and Sinclair Wash, 
Coconino County, Ariz.; $15,000 for Little 
Colorado River, Navajo County, Ariz.; $28,638 for 
Tanque Verde Wash tributaries, Pima County, 
Ariz.; $19,016 for West Clear Creek and Sinclair 
Wash, Yavapai County, Ariz.; $24,763 for New 
River, Imperial County, Calif.; $28,679 for 
Ridgecrest and vicinity, Kern County, Calif.; $39 
for upper Peters Canyon Wash and $30,138 for 
upper San Diego Creek and tributaries, both in 
33-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Orange County, Calif.; $10,126 for San Gorgonio 
River and tributaries, Riverside County, Calif.; 
$15,281 for San Luis Obispo Creek, San Luis 
Obispo County, Calif.; $11 for Montecito streams 
and $24,550 for Santa Barbara streams group, 
both in Santa Barbara County, Calif.; $16 for 
Muddy River, vicinity of Overton, and $9,550 for 
upper Las Vegas Wash, both in Clark County, 
Nev.; $71 for Puerco River, McKinley County, N. 
Mex.; $169,927 for technical services, including 
$16,472 for Keys Canyon, $5,106 for Moosa 
Canyon, $4,509 for Otay Canyon, $15,000 for Los 
Coches Creek, and $10,000 for San Luis Rey 
River, all in San Diego County, Calif,; $82,345 for 
flood plain management; and $8,098 for guides, 
pamphlets, and support studies. Fiscal year costs 
for research and data collection in connection 
with beach erosion control studies were -$8 required 
contributed funds and -$8 from funds 
supplied by Coastal Engineering Research 
Center. (See table 33-N on completed flood plain 
information studies.) 
34. RESEARCH AND 
DEVELOPMENT 
Fiscal year cost was $26,714 for hydrologic 
studies. 
33-20

LOS ANGELES, CALIF., DISTRICT 
TABLE 33-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Channel Islands 
Harbor, Calif. 
2. Morro Bay Harbor, 
Calif. 
3. Oceanside Harbor, 
Calif.5 
4. Port Hueneme, 
Calif. (Regular 
Funds) 
Other Contrib. 
Funds) 
(Advanced Funds) 
5. Port San Luis, 
Calif. 
6. San Diego Harbor, 
Calif. 
7. Santa Barbara 
Harbor, Calif. 
8. Ventura Marina, 
Calif. (Regular 
Funds) 
11. Imperial Beach, 
Calif.(Regular 
Funds) 
(Required Contrib. 
Funds) 
(Advanced Funds) 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Advanced 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Advanced 
Cost 
$566,173 
1,102,493 
103,120 
238,051 
67,732 
93,869 
89,400 
96,595 
1,000 
1,000 
5,325 
12,474 
900 
900 
877,500 
177,659 
5,518 
10,177 
15 
298,900 
241,772 
993,100 
900,000 
305,895 
355,893 
$968,089 
63,104 
40,872 
32,944 
299,750 
252,616 
420,000 
28,703 
500 
500 
2,468 
35,000 
32,839 
500 
500 
205,408 
750 
750 
1,029 
533,698 
545,753 
750,000 
839,803 
1,281,720 
1,279,788 
60,000 
17,854 
$716,000 
1,619,022 
331,000 
258,906 
12,000 
60,130 
650,000 
412,501 
6,000 
6,000 
25,000 
28,967 
1,000 
1,000 
-87,510 
132,452 
1,000 
1,000 
401,500 
446,270 
-24,909 
-28,264 
119,000 
120,172 
61,100 
57,919 
- $5,123,3451 
- 5,123,3451 
$311,865 6,755,1922 
64,317 6,502,4682 
- 2,612,093$ 
- 2,612,0938 
339,917 3,312,5064 
419,939 3,312,506' 
- 2,128,411 
- 2,128,411 
538,482 2,056,0166 
538,759 2,056,0166 
200,000 1,419,400 
127,582 699,549 
1,900 14,2257 
1,900 14,225' 
58,088 58,088 
54,800 54,800 
- 20,000 
- 20,000 
25,000 986,4178 
25,093 986,4108 
900 68,5898 
900 68,5899 
260,000 10,589,09510 
193,485 10,239,36310 
2,500 1,079,03711 
2,500 1,079,18111 
- 172,00012 
- 172,00012 
215,200 2,598,6191a 
137,730 2,520,8461 
-6,652 1,711,53914 
- 1,711,5391 
577,236 2,905,0201' 
577,610 2,904,63215 
50,348 242,9576 
47,893 192,32616 
- 25,601 
- 25,584 
- 21,330 
- 21,309 
33-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 33-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
15. Alamo Lake, 
Bill Williams 
River, Ariz. 
16. Cucamonga Creek, 
Santa Ana River 
Basin, Calif. 
17A. Gila River 
Basin, Ariz., 
Indian Bend Wash. 
17B. Gila River Basin, 
Ariz., Lower Gila 
River L and C 
improvements (Gila 
River and 
tributaries downstream 
from Painted 
Rock Dam) 
17C. Gila River Basin, 
Ariz., Painted 
Rock Dam (Gila 
River) 
17D. Gila River Basin, 
Ariz., Phoenix, 
Ariz., and vicinity 
(including New 
RiverRegular 
Funds) 
(Required Contrib. 
Funds) 
17E. Gila River Basin, 
Ariz., Santa Rosa 
Wash (Tat 
Momolikot Dam and 
Lake St. Clair) 
17F. Gila River Basin, 
Ariz. Whitlow 
Ranch Dam, 
Queen Creek 
18. Los Angeles County 
drainage area, 
Calif. (Regular 
Funds) 
(Required Contrib. 
Funds) 
(Other Contrib. 
Funds) 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
10,000 
4,219 
154,300 
126,162 
597,100 
595,230 
198,300 
181,974 
302,000 
202,516 
304,782 
327,907 
16,000 
38,449 
213,000 
195,909 
550,000 
551,853 
165,000 
207,431 
-695,000 
152,845 
24,000 
58,108 
143,775 133,000 
113,377 147,929 
1,013,600 1,200,000 
813,477 1,249,416 
115,000 47,000 
58,198 84,371 
134,350 179,000 
188,801 179,335 
519,800 500,000 
391,150 253,845 
318,500 1,050,000 
316,598 588,746 
-215,000 - 
153,466 8,381 
-731 
962 
153,000 
164,015 
897,697 
998,263 
- 14,000 - 
713,100 5,870,000 2,748,500 
570,009 4,322,855 4,230,936 
19,925 
19,169 
198,600 
203,833 
33,800 
29,665 
232,000 
336,648 
25,650 
30,454 
514,000 
218,332 
15,907,06017 
15,886,19218 
1,016,909 
1,013,541 
2,621,900 
2,234,841 
1,869,380 
1,391,470 
2,427,600 
2,413,051 
45,000 19,758,764 19 
40,169 19,753,9332� 
285,000 1,343,018 
286,345 1,338,788 
916,000 5,202,297 
853,604 5,079,006 
- 14,000 
5 5 
- 10,524,900 
123,696 10,088,655 
- 1,867,96321 
- 1,867,96321 
28,000 
25,997 
4,114,000 
1,772,501 
188,279 
186,189 
357,773,1832 23 
355,123,5422 24 
1,873,800 1,799,876 1,101,500 2,618,500 17,017,72722 
2,043,743 1,193,829 1,950,293 1,447,947 15,751,29522 
- - 400,000 2,529,000 2,929,00025 
- - 196,565 780,528 977,09326 
-237,521 - -23,502 - 36,644,86527 
231 95 - - 36,639,88827 
33-22

LOS ANGELES, CALIF., DISTRICT 
TABLE 33-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
19. Lytle and Warm 
Creeks Santa Ana 
River basin, 
Calif. (Regular 
Funds) 
(Other Contrib. 
Funds) 
20. Mojave River Dam, 
Moave River 
Basin, Calif. 
(Regular Funds) 
(Other Contrib. 
Funds) 
21. Pine and Mathews 
Canyons Dams, 
Colorado River 
Basin, Nev. 
22. San Diego River 
(Mission Valley), 
San Diego River 
Basin, Calif. 
23. Santa Ana River 
Basin (and Orange 
County), Calif. 
(Regular Funds) 
Required Contrib. 
Funds) 
24. Santa Paula Creek 
channel and debris 
basins (including 
Mud Creek), Santa 
Clara River Basin, 
Calif. (Regular 
Funds) 
(Other Contrib. 
Funds) 
25. Sweetwater River, 
Sweetwater River 
Basin, Calif. 
26. Tijuana River 
Basin, Calif. 
27. University Wash 
and Spring Brook, 
Riverside, Calif. 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
1,697,500 8,601,000 5,569,911 4,140,000 20,993,831 
283,873 5,221,076 9,661,402 4,555,184 20,706,241 
60,000 
1,423,400 
2,549,912 
35,000 
31,457 
22,800 
18,789 
50,000 
131,851 
2,642,000 
1,530,166 
400,000 
1,750,148 
66,000 
59,785 
28 
28,800 
18,618 
-62,000 
166,244 
228,557 
1,183,071 
80,800 
196,101 
39,000 
47,114 
35,000 
44,070 
141,700 
174,527 
517,753 3,448,310 
366,592 3,079,829 
25,000 17,597,000 
290,297 17,588,598 
102,500 243,800 
102,543 242,199 
- 286,300 
- 284,302 
- 1,401,248 
- 1,401,248 
29,000 282,355 
33,386 281,524 
200,000 1,509,700 
149,205 1,457,924 
- 375,731 1,087,000 43,536,63828 29 
- 128,186 915,795 43,117,8828 298 
605,500 
519,162 
1,383,300 
288,382 
121,600 
110,553 
400,000 
141,740 
67( 
65
0,224 
5,506 
2,033,420 
334,898 
887,000 940,600 
997,050 938,015 
348,500 1,325,426 
- 1,243,421 
71,700 -411,000 
1,971,735 153,711 
- 193,600 
- 44,962 
-121,600 110,000 
208,999 111,435 
65,898 75,455 
120,000 
119,284 
7 ,3 0 3,3572 82 
7 ,2 7 2,16528 82 
1,673,92693 
1,243,42184 
3,535,02096 
3,205,8503b 
- 193,600 
- 44,962 
110,403 939,403 
121,410 939,375 
-249,971 979,029 
33,786 838,270 
112,500 232,500 
94,029 213,313 
33-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 33-A (Continued) COST AND FINANCIAL STATEMENT 
1. Excludes $1,361,668 Navy funds; Coast Guard costs; 
and $210,748 other contributed funds. 
2. Includes $6,178 for reconnaissance and condition 
surveys. Excludes $1,565,847 for maintenance accomplished 
with Navy funds. 
3. Navy funds. 
4. Includes $115,955 for reconnaissance and condition 
surveys since FY 1958 and $307,945 Navy funds. 
5. Excludes $491,286 other contributed funds for new 
work. 
6. Includes $23,330 for reconnaissance and condition 
surveys. Excludes $1,915,805 for maintenance accomplished 
with Navy funds. 
7. Includes $14,225 for reconnaissance and condition 
surveys. 
8. Includes $568,417 for new work prior to modification 
by 1965 River and Harbor Act. Excludes Coast Guard costs. 
9. Includes $54,715 for maintenance for project prior to 
modification by 1965 River and Harbor Act and $13,874 for 
reconnaissance and condition surveys. 
10. Includes $154,704 for new work for previous projects; $86,352 public works funds; and $1,226,793 emergency relief 
funds. Excludes $4,441 other contributed funds for 
betterments desired by local interests; $254,795 Navy funds 
for dredging entrance channel in FY 1961 to depth of -42 feet 
mean lower low water (or 2 feet below project depth); and 
Coast Guard costs. 
11. Includes $59,904 for maintenance for previous 
projects and $90,644 for reconnaissance and condition surveys 
since FY 1958. In addition, includes $144 for retroactive pay 
increase shown in "cost" figure only, as reported in 1958 
Annual Report, page 1430. 
12. Excludes Coast Guard costs. 
13. Includes $29,198 public works funds; $11,000 working 
funds for work performed in addition to existing project; and 
$8,275 for reconnaissance and condition surveys. Excludes 
$462,986 other contributed funds spent by the Corps for 
maintenance-dredging betterments desired by local interests. 
14. Excludes $1,708,836 required contributed funds and 
Coast Guard costs. 
15. Includes $25,785 for reconnaissance and condition 
surveys. 
16. Excludes $66,124 other contributed funds. 
17. Includes $47,000 Code 710 funds since FY 1975. 
18. Includes $46,629 Code 710 funds since FY 1975. 
19. Includes $135,669 Code 710 funds since FY 1962. 
20. Includes $130,838 Code 710 funds since FY 1962. 
21. Includes $3,758 Code 710 funds since FY 1962. 
22. Includes $11,008,935 emergency relief funds for new 
work. Excludes $16,726,888 emergency relief funds spent by 
Corps in connection with emergency relief (previous) project 
and $107,939 for minor rehabilitation. 
23. Includes $4,518,000 Code 710 funds since FY 1974 
($200,000 for Sepulveda Dam; $3,347,000 for Whittier 
Narrows Dam; $22,000 for LACDA prototype; $341,000 for 
Hansen Dam; $258,000 for Santa Fe Dam; $200,000 for 
Tujunga Wash channel; $90,000 for Lopez Dam; and $60,000 
for Los Angeles River and Rio Hondo channels). 
24. Includes $1,870,668 Code 710 funds since FY 1974 
($196,998 for Sepulveda Dam; $1,447,274 for Whittier 
Narrows Dam; $22,000 for LAdDA prototype; $95 130 for 
Hansen Dam; $55,570 for Santa Fe Dam; $43 209 for Tujunga 
Wash channel; $3,128 for Lopez Dam* and $7,359 for Los 
Angeles River and Rio Hondo channels). 
25. Includes $2,929,000 Code 710 funds since FY 1974 
($200,000 for Sepulveda Dam; $2,529,000 for Whittier 
Narrows Dam; and $200,000 for Tujunga Wash channel). 
26. Includes $977,093 Code 710 funds since FY 1974 
($199,915 for Sepulveda Dam and $777,178 for Whittier 
Narrows Dam). 
27. Non-Federal funds spent by the Federal Govenment to 
June 30, 1975, for replacements required as part of local 
cooperation and betterments desired by local interests. 
Excludes $4,238,000 other contributed funds spent by the 
Corps in connection with emergency relief (previous) project. 
28. Comprises funds for Brea, Fullerton, Prado and San 
Antonio Dams, Carbon Canyon Dam and channel, Lytle and 
Cajon Creeks channel improvements, and San Antonio and 
Chino Creeks channel (active units). 
29. Includes $5,000 working funds for San Antonio Dam; 
$67,361 for San Juan Dam (inactive unit) (also reported under 
"Other Authorized Flood Control Projects"); and $85,310 
undistributed funds. Excludes other contributed funds spent 
by the Corps as follows: $124,105 for water conservation 
betterments desired by local interests at Prado Dam; $8,500 
for betterments desired by local interests at San Antonio 
Dam; $234,709 for betterments desired by local interests on 
San Antonio and Chino Creeks channel; and $601,762 for 
required items of local cooperation on Lytle and Cajon Creeks 
channel improvements. Excludes $290,000 spent direct by 
local interests on San Antonio and Chino Creeks channel for 
local cooperation items not required. 
30. Includes $1,462,731 Code 710 funds since FY 1974 
($868,731 for Carbon Canyon Dam and channel and $594,000 
for Fullerton Dam). 
31. Includes $1,043,981 Code 710 funds since FY 1974 
($866,723 for Carbon Canyon Dam and channel and $177,258 
or Fullerton Dam). 
32. Excludes maintenance for Lytle and Cajon Creeks 
channel improvements, which are operated and maintained 
by local interests. 
33. Includes $1,673,926 Code 710 funds since FY 1974 
$1,079,926 for Carbon Canyon Dam and channel and 
594,000 for Fullerton Dam). 
34. Includes $1,243,421 Code 710 funds since FY 1975 
$1,066,324 for Carbon Canyon Dam and channel and 
177,097 for Fullerton Dam). 
35. Excludes non-Federal costs of $295,000 for local 
cooperation items not required. 
33-24

LOS ANGELES, CALIF., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
CHANNEL ISLANDS HARBOR, CALIF. (See Section 1 
of Text) 
Sept. 3, 1954 Harbor for light-draft vessels and shore protection 
works. 
MORRO BAY HARBOR, CALIF. (See Section 2 of Text) 
Mar. 2, 1945 Adoption and improvement of existing entrance channel 
to bay, a breakwater extending south by west from 
Morro Rock, and bay channels and basins at locations 
and of dimensions substantially as shown on the Navy 
Department map on file in the Office of the Chief of 
Engineers. 
OCEANSIDE HARBOR, CALIF. (See Section 3 of Text) 
Oct. 27, 1965 Maintenance of general navigation features of Del 
Mar Boat Basin and of Oceanside Harbor. 
Aug. 13, 1968 
Aug. 11, 1888 
Sept. 19, 1890 
July 13, 1892 
Aug 18, 1894 
June 3, 1896 
Mar. 3, 1899 
June 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 27, 1908 
Mar. 4, 1909 
Mar. 4, 1911 
June 23, 1913 
Oct. 27, 1965 
PORT HUENEME, CALIF. (See Section 4 of Text) 
Adoption and maintenance of existing harbor for 
deep-draft vessels; dredge central basin to 35 feet 
deep; and widen, dredge to 35 feet deep, and extend 
southernmost interior channel. 
PORT SAN LUIS, CALIF. (See Section 5 of Text) 
Breakwater. 
Authorized to be appropriated an additional 
$40,000 for continuing improvement. 
Authorized to be appropriated an additional 
$30,000 for continuing improvement. 
Authorized to be appropriated an additional 
$40,000 for continuing improvement. 
Authorized to be appropriated an additional 
$40,000 for continuing improvement. 
Authorized to be appropriated an additional 
$55,000 for continuing improvement. 
Authorized to be appropriated an additional 
$50,000 for continuing improvement. 
Authorized to be appropriated an additional 
$25,000 for continuing improvement. 
Authorized to be appropriated an additional 
$63,660 for continuing improvement. 
Authorized to be appropriated an additional 
$60,000 for continuing improvement. 
Authorized to be appropriated an additional 
$30,000 for continuing improvement. 
Authorized to be appropriated an additional 
$64,000 for continuing improvement. 
Authorized to be appropriated an additional 
$46,000 for continuing improvement. 
Renamed from San Luis Obispo Harbor to Port 
San Luis; rehabilitation of existing breakwater 
and construction of an extension; construction 
of a detached breakwater; removal of rock 
pinnacles; and dredging. 
H. Doc. 362, 83d Cong., 
2d sess. 
H. Doc. 283, 77th Cong., 
1st sess. 
H. Doc. 76, 89th Cong., 
1st sess. 
H. Doc. 362, 90th Cong., 
2d sess. 
S. Doc. 81, 49th Cong., 
2d sess. 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
H. Doc. 148, 88th Cong., 
1st sess. 
33-25 
TABLE 33-B

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 33-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
SAN DIEGO HARBOR, CALIF. (See Section 6 of Text) 
Mar. 3, 1875 Diversion dike. 
Sept. 19, 1890 Jetty on Zuniga Shoal. 
June 25, 1910 Dredge channel through outer bar 30 feet deep and 
600 feet wide, and a channel through middle ground 
to 30 feet deep. 
Mar. 4, 1913 Dredge channel through outer bar 570 feet wide and 
35 feet deep, and a channel through middle ground 
32 feet deep. 
July 27, 1916 Widen approach (area B) to San Diego municipal pier 
by dredging area C (north of area B). 
Aug. 8, 1917 Dredging area A (south of area B). 
Aug. 8, 1917 Dredge 35-foot channel through middle ground. 
Sept. 22,1922 Dredging areas D and E. 
Mar. 3, 1925 Widen approach (area C) to San Diego municipal pier 
1 by dredging a portion of area F (north of area C). 
July 3, 1930 Deepen to 40 feet channel through outer bar; along 
south and north banks, main channel; dredge 
turning basin, widen area H, and dredge a channel 
to National City and Chula Vista. 
Aug. 30, 19351 Widen bay channel to 2,200 feet with depth of 35 feet 
from the vicinity of Whalers Bight in lower bay to 
naval air station opposite turning basin. 
Aug. 26, 1937 Dredging area Q, Q-1, M, N, and 0. 
Oct. 17, 1940 Dredge a seaplane basin (area S) of about 3,000 acres, 
10 feet deep, and fill an area of about 110 acres 
adjacent to southern end of basin. 
Mar. 2, 1945 Dredge triangular approaches to 26- and 35-foot 
anchorages, area M. 
Aug. 13, 1968 Deepen and extend existing navigation channels, 
delete uncompleted parts, and extend maintenance. 
SANTA BARBARA HARBOR, CALIF. (See Section 7 of 
Text) 
Aug. 30, 1935 Maintenance dredging present depths into harbor 
formed by breakwater constructed by local interests. 
Mar. 2, 1945 Permits maintenance by means of a fixed sandintercepting 
plant to be provided and operated by and 
at expense of local interests. United States to 
contribute to operating expense an amount not to 
exceed $30,000 annually, whenever funds are allotted 
therefor; funds thus contributed to be reduced by 
actual cost of harbor maintenance if and when 
intercepting plant has been installed. 
Oct. 23, 1962 Modification of existing project. 
Dec. 31, 1970 Dredging and maintenance by United States. 
VENTURA MARINA, CALIF. (See Section 8 of Text) 
Aug. 13, 1968 Adoption and maintenance of existing general 
navigation features of harbor, excluding interior 
basins; construction of an offshore breakwater; 
dredge a sand trap in lee of breakwater; repair 
existing north and middle jetties; and construction 
of recreational fishing facilities on jetty crests. 
Annual Report, 1873; 
p. 1142 
H. Ex. Doc. 177, 50th 
Cong., 1st sess. (Annual 
Report, 1888; p. 2114) 
H. Doc. 961, 60th Cong., 
1st sess. 
H. Doc. 1309, 62d Cong., 
3d sess. 
H. Doc. 648, 64th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 8, 64th 
Cong., 2d sess. 
H. Doc. 140, 65th Cong., 
1st sess. 
H. Doc. 1000, 66th Cong., 
3d sess. 
Rivers and Harbors 
Committee Doc. 2, 68th 
Cong., 1st sess. 
S. Doc. 81, 71st Cong., 
2d sess. 
H. Doc. 223, 73d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 89, 74th 
Cong., 2d sess. 
H. Doc. 844, 76th Cong., 
3d sess. 
H. Doc. 390, 77th Cong., 
1st sess. 
H. Doc. 365, 90th Cong., 
2d sess. 
S. Committee Print, 73d 
Cong., 2d sess. 
H. Doc. 348, 77th Cong., 
1st sess. 
H. Doc. 518, 87th Cong., 
2d sess.2 
None 
H. Doc. 356, 90th Cong., 
2d sess. 
33-26

LOS ANGELES, CALIF., DISTRICT 
TABLE 33-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
IMPERIAL BEACH, CALIF. (See Section 11 of Text) 
July 3, 1958 Federal participation by contribution of Federal 
funds toward cost of five groins. 
ALAMO LAKE, BILL WILLIAMS RIVER, ARIZ. (See 
Section 15 of Text) 
Dec. 22, 1944 Multiple-purpose dam and reservoir. 
Aug. 13, 1968 
CUCAMONGA CREEK, SANTA ANA RIVER BASIN, CALIF. 
(See Section 16 of Text) 
Debris-collection facilities, with a system of 
channels, and a diversion system. 
INDIAN BEND WASH, GILA RIVER BASIN, ARIZ. (See 
Section 17A of Text) 
Oct. 27, 1965 Channel, levees, a siphon system, and transition 
works. 
LOWER GILA RIVER LEVEE AND CHANNEL 
IMPROVEMENTS (GILA RIVER AND TRIBUTARIES 
DOWNSTREAM FROM PAINTED ROCK DAM), GILA 
RIVER BASIN, ARIZ. (See Section 17B of Text) 
Oct. 23, 1962 Levees and channel. 
PAINTED ROCK DAM (GILA RIVER), GILA RIVER 
BASIN, ARIZ. (See Section 17C of Text) 
May 17, 1950 Dam and flood control basin. 
PHOENIX ARIZ., AND VICINITY (INCLUDING 
NEW RIVER) GILA RIVER BASIN, ARIZ. (See 
Section 17D of text) 
Oct. 27, 1965 Detention basins, diversion channels, and channel 
improvements. 
SANTA ROSA WASH (TAT MOMOLIKOT DAM 
AND LAKE ST. CLAIR), GILA RIVER BASIN, 
ARIZ. (See Section 17E of Text) 
Oct. 27, 1965 Multiple-purpose dam and reservoir, irrigation works, 
and recreation and fish and wildlife facilities. 
WHITLOW RANCH DAM, QUEEN CREEK, GILA 
RIVER BASIN, ARIZ. (See Section 17F of Text) 
July 24, 1946 Dam and flood control basin. 
LOS ANGELES COUNTY DRAINAGE AREA, CALIF. 
(See Section 18 of Text) 
June 22, 1936 Reservoirs and flood channels for flood control and 
related purposes at an estimated construction cost 
not to exceed $70 million. 
May 15, 1937 Added flood channels on Ballona Creek and tributaries 
to project. 
June 28, 1938 Provision of lands, easements, and rights-of-way and 
relocations by Federal Government instead of by 
local interests. (Resultant additional cost to the 
United States $12,541,000.) 
Aug. 18, 1941 Project extended to include additional flood control 
reservoirs, flood control channels, and debris basins 
for flood control and related purposes. Also 
authorized to be appropriated $25 million for further 
accomplishment of plan. 
H. Doc. 399, 84th Cong., 
2d sess. 
H. Doc. 625, 78th Cong., 
2d sess. 
H. Doc. 323, 90th Cong., 
2d sess. 
H. Doc. 303, 88th Cong., 
2d sess. 
S. Doc. 116, 87th Cong., 
2d sess. 
H. Doc. 331, 81st Cong., 
1st sess. 
H. Doc. 216, 89th Cong., 
1st sess. 
H. Doc. 189, 89th Cong., 
1st sess. 
H. Doc. 220, 80th Cong., 
1st sess. 
None 
None 
None 
H. Doc. 838, 76th Cong., 
3d sess. 
33-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 33-B (Continued) AUTHORIZING LEGISLANTION 
Acts Work Authorized Documents 
Dec. 22, 1944 Authorized to be appropriated an additional $25 million 
for prosecution of comprehensive plan approved in 
Flood Control Act of Aug. 18, 1941. 
July 24, 1946 Authorized to be appropriated an additional $25 
million for further prosecution of comprehensive 
plan. 
May 17, 1950 Rio Hondo channel improvement, Whittier Narrows 
Reservoir to Los Angeles River (in lieu of enlarging 
channel and bridges on San Gabriel River downstream 
from reservoir). Also authorized to be appropriated 
an additional $40 million for further prosecution of 
comprehensive plan. 
Sept. 3, 1954 Authorized to be appropriated an additional 
$12,500,000 for further prosecution of 
comprehensive plan. 
July 3, 1958 Authorized to be appropriated an additional 
$44 million for further prosecution of comprehensive 
plan. 
July 14, 1960 Authorized to be appropriated an additional 
$32 million for further prosecution of comprehensive 
plan. 
Oct. 23, 1962 Authorized to be appropriated an additional 
$3,700,000 for further prosecution of 
comprehensive plan. 
Dec. 30, 1963 Authorized to be appropriated an additional $30 
million for further prosecution of comprehensive 
plan. 
June 18, 1965 In addition to all previous authorizations, completion 
of improvements under the comprehensive plan for 
flood control in the Los Angeles River Basin at a 
presently estimated cost of $31 million for 
completion. 
LYTLE AND WARM CREEKS, SANTA ANA RIVER 
BASIN, CALIF. (See Section 19 of Text) 
Oct. 27, 1965 Channels and levees. 
MOJAVE RIVER DAM, MOJAVE RIVER BASIN, 
CALIF. (See Section 20 of Text) 
July 14, 1960 Dam and reservoir, and an earthfill dike. 
PINE AND MATHEWS CANYONS DAMS, COLORADO 
RIVER BASIN, NEV. (See Section 21 of Text) 
May 17, 1950 Dams and flood control basins. 
SAN DIEGO RIVER (MISSION VALLEY), SAN 
DIEGO RIVER BASIN, CALIF. (See Section 22 of Text) 
Oct 27, 1965 Channels, levees, and transition. 
June 22, 1936 
June 28, 1938 
SANTA ANA RIVER BASIN (AND ORANGE COUNTY), 
CALIF. (See Section 23 of Text) 
Reservoirs and flood channels for flood control and 
related purposes for protection of metropolitan 
area of Orange County, at an estimated construction 
cost not to exceed $13 million. 
San Antonio and Chino Creeks channel portion of 
improvement. Authorized to be appropriated $6,500,000 
for initiation and partial accomplishment of plans 
for those creeks. Rescinded provisions of Flood 
Control Act of 1936, providing that local interests 
pay for relocations, lands, easements, and rightsof-
way. (Estimated resultant additional cost to 
United States, $3,500,000.) 
None 
None 
None 
None 
None 
None 
None 
None 
None 
S. Doc. 53, 89th Cong., 
1st sess. 
H. Doc. 164, 86th Cong., 
1st sess. 
H. Doc. 530, 81st Cong., 
2d sess. 
H. Doc. 212, 89th Cong., 
1st sess. 
None 
H. Doc. 688, 75th Cong., 
3d sess. 
33-28

TABLE 33-B (Continued) 
LOS ANGELES, CALIF., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 18, 1941 Authorized to be appropriated an additional None 
$2,500,000 for prosecution of projects approved in 
above flood control acts. 
Dec. 22, 1944 Authorized to be appropriated an additional X10 H. Doc. 534, 78th Cong., 
million for prosecution of projects adopted in above- 2d sess. 
mentioned flood control acts, including projects 
on Lytle and Cajon Creeks for local flood 
protection at San Bernardino and Colton, Calif. 
July 3, 1958 Authorized to be appropriated an additional $8 None 
million for prosecution of projects approved in 
above-mentioned flood control acts. 
SANTA PAULA CREEK CHANNEL AND DEBRIS BASINS 
(INCLUDING MUD CREEK), SANTA CLARA RIVER 
BASIN, CALIF. (See Section 24 of Text) 
June 30, 1948 Channel improvement. H. Doc. 443, 80th Cong., 
1st sess. 
SWEETWATER RIVER, SWEETWATER RIVER BASIN, 
CALIF. (See Section 25 of Text) 
Aug. 13, 1968 Channel improvement, as part of a combined flood H. Doc. 148, 90th Cong., 
control and highway project. 1st sess. 
TIJUANA RIVER BASIN, CALIF. (See Section 26 of 
Text) 
Oct. 10, 1966 Channels and appurtenant works, bridges, relocations, Public Law 640, 89th Cong., 
and jetties. 2d sess. 
UNIVERSITY WASH AND SPRING BROOK, RIVERSIDE, 
CALIF. (See Section 27 of Text) 
June 22, 19711 Channels and beautification features. S. Doc. 91-116, 91st Cong., 
2d seas. 
1. Included in the emergency relief program, May 28, 
1935.
2. Contains latest published map. 
3. Final date of approval by House and Senate Public 
Works Committees resolution under provisions of section 201, 
Public Law 89-298. 
33-29

TABLE 33-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 9 of Text) 
Name of Project Date Survey Conducted 
Dana Point Harbor, Calif. July 1974-June 1975 
Los Angeles and Long Beach Harbors, Calif. July 1974-June 1975 
Marina del Rey, Los Angeles County, Calif. July 1974-June 1975 
Newport Bay Harbor, Calif. July 1974-June 1975 
Redondo Beach Harbor (King Harbor), Calif. July 1974-June 1975 
San Diego River and Mission Bay, Calif. July 1974-June 1975 
TABLE 33-D OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 10 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Dana Point Harbor, Calif. 1972 $4,737,550' $12,4002 
Los Angeles and Long Beach Harbors, Calif. 1965 34,626,7198 2,937,0454 6 
Marina del Rey, Los Angeles County, Calif. 1974 4,238,7526 320,2307 
Newport Bay Harbor, Calif. 1958 796,8978 192,3519 
Redondo Beach Harbor (King Harbor), Calif. 1966 4,766,89810 34,163" 
San Diego River and Mission Bay, Calif. 1974 10,593,09912 638,464's 
1. Excludes $4,738,301 required contributed funds 
and Coast Guard costs. 
2. Includes $12,400 for reconnaissance and condition 
surveys. 
3. Includes $2,187,047 for new work for previous 
projects; $1,593,667 public works funds; a credit of 
$33,050 for transfer of land at Reservation Point; 
and $996,792 emergency relief funds. Excludes 
$1,672,575 other contributed funds spent by the Corps 
for new work betterments desired by local interests 
and Federal funds spent by the Navy for new work in 
middle breakwater. Excludes Coast Guard costs. 
4. Includes $139,347 for maintenance for previous 
projects. Excludes $87,120 other contributed funds 
spent by the Corps for maintenance betterments 
desired by local interests. 
5. Includes $96,523 reconnaissance and condition 
survey costs since FY 1958. 
6. Excludes $4,238,572 required contributed funds; 
$1,843,146 other contributed funds; and Coast Guard 
costs. 
7. Includes $40,175 for reconnaissance and condition 
surveys. 
8. Public Works Administration funds. Excludes 
$796,897 required contributed funds and $1,100 
preauthorization costs. 
9. Includes $66,108 reconnaissance and condition 
survey costs since FY 1958. 
10. Excludes Coast Guard costs. 
11. Includes $18,517 reconnaissance and condition 
survey costs since FY 1958. 
12. Excludes $557,832 other contributed funds. 
Includes $2,610,000 regular funds and excludes 
$2,910,000 required contributed funds, both for 
new work on flood control project, "San 
Diego River Basin, Calif." 
13. Includes $36,240 for reconnaissance and 
condition surveys. 
33-30

LOS ANGELES, CALIF., DISTRICT 
TABLE 33-E INSPECTION OF COMPLETED BEACH EROSION 
CONTROL PROJECTS 
(See Section 12 of Text) 
Project Date 
Anaheim Bay Harbor, Orange County, Calif. July 1974-June 1975 
Bird Rock area, La Jolla, San Diego County, Calif. July 1974-June 1975 
Coast of California, Point Mugu to San Pedro breakwater, Calif. (part) July 1974-June 1975 
Doheny Beach State Park, Calif. July 1974-June 1975 
Imperial Beach, San Diego County, Calif. July 1974-June 1975 
Ocean Beach, San Diego County, Calif. July 1974-June 1975 
Oceanside, San Diego County, Calif. July 1974-June 1975 
San Diego (Sunset Cliffs), Calif. (part) July 1974-June 1975 
San Gabriel River to Newport Bay (Surfside-Sunset and Newport July 1974-June 1975 
Beach), Orange County, Calif. (part) 
Ventura-Pierpont area, Calif. (part) July 1974-June 1975 
TABLE 33-F
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
(See Section 13 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Anaheim Bay Harbor, Orange County, Calif.' 1967 $89,119 - 
Bird Rock area, La Jolla, San Diego County, Calif.2 1967 25,8813 
Coast of California, Point Mugu to San Pedro 
breakwater, Calif. 1972 1,253,5944 - 
Doheny Beach State Park (Doheny State Beach), Calif. 1968 578,7176 - 
Ocean Beach, San Diego County, Calif.s 1960 7,912 - 
Oceanside, San Diego County, Calif. 1966 1,369,5717- 
San Diego (Sunset Cliffs), Calif. 1973 184,8418 - 
San Gabriel River to Newport Bay (Surfside-Sunset 
and Newport Beach), Orange County, Calif. 1974 3,688,779- 
Ventura-Pierpont area, Calif. 1969 715,81910 
1. The project authorized by the Act of Congress 
of October 23, 1962, H. Doc. 602, 87th Cong., 
2d sess., in lieu of part of the original Anaheim 
Bay Harbor project is covered under San Gabriel 
River to Newport Bay (Surfside-Sunset and Newport 
Beach), Orange County, Calif. 
2. Authorized by Chief of Engineers under authority 
of section 103, Public Law 87-874. 
3. Excludes $75,614 required contributed funds. 
4. Excludes $1,238,418 required contributed funds. 
5. Excludes $431,260 required contributed funds. 
6. Plant in service. 
7. Excludes $604,817 other contributed funds. 
8. Excludes $180,438 required contributed funds. 
Includes $356 expended in FY 1975. 
9. Excludes $1,800,383 required contributed funds. 
10. Excludes $117,406 other contributed funds 
for beach-nourishment betterments and $618,949 
required contributed funds. 
33-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 33-G BEACH EROSION CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Beach Erosion Control Activities Pursuant To Section 103, Public Law 87-874 (Preauthorization) 
(See Section 14 of Text) 
Project Fiscal Year Costs 
Las Tunas Beach Park, Calif. $19,347 
Royal Palms Beach Park, Calif. 40,007 
TABLE 33-H LOS ANGELES COUNTY DRAINAGE AREA, CALIF.: 
ESTIMATED FIRST COSTS FOR ALL UNITS OF IMPROVEMENT 
UNDER EXISTING PROJECT 
(See Section 18 of Text) 
Latest Approved Estimated Cost 19751 
Project Units Federal Local2 Total 
UNITS IN $70 MILLION PROJECT 
Los Angeles River Basin: 
Compton Creek, Los Angeles River to Hooper Ave. storm drain $2,510,500 - $2,510,500 
Haines Canyon 524,000 - 524,000 
Hansen Dam 11,343,000 - 11,343,000 
Los Angeles River channel: 
Lankershim Blvd. to Stewart and Gray Rd. 40,807,300 - 40,807,300 
Los Angeles River channel, Long Beach Blvd. 34,200 - 34,200 
Sepulveda Dam 6,657,000 - 6,657,000 
Sycamore Wash 24,000 - 24,000 
Verdugo Wash, Concord St. to upper Canada bridge 1,087,000 - 1,087,000 
San Gabriel River Basin: 
San Gabriel River channel: 
San Gabriel Canyon to Santa Fe Dam 810,800 - 810,800 
Approach channel to Santa Fe Dam (remedial work) 951,900 - 951,900 
Santa Fe Dam to Walnut Creek 32,300 - 32,300 
Santa Fe Dam 12,647,000 - 12,647,000 
Rio Hondo Basin: 
Alhambra Wash 1,109,000 - 1,109,000 
Ballona Creek Basin: 
Ballona Creek channel and jetties 1,280,000 - 1,280,000 
Subtotal 79,818,000 - 79,818,000 
UNITS OUTSIDE $70 MILLION PROJECT 
Los Angeles River Basin: 
Blanchard Canyon 682,000 $476,000 1,158,000 
Blue Gum Canyon 533,000 233,000 766,000 
Burbank-Eastern system 7,149,000 1,850,000 8,999,000 
Burbank-Western system (lower) 1,279,000 266,000 1,545,000 
Burbank-Western system (upper) 4,930,000 2,952,000 7,882,000 
Caballero Creek 1,484,200 490,000 1,974,200 
Compton Creek: 
Los Angeles River to Hooper Ave. storm drain 149,000 - 149,000 
Hooper Ave. storm drain to Main St. 1,052,000 457,000 1,509,000 
Dead Horse Canyon and Royal Blvd. channel 664,000 316,000 980,000 
Lopez Canyon diversion 743,500 665,000 1,408,500 
Lopez Dam 729,000 - 729,000 
33-32

LOS ANGELES, CALIF., DISTRICT 
LOS ANGELES COUNTY DRAINAGE AREA, CALIF.: 
ESTIMATED FIRST COSTS FOR ALL UNITS OF IMPROVEMENT 
UNDER EXISTING PROJECT 
TABLE 33-H (Continued) (See Section 18 of Text) 
Latest Approved Estimated Cost 19751 
Project Units Federal LocaP Total 
Los Angeles River channel: 
Owensmouth Ave. to Lankershim Blvd. 8,135,800 4,217,000 12,352,800 
Lankershim Blvd. to Stewart and Gray Rd. 9,202,100 - 9,202,100 
Stewart and Gray Rd. to Santa Ana Branch, Pacific Electric 
railway bridge 5,860,900 81,000 5,941,900 
Santa Ana Branch, Pacific Electric railway bridge to 
Pacific Ocean 32,612,000 9,173,000 41,785,000 
Pacoima Wash channel 3,178,100 1,303,000 4,481,100 
Tujunga Wash channel 7,322,900 2,558,000 9,880,900 
Verdugo Wash, upper Canada bridge to debris basin 635,000 363,000 998,000 
Wilson Canyon and Mansfield St. channel 3,917,500 856,000 4,773,500 
Winery Canyon 413,000 263,000 676,000 
San Gabriel River Basin: 
Coyote Creek (including North Fork) 18,802,300 8,352,000 27,154,300 
Emerald Wash and Live Oak Wash 1,658,600 1,182,000 2,840,600 
Marshall Creek 2,577,900 965,000 3,542,900 
San Gabriel River channel: 
Santa Fe Dam to Whittier Narrows Dam 5,748,800 1,759,000 7,507,800 
Whittier Narrows Dam to Pacific Ocean 20,887,200 3,108,000 23,995,200 
Thompson Creek and San Jose Wash (including San Jose Creek) 21,099,600 6,080,000 27,179,600 
Walnut Creek inlet channel 2,879,000 1,091,000 3,970,000 
Walnut Creek system 17,232,600 8,633,000 25,865,600 
Whittier Narrows Dam 32,254,000 38,000 32,292,000 
Rio Hondo Basin: 
Arcadia Wash system 5,236,800 1,890,000 7,126,800 
Eaton Wash 4,225,100 1,190,000 5,415,100 
Rio Hondo channel: 
Peck Rd. to Rosemead Blvd. (upper) 4,412,000 545,000 4,957,000 
Whittier Narrows Dam to Los Angeles River (lower) 8,165,000 2,556,000 10,721,000 
Rubio Canyon diversion 1,066,400 254,000 1,320,400 
Santa Anita Wash 3,045,700 433,000 3,478,700 
Sawpit Wash 2,348,600 742,000 3,090,600 
Sierra Madre Villa channel 781,400 366,000 1,147,400 
Sierra Madre Wash 1,607,000 246,000 1,853,000 
Ballona Creek Basin: 
Ballona Creek channel 746,600 - 746,600 
Benedict Canyon system 15,284,900 3,783,000 19,067,900 
Centinela Creek 4,083,800 4,776,000 8,859,800 
Sawtelle-Westwood system (including Sepulveda channel) 9,620,700 1,492,000 11,112,700 
Subtotal 274,436,000 76,000,000 350,436,000 
Grand total for comprehensive plan 354,254,000 76,000,000 430,254,000 
1. Excludes estimated cost for Code 710 funds and estimated 2. Approved by Los Angeles County Flood Control District 
cost for minor rehabilitation. as of June 30, 1975, except for Walnut Creek system channel 
estimate, which was increased by $26,000 to permit rounding 
of overall non-Federal estimate to three significant figures. 
33-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 33-I LOS ANGELES COUNTY DRAINAGE AREA, CALIF.: 
PROJECT COSTS TO JUNE 30, 1975 
(See Section 18 of Text) 
Non-Federal funds' 
Spent Spent 
Emergency Total Federal by Federal by local Total 
Units Regular funds relief funds funds Government 2 
interests' Total all funds 
UNITS IN $70 MILLION PROJECT 
Los Angeles River Basin: 
Compton Creek, Los Angeles River to 
Hooper Ave. storm drain 
Haines Canyon 
Hansen Dam 
Los Angeles River channel: 
Lankershim Blvd. to Stewart and Gray Rd. 
Los Angeles River channel, Long Beach Blvd. 
Sepulveda Dam
5 
Sycamore Wash 
Verdugo Wash, Concord St. to upper 
Canada bridge 
San Gabriel River Basin: 
San Gabriel River channel: 
San Gabriel Canyon to Santa Fe Dam 
Santa Fe Dam to Walnut Creek 
Santa Fe Dam
e 
Rio Hondo Basin: 
Alhambra Wash 
Ballona Creek Basin: 
Ballona Creek channel and jetties 
Plant 
Surveys and engineering 
Distribution of insurance and surplus plant accounts 
Subtotal - new work 
Subtotal - maintenance 
Subtotal - all work ($70 million project) 
UNITS OUTSIDE $70 MILLION PROJECT 
Los Angeles River Basin: 
Blanchard Canyon 
Blue Gum Canyon 
Burbank-Eastern system 
Burbank-Western system (lower) 
Burbank-Western system (upper) 
Caballero Creek 
Compton Creek: 
Los Angeles River to Hooper Ave. storm drain 
Hooper Ave. storm drain to Main St. 
Dead Horse Canyon and Royal Blvd. channel 
Lopez Canyon diversion 
Lopez Dam
7 
Los Angeles River channel: 
Owensmouth Ave. to Lankershim Blvd. 
Lankershim Blvd. to Stewart and Gray Rd.' 
Stewart and Gray Rd. to Santa Ana Branch, 
Pacific Electric railway bridge 
Santa Ana Branch, Pacific Electric railway 
bridge to Pacific Ocean
9 1 
Pacoima Wash channel 
Tujunga Wash channel"
1 
Verdugo Wash, upper Canada bridge todebrisbasin 
Wilson Canyon and Mansfield St. channel 
Winery Canyon 
San Gabriel River Basin: 
Coyote Creek (including North Fork) 
Emerald Wash and Live Oak Wash 
Marshall Creek 
San Gabriel River channel: 
Santa Fe Dam to Whittier Narrows Dam 
Whittier Narrows Dam to Pacific Ocean 
(including approach channel to Santa Fe 
Dam (remedial work)) 
Thompson Creek and San Jose Wash 
(including San Jose Creek) 
Walnut Creek inlet channel 
Walnut Creek system 
Whittier Narrows Daml2 
$1,878,930 
354,599 
11,425,334 
34,074,786 
13,678 
6,847,559 
8,835 
367,805 
1,900,514 
32,264 
12,692,519 
$745,849 $2,624,779 $25,409 
233,954 588,553 - 
- 11,425,334 - 
7,638,039 41,712,825 -1,302 
20,566 34,244 - 
- 6,847,559 199,915 
14,711 23,546 - 
362,557 730,362 155,121 
44,686 1,945,200 
- 32,264 
- 12,692,519 
529,318 580,437 1,109,755 
771,827 
363,474 
-781,900 
70,479,542 
13,636,700 
4,684 
509,118 1,280,945 72,201 
217,755 217,755 - 
24,000 387,474 - 
617,263 -164,637 - 
11,008,935 81,488,477 456,028 
- 13,636,700 - 
84,116,242 11,008,935 95,125,177 456,028 
741,887 
582,261 
7,149,291 
1,295,926 
4,911,988 
1,446,949 
149,034 
1,202,965 
727,464 
743,458 
732,187 
17,371,670 
9,112,403 
5,860,861 
22,017,272 
3,178,110 
7,402,566 
691,534 
3,917,506 
476,002 
- 741,887 218,610 
- 582,261 46,123 
- 7,149,291 806,960 
- 1,295,926 - 
- 4,911,988 781,354 
- 1,446,949 325,908 
- 149,034 - 
- 1,202,965 362,937 
- 727,464 132,857 
- 743,458 192,673 
- 732,187 - 
- 17,371,670 4,410,885 
- 9,112,403 - 
- 5,860,861 327,370 
- 22,017,272 1,582,691 
- 3,178,110 903,238 
- 7,402,566 2,286,305 
- 691,534 53,575 
- 3,917,506 361,722 
- 476,002 27,809 
18,754,663 - 18,754,663 1,681,301 
1,658,620 - 1,658,620 269,826 
2,577,875 - 2,577,875 388,401 
5,939,112 - 5,939,112 745,206 
20,502,038 
21,647,357 
2,869,424 
17,127,158 
33,701,585 
- 20,502,038 2,643,103 
- 21,647,357 2,354,249 
- 2,869,424 727,516 
- 17,127,158 4,277,539 
- 33,701,585 812,417 
- $25,409 $2,650,188 
- - 588,533 
- - 11,425,334 
- -1,302 41,711,523 
- - 34,244 
- 199,915 7,047,474 
- - 23,546 
- 155,121 885,483 
- - 1,945,200 
- - 32,264 
- - 12,692,519 
- 4,684 1,114,439 
- 72,201 1,353,146 
- - 217,755 
- - 387,474 
- - -164,637 
- 456,028 81,944,505 
- - 13,636,700 
- 456,028 95,581,205 
$403,690 622,300 1,364,187 
205,577 251,700 833,961 
994,840 1,801,800 8,951,091 
269,800 269,800 1,565,726 
1,726,446 2,507,800 7,419,788 
399,092 725,000 2,171,949 
- - 149,034 
158,763 521,700 1,724,665 
69,643 202,500 929,964 
489,727 682,400 1,425,858 
- - 732,187 
1,848,915 6,259,800 23,631,470 
- - 9,112,403 
18,230 345,600 6,206,461 
8,092,909 9,675,600 31,692,872 
528,862 1,432,100 4,610,210 
893,595 3,179,900 10,582,466 
312,425 366,000 1,057,534 
697,678 1,059,400 4,976,906 
205,091 232,900 708,902 
7,906,199 9,587,500 28,342,163 
974,074 1,243,900 2,902,520 
507,799 896,200 3,474,075 
1,206,194 1,951,400 7,890,512 
970,897 3,614,000 24,116,038 
3,981,051 6,335,300 27,982,657 
554,384 1,281,900 4,151,324 
6,357,061 10,634,600 27,761,758 
3,061 815,478 34,517,063 
33-34

LOS ANGELES, CALIF., DISTRICT 
LOS ANGELES COUNTY DRAINAGE AREA, CALIF.: 
PROJECT COSTS TO JUNE 30, 1975 
TABLE 33-I (Continued) (See Section 18 of Text) 
Non-Federal funds' 
Spent Spent 
Emergency Total Federal by Federal by local Total 
Units Regular funds relief funds funds Governmentt interests' Total all funds 
Rio Hondo Basin: 
Arcadia Wash system 5,063,273 - 5,063,273 1,264,448 811,052 2,075,500 7,138,773 
Eaton Wash 4,225,068 - 4,225,068 932,388 440,712 1,373,100 5,598,168 
Rio Hondo channel: 
Peck Rd. to Rosemead Blvd. (upper) 4,411,995 - 4,411,995 970,312 545,188 1,515,500 5,927,495 
Whittier Narrows Dam to Los Angeles River (lower) 8,164,705 - 8,164,705 1,429,176 811,124 2,240,800 10,405,005 
Rubio Canyon diversion 1,066,825 - 1,066,825 90,523 168,477 254,000 1,320,825 
Santa Anita Wash 3,045,713 - 3,045,713 412,879 180,921 593,800 8,639,513 
Sawpit Wash 2,337,809 - 2,337,809 252,731 503,669 756,400 8,094,209 
Sierra Madre Villa channel 846,442 - 846,442 4,368 863,082 367,400 1,213,842 
Sierra Madre Wash 253,218 - 253,218 - 248,600 248,600 501,818 
Ballona Creek Basin: 
Ballona Creek channel 600,582 - 600,582 - - - 600,582 
Benedict Canyon system 15,425,731 - 15,425,731 2,197,718 2,242,382 4,440,100 19,865,831 
Centinela Creek 4,083,771 - 4,083,771 1,696,998 8,118,702 4,815,700 8,899,471 
Sawtelle-Westwood system (including Sepulveda 
channel) 9,620,767 - 9,620,767 1,188,837 567,668 1,756,500 11,377,267 
Subtotal - new work 273,635,065 - 273,635,065 37,160,953 49,772,525 86,938,478 860,568,548 
Subtotal - maintenance 2,114,595 - 2,114,595 - - - 2,114,595 
Subtotal - all work (outside $70million project) 275,749,660 - 275,749,660 37,160,9583 49,772,525 86,9338,478 362,683,138 
Total - new work 344,114,607 11,008,985 355,123,542 37,616,981 49,772,525 87,389,506 442,513,048 
Total - maintenance 15,751,295 - 15,751,295 - - - 15,751,295 
Grand Total - all work (inside and outside 
$70 million project) 359,865,902 11,008,935 370,874,837 37,616,981 49,772,525 87,389,506 458,264,343 
1. Includes $11,344,400 for betterments, some of which were constructed 
by local interests and some by Federal Government out of non-Federal 
funds deposited by local interests. 
2. Other contributed funds (non-Federal) spent by Federal Government for 
required items of local cooperation under terms of project authorization 
and betterments desired by local interests. 
3. Non-Federal funds spent by local interests for required items of local 
cooperation under terms of project authorization and betterments desired 
by local interests. Includes non-Federal funds of $1,951,907 on deposit with 
Federal Government on June 30, 1975, but not yet spent as of that date. 
4. Includes Code 710 funds since FY 1975 ($95,130 all Federal). 
5. Includes Code 710 funds since FY 1974 ($196,998 Federal and $199,915 
non-Federal). 
6. Includes Code 710 funds since FY 1975 ($55,570 all Federal). 
7. Includes Code 710 funds since FY 1975 ($3,128 all Federal). 
8. Includes Code 710 funds since FY 1974 ($22,000 all Federal). 
9. Includes Code 710 funds since FY 1975 ($7,359 all Federal). 
Although these Code 710 funds are only indicated in the cost figure 
for this particular unit, they are also meant for the following two 
units: Los Angeles River channel, Stewart and Gray Road to Santa 
Ana Branch, Pacific Electric railway bridge; and Rio Hondo channel, 
Whittier Narrows Dam to Los Angeles River (lower). 
10. Includes funds for permanent construction of Los Angeles River at 
Long Beach Blvd. 
11. Includes Code 710 funds since FY 1975 ($43,209 all Federal). 
12. Includes Code 710 funds since FY 1974 ($1,447,274 Federal and $777,178 
non-Federal). 
Note: Does not include $107,939 for minor rehabilitation and does not 
include costs under Code 710 before FY 1974. 
33-35

TABLE 33-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
SANTA ANA RIVER BASIN 
(AND ORANGE COUNTY), CALIF. 
LATEST APPROVED ESTIMATED FEDERAL FIRST COST 
FOR ALL UNITS 
(See Section 23 of Text) 
Estimated Cost 
Project Total Latest Revision Date 
ACTIVE UNITi 
Completed: 
Brea Dam $1,189,0682 3 
Fullerton Dam 411,0762 3 
Lytle and Cajon Creeks channel improvements 7,612,000 
Prado Dam 9,473,2732 3 
San Antonio and Chino Creeks channel 10,924,170 3 
San Antonio Dam 7,001,1762 4 3 
Completed Except for Minor Completion Items: 
Carbon Canyon Dam and channel 5,150,0002 1961 
INACTIVE UNITS6 
Aliso Creek Dam 340,000 1954 
San Juan Dam 5,960,000 1954 
Trabuco Dam 2,190,000 1954 
Villa Park Dam 2,270,000 1954 
1. For details, see section 23 of text. 
2. Not including estimated cost of Code 710 funds. 
3. Plant in service. 
4. Includes $5,000 working funds. 
5. For additional information, see "Other Authorized Flood Control Projects." 
33-36

TABLE 33-K 
Project 
LOS ANGELES, CALIF., DISTRICT 
INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 28 of Text) 
Date 
June 1975 
June 1975 
June 1975 
April, May, 
and June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
June 1975 
May 1975 
May 1975 
August 1974 
August 1974 
May 1975 
Banning levee-San Gorgonio River, Whitewater River Basin, Calif. 
City Creek levee, Santa Ana River Basin, Calif. 
Devil, East Twin, and Warm Creeks channel improvements and 
Lytle Creek levee, Santa Ana River Basin, Calif. 
Los Angeles County drainage area, Calif., channels 
Lytle and Cajon Creeks channel improvements, Santa Ana 
River Basin (and Orange County), Calif. 
Mill Creek levees, Santa Ana River Basin, Calif. 
Oro Grande Wash channel improvements, Mojave River Basin, Calif. 
Riverside levees, Santa Ana River Basin, Calif. 
San Diego River channel and levees, San Diego River Basin, Calif. 
San Jacinto River levee and Bautista Creek channel, Santa Ana 
River Basin, Calif. 
Santa Clara River levee improvement, Santa Clara River Basin, Calif. 
Santa Maria Valley levees, Santa Maria River Basin, Calif. 
Stewart Canyon debris basin and channel, Ventura River Basin, Calif. 
Tahchevah Creek detention basin and channel improvements, 
Whitewater River Basin, Calif. 
Ventura River levee, Ventura River Basin, Calif. 
Emergency Flood Control Projects: 
Clifton, Ariz. 
Eloy, Ariz. 
Holbrook, Ariz. 
Jerome, Ariz. 
Tucson, Ariz. 
TABLE 33-L OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
City Creek levee, San Bernardino County, Calif.' 2 
Gila River Basin, Ariz.: 
Camelsback Dam (Gila River) 
Gila and Salt Rivers levee and channel improvements 
Middle Gila River channel improvements, upper end 
of Safford Valley to Buttes damsite (Camelsback 
damsite to Salt River) 
Pinal Creek channel improvements (Globe) (deferred) 
Tucson diversion channel 2 
Goleta, Calif., and vicinity 
Hodges Dam, San Dieguito River Basin, Calif. (inactive) 
Holbrook levee, Little Colorado River, Colorado 
River Basin, Ariz. 2 
Las Vegas Wash tributaries, Colorado River Basin, 
Nev. (inactive) 
1963 
1966 
1970 
1968 
1967 
1971 
1958 
1950 
1964 
$400,0003 
73,2014 
402,867 
121,5094 
5,764,6256 
335,000 
295,191 
33-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 33-L (Continued) (See Section 30 of Text) 
Project 
Needles, San Bernardino County, Calif.1 
Oro Grande Wash channel improvements, Mojave River 
Basin, Calif.' 2 
Quail Wash levee, Joshua Tree, San Bernardino County, 
Calif.' 2 
Ridgecrest, Kern County, Calif.' 8 
Rose Creek channel improvements, San Diego, Calif.' 2 
San Luis Rey River, San Luis Rey River Basin, Calif. 
Santa Ana River Basin, Calif.: 
Devil, East Twin, and Warm Creeks channel improvements 
and Lytle Creek levee 2 
Mill Creek levees 2 
Riverside levees 2 
San Jacinto River levee and Bautista Creek channel2 
Santa Ana River Basin (and Orange County), Calif.: 
Aliso Creek Dam (inactive) 
San Juan Dam (inactive) 
Trabuco Dam (inactive) 
Villa Park Dam (inactive) 
Santa Clara River levee improvement, Santa Clara 
River Basin, Calif.2 
Santa Maria Valley levees, Santa Maria River Basin, 
Calif.2 
Ventura River Basin, Calif.: 
Stewart Canyon debris basin and channel2 
Ventura River levee2 
Whitewater River Basin, Calif.: 
Banning levee-San Gorgonio River, Riverside 
County' 2 
Chino Canyon improvements, Palm Springs' 2 
Tahchevah Creek detention basin and channel 
improvements 2 
Tahquitz Creek 
Winslow (tributaries of Little Colorado River), 
Little Colorado River Basin, Ariz. 
For Last 
Full Report 
See Annual 
Report For 
Cost To June 30, 1975 
Construction 
Operation and 
Maintenance 
978,1486 
1,000,0007 
212,745 
195,194 
982,4329 
7,753,93710 
617,89011 
2,104,478 
3,026,97412 
1973 
1970 
1973 
1972 
1971 
1962 
1961 
1959 
1962 
1950 
1961 
1966 
1964 
1950 
1966 
1973 
1967 
1974 
1973 
67,361 
2,126,672 
5,535,73413 
939,90814 
1,343,63816 
97,868 
819,87816 
1,420,55217 
1,037,167 
1,831,300 
1. Authorized by Chief of Engineers under authority 
of section 205, Public Law 80-858, as amended. 
2. Completed. 
3. Excludes $371,058 other contributed funds. 
4. Advance planning only. 
5. Excludes $394,364 other contributed funds. 
6. Excludes $630,970 required contributed funds and 
$101,955 other contributed funds. Includes $26,184 
expended in FY 1975. 
7. Excludes $514,806 required contributed funds and 
$176,295 other contributed funds. 
8. Terminated. 
9. Excludes $251,000 required contributed funds 
and $154,733 other contributed funds. 
10. Excludes $200,000 required contributed funds 
and $1,641,668 other contributed funds. 
11. Excludes $35,830 other contributed funds. 
12. Excludes $327,723 other contributed funds. 
13. Excludes $106,364 other contributed funds. 
14. Excludes $179,148 other contributed funds. 
15. Excludes $17,006 other contributed funds. 
16. Excludes $8,718 required contributed funds 
and $53,470 other contributed funds. 
17. Excludes $74,718 required contributed funds. 
33-38

LOS ANGELES, CALIF., DISTRICT 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 80-858, 
As Amended (Preauthorization) 
TABLE 33-M (See Section 31 of Text) 
Project Fiscal Year Costs 
Puerco River, N. Mex. $27,104 
Yucca Valley, Calif. 5,080 
TABLE 33-N FLOOD PLAIN INFORMATION STUDIES COMPLETED 
DURING FISCAL YEAR 
(See Section 33 of Text) 
Location Requesting Agency Date Completed1 Federal Cost 2 
Orange County, Calif.: 
Upper Peters Canyon Wash 
(upstream from Santa 
Ana Freeway) 
Upper San Diego Creek 
and tributaries 
Riverside County, Calif.: 
San Gorgonio River and 
tributaries 
San Luis Obispo County, Calif.: 
San Luis Obispo Creek (San 
Luis Obispo Bay to San Luis 
Obispo city limits) 
Santa Barbara County, Calif.: 
Montecito streams (including 
Montecito, Oak, San Ysidro, 
Buena Vista, Romero, and 
Picay Creeks), vicinity of 
Montecito 
Clark County, Nev.: 
Muddy River, vicinity 
of Overton 
McKinley County, N. Mex.: 
Flood Control District 
of Orange County 
Flood Control District 
of Orange County 
Riverside County Flood 
Control and Water 
Conservation District 
City and County of 
San Luis Obispo 
Santa Barbara County Flood 
Control and Water 
Conservation District 
Clark County Department 
of Public Works 
Puerco River, vicinity 
of Gallup 
1. Report supplied to requesting agency. 2. Including costs for processing study applications. 
33-39 
Apr. 1975 
Apr. 1975 
$36,000 
35,000 
May 1975 49,020 
June 1975 45,000 
Sept. 1974 26,500 
Dec. 1974 
City of Gallup 
23,000 
Aug. 1974 40,820

SAN FRANCISCO, CALIF., DISTRICT* 
This district comprises the Klamath River 
Basin in southern Oregon and those portions of 
northern and western California consisting of 
drainage basins tributary to the Pacific Ocean 
from Oregon-California state line on the north, 
to Cape San Martin, California on the south, 
basins tributary to the San Francisco Bay 
system which lie east of the Benicia-Martinez 
Bridge. 
IMPROVEMENTS 
Navigation Page 
1. Bodega Bay, Calif ................ 34-1 
2. Crescent City Harbor, Calif.......... 34-2 
3. Humboldt Harbor and Bay, Calif.... 34-2 
4. Moss Landing Harbor, Calif......... 34-3 
5. Noyo River and Harbor, Calif ....... 34-4 
6. Oakland Harbor, Calif............... 34-4 
7. Petaluma River, Calif. ........... 34-5 
8. Redwood City Harbor, Calif. ....... 34-6 
9. Richmond Harbor, Calif............. 34-6 
10. San Francisco Bay to Stockton, 
Calif. (John F. Baldwin and 
Stockton Ship Channels)............. 34-7 
11. San Francisco Bay and Delta 
Model, Calif ......................... 34-7 
12. San Francisco Harbor, Calif........ 34-8 
13. San Francisco Harbor and Bay, 
Calif. ............................. 34-8 
14. San Pablo Bay and Mare Island 
Strait, Calif. ...................... 34-9 
15. Santa Cruz Harbor, Calif............ 34-9 
16. Suisun Bay Channel, Calif........... 34-10 
17. Reconnaissance and condition 
surveys ............................. 34-11 
18. Other authorized navigation 
projects ......................... 34-11 
Navigation (cont.) Page 
19. Navigation work under special 
authorization........................34-11 
Beach Erosion Control 
20. Other authorized beach erosion 
control projects ..................... 3411 
21. Beach erosion control work under 
special authorization .............. 34-11 
Flood Control 
22. Alameda Creek, Calif.............. 34-11 
23. Corte Madera Creek, Calif.......... 34-12 
24. Napa River Basin, Calif. ........... 34-12 
25. Russian River Basin, Calif........... 34-13 
26. Inspection of completed flood 
control projects ................... 34-14 
27. Other authorized flood control 
projects ............................. 34-14 
28. Flood control work under special 
authorization ........................ 34-14 
General Investigations 
29. Surveys ............................. 34-14 
30. Collection and study of basic 
data ..... .................... 34-14 
31. Research and development .......... 34-14 
Navigation 
1. BODEGA BAY, CALIF. 
Location. A triangular lagoon on California 
Coast 85 miles south of Noyo River and 58 miles 
north of San Francisco. (See Coast and Geodetic 
Survey Chart 5603.) 
Existing project. Entrance jetties 1,130 and 
1,650 feet long; a bulkhead to retain the 
sandspit; a channel shore; and a channel 10 feet 
deep, 100 feet wide, and 3,000 feet long on north 
side of Doran Beach Spit. All 12 feet deep, 100 
feet wide and 16,010 feet long to town of Bodega 
Bay thence southeasterly along shore, with 3 
turning basins 12 feet deep and 300 to 400 feet 
wide at inner end of entrance channel, at 
junction of bay and shore channels near town of 
Bodega Bay, and at southerly end of shore 
channel; a 4,500-foot riprapped earth mole 
westerly of channel along the eastern shore. 
Approved estimated cost of new work (1975) is 
$3,872,000 of which $2,642,000 (excluding Coast 
Guard costs) is Federal cost and $1,230,000 is to 
be contributed by local interests. Major rehabilitation 
of jetties and channels cost $397,779, 
exclusive of $2,000 contributed funds. Existing 
project was adopted by River and Harbor Acts 
of 1938 and 1965 (H. Docs. 619, 75th Cong., 3d 
sess., and 106, 89th Cong., 1st sess., contains 
latest published map). 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text 
and also appear at the end of this chapter. 
34-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Fully complied with for 
work performed. Act of October 27, 1965, 
requires local interests (a) contribute in cash 36 
percent of the first cost of construction for the 
mole, an amount presently estimated at $840,- 
000 and 50 percent of the first cost of dredging 
the Doran Beach channel, an amount presently 
estimated at $200,000; both amounts subject to 
final adjustment after actual costs have been 
determined; (b) provide without cost to the 
United States all lands, easements, and rightsof-
way required for construction and subsequent 
maintenance of the improvements, and of 
aids to navigation upon request of the Chief of 
Engineers, including suitable areas determined 
by the Chief of Engineers to be required in the 
general public interest for initial and subsequent 
disposal of spoil, and also necessary 
retaining dikes, bulkheads and embankments 
therefor or the cost of such retaining works; (c) 
hold and save the United States free from 
damages due to the construction works and 
subsequent maintenance of the improvements; 
and (d) provide and maintain without cost to the 
United States adequate service frontage and a 
public landing with suitable facilities at each 
location, necessary mooring facilities for local 
and transient boats with adequate depths in 
berthing areas, utilities, access roads and 
parking areas (including those on the mole), and 
other necessary public use shore facilities, open 
to all on equal terms, in accordance with plans 
approved by the Chief of Engineers. By 
Resolution No. 7674, dated November 12, 1963, 
the Board of Supervisors of Sonoma County 
furnished assurances of willingness and ability 
to meet the requirements of local cooperation. 
Operations and results during fiscal year. 
New work: Advance engineering and design for 
the earth mole and Doran Beach is continuing. 
Condition at end of fiscal year. Planning of 
the earth mole and Doran Beach Channel is 
about 30 percent complete. Work remaining is 
construction of earth mole and Doran Beach 
Channel. Jetties, bulkhead, and main Bodega 
Bay Channels and turning basins were completed 
in 1943. Major rehabilitation of channels 
and south jetty was completed in August 1961. 
2. CRESCENT CITY HARBOR, CALIF. 
Location. Harbor is 17 miles south of Oregon 
State line, 125 miles south of Coos Bay, Oreg., 
70 miles north of Humboldt Bay, Calif., and 
midway between San Francisco Bay and mouth 
of Columbia River. (See Coast and Geodetic 
Survey Chart 5895.) 
Existing project. A rubblemound outer breakwater 
extending about 3,700 feet on a bearing of 
S. 27 degrees E.; from Battery Point, thence 
about 1,000 feet on a bearing of S. 80 degrees 
E.; for maintenance dredging of an outer 
harbor basin 1,800 feet long and 1,400 feet wide 
to 20 feet depth at mean lower low water, 
except in rock; a rubblemound sand barrier 
from Whaler Island to easterly shore and 
maintenance dredging at seaward end of sand 
barrier; an inner breakwater extending northwesterly 
about 1,200 feet from Whaler Island, 
thence westerly 400 feet to form a protected 
fish-boat harbor; for removal of pinnacle rock in 
fish-boat harbor to 20-foot depth; and a 
T-shaped inner harbor basin 20 feet deep, 1,500 
feet long extending along north side of Citizen's 
Dock for 325 feet, with a stem 1,000 feet long. 
Approved estimated cost for new work (July 
1973 price levels) is $7,375,000 ($7,158,000 
Federal cost (excludes Coast Guard cost) and 
$217,000 contributed by local interests). Major 
rehabilitation of outer breakwater cost 
$525,000. (See table 34-B for authorizing 
legislation.) 
Local cooperation. Fully complied with for 
completed modifications and acts of 1927, 1937, 
1945, and 1965 portion for construction of 400- 
foot extension of the inner breakwater. However, 
dredging portion of the 1965 Act has been 
deferred, subject to local interests reevaluation 
of harbor conditions. 
Terminal facilities. Three piers, one of which 
is publicly owned and from which boats are 
fueled; one oil terminal; and a private mooring 
for barges discharging petroleum products to 
pipelines on inner breakwater. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Engineering and design, including 
testing and sampling and dredging surveys 
by hired labor. 
Condition at end of fiscal year. Project is 
complete except for dredge portion of T-shaped 
inner harbor basin 20 feet deep which has been 
deferred. The 3,000-foot outer breakwater was 
completed in 1930, sand barrier in 1939, inner 
breakwater in 1946, removal of pinnacle rock in 
1951, and outer breakwater extension in 1957. 
Major rehabilitation of outer breakwater was 
completed in 1964. The 400-foot extension of 
inner breakwater was completed in 1973. 
3. HUMBOLDT HARBOR AND BAY, 
CALIF. 
Location. Humboldt Bay is a landlocked 
harbor on coast of California, 225 miles north of 
San Francisco Bay and 70 miles south of 
Crescent City Harbor. (See Coast and Geodetic 
Survey Chart 5832.) 
Previous projects. For details see pages 1982- 
84 of Annual Report for 1915, page 1673 of 
34-2

SAN FRANCISCO, CALIF., DISTRICT 
Annual Report for 1929, and page 1689 of 
Annual Report for 1938. 
Existing project. Two rubblemound jetties at 
entrance-north jetty about 4,500 feet long and 
south jetty 5,100 feet long, not including shore 
revetments; a bar and entrance channel 40 feet 
deep tapered from 1,600 feet wide at seaward 
mile 0.91 to 500 feet at seaward mile 0.18, 
thence 500 feet wide to mile 0.75, with easing of 
bend at mile 0.75; a North Bay Channel 35 feet 
deep and 400 feet wide from mile 0.75 to 4.29; 
with widening of channel bends at mile 0.75 and 
2.6; an anchorage area in the North Bay 35 feet 
deep, 1200 feet wide and 1200 feet long; a 
channel 400 feet wide and 35 feet deep from 
mile 4.29 to 5.00, thence 26 feet deep to foot of 
N Street, Eureka; a channel 35 feet deep and 
300 feet wide from mile 4.29 across Indian 
Island Shoal to Samoa, at mile 5.84; a channel 
18 feet deep and 150 feet wide to Arcata wharf; 
and a channel 26 feet deep and 300 feet wide to 
Fields Landing, with a turning basin 600 feet 
wide and 800 feet long off Fields Landing 
Wharf. Approved estimated cost for new work 
(1975), exclusive of amounts expended on 
previous projects, is $8,479,000, of which 
$8,384,000 is Federal cost (excludes Coast 
Guard costs) and $95,000 contributed by local 
interests. (See table 34-B for authorizing 
legislation.) 
Local cooperation. Fully complied with for 
work performed. Estimated costs for all 
requirements of local cooperation for work 
performed, including required non-Federal 
contributions, were $1 million (prices as of dates 
of compliance). Local interests must furnish 
lands, easements, rights-of-way, and suitable 
spoil-disposal areas for maintenance dredging. 
Act of August 13, 1968 requires local interests 
provide and maintain adequate wharf and 
terminal facilities in the North Bay, Eureka 
and Samoa Channels, open to all on equal and 
reasonable terms for the storage, handling, and 
shipment of lumber and general commerce; 
provide and maintain, in the berthing areas and 
local access channels serving terminals and 
wharves commensurate with depths provided in 
related project channels; provide lands, easements 
and rights-of-way required for construction 
and subsequent maintenance of the project 
and for aids to navigation upon request of the 
Chief of Engineers; including suitable areas 
determined by the Chief of Engineers to be 
required in the general public interest for 
initial disposal of spoil, and necessary retaining 
dikes, bulkheads, and embankments therefor or 
the costs of such retaining works; hold and save 
the United States free from all claims for 
damages to wharves, piers, and other marine 
and submarine structures due to initial dredging 
work and subsequent maintenance dredging; 
and accomplish at local expense all 
alterations as may be required to sewer, water 
supply, drainage, and other utility facilities. 
Board of Supervisors of Humboldt County, by 
Resolution No. 66-85, July 26, 1966, furnished 
assurances of willingness and ability to comply. 
Terminal facilities. There are 37 wharves and 
piers, 3 of which are publicly owned; 4 oil 
terminals; 1 privately owned submarine pipeline 
for petroleum products; 2 boat-building and 
repair plants; 1 boat-icing plant; 6 small boat 
fueling stations; 2 small yacht and fishboat 
basins, 1 of which is publicly owned; and 
numerous log booms and small landings; 
exclusive of facilities owned by the United 
States. Facilities considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
New work: Planning for portion of remaining 
work (1968 Act) is about 10 percent complete. 
Maintenance: Engineering and design by hired 
labor, including dredging surveys of project 
channels, and U.S. hopper dredges Harding and 
Pacific removed 381,500 cubic yards of shoaled 
material from the bar and entrance channel, 
36,000 cubic yards from Fields Landing and 
turning basin, and 129,000 cubic yards from 
North Bay Channel cost $503,182. 
Condition at end of fiscal year. Planning for 
portion of remaining work (1968 Act) is about 
10 percent complete. Work remaining is 
deepening channels to 35 feet, widenings, and 
construction of North Bay anchorage area as 
authorized by 1968 River and Harbor Act. 
North jetty was completed in 1925; south jetty 
in 1927; Arcata Channel in 1931; entrance 
channel, 30 feet deep and 50 feet wide, in 1935; 
Fields Landing Channel and turning basin and 
Eureka and Samoa Channels, to 26 feet deep, in 
1939; entrance channel to 40 feet deep, and 
Eureka, Samoa, and North Bay Channels to 30 
feet deep in 1954. Total cost of existing project 
to end of fiscal year was $29,385,707, of which 
$3,491,670 was for new work ($3,396,670 
regular funds and $95,000 contributed funds) 
and $25,894,037 regular funds for maintenance. 
4. MOSS LANDING HARBOR, CALIF. 
Location. About 80 miles south of San 
Francisco Harbor on Monterey Bay about 
midway between cities of Santa Cruz and 
Monterey. (See Coast and Geodetic Survey 
Chart 5403.) 
Existing project. Entrance channel 200 feet 
wide and 15 feet deep, protected by jetties, from 
Monterey Bay into inner lagoon at Moss 
Landine. thence a channel in the lagoon, 100 
34-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
feet wide, 15 feet deep, and about 3,200 feet long 
extending southerly from entrance, with a 
flared widening to 200 feet for 400 feet long at 
southerly end. Project new work completed in 
1947 cost $343,552. Existing project authorized 
by 1945 River and Harbor Act (report on file in 
Office, Chief of Engineers). No map has been 
published. 
Local cooperation. Fully complied with for 
work performed. Local interests must furnish 
rights-of-way and suitable bulkheaded spoildisposal 
areas for maintenance work. 
Terminal facilities. Five piers, one of which 
has boat-fueling facilities, one marine ways, a 
boat launching ramp, and a number of mooring 
and berthing facilities within the protected 
harbor. Outside the harbor in Monterey Bay 
there is one submerged petroleum pipeline. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: Engineering and design including 
dredging survey by hired labor and removal 
of 56,040 cubic yards of shoaled material from 
entrance channel and turning basin, cost 
$332,077. 
Condition at end of fiscal year. Project 
completed in 1947. 
5. NOYO RIVER AND HARBOR, CALIF. 
Location. Noyo Harbor is a cove on California 
coast about 87 miles south of Humboldt Bay and 
135 miles northwest of San Francisco. Noyo 
River rises in Coast Range Mountains, flows 
westerly, and empties into Noyo Harbor. (See 
Coast and Geodetic Survey Chart 5703.) 
Previous projects. For details see page 1680, 
Annual Report for 1929, and page 1772, Annual 
Report for 1930. 
Existing project. Provides for two entrance 
jetties; an entrance channel into Noyo River 10 
feet deep and 100 feet wide and channel in river 
10 feet deep and 150 feet wide extending about 
0.6 mile above mouth, thence connecting channel 
about 400 feet long to mooring basin of 
about 8.5 acres 10 feet deep on south bank of 
river. Cost of new work construction completed 
in 1931 was $184,000, exclusive of amounts 
expended on previous projects. Minor rehabilitation 
of jetties completed in 1961 cost $222,810 
exclusive of $1,700 contributed funds. A 400- 
foot channel extension, mooring basin and 
connecting channel were constructed by Noyo 
Harbor District in 1968. Breakwater portion of 
project is considered inactive. Cost of this 
portion, last revised in 1963, was estimated to 
be $13,830,000 Federal cost and $340,000 to be 
contributed by local interests. (See table 34-B 
for authorizing legislation.) 
Local cooperation. Fully complied with for 
work performed. For details see Annual Report 
for 1973. 
Terminal facilities. None in harbor proper. In 
river above harbor there are two piers and nine 
fish-receiving wharves; three boat fueling 
wharves; two boat building and repair plants; 
one boat icing plant; three marine ways; and a 
number of privately owned mooring facilities. 
These facilities, together with those provided in 
the new mooring basin are adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Engineering and design by hired 
labor including removal of 73,000 cubic yards of 
shoaled material from entrance and river 
channels, cost $325,616. 
Condition at end of fiscal year. Project is 
complete except for construction of breakwaters 
in Noyo Harbor which is considered inactive. 
Jetties, rock removal and dredging entrance 
and river channels completed in 1931. Minor 
rehabilitation of jetties and north wall completed 
in September 1961. Mooring basin and 
connecting channel in river, constructed by 
local interests, was completed in October 1968. 
Total cost of existing project to end of fiscal 
year was $2,562,242, of which $451,497 was for 
new work, $1,890,235 for maintenance 
($1,886,235 regular funds and $4,000 contributed 
funds) and $224,510 for minor rehabilitation 
of jetties and north wall ($222,810 regular 
funds and $1,700 contributed funds). 
6. OAKLAND HARBOR, CALIF. 
Location. On eastern side of San Francisco 
Bay, opposite city of San Francisco. Inner 
harbor is between cities of Oakland and 
Alameda. (See Coast and Geodetic Survey Chart 
5535.) 
Previous project. For details see page 1979 of 
Annual Report for 1915, page 1755 of Annual 
Report for 1921, and page 1674 of Annual 
Report for 1938. 
Existing project. Provides entrance channel to 
Oakland Outer Harbor, 35 feet deep from deep 
water in San Francisco Bay and 800 feet wide 
across shoal southeast of Yerba Buena Island, 
narrowing to 600 feet at Oakland Mole; thence a 
channel and turning basin 35 feet deep and 
from 600 to 950 feet wide in outer harbor to the 
Army base. Project also provides entrance 
channel to Oakland Inner Harbor, 35 feet deep 
and 800 feet wide at bayward end, narrowing to 
600 feet wide at ends of Oakland jetties; a 
channel from ends of jetties 35 feet deep and 
34-4

SAN FRANCISCO, CALIF., DISTRICT 
600 feet wide to west end of Government Island, 
with additional widening to within 75 feet of 
pierhead line in front of Grove and Market 
Street (formerly municipal) piers and along 
south side of channel from Harrison Street 
eastward to harbor-line point 119 in Brooklyn 
Basin; a channel 35 feet deep and 500 feet wide 
through Brooklyn Basin; for dredging 35 feet 
deep a triangular a- 1 about 2,700 feet long and 
maximum width of 300 feet at western end of 
Brooklyn Basin; a channel along north side of 
Brooklyn Basin 35 feet deep and 300 feet wide 
for 1,300 feet, thence 25 feet deep to a turning 
basin at east end of Brooklyn Basin 35 feet deep, 
500 feet wide, and 1,200 feet long; a channel in 
tidal canal 35 feet deep and 275 feet wide from 
Brooklyn Basin to Park Street, thence 18 feet 
deep to San Leandro Bay; a total channel length 
of 8.5 miles from San Francisco Bay to San 
Leandro Bay. Project also includes parallel 
rubblemound jetties at entrance to inner 
harbor, north jetty 9,500 feet long and south 
jetty 12,000 feet long; three highway bridges 
across tidal canal, two of which (at Park Street 
and High Street) have been replaced by local 
interests. Railroad and highway bridges at 
Fruitvale Avenue are maintained and operated 
by the United States. Approved estimated cost 
for new work (July 1973 price levels), exclusive 
of amounts expended on previous projects, is 
$7,982,000 of which $7,592,000 is Federal cost 
and $390,000 to be contributed by local interests. 
Federal participation in reconstruction of 
Fruitvale Avenue Highway Bridge accomplished 
with Operation and Maintenance funds 
excluded from foregoing cost estimate. (See 
table 34-B for authorizing legislation.) 
Local cooperation. Fully complied with for 
work performed. For details see Annual Report 
for 1973. 
Terminal facilities. See Port Series No. 31, 
"The Ports of Oakland, Alameda, and Richmond, 
and Ports on San Pablo Bay, Carquinez 
Strait, and Mare Island Strait," revised 1962. 
Facilities will be adequate for existing commerce 
upon completion of 7th Street Terminal 
under construction to provide an additional nine 
deepwater berths. 
Operations and results during fiscal year. 
New work: Contract awarded June 1973, 
dredging from entrance to Ninth Avenue Wharf 
was completed February 1975. Maintenance: 
Operation and maintenance of Fruitvale 
Avenue highway and bridges, including engineering 
and design by hired labor, cost 
$478,145; and U.S. hopper dredges, Biddle and 
Harding removed 316,200 cubic yards of 
shoaled material from the inner and outer 
harbors, cost $291,436. 
Condition at end of fiscal year. Existing 
project is complete except for deepening inner 
harbor channels, a portion of the north channel 
in Brooklyn Basin and a portion of the tidal 
canal to 35 feet. Deepening portion of north 
channel in Brooklyn Basin from 25 to 35 feet 
and deepening tidal canal above Park Street 
Bridge to 25 feet, all inactive due to lack of 
economic justification. Jetties were completed 
in 1894. Dredging existing project channels was 
carried on from 1910 to 1931 when 30-foot depth 
was attained. The 35-foot depth in channel to 
outer harbor was attained in 1942 with military 
funds. Reconstruction of the Fruitvale Avenue 
Highway Bridge completed December 1973. 
Dredging from entrance to Ninth Avenue 
Wharf completed February 1975. Cost of 
existing project to end of fiscal year was 
$24,272,910, of which $7,109,885 was for new 
work ($6,712,619 regular funds and $397,266 
contributed funds), and $17,163,025 regular 
funds for maintenance. 
7. PETALUMA RIVER, CALIF. 
Location. Rises in hills north of Petaluma, 
flows southeasterly about 20 miles, and empties 
into northwest side of San Pablo Bay about 22 
miles from San Francisco. (See Coast and 
Geodetic Survey Chart 5533.) 
Previous projects. For details, see page 1982 of 
Annual Report for 1915, page 1665 of Annual 
Report for 1929, and page 1684 of Annual 
Report for 1938. 
Existing project. A channel 8 feet deep and 
200 feet wide in San Pablo Bay to mouth of 
river; thence 8 feet deep and 100 feet wide in 
river to Western Avenue, Petaluma, including a 
depth of 8 feet in turning basin; thence 4 feet 
deep and 50 feet wide to Washington Street 
Bridge; thence 4 feet deep and 40 feet wide to a 
point 935 feet above Washington Street Bridge. 
All depths refer to mean lower low water. 
Section under improvement is 19.5 miles long, 
of which 5 miles are in San Pablo Bay 
downstream from mouth of river. Cost of new 
work, completed in 1933, was $85,063, exclusive 
of amounts expended on previous projects. 
Existing project adopted by 1930 River and 
Harbor Act (H. Doc. 183, 70th Cong., 1st sess., 
which contains published map). 
Local cooperation. Fully complied with for 
work performed. Local interests must fuirnish 
satisfactory areas with necessary levees, spillways, 
and drainage works for proper disposal of 
spoil from maintenance. 
Terminal facilities. There are wharves and 
piers, 1 small yacht harbor with fueling 
facilities, arnd 11 small landings, all privately 
34-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
owned. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Engineering and design, including 
dredging survey by hired labor. 
Condition at end of fiscal year. Project was 
completed in 1933. Total cost of existing project 
to end of fiscal year was $1,850,041, of which 
$85,063 was for new work and $1,764,978 
regular funds for maintenance. 
8. REDWOOD CITY HARBOR, CALIF. 
Location. On Redwood Creek, a tributary of 
San Francisco Bay about 20 miles south of city 
of San Francisco. Project works also include a 
channel in San Francisco Bay east of Point San 
Bruno. (See Coast and Geodetic Survey Chart 
5531.) 
Previous projects. For details see page 1979 of 
Annual Report for 1915, and page 1672 of 
Annual Report for 1938. 
Existing project. Channel 500 feet wide and 30 
feet deep across San Bruno Shoal in San 
Francisco Bay; a channel 300 feet wide and 30 
feet deep to vicinity of confluence of West Point 
Slough and Redwood Creek, with a basin at that 
location 2,200 feet long and from 400 to 900 feet 
wide; thence a channel 400 feet wide, 30 feet 
deep, and about 1,300 feet long flaring to a 
second turning basin about 900 feet wide, 1,700 
feet long, and 30 feet deep; thence a channel 150 
feet wide and 5 feet deep extending to Steinberger 
Slough. New work under project cost 
$1,641,279 exclusive of $119,572 contributed by 
local interests and amounts expended on previous 
projects. (See table 34-B for authorizing 
legislation.) 
Local cooperation. (For details see Annual 
Report for 1973.) 
Terminal facilities. See Port Series No. 30, 
"The Ports of San Francisco and Redwood 
City," revised 1962. A new public wharf, a 
privately owned pier for receipts of sand and 
gravel, and a marine repair works pier have 
been constructed since 1962. Facilities are 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Engineering and design including 
dredging surveys by hired labor. 
Condition at end of fiscal year. Project 
completed in January 1965. Total cost of 
existing project to end of fiscal year was 
$4,350,567 of which $1,760,851 was for new 
work ($1,641,279 regular funds and $119,572 
contributed funds) and $2,589,716 regular funds 
for maintenance. 
9. RICHMOND HARBOR, CALIF. 
Location. On eastern shore of San Francisco 
Bay about 10 miles north of Oakland. (See Coast 
and Geodetic Survey Chart 5532.) 
Existing project. Provides for channel 35 feet 
deep and 600 feet wide adjacent to Southampton 
Shoal from deep water in San Francisco Bay to 
outer harbor; inner harbor entrance channel 35 
feet deep and 600 feet wide from deep water to 
Point Richmond, with a turning basin at that 
point; thence a channel 35 feet deep and 500 feet 
wide flaring to about 600 feet at Point Potrero 
with a turn at that point 1,150 feet wide and 35 
feet deep except for a depth of 30 feet at 
southerly apex of bend; thence 35 feet deep and 
850 feet wide to entrance to Santa Fe Channel; 
thence 35 feet deep and 200 feet wide in Santa 
Fe Channel for about 2,000 feet, and maintenance 
to depth of 30 feet of remainder of Santa 
Fe Channel and basin; a rubblemound training 
wall 10,000 feet long extending westerly from 
Brooks Island; approach areas 32 feet deep to 
within 75 feet of pierhead line in outer harbor 
at Point San Pablo and Point Orient; a channel 
20 feet deep, 150 feet wide, and about 2,000 feet 
long from deep water in San Pablo Bay easterly 
along north side of Point San Pablo; a maneuvering 
area at Richmond Long Wharf 45 feet 
deep; and a West Richmond Channel 45 feet 
deep, 600 feet wide, and about 2.5 miles long 
through west navigation opening of Richmond- 
San Rafael Bridge. New work, completed in 
1957, cost $2,886,695, exclusive of $524,778 
contributed by local interests. Estimated cost 
(1975) for 45-foot-deep maneuvering area at 
Richmond Long Wharf and for West Richmond 
Channel, authorized as part of "San Francisco 
Bay to Stockton, California (John F. Baldwin 
and Stockton Ship Channels)" project, is about 
$11,530,000 (See table 34-B for authorizing 
legislation). 
Local cooperation. Fully complied with for 
work performed. Estimated cost for all requirements 
under terms of project authorization, 
including required non-Federal contributions, 
was $4 million (price as of dates of compliance). 
Local interests must furnish easements 
and spoil-disposal areas for maintenance dredging. 
(See Sacramento District Annual Report 
for "San Francisco Bay to Stockton, California 
(John F. Baldwin and Stockton Ship Channels)" 
for requirements of Act of October 27, 1965.) By 
Resolution adopted August 6, 1963, Board of 
Supervisors of Contra Costa County indicated 
willingness to meet requirements applicable to 
West Richmond Channel and maneuvering area 
at Richmond Long Wharf. 
Terminal facilities. See Port Series No. 31, 
"The Ports of Oakland, Alameda, and Richmond 
34-6

SAN FRANCISCO, CALIF., DISTRICT 
and Ports on San Pablo Bay, Carquinez Strait, 
and Mare Island Strait," revised 1962. A 
privately owned dock for receipt of sand and 
gravel and two small-boat basins have been 
constructed since 1962. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
New work: Planning of San Francisco Bay to 
Stockton project continued. Maintenance: Engineering 
and design and U.S. hopper dredge 
Harding removed 262,500 cubic yards of 
shoaled material from inner harbor channel, 
cost $210,676. 
Condition at end of fiscal year. Existing 
project completed in 1957, except for dredging 
West Richmond Channel and enlarging and 
deepening to 45 feet the maneuvering area at 
Richmond Long Wharf authorized as part of 
San Francisco Bay to Stockton project. Dredging 
project channels was initiated in 1918 and 
carried on intermittently until 1940. Training 
wall was completed in 1931, and channel in San 
Pablo Bay in 1945. Dredging authorized by act 
of September 3, 1954, was initiated in October 
1955 and the Southampton Shoal Channel and 
enlarging and deepening to 35 feet the approach 
area to Richmond Long Wharf were completed 
in March 1956, inner harbor channels in 
December 1956, Santa Fe Channel in January 
1957, and removal of rock near Point Potrero in 
October 1957. Minor rehabilitation of training 
wall completed in 1967. 
10. SAN FRANCISCO BAY TO 
STOCKTON, CALIF. (JOHN F. 
BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. On navigation channels extending 
from entrance to San Francisco Bay to vicinity 
of Pittsburg through San Francisco, Marin, 
Contra Costa, Solano Counties. (See Coast and 
Geodetic Charts 5527 and 5532-5534 for respective 
areas.) 
Existing project. Project provides for modification 
of existing San Francisco Harbor, 
Richmond Harbor, San Pablo Bay and Mare 
Island Strait, Suisun Bay Channel to vicinity of 
Pittsburg and Navigation projects to provide 
depths of 55 feet for San Francisco Bar 
Channel, 45 feet for main internal bay channels 
upstream to vicinity of Pittsburg; enlargement 
and deepening to 45 feet of maneuvering areas 
adjacent to major petroleum refinery terminals 
along channel route; widening Suisun Bay 
Channel. Approved cost estimate (1975) of 
Federal cost (Corps), see Sacramento District 
Annual Report. Existing project was adopted 
by 1965 River and Harbor Act (H. Doc. 208, 
89th Cong., 1st sess., contains latest published 
map). 
Local cooperation. See Sacramento District 
Annual Report. 
Term inal facilities. See Part 2, Port Series 
No. 30, 31, and 32, revised 1962, titled respectively: 
"The Ports of San Francisco and 
Redwood City, Calif."; "The Ports of Oakland, 
Alameda, and Richmond and Ports on San 
Pablo Bay, Carquinez Strait and Mare Island 
Strait, Calif." Facilities are considered adequate 
for existing commerce and will be 
adequate for future commerce upon completion 
of new terminal facilities. 
Operatio1.ns and results during .fiscal year. 
New Work: Continued 
Condition at end of fiscal year. Planning 
activities continued. San Francisco Harbor 
Main Ship Channel was completed February 
1974. 
11. SAN FRANCISCO BAY AND DELTA 
MODEL, CALIF. 
Location. The model includes 17 miles of the 
Pacific Ocean beyond the Golden Gate, all of 
San Francisco Bay proper, San Pablo Bay, 
Suisun Bay and all of the Sacramento-San 
Joaquin Delta east of Suisun Bay to the cities of 
Sacramento on the northeast and Stockton and 
Tracy on the south. 
Existing project. The San Francisco 
Bay/Delta Model was constructed in a rehabilitated 
warehouse at Sausalito, California as a 
part of the San Francisco Bay, including San 
Pablo Bay, Suisun Bay and other adjacent bays, 
California Study authorized by the River and 
Harbor Act of May 17, 1950 (PL 81-516, Section 
110). Operation and Maintenance of the model 
was authorized in the Water Resources Development 
Act of 1974 (PL 93-251, Section 8). The 
model has successfully reproduced to the proper 
scale the rise and fall of the tide, flow and 
currents of the water, salinity intrusion and 
trends in disposition of sediments. It is a useful 
tool to examine forces existing in the bay and 
estuarine system and to predict results of 
proposed changes. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Operation and Maintenance: Operation and 
maintenance of the model and building continued. 
Cost $127,912. 
Condition at end of fiscal year. Original model 
construction was initiated 1956 and completed 
1957, and addition of Sacramento-San Joaquin 
Delta to the original model was initiated 1966 
and completed 1969. Continued testing of 
34-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
proposals affecting the environmental quality of 
the region including but not limited to: salinity 
intrusion, dispersion of pollutants, water quality, 
improvements for navigation, dredging, bay 
fill, physical structures and other shoreline 
changes. 
12. SAN FRANCISCO HARBOR, CALIF. 
Location. Works included are in San Francisco 
Bay, in vicinity of San Francisco, and in 
approach channels to Golden Gate, the bay 
entrance. (See Coast and Geodetic Survey Chart 
5532.) 
Previous projects. For details see page 1978 of 
Annual Report for 1915, page 1749 of Annual 
Report for 1921, page 1633 of Annual Report for 
1929, and page 1669 of Annual Report for 1938. 
Existing project. Dredged channel through 
San Francisco Bar on line of main ship channel, 
55 feet deep and 2,000 feet wide; removal of 
Presidio Shoal, Black Point Shoal, Rincon Reef 
Rock (inner), Rincon Reef Rock (outer), Blossom 
Rock, and Alcatraz Shoal westward of a northand-
south line 2,500 feet west of Alcatraz Light, 
to 40 feet deep; removal of Arch Rock, Shag 
Rocks 1 and 2, Harding Rock, Point Knox Shoal 
westward of a north-and-south line through 
Point Stuart Light, and a portion of shoal 
channelward of pierhead line near mouth of 
Islais Creek, to 35 feet deep; and dredging a 
channel 750 feet wide and 10 feet deep from 
that depth in bay to San Francisco Airport 
ending in a basin 10 feet deep and about 2,000 
feet wide. All depth refer to mean lower low 
water. Tidal range between mean lower low 
water and mean higher high water is 5.7 feet at 
Fort Point and 7.2 feet at San Francisco 
Airport. Extreme ranges at foregoing localities 
are 10.6 and 12 feet respectively. New work 
completed in 1959 cost $1,658,957, exclusive of 
$134,591 contributed funds and amounts 
expended on previous projects. Estimated cost 
(1975) for deepening Bar Channel from 50 to 55 
feet, authorized as part of "San Francisco Bay 
to Stockton, California (John F. Baldwin and 
Stockton Ship Channels)" project, is about 
$1,720,000 (See table 34-B for authorizing 
legislation.) 
Local cooperation. Fully complied with for 
work completed. Local interests must furnish 
suitably bulkheaded spoil-disposal areas for 
maintenance of channel to San Francisco 
Airport. (See Sacramento District Annual 
Report for "San Francisco Bay to Stockton, 
California (John F. Baldwin and Stockton Ship 
Channels)" for requirements of Act of 
October 27, 1965.) By Resolution adopted 
August 6, 1963, Board of Supervisors of Contra 
Costa County indicated willingness to meet 
requirements applicable to deepening San 
Francisco Bar Channel. 
Terminal facilities. See Port Series No. 30, 
"The Ports of San Francisco and Redwood 
City," revised 1962. A new deep-water terminal 
has been constructed since 1962. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
New work: Planning for San Francisco Bay to 
Stockton project continued. Maintenance: Condition 
and operation studies and dredging 
surveys of project channels by hired labor and 
U.S. hopper dredge Biddle removed 1,430,900 
cubic yards of shoaled material from main ship 
channel. Cost $831,053. 
Condition at end of fiscal year. Existing 
project completed in 1959, and deepening Bar 
Channel from 50 to 55 feet authorized as part of 
San Francisco Bay to Stockton project was 
completed in 1974. Dredging Islais Creek Shoal 
was completed in 1930, deepening Presidio 
Shoal in 1931, removal of various rocks in 1932, 
deepening Point Knox Shoal in 1934, deepening 
Alcatraz Shoal in 1936, deepening Black Point 
Shoal in 1937, dredging channel and basin at 
San Francisco Airport in 1941, and completion 
of bar channel 50 feet deep in 1959. Cost of 
existing project to end of fiscal year was 
$12,159,569 of which $1,793,548 was for new 
work ($1,465,957 regular funds, $193,000 Public 
Works funds, and $134,591 contributed funds) 
and $10,366,021 regular funds for maintenance. 
13. SAN FRANCISCO HARBOR AND 
BAY, CALIF. 
Location. Project applies to San Francisco 
Bay, lower San Francisco Bay, Oakland Harbor, 
Richmond, San Pablo Bay and Mare Island 
Strait, Richardson Bay, and their tributaries. 
Existing project. Collection and removal of 
drift from San Francisco Bay and its tributary 
waters. New work portion of project (acquisition 
of plant and equipment) is estimated to cost 
(1962) $1,110,000 and is considered inactive 
since a land fill method of disposal is now being 
used. Existing project was authorized by 1950 
River and Harbor Act (H. Doc. 268, 81st Cong., 
1st sess.). 
Local cooperation. None required. 
Terminal facilities. Described in pertinent 
separate project descriptions. 
Operations and results during fiscal year. 
Maintenance: Floating debris was collected and 
disposed of from project waterways by hired 
labor. 
Condition at end of fiscal year. No new work 
construction funds have been appropriated. 
Maintenance operations under existing project 
34-8

SAN FRANCISCO, CALIF., DISTRICT 
commenced July 1950. Costs for removal of drift 
before that time were carried as maintenance 
on applicable authorized river and harbor 
projects in the area. Modification of debrishandling 
facilities to implement the land fill 
method of disposal in lieu of burning completed 
1971. 
14. SAN PABLO BAY AND MARE 
ISLAND STRAIT, CALIF. 
Location. Channel extends from a point in 
lower end of San Pablo Bay west of Pinole Point 
generally northeasterly across Pinole Shoal in 
San Pablo Bay to junction of Carquinez Strait 
and Mare Island Strait, thence northwesterly in 
Mare Island Strait along frontage of Mare 
Island Navy Yard. (See Coast and Geodetic 
Survey Chart 5533.) 
Previous projects. For details see page 1680, 
Annual Report for 1938. 
Existing project. Dredged channel across 
Pinole Shoal in San Pablo Bay 600 feet wide, 45 
feet deep, and about 11 miles long, with a 
maneuvering area 45 feet deep adjacent to 
Oleum Pier at mouth of Carquinez Strait; a 
channel in Mare Island Strait 700 feet wide and 
30 feet deep flaring to a turning basin generally 
1,000 feet wide from former dike 6, Mare 
Island, to a line 75 feet southerly from causeway 
between Vallejo and Mare Island, 30 feet deep, 
except at northerly end where project depth is 
26 feet; maintenance of two approach areas to 
navy yard piers at southern end of Mare Island. 
New work completed in 1943 cost $282,669 
exclusive of amounts expended on previous 
projects. Uncompleted dredging of two 
approach areas at Vallejo and South Vallejo is 
considered inactive. Estimated cost of this 
portion (1956) is $120,000. Estimated cost (1975) 
of lengthening and deepening Pinole Shoal 
Channel to 45 feet and of dredging 
maneuvering area 45 feet deep at Oleum pier, 
authorized as part of "San Francisco Bay to 
Stockton, California (John F. Baldwin and 
Stockton Ship Channels)" project, is about 
$20,950,000 (See table 34-B for authorizing 
legislation.) 
Local cooperation. None required for work to 
date. (See Sacramento District Annual Report 
for "San Francisco Bay to Stockton, California 
(John F. Baldwin and Stockton Ship Channels)" 
for requirements of Act of October 27, 1965.) By 
resolution adopted August 6, 1963, Board of 
Supervisors of Contra Costa County indicated 
willingness to meet requirements applicable to 
deepening Pinole Shoal Channel and dredging 
maneuvering area at Oleum Pier. 
Terminal facilities. See Port Series No. 31, 
"The Ports of Oakland, Alameda, and Richmond 
and Ports on San Pablo Bay, Carquinez Strait, 
and Mare Island Strait," revised 1962. Facilities 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
New work: Planning for San Francisco Bay to 
Stockton project continued. Maintenance: Engineering 
and design including dredging surveys 
by hired labor and U.S. hopper dredge Harding 
removed 2,329,000 cubic yards of shoaled 
material from Mare Island Strait. Cost 
$868,926. 
Condition at end of fiscal year. Existing 
project was completed in 1943 except for 
portion considered inactive (approach areas at 
Vallejo and South Vallejo) and enlarged Pinole 
Shoal Channel and maneuvering area at Oleum 
authorized as part of San Francisco Bay to 
Stockton project. Pinole Shoal Channel 35 feet 
deep was completed in 1929. Mare Island Strait 
Channel and turning basin was completed in 
1943. Costs of existing project to end of fiscal 
year was $14,290,807 of which $282,669 was for 
new work and $14,008,138 for maintenance. 
15. SANTA CRUZ HARBOR, CALIF. 
Location. On north shore of Monterey Bay 
about 65 miles south of entrance to San 
Francisco Bay and 14 miles north of Moss 
Landing, the nearest small-boat harbor. (See 
Coast and Geodetic Survey charts 5402 and 
5403.) 
Existing project. Provides for a small-boat 
harbor consisting of two entrance jetties, east 
jetty 850 feet long and west jetty 1,125 feet long, 
protecting an entrance channel 100 feet wide, 
20 feet deep, and 900 feet long, thence 15 feet 
deep for an additional 370 feet; an inner harbor 
channel 15 feet deep, 150 feet wide, and 800 feet 
long, thence 10 feet deep for an additional 600 
feet, entering a turning basin 10 feet deep, 300 
feet wide, and 207 feet long, and a sandbypassing 
plant if .required. Approved estimated 
cost for new work (July 1964 price levels) 
is $2,910,000, of which $1,890,000 (exclusive of 
Coast Guard cost) is Federal cost and $1,020,000 
to be contributed by local interests (exclusive of 
$18,000 contributed in lieu of providing royaltyfree 
jetty stone). Existing project authorized by 
1958 River and Ha,'bor Act (H. Doc. 357, 85th 
Cong., 2d sess., as modified by Chief of Engineers). 
Local cooperation. Fully complied with for 
completed jetties and channels. Port district 
constructed portion of project for which they 
are responsible, furnished necessary real estate, 
and provided $915,000 for initial share of 
required cash contribution (35.1 percent of 
project first cost) and in lieu of providing 
royalty-free stone. Local interests are required 
to maintain project except jetties and dredged 
34-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
depths in entrance channel, inner channel, and 
turning basin until commencement of sandbypassing, 
at which time they will assume 
operation and maintenance of sand-bypassing 
plant, make replacements thereto, and maintain 
dredged depths in entrance channel, inner 
harbor channel, and turning basin with understanding 
that United States will reimburse 
local interests for actual cost of plant operation, 
maintenance, and replacement up to a limit of 
$35,000 annually, and with further understanding 
that cost of any required channel or basin 
maintenance incurred by the United States will 
be deducted from estimated $35,000 annual 
Federal reimbursement. Santa Cruz Port 
District, by resolution dated December 3, 1957, 
furnished assurances of their willingness and 
ability to comply with requirements. 
Terminal facilities. In the natural harbor 
there is one municipally owned wharf with 
facilities for fueling and servicing boats and 
receiving, handling, and processing fresh fish. 
The small-boat harbor includes a municipal 
pier, utilities, and berthing, marine repair and 
supply facilities. These are considered adequate 
for existing commerce but local interests have 
developed harbor-expansion plans to provide an 
additional 500 berths to meet recreational 
boating needs. 
Operations and results during fiscal year. 
New work: Construction of a sand bypassing 
plant was completed. However, the Santa Cruz 
Port District refused to accept it for operation 
because the dredge was unable to operate in the 
wave environment common to the harbor 
entrance. A Board of Examiners declared the 
dredge and attendant plant unsuitable for 
dredging in a coastal (ocean) environment with 
prevalent heavy swell conditions extending well 
into the inlet site. Maintenance: Engineering 
and design including dredging surveys by hired 
labor and 91,230 cubic yards of shoaled material 
removed by contract from project channels. 
Cost $267,641. 
Condition at end of fiscal year. Project is 
about 95 percent complete. Jetties were completed 
in June 1963 and channel dredging in 
November 1963. Work remaining is provision 
for sand bypassing and periodic harbor maintenance 
dredging. 
16. SUISUN BAY CHANNEL, CALIF. 
Location. Suisun Bay is about 30 miles 
northeast of San Francisco, Calif., and is an 
integral part of waterways which provide 
access to the Pacific Ocean from inland ports of 
California. Sacramento and San Joaquin Rivers 
flow to a junction and empty into Suisun Bay 
near Collinsville, and New York Slough, a 
distributary of San Joaquin River, which leads 
to head of Suisun Bay at Pittsburg, Calif. City 
of Sacramento is on Sacramento River about 60 
miles north of Collinsville; access to city has 
been provided by 10-foot shallow-draft channel 
along river route. Sacramento River deepwater 
ship channel, completed as an operating facility 
for oceangoing vessels in June 1963, provides 
deep-draft access to Sacramento. (For details 
see Improvement No. 1, Sacramento River, 
Calif. Sacramento District's Annual Report.) 
City of Stockton is on San Joaquin River about 
40 miles above Pittsburg and access to city 
provided by Stockton deepwater channel. (See 
Coast and Geodetic Survey Chart 5534.) 
Previous project. For details, see Sacramento 
District's Annual Report page 1756 for year 
1920, page 1562 for year 1926, and page 1714 
for year 1938. 
Existing project. For description of completed 
improvement and authorizing acts, see 
Sacramento District's Annual Report for 1967. 
Total Federal cost of new work for existing 
project, completed in 1934, exclusive of work 
accomplished under public works program as 
part of San Joaquin River 30-foot project, was 
$142,027. No local interests costs were incurred 
(for details, see page 1741 of Sacramento 
District's Annual Report for 1962). Modification 
of existing project is included as one unit of San 
Francisco Bay to Stockton, Calif., (John F. 
Baldwin and Stockton Ship Channels) 
authorized by 1965 River and Harbor Act (H. 
Doc. 208, 89th Congress, 1st sess.); this 
modification is reported in detail under 
Sacramento District, Improvement No. 2. 
Local cooperation. Fully complied with. 
Terminal facilities. Along channel between 
western end of bay and mouth of New York 
Slough are three wharves, all privately owned. 
A naval magazine with wharves and 
warehouses was constructed at Port Chicago, on 
southern shore (mile 6). These facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Project maintenance responsibility 
to Point Edith was transferred from 
Sacramento District, January 1, 1974. Engineering 
and design by hired labor including 
removal of 98,540 cubic yards of shoaled 
material from the channel. Cost $316,223. 
Condition at end of fiscal year. New work 
under existing project was initiated in June 
1930 and completed in 1934; a portion of this 
work was accomplished under public works 
program. Portion of existing project authorized 
before public works program was completed in 
1931 except for deepening 26-foot channel 
across Bulls Head Point to 30 feet; this portion 
was subsequently included in public works 
34-10

SAN FRANCISCO, CALIF., DISTRICT 
program. Work under public works program 
was accomplished during 1933 and 1934. 
Channel is navigable all year and provides 
access to San Francisco Bay and navigation 
channels of San Joaquin and Sacramento 
Rivers. Cost of existing project to end of fiscal 
year exclusive of work under public works 
program at a cost of $207,198 as a part of San 
Joaquin River 30-foot project, was $3,732,353 of 
which $142,027 was for new work and 
$3,590,326 for maintenance. (See table 34-A.) 
17. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and condition surveys of 
channels and harbor structures made throughout 
the year. No maintenance work was 
accomplished on Monterey Harbor, Redwood 
City Harbor, or San Rafael Creek projects 
during fiscal year. 
18. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 34-C. 
19. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to section 107, 
Public Law 86-645 (preauthorization) 
See table 34-D. 
Beach Erosion Control 
20. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
Humboldt Bay, Calif.-Inactive (See 1958 
Annual Report for full details); Santa Cruz, 
County, Calif. (See 1966 Annual Report for full 
details), construction costs $245,639. 
21. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to 
section 103, Public Law 87-874 (preauthorization) 
Fiscal year costs for preauthorization studies 
were $30,000 for Crescent City Bluff, Del Norte 
County, Calif. 
Flood Control 
22. ALAMEDA CREEK, CALIF. 
Location. Drains an area of 695 square miles 
of Coast Range on eastern shore of southern arm 
of San Francisco Bay. Arroyo del Valle, largest 
subtributary, drains 173 square miles of southern 
portion of interior basin. (See Geological 
Survey quadrangles Newark and Niles.) 
Existing project. Provides for levees, channel 
enlargement, bank protection and recreational 
trails system to be constructed by Federal 
Government in Coastal Plain of Alameda Creek 
from mouth in San Francisco Bay about 13 
miles to west end of Niles Canyon; and Federal 
participation in cost of Del Valle Dam and 
Reservoir to be constructed by State of California 
on Arroyo del Valle. Construction of Del 
Valle Dam about 227 feet above streambed will 
provide a gross storage capacity of 77,000 acrefeet 
for flood control and water conservation. 
Federal Government will provide a cash contribution 
commensurate with flood control benefits 
to be derived from reservoir, or 30.7 
percent of construction cost, but not to exceed 
$4,080,000, plus present worth of operation, 
maintenance, and replacement costs allocated to 
flood control during next 50 years. Approved 
estimated project cost (1975) is $59,600,000, of 
which $32,980,000 pertains to Coastal Plain 
channel improvements and $26,510,000 pertains 
to Del Valle Reservoir; total Federal cost is 
$25,945,000 ($20,855,000 Coastal Plain and 
$5,090,000 participation in Del Valle Reservoir 
including a Federal contribution of $4,080,000 
toward construction cost and $776,000 present 
worth of estimated operation and maintenance 
costs for 50 years allocated to flood control 
purposes; and $234,000 for Federal engineering 
and design and supervision administration); 
total non-Federal cost is $33,545,000 
($12,000,000 Coastal Plain lands and relocations, 
contribution of $125,000 for recreation 
facilities, and $21,420,000 Del Valle Reservoir). 
Existing project was authorized by 1962 Flood 
Control Act (S. Doc. 128, 87th Cong., 2d sess., as 
modified by Chief of Engineers). 
Local cooperation. Fully complied with for 
work performed. For details see Annual Report 
for 1973. 
Operations and results during fiscal year. 
New Work: Engineering and design for Coastal 
Plain channel improvements continued by hired 
labor. Under contract construction of four 
erosion control structures, develop pond No. 3, 
channel excavation to remove silt and environmental 
treatment vicinity of Coyote Hills to 
Newark Boulevard and marsh planting is 
continuing. Maintenance: Consists of work 
associated with the reservoir regulation for 
flood control. 
Condition at end of fiscal year. Coastal Plain 
channel improvements begun in April 1965 are 
95 percent complete. Relocation of the Southern 
Pacific Railroad Bridge was completed in 
November 1969. State of California contract for 
34-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
construction of Del Valle Dam began in March 
1966 and was completed in August 1968. State 
contract for relocation of Arroyo Road was 
completed in December 1966. Work remaining: 
construction of remaining four erosion control 
structures, develop pond No. 3, channel excavation 
to remove silt, environmental treatment in 
vicinity of Coyote Hills to Newark Boulevard 
and marsh planting. 
23. CORTE MADERA CREEK, CALIF. 
Location. Creek and tributaries drain an area 
of 28 square miles in Marin County, Calif., and 
discharge into west side of San Francisco Bay 
at a point about 9 miles north of Golden Gate. 
(See Geological Survey quadrangle San Rafael.) 
Existing project. Provides for about 11 miles 
of channel improvements, including realinement, 
enlargement, levees, riprapping, rectangular 
concrete sections, interior drainage facilities, 
bridge relocations, and debris removal on 
Corte Madera Creek and lower reaches of its 
tributaries, and a continuous channel right-ofway 
to deep water in San Francisco Bay 
reserved to assure channel outlet in the event of 
future tideland reclamation. Approved estimated 
cost for new work (1975) is $14,500,000 of 
which $14,300,000 is Federal cost and $200,000 
to be contributed by local interests. (See table 
34-B for authorizing legislation.) 
Local cooperation. Local interests must 
provide lands and rights-of-way, including 
suitable areas for disposal of waste material; 
modify or relocate all bridges and utilities 
necessary for construction and maintenance; 
hold the United States free from damages; 
maintain and operate completed project and 
prevent encroachment on flood channels that 
would decrease effectiveness of project for flood 
control; adjust all claims regarding water 
rights that might be affected by project; 
contribute in cash 1.5 percent of Federal 
construction cost of Ross Valley unit and tidal 
areas, an estimated $180,000. Local interests 
have requested staged construction of the 
project. By Resolutions No. 8861, 9261, 9414 and 
69-208 dated March 29, 1966, March 28, 1967, 
August 15, 1967 and July 8, 1969, respectively, 
the Board of Supervisors of Marin County Flood 
Control and Water Conservation District furnished 
assurances of willingness and ability to 
meet requirements for portion of project below 
Sir Francis Drake Boulevard. Rights-of-way 
and spoil-disposal areas are being acquired, 
relocations accomplished and cash contributions 
provided incrementally in advance of channel 
construction in individual reaches. 
Operations and results during fiscal year. 
New work: Engineering and design continued 
by hired labor. Construction from Lagunitas 
Road to Sir Frances Drake Boulevard delayed 
pending review of alternatives and construction 
upstream of Sir Frances Drake Boulevard 
indefinite due to lack of local support. 
Condition at end of fiscal year. Project 
construction below Sir Francis Drake Boulevard 
is about 75 percent complete. Work 
remaining: construction of unit from the vicinity 
of Lagunitas Road to Sir Francis Drake 
Boulevard and design and construction of 
project above Sir Francis Drake Boulevard, 
which is indefinite due to lack of local support. 
24. NAPA RIVER BASIN, CALIF. 
Location. Napa River rises in St. Helena 
Mountains, flows southerly and empties into 
Mare Island Strait near Vallejo. (See U.S. 
Geological Survey quadrangles, Mare Island, 
Napa and Cutting Wharf.) 
Existing project. Provides for improvement of 
Napa River between Trancas Road and downstream 
end of Edgerley Island (11-mile reach) 
for flood control and recreation purposes by 
channel enlargement and realignment, construction 
of levees and floodwalls and boatlaunching 
ramps and appurtenant recreation 
facilities. Approved estimated cost for new 
work (1975) is $33,150,000 of which $32,500,000 
is Federal cost and $650,000 to be contributed 
by local interests for non-Federal shares of 
recreational development. Existing project was 
authorized by 1965 Flood Control Act (H. Doc. 
222, 89th Cong., 1st sess.) in lieu of inactive 
improvements authorized by Flood Control Act 
of 1944. 
Local cooperation. Act of October 27, 1965, 
requires local interests provide lands and 
rights-of-way, including ponding, borrow, and 
spoil-disposal areas; hold the United States free 
from damages; make necessary modifications or 
relocations of utilities, highway bridges and 
approaches, and highways and roads, exclusive 
of railroad bridge and approaches; prevent 
encroachment on channel works and ponding 
areas which would interfere -with proper 
functioning, and if ponding areas and capacities 
are impaired, provide substitute storage 
capacity or equivalent pumping capacity; adjust 
claims regarding water rights which might be 
affected by project; operate and maintain 
completed works and, with regard to 
recreational facilities, provide lands or rights in 
lands necessary to insure public control of 
recreational development; and where appraised 
value of such land amounts to less than 50 
percent of total first cost of recreational 
34-12

SAN FRANCISCO, CALIF., DISTRICT 
development, make additional contributions 
sufficient to bring ron-Federal share to at least 
that level; operate and maintain boat-launching 
ramps, access roads, parking areas and 
necessary adjacent facilities for boat-launching 
ramps; and assure to all on equal terms. By 
resolutions dated December 17, 1963 and 
October 28, 1969, Napa County Board of Supervisors 
furnished assurances of willingness and 
ability to meet requirements. State and local 
cost sharing of non-Federal project costs, as 
established by Senate Bill 399 and Assembly 
Bill 60, (Sep 73), will be 75 percent/25 percent 
for lands, easements, and rights-of-way, 90 
percent/10 percent for relocations, and 100 
percent for land enhancement costs, Flood plain 
zoning ordinances have been adopted, appraisal 
of lands required for project purposes completed, 
and rights-of-way for initial stage of 
construction will be provided prior to advertising. 
Operations and results during fiscal year. 
New work: Planning for project construction is 
about 85 percent complete. 
Condition at end of fiscal year. Planning is 
about 85 percent complete. 
25. RUSSIAN RIVER BASIN, CALIF. 
Location. Russian River rises in Coast Range 
in northwestern California, flows southerly for 
87 miles, and then turns westerly to flow for 23 
miles to Pacific Ocean at Jenner, 60 miles 
northwest of San Francisco, Calif. (For general 
location see Geological Survey map for California.) 
Existing project. Active authorized project 
provides for construction of a dam on East Fork 
of Russian River at Coyote Valley to a height of 
160 feet; a dam on Dry Creek at Warm Springs 
to a height of 319 feet; and channel stabilization 
works on Russian River between mouth and 
mile 98, on lower reaches of several tributaries, 
and on Dry Creek downstream from dam. 
Coyote Valley Dam (Lake Mendocino), completed 
in 1959, is operated and maintained by 
the United States. (See tables 34-B, 34-E, and 
34-F, for authorizing legislation; latest 
approved estimated cost for new work; and 
details on project features and estimated costs. 
Knights Valley is inactive and has been 
recommended for deauthorization. (See 1974 
Annual Report for project details). 
Local cooperation. Fully complied with for 
Coyote Valley Dam and channel improvements 
accomplished to date. Responsible agencies in 
Sonoma and Mendocino Counties agreed that 
operating instructions for water conservation 
storage and releases will be issued by Sonoma 
County Flood Control and Water Conservation 
District. Total estimated costs for requirements 
under terms of Coyote Valley portion of project 
authorization, including a required non-Federal 
contribution of $5,598,000 in full payment of 
conservation benefits, are $5,844,000. In addition, 
local interests expended about $1 million to 
provide partial flood protection in area, constructed 
water distribution facilities at a cost of 
about $10 million, and plan to construct 
additional facilities in three stages at an 
estimated cost of $35 million. Local interests are 
required by the authorizing act to comply with 
the usual a., b., c. requirements for channel 
improvements and in addition perform necessary 
highway bridge and utility relocations, and 
prevent any encroachment in the channel of Dry 
Creek, which would interfere with proper 
functioning of the channel improvement works; 
adjust all claims concerning water rights 
arising from the construction and operation of 
the improvements, including acquisition of 
water rights needed for preservation of fish and 
wildlife resources affected by the project. Acts 
of October 23, 1962, and November 11, 1966, 
require local interests reimburse the United 
States for all costs allocated to water supply in 
accordance with Water Supply Act of 1958, as 
amended, such costs estimated at $50,300,000 
for construction of Dry Creek (Warm Springs) 
Lake and Channel, in addition to annual costs 
for operation, maintenance and major replacements. 
Sonoma County Water Agency (formerly 
Sonoma County Flood Control and Water 
Conservation District) provided assurances of 
willingness and ability to meet requirements by 
Resolutions No. DR 00793-1, September 1961, 
and No. DR 4770-1, December 17, 1962, for 
Dry Creek (Warm Springs) Lake and Channel. 
Contract providing for reimbursement to the 
United States for Dry Creek (Warm Springs) 
Lake and Channel costs allocated to water 
supply was executed and approved by the 
Secretary of the Army January 6, 1965. By 
letter dated March 7, 1967, Sonoma County 
Flood Control and Water Conservation District 
further indicated their interest in optimization 
of Dry Creek (Warm Springs) damsite to 
provide additional water supply storage. 
Operations and results during fiscal year. 
New work: Continued engineering and design 
and construction of recreation facilities at Lake 
Mendocino. Continued engineering and design 
of Dry Creek (Warm Springs) Lake and 
Channel. However, continued land acquisition 
and construction have been halted by litigation 
since May 30, 1974. Maintenance: Operation 
and maintenance. Coyote Valley Dam, including 
recreation facilities, and condition and operation 
studies by hired labor. 
Condition at end of fiscal year. Entire project, 
exclusive of recreation facilities at completed 
34-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
project (Lake Mendocino), is about 25 percent 
complete. Work remaining is construction of 
Dry Creek (Warm Springs) Lake and Channel 
and channel improvements on Dry Creek 
(Warm Springs) Lake portion of project is about 
34 percent complete. Flow regulation of Coyote 
Valley dam was initiated November 1958 and 
dam and appurtenant works were completed 
April 1959. Relocated State Highway 20 was 
opened to traffic in June 1958, and all work, 
including removal of slides resulting from 
severe storms in 1958, was completed in April 
1959. An initial 4-mile test section of bankstabilization 
work on Russian River near 
Geyerville was completed in February 1957. 
Channel improvements in remaining reaches on 
Russian River and East Fork of Russian River 
were completed in 1974. 
26. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Section 3, Flood Control Act of June 22, 1936, 
as amended and supplemented, included 
requirement that local interests maintain and 
operate completed flood control works in 
accordance with regulations prescribed by the 
Secretary of War. Inspections made throughout 
the year to determine effectiveness of operation 
and maintenance by local interests of completed 
local protection projects and works constructed 
under emergency and special authorities of 
Sections 205 and 208 of the 1948 Flood Control 
Act, Section 14 of the 1946 Flood Control Act, 
and Public Law 99, 84th Congress. Fiscal year 
cost $54,672. Total cost to June 30, 1975 was 
$297,795. 
27. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 34-G. 
28. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended 
(preauthorization). 
Fiscal year costs for preauthorization studies 
were $118,538 of which $3,985 for City of 
Yountville (Hopper Creek), Napa County, Calif., 
$5,000 for Mill and McClure Creeks, Talmage, 
Mendocino County, Calif., $104,553 for Pacifica- 
San Pedro Creek, San Mateo County, Calif., and 
$5,000 for Robinson Creek, Ukiah, Mendocino 
County, Calif. 
Emergency flood control activities-repair, 
flood fighting and rescue u ork (Public Law 99, 
84th Congress, and antecedent legislation). 
Fiscal year costs were $954,293 of which 
$66,202 was for advance preparation, $59,423 
for flood emergency operations and post flood 
reports, and $828,668 for repair and restoration. 
Emergency bank protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th Congress.) 
Fiscal year costs were $265,500 for 
emergency bank protection of which $8,000 for 
Calpella Water District, Russian River, Mendocino 
County, Calif., $152,000 for Blue Lake 
Sewage Treatment Plant, Humboldt County, 
Calif., $16,500 for Eel River, Cock Robin Island 
Bridge, Humboldt County, Calif., $46,000 for 
Fish Hatchery Road and Bridge, Blue Lake, 
Humboldt County, Calif., and $43,000 for 
Mattole River, Lindley Road Bridge, Humboldt 
County, Calif. 
Flood Insurance Activities (Sections 1301- 
1377, 1968 Housing and Urban Development 
Act, PL 90-448 as amended). 
In coordination with flood control activities 
five insurance studies were initiated, and three 
continued from prior year in accordance with 
interagency agreements (IAA) H-8-71, H-15-72 
and H-16-75. Fiscal year cost of $182,091 under 
Housing and Development Act Reimbursable 
order. 
General Investigations 
29. SURVEYS 
See Table 34-H. 
30. COLLECTION AND STUDY OF 
BASIC DATA 
During fiscal year, flood plain management 
service program continued. Studies on Corralitos 
Creek, Freshwater Creek and Penitencia 
Creek are about 60 percent complete and Llagas 
Creek Unit I and Trinity River were initiated. 
Fiscal year cost $161,763. (See table 34-I for 
completed flood plain studies.) 
31. RESEARCH AND DEVELOPMENT 
During fiscal year, hired labor costs of 
$19,041 were incurred for hydrologic studies. 
34-14

SAN FRANCISCO, CALIF., DISTRICT 
TABLE 34-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Bodega Bay, Calif. 
2. Crescent City 
Harbor, Calif. 
3. Humboldt Harbor 
and Bay, Calif. 
4. Moss Landing 
Harbor, Calif. 
5. Noyo River and 
Harbor, Calif. 
(Federal Funds) 
(Contrib. Funds) 
6. Oakland Harbor, 
Calif. 
7. Petaluma River, 
Calif. 
8. Redwood City Harbor, New Work 
Calif. Approp. - 
Cost 
Maint. 
Approp. 16,300 
Cost 16,361 
Total Cost to 
FY 73 FY 74 FY 75 June 30, 1975 
50,000 50,000 
8,914 56,983 
- 14,700 
- 14,668 
660,700 -10,000 
993,171 5,822 
1,378,200 269,800 
57,315 1,590,047 
80,000 
64,222 
13,000 
13,032 
16,500 
17,138 
34-15 
Funding FY 72 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 347,600 
Cost 46,382 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. - 
Cost 
Maint. 
Approp. 2,958,000 
Cost 6,612,115 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 142,740 
New Work 
Approp. -10,337 
Cost 
Maint. 
Approp. 209,200 
Cost 18,343 
Maint. 
Approp. 4,000 
Cost 
Minor rehab. 
Approp. 
Cost - 
New Work 
Approp. 2,442,000 
Cost 7,613 
Maint. 
Approp. 4,629,900 
Cost 2,058,320 
New Work 
Approp. 
Cost 
Maint. 
Approp. 15,300 
Cost 14,779 
821,800' 
771,9201 
311,1942 
311,1942 
397,7793 
397,7793 
7,156,9724 
7,156,9724 
4,284,9975 
4,284,997 
525,0006 
525,0006 
5,658,0767 
5,658,0417 
25,995,0728 
25,992,2438 
338,2159 
338,2159 
1,880,2241o 1 
1,880,22410 " 
463,48212 
463,48212 
2,004,75413 
1,918,33113 
4,000'1 
4,000'1 
222,810'1 
222,81015 
9,657,28416 
9,611,85116 
17,865,37317 
17,847,05417 
297,14616 
297,14616 
2,517,9171" 
2,079,670 " 
1,672,72226 
1,672,72220 
2,589,71621 
2,589,71621 
50,000 - 63,000 
- 28,008 84,957 
599,000 441,000 504,500 
1,688,579 439,677 503,182 
15,000 36,700 312,500 
3,421 29,842 332,077 
18,000 170,000 357,000 
213,009 115,343 325,616 
4,000 - - 
700,070 -16,000 - 678,100 
29,935 2,239,710 1,529,720 
615,000 770,700 760,100 
2,977,891 954,194 769,581 
45,000 24,000 573,750 
45,823 24,019 136,483 
11,000 - 8,500 
10,850 - 8,500

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 34-A (Con't) COST AND FINANCIAL STATEMENT 
See 
Section 
14. San Pablo Bay 
and Mare Island 
Strait, Calif. 
15. Santa Cruz 
Harbor, Calif. 
(Federal Funds) 
(Contrib. Funds) 
16. Suisun Bay Channel, 
Calif. 
22. Alameda Creek, 
Calif. 
23. Corte Madera 
Creek, Calif. 
(Federal Funds) 
(Contrib. Funds) 
24. Napa River Basin, 
Calif. 
Maint. 
Approp. 568,600 
Cost 570,226 
New Work 
Approp. 
Cost 
Maint. 
Approp. 75,800 
Cost 878,021 
New Work 
Approp. 
Cost 215,659 
New Work 
Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
9. Richmond Harbor, New Work 
Calif. Approp. - 
Cost - 
Maint 
Approp. 156,400 
Cost 156,384 
Minor rehab. 
Approp. 
Cost 
10. San Francisco Bay New Work 
to Stockton, Calif. Approp. 714,000 
(John F. Baldwin and Cost 651,417 
Stockton Ship 
Channels) 
11. San Francisco Bay New Work 
and Delta Model, Approp. - 
Calif. Cost - 
Maint. 
Approp. - 
Cost - 
12. San Francisco New Work 
Harbor, Calif. Approp. - 
Cost - 
Maint. 
Approp. 517,500 
Cost 336,513 
13. San Francisco New Work 
Harbor and Bay (Calif.) Approp. 
(Removal of Drift) Cost - 
uontri L. 1 dU,U - - - 
Cost 149,140 728 - 10,131 
Maint. 
Approp. 189,300 211,000 297,800 254,700 
Cost 185,315 182,956 317,856 26,641 
New Work 
Approp. - - - - 
Cost - - - - 
Maint. 
Approp. - - 27,000 305,750 
Cost - - 15,989 316,223 
New Work 
Approp. 1,889,600 2,994,000 686,000 828,200 
Cost 1,410,479 2,556,751 1,417,907 1,096,241 
Maint. 
Approp. 3,200 5,000 5,000 5,000 
Cost 3,200 5,000 4,998 5,002 
New Work 
Approp. 679,400 -66,000 - 13,700 
Cost 595,179 22,001 26,365 43,645 
New Work 
Contrib. - - - - 
Cost 15,000 9,957 - - 
New Work 
Approp. 246,400 26,200 122,000 440,000 
Cost 165,605 51,764 290,110 437,622 
485,000 144,300 206,000 
485,013 139,487 210,676 
- - -_ 
- - - 
650,000 1,100,000 150,000 
728,802 956,140 283,513 
- - 147,000 
- - 127,912 
- - - 
- - - 
1,163,695 1,037,100 1,599,200 
625,976 1,411,878 1,853,430 
560,000 902,000 725,000 
562,170 889,761 703,095 
406,000 871,700 870,000 
406,534 867,782 871,703 
- - -7,851 
81,756 1,508 - 
34-16 
2,886,69522 " 
2,886,6952 
5,210,66424 
5,210,52424 
164,689 
164,689 
3,359,000 
3,253,458 
147,000 
127,912 
2,689,356:1 27 
2,689,356: 2 
10,937,76026 
10,841,34221 
8,677,182 
8,639,817 
1,369,3721 '27 
1,369,3722 '27 
15,369,733 
15,367,5182$ 
1,852,340 
1,852,340 
160,0002 
160,0002 
1,926,259 
1,926,061 
- :" 
334,059" : 
333,521: 1 ": 
24,243,800 
24,155,414 
22,20032 
22,200 
6,219,875 
6,212,118 
97,400 
93,760 
1,884,600 
1,881,532

SAN FRANCISCO, CALIF., DISTRICT 
TABLE 34-A (Con't) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
25. Russian River Basin, 
Calif: 
Coyote Valley Dam New Work 
(Lake Mendocino) and Approp. 297,900 
Channel Improvements Cost 256,658 
Maint. 
Approp. 419,600 
Cost 428,455 
Dry Creek (Warm New Work 
Springs) Lake and Approp. 10,010,300 
Channel Improvements Cost 9,477,748 
1. Includes $641,800 for jetties, bulkheads, main 
Bodega Bay Channel and turning basin completed in 1943. 
2. Includes $52,544 for reconnaissance and condition 
surveys, FY 1956-1975. 
3. Excludes contributed funds of $2,000. 
4. Excludes contributed funds of $233,572 and $2,138 
surplus material from Corps military activities. 
5. Excludes contributed funds of $27,884. Includes 
$56,355 for reconnaissance and condition surveys, FY 1956- 
1975. 
6. Excludes $2,000 contributed funds in lieu of royaltyfree 
rock. 
7. Includes $2,261,371 for previous project. Excludes 
$95,000 contributed funds for existing project. 
8. Includes $98,206 for previous project and $1,641 for 
reconnaissance and condition surveys, FY 1956-1975. 
9. Excludes $5,337 for previous project. 
10. Includes $38,305 for reconnaissance and condition 
surveys, FY 1956-1975. 
11. Excludes $8,539 surplus material from Corps 
military activities. 
12. Includes $11,985 for previous project. 
13. Includes $32,097 for previous project and $15,436 for 
reconnaissance and condition surveys, FY 1956-1975. 
Excludes contributed funds of $820 for previous project. 
14. In lieu of providing dike disposal areas on existing 
project, and excludes $7,180 for previous project. 
15. Excludes contributed funds of $1,700. 
16. Includes $2,899,232 for previous projects. Excludes 
$397,266 contributed funds on existing project. 
17. Includes $684,028 for previous projects and $501 for 
reconnaissance and condition surveys, FY 1956-1975. 
18. Includes $212,083 for previous project. Excludes 
contributed funds of $15,559 for previous project. 
19. Includes $314,692 for previous project and $42,267 
for reconnaissance and condition surveys, FY 1956-1975. 
130,000 -67,000 - 
172,374 20,614 3,439 
445,000 502,800 775,700 
431,570 497,280 758,616 
14,435,8693 : i 
14,434,136 : 
4 5 
5,449,116 
5,403,712 
11,960,000 2,465.000 -200,000 40,509,300 
7,130,396 4,585,537 2,769,665 39,119,977 
20. Includes $31,443 for previous projects. Excludes 
$119,572 contributed funds for existing project. 
21. Includes $11,850 for reconnaissance and condition 
surveys, FY 1956-1975. 
22. Excludes contributed funds of $524,778. Includes 
$105,000 Public Works Administration funds. 
23. Excludes modification authorized October 27, 1965, 
under project "San Francisco Bay to Stockton, Calif. (John 
F. Baldwin and Stockton Ship Channels)." 
24. Excludes $34,800 contributed funds. Includes $3,138 
for reconnaissance and condition surveys, FY 1956-1975. 
25. Includes $1,030,399 for previous projects. Excludes 
$134,591 contributed funds for existing project. 
26. Includes $475,321 for previous projects and $5,234 
for reconnaissance and condition surveys, FY 1956-1975. 
27. Includes $1,086,703 for previous projects. 
28. Includes $1,359,380 for previous projects and $904 
for reconnaissance and condition surveys, FY 1956-1975. 
29. Excludes $810,046 contributed funds on previous 
project. 
30. See Sacramento District FY 1974 Annual Report for 
details. 
31. Project maintenance responsibility to Point Edith 
was transferred to San Francisco District January 1, 1974. 
Excludes Sacramento District's portion. Includes $1,309 for 
reconnaissance and project condition surveys, FY 1975. 
32. Includes $22,200 for scheduling reservoir operations. 
33. Excludes $5,598,000 contributed funds and $400,000 
for recreation facilities at completed projects funded under 
Public Work Acceleration Program. 
34. Excludes $1,515,211 for recreation facilities at 
completed projects funded under Code 711. 
35. Excludes $1,435,572 for recreation facilities at 
completed projects funded under Code 711. 
34-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 34-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 18, 1918 
Sept. 22, 1922 
Jan. 21, 1927 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Oct. 27, 1965 
June 25, 1910 
July 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 
July 16, 1952 
Aug. 13, 1968 
July 3, 1930 
Mar. 2, 1945 
July 14, 1960 
Oct. 23, 1962 
34-18 
CRESCENT CITY HARBOR, CALIF. (See Section 2 of Text) 
Breakwater. H. Doc. 434, 64th Cong., 
1st sess. 
Conditions of local cooperation modified. Rivers and Harbors Committee 
Doc. 4, 67th Cong., 2nd sess. 
Extend breakwater to 3,000 feet long. H. Doc. 595, 69th Cong., 
2nd sess. 
Dredge harbor basin, 1,800 feet long, 1,400 feet Rivers and Harbors Committee 
wide, and 20 feet deep. Doc. 40, 74th Cong., 1st sess. 
Sand barrier and maintenance dredging in vicinity of S. Commerce Committee print. 
seaward end thereof. 75th Cong., 1st sess. 
Extend breakwater to Round Rock (modified by H. Doc. 688, 76th Cong., 
Chief of Engineers). 3rd sess. 
Inner breakwater and removal of rock in inner harbor. Report on file in Office, Chief 
of Engineers: 
Extend inner breakwater 400 feet and dredge T-shaped H. Doc. 264, 89th Cong. 1 
basin 20 feet deep. 
HUMBOLDT HARBOR AND BAY, CALIF. (See Section 3 of Text) 
Rebuilding the jetties. H. Doc. 950, 60th Cong., 
1st sess. 
Depth of 20 feet and widths of 250 and 300 feet in bay H. Doc. 755, 69th Cong., 
channels and for channel to Arcata Wharf. 2nd sess. 
Entrance channel, 500 feet wide, 30 feet deep. Rivers and Harbors Committee 
Doc. 14, 74th Cong., 1st sess. 
Widths of 400 feet in Eureka Channel and 300 feet in Rivers and Harbors Committee 
Samoa and Fields Landing Channels, and construct Fields Doc. 11, 75th Cong., 1st sess. 
Landing Turning Basin, 600 feet wide and R80 feet 
long, all to a depth of 26 feet. 
Deepen to 40 feet and widen bar and entrance channel; H. Doc. 143, 82nd Cong., 
deepen Eureka and Samoa Channels to 30 feet; and 1st sess. 
construct North Bay Channel, 400 feet wide, 30 feet deep. 
Deepen to 35 feet North Bay and Samoa Channels and outer H. Doc. 330, 90th Cong., 
reach of Eureka Channel (miles 4.29 to 5.00); widen bends, 2nd sess.' 
miles 0.75 and 2.6; and construct North Bay anchorage area 35 
feet deep. 
NOYO RIVER AND HARBOR, CALIF. (See Section 5 of Text) 
Entrance channel, jetties, and channel in river. S. Doc. 156, 71st Cong., 
2nd sess. 
South breakwater in Noyo Harbor.3 H. Doc. 682, 76th Cong., 
3rd sess. 
Mooring basin in lieu of channel extension authorized by H. Doc. 289, 86th Cong., 
Act of June 30, 1948.4 2nd sess. 
North Breakwater in Noyo Harbor.3 S. Doc. 121, 87th Cong., 
2nd sess.' 
OAKLAND HARBOR, CALIF. (See Section 6 of Text) 
Jetties. Annual Report, Part II, 
1874, p. 378. 
North channel in Brooklyn Basin, 25 feet deep, and tidal H. Doc. 647, 61st Cong., 
canal to 18 feet. 2nd sess. 
Channel across shoal southeast of Yerba Buena Island and H. Doc. 144, 67th Cong., 
thence to Webster St.,; South channel in Brooklyn Basin; 2nd sess. 
Turning Basin at east end of Brooklyn Basin; and channel 
in Tidal Canal from Brooklyn Basin to Park St., 30 feet 
deep. 
Channel from Webster St. to Brooklyn Basin, maintain area H. Doc. 407, 69th Cong., 
to within 75 feet of pierhead line south of channel 1st sess.' 5 
from Harrison St. to Harbor Line Point 119 in Brooklyn 
Basin; dredge a triangular strip about 2,700 feet long 
and maximum width of 300 feet at western end of Brooklyn 
Basin, 30 feet deep. 
Local cooperation requirements modified to provide Public Res. 28, 70th Cong. 
alteration or replacement of bridges by local interests shall apply 
only to that feature of project covering deepening tidal canal 
to 25 feet. 
June 23, 
June 25, 
Sept. 22, 
1874 
1910 
1922 
Jan. 21, 1927 
Apr. 28, 1928

TABLE 34-B (Con't) 
SAN FRANCISCO, CALIF., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
Mar. 2, 1945 
Mar. 2, 1945 
Oct. 23, 19626 
June 25, 1910 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
May 17, 1950 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 19357 
June 20, 1938 
Mar. 2, 1945 
Sept. 3, 1954 
Drawbridges across Tidal Canal were required by 1882 
Decree of Court in condemnation proceedings whereby title was 
obtained to right-of-way for tidal canal. 
Entrance channel to outer harbor, 800 to 600 feet wide. 
Eliminated requirement that local interests contribute 
10 cents per cubic yard toward deepening tidal canal. 
Maintenance of 35-foot depth in channel to outer harbor and 
in outer harbor channel and turning basin. 
Deepen inner harbor 30-foot channels and lower 1,300 
feet of north channel in Brooklyn Basin to 35 feet. 
REDWOOD CITY HARBOR, CALIF. (See Section 8 of Text) 
A 5-foot channel to Steinberger Slough. 
A 20-foot channel to West Point Slough. 
A 27-foot channel to West Point Slough and a turning basin 27 
feet deep, 1,800 feet long, and 700 feet wide. 
A 30-foot channel across San Bruno Shoal and enlarge and 
deepen 27-foot channel and turning basin in Redwood Creek to 
30 feet. 
Extend 30-foot channel 1,300 feet upstream and provide a 
second turning basin 30 feet deep, 900 feet wide, and 1,700 
feet long at junction of Redwood Creek and Boundary Slough. 
Project name changed from Redwood Creek, Calif., to Redwood 
City Harbor, Calif. 
RICHMOND HARBOR, CALIF. (See Section 9 of Text) 
Channel 24 feet deep and 600 feet wide from San Francisco 
Bay to Ellis Slough (Santa Fe Channel); a turning basin 
at Point Potrero; a training wall. 
A 30-foot channel with lessened widths; a turning basin 
at head of navigation. 
Increase project widths in inner harbor, maintenance of 
Santa Fe channel to 30 feet; approach areas in outer harbor 
to 32 feet. 
Widen channel at Point Potrero and north thereof; enlarge 
and maintain to 30-foot depth turning basin at Terminal No. 1. 
Channel 20 feet deep, 150 feet wide, in San Pablo Bay 
north of Point San Pablo. 
Channel 35 feet deep and 600 feet wide adjacent to Southampton 
Shoal; enlarge and deepen to 35 feet approach area to 
Richmond Long Wharf; widen and deepen inner harbor and 
entrance channels; deepen turning basin at Point Richmond 
and southerly 2,000 feet of Santa Fe Channel. Eliminate 
restriction that widening north of Point Potrero will not 
be undertaken until local interests furnish assurances 
industries will avail themselves of improved navigation 
facilities. 
Rivers and Harbors Committee 
Doc. 43, 71st Cong., 2nd sess. 
H. Doc. 466, 77th Cong., 
1st sess. 
Report on File in Office, Chief 
of Engineers. 
H. Doc. 353, 87th Cong., 
2nd sess.' 
H. Doc. 307, 61st Cong., 2nd sess. 
H. Doc. 142, 70th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 10, 73rd Cong., 1st sess. 
H. Doc. 94, 79th Cong., 1st sess. 
H. Doc. 104, 81st Cong., 1st sess.' 
H. Doc. 515, 63rd Cong., 
2nd sess. 
Rivers and Harbors Committee 
Doc. 16, 70th Cong., 1st sess. 
Rivers and Harbors Committee 
Does. 7, 73rd Cong., 1st sess, 
and 10, 74th Cong., 1st sess. 
H. Doc. 598, 75th Cong., 
3rd sess. 
H. Doc. 715, 76th Cong., 
3rd sess. 
H. Doc. 395, 83rd Cong., 
2nd sess.' 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 19357 
Aug. 26, 1937 
SAN FRANCISCO HARBOR, CALIF. (See Section 12 of Text) 
Dredging at Islais Creek. H. Doc. 337, 69th Cong., 
1st sess. 
Remove Presidio Shoal, Rincon Reef Rock (Inner), Rincon H. Doc. 196, 70th Cong., 
Reef Rock (Outer), Blossom Rock, and Alcatraz Shoal 1st sess. 
to 40 feet deep, mean lower low water; remove Arch 
Rock, Shag Rocks 1 and 2, and Harding Rock to 35 feet 
deep; remove Racoon Shoal and Point Knox Shoal westward 
of a north-and-south line through Point Stuart Light 
to 35 feet deep; for a bar main ship channel 45 feet 
deep and 2,000 feet wide. 
A 50-foot depth in bar main ship channel, 2,000 feet Rivers and Harbors Committee 
wide, remove Black Point Shoal to 40 feet deep and certain Doc. 50, 72nd Cong., 2nd sess. 
modifications of areas to be deepened on Alcatraz and 
Islais Creek Shoals and abandon 34-foot depth area south of 
flared approach channel to Islais Creek. 
Channel to San Francisco Airport 750 feet wide and 10 feet Rivers and Harbors Committee 
deep ending in a basin 2,000 feet wide. Doc. 12, 75th Cong., 1st sess.' 
34-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 34-B (Con't) AUTHORIZING LEGISLATION 
Acts 
Jan. 21. 1927 
June 20, 1938 
Mar. 2, 1945 
Oct. 23, 1962 
Nov. 7, 1966 
May 17, 1950 
Feb. 10, 1956 
Oct. 23, 1962 
Nov. 11, 1966 
Work Authorized 
SAN PABLO BAY AND MARE ISLAND STRAIT, CALIF. (See 
Section 14 of Text) 
Pinole Shoal Channel 35 feet deep, 600 feet wide, 7.6 miles F 
long; Mare Island Strait channel 30 feet deep, 600 feet 
wide with turning basin 1,000 feet wide. 
Increase width of channel in Mare Island Strait to 700 feet 
and increase length of turning basin. 
Maintain approach areas to Navy Yard Piers at south end 
of Mare Island. 
CORTE MADERA CREEK, CALIF. (See Section 23 of Text) 
Levees and channel improvements, lower 11 miles of Corte F 
Madera Creek and tributaries, as modified by Chief of 
Engineers. 
Local cooperation requirements modified to provide 1.5 
percent cash contribution toward cost of Ross Valley unit. 
RUSSIAN RIVER BASIN, CALIF. (See Section 25 of Text) 
Coyote Valley Dam (Lake Mendocino): Channel improvements 
on lower 98 miles of Russian River and lower reaches 
of tributaries. 
Increased appropriation authorization for initial stage F 
of project development. 
Dry Creek (Warm Springs) Lake; Channel Improvements on 
Dry Creek below dam. 
Knights Valley Lake (Franz and Maacama Dams). 
Documents 
H. Doc. 104, 69th Cong., 
1st sess. 
H. Doc. 644, 75th Cong., 
3rd sess. 
H. Doc. 217, 77th Cong., 
1st sess. 
H. Doc. 545, 87th Cong., 
2nd sess. 
Sect. 204, 1966 Flood Control 
Act. 
H. Doc. 585, 81st Cong., 
2nd sess. 
Public Law 404, 84th Cong., 
2nd sess. 
H. Doc. 547, 87th Cong., 
2nd sess. 
H. Doc. 518, 89th Cong., 
2nd sess.' 
1. Contains latest published map. 
2. Previously authorized Public Works Administration 
program, Sept. 6, 1933. 
3. Inactive. Requires determination by Area 
Redevelopment Administration that improvement is 
essential to its program for redeveloping the area. 
4. A 400-foot channel extension, mooring basin and 
connecting channel constructed by Noyo Harbor District. 
The channel extension to be maintained by the Federal 
Government. 
5. Included deepening of tidal canal above Park Street 
Bridge to 25 feet, which is being declared inactive. 
6. Included Federal participation in reconstruction of 
Fruitvale Avenue Highway Bridge (S. Doc. 75, 87th Cong., 
2nd sess.) which is being accomplished with Operation and 
Maintenance funds. 
7. Included in part in Public Works Administration 
Program, Sept. 6, 1933. 
8. Included dredging two approach areas at Vallejo and 
South Vallejo, which is considered inactive. 
9. Included levee on Carnadero Creek which is 
considered inactive. 
34-20 
'~-----

SAN FRANCISCO, CALIF., DISTRICT 
TABLE 34-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 18 of Text) 
For Last Cost To June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Berkeley Harbor, Calif.' 1966 155,5502 
Halfmoon Bay Harbor, Calif." 1967 6,697,3964 110.103: 
Lower San Francisco Bay, Calif. (Inactive) 1935 
Monterey Harbor, Calif. (Inactive) 1971 1,108,1766 88.179 
Napa River, Calif: 
Channels3 1963 1,021,2747 541,2246 
Dikes and Revetments (Inactive) 1963 
San Francisco Marina (Gas House Cove) 1974 180,4729 153,6189 
San Rafael Creek, Calif.3 1970 32,359'� 879.371" 
Suisun Channel, Calif.'2 1972 217,67712 729.63612 
1. Authorized by Chief of Engineers (Sec. 107, Public 8. Includes $155,599 reconnaissance and condition 
Law 86-645). Completed October 1965. surveys, FY 1956-1975. 
2. Excludes $155,551 contributed funds. 9. Includes preauthorization costs $26,855 and excludes 
3. Completed. contributed funds $153,618 completed May 1975. 
4. Excludes $100,000 contributed funds. 10. Excludes $41,094 contributed funds. 
5. Includes $10,103 for reconnaissance and condition 11. Includes $72,924 reconnaissance and condition 
surveys, FY 1975. surveys, FY 1956-1975. 
6. Includes $207,800 Public Works Administration 12. Project maintenance assigned to San Francisco 
funds and Dikes and Revetments placed inactive 1974. District from Sacramento District January 1. 1974. See 
7. Excludes previous project costs. Sacramento District 1972 Annual Report for full report. 
TABLE 34-D NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant To Section 107, P.L. 86-645 (Preauthorization) 
(See Section 19 of Text) 
Study Identification Fiscal Year Costs 
Belmont Marina Channel, Calif. $17.444 
Oakland Outer Harbor, Calif. 3.565 
San Francisco Harbor (Islais Creek), Calif. 9.742 
San Leandro Marina, Calif. 53.323 
Total $84.074 
34-21

TABLE 34-E 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
RUSSIAN RIVER BASIN, CALIF.: ESTIMATED 
COST FOR NEW WORK 
(See Section 25 of Text)
Estimated Cost 
Non-Federal 
Project Feature Federal Contribution Total 
Coyote Valley Dam (Lake Mendocino); 
Channel Improvements Below Dam 
on Lower 98 Miles of Russian River $ 14,340,000 $ 5,598,000 $ 19,938,000' 
Dry Creek (Warm Springs) Lake; Channel 
Improvements Below Dam 130,700,000 50,300,0002 181,000,000 
Total $145,040,000 $55,898,000 $200,938,000 
1. Exclusive of $2,150,000 for recreation facilities at 
completed projects. 
2. Reimbursement by local interests to Federal Government 
for costs allocated to water supply storage to be paid 
over a period not to exceed 50 years after use of storage is 
initiated. 
TABLE 34-F RUSSIAN RIVER BASIN, CALIF.: PROJECT 
FEATURES AND ESTIMATED COSTS 
(See Section 25 of Text) 
Height of Reservoir 
Nearest City Distance Dam and Capacity Estimated 
Name (California) Above Mouth Type (Acre-Ft) Cost 
Coyote Valley Dam (Lake Ukiah Mile 0.8-East Fork 160 Feet-Earthfill 122,500 $ 17,550,000' 
Mendocino) of Russian River 
Channel Improvement (East Fork Ukiah Mile 0 to 0.8 East - - 2,482,000 
Fork 
Below Coyote Valley Dam and Guerneville Mile 0 to 98, Russian - 
Lower 98 Miles of Russian River) River 
Dry Creek (Warm Springs) Lake Healdsburg Mile 14.4-Dry Creek 319 Feet-Earthfill 381,000 179,260,000 
Channel Improvement (Dry Creek) Healdsburg Mile 1 to 14.4 Dry - - 1,740.000 
Below Dry Creek (Warm Springs Creek 
Dam) 
1. Exclusive of $2,150,000 for recreation facilities at 
completed projects. 
34-22

SAN FRANCISCO, CALIF., DISTRICT 
TABLE 34-G OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 27 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Alhambra Creek, Calif.' 1969 
Coyote Creek, Calif.2 1968 705,622 
East Weaver Creek, Calif.2 1965 220,636- 
Eel River, Calif. (Inactive) 1971 1,272,816- 
Klamath River, Calif. 7 1972 4,838,000 
Mad River Basin, Calif. (Inactive)5 1973 3,762,3845 
Pajaro River, Calif.s 1974 905,1586 
Pinole Creek, Calif. 2 1968 885,750 
Redwood Creek, Humboldt County, Calif.7 1970 4,513,225 
Rheem Creek, Calif.2 1962 400,000- 
Rodeo Creek, Calif.2 1966 974,100 
Salinas River, Calif.9 1952 94,213 
San Leandro Creek, Calif.7 1973 1,000,000'" 
San Lorenzo Creek, Calif.7 1962 5,130,821" 
San Lorenzo River, Calif.7 1966 4,314,40612 
Sonoma Creek, Calif. (Inactive)' 1973 781,500 
1. Placed inactive 1974. 7. Completed. 
2. Authorized by Chief of Engineers (Sec. 205, Public 8. Excludes $52,549 contributed funds. 
Law 86-645). Completed. 9. Improvement inactive. Cost includes engineering 
3. Includes $174,938 Public Works Acceleration and design prior to June 30, 1952 and costs of $4,288 FY 
Program Funds. 1962 and 1963 to determine if project classification to an 
4. Excludes $194,821 contributed funds and placed active category was justified. 
inactive 1973. 10. Excludes $285,329 contributed funds. 
5. Placed inactive 1974. Excludes $225,000 applicable 11. Excludes $200,000 estimated value of work 
to Public Works Acceleration Program and $162,761 performed in lieu of cash contribution. 
previous project, Blue Lake levee. 12. Excludes $421,182 contributed funds. 
6. Project delayed due to lack of local cooperation. 
Excludes $748,283 previous project. 
TABLE 34-H SURVEYS 
(See Section 29 of Text) 
Type of Study Fiscal Year Cost 
Navigation $ 296,656 
Flood Control 1,109,942 
Beach Erosion 1,686 
Review of Authorized Projects 8,466 
Coordination Studies with Other Agencies 19,041 
Total Surveys $1,435,791 
34-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 34-I FLOOD PLAIN STUDIES COMPLETED DURING FISCAL YEAR 
(See Section 30 of Text) 
Federal 
Location Requesting Agency Completed Cost 
Rush Creek, Calif. Marin County Jun 1975 $30.000 
San Benito River, Calif. San Benito County Nov 1974 35,000 
San Felipe Lake, Calif. San Benito County Jun 1975 25.000 
34-24

SACRAMENTO, CALIF. DISTRICT* 
This district comprises basins of Suisun Bay 
and San Joaquin and Sacramento Rivers in 
California; Goose Lake in Oregon; basins of the 
Great Salt Lake and Sevier Lake in Utah; an 
intervening portion of Great Basin in 
southeastern Idaho; and the upper Colorado 
River basin, which is in southwestern Wyoming,, 
eastern Utah, northeastern Arizona, 
northwestern New Mexico, and western 
Colorado, west of the Continental Divide. 
IMPROVEMENTS 
Navigation Page 
1. Sacramento River, Calif. ............ 35-2 
2. San Francisco Bay to Stockton, 
Calif. (John F. Baldwin and 
Stockton Ship Channels ............. 35-2 
3. San Joaquin River, Calif............. 35-3 
4. Reconnaissance and Condition 
Surveys ..................... ...... 35-4 
5. Other authorized navigation 
projects ............................. 35-4 
Flood Control 
6. Buchanan Dam-H. V. Eastman 
Lake, Chowchilla River, Calif........ 35-4 
7. Calaveras River and Littlejohn 
Creek and tributaries, including 
New Hogan Lake and Farmington 
Dam, Calif .......................... 35-5 
8. Chester, Calif....................... 35-6 
9. Fairfield Vicinity Streams, Calif..... 35-6 
10. Gleason Creek Dam, Nev............ 35-7 
11. Hidden Dam-Hensley Lake, Fresno 
River, Calif....................... 35-8 
12. Humboldt River and Tributaries, 
Nev .................................. 35-8 
13. Isabella Lake, Kern River, Calif..... 35-9 
14. Kaweah and Tule Rivers, including 
Terminus Dam and Success Lake, 
Calif................................35-10 
15. Lake Camanche, Calif. .............. 35-12 
16. Lake Oroville, Calif.................. 35-12 
17. Lakeport Lake, Scotts Creek, Calif... 35-13 
18. Little Dell Lake, Utah .............. 35-13 
19. Lower San Joaquin River and 
tributaries, including Tuolumne and 
Stanislaus Rivers, Calif.............. 35-14 
Flood Control (con't) Pa g, 
20. Martis Creek Lake, Martis Creek, 
Nev. and Calif....................... 35-15 
21. Merced County Stream Group, 
Calif .............................. 35-15 
22. Merced County Streams, Calif....... 35-16 
23. Merced River, Calif. ................ 35-17 
24. Mormon Slough, Calaveras River, 
Calif ............................... 35-17 
25. Pine Flat Lake and Kings River, 
Calif ................................... 35-17 
26. Sacramento River and tributaries, 
Calif., from Collinsville to Shasta 
Dam ................................ 35-19 
27. Walnut Creek, Calif.............. 35-21 
28. Inspection of completed flood 
control projects ..................... 35-22 
29. Scheduling flood control reservoir 
operations...........................35-22 
30. Other authorized flood control 
projects ............................. 35-22 
31. Flood control work under special 
authorization .......... ............. 35-22 
Multiple-Purpose Projects including Power 
32. Marysville Lake, Calif ............... 35-23 
33. New Melones Lake, Calif. .......... 35-23 
General Investigations 
34. 
35. 
36. 
Surveys ................. .......... 35-24 
Collection and study of basic data ... 35-24 
Research and development ......... 35-24 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text 
and also appear at the end of this chapter. 
35-1 
_ _

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Navigation 
1. SACRAMENTO RIVER, CALIF. 
Location. Rises in Trinity Mountains in northcentral 
California, flows generally southerly 
about 374 miles and empties into Suisun Bay, 
an arm of San Francisco Bay, at Collinsville, 
Calif. (See Geological Survey topographic map 
of Sacramento Valley, Calif.) 
Previous projects. For details see page 1985 of 
Annual Report for 1915 and page 1708 of 
Annual Report for 1938. 
Existing project. For description of 
Sacramento Deep Water Ship Channel, see 
Annual Report for 1969. Total first cost for 
completed portion was $43,932,558 ($39,560,558 
Federal (Corps), $300,000 (Coast Guard), and 
$4,072,000 non-Federal for lands and damages, 
including relocations) and excludes local 
interests cost $10,741,000 (June 1963) for 30-foot 
deep water ship channel and 13-foot deep 
connecting canal basic terminal facilities 
required under terms of project authorization. 
Project also provides for a shallow-draft 
channel 10 feet deep at mean lower low water 
150 to 200 feet bottom width, from Suisun Bay 
to Sacramento, Calif., 60 miles; a depth of 6 feet 
at low water between Sacramento and Colusa, 
85 miles; a depth of 5 feet at low water between 
Colusa and Chico Landing, 50 miles; and such 
depths as practicable between Chico Landing 
and Red Bluff, 53 miles, a total distance of 248 
miles. Estimated Federal cost (July 1973) of 
new work for shallow-draft river channel is 
$1,360,000 (includes $1,163,000 for deferred 
portion between Colusa and Chico Landing). 
(See table 35-B for authorizing legislation.) (See 
table 35-C on tidal and flood conditions prevailing.) 
Local cooperation. Fully complied with for 
deep water ship channel project. None required 
on shallow-draft feature. 
Terminal facilities. Piers, wharves, and docks 
at Port of Sacramento for shallow-draft navigation 
are open-pile structures with timber decks, 
some of which are designed to meet extreme 
high waters at flood stages. All main wharves at 
Sacramento have rail connections. Three of 
above facilities are owned by city of Sacramento 
and remainder by private interests; all are 
privately operated. For full description see 
"Port and Terminal Facilities at the Ports of 
Stockton and Sacramento, Calif., 1962." Deep 
water terminal facilities comprise wharves and 
piers, administration and storage buildings, and 
belt railroad facilities. Majority of these 
facilities are owned and operated by 
Sacramento-Yolo Port District; remainder are 
privately owned and operated. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
New work, Deep Water Ship Channel: None. 
(See table 35-D for major items of work 
included in maintenance.) 
Condition at end of fiscal year. Construction 
of 7-foot shallow-draft channel below 
Sacramento was initiated in September 1899 
and completed in 1904. Modified 10-foot 
shallow-draft channel up to Sacramento was 
initiated in fiscal year 1928 and completed in 
1931. Shallow-draft channel above Sacramento 
began in April 1946 and new work is about 48 
percent complete. In February 1974, remaining 
work for shallow-draft portion of project, 
provision of a 5-foot depth between Colusa and 
Chico Landing (50 miles), was reclassified as 
"deferred." Channel is navigable all year; 
however, there is no regular navigation above 
Colusa, 145 miles above river mouth. Construction 
of 30-foot deep water ship channel was 
initiated in July 1949; improvement dredging 
by continuing contracts resulted in provision of 
an operational facility for oceangoing vessels 
during June 1963. Bascule bridge was completed 
in April 1960, barge lock in August 1961, 
barge canal in November 1961, and entire deep 
water ship channel in June 1970. 
2. SAN FRANCISCO BAY TO 
STOCKTON, CALIF. (JOHN 
F. BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. On navigation channels extending 
from entrance to San Francisco Bay to Port of 
Stockton through San Francisco, Marin, Contra 
Costa, Solano, Sacramento, and San Joaquin 
Counties. (See Coast and Geodetic Charts 5527 
and 5532-5534 for respective areas.) 
Existing project. Project provides for 
modification of existing San Francisco Harbor, 
Richmond Harbor, San Pablo Bay and Mare 
Island Strait, Suisun Bay Channel, and San 
Joaquin River Navigation projects to provide 
depths of 55 feet for San Francisco Bar 
Channel, 45 feet for main internal bay channels 
upstream to vicinity of Pittsburg, and 35 feet 
from Pittsburg to Stockton; enlargement and 
deepening to 45 feet of maneuvering areas 
adjacent to major petroleum refinery terminals 
along channel route; widening Suisun Bay 
Channel; providing access and turning basin 
facilities for potential harbor in vicinity of 
Antioch; constructing a cutoff route to Stockton 
through False River and across certain Delta 
tracts; reclaiming shoreline marshes and inun- 
35-2

SACRAMENTO, CALIF., DISTRICT 
dated or low-lying areas by spoil deposit for 
public recreation and for industrial use; 
providing basic recreation facilities on some of 
the reclaimed areas for public use; and placing 
additional rock revetment on waterside of levees 
bordering channels. 
Approved project estimate (July 1975) is 
$124,460,000, comprising Federal cost (Corps) 
of $95,200,000, including basic recreation 
facilities ($2,080,000); Federal cost (Coast 
Guard) for navigation aids $760,000; and non- 
Federal cost of $28,500,000 for lands and 
damages, relocations, berthing areas, and spoil 
retention dikes, including the cash contribution 
($400,000) that local interests must make for 
land enhancement at time of construction. Local 
interests must also pay, contribute in kind, or 
repay with interest one-half of separable cost of 
project allocated to recreation and fish and 
wildlife $1,420,000. Existing project was 
adopted by 1965 River and Harbor Act (H. Doc. 
208, 89th Cong., 1st sess., contains latest 
published map). 
Local cooperation. Local interests, through a 
public body legally authorized and financially 
capable, must give assurances they will furnish 
lands, easements, and rights-of-way for construction 
and future maintenance of the project 
and for aids to navigation, including spoildisposal 
areas designated by the Chief of 
Engineers; provide necessary spoil retention 
dikes, bulkheads, and embankments except as 
applicable to spoil-disposal areas designated as 
public recreation areas; make utility 
modifications and relocations required for 
construction, including new bridges or bridge 
alterations (except for railroad bridges), and 
absorb any increased annual maintenance and 
operation costs resulting therefrom; provide and 
maintain all necessary berthing areas, at a 
depth commensurate with project depth, at all 
terminals and wharves to be served by the 
deepened channels and, for the Port of Antioch, 
provide, maintain, and operate public terminal 
and transfer facilities; and in recognition of the 
local land enhancement benefits to result from 
landfill during dredging, contribute to the 
United States 4 cents per cubic yard of all spoil 
material placed during initial construction for 
modification of Suisun Bay Channel project on 
areas not developed for public use. Local 
interests must also give satisfactory assurances, 
before starting construction of the affected 
units, that they will maintain and operate the 
Federally provided recreation areas and 
facilities, continue to maintain to adequate 
standards the levees altered, setback or 
provided revetment protection, and hold the 
U.S. Government free from damages due to 
deposition of spoil and construction of new 
levees or reconstruction of existing levees. Local 
interests, represented by Board of Supervisors 
of Contra Costa County and Stockton Port 
District, must, at time of construction, contribute 
$400,000 in cash for land enhancement; 
pay, contribute in kind, or repay with interest 
one-half of separable cost of project allocated to 
recreation and fish and wildlife ($1,420,000); 
and maintain and operate basic recreation 
facilities after construction and install 
additional basic facilities required as demands 
on area expand. No work shall be undertaken 
on a modification of Suisun Bay Channel project 
unit, regarding deepening channel between 
Point Edith and a proposed refinery or 
manufacturing plant, until local interests furnish 
formal assurances and definite plans for 
such installation within the Point Edith-Chipps 
Island reach of channel. Also, no work shall be 
undertaken on modification of San Joaquin 
River navigation project unit, regarding access 
channels in vicinity of Antioch, until local 
interests furnish formal assurances and definite 
plans for Port of Antioch. Formal assurances 
for deepening and otherwise improving the 
Stockton Deep Water Ship Channel from lower 
end of New York Slough to Stockton were 
furnished by Stockton Port District April 9, 
1970. 
Terminal facilities. See Part 2, Port Series 
No. 30, 31, and 32, revised 1962, titled respectively: 
"The Ports of San Francisco and 
Redwood City, Calif."; "The Ports of Oakland, 
Alameda, and Richmond and Ports on San 
Pablo Bay, Carquinez Strait, and Mare Island 
Strait, Calif."; and "The Ports of Stockton and 
Sacramento, Calif." Facilities are considered 
adequate for existing commerce and will be 
adequate for future commerce upon completion 
of new terminal facilities. 
Operations and results during fiscal year. 
New work: Sacramento District: Engineering, 
including preparation of general design 
memorandum and preparation and processing 
of environmental impact statements, continued 
at a cost of $265,912. San Francisco District: 
Continued planning activities. Continued 
dredge spoil dispersion study which will be 
continuous during and after dredging on San 
Francisco Bar to determine impact on ocean 
ecology. 
Condition at end of fiscal year. Construction 
of project was initiated in June 1971 and is 
about 1 percent complete. 
3. SAN JOAQUIN RIVER, CALIF. 
Location. Rises in east central California and 
flows westerly and northwesterly about 340 
miles to its confluence with Sacramento River 
35-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
at head of Suisun Bay, 48 miles northeast of San 
Francisco. Deep water channel in San Joaquin 
River extends 41 miles from its mouth to Suisun 
Bay at Pittsburg to city of Stockton. Waterborne 
access to city provided by Stockton 
Channel, an artificial cut extending from river 
about 2 miles into city. (See Coast and Geodetic 
Survey Sheet 5527.) 
Existing project. For description of completed 
improvement, modifications, and authorizing 
acts, see Annual Report for 1967. (See table 35- 
E for total cost of new work for project 
completed in May 1960.) 
Project units (1950 modification) reclassified 
and excluded from project cost are set forth in 
table 35-F. 
Modification of existing project is included as 
one unit of San Francisco Bay to Stockton, 
Calif., (John F. Baldwin and Stockton Ship 
Channels) project, authorized by 1965 River and 
Harbor Act (H. Doc. 209, 89th Cong., 1st sess.); 
this modification is reported in detail under 
Sacramento District, Improvement No. 2. 
Local cooperation. Fully complied with for 
completed portion of project; for details of 
required cash contributions on completed, 
inactive and deferred portions of project, see 
Existing project paragraph, Annual Report for 
1967. 
Terminal facilities. For description of harbor 
facilities at Port of Stockton, Calif., see Port 
Series 32, Ports of Stockton and Sacramento, 
Calif., revised 1962. Downstream from 
Stockton, traffic is accommodated by bank 
landings and sheds except at Antioch and near 
Pittsburg, where there are wharves for shallowand 
deep-draft vessels. Terminal transfer 
facilities at public ocean terminal of Port of 
Stockton are adequate for present and 
immediate future. 
Operations and results during fiscal year. 
Maintenance: Condition studies and miscellaneous 
inspections and reports were 
accomplished by hired labor. 
Condition at end of fiscal year. Active portion 
of existing project was completed in May 1960. 
Construction of project was initiated in 
December 1877. 
4. RECONNAISSANCE AND 
CONDITION SURVEYS 
Record and condition surveys were conducted 
at various times during fiscal year at several 
navigation projects at a cost of $10,146. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 35-G. 
Flood Control 
6. BUCHANAN DAM-H. V. EASTMAN 
LAKE, CHOWCHILLA RIVER, 
CALIF. 
Location. On Chowchilla River about 36 miles 
above its mouth and about 16 miles northeast of 
city of Chowchilla, Calif. (See Geological Survey 
quadrangles for area.) 
Existing project. Provides for construction of 
a 205-foot high rockfill dam to create a 
reservoir with gross storage capacity of 150,000 
acre-feet for flood control, irrigation, recreation, 
and fish and wildlife. In conjunction with dam, 
project plan provides for about 12 miles of 
downstream levee and channel construction on 
Ash Slough to accommodate a project design 
flow of 5,000 cubic feet per second within slough 
and 8 miles of levee and channel improvement 
on Berenda Slough. Operation and maintenance 
of dam and reservoir will be responsibility of 
the Federal Government. Approved cost 
estimate (July 1975) for existing project is 
$26,500,000, for which $25,000,000 is Federal 
cost, including $3,670,000 for basic recreation 
facilities, and $1,500,000 non-Federal costs for 
lands and damages, including relocations for 
downstream levee and channel improvements. 
Local interests have contracted with Bureau of 
Reclamation for irrigation service. For future 
non-Federal reimbursement, see Local cooperation 
paragraph. 
Local interests have also, over a period of 
years, expended about $500,000 for construction 
of low levees and clearing downstream channels 
to provide some local flood protection in project 
area. This work is inadequate during major 
floods. Existing project was adopted by 1962 
Flood Control Act (S. Doc. 98, 87th Cong., 2d 
sess., contains latest published map). Lake 
formed by Buchanan Dam on Chowchilla River 
was designated "H. V. Eastman Lake" by 
Public Law 93-217. 
Local cooperation. California officially 
adopted project by chapter 1203 of statutes of 
1963, and by chapter 1438 of those statutes 
authorized State Reclamation Board to furnish 
assurances that requirements for supplemental 
channel improvements will be met. With 
respect to the dam and reservoir, local interests 
must reimburse the Federal Government the 
portion of first cost and annual operation and 
maintenance cost allocated to irrigation functions 
of the project. These costs are estimated at 
35-4

SACRAMENTO, CALIF., DISTRICT 
44.3 percent of the joint-use first cost and 41.9 
percent of joint-use annual costs. Project 
authorization provides for project to be financially 
integrated into the Central Valley project 
of the Bureau of Reclamation. Irrigation 
repayment contracts were executed with the 
Chowchilla and La Branza Water Districts by 
the Bureau of Reclamation May 28, 1968. Local 
interests sponsoring any permanent pool in the 
reservoir for fish and wildlife or recreation 
must settle all claims for water rights pertaining 
to establishment and use of a permanent 
pool for these purposes. With respect to 
supplemental channel improvement work, section 
3, Flood Control Act of June 22, 1936, 
applies. Local interests must also preserve, or 
restore and thereafter maintain, the other 
channels of Chowchilla River and Ash and 
Berenda Sloughs, from Buchanan Dam 
downstream to Chowchilla Canal, at capacities 
existing in 1960. Formal assurances for 
supplemental channel improvements were furnished 
by State Reclamation Board May 18, 
1971. Supplemental assurances required by PL 
91-646 (relocation assistance benefits to persons 
displaced by, or who have real property taken 
for a Federal public improvement project) were 
requested September 3, 1971, and furnished 
September 20, 1971. 
Operations and results during fiscal year. 
New work: Engineering continued at cost of 
$261,339. Construction of main dam and 
appurtenances was continued at contract cost of 
$3,396,461. (Construction of Buchanan Lake and 
Hidden Lake dam and appurtenances combined 
under one contract.) Dam closure completed 
March 1975. Reservoir clearing and boundary 
fencing completed in May 1975 at costs of 
$90,917 and $115,163, respectively. 
Condition at end of fiscal year. Construction 
on project began in July 1971 and is about 78 
percent complete. 
7. CALAVERAS RIVER AND 
LITTLEJOHN CREEK AND 
TRIBUTARIES, INCLUDING 
NEW HOGAN LAKE AND 
FARMINGTON DAM, CALIF. 
Location. Streams comprising Calaveras 
River and Littlejohn Creek groups rise in Sierra 
Nevada and its foothills, flow westerly across 
flatlands of San Joaquin Valley and empty into 
San Joaquin River directly, or through various 
sloughs, in vicinity of Stockton, Calif. Littlejohn 
Creek is in Calaveras, Stanislaus, and San 
Joaquin Counties. The three principal stream 
systems of the group are, from south to north, 
Lone Tree Creek, Littlejohn Creek, and Duck 
Creek. Calaveras River group is in Calaveras 
and San Joaquin Counties. The two principal 
streams of the group are, from south to north, 
Calaveras River and Bear Creek. (See 
Geological Survey Valley Springs quadrangle 
for New Hogan reservoir area and Trigo and 
Bachelor Valley quadrangles for Farmington 
reservoir area.) 
Existing project. For description of completed 
improvements consisting of Farmington Dam, 
New Hogan Lake, and Bear Creek levee and 
channel improvement, and authorizing act, see 
Annual Report for 1967. (a) Farmington: Total 
first cost (July 1955) for project was $3,995,684, 
of which $3,676,384 was Federal and $319,300 
non-Federal for lands and damages including 
relocations. (b) New Hogan: Estimated (July 
1975) Federal cost for project is $15,906,000, 
including $462,000 for basic recreation 
facilities. For future non-Federal reimbursement, 
see Local cooperation paragraph. 
Estimated Federal cost for additional recreation 
facilities to be funded from Code 710 
appropriations is $722,000. (c) Bear Creek: 
Project cost is $6,485,734, of which $3,242,867 is 
Federal, including reimbursement ($488,096) to 
local interests of one-half of excess local interest 
cost of lands, rights-of-way, and relocations over 
estimated Federal construction cost in accordance 
with section 3, Public Law 738, 74th 
Congress. Non-Federal cost included in above 
amount is $3,242,867 for relocations and lands 
and damages, exclusive of above Federal 
reimbursement. 
Local cooperation. Fully complied with. New 
Hogan: Local interests must pay portion of first 
cost and annual operation and maintenance 
costs allocated to conservation functions of 
project. These costs are estimated at 36.2 
percent of first cost and 38 percent of annual 
costs. In addition, local interests contributed 
land, the (July 1964) market value of which was 
$556,000. For years 1961 through 1970, an 
interim contract between the Bureau of 
Reclamation and local water users provided for 
storage and payment of irrigation water; local 
interests paid $1,034,117 through December 31, 
1974. A long-term contract between the Bureau 
and local water users was executed August 25, 
1970. A concessionaire at New Hogan Marina 
provided public use facilities in accordance with 
lease agreement with the Secretary of the Army 
at an estimated cost of $95,000. 
Operations and results during fiscal year. 
New work: New Hogan Lake, regular funds: 
None. Code 710 funds: Initiated restroom 
contract at North Shore campground, $7,000. 
Bear Creek, San Joaquin County: None. 
Maintenance: Farmington Dam-Maintenance 
and operation activities continued; structures 
were maintained in serviceable condition. 
35-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
During the rainflood season, maximum flow of 
Duck Creek diversion was 380 cubic feet per 
second February 13, 1975. Maximum flow of 
Littlejohn Creek at Farmington was 1,540 cubic 
feet per second March 25, 1975. Maximum 
storage in the reservoir was 2,860 acre-feet 
March 17, 1975, and maximum bihourly inflow 
to the reservoir was 4,400 cubic feet per second 
March 22, 1975. New Hogan Lake- 
Maintenance and operation activities continued 
with condition and operation studies at a cost of 
$65,728 and major maintenance costs as follows: 
Dam and reservoir $60,408; service facilities 
$18,650; and recreation facilities $123,180. 
Structures were maintained in serviceable 
condition. Runoff of Calaveras River above New 
Hogan Dam was near normal for the year. 
Maximum storage of 255,800 acre-feet occurred 
July 1, 1974. Maximum estimated inflow to the 
reservoir was 11,000 cubic feet per second on 
March 25, 1975. Water released for flood control 
amounted to 150,000 acre-feet. Maximum 
release was 6,100 cubic feet per second on 
March 26, 1975. During the year, about 67,000 
acre-feet of water was released for irrigation 
and other purposes. 
Condition at end of fiscal year. Farmington 
Dam: Construction of Farmington project was 
initiated in July 1949, and completed for 
beneficial flood control operation in 1952. Duck 
Creek channel improvement was completed in 
November 1951; and channel improvement on 
south Littlejohn Creek was completed in May 
1955. There are no recreation facilities or 
public-use areas. All work completed. New 
Hogan Lake: Construction was initiated May 
1960, main dam closure November 1963, project 
completed for operational use in June 1964, all 
work completed October 1973. Additional 
recreation facilities are to be provided from 
Code 710 appropriations. Bear Creek, San 
Joaquin County: Construction began in June 
1963 and was completed in June 1967. Final 
cash contribution was made to local interests 
December 23, 1970. 
8. CHESTER, CALIF. 
Location. North Fork of Feather River, 
immediately upstream from the town of 
Chester, Plumas County, Calif. (See Geological 
Survey quadrangles for area.) 
Existing project. Provides for construction of 
a 45-foot high ungated diversion dam on North 
Fork of Feather River about one and one-half 
miles above Chester, Calif. Diversion dam 
would divert flows in excess of the outlet 
capacity of the dam into a partially leveed 
diversion channel for conveyance of floodflows 
circuitously around the town and into Lake 
Almanor. Major relocation works required by 
adoption of the plan comprise construction of 
two 300-foot long bridges over the floodway and 
about one mile of asphaltic-surfaced county 
road. Approved cost estimate (July 1975) for 
existing project is $6,370,000, of which $4,870,- 
000 is Federal cost; and $1,500,000 is non- 
Federal cost for lands, damages, and 
relocations. Existing project was adopted by 
1968 Flood Control Act (H. Doc. 314, 90th 
Cong., 2d sess., contains latest published map). 
Local cooperation. Prior to construction of the 
project, local interests must give assurances 
satisfactory to the Secretary of the Army that 
they will: (a) Provide without cost to the United 
States, all lands, easements, and rights-of-way 
necessary for construction and operation of the 
proposed improvements, including in this 
provision the undertaking of all necessary 
modifications and relocations of roads or other 
existing structures or utilities; (b) hold and save 
the United States free from damages due to the 
construction works; (c) maintain and operate 
the completed project in accordance with 
regulations prescribed by the Secretary of the 
Army; and (d) prescribe and enforce regulations 
designed to prevent encroachment of any type 
that would impair the flood control effectiveness 
of the works. The California State Reclamation 
Board has indicated intent to provide the 
foregoing assurances. 
Operations and results during fiscal year. 
New work: Preconstruction engineering studies 
and design memoranda were continued. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
9. FAIRFIELD VICINITY STREAMS, 
CALIF. 
Location. In Fairfield Streams area which 
comprises five streams in vicinity of city of 
Fairfield, Solano County, Calif. (See Geological 
Survey quadrangles for area.) 
Existing project. Provides for channel 
improvement on Ledgewood, Laurel, and 
McCoy Creeks and diversion of three creeks 
upstream from Fairfield (Pennsylvania Avenue 
Creek into Ledgewood Creek, Union Avenue 
Creek into Laurel Creek, and Laurel Creek into 
McCoy Creek). Only levee to be provided would 
be along McCoy Creek below State Highway 
No. 12. Project related recreation facilities such 
as access roads, parking areas, a boat-launching 
ramp, and hiking, bicycle, and horseback trails 
would also be constructed. Approved cost (July 
1975) estimate for existing project is $9,570,000, 
of which $5,020,000 is Federal, including 
reimbursement (estimated $880,000) to local 
35-6

SACRAMENTO, CALIF., DISTRICT 
interests, under section 3, Flood Control Act of 
June 22, 1936, and non-Federal is $4,550,000. 
For future non-Federal reimbursement, see 
Local cooperation paragraph. Existing project 
was adopted by sec. 201, 1965 Flood Control Act 
(1970 Senate and House Public Works Committee 
resolutions) (HD 91-159, 91st Cong., 1st 
sess., contains latest published map). 
Local cooperation. Prior to construction of the 
project, local interests must give assurances 
satisfactory to the Secretary of the Army that 
they will: (a) Provide without cost to the United 
States all lands, easements, and rights-of-way 
necessary for construction and maintenance of 
project, including all necessary modifications 
and relocations of roads or other existing 
structures or utilities, except railroad facilities 
necessitated by the project excluding rights-ofway 
required for such relocations; (b) hold and 
save the United States free from all damages 
due to the construction works; (c) maintain and 
operate completed project in accordance with 
regulations prescribed by the Secretary of the 
Army; (d) prevent encroachment upon the 
project channels of any works detrimental to 
flood control purposes of the project; and (e) 
pay, contribute in kind, or repay (which may be 
through user fees) with interest a portion of the 
cost of recreation facilities which when added to 
cost of recreation lands would amount to onehalf 
of total first cost of recreation lands and 
recreation facilities, non-Federal cost involved 
currently being estimated at $235,000. The 
California State Reclamation Board, by resolution 
December 1, 1966, stated that Board will 
provide required local assurances. The Solano 
County Board of Supervisors, by resolution 
January 3, 1967, stated they will participate in 
furnishing, or in making arrangements to 
furnish, the required assurances of local 
cooperation. 
Operations and resdlts during fiscal year. 
New work: Preconstruction engineering studies 
and design memoranda were continued. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
10. GLEASON CREEK DAM, NEV. 
Location. On Gleason Creek about 7 miles 
west of town of Ely, Nev. Gleason Creek basin, 
about 73 square miles in area, has a maximum 
length of about 19 miles and an average width 
of about 4 miles. Elevations range from about 
6,000 feet to 8,000 feet. Gleason and Murry 
Creeks are principal tributaries of Robinson 
watershed, and the combined waters flow 
through the city of Ely in a generally 
northeasterly direction and discharge onto 
waste land in Steptoe Valley, a closed mountain 
basin (See U.S. Geological Survey quadrangles 
for area.) 
Existing project. Provides for construction of 
an earthfill dam about 52 feet high to create a 
reservoir with gross storage capacity of 1,500 
acre-feet for exclusive purpose of flood control. 
Operation and maintenance of completed project 
would be responsibility of local interests. 
Approved estimated cost (July 1975) for 
existing project is $960,000, of which $870,000 
is Federal cost and $90,000 non-Federal cost for 
lands, damages, and relocations. For future 
non-Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted 
by 1960 Flood Control Act (H. Doc. 388, 86th 
Cong., 2d sess., contains latest published map.) 
Local cooperation. Local interests are to: (a) 
Provide without cost to the United States all 
lands, easements, and rights-of-way for the 
improvement; (b) bear the cost of all necessary 
alterations and construction of highway 
facilities, other structures, and utilities; (c) hold 
and save the United States free from damages 
due to the construction works; (d) maintain and 
operate all the works after completion in 
accordance with regulations prescribed by the 
Secretary of the Army; (e) preserve and 
maintain the stream channels through Ely to 
capacities existing in 1958; (f) adequately 
inform interests affected that the project does 
not provide protection against maximum floods; 
and (g) assume at least 20 percent of the cost 
(except costs of planning, design, and acquisition 
of water rights) of the completed project 
allocated to the production of local flood control 
benefits, payable either as construction 
proceeds or pursuant to a contract providing for 
repayment with interest within 50 years. The 
actual cost of fair market value of lands, 
easements, rights-of-way, and work performed 
or services rendered prior to completion of 
construction of the project, which are furnished 
by local interests shall be included in the share 
of the cost to be borne by the local interests. 
Local interests required future monetary contribution 
is presently estimated at $55,000. On 
February 8, 1971, city council of Ely, Nevada 
passed a resolution of intent to furnish 
necessary assurances of local cooperation. In 
April 1973, Nevada State Legislature passed 
bills to provide required project assurances and 
$50,000 for non-Federal costs. 
Operations and results during fiscal year. 
Preconstruction engineering studies and design 
memoranda were continued. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
35-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
11. HIDDEN DAM-HENSLEY LAKE, 
FRESNO RIVER, CALIF. 
Location. On Fresno River about 50 miles 
above its mouth and about 15 miles northeast of 
Madera, Calif. (See Geological Survey quadrangles 
for area.) 
Existing project. Provides for construction of 
a 163-foot high earthfill dam to create a 
reservoir with gross storage capacity of 90,000 
acre-feet for flood control, irrigation, recreation 
and other purposes. In conjunction with the 
dam, the project plan provides for about 13 
miles of downstream levee and channel improvements 
on Fresno River immediately 
upstream of Chowchilla Canal crossing to 
accommodate project design flow of 5,000 cubic 
feet per second. Operation and maintenance of 
dam and reservoir would be responsibility of 
Federal Government. Approved estimated (July 
1975) cost for existing project is $28,640,000, of 
which $27,400,000 is Federal cost, including 
$3,920,000 for basic recreation facilities, and 
$1,240,000 non-Federal cost for lands and 
damages including relocations for downstream 
levee and channel improvements. Local interests 
have contracted with Bureau of Reclamation 
for irrigation service. For future non- 
Federal reimbursement, see Local cooperation 
paragraph. Local interests have also, over a 
period of years, expended about $300,000 for 
construction of low levees and clearing downstream 
channels to provide some local flood 
protection in the project area. This work is 
inadequate during major floods. Existing project 
was adopted by 1962 Flood Control Act (S. 
Doc. 37, 87th Cong., 1st sess., contains latest 
published map). Lake created by Hidden 
Reservoir project on Fresno River was designated 
"Hensley Lake" by Public Law 93-603. 
Local cooperation. California officially 
adopted project by chapter 1202 of statutes of 
1963, and by chapter 1438 of those statutes 
authorized State Reclamation Board to furnish 
assurances that requirements for supplemental 
channel improvements will be met. With 
respect to the dam and reservoir, local interests 
must reimburse the Federal Government the 
portion of first cost and annual operation and 
maintenance costs allocated to irrigation function 
of project. These costs are estimated at 21.7 
percent of the joint-use first cost and 15.9 
percent of joint-use annual costs. Project authorization 
provides for project to be financially 
integrated into the Central Valley project of the 
Bureau of Reclamation. Irrigation repayment 
contract was executed by the Bureau with the 
Merced Irrigation District August 5, 1968. 
Local interests sponsoring any permanent pool 
in the reservoir for fish and wildlife or 
recreation must settle all claims for water 
rights pertaining to establishment and use of a 
permanent pool for these purposes. With respect 
to supplemental channel improvement work, 
section 3, Flood Control Act of June 22, 1936, 
applies; relocations include relocations of highway 
facilities and utilities. Local interests must 
also preserve, or restore and thereafter maintain, 
the Fresno River channel from Hidden 
Lake downstream to the authorized channel 
work at the capacities prevailing in 1959. 
Formal assurances for supplemental channel 
improvements were furnished by State Reclamation 
Board April 8, 1971. Supplemental 
assurances required by PL 91-646 (relocation 
assistance benefits to persons displaced by, or 
who have real property taken for a Federal 
public improvement project) were requested 
September 3, 1971, and furnished September 
20, 1971. 
Operations and results during fiscal year. 
New work. Engineering continued at cost of 
$109,373. Construction of main dam and appurtenances 
was continued at contract cost of 
$3,111,729. (Construction of Buchanan Lake and 
Hidden Lake main dam and appurtenances 
combined under one contract.) Dam closure 
completed March 1975. Reservoir clearing and 
boundary fencing completed in May 1975 at 
costs of $51,850 and $64,763, respectively. 
Condition at end of fiscal year. Construction 
on project began in July 1971 and is about 79 
percent complete. 
12. HUMBOLDT RIVER AND 
TRIBUTARIES, NEV. 
Location. In general vicinity of Elko, Nev., on 
headwater tributaries of Humboldt River. River 
basin of approximately 16,700 square miles is a 
high semiarid plateau crossed by numerous 
steep mountain ranges separated by broad, flat 
valleys. River valley extends about 300 miles. 
Principal headwater tributaries are North 
Fork, Marys River and South Fork. Elevations 
in basin vary from about 4,000 feet in Carson 
Sink to about 12,000 feet in Ruby Mountains. 
(See Geological Survey quadrangles for area.) 
Existing project. Provides for construction of 
three storage reservoirs on headwater tributaries 
and minor channel improvements at critical 
locations along Humboldt River above Rye 
Patch Reservoir. Dams are to be earthfill 
structures with gross storage capacities as 
follows: Hylton reservoir on South Fork, Humboldt 
River, 120,000 acre-feet; Devils Gate 
reservoir on North Fork, Humboldt River, 
80,000 acre-feet; and Vista reservoir on Marys 
River, 50,000 acre-feet. All reservoirs would be 
operated primarily for flood control, but also for 
35-8

SACRAMENTO, CALIF., DISTRICT 
irrigation, recreation, and fish and wildlife 
purposes. Operation and maintenance of dam 
and reservoir will be responsibility of the 
Federal Government. Approved cost estimate 
(July 1975) for existing project is $31,500,000, of 
which $28,700,000 is Federal cost, including 
$1,740,000 for basic recreation facilities, and 
$2,800,000 non-Federal cost for lands, damages, 
and relocations. Existing project was adopted 
by 1950 Flood Control Act (H. Doc. 586, 81st 
Cong., 2d sess., contains latest published map). 
Local cooperation. Prior to initiation of 
construction, local interests are required to 
contribute $2,762,000 in cash toward reservoir 
construction costs, and to furnish assurances 
satisfactory to the Secretary of the Army that 
they will: (a) Provide free of cost to the United 
States, all necessary rights-of-way for proposed 
channel improvements, and undertake all 
utility revisions required; (b) maintain and 
operate at their own expense such channel 
improvements and appurtenant works after 
completion, in accordance with regulations 
prescribed by the Secretary of the Army; (c) 
hold and save the United States free from all 
damages arising from construction of operation 
of channel improvements and appurtenant 
works; (d) enter into an agreement among 
themselves as to method of operation of the 
reservoirs for irrigation subject to flood control 
priority; and (e) bear not less than one-half the 
separable costs of project allocated to recreation 
and fish and wildlife presently estimated to be 
$950,000, and bear all costs for maintenance 
and operation for these purposes. Elko County 
Fair and Recreation Board, by resolution of 
December 5, 1969, stated that requirements of 
local cooperation would be provided by the 
District Engineer. Nevada State Legislature 
has passed a bill (Senate Bill 246) to provide 
$50,000 for an environmental and wildlife 
impact investigation for project. Right to store 
water in project reservoirs was awarded to Elko 
County Fair and Recreation Board in May 1970 
and ruling was upheld by court decision in 
October 1971. State Engineer considers that 
combination of Humboldt River Decree, Corps 
flood control operating criteria, and State 
ruling on water storage right constitutes 
operation agreement required by authorizing 
act. 
Operations and results during fiscal year. 
New work: Preconstruction engineering studies 
and design memoranda were continued. 
Condition at end of fiscal year. Preconstruetion 
planning was continued. 
13. ISABELLA LAKE, KERN RIVER, 
CALIF. 
Location. About 50 miles northeast of city of 
Bakersfield, Calif., near confluence of north and 
south forks of Kern River; auxiliary dam is 
about one-half mile east of main dam. (See 
Geological Survey quadrangles of area.) 
Existing project. For description of completed 
improvement authorizing act, see Annual 
Report for 1967. Estimated Federal cost (July 
1975) for new work is $22,027,000. For future 
non-Federal reimbursement see Local cooperation 
and Licenses paragraphs. Estimated Federal 
cost (July 1975) of recreation facilities for 
Isabella Lake, to be funded from Code 710 
appropriations is $2,376,000. Operation and 
maintenance of dam and reservoir is Federal 
responsibility. 
Local cooperation. California officially 
adopted project by chapter 1514 of statutes of 
1945, State of California. Local interests, 
represented by North Kern, Buena Vista, and 
Tulare Lake Basin Water Storage Districts and 
La Hacienda Water District, were required to 
reimburse the Federal Government the portion 
of first cost and annual operation and maintenance 
costs allocated to irrigation functions of 
project. These costs based on a cost allocation 
study completed in December 1955, are 
$4,573,000 of first cost and 21.7 percent of 
annual operation and maintenance costs. For 
the years 1956 through 1964, an interim 
contract between Bureau of Reclamation and 
local water users provided for storage and 
payment of irrigation water. Under provisions 
of this interim contract, local interests paid 
$1,936,229 through December 31, 1964. A longterm 
contract between the Bureau and local 
water users was executed October 23, 1964. 
Balance due on allocated first cost of $4,573,000 
was paid by the water users on March 31, 1965. 
Kern County assumed administration of recreation 
and development and maintenance of 
public use areas at project in accordance with a 
25-year license February 15, 1955. The agreement 
with Kern County provided for joint 
operation and development by the Corps and 
Kern County including permits granted to 
concessionaires by the county to provide certain 
services. As of September 30, 1971, Kern 
County relinquished all administration of recreation 
and development and maintenance of 
public use areas at the project. A State law 
permitting the Department of Navigation and 
Ocean Development to participate in inland 
water development with Federal agencies was 
signed by the Governor on August 11, 1972. All 
concessionaires will operate under permits 
granted by the Corps. Total cost of present 
35-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
recreation facilities developed by the county and 
its concessionaires is about $880,000; $235,000 
of this was a grant from the California Wildlife 
Conservation Board and about $370,000 is 
investment by concessionaires. 
Licenses. In accordance with Federal Power 
Commission Docket No. E-6578, issued April 1, 
1963, payment of $377,426 was made to the 
Federal Government by Pacific Gas and Electric 
Co. ($108,352) and Southern California 
Edison Co. ($269,074) for headwater benefits to 
downstream existing plants from Isabella Dam 
to cover benefits from April 15, 1954, to 
December 31, 1962. Subsequent to 1962, the 
power companies have in the aggregate made 
annual payments of $44,650 for headwater 
benefits. That amount will be paid each year 
until changes in operation, development, or 
costs indicate some modification to be advisable. 
Cumulative use charges collected by the Federal 
Power Commission and returned to the 
U.S. Treasury through period ending June 30, 
1975, amounted to $957,876. 
Operations and results during fiscal year. 
New work, regular funds: None. Code 710 
funds: Engineering continued. Construction of 
shower modifications at several campgrounds 
initiated by contract, $20,390. Boat launching 
facilities initiated by contract at Old Isabella 
Road, $11,670, contributed funds, other. 
Maintenance. Maintenance and operation 
activities continued with condition and operation 
studies at a cost of $45,526 and major 
maintenance costs as follows: Dam and reservoir 
$35,786; service facilities $31,576; and 
recreation facilities $365,307. Structures were 
maintained in good condition. Runoff of Kern 
River above Isabella Lake was near normal for 
the year. Maximum storage of 471,700 acre-feet 
occurred July 1, 1974, maximum daily inflow to 
Isabella Lake was 3,900 cubic feet per second on 
July 1, 1974, and maximum outflow of 2,020 
cubic feet per second occurred July 3, 1974. 
Release of water for irrigation and spreading 
uses totaled 678,000 acre-feet. 
Condition at end of fiscal year. Construction 
began in March 1948 and was completed in 
June 1968. Main dam, Borel Canal outlet works 
and appurtenances, and auxiliary dam were 
completed in April 1953. Storage impoundment 
began December 1952. Project is operating to 
provide flood protection and irrigation benefits 
for which it was designed. Additional recreation 
facilities are to be provided by Code 710 funds. 
14. KAWEAH AND TULE RIVERS, 
INCLUDING TERMINUS DAM 
AND SUCCESS LAKE, CALIF. 
Location. Terminus Dam is on Kaweah River 
about 20 miles east of Visalia, Calif. Success 
Lake is on Tule River about 5 miles east of 
Porterville, Calif. (See Geological Survey quadrangles 
of area.) 
Existing project. Terminus Dam: A rolled 
earthfill and rock shell main dam structure 250 
feet high and 2,375 feet long, an auxiliary 
earthfill dam 130 feet high and 870 feet long, 
and an ungated spillway in left abutment of 
dam. Reservoir has a gross storage capacity of 
150,000 acre-feet. Spreading ftcilities of capacity 
contemplated in authorizing document, 
comprising a complex system of channels, 
basins, and other irrigation facilities, have been 
constructed by local interests since preparation 
of survey report and are fully adequate for 
project purposes. Estimated Federal cost (July 
1975) of new work is $19,310,000, including 
$207,000 for basic recreation facilities and 
excluding spreading works constructed by local 
interests at an estimated (July 1957) cost of 
about $750,000. Estimated (July 1975) Federal 
cost of recreation facilities, to be funded from 
Code 710 appropriations is $736,000. Success 
Lake: A rolled earthfill main dam structure 142 
feet high and 3,490 feet long, an auxiliary 
rolled-earthfill dam or dike 40 feet high and 
7,650 feet long across Frazier Valley about 3.5 
miles northwesterly from main dam, and an 
ungated spillway. Reservoir has a gross storage 
capacity of 85,000 acre-feet. Estimated Federal 
cost (July 1975) of new work for Success Lake is 
$14,257,000, including $193,000 for basic recreation 
facilities. Estimated (July 1975) Federal 
costs of recreation facilities to be funded 
from Code 710 appropriations is $720,000. For 
future non-Federal reimbursements, see Local 
cooperation paragraph. Operation and maintenance 
of reservoirs is Federal responsibility. 
Flood Control Act of 1944 authorized existing 
project and $4,600,000 for initiation and partial 
accomplishment of construction of Success Lake 
and Terminus Dam. Additional monetary 
authorization for completion of this comprehensive 
plan was provided by Public Law 85-500 
(H. Flood Control Committee Doc. 1, 78th Cong., 
2d sess., and H. Doc. 559, 78th Cong., 2d sess., 
contains latest published map). Lake formed by 
Terminus Dam was designated "Lake Kaweah" 
by Public Law 87-568. 
Local cooperation. California officially 
adopted projects by chapter 1514 of statutes of 
1945, State of California. Local interests for 
Terminus Dam are represented by Kaweah 
Delta Water Conservation District. Local interests 
for Success Lake are considered to be 
represented by the Vandalia, Porterville, and 
Lower Tule River Irrigation District, the 
Tulare Lake Basin Water Storage District, and 
Pioneer Water Co., which represent over 90 
percent of irrigated land and water-right 
35-10

SACRAMENTO, CALIF., DISTRICT 
holders along Tule River below damsite. Local 
interests must reimburse the Federal Government 
the portion of first cost and annual 
operation and maintenance costs allocated to 
irrigation functions of projects. These costs are 
estimated at 14.1 percent of first and annual 
costs for Terminus and 9.5 percent of first and 
annual costs for Success. Local interests for 
Terminus stated they will continue to operate 
and maintain spreading works and downstream 
channel systems to provide required capacity 
for disposal of floodwaters. Local interests for 
Success stated they will continue to maintain 
downstream channel systems to provide required 
capacity for disposal of floodwaters. 
Renayment contracts between Bureau of Reclamation 
and local water users for irrigation 
supply from Terminus and Success reservoirs 
were executed January 11, 1965, and April 30, 
1965, respectively. Reservoirs are being operated 
for irrigation storage as well as flood 
control and incidental recreation use. Tulare 
County acquired water for recreation pools at 
the projects. Local interests paid the following 
total amounts for irrigation services from the 
reservoirs through December 31, 1974: Terminus, 
$915,705 and Success, $388,232. Tulare 
County was granted a 25-year license for 
planning, development, and management of 
public recreation areas at Success, July 10, 
1960, and at Terminus, June 5, 1961. Basic 
public-use facilities constructed by Corps at the 
Success reservoir were transferred to jurisdiction 
of Tulare County on January 18, 1962; 
facilities at Terminus were transferred June 20, 
1962. In March 1967, an amendment to the 
license agreements was approved by the Assistant 
Secretary of the Army. Under these 
amended licenses, Tulare County retained 
administration of only specified land areas and 
operation and maintenance of recreation facilities 
in these areas. In addition, they continued 
their program of water safety, boat inspection, 
and law enforcement at both reservoirs. The 
Corps took over the administration of the 
remainder of the project land areas and the 
operation and maintenance of recreation facilities 
in these areas. California Department of 
Fish and Game expended funds to improve 
fishery resources of the Terminus reservoir. As 
of April 1, 1972, Tulare County relinquished all 
planning, development, and management of 
public recreation areas at Terminus Dam. 
Tulare County by expenditure of county funds 
and by a lease to a concessionaire has aided in 
the development of recreation facilities at an 
estimated cost of $137,000. California Department 
of Fish and Game expended funds in 
conjunction with Tulare Sportsman's Council, 
developing a habitat for upland game birds at 
Success Lake. As of April 1, 1972, Tulare 
County relinquished all planning, development, 
and management of public recreation areas at 
Success Lake, except for the Bartlett Park 
recreation area. Tulare County has aided in 
development of recreation facilities. Total cost 
of present recreation facilities developed by the 
county and its concessionaires is about $196,000. 
Operations and results during fiscal year. 
New work: Terminus Dam, regular funds: 
None. Code 710 funds: Minor engineering for 
recreation facilities. 
Success Lake, regular funds: None. Code 710 
funds: Minor engineering for recreation facilities. 
Maintenance: Terminus Dam: Maintenance 
and operation activities continued with condition 
and operation studies at a cost of $52,669 
and major maintenance costs as follows: Dam 
and reservoir $33,301; service facilities $22,618; 
and recreation facilities $128,352. Structures 
were maintained in serviceable condition. 
Runoff of Kaweah River above Terminus Dam 
was near normal for the year. Maximum 
storage of 151,200 acre-feet occurred June 16, 
1975. Maximum daily inflow to the reservoir on 
June 1, 1975, was 3,600 cubic feet per second. 
Maximum outflow from reservoir occurred on 
June 12, 1975, and was 2,600 cubic feet per 
second. Release of water for irrigation and 
spreading uses totaled 348,000 acre-feet. Water 
released for flood control amounted to 27,000 
acre-feet. 
Success Lake: Maintenance and operation 
activities continued with condition and operation 
studies at a cost of $30;314 and major 
maintenance costs as follows: Dam and reservoir 
$54,056; service facilities $19,235; and 
recreation facilities $131,265. Structures were 
maintained in serviceable condition. Runoff of 
Tule River above the reservoir was near normal 
during the year. Maximum storage of 81,250 
acre-feet occurred June 22, 1975. Maximum 
bihourly inflow to reservoir was 1,300 cubic feet 
per second on February 10, 1975. Maximum 
outflow of 655 cubic feet per second occurred on 
August 8, 1974. Release of water for irrigation 
and spreading totaled 99,000 acre-feet. Water 
released for flood control amounted to 12,000 
acre-feet. 
Condition at end of fiscal year. Terminus 
Dam: Construction of project began in July 1957 
and was completed in June 1968 except for final 
settlement for one tract of land upon decision of 
pending court case. Construction of main dam 
and appurtenances, initiated in February 1959, 
was completed in June 1962. Dam has been 
operating since November 1961 to provide flood 
protection for which it was designed; conservation 
impoundment was commenced May 1962. 
35-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Appurtenances are in good condition. Additional 
recreation facilities are to be provided by 
Code 710 funds. Success Lake: Construction of 
project began in November 1956 and was 
completed in June 1968 except for final audit of 
historical land record. Construction of main 
dam and appurtenances, initiated in October 
1958, was completed in May 1961. Dam has 
been operating since October 1960 to provide 
flood protection for which it was designed; 
conservation impoundment was commenced 
March 1962. Additional recreation facilities are 
to be provided by Code 710 funds. 
15. LAKE CAMANCHE, CALIF. 
Location. Dam is on Mokelumne River, about 
50 miles upstream of its mouth and about 20 
miles northeast of Stockton. (See Geological 
Survey topographic maps of area.) 
Existing project. Federal participation consists 
of a contribution toward first cost of 
reservoir, in an amount commensurate with 
flood control benefits to be attained. Project 
construction was accomplished by East Bay 
Municipal Utility District. Federal contribution 
is based on provision of a maximum of 200,000 
acre-feet of reservoir storage for flood control 
operation, generally during winter months. 
Reservoir is a multiple-purpose storage reservoir 
for flood control and water supply. Improvement 
comprises a 171-foot high-zoned 
earth- and gravel-fill dam, creating a reservoir 
with a gross storage capacity of 431,500 acrefeet. 
Estimated (July 1975) cost is $34,780,000, 
of which $10,018,000 is Federal contribution 
toward flood control exclusive of $182,000 
incidental Federal cost, and $24,580,000 non- 
Federal cost for construction. Amount is based 
on cost allocation report approved by the 
President of the United States on March 9, 
1962. House Document 436, 87th Congress, 2d 
session, established Federal contribution at 28.9 
percent of actual construction cost, but not to 
exceed $14 million, excluding Federal costs for 
engineering, administration of funds, and 
interest on Federal expenditure during construction 
period. Federal contribution authorized 
by 1960 Flood Control Act. 
Local cooperation. In consideration for a 
Federal contribution toward first costs of 
construction, a formal contract pertaining to 
flood control operation of project based upon 
House Document 436, 87th Congress, 2d session, 
was consummated with East Bay Municipal 
Utility District on March 19, 1962, and approved 
by Secretary of the Army April 19, 
1962. An agreement dated January 3, 1961, 
between Utility District and State Department 
of Fish and Game relative to mitigation of 
damage to fish and wildlife was made a part of 
above formal contract. Utility District contracted 
with Amador and Calaveras Counties 
for upstream water rights. Except for final 
settlement for land acquisition, the Camanche 
project was completed in April 1964 and the 
reservoir is in operation. 
Operations and results during fiscal year. 
New work: Engineering continued. 
Condition at end of fiscal year. Construction 
of main dam was initiated in fiscal year 1963; 
dam closure was completed November 1963; 
main dam was completed in April 1964. Except 
for final settlement for land acquisition, Utility 
District has completed project. As of June 30, 
1975. Federal contribution toward flood control 
benefits to be attained was $10,014,293. 
16. LAKE OROVILLE, CALIF. 
Location. Dam is on Feather River, a tributary 
of Sacramento River in Butte County, 
Calif., about 4 miles northeast of town of 
Oroville, and about 70 miles above mouth of 
Feather River. (See Geological Survey topographic 
maps of area.) 
Existing project. Federal participation consists 
of a contribution toward first cost of Lake 
Oroville project, exclusive of cost of power 
facilities, in an amount commensurate with 
flood control benefits to be attained. Federal 
contribution is based on provision of a maximum 
of 750,000 acre-feet of reservoir storage 
space from mid-October to first of April for 
flood control operation of Oroville project. The 
reservoir is a multiple-purpose storage reservoir 
for municipal and industrial water supply, 
power generation, irrigation, flood control, and 
other purposes. The dam is a 770-foot high earth 
and rockfill structure with a total crest length 
of 6,850 feet, creating a reservoir with a 
capacity of about 3,538,000 acre-feet. Included 
in improvement are power-generating facilities 
of 600,000 kilowatts capacity. Cost estimate 
(July 1975) is $317,850,000 (exclusive of power 
facilities), of which $69,050,000 is Federal 
contribution toward new work, exclusive of 
$450,000 incidental Federal costs for engineering 
and administration of funds in connection 
with flood control reservation. Amount is based 
upon cost allocation studies completed in fiscal 
year 1961 and approved by the President of the 
United States on January 10, 1962. Total 
Federal participation is based on 22 percent of 
actual construction cost exclusive of cost of 
power and recreation facilities; however, the 
Federal cost is limited to $85 million including 
actual Federal cost for engineering and administration 
of funds and interest at 3.5 percent per 
annum on actual Federal expenditures during 
35-12

SACRAMENTO, CALIF., DISTRICT 
construction period. Non-Federal cost included 
in the above project amount is $248,350,000 for 
construction of dam and reservoir. Existing 
project was adopted by 1958 Flood Control Act 
(H. Doc. 434, 87th Cong., 2d sess., contains latest 
published map). 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: None. 
Condition at end of fiscal year. State of 
California began relocations in May 1957 and 
initiated main dam contract in January 1963. 
Closure of main dam was completed October 6, 
1967. Initial power unit went on line March 6, 
1968, in Thermolito plant and the first Oroville 
plant unit went on line March 28, 1968. Dam 
was completed in September 1968. Final power 
units went on line July 20, 1969. As of June 30, 
1975, total Federal contribution of $68,228,500 
has been made to the State. 
17. LAKEPORT LAKE, SCOTTS CREEK, 
CALIF. 
Location. On Scotts Creek about 4 miles west 
of city of Lakeport, Calif. (See Geological 
Survey quadrangles for area.) 
Existing project. Provides for construction of 
a 203-foot high earthfill dam to create a 
reservoir with gross storage capacity of 55,000 
acre-feet for flood control, municipal water 
supply, irrigation, general recreation, and fish 
and wildlife. In conjunction with dam, project 
plan provides for about 8 miles of downstream 
environmental mitigation easements, and flood 
plain easements on Scotts Creek below Scotts 
Valley in Lake County to accommodate a 
project design flow of 4,000 cubic feet per 
second in this reach. Operation and maintenance 
of dam and reservoir will be Federal 
responsibility. Approved cost estimate (July 
1975) for existing project is $25,650,000 of 
which $25,400,000 is Federal cost, including 
$900,000 for basic recreation facilities, and 
$250,000 non-Federal cost for lands and damages, 
including relocations for downstream 
levee and channel improvements. For future 
non-Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted 
by 1965 Flood Control Act (H. Doc. 259, 89th 
Cong., 1st sess., contains latest published map). 
Local cooperation. With respect to the dam 
and reservoir, local interests, represented by 
Lake County Flood Control and Water Conservation 
District, must reimburse the Federal 
Government the portion of first cost and annual 
operation, maintenance, and replacement costs 
allocated to municipal water supply (29.8 
percent of first cost and 21.7 percent of annual 
costs) and irrigation (16.6 percent of first cost 
and 8.3 percent of annual costs); pay, contribute 
in kind, or repay (which may be through user 
fees) with interest one-half of separable cost of 
project allocated to recreation and fish and 
wildlife; and bear all costs of operation, maintenance, 
and replacement of recreation and fish 
and wildlife facilities. Before construction, local 
interests must agree to make necessary arrangements 
for repayment of that part of construction 
cost and annual operation and maintenance 
costs allocated to municipal water supply and 
irrigation and settle all claims for water rights, 
including claims pertaining to establishment of 
a permanent pool for fish and wildlife or 
general recreation. With respect to supplemental 
channel improvement work, section 3, Flood 
Control Act of June 22, 1936, applies. Local 
interests must also prevent encroachment of any 
type that would impair flood control effectiveness 
of project works and preserve, or restore, 
and thereafter maintain, the other channels of 
Scotts Creek from the dam downstream to its 
confluence with Middle Creek, at capacities 
existing in 1963. The Lake County Flood 
Control and Water Conservation District has 
indicated intent to provide the foregoing assurances. 
Local cooperation requirements have 
been reviewed and comply with requirements of 
the Water Resources Development Act of 1974. 
Operations and results during fiscal year. 
New work: Land acquisition, preconstruction 
engineering studies, and design memoranda 
were continued, $171,112. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
18. LITTLE DELL LAKE, UTAH 
Location. On Dell Creek, a tributary of 
Parleys Creek, about 8 miles east of Salt Lake 
City, Utah. (See Geological Survey quadrangles 
for area.) 
Existing project. Provides for the construction 
of a dam about 253 feet high, to create a 
reservoir with a gross capacity of 30,000 acrefeet 
for flood control, municipal and industrial 
water supply, recreation and fish and wildlife. 
Project plan includes facilities for the diversion 
of water from Emigration Creek and Parleys 
Creek to the Little Dell reservoir. Reservoir 
would be operated with the existing Mountain 
Dell Reservoir (capacity 3,200 acre-feet) on 
Parleys Creek for flood control and water 
suprly. Approved cost estimate (July 1975) for 
existing project is $48,760,000, of which 
$47,260,000 is Federal cost, including 
$4,260,000 for basic recreation facilities; and 
$1,500,000 is non-Federal required cash contribution 
for lands and relocations allocated to 
35-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
flood control. For future non-Federal reimbursement, 
see Local cooperation paragraph. Existing 
project was adopted by 1968 Flood Control 
Act (S. Doc. 53, 90th Cong., 1st sess., contains 
latest published map). 
Local cooperation. Local interests must give 
assurances satisfactory to the Secretary of the 
Army that they will: (a) obtain without cost to 
the United States all water rights necessary for 
operation of the project in the interest of water 
supply; (b) hold and save the United States free 
from damages due to water-rights claims 
resulting from construction and operation of the 
project; (c) repay all costs allocated to water 
supply, as determined by the Chief of Engineers, 
in accordance with the provisions of the 
Water Supply Act of 1958, as amended; (d) 
contribute the cost of lands, easements, rightsof-
way, and relocations allocated to flood 
control, either in cash or in kind, and bear all 
costs of operation, maintenance and replacements 
for flood control; (e) maintain and operate 
the existing Mountain Dell Reservoir in accordance 
with flood control rules and regulations to 
be prescribed by the Secretary of the Army; (f) 
adequately inform interests affected that the 
project does not provide protection against 
rainfloods originating below the dam, and that 
the project-related diversion facilities do not 
provide protection against large floods on 
Emigration Creek; (g) protect channels downstream 
from the reservoir from encroachment 
which would adversely affect flood control 
operation of the Little Dell complex; and (h) in 
accordance with the Federal Water Project 
Recreation Act: Administer project land and 
water areas for recreation and fish and wildlife 
enhancement; pay, contribute in kind, or repay, 
which may be through user fees, with interest, 
one-half of the separable cost allocated to 
recreation and fish and wildlife enhancement, 
presently estimated at $2,450,000; and bear all 
costs of operation, maintenance and replacement 
of recreation and fish and wildlife lands 
and facilities. On July 7, 1965, the Board of 
Directors of the Metropolitan Water District of 
Salt Lake City passed a resolution of intent to 
furnish the necessary assurances of local 
cooperation. Resolution by Utah Board of Water 
Resources April 4, 1969, stated full support for 
project. On June 12, 1975, Salt Lake County 
Board of County Commissioners agreed to 
provide local cooperation requirements associated 
with flood control function predicated on 
willingness of Salt Lake City to dedicate its 
lands. Local cooperation requirements have 
been reviewed and comply with requirements of 
section 77, Water Resources Development Act of 
1974. 
Operations and results during fiscal year. 
Preconstruction engineering studies and design 
memoranda were continued, $290,656. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
19. LOWER SAN JOAQUIN RIVER 
AND TRIBUTARIES INCLUDING 
TUOLUMNE AND STANISLAUS 
RIVERS, CALIF. 
Location. (a) New Melones Lake: (See 
Improvement No. 33). (b) Tuolumne River 
Basin: Cherry Valley Reservoir-on Cherry 
Creek in upper Tuolumne River watershed, 
about 12 miles above junction with Tuolumne 
River, in northwest corner of Yosemite National 
Park, Calif. New Don Pedro Reservoir-on 
Tuolumne River, a tributary of San Joaquin 
River, in Tuolumne County, Calif., about 32 
miles east of city of Modesto. (c) Lower San 
Joaquin River and tributaries: On lower reaches 
of San Joaquin River and of Stanislaus and 
Tuolumne Rivers. (See Geological Survey quadrangles 
of area.) 
Existing project. Tuolumne River Basin: A 
Federal contribution for flood protection to be 
afforded by local interests construction and 
operation of Cherry Valley and New Don Pedro 
Reservoirs for municipal water supply, power 
generation, irrigation, and flood control. Flood 
protection is being derived from operation for 
flood control of at least 340,000 acre-feet of 
storage in New Don Pedro Reservoir. First 
phase of development by local interests was 
construction for municipal water supply, power 
generation, and other purposes of Cherry Valley 
Reservoir in upper Tuolumne River watershed, 
completed in December 1955 for interim flood 
control storage. Second phase of development 
was construction of New Don Pedro Dam on 
Tuolumne River. Improvement is a rock and 
earthfill dam, 565 feet high, creating a reservoir 
capacity of 2,030,000 acre-feet for municipal 
water supply, power generation, irrigation, 
and flood control. Estimated cost (July 1975) is 
$74,627,000 comprised of $59,768,000 non- 
Federal cost; $14,464,000 Federal contribution, 
including payments totaling $9,000,000 made to 
local interests toward first phase; and $395,000 
Federal engineering and administrative costs, 
including $236,000 expended for initial phase. 
Lower San Joaquin River and tributaries: 
Levee and channel improvement for flood 
control along San Joaquin River from mouth of 
Merced River to San Joaquin Delta near 
Stockton, and on lower reaches of Stanislaus 
and Tuolumne Rivers by raising and strengthening 
existing levees; construction of new 
35-14

SACRAMENTO, CALIF., DISTRICT 
levees; revetment of river banks where required; 
removal of accumulated snags in main 
river channel; and acquisition, by local interests, 
of flowage rights on natural overflow lands 
where necessary to insure continued effectiveness 
of channel storage on San Joaquin River. 
Project was modified to permit local interests to 
construct levees and channel improvements 
upstream from Merced River, where required, 
in lieu of acquiring flowage easements. This 
project is an integral unit of overall plan for 
flood control and other purposes on San Joaquin 
River and tributaries, and supplements reservoir 
units of overall plan involving flood control 
storage on Tuolumne and Stanislaus Rivers and 
in existing Friant Reservoir on upper San 
Joaquin River by providing required channel 
capacity for regulated flows. 
Cost estimate (July 1975) for existing project 
is $19,370,000, of which $13,070,000 is Federal 
cost and $6,300,000 non-Federal cost for lands 
and damages including relocations. Local interests 
constructed levee and channel improvement 
works in area adjacent to river above mouth 
Merced River in lieu of acquisition of flowage 
easements at cost of $24,218,629. Left bank 
levee in Tuolumne River to Merced River reach 
is considered active and is included in foregoing 
cost estimate. Existing project was adopted by 
1944 Flood Control Act (H. Flood Control 
Committee Doc. 2, 78th Cong., 2d sess., contains 
latest published map); as modified by Public 
Law 327, 84th Congress. The 1944 Flood 
Control Act authorized $8 million for partial 
accomplishment of project. Further monetary 
authorizations of $2,500,000, $5 million, $13 
million, $2 million, $17 million, $18 million, $44 
million, and $83 million were provided for this 
project by Public Laws 235 and 780, 83d 
Congress, and 85-500, 90-17, 90-483, 91-282, 92- 
222, and 93-251, making a total monetary 
authorization of $192,500,000 available. 
Local cooperation. Tuolumne River Basin: 
Fully complied with. Lower San Joaquin River 
and tributaries: Fully complied with. Project 
total of 103 miles of levee construction has been 
transferred to and accepted by the State. 
Operations and results during fiscal year. 
New work: Tuolumne River Basin, including 
Cherry Valley and New Don Pedro Reservoirs- 
None. Lower San Joaquin River and 
tributaries-None. 
Condition at end of fiscal year. Tuolumne 
River Basin: Cherry Valley Reservoir-first 
phase, completed in 1950; New Don Pedro 
Reservoir-second phase, construction began in 
August 1967 and was completed in May 1971. 
Total Federal contribution as of June 30, 1972, 
was $5,464,000. Lower San Joaquin River and 
tributaries: Construction began in July 1956 
and was completed in September 1972. State of 
California construction on non-Federal portion 
of project above mouth of Merced River, 
initiated in fiscal year 1960, is complete. 
20. MARTIS CREEK LAKE, MARTIS 
CREEK, NEV. AND CALIF. 
Location. Reservoir to be on Martis Creek, a 
tributary of Truckee River, near Truckee, 
Calif.; intermittent channel improvements 
would be on Truckee River in Reno, Nev. (See 
Geological Survey quadrangles for areas.) 
Existing project. Provides for construction of 
113-foot high rolled-earthfill dam to create a 
reservoir with gross storage capacity of 20,000 
acre-feet for flood control and future municipal 
and industrial water supply. In conjunction 
with the dam, the project provides for construction 
by local interests of intermittent channel 
improvements in Reno, Nev., necessary to 
provide a flood-carrying capacity of 14,000 
cubic feet per second through the city. Approved 
cost estimate (July 1975) for existing 
project is $8,650,000 of which $8,550,000 is 
Federal cost including $300,000 for basic 
recreation facilities, and $100,000 is non- 
Federal cost for channel improvement in Reno, 
Nev. In addition, local interests have, over a 
period of years, expended about $200,000 for 
construction of flood control channels within 
city of Reno. This work is inadequate during 
major floods. Existing project was authorized 
by 1962 Flood Control Act (H. Doc. 435, 87th 
Cong., 2d sess., contains latest published map.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Minor engineering for remedial 
work continued. Maintenance: Ordinary maintenance 
and operation of project, including 
recreation facilities, was continued. Structures 
were maintained in serviceable condition. 
Runoff above Martis Creek Dam was near 
normal for the year. Maximum storage of 3,200 
acre-feet occurred on May 29, 1975. Maximum 
daily inflow to the reservoir was 240 cubic feet 
per second on May 17, 1975, and maximum 
outflow of 127 cubic feet per second occurred on 
June 5, 1975. 
Condition at end of fiscal year. Construction 
of project was initiated in August 1967 and 
completed in June 1974. 
21. MERCED COUNTY STREAM 
GROUP, CALIF. 
Location. Reservoirs and channel improvements 
are on Bear, Burns, Mariposa, and 
Owens Creeks, in foothills of Sierra Nevada 
35-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
about 15 to 20 miles east of city of Merced, 
Calif. (See Geological Survey Haystack Mountain 
quadrangle for Burns and Indian Gulch 
quadrangle for Bear, Owens, and Mariposa 
areas.) 
Existing project. For description of completed 
improvements and authorizing act, see Annual 
Report for 1962. Improvements consist of 
reservoirs at Mariposa, Owens, Burns and Bear 
Creeks and diversions from Black Rascal Creek 
to Bear Creek and from Owens Creek to 
Mariposa Creek. Total first cost for project was 
$3,899,259, of which $2,751,259 was Federal 
and $1,148,000 non-Federal for lands including 
relocations and channel improvement. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Ordinary maintenance and operation 
of the four completed reservoirs continued 
at costs as follows: Mariposa $8,500; Owens 
$8,500; Bear $8,503; and Burns $8,500. Structures 
were maintained in a serviceable condition. 
Runoff from drainage areas above Merced 
County stream group reservoirs was normal for 
the year. (See table 35-H for maximum inflow 
storage and outflow for projects.) Outflows were 
less than channel capacity rates in the project 
streams. 
Condition at end of fiscal year. Construction 
was initiated March 1948, with construction of 
Mariposa project, which was completed in 
November 1948. Construction of Owens project, 
initiated in March, was completed in October 
1949; Burns project, initiated in July 1949; was 
completed in January 1950; and Bear project 
initiated in April, was completed in December 
1954. Black Rascal and Owens Creek diversion 
channels and stream-gaging stations were 
completed in April 1956. Local interests completed 
channel enlargement and restoration of 
channel capacities of Miles, Burns, Owens, and 
Mariposa Creeks in 1956 at their expense. 
Improvement of Bear Creek and Black Rascal 
Slough, below their confluence, was deferred 
pending possible improvements downstream, 
outside limits of project. 
22. MERCED COUNTY STREAMS, 
CALIF. 
Location. In vicinity of city of Merced, Calif., 
on streams draining from Mariposa County 
foothills of the Sierra Nevada into Merced 
County. Streams lie easterly of and drain into 
the San Joaquin River between Chowchilla 
River on the south and Merced River on the 
north. Drainage area represents about 1,000 
square miles; nearly 700 square miles of 
foothills and mountains in Mariposa County and 
about 300 square miles of flood plain in Merced 
County. (See Geological Survey quadrangles for 
area.) 
Existing project. Project is a modification of 
Merced County Stream Group, Calif., Improvement 
No. 21, authorized by 1944 Flood Control 
Act (H. Doc. 473, 78th Cong., 2d sess.) and 
completed fiscal year 1957. Existing project 
provides for construction of three new 
reservoirs-Castle, Haystack Mountain, and 
Marguerite on Canal, Black Rascal, and 
Deadman-Dutchman Creeks, respectively, and 
enlargement of four existing reservoirs-Burns, 
Bear, Owens, and Mariposa, providing a total 
capacity of 126,700 acre-feet for multipurpose 
storage; and about 52 miles of levee and channel 
improvements in lower reaches of Bear, Black 
Rascal, Mariposa, and Deadman Creeks, thereby 
tying the existing project channels into the 
Eastside Bypass of San Joaquin River flood 
control system. Haystack Mountain, Bear, and 
Owens projects would provide flood control 
only; Castle and Burns projects, flood control 
and recreation; Marguerite project, flood control 
and irrigation; and Mariposa project, all 
three purposes. Approved cost estimate (July 
1975) for existing project is $58,200,000, of 
which $54,300,000 is Federal, including 
$3,500,000 for basic recreation facilities, and 
$3,900,000 is non-Federal. For future non- 
Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted by 
1970 Flood Control Act (Document not yet 
printed.) 
Local cooperation. Based on cost allocation 
studies contained in Merced County Streams 
Review Report, about 26.5 percent of cost of 
Marguerite project and 17.7 percent of the cost 
of the Mariposa project (estimated at 
$4,400,000) is allocated to irrigation. Amount 
would be added to Central Valley Project and 
repaid through the sale of water from CVP by 
the U. S. Bureau of Reclamation. In addition, 
one-half of the separable cost of recreation and 
fish and wildlife enhancement (estimated at 
$7,400,000) will be repaid over a period of years 
by local interests. If the Secretary of the 
Interior is unable to make necessary repayment 
arrangements for irrigation services to be 
provided at either of two reservoirs, Mariposa 
or Marguerite, within three years after request 
by the Secretary of the Army, such reservoir, or 
reservoirs, may be constructed without irrigation 
function and reservoir capacity reduced 
accordingly. 
Regarding levees and channels, local interests 
must provide all lands, easements, and rightsof-
way; hold and save the United States free 
from damages due to construction of works; 
maintain and operate works after completion; 
accomplish all relocations and alterations to 
35-16

SACRAMENTO, CALIF., DISTRICT 
existing improvements, including highway 
facilities, which may be required for construction 
of projects; plus prevent encroachment on 
channels and preserve, at 1968 capacities, the 
flood channels within project area which are not 
improved by proposed project. Merced County 
must provide guidance in preventing unwise 
future development of flood plain by use of 
appropriate flood plain management techniques, 
and must at least annually inform 
affected interests of degree of protection provided 
by project. Merced County Board of 
Supervisors by resolution November 1, 1966, 
and reaffirmed by letter August 18, 1967, and 
resolution of July 22, 1969, indicated willingness 
to meet requirements of local cooperation. 
Operations and results during fiscal year. 
Preconstruction engineering studies and design 
memoranda were continued. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
23. MERCED RIVER, CALIF. 
Location. A tributary of San Joaquin River, 
northeast of town of Merced, Calif. (See 
Geological Survey topographic maps of the 
area.) 
Existing project. Federal interest in development 
is in flood protection afforded by multiplepurpose 
New Exchequer Reservoir. For description 
of improvement and authorizing act, 
see Annual Report for 1969. Estimated cost 
(July 1975) for project is $28,880,000, of which 
$11,020,000 is Federal cost, comprising 
$10,920,000 direct Federal contribution to local 
interests and $100,000 incidental Federal cost 
for engineering and administration of funds. 
Amount is based upon cost allocation studies 
approved by the President of the United States 
April 27, 1964. Total Federal contribution is 
based on 37.6 percent of actual construction cost 
of New Exchequer Dam and Reservoir, including 
all necessary relocations, but exclusive of 
cost of power and recreation facilities; however, 
the Federal contribution is limited to 
$19,400,000. Non-Federal cost included in the 
above amount is $17,860,000. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Federal contribution of $187,645 was made to 
the Merced Irrigation District. 
Condition at end of fiscal year. Merced 
Irrigation District inititated construction in 
June 1964; closure began in March 1965 and 
was completed in April 1966. Dam was completed 
in September 1966. As of June 30, 1975, 
total Federal contribution of $10,817,798 has 
been made to Irrigation District. 
24. MORMON SLOUGH, CALAVERAS 
RIVER, CALIF. 
Location. A distributary of Calaveras River, 
heads near town of Bellota, about 17 miles east 
of city of Stockton, Calif. Flows southwesterly to 
about 4 miles upstream from Stockton where it 
is diverted into Calaveras River through Stockton 
Diverting Canal. (See Geological Survey 
Sheet, Stockton quadrangle.) 
Existing project. For description of improvement 
and authorizing act, see Annual Report 
for 1969. Estimated cost (July 1975) is 
$5,770,800, of which $2,885,400 is Federal and 
$2,885,400 is non-Federal. Local interests also 
expended about $200,000 for construction of low 
levees in intermittent reaches along Mormon 
Slough, the diverting canal, and Calaveras 
River to provide some local flood protection. 
This protection is inadequate during major 
floods. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: None. 
Condition at end of fiscal year. Construction 
was initiated in October 1967 and completed in 
February 1970. All levee construction (25.2 
miles), channel improvement (14.2 miles), and 
the 3 interior drainage pumping plants have 
been transferred to and accepted by local 
interests, who have accepted maintenance 
responsibility for the project as well as for 
Stockton and Mormon Channels (Diverting 
Canal), Calif. As of June 30, 1975, total Federal 
contribution of $466,287 has been made to local 
interests. Final cash contribution to local 
interests is scheduled for next year. 
25. PINE FLAT LAKE AND KINGS 
RIVER, CALIF. 
Location. Reservoir is on Kings River, about 
25 miles east of Fresno, Calif., and channel 
improvements are on Kings River downstream 
from Lemoore weir, about 25 miles south of 
Fresno. (See Geological Survey quadrangles of 
area.) 
Existing project. Improvement is a unit in 
comprehensive plan for flood control and other 
related purposes for Sacramento-San Joaquin 
Basins. Project consists of a 429-foot high 
concrete gravity dam, including a gated overflow 
section with a maximum discharge capacity 
of 391,000 cubic feet per second, creating a 
reservoir with gross storage capacity of 1 
million acre-feet, for flood control, irrigation, 
and related purposes. Outlet provisions for 
future power development are included in dam, 
but Federal construction of power-generating 
facilities is not authorized. Improvement also 
35-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
includes a limited amount of channel improvement 
on Kings River and its distributaries on 
valley floor about 25 miles south of Fresno. 
Channel improvement work will enlarge channel 
capacities and regulate flows in lower 
branches of the Kings River. There are nine 
public-use and recreation areas: One maintained 
by the Corps, four by the Forest Service, 
three jointly by the Corps and concession, and 
one by Fresno County. Also, five boat accessonly 
areas are maintained by the Corps on the 
south side of reservoir. Approved cost estimate 
(July 1975) is $42,720,000, of whicl $42,100,000 
is Federal (including $13,700 for basic recreation 
facilities) and $620,000 non-Federal for 
rights-of-way for downstream channel improvements. 
For future non-Federal reimbursement, 
see Local cooperation paragraph. Estimated 
Federal cost of recreation facilities for Pine 
Flat Lake, to be funded from Code 710 
appropriations is $900,000 (July 1975) exclusive 
of recreation facilities previously provided at a 
cost of $13,700. In addition, Federal cost of 
recreation facilities for Pine Flat Lake, funded 
from Public Works Acceleration Executive Act 
of 1962 appropriations, was $239,235 (July 
1963). Operation and maintenance of dam and 
reservoir is Federal responsibility. Existing 
project was adopted by 1944 Flood Control Act 
(H. Doc. 630, 76th Cong., 3d sess., contains latest 
published map). 
Local cooperation. Local interests must reimburse 
the Federal Government for first costs 
allocated to irrigation functions of reservoir 
portion of project in accordance with reclamation 
law. Under provision of War Department 
Civil Appropriations Act of 1947, the Secretary 
of War, with concurrence of the Secretary of the 
Interior, determined allocation of cost to irrigation 
should be set at an amount not to exceed 
$14,250,000. In addition, local interests must 
pay 37.4 percent of annual maintenance, operation, 
and replacement costs of dam and reservoir 
allocated to irrigation function. Repayment 
contracts between Bureau of Reclamation and 
the local water users for the irrigation use of the 
reservoir were executed December 23, 1963. 
Bureau is administering the contracts in 
accordance with reclamation law; however, 
local interests are testing in court the validity of 
reclamation law in regard to the Pine Flat 
contracts. Prior to execution of the final 
contracts, the Bureau provided conservation 
water to local interests under an interim 
contract. Irrigation interests paid $12,029,686 
for irrigation services through December 31, 
1974. With respect to the downstream channel 
improvements, section 3, Flood Control Act of 
June 22, 1936, applies. Kings River Conservation 
District represents local interests; assurances 
were accepted November 20, 1959. Local 
interests have furnished all requirements for 
construction rights-of-way for construction of 
channel improvements required to date. Three 
concessionaires-one each at Lakeridge Marina 
(Deer Creek), Lakeview Marina (Lombardo's 
Fishing Village), and Trimmer Marina provided 
public-use facilities in accordance with 
lease agreements with the Secretary of the 
Army. Estimated cost of facilities installed by 
these concessionaires is $357,000. Fresno 
County developed public-use facilities on an 85- 
acre tract immediately downstream from dam 
for picnicking, camping, swimming, and playground 
activities, at an estimated cost of 
$88,500 under provisions of a license agreement. 
Forest Service operates a picnic area at upper 
end of reservoir and two campgrounds and a 
picnic area at sites along reservoir perimeter. 
Total cost of development of these sites is about 
$37,500. 
Licenses. License No. 1988, effective April 1, 
1955, was issued by Federal Power Commission 
to Pacific Gas and Electric Co. for hydroelectric 
power development of North Fork Kings River 
by the company upstream from the Pine Flat 
reservoir. Under interim Contract No. DA-04- 
167-eng-1182 with the Department of the Army, 
Pacific Gas and Electric Co. paid for storage of 
power water in the Pine Flat reservoir May 15, 
1954, through March 31, 1955. Current Contract 
No. DA-04-167-eng-1328 with the Department 
of the Army provides for storage of power 
water at the rate of 0.1375 per acre-foot; the 
contract covers April 1, 1955, through March 
31, 2005. Total payment under these contracts 
through June 30, 1975, amounts to $2,478,798; 
these funds are paid to Sacramento District and 
deposited for return to the Treasury. 
Operations and results during fiscal year. 
New work, regular funds: Engineering and 
design continued. Code 710 funds: None. Maintenance: 
Maintenance and operation activities 
continued with condition and operation studies 
at a cost of $66,671 and major maintenance 
costs as follows: Dam and reservoir $83,005; 
service facilities $67,991; and recreation facilities 
$108,561. Structures were maintained in 
serviceable condition. Runoff of Kings -River 
above Pine Flat Dam was near normal for the 
year. Maximum storage of 954,200 acre-feet 
occurred on July 1, 1974. Maximum daily 
inflow to reservoir was 12,300 cubic feet per 
second on June 1, 1975. Maximum outflow of 
7,450 cubic feet per second occurred on June 19, 
1975. Release of water for irrigation and 
spreading totaled 1,719,000 acre-feet. 
Condition at end of fiscal year. Construction 
began in April 1947 and project is about 99 
percent complete. Main dam was initiated in 
35-18

SACRAMENTO, CALIF., DISTRICT 
January 1950, completed in June 1954, and has 
been operating since February 1954 to provide 
flood protection for which it was designed. Total 
of 29.6 miles of channel improvement has been 
transferred to the Kings River Conservation 
District for maintenance. Recreation facilities 
for various recreation areas under Code 710 
appropriation initiated in fiscal year 1960 are 
100 percent complete. Work remaining consists 
of completion of minor channel improvements 
and recreation facilities in connection with 
overall development of reservoir area. 
26. SACRAMENTO RIVER AND 
TRIBUTARIES, CALIF., 
FROM COLLINSVILLE TO 
SHASTA DAM 
Location. Rises in Trinity Mountains in northcentral 
California, flows generally southerly 
about 374 miles and empties into Suisun Bay, 
an arm of San Francisco Bay at Collinsville, 
Calif. Works covered by this improvement are 
on Sacramento River and tributaries from 
Collinsville to Shasta Dam, about mile 312. 
Drainage area above Rio Vista is 26,500 square 
miles (See Geological Survey quadrangles of 
area for Sacramento River and Upper Butte 
Basin; Flournoy and Fruto quadrangles for 
Black Butte Lake; and Tuscan Buttes, Tehama, 
Redding, and Hooker quadrangles for Table 
Mountain Lake.) 
Existing project. Improvement of Sacramento 
River and tributaries, from Collinsville to 
Shasta Dam was authorized as a unit of a 
comprehensive plan for flood control and other 
related purposes in Sacramento River Basin. (a) 
Sacramento River and major and minor 
tributaries, for flood control purposes: Enlargement 
of existing levees on Sacramento River 
between vicinity of Moulton weir and Ord Bend; 
construction of new levees from present levee 
terminus to vicinity of Chico Landing; construction 
of a weir near Chico Landing, extension of 
Moulton weir, and construction of a bypass 
through Upper Butte Basin; construction of new 
levees in Lower Butte Basin; enlargement of 
existing levees in Sutter, Tisdale, Sacramento, 
and Yolo Bypasses; and levee construction 
and/or channel enlargement on following minor 
tributaries of Sacramento River: Antelope 
Creek; Chico and Mud Creeks and Sandy Gulch; 
Butte and Little Chico Creeks; Cherokee Canal; 
Elder Creek; Deer Creek (Tehama County); 
Thomes Creek; and Willow Creek. Improvement 
provides for about 155 miles of channel improvement 
and about 294 miles of levees with 
an average height of 12 feet and a freeboard of 3 
feet. Improvement also provides for revetment 
as required for protection of bypass levee slopes 
against erosion. Total first cost for project is $18 
million (July 1975), of which $11,900,000 is 
Federal, and $6,100,000 non-Federal for lands 
and damages, including relocations. (See table 
35-I on project units classified and excluded 
from cost estimate.) (b) Construction of about 
50,000 feet of bank protection and minor 
channel improvements as required on 
Sacramento River between Chico Landing and 
Red Bluff for flood control purposes. Improvement 
also contemplates flood plain zoning 
between Chico Landing and Keswick Dam to 
assure maintenance of present project floodway 
areas. Estimated first cost (July 1975) for 
project work in Tehama, Butte, and Glenn 
Counties is $4,660,000, of which $4,290,000 is 
Federal cost and $370,000 non-Federal cost for 
lands and damages including relocations. (c) 
Sacramento River, Calif., bank protection: 
Addition of about 430,000 lineal feet of bank 
erosion control works and setback levees at 
critical locations existing at time of report or 
expected to develop in 10 years, within limits of 
authorized or existing levees included in 
Sacramento River flood control project, as 
initial phase of a long-range program to protect 
integrity of levee system for flood control 
purposes. Total estimated (July 1975) first cost 
for project is $103,200,000, of which $64,800,000 
is Federal (including $1,740,000 for recreation 
facilities) and $34,400,000 non-Federal comprising 
$18,860,000 for lands and damages 
including relocations and $15,540,000 required 
cash contribution toward first cost. Construction 
in (a), (b), and (c) above supplements 
program of levee improvements which is being 
accomplished pursuant to 1917 Flood Control 
Act, as amended by subsequent acts, including 
1941 Flood Control Act, and which are reported 
by California Debris Commission under 
Sacramento River, Calif., flood control. (d) 
Authorization also provided for Black Butte 
Lake by construction of an earthfill dam, with a 
maximum height of 156 feet, to create a 
reservoir with gross storage capacity of 160,000 
acre-feet for flood control, irrigation, and 
related conservation purposes. Improvement is 
in Tehama and Glenn Counties about 9 miles 
west of Orland, Calif., on Stony Creek, a 
tributary entering Sacramento River at mile 
190. Estimated (July 1975) Federal first cost 
for project is $14,515,000, including $468,000 
for basic recreation facilities. For future non- 
Federal reimbursement, see Local cooperation 
paragraph. Estimated Federal cost for additional 
recreation facilities to be funded from 
Code 710 appropriations is $458,000. A concessionaire 
at Black Butte Marina provided 
public use facilities in accordance with lease 
agreement with the Secretary of the Army at an 
estimated cost of $65,000. (e) Authorization also 
35-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
provided for construction of Table Mountain 
(Iron Canyon) project, an earthfill dam, with a 
maximum height of 210 feet, to create a 
reservoir with gross storage capacity of 503,000 
acre-feet, for flood control, water conservation, 
and power generation. Reservoir would be on 
Sacramento River about 3 miles north of Red 
Bluff, in Tehama and Shasta Counties, Calif. 
This project unit was reclassified, is in an 
inactive status, and deauthorization of the 
project was recommended. Estimated Federal 
cost of this unit, including power facility, (July 
1954) is $77,200,000. Local interests would be 
required to pay the portion of first cost and 
annual operation and maintenance cost 
allocated to conservation functions of the 
project. These costs have not been determined. 
(See table 35-B for authorizing legislation.) 
Local cooperation. (a) Sacramento River and 
major and minor tributaries: Section 3, Flood 
Control Act of June 22, 1936, applies. Fully 
complied with for all work completed or under 
contract, and local interests indicated they will 
be able to fulfill requirements for remaining 
work as scheduled. Levee construction (107 
miles) total requirement for the "active" project 
has been completed, transferred to, and 
accepted by the State. (b) Sacramento River, 
Chico Landing to Red Bluff: Section 3, Flood 
Control Act of June 22, 1936, applies; local 
interests must also assume responsibility for 
flood plain zoning. Fully complied with for 
portion completed in Tehama County; completed 
work was transferred to and accepted by 
the State. Flood plain zoning ordinances were 
rejected by Butte County Board of Supervisors 
in July 1961 and by Glenn County residents in 
September 1963; work in both counties was 
classified inactive. Flood plain zoning requirements 
for Butte County were satisfied in 
March 1971; Butte County was reclassified as 
active in September 1971; and formal 
assurances were received June 29, 1972. Flood 
plain zoning requirements were satisfied in 
May 1972; Glenn County was reclassified as 
active in December 1972; and formal assurances 
were received March 1973. (c) Sacramento 
River, Calif., bank protection: Section 3, Flood 
Control Act of June 22, 1936, applies. Local 
interests must also contribute an amount in 
cash that, when added to costs of lands and 
rights-of-way and utility modifications, equals 
one-third of cost of each unit of remedial work; 
this contribution is estimated (July 1975) at 
$15,540,000. Local interests fully complied with 
requirements for all work completed or under 
contract, and indicated they will be able to 
fulfill requirements for all work completed or 
under contract, and fulfill requirements for 
remaining work as scheduled. In addition, for 
reaches where local interests request bank 
stabilization in lieu of more feasible levee setbacks, 
local interests will contribute costs over 
and above costs of setbacks, and provide local 
contribution indicated above. Completed units 
transferred to and accepted by the State. (d) 
Black Butte Lake: None required for construction. 
Local interests must pay the portion of 
first cost and annual operation and maintenance 
costs allocated to the conservation functions of 
the project; these costs are estimated at 39.9 
percent of first cost and 40.2 of annual costs. 
From March 2, 1960, to October 22, 1970, 
contract between the Bureau of Reclamation 
and the State of California provided for 
repayment of irrigation storage costs; Bureau 
administered contract in accordance with 
reclamation law. Local interests paid a total of 
$77,205 for irrigation services during this 
period. Public Law 502, 91st Cong., 2d sess., 
October 23, 1970, provided that Black Butte 
project be financially integrated with the 
Central Valley project, coordinated 
operationally with other Central Valley project 
storage units by the Bureau under the 
Secretary of the Interior, and that dam and 
reservoir at Black Butte be physically operated 
and maintained by the Corps in a manner 
compatible with recreational use of the reservoir. 
(e) Table Mountain (Iron Canyon) Lake: 
None required for construction. Local interests 
must pay for portion of first cost and annual 
operation and maintenance cost allocated to 
conservation functions of project; since the 
project is in an inactive status, these costs have 
not been determined. 
Operations and results during fiscal year. 
New work: (a) Sacramento River and major and 
minor tributaries-Engineering and design 
continued. (b) Sacramento River, Calif., bank 
protection-Engineering and design, including 
preparation of plans and specifications, continued 
by hired labor at a cost of $216,961, of 
which $168,575 was Federal cost and $48,386 
required contributed funds. (See table 35-J for 
construction accomplished and contract costs.) 
(c) Sacramento River, Chico Landing to Red 
Bluff-New work: Engineering continued at a 
cost of $113,633. Bank protection was accomplished 
at sites, mile 208.4 and mile 213.0, 
in Butte County by contract, $307,585. (d) Black 
Butte Lake, New work, regular funds: None. 
Code 710 funds: Minor engineering continued. 
Maintenance: Maintenance and operation activities 
continued with condition and operation 
studies at a cost of $45,806 and major 
maintenance costs as follows: Dam and reservoir 
$39,192; service facilities $23,327; and 
recreation facilities $166,548. Structures were 
maintained in serviceable condition. Runoff 
35-20

SACRAMENTO, CALIF., DISTRICT 
above Black Butte Dam was near normal for 
the year. Maximum storage of 119,000 acre-feet 
occurred April 30, 1975. Maximum inflow to 
reservoir was 19,000 cubic feet per second on 
March 22, 1975, and maximum outflow of 7,050 
cubic feet per second occurred on March 8, 
1975. Release of water for irrigation totaled 
229,000 acre-feet. Water released for flood 
control amounted to 276,000 acre-feet. 
Condition at end of fiscal year. (a) Major and 
minor tributaries (active portions): Construction 
was initiated in May 1949 on Deer Creek and 
Butte Creek units; Cherokee Canal, Elder 
Creek, Chico and Mud Creeks, and Sandy Gulch 
units have been completed. Active portion of 
this improvement is about 90 percent complete. 
Work remaining is completion of bypass levee 
revetment. (b) Sacramento River, Calif., bank 
protection: Construction of first unit was 
initiated in June 1963; initial phase of project is 
about 99 percent complete. Work remaining to 
complete improvement includes completion of 
work underway and provision of additional 
bank erosion control works and setback levees 
at critical locations now existing or expected to 
develop during authorized construction period. 
(c) Sacramento River, Chico Landing to Red 
Bluff: Active portion of project, bank protection 
in Tehama County, was initiated in June 1963 
and completed in March 1964. Project was 
reopened in June 1968 to place additional 
necessary bank protection. Bank protection in 
Tehama County reach was completed in October 
1968. Work authorized in Butte and Glenn 
Counties was reclassified inactive in October 
1963 pending receipt of local cooperation 
requirements for these counties. In March 
1971, local cooperation requirements for Butte 
County were received and in September 1971, 
Butte County was reclassified to active. In May 
1972, local cooperation requirements for Glenn 
County were received and in December 1972, 
Glenn County was reclassified to active. (d) 
Black Butte Lake: Construction began in March 
1960 and project is complete except for final 
settlement of land acquisition. Construction of 
main dam was initiated in June 1960 and 
completed in December 1963. Dam has been 
operating since November 1962 to provide the 
flood protection for which it was designed. 
27. WALNUT CREEK, CALIF. 
Location. Project is on Walnut Creek and 
lower reaches of its principal tributaries, 
Pacheco, Grayson, San Ramon, Las Trampas, 
Galindo, and Upper Pine Creeks in Contra 
Costa County, Calif. Improvement will extend 
from Suisun Bay to head of project about 1 mile 
above southern limits of city of Walnut Creek. 
City of Walnut Creek is about 10 miles south of 
Suisun Bay. (See Geological Survey quadrangles 
for area.) 
Existing project. Comprises extension of 
existing levees, construction of new levees and 
concrete channels, construction of pumping 
plants for disposal of interior drainage, channel 
rectification and enlargement, and utilization of 
improvements constructed or planned by local 
interests. Plan provides for about 21.8 miles of 
channel improvement, two reinforced-concrete 
drop structures, one stilling basin, 13.8 miles of 
levees, and one pumping plant. Approved cost 
estimate (July 1975) is $59,950,000, of which 
$43,900,000 is Federal and $16,050,000, non- 
Federal consisting of $12,550,000 for lands and 
damages and relocations except railroad facilities, 
and $3,500,000 required cash contribution 
for land enhancement benefits provided by the 
project. Local interests have also expended 
about $3 million for flood control in the project 
area since 1955, including concrete conduits 
constructed through city of Walnut Creek by 
local interests at an estimated cost of $1,000,000 
considered a preproject condition to be incorporated 
in the Corps project and cost thereof is not 
included in above costs of local cooperation. 
Improvement adopted by 1960 Flood Control 
Act (H. Doc. 76, 86th Cong., 1st sess., contains 
latest published map). 
Local cooperation. Section 3, Flood Control 
Act of June 22, 1936, applies, except that 
relocation of railroad facilities is a Federal 
responsibility. In addition, local interests must 
make a cash contribution to the United States, 
in amount of 7.4 percent of cost of construction 
for land enhancement benefits provided by 
project. Cash contribution is estimated (July 
1975) at $3,500,000. Local interests are represented 
by Contra Costa' County Flood Control 
and Water Conservation District; formal assurances, 
including evidence of financial and legal 
ability to fulfill requirement for the cash 
contribution, were accepted by the Sacramento 
District Engineer November 15, 1963. Flood 
Control District furnished all rights-of-way 
required to date and indicated that it will 
furnish all requirements as needed for future 
construction. Flood Control District will arrange 
for highway bridge modifications and 
utility relocations before start of work by the 
Corps contractor or the work will be coordinated 
with that of the Corps contractor. 
Payment of required contributed funds will be 
made in installments in amounts equal to 7.4 
percent of the estimated construction expenditure 
for each fiscal year. To date $1,995,916 has 
been furnished. 
35-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. 
New work: Engineering and design, including 
preparation of plans and specifications, continued 
by hired labor at a cost of $119,216, of 
which $108,773 was Federal cost and $10,443 
required contributed funds. 
Condition at end of fiscal year. Construction 
was initiated June 1964; project is about 54 
percent complete. Total of 13.1 miles of channel 
improvement, 9.2 miles of levee construction, 
part of channel improvement landscaping, and 
Drop Structures No. 1 and No. 2 have been 
transferred to local interests for operation and 
maintenance. Planning continued and is closely 
coordinated with Soil Conservation Service. 
28. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and 
maintenance of flood control works, part 208, 
title 33, Code of Federal Regulations, provide 
for inspection of completed projects transferred. 
to local interests for operation and maintenance 
to determine status of project and insure 
compliance with regulations. During fiscal 
year, inspections were made of: Completed units 
of Sacramento River and major and minor 
tributaries; completed units of Sacramento 
River flood control project, Kings River 
Channel Improvement (Pine Flat Lake project), 
and Walnut Creek project; American River 
levees; Middle Creek; Duck Creek diversion, 
Green Valley Creek, Littlejohn Creek, Mormon 
Slough, Bear Creek, and North Fork, Pit River 
at Alturas, all in California; Truckee River, 
Calif. and Nev.; completed units of lower San 
Joaquin River and tributaries, Calif; Big Dry 
Creek Dam and diversion, Calif.; Reese River, 
Battle Mountain, Nev.; Sevier River, Redmond 
and vicinity, Jordan River, Big Wash near 
Milford, and Kays Creek, all in Utah; various 
emergency flood control works under authority 
of section 208, Flood Control Act of June 30, 
1948, and September 3, 1954; Public Law 99, 
June 28, 1955, and antecedent legislation; and 
section 14 of Flood Control Act of July 24, 1946. 
Maintenance inspections conducted indicate 
that existing agreements and regulations are 
being complied with on completed flood control 
works. Continuing effort is required to improve 
maintenance practices and active steps are 
being taken by responsible State and local 
agencies to achieve desired results. Local 
agencies were advised, as necessary, of 
measures required to maintain these projects in 
accordance with standards prescribed by 
regulations. Total cost of inspection for fiscal 
year was $60,025. 
29. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with section 7, Flood Control 
Act of 1944, summaries of monthly operations 
at Oroville, Folsom, Friant, Shasta, Camanche, 
Wanship, Echo, Pineview, East Canyon, Lost 
Creek, Causey, Devil Creek, Prosser Creek, 
Stampede, Boca, Los Banos Detention, Big Dry 
Creek, New Bullards Bar, New Don Pedro, and 
New Exchequer (Lake McClure) Reservoirs 
were prepared and distributed. Interim operating 
instructions and draft of proposed flood 
control regulations for Indian Valley Reservoir 
were completed and a report on reservoir 
regulation for flood control was initiated. Corps 
personnel provided advice as requested during 
flood control operations at all section 7 reservoirs. 
Fiscal year cost was $79,175. Total cost to 
June 30, 1975, was $653,765. 
30. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 35-K. 
31. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 
205, Public Law 858, 80th Congress, as amended 
(Preauthorization) 
Fiscal year costs for preauthorization studies 
were as follows: Calif.: Kern River-California 
Aqueduct Intertie, $102,684; City of Isleton, 
$20,428; and Hamilton City, $5,116; and Utah: 
Barton and Mill Creeks, $6,048; Payson, 
$10,000; and Coal Creek, Cedar City, $56. 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation) 
Federal cost for fiscal year was $1,375,447, of 
which $79,982 was for advance preparation, 
-$52,502 for flood emergency operations, and 
$1,347,967 for repair and restoration. 
Emergency bank protection (sec 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Federal cost for fiscal year was $127,279. 
Bank protection was completed on Sacramento 
River near Ord Bend, Calif., ($56,276); Red 
Creek-water supply line near Paragonah, 
Utah ($623); and Yampa River-water treatment 
plant at Hayden, Colo., ($38,836) and 
sewage disposal plant at Steamboat Springs, 
Colo., ($23,688); and initiated on Sacramento 
River-waste treatment plant near city of 
Redding, Calif., ($7,861). 
35-22

SACRAMENTO, CALIF., DISTRICT 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (sec. 208, 
1954 Flood Control Act, Public Law 780, 83d 
Cong.) 
Federal cost for fiscal year was $29,566 for 
completion of snagging and clearing on Ash and 
Dry Creeks, Calif. 
Flood insurance activities (sec. 1301-1377, 
1968 Housing and Urban Development Act, 
Public Law 90-448 as amended) 
In coordination with flood control activities, 
one flood insurance study was completed, three 
flood insurance studies were continued, and ten 
flood insurance studies were initiated in accordance 
with Inter-Agency Agreements (IAA) H- 
2-73, H-16-74, and H-16-75 at a fiscal year cost 
of $238,954 under Housing and Urban Development 
reimbursable order. 
Multiple-Purpose Projects including Power 
32. MARYSVILLE LAKE, CALIF. 
Location. On main stem of Yuba River about 
11 miles northeast of city of Marysville, Calif. 
(See Geological Survey quadrangles for area.) 
Existing project. Provides for construction of 
(a) a 215-foot high earthfill dam to create a 
reservoir with gross storage capacity of about 
1,000,000 acre-feet for flood control, irrigation, 
power, general recreation and fish and wildlife 
purposes, (b) a powerplant with installed 
capacity of about 50,000 kilowatts, and (c) a low, 
combination concrete and earthfill afterbay 
dam about 19,200 feet long at Daguerre Point. 
Operation and maintenance of dam and powerplant 
will be the responsibility of the Federal 
Government. Approved cost estimate (July 
1975) for existing project is $275,000,000, all of 
which is Federal cost, including $4,140,000 for 
basic recreation facilities. For future non- 
Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted by 
1966 Flood Control Act. (H. Doc. 501, 89th 
Cong., 2d sess.). 
Local cooperation. With respect to the dam 
and reservoir, local interests, represented by the 
State of California, must (a) reimburse the 
Federal Government the portion of joint use 
first costs allocated to water supply (36.0 
percent) and to power (10.3 percent) in addition 
to specific power costs (presently estimated at 
$36,400,000), (b) pay, contribute in kind, or 
repay (which may be through user fees) with 
interest, one-half of the separable cost (presently 
estimated at $2,070,000) of the project 
allocated to recreation and fish and wildlife, 
and (c) bear all costs of operation, maintenance, 
and replacement of recreation and fish and 
wildlife lands and facilities. (Public Law 89-72, 
the Federal Water Project Recreation Act.) On 
June 29, 1966, the California Resources Agency 
stated its intention to provide necessary leadership 
in furnishing the assurances of local 
cooperation required by the 1965 Federal Water 
Project Recreation Act. On December 19, 1972, 
Yuba County Board of Supervisors stated 
intention to provide assurances of local cooperation 
required by the Federal Water Project 
Recreation Act. 
Operations and results during fiscal year. 
New work: Preconstruction engineering studies 
and design memoranda were continued, 
$527,235. 
Condition at end of fiscal year. Preconstruction 
planning was continued. 
33. NEW MELONES LAKE, CALIF. 
Location. On Stanislaus River about threequarters 
mile downstream from existing Melones 
Dam and about 35 miles northeast of city 
of Modesto. (See also Improvement No. 19 for 
Tuolumne River Basin and Lower San Joaquin 
River and tributaries.) (See Geological Survey 
quadrangles of the area.) 
Existing project. Provides for construction of 
(a) an earth and rockfill dam about 625 feet 
high to create a reservoir with gross storage 
capacity of about 2,400,000 acre-feet for flood 
control, irrigation, power, general recreation, 
fish and wildlife, and other purposes, and (b) a 
powerplant below the dam with an installed 
capacity of 300,000 kilowatts. Upon completion 
of construction of dam and powerplant by the 
Corps, the project shall become an integral part 
of Central Valley project and operated and 
maintained by the Secretary of the Interior 
pursuant to Federal reclamation laws, except 
that the flood control operation of the project 
shall be in accordance with rules and regulations 
prescribed by the Secretary of the Army. 
Maintenance of Stanislaus River channel from 
Goodwin Dam to San Joaquin River to a 
capacity of at least 8,000 cubic feet per second 
will also be Corps responsibility. Approved 
estimated (July 1975) Federal cost is 
$283,000,000. For future non-Federal reimbursement, 
see Local cooperation paragraph. In 
addition, local interests expended $300,000 for 
levees along lower reaches of Stanislaus River. 
Existing project was adopted by 1962 Flood 
Control Act (H. Doc. 453, 87th Cong., 2d sess., 
contains latest published map). This act modified 
original authorization adopted by 1944 
Flood Control Act. (H. Flood Control Committee 
Doc. 2, 78th Cong., 2d sess., contains latest 
published map.) The 1944 Flood Control Act 
35-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
authorized $8 million for partial accomplishment 
of project. Further monetary authorizations 
of $2,500,000, $5 million, $13 million, $2 
million, $17 million, $18 million, $44 million, 
and $83 million were provided for this project 
by Public Laws 235 and 780, 83d Cong., and 85- 
500, 90-17, 90-483, 91-282, 92-222, and 93-251, 
making a total monetary authorization of 
$192,500,000 available for the basin plan 
comprising Lower San Joaquin River and 
tributaries, including Tuolumne and Stanislaus 
Rivers, Calif. 
Local cooperation. Based on approved preliminary 
cost allocation studies (Jury 1965) local 
interests will be required to pay 35.2 percent of 
first cost and 12.7 percent of annual operation 
and maintenance costs allocated to irrigation. In 
addition, 31.1 percent of first cost and 62.5 
percent of annual cost would be allocated to 
power. Local interests must also maintain 
existing private levees along Stanislaus River 
from Goodwin Dam to San Joaquin River and 
prevent encroachment on channel and floodway 
between levees to preserve safe carrying capacity 
throughout that reach of at least 8,000 cubic 
feet per second. Recovery of costs allocated to 
irrigation and power will be responsibility of 
Bureau of Reclamation. Reimbursement of 
costs will be in accordance with Bureau of 
Reclamation policies and procedures for the 
Central Valley project. State of California 
officially adopted project by chapter 918 of 
statutes of 1963, and by chapter 1438 of those 
statutes authorized State Reclamation Board to 
furnish required assurances. The Board, by 
letter dated December 13, 1963, stated it will 
furnish required assurances when formally 
requested to do so. 
Operations and results during fiscal year. 
New work: Engineering studies pertaining to 
preparation of design memoranda were continued. 
Plans and specifications were continued 
for relocations, dam and appurtenances, and 
powerplant. Total engineering costs were 
$1,100,118. Land acquisition activities continued 
at cost of $1,642,934. State Highway 49 
relocation contract continued, $3,904,231. Main 
dam construction contract continued 
$23,842,503. 
Condition at end of fiscal year. Construction 
was initiated in August 1966; project is about 35 
percent complete. 
General Investigations 
34. SURVEYS 
See table 35-L. 
35. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain information studies were made at 
fiscal year costs as follows: Calif.: Anderson, 
$55,000; Downieville, $45,000; Redding, 
$30,000; and Stockton SW, $45,000; Colo.: 
Fruita, $24,000; and Steamboat Springs, 
$34,918; Farmington, $64,918; and Utah: 
Brigham City, $35,000. 
Technical assistance was performed for other 
Federal Agencies as well as non-Federal 
Agencies in connection with Flood Plain Management 
Services Program at a fiscal year cost 
of $220,672. (See table 35-M on completed flood 
plain information studies). 
Fiscal year costs for hydrologic studies were 
$18,111. 
36. RESEARCH AND DEVELOPMENT 
Fiscal year costs were $616,736, of which 
$606,736 was for engineering studies ES-100, 
Hydrologic Engineering Center; and $10,000 
for predictive sediment models. 
35-24

SACRAMENTO, CALIF., DISTRICT 
TABLE 35-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project Funding FY 72 
1. Sacramento River, New Work 
' A .,, _ 
Total Cost to 
FY 73 FY 74 FY 75 June 30, 1975 
35-25 
al. pprp. - - - - 
Cost - - - - 
Maint. 
Approp. 1,302,300 947,000 964,300 902,200 
Cost 1,028,369 1,161,688 1,098,690 898,231 
2. San Francisco Bay New Work 
to Stockton, Calif. Approp. 853,000 925,000 1,220,000 410,000 
(John F. Baldwin and Cost 962,680 856,010 1,233,217 589,153 
Stockton Ship 
Channels) 
3. San Joaquin River, New Work 
Calif. Approp. - - - 
Cost - - - 
Maint. 
Approp. 453,000 43,300 8,400 5,000 
Cost 451,427 31,999 22,317 4,948 
6. Buchanan Dam-H.V. New Work 
Eastman Lake, Approp. 1,719,200 6,078,000 6,000,000 4,100,000 
Chowchilla River, Cost 1,465,150 6,322,364 5,269,112 4,366,489 
Calif. 
(Federal Funds) 
(Contributed Funds New Work 
Other) Contrib. - - - 118,000 
Cost - - - 107,285 
7. Calaveras River and New Work 
Littlejohn Creek and Approp. -19,763 200 -1,350 55,000 
Tributaries including Cost 3,946 41,152 161 13,819 
New Hogan Lake and Maint. 
Farmington Dam, Approp. 296,786 352,800 307,045 408,400 
Calif. Cost 279,992 324,905 349,783 392,073 
(Federal Funds) 
(Contributed Funds, New Work 
Other) Contrib. - - 10,000 390,000 
Cost - - 9,529 9,117 
8. Chester, Calif. New Work 
(Federal Funds) Approp. 50,000 65,000 75,000 900,000 
Cost 37,929 56,220 68,692 133,863 
(Contributed Funds) New Work 
Other) Contrib. - - - 87,000 
Cost - - - 
9. Fairfield Vicinity New Work 
Streams, Calif. Approp. - 60,000 113,000 277,000 
Cost - 7,498 160,197 228,268 
10. j Gleason Creek Dam, New Work 
Nev. Approp. - - 55,000 120,000 
Cost - - 22,976 51,391 
11. Hidden Dam-Hensley New Work 
Lake, Fresno Approp. 2,562,300 6,200,000 8,880,000 2,450,000 
River, Calif. Cost 1,977,429 5,723,464 8,044,265 3,900,503 
(Federal Funds) 
(Contributed Funds, New Work 
Other) Contrib. - - - 167,000 
Cost - - - 
12. Humboldt River and New Work 
Tributaries, Nev. Approp. - 100,000 - 265,000 
Cost - - 23,049 177,426 
13. Isabella Lake, Kern New Work 
River, Calif. Approp. 22,648 421,794 63,461 50,000 
(Federal Funds) Cost 3,633 71,064 423,882 37,363 
Maint. 
Approp. 496,838 650,300 546,765 584,000 
Cost 482,240 576,808 583,265 621,461 
(Contributed Funds, New Work 
Other)'9 Contrib. - - 10,000 428,000 
Cost - - 3,005 29,147 
40,331,192' 
40,331,1922 
22,789,031P 
22,755,1164 
4,672,8005 
4,514,3376 
5,833,117~ 
5,833.117 
7.089,076 
7,088.111X 
20,009,597 
19,360,483 
118,0009 
107,2859 
23,345,893 � 
23,304,713" 
2,958,419 
2,933,498 
1,271,05612" 1 
889,702'4 
1,090,000 
296,705 
87,000'5 
450,000 
395,963 
178,810 
78,178 
22,268,752 
21,607,583 
167,000'" 
434,948 
268,389 
23,649,65817 
23,623,551's 
5,650,808 
5,628,548 
438,000 
32,152 
i
I
I
I
I
I
I
I
I
I
1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975. 
TABLE 35-A (Con't) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
14. Kaweah and Tule 
Rivers including 
Terminus Dam and 
Success Lake, Calif. 
15. Lake Camanche 
Calif. 
16. Lake Oroville, 
Calif. 
17. Lakeport Lake, 
Scotts Creek Calif. 
18. Little Dell Lake, 
Utah 
19. Lower San Joaquin 
River and 
Tributaries, 
including Tuolumne 
and Stanislaus 
Rivers, Calif. 
(Federal Funds) 
(Contributed Funds, 
Other)24 
20. Martis Creek Lake, 
Martis Creek, Nev., 
and Calif. 
21. Merced County Stream New Work 
Group, Calif. Approp. - 
Cost - 
Maint. 
Approp. 34,177 
Cost 34,227 
22. Merced County New Work 
Streams, Calif. Approp. - 
Cost - 
23. Merced River, Calif. New Work 
Approp. 96,100 
Cost 139,024 
24. Mormon Slough, New Work 
Calaveras River, Approp. - 
Calif. (Federal Cost 108 
Funds) 
Contributed Funds New Work 
Other) Contrib. - 
Cost 
25. Pine Flat Lake and New Work 
Kings River, Calif. Approp. - 
(Federal Funds) Cost 57,783 
Maint. 
Approp. 333,400 
Cost 322,882 
(Contributed Funds, New Work 
Other)29 Contrib. - 
Cost 
26. Sacramento River and New Work 
Tributaries, Calif. Approp. 3,529,000 
from Collinsville to Cost 3,476,141 
Shasta Dam Maint. 
(Federal Funds) Approp. 261,500 
Cost 248,173 
Total Cost to 
Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
New Work 
Approp. -80,185 
Cost 20,890 
Maint. 
Approp. 420,200 
Cost 404,723 
New Work 
Approp. 
Cost 10,690 
New Work 
Approp. -29,000 
Cost 3,503 
New Work 
Approp. 496,500 
Cost 353,820 
New Work 
Approp. 397,900 
Cost 299,942 
New Work 
Approp. 1,713,100 
Cost 1,597,358 
New Work 
Contrib. 63,000 
Cost 150,907 
New Work 
Approp. 2,912,900 
Cost 2,892,976 
Maint. 
Approp. - 
Cost - 
-1,711 44,000 34,502,33020 
141 13,897 34,472,22721 
515,090 604,000 
550,439 605,009 
- 37,550 
- 2,424 
-51,000 -725,108 
567 - 
117,500 74,003 
197,968 271,686 
477,000 430,000 
471,947 364,330 
-83,100 
-5,394 
10,250 
523,200 
494,375 
11,496 
-73,225 
1,538 
510,000 
659,581 
280,000 
346,230 
-10,600 
72,874 
95,000 
113,091 
365,000 
549,241 
63,800 
44,464 
39,000 
38,123 
72,500 
110,593 
345,000 
301,287 
10,600 
43,326 
441,400 
390,483 
4,482,500 
2,542,643 
307,400 
306,987 
3,961 
78,600 
79,783 
37,000 40,000 
38,594 34,003 
150,000 180,000 
85,800 231,632 
1,000 187,558 
1,000 187,645 
50,000 -100,000 
107 - 
- 100,000 
48,978 63,789 
368,665 431,300 
419,274 432,148 
1,703,148 1,511,789 
3,339,447 1,715,699 
316,035 356,000 
319,693 352,714 
4,533,726 
4,522,485 
10,182,550 
10,144,145 
68,676,667 
68,654,455 
2,343,00322 
2,288,63122 
2,009,900 
1,681,064 
27,835,26323 
27,834,43423 
3,043,948 
3,004,946 
8,500,873 
8,500,739 
200,400 
196,376 
2,751,25925 
2,751,25925 
446,806 
446,726 
330,000 
317,433 
10,917,958 
10,917,957 
2,835,402 
2,831,526 
634,217 
634,217 
41,534,63926 28 
41,473,40527 "X 
5,009,185 
4,992,858 
50,000 
38,843 
54,280,12430 31 
53,604,11230 32 
2,666,284 
2,651,658 
35-26 
3,473 
93,619 
58,000 
72,129

SACRAMENTO, CALIF., DISTRICT 
TABLE 35-A (Con't) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
(Required Contributed New Work 
Funds) Contrib. 385,000 1,708,504 1,410,000 300,000 8,782,538 
Cost 472,243 1,339,432 1,568,713 489,511 8,434,297 
(Contributed Funds, New Work 
Other)n Contrib. 3,000 - - 15,000 2,439,82834 3 4 
Cost 1,490 - - - 2,419,89134 
27. Walnut Creek Calif: New Work 
(Federal Funds) Approp. 1,247,700 1,389,030 -700,000 132,500 17,289,730 
Cost 924,171 261,073 496,444 131,120 17,011,760 
(Required Contributed New Work 
Funds)" Contrib. - 661,146 - - 1,995,916 
Cost 73,476 35,305 587,804 12,250 1,923,816 
(Contributed Funds, New Work 
Other)s 7 Contrib. 59,000 -36,475 - - 501,215 
Cost 132,586 - - - 501,215 
32. Marysville Lake, New Work 
Calif. Approp. 10,337 755,400 - 940,000 4,349,936 
Cost 187,479 215,182 375,094 631,595 3,833,027 
33. Lower San Joaquin New Work 
River and Approp. 21,134,500 22,050,000 17,050,000 15,905,000 98,417,304 * 
Tributaries, Calif. Cost 13,018,327 12,652,885 16,433,229 32,696,182 96,978,447 . 
including Tuolumne 
and Stanislaus 
Rivers, Calif., New 
Melones Lake, Calif." 
35-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 35-A (Con't) COST AND FINANCIAL STATEMENT 
1. Includes the following funds for new work: Regular 
funds: Previous project, $185,198; existing project, $585,436 
for shallow-draft and $39,560,558 for deep-draft. 
2. Includes the following costs for new work: Regular 
funds: Previous project, $185,198; existing project, $585,436 
for shallow-draft and $39,560,558 for deep-draft. 
3. Includes the following amounts for maintenance: 
Regular funds: Previous project, $553,720; existing project 
$14,422,397 for shallow-draft and $7,742,914 for deep-draft; 
and deferred maintenance funds, $70,000 for shallow-draft. 
4. Includes the following amounts for maintenance: 
Regular funds: Previous project, $553,720; existing project, 
$14,370,055 for shallow-draft and $7,761,341 for deep-draft; 
and deferred maintenance funds, $70,000 for shallow-draft. 
5. Includes $1,313,800 for Sacramento District and 
$3,359,000 for San Francisco District. 
6. Includes $1,260,879 for Sacramento District and 
$3,253,458 for San Francisco District. 
7. Includes $1,158,348 public work funds, of which 
$207,198 was for work done along 30-foot channel in Suisun 
Bay Channel; excludes $19,000 expended for engineering 
for inactive portion of 1950 modification. In addition, 
$1,342,500 was expended from required contributed funds. 
8. In addition, $1,250 was expended from required 
contributed funds. 
9. Contributed funds, other, from State of California for 
design and construction of downstream channel 
improvements on Ash and Berenda Sloughs below 
Buchanan Dam. 
10. Includes Code 710 funds for recreation facilities at 
New Hogan Lake: -$24,763, $200, -$589, and $55,000 for 
fiscal years 1972, 1973, 1974, and 1975, respectively. Total 
to date $520,492. 
11. Includes Code 710 costs for recreation facilities at 
New Hogan Lake: $758, $111, and $13,819 for fiscal years 
1972, 1973, and 1975, respectively. Total to date $479.311. 
12. For miscellaneous construction under local 
cooperation requirements, primarily Bear Creek, San 
Joaquin County; includes $108,056 as related to Duck and 
Littlejohn Creeks channel improvements as part of 
Farmington Dam project unit. 
13. Includes $390,000 contributed funds from California 
Department of Navigation and Ocean Development for 
design and construction of boat launching and related 
facilities at North Shore recreation area at New Hogan 
Lake. 
14. Includes $18,646 costs for design and constructibn of 
boat launching and related facilities at North Shore 
recreation area at New Hogan Lake. 
15. Contributed funds, other, from State of California, 
for design and construction of two low water crossings and 
appurtenances at Chester. 
16. Includes $167,000, contributed funds, other, from 
State of California for miscellaneous design and 
construction at Hidden Dam. 
17. Includes total Code 710 funds for recreation facilities 
at Isabella Lake: $22,648, $421,794, $63,641, and $50,000 for 
fiscal years 1972, 1973, 1974, and 1975, respectively. Total 
to date $1,622,205. 
18. Includes total Code 710 costs for recreation facilities 
at Isabella Lake: $3,633, $71,064, $423,882, and $37,363 for 
fiscal years 1972, 1973, 1974, and 1975, respectively. Total 
to date $1,596,098. 
19. Funds from California Department of Navigation 
and Ocean Development for design and construction of boat 
launching and related facilities at Old Isabella Road and 
Isabella Peninsula. 
20. Includes Code 710 funds for recreation facilities: 
Success Lake: -$37,208, -$3,894, and $10,000 for fiscal 
years 1972, 1973, and 1975, respectively. Total to date 
$677,898. Terminus Dam: -$50,977 and $34,000 for fiscal 
years 1972 and 1975, respectively. Total to date $274,254. 
21. Includes Code 710 costs for recreation facilities: 
Success Lake: $11,393, $6,107, and $5,091 for fiscal years 
1972, 1973, and 1975, respectively. Total to date $672,989. 
Terminus Dam: $7,062 and $8,806 for fiscal years 1972 and 
1975, respectively. Total to date $249,060. 
22. Includes $298,500 for advance acquisition of land 
under authority of Public Law 91-439. 
23. Excludes funds applicable to one unit of this basin 
authorization, which is Improvement No. 33, New Melones 
Lake, Calif. reported under Multiple-Purpose including 
Power. 
24. Contributed funds for miscellaneous engineering and 
construction (non-project) at expense of local interests under 
local cooperation requirements in connection with 
acquisition of rights-of-way for levee and channel 
improvements on Lower San Joaquin River and tributaries. 
25. In addition, $66,532 expended for new work from 
contributed funds, other, for miscellaneous construction 
under local cooperation requirements as related to 
acquisition of rights-of-way and utility alterations for 
project. 
26. Includes Code 710 funds for recreation facilities at 
Pine Flat Lake. Total to date $500,100. 
27. Includes Code 710 costs for recreation facilities at 
Pine Flat Lake. Total to date $500,100. 
28. Includes Public Works Acceleration, Executive (PL 
87-658) (Transfer to Corps of Engineers, Civil) 1963 funds 
for recreation facilities: Total appropriations $239,235 and 
total costs $239,235; and fiscal year 1975 special use funds 
$19,700. 
29. Miscellaneous construction and engineering and 
design services (non-project) accomplished at expense of 
State of California under local cooperation requirements in 
connection with acquisition of rights-of-way and utility 
alterations. 
30. Excludes $614,608 for Table Mountain (Iron Canyon) 
Project which is inactive and $531,000 for Sacramento 
River and major and minor tributaries portions which are 
considered inactive and deferred. 
31. Includes Code 710 funds for recreation facilities at 
Black Butte Lake: $30,000, -$6,000,,$3,148, and $10,289 for 
fiscal years 1972, 1973, 1974, and 1975, respectively. Total 
to date $69,162. 
32. Includes Code 710 costs for recreation facilities at 
Black Butte Lake: $3,324, $2,999, $19,885 and $166 for 
fiscal years 1972, 1973, 1974, and 1975, respectively. Total 
to date $54,328. 
33. Miscellaneous construction and engineering and 
design services (non-project) accomplished at expense of 
State of California under local cooperation requirements in 
connection with acquisition of rights-of-way and utility 
alterations (primarily for Sacramento River and major and 
minor tributaries project). 
34. Includes State Highway Commission payment, 
$789,008, for use of excess excavation from Chico and Mud 
Creeks and Sandy Gulch (Sacramento River and major and 
minor tributaries) for freeway embankment through city of 
Chico. 
35. Includes $15,000, contributed funds, other, from 
State of California for required modification of existing 
private facilities on Unit 3, Sacramento River, Chico 
Landing to Red Bluff. 
36. For land enhancement benefits provided by project. 
37. Miscellaneous construction and engineering and 
design services to be accomplished at expense of local 
interests under local cooperation requirements in 
connection with acquisition of rights-of-way and utility 
alterations. 
38. Excludes funds applicable to other units of this basin 
authorization (Lower San Joaquin River and tributaries and 
Tuolumne River Basin, Calif., which is Improvement No. 
19, reported under Flood Control). 
39. Includes $110,000 utilized for preparation of 1957 
Economic Feasibility Report and of Revised Feasibility 
Report (FY 1960, 1961, and 1962) applicable to 1962 
reauthorization of project. 
35-28

TABLE 35-B 
SACRAMENTO, CALIF., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
July 25, 1912 
Jan. 21, 1927 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
July 24, 1946 
Dec. 22, 1944 
May 17, 1950 
July 3, 1958 
July 3, 1958 
July 14, 1960 
May 12, 1967 
March 7, 1974 
SACRAMENTO RIVER, CALIF. (See Section 1 of Text) 
A depth of 7 feet below Sacramento. 
For work above Sacramento. 
The 10-foot channel up to Sacramento. 
A depth of 6 feet between Sacramento and Colusa and 5 feet 
between Colusa and Chico Landing, at a cost of $390,000 
provided flow of rivers is increased to minimum flow of 5,000 
cubic feet per second after Shasta Reservoir is built. 
Authority for a special direct participation of Federal 
Government of $12 million in cost of Shasta Reservoir. 
Transfer of authority for expenditure of above $12 million 
from Secretary of War to Secretary of the Interior. 
Modified existing navigation project for Sacramento River, 
Calif., to provide for construction of a ship channel 30 
feet deep and 200 to 300 feet wide from deep water in Suisun 
Bay to Washington Lake, including such works as may be 
necessary to compensate for or alleviate any detrimental 
salinity conditions resulting from ship channel; a triangular 
basin of equal depth, 2,400 by 2,000 by 3,400 feet at 
Washington Lake; and connecting channel 13 feet deep and 
120 feet wide, with lock and drawbridge, thence to 
Sacramento River. 
SACRAMENTO RIVER AND TRIBUTARIES, CALIF., 
FROM COLLINSVILLE TO SHASTA DAM (See 
Section 26 of Text) 
Modify Sacramento River Flood Control Project to provide for 
extensions in levees and other structures along Sacramento 
River and major and minor tributaries; construct Black Butte 
Dam and Reservoir; construct low-level Table Mountain Dam 
and Reservoir with power facilities; and provision of 
monetary authorization of $15 million for initiation of 
modification. 
Improvement for protection of Upper Butte Basin (included 
full monetary authorization). 
Extend existing Sacramento River Flood Control Project to 
Keswick Dam for purposes of zoning area below dam and 
modification of project by construction of bank protection 
and incidental channel improvements between Chico Landing 
and Red Bluff (included full monetary authorization). 
Additional authorization of $17 million for comprehensive plan 
approved in Act of December 22, 1944. 
Further modification of Sacramento River Flood Control 
Project by construction of initial 10-year phase of 
bank erosion control works and setback levees on 
Sacramento River and authorization of $14,240,000 for 
prosecution of modification. 
Additional authorization of $7 million for bank protection 
approved in Act of July 14, 1960. 
Initiation of construction of second phase of bank erosion 
control works and setback levees on Sacramento River as 
approved in Act of July 14, 1960, and additional 
authorization of $16 million for such purpose. 3 
H. Doc. 186, 55th Cong., 2d 
sess., and 48, 55th Cong., 
3d sess. (Annual Report 
1898, p. 2844 and 1899, 
p. 3171). 
H. Doc. 76, 62d Cong., 
1st sess.i 
H. Doc. 123, 69th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 35, 73d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 35, 73d Cong., 2d sess. 
S.Doc. 142, 79th Cong., 
2d sess. 
H. Doc. 649, 78th Cong., 
2d sess.2 
H. Doc. 367, 81st Cong., 
1st sess.2 
H. Doc. 272, 84th Cong., 
2d sess. 2 
S. Doc. 103, 80th Cong., 
2d sess. 2 
PL 90-17 
PL 93-251 
1. Contains latest published map of section above 
Sacramento. For map of section below Sacramento, see H. 
Doc. 1123, 60th Cong., 2d sess. and S. Doc. 142, 79th Cong., 
2d sess. 
2. Contains latest published map. 
3. Total monetary authorization available, exclusive of 
preauthorization studies from general investigations 
appropriations, amounts to $72,740,000. 
35-29

TABLE 35-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
SACRAMENTO RIVER, CALIF.: 
TIDAL AND FLOOD CONDITIONS PREVAILING 
(See Section 1 of Text) 
Miles from Range in Feet 
Place Mouth of Mean Extreme Ordinary Extreme 
River Tidal' Tidal2 Flood s Flood 4 
Collinsville 0 4.3 7 8 10 
Sacramento 59 2.02 3 20 28 
Verona (Mouth of Feather River) 80 - Trace 22 30 
Colusa 144 - - 26 32 
Chico Landing 193 - - 20 25 
Red Bluff 248 - - 24 30 
1. Mean lower low water to mean higher high water. 3. Mean lower low water to flood stage. 
2. Tide at low water season only. 4. Extreme low water to indicated flood condition. 
TABLE 35-D SACRAMENTO RIVER, CALIF.: 
MAJOR ITEMS OF WORK INCLUDED IN MAINTENANCE 
(See Section 1 of Text) 
Item Fiscal Year Costs 
Shallow Draft Channel: 
Removed snags, Sacramento River, Sacramento upstream to 
Colusa, by hired labor $105,740 
Condition and operation studies by hired labor 58,322 
Deep Water Ship Channel: 
Maintenance and operation locks and gates, hired 
labor 53,572 
Maintenance and operation service facilities, 
hired labor 31,565 
Dredging Sacramento River, vicinity Rio Vista bridge 
upstream to junction point, by contract suction 
dredge 439,531 
TABLE 35-E SAN JOAQUIN RIVER, CALIF.: 
TOTAL COST OF NEW WORK FOR PROJECTi 
(See Section 3 of Text) 
Federal Non-Federal2 
Corps of Coast Required Lands and 
Engineers Guard Cash Damages (includ- Total 
Modification (Construction) (Construction) Contribution ing Relocations) Total Project 
Prior to 1950 Modification $4,009,938 $80,000 $1,307,500 $1,042,000 $2,349,500 $6,439,438 
1950 Modification 1,823,179 - 35,000 135,000 170,000 - 1,993,179 
Total $5,833,117 $80,000 $1,342,500 $1,177,000 $2,519,500 $8,432,617 
1. Completed in May 1960. 
2. Excludes $5,865,000 (Feb. 1954) local interests costs 
for Stockton Deep Water Channel terminal facilities 
required under terms of project authorization. 
35-30

SACRAMENTO, CALIF.,. DISTRICT 
TABLE 35-F SAN JOAQUIN RIVER, CALIF. 
PROJECT UNITS (1950 MODIFICATION)RECLASSIFIED AND EXCLUDED 
FROM PROJECT COST 
(See Section 3 of Text)
Non-Federal 
Federal Required Lands and 
Corps of Cash Damages (includ- Total 
Unit Engineers Contribution ing Relocations) Total Project 
Settling Basin above head of Burns 
Cutoff' $1,073,000 $ 30,000 $ 200,000 $ 230,000 $1;303,000 
Burns Cutoff improvement; new 
turning basin; dredging Mormon 
Channel2 7,882,0003 431,000 1,455,000 1,886,000 9,768,000 
Upper Stockton Channel enlargement4 535,000 34,000 15,000 49,000 584,000 
1. Inactive; July 1959 price index. 4. Deleted by 1965 River and Harbor Act authorization 
2. Deferred; July 1960 price index. of San Fyargcisco Bay to Stockton Channel, Sacramento 
3. For lands and construction. District Improvement No. 2. 
TABLE 35-G OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Feather .River. Calif.' 1951 - 5,7522 
Middle River and Connecting 
Channels, Calif. ' 1974 8,354 93,494 
Mokelumne River, Calif.; 1974 8,500 189.152 
Navajo Reservoir, New Mex.; 6 7 - 2,132 
Old River, Calif.' 1970 " 23,185 631,128 
Stockton and Mormon Channels, 
Calif.' x 1970 253,151 218,854 
Suisun Bay Channel, 
Calif.' 9 10 11 1974 200,928 3.316,62211 117 
Suisun Channel, Calif.' 1973 217,677 733.489' 10 
Suisun Point Channel, Calif.; 17 1965 191,728 
1. Maintenance project, channels adequate for 
commerce. 
2. Includes $10 for maintenance for previous project. 
Excludes $6,160 for previous project and $3,840 for existing 
project for maintenance expended from contributed funds. 
3. Completed. 
4. Includes $1,600 for previous project. 
5. Includes $790 for previous project. 
6. Authorized by Chief of Engineers under authority of 
sec. 107, Public Law 86-645, as amended. 
7. All costs transferred from Los Angeles District in 
fiscal year 1968. 
8. Upon completion of Mormon Slough, Calaveras 
River. Calif. in February 1970, local interests accepted 
maintenance resplonsibility for Mormon Slough as well as 
for Stockton and Mormon Channels, Calif., and Federal 
maintenance was discontinued. No Federal maintenance 
costs have been incurred since fiscal year 1969. 
9. Includes $58,901 for previous projects. 
10. Excludes $59,551 expended from required 
contril)uted funds for previous project. 
11. Excludes work accomplished under existing project 
at a cost of $207,198 from Public Works Administration 
funds allotted to San Joaquin River, Calif. 
12. Includes $59,817 for previous projects. Excludes 
$5,449 expended from required contributed funds for 
previous project. 
13. Maintenance responsibility transferred to San 
Francisco District, January 1, 1974. 
14. Excludes $307,060 funds for San.Francisco District 
(includes reconnaissance and condition surveys: FY 1975. 
$1. 310). 
15. Excludes $317,532 costs for San Francisco District 
(includes reconnaissance and condition surveys: FY 1975, 
$1,310). 
16. Includes reconnaissance and condition surveys as 
follows: FY 1963, $5,496: FY 1964, $483. 
17. Authorized by Chief of Engineers, under authority of 
sec. 107, Public Law 86-(i45, as amended. Estimated cost 
(July 1964) to local interests was $12,000 for lands, 
damages, and spoil retention dikes. 
35-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 35-H MERCED COUNTY STREAM GROUP, CALIF.: 
MAXIMUM INFLOW, STORAGE, AND OUTFLOW FOR PROJECTS 
(See Section 21 of Text) 
Maximum 
Inflow Maximum Maximum 
(c.f.s.) Storage Outflow 
Stream (bi-hourly) (acre-feet) (c.f.s.) 
Burns 2,100 640 1,400 
Bear 2,300 1,330 1,340 
Owens 1,030 730 130 
Mariposa 2,900 3,230 770 
TABLE 35-I SACRAMENTO RIVER AND TRIBUTARIES, CALIF., 
COLLINSVILLE TO SHASTA DAM: 
PROJECT UNITS RECLASSIFIED AND EXCLUDED FROM COST ESTIMATE 
(See Section 26 of Text) 
Current Estimated Cost 
Unit Classification Federal Non-Federal1 Total 
1944 Modification: 
Antelope Creek2 Inactive $1,400,000 $ 340,000 1,740,000 
Lower Butte Basin3 Deferred 7,286,000 2,285,000 9,571,000 
Thomes Creek2 Deferred 1,140,000 140,000 1,280,000 
Willow Creek2 Inactive 1,290,000 120,000 1,410,000 
Bypass Levees4 Deferred 7,100,000 940,000 8,040,000 
Bypass Levees4 Inactive 3,010,000 - 3,010,000 
1950 Modification: 
Upper Butte Basin 2 Deferred 3,530,000 1,787,000 5,317,000 
1. For lands and damages, including relocations. 
2. July 1960 price level. 
3. Excludes work applicable to extension of Moulton 
weir (July 1954 price level). 
4. July 1961 price level. 
85-32

SACRAMENTO, CALIF., DISTRICT 
TABLE 35-J SACRAMENTO RIVER AND TRIBUTARIES, CALIF., 
FROM COLLINSVILLE TO SHASTA DAM 
CONSTRUCTION ACCOMPLISHED AND CONTRACT COSTS 
(See Section 26 of Text) 
Required 
Contributed 
(Bank Protection 
Contract Federal and Relocations) Total 
Miscellaneous minor contract and hired labor 
in connection with levee construction $ 63,961 $ 14,985 $ 78,946 
Contract No. 23 completion (Bank protection 
selected sites, Sacramento River, miles 
16.0-55.0) 13,995 7,820 21,815 
Contract No. 24 completion (Bank protection, 
selected sites, Sacramento River, miles 
60.0-111.0) 333,977 169,096 503,073 
Contract No. 25 completion (Bank protection, 
selected sites, Sacramento River, 
Steamboat, Miner, Sutter and Georgiana 
Sloughs including recreation facilities 
at mile 9.3, Georgiana Slough) 355,426 108,520 463,946 
Contract No. 26 completion (Bank protection, 
selected sites, Sacramento River, miles 
60.0-144.0 including recreation facilities 
at mile 98.3) 192,883 113,948 306,831 
35-33

REPORT OF THECHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 35-K OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 30 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation andl 
Project Report For Construction Maintenance 
American River, Calif.' 
Aquatic Plant Control,Calif.' 
Big Dry Creek Dam and diversion, Calif.' 
Big Wash, Milford, Beaver County, Utah' ' 
Burch Creek, Weber County, Utah; 
Cottonwood Creek, Calif. 
Duck Creek, San Joaquin County, Calif.' : 
Folsom Lake, American River, Calif.7 
Green Valley Creek, Solano County, Calif.' 
Kays Creek, Utah' : 
Little Valley Wash. Magna, Utah'" 
Middle Creek, Calif.' " 
New Bullards Bar, Calif. 
North Fork, Pit River at Alturas, Calif. 
Reese River, Battle Mountain, Nev.' 3 
Salt Lake City, Jordan River, Utah' 
Sevier River near Redmond, Utah' 
Spanish Fork River, Utah'* 
Truckee River and tributaries, Calif. and Nev. 
Weber River and tributaries, Utah 
1. Completed. 
2. Excludes $54,919 other contributed funds for 
miscellaneous construction for local interests pursuant to 
requirements of local cooperation. Total costs for all 
requirements of local cooperation were $951,000 (1959), for 
lands and relocations. 
3. Authorized by Chief of Engineers under authority of 
sec. 205, Public Law 80-858, as amended. 
4. Excludes $44,008 other contributed funds for 
construction in connection with bridge construction 
pursuant to requirements of local cooperation. Total cost to 
local interests for all requirements of local cooperation was 
$370,000 (1959) for lands and relocations. 
5. Excludes $22,000 for preauthorization studies. 
6. Excludes $50,000 for preauthorization studies. 
Estimated costs to local interests were $665,000 for lands 
and damages including relocations. 
7. Completed except for minor real estate costs. 
Transferred to Bureau of Reclamation in May 1956 for 
operation and maintenance by that agency in conjunction 
with other units of Central Valley project. 
8. Excludes $20,000 for preauthorization studies. 
9. Includes $30,000 for preauthorization studies. 
Estimated costs (fiscal year 1973) to local interests for all 
II). lnacll Iti ;tilutle t .1 
11. Estimated costs (fiscal year 1967) to local interests 
for all requirements of local cooperation were $1,340,000 for 
lands andt damages including relocations. 
12. Constructed by Yuba County Water Agency. Federal 
contril)ution of $12,759,127 for flood control reservation. 
13. Includes $41,800 for preauthorization studies. 
14. Excludes $146,000 other contributed funds for 
miscellaneous construction and engineering and design 
services under local cooperation requirements in connection 
with acquisition of rights-of-way, relocations, and utility 
alterations. 
15. Includes $19,000 for preauthorization studies. 
16. Estimated costs to local interests for all requirements 
of local cooperation were $463,000 (July 1962) for lands and 
damages including relocations. 
17. Excludes $48,000 required contributed funds toward 
first cost. Costs to local interests for all requirements of 
local cooperation, including required contributions, were 
$118,000 (1951). 
35-34
1959 
1967 
1955 
1961 
1964 
1971 
1967 
1957 
1963 
1973 
1951 
1967 
1972 
1974 
1969 
1961 
1952 
1955 
1968 
197- 1 
$ 2,125,8182 
1,000 
1,369,931' 
217,879 
26,049 
664,825' 
63,014,810 
136,026" 
407,989 
2,643.499 
12,890,625'' 
904,278 
133,3399 
1,227,570'" 
919,000'" 
20,000 
1.028.960 
75.12)

SACRAMENTO, CALIF., DISTRICT 
SURVEYS 
(See Section 34 of Text) 
TABLE 35-L 
Fiscal year costs were as follows: 
Navigation studies $112,163 
Flood control studies 655,164 
Coordination with Soil Conservation Service 3,300 
Coordination with Bureau of Reclamation pertaining 
to projects under reclamation program (including 
PL 984) 22,000 
Coordination with other agencies on Truckee, 
Carson, and Walker River Basins 12,000 
Deauthorization Review 5,000 
National Recreation Areas 8,141 
Inventory of Dams 5,664 
$823,432 
TABLE 35-M FLOOD PLAIN INFORMATION STUDIES 
COMPLETED DURING FISCAL YEAR 
(See Section 35 of Text) 
Requesting Federal 
Location Agency Date Completed Cost 
Durango, Animas River and Lightner 
and Junction Creeks, Colo. La Plata County Sep 1974 $43,247 
Enterprise, Churn Creek, Calif. Shasta County Aug 1974 44,574 
Farmington to Centerville, Farmington 
Centerville and Parrish Creeks, Utah Davis County Aug 1974 37,621 
Kelseyville, Big Valley Streams, Calif. Lake County Sep 1974 38,128 
Midvale to Draper, Jordan River and 
Bear, Willow, Dry and Corner 
Canyon Creeks, Utah Salt Lake County Sep 1974 44,436 
Reno, Southwest Foothill Streams, Nev. Reno, Sparks and Aug 1974 35,000 
Washoe County 
Stockton SE, Duck, Littlejohn and Lone 
Tree Creeks, Calif. San Joaquin County Jan 1975 47,392 
Truckee, Truckee River and Martis 
Creek, Calif. Placer County Jan 1975 38,229 
35-35

PACIFIC OCEAN, DIVISION* 
This division comprises the State of Hawaii. The 
division also performs such actions pertaining to 
preservation and protection of navigable waters on 
and about the island of Guam and American Samoa 
as provided for under River and Harbor Act of 1899. 
IMPROVEMENTS 
Navigation Page 
1. Ala Wai Small Boat Harbor, Oahu, 
Hawaii .............................. 36-1 
2. Barbers Point Harbor, Oahu, Hawaii .. 36-2 
3. Haleiwa Small Boat Harbor, Oahu, 
Hawaii.............................. 36-2 
4. Honolulu Harbor, Oahu, Hawaii ....... 36-2 
5. Kahului Harbor, Maui, Hawaii ....... 36-3 
6. Kahului Beach Road, Maui, Hawaii .... 36-3 
7. Kawaihae Harbor, Hawaii, Hawaii..... 36-3 
8. Kewalo Harbor, Oahu, Hawaii ....... 36-4 
9. Lahaina Small Boat Harbor, Maui, 
Hawaii ........................... 36-4 
10. Nawiliwili Small Boat Harbor, Kauai, 
Hawaii ........................... 36-4 
11. Ofu Small Boat Harbor, American 
Samoa .............................. 36-5 
12. Tau Small Boat Harbor, American 
Samoa .............................. 36-5 
13. Waianae Small Boat Harbor, Oahu, 
Hawaii.............................. 36-5 
14. Reconnaissance and Condition 
Surveys............................. 36-5 
15. Other Authorized Navigation 
Projects ............................ 36-5 
16. Navigation Work Under Special 
Authorization . . . . .................. 36-5 
Beach Erosion Control Page 
17. Kaaawa Beach, Oahu, Hawaii ......... 36-6 
18. Kaimu Black Sand Beach, Hawaii, 
Hawaii........................... 36-6 
19. Talofofo Bay, Territory of Guam ...... 36-6 
20. Waikiki Beach, Oahu, Hawaii ......... 36-6 
21. Other Authorized Beach Erosion 
Control Projects ................... 36-7 
22. Beach Erosion Control Work Under 
Special Authorization................ 36-7 
Flood Control 
23. Iao Stream, Maui, Hawaii ............ 
24. Kaneohe-Kailua Area, Oahu, Hawaii ... 
25. Namo River, Territory of Guam ....... 
26. Inspection of Completed Flood Control 
Projects ............................ 
27. Other Authorized Flood Control 
Projects .......................... 
28. Flood Control Work Under Special 
Authorization ........................ 
General Investigations 
29. Surveys............................. 
30. Collection and Study of Basic Data .... 
31. Hydrologic Studies ................. 
32. Research and Development ........... 
36-7 
36-7 
36-8 
36-8 
36-8 
36-8 
36-8 
36-8 
36-8 
36-8 
Navigation 
1. ALA WAI SMALL BOAT HARBOR, 
OAHU, HAWAII 
Location. On the southern coast of Oahu in the 
metropolitan area of the city of Honolulu. (See Coast 
and Geodetic Chart No. 4132.) 
Existing project. Project provides for breakwater; 
raise crest elevation from +7 feet to +9 feet 
MLLW. The mean tidal range between mean lower 
low water and mean higher high water is 1.9 feet. 
The usual extreme tidal range is 2.3 feet. The lowest 
tide on record has been minus 1.15 feet and the 
highest tide has been plus 3.1 feet. Approved project 
cost estimate (October 1975) is $418,000 of which 
$209,000 is Federal cost and $209,000 is non-Federal 
cost. (See table 36-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide 
all lands, easements, and rights-of-way for construction 
and subsequent maintenance; provide and 
maintain necessary berthing or mooring facilities 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at 
the end of this chapter. 
36- 1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
and attendant utilities, including a public landing 
with suitable supply facilities open to all on equal 
terms; provide all appropriate onshore structures, 
access roads, parking areas, public restrooms, and 
boat launching ramps as necessary; provide such 
utility, drainage, or other relocations or alterations 
as necessary; and provide a cash contribution estimated 
to be $209,000. 
Terminal facilities. Existing harbor owned by 
the State of Hawaii consists of three basins protected 
by a temporary seaward breakwater and an 
entrance channel 200 feet wide, 20 feet deep, and 
approximately 2,600 feet long. Two 1,500-foot long 
moles partition the basins. The berthing area is approximately 
40 acres and provides about 641 berths. 
Shoreside facilities include parking areas, a fueling 
dock, a boat repair yard, restrooms, and electric 
power and water resources. 
Operations and results during fiscal year. General 
Design Memorandum is 91 percent completed. 
No design work accomplished, pending State of 
Hawaii's approval of project. 
Condition at end of fiscal year. Preconstruction 
planning is approximately 88 percent complete. 
2. BARBERS POINT HARBOR, 
OAHU, HAWAII 
Location. On the west coast of Oahu, about 25 
miles from metropolitan Honolulu. (See Coast and 
Geodetic Charts Nos. 4110 and 4133.) 
Existing project. Deep-draft harbor provides for 
an entrance channel 4,200 feet long, 450 to 650 feet 
wide and 38 to 42 feet deep; an inshore harbor basin 
of about 77 acres and 38 feet deep; and 6,000 linear 
feet of wave absorber structures. Light-draft harbor 
provides for a main access channel 1,200 feet long, 
80-140 feet wide, and 12 feet deep; and wave absorber 
300 feet long. Approved project cost estimate 
(October 1975) for deep-draft harbor is $35,800,000 
of which $32,500,000 (including $100,000 for Coast 
Guard cost) is Federal cost, and $3,300,000 is non- 
Federal cost, including lands and rights-of-way and 
cash contribution. (See table 36-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way for construction and future 
maintenance, provide and maintain mooring 
facilities and utilities open to all on equal terms; 
provide such utility and drainage relocations or alterations 
as necessary; hold the United States free 
from damages; and provide a cash contribution estimated 
to be $694,000 for deep-draft harbor. 
Terminal facilities. Existing privately owned 
barge harbor consists of a concrete marginal wharf, 
250 feet long along south side of the barge basin. An 
offshore tanker facility is connected to the oil refinery 
by pipelines. 
Operations and results during fiscal year. Preconstruction 
planning has been deferred until the 
land issue is settled by the local cooperating agency 
on this project. 
Condition at end of fiscal year. Preconstruction 
planning for deep-draft harbor is 78 percent complete. 
Preconstruction planning for light-draft harbor 
deferred since FY 1970 as requested by the 
State of Hawaii, the local cooperating agency. 
3. HALEIWA SMALL BOAT HARBOR, 
OAHU, HAWAII 
Location. Haleiwa Harbor is on northwest coast 
of the island of Oahu. (See Coast and Geodetic Survey 
Chart No. 4110.) 
Existing project. The project provides for an entrance 
channel 740 feet long, 100 to 120 feet wide, 12 
feet deep; a revetted mole 1,310 feet long; a stub 
breakwater 80 feet long; and a wave absorber 140 
feet long. Project first cost (July 1975) is $525,800 of 
which $278,800 is Federal cost and $247,000 is non- 
Federal cost. Project authority is Section 107 of the 
1960 River and Harbor Act, as amended. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. A construction 
contract was awarded in April 1975 for 
$278,200. 
Condition at end of fiscal year. Construction 
completion is scheduled for November 1975. 
4. HONOLULU HARBOR, 
OAHU, HAWAII 
Location. On the southern coast of island of Oahu, 
Hawaii, in city of Honolulu. (See Coast and Geodetic 
Survey Chart No. 4109.) 
Existing project. Completed portion of project 
comprises three channels 35-40 feet deep, two harbor 
basins 35 feet deep, and a double-leaf-bascule 
bridge. Last full report on this project is on pages 
1828 and 1829 of Annual Report for 1962. Uncompleted 
portion provides deepening seaward 3,600 
feet of Fort Armstrong entrance channel to 45 feet, 
and removing a narrow strip from northeast corner 
of Sand Island; deepening main harbor basin and 
Kapalama Channel to 40 feet; widening Kapalama 
Channel by 60 feet along Sand Island side for 3,100 
feet; and relocating project line to provide a 100-foot 
offset from pierheads in Kapalama Channel and at 
piers 9, 10, and 11, and an offset of 50 to 75 feet 
elsewhere in the harbor. Approved project cost estimate 
(October 1975) for new work is $3,940,000 of 
which $3,840,000 (including $80,000 for Coast Guard 
cost) is Federal cost and $100,000 is non-Federal 
cost. (See table 36-B for Authorizing Legislation.) 
Local cooperation. Fully compiled with on existing 
project. State of Hawaii assures fulfilling their 
requirements of furnishing lands and rights-of-way 
for construction and future maintenance and hold 
36-2

PACIFIC OCEAN, DIVISION 
the United States free from damages. Non-Federal 
cash contribution is $100,000. 
Terminal facilities. There are 34 piers and 2 
marginal wharves, which include 3 piers and 1 marginal 
wharf owned by the Federal Government; 13 
piers and 1 marginal wharf owned by the State of 
Hawaii; and 18 piers State owned. All non-Federal 
piers are open to all on an equal basis, although 
certain ones are reserved for passenger terminals, 
for container ships or for handling specific bulk 
commodities such as petroleum products, pineapple, 
sugar, animal feed, and cement. 
Operations and results during fiscal year. New 
work: Preconstruction planning was held in 
abeyance pending designation of spoil area by the 
State of Hawaii. 
Condition at end of fiscal year. Preconstruction 
planning on modification is 68 percent complete. 
5. KAHULUI HARBOR, MAUI, HAWAII 
Location. On northern coast of island of Maui, at 
town of Kahului. (See Coast and Geodetic Survey 
Chart No. 4124.) 
Existing project. Rubblemound breakwaters on 
east and west sides of harbor, approximately 2,766 
and 2,315 feet long, respectively, and an entrance 
600 feet wide between breakwaters and a harbor 
basin 2,050 feet wide, 2,400 feet long, and 35 feet 
deep. Range of tide between mean lower low water 
and mean higher high water is 2.2 feet and extreme 
tidal range under normal conditions is 4.5 feet. (See 
table 36-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two wharves owned and operated 
by State of Hawaii which are open to shipping 
on equal terms. Pipelines for fuel oil, distillate, 
kerosene, gasoline, molasses, and water are available. 
There is also a bulk-sugar plant of 30,000-ton 
storage capacity with a conveyor loading system 
capable of conveying at a rate of about 750 tons per 
hour. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal 
year. Maintenance: The Kahului breakwater repair 
financially complete. 
Condition at end of fiscal year. In September 
1973, breakwater inspection was made and a recommendation 
for repair work in FY 1976 for the 
east and the west breakwaters at Kahului Harbor 
was submitted. 
6. KAHULUI BEACH ROAD, 
MAUI, HAWAII 
Location. On northern coast of island of Maui. The 
Kahului Beach Road borders the western shore of 
the Kahului Bay. (See Coast and Geodetic Survey 
Chart No. 4124.) 
Existing project. Project is prevention and mitigation 
of shore damages. Project provides for approximately 
890 linear feet of stone revetment along 
Kahului Beach Road; beach replenishment of 6,550 
cubic yards of sand; a 100-foot breakwater, and west 
groin 260 feet and east groin 300 feet. Project first 
cost is $815,000 of which $815,000 is Federal cost. 
Project authority is Section 111 of the River and 
Harbor Act of 1968, Public Law 90-483. 
Local cooperation. None required. 
Operations and results during fiscal year. A construction 
contract was awarded in June 1975 for 
$686,000. 
Condition at end of fiscal year. Construction 
completion is scheduled in April 1976. 
7. KAWAIHAE HARBOR, 
HAWAII, HAWAII 
Location. On northwestern coast of island of 
Hawaii, in town of Kawaihae. (See Coast and Geodetic 
Survey Chart No. 4176.) 
Existing project. Completed portion comprises of 
an entrance channel 3,270 feet long; widens from 500 
feet at the seaward end to 520 feet within a distance 
of 2,100 feet then flaring to the basin width of 1,450 
feet. Entrance channel is 40 feet deep for the seaward 
2,900 feet and transitions to a 35-foot depth at 
the harbor basin end; a harbor basin 1,450 feet wide, 
1,750 feet long on northeast side, 1,050 feet long on 
southwest side and 35 feet deep; and a rubblemound 
breakwater with maximum crest elevation 13 feet 
above mean lower low water and 2,650 feet long. 
Uncompleted portion provides for constructing a 
small boat harbor with west revetted mole extension 
375 feet long and east revetted mole 1,050 feet long; 
an offshore island 650 feet long with an average 
width of 175 feet; an interior mole 850 feet long; wave 
absorber 400 feet long; and an access channel 640 
feet long, 80 feet wide and 8 feet deep. Project 
TUGBOAT undertaken by Nuclear Cratering 
Group as a research experiment of chemical explosive 
excavation was completed in June 1971, which 
provided an entrance channel 850 feet long, 120 feet 
wide and 12 feet deep; a turning basin 200 feet by 200 
feet, 12 feet deep, and a breakwater 850 feet long, 
small boat harbor. Range of tide between mean 
lower low water and mean higher high water is 2.1 
feet, and extreme range under ordinary conditions is 
4.5 feet. Approved project cost (October 1975) for 
small boat harbor is $1,650,000 of which $881,000 
(including $10,000 Coast Guard cost) is Federal cost 
and $759,000 is non-Federal cost. (See table 36-B for 
Authorizing Legislation.) 
Local cooperation. Completed portion fully complied 
with. For small boat harbor, local interests 
must provide all lands, easements and rights-of-way 
for construction and subsequent maintenance; provide 
and maintain necessary berthing and mooring 
areas, installations and utilities, including a public 
36-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
landing with suitable supply facilities; accomplish 
without cost to the United States such utility, drainage, 
and other relocations or alterations as necessary; 
and provide a cash contribution estimated to be 
$759,000. 
Terminal facilities. A 605-foot concrete wharf 
and 12,000-square foot pier shed accommodates 
transpacific commerce; and a 410-foot long, 40-foot 
wide apron, and 3,600-square foot pier shed accommodates 
interisland tugs and barges including livestock. 
Other facilities also open to all on equal basis 
and considered adequate for existing commerce, include 
a 20,000-ton capacity bulk sugar storage building, 
10,000-ton molasses storage tank, petroleum 
tanks of 1.2 million gallon capacity and aqua ammonia 
tanks of three-quarter million gallon capacity. 
Operations and results during fiscal year. New 
work: General Design Memorandum No. 2 for small 
boat harbor is 99 percent complete. 
Condition at end of fiscal year. Preconstruction 
planning for the light draft harbor is approximately 80 
percent complete. A post authorization change has 
been approved by OMB for the relocation of the 
small boat harbor. 
8. KEWALO HARBOR, 
OAHU, HAWAII 
Location. Kewalo Harbor is on the south coast of 
Oahu between downtown Honolulu and Waikiki. 
(See Coast and Geodetic Survey Chart No. 4109,) 
Existing project. The project provides for three 
wave absorbers, one beginning at the seaward end 
and extending shoreward 580 feet along the northwest 
side of the entrance channel, another extending 
along the entire length (1,250 feet) of the southeast 
side of the channel, and the third, 230-foot long absorber 
in the southeast corner of the basin; and a 
jetty to provide support for the seaward 550 feet of 
wave absorber along the southeast side of the entrance 
channel. Project first cost (July 1972) is 
$280,000 of which $169,800 is Federal cost and 
$110,200 is non-Federal cost. Project authority is 
Section 107 of the 1960 River and Harbor Act, as 
amended. 
Local cooperation. Local interests must provide 
all lands and rights-of-way for construction and future 
maintenance of the project and aids to navigation; 
maintain necessary berthing and mooring 
facilities and utilities; provide and maintain all 
appropriate onshore structures, access roadways, 
parking areas, public restrooms and launching 
facilities; and provide a cash contribution of 40.1 
percent of the first cost of construction, estimated to 
be $110,200 before initiation of construction. 
Operations and results during fiscal year. Model 
study conducted by WES indicated that it is possible 
to reduce damages resulting from surge within the 
basin by providing rubble wave absorbers along the 
channel slopes. However, costs to accomplish this 
exceed the benefits that can be anticipated for such 
work. 
Condition at end of fiscal year. Project will be 
recommended for deauthorization because reevaluation 
has indicated that project cannot be economically 
justified. 
9. LAHAINA SMALL BOAT HARBOR, 
MAUI, HAWAII 
Location. On west coast of Maui, approximately 
22 road miles from Wailuku, the Maui county seat. 
(See Coast and Geodetic Survey Chart No. 4130.) 
Existing project. Project provides for two revetted 
moles 350 and 740 feet long; an offshore breakwater 
1,300 feet long; a turning basin and main access 
channel of 130,000 square feet, 12 to 15 feet 
deep; and entrance channel 600 feet long, 150 feet 
wide, 15 to 20 feet deep; and a wave absorber 435 
feet long. Harbor is designed to accommodate 380 
boats. Approved project cost estimate (October 
1975) is $3,550,000 of which $1,730,000 (including 
$20,000 in Coast Guard cost) is Federal cost, and 
$1,820,000 is non-Federal cost, including lands and 
rights-of-way and cash contribution. Plane of reference 
is mean lower low water datum. Tidal range 
between mean lower low water and mean higher 
high water is 2.2 feet, extreme range under normal 
conditions is 4.0 feet. (See table 36-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way for construction and future 
maintenance, provide and maintain mooring 
facilities and utilities open to all on equal terms; 
provide such utility and drainage relocations or alterations 
necessary; hold the United States free 
from damages; and provide a cash contribution estimated 
to be $1,510,000. 
Operations and results during fiscal year. The 
Senate and House Subcommittees on Public Works 
appropriations were notified in August 1975 of withdrawal 
of State and local support for the project as 
formulated. 
Condition at end of fiscal year. Preconstruction 
planning is approximately 80 percent complete. An 
evaluation study of potential alternate sites that 
would be within the scope and intent of project authorization 
will be initiated in FY 1976. 
10. NAWILIWILI SMALL BOAT HARBOR, 
KAUAI, HAWAII 
Location. Nawiiwili Small Boat Harbor is on the 
southeastern coast of the island of Kauai. (See Coast 
and Geodetic Survey Chart No. 4111.) 
Existing project. The project provides for an entrance 
and main access channel 1,035 feet long, 120 
feet wide and 12 feet deep; access channel 690 feet 
36-4

PACIFIC OCEAN, DIVISION 
long, 80 feet wide, 8-10 feet deep; a revetted dike 
1,458 feet long, a stub breakwater 142 feet long, and 
breakwater 453 feet long. Project first cost is 
$993,500 of which $588,000 (including $3,600 in 
Coast Guard cost) is Federal cost and $405,500 is 
non-Federal cost. Project authority is Section 107 of 
River and Harbor Act of 1960, as amended. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. A construction 
contract was completed in November 1974. 
Condition at end of fiscal year. Project work 
completed but financially not completed. 
11. OFU HARBOR, AMERICAN SAMOA 
Location. Ofu Harbor is on the island of Ofu, 
American Samoa, about 2,300 miles southwest of 
Hawaii, 1,236 miles northwest of Tahiti, and 80 miles 
southeast of Western Samoa. (See Coast and Geodetic 
Survey Chart No. 4190, Manu Islands.) 
Existing project. The project provides for a 1,071 
feet long revetment; a 220-foot long entrance channel, 
18 feet deep and 130 feet wide; a 2.54 acre 
turning basin, 16 feet deep and appurtenant aids to 
navigation. Plane of reference is mean sea level. 
Project first cost (July 1975) is $1,045,700 of which 
$980,700 is Federal cost and $65,000 is non-Federal 
cost. Project authority is Section 107 of River and 
Harbor Act of 1960, as amended. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Construction 
of harbor completed in August 1975. 
Condition at end of fiscal year. Construction of 
the harbor is essentially completed but financially 
not completed. 
12. TAU SMALL BOAT HARBOR, 
AMERICAN SAMOA 
Location. Tau Harbor is on the island of Tau, 
American Samoa, about 2,000 miles southwest of 
Hawaii, 1,236 miles northwest of Tahiti, and 80 miles 
southeast of Western Samoa. (See Coast and Geodetic 
Survey Chart No. 4190.) 
Existing project. Project provides for a 520-foot 
long entrance channel, 130 feet wide, 16 to 20 feet 
deep; a turning basin of 85,000 square feet, 16 feet 
deep; a rubble breakwater 290 feet long, 13 feet high; 
revetments with a total length of 975 feet; and a 
200-foot long groin. Project first cost (July 1975) is 
$1,801,000 of which $1,000,000 is Federal cost and 
$801,000 is non-Federal cost. Project authority is 
Section 107 of the 1960 River and Harbor Act, as 
amended. 
Local cooperation. Local interests must assume 
all costs in excess of Federal limitation ($1,000,000). 
Provide cash contribution estimated (May 1974) at 
$801,000 prior to initiation of construction. 
Operations and results during fiscal year. Plans 
and specifications have been completed. 
Condition at end of fiscal year. Project was approved 
for construction in December 1974. Construction 
to be initiated upon availability of local 
funds from the Government of American Samoa. 
13. WAIANAE SMALL BOAT HARBOR, 
OAHU, HAWAII 
Location. On west coast of island of Oahu, approximately 
30 road miles from Honolulu. (See 
Coast and Geodetic Survey Chart No. 4136.) 
Existing project. Authorized under River and 
Harbor Act of October 27, 1965. Project provides for 
an entrance channel 830 feet long, 150 feet wide, and 
15 to 17 feet deep; an access channel 870 feet long, 
100 to 150 feet wide, and 12 to 15 feet deep; a breakwater 
1,350 feet long; and a groin 175 feet long. 
Harbor is designed to accommodate about 380 boats. 
Approved project cost estimate (December 1975) is 
$5,500,000 of which $2,810,000 (including $10,000 for 
Coast Guard cost) is Federal cost and $2,690,000 is 
non-Federal cost, including lands and rights-of-way 
and cash contribution. Plane of reference is mean 
lower low water datum. Tidal range between mean 
lower low water and mean higher high water is 1.8 
feet, extreme range under normal conditions is 4.0 
feet. (See table 36-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way for construction and future 
maintenance, provide and maintain mooring 
facilities and utilities open to all on equal terms; 
provide such utility and drainage relocations or alterations 
as necessary; hold the United States free 
from damages; and provide a cash contribution estimated 
to be $2,580,000. 
Operations and results during fiscal year. Model 
studies by WES initiated. Phase I General Design 
Memorandum approximately 85 percent complete. 
Condition at end of fiscal year. Preconstruction 
planning is 45 percent complete. 
14. RECONNAISSANCE AND 
CONDITION SURVEYS 
See table 36-C. 
15. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See table 36-D. 
16. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities pursuant to Section 107, 
Public Law 86-645 (Preauthorization) 
Preauthorization studies continued on Agana Bay 
Harbor, Guam, $24,527; and Aunuu Harbor, American 
Samoa, $19,153. 
p6-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Beach Erosion Control 
17. KAAAWA BEACH, 
OAHU, HAWAII 
Location. Kaaawa Beach Park is on the northeast 
coast of the island of Oahu, approximately 25 miles 
from Honolulu. (See Coast and Geodetic Survey 
Chart No. 4110.) 
Existing project. The project provides for an initial 
beach fill placement of 9,300 cubic yards of beach 
sand with a berm elevation of 7.5 feet in the north 
sector and 5.5 feet in the south sector. Periodic 
nourishment of the beach on an average of once 
every four years of 2,700 cubic yards. The project 
first cost is $254,500 of which $152,000 is Federal 
cost and $102,500 is non-Federal cost. Project authority 
is Section 103a of River and Harbor Act of 
1962, as amended. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. A construction 
contract was awarded in June 1975 for 
$175,242. 
Condition at end of fiscal year. Construction contract 
completion scheduled in September 1975. 
18. KAIMU BLACK SAND BEACH, 
HAWAII, HAWAII 
Location. Kaimu Beach is on the southeast coast 
of the island of Hawaii. (See Coast and Geodetic 
Survey Chart No. 4115.) 
Existing project. The project provides for beach 
replenishment and construction of a submerged 
offshore breakwater to protect the replenished 
beach. Plan provides for replenishment of 1,520-foot 
reach with black sand. An estimated 48,800 cubic 
yards of sand would be required for the replenishment 
work. Construction of submerged breakwater 
across the width of the bay, 1,350 feet long, 1V on 2H 
side slope, a 15-foot crest width and a 0-foot MLLW 
crest elevation, minimum stone size 6-ton. The project 
first cost (July 1975) is $2,100,000 of which 
$1,000,000 is Federal cost and $1,100,000 is non- 
Federal cost. Project authority is Section 103a of 
River and Harbor Act of 1962, as amended. 
Local cooperation. Local interests must assume 
all costs in excess of Federal limitation ($1,000,000). 
Provide cash contribution estimated at $1,100,000 
prior to initiation of construction; provide lands, 
easements, and rights-of-way; hold the United 
States free from damages; assure that water pollution 
that would affect the health of bathers will not 
be permitted; assure that satisfactory measures are 
taken to reserve an approved source of black sand 
for initial construction and for maintenance of beach 
during the 50-year project life; maintain continued 
public ownership of shore and its administration for 
public use during the economic life of the project, 
and assure continued availability for public use of 
privately owned shores involved in project where 
Federal participation is based on such use. 
Operations and results during fiscal year. Plans 
and specifications approximately 90 percent complete. 
Condition at end of fiscal year. Project was approved 
for construction in March 1974. Planning deferred 
because no construction funds were available. 
19. TALOFOFO BAY, 
TERRITORY OF GUAM 
Location. Talofofo Bay is located on the southeast 
coast of Guam about midway between the southern 
end of the island and Pago Bay at its central waist. 
(See Coast and Geodetic Survey Chart No. 4196.) 
Existing project. Project provides for a 900-foot 
long rock revetment to protect the beach park 
shoreline against erosion by storm waves. The revetment 
will have a crest elevation of 7 feet MLLW 
and side slope of 1V to 2H. Project first cost (July 
1975) is $525,000 of which $288,250 is Federal cost 
and $236,750 is non-Federal cost. Project authority 
is Section 103a of River and Harbor Act of 1962, as 
amended. 
Local cooperation. Provide cash contribution estimated 
at $236,750, or 50 percent of the total construction 
costs of the project. 
Operations and results during fiscal year. Plans 
and specifications are approximately 90 percent 
complete. 
Condition at end of fiscal year. Project was approved 
for construction in January 1975. Section 103 
funds are depleted and project placed on backlog of 
approved projects for future construction. 
20. WAIKIKI BEACH, 
OAHU, HAWAII 
Location. Waikiki Beach is along the eastern end 
of Malama Bay on the south coast of the island of 
Oahu. (See Coast and Geodetic Survey Chart No. 
4132.) 
Existing project. For last full report on the existing 
project, see 1965 report. Project provides for 
restoration and protection of the shore of Waikiki 
Beach from Duke Kahanamoku Beach to the Elks 
Club. The plan consists of artificial placement of 
beach fill on the shore to average widths from 60 to 
200 feet; construction of eight new groins and appurtenant 
drainage facilities; modification of one existing 
groin, and demolition of the Natatorium. Approved 
project cost estimate (July 1974) is 
$3,130,000 of which $1,763,000 is Federal cost and 
$1,367,000 is non-Federal cost in cash contribution. 
Local cooperation. Local interests must obtain 
approval by the Chief of Engineers, prior to commencement 
of work, of detailed plans and specifications 
for the Kuhio segment; provide lands and 
36-6

PACIFIC OCEAN, DIVISION 
rights-of-way for construction and future maintenance; 
maintain continued public ownership or continued 
availability for unobstructed public use of the 
shores upon which the amount of Federal participation 
is based and administration of those shores for 
public use, exclusively for bathing and water-related 
recreation; maintain the project works as may be 
required to serve their intended purpose, except for 
the beach fill on the Fort DeRussy frontage; and 
control water pollution to the extent necessary to 
safeguard the health of bathers; hold the United 
States free from damages; and provide a cash contribution 
estimated to be $1,367,000. 
Terminal facilities. None. 
Operations and results during fiscal year. Available 
Civil Works funds under Waikiki Beach were 
used for a contract to place 2-foot of natural sand at 
the Fort DeRussy sector. Contract was awarded in 
June 1975 for $283,785 and completion scheduled in 
October 1975. 
Condition at end of fiscal year. Construction of 
this project is scheduled on an incremental basis by 
sectors. Construction of Fort DeRussy Beach segment 
was completed ii1 September 1970 utilizing 
military non-appropriated funds. The State of 
Hawaii has completed the construction of the Kuhio 
segment in June 1972. Preconstruction planning on 
Fort DeRussy to Royal Hawaiian sector and the 
Duke Kahanamoku sector has not been initiated. 
The State Legislature has not acted on the 
Natatorium matter and preconstruction planning 
has been deferred since FY 1974 on the Kapahulu 
Storm Drain to Elks Club sector. 
21. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See table 36-E. 
22. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103, Public Law 87-874 (preauthorization). 
Preauthorization studies continued on Afono 
Area, American Samoa, $3,304; Hilo Bay, Hawaii, 
Hawaii, $482; Kapaa Town, Kauai, Hawaii, $13,612; 
Kualoa Regional Park, Oahu, Hawaii, $13,314; Pago 
Pago and Nuuuli, American Samoa, $47,312; Poloa 
Area, American Samoa, $8,773; Swanzy Beach, 
Oahu, Hawaii, $39; Trading Point to Breakers Point, 
American Samoa, $4,911; and Vatia Area, American 
Samoa, $4,877. 
Flood Control 
23. IAO STREAM, MAUI, HAWAII 
Location. Iao Stream on the island of Maul drains 
a portion of the slopes of the west Maui mountains, 
and its lower course runs into the sea just to the east 
of the town of Wailuku, Maui. (See Coast and Geodetic 
Survey Chart No. 4124.) 
Existing project. Project provides for a debris 
basin 2.5 miles upstream of stream mouth, and 
channel improvements with levees and flood plain 
management considerations from debris basin to 
mouth. Debris basin capacity of 80,000 cubic yards; 
channel improvement below the debris basin to be 
trapezoidal in shape with base width of about 100 to 
300 feet and lined with boulder concrete; concrete 
lined side slopes; and downstream near the stream 
mouth to be realigned with a 50 to 100 feet wide 
rectangular concrete lined section with boulder concrete 
invert paving. Approved project cost estimate 
(October 1975) is $9,950,000 of which $9,500,000 is 
Federal cost and $450,000 is non-Federal cost for 
lands and relocations. (See table 36-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must provide 
lands, easements, and rights-of-way; provide without 
cost to the United States all relocations of buildings, 
utilities, bridges and roads, sewers, pipelines, 
and other alterations of existing improvements 
which may be required for construction of the project; 
hold the United States free from damages due to 
construction works; operate and maintain works 
after completion; and prohibit encroachment on improved 
channel. 
Operations and results during fiscal year. 
Phase I general design memorandum was completed 
in April 1975. 
Condition at end of fiscal year. Preconstruction 
planning is approximately 45 percent complete. 
24. KANEOHE-KAILUA AREA, 
OAHU, HAWAII 
Location. Kamooalii-Kaneohe Stream drainage 
basin is on the east coast of the island of Oahu. The 
drainage basin is bounded on west and south by the 
Koolau Mountain Range, on the east by the remnants 
of Kaneohe volcanic cone and on the north by 
Kaneohe Bay. (See Coast and Geodetic Chart No. 
4134 and U.S. Geological Survey quadrangles 
Kaneohe, Hawaii and Honolulu, Hawaii.) 
Existing project. Project provides for a dam and 
reservoir about 3.2 miles above the mouth of 
Kaneohe Stream on the tributary Kamooalii Stream. 
Project consists of an earth-fill dam 80 feet high, 
with a crest length of about 2,300 feet, and about 
1,000 feet of channel improvements, a concrete 
side-channel and chute spillway and reservoir with 
storage of 2,500 acre-feet, of which 500 acre-feet 
would be for sediment reserve and recreation use 
and 2,000 acre-feet for flood control. Approved project 
cost estimate (October 1975) is $22,700,000 of 
which $16,000,000 is Federal cost and $6,700,000 is 
non-Federal cost for lands and damages and relocations. 
Future non-Federal reimbursement is 
36-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
$4,750,000. (See table 36-B for Authorizing Legislation.) 
Local cooperation. Local interests are required 
to furnish all lands, easements, and rights-of-way, 
all necessary construction, modification or relocations 
of buildings, highways (including streets, 
roads, and bridges), and utilities; and prior to start 
of construction, agree to repay one-half of the separate 
first costs for recreation, general, and fish and 
wildlife and to operate and maintain and make major 
replacement of the recreational facilities. 
Operations and results during fiscal year. Phase 
II general design memorandum was approved in. 
April 1975. Preparation of plans and specifications 
was initiated. 
Condition at end of fiscal year. Plans and specifications 
are scheduled for completion in November 
1975 for the first package construction contract. 
Preconstruction planning is approximately 90 percent 
complete. 
25. NAMO RIVER, TERRITORY OF GUAM 
Location. The Agat-Santa Rita River (Namo) is 
on the west coast of the island of Guam, which is 
approximately 3,800 miles west of Honolulu, 
Hawaii, and 1,500 miles south of Tokyo. (See US 
Geodetic Survey Map N1313-W14436.) 
Existing project. Project provides for channel 
improvements for the lower 2,000-foot reach of the 
river, and flood plain management for the area extending 
from upper part of channel improvement to 
the existing Agat-Santa Rita bridge. Channel improvements 
include realignment and enlargement of 
existing river, lining channel with riprap, providing 
a stub outlet channel on the upstream side of Route 2 
bridge, and constructing a levee on north bank of 
unnamed tributary. Project first cost (July 1975) is 
$1,744,000 of which $1,000,000 is Federal cost and 
$744,000 is non-Federal cost. Project authorization 
is Section 205 of the Flood Control Act of 1948, as 
amended. 
Local cooperation. Local interests must assume 
all costs in excess of Federal limitation ($1,000,000). 
Provide cash contribution estimated at $744,000 
prior to initiation of construction. 
Operations and results during fiscal year. Plans 
and specifications have been completed. 
Condition at end of fiscal year. Project was approved 
for construction in January 1975. Federal 
construction funds were revoked because the Government 
of Guam was unable to provide cash contribution 
in FY 1975. 
26. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspections were conducted during October 
through December 1974 at Hanapepe River Flood 
Protection Works, Kauai; lao Stream Snagging and 
Clearing Project, Maui; Kaunakakai Stream Flood 
Protection Works, Molokai; Kawainui Swamp Flood 
Protection Works, Oahu; Kuliouou Stream Flood 
Protection Works, Oahu; and Wailoa Stream Flood 
Protection Project, Hawaii; total cost of $2,921. 
27. OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
See table 36-F. 
28. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization) 
Preauthorization study initiated on Waialua- 
Haleiwa Area, Oahu, $51,298; and studies continued 
on Kapaakea Stream, Molokai, $2,426, and Waimano 
Stream, Oahu, $13,284; and study completed on 
Vaipito Stream, American Samoa, $5,000. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th Congress, 
and antecedent legislation). 
Federal cost for fiscal year was $35,847 of which 
$9,720 was for advance preparation, $10,393 for 
emergency operations and $15,734 for rehabilitation. 
General Investigations 
29. SURVEYS 
Survey cost for fiscal year was $522,585 of which 
$363,157 was for navigation, $22,424 for flood control, 
$115,352 for comprehensive basin studies, 
$17,406 for review of authorized projects and $4, 246 
for coordination studies with other agencies. 
30. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management services costs totaled 
$295,486 of which $33, 860 was for technical services, 
$58,988 was for flood plain management service unit 
and $202,638 for special flood hazard information 
studies. See table 36-G on completed special flood 
hazard information studies.) 
31. HYDROLOGIC STUDIES 
Fiscal year cost was $5,094 for storm studies. 
32. RESEARCH AND DEVELOPMENT 
Fiscal year cost was $99 for plan information and 
evaluation studies. 
36-8

PACIFIC OCEAN, DIVISION 
TABLE 36-A COST AND FINANCIAL STATEMENT 
See 
Section Project Funding FY 72 FY 73 FY 74 FY 75 Total Cost to 
in Text June 30, 1975 
1. Ala Wai Small 
Boat Harbor, 
Oahu, Hawaii 
(Federal Funds) 
2. Barbers Point 
Harbor, Oahu, 
Hawaii 
(Federal Funds) 
3. Haleiwa Small 
Boat Harbor, 
Oahu, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
4. Honolulu Harbor, 
Oahu, Hawaii 
(Federal Funds) 
5. Kahului Harbor, 
Maui, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
6. Kahului Beach 
Road, Maui, 
Hawaii 
(Federal Funds) 
7. Kawaihae Harbor, 
Hawaii, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
8. Kewalo Harbor, 
Oahu, Hawaii 
9. Lahaina Small 
Boat Harbor, 
Maui, Hawaii 
(Federal Funds) 
10. Nawiliwili Small 
Boat Harbor, 
Kauai, Hawaii 
(Contributed 
Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
53,600 
105 
14,652 
8,191 
270 
26,760 
6,622 
6,516 
292,400 
292,400 
47,600 
29,621 
276 
402,000 
618,948 
68,100 
680 
69,000 
58,428 
2,959 
260,000 
283,987 
18 - 
-67,083 
423,588 
-6,300 
61,120 
-_ 
3,068 
-74,000 
2,334 
137 3,903 
21,371 36,769 
36-9 
-10,300 
30,598 
3,000 
16,744 
4,092 
1,223 
218,000 
59,270 
218,000 
78,829 
4,740 
-55 2,214 
43,300 
40,117 
268,000 
268,000 
278,800 
118,734 
275,800 
78,829 
8,559,874 
8,559,677 
1,370,171 
1,370,171 
2,388,693 
2,388,693 
3,199,161 
3,199,161 
2,110,528 
2,110,528 
30,200 
30,200 
500,000 
23,171 
5,972,501 
5,972,501 
61,800 
61,800 
62,102 
62,102 
98,800 
92,715 
170,385 
80,994 
584,513 
578,273 
413,578 
406,704 
500,000 
23,171 
10,496 10,496 
21,644 
100,000 
10,703 
32,398 
60,078 
82,176 
-3,800 
8,961 
-6,898 
606 
2,000 
46,216 
-5,000 
729 
352,800 
457,878 
353,500 
324,528

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 36-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
11. Ofu Harbor, 
American Samoa 
(Federal Funds) 
(Contributed 
Funds) 
12. Tau Small Boat 
Harbor, American 
Samoa 
(Federal Funds) 
13. . Waianae Small 
Boat Harbor, 
Oahu, Hawaii 
(Federal Funds) 
17. Kaaawa Beach, 
Oahu, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
20. Waikiki Beach, 
Oahu, Hawaii 
(Federal Funds) 
(Contributed 
Funds) 
23. Iao Stream, 
Maui, Hawaii 
(Federal Funds) 
24. Kaneohe-Kailua 
Area, Oahu, 
Hawaii 
(Federal Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Adv Funds 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
62,284 
59,284 
__ 
-_ 
11,000 
8,898 
299,300 
38,184 
158,900 
88,528 
916,000 
25,804 
65,000 
78,000 
14,137 
3,061 
68,583 
175,000 
203,450 
554,965 
27,352 
61,000 
107,740 
120,000 
24,544 
258,! 
18,E 
242,551 
30,574 
340,000 
38,039 
125,000 
114,886 
102,500 
95 6,738 
102,500
0 
931 -355,000 
819 69,842 
100,000 
175,000 
45,428 
315,000 
268,937 
81,500 
97,499 
556,000 
355,581 
1. Includes $216,356 for previous project. 
36-10 
980,784 
885,104 
65,000 
57,926 
481,500 
162,415 
245,000 
139,430 
152,000 
56,018 
102,500
0 
919,587 
419,8321 
82,000 
82,000 
100,000 
81,500 
175,000 
142,927 
1,204,900 
916,496

Work Authorized 
Mar. 2, 1945 
Oct. 27, 1965 
Mar. 3, 1905 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935; 
included in Public 
Works Administration 
program Sept. 6, 1933 
July 24, 1946 
Sept. 3, 1954 
Oct. 27, 1965 
June 25, 1910 
July 27, 1916 
Jan. 21, 1927 
July 14, 1960 
May 17, 1950 
ALA WAI SMALL BOAT HARBOR, OAHU, HAWAII (See Section 
1 of Text) 
Provide a revetted mole 1,400 feet long; a 60-foot stub breakwater; 
2 wave absorbers having a combined length of 580 feet; a turning 
area and access channels with total area of 6.8 acres dredged to a 
depth of 10 feet; and provide beautification by tree planting. 
BARBERS POINT HARBOR, OAHU, HAWAII (See Section 2 of 
Text) 
An entrance channel 42 feet deep, 450 feet wide, and 3,100 
feet long; an inshore basin of about 46 acres, 38 feet deep; a 
breakwater on the north side of the entrance channel if model 
study shows it to be necessary; spending beaches with wave absorbers 
within the harbor totaling 1,320 feet in length; and a main access 
channel 12 feet deep, 80 feet wide, and 1,200 feet long to a small-boat 
harbor on the west side of the deep-draft harbor to be developed by 
local interests. 
HONOLULU HARBOR, OAHU, HAWAII (See Section 4 of Text) 
Deepening to 35 feet the inner harbor with a general width of 1,200 
feet and casing the curve between the entrance channel and the 
inner harbor. 
For the channel 1,000 feet long. 
Channel connecting Honolulu Harbor and Kapalama Basin. 
Enlarging entrance channel to present project dimensions, 
widening of the harbor basin by 320 feet and the maintenance 
of the improved 400-foot wide portion of the reserved channel. 
A depth of 35 feet over the full width of 600 feet throughout 
the reserved channel; a turning basin in Kapalama Basin 35 feet 
deep by 1,000 feet wide and 3,000 feet long; and a slip of like 
depth 1,000 feet long on the easterly side of Pier 39. 
The second entrance channel; and installation of a moveable-type 
bridge across the 2d entrance channel. (Modified by the Chief 
of Engineers.) 
Reopening Fort Armstrong entrance channel to 45 feet, Main 
Harbor Basin and Kapalama Channel to 40 feet, and relocating 
existing project lines. 
KAHULUI HARBOR, MAUI, HAWAII (See Section 5 of Text) 
Extending east breakwater and dredging the basin. 
For the west breakwater. 
Extend both breakwaters and enlarge dredged basin. 
Enlarge harbor basin, 600 feet wide, 2,400 feet long, 35 feet 
deep. 
KAWAIHAE HARBOR, HAWAII, HAWAII (See Section 7 of Text) 
Provide for a basin 35 feet deep below mean lower low water and 
1,250 feet square with an entrance channel 40 feet deep, 
400 feet wide, and approximately 2,900 feet long extending 
northwestward to deep water in the ocean, and a protective 
breakwater about 4,400 feet long with maximum crest elevation 13 feet 
above mean lower low water, of which the seaward 3,200 feet shall 
be protected by heavy stone revetment. 
H. Doc. 353, 90th Cong., 
2d sess. 
H. Doc. 93, 89th Cong., 
1st sess. 
Annual Report, 1905, 
p. 2565. 
H. Doc. 392, 64th Cong., 
1st sess. 
H. Doc. 753, 69th Cong., 
2d sess. 
H. Doc. 54, 73d Cong., 
1st sess. 
H. Doc. 705, 79th Cong., 
2d sess. 
H. Doc. 717, 81st Cong., 2d 
sess. (Contains latest 
published map). 
H. Doc. 93, 89th Cong., 
1st sess. 
H. Doc. 593, 61st Cong., 
2d sess. 
H. Doc. 1330, 62nd Cong., 
3d sess. 
H. Doc. 235, 69th Cong., 
1st sess. 
H. Doc. 109, 86th Cong., 1st 
sess. (Contains latest 
published map.) 
H. Doc. 311, 81st Cong., 
1st sess. 
36-11 
TABLE 36-B 
Acts 
PACIFIC OCEAN, DIVISION 
AUTHORIZING LEGISLATION 
Documents

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 36-B (Continued) AUTHORIZING LEGISLATION 
Acts 
Oct. 27, 1965 
Oct. 27, 1965 
Oct. 27, 1965 
Sep. 3, 1954 
Oct. 27, 1965 
Aug. 13, 1968 
Dec. 31, 1970 
36-12 
Work Authorized 
Widening the entrance channel to 500 feet at the outer end 
tapering to the existing 520-foot width at the inner end; enlarging 
the deep-draft basin by widening by a maximum of 200 feet and 
lengthening by a maximum of 500 feet; extending the existing 
breakwater by 750 feet if the need is demonstrated by hydraulic 
model tests; constructing a wave absorber 1,075 feet long at the 
inner end of the deep-draft basin; dredging the boat harbor access 
channel, 900 feet long, 80 to 100 feet wide, and 8 to 10 feet deep, 
for a small boat basin at the inner end of the harbor, protected 
by the proposed wave absorber; and constructing a protective 
mole 190 feet long. 
LAHAINA SMALL BOAT HARBOR, MAUI, HAWAII (See 
Section 9 of Text) 
A revetted mole 620 feet long; offshore breakwater 950 feet long; 
turning basin and main access channel of 140,000 square feet; 
entrance channel 515 feet long, 150 feet wide, 15 feet to 20 feet 
deep; and a wave absorber 180 feet long. 
WAIANAE SMALL BOAT HARBOR, OAHU, HAWAII (See 
Section 13 of Test) 
A breakwater 1,350 feet long; a groin 175 feet long; an entrance 
channel 830 feet long, 150 feet wide, depth 15 feet to 17 feet; 
a main access channel 870 feet long, 100 feet to 150 feet wide, 
12 feet to 15 feet deep. 
WAIKIKI BEACH, OAHU, HAWAII (See Section 20 of Text) 
A plan comprising artificial placement of suitable sand fill in 
amount of approximately 385,000 cubic yards (not more than 
185,500 cubic yards of which are applicable to the publicly 
owned shore) on the shore to widen the beach berm to widths 
of 75 to 150 feet, construction of 1,200 feet of terrace wall, 2 groins 
and appurtenant drainage facilities for the protection and 
improvement of the publicly owned portions of the shore of 
Waikiki Beach from the War Memorial Natatorium to the 
southeast boundary of Fort DeRussy. 
A project for restoration and protection of the shore of Waikiki 
Beach from Duke Kahanamoku Beach to the Elks Club under 
a plan comprising artificial placement of beach fill on the shore 
to widen the beach to widths of 75 to 180 feet, construction of 
approximately 8 new groins and appurtenant drainage facilities 
and modification of 3 existing groins. 
IAO STREAM, MAUI, HAWAII (See Section 23 of Text) 
Channel enlargement, levees, a debris basin and related 
works. 
KANEOHE-KAILUA AREA, OAHU, HAWAII (See Section 
24 of Text) 
Provide a dam and reservoir about 3.2 miles above the mouth 
of Kaneohe Stream on the tributary Kamooalii Stream. Project 
consists of an earthfill dam 80 feet high, with a crest length 
of about 2,300 feet, and about 1,000 feet of channel 
improvements at the entrance of Kaneohe Stream to Kaneohe 
Bay; and reservoir with storage of 2,500 acre-feet, of which 
500 acre-feet would be for sediment reserve and recreation 
use and 2,000 acre feet for flood control. 
Documents 
H. Doc. 75, 89th Cong., 
1st sess. 
H. Doc. 353, 88th Cong., 
2d sess. 
H. Doc. 353, 88th Cong., 
2d sess. 
H. Doc. 227, 83d Cong., 
1st sess. 
H. Doc. 104, 89th Cong., 
1st sess. 
H. Doc. 151, 90th Cong., 
1st sess. 
H. Doc. 92-141, 92d Cong., 
1st sess.

PACIFIC OCEAN, DIVISION 
TABLE 36-C RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 14 of Text) 
Date Reconnaissance 
or condition survey 
Project conducted Cost 
Haleiwa Small Boat Harbor, Oahu, Hawaii January 1974 1,667 
Hilo Harbor, Hawaii, Hawaii June 1975 10,170 
Honokohau Small Boat Harbor, Hawaii, Hawaii June 1975 1,500 
Honolulu Harbor, Oahu, Hawaii December 1974 13,886 
Kahului Harbor, Maui, Hawaii June 1973 4,060 
Kaunakakai Harbor, Molokai, Hawaii June 1973 5,621 
Kawaihae Deep Draft Harbor, Hawaii, Hawaii June 1975 3,470 
Manele Small Boat Harbor, Lanai, Hawaii October 1973 5,100 
Nawiliwili Harbor, Kauai, Hawaii January 1975 8,082 
Port Allen Harbor, Kauai, Hawaii January 1975 8,638 
TABLE 36-D OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 15 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Haleiwa Small Boat Harbor, Oahu, Hawaii 1967 $ 255,3971 $ 71,933 
Hana Small Boat Harbor, Maui, Hawaii 1967 - - 
Hanalei Bay Small Boat Harbor, Kauai, Hawaii 1967 - 
Heeia-Kea Small Boat Harbor, Oahu, Hawaii 1972 1,481 
Hilo Harbor, Hawaii, Hawaii 1969 5,423,440 2,809,527 
Honokohau Small Boat Harbor, Hawaii, Hawaii2 1971 781,036 - 
Kailua Small Boat Harbor, Oahu, Hawaii 1967 - 
Kalaupapa Harbor, Molokai, Hawaii 1968 157,997 3,127 
Kaunakakai Harbor, Molokai, Hawaii 1966 138,188 240,649 
Keehi Lagoon, Oahu, Hawaiis 1956 3,348,000 41,857 
Kikiaola Small Boat Harbor, Kauai, Hawaii 4 
Maalaea Small Boat Harbor, Maui, Hawaii - - 
Manele Small Boat Harbor, Lanai, Hawaii 1967 372,0008 44,664 
Maunalua Bay Small Boat Harbor, Oahu, Hawaii 1972 30,378 - 
Nawiliwili Harbor, Kauai, Hawaii 1962 2,127,724' 2,086,398 
Port Allen Harbor, Kauai, Hawaii 2 1962 752,645 511,216 
Reeds Bay Small Boat Harbor, Hawaii, Hawaii 1967 - - 
Wake Island Harbor, Wake Island 1950 - 14,493 
Wells Harbor, Guam2 1950 2,488,056 2,111 
1. In addition $252,000 in Contributed Funds. 
2. Completed. 
3. In addition $630,568 in Contributed Funds. 
4. No previous full report; project authorized by R&H 
Act of 1968. 
5. Abandonment authorized by R&H Act of 1965 (H 
Doc. 98, 89th Cong., 1st sess.). 
6. In addition $246,000 in Contributed Funds. 
7. In addition $233,261 in Contributed Funds. 
36-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 36-E OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
(See Section 21 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Haleiwa Beach, Oahu, Hawaii 1967 $ 240,1481 
Hanapepe Bay, Kauai, Hawaii 1965 - 
Kihei Beach, Maui, Hawaii 1972 154,3132 
Waimea Beach, Kauai, Hawaii 3 
1. In addition $160,098 in Contributed Funds. 3. No previous full report; project authorized by R&H 
2. In addition $154,313 in Contributed Funds. Act of 1958. 
TABLE 36-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 27 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Hanapepe River, Kauai, Hawaiil 1967 $ 784,8672 
Kaunakakai Stream, Molokai, Hawaii' 1950 73,748 - 
Kawainui Swamp, Oahu, Hawaii' 1967 1,265,567 - 
Kuliouou Stream, Oahu, Hawaii' 1971 1,000,0003 - 
Wailoa Stream and Tributaries, Hawaii, Hawaii' 1966 1,044,888 - 
1. Completed. 3. In addition Contributed Funds in $540,335 
2. In addition Contributed Funds in $11,953 received and expended. 
received and expended. 
TABLE 36-G FLOOD PLAIN INFORMATION STUDIES COMPLETED 
DURING FISCAL YEAR 
(See Section 30 of Text) 
Location Requesting Agency Date Completed Federal Cost 
Kauai County, Hawaii: Hawaii State Department of 
Hanamaulu River Land and Natural Resources February 1975 $ 11,800 
Kauai County, Hawaii: Hawaii State Department of 
Kapaa (Moikiha-Waikeia) Land and Natural Resources February 1975 16,900 
Maui County, Hawaii: 
Kaluakoi (West Molokai), Hawaii State Department of 
Molokai Land and Natural Resources February 1975 18,800 
Maui County, Hawaii: Hawaii State Department of 
Olowalu Stream Land and Natural Resources February 1975 13,300 
Territory of Guam: Government of Guam March 1975 16,300 
Agana River 
Territory of Guam: Government of Guam March 1975 7,300 
Maseo River 
Territory of Guam: Government of Guam March 1975 7,300 
Salinas River 
Territory of Guam: Government of Guam March 1975 16,300 
Tamuning 
36-14

PORTLAND, OREG., DISTRICT* 
The territorial limits of the Portland District Umatilla Bridge below McNary Dam, and south 
include the Pacific coastal drainage area of the central Oregon west of the Malheur River and the 
State of Oregon, the portions of the States of Steens Mountains, but not including that part 
Oregon and Washington which lie within the which drains into the Klamath Lake and River. 
Columbia River watershed downstream of the 
IMPROVEMENTS 
Navigation Page 
1. Chetco River, Oreg......................... 37-2 
2. Columbia and Lower Willamette 
Rivers below Vancouver, Wash., 
and Portland, Oreg........................ 37-2 
3. Columbia River at Baker Bay, 
W ash...... ......... ........... ............. 37-4 
4. Columbia River at the Mouth, 
Oreg. and Wash .............................. 37-4 
5. Columbia River between Vancouver, 
Wash., and The Dalles, Oreg............ 37-5 
6. Coos Bay, Oreg......... ................. 37-6 
7. Coos and Millicoma Rivers, Oreg...... 37-7 
8. Coquille River, Oreg........................ 37-7 
9. Cowlitz River, Wash........................... 37-8 
10. Lewis River, Wash ...................... 37-8 
11. Port Orford, Oreg.......................... 37-9 
12. Rogue River, Harbor at 
Gold Beach, Oreg.......................... 37-9 
13. Siuslaw River, Oreg ........................ 37-9 
14. Skamokowa Creek, Wash .............. 37-10 
15. Skipanon Channel, Oreg .................. 37-10 
16. Tillamook Bay and Bar, Oreg........... 37-11 
17. Umpqua River, Oreg................... 37-12 
18. Willamette River above Portland 
and Yamhill River, Oreg............... 37-12 
19. Willamette River at Willamette 
Falls, Oreg. .............................. 37-13 
20. Yaquina Bay and Harbor, Oreg........ 37-14. 
21. Youngs Bay and River, Oreg............37-15 
22. Project Condition Surveys .............. 37-15 
23. Other Authorized Navigation 
Projects .................................. .... 37-15 
24. Navigation Work Under Special 
Authorization ................................ 37-15 
Alteration of Bridges Page 
25. Other Authorized Bridge 
Alteration ................. ............3.7..-15 
Flood Control 
26. Applegate Lake, Rogue River 
Basin, Oreg.................... ........... 37-15 
27. Beaver Drainage District, Oreg........37-16 
28. Beech Creek at Mount Vernon, 
Oreg ............................................. 37-16 
29. Blue River Lake, Oreg.....................37-17 
30. Cascadia Lake, Oreg........................37-17 
31. Cottage Grove Lake, Oreg ............... 37-17 
32. Cowlitz County Consolidated 
Diking Improvement District 
No. 2, W ash. ................................... 37-18 
33. Days Creek Lake, Oreg.............. 37-18 
34. Dorena Lake, Oreg ....................... 37-19 
35. Elk Creek Lake, Rogue River 
Basin, Oreg.... ..... ................ 37-19 
36. Fall Creek Lake, Oreg ........... 37-19 
37. Fern Ridge Lake, Oreg....................37-20 
38. Lower Columbia River Basin, , 
Oreg. and Wash. ............................ 37-20 
39. Lower Columbia River Basin 
Bank Protection, Oreg. 
and Wash ............ ................... 37-21 
40. Scappoose Drainage District, 
Oreg.............................................37-21 
41. Vancouver Lake Area, Wash...........37-22 
42. Wahkiakum County Consolidated 
Diking District No. 1, Wash ........... 37-22 
43. Willamette River Basin, Oreg.......,...37-22 
44. Willamette River Basin, 
Oreg.-Bank Protection ..................... 37-23 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
37-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
45. Inspection of Completed Flood 
Control Projects ............................. 37-23 
46. Scheduling Flood Control 
Reservoir Operations ...................... 37-24 
47. Other Authorized Flood Control 
Projects ....................................... 37-24 
48. Flood Control Work Under 
Special Authorization......................37-24 
Multiple-Purpose Power Projects 
49. Bonneville Lock and Dam-Lake 
Bonneville, Oreg. and Wash. ........... 37-24 
50. Cougar Lake, Oreg..........................37-25 
51. Detroit Lake, Oreg........................37-26 
52. Green Peter-Foster Lakes, Oreg.......37-26 
53. Hills Creek Lake, Oreg .................. 37-27 
54. John Day Lock and Dam-Lake 
Umatilla, Oreg. and Wash...........37-27 
55. Lookout Point Lake, Oreg ........... 37-28 
56. Lost Creek Lake, Rogue River 
Basin, Oreg...................................37-29 
57. The Dalles Lock and Dam- 
Lake Celilo, Wash. and Oreg ........... 37-29 
58. Other Authorized Multiple-Purpose 
Power Projects...............................37-30 
General Investigations 
59. Surveys ..................... ................ 37-30 
60. Collection and Study of 
Basic Data...................................37-30 
61. Research and Development ............ 37-31 
Navigation 
1. CHETCO RIVER, OREG. 
Location. Rises in Siskiyou Mountains of Coast 
Range at an elevation of 4,000 feet, flows for about 
51 miles in a circuitous route, and empties into 
Pacific Ocean at Brookings, Oreg., 300 miles 
south of entrance to Columbia River and 345 
miles north of San Francisco Bay. (See National 
Oceanic and Atmospheric Administration Charts 
18600 and 18203.) 
Existing project. Construction of two jetties 
originally authorized was accomplished 
December 1957 at a cost of $489,554. Modification 
in 1965 authorized an entrance 120 feet wide and 
14 feet deep; extension to north jetty about 450 
feet in length with an increase in elevation of existing 
portion; a barge turning basin about 250 
feet wide, 650 feet long, and 14 feet deep; a protective 
dike about 1,800 feet long with a top elevation 
of 18 feet; and a small-boat access channel 100 feet 
wide and 12 feet deep. Mean lower low water is 
plane of reference. Tidal range in cove between 
lower low water and mean higher high water is 
6.9 feet and extreme is from 2.6 feet below to 9.7 
feet above mean lower low water. Cost of project 
modification (1975) is $2,044,000. (See Table 37-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A small boat basin 
downstream from the town of Harbor, Oreg., has 
been developed by local interests. This basin and 
other attendant facilities serve vessels and connected 
shoreside industries. In addition to the existing 
small boat basin with launching ramps 
there is a private facility called Sporthaven dock 
open to all on equal terms for lumber loading and 
storage. There are several fish receiving docks 
and a dock and facilities for fueling and icing 
vessels. 
Operations and results during fiscal year. 
Maintenance: A total of 67,442 cubic yards of 
material was removed by U.S. hopper dredge 
Pacific and rental equipment. 
Condition at end of fiscal year. Construction of 
jetties was completed December 1957. Removal 
of rock pinnacles and an abandoned bridge structure 
was accomplished in June 1959. Under 
authorized modification of October 1965, two contracts 
were completed. Construction of north jetty 
extension and excavation of entrance channel 
was initiated July 1968 and completed July 1969; 
and construction of a dike at the mouth, and excavation 
of entrance channel, turning basin and 
small-boat basin were initiated September 1969 
and completed March 1970. 
2. COLUMBIA AND LOWER 
WILLAMETTE RIVERS BELOW 
VANCOUVER, WASH., AND 
PORTLAND, OREG. 
Location. Project embraces 103.5 miles of 
Columbia River below Vancouver, Wash., and 
14.6 miles of Willamette River below Portland, 
Oreg. For description of Columbia River see Improvement 
No. 5 and of Willamette River, Improvement 
No. 20. 
Previous project. For details see pages 1995 and 
1998 of Annual Report for 1915, and page 1746 of 
Annual Report for 1938. 
Existing project. Provides for a channel 35 feet 
deep and 500 feet wide from river mile 106.5 to 
105.5, distance between existing highway and 
railroad bridges; a channel 40 feet deep and 600 
feet wide from Vancouver, Wash., river mile 
105.5 to mouth of Columbia River, river mile 3; a 
turning basin at Vancouver, Wash., 40 feet deep, 
800 feet wide, and about 5,000 feet long; a turning 
basin at Longview, Wash., 40 feet deep, average 
37-2

PORTLAND, OREG., DISTRICT 
width of 1,200 feet, and about 6,000 feet long; and 
a channel 40 feet deep in Willamette River with 
varying widths of 600 to 1,900 feet from mouth 
(river mile 0) to Broadway Bridge (river mile 
11.6) which encompasses Portland Harbor area, 
subject to provisions that channel from mouth of 
Willamette River to turning basin at Vancouver, 
Wash., be limited to 500 feet in width until need 
for additional width is demonstrated by 
developed traffic. Existing project also provides 
for auxiliary channels 10 feet deep and 300 feet 
wide near Cathlamet, Wash.; 30 feet deep and 300 
feet wide in St. Helens (Oreg.) Channel; and 30 
feet deep and 500 feet wide connecting upper end 
of St. Helens Channel with main ship channel of 
Columbia; 24 feet deep and 200 feet wide along 
frontage of town of Rainier, Oreg., extended at its 
upper and lower ends to deep water in Columbia 
River, 8 feet deep and 150 feet wide from this 
depth in Columbia River through old mouth of 
Cowlitz River to a point about 3,000 feet upstream 
from present terminus of harbor line; a channel 
from Longview Port dock downstream along 
pierhead line and past Weyerhaeuser Timber Co. 
plant at Longview to a connection with main ship 
channel below Mount Coffin, the downstream 
2,400 feet of this channel to be 30 feet deep and 
300 feet wide and remainder to be 28 feet deep 
and 250 feet wide; construction of a small-boat 
mooring basin at Astoria, Oreg., to include a 
sheet-pile, sandfilled breakwater about 2,400 feet 
long with a 30-foot roadway along its full length, 
and steel pile shore wings totaling about 1,460 
feet long and for construction of stone-and-pile 
dikes and revetments. Plane of reference in estuary 
from mouth to Harrington Point is mean 
lower low water; thence to Portland and Vancouver, 
low water. Tidal range between mean 
lower low water and mean higher high water at 
mouth of Columbia is about 8 feet, and at 
Portland and Vancouver about 2.5 feet at low 
stages of rivers. Extreme tidal ranges are about 
13 and 3 feet, respectively. Annual freshets have 
little effect on depths at mouth of Columbia; at 
Portland and Vancouver they average about 20 
feet, while highest known reached a stage of 33 
feet above low water at Portland. Estimated 
Federal cost of new work (1975) is $27,200,000. 
(See Table 37-B for authorizing legislation.) 
Local cooperation. River and Harbor Act of 
1962 provides that local interests furnish lands 
and rights-of-way for construction and future 
maintenance and aids to navigation upon request 
of Chief of Engineers, including suitable disposal 
areas and necessary retaining dikes, bulkheads, 
and embankments therefor or costs of such 
retaining works; hold the United States free from 
damages; provide and maintain adequate public 
terminal and transfer facilities open to all on 
equal terms; make alterations as are required in 
sewer, water supply, drainage, and other utility 
facilities for construction and maintenance of the 
project; assist in work of improving and maintaining 
main ship channel in Columbia and 
Willamette Rivers by loaning the United States a 
suitable pipeline dredge in good operating condition, 
with full crew and equipment, without 
charge other than reimbursement for full 
operating costs of dredge on a basis approved by 
Chief of Engineers, said operating costs to include 
proportionate maintenance costs based on 
period of time dredge is in use for the United 
States; provide and maintain depths in berthing 
areas and access channels serving terminals, including 
50-foot adjacent to pierhead lines, commensurate 
with depths provided in related project 
areas; and contribute in cash 1.8 percent of 
cost of construction of 40-foot channel by the Corps 
for enhancement of land owned by Port of 
Portland and contribute in cash 3.5 percent of 
cost of construction of 35-foot channel by the 
Corps. Contributions in the amount of $386,000 
were paid in 1964 prior to commencement of construction. 
Total estimated non-Federal cost is 
$557,000, including estimated cash contribution 
of $507,000. 
Terminal facilities. At Portland, Oreg., there 
are 20 terminals with facilities to handle general 
cargo, bulk grain, lumber, and miscellaneous 
other cargo. Also available at this facility to the 
public, are 10 fuel oil and gasoline wharves and 
piers, mechanical handling devices, and heavy 
.lift equipment. Also within boundary of Portland 
harbor there are facilities for storing 12,680,000 
bushels of grain for transhipment by water. At 
Astoria, Oreg., there is a large municipal terminal 
with a 1-million bushel capacity grain 
elevator and facilities for receiving and handling 
all types of general cargo. At Vancouver, Wash., 
there are two municipal facilities, capable of 
berthing five ships simultaneously. Each berth is 
completely outfitted with mechanical and heavy 
lift facilities for receiving and handling all types 
of cargo. 
Also available are two grain elevators with a 
total capacity of 7,500,000 bushels of grain. Port 
of Longview has a public terminal on Columbia 
River and a privately owned grain elevator with a 
capacity of 5,365,000 bushels. At other locations 
on Columbia River between Portland and Columbia 
River entrance there are sufficient private 
facilities to accommodate river vessels and 
fishing craft. These facilities, with planned extensions, 
are considered adequate for existing 
commerce. (For details see Port Series Nos. 33 
and 34, Corps of Engineers, published in 1963 and 
1962 respectively.) 
Operations and results duringfiscal year. New 
Work: All new work dredging for the 40-foot 
channel is complete. Contract for rock removal 
37-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
was awarded 7 April 1975. Contract completion is 
scheduled for March 1977. 
Condition at end of fiscal year. Project as 
authorized by act of July 24, 1946, was completed 
September 1950. Main channel was completed in 
1933, except that a realignment at Harrington 
Point was made in 1935. Dikes were completed in 
1935 and extension of Vancouver turning basin in 
1939. Auxiliary channel in vicinity of Longview 
was completed in 1949, and improvement of 
mouth of Cowlitz River and small boat mooring 
basin at Astoria were completed in 1950. Dredging 
40-foot channel in Columbia River from 
Portland, Oreg., and Vancouver, Wash., to the sea 
is 94 percent complete. Project depths are maintained 
all year except during short shoaling 
periods following freshets which generally occur 
in May, June, and July. In Columbia and 
Willamette Rivers between mouth and Broadway 
Bridge at Portland a depth of 40 feet at low tide 
and 42 feet at high tide is practicable all year. In 
Columbia River between mouth of Willamette 
River and Vancouver, Wash., depths of 40 and 42 
feet at low and high tide, respectively, are practicable 
all year. (See Table 37-C for total cost of 
existing project to June 30, 1975.) Under authority 
contained in Section 107 of the 1960 RH Act as 
amended, a turning basin 40 feet deep at Astoria 
and improvements to the Hammond small boat 
basin were approved. Astoria turning basin is 
scheduled for construction in 1976. 
3. COLUMBIA RIVER AT 
BAKER BAY, WASH. 
Location. Baker Bay is a shallow body of water 
about 15 square miles in extent on north side of 
Columbia River near its mouth. Bay is separated 
from river by Sand Island, a low-lying sand bar 
only a few feet above high tide level. (See NOAA 
Chart 18521.) 
Existing project. A main channel, 10 feet deep 
and 200 feet wide extending through easterly 
passage at Sand Island to port of Ilwaco, a distance 
of about 5 miles; a mooring basin 10 and 12 
feet deep, about 20 acres in extent, east of port of 
Ilwaco dock, with protecting breakwaters; and a 
west channel 10 feet deep connecting basin with 
deep water in Columbia River, with a width of 
150 feet, increased to 200 feet for 2,000 feet at 
southerly end. Mean lower low water is plane of 
reference. Tidal range between mean lower low 
water and mean higher high water is about 8 feet, 
and extreme about 13 feet. (See Table 37-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Wharves, floats, ramps, 
and berths, for fishing craft, barges and towboats. 
Small-boat basin and protecting 
breakwater provides moorings for numerous 
fishing and recreational craft all year. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Sand-bypasser Sandwick 
displaced 14,000 cubic yards of material and 
7,017 cubic yards of material were removed by 
Dredge Pacific. 
Condition at end offiscal year. Channel extending 
through easterly passage of Sand Island was 
completed in 1934. Dredging west channel to 8 
feet was accomplished September 1948. Deepening 
west channel to 10 feet, and boat basin and 
breakwater construction at Ilwaco, Wash., finished 
December 1957, completed the project. 
4. COLUMBIA RIVER AT THE 
MOUTH, OREG. AND WASH. 
Location. The Columbia River rises in British 
Columbia, through which it flows for 425 miles. It 
enters the United States in northeastern 
Washington, flows southerly to mouth of Snake 
River, thence westerly between Oregon and 
Washington, and empties into Pacific Ocean 645 
miles north of San Francisco Bay and 160 miles 
south of Strait of Juan de Fuca. Total length of 
river is 1,210 miles. (See NOAA Charts 18520, 
18521, 18523, 18524, 18526, and 18531; also 
Geological Survey map of Washington.) 
Previous project. For details see page 1999, Annual 
Report for 1915 and page 1740 of Annual 
Report for 1938. 
Existing project. Provides for a. channel across 
bar of suitable alinement with depth of 48 feet at 
mean lower low water for a width of one-half 
mile, to be secured by dredging and construction 
of a spur jetty on north shore. Tidal range on bar 
between mean lower low water and mean higher 
high water is about 8 feet, and extreme tidal 
range is about 13 feet. Estimated Federal cost for 
new work (1975) is $27,301,000 which includes 
$701,000 for additional recreation facilities at 
completed project, but excludes $4,040,878 for 
jetty rehabilitation. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Estimated cost of local 
cooperation on basis of cost-sharing for additional 
recreation facilities is $543,000. 
Operations and results during fiscal year. 
Maintenance: U.S. hopper dredge Biddle 
removed 6,143,388 cubic yards of material from 
the entrance channel. 
Conditions at end of fiscal year. Existing project 
is 63 percent complete. Advance engineering 
studies have revealed that construction of spur 
jetty "B" is not economically justified. This portion 
of the project was placed in the inactive 
37-4

PORTLAND, OREG., DISTRICT 
category, March 24, 1972. Project as originally 
authorized consisting of extension of south jetty, 
constructed under previous project, construction 
of north jetty, and 40-foot channel depth over entrance 
bar, was completed in 1918. Dredging 48- 
foot bar channel was completed September 1957. 
Rehabilitation of south jetty was completed with 
new work funds September 1964 and rehabilitation 
of north jetty in April 1965. Total costs to 
June 30, 1975, from Federal funds for existing 
project were $47,008,437 of which $15,121,508 
was for new work, $4,040,878 for jetty restoration 
and $27,846,051 for maintenance. In addition, 
$475,000 and $25,000 contributed by Ports of 
Portland and Astoria, Oreg., respectively, were 
expended for new work. 
5. COLUMBIA RIVER BETWEEN 
VANCOUVER, WASH., AND 
THE DALLES, OREG. 
Location. On Columbia River, between Interstate 
Bridge at Vancouver, Wash., 106.5 miles 
above mouth and The Dalles, Oreg., mile 191, a 
distance of 84.5 miles. For description of Columbia 
River, see Improvement No. 4, "Columbia 
River at the Mouth." 
Existing project. Channel 27 feet deep at low 
water and 300 feet wide between Vancouver, 
Wash., and The Dalles, Oreg., 84.5 miles; a 
channel 10 feet deep at low water and 300 feet 
wide at upstream entrance to Oregon Slough, 
Oreg., a suitable turning basin adjacent to site of 
port development in vicinity of Camas and 
Washougal, Wash., a boat basin at Hood River, 
Oreg., 500 by 1,300 feet and 10 feet deep at normal 
Bonneville pool level, with a connecting channel 
of same depth to deepwater, and a protecting 
breakwater on easterly side; a barge channel to 
waterfront at Bingen, Wash., 10 feet deep at normal 
Bonneville pool level, 200 feet wide and about 
1 mile long, and an access channel 7 feet deep at 
normal Bonneville pool level, 100 feet wide and 
about 1,000 feet long, to a natural mooring basin 
for small boats near east end of channel; and construction 
of The Dalles Harbor, Oreg., to provide 
a breakwater and shear boom protected basin 
about 400 by 800 feet in size with depth of 8 feet 
below a pool elevation of 72.5 feet at mean sea 
level. Tidal range between mean lower low water 
and mean higher high water at Vancouver is 
about 2.5 feet and at Bonneville about 0.2 foot at 
low stages of the river. Extreme tidal ranges are 
about 4 feet and 0.4 foot, respectively. Annual 
freshets average about 21 feet at Vancouver, 
while the highest known stage reached 33 feet 
above low water. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. At Vancouver, Wash., immediately 
upstream from the two highway 
bridges are a privately owned sand and gravel 
facility, a Coast Guard dock, a private towboat 
moorage equipped with marine railway and shipbuilding 
facilities, and facilities for transfer of 
bulk petroleum from river barges. (For further 
details concerning facilities at Vancouver see 
Port Series No. 33, Corps of Engineers, published 
in 1963.) In northern section of Portland, Oreg., 
on south bank of Columbia River, about 1.7 miles 
upstream from interstate bridges, is a wharf with 
a 110-ton derrick used for transfer of cargoes 
between trucks and barges. About 3.5 miles upstream 
from interstate bridges are two liquidfertilizer 
storage tanks each with a capacity of 
229,000 gallons. This facility has necessary equipment 
for unloading tanker barges and loading 
trucks. At Camas, Wash., about 13.5 miles upstream 
from Vancouver, there is a private wharf 
used for transfer of papermill supplies and paper 
to and from barges, and facilities for discharging 
bulk oils from barges. Port of Camas-Washougal 
has a wharf 528 feet long at Washougal, Wash. At 
Port of The Dalles (mile 44 above Bonneville) 
there is a municipal wharf 125 by 1,100 feet for 
use by both ocean vessels and river boats. There 
are two 1-story timber and corrugated iron 
warehouses, each 94 by 461 feet, on this wharf 
with rail connections. There is also a municipal oil 
terminal consisting of a concrete and timber 
wharf 27 by 193 feet, about a mile below main 
wharf. There are private storage tanks with a 
total capacity of 2,300,000 gallons near this terminal 
for handling petroleum products. Storage 
tanks have rail, truck and water connections. A 
private elevator with a capacity of 40,000 bushels 
and a public elevator of 868,000-bushel capacity 
for handling bulk grain to river craft are also at 
The Dalles. Public elevator has rail, truck, and 
water connections. There is a privately owned rail 
connection about three-fourths mile below 
municipal wharf where certain types of cargo 
may be handled between railroad cars and river 
boats or barges by means of a derrick of up to 22- 
ton capacity. At numerous locations over entire 
waterway are log rollways for transfer of logs to 
water from trucks and public and private boat 
basins. Facilities are considered adequate for 
present commerce. 
Operations and results during fiscal year. 
Maintenance: A total of 34,000 cubic yards of 
material was removed by U.S. dredge Pacific. 
Condition at end of fiscal year. Existing project 
is complete. Construction of The Dalles Harbor, 
Oreg., was completed in 1949. Channel 
dredging at upper end of Oregon Slough was accomplished 
in 1957. Project depth of 27 feet 
between Bonneville and The Dalles, Oreg., was 
37-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
achieved April 1959. The 27-foot channel depth 
between Vancouver, Wash., and Bonneville, 
Oreg., except for removal of some submerged 
rock and dredging, was completed May 1960. Improvement 
of lower entrance of Bonneville Dam 
lock was completed in May 1961. Construction of 
a boat basin at Hood River, Oreg., and of Camas- 
Washougal, Wash., turning basin was accomplished 
February 1962. Construction of a 
barge channel in Columbia River near Bingen, 
Wash., was completed October 1962, except for 
removal of rock pinnacles encountered. This was 
accomplished by contract September 1963. Construction 
of 15-foot barge channel under Interstate 
Highway bridge was completed 
December 1963 under Section 107 of the 1960 
River and Harbor Act. Since ocean-going vessels 
are not using this channel, it is currently maintained 
to 15 feet for barge traffic. 
6. COOS BAY, OREG. 
Location. On Oregon coast 200 miles south of 
mouth of Columbia River and 445 miles north of 
San Francisco Bay. It is about 13 miles long and 1 
mile wide, with an area at high tide of about 15 
square miles. (See NOAA Charts 18580 and 
18587. 
Previous projects. For details see page 1987 of 
Annual Report for 1915, and page 1728 of Annual 
Report for 1938. 
Existing project. Two rubblemound, high-tide 
jetties at entrance; a channel across outer bar 40 
feet deep at mean lower low water, and a suitable 
width with dimensions reduced gradually to 
Guano Rock; a channel 30 feet deep at mean lower 
low water and generally 300 feet wide thence to 
mouth of Isthmus Slough; turning basins of same 
depth and 1,000 feet long and 600 feet wide opposite 
Coalbank Slough and at city of North Bend; 
anchorage basins 30 feet deep, 600 feet wide by 
2,000 feet long at mile 3.5 and near mile 7; a 
channel 22 feet deep and 150 feet wide from 
Smith's Mill (mouth of Isthmus Slough) to 
Millington; a mooring basin, about 500 by 900 
feet, for small boats at Charleston, with a connecting 
channel, 10 feet deep and 150 feet wide, to 
deep water in Coos Bay, and construction of a 
protecting breakwater and bulkhead. Project 
was modified by River and Harbor Act of 1970 to 
provide for: a channel 45 feet deep and 700 feet 
wide across the outer bar, dimensions reducing 
gradually to 35 feet deep and 300 feet wide near 
mile 1; an inner channel 35 feet deep and 300 feet 
wide from that point to about mile 9, thence 35 
feet deep and generally 400 feet wide to mile 15; 
deepening and widening the existing turning 
basins to 35 feet by 650 feet; an anchorage area, 
near mile 6, 1,200 feet wide, 2,000 feet long, and 
35 feet deep; and abandonment of existing 
authorized anchorages at mile 3.5 and mile 7. (See 
Table 37-B for authorizing legislation.) Plane of 
reference is mean lower low water. Tidal range 
between higher high water and plane of reference 
and extreme tidal range at entrance are 7 feet and 
about 11 feet, respectively, and at Coos Bay 7.3 
and 11 feet, respectively. Estimated C of E cost 
for 1970 modification is $16,400,000 (1975). Estimated 
non-Federal cost is $148,000 (1975). 
Local cooperation. River and Harbor Act of 
1970 provides that local interests furnish lands 
and rights-of-way for construction and subsequent 
maintenance of the improvement, and for 
aids to navigation upon request of the Chief of 
Engineers, including suitable disposal areas and 
also necessary retaining dikes, bulkheads, and 
embankments therefor, or the costs of such 
retaining works; hold the United States free from 
damages; provide without cost all alterations and 
relocations of utility facilities; provide and maintain 
without cost to the United States, depths in 
berthing and mooring areas and local access 
channels serving the terminals; adequate public 
terminal and transfer facilities, open to all on 
equal terms; and establish regulations 
prohibiting discharge of pollutants into the 
waters of the improved channel by users thereof, 
which regulations shall be in accordance with 
applicable laws or regulations of Federal, State, 
and local authorities responsible for pollution 
prevention and control. 
Terminal facilities. At North Bend there is a 
municipal dock 649 feet long fronting on channel, 
about 2,380 feet of privately owned mill docks, 
and three oil-receiving terminals in vicinity. At 
Coos Bay there is a privately owned dock with a 
frontage of 1,345 feet, open to the public on equal 
terms; several small landings for fishing and harbor 
craft; and three lumber docks with 1,300-, 
576-, and 500-foot frontages, respectively. At 
Eastside, on Isthmus Slough, there is a 200-foot 
dock to accommodate coastal lumber schooners. 
At Empire there is a privately owned lumber 
dock with frontage of 510 feet, and an oil terminal, 
also privately owned, for receipt of 
petroleum products by barge. About 1.5 miles 
below Empire there is a privately owned pulp 
mill dock with a frontage of 480 feet. At 
Charleston there are four wharves, one public 
and three private, with usable areas of 1,200,750, 
7,000 and 12,000 square feet, respectively, for 
receipt of fresh fish and shellfish and a large 
seafood receiving and processing plant. There is 
also a municipally owned small-boat basin, open 
to all on equal terms, capable of mooring 250 
fishing and recreation craft. Servicing facilities 
for small craft are available at all facilities, and 
public launching ramps have been constructed in 
Charleston area by private interests. A privately 
owned floating moorage on Joe Slough has 
37-6

PORTLAND, OREG., DISTRICT 
facilities for mooring about 50 fishing vessels. At 
Jordan Cove area there is a dock, 248 feet long, for 
wood chip ships. These facilities are considered 
adequate for existing commerce. (For details see 
Port Series No. 33, Corps of Engineers, published 
in 1963.) 
Operations and results during fiscal year. New 
Work: Revisions to the Environmental Impact 
Statement that was submitted to Council on Environmental 
Quality November 13, 1970, were 
completed and under Division review. Funds to 
initiate preconstruction planning for deep draft 
channel were appropriated during the fiscal year 
1973; however, initial allocation of funds was 
made in fiscal year 1974. Preparation of General 
Design Memorandum Phase I is 95 percent complete 
and Phase II 70 percent complete. Maintenance: 
Periodically, U.S. hopper dredges 
Pacific and Harding removed 2,027,278 cubic 
yards of material. 
Condition at end of fiscal year. South jetty was 
completed in 1928, north jetty in 1929, and 24-foot 
channel in 1937. The south jetty was restored in 
1941 and 1942 by construction of a concrete cap 
for full length of the jetty. Excavation of channel 
to 30 feet deep and generally 300 feet wide from 
entrance to Isthmus Slough was completed in 
1951. Dredging outer bar channel to a depth of 40 
feet, decreasing to 30 feet at Guano Rock was completed 
in 1952. Existing project was completed 
September 1956 with construction of small boat 
basin at Charleston, Oreg. Rehabilitation of south 
jetty was started in June 1962 and completed 
December 1963. Extension in South Slough under 
Section 107 was accomplished in May 1970. 
Repair of north jetty was completed in August 
1970. Total Federal costs to June 30, 1975, for existing 
project were $35,418,565 of which $8,473,- 
844 was for new work, $2,335,966 for jetty 
restoration and $24,608,755 for maintenance. In 
addition $43,513 for new work and $8,387 for 
maintenance from contributed funds were expended. 
7. COOS AND MILLICOMA 
RIVERS, OREG. 
Location. South Fork and Millicoma Rivers 
rise in Coast Range in southern Oregon, flow 
generally westerly and join to make Coos River, 
5.3 miles above mouth of Coos River in Coos Bay. 
(See NOAA Chart 18587, Allegany and Daniels 
Creek Quadrangle.) 
Existing project. Originally authorized project: 
a channel depth of 3 feet, generally, from 
mouth of Coos River and 1 foot near head of 
navigation. Project as modified: two channels 5 
feet deep and 50 feet wide from mouth of Coos 
River to Allegany on Millicoma River, mile 13.8 
and to Dellwood on South Fork, mile 14, and 
thence a channel 3 feet deep and 50 feet wide to 
mile 14.7 on South Fork, including stabilization 
works on Coos River. Mean lower low water is 
plane of reference. Tidal range between higher 
high water and plane of reference and extreme 
tidal ranges under ordinary conditions at mouth 
of Coos River are 7.3 and 11 feet, respectively, and 
there is a tidal range of about 1 foot at head of 
navigation in both forks. Freshet stages usually 
reach a height of from 10 to 15 feet at Allegany, 
head of navigation on Millicoma River. (See Table 
37-B for authorizing legislation. Latest published 
maps are in these documents.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small privately 
owned docks and landing places on the river are 
used by towboats and pleasure craft. There are no 
publicly owned docks. Present facilities are considered 
adequate for existing commerce. Project 
modification provides for construction of terminal 
facilities open to all on equal terms. 
Operations and results during fiscal year. 
Maintenance: A total of 16,260 cubic yards of 
material was dredged. 
Condition at end of fiscal year. Originally 
authorized project providing for a channel from 
mouth of Coos River to head of navigation in both 
forks, to provide a depth of 3 feet generally and 1 
foot near head of navigation, was completed in 
1899. In March 1966 construction of project as 
modified by 1948 River and Harbor Act was completed 
except for removal of rock encountered, 
which was accomplished in August 1966. Since 
anticipated scour in Coos River has not developed, 
it has been recommended that construction of 
stabilization works be delayed until need has 
been established. 
8. COQUILLE RIVER, OREG. 
Location. Rises in Coast Range, flows generally 
westerly for about 100 miles, and empties into 
Pacific Ocean at Bandon, Oreg., 225 miles south 
of mouth of Columbia River and 420 miles north 
of San Francisco Bay. (See NOAA Charts 18580 
and 18186.) 
Previous projects. For details see page 1986 of 
Annual Report for 1915, and page 1727 of Annual 
Report for 1938. 
Existing project. Two rubblemound high-tide 
jetties at river mouth, south jetty 2,700 feet long 
and the north, 3,450 feet long; and a channel 13 
feet deep at mean lower low water and of suitable 
width from the sea to a point 1 mile above old Coquille 
River Lighthouse, and snagging to State 
highway bridge at city of Coquille. Mean lower 
low water is plane of reference. Tidal range 
37-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
between mean lower low water and mean higher 
high water at mouth is 6.8 feet and extreme range 
about 10 feet. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. At Bandon: A privately 
owned mill dock used exclusively for shipping 
lumber on coastwise vessels, a publicly owned 
wharf, and a small-boat basin open to all equally. 
Above Bandon, on navigable waterway: A 
privately owned lumber shipping facility and 
numerous log booms and rollways. Facilities are 
considered adequate for present commerce. 
Operations and results during fiscal year. New 
work: Plans and specifications for Coquille 
Lighthouse Rehabilitation are 95 percent complete. 
Maintenance: Government hopper 
dredge Pacific removed 15,000 cubic yards of 
material from entrance channel. 
Condition at end of fiscal year. Jetties were 
completed in 1908 and entrance channel in 1933. 
North jetty was reconstructed in 1942 and a 750- 
foot extension to easterly end was constructed in 
1951. South jetty was repaired in 1954 and north 
jetty in 1956. Total Federal costs for existing project 
to June 30, 1975, were $2,552,667 of which 
$319,938 was for new work ($3,298 for Recreation) 
and $2,232,729 for maintenance: In addition, 
$72,891 was expended for new work from contributed 
funds. 
9. COWLITZ RIVE"' WASH. 
Location. Rises in Cascade Range in 
Washington, flows westerly and southerly about 
120 miles and empties into Columbia River about 
69 miles from its mouth. (See NOAA Chart 
18524.) 
Previous project. For details see page 2000, Annual 
Report for 1915 and page 1763, Annual 
Report for 1938. 
Existing project. A channel 4 feet deep at low 
water and 50 feet wide from mouth to Ostrander 
(9 miles), 2.5 feet deep and 50 feet wide to Castle 
Rock (10 miles), and 2.5 feet deep at low water and 
not less than 40 feet wide to Toledo (18 miles) to be 
secured by snagging, dredging, and regulating 
works. Detailed project report covering modification 
of project to 8 feet deep and 100 feet wide in 
the lower 4.75 miles under Section 107 of 1960 
River and Harbor Act was approved January 3, 
1965. Water level due to tides, varies from 4 feet 
at mouth to zero at Ostrander. During ordinary 
freshets a stage of 20 feet, and at extreme floods a 
stage of 25 feet is reached in river at Kelso, Wash. 
(See Table 37-B for authorizing legislation.) For 
latest published map see House Document 1167, 
60th Congress, 2d Session. 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned and 
operated landings, a sand and gravel dock, log 
rollways, and storage booms. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Sand by-passer Sandwick 
displaced 20,900 cubic yards of material. 
Condition at end offiscal year. Existing project 
was completed in 1913. Project as modified, under 
Section 107 of the 1960 River and Harbor Act 
and approved January 1965, was completed 
August 1968. Above Kelso, channel is in poor condition. 
Total costs under existing project to June 
30, 1975 were $1,247,148 of which $272,437 was 
for new work and $974,711 for maintenance. 
10. LEWIS RIVER, WASH. 
Location. Rises in Cascade Range in 
Washington, flows westerly and southwesterly 
110 miles, and empties into Columbia River about 
88 miles from its mouth. (See NOAA Chart 
18524.) 
Previous projects. For details see page 2001, 
Annual Report for 1915, and page 1762, Annual 
Report for 1938. 
Existing project. A low-water channel 6 feet 
deep and 50 feet wide to mouth of East Fork (3.75 
miles); 4 feet deep and 50 feet wide on East Fork 
from its mouth to La Center (3 miles); 4 feet deep 
and 50 feet wide on Lewis River (North Fork) and 
from East Fork to Woodland (2.5 miles), secured 
by dredging and construction of regulating 
.works and clearing channel to Ariel (16 miles 
from Woodland). Maximum variation of water 
level, due to tide, ranges from about 3 feet at 
mouth to 1.5 feet at La Center and zero at 
Woodland. During ordinary freshets a stage of 14 
feet and, at extreme floods, a stage of 24 feet is 
reached in main river at Woodland, Wash. For 
latest published map see page 3557 of Annual 
Report for 1904. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. At Woodland on Lewis 
River there are several privately owned facilities 
for mooring, fishing and pleasure craft. Facilities 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: 6,880 cubic yards of material 
were displaced by the Sand by-passer Sandwick. 
Condition at end of fiscal year. Existing project 
was completed in 1927. Total cost for existing 
project to June 30, 1975 was $482,320 of which 
$35,880 was for new work and $446,440 for 
maintenance. 
37-8

PORTLAND, OREG., DISTRICT 
11. PORT ORFORD, OREG. 
Location. On Oregon coast 250 miles south of 
Columbia River entrance and 390 miles north of 
San Francisco Bay. (NOAA Chart 18203 and 
Geological Survey Quadrangle, Port Orford, 
Oreg.). 
Existing project. Improvement of harbor by 
550-foot extension of existing locally constructed 
breakwater. Federal cost of new work is $758,- 
692. (See Table 37-B for authorizing legislation.) 
Local cooperation. Complied with. 
Terminal facilities. A lumber dock which is a 
timber piling structure about 210 by 70 feet, 
equipped with two fork lifts for handling bundled 
lumber and a fish dock, attached to inshore end of 
lumber dock, 120 feet long by 70 feet wide. About 
25 local fishing boats make Port Orford their 
home base. These facilities are considered adequate 
for present commerce. 
Operations and results during fiscal year. 
Maintenance: The U.S. sand-bypasser 
Sandwick displaced 11,839 cubic yards of 
material. 
Condition at end offiscal year. Extension of existing 
locally constructed breakwater by 550 feet 
was completed October 1968. Turning basin was 
completed September 1971. 
12. ROGUE RIVER, HARBOR AT 
GOLD BEACH, OREG. 
Location. Rises in Cascade Range in 
southwestern Oregon, flows westerly through 
Coast Range, and empties into Pacific Ocean 264 
miles south of mouth of Columbia River and 381 
miles north of San Francisco Bay. (See NOAA 
Chart 18202.) 
Existing project. Two jetties at entrance, and a 
channel 13 feet deep and 300 feet wide from ocean 
to a point immediately below State Highway 
Bridge, about 1 mile, including widening channel 
at a point about 0.25 mile below bridge to form a 
turning basin 13 feet deep, 500 feet wide, and 650 
feet long. At request of local interests, turning 
basin was located in south portion of estuary 
downstream from a point 0.25 mile below bridge. 
This change was effected to permit adequate terminal 
facilities to be constructed adjacent to turning 
basin. A map showing this revision is in 
Portland District office. Mean lower low water is 
plane of reference. Range of tide between mean 
lower low water and mean higher high water is 
6.7 feet, and extreme range of tide from lower low 
to higher high water is estimated to be 14 feet. Estimated 
Federal cost of new work (1975) is $4,- 
156,252 exclusive of $635,783 for rehabilitation of 
north jetty. Authorizing document contains latest 
published maps. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One-half mile below 101- 
highway bridge is a steel sheet piling and fill dock 
used exclusively for shipment of lumber by oceangoing 
barge. There are various other landings for 
fishing and recreational craft. At Wedderburn, 
across river from Gold Beach, is a facility to accommodate 
excursions passengers and small 
freight items destined for various private landings 
between Wedderburn and Agness, Oreg. 
Facilities considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: U.S. Government plants removed 
35,499 cubic yards of material from the river 
channel and entrance bar, and dredging by contract 
removed an additional 3,549 cubic yards. 
Condition at end offiscal year. Existing project 
as authorized is completed. Construction of two 
jetties at entrance was completed September 
1960. Dredging river channel by contract and entrance 
bar by government plant was completed 
October 1961. North jetty along channel side suffered 
considerable damage from December 1964 
flood and rehabilitation was completed October 
1966. Breakwater construction and dredging, under 
contract awarded in September 1964, was 17 
percent accomplished when flood of December 
1964 destroyed all completed works and contract 
was terminated. Bank protection work at 
Wedderburn location was completed in October 
1972. A major portion of breakwater, constructed 
by Port of Gold Beach, was completed during 
1973. 
13. SIUSLAW RIVER, OREG. 
Location. Rises in coast range, flows about 110 
miles westerly and empties into Pacific Ocean 
about 160 miles south of entrance of Columbia 
River and 485 miles north of San Francisco Bay, 
Calif. (See NOAA Charts 18583 and 18580.) 
Previous project. For details see page 1988, Annual 
Report for 1915. 
Existing project. Provides for a 600-foot extension 
of north jetty; an entrance channel 18 feet 
deep and 300 feet wide from deep water in ocean 
to a point 1,500 feet inside the outer end of existing 
north jetty; thence a channel 16 feet deep, 
200 feet wide with additional widening at bends, 
and about 5 miles long, to a turning basin, 16 feet 
deep, 400 feet wide, and 600 feet long, opposite 
Siuslaw dock at Florence; and a channel 12 feet 
deep, 150 feet wide from Florence to Cushman. 
Mean lower low water is plane of reference. Tidal 
range between mean higher high water and plane 
of reference and extreme tidal ranges at mouth of 
37-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
river is 6.6 feet and about 11 feet, respectively. 
During low stages of river, tidal effect extends to 
Mapleton, 20.5 miles above mouth. A detailed 
project report covering modification of existing 
project to provide for a minimum navigation 
channel 12 feet deep and 150 feet wide from 
Cushman to Mapleton under Section 107 of the 
1960 River and Harbor Act was approved March 
18, 1974. Estimated Federal cost of new work 
(1974) is $3,650,000 which includes $190,000 for 
channel modification under Section 107 of the 
1960 River and Harbor Act; $879,285 for jetty 
rehabilitation. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Fully complied with for all 
completed work. River and Harbor Act of 1958 
provides that construction of north jetty extension 
be deferred until experience demonstrates, 
in judgment of Chief of Engineers, that this work 
is advisable. Real estate assurances were 
accepted November 9, 1966. Estimated costs for 
all requirements under terms of project 
authorization were $156,000 (1967). 
Terminal facilities. Port dock at Florence is 
principal terminal facility on river. This dock, 
150 feet wide and 350 feet long, is about 5.3 miles 
above river entrance and accommodates a fishreceiving 
station at east end of wharf which maintains 
a 2-ton capacity winch and supplies gasoline, 
oil, and ice to fishermen. Other facilities at 
Florence consist of various floatways which 
provide docking facilities for fishing vessels and 
other small craft and a floating dock with accommodations 
for 75 commercial fishing vessels. Adjacent 
to commercial basin is mooring basin with 
accommodations for 200 sport boats of all sizes. 
Across the river and below highway bridge at 
Glenada are floatways used by small craft. 
Modern docks for loading ocean-going barges 
with packaged lumber are maintained, at 
Cushman, by Murphy Bros. Lumber Co.; between 
Cushman and Mapleton, by Davidson Industries; 
and in Mapleton, by U.S. Plywood Champion 
Lumber Co. There are also a number of private 
landings and log booms between Cushman and 
Mapleton, to accommodate river traffic. These 
facilities are considered adequate for existing 
traffic. 
Operations and results during fiscal year. 
Maintenance: U.S. hopper dredge Pacific 
removed 171,535 cubic yards of material from entrance 
channel and 165,269 cubic yards were 
removed by contract dredging. Channel 
stabilization work consisting of revetment, pile 
dike and groin construction was initiated FY 
1974 and completed FY 1975. 
Condition at end offiscal year. Extension ofjetties 
constructed under previous project was completed 
in 1917. The 12-foot channel was completed 
in 1930. In March 1958, rehabilitation of 
north jetty was accomplished. Rehabilitation of 
south jetty was completed December 1962. 
Modified project, as authorized July 3, 1958 and 
initiated August 1968, is 28 percent complete. 
Constructed portion consists of: dredging river 
channel, turning basin and range construction, 
completed 1968; dredging 18-foot bar channel, 
completed September 1969; stabilizing spoil 
areas, completed 1970; and channel stabilization, 
completed 1974. Final EIS was filed with CEQ 21 
January 1974. Construction of a 12 foot deep by 
150 foot wide channel from Florence to Mapleton 
was completed in 1975 under Sec. 107 authority. 
Remaining work consists of extension of north jetty 
which has been placed in the deferred 
category. Total Federal costs for existing project 
to June 30, 1975 were $5,561,547 of which $1,488,- 
780 was for new work, $879,285 for jetty restoration, 
and $3,345,183 for maintenance. In addition 
$322,532 was expended for new work from contributed 
funds. 
14. SKAMOKAWA CREEK, WASH. 
Location. Rises in Wahkiakum County, in 
southwestern part of the State of Washington, 
flows southwesterly and southerly about 10 miles, 
and empties into Columbia River about 34 miles 
above mouth. (See NOAA Chart 18523.) 
Existing project. Provides for a channel 6.5 feet 
deep at low water and 75 feet wide, between 
Steamboat and Brooks Sloughs, about 1,600 feet 
long. Tidal range between mean lower low water 
and mean higher high water is about 7 feet and 
maximum variation of water level due to tides or 
freshets is about 12 feet. During ordinary freshets 
a stage of 12 feet is reached in creek at 
Skamokawa, Wash. Cost for new work was $2,- 
400. (See Table 37-B for authorizing legislation.) 
Latest published map is in project document. 
Local cooperation. None required. 
Terminal facilities. There are several privately 
owned docks on Skamokawa Creek, Steamboat 
Slough, and Brooks Slough for use of towboats 
and pleasure craft. These facilities are in need of 
repair. 
Operations and results during fiscal year. 
Maintenance: A total of 180,910 cubic yards of 
material was removed by U.S. dredge Biddle and 
U.S. sand-bypasser Sandwick. 
Condition at end offiscal year. Project was completed 
in 1920. 
15. SKIPANON CHANNEL, OREG. 
Location. In tidal waterway extending south 
2.7 miles from deep water in Columbia River. 
Channel enters Columbia about 10 miles above 
mouth and 4 miles below Astoria, Oreg. (See 
NOAA Chart 18523.) 
37-10

PORTLAND, OREG., DISTRICT 
Existing project. Channel 30 feet deep and 
generally 200 feet wide extending from deep 
water in Columbia River to railroad bridge at 
Warrenton, Oreg., distance of 1.8 miles, turning 
basin of same depth, mooring basin 12 feet deep at 
mean lower low water at Warrenton, Oreg., and 
channel 6 feet deep, generally 40 feet wide, with 
increased widths at log dumps and terminals, for 
4,500 feet via cutoff channel above railroad 
bridge. Mean lower low water is plane of 
reference. Tidal range between mean lower low 
water and mean higher high water is about 8 feet; 
extreme tidal range is about 13 feet. (See Table 
37-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. City of Warrenton owns" 
wharf with a 300-foot frontage open to public on 
equal terms. One privately owned cannery wharf 
with a 300-foot frontage is used for unloading fish 
and handling fish nets. One privately owned 
boatyard has floats and moorage facilities for use 
of a maximum of 80 small boats. In channel above 
railroad bridge facilities consist of log rollways 
used for sorting logs. Small-boat basin has 
facilities for numerous fishing and recreation 
craft. These facilities, except during the fishing 
season, are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: U.S. hopper dredge Pacific 
removed 97,500 cubic yards of material. 
Condition at end of fiscal year. Dredging river 
channel and turning basin was completed in 
1939. Construction of small-boat mooring basin at 
Warrenton, Oreg., was completed October 1957, 
and fill stabilization work was accomplished in 
August 1958 completing the project. 
16. TILLAMOOK BAY AND BAR, 
OREG. 
Location. Bay is on Oregon coast about 50 miles 
south of mouth of Columbia River. (See NOAA 
Charts 18520 and 18558.) 
Previous project. For details see pages 1989 of 
Annual Report for 1915, and page 1474 of Annual 
Report for 1936. 
Existing project. Provides for a jetty about 
5,700 feet long on north side of entrance and a jetty 
8,000 feet long on south side (The south side 
plan of improvement currently provides for a 
6,500-foot long rubble stone jetty. The jetty length 
is 1,500-feet shorter than that provided in the 
authorizing document as a result of model studies 
conducted in 1971 to determine optimum length 
and alinement.); a channel through bar 18 feet 
deep and of such width as can be practically and 
economically obtained; for a channel 200 feet 
wide and 18 feet deep from deep water in bay to 
Miami Cove; and for initial dredging to 12 feet 
deep of a small-boat basin and approach thereto 
at Garibaldi, Oreg. Project also provides for improvement 
of Bayocean Peninsula, Oreg.; for 
navigation, by construction of sand and rockfill 
dike 1.4 miles long, on alinement extending 
between Pitcher Point and town of Bayocean. 
Mean lower low water is plane of reference. Tidal 
range between mean higher high water and plane 
of reference and extreme tidal range at entrance 
are 7.5 feet and about 13.5 feet, respectively. Estimated 
Federal cost of new work (1975) is $12,- 
166,000 exclusive of $2,839,799 for jetty 
rehabilitation. Hobsonville Channel portion of 
project is inactive and excluded from foregoing 
cost. Estimated cost (1955) of this portion is $99,- 
000. (See Table 37-B for authorizing legislation.) 
Local cooperation. Complied with for all work. 
River and Harbor Act of 1965 required local interests 
provide lands, easements, and right-ofway 
for construction and future maintenance and 
aids to navigation upon request of the Chief of 
Engineers, including suitable disposal areas, and 
necessary retaining dikes, bulkheads, and embankments 
therefor or the costs of such retaining 
works; hold United States free from damages; 
provide and maintain adequate public terminal 
and transfer facilities open to all equally; and 
provide and maintain depths in berthing areas 
and local access channels serving the terminals, 
including the 50-foot strip adjacent to pierhead 
lines, commensurate with depths provided in 
related project areas. Assurances and rights-ofway 
for construction of south jetty received 
December 6, 1967. 
Terminal facilities. At Garibaldi: A privately 
owned facility for shipping lumber and receiving 
logs, a public landing suitable for mooring 
fishing vessels, towboats, and other craft. Smallboat 
basin has adequate facilities for mooring 
fishing and recreational craft. At Bay City: A 
privately owned wharf used exclusively for 
receipt of fresh fish and shellfish. Near city of 
Tillamook: Several log rollways. Facilities considered 
adequate for existing commerce. 
Operations and results during fiscal year. New 
work: Project completed September 1974. 
Maintenance: U.S. Government plant dredged 
13,800 cubic yards of material. 
Condition at end of fiscal year. Under existing 
project except for construction of Hobsonville 
Channel portion, classified inactive, channels 
were completed in 1927, north jetty in 1933, improvement 
of Bayocean Peninsula in 1956, and 
small-boat basin in 1958. Rehabilitation of north 
jetty was accomplished September 1965. Construction 
of south jetty, initiated April 1969, is 
complete. The first phase contract between Sta. 
37-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
4+75 and 41+70 was completed in September 
1971, and the second phase for remaining work 
was completed in September 1974. Total Federal 
costs of existing project to June 30, 1975, were 
$18,322,345 of which $13,885,934 was for new 
work, $2,839,799 for jetty restoration, and $1,- 
596,612 for maintenance. In addition, $592,622 
was expended for new work and $6,450 for 
maintenance from contributed funds. 
17. UMPQUA RIVER, OREG. 
Location. Rises in Cascade Range, flows 
westerly about 120 miles, and empties into 
Pacific Ocean 180 miles south of Columbia River 
and 465 miles north of San Francisco Bay. (See 
NOAA Charts 18580 and 18584.) 
Previous projects. For details see page 2967 of 
Annual Report for 1898, and page 1732 of Annual 
Report for 1938. 
Existing project. A jetty on north side of entrance 
about 8,000 feet long, westerly from 
highwater line to the sea; a south jetty 4,200 feet 
long extending to a point 1,800 feet south of outer 
end of north jetty; dredging to provide a usable 
entrance channel 26 feet deep, and a river 
channel 22 feet deep and 200 feet wide, from 
mouth to Reedsport, a distance of about 11 miles 
with a turning basin at Reedsport 1,000 feet long, 
600 feet wide, and 22 feet deep; a channel 12 feet 
deep and 100 feet wide from deep water in the 
river to vicinity of docks in Winchester Bay with a 
mooring and turning basin 12 feet deep, 175 feet 
wide, and 300 feet long at inner end; and a 
channel 22 feet deep and 200 feet wide from main 
river channel near mile 8 to Gardiner, Oreg., and 
a turning basin of same depth, 500 feet wide, and 
800 feet long, opposite Gardiner. Project was 
modified in 1954 to provide a channel in 
Scholfield River, 12 feet deep at mean lower low 
water generally 100 feet wide from its confluence 
with Umpqua River to a point 0.5 mile below first 
railroad bridge, a distance of 2 miles, entrance to 
be widened to 300 feet in 500 feet. Mean lower low 
water is plane of reference. Tidal range between 
mean lower low water and mean higher high 
water at river mouth is 6.9 feet, and extreme 
range is about 11 feet. Federal cost of new work is 
$2,664,635, exclusive of $2,500,677 for jetty 
rehabilitation. Scholfield River channel portion 
of project is classified inactive and excluded from 
foregoing cost estimate. Estimated cost of this 
portion (1957), $54,000. (See Table 37-B for 
authorizing legislation.) 
Local cooperation. Complied with for all work 
except Scholfield River channel modification. 
River and Harbor Actof 1954 provides in connection 
with construction of Scholfield River 
channel, that local interests contribute in cash 
$10,000 toward cost of new work; furnish suitable 
disposal areas for initial work and future 
maintenance; and hold the United States free 
from damages. Submission of assurances was requested 
of Port of Umpqua, July 3, 1956. On April 
8, 1957, local interests report inability to furnish 
required cooperation. 
Terminal facilities. At Gardiner there is about 
650 feet of wharf frontage of which 60 feet is 
publicly owned. At river mile 8.6, Gardiner, there 
is an oil unloading facility owned by International 
Paper Co. for exclusive use of tanker barges. At 
Reedsport there is a privately owned mill dock for 
shipment of lumber, and a dock for receipt and 
shipment of river-run sand and gravel. Port of 
Umpqua owns one wharf with 456 feet of water 
frontage, of which 228 feet is usable for vessels 
and another with about 75 feet of water frontage 
which has not been used generally for commercial 
shipping. On Bolon Island across the river 
from Reedsport a wharf was constructed which 
has about 5 acres of open storage for lumber and 
available to all on equal terms. At Winchester 
Bay, 2 miles from river entrance, there is a 
public-landing float with a wooden pile and 
timber shore approach, and a privately owned 
wharf used by excursion and commercial fishing 
vessels. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance: U.S. hopper dredge Pacific 
removed 483,305 cubic yards of material from the 
entrance channel. 
Condition at end offiscal year. Existing project 
is complete. North jetty was completed in 1940. 
Extension to original south jetty was completed 
in 1938 and construction of a new training jetty on 
south side of entrance to replace original south 
jetty which was partially destroyed by storms 
was completed in 1951. Dredging a 22-foot 
channel from mouth of river to Reedsport was 
completed in 1941. Gardiner Channel and turning 
basin was completed in 1949 and Winchester 
Bay channel and mooring basin in 1956. Remaining 
under authorization is construction of 12-foot 
channel in Scholfield River, currently classified 
inactive and south jetty wave gage surveillance. 
Rehabilitation of south jetty was completed 
August 1963. Total Federal costs for existing 
project, June 30, 1975 were $12,064,894 of which 
$2,664,635 was for new work, $2,500,677 for jetty 
restoration, and $6,899,582 for maintenance. In 
addition, $276,500 was expended for new work 
from contributed funds. 
18. WILLAMETTE RIVER ABOVE 
PORTLAND AND YAMHILL 
RIVER, OREG. 
Location. Willamette River rises in Cascade 
Range in southwestern Oregon, flows northerly, 
37-12

PORTLAND, OREG., DISTRICT 
and empties into Columbia River about 100 miles 
from the sea. Its length from source of Middle 
Fork is about 294 miles. (See NOAA Chart 18526 
and Geological Survey map, State of Oregon.) 
Yamhill River rises in Coast Range, flows easterly, 
and empties into Willamette River about 42 
miles above Portland. Its length from source of 
South Fork is about 52 miles. 
Previous projects. For details see page 1997 of 
Annual Report for 1915, and page 1754 of Annual 
Report for 1938. 
Existing project. Provides for improvement of 
Willamette River between Portland (mile 14) and 
Oregon City (mile 26) by a channel 8 feet deep at 
low water, 200 feet wide below Cedar Island and 
150 feet wide thence to Oregon City; such channel 
improvement and contraction works as may be 
necessary to secure with streamflow regulation, 
controlling depths of 6 feet at low water and of no 
prescribed width, from Oregon City to mouth of 
Santiam River (mile 108.5), 5 feet from that point 
to Albany (mile 120), 2.5 to 3.5 feet deep from 
Albany to Corvallis (mile 132), and for necessary 
snagging between Corvallis and Eugene (mile 
185). Project also provides for a channel in 
Yamhill River 4 feet deep at low water and 60 feet 
wide from its mouth to McMinnville (18 miles) 
secured by means of a lock and dam near 
Lafayette and by removal of obstructions. Section 
of Willamette River in vicinity of Willamette 
Falls at Oregon City is covered by Improvement 
No. 19. For Willamette River below falls at 
Oregon City ordinary fluctuation of stage of 
water is 15 feet and extreme fluctuation due to 
flood conditions 35 to 50 feet. Above Oregon City 
ordinary fluctuation is 12 to 20 feet and extreme 
is 20 to 27 feet. For Yamhill River ordinary fluctuation 
is 35 feet and extreme 48 feet. Tidal 
changes vary from about 2.5 feet at mouth of 
Willamette to zero, 26 miles above mouth. Estimated 
cost of new work (1971) is $4,790,000, including 
$4,175,000 for deferred work. (See Table 
37-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Between Ross Island 
Bridge at Portland and Willamette Falls at 
Oregon City: Privately owned mill docks, sand 
and gravel wharves, a cement loading facility, a 
small shipyard, and oil-receiving stations. Above 
the falls there are privately owned landings including 
a facility at Pulp Siding (3 miles above 
the falls) with rail and water connections for shipment 
of clay and receipt of papermill products by 
barge. At Wilsonville and Newberg there are 
sand and gravel facilities. At Salem there is a 
420,000 gallon fuel tank which is serviced by 
tanker barges. At numerous locations as far as 
Corvallis (river mile 132) there are log rollways 
with water and rail or truck connections, to 
facilitate moving logs to mills in lower 
Willamette and Columbia Rivers. At Oswego 
there is a dock for the receipt of limerock used in 
the manufacture of cement. Facilities considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: A total of 35,604 cubic yards of 
material was removed from river channel by contract 
dredging. Releases of stored water from 
Fern Ridge, Cottage Grove, Dorena, Detroit, 
Lookout Point, Hills Creek, Cougar, Fall Creek, 
Green Peter, and Blue River Lakes aided 
materially during low water periods in providing 
sufficient depths for existing traffic. For information 
on reservoir release see reports covering 
these reservoirs under flood control and multiple 
purpose power projects. 
Condition at end offiscal year. Existing project 
is about 18 percent complete. The 8-foot channel 
between Portland and Oregon City and 2.5- to 3.5- 
foot channel between Oregon City and Albany 
were completed in 1939. The 2.5- to 3.5-foot 
channel between Albany and Corvallis was completed 
in 1945. Remaining work required to complete 
project consists of construction of such contraction 
works and channel improvements as 
may be necessary, with streamflow regulation, to 
secure controlling depths of 6 feet at low water 
from Oregon City to mouth of Santiam River, and 
5 feet from that point to Albany. This remaining 
portion has been placed in the deferred category. 
Due to lack of use by commercial traffic for which 
facilities were provided, operation of Yamhill 
lock was discontinued February 7, 1954, and the 
lock and adjacent property reported surplus and 
turned over to Yamhill County January 16, 1959. 
Total Federal costs of existing project, June 30, 
1975, were $17,490,975 of which $615,170 was for 
new work, and $16,875,805 for maintenance. In 
addition $106,433 expended between September 
24, 1900, and June 30, 1935, on operating and care 
of improvement under provisions of permanent 
indefinite appropriations for such purposes. Additional 
$7,500 expended from contributed funds 
for maintenance and $299,900 emergency relief 
administration funds for new work. 
19. WILLAMETTE RIVER AT 
WILLAMETTE FALLS, OREG. 
Location. Locks and dam covered by this project 
are at Willamette Falls, a rocky reef in 
Willamette River at Oregon City, Oreg., about 26 
miles above mouth of river. 
Existing project. Provides for construction of a 
new single-lift main lock and a guard lock each 
37-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
with clear dimensions of 56 by 400 feet and a 
minimum depth over sills of 9.5 feet, to replace 
existing facilities which were provided for by 
purchase, rehabilitation, and deepening to 6 feet 
at low water of existing canal and locks and 
separation of canal from waterpower intake by 
construction of a concrete division wall. Total 
length of existing canals and locks is about 3,500 
feet. Principal features of existing canal and 
locks at Willamette Falls are set forth in Table 37- 
D.
Ordinary fluctuation of stage of water above 
locks is 12 feet and extreme, due to flood conditions, 
20 feet. Below locks, ordinary fluctuation 
is 15 feet and extreme 50 feet. Estimated Federal 
cost (1971) is $19,978,000, which includes $378,- 
000 for completed modifications. (See Table 37-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Crown Zellerbach Corp. 
has a timber wharf about 850 feet long, extending 
to and supported by concrete division wall built in 
lock canal by United States. This wharf is used 
for receiving mill supplies and shipping paper 
and paper products. 
Operations and results during fiscal year. 
Maintenance; Normal operation and 
maintenance continued. 
Condition at end of fiscal year. Existing canal 
and locks originally constructed by private interests 
in 1873 were purchased by the United 
States in April 1915 for $375,000. Final report on 
purchase and rehabilitation of canal and locks is 
in Annual Report for 1923, when project was 
reported 98 percent complete. Replacement of 
gates Nos. 6 and 7 was completed August 1967 under 
minor rehabilitation funds. Existing locks 
and grounds are in fair condition and in continuous 
operation except when flooded out by 
high water or undergoing repair. Facilities are 
obsolete and inadequate for existing traffic. No 
construction work has been done on lock and 
guard lock, which was authorized to replace existing 
facilities by Flood Control Act of 1939, and 
River and Harbor Act of 1945. This portion of the 
project has been reclassified "deferred". 
20. YAQUINA BAY AND HARBOR, 
OREG. 
Location. Bay is on Oregon coast, 113 miles 
south of mouth of Columbia River. (See NOAA 
Charts 18580 and 18581.) 
Previous projects. For details see Annual 
Report for 1893, part 4, page 3314, and Annual 
Report for 1938, page 1736. 
Existing project. Two high tide rubblemound 
jetties at entrance, north jetty 7,000 feet, and 
south jetty 8,600 feet long; a spur jetty on channel 
side of south jetty 4,700 feet from its sea end, 800 
feet long; five groins channelward from south jetty; 
channel 40 feet deep for a general width of 400 
feet across bar and at outer end of entrance 
channel; a channel 30 feet deep and 300 feet wide 
to a turning basin of same depth, 900 to 1,200 feet 
wide and 1,400 feet long, and a channel 18 feet 
deep and 200 feet wide from 30-foot channel at 
about mile 2.4, thence upstream to abandoned 
railroad terminus at Yaquina, a distance of about 
4.5 miles. Project also provides for a small-boat 
mooring basin at Newport, Oreg. Mean lower low 
water is plane of reference. Tidal range between 
mean higher high water and plane of reference 
and extreme tidal range are 8.1 and 11.5 feet, 
respectively. Federal cost of new work (1975) is 
$16,182,987. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. At McLean Point, on north 
side of bay, about 2 miles from entrance, Yaquina 
Bay Dock & Dredge Co., Inc., has two berths 
capable of serving ocean-going vessels, one 420 
feet long, the second 450 feet long. At the time the 
second berth was dredged, a retaining wall and 
fill of 6 acres was constructed adjacent to deep 
water. The company now has 17 acres of filled 
land adjacent to deep water, and of this total, 7 
acres was constructed in 1956-57. This facility 
has necessary carriers and lift trucks for handling 
lumber cargoes, and is open to all on equal 
terms. Port of Newport has a public wharf with 
300 feet of frontage for servicing fishing boats. In 
addition, Port of Newport maintains 340 berths 
for mooring commercial and sport fishing 
vessels. There are several seafood companies on 
the bay which have their own facilities for handling 
fresh fish and crab. Supplies and petroleum 
products are readily available for small vessels. 
On south side of bay about 1.5 miles above entrance, 
Newport Dock Co. maintains a wharf, 
bulkhead, and dolphins for loading ocean-going 
lumber barges. These facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: U.S. hopper dredges Harding 
and Pacific worked at various times throughout 
the season removing a total of 671,763 cubic yards 
of material from river channel. 
Condition at end offiscal year. Existing project 
as originally authorized was completed in May 
1952. Restoration of jetties was completed in 1934 
and extension of north jetty 1,000 feet seaward 
was completed in 1940. Construction of mooring 
basin at Newport and dredging of channel and 
turning basin to project dimensions were completed 
during fiscal year 1949. Restoration of 
37-14

PORTLAND, OREG., DISTRICT 
north jetty was again accomplished in 1956. Under 
modification of July 3, 1958, extension of 
north jetty was completed in September 1966, 
dredging of 40-foot bar channel and 30-foot river 
channel was completed in October 1968, and extension 
of south jetty was completed in June 1972. 
Total Federal costs for existing project were $26,- 
252,076 of which $18,534,733 was for new work 
(including $53,277 Section 107), $12,005 for 
rehabilitation, and $7,705,338 for maintenance. 
In addition, $729,168 of contributed funds was expended 
for new work. 
21. YOUNGS BAY AND YOUNGS 
RIVER, OREG. 
Location. Youngs River is a tributary of the 
lower Columbia River. It empties into Youngs 
Bay south and west of Astoria, Oreg., about 10 
miles above the mouth of the Columbia River. The 
total length of the river is about 20 miles, of which 
the lower 8 miles are tidal. (See NOAA Chart No. 
18521.) 
Existing project. A channel 10 feet deep and 150 
feet wide, from the Columbia River to the foot of 
Haven Island, a distance of about 2.5 miles across 
Youngs Bay and 4 miles in Youngs River. 
Modified project provides for a channel 10 feet 
deep by 150 feet wide, from the existing channel 
in Youngs Bay to the mouth of Lewis and Clark 
River, thence 100 feet wide to the end of the 
proposed project a distance of about 4.4 miles. 
The plane of reference is mean lower low water. 
The tidal range between mean lower low water 
and mean higher high water is about 8 feet, and 
extreme tidal range about 13 feet. Estimated 
Federal cost is $267,000 (1974). (See Table 37-B 
for authorizing legislation.) The latest published 
map is in the project document. 
Local cooperation. River and Harbor Act of 
1965 provides that local interests be required 
to: provide lands, easements, and rights-of-way 
required for construction and subsequent 
maintenance of the project; hold and save the United 
States free from damages; construct, operate 
and maintain adequate mooring facilities, open to 
all on equal terms; and accomplish without cost to 
the United States such alterations of utility 
facilities as required for project. In addition, contribute 
$1,000 for non self-liquidating local costs. 
Terminal facilities. There are no public terminals 
or wharves. Pacific Power and Light Company 
owns and operates a small oil-receiving 
wharf in connection with its power plant on the 
north side of Youngs Bay. Astoria Yacht Club has 
moorage immediately upstream from old U.S. 
101 Highway Bridge. Next upstream is Bumble 
Bee Seafood Company shipyard for construction 
and repair of fishboats. A log dump is on south 
side of bay above bridge. Two more log dumps are 
located farther up Youngs River beyond upstream 
end of project. 
Operations and results during fiscal year. A reevaluation 
of Lewis and Clark connecting 
channel was underway in FY 1975. 
Maintenance: Project condition surveys were 
conducted in August 1974. 
Condition at end of fiscal year. The existing 
project was completed in 1938. Modified project 
planning for dredging and clearing is underway. 
22. PROJECT CONDITION SURVEYS 
See Table 37-E. 
23. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 37-F. 
24. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to section 107, 
Public Law 86-645 (preauthorization) 
See Table 37-G. 
Alteration of Bridges 
25. OTHER AUTHORIZED 
BRIDGE ALTERATIONS 
See Table 37-H. 
Flood Control 
26. APPLEGATE LAKE, ROGUE 
RIVER BASIN, OREG. 
Location. In Jackson County, Oreg., on Upper 
Applegate River, a tributary of Rogue River, at 
river mile 45.7, about 23 airline miles southwest 
of Medford, Oreg. 
Existing project. Plan provides for .a rockfill 
embankment dam, 233 feet high from streambed 
to crest with an overall length of 1,200 feet. A 
gate-controlled concrete chute-type spillway on 
the right abutment, and a regulating outlet conduit, 
and intake tower with multilevel intakes on 
the left side of valley floor. Lake, 4.5 miles long 
will provide 75,000 acre-feet of usable storage for 
flood control and water conservation utilization. 
Project will control runoff from a drainage area 
of 223 square miles. In addition to flood control, 
reservoir will be operated to provide irrigation, 
fish and wildlife enhancement, water quality control, 
and recreation benefits. Estimated cost of 
project (1975) is $63,000,000. Excluded from the 
estimate of $63,000,000 is $5,448,000 for recreation 
facilities which will be funded and developed 
37-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
by the U.S. Forest Service. (See Table 37-B for 
authorizing legislation.) 
Local cooperation. Authorizing act requires 
that State of Oregon take action, prior to construction, 
to insure maintenance in stream of 
flows to be released for fishery. In addition, costs 
allocated to irrigation would have to be repaid in 
a manner and to an extent consistent with 
Reclamation laws and policies. Oregon Department 
of Fish and Wildlife made filing May 31, 
1962 with State Engineer for water rights for use 
of stored water and natural flows for fish habitat 
improvement in amounts and at times specified 
in project authorization. U.S. Bureau of Reclamation 
is currently making a feasibility study of 
Applegate Irrigation Division. Local interests 
have furnished all local cooperation specified by 
the Flood Control Act 1970. The assurances were 
approved by the Secretary of the Army on 8 May 
1975. 
Operations and results during fiscal year. Environmental, 
turbidity and economic studies 
were being conducted. Initial land acquisition 
funds were received in March 1974 and acquisition 
work continues. 
Condition at end of fiscal year. Preconstruction 
engineering and studies continue. Design 
memorandums approved are: site selection; 
hydrology and meteorology; relocations; general; 
real estate; land requirements plan-public use; 
Lower Applegate Road and detour supplement; 
spillway, outlet works and fish facilities; and 
clearing. Final Environmental Impact Statement 
and Supplement No.1 were filed with Council 
on Environmental Quality February 15, 1972 
and July 21, 1972, respectively. Preparation of 
plans and specifications for initial road relocation 
contract is underway. 
27. BEAVER DRAINAGE DISTRICT, 
COLUMBIA COUNTY, OREG. 
Location. In Columbia County, Oreg., north of 
town of Clatskanie and extends along Columbia 
River and Bradbury Slough between river miles 
49.7 and 55.4. 
Existing project. The project originally provided 
for reconstruction of 10.4 miles of existing 
levee; construction of 0.9 mile of new levee; construction 
of 2.5 miles stone revetment, one pumping 
plant and 1.1 miles of diversion canal. The 
Flood Control Act of May 17, 1950 authorized additional 
improvements. The present plan includes 
raising and strengthening the existing 
levee and installing toe drains where required; 
removing two antiquated pumping stations from 
the levee section; constructing a new pumping 
station with increased capacity; remove the existing 
Tank Creek tide box structure; and replace 
the Tank Creek tide box with a fresh water intake. 
Estimated Federal cost is $2,190,000. (See 
Table 37-B for authorizing legislation.) 
Local cooperation. Flood Control Act of 1950, 
provides local interests furnish lands and rightof-
way; make necessary highway, highway 
bridge, and utility alterations; hold the United 
States free from damages; and maintain and 
operate works after completion. In addition, local 
interests must agree to comply with the requirements 
of the Uniform Relocation Assistance 
and Land Acquisition Policies Act of 1970, Title 
VI, of the Civil Rights Act of 1964, and Section 
221 of the Flood Control Act of 1970, Public Law 
91-611. A resolution of formal assurances for local 
cooperation was signed by the Board of Supervisors 
for Beaver Drainage District on 30 June 
1966 and accepted by the Portland District 
Engineer on 18 November 1966. Drainage District 
officials by letter dated 4 March 1970, affirmed 
that their district could meet all requirements 
of local cooperation not later than two 
years from the date of that letter. Formal 
assurances of local cooperation have been furnished 
and accepted by the Portland District 
Engineer. In addition, a reaffirmation was made 
in a 30 October 1973 letter to fulfill required 
assurances. Estimated costs for all requirements 
of local cooperation under terms of project 
authorization are $426,000 (1975). 
Operations and results during fiscal year. 
Preconstruction planning was completed in April 
1974 when the revised design memorandum was 
published. An A-E contract for plans and 
specifications was awarded on 20 May 1975. 
Pump supply contract was awarded 2 June 1975. 
Condition at end of fiscal year. The work 
originally authorized was completed in 1939. 
Design memorandum for the improvements 
authorized by the Flood Control Act of 1950 was 
completed in 1962 and updated in 1974. Sponsor 
has furnished schedule for acquiring the 
remainder of the rights-of-way and utility 
relocations of the project. 
28. BEECH CREEK, 
MT. VERNON, OREG. 
Location. Mt. Vernon is located at the junction 
of U.S. Highways 395 and 26. Beech Creek flows 
through Mt. Vernon to its confluence withl the 
John Day River just below town. The area around 
Mt. Vernon is mountainous with nearly all 
development located in the relatively narrow 
valleys. 
Existing project. Detailed Project Report was 
approved by Chief of Engineers November 1973. 
Solution to the flood problem includes channel 
37-16

PORTLAND, OREG., DISTRICT 
enlargement, levees and bank revetment for approximately 
3,000 feet through the City of Mt. 
Vernon. Channel improvements necessitate 
replacement of the Ingle Road Bridge and Grant 
County has given written assurance to replace 
this structure. Channel improvement design includes 
a drop structure with stilling basin and 
fish passage facilities. The planting of trees at appropriate 
locations will also be a project feature. 
Estimated Federal cost as of June 1974 is $484,- 
000. (See Table 37-B for authorizing legislation.) 
Local cooperation. Section 205 of the 1948 Flood 
Control Act requires that local interests furnish 
lands and rights-of-way; make necessary 
highway and utility alterations; hold theUnited 
States free from damages; and maintain and 
operate completed work. Estimated local cost 
April 1973 is $48,000. By letter dated 19 June 
1975, the City of Mt. Vernon, Oregon, withdrew 
sponsorship of this project, due to their inability 
to provide rights-of-way required for project construction. 
Operations and results during fiscal year. Additional 
studies were made to arrive at an alternative 
which would reduce cost to City of Mt. Vernon. 
All alternatives which resulted in cost to city 
became economically infeasible. 
Condition at end of fiscal year. Plans are being 
made to terminate project. 
29. BLUE RIVER LAKE, OREG. 
Location. On Blue River, a major tributary of 
McKenzie River, 1.7 miles above confluence of the 
two streams at the confluence of Quartz Creek 
and Blue River and about 38 miles easterly of Eugene, 
Oreg. 
Existing project. A gravel-fill embankment 
dam 1,329 feet long at crest including spillway 
and 319 feet above the lowest point of the general 
foundation. A concrete gravity chute-type 
spillway with two gates is located on left abutment. 
Outlet works are in left abutment. On left 
shore of reservoir an earth-and-gravel fill embankment, 
about 1,535 feet long and 70 feet high, 
closes a low saddle between Blue River and 
McKenzie River. Project controls runoff from 
drainage area of 88 square miles. Reservoir 
provides 85,000 acre-feet of usable flood control 
storage and is operated as a unit of coordinated 
reservoir system to protect Willamette River 
Valley and increase low waterflows for navigation 
and other purposes. Recreation facilities are 
provided by the U.S. Forest Service under a 
Memorandum of Agreement. Estimated cost of 
project (1975) is $32,038,225. (See Table 37-B for 
authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
Work: Rehabilitation of the viewpoint, irrigation 
system and landscaping, awarded in January 
1973, was completed August 1974. Maintenance: 
Normal operation and maintenance work performed. 
Freshets regulated by Blue River Lake 
project on Blue River, a major tributary of 
McKenzie River, are shown in Table 37-I. 
Condition at end of fiscal year. Project is complete. 
Construction of dam and appurtenant 
works was initiated in May 1963 and placed in 
useful operation October 1968. Settlement of 
claims was completed in May 1974. 
30." CASCADIA LAKE, OREG. 
Location. In Linn County, Oreg., at river mile 
42.2 on South Santiam River, about 30 miles 
southeast of Albany, Oreg. 
Existing project. Plan provides for a rockfill 
embankment dam, 267 feet high from streambed 
to crest and 1,170 feet long, a gate-controlled concrete 
chute-type spillway, located on the right 
abutment and a regulating outlet works located 
on the left abutment. Reservoir will provide 145,- 
000 acre-feet of usable flood control storage and 
will control 193 square miles of drainage area. 
Estimated cost of project (1975) is $104,000,000. 
(See Table 37-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Design Memorandums in various stages of completion 
were: general, 95 percent; relocations, 
75 percent; Oregon State Hwy. Dept. No. 20 
bypass and detour, 12 percent; recreation 
resources appendix, 55 percent; real estate, 25 
percent; and utilities, 5 percent. 
Condition at end of fiscal year. Under advance 
engineering, preparation of design memorandums 
is in progress. Those design memorandums 
completed are: site selection and supplement 
No. 1; and hydrology and meteorology. Final environmental 
impact statement was filed with 
CEQ in August 1971. The decision to relocate 
dam site necessitated a supplement to the approved 
site selection design memorandum. 
Further work will be scheduled when funds 
become available. 
31. COTTAGE GROVE LAKE, OREG. 
Location. On Coast Fork of Wiliamette River, 
29 miles from mouth. Coast Fork rises in Douglas 
County, Oreg., on western slope of Cascade Range 
and northern slope of Calapooia Range, flows 
north for 49 miles, and unites with Middle Fork to 
form main Willamette River. 
37-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Existing project. An earthfill dam, 1,750 feet 
long at crest, 114 feet high from lowest point of 
the general foundation, a concrete gravity free 
overflow spillway 264 feet long near the right 
abutment, and a concrete gravity non-overflow 
section 96 feet long forming the right abutment. 
Total length of dam is 2,110 feet. Outlet works, 
consisting of three gate-controlled conduits, pass 
through spillway section. Reservoir provides 30,- 
060 acre-feet of usable flood control storage and 
controls runoff of drainage area of 104 square 
miles. Project is operated as a unit of coordinated 
reservoir system to protect Willamette River 
Valley and increase low waterflow for navigation 
and other purposes. Estimated total Federal cost 
of project (1975) is $5,851,997 of which estimated 
Federal cost of construction for additional recreation 
facilities at completed project is $2,580,000 
(1975). (See Table 37-B for authorizing legislation.) 
Local cooperation. Estimated costs of local 
cooperation on basis of cost-sharing for recreation 
facilities is $1,073,000. 
Operations and results during fiscal year. New 
work: A contract to construct a water distribution 
system, awarded in April 1973, was completed 
August 1974. Maintenance: Ordinary 
maintenance was accomplished as required. 
Freshets regulated by Cottage Grove Lake on 
Coast Fork Willamette River are shown in Table 
37-I. 
Condition at end of fiscal year. Construction of 
project initiated August 1940 was completed 
April 1952 except for construction of additional 
recreation facilities. Dam and reservoir have 
been in continuous operation since September 
1942. Planning of additional recreation facilities 
is under way. 
32. COWLITZ COUNTY CONSOLIDATED 
DIKING IMPROVEMENT DISTRICT 
NO. 2, WASH. 
Location. In southwest corner of Cowlitz County, 
Wash., at confluence of Lewis River with 
Columbia River and extends downstream along 
Columbia River between miles 80.5 and 86.5. 
Existing project. Provides for raising and 
strengthening existing levees and construction of 
new levees adjacent to town of Woodland to 
provide added protection. Estimated Federal 
cost (1975) is $1,658,000. (See Table 37-B for 
authorizing legislation.) 
Local cooperation. Flood Control Act of 1950 
provides local interests furnish lands and rightsof-
way; make necessary highway, highway 
bridge, and utility alterations; hold the United 
States free from damages; and maintain and 
operate completed works. Estimated costs of all 
requirements of local cooperation under terms of 
project authorization were $85,000 (1971). 
Operations and results during fiscal year. New 
work: Operations manual being prepared. 
Condition at end of fiscal year. Construction on 
existing project begun September 1967 was completed 
May 21, 1971 except for levee improvements 
along the right bank of the Lewis 
River completed 14 June 1974. 
33. DAYS CREEK LAKE, OREG. 
Location. In Douglas County on South Umpqua 
River, 60 miles from its junction with North 
Umpqua River, 172 miles from mouth of Umpqua 
River, and one mile upstream from the Town 
of Days Creek. 
Existing project. Plan provides for a gravel embankment 
dam, 254 feet high from lowest point of 
foundation to crest and 1,031 feet long; a concrete 
gravity spillway on the right abutment with five 
electrically operated tainter gates; and 
regulating outlet works under the center of the 
dam. Reservoir will provide for 260,000 acre-feet 
of multiple-use storage for flood control, irrigation, 
fishery enhancement, water supply, recreation 
and water quality improvement and will control 
640 square miles of drainage area. Estimated 
Federal cost of project is $175,000,000 (1975). 
(See Table 37-B for authorizing legislation.) 
Local cooperation. Local interests will be required 
to adopt, prior to project construction, 
land-use regulations which would prevent encroachment 
of future development on the 
floodway. Douglas County Commission has indicated 
willingness to adopt appropriate land-use 
regulations prior to project construction. Costs 
allocated to irrigation would have to be repaid in 
a manner and to an extent consistent with 
Reclamation laws and policies. All construction, 
operation and maintenance, replacement and interest 
costs allocated to water supply will have to 
be reimbursed. Assurances of present intent to 
make future use of water stored in Days Creek 
Lake have been received from potential water 
users. In accordance with Water Resources Project 
Recreation Act of 1965 (PL 89-72). a non- 
Federal public entity must assume 50 percent of 
the separable costs of project recreational lands 
and facilities for construction and 100 percent for 
the annual operation, maintenance and replacement 
costs, except that, as amended by Water 
Resources Development Act of 1974, only 25 percent 
of separable costs for fish enhancement are 
reimbursable. Total estimated separable costs for 
project recreational lands and facilities for construction 
are $7,812,000 (1975) of which an estimated 
$3,906,000 would have to be reimbursed. 
Douglas County and the City of Roseburg hav( 
37-18

PORTLAND, OREG., DISTRICT 
provided preliminary assurances that they would 
participate in planned recreation development. 
Operation and results during fiscal year. Phase 
I study is in progress. 
Condition at end of fiscal year. Final EIS was 
filed with CEQ 6 October 1972. General Design 
Memorandum Phase I is 12 percent complete. 
34. DORENA LAKE, OREG. 
Location. On Row River, Oreg., 7 miles from 
mouth. Row River rises in Lane County on 
western slope of Cascade Range, flows northwest 
for 19 miles, and enters Coast Fork of Willamette 
River 19.5 miles above mouth. 
Existing project. An earthfill embankment 
dam, 3,352 feet long at crest and 145 feet high 
from lowest point of the general foundation. Concrete 
gravity free-overflow spillway, 200 feet 
long, forms right abutment. Outlet works on five 
slide-gate-controlled conduits pass through 
spillway section. Reservoir provides 70,500 acrefeet 
of usable flood control storage and controls 
runoff of 265 square miles, practically entire 
drainage area tributary to Row River. Project is 
operated as a unit of coordinated reservoir system 
to protect Willamette River Valley and increase 
low waterflows for navigation and other purposes. 
Estimated total Federal cost of project 
(1975) is $15,485,000 of which Federal construction 
cost of additional recreation facilities at completed 
project is estimated at $1,956,000 (1975). 
(See Table 37-B for authorizing legislation.) 
Local cooperation. Estimated costs of local 
cooperation on basis of cost-sharing for recreation 
facilities is $1,428,000. 
Operations and results during fiscal year. 
Maintenance: Project was in continuous,operation 
with additional maintenance accomplished 
as required. Freshets regulated by Dorena Lake 
project on Row and Coast Fork Willamette Rivers' 
are shown in Table 37-I. 
Condition at end of fiscal year. Co hstruction of 
project initiated June 1941 was completed October 
1952 except for construction of additional 
recreation facilities authorized in 1954. Dam and 
reservoir have been in continuous operation since 
November 1949. 
35. ELK CREEK LAKE, ROGUE 
RIVER BASIN, OREG. 
Location. In Jackson County, Oreg., at river 
mile 1.7 on Elk Creek, a tributary of Rogue River, 
about 26.5 miles northerly from Medford, Oreg. 
Existing project. Plan provides for a rock and 
gravel embankment dam, 233 feet high from 
streambed to crest with an overall length of 2,685 
feet. A gate-controlled concrete chute-type 
spillway on the right abutment, and a regulating 
outlet tunnel and intake tower with multilevel intakes 
will be in left abutment. Reservoir 6.2 miles 
long will provide 95,000 acre-feet of usable 
storage for flood control and water conservation 
utilization. Project will control runoff from a 
drainage area of 127 square miles. Reservoir will 
be operated to provide future municipal and industrial 
water supply, irrigation, fish and 
wildlife enhancement, water quality control, and 
recreation benefits. Estimated Federal cost of 
project (1975) is $64,400,000. (See Table 37-B for 
authorizing legislation.) 
Local cooperation. Authorizing act requires 
that State of Oregon take action, prior to construction, 
to insure maintenance in stream of flow 
to be released for fishery. In addition, costs 
allocated to irrigation would have to be repaid in 
a manner and to an extent consistent with 
Reclamation laws and policies. On February 24, 
1966 State of Oregon Water Resources Board 
filed for withdrawal rights of 25 c.f.s. to maintain 
minimum flow for fish. U.S. Bureau of Reclamation 
has completed feasibility study for irrigation 
of Medford Division from Lost Creek and Elk 
Creek Lakes, and will determine repayment requirements 
by local interests. 
Operations and results during fiscal year. New 
work: Stockpiling of materials for the main 
dam construction was continuing. The bids for 
the main dam were opened 3 April 1975, with the 
apparent low bidder, Perini Corp. and Hensel 
Phelps submitting a bid of $39,680,759. Award is 
being delayed because of a lack of support by the 
State of Oregon, Water Resources Board. 
Condition at end of fiscal year. Construction of 
the project was initiated in July 1972. Final environmental 
statement was filed with CEQ June 
15, 1972. Award of main dam contract is pending. 
36. FALL CREEK LAKE, OREG. 
Location. On Fall Creek, a tributary of Middle 
Fork Willamette River, about 7 miles above confluence 
of the streams and about 19 miles 
southeasterly of Eugene, Oreg. 
Existing project. An earth-and-gravel fill embankment 
about 5,100 feet long at crest and 193 
feet high from lowest point of the general foundation. 
A gated concrete gravity spillway is in left 
abutment. Outlet is in right abutment. Reservoir 
provides 115,000 acre-feet of usable flood control 
storage and is operated as a unit of coordinated 
reservoir system to protect Willamette River 
Valley and increase low waterflows for navigation 
and other purposes. Estimated total Federal 
cost of project (1975) is $22,754,833 which includes 
an estimated $1,475,000 for additional 
37-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
recreation facilities at completed project. (See 
Table 37-B for authorizing legislation.) 
Local cooperation. Estimated costs of local 
cooperation on basis of cost-sharing for recreation 
facilities is $980,000. 
Operations and results during fiscal year. New 
work: Plans and specifications for Sky Camp 
sewage disposal system are 50 percent complete; 
for the sewage collection and treatment system 
they are 10 percent complete. Construction is 
scheduled for FY 1976. Maintenance: Normal 
operation and maintenance carried on. Freshets 
regulated by Fall Creek Lake Project on Fall 
Creek, a tributary of Middle Fork Willamette 
River, are shown in Table 37-I. 
Condition at end of fiscal year. Construction of 
project began May 1962 and was essentially complete 
November 1965. Reservoir storage for flood 
control was effective October 1965. Planning of 
additional recreation facilities is underway. 
37. FERN RIDGE LAKE, OREG. 
Location. On Long Tom River, 23.6 miles from 
the mouth. Long Tom River rises in Lane County, 
Oreg., on eastern slope of Coast Range, flows 
north for 50 miles, and enters Willamette River 
147 miles above its mouth. 
Existing project. A main dam, 6,624 feet long at 
crest and 49 feet high from lowest point of the 
general foundation and two auxiliary dikes, 915 
and 3,929 feet long, along northeasterly boundary 
of lake. Main dam consists of an earthfill embankment 
dam, 6,330 feet long and a concrete gravity 
spillway near left abutment with a non-overflow 
structure, 46 feet long, containing outlet works, 
and an overflow structure, 248 feet long, controlled 
by six automatic gates. Project includes 
rectification of channel of Long Tom River. 
downstream of dam. Reservoir provides 110,000 
acre-feet of usable flood control storage and controls 
runoff of tributary drainage area of 275 
square miles. Reservoir protects Long Tom River 
Valley and is operated as a unit of coordinated 
reservoir system to protect Willamette River 
Valley generally and to increase low waterflows 
for navigation and other purposes. Dam was 
originally constructed in 1941 to height of 47 feet. 
Provision of additional storage for flood control 
was obtained in 1965 by raising embankments 2 
feet to 49 feet above lowest point of the general 
foundation. Estimated Federal cost of project 
(1975) is $11,384,000 including $136,482 cost of 
raising dam and $6,888,000 cost of construction of 
recreation facilities at completed project. (See 
Table 37-B for authorizing legislation.) 
Local cooperation. Estimated costs of local 
cooperation on basis of cost-sharing for recreation 
facilities is $3,596,000. 
Operations and results during fiscal year. New 
work: Work at Krugur Park completed 15 May 
1975. Maintenance: Ordinary operation of dam 
and reservoir being performed. Freshets 
regulated by Fern Ridge Lake project on Long 
Tom River are shown in Table 37-I. 
Condition at end of fiscal year. Construction of 
project initiated April 1940 was completed 
August 1951, except for construction of additional 
recreation facilities authorized in 1954 
and provision of additional storage for flood control 
authorized in 1962 and completed April 1965. 
Dam and reservoir have been in continuous 
operation since December 1941. Planning for additional 
recreation facilities continues. 
38. LOWER COLUMBIA RIVER 
BASIN, OREG. AND WASH. 
Location. On Columbia River and minor 
tributaries, channels, and sloughs, between 
Sandy River, Oreg., about 15 miles east of Vancouver, 
Wash., and mouth of Columbia River. 
Existing project. Plan for bank protection 
work, improvements to existing projects, and 
construction of flood control works in Lower 
Columbia River Basin provides for new construction 
and supplementing and extending projects 
constructed in Lower Columbia River Basin under 
authority of 1936 Flood Control Act: (a) 
Lower Columbia River bank protection, Oregon 
and Washington, provides for bank protection 
works at 96 locations on Columbia River and 
tributaries between Sandy River and mouth of 
Columbia River, totaling about 224,145 linear 
feet. Estimated total Federal cost (1975) is $16,- 
100,000 and non-Federal cost is $220,000; (b) See 
Table 37-J on Levees and Improvements to Existing 
Works; (c) Lower Columbia River Basin 
levees at new locations, Oregon and Washington, 
provides for construction of flood control works 
at: Washougal area, Clark County, Washington, 
about 5.5 miles of levee and appurtenant works at 
an estimated Federal cost (1972) of $1,802,294, 
and non-Federal cost at $98,000; and Vancouver 
Lake area in vicinity of Vancouver, Washington, 
about 18 miles of levee and appurtenant works at 
an estimated Federal cost (1975) of $12,600,000 
and non-Federal cost at $583,000. Total estimated 
Federal costs (1975) are $14,402,294 and non- 
Federal costs $681,000. Following locations 
reclassified and excluded from foregoing estimate: 
Kalama River south area, Cowlitz County, 
Wash., inactive, Federal cost estimate (1969) 
of $742,000 and non-Federal cost of $22,000; 
Clatskanie River area, Columbia County, Oreg., 
inactive, Federal cost estimate (1959) of $183,000 
and non-Federal cost at $11,000; and Hayden 
Island, Multnomah County, Oreg., inactive, estimated 
Federal cost (1960) of $615,000 and non- 
Federal at $64,000. Approved (1975) Federal cost 
37-20

PORTLAND, OREG., DISTRICT 
estimate for all active work under project, Lower 
Columbia River Basin, Oreg. and Wash., is $45,- 
028,000. (See Table 37-B for authorizing legislation.) 
Local cooperation. Flood Control Act of 1950 
provides local interests furnish lands and rightsof-
way; make necessary highway, highway 
bridge, and utility alterations; hold the United 
States free from damages; and maintain and 
operate completed works. Total non-Federal 
costs for all active work are $2,656,000 (1975). For 
details of status or requirements of local cooperation 
see individual project reports. 
Operations and results during fiscal year. See 
individual projects. 
Condition at end of fiscal year. Construction of 
improvement to existing project in Sandy 
Drainage District, Oreg., was completed by local 
interests at no construction cost to the Government. 
Improvements of levees have been accomplished 
by contract at the following 
locations: Multnomah County Drainage District, 
No. 1, Oreg., June 1962; Sauvie Island 
Drainage District, Oreg., October 1962; Woodson 
Drainage District, Oreg., December 1963; 
Rainier Drainage District, Oreg., June 1964; 
Cowlitz County Diking Improvement District 
No. 15, Wash., December 1965; Cowlitz County 
Diking Improvement Districts Nos. 2 and 13, 
Wash., June 1965; Midland Drainage District, 
Oreg., April 1967; and Cowlitz County Consolidated 
Diking Improvement District No. 2, 
Wash., June 1974. Construction for improvements 
to three districts has been initiated 
with award of pump supply contracts. Washougal 
area, Washington (new location) levee construction 
has been completed. Under authorization for 
Lower Columbia River Basin bank protection 
works, construction is complete at 53 locations, of 
which 47 are in 12 drainage or diking districts. 
39. LOWER COLUMBIA RIVER BASIN 
BANK PROTECTION, OREG. AND 
WASH. 
Location. On Columbia River and tributaries 
between Sandy River, Oreg., and mouth of 
Columbia River. 
Existing project. Provides for construction of 
224,145 linear feet of bank protection works at 96 
locations along Lower Columbia River below 
river mile 125 and along principal tributaries in 
this reach, to protect existing improvements such 
as levees and developed industrial lands from 
further erosion. Existing project is a unit of 
general comprehensive plan for flood control, 
navigation, and other purposes in Columbia 
River Basin. Estimated Federal cost (1975) is 
$16,100,000. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Flood Control Act of 1950 
provides local interests furnish lands and rightsof-
way; make necessary highway, highway 
bridge, and utility alterations; hold the United 
States free from damages; and maintain and 
operate works after completion. Estimated costs 
for all requirements of local cooperation are 
$220,000 (1975). 
Operations and results during fiscal year. New 
work: Completed 2,985 linear feet of bank 
protection at locations set forth in Table 37-K. 
Shields Ranch Extension in Sauvie Island 
Drainage District was completed in November 
1974. Grain Elevator Location, sponsored by the 
Port of Kalama, was completed in November 
1974. Preparation of plans and specifications for 
Russian Point and Burkholder Location in Clatsop 
County Diking District No. 9 were completed 
in April 1975. Contracts for these locations were 
awarded in June 1975. 
Condition at end of fiscal year. Construction of 
project began in July 1961 and is 75 percent complete. 
A total of 123,266 linear feet of bank protection 
work at 53 locations, of which 47 are in 12 
drainage or diking districts, has been completed. 
Planning for construction at five additional 
locations is under way. 
40. SCAPPOOSE DRAINAGE 
DISTRICT, OREG. 
Location. In Columbia County, Oreg., along left 
bank of Multnomah Channel opposite Columbia 
River mile 90.3 to 97.0. 
Existing project. The project as originally 
authorized by the Flood Control Act of June 22, 
1936, provided for reconstruction of the existing 
levee system. Additional improvements provide 
for raising and strengthening 52,000 feet of levee, 
construction of toe drains, and additional pumping 
capacity. Estimated Federal cost (1975) is 
$3,950,000. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Flood Control Act of 1950, 
provides local interests furnish lands, easements, 
and rights-of-way; make necessary highway, 
highway bridge, and utility alterations; hold the 
United States free from damages; and maintain 
and operate completed works. Estimated costs of 
all requirements of local cooperation under terms 
of project authorization were $114,000 (1975). 
The Board of Supervisors adopted a resolution 
dated February 12, 1968, indicating approval of 
the proposed work and expressing their ability 
and willingness to provide the necessary local 
cooperation. Local assurances approved by OCE 
37-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
22 April 1974. Local interests have worked closely 
with the Corps in developing the revised plan of 
improvement. Right-of-way drawings were furnished 
to diking district officials in the second 
quarter of FY 1975. No difficulties are anticipated 
in obtaining rights-of-way and 
easements and other items of local assurance as 
the district now possesses or has authority to furnish 
such items for authorized work and district 
officials have been kept fully informed of the 
latest requirements. 
Operations and results during fiscal year. 
Preparation of plans and specifications on levees 
and pumping plant was continued. Revisions in 
pumping station design replaced timber piling 
foundation with a concrete foundation. Advertising 
will be scheduled when funds become adequate 
for construction in FY 1976. 
Condition at end of fiscal year. Project as 
originally authorized was completed in 1941. 
Design memorandum approved by higher 
authority in September 1971. Final environmental 
impact statement filed with CEQ April 24, 
1972. Supplement to EIS was filed with CEQ 29 
July 1974. Construction is scheduled for FY 1976. 
41. VANCOUVER LAKE AREA, WASH. 
Location. In the southwestern part of Clark 
County, Wash., along the Columbia River 
between river miles 96.1 and 105.6. Part of the 
easterly boundary of this area lies within the City 
of Vancouver, Wash. 
Existing project. Provides for raising and 
strengthening an existing levee, and construction 
of new levee with a cross levee to proposed State 
Secondary Highway No. 501 along Lake River. 
Pumping plants and drainage structures would 
be provided for evacuation of surface drainage 
and seepage. About 8.7 miles of existing levee 
would be improved and about 2 miles of new levee 
would be required. Estimated Federal cost $12,- 
600,000 (1975). (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Flood Control Act of 1950, 
provides local interests furnish lands, easements, 
and rights-of-way; make necessary highway, 
highway bridge, and utility alterations; hold the 
United States free from damages; and maintain 
and operate completed works. Estimated costs of 
all requirements of local cooperation under terms 
of project authorization were $583,000 (1975). 
Operations and results duringfiscal year. Coordination 
with Clark County continues. 
Condition at end of fiscal year. Planning is 
suspended until Clark County land use planning 
is completed. 
42. WAHKIAKUM COUNTY 
CONSOLIDATED DIKING 
DISTRICT NO. 1, WASH. 
Location. District occupies both Puget and Little 
Islands in Columbia River between river miles 
38.4 and 45.0 These islands are in Wahkiakum 
County, Wash., near town of Cathlamet. 
Existing project. Provides for raising and 
strengthening existing levees, removing several 
abandoned tide boxes, constructing a new tide 
box, extending an existing tide box and adding a 
gate well structure, constructing a new pumping 
station and relocating 3 existing pumping 
stations; raising the discharge lines of all pumping 
stations; and filling borrow ditches along the 
landward levee toe. Estimated Federal cost 
(1975) is $4,500,000. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Flood Control Act of 1950 
provides local interests furnish lands and rightsof-
way; make necessary highway, highway 
bridge, and utility alterations; hold the United 
States free from damages; and maintain and 
operate completed works. Estimated costs for all 
requirements of local cooperation under terms of 
project authorization were $303,000 (1975). 
Operations and results during fiscal year. 
Preconstruction planning for levees continues. 
Contract to remove and construct tide box awarded 
on 23 June 1975. Pump supply contract awarded 
7 October 1974. 
Condition at end offiscal year. Construction of a 
new drainage structure and removal of existing 
tide boxes is scheduled to begin in FY 1976. Final 
EIS filed 18 September 1972. 
43. WILLAMETTE RIVER 
BASIN, OREG. 
Location. Willamette River is formed by Coast 
and Middle Forks which join a few miles above 
Eugene, Oreg., flows north 189 miles, and enters 
Columbia River 101.5 miles above its mouth. 
Basin has an area of 11,200 square miles and lies 
between Cascade Range on the east and Coast 
Range on the west. Major tributaries of 
Willamette River rise in Cascade Mountains and 
consist of Coast and Middle Forks and McKenzie, 
Calapooia, Santiam, Molalla, and Clackamas 
Rivers. Important tributaries that head in the 
Coast Range are Luckiamute, Yamhill, and 
Tualatin Rivers. Minor tributaries, all of which 
enter main stream from the west, are Marys 
River, Rickreall Creek, and Long Tom River. 
Existing project. Flood Control Act of 1938 approved 
general comprehensive plan for flood control, 
navigation, and other purposes in 
37-22

PORTLAND, OREG., DISTRICT 
Willamette River Basin and authorized $11,300,- 
000 for initiation and partial accomplishment of 
plan recommended for initial development: the 
reservoirs and related works to be selected by 
Chief of Engineers. Subsequent Flood Control 
Acts, 1941 through 1974, authorized additional 
flood control and other works and increased 
monetary authority. The Flood Control Act of 
1950 included the Willamette River Basin in the 
Columbia River Basin monetary authorization. 
The Columbia River Basin monetary authorization 
is $1,974,300,000 (1974). (See Table 37-L on 
Willamette River Basin comprehensive plan, and 
Table 37-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act 
of June 28, 1938, applies to reservoir projects. 
Local cooperation for other projects is inm individual 
reports for those projects. 
Operations and results during fiscal year. See 
individual reports. 
Condition at end of fiscal year. Following projects 
were completed as authorized and in continuous 
operation: Fern Ridge Lake, August 
1951; Cottage Grove Lake, March 1952; Dorena 
Lake, October 1952; Detroit Lake, December 
1960; Lookout Point Lake, June 1961; Hills Creek 
Lake, June 1963; Cougar Lake, March 1964; Fall 
Creek Lake, November 1965; Green Peter-Foster 
Lakes, June-December 1967 respectively; and 
Blue River Lake, October 1968. Under the 
authorization for construction of recreation 
facilities on completed projects, work has been accomplished 
at Fern Ridge, Cottage Grove, 
Dorena, Lookout Point, and Fall Creek Lakes. 
Advance engineering and design for proposed 
construction of Holley Lake project was placed in 
deferred status pending completion of a study to 
determine extent of increased capacity required 
in Calapooia River for flood control operation of 
the project. Details of operation, construction, 
and financial status of projects are in individual 
reports. During low-water season, July- 
September, supplemental water releases are 
made from Willamette River Basin Reservoirs 
for conservation purposes. Interests which 
benefit from increased downstream flows include 
irrigation, navigation, power, pollution abatement, 
and recreation. Although optimum regulation 
cannot be provided for every conservation interest, 
water released from reservoirs during the 
low-water season for a particular purpose will 
usually provide benefits to other conservation 
uses as well. Basic policy is to provide most 
beneficial overall regulation, consistent with established 
water-use priorities. 
44. WILLAMETTE RIVER BASIN, 
OREG. - BANK PROTECTION 
Location. On Willamette River and tributaries, 
between Cascade Range and Coast Range, from a 
point south of Eugene to Portland, Oreg. 
Existing project. Provides for clearing, sloping, 
and revetting riverbanks; construction of pile and 
timber bulkheads and drift barriers; minor 
channel improvements; and maintenance of existing 
works for control of floods and prevention 
of erosion at various locations along Willamette 
River and its tributaries. The current scope of the 
project is a total of 510,000 linear feet of bank 
protection. Estimated Federal cost of project 
(1975) is $19,800,000. (See Table 37-B for 
authorizing legislation.) 
Local cooperation. Section 3, Flood Control Act 
of 1936, applies. Estimated costs for all requirements 
of local cooperation under terms of 
project authorization were $325,000 (1975). 
Operations and results during fiscal year. New 
work: Completed 6,899 linear feet of bank 
protection work at locations set forth in Table 37- 
M. Contracts for work at Danis, Stoutenberg Upstream 
Extension and Lassen, Willamette River 
and Upper Bryant, Santiam River were awarded 
June 24, July 22, August 21 and June 5, 1974, 
respectively. Plans and specifications for contractual 
work at Spong Road, Willamette River and 
Wilke, Molalla River were completed and award 
scheduled in FY 1976. Work at these locations 
is underway. Maintenance: Contractual repair at 
Wilfert and Santiam River completed early in 
FY 1976. 
Condition at end of fiscal year. Construction of 
project began in 1938 and is 74 percent complete. 
A total of 455,829 linear feet of bank protection 
work at 212 locations consisting of revetment of 
river banks, pile and timber bulkheads, drift 
barriers, and channel improvements, have been 
completed on Willamette River and tributaries. 
In addition 7,075 lineal feet of restoration work at 
2 previously constructed locations has been accomplished. 
45. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Funds appropriated for inspection of completed 
local flood protection works' are used to 
determine condition of completed works and to 
ascertain whether those works are being properly 
maintained by local interests. A total of 56 leveed 
areas and 263 bank protection works were inspected 
at various locations along both banks of 
Lower Columbia River below Bonneville Dam, 
along Oregon Coast and in Willamette River 
Basin. Of this total, 30 leveed areas in Oregon and 
14 leveed areas in Washington along Lower 
Columbia River; and 12 leveed areas and 3 
37-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
revetments along Oregon Coast were inspected 
July 1974 through June 1975. Also during May 
1975, 212 revetments along Willamette River and 
tributaries were inspected. A representative of 
sponsoring districts accompanied the Portland 
District representatives performing the levee inspections. 
Aerial inspection of revetments in 
Willamette River Basin was supplemented by an 
on-site inspection at locations requiring 
maintenance. Deficiencies in maintenance and 
need for repairs were discussed with sponsoring 
districts' representatives and a report was made 
to each sponsor with recommendations for improving 
maintenance. The campaign to improve 
maintenance of completed Federal projects initiated 
by House Appropriations Committee on 
Civil Functions was continued. Periodic contact 
was maintained with uncooperative areas 
reported in fiscal year 1975 to ascertain any 
change in attitude and to provide technical 
assistance, if requested. Of the 110 sponsors of 
local flood protection projects inspected in 
Portland District, 14 were reported deficient in 
maintenance. Fiscal year costs were $44,719 and 
costs to June 30, 1975 were $450,920. 
46. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Corps of Engineers monitored flood control 
operations at four Bureau of Reclamation sponsored 
projects (Prineville, Ochoco, Emigrant 
Lake and Scoggins) and (Mossyrock) a municipally 
operated power project by the Tacoma City 
Light. The Bureau of Reclamation projects were 
partially constructed with flood control funds and 
thereby this phase of the project operation is subject 
to monitoring by the Corps of Engineers under 
Section 7, Flood Control Act of 1944. Monitoring 
of Mossyrock flood control operation is assigned 
to the Corps by the Federal Power Commission 
as the Mossyrock license calls for specific flood 
control regulation. The Bureau sponsored projects 
during Fiscal Year 1975 were operated 
satisfactorily for flood control. Scoggins project 
(Henry Hagg Lake) commenced initial filling 
November 1974. At Mossyrock, two significant 
winter highwaters occurred and a higher than 
normal spring runoff occurred from snowmelt. 
Regulation during the 21 December 1974 and 18 
January 1975 highwaters stored 127,000 and 
237,000 acre-feet respectively at Mossyrock and 
the outflow was controlled to a peak of 39,550 cfs 
at Castle Rock, as compared to the goal of 70,000 
cfs for that station. All reservoirs filled to their 
maximum conservation levels following the flood 
season. A preliminary Reservoir Regulation 
Manual for Scoggins project is in the process of 
preparation. Total cost of monitoring the five 
projects during Fiscal Year 1975 was $1,982. 
47. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 37-N. 
48. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization) 
See Table 37-0. 
Emergency flood control activities-repairf,l ood 
fighting and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation.) 
See Table 37-0. 
Emergency bank protection under Sec. 14 of the 
1946 Flood Control Act. 
See Table 37-0. 
Multiple-Purpose Power Projects 
49. BONNEVILLE LOCK AND 
DAM-LAKE BONNEVILLE, 
OREG. AND WASH. 
Location. Project is on Columbia River, 42 
miles east of Portland, Oreg., about 146 miles 
above mouth of river. For description of Columbia 
River see Improvement No. 5. 
Existing project. A dam, powerplant, and lock 
for power and navigation. Spillway dam extends 
across main channel from Washington shore to 
Bradford Island, which divides the river at this 
point. Overflow crest at 24 feet above mean sea 
level is surmounted by 18 vertical-lift steel gates 
placed between piers which extend to elevation 99 
feet where a service roadway permits operation of 
two 350-ton gantry cranes for regulating gates. 
Powerhouse extending across Bradford Slough to 
Oregon shore has an installation of 10 units, consisting 
of two units of 43,200 kilowatts each and 
eight units of 54,000 kilowatts each, totaling 518,- 
400 kilowatts. Ordinary and extreme fluctuations 
of river at lower lock gate are about 21 and 47 feet 
respectively. Project includes fish ladders and 
locks to serve both main channel and Bradford 
Slough channel. Navigation lock and powerhouse 
are founded on andesite, and main dam rests upon 
solidified sedimentary rock of volcanic origin. 
Pool created by dam provides a navigable 
channel with a depth of 30 feet and over between 
Bonneville and The Dalles Dams, a distance of 47 
miles. Principal data concerning navigation lock 
spillway dam, and powerplant are set forth in 
Table 37-P. 
Dam, navigation lock, 10-unit power 
generating installation, fishways, and attendant 
buildings and grounds cost $83,239,395, of which 
37-24

PORTLAND, OREG., DISTRICT 
$6,072,480 is for navigation facilities, $39,350,824 
for power facilities and $37,816,091 for joint 
facilities, consisting of darn, fishways, buildings 
and grounds, and headwall section of power units 
0 to 6, cost of which $2,106,000 is allocated to dam 
and lake facilities. Estimated total Federal cost of 
completed project (1975) is $83,947,395 which includes 
$708,000 for construction of recreation 
facilities at completed project. (See Table 37-B 
for authorizing legislation.) 
A modification for peaking is required as a corrective 
measure to provided features for operation 
of the spillway, powerhouse and fish ladders 
to minimize adverse environmental effects under 
rapidly-changing flow conditions expected from 
The Dalles and John Day peaking plants. The 
project modification also provides for increased 
power installation by building a second 
powerhouse located on the Washington shore adjacent 
to the north end of the existing spillway. 
The new powerhouse would contain eight units of 
67,600 kw each for a capacity of 540,800 kw to 
bring the total Bonneville capacity to 1,059,200 
kw. Additional facilities would be included for 
fish passage, visitors and public recreation. Under 
authority of the Bonneville Project Act 
(August 26, 1937), a letter from Bonneville Power 
Administration to North Pacific Division dated 
January 21, 1965, requested construction of a second 
powerhouse. Estimated cost (1975) is $492,- 
500,000 which includes $30,500,000 for modification 
for peaking and $462,000,000 for construction 
of second powerhouse. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Nearly all the design work for the second 
powerhouse is complete. Major contracts awarded 
during the fiscal year were the Pilot Tunnel, 
June 1975; Seepage Control-Phase I, August 
1974; and Seepage Control-Phase II, April 1975. 
Modification for peaking design memorandums 
are all complete. Bradford Island Visitors Center 
construction completed April 1975. Expansion of 
Bonneville Fish Hatchery is continuing and is 
about 70 percent complete. Other minor contracts 
under modification for peaking were completed 
in Fiscal Year 1975. Studies continued on 
nitrogen supersaturation; fish screens; and 
national marine fishery studies. 
Maintenance: Normal operation and 
maintenance with a contract for south shore 
sanitary facilities awarded October 1974. During 
the fiscal year 4,498,162,000 kilowatt-hours of 
electrical power energy were generated, of which 
4,481,404,000 kilowatt-hours were delivered to 
Bonneville Power Administration, the marketing 
agency. Traffic through the navigation lock consisting 
of rafted logs, petroleum products, grains, 
and miscellaneous cargo amounted to 4,093,395 
tons during calendar year 1974. 
Condition at end of fiscal year. Construction of 
project started October 1933, was completed 
February 1953. Modification of powerhouse control 
equipment started March 1957, was completed 
September 1958. First two power units 
were placed in operation during fiscal year 1938. 
Powerhouse with complete installation of 10 
units, was in operation December 1943. Advance 
engineering for construction of second 
powerhouse is complete. Construction of 
modification for peaking work commenced in 
September 1970 and overall project is about 94 
percent complete. Preparation of plans and 
specifications for additional contracts is underway. 
Final environmental impact statement 
was filed with Council on Environmental Quality 
in September 1971. Planning for relocation of the 
Town of North Bonneville is completed. Power 
generation through June 1975 has been 131.1 
billion kilowatt hours, representing a gross income 
of $102.7 million to the U.S. Treasury from 
the sale of power by the Bonneville Power Administration. 
50. COUGAR LAKE, OREG. 
Location. At mile 4.4 on South Fork McKenzie 
River which joins McKenzie River about 56.5 
miles above its confluence with Willamette River. 
Project is about 42 miles east of Eugene, Oregon. 
Existing project. A rockfill dam with an impervious 
earth core, about 1,738 feet long at crest and 
445 feet high above the streambed. Reservoir is 6 
miles long with storage capacity at full pool of 
219,000 acre-feet and controls runoff of tributary 
drainage area of 210 square miles. Spillway is on 
right abutment and outlet and power tunnels in 
left abutment. Outlet tunnel is provided with a 
chute and stilling basin. Powerplant consists of 
two 12,500 kilowatt units with minimum 
provisions for installing a third unit of 35,000 
kilowatts for future peaking capacity. Improvement 
functions as a unit in coordinated system of 
reservoirs for multiple-purpose development of 
water resources in Willamette River Basin. 
Recreation facilities are provided by the U.S. 
Forest Service. Estimated project cost (1975) is 
$57,500,000. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Contract for McKenzie River Hatchery 
was awarded November 1974 and construction is 
about 55 percent complete. Maintenance: Ordinary 
operation and maintenance continued. 
During fiscal year 171,005,000 kilowatt-hours of 
electrical energy were generated at project, of 
which 170,239,000 kilowatt-hours were delivered 
to Bonneville Power Administration, the 
marketing agency. Freshets regulated by Cougar 
37-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Lake project on South Fork McKenzie River are 
shown in Table 37-I. 
Condition at end of fiscal year. Construction of 
project initiated June 1956 is 97 percent complete. 
Remaining work consists of fish hatchery 
facilities, landscaping and view points. 
Generating units 1 and 2 were placed in commercial 
operation March 23 and February 4, 1964, 
respectively. Physically in service date for flood 
control was November 29, 1963. Planning for 
view points and area upgrading is underway. 
Power generation through June 1975 has been 1.5 
billion kilowatt hours, representing a gross income 
of $7.5 million to the U.S. Treasury from the 
sale of power by the Bonneville Power Administration. 
51. DETROIT LAKE, OREG. 
Location. On North Santiam River with dam 50 
miles from mouth and 45 miles southeast of 
Salem, Oreg. North Santiam River flows north 
and west for 85 miles, and unites with South Santiam 
River to form Santiam River, which 10 miles 
downstream enters Willamette River 108 miles 
above its mouth. 
Existing project. One main dam and a 
reregulating dam, both with power-generating 
facilities. Detroit Dam is a concrete gravity structure 
about 1,522 feet long and 454 feet high from 
lowest point of the general foundation to roadway 
deck. Spillway is a gate-controlled overflow section, 
and outlet works are gate-controlled conduits 
through dam. Powerhouse with two units 
having a capacity of 50,000 kilowatts each is in 
right abutment immediately below dam. Reservoir 
has a storage capacity at full pool of 454,900 
acre-feet and controls runoff of tributary 
drainage area of 438 square miles. It is being 
operated as a unit in coordinated reservoir system 
to protect Willamette Valley from floods, to increase 
low water flows in interest of navigation 
and irrigation, to generate power, and for other 
purposes. Reregulating dam 3 miles downstream 
at Big Cliff site is concrete gravity type, about 191 
feet high from lowest point of the general foundation 
to roadway deck. Power installation consists 
of one unit with a capacity of 18,000 kilowatts. 
Reservoir has a storage capacity of 5,930 acre-feet 
at full pool. Project is a unit of comprehensive 
plan for flood control and other purposes in 
Willamette Basin. Recreation facilities are 
provided by the U.S. Forest Service, Oregon 
State Park System and the Town of Detroit. (See 
Table 37-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: None. Maintenance: Ordinary operation 
and maintenance continued. During fiscal 
year 583,402,000 kilowatt-hours of electrical 
energy were generated at project of which 580,- 
717,000 kilowatt-hours were delivered to 
Bonneville Power Administration, the marketing 
agency. Freshets regulated by the Detroit Lake 
project on North Santiam River are shown in 
Table 37-I. 
Condition at end of fiscal year. Construction of 
project begun in May 1947 was completed 
December 1960. The two powerhouse generating 
units were placed in commercial operation June 
and October 1953. At Big Cliff powerhouse, 
single generating unit was placed on-the-line 
June 1954. Use of Big Cliff Dam for reregulating 
fluctuating flow from Detroit units was effected 
October 1953. Power generation through June 
1975 has been 10.8 billion kilowatt hours, 
representing a gross income of $35.7 million to 
the U.S. Treasury from the sale of power by the 
Bonneville Power Administration. 
52. GREEN PETER-FOSTER 
LAKES, OREG. 
Location. At approximate mile 5.5 on Middle 
Santiam River which joins South Santiam River 
about 56.8 miles above its confluence with 
Willamette River. Dam is about 30 miles 
southeast of Albany in Linn County, Oreg. 
Existing project. One main dam and a 
reregulating dam, both with power-generating 
facilities. Green Peter Dam is a concrete gravity 
structure, 1,400 feet long and 385 feet high above 
the lowest point of the general foundation with a 
gate-controlled spillway. Outlet works consist of 
two conduits through spillway, discharging into a 
stilling basin. Powerplant, on right bank adjacent 
to spillway stilling basin, consists of two units 
with an installed capacity of 80,000 kilowatts. 
Reservoir provides storage capacity at full pool of 
430,000 acre-feet, extending 6.5 miles up Quartzville 
Creek and some 7.5 miles up Middle Santiam 
River above creek junction, forming a Y-shaped 
pool. Reservoir controls runoff of tributary 
drainage area of 277 square miles. Foster Dam, 7 
miles downstream from Green Peter Dam is 
located on South Santiam River about 38 miles 
above its confluence with Santiam River and 1.5 
miles below its confluence with Middle Santiam 
River. Foster Dam consists of an earth, gravel, 
and rock-filled embankment, 146 feet high from 
lowest point of the general foundation and a concrete 
gravity gate-controlled spillway and stilling 
basin for a total length of 4,800 feet. Power installation 
consists of two units with a capacity of 
20,000 kilowatts. Foster Lake has a storage 
capacity, at full pool, of 61,000 acre-feet. Project 
functions as a unit in coordinated system of reservoirs 
for multiple-purpose development of water 
resources in Willamette River Basin. Estimated 
37-26

PORTLAND, OREG., DISTRICT 
Federal cost of project (1975) is $85,078,000 
which includes an estimated $1,076,000 for additional 
recreation facilities at completed project. 
(See Table 37-B for authorizing legislation.) 
Local cooperation. Estimated cost of local 
cooperation on basis of cost-sharing for recreation 
facilities is $1,076,000. 
Operations and results during fiscal year. New 
work: Work on landscaping, irrigation and 
visitors facilities was completed. 
Maintenance: Normal operation and 
maintenance being performed. During fiscal 
year 380,441,000 kilowatt-hours of electrical 
energy was generated at project of which 376,- 
563,000 kilowatt-hours were delivered to 
Bonneville Power Administration, the marketing 
agency. Freshets regulated by Green Peter Lake 
project on Middle Santiam River are shown in 
Table 37-I. 
Condition at end of fiscal year. All major construction 
on Green Peter-Foster Lakes project initiated 
June 1961 is completed. Green Peter Lake 
was placed in operation for useful flood control 
June 1967 as a unit of coordinated reservoir 
system for protection of the Willamette River 
Basin. First power-generation unit was placed on 
the line June 9, 1967 and second, June 28, 1967. 
Use of Foster Lake for reregulating fluctuating 
flows from Green Peter units was effective 
December 1967. First power generation unit was 
placed on-the-line August 22, 1968 and second, 
September 6, 1968. Power generation through 
June 1975 has been $2.9 billion kilowatt hours, 
representing a gross income of $13.1 million to 
the U.S. Treasury from the sale of powei by the 
Bonneville Power Administration. 
53. HILLS CREEK LAKE, OREG. 
Location. On the Middle Fork, Willamette 
River, 47.8 miles from mouth and 26.5 miles upstream 
from Lookout Point Dam. Middle Fork, 
Willamette River rises on west slope of Cascade 
Range and flows northwesterly to its junction 
with Coast Fork, Willamette River. Dam is about 
45 miles southeast from Eugene, Oreg. 
Existing project. An earth-and-gravel-fill dam 
about 2,150 feet long at the crest and 338 feet 
above lowest point of the general foundation. A 
gate-controlled concrete gravity chute-type 
spillway is in right abutment. Diversion tunnel, 
outlet tunnel and power tunnel are in same abutment. 
Powerhouse with two 15,000 kilowatt units 
is located next to spillway. Hills Creek Lake is 
about 8.5 miles long and provides storage capacity 
at full pool of 356,000 acre-feet. Project controls 
runoff of drainage area of 389 square miles and is 
an integral unit of comprehensive plan for 
development of water resources of Willamette 
River Basin. Hills Creek Lake and Lookout Point 
Lake are operated as a unit for control of floods 
and generation of power on Middle Fork 
Willamette River. These projects, in conjunction 
with Dexter reregulating dam and Fall Creek 
Lake flood control system, will effectively control 
floods on Middle Fork and provide maximum efficient 
generation of hydroelectric power. 
Recreation facilities are provided by the U.S. 
Forest Service. Total cost of project is $45,700,- 
619. (See Table 37-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. Ordinary 
operation and maintenance continued. 
During fiscal year 198,929,000 kilowatt-hours of 
electrical power were generated, of which 198,- 
521,000 kilowatt-hours were delivered to 
Bonneville Power Administration, the marketing 
agency. Freshets regulated by Hills Creek Lake 
on Middle Fork Willamette River are shown in 
Table 37-I. 
Condition at end of fiscal year. Construction of 
project, initiated May 1956, was completed June 
1963. The project was placed in service for useful 
flood control in November 1961. On May 2, 1962, 
the two power generation units were placed onthe-
line. Power generation through June 1975 has 
been 2.0 billion kilowatt hours, representing a 
gross income of $8.6 million to the U.S. Treasury 
from the sale of power by the Bonneville Power 
Administration. 
54. JOHN DAY LOCK AND DAM-LAKE 
UMATILLA, OREG. AND WASH. 
Location. On Columbia River about 3 miles 
downstream from mouth of John Day River and 
about 215 miles above mouth of Columbia River. 
Existing project. A dam, powerplant, navigation 
lock, fish ladders, and appurtenant facilities 
with a slack-water lake about 75 miles long extending 
to McNary Lock and Dam. Included is 
relocation of railroads, highways, utilities, and 
communities affected by the impoundment. The 
project as originally authorized would have 
provided 2,000,000 acre-feet of flood control 
storage. As modified, the project provides 500,- 
000 acre-feet of flood control storage between 
elevations 257 and 268. The structure is 5,900 feet 
in length and stands about 161 feet above 
streambed. Powerhouse has space for 20 
generating units of 135,000 kilowatts each; 16 units 
have been installed for a present capacity of 2,- 
160,000 kilowatts. Principal project data are set 
forth in Table 37-P. 
A detailed description of project as authorized 
and modified is on pages 1992 and 1993 of Annual 
Report for 1962. Estimated Federal cost of new 
work (July 1975) is $494,678,000, consisting of 
37-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
$496,000,000 Corps of Engineers funds, $333,000 
for Coast Guard navigation aids, $300,000 for 
value of public-owned lands, and a net reduction 
of $1,955,000 for value of other property 
transferred to and from the project without reimbursement. 
(See Table 37-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Design memorandums are completed 
and plans and specifications were nearing completion 
for upstream channel dredging, fish viewing 
expansion and elevator. Contracts awarded 
were for visitors' facilities, graphics displays, 
color design; supergraphics and interpretive display. 
Operation and maintenance: During fiscal 
year 11,782,374,000 kilowatt-hours of electrical 
power were generated by the 16 generating units 
of which 11,762,783,000 kilowatt-hours were 
delivered to Bonneville Power Administration, 
the marketing agency. Traffic through the 
navigation lock, consisting of petroleum 
products, grains, and miscellaneous cargo, 
amounted to 3,216,191 tons during calendar year 
1974. 
Condition at end of fiscal year. Construction 
began July 1958, and the project was opened to 
navigation April 1968. Sixteen generating units 
of 135,000 kilowatts each are producing a total 
output of 2,160,000 kilowatts. Main dam completion 
contract is complete. Relocations are essentially 
complete except for Umatilla Indian Burial 
Relocation. Remaining to complete are the 
Bonneville Fish Hatchery and landscaping and 
grounds development, North Shore recreation 
facilities, and monolith joint seals. Entire project 
is estimated to be 96 percent complete. Power 
generation through June 1975 has been 70.5 
billion kilowatt hours, representing a gross income 
of $68.2 million to the U.S. Treasury from 
the sale of power by the Bonneville Power Administration. 
55. LOOKOUT POINT LAKE, OREG. 
Location. On Middle Fork, Willamette River at 
Meridian site, 21.3 miles from mouth. Middle 
Fork, Willamette River, rises in Lane County on 
western slope of Cascade Range and flows 
northwesterly to its junction with Coast Fork, 
which is head of main stem Willamette River. 
Dam is about 22 miles southeast from Eugene, 
Oreg. 
Existing project. A main dam at Meridian site 
and a reregulating dam 3 miles downstream at 
Dexter site. Both dams are earth-and-gravel-fills 
with concrete spillways and have power 
generating facilities. Main dam is 258 feet high 
from lowest point of the general foundation to 
deck and is 3,381 feet long at crest forming a 
reservoir 14.2 miles long providing storage of 
456,000 acre-feet at full-pool level. Reservoir controls 
runoff of tributary drainage area of 991 
square miles. Spillway, 274 feet long, is a gatecontrolled 
overflow type, forming right abutment. 
Outlet works consisting of slide-gatecontrolled 
conduits pass through spillway section. 
Powerhouse has three main generating units 
with a capacity of 120,000 kilowatts. 
Reregulating dam has a maximum height of 107 
feet above lowest point of the general foundation 
and is 2,765 feet long at crest, forming a full pool 
of 27,500 acre-feet extending upstream to main 
dam and providing pondage to regulate Lookout 
Point powerhouse water releases to a uniform discharge. 
Spillway consists of a gate-controlled 
overflow section 509 feet long forming right abutment. 
Flow regulation is accomplished by use of 
spillway gates and releases through powerhouse, 
which contains one 15,000-kilowatt unit. Lookout 
Point and Dexter Lakes are operated as a single 
unit of a coordinated system of reservoirs to 
protect Willamette River Valley against floods, to 
provide needed hydroelectric power, and to increase 
low water flows for navigation, irrigation, 
and other purposes. Existing project authorized 
as a unit of comprehensive plan for flood control 
and other purposes in Willamette River Basin. 
Estimated total Federal cost of project (1975) is 
$92,471,000. Included is the estimated Federal 
cost of $4,690,000 (1975) for construction of additional 
recreation facilities at the completed 
project. (See Table 37-B for authorizing legislation.) 
Local cooperation. Estimated costs of local 
cooperation on basis of cost-sharing for recreation 
facilities is $5,571,000. 
Operations and results during fiscal year. New 
work: None. Maintenance: Normal operation 
and maintenance continued. During fiscal year 
488,766,000 kilowatt-hours of electrical power 
energy were generated at project of which 487,- 
439,000 kilowatt-hours were delivered to 
Bonneville Power Administration, the marketing 
agency. Freshets regulated by Lookout Point 
Lake project on Middle Fork Willamette River 
are shown in Table 37-I. 
Condition at end of fiscal year. Construction of 
project initiated May 1947 was completed June 
1961, except for construction of additional recreation 
facilities authorized in 1954. At Lookout 
Point powerhouse, generating units 1, 2 and 3 
were placed in commercial operation December 
1954, February 1955, and April 1955 respectively. 
At Dexter powerhouse the single unit was 
placed on-the-line May 1955. Use of Dexter Lake 
for reregulating fluctuating flows from Lookout 
37-28

PORTLAND, OREG., DISTRICT 
Point units was effected in December 1954. 
Power generation through June 1975 has been 8.5 
billion kilowatt hours, representing a gross income 
of $33.3 million to the U.S. Treasury from 
the sale of power by the Bonneville Power Administration. 
56. LOST CREEK LAKE, ROGUE 
RIVER BASIN, OREG. 
Location. On upper Rogue River at mile 153.6 
about 26.5 miles northeasterly from Medford, 
Oreg. 
Existing project. Provides for rock and gravelfill 
embankment dam about 327 feet high from 
streambed to crest, with an overall length of 3,750 
feet with an impervious earth core and a gatecontrolled 
concrete spillway. Powerhouse will be 
on right abutment and house two Francis-type 
turbines with installed capacity of 24,500 
kilowatts each. Regulating outlet facility with 
provisions for temperature regulation for 
releases in interest of fishery enhancement will 
also be in right bank. Reservoir 10 miles long will 
provide 315,000 acre-feet of usable storage. Project 
will provide control of runoff of drainage area 
of 674 square miles. In addition to hydroelectric 
power generation, project will be operated to 
provide flood control, irrigation, future 
municipal and industrial water supply, fish and 
wildlife enhancement, water quality control and 
recreation benefits. Estimated project cost (1975) 
is $145,000,000. (See Table 37-B for authorizing 
legislation.) 
Local cooperation. Authorizing act requires 
that local agencies furnish assurances prior to 
construction that demands will be made for 
future use of water supply storage within a period 
that will permit repayment of costs, including interest, 
allocated to water supply within life of the 
project; that State of Oregon take action, prior to 
construction to insure maintenance in stream of 
flows to be released for fishery; in addition, costs 
allocated to irrigation would have to be repaid in 
manner and to an extent consistent with 
Reclamation laws and policies; and costs 
allocated to power will be repaid on a system basis 
by revenue from sales of power in Pacific 
Northwest Federal system by Bonneville Power 
Administration. Assurances for municipal and 
industrial water supply have been obtained from 
6 communities in Rogue River Valley. On 
February 26, 1966 Oregon State Game Commission 
agreed to operate Rogue River hatchery for 
mitigation and enhancement of fish. U.S. Bureau 
of Reclamation has completed feasibility study 
for irrigation of Medford Division from Lost 
Creek and Elk Creek Lakes and repayment by 
local interests for cost allocated to irrigation will 
be repaid over a period not to exceed 50 years, exclusive 
of a development period of up to 10 years. 
Operations and results during fiscal year. New 
work: Plans and specifications continued for 
Stewart State Park, powerline clearing and 
relocation, and erosion control. Contracts underway 
and awarded during fiscal year were for 
relocation of roads; construction of Peyton 
Bridge; construction on main dam; parking and 
visitors' facilities; manufacture of hydraulic turbines, 
generators, overhead crane, butterfly 
valves, substation equipment, fish feeding equipment; 
clearing, powerhouse and erosion control. 
Condition at end of fiscal year. Project initiated 
July 1967 is 58 percent complete. Construction of 
.major features are in various stages of completion. 
Work continues on contractual plans and 
specifications. Land acquisition is 97 percent 
complete. Final environmental statement was 
filed with Council on Environmental Quality in 
June 1972. 
57. THE DALLES LOCK AND DAMLAKE 
CELILO, WASH. AND OREG. 
Location. On Columbia River at head of pool 
behind Bonneville Dam, about 193 miles above 
mouth of river and 90 miles east of Portland, 
Oreg. 
Existing project. A dam, powerplant, navigation 
lock, and appurtenant facilities. Improvement 
provides for navigation and hydroelectric 
power generation. Dam is designed for a normal 
pool at elevation 160 feet at mean sea level. Normal 
pool forms a reservoir extending upstream 
about 25 miles providing slackwater to John Day 
Dam site. The Dalles Dam is 8,700 feet long and 
consists of a rock, gravel, and sand river closure 
section from Oregon shore connecting to a nonoverflow 
section which in turn joins powerhouse, 
then concrete nonoverflow sections connecting 
spillway with powerhouse and spillway with 
navigation lock at right abutment on Washington 
shore. Fish-passing facilities including two 
ladders and a fish lock are provided. Powerhouse 
was constructed for 14 units which were installed 
initially and with substructure constructed for 8 
additional units, an ultimate total of 22 units. Initial 
installation, excluding two 13,500 kilowatt 
fishwater units, is 1,092,000 kilowatts. 
Powerhouse completed and 8 units installed with 
capacity of 687,800 kilowatts. Total for 22 units is 
1,779,800 kilowatts. Structures are founded on 
Columbia River basalt. Principal data concerning 
lock, spillway, and powerhouse are set forth in 
Table 37-N. Estimated Federal cost of initial 
work, Units 1-14 (1975) is $253,134,000 which includes 
$6,134,000 for construction of recreation 
37-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
facilities at completed project. Estimated 
Federal cost for additional power units is $69,- 
700,000 (1975). Total Federal project cost estimate 
is $322,834,000 (1975). (See Table 37-B for 
authorizing legislation.) 
Local cooperation. Estimated cost of local 
cooperation on basis of cost sharing for additional 
recreation facilities is $5,023,000. 
Operations and results during fiscal year. New 
work: Contracts completed or near completion 
in Fiscal Year 1975 were: powerhouse units 15- 
22, landscaping and site development at Spearfish 
Lake, installation of units 15-22, control 
switch boards, and digital operations controller. 
Modification of powerhouse fish collection system 
is subject to Bonneville Reservoir regulation 
studies. Studies are scheduled for design of 
spillway deflectors to reduce nitrogen supersaturation 
and fish screens to improve fingerling 
passage through the dam. Maintenance: Ordinary 
operation and maintenance continued. 
Preparation of plans and specifications for 
navigation lock gate repair was completed and 
contract was awarded November 1974. During 
fiscal year 8,954,970,000 kilowatt-hours of electrical 
power energy were generated at project of 
which 8,933,643,000 kilowatt-hours were 
delivered to Bonneville Power Administration, 
the marketing agency. Traffic through the 
navigation lock, consisting of petroleum 
products, grains and miscellaneous cargo 
amounted to 3,271,729 tons during calendar year 
1974. 
Condition at end offiscal year. Major construction 
of project, initiated February 1952, was completed 
October 1960, when unit No.14 was placed 
in commercial operation. Initial contract for additional 
units 15-22 was awarded September 
1967. Additional 8-unit phase was completed 
when Unit 22 was placed in commercial operation 
in November 1973. Remaining work consists 
of improvement of visitor facilities. Power 
generation through June 1975 has been 108.3 
billion kilowatt hours, representing a gross income 
of $135.5 million to the U.S. Treasury from 
the sale of power by the Bonneville Power Administration. 
58. OTHER AUTHORIZED MULTIPLEPURPOSE 
POWER PROJECTS 
See Table 37-Q. 
General Investigations 
59. SURVEYS 
Fiscal year costs were $1,708,023 of which 
$172,017 was for navigation studies, $1,056,968 
for flood control studies, $65,082 for special 
studies, $355,812 for comprehensive basin 
studies, $15,868 for review of authorized projects 
and $42,276 for inventory of dams. 
60. COLLECTION AND STUDY 
OF BASIC DATA 
International water studies. The Columbia 
River Treaty between Canada and the United 
States of America relating to Cooperative 
Development of the Water Resources of the 
Columbia River Basin was signed at Washington, 
D.C. on January 17, 1961, and the exchange of 
ratifications took place on 16 September 1964. 
Implementation of the Treaty by the United 
States and Canada entities under the guidance of 
the Permanent Engineering Board has continued. 
The two permanent committees established 
by the entities, the Operating Committee and 
the Hydrometeorological Committee, continue to 
function. 
The Operating Committee prepared four 
reports which are issued each year by the Entities: 
the Assured Operating Plan for Operating 
Year 1980-81; the Determination of Downstream 
Benefits Resulting from Canadian Storage for 
Operating Year 1980-81; the Detailed Operating 
Plan for Operating Year 1975-76; and the annual 
report on Operation of Treaty Projects. The 
Operating Plans are based on systems analysis 
studies conducted by the Operating Committee. 
This Committee also worked on revising the document 
"Principles and Procedures for the 
Preparation and Use of Hydroelectric Operating 
Plans." 
The Hydrometeorological Committee reviewed 
and approved a new volumetric forecast 
procedure for the Canadian projects, and continued 
the ongoing planning of hydromet systems 
for support of the Treaty project operations. Costs 
during fiscal year were $82,968. 
Flood Plain Information Studies. Accomplished 
hydraulic studies and flood plain 
mapping for inclusion in two flood plain information 
reports. A narrative, including a description 
of the flood situation along each stream studied, 
was also prepared for publication in the reports. 
Both reports were started in Fiscal Year 1974, 
and will be completed in FY 1976. They are identified 
as the "McMinnville, Oregon" and 
"Sheridan-Willamina, Oregon", Flood Plain Information 
Reports. Field surveys and other 
means were used to collect basic data and accomplish 
hydraulic studies and maps for 
Portland Flood Plain Information Report. That 
report is essentially complete, and will be 
reproduced in FY 1977. Completed studies are 
37-30

PORTLAND, OREG., DISTRICT 
identified in Table 37-R. Costs for flood plain information 
studies during the fiscal year were 
$281,776. 
Hydrologic Studies. Hydrologic studies for 
Flood Plain Information Reports and Flood Insurance 
Reports have been numerous as local interests 
are becoming more concerned about 
damages resulting from floods. Environmental 
and ecological aspects are being taken into consideration 
on all hydrologic studies. The start of a 
real time automated reporting hydrologic 
network for reservoir regulation is underway 
with three design memorandums and plans and 
specifications completed in Fiscal Year 1975 and 
Invitation for Bid to be issued in FY 1976. Improvements 
in procedures to determine reservoir 
temperatures, nitrogen supersaturation, dissolved 
oxygen, suspended sediment, turbidity, design 
floods, flood forecasting and flood regulation are 
a continuing program. Costs for hydrologic 
studies during fiscal year were $13,248. Total 
costs for collection and study of basic data were 
$377,992. 
61. RESEARCH AND DEVELOPMENT 
Water quality investigation. Program of observing 
water temperatures and meteorological 
data at several of the larger and more significant 
storage projects in Willamette Basin is still active. 
The Fish Commission of Oregon is still active 
in monitoring specific projects where they have 
an interest. Stored water was released during the 
low flow season to increase streamflow for 
navigation, pollution abatement, and fish life. 
The dissolved oxygen content of Willamette River 
in the Portland area is no longer a barrier to the 
fall run of salmon that start moving into 
Willamette River in late August. The Corps 
Waterways Experiment Station has developed a 
computer program for the Portland District that 
will predict the turbidity that can be expected at 
future storage projects. This program was utilized 
in the study of Rogue River projects. Nitrogen 
supersaturation has become a water quality 
problem on Columbia River as it relates to the 
fishery industry. Studies are underway to determine 
the degree of nitrogen supersaturation and 
how best to alleviate or minimize this very serious 
problem. The State of Oregon has enacted very 
exacting laws with regard to this nitrogen 
problem. A computer program for determining 
the effect of storage projects on downstream 
water temperature has been developed and its 
application has been used extensively during the 
past year to study the downstream effects and 
enhancement that proposed storage projects will 
have on river temperatures. 
Civil Works Investigations. Water surface 
profiles, cross-sections and photographs were obtained 
from the Detroit Test Chute (ES 826) during 
Fiscal Year 1974. Compilation and review of 
the data obtained, was continued in Fiscal Year 
1975. 
Computer programs. Utilization of computer 
programs in the design and analysis of complex 
structures is a continuing program. Data reduction 
and computations of earthwork quantities, 
control of survey work, and economic analysis is 
continuing. Installation of a new electronic 
plotter has been completed. 
Total research and development costs were $1,- 
051. 
37-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-A 
See 
Section 
in Text Project 
Chetco River, 
Oreg. 
2. Columbia and Lower 
Willamette Rivers 
Below Vancouver, 
Wash. and Portland, 
Oreg. (Federal 
Funds) 
(Contributed 
Funds) 
3. Columbia River at 
Baker Bay, Wash. 
4. Columbia River at 
The Mouth, Oreg. 
and Wash. 
5. Columbia River 
Between Vancouver, 
Wash. and The 
Dalles, Oreg. 
6. Coos Bay, Oreg. 
7. Coos and Millicoma 
Rivers, Oreg. 
8. Coquille River, 
Oreg. 
9. Cowlitz River, 
Wash. 
10. Lewis River, 
Wash. 
COST AND FINANCIAL STATEMENT 
1. 
Total Cost to 
Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
48,348 
138,106 
138,106 
1,242,148 
1,221,550 
5,293 
26,586 
26,586 
-3,603 
1,219,218 
1,128,607 
2, 
2, 
189,924 265,331 
189,924 203,431 
- 272,103 
- 169,192 
919,708 1,954,789 
884,723 1,962,870 
11,540 
36,272 
37,000 
36,111 
127,036 
964,697 
960,772 
158,853 
160,168 
479,987 
477,262 
53,589 
46,102 
33,567 
32,672 
85,289 
86,383 
110,492 
73,694 
48,869 
69,061 
-29,909 
129,711 
65,389 105,752 77,654 
64,994 105,752 77,075 
445,500 2,655,000 200,000 
620,305 2,637,580 290,427 l 
4,234,194 3,905,551 3,208,928 4, 
4,021,099 4,083,295 3,126,722 4,E 
37-32 
- 2,043,713 1 
- 2,043,713 
249,800 1,024,674 
248,782 1,022,577 
250,286 27,161,876 2 
179,121 27,065,183 2 
582,500 84,126,264 3 
643,719 84,058,070 ' 
- 606,817 4 5 
9,596 606,021 4 
- 941,252 
- 941,252 
32,500 1,277,374 
32,245 1,277,119 
- 17,107,761 6 
- 17,107,761 6 
709,100 30,047,028 7 
809,362 30,032,051 
- 4,040,878 7 
- 4,040,878 
- 6,004,790 8 
- 6,004,790 8 
82,000 6,990,048 9 
143,862 6,990,048 
116,500 9,294,520 101o1 
200,831 9,275,940 10 
529,900 24,807,783 12 13 
539,407 24,787,556 12 
- 2,335,966 
- 2,335,966 
- 350,238 14 
- 350,238 
53,000 445,999 
87,694 436,778 
31,000 688,366 15 
3,298 660,664 15 
63,000 2,280,244 16 17 
56,952 2,274,196 16 17 
- 277,436 18 
- 277,436 18 
34,700 1,023,372 19 
34,222 1,022,894 19 
- 58,132 20 
- 58,132 20 
32,808 
39,271 
173,012 
153,820 
210,521 
50,901 
L 
111,,,ff

PORTLAND, OREG., DISTRICT 
TABLE 37-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
11. Port Orford, 
Oreg. 
12. Rogue River Harbor 
at Gold Beach, 
Oreg. 
13. Siuslaw River, 
Oreg. 
14. Skamokowa Creek, 
Wash. 
15. Skipanon Channel, 
Oreg. 
16. Tillamook Bay 
and Bar, Oreg. 
17. Umpqua River, 
Oreg. 
18. Willamette River 
Above Portland 
and Yamhill River, 
Oreg. 
19. Willamette River 
at Willamette 
Falls, Oreg. 
Funding 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
22,148 
22,217 
168,592 
62,287 
225,000 
110,718 
318,144 
187,913 
12,845 
11,144 
159,256 
121,486 
32,154 
32,154 
26,138 
26,447 
1,599,600 
1,628,569 
18,835 
20,047 
101,297 
109,696 
380,628 
380,628 
72,364 
5,114 
20,428 
129,628 
-76,113 
165,373 
135,151 
265,212 
19,500 
11,948 
212,627 
195,252 
-26,138 
41,112 
93,465 
92,969 
400 
4,114 
248,739 
235,301 
11,869 
12,952 
873,642 
752,110 
19,394 
19,394 
44,342 16,074 
44,342 16,074 
3,000,000 2,406,345 
2,688,643 1,912,445 2 
36,739 76,197 
27,061 85,968 
106,681 
97,241 
603,623 
603,623 
224,049 
234,849 
211,451 
206,506 
10,500 454,747 21 
10,291 454,538 21 
- 758,692 22 
- 758,692 22 
47,200 395,628 
46,519 394,451 
-286 4,156,252 23 
- 4,156,252 23 
274,000 2,217,020 24 
255,747 2,184,829 24 
- 635,783 
- 635,783 
284,878 1,488,780 25 
296,000 1,488,780 25 
349,100 3,353,043 26 27 
518,022 3,345,183 26 
- 879,285 
- 879,285 
- 2,400 
- 2,400 
9,200 147,549 
9,116 147,465 
- 280,854 
- 280,854 
122,000 625,907 
119,079 622,986 
970,000 13,973,504 28 29 
,397,518 13,963,142 28 
119,500 1,672,483 30 
115,156 1,668,110 30 
- 2,839,799 
- 2,839,799 
- 2,703,877 31 32 
- 2,703,877 31 
485,300 6,940,805 
444,077 6,899,582 
- 2,500,677 
- 2,500,677 
- 862,918 33 34 
- 862,918 33 
239,400 16,914,556 85 
205,594 16,875,805 
- 520,005 36 
- 520,005 86 
37-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
20. Yaquina Bay and 
Harbor, Oreg. 
21. Youngs Bay and 
Youngs River, Oreg. 
26. Applegate Lake, 
Rogue River Basin, 
Oreg. 
27. Beaver Drainage 
District, Oreg. 
28. Beech Creek at 
Mount Vernon, Oreg. 
29. Blue River 
Lake, Oreg. 
30. Cascadia Lake, 
Oreg. 
31. Cottage Grove Lake, 
Oreg. 
32. Cowlitz County 
Consolidated 
Diking Improvement 
District No. 2, Wash. 
33. Days Creek 
Lake, Oreg. 
34. Dorena Lake, 
Oreg. 
35. Elk Creek Lake, 
Rogue River Basin, 
Oreg. 
36. Fall Creek 
Lake, Oreg. 
Funding 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
188,300 
432,425 
3,425,400 
3,418,520 
394,642 
394,248 
-OO 
9,L
5, 
5, 
5, 
20,( 
1, 
21,( 
98,1 
58,( 
51,E 
218,157 
221,671 
411,000 
416,344 
386,416 
386,558 
G41 
289 3,995 
569 2,344 
569 2,344 
000 58,609 
775 52,633 
42,400 
91 29,179 
5,390 
717 3,729 
000 503,000 
139 202,050 
059 94,762 
537 101,542 
1,380 
459 
172,341 
119,647 
182,787 
161,945 
8,027 
-877 
98 
104,093 
136,141 
1,106,700 
1,123,255 
343 
90,402 
90,511 
330,829 
449,927 
200,432 
220,883 
356,000 
37,747 
15,000 
15,000 
127,197 
123,560 
2,878,379 
2,132,651 
124,942 
39,617 
165,665 
159,767 
445,452 
441,799 
-6,413 
701,254 
702,254 
-2,200 
6,548 
7,305 
7,305 
163,000 
68,276 
39,000 
50,102 
50,000 
48,665 
2,680,000 
2,960,948 
78,888 
69,932 
1,786 
103,745 
231,502 
232,331 
-160,000 
145,133 
147,943 
157,236 
1,385,000 
2,091,044 
34,709 
109,576 
129,931 
134,702 
247,700 8,102,323 37 
243,710 8,094,608 
234,794 
- 234,794 
- 19,242,046 38 39 
- 19,242,046 38 
721,300 7,709,007 40 
717,631 7,705,338 40 
- 12,005 
- 12,005 
-220,000 54,187 41 
330 51,840 41 
1,613 67,494 
1,613 67,494 
1,000,000 1,971,609 
393,568 1,241,042 
302,086 491,366 
136,169 323,288 
230 93,237 42 
1,289 91,276 
-25,000 32,049,000 43 
10,643 32,038,225 43 
43,000 395,391 
50,837 394,112 
- 1,066,380 44 
63 1,066,114 44 
10,000 3,282,097 45 
35 3,271,997 
227,110 2,263,900 46 
217,153 2,253,294 46 
-4,500 1,658,828 
1,741 1,650,189 
300,514 
164,452 
148,150 
148,007 
1,730,000 
1,936,163 
100,000 
38,640 
173,740 
174,741 
300,514 
164,452 
14,057,562 47 
14,057,562 47 
1,771,174 
1,770,788 
8,177,079 
8,155,344 
21,351,651 48 
21,279,833 48 
1,063,265 
1,062,917 
37-34

PORTLAND, OREG., DISTRICT 
TABLE 37-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project Funding 
37. Fern Ridge Lake, New Work 
Oreg. Approp. 
Cost 
Maint. 
Approp. 
Cost 
39. Lower Columbia New Work 
River Basin Bank Approp. 
Protection Works, Cost 
Oreg. and Wash. 
40. Scappoose Drainage New Work 
District, Oreg. Approp. 
Cost 
41. Vancouver Lake New Work 
Area, Wash. Approp. 
Cost 
42. Wahkiakum County New Work 
Consolidated Diking Approp. 
District No. 1, Cost 
Wash. 
44. Willamette River New Work 
Basin, Oreg. (Bank Approp. 
Protection) Cost 
Maint. 
Approp. 
Cost 
49. Bonneville Lock and New Work 
Dam-Lake Bonneville, Approp. 
Oreg. and Wash. Cost 
Maint. 
Approp. 
Cost 
50. Cougar Lake, Oreg. New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
51. Detroit Lake, Oreg. New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
52. Green Peter-Foster New Work 
Lakes, Oreg. Approp. 
Cost 
Maint. 
Approp. 
Cost 
53. Hills Creek New Work 
Lake, Oreg. Approp. 
Cost 
Maint. 
Approp. 
Cost 
54. John Day Lock and New Work 
Dam-Lake Umatilla- Approp. 
Oreg. and Wash. Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
105,958 984 1,567,000 166,500 7,819,404 49 
28,782 101,189 705,012 871,839 7,662,755 49 
172,358 728,713 380,621 392,000 3,674,733 5 
165,814 282,565 317,236 416,730 3,633,300 
457,082 1,125,000 600,000 438,200 7,043,745 
302,387 923,899 868,413 359,134 6,875,053 
5,000 16,000 169,000 280,000 
5,075 15,612 167,016 98,576 
288,500 -53,609 -7,000 -500 
119,492 99,129 6,204 426 
99,300 18,000 231,000 359,000 
96,497 24,017 94,790 297,782 
184,017 
197,224 
73,500 
73,530 
5,184,241 
5,505,886 
2,028,620 
2,175,025 
1,002,304 
971,987 
227,363 
211,398 
567,281 
587,232 
2,805 
1,665,000 
818,076 
637,778 
615,382 
400,000 
340,127 
97,089 
97,149 
4,760,229 
4,416,350 
2,447,729 
2,276,725 
157,000 
62,256 
253,238 
258,031 
876,348 
713,071 
82,419 
786,000 
983,769 
749,430 
744,126 
700,000 
328,180 
317,695 
185,961 
8,107,391 
7,975,787 
2,665,998 
2,772,030 
880,000 
225,778 
328,055 
335,857 
824,638 
771,079 
-20,120 
1,650 
575,323 
893,250 
941,561 
171,255 216,401 256,069 
163,745 217,733 262,707 
7,758,700 6,331,000 10,742,000 
7,545,631 6,249,884 3,571,995 
1,994,516 2,437,058 2,214,563 
1,988,249 59 2,436,064 60 2,153,8356 
570,339 
386,292 
292,391 
290,143 
819,108 
621,082 
395,700 14,864,141 52 
827,211 14,863,962 52 
90,000 2,420,944 
211,152 2,410,362 
19,250,952 127,165,958 " 
19,463,086 126,593,458 " 
3,872,000 55,188,701 * 
2,886,768 54,091,410 * 
250,000 55,588,718 " 
830,856 55,367,233 " 
278,700 2,803,616 
277,272 2,798,211 
- 62,729,698 
- 62,729,698 
718,000 10,939,667 
911,704 10,901,719 
- 363,086 
- 363,086 
25,000 83,986,000 57 
78,014 83,940,831 57 
876,000 - 5,030,184 
815,401 4,962,324 
- 45,700,619 
- 45,700,619 
265,100 2,487,267 
259,554 2,481,047 
4,700,000 471,308,262 51 
12,574,408 471,022,766 
2,765,900 13,978,559 
2,431,022 13,548,250 
37-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
55. Lookout Point New Work 
Lake, Oreg. Approp. -89 - 235,000 130,000 88,306,395 8 
Cost 8,239 - 42,091 209,144 88,192,630 8 
Maint. 
Approp. 759,958 1,018,615 853,991 1,012,900 11,892,150 
Cost 672,590 1,105,542 884,449 971,886 11,834,952 
56. Lost Creek Lake, New Work 
Rogue River Approp. 7,794,600 24,372,000 21,050,000 23,871,500 91,583,100 
Basin, Oreg. Cost 7,879,913 22,066,562 17,496,917 29,590,330 91,235,830 
57. The Dalles Lock New Work 
and Dam-Lake Approp. 20,041,485 5,166,216 1,145,000 425,000 297,991,022 62 
Celilo, Wash. Cost 20,201,764 5,016,206 1,059,430 424,660 297,180,761 62 
and Oreg. Maint. 
Approp. 1,822,100 1,688,376 2,058,555 2,619,000 26,884,548 
Cost 1,639,257 1,836,053 1,982,637 2,433,557 26,574,221 
37-36

PORTLAND, OREG., DISTRICT 
TABLE 37-A (Continued) COST AND FINANCIAL STATEMENT 
1. Excludes $17,742 contributed funds for new work. 
2. Includes $1,529,413 for previous project. 
3. Includes $150,955 allotted from deferred maintenance 
funds, Code 700, $62,296 for public works accelerated 
program repair, and $1,214,865 for previous project. Excludes 
$24,320 expended from contributed funds prior to 
1964.
4. Excludes $31,636 contributed by City of Astoria and 
Bumble Bee Sea Foods, Astoria, Oregon (not part of regular 
project). 
5. Includes $223,026 expended from contributed funds 
prior to 1964 and $369,000 contributed by Port of Portland 
and $14,792 by Port of Vancouver, paid prior to commencement 
of dredging of 40-foot and 35-foot channel authorization. 
6. Includes $1,986,253 for previous project and $158,111 
allotted under Code 711, recreation facilities at completed 
project. Excludes $500,000 contributed funds. 
7. Includes $2,186,000 for previous project and $1,188,- 
625 allotted under deferred maintenance, Code 700. 
8. Includes funds allotted under Code 721 (small 
authorized projects) $30,393 Entrance to Oregon Slough 
$161,897 Camas-Washougal Turning Basin; $227,908 Hood 
River Small Boat Basin; $157,470 Bingen, Wash., Barge 
Channel; and $140,619 The Dalles Small Boat Basin; and $15,- 
281 allotted under Section 107 Barge Channel under Interstate 
Bridge. 
9. Includes $2,033,408 allotted under Code 700 (Deferred 
Maintenance). 
10. Includes $802,096 for previous project. Excludes $43,- 
513 expended from contributed funds. 
11. Includes $26,821 allotted under Sec. 107. 
12. Includes $178,801 for previous project. Excludes $8,- 
387 expended from contributed funds. 
13. Includes $1,444,640 allotted under Code 700, Deferred 
Maintenance. 
14. Excludes $80,000 (other funds) contributed for new 
work by Port of Coos Bay to cover additional cost of disposing 
of dredge spoils in Coos Bay, Oreg. 
15. Includes $340,726 for previous project. Excludes $72,- 
891 contributed funds expended for new work. Includes $31,- 
000 allotted under Code 711. 
16. Includes $41,467 for previous project. 
17. Includes $78,500 allotted under Code 700, Deferred 
Maintenance. 
18. Includes $4,999 for previous project. Also includes 
$239,529 Section 107 funds. 
19. Includes $48,184 for previous project. 
20. Includes $22,252 for previous project. 
21. Includes $8,098 for previous project. 
22. Excludes $9,900 contributed funds. 
23. Excludes $13,779 (other funds) contributed for additional 
landfill and extension of drainage lines. 
24. Includes $20,750, Wedderburn Study Funds. 
25. Includes $151,701 for previous project. Excludes 
$322,532 expended from contributed funds. Also includes 
$329,423 Section 107 funds. 
26. Includes $10,611 for previous project. 
27. Includes $188,000 allotted under Code 700, Deferred 
Maintenance. 
28. Includes $77,209 for previous project. Excludes $592,- 
622 expended from contributed funds and $300,000 expended 
for channel dredging by local interest. 
29. Includes $57,767 allotted under Code 720 (Small 
Authorized Projects) Garibaldi Boat Basin. 
30. Includes $71,498 for previous project. Excludes $6,450 
expended from contributed funds. 
31. Includes $39,242 for previous project. Excludes $276,- 
500 contributed funds. 
32. Includes $58,824 allotted under Code 720 (Small 
Authorized Projects) Winchester Bay, and Schofield River, 
Oregon. 
33. Includes $247,748 for previous project. 
34. Excludes $484,900 Emergency Relief Administration 
flood control funds for bank protection. 
35. Includes $51,500 allotted from deferred maintenance 
funds Code 700, and $35,935 for Public Works Acceleration 
program repair. In addition $7,500 for maintenance was expended 
from contributed funds and $246,637 on operating 
and care of improvements under provisions of permanent indefinite 
appropriation. 
36. Excludes $300,000 contributed funds. 
37. Includes $452,110 expended on operation and care 
from permanent indefinite appropriation and $150,000 
allotted under maintenance and operation of dams and other 
improvements of navigable waters. 
38. Includes $707,313 for previous project and $170,000 
appropriated from public works acceleration program for 
north jetty rehabilitation. Also includes $53,277 Section 107 
funds. 
39. Excludes $729,168 contributed funds. 
40. Includes $6,026 for previous project. 
41. Includes $9,348 for work completed in 1938 and $44,- 
839 for Lewis and Clark Connecting Channel Section 107. 
42. Includes $43,007 received and expended by Walla 
Walla District. 
43. Includes $96,000 pro rata share of site selection costs in 
lieu of Quartz Creek Lake. 
44. Includes $112,000 pro rata share of site selection costs 
in lieu of Sweet Home Lake. 
45. Includes $908,803 allotted under Code 711, recreation 
facilities at completed project. 
46. Includes $3,000 special recreation use fees. 
47. Includes $528,090 allotted under Code 711, recreation 
facilities at completed project. 
48. Includes $259,650 allotted under Code 711, recreation 
facilities at completed project. 
49. Includes $765,164 allotted under Code 711 and $2,421,- 
978 allotted under Code 712, recreation facilities at completed 
project and $136,482 allotted under Code 721 (small authorized 
project) reservoir modification. Excludes $2,100 (other 
funds contributed). 
50. Includes $9,750 allotted under Code 700, deferred 
maintenance. 
51. Reported by Walla Walla District prior to 1974. 
52. Excludes $77,469 contributed funds. 
53. Includes $12,200,000 Public Works Administration 
funds and $20,240,700 National Recovery Act funds. 
54. Includes $25,397,700 modification for peaking funds 
$18,092,352 second powerhouse funds and $436,511 allotted 
under Code 711, recreation facilities at completed project. 
55. Includes $540,000 allotted from deferred maintenance 
funds, Code 700 and $450,000 allotted under maintenance and 
operation of dams and other improvements of navigable 
waters. 
56. Includes $96,000 pro rata share of site selection in lieu 
of Quartz Creek Lake. 
57. Includes $113,000 pro rata share of site selection costs 
in lieu of Sweet Home Lake. 
58. Includes $525,611 allotted under Code 711, recreation 
facilities at completed project. 
59. Includes $63,500 for O&M of Spring Creek Hatchery 
(funds are revoked and paid to USFWS at OCE level, but are a 
cost to project). 
60. Includes $164,100 for O&M and fish evaluation of Spring 
Creek Hatchery (funds are revoked and paid to USFWS at 
OCE level, but are a cost to project). 
61. Includes $213,500 for O&M and fish evaluation of Spring 
Creek Hatchery (funds are revoked and paid to USFWS at 
OCE level, but are a cost to project); and $3,000 special recreation 
use fees. 
62. Includes $985,318 allotted under Code 712, $138,682 
allotted under Code 711, recreation facilities at completed 
project, and $49,940,700 additional units 15-22 funds. 
37-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 2, 1945 
Oct. 27, 1965 
Feb. 27, 1911 
July 25, 1912 
July 27, 1916 
Aug. 8, 1917 
Sept. 22, 1922 
Mar. 4, 19232 
Mar. 3, 1925 
Mar. 3, 1927 
July 3, 1930 
Sept. 6, 19333 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
Oct. 23, 1962 
Oct. 23, 1962 
CHETCO RIVER, OREG. (See Section 1 of Text) 
To provide for the stabilization of the channel, by 
constructing jetties and dredging. 
Modification of channel entrance and channel 
improvements. 
COLUMBIA AND LOWER WILLAMETTE RIVERS 
BELOW VANCOUVER, WASH., AND PORTLAND, OREG. 
(See Section 2 of Text) 
2 pipeline dredges and accessories. 
Increasing main channel to 30 feet. 
Consolidating improvement below Portland, Oreg., 
and between Vancouver, Wash., and Mouth of 
Willamette. 
For the Cathlamet channel. 
Construct an additional dredge (dredge was not built) 
and accessories for better maintenance, and construct 
contraction works. 
Channel from deep water in Willamette Slough to deep 
water in Columbia River. 
Depth of 25 feet and width of 300 feet from mouth of 
Willamette River to Vancouver, Wash. 
Closing east channel at Swan Island in Willamette 
River on condition that main channel to be opened 
to project dimensions on west side of island by 
Port of Portland. 
For a 35-foot channel 500 feet wide from Portland 
to the sea. 
A channel 28 feet deep and 300 feet wide from mouth of 
Willamette River to Vancouver, with 2 turning basins, 
each generally 28 feet deep by 800 feet wide by 2,000 
feet long. 
A channel in Columbia River from Mouth of Willamette to 
interstate highway bridge at Vancouver, Wash., 30 feet 
deep and 300 feet wide, with 2 turning basins at 
Vancouver. 
Maintenance of not to exceed 35-foot depth at low water 
in Portland Harbor and Willamette River between its 
mouth and Broadway Bridge at Portland. 
Auxiliary channels, 30 feet deep, 300 feet and 500 
feet at St. Helens. 
Extension of lower turning basin at Vancouver, Wash., 
1,000 feet downstream. 
An auxiliary channel 24 feet deep and 200 feet wide 
along waterfront at Rainier, Oreg. 
Improvement of old mouth of Cowlitz River. 
An auxiliary channel in vicinity of Longview, W~ash. 
A small-boat mooring basin at Astoria, Oreg. 
A channel 35 feet deep and 500 feet wide from mouth of 
Willamette River to interstate highway bridge at 
Vancouver, Wash., with 2 turning basins of same depth. 
A channel 40 feet deep and 600 feet wide from Vancouver, 
Wash., to Mouth of Columbia River; a turning basin at 
Vancouver, Wash., a turning basin at Longview, Wash., 
37-38 
H. Doc. 817, 77th Cong., 
2nd Sess. 
S. Doc. 21, 89th Cong., 
1st Sess. 
H. Doc. 1278, 61st Cong., 
3rd Sess.i 
H. Doc. 1278, 61st Cong., 
3rd Sess.' 
No Prior Report. 
H. Doc. 120, 63rd Cong., 
1st Sess.' 
H. Doc. 1009, 66th Cong., 
3rd Sess. 
H. Doc. 156, 67th Cong., 
2nd Sess. 
H. Doc. 126, 68th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 10, 
69th Cong., 2nd Sess. 
H. Doc. 195, 70th Cong., 
1st Sess. and Rivers and 
Harbors Committee 
Doc. 8, 71st Cong., 
1st Sess.' 
H. Doc. 249, 72nd Cong., 
2nd Sess.i 
Rivers and Harbors 
Committee Doc. 1, 
7.4th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 6, 
73rd Cong., 1st Sess.i 
H. Doc. 235, 72nd Cong., 
1st Sess.' 
Rivers and Harbors 
Committee Doc. 81, 
74th Cong., 2nd Sess.' 
H. Doc. 203, 75th Cong., 
1st Sess.' 
H. Doc. 341, 77th Cong., 
1st Sess.i 
H. Doc. 630, 77th Cong., 
2nd Sess.' 
H. Doc. 692, 79th Cong., 
2nd Sess.' 
H. Doc. 203, 87th Cong., 
1st Sess. 
H. Doc. 452, 87th Cong., 
2nd Sess.'

PORTLAND, OREG., DISTRICT 
TABLE 37-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Dec. 11, 1933 
Aug. 30, 1935 
Mar. 2, 1945 
Mar. 17, 1950 
Mar. 3, 1905 
Sept. 3, 1954 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 14, 1960 
June 25, 1910 
Mar. 2, 1919 
Sept. 22, 1922 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
July 24, 1946 
June 30, 1948 
July 14, 1960 
and a channel 40 feet deep in Willamette River from 
mouth to Broadway Bridge which encompasses Portland 
Harbor area. 
COLUMBIA RIVER AT BAKER BAY, WASH., 
(See Section 3 of Text) 
Main channel 
Main channel 
West channel 8 feet deep 
West channel 10 feet deep and mooring basin with 
protecting breakwaters. 
COLUMBIA RIVER AT THE MOUTH, OREG. AND 
WASH. (See Section 4 of Text) 
Extend South Jetty and construct North Jetty and 
dredging. 
Bar channel of 48-foot depth and spur jetty on north 
shore. 
COLUMBIA RIVER, BETWEEN VANCOUVER, WASH., 
AND THE DALLES, OREG. (See Section 5 
of Text) 
Construct a channel 27 feet deep by 300 feet from 
Vancouver, Wash., to Bonneville, Oreg. 
Construct Camas-Washougal turning basin. 
Construct a channel 27 feet deep by 300 feet wide from 
Bonneville, Oreg., to The Dalles, Oreg. 
Construct a boat basin at Hood River, Oreg., 10 feet 
deep, 500 feet wide, by 1,300 feet long. 
Construct a barge channel at Bingen, Wash., 10 feet 
deep, 200 feet wide, by 1 mile long, and an access 
channel 7 feet deep, 100 feet wide, by 1,000 feet 
long to natural mooring basin. 
Construct The Dalles Harbor 8 feet deep, 400 feet wide 
by 800 feet long. 
Construct alternate barge Channel 15 feet deep and 300 
feet wide, under wide span of Interstate Hwy. Bridge. 
COOS BAY, OREG. (See Section 6 of Text) 
Dredging the Ocean Bar Channel 
A channel 22 feet deep to Smith's Mill 
Restore North Jetty 9,600 feet long, construct a South 
Jetty about 3,900 feet long, extend 22-foot bay channel 
from Smith's Mill to Millhngton. 
Extend jetties to such lengths as may be practicable 
within estimate of total cost of jetties, $3,250,000 
as given in H. Doc. 150, 67th Cong. 
A channel 24 feet deep and 300 feet wide, through 
Pigeon Point Reef, following a location along westerly 
side of bay. 
For 24-foot channel from Pigeon Point Reef to Smith's 
Mill and a turning basin above Marshfield. 
Increased dimensions of channel across bar and to 
Isthmus Slough and turning basin opposite Coalbank 
Slough and at City of North Bend; anchorage basins 
at mile 3.5 and near mile 7. 
A mooring basin and connecting channel at Charleston. 
Channel extension in South Slough near Charleston. 
37-39 
Public Works 
Administration 
H. Doc. 44, 73rd Cong., 
1st Sess. 
H. Doc. 443, 76th Cong., 
1st Sess. 
S. Doc. 95, 81st Cong., 
1st Sess. 
H. Doc. 94, 56th Cong., 
1st Sess. 
H. Doc. 249, 83rd Cong., 
2nd Sess.' 
H. Committee Doc. 94, 
74th Cong., 2nd Sess.i 
H. Doc. 218, 76th Cong., 
1st Sess. 
H. Doc. 704, 79th Cong., 
2nd Sess. 
H. Doc. 704, 79th Cong., 
2nd Sess. 
H. Doc. 704, 79th Cong., 
2nd Sess. 
S. Doc. 89, 79th Cong., 
1st Sess.' 
Sec. 107 approved 
Dec. 5, 1962 
H. Doc. 958, 60th Cong., 
1st Sess. 
H. Doc. 325, 65th Cong., 
1st Sess. 
H. Doc. 150, 67th Cong., 
2nd Sess. 
H. Doc. 110, 70th Cong., 
1st Sess.i 
S. Committee Print, 
73rd Cong., 2nd Sess.i 
S. Doc. 253, 79th Cong., 
2nd Sess. 
H. Doc. 646, 80th Cong., 
2nd Sess. 
Sec. 107 approved Oct. 
1968

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Dec. 31, 1970 
June 3, 1896 
June 30, 1948 
June 25, 1910 
Mar. 2, 1919 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
June 25, 1910 
June 25, 1910 
July 14, 1960 
March 3, 1897 
March 4, 1913 
Oct. 27, 1965 
Sept. 3, 1954 
June 25, 1910 
Mar. 3, 1925 
July 3, 1958 
July 14, 1960 
March 2, 1919 
July 3, 1930 
Increase dimensions to provide for bar channel 45 feet 
deep, inner channel 35 feet deep to mile 15, and 
deepening and widening existing turning basins and 
anchorage area. 
COOS AND MILLICOMA RIVERS, OREGON 
(See Section 7 of Text) 
Dredging channel from mouth to head of navigation. 
For a 5 ft. depth from mouth to head of navigation on 
the Millicoma River and South Fork. Except on 
South Fork above M. 14 where 3 ft. will suffice. 
COQUILLE RIVER, OREG. (See Section 8 of Text) 
Dredging shoals between mouth and Riverton, and removing 
obstruction between mouth of North Fork and Bandon. 
For a 13-foot channel from ocean to Bandon. 
Deepen channel to 16 feet between sea and eastern end 
of North Jetty. 
Present project depth between sea and eastern end of 
North Jetty. 
For 13-foot depth from sea to a point 1 mile above 
Coquille River Lighthouse and snagging to State 
Highway Bridge. 
COWLITZ RIVER, WASH. (See Section 9 of Text) 
To provide a channel 4 ft. deep from mouth to 
Ostrander; 2.5 ft. deep to Castle Rock. 
Extend channel to Toledo. 
Modification of original channel to 8 ft. deep and 100 
ft. wide for lower 4.75 miles. 
LEWIS RIVER, WASH. (See Section 10 of Text) 
Provide a channel to head of navigation. 
Increase the control depth and widen channel. 
PORT ORFORD, OREG. (See Section 11 of Text) 
Extension of existing breakwater by 550 feet. 
ROGUE RIVER, HARBOR AT GOLD 
BEACH, OREG. (See Section 12 of Text) 
Two jetties at entrance and improvement of channel. 
SIUSLAW RIVER, OREG. (See Section 13 of Text) 
Extension of jetties. 
12-foot deep channel. 
18-foot bar channel and 16-foot river channel and a 
600-foot extension of North Jetty. 
Cushman-Mapleton Channels 
SKAMOKAWA CREEK, WASH. (See Section 14 of Text) 
Channel 6.5 feet deep and 75 feet wide, at low water 
between Steamboat and Brooks Slough. 
SKIPANON CHANNEL, OREG. (See Sec. 15 of Text) 
Channel from deep water in Columbia River to railroad 
bridge. 
37-40 
H. Doc. 151, 91st Cong., 
2nd Sess. 
H. Doc. 237, 53d Cong., 
3rd Sess. 
S. Doc. 124, 8th Cong., 
2nd Sess. 
H. Doc. 673, 61st Cong., 
2nd Sess. 
H. Doc. 207, 65th Cong., 
1st Sess. 
H. Doc. 186, 70th Cong., 
1st Sess.' 
S. Committee Print, 74th 
Cong., 1st Sess. 
H. Doc. 672, 76th Cong., 
2nd Sess.' 
H. Doc. 1167, 60th Cong. 
2nd Sess. 
H. Doc. 404, 61st Cong., 
2nd Sess. 
Sec. 107 approved 
Jan. 3, 1965 
H. Doc. 64, 55th Cong., 
1st Sess. 
H. Doc. 28, 62nd Cong., 
1st Sess. 
S. Doc. 62, 88th Cong., 
2nd Sess. 
S. Doc. 83, 83rd Cong., 
2nd Sess. 
H. Doc. 648, 61st Cong., 
2nd Sess.8 
S. Committee Print, Serial, 
68th Cong., 1st Sess. 
H. Doc. 204, 85th Cong., 
1st Sess.' 
Sec. 107 approved 
Mar. 18, 1974 
H. Doc. 3, 63rd Cong., 
1st Sess. 
H. Doc. 278, 70th Cong., 
1st Sess.'

PORTLAND, OREG., DISTRICT 
TABLE 37-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 26, 1937 
June 30, 1948 
July 26, 1912 
Mar. 4, 1913 
Mar. 2, 1919 
Mar. 3, 1925 
Mar. 2, 1945 
June 30, 1948 
Sept. 3, 1954 
Oct. 27, 1965 
Sept. 22, 1922 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
June 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
June 30, 1948 
Sept. 3, 1954 
June 3, 1896 
June 3, 1896 
July 25, 1912 
July 3, 1930 
Channel extending upstream from railroad bridge a 
distance of 4,500 feet. 
Mooring basin 12 feet deep at Warrenton. 
TILLAMOOK BAY AND BAR, OREG. 
(See Section 16 of Text) 
Construct NJorth Jetty 5,700 feet long and dredging 
channel 16 feet deep, 200 feet wide, to Bay City. 
Abandon that portion of project above Bay City. 
Abandon Bay City Channel and present project dimension 
of channels and turning basins with regulating works 
as needed. 
Repair damage and check erosion on Bayocean Peninsula 
caused by storm Jan. 1939. 
Dredging small-boat basin and approach at Garibaldi, 
Oreg., to depth of 12 feet. 
Closure of breach in Bayocean Peninsula. 
Construct South Jetty, 8,000 feet long. 
UMPQUA RIVER, OREG. (See Section 17 of Text) 
North Jetty, 7,500 feet long. 
Present project dimensions of North Jetty and dredging 
ocean bar. 
A short south jetty. 
A full length south jetty and maintenance dredging to 
a 26-foot length. 
Channel 22 feet deep and 200 feet wide from mouth to 
Reedsport. 
Channel 22 feet deep and 200 feet wide from river 
channel to Gardiner and turning basin 22 feet deep, 
500 feet wide and 800 feet long. 
Channel 10 feet deep and 100 feet wide from river 
channel to dock in Winchester Bay with mooring and 
turning basin 10 feet deep, 175 feet wide, and 300 
feet long at inner end. 
Channel 12 feet deep and 100 feet wide from river 
channel to dock in Winchester Bay with mooring and 
turning basin 12 feet deep, 175 feet wide, and 300 
feet long at inner end.1 
Channel 12 feet deep, Scholfield River. 
WILLAMETTE RIVER ABOVE PORTLAND AND 
YAMHILL RIVER, OREG.8 (See Section 18 
of Text) 
Improvement of Willamette River above Oregon City. 
Improvement of Yamhill River by lock and dam 
construction. 
Project modified in 1904 by abandoning 20-mile stretch 
of river between Harrisburg and Eugene as unworthy of 
improvement. 
A 6-foot channel in Willamette River below Oregon City. 
For 8-foot channel between Portland and Oregon City. 
37-41 
H. Doc. 201, 75th Cong., 
1st Sess.' 
S. Doc. 95, 81st Cong., 
1st Sess.' 
H. Doc. 349, 62nd Cong., 
2nd Sess. 
H. Doc. 760, 65th Cong., 
2nd Sess. 
H. Doc. 562, 68th Cong., 
2nd Sess.4 
S. Doc. 35, 79th Cong., 
1st Sess.5 
H. Doc. 650, 80th Cong., 
1st Sess. 
S. Doc. 128, 83rd Cong., 
2nd Sess.' 
S. Doc, 43, 89th Cong., 
1st Sess.' 
H. Doc. 913, 65th Cong., 
2nd Sess. 
H. Doc. 320, 69th Cong., 
1st Sess. 
H. Doc. 317, 70th Cong., 
1st Sess.' 
Rivers and Harbors 
Committee Doc. 9, 
72nd Cong., 1st Sess.' 
S. Doc. 158, 75th Cong., 
3rd Sess.' 
S. Doc. 86, 76th Cong., 
1st Sess.' 
S. Doc. 191, 77th Cong., 
2nd Sess.' 
S. Doc. 154, 80th Cong., 
2nd Sess.' 
S. Doc. 133, 81st Cong., 
2nd Sess.' 
H. Doc. 260, 54th Cong., 
1st Sess. (Annual Report, 
1896, p. 3300) 
Annual Report, 1895, 
p. 3602 
Annual Report, 1904, 
p. 3529 
H. Doc. 438, 62nd Cong., 
2nd Sess. 
H. Doc. 372, 71st Cong., 
2nd Sess.'

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 26, 19346 
June 28, 19387 
June 25, 1910 
Aug. 8, 1917 
June 26, 19347 
Mar. 2, 1945 
Mar. 2, 1919 
Aug. 26, 1937 
Mar. 2, 1945 
July 24, 1946 
July 3, 1958 
Aug. 30, 1935 
July 14, 1960 
Oct. 23, 1962 
June 22, 1936 
May 17, 1950 
June 30, 1948 
March 17, 1950 
Operating and care of lock and dam at Yamhill River and 
provided for with funds from War Department appropriations 
for rivers and harbors. 
Streamflow regulation with controlling depths of 6 feet 
to Mouth of Santiam River and 5 feet to Albany with 
enlargement of locks at Oregon City. 
Operation of Yamhill Lock was discontinued February 7, 
1954, and the lock and adjacent property turned over 
to Yamhill County January 16, 1959. 
WILLAMETTE RIVER AT WILLAMETTE FALLS, 
OREG. (See Section 19 of Text) 
For purchase and rehabilitation of system and construction 
of concrete division wall. 
Deepening of locks. 
Operation and care of canal and locks provided for with 
funds from War Department appropriations for Rivers 
and Harbors. 
Construction of New Willamette Falls Lock. 
YAQUINA BAY AND HARBOR, OREG. 
(See Section 20 of Text) 
Restoration and extension of jetties constructed under 
previous projects, rock removal at entrance, and dredging 
in bay up to railroad terminus at Yaquina. 
Extension of north jetty seaward 1,000 feet. 
26-foot channel of suitable width across entrance bar, 
so far as rock bottom will allow, a 20-foot channel 
300 feet wide along south side of bay to and including 
a turning basin 22 feet deep, 1,000 feet wide and 
1,200 feet long. 
Construct a small-boat mooring basin at Newport, Oreg. 
40-foot bar channel and 30-foot river channel and 
extension of jetties at entrance. 
YOUNGS BAY AND YOUNGS RIVER, OREG. 
(See Section 21 of Text) 
Improvements to channel, from mouth to Haven Island 
and 4 miles up Youngs River. 
A channel 10 feet deep, 150 feet wide from existing 
channel in Youngs River to Lewis and Clark River. 
APPLEGATE LAKE, ROGUE RIVER BASIN, OREG. 
(See Section 26 of Text) 
Authorizes a rockfill embankment dam. 
BEAVER DRAINAGE DISTRICT, COLUMBIA COUNTY, 
OREG. (See Section 27 of Text) 
Improvements to existing levee and additional levee 
and revetment construction. 
Authorizes upgrading of existing improvements. 
BEECH CREEK, MT. VERNON, OREGON 
(See Section 28 of Text) 
Channel enlargement, levees and bank revetment. 
BLUE RIVER LAKE, OREGON (See Section 29 of Text) 
Authorizes gravel-filled embankment dam. 
H. Doc. 544, 75th Cong., 
3rd Sess. 
H. Doc. 202, 56th Cong., 
1st Sess. and Annual 
Report, 1900, p. 4374 
H. Doc. 1060, 62nd Cong., 
3rd Sess.1 
H. Doc. 544, 75th Cong., 
3rd Sess.8 
H. Doc. 109, 65th Cong., 
1st Sess. 
S. Committee Print, 75th 
Cong., 1st Sess. 
S. Doc. 119, 77th Cong., 
1st Sess.' 
S. Doc. 246, 79th Cong., 
2nd Sess. 
S. Doc. 8, 85th Cong., 
1st Sess.i 
H. Doc. 209, 72nd Cong., 
1st Sess. 
Sec. 107 approved 
Jan. 7, 1970 
H. Doc. 566, 87th Cong., 
2nd Sess. 
F.C. Act 1936 
H. Doc. 531, 81st Cong., 
2nd Sess. 
Sec. 205 Approved 
Nov. 1, 1973 
H. Doc. 531, 81st Cong., 
2nd Sess. 
37-42

PORTLAND, OREG., DISTRICT 
TABLE 37-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
March 16, 1938 
May 16, 1950 
March 7, 1974 
March 16, 1938 
Oct. 23, 1962 
March 20, 1950 
March 16, 1938 
Oct. 23, 1962 
March 20, 1950 
March 20, 1950 
June 22, 1936 
March 20, 1950 
March 20, 1950 
March 20, 1950 
CASCADIA LAKE, OREG., (See Section 30 of Text) 
Authorizes rockfill embankment dam. 
COTTAGE GROVE LAKE, OREG., (See Section 31 
of Text) 
Earthfill dam. 
COWLITZ COUNTY CONSOLIDATED DIKING 
IMPROVEMENT DISTRICT NO. 2, WASH. 
(See Section 32 of Text) 
Raising and strengthening existing levees and 
constructing new ones. 
DAYS CREEK LAKE, OREG. (See Section 33 of Text) 
Earthfill dam. 
DORENA LAKE, OREG., (See Section 34 of Text) 
Earthfill dam. 
ELK CREEK LAKE, ROGUE RIVER BASIN, OREG., 
(See Section 35 of Text) 
Rock and gravel embankment dam. 
FALL CREEK LAKE, OREG. 
(See Section 36 of Text) 
Earth and gravel fill embankment dam. 
FERN RIDGE LAKE, OREG. 
(See Section 37 of Text) 
Earthfill embankment dam. 
Raise height of dam to obtain additional storage. 
LOWER COLUMBIA RIVER BASIN, OREG. AND 
WASH. (See Section 38 of Text) 
Bank protection work, improvements to existing 
projects, and construction of flood control works 
in Lower Columbia River Basin. 
LOWER COLUMBIA RIVER BANK PROTECTION, 
OREG. AND WASH. (See Section 39 of Text) 
Provides bank protection on Columbia River below 
river mile 125 and along principal tributaries. 
SCAPPOOSE DRAINAGE DISTRICT, OREG. 
(See Section 40 of Text) 
Construction of levee system. 
Raising and strengthening of levee. 
VANCOUVER LAKE AREA, WASH. 
(See Section 41 of Text) 
Raising and strengthening existing levee. 
WAHKIAKUM COUNTY CONSOLIDATED DIKING 
DISTRICT NO. 1, WASH. (See Section 42 of Text) 
Raising and strengthening all levees encircling 
islands. Construct drainage canal, tide box and 
pumping plant. 
H. Doc. 403, 87th Cong., 
2d Sess. 
H. Doc. 544, 75th Cong., 
3rd Sess. 
H. Doc. 541, 81st Cong., 
2nd Sess. 
H. Doc. 371, 92nd Cong., 
2nd Sess. 
H. Doc. 544, 75th Cong., 
3rd Sess. 
H. Doc. 566, 87th Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
H. Doc. 544, 75th Cong., 
3rd Sess. 
H. Doc. 403, 87th Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
F.C. Act 1936 
H. Doc. 531, 81st Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
37-43

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 16, 1938 
March 20, 1950 
June 22, 1936 
March 16, 1938 
March 20, 1950 
Aug. 30, 1935 
Aug. 20, 1937 
March 7, 1974 
March 20, 1950 
Sept. 3, 1954 
March 16, 1938 
June 30, 1948 
March 20, 1950 
Sept. 3, 1954 
May 26, 1960 
March 20, 1950 
March 20, 1950 
WILLAMETTE RIVER BASIN, OREG. 
(See Section 43 of Text) 
Comprehensive plan for flood control, navigation 
and other purposes in Willamette River Basin. 
General improvements. 
WILLAMETTE RIVER BASIN, OREG., BANK 
PROTECTION (See Section 44 of Text) 
Bank protection works, with channel clearing. 
Provide additional protection against flooding. 
Addition of 77 locations to scope of project. 
BONNEVILLE LOCK AND DAM-BONNEVILLE 
LAKE, OREG. AND WASH. (See Section 49 
of Text) 
Existing project was originally authorized Sept. 30, 
1933, by Federal Emergency Administration of Public 
Works. 
Existing project authorized by Congress. 
Completion, maintenance, and operation of Bonneville 
Project under direction of Secretary of War and 
supervision of Chief of Engineers, subject to certain 
provisions therein relating to powers and duties of 
Bonneville Power Administrator. 
Authorizes relocation of town of North Bonneville 
to new town site. 
COUGAR LAKE, OREG. (See Section 50 of Text) 
Rockfill dam. 
Addition of power. 
DETROIT LAKE, OREG. (See Section 51 of Text) 
Authorizes concrete gravity structure. 
Addition of power and reregulating dam with power. 
GREEN PETER-FOSTER LAKES, OREG. 
(See Section 52 of Text) 
Authorized Green-Peter Dam in lieu of originally 
authorized Sweet Home Lake (1938). 
Addition of power at Green-Peter and White Bridge 
Reregulating Dam. 
Changes location of reregulating dam from White 
Bridge location to Foster. 
HILLS CREEK LAKE, OREG. (See Section 53 
of Text) 
Earth and gravel fill dam. 
JOHN DAY LOCK AND DAM-LAKE 
UMATILLA OREG. AND WASH. 
(See Section 54 of Text) 
Multiple-purpose dam, flood control, navigation 
and power. 
H. Doc. 544, 75th Cong., 
3d Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
F.C. Act 1936 
H. Doc. 544, 75th Cong., 
3rd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
S. Committee Print, 73rd 
Cong., 2nd Sess., 
(Report of Chief of 
Engineers Date Aug. 21, 
1938) 
P.L. 93-251, Water 
Resources Development 
Act 
H. Doc. 531, 81st Cong., 
2nd Sess. 
P.L. 83-780 
F.C. Act 1954 
H. Doc. 544, 75th Cong., 
3rd Sess. 
P.L. 858, 80th Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
P.L. 83-780 
F.C. Act 1954 
S. Doc. 104, 86th Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
H. Doc. 531, 81st Cong., 
2nd Sess. 
37-44

PORTLAND, OREG., DISTRICT 
TABLE 37-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 24, 1965 John Day waterfowl management area. S. Doc. 28, 89th Cong., 
1st Sess. 
LOOKOUT POINT LAKE, OREG. 
(See Section 55 of Text) 
March 16, 1938 Earth-and-gravel filled dam. H. Doc. 544, 75th Cong., 
3rd Sess. 
March 20, 1950 Addition of power. H. Doc. 531, 81st Cong., 
2nd Sess. 
LOST CREEK LAKE, ROGUE RIVER BASIN, OREG. 
(See Section 56 of Text) 
Sept. 21, 1962 Rock and gravel fill embankment dam, including H. Doc. 566, 87th Cong., 
power. 2nd Sess. 
THE DALLES LOCK AND DAM-LAKE CELILO, 
WASH. AND OREG. (See Section 57 of Text) 
March 20, 1950 Multiple-purpose dam, flood control, navigation H. Doc. 531, 81st Cong., 
and power. 2nd Sess. 
1. Contains latest published maps. 
2. Public Resolution 105, 67th Cong. 
3. Public Works Administration. 
4. Includes following work, classified inactive. A channel 
to Hobsonville 200 feet wide and 16 feet deep, with a turning 
TABLE 37-C 
basin 500 feet wide at Hobsonville, and regulating works as 
needed. 
5. Inactive. 
6. Flood Control Act. 
7. Permanent Appropriations Repeal Act. 
8. Classified deferred. 
Funds New Work Maintenance Total 
Regular 24,951,025 82,730,024 107,681,049 
Public Works 446,296 14,515 460,811 
Emergency Relief Administration 138,449 98,668 237,117 
Total U.S. 25,535,770 82,843,207 108,378,977 
Contributed Prior to 1964 223,026 24,320 247,346 
Do (1975) 35 to 40-foot channel 382,995 - 382,995 
Total Contributed 606,021 24,320 630,341 
Total All Funds 26,141,791 82,867,527 109,009,318 
37-45 
COLUMBIA AND LOWER WILLAMETTE RIVER BELOW 
VANCOUVER, WASH., AND PORTLAND, OREG. 
TOTAL COST OF EXISTING PROJECT TO JUNE 30, 1975 
(See Section 2 of Text)

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-D WILLAMETTE RIVER AT WILLAMETTE FALLS, OREG. 
PRINCIPAL FEATURES OF EXISTING CANAL AND LOCKS 
(See Section 19 of Text) 
Usable Lock Dimensions Series of 4 locks, each 175 by 37 feet 1 
Lift of Each Lock Lock 1 (Lower), 22.5 feet; Lock 2, 8.7 feet; 
Lock 3, 10.9 feet & Lock 4 (Upper), 8.1 feet2 
Depth on Miter Sills at Lower Water Lower Lock, 8.4 feet; Upper Lock, 6 feet. 
Character of Foundation Rock 
Kind of Dam Fixed.3 
Type of Construction Concrete. 
Year of Completion 1873; Purchased by United States Apr. 26, 1915 
Cost Unknown; purchase price, $375,000. 
1. A guard lock 210 by 40 feet, which is used only at supplied water for powerplants operated by Crown Zellerhigher 
stages of water, is at upper end of canal basin. bach Corp., and Portland Ry., Li ht & Power Co., which is 
2. A concrete division wall, 1,227 feet long, extending now being operated by Portland General Electric Co. 
from Lock 4 to Guard Lock, separates upper basin of canal 3. The dam is owned by private parties. 
from head race, which formerly led directly from basin and 
TABLE 37-E PROJECT CONDITION SURVEYS 
(See Section 22 of Text) 
Name of Project Date Survey Conducted 
Clatskanie River, Oreg. (Recon) Jun 1975 
Deep River, Wash. Jun 1975 
Depoe Bay, Oreg. Jan 1975 
Elochoman Slough, Wash. (Recon) Jun 1975 
Grays River, Wash. (Recon) Jun 1975 
Lake River, Wash. (Recon) Feb 1975 
Multnomah Channel, Oreg. Jun 1975 
Oregon Slough, Oreg. Jan 1975 
Smith River, Oreg. Nov 1974 
Yaquina River, Oreg. (Recon) Aug 1974 
Youngs Bay and River, Oreg. (Recon) Aug 1974 
37-46

PORTLAND, OREG., DISTRICT 
TABLE 37-F OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Clatskanie River, Oreg.' 2 1969 19,2403 190,3524 
Columbia River between Chinook, Wash. 
and Head of Sand Island1 2 1971 305,2135 385,533 
Columbia Slough, Oreg.6 1953 - 1,054 
Deep River, Wash.1 2 1963 15,384 49,329 
Depoe Bay, Oreg.' 1971 512,9527 308,913 
Elochoman Slough, Wash.' 2 1971 190,1088 26,901 
Grays River, Wash.1 2 1941 2,500 10,915 
Lake River, Wash.' 2 1965 2,700 33,293 
Multnomah Channel, Oreg.1 2 1949 18,112 4,017 
Nehalem Bay, Oreg.1 2 1949 302,0069 29,132 
Oregon Slough (North Portland Harbor) 
Oreg.1 2 1963 16,881 105,542 
Salmon River, Oreg.1 2 1949 2,145 501 
Skamokawa (Steamboat Slough), Wash.5 6 1932 
The.Cascades Canal, Columbia River, 
Oreg.' 10 1939 3,903,780 559,858 
The Dalles-Celilo Canal, Oreg. 
and Wash.'" 1957 4,716,205 2,833,888 
Umatilla Harbor, Oreg.14 '1 1952 
Westport Slough, Oreg.2 
16 1966 16,276 181,175 
Yaquina River, Oreg.1 2 1971 224,11312 418,58113 
Alsea Bay and River, Oreg. 1974 
Smith River, Oreg. 1974 143,120 219,431' 
1. Completed. 
2. Channel adequate for present commerce. 
3. Includes $15,537 for previous project. 
4. Includes $23,489 for previous project. 
5. Includes $84,930 rehabilitation funds. 
6. Classified inactive. 
7. Includes $145,588 Sec. 107 funds. Excludes $42,000 
expended from contributed funds. 
8. Includes $171,467 allotted under Sec. 107, Cathlamet, 
Wash. Excludes $19,555 contributed funds and $67,031 (other 
funds) contributed for additional dredging by Port of 
Cathlamet. 
9. Excludes $304,826 contributed funds for new work. 
10. Project abandoned due to flooding by Bonneville Dam 
pool. 
11. Project abandoned due to flooding by The Dalles Dam 
pool. 
12. Includes $195,313 Sec. 107 funds. Excludes $50,565 
contributed funds. 
13. Excludes $3,000 contributed funds. 
14. Project transferred to Portland District from Walla 
Walla District FY 1974. 
15. Project abandoned due to flooding by the John Day 
Dam pool. 
16. Deferred for restudy. 
37-47

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-G NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 24 of Text) 
Study Identification Fiscal Year Costs 
Preauthorization studies: 
Hammond Small Boat Basin 2 11,654 
Lewis and Clark Connecting Channel 6 330 
Multnomah Channel, Oreg. 3 10,435 
Rock Creek, Wash. 5,543 
Turning Basin at Astoria, Oreg. 1 5,319 
Wind River, Wash. 4 9,093 
Yaquina Bay and Harbor, Small Boat Basin 5 4,027 
TOTAL 46,401 
1. Preliminary Report Approved, September 28, 1971. 4. Preliminary Report Approved, July 24) 1973. 
2. Preliminary Report Approved, May 19, 1971. 5. Preliminary Report Approved, September 26, 1973. 
3. Preliminary Report Approved, July 29, 1971. 6. Preliminary Report Approved, January 7, 1970. 
TABLE 37-H OTHER AUTHORIZED BRIDGE ALTERATIONS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Bridges across Columbia River at Cascade 
Locks and Hood River, Oreg.1 1944 1,081,806 
Interstate Bridge, Columbia River, Portland, 
Oreg. to Vancouver, Wash.1 1961 1,154,1622 
1. Completed. 2. Non-Federal Funds $1,204,100. 
37-48

PORTLAND, OREG., DISTRICT 
TABLE 37-I FLOOD CONTROL RESERVOIR OPERATIONS 
See 
Section Peak Inflow Storage Used 
in Text Project Date of Peak Inflow cu. ft./sec. acre/feet 
29. Blue River Lake, December 21, 1974 11,900 15,480 
Oregon January 26, 1975 4,880 17,000 
31. Cottage Grove Lake, December 28, 1974 1,680 2;320 
Oregon January 6, 1975 2,670 6,290 
50. Cougar Lake, December 20, 1974 7,500 18,700 
Oregon January 24, 1975 6,700 23,540 
51. Detroit Lake, December 20, 1974 21,850 56,500 
Oregon January 25, 1975 19,700 61,700 
34. Dorena Lake, December 15, 1974 5,900 11,400 
Oregon January 6, 1975 7,620 11,245 
36. Fall Creek Lake, December 21, 1974 4,230 9,020 
Oregon January 27, 1975 6,070 9,020 
37. Fern Ridge Lake, December 22, 1974 2,070 6,710 
Oregon January 26, 1975 1,780 3,700 
52. Foster Lake, December 20, 1974 12,460 2,280 
Oregon January 25, 1975 13,120 1,390 
52. Green Peter Lake, December 20, 1974 25,950 54,080 
Oregon January 25, 1975 19,275 52,020 
53. Hills Creek Lake, December 21, 1974 3,530 6,050 
Oregon January 26, 1975 4,870 8,140 
55. Lookout Point Lake, December 21, 1974 12,350 24,380 
Oregon January 25, 1975 14,510 30,150 
37-49

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-J LOWER COLUMBIA RIVER BASIN, OREG. AND WASH. 
LEVEES AND IMPROVEMENTS TO EXISTING WORKS 
(See Section 38 of Text) 
Estimated Cost 
of Work 
Location Approved 1975 
Beaver Drainage District, Oreg. 
Cowlitz County Diking Improvement District 2, Wash. 
Cowlitz County Diking Improvement District 13, Wash. 
Cowlitz County Diking Improvement District 15, Wash. 
Cowlitz County Consolidated Diking Improvement District 2, Wash. 
Midland Drainage District, Oreg. 
Multnomah County Drainage District 1, Oreg. 
Rainier Drainage District, Oreg. 
Sandy Drainage District, Oreg. 
Sauvie Island Drainage District, Oreg. 
Scappoose Drainage District, Oreg. 
Wahkiakum County Consolidated Diking District 1, Wash. 
Woodson Drainage District, Oreg. 
Total Estimated Cost, Federal Funds 
Estimated Non-Federal Cost 
Locations reclassified inactive or deferred and excluded from above cost estimate: 
Bachelor Island, Wash. 
Clatskanie Drainage District, Oreg. 
Clatsop County Drainage District 1, Oreg. 
Clatsop County Diking District 4, Oreg. 
Clatsop County Diking District 6, Oreg. 
Columbia Drainage District 1, Oreg. 
Cowlitz County Consolidated Diking Improvement District 1, Wash. 
Deer Island Drainage District, Oreg. 
John Drainage District, Oreg. 
Lake River Delta Area, Wash. 
Lewis River Area, Wash. 
Magruder Drainage District, Oreg. 
Peninsula Drainage District 1, Oreg. 
Peninsula Drainage District No. 2, Oreg. 
Wahkiakum County Diking District 4, Wash. 
Cost of These Locations is 
2,190,000 
363,000 
65,000 
305,000 
1,659,000 
305,000 
1,492,000 
594,000 
15,0001 
671,000 
3,950,000 
4,500,000 
163,000 
16,272,000 
1,809,000 
1,040,000(1955) 
574,000(1963) 
22,000(1959) 
56,000(1956) 
61,000(1960) 
1,192,000(1954) 
1,570,000(1960) 
547,000(1960) 
151,000(1960) 
1,110,000(1957) 
903,000(1955) 
76,000(1960) 
2,310,000(1971) 
496,000(1960) 
758,000(1960) 
10,866,000 
1. Cost is for Engineering only. Project was constructed 
by local interests. 
37-50

TABLE 37-K 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
LOWER COLUMBIA RIVER BASIN 
(BANK PROTECTION WORKS), OREG. AND WASH.: 
OPERATION AND RESULTS DURING FISCAL YEAR. 
(See Section 39 of Text) 
Quantity 
Location Nature of Work (Linear Feet) 
Sauvie Island Drainage District 
Shields Ranch Extension Dumped stone revetment 2,232 
Port of Kalama 
Grain Elevator Location Dumped stone revetment 753 
TOTAL 2,985 
TABLE 37-L WILLAMETTE RIVER BASIN COMPREHENSIVE PLAN 
(See Section 43 of Text) 
Project 
Blue River Lake, McKenzie Basin' 3 
Cascadia Lake, South Santiam River1 
4 
Channel Clearing and Snagging on Willamette 
River and Major Tributaries 6 
Channel Improvements for Flood Control and 
Major Drainage on 16 Streams 
Tributary to Willamette River' 7 
Cottage Grove Lake, Coast Fork' 
Cougar Lake, South Fork McKenzie' 3 
Detroit Lake, Including Big Cliff 
Lake, North Santiam River' 
Dorena Lake, Row River' 
Fall Creek Lake, Middle Fork' 
Fern Ridge Lake, Long Tom River' 
Floodwall Levees, Portland, Oreg.6 
Gate Creek Lake, McKenzie Basin3 
Green Peter-Foster Lakes, 
Middle Santiam' 4 
Hills Creek Lake, Middle Fork 
Holley Lake, Calapooya River s 
Authorizing Act 
May 17, 1950, H. Doc. 531 
81st Cong. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2nd Sess. 
May 17,1950, H. Doc. 531, 
81st Cong., 2nd Sess. 
May 17,1950, H. Doc. 531, 
81st Cong., 2nd Sess. 
June 28,1938, H. Doc. 544, 
75th Cong., 3rd Sess. 
May 17, 1950, H. Doc. 531 
81st Cong., 2nd Sess. and 
Sept. 3, 1954, S. Doc. 131, 
83rd Cong., 2nd Sess. 
June 28,1938, H. Doc. 544, 
75th Cong., 3rd Sess. and 
June 30, 1948, Public Law 
858. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3rd Sess. 
May 17, 1950, H. Doc. 531 
81st Cong., 2nd Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3rd Sess. 
May 17,1950, H. Doc. 531, 
81st Cong., 2nd Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2nd Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2nd Sess. and 
Sept. 3, 1954, S. Doc. 131, 
83rd Cong., 2nd Sess. and 
July 14,1960, S. Doc. 104, 
86th Cong., 2nd Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2nd Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2nd Sess. 
37-51 
Estimated 
Federal 
Cost-1975 
$32,038,2252 
104,000,000 
3,005,000 
1,214,3002 
4,953,294 
57,500,000 
62,729,6982 
15,473,101 
22,567,000 
11,384,000 
18,900,000 
73,900,000 
85,078,000 
45,700,619 
13,300,000

PORTLAND, OREG., DISTRICT 
TABLE 37-L 
(Continued) 
WILLAMETTE RIVER BASIN COMPREHENSIVE PLAN 
(See Section 43 of Text) 
Estimated 
Federal 
Project Authorizing Act Cost-1975 
Johnson Creek, Vicinity of Portland, Oreg.5 May 17, 1950, H. Doc. 531, 2,013,000 
81st Cong., 2nd Sess. 
Lookout Point Lake, Including Dexter June 28,1938, H. Doc. 544, 92,471,000 
Lake, Middle Fork' 75th Cong., 3rd Sess., and 
May 17, 1950, H. Doc. 
531, 81st Cong., 2nd Sess. 
Strube Lake & Cougar Additional Power, Oct. 23, 1962, H. Doc. 403, 26,800,000 
South Fork McKenzie5 87th Cong., 2nd Sess. 
Waldo Lake Tunnel and Reregulating Works May 17,1950, H. Doc. 531, 8 
North Fork, Middle Fork, Willamette River 81st Cong., 2nd Sess. 
Willamette Falls Fish Ladder6 May 17,1950, H. Doc. 531, 214,000 
81st Cong., 2nd Sess. 
Willamette River Bank Protection' June 22, 1936, Special 19,800,000 
Report Division Engr., 
June 28, 1938, H. Doc. 
544, 75th Cong., 3rd Sess., 
and May 17, 1950, H. Doc. 
531, 81st Cong., 2nd Sess. 
1. See individual reports for details of the project. 5. Project reclassified deferred. 
2. Actual cost. 6. Project reclassified inactive. 
3. For construction in lieu of originally authorized 7. Does not include $25,075,000 Reclassified Locations. 
Quarts Creek Lake. 8. Authorization rescinded August 28, 1958, Public Law 
4. For construction in lieu of originally authorized Sweet 85-820. 
Home Lake. 
TABLE 37-M WILLAMETTE RIVER BASIN, OREG., (BANK PROTECTION) 
OPERATION AND RESULTS DURING FISCAL YEAR 
(See Section 44 of Text) 
Quantity 
Location Nature of Work (Linear Feet) 
Santiam River 
Upper Bryant Stone Revetment 1,619 
Willamette & Middle Fork 
Danis Location Stone Revetment 2,976 
Lassen Location Stone Revetment 1,717 
Stoutenberg Upstream Ext. Stone Revetment 587 
37-52

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-N OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
COLUMBIA RIVER BASIN 
Beaver Drainage District, Columbia 
County, Oreg.' 1940 274,578 
Blind Slough Diking District, Clatsop 
County, Oreg.' 1939 163,397 
Consolidated Diking and Improvement 
District 1, Cowlitz County, Wash.' 1941 163,291 
Deep River area, Wahkiakum County, 
Wash.' 1942 69,724 - 
Deer Island area, Columbia County, Oreg.' 1943 574,123 - 
Diking District 2, Clatsop County, Oreg.' 1940 43,150 
Diking District 3, Clatsop County, Oreg.2 1938 258 - 
Diking District 5, Clatsop County, Oreg.' 1940 25,609 - 
Diking and Improvement District 5, Cowlitz 
County, Wash.' 1940 161,381 
Diking District 1 and 3 (Puget Island) and 
Little Island, Wahkiakum County, Wash.' 1941 258,795 
Diking Improvement District 1, Pacific 
County, Wash.' 1941 26,810 
Diking and Improvement District 4, Wahkiakum 
County, Wash.' 1951 169,542 - 
Drainage District 1, Clatsop County, Oreg.' 1939 240,939 - 
John Day River, Oreg., Columbia River Basin 
Local Flood Protection 1974 210,220 
John Day River area, Clatsop County, 
Oreg.' 1942 33,080 - 
Karlson Island, Clatsop County, Oreg.' 1941 25,773 - 
Knappa area, Clatsop County, Oreg.' 1942 18,789 - 
Lewis and Clark River area, Clatsop 
County, Oreg.' 1942 158,419 
Magruder Drainage District, Columbia 
County, Oreg.' 1940 61,186 
Marshland Drainage District, Columbia 
County, Oreg.' 1940 39,475 
Midland Drainage District, Columbia 
County, Oreg.' 1939 77,7743 - 
Multnomah Drainage District 1, Oreg.' 1951 585,6524 - 
Peninsula Drainage District 1, Multnomah 
County, Oreg.' 1942 211,160 
Peninsula Drainage District 2, Multnomah 
County, Oreg.' 1942 241,148 - 
Prescott area, Columbia County, Oreg.2 1941 125 - 
Rainier Drainage District, Columbia 
County, Oreg.' 1942 47,662 
Sandy Drainage District, Multnomah 
County, Oreg.' 1942 138,956 
Sauvie Island areas A and B, Multnomah 
County, Oreg.' 1951 1,623,505 
Scappoose Drainage District, Columbia 
County, Oreg.' 1942 424,310 
Skamokawa Creek area, Wahkiakum County, 
Wash.1 1946 178,885 - 
Tenasillahe Island, Clatsop County, Oreg.' 1939 133,778 - 
Upper Grays River area, Wash.' 1947 61,263 30,000 
Walluski River, Clatsop County, Oreg.' 1942 66,932 - 
Warrenton Diking District 1, Clatsop 
County, Oreg.' 1940 69,503 
Warrenton Diking District 2, Clatsop 
County, Oreg.' 1940 117,143 
37-53

PORTLAND, OREG., DISTRICT 
Project 
Warrenton Diking District 3, Clatsop 
County, Oreg.' 
Webb District Improvement Co., Columbia 
County, Oreg.' 
Westland District Improvement Co., Columbia 
County, Oreg.' 
Westport District, Columbia and Clatsop 
Counties, Oreg.' 
Woodson Drainage District, Columbia 
County, Oreg.' 
Youngs River Dikes, Clatsop County, Oreg.' 
Total Columbia River Basin 
LEWIS RIVER BASIN 
Diking and Improvement District 11, 
Cowlitz County, Wash.' 
COWLITZ RIVER BASIN 
Cowlitz County Drainage Improvement 
District 1, Wash.' 
Diking Improvement District 2, Cowlitz 
County, Wash.' 
Diking Improvement District 13, Cowlitz 
County, Wash.' 
Total Cowlitz River Basin 
LOWER COLUMBIA RIVER BASIN 
Bachelor Island, Wash.2 
Clatskanie Drainage District, Oreg.2 
Clatskanie River area, Columbia 
County, Oreg. 2 
Clatsop County Drainage District 1, 
Oreg. 2 
Clatsop County Diking District 4, 
Oreg.2 
Clatsop County Diking District 6, Oreg. 2 
Columbia Drainage District 1, Oreg.2 
Cowlitz County Consolidated Diking 
Improvement District 1, Wash.2 
Cowlitz County Diking Improvement District 2, 
Wash.' 
Cowlitz County Diking Improvement District 13, 
Wash.' 
Cowlitz County Diking Improvement District 15, 
Wash.' 
Deer Island Drainage District, Oreg.2 
Hayden Island, Oreg.2 
John Drainage District, Oreg.5 
Kalama River (South Area) Levee, 
Cowlitz County, Wash.2 
Lake River Delta area, Wash.5 
Lewis River area, Wash.2 
Magruder Drainage District, Oreg.2 
Midland Drainage District, Oreg.' 
Multnomah County Drainage District 1, 
Oreg. 
Peninsula Drainage District 1, Oreg.2 
Peninsula Drainage District 2, Oreg.2 
Rainier Drainage District, Oreg.' 
Sandy Drainage District, Oreg. 
For Last Cost to June 30, 1975 
Full Report 
See Annual 
Report For Construction Maintenance 
1940 
1940 
1940 
1943 
1940 
1942 
1943 
1939 
1940 
1939 
1964 
1960 
1960 
1961 
1967 
1967 
1967 
1950 
1961 
1969 
1960 
1971 
1964 
1961 
1961 
1967 
1954 
74,596 
84,592 
205,531 
40,658 
22,797 
248,802 
7,163,061 
172,521 
42,978 
121,165 
28,592 
192,735 
18,543 
268 
4,472 
8,824 
363,000 
65,345 
304,794 
23,754 
55,594 
774 
304,511 
1,491,425 
43,292 
35,265 
593,945 
15,0566 
30,000 
37-54 
TABLE 37-N 
(Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-N 
(Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual 
Project Report For Construction Maintenance 
Sauvie Island Drainage District, Oreg.' 1966 667,440 - 
Wahkiakum Co. Diking District 4, Wash.2 1971 48,619 - 
Washougal Area Levees, Clark County, Wash. 1973 1,796,640 - 
Woodson Drainage District, Oreg.' 1964 162,500 - 
Total Lower Columbia River Basin - 6,004,061 - 
WILLAMETTE RIVER BASIN 
Amazon Creek, Oreg.' 1960 1,214,3007 - 
Area east of Albany, Oreg.5 
Bear Creek, Long Tom River, Oreg.2 1966 4,559 
Calapooia River, Oreg.2 1959 11,595 - 
Coyote and Spencer Creeks, Long Tom River, 
Oreg.2 1960 6,819 - 
East Muddy and Lake Creek, Oreg.2 1959 6,465 - 
Ferguson Creek, Long Tom River, Oreg.2 
Flat Creek, Long Tom River, Oreg.2 
Floodwall and Levees at Portland, Oreg. 2 
Gate Creek Lake, Oreg. 1972 840,001 
Holley Lake, Oreg.5 1963 241,992 
Johnson Creek, OGeg.' 1966 76,437 - 
Mud and Baskett Slough, Rickreall 
Creek, Oreg.5 
Pudding River, Oreg.2 1950 5,000 - 
Shelton Ditch, Willamette River, Oreg.2 1967 39,624 - 
Soap Creek, Willamette River, Oreg.5 
Turner Prairie, Mill Creek, Oreg.5 
West Muddy Creek and Marys River, 
Oreg.2 1962 4,056 - 
Wiley Creek Lake, Oreg.s - 112,0009 
Willamette River Basin Channel clearing 
and snagging. 2 
Total Willamette River Basin - 2,562,848 - 
ALL OTHER FLOOD CONTROL 
Arlington, Alkali Canyon, Oreg.2 10 11 1950 23,43912 - 
Beaver Creek near Tillamook, Oreg.' 3 1967 106,198 
Castle Rock, Cowlitz River, Wash.' 1957 104,921 
Catching Inlet Drainage District, Coos 
River, Oreg.' 13 1959 182,655 
Clackamas River at Dixon Farm 
Location, Oreg.' 13 1952 61,344'4 - 
Coquille River, Oreg.2 1948 908 - 
Cowlitz River at Randle, Wash. 1962 11,095 - 
Lower Cowlitz River, Wash. 1962 181,652 
McKenzie River near Walterville, Oreg.' 13 1967 148,358 
Mill Four Drainage District, Yaquina River, 
Oreg.' 1948 118,433 
Molalla River at Milk Creek location, 
Oreg.' 's 1955 55,007 - 
Molalla River at Ressel location, Oreg.' '3 1952 55,189 - 
Pendleton Levees, Umatilla River, Oreg.'o 1960 
(a) Riverside Area Units5 9,100 - 
(b) State Hospital and City Areas (Zone 1) 267,748 
Pendleton, Umatilla River, Oreg."o 1939 143,263 
Pilot Rock, Birch Creek, Oreg.' o '5 1963 4,558 - 
Prineville, Oreg. 1962 11,318 
Reedsport Levees, Umpqua River, Oreg.' 1971 968,71616 - 
37-55

PORTLAND, OREG., DISTRICT 
TABLE 37-N 
(Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual 
Project Report For Construction Maintenance 
Salmon Creek at Oakridge, Oreg.' '3 1960 288,447 
Stillwell Drainage District, Tillamook Bay, 
Oreg.1 13 1961 176,351 
Umatilla River (Echo), Columbia River Basin, 
Oreg. 0o 17 1960 24,145 
Umpqua River and tributaries, Oreg.' 1952 428,881 
Vicinity of Nehalem, Nehalem River, Oreg.' 1952 45,677 
1. Completed. 11. Abandoned. Necessity for development was 
2. Classified inactive, eliminated when Lake Umatilla was created. 
3. Includes $26,241, Emergency Relief Act funds. 12. Includes $3,328 spent in fiscal year 1960 under 
4. In addition $25,000 contributed funds expended for authorization of P.L. 685, 84th Congress. See Annual Report 
new work. for fiscal year 1960, page 1887. 
5. Deferred. 13. Authorized by Chief of Engineers. 
6. Cost is for engineering only. Project was constructed 14. In addition $2,520 contributed funds expended for new 
by local interests, work. 
7. In addition $154,751 contributed funds expended for 15. Deauthorized. Five-year limitation on project 
new work, $88,784 "Required" and $65,967 "Other". authorization reached December 2, 1968. 
8. Recommendation for early authorization rescinded by 16. Excludes $230,070 contributed funds for new work 
S. Doc. 104, 86th Cong., 2d Sess. in Flood Control Act 1960. and $31,284 Government furnished sheet steel pile. 
9. Pro rata share of site selection studies. 17. Deauthorized November 19, 1964. 
10. Reported by Walla Walla District prior to 1974. 
TABLE 37-0 FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
(See Section 48 of Text) 
Fiscal Year 
Costs 
Preauthorization studies: 
Beech Creek, Mt. Vernon Location, 
John Day River, Oregon 1,289 
Devils Lake Area, Lincoln Co., Oregon 54,056 
Elk Creek-Cannon Beach, Oregon 9,986 
Palouse Creek and Larsen Slough, Oregon 2,963 
Silver Creek, Silverton, Oregon 4,511 
Stage Gulch-Stanfield, Oregon 2,679 
Condor Road, Nestucca River, 
Tillamook Co., Oregon 2,875 
Miami River, Tillamook Co., Oregon 15,321 
Rogue River, Josephine Co., Oregon 20,426 
Sumner Parker Airport, Jackson Co., Oregon 92,500 
Emergency flood control activities: 
Advance preparation 48,998 
Flood emergency operations 189,818 
Rehabilitation 513,444 
37-56

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 37-P PRINCIPAL DATA CONCERNING NAVIGATION LOCK, 
SPILLWAY DAM AND POWERPLANT 
Project 
Bonneville Lock and Dam, 
Oreg. and Wash.-Lake Bonneville 
(See Section 49 of Text) 
John Day Lock and 
Dam, Lake Umatilla 
Oreg. and Wash. 
(See Section 54 of Text) 
NAVIGATION LOCK 
Dimensions: 
Clear Width of Chamber 
Greatest Length Available for Full Width 
Lift (Vertical): 
At Extreme Low Water and Normal Pool Level 
At Normal River Stage 
At Extreme High Water 
Depth Over Miter Sills at Adopted Low Water 
Character of Foundation 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Capacity 
Elevation of Gate Sills on Crest of Spillway 
Height Above Lowest Foundation 
Length of Dam Proper 
Length of Dam Overall 
Width at Base 
Gate Openings 
Crest Overflow (Above Mean Sea Level) 
Pool Elevation (Normal)(Above Mean Sea Level) 
POWERPLANT 
Length 
Width 
Height (Roof to Bedrock) 
Generator (Station Unit) 
Generators 
Total Rated Capacity 
Speed 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
76 Feet 
500 Feet 
66 Feet 
59 Feet 
About 30 Feet 
24.2 Feet 
Andesite 
January 1938 
Concrete Gravity 
1938 
1,600,000 Cubic Feet 
Per Second 
23.3 Feet 
About 170 Feet 
1,090 Feet 
1,230 Feet 
200 Feet 
18 
24 Feet 
72 Feet 
1,027 Feet 
190 Feet 
190 Feet 
1-4,000 kw 0.8 Power 
Factor 
2-43,200 kw 0.9 
Power Factor 
8-54,000 kw 0.9 
Power Factor 
518,400 kw 0.9 
Power Factor 
75 Revolutions Per Minute 
86 Feet 
669 Feet 
97 Feet 
105 Feet 
113 Feet 
15 Feet 
April 1968 
Concrete Gravity 
March 1968 
2,250,000 cfs 
210 
Tainter 
50 Ft. by 58.5 Ft. 
20 
37-57

PORTLAND, OREG., DISTRICT 
PRINCIPAL DATA CONCERNING NAVIGATION LOCK, 
SPILLWAY DAM AND POWERPLANT 
Project 
POWERPLANT 
The Dalles Lock and Dam 
Wash. and Oreg.-Lake Celilo 
(See Section 57 of Text) 
Length 
Width 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Installed Capacity 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at 
Elevation 268 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Type 
Lift Normal 
Net Clear Length 
Net Clear Width 
Normal Depth Over Upper Sill 
Minimum Depth Over Lower Sill 
Opened to Navigation 
SPILLWAY DAM 
Type 
Elevation of Crest 
Top of Crest Gates 
Number of Gates 
Size of Gates 
Height (Foundation to Crest) 
Design Flood 
POWERPLANT 
Powerhouse Dimensions 
Generators Main Units 
Generators Main Units 
Total Rated Capacity 
Fishwater Supply Units 
Station Service Units 
1,975 Feet 
243 Feet 
16 
4
135,000 kw 
2,160,000 kw 
2,700,000 kw 
235 Feet 
July 1968 
268-257 
276 
500,000 Ac.-Ft. 
76.4 Miles 
55,000 Acres 
15 Ft. by 250 Ft. 
200 Miles 
Single Lift 
87.5 Feet 
675 Feet 
86 Feet 
20 Feet 
15 Feet 
March 17, 1957 
Controlled 
121 Ft. msl 
162 Ft. msl 
23 
50 by 43 Feet 
120 Feet 
2,290,000 cfs 
240 by 2,150 Feet 
14 @ 78,000 kw Each 
Additional 8 @ 
85,975 kw Each 
Ultimate 22-1,779,800 kw 
2 @ 13,500 kw Each 
2 @ 3,000 kw Each. 
37-58 
TABLE 37-P 
(Continued)

TABLE 37-Q 
Pr 
Restoration of Indian Fishin 
Bonneville, Oreg. 
Strube Lake and Cougar Ad 
Oreg.' 
Waldo Lake Tunnel, Oreg.2 
1. Classified deferred. 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED MULTIPLE-PURPOSE 
POWER PROJECTS 
For Last Cost 
Full Report 
See Annual 
'oject Report For Constr 
g Grounds, 
1969 185 
ditional Power, 
to June 30, 1975 
Operation and 
uction Maintenance 
i,000 
1964 
2. Authorization rescinded August 28, 1958 (Public Law 
85-820). 
37-59 
--

PORTLAND, OREG., DISTRICT 
TABLE 37-R COMPLETED FLOOD PLAIN INFORMATION STUDIES 
(See Section 60 of Text) 
Date Federal 
Location Requesting Agency Completed Cost 
Rogue River Basin 
Interim Report 
Umpqua River Basin 
Interim Report 
Willamette River Basin 
Interim Report 
Willamette River Basin 
Lane County, Oreg. 
Willamette R. Basin 
Marion & Polk Counties, 
Oreg. 
Cowlitz R. Basin 
Cowlitz County, Wash. 
City of John Day and 
Canyon City 
Willamette R. Basin 
Washington County, Oreg. 
Umatilla River Basin 
Mission-Riverside 
Area, Oreg. 
Willamette R. Basin 
Milwaukie-Oak Grove- 
Lake Oswego Area, Oreg. 
Willamette R. Basin 
Oregon City-Gladstone- 
West Linn-Jennings 
Lodge, Oreg. 
Willamette R. Basin 
Canby-Barlow-Wilsonville, 
Oreg. 
Umatilla River Basin 
Pendleton, Oreg. 
Willamette R. Basin 
Newberg, Oreg. 
Willamette River Basin 
Corvallis & Philomath, 
Oreg. 
Willamette R. Basin 
Albany, Oreg. 
Willamette R. Basin 
Harrisburg, Oreg. 
Willamette R. Basin 
Lebanon, Oreg. 
Umatilla R. Basin 
Echo-Stanfield Area 
Willamette River Basin 
Sweet Home Area, Oreg. 
Willamette River Basin 
Brownsville, Oreg. 
Columbia R. Basin 
Heppner, Oreg. 
Umatilla River 
Cayuse-Gibbon, Oreg. 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Washington State Dept. 
of Ecology 
City of John Day, 
Canyon City & Grant 
County 
Oregon State Water 
Resources Board 
Umatilla County 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Umatilla County 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
Oregon State Water 
Resources Board 
$ 5,495 
3,424 
3,963 
139,601 
99,265 
Dec 1965 
Jun 1966 
Mar 1966 
Jan 1967 
May 1963 
Jan 1969 
May 1969 
Jun 1969 
Nov 1969 
May 1970 
Jun 1970 
Jun 1970 
Mar 1971 
Jun 1971 
Mar 1971 
Jun 1971 
Dec 1972 
Jun 1973 
Jun 1974 
Jun 1974 
Aug 1974 
Jun 1974 
Jul 1975 
49,498 
9,968 
48,997 
19,684 
28,883 
28,352 
31,585 
35,368 
26,694 
38,816 
39,521 
20,412 
38,466 
36,900 
43,616 
66,677 
14,843 
20,798 
37-60

SEATTLE, WASH., DISTRICT* 
This District comprises Washington except 
southern and southeastern portions, northern 
Idaho, and northwestern Montana embraced in 
drainage basins tributary to Pacific Ocean south 
of international boundary to Cape Disappointment, 
and to Columbia River above Yakima 
River, inclusively. 
IMPROVEMENTS 
Navigation Page 
1. Anacortes Harbor, Wash ................ 38-1 
la. Anacortes Navigation Channel, 
W ash .............................................. 3 8-2 
2. Everett Harbor and Snohomish 
River, W ash................................... 38-3 
3. Grays Harbor and Chehalis 
River, Wash............................... 3 8-3 
4. Lake Washington Ship Canal, Wash. 38-4 
5. Olympia Harbor, Wash...................38-5 
6. Puget Sound and its Tributary 
W aters, W ash ................... 388..-.5.......... 
7. Quillayute River, Wash................. 38-5 
8. Seattle Harbor, Wash...................... 3 8-6 
9. Swinomish Channel, Wash ............. 38-6 
10. Tacoma Harbor, Wash................. 3 8-7 
11. Waterway Connecting Port Townsend 
and Oak Bay, Wash ........................ 3 8-7 
12. Willapa River and Harbor and 
Naselle River, Wash ........................ 38-8 
13. Project ConditionSurveys .................3 8-8 
14. Other Authorized Navigation 
Projects...................... 38-8 
15. Navigation Work under Special 
Authorization .................................. 3 8- 8 
Beach Erosion 
16. Ediz Hook, Wash.................... 3388--88...... 
17. Beach Erosion Work Under Special 
Authorization.................................. 38-9 
Navigation 
1. ANACORTES HARBOR, WASH. 
Flood Control 
18. Howard A. Hanson Dam, Wash........ 38-9 
19. Mud Mountain Dam, Wash.............. 38-9 
20. Stillaguamish River, Wash.......... 38-10 
21. Tacoma, Puyallup River, Wash......... 38-10 
22. Wenatchee, Canyons 1 and 2, Wash... 38-10 
23. Wynoochee Lake, Wash....................38-11 
24. Inspection of Completed Flood 
Control Projects ........................... 38-11 
25. Scheduling Flood Control 
Reservoir Operations................... 38-11 
26. Other Authorized Flood Control 
Projects ........................................ 38-12 
27. Flood Control Work Under Special 
Authorization.................................. 38-12 
Multiple-Purpose Power Projects 
28. Albeni Falls Dam, Idaho................ 38-12 
29. Chief Joseph Dam - Rufus Woods 
Lake, Wash.................. 38-12 
30. Libby Dam - Lake Koocanusa, 
Mont .............................. .... ... 38-13 
31. Other Authorized Multiple-Purpose 
Power Projects.............................. 38-14 
General Investigations 
32. Surveys........................................38-14 
33. Collection and Study of Basic Data... 38-14 
34. Research and Development .............. 38-15 
Wash., and 64 miles north of Seattle. The main 
harbor is on Guemes Channel. (See Coast and 
Geodetic Survey Chart 6377.) 
Location. On northern point of Fidalgo Island Existing project. Channel in Capsante 
in Puget Sound, 17 miles south of Bellingham, Waterway, 12 feet deep and 150 to 250 feet wide, 
* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
38-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
between east side of Q Avenue and deep water in 
Fidalgo Bay, a distance of 2,850 feet; and mooring 
basin 12 feet deep, 570 feet wide, and 960 feet 
long adjacent to north side of Capsante 
Waterway, protected by two pile breakwaters, 
each 470 feet long, east and southeast of basin. 
Plane of reference is mean lower low water. 
Range between mean lower low water and mean 
higher high water is 8.2 feet. Extreme range is 
about 15.5 feet. (See Table 38-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. Expended 
$59,523 contributed funds. Other non- 
Federal costs are estimated at $98,000 (July 
1958). 
Terminal facilities. There are 27 piers and 
wharves in the Port of Anacortes; 18 on Guemes 
Channel, 3 on Capsante Waterway, and 6 on 
Fidalgo Bay. Three wharves on Guemes Channel 
are open for public use; of these, two are publicly 
owned and operated and used for handling 
general cargo in foreign and domestic trade. In 
addition, two wharves are used for ferries plying 
to the San Juan Islands and to Vancouver Island, 
British Columbia. One of these is privately owned 
and operated, and the other publicly owned and 
operated. Two of the wharves on Capsante 
Waterway and basin are publicly owned and 
operated and used for receiving petroleum 
products, and as a moorage for fishing and 
pleasure craft. All other wharves are used for 
general industrial purposes. In addition, there 
are two oil-refinery wharves located to the south 
of Capsante Waterway that are privately owned 
and operated and used for handling petroleum 
products in foreign and domestic trade. These 
facilities are considered adequate for existing 
commerce. (See Port Series No. 37-Port of 
Everett, Bellingham, Port Angeles, and 
Anacortes, Wash., revised 1963). 
Operations and results during fiscal year. 
Maintenance contract: Capsante Waterway was 
maintained by dredging of approximately 66,000 
cubic yards of shoal material. Contract work was 
accomplished in January and February at a cost 
of $187,000. 
Condition at end offiscal year. Project was completed 
in July 1957, excluding the inactive portion 
and inner portion of boat basin. For further 
details, see Annual Report for 1958. 
la. ANACORTES NAVIGATION 
CHANNEL, WASH. 
Location. On northern point of Fidalgo Island 
in Puget Sound, 17 miles south of Bellingham, 
Washington, and 61 miles north of Seattle. The 
main harbor is on Guemes Channel. (See Coast 
and Geodetic Survey charts 6300, 6376 and 6380.) 
Existing project. Provides for construction of a 
channel 150 feet wide to minus 18 feet extending 
5,180 feet from deep water in Guemes Channel to 
the urban renewal landfill on the east shore of 
Fidalgo Bay. Plane of reference is mean lower 
low water. Range between mean lower low water 
and mean higher high water is 8.2 feet. Extreme 
range is about 15.5 feet. (See Table 38-B for 
authorizing legislation.) 
Local cooperation. Local interests must provide 
all lands, easements and rights-of-way required 
for navigation aids and for construction and subsequent 
maintenance of the project, including 
suitable disposal areas for dredged materials and 
necessary retaining dikes, bulkheads and embankments 
for such areas; hold the United States 
free from damages due to construction and 
maintenance of the recommended improvements; 
accomplish such utility and other relocations 
for alterations as may be required; provide 
and maintain adequate public terminal and 
transfer facilities; provide and maintain depths 
of berthing areas and local access channels serving 
the terminals commensurate with the depth 
provided in the regulated project areas; establish 
regulations for prevention of pollution in accordance 
with existing laws and regulations; and contribute, 
prior to the start of construction, 0.9 percent 
of the cost of the recommended channel, 
presently estimated at $4,600. Agreement has 
been signed, disposal area provided and funds 
deposited. 
Terminal facilities. There are 27 piers and 
wharves in the Port of Anacortes: 18 on Guemes 
Channel, 3 on Capsante Waterway, and 6 on 
Fidalgo Bay. Three wharves on Guemes Channel 
are open for public use; of these, two are publicly 
owned and operated and used for handling 
general cargo in foreign and domestic trade. In 
addition, two wharves are used by ferries plying 
to the San Juan Islands and to Vancouver Island, 
British Columbia. One of these ferries is privately 
owned and operated and the other is publicly 
owned and operated. Two of the wharves on Capsante 
Waterway and basin are publicly owned 
and operated and used for receiving petroleum 
products, and as a moorage for fishing and 
pleasure craft. All other wharves are used for 
general industrial purposes. 
Operation duringfiscal year. New work, hired 
labor: Completed detailed project report and 
plans and specifications. 
New work, contract: Contract for biological 
study of before, during and after condition of area 
to be dredged, awarded April 1975. Contract for 
dredging and disposal awarded June 1975. 
Condition at end offiscal year. Construction not 
started. 
38-2

SEATTLE DISTRICT 
2. EVERETT HARBOR AND 
SNOHOMISH RIVER, WASH. 
Location. On Port Gardner Bay, at northern 
end of Possession Sound, an arm of Puget Sound 
at Everett, in northwestern Washington; and 
Snohomish River for 6.3 miles above mouth. (See 
Coast and Geodetic Survey Chart 6448.) 
Previous projects. For details see page 704 of 
Annual Report for 1905, page 2005 of Annual 
Report for 1915, and page 1883 of Annual Report 
for 1938. 
Existing project. Training dike extending from 
a point opposite 23d Street northward 12,550 feet 
to outlet of Snohomish River, with spur dike 
extending 400 feet to pierhead line from north 
end of main dike; spur dike extending 1,410 feet 
westward from Preston Point; removal of a section 
of training dike north of Snohomish River 
outlet; channel 150 to 425 feet wide and 15 feet 
deep from deep water in Port Gardner Bay to 
14th Street dock; thence a settling basin 700 feet 
wide, 1,200 feet long, and 20 feet deep, thence a 
channel 150 feet wide and 8 feet deep up river to 
head of Steamboat Slough, a total distance of 
about 6.3 miles; settling basin within upper 
channel reach about 1 mile long with a capacity of 
1 million cubic yards; maintaining East 
Waterway to 30 feet deep; and raising the 
southerly 4,100 feet of existing training dike, 
extending the training dike 1,500 feet farther 
south, and constructing a breakwater along the 
south and west sides of the existing small boat 
basin. Plane of reference is mean lower low 
water. Range between mean lower low water and 
mean higher high water is 11.1 feet. Extreme 
tidal range is about 19 feet. The boat basin 
breakwater has been deleted at the request of the 
local sponsor, and the remainder of the project 
has been deferred indefinitely. (See Table 38-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. Local 
interests must provide disposal areas for 
maintenance dredging including diking of those 
areas upstream of the 14th Street boat basin. 
Local interests are also required to provide and 
maintain an adequate public landing or wharf, 
with provisions for sale of motor fuel, lubricants, 
and potable water, access roads, parking areas, 
and other necessary public-use shore facilities; 
and make utility and other relocations or 
alterations as required for project purposes. 
Terminal facilities. These include: 1 publicly 
owned terminal with 4 berths handling oceangoing 
vessels, and 15 other wharves and piers in 
Port Gardner; also, 1 publicly owned terminal 
and small-boat basin handling fishing and 
pleasure craft with 2 other wharves in the 
Bayside area, and 9 wharves or piers on the 
Snohomish River. The Port of Everett is planning 
future expansion in the Bayside area. 
Operations and results during fiscal year. 
Maintenance, hired labor: Condition survey for 
preparation of plans and specifications for 
maintenance dredging was completed in 
February. 
Maintenance, contract: Rehabilitation of the 
south 3,250 feet of the dike was completed. Contract, 
awarded in May 1974, included placement 
of 36,500 tons of quarry spoils and 19,100 tons of 
armor rock. 
Condition at end of fiscal year. Existing project 
was completed in April 1963 except for the 
1968 Modification, which has been deferred. Dike 
rehabilitation is 100 percent complete. (See Table 
38-C for total cost of existing project to June 30, 
1975.) 
3. GRAYS HARBOR AND 
CHEHALIS RIVER, WASH. 
Location. Harbor lies at Mouth of Chehalis 
River, in southwestern part of Washington, 45 
miles north of entrance to Columbia River. Inner 
portion comprises two main channels, the south 
and the 'north, connecting harbor proper with 
Chehalis River at Aberdeen. Chehalis River rises 
in southwestern part of Washington about 40 
miles east of Pacific Ocean, flows generally 
northwesterly and empties into eastern part of 
Grays Harbor. (See Coast and Geodetic Survey 
Chart 6195.) 
Previous projects. For details see pages 2002-03 
of Annual Report for 1915, and page 1863 of Annual 
Report for 1938. 
Existing project. Provides for an entrance 
channel across the bar 600 feet wide and 30 feet 
deep, to be secured by a south jetty 13,734 feet 
long and a north jetty 16,000 feet long, both at an 
elevation of 16 feet, and by dredging; 
maintenance of channel 30 feet deep and 350 feet 
wide from deep water in Grays Harbor 14 miles to 
Cow Point; thence 30 feet deep and 200 feet wide, 
suitably widened at bends, to a point 13,700 feet 
upstream from Union Pacific Railroad bridge at 
Aberdeen, a distance of 4.125 miles; a turning 
basin 30 feet deep, 550 feet wide, and 1,000 feet 
long at upstream end of 30-foot channel near 
Cosmopolis; a channel 14 feet deep and 10 feet 
wide in South Bay to Bay City; two breakwaters 
at, and maintenance of entrance channel to, 
Westhaven Cove; and protection of Point Chehalis 
for an exposed length of about 7,500 feet. Plane of 
reference is mean lower low water. Tidal range 
between mean lower low water and mean higher 
high water is 9 feet at Point Chehalis, 9.9 feet at 
Aberdeen, and 8.1 feet at Montesano. Extreme 
range is 15 feet at Point Chehalis, 18.1 feet at 
38-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Aberdeen, and 23.8 feet at Montesano (river flood 
of 1935). (See Table 38-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. In Aberdeen, there are 2 
terminals with 7 berths owned by the Port of 
Grays Harbor handling ocean-going vessels and 
10 usable privately owned piers and wharves, and 
1 each at Markham and Cosmopolis, 7 at 
Hoquiam, 5 private wharves, and 1 Coast Guard 
station at Westhaven Cove. Of the 24 privately 
owned, 2 are used for the receipt of sand and 
gravel, 5 for fish, and 6 for lumber or logs. In addition, 
there are 11 log dumps or receiving areas 
in Grays Harbor. The facilities owned by the Port 
of Grays Harbor are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance, hired labor: Channel condition 
surveys were conducted throughout the year. 
Preconstruction planning is about 80 percent 
complete, for realinement of the Sand Island 
Channel (to be renamed South Reach) which will 
result in a significant reduction in maintenance 
on that reach of the channel. U.S. hopper dredge 
Biddle removed 816,000 cubic yards and the 
hopper dredge Pacific removed 220,000 cubic 
yards from the crossover in Sand Island reaches 
of the navigation channel between November 
1974 and April 1975. 
Maintenance, contract: Approximately 820,- 
000 cubic yards of shoaled material were removed 
from the north channel reach of the project by 
pipeline dredge between Moon Island and Cal 
Point. 
Condition at end of fiscal year. Existing project 
was completed in March 1965, except for the 
deferred and inactive portions. Rehabilitation of 
4,000 feet of the south jetty was completed in October 
1966. For further details, see Annual 
Report for 1967. (See Table 38-C on total cost of 
existing project to June 30, 1975.) 
4. LAKE WASHINGTON SHIP 
CANAL, WASH. 
Location. Entirely within City of Seattle and 
extends from Puget Sound through Shilshole 
Bay, Salmon Bay, Lake Union, Portage Bay, and 
Union Bay to deep water in Lake Washington. 
(See Coast and Geodetic Survey Chart 6447.) 
Previous projects. For details see page 2003, 
Annual Report for 1915, and page 1880, Annual 
Report for 1938. 
Existing project. Provides for a double lock and 
fixed dam with gated spillway and necessary 
accessory works at the Narrows at entrance to 
Salmon Bay, about 1.25 miles from deep water in 
Puget Sound; for a channel 34 feet deep and 300 
feet wide from Puget Sound to Burlington 
Northern Railway bridge, about 5,500 feet, with a 
passing basin 34 feet deep and log basin 8 feet 
deep at turn below railway bridge; then 34 feet 
deep and 150 feet to 200 feet wide to locks, about 
900 feet; and a guide pier 600 feet long; for revetment 
of canal banks between locks and Lake 
Union and between Lakes Union and 
Washington; and for a channel 30 feet deep with a 
width of 100 feet from locks to Lake Union, 200 
feet thence to Portage Cut, 100 feet through Portage 
Cut, and thence 200 feet wide through Union 
Bay to Lake Washington. Section included in 
project is about 10 miles long. Plane of reference 
is mean lower low water. Extreme tidal range is 
19.3 feet. Range between mean lower low water 
and mean higher high water is 11.3 feet, and 
between mean lower low water and extreme low 
water is 4.6 feet. Ordinary fluctuation in upper 
pool is about 22 inches; extreme fluctuation has 
been 3.6 feet. Principal features of double lock 
and dam (structures are at Seattle, Wash.) are set 
forth in Table 38-D. (See also Table 38-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 104 wharves and 
piers on Lake Washington ship canal and adjacent 
inland waters, including Salmon Bay, Lake 
Union, Portage Bay, and Lake Washington. Of 
these, 17 are publicly owned, 8 of which are 
privately operated. The other wharves include 32 
used for building, outfitting, or repair of vessels, 
10 for handling petroleum products, 20 for 
various industrial purposes, and 25 for mooring 
and servicing pleasure craft. Facilities are considered 
adequate for existing commerce. (See 
Port Series No. 36-The Port of Seattle, 
Washington - Revised 1963.) 
Operations and results during fiscal year. Code 
710 Funds: New work, hired labor: Design of 
sanitary facilities was initiated with construction 
scheduled for the "T" Quarter. 
Maintenance, hired labor; Locks were 
operated and maintained all year. 
Maintenance, contract: A $2,105,284 contract 
to rehabilitate the fishladder is 77 percent complete 
with construction completion expected in 
June 1976. A contract for electrical rehabilitation 
of the locks in the amount of $487,830 was awarded 
in June with completion expected in August of 
1977. 
Condition at end offiscal year. Project was completed 
in 1934. (For further details, see Annual 
Report for 1935.) (See Table 38-C for total cost of 
existing project to June 30, 1975.) 
38-4

SEATTLE DISTRICT 
5. OLYMPIA HARBOR, WASH. 
Location. Near southern end of Puget Sound at 
head of Budd Inlet, about 45 miles southwest of 
Tacoma. (See Coast and Geodetic Survey Chart 
6462.) 
Previous projects. For details, see page 1369 of 
Annual Report for 1934 and page 1873 of Annual 
Report for 1938. 
Existing project. Provides for a channel 
between deep water in Budd Inlet and port terminal, 
30 feet deep at mean lower low water and 
500 feet wide, with suitable additional width at 
bend, and a turning basin adjacent to port terminal 
30 feet deep, 3,350 feet long, and 500 to 960 
feet wide. Extreme tidal range is 22.5 feet. Range. 
between mean lower low water and mean higher 
high water is 14.4 feet. Entrance channel and 
turning basin authorized by the 1945 River and 
Harbor Act have been deferred. Estimated cost of 
this portion is $373,000 (July 1957). (See Table 38- 
B for authorizing legislation.) 
Local cooperation. Modification authorized by 
River and Harbor Act of March 2, 1945, requires 
that local interests furnish suitably bulkheaded 
areas for retention of dredged materials, when 
and as required. The Port of Olympia advised on 
January 25, 1949, that it could not comply with requirements 
at that time, but would do so on 
earliest possible date. 
Terminal facilities. There are 15 wharves and 
piers on Olympia Harbor. One publicly owned 
terminal with 4 berths handles ocean-going 
vessels, and there are 13 other wharves and piers 
in the harbor. These facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance, hired labor: Condition surveys 
were conducted and final distribution was made 
on environmental study of open water disposal accomplished 
in 1973. 
Condition at end of fiscal year. Existing project 
was completed in 1939, except for the 1945 
modification. 
6. PUGET SOUND AND ITS 
TRIBUTARY WATERS, WASH. 
Location. Puget Sound is in western part of 
Washington, Cities of Seattle, Tacoma, Olympia, 
Everett, Bellingham, and many small towns are 
on its bays and inlets. (See Coast and Geodetic 
Survey Charts 6300, 6450, and 6460.) 
Previous projects. For details, see page 2003 of 
Annual Report for 1915 and page 1869 of Annual 
Report for 1938. 
Existing project. Maintenance of Puget Sound 
and its tributary waters by snagging and dredging; 
and removal, in cooperation with City of 
Seattle, of floating debris from Seattle Harbor 
area. (See Table 38-B for authorizing legislation.) 
Local cooperation. None required. City of 
Seattle is cooperating in a program for control of 
floating debris in Seattle Harbor. 
Terminal facilities. Terminal facilities at 
numerous localities on Puget Sound and its 
tributary waters are, in general, considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance, hired labor: U.S. snag boat W. T. 
Preston and debris boat Puget are operated continuously 
throughout Puget Sound and its 
tributary waters, removing floating debris and 
hazards to navigation. Debris is loaded aboard 
barges and disposed of by contract. Sweeping and 
snagging operations were accomplished at 
Bellingham Harbor, Swinomish Channel, 
Everett Harbor, Lake Washington Ship Canal, 
Lake Washington, Tacoma Harbor, Duwamish 
River and at Elliott Bay. A plan of study is being 
developed for study of the efficiency of the debris 
collection and disposal operation and for determining 
alternative disposal methods compatible 
with current environmental controls. 
Maintenance, contract: Approximately 3,000 
tons of harbor debris were disposed of. Current 
contractor is recycling approximately 90 percent 
of the debris and placing the remainder in a landfill 
site near Marysville, Washington. 
Condition at end of fiscal year. Work consists 
chiefly of snagging in principal tributaries of 
Puget Sound. No permanent results are obtainable, 
but adequate maintenance of existing 
channels requires practically continuous operation 
of both the snag boat W. T. Preston and debris 
boat Puget. (See Table 38-C for total cost of existing 
project to June 30, 1975.) 
7. QUILLAYUTE RIVER, WASH. 
Location. River is formed by junction of 
Soleduck and Bogachiel Rivers, in northwestern 
Washington, and flows westerly 5 miles to Pacific 
Ocean at La Push, about 30 miles south of Cape 
Flattery. (See Coast and Geodetic Survey Chart 
6102.) 
Existing project. Provides for: (a) Jetty 15 feet 
high on easterly side of river mouth, and a dike on 
westerly side, with a view of stabilizing entrance; 
(b) channel 10 feet deep and 100 feet wide extending 
2,000 feet upstream from deep water; and (c) 
basin 10 feet deep, 300 to 425 feet wide, and 2,400 
feet long upstream of channel. Section included in 
project is 4,400 feet long. Plane of reference is 
mean lower low water. Range between mean 
lower low water and mean higher high water at 
La Push is 8.3 feet. Extreme range is about 15 
feet. (See Table 38-B for authorizing legislation.) 
38-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Local cooperation. Fully complied with. Expended 
$20,000 contributed funds. 
Terminal facilities. There are 7 wharves or 
docks at La Push, near the mouth of the 
Quillayute River; 6 are privately owned. The 
seventh is owned by the United States, and is used 
by the Coast Guard. In addition, there is a 
protected boat basin owned by the Port of Port 
Angeles and used by fishing boats and pleasure 
craft. With the exception of the boat basin, these 
facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. 
Maintenance, hired labor: Condition surveys and 
studies were made of the river channel 
throughout the year. 
Maintenance, contract: Repair of the natural 
spit to the west of the small boat basin was accomplished 
by placing 49,500 tons of small rock in 
a section of the spit, subject to severe storm-wave 
attack. Work was completed in September. 
Condition at end offiscal year. Project was completed 
in February 1960. (For further details, see 
Annual Report for 1963.) The spit which protects 
the boat basin and navigation channel was 
nourished in conjunction with channel dredging 
contract completed in June 1973, and 
rehabilitated with rock in 1974. Erosion is continuing, 
but at a slower rate. 
8. SEATTLE HARBOR, WASH. 
Location. Harbor at Seattle, Wash., includes all 
waterways within city limits. Chief anchorage 
basin is Elliott Bay, an arm of Puget Sound. (See 
Coast and Geodetic Survey Chart 6449.) 
Existing project. Maintenance of East and West 
Waterways, 34 feet deep and 750 feet wide for 
6,500 and 5,200 feet, respectively, from pierhead 
line in Elliott Bay; for maintenance of East 
Waterway between upper end of 750-foot section 
and Spokane Street, 34 feet deep, 700 feet long, 
and 400 feet wide, and a turning basin, including 
head of East Waterway at junction of waterways 
south of Chicago, Milwaukee, St. Paul & Pacific 
Railroad Bridge, to 30 feet deep, after these sections 
of waterway are dredged by local interests 
to full project dimensions; and dredging 
Duwamish Waterway 200 feet wide and 30 feet 
deep between West Waterway and First Avenue 
South, 150 by 20 feet between First and Eighth 
Avenues South, thence 150 feet by 15 feet to a 
point about 1.4 miles about 14th Avenue South 
Bridge, with turning basin 600 by 350 feet and 20 
feet deep just south of First Avenue South Bridge, 
and turning basin 500 by 250 feet and 15 feet 
deep, and settling basin of about 100,000 cubic 
yards capacity at upper end of waterway, a distance 
of 5.12 miles. Total length of waterways included 
in project is about 7.5 miles. Plane of 
reference is mean lower low water. Range 
between mean lower low water and mean higher 
high water is 11.3 feet. Extreme tidal range is 
19.3 feet. (See Table 38-B for authorizing legislation.) 
Local cooperation. Complied with, except for 
inactive portion of project. 
Terminal facilities. There are 112 wharves and 
piers on Seattle Harbor, exclusive of those given 
in report for Lake Washington Ship Canal. These 
facilities are considered adequate for existing 
commerce and are described in Port Series No. 
36-The Port of Seattle, Wash., revised 1963. 
Operations and results during fiscal year. 
Maintenance, hired labor: Condition surveys 
were made. Maintenance, contract: Dredging 
Duwamish Waterway was completed with 250,- 
000 cubic yards of material removed. The 
clamshell dredging operation, with open-water 
disposal, was monitored and a detailed report will 
be furnished. 
Condition at end of fiscal year. Existing project 
was completed in 1931, except settling basin 
at upstream end of project, which is classified inactive, 
and East Waterway above the 750-foot section. 
(For further details, see Annual Report for 
1932.) 
9. SWINOMISH CHANNEL, WASH. 
Location. An inland passage, 11 miles long, 
between Saratoga Passage and Padilla Bay, in 
northwestern part of Washington, about 60 miles 
north of Seattle. (See Coast and Geodetic Survey 
Charts 6300, 6376, and 6380.) 
Existing project. A channel 100 feet wide and 12 
feet deep for 11 miles from deep water in 
Saratoga Passage to deep water in Padilla Bay, 
by dredging and dike construction where 
necessary; and removal of projecting rocky points 
of McGlinn and Fidalgo Islands obstructing 
navigation at "Hole-in-the-Wall". Plane of 
reference is mean lower low water. Range 
between mean lower low water and mean higher 
high water is 11.5 feet at south end of channel, 8.4 
feet at north end, and 10 feet at La Conner. Extreme 
tidal range is about 19.5 feet at south end of 
channel and about 16 feet at north end. (See Table 
38-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 18 wharves, 
docks, and piers on Swinomish Channel, all but 3 
of which are privately owned. Of these, 1 is used 
38-6

SEATTLE DISTRICT 
for handling general cargo, 5 are used exclusively 
for moorage, unloading, and servicing of fishing 
vessels; 2 are used for handling petroleum 
products; 3 facilities are used for log dumps; and 2 
for handling non-metallic minerals. Three 
publicly owned facilities for launching, mooring, 
and servicing small craft are within the city 
limits of La Conner. Terminal facilities for 
general cargo are not considered adequate for existing 
commerce; and Skagit County is planning 
for additional vessel accommodations. 
Operations and results during fiscal year. 
Maintenance, hired labor: Condition surveys 
were made. A major sedimentation study, to 
determine the optimum maintenance plan, was 
initiated. 
Maintenance, contract: Pipeline dredging contract 
awarded in January removed approximately 
125,000 cubic yards of shoal material 
from the channel. 
Condition at end of fiscal year. Project was completed 
in March 1965. (For further details, see 
Annual Report for 1965.) The south jetty west of 
Goat Island has been rehabilitated to reduce 
shoaling from the Skagit River delta area. 
10. TACOMA HARBOR, WASH. 
Location. Harbor includes Commencement 
Bay and tributary waterways at Tacoma, in 
northwestern Wash. (See Coast and Geodetic Survey 
Chart 6407.) 
Previous projects. For details see pages 1372 to 
1376 of Annual Report for 1934 and page 1875 of 
Annual Report for 1938 for Puyallup Waterway; 
and page 1702 of Annual Report for 1944, and 
page 1502 of Annual Report for 1954 for Blair 
(formerly Wapato and Port Industrial) 
Waterway. 
Existing project. Provides for: (a) Channel in 
City Waterway 500 feet wide and 29 feet deep 
from deep water in Commencement Bay to 11th 
Street Bridge, 500 feet wide and 22 feet deep to 
14th Street Bridge, and varying from 500 to 250 
feet wide and 19 feet deep from 14th Street 
Bridge to end of this waterway, a total length of 
8,500 feet; (b) channel in Hylebos Waterway 30 
feet deep, 3.1 miles long, and 200 feet wide except 
where width is increased to 250 feet at the bend 
below East 11th Street, to 300 feet at Lincoln 
Avenue bend, and to 510 feet and 770 feet, respectively, 
at the channel widening above Lincoln 
Avenue and the turning basin at the head of the 
waterway; (c) construction of two training walls, 
each about 700 feet long at mouth of Puyallup 
River; and (d) channel in Blair Waterway 2.6 
miles long, including a portion seaward of East 
11th Street 650 feet wide and 30 feet deep over 
southerly 350 feet, and 35 feet deep over northerly 
300 feet; and remaining portion, 35 feet deep and 
150 feet wide at East 11th Street, 600 feet wide 
between East 11th Street and Lincoln Avenue, 
and 300 feet wide between Lincoln Avenue and a 
1,200-foot wide turning basin at head of 
waterway. Plane of reference is mean lower low 
water. Range between mean lower low water and 
mean higher high water is 11.8 feet. Extreme 
tidal range is about 20 feet. (See Table 38-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminalfacilities. There are 63 privately owned 
piers and wharves, 4 of which handle general 
cargo, 8 handle petroleum products, 2 are copperhandling 
docks, 4 handle wood chips or hogged 
fuel, 3 handle industrial chemicals and salt, 2 
receive sand and gravel, and there is 1 ferry dock. 
The remainder of the privately owned facilities 
are used for various activities normal to a port of 
this size. In addition, the Port of Tacoma owns 7 
terminals, 1 industrial yard, and an industrial 
area including 29 usable berths. The Port of 
Tacoma is presently in an expansion program. 
Operations and results during fiscal year. 
Maintenance, hired labor: Condition surveys 
were made of Puyallup, Hylebos and City 
Waterways. 
Maintenance, contract: Contract awarded in 
April 1974 for removal of 385,000 cubic yards of 
material from Blair Waterway was completed in 
August 1974. 
Condition at end of fiscal year. Existing project 
was completed in December 1966. For further 
details, see Annual Report for 1967. (See Table 
38-C for total cost of existing project to June 30, 
1975.) 
11. WATERWAY CONNECTING 
PORT TOWNSEND AND 
OAK BAY, WASH. 
Location. Canal connects two bays which are 
arms of Admiralty Inlet on west side of Puget 
Sound, in northwestern part of Washington, 
about 40 miles north of Seattle. (See U.S. Coast 
and Geodetic Survey Chart No. 6405.) 
Existing project. Provides for a canal 15 feet 
deep, 75 feet wide on the bottom, and about 4,800 
feet long, and for construction of jetties to protect 
channel at southern or Oak Bay end, and a 
bulkhead for retention of dredged material. 
Plane of reference is mean lower low water. 
Range between mean lower low water and mean 
higher high water is 8.3 feet in Port Townsend 
Bay and 9.4 feet in Oak Bay. Extreme tidal range 
is 16 feet. (See Table 38-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
38-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Terminal facilities. None directly served by the 
canal. 
Operations and results during fiscal year. 
Maintenance, hired labor: Condition Surveys 
were made. 
Condition at end of fiscal year. Project was initiated 
and completed in 1915. 
12. WILLAPA RIVER AND HARBOR 
AND NASELLE RIVER, WASH. 
Location. Willapa Harbor consists of lower 
reaches of Willapa River and Bay, an inlet of 
Pacific Ocean about 30 miles north of Mouth of 
Columbia River in Washington. Willapa River 
rises about 30 miles east of harbor, flows generally 
westerly, and empties into the bay. Naselle 
River enters the bay near its southerly end. (See 
Coast and Geodetic Survey Chart 6185.) 
Previous projects. For details see Annual 
Reports for 1915 (page 2001), 1910 (page 968), and 
1938 (page 1861). 
Existing project. Provides for: (a) channel over 
bar at mouth of Willapa Bay, 26 feet deep and at 
least 500 feet wide; (b) channel 24 feet deep and 
200 feet wide from deep water in Willapa Bay to 
foot of Ferry Street at South Bend, thence 300 feet 
wide to westerly end of narrows, thence 250 feet 
wide to forks of river at Raymond, including a 
cutoff channel 3,100 feet long at narrows and a 
closing dike at Mailboat Slough; (c) channel 24 
feet deep and 150 feet wide up south fork to deep 
basin above Cram lumber mill, and up north fork 
to 12th Street, with a turning basin 250 feet wide, 
350 feet long, and 24 feet deep at latter point; (d) 
channel 10 feet deep and 40 feet wide from deep 
water in Palix River to Bay Center dock, with 
widening at shoreward end to provide a small 
mooring basin; (e) mooring basin 15 feet deep, 350 
feet wide, and 600 feet long adjacent to port wharf 
at Tokeland; (f) entrance channel at Nahcotta 10 
feet deep and 300 feet wide, and mooring basin 10 
feet deep, 500 feet wide, and 1,100 feet long, 
protected by a rubblemound breakwater about 
1,600 feet long; and (g) removal of snags, piles, 
and other obstructions in navigable channel of 
Naselle River between Naselle and mouth. Project 
includes about 26 miles of channel from entrance 
through Willapa River forks, 2,800 feet of 
Palix River-Bay Center channel, and 9 miles of 
Naselle River upstream of U.S. Highway 101 
Bridge. Plane of reference is mean lower low 
water. Tidal range between mean lower low 
water and mean higher high water is 8.9 feet at 
Toke Point; 9.9 feet at Raymond; 9.2 feet at Bay 
Center; and 10.8 feet near Naselle. Extreme 
range is 18 feet at Toke Point; 19.3 feet at Raymond; 
16 feet at Bay Center; and 18 feet near 
Naselle. (See Table 38-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 24 wharves on 
Willapa River and Harbor, including 5 in 
Willapa Bay, 4 in Bay Center, 12 in Raymond and 
South Bend, and 1 in Tokeland. Two of the 
wharves at Raymond and South Bend are 
suitable for use by ocean-going vessels; one of 
these is publicly owned and operated as a general 
cargo terminal, and one is located at a sawmill. 
The other wharves, including 3 that are publicly 
owned and operated, are used by shallow-draft 
vessels. These facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance, hired labor: U.S. hopper dredge 
Pacific removed 25,000 cubic yards of material 
from the Bay Center channel. Numerous condition 
surveys were conducted on the inner and bar 
channels. 
Maintenance, contract: Contract awarded in 
May 1974 for maintenance dredging of Willapa 
River removed 43,486 cubic yards of material by 
pipeline dredge from the entrance channels at the 
Bay Center and Toke Point boat basins. Work was 
completed in September. 
Condition at end of fiscal year. Project was completed 
in November 1958. (For further details, 
see Annual Report for 1959.) (See Table 38-C for 
total cost of existing project to June 30, 1975.) 
13. PROJECT CONDITION SURVEYS 
See Table 38-E. 
14. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 38-F. 
15. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to section 107, 
Public Law 86-645 (preauthorization) 
Fiscal year costs for preauthorization studies 
were $782 for Dungeness-Sequim Small Boat 
Basin, Wash.; $15,000 for East Bay Small Boat 
Basin, Olympia, Wash.; $34 for La Conner Small 
Boat Basin Expansion, La Conner, Wash.; $8,887 
for Squalicum Small Boat Harbor, Bellingham, 
Wash.; and $40 for Tulalip Bay Small Boat Basin, 
Tulalip, Wash. 
16. EDIZ HOOK, WASH. 
Location. Ediz Hook and the City of Port 
Angeles are on thle Strait of Juan de Fuca in 
Clallam County, Washington, about 100 miles 
northwest of Seattle. 
38-8

SEATTLE DISTRICT 
Existing project. Provides for construction of 
about 10,000 lineal feet of rock revetment, 
together with initial beach replenishment and annual 
nourishment. Also, provides emergency interim 
measures necessary to prevent the 
breaching of Ediz Hook prior to construction of 
authorized project. Estimated cost of project is 
$7,850,000 (October 1975), including $7,310,000 
Federal funds and non-Federal costs of $540,000. 
In addition, cost of interim measures is $700,000. 
(See Table 38-B for authorizing legislation.) 
Local cooperation. Local interests are required 
to provide all necessary lands, easements, and 
rights-of-way necessary for construction of the 
improvements; hold and save the United States 
free from claims for damages that may result 
from construction or maintenance of the protective 
works; bear 6.9 percent of the total first cost; 
assure maintenance and repair of the revetment 
works and periodic beach nourishment during 
the economic life of the project as may be required 
to serve the intended purpose, subject to Federal 
participation; and assure continued public 
ownership of the shore upon which the amount of 
Federal participation is based, and its administration 
for public use during the economic 
life of the project. The City of Port Angeles, by 
letter dated 23 July 1971, agreed to sponsor the 
project and meet requirements of local cooperation. 
Operations and results during fiscal year. New 
work, hired labor: Preparation of a General 
Design Memorandum was initiated. 
New work, contract: Contract for interim 
emergency repair, awarded on June 29, 1974, was 
completed in November. 
17. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION. 
Beach erosion activities pursuant to Section 103, 
Public Law 86-645 (preauthorization) 
Fiscal year costs for preauthorization studies 
were $43,268 for Sunnyside Beach Erosion 
Protection, Steilacoom, Wash., and $76,099 for 
Waterfront Parks, Seattle, Wash. 
Flood Control 
18. HOWARD A. HANSON DAM, WASH. 
Location. Green River, in northwestern 
Washington, flows westerly for 40 miles to 
Auburn, thence northerly 32 miles to its mouth in 
Elliott Bay at Seattle. Dam is at river mile 64, 6 
miles southeast of Kanaskat, and 1 mile 
downstream from Mouth of North Fork. (See 
Geological Survey topographic sheet, "Cedar 
Lake quadrangle, Wash.") 
Existing project. Rockfill dam about 235 feet 
high, with gated spillway having a concrete weir 
at elevation 1176 feet above mean sea level and 
top of gates at elevation 1206, creating a reservoir 
with capacity of 106,000 acre-feet. Dam along 
crest is about 675 feet long. Improvement is 
designed to control flooding in Green River 
Valley to alleviate agricultural and urban flood 
damage, and make possible further expansion of 
Seattle industrial area. Also, supplements 
Tacoma water supply which was included as a 
betterment. (See Table 38-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. Contributed 
funds expended, $2 million. 
Operations and results during fiscal year. 
Maintenance, hired labor: Operation continued 
all year. Routine maintenance was accomplished 
on roads, gages, debris booms, turbidimeter, 
ditches, powerline, and other project features. 
Work continued on water quality surveys, water 
storage studies, and channel capacity study. 
Maintenance, contract: Settlement of the fill 
for the relocated Burlington Northern Railway 
between stations 10989 and 10991 was under continued 
surveillance. The deferred construction 
period has been extended to cover this area to 
observe effect of remedial work. (Improvements 
to the drainage system have apparently stabilized 
the railroad fill.) 
Condition at end offiscal year. Project was completed 
in June 1963. (For further details, see Annual 
Report for 1966.) 
19. MUD MOUNTAIN DAM, WASH. 
Location. On White River, principal tributary 
of Puyallup River, near Mud Mountain, 28 miles 
above its confluence with Puyallup River, and 38 
miles above Mouth of Puyallup River. Dam is 6 
miles southeast of Enumclaw, in northwestern 
Washington, and 38 miles east of Tacoma. (See 
Geological Survey topographic sheet "Cedar 
Lake quadrangle, Washington.") 
Existing project. Rockfill dam, 700 feet long at 
crest elevation, rises 425 feet above bedrock. 
Reservoir has storage capacity of about 106,000 
acre-feet. Outlet works are in right abutment and 
permit controlled discharge of 17,700 cubic feet 
per second through two concrete-lined tunnels 
with uncontrolled discharge over spillway having 
maximum capacity of 139,000 cubic feet per second. 
Improvement affords flood protection to 
White and Puyallup River Valleys and protects 
Tacoma industrial district in conjunction with 
Puyallup River project at Tacoma against floods 
about 50 percent greater than maximum discharge 
of record. Estimated cost of recreation 
facilities for completed project is $644,600 (July 
38-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
1974). (See Table 38-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance, hired labor: Project features were 
operated all year. Maintenance was accomplished 
on dam facilities, 9-foot regulating 
outlet tunnel, intake structure, gages, debris 
booms, power lines, roads, ditches, and fish 
facilities. Tank trucks hauled 1,789 fish past the 
dam. 
Maintenance, contract: Construction was completed 
in July 1974 on a new sewage treatment 
facility, in October 1974 on the water system improvements 
and in November 1974 on the electrical 
distribution system. 
Condition at end of fiscal year. Project was completed 
in June 1953, except for recreation 
facilities. (For further details, see Annual Report 
for 1953.) The Corps has constructed two vistas, a 
picnic area, and playground adjacent to the project 
office, a reservoir access point for hunters and 
fishermen, and a 1,760-foot trail leading to the 
lower vista area. 
20. STILLAGUAMISH RIVER, WASH. 
Location. Formed by confluence of its north 
and south forks at Arlington, in northwestern 
Washington, Stillaguamish River flows westerly 
22 miles to Puget Sound, entering Port Susan 
through Hat Slough and South Pass, and Skagit 
Bay through West Pass. (See Coast and Geodetic 
Survey Chart 6450, and Geological Survey 
quadrangles Stanwood, Marysville, and' 
Stillaguamish, Wash.) 
Existing project. Works to reduce bank erosion 
and channel changes on Stillaguamish River 15 
miles between Arlington and head of Hat Slough, 
and on Cook Slough, 3 miles long, as 
follows: Revetment at 26 places on river and 
Cook Slough; concrete weir 275 feet long between 
steel-sheet-pile piers at head of Cook Slough to 
limit flow through slough; and two cutoff 
channels, each about 900 feet long, to eliminate 
sharp bends in Cook Slough. Tidal influence extends 
about 3 miles into improved section.. Flood 
stages of 16 feet above low water at Cook Slough 
weir have been observed. (See Table 38-B for 
authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance, hired labor: Removed brush and 
trees on approximately 2,000 linear feet of revetment. 
Condition at end offiscal year. Project was completed 
in July 1939. (For further details see Annual 
Report for 1940.) 
21. TACOMA, PUYALLUP RIVER, WASH. 
Location. Puyallup River has its source in 
glaciers on western slopes of Mount Rainier, 
Wash., flows northwesterly 50 miles, and empties 
into Commencement Bay, an arm of Puget Sound, 
at Tacoma. Work covered by this project is on 
Puyallup River, within city limits of Tacoma. 
(See Coast and Geodetic Survey Chart 6407.) 
Existing project. A channel with a capacity of 
50,000 second-feet between East 11th Street 
Bridge and lower end of inter-county improvement, 
a distance of about 2.2 miles, by straightening 
channel, building levees, revetting channel 
and levees, and making necessary bridge 
changes. The 11th Street Bridge at lower end of 
project is 0.75 mile above Mouth of Puyallup 
River. Diurnal tidal range at mouth of river is 
11.8 feet and extreme range is 20 feet. Improvement 
was planned in conjunction with Mud 
Mountain Dam and affords protection against 
floods about 50 percent greater than maximum 
discharge of record. (See Table 38-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance, hired labor: Routine operation and 
condition studies were made, surveys of silt 
ranges were taken, and a herbicide was spread on 
levee banks to kill brush and trees. 
Condition at end offiscal year. Project was completed 
in May 1950. (For further details, see Annual 
Report for 1950.) 
22. WENATCHEE, CANYONS 1 AND 
2, WASH. 
Location. Canyons 1 and 2 lie west of 
Wenatchee, in central Washington, in foothills on 
the east slope of the Cascade Mountains. (See 
Geological Survey quadrangles Wenatchee and 
Monitor, Wash.) 
Existing project. Provides for construction of 
about 4.6 miles of reinforced-concrete-lined 
channels to control flooding from Canyons 1 and 
2. Individual channels would begin at an inlet and 
debris basin near the mouth of each canyon and 
extend to a confluence structure in north 
Wenatchee. A combined channel would carry 
flows through Wenatchee from the confluence 
structure to an outlet structure and stilling basin 
on the Columbia River. Estimated cost of project 
is $21,500,000 (October 1975), including $20,000,- 
000 Federal funds and non-Federal costs of $1,- 
500,000. (See Table 38-B for authorizing legislation.) 
Local cooperation. Prior to construction, local 
interests must furnish assurances satisfactory to 
the Secretary of the Army that they will provide 
38-10

SEATTLE DISTRICT 
without cost to the United States all lands, 
easements, and rights-of-way necessary for construction 
of the project; save the United States 
free from damages due to the construction works; 
maintain and operate all the works after completion 
in accordance with regulations prescribed by 
the Secretary of the Army; provide without cost to 
the United States necessary relocations of 
buildings, utilities, sewers, and related facilities, 
and construction of bridges; prevent encroachment 
on the rights-of-way of the improvement 
that would reduce the flood-carrying capacity of 
the streams or interfere with operation and 
maintenance of the project; and make annual inspections 
of the drainage areas above the project 
to remove large debris, such as logs and fallen 
timbers, which could be carried downstream and 
impair the flood-carrying capacities of the 
channels. 
Operations and results during fiscal year. New 
work, hired labor: Engineering and design work 
continued. 
New work, contract: Contract for an environmental 
analysis was completed. 
Condition at end of fiscal year. No construction 
work has been done. 
23. WYNOOCHEE LAKE, WASH. 
Location. On Wynoochee River, a tributary of 
Chehalis River, about 28 miles north of 
Montesano, Grays Harbor County, Wash. (See 
Geological Survey quadrangles, Grisdale, 
Wynoochee Valley, and Montesano.) 
Existing project. Provides for a concrete and 
earthfill dam, 177 feet high, and reservoir of 70,- 
000 acre-feet of total storage for water supply, 
flood control, irrigation, and fish and wildlife. Installation 
of power-generating facilities was not 
authorized, pending a reexamination report by 
the Chief of Engineers. In February 1966, the 
Federal Power Commission asserted that power 
production as part of the Wynoochee project was 
not feasible at that time. Estimated cost of the 
project is $24,100,000 (July 1975). (See Table 38-B 
for authorizing legislation.) 
Local cooperation. Local interests must repay 
all costs allocated to water supply, in accordance 
with the Water Supply Act of 1958, as amended. 
A water supply contract was signed in August 
1967. Repayment estimate is $18,371,000. This 
reimbursable cost is divided into three increments 
corresponding to three increments of 
storage allocated to water supply, each of which 
must be paid, with interest, within 50 years of the 
first use of that increment of storage. The first increment, 
$10,718,000, is considered nondeferrable, 
with annual payments beginning in 
January 1973. A Congressional authorized 
amendment permitted deferral of the major portion 
of the first 10 years payments. Local interests 
must also repay such costs allocated to irrigation 
as are later determined to be repayable under 
Federal reclamation law; and hold the United 
States free from damages for water-rights claims 
resulting from construction and operation of the 
project. 
Operations and results during fiscal year. New 
work, hired labor: Work continued on miscellaneous 
items such as preparation of agreement 
for fish hatchery and study of downstream 
fish passage. 
New work, contract: None. 
Maintenance, hired labor: Project facilities 
'were operated all year. Maintenance was accomplished 
on dam and fish facilities, roads, 
ditches, culverts, and visitors' facilities. 
Washington State Department of Fisheries was 
furnished assistance in performance of tests of 
low-flow outlet conduits. A tank truck hauled 
3,669 fish past the dam. 
Condition at end of fiscal year. Upstream fish 
facilities were operational in the fall of 1970. Project 
as a whole is 98 percent complete with only 
construction of fish and wildlife items by State 
agencies yet to be completed. 
24. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS. 
Inspections are made of Federally constructed 
local flood protection projects which are maintained 
by local interests; and agencies responsible 
for their operation and maintenance are advised 
of any needed repairs. During the fiscal year, inspections 
were made on the Nooksack and 
Spokane Rivers in Washington, St. Joe and Coeur 
d'Alene Rivers in Idaho and Flathead River, 
Montana, in July and August; and Yakima, 
Skagit, Puyallup and Stillaguamish Rivers, 
Washington, in October; Snohomish, Yakima, 
Cedar, Green, Nisqually and Deschutes Rivers, 
Washington, in February; and Okanogan, 
Methow Rivers, Washington and Bitterroot 
River, Montana, in April. Fiscal year costs were 
$20,885. Costs to date have been $152,362. 
25. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Flood control storage was reserved in Hungry 
Horse Reservoir, Mont., and Ross Reservoir, 
Wash., in accordance with prescribed rule 
curves. Guidance forecasts were made during the 
flood control season, as required, and monthly 
reports on operations were submitted. Storage 
for replacement of lost valley storage at Upper 
Baker, Rocky Reach, and Priest Rapids and Wells 
38-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Dams, in Washington, was provided in accordance 
with rule curves and flood forecasts. Daily 
and/or hourly data were collected and tabulated 
as required to check compliance with operating 
criteria. Coordination necessary in preparation 
or revision of reservoir regulation manuals was 
carried on during the year with agencies responsible 
for the operation of these projects. Fiscal 
year costs were $55,912. 
26. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 38-G. 
27. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization) 
Fiscal year costs for preauthorization studies 
were $454 for Lower Elwha River near Port 
Angeles, Wash.; $114,533 for Omak, Okanogan 
River, Wash., and $72,050 for Oroville, Okanogan 
River, Wash. 
Emergency flood-control activities - repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation.) 
See Table 38-H. 
Emergency bank protection (sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.). 
See Table 38-H. 
Multiple-Purpose Power Projects 
28. ALBENI FALLS DAM, IDAHO 
Location. Dam is on Pend Oreille River about 
25 miles west of Sandpoint, in northern Idaho, 
and 50 miles northeast of Spokane, Wash. Dam is 
838 and 90 miles upstream from mouths of 
Columbia and Pend Oreille Rivers, respectively. 
(See Geological Survey topographic sheets, Sandpoint, 
Idaho, and Newport, Wash.) 
Existing project. Provides flood control, 
hydroelectric power, and related water uses on 
Pend Oreille River as a part of the multiplepurpose 
plan for development of Columbia River 
Basin, including recreation development. At the 
dam, channel was formerly divided by an island 
and a low waterfall of about 7 feet. Dam is a gated, 
gravity-structure spillway in left channel and a 
powerhouse having an installation of 42,600 
kilowatts in right channel, creating a reservoir 
with a usable storage capacity of 1,153,000 acrefeet. 
Estimated cost of recreation facilities for 
completed project is $1,063,600 (July 1974). (See 
Table 38-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. Code 
710 funds: New work, hired labor: Engineering 
studies continued. 
New work, contract: Showers were added to 
campground restrooms at Priest River and a new 
restroom constructed at Albeni Cove. 
Regular funds: Maintenance, hired 
labor: Reservoir was operated through its annual 
cycle of storage and release. Routine structural, 
mechanical, and electrical maintenance was performed 
on spillway, dam, powerhouse, and equipment. 
Condition at end of fiscal year. Project was completed 
in June 1957. (For further details, see Annual 
Report for 1957.) Recreation facilities for 
public use have been provided at Albeni Cove, 
Priest River, Riley Creek, Johnson Creek, Trestle 
Creek, Strongs Island, and Springy Point, and 
planning for additional areas and further 
development of existing areas is underway. 
29. CHIEF JOSEPH DAM - 
RUFUS WOODS LAKE, WASH. 
Location. On Columbia River in north central 
Washington, at river mile 545, just upstream 
from Mouth of Foster Creek, 1.5 miles upstream 
from Town of Bridgeport. (Geological Survey 
topographic sheet Okanogan, Wash., shows 
general locality.) 
Existing project. A straight concrete gravity 
overflow dam, 220 feet high; powerhouse; and intake 
structure with gate bays for 27 generating 
units. Ultimate installed capacity depends on 
future development of upstream storage. 
Powerhouse has 16 generator units installed, and 
provides superstructure for 17 units and substructure 
for 20 units. All installed units are of 
64,000 kilowatts nameplate capacity. Estimated 
cost of 11 additional units is $315,000,000 (October 
1975). (See Table 38-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Regular funds; New work, hired 
labor: Engineering and design work continued 
on additional generator units and structural 
modifications. Design memoranda supplements 
on structural modifications and concrete 
materials investigations were completed and real 
estate design memorandum approved. Work continued 
on design memoranda for landscaping, 
visitors facilities, relocations, master plan and 
recreation. Plans and specifications were 97 percent 
complete for structural modifications, 98 
percent complete for digital processor and 1 percent 
complete on Box Canyon recreation site. 
38-12

SEATTLE DISTRICT 
New work, contract: Supply contracts were 
awarded for intake gate hoists, generators, governors, 
14.4-KV switchgear and bus structures, 
wire and cable, 480-volt equipment, transformers 
and high-voltage equipment. Construction contracts 
were awarded for penstocks, powerhouse 
initial excavation and cofferdam, resident and 
administration building and powerhouse structure 
and equipment installation. Contracts on 
reinforcing steel and rock bolts and drains were 
completed. 
Maintenance, hired labor: Project was 
operated all year, and routine maintenance work 
was performed. 
Maintenance, contract: Cleaning and scaling 
of penstock area was completed. Stilling basin inspection, 
initiated in 1974, was finished. 
Cadastral retracement survey was completed in 
early 1975. Miscellaneous small contracts, covering 
new gas/diesel dispensing pump, spillway 
maintenance scaffold and generator air coolers, 
were completed. 
Condition at end of fiscal year. Project 
providing initial 16 power units was completed in 
fiscal year 1961. (For further details, see Annual 
Report for 1962.) Recreation facilities have been 
provided at the damsite and at Bridgeport State 
Park for public use. Preconstruction planning for 
installation of 11 additional units is complete. 
Construction on the additional units continued 
and is 9 percent complete. 
30. LIBBY DAM - LAKE KOOCANUSA, 
MONT. 
Location. On Kootenai River in Lincoln County, 
Mont., about 17 miles upstream from Libby, and 
219 miles upstream from confluence of Kootenai 
with Columbia River. (See Geological Survey 
topographic sheet, Thompson Lakes, Mont.) 
Existing project. Provides storage for local 
flood control protection in Montana and Idaho, 
and main stem flood control in Lower Columbia 
River, hydroelectric power generation at-site and 
at downstream plants through storage release. 
Project will be operated as a unit of comprehensive 
system for improvement of Columbia River 
Basin for flood control, navigation, hydro-electric 
power, and other purposes. 
Libby Dam - Lake Koocanusa Project. Dam is a 
straight concrete gravity overflow type, 420 feet 
high, 3,055 feet long, with normal full pool at 
elevation 2459 feet above mean sea level. Powerhouse 
has an initial installed capacity of 420,000 
kilowatts from four hydro-electric generating units 
with provision for four additional units. Lake 
Koocanusa is 90 miles long, backing water 42 
miles into Canada, has a usable storage capacity 
of 4,965,000 acre-feet at 50 percent drawdown. 
Construction of dam is in accordance with treaty 
between United States and Canada relating to international 
cooperation in water-resource 
development of the Columbia River Basin. Project 
features include: Relocation of 52 miles of 
Montana State Highway; 60 miles of Burlington 
Northern Railroad, including a seven mile 
tunnel; 50 miles of Forest Development roads, 
including a 2,400 foot long steel truss bridge; 
construction of a selective withdrawal structure 
to control temperature and oxygen conditions of 
water released past the dam; a visitor center with 
an exhibit program developed and operated by 
the Montana Historical Society as the western 
branch museum of the State of Montana; school 
facilities for education of dependents of construction 
personnel; participation in airport facilities 
at Kelley Flats, Montana; use of $4,000,000 project 
funds for fish production measures; acquisition 
and conveyance to the State of Montana not 
more than 12,000 acres of land, at cost not to exceed 
$2,000,000, for the prevention of wildlife 
grazing losses caused by the project; relocating 
Deep Creek Bridge, Boundary County, Idaho; 
compensating drainage districts and owners of 
leveed and unleveed tracts in Kootenai Flats, 
Boundary County, Idaho, for modification of 
pumping facilities, crops and other damages 
caused by duration of higher flows during drawdown 
operation of Libby Dam; constructing central 
sewage collection and treatment facilities as 
part of the relocation of municipal facilities of 
Rexford, Montana; and 8 campground recreation 
facilities. Recreation development beyond 
the initial 8 sites will be by the U.S. Forest Service. 
Cost estimate for the new work (4 units) is 
$480,000,000 (October 1975) Corps of Engineers 
funds; $185,349 Federal Aviation Agency funds; 
and $17,500 contributed funds for Kelley Flats 
airport facility. (See Table 38-B for authorizing 
legislation.) 
Libby Additional Units and Reregulating Dam 
Project. Provides for installation of 4 additional 
units at the Libby Dam Powerhouse, construction 
of a reregulating dam about 10 miles downstream 
of Libby Dam, and associated relocation 
of about 9 miles of Burlington Northern Railroad 
and Montana State Highway. Estimated Federal 
cost is $193,000,000 (October 1975). Project is 
pending authority and funds for construction 
start. (See Table 38-B for authorizing legislation.) 
Libby Reregulating Dam -Power Units Project. 
Provides for installation of three hydro-electric 
generating units at the reregulating dam with 
76,400 kilowatt installed capacity. Cost to install 
the three units is estimated at $33,000,000 (October 
1975), not including $29,000,000 included 
with the Libby Additional Units and 
Reregulating Dam Project for minimum future 
38-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
power facilities. (See Table 38-B for authorizing 
legislation.) 
Local cooperation. Fully complied with (participation 
in construction of airport facility at 
Kelley Flats, Montana). Contributed funds 
expended $15,910. 
Operations and results during fiscal year. New 
work, hired labor: Design efforts were started on 
Montana State Highway 37, Unit 3A final relocation, 
Montana State Highway landscape restoration, 
rehabilitation Forest Development Road, 
arrangements with Boundary County for design 
and construction of Deep Creek Bridge, and 
Souse Gulch day use area boat dock. 
New work, contract: Construction work began 
on the reconstruction of Deep Creek Bridge by 
Boundary County, Idaho, and commemorative 
sculpturing on the Treaty Tower. Work continued 
on the selective withdrawal structure, 
powerhouse and installation of electrical equipment, 
visitor center building, Souse Gulch day 
use area and installation of exhibits in the Visitor 
Center Building. Lake Koocanusa was 
transferred to the Forest Service for supervision 
and management in accordance with the 
Memorandum of Understanding, and Montana 
State Highway 37 was transferred to the Montana 
Department of Highway November 1974 in 
accordance with the relocation agreement. Coordination 
with the Libby Chamber of Commerce 
on preparation for dam dedication, August 1975, 
was initiated. 
On the Libby Additional Units and Reregulating 
Dam Project, preconstruction planning was 
completed with the submission of General Design 
Memorandum Phase 2. 
On the Libby Reregulating Dam - Power Units 
Project, preconstruction planning began with the 
initiation of work on the GDM Phase 1. 
Maintenance, hired labor: Operation Division 
assumed responsibility for the dam on December 
6, 1973. Maintenance was accomplished on dam, 
buildings, grounds, and powerhouse equipment 
as completed. First power-on-line has been 
rescheduled to August 1975 in conjunction with 
the dam dedication ceremonies scheduled 24 
August 1975. 
Condition at end of fiscal year. Libby Dam - 
Lake Koocanusa Project: Planning and design is 
90 percent complete with remaining work consisting 
of: continued coordination with Canada 
for water quality protection; fish hatchery; 
landscape restoration; recreation campgrounds; 
wildlife land acquisition; cultural resources 
preservation; Montana State Highway 37 Unit 
3A; Forest Development Road rehabilitation; 
boat dock; bas relief in Treaty Tower grotto; 
aquarium; public use plan; and hydrology and 
reservoir operations. Completed construction 
work includes: dam, relocation of 60 miles of 
Burlington Northern Railroad, Forest Service 
Ranger Station and work center at Canoe Gulch, 
Forest Service work center at Eureka, cemetary 
and grave relocations, airport facilities at Kelley 
Flats, school facilities to assist local communities 
in meeting their needs for additional classrooms, 
reservoir clearing, relocation of town of Rexford 
municipal facilities, and 50 miles of Forest 
Development Road. Relocation of 52 miles of 
Montana State Highway is essentially complete 
with highway open to public travel since 
November 1974. A short reach, about 3/4 miles 
long, remains to be constructed to final alinement 
and grade as soon as a railroad spur track used for 
delivering materials to the dam site can be 
removed. Powerhouse and miscellaneous structures 
contract, including installation of power 
generation equipment, is 89 percent complete. 
The project as a whole is about 90 percent complete. 
Canada has completed all reservoir clearing 
work in their portion of Lake Koocanusa, 
including relocation of railroads and roads. 
Libby Additional Units and Reregulating Dam 
Project. Further work on this project is pending 
authority and funds for construction start. 
Libby Reregulating Dam -Power Units Project. 
Continuation of preconstruction planning by initiating 
work on General Design Memorandum 1, 
Phase 2, is pending authorization to proceed. 
31. OTHER AUTHORIZED 
MULTIPLE-PURPOSE POWER 
PROJECTS 
See Table 38-I. 
General Investigations 
32. SURVEYS 
Fiscal year costs were $1,320,984, of which 
$699,182 was for flood control studies, $231,817 
was for navigation studies, $5,796 was for special 
studies, $249,341 was for comprehensive basin 
studies, and $134,848 was for review of authorized 
projects. 
33. COLLECTION AND STUDY OF 
BASIC DATA 
The work programmed for collection and study 
of basic data covers international water studies, 
flood plain management services, and hydrologic 
studies. Work on international water studies included 
checking Kootenay Lake storage computations 
to determine compliance of West 
Kootenay Power & Light Co. with orders of International 
Joint Commission, and coordination 
38-14

SEATTLE DISTRICT 
with International Kootenay Lake, Osoyoos Lake, 
and Skagit River Boards of Control in enforcement 
of International Joint Commission orders. 
Technical assistance was provided other Federal 
and non-Federal agencies in flood hazard evaluation 
and related services as requested. Flood 
plain information reports were prepared for Lolo 
Creek, Montana; Snohomish River, Washington; 
Chehalis and Skookumchuck Rivers, 
Washington; and Yakima River, Washington. 
Fiscal year costs were $8,491 for international 
water studies, $299,143 for flood plain management 
services, and $7,021 for hydrologic studies, 
a total of $314,655. (See Table 38-J on completed 
flood plain studies.) 
34. RESEARCH AND DEVELOPMENT 
No program for F.Y. 1975. 
38-15

TABLE 38-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Anacortes Harbor 
Wash. 
(Federal Funds) 
(Contrib. Funds) 
la. Anacortes Navigation 
Channel, Wash. 
(Sec. 107) 
2. Everett Harbor 
and Snohomish 
River, Wash. 
(Federal Funds) 
(Contrib. Funds) 
3. Grays Harbor and 
Chehalis River, 
Wash. 
(Federal Funds) 
(Contrib. Funds) 
4. Lake Washington 
Ship Canal, Wash. 
5. Olympia Harbor, 
Wash. 
6. Puget Sound and its 
Tributary Waters, 
Wash. 
7. Quillayute River, 
Wash. 
(Federal Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 222,345 
- 222,345 
5,322 
5,322 
5,606 
5,606 
13,006 
13,006 
243,200 
.243,005 
5,000 
5,000 
779,300 
183,379 
5,595 
31,817 
31,850 
-85 
2,350 
226,233 
65,475 
356,000 
501,427 
372,980 
372,785 2 
59,523 
59,523 
5,000 
5,000 
779,300 
183,379 
- 1,775,744 
- 1,775,744 1 
337,500 2,452,902 
350,995 2,451,066 2 3 
- - - - 5,618 
- - - - 5,618 
- - - - 5,030,851 
- - - - 5,030,851 4 
2,098,959 2,105,447 2,109,873 3,749,700 35,098,416 
1,449,558 2,791,119 1,985,920 3,281,012 34,464,201 5 
- - - - 120,592 
- - - - 120,592 
- - - - 4,606,145 
- - - - 4,606,145 
- - - - 35,834 
- - - - 35,834 
- - - - 47,889 
- - - - 47,889 
- - - 6,200 
- - - 4,498 
1,650,100 1,905,143 2,322,500 2,933,600 
1,173,594 2,133,841 2,460,062 2,649,250 
577 
89,444 
19,444 
460,175 
460,200 
260,236 
447,569 
369 
268,228 
334,228 
483,467 
481,653 
190,237 
190,590 
6,000 
5,399 
595,000 
595,204 
176,372 
154,093 
4,030,497 7 
4,028,795 6 8 
25,647,630 
25,172,998 9 
- 464,782 
- 464,782 10 
4,300 560,333 
8,690 560,122 2 11 
- 43,337 
- 43,337 
578,700 7,372,133 
575,780 7,367,553 12 
- 521,850 
- 521,850 13 
506,500 2,764,760 
528,902 2,764,570 
38-16

SEATTLE DISTRICT 
TABLE 38-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
(Contrib. Funds) 
8. Seattle Harbor, 
Wash. 
(Federal Funds) 
(Contrib. Funds) 
9. Swinomish Channel, 
Wash. 
10. Tacoma Harbor, 
Wash. 
(Federal Funds) 
(Contrib. Funds) 
11. Waterway Connecting 
Port Townsend and 
Oak Bay, Wash. 
12. Willapa River and 
Harbor and Naselle 
River, Wash. 
(Federal Funds) 
(Contrib. Funds) 
16. Ediz Hook, Wash. 
(Federal Funds) 
18. Howard A. Hanson 
Dam, Wash. 
(Federal Funds) 
(Contrib. Funds) 
19. Mud Mountain Dam, 
Wash. 
20. Stillaguamish 
River, Wash. 
Funding 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
19,400 
19,400 
462,012 
290,900 
43,597 
207,397 
4,244 
4,244 
11,478 
11,478 
154,612 
153,506 
-362 
189,912 
26,112 
877 
877 
32,476 
30,617 
265,000 
432,834 
338,155 
159,373 
85,500 
77,746 
663,505 
588,546 
295,405 
277,659 
34,589 
856,500 
854,524 
- 20,000 
- 20,000 
- 170,335 
- 170,335 
407,400 2,848,041 
406,715 2,845,497 2 
- 69,333 
- 69,333 
- 808,332 
- 808,332 14 
342,300 3,761,743 
344,276 3,758,935 
- 2,435,500 
- 2,435,500 15 
-9,200 1,111,075 
169,581 1,111,074 2 16 
- 559,581 
- 559,581 17 
- 73,322 
- 73,322 
-300 233,293 
7,454 233,293 2 
- 1,579,269 
- 1,579,269 18 
75,800 10,863,678 
151,165 10,861,226 19 
- 78,372 
- 78,372 20 
450,000 950,000 
927,284 943,443 
- 37,048,061 
- 37,048,061 
404,000 3,701,651 
374,306 3,644,935 
- 2,000,000 
- 2,000,000 
- 13,295,848 21 
- 13,295,848 22 
469,500 5,816,772 
502,799 5,814,424 
- 285,908 
- 285,908 
- 220,594 
- 220,594 
871,926 769,670 
517,163 1,125,300 
320,965 
317,081 
6,035 
144 
440,120 
268,371 
394,132 
403,770 
48,000 
19,411 
535,030 
689,460 
38-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 38-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
21. Tacoma, Puyallup 
River, Wash. 
22. Wenatchee, 
Canyons 1 and 2, 
Wash. 
23. Wynoochee Lake, 
Wash. 
28. Albeni Falls Dam, 
Idaho 
29. Chief Joseph Dam - 
Rufus Woods Lake, 
Wash. 
30. Libby Dam - Lake 
Koocanusa, Mont. 
(Federal Funds) 
(Contrib. Funds) 
Funding 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Costs 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
19,223 
7,281 
-7,965 
12,248 
12,248 
49,700 
27,894 
8,720,100 
8,004,142 
8,807 
52,876 
734,953 
657,431 
-3,977 
362,626 
1,840,347 
1,725,202 
27,139 
39,887 
16,017 
16,017 
85,000 
104,307 
2,400,000 
2,452,459 
275,293 
164,517 
35,000 
36,689 
788,010 
849,268 
394,000 
440,707 
1,947,175 
1,985,339 
17,314 
15,242 
19,486 
19,486 
91,000 
93,499 
587,087 
269,595 
269,027 
28,000 
53,912 
841,336 
823,241 
3,556,000 
3,457,173 
2,126,300 
2,112,620 
2
2! 
2
4! 
41 
69( 
6( 
341 
34, 
20] 
61 
83' 
85f 
22,50( 
22,35 
2,24' 
2,01' 
65,495,600 46,110,000 32,595,000 28,57 
61,643,449 49,265,806 32,790,824 29,18( 
76,515 
67,799 
261,964 
235,707 
63 
64'
3,100 655,119 
4,143 654,090 
- 3,943,853 
- 3,943,853 23 
9,600 163,723 
8,995 163,118 
9,500 275,200 
9,071 274,771 
6,000 23,457,245 
6,890 22,744,021 
9,500 794,388 
7,790 781,334 
1,800 31,747,497 24 
8,632 31,614,302 25 
2,000 9,489,356 
8,228 9,419,857 
0,000 173,149,235 26 
9,215 172,840,658 27 
7,000 24,624,435 
3,155 24,272,590 
- 297,630 
- 297,630 
5,000 431,350,343 28 
6,731 431,088,599 29 
- 17,500 
15,910 30 
5,000 973,479 
7,652 951,158 
38-18

SEATTLE DISTRICT 
TABLE 38-A (Continued) COST AND FINANCIAL STATEMENT 
1. Includes $418,209 for previous projects. Excludes 
$43,000 Coast Guard funds expended. 
2. Includes applicable portion of Reconnaissance and 
Condition Surveys appropriations and costs. 
3. Includes $5,869 for previous projects. 
4. Includes $113,134 for previous projects. Excludes 
$162,000 Navy funds and $6,000 Coast Guard funds expended. 
5. Includes $37,415 for previous projects. 
6. Includes $485,002 for previous projects. 
7. Includes $6,200 Code 710 funds for recreation on completed 
project. 
8. Includes $4,498 Code 710 funds for recreation on completed 
project. 
9. Includes $1,631,195 expended between 1916 and 1936 
on operation and care of works of improvement, under 
provisions of the permanent indefinite appropriation for such 
purposes. 
10. Includes $183,257 for previous projects, and $2,803expended 
for restudy Fiscal Years 1971-1973. 
11. Includes $14,418 for previous projects. 
12. Includes $67,496 for previous project. 
13. Excludes Navy funds expended on dredging river 
channel in 1944; and Coast Guard funds expended for channel 
dredging in 1948 and 1949. 
14. Excludes $1,000 Coast Guard funds expended. 
15. Includes $159,584 for previous projects. 
16. Includes $5,347 for previous projects. 
17. Includes $62,697 value in work contributed by Port of 
Tacoma. 
18. Includes $228,084 for previous projects. Excludes 
$40,000 Coast Guard funds expended. 
19. Includes $309,177 for previous projects. 
20. Includes $6,597 for previous project. 
21. Includes $87,785 Code 710 funds for recreation on completed 
project. 
22. Includes $87,785 Code 710 funds for recreation on completed 
project. 
23. Includes $1,035 Code 710 funds for recreation on completed 
project. 
24. Includes $136,736 Public Works Acceleration Act 
funds and $841,147 Code 710 funds for recreation on completed 
project. 
25. Includes $136,736 Public Works Acceleration Act 
funds and $707,954 Code 710 funds for recreation on completed 
project. 
26. Includes $28,605,000 for 11 additional generator units: 
and $58,000 Public Works Acceleration Act funds and $147,- 
983 Code 710 funds for recreation on completed project. 
27. Includes $28,296,422 for 11 additional generator units: 
and $58,000 Public Works Acceleration Act funds and $147,- 
983 Code 710 funds for recreation on completed project. 
28. Includes $2,105,000 for planning for additional units 
and reregulating dam, and $75,000 for power. 
29. Includes $2,072,200 for planning for additional units 
and reregulating dam, and $74,737 for power. 
30. Excludes $185,349 Federal Aviation Agency funds for 
construction of Kelley Flats airport facility. 
38-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 38-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
ANACORTES HARBOR, WASH. 
(See Section 1 of Text) 
Channel in Capsante Waterway.9 
Mooring basin. 
Mar. 2, 1919 
Sept. 3, 1954 
July 14, 1960, 
as amended 
(Sec. 107)' 
June 25, 1910 
July 3, 1930 
June 20, 1938 
Sept. 3, 1954 
July 14, 1960 
Aug. 13, 1968 
June 3, 1896 
Mar. 2, 1907 
Mar. 2, 1907 
June 25, 1910 
June 25, 1910 
Aug. 8, 1917 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Aug. 30, 1935 
Mar. 2, 1945 
ANACORTES NAVIGATION CHANNEL, WASH. 
(See Section la. of Text) 
Navigation channel. 
EVERETT HARBOR AND SNOHOMISH RIVER, WASH. 
(See Section 2 of Text) 
Training dike 10,500 feet long extending across bar at 
outlet of old river channel. 
Raise 6,000 feet of training dike, extend spur dike, 
widen gap in dike as required, maintain East Waterway 
and channel to gap. 
Abandon project for Snohomish River and provide 
settling basin near 14th Street. 
Spur dike at Preston Point, remove training dike north 
of river outlet, enlarge channel to 14th Street, and 
deepen settling basin. 
Widen channel from settling basin to gap; extend channel 
to head of Steamboat Slough; and a settling basin 
within upper channel reach. 
Raise and extend existing training dike; and construct 
breakwater on westerly and southerly sides of 14th 
Street small-boat basin. 
GRAYS HARBOR AND CHEHALIS RIVER, WASH. 
(See Section 3 of Text) 
South jetty. 
A north jetty 9,000 feet long. 
The 18-foot channel. 
Extend north jetty 7,000 feet; length of south jetty 
fixed at 13,734 feet. 
A 6-foot channel above Cosmopolis. 
Dredging in bar channel 
Dredging in bar channel. 
16-foot channel from Cosmopolis to Montesano. 3 
Reconstruct north and south jetties to an elevation of 
16 feet above mean lower low water. 
Maintain 26-foot channel below Aberdeen (as authorized 
by Public Works Administration Dec. 11, 1933) and 
combining projects for Grays Harbor and bar entrance 
and Grays Harbor, inner portion, and Chehalis River 
under a modified project for Grays Harbor and Chehalis 
River. 
Maintain 30-foot depth in channel from deep water in 
Grays Harbor to Port of Grays Harbor Commission terminal, 
which was deepened from 26 to 30 feet with Navy funds. 
38-20 
H. Doc. 1117, 64th Cong., 
1st Sess. 
S. Doc. 102, 83d Cong., 
2d Sess. 
Detailed Project Report in 
Office, Chief of Engineers 
H. Doc. 1108, 60th Cong., 
2d Sess. 
H. Doc. 377, 71st Cong., 
2d Sess. 
H. Doc. 546, 75th Cong., 
3d Sess. 
H. Doc. 569, 81st Cong., 
2d Sess. 
H. Doc. 348, 86th Cong., 
2d Sess. 
H. Doc. 357, 90th Cong., 
2d Sess. 2 
Annual Report, 1895, 
pp. 3517-3533 
Rivers and Harbors 
Committee Doc. 2, 59th 
Cong., 2d Sess. 
H. Doc. 507, 59th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 29, 
61st Cong., 2d Sess. 
H. Doc. 1125, 60th Cong., 
2d Sess. 
H. Doc. 1729, 64th Cong., 
2d Sess. 
H. Doc. 582, 69th Cong., 
2d Sess. 
H. Doc. 315, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 2, 
74th Cong., 1st Sess. 
H. Doc. 53, 73d Cong., 
1st Sess.; Rivers and 
Harbors Committee Doc. 
2, 74th Cong., 1st Sess. 
Report in Office, Chief 
of Engineers

SEATTLE DISTRICT 
TABLE 38-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 30, 1948 
Sept. 3, 1954 
Sept. 3, 1954 
June 25, 1910 
Mar. 4, 1913 
Aug. 8, 1917 
Sept. 22, 1922 
June 26, 19345 
Aug. 30, 19356 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 19358 
Aug. 26, 1937 
Mar. 2, 1945 
14-foot channel to Bay City; breakwater at Westhaven; 
protection of Point Chehalis; and maintenance of 
Westhaven entrance channel. 4 
Dredging and maintenance of a 30-foot channel and 
turning basin from Aberdeen to Cosmopolis. 
Additional breakwater, 1,400 feet long, at Westhaven 
Cove. 
LAKE WASHINGTON SHIP CANAL, WASH. 
(See Section 4 of Text) 
For a double lock and fixed dam with gated spillway 
and necessary accessory works at entrance to Salmon 
Bay; dredging a channel from locks to deep water in 
Puget Sound, and excavation by local interests of a 
channel from locks into Lake Washington. 
Dredging below locks and revetting canal banks. 
Increased dimensions of channel between Puget Sound and 
locks and a 600-foot extension of lower guide pier. 
Operating and care of locks and dam provided for with 
funds from War Department appropriations for Rivers 
and Ha-bors. 
Enlarge channel between locks and Lake Washington. 
OLYMPIA HARBOR, WASH. (See Section 5 of Text) 
Channel 22 feet deep and 150 feet wide. 
Channels of 26-foot depth on east side of harbor. 
Elimination from project of 12-foot channel on east 
and west sides of harbor, and for a channel 30 feet 
deep and 300 feet wide between Budd Inlet and port 
terminal, with turning basin of same depth. 
Widen outer portion of channel to 500 feet, and 
widen entrance to turning basin. 
Entrance channel 500 feet wide to and including 
a turning basin 3,350 feet long and generally 
960 feet wide, all at a depth of 30 feet at mean 
lower low water.' 
PUGET SOUND AND ITS TRIBUTARY WATERS, WASH. 
(See Section 6 of Text) 
Maintenance of the rivers tributary to Puget Sound by 
snagging and dredging; and removal of floating debris 
from Seattle Harbor. 
QUILLAYUTE RIVER, WASH. (See Section 7 of Text) 
Jetty (5 feet high) on easterly side of mouth, and a 
dike with groins, on westerly side, to stabilize 
entrance. 9 
Maintenance dredging to provide a channel 6 feet deep 
and of suitable width from ocean to within river 
mouth. 
Raising jetty to 15 feet; channel 10 by 100 feet, 
2,000 feet long; moorage basin.o 
SEATTLE HARBOR, WASH. (See Section 8 of Text) 
Maintenance of East and West Waterways 750 feet 
wide and 34 feet deep, and of Duwamish Waterway 
20 feet deep and 150 feet wide as far south as 
Eighth Avenue South Bridge. 
Enlargement of Duwamish Waterway." 
Annual Report for 1893, 
page 34258 
H. Doc. 125, 71st Cong., 
1st Sess. 
H. Doc. 218, 78th Cong., 
1st Sess. 
H. Doc. 579, 81st Cong., 
2d Sess.2 
S. Doc. 313, 65th Cong., 
3d Sess. 
H. Doc. 108, 68th Cong., 
1st Sess., and H. Doc. 
126, 71st Cong., 2nd 
Sess. 2 
38-21 
H. Doc. 635, 80th Cong., 
2d Sess. 
H. Doc. 412, 83d Cong., 
2d Sess. 
H. Doc. 30, 84th Cong., 
1st Sess.2 
H. Doc. 953, 60th Cong., 
1st Sess. 
H. Doc. 800, 64th Cong., 
1st Sess. 
H. Doc. 324, 67th Cong., 
2d Sess. 
H. Doc. 140, 72d Cong., 
1st Sess.2 
H. Doc. 244, 69th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 5, 71st 
Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 21, 
73rd Cong., 2d Sess. 
Rivers and Harbors 
Committee Doc. 75, 
74th Cong., 2d Sess. 
H. Doc. 699, 76th Cong., 
3d Sess.2 
July 13, 1892 
July 3, 1930 
Mar. 2, 1945 
Sept, 3, 1954 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 38-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
July 13, 1892 
Aug. 30, 1935 
Oct. 23, 1962 
Dec. 22, 1944 
as amended 
June 13, 1902 
July 3, 1930 
Aug. 26, 1937 
Aug. 30, 1935 
Sept. 3, 1954 
Oct. 23, 1962 
Mar. 4, 191312 
July 27, 1916 
Aug. 30, 19356 
Aug. 30, 193513 
Mar. 2, 1945 
Sept, 3, 1954 
Mar. 7, 1974 
(P.L. 93-251, 
93rd Cong.) 
May 17, 1950 
Aug. 6, 1958 
(P.L. 85-592) 
Maintenance of East Waterway between 750-foot section 
and Spokane Street, and turning basin at junction of 
East and Duwamish Waterways. 
SWINOMISH CHANNEL, WASH. (See Section 9 of Text) 
Channel 4 feet deep and 100 feet wide, and dike 
construction. 
Enlargement of channel to present project dimensions. 
Removal of navigation hazards at "Hole-in-the-Wall". 
Construction, operation, and maintenance of recreation 
facilities. 
TACOMA HARBOR, WASH. (See Section 10 of Text) 
City Waterway. 
Hylebos Waterway. 
Training walls at mouth of Puyallup River (previously 
authorized by Public Works Administration Sept. 6, 
1933). 
Blair Waterway extension. 
Blair and Hylebos Waterways extension. 
WATERWAY CONNECTING PORT TOWNSEND AND 
OAK BAY, WASH. (See Section 11 of Text) 
Canal 15 feet deep, 75 feet wide on the bottom, and 
about 4,800 feet long; construct jetties to protect 
channel at southern or Oak Bay end, and a bulkhead 
for retention of dredged material. 
WILLAPA RIVER AND HARBOR AND NASELLE 
RIVER, WASH. (See Section 12 of Text) 
Channel 24 feet deep, 200 feet wide, in Willapa River, 
and 150 feet wide in the forks. 
Maintenance of channel over bar to a depth of 26 feet 
and minimum width of 500 feet. 
For cutoff channel at Narrows. 
Channel from deep water in Palix River to Bay Center 
dock. 
Widen Willapa River channel to 360 and 250 feet between 
South Bend and the forks; Tokeland and Nahcotta 
basins; and Naselle River clearance. 
EDIZ HOOK, WASH. (See Section 16 of Text) 
Construction of 10,000 lineal feet of rock revetment, 
together with initial beach replenishment and annual 
nourishment. 
Emergency interim measures necessary to prevent breaching 
of Ediz Hook prior to construction of authorized 
project. 
HOWARD A. HANSON DAM, WASH. (See Section 18 
of Text) 
Eagle Gorge flood control dam on Green River. 
Redesignation of project as Howard A. Hanson Dam. 
H. Doc. 211, 72nd Cong., 
1st Sess.2 
H. Doc. 31, 52d Cong., 
1st Sess. and Annual 
Report, 1892, p. 2752. 
S. Committee Print, 
73d Cong., 1st Sess. 
H. Doc. 499, 87th Cong., 
2d Sess.2 
H. Doc. 76, 56th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Does. 25, 
71st Cong., 2d Sess., 
and 91, 74th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 55, 
72d Cong., 2d Sess. 
H. Doc. 171, 84th Cong. 
2d Sess. 
S. Doc. 101, 87th Cong., 
2d Sess.2 
H. Doc. 625, 62d Cong., 
2d Sess. 
H. Doc. 706, 63d Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 41, 
72d Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 37, 
73d Cong., 2d Sess. 
H. Doc. 481, 76th Cong., 
2d Sess. 
H. Doc. 425, 83d Cong., 
2d Sess.2 
H. Doc. 93-101, 93rd Cong., 
1st Sess. 
H. Doc. 271, 81st Cong., 
1st Sess.2 
38-22

SEATTLE DISTRICT 
TABLE 38-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 22, 1936 
Dec. 22, 1944 
as amended 
June 22, 1936 
June 28, 1938 
June 22, 1936 
Dec. 22, 1944 
as amended 
Oct. 27, 1965 
(Sec. 201) 
Authorized 1970) 14 
Oct. 23, 1962 
Mar. 7, 1974 
(P.L. 93-251) 
Mar. 7, 1974 
(P.L. 93-251) 
May 17, 1950 
Dec. 22, 1944 
as amended 
July 24, 1946 
June 30, 1948 
(P.L. 858, 80th 
Cong., 2d Sess.) 
July 9, 1952 
(P.L. 469, 82d 
Cong., 2d Sess. 
Dec. 22, 1944 
as amended 
May 17, 1950 
Nov. 7, 1966 
(P.L. 89-789) 
Jan. 2, 1968 
(P.L. 90-239) 15 
MUD MOUNTAIN DAM, WASH. (See Section 19 of Text) 
Flood control dam on White River. 
Construction, operation, and maintenance of recreation 
facilities. 
STILLAGUAMISH RIVER, WASH. (See Section 20 
of Text) 
Improvement of flood channel by clearing and bank 
revetment at 26 places; concrete weir at head of 
Cook Slough; and 2 cutoff channels in Cook Slough. 
Maintenance of improvements. 
TACOMA, PUYALLUP RIVER, WASH. (See Section 21 
of Text) 
Channel improvement to protect people and industrial 
section of City of Tacoma. 
Construction, operation, and maintenance of recreation 
facilities. 
WENATCHEE, CANYONS 1 AND 2, WASH. 
(See Section 22 of Text) 
Reinforced concrete channels and appurtenances, 4.6 
miles long, to protect people and City of Wenatchee 
and agricultural land from floods. 
WYNOOCHEE LAKE, WASH. (See Section 23 of Text) 
Dam and reservoir for water supply, flood control, 
irrigation, fish and wildlife, and recreation. 
Transfer to State of Washington as a part of project 
costs $696,000 for construction of fish hatchery 
facilities. 
Amend contract between City of Aberdeen and United 
States for use of storage space, permitting deferral 
of the major portion of the first 10-years payments. 
ALBENI FALLS DAM, IDAHO (See Section 28 of Text) 
Multi-purpose dam with powerhouse. 
Construction, operation, and maintenance of recreation 
facilities. 
CHIEF JOSEPH DAM - RUFUS WOODS LAKE, WASH. 
(See Section 29 of Text) 
Multi-purpose dam and powerhouse on Columbia River at 
Foster Creek. 
Redesignation of the project as Chief Joseph Dam. 
Designation of reservoir as Rufus Woods Lake. 
Construction, operation, and maintenance of recreation 
facilities. 
LIBBY DAM - LAKE KOOCANUSA, MONT. 
(See Section 30 of Text) 
Multi-purpose dam and powerhouse, and reregulating 
facilities. 
School facilities for education of dependents of 
construction personnel, Libby project. 
Airport facility at Kelley Flats, Mont. 
S. Comm. Print, 
Puyallup River, Wash., 
74th Cong., 2d Sess. 
H. Doc. 657, 71st Cong., 
3d Sess.2 
S. Comm. Print, 
Puyallup River, Wash., 
74th Cong., 2d Sess. 2 
H. Doc. 91-3702 
H. Doc. 601, 87th Cong., 
2d Sess.2 
S. Doc. 9, 81st Cong., 
1st Sess. 2 
H. Doc. 693, 79th Cong., 
2d Sess.2 
H. Doc. 531, 81st Cong., 
2d Sess. 2 
38-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 38-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 13, 1968 Design standards for relocation of Montana State 
(P.L. 90-483)16 Highway 37 to be those adopted by State of Montana 
pursuant to provisions of Highway Safety Act of 
1966. 
June 19, 1970 Participation with State of Montana in construction, 
(P.L. 91-282)17 operation and maintenance of fish hatchery facilities. 
Dec. 31, 1970 Designation of lake formed by the waters impounded by 
(P.L. 91-625) Libby Dam as Lake Koocanusa. 
Dec. 31, 1970 Design and construction of sewage collection and sewage 
(P.L. 91-611) treatment facility as part of relocation of municipal 
facilities of Rexford, Montana; and compensation for 
railroad employees suffering long-term economic injury 
through reduction of income as result of the relocation 
of rail transportation facilities due to the 
construction of Libby Dam. 
Mar. 7, 1974 Phase I design memorandum stage for installation of S. Doc. 93-29, 93d Cong., 
(P.L. 93-251) power generating facilities at Libby Reregulating Dam. 1st Sess. 
Mar. 7, 1974 Construction of fish production measures to compensate 
(P.L. 93-251) for fish losses attributed to the project, and for 
acquisition of necessary real estate, construction of 
access roads and utilities (Amends P.L. 91-282 by 
increasing limitation from $750,000 to $4,000,000) 
Mar. 7, 1974 Acquisition of land not to exceed $2,000,000 for 
(P.L. 93-251) prevention of wildlife grazing losses caused by 
the project. 
Mar. 7, 1974 Reimbursement (not to exceed $350,000) to Boundary 
(P.L. 93-251) County, Idaho for reconstruction of Deep Creek 
Bridge made necessary by duration of high flows 
during drawdown operations at Libby Dam. 
Mar. 7, 1974 Compensation, not to exceed $1,500,000, to Drainage 
(P.L. 93-251) Districts and owners of leveed and unleveed lands, 
in Kootenai Flats, Boundary County, Idaho, for 
damages caused by duration of higher flows during 
drawdown operations at Libby Dam. 
1. Authorized by Chief of Engineers Dec. 31, 1974. 
2. Contains latest published map. 
3. Inactive. 
4. A portion deferred. 
5. Permanent Appropriations Repeal Act. 
6. Included in Public Works Administration Program. 
7. Deferred. 
8. Annual Report for 1913 contains latest published map 
(Page 3127). 
9. A portion inactive. 
10. Maintenance of these items, as well as sandspit north of 
James Island, is included in this modification. 
11. Includes settling basin of 100,000 cubic yards capacity 
which has been classified as inactive. 
12. Annual report for 1915 contains latest published map 
(Page 3441). 
13. Included in Emergency Relief Program, May 28, 1935. 
14. Authorized by House of Representatives and Senate 
Public Works Committee resolutions adopted December 15 
and 17, 1970, respectively. 
15. Supplemental Appropriations Act of 1968, Section 
502.
16. Flood Control Act of 1968, Section 212. 
17. River Basin Monetary Authorization and Miscellaneous 
Civil Works Amendments Act of 1970, Section 7. 
38-24

SEATTLE DISTRICT 
TABLE 38-C TOTAL COST OF EXISTING PROJECT 
TO JUNE 30, 1975 
Section Project Funds New Work Maintenance Rehabilitation Total 
2. Everett Harbor Regular $1,357,535 $2,431,702 - $3,789,237 
and Snohomish U.S. Coast Guard 43,000- - 43,000 
River, Wash. Total, U.S. 1,400,535 2,431,702 - 3,832,237 
Contributed 5,618 - - 5,618 
Total, All 1,406,153 2,431,702 3,837,855 
3. Grays Harbor and Regular 4,917,717 33,960,126 4,615,737 43,493,580 
Chehalis River, Public Works - 57,000 - 57,000 
Wash. Public Works 
Acceleration Act - - 111,000 111,000 
Emergency Relief - 409,660 - 409,660 
U.S. Coast Guard 6,000 - - 6,000 
U.S. Navy 162,000 - 162,000 
Total, U.S. 5,085,717 34,426,786 4,726,737 44,239,240 
Contributed 35,834 47,889 83,723 
Total, All 5,121,551 34,474,675 4,726,737 44,322,963 
4. Lake Washington Regular 3,351,277 25,172,998 - 28,524,275 
Ship Canal, Wash. Public Works 192,516 - - 192,516 
Total 3,543,793 25,172,998 - 28,716,791 
6. Puget Sound and Regular 43,337 7,300,057 - 7,343,394 
its Tributary 
Waters, Wash. 
10. Tacoma Harbor, Regular 2,224,307 1,105,427 - 3,329,734 
Wash. Public Works 51,609 - - 51,609 
Total, U.S. 2,275,916 1,105,427 - 3,381,343 
Contributed 559,581 - - 559,581 
Total, All 2,835,497 1,105,427 - 3,940,924 
12. Willapa River and Regular 1,158,871 10,473,516 - 11,632,387 
Harbor and Naselle Public Works - 78,533 - 78,533 
River, Wash. U.S. Coast Guard 40,000 - - 40,000 
Emergency Relief 192,314 - - 192,314 
Total, U.S. 1,391,185 10,552,049 - 11,943,234 
Contributed 71,775 - - 71,775 
Total, All 1,462,960 10,552,049 - 12,015,009 
38-25

TABLE 38-D 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
LAKE WASHINGTON SHIP CANAL, WASH. 
PRINCIPAL FEATURES OF DOUBLE LOCK AND DAM 
(See Section 4 of Text) 
Section Large Lock Small Lock 
Miles above mouth 1-1/4 1-1/4 
Clear width of chamber Feet 80 28 
Maximum available length Feet 760 123 
Lift Feet 26 26 
Depth on upper miter sill' Feet 36 16 
Depth on intermediate miter sill2 Feet 29 - 
Depth on lower miter sill2 Feet 29 16 
Character of foundation Clay Clay 
Kind of dam Fixed dam with Fixed dam with 
gated spillway. gated spillway. 
Type of construction Concrete Concrete 
Year completed 1916 1916 
Cost 3 3 
1. Low water in upper pool. 3. Cost of double lock and dam was $2,224,712 and the 
2. Mean lower low water in Puget Sound. emergency gates, completed in 1923, $174,693. 
TABLE 38-E PROJECT CONDITION SURVEYS 
(See Section 13 of Text) 
Name of Project Date Survey Conducted 
Washington: 
Bellingham Harbor May 1975 
Blaine Harbor June 1975 
Hoquiam River April 1975 
Kingston Harbor March 1975 
Lake Crockett December 1974 
Neah Bay November 1974 
Olympia Harbor July 1974 
Port Angeles Harbor June 1975 
Port Gamble Harbor June 1975 
Port Orchard Bay June 1975 
Port Townsend April 1975 
Shilshole Bay, Seattle March 1975 
38-26

SEATTLE DISTRICT 
TABLE 38-F OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 14 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 1 
Bellingham Harbor, Wash. 2 1970 1,566,840 3 377,539 4 
Bellingham Harbor, Wash. (I&J Street 
Waterway) 2 1966 125,634 2,700 
Blaine Harbor, Wash. 2 1958 346,650 18,448 
Brownsville, Wash. 1972 79,305 - 
Columbia River, Wenatchee to 
Kettle Falls, Wash. 2 1923 274,390 6 7,693 
Edmonds Harbor, Wash. 1966 - 7,176 
Flathead River, Mont. 2 1901 9,811 - 
Hammersley Inlet, Wash. 1950 9,000 20,418 
Hoquiam River, Wash. 2 1950 51,294 12,201 
Kingston Harbor, Wash. 2 1967 262,570 7 13,448 8 
Kootenai River, Idaho and Mont. 2 1933 9,255 5,643 
Lake Crockett, Wash. 2 1971 260,240 244,440 
Mats Mats Bay, Wash. 2 1970 137,679 9 7,093 
Neah Bay, Wash. 2 1968 2,057,266 260,466 
Poison Bay, Flathead Lake, Mont. 2 1918 4,491 259 
Port Angeles Harbor, Wash. 1960 470,873 38,108 
Port Gamble Harbor, Wash. 1953 11,911 10 33,709 
Port Orchard Bay, Wash. 2 1928 42,804 4,122 
Port Townsend, Wash. 1974 480,899 11 41,161 
Sammamish River, Wash. 1972 18,280 5 
Shilshole Bay, Seattle, Wash. 2 1962 2,575,091 17,236 
Skagit River, Wash. 1950 102,330 12 60,265 
Stillaguamish River, Wash. 1946 4,234 13 - 
1. Includes applicable portion of reconnaissance and condition 
survey costs. 
2. Completed. 
3. Includes $56,582 expended for previous project. 
4. Includes $1,092 expended for previous project. 
5. Project deferred pending compliance by sponsor with 
local cooperation requirements. 
6. Includes $8,005 expended for previous project. 
7. Excludes $117,585 contributed funds expended. 
8. Includes $5,000 for mitigation shore damages study 
expended. 
9. Excludes $28,288 contributed funds expended. 
10. Excludes $21,260 contributed funds expended. 
11. Excludes $85,223 contributed funds expended. 
12. Includes $2,500 expended for previous project. 
13. For economic study, only. 
38-27

TABLE 38-G 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 26 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
American Lake, Vicinity of Fort Lewis, 
Wash. 1 2 1957 59,582 3 
Coeur d'Alene, Spokane River, Idaho 2 1942 152,872 
Columbia River Basin, Local Protection 
Projects, Idaho, Mont., and Wash.: 
Clark Fork at Missoula, Mont. 2 1968 377,012 
Entiat River, Wash. 1958 
Lightning Creek, Clark Fork, Idaho 2 1959 42,726 
Methow River, Wash. 1958 - - 
Okanogan River, Wash. 1958 1,100 4 
St. Regis River, Mont. 1958 1,400 4 
Wenatchee River, Wash. 1958 
Yakima River at Ellensburg, Wash. 1970 14,300 4 
Dungeness River, Clallam County, Wash. 1 2 1964 392,106 
Mission Creek at Cashmere, Wash. 1 1955 10,856 4 
Placer Creek, Idaho 1971 
Raymond, Willapa River, Wash. 1950 32,630 4 
St. Maries, St. Joe River, Idaho 2 1942 357,698 
Sammamish River, Wash. 2 1967 2,582,537 5 
Skagit River, Wash. (Avon Bypass) 1968 54,468 4 
Skagit River, Wash. (Levee and Channel 
Improvements) 1967 
Spokane, Spokane River, Wash. 1939 2,944 4 
Startup, Wallace River, Wash. 1 2 1970 271,713 
Upper Puyallup River, Wash. 2 1938 71,495 
Yakima, Yakima River, Wash. 2 1948 381,961 
1. Authorized by Chief of Engineers under authority of 
section 205, Public Law 858, 80th Congress, as amended. 
2. Completed. 
3. Excludes $10,000 contributed funds expended. 
4. Preconstruction planning only. 
5. Excludes $689,523 contributed funds expended. 
38-28

SEATTLE DISTRICT 
TABLE 38-H FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
(See Section 27 of Text) 
Project Federal Cost 
EMERGENCY FLOOD CONTROL ACTIVITIES 
Advance preparation $ 108,424 
Flood emergency operations 246,646 
Repair and restoration: 
Hoquiam River, Wash. 89 
Naches River, Wash. 30,968 
Pend Oreille River, Wash. 1,157 
Pilchuck River, French Slough, Wash. 16,759 
Placer Creek, Idaho 568 
Placer Creek, Wallace, Idaho 12,231 
Rehabilitation Projects (1974 Flood Emergency) 18,264 
St. Joe River, Idaho (Benwah County) 4,896 
Satus Creek, Wash. (Unfavorable Investigation) 3,100 
Similkameen River, Wash. 7,653 
Swinomish Channel, Wash. (Drainage District 19) 2,083 
Yakima River, Wash. 13,743 
EMERGENCY BANK PROTECTION 
Methow River, Wash. (Met 1-74) 1 2,442 
Methow River, Wash. (Met 2-74) 1 4,657 
Methow River, Wash. (Met 3-74) 2 4,539 
Okanogan River, Wash. 1 1,043 
Rock Creek, Granite County, Mont. 3 5,673 
Sauk River, Wash. 20,860 
Wynoochee River, Wash. (County Road 141) 4 2,039 
1. Completed in May 1974. 3. Completed in April 1974. 
2. Completed in June 1974. 4. Completed in February 1974. 
TABLE 38-I OTHER AUTHORIZED MULTIPLE PURPOSE 
POWER PROJECTS 
(See Section 31 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Priest Rapids Dam, Columbia 
River, Wash. 1954 350,000 
1. For partnership planning. Excludes funds expended 
for acquisition of lands under partnership arrangement for 
Priest Rapids and Wanapum Dams, in accordance with 
Public Law 544, 83d Congress. Project constructed by Grant 
County Public Utility District. 
38-29

TABLE 38-J 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
FLOOD PLAIN INFORMATION STUDIES 
COMPLETED DURING FISCAL YEAR 
(See Section 33 of Text) 
DateP 
Location Requesting Agency Completed Cost 
Montana: 
Lolo Creek, Missoula County State of Montana Jun 1975 $10,000 
Water Resource Board 
Washington: 
Chehalis and Skookumchuck State of Washington Aug 1974 10,000 
Rivers near Centralia Dept. of Ecology 
and Chehalis; Lewis County 
Snohomish River, Vicinity Do. Apr 1975 60,000 
of Snohomish to Everett; 
Snohomish County 
Yakima River, Vicinity Do. Jun 1975 93,760 
of Parker to Mabton; 
Yakima County 
38-30 
Fid rla 

WALLA WALLA, WASH., DISTRICT* 
This District consists of all Columbia River 
drainage and tributaries thereto between the 
head of the McNary pool (river mile 345.4) and 
the Umatilla Bridge below McNary Dam, except 
the Yakima River Basin above the Van Giesen 
Street Bridge near Richland, Washington. 
IMPROVEMENTS 
Navigation Page 
1. Other Authorized Navigation 
Projects ..................................... 3..9..-.1 
Flood Control 
2. Blackfoot Reservoir, Idaho ............... 3 9-1 
3. Catherine Creek Lake, Oreg.............39-2 
4. Columbia River Basin, Local 
Flood Protection Projects ................. 39-3 
5. Jackson Hole, Snake River, 
W yo .............................................. 39-3 
6. Lucky Peak Lake, Idaho ................. 3 9-3 
7. Mill Creek Lake, Wash....................39-4 
8. Pullman, Palouse River, Wash.......... 3 9-4 
9. Ririe Lake, Idaho ............................ 3 9-4 
10. Willow Creek Lake, Heppner, 
Oreg............................................... 3 9-5 
11. Zintel Canyon Dam, Wash................ 3 9-5 
12. Inspection of Completed Flood 
Control Projects ............................ 3 9-6 
13. Scheduling Flood Control 
Reservoir Operations ....................... 3 9-6 
14. Other Authorized Flood Control 
Projects .................................... 39-6 
15. Flood Control Work Under 
Special Authorization ...................... 3 9-6 
Multiple-Purpose Projects 
Including Power 
Page 
16. Dworshak Dam and Reservoir, 
Idaho ............................................. 39-6 
17. Ice Harbor Lock and Dam-Lake 
Sacajawea-Wash........................... 3 9-7 
18. Little Goose Lock and Dam- 
Lake Bryan-Wash.......................... 39-8 
19. Lower Granite Lock and Dam, 
W ash.......................................3....... 9-9 
20. Lower Monumental Lock and Dam, 
W ash..............................................39-10 
21. McNary Lock and Dam-Lake 
Wallula-Oreg. & Wash................ 39-10 
22. Snake River Downstream from 
Johnson Bar Landing, Oreg., 
W ash. & Idaho ................................ 39-11 
23. Other Authorized Multiple- 
Purpose Projects ..................... 39-11 
General Investigations 
24. Surveys ............... ...................... 39-11 
25. Collection and Study of 
Basic Data......................................39-11 
26. Research and Development ............ 39-11 
Navigation 
1. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 39-C. 
Flood Control 
2. BLACKFOOT RESERVOIR, IDAHO 
Location. On Blackfoot River in Caribou County, 
Idaho, about 40 miles southeast of City of 
* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
39-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Blackfoot. (See Geological Survey quadrangle 
sheets Paradise Valley, Cranes Flat, Portneuf, 
and Henrys Fork location and surroundings in 
immediate vicinity of project.) 
Existing project. See Table 39-B for authorizing 
legislation. Blackfoot Reservoir is owned and 
operated by Fort Hall Agency of Bureau of Indian 
Affairs, Department of Interior. Main dam, 
which is about 55 feet high above streambed, is a 
rockfill structure with a concrete core. China Hat 
Dam, an earthfill structure, closes an arm of 
reservoir near its upstream end to minimize 
storage loss due to seepage in pervious formation 
of that area. Existing main dam structure includes 
a 3,800-cubic-foot-per-second spillway on 
the right abutment and an outlet tunnel in left 
abutment with a capacity of 2,000 cubic feet per 
second. Reservoir has a usable storage capacity of 
413,000 acre-feet at design maximum water surface 
elevation 6124. However, due to experience 
with seepage losses from southern end of reservoir, 
operating level has been limited to about 
elevation 6120, or about 340,000 acre-feet storage 
capacity. Water stored in reservoir is used to 
irrigate lands in Fort Hall Indian Reservation in 
vicinity of Blackfoot and south. Recommended 
modifications to the project would provide 38,000 
acre-feet additional storage capacity for flood 
control. Modifications would permit operation of 
reservoir for flood control to a maximum water 
surface elevation of 6126. The spillway capacity 
would be increased to 21,700 cubic feet per second 
by lowering crest elevation from 6118.5 to 6112 
and increasing spillway width from 52 feet to 94 
feet. Spillway would be equipped with new gates. 
Outlet works would be modernized and 
rehabilitated for flood control operation. China 
Hat Dam would be raised 10 feet and Idaho State 
Highway No. 34 would be raised in grade for approximately 
one-half mile along with grade raising 
of two existing bridges. Construction to be accomplished 
by the Corps, with continued operation 
of project by Bureau of Indian Affairs. Estimated 
Federal cost of proposed modifications 
(October 1975) is $4,020,000. 
Local cooperation. None required. 
Operations and results during fiscal year. As a 
result of a public meeting held 1 May 1974 and as 
a part of the review procedure for the environmental 
impact statement, the District is 
preparing a supplement to the General Design 
Memorandum that could result in a lower 
operating pool level. Submittal of the final environmental 
impact statement has been delayed 
pending approval of this supplement. 
Condition at end of fiscal,.year. Hydrology 
design memorandum has been approved. The 
general design memorandum has been conditionally 
approved subject to comments of the 
Office of Management and Budget on postauthorization 
changes. The Real Estate Design 
Memorandum was submitted December 1971 
and approved 8 April 1972. The postauthorization 
report was approved by Office of 
Management and Budget 9 January 1973. 
Opposition to the project has been voiced to the 
Idaho Congressional Delegation by owners of 
summer homes adjacent to the reservoir which 
have been or are being constructed below the existing 
authorized reservoir storage elevation. 
3. CATHERINE CREEK LAKE, OREG. 
Location. On Catherine Creek about 8 miles 
above Union, Oreg., in Section 7, Township 5 
South, Range 41 East, Willamette Meridian. 
Existing project. See Table 39-B for authorizing 
legislation. Dam will be an earth embankment 
with an impervious core protected by sand 
and gravel filters. Shell material will consist of 
granular fill covered with rockfill zones on outside 
surfaces. Upstream face will be protected by 
riprap. Height will be about 210 feet above 
streambed and crest length 790 feet. The ungated 
side-channel spillway will have a capacity of 18,- 
500 cubic feet per second. Lake will have a 
storage capacity of 61,000 acre-feet with 52,000 
acre-feet of usable space at elevation 3435. Improvement 
will provide for flood control, irrigation, 
municipal water supply, fish and wildlife, 
and recreation. Estimated costs (October 1975) 
are $28,700,000 Federal and $192,000 non- 
Federal. 
Local cooperation. The Water Supply Act of 
1958 as amended applies. The City of Union, 
Oreg., has provided assurances of willingness and 
ability to meet requirements. Reimbursable costs 
are estimated to be $107,400 for construction and 
$40 annually for operation, maintenance, and 
replacement. 
The Federal Water Project Recreation Act of 
1965 applies. This requirement for local cooperation 
was added after submittal of the survey 
report. Union County Court has submitted a 
letter of assurance of local cooperation on project 
recreation. Reimbursable costs for recreation are 
estimated to be $181,000 for construction and 
$16,100 annually for operation, maintenance, and 
replacement. 
In accordance with reclamation law, local 
irrigation interests will be required to repay portion 
of first costs and annual operation, 
maintenance, and replacement costs of dam and 
lake allocated to the irrigation function, currently 
estimated at $4,722,900 and $27,100, respectively. 
Portion of construction cost beyond ability 
of irrigators to repay will be returned to reclamation 
fund from revenues derived from disposition 
39-2

WALLA WALLA DISTRICT 
of power marketed through the Bonneville Power 
Administration. Irrigation districts are to contract 
for repayment of cost allocated to irrigation. 
Local interests will be required to pay onefourth 
of the separable costs allocated to fish and 
wildlife enhancement, presently estimated at 
$11,000, and will be responsible for average annual 
costs of $2,400. 
Operations and results during fiscal year. Additional 
foundation explorations for the dam and 
highway relocations were accomplished. The 
feature design memorandum for all relocations is 
scheduled for completion in FY 1976. 
Condition at end of fiscal year. Construction 
funds have been appropriated but construction 
has not started due to a suit filed by the local Indians 
for injunction to stop construction. The Indians 
filed suit in the U.S. District Court in 
Portland, Oregon, on 19 December 1974. The 
hearing had not been held by the end of the fiscal 
year. A local committee calling themselves "The 
Committee for Catherine Creek" was formulated 
during the year to oppose the construction of the 
project. This committee, although small, has 
generated much opposition outside of the local 
area. The final environmental impact statement 
was filed with the Council on Environmental 
Quality on 15 January 1975. 
4. COLUMBIA RIVER BASIN, LOCAL 
FLOOD PROTECTION PROJECTS 
Location. Improvements included in this project 
are along Columbia River and its tributaries. 
Existing project. Flood Control Act of 1950 approved 
a general comprehensive plan for Columbia 
River Basin for flood control and other purposes 
based on plans in H. Doc. 531, 81st Cong., 2d 
Sess. and authorized $75 million to be appropriated 
for partial accomplishment of certain 
projects. Of that authorization, not to exceed $15 
million was allotted for construction of local flood 
protection works throughout Columbia River 
Basin, subject to conditions that all work undertaken 
pursuant to authorization should be 
economically justified prior to construction, and 
local cooperation specified in 1936 Flood Control 
Act, as amended, should be required. (See Tables 
39-B and 39-D for projects in Walla Walla District.) 
Local cooperation. Section 3 of the Flood Control 
Act approved June 22, 1936, as amended, 
applies to all the flood control projects. 
Operations and results during fiscal year. 
Restudy reports are being prepared for possible 
improvements along the Weiser River and in 
Boise Valley. The report for Weiser River covers 
the proposed development in the Weiser, Midvale, 
and Cambridge areas. The report for Boise 
Valley includes proposed development along 
Boise River in Ada County. 
Condition at end of fiscal year. The restudy 
reports on Weiser and Boise Rivers are scheduled 
for completion in fiscal year 1976. 
5. JACKSON HOLE, SNAKE 
RIVER, WYO. 
Location. On both banks of Snake River near 
Wilson, Wyo. 
Existing project. See Table 39-B for authorizing 
legislation. A levee with full riprap protection 
on right bank, extending from J. Y. Ranch, which 
is 10 miles upstream from Jackson-Wilson 
Highway Bridge, to 3.5 miles below same 
bridge-a total length of 13.5 miles. Also provides 
a levee with full riprap protection along left bank, 
extending from north line of Lucas Ranch, which 
is 10 miles upstream from Jackson-Wilson 
Highway Bridge, to 5 miles downstream and 
extending 1.5 miles immediately upstream from 
Jackson-Wilson Highway Bridge to 3.5 miles 
below bridge for a total length of 10 miles. 
Federal cost of completed project was $2,232,681 
and $18,500 non-Federal cost consisting of rightsof-
way furnished by sponsor. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. The 
existing levee system is being analyzed to determine 
what modifications may be warranted or 
necessary to maintain the integrity of the system, 
reduce operation and maintenance costs, and 
reduce future emergency repairs. This study is 
scheduled for completion in FY 1976. Expenditures 
for FY 1975 total $51,850. 
Condition at end of fiscal year. Construction 
began November 1957 and was completed May 
1964. Design flood flows were experienced during 
spring of 1965. Direct lateral flow of the river 
attacked the levee in three separate locations, requiring 
emergency repairs to avoid an avulsion. 
Expenditures for emergency repair and ordinary 
operation and maintenance have continued to be 
excessive. 
6. LUCKY PEAK LAKE, IDAHO 
Location. On Boise River in southwestern Idaho 
about 10 miles southeast of City of Boise, and 
about 12 miles downstream from Arrowrock 
Reservoir. 
Existing project. See Table 39-B for authorizing 
legislation. A rolled-earthfill dam about 250 
feet high above streambed and 1,700 feet long at 
39-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
crest, with a lake providing a total storage at upper 
operating lake level of 306,000 acre-feet. For 
further details see page 2000 of Annual Report 
for 1962. Federal cost of completed project was 
$19,081,250. Expenditures on recreation 
facilities for completed project have been $295,- 
950, raising total project cost to $19,377,200. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: None during fiscal year 1975. 
Operation and maintenance: Normal operation 
for flood control and irrigation continued. A 
draft Environmental Impact Statement was filed 
with the Council on Environmental Quality. 
Condition at end of fiscal year. Construction of 
existing project was initiated November 1949 
and completed June 1961. More than $34,000,000 
in potential flood damages have been prevented 
by the project since 1961. 
7. MILL CREEK LAKE, WASH. 
Location. In and upstream from Walla Walla, 
Wash., on Mill Creek, a tributary of Walla Walla 
River. 
Existing project. See Table 39-B for authorizing 
legislation. Off-stream storage dam about 145 
feet high and 3,200 feet long at the crest, outlet 
works, diversion works, and division structures. 
Channel through City of Walla Walla was added 
to project in 1941. For further details see page 
2005 of Annual Report for 1962. Federal cost of 
original project was $2,162,155. Adding recreation 
facilities has thus far increased project costs 
by $68,446 to $2,230,601. Not included in that cost 
is $80,000 contributed by local interests toward 
construction of the channel through Walla Walla. 
Local cooperation. Fully complied with. For 
details see page 2006 of Annual Report for 1962. 
Operations and results during fiscal year. Ordinary 
general maintenance by Government 
forces continued, which included routine regulation 
of lake and care of recreation area. A draft 
Environmental Impact Statement was filed with 
the Council on Environmental Quality. 
Condition at end of fiscal year. Construction of 
dam and appurtenant works was completed in 
1942. Paving of channel through City of Walla 
Walla was completed in 1948. Park and recreation 
facilities were opened to public July 1, 1964. 
A design memorandum for the rehabilitation of 
reservoir outlet canal to Mill Creek was submitted 
to higher authority June 1973. About $3,- 
280,000 in potential flood damages have been 
prevented by the combined storage and channel 
operation since 1942. 
8. PULLMAN, PALOUSE 
RIVER, WASH. 
Location. On South Fork Palouse River and 
Missouri Flat Creek at Pullman in eastern 
Washington. 
Existing project. See Table 39-B for authorizing 
legislation. Provides for flood control at 
Pullman, Wash., by channel rectification and intermittent 
levee construction along 1.36 miles of 
South Fork Palouse River and 0.42 mile of Missouri 
Flat Creek. Estimated Federal cost of project 
is $6,060,000 at October 1975 price levels. Estimated 
non-Federal costs are $620,000 for 
rights-of-way and street, railroad, and bridge 
modifications. 
Local cooperation. In addition to usual requirements, 
local interests were to make street, 
railroad and bridge modifications for construction 
of project. Local interests stated their inability 
to meet those requirements, and the project 
was classified inactive in 1964 and reclassified to 
deferred category June 1969. 
Operations and results during fiscal year. A 
restudy to determine if an economically justified 
plan of improvement could be developed that 
would be generally acceptable to the local people 
and within the authorized project scope was completed. 
A report recommending reclassification 
to active status was submitted to OCE in FY 1975. 
In a related study, the Corps of Engineers Institute 
for Water Resources used the Pullman 
area to test methods for flood plain management. 
That study was published by IWR in FY 1975. 
Condition at end of fiscal year. Restudy report 
is being reviewed by OCE. 
9. RIRIE LAKE, IDAHO 
Location. On Willow Creek, a tributary of 
Snake River, in Bonneville County, Idaho. 
Proposed channel improvement extends from 
junction of Sand and Willow Creeks to a point on 
Snake River about 4 miles upstream from City of 
Idaho Falls, Idaho. (See Geological Survey 
quadrangle map, Ucon, Idaho.) Damsite is about 
5 miles below confluence of Willow Creek and 
Meadow Creek and about 15 miles northeast of 
City of Idaho Falls, Idaho. (See Geological Survey 
quadrangle map, Poplar, Idaho.) 
Existing project. See Table 39-B for authorizing 
legislation. Provides for a rockfill dam about 
840 feet long at the crest and about 184 feet high 
above streambed, and downstream channel construction. 
Spillway will have a concrete-lined 
channel in right abutment. Outlet works will 
utilize a reinforced concrete conduit leading from 
an intake tower upstream to a stilling basin 
downstream at the toe of left abutment. Lake will 
39-4

WALLA WALLA DISTRICT 
have gross storage capacity of 100,000 acre-feet; 
90,000 acre-feet of active space for flood control, 
irrigation, and recreation and 10,000 acre-feet of 
space for sediment storage and conservation. 
Floodway channel will be about 8.0 miles long 
with a capacity of 900 cubic feet per second. 
Authorization specified that the project shall be 
constructed by the Corps of Engineers and 
operated and maintained by the Bureau of 
Reclamation. Estimated Federal cost of new 
work (October 1975) is $36,530,000 including 
$30,000 for value of public-owned lands. 
Local cooperation. Fully complied with. 
Operations and results duritg fiscal year. A 
master plan was prepared by the Bureau of 
Reclamation and has been approved. Stream. 
diversion began July 1973. Outlet channel contract 
awarded for $5,147,814. A Project Transfer 
Agreement was sent to the Bureau of Reclamation 
for their consideration. Project Fish & 
Wildlife Mitigation Agreement was sent to concerned 
agencies for review. Combination of a 
strike by the labor force, bad weather, and unanticipated 
poor foundation conditions has delayed 
project completion until FY 1977. Main dam construction 
is about 94 percent complete. 
Condition at end of fiscal year. Construction 
began June 1967. Approximately 97 percent of 
necessary real estate has been acquired. Entire 
project is about 68 percent complete. The final 
Environmental Impact Statement was filed with 
the Council on Environmental Quality February 
13, 1973. 
10. WILLOW CREEK LAKE, 
HEPPNER, OREG. 
Location. On Willow Creek just upstream from 
Heppner and just downstream from junction of 
Balm Fork and Willow Creek in Section 35, 
Township 2 South, Range 26 East, Willamette 
Meridian. 
Existing project. See Table 39-B for authorizing 
legislation. Project will provide flood protection 
to the City of Heppner and downstream area 
by controlling runoff from a drainage area of 96 
square miles. The dam will be an earth and 
rockfill structure 149 feet high at crest elevation 
2130. Ancillary features include an ungated sidechannel 
spillway with capacity of 88,000 cfs and 
an outlet works with capacity of 500 cfs. The outlet 
works will be uncontrolled except for 
provisions to release lake inflows during periods 
of low flow. Limited recreational facilities will be 
provided. Gross storage capacity of the project 
will be 11,500 acre-feet, consisting of 9,500 acrefeet 
for exclusive flood control and 2,000 acre-feet 
for fish, wildlife, recreation, sediment accumulation, 
and esthetics. Estimated Federal project 
cost (July 1974) is $14,700,000. 
Local cooperation. Local interests will not be required 
to share in construction costs, but will be 
responsible for administering project lands and 
water areas for recreation enhancement; paying, 
contributing in kind, or repaying (w 
through user fees) with interest one-half of the 
separable costs allocated to recreation enhancement; 
bearing all costs of operation, maintenance, 
and replacement of the recreation facilities; and 
establishing a resident fishery in the lake. 
Operations and results during fiscal year. A 
reauthorization bill sponsored by the Oregon 
delegation was passed by the U.S. Congress. The 
bill was vetoed by the President on 18 December 
1974 because of economic reasons. Work on plans, 
specifications, surveys, and explorations for the 
damsite and relocations was suspended as a result 
of the veto. 
Condition at end of fiscal year. Project scope 
has changed since authorization; irrigation has 
been deferred to some future date, municipal and 
industrial water supply and water quality control 
have been dropped, and recreation has been 
reduced in scope. A reevaluation of project 
economics, in accordance with ER 1105-2-351, 
will be required before reauthorization 
procedures can be resumed. 
11. ZINTEL CANYON DAM, WASH. 
Location. In Zintel Canyon, 2.1 miles southwest 
of Kennewick, Wash., in Section 16, Township 8 
North, Range 29 East, Willamette Meridian. 
Existing project. See Table 39-B for authorizing 
legislation. Main dam, 119 feet high above 
streambed and 555 feet long at the crest, will be 
primarily of rock fill, with an impervious core 
protected both upstream and downstream by a 
sandy gravel filter zone. A dike will extend from 
near the left abutment of the main dam for 1,480 
feet across a saddle in the left bank; it will have a 
top width of 20 feet and a maximum height of 29 
feet, and will consist mostly of a homogeneous section 
of sandy silt. The spillway will be an ungated 
160-foot wide channel cut through rock in the 
right abutment; maximum spillway discharge 
will be 32,300 cubic feet per second. The outlet 
will consist of a 48-inch conduit through the dam 
with a fixed orifice at the intake sized to pass a 
maximum flow of 60 cfs. A supplemental gated 
opening will permit increased releases up to 165 
cfs under maximum streamflow conditions. 
Downstream channel will consist of 12,000 feet of 
unimproved natural channel between the damsite 
and a conduit intake structure, 4,195 feet of 
buried conduit, and an improved open channel 
39-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
1,205 feet long. Project will provide flood control 
for the City of Kennewick, Wash. Storage space 
behind the dam will be drained completely when 
not needed. 
Project adopted by resolution of House Committee 
on Public Works December 15, 1970 and 
by resolution of Senate Committee on Public 
Works December 17, 1970 under authority of Section 
201 of Flood Control Act of 1965 (P.L. 298, 
89th Cong.). Estimated Federal cost (October 
1975) is $3,800,000. Estimated non-Federal cost 
for land and relocations is $422,000. 
The final Environmental Impact Statement 
was filed with the Council on Environmental 
Quality 8 January 1975. 
Local cooperation. City of Kennewick has 
provided assurances of willingness and ability to 
meet requirements. 
Operations and results during fiscal year. Postauthorization 
change report was submitted 
December 1973. Hydrology and general design 
memorandums were approved April 1974. Study 
underway for alternative optimum gravity dam 
using cement-enriched natural soils. 
Condition at end of fiscal year. Preconstruction 
planning is nearly complete. 
12. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Federal law requires local interests to maintain 
and operate completed local protection projects 
in accordance with regulations prescribed by 
Secretary of Army. Inspections were made to 
determine extent of compliance and to advise 
local interests as necessary of measures required 
to correct deficiencies. See Table 39-E for inspections 
made during fiscal year. 
Fiscal year costs were $21,000. Total costs to 
June 30, 1975 have been $221,678. 
13. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Functional regulation of non-Corps projects 
was accomplished under several authorities. 
Regulation of Palisades, Little Wood, and Anderson 
Ranch Reservoirs in Idaho, and Bully Creek, 
Warm Springs, Agency Valley, and Mason 
Reservoirs in Oregon, was accomplished as 
authorized under section 7, Flood Control Act of 
1944, and coordinated with the Bureau of 
Reclamation. 
Flood control operations at Jackson Lake, 
Arrowrock Reservoir, and Lake Lowell were in 
accordance with formal agreements with the 
Bureau. Regulation of American Falls, Owyhee, 
Magic, Mackay, Cascade, and Deadwood Reservoirs, 
Idaho, for flood control was accomplished 
under informal agreements. Brownlee, Oxbow, 
and Hells Canyon Reservoirs provided flood control 
regulation in accordance with provisions of 
the Federal Power Commission license to Idaho 
Power Company. 
Fiscal year costs were $21,000. 
14. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 39-F. 
15. FLOOD CONTROL WORKS UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
P.L. 858, 80th Cong., as amended (preauthorization). 
See Table 39-G. 
Emergency flood control activities-repair and 
flood fighting and rescue work (P.L. 99, 84th 
Cong., and antecedent legislation). Federal costs 
for fiscal year were $20,565 for advance preparation, 
$182,485 for flood emergency operations, 
and $304,904 for repair and restoration. 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (sec. 208, 
1954 Flood Control Act, P.L. 780, 83d Cong.). 
Federal costs for fiscal year for snagging and 
clearing were $58,998. 
Multiple-Purpose Projects 
Including Power 
16. DWORSHAK DAM AND 
RESERVOIR, IDAHO 
Location. Dam is on North Fork Clearwater 
River 1.9 miles above its junction with 
Clearwater River, near Orofino, Idaho, and about 
35 miles east of Lewiston, Idaho. 
Existing project. See Table 39-B for authorizing 
legislation. A straight concrete gravity dam 
about 717 feet in maximum structural height 
above foundation and 3,300 feet long at crest 
elevation 1613. The reservoir has a gross storage 
capacity of 3,453,000 acre-feet, of which 2,000,000 
acre-feet are effective for both local and regional 
flood control, and for at-site and downstream 
power generation. In addition, the reservoir, 
extending 53 miles into a rugged and relatively 
inaccessible timberland, provides important 
transportation savings in connection with 
movements of marketable logs and affords substantial 
recreational benefits. Powerhouse includes 
two 90,000 and one 220,000 kilowatt 
39-6

WALLA WALLA DISTRICT 
generating units, with provisions for three additional 
220,000 kilowatt units for an ultimate installed 
capacity of 1,060,000 kilowatts. Principal 
project data are set forth in Table 39-H. 
Fish passage at Dworshak Dam is not feasible, 
and a hatchery has been built below the dam to 
assure continuance of fish runs. The reservoir 
area has been habitat for elk, deer, and other 
wildlife. Project plans include acquisition of land 
outside reservoir limits to mitigate losses of big 
game winter browse areas inundated by reservoir. 
Estimated total cost for new work (October 
1975) is $314,805,000 consisting of $312,000,000 
for construction, $2,740,000 for value of publicdomain 
lands, and $65,000 for deferred construction 
on highway district roads following project 
completion. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Main contract for construction of dam and 
other features is complete. Construction was completed 
on a multi-level power intake structure on 
upstream face of dam so that natural river water 
temperatures downstream can be duplicated to 
assure continuance of existing fish runs. 
Construction continues on the main dam 
spillway repairs and Dent recreation area. Construction 
of powerplant is complete. Reservoir 
clearing continues and work continued on 
development of recreation areas. Area schools, 
impacted by students from the project, received 
Federal aid under P.L. 90-483. A draft Environmental 
Impact Statement was filed with the 
Council on Environmental Quality. 
Operation and maintenance: Deficiencies in 
power generating units, causing reduction in 
capacity due to overheating are to be corrected by 
fiscal year 1976. The contract for debris clearing 
is complete, but debris left stranded due to a fluctuating 
and falling lake level refloated at the head 
and in the spring curtailing the use of recreation 
facilities and limiting lake use to the lower end. 
Logging activities in tributaries caused turbidity 
problems which reduced fish food production and 
fish population. The fish hatchery captured 1,560 
adult steelhead which produced 5,562,000 eggs, 
4,000,000 fry, and 1,750,000 smolts. Fish releases 
into the reservoir totaled 111,000 cutthroat, 548,- 
000 rainbow, 100,000 bass, 3,085,000 kokanee, 
and 123,000 dolly varden. A total of 1.70 billion 
kilowatt hours of electric energy was delivered to 
Bonneville Power Administration, the marketing 
agency. 
Condition at end of fiscal year. Construction of 
the project started April 1963 and is estimated to 
be 93 percent complete; it became operational for 
flood control October 1971 and has prevented 
about $727,000 in potential flood damages 
downstream since then. Log handling facilities 
have been completed. All project lands have been 
acquired except those required to replace the loss 
of wildlife browse areas from inundation by 
reservoir. Relocations are estimated to be 100 
percent complete; dam 100 percent; fish and 
wildlife facilities 92 percent; powerplant 100 percent; 
reservoir clearing 86 percent; and recreation 
facilities 43 percent. 
Power generating unit No. 1, 90,000-kw 
capacity, was put in service March 1,1973; unit 2, 
also 90,000-kw capacity, began producing April 
6, 1973; unit 3, 220,000-kw capacity, went on the 
line April 20, 1973. 
Eighty mini-recreation sites have been established 
along the reservoir shoreline. Each site 
includes at least a picnic table, garbage can, U.S. 
Forest Service-type fireplace, and chemical 
toilet. Some of the sites have several picnic tables. 
Power generation through June 1975 has been 
3.70 billion kilowatt hours, representing a gross 
income of $22.0 million to the U.S. Treasury from 
sale of power by Bonneville Power Administration. 
17. ICE HARBOR LOCK AND 
DAM-LAKE SACAJAWEA, WASH. 
Location. On Snake River, 9.7 miles above river 
mouth at head of Lake Wallula and 12 miles east 
of Pasco, Wash. 
Existing project. See Table 39-B for authorizing 
legislation. A dam, powerplant, navigation 
lock, fish ladders, appurtenant facilities, and 
relocation of railroads. Project provides for 
navigation, hydroelectric power generation, and 
incidental irrigation. Dam has normal operating 
range between elevations 440 and 437 mean sea 
level. The lake extends upstream about 31.9 
miles, providing slack water to Lower Monumental 
Lock and Dam. Structure is about 2,790 feet 
long and about 130 feet high above streambed. 
Beginning at south end, project consists of a concrete 
nonoverflow section, concrete powerhouse, 
spillway dam, concrete nonoverflow section, 
navigation lock, and an earth and rockfill embankment 
at north abutment. Fish passing 
facilities, including two ladders, are provided. 
Powerplant now has three 90,000-kilowatt units, 
and three 111,000-kilowatt units are being installed. 
Spillway dam is 610 feet long, and 
overflow crest at elevation 391 mean sea level is 
surmounted by 10 radial gates, 50 feet wide by 51 
feet high, which provide capacity to pass a design 
flood of 850,000 cubic feet per second. Deck is at 
39-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
elevation 453 mean sea level and provides a service 
road and track for a gantry crane. Navigation 
lock is single-lift type with clear plan dimensions 
of 86 by 665 feet and 15 feet minimum depth 
over the sills. A navigation channel 250 feet wide 
and 15 feet deep is provided from mouth of Snake 
River to dam. Principal project data are set forth 
in Table 39-H. 
Estimated cost for new work (October 1975) is 
$169,336,800 consisting of $129,600,000 for the 
completed project, $37,900,000 for power units 4 
through 6, $87,000 for U.S. Coast Guard navigation 
aids, $22,300 for value of public-domain 
lands, $1,645,000 for recreational facilities, and a 
non-Federal contribution of $82,500 toward an 
artificial fish spawning channel. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: Work is continuing on contracts for turbines, 
generators, transformers, and governors 
for power generating units 4 through 6. An improved 
irrigation system, a group shelter and 
modified protection for the swimming area were 
added at Charbonneau Park and an additional 30 
campsites and new well were added at Fishhook 
Park. 
Operation and Maintenance. Normal operation 
and maintenance of navigation lock and 
powerplant continued, and 3.14 billion kilowatt 
hours of electric energy were delivered to 
Bonneville Power Administration, the marketing 
agency. A total of 1,073,443 tons of cargo passed 
through navigation lock during calendar year 
1974. 
Condition at end of fiscal year. Construction 
started December 1955 and the project was placed 
in useful operation January 1962. Installation 
of power units 4 through 6 is 85 percent complete. 
Modifications to the fish facilities are 16 percent 
complete. 
An Environmental Impact Statement concerning 
power units 4 through 6 was filed with the 
Council on Environmental Quality August 1971. 
Power generation through June 1975 has been 
28.1 billion kilowatt hours, representing a gross 
income of $42.7 million to the U.S. Treasury from 
sale of power by Bonneville Power Administration. 
18. LITTLE GOOSE LOCK AND 
DAM-LAKE BRYAN-WASH. 
Location. Dam is 70.3 miles above mouth of 
Snake River at head of Lower Monumental Lake, 
about 40 airline miles northerly of Walla Walla, 
Wash., and 50 miles westerly of Lewiston, Idaho. 
Existing project. See Table 39-B for authorizing 
legislation. A dam, powerplant, navigation 
lock, fish ladder, and appurtenant facilities. Improvements 
provide navigation, hydroelectric 
power generation, recreation, and incidental 
irrigation. Dam has a normal operating range 
between elevations 638 and 633 mean sea level. 
Lake Bryan extends upstream about 37.2 miles 
and provides slack water to Lower Granite Lock 
and Dam. Dam structure is 2,670 feet long and 
about 160 feet high above streambed and consists 
of a powerhouse, spillway dam, navigation lock, 
and necessary nonoverflow sections. Fish passing 
facilities include one ladder with entrances on 
both shores with a fish channel through spillway 
which connects to powerhouse fish collection 
system and south shore ladder. Powerhouse now 
has three 135,000-kilowatt generating units. The 
contract has been awarded for three additional 
135,000-kilowatt units for an ultimate capacity of 
810,000 kilowatts. Spillway dam can pass a 
design flood of 850,000 cubic feet per second. 
Navigation lock is single-lift type with clear plan 
dimensions of 86 by 668 feet and a minimum 
depth of 15 feet over the sills. Relocations along 
the lake include 32 miles of Camas Prairie 
Railroad, 5.8 miles of county roads, 2.2 miles of 
state highways, and Central Ferry bridge. Principal 
project data are set forth in Table 39-H. 
Estimated cost for new work (October 1975) is 
$219,189,000 consisting of $160,700,000 for the 
completed project, $58,100,000 for power units 4 
through 6, $87,000 for U.S. Coast Guard navigation 
aids, and $302,000 for value of publicly owned 
land. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Installation of traveling fish screens was completed 
in units 1, 2, and 3. The contract has been 
awarded for installation of the traveling fish 
screens in units 4, 5, and 6. Additions and 
revisions were completed to the domestic water 
system. Construction of recreation facilities and 
public use areas along Lake Bryan were completed. 
A draft Environmental Impact Statement 
was filed with the Council on Environmental 
Quality. 
Operations and maintenance: A total of 2.71 
billion kilowatt hours of electric energy was 
delivered to Bonneville Power Administration, 
the marketing agency. A total of 755,877 tons of 
cargo passed through the navigation lock during 
calendar year 1974. 
Condition at end of fiscal year. Construction 
began June 1963 and the project was opened to 
navigation May 1970. Recreational facilities 
along Lake Bryan are 100 percent complete, and 
the entire project is about 99 percent complete. 
Remaining items of work consist of providing 
landscaping and visitor facilities at the dam, 
39-8

WALLA WALLA DISTRICT 
modifying the fish facilities, and installing power 
generating units 4 through 6. 
Power generation through June 1975 has been 
13.0 billion kilowatt hours, representing a gross 
income of $18.4 million to the U.S. Treasury from 
sale of power by Bonneville Power Administration. 
19. LOWER GRANITE LOCK 
AND DAM, WASH. 
Location. At river mile 107.5 on Snake River at 
head of Lake Bryan and about 33 miles 
downstream from Lewiston, Idaho. 
Existing project. See Table 39-B for authorizing 
legislation. Provides for a dam, powerplant, 
navigation lock, fish ladder, and appurtenant 
facilities, and requires about 8 miles of 
backwater levees along Snake and Clearwater 
Rivers at Lewiston, Idaho. Benefits afforded by 
project include slack-water navigation, power 
generation, recreation, and incidental irrigation. 
Water surface at the dam varies between 
elevations 738 and 724 to maintain a normal 
operating range between elevations 738 and 733 
in the Lewiston, Idaho-Clarkston, Wash., area. 
Dam structure is about 3,200 feet long and about 
146 feet high above streambed. Powerhouse now 
has three 135,000-kilowatt units and construction 
is underway for three additional similar units. 
Spillway has a capacity for a design flood of 850,- 
000 cubic feet per second. Navigation lock is a 
single-lift type (105 feet maximum) with clear 
plan dimensions of 86 by 674 feet and a minimum 
depth of 15 feet over the sills. Principal project 
data are set forth in Table 39-H. 
Estimated cost for new work (October 1975) is 
$362,237,000 consisting of $310,000,000 for the 
initial installation, $52,100,000 for power units 4 
through 6, $135,000 for U.S. Coast Guard navigation 
aids, and $2,000 for value of publicly owned 
lands. 
Local cooperation. None required. 
Operations and results during fiscal year. Additional 
units concrete placement is continuing. A 
fingerling bypass was installed in the 
powerhouse. Generators and turbines were installed 
in powerhouse bays 1, 2, and 3. The north 
shore embankment construction was completed. 
All relocations work was essentially completed. 
Raising and modification of the CPRR Bridge 
over the Clearwater River at Lewiston was finished. 
Backwater levees in Lewiston are completed. 
Design for levee beautification, remaining 
recreation facilities, and public use areas along 
the lake is nearly complete. 
Operation and maintenance. A total of 0.45 
billion kilowatt hours of electric energy were 
delivered to Bonneville Power Administration, 
the marketing agency. 
Condition at end of fiscal year. Construction 
started July 1965 and is about 86 percent complete. 
Acquisition of lands is estimated to be 95 
percent complete. Lake was filled 15 February 
1975 and the first power generating unit went on 
the line 15 April 1975. An Environmental Impact 
Statement was filed with the Council on Environmental 
Quality November 1971. 
Construction completion percentages 
are: relocations 86; lake area 95; dam 95; navigation 
lock 100; fish facilities 72; powerplant 91; 
recreation facilities 36; and backwater levees 100. 
Power generation through June 1975 has been 
0.45 billion kilowatt hours, representing a gross 
income of $0.5 million to the U.S. Treasury from 
sale of power by Bonneville Power Administration. 
The Association of Northwest Steelheaderb and 
seven other environmental organizations in 
March 1970 sued to stop construction of Lower 
Granite Lock and Iam and to preserve as a 
natural river the reach of river the impoundment 
would occupy. The Department of Fisheries and 
the Department of Game of the State of 
Washington joined the suit as plaintiffs to require 
the Corps to consult directly with them on impacts 
of water resource development on wildlife, 
to pay them for their services, and to require the 
Corps to submit their comments or reports to Congress 
but not to stop the dams under construction 
or modification of existing dams. Motions were 
heard at Spokane, Washington, on 12 November 
1971 by U.S. Judge William N. Goodwin. On 14 
December 1971 he filed a Memorandum of Opinion 
concluding that the Court lacked jurisdiction 
and the action of the plaintiffs was dismissed. 
Notice of appeal to the U.S. Circuit Court of 
Appeals at San Francisco was filed in January 
1972. Appellants Briefs were filed 24 April 1972. 
The Government's reply Brief was filed in May 
1972. Hearings were held on 13 June 1973 at San 
Francisco and on 21 September 1973 the District 
Court opinion was reversed and remanded to the 
District Court with instructions to the District 
Court that the trial court should determine 
whether each point for relief requested by plaintiffs 
would constitute such an intolerable burden 
to Governmental functions when weighed against 
private harm that dismissal of each point is requested. 
Pre-trial hearing was held 20 May 1974 
at which time the plaintiffs were required to file a 
restatement of their contentions but no definite 
time was set for this file to be submitted. The 
plaintiffs filed amended contentions on 16 June 
1975 and 31 July 1975. The Government's reply 
thereto was due 16 September 1975, however, the 
39-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
U.S. Attorney obtained an extension and the 
reply was filed on 1 October 1975. 
20. LOWER MONUMENTAL LOCK 
AND DAM, WASH. 
Location. On Snake River at head of Lake Sacajawea, 
about 45 miles northeast of Pasco, Wash., 
and 41.6 miles above river mouth. 
Existing project. See Table 39-B for authorizing 
legislation. A dam, powerplant, fish ladders, 
navigation lock, appurtenant facilities, and 
relocation of railroads and highways. Dam has 
normal operating range between elevations 540 
and 537. The Lake extends about 29 miles upstream 
to Little Goose Lock and Dam. The Dam is 
concrete gravity with earthfill and rockfill 
abutments, is 3,800 feet long including 
abutments, spillway, navigation lock, and 
powerhouse, and is about 135 feet high above 
streambed. There are two fish ladders, one at 
each end of the dam. Powerhouse has three 
135,000-kilowatt units and a contract has been 
awarded for installation of three additional units 
of the same size for an ultimate total capacity of 
810,000 kilowatts. Spillway is 508 feet long, and 
overflow crest at elevation 483 feet above mean 
sea level is surmounted by 8 radial gates, each 50 
feet wide and 61 feet high. Deck is at elevation 553 
feet and provides a service road and track for a 
gantry crane. Navigation lock is single-lift type, 
with lock chamber 86 by 675 feet and minimum 
depth of 15 feet over the sills. Principal project 
data are set forth in Table 39-H. 
Estimated cost for new work (October 1975) is 
$241,287,000 consisting of $185,400,000 for the 
completed project, $55,800,000 for power units 4 
through 6, and $87,000 for U.S. Coast Guard 
navigation aids. 
Local cooperation. None required. 
Operations and results during fiscal year. Flip 
lips have been completed in bays 2 through 7. The 
landscaping and visitors facilities are complete. 
Modifications to the domestic water supply 
system are underway. 
Operation and maintenance: Normal operation 
and maintenance continued. A total of 2.66 
billion kilowatt hours of electric energy was 
delivered to Bonneville Power Administration, 
the marketing agency. Cargoes totaling 875,474 
tons passed through navigation lock during 
calendar year 1974. 
Condition at end of fiscal year. Construction 
began June 1961, and the project was opened to 
navigation April 1969. Deferred construction on 
the Union Pacific Railroad is nearly complete. 
The entire project is about 99 percent complete. 
Power generation through June 1975 has been 
16.0 billion kilowatt hours, representing a gross 
income of $26.0 million to the U.S.Treasury from 
sale of power by Bonneville Power Administration. 
21. McNARY LOCK AND DAM-LAKE 
WALLULA, OREG.-WASH. 
Location. On Columbia River 292 miles above 
mouth, near Umatilla, Oreg., and 3 miles above 
mouth of Umatilla River. 
Existing project. See Table 39-B for authorizing 
legislation. A dam 7,365 feet long overall and 
about 180 feet high above streambed, powerplant 
with 14 power generating units, navigation lock, 
fishways, levees and pumping plants, incidental 
irrigation, and modification of railroad bridges 
over Columbia and Snake Rivers in order to 
eliminate hazards to navigation. Principal project 
data are set forth in Table 39-H. 
Estimated total cost for new work (October 
1975) is $312,613,000 consisting of $302,900,000 
for construction, a net reduction of $851,000 for 
cost and property transferred from project, $63,- 
000 for Coast Guard navigation aids, and $10,- 
501,000 for modification of the Union Pacific 
Railroad bridge over Snake River by the Coast 
Guard. Expenditures on recreation facilities for 
completed project have been $571,027. 
Local cooperation. None required. 
Operations and results during fiscal year. New 
work: A study is underway to establish the 
feasibility of installing additional power 
generating units at the project. 
Operation and maintenance: Normal operation 
and maintenance of project continued. Approximately 
7.37 billion kilowatt hours of electric 
energy were delivered to Bonneville Power Administration, 
the marketing agency. A total of 3,- 
014,769 tons of commodities passed through the 
navigation lock. 
Condition at end of fiscal year. Construction 
started May 1947 and is 100 percent complete except 
for modification of fish facilities for nitrogen 
control. Project placed on permanent operating 
basis and lake raised to elevation 340 in 
November 1953. Except for maintenance interuptions, 
all 14 power units have been in commercial 
operation since February 1957. Design 
for modification of UPRR bridge over Snake 
River is complete, with construction scheduled 
for FY 1976. 
Power generation through June 1975 has been 
122.6 billion kilowatt hours, representing a gross 
income of $188.3 million to the U.S. Treasury 
from sale of power by Bonneville Power Administration. 
A draft Environmental Impact 
39-10

WALLA WALLA DISTRICT 
Statement was filed with Council on Environmental 
Quality in March 1974. 
22. SNAKE RIVER DOWNSTREAM 
FROM JOHNSON BAR LANDING, 
OREG., WASH., & IDAHO 
Location. On Snake River downstream from 
Johnson Bar Landing, river mile 231. Snake 
River, which is largest tributary of Columbia 
River, rises in Yellowstone National Park in 
western part of Wyoming, flows generally 
westerly for about 1,000 miles, and empties into 
Columbia River near Pasco, Wash., 324 miles 
from Pacific Ocean. 
Previous projects. For details see Annual 
Reports, page 2246 for 1903; page 1986 for 1906; 
page 1991 for 1915; and page 1981 for 1962. 
Existing project. See Table 39-B for authorizing 
legislation. The River and Harbor Act of 1945 
authorized construction of dams as necessary and 
open channel improvements for purposes of 
providing slack-water navigation and irrigation 
between mouth of Snake River and Lewiston, 
Idaho. That authorization modified previous 
authorizations only for that portion of improvement 
below Lewiston, Idaho. Acts of June 13, 
1902, and August 30,1935, as they pertain to open 
river improvement from Lewiston, Idaho, to 
Johnson Bar Landing, remain part of existing 
project. 
Improvements included in existing project are 
Ice Harbor Lock and Dam-Lake Sacajawea; Little 
Goose Lock and Dam-Lake Bryan; Lower 
Granite Lock and Dam; Lower Monumental Lock 
and Dam; and open-river improvement, Lewiston 
to Johnson Bar Landing. Each of the four locks 
and dams is described in an individual report, 
and cost and financial data for the entire project 
are shown on Tables 39-A and 39-I. 
Local cooperation. None required. 
Terminal facilities. On Snake River from the 
mouth to Johnson Bar Landing there are 11 
privately owned barge terminals in use for shipping 
grain, petroleum products, fertilizers, cement, 
and other general cargo. There are also 5 
marinas and 28 small-boat launching ramps, all 
open to public use. The facilities serve slackwater 
navigation to Snake River mile 138, the site 
of Lewiston, Idaho. That slack-water reaches the 
Lewiston, Idaho-Clarkston, Wash., area since the 
lake behind Lower Granite Dam was filled in 
February 1975. 
Operations and results during fiscal year. See 
individual reports for Ice Harbor, Lower 
Monumental, Little Goose, and Lower Granite 
locks and dams. On Snake River from Lewiston, 
Idaho, to Johnson Bar Landing, reconnaissance 
and condition surveys were conducted and 
navigation aids were maintained. 
Condition at end of fiscal year. Ice Harbor, 
Lower Monumental, Little Goose and Lower 
Granite are in full operation. Lower Granite construction 
is about 86 percent complete. (See individual 
reports for details.) 
23. OTHER AUTHORIZED MULTIPLEPURPOSE 
PROJECTS 
See Table 39-J. 
General Investigations 
24. SURVEYS 
Total cost of surveys during fiscal year was 
$513,655. That sum was spent for: flood control 
studies, $461,939; cooperative studies with the 
Soil Conservation Service and the Bureau of 
Reclamation, $34,905; a restudy of the Boise 
Valley, $4,938; and project deauthorization 
review, $11,873. 
25. COLLECTION AND STUDY 
OF BASIC DATA 
During the fiscal year flood hazard data for a 
number of locations in the District were collected 
and analyzed. Flood information was provided to 
several Federal agencies, to the States of Idaho, 
Oregon, and Washington, to various cities and 
counties in those states, and to some private 
organizations. 
Flood plain information reports were completed 
for Lawyers Creek in the area of Kamiah, 
Idaho, and Walla Walla River, vicinity of Milton- 
Freewater, Oregon. A special flood hazard report 
was prepared on the Boise River vicinity of 
Caldwell, Idaho. 
Total fiscal year costs were $250,642. 
26. RESEARCH AND DEVELOPMENT 
No special research and development activities 
were conducted during fiscal year 1975. 
39-11

TABLE 39-A 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
2. Blackfoot Reservoir, 
Idaho 
3. Catherine Creek 
Lake, Oreg. 
4. Columbia River 
Basin Local Flood 
Protection Projects 
(Consolidated) 
5. Jackson Hole, 
Snake River, Wyo. 
6. Lucky Peak Lake, 
Boise River, Idaho 
7. Mill Creek Lake, 
Wash. 
8. Pullman, Palouse 
River, Wash. 
9. Ririe Lake, 
Idaho 
10. Willow Creek Lake, 
Heppner, Oreg. 
11. Zintel Canyon Dam, 
Wash. 
16. Dworshak Dam and 
Reservoir, Idaho 
17. Ice Harbor Lock 
and Dam-Lake 
Sacajawea-Wash. 
18. Little Goose Lock 
and Dam-Lake 
Bryan-Wash. 
19. Lower Granite Lock 
and Dam, Wash. 
20. Lower Monumental 
Lock and Dam, 
Wash. 
r-va-vava Total Cost: to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
8,500 
11,392 
20,000 
49,560 
45,000 
1,480 
33,000 
25,651 
16,326 
Funding 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
29,363 
46,763 
400,000 
346,195 
-3,000 
6,283 
82,000 
75,708 
1,412 
-3,000 
3,483 
218,900 
181,739 
135,300 
174,688 
8,837 
1,389,600 
795,484 
282,400 
73,163 
158,900 
81,018 
45,493,296 
43,455,424 
6,900 
4,797 
4,806,591 
3,489,677 
832,000 
851,263 
6,845,500 
3,756,150 
1,171,800 
899,736 
61,642,900 
60,815,051 
7,587,000 
4,108,107 
751,000 
833,822 
-648,000 3,876,000 
2,401,842 3,678,804 
787,623 811,616 
772,675 812,726 
-18,000 253,179 
8,233 253,178 
295,000 1,389,000 
354,470 1,383,169 
-12,670 11,090,191 
309 11,090,191 
65 
2( 
33 
361 
20,957 
261,966 
236,500 
137,334 
144,197 
7,364 
2,728,000 
1,675,446 
76,000 
167,215 
40,000 
87,848 
23,416,000 
23,536,628 
171,341 
157,102 
5,611,088 
6,083,811 
1,712,028 
1,460,106 
1,956,493 
2,996,877 
785,410 
1,158,475 
57,882,000 
54,498,069 
9,000 2,383,681 
1,850 2,360,239 
0,000 19,397,200 1 
- 19,377,200 1 
6,970 2,754,204 
6,316 2,746,878 
- 2,230,601 23 
- 2,230,601 2 3 
2,800 1,908,609 
9,632 1,887,928 
2,830 99,540 
389 99,540 
8,810 21,121,448 
7,520 21,032,631 
8,810 674,227 
4,886 674,227 
5,000 358,900 
2,528 358,899 
0,000 287,263,396 4 
8,611 287,097,908 
4,369 2,121,860 6 
2,167 2,058,515 
0,000 157,309,745 6 
9,732 157,224,744 6 
4,929 13,176,949 
9,066 13,034,988 
7,500 162,141,593 
3,295 162,059,333 
9,170 5,194,113 
1,702 5,169,085 
0,500 278,946,223 
2,459 278,671,721 1 
8,962 128,962 
9,607 19,607 
4,000 184,454,361 
1,546 184,443,798 
2,609 4,738,187 
8,304 4,712,995 
39-12 
265,723 
308,414 
202,777 
222,528 
3,000 
3,580 
2,945,000 
4,295,560 
444,637 
288,964 
135,000 
77,505 
8,644,000 
10,742,553 
819,250 
764,449 
11,245,000 
12,124,553 
1,483,408 
1,614,794 
1,977,000 
3,475,156 
1,145,972 
1,090,529 
51,541,000 
54,890,576 
20 
19! 
8,451 
8,88 
-121 
14, 
2 
11, 
9,25 
9,44 
1,12 
1,13 
5,49 
5,49 
1,86 
1,90 
2,04 
2,85 
1,11 
1,17 
40,201 
40,88 
121 
1,47 
2,15 
94, 
95

WALLA WALLA DISTRICT 
TABLE 39-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
21. McNary Lock and New Work 
Dam-Lake Wallula- Approp. 350,609 228,819 1,318,000 1,060,000 292,987,154 7 
Oreg. & Wash. Cost 535,758 165,665 146,895 1,944,988 292,542,696 8 
Maint. 
Approp. 2,286,000 3,323,599 3,344,555 3,176,178 39,478,806 
Cost 2,489,085 3,071,000 3,615,671 3,051,514 39,199,468 
22. Snake River Down- New Work 
stream from Johnson Approp. 80,881,991 72,977,581 60,463,000 49,212,000 783,286,686 9 
Bar Landing, Oreg., Cost 72,168,986 65,980,599 74,169,087 51,387,032 782,834,360 9 
Wash., & Idaho Maint. 
Approp. 2,766,600 3,094,941 3,448,095 4,226,924 23,596,035 10 
Cost 2,592,139 3,397,565 3,525,112 4,068,679 23,294,250 10 
1. Includes $315,950 for Code 710, Recreation Facilities 
on Completed Projects. 
2. Excludes $80,000 contributed funds. 
3. Includes $68,446 Code 710, Recreation Facilities on 
Completed Projects. 
4. Excludes $2,046,100 regular project construction 
funds transferred to Department of Interior in Fiscal Years 
1969 through 1972 for hatchery operations. 
5. Excludes $2,917,100 regular project operation and 
maintenance funds transferred to Department of Interior 
starting Fiscal Year 1972 for hatchery operations. 
6. Includes $345,150 for Code 710, Recreation Facilities 
on Completed Projects. Excludes $82,500 contributed for artificial 
spawning channel. 
7. Includes $929,154 allotted for Code 710, Recreation 
Facilities on Completed Projects. 
8. Includes $850,375 net value of non-appropriation 
transfer of cost or property from project. Includes $497,256 
expended for Code 710, Recreation Facilities on Completed 
Projects. 
9. Includes $400,150 for new work on previous projects 
(Pasco to Lewiston). Excludes $167,500 contributed funds for 
new work consisting of $85,000 for previous projects (Pasco to 
Riparia), plus $82,500 for new work on existing artificial 
spawning channel (Ice Harbor Lock and Dam Project). 
10. Includes $186,570 for maintenance on previous projects 
(Pasco to Lewiston). 
11. Excludes $405,819 contributed funds. 
39-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 39-B AUTHORIZING LEGISLATION 
Acts Work Authorized 
Oct. 23, 1962 
Oct. 27, 1965 
May 17, 1950 
July 3, 1958 
Oct. 23, 1962 
Aug. 15, 1963 
Mar. 2, 1945 
May 17, 1950 
Mar. 2, 1945 
BLACKFOOT RESERVOIR, IDAHO 
(See Section 2 of Text) 
Modify existing Bureau of Indian Affairs dam to add 
exclusive flood-control storage space. 
CATHERINE CREEK LAKE, OREG. 
(See Section 3 of Text) 
Dam and lake for flood control, irrigation, 
recreation, municipal water supply, 
and fish and wildlife. 
COLUMBIA RIVER BASIN, ACTIVE LOCAL FLOOD 
PROTECTION PROJECTS (See Section 4 of Text) 
Blackfoot Area, Snake River, Idaho. Levee left bank. 
Blackfoot River, Idaho. Levees, channel improvement, 
and rectification works. 
Boise Valley, Boise River, Idaho. Channel improvement 
and enlargement, levees, and revetments in Ada County. 
Canyon County unit was deauthorized April 18, 1967. 
Grande Ronde Valley, Oreg. Levees and channel clearing, 
straightening, and realignment; would complement stream 
regulation by upstream storage projects. 
Heise-Roberts Extension, Snake River, Idaho. Channel 
clearing and rectification, levees, and bank protection. 
Kendrick, Potlatch River, Idaho. Revetted levee. 
Malheur River, Oreg. Channel rectification, levees, and 
bank protection at Vale. Willow Creek unit was deauthorized 
October 14, 1969. 
Palouse River, Wash. Flood protection for urban and 
rural areas at Garfield and near Malden. 
Payette Valley, Idaho. Channel rectification, levees, 
and bank protection along 38 miles of Payette River 
below Black Canyon Dam. 
Portneuf River and Marsh Creek, Idaho. Concrete-lined 
channel through Pocatello. Inkom-Marsh Creek unit was 
deauthorized October 14, 1969. 
Shelley Area, Snake River, Idaho. Bank protection. 
Weiser River, Weiser Area, Idaho. Intermittent channel 
realignment and improvement, levees, and bank protection, 
lower river area. 
(BRUCES EDDY) DWORSHAK DAM AND RESERVOIR, 
IDAHO (See Section 16 of Text) 
Preparation of detailed plans. 
Bruces Eddy dam and reservoir for flood control, navigation, 
power, recreation, and area redevelopment. 
Redesignation of project as Dworshak Dam and Reservoir. 
ICE HARBOR LOCK AND DAM-LAKE SACAJAWEAWASH. 
(See Section 17 of Text) 
Unit 1 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, and irrigation. 
JACKSON HOLE, SNAKE RIVER, WYO. 
(See Section 5 of Text) 
Channel rectification, levees, and revetment. 
LITTLE GOOSE LOCK AND DAM-LAKE BRYANWASH. 
(See Section 18 of Text) 
Unit 3 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, and irrigation. 
39-14 
Documents 
H. Doc. 568, 87th Cong., 
2nd Sess. 
H. Doc. 280, 89th Cong., 
1st Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
S. Doc. 51, 84th Cong., 
1st Sess. 
H. Doc. 403, 87th Cong., 
2d Sess. 
P.L. 88-96 
H. Doc. 704, 75th Cong., 
3d Sess. 
H. Doc. 531, 81st Cong., 
2d Sess. 
H. Doc. 704, 75th Cong., 
3d Sess.

WALLA WALLA DISTRICT 
TABLE 39-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
Mar. 2. 1945 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Oct. 23, 1962 
LOWER GRANITE LOCK AND DAM, WASH., AND IDAHO 
(See Section 19 of Text) 
Unit 4 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, and irrigation. 
LOWER MONUMENTAL LOCK AND DAM, WASH. 
(See Section 20 of Text) 
Unit 2 of 4, Lower Snake River project. Lock and dam 
for navigation, power, recreation, and irrigation. 
LUCKY PEAK LAKE, IDAHO 
(See Section 6 of Text) 
Dam for flood control, irrigation, and recreation. 
McNARY LOCK AND DAM-LAKE WALLULA-OREG., 
AND WASH. (See Section 21 of Text) 
Lock and dam for navigation, power, recreation, and 
irrigation. 
MILL CREEK LAKE, WALLA WALLA, WASH. 
(See Section 7 of Text) 
Off-stream storage project upstream from Walla Walla. 
Channel improvement through Walla Walla; concretelined 
channel. 
PULLMAN, PALOUSE RIVER, WASH. 
(See Section 8 of Text) 
Concrete-lined channel, levees, and revetments. 
RIRIE LAKE, IDAHO (See Section 9 of Text) 
Storage project for flood control, irrigation, 
recreation & sports fishery. 
SNAKE RIVER MOUTH TO JOHNSON BAR, WASH. 
AND IDAHO (See Section 22 of Text) 
Open-river navigation. 
Riparia to Pittsburg Landing. 
Mouth to Riparia. 
Pittsburg Landing to Johnson Bar. 
Supersedes previous legislation mouth to Lewiston, 
Idaho, only. See Ice Harbor, Lower Monumental, 
Little Goose, and Lower Granite Locks and Dams. 
WILLOW CREEK LAKE, OREG. 
(See Section 10 of Text) 
Storage project for flood control, recreation, and 
fish and wildlife. 
ZINTEL CANYON DAM, KENNEWICK, WASH. 
(See Section 11 of Text) 
Dam and storage space for temporary detention of 
flood flows plus channel improvement downstream. 
H. Doc. 127, 56th Cong., 
2d Sess. 
H. Doc. 411, 55th Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 25, 72d 
Cong., 1st Sess. 
H. Doc. 704, 75th Cong., 
2d Sess. 
H. Doc. 233, 89th Cong., 
1st Sess. 
H. Doc. 416, 91st Cong., 
2d Sess. 
39-15 
H. Doc. 704, 75th Cong., 
3d Sess. 
H. Doc. 704, 75th Cong., 
3d Sess. 
P.L. 526-79 
Chief of Engineers 
Report dated May 13, 1946 
H. Doc. 704, 75th Cong., 
3d Sess. 
H. Doc. 578, 75th Cong., 
3d Sess. 
H. Doc. 719, 76th Cong., 
3d Sess. 
H. Doc. 888, 77th Cong., 
2d Sess. 
H. Doc. 562, 87th Cong., 
2d Sess. 
June 13, 1902 
June 25, 1910 
Aug. 30, 1935 
Mar. 2, 1945 
Oct. 27, 1965 
Oct. 27, 1965

TABLE 39-C 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Columbia River and Tributaries above Celilo 
Falls to Kennewick, Wash.' 1968 1,851,195 1,108,259 
Snake River vicinity of Weiser, Idaho2 
1. Obviated by The Dalles, John Day, and McNary Proj- 2. Authorized by Chief of Engineers. Deferred. 
ects. 
TABLE 39-D COLUMBIA RIVER BASIN, LOCAL 
FLOOD PROTECTION PROJECTS 
(See Section 4 of Text) 
Estimated Status June 30, 1975 
Federal 
Project Cost Appropriated Cost 
Blackfoot Area, Snake River, Idaho ' 2 42,796 42,796 
Blackfoot River, Idaho 1 2 391,143 391,143 
Boise Valley, Idaho 1 
Ada County Unit 3 4 1,060,000 46,084 46,084 
Canyon County Unit (Deauthorized April 18, 1967) 
(Final Report) - 10,600 10,600 
Camas Creek (Deauthorized March 23, 1965) (Final Report) - 9,080 9,080 
Grande Ronde Valley, Oreg. 1 4 8,639,000 102,458 102,458 
Heise-Roberts Extension, Idaho 1 
Henrys Fork Unit 4 2 27,800 27,800 
Snake River Unit 2 3,375,158 3,375,158 
Kendrick, Potlatch River, Idaho 1 2 59,942 59,942 
Little Wood River, Carey, Idaho (Deauthorized 
April 21, 1965)' (Final Report) - 21,334 21,334 
Lower Walla Walla River, Wash. (not feasible) - 4,000 4,000 
Malheur River, Oreg. 
Vale Unit 1 2 325,581 325,581 
Willow Creek Unit (Deauthorized October 14, 
1969) 1 (Final Report) - 13,000 13,000 
Mill Creek, Wash. (not feasible) - 3,537 3,537 
Mud Lake Area, Idaho (not feasible) - 5,996 5,996 
Palouse River, Wash. 4 914,000 
Payette Valley, Idaho 4 - 23,178 23,178 
Portneuf River and Marsh Creek, Idaho 1 
Pocatello Unit 2 6,456,032 6,456,032 5 
Inkom-Marsh Creek Unit (Deauthorized October 14, 
1969) (Final Report) 
Shelley Area, Snake River, Idaho 1 2 32,335 32,335 
South Fork Clearwater River, Idaho 6 - 3,899 3,899 
Teton River, Idaho (not feasible) - 10,387 10,387 
Touchet River, Wash. (not feasible) - 11,198 11,198 
Weiser River, Idaho 1 4 1,565,000 112,757 112,757 7 
Whitebird Creek, Idaho 6 - 1,896 1,896 
TOTAL 11,090,191 11,090,191 
1. See Table 39-F. 
2. Completed Project. 
3. Economic justification of work proposed has been established 
in compliance with conditions set forth in Flood 
Control Act of 1950. 
4. Deferred for restudy. 
5. Exclusive of $36,800 contributed funds. 
6. Emergency construction at this location has obviated 
need for project. 
7. Includes $75,000 spent on infeasible Cambridge and 
Midvale areas. 
39-16

WALLA WALLA DISTRICT 
INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
(See Section 12 of Text) 
Colfax, Palouse River, Wash. 
Dayton, Touchet River, Wash. 
Gooding Area, Little Wood River, Idaho 
Heise-Roberts Area, Snake River, Idaho 
Heise-Roberts Extension, Snake 
River, Idaho 
Jackson Hole, Snake River, Wyo. 
Kendrick, Potlatch River, and Bear 
Creek, Idaho 
Lapwai Creek, Culdesac, Idaho 
Lower Dry Creek, Lowden, Wash. 
F
F 
Se 
F
F
'ebruary 1975 Malheur Improvement District, Snake 
'ebruary 1975 River, Oreg. March 1975 
ptember 1974 Malheur River, Vale, Oreg. March 1975 
August 1974 Milton-Freewater, Walla Walla River, Oreg. March 1975 
Mission Creek, Idaho February 1975 
August 1974 Pocatello Unit, Portneuf River, Idaho September 1974 
August 1974 Tomanovich-Salmon City, Salmon 
River, Idaho April 1975 
'ebruary 1975 Tucannon River, Camp Wooten, Wash. February 1975 
'ebruary 1975 West Richland, Yakima River, Wash. October 1974 
April 1975 
39-17 
TABLE 39-E

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Bear Creek, Kendrick, Idaho 1 2 
Blackfoot Area, Snake River, Columbia 
River Basin, Idaho 1 
Blackfoot River, Columbia River Basin, Idaho 1 
Boise Valley, Columbia River Basin, Idaho 
(a) Ada County Unit 3 
(b) Canyon County Unit 4 (Final Report) 
Colfax, Palouse River, Wash. 1 
Cottonwood Creek Dam, Boise, Idaho 
Dayton, Touchet River, Wash. 1 
Esquatzel Coulee, Connell, Wash. 1 2 
Gooding Area, Idaho 1 3 
Grande Ronde Lake, Oreg. 
Grande Ronde Valley, Columbia River Basin, 
Oreg. 3 
Heise-Roberts Area, Snake River, Idaho 1 
Heise-Roberts Extension, Columbia River 
Basin, Idaho 
(a) Henrys Fork Unit 3 
(b) Snake River Unit 1 
Kendrick, Potlatch River, Columbia River 
Basin, Idaho 1 
Lapwai Creek, Culdesac, Idaho 1 2 
Lewiston Levees 5 
Little Wood River (Carey), Columbia River 
Basin, Idaho 4 (Final Report) 
Lower Dry Creek, Lowden, Wash. 1 2 
Lyman Creek, Idaho 1 2 
Malheur Improvement District, Snake 
River, Oreg. 1 
Malheur River, Columbia River Basin, Oreg. 
(a) Vale Unit 1 
(b) Willow Creek Unit 4 (Final Report) 
Milton-Freewater, Walla Walla River, Oreg. 1 
Mission and Lapwai Creeks, Idaho 1 2 
Portneuf River and Marsh Creek, Columbia 
River Basin, Idaho 
(a) Inkom-Marsh Creek Unit 4 (Final Report) 
(b) Pocatello Unit 1 
Shelley Area, Snake River, Columbia River 
Basin, Idaho 1 
Stuart Gulch Dam, Boise, Idaho 
Tomanovich-Salmon City, Idaho 1 2 
Tucannon River, Camp Wooten, Wash. 1 2 
Weiser River, Columbia River Basin, Idaho 3 
Yakima River, West Richland, Wash.' 2 
1. Completed project. 
2. Authorized by Chief of Engineers. 
3. Deferred for restudy. 
4. Deauthorized. For specific date, see Table 39-D. 
5. Withdrawn as a local flood protection project in June 
1959. Included as a feature of Lower Granite Lock and Dam, 
Snake River, Wash. 
6. Exclusive of $6,300 contributed funds. Includes $550,- 
875 spent under Public Law 99 authority. 
7. Includes an estimated $75,000 spent for planning on 
infeasible areas. 
8. Inactive. Five-year limitation on project authorization 
began May 17, 1974. 
39-18 
TABLE 39-F 
1970 
1958 
1965 
1967 
1966 
1973 
1966 
1967 
1954 
1966 
1958 
1955 
1968 
1960 
1972 
1950 
1960 
1961 
1971 
1957 
1961 
1968 
1965 
1969 
1958 
1974 
1955 
1971 
1960 
1964 
133,518 
42,796 
391,143 
46,084 
10,600 
5,557,240 
183,100 
380,617 
292,792 
59,167 
102,458 
1,575,838 
27,800 
3,375,158 
59,942 
176,833 
21,334 
402,018 
230,315 
55,894 
325,580 
13,000 
2,337,628 6 
54,538 
6,456,032 
32,335 
234,100 8 
128,635 
73,932 
112,757 7 
238,890

WALLA WALLA DISTRICT 
TABLE 39-G FLOOD CONTROL WORKS UNDER 
SPECIAL AUTHORIZATION 
(See Section 15 of Text) 
Fiscal Year Costs 
Little Canyon Creek, Glenns Ferry, Idaho $ 6,289 
Mud Lake, Idaho 7,151 
Payette River, Idaho - Chapman Location 7,694 
TABLE 39-H PRINCIPAL DATA CONCERNING NAVIGATION 
LOCK, SPILLWAY DAM, POWERPLANT, 
AND IMPOUNDMENT 
Project 
SPILLWAY DAM 
Dworshak Dam and 
Reservoir, Idaho 
(See Section 16 of Text) 
Ice Harbor Lock 
and Dam, Wash. 
(See Section 17 of Text) 
Type of Construction 
Completed 
Maximum Capacity 
Concrete Gravity 
Under Construction 
150,500 Cubic Feet 
Per Second 
1613 Feet 
Tainter 
50 Ft. by 55 Ft. 
2
428 Feet 
3
3
2 @ 90,000 kw; 4 @ 
220,000 kw 
400,000 kw 
1,060,000 kw 
150 Feet 
March 1973 
1600-1445 Feet 
1605 Feet 
2,000,000 Ac.-Ft. 
53 Miles 
17,090 Acres 
175 Miles 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Capacity Installed 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at 
Elevation 1600 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
86 Feet 
665 Feet 
97 Feet 
100 Feet 
103 Feet 
15 Feet 
May 1962 
39-19

TABLE 39-H 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
PRINCIPAL DATA CONCERNING NAVIGATION 
LOCK, SPILLWAY DAM, POWERPLANT, 
AND IMPOUNDMENT 
Project 
Little Goose Lock 
and Dam, Wash. 
(See Section 18 of Text) 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Additional Under Construction 
Rating, Each 
Total Installed Capacity 
Total Capacity to be Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at 
Elevation 440 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
Concrete Gravity 
January 1962 
850,000 cfs 
391 Feet 
Tainter 
50 Ft. by 51 Ft. 
10 
671 Feet 
3
3
3 @ 90,000 kw; 3 @ 
111,000 kw 
270,000 kw 
603,000 kw 
226 Feet 
December 1961 
440-437 Feet 
446 Feet 
31.9 Miles 
9,200 Acres 
14 Ft. by 250 Ft. 
80 Miles 
86 Feet 
675 Feet 
93 Feet 
98 Feet 
101 Feet 
15 Feet 
May 1970 
Concrete Gravity 
January 1970 
850,000 cfs 
581 Feet 
Tainter 
50 Ft. by 60 Ft. 
89-20

WALLA WALLA DISTRICT 
TABLE 39-H 
(Continued) 
PRINCIPAL DATA CONCERNING NAVIGATION 
LOCK, SPILLWAY DAM, POWERPLANT, 
AND IMPOUNDMENT 
Project 
POWERPLANT 
Lower Granite Lock 
and Dam, Wash. 
(See Section 19 of Text) 
Length 
Width 
Generating Units: 
Number Installed 
Additional Under Construction 
Rating, Each 
Total Installed Capacity 
Total Capacity to be Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at 
Elevation 638 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
SPILLWAY DAM 
Type of Construction 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Additional Under Construction 
Rating, Each 
Total Capacity Installed 
Total Capacity to be Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
656 Feet 
243 Feet 
3
3
135,000 kw 
405,000 kw 
810,000 kw 
244 Feet 
March 1970 
638-633 Feet 
646.5 Feet 
37.2 Miles 
10,025 Acres 
14 Ft. by 250 Ft. 
92 Miles 
86 Feet 
674 Feet 
95 Feet 
100 Feet 
105 Feet 
15 Feet 
Concrete Gravity 
850,000 cfs 
581 Feet 
Tainter 
50 Ft. by 60.5 Ft. 
8
656 Feet 
243 Feet 
3
3
135,000 kw 
405,000 kw 
810,000 kw 
246 Feet 
April 1975 
738-733 Feet 
746.5 Feet 
39-21

TABLE 39-H 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
PRINCIPAL DATA CONCERNING NAVIGATION 
LOCK, SPILLWAY DAM, POWERPLANT, 
AND IMPOUNDMENT 
Project 
Project 
Lower Monumental 
Lock and Dam, Wash. 
(See Section 20 of Text) 
McNary Lock and 
Dam, Oreg. and 
Wash. (See Section 
21 of Text) 
Lake Length 
Lake Water Surface Area at 
Elevation 738 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Additional Under Construction 
Rating, Each 
Total Installed Capacity 
Total Capacity to be Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevation: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at 
Elevation 540 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
39 Miles 
8,900 Acres 
14 Ft. by 250 Ft. 
91 Miles 
86 Feet 
675 Feet 
97 Feet 
98 Feet 
103 Feet 
15 Feet 
April 1969 
Concrete Gravity 
March 1969 
850,000 cfs 
483 Feet 
Tainter 
50 Ft. by 61 Ft. 
8
656 Feet 
243 Feet 
3
3
135,000 kw 
405,000 kw 
810,000 kw 
242 Feet 
January 1970 
540-537 Feet 
548 Feet 
28.7 Miles 
6,590 Acres 
14 Ft. by 250 Ft. 
78 Miles 
86 Feet 
675 Feet 
67 Feet 
75 Feet 
92 Feet 
39-22

WALLA WALLA DISTRICT 
TABLE 39-H 
(Continued) 
PRINCIPAL DATA CONCERNING NAVIGATION 
LOCK, SPILLWAY DAM, POWERPLANT, 
AND IMPOUNDMENT 
Project 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Compjeted 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Installed Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at 
Elevation 340 
Navigation Channel, Depth by Width 
Length of Shoreline 
15 Feet 
November 1953 
Concrete Gravity 
October 1953 
2,200,000 cfs 
291 Feet 
Vertical Lift 
50 Ft. by 51 Ft. 
22 
1,348 Feet 
241 Feet 
14 
70,000 kw 
980,000 kw 
193 Feet 
November 1953 
340-335 Feet 
356.5 Feet 
64 Miles 
38,800 Acres 
14 Ft. by 250 Ft. 
242 Miles 
39-23

TABLE 39-I 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING, 
OREG., WASH., AND IDAHO 
(See Section 22 of Text) 
Estimated 
Cost (Corps New Work Maintenance 
of Engineers to June 30, 1975 to June 30, 1975 Percent Constr. 
Projects Funds Only) Approp. Cost Approp. Cost Completed Started 
Ice Harbor Lock 
and Dam 
Initial Project 
Code 710 Recreation 
Facilities 
Power Units 4-6 
Totals 
Little Goose 
Lock & Dam 
Initial Project 
Power Units 4-6 
Totals 
Lower Granite 
Lock & Dam 
Initial Project 
Power Units 4-6 
Totals 
Lower Monumental 
Lock & Dam 
Initial Project 
Power Units 4-6 
Totals 
Open River Lewiston 
to Johnson Bar 
Landing 
Open River Pasco 
to Lewiston 
Totals Existing 
Project 
Previous Projects 
Pasco to Lewiston 
Totals Authorized 
Project 
129,622,300 129,578,479 129,578,479 
1,645,000 
37,900,000 
169,167,300 
160,687,000 
58,100,000 
218,787,000 
310,000,000 
52,100,000 
362,100,000 
185,400,000 
55,800,000 
241,200,000 
345,150 
27,386,116 
157,309,745 
159,784,215 
2,357,378 
162,141,593 
276,574,723 
2,371,500 
278,946,223 
184,109,361 
345,000 
184,454,361 
34,613 
270,809 
27,375,456 
157,224,744 
159,777,642 
2,281,691 
162,059,333 
276,378,796 
2,292,925 
278,671,721 
184,105,660 
338,138 
184,443,798 
13,176,949 13,034,988 
13,176,949 13,034,988 
5,194,113 
5,194,113 
128,962 
128,962 
4,738,187 
4,738,187 
5,169,085 
5,169,085 
19,607 
19,607 
4,712,995 
4,712,995 
- FY 56 
93 
74 
77 
76 
FY 57 
FY 71 
FY 63 
FY 74 
FY 65 
FY 74 
FY 61 
FY 75 
34,613 1 34,613 1 166,904 166,655 
4,350 4,350 
991,288,913 782,886,535 782,434,209 23,409,465 23,107,680 
400,150 400,150 400,150 186,570 
79 
186,570 
991,689,063 783,286,685 782,834,359 23,596,035 23,294,250 
1. New work appropriations used for maintenance prior to 1953. 
TABLE 39-J OTHER AUTHORIZED MULTIPLE-PURPOSE 
PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Asotin Dam, Snake River, Idaho and Wash. 1964 
39-24

ALASKA DISTRICT* 
This District consists of the State of Alaska. 
IMPROVEMENTS 
Navigation Page 
1. Anchorage Harbor, Alaska ............. 40-1 
2. Bethel Small-Boat Harbor, 
Alaska....................... 40-2 
3. Cook Inlet Shoals, Alaska............... 40-2 
4. Dillingham Harbor, Alaska.............. 40-3 
5. Homer Harbor, Alaska................. 40-3 
6. Hoonah Harbor, Alaska................... 40-3 
7. Humboldt Harbor, Alaska ............ 40-4 
8. Kake Harbor, Alaska..................... 40-5 
9. Kasilof River, Alaska....................... 40-5 
10. Metlakatla Harbor, Alaska ............ 40-6 
11. Ninilchik Harbor, Alaska .............. 40-6 
12. Nome Harbor, Alaska.................... 40-7 
13. Other Authorized Navigation 
Projects............................. 40-7 
14. Navigation Work Under 
Special Authority........................ 40-7 
Flood Control 
15. Chena River Lakes, Alaska ............ 40-7 
Flood Control (Cont.) Page 
16. Gold Creek, Alaska.......................... 40-8 
17. Inspection of Completed 
Flood Control Projects............... 40-8 
18. Other Authorized Flood 
Control Projects .......................... 40-8 
19. Flood Control Work Under 
Special Authorization........................ 40-8 
20. 
21. 
Multiple-Purpose Projects 
Including Power 
Snettisham, Alaska ...................... 40-8 
Bradley Lake, Alaska ......... 40-9 
General Investigations 
22. Surveys........................................ 40-9 
23. Collection and Study of 
Basic Data..................................... 40-9 
24. Research and Development .......... 40-10 
Navigation 
1. ANCHORAGE HARBOR, ALASKA 
Location. Anchorage is in southcentral Alaska 
on the southeast shore of Knik Arm, north of Turnagain 
Arm near its junction with Cook Inlet. 
(See NOAA Charts 16660 and 16664.) 
Existing project. Provides for a deepwater harbor 
by dredging adjacent to municipal docks to a 
depth of 35 feet below mean lower low water and 
constructing two jetties or other protective works 
when required, along northerly and southerly 
ends. Dredging was completed June 1967; 
construction of jetties and purchase of a dredge 
have been deferred. Tidal range between mean 
lower low water and mean higher high water is 
29.0 feet and extreme range is 42.0 feet. (See 
Table 40-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Four wharves capable of 
handling oceangoing vessels and open for public 
use. Two are owned by the city; a general cargo 
wharf and an oil handling and bunkering facility. 
The other two are privately owned. Five additional 
privately owned wharves are used for industrial 
purposes. Expansion of the city general 
cargo wharf is underway. 
Operations and results during the fiscal year. 
Regular funds, maintenance: Annual 
maintenance dredging contract was awarded 
June 1974 and dredging was completed in 
September 1974 with 97,651 cubic yards of 
material removed. 
* All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and 
also appear at the end of this chapter. 
40-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Condition at end of fiscal year. Dredging was 
accomplished jointly by local interests and 
United States Army to provide a depth of 35 feet. 
alongside the newly constructed City Dock and 32 
feet at a distance of 50 feet from Ocean Dock in 
July 1961; city and Army funds were used. Ocean 
Dock was destroyed in the March 27, 1964 earthquake. 
Emergency dredging was performed at 
City Dock July and August 1965. The first phase 
of new work in the authorized project, consisting 
of dredging the port area to a depth of 35 feet, was 
accomplished October 1966 through June 1967. 
During the design stage, the project basin was 
modified to match City Dock, including expansion 
then underway. 
2. BETHEL SMALL-BOAT 
HARBOR, ALASKA 
Location. The city of Bethel is 65 miles upriver 
on the north bank of the Kuskokwim River, which 
flows through southwestern Alaska. (See Coast 
and Geodetic Survey Chart 9302 and USGS Map 
Bethel D8.) 
Existing project. Project includes provision of a 
7,700-foot-long small-boat harbor and entrance 
channel by deepening, widening, and straightening 
of the upper 6,800 feet of Brown's Slough. Estimated 
cost of the project (1973) is $1,000,000 in 
Federal funds, plus $34,000 from local interests 
(See paragraph on local cooperation). Range 
between mean lower low water and mean higher 
high water is 3.4 feet and extreme tidal range is 
4.0 feet, during low summer water flow in 
Kuskokwim River. Water level also depends on 
river stage; tidal effects decrease with higher 
river flows, disappearing only at the 20-yearfrequency 
flood stage. (See Table 40-B for 
authorizing legislation.) 
Local cooperation. Local interests will provide, 
maintain, and operate without cost to the United 
States, as needed for transient and local 
operators, adequate public access roads, parking 
areas, and other needed public use shore 
facilities, open and available to all on equal terms; 
provide, without cost to the United States all 
necessary lands, easements, and rights-of-way required 
for construction and subsequent 
maintenance of the project, including suitable 
soil-disposal areas with necessary retaining 
dikes, bulkheads, and embankments therefor; 
hold and save the United States free from 
damages that may result from construction and 
maintenance of the project; accomplish without 
cost to the United States alterations and 
relocations as required in sewer, water supply, 
drainage, and other utility facilities; establish 
regulations concerning discharge of untreated 
sewage, garbage, and other pollutants in the 
waters of the anchorage by users thereof, which 
regulations shall be in accordance with 
applicable laws or regulations of Federal, State, 
and local authorities responsible for pollution 
prevention and control; assure full responsibility 
for all project costs in excess of the Federal cost 
limitation of $1,000,000. City of Bethel signed the 
local cooperation agreement on June 5, 1973. 
Terminal facilities. The seawall at Bethel has 
facilities for loading and unloading barges. Other 
vessels must be tied to shore or pulled onto the 
riverbank. 
Operations and results during fiscal year. 
Regular funds, new work: Project-owned 
hydraulic dredge was acquired by the Alaska 
District and sent to Nome, Alaska, to aid in clearing 
the storm-damaged entrance channel and 
harbor. 
Condition at end of fiscal year. Construction 
was not initiated due to inability of local interests 
to acquire lands, easements, and rights-of-way 
and the project was deauthorized in April 1975. 
3. COOK INLET SHOALS, ALASKA 
Location. This navigation obstruction was 
reported at 61�12'03" north latitude and 
150004'48" south longitude at an elevation -19 feet 
below mean lower low water (MLLW). This is on 
the eastern edge of the main deepdraft channel to 
the Port of Anchorage about 3-4 miles southwest 
of the city. 
Previous project. None. A study of a shoaling 
condition found at -15 MLLW in this portion of 
Cook Inlet was initiated in FY 1971 and is 
scheduled for completion in FY 1977. 
Existing project. During the summer of 1975 
Congress directed the Corps of Engineers to 
remove the -19 foot shoal- area to insure timely 
completion of the oil pipeline project, and appropriated 
$1,000,000 for the work (Amendment 
to FY 1975 Supplemental Appropriation Bill). 
Local cooperation. Local citizens committee advocated 
removal of the -19 foot shoal. 
Terminal facilities. None. This area is part of 
the channel leading to the Port of Anchorage. 
Operations and results during fiscal year. During 
FY 1975 a total of $85,000 was allocated to 
survey and sample the Cook Inlet Shoals. A $5,- 
000 survey contract was awarded and completed 
in June 1975. The contract to sample the shoal 
was awarded in June 1975, and $72,452 of the 
$80,000 was obligated. 
Condition at end offiscal year. Dredging will be 
completed in FY 1976. 
40-2

ALASKA DISTRICT 
4. DILLINGHAM HARBOR, ALASKA 
Location. At head of Nushagak Bay, an arm of 
Bristol Bay, on right bank of Nushagak River just 
below its confluence with Wood River; about 470 
miles northeasterly of Dutch Harbor and 300 
miles southwest of Anchorage, Alaska. (See Coast 
and Geodetic Survey Chart 9052.) 
Existing project. A small-boat basin 230,000 
square feet in area with a depth of 2 feet above 
mean lower low water along Scandinavian Creek; 
with entrance channel 1,100 feet long and 40 feet 
wide in Scandinavian Creek; and a sheet pile sill 
across the basin outlet with a top elevation of 7 
feet above mean lower low water. During design 
stage the project was revised to include a rock sill 
with adjacent scour-protection blankets and the 
embankment was relocated to include a berm 
between the basin and the embankment. Tidal 
range between mean lower low water and mean 
higher high water is 19.8 feet. Extreme range is 
30.0 feet. (See Table 40-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two docks at the city of 
Dillingham, both privately owned, and a publicly 
owned small-boat float in the project basin. One 
dock is used for salmon-cannery operations; the 
second is an oil handling and bunkering terminal. 
An additional salmon-cannery dock is under construction. 
Small-boat approach and floats were 
installed in small-boat basin in summer of 1963, 
and were demolished by winter ice movement. 
New floats were installed May 1971, and are 
removed before fall freezeup and replaced each 
spring. Cargo and passengers from ocean vessels 
are lightered from the anchorage just below Snag 
Point, and are unloaded at the docks or in the 
small-boat basin. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
Regular funds, maintenance: Government 
plant and hired labor performed maintenance 
dredging from July 1 through September 1974 
and June 15 through June 30, 1975. 61,114 cubic 
yards of material were dredged this fiscal year. 
Condition at end of fiscal year. Project was 
started in September 1960 and completed in July 
1962. (For further details see Annual Report for 
1970.) 
5. HOMER HARBOR, ALASKA 
Location. In Kachemak Bay, on Kenai Peninsula, 
152 miles by water southwest of Anchorage. 
Harbor site is land based near the extremity of 
Homer Spit which varies to one-quarter mile in 
width and extends 4.5 miles southeasterly from 
the mainland. (See Coast and Geodetic Survey 
Charts 8554 and 8531.) 
Previous projects. See page 1593 of Annual 
Report for 1964. 
Existing project. Provides for sheltered smallboat 
harbor, relocated and based within Homer 
Spit about 10 acres in area, with a 2.75-acre 
berthing area 14 feet deep and a 7.25-acre 
anchorage area 15 feet deep, below mean lower 
low water; a north entrance channel; protected by 
a main rock breakwater 1,018 feet long and secondary 
rock breakwater 238 feet long. Tidal range 
between mean lower low and mean higher high 
water is 18.1 feet, with an extreme range of 30.4 
feet. (See Table 40-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One publicly owned and 
operated wharf capable of handling oceangoing 
vessels serves for passengers and general cargo. 
Small-boat facilities in basin area include publicly 
owned mooring floats, a publicly owned wharf, 
and an industrial wharf. A separate basin with 
unloading facilities for barges and small boats is 
being constructed by private interests. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Regular funds, maintenance: Maintenance 
dredging of the entrance channel to project depth 
and construction of a 175-foot wooden beach groin 
were accomplished July and August 1974. The 
beach groin was destroyed by a storm in October 
1974. 
Condition at end of fiscal year. The harbor for 
the original project was started in September 
1961, completed in June 1962 and essentially 
destroyed by the March 27, 1964 earthquake. 
Emergency repair work, which included raising 
the first leg of the breakwater, was accomplished 
July and August 1964. The harbor was restored 
by construction of an extension to the breakwater, 
removal of part of the original breakwater to 
form an entrance, removal of basin material inland, 
and disposal of the material to form a 
protective berm around the landward side of the 
basin. Restoration work began August 1964 and 
was completed March 1965. Expansion of the 
harbor began November 1964 and was completed 
March 1965. Local interests extended length of 
basin and protective berm by 700 feet in fiscal 
years 1968 to 1970, with supervision by the Corps 
to insure the integrity of the Federal project. 
6. HOONAH HARBOR, ALASKA 
Location. Hoonah is located on the eastern 
shore of Port Frederick, a deep tidal fjord on the 
northeastern shore of Chichagof Island in 
southeastern Alaska. The city is 70 miles west of 
40-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Juneau. (See National Geodetic Survey Charts 
8202 and 8302.) 
Existing project. Consists of an authorized 
small-boat basin to be 15.1 acres in extent, 11.1 
acres to a depth of 16 feet below mean lower low 
water (MLLW) and 4.0 acres to a depth of 10 feet 
below MLLW bedrock conditions permitting; 
with an entrance channel 150 feet wide and 800 
feet long (with provision for future lengthening to 
1200 feet); three rubblemound breakwaters 250, 
1,040, and 1,500 feet long; and a rubblemound 
diversion dike 2,215 feet long. Tidal range 
between MLLW and mean higher high water is 
14.8 feet. Extreme tidal range is 25 feet. Estimated 
project cost is $6,008,400 (July 1974), including 
$5,980,000 Corps of Engineers funds, $4,- 
600 Coast Guard funds, and $23,800 non-Federal 
cost. (See Table 40-B for authorizing legislation.) 
Local cooperation. Local interests must 
provide, without cost to the United States, all 
lands, easements, and rights-of-way required for 
construction and subsequent maintenance of the 
project, and for aids to navigation upon the request 
of the Chief of Engineers; hold and save the 
United States free from damages that may result 
from the construction and maintenance of the 
project; provide and maintain, without cost to the 
United States, adequate berthing area and 
dredged depth necessary for mooring facilities; 
and provide shore facilities including, a public 
landing with suitable supply facilities open to all 
on equal terms; accomplish, without cost to the 
United States, such utility or other relocations as 
necessary for project purposes; and establish 
regulations concerning discharge of untreated 
sewage, garbage, and other pollutants in the 
waters of the harbor by the users thereof, which 
regulations shall be in accordance with 
applicable laws or regulations of Federal, State, 
and local authorities responsible for pollution 
prevention and control. 
Terminal facilities. Publicly owned facilities 
are two general cargo docks, a ferry dock and a 
small boat float attached to one of the cargo docks. 
Privately owned facilities are one oil dock and one 
industrial-oil dock. Facilities are not sufficient or 
suitable for moorage of more than a small portion 
of the resident and transient commercial fishing 
vessels operating at Hoonah. The authorized harbor 
will provide the necessary moorage. 
Operations and results during fiscal year. 
Preparation of the final project design memorandum 
was initiated. 
Conditions at end of fiscal year. Preconstruction 
engineering is in progress, i.e. Phase II GDM. 
7. HUMBOLDT HARBOR, ALASKA 
Location. Humboldt Harbor is an indentation 
in the northwestern shore of Popof Island in the 
Shumagin Islands of southwestern Alaska. The 
harbor is just south of the city of Sand Point, 
Alaska, 350 miles southwest of Kodiak and 250 
miles east of Dutch Harbor. (See Coast and 
Geodetic Survey Chart 8700.) 
Existing project. Construction of two 
rubblemound breakwaters aggregating about 
1,635 feet in length and providing a protected 
area of about 16.6 acres; an entrance channel 
between breakwaters, 120 feet wide, 18 feet deep, 
and about 1,200 feet long; and a rubblemound 
diversion dike, about 1,175 feet long, with a diversion 
channel about 775 feet long. Local interests 
are responsible for dredging of basin and provision 
of mooring facilities. Tidal range between 
mean higher high and mean lower low water is 
7.3 feet with an extreme range of 14.5 feet. Estimated 
project cost is $4,413,000 (July 1974), including 
$4,400,000 Corps of Engineers funds, $3,- 
000 Coast Guard funds, and $10,000 non-Federal 
cost. (See Table 40-B for authorizing legislation.) 
Local cooperation. Provide without cost to the 
United States, all lands, easements, and rights-ofway 
required for construction and subsequent 
maintenance of the project and for aids to navigation. 
Hold and save the United States free from 
damages that may result from the construction 
and maintenance of the project. Provide and 
maintain without cost to the United States an adequate 
berthing area of suitable depth and 
necessary mooring facilities and utilities, including 
a public landing with suitable supply 
facilities, open to all on equal terms. Accomplish 
without cost to the United States such utility or 
other relocations as may be necessary for project 
purposes. Establish regulations concerning discharge 
of untreated sewage, garbage, and other 
pollutants into the waters of the harbor by the 
users thereof, which regulations shall be in accordance 
with applicable laws or regulations of 
Federal, State, and local authorities responsible 
for pollution prevention and control. 
Terminal facilities. There are three docks in 
Humboldt Harbor; all are privately owned. Two 
are in the city of Sand Point: a deep-draft wharf 
for transfer of general cargo and offloading of 
petroleum products, with freight containerized 
in vans and cargo handling by ship's gear; and an 
oil dock, for refueling the fishing fleet and miscellaneous 
small boats. An industrial wharf is 
located at Sand Point spit, south of the proposed 
project. Facilities are adequate for existing deepdraft 
commerce, but inadequate for the fishing 
fleet operating in the area. 
Operations and results during fiscal year. 
Regular funds, new work: Contract was awarded 
June 1975 for construction of the project. State 
of Alaska provided $865,000 for dredging of 
basin, including design and administrative costs. 
This dredging forms part of awarded contract. 
40-4

ALASKA DISTRICT 
Condition at end of fiscal year. Construction 
contract has been awarded but no on-site work 
has been accomplished. 
8. KAKE HARBOR, ALASKA 
Location. Kake Harbor is located in the city of 
Kake, on the northwest corner of Kupreanof 
Island in southeastern Alaska, 39 air miles west 
of Petersburg, Alaska, and 850 water miles 
northwesterly of Seattle, Washington. (See Coast 
and Geodetic Chart 8201.) 
Existing project. The authorized project consists 
of a 1,580-foot-long west breakwater and a 
900-foot-long south breakwater, enclosing a 7- 
acre berthing area. Tidal range between mean 
lower low and mean higher high water is 14.0 
feet, with an extreme range of 22 feet. Estimated 
project cost is $3,720,000 (October 1975), including 
$3,710,000 Corps of Engineers funds, $6,- 
000 Coast Guard funds, and $4,000 non-Federal 
cost. (See Table 40-B for authorizing legislation.) 
Local cooperation. Local interests are required 
to provide, without cost to the United States, all 
lands, easements, and rights-of-way required for 
construction and maintenance of the project and 
for aids to navigation; hold and save the United 
States free from damages that may result from 
the construction and maintenance of the project; 
provide and maintain, without cost to the United 
States, necessary mooring facilities and utilities 
including a public landing with suitable facilities 
open to all on equal terms; accomplish, without 
cost to the United States, such utility or other 
relocations or alterations as necessary for project 
purposes; and establish regulations concerning 
discharge of untreated sewage, garbage, and 
other pollutants in the waters of the harbor by the 
users thereof, which regulations shall be in accordance 
with applicable laws or regulations of 
Federal, State, and local authorities responsible 
for pollution prevention and control. The city of 
Kake, as project sponsor, by resolution dated 
September 30, 1966, has indicated a willingness 
and ability to cooperate with all these conditions 
except water pollution. No problems are anticipated 
in securing an agreement prior to construction 
on control of discharge of sewage, garbage, 
and other pollutants in the waters of the 
anchorage by users thereof. 
Terminal facilities. At Kake, a publicly owned 
wharf with seaplane float for float equipped airplanes 
and shallow-draft vessels, is located within 
area of proposed basin. At cannery 1 mile from 
city, there are two privately owned deep-draft 
piers: one for cargo, open to all local boat 
owners, the second for fuel, including a float for 
fueling small boats. At Portage Cove, there is one 
publicly owned small-boat float. Facilities are 
considered adequate for present commerce, with 
the exception of the following deficiencies in 
small-boat facilities: the complete lack of 
protection in the directions of the most severe 
storms; shallow water at Portage Cove float and 
its approaches; and transportation problems 
between city and present small-boat float at Portage 
Cove. 
Operations and results during fiscal year. 
Foundation and materials investigation and survey 
were partially completed and are scheduled 
for completion in FY 1976. 
Condition at end of fiscal year. Preconstruction 
engineering is in progress. 
9. "KASILOF RIVER, ALASKA 
Location. Kasilof River is located on the easterly 
shore of Cook Inlet approximately 10 miles 
south of Kenai in southcentral Alaska. The project 
site incorporates the lower reaches of the river 
and the extension of the river into salt water. 
Existing project. The river is navigable to commercial 
fishing craft for approximately 3 miles 
above the mouth. The mouth of the river provides 
storm refuge to 24 resident and up to 200 transient 
small craft. Boats entering or leaving the 
river must await higher tides to maneuver over 
rocks located at the river mouth. An estimated 25 
rocks, with the largest being 15 feet at its greatest 
dimension, obstructed all-tide access and 
presented the primary hazards to navigation. 
Furthermore, navaids marking the entry were 
inadequate. (See Table 40-B for authorizing 
legislation.) 
Local cooperation. Fully complied with by the 
City of Soldotna and the State of Alaska. Local 
cooperation prior to construction included provision 
of lands, easements and rights-of-way by the 
State and, upon completion of the project, 
assumption of operation and maintenance by the 
City of Soldotna. The State also has constructed 
shore based facilities. 
Terminal facilities. As constructed by the State 
Division of Waters & Harbors, terminal facilities 
include a steel-sheeted bulkhead with gravel 
backfill and parking area, access road, unloading 
facilities, storage area and fuel and water services. 
Prime object of the facility is to provide a 
loading and unloading terminal for commercial 
fishing. 
Operations and results during fiscal year. 
Regular funds, new work: Rock removal project 
will be completed by Corps of Engineers tin 
August 1975 when 35 rocks will have been removed 
from the river entrance channel. Shore based 
and terminal facilities construction is underway 
by the State of Alaska and scheduled for completion 
as soon as possible following spring of 1976 in 
40-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
order to have the facilities available for use by 
commercial fishing craft during open season in 
summer of 1976. U.S. Coast Guard has 
operational plan for revamping and installation 
of new, more comprehensive river entrance 
navaids in the spring of 1976. 
Condition at end of fiscal year. Hazards to navigation 
will have been removed by the end of 
August 1975 and the terminal facilities provided 
by the State will be completed in late spring of 
1976. 
10. METLAKATLA HARBOR, ALASKA 
Location. Metlakatla is located in the southern 
portion of Port Chester, a small bay on the 
northwest coast of Annette Island in southeastern 
Alaska, 18 miles south of Ketchikan. (See Coast 
and Geodetic Charts 8074, 8075, and 8102.) 
Existing project. Consists of two small-boat 
basins. Existing basin is 2.18 acres in extent with 
a depth of 10 feet below mean lower low water, 
protected by a rubblemound breakwater 900 feet 
long. Proposed basin consists of two rubblemound 
breakwaters, 2,160 and 600 feet long, and an entrance 
channel and maneuvering area, 1,000 feet 
long, 100 feet wide, dredged to a depth of 15 feet 
below mean lower low water. Tidal range 
between mean lower low water and mean higher 
high water is 14.6 feet, with an extreme range of 
24 feet. Estimated project cost of proposed basin 
is $3,802,000 (October 1975) including $3,750,000 
Corps of Engineers funds, $6,000 Coast Guard 
funds, and $46,000 non-Federal cost. (See Table 
40-B for authorizing legislation.) 
Local cooperation. Fully complied with on existing 
basin. For proposed basin, local interests 
must provide without cost to the United States all 
lands, easements, rights-of-way, and quarry 
rights required for construction and subsequent 
maintenance of the project and for aids to navigation 
upon the request of the Chief of Engineers; 
hold and save the United States free from 
damages that may result from the construction 
and maintenance of the project; provide and 
maintain without cost to the United States adequate 
berthing depths, surface area, and 
necessary mooring facilities and utilities, including 
a public landing with suitable supply 
facilities open to all on equal terms; accomplish 
without cost to the United States such utility or 
other relocations as necessary for project purposes; 
and establish regulations prohibiting discharge 
of pollutants into the waters of the harbor 
by users thereof, which regulations shall be in accordance 
with applicable laws or regulations of 
Federal, State, and local authorities responsible 
for pollution prevention and control. 
Terminal facilities. Publicly owned facilities 
are one general-cargo dock, one barge ramp, and 
a small-boat float system in existing basin. 
Privately owned facilities are one oil pier and one 
industrial wharf. Facilities are not adequate for 
mooring the commercial fishing vessels 
operating from Metlakatla. Existing protected 
harbor area is fully utilized. 
Operations and results during fiscal year. 
Regular funds, new work: Preparation of final 
design for proposed basin initiated. Regular 
funds, maintenance: No activity in FY 1975. 
Condition at end of fiscal year. Existing basin 
was constructed April through June 1956. 
Preconstruction planning for proposed basin is in 
progress. 
11. NINILCHIK HARBOR, ALASKA 
Location. At mouth of Ninilchik River in Cook 
Inlet, at the community of Ninilchik, Alaska, 
about 40 miles upcoast from Homer and 112 miles 
southwest of Anchorage. (See Coast and Geodetic 
Survey Chart 8554.) 
Existing project. A small-boat basin 320 feet 
long by 150 feet wide dredged to elevation of 2 feet 
above mean lower low water, with an approach 
channel 400 feet long and 50 feet wide dredged to 
an elevation of 9 feet above mean lower low water; 
protected by a pile jetty 410 feet long. Project was 
modified in design stage to delete pile jetty and 
revise harbor dimensions to 400 feet long by 125 
feet wide, and was completed in November 1961. 
Modification, including river channel diversion, 
two armor rock jetties, and beach protection, was 
accomplished 1967 and 1969. Range between 
mean lower low water and mean higher high 
water is 19.1 feet, with an extreme range of 33.5 
feet. (See Table 40-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, limited to 
shallow-draft vessels and accessible from Cook 
Inlet only at half-tide or higher, are: a cannery 
dock along Ninilchik River available for 
offloading fish, and small-boat floats in project 
basin, provided by State of Alaska. Other 
supplies are landed on beach or brought by road 
from deep-draft ports in the vicinity. Facilities 
are inadequate for the number of boats presently 
using harbor. Expansion of facilities would require 
construction of additional protected harbor 
area. 
Operations and results during fiscal year. 
Regular funds, maintenance: Maintenance 
dredging of the harbor and entrance channel was 
accomplished with 5,495 cubic yards removed in 
April and May, 1975. Repair of the log revetment 
was also accomplished at this time. 
40-6

ALASKA DISTRICT 
Condition at end of fiscal year. Construction 
was initiated in October 1961 and November 
1961. Modifications to reduce sedimentation and 
prevent beach erosion on the seaward sandspit 
were completed November 1969. Emergency 
dredging was accomplished June 1970 and June 
1971. (For further details see Annual Report for 
fiscal year 1970.) 
12. NOME HARBOR, ALASKA 
Location. At mouth of Snake River at the city of 
Nome, Alaska, on northerly shore of Norton 
Sound, an arm of Bering Sea. It is a shallow open 
roadstead, 581 nautical miles north of Dutch Harbor 
and 545 air miles northwest of Anchorage. 
(See Coast and Geodetic Survey Charts 9302 and 
9380.) 
Existing project. Provides for two jetties, the 
easterly 951 and the westerly not exceeding 676 
feet long, at mouth of Snake River; a channel 8 
feet deep at mean lower low water, 75 feet wide, 
from Norton Sound through Snake River to 
mouths of Bourbon and Dry Creeks, in city of 
Nome, ending in a turning basin of the same 
depth, 250 feet wide and 600 feet long; revetting 
banks of rivers; and protecting all existing waterfront 
improvements on easterly beach by means 
of rock-mound seawall 3,350 feet long extending 
easterly from east jetty. Project has been completed 
except extension of jetties beyond present 
400 and 240 feet, which is classified inactive. 
Range between mean lower low water and mean 
higher high water is 1.6 feet and extreme tidal 
range is 7.5 feet, but water levels are influenced 
more by wind than tide. Levels of 5 feet below 
mean lower low water have been observed during 
offshore winds, and a level of 14 feet above mean 
lower low water has been observed during a 
southerly storm. (See Table 40-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. Total 
actual costs for all requirements of local cooperation 
under terms of original project authorization 
are $2,500 annually. Local interests also maintain 
seawall. 
Terminal facilities. Cargoes and passengers 
from ocean vessels are lightered to and from 
shore a distance of about 2 miles. Traffic enters 
dredged channel and is handled over revetment, 
where lighterage company has transfer facilities 
which are open to the public. Facilities considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Regular funds, maintenance: Maintenance 
dredging by Government plant and hired labor 
was accomplished throughout the ice-free season. 
Contract dredging was also done in the winter 
months to repair damage from a severe fall storm 
in 1974 in the Bering Sea. A Government-owned 
pipeline dredge was sent to assist the permanently 
assigned clamshell dredge in maintenance of 
the turning basin. Approximately 80,000 cubic 
yards of material were removed from the entrance 
channel and turning basin. 
Condition at end of fiscal year. Construction of 
original 335- and 460-foot jetties and revetments 
was completed in 1923. Reconstruction of jetties 
with concrete to modified lengths of 240 and 400 
feet was completed in 1940. Dredging entrance 
channel and original 200- by 250-foot basin was 
completed in 1922. Construction of seawall was 
completed June 1951. Dredging 400-foot extension 
of basin was commenced in 1949 and was 
completed in 1951, with exception of small areas 
in northerly portion of small-boat harbor extension 
and around Corps marine ways which are not 
required. Jetty repairs were made in 1954 and 
July through October 1965. 
13. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 40-C. 
14. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (Preauthorization). 
Fiscal year costs were: $44,040 for Bar Point 
Harbor, Ketchikan, $28,656 for Haines Small- 
Boat Harbor, $18,118 for Unalaska Harbor, $11,- 
169 for Seldovia Harbor, $3,816 for Wrangell 
Small-Boat Harbor. (See Section 2 for Bethel 
Harbor, Section 9 for Kasilof River.) 
Flood Control 
15. CHENA RIVER LAKES, ALASKA 
Location. In the vicinity of Fairbanks, Alaska, 
and encompassing the Tanana River, Chena 
River, Little Chena River, and their tributaries. 
(See USGS map Fairbanks C1, D1, D2, and Big 
Delta D6.) 
Existing project. Provides for a dam on the 
Chena River, 17 miles east of Fairbanks, a dam on 
the Little Chena River about 11 miles upstream 
from its confluence with the main Chena River, 
and a 22-mile levee system along the Tanana and 
Chena Rivers. Estimated Federal cost (October 
1975) is $186 million, and estimated non-Federal 
cost is $15,490,000. (See Table 40-B for authorizing 
legislation. 
Local cooperation. Local interests are required 
to hold and save the United States free from 
40-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
damages due to construction of the levees and 
drainage works; provide without cost to the 
United States, all lands, easements, and rights-ofway 
necessary for the construction of the levee 
and interior drainage works; accomplish without 
cost to the United States, all necessary relocations 
of buildings, streets, and utilities as required for 
the levee project; maintain and operate the levee 
system and interior drainage works after completion 
in accordance with regulations prescribed by 
the Secretary of the Army. The North Star 
Borough formally signed this agreement on 1 
February 1973. 
Operations and results during fiscal year. 
Regular funds, new work: Foundation excavation 
was completed for the major portion of Moose 
Creek Dam on the Chena River. 
Condition at end of fiscal year. Construction of 
the project was initiated June 26, 1973. Phase I of 
Tanana levee is complete. Design of interior 
drainage channels B and C is complete. Phase I 
Moose Creek Dam foundation excavation is complete. 
Design of remainder of levee system and interior 
drainage system is near completion. 
Construction contract advertising for additional 
Moose Creek Dam construction is scheduled for 
FY 1976. 
16. GOLD CREEK, ALASKA 
Location. Rises in coastal mountains about 4 
miles east of Juneau and flows through western 
section of city of Juneau and empties into Gastineau 
Channel. Its total length is about 5 miles 
and it drains an area of about 10.2 square miles. 
(See Coast and Geodetic Survey Chart 8235.) 
Previous projects. For details see page 1608 of 
Annual Report for 1964. 
Existing project. A reinforced-concrete channel 
lining 1,717 feet long for portion of Gold Creek 
passing through city of Juneau together with 
necessary intake and downstream energy dissipating 
structures. Project will provide protection 
to city of Juneau from a project flood of 4,800 
cubic feet per second. Project modified in 1962 
reinforcing concrete lining of channel, removal of 
material to form a catch basin, construct concrete 
weir or check dam and place derrick stone for 
channel protection at head of channel. (See Table 
40-B for authorizing legislation.) 
Local cooperation. Fully complied with. City of 
Juneau contributed $1,900 for repair of existing 
channel invert structures. 
Operations and results during fiscal year. 
Regular funds, new work: Contract to repair 
600 feet existing channel, lining was awarded on 
April 25, 1974, and work was completed May, 
1975. 
Condition at end of fiscal year. Construction of 
2,080 linear feet of reinforced concrete-lined 
channel was commenced in April 1957 and completed 
in March 1958. Establishment of staff 
gages in the structure for engineering research 
purposes was accomplished in fiscal year 1960. 
Rehabilitation of channel lining and construction 
of a stilling basin was accomplished from March 
to June 1962. Four test areas in the channel, each 
25 feet long, were included to test materials for 
cohesion and resistance to abrasion. Two of the 
four test areas installed in 1962 deteriorated and 
are considered failures. Supplemental design 
memorandum was completed and approved in 
February 1967. As a result of this, a repair contract 
was awarded in April of 1974. Work was 
completed May 1975. 
17. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
No activity in FY 1975. 
18. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 40-D. 
19. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities--repair, 
flood fighting, and rescue work (Public Law 99, 
84th Congress, and antecedent legislation). 
Federal costs for fiscal year 1975 were $29,375 
for advance preparation and $31,882 for 
emergency operations. 
Multiple-Purpose Projects Including Power 
20. SNETTISHAM, ALASKA 
Location. At mouth of Speel River, between 
Crater Lake to the west and Long Lake to the 
north, 28 nautical miles southeast of Juneau, 
Alaska. (See Coast and Geodetic Survey Chart 
8227.) 
Existing project. Snettisham is a two-stage 
power project. The initial stage includes tapping 
Long Lake and Crater Lake, construction of an 
underground powerhouse, installation of three 
power units and construction of a transmission 
line to Juneau, Alaska. The ultimate stage would 
provide a dam at the head of Long Lake to increase 
the energy capability of Long Lake. The 
Long Lake Dam is in a "Deferred" status. From 
Long Lake (elevation 815'), the water is 
40-8

ALASKA DISTRICT 
transported through an approximately horizontal 
tunnel 8,400 feet long and a 1,400-foot 
penstock dropping at a 46 degree angle to the underground 
powerhouse at tidewater to drive two 
turbines with a generating capacity of 46,700 
kilowatts. Power from two generators to be 
supplied to Juneau by 138 kilovolt overhead 
transmission lines except for a submarine cable 
traversing Taku Inlet. Crater Lake phase of initial 
construction provides for tapping Crater 
Lake (elevation 1,022') to drive a third turbine to 
be installed in the underground powerhouse 
(constructed under the Long Lake phase of initial 
construction) to provide an additional generating 
capacity of 27,000 kilowatts. Estimated cost of initial 
stage construction is $111,000,000 (October 
1975). The project will be turned over to the 
Alaska Power Administration for operation and 
maintenance. (See Table 40-B for authorizing 
legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Regular funds, new work: During fiscal year 
1975, the restoration of the Salisbury Ridge portion 
of the transmission line was completed. TThe 
line continued to suffer numerous outages during 
the winter months. Negotiations have been completed 
with Commonwealth Associates, Inc. for 
design of the relocation of the Salisbury Ridge 
line. Relocation should be completed by October 
1976. 
Condition at end of fiscal year. Construction 
was initiated 11 July 1967. The Long Lake phase 
of the first stage of the project is essentially complete. 
Temporary restoration of the damaged 
transmission line over Salisbury Ridge is complete 
with power-on-line. Permanent replacement 
or relocation of this section of line is under 
study with completion scheduled for October 
1976. 
21. BRADLEY LAKE, ALASKA 
Location. Near head of Kachemak Bay near 
southwestern end of Kenai Peninsula, Alaska, 
about 100 air miles south of Anchorage and 25 
miles northeast of Homer. (See Coast and 
Geodetic Survey Chart 8552.) 
Existing project. Provides for a main dam raising 
waters of Bradley Lake from an elevation of 
1,090 feet to elevation 1,196 feet; two small dams 
to divert water from nearby drainages; a power 
tunnel, surge tank, and penstock to deliver water 
to a powerhouse located at tidewater, with an installed 
capacity of 64,000 kilowatts and transmission 
facilities to serve the Cook Inlet area. 
Latest cost estimate for new work (1971) is $152 
million. (See Table 40-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Regular funds, new work: A technical update of 
the Bradley Lake Project was initiated by AE 
contract with Sverdrup and Parcel and 
Associates on 18 June 1974 for a total cost of $49,- 
375. Work under this contract is scheduled to be 
completed in November 1975. An AE contract for 
assessment of the effects of the project on environmental 
and recreational resources is being 
prepared for advertisement in early FY 1976. 
Condition at end of fiscal year. Reappraisal of 
the economic and financial feasibility was initiated 
in March 1974 because of renewed interest 
in the project resulting primarily from the 
nations awareness of energy shortages. The 
Federal Power Commission is in the process of 
preparing an update of power values. When the 
two sets are received-one for coal and one for a 
natural gas alternative-they will be used to 
bring the economic analysis up-to-date. The investigation 
is being coordinated with the Alaska 
Power Administration, Department of the Interior, 
the potential marketing agency. 
General Investigations 
22. SURVEYS 
Fiscal year costs of $563,164 for surveys include 
$97,000 for navigation studies, $421,964 for 
flood control studies, $4,700 for special studies, 
$30,000 for coordination studies and $9,500 for 
review of deauthorization. 
23. COLLECTION AND STUDY OF 
BASIC DATA 
Technical assistance, information, flood plain 
management guidance and other flood plain 
management services have been provided to 
military and nonmilitary Federal agencies, 
State, and local government agencies, local communities, 
and others at a fiscal year cost of $133,- 
262. Flood plain information reports for Kenai 
River Phase II in the Kenai Peninsula Borough, 
and Resurrection River and Salmon Creek near 
Seward, were prepared and presented at a fiscal 
year cost of $64,294. In addition, special Flood 
Hazard Reports were completed for Ship Creek 
(included in Technical Services), Campbell 
Creek, Chester Creek, and Fish Creek at the fiscal 
year cost of $45,940 (all are located in the 
Anchorage area). Partial studies were under way 
for Eagle-Herbert Rivers in the Juneau area with 
a fiscal year expenditure of $56,377. 
Additional activities included the initiation of a 
Type 15 Study for the Greater Anchorage Area 
Borough. This study is still under way and should 
be completed during FY 76. For completed Flood 
Plain Information Reports see Table 40-E. 
40-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
24. RESEARCH AND DEVELOPMENT 
Work programmed for research and development 
consisted of hydrologic studies. Fiscal year 
costs of these studies were $16,356. 
40-10

ALASKA DISTRICT 
TABLE 40-A 
See 
Section 
in Text Project 
1. Anchorage Harbor, 
Alaska 
2. Bethel Small Boat 
Harbor, Alaska 
3. Cook Inlet Shoals, 
Alaska 
4. Dillingham Harbor, 
Alaska 
5. Homer Harbor, 
Alaska 
6. Hoonah Harbor, 
Alaska 
7. Humboldt Harbor, 
Alaska 
8. Kake Harbor, 
Alaska 
9. Kasilof River, 
Alaska 
10. Metlakatla Harbor, 
Alaska 
11. Ninilchik Harbor, 
Alaska 
12. Nome Harbor, 
Alaska 
(Contrib. Funds) 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 1 
Approp. 
Cost 
New Work 
Approp. 
Cost * 
New Work 
Approp. 
Cost 
Maint. 1 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 1 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 1 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 1 
Approp. 
Cost 
Contrib. Fund 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 1 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 1 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Total Cost to 
FY 72 FY 73 FY 74 FY 75 June 30, 1975 
492,116 
337,728 
297,900 
188,008 
129,814 
136,052 
13,200 
12,270 
49,600 
1,041 
94,700 
18,110 
11,152 
11,152 
178,122 
165,470 
133,100 
207,795 
221,345 
362,263 
17,750 
120,150 
104,501 
202,276 
144,698 
6,000 
54,559 
-37,000 
72,027 
37,000 
11,812 
4,012 
56,406 
69,743 
167,749 
170,654 
194,821 
240,023 
24,510 
108,295 
126,795 
185,173 
114,681 
57,000 
55,754 
464,000 
86,015 
47,000 
39,521 
5,500 
18,776 
45,000 
31,234 
10,420 
18,220 
152,781 
150,472 
307,780 
299,084 
- 428,720 
- 428,720 
139,113 1,108,118 
141,422 1,108,118 
- 1,348,240 
- 1,348,240 
522,087 3,747,221 
524,971 3,741,409 
- 125 
- 125 
40-11 
- 533,235 
- 533,235 
569,153 2,576,033 
566,221 2,560,613 
-581,301 250,797 
-138,000 250,797 
80,000 80,000 
5,000 5,000 
5,000 5,000 
- 548,790 
- 548,790 
163,284 1,112,674 
157,376 1,105,774 
- 1,509,677 
- 1,509,677 
61,420 1,004,738 
190,420 1,004,738 
- 67,974 
- 67,974 
75,000 132,000 
64,593 120,347 
200,000 719,600 
406,658 548,273 
- 154,700 
15,629 154,700 
67,348 109,848 
91,072 109,848 
75,000 406,470 
69,406 387,110 
- 39,901 
- 39,901 
- 40,000 
- 40,000

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 40-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 
Maint. 1 
Contrib. 2,500 
Cost 2,500 
15. Chena River Lakes, New Work 
Alaska Approp. 1,291,000 
Cost 1,248,658 
16. Gold Creek, New Work 
Alaska Approp. - 
Cost - 
Maint. ' 
Approp. 
Cost 
20. Snettisham, New Work 
Alaska Approp. 22,260,700 
Cost 20,893,474 
21. Bradley Lake, New Work 
Alaska Approp. 
Cost 844 
1. Includes applicable portion of Reconnaissance and 
Condition Surveys appropriations and costs. 
FY 73 FY 74 FY 75 June 30. 1975 
2,500 
2,500 
8,965,000 
9,447,883 
200,000 
57,158 
930 
930 
3,818,000 
5,814,665 
25,000 
3,109 
2,500 
2,500 
11,650,000 
11,783,654 
130,244 
2,500,000 
3,805,964 
67,000 
88,891 
132,500 
132,500 
24,339,000 
24,275,380 
888,604 
876,006 
5,301 
5,301 
67,540,700 
67,257,346 
241,000 
241,000 
2,500 
2,500 
1,355,000 
852,174 
9,322,000 
7,181,341 
40-12

ALASKA DISTRICT 
TABLE 40-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
July 14, 1960, 
as amended 
(Sec. 107)3 
May 21, 1975 
July 3, 1958 
July 3, 1958 
Aug. 19, 19644 
Oct. 27, 1965 (Sec 201) 
(Auth. Oct 12, 1972) 
Oct. 27, 1965 (Sec 201) 
(Auth. Sep. 29, 1970) 
Aug. 13, 1968 
July 14, 1960 
as amended 
(Sec. 107) 5 
Mar. 2, 1945 
Oct. 27, 1965 (Sec 201) 
(Auth. Oct. 12, 1972) 
ANCHORAGE HARBOR, ALASKA 
(See Section 1 of Text) 
Deep water harbor, adjacent to docks, dredge to 35 feet 
below mean lower low water, protected by two jetties.' 
BETHEL SMALL BOAT HARBOR, ALASKA 
(See Section 2 of Text) 
Construct 7,700-foot-long small boat harbor and entrance 
channel by deepening, widening, and straightening the 
upper 6,800 feet of Brown's Slough. 
COOK INLET SHOALS, ALASKA 
(See Section 3 of Text) 
Sampling of shoals material and underwater terrain and 
removal of shoals from Inlet. 
DILLINGHAM HARBOR, ALASKA 
(See Section 4 of Text) 
Basin 230,000 square feet in area with depth of 2 feet 
above mean lower low water along Scandinavian Creek, 
with entrance channel 1,100 feet long and 40 feet wide. 
HOMER HARBOR, ALASKA (See Section 5 of Text) 
Basin 2.7 acres in area with depth of 12 feet below mean 
lower low water, and rock breakwater 1,260 feet long. 
Relocation and rehabilitation of project destroyed by 
March 27, 1964 earthquake, by construction of basin 10 
acres in area with 12-foot depth over 2.75 acres and 
15-foot depth over 7.25 acres protected by rock breakwaters 
1,018 feet and 238 feet long. 
HOONAH HARBOR, ALASKA (See Section 6 of Text) 
Entrance channel, a rubble-mound breakwater and diversion 
dike and two rubble-mound breakwaters inclosing a 15.1 
acre harbor area. 
HUMBOLDT HARBOR, ALASKA (See Section 7 of Text) 
Basin 16.6 acre mooring area inclosed by two breakwaters, 
a 1,050-foot north rock breakwater and a 600-foot south 
rock breakwater, an entrance channel 150 feet wide by 
800 feet long to a depth of 18 feet; a 1,060-foot rubblemound 
diversion dike and a 200-foot diversion channel. 
KAKE HARBOR, ALASKA (See Section 8 of Text) 
Basin 7-acre berthing area, 15 feet deep, inclosed by a 
1,580-foot west rock breakwater and a 900-foot south 
rock breakwater. 
KASILOF RIVER, ALASKA (See Section 8 of Text) 
Removal of rocks from river mouth channel to provide 
all-tide access for commercial fishing boats. 
METLAKATLA HARBOR, ALASKA 
(See Section 10 of Text) 
Dredging small boat basin 2.18 acres in extent to a depth 
of 10 feet below plane of MLL water; construction of 
rubble-mound breakwater 900 feet long. 
Improvement consists of entrance channel and two rubblemound 
breakwaters inclosing a 7.0 acre basin. 
H. Doc. 34, 85th Cong., 
1st Sess.2 
Report in Office of Chief 
of Engineers 
Emergency Authorization 
by Conference Report 
Pursuant to Section 203, 
P.L. 93-153 
H. Doc. 390, 84th Cong., 
2d Sess. 2 
H. Doc. 34, 85th Cong., 
1st Sess.2 
H. Doc. 92-200, 92nd 
Cong., 2nd Sess.2 
H. Doc. 91-393, 91st 
Cong., 2d Sess.2 
S. Doc. 70, 90th Cong., 
2nd Sess.2 
Report in Office of 
the Chief of Engineers 
H. Doc. 138, 76th Cong., 
1st Sess. 
S. Doc. 92-64, 92d Cong., 
2d Sess.2 
40-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 40-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
NINILCHIK HARBOR, ALASKA 
(See Section 11 of Text) 
Basin 320 feet long by 150 feet wide with depth of 2 feet 
above mean lower low water, approach channel 400 feet long 
and 50 feet wide with depth of 9 feet above mean lower low 
water, protected by 410-foot jetty. 
NOME HARBOR, ALASKA (See Section 12 of Text) 
Two jetties, easterly 335 feet and westerly 460 feet long 
revetment, channel and basin 200 feet wide and 250 feet 
long. 
Extension of the jetties and enlarging basin to 250 feet 
wide and 600 feet long. 6 
Sea wall. 
CHENA RIVER LAKES, ALASKA 
(See Section 15 of Text) 
Dam and reservoir on the main Chena River, a dam and 
detention reservoir on the Little Chena River, and a 
levee along the north side of the Tanana River. 
GOLD CREEK, ALASKA (See Section 16 of Text) 
Reinforced concrete channel lining 1,717 feet long. 
SNETTISHAM, ALASKA (See Section 20 of Text) 
Multi-purpose dam, with powerhouse and transmission 
facilities. 
BRADLEY LAKE, ALASKA 
(See Section 21 of Text) 
Multi-purpose dam, with powerhouse and transmission 
facilities. 
H. Doc. 34, 85th Cong., 
1st Sess. 2 
H. Doc. 1932, 64th Cong., 
2d Sess.2 
H. Doc. 404, 71st Cong., 
2d Sess. and Rivers and 
Harbors Committee Doc. 
38, 73d Cong., 2d Sess.2 
Report of Chief of Engineers 
dated March 8, 1948. 
H. Doc. 148, 90th Cong., 
2d Sess.2 
H. Doc. 54, 82d Cong., 
1st Sess.2 
H. Doc. 40, 87th Cong., 
1st Sess.2 
H. Doc. 455, 87th Cong., 
2d Sess. 2 
1. Purchase of dredge and deepwater jetties deferred. 4. P.L. 88-451. 
2. Contains latest published map. 5. Authorized by Chief of Engineers August 8, 1974. 
3. Authorized by Chief of Engineers December 30,1969. 6. Extension of jetties classified "inactive". 
40-14 
July 3, 1968 
Aug. 8, 1917 
Aug. 30, 1935 
June 16, 1948 
Aug. 13, 1968 
1954 Flood 
Control Act 
Oct. 23, 1962 
Oct. 23, 1962

ALASKA DISTRICT 
TABLE 40-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 13 of Text) 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 1 
Apoon Mouth of Yukon River, Alaska 2 3 1920 128,896 2,981 
Cordova Harbor, Alaska 2 1973 1,519,234' 523,670 
Craig Harbor, Alaska 2 1974 377,260 84,414 
Douglas Harbor, Alaska 2 1963 282,019 29,430 
Dry Pass, Alaska 2 1960 943,351 28,480 
Egegik River, Alaska 2 1972 4,441 8,218 
Elfin Cove, Alaska 2 1959 154,191 15,523 
Gastineau Channel, Alaska 2 1964 789,461 192,646 
Iliuliuk Harbor, Alaska 2 1941 66,037 - 
Juneau Harbor, Alaska 2 1974 1,381,150 351,623 
Ketchikan Harbor, Alaska 2 1974 1,602,417 267,601 
King Cove Harbor, Alaska 2 1974 2,264,948 
Kodiak Harbor, Alaska 2 1973 1,891,212 s 60,209 
Myers Chuck Harbor, Alaska 2 1970 9,700 - 
Naknek River, Alaska 2 1961 20,789 4,069 
Neva and Olga Straits, Alaska 2 1960 155,009 6,906 
Old Harbor, Kodiak Island, Alaska 2 1972 370,415 139,286 
Pelican Harbor, Alaska 2 1964 369,683 35,732 
Petersburg Harbor, Alaska 2 1972 252,932 91,822 
Port Alexander, Alaska 2 6 1949 17,000 594 
Rocky Pass, Alaska 2 1960 337,668 43,313 
Seldovia Harbor, Alaska 2 1974 1,051,883 7 38,261 
Sergius Whitestone, Alaska 2 1973 1,798,010 3,420 
Seward Harbor, Alaska 2 1973 709,841 8 267,333 
Sitka Harbor, Alaska 2 1973 1,611,009 39,030 
Skagway Harbor, Alaska 2 1972 133,180 81,685 
St. Michael Canal, Alaska 2 3 1916 337,062 560 
Stikine River, Alaska 2 1974 - 89,320 
Valdez Harbor, Alaska 2 1968 647,027 9 240,398 
Wrangell Harbor, Alaska 2 1969 537,020 154,030 
Wrangell Narrows, Alaska 2 1972 3,562,343 607,843 
1. Includes applicable portion of reconnaissance and condition 
survey costs. 
2. Complete. 
3. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st Sess. 
4. Includes $675,700 for rehabilitation. 
5. 
6. 
7. 
8. 
9. 
Includes $594,163 for rehabilitation. 
Inactive. 
Includes $400,000 for rehabilitation. 
Includes $90,026 for rehabilitation. 
Includes $73,000 for rehabilitation. 
40-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 40-D OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to June 30, 1975 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Fairbanks, Alaska 1 1964 310,000 
Fairbanks, Tanana River & Chena Slough, Alaska 2 1943 557,000 
Klutina River, Copper Center, Alaska 2 1973 265,799 
Lowell Creek, Alaska 2 1945 416,382 3 30,771 4 
Salmon River, Alaska 2 1963 37,770 5 6 - 7 8 
Skagway River, Alaska 2 1966 26,385 
Talkeetna, Alaska 1970 
1. Reauthorized, see Section 15, Chena River Lakes. 5. In addition, $7,000 expended from contributed funds. 
2. Completed and transferred to local interests for 6. Includes $34,197 of PWA funds. 
maintenance. 7. In addition, $138,957 expended for emergency flood 
3. In addition, $25,000 expended from contributed funds. activities (1963). 
4. In addition, $12,000 expended from contributed funds. 8. In addition, $27,400 expended from contributed funds. 
TABLE 40-E COMPLETED FLOOD PLAIN 
INFORMATION REPORTS 
Location Requesting Agency Completed Cost 
Kenai River PH II Kenai Peninsula June 1975 $34,069 
Kenai-Soldotna Borough 
Resurrection River Kenai Peninsula June 1975 30,225 
(Bear Creek & Borough 
Salmon Creek) 
Seward 
Chester Creek 1 Greater Anchorage January 1975 25,080 
Anchorage Area Borough 
Campbell Creek 1 Greater Anchorage May 1975 Included with 
Anchorage Area Borough Chester Creek 
Costs 
Fish Creek 1 Greater Anchorage June 1975 20,860 
Anchorage Area Borough 
Ship Creek 1 Greater Anchorage June 1975 Included in 
Anchorage Area Borough Technical 
Services 
1. Special Flood Hazard Report. 
40-16

BOARD OF ENGINEERS 
FOR RIVERS AND HARBORS 
The tables that are referenced in this text 
will appear at the end of the chapter. 
The Board of Engineers for Rivers and 
Harbors is a continuing body created by Section 
3 of the 1902 River and Harbor Act. The 
Board is selected by the Chief of Engineers 
and is comprised of seven senior engineer 
officers. The Deputy Chief of Engineers normally 
serves as Chairman. Five members are 
Division Engineers rotated from within continental 
U. S. Army Engineer Divisions. The 
seventh member, assigned full time to the 
Board as Resident Member, also directs the 
staff in carrying out the responsibilities of 
the Board. The Board meets on call of the 
Chairman. 
Statutory duties of the Board, as set forth 
in the Act of June 13, 1902, and subsequent 
acts and amendments, are: (a) to conduct independent 
reviews of survey reports covering 
projects for river and harbor, flood control, 
erosion of coastal and lake waters, and multiple-
purpose improvements prepared by the 
Corps in response to acts of Congress or resolutions 
of Congressional Committees, and to 
report its conclusions and recommendations 
thereon to the Chief of Engineers, who forwards 
the reports with his conclusions and 
recommendations to the Secretary of the 
Army for transmission to the Congress; (b) to 
conduct independent reviews of special reports 
ordered by the Congress and report 
thereon in the same manner as for survey 
reports when directed by the Chief of Engineers; 
and (c) to consider and approve general 
plans for major modification and reconstruction 
of any lock, canal, canalized river or other 
work for the use or benefit of navigation. 
An additional statutory duty was assigned 
the Board under the terms of the Merchant 
Marine Act of June 5, 1920. Under this act, 
the Board, in cooperation with the Maritime 
Administration, collects, compiles, and publishes 
information on characteristics of U.S. 
ports. Physical characteristics of the ports 
are the responsibility of the Corps, and administrative 
characteristics are the responsibility 
of the Maritime Administration. 
In addition to its statutory duties, the following 
duties are assigned by the Chief of 
Engineers: review Corps policies and procedures 
as directed; review reports of other 
Federal agencies pertaining to water resource 
development; conduct investigations and studies 
of economics of ports and waterways; and 
conduct a year-long program of in-service 
training for Corps planners, generally at GS 
12 and GS 13 levels, in all aspects of Federal 
water resources development to assist in 
meeting the needs of the Corps for increased 
numbers of qualified personnel in this field. 
In addition to his other duties, the Resident 
Member of the Board is second alternate for 
the Secretary of the Army on the Foreign- 
Trade Zones Board, and ex-officio secretary of 
the American Section, Permanent International 
Association of Navigation Congresses, a 
quasi-official organization. 
On June 30, 1975, the Board was comprised 
of the following members: Major General 
Daniel A. Raymond, Chairman; Major General 
Francis P. Koisch, Lower Mississippi Valley 
Division; Major General Richard E. Mc- 
Connell, North Pacific Division; Brigadier 
General James L. Kelly, North Atlantic Division; 
Brigadier General Wayne S. Nichols, 
Ohio River Division; Brigadier General Carroll 
N. LeTellier, South Atlantic Division; and 
Colonel William G. Kratz, Resident Member. 
In addition to the foregoing, the following 
officers were also assigned for a period during 
the year to membership on the Board: Major 
General Charles C. Noble, Lower Mississippi 
Valley Division; Major General Richard H. 
Groves, North Atlantic Division; and Brigadier 
General George B. Fink, South Pacific 
Division. 
A summary of investigations authorized by 
the Congress from establishment of the Board 
in 1902 to the end of the Fiscal Year 1975, the 
number of authorizations completed, the 
number of authorizations remaining to be 
reported on, and the number of reports submitted 
under continuing authorizations are 
set forth in Table 41-A. 
41-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
From 1902 through June 30, 1975, the 
Board took final action on 8,296 reports, recommending 
favorably on 3,670 and unfavorably 
on 4,626. During Fiscal Year 1975, the 
Board held four meetings of two to three 
days' duration in Washington. The Board 
considered 67 reports, acting favorably on 36, 
unfavorably on 24, and returning 7. The 
Board recommended construction of projects 
totaling $1,043,749,800, of which $900,104,800 
was the estimated U. S. cost and $143,645,000 
the cost to local interests for work and cash 
contributions. During Fiscal Year 1975, the 
Board staff submitted comments to the Chief 
of Engineers on eleven General Design Memorandums. 
Studies prescribed by various River and 
Harbor Acts and Section 8 of the Merchant 
Marine Act of 1920 continued, and the results 
were published in a series of reports titled 
"Port Series" (See Table 41-B). 
41-2

BOARD OF ENGINEERS FOR RIVERS AND HARBORS 
TABLE 41-A BOARD OF ENGINEERS FOR RIVERS AND HARBORS 
Reports Submitted 
During Fiscal 
Authorities Authorities Authorities Authorities Authorities Year 1975 (under 
Received Received Completed Completed Remaining Continuing, Multi 
Authority for Prior to During Prior to During to be Re- ple, and Special 
Investigation July 1, 1974 Fiscal Year July 1, 1974 Fiscal Year ported on Authority) 
Flood Control and 
River and Harbor Acts, 
Exclusive of 1909 
River and Harbor Act 5,234 51 4,912 1 372 
River and Harbor Act 
of 1909--Continuing 
Authority for Major 
Modification 1 - - - 1 0 
Congressional Resolutions 
Exclusive of 
Great Lakes Harbors 4,738 45 3,310 27 1,446 
Public Law 71-84-1 
Authority for Multiple 
Hurricane Studies 1 - - - 1 0 
Total 9,974 96 8,222 28 1,820 
TABLE 41-B PORTS SERIES PUBLICATIONS 
Published during the year: 
No. 16- Miami, Port Everglades, and Palm Beach, Fla. 
No. 30 - San Francisco and Redwood City, California 
No. 47- Milwaukee, Wis. 
No. 48 - Green Bay and Manitowoc, Wis.; Muskegon and Escanaba, Mich.; and Indiana Harbor and 
Burns Waterway Harbor, Ind. 
Being printed at end of the year: 
No. 46 - Chicago, Ill. 
No. 49 - Duluth, Minn.; Superior, Wis.; Taconite Harbor, Silver Bay and Two Harbors, Minn.; and 
Ashland, Wis. 
In progress at end of year: 
No. 31 -Oakland, Alameda, Richmond, Vallejo, and Ports on Carquinez Strait, Calif. 
No. 32 - Sacramento, Stockton, Pittsburg, and Antioch, Calif. 
No. 33 - Coos Bay and Astoria, Oreg.; and Longview and Vancouver, Wash. 
No. 34- Portland, Ore. 
No. 35- Tacoma, Grays Harbor, and Olympia, Wash. 
No. 36- Seattle, Wash. 
41-3

MISSISSIPPI RIVER COMMISSION* 
The Mississippi River Commission, created by 
an act of Congress on Jun. 28, 1879, consists of 
three officers of the Corps of Engineers, one from 
the former Coast and Geodetic Survey (presently 
the National Oceanic and Atmospheric 
Administration), and three civilians, two of 
whom must be civil engineers. All members are 
appointed by the President with the advice and 
consent of the Senate. During the fiscal year the 
Commissioners were: MG Charles C. Noble, 
U. S. Army, President, until his retirement Aug. 
31, 1974; MG F. P. Koisch, U. S. Army, President, 
beginning Dec. 16, 1974; Mr. Harold T. Council; 
Dr. Frederic H. Kellogg, civil engineer, until his 
retirement Jul. 31, 1974; Mr. Roy T. Sessums, 
civil engineer; MG Harold R. Parfitt, U. S. 
Army; RAdm Allen L. Powell, Director, 
National Ocean Survey, National Oceanic and 
Atmospheric Administration; and Mr. Richard 
Hall, civil engineer, beginning Dec. 16, 1974. 
COL Howard L. Strohecker, U. S. Army, served 
as Secretary of the Commission in the office of its 
President, Mississippi River Commission 
Building, Vicksburg, Miss., until his retirement 
Aug. 31, 1974. COL John L. Cannon assumed the 
position Aug. 29, 1974. The Mississippi River 
Commission is charged, under direction of the 
Secretary of the Army and supervision of the 
Chief of Engineers, with prosecution of 
improvements for flood control of the Mississippi 
River and of its tributaries and outlets in its 
alluvial valley, so far as they are affected by 
Mississippi River backwater, between Head of 
Passes, La. (mile 0), and Cape Girardeau, Mo. 
(1,006 miles AHP-Lower Mississippi mileage 
terminates at mile 954 AHP), and with 
prosecution of improvements in the interest of 
navigation between Cairo, Ill. (954 miles AHP), 
and Baton Rouge, La. (234 miles AHP); and for 
stabilization of the lower 7 miles of the right bank 
of the Ohio River, to former mouth of Cache 
River. It also is charged with prosecution of 
certain flood control works on the Mississippi 
River and tributaries, as far as they are affected 
by backwater, between Cape Girardeau, Mo., and 
Rock Island, Ill. (1,437 miles AHP), and with 
prosecution of improvements on designated 
tributaries and outlets below Cape Girardeau for 
flood control, navigation, major drainage, and 
related water uses. Authorized operations of the 
Commission below Cape Girardeau are 
conducted by District Engineers of New Orleans, 
Vicksburg, and Memphis Districts within the 
areas described below, in accordance with 
approved directives and programs and 
congressional appropriations therefor. 
New Orleans District: Mississippi River 
project levees and river channel stabilization as 
required from Head of Passes, mile 0 to 320 AHP, 
including south bank levee of Red River to 
Hotwells, La.; construction of four salinitycontrol 
structures for fish and wildlife 
enhancement in lower Mississippi River Delta 
region; Bonnet Carrd and Morganza Floodways; 
maintenance and improvements of Mississippi 
River navigation channel from Baton Rouge, La. 
(mile 234 AHP), to mile 320; Baton Rouge Harbor 
(Devils Swamp); navigation improvement of 
Atchafalaya and Old Rivers from Mississippi 
River to Morgan City; control of Old and 
Atchafalaya Rivers; Lake Pontchartrain 
protection levee, Jefferson Parish, La.; 
Atchafalaya Basin Floodways; flood control and 
drainage improvements in Bayou Cocodrie and 
tributaries, in Bayou des Glaises, and in Upper 
Pointe Coupee Loop area; flood protection in 
eastern Rapides and south-central Avoyelles 
Parishes, La.; and freshwater distribution from 
Atchafalaya River to Teche-Vermilion Basins. 
Vicksburg District: Mississippi River project 
levees and river channel stabilization as required 
from upper limits of New Orleans District (mile 
320 AHP) in vicinity of Black Hawk, La., to 
Coahoma-Bolivar County line, Miss. (mile 620 
AHP) on left bank, and to vicinity of mouth of 
White River, Ark. (mile 599 AHP), on right bank 
including south bank Arkansas River levee to 
vicinity of Pine Bluff, Ark., and north bank levee 
to vicinity of Tucker on left bank of Plum Bayou, 
Ark.; bank stabilization in lower 36.1 miles of 
Arkansas River; maintenance and improvement 
of Mississippi River navigation channel between 
miles 320 and 599 AHP; Vicksburg and 
Greenville Harbors; specific fish and wildlife 
facilities in Red River, Yazoo, and Big Sunflower 
Basins; a streambank erosion control project in 
the Yazoo Basin; flood control and drainage 
improvements in Red River backwater area 
* Authorizing legislation (Tables 42-D and 42-E) and cost and financial statement (Table 42-U) are listed at the end of this 
chapter. All other tables are referenced in text and also appear at the end of this chapter. 
42-1

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
including leveed portion east and west of Black 
River and south of Red River; Jonesville, La., 
Boeuf and Tensas Rivers'and Bayou Macon Basins 
and tributaries, Ark. and La., and Bayou 
Lafourche, La.; Yazoo River Basin, Miss., 
including backwater area; Big and Little 
Sunflower Rivers, Deer Creek, and Steele Bayou, 
Miss.; and Grand Prairie Region and Bayou Meto 
Basin, Ark., including provision for agricultural 
water supply. 
Memphis District: Mississippi River project 
levees and river channel stabilization as 
required, from upper limits of Vicksburg 
District to north bank of Little River diversion 
channel, Mo. (1,003 miles AHP), a few miles 
below Cape Girardeau, Mo., on right bank, and to 
Cache River diversion channel (967 miles AHP) 
above Cairo, Ill., on left bank, including levees 
and revetment on right bank of Ohio River, in 
Mounds-Mound City area, Ill.; except operations 
above Cairo, Ill., do not include channel 
stabilization on the Mississippi River. 
Maintenance and improvement of Mississippi 
River navigation channel between miles 599 and 
954 AHP and of Memphis Harbor, Tenn.; specific 
fish and wildlife facilities in St. Francis Basin; 
levees in White River backwater area up to 
vicinity of Augusta, Ark., and a pumping plant 
near mouth of White River; levees and pumping 
plants at De Valls Bluff and Des Arc, Ark.; 
channel improvements in Cache River Basin, 
Ark.; channel improvements in Big Creek and 
tributaries, Ark.; improvement works in St. 
Francis River Basin, Mo. and Ark., including 
backwater area improvements in Belle Fountain 
Ditch and Drainage District No. 17, Ark.; Little 
River diversion channel, Mo., and L'Anguille 
River, Ark.; Wolf River Basin, Tenn.; Obion and 
Forked Deer River Basins, Tenn.; Reelfoot Lake 
area, including channel improvement for Bayou 
du Chien and Lake No. 9, Tenn. and Ky.; West 
Kentucky tributaries, Ky.; Mud Lake pumping 
station, Tenn.; and pumping plants and outlet 
structures in the Cairo-Mounds-Mound City area, 
Ill.
Field operations of the Commission restricted 
to levee construction under Sec. 6, 1928 Flood 
Control Act (local interests contributing onethird 
of costs and furnishing rights-of-way) are 
conducted within the following limits by two 
districts reporting directly to the Commission on 
matters within their jurisdiction-St. Louis 
District: Mississippi River (Sec. 6) levees from 
upper limits of Memphis District to Clemens 
Station, Mo. (1,254 miles AHP), on right bank and 
Hamburg Bay, Ill. (1,215 miles AHP), on left 
bank, and Illinois River from its mouth to mile 
120 at Havana, Ill. Rock Island District: 
Mississippi River (Sec. 6) levees from upper 
limits of St. Louis District to Rock Island, Ill. 
(1,437 miles AHP). Table 42-N shows work 
accomplished. 
MISSISSIPPI RIVER AND ALLUVIAL 
VALLEY BELOW CAPE GIRARDEAU, 
MO. 
Location and description. The Mississippi 
River rises in Lake Itasca, Minn., and flows 
generally southerly for 2,340 miles through the 
central portion of United States to empty into the 
Gulf of Mexico 115 miles below New Orleans. It is 
improved for barge navigation for 1,832 miles to 
Minneapolis, Minn. The Mississippi River and its 
major tributaries, the Missouri, Ohio, 
St. Francis, White, Arkansas, Yazoo, and Red- 
Old Rivers, drain 1,245,000 square miles in all or 
part of 31 states between the Rocky and 
Appalachian Mountains and part of two 
Canadian provinces. Below Cape Girardeau, Mo., 
53 miles above Ohio River, river bottomlands 
widen abruptly into an alluvial valley of 35,460 
square miles which was originally subject to flood 
overflow. A major part of the alluvial valley has 
been protected from floods by levees which 
confine floodflows within a floodplain having an 
average width of 5 miles. (See map of alluvial 
valley of Mississippi River, scale 1:500,000.) 
Observations made by Mississippi River 
Commission to Jun. 30, 1974, show approximate 
all-time maximum and minimum discharges 
between levees as follows: Cairo to White River, 
2,000,000 and 70,000 cubic feet per second; thence 
to Red River, 2,150,000 and 90,000 cubic feet per 
second; thence to the Gulf of Mexico, 1,500,000 
and 50,000 cubic feet per second in Mississippi 
River and 660,000 and 11,000 cubic feet per 
second in Atchafalaya River. As the 1927 
floodflow was not confined between levees, 
maximum discharges recorded do not include 
entire flow of the 1927 flood, maximum of record 
below White River. High water and flood stages 
usually occur in late winter or early spring, but 
great floods such as that of 1937 occurred as early 
as January. Low water stages generally prevail 
from August to December. Extreme all-time 
ranges in stages recorded at representative gages 
(rounded to nearest foot) are 60 feet at Cairo, 49 
feet at Memphis, 57 feet at Red River Landing, 
and 21 feet at New Orleans (Carrollton). The river 
is nontidal above Red River Landing where tidal 
amplitude rarely exceeds 0.1 foot during extreme 
low water. 
Previous projects. For details see page 1944, 
Annual Report for 1932. 
42-2

MISSISSIPPI RIVER COMMISSION 
Existing project. The Mississippi River and 
tributaries project in the alluvial valley between 
Head of Passes, La., and Cape Girardeau, Mo., 
provides protection from floods by means of 
levees, floodwalls, floodways, reservoirs (in Yazoo 
and St. Francis Basins), bank stabilization, and 
channel improvements in and along the river and 
its tributaries and outlets insofar as affected by 
backwater of Mississippi River, including levee 
work on the main stem between Cape Girardeau 
and Rock Island. When completed, 23,621 square 
miles will be protected from the Mississippi River 
project flood. The project also provides for a 12- 
by 300-foot navigation channel between Baton 
Rouge, La., and Cairo, Ill.; for salinity-control 
structures; and for channel realinement and 
improvement including bank stabilization and 
dikes to reduce flood heights, control natural 
tendency of river to lengthen by meandering, and 
protect levees from being destroyed by caving 
banks. Locations of major main stem Mississippi 
River improvements are shown in Table 42-A and 
those for off-main stem tributaries are shown in 
Table 42-B. Pertinent data on dams and lakes are 
shown in Table 42-C. Authorizing and 
incorporating legislation are shown in Tables 42- 
D and 42-E. Summary of presently estimated 
Federal cost of authorized improvements is 
shown in Table 42-F. Construction of the existing 
project began in 1928 and has continued 
throughout ensuing years. Based on the 
estimated cost of $5,628,153,000 (Jul. 1, 1975 
price levels) and actual expenditures through 
Jun. 30, 1975, of $2,050,879,700, the entire project 
is about 36 percent complete. 
Recommended modifications. None. 
Local cooperation. The Flood Control Act of 
1928, as amended, applies. Such requirements 
have, in general, been complied with by local 
interests. 
Terminal facilities. See volume 1 of two-volume 
Port Series No. 21, 1969, "Ports on the Gulf Coast 
of the United States," for Baton Rouge and Lake 
Charles, La.; Port Series No. 20, 1970, for New 
Orleans, La.; also folio of Flood Control and 
Navigation Maps of Mississippi River, Cairo, Ill., 
to the Gulf of Mexico (42nd edition), 1974. 
Project cost. Total monetary authorizations, 
including the modifications to Jun. 30, 1975, are 
$2,159,922,600. Total allotted for flood control, 
including maintenance charges through Aug. 18, 
1941, chargeable under authorizations to Jun. 30, 
1975, was $2,121,096,200. (See Table 42-S.) (See 
also Tables 42-R, 42-T, and 42-U for additional 
financial statements.) 
Operations and results during fiscal year. 
Commission activities: The 292nd session was 
held, Oct. 7-11, 1974, on board the U. S. MV 
Mississippi en route on the Mississippi River 
from Cairo, Ill., to Old River, La., thence from Old 
River to Simmesport, La., and down the 
Atchafalaya River to Morgan City, La. Major 
features of the project were inspected, including 
bank protection works, contraction works, levees, 
and general channel conditions to the extent 
permitted by river stages. Public meetings held 
at Cairo, Ill., Memphis, Tenn., Vicksburg, Miss., 
and Morgan City, La., were attended by about 210 
representatives of local governmental, 
navigation, levee, commercial, and other 
interests. About 50 of those in attendance 
addressed the Commission and presented 
problems pertaining to flood control and 
navigation. This session was adjourned at 
Morgan City, La., at 6:00 p.m., Oct. 11, 1974. 
The 293rd session was held Jan. 23-24, 1975. 
The Commission met in Executive Session at its 
headquarters in Vicksburg, Miss., for the 
purpose of discussing the work of the 
Commission, the direction of the budgetary 
processes, and future work and problems. This 
session was adjourned at 12:30 p.m., Jan. 24, 1975. 
The 294th session was held May 5-9, 1975, on 
board the U. S. MV Mississippi en route on the 
Mississippi River from Cairo, Ill., to New 
Orleans, La. Bank protection works, levees, and 
channel conditions were observed to the extent 
permitted by river stages. On May 9 the 
Commission made an aerial inspection of the 
levees from New Orleans to Head of Passes and 
Southwest Pass. Approximately 200 persons 
attended public meetings held at Cairo, Ill., 
Memphis, Tenn., Vicksburg, Miss., and New 
Orleans, La. About 65 of the representatives 
presented various problems pertaining to flood 
control and navigation. This entire session was 
adjourned at New Orleans, La., on May 9, 1975. 
Records of Proceedings of all sessions of the 
Mississippi River Commission are on file in the 
office of the President. 
Alluvial Valley Mapping 
General. Contoured quadrangles and general 
maps of the alluvial valley are available for 
departmental use and public distribution under 
prescribed regulations. Preparation, revision, 
42-3

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
and publication of quadrangle maps (scale 
1:62,500) continued. Road-map-type information 
brochures of principal portions of the 
overall project were published along with pamphlets 
on the subject of flood control and navigation. 
Maps and supplemental data sheets for 
active works were updated and published as 
required. The 1974 (42nd) edition of the folio of 
flood control and navigation maps (scale 
1:62,500) covering the Mississippi River from 
Cairo, Ill., to the Gulf of Mexico was revised 
and printed. 
The National Aeronautics and Space 
Administration completed high-level 
photography of the alluvial valley. Photographic 
missions were flown during September, October, 
and November 1974, using PB-57 aircraft, at an 
altitude of 60,000 feet. North and south flight 
lines were centered on United States Geological 
Survey fifteen-minute quadrangles with 60 
percent overlap between frames. A contract 
was awarded to Mead Technical Laboratory, 
Dayton, Ohio, to enlarge 900 frames to a scale of 
1:62,500, and to furnish prints with and without 
contours. 
Approximately 2,224 flight-line miles of 
infrared color; 10,542 flight-line miles of blackand-
white aerial photography (various scales); 
and about 285 hours of oblique photography were 
flown along the Mississippi River and tributaries 
in the New Orleans, Vicksburg, and Memphis 
Districts. 
Work accomplished in the Districts: New 
Orleans District-Series conversions of the 
Opelousas, Carencro, Arnaudville, St. 
Martinville, Lake Chicot, Centerville, Bayou 
Sale, and Point au Fer, La., quadrangles are in 
progress. 
Vicksburg District-Series conversions of 
U. S. Geological Survey 1:24,000-scale 
quadrangles to 1:62,500-scale with addition of 
flood control features of Prescott, Camden, 
Sparkman, and Fountain Hill, Ark., were 
printed. Quadrangles for Gillett, Ingalls, and 
Altheimer, Ark., and Edwards, Miss., are ready 
for printing. Series conversions of Chidester and 
Hamburg, Ark., and Big Island and Lamont, 
Miss., and Ark., are in progress. 
Memphis District-Series conversions of U. S. 
Geological Survey 1:24,000-scale quadrangles to 
1:62,000-scale quadrangles of Marvell, Hunter, 
and Brinkley, Ark., were printed. Series 
conversions of Jericho and Millington, Tenn., are 
ready for printing. Color separations of Hales 
Point and Osceola, Tenn., and Ark.; Blytheville, 
Ark., Tenn., and Mo.; Rialto, Atwood, Trimble, 
and McKenzie, Tenn.; and Deckerville, Ark., are 
under way. Revised General River Map of the 
Mississippi River was printed. 
Floods 
The final Post Flood Report covering 
Mississippi River and tributaries flooding during 
1973 was distributed in March 1975. Draft of the 
Post Flood Report covering Mississippi flooding 
during the 1974-75 flood season is currently being 
prepared. Target date for distribution of the 
completed report is December 1975. 
Observations in the Districts: Memphis 
District-Mississippi River crest stage of 56.4 
feet at Cairo gage on Apr. 3-4, 1975, and 
maximum discharge of 1,661,000 cubic feet per 
second, occurred on Apr. 4, 1975, at Hickman, 
Ky., and crest stage of 40.3 feet at Memphis on 
Apr. 7, 1975, with maximum discharge of 
1,768,000 cubic feet per second on Apr. 6, 1975. 
Vicksburg District-Stages on the Mississippi 
River were above normal during the entire year. 
The river began a steady rise in January and 
crested in April below bankfull at Arkansas City, 
6.2 feet above bankfull at Greenville, 6.8 feet 
above bankfull at Vicksburg, and 6.0 feet above 
bankfull at Natchez. The Ouachita River stages 
remained very high during the year. Crest stages 
occurred in February and May from Camden to 
Jonesville and February, March, and May above 
Camden. They were about 3.2 feet above bankfull 
at Arkadelphia, 8.8 feet above bankfull at 
Camden, and 4.2 feet above bankfull at Monroe. 
Operation of flood control works reduced 
maximum stages by 3.0 feet at Arkadelphia and 
2.4 feet at Camden. Significant flooding of long 
duration occurred almost everywhere in the 
Yazoo Basin. Maximum stages were 3.3 feet 
above bankfull at Swan Lake, 1.2 feet below 
bankfull at Greenwood, and 4.4 feet above 
bankfull at Yazoo City. Operation of flood control 
works reduced stages an average of about 3 feet 
on the Coldwater River, 4.5 feet on the 
Tallahatchie River, 6.5 feet at Greenwood, and 
about 2 feet at Yazoo City. The Big Black River 
crested approximately 10.3 feet above bankfull 
stage during March 1975. 
New Orleans District-On the Mississippi 
River, the Red River Landing gage recorded 56.7 
feet msl on Apr. 15, 1975, and the New Orleans 
gage recorded a stage of 18.0 feet msl on Apr. 14, 
1975. Simmesport gage on the Atchafalaya River 
recorded a maximum of 49.1 feet msl on Apr. 17, 
1975. The Red River gage at Alexandria recorded 
30.6 feet on May 12, 1975. 
Studies and Investigations 
General investigations. Surveys and reports, 
authorized by laws and by Senate and House 
Public Works Committee resolutions, were made 
as required. Collection and study of basic data 
continued. Forwarded the following reports: 
42-4

MISSISSIPPI RIVER COMMISSION 
"Review Report-St. Johns Bayou and New 
Madrid Floodway, Missouri," dated Jul. 22, 1974, 
which recommended that the Flood Control Act 
of May 15, 1928, as amended, be further modified 
and expanded to provide for additional 
improvements in the St. Johns Bayou area at an 
estimated Federal first cost of $17,629,000. 
"Lower Mississippi Region Comprehensive 
Study." The main report with the Plan 
Formulation appendix, prepared under 
supervision of the Lower Mississippi Region 
Comprehensive Study Coordinating Committee, 
was transmitted May 9, 1975, to the Water 
Resources Council prior to its transmittal 
through the President of the United States to 
Congress. The recommended framework 
program demonstrates that future needs will 
require judicious planning for fulfillment, and 
that capital investment in water and related land 
resources management and development is one 
method of satisfying the needs. Major elements of 
the program consist of plans for water supply, 
water surface area, land use, problem 
amelioration, and public investment. 
Engineering studies. A research program was 
continued for development of materials and more 
effective and economical design of regulation 
features for placing and stabilizing the 
Mississippi River in a suitable alinement. 
Conditions observed during and after the 1973 
flood indicated channel deterioration in the 
Mississippi River, Atchafalaya River, and 
Atchafalaya Bay area which seriously affected 
the project flood flow line. The 1973 adjustments 
to the Mississippi River and Tributaries Project 
flood flow line were based on analytical and 
physical model tests to identify problem areas 
and the relative magnitude of the flow-line 
adjustments. A study is now under way to refine 
the flow-line adjustments to include a 
reevaluation of the Mississippi River and 
Atchafalaya Floodway flow lines for the 
Mississippi River and Tributaries Project. 
Channel and overbank surveying is nearing 
completion for the development of a current data 
base. A program of potamology studies to 
examine river characteristics was initiated in 
1974. Data collection is scheduled for completion 
in 1976, and further studies are to correlate 
changes in river characteristics to hydrology and 
hydraulic factors and to construction features. 
Mississippi River and Tributaries-Levees 
Operations and results during fiscal year. This 
feature consists of construction of new, and 
enlargement of existing, levees to approved grade 
and section; construction and restoration of levee 
berms; and construction, repair, and 
maintenance of roads on levees. Work 
accomplished was as follows: 
New Orleans District-Enlarged 104.0 miles of 
levees in the Main Stem System and surfaced 7.6 
miles of roads on Atchafalaya River levees. See 
Table 42-K. 
Vicksburg District-Constructed 19.1 miles of 
roads on main stem levees and surfaced 155.0 
miles on Yazoo River levees. See Table 42-L. 
Memphis District-Constructed 27.2 miles of 
levee enlargement, 2.8 miles of berms, and 38.2 
miles of gravel surfacing on the main stem and 
9.6 miles of surfacing on the Little River levees. 
See Table 42-M. 
Condition at end of fiscal year. (See Tables 42- 
K, 42-L, and 42-M.) There are 1,608.3 miles of 
levees authorized for the Mississippi River below 
Cape Girardeau, of which 1,600.2 are in place 
with 1,213.3 built to approved grade and section. 
The Main Stem Levee System consists of 2,202.7 
miles, of which 2,189.9 are in place with 1,544.9 
miles completed to approved grade and section. 
Included in this system are additional levees and 
structures along the south bank of Arkansas 
River (85.4 miles); along the south bank of Red 
River (59.8 miles, with 43.9 completed); and 449.2 
miles in the Atchafalaya River Basin, with 202.3 
essentially complete. Of the authorized 801.0 
miles of berms, 352.7 are complete. Graveled or 
hard-surfaced roads have been constructed on 
1,645.5 miles of these levees. 
There are an additional 1,569.4 miles of 
authorized levees off the main stem of which 
1,004.5 are in place with 804.5 to approved grade 
and section. Berms have been completed on 9.8 
miles and 317.0 miles of graveled or hardsurfaced 
roads have been constructed on the 
levees. 
Status of levees authorized under provisions of 
Sec. 6, 1928 Act, is summarized in Table 42-N. 
Mississippi River and Tributaries-Channel 
Improvements 
Operations and results during fiscal year. Bank 
revetment and dikes: (See Tables 42-H, 42-I, and 
42-J.) Construction of 19.40 miles of new bank 
revetment and 4.01 miles of reinforcement of 
existing revetment along the Mississippi River 
was completed by Government plant and hired 
labor, and construction of 15.95 miles of new 
dikes and 1.00 mile of dike reinforcement was 
completed by contract. 
In addition, work on tributaries consisted of 
5.45 miles of new bank revetment and 1.15 miles 
of revetment reinforcement and construction of 
0.31 mile of new dike. 
Dredging: Mississippi River Main Stem-(See 
Table 42-G.) Work included dredging 40,860,000 
42-5

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
cubic yards for channel and harbor maintenance 
and channel construction and revetment. 
Minimum channel depth of 9 feet was 
maintained. Dredging was done with the 
following plant: New Orleans District, one 
contract cutterhead dredge; Vicksburg District, 
two Government-owned dustpan dredges (on 
loan), and one leased cutterhead dredge; and 
Memphis District, four Government-owned 
dustpan dredges (one on loan) and three leased 
cutterhead dredges. Mississippi River 
Tributaries-(See Tables 42-0, 42-P, and 42-Q.)- 
Operations included 48.4 miles of channel 
improvement, 9,195,000 cubic yards of 
excavation, and 9.7 miles of cleanout. 
Other work performed in the interest of 
navigation, supplementing maintenance 
dredging on Mississippi River between Cairo, Ill., 
and Baton Rouge, La., included removal of snags, 
wrecks, and obstructions; issuance of bulletins by 
the Vicksburg District providing information on 
available high-water velocities at selected 
locations; maintaining bulletin boards showing 
daily gage readings at regular MRC gages; and 
contact pilot service furnishing navigation 
interests with latest information and advice on 
channel conditions and obtaining their views as to 
needs of navigation interests. Cost of this work is 
given in Table 42-R. 
Condition at end of fiscal year. In carrying out 
authorized channel improvement program 
between Baton Rouge and Cairo, 16 cutoffs were 
developed between 1933 and 1942. These, 
combined with chute channel development and 
alinement improvements, decreased channel 
length between these cities by about 170 miles. 
However, current velocities increased the attack 
on the banks and the river began to regain its 
length. As a result, the net shortening between 
1933 and 1962 was 114 miles of the theoretical 
170-mile cutoff. There are now in place 690.84 
miles of operative bank revetment and 160.07 
miles of dikes on the Mississippi and lower Ohio 
Rivers. 
There are 41.74 miles of revetment and 5.20 
miles of dikes on the tributaries as listed in Tables 
42-H, 42-I, and 42-J. This amount of channel 
stabilization should prevent the river from 
regaining much more of its length due to 
meandering. A navigation channel 9 by 300 feet is 
being accomplished by revetment and dikes and 
maintained by dredging as required during the 
low-water season. Due to growing effectiveness of 
channel improvement program, average 
maintenance dredging requirements are 
steadily being reduced, and an increase 
in navigable depth is being obtained. Approximately 
97 miles of foreshore protection have 
been constructed along the lower Mississippi 
River. 
New Orleans District 
ATCHAFALAYA BASIN, LA. 
Operations and results during fiscal year. New 
work by hired labor: Real estate activities and 
planning for construction were continued. 
Bank stabilization consisted of placing 5.5 
miles of articulated concrete mattress at 
Odenburg, McCrea, Woodside, Goudeau, Cross 
Bayou, Holloway Lake, and Sherburne, La., on 
the Atchafalaya River. 
New work by contract: Construction of 
floodside and landside berms arid levee 
enlargement continued intermittently on the east 
and west protection levees, although there was 
considerable delay during the year due to 
exceptionally high water flooding the borrow 
pits. One contract on the west protection levee, 
initiated in a prior year, was completed over a 
distance of 5.3 miles with placement of 267,387 
cubic yards this fiscal year. Three contracts on 
the east protection levee, initiated in a prior year, 
were completed over a distance of 3.5 miles with 
placement of 242,852 cubic yards this fiscal year. 
An additional 8.0 miles of levee enlargement and 
floodside and landside berms are under 
construction on the west protection levee 
involving placement of 1,948,576 cubic yards 
during the fiscal year and 1.2 miles of levee 
enlargement and floodwall on the east protection 
levee with placement of 756,623 cubic yards. 
Contracts for an additional 2.8 miles of levee 
enlargement and floodside and landside berms on 
the east protection levee and 4.1 miles of levee 
enlargement and floodside and landside berms on 
the west protection levee have been awarded, but 
construction has not started. 
Maintenance by hired labor: Bayou Boeuf, 
Berwick, and Bayou Sorrel Locks, Morganza 
Control Structure, and numerous drainage and 
flood control structures were operated and 
maintained. Wax Lake East drainage structure, 
dredging of discharge channel, resulted in 15,000 
cubic yards removed between May 1 and Jun. 30, 
1975. Riprap was placed at Bayou Boeuf Lock 
between Apr. 16 and May 16, 1975, and at Bayou 
Sorrel Lock between Apr. 14 and Apr. 30, 1975. 
Maintenance by contract: Morganza bridge 
pier repairs at Morganza Control Structure were 
initiated Aug. 2, 1974, and completed Feb. 11, 
1975. Chamber guide walls at Bayou Sorrell Lock 
were constructed between Aug. 2, 1974, and Nov. 
24, 1974, and chamber guide walls at Bayou 
Boeuf Lock were constructed between Aug. 15, 
1974, and Jan. 16, 1975. Contracts were awarded 
for the modification to Point Coupee drainage 
structure and construction of a levee setback at 
Cross Bayou. This work will be performed with 
Public Law 99 (Rehabilitation) funds. 
42-6

MISSISSIPPI RIVER COMMISSION 
Maintenance dredging was performed, 
resulting in the removal of 185,778 cubic yards 
from the West Access Channel and 766,609 cubic 
yards from the East Access Channel between Jul. 
26 and Dec. 16, 1974; 171,363 cubic yards from 
Three Rivers and Six Mile Lake between Jul. 13 
and Sep. 4, 1974; 310,707 cubic yards from 
Morgan City and Berwick Bay Harbors. This 
contract was initiated in Fiscal Year 1974 and 
completed Jul. 18, 1974; and 1,124,020 cubic 
yards from East Freshwater Distribution 
Channel between Aug. 7, 1974, and Jan. 6, 1975. 
Approximately 723,163 cubic yards were 
removed by leased dredge in maintenance 
dredging of Berwick Bay Harbor and Berwick 
Lock forebay between Aug. 22 and Sep. 11, 1974, 
and 319,977 cubic yards from Six Mile Lake 
between Sep. 11 and Sep. 23, 1974. 
Condition at end of fiscal year. Construction 
was initiated Aug. 7, 1929, with the 
commencement of the west protection levee from 
Bordelonville to Hamburg, La. The project is 28 
percent complete, based on the current estimated 
cost of $849,000,000 which includes funds for 
Upper Pointe Coupee Loop area. Of the 449.2 
miles of levees and floodwalls authorized for the 
Atchafalaya system, 202.3 miles are built to 
grade. See Table 42-K for status of levees. 
Major items remaining to be completed include 
completion of levees to grade and section, channel 
improvement by dredging to reduce flow line, 
and bank stabilization. The channel has been 
enlarged to 60,000 square feet from mile 54.5 to 
96.2, and 40,000 square feet from mile 96.2 to 
112.3. Enlargement to 100,000 square feet from 
mile 54.5 to 112.3 remains to be done. Drainage 
improvements in Upper Pointe Coupee Loop area 
have not been initiated. Approximately 26.4 
miles of bank stabilization have been placed as 
shown in Table 42-H. 
BATON ROUGE HARBOR (DEVILS 
SWAMP), LA. 
Operations and results during fiscal year. 
Maintenance by contract: Dredging to remove 
shoal was initiated Jul. 13, 1974, and completed 
Sep. 4, 1974. As a result, 105,060 cubic yards were 
removed from the entrance channel. Contract for 
additional dredging was awarded, but did not 
initiate. Construction and raising of dikes 
initiated last fiscal year were completed Aug. 8, 
1974. Additional construction and raising of 
dikes were initiated Jan. 24, 1975, and completed 
Apr. 20, 1975. 
Condition at end of fiscal year. Construction of 
the first 2.5 miles of the proposed 5.0 miles of 
channel was initiated in January 1958 and 
completed in July 1959, with 7,458,086 cubic 
yards excavated. 
The project is 16 percent complete, based on the 
current estimated Federal cost of $7,590,000 and 
cash contributions of $750,000. Completion of the 
remaining 2.5 miles is dependent on economic 
justification by developments on the initial 
channel. 
BAYOU COCODRIE AND TRIBUTARIES, 
LA. 
Operations and results during fiscal year. 
Maintenance by hired labor consisted of condition 
and operation studies. 
Condition at end of fiscal year. Construction 
was initiated in June 1946 and is 24 percent 
complete, based on the current estimated cost of 
$14,500,000. See page 2031, Annual Report for 
1961, for description of completed work. 
Work required to complete the project consists 
of enlargement of 13.5 miles of upper Bayou 
Boeuf, channel improvement of 25.3 miles of 
Bayou Cocodrie, enlargement of Bayou 
Courtableau from Washington, La., to the west 
protection levee and additional culverts through 
the west protection levee at 100 percent Federal 
cost in lieu of the previously authorized diversion 
channel from Washington to the Bayou 
Courtableau drainage structure. 
BONNET CARRE SPILLWAY, LA. 
Operations and results during fiscal year. 
Maintenance by hired labor: Condition and 
operation studies and ordinary maintenance of 
the control structure and spillway continued. 
Maintenance by contract: Dredging of the 
spillway forebay by two leased dredges was 
accomplished between Mar. 20 and May 22, 1975, 
with removal of approximately 1,423,340 cubic 
yards, utilizing Public Law 99 (Rehabilitation) 
funds. 
Condition at end of fiscal year. Construction of 
the spillway was initiated in Fiscal Year 1929. 
The control structure was completed in 1931, 
levees were completed in 1932, and utility 
crossings completed in 1936. 
It was necessary to operate the structure to 
reduce flood stages in 1937, 1945, 1950, 1973, and 
1975. 
LOWER RED RIVER-SOUTH BANK RED 
RIVER LEVEES, LA. 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering 
studies. 
New work by contract: Construction of 3.2 
miles of levee enlargement at mile 123.5, initiated 
in a prior year, is 87 percent complete. 
42-7

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Approximately 215,403 cubic yards was placed in 
the embankment this fiscal year. Stone has been 
stockpiled, but placement has not started. 
Contract for Smith board mattress revetment, 
mile 91.0, was initiated Mar. 10, 1975. Stone has 
been stockpiled, but placement has not started. 
Maintenance by hired labor consisted of 
condition and operation studies and engineering 
studies. 
Maintenance by contract consisted of pile dike 
repairs from mile 80.0 to mile 71.0. This contract 
was initiated Dec. 7, 1972, and completed Sep. 5, 
1974. 
Condition at end of fiscal year. Construction 
was initiated in Fiscal Year 1929 and is 36 
percent complete, based on the current estimated 
cost of $29,700,000. Of the 59.8 miles of levees 
authorized, 41.3 miles are completed. (See Table 
42-K for status of levees and Table 42-H for status 
of revetments.) 
OLD RIVER, LA. 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering 
studies. 
New work by contract consisted of installation 
of an additional gantry crane at the low-sill 
structure. Assembly work began in a prior year 
and is 91 percent complete. Contract is dormant 
pending corrections to engine generator system. 
Maintenance by hired labor consisted of 
operation and maintenance of the lock and control 
structures as required, condition and operation 
studies, maintenance of cleared areas, operation 
of a picket boat at the inflow channel to the lowsill 
control structure during high river stages, 
and engineering studies. 
Maintenance by contract: During the period 
Jul. 13 to Sep. 4, 1974, 289,519 cubic yards of shoal 
were dredged from the lock forebay. Emergency 
scour repairs of the Old River low-sill structure 
were initiated Mar. 6 and completed Mar. 17, 
1975, with 8,673.8 tons of stone placed; structure 
lighting system was initiated Oct. 16, 1974, and 
completed Feb. 4, 1975; modification and repair 
of the overbank structure and bridge was 
initiated Aug. 9, 1974, and completed Jan. 17, 
1975; and modification of the vertical gate lift 
connection devices was initiated Jul. 12, 1974, and 
completed Jan. 7, 1975; rehabilitation funds were 
utilized in the fabrication and installation of 
parapet wall and the patching of holes in highway 
bridge deck. Contracts for modifications to 
existing gantry cranes at the overbank structure 
and capping steel sheet piles at the Old River 
navigation lock were awarded, but did not 
initiate this fiscal year. 
Public Law 99 (Rehabilitation) funds were 
utilized in making emergency repair of damages 
to the control structures caused by the 1973 flood; 
76,601 tons of stone were placed during the fiscal 
year. The contract was completed Jan. 29, 1975. 
Condition at end of fiscal year. Construction 
began September 1955 and is 83 percent 
complete, based on the current estimated Federal 
cost of $81,200,000. Principal items completed 
are as follows: Low-sill structure June 1959; 
overbank structure October 1959; levees and 
levee enlargements October 1963; inflow and 
outflow channels February 1961; navigation lock 
completed December 1962 and opened to 
navigation March 1963, at which time Old River 
was closed to navigation with a rock and earthfill 
dam; highway approaches and bridge over lock 
completed March 1965. Approximately 2.1 miles 
of bank protection have been constructed at the 
inflow and outflow channels. (See Table 42-H for 
details of bank protection.) 
Principal items remaining to complete the 
project consist of constructing additional bank 
protection works, providing additional scour 
protection in the inflow and outflow channels, an 
additional gantry crane for the low-sill structure, 
and construction for the prevention of marine 
accidents at the low-sill structure. 
Vicksburg District 
TENSAS BASIN, ARK. AND LA. 
Operations and results during fiscal year. 
(a) Boeuf and Tensas Rivers, and Bayou Macon, 
Ark. and La. Planning and design were 
continued on project features, and on Lake Chicot 
Pumping Plant. Acquisition of right-of-way 
continued on Big and Colewa Creeks, and on 
Bayou Lafourche. Channel improvements were 
continued on Bayou Lafourche (Reach BL-1) 
between miles 27.0-32.6 of Boeuf River and 
improvements on Big and Colewa Creeks, Reach 
1-B (miles 0-20). Construction continued on two 
parish bridges and two state highway bridges on 
Big and Colewa Creeks, Reach 1-B. Construction 
was initiated on Big and Colewa Creeks (Reach 2) 
between miles 20-40. 
(b) Red River backwater area. Planning and 
design continued on project features, including 
the Tensas-Cocodrie Pumping Plant. 
Construction continued on the Long Branch 
drainage structure. Construction continued on 
2.3 miles of channel in the Larto Lake to 
Jonesville area. Planning and design are 
continuing on remaining levee construction. 
Condition at end of fiscal year. 
(a) Boeuf and Tensas Rivers, and Bayou Macon, 
Ark. and La. Channel improvement has been 
accomplished on 744.6 miles of project streams, 
42-8

MISSISSIPPI RIVER COMMISSION 
providing major drainage outlets for the 
tributary areas. 
(b) Red River backwater area. Levees in Tensas- 
Cocodrie area are complete except for levee 
raising necessary to conform to the 1973-revised 
project design flow line on the Mississippi River. 
The work comprised 93.1 miles of new levee, 
excluding 2.1 miles of high ground where no 
levees are required, and 72.3 miles of gravel road 
on levees. The Tensas-Cocodrie Pumping Plant, 
authorized in October 1965, is in the planning and 
design stage. Construction of 30.6 miles of levee, 
Larto Lake to Jonesville west of Black River and 
Catahoula Lake Control Structure, have been 
completed. 
LOWER ARKANSAS BASIN, ARK. 
Operations and results during fiscal year. 
Arkansas River levees. South Bend stability berm 
restoration was completed. 
Condition at end offiscal year. Arkansas River 
levees. A total of 56.2 miles of the 61.5 miles of 
north bank levees and all of the 85.4 miles of south 
bank levees have been completed to approved 
grade and section. These levees above mile 36.1 
are protected by bank-protection works 
constructed as a feature of project for Arkansas 
River and tributaries, Arkansas and Oklahoma. 
For present status of this work, see report of 
Little Rock District. Below mile 36.1, needed 
bank protection is constructed with project 
maintenance funds. 
YAZOO BASIN, MISS. 
Operations and results during fiscal year. 
(a) Yazoo City and Belzoni protection works. 
Hired labor forces continued operation and 
maintenance of levees, drainage facilities, and 
pumping plant. 
(b) Greenwood protection works. Construction is 
essentially complete on Big Sand Creek diversion 
channel. Hired labor forces continued operation 
and maintenance of pumping plant, levees, and 
drainage facilities. A review of the protection 
provided to Greenwood and vicinity is under way. 
(c) Main stem. Planning and design of levees 
and channel improvements are continuing in 
connection with studies of the Upper Auxiliary 
Channel alternative. 
Channel maintenance. Random clearing and 
snagging and herbicide willow control continued, 
as required, in Coldwater, Tallahatchie, and 
Yazoo Rivers, and Will M. Whittington Auxiliary 
Channel. An emergency contract for removing 
sediment deposits in a 13-mile reach of 
Tallahatchie River is under way. 
(d) Big Sunflower River. A channel 
improvement contract for Steele Bayou, Item 30- 
A (miles 23.1 to 37.1) is under way. County and 
state highway bridge relocations on Steele Bayou, 
Item 30-A are also under way. Construction was 
initiated on Steele Bayou, Item 43-A (miles 37.1 to 
46.2). Planning was continued on additional work 
in the Steele Bayou Basin, authorized in 1970. 
(e) Tributaries. Construction: (1) Levees. A 
contract for construction of Panola-Quitman 
Floodway levee, Item B, is under way. (2) Bank 
stabilization. Construction of bank stabilization 
works, authorized in Fiscal Year 1972, is 
complete. Construction was completed on bank 
stabilization work on Batupan Bogue, utilizing 
funds appropriated in Fiscal Years 1973 and 
1974. (3) Channels. Construction was continued 
on Alligator-Catfish Bayou. Construction was 
essentially completed on David Bayou extension. 
Real estate activities and planning continued on 
various project features. Relocation of the bridge 
across Alligator-Catfish Bayou is under way. 
Maintenance of channels of Yalobusha, Little 
Tallahatchie, and Yocona Rivers; Cassidy, David, 
Burrell, and Bobo Bayous; and Ascalmore Creek, 
by random clearing and snagging and herbicide 
willow control, continued. 
(f) Enid Lake. (See Table 42-C.) Construction 
and maintenance of public use facilities 
continued. The dam and appurtenant structures 
were maintained and operated. Rehabilitation of 
boat channels and snagging and clearing of 
tributary streams in the lake area continued. The 
flood control outlet channel is being reshaped to 
improve visitor safety and esthetics. Maximum 
pool elevation in the lake was 261.6 feet above 
mean sea level on Apr. 2, 1975, when storage in 
flood control pool amounted to 439,600 acre-feet. 
Peak inflow was 34,600 cubic feet per second on 
Mar.29, 1975. On Jun. 30, 1975, pool elevation was 
257.8 feet above mean sea level, when storage in 
flood control pool amounted to 356,300 acre-feet. 
(g) Grenada Lake. (See Table 42-C.) 
Construction and maintenance of public use 
facilities continued. The dam and appurtenant 
structures were operated and maintained. 
Maintenance snagging and clearing of tributary 
streams in the lake area continued. Maximum 
pool elevation in the lake was 225.2 feet above 
mean sea level on Apr. 2, 1975, when storage in 
flood control pool amounted to 913,100 acre-feet. 
Peak inflow was 83,300 cubic feet per second on 
Mar.13, 1975. On Jun. 30,1975, pool elevation was 
222.7 feet above mean sea level, when storage in 
flood control pool amounted to 784,800 acre-feet. 
(h) Sardis Lake. (See Table 42-C.) Construction 
and maintenance of public use facilities 
continued. The dam and appurtenant structures 
were maintained and operated. Clearing of 
tributary streams in the lake area continued. 
42-9

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
Maximum pool elevation in the lake was 273.3 
feet above mean sea level on Jun. 3, 1975, when 
storage in flood control pool amounted to 
1,029,900 acre-feet. Peak inflow was 57,600 cubic 
feet per second on Mar. 14, 1975. On Jun. 30, 1975, 
pool elevation was 271.2 feet above mean sea level, 
when storage in flood control pool amounted to 
933,000 acre-feet. Improved relief well outfall 
ditch. Installed two new relief wells at toe of dam. 
Outlet channel was rehabilitated, providing 
visitor safety and improved esthetics. 
(i) Arkabutla Lake. (See Table 42-C.) 
Construction and maintenance of public use 
facilities continued. The dam and appurtenant 
structures were maintained and operated. 
Clearing of tributary streams in the lake area was 
continued. Maximum pool elevation in the lake 
was 233.3 feet above mean sea level on Apr. 1, 
1975, when storage in flood control pool amounted 
to 343,300 acre-feet. Peak inflow was 64,800 cubic 
feet per second on Mar. 13, 1975. On Jun. 30, 1975, 
pool elevation was 226.8 feet above mean sea level, 
when storage in flood control pool amounted to 
196,100 acre-feet. Reshaped spillway outlet 
slopes to prevent silting in stilling basin. 
Completed grouting of foundation of outlet works 
conduit and chute. Construction of a boat 
launching ramp is under way. 
(j) Yazoo Basin backwater. Little Sunflower 
drainage structure is essentially complete. 
Construction continued on the Collins Creek 
drainage structure and levee Items 11 and 12. 
Construction continued on Levee Item 15, Items 9 
and 10, and Items 1 and 2 in the Satartia area. 
Planning and design were continued on 
remaining project features. Construction 
continued on the Muddy Bayou Control 
Structure. 
Condition at end offiscal year. The first feature 
of Yazoo Basin project was started in 1936, and 
the total project is about 40 percent complete. A 
total of 19.2 miles of backwater levee has been 
completed. 
Memphis District 
ST. FRANCIS BASIN, ARK. AND MO. 
Operations and results during fiscal year. 
(a) Little River drainage. Contract for channel 
excavation, Item No. 3, Ditch 81 Extension is in 
progress and 40 percent complete. Contract for 
channel excavation, Item No. 2, Ditch 81 
Extension is in progress and 5 percent complete. 
Contract for channel enlargement of Upper Ditch 
No. 1, Item No. 2 is in progress and 15 percent 
complete. Contract for Ditch 81 Extension 
structures is in progress and is 35 percent 
complete. Contract for channel cleanout, Item 
No. 1, Iron Mines Creek and below Rivervale, 
Ark., was completed. Contract for channel 
cleanout, Item No. 2, Iron Mines Creek and below 
Rivervale, Ark., was awarded; contractor has not 
begun work. Completed 47 miles of hired labor 
brush kill on Upper Ditch No. 1, Ditch No. 251, 
and Elk Chute Ditch. 
(b) Upper St. Francis River and floodway. 
Contract for channel excavation, Item No. 2, 
Wappapello-Crowleys Ridge is in progress and is 
98 percent complete. Contract for channel 
improvement on Dudley Ditch-Lick Creek is in 
progress and is 84 percent complete. Contract for 
channel excavation of Mingo Ditch is in progress 
and is 21 percent complete. Contract for channel 
cleanout, below Item No. 1, Wappapello- 
Crowleys Ridge was completed. Contract for St. 
Francis Lake Control Structure is in progress 
and is 95 percent complete. Contracts for three 
county bridges across Mingo Ditch have been 
completed. Contracts for eight county bridges 
across Ditch 27 and tributaries were awarded; 
four of the bridges have been completed, two 
bridges are 62 percent complete, and 
construction has not commenced on the last two 
bridges. Contract for construction of two county 
bridges across Locust Creek Ditch has been 
awarded; work has not begun. Reimbursable 
contract for alteration of Missouri Pacific 
Railroad Bridge across Lick Creek has been 
completed. Reimbursable contract for alteration 
of Missouri Pacific Railroad Bridge across Mingo 
Ditch is in progress and is 35 percent complete. 
Reimbursable contract for alteration of Arkansas 
State Highway 181 bridge across Ditch 27 and 
tributaries has been awarded; work has not 
begun. 
(c) Lower St. Francis River. Contract for 
channel enlargement, Item No. 2, Parcel No. 1, 
Ditches 9 and 10, was completed. Contract for 
landside ditch cleanout, Monterey-Princedale, 
was completed. Contract for channel excavation 
of Ditch No. 11 extension was awarded and 
completed. Contract for plug removal, Ditch No. 
10, under Arkansas Highway No. 14, was 
awarded and completed. Contract for channel 
diversion, Ditch No. 9 was awarded and 
completed. Contract for channel enlargement, 
Item No. 3, Tyronza River was awarded and is 18 
percent complete. Contract for channel 
enlargement, Item No. 2, Parcel No. 2, Ditches 9 
and 10 was awarded; work has not begun. 
Contract for scour repairs to Bridges Nos. 3 and 4, 
Madison to Marianna was completed. Contract 
for W. G. Huxtable Pumping Plant is in progress 
and is 58 percent complete. Alteration work 
under two reimbursable contracts of Poinsett and 
Craighead county bridges across Ditches 9 and 10 
were completed. Reimbursable contract for 
42-10

MISSISSIPPI RIVER COMMISSION 
construction of U. S. Highway 70 and Arkansas 
Highway 50 levee closure is in progress and is 90 
percent complete. Reimbursable contract for 
alteration of Arkansas State Highway 69 across 
Ditches 9 and 10 is in progress and is 30 percent 
complete. Reimbursable contract for alteration of 
U. S. Highway 63 and Arkansas State Highway 
135-118 is in progress and is 57 percent complete. 
Reimbursable contract for alteration of St. Louis- 
San Francisco Railroad Bridge across Tyronza 
River is in progress and is 47 percent complete. 
Reimbursable contract for alteration of Arkansas 
Highways 149 and 118 was awarded. Work has 
not begun. Reimbursable contract was awarded 
for alteration of two county bridges across Big 
Creek; work has not commenced. Contract for 
construction of County Road No. 86 bridge, 
station 1862+37, across Tyronza River was 
awarded and is 94 percent complete. Contract for 
construction of Craighead County Road No. 2052 
bridge across Big Bay Ditch was awarded and is 5 
percent complete. 
(d) Levees. Surfacing material was placed on 
9.6 miles of levee roads. 
(e) Wappapello Lake. (See Table 42-C.) 
Development of public use facilities continued. 
About 2,115,162 persons visited the reservoir 
area. Maintenance of the dam, appurtenant 
structures, and project lands, including 
recreation facilities, was continued. Leases to 
private individuals for commercial and 
agricultural purposes continued. Missouri 
Department of Conservation maintained fish and 
wildlife conservation program under agreement 
with Secretary of Army. Water samples were 
collected and analyzed under the water quality 
investigation program. Also, wastewater 
samples were collected and analyzed and a report 
was forwarded to the United States 
Environmental Protection Agency. Maximum 
water surface elevation was 369.8 feet above 
mean sea level on Mar. 31, 1975, with a flood 
control storage of 136,062 acre-feet. Peak inflow 
was 45,700 cubic feet per second on Apr. 25, 1975. 
Maximum outflow was 9,620 cubic feet per 
second on Mar. 30, 1975. Chemical treatment for 
control of aquatic plant growth continued. 
Constructed two change shelters and a restroom 
facility and added additional camp sites. 
Completed boundary monumentation survey. 
Master plan updated by A-E contract, 
Condition at end of fiscal year. 
(a) Little River drainage. Project was initiated 
in 1938 and is 42 percent complete. 
(b), (c), & (d) St. Francis River & Tribs. (Upper 
and Lower). Project was initiated during 1937 
and is 51 percent complete. 
(e) Wappapello Lake, Mo. Project was initiated 
in 1938 and completed in 1941. 
LOWER WHITE RIVER LEVEECLARENDON 
LEVEE 
Operations and results during fiscal year. 
Contract for levee enlargement and drainage 
structures, Item No. 1, Parcel No. 1, was 
completed. 
Condition at end of fiscal year. Project was 
initiated during 1972 and is 61 percent complete. 
CACHE BASIN, ARK. 
Operations and results during fiscal year. No 
contracts for channel excavation were awarded 
or completed. 
Condition at end of fiscal year. Project was 
initiated during 1971 and is 3 percent complete. 
REELFOOT LAKE-LAKE NO. 9, TENN. 
AND KY. 
Operations and results during fiscal year. 
Contract for Lake No. 9 floodgate is in progress 
and is 62 percent complete. 
Condition at end of fiscal year. Project was 
initiated during 1974 and is 33 percent complete. 
WEST TENNESSEE TRIBUTARIES, 
TENN. 
Operations and results during fiscal year. 
(a) Obion River, Tenn. Contract for channel 
improvement, Item No. 1, Parcel No. 1, Obion 
River, Mengelwood, Tenn., was awarded; work 
has not begun. Reimbursable contract for 
alteration of Illinois Central Gulf Railroad 
bridges across South and Middle Forks, Obion 
River, is essentially complete (remaining work, 
installing sway bracing, will be performed after 
channel excavation under bridges has been 
completed by others). 
(b) Forked Deer River, Tenn. Contract for 
channel improvement, Item No. 1, North Fork, 
Forked Deer River, Middle City, Tenn., has been 
completed. Reimbursable contract for alteration 
of Illinois Central Gulf Railroad bridges across 
North and South Forks, Forked Deer River, is in 
progress and is 96 percent complete. 
Condition at end of fiscal year. 
(a) Obion River, Tenn. Project was initiated 
during 1961 and is 55 percent complete. 
(b) Forked Deer River, Tenn. Project was 
initiated during 1966 and is 19 percent 
complete. 
42-11

TABLE 42-A 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes 
0-9571 
10-81 
11-25 
38 
45 
59 
75 
44-91 
81-96 
91-104 
96-279 
101-234 
127-129 
235 
279-287 
287-303 
303-314 
306-572 
437 
437-721 
537 
605-665 
672-993 
720-725 
721-734 
--- 
42-12 
Locality 
Head of Passes, La.-Cairo, Ill. 
The Jump-New Orleans, La. 
Baptiste Collette-Bayou 
Ostrica, La. 
Homeplace, La. 
Bohemia, La. 
Myrtle Grove, La. 
Scarsdale, La. 
Bohemia, La.-New 
Orleans, La. 
New Orleans, La. 
New Orleans, La. 
New Orleans-Morganza, La. 
New Orleans-Baton Rouge, La. 
Bonnet Carrd Floodway, La. 
Baton Rouge Harbor 
Morganza Floodway, La. 
Morganza-Old River, La. 
Old River, La., control 
Old River-Cypress 
Creek, Ark. 
Vicksburg Harbor, Miss. 
Vicksburg-Lake View, Miss. 
Greenville Harbor, Miss. 
Long Lake, Helena, Ark. 
Henrico-Helena, Ark. 
St. Francis River- 
Commerce, Mo. 3 
Industrial levee (Ensley 
Bottoms) 
Memphis Harbor, Tenn. 
I : 
Improvement 
Dredging, revetment, and contraction 
work 
Main line levee, right bank 
Main line setback, left bank 
Salinity control structure, right 
bank 
Salinity control structure, left 
bank 
Salinity control structure, right 
bank 
Salinity control structure, left 
bank 
Main line levee and floodwall, 
left bank 
Main line levee, right bank 
Main line levee and floodwall, left 
bank 
Main line levee, right bank 
Main line levee and floodwall, left 
bank 
Regulating spillway, left bank 
Devils Swamp barge channel 
Regulating spillway, right bank 
Main line levee, right bank 
Levee closure and enlargement, 
low and high water spillway 
structures, navigation lock, 
and approach channels, 
right bank 
Main line levee, right bank 
Ha bor extension and industrial 
Main line levee, left bank 
Harbor improvements and port 
area 
Culvert and floodgate, right 
bank 
Main line levee and floodwall, right 
bank 
Main line levee, right bank 
Levee and pumping station 
Closure of Tennessee Chute, industrial 
fill, levee, harbor 
channels, etc. 
Remarks 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 81-516. 
Authorized by Public 
Law 81-516. 
Incorporated in 
MR&T by Public 
Law 80-858. 2 
Modified by Public 
Law 87-874. 
Extends up south 
bank of Old River 
to Barbre Landing. 
Authorized by Public 
Law 83-780. 
Joins Arkansas River, 
south bank levee. 
Authorized by Public 
Law 70-391. Modified 
by Public Laws 
79-526 and 83-780. 
Authorized by Public 
Law 85-500. 
Authorized by Public 
Law 79-526. 2 
Authorized by Public 
Law 79-526.

MISSISSIPPI RIVER COMMISSION 
TABLE 42-A 
(Continued) 
MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes Locality Improvement Remarks 
803-873 Tiptonville-Obion River Main line levee, left bank, levee Extension and incorextension, 
and diversion poration of existing 
Obion River project into MR&T 
by Public Law 79- 
526, Public Law 92- 
222 modified requirements 
of local 
cooperation.2 
857 Near Mud Lake, Tenn. Pumping station and adjacent Authorized in Decemchannel 
improvements ber 1970. See Table 
42-D. 
890 St. Johns Bayou, Mo. Drainage floodgate and levee Authorized by Public 
closure Law 79-526. 
890 New Madrid Flood- Drainage floodgate and levee Authorized by Public 
way, Mo. closure Law 83-183. 
890-954 New Madrid-Birds Floodway, right bank 
Point, Mo. 
902-922 Slough Bend, Hickman, Ky. Main line levee, left bank 
922 Hickman, Ky. Floodwall, left bank 
946 Peafield, Mo. Drainage floodgate Authorized by Public 
Law 89-298. 
9571 Cairo, Cairo drainage district Floodwalls and levees 
9571 Cairo, Cairo drainage district, Floodwalls, levees, and pump- 
Mounds, Mound City, ing plant 
and vicinity 
Thebes-Rock Island, Ill. Levees, both banks Intermittent (Sec. 6) 
Cape Girardeau, Mo., to Levees Intermittent (Sec. 6). 
Rock Island, Ill. 
1. Cairo, Ill., is on Ohio River about 3 miles above its 
mouth (Mississippi River mile 954 AHP). 
2. Also see Tables 42-D, "Authorizing Legislation," and 
42-E, "Incorporating and Authorizing Legislation." 
3. Commerce, Mo., is on Upper Mississippi River, 
39 miles above mouth of Ohio River. 
42-13

TABLE 42-B 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
ATCHAFALAYA BASIN, LA.' 
Atchafalaya Basin. Morganza and 
West Atchafalaya Floodways 
West Atchafalaya Floodway between 
Red River and Alabama 
Bayou 
Morganza Floodway between 
Mississippi River and Alabama 
Bayou 
Atchafalaya Basin Floodway 
between Alabama Bayou and 
Morgan City 
East protection levee (Morganza 
and Atchafalaya Floodways) 
Lacour-Red Cross 
Morganza-Morgan City 
Bayou Latenache 
Upper Pointe Coupee 
Loop area 
Bayou Fordoche-Ramah 
Bayou Sorrel' 
Bayou Sorrel Lock-Morgan 
City 
Morgan City 
Below Morgan City 
Below Morgan City 
Atchafalaya Basin Floodway 
lower protection levee 
Calumet 
Below Morgan City 
Floodway 
Floodway 
Floodway 
0-54 
27-54 
54-117 
20-27 
25-117 
27 
0-27 
31-57 
80 
53-117 
117 
117-129 
117-129 
105 
105-120 
Including lower Morganza 
Floodway guide levee. 
Through upper Morganza 
guide levee and enlargement 
of outlet channel. 
Enlargement of Bayou 
Latenache. Approved 
Jun. 4, 1970. See 
Table 42-D. 
Levee landside borrow 
pit. 
Alternate route, Gulf 
Intracoastal Waterway 
Port Allen to Morgan 
City. 
Gulf Intracoastal Waterway 
utilizes levee west 
side borrow pitchannel 
Gulf Intracoastal 
Waterway. 
Bypass route for Gulf 
Intracoastal 
Waterway. 
East of lower river. 
Bayou Teche-Wax Lake 
Outlet. 
Inclosed area between 
Wax Lake Outlet 
and Berwick. 
42-14 
Levee, upper Morganza guide 
Levee and Morgan City floodwall 
Drainage structure, Point 
Coupee, and channel 
enlargement 
Additional drainage facilities 
Drainage channel 
Lock 
Alternate navigation channel, 
Gulf Intracoastal 
Waterway 
Lock in Bayou Boeuf' 
Channel relocation 
Levees, floodwall 
Floodgate, east 
Levees, floodwall; drainage 
structures, and pumping 
plants

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
Berwick' 
Patterson 
Lock 
Water system 
West protection levee (Atchafalaya 
Basin and West Atchafalaya 
Floodways) 
Simmesport-Hamburg 
Mansura to Wax Lake Outlet 
Coulee des Grues 
West Atchafalaya Floodway 
Morganza Floodway 
Bayou Darbonne 
West Atchafalaya Floodway 
Morganza Floodway 
Bayou Courtableau 
West Atchafalaya Floodway 
Morganza Floodway 
Charenton 
Jaws-Lake Fausse Pointe 
105 Calumet 
105 Wax Lake Outlet 
Atchafalaya River 
0-54 Barbre Landing-Alabama 
Bayou 
5-6 Simmesport 
5-66 Simmesport-Bayou Garofier 
28-30 Melville 
40-41 Krotz Springs 
54-117 Below Alabama Bayou 
94-106 Mississippi River-Morgan 
City 
115 
116 
5 
5-105 
29 
29 
40 
40 
40 
41 
41 
41 
94 
94 
Lower Atchafalaya River. 
Adjustment to provide 
fresh water. 
West Atchafalaya 
Floodway. 
Through West Atchafalaya 
protection levee. 
Borrow pit channel to 
Grand Lake through 
West Atchafalaya protection 
levee. 
Restoration of drainage 
west of West 
Atchafalaya Basin protection 
levee. 
Bayou Teche and Wax 
Lake Outlet. 
To lower flood heights. 
East bank, levee 
Levee, ring, and drainage 
structure 
West bank, levee 
Levee, ring 
Levee, ring 
Channel enlargement 
12- by 125-foot navigation 
channel 
Increase channel capacities 
to decrease flood 
heights. 
Through Grand and Six 
Mile Lakes. 
42-15 
Levee fuse plug 
Protection levee 
Levee enlargement and floodgate 
extension 
Railway 
Railway 
Gated drainage structures 
Highway 
Highway 
Gated drainage control 
structures and channels 
Railway 
Railway 
Floodgate and approach 
channels 
Outlet, Charenton drainage 
canal and protection 
levee 
Floodgate, west 
Drainage canal-railway 
and highway bridges

TABLE 42-B 
(Continued) , 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head 
of Atchafalaya 
River Locality Improvement Remarks 
TECHE-VERMILION 
BASINS, LA. 
Atchafalaya River to Teche- 
Vermilion Basins 
Courtableau Basin, 
La., and outlets 
Charenton Canal 
West Atchafalaya protection 
levee borrow pit channel 
Bayou Courtableau spillway 
Bayou des Glaises 
BAYOU COCODRIE AND 
TRIBUTARIES 
Bayou Courtableau 
Bayou Cocodrie 
Bayous Cocodrie-Bouef 
diversion 
Bayou Boeuf 
Bayous Boeuf-Rapides 
diversion 
Upper Cocodrie 
Bayou Boeuf 
Bayou Lamourie to Kincaid 
Structures 
Lecompte Control Structure 
Bayou Rapides Control 
Structure 
Bayou Lamourie Control Structure 
Various 
LAKE PONTCHARTRAIN, LA. 
Lake Pontchartrain, Jefferson 
Parish, La. 
AMITE RIVER, LA. 
Amite River, La. 
Pumping station above 
Krotz Springs, conveyance 
channels, and appurtenant 
works 
Drainage channel 
Drainage channel 
Drainage control structure 
Diversion channel 
Enlargement and additional 
culverts 
Enlargement and realinement 
New channel 
New channel 
New channel 
Enlargement, clearing, 
and snagging 
Enlargement, realinement, 
clearing, and snagging 
Fixed elevation weir 
Gated drainage stricture 
Gated drainage structure 
Railway, highway, and 
local road bridges, 
and pipeline crossing 
Flood protection 
Bank protection 
Freshwater distribution 
from Atchafalaya 
River to Teche- 
Vermilion Basins. 
Outlet to gulf. 
Intercepting drainage 
channel. 
Washington to west 
protection levee 
(2,3) 
Authorized by Public 
Law 81-516. Eliminated 
by Public Law 
89-298. 
42-16 
Mileage 
Above 
Mouth 
0-8 
50-133 
96 
133 
0-17 
17-40 
40-51 
51-60 
17-42 
87-107 
40 
60 
87

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Above 
Mouth Locality Improvement Remarks 
82-145 
3-56 
3-56 
56 
0-32 
0-56 
151-235 
210-286 
286-296 
0-75 
0-8 
0-7 
0-33 
0-10 
0-9 
0-14 
LOWER RED RIVER, SOUTH 
BANK, RED RIVER 
LEVEES, LA. 
Moncla-Hotwells 
Red River-Moncla to 
Lake Long 
EASTERN RAPIDES AND 
SOUTH-CENTRAL AVOYELLES 
PARISHES, LA. 
Eastern Rapides and south-central 
Avoyelles Parishes, La. 
TENSAS BASIN, ARK. AND 
LA. 
Red River backwater area 
Tensas-Cocodrie area 
Larto Lake-Jonesville 
Sicily Island area 
Below Red River area 
Black River, La. 
Jonesville, La. 
Ouachita River 
Boeuf and Tensas Rivers and 
Bayou Macon, Ark. and La. 
Boeuf River, Ark. and La. 
Below Bayou Lafourche 
Bayou Lafourche 
Boeuf River, Ark. and La., 
above Bayou Lafourche 
Canal 19 
Canal 19 extension 
Big and Colewa Creeks 
Tributaries of Boeuf River- 
Canal 19 
Fleschmans Bayou 
Caney Bayou 
Big Bayou 
Canal 18 
Kirsch Lake Canal 
Black Pond Slough 
Intermittent (Sec. 6). 
Authorized by Public 
Law 91-611. 
(4) 
(4) 
(4) 
(4) 
Levee, south bank 
Levees 
Flood protection and 
drainage improvement 
Levees, drainage channels, 
structures, and pumping 
plant 
Levees, drainage channels, 
and structures 
Levees, drainage channels, 
and structures 
Levees, drainage channels, 
and structures 
Levees, floodwall, pumping 
plant, and interior 
drainage 
Levees, drainage channels, 
and structures 
Clearing 
Channel improvement and 
realinement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvements 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
(6) 
(6) 
(5) 
(6) 
(6) 
(6) 
42-17 
Portion of levee built 
under Sec. 6. Incorporated 
in MR&T by 
Public Law 81-516.2 
Monroe to Sandy Bayou 
and Bawcomville 
(Sec. 6). 
(5) 
(5) 
Authorized by Public 
Laws 78-534 and 
79-526.2,3 
(r 
Authorized by Public 
Law 78-534.3

TABLE 42-B 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Above 
Mouth Locality Improvement Remarks 
0-170 
0-34 
0-35 
Lake 
Chicot 
0-6 
0-160 
0-16 
0-0.2 
23-98 
35-98 
48-102 
0-75 
0-381 
75-366 
75-345 
45-109 
,75 
127 
185 
Channel improvement 
Channel improvement 
Channel improvement 
To divert flows from Lake 
Chicot 
Clearing 
Channel improvement 
Channel improvement 
Filling canal 
See Table 42-E. 
(5) 
(5) 
Authorized by Public 
Law 90-483. 
(6) 
Authorized by Public 
Law 78-534.3 
Authorized by Public 
Law 89-293. 
Authorized by Public 
Law 81-516. 
Bayou Macon, Ark. and La. 
Bayou Macon 
Canal 43 
Canal 81 
Pumping plant and drainage 
structure 
Tributary of Bayou Macon 
Rush Bayou 
Tensas River, Ark. and La. 
Tensas River 
Tributary of Tensas River 
Mill and Vidal Bayous 
Grant's Canal, La. 
Grant's Canal at 
Lake Providence 
LOWER ARKANSAS 
RIVER, ARK. 
Yancopin-Pine Bluff 
Fletcher Bend, Ark., to 
Pine Bluff 
North Little Rock to 
Gillett (below Plum 
Bayou) 
GRAND PRAIRIE-BAYOU 
METO, ARK. 
Grand Prairie Region and 
Bayou Meto Basin, Ark. 
YAZOO BASIN, MISS. 
Yazoo Backwater area 
Yazoo River below Arkabutla 
Lake 
Yazoo River between Yazoo 
City and Prichard 
Yazoo River between Yazoo 
City and Askew 
Will M. Whittington Auxiliary 
Channel 
Yazoo City protection 
Rocky Bayou area 
Belzoni protection 
Greenwood protection 
Water supply and drainage 
improvements 
Levees and pumping plants 
Channel improvement 
Levees, right bank 
Levees, left bank 
(5) 
Authorized by Public 
Law 81-516. 
Including Tallahatchie 
and Coldwater Rivers. 
Intermittent. 
Intermittent. 
Floodway channel 
Levee, drainage structure, 
and pumping plant 
Channel clearing and 
enlargement 
Levee and floodwall 
Levees, channel improvement, 
drainage structures, 
and pumping plants 
Improvement of 7.8 
miles was approved 
Apr. 29, 1970. 
42-18 
Levee, south bank 
Revetment 
Levee, north bank

TABLE 42-B 
(Continued) 
Mileage 
Above 
Mouth 
381 
0-64 
64 
0-24 
0-26 
26 
0-13 
13
0-88 
137-260 
75-381 
0-7 
0-23 
0-42 
275-290 
0-204 
0-8 
0-28 
0-81 
0-43 
0-4 
0-27 
MISSISSIPPI RIVER COMMISSION 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Locality 
Arkabutla Lake 
Yalobusha River below 
Grenada Lake 
Grenada Lake 
Tallahatchie River-Little 
Tallahatchie River 
Little Tallahatchie River 
below Sardis Lake 
Sardis Lake 
Yocona River below Enid Lake 
Enid Lake 
Cassidy Bayou below Old 
Coldwater River 
Upper auxiliary channel 
Area between main stem and 
hills including Bobo Bayou 
McKinney Bayou 
Alligator-Catfish Bayous 
Bear Creek 
Whiteoak Bayou 
Tallahatchie River, Miss. 
Big Sunflower River, etc. 
Big Sunflower River 
Hull Brake-Mill Creek Canal 
Hushpuckena River 
Quiver River 
Gin and Muddy Bayous, Miss. 
Bogue Phalia 
Ditchlow Bayou 
Little Sunflower River 
42-19 
Improvement 
Flood detention and 
conservation 
Channel improvement 
Flood detention and 
conservation 
Levees, Panola-Quitman 
Floodway 
Channel improvement 
Flood detention and 
conservation 
Channel improvement 
Flood detention and 
conservation 
Channel improvement 
Floodway channel 
Levees and channel 
improvement 
Channel improvement and 
enlargement of pumping 
plant 
Channel improvement 
Channel improvement 
Channel improvement 
Two road crossings of Panola- 
Quitman Floodway, Miss., and 
for protection of Sheley 
Bridge 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Remarks 
See Table 42-C. 
See Table 42-C. 
See Table 42-C. 
See Table 42-C. 
Including Moores Bayou, 
Cutoff Bayou, Whiting 
Lake and outlet. 
Authorized by Public 
Law 79-526. 
Authorized by Public 
Law 79-526. 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 90-147. 
Authorized by Public 
Law 78-534. 3 
Authorized by Public 
Law 87-874. 
Authorized by Public 
Law 78-534. 3 
Authorized by Public 
Law 78-534. 3 
Authorized by Public 
Law 78-534. 3

TABLE 42-B 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Above 
Mouth Locality Improvement Remarks 
153-160 Deer Creek 
0-68 
13-55 
0-68 
99 
99-198 
122 
143 
0-196 
0-90 
0-225 
225 
0-105 
86 
0-36 
0-29 
0-17 
0-12 
0-108 
Steele Bayou 
Muddy Bayou 
LOWER WHITE RIVER 
AND BASIN, ARK. 
Laconia Circle-Old Town Lake 
Big Creek and tributaries 
Clarendon levee 
Augusta to Clarendon 
De Valls Bluff 
Des Arc, Ark. 
CACHE BASIN, ARK. 
Cache River, Ark. 
Bayou DeView, Ark. 
ST. FRANCIS RIVER AND 
BASIN, ARK. AND MO. 
Mouth of St. Francis River- 
Wappapello Dam 
Wappapello Lake 
Little River Basin 
Marked Tree, Ark. 
Tyronza River 
Big Slough Ditch 
Mayo Ditch 
Cross County Ditch 
Belle Fountain Ditch 
Drainage District No. 17 
L'ANGUILLE RIVER, ARK. 
L'Anguille River and 
tributaries, Brushy 
and First Creeks 
Channel improvement 
Channel improvement 
Water-control structure 
Levee, backwater including 
outlet 
Pumping plant 
Channel improvement 
and structures 
Levee and outlet 
structures 
Levees, outlet structures 
Levee, outlet structure, 
and pumping station 
Levee, outlet structure, 
and pumping station 
Channel improvement 
and structures 
Channel improvement 
and structures 
Floodway, levees, drainage 
channels, and structures 
Flood detention and 
conservation 
Floodway, levees, drainage 
channels, and structures 
Marked Tree Siphon 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement and 
pumping station 
Channel improvement 
42-20 
Authorized by Public 
Law 78-534.3 
Authorized by Public 
Law 78-534. 3 Modified 
in December 
1970. See Table 42-D. 
Approved Mar. 3, 
1970. See Table 42-D. 
Mile 605-645 Mississippi 
River 
(6) 
Authorized by Public 
Law 89-298. 
Authorized by Public 
Law 89-298. 
(5) 
(5) 
Authorized by Public 
Law 81-516. 
Authorized by Public 
Law 81-516. 
Authorized by Public 
Law 81-516. 
See Table 42-C. 
Authorized by Public 
Law 90-483. 
Authorized by Public 
Law 90-483. 
Authorized by Public 
Law 80-858.

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Above 
Mouth Locality Improvement Remarks 
WEST TENNESSEE 
TRIBUTARIES 
Wolf River and tributaries, 
Tenn. 
Obion River and tributaries, 
North, South, Middle, 
and Rutherford Forks 
Forked Deer River and 
tributaries, North, Middle, 
and South Forks 
REELFOOT LAKE-LAKE NO.9, 
TENN. AND KY. 
Running Reelfoot Bayou, 
Tenn. 
Bayou du Chien and Lake 
No. 9, Ky. and Tenn. 
WEST KENTUCKY TRIBUTARIES, 
KY. 
Obion Creek, Ky. 
LITTLE RIVER DIVERSION 
CHANNEL, MO. 
Delta to Ancell, Mo. 
MISSOURI RIVER, MO. 
Mouth to St. Charles, Mo. 
ILLINOIS RIVER, ILL. 
Mouth to Havana, Ill. 
OHIO RIVER, ILL., 
AND KY. 
Cairo to Mound City 
and Mounds, Ill. 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvements 
and pumping station 
Channel improvement 
Levees 
Levees 
Levees 
Floodwall, levee, revetment, 
and pumping plant 
(6) 
Authorized by 1948 
Flood Control Act. 
Authorized by 1948 
Flood Control Act. 
Authorized by Public 
Law 83-780. 
Authorized in December 
1970. See Table 42-D. 
Authorized by Public 
Law 89-298. 
Mile 49 above Cairo. 
Intermittent (Sec. 6). 
Intermittent (Sec. 6). 
1. General data concerning Bayou Boeuf, Bayou Sorrel, 
and Berwick locks where Atchafalaya Basin protection 
levees cross Gulf Intracoastal Waterway, alternate route 
to Plaquemine, La., and lower Atchafalaya River (extension 
of Bayou Teche Waterway), respectively, are in report 
of New Orleans District. 
2. Also see Tables 42-D, "Authorizing Legislation," 
and 42-E, "Incorporating and Authorizing Legislation." 
3. Public Law 81-516 modified requirements of 
local cooperation, 
4. Authorized by Public Law 77-228. Modified by Public 
Law 89-298. 
5. Authorized or incorporated in MR&T by Public Law 
79-526. 3 See Tables 42-D and 42-E. 
6. Authorized by Public Law 85-500. 
42-21 
0-22 
0-81 
0-75 
0-20 
0-47 
0-28 
0-120

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 42-C MISSISSIPPI RIVER TRIBUTARY 
DAMS AND LAKES 
Grenada Enid Sardis Arkabutla Wappapello 
Name' Lake Lake Lake Lake Lake 
River Yalobusha Yocona Little Tallahatchie Coldwater St. Francis 
Nearest town to damsite Grenada Enid Sardis Arkabutla Wappapello 
Drainage area, square miles 1,320 560 1,545 1,000 1,310 
Conservation pool: 
Area, thousand acres 10 6 11 5 4 
Volume, thousand acre-feet 86 58 108 31 31 
Elevation, feet, mean sea level 193 230 236.0 209.3 354.7 
Flood control pool: 
Area, thousand acres 65 28 58.5 33 23 
Volume, thousand acre-feet 1,252 602 1,462 494 582 
Runoff, inches 17.8 '20.2 17.7 9.3 8.4 
Outlet gates: 
Number 3 2 4 3 3 
Size, feet 7.5 by 14 8 by 16 6 by 12 8.5 by 19 10 by 20 
Capacity, thousand cubic feet per second 10.7 9.4 10.0 10.0 18.0 
Spillway: 
Type, uncontrolled Chute Chute Chute Chute Gravity 
Length, feet 200 200 400 300 740 
Elevation, crest, feet, mean sea level 231 268 281.4 238.3 394.7 
Discharge capacity, thousand cubic 52 50 132 89 229 
feet per second 
Surcharge pool: 
Area, thousand acres 106 41 90 63 32 
Volume, thousand acre-feet 1,385 554 1,447 858 521 
Runoff, inches 19.7 18.5 17.6 16.1 7.5 
Elevation, feet, mean sea level 247.5 284.0 301.0 256.3 413.7 
Dam: 
Type, earthfill Rolled Rolled Hydraulic Rolled Rolled 
Length, thousand feet 13.9 8.4 15.3 11.5 2.7 
Elevation, crest, feet, mean sea level 256.0 293.0 311.4 264.3 419.7 
1. Grenada, Enid, Sardis, and Arkabutla Lakes are in 
Yazoo River Basin, Miss.; Wappapello Lake is in St. Francis 
River Basin, Mo. 
42-22

TABLE 42-D 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
May 15, 1928 
Jun. 19, 1930 
Feb. 15, 1933 
Apr. 23, 1934 
Aug. 30, 1935 
Jun. 15, 1936 
Aug. 28, 1937 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Jul. 24, 1946 
Flood protection in alluvial valley of Mississippi River, revetment 
and contraction works and dredging to provide least 
channel depth of 9 feet and width of 300 feet below Cairo. 
Provided for allotment of the balance of emergency rescue 
funds to reimburse levee districts and others for expenditures 
in flood-control works during the 1927 and 
subsequent floods. 
Provided for ownership of lands in Bonnet Carre Spillway 
and Floodway with proviso for granting rights-of-way, 
easements, and permits, in said lands. 
Authorized payment for purchase of, or to reimburse states 
and local levee districts for the cost of, levee rightsof-
way for flood control work in the Mississippi Valley, 
and for other purposes. 
Improvement of Wolf and Nonconnah Rivers, Tenn. 
(Nonconnah Creek is correct title) 
Improvement of Wolf River (Memphis Harbor), Tenn. 
Modification of the 1928 Act to provide for: 
Construction of a backwater levee at mouth of White 
River, Ark. 
Construction of Eudora floodway in lieu of Boeuf floodway; 
flood control, Yazoo River; construction of Morganza 
floodway; and an outlet to the Gulf of Mexico west 
of Berwick, La., including a 6-year program for the 
improvement and regularization of the Mississippi River 
between Arkansas and Red Rivers, and Atchafalaya River; 
and construction of roads on levees and drainage adjustments 
incident to floodway levees. 
Provided for construction of floodwalls, levees, and revetments 
along Wolf River and Nonconnah Creek for protection 
of Memphis, Tenn. 
Modify the Yazoo River project to substitute a combined 
reservoir floodway and levee plan. 
Construction of Mounds to Mound City levee and control 
works along Cache River, Ill. 
Modification of previous act pertaining to floodways and 
outlets and lands therein; including program for the improvement 
and regularization of the Mississippi River, between 
Cairo and Arkansas River, extension of levee road system; 
strengthening of levees. 
Enlarge main line levees to offset abandonment of floodways 
between Arkansas and Red Rivers, flood control works 
in backwater areas of Yazoo and Red Rivers, and in 
Bayous Rapides, Boeuf, and Cocodrie, La. 
Navigation channel 12 feet deep and 300 feet wide 
between Baton Rouge and Cairo; flood protection of 
Yazoo River Backwater Area in vicinity of Satartia, Miss. 
Continue prosecution of channel' improvement and stabilization 
program, $200 million. 
Flood control on the Big Sunflower, Little Sunflower, 
Hushpuckena, and Quiver Rivers and their tributaries, 
and on Hull Brake-Mill Creek Canal, Bogue Phalia, Ditchlow 
Bayou, Deer Creek, and Steele Bayou, Miss. 
Improve Boeuf and Tensas Rivers and Bayou Macon, Ark.' 
Improve Bayou Lafourche, La. 
Improve Yazoo River tributaries. 
North bank, Arkansas River levees (below Plum Bayou).' 
42-23 
H. Doc. 90, 70th Cong., 
1st sess. 
Public 395, 71st Cong., 
2d sess. 
Public 351, 72d Cong. 
Public 171, 73d Cong. 
R&H Comm. Doc. 26, 72d 
Cong., 1st sess. 
R&H Comm. Doc. 45, 74th 
Cong., 1st sess. 
Unpublished report dated 
Apr. 2, 1925. 
H. Comm. on Flood Control, 
Doc. 1, 74th Cong., 
1st sess. 
Unpublished report on 
record in OCE. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 
1st sess. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 359, 77th Cong., 
1st sess. 
H. Doc. 509, 78th Cong., 
2d sess. 
Public Law 534, 78th Cong., 
2d sess. 
H. Doc. 516, 78th Cong., 
2d sess. 
S. Doc. 151, 78th Cong'., 
2d sess. 
S. Doc. 191, 79th Cong., 
2d sess. 
H. Doc. 516, 78th Cong., 
2d sess. 
H. Doc. 308, 74th Cong., 
1st sess.

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 42-D AUTHORIZING LEGISLATION 
(Continued) 
Act or 
Authorization 
42-24 
Jun. 30, 1948 
May 17, 1950 
Oct. 30, 1951 
Sep. 3, 1954 
Jul. 3, 1958 
Work Authorized 
Levees on White River (Augusta to Clarendon).' 
Bayou des Glaises diversion channel, La.' 
Modify local cooperation requirements in St. Francis and 
Yazoo Basins. 
Tiptonville-Obion levee and drainage improvements.' 
Improvement of St. Johns Bayou, Mo. 
Big Sunflower River, etc.' 
Tennessee Chute (Memphis Harbor), Tenn. 
Continue prosecution of project for flood control and 
channel improvement, $100 million. 
Improve Mississippi River below Cape Girardeau, Mo., 
with respect to West Tennessee tributaries. 
Improve L'Anguille River, Ark. 
Baton Rouge Harbor (Devils Swamp), La.' 
Flood protection at Des Arc, Ark. 
Improve St. Francis River and Basin, Ark. and Mo. 
Improve Cache River and Bayou DeView, Ark. and Mo. 
Improve Grand Prairie Region and Bayou Meto Basin, Ark. 
Flood protection, Lake Pontchartrain, Jefferson 
Parish, La.' 
Filling Grant's Canal, Lake Providence, La. 
Additional protection to Red River Backwater Area. 
Extend Federal jurisdiction to cover levees in Orleans 
Parish, La. 
Bank protection, Amite River, La. 
Continue prosecution of project for flood control and 
channel improvement, $200 million. 
Jonesville, La., levee, retaining wall, and drainage 
structure.' 
Modify requirements for local cooperation in White River 
Backwater Area, Ark. 
Navigation improvement of Atchafalaya from Mississippi 
River to Morgan City, La. 
Modify project for Vicksburg-Yazoo Area, Miss. 
Improve New Madrid Floodway, Mo. 
Control of Old and Atchafalaya Rivers and a lock for 
navigation. 
Improve Reelfoot Lake Area, Ky. and Tenn. 
Improve Greenville Harbor, Miss. 
Extensions to project for Boeuf and Tensas Rivers and 
Bayou Macon in Arkansas. 
Document 
H. Doc. 98, 76th Cong., 
1st sess. 
H. Doc. 602, 79th Cong., 
2d sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 757, 79th Cong., 
2d sess. 
H. Doc. 138, 80th Cong., 
1st sess. 
H. Doc. 516, 78th Cong., 
2d sess. 
S. Doc. 51, 80th Cong., 
1st sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 627, 80th Cong., 
2d sess. 
H. Doc. 651, 80th Cong., 
2d sess. 
H. Doc. 321, 80th Cong., 
1st sess. 
H. Doc. 485, 81st Cong., 
2d sess. 
H. Doc. 132, 81st Cong., 
1st sess. 
S. Doc. 88, 81st Cong., 
1st sess. 
H. Doc. 255, 81st Cong., 
1st sess. 
S. Doc. 139, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
S. Doc. 117, 81st Cong., 
1st sess. 
Public Law 237, 82d Cong., 
1st sess. 
S. Doc. 53, 82d Cong., 
1st sess. 
H. Doc. 85, 83d Cong., 
1st sess. 
H. Doc. 183, 83d Cong., 
1st sess. 
H. Doc. 478, 83d Cong., 
2d sess. 
S. Doc. 160, 83d Cong., 
2d sess. 
S. Doc. 15, 86th Cong., 
1st sess. 
H. Doc. 108, 85th Cong., 
1st sess.

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Jul. 14, 1960 
Oct. 23, 1962 
Jun. 18, 1965 
Oct. 27, 1965 
Oct. 27, 1965 
Nov. 7, 1966 
Nov. 20, 1967 
Aug. 13, 1968 
Sep. 10, 19682 
Mar. 3, 19702 
Apr. 29, 19702 
Jun. 4, 19702 
White River backwater area pumping plant. 
Wolf River and tributaries for flood protection in 
Tennessee. 
Continue prosecution of project for channel 
improvement-$50 million. 
Modification-Baton Rouge Harbor (Devils Swamp), La. 
Construct improvements in Gin and Muddy Bayous, Yazoo 
River Basin, Miss. 
Replace 2 bridges with adequate floodway over Boeuf River 
and Big Bayou in Boeuf Basin, Ark. 
Continue prosecution of project for flood control and 
channel improvement, $53 million. 
Modify and expand levees and channel improvement features 
of main stem project. 
Modify flood control improvements in following tributary 
areas and basins: Cairo-Mounds-Mounds City, St. Francis, 
Lower White, Boeuf-Tensas-Macon, Red River backwater, 
Yazoo headwater, Grand Prairie, and Bayou Meto. 
Acquire any modified easements required in New Madrid 
Floodway as provided by Sec. 4 of May 15, 1928 act. 
Operate and maintain pumping plant in Red River 
backwater area. 
Provide improvements in West Kentucky tributaries. 
Provide fish and wildlife facilities in St. Francis and 
Big Sunflower Basins; Yazoo Headwater and Backwater 
Areas; and Mississippi Delta region. 
Deauthorize Amite River, La., project. 
Modify St. Francis River, Mo. and Ark., project within 
District No. 7, Poinsett County, Ark. 
Construction of improvements to supplement freshwater 
supply in Teche-Vermilion Basins in Louisiana. 
Bank revetment for protection of existing industrial facilities 
along Mississippi River below Baton Rouge, La. 
Modification of West Tennessee tributaries feature to provide 
relocation of gas transmission lines at Federal 
expense. 
Continue emergency work, $87,135,000, which includes 
$100,000 for road crossing of Panola-Quitman Floodway, Miss., . 
and $80,000 for protection of Sheley Bridge, Tallahatchie 
River, Miss. 
Improvements in Boeuf and Tensas Rivers and Bayou Macon 
Basin to divert flows that would otherwise enter Lake 
Chicot, Ark. 
Improvements in the Belle Fountain ditch and tributaries, 
Mo., and Drainage District No. 17, Ark. 
Provide pumping plants and other drainage facilities in 
Cairo, Ill., and vicinity. 
Modification of Yazoo Headwater Project to include cleanout 
along David Bayou, Miss. 
Modify Yazoo Backwater feature to include a control structure 
in Muddy Bayou, Miss. 
Modification of Yazoo Headwater Project to include drainage 
structure and channel improvement on Rocky Bayou, Miss. 
Provide for enlargement of Bayou Latenache from Pointe 
Coupee drainage structure to Alabama Bayou, La. 
42-25 
S. Doc. 26, 85th Cong., 
1st sess. 
H. Doc. 76, 85th Cong., 
1st sess. 
Public Law 86-645. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 89-42. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
S. Doc. 57, 89th Cong., 
1st sess. 
H. Doc. 524, 89th Cong., 
2d sess. 
Public Law 89-789. 
Public Law 89-789. 
Public Law 90-147. 
H. Doc. 168, 90th Cong., 
1st sess. 
H. Doc. 339, 90th Cong., 
2d sess. 
Public Law 90-483. 
Unpublished MRC report 
dated May 8, 1968. 
Unpublished MRC report 
dated Feb. 2, 1970. 
Unpublished MRC report 
dated Mar. 6, 1970. 
Unpublished MRC report 
dated Sep. 22, 1969.

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Dec. 31, 1970 
Senate and House 
Public Works 
Resolutions 
adopted Dec. 17 
and 15, 1970, 
respectively.3 
River Basin 
Monetary Act of 
Dec. 23, 1971 
Jan. 19, 19734 
TITLE I Water 
Resources Development 
Act of 
1974, approved 
Mar. 7, 1974 
Modify and expand project to include flood protection 
within the area of eastern Rapides and south-central 
Avoyelles Parishes, La., that are drained by Bayou des 
Glaises diversion channel and Lake Long, and their 
tributaries. 
Modify the project for West Kentucky tributaries (Obion 
Creek), Ky., to provide for all relocations, at Federal 
expense, of all transmission lines required by the 
project. 
Report on Western Tennessee Tributaries, Tenn. and Ky., 
authorized: 
a. Modification of Reelfoot Lake feature to provide 
channel improvements on Bayou du Chien and Lake 
No. 9 in Ky. and Tenn. 
b. Modification of Mississippi levee feature to 
include a pumping station near Mud Lake floodgate 
and adjacent channel improvements. 
Modification of Big Sunflower Basin feature to provide 
additional improvements in Steele Bayou 
Basin, Miss. 
Continue prosecution of project for the comprehensive 
development of the basin, $97 
million 
Modification of Tiptonville-Obion River levee feature 
to relieve local interests of all responsibility except 
that of providing maintenance. 
Modification of the Mississippi levee feature to provide 
additional drainage facilities in Long Lake area, 
vicinity of Helena, Ark. 
Projects recommended by four completed reports were 
authorized for accomplishment of Phase I design memorandum 
of advance engineering and design on: 
a. Greenville Harbor, Greenville, Miss. 
b. East bank of Mississippi River, Warren to 
Wilkinson Counties, Miss. (Natchez area). 
c. East bank of Mississippi River, Warren to 
Wilkinson Counties, Miss. (Vicksburg-Yazoo area). 
d. Bushley Bayou Area of Red River backwater 
area, La. 
Modification of West Tennessee tributaries feature (Obion 
and Forked Deer Rivers), Tenn., to acquire lands for fish 
and wildlife, recreation, and environmental purposes. 
Modification of the Yazoo Basin, Miss., feature to provide 
for a streambank erosion control demonstration project for 
the delta and hill areas of basin. 
Modification of project to provide that the Secretary 
of the Army, acting through the Chief of Engineers, can 
substitute authorized mitigation lands, not yet acquired and no 
longer suitable, for like acreage in the same or adjacent 
subbasins of the project area. This section provides the 
authority to substitute authorized mitigation lands in: 
a. Tensas Basin, La. and Ark., feature (Red River 
backwater). 
b. St. Francis Basin, Ark. and Mo., feature. 
Modification of Bayou Cocodrie and tributaries, La., 
feature, to provide for: enlargement of Bayou Courtableau 
from Washington to west protection levee; right-of-way and 
spoil disposal areas at Federal expense; and necessary 
additional culverts through west protection levee. 
S. Doc. 91-113, 
2d sess. 
Public Law 91-611. 
H. Doc. 91-414, 
2d sess. 
S. Doc. 91-74, 
2d sess. 
Sec. 1, Public 
Law 92-222. 
Sec. 7, Public 
Law 92-222. 
Unpublished Memphis 
District's MRC report 
dated Oct. 4, 1972. 
Sec. 1, Public 
Law 93-251. 
S. Doc. 93-38, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-149, 1st sess. 
H. Doc. 93-157, 1st sess. 
Sec. 3, Public 
Law 93-251. 
Sec. 32, Public 
Law 93-251. 
Sec. 42, Public 
Law 93-251. 
Sec. 87, Public 
Law 93-251. 
42-26

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Modification of Cache River Basin, Ark., feature to Sec. 99, Public 
provide for: acquisition by fee easements of lands for Law 93-251. 
fish and wildlife management, recreation, and environmental 
purposes. 
TITLE II River Continue prosecution of project for the comprehensive Sec. 201, Public 
Basin Monetary development of the basin, $211 million. Law 93-251. 
Authorization 
Act of 1974, 
approved Mar. 7, 
1974. 
1. Incorporated into Mississippi River and tributaries 
project as shown in Table 42-E. 
2. Date minor modification was approved under discretionary 
authority of Chief of Engineers contained in May 15, 
1928, Flood Control Act, as amended. 
3. Projects approved under the provisions of Sec. 201 of 
Flood Control Act of Oct. 27, 1965. 
4. Date minor modification for blocked drainage was approved 
under delegated authority of the President, Mississippi 
River Commission, and in accordance with Sec. 10(p) of the 
1946 Flood Control Act (Public Law 79-526). 
42-27

REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
TABLE 42-E INCORPORATING AND AUTHORIZING LEGISLATION 
For Last 
Public Full Report 
Act of Law Authorizing See Annual 
Incorporation No. Act Description Report for 
Jul. 24, 1946 79-526 Jun. 22, 1936 Tiptonville-Obion levee and drainage improve- 1941, p.943 
ments, Tenn. 
Jul. 24, 1946 79-526 Jun. 22, 1936 Bayou des Glaises diversion ditch, La. 1946, p. 1029 
Jul. 24, 1946 79-256 Jun. 22, 1936 From North Little Rock, Ark., to Gillett, Ark., 1946, p. 1053 
on north bank of Arkansas River (portion 
below Plum Bayou). 
Jul. 24, 1946 79-256 Aug. 18, 1941 White River levees, Augusta to Clarendon and 1946, p. 1083 
De Valls Bluff, Ark. 
Jul. 24, 1946 79-526 Dec. 22, 1944 Boeuf and Tensas Rivers and Bayou 1945, p. 982 
Macon, La. 
Jul. 24, 1946 79-526 Dec. 22, 1944 Big Sunflower River, etc. 1946, p. 1061 
Jun. 30, 1948 80-858 Jul. 24, 1946 Devils Swamp barge channel at Baton 1948, p. 1059 
Rouge, La. (Baton Rouge Harbor) 
May 17, 1950 81-516 Jun. 22, 1936 Jonesville, La. 1953, p. 773 
May 17, 1950 81-516 Jul. 24, 1946 Lake Pontchartrain-Jefferson Parish, La. 1953, p. 737 
42-28

MISSISSIPPI RIVER COMMISSION 
TABLE 42-F SUMMARY OF PRESENTLY ESTIMATED 
FEDERAL FIRST COST OF 
AUTHORIZED IMPROVEMENTS 
Project Title 
Estimated Cost 
FY 75 
Completed features' 
Mississippi River levees 
Mud Lake Pumping Station, Tenn. 
Sec. 6 levees, 1928 Flood Control Act 
Channel improvement 
Baton Rouge Harbor, La. 
Atchafalaya Basin, La. 
Bayou Cocodrie and tributaries, La. 
Old River, La. 
Lower Red River-- 
South Bank Red River levees, La. 
Eastern Rapides and south-central Avoyelles Parishes, La. 
Mississippi Delta Region, La. 
Teche-Vermilion Basins, La. 
Tensas Basin, Ark. and La. 
Lower Arkansas River, Ark. 
Grand Prairie-Bayou Meto, Ark. 
Yazoo Basin, Miss. 
Lower White River, Ark. 
Cache Basin, Ark. 
St. Francis Basin, Ark. and Mo. 
L'Anguille Basin, Ark. (Inactive) 
West Tennessee tributaries, Tenn. 
Reelfoot Lake-Lake No. 9, Tenn. & Ky. 
Reelfoot Lake, Tenn. & Ky.(Completed) 
Reelfoot Lake-Lake No. 9, Tenn. & Ky. 
West Kentucky tributaries, Ky. 
TOTAL 
$ 164,733,000 
950,000,000 
1,080,000 
4,000,000 
2,027,000,000 
7,590,000 
849,000,000 
14,500,000 
81,200,000 
29,700,000 
31,900,000 
17,600,000 
18,900,000 
231,400,000 
30,300,000 
94,600,000 
627,000,000 
35,500,000 
86,000,000 
258,000,000 
9,150,000 
43,400,000 
(9,700,000) 
440,000 
9,260,000 
5,900,000 
$5,628,153,000 
1. Includes Bonnet Carr, Morganza, and New Madrid Floodways; Memphis, Greenville, and Vicksburg Harbors; 
Lake Pontchartrain; Wolf River; completed roads on main stem levees; channel construction works; Atchafalaya River 
and Basin; Wax Lake Outlet; Charenton Canal; Bayou des Glaises diversion channel, Boeuf Basin levees; Grant's 
Canal; De Valls Bluff, Jonesville, and Des Arc protection works; and miscellaneous features. 
42-29

TABLE 42-G 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
MISSISSIPPI RIVER MAIN STEM 
CHANNEL IMPROVEMENTS 
Operations in 1,000 Cubic Yards 
Location Fiscal Year 1975 
Mileage 
Above Head Channel 
District of Passes Construction Maintenance Total 
New Orleans 
Baton Rouge Harbor 
(Devils Swamp) 235 - 105 105 
Main stem channel 234-320 - 0 0 
Vicksburg 
Main stem channel 320-600 - 10,157 10,157 
Vicksburg Harbor 437 - 160 160 
Greenville Harbor 537 - 846 846 
Memphis 
Main stem channel 600-954 5,174 23,775 28,949 
Memphis Harbor 726 - 643 643 
TOTAL 5,174 35,686 40,860 
42-30

TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun. 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Lower Childress-Fort Jackson, La... 
Buras, La . ................. ...... 
Tropical Bend, La. ................ 
Port Sulphur, La ................ 
Diamond, La............ ......... 
Gravolet, La....................... 
Junior, La.................. ....... 
Alliance, La....................... 
Jesuit Bend, La..................... 
Oak Point, La ................... 
Poydras, La...................... 
Cutoff, La ...... ............. 
Third district reach, La. ........... 
Algiers Point, La ................ 
Gouldsboro Bend, La............... 
Gretna Bend, La ................. 
Greenville Bend, La .............. 
Carrollton Bend, La .............. 
Avondale Bend, La ............... 
Kenner, La ...... ........ ......... 
Luling, La......................... 
Good Hope, La .................... 
Waterford, La...................... 
Montz, La......................... 
Lucy, La. ................. ......... 
Reserve, La ... ......... ......... 
Vacherie, La...................... 
Belmont, La...................... 
Rich Bend, La.................... 
Romeville, La..................... 
St. Alice, La...................... 
Burnside, La..................... 
22 
25 
30 
39 
49 
51 
54 
62 
68 
72 
82 
88 
93 
95 
96 
97 
100 
104 
109 
114 
119 
126 
128 
132 
136 
138 
148 
152 
157 
161 
165 
170 
R
R
R
R
R
L
R
R
R
R
L
R
L
R
R
R
R
L
R
L
R
L
R
L
R
L
R
L
R
L
R
L 
1,790 
7,040 
1,890 
-_ 
8,510 
10,650 
4,195 
27 
25 
45 
6,277 
27,993 
11,186 
7,124 
17,283 
20,692 
13,823 � 
8,750 
6,230 
5,690 
7,150 
17,545 
7,040 M 
12,040 
4,290 0 
21,101 
7,728 
4,960 
9,662 S 
22,045 
15,015 
22,371 
9,089 
27,528 
14,980 
4,340 
5,965 
11,916 
20,947 
13,295 
10,650 
10,625 
7,540 
3,492 
16,050 
34,579 
44,737 
23,959 
-_ 
-_

TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(Continued) (Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun. 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER-continued 
Standard revetment: 
Marchand, La. ..................... 180 
Philadelphia Point, La. ............. 183 
New River Bend, La. ............... 185 
White Castle, La. .................. 193 
St. Gabriel, La. ... :................. 201 
Plaquemine Bend, La. .............. 209 
Manchac, La ....................... 215 
Missouri Bend, La. ................. 222 
Arlington, La. ...................... 227 
Port Allen, La ..................... 231 
Allendale, La. ...................... 238 
Springfield Bend, La. .............. 244 
Arbroth, La. ....................... 250 
Grand Bay, La ..................... 258 
Bayou Sara, La .................... 265 
Red Store, La ..................... 269 
Arrow Bend, La. ................... 272 
Boies Point, La..................... 275 
Morganza, La ...................... 279 
Iowa Point, La ..................... 282 
Brunette Point, La. ................. 285 
Greenwood Bend, La................ 289 
Hog Point, La. ..................... 296 
Carr Point, La. .................... 304 
Above Old River, La. ............... 305 
Fort Adams, Miss. ................. 308 
Point Breeze, La. ................... 313 
Coochie, La. ................... 317 
Palmetto, Miss..................... 322 
Subtotal New Orleans District, 
Mississippi River ............. 
L
R
L
R
L
R
L
R
L
R
R
L
R
R
L
R
L
R
R
L
R
L
R
R
R
L
R
R
L 
7,570 
13,516 
65 37,010 
80,495 
676 2,514 
_ 
0 
4,660 
5,379 0 
24,394 T 
16,552 m 
14,371 T 
35,475 
13,516 p 
16,193 T 
12,244 0 
11,320 j 
17,940 
25,690 
13,190 
7,090 
4,780 c 
7,830 . 
13,600 i 
16,094 > 
20,513 
11,375 4 
8,038 $ 
14,987 e 
8,673 
8,600 
4,800 
17,219 
4,850 
14,660 
30,864 
1,363 
4,309 
1,563 
3,834 
1,551 
1,747 
2,282 
8,436 
55,161 
(10.45 Miles) 
162 266,236 676 
(0.13 Mile) 
2,514 25,085 - 791,853 
(149.97 Miles) 
Dikes: 
None 
m 
>

OLD RIVER CONTROL 
Standard revetment: 
Inflow channel ......... ............... 315 L 
Inflow channel ..................... 315 R 
Outflow channel .................... 315 R 
Total standard revetment, 
Old River ................... 
Dikes: 
None
ATCHAFALAYA RIVER 
Standard revetment: 
Mile One, La........................ 
Coville Bayou, La. .................. 
Legonier, La. ................ 
Simmesport, La..................... 
Odenburg, La ..................... 
McCrea, La. ....................... 
Woodside, La. ................ 
Provosty, La. ............ ........ 
Crooked Bayou, La ................ 
Mercier, La ...................... . 
Evans Point, La ................. 
Goudeau, La. ...................... 
Morris Bayou, La.................. 
Goodwood, La. ................ 
Melville, La ..................... 
Cross Bayou, La. ....... ...... 
Melville South, La. ................ 
Toles, La.......................... 
Petite Prairie, La . ................. 
Holloway Lake, La.............. 
Krotz Springs, La .................. 
Sherburne, La...................... 
Morgan City, La ................. 
Total standard revetment ......... 
Below Confluence 
of Red and 
Atchafalaya 
Rivers 
1 L 
3 R 
4 L 
6 R 
9 R 
13 L 
14 R 
17 L 
18 R 
22 L 
24 L 
26 R 
27 L 
28 R 
30 R 
31 L 
33 R 
35 L 
36 R 
37 L 
40 R 
43 R 
115 L 
Dikes: 
None 
5,375 
2,015 
3,150 
320 
3,815 
7,085 
7,035 
28,795 
(5.45 Miles) 
320 
200 
12,606 
11,144 
12,316 
2,303 
20,904 
30,651 
34,123 
124,047 
485 
445 
300 
780 
4,080 
6,090 
(1.15 Miles) 
1,478 
1,159 
1,282 
3,065 
13,688 
20,672 
973 
503 
11,981 
8,895 
13,351 
6,101 
41,804 
4,150 - 
6,550 
8,940 ( 
10,636 3 
5,375 z 
5,027 ' 
13,002 4 
7,768 
9,600 4 
8,520 
2,880 ) 
3,938 
3,800 Z 
4,355 
4,870 
3,815 
4,070 
6,355 
3,810 
7,085 
4,625 
7,035 
3,410 
139,616 
(26.44 Miles) 
26,065 
26,065 
2,415 
2,785 
6,100 
11,300 
(2.14 Miles) 
co

TABLE 42-H 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun. 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
LOWER RED RIVER 
Standard revetment: 
Naples, La...................... 
Turnbull Island, La. ............... 
Total standard revetment ......... 
RED RIVER2 
Standard revetment: 
Dupre, La .................. ....... 
Egg Bend, La. .................... 
Cologne Bend, La................... 
Roxana, La........................ 
Ryland, La. ................ ........ 
Latanier, La...................... 
Hudson, La........................ 
Alexandria Front, La. ............. 
Rapides, La........................ 
Boyce, La . ............... ........ 
Total standard revetment, 
Red River ............... 
Dikes:3 
Choctaw Bayou Bend, La. .......... 
Bringol (Egg Bend), La. ........... 
Egg Bend, La..................... 
Cologne Bend, La. ............ 
Echo, La ................. ........ 
Richardson, La .................. 
Alexandria, La .................. 
Bertrand, La. .................... 
Total dikes, Red River ............ 
Above Confluence 
of Old and 
Mississippi 
Rivers 
7 R 
9 L 
69 
75 
77 
83 
88 
93 
99 
105 
119 
125 
71 
73 
75 
77 
78 
79 
105 
122 
3,110 
3,110 
-_ 
-_ 
_
-_ 
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R 
- 6,190 
- 6,815 
- 13,005 
(2.46 Miles) 
- 2,690 
- 2,400 
- 650 
- 3,325 
- 3,925 
- 2,460 
- 1,458 
- 5,280 
- 1,030 
- 4,548 
- 27,766 
(5.26 Miles) 
- 2,000 
- 2,477 
- 900 
- 1,850 
- 1,900 
- 2,700 
(rock groin) 270 
- 7,630 
- 19,727 
(3.74 Miles) 
1. Gross squares articulated concrete mattress 
(100 square feet). 
2. Mileages based on 1967 hydrographic 
3. Includes all types of dikes and retards. 
cF3 
C
0
0
C
y
r
C
c' 
Cl' 
survey. 
---

TABLE 42-I BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operativ 
Head Bank Exten- Jun, 30, Jun. 30 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Bougere Bend, La.................. 329 R - - - - - - - 20,805 
Morville, La. ....................... 356 R - - - - - 5,730 
Natchez Island, Miss. ............... 357 R - - - - - - 2,180 
Carthage, Miss. .................... 361 L - - - - - - - 6,180 
Natchez Front, Miss. ............... 364 L - - - - - - 6,045 
Gibson, La........................ 371 R 9,515 - 36,295 565 1,133 11,976 - 21,285 
Kempe Bend, La ................... 383 R 1,220 - 4,965 140 391 8,383 - 20,400 
Browns Field, La. .................. 389 R - - - - - 9,285 - 9,280 
Goldbottom, Miss. ................. 392 L 3,080 - 9,248 1,739 5,184 16,821 - 26,380 
Hardscrabble, La .................. 398 R - . -1,534 - 22,53 
Grand Gulf, Miss. .................. 403 L 5,285 - 19,209 - -6,976 - 36,200 
Point Pleasant, La.-Miss............ 413 R - - - - - 19,559 - 32,34 
Lake Karnac, La.-Miss. ............. 419 L - - - - - - 19,260 
Diamond Point, La.-Miss. ........... 423 R - - - - - 12,12 
Reid-Bedford, La. .................. 429 R - - - - - 18,392 
Racetrack, Miss .................... 433 L - - - - - 13,93 
Barge Line Terminal, Miss. ......... 437 L - - - - - - - 3,040 
Vicksburg Harbor, Miss. ........... 437 L - - - - - - 7,350 
Delta Point, La. .................... 437 R 590 - 1,704 - - - 7,650 
King's Point-Opposite 
Delta Point, La.-Miss............... 439 L - - - - - 19,33( 
False Point, La. .................... 443 R - - - 735 1,921 2,566 - 12,86( 
Marshall-Brown's Point, La.-Miss. ... 446 L - - - - - - - 19,58( 
Milliken Bend, La. ................. 453 R - - - - 12,984 - 44,65 
Belle Island, La.-Miss. .............. 460 L - - - - 5,991 - 23,16( 
Goodrich, La. ...................... 467 R - - - - - 32,30 
Fitler-Cottonwood, Miss. ............ 474 L - - - - - 3,926 - 28,42 
Hagaman, La...................... 481 R 37,75( 
Ben Lomond, Miss. ................. 486 L 10,23 
Baleshed Towhead-Stack Island, 
La.-Miss ......................... 488 R - - - - - 2,162 - 44,31 
Lake Providence, La. ............... 489 R - - - - 11,60( 
Mayersville, Miss. .................. 497 L - - - - 1,995 - 31,46 
Sarah Island-Opossum Point, 
La.-Miss......................... 503 R - - - - 16,97( 
Carolina, Miss. .................... 507 L - - - - - - - 11,08(
e 
ci: 
IIf 
1
C,, 
C,) 
Cz
i 
- 
i 
Cf

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun, 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER--continued 
Standard revetment: 
Cracraft, Ark ..................... 
Worthington, Miss.-Ark............. 
Walnut Point Kentucky 
Bend, M iss . ............ ........ 
American Cutoff, Miss.-Ark. ........ 
Sunnyside-Lakeport, Ark. .......... 
Vaucluse, Ark...................... 
Island 84, Ark.-Miss........... 
Warfield Point, Miss................ 
LaGrange Towhead, Miss. .......... 
Spanish Moss, Ark ............... 
Leland Cutoff, Ark.................. 
Tarpley Island, Miss ............. 
Miller Bend, Miss ................ 
Island 82, Ark...................... 
Ashbrook Island, Miss. ............ 
Arkansas City-Yellow Bend, Ark. ... 
Huntington Point, Miss. ........... 
Pair O'Dice, Ark ................. 
Eutaw-Mounds, Miss........... 
Cypress Bend, Ark ............... 
Catfish Point, Miss ............... 
Ozark, Ark.-Miss ................ 
Prentiss, Ark.-Miss. ............... 
Rosedale Bend, Ark. ............... 
Riverton, Miss..................... 
Klondike, Ark...................... 
Victoria Bend-Terrene, Miss. ....... 
Big Island, Ark..................... 
Smith Point, Miss ................ 
Dennis, Miss. ....... ......... 
Cessions, Miss . . ................. 
Total revetment, Vicksburg 
District, Mississippi River .... 
511 R 
514 R 
519 
526 
530 
534 
535 
537 
538 
539 
539 
542 
544 
546 
549 
553 
556 
561 
563 
568 
573 
578 
582 
585 
586 
588 
593 
598 
601 
611 
615 
L
L
R
R
L
L
L
R
L
R
L
R
R
R
L
R
L
R
L
R
L
L
L
R
L
R
L
L
L 
19,690 
(3.73 Miles) 
71,421 
1,055 
635 
4,065 
-_ 
-_ 
-_ 
_ 
_
-_ 
-_ 
-_ 
-35 
_
-,06 
-_ 
-_ 
-_ 
8,934 
2,897 
-_ 
5,724 
4,453 
12,508 
2,235 
_ 
1,865 
11,752 
25,143 
(1.69 Miles) 
5,367 
-_ 
-_ 
134,445 
Cb3 
22,210 
8,350 'O 
45,653 
2,980 
33,685 n 
4,300 
13,475 M 
4,320 
9,130 m 
4,580 M 
1,300 
2,000 Z 
29,360 
3,080 
3,455 
40,560 
10,045 - 
9,095 
36,023 
26,585 C 
20,075 * 
22,015 m 
20,315 
4,820 
12,500 
23,400 
29,245 
16,515 
18,185 
14,520 
10,910 
1,137,518 
(215.44 Miles) 
--

Dikes:2 
Natchez Island, La.-Miss. .......... 
Waterproof Bar, La .............. 
Cottage Bend, La.-Miss ........... 
Bondurant Towhead, La. ........... 
Coffee Point, La.................... 
Yucatan, Miss ................... 
Togo Island, La..................... 
Below Racetrack, Miss. ............ 
Racetrack Towhead, Miss. .......... 
Willow Cutoff, La ................ 
Point Lookout, La ................ 
Ajax Bar, Miss .................. 
Ben Lomond, Miss ............... 
Baleshed Ldg., Miss .............. 
Wilson Point, La .................. 
Carolina, Ark ..................... 
Cracraft Lower, Ark. .............. 
Cracraft, Ark ..................... 
Leota, Miss........................ 
Island 86, Ark...................... 
Seven Oaks, Ark.................... 
Walnut Point, Miss .............. 
Island 84, Ark................. 
Leland Bar, Ark.-Miss. ............ 
Leland Neck, Ark.............. 
Tarpley Cutoff, Miss.-Ark. ......... 
Island 82-Miller Bend, 
Ark.-M iss . ...................... 
Ashbrook-Miller Bend, 
Ark.-Miss ............. ........... 
Ashbrook Cutoff, Miss........... 
Chicot Ldg., Ark... ................ 
Catfish Point, Miss.................. 
Below Prentiss, Miss. .............. 
Malone Field, Ark ............... 
Terrene, Miss. ..................... 
White River Landing, Ark. ......... 
Montgomery Towhead, Ark. ........ 
Smith Point, Miss, .................. 
Island 70, Miss. ..................... 
Total dikes, Vicksburg 
District, Mississippi River .... 
358 
379 
389 
394 
405 
410 
416 
430 
431 
462 
478 
482 
488 
493 
500 
509 
510 
513 
514 
520 
523 
525 
532 
538 
540 
540 
RR 
L
R
R
R
L
L
R
R
R
L
L
L
R
L
R
R
L
R
R
L
L
R
R
R 
3,949 
4,421 
418 
4,146 
1,910 
2,751 
2,610 
2,897 
4,406 
463 
169 
-_ 
-_ 
3,700 
8,180 
3,949 
4,421 
3,260 
9,010 
4,146 
6,139 
1,752 
1,910 
2,751 
19,064 
22,007 
8,238 
3,592 
2,897 
9,614 
3,809 
7,571 
6,592 
5,754 
4,725 M 
4,580 
14,428 O 
4,315 
5,100 
13,646 p 
10,799 
8,728 
17,451 
5,290 
4,240 
7,549 
7,921 
2,201 
6,071 
5,092 
14,949 
457 
-_ 
544 R&L 
547 
549 
564 
571 
580 
585 
590 
591 
592 
600 
608 
L&R 
L
R
L
R
R
L
R
R
L
L 
246 
7,664 
108 
380 
27,971 9,024 
(5.30 Miles) 
- 275,441 
(52.17 Miles)

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun, 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares)' (Squares)' Feet) Feet) 
Miles 
Above 
Mouth 
ARKANSAS RIVER 3 
Standard revetment: 
Menard Bend, Ark. ................ 31 L - - - - - -11,770 
Como, Ark.. .................... 34 R - - - - - - -11,720 
Morgan Bend, Ark. ................ 36 L - - - - - - 5,250 
Total standard revetment, 
Arkansas River .............. - - - - - -28,740 
(5.44 Miles) 
Dikes:2 
Hopedale Cutoff, Ark. .............. 30 R 1,848 
Morgan Bend, Ark. ................ 36 L 1,663 - - - - - - 3,658 
Fletcher Bend, Ark. ................ 39 R _ - - - - - - 2,187 
Total dikes, Arkansas River ....... 1,663 -7,693 
(0.31 Mile) (1.46 Miles) 
1.Gross squares articulated concrete mattress 
(100 square feet). 
2. Linear feet of dike on which repairs were made. 
3. See report on Arkansas River and tributaries, 
Ark. and Okla., under Little Rock District. 
O
0
C 
O
y
C, 
nx 
O
trj 
v 
Wr 
n 
V 
Io

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun. 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Big Island, Ark ..................... 598 R - - - - 3,905 
Scrubgrass Bend, Ark. ............. 600 R - - - - 7,450 
Henrico, Ark. ...................... 606 R ----- 25,040 
Cessions Towhead, Ark. ........... 615 L - - - - - 3,152 10,615 g 
Knowlton, Ark. .................... 620 R - - - - - 1,838 16,900 
Island 67, Miss. .................... 621 L - - ----- 7,625 
Island 68 Bar, Ark.................. 622 R - - - - - - 6,445 
Ludlow, Ark...................... 626 R - - - - - 1,495 10,390 1 
Rescue Landing, Ark.-Miss. ......... 629 L - - - 27,020 
Fair Landing, Ark. ................. 632 R - - - - - 2,652 - 16,850 
Burke Landing, Miss. ............... 637 L - - 19,070 
Island 62, Ark. ..................... 638 R - - - - - - 9,030 
Island 63, Miss. .................... 639 L 5,080 300 18,261 2,637 8,158 - 11,454 � 
Island 63 Bar, Miss. ................ 639 L - - - - - - - 3,795 
Oldtown Bend, Ark. ................ 644 R - - - - - - - 25,995 
Horseshoe, Miss. ................... 647 L - - - - - 16,385 
Westover, Ark ..................... 650 R - - - - - 12,730 
Delta-Friars Point, Miss. ........... 655 L - - - 30,090 Z 
Helena, Ark. ....................... 660 R - - - - -36,460 
Trotters Landing, Miss. ............. 665 L -- - 32,905 
Flower Lake, Miss. ................. 667 L - - - - - 6,378 - 16,385 
St. Francis, Ark. ................... 672 R - - - 5,555 18,249 - 13,515 
Harbert Point, Miss. ................ 675 L 1,000 310 4,981 -- 9,065 
Walnut Bend, Ark. ................. 680 R - - - - - 3,011 - 27,220 
Mhoon Bend, Miss. .................. 685 L - - - 2,984 9,690 - - 35,828 
Peters, Ark. ....................... 692 R - - - - - - 23,675 
Commerce, Miss ........................ 695 L - - - - - - 11,615 
Porter Lake, Ark. .................. 700 R - - - - - 34,155 
Pickett, Miss.-Ark. ................. 703 L - - - - - 12,575 
Norfolk-Star, Miss. .................. 709 L - - - - -35,582 
Cow Island Bend, Ark. ............. 714 R - - - - 22,274 
Cow Island Bend (Upper), Tenn. .... 716 R --- - 7,003

TABLE 42-4 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun. 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER-continued 
Standard revetment: 
Coahoma, Tenn. .................... 717 
Ensley, Tenn. .................. .. 723 
Dismal Point, Ark. ................. 724 
Bauxippi-Wyanoke, Ark............ 730 
Presidents Island, Tenn. ............ 733 
Hopefield Point, Ark.-Tenn........... 736 
Loosahatchie-Memphis, Tenn. ....... 737 
Loosahatchie Bar, Tenn. ............. 740 
St. Clair, Ark. ..................... 742 
Island 40, Tenn.-Ark ............... 744 
Brandywine, Ark.-Tenn. ............ 750 
Shelby Forest, Tenn. ............... 753 
Dean Island, Ark. .................. 756 
Cedar Point-Densford, Tenn......... 759 
Chute of Island 35, Tenn. .......... 764 
Lookout Bar, Tenn................... 772 
Lookout, Tenn. ..................... 774 
Sunrise Towhead, Tenn. ............ 776 
Lower Bullerton, Ark. .............. 782 
Island 30, Tenn .................... 786 
Osceola, Ark. ...................... 786 
Osceola, Ark.... .................... 786 
Kate Aubrey Towhead, Tenn. ....... 788 
Ashport-Keyes Point, Tenn. ......... 791 
Kate Aubrey, Tenn. ................ 793 
Island 26, Tenn. .................... 798 
Bend of Island 25, Tenn. ............ 803 
Barfield, Ark. .................... 808 
Obion-Tamm, Tenn................. 819 
Huffman-Hickman, Ark.-Tenn. ..... 826 
Heloise, Tenn. ..................... 831 
L
L
R
R
L
R
L
R
R
R
R
L
R
L
R
R
R
R
R
R
R
R
R
L
R
R
L
R
L
R
L 
2,480 
1,370 
310 
140 
6,588 
4,196 
430 1,347 9,293 
O 
- 9,270 y 
- 36,566 
- 7,200 j 
- 23,300 
- 12,755 
- 5,390 c 
- 31,293 x 
- 2,070 , 
- 2,9302 0 
- 30,750 
- 18,010 z 
- 9,560 
- 7,555 
- 20,190 m 
- 29,190 6 
- 2,9902 
- 5,005 " 
- 14,615 
- 27,320 
- 13,545 
- 1,3503 
- 5,823 -.1 
- 11,773 
- 40,482 
- 2,500 
- 15,690 
- 22,730 
- 44,040 
- 44,195 
- 26,984 
- 12,935 
0P 
0

Island 18, Mo. ................... 836 
Linwood Bend, Tenn ............... 841 
Blaker Towhead, Tenn. ............. 845 
Bells Point, Mo. ............ ...... 845 
Gayoso-Caruthersville, Mo. .......... 848 
Island 15, Tenn. ................... 851 
Hathaway Landing, Tenn........... 852 
Robinson Bayou, Mo. ............... 852 
Fritz Landing, Tenn. ............... 857 
Lee Towhead, Mo. .................. 859 
Bend of Island 14, Tenn. ............ 859 
Above Lee Towhead, Tenn. ......... 861 
Little Cypress, Mo. ................ 864 
Merriwether-Cherokee, Tenn........ 869 
Linda, Mo................ 876 
Below Toney's Towhead, Tenn. ...... 879 
New Madrid Bend, Mo. ............. 886 
Kentucky Point, Ky. ................ 887 
New Madrid, Mo. .................. 889 
La Forge, Mo ...................... 892 
Slough Landing Neck, Tenn.-Ky. .... 899 
Winchester Towhead, Mo. ........... 900 
Island 9, Ky.-Tenn. ................. 905 
Milton Bell, Mo.................... 908 
Chute of Island 8, Ky. .............. 913 
Bend of Island 8, Mo. ............... 914 
Island 8, Ky. ....................... 914 
Hickman-Reelfoot, Ky. ............. 919 
Beckwith Bend, Mo. ................ 924 
Williams, Ky. ..................... 927 
Wolf Island, Ky. .................... 934 
Columbus, Ky ..................... 937 
Belmont, Mo. ...................... 938 
Island 3 and 4, Ky ......................... 940 
Campbell, Ky ...................... 943 
Pritchard, Mo ..................... 948 
Mayfield Creek, Ky. ................ 949 
Wickliffe, Ky. ..................... 953 
Cache-Cairo, Ill. (Ohio River) ....... 958 
Total revetment, Memphis District, 
Mississippi River ............. 
Dikes: 
Henrico, Ark. ...................... 603 
Io 
R
L
L
R
R
L
L
R
L
L
L
L
R
L
R
L
R
L
R
R
L
R
L
R
L
R
R
L
R
L
R
L
R
R
L
R
L
L
R 
2,960 
7,8604 
2,270 
1,0805 
3,450 
L- 
360 
280 
25 
-_ 
27,550 
(5.22 Miles) 
6,706 
7,836 
7,343 
3,270 
10,112 
1,725 
2,447 
5,486 
1,775 
69,293 11,606 
(2.19Miles) 
(6) 
37,444 37,527 
(7) 
- 22,170 
- 14,850 
- 10,757 
- 5,420 
- 25,600 
- 3,895 
- 1,000 
- 22,970 
- 15,670 
- 8,470 
- 12,050 
- 4,943 
- 32,240 
- 41,058 
- 11,950 g 
- 20,895 
- 30,348 
- 7,960 
- 5,559 
- 20,680 
- 28,960 
- 2,960 
- 27,935 
- 14,375 n 
- 12,620 
- 9,800 
- 9,990 
- 41,909 p 
- 14,588 Z 
- 10,015 
- 17,585 
- 3,825 
- 5,785 
- 19,970 
- 6,865 
- 15,045 
- 5,935 
- 8,455 
- 26,152 
- 1,718,306 
(325.43 Miles) 
(8) 
- 6,310

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Built during fiscal year, and operative protection in place Jun. 30, 1975) 
Operations Fiscal Year 1975 Nonop- 
Construction erative 
Above New Work Reinforcement Since Operative 
Head Bank Exten- Jun. 30, Jun. 30, 
Location of R sion Lap Mainte- 1974 1975 
Passes or (Linear (Linear (Linear nance (Linear (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) Feet) 
MISSISSIPPI RIVER-continued 
Dikes: 
Below Knowlton, Ark. ............. 
Island 67, M iss. ................... 
Below Ludlow, Ark. ............... 
Sunflower, Ark. .................... 
Island 64, Ark.................... 
Island 62, Ark..................... 
Island 63 Bar, Miss. ............... 
Island 63, M iss.. ........... ........ 
Kangaroo Point, Ark. ........... 
Friars Point, Miss ............... 
Montezuma Towhead, Ark. ......... 
Prairie Point, Ark ............... 
St. Francis Towhead, Miss. ......... 
Below Walnut Bend, Ark .......... 
Bordeaux Point., Miss. .............. 
Commerce, Miss ................. 
Basket Bar, Ark ................. 
Buck Island, Miss. ................. 
Porter Lake, Ark ................ 
Pickett, Miss...................... 
Seyppel, Ark................. 
Cat Island, Ark. .................. . 
Coahoma, Tenn................... 
Armstrong, Ark.-Tenn. ............ 
Dismal Point, Ark.................. 
Hopefield Point, Ark. ............... 
Robinson Crusoe, Tenn. ............ 
Loosahatchie Bar, Tenn............. 
Above Loosahatchie, Tenn. .......... 
Redman Point, Ark................. 
Randolph Point, Tenn. .............. 
Poker Point, Ark ................ 
616 
621 
624 
627 
630 
638 
639 
640 
649 
652 
656 
668 
671 
676 
681 
694 
696 
700 
701 
704 
706 
710 
718 
720 
724 
736 
738 
739 
742 
743 
747 
748 
R
L
R
L
R
R
L
L
R
L
R
R
L
R
L
L
R
L
R
L
R
R
L
R
R
R
R
R
L
R
L
R 
6,590 
26009 
-_ 
-_ 
1,868 
-_ 
-_ 
300 
300 
75 
150 
100 
275 
140 
375 
1,9879 
200 
250 
200 
110 
1,26010 
1,99010 
0
0
0E
�,D 
- 4,190 
- 4,320 
5,040 
- 5,520 
- 7,330 
23,180 
2,600 
- 5,640 
- 5,730 
- 6,870 
- 3,450 
- 8,810 
- 3,380 
- 6,420 
- 4,920 
- 5,700 
- 5,060 
- 7,320 
330 7,600 
- 7,180 
- 11,640 
- 15,590 
- 4,640 
- 18,690 
350 22,170 
- 1,330 
- 21,670 
- 3,950 
- 8,990 
- 7,750 
- 16,740 
- 8,050

Corona Bar, Tenn.-Ark. ............ 
Densford, Tenn. .................... 
Cedar Point, Tenn. ................. 
Below Richardson Landing, Tenn. ... 
Lookout, Tenn.-Ark. ................ 
Plum Point, Tenn. .................. 
Kate Aubrey, Tenn. ................ 
Keyes Point, Tenn .................. 
Ashport-Golddust, Tenn.-Ark. ....... 
Forked Deer, Tenn................... 
Island 25, Ark....................... 
Below Tamm Bend, Tenn......... . 
Wrights Point, Ark. .............. 
Island 21 Chute, Tenn. ............. 
Head of Island 21, Tenn. ........... 
Island 20, Mo.-Tenn. ................. 
Tennemo, Tenn. .................... 
Caruthersville-Linwood Bend, Mo. .. 
Sandy Hook, Tenn. ................. 
Island 15, Tenn. ..................... 
Robinson Bayou, Mo .............. 
Hathaway, Tenn. .................... 
g Island 15 Neck, Tenn. ............ 
Cw Above Lee Towhead, Tenn. ......... 
Below Cherokee, Tenn. ............. 
Stewart Towhead, Mo............ 
Ruddles Point, Mo .................. 
Morrison Towhead, Mo. ............. 
Donaldson Point, Mo. .............. 
Island 9, Ky ....................... 
Campbell, Ky ..................... 
Pritchard, Mo ..................... 
Island 1, Ky. ........................ 
Total dikes, Memphis District, 
Mississippi River ............. 
755 
757 
759 
767 
771 
784 
791 
791 
795 
798 
804 
813 
820 
824 
828 
831 
842 
844 
850 
851 
853 
854 
854 
859 
866 
871 
874 
890 
905 
906 
942 
944 
948 
R
L
L
L
R
L
R
L
R
L
R
L
R
L
L
R
L
R
R
L
R
L
L
L
L
R
R
R
R
L
L
R
L 
5,950 
5,760 
2,780 
7,500 
2,910 
21,100 
1,070 
2
3
9 
5,5 
56,260 
(10.65 Miles) 
5,118 
(1.00 Mile) 
2
2
8
- 
:50 - 
- 510 
25 - 
70 - 
35 - 
75- 510 
50 - 
?25 - 
00 - 
50 - 
350 - 
--
50 - 
50 - 
- 
-- 
-_- 
13,892 1,190 569,725 
(107.90 Miles) 
1. Gross squares-articulated concrete mattress 
(100 square feet). 
2. Lumber mattress revetment. 
3. Rock groins. 
4. Includes 4,890 linear feet extension by stone 
bank paving. 
5. Includes 176 linear feet extension by stone bank 
paving. 
6. Stone in pile dike. 
7. Linear feet of dike on which repairs were made. 
8. Linear feet of dike to nearest ten feet. 
9. PL 84-99 work. 
10. Elevation of dike raised-no extension of original 
length. 
11. Stone dike along Highway 79 and stone closure 
across scour hole. 
12. Linear feet of triangular frame retards and pile 
dikes. 
8,430 
7,780 
2,890 
5,950 
5,500 
5,760 
7,990 
8,040 
17,330 
8,550 
5,310 
8,300 
27,990 
3,170 
5,460 
18,080 
2,505 
17,100 
2,350 
5,130 
6,240 
13,670 
21,100 9,11 
1,300 
5,940 
18,290 
8,130 
1,070 
8,320 
7,01012 
2,610 
9,390 
15,260 
Ch1J22 
G) 
cl 
F1 
C
n
C
h~ll 
CI 
zt 
8

TABLE 42-K PROJECT LEVEES: NEW ORLEANS DISTRICT 
(Present condition of project levees, from Cape Girardeau, Mo., to Head of Passes, La., 
and levee operations for Fiscal Year 1975 as provided for in Sec. 1 of the act of 
May 15, 1928, as amended) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved In In 
Location In Grade and Section System Com- System Com- 
Authorized Place When Built plete When Built plete 
for Jun. 30, This Jun. 30, Com- This Jun. 30, Cor- This Jun. 30, 
System 1975 FY 19751 pleted 2,3 FY 1975 pleted FY 19754 
MISSISSIPPI RIVER 
Fifth Louisiana Levee District ........... 
Levees ................ ............... 
Floodw alls ........................... 
Old River structures and levees5'....... 
Atchafalaya Basin Levee District ........ 
Levees ................................ 
Floodw alls ........................... 
Morganza structure and levee5 ......... 
Morganza forebay levee ................ 
Port Allen lock5 ................. 
Lafourche Basin Levee District .......... 
Above New Orleans 
Levees6 ........ . . . . . . . . . . . . . . . . . . . . . . . 
Floodwalls ............. ........ 
Harvey Canal lock ................... 
Below New Orleans 
Levees6 ........ . . . . . . . . . . . . . . . . . . . . . . . . 
Floodw alls ............................ 
Buras Levee District .................... 
Levees6 ........ . . . . . . . . . . . . . . . . . . . . . . . 
Floodwalls ............. ........ 
Empire lock? . . . . . . . . . . . . . . . . . . . . 
Baton Rouge front levees ................ 
Pontchartrain Levee District ............. 
Levees6 ........ . . . . . . . . . . . . . . . . . . . . . . . 
Floodwalls . ..................... 
Bonnet Carre guide levees ............. 
Bonnet Carrd forebay levees . . . . . . . . . ... 
Bonnet Carrd structure ................ 
Orleans Levee District ................... 
(16.8) 
15.5 
1.3 
(127.3) 
119.7 
0.8 
6.7 
0.1 
(120.7) 
82.5 
0.1 
0.1 
38.0 
(34.0) 
33.9 
0.1 
(2.1) 
(136.3) 
122.2 
11.3 
1.3 
1.5 
(25.9) 
(16.8) 
15.5 
1.3 
(127.3) 
119.7 
0.8 
6.7 
0.1 
(120.7) 
82.5 
0.1 
0.1 
38.0 
(34.0) 
33.9 
0.1 
(2.1) 
(135.0) 
122.2 
11.3 
1.5 
(25.9) 
(-) 
(39.0) 
17.0 
22.0 
(30.4) 
30.4 
(-) 
(-) 
(-) 
(4.2) 
2.9 
1.3 
(102.0) 
94.4 
0.8 
6.7 
0.1 
(116.4) 
78.2 
0.1 
0.1 
38.0 
(30.4) 
30.4 
(0.9) 
(132.1) 
119.3 
11.3 
1.5 
(1.5) 
(-) 
(5.3) 
5.3 
(0.1) 
(-) 
(-) 
(-) 
0.1 
(-) 
(-) 
(4.7) 
4.7 
(-) 
(-) 
(-) 
(-) 
(-) 
(-) (15.5) 
- 15.5 
(-) (119.7) 
- 119.7 
(0.1) (120.6) 
0.1 82.5 
- 0.1 
- 38.0 
(-) (33.9) 
- 33.9 
(-) (2.1) 
(-) (122.2) 
- 122.2 
(-) (17.1) 
C
by 
(15.5) 0 
15.5 
- 
119.7) x 
119.7 
0 
- C
Z 
- 
120.6) Z 
82.5 
0.1 
C1 
(-) (1 
- 1 
(-) (1 
(-) 
(-) 
(-) 
(-) 
N
CC �,o 
�j1 
38.0 
(33.9) 
33.9 
(2.1) 
(122.2) 
122.2 
(24.3) 
(-)

Left descending, east bank 
Levees .................. .............. 
Floodwalls8 6 . . . . . . . . . . . . . . . . . . . . 
IHNC lock...................... 
Right descending, west bank 
Levees6 ........ . . . . . . . . . . . . . . . . . . . . . . . 
Floodwalls8 ...... . . . . . . . . . . . . . . . . . . . . . 
Algiers Canal lock ..................... 
Lake Borgne Basin Levee District ........ 
Levees ............. ........... 
Floodwalls ............................ 
Grand Prairie Levee District ............. 
Levees . . . . . . . . . . . . . . . . . . . . . . . . . 
Floodwalls ............................ 
Total Mississippi River ............ 
LOWER RED RIVER-SOUTH BANK 
RED RIVER 
Lower Red River-South Bank 
Red River levees ....................... 
Hotwells to Moncla, La., levees 6 . . . . . . . . 
Floodw alls ........................ ... 
Total Lower Red River ............ 
ATCHAFALAYA BASIN FLOODWAY 
Atchafalaya River and 
Bayou des Glaises ................. 
East bank Atchafalaya River .......... 
Bayou des Glaises ..................... 
West bank Atchafalaya River .......... 
Simmesport Ring ................. 
Melville Ring .............. ...... 
Krotz Springs Ring .................... 
Mansura Hills to Hamburg........... . 
West protection levee, Hamburg to Berwick 
drainage canal via Calumet ........ 
Levees ......................... 
Floodwalls ....................... 
Levees west of Berwick, Berwick drainage 
canal to Charenton drainage canal .. 
Morganza upper guide levee ............. 
East protection levee, Morganza to Cutoff 
Bayou, including 19.5 miles of 
Morganza lower guide levee.......... 
Levees ................. ............... 
3.6 
8.6 
0.1 
13.5 
0.1 
(11.5) 
11.5 
(37.0) 
37.0 
10.8 
1.4 
0.1 
13.5 
0.1 
(11.5) 
11.5 
(37.0) 
37.0 
3.6 
1.3 
0.1 
(-) 
(22.8) 
22.8 
0.1 
(10.6) 
10.6 
(35.0) 
35.0 
- - 
(-) (-) 
(-) 
- 13.5 
(-) (11.5) 
- 11.5 
(-) (37.0) 
- 37.0 
(-) 
(-) 
10.89 
13.5 
(11.5) 
11.5 
(37.0) 
37.0 
511.6 510.3 92.2 433.1 10.1 - 0.1 479.6 - 486.89 
(59.8) (59.8) (-) (43.9) (-) (-) (-) (59.8) (-) (20.0) 
59.8 59.8 - 43.9 - - - 59.8 - 20.0 
59.8 59.8 - 43.9 - - - 59.8 - 20.0 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(128.7) 
124.7 
4.03 
(56.5) 
(8.9) 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(125.7) 
124.7 
1.010 
(56.5) 
(8.9) 
(106.7) (105.0) 
95.3 95.3 
(-) (82.4) 
46.6 
1.7 
26.0 
1.6 
4.1 
1.7 
0.7 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(127.7) 
127.7 
(7.6) (53.1) 
7.6 53.1 
(-) 
(-) 
(43.7) 
(8.9) 
cC112 
H 
CID 
Cn
C
z 
(-) (30.7) 
- 7.0 
- 12.0 
- 11.7 
(7.6) (53.1) 
7.6 53.1 
(56.5) (-) 
(8.9) (-) 
(4.2) (14.2) 
- 10.0 
(14.0) 
(8.9) 
(105.0) (-) (10.0) 
95.3 - 10.0

TABLE 42-K 
(Continued) 
PROJECT LEVEES: NEW ORLEANS DISTRICT 
(Present condition of project levees, from Cape Girardeau, Mo., to Head of Passes, La., 
and levee operations for Fiscal Year 1975 as provided for in Sec. 1 of the act of 
May 15, 1928, as amended) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved In In 
Location In Grade and Section System Com- System Com- 
Authorized Place When Built plete When Built plete 
for Jun. 30, This Jun. 30, Com- This Jun. 30, Com- This Jun. 30, 
System 1975 FY 19751 pleted 2 3 FY 1975 pleted FY 19754 
ATCHAFALAYA BASIN 
FLOODWAY-continued 
Floodwalls ................ ........... 11.43 9.710 4.2 4.2 - - -9.7 
Total Atchafalaya Basin and 
Floodway ........................ 449.2 444.5 11.8 202.3 - - - 446.5 7.6 116.7 
Total-Main Stem System ....... 1,020.6 1,014.6 104.0 679.3 10.1 - 0.1 985.9 7.6 623.5 
LAKE PONTCHARTRAIN, LA. 
Lake Pontchartrain, La. ................. (17.4) (17.4) (-) (17.4) (-) (-) (-) (17.4) 
Item A levees ........................ 5.0 5.0 - 5.0 - - - 5.0 - 5.0 
Item B levees ........................ 10.1 10.1 - 10.1 - - - 10.1 - 10.1 
Item C levees ......................... 2.3 2.3 - 2.3 - - 2.3 - 2.3 
Total-Off Main Stem ........... 17.4 17.4 - 17.4 - - -17.4 - 17.4 
1. Figures reflect grade only-sections of entire system 
not available at this time. 
2. Figures indicate landside seepage berms only. 
3. Estimated. 
4. Figure includes approximately 158.4 miles of levee 
surfaced during 1973, 1974, and 1975 flood fights. 
5. Existing freeboard sufficient not to require modification 
due to recent flow line changes. 
6. Includes work now in construction. 
7. Lock modification in design phase by Louisiana 
Department Public Works. 
8. In design phase; exact length not yet determined. 
9. Levees and roads presently in place will be eliminated 
when floodwalls are constructed. 
10. Sheetpile floodwall and levee combination. Levee 
presently in place, floodwall is not. 
C
O
O
x
C
vi 
xr 
0
z
z 
tA \3 
g 
Q

TABLE 42-L PROJECT LEVEES: VICKSBURG DISTRICT 
(Present condition of project levees, from Cape Girardeau, Mo., to Head of Passes, La., 
and levee operations for Fiscal Year 1975 as provided for in Sec. 1 of the act of 
May 15, 1928, as amended) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved In In 
Location In Grade and Section System Com- System Com- 
Authorized Place When Built plete When Built plete 
for Jun. 30, This Jun. 30, Com- This Jun. 30, Com- This Jun. 30, 
System 1975 FY 19752 pleted3 FY 1975 pleted FY 1975 
MISSISSIPPI RIVER 
East bank in Mississippi ................. 178.34 178.3 - 135.3 166.2 - 58.2 173.5 19.1 152.4 
Greenville Harbor dikes ................. 7.8 7.8 - 7.8 - - - 
West bank in Arkansas .................. 75.6 75.6 - 48.6 51.4 - 13.4 75.4 75.4 
West bank in Louisiana 
(above Red River) ...................... 198.7 198.7 - 25.7 143.1 - 43.1 198.4 - 186.6 
Total Mississippi River ................. 460.4 460.4 - 217.4 360.7 - 114.7 447.3 19.1 414.4 
YAZOO RIVER BASIN 
Headwater ........................... 574.6 262.2 - 88.3 - - - 574.6 155.0 262.2 
Backwater ........................... 96.6 19.0 - 0.0 10.2 - 3.9 96.6 - 12.9 
Total Yazoo River Basin ............... 671.2 281.2 - 88.3 10.2 - 3.9 671.2 155.0 275.1 
ARKANSAS RIVER, ARKANSAS 
North bank ......................... 61.5 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 
South bank .......................... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 -81.1 
Total Arkansas River .................. 146.9 141.6 - 141.6 33.0 - 33.0 131.5 - 128.5 
RED RIVER BACKWATER LEVEES 
Total Red River backwater ............. 274.0 123.6 - 118.3 - - 157.1 - 86.9 
1. This tabulation does not include riverside berms 
which are considered an integral part of the levee 
section. Riverside berms will be constructed along 
with levee enlargements or seepage berm contracts. 
2. Levee that has adequate freeboard based on the 
1973 project design flow line for the Mississippi 
River. Levees with more than 2 feet of freeboard are 
considered adequate. 
3. Subject to change as planning progresses. 
4. Includes 1.4 miles of concrete floodwall and 
0.3 mile of levee on Vicksburg city, front. 
5. Includes 33.1 miles of local protection works; 
117.3 miles along auxiliary channels; 265.6 miles 
along main stem; and 158.6 miles on tributaries. 
6. Includes 5.3 miles for Gillett new levee. 
a 
F 1 
w
CC
cI) 
CI) 
C
z

TABLE 42-M PROJECT LEVEES: MEMPHIS DISTRICT 
(Present condition of project levees, from Cape Girardeau, Mo., to Head of Passes, La., 
and levee operations for Fiscal Year 1975 as provided for in Sec. 1 of the act of 
May 15, 1928, as amended) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved In In 
Location In Grade and Section System Com- System Com- 
Authorized Place When Built plete When Built plete 
for Jun. 30, This Jun. 30, Com- This Jun. 30, Com- This Jun. 30, 
System 1975 FY 1975 pleted' FY 1975 pleted FY 1975 
MISSISSIPPI RIVER 
M ounds, Ill . ........................... 
Mound City, Ill.................... 
Cairo Drainage District .................. 
City of Cairo ...................... 
Little River Drainage District ........... 
Levee District No. 2, 
Scott County, Mo. ................ ...... 
Levee District No. 3, 
Mississippi County, Mo............. 
St. Johns Levee and 
Drainage District .................... 
St. Francis Levee District of Mo......... 
City of Hickman, Ky .................. 
Fulton County Levee District of 
Fulton County, Ky................. 
Reelfoot Levee District of Lake and 
Obion Counties, Tenn................... 
Madrid Bend Levee District ............. 
Lake County Levee and 
Drainage District ...................... 
Dyer County Levee and 
Drainage District No. 1 ................. 
Tiptonville-Obion levee extension ......... 
St. Francis Levee District of Ark....... . 
Helena Improvement District No. 1 ...... 
Cotton Belt Levee District No. 1 .......... 
Laconia Drainage and Levee District 
of Phillips County, Ark.................. 
Laconia Levee District No. 1 of 
Desha County, Ark ..................... 
Laconia Circle Special Drainage 
District of Desha County, Ark. .......... 
Yazoo-Mississippi Delta Levee 
District ....... ................... 
New Madrid, Mo., St. Johns 
Levee and Drainage District ............ 
3.9 
2.7 
13.83 
6.2 
19.3 
13.8 
26.0 
58.75 
55.7 
1.4 
16.7 
4.5 
9.6 
15.9 
21.3 
6.5 
156.7 
5.3 
23.9 
20.5 
18.1 
6.6 
93.6 
3.9 
2.7 
13.8 
6.2 
19.3 
13.8 
26.0 
58.7 
55.7 
1.4 
16.7 
- 3.9 
- 2.7 
- 13.8 
- 6.2 
- 19.3 
- 13.8 
9.9 25.9 
25.3 
55.7 
1.4 
6.4 
- 16.3 
4.5 - 0.1 
9.6 2.5 5.9 
15.9 
21.3 
156.7 
5.3 
23.9 
20.5 
- 15.9 
0.5 
0.7 
21.3 
153.2 
5.3 
19.7 
0.4 17.4 
18.1 0.6 13.2 
0.32 
10.52 
2.92 
8.02 
13.02 
16.02 
42.72 
10.62 
16.32 
4.02 
13.02 
13.02 
94.62 
2.4 
16.4 
0.9 
2.4 
3.6 
1.1 
8.5 
4.0 
19.3 
13.8 
3.6 
1.1 
8.5 
3.5 
19.3 
13.8 
0
00 
y
x
C
n
x
0
z
C1 
z
r
�
Iv 
M
Lf 
26.04 10.3 25.9 
10.4 
10.6 
46.64 
55.1 
0.5 
16.7 
1.0 2.9 
- 55.1 
-- 
16.3 
0.3 4.5 - - 
- 5.0 5.0 5.0 
4.5 15.9 - 15.9 
- 
2.1 
0.7 
8.4 
12.12 
65.7 
2.4 
11.3 
21.3 
6.5 
156.7 
4.7 
23.9 
21.8 
0.1 
8.4 20.5 
10.6 
6.6 
93.6 
18.1 
21.3 
154.66 
4.2 
19.6 
20.5 
CD 
C' 
16.5 
6.6 
- . 93.6, 85.7 .. . - .- 85.7 93.6 93.6 
0.3 0.32 0.3

Birds Point-New Madrid 
setback levee ......................... 
Total Mississippi River .............. 
ST. FRANCIS RIVER 
East bank ................ . ............ 
West bank .............................. 
Total St. Francis River .............. 
LITTLE RIVER 
East bank (left) ......................... 
West bank ............................ 
Elk Chute .................. ........... 
West Basin and middle valley ............ 
Total Little River ................... 
LOWER WHITE RIVER 
White River backwater levee ........... 
Augusta to Clarendon ................. 
Clarendon levee ....................... 
MEMPHIS HARBOR 
Memphis Harbor ....................... 
35.3 35.3 6.2 32.97 35.32 - - 35.3 - 35.3 
636.3 629.5 27.2 562.8 405.5 2.8 213.2 608.1 38.2 536.5 
159.5 152.9 - 152.9 - - - 156.7 - 56.6 
148.7 146.7 - 146.7 - - - 144.3 - 15.7 
308.2 299.6 - 299.6 - - - 301.0 - 72.3 
40.7 40.7 - 40.7 - - - 40.7 - - 
35.1 35.1 - 35.1 - - - 35.1 - 13.0 
39.9 39.9 - 39.9 - - - 39.7 9.6 17.3 
14.4 14.4 - 14.4 - - - 13.4 - 13.4 
130.1 130.1 - 130.1 - - - 128.9 9.6 43.7 
40.2 
49.2 
6.2 
10.5 
40.2 
39.5 
6.2 
10.5 
40.2 
39.5 
4.4 
10.5 
38.8 
49.2 
6.92 - 1.5 10.5 
38.8 
- 10.5 
1. Subject to change as planning progresses. 
2. Adjusted to include additional reaches selected 
for study based on seepage data collected during recent floods. 
3. Includes 5.1 miles of Cache River levee. This 
levee was enlarged to 1928 grades with Federal funds, 
but since that time has been classified as a 
secondary levee. 
4. Mileage adjusted to include reaches of levee not 
previously proposed to be surfaced. 
5. Includes 12.1 miles of Farrenburg levee. This levee 
was enlarged to 1928 grades with Federal funds, 
but since that time has been classified as a 
secondary levee. 
6. Reduced 1.9 miles to correct previous error. 
7. Adjusted to reflect miles previously shown 
complete but were deficient in cross section. 
12 
Cb 1 
C,, 
0
I 1 
C
C
n
O
z 
�,

TABLE 42-N LEVEES: YARDAGE AND OPERATIONS 
(As provided for in Sec. 6, Flood Control Act of 1928, as amended) 
Miles in Miles Operations 
System Miles Built to Fiscal Year 1975 
When Built Approved Contents Contents Required Estimated 
Com- Jun. 30, Grade and Jun. 30, New Lost or Jun. 30, to Final 
Location of Levee pleted 1975 Section 1974 Work Abandoned 1975 Complete Contents 
MISSISSIPPI RIVER 
St. Louis District 
Clemens Station, Mo., to mouth of Missouri River 
Mouth of Illinois River to Prairie du Pont, Ill. 
Prairie du Pont, Ill., to Grand Tower, Ill. 
Mouth of Missouri River to Cape Girardeau, Mo. 
Grand Tower, Ill., to Thebes, Ill. 
Rock Island District 
Rock Island to New Boston, Ill. 
Total Mississippi River 
MISSISSIPPI RIVER TRIBUTARIES 
New Orleans District 
RED RIVER 
Moncla to Lake Long, La. 
Vicksburg District 
OUACHITA RIVER 
East bank below Monroe, La. 
West bank: 
Bawcomville, La. 
Harrisonburg to Little River, La. 
Total Ouachita River 
YAZOO RIVER 
West bank 
Memphis District 
WHITE RIVER 
Horn Lake, Ark. 
St. Louis District 
ILLINOIS RIVER 
Havana, Ill., to Beardstown, Ill. 
Beardstown, Ill., to mouth of Illinois River 
Total Illinois River 
Total Sec. 6 Levees 
1,000 
Cubic 
Yards 
28 
20
4 
46 
28 
20
4 
46 
1,000 
Cubic 
Yards 
1,000 
Cubic 
Yards 
25.6 
27.1 
- 57.2 
3 1,252.4 
1,000 
Cubic 
Yards 
25.6 
27.1 
57.2 
1,252.4 
1,000 
Cubic 
Yards 
1,000 
Cubic 
Yards 
31.4 31.4 31.4 4,485.0 - - 4,485.0 
129.4 129.4 34.4 5,847.3 - - 5,847.3 - - 
20.7 20.7 20.7 394 - - 394 - 394 
68.5 64.71 64.71 3,7372 - - 3,737 500 4,237 
3.1 3.1 3.1 283 - - 283 - 283 
12.4 12.4 12.4 6823 - - 682 - 682 
84.0 80.2 80.2 4,702 - - 4,702 500 5,202 
8.7 8.7 8.7 735 - - 735 - 735 
1.8 1.8 1.8 50.1 - - 50.1 - 50.1 
25 25 8 1,610 - - 1,610 - - 
166 166 127 15,940 - - 15,9440 - 
191 191 135 17,550 - - 17,550 - - 
435.6 431.8 280.8 29,278.4 - - 28,962.9 -- 
1. Includes 1.3 miles constructed by local interests. 
2. Includes 115,000 cubic yards constructed by local 
interests. 
3. Includes about 95,000 cubic yards constructed by local 
interests. 
0
0
O
y
0
z
C12 
c=ll 
M
CM+D 
Cl'

TABLE 42-0 CHANNEL IMPROVEMENTS: NEW ORLEANS DISTRICT 
(New work accomplished during fiscal year and operative portion of 
project feature in place Jun. 30, 1975) 
In Project When Complete Completed Jun. 30, 1975 Operations During FY 1975 
Per- 
Year Exca- Clean Exca- Clean Exca- Clean cent 
Location Initi- Total vation Out Total vation Out Total vation Out Comated 
(Miles) (Mc.y.) (Miles) (Miles) (Mc.y.) (Miles) (Miles) (Mc.y.) (Miles) plete 
Bayou des Glaises diversion channel ......... 1938 6.0 2,223 - 6.0 2,223 - - - - 100 
Bayous Rapides, Boeuf, and Cocodrie ........ 1946 92.6 22,039 21.8 63.4 16,483 12.2 - - - 75 
Charenton drainage and navigation canal .... 1939 6.3 10,879 - 6.3 10,879 - - - - 100 
Wax Lake Outlet ......................... 1938 15.7 57,546 - 15.7 57,546 - - - - 100 
Atchafalaya Basin Floodway ................ 1933 244.2 813,418 - 186.4 397,857 - - 49 
Morganza Floodway ...................... 1941 3.3 1,322 - 3.3 1,322 - - - - 100 
Old River outflow channel .................. 1956 7.4 67,449 - 7.4 67,449 - - - - 100 
Old River inflow channel .................. 1960 0.4 6,182 - 0.4 6,182 - - - - 100 
Old River lock approach channels ........... 1961 2.2 6,731 - 2.2 6,731 - - - - 100 
Baton Rouge Harbor (Devils Swamp) ........ 1958 5.0 17,075 - 2.5 7,458 - - - - 44 
C' 
1I, V1 
CI, 
CI, 
0Cz 
C,

TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT 
(New work accomplished during fiscal year and operative portion of 
project feature in place Jun. 30, 1975) 
In Project When Complete Completed Jun. 30, 1975 Operations During FY 1975 
Per- 
Year Exca- Clean Exca- Clean Exca- Clean cent 
Location Initi- Total vation Out Total vation Out Total vation Out Comated 
(Miles (Mc.y.) (Miles) (Miles) (Mc.y.) (Miles) (Miles) (Mc.y.) (Miles) plete 
BIG SUNFLOWER RIVER, 
ETC., MISS. 
Big Sunflower River ...................... 1947 199.1 
Quiver River ............................. 1947 69.6 
Deer Creek ............................. 1947 7.0 
Steele Bayou ............................. 1947 66.9 
Big Sunflower River tributaries ............. 1957 227.4 
Quiver River tributaries ................... 1960 35.4 
Steele Bayou tributaries ................... 1959 76.0 
YAZOO BACKWATER 1960 39.9 
YAZOO BASIN HEADWATER, MISS. 
Coldwater River ........................... 1941 54.6 
Arkabutla Canal .......................... 1948 0.4 
Tallahatchie River .......................... 1940 74.8 
Little Tallahatchie River and 
Panola-Quitman Floodway ................. 1939 48.0 
Greenwood protection works ................ 1971 2.9 
Yocona River .............................. 1952 1.8 
Bobo Bayou ............................... 1944 16.1 
Cassidy Bayou ...... ....................... 1943 69.0 
Yalobusha River .......................... 1939 46.0 
Yazoo River ............................... 1940 160.2 
Whittington Auxiliary Channel ............. 1956 30.8 
Tchula Lake .............................. 1964 26.4 
David-Burrell Bayou ......... ............ 1957 40.4 
McKinney Bayou ........................... 1960 3.5 
Hillside Floodway ........................ 1964 11.0 
Yazoo City protection works ................ 1953 1.6 
Ascalmore-Tippo Bayous ......... .......... 1975 29.8 
Alligator-Catfish Bayou .................... 1973 8.3 
Pelucia Creek ............................. 1975 2.9 
BOEUF AND TENSAS BASINS, ARK. 
AND LA. 
Bayou Lafourche, La. ....................... 1949 44.6 
Big and Colewa Creeks, La. ................. 1947 75.5 
Tensas River, La. .......... ......... ..... 1947 157.5 
Boeuf River, Ark. and La ................... 1953 103.9 
Fleschmans Bayou, Ark. ................... 1963 6.6 
5,912 187.91 
2,401 42.04 
73 2.04 
24,551 45.40 
7,856 173.45 
481 23.08 
10,170 13.44 
20,512 4.6 
9,897 43.5 
81 - 
7,361 64.8 
1,170 43.0 
810 - 
606 - 
2,776 1.9 
10,538 47.6 
6,337 36.1 
5,400 155.6 
23,520 - 
2,121 15.4 
1,332 28.6 
207 2.2 
877 4.8 
2,457 - 
2,380 13.3 
1,600 
316 0.9 
52,1061 1.10 
20,1791 47.21 
19,9421 151.29 
20,937 50.58 
513 2.70 
199.1 
69.6 
7.0 
27.4 
227.1 
35.4 
76.0 
18.9 
5,912 187.91 
2,401 42.04 
73 2.04 
8,594 45.40 
7,856 173.45 
481 23.08 
791 13.44 
15,260 - 
5.2 1,217 
54.6 9,897 43.5 - 
0.4 81 - - 
73.5 5,856 64.8 - 
48.0 
2.9 
1.8 
16.1 
46.0 
160.2 
30.8 
26.4 
40.4 
3.5 
11.0 
1.6 
13.3 
6.9 
3.6 
8.8 
61.0 
103.9 
6.6 
1,170 43.0 
810 - 
606 
2,776 1.9 
3,033 47.6 
6,337 36.1 
5,400 155.6 
23,520 
2,121 15.4 
1,332 28.6 
207 2.2 
877 - 
2,457 - 
- 13.3 
1,328 - 
36,316 1.10 
4,925 34.01 
1,092 86.16 
20,937 50.58 
513 2.70 
9.7 
2.9 
13.3 
2.9 
0.6 
1.8 
-_
-_ 
- 9.7 
570 - 
- 13.3 
728 - 
500 - 
550 - 
cn 
C
O
c- 
O
y 
x3 
nd 
x
O
z
z
Ct2 
100 
100 
100 
201 
100 
100
4 
74 
100 
100 
85 
100 
100 
100 
100 
33 
100 
100 
100 
100 
100 
100 
100 
100 
10 
83 
10 
101 
201 
71 
100 
100

Caney Bayou, Ark ......................... 1964 7.1 406 1.89 7.1 406 1.89 
Canal 18, Ark ............................ 1963 10.3 776 1.59 10.3 776 1.59 
Big Bayou, Ark. ............................ 1952 33.3 1,827 14.87 33.3 1,827 14.87 
Black Pond Slough, Ark................... 1962 14.3 947 - 14.3 947 - 
Bayou Macon, Ark. and La. ................. 1959 146.4 15,863 110.08 146.4 15,863 110.08 
Rush Bayou, Ark ......................... 1964 6.2 - 6.2 6.2 - 6.73 
Canal 19, Ark. ........................... 1957 50.2 11,348 - 50.2 11,348 - 
Canal 43, Ark. ........................... 1956 34.5 698 24.80 34.5 698 24.80 
Canal 81, Ark. ............................ 1957 32.7 4,433 7.01 32.7 4,433 7.01 
Mill Bayou and Bayou Vidal ................ - 16.4 - 16.40 - - - 
Kirsch Lake Canal ........................ - 9.3 620 - - - 
Canal 19 (Ext.) ........................... 1964 9.4 1,040 - 9.4 1,040 - 
Lake Chicot ................................ - 14.0 3,354 9.9 
23.1 3,565 
1. Authorized additional enlargement. 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
9.7 
C12 
b
C2 
n
O
zl

TABLE 42-Q CHANNEL IMPROVEMENTS: MEMPHIS DISTRICT 
(New work accomplished during fiscal year and operative portion of 
project feature in place Jun. 30, 1975) 
In Project When Complete Completed Jun. 30, 1975 Operations During FY 1975 
Per- 
Year Exca- Clean Exca- Clean Exca- Clean cent 
Location Initi- Total vation Out Total vation Out Total vation Out Comated 
(Miles) (Mc.y.) (Miles) (Miles) (Mc.y.) - (Miles) (Miles) (Mc.y.) (Miles) plete 
BIRDS POINT-NEW MADRID 
FLOODWAY 
Birds Point-New Madrid Intercepting Ditch 
Enlargement, Samos and Vicinity, Mo. ..... 1952 9.6 285 4.6 9.6 285 4.6 -100 
ST. FRANCIS BASIN 
Little River Drainage, Mo.......... ........ 1963 291.3 37,600 - 165.4 21,588 - 4.4 964 - 57 
Miss. County, Drainage District No. 17, Ark... 1947 15.9 1,068 - 15.9 1,068 - - - - 100 
St. Francis River, Mo. and Ark.............. 1953 568.5 137,200 49.0 243.5 88,761 25.1 20.9 4,666 - 65 
West Memphis Drainage, Ark. .............. 1951 19.8 1,747 2.2 19.8 1,747 2.2 - - - 100 
Cross County Project Ditch, Ark............. 1942 11.8 7,710 - 11.8 7,710 - - - - 100 
Tyronza River, Ark ........................ 1939 12.7 2,795 - 12.7 2,795 - - - - 100 
L'Anguille River, Ark ...................... (1) 112.0 16,000 23.52 - - - - 
LOWER WHITE RIVER 
BASIN, ARK. 
Cache River Basin, Ark. .................... 1972 231.5 115,500 9.0 4.5 1,651 - - - - 1 
Big Creek and tributaries, Ark. ............. (1) 103.8 27,738 - - - - - 
WEST KENTUCKY TRIBUTARIES 
Obion Creek, Ky ............................ (1) 30.6 7,380 
WEST TENNESSEE TRIBUTARIES 
Miss. River, Western Tenn. tributaries.; 
(Backwater Areas) (1946 Act) .............. 1952 34.3 1,883 26.1 34.3 1,883 26.1 -100 
Obion River Diversion Channel, 
Tenn. (1946 Act) ......................... (1) 9.3 12,200 
Reelfoot Lake-Lake No. 9, Ky. 
and Tenn ............................... (1) 18.3 797 - - - - - 
Running Reelfoot Bayou, Tenn. ............. 1955 19.7 4,145 - 19.7 4,145 - - 100 
Miss. River Below Cape Girardeau; West 
Tenn. tributaries. (1948 Act) ............... 1961 225.0 61,700 10.3 72.9 27,919 - - - - 45 
Wolf River and tributaries., Tenn............ 1960 25.5 5,338 - 25.5 5,338 - - 100 
1. Not started. 
2. Includes 5.8 miles of cleanout done under 
St. Francis River, Mo. and Ark., Project. 
0
0
x
tTj 
0
'TI 
z
z
r 
c
C, 
01 
tI P3

MISSISSIPPI RIVER COMMISSION 
TABLE 42-R COSTS DURING FISCAL YEAR 1975 
Construction 
FEDERAL FUNDS 
Flood control, Mississippi River and tributaries: 
Memphis District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
St. Francis Basin 
Lower White River 
Cache River, Ark. 
Channel improvement 
West Tennessee tributaries 
West Kentucky tributaries 
Inspection of completed works 
Mapping 
Reelfoot Lake 
Subtotal 
Vicksburg District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
Lower Arkansas River 
Tensas Basin 
Yazoo Basin 
Channel improvement 
Mapping 
Inspection of completed works 
Recreation facilities-completed project 
Streambank erosion control 
Subtotal 
New Orleans District: 
General investigations 
Advance engineering and design 
Mississippi River levees 
Lower Red River 
Old River 
Bayou Cocodrie and tributaries 
Atchafalaya Basin 
Channel improvement 
Bonnet Carre 
Inspection of completed works 
Mapping 
Subtotal 
Total Federal Funds 
CONTRIBUTED FUNDS 
Memphis District: 
Little River Drainage 
Revetments 
New Orleans District: 
Old River 
Revetments 
Total Contributed Funds 
Grand Total, Federal and 
Contributed Funds 
29,127 
8,708,428 
18,568,326 
40,310 
224,901 
18,897,306 
734,868 
75,462 
-_- 
$ -- 
1,019,162 
1,283,908 
239,005 
11,573,835 
27,646 
78,316 
$ 579,137 
1,6oO,7O1 . 
48,932,459 14,221,872 579,137 
-- -- 266,983 
335,931 - 
6,933,376 162,558 - 
- - 90,146 -- 
6,263,623 131,760 
14,255,899 9,167,231 
19,149,939 8,297,179 
-- 95,149 
- - 59,120 
782,768 - 
177,027 - 
47,898,563 18,003,143 266,983 
-- - 1,046,200 
199,805 - 
14,623,473 3,203,387 
534,524 313,830 
832,734 1,891,304 
5,111 54,877 
29,797,232 6,526,178 
23,523,710 3,972,995 
-- 262,713 
--40,338 
- - 63,221 
69,516,589 16,328,843 1,046,200 
166,347,611 48,553,858 1,892,320 
42,569 
1,970 
-- 49,191 -- 
1,700,000 -- -- 
1,744,539 49,191 -- 
$168,092,150 $48,603,049 $1,892,320 
42-55 
Maintenance Other

TABLE 42-S 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES (COSTS) UNDER APPROPRIATIONS 
FOR FLOOD CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, THROUGH 
FISCAL YEAR 1975 (NEW STRUCTURE EFFECTIVE 
1 JUL. 1955) 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Jun. 30, 1975 
ALLOTMENTS AND ACCRUED EXPENDITURES 
CHARGEABLE AGAINST FLOOD CONTROL 
ACT LIMITATIONS: 
COMPLETED WORKS: 
Waterways Experiment Station 
Office, Chief of Engineers 
Rock Island District: 
S. G. & 0. prior to Aug. 18, 1941 
St. Louis District: 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Memphis District: 
Des Arc, Ark. 
Contraction works 
DeValls Bluff, Ark. 
Mapping 
Memphis Harbor 
New Madrid Floodway 
Wolf River and tributaries 
Roads on levees (Mississippi River levees) 
S. G. & O. prior to Aug 18, 1941 
Subtotal 
Vicksburg District: 
Boeuf Basin levees 
Channel realignment, Arkansas River 
Contraction works 
Eudora Floodway 
Vicksburg Harbor 
Greenville Harbor 
Grants Canal (Mississippi River levees) 
Mapping 
Jonesville, La. 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
New Orleans District: 
Atchafalaya River and Basin, La. 
Bonnet Carre Spillway, La. 
Contraction works 
Mapping 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Wax Lake Outlet and Charenton Canal 
Morganza Floodway and structure 
Lake Pontchartrain 
Atchafalaya Basin, rights-of-way and flowage, 
Bayou des Glaises setback 
Subtotal 
All other completed items: 
Surveys under Sec. 10, Flood Control Act of 1928 
Impounded savings 
Plant transferred to revolving fund 
OCE (portion of allotment transferred to 
revolving fund, Washington Dist.) 
Subtotal 
F'otal completed works 
$ 874,000 
19,158 
14,010 
1 - '~ 
$ 874,000 
19,158 
14,010 
19,352 169,352 - - 
1,076,520 1,076,520 - - 
178,925 178,925 - - 
8,692,791 8,692,791 -- 
231,215 231,215 - - 
1,450,337 1,450,337 - - 
18,736,432 18,736,432 - - 
6,521,543 6,521,543 -- 
1,723,620 1,723,620 - - 
12,426 12,426 - - 
1,998,766 1,998,766 -- 
39,546,055 39,546,055 - - 
2,764,605 2,764,605 -- 
125,074 125,074 - - 
1,972,183 1,972,183 -- 
826,235 826,235 - - 
4,664,515 4,664,515 -- 
2,864,516 2,864,516 -- 
7,070 7,070 - - 
1,531,021 1,531,021 -- 
172,950 172,950 -- 
105,660 105,660 -- 
2,350,201 2,350,201 -- 
17,384,030 17,384,030 -- 
3,375,492 3,375,492 - - 
14,212,198 14,212,198 -- 
1,258,916 1,258,916 
1,112,967 1,112,967 -- 
540,838 540,838 -- 
2,701,566 2,701,566 -- 
10,098,817 10,098,817 -- 
35,992,117 35,992,117 -- 
5,513,110 5,513,110 -- 
387,917 387,917 -- 
75,193,938 75,193,938 -- 
4,995,215 4,995,215 -- 
1,593,097 1,593,097 -- 
24,924,578 24,924,578 - - 
19,882 19,882 -- 
31,532,772 31,532,772 -- 
164,733,315 164,733,315 -- 
42-56

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES (COSTS) UNDER APPROPRIATIONS 
FOR FLOOD CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, THROUGH 
FISCAL YEAR 1975 (NEW STRUCTURE EFFECTIVE 
1 JUL. 1955) 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Jun. 30, 1975 
UNCOMPLETED WORKS: 
Rock Island District: 
Levees under Sec. 6, Flood Control Act of 1928 
St. Louis District: 
Levees under Sec. 6, Flood Control Act of 1928 
Subtotal 
Memphis District: 
Mississippi River levees: 
Mississippi River levees 
New Madrid 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Reelfoot Lake 
Reelfoot Lake, Lake No. 9 
St. Francis Basin: 
Wappapello Lake 
St. Francis River and tributaries 
Big Slough and Mayo ditch 
Little River drainage 
Lower White River: 
Clarendon levee, Ark. 
Augusta to Clarendon, Ark. 
White River backwater levee, Ark. 
Levees under Sec. 6, Flood Control Act of 1928 
West Tennessee tributaries 
Cache River, Ark. 
West Kentucky tributaries 
Subtotal 
Vicksburg District: 
Mississippi River levees (excludes Grants Canal, 
$7,070, shown under completed works) 
Lower Arkansas River: 
North Bank 
South Bank 
Tensas Basin: 
Boeuf and Tensas Rivers, etc. 
Red River backwater levee, La. 
Tensas, Cocodrie pumping plant 
Lake Chicot pumping plant 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Levees under Sec. 6, Flood Control Act of 1928 
Yazoo Basin: 
Sardis Lake 
Enid Lake 
Arkabutla Lake 
Grenada Lake 
Greenwood 
Belzoni 
Yazoo City 
Will M. Whittington auxiliary channel 
$ 579,462 
1,897,980 
2,477,442 
109,708,354 
98,000 
275,209,307 
53,114,400 
63,300,000 
439,434 
2,135,000 
8,973,000 
101,800,771 
965,429 
16,835,800 
420,000 
1,378,172 
10,624,501 
108,651 
10,400,900 
1,485,000 
270,000 
657,266,720 
102,618,990 
7,049,414 
15,676,286 
34,395,000 
23,778,546 
1,035,400 
1,380,000 
228,539,565 
22,655,245 
40,392,555 
958,175 
12,717,000 
15,655,000 
12,798,000 
32,032,000 
6,688,000 
316,656 
2,205,611 
10,950,966 
$ 579,462 
1,897,980 
2,477,442 
106,698,921 
98,000 
274,882,545 
53,068,931 
63,187,153 
439,434 
1,788,463 
8,972,229 
98,706,749 
965,429 
16,085,791 
419,886 
1,378,172 
10,624,501 
108,651 
10,114,047 
1,261,231 
261,378 
649,061,513 
91,820,406 
7,049,414 
15,676,286 
30,455,681 
20,353,041 
651,941 
1,037,955 
221,829,656 
22,655,245 
39,893,127 
958,175 
12,482,275 
15,533,448 
12,751,750 
31,993,694 
6,241,827 
316,656 
2,205,611 
10,950,966 
3,009,433 
326,762 
45,469 
112,847 
346,537 
771 
3,094,021 
750,009 
114 
286,853 
223,769 
8,622 
8,205,207 
10,798,585 
3,939,319 
3,425,504 
383,459 
342,045 
6,709,910 
499,429 
234,725 
121,552 
46,250 
38,306 
446,173 
42-57

TABLE 42-S 
(Continued) 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES (COSTS) UNDER APPROPRIATIONS 
FOR FLOOD CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, THROUGH 
FISCAL YEAR 1975 (NEW STRUCTURE EFFECTIVE 
1 JUL. 1955) 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Jun. 30, 1975 
Vicksburg District: (Continued) 
Yazoo Basin: (Continued) 
Main Stem 
Tributaries 
Tributaries-Bank Stabilization 
Tributaries 
Big Sunflower, etc. 
Yazoo backwater 
Yazoo backwater-Muddy Bayou 
Upper auxiliary channel 
Streambank erosion control, evaluation and demonstration 
Subtotal 
New Orleans District: 
Baton Rouge Harbor 
Bayou Cocodrie and tributaries 
Channel improvement: 
Dredging 
Revetments 
Lower Red River (south bank levees) 
Levees under Sec. 6, Flood Control Act of 1928 
Mississippi River levees 
Atchafalaya Basin: 
Atchafalaya Basin Floodway 
Atchafalaya River navigation 
Old River 
Subtotal 
Total uncompleted projects 
ADVANCE ENGINEERING AND DESIGN 
(CONSTRUCTION) 
Memphis District: 
Reelfoot Lake, Lake No. 9 
Cache River 
Big Creek and tributaries, Lower White River 
Clarendon Levee, Lower White River 
West Kentucky tributaries 
Mud Lake pumping station, Tenn. 
Subtotal 
Vicksburg District: 
Yazoo Basin, Big Sunflower River, Steele Bayou 
Bushley Bayou, Red River backwater, Tensas Bayou 
Greenville Harbor, Miss. 
Mississippi River east bank, Vicksburg-Yazoo area, Miss. 
Mississippi River east bank, Natchez area, Miss. 
Subtotal 
New Orleans District: 
Mississippi Delta Region 
Teche Vermilion, basin water supply 
E. Rapides and south central Avoyelles Parishes 
Subtotal 
Total advance engineering and design 
Total completed works, uncompleted works, 
and advance engineering and design 
$ 18,461,000 
25,303,610 
612,484 
1,159,900 
16,851,300 
31,653,500 
2,078,500 
918,006 
200,000 
669,080,710 
699,185 
3,473,608 
35,945,266 
163,715,517 
11,552,000 
200,680 
93,088,000 
239,580,537 
303,463 
67,701,000 
616,259,255 
$ 18,011,129 
23,696,983 
612,484 
1,117,806 
14,674,342 
25,229,071 
1,456,721 
904,194 
177,027 
630,736,910 
699,185 
3,428,719 
35,945,266 
161,416,831 
10,645,308 
200,680 
80,702,472 
233,679,086 
303,463 
67,370,762 
594,391,770 
$ 449,871 
1,606,628 
42,094 
2,176,958 
6,424,429 
621,779 
13,812 
22,973 
38,343,800 
44,889 
2,298,686 
906,692 
12,385,528 
5,901,452 
330,238 
21,867,485 
1,945,084,127 1,876,667,635 68,416,492 
30,000 30,000 -- 
420,000 420,000 -- 
360,000 360,000 -- 
65,000 65,000 -- 
175,000 175,000 -- 
30,000 29,127 873 
1,080,000 1,079,127 873 
29,700 29,700 -- 
200,000 145,917 54,083 
200,000 110,590 89,410 
50,000 39,478 10,522 
50,000 39,946 10,054 
529,700 
159,000 
1,109,000 
615,000 
1,883,000 
3,492,700 
2,113,310,142 
365,631 
69,748 
649,209 
274,647 
993,604 
2,438,362 
2,043,839,312 
164,069 
89,252 
459,791 
340,353 
889,396 
1,054,338 
69,470,830 
42-58 
_

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES (COSTS) UNDER APPROPRIATIONS 
FOR FLOOD CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, THROUGH 
FISCAL YEAR 1975 (NEW STRUCTURE EFFECTIVE 
1 JUL. 1955) 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Jun. 30, 1975 
RECREATION FACILITIES-COMPLETED 
PROJECTS 
Eight-Year Program Funds 
Vicksburg District: 
Sardis Lake $ 1,585,500 $ 1,506,721 $ 78,779 
Enid Lake 2,286,800 2,160,314 126,486 
Arkabutla Lake 2,269,300 1,776,942 492,358 
Grenada Lake 1,644,500 1,595,459 49,041 
Total Eight-Year Program Funds 7,786,100 7,039,437 746,663 
Total chargeable against Flood Control 
Act Limitations excluding flood 
control emergencies 2,121,096,242 2,050,878,750 70,217,492 
Total maintenance since Aug. 18, 1941 701,626,855 695,032,483 6,594,372 
Total flood control emergencies 14,900,300 14,900,300 - - 
Total general investigations 14,212,881 13,461,003 751,878 
Total flood control, MR&T appropriations 2,851,836,278 2,774,272,536 77,563,743 
Appropriations in addition to flood control, MR&T 
Other appropriations itemized in footnote (1), 
pp. 2068-69, Annual Report for 1953 32,068,909 32,068,909 - - 
Grand total appropriated to Jun. 30, 1975 2,883,905,187 2,806,341,444 77,563,743 
Note: Preauthorization study costs chargeable to the MR&T authorization have been transferred to completed 
work. Costs not chargeable have been excluded from this report. 
TABLE 42-T STATEMENT OF EXPENDITURES FOR LEVEES BY 
STATE AND LOCAL ORGANIZATIONS FROM 
BEGINNING OF EARLIEST AVAILABLE 
RECORDS THROUGH DEC. 31, 1974 
Engineer 
District Expenditures 
Rock Island $ 9,813,671 
St. Louis 47,725,466 
Memphis 175,736,094 
Vicksburg 74,676,521 
New Orleans 327,590,136 
Total $635,541,888 
42-59

TABLE 42-U 
REPORT OF THE CHIEF OF ENGINEERS, U. S. ARMY 1975 
COST AND FINANCIAL STATEMENT 
Total 
Project Funding FY 72 FY 73 FY 74 FY 75 Jun. 30, 1975 
Mississippi River and General investitributaries 
(Regular gations: 
Funds) 1 Allotted 1,252,000 1,345,000 1,600,000 1,870,000 14,212,881 
Cost 1,180,977 1,231,058 1,321,624 1,892,320 13,461,004 
Construction (includes 
advance 
engineering 
and design): 
Allotted 60,035,600 77,278,000 215,825,5002 81,409,000 2,071,253,827 
Cost 61,738,019 57,910,188 88,925,1382 166,347,610 2,001,036,335 
Maintenance 
Allotted 31,300,000 32,900,000 50,567,000 36,772,000 752,005,406 
Cost 30,644,870 27,002,418 40,200,423 48,553,860 745,411,033 
Flood control 
emergencies 
(Maintenance): 
Allotted -- -- -- -- 14,885,922 
Cost -- -- -- -- 14,885,922 
(Contributed Funds) New Work: 
Contributed 14,700 5,300 71,050 1,750,971 6,856,413 
Cost 2,085 10,128 5,124 1,744,539 6,776,014 
Maintenance 
Contributed .27,225 28,313 33,6242 46,506 683,937 
Cost 26,950 28,274 31,368 49,191 683,937 
1. Appropriations were as follows: 
Appropriations chargeable against Flood Control Act authorizations: 
Flood Control, MR&T except for emergencies (excludes Maintenance 
allotments Aug. 18, 1941, through Jun. 30, 1975): 
Net total allotted for works under Mississippi River Commission: 
Eight-Year Program Funds, Construction General: 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 
Transferred to revolving fund: 
Impounded savings: 
Flood control emergencies: 
Net total allotted: 
Impounded savings: 
Additional funds not chargeable against Flood Control Act authorizations: 
Appropriations for Flood Control, MR&T, except for flood control emergencies: 
General investigations: 
Maintenance allotments Aug. 18, 1941, through Jun. 30, 1975: 
Appropriations in addition to appropriations for Flood Control, MR&T 
(itemized in footnote (1), pp. 2068-69, Annual Report for 1953): 
Budgetary and OCE Reserves: 
Grand total: 
Reconciliation of appropriations and allotments: 
Total allotted to Jun. 30, 1975: 
Transferred to revolving fund: 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 
Impounded savings withdrawn by Chief of Engineers: 
Budgetary and OCE Reserves: 
Total Appropriations to Jun. 30, 1975: 
Appropriations for past 4 years were as follows: 
FY 72: $92,587,600; FY 73: $111,523,000; and FY 74: $267,992,500 (see note 2 
below); and FY 75: $120,051,000. 
2. Correction of previously reported totals. 
$2,081,777,370 
7,786,100 
4,995,215 
24,944,460 
1,593,097 
14,885,922 
14,378 
14,212,881 
701,626,855 
$2,121,096,242 
14,900,300 
715,839,736 
32,068,909 
2,883,905,187 
2,852,358,037 
24,944,460 
4,995,215 
1,607,475 
2,883,905,187 2,883,905,187 
42-60

COASTAL ENGINEERING RESEARCH 
CENTER 
Organization and functions. The U.S. Army 
Coastal Engineering Research Center (CERC) 
was established under authority of Public 
Law 172, 88th Congress, which abolished the 
former Beach Erosion Board (organized under 
authority of sec. 2, 1930 River and Harbor 
Act, as amended (33 USC 426)) and directed 
that its functions, other than the review of 
reports of investigations made concerning 
erosion and protection of shores of coastal 
and lake waters, be vested with the Coastal 
Engineering Research Center. The report review 
function was transferred to the Board of 
Engineers for Rivers and Harbors, putting 
reports on beach erosion control and shore 
protection studies under the same review procedures 
as reports in other phases of the water 
resources study program of the Corps. 
The authorizing act also provided that the 
functions of the Coastal Engineering Research 
Center be conducted with the guidance 
and advice of a Coastal Engineering Research 
Board, to be constituted by the Chief of Engineers 
in the same manner as the former 
Beach Erosion Board. 
During fiscal year 1975, the following 
served as members of the Coastal Engineering 
Research Board: Major General John W. 
Morris and Major General Ernest Graves, 
U.S. Army, successive Directors of Civil 
Works, Office Chief of Engineers, President; 
Major General Carroll N. LeTellier, U.S. 
Army, Division Engineer, South Atlantic Division; 
Brigadier General Walter O. Bachus, 
U.S. Army, Division Engineer, North Central 
Division; Brigadier General Richard M. Connell, 
U.S. Army, Division Engineer, South 
Pacific Division; Brigadier General Robert L. 
Moore, U.S. Army, North Central Division; 
Dean Morrough P. O'Brien, Dean Emeritus, 
College of Engineering, University of California 
at Berkeley; Dr. Robert G. Dean, Professor 
of Civil Engineering and Marine Studies, 
University of Delaware; and Professor Robert 
L. Wiegel, Department of Civil Engineering, 
University of California at Berkeley; 
Colonel James L. Trayers was Executive Secretary 
to the Board and the Commander and 
Director of the Center. 
The Coastal Engineering Research Center 
is the principal research and development facility 
of the Corps in the field of coastal engineering. 
The mission of the Center is to: 
a. Conceive, plan, and conduct research and 
data collection in coastal engineering and 
nearshore oceanography to: 
(1) Provide a better understanding of the 
littoral forces (e.g., waves, winds, water levels, 
tides, currents) and the resultant coastal 
processes and the interaction of these forces 
and processes with shores and beaches, coastal 
and offshore structures, and the materials 
forming these shores, beaches, and structures; 
(2) Provide scientific and engineering data 
and design criteria; and 
(3) Determine the effects of the coastal activities 
of the Corps of Engineers on the ecology 
of the coastal zone. Research is directed 
toward application to shore and beach erosion 
control; flood and storm protection; the 
location, layout, design, construction, operation, 
and maintenance of harbor and of coastal 
and offshore structures; navigation improvement; 
and recreation. 
b. Publish findings and data resulting from 
research and other information concerning 
coastal phenomena which are useful to the 
Corps of Engineers and the public. 
c. Provide consulting services to the Corps 
of Engineers and other public agencies as 
requested or directed: 
(1) On the planning and design of coastal 
and offshore works; 
(2) On coastal and nearshore phenomena 
and related engineering and environmental 
problems; and 
(3) By reviewing studies, and plans and 
specifications for coastal and offshore engineering 
works. 
d. Operate a Coastal Engineering Information 
and Analysis Center to collect, evaluate, 
analyze, and disseminate coastal engineering 
information. 
43-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
Operations and results during fiscal year. 
The staff of the Coastal Engineering Research 
Center reviewed 16 reports for technical 
adequacy, of which 4 concerned navigation 
projects being considered for shore erosion 
mitigation work under policy expressed 
in sec. 111 of 1968 River and Harbor Act, 9 
concerned beach erosion control projects; 2 
concerned combined beach erosion-hurricane 
protection projects, and 1 concerned a combined 
beach erosion protection-navigation 
project. In keeping with the responsibility for 
publishing information and data concerning 
coastal phenomena, a number of technical 
reports by staff members were published by 
CERC or in other technical journals during 
the year and others were currently undergoing 
edit. 
Two Special Reports, nine Technical Memoranda, 
and seven Miscellaneous Papers were 
issued by the Coastal Engineering Research 
Center, and 27 manuscripts were backlogged 
for preparation to go to press in all categories. 
Eleven technical papers by CERC staff 
published elsewhere in the technical press 
were issued as CERC Reprints. Corrigenda 
were being compiled for the Center's major 
new compendium on shore protection, "Shore 
Protection Manual," which was completed and 
published in FY 1974 to replace the out-ofprint 
Technical Report No. 4, "Shore Protection 
Planning and Design." Work was also 
continued on preparation of a broader scope 
compendium titled "Coastal Engineering 
Manual" comprised of 25 separate chapter 
reports. One completed chapter report was 
published in FY 1975, one was near completion 
and two others were started. 
The staff worked on several major research 
or engineering projects for various agencies 
(including Corps field offices) and prepared 
reports thereon. Technical and administrative 
assistance was provided to the Corps Shore 
Erosion Advisory Panel. 
A training course in coastal engineering 
was given at CERC to a group of trainees 
from the Board of Engineers for Rivers and 
Harbors and attendees from other Federal 
agencies in the Washington, D.C. area; a special 
course in coastal engineering specifically 
on the "Shore Protection Manual" and its use 
was given at Atlanta, Georgia, for the staffs 
of SAD, LMVD and SWD, and again at CERC 
for attendees from NAD and NED; lectures 
were given by staff members to universities 
and to technical and nontechnical groups. 
Members of the staff participated in a 
number of committees of various technical 
societies (particularly ASCE). A staff member 
served as a U.S. delegate on the Permanent 
International Commission of the Permanent 
International Association of Navigation Congresses. 
Contract research to supplement 
staff activities was carried out at universities 
and with institutions and commercial concerns; 
funds were supplied other Corps offices 
for data collection; and funds were provided 
the Waterways Experiment Station to assist 
in carrying out a laboratory portion of the 
generalized tidal inlet study. At the end of the 
year work and studies by the staff were in 
progress in such areas as wave data analysis 
techniques, analysis of wave spectra, sources 
of sand for use as beach fill, development of 
criteria for evaluating suitability characteristics 
for beach fill, durability of various pile 
coatings in the surf zone; relation of longshore 
transport to incident waves; techniques 
for measuring longshore transport rates, 
wave direction measurements, effectiveness of 
vegetation for dune stabilization, coastal siltation 
problems peculiar to the Alaskan environment, 
use of remote sensing in coastal 
studies, geomorphology of the Atlantic coastal 
zone, ecological effects of offshore dredging, 
correlation of wave climate and beach 
deformation, effects of long-term water-level 
changes in the Great Lakes, wave refraction, 
and effects on design waves, development of 
standardized coastal revetment designs; evaluation 
of completed coastal works; and others. 
43-2

CALIFORNIA DEBRIS COMMISSION* 
This Commission, consisting of three Corps 
officers appointed by the President with the 
consent of the Senate, created by act of March 1, 
1893 (27 Stat. L., p. 507), was organized in San 
Francisco, Calif., on June 8, 1893, and has 
jurisdiction and duties extending over drainage 
area of Sacramento and San Joaquin Rivers, 
comprising great central valley of California 
and extending from crest of the Sierra Nevada 
on the east to that of the Coast Range on the 
west, and from Mount Shasta and Pit River 
Basin on the north to Tehachapi Mountains on 
the south. These rivers empty into head of 
Suisun Bay ultimately discharging into Pacific 
Ocean through connecting bays and straits and 
the Golden Gate. Duties of the Commission 
comprise regulation of hydraulic mining in 
drainage area of Sacramento and San Joaquin 
Rivers, Calif., so that debris will not be carried 
into navigable waters or otherwise cause 
damage; jurisdiction over construction and 
control of water storage facilities for domestic, 
irrigation, and power development purposes; 
and direction of improvements for control of 
floods on Sacramento River. 
IMPROVEMENTS 
Navigation Page 
1. Regulation of hydraulic mining and 
preparation of plans................ 44-1 
2. Sacramento River and tributaries, 
Calif. (debris control)................ 44-2 
Navigation (Cont'd) 
3. Treatment of Yuba River debris 
situation-restraining barriers, Calif. 44-2 
Flood Control 
4. Sacramento River, Calif............ 44-3 
Navigation 
1. REGULATION OF HYDRAULIC 
MINING AND PREPARATION 
OF PLANS 
Location. Operations largely limited to territory 
between Mount Lassen on the north and 
Yosemite Valley on the south, on western 
watershed of Sierra Nevada. (See Geological 
Survey sheets for the area, 25 in number.) 
Existing project. Provides for regulating 
hydraulic mining operations, planning improvement 
of conditions upon Sacramento and San 
Joaquin Rivers and their tributaries affected by 
such operations, and preparation of plans to 
enable hydraulic mining to be resumed in their 
drainage areas. In addition, the Secretary of 
Army is authorized to enter into contracts to 
supply storage for water and use of outlet 
facilities from debris-storage reservoirs for 
domestic and irrigation purposes and power 
development upon such conditions of delivery, 
use, and payment as he may approve. Applications 
of prospective miners are fully investigated 
by California Debris Commission and 
permits to operate are issued to those who 
provide satisfactory debris-restraining basins 
by construction of suitable dams where necessary 
or agree to make payment for storage in 
Government-constructed debris-restraining 
reservoirs constructed under act of June 19, 
1934, as set forth below. For location and 
description of Government-constructed, debrisrestraining 
reservoirs for general hydraulic 
mining, see Improvement 2. (See table 44-B for 
authorizing legislation.) 
Local cooperation. Mineowners must bear all 
expenses incurred in complying with orders of 
the Commission for regulation of mining and 
restraint of debris. 
*All cost and financial statements and authorizing legislation for projects are listed at the end of this chapter. All other 
tables are referenced in text and also appear at the end of this chapter. 
44-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Operations and results during fiscal year. 
Inspected hydraulic mines to determine compliance 
of mineowners with requirements of 
license issued. Administrative work overlaps 
that of improvements 2, 3, and 4, hereunder, 
and that of Sacramento District. 
Condition at end of fiscal year. The Commission 
received 1,292 applications for hydraulic 
mining licenses; 1 mine is licensed, but does not 
use storage behind Government debris dams. 
Work remaining is, in general, continuation of 
above or similar operations. 
2. SACRAMENTO RIVER AND 
TRIBUTARIES, CALIF. (DEBRIS 
CONTROL) 
Location. Project reservoirs are to be constructed 
in watersheds of Yuba, Bear, and 
American Rivers, Calif. (See Geological Survey 
sheets for basin areas, seven in number.) 
Existing project. Designed to permit resumption 
of hydraulic mining on a substantial scale 
and provides for construction of reservoirs for 
purpose of retaining mining debris. North Fork 
project is on North Fork of American River 
about 5 miles northeast of city of Auburn and 40 
miles northeast of Sacramento. Dam is 155 feet 
high, 620 feet long, and reservoir has debris 
storage capacity of 26 million cubic yards. 
Harry L. Englebright project is on Yuba River 
about 20 miles northeast of city of Marysville. 
Dam is 280 feet high, 1,142 feet long, and 
reservoir has a debris storage capacity of 118 
million cubic yards. Completed reservoirs are 
also utilized for recreation purposes; initial 
facilities were provided in fiscal year 1959. 
Recreation areas at Harry L. Englebright Dam 
are maintained by the Corps. Recreation areas 
at North Fork Dam are maintained and 
operated by Auburn Recreation Park and 
Parkway District. Total Federal cost of new 
work for construction of these reservoirs was 
$4,646,872, including $40,000 for recreation 
facilities. Cost of recreation areas at North Fork 
Dam was $57,500. It is estimated (July 1975) 
that improvements to recreation areas will cost 
$364,800 for Harry L. Englebright Dam. 
Reservoir project sites on Middle Fork of 
American River and on Bear River are considered 
inactive and excluded from foregoing cost 
estimate. Estimated cost of this portion is 
$1,820,000 (1935). Existing project was adopted 
by River and Harbor Act of 1935 (Rivers and 
Harbors Committee Doc. 50, 74th Cong., 1st 
sess.). For latest published map, see project 
document. Act of November 6, 1945, provided 
that dam constructed at Upper Narrows site on 
Yuba River, Calif., should thereafter be Harry 
L. Englebright Dam. 
Local cooperation. Satisfactory assurances 
were furnished the Secretary of the Army for 
repayment of capital cost of reservoir from 
taxes on material hydraulically mined, under 
licenses, and impounded in these reservoirs. 
Improvements made to facilities at North Fork 
Dam by Auburn Recreation Park and Parkway 
District under a lease agreement with the 
Secretary of the Army and Auburn Boat Clubs 
(concessionaire) at an estimated cost of $46,000 
since September 1953. 
Licenses. Under provisions of Contract No. W- 
1105-eng-2998 with Pacific Gas and Electric 
Co., payment is to be made to the Federal 
Government of $18,000 per year for the first 30 
years (December 29, 1942 through December 
28, 1972) and $48,000 per year between 
December 29, 1972, and December 28, 1992, in 
return for use of head at Englebright Dam and 
generation of hydroelectric power. Total payment 
through June 30, 1975, amounts to 
$654,393; these funds are paid to California 
Debris Commission and deposited for return to 
the Treasury. License No. 2246, effective April 
9, 1970 (date New Narrows powerplant put in 
operation) was issued by Federal Power Commission 
to Yuba County Water Agency for 
hydroelectric power development of Yuba River 
by the company upstream from Englebright 
Dam. Under provisions of Contract No. DA-04- 
167-CIVENG-66-95 with Yuba County Water 
Agency, payment is to be made to the Federal 
Government of $100,000 per year for no more 
than 50 years. First payment (partial) of 
$73,151 was made April 1, 1971; total payment 
through June 30, 1975, amounts to $473,151. 
These funds are paid to Sacramento District 
and deposited for return to the Treasury. 
Operations and results during fiscal year. 
Maintenance and operation activities continued 
at North Fork Dam at a cost of $24,564; and at 
Harry L. Englebright Dam at a cost of 
$142,864, including recreation facilities 
($60,250). 
Condition at end of fiscal year. Construction 
of dams was initiated in 1937; North Fork 
project was completed and in use at end of fiscal 
year 1939, and Harry L. Englebright project 
was completed in January 1941. The two debriscontrol 
structures are in good condition. Public 
use of these reservoir recreation areas greatly 
overtaxes present capacities. 
3. TREATMENT OF YUBA RIVER 
DEBRIS SITUATIONRESTRAINING 
BARRIERS, CALIF. 
Location. Works are on Yuba River between 
Marysville and where the river emerges from 
the foothills, near Hammonton, some 10 miles 
44-2

CALIFORNIA DEBRIS COMMISSION 
easterly from Marysville, or about 9 miles below 
the Narrows. (See Geological Survey Topographic 
map of Sacramento Valley, Calif.) 
Existing project. Provides for storage of 
mining debris within riverbed of Yuba River, a 
non-navigable stream, to keep such debris from 
passing into Feather and Sacramento Rivers to 
detriment of navigation therein. Improvement 
consists of a debris barrier, a 40-foot wide 
reinforced concrete stepped slab with upstream 
and downstream cutoff walls; training walls 
85,100 feet long which provide a 600-foot wide 
channel above and a 500-foot wide channel 
below dam; dikes across overflow channels; and 
protective works downstream to maintain Yuba 
River in its confined channel to its junction with 
Feather River at Marysville. Total cost of new 
work was $723,259, of which $361,482 was U.S. 
funds and $361,777 required contributed funds 
by State of California. (For details of project in 
its original form, see Annual Report, 1917, p. 
1810.) In February 1963, center section of dam 
failed and major rehabilitation of structure was 
completed in December 1964. Total cost for 
required rehabilitation was $1,660,000, of which 
$830,000 was Federal cost and $830,000 
required contribution by State of California 
toward rehabilitation cost. During the 
December 24, 1964, floodflows on the Yuba 
River, the rehabilitated Daguerre Point Dam 
sustained considerable damage. (See 1965 
Annual Report, p. 1647 "Operations and results 
during fiscal year.") The reconstructed portion 
of the dam completed earlier in December 1964 
was undamaged by the flood. Permanent repair 
of Daguerre Point Dam abutment and fish 
facilities was completed in October 1965 at a 
cost of $447,808 with Federal and required 
State contributed funds on a matching basis. 
Existing project was adopted in a rather 
indefinite form by River and Harbor Act of 
1896 and in its more definite form by River and 
Harbor Act of 1902 (H. Doc. 431, 56th Cong., 1st 
sess.). (For latest published map, see Geological 
Survey topographic map of Sacramento Valley, 
Calif.) 
Local cooperation. Fully complied with for 
new work and major rehabilitation work. Total 
first cost to local interests for new work was 
$361,777, all of which was required contribution 
by State of California. In addition, training 
walls were built on each bank below Daguerre 
Point for 11,250 feet and just above Daguerre 
Point, on the south bank, for 11,000 linear feet 
by two gold-dredging companies in connection 
with their dredging operations. It was estimated 
(1902) that it would have cost the United 
States $450,000 to build these training walls. 
Flood channels were also built by gold-dredging 
companies within the confines of the project 
works. It was estimated (1926) that cost of 
equally effective works to restrain debris 
movement would have been more than $776,000 
to the United States. Total costs to local 
interests for initial and permanent major 
rehabilitation works were $830,000 and 
$223,904, respectively, all of which was 
required contribution by State of California. 
State of California must contribute annually an 
amount equal to the Federal allotment for 
maintenance. 
Operations and results during fiscal year. 
Maintenance: Operations included condition 
and operation studies by hired labor; and a 
chain link fence around Daguerre Dam completed 
by contract, $4,449. 
Condition at end of fiscal year. Construction 
of project works was initiated in November 
1902. Construction of Daguerre Point Dam was 
completed in May 1906; diversion of river over 
dam was completed in 1910; training walls and 
dikes were completed in 1935. About 149 
million cubic yards of debris are held in lower 7 
miles of Yuba River between Marysville and 
downstream end of training walls. About 20 
million cubic yards are confined in river 
channel by Daguerre Point Dam. Additional 
millions of yards of loose material are in mine 
tailing fields adjacent to project training walls 
in upper 7-mile reach of project. Initial rehabilitation 
of Daguerre Point Dam begun in July 
1963 was completed in December 1964. Contract 
for permanent rehabilitation of structure 
was initiated in July and completed in October 
1965. 
Flood Control 
4. SACRAMENTO RIVER, CALIF. 
Location. Works covered by this improvement 
are on Sacramento River and tributaries in 
north-central California from Collinsville to Ord 
Bend, a distance of 184 miles. 
Previous project. For details see page 1815 of 
Annual Report for 1917, page 1995 of Annual 
Report for 1938, and page 2262 of Annual 
Report for 1907. 
Existing project. Sacramento River flood 
control project is a comprehensive plan of flood 
control for Sacramento River and lower reaches 
of its principal tributaries. Improvement 
extends along Sacramento River from Ord 
Bend in Glenn County, Calif., 184 miles downstream 
to its mouth at Collinsville at upper end 
of Suisun Bay, and comprises a system of levees, 
overflow weirs, drainage pumping plants, and 
flood bypass channels or floodways designed to 
carry surplus floodwaters without inundation of 
valley lands. About 980 miles of levee construc- 
44-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
tion with an average height of 15 feet, and 98 
miles of bank protection are involved in project. 
For further details, see Annual Report for 1962, 
page 2115. (See table 44-B for authorizing 
legislation.) 
Estimated (July 1975) cost for existing project 
(exclusive of above supplemental levee improvements), 
including new work and maintenance, 
is $163,640,000 of which $68,640,000 is Federal 
cost and $95 million non-Federal ($90,050,562 
for lands and damages and relocations and 
$4,949,438 required contributed funds for levee 
construction, bank protection works, and levee 
setbacks). Of this amount $4,939,752 was for 
new work and $9,686 for maintenance. In 
addition to project requirements, local interests 
constructed several pumping plants for drainage 
of agricultural and urban land protected by 
project levees. Also, some channel clearing work 
was accomplished by State of California and 
other local interests to supplement project levee 
construction. Dredging below Cache Slough and 
reconstruction of Cache Creek settling basin 
weir are considered deferred and excluded from 
foregoing cost estimate. Estimated cost (July 
1962) of these project units is $2,560,000 and 
$520,000, respectively, a total of $3,080,000 plus 
U.S. costs, for construction. Operation and 
maintenance of completed project will be 
responsibility of local interests; as units of 
project are completed, they are transferred to 
agencies of State of California for operation and 
maintenance. Existing project was adopted by 
1917 Flood Control Act (H. Doc. 81, 62d Cong., 
1st sess., as modified by Rivers and Harbors 
Committee Doc. 5, 63d Cong., 1st sess.), 1928 
Flood Control Act (S. Doc. 23, 69th Cong., 1st 
sess.), River and Harbor Act of 1937 (S. 
Committee print 75th Cong., 1st sess.), and 1941 
Flood Control Act (H. Doc. 205, 77th Cong., 1st 
sess.). 
Local cooperation. Local interests have fully 
complied with requirements for all work 
completed or under contract, and indicated they 
will be able to fulfill requirements for remaining 
work as scheduled. Local interests costs 
from required contributed funds for project 
work total $4,949,438 for levee construction, 
bank protection works, and levee setbacks, of 
which $4,939,752 was for new work and $9,686 
for maintenance. 
Operations and results during fiscal year. 
Regular funds: Minor levee reconstruction and 
engineering continued. 
Condition at end of fiscal year. Construction 
of existing project began in fiscal year 1918 and 
is about 99 percent complete. Channel improvement 
to date has produced a channel with a 
capacity of 579,000 cubic feet per second in 
Sacramento river below Cache Slough. In 
addition, discharges up to 21,000 cubic feet per 
second can be diverted from Sacramento River 
through Georgiana Slough. Completed major 
project items include about 977 miles of levees; 
five weirs with a combined discharge capacity 
of 602,000 cubic feet per second; two cutoff 
channels; two sets of outfall gates; channel 
improvement and clearing in Sacramento 
River, Butte Creek, Putah Creek, and Sutter 
and Tisdale Bypasses; construction of two main 
bypasses or floodways and secondary bypasses 
at Tisdale and Sacramento weirs and at 
Wadsworth Canal; construction of Knights 
Landing ridge cut and of Cache Creek settling 
basin; installation of gaging stations; and 
enlargement of Sacramento River below Cache 
Slough. Cutoffs at Collins Eddy and between 
Wild Irishman and Kinneys Bends were made 
in 1918 and 1919, respectively. Sacramento weir 
was completed in 1917, Fremont weir in 1924, 
Tisdale and Moulton weirs in 1932, and Colusa 
weir in 1933. Outfall gates at Knights Landing 
were constructed in 1930 and at mouth of Butte 
Slough in 1936. Pumping plants on Sutter 
Bypass were completed in 1944. Work items 
with reference to clearing, snagging, rectification 
of channels, and bank protection on 
Sacramento River and tributaries in Tehama 
County and from Red Bluff southerly, provided 
for by 1941 Flood Control Act were accomplished 
in fiscal years 1947, 1948, 1949, and 1951. 
Work remaining comprises completion of levee 
stage construction, Yolo Bypass and Cache 
Slough. (See table 44-C for total cost of existing 
project to June 30, 1975.) (See table 44-D for 
contributed funds, other.) 
44-4

CALIFORNIA DEBRIS COMMISSION 
TABLE 44-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 72 FY 73 FY 74 FY 75 June 30, 1975 
1. Regulation of 
Hydraulic Mining and 
Preparation of Plans 
2. Sacramento River and 
Tributaries, Calif. 
(Debris Control) 
3. Treatment of Yuba 
River Debris 
Situation Restraining 
Barriers, Calif. 
(Federal Funds) 
Required Contributed 
Funds) 
(Contributed Funds, 
Other)7 
4. Sacramento River, 
Calif. (Federal 
Funds) 
(Contributed Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
Rehab. 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
118 2,154 
118 2,154 
74,900 -62,100 
4,433 5,347 
97,000 153,400 
94,009 114,302 
14,000 
12,610 
12,610 
11,000 
18,168 
3,427 
29,671 
10,700 
3,900 
3,827 
-3,020 25,000 
112 
121,793 166,500 
154,516 167,428 
-2,800 
651 
651 
17,100 
4,226 11,587 
5,600 
3,808 
3,841 
1,000 
6,362 
1. Exclusive of $644,503 appropriation and costs on 
inactive portion of project. 
2. Includes $397,277 for recreational facilities at North 
Fork and Harry L. Englebright, Code 710 appropriations. 
3. Includes $372,389 for recreational facilities at North 
Fork and Harry L. Englebright. Code 710 costs. 
4. Includes $1,244,840 from regular funds and $599,931 
from Hydraulic Mining in California funds. 
5. Includes $1,236,282 from regular funds and $599,931 
from Hydraulic Mining in California funds. 
6. Includes deferred maintenance funds in amount of 
$207,500. 
7. Miscellaneous engineering and construction 
accomplished at expense of local interests in connection 
with rehabilitation of Daguerre Point Dam necessitated by 
December 1964 floodflows. 
8. Includes appropriation and cost of $680,000 for new 
work for previous project and $1,486,469 public works 
funds for new work for existing project. 
9. Includes $680,000 required contribution for previous 
project; $4,939,752 required contributed funds for existing 
p)roject; and $310,801 voluntary contribution for bank 
protection for existing project. 
10. Includes $9,686 required contributed funds for 
existing project. 
44-5 
821,325 
821,325 
5,044,1551 2 
5,019,2671 3 
1,844,7714 
1,836,2135 
361,482 
361,482 
1,4976 
1,491,3186 
1,053,904 
1,053,904 
361,777 
361,777 
1,493,223 
1,490,983 
1,053,904 
1,053,904 
34,000 
34,000 
67,288,3358 
67,283,2788 
1,979,104 
1,979,104 
10,724,0859 
10,721,7699 
9,68610 
9,68610

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
TABLE 44-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 1, 1893 
Feb. 27, 1907 
June 19, 1934 
June 25, 1938 
Dec. 22, 1944 and 
May 17, 1950 
July 3, 1958 
July 14, 1960 
REGULATION OF HYDRAULIC MINING AND 
PREPARATION OF PLANS (See Section 1 of Text) 
Created California Debris Commission and authorized: (a) 
Hydraulic mining under its regulation in drainage areas of 
Sacramento and San Joaquin Rivers, if possible without 
injury to navigability of these river systems or to lands 
adjacent thereto; and (b) preparation of plans by Commission 
for improvement of navigability of these river systems, and 
flood and debris-control therein. 
Authorized California Debris Commission to permit hydraulic 
mining without construction of impounding works, provided 
there is no injury to navigability of above river systems or 
lands adjacent thereto. 
Amended Act of Mar. 1, 1893, which provides for construction 
of debris dams or other restraining works by California 
Debris Commission and collection of a 3-percent tax on gross 
proceeds of each mine using such facilities, so as to 
eliminate this tax and substitute an annual tax per cubic 
yard mined, obtained by dividing total capital cost of each 
dam, reservoir, and rights-of-way, by total capacity of 
reservoir for restraint of debris; and authorized revocation 
of Commission orders permitting such mining, for failure to 
pay this annual tax within 30 days after its due date; and 
also authorized receipt of money advances, from mineowners 
to aid such construction, to be refunded later from annual 
payments of yardage taxes on material mined. 
Added at end of Sec. 23 of above Act, a provision that the 
Secretary of the Army is authorized to enter into contracts 
to supply storage for water and use of outlet facilities 
from debris-storage reservoirs for domestic and irrigation 
purposes and power development, upon such conditions of 
delivery, use, and payment as he may approve, these payments 
are to be deposited to credit of such reservoir project, 
reducing its capital cost to be repaid by tax on mining 
operations. 
SACRAMENTO RIVER, CALIF. (See Section 4 of Text) 
Additional levee construction and reconstruction, including 
levee protection of Upper Butte Basin, and multipurpose 
reservoirs. 2 
Bank protection and incidental channel improvements, 
Sacramento River from Chico Landing to Red Bluff, and 
local interests flood plain zoning above Chico Landing.2 
Bank protection works at critical locations, Sacramento River.2 
1. For latest published map, see Annual Report for 1913, 2. This supplemental work is reported in detail under 
p. 3170, and Rivers and Harbors Committee Document 50, Sacramento District, Improvement No. 26. 
74th Cong., 1st sess. 
44-6 
Ex. Doc. 267, 51st Cong., 
2d sess., Ex. Doc. 98 
47th Cong., 1st sess.1 
(Amendment of sec. 13, 
Act of Mar. 1, 1893.) 1 
H. Does. 649, 78th Cong., 
2d sess., and 367, 81st 
Cong., 1st sess. 
H. Doc. 272, 84th Cong., 
2d sess. 
S. Doc. 103, 86th Cong., 
2d sess.

CALIFORNIA DEBRIS COMMISSION 
TABLE 44-C SACRAMENTO RIVER, CALIF.: TOTAL COST OF 
EXISTING PROJECT TO JUNE 30, 1975 
(See Section 4 of Text) 
Funds New Work Maintenance Total 
Regular $65,116,809 $1,979,104 $67,095,913' 
Public Works 1,486,469 - 1,486,469 
Total U.S. $66,603,278 $1,979,104 $68,582,382 
Contributed Project Work 4,939,752 9,686 4,949,438 
Contributed, Other 5,102,017 - 5,102,017 
Total All Funds $76,645,047 $1,988,790 $78,633,837 
1. Excludes $429,671 representing book value of plant 
purchased with previous project funds and transferred to 
existing project without reimbursement. 
44-7

TABLE 44-D SACRAMENTO RIVER, CALIF.: RIVERS AND HARBORS, 
CONTRIBUTED FUNDS, OTHER (FY 1975) 
(See Section 4 of Text) 
Appropriations Expenditures Unexp. Unoblig. 
Bal. Bal. 
Project New Work Maintenance Total New Work Maintenance Total 6/30/75 6/30/75 
Sacramento River FCP $ - $ - $ - $ - $ - $ - $2,316 $2,316 
Sacramento Riv, Chico Ldg to 
Red Bluff' _ - _ _ - - 1,510 1,510 
Totals, FY 1975 - - - - - - 3,826 3,826 
Totals to June 30, 1975 
Sacramento River FCPs 10,724,085 9,686 10,733,771 10,721,769 9,686 10,731,455 
Sacramento R. & M&M Tribs.2 1,603,811 - 1,603,811 1,603,811 - 1,603,811 
Sacramento R., Chico Landing 
to Red Bluff' 28,582 - 28,582 27,072 - 27,072 
Emergency FC Work - 48,014 48,014 - 48,014 48,014 
American River 54,019 - 54,019 54,019 - 54,019 
Totals to June 30, 1975 $12,410,497 $57,700 $12,468,197 $12,406,671 $57,700 $12,464,371 
1. Includes Contributed Funds, Other for reactivated 
units of Sacramento River, Chico Landing to Red Bluff 
Project. 
2. Excludes $789,008 contributed by State Highway 
Department under Project No. 811, Contributed Funds, 
Other. 
3. Includes $680,000 for previous project. 
0d00 
O
y0 
z
n
0
z
c 
z
r
JD 
x

U. S. ARMY ENGINEER WATERWAYS 
EXPERIMENT STATION 
Organization and functions. The Waterways 
Experiment Station is a field operating agency of 
the Chief of Engineers operating under the staff 
supervision of the Chief, Research & 
Development Office, in accordance with General 
Orders No. 4, 1974. It was originally established 
as a hydraulic laboratory, June 18, 1929, under 
the President, Mississippi River Commission, by 
direction of the Chief of Engineers. Colonel G. H. 
Hilt, Corps of Engineers, is Director. 
The organization is the largest laboratory 
complex of the Corps of Engineers for research, 
testing, and development. It is engaged in 
research and engineering investigations in 
support of the civil and military missions of the 
Chief of Engineers in the scientific fields of 
hydraulics, soil mechanics, concrete, expedient 
construction, nuclear and conventional weapons 
effects and explosives excavation, protective 
structures, vehicle mobility, environmental 
relationships, engineering geology, rock 
mechanics, and pavements. On a reimbursable 
basis, the Waterways Experiment Station 
performs basic and applied research in these and 
related fields, develops methods and techniques, 
tests materials and equipment, and provides 
consulting services in its specialized fields of 
competence. Such services include essential 
technical support in instrumentation 
development and scientific and engineering 
computer services. Subject to approval by the 
Chief of Engineers, studies and investigations 
may be undertaken for other agencies. 
The Waterways Experiment Station maintains 
an extensive scientific and engineering reference 
library to serve specialized needs of the Corps of 
Engineers; issues publications of general interest 
(including translations) which can help eliminate 
duplication of effort throughout the Corps in 
conducting experimental studies; operates DOD 
Information Analysis Centers in the fields of 
Pavements and Soils Trafficability, Concrete 
Technology, Hydraulic Engineering, and Soil 
Mechanics; maintains the Corps of Engineers 
Engineering Computer Programs Library 
(including audiovisual training aids), the Corps of 
Engineers motion picture lending library, and 
the Corps Guide Specifications service. 
During Fiscal Year 1975, 201 reports of 
individual studies conducted at the Waterways 
Experiment Station, 8 in-house translations, 7 
contract translations, 15 contract reports, and 38 
miscellaneous publications for the Waterways 
Experiment Station and other offices were 
distributed to Corps offices and interested outside 
agencies. In addition, editing and printing units 
completed about 3,000 miscellaneous 
assignments for the Waterways Experiment 
Station and other offices. 
Operations and results during fiscal year. Work 
accomplished at the Waterways Experiment 
Station is, in general, initially financed by a 
revolving fund, with direct reimbursement from 
agencies for whom the work is performed. The 
Station's program for Fiscal Year 1975 was 
$39,185,500 of which $35,333,113 was charged to 
establishments served for research investigations 
and related services, and $3,852,387 for 
permanent improvements and equipment. Of 
the reimbursable work, $15,924,482 was charged 
to civil funds, $18,965,846 to military funds, 
and $442,785 to nongovernmental agencies. 
Work includes $6,015,568 performed by 
contract. 
45-1

PERMANENT INTERNATIONAL 
ASSOCIATION OF 
NAVIGATION CONGRESSES 
The United States by Act of June 28, 1902, 
appropriated $3,000 annually for support and 
maintenance of the Permanent International 
Association of Navigation Congresses and for 
payment of the actual expenses of properly 
accredited national delegates of the United 
States to meetings of the Congresses and 
Commission. An increase in the appropriation 
of $5,000 annually was authorized by the 
1948 River and Harbor Act and an appropriation 
of $22,000 annually by the 1965 River 
and Harbor Act. The current appropriation of 
$45,000 was authorized by the 1974 Water 
Resources Development Act. Of this amount, 
$6,000 is paid by the American Section to the 
International Association in Brussels, Belgium. 
The objective of the Association-to promote 
the progress of inland and maritime navigation-
is met by holding International Congresses 
and publishing technical bulletins and 
other documents. The Congresses are held in 
various member countries, usually at 4-year 
intervals. The Association is supported principally 
by member governments, but membership 
also extends to corporations and individuals. 
Member governments are represented at 
the Congresses and at meetings of the Permanent 
International Commission by delegates, 
the number of official delegates to be determined 
by the amount of the annual subsidy 
paid by the government, but not to exceed ten. 
Corporate members may send one official representative 
to the Congresses, Individual 
membership is of two classes, Annual and 
Life, depending on the method of payment of 
dues. 
The affairs of the Association are managed 
by the Permanent International Commission, 
composed of delegates from the supporting 
governments. The National Commission constitutes 
the governing body of the American 
Section and the U. S. members of the Permanent 
International Commission. The Director 
of Civil Works, Office of the Chief of Engineers, 
U. S. Army, and the Resident Member, 
Board of Engineers for Rivers and Harbors, 
are the ex-officio Chairman and Secretary, 
respectively, of the National Commission. The 
Secretary handles all administrative matters 
of the American Section. 
During Fiscal Year 1975, National Commissioners 
were: MG J. W. Morris, USA, ex-officio 
Chairman; COL William G. Kratz, CE, USA, 
ex-officio Secretary; Mr. Kenneth J. Bousquet; 
COL Carl H. Bronn, USA (Ret); RADM Roderick 
Y. Edwards, USCG (Ret); Mr. Minard I. 
Foster; Honorable David W. Oberlin; Mr. J. 
W. Hersey; Mr. Duane Orr; and Mr. Thorndike 
Saville. 
Membership of the American Section on 
June 30, 1975, totaled 647, consisting of 160 
life, 421 individual, and 66 corporate members. 
A total of 44 new individual members 
and 12 corporate members were added during 
the fiscal year, and 3 life members, 32 individual 
members, and 11 corporate members were 
deleted, either through resignations, death, or 
non-payment of dues. 
Federal funds from annual appropriations 
were estimated as follows: $6,000 for annual 
U. S. contribution to the association, $20,418 
for expenses of representatives to meetings, 
and $6,531 for miscellaneous expenditures. 
464-

INVESTIGATIONS AND SUPERVISION 
OF PROJECTS UNDER FEDERAL 
WATER POWER ACT 
The Federal Water Power Act of June 10, 
1920, created the Federal Power Commission, 
composed of the Secretaries of War, Interior, 
and Agriculture, with authority to grant 
permits and licenses for hydroelectric development 
in all waters over which Congress has 
jurisdiction. The act further required that 
work of the Commission be performed by and 
through the Departments of War, Interior 
and Agriculture and their engineering, technical, 
and other personnel except as may be 
otherwise provided by law. By an act of June 
23, 1930, entitled "An Act to Reorganize the 
Federal Power Commission," Secs. 1 and 2 of 
the Federal Water Power Act of 1920 were 
amended. A commission was provided for, to 
be composed of five commissioners to be appointed 
by the President, by and with the advice 
and consent of the Senate. The necessity 
of performing work through the Departments 
of War, Interior, and Agriculture was removed 
and the Commission was authorized to 
appoint such officers and employees as necessary 
in executing its function. By title II, 
Public Utility Act of 1935, the original Federal 
Water Power Act was made Part I of the 
Federal Power Act, and Parts II and III were 
added to that act. Section 4(e) of the Federal 
Power Act provides that no waterpower license 
affecting navigable capacity of any 
navigable waters of the United States shall 
be issued until plans of the dam or other 
structures affecting navigation have been 
approved by the Chief of Engineers and the 
Secretary of the Army. By an action, notice 
of which was published in the Federal Register 
Volume 40, Number 74, dated April 16, 
1975, the Secretary of the Army delegated to 
the Chief of Engineers his authority under 
Sec. 4(e) of the Federal Power Act. There is 
further provision whereby any person or corporation 
intending to construct hydroelectric 
project works in or along any stream over 
which Congress has jurisdiction, other than 
navigable waters, shall file a declaration of 
intention for the purpose of ascertaining 
whether or not jurisdiction of the Federal 
Power Commission will attach. 
The following work of an engineering nature 
was assigned and accomplished during 
the fiscal year: 19 plans approved by the 
Chief of Engineers in accordance with Sec. 
4(e) of the Federal Water Power Act; 43 reports 
submitted on applications for preliminary 
permits or licenses or amendments thereto 
and reports on licensed projects subject to 
recapture (including environmental statements); 
and supervision of 7 licensed projects 
for the Commission. 
Necessary expenses in excess of nominal 
amounts for transportation and subsistence 
of personnel engaged in investigations and 
cost of supervision under provisions of the 
Federal Water Power Act are paid from appropriations 
made for the Federal Power 
Commission. All other costs of administration 
of laws in question are paid from funds available 
for general expense of the Corps of Engineers. 
No expenses were paid from appropriations 
made for the Federal Power Commission 
during the fiscal year. 
47-1

MISCELLANEOUS CIVIL WORKS 
TABLE OF CONTENTS 
1. Miscellaneous Activities ................ 48-1 
2. International Boundary Waters 
Boards .............. ............................. 48-2 
2A. International St. Croix River Board 
of Control ........................................ . 48-2 
2B. International Lake Memphremagog 
Board ..................................... 48-3 
2C. International Lake Champlain 
Board of Control ............................. 48-4 
2D. International Champlain-Richelieu 
Engineering Board .......................... 48-4 
2E. International Champlain-Richelieu 
Board ..................................... 48-5 
2F. International St. Lawrence River 
Board of Control ............................. 48-6 
2G. International Niagara Board of 
Control ..................................... 48-8 
2H. International Niagara Committee .. 48-10 
21. American Falls International 
Board ..................................... 48-11 
2J. International Great Lakes Levels 
Board ............................................... 4 -12 
2K. Coordinating Committee on Great 
Lakes Basic Hydraulic and 
Hydrologic Data ................................ 48-13 
2L. International Great Lakes Study 
Group ..................................... 48-14 
2M. International Lake Superior Board 
of Control ............................................ 48-14 
2N. International Prairie Portage 
Board of Control ............................. 48-16 
20. International Rainy Lake Board of 
Control ..................................... 48-16 
2P. International Lake of the Woods 
Control Board .................................. 48-17 
2Q. International Pembina River 
Engineering Board .......................... 48-18 
2R. International Souris-Red Rivers 
Engineering Board .......................... 48-18 
2S. International Roseau River 
Engineering Board .......................... 48-19 
2T. International Kootenay Lake Board 
of Control ............................................ 48-20 
2U. International Osoyoos Lake Board 
of Control ........................................ 48-21 
2V. International Skagit River Board of 
Control ..................................... 48-21 
2W. Columbia River Treaty Entities ...... 48-22 
2X. Columbia River Treaty Permanent 
Engineering Board .......................... 48-23 
1. MISCELLANEOUS ACTIVITIES 
In addition to the work of improving rivers 
and harbors, civil works of a miscellaneous 
character, as indicated below, have been 
committed to the Corps of Engineers. 
Work accomplished. The work of the fiscal 
year is summarized as follows: 6 danger zone 
regulations established or modified under 
provisions of Chapter XIX of the Army Act of 
July 9, 1918, or Sec. 7 of the River and Harbor 
Act of August 8, 1917; 5 navigation regulations 
established or modified under provisions 
of Sec. 7, River and Harbor Act of August 
8, 1917; 12,770 permits issued for work 
on structures in navigable waters under provisions 
of Sec. 10, River and Harbor Act of 
March 3, 1899, Sec. 404 of the Federal Water 
Pollution Control Act, and Sec. 103 of the 
Marine Protection Research Sanctuaries Act 
of 1972; 27 sunken vessels removed under 
provisions of Sec. 18 and 20, River and Harbor 
Act of 1899; and 392 sunken vessels investigated 
and either removed by owner or removal 
was not considered necessary. 
Funds with which the above miscellaneous 
activities were prosecuted during the fiscal 
year totaled $19,531,398. See Table 48-A for 
breakdown. 
48-1

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
2. INTERNATIONAL BOUNDARY 
WATERS BOARDS. 
In order to carry out United States obligations 
under international agreements, the 
Office of the Chief of Engineers, several Divisions 
and Districts of the Corps with jurisdiction 
over areas bordering Canada, have representation 
on numerous international boards 
and committees. The majority of these boards 
are established by the International Joint 
Commission (IJC) as empowered in accordance 
with the provisions of the Boundary Waters 
Treaty of 1909 between the United States and 
Great Britain (for Canada). IJC boards fall 
into two broad categories; boards of control, 
which are more or less permanent and supervise 
compliance over an IJC Order; and engineering 
or technical boards, which are usually 
dissolved after completing an investigation 
assignment. In addition to boards created by 
the Commission, other international boards 
and committees are created by treaties or 
other informal arrangement in matters concerned 
with the water resources of joint interest, 
and the members report directly to the 
Government or establishing agency. A listing 
of these international boards and committees 
having Corps of Engineers membership during 
the fiscal year follows: 
2A. THE INTERNATIONAL ST. CROIX 
RIVER BOARD OF CONTROL 
Constitution and duties. The Board was 
organized pursuant to conditions in the Orders 
of the International Joint Commission 
approving the maintenance and operation of 
the dam built by the St. Croix Water Power 
Co. and the Sprague Falls Manufacturing Co., 
Ltd., across the St. Croix River at Grand 
Falls, Maine, and subsequent agreements 
reached between the Goverments of the Unted 
States and Canada. The Board is charged 
with the duty of formulating and administering 
rules under which the power plant and 
accessories are to be operated to prevent as 
nearly as possible a level of water at the dam 
higher than 203.5 feet (mean sea level), and to 
secure for the users of water below Grand 
Falls the flow of water to which they are entitled. 
The Board is also charged with the supervision 
of the operation of all fishways on 
that portion of the St. Croix River that forms 
the international boundary. On October 2, 
1934, the Commission issued an Order approving 
the reconstruction of the dam by the Canadians 
Cottons, Ltd., extending across the 
St. Croix River from Milltown, New Brunswick, 
Canada, to Milltown, Maine which contained 
the following conditions: (a) the reconstructed 
dam to be operated to insure that the 
forebay levels rise to no higher evaluation 
than that which was obtained in the operation 
of the dam being replaced; (b) during 
floods the sluiceways of the dam shall be sufficiently 
open to insure passage of the river 
flow; and (c) the operation of the dam, insofar 
as is necessary to insure the observance of 
the provisions of the Order, be under the supervision 
of the Board. On November 19, 
1965, the Commission directed the Board, in 
addition to the duties previously assigned, to 
carry out the duties contained in the Order 
dated October 15, 1965, for the construction 
of the storage dam at Vanceboro, Maine, and 
to report to the Commission annually in 
March. 
Members of the Board for fiscal year. Colonel 
J. H. Mason, Division Engineer, U. S. 
Army Engineer Division, New England, Waltham, 
Massachusetts, was United States 
member and Mr. J. E. Peters, District Engineer, 
Inland Waters Directorate, Department 
of the Environment, Halifax, Nova Scotia, 
was the Canadian member. 
Operations during fiscal year. Supervision 
was maintained and inspection was made by 
the Board members and their representatives 
to insure that the Orders of the Commission 
were followed. 
The Board performed the annual inspection 
of the St. Croix River Basin in the period 
June 16-17, 1975 meeting with officers of the 
New Brunswick Electric Power Commission at 
Milltown, New Brunswick, and the Georgia- 
Pacific Corporation in Woodland, Maine. 
The Board submitted a Plan of Study in 
August 1972 for the Water Resources System 
Operation investigation. The Commission 
approved a revised Plan of Study, dated November, 
1972. The study considered re-regulation 
of the complex of storage reservoirs operated 
by Georgia-Pacific Corporation with 
particular attention given to moderating the 
allowable drawdown levels specified for 
Spednic Lake and its control structure, Vanceboro 
Dam. Studies by the Board were completed 
and a report submitted on April 8, 1975 
to the Commission. The public was notified of 
the Board's findings on May 15, 1975. 
The study of fluctuations in r leases from 
the Vanceboro Dam indicates that during a 
5-year period (1967 - 1971) there were numerous, 
random, occasions when the change in 
mean daily discharge, for consecutive days, 
was greater than 25 percent. These changes 
were, therefore, not necessitated by abnormal 
hydrologic events. The Fisheries and Marine 
48-2

MISCELLANEOUS CIVIL WORKS 
Service, Environment Canada, have indicated 
no problems with flow increases for fish habitat, 
but recommended decreases should be 
held to 25 percent or less. The Georgia-Pacific 
Corporation, which operates the dam, has indicated 
that they would be likely to hold decreases 
in discharge to within 25 percent over 
a 24-hour period. A general trend toward fewer 
extreme changes is apparent during the 
period studied, possibly indicating a greater 
awareness by the Georgia-Pacific Corporation 
of the adverse effects of these extreme flow 
variations. 
Five alternative plans of regulations for 
Spednic Lake were developed. For the purposes 
of comparison, these alternatives plans 
vary from the extremes of operating the lake 
for power purposes only, to operating for the 
enhancement of fisheries at the expense of all 
other interests. The report discussing the 
advantages and disadvantages of each plan 
was presented informally to major concerned 
interests of the basin at a meeting in Halifax, 
Nova Scotia on February 12, 1975. 
Tentatively, the best plan appears to be to 
maintain the level of Spednic Lake at or 
above elevation 378.5 feet (mean sea level) on 
a year round basis for a two-year trial period. 
The Board report proposes that after 
this monitoring period the operations Order 
be reviewed and modified, if appropriate, and 
adopted on a permanent basis. However, the 
power studies conducted in this interim report 
were based on a general understanding of the 
existing and past operation of the Georgia- 
Pacific Corporation storage system. It should 
be noted that the current energy crisis may 
cause a change in the existing operation of 
the Georgia-Pacific hydroelectric plants, using 
them more for peaking purposes. Because 
of the current energy situation, Georgia-Pacific 
has serious objections to any further 
restrictions in regulation of the lake system. 
Also the effects of changes in flow regulation 
on the New Brunswick Electric power facilities 
at Milltown should be analyzed. Before a 
final plan for Spednic Lake regulation can be 
proposed, additional data on the operation of 
the Georgia-Pacific system is required. The 
Corporation advises that they are conducting 
such studies and plan to evaluate them in 
conjunction with the findings of the Board's 
interim report. 
The Board met with officials of Georgia- 
Pacific Corporation and New Brunswick Electric 
Power Commission on June 17, 1975 at 
Woodland, Maine to discuss Georgia-Pacific's 
proposed power system study. The study will 
be done by a private consultant from Pittsfield, 
Maine and will analyze the present thermal/
hydroelectric system with the objective of 
maximizing its output. Their study is scheduled 
for completion in the fall of 1975. 
2B. INTERNATIONAL LAKE 
MEMPHREMAGOG BOARD 
Construction and duties. Lake Memphremagog 
is in northern Vermont and southeastern 
Quebec and has as its outlet Magog River in 
Canada. In 1920 the city of Newport and 
towns of Derby, Conventry, and Barton, in 
Vermont, alleged they had been harmed by 
lake levels attributable to construction and 
operation of power plants on the Magog River. 
As a result, the Board composed of one 
engineer each from the United States and 
Canada was appointed by the two Governments 
to consider the matter and submit a 
joint report to each Government as to the level 
or levels at which Lake Memphremagog 
should, so far as possible, be maintained. At 
the request of local interests consideration of 
the problem was suspended until 1931 when a 
survey was made. Subsequently a joint report 
by the Board, dated May 14, 1934, was submitted 
to each Government. This report recommended 
that the lake levels under normal 
flow conditions range between an upper elevation 
of 682.70 feet above mean sea level (Geodetic 
Survey of Canada, 1923 adjustment), 
and a lower limit of 678.98 feet. During flood 
conditions, the sluiceways of the dam should 
be so operated as to reduce the flood water 
elevations to the normal regulated level of 
682.70 as rapidly as possible. The Board was 
reactivated by Governments on August 12, 
1960, as a result of a complaint on July 20, 
1959 by a resident of Newport, Vt., concerning 
high lake levels due to alleged improper 
operation of the power plant. 
Members of the Board for fiscal year. For 
Canada: Mr. R.L. Pentland, Inland Waters 
Directorate, Department of the Environment 
and for the United States: Colonel H.W. Lombard, 
New York District Engineer, U.S. Army 
Corps of Engineers until December 15, 1974 
and Colonel T.C. Hunter, Jr., same office 
thereafter. 
Operations during fiscal year. Supervision 
of the levels was maintained. The Water Resources 
Branch of the U.S. Geological Survey 
records daily readings of the elevation of 
Lake Memphremagog at Newport, Vermont. 
Datum of the gage is 673.00 feet above mean 
sea level, U.S. Geological Survey 1929 adjustment, 
which is 0.30 feet higher than the comparable 
Geodetic Survey of Canada, 1923 ad- 
48-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
justment. The upper limit of the recommended 
lake level was exceeded for several days in 
July 1974 and local interests in the Bluffs section 
of Newport complained of erosion damages 
to their lands caused by high water and 
wave wash. The Canadian member of the 
Board inspected the flood area in July 1974 
during a period of high water accompanied by 
a representative of the United States member 
and a leader of the local United States property 
owners group. Interested Canadian and 
United States' citizens formed Lake Memphremagog 
Conservation, Inc. The two citizen 
groups, working in conjunction with the Dominion 
Textile Co. agreed on a regulation 
scheme within the limits of the international 
agreement. As of June 30, 1975, the regulation 
of the lake in accordance with the mutually 
agreed scheme appears to have eliminated 
damage problems. 
2C. INTERNATIONAL LAKE CHAMPLAIN 
BOARD OF CONTROL 
Constitution and duties. The Board was 
organized pursuant to the provision of the 
Order of Approval, dated June 10, 1937, of the 
International Joint Commission approving 
construction and operation of certain remedial 
works in the Richelieu River at Fryers Island, 
Quebec. The Board submitted a report 
to the Commission dated May 4, 1938 soon 
after completion of the Fryers Island Dam. 
The Board is responsible for insuring compliance 
with provisions of the Order insofar as 
they relate to the regulation of the levels of 
Lake Champlain. 
Members of the Board for fiscal year. Mr. J. 
Bathurst, Chief, Engineering Division, Water 
Planning and Management Branch, Inland 
Waters Directorate, Department of the Environment, 
and Colonel H. W. Lombard, District 
Engineer, U.S. Army Engineer District, New 
York, for the United States until December 
15, 1974 and Colonel T. C. Hunter, Jr., same 
office, thereafter. 
Operations during fiscal year. No construction 
or other operations on the Richeleiu River 
have been performed during the fiscal year. 
The proposed construction of a new lock just 
below St. Jean Rapids, which would provide 
navigational access from the Chambly Canal 
into the reach of the river upstream of Fryers 
Island Dam, has been delayed pending a decision 
of flood control measures for the river. 
Information and complaints have been received 
from numerous communities along 
Lake Champlain of flood damages caused by 
high lake levels prevailing since 1972. Informal 
investigations indicated that high lake 
levels were presumably caused by heavy rainfail 
and the natural barriers in the channel of 
the Richelieu River for which the Board and 
Commission concluded that the Canadian 
Government is in no way responsible. However, 
as a result of these conditions, the Governments 
of Canada and the United States 
agreed to request the International Joint 
Commission to investigate possible regulation 
(See International Champlain-Richelieu Engineering 
Board). 
2D. INTERNATIONAL CHAMPLAINRICHELIEU 
ENGINEERING BOARD 
Constitution and duties. The Governments 
of Canada and of the United States agreed by 
letter dated March 29, 1973, pursuant to Article 
IX of the Boundary Waters Treaty of 
1909, to request the International Joint Commission 
to investigate and report upon the 
feasibility and desirability of regulation of 
Lake Champlain with remedial works in the 
Richelieu River for the purpose of alleviating 
extreme water conditions in the Richelieu 
River and in Lake Champlain, and for other 
beneficial purposes. Pursuant to the Commission's 
decision April 6, 1973, the Engineering 
Board was established on April 24, 1973 to 
undertake, through appropriate agencies in 
Canada and the United States, the necessary 
investigations and studies and to advise the 
Commission on all matters which it must consider 
in making its reports to Governments 
under the Reference of March 29. 1973. 
Members of the Board for fiscal year. The 
Canadian members were: Mr. H.B. Rosenberg, 
Department of the Environment, Chairman; 
Mr. E. Morin, Parks Canada, Department of 
Indian and Northern Affairs; Mr. B. Harvey, 
Department of Natural Resources, Province 
of Quebec; and Mr. B. Vallee, Province of 
Quebec, Planning and Development Office. The 
U. S. members were: Colonel H.W. Lombard, 
District Engineer, U.S. Army Engineer District, 
New York, Chairman until December, 
15, 1974 and Colonel T.C. Hunter, Jr., same 
office thereafter; Mr. J.A. Finck, Jr., New 
York State Department of Environmental 
Conservation; Mr. A. W. Albert, Vermont 
Agency for Environmental Conservation; and 
Mr. T.K. Klock, New England River Basins 
Commission. 
Operations during fiscal year. Additional 
data wre obtained by the Board on flood damages 
resulting from high lake levels and the 
effect of varying lake levels on the existing 
environment of Lake Champlain. 
48-4

MISCELLANEOUS CIVIL WORKS 
Several aspects of the investigation were 
pursued simultaneously by the Committees 
established by the Board to consider hydraulics, 
economics and environment. The Board 
did not presuppose that human regulation of 
Lake Champlain was. either necessary or desirable. 
Therefore, great emphasis was placed 
from the beginning of the study on the early 
resolution of the question of the desirability 
of such regulation. At the same time, the very 
possibility that such regulation might prove 
to be desirable meant that the study of engineering 
alternatives to achieve such regulation 
must also be initiated immediately, if the 
Board was to report intelligently to the 
Commission within one year as requested. 
The final report of the Board was completed 
in September 1974 and the Commission held 
public hearings in the area in December 1974 
on the Board's findings. The Board's report 
concluded that regulation of Lake Champlain 
to reduce extreme water levels and attendant 
damages was feasible and was desirable to 
the extent that the avoidance of such damage 
was a desirable objective. No better means of 
avoiding such damage to existing development 
was available but non-structural measures 
were feasible to reduce damages to future 
development. The Board considered 62 
schemes and presented four of them as suited 
for specific objectives. One scheme was agreed 
to be environmentally least disturbing. The 
United States Section of the Board concluded 
that the decision on regulation of Lake Champlain 
should be deferred until completion of 
the recommended environmental study. The 
Canadian Section of the Board concluded that 
regulation, once implemented, could be modified 
at any time to meet environmental requirements. 
The Commission reported to the 
Governments on March 6, 1975 and disbanded 
this Board on April 18, 1975 and formed a 
new Board: The International Champlain- 
Richelieu Board. 
2E. INTERNATIONAL CHAMPLAINRICHELIEU 
BOARD 
Constitution and duties. Pursuant to the 
decision of the International Joint Commission 
and in response to its March 6, 1975 Interim 
Report on the Regulation of the Richelieu 
River and Lake Champlain, the Board 
was established by the Commission on May 5, 
1975. This new study Board replaced the Engineering 
Board which was disbanded by the 
Commission in April 1975. The new Board was 
directed to undertake, through appropriate 
agencies in Canada and the United States, the 
necessary investigations and follow-up studies 
and to advise the Commission on all matters 
which it must consider in completing its 
report to Government under the March 29, 
1973 Reference from the Governments. The 
Commission issued a directive to the Board on 
June 11, 1975 requesting, in the light of the 
Commission's Interim Report and the Goverments' 
responses thereto, to provide information 
as to: (a) the beneficial and adverse effects 
on the environment in the United States 
and Canada of regulating the water levels of 
Lake Champlain; (b) net economic benefits, 
including flood control benefits, to each country, 
of regulating the water levels of Lake 
Champlain; compatible methodology and criteria 
are to be applied in both countries; (c) 
the desirable criteria for regulation of Lake 
Champlain by means of works which may be 
undetaken in the St. Jean Rapids, bearing in 
mind impact on agriculture, water supply and 
sanitation, recreation, navigation, environmental 
factors, including fish and wildlife, 
reclamation and preservation of wetlands and 
flood control and such other purposes as may 
warrant consideration in the judgment of the 
Board; (d) the operational plan or plans of 
regulation developed utilizing the results of 
the environmental and net benefit studies 
which best meet the criteria mentioned above; 
(e) the specific benefits and adverse effects 
which would accrue to each country from implementation 
of the plan, or plans, of regulation. 
The Commission also directed the Board 
to prepare an outline of a program of investigations 
and studies, with cost and time estimates; 
to carry out the program as approved 
by the Commission, suggesting modifications 
if necessary and to submit a final report and 
recommendations by July 1, 1977. The directive 
also instructed the Board to review and, 
as far as possible, utilize the final report of 
the Engineering Board and other previously 
acquired information. 
Members for the Board for fiscal year. The 
United States members were: Mr. H.N. Larsen 
(Chairman), Deputy Associate Director of 
Fisheries, U.S. Fish and Wildlife Service Department 
of the Interior; Mr. T.P. Curran, 
Director of Environmental Analysis, New 
York State Department of Environmental 
Conservation ; Mr. T.K. Klock, Senior Staff 
Associate, New England River Basins Commission; 
Mr. A.W. Albert, Senior Staff Engineer, 
Vermont Agency of Environmental Conservation; 
and Colonel T.C. Hunter, Jr., District 
Engineer, U. S. Army Engineer District, 
New York. The Canadian members were Mr. 
H.B. Rosenberg (Chairman), Chief, Socio-Economic 
Division, Water Planning and Management 
Branch, Environment Canada; Mr. J.E. 
48-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
Bryant, Director Eastern Region Canadian 
Wildlife Service, Environment Canada; Mr. B. 
Harvey, Director, Hydraulic Development 
Service, Quebec Department of Natural Resources; 
Mr. R. Baillargeon, District Director 
Agricultural Hydraulics; and Mr. Y.L. Page, 
Directeur de la Connaissance de la Qualitie du 
Milieu, Quebec Services de Protection de 
1' Environment. 
Operation during the fiscal year. Topographic 
maps of Lake Champlain are under 
preparation and an ecological study is underway. 
The Board is preparing a Plan of 
Study. 
2F. INTERNATIONAL ST. LAWRENCE 
RIVER BOARD OF CONTROL 
Constitution and duties. The Board was 
established December 16, 1953 pursuant to 
the provisions of the Order of Approval dated 
October 29, 1952, of the International Joint 
Commission for the construction of certain 
works for the development of power in the 
International Rapids Section of the St. Lawrence 
River. The Commission instructed the 
Board to perform the duties assigned to it by 
the Order. These responsibilities include the 
following items: (a) The Board is to determine 
the gages, measurements and other services 
to be provided by the Power Authority of the 
State of New York and the Hydro-Electric 
Power Commission of Ontario in order to furnish 
accurate records relating to water levels 
and the discharge of water through the works 
and the regulation of the flow of water 
through the International Rapids Section; (b) 
Upon completion of the works the duties of 
the Board shall be to insure that the provisions 
of the Orders relating to water levels 
and regulation of the discharge of water from 
Lake Ontario and the flow of water through 
the International Rapids Section are complied 
with, and that Ontario-Hydro and PASNY 
shall duly observe any direction given them 
by the Board for the purpose of ensuring 
such compliance. The Board shall report to 
the Commission at such times as the Commission 
may determine; (c) In addition to the reports 
to be made to the Commission in accordance 
with the terms of the Order, the Board 
was requested to report semi-annually to the 
Commission and to keep the Commission currently 
informed with regard to the discharge 
of water from Lake Ontario and the flow 
through the International Rapids Section of 
the St. Lawrence River; and (d) At a meeting 
of the Commission in Toronto on January 25, 
1957, further studies of the regulation of 
Lake Ontario, beyond studies accomplished by 
the International Lake Ontario Board of Engineers, 
were assigned to the Board of Control. 
Members of the Board for fiscal year. The 
Canadian members were: Mr. R.H. Smith, 
Chief, Waterways Development Division, Ministry 
of Transport, Chairman; Mr. J.B. Bryce, 
Hydraulic Engineer, Hydro-Electric Power 
Commission of Ontario; Mr. Y. DeGuise, 
Commission, Hydro-Electric Power Commission 
of Quebec; and Mr. R.H. Clark, Senior 
Engineering Adviser to the Director, Inland 
Waters Directorate, Department of the Environment. 
The United States members were: 
The Division Engineer, U.S. Army Engineer 
Division, North Central, Chairman; Mr. D. 
Brown, Head, Section of Inspections, Federal 
Power Commission; Mr. R.D. Conner, Resident 
Manager, Power Authority of the State of 
New York; and Mr. W.H. Kennedy, Resident 
Manager, St. Lawrence Seaway Development 
Corporation. Brigadier General W. O. Bachus 
was the Division Engineer during the year. 
Operations during fiscal year. The Board 
met in Toronto, Ontario, on August 15, 1974; 
in Ottawa, Ontario, on October 1, 1974; in 
Montreal, Quebec, on December 6, 1974; in 
Chicago, Illinois, on March 21, 1975; and, in 
Alexandria, Virginia, on April 8, 1975. 
The Board has continued to regulate the 
Lake Ontario outflow in accordance with the 
Commission's directive of April 8, 1960, that, 
commencing on April 20, 1960, the St. Lawrence 
project be so operated as to conform to 
the criteria and other requirements of the 
Orders dated October 29, 1952 and July 2, 
1956. Regulation Plan 1958-D, the plan currently 
approved by the Commission, with its 
discretionary authority and with continuing 
guidance from the Commission and advice 
from the interests involved, is used by the 
Board in consulting with the Power Entities 
and other concerned interests. 
The Commission by letter dated October 11, 
1974, informed the Board that the six ice 
booms in the Prescott-Gallop reach of the St. 
Lawrence River would henceforth be included 
as works approved by the Commission's Order 
of October 29, 1952. The Board at the request 
of the Commission reviewed a "Statement on 
Procedures for Installing and Removing Ice 
Booms" prepared by the Power Entities. The 
Board concurred in these procedures by letter 
dated December 11, 1974 and noted it had 
assumed the duty of overseeing the installation 
and rmeoval of the ice booms. 
The Board maintained contact with the project 
operation through its Regulation Representatives 
and provided information on levels 
48-6

MISCELLANEOUS CIVIL WORKS 
and outflows. The Board's Operations Advisory 
Group, which represents navigation and 
power interests, and provides advice on operational 
aspects of regulation, continued to 
provide weekly summaries of its activities to 
the Board and to the Regulation Representatives. 
The Board, and its Working Committee, 
continually reviewed the 1974-75 high water 
situation on Lake Ontario and in the St. 
Lawrence River. 
In addition to its nomal functions the 
Board completed studies and a report of the 
unprecedented high supplies of 1972-74 to 
determine possible improvements to the regulation 
procedures for Lake Ontario within the 
existing Orders of Approval. The report indicated 
that none of the modifications studied 
would provide significant improvements over 
the results of the current Plan 1958-D with 
discretionary authority. The Commission was 
informed of these results. 
The issuance of monthly public information 
bulletins, initiated by the Board in October 
1973, has continued. 
1974 was the first year since 1966 in which 
the precipitation over the entire Great Lakes 
basin has been below the long-term (1900- 
1973) average. Due to the large volumes and 
relatively small outflow capacities, the levels 
of Lakes Michigan, Huron and Erie, although 
declining, have remained substantially above 
average during the fiscal year. Thus, supplies 
to Lake Ontario remained substantially above 
average. 
The Power Entities continued their operation 
and maintenance of the gages required 
for recording river levels and determining 
flows. This program is monitored by the St. 
Lawrence Committee on River Gaging. The 
Committee's calendar year 1974 report included 
tabulations of daily mean outflows from 
Lake St. Lawrence, as well as the distribution 
of flows through the various structures, and 
the daily mean water levels recorded at the 13 
river gages under the supervision of the 
Committee. Also included were the recorded 
water levels of the Canadian Hydrographic 
Service gaging stations at Cornwall and 
Summerstown, Ontario, and the NOAA, Lake 
Survey Center, gaging station at Ogdensburg, 
New York. 
The Regulation Representatives reported 
that for the first time since August 1972 the 
storage available to Lake Ontario to June 30, 
1975 was less than the maximum calculated 
during the period (1900-1968). This indicator 
has been regularly used by the Board since 
1964 when considering the application of Criterion 
(k). The Board reviewed this information 
in March and concluded at that time that 
operations should continue under Criterion 
(k). Supply conditions continued to improve 
and the Board notified the IJC on June 9, 1975 
that Criterion (k) no longer applied and that 
the discretionary deviations accumulated 
from November 3, 1972 through May 1975 are 
cancelled. 
From the beginning of the fiscal year 
through the first week of August, the level of 
Lake Ontario was above 246.77 feet. The lake 
level remained above the long-term monthly 
mean through September. During the remainder 
of the navigation season the Board continued 
to approve, whenever feasible, flows 
greater than those specified by Plan 1958-D 
with due regard for downstream riparian interests 
and the maintenance of the minimum 
water surface levels prescribed for navigation 
in the International Rapids Section. As a 
result Lake Ontario receded on 16 November 
to 243.91 feet-its minimum elevation in 1974 
about 31/2 inches below the recorded long-term 
(1860-1973) mean for November-and marked 
the first occasion since January 1972 that the 
elevation of the lake was below elevation 
244.0 feet. During December and early January 
1975, the Board was able to authorize 
discharges well in excess of Plan 1958-D 
flows. After 15 January, the Board continued 
to release as much water from Lake Ontario 
as possible, consistent with the need to form 
and maintain a stable ice cover. The ice cover 
dissipated in early March. The Power Entities' 
1974 annual application to conduct test 
peaking and ponding operations during the 
navigation season, that were the same as 
requested in the past, were not fully agreed to 
by the St. Lawrence Seaway Development 
Corporation. The Seaway Corporation would 
not accept the range of 30,000 cfs above and 
below the daily mean flow or rate of change in 
flows of 20,000 cfs per hour. They felt that 
peaking intensifies the adverse effects of 
cross currents which normally exist in the 
South Cornwall Channel. On November 7, 
1974 after review and study, the Board recommended 
an interim range of 20,000 cfs 
above and below the daily mean flow, with a 
rate of change not to exceed 10,000 cfs per 
hour. This revised condition was acceptable 
to all concerned for the remainder of the 1974 
navigation season and was approved by the 
Commission in its letter of November 14, 
1974. 
The Board received the Power Entities application 
for test peaking by letter dated 
48-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
March 11, 1975. Again, the Power Entities 
asked for the+30,000 cfs range and 20,000 cfs 
per hour rate of change during the navigation 
season. And again, the Seaway Corporation 
did not agree, and requested the same 
terms for peaking during the 1975 navigation 
season as agreed to in 1974. The 1975 peaking 
request was approved by the IJC in its letter 
of June 19, 1975. 
The official closing date for commercial navigation 
in the Montreal-Lake Ontario reach 
was December 17, 1974. The last commercial 
vessel passed upbound through Iroquois Lock 
on December 19. Traffic in the upper section 
of the river continued until January 1, 1975 
when the last vessel passed through the Ogdensburg-
Prescott ice boom to winter berth at 
Prescott. Due to the unseasonably mild 
weather, all of the above transits were made 
under open water conditions. From mid-December 
to mid-January, high Lake Ontario 
outflows, ranging from 270,000 to 290,000 cfs, 
were authorized by the Board. These high 
outflows were due to both the lack of an ice 
cover on Lake St. Francis and Lake St. Lawrence 
and the Board's decision to continue to 
release the maximum discharge possible from 
Lake Ontario, consistent with downstream 
conditions. 
Lake Ontario outflow was reduced from 
290,000 cfs beginning on January 15 and 
reached 230,000 cfs on January 18 to assist 
the ice formation in the Soulanges Section of 
the River. This reduction was accomplished 
progressively at a rate of 10,000 cfs every 12 
hours. On December 23, the main Galop ice 
boom was closed following the last commercial 
ship transit and the Ogdensburg-Prescott 
boom opening was narrowed on this date from 
2,000 feet to 1,200 feet to facilitate final closure. 
On that day the water temperature in 
the forebay of the Moses-Saunders Powerdam 
was 37�F, which is the highest recorded on 
this date since 1960. On January 3, the Ogdensburg-
Prescott boom was closed. By January 
20, formation of an ice cover in the International 
Rapids Section had begun. On January 
27, it was observed that strong winds 
during the weekend had broken one section of 
the Ogdensburg-Prescott boom and repairs to 
the boom were completed the next day. By 
February 1, the head of the ice cover had 
progressed to within 1/2 miles of Iroquois 
Dam and the gates were dipped to initiate an 
ice cover upstream from the structure. Flows 
were maintained at 230,000 cfs from January 
18 until February 8 when the cover was considered 
sufficiently complete and stable to increase 
to 250,000 cfs and, on the following 
day, the gates at Iroquois Dam were raised. 
On February 15, the flow was increased further 
to 260,000 cfs. In early March the ice 
cover dissipated rapidly and the opening and 
removal of the booms started on 10 March. 
Removal was completed on March 18, 1975. 
During this winter a testing program on 
the St. Lawrence River developed by the U.S. 
Winter Navigation Board began. An experimental 
ice boom at Copeland's Cut was installed 
after the close of navigation. Following 
the formation of an ice cover in the test 
area, a series of instrumented tests were 
made both with and without vessel transit. 
The tests ended on March 7 and the test boom 
and its attachments were removed by March 
15.
The fiscal year began with flows in excess of 
the capacity of the Saunders-Moses power 
plants, so water was spilled over Long Sault 
Dam for 54 days during the period July 1, 
1974 through August 23, 1974. The total volume 
of water passed through the Dam was 
equivalent to about 0.37 feet of storage on 
Lake Ontario. The largest amount of water 
spilled during this period was about 19,000 
cfs in August. No further spillage was made 
during the year. 
2G. INTERNATIONAL NIAGARA 
BOARD OF CONTROL 
Constitution and duties. The Board was 
established August 19, 1953 by the International 
Joint Commission to supervise the construction, 
maintenance and operation of the 
Niagara Remedial Works, recommended by 
the Commission in its 1953 report on the 
"Preservation and Enhancement of Niagara 
Falls." 
Members of the Board for fiscal year. The 
United States members were the Division 
Engineer, U. S. Army Engineer Division, 
North Central, Chairman; and Mr. D. Brown, 
Head, Section of Inspections, Federal Power 
Commission. Brigadier General W. O. Bachus 
was Division Engineer during the year. The 
Canadian members were Mr. D. M. Foulds, 
Regional Head, Water Planning and Management, 
Department of the Environment, Chairman; 
and Mr. C.K. Hurst, Chief Engineer, 
Department of Public Works. 
Operations during fiscal year. The diversions 
to the DeCew Falls Plants of Ontario 
Hydro by way of the Welland Canal were 
temporarily reduced for about two weeks 
starting on September 1, 1974. This was done 
48-8

MISCELLANEOUS CIVIL WORKS 
to reduce velocities during operations to clear 
the canal after an ore carrier collided with 
and demolished the vertical lift bridge at Port 
Robinson, Ontario, on August 25, 1974. From 
January 8, 1975 to March 7, 1975 the DeCew 
Falls Plants used an additional diversion of 
about 350 cfs of water to compensate for the 
reduced diversions during September 1974. 
The Power Entities complied with the 
Board's directive of February 27, 1973 in the 
operation of the Chippawa-Grass Island Pool 
during this fiscal year. The accumulated deviation 
for March 1973 through February 
1975 was 2.3 foot-months above the long-term 
mean level (established limit is 3.0 footmonths) 
in spite of continuing record high 
flows. Tolerances were suspended on 11 days 
during the fiscal year because of Niagara 
River flows in excess of 270,000 cfs for four 
or more consecutive hours. The Board waived 
tolerances from November 12 to November 14, 
1974 and from April 21 to April 25, 1975 during 
the discharge measuring programs. They 
were also suspended four days in February 
and five days in March because of ice conditions. 
The Board in response to an April 1, 1974 
request from the International Great Lakes 
Levels Board, requested its Working Committee 
to outline study which would endeavor to 
answer the following questions: 1. Can the 
outflow from Lake Erie be increased or decreased 
by manipulating the levels of the 
Chippawa-Grass Island Pool? and, 2. if so, 
can the technique be used as a means to partially 
regulate the outflows of Lake Erie? 
The Board's Working Committee proposed a 
field measurement program in which the Lake 
Erie outflow was to be measured under a nearconstant 
Lake Erie level and different levels 
of the Chippawa-Grass Island Pool during 
two periods, the first during May 1974, and 
the second in November 1974. The Working 
Committee reported on the test program by 
letter of March 27, 1975. Due to inclement 
weather, unfavorable lake conditions and the 
malfunction of the Leading-Edge Flowmeter, 
the November measurement program was 
cancelled. The Working Committee found that 
lowering the Pool level from 562.0 to 560.0 
feet increased the outflow from 3,000-6,000 cfs 
when Lake Erie level elevation was 573.0 feet. 
However, it was noted that the present procedure 
for operating the Pool to the 561.0 foot 
target level would, at times of high levels on 
Lake Erie, provide a good part of the increase 
in outflow. It was also noted that the diversion 
control structure was not designed, nor 
constructed, to regulate the level of Lake 
Erie. It was built only to control the river 
flow as required by the Treaty. The Board 
forwarded the letter report to the IJC on 
April 11, 1975 stating that regulation of the 
Chippawa-Grass Island Pool in a manner 
appreciably different from present operating 
procedure cannot be used as a practical 
means to partially regulate the level of Lake 
Erie. The Board recommended that no further 
field measurements be done. 
During tourist hours of the fiscal year, 
flow over the Falls was only slightly in excess 
of Treaty requirements. During non-tourist 
hours, when the minimum allowable flow over 
the Falls is 50,000 cfs, this excess averaged 
10,000 cfs. These excess flows were caused by 
high Lake Erie discharges, limited diversion 
capability of the power plants and the requirement 
to meet the set Pool tolerances. 
A cableway, located immediately upstream 
of the Robert Moses Power Plant tailrace, 
provides a means for direct measurement of 
the total flow past the Ashland Avenue Gage 
and serves as a means to determine the reliability 
of the existing Ashland Avenue rating 
curve. Measurements were made during 1973 
and 1974 and also between April 21 and 25, 
1975. 
By letter of October 1, 1974, the Federal 
Power Commission (FPC) notified the Power 
Authority of the State of New York (PASNY) 
that it had approved the Board's request for 
the relocation of the American Falls Channel 
gage. PASNY is providing the necessary 
funds to the Buffalo District Engineer for the 
relocation as authorized by Article 6 of the 
FPC license for the project. The new site is 
approximately 400 feet upstream of the existing 
gage. Buffalo District plans to award a 
contract to rebuild the gage during the 1975 
construction season. 
Above normal supplies in recent years have 
continued to produce high Lake Erie levels 
and Niagara River flows. The Niagara River 
1974 annual flow of 242,000 cfs was considerably 
greater than the long-term mean of 
202,000 cfs. The annual flow was the second 
highest of record, exceeded only by the 1973 
annual flow of 247,000 cfs. 
The installation of the Lake Erie-Niagara 
River Ice Boom started on 11 December and 
was completed on December 30. Eastern Lake 
Erie's first ice cover formation was abnormally 
later this winter because of the above normal 
air temperatures. The first significant ice 
cover behind the boom was observed on 23 
January but it was dissipated by a storm. The 
boom remained practically ice free from Janu- 
48-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
ary 26 until Feburary 8. There were severe 
reductions in the diversions to the power 
plants on February 14 after strong southwest 
winds on the 13th caused a large ice run in 
the Niagara River. PASNY diversions were 
reduced to 26,000 cfs, one quarter of its capacity. 
During the same period, flow over the 
Falls was more than double the required minimum 
Treaty flow. Another heavy ice run began 
with winds from the southwest gusting 
up to 60 mph. The area and almost all of the 
upper Niagara River were ice covered causing 
the Power Entities to reduced their diversions 
by more than 50 percent. Compacted ice, as 
much as 17 feet thick, grounded in front of 
the Control Structure and the other outlets of 
the Pool and caused the Pool to raise to an 
extremely high level. The result was floods in 
the Cayuga Island and Grand Island areas in 
New York, and in Fort Erie and Black Creek 
areas in Ontario. 
An approximate power loss of 125,000 
mega-watt hours resulted over the period 
February 26-March 5. Normal power diversions 
were resumed by mid-day on March 5. 
The power losses incurred because of ice 
problems during this last winter totaled 
165,000 mega-watt hours. This was the greatest 
energy loss since the ice boom was installed. 
Aerial surveillance on March 5 showed ice 
cover over at least 200 square miles, as much 
as 1,000 square miles on March 11, 300 square 
miles on March 18, and only 30 square miles 
of ice coverage on March 21. The Board recommended 
to the Commission that the Ice 
Boom removal start on March 24, which was 
approved, and it was completely removed by 
March 28. 
As recommended in the Lake Erie-Niagara 
River Ice Boom Study, dated January 1974, 
the Board and its Working Committee developed 
a program for the collection of additional 
climatic, ice and hydrologic data needed to 
further develop and refine the simplified ice 
dissipation simulation model. The data collection 
program covers three categories: 
a. Ice Cover Data Collection-Side Looking 
Airborne Radar flights over Lake Erie by 
NASA obtained the extent of the ice cover 
and Short Pulse Radar measurements to indicate 
a maximum ice thickness. Also, the actual 
measuring of ice thickness in the eastern 
end of Lake Erie to verify flight data. 
b. Meteorological Data Collection-In view 
of the inadequacy of existing meteorological 
data at the boom site, a new meterological 
station has been established to record incoming 
shortwave radiation, air temperature, 
relative humidity and wind velocity and direction. 
The new station became operational during 
January 1975 and is located at the U. S. 
Coast Guard Station at Buffalo, New York. 
c. Ice Observation-A program of visual 
and photographic ice observations from the 
Peace Bridge was carried out to determine the 
amount of ice leaving Lake Erie by way of 
the Niagara River during large ice runs. 
The Power Entities, by letters dated January 
10 and 29, 1975, requested an indefinite 
extension to the authority to operate and 
maintain the ice boom in conformance with 
the terms and conditions of the Commission's 
Order. The Commission held a public hearing 
to hear and consider public views on the extension 
of the authority and the timing for 
opening of the boom this spring. On April 11, 
1975, the Commission approved the request 
which will expire May 15, 1980 and reserving 
the authority to amend the Order at any time. 
In January 1975, the Board reported to the 
Commission the results of its hydraulic study 
regarding the "Effect of the Land Fill Operations 
at Fort Erie on Lake-Erie-Niagara River 
Water Levels." This fill was placed in the 
waterway without approval. The Board further 
reported that since this fill does not affect 
navigation, there appears to be no legal 
recourse, at least at the Candian Federal level 
of government, to force the removal of an 
existing fill. 
2H. INTERNATIONAL NIAGARA 
COMMITTEE 
Constitution and duties. A Treaty between 
Canada and the United States concerning the 
uses of waters of the Niagara River was 
signed on February 27, 1950. By its provisions, 
limitations on the diversions of Niagara 
River water for power in accordance with 
Article V of the Treaty of 1909 are terminated 
as well as temporary international agreements 
for the allocating of waters of the Niagara 
River for power purposes are replaced. 
In accordance with the provisions of Article 
VII of the 1950 Treaty, a representative was 
appointed by each Government who, acting 
jointly, shall ascertain and shall record the 
same and shall also record the amounts of 
water used for power diversions. By an exchange 
of notes during January 1955, the two 
Governments officially designated the representatives 
appointed in conformance with 
Article VII of the 1950 Treaty as the International 
Niagara Committee. With regard to 
flows and diversions, the 1950 Treaty became 
48-10

MISCELLANEOUS CIVIL WORKS 
effective October 10, 1950. Under Article III 
the Treaty, all waters in excess of certain 
minimum flows which are required to maintain 
the scenic spectacle at Niagara Falls are 
available for diversion for power and, with 
the exception of the 5,000 cubic feet per second 
authorized October 1940 for the Long 
Lac-Ogoki diversions by Canada, and are to 
be allocated equally between both countries. 
Minimum flows over the Falls shall not be less 
than 100,000 cubic feet per second between 8 
am and 10 pm EST from April 1 to September 
15, and 8 am to 8 pm from September 16 to 
October 31. At all other times the flow over 
the Falls shall not be less than 50,000 cubic 
feet per second. A brief history regarding the 
measurement and supervision of diversion of 
waters from the Niagara River prior to the 
1950 Treaty is included in the Committee's 
1955, First, Annual Report. In 1973, the two 
Governments agreed to use Eastern Daylight 
Saving Time (EDST) when officially in effect 
in either country at Niagara Falls, rather 
than Eastern Standard Time (EST) as stipulated 
in the 1950 Treaty. 
Members of the Committee for fiscal year. 
The Canadian representative was Mr. D. M. 
Foulds, Director, Ontario Region, Inland Waters 
Directorate, Department of the Environment, 
and the U. S. representative, was the 
Division Engineer, U. S. Army Engineer Division, 
North Central. Brigadier General W. O. 
Bachus was Division Engineer during the 
year. 
Operations during fiscal year. The Committee 
received daily reports of operation of the 
hydro-electric generating stations on the 
Niagara River which diverted water from the 
river above the Falls, and the DeCew Falls 
Plants, which diverts water from Lake Erie 
through the Welland Canal. These reports, 
submitted in the form prescribed by the 
Committee and showing for each hour the 
quantities of water diverted by each plant, 
were checked by the Committee. Monthly and 
annual summaries were prepared. During the 
year there was one violation of Treaty flow 
requirement over Niagara Falls which occurred 
on April 13, 1975 for two hours. The 
violation was deliberate in order to aid the 
Niagara Parks Commission Police in the rescue 
of a man and his daughter who were fishing 
and became stranded on a rock in the lower 
river at the Glen area in Ontario. They 
became stranded after the Falls flow was 
changed from 50,000 efs to 100,000 efs at 8:00 
a.m. 
Bi-weekly and intermittent inspections of 
all plants were made by representatives of 
the Committee, jointly and individually, to 
obtain independent watt-meter readings of 
power output and to assure compliance with 
all provisions of the Treaty. Records of water 
levels in the Niagara River above and below 
the Falls were obtained by means of self-registering 
gages. However, the American Falls 
Channel gage used for the purpose of determining 
flows over the American Falls has 
been providing inconsistent data since the 
dewatering of the Falls in 1969. Efforts to 
establish a reliable stage-discharge relationship 
reflecting current conditions have not 
been successful. The International Niagara 
Board of Control has investigated the gage 
and the data it produces and determined that 
the gage inlet pipe is located in an area of 
turbulent stream flow. A decision has been 
made to relocate the American Falls gage 
upstream of the existing location. The Federal 
Power Commission in an order dated October 
1, 1974, directed that the Power Authority 
of the State of New York provide funds for 
the relocation of the American Falls gage. 
The Buffalo District Engineer prepared detailed 
plans and specifications for the new 
gage installation. Plans are to construct the 
new gage during the 1975 construction season. 
Until a rating is established for the new 
gage, the monthly report, columns 12 and 
13-Horseshoe and American Falls flows, are 
labelled "Diversion of Flow Subject to Re- 
Rating of the American Falls Gage". 
The diversion to the DeCew Falls Plants of 
Ontario Hydro by way of the Welland Canal 
were temporarily reduced for about two 
weeks starting on September 1, 1974. This 
was done to reduce velocities during operations 
to clear the canal after an ore carrier 
collided with and demolished the vertical lift 
bridge at Port Robinson, Ontario, on August 
25, 1974. From January 8, 1975 to March 7, 
1975 the DeCew Falls Plants used an additional 
diversion of about 350 cfs of water to 
compensate for the reduced diversions during 
September 1974. 
21. AMERICAN FALLS INTERNATIONAL 
BOARD 
Constitution and duties. In a Reference dated 
March 31, 1967, the Governments of the United 
States and Canada, pursuant to Article IV 
Of the Boundary Waters Treaty of 1909, requested 
the International Joint Commission 
to investigate and report upon measures necessary 
to preserve and enhance the beauty of 
the American Falls at Niagara. The Board 
was established July 24, 1967, by the Commis- 
48-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
sion to carry out the investigations required 
under the Reference. 
Members of the Board for fiscal year. The 
U. S. members of the Board were the Division 
Engineer, U. S. Army Engineer Division, 
North Central, Chairman, and Mr. G. Eckbo, 
Chairman, Department of Landscape and 
Architecture, University of California at 
Berkley. Brigadier General W. O. Bachus was 
North Central Division Engineer during the 
year.Canadianmembers were Mr. N. H. James, 
Director, Water Planning and Management 
Branch, Department of the Environment, 
Chairman, and Mr. H. S. M. Carver, Consultant, 
Central Mortgage and Housing Corporation, 
Ottawa, (Retired). 
Operations during fiscal year. The U. S. 
Army Corps of Engineers received study completion 
funds of $20,000 for the fiscal year. 
Departments of the Canadian Government 
funded operations of their personnel who are 
involved in the activities of the Board and its 
Committee. The expense of the representatives 
of the two Park Commissions have been 
borne by the respective Park Commission. 
The Board submitted its Final Report to 
the IJC by letter dated June 30, 1974. The 
seven technical appendices to the report were 
completed and transmitted to the IJC by December 
1974. The Board concluded that the 
process of erosion of the American Falls 
should not be interrupted and that talus 
should not be removed at this time. However, 
improved safety plans to protect the viewing 
public were outlined. The most desirable plan 
for improved safety is as follows: 
(1) The railing at upper Prospect Point, 
Goat Island, and Terrapin Point would be 
reset. This would reduce the hazard in the 
upper areas from small and some moderate 
sized rock failures. 
(2) An expanded warning system would be 
installed at all three flank areas. This would 
provide a significant degree of safety from 
major and moderate sized rock failures. 
(3) Surface stabilization would be performed 
at Prospect Point and Goat Island and 
alterations to the footpaths would be made in 
the lower viewing areas at Prospect Point 
and Goat Island. 
(4) The new railing alignment would allow 
close-up viewing at Prospect Point and Goat 
Island but not a Terrapin Point. 
The Board's recommended plan for improved 
safety would require one year for construction 
and an estimated cost of $2,800,000. 
The total cost would be to the United States. 
In preparation for the IJC Public Hearing 
on the Report, the Board prepared a brochure 
which summarized the conclusions of the report. 
A total of 10,000 copies were printed 
and distributed in the United States and Canada 
to the news media and interested individuals. 
On March 4, 1975 the IJC held a public 
hearing in Niagara Falls, New York, on the 
Board's Report. Only a small number of the 
attendees testified at this hearing. In general, 
there was no opposition to the Board's proposals 
and the findings seemed to enjoy solid 
public support. This Board has completed all 
of its assignments. The IJC is expected to 
complete its report to the Governments of 
Canada and United States in the Fall of 1975. 
2J. INTERNATIONAL GREAT LAKES 
LEVELS BOARD 
Constitution and duties. The Governments 
of Canada and the United States, by Reference 
dated October 7, 1964, requested the International 
Joint Commission to determine 
whether measures within the Great Lakes 
Basin can be taken in the public interest to 
regulate further the levels of the Great Lakes 
or any of them and their connecting waters so 
as to reduce the extremes of stages which 
have been experienced, and for the beneficial 
effects in these waters. 
At a meeting on December 2, 1964 the Commission 
established the Board to undertake 
the necessary investigations and studies, and 
to advise the Commission on all matters 
which it must consider in making a report or 
reports to the Governments under the Reference. 
At the first meeting of the Board on 
January 6, 1965, a Working Committee was 
selected. The Working Committee met on July 
7, 1965 and set up four Subcommittees to investigate 
and report on separate areas of 
study involved: Shore Property, Navigation, 
Power, and Regulation. A Subcommittee on 
Regulatory Works was subsequently established 
by the Working Committee in September 
1967 and a Reports Subcommittee in June 
1968. 
Members of the Board for fiscal year. United 
States members of the Board were the Diyision 
Engineer, U. S. Army, North Central 
Division, Chairman (Brigadier General W. O. 
Bachus was Division Engineer during the 
year);:Mr. M. Abelson, Special Assistant to the 
Secretary, Department of the Interior; until 
March 21, 1975 and Ms. Madonna F. McGrath 
thereafter; and Mr. B. T. Jose, (retired) formally 
Assistant Administrator, St. Lawrence 
48-12

MISCELLANEOUS CIVIL WORKS 
Seaway Development Corporation, Department 
of Transportation. Canadian members 
of the Board were Mr. C. K. Hurst, Chief Engineer, 
Department of Public Works, Chairman, 
Mr. R. H. Smith, Chief, Waterways Development 
Division, Ministry of Transport; 
and Mr. N. H. James, Director, Water Planning 
and Management Branch, Department of 
the Environment. The Working Committee 
consists of five members representing the 
United States and three members representing 
Canada. U. S. members of the Working 
Committee were Dr. L. H. Blakey, Chief Engineering 
Division, U. S. Army Engineer Division, 
North Central, Chairman, Mr. M. Abelson 
(resigned March 21, 1975); Mr. F. A. 
Blust, Lake Survey Center, NOAA, Department 
of Commerce; Mr. A. M. Monaco, Regional 
Engineer, New York Regional Office, Federal 
Power Commission; and Mr. D. N. Robb, St. 
Lawrence Seaway Development Corporation, 
Department of Transportation. Canadian 
members of the Working Committee were Mr. 
R. H. Clark, Senior Engineering Adviser to 
the Director, Inland Waters Directorate, Department 
of Environment, Chairman, Mr. D. 
W. Quinlan, Program Management Evaluation, 
Department of Public Works; and Mr. C. 
J. R. Lawrie, Waterways Development Division, 
Ministry of Transport. The six subcommittees 
have been formed with membership 
drawn from agencies participating in the 
study and represented on the Board and 
Working Committee. 
Operations during fiscal year. During the 
year the activities of the Board, its Working 
Committee and Subcommittees focused on 
completing the printing and distribution of 
the seven Appendices to the Report and participation 
in the IJC Public Hearings on the 
Board's final report. 
The seven appendices were printed and distribution 
made by October 1974. The U. S. 
Section of the Board assisted the U. S. Section 
of the Commission in preparing distribution 
lists and in mailing copies of the Board's 
Report and Appendices in the United States. 
The Corps of Engineers, upon request from 
the Chairman, U. S. Section, International 
Joint Commission, undertook additional Lake 
Erie regulation studies and prepared a report 
entitled "Regulation Plan SEO-17P." This 
Plan is a refinement of the Board's Plan SEO- 
42P. The SEO-17P report was provided to the 
IJC in early October 1974. It was publicly released 
by the Corps in November 1974. 
Members of the Board, Committee and Subcommittees 
participated in thirteen IJC Public 
Hearings on the Board's Report. The hearings 
were held throughout the Great Lakes 
basin during the period October 21-December 
6, 1974. In the United States they took 
place in Detroit and Muskegon, Michigan; 
Green Bay and Milwaukee, Wisconsin; Chicago, 
Illinois; Duluth, Minnesota, Cleveland, 
Ohio; and, Rochester, New York. All the work 
assigned to the Board has been completed. 
Technical representatives of the Board 
have held several meetings with representatives 
of the 8 Great Lakes States to discuss 
the Board's Report and answer questions and 
concerns raised. The computer models and 
basic data used in the design of the Board's 
regulation plans have been made available to 
several of the States. 
The Corps of Engineers initiated a damage 
survey in cooperation with the States to assess 
the damages incurred during the July 
1972--July 1974 high water period on all the 
Great Lakes. A total of eleven counties located 
on four lakes were completed during the 
fiscal year. This new data will be useful for 
updating the stage-damage curves developed 
by the Board. 
2K. COORDINATING COMMITTEE ON 
GREAT LAKES BASIC HYDRAULIC 
AND HYDROLOGIC DATA 
Constitution and duties. The Committee was 
formed on May 7, 1953, for the purpose of 
establishing a basis for development and acceptance 
by both countries (United States 
and Canada) of identical hydraulic and hydrologic 
data for the Great Lakes and their 
outflow channels. The Committee was established 
advisory to the agencies of the United 
States and Canada which are charged with 
the responsibility for collecting and compiling 
the Great Lakes hydraulic and hydrologic 
data. Three working subcommittees, designated 
the River Flow Subcommittee, the Vertical 
Control Subcommittee and the Lake Level 
Subcommittee, were formed to assist the Coordinating 
Committee in its work. Subsequently, 
the Physical Data Subcommittee was formed. 
The Vertical Control and Lake Level Subcommittees 
were combined into one subcommittee 
in 1969. These subcommittees have been conducting 
the required technical studies 
through collabroration of the appropriate 
agencies of the United States and Canada. 
Members of the Committe for fiscal year. 
The United States members were Mr. D. J. 
Leonard, Chief, Water Control Center, U. S. 
Army Engineer Division, North Central, 
Chairman; Mr. B. C. DeCooke, Assistant 
Chief, Engineering Division, U. S. Army Engi- 
48-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
neer District, Detroit; and Mr. F. A. Blust, 
Chief, Marine Mapping Division, U. S. Lake 
Survey Center, National Ocean Survey, 
NOAA, Department of Commerce. Members 
for Canada were Mr. D. F. Witherspoon, 
Great Lakes - St. Lawrence Study Office, 
Department of the Environment, Chairman, 
and Mr. R. H. Smith, Chief, Waterways Development 
Division, Ministry of Transport. 
Operations during fiscal year. The River 
Flow Subcommittee continued its study of 
coordinated St. Clair River and Detroit River 
flows. These flow data are expected to be 
available for publication in 1976. A program 
to recalibrate the Lake Superior control 
works was continued in June 1975 in coordination 
with the International Lake Superior 
Board of Control. 
The Vertical Control and Lake Level Subcommittee 
continued preparation of gage histories 
for the Upper Great Lakes and St. 
Marys, St. Clair and Detroit Rivers. Vertical 
(crustal and other) movement assessments for 
all Great Lakes gage sites are being determined 
and coordinated. The Subcommittee has 
completed a draft report on vertical movement 
in the Great Lakes area. Efforts are 
underway to coordinate a U. S. and Canadian 
forecast of Great Lakes water levels. This 
includes agreement on period of record values 
to be used in the reproduction of the hydrograph 
of levels. 
The Physical Data Subcommittee has completed 
essentially all its data coordination 
and preparation of the Physical Data Report. 
The Committee held two meetings during 
the year to review work of the Subcommittees 
and to finalize several data reports. 
2L. INTERNATIONAL GREAT LAKES 
STUDY GROUP 
Constitution and duties. The Study Group is 
an informal organization including representatives 
of Canadian and U. S. agencies 
and institutions engaged in basic and applied 
research, and engineering investigations related 
to the development and utilization of 
the Great Lakes water resources. The Group 
was formed October 1962 as the Lake Erie 
Study Group and was later renamed the International 
Great Lakes Study Group in recognition 
of the members interest in all the 
Great Lakes. Its primary purpose is to facilitate 
the exchange of information and to provide 
informal coordination among the various 
research activities relating to the Lakes. The 
Group provides a forum for assisting, coordinating 
and eliminating duplication. It also 
sponsors a data repository for the cataloging, 
storage and circulation of basic data. 
Members of the Group for fiscal year. The 
Steering Committee for the Study Group 
consists of up to six members from each country. 
During the year the United States Chairman 
was Mr. L. T. Crook, Planning Director, 
Great Lakes Basin Commission. Members 
were Dr. L. H. Blakey, Chief, Engineering 
Division, U. S. Army Corps of Engineers, 
North Central Division; Dr. D. C. Chandler, 
Director, Great Lakes Research Division, 
University of Michigan; Dr. A. P. Pinzak, 
Lake Survey Center, NOAA, Department of 
Commerce; Dr. R. Rummer, State University 
of New York at Buffalo; and Mr. L. A. Cook, 
Michigan Water Resources Commission. The 
Canadian members of the Group were Dr. A. 
D. Misener, Director, Institute for Environmental 
Studies, University of Toronto; Mr. T. 
L. Richards, Atmospheric Environment Service, 
Department of the Environment; Dr. A. R. 
LeFeuvre, Director General, Canada Centre 
for Inland Waters; Dr. A. M. McCombie, Ontario 
Department of Lands and Forests; and 
Mr. F. A. Voege, Assistant General Manager, 
Ontario Ministry of the Environment. 
Operations during the fiscal year. The 
Study Group has continued its coordination 
of research activities in connection with the 
International Field Year of the Great Lakes 
and the International Hydrologic Decade. 
Large Lake Research Programs have been 
coordinated in connection with activities of 
the Group related to the International Joint 
Commission's Great Lakes levels and water 
quality studies. The Group has continued, 
through informal discussions, its efforts to 
get most or all agencies concerned with the 
Great Lakes closer together and to coordinate 
their activities. During the year the Group 
held no formal meetings. Informal discussions 
of on-going U.S. and Canadian Great Lakes 
Research programs were held. 
2M. INTERNATIONAL LAKE SUPERIOR 
BOARD OF CONTROL 
Constitution and duties. The Board, established 
in pursuance of Orders issued by the 
International Joint Commission on May 26 
and 27, 1974, is charged with the supervision 
of the operations of all compensating works, 
all power canals and appurtenances at Sault 
Ste. Marie, Michigan and Ontario, with a view 
to so control the outflow from Lake Superior 
as to maintain its level as nearly as may be 
between elevations 600.5 and 602.0 feet above 
48-14

MISCELLANEOUS CIVIL WORKS 
mean water level at Father Point, Quebec (International 
Great Lakes Datum--1955) and to 
so control the outflow as to prevent the level 
of the St. Marys River below the locks from 
exceeding elevation 582.9 feet. The Board 
reports annually in March to the Commission. 
Members of the Board for fiscal year. Mr. 
D. M. Foulds, Director, Ontario Region, Inland 
Waters Directorate, Department of the 
Environment was the member for Canada. 
The Division Engineer, U. S. Army Engineer 
Division, North Central was the United 
States member. Brigadier General W. O. Bachus 
was Division Engineer during the year. 
Operations during fiscal year. The Board 
kept in touch during the year with conditions 
pertaining to the regulation of Lake Superior 
through representatives of Canada and the 
United States in the area and by means by 
regular and systematic reports of the water 
levels on Lake Superior, in the St. Marys 
River above and below the Sault Ste. Marie 
Locks, and on Lake Huron. Records of discharge 
at Sault Ste. Marie through the rapids, 
navigation canals and power plants were 
also systematically reported to the Board. 
Changes in the rate of outflow from Lake 
Superior are directed by the Board as indicated 
by the rule curve currently in use. During 
the past year the Board was directed by the 
Commission by letter, dated June 29, 1973, to 
regulate Lake Superior in such a way so as to 
provide all possible relief from critical high 
water levels on the downstream lakes without 
causing undue detriment to Lake Superior 
interests. For this purpose, the Board was 
requested to use as a guide, the Plan SO-901 
regulation objective as described in the "Interim 
Report on Lakes Superior and Ontario 
Regulation to the International Joint Commission 
by the International Great Lakes 
Levels Board," dated March 15, 1973. 
The Lake reached a seasonal monthly mean 
high level in September 1974 at 601.8 feet. In 
late September and early October, the Lake 
Superior level began its seasonal decline. The 
maximum 1974 level on Lakes Michigan-Huron 
was 581.0 feet in July. This Lake then 
began its seasonal decline. 
Using Regulation Plan SO-901 as a guide, 
and on the basis of the existing levels on 
Lakes Superior and Michigan-Huron, the 
Board continued to maintain the Lake Superior 
outflow at about 75,000 cfs from July to 
October 1974. Because of high supplies to the 
Lake, the Board increased the Lake Superior 
outflow in November to 85,000 cfs. Due to 
continuing high levels on Lake Superior, the 
outflow was further increased to average 
97,000 cfs during December. On December 23 
the initial winter outflow for the 1974-75 winter 
season was commenced at 85,000 cfs. The 
5-gates ohzn setting remained in effect 
throught the early winter when the setting 
was increased, on a test basis, to 6-gates open 
on 7 March and to 7-gates open on 17 March 
1975, as a result of the unfavorable conditions 
on Lake Superior. Two additional outflow 
increases were made on April 3 and April 
15, 1975, which resulted in an eleven gates 
open setting. The monthly outflows for March 
and April were 86,000 cfs and 92,000 cfs, respectively. 
Because of more favorable conditions 
on Lake Superior in the spring, and the 
concern of high water on Lakes Michigan- 
Huron and downstream as they reached their 
seasonal peak levels, the outflow was reduced 
to 7-gates open in mid-May. In mid-June three 
additional gates were closed. The outflows for 
May and June 1975 averaged 98,000 and 89,- 
000 cfs, respectively. 
By letters dated June 29 and July 7, 1973, 
the Commission requested the Board to undertake 
a feasibility study of remedial works or 
other measures to ensure that the crucial 
areas of the St. Marys Rapids are not dried 
under low flow releases. A study team comprised 
of representatives from federal, provincial 
and state agencies in both countries 
was subsequently appointed to carry out the 
one year study. The Board submitted its 
study report to the IJC in September 1974. 
The Board's conclusion was that certain remedial 
works are feasible and preferable over 
other measures and that a high-level containing 
dike or wall separating the fishery area 
from the rest of the rapids is the recommended 
plan. In October 1974 the IJC held a public 
hearing on the Board's report in Sault Ste. 
Marie, Ontario. 
Analysis of the Board's June 1974 hydraulic 
measurements to check the ratings of the 
gate settings of the Compensating Works was 
completed. It is considered that reasonable 
results were obtained for the settings of one 
gate open up to eight gates open, but that 
those for nine and ten gates open deviated 
appreciably from the rating curve. From 
evaluations of the method of measurement 
and the results obtained, it is concluded that 
this method does not yield the precision needed 
for a calibration program. A proposed new 
method would measure the combined flow 
through the Compensating Works and U. S. 
Power Canal at a section upstream of the 
Works. Test measurements were made in June 
1975. If an analysis shows satisfactory re- 
48-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
suits, measurements are expected to be made 
in the Fall to rate all gate openings from one 
to sixteen. 
The Board made its annual inspection of 
the Compensating Works on September 13, 
1974. No repair work was done on the Canadian 
portion of the structure during the fiscal 
year. Minor repairs of gate seals and to some 
of the concrete piers is required on the U. S. 
portion of the structure. Plans and specifications 
for these items have been prepared and 
approved by the Board. The gate seal repairs 
are expected to be completed during the 1975 
construction season. The concrete repair 
work to the piers is expected to be completed 
during the 1976 construction season. 
During the fiscal year, diversion of water 
from the Albany River watershed into Lake 
Superior basin continued. However, the high 
Lake Nipigon outflows and the release of 
Ogoki waters to the North, which began in 
May 1974, continued until August 1974. At 
the time the Ogoki water was again diverted 
south and Ontario Hydro resumed normal 
operations, no longer withholding Ogoki waters. 
At the time the Nipigon River flow into 
Lake Superior was 16,000 cfs and this flow 
prevailed through the end of the fiscal year. 
The Board continued its surveillance of 
water level and ice conditions in the lower St. 
Marys River during the winter of 1974-75 to 
ensure that appropriate remedial action could 
be taken in case of severe ice jamming in the 
river. Standby facilities were maintained for 
providing steam heat to assist in de-icing the 
gates of the Compensating Works in an emergency. 
These facilities were used on four different 
occasions when winter gate changes 
were made in March and April 1975. 
Several letters from U. S. property owners 
were received during the fiscal year by the U. 
S. Member of the Board concerning high water 
conditions on the lake and the emergency 
action by the Commission to reduce the outflow 
from Lake Superior to alleviate the high 
water levels plaguing the lower Great Lakes. 
Appropriate replies were made in each case. 
News releases were prepared and distributed 
whenever gate changes were made. 
2N. INTERNATIONAL PRAIRIE 
PORTAGE BOARD OF CONTROL 
Constitution and duties. The Board was 
formed by the International Joint Commission 
for purpose of furnishing it with technical 
advice regarding suitability of a dam structure 
at Prairie Portage, Lake County, Minnesota. 
After approval of plans by Department 
of the Army and the Commission, the Board 
was retained to advise the Commission further 
regarding progress of construction and 
any other matters which might arise concerning 
this project. The U. S. Forest Service constructed 
a cofferdam before World War II but 
postponed work on the project during the 
war. On June 12, 1968 after a period of heavy 
rains the cofferdam was washed out, resulting 
in lowering the lake levels of Birch, Sucker, 
Moose, Newfound and Ensign Lakes. This 
caused considerable difficulty for boating, as 
shallow water resulted at the outlet of the 
lakes. By November 10, 1968 the U. S. Forest 
Service completed reconstruction of the 
Prairie Portage cofferdam which has been 
functioning satisfactorily as the control dam 
for the lakes. The Board reports annually in 
March to the Commission. 
Members of the Board for fiscal year. Mr. 
R. H. Clark, Senior Engineering Advisor to 
the Director, Inland Waters Directorate, and 
Mr. R. M. Watt, Water Resources Branch, 
both in the Department of the Environment, 
represented Canada. Colonel M. W. Noah, District 
Engineer, U. S. Army Engineer District, 
St. Paul, represented the United States. 
Operations during the fiscal year. During 
the year, both the Draft and Final EIS's for 
the permanent control dam were made available 
to the CEQ and the public on August 22, 
1974 and November 26, 1974, respectively. 
Funds for construction of the dam were also 
received by the U. S. Forest Service. A contract 
was let on March 7, 1975 to Slavin and 
Shafer of Salmon, Idaho, in the amount of 
$245,860. Completion is scheduled for mid- 
November 1975. Construction was on schedule 
at the time of the Board's inspection trip on 
June 18, 1975 and also at the time of the visit 
by the U. S. Section of the International Joint 
Commission on August 26, 1975. 
20. INTERNATIONAL RAINY LAKE 
BOARD OF CONTROL 
Constitution and duties. The Convention 
between the United States and Canada, ratified 
by U. S. Senate August 30, 1940, provides 
in part that: "The International Joint Commission 
... is hearby clothed with power to 
determine when emergency conditions exist in 
the Rainy Lake watershed, in the event the 
Commission shall determine that such emergency 
conditions exist." On June 8, 1939, the 
Commission issued an Order to the owners of 
dams at outlets of Namakan Lake and Rainy 
Lake, which provide for a method of regulation 
as recommended by the Board of Control. 
The Order provides for certain levels during 
48-16

MISCELLANEOUS CIVIL WORKS 
the various seasons of the year as well as 
control of outflows, with a view to securing 
most advantageous use of water in total to 
the various interests. A Supplementary Order, 
dated October 1, 1957, modified regulations 
for Namakan Lake to provide for some 
variation in operation based on anticipated 
spring runoff. This Supplementary Order was 
extended to October 1967 and again to October 
1972, by action of the Commission on October 
2, 1962 and April 5, 1967, respectively. 
On July 29, 1970, the Supplementary Order in 
the matter of emergency regulation of Rainy 
Lake and of the Boundary Waters in the 
Rainy Lake Watershed was approved by the 
Commission. Since that time, Rainy and Namakan 
Lakes have been operated in accordance 
with rules curves prescribed by this 
Supplementary Order. The Board reports 
annually in March to the Commission. 
Members of the Board for fiscal year. Mr. 
R. H. Clark, Senior Engineering Adviser to 
the Director, Inland Waters Directorate, Department 
of the Environment, represented 
Canada, and Colonel M. W. Noah, District 
Engineer, U. S. Army Engineer District, St. 
Paul, represented the United States. 
Operations during fiscal year. At the beginning 
of the year both Rainy and Namakan 
continued to experience high levels as a result 
of the heavy rains in early June. Rainy Lake 
was at elevation 1109.3 feet with the dam 
wide open and discharging 34,000 cfs. Namakan 
Lake had just returned to within the rule 
curves and was at elevation 1118.4 feet. The 
discharge was 17,000 cfs. By July 20, outflows 
from Rainy and Namakan had returned to 
near normal, 10,000 and 5,000 cfs respectively. 
For the remainder of calendar year 1974, 
both lakes remained essentially within their 
respective rule curves and their outflows 
nearly constant. This continued until April 15 
when the lakes reached their minimum levels 
just prior to spring breakup. Rainy reached 
elevation 1104.5 feet and Namakan 1109.7 
feet. Even though the snow pack was 150% of 
normal, the refilling of both lakes was accomplished 
in fairly routine fashion. Rainy remained 
within the rules curves through the 
end of the fiscal year and on June 30 the lake 
was at 1107.9 feet and the outflow was 16,000 
cfs. The Kettle Falls dams at the outlet of the 
Namakan Chain of Lakes was wide open from 
April 2 until May 27 and rose to a maximum 
of 0.6 feet above the maximum rule curve on 
May 15. By June 30 the level was 1118.5 feet 
and the outflow was 9,000 cfs. On April 15, 
1975, the Board met in International Falls, 
Minnesota, with local residents to discuss the 
operation of the lake levels. The meeting was 
very well attended, not only by residents of 
the Crane and Kabetogama Lakes who have 
voiced their objections to the lower water levels 
on the Namakan Chain of Lakes during the 
period May 15 to June 1 in recent years but 
also by an increased number of residents 
from Rainy Lake who were concerned about 
the high water levels of 1974. 
2P. INTERNATIONAL LAKE OF THE 
WOODS CONTROL BOARD 
Constitution and duties. The Convention 
between the United States and Great Britain 
proclaimed July 17, 1925, provides for the 
regulation of the level of the Lake of the 
Woods in order to secure to the inhabitants of 
the United States and Canada the most advantageous 
use of the waters thereof, and of 
the waters flowing into and from the lake on 
each side of the boundary between the two 
countries. The Convention also provided for 
the Government of Canada to establish and 
maintain a Canadian Lake of the Woods Control 
Board to regulate and contr outflow of 
waters of that lake, and for establishment 
and maintenance of an International Lake of 
the Woods Control Board, composed of two 
engineers, one representing the United States 
and the other representing Canada, to whose 
approval the rate of total discharge shall be 
subject whenever the water level rises above 
elevation 1061 feet or falls below elevation 
1056 feet, sea level datum. The dam which 
regulates the Lake was constructed by Canadian 
interests in 1887 primarily to improve 
navigation. In 1898 it was replaced by the 
present structure to permit regulation of 
both water power and navigation and is presently 
owned by the Ontario-Minnesota Pulp 
and Paper Company, Limited. The Board reports 
annually in March to the Commission. 
Members of the Board for fiscal year. Mr. 
R. H. Clark, Senior Engineering Adviser to 
the Director, Inland Waters Directorate; and 
Mr. R.M. Watt, Water Resources Branch, 
both in the Department of the Environment, 
represented Canada and Colonel M. W. Noah, 
District Engineer, U. S. Army Engineer District, 
St. Paul, represented the United States. 
Operations during the fiscal year. The 
Board maintained supervision to insure that 
every effort was being made to comply with 
provisions of the Convention. On July 1, 1974, 
Lake of the Woods was right at the upper 
Treaty limit of 1061.25 feet and dropping 
slowly. Discharge was being maintained at 
approximately 47,000 efs. By the end of July, 
48-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
the level had dropped to 1060.4 feet and the 
outflow had been cut to plant capacity flow of 
14,000 cfs. Winter drawdown commenced on 
November 21 as the outflow was increased to 
20,000 cfs, with the lake at 1059.7 feet. The 
outflow was further increased to 24,000 on 
February 14 because of the accumulation of 
an above normal snowpack. Lake of the 
Woods reached a minimum level of 1057.4 on 
April 14 just prior to the spring snowmelt. At 
this time, outflow was reduced to 17,000 cfs 
and the lake rose to a crest of 1060.5 on June 
10. As the lake crested, outflow was again 
reduced to power plant capacity (14,000 cfs) 
for the remainder of the year. Rain in late 
June caused a rise to elevation 1060.9 on June 
30. Lake of the Woods eventually crested at 
1061.2 feet on July 5. On April 15 and 16, 
1975, the Board met with local interests in 
Warroad and Kenora respectively, to discuss 
levels on Lake of the Woods. These meetings 
are a cooperative effort of Board members to 
arrive at the best solution for the operating 
problems. Attendance at both meetings was 
substantially less than at similar meetings 
during the previous two years primarily because 
of the more satisfactory outlook for 
summer water levels. 
2Q. INTERNATIONAL PEMBINA RIVER 
ENGINEERING BOARD 
Constitution and duties. The Board was 
established April 3, 1962 by the International 
Joint Commission to investigate and report 
upon the measures which could be taken to 
develop the water resources of the Pembina 
River, Manitoba and North Dakota, and to 
reduce recurring flood loses in the basin. The 
Board performs technical investigations and 
studies necessary to enable the Commission to 
prepare and submit its report and recommendations 
to the Governments of Canada and 
the United States. 
Members of the Board for fiscal year. The 
Board consists normally of five members. The 
Canadian representatives were Mr. R. H. 
Clark, Senior Engineering Adviser to the 
Director, Inland Waters Directorate, Department 
of the Environment, Ottawa, Ontario, 
Chairman, and Mr. N. H. James, Director, 
Water Management and Planning, Inland 
Waters Branch, Department of the Environment, 
Ottawa, Ontario. The United States 
representatives were Chairman (Vacant, was 
with Bureau of Reclamation); and member 
(vacant, was with U. S. Geological Survey), 
both with Department of the Interior; and 
Colonel M. W. Noah, District Engineer, U. S. 
Army Engineer District, St. Paul. The Board 
is authorized to establish such committees 
and working groups as may be required to 
effectively accomplish its mission. 
Operations during fiscal year. The Board 
reports annually to the Commission. With 
regard to its assignment, the Board submitted 
its main report, dated December 31, 1964, to 
the Commission. During June 1965 the Commission, 
with the Board in attendance, held 
public hearings in Manitou, Manitoba, and 
Walhalla, North Dakota, where the views of 
concerned interests were presented relative to 
the information and conclusions in the 
Board's report. Subsequently, the Commission 
prepared a separate report, dated October 
1967, which was furnished to the Governments 
of Canada and the United States. To 
date no action has been taken by either Government 
on the IJC recommendation and the 
Board was in an inactive status during the 
fiscal year. 
2R. INTERNATIONAL SOURIS-RED 
RIVERS ENGINEERING BOARD 
Constitution and duties. The Board was 
established April 3,1948 by the International 
Joint Commission to investigate and report 
on the water resources of a broad area along 
the international boundary extending from 
the Milk River drainage basin in the west up 
to and including the drainage basin at the 
Red River of the North on the east. The 
Board reported in 1959 to the Commission 
that with the possible exception of the Pembina 
River there were no significant problems on 
international streams within the terms of the 
January 12, 1948 Reference and Board assignment. 
The Board has been retained to 
investigate and report on the water and related 
problems of material concern to the two 
countries arising out of the operation of existing 
dams and other work or proposed water 
related improvements, proposals for further 
uses of water by either of the two countries, 
recommendations concerning the apportionment 
between the two countries of those waters 
which cross the international boundary, 
and to investigate and review plans of mutual 
advantage of the two countries for the conservation, 
control and use of the waters within 
the area of reference. The Board reports 
annually in September to the Commission. By 
letter of February 20, 1975, the Commission 
requested the Board to review a Canadian 
company proposal for a new generating station 
on the Poplar River, a tributary to the 
Missouri River, and in light of the January 
12, 1948 Reference to the Commission from 
the two Governments. The Board was in- 
48-18

MISCELLANEOUS CIVIL WORKS 
structed to report to the Commission as soon 
as possible on the Poplar River assignment. 
Members of the Board for fiscal year. The 
Board consists of six members. The Canadian 
representatives were Mr. E. F. Durrant, 
Western Region, Inland Waters Directorate, 
Department of the Environment, Regina, Saskatchewan, 
Chairman; R. H. Clark, Senior 
Engineering Adviser to the Director, Inland 
Waters Directorate, Department of the Environment, 
Ottawa, Ontario; and Mr. G. S. 
Brown, Chief, Water Development Service, 
PFRA, Department of Regional Economic 
Expansion, Regina, Saskatchewan. The United 
States representatives were Mr. G. G. 
Stamm, Commissioner, Bureau of Reclamation, 
Department of the Interior, Washington, 
D.C., Chairman; Mr. E. L. Hendricks, Senior 
Scientist, U. S. Geological Survey, Department 
of the Interior; and Colonel M. W. Noah, 
District Engineer, U. S. Army Engineer District, 
St. Paul 
Operations during the fiscal year. In accordance 
with the August 20, 1969 instructions 
from the Commission the Board has been 
considering the survey report for flood control 
prepared by the Corps of Engineers on 
the Souris River, North Dakota. The Board 
has been requested to report to the Commission 
on the effects of the Corps of Engineers 
authorized Burlington Dam and Reservoir on 
the Souris River near Minot, North Dakota, 
upstream in Saskatchewan and downstream 
during period of reservoir drawdown on flows 
into Manitoba. An ad hoc Engineering Committee, 
including representatives of the Corps 
of Engineers, the Bureau of Reclamation and 
the North Dakota State Water Commission, is 
conducting the necessary United States studies 
and working with Canadian members in 
preparation of the required reports. The 
study is underway but completion had been 
delayed pending approval of the damsite location, 
the amount of storage to be provided, 
and the method of operation. Completion of 
the Board's report on the Souris River is dependent 
upon resolution of several problems 
relating to the Corps authorized project and 
is not expected until fiscal year 1976. 
For the Poplar River assignment the U. b. 
Section of the Board established a Task 
Force composed of representatives of the 
Bureau of Reclamation, U. S. Geological Survey, 
Soil Conservation Service, and the State 
of Montana. The Board reported to the Commission 
on March 26, 1975 on the proposed 
Canadian development on the Poplar River 
and requested authorization to undertake certain 
studies. On April 9, 1975 the Commission 
instructed the Board to carry out a water 
apportionment study. The Board's Task Force 
established a network of stream flow stations 
on the Poplar River and tributaries to monitor 
surface water flows and has prepared a 
suggested program for monitoring water 
quality. The Board has recommended to the 
Commission that a five-year basic data water 
quality monitoring program be established 
with appropriate funding. The matter of air 
quality effects will be considered by a separate 
Commission Board. 
2S. INTERNATIONAL ROSEAU RIVER 
ENGINEERING BOARD 
Constitution and duties. The Board was reestablished 
by the International Joint Commission 
on August 26, 1971 to undertake, 
through appropriate agencies in Canada and 
the United States, the necessary investigations 
and studies and to advise the Commission 
on all matters which it must consider in 
making a final and complete report on the 
questions referred to it by the two Governments 
in the December 14, 1928 Reference; (a) 
should there be coordinated projects for the 
control of Roseau River waters on both sides 
of the boundary?; (b) will the protective 
works proposed by Canada have any effect on 
the United States side of the boundary?; and 
(c) what are the effects if any of flood control 
works and resultant flood flows on the Roseau 
and Red Rivers? The Board was instructed to 
complete the investigation assigned in the 
terms of the Reference that was partially 
reported in the Commission's Interim Report 
of June 8, 1929 and the December 5, 1949 report 
with respect to the diversion of Pine 
Creek, a tributary of the Roseau River. 
Members of the Board for fiscal year. The 
Board consists of four members. For Canada: 
Mr. W. B. Thomson, Director, PFRA, Department 
of Regional Economic Expansion, Regina, 
Saskatchewan, Chairman; and Mr. T. E. 
Weber, Senior Assistant Deputy Minister, 
Manitoba Department of Mines, Resources 
and Environmental Management, Winnipeg, 
Manitoba. For the United States: the District 
Engineer, U. S. Army Engineer District, St. 
Paul, Chairman; and Mr. E. R. Gere, Director, 
Division of Waters, Soils, and Minerals, Minnesota 
Department of Natural Resources, St. 
Paul, Minn. Colonel M. W. Noah was the St. 
Paul District Engineer during the year. The 
Board formed a Task Force on October 21, 
1971 to prepare a program of studies and to 
coordinate and conduct studies assigned by 
the Board. The Task Force consisted of Mr. 
48-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
N. Mudry, Chief of Planning, Water Resources 
Branch, Manitoba Department of 
Mines, Resources and Environmental Management; 
Dr. F. Quinn, Water Planning and 
Management Branch, Department of the Environment; 
Mr. D. G. Retka, Hydrologist, Division 
of Waters, Soils, and Minerals, Minnesota 
Department of Natural Resources; and 
Mr. P. A. Fischer, Assistant Chief, 
Engineering Division, U. S. Army Engineer 
District, St. Paul 
Operations during fiscal year. The Board 
met on September 11, 1974, December 10, 
1974, February 13, 1975, April 9, 1975, and 
June 24, 1975. The Board appeared before the 
Commission on October 2, 1974 and April 9, 
1975. The Task Force met on October 17, 
1974, January 28, 1975, April 15, 1975, May 
15, 1975, June 3, 1975 and June 25, 1975. All 
of the individual reports of the cooperating 
agencies in Canada and the United States 
have been received by the Task Force and 
were evaluated. 
Drafts of the Board's main report and its 
six appendices have been completed, reviewed, 
corrected and prepared for final printing. The 
final issue will be available for public distribution 
by October 31, 1975. 
The Board's main report and appendices 
develop the necessary information that will 
permit the Commission to make a final response 
to the Governments. The report also 
develops a coordinated plan for the control 
and use of the waters of the Roseau River 
Basin. 
The Board considers that the Canadian mitigation 
measures and costs outlined in the 
plan provide a sound basis for subsequent 
negotiations between the United States and 
Canada toward the execution of an agreement 
under which the U. S. authorized flood control 
project on the Roseau River in Minnesota 
could proceed. 
2T. INTERNATIONAL KOOTENAY LAKE 
BOARD OF CONTROL 
Constitution and duties. The Board was 
established November 11, 1938 to secure compliance 
with the provisions of the Orders of 
Approval of the International Joint Commission 
dated November 11, 1938 and August 5, 
1949, relating to the construction and operation 
of control works by the Consolidated 
Mining and Smelting Company, of Canada, 
Ltd. (Cominco), through the West Kootenay 
Power and Light Co., Ltd., in and adjacent to 
the channel of the Kootenay River regulation 
of the levels of Kootenay Lake in the Province 
of British Columbia. Later the Board 
was assigned supervision of the operation of 
the Duck Lake outlet control works of the 
Creston Valley Wildlife Management Authority, 
in accordance with the Orders of the 
Commission dated October 12, 1950, April 3, 
1956 and March 31, 1970. The Board reports 
annually in March to the Commission. 
Members of the Board for fiscal year. For 
Canada: Mr. G. Tofte, District Engineer, 
Water Survey of Canada, Department of the 
Environment, Vancouver, British Columbia, 
Chairman, and Mr. H. M. Hunt, Chief of Power 
and Major Licencing Division, Water Resources 
Service, Department of Lands, Forests 
and Water Resources, Victoria, British 
Columbia; and for the United States: Colonel 
R. J. Eineigl, District Engineer, U. S. Army 
Engineer District, Seattle, Chairman, and Mr. 
H. K. Hall, District Chief, Water Resources 
Division, U. S. Geological Survey, Boise, Idaho.
Operations during fiscal year. No meetings 
of the Board were held during the fiscal year; 
however, Board members visited the area individually. 
The Board reported that during 
the year Cominco regulated the level of Kootenay 
Lake within the prescribed limits of 
the Order. 
On September 8, 1975 deviation from natural 
conditions was zero. The lake rose to a 
maximum of 1.4 feet above the computed natural 
level on October 15th. Storage at Duncan 
and at Libby Dams has affected the inflow to 
Kootenay Lake. The levels of Kootenay Lake 
under 1929 outlet conditions (called natural 
conditions) were computed without including 
the storage changes in Duncan Lake nor in 
Libby Reservoir. Under the Order of the 
Commission, the Company is required to lower 
Kootenay Lake below the computed natural 
level (depending on the discharge at Nelson, 
British Columbia, computed for natural outlet 
conditions). 
Stream flow measurements have been made 
regularly throughout the year by the United 
States Geological Survey and by the Water 
Survey of Canada. 
The West Kootenay Power and Light Company 
has continued to supply the Board and 
other agencies involved with complete records 
of the regulation of Kootenay Lake as affected 
by operation of Corra Linn Dam and power 
plant. 
The discharge control works at the outlet 
of Duck Lake were operated during the year 
in accordance with the Orders of the Commission 
dated October 12, 1950, April 3, 1956 and 
48-20

MISCELLANEOUS CIVIL WORKS 
March 31, 1970. The gates of the Duck Lake 
outlet works were opened on August 29, 1974 
when the elevation of Duck Lake was 1,746.14 
feet, and the elevation of Kootenay Lake at 
Queens Bay was 1,743.97 feet. The gates were 
kept open for the remainder of 1974. 
A staff gage was maintained in Duck Lake 
and gage readings were obtained by the 
Creston Valley Wildlife Management Area 
during the year in accordance with the Order 
of the Commission dated March 31, 1970. 
Storage at Libby Dam greatly reduced the 
inflow to Kootenay Lake durirtg the storage 
filling period (and reduced the peak flow), and 
moderately increased the inflow to Kootenay 
Lake during the storage drawdown periods. 
Work on the new Kootenay Canal Plant is 
proceeding on a schedule. The canal is completed. 
The powerhouse has been completed and 
work is progressing on generating units 1 and 
2 which should be on line by 1 October 1975. 
2U. INTERNATIONAL OSOYOOS LAKE 
BOARD OF CONTROL 
Constitution and duties. The Board was 
constituted in insure compliance with the 
provision of the Order of Approval of the International 
Joint Commission dated July 12, 
1943, directing investigation of high water 
conditions of the Okanogan River and studies 
of the relationship between certain obstructions, 
complained of in an application of the 
State of Washington, and the levels of Osoyoos 
Lake. The Board was enlarged from two 
to four members by an Order of the Commission 
dated September 12, 1946, to carry out 
the provision of the Order relative to the alternation 
and operation of Zosel Dam. The 
Board reports annually in March to the 
Commission. 
Members of the Board for fiscal year. For 
Canada: Mr. G. Tofte, District Engineer, 
Water Survey of Canada, Department of the 
Environment, Vancouver, British Columbia, 
Chairman, and Mr. J. N. Stevens, Marine Engineer, 
Pacific Region, Department of Public 
Works, Vancouver, British Columbia; and for 
the United States Mr. L. B. Laird, District 
Chief, Water Resources Division, U. S. Geological 
Survey, Tacoma, Wash., Chairman, 
until December 1975 and Mr. J. E. McCall, 
same agency, thereafter, and the District 
Engineer, U. S. Army Engineer District, Seattle. 
Colonel R. J. Eineigl was the Seattle District 
Engineer during the year. 
Operations during fiscal year. The Board 
met twice during the year, although on neither 
occasion were all Board members present. 
The following seven international gaging 
stations are being operated in the Osoyoos 
Lake area: (a) For Stage Records: Osoyoos 
Lake near Oroville, Okanogan River at 
Bridge Street, Okanogan River at Zosel Mill 
Pond, and Okanogan River at Oroville (base 
and auxiliary gates). For Discharge Records: 
Okanagan River near Oliver, B. C., Okanogan 
River at Oroville, Wash., and Similkameen 
River near Nighthawk, Wash. 
No reports or complaints of flood damage in 
the vicinity of Osoyoos Lake were received by 
the Board during the year but after a section 
of Zosel's Dam washed out in early August, 
the Water Resources Service of the Province 
of British Columbia received expressions of 
concern regarding low lake levels from residents 
around Osoyoos Lake north of the border. 
This concern was expressed to the Chairman 
of the Canadian Section of the Board. 
At the beginning of August 1974, a 12 foot 
section of Zosel's Dam washed out, but because 
of the relatively large flows through 
Osoyoos Lake (1,100 cfs), the lake level did 
not fall appreciably. There was considerable 
erosion below this section of the dam, however, 
and to reduce pressure on the dam, all 
gates were opened. About August 20, officials 
of the Washington State Department of Ecology 
visited the dam site and discussed the 
problem with the owner and local officials. 
Agreement was reached on emergency restoration, 
which was completed in early September. 
A daily elevation of Zosel Mill Pond exceeded 
911.00 feet from October 2 to 7,1974. U. 
S. Geological Survey and the Water Survey of 
Canada made surveys of the network of cross 
profiles and radials on the gravel bar at the 
outlet of Osoyoos Lake during the period October 
29 to 31, 1974. 
2V. INTERNATIONAL SKAGIT RIVER 
BOARD OF CONTROL 
Constitution and duties. The International 
Joint Commission approved on January 27, 
1942, an application by the City of Seattle, 
Wash., to raise Ross Dam to impound Skagit 
River water to a maximum elevation 1725 feet 
above mean sea level at the international 
boundary, subject to a binding agreement 
being entered into between the City of Seattle 
and the Government of British Columbia 
providing for indemnifing British Columbia 
for any injury that may be sustained by reason 
of the City's operations on the Skagit 
River. The Order of Approval provided for 
48-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
the appointment of the Board of Control, to 
consist of two members, one from the engineering 
services of Canada and one from the 
United States, but the Commission did not 
establish the Board at that time. On January 
10, 1967, the Province of British Columbia 
and the City of Seattle entered into a 99-year 
agreement permitting flooding of the lands of 
the Skagit River watershed in British Columbia 
up to elevation 1725 feet, North American 
datum (1927) as established by the Geodetic 
Survey of Canada. In a July 31, 1967 directive 
to the designated Board members the Commission 
stated that the Board was established on 
April 4, 1967. The Board reports annually in 
March to the Commission. 
Members of the Board for fiscal year. Mr. 
G. Tofte, District Engineer, Water Survey of 
Canada, Department of the Environment, Vancouver, 
British Columbia, for Canada, and the 
District Engineer, U. S. Army Engineer District 
Seattle, Washington for the United 
States. Colonel R. J. Eineigl was the Seattle 
District Engineer during the year. 
Operations during the fiscal year. The water 
surface at the international boundary 
reached a maximum elevation of 1603.73 feet 
on August 19, 1974 as recorded by the gaging 
station, No. 8PA-4, Skagit River at the 
boundary, near Hope. The Board did not meet 
formally or visit the area during the year. 
There is known environmental concern over 
the proposed raising of Rosa Dam and Lake. 
The Commission accomplished an environmental 
study of the area independent of the 
Board. 
2W. COLUMBIA RIVER TREATY 
ENTITIES 
Constitution and duties. The Columbia River 
Treaty, which provides for the cooperative 
development of water resources of the Columbia 
River Basin by the United States and 
Canada, was ratified on September 16, 1964 
by the two Goverments. Article XIV of the 
Treaty provided that each country should 
designate entities to carry out the operating 
arrangements necessary to implement the 
Treaty. The principal recurring duties of the 
entities include: establishment and operation 
of a hydrometeorological system; preparation 
of hydroelectric operating plans and flood 
control operating plans; determination of 
downstream power benefits; and assisting and 
cooperating with the Permanent Engineering 
Board in the discharge of its functions. 
Executive Order No. 11177 dated September 
16, 1964 designated the Administrator, Bonneville 
Power Administration and the Division 
Engineer, North Pacific Division, Corps of 
Engineers, as the United States Entity with 
the Administrator as Chairman. British Columbia 
Hydro and Power Authority was designated 
as the Canadian Entity. To carry out 
their functions, the Entities organized two 
permanent international committees: the Columbia 
River Treaty Operating Committee and 
the Columbia River Treaty Hydrometeorological 
Committee. The United States Entity 
also appointed a Secretary and two Coordinators, 
one from the Bonneville Power Administration 
and one from the Corps of Engineers. 
The Canadian Entity appointed a Manager, 
Canadian Entity Services. 
Membership for the fiscal year. Entities and 
its Committees consisted of Mr. D. P. Hodel, 
Administrator, Bonneville Power Administration, 
and Major General R. E. McConnell, Division 
Engineer, North Pacific Division, Corps 
of Engineers, as Chairman and member of the 
United States Entity, respectively. Mr. W. D. 
Kennedy of B. C. Hydro and Power Authority 
represented the Canadian Entity. Messrs. B. 
Goldhammer, assistant Administrator for 
Power Management, BPA, and P. L. Cole, 
Chief, Engineering Division, NPD served as 
U.S. Entity Coordinators. Mr. H. Kropitzer, 
Executive to the Administrator, BPA, succeeded 
Mr. Goldhammer in January 1975. Mr. 
W. D. Kennedy of B.C. Hydro and Power Authority 
was Manager, Canadian Entity Services 
and Mr. H. Kropitzer, succeeded by Mr. 
C. E. Cancilla, BPA, in January 1975, was 
U.S. Entity Secretary. 
Membership on the Columbia River Treaty 
Operating Committee was as follows: The U. 
S. Section of the Committee consisted of 
Messrs. D. M. Rockwood (co-chairman) and G. 
G. Green of the Corps of Engineers, and Mr. 
H. M. McIntyre (co-chairman until December 
31, 1974) and C. W. Blake (co-chairman after 
January 1, 1975) of the Bonneville Power 
Administration. Mr. K. D. Earls succeeded Mr. 
McIntyre in January 1975. The Canadian Section 
was comprised of Messrs. P. R. Purcell 
(chairman), D. R. Forrest, W. E. Kenny, and T. 
J. Newton (appointed in September 1974) all 
of B. C. Hydro and Power Authority. Mr. D. 
D. Speers, Corps of Engineers, served as Secretary. 
Membership of the Columbia River 
Treaty Hydrometeorological Committee was 
Messrs. F. A. Limpert of BPA (chairman) and 
M. L. Larson of the Corps of Engineers, for 
the U. S. Section, and Messrs. P. R. Purcell 
(chairman) and U. Sporns, both of B. C. Hy- 
48-22

MISCELLANEOUS CIVIL WORKS 
dro and Power Authority for the Canadian 
Section. 
Operations during the fiscal year. The Mica, 
Hugh Keenleyside (Arrow), Duncan, and Libby 
projects were operated in accordance with 
the "Detailed Operating Plan for Canadian 
Storage--July 1, 1974 through July 31, 1975", 
dated September 1974. The Mica project, 
which become operational on March 29, 1973, 
was operated in accordance with the 1974-75 
Detailed Operating Plan, and the "Program 
for Initial Filling of Mica Reservoir", dated 
26 July 1967, as amended. 
The Entities and their Coordinators and 
Committes met on several occasions during 
the fiscal year. The Entities met with the 
Permanent Engineering Board on November 
26, 1974. 
The Entities issued a "Report of the Columbia 
River Treaty, Canadian and United 
States Entities, for the period 1 October 1973 
to 30 September 1974", dated October 1974. 
The Columbia River Treaty Operating Committee 
prepared four reports: "Detailed Operating 
Plan for Columbia River Treaty Storage, 
1 July 1974 thru 31 July 1975", dated 
September 1974; "Report on Operation of 
Columbia River Treaty Projects, 1 August 
1973 thru 31 July 1974", dated September 
1974; "Columbia River Treaty Hydroelectric 
Operating Plan, Assured Operating Plan for 
Operation year 1979-80", dated September 
1974; and "Determination of Downstream 
Power Benefits Resulting From Canadian 
Storage for Operating Year 1979-80", dated 
September 1974. The Columbia River Treaty 
Hydrometeorological Committee issued the 
report "Hydrometeorological System Plan for 
Exchange of Operational Hydromet Data", 
dated December 1974. 
2X. COLUMBIA RIVER TREATY 
PERMANENT ENGINEERING BOARD 
Constitution and duties. The Columbia River 
Treaty, which provides for co-operative 
development of the water resources of the 
Columbia River Basin, was signed on January 
17, 1961 by representatives of the United 
States and Canada. Article XV of the Treaty 
established a Permanent Engineering Board 
consisting of four members, two from each 
country. Pursuant to Executive Order No. 
11177 dated September 16, 1964 the Secretary 
of the Army and the Secretary of the Interior 
on December 7, 1964 appointed two members 
and two alternate members to form the U. S. 
Section of the Board. The general duties and 
responsibilities of the Board as set in the 
Treaty and related documents are to: (a) assemble 
certain records of flow; (b) report any 
substantial deviation from operating plans to 
recommend adjustments; (c) assist the Entities 
in reconciling technical and operational 
differences; (d) make periodic inspections and 
required reports with a view to insuring that 
the objectives of the Treaty are being met; (e) 
make annual and special reports to the Governments; 
(f) investigate and report other 
matters at the request of either Government; 
and (g) consult with the Entities in establishing 
and operating a hydrometerological system 
for the basin. 
Members of the Board for fiscal year. The 
Canadian members were Mr. G. M. MacNabb, 
Senior Assistant Deputy Minister, Energy 
Development, Department of Energy, Mines 
and Resources, Ottawa, Ontario, (Chairman), 
and Mr. B. E. Marr, Department of Lands, 
Forests and Water Resources, Victoria, B. C. 
The United States members were Mr. H. B. 
Willis, Chief, Engineering Division, Civil 
Works Directorate, U. S. Army Office of the 
Chief of Engineers, Washington, D.C. (Chairman) 
and Mr. C. K. Mallory, Deputy Assistant 
Secretary for Energy and Minerals, U. S. 
Department of the Interior, Washington, D.C. 
Operations during the fiscal year. The 
Board met on November 26, 1974 to independently 
review progress and later met in a joint 
meeting with the Entities on the same day. 
The Board sent its 10th annual report for the 
period ending September 30, 1974 to both 
Governments on December 31, 1974. The annual 
report summarizes activities of the Permanent 
Engineering Board and the Entities, 
the progress on construction of the Treaty 
projects, Libby and Mica, and on studies under 
way. Operations of Mica, Libby, Arrow 
and Duncan reservoirs and the related benefits 
accrued are described. Regulation of the 
four Treaty projects during the 1975 freshet 
period prevented significant flooding in both 
countries. The report also records the conclusion 
of the Board that the objectives of the 
Treaty are being met. 
48-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY, 1975 
TABLE 48-A MISCELLANEOUS CIVIL WORKS: APPROPRIATIONS 
(See Sec. 1 of Text) 
APPROPRIATIONS. For investigations, inspections, hearings, reports, service of notice, or other action incidental 
to examination of plans or sites of structures built or proposed to be built in or over navigable waters or to examinations 
into alleged violations of law of the protection and preservation of navigable waters of the United States or 
to the establishment of marking or harbor lines 
Allotted during year ........................................ 15,587,800 
(These funds were allotted from river and harbor appropriation in accordance 
with the provisions of Sec. 6, River and Harbor Act of Mar. 3, 1905.) 
For the investigation and removal of sunken vessels: 
Balance on hand Jul. 1, 1974 ......................................................................................... 504,384 
Allotted during year (net) ........................................ 9,986,723 
(These funds were allotted from the appropriation "Operation and Maintenance, 
General, Protection of Navigation, Removal of Sunken Vessels and other 
Obstructions.") 
Total .................................................. 26,078,907 
EXPENDITURES. Total expenditures for fiscal year exclusive of outstanding liabilities, amounting to $26,037 were 
$19,505,361 expended as follows: 
For investigations, inspections, hearings, and other action 
incidental to administration of Federal laws ............................... .. $15,587,800 
For removal of sunken vessels .................. .......................... $ 3.917.561 
Total ............................................................................................................................... $19,505,361 
Total funds available ........................................ $26,078,907 
Total expenditures ..................................... $19,505,361 
Outstanding liabilities .............................................. $ 26,037 $19,531,398 
Balance available Jun. 30, 1975 $ 6,547,509 
48-24

INDEX 
The following abbreviations are used in the index: 
BERH Board of Engineers for Rivers and Harbors 
CDC California Debris Commission 
CERC Coastal Engineering Research Center 
LMK Vicksburg, Miss., District 
LMM Memphis, Tenn., District 
LMN New Orleans, La., District 
LMS St. Louis, Mo., District 
MR&T Mississippi River and Tributaries Project 
MRK Kansas City, Mo., District 
MRO Omaha, Nebr., District 
NAB Baltimore, Md., District 
NAN New York, N.Y., District 
NAO Norfolk, Va., District 
NAP Philadelphia, Pa., District 
NCB Buffalo, N.Y., District 
NCC Chicago, Ill., District 
NCE Detroit, Mich., District 
NCR Rock Island, Ill., District 
NCS St. Paul, Minn., District 
NED New England Division 
NPP Portland, Oreg., District 
Abbapoola Creek, S. C. (SAN) 7-16 
Aberdeen Creek, Va. (NAO) 5-2, 5-19, 5-22 
Aberdeen, Ohio (ORH) 25-25, 25-29, 25-31 
Abilene Channel Improvement, Tex. (SWF) 16-5, 16-19 
Abilene, Kan. (MRK) 20-31, 20-32, 20-33 
Abiquiu Dam, N. Mex. (SWA) 17-11, 17-16, 17-19 
Absecon Creek, N.J. (NAP) 3-26 
Absecon Inlet, N.J. (NAP) 3-2, 3-19, 3-22 
Accotink Creek, Va. (NAB) 4-37 
Adams Creek, S. C. (SAN) 7-1, 7-11, 7-12 
Adams Levee, Ind. (ORL) 24-33 
Adams, Mass. (NAN) 2-47 
Addicks Dam, Tex. (SWG) 15-41 
Addison, N.Y. (NAB) 4-15, 4-28, 4-41 
Adena, Ohio (ORP) 26-28, 26-31 
Adkin Branch, N. C. (SAW) 6-32 
Aitkin, Minn. (NCS) 27-33 
Alabama-Coosa Rivers, Ala., and Ga. (SAM) 10-17, 10-2 
36, 10-42 
Alabama River at Montgomery, Ala. (SAM) 10-41 
Alameda Creek, Calif. (SPN) 34-11, 34-16 
Alamogordo Diversion Channel, N. Mex: (SWA) 17-20 
?8, 10- 
NPS 
NPW 
ORD 
ORH 
ORL 
ORN 
ORP 
POD 
SAJ 
SAM 
SAN 
SAS 
SAW 
SPK 
SPL 
SPN 
SWA 
SWF 
SWG 
SWL 
SWT 
Seattle, Wash., District 
Walla Walla, Wash., District 
Ohio River Division 
Huntington, W. Va., District 
Louisville, Ky., District 
Nashville, Tenn., District 
Pittsburgh, Pa., District 
Pacific Ocean Division 
Jacksonville, Fla., District 
Mobile, Ala., District 
Charleston, S.C., District 
Savannah, Ga., District 
Wilmington, N.C., District 
Sacramento, Calif., District 
Los Angeles, Calif., District 
San Francisco, Calif., District 
Albuquerque, N. Mex., District 
Fort Worth, District 
Galveston, Tex., District 
Little Rock, Ark., District 
Tulsa, Okla., District 
Alamo Lake, Ariz. (SPL) 33-8, 33-22, 33-27 
Ala Wai Small Boat Harbor, Oahu, Hawaii (POD) 36-1, 36-9, 
36-11 
Albany, Oreg. (NPP) 37-55 
Albemarle and Chesapeake Canal, Great Bridge, Va. (NAO) 
5-25 
Albeni Falls Dams, Idaho (NPS) 38-12, 38-18, 38-23 
Albuquerque Diversion Channels Project, N. Mex. (SWA) 17- 
1, 17-16 
Algiers Lock, La. (LMN) 11-12, 11-51 
Algoma Harbor, Wis. (NCC) 30-2, 30-22 
Alhambra Creek, Calif. (SPN) 34-23 
Aliso Creek Dam, Calif. (SPL) 33-36, 33-38 
Alkali Canyon, Arlington, Oreg. (NPP) 37-55 
Allatoona Lake and Dam, Ga. (SAM) 10-20, 10-29, 10-37, 10- 
42 
Allegany, N.Y. (ORP) 26-3, 26-19 
Allegany, N.Y., Unit I, Allegheny River (ORP) 26-28, 26-31 
Allegany, N.Y., Unit II, Five Mile Creek Area (ORP) 26-28 
Allegheny River, Pa. (ORP) 26-2, 26-19, 26-22, 26-24, 26-27, 
26-29 
Allentown, Pa. (NAP) 3-17, 3-28 
I-1 
P

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Alligator-Catfish Bayou, Miss. (MR&T) 42-52 
Alloway Creek, N.J. (NAP) 3-26 
Alma Harbor, Wis. (NCD) 29-8 
Almond Lake, N.Y. (NAB) 4-15, 4-28, 4-40, 4-41 
Almond Village, N.Y. (NAB) 4-41, 4-44 
Aloha-Rigolette Area, Grant and Rapides Parishes, La. (LMN) 
11-56, 11-57 
Alpena Harbor, Mich. (NCE) 31-2, 31-36, 31-44 
Alpine, Tex. (SWA) 17-2, 17-17 
Alpine Dam, Rockford, Ill. (NCR) 28-11 
Alsea Bay and River, Oreg. (NPP) 37-47 
Altamaha, Oconee and Ocmulgee Rivers, Ga. (SAS) 8-1, 8-11, 
8-12 
Alton, Ill., Urban Areas at (LMS) 14-19 
Alton, Ind. (ORL) 24-33, 24-38 
Alton Pool, Ill. (NCC) 30-7 
Alum Creek Lake, Ohio (ORH) 25-3, 25-20 
Alvin R. Bush Dam, Pa. (NAB) 4-21, 4-29, 4-43 
Amazon Creek, Oreg. (NPP) 37-55 
American Falls International Board 48-11 
American Lake, Vicinity of Fort Lewis, Wash. (NPS) 38-28 
American River, Calif. (SPK) 35-22, 35-34 
Ames Lake, Iowa (NCR) 28-12 
Amite River and Bayou Manchac, La. (LMN) 11-53 
Amite River and Tributaries, La. (LMN) 11-57 
Amite River, La. (MR&T) 42-16 
Amsterdam, Ohio (ORP) 26-30, 26-31 
Anacortes Harbor, Wash. (NPS) 38-1, 38-16, 38-20 
Anacortes Navigation Channel, Wash. (NPS) 38-2, 38-16, 38- 
20 
Anacostia River and Flats, Md. (NAB) 4-37 
Anacostia River and Tributaries, Flood Protection and 
Navigation Improvements, D.C. and Md. (NAB) 4-11, 4- 
27, 4-34 
Anacostia River and Tributaries, Prince Georges County, Md. 
(NAB) 4-12, 4-27, 4-34 
Anaheim Bay Harbor, Calif. (SPL) 33-31 
Anahuac Channel, Tex. (SWG) 15-10 
Anchorage Harbor, Alaska (NPA) 40-1, 40-11, 40-13 
Anclote River, Fla. (SAJ) 9-40, 9-41 
Andalusia Harbor, Ill. (NCD) 29-2, 29-8 
Andover Lake, Conn. (NED) 1-75, 1-76 
Andrews, George W., Lock and Dam, Ala. and Ga. (SAM) 10- 
21, 10-22, 10-29, 10-37, 10-43 
Andrews River, Mass. (NED) 1-2, 1-46, 1-55 
Annapolis Harbor, Md. (NAB) 4-37 
Annisquam River, Gloucester, Mass. (NED) 1-65, 1-66 
Ansonia, Conn. (NED) 1-44 
Ansonia-Derby, Conn. (NED) 1-31, 1-52, 1-62, 1-73 
Anthony Shoals Dam and Lake, Ga. (SAS) 8-16 
Apalachee Bay, Fla. to New Orleans, La. (SAM) 10-33 
Apalachicola Bay, Fla. (SAM) 10-2, 10-26, 10-30 
Apalachicola Bay to St Marks River, Fla. (SAM) 10-33 
Apalachicola, Chattahoochee, and Flint Rivers, Ala., Ga., and 
Fla. (SAM) 10-20, 10-29, 10-37, 10-43 
Apalachicola River to St. Andrew Bay, Fla. (SAM) 10-33 
Apoon Mouth of Yukon River, Alaska, (NPA) 40-15 
Applegate Lake, Oreg. (NPP) 37-15, 37-34, 37-42 
Appleton Locks and Dams, Wis. (NCC) 30-36 
Appomattox River, Va. (NAO) 5-26, 5-27 
Apponaug Cove, R.I. (NED) 1-65, 1-66 
Appoquinimink River, Del. (NAP) 3-26 
Aquashicola Reservoir, Pa. (NAP) 3-28 
Aquatic Plant Control 
Baltimore, Md., District (NAB) 4-8, 4-26 
Buffalo, N.Y., District (NCB) 32-42 
Charleston, S.C., District (SAN) 7-2 
Galveston, Tex., District (SWG) 15-2, 15-17, 15-21, 15-32 
Jacksonville, Fla., District (SAJ) 9-2, 9-25, 9-29, 9-13, 9-27, 
9-32, 9-40, 9-41 
Mobile, Ala., District (SAM) 10-2, 10-13, 10-26, 10-28, 10- 
31, 10-36, 10-40 
New England Division (NED) 1-2, 1-46, 1-55 
New Orleans, La., District (LMN) 11-2, 11-24, 11-37, 11-39, 
11-42, 11-47 
New York, N.Y., District (NAN) 2-2, 2-32, 2-36 
Norfolk, Va., District (NAO) 5-3, 5-19 
Omaha, Nebr., District (MRO) 21-10 
Philadelphia, Pa., District (NAP) 3-2, 3-19 
Sacramento, Calif., District (SPK) 35-34 
Savannah, Gt., District (SAS) 8-2, 8-11, 8-12, 8-16 
Wilmington, N.C., District (SAW) 6-2, 6-23, 6-29 
Aquia Creek, Va. (NAB) 4-37 
Aquilla Lake, Tex. (SWF) 16-6, 16-19, 16-24 
Arcadia Harbor, Mich. (NCE) 31-2, 31-36, 31-44 
Arcadia Lake, Okla. (SWT) 19-5, 19-25, 19-30 
Arch Creek, Fla. (SAJ) 9-24, 9-51 
Arecibo Harbor, P. R. (SAJ) 9-2, 9-25, 9-29 
Arkabutla Lake, Miss. (MR&T) 42-10, 42-19, 42-22, 42-52, 
42-57, 42-59 
Arkansas River and Tributaries Above John Martin Dam, 
Colo. (SWA) 17-2, 17-17 
Arkansas River Bank Stabilization and Channel Rectification, 
Ark. and Okla. (SWT) 19-2, 19-32 
Arkansas River Basin, Ark., Okla., and Kans. (SWL) (SWT) 
18-2, 18-12, 18-14, 18-16, 18-18, 19-2, 19-32 
Ark-Red River Basins Chloride Control, Tex. (SWT) 19-6, 
19-25, 19-33 
Ark-Red River Basins Chloride Control, Okla., Tex., and 
Kans. (SWT) 19-5, 19-6, 19-25; 19-30; 19-33, 19-34 
Ark-Red River Basins Chloride Control, Supplemental 
Studies, Okla. (SWT) 19-6, 19-25 
Arkansas-Red River Basins Water Quality Control, Tex., 
Okla., and Kans. (SWT) 19-5, 19-30 
Arkansas River, Channel Realignment (MR&T) 42-56 
Arkansas River Channelization Test Reach (SWA) 17-4, 17-18 
Arkansas River Floodway Brewster to Florence, Colo. (SWA) 
17-4, 17-18 
Arkansas River Levees, Ark. (MR&T) 42-9 
Arkansas River, Standard Revetments (MR&T) 42-1, 42-38 
Arkport Dam, N.Y. (NAB) 4-15, 4-28, 4-40, 4-41 
Arlington Lake, Mo. (MRK) 20-31, 20-33 
Armuchee Creek, Ga. (SAM) 10-17, 10-41 
Ascalmore-Tippo Bayous, Miss. (MR&T) 42-52 
Ashland Harbor, Wis. (NCS) 27-2, 27-23, 27-27 
Ashland, Ky. (ORH) 25-25, 25-30, 25-31 
Ashley River, S. C. (SAN) 7-16 
Ashtabula Harbor, Ohio (NCB) 32-2, 32-26, 32-31 
Asotin Dam, Idaho and Wash. (NPW) 39-24 
Atchafalaya Basin Floodway, La. (MR&T) 42-1, 42-14, 42-15, 
42-45, 42-51, 42-58 
Atchafalaya River and Bayous Chene, Boeuf, and Black, La. 
(LMN) 11-3, 11-37, 11-42 
Atchafalaya Basin, La. (MR&T) 42-6, 42-14, 42-29, 42-55, 42- 
56, 42-58 
Atchafalaya River, La. (MR&T) 42-1, 42-15, 42-56, 42-58 
Atchafalaya River, Morgan City to Gulf of Mexico, La. (LMN) 
11-4, 11-37, 11-42 
Atachafalaya River, Standard Revetment (MR&T) 42-33 
Atchison, Kans. (MRK) 20-33 
Athalia, Ohio (ORH) 25-25, 25-31 
Athens, Ohio (ORH) 25-3, 25-20, 25-30, 25-31 
Atlantic Beach Channels, N. C. (SAW) 6-29 
Atlantic City, N.J. (NAP) 3-27 
I-2

INDEX 
Atlantic Coast of N.J., Sandy Hook to Barnegat Inlets (NAN) 
2-47 
Atlantic Gulf Ship Canal, Fla. (SAJ) 9-41 
Atlantic Intracoastal Waterway between Norfolk, Va., and St. 
Johns River, Fla. (NAO) (SAW) (SAN) (SAS) (SAJ) 5-2, 5- 
19, 5-22, 5-25, 6-2, 6-23, 6-26, 7-2, 7-11, 7-13, 8-3, 8-11, 
8-12, 9-2, 9-25, 9-29 
Auburn, N.Y., Owasco Outlet (NCB) 32-44 
Aubrey Lake, Tex. (SWF) 16-6, 16-19 
Augusta, Ark. (MR&T) 42-2, 42-57 
Augusta, Ga. (SAS) 8-8, 8-16 
Augusta, Kans. (SWT) 19-38 
Augusta, Ky. (ORH) 25-25, 25-29, 25-31 
Aurora, Ind. (ORL) 24-33 
Aurora, Westerly Creek,,Colorado (MRO) 21-21 
Au Sable Harbor at Au Sable River (Oscod'a), Mich (NCE) 
31-3, 31-36, 31-44 
Autauga Creek, Prattville, Ala. (SAM) 10-17 
Avoca, N.Y. (NAB) 4-16, 4-28, 4-41 
Avon Harbor, N. C. (SAW) 6-4, 6-23 
Aycock Swamp Reservoir, N. C. (SAW) 6-31 
Aylesworth Creek Lake, Pa. (NAB) 4-14, 4-27, 4-39, 4-40 
B 
B. A. Steinhagen Lake, Tex. (SWF) 16-2, 16-19 
B. Everett Jordon Dam and Lake, N. C. (SAW) 6-14, 6-25, 6- 
31 
Babylon Creek Inlet, N.Y. (NAN) 2-46 
Bachelor Island, Wash. (NPP) 37-50, 37-54 
Back Creek, Md. (NAB) 4-37 
Bad River, Ft. Pierre, S. Dak. (MRO) 21-20 
Bagaduce River, Maine (NED) 1-66 
Bailey, R. D., Lake, W. Va. (ORH) 25-15, 25-22 
Bainbridge, N.Y. (NAB) 4-44 
Baker Brook, Mass. (NED) 1-74, 1-76 
Bakers Haulover Inlet, Fla. (SAJ) 9-41 
Bakers Mill Reservoir, N. C. (SAW) 6-31 
Baldhill Dam, N. Dak. (NCS) 27-14, 27-25 
Baldwin and Hannon Sloughs, Montgomery, Ala. (SAM) 10- 
41 
Ballona Creek Basin, Calif. (SPL) 33-13, 33-32, 33-34 
Ballona Creek Channel and Jetties, Calif. (SPL) 33-32, 33-34 
Ball Mountain Lake, Vt. (NED) 1-23, 1-50, 1-61, 1-71 
Ball Park Creek, Bayfield, Wis. (NCS) 27-34 
Baltimore Harbor and Channels, Md. (NAB) (NAO) 4-2, 4- 
26, 4-31, 5-4, 5-19, 5-22 
Baltimore Harbor, Md., Collection and Removal of Drift 
(NAB) 4-4, 4-26, 4-32 
Baltimore Harbor, Md., Prevention of Obstructions and 
Injurious Deposits (NAB) 4-5, 4-26, 4-32 
Bank Revetments and Dikes (MR&T) 42-39 
Bank Stabilization and Channel Rectification, Ark. (SWL) 18- 
2, 18-12, 18-19, 18-20 
Bankhead, John Hollis, Lock and Dam, Ala. (SAM) 10-5, 10- 
38 
Banner Special Drainage and Levee District, Ill. (NCC) 30-41, 
30-42 
Banning Levee, Calif. (SPL) 33-37, 33-38 
Bar Harbor, Maine (NED) 1-66 
Barataria Bay Waterway, La. (LMN) 11-4, 11-37, 11-42 
Barbers Point Harbor, Oahu, Hawaii (POD) 36-2, 36-9, 36-11 
Barboursville, W. Va. (ORH) 25-30 
Barbourville, Ky. (ORN) 23-18 
Barcelona Harbor, N.Y. (NCB) 32-42 
Bardwell Lake, Tex. (SWF) 16-6, 16-19, 16-26 
Barker Dam, Tex. (SWG) 15-41 
Barkley Dam and Lake Barkley, Ky. and Tenn. (ORN) 23-2, 
23-14, 23-19 
Barnegat Inlet, N.J. (NAP) 3-3, 3-19, 3-22 
Barnegat Light, N.J. (NAP) 3-27 
Barnett Creek, Ky. (ORL) 24-33 
Barre Falls Dam, Mass. (NED) 1-24, 1-50, 1-61, 1-71 
Barren River Lake, Ky. (ORL) 24-3, 24-24, 24-36 
Bartley, Nebr. (MRK) 20-31, 20-32, 20-33 
Bass Harbor Bar, Maine (NED) 1-65, 1-66 
Bass Harbor, Maine (NED) 1-65, 1-66 
Bastrop Bayou, Tex. (SWG) 15-32 
Bastrup, La., to Mouth of Boeuf River and at West Monroe, 
La. (LMK) 12-12 
Batavia and Vicinity, Tonawanda Creek, N.Y. (NCB) 32-44 
Bath, N.Y. (NAB) 4-41, 4-44 
Baton Rouge Harbor, (Devils Swamp) La. MR&T) 42-1, 42- 
7, 42-29, 42-30, 42-51, 42-58 
Battle Creek, Mich. (NCE) 31-30 
Battle Creek, Nebr. (MRO) 21-21 
Baudette Harbor, Minn. (NCS) 27-31 
Bay City Harbor, Wis. (NCD) 29-3, 29-8 
Bay Port Harbor, Mich. (NCE) 31-3, 31-36, 31-44 
Bay Ridge and Red Hook Channels, N.Y. (NAN) 2-2, 2-32, 2- 
36 
Bay River, N. C. (SAW) 6-29 
Bayard, W. Va. (NAB) 4-44 
Bayfield Harbor, Wis. (NCS) 27-2, 27-23 
Bayou Bartholomew and Tributaries, Ark. and La. (LMK) 12- 
5, 12-8, 12-9, 12-12 
Bayou Bartholomew, La. and Ark. (LMK) 12-11 
Bayou Bodca and Tributaries, Ark. and La. (LMN) 11-26, 11- 
39, 11-47, 11-55 
Bayou Bodcau, Red Chute, and Loggy Bayou, La. (LMN) 11- 
56, 11-57 
Bayou Bodcau Reservoir, La. (LMN) 11-27, 11-39, 11-47, 11- 
54, 11-56 
Bayou Bodcau, Red Chute, and Loggy Bayou, La. (LMN) 11- 
56, 11-57 
Bayou Boeuf La. (MR&T) 42-16 
Bayou Boeuf Lock, La. (LMN) 11-51 
Bayou Bonfouca, La. (LMN) 11-53 
Bayou Choupique, La. (LMN) 11-57 
Bayou Cocodrie and Tributaries, La. (MR&T) 42-1, 42-7, 42- 
16, 42-29, 42-55, 42-57, 42-58 
Bayou Coden, Ala. (SAM) 10-3, 10-26, 10-31 
Bayou des Glaises, (MR&T) 42-1, 42-16, 42-51, 42-56 
Bayou Dorcheat, Loggy Bayou, and Lake Bisteneau, La. 
(LMN) 11-53 
Bayou du Chien, Tenn., and Ky. (MR&T) 42-2, 42-21 
Bayou Dupre, La. (LMN) 11-53 
Bayou Galere, Miss. (SAM) 10-40 
Bayou Grand Caillou, La. (LMN) 11-25, 11-39 
Bayou Grosse Tete, La. (LMN) 11-53 
Bayou LaBatre, Ala. (SAM) 10-3, 10-26, 10-31 
Bayou Lacombe, La. (LMN) 11-53 
Bayou LaFourche and LaFourche-Jump Waterway, La. 
(LMN) 11-4, 11-37, 11-42 
Bayou LaFourche, La. (MR&T) 42-2, 42-52 
Bayou LeCarpe, La. (LMN) 11-25, 11-39 
Bayou Macon, Ark., and La. (MR&T) 42-18, 42-53 
Bayou Nicholas, Coushatta, La. (LMN) 11-55, 11-57 
Bayou Pierre, La. (LMN) 11-27, 11-39, 11-47, 11-56 
Bayou Pierre in Vicinity of Shreveport, La. (LMN) 11-55, 11- 
57 
Bayou Plaquemine Brule, La. (LMN) 11-53 
I-3

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Bayou Queue DeTortue, La. (LMN) 11-53 
Bayou Rapides, La. (LMN) 11-57 
Bayou Segnette Waterway, La. (LMN) 11-53 
Bayou Sorrel Lock, La. (LMN) j,1-51 
Bayou Teche and Vermilion River, La. (LMN) 11-6, 11-37, 
11-43 
Bayou Teche, La. (LMN) 11-6, 11-37, 11-43, 11-50 
Bayou Teche, La., Locks (LMN) 11-50 
Bayou Terrebonne, La. (LMN) 11-53 
Bayou Vermilion, La. (LMN) 11-53 
Bayous D'Arbonne and Corney, La. (LMK) 12-11 
Bayous LaLoutre, St. Malo, and Yscloskey, La. (LMN) 11-53 
Bayous Rapides, Boeuf, and Cocodrie, La. (MR&T) 42-51 
Bayport, Fla. (SAJ) 9-41 
Beals Creek, Big Spring, Tex. (SWF) 16-22 
Beals Harbor, Maine (NED) 1-65, 1-66 
Bear Creek at Hannibal, Mo (NCR) 28-12 
Bear Creek Dam, Hannibal, Mo (NCR) 28-12 
Bear Creek, Kendrick, Idaho (NPW) 39-17, 39-18 
Bear Creek Lake, Colo. (MRO) 21-3, 21-14 
Bear Creek, Oreg. (NPP) 37-55 
Bear Stream, Calif. (SPK) 35-16, 35-22 
Beards Brook Reservoir, N.H. (NED) 1-76 
Beardstown Sanitary District, Ill. (NCC) 30-41 
Beatrice, Nebr. (MRK) 20-31, 20-33 
Beaufort Harbor, N. C. (SAW) 6-4, 6-23, 6-27 
Beulahtown Reservoir, N. C. (SAW) 6-31 
Beaver and Mahoning Rivers, Pa. and Ohio (ORP) 26-27, 26- 
29 
Beaver Bay Harbor, Minn. (NCS) 27-3, 27-23 
Beaver Brook Lake, N.H. (NED) 1-71, 1-76 
Beaver Creek, Langley, Ky. (ORH) 25-30 
Beaver Creek, Montezuma, Ga. (SAM) 10-41 
Beaver Creek Near Tillamook, Oreg. (NPP) 37-55 
Beaver Creek Wayland to Garrett, Ky. (ORH) 25-30 
Beaver Drainage District, Oreg. (NPP) 37-16, 37-34, 37-42, 
37-50, 37-53 
Beaver Lake, Ark. (SWL) 18-7, 18-9, 18-13, 18-22, 18-23 
Beaver Slough, Clinton, Iowa (NCD) 29-2 
Bedford, Iowa (MRK) 20-32, 20-33 
Beech Creek, Mt. Vernon, Oreg. (NPP) 37-16, 37-34, 37-42 
Beech Fork Lake, W. Va. (ORH) 25-4, 25-20 
Belfast Harbor, Maine (NED) 1-65, 1-66 
Belhaven Harbor, N. C. (SAW) 6-29 
Bell Drainage District, Ill. (NCC) 30-42 
Bell Foley Lake, Ark. (SWL) 18-4, 18-12, 18-22 
Bellaire, Ohio (ORP) 26-28, 26-31 
Bellamy River, N.H. (NED) 1-66 
Belle Fountain Ditch and Drainage District No. 17, Ark.(MR- 
&T) 42-2, 42-20 
Belle Fourche, Belle Fourche River, S. Dak. (MRO) 21-20 
Belle Fourche, Cheyenne River, S. Dak. (MRO) 21-22 
Belle River, Mich. (NCE) 31-55, 31-56 
Belleville Locks and Dam, Ohio (ORD) 22-1, 22-2, 22-8 
Bellevue, Ky. (ORL) 24-33, 24-38 
Bellingham Harbor, Wash. (NPS) 38-26, 38-27 
Belpre, Ohio (ORH) 25-25, 25-31 
Belton Lake, Tex. (SWF) 16-6, 16-19, 16-22, 16-24 
Beltzville Lake, Pa. (NAP) 3-14, 3-21 
Belzoni, Miss. (MR&T) 42-57 
Benbrook Lake, Tex. (SWF) 16-7, 16-19, 16-26 
Bennett-McDonald-Smithland D. D., Little Sioux River, Iowa 
(MRO) 21-21 
Bennington Reservoir, N.H. (NED) 1-76 
Bennington, Vt. (NAN) 2-47 
Benson Creek Area, Ky. (ORL) 24-338 
Benwood, W. Va. (ORP) 26-28, 26-31 
Beresford Creek, S. C. (SAN) 7-16 
Berkeley Harbor, Calif. (SPN) 34-21 
Berlin Lake, Ohio (ORP) 26-4, 26-19, 26-29 
Berrien County Shore, St. Joseph, Mich. (NCE) 31-25 
Berwick Bay Bridge, Alteration of (LMN) 11-53 
Berwick Lock, La. (LMN) 11-50 
Bethel Small Boat Harbor, Alaska (NPA) 40-2, 40-11, 40-13 
Bethlehem, Pa. (NAP) 3-17, 3-28 
Bettendorf, Iowa (NCR) 28-2, 28-8, 28-10 
Betterton Harbor, Md. (NAB) 4-37. 
Beverly Harbor, Mass. (NED) 1-65, 1-66 
Big and Colewa Creek, La. (MR&T) 42-52 
Big Bay Harbor, Mich. (NCS) 27-3, 27-23 
Big Bayou, Ark. (MR&T) 42-53 
Big Bend Dam-Lake Sharpe, S. Dak. (MRO) 21-10, 21-15, 21- 
19 
Big Bend Reservoir, W. Va. (ORH) 25-27, 25-32 
Big Black River, Miss. (LMK) 12-11, 12-12 
Big Blue Lake, Ind. (ORL) 24-4, 24-24, 24-37 
Big Blue River, Seward, Nebr. (MRK) 20-33 
Big Brown Creek, Miss. (SAM) 10-17 
Big Choctaw Bayou, La. (LMK) 12-12 
Big Creek and L'Anguille River, Ark. (LMM) 13-9 
Big Creek Canal, Millington, Tenn. (LMM) 13-4, 13-7, 13-8 
Big Creek and Tributaries, Ark (MR&T) 42-2, 42-54, 42-58 
Big (Cunningham) Creek, Ohio (NCB) 32-42 , 
Big Darby Reservoir, Ohio (ORH) 25-27, 25-32 
Big Dry Creek Dam and Diversion, Calif. (SPK) 35-22, 35-34 
Big Fossil Creek, Tex. (SWF) 16-7, 16-19, 16-26 
Big Hill Lake, Kans. (SWT) 19-7, 19-25, 19-30 
Big Hog Intake Bayou, Wallisville, Tex. (SWG) 15-16 
Big Hole River, Mont. (MRO) 21-20 
Big Horn River, Mont. (MRO) 21-20 
Big Lake Drainage and Levee District, Ill. (NCC) 30-41, 30-42 
Big Pigeon and Little Pigeon Bayous, La. (LMN) 11-53 
Big Pine Lake, Ind. (ORL) 24-4, 24-24 
Big Pine Lake, Tex. (SWT) 19-7, 19-25, 19-30 
Big Prairie Drainage and Levee District, Ill. (NCC) 30-42 
Big Run, Pa. (ORP) 26-30, 26-31 
Big Sandy Lake, Tex. (SWF) 16-22, 16-25 
Big Sandy River, W. Va. and Ky., including Levisa and Tug 
Forks (ORH) 25-24, 25-27 
Big Sioux River at Sioux City, Iowa and S. Dak. (MRO) 21-3, 
21-14 
Big Sipux River, Near Flandreau, S. Dak. (MRO) 21-20 
Big Sioux River, S. Dak. and Iowa (MRO) 21-18 
Big Slough and Mayo Ditch (MR&T) 42-57 
Big South Fork National River and Recreation Area, Ky., and 
Tenn. (ORN) 23-10 
Big Stone Lake and Whetstone River, Minn. and S. Dak. 
(NCS) 27-11, 27-25 
Big Stranger Creek, Kans. (MRK) 20-32, 20-33 
Big Suamico River, Wis. (NCC) 30-2, 30-22 
Big Sunflower River, Miss. (LMK) 12-11 
Big Sunflower River, Miss. (LMK) (MR&T) 12-11, 42-1, 2-2, 
42-9, 42-19, 42-52, 42-58 
Big Swan Drainage and Levee District, Ill. (LMS) 14-19 
Big Timber Creek, N.J. (NAP) 3-26 
Big Walnut Lake, Ind. (ORL) 24-4, 24-24, 24-37 
Big Walnut Reservoir, Ohio (ORH) 25-29 
Big Wash, Milford, Utah (SPK) 35-22, 35-34 
Billings, Mont. (MRO) 21-3, 21-14 
Biloxi Harbor, Miss. (SAM) 10-4, 10-26, 10-31 
Binghamton, N.Y. (NAB) 4-16, 4-28, 4-40, 4-41 
Birch Hill Dam, Mass. (NED) 1-24, 1-50, 1-61, 1-71 
Birch Lake, Okla. (SWT) 19-8, 19-25, 19-30 
Birch Reservoir, W, Va, (ORH) 25-27, 25-29, 25-32 
1-4

INDEX 
Bird Rock Area, LaJolla, Calif. (SPL) 33-31 
Birds Point - New Madrid Floodway, Mo. (MR&T) 42-54 
Biscayne Bay, Fla., Hurricane Protection (SAJ) 9-51 
Bitterroot River, Wash. (NPS) 38-11 
Black Bayou Lake, La. (LMN) 11-56, 11-57 
Black Bayou-Pine Island Area, La. (LMN) 11-57 
Black Butte Lake, Calif. (SPK) 35-19 
Black Creek, Gadsden, Ala. (SAM) 10-17, 10-41 
Black Creek Reservoir, N. C. (SAW) 6-31 
Black Fork at Hendricks, W. Va. (ORP) 26-31 
Black Hawk Creek, Davenport, Iowa (NCR) 28-11 
Black Pond Slough, Ark. (MR&T) 42-53 
Black River, Ark. and Mo. (SWL) 18-20 
Black River, La. (MR&T) 42-2, 42-17 
Black River (Alcona Co.) Mich. (NCE) 31-56 
Black River, Mich. (NCE) 31-3 
Black River, N.C. (SAW) 6-13, 6-25, 6-29 
Black River, Poplar Bluff, Mo. to Knobel, Ark. (SWL) 18-24 
Black River, Port Huron, Mich. (NCE) 31-3, 31-36, 31-44 
Black River, Wis. (NCS) 27-31 
Black River, Harbor, N.Y. (NCB) 32-42 
Black River, Harbor, Mich. (NCS) 27-3, 27-23 
Black Rock Channel and Tonawanda Harbor, N.Y. (NCB) 
32-2, 32-26, 32-31 
Black Rock Lake, Conn. (NED) 1-32, 1-52, 1-62, 1-73 
Black Walnut Harbor, Md. (NAB) 4-37 
Black Warrior and Tombigbee Rivers, Ala. (SAM) 10-4, 10- 
26, 10-31, 10-38 
Blackbird Creek, Near Macy, Nebr. (MRO) 21-22 
Blackfoot Area, Snake River, Idaho (NPW) 39-16, 39-18 
Blackfoot Reservoir, Idaho (NPW) 39-1, 39-12, 39-14 
Bla-kfoot River, Idaho (NPW) 39-16, 38-18 
Blackstone, Mass. (NED) 1-44 
Blackstone River Basin, Mass. and R.I. (NED) 1-20, 1-44, 1- 
70 
Blackwater Dam, N.H. (NED) 1-35, 1-52, 1-63, 1-74 
Blackwater River, Fla. (SAM) 10-40 
Blackwater River, Va. (NAO) 5-4, 5-19, 5-22 
Blaine Harbor, Wash. (NPS) 38-26, 38-27 
Blakely Mountain Dam-Lake Ouachita, Ark. (LMK) 12-4, 12- 
8, 12-12 
Blieders Creek Lake, Tex. (SWF) 16-22 
Blind Slough Diking District, Oreg. (NPP) 37-53 
Block Island, Great Salt Pond, R.I. (NED) 1-65, 1-66 
Block Island Harbor of Refuge, R.I. (NED) 1-65, 1-66 
Bloomington Lake, Md. and W. Va. (NAB) 4-12, 4-27, 4-34 
Blue and Delaware Rivers, Kans. (MRK) 20-32 
Blue Marsh Lake, Pa. (NAP) 3-15, 3-21 
Blue Mountain Lake, Ark. (SWL) 18-2, 18-4, 18-12, 18-18, 
18-21 
Blue River Basin (MRK) 20-26 
Blue River Channel, Kansas City, Mo. (MRK) 20-3, 20-22 
Blue River Lake, Oreg. (NPP) 37-17, 37-34, 37-42, 37-49, 37- 
51 
Bluestone Lake, W. Va. (ORH) 25-4, 25-20, 25-27 
Bluff Creek, Miss. (SAM) 10-40 
Board of Engineers for Rivers and Harbors (BERH) 41-1 
Bobo Bayou, Miss. (MR&T) 42-52 
Bodega Bay, Calif. (SPN) 34-1, 34-15 
Bodie Island, N. C. (SAW) 6-32 
Boeuf and Tensas Rivers and Bayou Macon, La. and Ark. 
(MR&T) 42-2, 42-8, 42-17, 42-52 
Boeuf River, La. (LMK) 12-11 
Boeuf River, La. and Ark. (MR&T) 42-17, 42-52, 42-56, 42- 
57 
Bogue Chitto, La. (SAM) 10-40 
Boise Valley, Idaho (NPW) 39-16, 38-18 
Bolles Harbor, Mich. (NCE) 31-4, 31-36, 31-44 
Bon Secour River, Ala. (SAM) 10-39, 10-40 
Bonnet Carre Spillway, La. (MR&T) 42-1, 42-7, 42-55, 42-56 
Bonneville Lock and Dam-Lake Bonneville Oreg. and Wash. 
(NPP) 37-24, 37-35, 37-44, 37-57 
Bonneville, Oreg. (NPP) 37-59 
Bonpas Creek, Ill. (ORL) 24-33 
Bonum Creek, Va. (NAB) 4-37 
Boone County, Ky. (Bank Protection & Repair Roads) (ORL) 
24-5 
Booneville Lake, Ky. (ORL) 24-5, 24-24, 24-36 
Boothbay Harbor, Maine (NED) 1-65, 1-66 
Boston Harbor, Mass. (NED) 1-3, 1-46, 1-55, 1-65 
Boswell Lake, Okla. (SWT) 19-36, 19-38 
Boulder, Colo. (MRO) 21-4, 21-14 
Boundary Waters Boards, International 48-2 
Bowman-Haley Lake, N. Dak. (MRO) 21-4, 21-14 
Brackenridge, Tarentum, and Natrona, Pa. (ORP) 26-28, 26- 
31 
Bradford, Pa. (ORP) 26-30, 26-31 
Bradley Lake, Alaska (NPA) 40-9, 40-12, 40-14 
Bramwell, W. Va. (ORH) 25-30 
Brandon Road Lock and Dam, Ill. (NCC) 30-8, 30-37, 30-38 
Branford Harbor, Conn. (NED) 1-3, 1-46, 1-56, 1-65 
Branson Cove, Va. (NAB) 4-37 
Brant Rock Beach, Marshfield, Mass. (NED) 1-69 
Braymer Lake, Mo. (MRK) 20-33 
Brays Bayou Channel, Houston, Tex. (SWG) 15-16 
Brazil (Big Walnut Creek), Ind. (ORL) 24-43 
Brazos Island Harbor, Tex. (SWG) 15-2, 15-17, 15-21, 15-33, 
15-34, 15-40 
Brazos River and Tributaries, Tex. (SWF) 16-24 
Brazos River, Tex. from Velasco to Old Washington (SWG) 
15-32 
Brazos River Basin, Texas (SWF) (SWL) 16-7, 18-15, 18-22 
Brazos River Floodgates, Tex. (SWG) 15-7 
Brazos River and Tributaries, Tex. (SWF) 16-24 
Brea Dam, Calif. (SPL) 33-17, 33-36 
Breton Bay, Md. (NAB) 4-37 
Brevard County, Fla. (SAJ) 9-16, 9-27, 9-35 
Brevoort Levee, Ind. (ORL) 24-38, 24-42 
Bridge Alterations, Authorized 
Chicago, Ill., District (NCC) 30-40 
Nashville, Tenn., District (ORN) 23-5 
New England Division (NED) 1-19 
Portland, Oreg., District (NPP) 37-48 
Bridgeport Harbor, Conn. (NED) 1-4, 1-46, 1-56, 1-65 
Bridgewater, Va. (NAB) 4-44 
Brilliant, Ohio (ORP) 26-28, 26-31 
Bristol Harbor, R.I. (NED) 1-66 
Broad Creek, Md. (NAB) 4-37 
Broad Creek, N. C. (SAW) 6-20, 6-32 
Broad Creek, Va. (NAO) 5-26, 5-27 
Broad Creek River, Del. (NAB) 4-37 
Broadkill River, Del. (NAP) 3-3, 3-19 
Broadwater Creek, Md. (NAB) 4-37 
Broadway Lake, S. C. (SAS) 8-16 
Brockway, Pa. (ORP) 26-28, 26-31 
Brockway Lake, Vt. (NED) 1-71, 1-76 
Broken Bow, Mud Creek, Nebr. (MRO) 21-21 
Broken Bow Lake, Okla. and Ark. (SWT) 19-21, 19-28, 19- 
35, 19-36 
Bromley, Ky. (ORL) 24-33, 24-38 
Bronx River, N.Y. (NAN) 2-44, 2-45 
Brookfield Lake, Mo. (MRK) 20-3, 20-22 
Brooklyn, W. Va. (ORH) 25-25, 25-31 
Brookport, Ill. (ORL) 24-33, 24-38, 24-42 
1-5

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Brookville, Pa. (ORP) 26-30, 26-31 
Brookville Lake, Ind. (ORL) 24-5, 24-24, 24-36 
Broward County, Fla., Beach Erosion Control and Hillsboro 
Inlet, Fla., Navigation Project (SAJ) 9-17, 9-27, 9-35 
Brown, Clarence J., Dam and Reservoir, Ohio (ORL) 24-9, 
24-25 
Browns Creek, N.Y. (NAN) 2-2, 2-32, 2-36, 2-44 
Brownsville, Wash. (NPS) 38-27 
Brownwood Channel Improvement, Tex. (SWF) 16-22 
Bruces Eddy (Dworshak) Dam and Reservoir, Idaho (NPW) 
39-6, 39-12, 39-14 
Brunswick County Beaches, N. C., Cape Fear to N. C.-S. C. 
State Line (SAW) 6-13, 6-25 
Brunswick Harbor, Ga. (SAS) 8-3, 8-11, 8-13 
Brush Bayou, La. (LMN) 11-27, 11-39, 11-47 
Buchanan Dam-H. V. Eastman Lake, Calif. (SPK) 35-4, 35-25 
Buck Creek, N. C. and S. C. (SAN) 7-17 
Buckhannon River, W. Va. (ORP) 26-27 
Buckhannon, W. Va. (ORP) 26-30, 26-31 
Buckhorn Lake, Ky. (ORL) 24-6, 24-24, 24-36 
Buckhorn Reservoir, N. C. (SAW) 6-31 
Buckman, Henry H., Lock, Fla. (SAJ) 9-37 
Bucks Harbor, Maine (NED) 1-4, 1-46, 1-57 
Bucksport Harbor, Maine (NED) 1-65, 1-66 
Buena Vista, Ohio (ORH) 25-25, 25-31 
Buena Vista, Va. (NAO) 5-17, 5-21, 5-24 
Buffalo Bayou Rectified Channel, Tex. (SWG) 15-16 
Buffalo Bayou and Tributaries, Tex. (SWG) 15-12, 15-16, 15- 
18, 15-30, 15-41 
Buffalo Creek, Meadow Grove, Nebr. (MRO) 21-22 
Buffalo Creek, Scranton, N. Dak. (MRO) 21-22 
Buffalo Harbor, N.Y. (NCB) 32-3, 32-26, 32-32 
Buffalo River, Miss. (LMK) 12-12 
Buffumville Lake, Mass. (NED) 1-41, 1-53, 1-64, 1-75 
Bull Shoals Lake, Ark. (SWL) 18-7, 18-9, 18-13, 18-22, 18-23 
Bullocks Point Cove, R.I. (NED) 1-66 
Bunker Harbor, Maine (NED) 1-65, 1-66 
Burch Creek, Utah (SPK) 35-34 
Burgettstown, Pa. (ORP) 26-31 
Burgettstown-Slovan, Pa. (ORP) 26-30 
Burial Hill Beach, Westport, Conn. (NED) 1-20, 1-69 
Burlington Dam, N. Dak. (NCS) 27-12, 27-25 
Burlington Harbor, Vt. (NAN) 2-45 
Burlington, Ohio (ORH) 25-25, 25-31 
Burns Stream, Calif. (SPK) 35-16 
Burns Waterway Harbor, Ind. (NCC) 30-2, 30-22 
Burnsville Lake, W. Va. (ORH) 25-5, 25-20, 25-27 
Burr Oak, Mich. (NCE) 31-30 
Bush, Alvin R., Dam, Pa. (NAB) 4-21, 4-29, 4-43 
Butler, Pa. (ORP) 26-30, 26-31 
Buttermilk Bay Channel, Mass. (NED) 1-66 
Buttermilk Channel, N.Y. (NAN) 2-45 
Byram River at Pemberwick, Conn. (NAN) 2-47 
C 
Cache River Basin, Ark. (MR&T) 42-2, 42-11, 42-20, 42-29, 
42-54, 42-55 
Cache River Diversion, Ill. (LMS) 14-19 
Caddo Lake, La. (LMN) 11-28, 11-39, 11-48, 11-55 
Cadet Bayou, Miss. (SAM) 10-39, 10-40 
Cadle Creek, Md. (NAB) 4-37 
Caesar Creek Lake, Ohio (ORL) 24-6, 24-24, 24-36 
Cagles Mill Lake, Ind. (ORL) 24-6, 24-24, 24-36 
Cahaba River, Ala. (SAM) 10-40 
Cairo and Mound City, Ill. (MR&T) 42-2, 42-21 
Cairo, W. Va. (ORH) 25-30 
Calapooia River, Oreg. (NPP) 37-55 
Calaveras River and Littlejohn Creek and Tributaries 
Including New Hogan Lake and Farmington Dam, Calif. 
(SPK) 35-5, 35-25 
Calcasieu Lock, La. (LMN) 11-12, 11-51 
Calcasieu River and Pass, La. (LMN) 11-7, 11-37, 11-43, 11- 
50 
Calcasieu River at Coon Island, La. (LMN) 11-8, 11-37, 11-43 
Calcasieu River at Devil's Elbow, La. (LMN) 11-9, 11-37, 11- 
43 
Calcasieu River Saltwater Barrier, La. (LMN) 11-53 
Caledonia, N.Y. (NCB) 32-44 
Calf Pasture Beach Park, Norwalk, Conn. (NED) 1-20, 1-69 
Calico Rock, Ark. (SWL) 18-7, 18-23 
California Branch, S. C. (SAN) 7-17 
California (Cincinnati), Ohio (ORL) 24-33, 24-38 
Caliin, Ark. (LMK) 12-10, 12-12 
Calumet Harbor and River, Ill. and Ind. (NCC) 30-3, 30-22, 
30-26, 30-33 
Calumet River Bridges, Ill. (NCC) 30-40 
Camas Creek, Idaho (NPW) 39-16 
Cambridge Harbor, Md. (NAB) 4-36, 4-37 
Cambridgeport Lake, Vt. (NED) 1-71, 1-76 
Camden Harbor, Maine (NED) 1-65, 1-66 
Camelsback Dam, Ariz. (SPL) 33-37 
Camp Ground Lake, Ky. (ORL) 24-7, 24-24 
Camp Perry, Ohio (NCE) 31-57 
Campbells Island, Ill. (NCR) 28-12 
Campti-Clarence Area in Natchitoches Parish, La. (UU-K) 5, 
11-57 
Canal 18, Ark. (MR&T) 42-52 
Canal 19, Ark. (MR&T) 42-53 
Canal 43, Ark. (MR&T) 42-53 
Canal 81, Ark. (MR&T) 42-53 
Canapitsit Channel, Mass. (NED) 1-66 
Canaveral Harbor, Fla. (SAJ) 9-3, 9-25, 9-29, 9-37 
Candy Lake, Okla. (SWT) 19-8, 19-25, 19-30 
Cane River, La. (LMN) 11-53 
Caney Bayou, Ark. (MR&T) 42-53 
Caney Fork River, Tenn. (ORN) 23-17 
Canisteo, N.Y. (NAB) 4-16, 4-28, 4-41 
Cannelton, Ind. (ORL) 24-33, 24-38, 24-42 
Cannelton Locks and Dam, Ind. (ORD) 22-1, 22-2, 22-3, 22-9 
Cannon, Clarence, Dam and Reservoir, Mo. (LMS) 14-11, 14- 
14, 14-16 
Canton Lake, Okla. (SWT) 19-8; 19-25, 19-32, 19-35 
Canton, Mass. (NED) 1-44, 1-76 
Canton, Mo. (NCR) 28-12 
Canton, Okla. (SWL) 18-2, 18-18 
Canyon Lake, Tex. (SWF) 16-8, 16-19 
Cape Charles City Harbor, Va. (NAO) 5-26, 5-27 
Cape Cod Canal, Mass. (NED) 1-4, 1-46, 1-57 
Cape Fear River Basin, N. C. (SAW) 6-13, 6-31 
Cape Fear River, N. C., Above Wilmington (SAW) 6-4, 6-23 
Cape Florida State Park, Fla. (SAJ) 9-43 
Cape Girardeau, Mo., Reach No. 2 (LMS) 14-19 
Cape Girardeau, Mo., Reaches Nos. 1, 3, and 4 (LMS) 14-19 
Cape Henry Channel, Va. (NAO) 5-4, 5-22 
Cape Lookout, N. C. (SAW) 6-30 
Cape May City, N.J. (NAP) 3-27 
Cape Porpoise Harbor, Maine (NED) 1-65, 1-66 
Cape Vincent Harbor, N.Y. (NCB) 32-4, 32-26, 32-33 
Captain Anthony Meldahl Locks and Dam, Ky. (ORD) 22-1, 
22-2, 22-3, 22-8 
Carbon Canyon Dam and Channel, Calif. (SPL) 33-17, 33-36 
I-6

INDEX 
Carden's Bottom Drainage District No. 2, Ark. (SWL) 18-24 
Carl L. Estes Dam and Lake, Tex. (SWF) 16-8, 16-9, 16-25 
Carlyle Lake, Ill. (LMS) 14-5, 14-13, 14-17 
Carlyle to New Athens Drainage and Levee Districts Nos. 3, 
4, 8, 10, and 13 (LMS) 14-17 
Carolina Beach and Vicinity, N. C. (SAW) 6-15, 6-20, 6-25 
Carr Fork Lake, Ky. (ORL) 24-7, 24-24, 24-36 
Carrabelle Harbor, Fla. (SAM) 10-39, 10-40 
Carroll County Levee and Drainage District, No. 1, Ill. (NCR) 
28-12 
Carrollton, Ky. (ORL) 24-33, 24-38 
Carters Creek, Va. (NAO) 5-27 
Carters Dam and Lake, Ga. (SAM) 10-18, 10-28, 10-42 
Carthage Dam, Tenn. (ORN) 23-2 
Carthage Levee, Mo. (SWT) 19-37, 19-38 
Carvers Harbor, Vinalhaven, Maine (NED) 1-66 
Cascadia Lake, Oreg. (NPP) 37-17, 37-34, 37-43, 37-51 
Cascadilla Creek, Ithaca, N.Y. (NCB) 32-44 
Caseville, Harbor Mich. (NCE) 31-5, 31-36, 31-44, 31-55 
Caseyville, Ky. (ORL) 24-33, 24-38 
Cashie River, N. C. (SAW) 6-29 
Cassidy Bayou, Miss. (MR&T) 42-52 
Castle Rock, Wash. (NPP) 37-55 
Castlewood Lake, Cherry Creek and Tributaries, Colo. 
(MRO) 21-22 
Catching Inlet Drainage District, Oreg. (NPP) 37-55 
Cathance River, Maine (NED) 1-66 
Catherine Creek Lake, Oreg. (NPW) 39-2, 39-12, 39-14 
Catlettsburg, Ky. (ORH) 25-25, 25-30, 25-31 
Cattaraugus Creek, N.Y. (NCB) 32-42 
Cattaraugus Harbor, N.Y. (NCB) 32-5, 32-26 
Cave-in Rock, Ill. (ORL) 24-33, 24-38 
Cave Run Lake, Ky. (ORL) 24-8, 22-25, 22-36 
Cecil M. Harden Lake, Ind. (ORL) 24-8, 22-25 
Cedar Bayou, Tex. (SWG) 15-2, 15-17, 15-21, 15-33, 15-34 
Cedar Keys Harbor, Fla. (SAJ) 9-40, 9-41 
Cedar Point Lake, Kans. (SWT) 19-8, 19-25, 19-30 
Cedar River Harbor, Mich. (NCC) 30-40 
Cedar River, Wash. (NPS) 38-11 
Cedars Lock and Dam, Wis. (NCC) 30-36 
Celina Dam, Ky. (ORN) 23-2, 23-14, 23-19 
Center Hill Lake, Tenn. (ORN) 23-6, 23-10, 23-18 
Central and Southern Florida (SAJ) 9-20, 9-28, 9-35, 9-44, 9- 
45, 9-46, 9-47, 9-48, 9-49 
Central City Lake, Iowa (NCR) 28-12 
Ceredo-Kenova, W. Va. (ORH) 25-25, 25-30, 25-31 
Chambersburg, Ohio (ORH) 25-25, 25-31 
Champlain-Richelieu Board, International 48-5 
Champlain-Richelieu Engineering Board, International 48-4 
Chandlerville, Ill., East Of, (ORH) (NCC) 30-42 
Channel between North and South Hero Island, Vt. (NAN) 
2-45 
Channel Connecting Plain Dealing Creek and Oak Creek, 
Md. (NAB) 4-37 
Channel Connecting Thoroughfare Bay With Cedar Bay, N. 
C. (SAW) 6-5, 6-23 
Channel Connecting York River, Va., With Back Creek to 
Slaights Wharf (NAO) 5-27 
Channel from Back Sound to Lookout Bight, N. C. (SAW) 6- 
5, 6-23, 6-28 
Channel from Naples to Big Marco Pass 12-Foot Channel, 
Gordon Pass to Naples, Fla. (SAJ) 9-40, 9-41 
Channel from Pamilco Sound to Rodanthe, N. C. (SAW) 6-6, 
6-23 
Channel from Phoebus, Va., to Deep Water in Hampton 
Roads (NAO) 5-27 
Channel Improvements, New Orleans District (MR&T) 42-51 
Channel Islands Harbor, Calif. (SPL) 33-2, 33-21, 33-25 
Channel to Aransas Pass, Tex. (SWG) 15-38 
Channel to Barroom Bay, Tex. (SWG) 15-38 
Channel to Harlingen Via South Turnout, Tex. (SWG) 15-39 
Channel to Liberty, Tex. (SWG) 15-10 
Channel to Newport News, Va. (NAO) 5-8, 5-23 
Channel to Palacios, Tex. (SWG) 15-38 
Channel to Port Bolivar, Tex. (SWG) 15-32 
Channel to Port Mansfield, Tex. (SWG) 15-38 
Channel to Rockport, Tex. (SWG) 15-38 
Channel to Victoria, Tex. (SWG) 15-16, 15-38 
Channels in the Straits of Mackinac, Mich. (NCE) 31-56 
Charenton Canal (MR&T) 42-51, 42-56 
Chariton-Little Chariton Basins, Mo. (MRK) 20-3, 20-22 
Chariton River, Iowa and Mo. (MRK) 20-32 
Chariton River, Mo. (MRK) 20-32, 20-33 
Charles River Dam, Mass. (NED) 1-21, 1-50, 1-61 
Charles River (Natural Valley Storage Areas), Mass. (NED) 1- 
22, 1-50, 1-61 
Charleston Harbor, S. C. (SAN) 7-3, 7-11, 7-13 
Charlestown, N.H. (NED) 1-24, 1-50, 1-61, 1-72 
Charlevoix Harbor, Mich. (NCE) 31-5, 31-36, 31-44 
Charlotte Harbor, Fla. (SAJ) 9-3, 9-25, 9-29 
Chartiers Creek, Pa. (ORP) 26-4, 26-19, 26-30 
Chatfield Lake, Colo. (MRO) 21-4, 21-14 
Chatham (Stage) Harbor, Mass. (NED) 1-66 
Chattanooga, Tenn. and Rossville, Ga. (ORN) 23-18 
Chattooga Units (4), Ga., and S. C. (SAS) 8-16 
Cheat River, W. Va. (ORP) 26-27 
Cheatham Lock and Dam, Tenn. (ORN) 23-2, 23-14, 23-19 
Cheboygan Harbor, Mich. (NCE) 31-55, 31-56 
Cheesequake Creek, N.J. (NAN) 2-44, 2-45 
Chefuncte River and Bogue Falia, La. (LMN) 11-53 
Chehalis River and Grays Harbor, Wash. (NPS) 38-3, 38-16, 
38-20 
Chehalis River, Wash. (NPS) 38-25 
Chena River Lakes, Alaska (NPA) 40-7, 40-12, 40-14 
Cherry and Red Fork Creeks, Okla. (SWT) 19-37, 19-38 
Cherry Creek Lake, Colo. (MRO) 21-5, 21-14, 21-16 
Cherry Valley Reservoir, Calif. (SPK) 35-14 
Cherryfield, Maine (NED) 1-44, 1-76 
Chesapeake, Ohio (ORH) 25-25, 25-31 
Chesconessex Creek, Va. (NAO) 5-26, 5-27 
Cheshire, Ohio (ORH) 25-25, 25-31 
Chester, Calif. (SPK) 35-6, 35-25 
Chester, Pa. (NAP) 3-17 
Chester River, Md. (NAB) 4-4, 4-26, 4-32 
Chester River, Pa. (NAP) 3-26 
Chetco River, Oreg. (NPP) 37-2, 37-32, 37-38 
Chicago, Ill. (NCC) 30-41 
Chicago Harbor, Ill. (NCC) 30-4, 30-22, 30-26, 30-33 
Chicago River, Ill. (NCC) 30-4, 30-32, 30-26 
Chicago River, Ill. (North Branch) (NCC) 30-18, 30-25 
Chickamauga, Tenn. (ORN) 23-16 
Chico Landing, Sacramento River, Calif. (SPK) 35-30 
Chicopee Falls, Mass. (NED) 1-25, 1-44, 1-50, 1-61, 1-72 
Chicopee, Mass. (NED) 1-44, 1-72, 1-76 
Chief Joseph Dam and Rufus Woods Lake, Wash. (NPS) 38- 
12, 38-18, 38-23 
Chillicothe, Ohio (ORH) 25-5, 25-20, 25-30 
Chilo, Ohio (ORH) 25-25, 25-31 
Chincoteague Bay, Va. (NAO) 5-26, 5-27 
Chincoteague Harbor of Refuge, Va. (NAO) 5-5, 5-19, 5-22, 
5-26 
Chincoteague Inlet, Va. (NAO) 5-23, 5-27 
Chino Canyon Improvements, Palm Springs, Calif. (SPL) 33- 
38 
I-7

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Chippewa Harbor, Mich. (NCS) 27-31 
Chittenango Creek and Tributaries, N.Y. (NCB) 32-44 
Chocolate Bayou Channel, Tex. (SWG) 15-38 
Choctaw Bayou and Tributaries, La. (LMN) 11-28, 11-40, 11- 
48 
Choctawhatchee Bay to Pensacola Bay, Fla. (SAM) 10-33 
Choctawhatchee Bay to West Bay, Fla. (SAM) 10-33 
Choptank River, Md. (NAB) 4-5, 4-26, 4-32 
Chouteau Lock and Dam, Okla. (SWL) (SWT) 18-2, 18-17, 
19-4, 19-32, 19-35 
Chouteau, Nameoki, and Venice Drainage and Levee District, 
Ill. (LMS) 14-19 
Chowan River, N.C. (NAO) (SAW) 5-5, 5-19, 5-22, 6-29 
Christiansted Harbor, V.I. (SAJ) 9-40, 9-41 
Cincinnati, Ohio (ORL) 24-33, 24-38, 24-42 
Cincinnati (Unit 2), Ohio (ORL) 24-33, 24-38 
Cincinnati (Unit 4 Remainder), Ohio (ORL) 24-33, 24-38 
City Creek Levee, Calif. (SPL) 33-37 
Clackamas River at Dixon Farm Location, Oreg. (NPP) 37-55 
Claiborne Harbor, Md. (NAB) 4-37 
Claiborne Lock and Dam, Ala. (SAM) 10-18, 10-19, 10-28, 
10-42 
Clanton, Ala. (SAM) 10-17, 10-41 
Claremont Lake, N.H. (NED) 1-71, 1-78 
Clarence Cannon Dam and Reservoir, Mo. (LMS) 14-11, 14- 
14, 14-16 
Clarence J. Brown Dam and Reservoir, Ohio (ORL) 24-9, 24- 
25 
Clarendon Levee, Ark. (MR&T) 42-57, 42-58 
Clarendon to Laconia Circle, Ark. (LMM) 13-9 
Clarington, Ohio (ORP) 26-28, 26-31 
Clark Fork River, Mont. (NPS) 
Clark Hill Lake, Ga., and S. C. (SAS) 8-9, 8-11, 8-15, 8-16 
Clark Point, New Bedford, Mass. (NED) 1-69 
Clarkson, Maple Creek, Nebr. (MRO) 21-21, 21-22 
Clarksville, Ark. (SWL) 18-24 
Clatskanie Drainage District, Oreg. (NPP) 37-50, 37-54 
Clatskanie River, Oreg. (NPP) 37-46, 37-47, 37-54 
Clatsop County Drainage District 1, Oreg. (NPP) 37-50, 37- 
53, 37-54 
Clatsop County Diking District 2, Oreg. (NPP) 37-53 
Clatsop County Diking District 3, Oreg. (NPP) 37-53 
Clatsop County Diking District 4, Oreg. (NPP) 37-50, 37-54 
Clatsop County Diking District 5, Oreg. (NPP) 37-53 
Clatsop County Diking District 6, Oreg. (NPP) 37-50, 37-54 
Clayton Lake, Okla. (SWT) 19-9, 19-25, 19-36 
Clear Creek, Tex. (SWG) 15-12, 15-18, 15-30 
Clear Creek and Clear Lake, Tex. (SWG) 15-32 
Clear Creek Drainage and Levee District, Ill. (LMS) 14-19 
Clear Lake Special Drainage District, Ill. (NCC) 30-41, 30-42 
Clearwater Lake, Mo. (SWL) 18-5, 18-12, 18-21, 18-22 
Clearwater Pass, Fla. (SAJ) 9-40, 9-41 
Clearwater River, Minn. (NCS) 27-33 
Clendenin Reservoir, W. Va. (ORH) 25-29 
Cleveland and Lakewood, Ohio (NCB) 32-43 
Cleveland Harbor, Ohio (NCB) 32-6, 32-26, 32-33 
Cleves, Ohio (ORL) 24-33, 24-38 
Cliff Walk, Newport, R.I. (NED) 1-20, 1-69 
Clifton, W. Va. (ORH) 25-25, 25-31 
Clifty Creek Lake, Ind. (ORL) 24-9, 24-25 
Clinch River, Tenn. and Va. (ORN) 23-16 
Clinton Harbor, Conn. (NED) 1-6, 1-46, 1-57, 1-65 
Clinton Harbor, Iowa (NCD) 29-2, 29-8 
Clinton, Ind. (ORL) 24-33, 24-38 
Clinton, Iowa (NCR) 28-2, 28-8, 28-10 
Clinton Lake, Kans. (MRK) 20-4, 20-22 
Clinton River, Mich. (NCE) 31-5, 31-37, 31-44 
Clopton Crossing, Tex. (SWF) 16-22 
Cloverport, Ku. (ORL) 24-33, 24-38, 24-43 
Clyde Park, Mont. (MRO) 21-20 
Clyde, R.I. (NED) 1-78 
Coal Creek and Tributaries (Lake City), Tenn. (ORN) 23-18 
Coal Creek Drainage and Levee District, Ill. (NCC) 30-41, 30- 
42 
Coal Grove, Ohio (ORH) 25-25, 25-29, 25-31 
Coal River Basin, W. Va. (ORH) 25-5, 25-20 
Coan River, Va. (NAB) 4-37 
Coast of California, Point Mugu to San Pedro Breakwater, 
Calif. (SPL) 33-31 
Coastal Engineering Research Center (CERC) 43-1 
Coasters Island Harbor, R.I. (NED) 1-66 
Cobscook Bay, Maine (NED) 1-66 
Cocheco River, N.H. (NED) 1-66, 1-76 
Cochiti Lake, N. Mex. (SWA) 17-11, 17-16, 17-19, 17-20 
Cochrane, Wis. (NCD) 29-3 
Cockrells Creek, Va. (NAO) 5-27 
Coeur D'Alene, Idaho (NPS) 38-28 
Coeur D'Alene River, Idaho (NPS) 38-11 
Coffeeville Lock and Dam, Ala. (SAM) 10-38 
Coffeyville Levee, Kans. (SWT) 19-37 
Cohansey River, N.J. (NAP) 3-3, 3-19, 3-22 
Cohasset Harbor, Mass. (NED) 1-65, 1-66 
Cold Brook Lake, S. Dak. (MRO) 21-5 
Cold Spring Inlet, N.J. (NAP) 3-4, 3-19, 3-22 
Cold Water River, Miss. (MR&T) 42-52 
Colebrook River Lake, Conn. (NED) 1-25, 1-50, 1-61, 1-71 
Colfax, La. (LMN) 11-56, 11-57 
Colfax, Wash. (NPW) 39-17, 39-18 
Collection and Removal of Drift 
Baltimore, Md., District (NAB) 4-4, 4-7, 4-26, 4-32, 4-33 
New York, N.Y., District (NAN) 2-12, 2-33, 2-38 
Norfolk, Va., District (NAO) 5-7, 5-20, 5-23 
Colliers, W. Va. (ORP) 26-30 
Collinsville, Ala. (SAM) 10-17, 10-41 
Collinsville, Calif. (SPK) 35-30 
Colonial Beach, Va. (NAB) 4-39 
Colorado River Channel, Tex. (SWG) 15-38 
Colorado River Locks, Tex. (SWG) 15-7 
Colorado River, Matagorda, Tex. (SWG) 15-16, 15-32 
Colorado River, Mouth of (SWG) 15-38 
Colorado Springs, Colo. (SWA) 17-20 
Columbia and Lower Willamette Rivers below Vancouver, 
Wash., and Portland, Oreg. (NPP) 37-2, 37-32, 37-38, 
37-45 
Columbia Drainage and Levee District No. 3, Ill.(L MS) 14-3, 
14-13, 14-15 
Columbia Drainage District 1, Oreg. (NPP) 37-50, 37-54 
Columbia, La. (LMK) 12-10, 12-12 
Columbia River and Tributaries above Celilo Falls to 
Kennewick, Wash. (NPW) 39-16 
Columbia River at Baker Bay, Wash. (NPP) 37-4, 37-32, 37- 
39 
Columbia River at the Mouth, Oreg. and Wash. (NPP) 37-4, 
37-32, 37-39 
Columbia River Basin Local Flood Protection Projects, Oreg., 
Wash. And Idaho (NPW) 39-3, 39-12, 39-14, 39-16 
Columbia River Basin, Local Protection Projects, Idaho, 
Mont., and Wash. (NPS) 38-28 
Columbia River Basin, Wash. and Oreg. (NPP) 37-53 
Columbia River Between Chinnook, Wash. and Head of Sand 
Island (NPP) 37-47 
Columbia River Between Vancouver, Wash., and The Dalles, 
Oreg. (NPP) 37-5, 37-32, 37-39 
I-8

INDEX 
Columbia River, Wenatchee to Kettle Falls, Wash. (NPS) 38- 
27 
Columbia River Treaty Entities 48-22 
Columbia River Treaty Permanent Engineering Board 48-23 
Columbia Slough, Oreg. (NPP) 37-47 
Columbus, Nebr. (MRO) 21-21 
Columbus, Ohio (ORH) 25-29, 25-31 
Colusa, Calif. (SPK) 35-30 
Community of Eldred, Ill. (LMS) 14-19 
Community of Meredosia and Willow Creek, and Coon Run 
Drainage and Levee Districts, Ill. (LMS) 14-19 
Compo Beach, Westport, Conn. (NED) 1-20, 1-69 
Conant Brook Dam, Mass. (NED) 1-26, 1-50, 1-61, 1-71 
Conchas Lake, N. Mex. (SWA) 17-5, 17-16 
Concordia, Ky. (ORL) 24-33, 24-38 
Conemaugh River Lake, Pa. (ORP) 26-5, 26-19, 26-29 
Conetoe Creek, N. C. (SAW) 6-32 
Coney Island Channel, N.Y. (NAN) 2-44 
Coney Island Creek, N.Y. (NAN) 2-45 
Coney Island Inlet, N.Y. (NAN) 2-45 
Congaree River, S. C. (SAN) 7-16 
Conklin-Kirkwood, N.Y. (NAB) 4-44 
Conneaut Harbor, Ohio (NCB) 32-7, 32-26, 32-34 
Connecticut River above Hartford, Conn. (NED) 1-66 
Connecticut River Basin, Vt., N.H., Mass. and Conn. (NED) 
1-23, 1-44, 1-71 
Connecticut River Below Hartford, Conn. (NED) 1-6, 1-46, 1- 
57, 1-65 
Connell, Wash. (NPW) 39-21 
Conoho Creek, N. C. (SAW) 6-32 
Contentnea Creek, N. C. (SAW) 6-29, 6-32 
Conway County Drainage and Levee District No. 1, Ark. 
(SWL) 18-24 
Conway County Levee Districts Nos. 1, 2, and 8, Ark. (SWL) 
18-24 
Conway County Levee District No. 6, Ark. (SWL) 18-24 
Cook Inlet Shoals, Alaska 40-2, 40-11, 40-13 
Cooper Lake and Channels, Tex. (LMN) 11-28, 11-40, 11-48, 
11-55 
Cooper River, Charleston Harbor, S. C. (SAN) 7-3, 7-11, 7-13 
Cooper River, N.J. (NAP) 3-26 
Coordinating Committee on Great Lakes Basic Hydraulic and 
Hydrologic Data 48-13 
Coos and Millicoma Rivers, Oreg. (NPP) 37-7, 37-32, 37-40 
Coos Bay, Oreg. (NPP) 37-6, 37-32, 37-39 
Coos River, Catching Inlet Drainage District, Oreg. 
Copan Lake, Okla. (SWT) 19-9, 19-25, 19-30 
Copes Corner Lake, N.Y. (NAB) 4-40, 4-41, 4-44 
Coquille River, Oreg. (NPP) 37-7, 37-32, 37-40, 37-55 
Coralville Lake, Iowa (NCR) 28-2, 28-8, 28-10 
Coraopolis, Pa. (ORP) 26-28, 26-31 
Corbin, Ky. (ORN) 23-18 
Corbin, Lynn Camp Creek, Ky. (ORN) 23-18 
Cordell Hull Lock and Dam, Tenn. (ORN) 23-2, 23-14, 23-19 
Cordova Harbor, Alaska (NPA) 40-15 
Core Creek, N. C. (SAW) 6-20, 6-32 
Corea Harbor, Maine (NED) 1-65, 1-66 
Corning, N.Y. (NAB) 4-17, 4-28, 4-41 
Cornucopia Harbor, Wis. (NCS) 27-4, 27-23, 27-27 
Corpus Christi Beach, Tex. (Restoration Project) (SWG) 15- 
11, 15-18, 15-29 
Corpus Christi Ship Channel, Tex. (SWG) 15-3, 15-17, 15-21, 
15-33, 15-34, 15-40 
Corpus Christi, Tex., Channel to Navy Seaplane Base, 
Encinal Peninsula (SWG) 15-32 
Corsica River, Md. (NAB) 4-37 
Corte Madera Creek, Calif. (SPN) 34-12, 34-16, 34-20 
Cortland, N.Y. (NAB) 4-42, 4-43, 4-44 
Cottage Grove Lake, Oreg. (NPP) 37-17, 37-34, 37-43, 37-49, 
37-51 
Cottonwood Creek, Calif. (SPK) 35-34 
Cottonwood Creek Dam, Idaho (NPW) 39-18 
Cottonwood Slough Pumping Plant, Ill. (LMM) 13-9 
Cottonwood Springs Lake, S. Dak. (MRO) 21-5 
Cotuit Harbor, Mass. (NED) 1-66 
Cougar Lake, Oreg. (NPP) 37-25, 37-35, 37-44, 37-49, 37-51 
Council Bluffs, Iowa (MRO) 21-19, 21-21, 21-22 
Council Grove Lake, Kans. (SWT) 19-9, 19-26, 19-35 
Courtableau Basin, La. and Outlets (MR&T) 42-16 
Courtenay Channel, Fla. (SAJ) 9-41 
Cove Island, Stamford, Conn. (NED) 1-20, 1-69 
Covington, Ky. (ORL) 24-33, 24-38, 24-42 
Cow Creek, Kans. (SWT) 19-38 
Cowanesque Lake, Pa. (NAB) 4-20, 4-29, 4-42 
,Cowden to Vandalia Drainage and Levee Districts Nos. 22, 
27, 28, And 28A (LMS) 14-17 
Cowlitz County Consolidated Diking Improvement District 1, 
Wash. (NPP) 37-50, 37-53, 37-54 
Cowlitz County Consolidated Diking Improvement District 
No. 2, 37-18, 37-34, 37-43, 37-50 
Cowlitz County Diking Improvement District 2, Wash. (NPP) 
37-50, 37-54, 37-54 
Cowlitz County Diking Improvement District 5, Wash. (NPP) 
37-53 
Cowlitz County Diking Improvement District 11, Wash. (NPP) 
37-54 
Cowlitz County Diking Improvement District 13, Wash. (NPP) 
37-50, 37-54 
Cowlitz County Diking Improvement District 15, Wash. (NPP) 
37-50, 37-54 
Cowlitz River at Randle, Wash. (NPP) 37-55 
Cowlitz River Basin, Wash. (NPP) 37-54 
Cowlitz River, Wash. (NPP) 37-8, 37-32, 37-40 
Cowpens Swamp, S. C. (SAN) 7-17 
Coyote Creek, Calif. (SPN) 34-22, 34-23 (SPL) 33-13, 33-33, 
33-34 
Coyote & Spencer Creeks, Long Tom River, Oreg. (NPP) 37- 
55 
Coyote Valley Dam (Lake Mendocino), Calif. (SPN) 34-13, 34- 
17, 34-22 
Crabtree Swamp, S. C. (SAN) 7-17 
Craig Harbor, Alaska 
Crane Creek Drainage and Levee District (NCC) 30-41, 30-42 
Crane Creek State Park, Ohio (NCE) 31-25 
Cranes Creek, Va. (NAO) 5-26, 5-27 
Crawford County Levee District, Ark. (SWL) 18-24 
Creede, Willow Creek, Colo. (Floodway) (SWA) 17-20 
Crescent City Harbor, Calif. (SPN) 34-2, 34-15, 34-18 
Criehaven Harbor, Maine (NED) 1-66 
Crisfield Harbor, Md. (NAB) 4-37 
Crooked Creek, Lake and Levee, Ark. (SWL) 18-24 
Crooked Creek Lake, Pa. (SWL) (ORP) 26-6, 26-19, 26-29 
Cross County Project Ditch, Ark. (MR&T) 42-54 
Cross-Florida Barge Canal (SAJ) 9-3, 9-25, 9-29, 9-37, 9-38 
Cross Rip Shoals, Mass. (NED) 1-66 
Cross Village, Mich. (NCE) 31-56 
Crutcho Creek, Okla. (SWT) 19-38 
Crystal River, Fla. (SAJ) 9-40, 9-41 
Cucamonga Creek, Calif. (SPL) 33-9, 33-22, 33-27 
Cuckold Creek, Md. (NAB) 4-37 
Cuivre River, Mo. (LMS) 14-17 
Cumberland, Ky. (ORH) 25-17 (ORN) 23-10, 23-17 
Cumberland, Md., and Ridgeley, W. Va. (NAB) 4-13, 4-27, 4- 
34 
I-9

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Cumberland River Above Nashville (ORN) 23-2, 23-12 
Cumberland River Below Nashville (ORN) 23-2, 23-12 
Cumberland River, Ky., South Fork (ORN) 23-17 
Cumberland River, Tenn. and Ky. (ORN) 23-1, 23-10, 23-14 
Cummings Park, Stamford, Conn. (NED) 1-20, 1-69 
Cunninghill Cove, Md. (NAB) 4-37 
Current River, Ark. and Mo. (SWL) 18-20 
Curry Creek Dam and Lake, Ga. (SAS) 8-16 
Curwensville Lake, Pa. (NAB) 4-22, 4-29, 4-43 
Cuttyhunk Harbor, Mass. (NED) 1-6, 1-46, 1-57 
Cypress Bayou and Waterway Between Jefferson, Tex. and 
Shreveport, La. (LMN) 11-53 
Cypress Creek, Ky. (ORL) 24-33, 24-43 
Cypress Creek, Md. (NAB) 4-37
D 
Dade County, Fla. (SAJ) 9-17, 9-27, 9-35 
Dakota, Minn. (NCD) 29-2 
Dale Hollow Lake, Tenn. and Ky. (ORN) 23-7, 23-10, 23-18 
Dallas Floodway, Tex. (SWF) 16-3, 16-5, 16-26 
Dam a Lake, Tex. (SWF) 16-22, 16-23 
Damariscotta River, Maine (NED) 1-66 
Dana Point Harbor, Calif. (SPL) 33-30 
Danbury, Conn. (NED) 1-32, 1-52, 1-63, 1-73 
Dansville and Vicinity, N.Y. (NCB) 32-44 
Dardanelle, Ark., Near (SWL) 18-24 
Dardanelle Lock and Dam, Ark. (SWL) 18-2, 18-9, 18-13, 18- 
16 
Dardanelle Marine Terminal, Ark. (SWL) 18-2 
Darien Harbor, Ga. (SAS) 8-4, 8-11, 8-13 
Dashields Locks and Dam, Pa. (ORD) 22-1, 22-2, 22-3, 22-7 
Dauphin Island Bay, Ala. (SAM) 10-6, 10-26, 10-32 
Davenport Center Lake, N.Y. (NAB) 4-40, 4-41, 4-44 
Davenport Harbor, Iowa (Credit Island) (NCD) 29-8 
Davenport Harbor, Iowa (Lindsay Park) (NCD) 29-2, 29-8 
Davenport, Iowa (NCD) 29-8 (NCR) 28-3, 28-8, 28-10 
David-Burrell Bayou, Miss. (MR&T) 42-52 
David D. Terry Lock and Dam, Ark. (SWL) 18-2, 18-3, 18-16 
Davids Creek Lake, Iowa (MRO) 21-22 
Davis Creek, Va. (SAW) (NAO) 5-26, 5-27 
Davis Lock, Mich. (NCE) 31-54 
Day, John, Lock and Dam-Lake Umatilla, Oreg. and Wash. 
(NPP) 37-27, 37-35, 37-44, 37-57 
Day, John, River, Oreg. (NPP) 37-53 
Day, John, River Area, Oreg. (NPP) 37-53 
Days Creek Lake, Oreg. (NPP) 37-18, 37-34, 37-43 
Dayton, Ky. (ORL) 24-9, 24-25 
Dayton, Wash. (NPW) 39-17, 39-18 
Dayton, Wyo. (MRO) 21-22 
Deauthorized Projects 
New England Division (NED) 1-78 
Decorah, Iowa (NCS) 27-33 
Deep Creek, Accomack Co., Va. (NAO) 5-26, 5-26 
Deep Creek, Newport News, Va. (NAO) 5-6, 5-19, 5-22 
Deep River, Wash. (NPP) 37-46, 37-47 
Deep River Area, Wash. (NPP) 37-53 
Deer Creek, Miss. (MR&T) 42-2, 42-20, 42-52 
Deer Creek, Okla. (SWT) 19-38 
Deer Creek Lake, Ohio (ORH) 25-6, 25-20, 25-27 
Deer Creek Prairie Levee, Ind. (ORL) 24-33, 24-38 
Deer Island Area, Oreg. (NPP) 37-53 
Deer Island Drainage District, Oreg. (NPP) 37-50, 37-54 
Deer Island Thoroughfare, Maine (NED) 1-66 
Degognia and Fountain Bluff Levee and Drainage District, Ill. 
(LMS) 14-19 
Degray Lake, Ark. (LMK) 12-4, 12-8, 12-12 
Delaware Bay - Chesapeake Bay Waterway, Del., Md., and 
Va (NAP) (NAO) 3-4, 3-19, 5-6, 5-19, 5-22 
Delaware Coast Protection, Del. (NAP) 3-15, 3-21 
Delaware Lake, Ohio (ORH) 25-6, 25-20, 25-27 
Delaware River at Camden, N.J. (NAP) 3-4, 3-19 
Delaware River Between Philadelphia, Pa. and Trenton, N.J. 
(NAP) 3-5, 3-19, 3-22, 3-25 
Delaware River, Kans., Mouth of (MRK) 20-32 
Delaware River, N.Y., N.J., and Pa. at or Near Mouth of 
Neversink River (NAP) 3-5, 3-19, 3-22, 3-25, 3-26 
Delaware River, Pa., N.J. and Del., Philadelphia to the Sea 
(NAP) 3-6, 3-19, 3-23, 3-25 
Delphi, Ind. (ORL) 24-33, 24-38, 24-42 
Demopolis Lock and Dam, Ala. (SAM) 10-5, 10-38 
Denison Dam-Lake Texoma, Tex. and Okla. (SWT) 19-21, 
19-28, 19-35, 19-39 
Dennis Creek, N.J. (NAP) 3-26 
DePere Lock and Dam, Wis. (NCC) 30-36 
Depoe Bay, Oreg. (NPP) 37-46, 37-47 
Dequeen Lake, Ark. (SWT) 19-10, 19-26, 19-36 
Derby, Conn. (NED) 1-33, 1-44, 1-52, 1-63, 1-73 
Derby, Ind. (ORL) 24-33, 24-38 
Des Moines and Mississippi Levee District No. 1, Mo. (NCR) 
28-12 
Des Moines, Iowa (NCR) 28-11, 28-12 
DesArc, Ark. (MR&T) 42-2, 42-20, 42-56 
Deschutes River, Wash. (NPS) 38-11 
Desoto, Kans., Bridge Protection (MRK) 20-32 
Detroit Lake, Oreg. (NPP) 37-26, 37-35, 37-44, 37-49, 37-51 
Detroit River, Mich. (NCE) 31-6, 31-37, 31-44, 31-53 
DeValls Bluff, Ark. (MR&T) 42-2, 42-20, 42-56 
Devil, East Twin, and Warm Creeks Channel Improvements 
and Lytle Creek Levee, Calif. (SPL) 33-37 
Dewey Lake, Ky. (ORH) 25-7, 25-20, 25-27 
Dexter Lake, Oreg. (NPP) 37-28 
Dickey-Lincoln School Lakes, Maine (NED) 1-39, 1-53, 1-64, 
1-78 
Dickinson Bayou, Tex. (SWG) 15-32 
Dierks Lake, Ark. (SWT) 19-10, 19-26, 19-35, 19-36 
Dillingham Harbor, Alaska (NPA) 40-2, 40-11, 40-13, 40-15 
Dillon Lake, Ohio (ORH) 25-7, 25-20, 25-27 
Dillonvale, Ohio (ORP) 26-28, 26-31 
Dismal Swamp Canal, Deep Creek, Va. (NAO) 5-25 
Dismal Swamp Canal, South Mills, N.C. (NAO) 5-25 
Dively Drainage and Levee District No. 23, Ill. (LMS) 14-7, 
14-14, 14-17 
Dodge City, Kans. (SWA) 17-6, 17-16, 17-18 
Dog and Fowl Rivers, Ala. (SAM) 10-6, 10-26, 10-32 
Doheny Beach State Park, Calif. (SPL) 33-31 
Don Pedro Reservoir, Calif. (SPK) 35-14 
Donovan Creek, Miss. (SAM) 10-17 
Donovan Levee, Ill. (NCC) 30-42 
Dorchester Bay and Neponset River, Mass. (NED) 1-66 
Dorena Lake, Oreg. (NPP) 37-19, 37-34, 37-43, 37-49, 37-51 
Dosh, R. N. Bert, Lock, Fla. (SAJ) 9-37 
Double Bayou, Tex. (SWG) 15-32 
Double Creek, N.J. (NAP) 3-26 
Douglas Harbor, Alaska (NPA) 40-15 
Douglass Lake, Kans. (SWT) 19-38 
Dover, Ky. (ORH) 25-25, 25-31 
Downeyville, Ind. (ORL) 24-37 
Dresden Island Lock and Dam, Ill. (NCC) 30-8, 30-37, 30-38 
Drum Inlet, N. C. (SAW) 6-6, 6-23 
Drury Drainage District, Ill. (NCR) 28-11, 28-12 
I-10

INDEX 
Dry Creek, Hawarden, Iowa (MRO) 21-22 
Dry Creek (Warm Springs) Lake and Channel, Calif. (SPN) 
34-13, 34-17, 34-22 
Dry Fork and East Fork Lakes, Mo. (MRK) 20-33 
Dry Pass, Alaska (NPA) 40-15 
Dry Run, Iowa (NCS) 27-34 
DuBois, Pa. (ORP) 26-6, 26-19 
Dubuque Harbor, Iowa (NCD) 29-2, 29-8 
Dubuque, Iowa (NCR) 28-11, 28-12 
Duck Creek, Calif. (SPK) 35-22, 35-34 
Duck Creek Channel Improvement, Tex. (SWF) 16-8, 16-19 
Duck Island Anchorage, (NED) 1-65 
Duck Island Harbor, Conn. (NED) 1-66 
Duck Point Cove (Hearns Creek), Md. (NAB) 4-37 
Duck River, Tenn. (ORN) 23-17 
Duluth-Superior Harbor, Minn. and Wis. (NCS) 27-4, 27-23, 
27-27 
Dungeness River, Wash. (NPS) 38-28 
Dunkirk Harbor, N.Y. (NCB) 32-8, 32-26, 32-35 
Dunn Branch, Woodbine, Ga. (SAS) 8-7, 8-11, 8-14 
Dunnellon Lock, Fla. (SAJ) 9-37 
Duval County, Fla. (SAJ) 9-18, 9-27, 9-35 
Duxbury Harbor, Mass. (NED) 1-65, 1-66 
Dworshak (Bruces Eddy) Reservoir Dam and Idaho (NPW) 
39-6, 39-12, 39-14, 39-19 
Dyersburg, Tenn. (Southwest) (LMM) (LMN) 13-3, 13-7, 13- 
8, 13-9 
Dymers Creek, Va. (NAO) 5-26, 5-27 
E 
Eagle Bay and Fort Yates Highway Bridges, N. Dak. (MRO) 
21-11, 21-15 
Eagle Creek Lake, Ky. (ORL) 24-10, 24-25 24-36 
Eagle Creek Reservoir, Ohio (ORP) 26-29, 26-31 
Eagle Harbor, Mich. (NCS) 27-31 
East Barre Dam, Vt. (NAN) 2-47 
East Bay Bayou (Hanna Reef), Tex. (SWG) 15-32 
East Boothbay Harbor, Maine (NED) 1-66 
East Branch, Clarion River Lake, Pa. (ORP) 26-7, 26-19, 26- 
29 
East Branch Dam, Conn. (NED) 1-44, 1-73, 1-76 
East Branch, N.Y. (NAP) 3-17 
East Brimfield Lake, Mass.'(NED) 1-42, 1-54, 1-64, 1-75 
East Cape Girardeau and Clear Creek Drainage District, III. 
(LMS) 14-19 
East Chester Creek, N.Y. (NAN) 2-3, 2-32, 2-36, 2-44 
East Fork Lake, Ohio (ORL) 24-10, 24-25, 24-36 
East Hartford, Conn. (NED) 1-44, 1-72, 1-76 
East Liverpool Drainage and Levee District, Ill. (NCC) 30-41, 
30-42 
East Lynn Lake, W. Va. (ORH) 25-7, 25-20, 25-27 
East Moline, Ill. (NCR) 28-3, 28-8, 28-10 
East Muddy Creek, Mo. (MRK) 20-33 
East Muddy and Lake Creek, Oreg. (NPP) 37-55 
East Nishnabotna River, Red Oak, Iowa (MRO) 21-22 
East Pass Channel from Gulf of Mexico Into Choctawhatchee 
Bay, Fla. (SAM) 10-7, 10-26, 10-32 
East Pearl River, Miss. (SAM) 10-39, 10-40 
East Peoria Drainage and Levee District, Ill. (NCC) 30-41, 30- 
42 
East Peoria Sanitary District, Ill. (NCC) 30-41 
East Point, La. (LMN) 11-55, 11-57 
East Poplar Bluff and Poplar Bluff, Mo. (SWL) 18-24 
East Protection Levee, La. (MR&T) 42-14 
East Rainelle, W. Va. (ORH) 25-30, 25-31 
East River, N.Y. (NAN) 2-3, 2-32, 2-36, 2-44 
East Rockaway Inlet, N.Y. (NAN) 2-4, 2-32, 2-36 
East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, N.Y. 
(Pt. I) (NAN) 2-17, 2-34, 2-40 
(Pt. II) (NAN) 2-19, 2-34, 2-40 
East Rockwood, Silver Creek, Mich. (NCE) 31-30 
East Sidney Lake, N.Y. (NAB) 4-17, 4-28, 4-40, 4-41 
East St. Louis and Vicinity, Ill. 
East Weaver Creek, Calif. (SPN) 34-23 (LMS) 14-3, 14-13, 14- 
15 
Eastern Rapides and South-Central Avoyelles, La. (MR&T) 
42-1, 42-17, 42-29, 42-58 
Eastlake, Ohio (NCB) 32-20, 32-29 
Eastman, H. V., Lake-Buchanan Dam, Calif. (SPK) 35-3, 35- 
25 
Easton-Saxton, Mo., Bridge Protection (MRK) 20-32 
Eastport Harbor, Maine (NED) 1-66 
Eau Galle River, Wis. (NCS) 27-12, 27-25 
Eau Gallie Harbor, Fla. (SAJ) 9-40, 9-41 
Echo Bay Harbor, N.Y. (NAN) 2-45 
Edenton Harbor, N. C. (SAW) 6-28, 6-29 
Edgartown Harbor, Mass. (NED) 1-7, 1-47, 1-58 
Edgewater Park, Ohio (NCB) 32-43 
Edinburg Lake, Miss. (SAM) 10-15, 10-28, 10-36 
Edisto River, S. C. (SAN) 7-16, 7-17 
Ediz Hook, Wash. (NPS) 38-8, 38-17, 38-22 
Edmonds Harbor, Wash. (NPS) 38-27 
Edward MacDowell Lake, N.H. (NED) 1-35, 1-53, 1-63, 1-74 
Edwardsport, Ind. (ORL) 24-43 
Eel River, Calif. (SPN) 34-23 
Eel River, Ind. (ORL) 24-33, 24-38 
Egegik River, Alaska (NPA) 40-15 
El Dorado, Kans. (SWT) 19-11, 19-26 
El Dorado Lake, Kans. (SWT) 19-10, 19-26, 19-30 
El Paso, Tex. (SWA) 17-7, 17-16, 17-18 
Elba, Ala. (SAM) 10-17 
Eldred, Pa. (ORP) 26-30 
Eldred and Spankey Drainage and Levee District, Ill. (LMS) 
14-19 
Elfin Cove, Alaska (NPA) 40-15 
Elizabeth, N.J. (NAN) 2-20, 2-34, 2-40 
Elizabeth River, N.J. (NAN) 2-45 
Elizabethtown, Ill. (ORL) 24-33, 24-38 
Elk and Little Elk Rivers, Md. (NAB) 4-37 
Elk City, Kans. (SWL) 18-2, 18-18 
Elk City Lake, Kans. (SWT) 19-11, 19-26, 19-32, 19-35 
Elk Creek, Clyde, Kans. (MRK) 20-4, 20-22, 20-32 
Elk Creek, Pa. (NCB) 32-42 
Elk Creek Lake, Oreg. (NPP) 37-19, 37-34, 37-43 
Elk River, Ala. and Tenn. (ORN) 23-17 
Elk River, Minn. (NCS) 27-33, 27-34 
Elk River, W. Va. (ORH) 25-24 
Elkhorn River, Near Gretna, Nebr. (MRO) 21-21 
Elkhorn River Near Norfolk, Nebr. (MRO) 21-21 
Elkins, W. Va. (ORP) 26-7, 26-19, 26-28 
Elkland, Pa. (NAB) 4-42, 4-43, 4-44 
Elkport, Iowa (NCR) 28-11, 28-12 
Ellerbe Creek, N. C. (SAW) 6-20, 6-32 
Ellicott Creek, N.Y. (NCB) 32-20, 32-29 
Ellis Swamp, N. C. (SAW) 6-20, 6-32 
Elm Fork Floodway, Tex. (SWF) 16-9, 16-19, 16-26 
Elmira, N.Y. (NAB) 4-18, 4-28, 4-41 
Elochoman Slough, Wash. (NPP) 37-46, 37-47 
Emergency Bank Protection Activities 
Albuquerque, N. Mex., District (SWA) 17-15 
Baltimore, Md., District (NAB) 4-23 
I-11

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Buffalo, N.Y., District (NCB) 32-25 
Huntington, W. Va., District (ORH) 25-33 
Kansas City, Mo., District (MRK) 20-18 
Little Rock, Ark., District (SWL) 18-9 
Louisville, Ky., District (ORL) 24-41 
Memphis, Tenn., District (LMM) 13-5 
New England Division (NED) 1-44 
Omaha, Nebr., District (MRO) 21-10 
Sacramento, Calif., District (SPK) 35-22 
San Francisco, Calif., District (SPN) 34-14 
Seattle, Wash., District (NPS) 38-29 
St. Paul, Minn., District (NCS) 27-35 
Tulsa, Okla., District (SWT) 19-21 
Vicksburg, Miss., District (LMK) 12-6 
Emergency Flood Control Activities 
Alaska District (NPA) 40-8 
Albuquerque, N. Mex., District (SWA) 17-15 
Baltimore, Md., District (NAB) 4-45 
Charleston, S.C., District (SAN) 7-9 
Chicago, Ill., District (NCC) 30-43 
Detroit, Mich., District (NCE) 31-31 
Fort Worth, Tex., District (SWF) 16-17 
Galveston, Tex., District (SWG) 15-16 
Jacksonville, Fla., District (SAJ) 9-24 
Kansas City, Mo., District (MRK) 20-18 
Little Rock, Ark., District (SWL) 18-8 
Los Angeles, Calif., District (SPL) 33-19 
Memphis, Tenn., District (LMM) 13-5 
Mississippi River between Missour/River and Minneapolis, 
Minn. (NCD) 29-2 
Mobile, Ala., District (SAM) 10-42 
New England District (NED) 1-45 
New Orleans, La., District (LMN) 11-58 
New York, N.Y., District (NAN) 2-30 
Omaha, Nebr., District (MRO) 21-10 
Pacific Ocean Division (POD) 36-8 
Philadelphia, Pa., District (NAP) 3-18 
Portland, Oreg., District (NPP) 37-56 
Rock Island, Ill., District (NCR) 28-14 
Sacramento, Calif., District (SPK) 35-22 
San Francisco, Calif., District (SPN) 34-14 
Savannah, Ga., District (SAS) 8-8 
Seattle, Wash., District (NPS) 38-29 
St. Louis, Mo., District (LMS) 14-11 
St. Paul, Minn., District (NCS) 27-35 
Tulsa, Okla., District (SWT) 19-20 
Vicksburg, Miss., District (LMK) 12-13 
Walla Walla, Wash., District (NPW) 39-6 
Wilmington, N.C., District (SAW) 6-20 
Empire and Stratton, Ohio (ORP) 26-28, 26-31 
Emsworth Locks and Dam, Pa. (ORD) 22-1, 22-2, 22-7 
Endicott, Johnson City, and Vestal, N.Y. (NAB) 4-44 
England Pond Levee, Ill. (ORL) 24-33, 24-38, 24-42 
English, Ind. (ORL) 24-38, 24-43 
Enid Diversion Channel and Levee, Okla. (SWT) 19-37, 19-38 
Enid Lake, Miss. (MR&T) 42-9, 42-19, 42-22, 42-57, 42-59 
Entiat River, Wash. (NPS) 38-28 
Erie Harbor, Pa. (NCB) 32-9, 32-27, 32-35 
Escambia and Conecuh Rivers, Ala. and Fla. (SAM) 10-7, 10- 
27, 10-32 
Escanaba, Mich. (NCC) 30-41 
Esquatzel Coulee, Connell, Wash. (NPW) 39-18 
Essex River, Mass. (NED) 1-65, 1-66 
Estes, Carl L., Dam and Lake, Tex. (SWF) 16-8, 16-19, 16-25 
Estral Beach, Mich. (NCE) 31-30 
Eudora Floodway (MR&T) 42-56 
Eufala, Okla. (SWL) 18-2, 18-18 
Eufaula Lake, Okla. (SWL) (SWT) 19-22, 19-28, 19-32, 19-35 
Eureka Lock and Dam (SAJ) 9-37 
Evansdale, Iowa (NCR) 28-12 
Evanston, Ill. (NCC) 30-41 
Evansville, Ind. (ORL) 24-10, 24-25, 24-33, 24-42 
Everett Harbor and Snohomish River, Wash. (NPS) 38-3, 38- 
16, 38-20, 38-25 
Everett Lake, N.H. (NED) 1-36, 1-53, 1-63, 1-74 
Everglades Harbor, Fla. (SAJ) 9-40, 9-41 
Exeter River, N.H. (NED) 1-66 
Experimental Chloride Control Project, Red River Basin, 
Tex. (SWT) 19-6, 19-25 
F 
Fabius River Drainage District, Mo. (NCR) 28-12 
Fair Haven Beach State Park, N.Y. (NCB) 32-43 
Fairbanks, Alaska (NPA) 40-16 
Fairbanks, Tanana River and Chena Slough, Alaska (NPA) 
40-16 
Fairbury, Nebr. (MRK) 20-32, 20-33 
Fairfield Vicinity Streams, Calif. (SPK) 35-6, 35-25 
Fairport Harbor, Ohio (NCB) 32-10, 32-27, 32-36 
Fajardo Harbor, P.R. (SAJ) 9-41 
Fall Brook Lake, Pa. (NAB) 4-39, 4-40, 4-44 
Fall Creek, Ithaca, N.Y. (NCB) 32-44 
Fall Creek Lake, Oreg. (NPP) 37-19, 37-34, 37-43, 37-49, 37- 
51 
Fall River, Kans. (SWL) 18-2, 18-18 
Fall River Basin, S. Dak. (MRO) 21-5, 21-14 
Fall River Harbor, Mass. (NED) 1-7, 1-47, 1-58 
Fall River Lake, Kans. (SWL) (SWT) 19-11, 19-26, 19-32, 19- 
35 
Falls Lake, N. C. (SAW) 6-17, 6-25, 6-31 
Falmouth Harbor, Mass. (NED) 1-65, 1-66 
Falmouth Lake, Ky. (ORL) 24-11, 24-25, 24-36 
Fancy Bluff Creek, Ga. (SAS) 8-15, 8-16 
Far Creek, N. C. (SAW) 6-6, 6-23 
Fargo, N. Dak. (NCS) 27-33 
Farm Creek, Ill. (NCC) 30-18, 30-25 
Farmers Levee and Drainage District, Ill. (NCC) 30-41, 30-42 
Farmington, N.H. (NED) 1-44 
Farmington Dam, Calif. (SPK) 35-5, 35-25 
Faulkner County Levee District No. 1, Ark. (SWL) 18-24 
Feather River, Calif. (SPK) 35:-31 
Federal Water Power Act, Investigations and Supervision of 
Projects under 47-1 
Felsenthal, Ark. (LMK) 12-10 
Felton Ditch, Minn. (NCS) 27-20, 27-26 
Ferguson Creek, Oreg. (NPP) 37-55 
Fern Ridge Lake, Oreg. (NPP) 37-20, 37-34, 37-43, 37-49, 37- 
51 
Fernandina Harbor, Fla..(SAJ) 9-5, 9-25, 9-29 
Ferrells Bridge Dam-Lake O' the Pines, Tex. (ILMN) 11-29, 
11-40, 11-48, 11-54, 11-55 
Filberts Creek, N. C. (SAW) 6-20, 6-32 
Fire Island Inlet, N.Y. (NAN) 2-45 
Fire Island Inlet to Jones Inlet, N.Y. (NAN) 2-18, 2-34, 2-40 
Fire Island Inlet to Montauk Point, N.Y. (NAN) 2-21, 2-34, 2- 
40 
Fisher, O. C., Dam and Lake, Tex. (SWF) 16-13, 16-20 
Fishing Bay, Md. (NAB) 4-37 
Fishing Creek, Md. (NAB) 4-36, 4-37 
Fishing Creek, N. C. (SAW) 6-29 
I-12

INDEX 
Fishing Creek, Pine Grove, W. Va. (ORH) 25-30 
Fishtrap Lake, Ky. (ORH) 25-8, 25-20, 25-27 
Fitchburg, Mass. (NED) 1-44 
Fivemile River Harbor, Conn. (NED) 1-66 
Flannagan, John W., Dam and Reservoir Va. (ORH) 25-9, 25- 
21, 25-27 
Flat Creek, Oreg. (NPP) 37-55 
Flat Rock Creek, Tulsa, Okla. (SWT) 19-12, 19-26 
Flathead River, Mont. (NPS) 38-11, 38-27 
Fleschmans, Bayou, Ark. (MR&T) 42-52 
Fletcher and Sunshine Garden Levee, Ind. (ORL) 24-33, 24- 
38 
Flint, Mich. (NCE) 31-30 
Flood Control, Mississippi River and Tributaries (MR&T) 42- 
56 
Flood Control and Coastal Emergency Activities 
Buffalo, N.Y., District (NCB) 32-25 
Huntington, W. Va., District (ORH) 25-19 
Louisville, Ky., District (ORL) 24-23 
Nashville, Tenn., District (ORN) 23-6 
Pittsburgh, Pa., District (ORP) 26-18 
Flood Plain Studies Completed during Fiscal Year 
Alaska District (NPA) 40-16 
Baltimore, Md., District (NAB) 4-45 
Buffalo, N.Y., District (NCB) 32-44 
Charleston, S.C., District (SAN) 7-18 
Chicago, Ill., District (NCC) 30-43 
Fort Worth, Tex., District (SWF) 16-27 
Galveston, Tex., District (SWG) 15-42 
Jacksonville, Fla., District (SAJ) 9-51 
Little Rock, Ark., District (SWL) 18-24 
Los Angeles, Calif., District (SPL) 33-39 
Louisville, Ky., District (ORL) 24-44 
Mobile, Ala., District (SAM) 10-44 
Nashville, Tenn., District (ORN) 23-19 
New England Division (NED) 1-78 
New York, N.Y., District (NAN) 2-48 
Pacific Ocean Division (POD) 36-14 
Pittsburgh, Pa., District (ORP) 26-33 
Portland, Oreg., District (NPP) 37-60 
Rock Island, Ill., District (NCR) 28-15 
Sacramento, Calif., District (SPK) 35-35 
San Francisco, Calif., District (SPN) 34-24 
Savannah, Ga., District (SAS) 8-17 
Seattle, Wash., District (NPS) 38-30 
St. Paul, Minn., District (MCS) 27-36 
Tulsa, Okla., District (SWT) 19-39 
Wilmington, N.C., District (SAW) 6-33 
Floodwall Levees, Portland, Oreg. (NPP) 37-51, 37-55 
Florence, Colo. (SWA) 17-3, 17-17 
Florence Levee, Kans. (SWT) 19-37, 19-38 
Floyd River, Sioux City, Iowa (MRO) 21-22 
Flushing Bay and Creek, N.Y. (NAN) 2-44, 2-45 
Fly Creek, Ala. (SAM) 10-39, 10-40 
Follansbee, W. Va. (ORP) 26-28, 26-31 
Folsom Lake, Calif. (SPK) 35-34 
Forest Heights, Md. (NAB) 4-44 
Forest River, N. Dak. (NCS) 27-33 
Forestville, Mich. (NCE) 31-56 
Forked Deer River, Tenn., Including South Fork (LMM) 13-9 
Forked Deer River Basin, Tenn. (MR&T) 42-2, 42-11, 42-21 
Forsyth, Mont. (MRO) 21-20, 21-22 
Fort Charters and Ivy Landing Drainage District No. 5, Ill. 
(LMS) 14-19 
Fort Chartres and Ivy Landing Drainage District No.5 and 
Stringtown Drainage and Levee District No. 4, Ill. (LMS) 
14-19 
Fort Gibson Lake, Okla. (SWL) (SWT) 18-18, 19-22, 19-28, 
19-32, 19-35 
Fort Kent, Maine (NED) 1-40, 1-53, 1-64 
Fort Leavenworth, Kans., Bridge Removal (MRK) 20-29 
Fort Loudon, Tenn. (ORN) 23-16 
Fort Macon State Park, N. C. (SAW) 6-30 
Fort Madison Harbor, Iowa (NCD) 29-1, 29-2, 29-3, 29-9 
Fort Myers Beach, Fla. (SAJ) 9-5, 9-25, 9-29 
Fort Randall Dam-Lake Francis Case, S. Dak. (MRO) 21-11, 
21-15, 21-19 
Fort Niagara State Park, N.Y. (NCB) 32-43 
Fort Peck Lake, Mont. (MRO) 21-2, 21-14 
Fort Pierce, Fla. (SAJ) 9-43 
Fort Pierce Harbor, Fla. (SAJ) 9-5, 9-25, 9-29 
Fort Riley, Kans. (MRK) 20-32 
Fort Scott Lake, Kans. (MRK) 20-4, 20-22, 20-31 
Fort Smith, Ark. (SWL) 18-24 
Fort Supply Lake, Okla. (SWT) 19-12, 19-26, 19-36 
Fort Wayne Mechanic St. Dike, Ind. (NCE) 31-30 
Fort Worth Floodway, Tex. (SWF) 16-26 
Fort Worth Floodway (Clear Fork), Tex. (SWF) 16-9, 16-19, 
16-26 
Fort Worth Floodway (West Fork), Tex. (SWF) 16-9, 16-19, 
16-26 
Foster Joseph Sayers Dam, Pa. (NAB) 4-22, 4-29, 4-43 
Foster Lake, Oreg. (NPP) 37-26, 37-35, 37-44, 37-49, 37-51 
Fountain Lake, Colo. (SWA) 17-5, 17-18 
Four River Basins, Fla. (SAJ) 9-22, 9-28, 9-36, 9-49, 9-50 
Fourche Creek, Little Rock, Ark. (SWL) 18-24 
Fourmile Run, Va. (NAB) 4-13, 4-27, 4-35 
Fourpole Creek, huntington, W. Va. (ORH) 25-30 
Fox Point Barrier, R.I. (NED) 1-30, 1-44, 1-51, 1-62 
Fox River, Wis. (NCC) 30-5, 30-22, 30-27, 30-36 
Francis E. Walter Dam, Pa. (NAP) 3-15, 3-21 
Frankenmuth, Mich. (NCE) 31-30 
Frankfort, Kans. (MRK) 20-32, 20-33 
Frankfort, Ky. (ORL) 24-11, 24-25, 24-33, 24-38, 24-42 
Frankfort Harbor, Mich. (NCE) 31-6, 31-37, 31-45 
Franklin, W.P., Lock and Dam, Fla. (SAJ) 9-45 
Franklin Falls Dam, N.H. (NED) 1-36, 1-53, 1-63, 1-74 
Frazer-Wolf Point, Mont. (MRO) 21-6, 21-14 
Frazeysburg Reservoir, Ohio (ORH) 25-27, 25-29, 25-32 
Fredericksburg Dam, Va. (NAO) 5-18 
Freeport, Pa. (ORP) 26-28, 26-31 
Freeport and Vicinity (Hurricane-Flood Protection), Tex. 
(SWG) 15-13, 15-16, 15-19, 15-30 
Freeport Harbor, Tex. (SWG) 15-4, 15-17, 15-23, 15-33, 15- 
34, 15-40 
Freeport, Ill. (NCR) 28-12 
Fremont, Ohio (NCB) 32-21, 32-29 
Frenchboro Harbor, Maine (NED) 1-8, 1-47, 1-58 
French Broad and Little Pigeon Rivers, Tenn. (ORN) 23-17 
Freshwater Bayou, La. (LMN) 11-9, 11-37, 11-44 
Friendly, W. Va. (ORH) 25-25, 25-31 
Friendsville, Md. (ORP) 26-30, 26-31 
Fullerton, Ky. (ORH) 25-25, 25-31 
Fullerton Dam, Calif. (SPL) 33-17, 33-36 
Fulton, Ill. (NCR) 28-3, 28-8, 28-10 
G 
Galax, Va. (ORH) 25-25, 25-30, 25-31 
Galena, Ill. (NCR) 28-11, 28-12 
Galisteo Dam, N. Mex. (SWA) 17-11, 17-16, 17-20 
Gallipolis, Ohio (ORH) 25-25, 25-31 
1-13

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Gallipolis Locks and Dam, W. Va. (ORD) 22-1, 22-2, 22-8 
Galveston Harbor and Channel, Tex. (SWG) 15-5, 15-17, 15- 
23, 15-33, 15-35, 15-40 
Galveston Seawall, Tex. (SWG) 15-16 
Gapway Swamp, N. C. and S. C. (SAN) 7-17 
Gardner, Mass. (NED) 1-44, 1-72, 1-76 
Gardners Creek, N. C. (SAW) 6-20, 6-32 
Garland City, Ark. (LMN) 11-30, 11-40, 11-48, 11-55 
Garnett Lake, Kansas (MRK) 20-31, 20-33 
Garrison Dam-Lake Sakakawea, N. Dak. (MRO) 21-11, 21-15, 
21-19 
Gasconade River, Mo. (MRK) 20-29 
Gastineau Channel, Alaska (NPA) 40-15 
Gaston Dam and Reservoir, Va. and N. C. (SAW) 6-31 
Gate Creek Lake, Oreg. (NPP) 37-51, 37-55 
Gathright Lake, Va. (NAO) 5-16, 5-21, 5-24 
Gauley River, W. Va. (ORH) 25-24 
Gavins Point Dam-Lewis and Clark Lake, Nebr. and S. Dak. 
(MRO) 21-12, 21-15, 21-19 
Gavins Point Dam-Lewis and Clark Lake-Relocation of 
Niobrara, Nebr. (MRO) 21-12, 21-15, 21-19 
Gaysville Lake, Vt. (NED) 1-71, 1-76 
Genegantslet Lake, N.Y. (NAB) 4-44 
General Edgar Jadwin Dam and Reservoir, Pa. (NAP) 3-16, 3- 
21 
General Joe Wheeler Main Lock, Ala. (ORN) 23-4, 23-16 
Geneva, Ala. (SAM) 10-17 
Geneva-On-The-Lake, Ohio (NCB) 32-42 
George W. Andrews Lock and Dam, Ala. and Ga. (SAM) 10- 
21, 10-22, 10-29, 10-37, 10-43 
George, Walter F., Lock and Dam, Ala. and Ga. (SAM) 10-21, 
10-24, 10-29, 10-37, 10-43 
Georges River, Maine (NED) 1-65, 1-66 
Georgetown Harbor, S. C. (SAN) 7-4, 7-11, 7-14 
Gering Valley, Gering Drain and Tributaries, Nebr. (MRO) 
21-21 
Gering Valley, Nebr. (MRO) 22-22 
Gila and Salt Rivers Levee and Channel Improvements, Ariz. 
(SPL) 33-37 
Gila River Basin, Ariz. (SPL) 33-10, 33-22, 33-37 
Giles Creek, Nebr. (MRO) 21-22 
Gill Township Levee Unit, Ind. (ORL) 24-38, 24-42 
Gillham Lake, Ark. (SWT) 19-12, 19-26, 19-36 
Girtys Run, Millvale, Pa. (ORP) 26-7, 26-19 
Glasgow, Mont. (MRO) 21-20, 21-22 
Gleason Creek, Nev. (SPK) 35-7, 35-25 
Glen Cove Creek, N.Y. (NAN) 2-44, 2-45 
Glen Cove Harbor, N.Y. (NAN) 2-45 
Gloucester, Mass. (NED) 1-65 
Gloucester Harbor and Annisquam River, Mass. (NED) 1-66 
Goat Island Reservoir, Ga. and S. C. (SAS) 8-16 
Golconda, Ill. (ORL) 24-33, 24-38, 24-42 
Gold Creek, Alaska (NAP) 3-17 (NPA) 40-8, 40-12, 40-14 
Goldsboro, N. C. (SAW) 6-20, 6-32 
Goleta and Vicinity, Calif. (SPL) 33-37 
Gonzales Lake, Tex. (SWF) 16-22, 16-25 
Gooding Area, Idaho (NPW) 39-17, 39-18 
Goose Creek, Md. (NAB) 4-37 
Gordon's Landing, Vt. (NAN) 9-45 
Goshen Creek, N.J. (NAP) 3-26 
Governor's Run, Md. (NAB) 4-37 
Gowanus Creek Channel, N.Y. (NAN) 2-44, 2-45 
Graham, Newt, Lock and Dam, Okla. (SWL) (SWT) 18-2, 18- 
17, 19-4, 19-32, 19-35 
Grahn, Ky. (ORH) 25-30 
Grand Bayou Pass, La. (LMN) 11-53 
Grand Calumet Lock, Ill. (NCC) 30-37 
Grand Forks, N. Dak. (NCS) 27-33 
Grand Haven Harbor and Grand River, Mich. (NCE) 31-7, 
31-37, 31-45 
Grand Lagoon, Panama City, Fla. (SAM) 10-40 
Grand Marais Harbor, Mich. (NCE) 31-8, 31-37, 31-46 
Grand Marais Harbor, Minn. (NCS) 27-4, 27-23, 27-27 
Grand Prairie-Bayou Meto, Ark. (MR&T) 42-2, 42-18, 42-29 
Grand River, Grandville, Mich. (NCE) 31-57 
Grand River, Lansing, Mich. (NCE) 31-57 
Grand River at Brunswick, Mo. (MRK) 20-32 
Grand River at Salt Creek, Mo. (MRK) 20-32 
Grand Tower Levee Project, Ill. (LMS) 14-18 
Grand Traverse Bay Harbor, Mich. (NCS) 27-5, 27-23 
Grand View Bay, N.Y. (NCB) 32-42 
Grande Ronde Lake, Oreg. (NPW) 39-18 
Grande Ronde Valley, Oreg. (NPW) 39-17, 39-18 
Grandview, Ind. (ORL) 24-33, 24-38 
Granger Dam and Lake, Tex. (SWF) 16-24 
Grant Parish, below Colfax, La. (LMN) 11-56, 11-57 
Grant's Canal, La. (MR&T) 42-18, 42-56 
Granville, Pa. (ORP) 26-30, 26-31 
Grapevine Lake, Tex. (SWF) 16-9, 16-20, 16-26 
Grasse River (Massena), N.Y. (NCB) 32-42 
Grassy Creek, Jackson County, Ind. (ORL) 24-38 
Grays Harbor and Chehalis River, Wash. (NPS) 38-3, 38-16, 
38-20, 38-25 
Grays Landing Lock and Dam (ORP) 26-25 
Grays Reef Passage, Mich. (NCE) 31-56 
Grays River, Wash. (NPP) 37-46, 37-47 
Grayson Lake, Ky. (ORH) 25-9, 25-20 
Great Bend, Kans. (SWA) 17-7, 17-16, 17-18 
Great Chazy River, N.Y. (NAN) 2-45 
Great Falls, Mont. (MRO) 21-6, 21-14 
Great Kills Harbor, N.Y. (NAN) 2-45 
Great Lakes Basic Hydraulic and Hydrologic Data, 
Coordinating Committee on 48-13 
Great Lakes Levels Board, International 48-12 
Great Lakes Study Group, International 48-14 
Great Lakes to Hudson River Waterway, N.Y. (NAN) 2-45 
Great Miami River, Ind. (ORL) 24-36 
Great Pee Dee River, S. C. (SAN) 7-16 
Great Salt Plains Lake, Okla. (SWT) 19-13, 19-26, 19-35 
Great Salt Pond, Block Island, R.I. (NED) 1-65, 1-66 
Great Sodus Bay Harbor, N.Y. (NCB) 32-11, 32-27, 32-36 
Great South Bay, N.Y. (NAN) 2-44, 2-45 
Great Swamp Dam and Reservoir, N. C. (SAW) 6-31 
Green and Barren Rivers, Ky. (ORL) 24-2, 24-24, 24-28, 24- 
30, 24-31, 24-36 
Green Bay Harbor, Wis. (NCC) 30-6, 30-22, 30-27, 30-33 
Green Bay Levee and Drainage District No. 2, Iowa (NCR) 
28-12, 28-13 
Green Bay - Marinette, Wis. (NCC) 30-47 
Green Harbor, Mass. (NED) 1-9, 1-47, 1-58 
Green Island Levee and Drainage District No. 1, Iowa (NCR) 
28-13 
Green Peter-Foster Lakes, Oreg. (NPP) 37-26, 37-35, 37-44, 
37-49, 37-51 
Green River, Wash. (NPS) 38-11 
Green River Lake, Ky. (ORL) 24-12, 24-25, 24-36 
Green Valley Creek, Calif. (SPK) 35-22, 35-34 
Greene, N.Y. (NAB) 4-44 
Greenfield Bayou Levee, Ind. (ORL) 24-12, 24-25, 24-33 
Greenport Harbor, N.Y. (NAN) 2-45 
Greenup, Ky. (ORH) 25-25, 25-29, 25-31 
Greenup Locks and Dam, K.Y. (ORD) (ORP) 22-1, 22-2, 22- 
3, 22-8 (ORH) 25-25, 29-31 
I-14

INDEX 
Greenvale Creek, Va. (NAO) 5-26, 5-27 
Greenville, Tex. (SWF) 16-10, 16-20, 16-25 
Greenville Harbor, Miss. (MR&T) 42-1, 42-30, 42-56, 42-58 
Greenwich Bay, R.I. (NED) 1-66 
Greenwich Harbor, Conn. (NED) 1-66 
Greenwich Point Park, Conn. (NED) 1-69 
Greenwood, Miss. (MR&T) 42-57 
Greenwood, S. Dak., Mo. River (MRO) 21-20 
Greenwood Protection Works, Miss. (MR&T) 42-9, 42-18, 42- 
52 
Greers Ferry Lake, Ark. (SWL) 18-9, 18-13, 18-21, 18-22 
Gregory Drainage District, Mo. (NCR) (NCD) 28-12, 28-13, 
29-2 
Grenada Lake, Miss. (MR&T) 42-9, 42-19, 42-22, 42-57, 42- 
59 
Greybull, Wyo. (MRO) 21-20, 21-22 * 
Griffithsville-Yawkey, W. Va. (ORH) 25-30 
Grove Lake, Kans. (MRK) 20-5, 20-22 
Guadalupe and San Antonio Rivers, Tex. (SWF) 16-10, 16-25 
Guadalupe River (Remove Log Jams), Tex. (SWG) 15-13, 15- 
19, 15-30 
Guadalupe River Levee, Victoria, Tex. (SWG) 15-16 
Guayanes Harbor, P.R. (SAJ) 9-41 
Guilford Harbor, Conn. (NED) 1-9, 1-47, 1-58 
Guilford Point Beach (Jacobs Beach), Guilford, Conn. (NED) 
1-20, 1-69 
Gulf Beach, Milford, Conn. (NED) 1-20, 1-69 
Gulf Intracoastal Waterway Between Apalachee Bay, Fla., and 
Mexican Border (SAM) (LMN) (SWG) 10-7, 10-27, 10-32, 
11-10, 11-38, 11-44, 15-6, 15-16, 15-17, 15-24, 15-33, 15- 
38, 15-40 
Gulf Intracoastal Waterway Between Apalachee Bay, Fla., and 
Mexican Border, Locks (LMN) 11-51 
Gulf Intracoastal Waterway, St. Marks to Tampa Bay, Fla. 
(SAJ) 9-41 
Gulfport Harbor, Miss. (SAM) 10-8, 10-27, 10-33 
Gull Lake, Minn. (NCS) 27-29 
Guntersville, Ala. (ORN) 23-16 
Guttenberg, Iowa (NCS) 27-34 
Guyandot River, W. Va. (ORH) 25-24, 25-27 
Gypsum, Gypsum Creek, Kans. (MRK) 20-5, 20-22 
H 
H. V. Eastman Lake-Buchanan Dam, Calif. (SPK) 35-3, 35-25 
Hackleman Corners Lake, Mo. (MRK) 20-31, 20-33 
Haleiwa Beach, Oahu, Hawaii (POD) 36-14 
Haleiwa Small Boat Harbor, Oahu, Hawaii (POD) 36-2, 36-9, 
36-13 
Halfmoon Bay Harbor, Calif. (SPN) 34-21 
Hall Meadow Brook Dam, Conn. (NED) 1-44, 1-73, 1-76 
Hamburg L-575, Iowa (MRO) 21-21 
Hamlin Beach Harbor, N.Y. (NCB) 32-42 
Hamlin Beach State Park, N.Y. (NCB) 32-18, 32-28 
Hammersley Inlet, Wash. (NPS) 38-27 
Hammond Bay Harbor, Mich. (NCE) 31-8, 31-38, 31-46 
Hammonasset Beach, Madison, Conn. (NED) 1-20, 1-69 
Hammond Lake, Pa. (NAB) 4-20, 4-29, 4-42 
Hammondsport, N.Y. (NCB) 32-44 
Hampton Beach, Hampton, N.H. (NED) 1-20, 1-69 
Hampton Creek, Va. (NAO) 5-26, 5-27 
Hampton Harbor, N.H. (NED) 1-9, 1-47, 1-58 
Hampton Institute, Va. (NAO) 5-7, 5-20, 5-23 
Hampton Roads, Va., Supervision of Harbor of (Prevention 
of Obstructive and Injurious Deposits) (NAO) 5-14, 5-20 
Hampton Roads and Harbors of Norfolk and Newport News, 
Va.-Collection And Removal of Drift (NAO) 5-7, 5-20, 5- 
23 
Hampton Roads, Va. (NAO) 5-8, 5-20, 5-23 
Hana Small Boat Harbor, Maui, Hawaii (POD) 36-13 
Hanalei Bay Small Boat Harbor, Kauai, Hawaii (POD) 36-13 
Hanapepe Bay, Kauai, Hawaii (POD) 36-14 
Hanapepe River, Kauai, Hawaii (POD) 36-8, 36-14 
Hancock Brook Lake, Conn. (NED) 1-33, 1-52, 1-63, 1-73 
Hanging Rock, Ohio (ORH) 25-25, 25-31 
Hannibal, Mo. (NCR) 28-13 
Hannibal Harbor, Mo. (NCD) 29-2, 29-9 
Hannibal Locks and Dam, W. Va. (ORD) 22-1, 22-2, 22-3, 22- 
7 
Hanson, Howard A., Dam, Wash. (NPS) 38-9, 38-17, 38-22 
Harbor Beach, Mich., Harbor of Refuge at (NCE) 31-8, 31- 
38, 31-46 
Harbor of Baltimore, Md., Prevention of Obstructions and 
Injurious Deposits (NAB) 4-5, 4-26, 4-32 
Harbor of Refuge at Harbor Beach, Mich. (NCE) 31-8, 31-38, 
31-46 
Harbor of Refuge, Block Island, R.I. (NED) 1-65, 1-66 
Harbor of Refuge, Delaware Bay, Del. (NAP) 3-26 
Harbor of Refuge, N. C. (SAW) 6-29 
Harbor of Refuge, Point Judith, R.I. (NED) 1-66 
Harbors at Washington Island, Wis. (NCC) 30-40 
Harden, Cecil M., Lake, Ind. (ORL) 24-8, 24-25 
Hardwick Dams, Vt. (NAN) 2-47 
Harlan County Lake, Nebr. (MRK) 20-5, 20-22, 20-31 
Harlem River, N.Y. (NAN) 2-44, 2-45 
Harpers Ferry, W. Va. (NAB) 4-44 
Harraseeket River, Maine (NED) 1-66 
Harriet Island Harbor, Minn. (SAM) (NCD) 29-3, 29-8 
Harrisburg, Ill. (ORL) 24-33, 24-38, 24-42 
Harrison County, Miss., Shore Protection (SAM) 10-41 
Harrisonville and Ivy Landing Drainage and Levee District 
No. 2, Ill. (LMS) 14-4, 14-13, 14-15 
Harrisville Mich. (NCE) 31-55, 31-56 
Harrodsburg Creek, Ky. (ORL) 24-43 
Harry S. Truman Dam and Reservoir, Mo. (MRK) 20-18, 20- 
24, 20-31 
Hartford, Conn. (NED) 1-44, 1-72, 1-76 
Hartford, Vt. (NED) 1-72, 1-76 
Hartford, W. Va. (ORH) 25-25, 25-31 
Hartwell Drainage and Levee District, Ill. (LMS) 14-19 
Hartwell Lake, Ga. and S. C. (SAS) 8-9, 8-12, 8-15, 8-16 
Harve, Mont. (MRO) 21-20, 21-22 
Harve, Mont., Scott Coulee-Bull Hook Dam (MRO) 21-20 
Harvey Canal, Bayou Barataria Levee, La. (LMN) 11-30, 11- 
40, 11-48 
Harvey Lock, La. (LMN) 11-51 
Hastings Harbor, Minn. (NCD) 29-3, 29-8 
Haverhill, Mass. (NED) 1-44 
Hawarden, Dry Creek, Iowa (MRO) 21-21 
Hawesville, Ky. (ORL) 24-33, 24-38, 24-42 
Hay (West Harbor), N.Y. (NED) 1-65, 1-66 
Hayden Island, Oreg. (NPP) 37-54 
Hays, Kans. (MRK) 20-33 
Haysi, Va. (ORH) 25-27, 25-29, 25-32 
Hayward Creek, Quincy-Braintree, Mass. (NED) 1-31, 1-52, 
1-62 
Heeia-Kea Small Boat Harbor, Oahu, Hawaii (POD) 36-13 
Heise-Roberts Area, Snake River, Idaho (NPW) 39-17, 39-18 
Heise-Roberts Extension, Idaho (NPW) 39-16, 39-17, 39-18 
Helena Harbor, Ark. (LMM) 13-1, 13-7, 13-8 
Helens Creek, bd. (NAB) 4-37 
Helm, Ill. (ORL) 24-37 
I-15

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Helm Lake, Ill. (ORL) 24-12, 24-25 
Hempstead County Levee District No. 1, Ark. (LMN) 11-56, 
11-57 
Hempstead Harbor, N.Y. (NAN) 2-44, 2-45 
Henderson, W. Va. (ORH) 25-25, 25-31 
Henderson County Drainage District No. 1, Ill. (NCR) 28-11, 
28-13 
Henderson County Drainage District No. 2, Ill. (NCR) 28-11, 
28-13 
Henderson County Drainage District No. 3, Ill. (NCR) 28-11, 
28-13 
Henderson River, Ill. (NCR) 28-13 
Hendrick's Harbor, Maine (NED) 1-66 
Hennepin Drainage and Levee District, Ill. (NCC) 30-41, 30- 
42 
Henry H. Buckman Lock, Fla. (SAJ) 9-37 
Henry T. Rainey Dam, Ill. (NCD) 29-3, 29-7 
Hensley Lake-Hidden Dam, Calif. (SPK) 35-8, 35-25 
Herkimer, N.Y. (NAN) 2-47 
Herreid, Spring Creek, S. Dak. (MRO) 21-20, 21-22 
Herring Bay and Rockhold Creek, Md. (NAB) 4-37 
Herring Creek, Md. (NAB) 4-37 
Heyburn Lake, Okla. (SWT) 19-13, 19-26, 19-35 
Hickman, Ky. (MR&T) 42-13 
Hickman Harbor, Ky. (LMM) 13-2, 13-7, 13-8 
Hidden Dam-Hensley Lake, Calif. (SPK) 35-8, 35-25 
Higginsport, Ohio (ORH) 25-25, 25-31 
Highland Bayou, Tex. (SWG) 15-13, 15-19, 15-30 
Hildebrand Lock and Dam, W. Va. (ORP) 26-25 
Hills Creek Lake, Oreg. (NPP) 37-27, 37-35, 37-44, 37-49, 37- 
51 
Hillsboro Dam, N. C. (SAW) 6-31 
Hillsborough Bay, Fla. (SAJ) 9-51 
Hillsborough River, Fla. (SAJ) 9-34 
Hillsdale Lake, Kans. (MRK) 20-6, 20-22, 20-31 
Hillside Floodway, Miss. (MR&T) 42-52 
Hillview Drainage and Levee District, Ill. (LMS) 14-19 
Hilo Harbor, Hawaii, Hawaii (POD) 36-13 
Hingham Harbor, Mass. (NED) 1-65, 1-66 
Hitchins, Ky. (ORH) 25-30 
Hiwassee River, Tenn. (ORN) 23-17 
Hocking River, Ohio (ORH) 25-25 
Hockingport, Ohio (ORH) 25-25, 25-31 
Hodges Dam and Reservoir, Calif. (SPL) 33-37 
Hodges Village Dam, Mass. (NED) 1-42, 1-54, 1-64, 1-75 
Hogtown Creek, Fla. (SAJ) 9-51 
Hoguiam River, Wash. (NPS) 38-26, 38-27 
Holbrook Levee, Ariz. (SPL) 33-37 
Holla Bend Bottom, Ark. (SWL) 18-24 
Holland Harbor, Mich. (NCE) 31-9, 31-38, 31-46 
Holley Lake, Oreg. (NPP) 37-51, 37-55 
Holmes Creek, Fla. (SAM) 10-40 
Holston River, Tenn. (ORN) 23-17 
Holt Lock and Dam, Ala. (SAM) 10-5, 10-38 
Holyoke, Mass. (NED) 1-44, 1-72, 1-76 
Homer Harbor, Alaska (NPA) 40-3, 40-11, 40-13 
Hominy Swamp, N. C. (SAW) 6-32 
Homme Lake and Dam, N. Dak. (NCS) 27-12, 27-25 
Homochitto River, Miss. (LMK) 12-11, 12-12 
Homosassa River, Fla. (SAJ) 9-41 
Honey Creek Levee, Ind. (ORL) 24-33, 24-25 
Honey Hill Reservoir, N.H. (NED) 1-71, 1-76 
Honga River and Tar Bay, Md. (NAB) 4-36, 4-37 
Honokohau Small Boat Harbor, Hawaii, Hawaii (POD) 36-13 
Honolulu Harbor, Oahu, Hawaii (POD) 36-2, 36-9, 36-11 
Hoonah Harbor, Alaska (NPA) 40-3, 40-11, 40-13 
Hooper, Nebr. (MRO) 21-21, 21-22 
Hoosic Falls, N.Y. (NAN) 2-47 
Hop Brook Lake, Conn. (NED) 1-33, 1-52, 1-63, 1-73 
Hopkins East Fork, 102 River, Mo. (MRK) 20-32 
Hopkinton-Everett Lakes, N.H. (NED) 1-36, 1-53, 1-63, 1-74 
Hords Creek Lake, Tex. (SWF) 16-10, 16-20 
Horn Harbor, Va. (NAO) 5-26, 5-27 
Hornell, N.Y. (NAB) 4-18, 4-28, 4-41 
Horseshoe Cove, Fla. (SAJ) 9-40, 9-41 
Hoskins Creek, Va. (NAO) 5-11, 5-20, 5-24, 5-26 
Hot Springs, N. Mex. (SWA) 17-13, 17-19 
Hot Springs Channel Improvement, S. Dak. (MRO) 21-5, 21- 
20 
Houma Navigation Canal, La. (LMN) 11-13, 11-38, 11-44 
Housatonic River Basin, Conn. (NED) 1-31, 1-44, 1-73 
Housatonic River, Conn. (NED) 1-10, 1-47, 1-58, 1-65 
Houston Ship Channel, Tex. (SWG) 15-7, 15-18, 15-26, 15- 
33, 15-35, 15-40 
Howard A. Hanson Dam, Wash. (NPS) 38-9, 38-17, 38-22 
Howards Mill Lake, N. C. (SAW) 6-14, 6-25, 6-31 
Hubley Bridge, Ill., East of (NCC) 30-42 
Hudson River, Fla. (SAJ) 9-41 
Hudson River, N.Y. (NAN) 2-5, 2-32, 2-36, 2-42, 2-44 
Hudson River Channel, N.Y. (NAN) 2-6, 2-32, 2-37 
Hugo Lake, Okla. (SWT) 19-13, 19-26, 19-35, 19-36 
Hulah Lake, Okla. (SWT) 19-13, 19-27, 19-35 
Hull, Cordell, Lock and Dam, Tenn. (ORN) 23-2, 23-14, 23- 
19 
Humboldt Harbor, Alaska (NPA) 40-4, 40-11, 40-13 
Humboldt Harbor and Bay, Calif. (SPN) 34-2, 34-15, 34-18 
Humboldt River and Tributaries, Nev. (SPK) 35-8, 35-25 
Hunt Drainage District and Lima Lake Drainage District, Ill. 
(NCR) 28-11, 28-13 
Hunting Island Beach, S. C. (SAN) 7-6, 7-12, 7-15 
Huntington, W. Va. (ORH) 25-25, 25-30, 25-31 
Huntington Harbor, N.Y. (NAN) 2-45 
Huntington Lake, Ind. (ORL) 24-13, 24-25 
Huntington, Mass. (NED) 1-72, 1-76 
Huron Harbor, Ohio (NCB) 32-12, 32-27, 32-37 
Hurricane Barrier Operations (NED) 1-44 
Hutchinson Levee, Kans. (SWT) 19-37, 19-38 
Hyannis Harbor, Mass. (NED) 1-10, 1-47, 1-58, 1-65 
Hyde County Dike, N. C. (SAW) 6-32 
Hydraulic Mining and Preparation of Plans, Regulation of 
(CDC) 44-1, 44-5, 44-6 
I 
Iao Stream Maui, Hawaii (POD) 36-7, 36-8, 36-10, 36-12 
Ice Harbor at Marcus Hook, Pa. (NAP) 3-26 
Ice Harbor at New Castle, Del. (NAP) 3-26 
Ice Harbor Lock and Dam-Lake Sacajawea, Wash. (NPW) 39- 
7, 39-12, 39-14, 39-19, 39-24 
Ida Grova, Iowa (MRO) 21-21, 21-22 
Iliuliuk Harbor, Alaska (NPA) 40-15 
Illinois and Mississippi Canal, Ill. (NCR) 28-1, 28-8 
Illinois River, Ill. (LMS) (NCC) (MR&T) 30-41, 30-42, 42,21 
Illinois River Levees (MR&T) 42-50 
Illinois River, Mouth to Utica, Ill. (NCC) 30-38 
Illinois Waterway, Ill. and Ind. (NCC) 30-6, 30-22, 30-27, 30- 
33, 30-37, 30-38, 30-39 
Imperial Beach, Calif. (SPL) 33-8, 33-21, 33-27, 33-31 
Inavale, Nebr. (MRK) 20-32 
Indian Bend Wash., Ariz. (SPL) 33-10, 33-27 
Indian Creek, Corydon, Ind. (ORL) 24-38, 24-43 
I-16

Indian Creek Area, Ill. (LMS) 14-19 
Indian Grave Drainage District, Ill. (NCR) 28-11, 28-13 
Indian Lake, Kans. (MRK) 20-6, 20-22 
Indian River Inlet and Bay, Del. (NAP) 3-7, 3-20, 3-23, 3-25 
Indiana Harbor, Ind. (NCC) 30-8, 30-23, 30-28 
Indianapolis, Ind. (ORL) 24-13, 24-25, 24-42 
Indianola, Nebr. (MRK) 20-31, 20-32, 20-33 
Industrial Canal Lock, La. (LMN) 11-13 
Industry, Pa. (ORP) 26-28, 26-31 
Inez, Rock Castle Creek, Ky. (ORH) 25-30 
Inglis Lock and Dam, Fla. (SAJ) 9-37 
Inland Route, Mich. (NCE) 31-9, 31-38, 31-46 
Inland Waterway from Chincoteague Bay, Va., to Delaware 
Bay, Del. (NAP) 3-8, 3-20 
Inland Waterway from Delaware River to Chesapeake Bay, 
Del. and Md. (NAP) 3-8, 3-20, 3-23, 3-25 
Inland Waterway from Franklin to Mermentau River, La. 
(LMN) 11-53 
Inland Waterway, Rehoboth Bay to Delaware Bay, Del. (NAP) 
3-7, 3-20, 3-23 
Inner Harbor Navigation Canal Lock, La. (LMN) 11-52 
Intercounty Drainage District Iowa (MRO) 21-21 
International Board, American Falls 48-11 
International Boundary Waters Boards 48-2 
International Champlain-Richelieu Board 48-5 
International Champlain-Richelieu Engineering Board 48-4 
International Great Lakes Levels Board 48-12 
International Great Lakes Study Group 48-14 
International Kootenay Lake Board of Control 48-20 
International Lake Champlain Board of Control, 48-4 
International Lake Memphremagog Board, 48-3 
International Lake of the Woods Control Board 48-17 
International Lake Superior Board of Control 48-14 
International Niagara Board of Control 48-8 
International Niagara Committee 48-10 
International Osoyoos Lake Board of Control 48-21 
International Pembina River Engineering Board 48-18 
International Prairie Portage Board of Control 48-16 
International Rainy Lake Board of Control 48-16 
International Roseau River Engineering Board 48-19 
International Skagit River Board of Control 48-21 
International Souris-Red Rivers Engineering Board 48-18 
International St. Croix River Board of Control 48-2 
International St. Lawrence River Board of Control 48-6 
Intracoastal Waterway, Caloosahatchee River to Anclote 
River, Fla. (SAJ) 9-6, 9-25, 9-30 
Intracoastal Waterway from the Mississippi River to Bayou 
Teche, La. (LMN) 11-53 
Intracoastal Waterway, Jacksonville to Miami, Fla. (SAJ) 9-6, 
9-25, 9-30 
Intracoastal Waterway, Miami to Key West, Fla. (SAJ) 9-41 
Investigations and Supervision of Projects under Federal 
Water Power Act 47-1 
Iola, Kans. (SWT) 19-38 
Iowa River-Flint Creek Levee District No. 16, Iowa (NCR) 28- 
12, 28-13 
Ipswich River, Mass. (NED) 1-66 
Iron Canyon, Calif. (SPK) 35-20 
Irondale Lake, Mo. (LMS) 14-17 
Irondequoit Bay, N.Y. (NCB) 32-12, 32-27 
Ironton, Ohio (ORH) 25-25, 25-30, 25-31 
Irvington Harbor, N.Y. (NAN) 2-45 
Isabella Lake, Calif. (SPK) 35-9, 35-25 
Island Creek, Md. (NAB) 4-37 
Island Creek, St. Georges Island, Md. (NAB) 4-37 
Island Levee, Ind. (ORL) 24-14, 24-25, 24-33 
Isle Au Haut Thoroughfare, Maine (NED) 1-66 
JDEX 
Isle of Shoals Harbor, Maine and N.H. (NED) 1-11, 1-47, 1- 
58 
Ithaca, N.Y., Cahuga Inlet (NCB) 32-21, 32-29 
Ithaca, N.Y. (NCB) 32-44 
J 
Jackson, Ky. (ORL) 24-33, 24-38, 24-43 
Jackson, Minn. (NCR) 28-13 
Jackson and East Jackson, Miss. (SAM) 10-14, 10-17, 10-28, 
10-36 
Jackson Creek, Va. (NAO) 5-26, 5-27 
Jackson Hole, Wyo. (NPW) 39-3, 39-12, 39-14, 39-17 
Jackson Lock and Dam, Ala. (SAM) 10-5 
Jacksonburg, W. Va. (ORH) 25-30 
Jacksonville Harbor, Fla. (SAJ) 9-7, 9-26, 9-30 
Jacobs Beach, Guilford, Conn. (NED) 1-20, 1-69 
Jadwin, General Edgar, Dam and Reservoir, Pa. (NAP) 3-16, 
3-21 
Jamaica Bay, N.Y. (NAN) 2-44, 2-45 
James River, Va. (NAO) 5-11, 5-20, 5-24 
Jamestown Reservoir, N. Dak. (MRO) 21-22 
Janesville and Indian Ford Dams, Wis. (NCR) 28-13 
Jefferson River, Mont., Near Three Forks (MRO) 21-20 
Jefferson River, Waterloo, Mont. (MRO) 21-20 
Jeffersonville-Clarksville, Ind. (ORL) 24-33, 24-38, 24-42 
Jemez Canyon Dam, N. Mex. (SWA) 17-12, 17-17, 17-19 
Jenkins, Tom, Reservoir, Ohio (ORH) 25-17, 25-22, 25-27 
Jenks Levee, Okla. (SWT) 19-37, 19-38 
Jennings Beach, Fairfield, Conn. (NED) 1-20, 1-69 
Jim Woodruff Lock and Dam, Ga. and Fla. (SAM) 10-21, 10- 
23, 10-29, 10-37, 10-43 
Joe Creek, Tulsa, Okla. (SWT) 19-38 
John Day Lock and Dam-Lake Umatilla Oreg. and Wash. 
(NPP) 37-27, 37-35, 37-44, 37-57 
John Day River, Oreg. (NPP) 37-53 
John Day River Area, Oreg. (NPP) 37-53 
John Drainage District, Oreg. (NPP) 37-50, 37-54 
John Hollis Bankhead Lock and Dam, Ala. (SAM) 10-5, 10-38 
John H. Kerr Dam and Reservoir, Va. and N. C. (SAW) 6-20, 
6-26, 6-31 
John Martin Reservoir, Colo. (SWA) 17-8, 17-16 
John Redmond Dam and Reservoir, Kans. (SWT) 19-14, 19- 
27, 19-35 
John Redmond Wildlife Refuge, Kans. (SWT) 19-38 
John W. Flannagan Dam and Reservoir, Va. (ORH) 25-9, 25- 
20, 25-27 
Johns Pass, Fla. (SAJ) 9-41 
Johnson Bayou, La. (SWG) 15-32 
Johnson Creek, Oreg. (NPP) 37-55 
Johnson Creek, Vicinity of Portland, Oreg. (NPP) 37-52 
Johnson Gorges, Vt. (NAN) 2-47 
Johnsonburg, Pa. (ORP) 26-28, 26-30, 26-31 
Johnstown, Pa. (ORP) 26-8, 26-19, 26-28 
Jones Bluff Lock and Dam, Ala. (SAM) 10-18, 10-19, 10-28, 
10-42 
Jones Inlet, N.Y. (NAN) 2-7, 2-32, 2-37, 2-44 
Jonesville, La. (LMK) (MR&T) 12-10, 42-2, 42-56 
Jordan, B. Everett, Dam and Lake, N. C. (SAW) 6-14, 6-25, 
6-31 
Josias River, Maine (NED) 1-65, 1-66 
J. Percy Priest Dam and Reservoir, Tenn. (ORN) 23-7, 23-10, 
23-18 
Joyce Creek, N. C. (SAW) 6-16, 6-25 
Juneau Harbor, Alaska (NPA) 40-15 
I-17

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
K 
Kaaawa Beach, Oahu, Hawaii 36-6, 36-10 
Kahului Beach Road, Maui, Hawaii 36-3, 36-9 
Kahului Harbor, Maui, Hawaii (POD) 36-3, 36-9, 36-11 
Kailua Small Boat Harbor, Oahu, Hawaii (POD) 36-13 
Kaimu Black Sand Beach, Hawaii, Hawaii (POD) 36-6 
Kake Harbor, Alaska (NPA) 40-5, 40-11, 40-13 
Kalama River (South Area) Levees, Wash. (NPP) 37-54 
Kalamazoo River, Battle Creek, Mich. (NCE) 31-25, 31-42, 
31-51 
Kalamazoo River, Kalamazoo, Mich. (NCE) 31-26, 31-42, 31- 
51 
Kalaupapa Harbor, Molokai, Hawaii (POD) 36-13 
Kanawha River, W. Va. (ORH) 25-2, 25-20, 25-24, 25-27 
Kaneohe-Kailua Area, Oahu, Hawaii (POD) 36-7, 36-10, 36- 
12 
Kankakee River, Ill. and Ind. (NCC) 30-42 
Kanopolis Lake, Kans. (MRK) 20-7, 20-23, 20-31 
Kansas City, Kans. (MRK) 20-7, 20-23 
Kansas Citys on Missouri and Kansas Rivers, Mo. and Kans. 
(MRK) 20-26, 20-32, 20-33 
Kansas River and Minor Tributaries, Kans. (MRK) 20-32 
Kansas River Navigation, Kans. (MRK) 20-29 
Karlson Island, Oreg. (NPP) 37-53 
Kasilof River, Alaska () 40-5, 40-11, 40-13 
Kaskaskia Island Drainage and Levee District, Ill. (LMS) 14-4, 
14-13, 14-15 
Kaskaskia Island Levee Project, Ill. (LMS) 14-18 
Kaskaskia River, Ill. (LMS) 14-2, 14-5, 14-13, 14-15, 14-17 
Kaukauna Locks and Dam, Wis. (NCC) 30-36 
Kaunakakai Harbor, Molokai, Hawaii (POD) 36-13, 36-14 
Kaunakakai Stream, Molokai, Hawaii (POD) 36-8 
Kaw Lake, Okla. (SWT) 19-14, 19-27, 19-30, 19-36 
Kawaihae Harbor, Hawaii, Hawaii (POD) 36-3, 36-9, 36-11 
Kawainui Swamp, Oahu, Hawaii (POD) 36-8, 36-14 
Kaweah and Tule Rivers, Including Terminus Dam and 
Success Lake, Calif. (SPK) 35-10, 35-36 
Kawkawlin, Mich. (NCE) 31-30 
Kawkawlin River, Mich. (NCE) 31-57 
Kays Creek, Layton, Utah (SPK) 35-22, 35-34 
Keach Drainage and Levee District, Ill. (LMS) 14-19 
Keehi Lagoon, Oahu, Hawaii (POD) 36-13 
Keene, N.H. (NED) 1-44, 1-72, 1-76 
Kehoe Lake, Ky. (ORH) 25-9, 25-21 
Keithsburg Drainage District, Ill. (NCR) 28-13 
Kelleys Island Harbor, Ohio 
Kelly Lake Drainage and Levee District, Ill. (NCC) 30-41, 30- 
42 
Kellys Island, Mich. (NCE) 31-56 
Kendrick, Potlatch River, Idaho (NPW) 39-16, 39-18 
Kendrick, Potlach River and Bear Creek, Idaho (NPW) 39-17 
Kenilworth, Ill. (NCC) 30-41 
Kennebec River, Maine (NED) 1-11, 1-47, 1-59 
Kennebunk River, Maine (NED) 1-12, 1-48, 1-59 
Kenosha Harbor, Wis. (NCC) 30-9, 30-23, 30-29, 30-33 
Kentucky Project, Ky. (ORN) 23-16 
Kentucky River, Ky. (ORL) 24-2, 24-24, 24-32, 24-36 
Keokuk Harbor, Iowa (NCD) 29-9 
Kerr, John H., Dam and Reservoir, Va., and N. C. (SAW) 6- 
20, 6-26, 6-31 
Kerr, Robert S., Lock and Dam and Reservoir, Okla. (SWL) 
(SWT) 18-2, 18-17, 19-23, 19-28, 19-32, 19-36 
Kerr, Robert S., Marine Terminal, Okla. (SWL) (SWT) 18-2, 
19-5, 19-32 
Kerton Valley Drainage and Levee District, Ill. (NCC) 30-41 
Ketchikan Harbor, Alaska (NPA) 40-15 
Kewalo Harbor, Oahu, Hawaii (POD) 36-4, 36-9 
Kewaunee Harbor, Wis. (NCC) 30-10, 30-23, 30-29, 30-34 
Keweenaw Waterway, Mich. (NCS) 27-5, 27-23, 27-28 
Key West, Fla. (SAJ) 9-43 
Key West Harbor, Fla. (SAJ) 9-41 
Keyport Harbor, N.J. (NAN) 2-45 
Keystone Lake Okla. (SWL) (SWT) 18-18, 19-22, 19-28, 19- 
32, 19-35 
Keystone Lock, La. (LMN) 11-50 
Kihei Beach, Maui, Hawaii (POD) 36-14 
Kikiaola Small Boat Harbor, Kauai, Hawaii (POD) 36-13 
Kindred Lake, N. Dak. (NCS) 27-13 
King Beach Harbor, Calif. (SPL) 33-30 
King Cove Harbor, Alaska (NPA) 40-15 
Kings Creek, Va. (NAO) 5-27 
Kings River Channel Improvement, Calif. (SPK) 35-17, 35-22, 
35-26 
Kingston-Edwardsville, Pa. (NAB) 4-44 
Kingston Harbor, Wash. (NPS) 38-26, 38-27 
Kingston Harbor (North Plymouth), Mass. (NED) 1-66 
Kingstree Branch, S. C. (SAN) 7-9, 7-12, 7-15 
Kinzua Dam and Allegheny Reservoir, Pa. and N.Y. (ORP) 
26-8, 26-20, 26-29 
Kirsch Lake Canal (MR&T) 42-53 
Kirwan, Michael J., Dam and Reservoir, Ohio (ORP) 26-10, 
26-20 
Kishwaukee River at De Kalb, Ill. (NCR) 28-11, 28-13 
Kissimmee River, Fla. (SAJ) 9-41 
Kittanning, Pa. (ORP) 26-30 
Kittanning, Pa., Part I (ORP) 26-28, 26-31 
Kittanning, Pa., Part II (ORP) 26-28, 26-31 
Kitzmiller, Md. (NAB) 4-44 
Klamath River, Calif. (SPN) 34-23 
Klutina River, Alaska (NPA) 40-16 
Knappa Area, Oreg. (NPP) 37-53 
Knapps Narrows, Md. (NAB) 4-5, 4-26, 4-32 
Knife River Harbor, Minn. (NCS) 27-6, 27-23, 27-28 
Knights Valley Lake, Calif. 
Knightville Dam, Mass. (NED) 1-26, 1-50, 1-61, 1-71 
Knobbs Creek, N. C. (SAW) 6-28, 6-29 
Kodiak Harbor, Alaska (NPA) 40-15 
Kootenai River, Idaho and Mont. (NPS) 38-27 
Kootenay Lake Board of Control, International 48-20 
Kuliouou Stream, Oahu, -Hawaii (POD) 36-8, 36-14 
L 
Lac La Belle Harbor, Mich. (NCS) 27-6, 27-23 
Lac Qui Parle Lake, Minn. (NCS) 27-13, 27-25 
La Carne-Camp Perry, Ohio (NCE) 31-30 
Lacey Drainage-and Levee District, Ill. (NCC) 30-41 
Lackawanna, N.Y., Smokes Creek (NCB) 32-44 
Lackawanna River Basin, Pa. (NAB) 4-14, 4-35, 4-39, 4-40 
Lacy Langellier, West Mantanzas and Kerton Valley Drainage 
and Levee District, Ill. (NCC) 30-42 
La Farge Lake and Channel Improvement, Wis. (NCS) 27-13, 
27-25 
Lafayette Lake, Ind. (ORL) 24-14, 24-26 
Lafayette River, Va. (NAO) 5-26, 5-27 
Lago DeCerrillos, P.R. (SAJ) 9-36 
1-18

INDEX 
Lago DePortugues, P.R. (SAJ) 9-36 
Lagoon Pond, Mass. (NED) 1-12, 1-48, 1-59 
LaGrange Bayou, Fla. (SAM) 10-39, 10-40 
LaGrange Lock and Dam, Ill. (NCC) 30-7, 30-37, 30-38 
Lahaina Small Boat Harbor, Maui, Hawaii (POD) 36-4, 36-9, 
36-12 
LaJunta (Anderson and King Arroyos), Colo. (SWA) 17-3, 17- 
17 
LaJunta (Reach 2-Urban), Colo. (SWA) 17-5, 17-18 
Lake 1-38, Mo. (LMS) 14-17 
Lake Ashtabula and Baldhill Dam, N. Dak. (NCS) 27-14, 27- 
25 
Lake Barkley, Ky., and Tenn. (ORN) 23-2, 23-14, 23-19 
Lake Bluff, Ill. (NCC) 30-18, 30-25 
Lake Brownwood Modification, Tex. (SWF) 16-10, 16-20 
Lake Bryan-Little Goose Lock and Dam, Wash. (NPW) 39-8, 
39-12, 39-14 
Lake Camanche, Calif. (SPK) 35-12, 35-26 
Lake Celilo-the Dalles Lock and Dam, Wash. and Oreg. 
(NPP) 37-29, 37-36, 37-45, 37-58 
Lake Champlain Board of Control, International 48-4 
Lake Charles Deep Water Channel, La. (LMN) 11-53 
Lake Chautauqua and Chadakoin River, N.Y. (ORP) 26-28, 
26-31 
Lake Chicot (MR&T) 42-53, 42-57 
Lake City, Tenn. (ORN) 23-18 
Lake City Harbor, Minn. (NCD) 29-2, 29-3, 29-8 
Lake Crescent and Dunns Creek, Fla. (SAJ) 9-41 
Lake Crockett, Wash. (NPS) 38-26, 38-27 
Lake Cumberland, Ky. (ORN) 23-8, 23-10, 23-18 
Lake Douglas, Ga. (SAM) 10-17, 10-41 
Lake Erie-Ohio River Canal, Ohio and Pa. (ORP) 26-27 
Lake Forest, Ill. (NCC) 30-18, 30-25, 30-41 
Lake Fork Lake, Tex. (SWF) 16-22, 16-25 
Lake Fork of Salt Creek, Ill. (NCC) 30-42 
Lake Francis Case, S. Dak. (MRO) 21-11, 21-15, 21-19 
Lake Greeson, Ark. (LMK) 12-4, 12-8, 12-12 
Lake Kemp, Tex. (SWT) 19-14, 19-27, 19-30, 19-35 
Lake Koocarhusa-Libby Dam, Mont. (NPS) 38-13, 38'18, 33- 
23 
Lake Memphremagog Board, International 48-3 
Lake Mendocino, Calif. (SPN) 34-13, 34-17, 34-22 
Lake Michigan, Escanaba, Mich. (NCC) 30-41 
Lake Michigan, Lake Forest, Ill. (NCC) 30-41 
Lake Michigan, Racine, Wis. (NCC) 30-41 
Lake Montauk Harbor, N.Y. (NAN) 2-7, 2-32, 2-37, 2-44 
Lake O' the Pines, Tex. (LMN) 11-29, 11-40, 11-48, 11-54, 
11-55 
Lake Oake, N. Dak., and S. Dak. (MRO) 21-12, 21-16, 21-19 
Lake of the Woods Control Board, International 48-17 
Lake Ogleton, Md. (NAB) 4-37 
Lake Okeechobee, Fla. (SAJ) 9-21, 9-48 
Lake Oklawaha, Fla. (SAJ) 9-4 
Lake Oroville, Calif. (SPK) 35-12, 35-26 
Lake Ouachita, Ark. (LMK) 12-4, 12-8, 12-12 
Lake Pontchartrain and Vicinity, (Hurricane Protection) 
(LMN) 11-30, 11-40, 11-48 
Lake Pontchartrain, La. (MR&T) 42-1, 42-16, 42-46, 42-56 
Lake Providence Harbor, La. (LMK) 12-1, 12-8, 12-9 
Lake River, Wash. (NPP) 37-46, 37-47 
Lake River Delta Area, Wash. (NPP) 37-50, 37-54 
Lake Rousseau, Fla. (SAJ) 9-4 
Lake Sacajawea-Ice Harbor Lock and Dam, Wash. (NPW) 39- 
7, 39-12, 39-14 
Lake Sakakawea, N. Dak. (MRO) 21-11, 21-15, 21-19 
Lake Sharpe, S. Dak. (MRO) 21-10, 21-15, 21-19 
Lake Shelbyville, Ill. (LMS) 14-6, 14-13, 14-17 
Lake Sidney Lanier, Ga. (SAM) 10-21, 10-22, 10-29, 10-37, 
10-43 
Lake St. Clair, Mich., Channels (NCE) 31-10, 31-38, 31-46 
Lake St. Clair and Tat Momolikot Dam, Ariz. (SPL) 33-11, 
33-22, 33-27 
Lake Superior Board of Control, International 48-14 
Lake Traverse, Minn. and S. Dak. (NCS) 27-31 
Lake Traverse and Bois De Sioux River, S. Dak., N. Dak. and 
Minn. (NCS) 27-15, 27-25 
Lake Umatilla-John Day Lock and Dam, Oreg. and Wash. 
(NPP) 37-27, 37-35, 37-44, 37-57 
Lake Wallula-McNary Lock and Dam, Oreg. and Wash. 
(NPW) 39-10, 39-13, 39-15 
Lake Washington Ship Canal, Wash. (NPS) 38-4, 38-16, 38- 
21, 38-25, 38-26 
Lakeport Lake, Scotts Creek, Calif. (SPK) 35-13, 35-26 
Lakeview Lake, Tex. (SWF) 16-11, 16-20 
Lakeview Park, Lorain, Ohio (NCB) 32-19, 32-28 
Lamoille River, Vt. (NAN) 2-47 
Lamprey River, N.H. (NED) 1-66 
Lancaster, Cayuga Creek, N.Y. (NCB) 32-44 
Langellier Drainage and Levee District, Ill. (NCC) 30-41 
L'Anguille River, Ark. (MR&T) 42-2, 42-20, 42-29, 42-54 
Lansing Harbor, Iowa (NCD) 29-3, 29-8 
La Pointe Harbor, Wis. (NCS) 27-31 
Lapwai Creek, Culdesac, Idaho (NPW) 39-17, 39-18 
Larchmont Harbor, N.Y. (NAN) 2-45 
Largo Sound Channel, Fla. (SAJ) 9-41 
Larose to Golden Meadow, La., Hurricane Protection (LMN) 
11-32, 11-40, 11-49 
LasAnimas, Colo. (SWA) 17-8, 17-16, 17-18 
LasCruces, N. Mex. (SWA) 17-9, 17-16, 17-18 
LaTrappe River, Md. (NAB) 4-37 
Las Tunas Beach Park, Calif. 
Las Vegas Wash Tributaries (Inactive), Nev. (SPL) 33-37 
Latrobe, Pa. (ORP) 26-28, 26-30, 26-31 
Laurel River Lake, Ky. (ORN) 23-8, 23-10, 23-18, 23-19 
Lavaca-Navidad Rivers, Tex. (SWG) 15-16, 15-32 
Lavon Lake, Tex. (SWF) 16-12, 16-20, 16-26 
Lavon Lake Modification and East Fork Channel 
Improvement, Tex. (SWF) 16-12, 16-20 
Lawrence, Kans. (MRK) 20-8, 20-23, 20-31, 20-32 
Lawrenceburg, Ind. (ORL) 24-33, 24-38, 24-42 
Lazer Creek Lake, Ga. (SAM) 10-21, 10-43 
Leading Creek Lake, W. Va. (ORH) 25-27, 25-29, 25-32 
Leaf and Chickasawhay Rivers, Miss. (SAM) 10-40 
Leavenworth, Ind. (ORL) 24-33, 24-38 
Lebanon Junction, Ky. (ORL) 24-38, 24-42 
Le Claire Lock, Iowa (NCD) 29-6 
Lee, Mass. (NED) 1-34, 1-52, 1-63 
Lee County, Fla. (SAJ) 9-43 
Leech Lake, Minn. (NCS) 27-29 
Leesville Reservoir, Va. (SAW) 6-31 
Leetonia, Ohio (ORP) 26-30, 26-31 
Leetsdale, Pa. (ORP) 26-28, 26-31 
Leipsic River, Del. (NAP) 3-26 
Leland Harbor, Mich. (NCE) 31-10, 31-38, 31-46 
Lemon Creek, N.Y. (NAN) 2-45 
Les Cheneaux Islands Channels, Mich. (NCE) 31-11, 31-38, 
31-47 
Letart, W. Va. (ORH) 25-25, 25-31 
Letart Falls, Ohio (ORH) 25-25, 25-31 
Levee Between Shelby Bridge and Baum's Bridge in Ind. 
(NCC) 30-42 
Levee Unit 1, Eel River, Ind. (ORL) 24-33, 24-38 
Levee Unit 1, Little Wabash River, Ill. (ORL) 24-33 
Levee Unit 1, Wabash River, Ill. (ORL) 24-39 
I-19

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Levee Unit 1, White River, Ind. (ORL) 24-34 
Levee Unit 2, Eel River, Ind. (ORL) 24-33, 24-38 
Levee Unit 2, Little Wabash River, Ill. (ORL) 24-34 
Levee Unit 2, White River, Ind. (ORL) 24-34, 24-38 
Levee Unit 3, East Fork of White River, Ind. (ORL) 24-39 
Levee Unit 5, Wabash River, Ind. (ORL) 24-14, 24-26, 24-42 
Levee Unit 6, Wabash River, Ill. (ORL) 24-34, 24-39 
Levee Unit 7, White River, Ind. (ORL) 24-34 
Levee Unit 8, White River, Ind. (ORL) 24-39, 24-42 
Levee Unit 17, Ind. (Wabash River Basin) (ORL) 24-34 
Levee Units 1 and 2, Wabash River, Ill. (ORL) 24-39 
Levee Units 3 and 4, Wabash River, Ill. (ORL) 24-39 
Levee Units 9 and 10, White River, Ind. (ORL) 24-39 
Lewis and Clark Lake, Nebr. and S. Dak. (MRO) 21-12, 21- 
15, 21-19 
Lewis and Clark Lake Relocation of Niobrara, Nebr. (MRO) 
21-12, 21-15, 21-19 
Lewis and Clark River Area, Oreg. (NPP) 37-53 
Lewis River, Wash. (NPP) 37-8, 37-32, 37-40 
Lewis River Area, Wash. (NPP) 37-50, 37-54 
Lewis River Basin, Wash. (NPP) 37-54 
Lewisport, Ky. (ORL) 24-34, 24-39 
Lewiston Levees, Wash. (NPW) 39-18 
Lewisville Dam, Tex. (SWF) 16-11, 16-20, 16-26 
Lexington Harbor, Mich. (NCE) 31-11, 31-39, 31-47 
Libby Dam-Lake Koocanusa, Mont. (NPS) 38-13, 38-18, 38-23 
Liberty Local Protection Project, Tex. (SWG) 15-32 
Lick Run, Roanoke, Va. (SAW) 6-20, 6-32 
Licking River, Ky. (ORL) 24-36, 24-44 
Lido Key, Fla. (SAJ) 9-43 
Lighthouse Point Park (Area 9), Conn. (NED) 1-20, 1-69 
Lightning Creek, Clark Fork, Idaho (NPS) 38-28 
Lincoln Lake, Ill. (ORL) 24-15, 24-26 
Lincoln, Salt Creek and Tributaries, Nebr. (MRO) 21-21 
Lincoln School Lake, Maine (NED) 1-39, 1-53, 1-64, 1-78 
Linton, N. Dak. (MRO) 21-22 
Lisle, N.Y. (NAB) 4-18, 4-29, 4-40, 4-41 
Little Bay, Tex. (SWG) 15-32 
Little Bay De Noc, Gladstone Harbor and Kipling, Mich. 
(NCC) 30-40 
Little Blue River Channel Improvement, Mo. (MRK) 20-8, 
20-23 
Little Blue River Lakes, Mo. (MRK) 20-8, 20-23 
Little Buffalo Reservoir, N. C. (SAW) 6-31 
Little Caillou Bayou, La. (LMN) 11-53 
Little Calumet River, Ill. (NCC) 30-19, 30-25, 30-42 
Little Calumet River and Tributaries, Ill. and Ind. (NCC) 30- 
42 
Little Chute Locks and Dam, Wis. (NCC) 30-36 
Little Colorado River Basin, Ariz. (SPL) 33-38 
Little Cove Creek, Glencoe, Ala. (SAM) 10-17, 10-41 
Little Creek, Md. (NAB) 4-37 
Little Cyprus Bayou, Orange, Tex. (SWG) 15-16 
Little Dell Lake, Utah (SPK) 35-13, 35-26 
Little Egg Harbor, N.J. (NAP) 3-26 
Little Goose Lock and Dam-Lake Bryan, Wash. (NPW) 39-8, 
39-12, 39-14, 39-20, 39-24 
Little Harbor, Mass. (NED) 1-65, 1-66 
Little Harbor, N.H. (NED) 1-12, 1-48, 1-59, 1-65 
Little Kanawha River, W. Va. (ORH) 25-24, 25-27 
Little Kaukawna Lock and Dam, Wis. (NCC) 30-36 
Little Lake Harbor, Mich. (NCE) 31-12, 31-39, 31-47 
Little Machipongo River, Va. (NAO) 5-26, 5-27 
Little Manatee River, Fla. (SAJ) 9-41 
Little Miami River, Ohio (ORL) 24-36 
Little Missouri River, Ark. (LMK) 12-11 
Little Missouri River below Murfreesboro, Ark. (LMK) 12-12 
Little Neck Bay, N.Y. (NAN) 2-45 
Little Nemaha River, Nebr. (MRO) 21-22 
Little Papillion, Little Papillion Creek, Neb. (MRO) 21-21 
Little Papillion Creek, Nebr. (MRO) 21-6, 21-14 
Little Pee Dee River, S. C. (SAN) 7-16 
Little River, Del. (NAP) 3-9, 3-20 
Little River, La. (LMK) 12-11 
Little River, at Cayuga Island, N.Y. (NCB) 32-42 
Little River (Creek), Va. (NAO) 5-26, 5-27 
Little River Diversion Channel, Mo. (MR&T) 42-2, 42-21 
Little River Drainage, Mo. (MR&T) 42-10, 42-11, 42-54, 42- 
55, 42-57 
Little River Inlet, N. C. and S. C. (SAN) 7-4, 7-11, 7-14 
Little River Levees (MR&T) 42-49 
Little Rock Levee, Ark. (East End-Fourche Bayou) (SWL) 18- 
5, 18-12, 18-14 
Little Rockfish Creek, Hope Mills, N. C. (SAW) 6-16, 6-25 
Little Sioux River and Tributaries, Iowa (MRO) 21-22 
Little Sodus Bay Harbor, N.Y. (NCB) 32-13, 32-27, 32-37 
Little Sugar Creek, Charlotte, N. C. (SAN) 7-8, 7-12 
Little Sunflower River, Miss. (MR&T) 42-2, 42-19 
Little Tallahatchie River, Miss. (LMK) 12-11 
Little Tallahatchie River and Panola-Quitman Floodway, Miss. 
(MR&T) 42-52 
Little Tennessee River, Tenn. (ORN) 23-17 
Little Valley Wash, Magna, Utah (SPK) 35-34 
Little Wabash River, Ill. (ORL) 24-33, 24-34 
Little Wicomico River, Va. (NAB) 4-36, 4-37 
Little Wood River, Carey, Idaho (NPW) 39-16, 39-18 
Littlejohn Creek, Calif. (SPK) 35-5, 35-22, 35-25 
Littleville Lake, Mass. (NED) 1-26, 1-51, 1-62, 1-71 
Liverpool Drainage and Levee District, Ill. (NCC) 30-41, 30- 
42 
Lock and Dam No. 1, Minn. (NCD) 29-1, 29-2, 29-3, 29-6, 
29-10 
Lock and Dam No. 2, Allegheny River, Pa. (ORP) 26-24 
Lock and Dam No. 2, Ark. (SWL) 18-2, 18-3, 18-16 
Lock and Dam No. 2, Minn. (NCD) 29-2, 29-6 
Lock and Dam No. 2, Monongahela River, Pa. (ORP) 26-25 
Lock and Dam No. 3, Ark. (SWL) 18-2, 18-3, 18-16 
Lock and Dam No. 3, Minn. (NCD) 29-2, 29-3, 29-6 
Lock and Dam No. 3, Monogahela River, Pa. (ORP) 26-25 
Lock and Dam No. 4, Allegheny River, Pa. (ORP) 26-24 
Lock and Dam No. 4, Ark. (SWL) 18-2, 18-3, 18-16 
Lock and Dam No. 4, Monongahela River, Pa. (ORP) 26-25 
Lock and Dam No. 4, Wis. (NCD) 29-3, 29-6 
Lock and Dam No. 5, Allegheny River, Pa. (ORP) 26-24 
Lock and Dam No. 5, Ark. (SWL) 18-2, 18-3, 18-16 
Lock and Dam No. 5, Minn. (NCD) 29-2, 29-3, 29-6 
Lock and Dam No. 5 A, Minn. (NCD) 29-3, 29-6 
Lock and Dam No. 6, Allegheny River, Pa. (ORP) 26-24 
Lock and Dam No. 6, Wis. (NCD) 29-6 
Lock and Dam No. 7, Allegheny River, Pa. (ORP) 26-24 
Lock and Dam No. 7, Minn. (NCD) 29-3, 29-6 
Lock and Dam No. 7, Monongahela River, Pa. (ORP) 26-25 
Lock and Dam No. 8, Allegheny River, Pa. (ORD) 26-24 
Lock and Dam No. 8, Monongahela River, Pa. (ORP) 26-25 
Lock and Dam No. 8, Wis. (NCD) 29-3, 29-6 
Lock and Dam No. 9, Allegheny River, Pa. (ORP) 6-24 
Lock and Dam No. 9, Ark. (SWL) 18-2, 18-3, 18-16 
Lock and Dam No. 9, Wis. (NCD) 29-2, 29-3, 29-6 
Lock and Dam No. 10, Iowa (NCD) 29-3, 29-6 
Lock and Dam No. 11, Ark. (SWL) 18-16 
Lock and Dam No. 11, Iowa (NCD) 29-3, 29-6 
Lock and Dam No. 12, Iowa (NCD) 29-2, 29-3, 29-6 
Lock and Dam No. 12, Ohio River, W. Va. (ORD) 22-7 
Lock and Dam No. 13, Ark. (SWL) 18-2, 18-3, 18-17 
I-20

INDEX 
Lock and Dam No. 13, Arkansas River Basin, Okla. (SWL) 
(SWT) 19-4 
Lock and Dam No. 13, Iowa (NCD) 29-2, 29-6 
Lock and Dam No. 13, Ohio River, W. Va. (ORD) 22-7 22-2, 
22-3, 22-8 
Lock and Dam No. 14, Iowa (NCD) 29-3, 29-6 
Lock and Dam No. 15, Ill. (NCD) 29-2, 29-3, 29-6 
Lock and Dam No. 16, Iowa (NCD) 29-3, 29-7 
Lock and Dam No. 17, Ill(.N CD) 29-2, 29-3, 29-7 
Lock and Dam No. 18, Iowa (NCD) 29-3, 29-7 
Lock and Dam No. 19, Iowa (NCD) 29-1, 29-3, 29-7 
Lock and Dam No. 20, Mo. (NCD) 29-3, 29-7 
Lock and Dam No. 21, Ill. (NCD) 29-3, 29-7 
Lock and Dam No. 22, Mo. (NCD) 29-2, 29-3, 29-7 
Lock and Dam No. 24, Mo. (NCD) 29-3, 29-4, 29-7 
Lock and Dam No. 25, Mo. (NCD) 29-3, 29'4, 29-7 
Lock and Dam No. 26, Ill. (NCD) 29-3, 29-4, 29-7 
Lock and Dam No. 38 Allegheny River, Pa. (ORP) 26-24 
Lock and Dam No. 53, Ohio River, (ORD) 22-3, 22-9 
Lock on Buttonwood Canal, Fla. (SAJ) 9-45 
Lock S-53, Fla. (SAJ) 9-45 
Lock S-55, Fla. (SAJ) 9-45 
Lock S-57, Fla. (SAJ) 9-45 
Lock S-58, Fla. (SAJ) 9-45 
Lock S-59, Fla. (SAJ) 9-45 
Lock S-60, Fla. (SAJ) 9-45 
Lock S-61, Fla. (SAJ) 9-45 
Lock S-62, Fla. (SAJ) 9-45 
Lock S-63, Fla. (SAJ) 9-45 
Lock S-63A, Fla. (SAJ) 9-45 
Lock S-65, Fla. (SAJ) 9-45 
Lock S-65A, Fla. (SAJ) 9-45 
Lock S-65B, Fla. (SAJ) 9-45 
Lock S-65C, Fla. (SAJ) 9-45 
Lock S-65D, Fla. (SAJ) 9-45 
Lock S-65E, Fla. (SAJ) 9-45 
Lock S-96, Fla. (SAJ) 9-45 
Lock S-96A, Fla. (SAJ) 9-45 
Lock S-157, Fla. (SAJ) 9-45 
Lock S-158, Fla. (SAJ) 9-45 
Lock S-193 (HGS-6 Mod.) (SAJ) 9-45 
Lock S-308B, Fla. (SAJ) 9-45 
Lock S-310 (HGS-2 Mod.) (SAJ) 9-45 
Lockport Lock and Dam, Ill. (NCC) 30-8, 30-37, 30-38 
Locks in Pearl River Project (La.) (SAM) 10-39 
Locklies Creek, Va. (NAO) 5-26, 5-27 
Lockwoods Folly River, N. C. (SAW) 6-6, 6-24 
Logan Creek, Near Bancroft, Nebr. (MRO) 21-21 
Logan Reservoir, Ohio (ORH) 25-27, 25-32 
Lone Rock Lake, Ark. (SWL) 18-22, 18-24 
Long Beach Island, N.J. (NAP) 3-27 
Long Branch Lake, Mo. (MRK) 20-9, 20-23 
Long Island Intracoastal Waterway, N.Y. (NAN) 2-8, 2-32, 2- 
37, 2-44 
Lookout Point Lake, Oreg. (NPP) 37-28, 37-36, 37-45, 37-49, 
37-52 
Lorain Harbor, Ohio (NCB) 32-13, 32-27, 32-37 
Los Angeles and Long Beach Harbors, Calif. (SPL) 33-30 
Los Angeles County Drainage Area, Calif. (SPL) 33-12, 33-22, 
33-27, 33-32, 33-34, 33-37 
Los Angeles River Basin, Calif. (SPL) 33-13, 33-32, 33-34 
LosEsteros Lake, N. Mex. (SWA) 17-9, 17-16, 17-18 
Lost Creek Drainage and Levee District, Ill. (NCC) 30-41, 30- 
42 
Lost Creek Lake, Oreg. (NPP) 37-29, 37-36, 37-45 
Lost River, Minn. (NCS) 27-33, 27-34 
Louisville, Ky. (ORL) 24-15, 24-26 
Louisville and Portland Canal, Ky. (ORD) 22-1, 22-2 
Louisville Lake, Ill. (ORL) 24-15, 24-26, 24-37 
Louisville, Ky. (ORL) 24-34, 24-39, 24-42 
Loup River, Columbus, Nebr. (MRO) 21-22 
Low Head Locks and Dams, Okla. (SWT) 19-4, 19-25, 19-30 
Lowell, Mass. (NED) 1-44, 1-74, 1-76 
Lowell Creek, Alaska (NPA) 40-16 
Lower Arkansas River Basin, Ark. (MR&T) 42-9, 42-18, 42- 
29, 42-55, 42-57 
Lower Auchumpkee Creek Lake, Ga. (SAM) 10-21, 10-43 
Lower Big Sioux River, Iowa and S. Dak. (MRO) 21-22 
Lower Branch Rush River, N. Dak. (NCS) 27-34 
Lower Columbia River Basin, Oreg. and Wash. (NPP) 37-20, 
37-23, 37-43, 37-50, 37-54 
Lower Columbia River Basin Bank Protection, Oreg. and 
Wash. (NPP) 37-21, 37-23, 37-35, 37-43, 37-51 
Lower Cowlitz River, Wash. (NPP) 37-55 
Lower Dry Creek, Lowden, Wash. (NPW) 39-17, 39-18 
Lower Gila River Levee and Channel Improvements from 
(Gila River and Tributaries Downstream from Painted 
Rock Dam), Ariz. (SPL) 33-10, 33-22, 33-27 
Lower Grand River, Mo. (MRK) 20-33 
Lower Granite Lock and Dam, Wash. (NPW) 39-9, 39-12, 39- 
15, 39-21, 39-24 
Lower Guyandot River Basin, W.Va. (ORH) 25-10, 25-21 
Lower Heart River, N. Dak. (MRO) 21-22 
Lower Machodoc Creek, Va. (NAB) 4-37 
Lower Monumental Lock and Dam, Wash. (NPW) 39-10, 39- 
12, 39-15, 39-22, 39-24 
Lower Red River, La. (MR&T) 42-55, 42-58 
Lower Red River - South Bank, Red River Levees, La. (MR& 
T) 42-7, 42-17, 42-29, 42-45 
Lower Red River, Standard Revetments (MR&T) 42-34 
Lower Rio Grande Basin, Tex. (SWG) 15-13, 15-19, 15-30 
Lower San Francisco Bay, Calif. (SPN) 34-21 
Lower San Joaquin River and Tributaries, Including 
Tuolumne And Stanislaus Rivers, Calif. (SPK) 35-14, 35= 
26, 35-27 
Lower St. Francis River, Ark. (MR&T) 42-10, 42-11 
Lower Thorofare, Md. (NAB) 4-37 
Lower Walla Walla River, Wash. (NPW) 39-16 
Lower White River, Ark. (MR&T) 42-29, 42-55, 42-57 
Lower White River and Basin, Ark. (MR&T) 42-20, 42-54 
Lower White River Levee, Clarendon Levee (MR&T) 42-11, 
42-49 
Lower White River Levees (MR&T) 42-49 
Lower Woonsocket, R.I. (NED) 1-70, 1-76 
Lowes Wharf, Md. (NAB) 4-37 
Loyalhanna Lake, Pa. (ORP) 26-9, 26-20, 26-29 
Lubec Channel, Maine (NED) 1-66 
Lucky Peak Lake, Idaho (NPW) 39-3, 39-12, 39-15 
Ludington Harbor, Mich. (NCE) 31-12, 31-39, 31-47 
Ludlow, Ky. (ORL) 24-34, 24-39 
Ludlow Reservoir, Vt. (NED) 1-71, 1-76 
Lukfata Lake, Okla. and Ark. (SWT) 19-15, 19-27, 19-36 
Lumber River, N. C. and S. C. (SAN) 7-16 
Lussenhop Levee, Ill. (NCC) 30-42 
Lutsen Harbor, Minn. (NCS) 27-6, 27-24 
Luxapalila Creek, Ala. (SAM) 10-17 
Lyford Levee Unit, Ind. (ORL) 24-39, 24-42 
Lyman Creek, Idaho (NPW) 39-18 
Lynches River and Clark Creek, S. C. (SAN) 7-16 
Lynn Harbor, Mass. (NED) 1-65, 1-66 
Lynnhaven Inlet, Va. (NAO) 5-12, 5-20, 5-24 
Lynnhaven Inlet, Va., (Entrance Channel) (NAO) 5-26 
Lynnhaven Inlet, Va., (Narrows) (NAO) 5-26 
Lynn-Nahant Beach, Mass. (NED) 1-69 
1-21

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Lytle and Cajon Creeks Channel Improvements, Calif. (SPL) 
33-17, 33-36, 33-37 
Lytle and Warm Creeks, Calif. (SPL) 33-15, 33-23, 33-28 
M 
Maalaea Small Boat Harbor, Maui, Hawaii (POD) 36-13 
MacArthur Lock, Mich. (NCE) 31-54 
MacDowell, Edward, Lake, N.H. (NED) 1-35, 1-53, 1-63, 1-74 
Machias River, Maine (NED) 1-66 
Mackay Creek, N. C. (SAW) 6-17, 6-25, 6-29 
Mackinac Island Harbor, Mich. (NCE) 31-55, 31-56 
Mackinaw City Harbor, Mich. (NCE) 31-55, 31-56 
Macon, Ga. (SAS) 8-8, 8-16 
Macy, Blackbird Creek, Nebr. (MRO) 21-21 
Mad River Basin, Calif. (SPN) 34-23 
Mad River, Conn. (NED) 1-44 
Mad River Lake, Conn. (NED) 1-71, 1-76 
Madison, Ind. (ORL) 24-34, 24-39 
Madison, Nebr., Union and Taylor Creeks, Nebr. (MRO) 21- 
21, 21-23 
Magruder Drainage District, Oreg. (NPP) 37-50, 37-53, 37-54 
Mahoning Creek Lake, Pa. (ORP) 26-9, 26-20, 26-29 
Maiden Creek Reservoir, Pa. (NAP) 3-28 
Maintenance and Repair Fleet and Marine Terminals, Ark. 
(SWL) 18-4 
Maintenance and Repair Fleet and Marine Terminals, Okla. 
(SWT) 19-5, 19-31 
Malden River, Mass. (NED) 1-66 
Malheur Improvement District, Oreg. (NPW) 39-17, 39-18 
Malheur River, Oreg. (NPW) 39-16, 39-17, 39-18 
Mamaroneck Harbor, N.Y. (NAN) 2-45 
Manasquan River, N.J. (NAP) 3-10, 3-20, 3-24 
Manatee River, Fla. (SAJ) 9-41 
Manchester Harbor, Mass. (NED) 1-67 
Manchester, Ohio (ORH) 25-25, 25-29, 25-31 
Mandan, N. Dak. (MRO) 21-20, 21-23 
Manele Small Boat Harbor, Lanai, Hawaii (POD) 36-13 
Manhasset Bay, N.Y. (NAN) 2-45 
Manhattan, Kans. (MRK) 20-31, 20-32, 20-33 
Maniece Bayou, Ark. (LMN) 11-55, 11-57 
Manistee Harbor, Mich. (NCE) 31-13, 31-39, 31-47 
Manistique Harbor, Mich. (NCE) 31-55, 31-56 
Manitowac County, Wis., Shore of (NCC) 30-41 
Manitowoc Harbor, Wis. (NCC) 30-10, 30-23, 30-29, 30-34 
Mankato and North Mankato, Minn. (NCS) 27-15, 27-25 
Manns Harbor, N. C. (SAW) 6-29 
Manokin River, Md. (NAB) 4-37 
Mansfield Hollow Lake, Conn. (NED) 1-42, 1-54, 1-64, 1-75 
Mansfield Lake, Ind. (ORL) 34-36 
Mantachie Creek, Miss. (SAM) 10-17 
Manteo (Shallowbag) Bay, N. C. (SAW) 6-7, 6-24 
Mantua Creek, N.J. (NAP) 3-26 
Maple River, N. Dak. (NCS) 27-32 
Mapleshade, Ohio (ORH) 25-25 
Marblehead Harbor, Mass. (NED) 1-67 
Marietta, Ohio (ORH) 25-25, 25-31 
Marina Del Rey, Calif. (SPL) 33-30 
Marion, Ind. (ORL) 24-16, 24-26, 24-35 
Marion, Kans. (SWT) 19-15, 19-27, 19-31 
Marion County Drainage District, Mo. (NCR) 28-12, 28-13 
Marion Lake, Kans. (SWT) 19-15, 19-27, 19-35 
Mariposa Stream, Calif. (SPK) 35-16 
Markham Ferry Reservoir Okla. (SWL) (SWT) 18-18, 19-23, 
19-32, 19-36, 19-37 
Markland Locks and Dam, Ind. (ORD) 22-1, 22-2, 22-3, 22-6, 
22-8 
Marmarth, N. Dak. (MRO) 21-20, 21-23 
Marquette Harbor, Minn. (NCS) 27-7, 27-24, 27-28 
Marseilles Lock and Dam, Ill. (NCC) 30-8, 30-37, 30-38 
Marsh Creek, Geneva, N.Y. (NCB) 32-44 
Marsh River, Minn. (NCS) 27-33 
Marshall, Minn. (NCS) 27-33, 27-34 
Marshalltown, Iowa (NCR) 28-4, 28-8, 28-10 
Marshland Drainage District, Oreg. (NPP) 37-53 
Martin, John, Reservoir, Colo. (SWA) 17-8, 17-16 
Martin, Ky. (ORH) 25-10, 25-21 
Martins Ferry, Ohio (ORP) 26-28, 26-31 
Martins Fork Lake, Ky. (ORN) 23-5, 23-10, 23-18 
Martis Creek Lake, Nev. and Calif. (SPK) 35-15, 35-26 
Marysville, Kans. (MRK) 20-33 
Marysville Lake, Calif. (SPK) 35-23, 35-27 
Mason and Menard Drainage District, Ill. (NCC) 30-41, 30-42 
Mason, W. Va. (ORH) 25-25, 25-31 
Mason J. Niblack Levee, Ind. (ORL) 24-16, 24-26, 24-34, 24- 
39, 24-42 
Matagorda Ship Channel, Tex. (SWG) 15-8, 15-18, 15-27, 15- 
35, 15-41 
Matawan Creek, N.J. (NAN) 2-45 
Mathews and Pine Canyons Dams, Nev. (SPL) 33-16, 33-23, 
33-28 
Matinicus Harbor, Maine (NED) 1-67 
Mats Mats Bay, Wash. (NPS) 38-27 
Mattapoisett Harbor, Mass. (NED) 1-67 
Mattaponi River, Va. (NAO) 5-27 
Mattituck Harbor, N.Y. (NAN) 2-8, 2-33, 2-37, 2-44 
Matunuck Beach, South Kingston, R.I. (NED) 1-69 
Mauckport, Ind. (ORL) 24-34, 24-39 
Maumee River Above Toledo, Ohio (NCE) 31-56 
Maunalua Bay Small Boat Harbor, Oahu, Hawaii (POD) 36- 
13 
Maurice River, N.J. (NAP) 3-26 
Maxwell Locks and Dam, Pa. (ORP) 26-25 
Mayaguez Harbor, P.R. (SAJ) 9-8, 9-26, 9-31 
Mayo, W.D., Lock and Dam, Okla. (SWL) (SWT) 18-2, 18-17, 
19-4, 19-32, 19-36 
Mayse, Pat, Lake, Tex. (SWT) 19-17, 19-27, 19-35 
Maysville, Ky. (ORH) 25-25, 25-30, 25-31 
McAlpine Locks and Dam, (ORD) 22-1, 22-3, 22-6, 22-9 
McClellan-Kerr Arkansas River Navigation System, Ark. and 
Okla. (SWT) 19-2, 19-32 
McCook, Nebr. (MRK) 20-32 
McCook Lake, S. Dak, (MRO) 21-22 
McDowell-Drift, Ky. (ORH) 25-30 
McGee Creek Drainage and Levee District, Ill. (LMS) 14-7, 
14-14, 14-16 
McGinnis Levee, Ind. (ORL) 24-34, 24-39 
McKees Rocks, Pa. (ORP) 26-28, 26-31 
McKenzie River Near Walterville, Oreg. (NPP) 37-55 
McKinney Bayou, Ark. (LMN) (MR&T) 11-55, 11-57, 42-19, 
42-52 
McLean Bottom Levee District No. 3, Ark. (SWL) 18-24 
McNary Lock and Dam-Lake Wallula, Oreg. and Wash. 
(NPW) 39-10, 39-13, 39-15, 39-22 
Meadow Grove, Buffalo Creek, Nebr. (MRO) 21-21 
Medomak River, Maine (NED) 1-67 
Meherrin River, N.C. (NAO) 5-27 
Melbourne Harbor, Fla. (SAJ) 9-40, 9-41 
Meldahl, Captain Anthony, Locks and Dam, Ky. (ORD) 22-1, 
22-2, 22-3, 22-8 
Mellen, Wis. (NCS) 27-34 
Melrose Reservoir, Va. (SAW) 6-31 
I-22

INDEX 
Melton Hill, Tenn. (ORN) 23-16 
Melvern Lake, Kans. (MRK) 20-9, 20-23, 20-31 
Melvern Lake and Pomona Lake (Road Improvement), Kans. 
Memphis, Wolf River and Nonconnah Creek, Tenn. (LMM) 
13-9 
Memphis Harbor, Tenn. (MR&T) 42-12, 42-30, 42-49, 42-56 
Menasha Lock and Dam (NCC) 30-36 
Menemsha Creek, Mass. (NED) 1-67 
Menominee Harbor and River, Mich. and Wis. (NCC) 30-11, 
30-23, 30-30, 30-34 
Meramec Park Lake, Mo. (LMS) 14-7, 14-14, 14-17 
Meramec River Basin, Mo. (LMS) 14-7, 14-16, 14-17, 14-19 
Merced County Stream Group, Calif. (SPK) 35-15, 35-26, 35- 
32 
Merced County Streams, Calif. (S'PK) 35-16, 35-26 
Merced River, Calif. (SPK) 35-17, 35-26 
Mercer Lake, Mo. (MRK) 20-10, 20-23 
Meredosia and Valley City, Ill. (LMS) 14-17 
Meredosia Lake and Willow Creek Levee, Ill (LMS) 14-18, 
14-19 
Meredosia Levee and Drainage District, Ill. (NCR) 28-4, 28-8, 
28-10 
Mermentau River, Bayou Nezpique, and Bayou Des Cannes, 
La. (LMN) 11-14, 11-38, 11-45 
Mermentau River, La. (LMN) 11-15, 11-38, 11-45 
Merriam, Turkey Creek, Kans. (MRK) 20-33 
Merrimack River Basin, N.H. and Mass. (NED) 1-35, 1-44, 1- 
74 
Merrimack River, Mass. (NED) 1-67 
Metamora Lake, Ind. (ORL) 24-36, 24-39 
Methow River, Wash. (NPS) 38-11, 38-28 
Metlakatla Harbor, Alaska (NPA) 40-6, 40-11, 40-13 
Metropolis, Ill. (ORL) 24-34, 24-39 
Miami Harbor, Fla. (SAJ) 9-9, 9-26, 9-31 
Miami River, Fla. (SAJ) 9-31 
Mianus River, Conn. (NED) 1-65, 1-67 
. Michael J. Kirwan Dam and Reservoir, Ohio (ORP) 26-10, 26- 
20 
Michigan City Harbor, Ind. (NCC) 30-12, 30-23, 30-30, 30-34 
Middle Beach, Conn. (NED) 1-20, 1-69 
Middle Creek, Calif. (SPK) 35-22, 35-34 
Middle Gila River Channel Improvements, Upper End of 
Safford Valley To Buttes Dam site (Camelsback Dam site 
to Salt River), Ariz. (SPL) 33-37 
Middle River and Connecting Channels, Calif. (SPK) 35-31 
Middle River and Dark Head Cfeek, Md. (NAB) 4-37 (ORN) 
23-5, 23-10 
Middleport, Ohio (ORH) 25-25, 25-29, 25-31 
Middlesboro Diversion Canal, Ky. (ORN) 23-18 
Middlesboro (Yellow Creek), Ky. (ORN) 23-17, 23-18 
Midland Drainage District, Oreg. (NPP) 37-50, 37-53, 37-54 
Middleton Shoals Dam and Lake, Ga., and S. C. (SAS) 8-16 
Milan, Ill. (NCR) 28-4, 28-8, 28-10 
Miles City, Mont. (MRO) 21-6, 21-14, 21-23 
Milford Harbor, Conn. (NED) 1-67 
Milford Haven, Va. (NAO) 5-26, 5-27 
Milford Lake, Kans. (MRK) 20-10, 20-23, 20-31 
Mill Bayou and Bayou Vidal (MR&T) 42-53 
Mill Creek, Md. (NAB) 4-37 
Mill Creek, N. C. (SAW) 6-32 
Mill Creek, Ohio (ORL) 24-17, 24-26, 24-36 
Mill Creek, Tex. (SWG) 15-32 
Mill Creek, Va. (NAO) 5-26, 5-27 
Mill Creek and South Slough at Milan, Ill. (NCR) 28-2, 28-8, 
28-10 
Mill Creek, Wash. (NPW) 39-16 
Mill Creek Lake, Ohio (ORH) 25-11, 25-11 
Mill Creek Lake, Wash. (NPW) 39-4, 39-12, 39-15 
Mill Creek Levees, Calif. (SPL) 33-37, 33-38 
Mill Four Drainage District, Oreg. (NPP) 37-55 
Mill Lake, Mo. (MRK) 20-33 
Miller, Ohio (ORH) 25-25, 25-31 
Miller Pond Levee Project, Ill. (LMS) 14-18 
Millers Ferry Lock and Dam, Ala. (SAM) 10-18, 10-19, 10-29, 
10-42 
Millersburg Reservoir, Ohio (ORH) 25-27, 25-32 
Millican Lake, Tex. (SWF) (SWL) 16-24, 18-6, 18-12, 18-22 
Millicoma and Coos Rivers, Oreg. (NPP) 37-7, 37-32, 37-40 
Millwood, W. Va. (ORH) 25-25, 25-31 
Millwood Lake, Ark. (SWL) (SWT) 19-16, 19-27, 19-35, 19-36 
Milton Harbor, N.Y. (NAN) 2-44, 2-45 
Milton-Freewater, Oreg. (NPW) 39-17, 39-18 
Milton, Ky. (ORL) 24-34, 24-39 
Milwaukee Harbor, Wis. (NCC) 30-12, 30-23, 30-30, 30-34 
Mines Creek, Spring Valley, Wis. (NCS) 27-33 
Mingo Creek, S. C. (SAN) 7-16 
Mingo Junction, Ohio (ORP) 26-28, 26-31 
Mining City Lake, Ky. (ORL) 24-36, 24-39 
Minneapolis, Minn. (NCD) 29-3 
Minneota, Minn. (NCS) 27-33, 27-34 
Minnesota River, Minn. (NCS) 27-7, 27-24, 27-28 
Minot, N. Dak. (NCS) 27-15, 27-25 
Miscellaneous Activities 48-1, 48-24 
Mispillion River, Del. (NAP) 3-26 
Misquamicut Beach, Westerly, R.I. (NED) 1-20, 1-69 
Massillon, Ohio (ORH) 25-10, 25-21, 25-25, 25-30 
Mission and Lapwai Creeks, Idaho (NPW) 39-18 
Mission Creek at Cashmere, Wash. (NPS) 38-28 
Mission Creek, Idaho (NPW) 39-17 
Mississinewa Lake, Ind. (ORL) 24-17, 24-26 
Mississippi and Leech Rivers, Minn. (NCS) 27-31 
Miss. County Drainage District No. 17, Ark. (MR&T) 42-54 
Mississippi Delta Region, La. (MR&T) 42-29, 42-58 
Mississippi River, Alton to Gale, Ill. (LMS) 14-19 
Mississippi River Agricultural Area No. 8, Mo. (LMS),14-8, 
14-14, 14-16 
Mississippi River Agricultural Area No. 10, Mo. (LMS) 14-19 
Mississippi River Agricultural Area No. 12, Mo. (LMS) 14-19 
Mississippi River Alluvial Valley Mapping (MR&T) 42-3 
Mississippi River and Alluvial Valley below Cape Girardeau, 
Mo. (MR&T) 42-2 
Mississippi River and Tributaries 
Alluvial Valley 42-2 
Bank Revetments and Dikes 42-1, 42-2, 42-31, 42-35, 42-39 
Channel Improvements 42-1, 42-2, 42-5, 42-12, 42-14, 42- 
51, 42-52, 42-54 
Dam and Lakes 42-22 
Flood Control 42-4, 42-56 
Levees 42-1, 42-2, 42-5, 42-44, 42-47, 42-48, 42-50 
Main Stem 42-5, 42-30 
Memphis, Tenn., District (LMM) 42-2, 42-4, 42-5, 42-10, 
42-39, 42-48, 42-50 42-54, 42-55, 42-56, 42-57, 42-58 
New Orleans, La., District (LMN) 42-1, 42-4, 42-5, 42-6, 
42-31, 42-44, 42-50, 42-51, 42-55, 42-56, (LMN) 42-57, 
42-58 
Vicksburg, Miss., District (LMK) 42-1, 42-4, 42-5, 42-8, 42- 
35, 42-47, 42-50, 42-52, 42-55, 42-56, (LMK) 42-57, 42- 
58 
Mississippi River and Tributaries-levees (MR&T) 42-5 
Mississippi River at St. Louis, Mo. 
Mississippi River, Baton Rouge to Gulf of Mexico, La. (LMN) 
11-15, 11-38, 11-45 
Mississippi River Between Brainerd and Grand Rapids, Minn. 
(NCS) 27-31 
I-23

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Mississippi River Between Missouri River and Minneapolis, 
Minn. (LMS) (NCS) (NCD) 14-2, 27-7, 29-1, 29-5, 29-10, 29- 
11 
Mississippi River Between Ohio and Missouri Rivers, Mo. and 
Ill. (LMS) 14-2, 14-13, 14-15 
Mississippi River - Channel Improvements (MR&T) 42-1, 42- 
2, 42-5, 42-12, 42-14 
Mississippi River Commission (MR&T) 42-1 
Mississippi River Delta at and below New Orleans, La. (New 
Orleans to Venice, La. Hurricane Protection) (LMN) 11- 
32, 11-40, 11-49 
Mississippi River Floods (MR&T) 42-4 
Mississippi River-Gulf Outlet, La. (LMN) 11-17, 11-38, 11-45 
Mississippi River-Gulf Outlet, Michoud Canal, La. (LMN) 11- 
18, 11-38, 11-45 
Mississippi River Improvements (MR&T) 42-12 
Mississippi River Levees (MR&T) 42-1, 42-2, 42-29, 42-44, 
42-47, 42-48, 42-50, 42-55, 42-56, 42-56, 42-57, 42-48 
Mississippi River Main Stem Channel Improvements (MR&T) 
42-30 
Mississippi River, Minn., Reservoirs at Headwaters of (NCS) 
27-9, 27-24, 27-28, 27-29 
Mississippi River, Minn. Reservoirs at Headwaters of (NCS) 
27-9, 27-24 
Mississippi River Near Aitkin, Minn. (NCS) 27-34 
Mississippi River Outlets, Venice, La. (LMN) 11-18, 11-38, 
11-46 
Mississippi River Standard Revetments (MR&T) 42-31, 42-35, 
42-39 
Mississquoi River at Richford, Vt. (NAN) 2-47 
Missouri River at Fort Peck, Mont. (MRO) 21-14 
Missouri River at New Haven, Mo. (MRK) 20-32, 20-33 
Missouri River, Aten, Nebr. (MRO) 21-23 
Missouri River, Garrison Dam to Lake Oahe, N. Dak. (MRO) 
21-6, 21-14, 21-19 
Missouri River, Kenslers Bend, Nebr. to Sioux City, Iowa 
(MRO) 21-7, 21-14 
Missouri River Levee System, Iowa, Nebr., Kans. and Mo. 
(Rulo, Nebr. to Mouth) (MRK) 20-11, 20-23, 20-26, 20- 
30, 20-31, 20-32 
Missouri River Levee System, Iowa, Nebr., Kans., and Mo. 
(MRO) 21-7, 21-15, 21-17, 21-19, 21-21 
Missouri River, Mo. (MR&T) 42-21 
Missouri River, Niobrara, Nebr. (MRO) 21-23 
Missouri River, Sioux City, Iowa to Fort Benton, Mont. 
(MRO) 21-18 
Missouri River, Sioux City, Iowa, to Mouth (Rulo, Nebr., to 
Mouth) (MRK) 20-2, 20-22, 20-25, 20-26, 20-28 
Missouri River, Sioux City, Iowa, to Mouth (Sioux City, Iowa, 
To Rulo, Nebr.) (MRO) 21-2, 21-14, 21-16, 21-18 
Missouri Pacific Railroad Bridge and Access Road, (SWG) 15- 
16 
Mobile Bay, Ala., to New Orleans, La. (SAM) 10-33 
Mobile Harbor, Ala. (SAM) 10-9, 10-27, 10-34 
Moccasin Springs, Mo. (LMS) 14-17 
Moccasin Swamp, N. C. (SAW) 6-32 
Mojave River Dam, Calif. (SPL) 33-15, 33-23, 33-28 
Mokelumne River, Calif. (SPK) 35-31 
Molalla River at Milk Creek Location, Oreg. (NPP) 37-55 
Molalla River at Ressel Location, Oreg. (NPP) 37-55 
Moline, Ill. (NCR) 28-4, 28-8, 28-10 
Moline Harbor, Ill. (NCD) 29-2, 29-8 
Monongahela River, Pa. and W. Va. (ORP) 26-2, 26-19, 26- 
22, 26-25, 26-27, 26-29 
Monoosnoc Brook, Mass. (NED) 1-74, 1-76 
Monoosnoc Lake, Mass. (NED) 1-74, 1-76 
Monroe Bay and Creek, Va. (NAB) 4-37 
Monroe Floodwall, La. (LMK) 12-5, 12-8, 12-9 
Monroe Floodwall, La. Plan B (LMK) 12-12 
Monroe Harbor, Mich. (NCE) 31-13, 31-39, 31-47 
Monroe Lake, Ind. (ORL) 24-17, 24-26, 24-36 
Montcalm, W. Va. (ORH) 25-30 
Monterey Harbor, Calif. (SPN) 34-21 
Montezuma, Ga. (SAM) 10-17 
Montgomery Locks and Dam, Pa. (ORD) 22-1, 22-2, 22-7 
Montour Falls, N.Y. (NCB) 32-44 
Moore Haven Lock (HGS-1 Mod.), Fla. (SAJ) 9-45 
Moorefield, W. Va. (NAB) 4-44 
Moores Ferry Reservoir, Va. (ORH) 25-27, 25-32 
Moorhead, Minn. (NCS) 27-32 
Moosabec Bar, Maine (NED) 1-67 
Morehead City Harbor, N. C. (SAW) 6-8, 6-24 
Morgan City and Vicinity, La., Hurricane Protection (LMN) 
11-33, 11-40, 11-49 
Morgan City, La. (MR&T) 42-14. 
Morgantown Lock and Dam, W. Va. (ORP) 26-25 
Morganza Floodway, La. (MR&T) 42-1, 42-14, 42-15, 42-51, 
42-56 
Moriches Inlet, N.Y. (NAN) 2-9, 2-33, 2-37, 2-44 
Mormon Slough, Calif. (SPK) 35-17, 35-22, 35-26 
Morrison, Bear Creek, Colo. (MRO) 21-23 
Morristown Harbor, N.Y. (NCB) 32-42 
Morro Bay Harbor, Calif. (SPL) 33-3, 33-21, 33-25 
Moscow, Ohio (ORL) 24-34, 24-39 
Mosquito Creek Lake, Ohio (ORP) 26-10, 26-20, 26-29 
Moss Bluff Lock, Fla. (SAJ) 9-49 
Moss Landing Harbor, Calif. (SPN) 34-3, 34-15 
Mott, N. Dak. (MRO) 21-23 
Mound City Locks and Dam, Ill. (ORD) 22-1, 22-9 
Mounds and Mound City, Ill. (LMM) 13-9 
Moundsville, W. Va. (ORP) 26-28, 26-31 
Mount Clemens, Mich. (NCE) 31-57 
Mount Clemens Spillway ar.d Cutoff Canal, Mich. (NCE) 31- 
30 
Mount Vernon, Ohio (ORH) 25-30 
Mountain Brook Dam, N.H. (NED) 1-74, 1-76 
Mouth of Sangamon River, Ill. (NCC) 30-19, 30-25 
Mouth of Yazoo River, Miss. (LMK) 12-11 
Moyock Creek, N. C. (SAW) 6-32 
Mt. Carmel, Ill. (ORL) 24-39, 24-42 
Mt. Holly, N.J. (NAP) 3-17, 3-28 
Mt. Morris Lake, N.Y. (NCB) 32-22, 32-29 
Mud and Baskett Slough, Rickreall Creek, Oreg. (NPP) 37-55 
Mud Creek, Broken Bow, Nebr. (MRO) 21-7, 21-15 
Mud Creek, Idabel, Okla. (SW.T) 19-16 
Mud Lake Area, Idaho (NPW) 39-16 
Mud Lake Pumping Station, Tenn. (MR&T) 42-2, 42-29, 42- 
58 
Mud Mountain Dam, Wash. (NPS) 38-9, 38-17, 38-23 
Mud River, W. Va. (ORH) 25-32 
Mud River Reservoir, W. Va. (ORH) 25-27 
Muddy Creek Dam, Pa. (ORP) 26-11, 26-20 
Muddy Hook and Tyler Coves, Md. (NAB) 4-37 
Mulberry Creek, Va. (NAO) 5-27 
Mullet Key, Fla. (SAJ) 9-43 
Multnomah Channel, Oreg. (NPP) 37-46, 37-47 
Multnomah County Drainage District 1, Oreg. (NPP) 37-50, 
37-53, 37-54 
Muncie, Ind. (ORL) 24-39, 24-42 
Murderkill River, Del. (NAP) 3-10, 3-20 
Murfreesboro Dam and Lake (LMK) 12-12 
Murray Lock and Dam, Ark. (SWL) 18-2, 18-4, 18-16 
Murrells Inlet, S. C. (SAN) 7-5, 7-11, 7-14 
Muscatatuck River, Ind. (ORL) 24-43 
I-24

TINDEX 
Muscatine, Mad Creek, Iowa (NCR) 28-4, 28-8, 28-10, 28-11, 
28-13 
Muscatine Harbor, Iowa (NCD) 29-2, 29-8 
Muscatine Island Levee District and Muscatine-Louisa County 
Drainage District No. 13, Iowa (NCR) 28-12, 28-13 
Muskegon Harbor, Mich. (NCE) 31-14, 31-39, 31-47 
Muskingum River, Ohio (ORH) 25-24, 25-27 
Muskingum River Lakes, Ohio (ORH) 25-11, 25-21, 25-27 
Mustinka River, Minn. (NCS) 27-32, 27-33 
Myers Chuck Harbor, Alaska (NPA) 40-15 
Mystic River, Conn. (NED) 1-65, 1-67, 1-78 
Mystic River, Mass. (NED) 1-67
N 
Nagel Drainage District Iowa (MRO) 21-21 
Nahunta Swamp, N. C. (SAW) 6-32 
Naknek River, Alaska (NPA) 40-15 
Namo River, Guam 36-8 
Nan Cove, Md. (NAB) 4-37 
Nandua Creek, Va. (NAO) 5-26, 5-27 
Nansemond River, Va. (NAO) 5-13, 5-20, 5-24, 5-26 
Nantasket Beach, Mass. (NED) 1-69 
Nanticoke River (Including Northwest Fork), Del. and Md. 
(NAB) 4-36, 4-37 
Nanticoke River, Md. (NAB) 4-36, 4-37 
Nanticoke River at Bivalve, Md. (NAB) 4-6, 4-26, 4-32 
Nantucket (Harbor of Refuge), Mass. (NED) 1-65, 1-67 
Napa River Basin, Calif. (SPN) 34-12, 34-16 
Napa River, Calif. (SPN) 34-21 
Napatree Beach, R.I. (NED) 1-69 
Narragansett Pier, R.I. (NED) 1-78 
Narragaugus River, Maine (NED) 1-65, 1-67 
Narrows Dam-Lake Greeson, Ark. (LMK) 12-4, 12-8, 12-12 
Narrows of Lake Champlain, N.Y. and Vt. (NAN) 2-9, 2-33, 
2-38, 2-44 
Naselle River and Willapa River and Harbor, Wash. (NPS) 
38-8, 38-17, 38-22, 38-25 
Nashua, N.H. (NED) 1-44, 1-74, 1-76 
Natchez Port Area, Miss. (LMK) 12-12 
Natchitoches Parish, La. (LMN) 11-56, 11-57 
Navajo Reservoir, N. Mex. (SPK) 35-31 
Navarro Mills Lake, Tex. (SWF) 16-13, 16-20, 16-26 
Navasota Lake, Tex. (SWF) 16-22, 16-24 
Nawiliwili Small Boat Harbor, Kauai, Hawaii (POD) 36-4, 36- 
9, 36-13 
Neabsco Creek, Va. (NAB) 4-6, 4-26, 4-32 
Neah Bay, Wash. (NPS) 38-26, 38-27 
Neale Sound, Md. (NAB) 4-37 
Near Springfield on Sangamon River, Ill. (NCC) 30-42 
Neavitt Harbor, Md. (NAB) 4-37 
Neches and Angelina Rivers, Tex. (SWF) 16-2, 16-23 
Needles, San Bernardino County, Calif. (SPL) 33-38 
Nehalem Bay, Oreg. (NPP) 37-47 
Nehalem River, Vicinity of Nehalem, Oreg. (NPP) 37-56 
Nemaha River, Tecumseh, Nebr. (MRK) 20-32 
Neodesha Lake, Kans. (SWL) (SWT) 18-18, 19-32, 19-38 
Neon-Fleming, Ky. (ORL) 24-39, 24-43 
Neponset River, Mass. (NED) 1-65 
Neshaminy State Park Harbor, Pa. (NAP) 3-11, 3-20 
Neuse River Barrier, N. C. (SAW) 6-32 
Neuse River Basin, N. C. (SAW) 6-17, 6-31 
Neuse River, N. C. (SAW) 6-28, 6-29 
Neva and Olga Straits, Alaska (NPA) j/-uk 
Neville Island, Pa. (ORP) 26-28, 26-31 
New Albany, Ind. (ORL) 24-34, 24-39, 24-42 
New Amsterdam, Ind. (ORL) 24-34, 24-39 
New Bedford, Mass. (NED) 1-44, 1-53 
New Bedford-Fairhaven Barrier, Mass. (NED) 1-44 
New Bedford and Fairhaven Harbor, Mass. (NED) 1-67 
New Bedford, Fairhaven and Acushnet, Mass. (NED) 1-38, 1- 
63 
New Bedford Harbor, Mass. (NED) 1-65 
New Buffalo Harbor, Mich. (NCC) 30-13, 30-24 
New Bullards Bar, Calif. (SPK) 35-34 
New Cumberland, W. Va. (ORP) 26-28, 26-31 
New Cumberland Locks and Dam, Ohio (ORD) 22-1, 22-2, 
22-3, 22-7 
New Harbor, Maine (NED) 1-67 
New Harmony, Ind. (ORL) 24-34, 24-39 
New Harmony Bridge, Ill. (ORL) 24-34, 24-39 
New Hartford, Iowa (NCR) 28-13 
New Haven Breakwater, Conn. (NED) 1-67 
New Haven Harbor, Conn. (NED) 1-13, 1-48, 1-59, 1-65 
New Hogan Lake, Calif. (SPK) 35-5, 35-25 
New Hope Lake, N. C. (SAW) 6-14, 6-25, 6-31 
New Jersey Inlets and Beaches-Corson Inlet and Ludlam 
Beach (NAP) 3-11, 3-20 
New Jersey Inlets and Beaches-Great Egg Harbor Inlet and 
Peck Beach (NAP) 3-11, 3-20 
New Jersey Intracoastal Waterway (NAP) 3-12, 3-20 
New Kensington and Parnassus, Pa. (ORP) 26-28, 26-31 
New London, Conn. (NED) 1-38, 1-53, 1-64 
New London Harbor, Conn. (NED) 1-67 
New Madrid Floodway, Mo. (MR&T) 42-13, 42-56, 42-57 
New Madrid Harbor, Mo. (LMM) 13-2, 13-7, 13-8 
New Martinsville, W. Va. (ORH) 25-25, 25-31 
New Matamoras, Ohio (ORH) 25-25, 25-31 
New Melones Lake, Calif. (SPK) 35-23, 35-27 
New Orleans District, Bank Revetments and Dikes (MR&T) 
42-31 
New Orleans District, Project Levees (MR&T) 42-44 
New Pass, Sarasota, Fla. (SAJ) 9-10, 9-26, 9-31 
New Poe Lock, Mich. (NCE) 31-54 
New Richmond, Ohio (ORL) 24-34, 24-39 
New River, Fla. (SAJ) 9-41 
New River, N. C. (SAW) 6-32 
New River, Onslow County, N. C. (SAW) 6-20, 6-32 
New River, Va. and W. Va. (ORH) 25-24 
New Rochelle Harbor, N.Y. (NAN) 2-44, 2-45 
New York Harbor, N.Y. (NAN) 2-44 
New York Harbor - Collection and Removal of Drift (NAN) 
2-12, 2-33, 2-38 
New York Harbor - Entrance Channels and Anchorage Areas 
(NAN) 2-13, 2-33, 2-39 
New York Harbor, Supervisor of (NAN) 2-16, 2-33, 2-43 
New York and New Jersey Channels (NAN) 2-11, 2-33, 2-38, 
2-42 
Newark, Ohio (ORH) 25-12, 25-21, 25-25, 25-30 
Newark Bay, Hackensack and Passaic Rivers, N.J. (NAN) 2- 
10, 2-33, 2-38, 2-44 
Newbegun Creek, N. C. (SAW) 6-29 
Newburgh, Ind. (ORL) 24-39, 24-43 
Newburgh Locks and Dam, Ind. (ORD) 22-1, 22-2, 22-3, 22-9 
Newburyport Harbor, Mass. (NED) 1-13, 1-48, 1-59 
Newmarket Creek, Va. (NAO) 5-28 
Newport, Ark. (SWL) 18-7, 18-23, 18-24 
Newport, Ky. (ORL) 24-34, 24-39, 24-42 
Newport, Ohio (ORH) 25-25, 25-31 
Newport Bay Harbor, Calif. (SPL) 33-30 
Newport Harbor, R.I. (NED) 1-67 
Newport News, Va., Channel to (NAO) 5-8, 5-23 
I-25

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Newport News Creek, Va. (NAO) 5-13, 5-20, 5-24 
Newport-Wilders, Ky. (ORL) 24-18, 24-26 
Newry-Old Pickens Dam and Lake, S. C. (SAS) 8-16 
Newt Graham Lock and Dam, Okla. (SWL) (SWT) 18-2, 18- 
17, 19-4, 19-32, 19-35 
Newtown Creek, N.Y. (NAN) 2-44, 2-45 
Niagara Board of Control, International 48-8 
Niagara Committee, International 48-10 
Niagara Remedial Works, N.Y. (NCB) 32-42 
Niagara River, N.Y. (NCB) 32-42 
Niantic Bay and Harbor, Conn. (NED) 1-67 
Niblack, Mason J., Levee, Ind. (ORL) 24-16, 24-26, 24-34, 24- 
39, 24-42 
Nichols, N.Y. (NAB) 4-42, 4-43, 4-44 
Nickajack Project, Tenn. (ORN) 23-16 
Nimishillen Creek, Canton, Ohio (ORH) 25-30 
Nimrod Lake, Ark. (SWL) 18-2, 18-6, 18-13, 18-18, 18-21 
Ninilchik Harbor, Alaska (NPA) 40-6, 40-11, 40-14 
Niobrara, Nebr. (MRO) 21-12 
Nishnabotna River at Hamburg, Iowa (MRO) 21-23 
Nisqually River, Wash. (NPS) 38-11 
Nixon Creek, Tenn. (LMM) 13-9 
Nolin Lake, Ky. (ORL) 24-18, 24-26, 24-36 
Nome Harbor, Alaska (NPA) 40-7, 40-11, 40-14 
Nomini Bay and Creek, Va. (NAB) 4-37 
Nookagee Lake, Mass. (NED) 1-37, 1-53, 1-63, 1-74 
Nooksack River, Wash. (NPS) 38-11 
Norfolk Floodwall, Va. (NAO) 5-28 
Norfolk Harbor, Va. (NAO) 5-9, 5-23 
Norfolk, Nebr. (MRO) 21-21, 21-23 
Norfork Lake, Ark. (SWL) 18-7, 18-10, 18-13, 18-22, 18-23 
Normal, Ky. (ORH) 25-25, 25-31 
Norrell Lock and Dam, Ark. (SWL) 18-2, 18-4, 18-16 
North Adams, Mass. (NAN) 2-47 
North Alexander Drainage and Levee District, Ill. (LMS) 14- 
19 
North Andover and Lawrence, Mass. (NED) 1-74, 1-76 
North Branch of Kokosing River Lake, Ohio (ORH) 25-12, 
25-21 
North Ellenville, N.Y. (NAN) 2-23, 2-34, 2-40 
North Fork, Alturas, Calif. (SPK) 35-22, 35-34 
North Fork Dam and Lake, Tex. (SWF) 16-24 
North Fork of Pound River Lake, Va. (ORH) 25-13, 25-21 
North Frankfort Area, Ky. (ORL) 24-33 
Northampton, Mass. (NED) 1-44, 1-72, 1-76 
North Hampton Beach, North Hampton, N.H. (NED) 1-69 
North Hartland Lake, Vt. (NED) 1-27, 1-51, 1-62, 1-71 
North Little Rock, Ark. (SWL) 18-24 
North Little Rock to Gillett, Ark. (Above Plum Bayou) (SWL) 
18-24 
North Nashua River, Mass. (NED) 1-74, 1-76 
North River Dike, N. C. (SAW) 6-32 
North Scituate Beach, Scituate, Mass. (NED) 1-20, 1-69 
North Springfield Lake, Vt. (NED) 1-27, 1-51, 1-62, 1-71 
North Wildwood, N.J. (NAP) 3-27 
Northeast (Cape Fear) River, N. C. (SAW) 6-29, 6-32 
Northeast Harbor, Maine (NED) 1-67 
Northeast River, Md. (NAB) 4-37 
Northfield Brook Lake, Conn. (NED) 1-34, 1-52, 1-63, 1-73 
Northport Harbor, N.Y. (NAN) 2-45 
Northport Harbor, Wis. (NCC) 30-13, 30-24 
Norwalk, Conn. (NED) 1-44, 1-76 
Norwalk Harbor, Conn. (NED) 1-65, 1-67 
Norwalk-Wilton, Conn. (NED) 1-67 
Norwich, Conn. (NED) 1-75, 1-76 
Norwich, N.Y. (NAB) 4-44 
Noxubee River, Miss. (SAM) 10-40 
Noyo River and Harbor, Calif. (SPN) 34-3, 34-15, 34-18 
Nutwood Drainage and Levee District, Ill. (LMS) 14-19 
O 
Oahe Dam and Lake Oahe, S. Dak. and N. Dak. (MRO) 21- 
12, 21-16, 21-19 
Oak Bluffs Town Beach, Mass. (NED) 1-19, 1-49, 1-60 
Oak Orchard Harbor, N.Y. (NCB) 32-14, 32-27 
Oakdale, Pa. (ORP) 26-31 
Oakford Special Drainage District, Ill. (NCC) 30-41, 30-42 
Oakland Harbor, Calif. (SPN) 34-4, 34-15, 34-18 
Obey River, Tenn. (ORN) 23-17 
Obion Creek, Ky. (MR&T) 42-54 
Obion River, Tenn. (LMM) (MR&T) 13-9, 42-2, 42-11, 42-13, 
42-21 
Obion River Diversion Channel, Tenn. (MR&T) 42-54 
O'Brien, T.J., Lock and Dam, Ill. (NCC) 30-7, 30-37, 30-38 
Occohannock Creek, Va. (NAO) 5-26, 5-27 
Occoquan Creek, Va. (NAB) 4-38 
Ocean Beach, Calif. (SPL) 33-31 
Ocean City Harbor and Inlet and Sinepuxent Bay, Md. 
(NAB) 4-7, 4-26, 4-33 
Ocean City, N.J. (NAP) 3-27 
Oceanside, Calif. (SPL) 33-31 
Oceanside Harbor, Calif. (SPL) 33-3, 33-21, 33-25 
O. C. Fisher Dam and Lake, Tex. (SWF) 16-13, 16-20 
Ocholockonee (Ochlockney) River, Ga. and Fla. (SAM) 10-40 
Oconto Harbor, Wis. (NCC) 30-14, 30-24, 30-31, 30-35 
Ocracoke Inlet, N. C. (SAW) 6-8, 6-24 
Ocracoke Island, N. C. (SAW) 6-18, 6-25 
Offatts Bayou, Tex. (SWG) 15-6, 15-38 
Ofu Harbor, American Samoa (POD) 36-5, 36-10 
Ogdensburg Harbor, N.Y. (NCB) 32-42 
Ohio River Basin (Huntington District) (ORH) 25-13, 25-21, 
25-25, 25-27, 25-28, 25-29 
Ohio River Basin (Louisville Dist.) (ORL) 24-18, 24-26, 24-28, 
24-33, 24-36 
Ohio River Basin (Nashville Dist.) (ORN) 23-5, 23-12, 23-17 
Ohio River Basin (Pittsburgh District) (ORP) 26-11, 26-20, 26- 
23, 26-29 
Ohio River, Construction of Locks and Dams on (ORD) 22-1, 
22-5, 22-7 
Ohio River, Ill. and Ky. (MR&T) 42-2, 42-21 
Ohio River, Open Channel Work (ORD) 22-4, 22-5, 22-11 
Oil City, Pa. (ORP) 26-30, 26-31 
Okabena Creek at Worthington, Minn. (NCR) 28-12, 28-13 
Okanogan River, Wash. (NPS) 38-11, 38-28 
Okatibbee Lake, Miss. (SAM) 10-14, 10-28, 10-36 
Okeechobee Waterway, Fla. (SAJ) 9-10, 9-26, 9-32, 9-39 
Oklahoma City Floodway, Okla. (SWT) 19-37, 19-38 
Oklawaha River, Fla. (SAJ) 9-11, 9-26, 9-32 
Olcott Harbor, N.Y. (NCB) 32-42 
Old Field Swamp, N. C. (SAN) 7-17 
Old Harbor, Alaska (NPA) 40-15 
Old Hickory Lock and Dam, Tenn. (ORN) 23-2, 23-19 
Old River, Calif. (SPK) 35-31 
Old River, La. (MR&T) 42-1, 42-8, 42-12, 42-29, 42-55, 42-58 
Old River, Standard Revetments (MR&T) 42-33 
Old Town Creek, Miss. (SAM) 10-17, 10-40 
Oldmans Creek, N.J. (NAP) 3-26 
Olean, N.Y. (ORP) 26-28, 26-30, 26-31 
Olive Hill, Ky. (ORH) 25-30 
Oliver, William Bacon, Lock and Dam, Ala. (SAM) 10-5, 10- 
38 
I-26

INDEX 
Olympia Harbor, Wash. (NPS) 38-5, 38-16, 38-21, 38-26 
Omaha, Nebr. (MRO) 21-19, 21-21, 21-23 
Onaga Lake, Kans. (MRK) 20-11, 20-23 
Onancock River, Va. (NAO) 5-26, 5-27 
Onondaga Creek, Nedrow, N.Y. (NCB) 32-44 
Ontonagon Harbor, Mich. (NCS) 27-8, 27-24, 27-28 
Oologah Lake, Okla. (SWL) (SWT) 18-18, 19-16, 19-27, 19- 
31, 19-32, 19-35 
Oostanaula and Coosawatee Rivers, Ga. (SAM) 10-40 
Opekiska Lock and Dam, W. Va. (ORP) 26-25 
Open River, Lewiston to Johnson Bar Landing (NPW) 39-24 
Open River, Pasco to Lewiston (NPW) 39-24 
Optima Lake, Okla. (SWT) 19-16, 19-27, 19-31 
Orange Reservoir, N. C. (SAW) 6-31 
Orange River, Fla. (SAJ) 9-41 
Oregon Slough, Oreg. (NPP) 37-46, 37-47 
Orleans, Ind. (ORL) 24-39 
Oro Grande Wash Channel Improvements, Calif. (SPL) 33- 
37, 33-38 
Orowoc Creek, N.Y. (NAN) 2-45 
Orwell Reservoir, Minn. (NCS) 27-32 
Osage River Lock and Dam, Mo. (MRK) 20-29 
Osage River, Mo. and Kans. (MRK) 20-32 
Osawatomie, Osage (Marais Des Cygnes) River, Kans. (MRK) 
20-31, 20-32 
Osawatomie, Pottawatomie Creek, Kans. (MRK) 20-33 
Osceola Harbor, Ark. (LMM) 13-2, 13-7, 13-8 
Osoyoos Lake Board of Control, International 48-21 
Oswego Harbor, N.Y. (NCB) 32-15, 32-27, 32-38 
Ottawa, Ohio (NCE) 31-57 
Ottawa River Harbor, Mich. and Ohio (NCE) 31-14, 31-39, 
31-47 
Ottawa, Kans. (MRK) 20-31, 20-32, 20-33 
Otter Brook Lake, N.H. (NED) 1-28, 1-51, 1-62, 1-71 
Otter Creek, Vt. (NAN) 2-45 
Otter Tail River, Minn. (NCS) 27-32, 27-33 
Ouachita and Black Rivers, Ark. and La., Locks and Dams 
(LMK) 12-10 
Ouachita and Black Rivers below Camden, Ark. (LMK) 12-2, 
12-8, 12-9 
Ouachita River and Tributaries, Ark. and La. (LMK) 12-3, 
12-9, 12-12 
Ouachita River Levees (MR&T) 42-50 
Ouiver River, Miss. (MR&T) 42-52 
Overton-Red River Waterway, La. (LMN) 11-19, 11-38, 11-46 
Ottumwa, Iowa (NCR) 28-5, 28-8, 28-10 
Ouachita River Levees, La. (LMK) 12-6, 12-8, 12-12 
Owasco Inlet and Outlet, Montville and Dry Creek, State 
Ditch and Crane Brook N.Y. (NCB) 32-44 
Owens Stream, Calif. (SPK) 35-16 
Owensboro, Ky. (ORL) 24-34, 24-39 
Owls Head Harbor, Maine (NED) 1-65, 1-67 
Oxford, Md. (NAB) 4-39 
Oxford, N.Y. (NAB) 4-19, 4-29, 4-40, 4-41 
Oyster Channel, Va. (NAO) 5-26, 5-27 
Oyster Creek, Tex. (SWG) 15-32 
Ozan Creek, Ark. (LMK) 12-12 
Ozark Lock and Dam, Ark. (SWL) 18-2, 18-10, 18-13, 18-16 
Ozona, Fla., Channel and Turning Basin (SAJ) 9-41 
P 
Pacific County Diking Improvement District 1, Wash. (NPP) 
37-53 
Paducah, Ky. (ORL) 24-34, 24-39, 24-42 
Pagan River, Va. (NAO) 5-26, 5-27 
Paint Creek, Washington Court House, Ohio (ORH) 25-30 
Paint Creek Lake, Ohio (ORH) 25-13, 25-21, 25-27 
Paint Rock River, Ala. (ORN) 23-18 
Painted Post, N.Y. (NAB) 4-41, 4-44 
Painted Rock Dam, Ariz. (SPL) 33-10, 33-22, 33-27 
Paintsville Lake, Ky. (ORH) 25-14, 25-22 
Pajaro River, Calif. (SPN) 34-23 
Palm Beach, Fla., Side Channel and Basin (SAJ) 9-41 
Palm Beach County, Fla., from Martin County Line to Lake 
Worth Inlet And from South Lake Worth Inlet to 
Brownard County Line (SAJ) 9-18, 9-28, 9-35 
Palm Beach County, Fla. from Lake Worth Inlet to South 
Lake Worth Inlet (SAJ) 9-43 
Palm Beach Harbor, Fla. (SAJ) 9-11, 9-26, 9-32 
Palouse River, Wash. (NPW) 39-16 
Pamlico and Tar Rivers, N. C. (SAW) 6-29 
Pamunkey River, Va. (NAO) 5-27 
Panacea Harbor, Fla. (SAM) 10-39 
Panacea Harbor, Miss. (SAM) 10-40 
Panama City Harbor, Fla. (SAM) 10-10, 10-27, 10-34 
Pantego Creek and Cucklers Creek, N. C. (SAW) 6-20, 6-32 
Panther Creek, Ky. (ORL) 24-39, 24-43 
Panther Creek Lake, W. Va. (ORH) 25-14, 25-22 
Panther Creek Levee, Ill. (NCC) 30-42 
Papillion Creek and Tributaries, Lakes, Nebr. (MRO) 21-7, 
21-15 
Parish Creek, Md. (NAB) 4-38 
Park River, Hartford Conn. (NED) 1-28, 1-51, 1-62, 1-72 
Park River, N. Dak. (NCS) 27-33 
Parker Creek, Va. (NAO) 5-26, 5-27 
Parkersburg, W. Va. (ORH) 25-25, 25-30, 25-31 
Parrotts Creek, Va. (NAO) 5-26, 5-27 
Pascagoula Harbor, Miss. (SAM) 10-10, 10-27, 10-34 
Pascagoula River, Miss. (SAM) 10-39, 10-40 
Pasquotank Dike, N. C. (SAW) 6-20 
Pasquotank River, N. C. (SAW) 6-32 
Pass-A-Grille Pass, Fla. (SAJ) 9-40, 9-41 
Pass Christian Harbor, Miss. (SAM) 10-11, 10-27, 10-35 
Pass Manchac, La. (LMN) 11-53 
Passamaquoddy Tidal Power Project, Maine (NED) 1-78 
Pat Mayse Lake, Tex. (SWT) 19-17, 19-27, 19-35 
Patchogue River, Conn. (NED) 1-65, 1-67 
Patman, Wright, Dam and Lake, Tex. (LMN) 11-35, 11-41, 
11-49, 11-54, 11-55 
Patoka Lake, Ind. (ORL) 24-19, 24-26 
Patriot, Ind. (ORL) 24-34, 24-39 
Pattonsburg Lake, Mo. (MRK) 20-11, 20-23 
Patuxent River, Md. (NAB) 4-38 
Pawcatuck, Conn. (NED) 1-44, 1-76 
Pawcatuck Barrier, Conn. (NED) 1-44 
Pawcatuck River, R.I. and Conn. (NED) 1-67 
Pawtucket, R.I. (NED) 1-70, 1-76 
Pawtuxet Cove, R.I. (NED) 1-14, 1-48, 1-60 
Payette Valley, Idaho (NPW) 39-16 
Peacock Creek, Ga. (SAS) 8-8, 8-11, 8-15 
Pearl River, Miss., and La., Jackson, Miss. (SAM) 10-41 
Pearl River, Miss., and La. (SAM) 10-11, 10-27, 10-35, 10-39 
Pearl River, Miss., Edinburg to Jackson, Miss. (SAM) 10-40 
Pearl River Lock No. 1, La. (SAM) 10-12, 10-39 
Pearl River Lock No. 2, La. (SAM) 10-12, 10-39 
Pearl River Lock No. 3, La. (SAM) 10-12, 10-39 
Pecan Bayou Lake, Tex. (SWF) 16-22 
Pecatonica River at Darlington, Wis. (NCR) 28-13 
Peconic River, N.Y. (NAN) 2-45 
Pecos, Tex. (SWA) 17-10, 17-16, 17-18 
Peekskill Harbor, N.Y. (NAN) 2-45 
I-27

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Pekin and LaMarsh Drainage and Levee District, Ill. (NCC) 
30-41, 30-42 
Pelican Harbor, Alaska (NPA) 40-15 
Pelucia Creek, Miss. (MR&T) 42-52 
Pembina River Engineering Board, International 48-18 
Pembina River Lake, N. Dak. (NCS) 27-34 
Pembroke Creek, N. C. (SAW) 6-9, 6-24 
Pendleton, Oreg. (NPP) 37-53 
Pendleton Levees, Oreg. (NPP) 37-55 
Peninsula Drainage District 1, Oreg. (NPP) 37-50, 37-53, 37- 
54 
Peninsula Drainage District 2, Oreg. (NPP) 37-50, 37-53, 37- 
54 
Penny Slough, Ill. (NCR) 28-13 
Penny Slough Drainage and Levee District, Ill. (NCR) 28-11 
Penobscot River, Maine (NED) 1-65, 1-67 
Pensacola, Okla. (SWL) 18-2, 18-18 
Pensacola Bay, Fla., to Mobile Bay, Ala. (SAM) 10-33 
Pensacola Harbor, Fla. (SAM) 10-12, 10-27, 10-35 
Pensacola Lake, Okla. (SWT) 19-17, 19-27, 19-32, 19-36, 19- 
37 
Pensaukee Harbor, Wis. (NCC) 30-40 
Pentwater Harbor, Mich. (NCE) 31-15, 31-39, 31-47 
Peoria, Ill. (NCC) 30-42 
Peoria Lock and Dam, Ill. (NCC) 30-7, 30-37, 30-38 
Pepin Harbor, Wis. (NCD) 29-3, 29-8 
Pepper Creek, Del. (NAP) 3-26 
Pepperell Cove, Maine (NED) 1-65, 1-67 
Perdido Pass Channel, Ala. (SAM) 10-12, 10-27, 10-35 
Permanent International Association of Navigation 
Congresses 46-1 
Perquimans River, N. C. (SAW) 6-20, 6-29, 6-32 
Perry County Drainage and Levee Districts Nos. 1, 2, and 3, 
Mo. (LMS) 14-9, 14-14, 14-16 
Perry Lake Area (Road Improvements), Kans. (MRK) 20-12, 
20-23 
Perry Lake, Kans. (MRK) 20-12, 20-24, 20-31 
Perth Amboy, N.J. (NAN) 2-47 
Petaluma River, Calif. (SPN) 34-5, 34-15 
Petersburg Harbor, Alaska (NPA) 40-15 
Petit Anse, Tigre, and Carlin Bayous, La. (LMN) 11-20, 11- 
38, 11-46 
Petit Jean River, Ark. (SWL) 18-24 
Petoskey, Mich. (NCE) 31-56 
Peyton Creek, Tex. (SWG) 15-14, 15-19, 15-30 
Phillippi Creek Basin, Fla. (SAJ) 9-51 
Phillips Reservoir, Mass. (NED) 1-74, 1-76 
Philpott Lake, Va. (SAW) 6-21, 6-26, 6-31 
Phoebus Channel, Va. (NAO) 5-26 
Phoenix and Vicinity (INCLUDING New River), Ariz. (SPL) 
33-11, 33-22, 33-27 
PIANC 46-1 
Pick-Sloan Missouri Basin Program, Mo., Kans., and Nebr. 
(MRK) (MRO) 20-13, 20-24, 20-26, 20-31, 21-8, 21-17, 
21-19 
Pickwick Landing, Tenn. (ORN) 23-16 
Pierce, Nebr. (MRO) 21-21, 21-23 
Pig Island Gut, Maine (NED) 1-67 
Pike Island Locks and Dam, W. Va. (ORD) 22-1, 22-2, 22-3, 
22-7 
Pilot Rock, Birch Creek, Oreg. (NPP) 37-55 
Pinal Creek Channel Improvements (Globe) (Deferred), Ariz. 
(SPL) 33-37 
Pine and Mathews Canyons Dams and Reservoirs, Nev. (SPL) 
33-16, 33-23, 33-28 
Pine Bluff, Ark., Local Protection (LMK) 12-12 
Pine Bluff Marine Terminal (SWL) 18-2 
Pine Creek, Angle Inlet, Minn. (NCS) 27-31 
Pine Creek Lake, Okla. (SWT) 19-17, 19-27, 19-35, 19-36 
Pine Flat Lake and Kings River, Calif. (SPK) 35-17, 35-22, 35- 
26 
Pine Ford Lake, Mo. (LMS) 14-17 
Pine Mountain Lake, Ark. (SWL) 18-6, 18-13 
Pine River Reservoir, Minn. (NCS) 27-29 
Pine River, Mich. (NCE) 31-56 
Pinellas County, Fla. (SAJ) 9-19, 9-28, 9-35 
Pineville, Ky. (ORN) 23-18 
Pineville, La. (LMN) 11-56, 11-57 
Pinole Creek, Calif. (SPN) 34-23 
Pinon Canyon Dam, Colo. (SWA) 17-20 
Pioneer Lake, Kans. (MRK) 20-33 
Pioneer Lake, Colo. and Kans. (MRK) 20-31 
Pipestem Lake, N. Dak. (MRO) 21-8, 21-15 
Pithlachascotee River, Fla. (SAJ) 9-41 
Pittsburgh, Pa. (Golden Triangle) (ORP) 26-28, 26-31 
Pittsburgh, Pa. (North Side) (ORP) 26-28, 26-31 
Pittsburgh, Pa. (the Strip) (ORP) 26-28, 26-31 
Pittsburgh Harbor, Pa. (ORP) 26-27 
Placer Creek, Idaho (NPS) 38-28 
Plaquemine Lock, La. (LMN) 11-52 
Platte River, Mo. (MRK) 20-32 
Platte River, Mo., Channel Improvement (MRK) 20-33 
Platte River and Lost Creek, Schuyler, Nebr. (MRO) 21-23 
Platte River Near Schuyler, Nebr. (MRO) 21-23 
Plattsburgh Harbor, N.Y. (NAN) 2-45 
Pleasant Bay, Mass. (NED) 1-67 
Pleasant River, Maine (NED) 1-67 
Pleasanton Floodway, Tex. (SWF) 16-26 
Plum Creek, Ky. (ORL) 24-43 
Plum Island, Mass. (NED) 1-19, 1-49, 1-61 
Plymouth Harbor, Mass. (NED) 1-14, 1-48, 1-60, 1-65 
Plymouth, Pa. (NAB) 4-44 
Plymouth Town Beach, Mass. (NED) 1-20 
Poca Reservoir, W. Va. (ORH) 25-27, 25-32 
Pocatello Unit, Portneuf River, Idaho (NPW) 39-17 
Pocomoke River, Md. (NAB) 4-36, 4-38 
Point Judith, R.I. (NED) 1-76 
Point Judith Harbor, R.I. (NED) 1-65 
Point Lookout, Mich. (NCE) 31-56 
Point Place, Toledo, Ohio (NCE) 31-26, 31-42, 31-51 
Point Pleasant, W. Va. (ORH) 5-25, 25-30, 25-31 
Pointe Lookout Harbor, Mich. (NCE) 31-55 
Pokegama Reservoir, Minn. (NCS) 27-29 
Polecat Creek Channel Improvement, Okla. (SWT) 19-37 
Pollock Rip Shoals, Mass. (NED) 1-67 
Poison Bay, Flathead Lake, Mont. (NPS) 38-27 
Pomeroy, Ohio (ORH) 25-25, 25-31 
Pomme DeTerre Lake, Mo. (MRK) 20-13, 20-24, 20-31 
Pomona Lake, One Hundred Ten Mile Creek, Kans. (MRK) 
20-14, 20-24, 20-31 
Ponce, P.R. (SAJ) 9-36 
Ponce DeLeon Inlet, Fla. (SAJ) 9-12, 9-26, 9-32 
Ponce Harbor, P.R. (SAJ) 9-12, 9-27, 9-32 
Pontiac Diversion, R. I. (NED) 1-78 
Port Alexander, Alaska (NPA) 40-15 
Port Allen Harbor, Kauai, Hawaii (POD) 36-13 
Port Allen Lock, La. (LMN) 11-13, 11-52 
Port Angeles Harbor, Wash. (NPS) 38-26, 38-27 
Port Arthur and Vicinity, Tex. (Hurricane-Flood Protection) 
(SWG) 15-14, 15-16, 15-19, 15-30 
Port Austin Harbor, Mich. (NCE) 31-16, 31-39, 31-48 
Port Bay, N.Y. (NCB) 32-42 
Port Clinton Harbor, Ohio (NCE) 31-16, 31-40, 31-48 
Port Everglades Harbor, Fla. (SAJ) 9-40, 9-41 
I-28

INDEX 
Port Gamble Harbor, Wash. (NPS) 38-26, 38-27 
Port Henry Harbor, N.Y. (NAN) 2-45 
Port Hueneme, Calif. (SPL) 33-4, 33-21 33-25 
Port Isabel, Tex. (SWG) 15-6, 15-39 
Port Jefferson Harbor, N.Y. (NAN) 2-45 
Port Ontario Harbor, N.Y. (NCB) 32-42 
Port Orchard Bay, Wash. (NPS) 38-26, 38-27 
Port Orford, Oreg. (NPP) 37-9, 37-33, 37-40 
Port Royal Harbor, S. C. (SAN) 7-5, 7-11, 7-14 
Port St. Fla. (SAM) 10-39, 10-40 
Port San Luis, Calif. (SPL) 33-5, 33-21, 33-25 
Port Sanilac Harbor, Mich. (NCE) 31-16, 31-40, 31-48 
Port Townsend, Wash. (NPS) 38-26, 38-27 
Port Townsend and Oak Bay, Waterway Connecting, Wash. 
(NPS) 38-7, 38-17, 38-22 
Port Washington Harbor, Wis. (NCC) 30-14, 30-24, 30-31, 
30-35 
Port Wing Harbor, Wis. (NCS) 27-8, 27-24, 27-28 
Portage Lake Harbor, Mich. (NCE) 31-16, 31-39, 31-48 
Portage, Pa. (ORP) 26-30, 26-31 
Portchester Harbor, N.Y. (NAN) 2-45 
Portland, Colo. (SWA) 17-4, 17-17 
Portland, Ind. (ORL) 24-39, 24-43 
Portland, Ohio (ORH) 25-25, 25-31 
Portland Harbor, Maine (NED) 1-65, 1-67 
Portneuf River and Marsh Creek, Idaho (NPW) 39-16, 39-18 
Portsmouth Harbor, N.H. (NED) 1-65 
Portsmouth Harbor, Va., Channel to Nansemond Ordnance 
Depot (NAO) 5-27 
Portsmouth Harbor and Piscataqua River, Maine and N.H. 
(NED) 1-67 
Portsmouth-New Boston, Ohio (ORH) 25-25, 25-30, 25-31 
Portsmouth State Park Marina, Ohio (ORH) 25-2, 25-20 
Portugues and Bucana Rivers, P.R. (SAJ) 9-23, 9-28, 9-36 
Portville, N.Y. (ORP) 26-28, 26-30, 26-31 
Posten Bayou, Ark., and La. (LMN) 11-55, 11-57 
Poteet Channel Improvement, Tex. (SWF) 16-26 
Potomac and Anacostia Rivers, D.C., Collection and Removal 
of Drift (NAB) 4-7, 4-26, 4-33 
Potomac Estuary Pilot Water Treatment Plant, Md., D.C. and 
Va. (NAB) 4-23, 4-30, 4-35 
Potomac River and Tributaries at and below Washington, 
D.C. Elimination of Waterchestnut (NAB) 4-8, 4-26, 4-33 
Potomac River at Alexandria, Va. (NAB) 4-38 
Potomac River at Lower Cedar Point, Md. (NAB) 4-38 
Potomac River at Mount Vernon, Va. (NAB) 4-38 
Potomac River below Washington, D.C. (NAB) 4-36, 4-38 
Potomac River North Side of Washington Channel, D.C. 
(NAB) 4-38 
Potowomut River, R.I. (NED) 1-67 
Powhatan Point, Ohio (ORH) (ORP) 26-28, 26-31 
Prado Dam, Calif. (SPL) 33-17, 33-36 
Prairie Du Chien, Wis. (NCS) 27-16, 27-25 
Prairie DuPont Levee and Sanitary District, Ill. (LMS) 14-19 
Prairie DuRocher and Vicinity, Ill. (LMS) 14-19 
Prairie Du Chien Harbor, Wis. (NCD) 29-3, 29-8 
Prairie Portage Board of Control, International 48-16 
Prattville, Autauga Creek, Ala. (SAM) 10-41 
Preauthorization Studies for Beach Erosion Control Activities 
Baltimore, Md., District (NAB) 4-11 
Buffalo, N.Y., District (NCB) 32-20 
Charleston, S.C., District (SAN) 7-7 
Jacksonville, Fla., District (SAJ) 9-43 
Los Angeles, Calif., District (SPL) 33-32 
New England Division (NED) 1-70 
New York, N.Y., District (NAN) 2-19 
Norfolk, Va., District (NAO) 5-16 
Pacific Ocean Division (POD) 36-7 
Philadelphia, Pa., District (NAP) 3-27 
San Francisco, Calif., District (SPN) 34-11 
Seattle, Wash., District (NPS) 38-9 
St. Paul, Minn., District (NCS) 27-32 
Preauthorization Studies for Flood Control Activities 
Albuquerque, N. Mex., District (SWA) 17-15 
Baltimore, Md., District (NAB) 4-23 
Buffalo, N.Y., District (NCB) 32-25 
Charleston, S.C., District (SAN) 7-17 
Fort Worth, Tex., District (SWF) 16-17 
Huntington, W. Va., District (ORH) 25-33 
Jacksonville, Fla., District (SAJ) 9-51 
Los Angeles, Calif., District (SPL) 33-39 
Louisville, Ky., District (ORL) 24-41 
Memphis, Tenn., District (LMM) 13-5 
Mobile, Ala., District (SAM) 10-42 
New England Division (NED) 1-77 
New York, N.Y., District (NAN) 2-30 
Norfolk, Va., District (NAO) 5-18 
Omaha, Nebr., District (MRO) 21-33 
Pacific Ocean Division (POD) 36-8 
Philadelphia, Pa., District (NAP) 3-28 
Pittsburgh, Pa., District (ORP) 26-33 
Portland, Oreg., District (NPP) 37-56 
Rock Island, Ill., District (NCR) 28-14 
Sacramento, Calif., District (SPK) 35-22 
San Francisco, Calif., District (SPN) 34-14 
Savannah, Ga., District (SAS) 8-8 
Seattle, Wash., District (NPS) 38-12 
St. Louis, Mo., District (LMS) 14-11 
St. Paul, Minn., District (NCS) 27-35 
Tulsa, Okla., District (SWT) 19-39 
Vicksburg, Miss., District (LMK) 12-6 
Walla Walla, Wash., District (NPW) 39-19 
Wilmington, N.C., District (SAW) 6-33 
Preauthorization Studies for Navigation Activities 
Alaska District (NPA) 40-7 
Baltimore, Md., District (NAB) 4-11 
Buffalo, N.Y., District (NCB) 32-18 
Charleston, S.C., District (SAN) 7-6 
Chicago, Ill., District (NCC) 30-17 
Detroit, Mich., District (NCE) 31-25 
Galveston, Tex., District (SWG) 15-11 
Jacksonville, Fla., District (SAJ) 9-43 
Louisville, Ky., District (ORL) 24-3 
Memphis, Tenn., District (LMM) 13-3 
Mobile, Ala., District (SAM) 10-14 
New England District (NED) 1-68 
New Orleans, La., District (LMN) 11-26 
New York, N.Y., District (NAN) 2-17 
Norfolk, Va., District (NAO) 5-15 
Pacific Ocean Division (POD) 36-5 
Philadelphia, Pa., District (NAP) 3-14 
Portland, Oreg., District (NPP) 37-48 
Rock Island, Ill., District (NCR) 28-2 
San Francisco, Calif., District (SPN) 34-21 
Savannah, Ga., District (SAS) 8-6 
Seattle, Wash., District (NPS) 38-8 
St. Paul, Minn., District (NCS) 27-32 
Tulsa, Okla., District (SWT) 19-5 
Vicksburg, Miss., District (LMK) 12-3 
Wilmington, N.C., District (SAW) 6-30 
Prescott Area, Oreg. (NPP) 37-53 
Presque Isle Harbor, Mich. (NCS) 27-8, 27-24, 27-28 
Presque Isle Peninsula, Erie, Pa. (NCB) 32-19, 32-28, 32-40 
Preston Drainage and Levee District, Ill. (LMS) 14-19 
I-29

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Prestonsburg, Ky. (ORH) 25-30 
Prestonville, Ky. (ORL) 24-34, 24-39 
Prevention of Obstructions and Injurious Deposits 
Baltimore, Md., District (NAB) 4-5, 4-26, 4-32 
Norfolk, Va., District (NAO) 5-14, 5-20 
Priest, J. Percy, Dam and Reservoir, Tenn. (ORN) 23-7, 23- 
10, 23-18 
Priest Rapids Dam, Wash. (NPS) 38-29 
Princeton, W. Va. (ORH) 25-30, 25-31 
Prineville, Oreg. (NPP) 37-55 
Princeville Dike, N. C. (SAW) 6-20 
Proctor, Vt. (NAN) 2-47 
Proctor, W. Va. (ORP) 26-28, 26-31 
Proctor Lake, Tex. (SWF) 16-13, 16-20, 16-24 
Proctorville, Ohio (ORH) 25-25, 25-31 
Prompton Lake, Pa. (NAP) 3-16, 3-21 
Prospect Beach, West Haven, Conn. (NED) 1-20, 1-69 
Prosperity Lake, Mo. (SWT) 19-17, 19-31 
Providence, R.I. (NED) 1-44 
Providence River and Harbor, R.I. (NED) 1-15, 1-48, 1-60 
Provincetown Beach, Provincetown, Mass. (NED) 1-69 
Provincetown Harbor, Mass. (NED) 1-67 
Pudding River, Oreg. (NPP) 37-54 
Pueblo, Arkansas River, Colo. (SWA) 17-20 
Pueblo (Dry Creek), Colo. (SWA) 17-4, 17-17 
Puget Sound and Its Tributary Waters, Wash. (NPS) 38-5, 38- 
16, 38-21, 38-25 
Pullman, Wash. (NPW) 39-4, 39-12, 39-15 
Pultneyville Harbor, N.Y. (NCB) 32-42 
Pungo Creek, N. C. (SAW) 6-20, 6-32 
Pungo River, N. C. (SAW) 6-20, 6-32 
Punxsutawney, Pa. (ORP) 26-11, 26-20, 26-28 
Put-In-Bay, Ohio (NCE) 31-55, 31-56 
Puyallup River, Wash. (NPS) 38-11 
Q 
Quail Wash Levee, Joshua Tree, Calif. (SPL) 33-38 
Queens Creek, Va. (NAO) 5-26, 5-27 
Queenstown Harbor, Md. (NAB) 4-38 
Quillayute River, Wash. (NPS) 38-5, 38-16, 38-21 
Quinby Creek, Va. (NAO) 5-27 
Quincy Harbor, Ill. (NCD) 29-2, 29-9 
Quincy, Ill., Harbor Access Channel (NCR) 28-9 
Quincy Shore Beach, Quincy, Mass. (NED) 1-20, 1-69 
R 
R. D. Bailey Lake, W. Va. (ORH) 25-15, 25-22 
R. N. Bert Dosh Lock, Fla. (SAJ) 9-37 
Raccoon Creek, N.J. (NAP) 3-26 
Raccoon Creek Levee, Ind. (ORL) 24-34, 24-39 
Racine, Ohio (ORH) 25-25, 25-31 
Racine, Wis. (NCC) 30-41 
Racine Harbor, Wis. (NCC) 30-15, 30-24, 30-31, 30-35 
Racine Locks and Dam, Ohio (ORD) 22-1, 22-2, 22-3, 22-8 
Rahway, N.J. (NAN) 2-47 
Rahway River, N.J. (NAN) 2-45 
Rahway, South Branch, N.J. (NAN) 2-24, 2-34, 2-40 
Rainey, Henry T., Dam, Ill. (NCD) 29-3, 29-7 
Rainier Drainage District, Oreg. (NPP) 37-50, 37-53, 37-54 
Rainy Lake Board of Control, International 48-16 
Rancocas River, N.J. (NAP) 3-26 
Randleman Lake, N. C. (SAW) 6-15, 6-25, 6-31 
Randolph Reservoir, Va. (SAW) 6-31 
Rapid City, Cedar Canyon Dam, S. Dak. (MRO) 21-20 
Rapide Croche Lock and Dam, Wis. (NCC) 30-36 
Rappahannock River at Bowlers Wharf, Va. (NAO) 5-27 
Rappahannock River, Va. (NAO) 5-26, 5-27 
Rappahannock Shoal Channel, Va. (NAO) 5-4, 5-22 
Raritan Bay and Sandy Hook Bay, N.J. (NAN) 2-25, 2-34, 2- 
40 
Raritan River, N.J. (NAN) 2-14, 2-33, 2-39, 2-44 
Raritan River to Arthur Kill Cutoff Channel, N.J. (NAN) 2-45 
Rathbun Lake, Iowa (MRK) 20-14, 20-24 
Rathbun Lake (Fish Hatchery), Iowa (MRK) 20-15, 20-24, 20- 
31 
Ravenswood, W. Va. (ORH) 25-25, 25-31 
Rayburn, Sam, Dam and Reservoir, Tex. (SWF) 16-17, 16-21, 
16-23 
Raymond, Wash. (NPS) 38-28 
Raystown Lake, Pa. (NAB) 4-14, 4-28, 4-35 
Red and Arkansas River Basins Chloride Control Study 
Okla., Tex., And Kans. (SWT) 19-5, 19-30, 19-33, 19-34 
Red Bluff, Calif. (SPK) 35-30 
Red Brook Harbor, Bourne, Mass. (NED) 1-67 
Red Creek, N.Y. (NCB) 32-22, 32-29 
Red Dale Gulch, Rapid City, S. Dak. (MRO) 21-23 
Red Lake and Red Lake River, Minn. (NCS) 27-31 
Red Lake River, Minn., Including Clearwater River, Minn. 
(NCS) 27-16, 27-26, 27-33 
Red Oak, Iowa (MRO) 21-21 
Red River at East Grand Forks, Minn. (NCS) 27-32 
Red River at Fargo, N. Dak. (NCS) 27-32 
Red River at Grand Forks, N. Dak. (NCS) 27-32 
Red River below Denison Dam, Levees and Bank 
Stabilization, Tex., Ark., and La. (LMN) 11-34, 11-40, 
11-49, 11-55 
Red River below Denison Dam (LMN) (SWT) 11-34, 11-55, 
l1-56, 19-18, 19-31, 19-36, 19-38 
Red River below Fulton, Ark. (LMN) 11-20, 11-39, 11-46 
Red River Backwater Area (MR&T) 42-1, 42-8, 42-9, 42-17, 
42-57, 42-58 
Red River Basin (MR&T) 42-1 
Red River Basin, Tex. Experimental Chloride Control Project 
(SWT) 19-6, 19-25 
Red River, Dikes (MR&T) 42-34 
Red River Emergency Bank Protection (LMN) 11-21, 11-39, 
11-46 
Red River in Vicinity of Shreveport, La. (LMN) 11-56, 11-57 
Red River from Fulton, Ark. to Mouth of Washita River. 
(SWT) 19-5 
Red River Lake, Ky. (ORL) 24-19, 24-26 
Red River Levees (MR&T) 42-50 
Red River of the North Drainage Basin, Minn., S. Dak., and 
N. Dak. (NCS) 27-17, 27-26, 27-32 
Red River of the North, Minn. and N. Dak. (NCS) 27-31 
Red River of the North, Oslo, Minn. (NCS) 27-17, 27-26 
Red River of the North, Pembina, N. Dak. (NCS) 27-18, 27- 
26 
Red River Parish, La. (LMN) 11-56, 11-57 
Red River, Standard Revetments (MR&T) 42-34 
Red River, Tenn. (ORN) 23-17 
Red River Waterway-Mississippi River to Shreveport, La. 
(LMN) 11-21, 11-39, 11-46 
Red River Waterway, La., Ark., Okla., and Tex. (LMN) 11- 
35, 11-53 
Red River Waterway Shreveport, La., to Daingerfield, Tex. 
(LMN) 11-23, 11-39, 11-47 
I-30

INDEX 
Red Rock Dam and Lake Red Rock, Iowa (NCR) 28-5, 28-8, 
28-11 
Red Run, Mich. (NCE) 31-27, 31-30, 31-42, 31-51 
Red Wing Harbor, Minn. (NCD) 29-3, 29-8 
Redbank Creek Lake, Pa. (ORP) 26-29, 26-32 
Reddies River Lake, N. C. (SAN) 7-8, 7-12, 7-15, 7-16 
Redmond, John, Dam and Reservoir, Kans. (SWT) 19-14, 19- 
27, 19-35 
Redmond, John, Wildlife Refuge, Kans. (SWT) 19-38 
Redondo Beach Harbor (King Harbor), Calif. (SPL) 33-30 
Redwood City Harbor, Calif. (SPN) 34-6, 34-15, 34-19 
Redwood Creek, Calif. (SPN) 34-23 
Redwood River, Marshall, Minn. (NCS) 27-33, 27-34 
Reeds Bay Small Boat Harbor, Hawaii (POD) 36-13 
Reedsport Levees, Oreg. (NPP) 37-55 
Reedy River, S. C. (SAN) 7-17 
Reelfoot Lake-lake No. 9, Ky. and Tenn. (MR&T) 42-2, 42- 
11, 42-21, 42-29, 42-54, 42-55, 42-57, 42-58 
Reese River, Battle Mountain, Nev. (SPK) 35-22, 35-34 
Reevesville, Ill. (ORL) 24-34, 24-39, 24-42 
Regulation of Hydraulic Mining and Preparation of Plans 
(CDC) 44-1, 44-5, 44-6 
Rehoboth Beach to Indian River Inlet, Del. (NAP) 3-27 
Removing Snags and Wrecks from Mississippi River below 
Mouth of Missouri River and from Old and Atchafalaya 
Rivers (LMK) (LMM) 12-11, 13-9 
Removing Water Hyacinth (SAM) (LMN) 10-13, 10,28, 10-36, 
11-24, 11-39, 11-47 
Rend Lake, Ill. (LMS) 14-10, 14-14, 14-16 
Reno Beach-Howard Farms, Ohio (NCE) 31-30, 31-57 
Republican River, Nebr. and Kans. (MRK) 20-32 
Restoration of Indian Fishing Grounds, Bonneville, Oreg. 
Revere Beach, Mass. (NED) 1-20, 1-49, 1-61 
Reynoldsville, Pa. (ORP) 26-30, 26-32 
Rheem Creek, Calif. (SPN) 34-23 
Rhodes Point to Tylerton, Md. (NAB) 4-38 
Rice Creek, Fla. (SAJ) 9-41 
Richard B. Russell Dam and Lake, Ga. and S. C. Trotters 
Shoals Lake (SAS) 8-9, 8-12, 8-15 
Richland Creek, Ill. (LMS) 14-19 
Richland Hills Local Flood Protection, Tex. (SWF) 16-26 
Richland Lake, Mo. (MRK) 20-31, 20-33 
Richmond Harbor, Calif. (SPN) 34-6, 34-16, 34-16, 34-19 
Richmond Harbor, Maine (NED) 1-67 
Richmond's Island Harbor, Maine (NED) 1-67 
Richwood, Fenwick, W. Va. (ORH) 25-30 
Ridgecrest, Calif. (SPL) 33-38 
Ridgway and Vicinity, Pa. (ORP) 26-12, 26-20, 26-28, 26-30, 
26-32 
Rio Grande Basin, N. Mex. (SWA) 17-10, 17-16, 17-18, 17-19 
Rio Grande Floodway, N. Mex. (SWA) 17-12, 17-17, 17-19, 
17-20 
Rio Hondo Basin, Calif. (SPL) 33-13, 33-32, 33-34 
Ripley, Ohio (ORH) 25-25, 25-29, 25-31 
Rising Sun, Ind. (ORL) 24-34, 24-39 
River Rouge, Mich. (NCE) 31-28, 31-42, 31-51 
Riverdale, Mass. (NED) 1-72, 1-76 
Riverside Levees, Calif. (SPL) 33-37, 33-38 
Riverview, W. Va. (ORH) 25-25, 25-31 
Roanoke Rapids Reservoir, N. C. (SAW) 6-31 
Roanoke River Basin, Va. and N. C. (SAW) 6-20, 6-26, 6-31 
Roanoke River, N. C. (SAW) 6-29 
Roaring River, N. C. (SAN) 7-9, 7-12, 7-15, 7-16 
Roaring River Lake, N. C. (SAN) 7-16 
Robert S. Kerr Lock and Dam and Reservoir, Okla. (SWL) 
(SWT) 18-2, 18-17, 19-23, 19-28, 19-32, 19-36 
Robert S. Kerr Marine Terminal, Okla. (SWL) (SWT) 18-2, 
19-5, 19-32 
Rochester, Minn. (NCS) 27-18, 27-26 
Rochester and McCleary's Bluff Levee, Ill. (ORL) 24-34, 24- 
39, 24-42 
Rochester Harbor, N.Y. (NCB) 32-16, 32-28, 32-39 
Rochester Lake, Iowa (NCR) 28-13 
Rochester, Pa. (ORP) 26-28, 26-32 
Rock Hall Harbor, Md. (NAB) 4-38 
Rock Island Harbor, Ill. (NCD) 29-2, 29-8 
Rock Island, Ill. (NCR) 28-6, 28-9, 28-11 
Rock River Agricultural Levees, Ill. (NCR) 28-13 
Rock River, Ill., and Wis., at South Beloit, Ill. (NCR) 28-13 
Rockfish Creek, N. C. (SAW) 6-19, 6-25 
Rockford, Ill. (NCR) 28-5, 28-8, 28-11 
Rockland Harbor, Maine (NED) 1-67 
Rockland Lake, Tex. (SWF) 16-22, 16-23 
Rockport Harbor, Maine (NED) 1-67 
Rockport Harbor, Mass. (NED) 1-67 
Rockport, Ind. (ORL) 24-34, 24-39 
Rocky Ford Drainage and Levee District, Ill. (NCC) 30-42 
Rocky Fork Reservoir, Ohio (ORH) 25-27, 25-29, 25-32 
Rocky Pass, Alaska (NPA) 40-15 
Rocky River Harbor, Ohio (NCB) 32-16, 32-28, 32-39 
Rodeo Creek, Calif. (SPN) 34-23 
Rogers City, Mich. (NCE) 31-56 
Rogue River Harbor at Gold Beach, Oreg. (NPP) 37-9, 37-33, 
37-40 
Roland Drainage District, Ark. (SWL) 18-24 
Rollinson Channel, N. C. (SAW) 6-9, 6-24 
Rome, Ind. (ORL) 24-34, 24-39 
Rome, Ga. (SAM) 10-17, 10-41 
Rome, N.Y. (NAN) 2-47 
Rondout Harbor, N.Y. (NAN) 2-45 
Rose Creek Channel Improvements, San Diego, Calif. (SPL) 
33-38 
Roseau River, Minn. (NCS) 27-18, 27-26 
Roseau River Engineering Board, International 48-19 
Rosendale, N.Y. (NAN) 2-24, 2-34, 2-40 
Roseville, Ohio (ORH) 25-15, 25-22, 25-25, 25-30 
Rosiclare, Ill. (ORL) 24-39, 24-42 
Rossview Reservoir, Tenn. and Ky. (ORN) 23-18 
Rouge River, Mich. (NCE) 31-17, 31-40, 31-48 
Rough River Lake and Channel Improvement, Ky. (ORL) 24- 
20, 24-27, 24-36 
Rough River, Ky. (ORL) 24-34, 24-44 
Rouses Point, N.Y. (NAN) 2-45 
Rouseville, Pa. (ORP) 26-32 
Rowlesburg Lake, W. Va. (ORP) 26-12, 26-20 
Royal River, Maine (NED) 1-65, 1-67 
Ruby River, Mont. (MRO) 21-20 
Rufus Woods Lake-Chief Joseph Dam, Wash. (NPS) 38-12, 
38-18, 38-23 
Running Reelfoot Bayou, Tenn. (MR&T) 42-54 
Running Water Draw, Plainview, Tex. (SWF) 16-22 
Rush Bayou, Ark. (MR&T) 42-53 
Rush River, N. Dak. (NCS) 27-32, 27-33 
Rush River (Lower Branch), N. Dak. (NCS) 27-33 
Rushford, Minn. (NCS) 27-19, 27-26, 27-33 
Russell, Ky. (ORH) 25-25, 25-30, 25-31 
Russell, Richard B., Dam and Lake, Ga. and S. C. Trotters 
Shoals Lake (SAS) 8-9, 8-12, 8-15 
Russell and Allison Levee, Ill. (ORL) 24-34, 24-40 
Russell Creek, S. C. (SAN) 7-16 
Russian River Basin, Calif. (SPN) 34-13, 34-17, 34-20, 34-22 
1-31

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Rutland, Vt. (NAN) 2-47 
Rutledge Hollow Creek Channel Improvement, Poteet, Tex. 
(SWF) 16-14, 16-20 
Rye Harbor, N.H. (NED) 1-65, 1-67 
S 
Sabin Lock, Mich. (NCE) 31-54 
Sabine-Neches Waterway, Tex. (SWG) 15-8, 15-18, 15-27, 15- 
33, 15-36, 15-41 
Sabine River Basin, Tex. (SWF) 16-14 
Sabine River and Tributaries, Tex. (SWG) (SWF) 16-25 
Sabine River and Tributaries, Tex. (Echo to Morgan Bluff) 
(SWG) 15-32 
Sabula, Iowa (NCR) 28-11, 28-13 
Sackets Harbor, N.Y. (NCB) 32-42 
Saco, Beaver Creek, Mont. (MRO) 21-20 
Saco, Mont. (MRO) 21-23 
Saco River, Maine (NED) 1-65, 1-67 
Sacramento, Calif. (SPK) 35-32 
Sacramento River, Calif. (SPK) (CDC) 35-2, 35-25, 35-29, 35- 
30, 44-3, 44-5, 44-6, 44-7, 44-8 
Sacramento River and Tributaries from Collinsville to Shasta 
Dam, Calif. (SPK) 35-19, 35-22, 35-26, 35-27, 35-32, 35- 
33 
Sacramento River and Tributaries (Debris Control), Calif. 
(SPK) (CDC) 44-2, 44-5 
Sacred Heart Hospital, Emergency Bank Stabilization, 
Yankton, S. Dak. (MRO) 20-9, 21-15 
Sag Harbor, N.Y. (NAN) 2-44, 2-45 
Saginaw River, Mich. (NCE) 31-18, 31-29, 31-40, 31-42, 31- 
48, 31-51 
Sakonnet Harbor, R.I. (NED) 1-67 
Sakonnet River, R.I. (NED) 1-67 
Salamanca, N.Y. (ORP) 26-30, 26-32 
Salamonie Lake, Ind. (ORL) 24-20, 24-27 
Salem Church Lake, Va. (NAO) 5-18, 5-21, 5-24 
Salem Harbor, Mass. (NED) 1-67 
Salem River, N.J. (NAP) 3-26 
Salina, Kans. (MRK) 20-31, 20-32, 20-33 
Salinas River, Calif. (SPN) 34-23 
Saline Point, La. (LMN) 11-56, 11-57 
Saline River and Tributaries, Ill. (ORL) 24-20, 24-27 
Saline River, Ark. (LMK) 12-11 
Salkahatchie River, S. C. (SAN) 7-16 
Salmon Creek at Oakridge, Oreg. (NPP) 37-56 
Salmon River, Alaska (NPA) 40-16 
Salmon River, Oreg. (NPP) 37-47 
Salt Creek, Barnard, Kans. (MRK) 20-32, 20-33 
Salt Creek, Ill. (NCC) 30-42 
Salt Creek Lake, Ohio (ORH) 25-16, 25-22 
Salt Creek and Tributaries, Nebr. (MRO) 21-9, 21-15 
Salt Creek in Vicinity of Middletown, Ill. (NCC) 30-42 
Salt Lake City, Utah (SPK) 35-34 
Salyersville, Ky. (ORL) 24-40 
Sam Rayburn Dam and Reservoir, Tex. (SWF) 16-17, 16-21, 
16-23 
Sammamish River, Wash. (NPS) 38-27, 38-28 
San Antonio and Chino Creeks Channel, Calif. (SPL) 33-17, 
33-36 
San Antonio Channel Improvement, Tex. (SWF) 16-14, 16. 
21, 16-25 
San Antonio Dam, Calif. (SPL) 33-17, 33-36 
SanBernard River Channel, Tex. (SWG) 15-38 
SanDiego Creek, Alice, Tex. (SWG) 15-16, 15-32 
San Diego Harbor, Calif. (SPL) 33-5, 33-21, 33-26 
San Diego River Channel and Levees, Calif. (SPL) 33-37 
San Diego River and Mission Bay, Calif. (SPL) 33-30 
San Diego River (Mission Valley), Calif. (SPL) 33-16, 33-23, 
33-28 
San Diego (Sunset Cliffs), Calif. (SPL) 33-31 
San Francisco Bay and Delta Model, Calif. (SPN) 34-7, 34-16 
San Francisco Bay to Stockton, Calif. (John F. Baldwin and 
Stockton Ship Channels) (SPN) (SPK) 34-7, 34-16, 35-2, 
35-25 
San Francisco Harbor, Calif. (SPN) 34-8, 34-19 
San Francisco Harbor and Bay, Calif. (SPN) 34-8 
San Francisco Harbor and Bay Removal of Drift, Calif. (SPN) 
34-16 
San Francisco Marina (Gas House Cove), Calif. (SPN) 34-21 
San Gabriel River, Tex. (SWF) 16-14, 16-21 
San Gabriel River Basin, Calif. (SPL) 33-13, 33-32, 33-34 
San Gabriel River to Newport Bay (Surfside-Sunset and 
Newport Beach), Calif. (SPL) 33-31 
San Jacinto River, Calif. (SPL) 33-37 
San Jacinto River Levee and Bautista Creek, Calif. (SPL) 33- 
37, 33-38 
San Joaquin River, Calif. (SPK) 35-3, 35-22, 35 25, 35-30, 35- 
31 
San Juan, P.R. (SAJ) 9-43 
San Juan Dam, Calif. (SPL) 33-36, 33-38 
San Juan Harbor, P. R. (SAJ) 9-14, 9-27, 9-33 
San Leandro Creek, Calif. (SPN) 34-23 
San Lorenzo Creek, Calif. (SPN) 34-23 
San Lorenzo River, Calif. (SPN) 34-23 
San Luis Rey River, Calif. (SPL) 33-38 
San Pablo Bay and Mare Island Strait, Calif. (SPN) 34-9, 34- 
16, 34-20 
San Rafael Creek, Calif. (SPN) 34-21 
Sand Creek Channel Improvement, Kans. (SWT) 19-37, 19- 
38 
Sand Hill Cove Beach, R.I. (NED) 1-20, 1-69 
Sand Hill River, Minn. (NCS) 27-32, 27-33 
Sand Lake, Okla. (SWT) 19-38 
Sandburg Creek, Spring Glen, N.Y. (NAN) 2-26, 2-34, 2-40 
Sandusky Harbor, Ohio (NCB) 32-16, 32-28, 32-39 
Sandusky River, Ohio (NCB) 32-42 
Sandy Bay (Harbor of Refuge), Mass. (NED) 1-67 
Sandy Drainage District, Oreg. (NPP) 37-50, 37-53, 37-54 
Sandy Hook Bay at Leonardo, N.J. (NAN) 2-44, 2-45 
Sandy Hook Bay, N.J. (NAN) 2-44, 2-45 
Sandy Lake, Minn. (NCS) 27-29 
Sangamon River, Ill. (NCC) 30-19, 30-25, 30-41, 30-42 
Sanitary District of Beardstown, Ill. (NCC) 30-41 
Santa Ana River Basin (and Orange County), Calif. (SPL) 33- 
17, 33-23, 33-28, 33-36, 33-38 
Santa Ana River Basin, Calif. (SPL) 33-38 
Santa Barbara Harbor, Calif. (SPL) 33-7, 33-21, 33-26 
Santa Clara River, Calif. (SPL) 33-37, 33-38 
Santa Clara River Levee Improvement, Calif. (SPL) 33-37, 33- 
38 
Santa Cruz Harbor, Calif. (SPN) 34-9, 34-16 
Santa Maria Valley Levees, Calif. (SPL) 33-37, 33-38 
Santa Paula Creek Channel and Debris Basins (Including 
Mud Creek), Calif. (SPL) 33-17, 33-23 
Santa Rosa Wash (Tat Momolikot Dam and Lake St. Clair), 
Ariz. (SPL) 33-11, 33-22, 33-27, 33-29 
Santee River, N. C. and S. C. (SAN) 7-16 
Santiam River, Oreg. (NPP) 37-52 
Sapelo Harbor, Ga. (SAS) 8-16 
Sardis, Ohio (ORH) 25-26, 25-31 
Sardis Lake, Miss. (MR&T) 42-9, 42-19, 42-22, 42-57, 42-59 
1-32

INDEX 
Sasanoa River, Maine (NED) 1-67 
Sasco Hill Beach, Fairfield, Conn. (NED) 1-20, 1-69 
Satilla River, Ga. (SAS) 8-15, 8-16 
Saugatuck Harbor and Kalamazoo River, Mich. (NCE) 31-22, 
31-41, 31-50 
Saugerties Harbor, N.Y. (NAN) 2-45 
Sauvie Island Areas A and B, Oreg. (NPP) 37-53 
Sauvie Island Drainage District, Oreg. (NPP) 37-50, 37-55 
Savage River Dam, Md. (NAB) 4-44 
Savannah Harbor, Ga. (SAS) 8-4, 8-11, 8-13 
Savannah River Above Augusta, Ga. (SAS) 8-16 
Savannah River at Augusta, Ga. (SAS) 8-16 
Savannah River Basin, Ga. and S. C. (SAS) 8-8, 8-16 
Savannah River below Augusta, Ga. (SAS) 8-6, 8-11, 8-14 
Sawmill Branch, S. C. (SAN) 7-17 
Saxon Harbor, Wis. (NCS) 27-10, 27-24 
Saxonville, Mass. (NED) 1-37, 1-53, 1-63, 1-74 
Sayers, Foster Joseph, Dam, Pa. (NAB) 4-22, 4-29, 4-43 
Saylorville Lake, Iowa (NCR) 28-6, 28-9, 28-11 
Scajaquada Creek, N.Y. (NCB) 32-23, 32-29 
Scappoose Drainage District, Oreg. (NPP) 37-21, 37-35, 37- 
43, 37-50, 37-53 
Scarboro River, Maine (NED) 1-16, 1-49, 1-60 
Schuyler, Platte River, Nebr. (MRO) 21-21 
Schuyler, Lost Creek and Platte River, Nebr. (MRO) 21-21 
Schuylkill River Above Fairmount Dam, Pa. (NAP) 3-26 
Schuylkill River, Pa. (NAP) 3-13, 3-21, 3-24 
Scioto River at Portsmouth, Ohio (ORH) 25-24 
Scioto River, Ohio (ORH) 25-27 
Sciotoville, Ohio (ORH) 25-26, 25-31 
Scituate, Mass. (NED) 1-44 
Scituate Harbor, Mass. (NED) 1-67 
Schoolfield, Va. and N. C. (SAW) 6-31 
Scott County Drainage and Levee District, Ill. (LMS) 14-19 
Scott, W. Kerr, Dam and Reservoir (Wilkesboro Reservoir), 
N. C. (SAN) 7-7, 7-12, 7-15, 7-16 
Scranton, Pa. (NAB) 4-39, 4-40, 4-44 
Scranton, Buffalo Creek, N. Dak. (MRO) 21-20 
Scuppernong River, N. C. (SAW) 6-19, 6-26, 6-29 
Sea Horn Drainage and Levee District, Ill. (NCC) 30-41, 30- 
42 
Searsport Harbor, Maine (NED) 1-65, 1-67 
Seaside Park, Conn. (NED) 1-20, 1-69 
Seattle Harbor, Wash. (NPS) 38-6, 38-17, 38-21 
Sebewaing River, Mich. (NCE) 31-22, 31-41, 31-42, 31-50 
Sebewaing, Mich. (NCE) 31-30, 31-42, 31-51 
Seekonk River, R.I. (NED) 1-65, 1-67 
Seldovia Harbor, Alaska (NPA) 40-15 
Selkirk Shores State Park, N.Y. (NCB) 32-43 
Sergius Whitestone, Alaska (NPA) 40-15 
Sevier River, Redmond and Vicinity, Utah (SPK) 35-22, 35-34 
Seward, Nebr. (MRK) 20-32 
Seward Harbor, Alaska (NPA) 40-15 
Shad Landing State Park, Md. (NAB) 4-38 
Shallotte River, N. C. (SAW) 6-9, 6-24, 6-28 
Shark River, N.J. (NAN) 2-46 
Shawneetown, Ill. (ORL) 24-34, 24-40, 24-42 
Sheboygan Harbor, Wis. (NCC) 30-15, 30-24, 30-31, 30-35 
Sheepshead Bay, N.Y. (NAN) 2-44, 2-46 
Sheffield Lake Community Park, Ohio (NCB) 32-43 
Shell Creek, Nebr. (MRO) 21-23 
Shelley Area, Snake River, Idaho (NPW) 39-16, 39-18 
Shelton Ditch, Willamette River, Oreg. (NPP) 37-55 
Shenango River Lake, Pa. and Ohio (ORP) 26-13, 26-20, 26- 
29 
Sheridan, Wyo. (MRO) 21-9, 21-15, 21-20 
Sherwood Island State Park, Conn. (NED) 1-20, 1-69 
Sheyenne River, N. Dak. (NCS) 27-32, 27-33 
Shidler Lake, Okla. (SWT) 19-18, 19-27, 19-31 
Shields River, Near Clyde Park, Mont. (MRO) 21-23 
Shields River, Grannis Bridge, Near Livingston, Mont. (MRO) 
21-20 
Shields River, Chadborne Bridge, Near Livingston, Mont. 
(MRO) 21-20 
Shilshole Bay, Seattle, Wash. (NPS) 38-26, 38-27 
Shinnecock Inlet, N.Y. (NAN) 2-46 
Shipyard River, S. C. (SAN) 7-5, 7-11, 7-14 
Shoal Creek, Proctorville, Mo. (MRK) 20-32 
Shoal Harbor and Compton Creek, N.J. (NAN) 2-44, 2-46 
Shoals, East Fork of White River, Ind. (ORL) 24-40 
Shore of Manitowac County, Wis. (NCC) 30-41 
Short Beach, Conn. (NED) 1-20, 1-69 
Shoshone River, Lovell, Wyo. (MRO) 21-20, 21-23 
Shot Pouch Creek, S. C. (SAN) 7-17 
Shrewsbury River, N.J. (NAN) 2-15, 2-33, 2-39 
Shufflebarger Levee, Ind. (ORL) 24-34, 24-40 
Sid Simpson Flood Control Project, Ill. (NCC) 30-42 
Silver Beach to Cedar Beach, Conn. (NED) 1-20, 1-69 
Silver Lake Harbor, N. C. (SAW) 6-10, 6-24, 6-27 
Simmons Bay, N. C. (SAN) 7-17 
Simpson, Sid, Flood Control Project, Ill. (NCC) 30-42 
Simpson Creek, S. C. (SAN) 7-17 
Sioux City, Floyd River, Iowa (MRO) 21-21 
Sioux City, Iowa, Small Navigation Project (MRO) 21-18 
Sioux Falls, S. Dak. (MRO) 21-20, 21-23 
Sioux Falls, Big Sioux River, S. Dak. (MRO) 21-20 
Sistersville, W. Va. (ORH) 25-26, 25-31 
Sitka Harbor, Alaska (NPA) 40-15 
Siuslaw River, Oreg. (NPP) 37-9, 37-33, 37-40 
Six Runs Creek, N. C. (SAW) 6-32 
Sixes Bridge Lake, and Pa. (NAB) 4-44 
Skaggs Ferry, Ark. (SWL) 18-24 
Skagit River, Wash. (NPS) 38-11, 38-27 
Skagit River, Wash. (Avon Bypass) (NPS) 38-28 
Skagit River, Wash. (Levee and Channel Improvements) 
(NPS) 38-28 
Skagit River Board of Control, International 48-21 
Skagway Harbor, Alaska (NPA) 40-15 
Skagway River, Alaska (NPA) 40-16 
Skamokawa Creek Area, Wash. (NPP) 37-53 
Skamokawa Creek, Wash. (NPP) 37-10, 37-33, 37-40 
Skamokawa (Steamboat Slough), Wash. (NPP) 37-47 
Skiatook Lake, Okla. (SWT) 19-18, 19-28, 19-31 
Skipanon Channel, Oreg. (NPP) 37-10, 37-33, 37-40 
Slaughter Creek, Md. (NAB) 4-8, 4-26, 4-33 
Slovan, Pa. (ORP) 26-32 
Smelt Brook, Weymouth-Braintree, Mass. (NED) 1-40, 1-53, 
1-64 
Smith Creek, Md. (NAB) 4-38 
Smith River, Oreg. (NPP) 37-46, 37-47 
Smith Mountain Reservoir, Va. (SAW) 6-31 
Smithfield, W. Va. (ORH) 25-30 
Smithland, Ky. (ORL) 24-34, 24-40 
Smithland Locks and Dam, Ky. (ORD) 22-1, 22-3, 22-9 
Smiths Creek, N. C. (SAW) 6-10, 6-24, 6-28, 6-29 
Smiths Ferry, Pa. (ORP) 26-28, 26-32 
Smithville Channel, Mo. (MRK) 20-33 
Smithville Lake, Mo. (MRK) 20-15, 20-24 
Smoky Hill River, Solomon, Kans., Bridge Protection (MRK) 
20-32 
Smoky Hill, Salina, and Solomon Rivers, Kans. (MRK) 20-32 
Smyrna River, Del. (NAP) 3-26 
Snagging and Clearing Activities 
Albuquerque, N. Mex., District (SWA) 17-15 
I-33

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Charleston, S.C., District (SAN) 7-6 
Huntington, W. Va., District (ORH) 25-33 
Jacksonville, Fla., District (SAJ) 9-41 
Kansas City, Mo., District (MRK) 20-18 
Louisville, Ky., District (ORL) 24-41 
Rock Island, Ill., District (NCR) 28-7 
Sacramento, Calif., District (SPK) 35-23 
St. Louis, Mo., District (LMS) 14-11 
St. Paul, Minn., District (NCS) 27-35 
Walla Walla, Wash., District (NPW) 39-6 
Snake River, Weiser, Idaho (NPW) 39-16 
Snake River Downstream from Johnson Bar Landing, Oreg., 
Wash., And Idaho (NPW) 39-11, 39-13, 39-15, 39-24 
Snake River Vicinity of Weiser, Idaho (NPW) 39-16 
Snettisham, Alaska (NPA) 40-8, 40-12, 40-14 
Snohomish River and Everett Harbor, Wash. (NPS) 38-3, 38- 
16, 38-20, 38-25 
Snohomish River, Wash. (NPS) 38-11 
Sny Basin, Ill. (NCR) 28-11, 28-13 
Sny Island Levee Drainage District, Ill. (NCR) 28-11, 28-13 
Soap Creek, Oreg. (NPP) 37-55 
Socorro Diversion Channel, Tributaries of Rio Grande, N. 
Mex. (SWA) 17-20 
Somerville Lake, Tex. (SWF) 16-15, 16-21, 16-24 
Sonoma Creek, Calif. (SPN) 34-23 
Souris-Red Rivers Engineering Board, International 48-18 
South Amsterdam, N.Y. (NAN) 2-47 
South Bank Arkansas River (Head Fourche Island to 
Pennington Bayou), Ark. (SWL) 18-24 
South Bank Arkansas River, Little Rock to Pine Bluff, Ark. 
Tucker Lake (SWL) 18-24 
South Beardstown and Valley Drainage and Levee District, 
Ill. (NCC) 30-42 
South Beardstown Drainage and Levee District, Ill. (NCC) 30- 
41, 30-42 
South Bristol Harbor, Maine (NED) 1-67 
South Coventry Lake, Conn. (NED) 1-75, 1-76 
South Deer Creek Levee, Okla. (SWT) 19-37 
South Creek, N. C. (SAW) 6-20, 6-32 
South Ellenville, N.Y. (NAN) 2-27, 2-34, 2-40 
South Fork, Clearwater River, Idaho (NPW) 39-16 
South Fork of Cumberland River, Ky. (ORN) 23-17 
South Fork Dam and Lake, Tex. (SWF) 16-24 
South Frankfort Area, Ky. (ORL) 24-33 
South Haven Harbor, Mich. (NCE) 31-22, 31-41, 31-50 
South Milwaukee Harbor, Wis. (NCC) 30-40 
South Orange, N.J. (NAN) 2-27, 2-35, 2-40 
South Platte River, Denver, Colo. (MRO) 21-21 
South Platte River Basin, Colo. (MRO) 21-9, 21-17 
South Platte River Levees and Channel Improvements, 
Chatfield Lake to Ft. Morgan, Colo. (MRO) 21-23 
South Plymouth Lake, N.Y. (NAB) 4-44 
South Point, Ohio (ORH) 25-26, 25-31 
South Portsmouth, Ky. (ORH) 25-26, 25-31 
South Quincy Drainage and Levee District, Ill. (NCR) 28-11, 
28-13 
South River Drainage District, Mo. (NCR) 28-12, 28-13 
South River, N. C. (SAW) 6-29 
South St. Paul, Minn. (NCS) 27-33 
South Tunbridge Lake, Vt. (NED) 1-71, 1-76 
South Williamson, Ky. (ORH) 25-30 
Southern New York Flood Control Projects (NAB) 4-15, 4-35, 
4-40, 4-41 
Southport Beach, Conn. (NED) 1-20, 1-69 
Southport Harbor, Conn. (NED) 1-65, 1-67 
Southwest Harbor, Maine (NED) 1-67 
Southwestern Jefferson County, Ky. (ORL) 24-21, 24-27 
Sowashee Creek, Meridian, Miss. (SAM) 10-17, 10-41 
Spanish Fork River, Utah (SPK) 35-34 
Spewrell Bluff Lake, Ga. (SAM) 10-21, 10-23, 10-29, 10-37, 
10-43 
Spokane River, Wash. (NPS) 38-11 
Spokane, Wash. (NPS) 38-28 
Spring City, Tenn. (ORN) 23-18 
Spring Creek, Springdale, Ark. (SWT) 19-19, 19-28 
Spring Lake Drainage and Levee District, Ill. (NCC) 30-41, 
30-42 
Springdale, Mass. (NED) 1-72, 1-76 
St. Thomas Harbor, V.I. (SAJ) 9-41 
Springer, William L., Lake, Ill. (NCC) 30-20, 30-25 
Springfield, Mass. (NED) 1-44, 1-72, 1-76 
Squaw Chute at Quincy, Ill. (NCR) 28-9 
St. Albans Harbor, Vt. (NAN) 2-45 
St. Anthony Falls, Minn. (NCD) 29-1, 29-3, 29-6, 29-10 
St. Augustine Harbor, Fla. (SAJ) 9-13, 9-27, 9-33 
St. Catherines Sound, Md. (NAB) 4-38 
St. Clair River, Mich. (NCE) 31-19, 31-40, 31-48, 31-53 
St. Croix River Board of Control, International 48-2 
St. Croix River, Maine (NED) 1-67 
St. Croix River, Minn. and Wis. (NCS) 27-9, 27-24, 27-28 
St. Francis and L'Anguille Rivers and Blackfish Bayou, Ark. 
(LMM) 13-9 
St. Francis Basin, Ark. and Mo. (MR&T) 42-2, 42-10, 42-12, 
42-20, 42-29, 42-54, 42-55, 42-57 
St. Francis River, Ark. and Mo. (MR&T) 42-54, 42-57 
St. Francis River Levees (MR&T) 42-49 
Ste. Genevieve Levee District No. 1, Mo. (LMS) 14-19 
St. Georges Creek, Md. (NAB) 4-38 
St. James Harbor, Mich. (NCE) 31-55 
St. James, Beaver Island, Mich. (NCE) 31-56 
St. Jeromes Creek, Md. (NAB) 4-38 
St. Joe River, Idaho (NPS) 38-11 
St. John River Basin, Maine (NED) 1-39 
St. Johns Bayou, Mo. (MR&T) 42-13 
St. Johns River, Fla. (SAJ) 9-30 
St. Johns River, Fla. Opposite the City of Jacksonville, Fla. 
(SAJ) 9-30 
St. Johns River, Jacksonville to Lake Harney, Fla. (SAJ) 9-40, 
9-41 
St. Johns River, Jacksonville to the Ocean, Fla. (SAJ) 9-30 
St. Jones River, Del. (NAP) 3-26 
St. Joseph Harbor, Mich. (NCE) 31-19, 31-40, 31-49 
St. Joseph River, Mich. (NCE) 31-20, 31-41, 31-49 
St. Lawrence River Board of Control, International 48-6 
St. Louis County Drainage and Levee District, Mo. (LMS) 14- 
19 
St. Lucie Inlet, Fla. (SAJ) 9-13, 9-27, 9-33 
St. Maries, Idaho (NPS) 38-28 
St. Marks River, Fla. (SAM) 10-39, 10-40 
St. Marys, Pa. (ORP) 26-28, 26-32 
St. Marys, W. Va. (ORH) 25-26, 25-31 
St. Marys River, Ga. and Fla., and North River, Ga. (SAS) 8- 
15, 8-16 
St. Marys River, Mich. (NCE) 31-20, 31-41, 31-49, 31-54 
St. Michael Canal, Alaska (NPA) 40-15 
St. Michaels Harbor, Md. (NAB) 4-38 
St. Patricks Creek, Md. (NAB) 4-38 
St. Paul, Minn. (NCS) 27-33 
St. Paul and South St. Paul, Minn. (NCS) 27-34 
St. Paul Harbor, Minn. (NCD) 29-3, 29-8 
St. Peters Creek, Md. (NAB) 4-38 
St. Petersburg Harbor, Fla. (SAJ) 9-40, 9-41 
St. Regis River, Mont. (NPS) 38-28 
1-34

INDEX 
Stage Harbor, Mass. (NED) 1-66 
Stamford, Conn. (NED) 1-41, 1-44, 1-53, 1-64 
Stamford Barrier, Conn. (NED) 1-44 
Stamford Harbor, Conn. (NED) 1-65, 1-67 
Stanislaus River, Calif. (SPK) 35-14, 35-26 
Stantonsburg Reservoir, N. C. (SAW) 6-31 
Starlings Creek, Va. (NAO) 5-26, 5-28 
Startup, Wash. (NPS) 38-28 
Starved Rock Lock, and Dam, Ill. (NCC) 30-8, 30-37, 30-38 
State Road and Ebner Coulees, Wis. (NCS) 27-19, 27-26 
Staten Island, N.Y. (NAN) 2-28, 2-35, 2-41 
Staten Island Rapid Transit Railway Co. Bridge Across 
Arthur Kill, N.Y. (NAN) 2-46 
Steele Bayou, Miss. (MR&T) 42-2, 42-19, 42-52, 42-58 
Steinhagen, B. A. Lake, Tex. (SWF) 16-2, 16-19 
Steinhatchee River, Fla. (SAJ) 9-41 
Stewart Canyon Debris and Channel, Calif. (SPL) 33-37, 33- 
38 
Stikine River, Alaska (NPA) 40-15 
Stillaguamish River, Wash. (NPS) 38-10, 38-11, 38-17, 38-23, 
38-27 
Stillhouse Hollow Dam, Tex. (SWF) 16-15, 16-21, 16-24 
Stillwater Creek and Tributaries, Okla. (SWT) 19-38 
Stillwater Lake, Pa. (NAB) 4-20, 4-29, 4-35 
Stillwell Drainage District, Oreg. (NPP) 37-56 
Stockton Harbor, Maine (NED) 1-65, 1-67 
Stockton Lake, Mo. (MRK) 20-19, 20-25, 20-31 
Stockton and Mormon Channels, Calif. (SPK) 35-31 
Stone Harbor, N.J. (NAP) 3-27 
Stonehouse Creek, Kans. (MRK) 20-33 
Stonewall Jackson Lake, W. Va. (ORP) 26-13, 26-21 
Stonewood-Nutter Fort, W. Va. (ORP) 26-30 
Stonington Harbor, Conn. (NED) 1-67 
Stonington Harbor, Maine (NED) 1-67 
Stony Creek, Branford, Conn. (NED) 1-65, 1-67 
Stratford, Conn. (NED) 1-76 
Stringtown Fort/Chartres and Ivy Landing, Ill. (LMS) 14-18 
Strube Lake and Cougar Additional Power, Oreg. (NPP) 37- 
52, 37-59 
Stuart Gulch Dam, Idaho (NPW) 39-18 
Stuart Reservoir, Va. and N. C. (SAW) 6-31 
Stumpy Point Bay, N. C. (SAW) 6-10, 6-24 
Sturgeon Bay and Lake Michigan Ship Canal, Wis. (NCC) 30- 
16, 30-24, 30-31, 30-35 
Sturgis, Ky. (ORL) 24-34, 24-40, 24-42 
Subdistrict No. 1 of Drainage Union No. 1 and Bay Island 
Drainage And Levee District No. 1, Illinois (NCR) 28-11, 
28-13 
Success Lake, Calif. (SPK) 35-10, 35-26 
Sucker Brook Dam, Conn. (NED) 1-29, 1-44, 1-51, 1-62, 1-71 
Sugar and Briar Creeks, N. C. (SAN) 7-8, 7-12, 7-15 
Sugar Creek Levee, Ind. (ORL) 24-34, 24-40 
Sugar Hill Reservoir, N.H. (NED) 1-71, 1-78 
Suisun Bay Channel, Calif. (SPN) (SPK) 34-10, 34-16, 34-21, 
35-31 
Suisun Channel, Calif. (SPK) 35-31 
Suisun Point Channel, Calif. (SPK) 35-31 
Sullivan Falls Harbor, Maine (NED) 1-67 
Sulphur River, Ark., and Tex. (LMN) 11-35, 11-53 
Summersville Lake, W. Va. (ORH) 25-16, 25-22, 25-27 
Sumpawanus (Babylon Creek) Inlet, N.Y. (NAN) 2-46 
Sunbury, Pa. (NAB) 4-44 
Supervisor of Harbor of Hampton Roads, Va. (Prevention of 
Obstructive and Injurious Deposits) (NAO) 5-14, 5-20 
Supervisor of New York Harbor (NAN) 2-16, 2-33, 2-43 
Surry Mountain Lake, N.H. (NED) 1-29, 1-51, 1-62, 1-71 
Survey of North Central Lakes (NCE) 31-31, 31-42 
Susquehanna River at and below Havre DeGrace, Md. (NAB) 
4-38 
Susquehanna River at Williamsport, Pa. (NAB) 4-38 
Susquehanna River Flood Control Projects, N.Y. and Pa. 
(NAB) 4-20, 4-35, 4-42 
Sutton Lake, W. Va. (ORH) 25-16, 25-22, 25-27 
Suwannee River, Fla. (SAJ) 9-40, 9-41 
Swanton Harbor, Vt. (NAN) 2-46 
Sweetwater Creek, N. C. (SAW) 6-32 
Sweetwater River, Calif. (SPL) 33-18, 33-23, 33-29 
Swift Creek, N. C. (SAW) 6-29 
Swift Creek, Pitt and Craven Counties, N. C. (SAW) 6-20, 6- 
32 
Swiger Whitney, Young, Hobit Levee, Ill. (NCC) 30-42 
Swinomish Channel, Wash. (NPS) 38-6, 38-17, 38-22 
Swoyersville and Forty Fort, Pa. (NAB) 4-44 
Sycamore Creek, Coffeyville, Kans. 
Sykesville, Pa. (ORP) 26-30, 26-32 
Syracuse, N.Y. (NCB) 32-44 
Syracuse, Ohio (ORH) 25-26, 25-32 
T 
T.J. O'Brien Lock and Dam, Ill. (NCC) 30-7, 30-37, 30-38 
Taber Reservoir, Va. (SAW) 6-31 
Table Mountain (Iron Canyon), Calif. (SPK) 35-20 
Table Rock Lake, Mo. (SWL) 18-7, 18-11, 18-13, 18-22, 18-23 
Tacoma, Puyallup River, Wash. (NPS) 38-10, 38-18, 38-23, 
38- 
Tacoma Harbor, Wash. (NPS) 38-7, 38-17, 38-22, 38-25 
Tahchevah Creek Detention Basin and Channel 
Improvements, Calif. (SPL) 33-37, 33-38 
Tahquitz Creek, Calif. (SPL) 33-38 
Talkeetna, Alaska (NPA) 40-16 
Tallahala Creek Lake, Miss. (SAM) 10-15, 10-28, 10-36 
Tallahatchie River, Miss. (MR&T) 42-52 
Tallahatchie and Coldwater Rivers, Miss. (LMK) 12-11 
Tallapoosa River, Ala. (SAM) 10-40 
Tallow Hill, Ga. (SAS) 8-16 
Talofofo Bay, Guam 36-6 
Tampa and Hillsborough Bays, Fla. (SAJ) 9-33 
Tampa Bay, Fla. (SAJ) 9-33 
Tampa Harbor, Fla. (SAJ) 9-15, 9-27, 9-33, 9-34 
Tangier Channel, Va. (NAO) 5-26, 5-28 
Tangipahoa River, La. (LMN) 11-53 
Tar Creek Levee, Ill. (NCC) 30-42 
Tar River and Tributaries, N. C. (SAW) 6-32 
Tar River, N. C. (SAW) 6-32 
Tar River, Princeville, N. C. (SAW) 6-32 
Tarentum, Pa. (ORP) 26-30, 26-32 
Tarrytown Harbor, N.Y. (NAN) 2-46 
Taskinas Creek, Va. (NAO) 5-14, 5-21, 5-24 
Tat Momolikot Dam and Lake St. Clair, Ariz. (SPL) 33-11, 
33-22, 33-27 
Tau Small Boat Harbor, American Samoa 36-5, 36-10 
Taunton River, Mass. (NED) 1-67 
Tawas Bay Harbor, Mich. (NCE) 31-23, 31-41, 31-50 
Taylors Bayou, Tex. (SWG) 15-15, 15-19, 15-30 
Taylorsville, Ky. (ORL) 24-34, 24-40, 24-42 
Taylorsville Lake, Ky. (ORL) 24-21, 24-27 
Tchula Lake, Miss. (MR&T) 42-52 
Teche-Vermilion Basins, La. (MR&T) 42-16, 42-29, 42-58 
Tell City, Ind. (ORL) 24-34, 24-40, 24-42 
Templeton Gap Floodway, Colo. (SWA) 17-20 
Tenants Harbor, Maine (NED) 1-67 
I-35

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Tenasillahe Island, Oreg. (NPP) 37-53 
Tenkiller Ferry Lake, Okla. (SWL) (SWT) 18-18, 19-23, 19- 
28, 19-32, 19-36 
Tenmile Creek at Marianna, Pa. (ORP) 26-15, 26-21 
Tennessee Colony Lake, Tex. (SWF) 16-3, 16-4 
Tennessee River, Ala. and Miss. (SAM) 10-13, 10-28, 10-36 
Tennessee River, Tenn., Ala., and Ky. (ORN) 23-3, 23-10, 
23-12, 23-16, 23-17 
Tennessee-Tombigbee Waterway, Ala. and Miss. (ORN) 23-4, 
23-10, 23-13 
Tensas River and Bayou Macon, La. (LMK) 12-11 
Tensas River Basin, La. and Ark. (MR&T) 42-8, 42-17, 42-18, 
42-29, 42-52, 42-55, 42-57 
Terminus Dam, Calif. (SPK) 35-10, 35-26 
Terre Haute (Conover Levee) Ind., (ORL) 24-40, 24-42 
Terre Noire Creek, Ark. (LMK) 12-12 
Terry, David D., Lock and Dam, Ark. (SWL) 18-2, 18-3, 18- 
16 
Teton River, Idaho (NPW) 39-16 
Texas City and Vicinity, Tex. (Hurricane-Flood Protection) 
(SWG) 15-15, 15-16, 15-19, 15-30 
Texas City Channel, Tex. (SWG) 15-9, 15-18, 15-29, 15-33, 
15-36, 15-41 
Thames River Basin, Conn., R.I. and Mass. (NED) 1-41, 1-44, 
1-75 
Thames River, Conn. (NED) 1-65, 1-67 
The Cascades Canal, Oreg. (NPP) 37-47 
The Dalles-Celilo Canal, Oreg. and Wash. (NPP) 37-47 
The Dalles Lock and Dam-Lake Celilo, Wash. and Oreg. 
(NPP) 37-29, 37-36, 37-45, 37-58 
The Inland Route, Mich. (NCE) 31-9, 31-38, 31-46 
The Island Lake, Vt. (NED) 1-71, 1-76 
Thimble Shoal Channel, Va. (NAO) 5-10, 5-24 
Thomaston Dam, Conn. (NED) 1-34, 1-52, 1-63, 1-73 
Thompson Lake Drainage and Levee District, Ill. (NCC) 30- 
41, 30-42 
Thoroughfare Swamp, N. C. (SAW) 6-19, 6-26 
Three Forks, Mont. (MRO) 21-20 
Three Islands Reservoir, Tenn. (ORN) 23-18, 23-19 
Three Rivers, Mass. (NED) 1-44, 1-72, 1-76 
Three Rivers, Tex. (SWF) 16-16, 16-21 
Thumpertown Beach, Eastham, Mass. (NED) 1-69 (SPK) 35- 
22, 35-34 
Tickfaw, Natalbany, Pontchatoula, and Blood Rivers, La. 
(LMN) 11-53 
Ticonderoga River, N.Y. (NAN) 2-46 
Tijuana River Basin, Calif. (SPL) 33-18, 33-23, 33-29 
Tilghman Island Harbor, Md. (NAB) 4-38 
Tillamook Bay and Bar, Oreg. (NPP) 37-11, 37-33, 37-41 
Tioga-Hammond Lakes, Pa. (NAB) 4-20, 4-29, 4-42, 4-43 
Tionesta Lake, Pa. (ORP) 26-15, 26-21, 26-29 
Toad Suck Ferry Lock and Dam, Ark. (SWL) 18-2, 18-4, 18- 
16 
Tocks Island Lake, Pa., N.J. and N.Y. (NAP) 3-18, 3-21 
Todd Swamp, S. C. (SAN) 7-17 
Toledo Harbor, Ohio (NCE) 31-23, 31-41, 31-50 
Toiu, Ky. (ORL) 24-35, 24-40 
Tom Jenkins Reservoir, Ohio (ORH) 25-17, 25-22, 25-27 
Tomahawk Lake, Kans. (MRK) 20-15, 20-24 
Tomanovich-Salmon City, Idaho (NPW) 39-17, 39-18 
Tombigbee River, Miss. and Ala. (SAM) 10-13, 10-16, 10-28, 
10-36 
Tombigbee River Tributaries, Miss., and Ala. (SAM) 10-16, 
10-28, 10-36 
Tombigbee Rivers, Ala. (SAM) 10-4, 10-26, 10-31, 10-38 
Toms River, N.J. (NAP) 3-26 
Tongue River Lake, N. Dak. (NCS) 27-34 
Topeka, Kans. (MRK) 20-31, 20-32, 20-33 
Topsail Beach and Surf City, N. C. (SAW) 6-32 
Toronto, Kans. (SWL) 18-2, 18-18 
Toronto Lake, Kans. (SWL) (SWT) 19-19, 19-28, 19-32, 19-35 
Torrington, Conn. (NED) 1-44 
Torrington, East Branch, Conn. (NED) 1-76 
Torrington, West Branch, Conn. (NED) 1-76 
Totuskey Creek, Va. (NAO) 5-26, 5-28 
Touchet River, Wash. (NPW) 39-16 
Towanda Lake, Kans. (SWT) 19-38 
Town Beach, Plymouth, Mass. (NED) 1-69 
Town Bluff Dam-B. A. Steinhagen Lake, Tex. (SWF) 16-2, 
16-19, 16-23 
Town Creek, Americus, Ga. (SAM) 10-17, 10-41 
Town Creek, Harrodsburg, Ky. (ORL) 24-40 
Town Creek, Md. (NAB) 4-38 
Town Neck Beach, Sandwich, Mass. (NED) 1-69 
Townshend Lake, Vt. (NED) 1-29, 1-51, 1-62, 1-71 
Trabuco Dam, Calif. (SPL) 33-36, 33-38 
Tradewater River, Ky. (ORL) 24-44 
Tranquitas Creek, Kingsville, Tex. (SWG) 15-16, 15-32 
Tranters Creek, N. C. (SAW) 6-32 
Traverse City, Mich. (NCE) 31-55 
Traverse City Harbor, Mich. (NCE) 31-56 
Treasure Island, Mo. (LMM) 13-4, 13-7, 13-8 
Treatment of Yuba River Debris Situation-Restraining 
Barriers, Calif. (CDC) 44-2, 44-5 
Tred Avon River, Md. (NAB) 4-8, 4-27, 4-33 
Trent River, N. C. (SAW) 6-29, 6-32 
Trenton Lake, Mo. (MRK) 20-33 
Trexler Lake, a. (NAP) 3-17, 3-21 
Trinidad Lake. Colo. (SWA) 17-13, 17-17, 17-19 
Trinity River and Tributaries, Tex. (SWF) (SWG) 15-9, 15-18, 
15-29, 15-33, 15-37, 15-41, 16-2, 16-16, 16-26 
Trinity River Project, Tex. (SWF) 16-3, 16-19 
Triplett Creek, Morehead, Ky. (ORL) 24-43 
Tri-Pond Levee, Ill. (ORL) 24-35, 24-40 
Trotters Shoals Dam and Lake, Ga. and S. C. (SAS) 8-9, 8-12, 
8-15 
Troublesome Creek, Ky. (ORL) 24-43 
Troy, Ind. (ORL) 24-35, 24-40 
Truckee River and Tributaries, Calif. and Nev. (SPK) 35-22, 
35-34 
Truman, Harry S., Dam and Reservoir, Mo. (MRK) 20-18, 
20-24, 20-31 
Trumbull Lake, Conn. (NED) 1-76 
Trussville, Ala. (SAM) 10-41 
Truth or Consequences (Hot Springs) Unit, N. Mex. (SWA) 
17-13, 17-19 
Tucannon River, Camp Wooten, Wash. (NPW) 39-17, 39-18 
Tuckahoe River, Md. (NAB) 4-38 
Tuckerton Creek, N.J. (NAP) 3-26 
Tug Fork Valley, Ky., Va., and W. Va. (ORH) 25-17, 25-22 
Tule River, Calif. (SPK) 35-10, 35-26 
Tully Lake, Mass. (NED) 1-30, 1-51, 1-62, 1-71 
Tulsa and West Tulsa Levees, Okla. (SWT) 19-37, 19-38 
Tuolumne River, Calif. (SPK) 35-14, 35-26 
Turkey Creek, Okla. (SWT) 19-38 
Turkey Creek, Sumter County, S. C. (SAN) 7-17 
Turner Prairie, Mill Creek, Oreg. (NPP) 37-55 
Turtle Creek, Pa. (ORP) 26-30, 26-32 
Turtle Creek, Yukon, Okla. (SWT) 19-19 
Tuscon Diversion Channel, Ariz. (SPL) 33-37 
Tuskahoma Lake, Okla. (SWT) 19-36, 19-38 
Tuttle Creek Lake, Kans. (MRK) 20-16, 20-24, 20-31 
1-36

INDEX 
Tuttle Creek Lake (Road Improvements), Kans. (MRK) 20- 
16, 20-24, 20-31 
Twelvemile Bayou, La. (LMN) 11-57 
Twelvepole Creek, W. Va. (ORH) 25-27 
Twenty Mile Creek, Miss. (SAM) 10-17 
Twin Valley Lake, Minn. (NCS) 27-19, 27-26 
Twitch Cove and Big Thorofare, Md. (NAB) 4-9, 4-27, 4-33 
Two Harbors, Minn. (NCS) 27-10, 27-25, 27-28 
Two Rivers Dam, N. Mex. (SWA) 17-14, 17-17 
Two Rivers Harbor, Wis. (NCC) 30-16, 30-24, 30-32, 30-35 
Tyaskin Creek, Md. (NAB) 4-38 
Tybee Island, Ga. (SAS) 8-6, 8-11, 8-14 
Tygart River Lake, W. Va. (ORP) 26-3, 26-19 
Tylers Beach, Va. (NAO) 5-26, 5-28 
Tyrone, Pa. (NAB) 4-21, 4-29, 4-35 
Tyrzona River, Ark. (MR&T) 42-52 
U 
Umatilla Harbor, Oreg. (NPP) 37-47 
Umatilla River (Echo), Oreg. (NPP) 37-56 
Umpqua River, Oreg. (NPP) 37-12, 37-33, 37-41 
Umpqua River and Tributaries, Oreg. (NPP) 37-56 
Unadilla, N.Y. (NAB) 4-44 
Union City Lake, Pa. (ORP) 26-15, 26-21 
Union Lake, Mo. (LMS) 14-8, 14-14, 14-17 
Union River, Maine (NED) 1-67 
Union Township Drainage District, Mo. (NCR) 28-12, 28-13 
Union Village Dam, Vt. (NED) 1-30, 1-51, 1-62, 1-71 
Uniontown, Ky. (ORL) 24-35, 24-40, 24-42 
Uniontown, Pa. (ORP) 26-32 
Uniontown Locks and Dam, Ky. (ORD) 22-1, 22-2, 22-3, 22-9 
University Wash and Spring Brook, Riverside, Calif. (SPL) 
33-18, 33-23, 33-29 
Upper Chipola River, Fla., from Mariana to Its Mouth (SAM) 
10-40 
Upper Grand River, Mo. (MRK) 20-33 
Upper Grays River Area, Wash. (NPP) 37-53 
Upper Iowa River, Iowa (NCS) 27-33, 27-34 
Upper Machodoc Creek, Va. (NAB) 4-38 
Upper Marlboro, Md. (NAB) 4-44 
Upper Mississippi River Basin (Rock Island District) (NCR) 
28-13 
Upper Mississippi River Basin (LMS) 14-10, 14-16 
Upper Mississippi River Basin (St. Paul Dist.) Black River 
Lake, Wis. (NCS) 27-34 
Upper Pointe Coupee Loop, La. (MR&T) 42-1, 42-14 
Upper Puyallup River, Wash. (NPS) 38-28 
Upper River Rouge, Mich. (NCE) 31-57 
Upper St. Francis River and Floodway (MR&T) 42-10, 42-11 
Upper Thorofare, Md. (NAB) 4-9, 4-27, 4-34 
Upper White River, Ark. (SWL) 18-20 
Urban Areas at Alton, Ill. (LMS) 14-19 
Urbanna Creek, Va. (NAO) 5-26, 5-28 
Utica, Ind. (ORL) 24-35, 24-40 
Utica, Ohio (ORH) 25-30 
Utica Lake, Ohio (ORH) 25-17, 25-22 
V 
Valdez Harbor, Alaska (NPA) 40-15 
Valley City Drainage and Levee District Ill. (LMS) 14-19 
Valley Drainage and Levee District, Ill. (NCC) 30-41 
Van Buren, Ark. (SWL) 18-24 
Vanceburg, Ky. (ORH) 25-26, 25-32 
Vancouver Lake Area, Wash. (NPP) 37-22, 37-35, 37-43 
Vandalia Drainage and Levee District No. 21, Ill. (LMS) 14-6, 
14-13, 14-17 
Van Meter, Iowa (NCR) 28-11, 28-13 
Vaughn, Mont. (MRO) 21-20, 21-23 
Velva, N. Dak. (NCS) 27-34 
Ventnor, Margate and Longport, N.J. (NAP) 3-27 
Ventura Marina, Calif. (SPL) 33-7, 33-21, 33-26 
Ventura-Pierpont Area, California (SPL) 33-31 
Ventura River Basin, Calif. (SPL) 33-38 
Ventura River Levee, Calif. (SPL) 33-37, 33-38 
Vermilion Harbor, Ohio (NCB) 32-17, 32-28, 32-40 
Vermilion Lock, La. (LMN) 11-12, 11-13, 11-52 
Verona Lake, Va. (NAB) 4-23, 4-30, 4-36 
Verona (Mouth of Feather River), Calif. (SPK) 35-30 
Vevay, Ind. (ORL) 24-35, 24-40 
Vicksburg Harbor, Miss. (MR&T) 42-1, 42-12, 42-30, 42-56 
Victory Lake, Vt. (NED) 1-71, 1-76 
Villa Park Dam, Calif. (SPL) 33-36, 33-38 
Village Creek, Ark. (SWL) 18-7, 18-13, 18-14 
Village Creek, S. C. (SAN) 7-6, 7-11, 7-15 
Village Creek, White River, and Mayberry Levee Districts, 
Ark. (SWL) 18-24 
Village of New Athens, Ill. (LMS) 14-17, 14-19 
Villisca, Iowa (MRK) 20-32 
Vince and Little Vince Bayous, Tex. (SWG) 15-15, 15-19, 15- 
31 
Vincennes, Ind. (ORL) 24-35, 24-40, 24-42 
Vineyard Haven, Mass. (NED) 1-68 
Vinton Waterway, La. (LMN) 11-53 
Virginia Beach, Va. (NAO) 5-15, 5-21, 5-24 
Virginia Key and Key Biscayne, Fla. (SAJ) 9-19, 9-28, 9-35 
W 
W. D. Mayo Lock and Dam, Okla. (SWL) (SWT) 18-2, 18-17, 
19-4, 19-32, 19-36 
W. Kerr Scott Dam and Reservoir (Wilkesboro Reservoir), N. 
C. (SAN) 7-7, 7-12, 7-15, 7-16 
W. P. Franklin Lock and Dam, Fla. (SAJ) 9-45 
Wabash River Basin, Ind., Ill. and Ohio (ORL) 24-14, 24-22, 
24-26, 24-29, 24-34, 24-35, 24-36, 24-39, 24-42 
Wabasha Harbor, Minn. (NCD) 29-3, 29-8 
Wabash Railroad Bridges Meredosia and Valley City, Ill. 
(LMS) 14-17 
Waccamaw River, N. C. and S. C. (SAN) 7-16, 7-17 
Waco Lake, Tex. (SWF) 16-16, 16-21, 16-24 
Wahkiakum County Consolidated Diking District No. 1, 
Wash. (NPP) 37-22, 37-35, 37-43, 37-50 
Wahkiakum County Diking Districts 1 and 3, Wash. (NPP) 
37-53 
Wahkiakum County Diking Improvement District 4, Wash. 
(NPP) 37-50, 37-53, 37-55 
Waianae Small Boat Harbor, Oahu, Hawaii (POD) 36-5, 36- 
10, 36-12 
Waikiki Beach, Oahu, Hawaii (POD) 36-6, 36-10, 36-12 
Wailoa Stream and Tributaries, Hawaii, Hawaii (POD) 36-8, 
36-14 
Waimea Beach, Kauai, Hawaii (POD) 36-14 
Wake Island Harbor, Wake Island (POD) 36-13 
Waldo Lake Tunnel and Reregulating Works, Oreg. (NPP) 
37-52, 37-59 
Wallabout Channel, N.Y. (NAN) 2-46 
1-37

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Wallace, W. Va. (ORP) 26-32 
Wallace Channel, Pamlico Sound, N. C. (SAW) 6-29 
Wallace Lake, La. (LMN) 11-35, 11-41, 11-49, 11-54, 11-56 
Wallis Sands State Beach, Rye, N.H. (NED) 1-20, 1-69 
Wallisville Lake, Tex. (SWG) 15-10 
Walluski River, Oreg. (NPP) 37-53 
Walnut Bayou Channel Improvement, Ark. (SWT) 19-36, 19- 
37, 19-38 
Walnut Creek, Calif. (SPK) 35-21, 35-22, 35-27 
Walter F. George Lock and Dam, Ala. and Ga. (SAM) 10-21, 
10-24, 10-29, 10-37, 10-43 
Walter, Francis E., Dam, Pa. (NAP) 3-15, 3-21 
Wappapello Lake, Mo. (MR&T) 42-11, 42-20, 42-22, 42-57 
Wappinger Creek, N.Y. (NAN) 2-46 
Wappinger Creek at Pleasant Valley, N.Y. (NAN) 2-47 
Ware, Mass. (NED) 1-44, 1-72, 1-76 
Wareham Harbor, Mass. (NED) 1-68 
Wareham-Marion, Mass. (NED) 1-76 
Warm Springs Lake and Channel, Calif. (SPN) 34-13, 34-17, 
34-22 
Warren River, R.I. (NED) 1-68 
Warrenton Diking District 1, Oreg. (NPP) 37-53 
Warrenton Diking District 2, Oreg. (NPP) 37-53 
Warrenton Diking District 3, Oreg. (NPP) 37-54 
Warroad Harbor and River, Minn. (NCS) 27-10, 27-25, 27-28 
Warrior Lock and Dam, Ala. (SAM) 10-5, 10-38 
Warroad River and Bull Dog Creek, Minn. (NCS) 27-34 
Washougal Area Levees, Wash. (NPP) 37-55 
Water Hyacinth Removal, La. (LMN) 11-24, 11-39, 11-47 
Waterbury Dam, Vt. (NAN) 2-29, 2-35, 2-41, 2-47 
Warsaw Harbor, Ill. (NCD) 29-2, 29-9 
Warsaw, N.Y., Oatka Creek (NCB) 32-44 
Warwick Cove, R.I. (NED) 1-16, 1-49, 1-60, 1-65 
Warwick River, Md. (NAB) 4-38 
Warwood, W. Va. (ORP) 26-28, 26-32 
Washington Aqueduct, Maintenance, Operation, and Capital 
Outlay (NAB) 4-24, 4-46 
Washington Canal and South River, N.J. (NAN) 2-46 
Washington, D.C. and Vicinity (NAB) 4-44 
Washington Harbor, D.C. (NAB) 4-10, 4-27, 4-34 
Washington, Pa. (ORP) 26-30, 26-32 
Watch Hill Cove, R.I. (NED) 1-65 
Water Chestnut Elimination (NAB) 4-8, 4-26, 4-33 
Water Hyacinth Removal (SAM) 10-13, 10-28, 10-36 
Water Hyacinth Removal from Navigable Waters in the State 
of Florida (SAJ) 9-13, 9-27, 9-32, 9-40 
Water Valley Lake, Ark. and Mo. (SWL) 18-22, 18-24 
Waterbury, Conn. (NED) 1-44 
Waterbury-Watertown, Conn. (NED) 1-76 
Wateree River, S. C. (SAN) 7-16 
Waterford, Hudson and Mohawk Rivers, N.Y. (NAN) 2-47 
Waterloo, Iowa (NCR) 28-6, 28-9, 28-11 
Waterloo, Nebr. (MRO) 21-21, 21-23 
Waterway Connecting Pamlico Sound and Beaufort Harbor, 
N. C. (SAW) 6-11, 6-24, 6-28 
Waterway Connecting Port Townsend and Oak Bay, Wash. 
(NPS) 38-7, 38-17, 38-22 
Waterway Connecting Swanquarter Bay With Deep Bay, N. 
C. (SAW) 6-11, 6-25 
Waterway Connecting Tombigbee and Tennessee Rivers, Ala. 
and Miss. (SAM) 10-13, 10-28, 10-36 
Waterway from Empire, La., to Gulf of Mexico (LMN) 11-25, 
11-39, 11-47 
Waterway from Indian River Inlet to Rehoboth Bay, Del. 
(NAP) 3-26 
Waterway from Intracoastal Waterway to Bayou Dulac, La. 
(Bayous Grand Caillou and Le Carpe, La.) (LMN) 11-25, 
11-39, 11-47 
Waterway from Little Choptank River to Choptank River, 
Md. (NAB) 4-38 
Waterway from White Lake to Pecan Island, La. (LMN) 11-53 
Waterway-Norfolk, Va., to Sounds of N. C. (SAW) 6-11, 6-25 
Waterway on the Coast of Virginia (NAO) 5-6, 5-19, 5-22 
Waterways Experiment Station (WES) 45-1 
Watkins Glen, N.Y. (NCB) 32-44 
Watts Bar, Tenn. (ORN) 23-16 
Watts Levee, Ill. (NCC) 30-42 
Waukegan Harbor, Ill. (NCC) 30-17, 30-24, 30-32, 30-35 
Waurika Lake, Okla. (SWT) 19-19, 19-28, 19-31 
Waverly, W. Va. (ORH) 25-26, 25-32 
Wax Lake Outlet, La. (MR&T) 42-15, 42-51, 42-56 
Waycake Creek, N.J. (NAN) 2-44, 2-46 
Webb District Improvement Co., Oreg. (NPP) 37-54 
Webbers Falls Lock and Dam, Okla. (SWL) (SWT) 18-2, 18- 
17, 19-24, 19-29, 19-31, 19-32, 19-36 
Weber River and Tributaries, Utah (SPK) 35-34 
Weidmer Chemicals Drainage and Levee District, Mo. (LMS) 
14-19 
Weiser River, Idaho (NPW) 39-18 
Wellfleet Harbor, Mass. (NED) 1-65, 1-68 
Wells Harbor, Guam (POD) 36-13 
Wells Harbor, Maine (NED) 1-17, 1-49, 1-60, 1-65 
Wellsburg, W. Va. (ORP) 26-28, 26-32 
Wellsville, N.Y. (NCB) 32-24, 32-29 
Wellsville, Ohio (ORP) 26-30 
Wellsville, Ohio, Sec. I (ORP) 26-28, 26-32 
Wellsville, Ohio, Sec. II (ORP) 26-28, 26-32 
Wenatchee Canyons #1 and 2, Wash. (NPS) 38-10, 38-18, 38- 
23 
Wenatchee River, Wash. (NPS) 38-28 
Wessagusett Beach, Weymouth, Mass. (NED) 1-20, 1-69 
West Branch Chisholm Creek, Kans. (SWT) 19-38 
West Branch of Susquehanna River, Pa. (NAB) 4-21, 4-35, 4- 
43 
West Bridgewater, Pa. (ORP) 26-28, 26-32 
West Brookfield Reservoir, Mass. (NED) 1-71, 1-78 
West Canaan Lake, N.H. (NED) 1-71, 1-76 
West Fork Floodway, Tex. (SWF) 16-4, 16-5 
West Fork Lake, W. Va. (ORH) 25-27, 25-29, 25-32 
West Fork of Mill Creek Lake, Ohio (ORL) 24-22, 24-27, 24- 
36 
West Glendive, Mont. (MRO) 21-20 
West Harbor, Ohio (NCE) 31-56 
West Hickman Area, Hickman, Ky. (LMM) 13-5, 13-7, 13-8 
West Hill Dam, Mass. (NED) 1-21, 1-49, 1-61, 1-70 
West Kentucky Tributaries, Ky. (MR&T) 42-2, 42-21, 42-29, 
42-54, 42-55, 42-57, 42-58 
West Matanzas Drainage and Levee District, Ill. (NCC) 30-41 
West Memphis Drainage, Ark. (MR&T) 42-52 
West Muddy Creek and Marys River, Oreg. (NPP) 37-55 
West of Morrilton, Ark. (SWL) 18-24 
West Oneonta Lake, N.Y. (NAB) 4-40, 4-41, 4-44 
West Point, Ga. (SAM) 10-17, 10-41 
West Point, Ky. (ORL) 24-35, 24-40 
West Point, Nebr. (MRO) 21-23 
West Point, Elkhorn River, Nebr. (MRO) 21-21 
West Point Lake, Ga. and Ala. (SAS) (SAM) 8-i0, 10-21, 10- 
24, 10-29, 10-37, 10-43 
West Protection Levee, La. (MR&T) 42-52 
West Richland, Wash. (NPW) 39-17 
West Springfield, Mass. (NED) 1-44, 1-72, 1-77 
I-38

INDEX 
West Tennessee Tributaries, Tenn. (MR&T) 42-11, 42-21, 42- 
29, 42-54, 42-55, 42-57 
West Terre Haute, Ind. (ORL) 24-22, 24-27, 24-35, 24-42 
West Thompson Lake, Conn. (NED) 1-43, 1-54, 1-64, 1-75 
West Union, W. Va. (ORH) 25-30 
West Warren, Mass. (NED) 1-44, 1-72, 1-77 
Westchester Creek, N.Y. (NAN) 2-46 
Westcott Cove, Conn. (NED) 1-68 
Westerly, R.I. (NED) 1-76 
Westfield, Mass. (NED) 1-78 
Westland District Improvement Co., Oreg. (NPP) 37-54 
Weston, Vt. (NED) 1-44, 1-72, 1-77 
Weston, W. Va. (ORP) 26-30 
Westport, Conn. (NED) 1-78 
Westport, Ky. (ORL) 24-35, 24-40 
Westport District, Oreg. (NPP) 37-54 
Westport Harbor, Conn. (NED) 1-65 
Westport Harbor and Saugatuck River, Conn. (NED) 1-68 
Westport River, Mass. (NED) 1-68 
Westport Slough, Oreg. (NPP) 37-47 
Westville Lake, Mass. (NED) 1-43, 1-54, 1-64, 1-75 
Weymouth Back River, Mass. (NED) 1-68 
Weymouth-Fore and Town Rivers, Boston Harbor, Mass. 
(NED) 1-17, 1-49, 1-60 
Wheeler, General Joe, Lock Ala. (ORN) 23-4, 23-16 
Wheeling, W. Va. (ORP) 26-28, 26-32 
Wheeling, W. Va. (North Wheeling) (ORP) 26-28, 26-32 
Wheeling, W. Va. (Wheeling Island) (ORP) 26-28, 26-32 
White City Park, Ohio (NCB) 32-43 
White Lake Harbor, Mich. (NCE) 31-24, 31-42, 31-51 
White Oak Dike, N. C. (SAW) 6-20, 6-32 
White River, Ark. (MR&T) 42-2, 42-57 
White River, Ark. (Above Peach Orchard Bluff) (SWL) 18-20 
White River, Ark. (below Newport) (LMM) 13-2, 13-7, 13-8 
White River, Ind. (ORL) 24-34, 24-38, 24-39, 24-44 
White River Basin, Ark. (SWL) 18-7, 18-13, 18-14, 18-22, 18- 
23 
White River Levees (MR&T) 42-50 
Whitebird Creek, Idaho (NPW) 39-16 
Whitefish Point Harbor, Mich. (NCE) 31-24, 31-41, 31-50 
Whitesburg, Ky. (ORL) 24-43 
Whitewater River Basin, Calif. (SPL) 33-38 
Whitings Creek, Va. (NAO) 5-26, 5-28 
Whitlow Ranch Dam and Reservoir, Ariz. (SPL) 33-12, 33-22, 
33-27 
Whitmanville Lake, Mass. (NED) 1-74, 1-77 
Whitney Lake, Tex. (SWF) 16-18, 16-21 
Whitney Point Lake, N.Y. (NAB) 4-19, 4-29, 4-40, 4-41 
Whitney Point Village, N.Y. (NAB) 4-19, 4-29, 4-40, 4-41 
Whittington, Will M., Canal (MR&T) 42-57 
Wichita and Valley Center, Kans. (SWT) 19-37, 19-38 
Wichita River Chloride Control Plan, Tex. (SWT) 19-6, 19-33 
Wickford Harbor, R.I. (NED) 1-65, 1-68 
Wicomico River, Md. (NAB) 4-10, 4-27, 4-34 
Wiggins Mill Dam and Reservoir, N. C. (SAW) 6-31 
Wilcox, Pa. (ORP) 26-32 
Wild Rice, Minn. (NCS) 27-33 
Wild Rice and Marsh Rivers, Minn. (NCS) 27-32 
Wild Rice River - South Branch and Felton Ditch, Minn. 
(NCS) 27-20, 27-26 
Wilders, Ky. (ORL) 24-35 
Wilds Bend (NCD) 29-3 
Wiley Creek Lake, Oreg. (NPP) 37-55 
Wilkes-Barre, Pa. (NAB) 4-44 
Wilkesboro Reservoir, N. C. (SAN) 7-7, 7-12, 7-15 
Will M. Whittington Canal (MR&T) 42-57 
Willamette Falls Fish Ladder, Oreg. (NPP) 37-52 
Willamette River Above Portland and Yamhill River, Oreg. 
(NPP) 37-12, 37-33, 37-41 
Williamette River and Major Channel Clearing and Snagging 
on Tributaries, Oreg. (NPP) 37-51, 37-55 
Willamette River and Middle Fork, Oreg. (NPP) 37-52 
Willamette River at Willamette Falls, Oreg. (NPP) 37-13, 37- 
33, 37-42, 37-46 
Willamette River Basin, Oreg. (NPP) 37-22, 37-44, 37-51, 37- 
55 
Willamette River Basin, Bank Protection Oreg. (NPP) 37-23, 
37-35, 37-44, 37-52 
Willamette River Basin Channel Clearing and Snagging, 
Oreg. (NPP) 37-51, 37-55 
Willamette River Basin Flood Control Projects, Oreg. (NPP) 
37-23, 37-51 
Willapa River and Harbor and Naselle River, Wash. (NPS) 
38-8, 38-17, 38-22, 38-25 
William Bacon Oliver Lock and Dam, Ala. (SAM) 10-5, 10-38 
William L. Springer Lake, Ill. (NCC) 30-20, 30-25 
Williamson, W. Va. (ORH) 25-30, 25-32 
Williamsport, Pa. (NAB) 4-44 
Williamstown, W. Va. (ORH) 25-26, 25-32 
Williamsville Reservoir, Vt. (NED) 1-77 
Williston, N. Dak. (MRO) 21-20 
Willoughby Channel, Va. (NAO) 5-26, 5-28 
Willow Creek Lake, Oreg. (NPW) 39-5, 39-12, 39-15 
Willow Island Locks and Dam, W. Va. (ORD) 22-1, 22-2, 22- 
3, 22-7 
Wilmington Harbor, Del. (NAP) 3-13, 3-21, 3-24 
Wilmington Harbor, N. C. (SAW) 6-12, 6-25 
Wilmore, Pa. (ORP) 26-30, 26-32 
Wilson Harbor, N.Y. (NCB) 32-18, 32-28, 32-40 
Wilson Lake, Kans. (MRK) 20-17, 20-24, 20-31 
Wilson Mills Reservoir, N. C. (SAW) 6-31 
Wilson Point Harbor, Conn. (NED) 1-68 
Wilson Project, Ala. (ORN) 23-16 
Wilton, N.H. (NED) 1-44 
Winfield, Kans. (SWT) 19-20, 19-28, 19-31, 19-38 
Winnetka, Ill. (NCC) 30-41 
Winnibigoshish Reservoir, Minn. (NCS) 27-29 
Winnipesaukee Lake, N.H. (NED) 1-68 
Winona Harbors, Minn. (NCD) 29-3, 29-8 
Winona, Minn. (NCS) 27-20, 27-26, 27-33 
Winooski River, Vt. (NAN) 2-47 
Winslow (Tributaries of Little Colorado River), Ariz. (SPL) 
33-38 
Winsted, Conn. (NED) 1-44, 1-72, 1-77 
Winter Harbor, Maine (NED) 1-18, 1-49, 1-60 
Winter Harbor, Va. (NAO) 5-26, 5-28 
Winthrop Beach, Mass. (NED) 1-20, 1-69 
Winthrop Harbor, Mass. (NED) 1-68 
Wisconsin River, Wis. (NCS) 27-31 
Wishart Point Channel, Va. (NAO) 5-15, 5-21, 5-24 
Wister, Okla. (SWL) 18-2, 18-18 
Wister Lake, Okla. (SWL) (SWT) 19-20, 19-28, 19-32, 19-35 
Withlacoochee River, Fla. (SAJ) 9-40, 9-41 
Wolf - Coffee Lake, Kans. (MRK) 20-17, 20-24 
Wolf Creek Dam and Lake Cumberland, Ky. (ORN) 23-8, 23- 
10, 23-18 
Wolf and Jordan Rivers, Miss. (SAM) 10-39, 10-40 
Wolf River (Memphis Harbor), Tenn. (LMM) 13-3, 13-7, 13-8 
Wolf River and Tributaries, Tenn. (MR&T) 42-2, 42-54, 42- 
56 
Wood Island Harbor, Maine (NED) 1-65 
Wood Island Harbor, Maine and Pool at Biddeford (NED) 1- 
68 
I-39

REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1975 
Wood River Drainage and Levee District, Ill. (LMS) 14-10, 
14-14, 14-16 
Wood River Levee Project, Ill. (LMS) 14-18 
Woodbridge Creek, N.J. (NAN) 2-46 
Woodbury Creek, N.J. (NAP) 3-26 
Woodcock Creek Lake, Pa. (ORP) 26-16, 26-21 
Woodland Street Bridge, Nashville, Tenn. (ORN) 23-5 
Woodlands, W. Va. (ORH) (ORP) 26-28, 26-32 
Woodmont Shore, Milford, Conn. (NED) 1-20, 1-69 
Woodruff, Jim, Lock and Dam, Ga. and Fla. (SAM) 10-21, 10- 
23, 10-29, 10-37, 10-43 
Woods Hole Channel, Mass. (NED) 1-65, 1-68 
Woodson Drainage District, Oreg. (NPP) 37-50, 37-53, 37-54 
Woonsocket, R. I. (NED) 1-44, 1-70, 1-77 
Worcester Diversion, Mass. (NED) 1-21, 1-44, 1-50, 1-61, 1-70 
Wrangell Harbor, Alaska (NPA) 40-15 
Wrangell Narrows, Alaska (NPA) 40-15 
Wright Patman Dam and Lake, Tex. (LMN) 11-35, 11-41, 11- 
49, 11-54, 11-55 
Wrights Creek, N. C. (SAW) 6-29 
Wrightsville Beach, N. C. (SAW) 6-20, 6-33 
Wrightsville Dam, Vt. (NAN) 2-47 
Wynoochee Lake, Wash. (NPS) 38-11, 38-18, 38-23 
Y 
Yacona River, Miss. (MR&T) 42-52 
Yadkin River, N. C. (SAN) 7-7, 7-15, 7-16 
Yakima River at Ellensburg, Wash. (NPS) 38-28 
Yakima River, Wash. (NPS) 38-11 
Yakima River, West Richland, Wash. (NPW) 39-18 
Yalobusha River, Miss. (LMK) (MlR&T) 12-11, 42-52 
Yamhill River and Williamette River from above Portland, 
Oreg. (NPP) 37-12, 37-33, 37-41 
Yankton Sacred Heart Hospital, Emergency Bank 
Stabilization, S. Dak. (MRO) 20-9, 21-15 
Yaquina Bay and Harbor, Oreg. (NPP) 37-14, 37-34, 37-42 
Yaquina River, Oreg. (NPP) 37-46, 37-47 
Yatesville Lake, Ky. (ORH) 25-18, 25-22 
Yazoo Basin Backwater, Miss. (MR&T) 42-2, 42-10, 42-18, 42- 
47, 42-52, 42-58 42-58 
Yazoo Basin Headwater, Miss. (MR&T) 42-47, 42-52 
Yazoo Basin, Miss. (MR&T) 42-1, 42-2, 42-9, 42-18, 42-29, 
42-52, 42-55, 42-58, 42-57 
Yazoo City and Belzoni Protection Works, Miss. (MR&T) 42- 
9, 42-52, 42-57 
Yazoo River, Miss. (LMK) 12-2, 12-8, 12-9 
Yazoo River Basin Levees (MR&T) 42-47, 42-50 
Yellow Jacket Creek, Hogansville, Ga. (SAM) 10-41 
Yellowstone River, Mont. (MRO) 21-20 
Yellowstone River, W. Glendire, Mont. (MRO) 21-23 
Yonkers, N.Y. (NAN) 2-29, 2-35, 2-41 
York, Codorus Creek, Pa. (NAB) 4-22, 4-29, 4-35 
York Harbor, Maine (NED) 1-18, 1.49, 1-60 
York River, Va. (NAO) 5-26, 5-28 
York Spit Channel, Va. (NAO) 5-4, 5-22 
Youghiogheny River, Pa. and Md. (ORP) 26-27 
Youghiogheny River Lake, Pa. and Md. (ORP) 26-17, 26-21, 
26-29 
Yqungs River and Youngs Bay, Oreg. (NPP) 37-15, 37-34, 37- 
42, 37-46 
Youngs River Dikes, Oreg. (NPP) 37-54 
Youngstown, Ohio (ORP) 26-17, 26-21, 26-30 
Yuba River, Calif., Treatment of Debris Situationrestraining 
Barriers, (CDC) 44-2, 44-5 
Z 
Zanesville, Ohio (ORH) 25-26, 25-32 
Zintel Canyon Dam, Wash. (NPW) 39-5, 39-12, 39-15 
Zippel Bay Harbor, Minn. (NCS) 27-31 
Zumbro River, Minn. (NCS) 27-21, 27-26 
I-40

" !! 11ii 
'I t 
. 
'II 
I 'i 
'I' 
'II 
)I 1 
,I 
,1 '
~I 
1II 
, 
. +i 
1p2u1I 
i' 
,J

